﻿Fiscal Year 1983
A' tha.. of ChefEgneso 
* aa CivilWork Actiitie a f
* A

FY 1983 STATISTICAL HIGHLIGHTS 
ITEM 
APPROPRIATIONS' ($ Millions) 
New Work' 
Navigation .................................... 
Flood ControlT otal. ............................ 
Flood Control 
Mississippi River and Tributaries' ............... 
Multipurpose, including power .................... 
Beach Erosion Control .......................... 
Total New W ork ............................... 
Other W ork' .................................. 
T otal . .. . . . . . . . . .. .. . . . . . . . . . . . . . . .. . .. . . . . 
NAVIGATION (Calendar Year)* 
Ton-Miles of Commerce (Thousands) 
Foreign, Coastal Ports .......................... 
Foreign, Great Lakes Ports ....................... 
Domestic, Coastal (Intraterritory, not compiled)...... 
Domestic, Great Lakes .......................... 
Dom estic, Inland ............................... 
Dom estic, Local ................................ 
T O T A L ..................................... 
Tons of Commerce (Millions) 
Foreign CoastalP orts. .......................... 
Foreign Great Lakes Ports ....................... 
Domestic, Coastal and Intraterritory ............... 
Domestic, Great Lakes .......................... 
Dom estic, Inland ............................... 
Dom estic, Local ................................ 
TOTAL ................. ......... .......... 
FLOOD DAMAGES PREVENTED ($ Billions) ......... 
POWER 
Installed (Cumulative in millions of kw) .............. 
Generated (Billions of kwh) ........................ 
RESERVOIR STORAGE (Millions of acre-feet) 
A ll Purposes .................................... 
Flood Control (Maximum) ......................... 
Water Supply ...... :............................ 
Irrigation ...................................... 
PUBLIC ATTENDANCE AT RESERVOIRS 
(Millions of visitor days, calendar years) .............. 
1983 1983 1981 1980 1979 1978 1977 1976 1975 1974 
577 552 607 485 395 357 
882 774 772 873 802 895 
261 358 221 193 
859 1,004 580 650 
(291) (177) (145) (211) (158) (188) (173)' (158) (122) (212) 
221 247 275 538 358 155 464 479 287 288 
5 7 12 9 12 12 16 10 3 3 
1,685 1,580 1,666 1,905 1,567 1,719 1,600 1,851 1,098 1,134 
1,734 1,417 1,331 1,296 1,223 1,070 887 992 659 636 
3,419 2,997' 2,997 3,201 2,790 2,789 2,487 2,843 1,757 1,770 
51,262.7 58,929.2 60,569.8 59,940.5 58,925.6 58,925.1 50,979.6 43,521.7 44,019.1 
27,165.5 35,294.0 33,679.6 43,146.4 42,108.8 37,734.3 34,347.9 29,944.8 26,800.0 
632,707.1 634,765.3 631,149.2 532,290.2 540,373.2 343,536.6 322,932.3 315,834.9 322,802.2 
35,623.3 62,148.4 61,749.1 77,971.9 76,284.0 52,416.9 70,684.2 68,516.8 78,880.4 
217,026.7 231,184.1 227,343.0 217,090.2 209,266.2 201,784.2 197,072.8 180,399.2 183,202.6 
1,111.7 1,315.6 1,596.4 1,710.2 1,339.8 1,262.3 1,164.2 1,222.3 1,460.1 
964,897.0 1,023,636.5 1,016,085.1 931,846.4 928,297.6 692,527.4 477,181.0 639,450.7 656,164.3 
769.2 823.9 860.8 919.7 875.5 866.1 790.3 691.8 712,6 
50.4 62.3 60.6 73.8 70.6 69.2 65.7 56.9 51.5 
313.9 322.0 333.2 308.7 308.6 251.7 239.2 234.8 237.4 
72.1 115.4 115.2 143.6 142.7 109.1 132.1 129.3 146.1 
495.5 520.7 535.0 535.0 534.5 528.7 524.0 53.9 511.0 
75.6 93.2 94.2 93.1 89.5 83.4 83.7 78.3 88.2 
1,776.7 1,938.4 1,999.0 2,073.9 2,021.4 1,908.2 1,832.1 1,692.2 1,742.7 
23.2 4.3 1.2 7.3 19.4 6.3 2.6 1.7 15.9 13.0' 
19.7' 19.7' 19.2' 19.0' 19.0' 17.9 16.4 16.0 14.9 14.4 
88.2 75.8 77.3 77.8 81.2 83.6 64.0 108.0 82.9 76.8 
270.6 269.0 268.5 263.3 263.3 262.9 252.0 250.6 248.3 244.6 
123.0 123.0 122.7 120.4 120.4 120.1 104.0 102.9 101.0 99.2 
9.2 9.2 9.1 8.9 7.8 7.7 7.6 7.3 7.2 6.8 
7.8 7.8 7.8 7.8 7.8 7.8 7.8 7.8 7.8 7.8 
470 480 469 457 449 439 424 391 376 352 
'FY 1976 includes 1976T (Transition Quarter) figures cover period from July 1, 1975 through 'Operation and maintenance surveys, administration and misc. programs and activities. 
September 30, 1976. FY 83 funds provided under continuing resolution authority of PL 97-377 '$102 million deferred in FY 82. 
and the Productive Employment Appropriations Act of 1983 (PL 98-8). 'Includes New Melones and Snettisham, built by the Corps and operated by others. 
'Advance engineering and design, and construction. (Including major rehabilitation projects.) 
Savings and slippage applied to projects. *For further information on waterborne commerce, see Waterborne Commerce of the United 
'Included in Floor Control. States, published annually. It may be obtained by writing the District Engineer, U. S. Army 
'Revised figure. Engineer District, new Orleans, P.O. Box 60267, New Orleans, Louisiana 70160.

CONTENTS NECSA Tealet LI y 
Page 
NEW ENGLAND DIVISION ............................................................... 1-1 
NORTH ATLANTIC DIVISION: 
New York, NY, District ............. ................................................... 2-1 
Philadelphia, PA, District .................................................................. 3-1 
Baltimore, MD, District ............................................................. .... 4-1 
Norfolk, VA, District ................................................................ ... 5-1 
SOUTH ATLANTIC DIVISION: 
Wilmington, NC, District .............................................................. 6-1 
Charleston, SC, District ................................................................ 7-1 
Savannah, GA, District .............................. ... ........................... 8-1 
Jacksonville, FL, District ........ ................... .............................. 9-1 
Mobile, AL, District ................................................................. 10-1 
LOWER MISSISSIPPI VALLEY DIVISION: 
New Orleans, LA, District ................................................................. 11-1 
Vicksburg, MS, District ........................................................ 12-1 
Memphis, TN, District ..................................................................... 13-1 
St. Louis, MO, District ..................................................................... 14-1 
SOUTHWESTERN DIVISION: 
Galveston, TX, District ....................................................................................... 15-1 
Fort Worth, TX, District ..................................... .............................. 16-1 
Albuquerque, NM, District ................................................................. 17-1 
Little Rock, AR, District .............................................................. 18-1 
Tulsa, OK, District .................................................................. 19-1 
MISSOURI RIVER DIVISION: 
Kansas City, MO, District ................................................................. 20-1 
Omaha, NE, District ................................................................. ... 21-1 
OHIO RIVER DIVISION: 
Ohio River ......................................................... ....... ............ 22-1 
Nashville, TN, District .................................................................... 23-1 
Louisville, KY, District ................................................................... 24-1 
Huntington, WV, District ...... .... .. ................................................ 25-1 
Pittsburg, PA, District ..................... ........................................... 26-1 
NORTH CENTRAL DIVISION: 
St. Paul, M N, District ..................................................................... 27-1 
Rock Island, IL,District................................................................... 28-1 
Mississippi River between Missouri River and Minneapolis, MN ................................... 29-1 
Chicago, IL, District...................................................................... 30-1 
Detroit, MI, District...................................................................... 31-1 
Buffalo, NY, District ..................................................................... 32-1 
SOUTH PACIFIC DIVISION: 
Los Angeles, CA, District ................................................................. 33-1 
San Francisco, CA, District ................................................................ 34-1 
Sacramento, CA, District.................................................................. 35-1 
PACIFIC OCEAN DIVISION: ............................................................. 36-1 
NORTH PACIFIC DIVISION: 
Portland, OR, District .................................................................... 37-1 
Seattle, W A, District ..................................................................... 38-1 
Walla W alla, W A, District.................................................................. 39-1 
A laska District........................................................................... 40-1 
Board of Engineers for Rivers and Harbors ..................................................... 41-1 
Mississippi River Commission ............................................................... 42-1 
Natural Disaster Preparedness, Response & Recovery Activities .................................... 43-1 
California Debris Commission ................................................................ 44-1

Waterways Experiment Station.............................................................. 45-1 
Permanent InternationaAssociation of Navigation Congresses..................................... 46-1 
Investigations of Projects Under Federal Power Act.............................................. 47-1 
Regulatory Sunken Vessel Removal and National Emergency Preparedness........................... 48-1 
International Boundary Waters Boards ....................................................... 49-1 
Construction Engineering Research Laboratory................................................. 50-1 
Engineer Topographic Laboratories ........... ............................................... 51-1 
Cold Regions Research Engineering Laboratory................................................. 52-1 
Water Resources Support Center........... . ................................................. 53-1 
APPENDICES: 
Flood Control Reservoirs Operable September 30,1982 ......................................... A-1 
Flood Control Projects Under Construction During Fiscal Year 1982 .............................. B-1 
Navigation Locks and Dams Operable September 30,1982 ...................................... C-1 
Navigation Projects Under Construction September 30,1982 .................................... D-1 
Multipurpose Projects Including Power In Operation September 30,1982............................ E-1 
Multipurpose Projects Including Power Under Construction September 30, 1982 ...................... F-1 
Flood Damages Prevented (By Region and by District) During Fiscal Year 1982 ...................... G-1 
IN D E X ......... ..............................................................................

NEW ENGLAND DIVISION* 
The New England Division, an operating division with 
both district and division functions, comprises all of New 
England except western Vermont and small portions of 
Massachusetts and Connecticut along their western 
boundaries, and includes small portions of southeastern 
New York, all embraced in the drainage basins tributary 
to Long Island Sound and the Atlantic Ocean east of the 
New York-Connecticut State line. It also includes Fishers 
Island, N.Y. 
IMPROVEMENTS 
Navigation 
1. Aquatic Plant Control............. 
2. Black Rock Harbor, CT ............. 
3. Boston Harbor, MA................ 
4. Bridgeport Harbor, CT ............. 
5. Bristol Harbor, RI............... 
6. Buttermilk Bay Channel, MA ........ 
7. Cape Cod Canal, MA ............... 
8. Chatham (Stage) Harbor, MA ........ 
9. Clinton Harbor, CT ................ 
10. Connecticut River Below 
Hartford, CT .................... 
11. Corea Harbor, Gouldsboro, ME ....... 
12. Fall River Harbor, MA ............ 
13. Fore River, Braintree and 
Weymouth, MA.................. 
14. Gloucester Harbor and 
Annisquam River, MA .............. 
15. Great Salt Pond, Block Island, RI ..... 
16. Green Harbor, MA................ 
17. Guilford Harbor, CT .............. 
18. Harbor of Refuge, Block 
Island, RI ....................... 
19. Harbor of Refuge and Point Judith 
Pond, Point Judith, RI ............. 
20. Housatonic River, CT .............. 
21. Island End River, Chelsea, MA ....... 
22. Kennebunk River, ME.............. 
23. Mystic River, MA ................. 
24. New Haven Harbor, CT............. 
25. Newburyport Harbor, MA ........... 
26. Norwalk Harbor, CT ............... 
27. Patchogue River, CT ............... 
28. Portsmouth Harbor and 
Piscataqua River, ME and NH ....... 
29. Saco River, ME ................... 
30. Sakonnet Harbor, RI............... 
31. Sesuit Harbor, MA ................ 
Page 
1-3 
1-3 
1-3 
1-4 
1-4 
1-4 
1-4 
1-5 
1-5 
1-5 
1-6 
1-6 
1-7 
1-7 
1-7 
1-8 
1-8 
1-8 
1-8 
1-9 
1-9 
1-9 
1-10 
1-10 
1-10 
1-11 
1-11 
1-12 
1-12 
1-12 
1-12 
56. Stonington Harbor, ME............. 
32. Reconnaissance and condition 
surveys ......................... 
33. Other authorized navigation 
projects ......................... 
34. Navigation activities pursuant to 
Section 107, Public Law 86-64513 
(Preauthorization) ................. 
35. Authorized bridge alteration ......... 
Beach Erosion Control 
36. Cliff Walk, Newport, RI............. 
37. Sherwood Island State 
Park, Westport, CT............... 
38. Willard Beach, South 
Portland, ME..................... 
39. Inspection of completed beach 
erosion control projects ............. 
40. Other autorized beach erosion 
control projects .................. 
41. Beach erosion control activities 
pursuant to Section 103, Public 
Law 87-874 (Preauthorization) ........ 
Flood Control 
42. Blackstone River Basin, MA and RI ... 
42A. Pawtuxet River, Warwick, RI ........ 
42B. West Hill Dam, MA............... 
42C. Charles River (Natural Valley 
Storage Areas), MA................ 
43. Connecticut River Basin, VT 
NH, MAandCT ................. 
43A. Ball Mountain Lake, VT ............ 
43B. Barre Falls Dam, MA .............. 
43C. Birch Hill Dam, MA ............... 
43D. Colebrook River Lake, CT ........... 
43E. Conant Brook Dam, MA ........... 
43F. Knightville Dam, MA ............. 
1-1 
Page 
1-27 
1-13 
1-13 
1-13 
1-13 
1-13 
1-13 
1-14 
1-14 
1-14 
1-14 
1-14 
1-14 
1-15 
1-15 
1-15 
1-16 
1-16 
1-16 
1-16 
1-17 
1-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
43G. Littleville Lake, MA ............... 
43H. North Hartland Lake, VT ........... 
43I. North Springfield Lake, VT 
43J. Otter Brook Lake, NH .............. 
43K. Park River, Hartford, CT............ 
43L. Salmon River, Colchester, CT ........ 
43M. Saxtons River, Rockingham, VT ...... 
43N. Surry Mountain Lake, NH ........... 
430. Townshend Lake, VT ............... 
43P. Tully Lake, MA.................. 
43Q. Union Village Dam, VT ............. 
43R. West Branch Westfield 
River, Huntington, MA ............. 
43S. West Springfield, Connecticut 
River Basin, MA .................. 
44. Housatonic River Basin, CT and MA .. 
44A. Black Rock Lake, CT ............... 
44B. Hancock Brook Lake CT ............ 
44C. Hop Brook Lake, CT.............. 
44D. Housatonic River, Pittsfield, MA ..... 
44E. Northfield Brook Lake, CT .......... 
44F. Squantz Pond, New Fairfield, CT ..... 
44G. Thomaston Dam, CT ............... 
45. Island Avenue, Quincy, MA ......... 
46. Islesboro (The Narrows), ME ........ 
47. Johnson Bay, Lubec, ME ............ 
48. Port 5 Facility, Bridgeport, CT ....... 
49. Trumbull Lake, CT ................ 
50. Merrimack River Basin, NH and MA .. 
50A. Blackwater Dam, NH .............. 
50B. Edward MacDowell Lake, NH ........ 
50C. Franklin Falls Dam, NH ............ 
50D. Hopkinton-Everett Lakes, NH ....... 
51. New Bedford, Fairhaven, and 
Acushnet, MA .................... 
52. New London, CT ................. 
53. Saint John River Basin, ME ......... 
53A. Dickey-Lincoln School Lakes, ME ..... 
54. Bagaduce River, Castine, ME ........ 
55. Sebasticook River, Hartland, ME ..... 
57. Stamford, CT ..................... 
58. Thames River Basin, CT, RI 
andM A ......................... 
58A. Buffumville Lake, MA .............. 
58B. East Brimfield LaKe, MA ........... 
58C. Hodges Village Dam, MA ........... 
Page 
1-17 
.1-17 
1-17 
1-17 
1-18 
1-18 
1-18 
1-19 
1-19 
1-19 
1-19 
1-20 
1-20 
1-20 
1-21 
1-21 
1-21 
1-21 
1-21 
1-22 
1-22 
1-22 
1-22 
1-23 
1-23 
1-23 
1-24 
1-24 
1-24 
1-24 
1-24 
1-25 
1-25 
1-25 
1-26 
1-26 
1-26 
1-27 
1-27 
1-28 
1-28 
1-28 
58D. Mansfield Hollow Lake, CT ......... 
58E. West Thompson Lake, CT ........... 
58F. Westville Lake, MA ................ 
59. Inspection of completed flood 
control projects ................... 
60. Flood control reservoir 
operations ....................... 
61. Hurricane barrier operations ......... 
62. Other authorized flood 
control projects ................... 
63. Flood control work under 
special authorization ............... 
64. Deauthorized Projects .............. 
General Investigations 
65. 
66. 
67. 
Tables 
Surveys ......................... 
Collection and Study of Basic Data. .... 
Advance Engineering and Design ..... 
Table 1-A Cost & Financial 
Statem ent ................... 
Table 1-B Authorizing Legislation .......... 
Table 1-C Other Authorized 
Navigation Projects ............. 
Table 1-D Other Authorized Beach 
Erosion Control Projects ......... 
Table 1-E Other Authorized 
Flood Control Projects ........... 
Table 1-F Multiple Puropse Projects 
Including Power ................ 
Table 1-G Deauthorized Projects ........... 
Table 1-H Navigation Activities 
Pursuant to Sec. 107 . ........... . 
Table 1-I Beach Erosion Activities 
Pursuant to Sec. 103 ........... 
Table 1-J Flood Control Activities 
Pursuant to Sec. 205............ 
Table 1-K Blackstone River Basin .......... 
Table 1-L Connecticut River Basin ......... 
Tablel-M Housatonic River Basin .......... 
Table 1-N Merrimack River Basin ........... 
Table 1-0 Thames River Basin............ 
Table 1-P Boston Harbor, MA ............. 
Table 1-Q Reconnaissance and 
Condition Surveys .............. 
1-2 
Page 
1-28 
1-28 
1-29 
1-29 
1-29 
1-30 
1-30 
1-30 
1-30 
1-30 
1-30 
1-31 
1-32 
1-41 
1-50 
1-54 
1-55 
1-56 
1-57 
1-58 
1-58 
1-59 
1-59 
1-60 
1-61 
1-63 
1-64 
1-64 
1-65

NEW ENGLAND DIVISION 
Navigation 
1. AQUATIC PLANT CONTROL 
Location. The program is conducted in all navigable 
waters, tributary streams, connecting channels and 
associated waters under the New England Division 
jurisdiction. 
Existing project. The purpose of the program is to 
eradicate or control aquatic plants that are causing or 
have the potential to cause major economic problems in 
the above waterways. The plant control is done in the 
interest of navigation, flood control, drainage, agriculture, 
fish and wildlife conservation, public health and research. 
The program is administered by the Chief of Engineers, 
under the direction of the Secretary of the Army, and in 
cooperation with other Federal and State agencies. (See 
Table 1-B at end of chapter for Acts authorizing existing 
program). 
Local cooperation. Local interests must contribute 30 
percent of the cost of controlling the aquatic plants, and in 
addition must hold the United States free from damages 
that may occur from control operations. 
Operations during fiscal year. The office received many 
requests from communities to help with their aquatic 
plant problems. Field surveys and meetings with local 
people were held to determine the extent and cause of the 
problems. In most cases, the problems resulted from excess 
nutrients washing into the waters from adjacent lands. 
This problem does not meet the criteria for Corps 
participation. 
2. BLACK ROCK HARBOR, CT 
Location. On north shore of Long Island, about 51 miles 
east of New York City. (See National Ocean Survey Chart 
12369). 
Existing project. Black Rock Harbor and Cedar Creek 
Channel, 18 feet deep and 100 to 200 feet wide from the 18 
foot contour in Black Rock Harbor to the heads of both 
branches of Cedar Creek, about 2.4 miles. (See Table 1-B 
at end of chapter for Act authorizing existing project). 
Local cooperation. Fully complied with for completed 
portion of project; for Black Rock Harbor breakwaters 
and Burr and Cedar Creek anchorage there is no reasonable 
prospect that required cooperation will be forthcoming 
from local interests. For further details see Annual Report 
for 1968. 
Terminal facilities. There are 6 waterfront facilities 
serving Black Rock Harbor. Facilities are adequate for 
existing commerce. 
Operations during fiscal year. A dredging contract was 
awarded in December 1982 and completed in May 1983. A 
total of 210,000 c.y. of material were removed at a contract 
cost of $1,017,945. Hired labor costs of $171,855 were 
incurred for surveys, preparation of plans and specifications, 
and supervision and inspection. $126,099 was spent for 
contract work under disposal area monitoring. A contract 
was awarded in September 1983 for construction of an 
upland/wetland disposal site as part of the Field Verification 
Program; the contract amount was $215,000. At the end 
of the FY work had not begun. 
3. BOSTON HARBOR, MA 
Location. Harbor includes all expanse of tidewater 
lying within a line from Point Allerton to Point Shirley 
and extending from that line westward to mainland. This 
comprises an area of about 47 square miles, exclusive of 
the islands. (See National Ocean Survey Charts 13270 and 
13272). 
Previous project. For details see Annual Reports for 
1915, 1917, 1938. 
Existing project. The existing project for Boston Harbor, 
adopted in 1825 and supplemented by enactments through 
1958, provides for the improvement of the harbor proper 
and its approaches. Fort Point channel, Reserved Channel, 
Chelsea River and Weir River. For a more detailed 
description see page 3 of Annual Report for 1974. (See 
Table 1-B at end of chapter for Acts authorizing existing 
projects). Existing project was completed in May 1966 
with the construction of Chelsea River 35-foot channel 
and maneuvering basin. That portion of Fort Point Channel 
from northeasterly side of Summer Street Highway Bridge 
to the easterly side of Dorchester Highway Bridge has 
been abandoned pursuant to P.L. 91-624 dated 31 December 
1970. Remaining area of the authorized channel from the 
entrance to the northeasterly side of the Summer Street 
Bridge has not been abandoned. (See Table 1-P at end of 
chapter for total Federal cost of existing project to 
September 1983). 
Local cooperation. Fully complied with. 
Terminal facilities. There are 156 wharves and piers in 
harbor, not including Mystic, Weymouth, Fore, and Town 
Rivers, which are reported elsewhere. Of the terminals, 28 
are publicly owned, 13 are open to public use, 73 have 
mechanical-handling facilities, and 70 have railroad 
connections. Facilities are considered adequate for existing 
commerce. For a full description of channel facilities in 
Chelsea River refer to House Document 350, 87th Congress, 
2nd session (See Port Series No. 3, Part 2, Port of Boston, 
MA dated 1967). 
Operations during fiscal year. Maintenance. Dredging 
under a contract awarded in FY 1982 was completed in 
March 1983. A total of 340,000 c.y. was removed from 
Presidents Road Anchorage at a contract cost of $1,030,000. 
Hired labor costs of $118,550 were incurred for surveys 
and supervision and inspection. $10,000 was spent for 
disposal area monitoring work. Work under the contract 
for maintenance dredging of Chelsea River awarded last 
fiscal year was completed in March 1983. A total of 126,586 
cubic yards of material were dredged at a total contract 
cost of $984,785. Hired labor costs of $66,948 were incurred 
during the year for surveys, preparation of plans and 
specifications, and supervision and inspection. 
1-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
4. BRIDGEPORT HARBOR, CT. 
Location. On north shore of Long Island Sound, about 51 
miles east of New York City. (See National Ocean Survey 
Chart 12369). 
Previous projects. For details, see page 1756 of Annual 
Report for 1915 and page 133 of Annual Report for 1938. 
Existing project. For description of completed improvement 
see Annual Report for 1968. (See Table 1-B at end of 
chapter for Acts authorizing existing project). 
Local cooperation. Fully complied with for completed 
portion of project; for Black Rock Harbor breakwaters and 
Burr and Cedar Creek anchorage there is no reasonable 
prospect that required cooperation will be forthcoming 
from local interests. For further details, see Annual Report 
for 1968. 
Terminal facilities. There are 35 waterfront facilities 
serving port of Bridgeport, all of which are used or in usable 
condition. Three wharves are owned by city of Bridgeport 
and three others may be used by public upon agreement 
with the owners or operators. (See Port and Terminal Facilities 
of Southern New England No. 4, revised in 1952). 
Facilities are adequate for existing commerce. 
Operations during fiscal year. Maintenance. A dredging 
contract was awarded in December 1982. A total of 22,963 
cubic yards of material was dredged to deepen a portion of 
the 25' anchorage to 35' at mean low water at a cost of 
$71,185. Hired labor costs of $33,244 were incurred for surveys, 
plans and specifications, supervision and inspection. 
5. BRISTOL HARBOR, BRISTOL, RI 
Location. Bristol Harbor is on the east side of upper 
Narragansett Bay, in Bristol County, about 13 miles 
southeast of Providence, Rhode Island. (See National 
Ocean Survey Charts 13224, 13221 and 13218). 
Existing project. The project provides for an offshore 
breakwater 1,600 feet long located about 400 feet west of 
the Coast Guard pier and extending generally in a 
northwesterly direction. Construction has not begun. 
Revised plan developed during advance engineering and 
design will now recommend an A-frame type breakwater 
1,250 feet long. Total estimated cost (Sept. 1983) of the 
modified plan is $3,300,000 of which $1,650,000 is non- 
Federal cost. (See Table 1-B at end of chapter for Acts 
authorizing existing project). 
Local cooperation. Local interests are required to provide, 
without cost to the United States, all lands, easements 
and rights-of-way necessary for construction; hold and 
save the United States free from damages due to 
construction and subsequent maintenance of the project 
and provide a cash contribution currently estimated at 50 
percent of project cost based on project benefits. 
Terminal facilties. The developed waterfront of Bristol 
Harbor is concentrated along a half-mile stretch of east 
shore of harbor. In this section, there are six privatelyowned 
landings, two owned by the Town, one by the 
State, and one by the Federal government. All private 
landings are of granite construction and have truck access. 
Two have gasoline and one has diesel oil service; and are 
used primarily for landing shellfish. Town and State piers 
are open to public, and include facilities for about 50 small 
boats and finger piers for larger craft. 
Operations during fiscal year. New work. Advance 
engineering and design was continued. 
6. BUTTERMILK BAY CHANNEL, MA 
Location. Buzzards Bay, MA, is at the southern end of 
Cape Cod Canal. It is connected with Buttermilk Bay to 
the north by a natural channel branching from Cape Cod 
Canal and extending northerly past Butler Cove for a 
distance of 2 miles into Buttermilk Bay. (See National 
Ocean Survey Chart 13236). 
Existing project. Provides for a channel 100 feet wide 
and 7 feet deep at mean low water through the sand bar 
across the channel, to just above Taylor's Point, then a 
2,500 foot extension 6 feet deep and 80 feet wide to the site 
of a public marina to be built by the Town of Bourne and 
the Commonwealth of Massachusetts. 
Project except for channel extension was completed in 
1953. Construction of extension is underway. (See Table 
1-B at end of chapter for Acts authorizing existing project). 
Local cooperation. Fully complied with for completed 
work. For the channel extension, local interests are required 
to contribute in cash 50 percent of the first cost of 
construction, an amount currently estimated at $60,500. 
Contribution has been received. 
Terminal facilities. There are no wharves bordering on 
the channel. The only facilities in Buttermilk Bay are 
small private piers for shallow-draft boats. 
Operations during fiscal year. New work and maintenance. 
Plans and specifications were prepared and 
contract awarded in September 1983 for both improvement 
dredging (channel extension) and maintenance dredging. 
Hired labor costs were $14,363. 
7. CAPE COD CANAL, MA 
Location. This waterway is a sea level Canal; extending 
from head of Buzzards Bay, MA, to a point on Cape Cod 
Bay about 15 miles southeast of Plymouth Harbor, MA. 
In general direction Canal trends from Buzzards Bay 
easterly to Cape Cod Bay. (See National Ocean Survey 
Chart 13246). 
Existing Project. For description of existing project see 
Annual Report for 1975. (See Table 1-B at end of chapter 
for Acts authorizing existing project). Navigational 
improvements were completed in April 1963, with 
completion of East Boat Basin extension. Initial recreational 
development consists of public use facilities at various 
locations, which were completed in February 1965. Improvements 
to public use facilities at the East Boston Basin were 
completed in May 1974. Construction of public use facilities 
at Bourne Scenic Park were completed in May 1976. Canal is 
crossed by two high-level highway bridges and vertical-lift 
railroad bridge. Initial major rehabilitation of Bourne highway 
was completed in December 1965. Minor rehabilitation 
of stone breakwater was completed in October 1963. 
1-4

NEW ENGLAND DIVISION 
Local cooperation. Fully complied with. Local interests 
must also bear 50 percent of future recreational development 
in accordance with 1965 Federal Water Project Recreation 
Act. 
Terminal facilities. There are seven terminals on the 
Canal, of which three are privately owned. Four are used 
for receipt and freezing of fish and two are used for receipt 
and storage of oil. Seventh terminal is State pier, owned 
by Commonwealth of Massachusetts, and on north bank 
of Canal at Bourne Neck. Terminals are adequate for 
purposes for which they are used. 
Operations during fiscal year. Maintenance: Contracts 
awarded and contract costs were $487,608 to purchase 
microwave equipment to replace portions of the Electronic 
Traffic Control System; replace steel access doors on 
highway bridge abutments $6,499; and repair fender piles 
Sandwich Bulkhead $13,165. Painting contract for railroad 
bridge, awarded in FY 82 was completed in October 82; 
FY expenditures were $25,000. A $169,300 contract for 
replacement of public sanitary facilities was awarded in 
July with work to begin in September 1983 after peak 
tourist season. The following contracts for roofing repairs 
to Buzzards Bay Railroad Bridge $12,894; paving of the 
West Boat Basin pier $13,620; and sanitary disposal system 
Administration Area $9,960; were awarded late in fiscal 
year. No work was performed during FY83 on these 
contracts. Other costs by hired labor and contract were 
Railroad Bridge Tower and Signal System $146,904; 
Condition Surveys $72,622; operational costs for roads, 
bridges and project facilities $1,542,625; real estate 
activities $56,176; traffic control activities $1,357,097; 
administrative costs $171,967; engineering and design 
$60,516; contract specifications and drawings $60,715; 
contract supervision and inspection $20,581. Expenditures 
for replacement and upgrading of Electronic Traffic Control 
System under continuing contract awarded in September 
1982 were $1,021,737. 
Major rehabilitation. Major rehabilitation of the two 
highway bridges crossing the Canal is now completed. 
The rehabilitation consists of replacing the decks of both 
bridges, repair or replacement, where appropriate, of 
structural steel members and cleaning and painting 
superstructures of bridges. A contract for rehabilitation 
of the Bourne Bridge was completed in 1981. Another 
continuing contract for the Sagamore Bridge, was awarded 
in April 1981 and completed in December 1982. Fiscal 
Year 1983 expenditures were $521,000; total contract 
amount was $9,589,000. 
8. CHATHAM (STAGE) HARBOR,MA 
Location. At northeastern corner of Nantucket Sound, 
about 16 miles east of Hyannis Harbor, MA, and 66 miles 
south of Providence Harbor at northern extremity of Cape 
Cod. (See National Ocean Survey Chart 13237). 
Previous Project. For details see Annual Report for 
1942. 
Existing project. An entrance channel 10 feet deep and 
150 feet wide from Chatham Roads into upper harbor. (See 
Table 1-B at end of chapter for Acts authorizing existing 
project). Construction of existing project was initiated in 
September and completed in October 1957. By 1961, a 
break in barrier beach connecting Morris and Monomoy 
Islands caused Federal Channel to fill completely. Local 
interests dredged an emergency channel to obtain 8-foot 
depth in June 1962 and performed additional dredging in 
1963. Minimal maintenance dredging by the Federal Government 
in April and May 1964, provided access to inner 
harbor for 1964 boating season. A new 10-foot channel 
through Harding Beach to Morris Island was completed 
in July 1965. 
Local cooperation. Fully complied with. 
Terminal facilities. There are three commercial wharves 
on north side of inner harbor open to public use subject to 
owner's convenience. Facilities are adequate for existing 
commerce. 
Operations during fiscal year. Maintenance: Work for 
removal and disposal of a timber pile jetty was completed. 
Contract cost this year was $8,890 for a total contract cost 
of $23,890. Hired labor costs of $939 were incurred for 
supervision and inspection. 
9. CLINTON HARBOR, CT 
Location. On north shore of Long Island sound, about 
10 miles west of mouth of Connecticut River and about 20 
miles east of New Haven Harbor, CT. (See National Ocean 
Survey Charts 12374 and 12354). 
Previous Project. For details see page 640, Annual 
Report for 1894 and page 112, Annual Report for 1943. 
Existing project. A channel 8 feet deep at mean low water 
and 100 feet wide from Long Island Sound to upper end of 
wharves at Clinton, and anchorage area of same depth 
opposite and above wharves, 50 feet wide south of channel 
and extending 600 feet above end of channel, with widths 
of 150 to 250 feet, and for maintenance of a stone dike 
closing a breach in the sandy peninsula which separates 
the river from outer harbor. (See Table 1-B at end of 
chapter for Acts authorizing existing project). Project 
was completed in 1950. 
Local cooperation. Fully complied with. 
Terminal facilities. There are several small private 
wharves, some of which are open to public use. These 
facilities are adequate for existing commerce. 
Operations during fiscal year. Maintenance: Administrative 
closeout of maintenance dredging contract completed 
at the end of the prior fiscal year was accomplished. 
10. CONNECTICUT RIVER BELOW 
HARTFORD, CT 
Location. Has its source in Connecticut Lake in northern 
New Hampshire, flows southerly 380 miles and empties 
into Long Island Sound at Saybrook, CT, 14 miles west of 
New London. Hartford, now head of commercial navigation, 
is 52 statute miles, by channel, from mouth. (See National 
Ocean Survey Charts 12373 and 12377). 
Previous project. For details see Annual Reports for 
1915 and 1938. 
1-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Eightmile River, CT, elimination as separate project: 
Provides for a channel 8 feet deep 75 feet wide from deep 
water in Connecticut River to Hamburg and for turning 
basin of same depth, 150 feet wide, approximately 300 feet 
long at Hamburg. Project was adopted by River and 
Harbor Act of 1910. Costs and expenditures were $9,000 
all for new work. In accordance with River and Harbor 
Act of 1950, project for Connecticut River below Hartford 
was modified to include project for Eightmile River. 
Aforementioned Act also provided for an anchorage basin 
6 feet deep and about 6.5 acres in area in upper cove in 
Hamburg. A channel 15 feet deep and 150 feet wide for a 
distance of 52 miles upstream to Hartford; two riprap 
jetties at the mouth of the river; and dikes, training walls, 
revetments and other regulatory works along the river 
between Hartford and Gildersleeve Island. The project 
provides for small-boat improvements at Wethersfield 
Cove; Eightmile River; Essex, and North Cove, Old 
Saybrook. For a more detailed description of project see 
page 7 of Annual Report for 1974. (See Table 1-B at end of 
chapter for Acts authorizing existing project). Existing 
project was completed in September 1965 with the 
construction of channel and anchorage in North Cove, Old 
Saybrook, CT. For further details, see Annual Report for 
1974. 
Local cooperation. Fully complied with. 
Terminal facilities. Along both Connecticut and 
Eightmile Rivers there are two or three wharves at each 
river town, one or more in each town being open to public 
use. At Hartford and Middletown there is about one-half 
of wharf frontage along west bank of river. Facilities 
adequate for existing commerce. 
Operations during fiscal year. Maintenace: A dredging 
contract awarded in FY 1982 was completed. A final total 
of 100,000 c.y. of material was dredged at a total contract 
cost of $713, 627. Two additional maintenance contracts 
were awarded at the end of the fiscal year; one ($712,840) 
for dredging upriver bars and the other ($898,690) for 
dredging bars near the mouth. Hired labor costs of $195,622 
were incurred for an environmental assessment, surveys, 
plotting, preparation of plans and specs and supervision 
and inspection. Costs of $132,974 were incurred for range 
layout, drawings and specs., sampling and testing and 
$26,000 was spent on a short-nose sturgeon study (study 
was done by the National Marine Fisheries Service). 
11. COREA HARBOR, 
GOULDSBORO, ME 
Location. Corea Harbor is located within the village of 
Corea in the town of Gouldsboro, Hancock County, Maine. 
It is 130 miles northeast of Portland and 55 miles southeast 
of Bangor. (See National Survey Chart 13324). 
Existing project. Provides for an anchorage basin 8 feet 
deep, 600 feet long in an east and west direction and 400 
feet wide in a north and south direction. (See Table 1-B at 
end of chapter for Act authorizing existing project). 
Construction was completed in 1982. 
Local cooperation. Local interests are required to provide, 
maintain and operate without cost to the United 
States, an adequate public landing with provisions for the 
sale of motor fuel, lubricants and potable water open and 
available to the use of all on equal terms; provide without 
cost to the United States all necessary lands, easements 
and rights-of-way required for construction and subsequent 
maintenance of the project including suitable dredged 
material disposal areas with necessary retaining dikes, 
bulkheads and embankments therefor; hold and save the 
United States free from damages that may result from 
construction and maintenance of the project; accomplish 
without cost to the United States alterations and relocations 
as required in sewer, water supply, drainage and other 
utility facilities; establish regulations prohibiting the 
discharge of untreated sewage, garbage and other pollutants 
in the waters of the harbor users thereof, which regulations 
shall be in accordance with applicable laws or regulations 
of Federal, State and local authorities responsible for 
pollution prevention and control. 
Terminal facilities. There are 21 wharves, 15 of which 
are small and cannot be approached by vessels at low tide. 
The wharves are privately owned. Facilities are considered 
adequate for present commerce. 
Operations during fiscal year. New work: A contract, 
awarded in August 1982, for improvement dredging was 
completed in November 1982. The contract earnings were 
$470,002 and 36,810 cubic yards of material was removed. 
12. FALL RIVER HARBOR, MA 
Location. At mouth of Taunton River, on east side and 
at head of Mount Hope Bay, which empties into ocean 
through Narragansett Bay and Sakonnet River; it is about 
18 miles northerly from Newport Harbor. (See National 
Ocean Survey Chart No. 13221). 
Previous projects. For details see Annual Reports for 
1915 and 1938. 
Existing project. For description of existing project see 
Annual Report for 1978. Deepening to 35 feet was completed 
in March 1959. The authorized deepening to 40 feet has 
not yet begun. (See Table 1-B at end of chapter for Acts 
authorizing existing project). 
Local cooperation. Fully complied with for completed 
work. For terms of local cooperation pertinent to remaining 
work authorized by River and Harbor Act of 1968, see 
Annual Report for 1975. 
Terminal facilities. In upper harbor there are several 
deep-draft terminals, two of which are in Somerset and 
three in Fall River, four more deep-draft terminals are 
located along the Tiverton waterfront in Rhode Island. 
These are modern terminals used in connection with 
electrical generating stations; receipt, distribution and 
storage of oil and petroleum products; and a State Pier for 
handling general cargo, and a permanent berth for the 
battleship Massachusetts. 
There are six other wharves with berthing depth of less 
than 25 feet used for mooring recreational and training 
craft, receipt and storage of petroleum products, boat 
servicing and repairs. (See Port and Terminal Facilities of 
Southern New England, No. 4 Revised in 1976). 
1-6

NEW ENGLAND DIVISION 
Operations during fiscal year. New work: The lack of an 
acceptable disposal site for the materials to be dredged 
continued to delay implementation of deepening to 40 
feet. Extensive coordination continued throughout the 
year between local interests and local, regional and Federal 
officials concerning the identification and acceptance of a 
disposal site. 
13. FORE RIVER, BRAINTREE 
AND WEYMOUTH, MA 
Location. The Weymouth-Fore River is located approximately 
nine miles from downtown Boston. It flows into 
Hingham Bay which forms the southern portion of Boston 
Harbor. The river forms a portion of the boundary between 
the cities of Weymouth and Braintree. (See National Ocean 
Survey Chart 13270). 
Existing Project. Provides for a channel 6 feet deep 
with a width from 60 to 100 feet. The channel would begin 
at the Federal ship channel in Quincy and extend 8,000 
feet upstream to the Quincy Avenue Bridge. (See Table 
1-B at end of chapter for Act authorizing existing project). 
Construction was completed in July 1983. 
Local cooperation. Local interests would provide a cash 
contribution of 50 percent of the cost of construction; 
provide without cost to the United States all necessary 
lands, easements, and rights-of-way required for construction 
and subsequent maintenance of the project including 
suitable dredged material disposal areas with necessary 
retaining dikes, bulkheads, and embankments therefor; 
hold and save the United States free from damages that 
may result from construction and maintenance of the 
project; provide and maintain berths, floats, piers, and 
similar marina and mooring facilities as needed for transient 
and local vessels as well as necessary access roads, parking 
areas, and other needed public use shore facilities open 
and available to all on equal terms; establish regulations 
prohibiting the discharge of untreated sewage, garbage 
and other pollutants in the waters of the harbor users 
thereof, which regulations shall be in accordance with 
applicable laws or pollution prevention and control. 
Operations during fiscal year. New work; All work on 
improvement dredging contract awarded in FY 1982 was 
completed in July 1982 except for one reach which was 
completed in July 1983. Final contract earnings were 
$217,800 and a total of 30,000 cubic yards of material were 
removed. 
14. GLOUCESTER HARBOR AND 
ANNNISQUAM RIVER, MA 
Location. Gloucester Harbor is at southern extremity 
of Cape Ann, about 23 miles northeast by water from 
Boston Harbor. Annisquam River is a narrow tidal 
waterway extending across base of Cape Ann from 
Gloucester Harbor on south side to Ipswich Bay on 
northside, a distance of approximately 4 miles. A reach of 
this water way, at Gloucester Harbor end, for a length of 
about 1,800 feet, is known as Blynman Canal. (See National 
Ocean Survey Chart 13279). 
Previous projects. For details see Annual Reports for 
1915, and 1937. 
Existing Project. Provides for a breakwater at the Outer 
Harbor entrance; the removal of eight ledge areas in the 
northern half of the harbor; a 20-foot entrance channel into 
the Inner Harbor, separating into two 20-foot access 
channels along the side of the State Fish Pier; a 16-foot 
anchorage at the junction of the two 20-foot access channels; 
in an 18-foot entrance channel into Harbor Cove, with a 
15-foot anchorage outside Harbor Cove and a 10-foot access 
channel in Harbor Cove; a 16-foot entrance channel into 
Smith Cove; and removal of a rock shoal in the entrance 
channel to Harbor Cove to a depth of 24 feet. Annisquam 
River provides for a channel 8 feet deep from Gloucester 
Harbor to Ipswich Bay, and an anchorage about 17 acres 
in extent and 8 feet deep at entrance of Lobster Cove. For 
a more detailed description of existing project see Annual 
Report for 1973. (See Table 1-B at end of chapter for Acts 
authorizing existing project). Project was completed in 
July 1965. 
Local cooperation. Fully complied with. 
Terminal Facilities. In Gloucester Harbor, 75 piers and 
wharves, 90 percent of which are used in some connection 
with the fishing industry. Of these two are owned by the 
city. Fish pier is owned by Massachusetts and leased to 
city. All others are privately owned, and not available to 
the public. There are also two commercial wharves on east 
bank of Annisquam River. There are no railroad sidings 
available. Facilities are adequate for existing commerce. 
Operations during fiscal year. Maintenance: Preparation 
of plans and specifications was initiated in anticipation of 
maintenance dredging. 
15. GREAT SALT POND, BLOCK 
ISLAND, RI 
Location. On west shore of Block Island, about 11 miles 
southwest by south from Point Judith Harbor, RI, and 18 
miles southeasterly from Stonington Harbor, CT. (See 
National Ocean Survey Chart 13217). 
Exisiting project. Provides for a channel 18 feet deep 
from ocean to pond 300 feet wide with a central depth of 25 
feet for a width of 150 feet; a riprap jetty at the entrance 
on a southerly side extending 350 feet beyond 18-foot 
contour (actual length 1,691 feet, including 837 feet built 
by State); stone revetment and sand fences to protect 
banks through original beach. Portion of project for 
widening and deepening channel, construction of north 
jetty, and dredging inner harbor channel and basin is 
considered inactive. Cost of this portion of project last 
revised in 1954 was estimated to be $452,000, exclusive of 
$8,000 to be contributed by local interests. (See Table 1-B 
at end of chapter for Acts authorizing existing project). 
South jetty was completed in 1905. 
Local cooperation. Not required on active portion of 
project. 
Terminal facilities. Consist of a wharf with about 600 
feet of publicly available berthage and several privately 
owned and operated small wharves and piers. Facilities 
are considered adequate for existing commerce. 
1-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Operations during fiscal year. Maintenance: Hired labor 
costs of $1,967 were incurred for completing work on an 
after dredge survey for dredging accomplished in FY 
1982. 
16. GREEN HARBOR, MA 
Location. On west side of Massachusetts Bay within 
the town of Marshfield about 30 miles southeast of Boston 
and 9 miles north of Plymouth Harbor. (See National 
Ocean Survey Chart 13253). 
Existing Project. Provides for channel 6 feet deep (8 
feet at entrance), 100 feet wide extending about 4,000 feet 
from deep water to head of navigation with small turning 
basin at upstream limit; 5-acre anchorage near Town Pier, 
6 feet deep; sealing, rebuilding in part, and a 200 feet 
extension of existing west jetty at elevation + 12, with 
dike to beach berm at elevation +14 feet, and raising east 
jetty to elevation + 14. (See Table 1-B at end of chapter for 
Act authorizing existing project). Construction was 
completed in October 1969. 
Local cooperation. Fully complied with. 
Terminal Facilities. Major terminal facility is Town 
Pier in village of Brant Rock. Facility is a bulkheaded, 
earth-filled landing and parking area about 290 feet wide, 
extending 210 feet into harbor. A marina service is south 
of Town Pier; and a facility for recreational craft has been 
developed on south side of harbor near head of navigation. 
Operations during fiscal year. Maintenance: A contract 
for maintenance dredging was awarded and completed. 
45,384 c.y. of material was removed at a cost of $164,382. 
Final payment awaited resolution of a contract claim. 
Hired labor costs of $76,884 were incurred for sampling 
and testing, preparation of an environmental assessment, 
and supervision and inspection. Miscellaneous Purchase 
Orders totalling $22,770 were spent for Wave Gauge Study. 
17. GUILFORD HARBOR, CT 
Location. On north side of Long Island Sound about 13 
miles east of New Haven Harbor, CT. (See National Ocean 
Survey Chart 12354). 
Existing project. An entrance channel 6 feet deep, 100 
feet wide through the harbor from Long Island Sound to 
an anchorage basin in East River, length 0.8 mile, a channel 
6 feet deep, 60 feet wide up Sluice Creek 880 feet to 
Whitfield Street; an anchorage basin 6 feet deep, 200 feet 
wide in East River, length 1,500 feet. Mean and spring 
tidal ranges are 5.4 and 6.4 feet, respectively. (See Table 
1-B at end of chapter for Act authorizing existing project). 
Project was completed in April 1957. 
Local cooperation. Fully complied with. 
Terminal facilities. State wharf about 370 feet long 
provides adequate facilities for existing commerce. Town 
wharf on north bank of East River at foot of Whitfield 
Street is no longer useable. 
Operations during fiscal year. Maintenance: A contract 
was awarded and completed for removal of unclassified 
material in the 6-foot channel. Total contract cost was 
$22,830. Hired labor costs of $15,170 were incurred for 
surveys, preparation of plans and specifications, and 
supervision and inspection. 
18. HARBOR OF REFUGE, BLOCK 
ISLAND, RI 
Location. On east side of Block Island, near south end 
of inner curve of shoreline 13 miles south-southwest from 
Point Judith Harbor and about 25 miles southeasterly 
from Stonington Harbor, CT. (See National Ocean Survey 
Chart 13217). 
Existing project. For description of existing project, 
see Annual Report for 1976. (See Table 1-B at end of 
chapter for Acts authorizing existing project). Completed 
in 1916 except for inactive portion. 
Local cooperation. None required. 
Terminal facilities. Two wharves in harbor, both steel 
sheetpile bulkhead which comprises southern and eastern 
limits of basin. Total docking space amounts to 500 feet. 
No mechanical-handling facilities are available. One wharf 
owned by town and open to public, is considered inadequate 
for present general needs of boating in harbor. There is 
ample room for expansion of terminal facilities. 
Operations during fiscal year. Maintenance: A payment 
adjustment was made on a maintenance dredging contract 
awarded in FY82. Corrected dredging quantity for work 
completed in the previous fiscal year is 3,532 c.y. Hired 
labor costs of $2,425 were incurred for surveys and contract 
closeout. 
19. HARBOR OF REFUGE AND POINT 
JUDITH POND, POINT JUDITH, RI 
Location. Point Judith marks southwestern entrance to 
Narragansett Bay. Harbor lies in shallow bight west of 
point, about 14 miles southwest of Newport Harbor, RI, 
and 33 miles east of New London Harbor, CT. Point 
Judith Pond is a shallow salt pond, with a length north 
and south of about 4 miles, lying in rear of sandy beach of 
Rhode Island shore, just west of Point Judith Harbor by a 
narrow opening through sand dunes. (See National Ocean 
Survey Charts 13218 and 13219). 
Previous project. For details see Annual Report for 
1948. 
Existing project. For description of existing project 
see Annual Report for 1977. (See Table 1-B at end of chapter 
for Acts authorizing existing project). All work for 
project authorized prior to 1949 was completed in 1950. 
Breakwaters were completed in 1914 and dredging of 
shoals in project area was done in 1921. Main and east 
shore arm breakwater had deteriorated and required restoration 
to project design. In 1962 reconstruction of east 
arm breakwater and main breakwater dock facilities were 
1-8

NEW ENGLAND DIVISION 
completed. Rehabilitation required for remainder of 
breakwater restoration was completed in October 1963. 
The extension of the 15-foot channel was completed in 
April 1977. 
Local cooperation. Fully complied with. 
Terminal facilities. For further details on terminal 
facilities see Annual Report for 1977. 
Operations during fiscal year. Maintenance: Two 
contracts were awarded for repairs to the breakwaters. 
The amount of a contract for work on the east shore arm was 
$870,151. Work under this contract was continuing at the 
end of the fiscal year. Hired labor costs of $65,770 were 
incurred for preparation of plans and specifications and 
supervision and inspection. The contract amount for repairs 
to the main breakwater was $2,306,249. Work under this 
contract had not begun at the end of the fiscal year. 
20. HOUSATONIC RIVER, CT 
Location. Rises in northwestern Massachusetts, flows 
southerly 130 miles through Massachusetts and Connecticut, 
and empties into Long Island at Stratford, 5 miles 
east of Bridgeport Harbor. (See National Ocean Survey 
Chart 12370). 
Existing project. A channel 18 feet deep and 200 feet 
wide for a distance of 5 miles to lower end of Culvers bar, 
then 7 feet deep for 8 miles to Derby and Shelton; a 
5,820-foot riprap breakwater at the mouth; a 1,500-foot 
training dike 2 miles upstream at Stratford; and a 163-foot 
riprap jetty 13 miles upstream at East Derby. The enlargement 
of the breakwater and extension of the Stratford dike 
are inactive portions of the existing project. For more 
detailed description see page 11 of Annual Report for 1974. 
(See Table 1-B at end of chapter for Acts authorizing 
existing project). Except for inactive portions, the existing 
project was completed in September 1957. Inactive portion 
was deauthorized in November 1979. 
Local cooperation. Fully complied with. 
Terminal facilities. There are 8 wharves for commercial 
use at Stratford, 2 at Devon, and 8 at Shelton and Derby. 
The facilities are considered adequate for the existing 
commerce. 
Operations during fiscal year. Maintenance: Hired labor 
costs of $10,000 were incurred for preparation of an 
environmental assessment and work on a specification 
survey. 
21. ISLAND END RIVER, 
CHELSEA, MA 
Location. The Island End River is located approximately 
two miles north of downtown Boston in the heart of the 
Boston Metropolitan area. The river forms a portion of the 
boundary between the cities of Chelsea and Everett, and 
coincidentally Middlesex and Suffolk Counties. The Island 
End River flows into the Mystic River about one-half mile 
upstream of the confluence of the Mystic and Chelsea 
Rivers in Boston's Inner Harbor. (See National Ocean 
Survey Chart 13272). 
Existing project. The project provides recreational 
boaters with a 100-foot wide access channel extending 
from the Mystic River for a length of approximately 2,500 
feet to the site of a proposed marina facility and boat 
launching ramp, and would allow for an overall depth of 6 
feet at mean low water. Total cost is $504,240 of which 
$192, 363 is non-Federal cost. (See Table 1-B at end of 
chapter for Act authorizing existing project). Project was 
completed in April 1982. 
Local cooperation. Local interests would provide a cash 
contribution of 50 percent of the cost of construction; 
provide without cost to the United States all necessary 
lands, easements and rights-of-way required for construction 
and subsequent maintenance of the project 
including suitable dredged material disposal areas with 
necessary retaining dikes, bulkheads and embankments 
therefor; hold and save the United States free from damages 
that may result from construction and maintenance 
of the project; provide and maintain berths, floats, piers, 
and similar marina and mooring facilities as needed for 
transient and local vessels as well as necessary access 
roads, parking areas and other needed public use shore 
facilities open and available to all on equal terms; establish 
regulations prohibiting the discharge of untreated sewage, 
garbage, and other pollutants in the waters of the harbor 
users thereof, which regulations shall be in accordance 
with applicable laws or regulations of federal, state and 
local authorities responsible for pollution prevention and 
control. 
Operation during fiscal year. New work: Final adjustment 
of project cost sharing, administrative closeout of project 
and return of unused contributed funds were accomplished. 
22. KENNEBUNK RIVER, ME 
Location. Source of Kennebunk River in central part of 
York County in southwestern Maine. Stream flows about 
15 miles southeasterly and discharges into Atlantic Ocean 
about 350 miles southwest of Portland, Maine. (See National 
Ocean Survey Chart 13286). 
Existing project. For description of existing project see 
Annual Report for 1977. (See Table 1-B at end of chapter 
for Acts authorizing existing project). Project was 
completed in December 1968 with completion of rock 
removal at entrance to west channel. Extension of west 
jetty was completed in April 1965. Dredging and sand 
fence were completed in November 1965. 
Local cooperation. Fully complied with. 
Terminal facilities. There are 22 landings 16 of which 
are private, 1 public, 2 yacht clubs, 1 hotel, and 2 boatyards. 
Marine railway facilities include two of 15-ton capacity, 
and one of 10-ton capacity. There are 4 berths and 10 
moorings. Open storage, boat building, repairs, and supplies 
are available for pleasure and commercial craft. Public 
landing of granite block construction, has unloading 
facilities which include two tackle and falls on arms; and is 
used by fishing craft to transfer catches for transportation. 
Facilities are adequate for existing commerce. 
Operations during fiscal year. Maintenance: A contract 
was awarded for removal of unclassified material in the 6' 
1-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
channel and anchorage. Final payment totalled $20,162. 
Hired labor costs of $35,193 were incurred for surveys, 
plans and specifications, and supervision and inspection. 
23. MYSTIC RIVER, MA 
Location. Rises in Mystic Lake, MA, flows southeasterly 
7 miles and empties into Boston Harbor near Boston 
Naval Shipyard. (See National Ocean Survey Chart 13272). 
Previous projects. For details see page 1743 of Annual 
Report for 1915, and page 59 of Annual Report for 1938. 
Existing project. Channel 35 feet deep, extending from 
limit of 35-foot channel of Boston Harbor at Mystic River 
Bridge to approximately 300 feet downstream of Malden 
Bridge, having width varying from about 940 feet at its 
lower end, to about 1,060 feet at a point about 1,200 feet 
below the Malden Bridge, thence decreasing to 150 feet at 
its upper limit; channel 20 feet deep from head of existing 
35-foot channel to a point 800 feet above Malden Bridge, 
with widths decreasing from 150 feet at lower end to 75 
feet through drawspan, thence increasing to about 340 
feet to form turning basin above bridge; channel 6 feet 
deep and 100 feet wide from Boston & Maine Railroad 
(western division) Bridge to about 2,500 feet above 
Wellington Bridge, about 1 mile, and thence 4 feet deep, 
gradually narrowing from 100 to 50 feet at upper end for 
about 2 miles to head of commercial navigation at Craddock 
Bridge in Medford. Project depths refer to mean low 
water. Mean range of tide is 9.6 feet at Mystic River 
Bridge, 9.6 feet at Wellington Bridge, and 9.3 feet at 
Craddock Bridge. Extreme range is 13.7 feet. Federal cost 
of new work for completed project was $3,097,054, exclusive 
of amounts expended for previous projects. Project was 
completed in June 1958. (See Table 1-B at end of chapter 
for Acts authorizing existing project). 
Local cooperation. None required. 
Terminal facilities. In section of river benefited by 35- 
foot channel project there are on the south bank four 
wharves consisting of substantial stone or wooden 
bulkheads filled solid, aggregating over 4,000 feet of 
berthing space; also a lumber terminal, the largest of its 
kind on the Atlantic Coast, equipped with most modern 
mechanical appliances, has railroad connections and 
occupies 4,400 feet of waterfront. On north bank of river 
there is a large wharf used for receipt and shipment of oil 
on extensive scale; and adjacent thereto an extensive 
terminal used in connection with an iron works. There are 
several other wharves downstream of Malden Bridge and 
on west bank of Island End River used for receipt and 
shipment of coal, coke, tar, oil and in connection with a 
generating plant. None of the above is publicly owned or 
opened to general public use. In 20-foot channel section on 
south bank there are 1,850 feet and on north bank 1,235 
feet of available dockage; none of which is publicly owned, 
two are open to public on payment of charges. Facilities 
are considered adequate for existing commerce. 
Operations during fiscal year. Maintenance: Dredging 
which began last fiscal year was completed. Total contract 
costs were $882,000, and a total of 283,000 cubic yards of 
material were removed under the contract. Hired labor 
costs of $43, 015 were incurred for surveys, and supervision 
and inspection. 
24. NEW HAVEN HARBOR, CT 
Location. On north shore of Long Island Sound, about 
67 miles east of New York City. (See National Ocean 
Survey Chart 12371). 
Previous project. For details, see Annual Report for 
1915 and 1938. 
Existing project. For description of existing project see 
Annual Report for 1978. (See Table 1-B at end of chapter 
for Acts authorizing existing project). Project is complete. 
Local cooperation. Fully complied with. 
Terminal facilities. Port of New Haven is served by 53 
waterfront facilities; 40 are within city limits of New 
Haven, and 5 in West Haven. Improved waterways within 
port area along which facilities are located include West 
River, Main Harbor, West and East Branches of Mill 
River, and Quinnipiac River channels. Facilities are all 
privately owned and operated with exception of city wharf 
and U.S. Coast Guard wharf. Depths alongside piers and 
wharves range from 35 to zero feet at mean low water. 
Nearly half of the facilities have rail connections either on 
or at rear which connect with NY, NH & Hartford Railroad 
and most are accessible by paved streets. Nineteen wharves 
have mechanical handling facilities, six wharves are open 
to public use upon agreement with the owners. Facilities 
are adequate for existing commerce. (For further details 
see Port and Terminal Facilities of Southern New England 
No. 4, revised 1964). 
Operations during fiscal year. Maintenance: A contract 
for maintenance dredging was awarded in January 83. 
465,000 cubic yards of material have been dredged at a 
total contract cost of $1,488,000. Hired labor costs of 
$266,499 were incurred for surveys, plans and specifications, 
and supervision and inspection. An additional maintenance 
dredging contract was awarded in September for $857, 
500. Work had not begun at the end of the fiscal year. 
Disposal area monitoring work was awarded at a cost of 
$292,560. 
25. NEWBURYPORT HARBOR, MA 
Location. On south bank of Merrimack River, about 2.5 
miles above mouth, and about 48 miles by water north of 
Boston. (See National Ocean Survey Chart 13282). 
Existing project. Two jetties, one projecting 4,118 feet 
from the north shore, the other projecting 2,445 feet from 
the south shore, converging until 1,000 feet apart, then 
extending seaward 1,000 feet parallel to axis of channel; 
partially closing Plum Island Basin by a timber dike; 
channel 12 feet deep and 400 feet wide through bar, thence 
9 feet deep and 200 feet wide to and including a widened 
turning basin in front of wharves. Portion of project for 
continuous channel from sea to wharves at Newburyport, 
15 feet deep and 200 feet wide to and including a widened 
turning basin in front of wharves is considered inactive. 
Estimated cost of this portion (June 1955) is $106,000. 
1-10

NEW ENGLAND DIVISION 
(See Table 1-B at end of chapter for Acts authorizing 
existing project). Existing project except for inactive 
portion was completed in August 1958, with the improvement 
of 12-foot channel and outer harbor. North jetty was 
completed in 1914; south jetty was completed, except for a 
length of about 30 feet at its outer end, in 1905. Required rehabilitation 
in these jetties completed in September 1970. 
Plum Island basin was partially closed in 1883 by constuction 
of a timber dike. North Rock was removed in 1901. 
Local cooperation. Fully complied with. 
Terminal facilities. Twenty wharves extending along a 
frontage of about 3,500 feet of south bank of Merrimack 
River below highway bridge and one small pier on north 
side of river. Terminal facilities are adequate for existing 
commerce. 
Operations during fiscal year. Maintenance: A dredging 
contract was awarded and work was completed. 123,500 
cubic yards of material were dredged at a total contract 
cost of $603,241. Hired labor costs of $34,731 were incurred 
for surveys, plans and specifications, and supervision and 
inspection. A total of $22,148 was spent on work by the 
Waterways Experiment Station on the hydraulic model 
study report and shelter for the model. 
26. NORWALK HARBOR, CT 
Location. On north shore of Long Island Sound, about 
40 miles east of New York City. (See National Ocean 
Survey Chart 12368). 
Previous projects. For details see Annual Reports of 
1915 and 1938. 
Existing project. For description of existing project see 
Annual Report for 1973. (See Table 1-B at end of chapter 
for Acts authorizing existing project). Project was 
completed in 1950. 
Local cooperation. Fully complied with. 
Terminal facilities. There are two city wharves, neither 
of which is in usable condition. There are 19 private wharves 
in use or in usable condition, having a total berthing space 
of about 3,100 feet. One has rail connections. Private 
wharves are inadequate for existing commerce. (See Port 
Series No. 4 for Southern parts of New England (1952). 
Operations during fiscal year. Maintenance: Hired labor 
costs were incurred for planning activity in preparation 
for maintenance dredging. 
27. PATCHOGUE RIVER, CT 
Location. A small tidal stream 3 miles long, in town of 
Westbrook, CT, on north shore of Long Island Sound, about 
7 miles west of mouth of Connecticut River. (See National 
Ocean Survey Charts 12374 and 12354). 
Existing project. Provides for a channel 75 feet wide and 
8 feet deep extending about one mile from deep water in 
Duck Island Roads to highway bridge on U.S. Route 1; an 
anchorage and maneuvering area 8 feet deep, 75 feet wide, 
500 feet long opposite town wharf; a sand-tight stone jetty 
extending 600 feet southerly into Duck Island Roads from 
a point on west side of river mouth; and an access channel 
8 feet deep extending from deep water in Long Island 
Sound to the confluence of the Patchogue and Menunketesuck 
Rivers, a distance of 1,800 feet, at a width of 125 feet. 
(See Table 1-B at the end of chapter for Acts authorizing 
existing project). 
Project is complete except for the construction of the 
8-foot deep access channel from deep water in Long Island 
Sound to the confluence of the two rivers, which is 
underway. Construction of breakwater was initiated in 
April and completed in July 1956. Dredging 8-foot channel, 
anchorage, and maneuvering basin was initiated in September 
and completed in November 1956. 
Local cooperation. Fully complied with. Total costs for 
all requirements of local cooperation under terms of project 
authorization, including required non-Federal contributions, 
are $188,000. 
Terminal facilities. There are 5 wharves along the 
Patchogue River. The town of Westbrook constructed on 
right bank of river a free public wharf. It has no boat 
servicing nor transfer facilities. There are 60 feet of wharf 
space used principally by local fishing fleet for transfer of 
its catch to motor trucks that transport it directly to 
market. Wharf is solid-fill construction with rubblestone 
sides and earthfill, topped with a bituminous pavement. 
There are four private wharves in the central reach, two 
owned by Standard Fish Co., flank town wharf on north 
and south sides is a 90-foot marginal landing constructed 
on planks on 2-pile bents. Adjacent to this wharf is a 
marine railway, capable of handling boats up to 30 feet 
long, with storage space for 30 boats. Wharf on north side 
is a 35-foot long marginal landing of plank and pile 
construction with fishhouse attached. This wharf is used 
principally in fish and lobster business. Immediately 
upstream and abutting this wharf is a privately owned 
100-foot long marginal wharf of similar construction, which 
will be used in conjunction with the boatyard. Fuel-handling 
facilities are installed on the wharf. Remaining private 
wharf is on left bank of river, immediately below highway 
bridge. It is a 180-foot long marginal structure of timber, 
pile and rubblestone construction. Dock space is rented at 
this wharf and there is a building on shore adjacent to 
wharf, in which a retail and wholesale fish business is 
operated. There is adequate room for expansion of terminal 
facilities. 
Operations during fiscal year. Maintenance: A contract 
was awarded in September 1983 for maintenance dredging 
in combination with improvement dredging; the amount 
of the maintenance portion was $68,000. Hired labor costs 
of $16,293 were incurred for preparation of plans and 
specifications, sampling and testing, and a specification 
survey. New work: Contract was awarded in September 
1983 for dredging of the access channel from deep water in 
Long Island Sound to the confluence of the Patchogue 
and Menunketesuck Rivers. Work will be accomplished 
early in next fiscal year. 
1-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
28. PORTSMOUTH HARBOR AND 
PISCATAQUA RIVER, ME 
AND NH 
Location. Piscataqua River forms a portion of boundary 
between Maine and New Hampshire. Mouth of this river 
is called Portsmouth Harbor. It is 45 miles northeast of 
Boston Harbor, MA and 37 miles southwest of Portland 
Harbor, ME. (See National Ocean Survey Chart 13278). 
Previous project. For details see Annual Report for 
1892. 
Existing project. For description of existing project see 
Annual Report for 1972. (See Table 1-B at end of chapter 
for Acts authorizing existing project). Removal of ledge 
rock areas in the 35-foot channel, except for removal of 
sand shoal 400 feet upstream of Interstate Bridge, and 
removal of railroad engine from the harbor were completed 
in 1966. Shoal removal was completed in 1969 in the 
35-foot channel. Construction of 6-foot channel and 
anchorage was completed in 1971 at a reduced scope due 
to high construction costs, evidenced by initial bids 
received. 
Local cooperation. Fully complied with. 
Terminal facilities. For further details on terminal 
facilities see Annual Report for 1972. 
Operations during fiscal year. Maintenance: Hired labor 
costs were incurred for an environmental assessment and 
sampling and testing in preparation for future maintenance 
dredging. 
29. SACO RIVER, ME 
Location. Rises in White Mountain region of New 
Hampshire at an elevation about 1,900 feet above sea 
level, flows about 105 miles in a general southeasterly 
direction, and discharges into Atlantic Ocean about 16 
miles southwest of Portland Maine. (See National Ocean 
Survey Chart 13287). 
Existing project. For description of completed existing 
portion of project see Annual Report for 1978. (See Table 
1-B at end of chapter for Acts authorizing existing project). 
The current project now under construction consists of 
dredging a 3-acre 6 foot deep anchorage, protected by a 
series of 11 ice breaker structures, to be located to the east 
of the existing city pier and adjacent to the existing 
Federal navigation channel in the Saco River. Also, the 
installation of two ice breaker structures, to be placed to 
the west of the city pier, for protection of the pier. Estimated 
federal cost is $237,700. (See Table 1-B at end of chapter 
for Acts authorizing existing project). 
Local cooperation. Fully complied with. 
Terminal facilities. There are five wharves of solid fill 
construction at Saco and Biddeford, none of which has 
railroad connection; and a small pier near mouth of river 
used for summer passenger business. 
Operations during fiscal year. New work: A contract, 
awarded in September 1982, for improvement dredging 
and installation of ice breaker structures, was completed 
in January 1983. Final contract earnings were $174,000. 
Hired labor costs of $37,293 were incurred for contract 
administration and after dredge surveys. 
30. SAKONNET HARBOR, RI 
Location. Sakonnet Harbor, originally known as Church 
Cove, is located in the southwestern part of the town of 
Little Compton, Newport County, Rhode Island. It is 
about 30 miles southeast of Providence, and 5 miles east 
of Newport. The harbor is located at the eastern side of the 
entrance to the Sakonnet River, and directly adjoins the 
Atlantic Ocean at Block Island Sound. (See National 
Ocean Survey Chart 13221). 
Exisiting project. This provides for a breakwater 400 
feet long in a northerly direction; a 400-foot extension in a 
northeasterly direction; removal of rock nearest the wharf 
to a depth of 8 feet and dredging the harbor to a depth of 8 
feet. (See Table 1-B at end of chapter for Acts authorizing 
existing project). Original breakwater completed in 1900, 
extended in 1957. 
Local cooperation. Fully complied with. 
Terminal facilities. There are four wharves in the harbor, 
none of which are publicly owned. The Sakonnet Yacht 
Club pier on the east side of the harbor projects about 300 
feet from the shore has a float which makes it readily 
accessible to small craft. The three other wharves are 
located on the west side of the harbor. These wharves, for 
practical purposes, form one structure about 150 feet wide 
with two piers, 30 and 40 feet wide, projecting 35 and 70 
feet therefrom. The piers are open to the public free of 
charge. The State highway located along two sides of the 
harbor provides access to the wharves. These facilities are 
adequate for existing commerce. 
Operations during fiscal year. Maintenance: A contract, 
awarded in January 1983, for removal of unclassified 
material in the 8-foot anchorage was completed in April 
1983. Contract earnings were $24,785. Hired labor costs of 
$18,215 were incurred for preparation of plans & specifications, 
supervision & inspection and surveys. 
31. SESUIT HARBOR, MA 
Location. Sesuit Harbor is located on the north shore of 
Dennis in Barnstable County, about 85 miles southeast of 
Boston, MA. The town of Dennis is bordered on the north 
by Cape Cod Bay, Brewster and Harwich on the east, 
Nantucket Sound on the south, and Yarmouth on the 
west. Land area within the town is 20.66 square miles and 
has a tidal shoreline of 29.8 miles. (See National Ocean 
Survey Chart 13250). 
Existing project. Provides for a channel 6 feet deep 
below mean low water and 100 feet wide from deep water 
in Cape Cod Bay to a point opposite the Dennis Yacht 
Club thence reducing in width to 80 feet at the entrance to 
the inner harbor basin, for a total channel length of 2,400 
feet. The current estimated project cost is $189,100. (See 
Table 1-B at end of chapter for Act authorizing existing 
project). Project was completed in August 1982. 
Local cooperation. Local interests are responsible for 
fifty percent of the project construction costs, as well as 
the costs for dredging of all berthing areas outside the 
1-12

NEW ENGLAND DIVISION 
limits of the federal project. They would also be responsible 
for provision of necessary lands, easements, rights-of-way; 
any necessary vegetation of disposal areas; holding the 
United States free from damages due to construction and 
maintenance of additional berthing spaces as required for 
expansion of the project support facilities during the life 
of the project as well as establish regulations prohibiting 
disposal of pollutants into the waterway. Required contributions 
have been received. 
Operations during the fiscal year. New work: Computation 
of final project cost sharing was completed; additional 
Contributed Funds Required were received; and project 
administration was completed. 
32. RECONNAISSANCE AND 
CONDITION SURVEYS 
(See Table 1-Q at end of chapter). 
33. OTHER AUTHORIZED 
NAVIGATION PROJECTS 
(See Table 1-C at end of chapter). 
34. NAVIGATION ACTIVITIES 
PURSUANT TO SECTION 107, 
PUBLIC LAW 86-645 
(PREAUTHORIZATION) 
(See Table 1-H at end of chapter). 
Alterations of Bridges 
35. AUTHORIZED BRIDGE 
ALTERATION 
Location. Chelsea Street Highway Bridge MA. Construction 
was completed in October 1961 with a Federal 
cost of $138,518. In addition non-Federal contributed funds 
amounted to $8,602. For details see page 63 of Annual 
Report for 1962. 
Beach Erosion Control 
36. CLIFF WALK, NEWPORT, RI 
Location. In Newport, RI, about 25 miles south of 
Providence, it faces the Atlantic Ocean near mouth of 
Naragansett Bay on south side of Aquidneck Island, and 
extends 3.5 miles southward from west end of Newport 
(Eastons) Beach to and around Lands End and thence 
northward to east end of Bailey Beach. (See Coast Guard 
and Geodetic Survey Coast Charts 236, 353, and 1210.) 
Exisiting project. Provides for construction of improvements 
for shore protection at Newport, RI, extending 
18,000 feet from west end of Newport Beach to east end of 
Bailey Beach; consisting of: Intermittent reaches of backfill, 
dumped riprap, stone mounds, slope revetment and 
breakwaters; concrete toe walls, seawalls and parapet 
walls; grading and surfacing Cliff Walk and providing 
drainage therefore. Mean range of tide is 3.5 feet and spring 
range is 4.4 feet. Latest approved estimate of cost is 
$3,281,000 of which $2,558,000 is non-Federal. Latest 
published map is in project document (H. Doc. 228, 89th 
Cong., 1st sess). (See Table 1-B at end of chapter for Act 
authorizing existing project). Initial portion of the project 
was completed in 1972. Remainder of project could not be 
completed at that time due to lack of local funds. A second 
portion is now proposed to be accomplished in area near 
Salve Regina College. Congress appropriated funds in FY 
1982, but work on additional area has not been initiated. 
Local cooperation. Fully complied with for completed 
work, non-Federal contributions were $955,237. 
Operations during fiscal year. New Work: Coordination 
with local interests continued with respect to financing of 
non-Federal share of next phase of project construction. 
37. SHERWOOD ISLAND STATE 
PARK, WESTPORT, CT 
Location. In Westport, CT, approximately ten miles 
west of Bridgeport and 50 miles east of New York City. 
The beach is separated by Sherwood Point into two bathing 
areas known as East Beach and West Beach. 
Existing project. Provides for beach widening by 
direct placement of sandfill along 1,800 feet of West Beach, 
extending west from the existing Federal groin structures 
to Sherwood Point. Also included is the lowering of the 
landward portion of the existing groin and the construction 
of an intermediate low-profile groin structure approximately 
900 feet west of Sherwood Point. The current 
project cost estimate is $1,357,637 (excluding preauthorization 
costs of $158,891), of which $516,528 would 
be non-Federal (See Table 1-B at end of chapter for Act 
authorizing existing project). Project construction is 
completed. 
Local cooperation. Local interests are required to 
contribute, prior to construction, 30 percent of all project 
costs and must bear all project cost in excess of the 
Federal cost limitation of $1 million. Future nourishment 
would have to be borne by non-Federal interests since the 
$1 million Federal limitation will be incurred during initial 
construction. 
Operations during fiscal year. New work: The contract 
awarded in the prior fiscal year was completed in January 
1983. Final contract earnings were $1,277,230. A total of 
$39,968 in hired labor costs were incurred this fiscal year 
for contract administration. Final project cost sharing 
has been computed and $79,472 in unused Contributed 
Funds, Required is to be returned to local interests. 
1-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
38. WILLARD BEACH, SOUTH 
PORTLAND, ME 
Location. Willard Beach is located on the western 
extremity of Casco Bay in Simonton Cove, which is located 
south of the Fore River in the city of South Portland, ME. 
Existing project. Provides for beach widening by the 
direct placement of suitable sandfill along 1,700 feet of 
Willard Beach to a backshore elevation of 13.0 feet above 
mean low water, the construction of one terminal groin 
structure approximately 200 feet north of the southern 
limit of the beach, with rock revetment between the groin 
and the southern project limit, and backshore dune 
restoration. The current project cost estimate is $802,000 
(September 1983) which includes the first year of periodic 
nourishment, of which $401,000 is non-Federal. (See Table 
1-B at end of chapter for Act authorizing existing project). 
Construction has not been initiated. 
Local cooperation. Local interests must contribute prior 
to construction, in cash, 50 percent of the first cost of 
construction; assume full responsibility for all project 
costs in excess of the Federal cost limitation of $1,000,000, 
which includes the cost of periodic sand nourishment for 
the 50-year economic life of the project; maintain continued 
public ownership of the park and shore and its administration 
for public use during the 50-year economic life of 
the project; provide without cost to the United States all 
lands, easements and rights-of-way necessary for project 
construction and subsequent maintenance; maintain the 
protective measures during the economic life of the project 
as may be required by contributing in cash 100 percent of 
the cost of groin maintenance and 50 percent of the cost of 
periodic sand nourishment for the life of the project; and 
provide, at no cost to the Federal Government, relocation 
of the existing marsh drain and a street end drainage 
diversion system for the fresh water runoff that impacts 
the proposed backfill area. 
Operations during fiscal year. New work: A Detailed 
Project Report was completed and the project was approved 
for construction in April 1983. Funding for the preparation 
of plans and specifications was received and the project 
was included in the approved Jobs Bill program resulting 
from the Productive Employement Appropriations Act of 
1983. At year end, local interest had not yet indicated an 
ability to participate in the cost of construction at this 
time. 
39. INSPECTION OF COMPLETED 
BEACH EROSION CONTROL 
PROJECTS 
Inspections of beach erosion control protects were not 
conducted in fiscal year 1983. 
40. OTHER AUTHORIZED BEACH 
EROSION CONTROL 
PROJECTS. 
(See Table 1-D at end of chapter). 
41. BEACH EROSION CONTROL 
ACTIVITIES PURSUANT TO 
SECTION 103, PUBLIC LAW 
87-874 (PREAUTHORIZATION) 
(See Table 1-I at end of chapter). 
Flood Control 
42. BLACKSTONE RIVER BASIN, 
MA AND RI 
Works covered by this plan consist of a dam and reservoir 
on West River and local protection works at three cities on 
Blackstone River. Flood Control Act of 1944 authorized 
plan for a reservoir on West River and local protection 
works at Worcester, MA, and Woonsocket and Pawtucket, 
RI, substantially in accordance with House Document 
624, 78th Congress, 2nd session. Flood Control Act of 
1960 authorized a local flood protection project at Lower 
Woonsocket, RI, substantially in accordance with Senate 
Document 87, 85th Congress, 2nd session. Local protection 
nonstructural project authorized in 1982 for Belmont Park 
section of Warwick, RI along the Pawtuxet River. (See 
Table 1-K at end of chapter on reservoir and local protection 
projects, Blackstone River Basin, for projects comprising 
authorized plan). 
42A. PAWTUXET RIVER, 
WARWICK RI 
Location. The Pawtuxet River flows in a northeasterly 
direction through West Warwick, Warwick and Cranston 
before it discharges into Narragansett Bay at Pawtuxet 
Cove. The watershed has a maximum length of 18 miles 
running west to east and 23 miles width from north to 
south. The drainage area at its mouth in Pawtuxet Cove is 
230 square miles. The project is located in the Norwood 
section of Warwick, locally referred to as Belmont Park. 
Existing project. Consists of acquisition, demolition 
and removal from the flood plain a total of 59 homes; 
acquisition of 19 privately-owned vacant lots; construction 
of 17 above-ground utility room additions to residences 
which experience basement flooding; and the installation 
of an automated flood forecasting and warning system. 
The current estimated project cost is $3,700,000 with the 
Federal government paying 80 percent of the project cost 
up to a Federal limit of $4 million. After implementation, 
the City of Warwick would be responsible for the cost of 
operating and maintaining the flood forecasting/ warning 
system. (See Table 1-B at end of chapter for authorizing 
legislation). Project implementation was begun in 
September 1982 with property acquisition. 
Local cooperation. Local interests must implement 
acquisition and removal of properties and pay 20 percent 
of project costs unless total project costs exceed 
$5,000,000 in which case local interests incur all costs 
above that figure. 
Operations during fiscal year. Acquisition continued. A 
total of 24 properties were acquired during the year. 
1-14

NEW ENGLAND DIVISION 
42B. WEST HILL DAM, MA 
Location. Dam is on West River, MA, 3 miles above its 
confluence with Blackstone River and 2.5 miles northeast 
of Uxbridge, MA. (See Geological Survey maps- 
Blackstone, MA and RI, Milford, MA, and Grafton, MA). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report for 
1975. Project is complete. Work on contract for dam and 
appurtenant structures was initiated in June 1959 and 
completed in June 1961. Construction of recreational 
facilities was completed in June 1967. 
Cost of new work for completed project was $1,367,000 for 
construction and $940,000 for lands and damages including 
highway and utility relocations, a total of $2,307,000. 
Local cooperation. Section 3, Flood Control Act of 1944, 
applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. 
42C. CHARLES RIVER(NATURAL 
VALLEY STORAGE AREAS), MA 
Location. The Charles River extends inland from Boston 
Harbor southwesterly toward the Massachusetts-Rhode 
Island border and is some 80 miles long with a watershed 
covering 307 square miles. 
Existing project. The project provides for Federal 
acquisition and protection of 17 natural valley storage 
areas totalling 8,136 acres in what is known as the Middle 
and Upper watershed of the Charles River. The acquisition 
in fee or by easement of the major natural valley storage 
areas within the Charles River watershed is intended as a 
multiple-purpose project for flood control, recreation, and 
fish and wildlife management. The latest approved cost 
estimate (October 1983) for new work is $8,200,000. (See 
Table 1-B at end of chapter for Act authorizing existing 
project). Land acquisition is complete. 
A total of 3,269 acres have been acquired in fee at a cost 
of $1,992,000 and restrictive easements have been obtained 
for 4,867 acres at a cost of $519,361. 
Local cooperation. Local interests are required to prevent 
modifications or alteration of existing roadways, utilities, 
bridges, culverts, and any other improvements that might 
affect the drainage characteristics of the natural storage 
areas; adopt and enforce regulations to restrict development 
of flood plan lands; and operate and maintain the existing 
dams along the Charles River. Local assurances have been 
received. 
Operations during fiscal year. New work: Aquisition was 
substantially completed with the resolution of approximately 
100 condemnation cases remaining to complete 
the project. 
43. CONNECTICUT RIVER BASIN, 
VT, NH, MA AND CT 
Location. Works covered by this project are a series of 
dams and reservoirs on tributaries of Connecticut River in 
Vermont, New Hampshire and Massachusetts, within a 
radius of 230 miles from Hartford, CT, and local protection 
works at several cities in the basin. 
Existing project. Flood Control Act of 1936, as amended 
by Act of May 25, 1937, authorized construction of 10 
reservoirs on tributaries of Connecticut River in accordance 
with plans in House Document 412, 74th Congress, 2nd 
session, as the same may be revised upon further 
investigation of 1936 flood. Flood Control Act of 1938 
approved a general comprehensive plan for control of 
floods and other purposes in Connecticut River Valley, as 
set forth in House Document 455, 75th Congress, 2nd 
session, and authorized $11,524,000 for construction of 
local flood protection projects in the plan. Act of October 
15,1940, modified Act of June 18,1938, to provide additional 
protection at East Hartford, CT, as set forth in House 
Document 653, 76th Congress, 3rd session. Act of August 
18, 1941, modified comprehensive plan approved in 1938 
to include improvements recommended in House Document 
653, 76th Congress, 3rd session, and House Document 
724, 76th Congress, 3rd session, with such further 
modifications as may be found justifiable in discretion of 
Secretary of the Army and Chief of Engineers. Latter Act 
also authorized to be appropriated additional $6 million 
for local protection works and $10 million for reservoirs. 
Act of October 26, 1942, further modified plan by including 
construction of Gully Brook conduit at Hartford, CT. 
Flood Control Act of 1944 authorized expenditure of $30 
million in addition to previous authorization for comprehensive 
plan approved in 1938 and modified plan by directing 
specific consideration of an alternative plan of Vermont 
State Water Conservation Board instead of Williamsville 
Reservoir in West River Basin, VT; directing consultation 
with affected States during course of investigations and 
transmission of proposal and plans to each affected State 
for written views and recommendations for reservoir 
projects heretofore authorized for construction at Cambridgeport, 
Ludlow, South Tunbridge, and Gaysville, and 
resubmission of projects or modifications for construction 
of Sugar Hill site. Flood Control Act of 1950 modified 
project for flood control at Hartford, CT, authorized by 
Flood Control Act of 1938, as amended, to include Folly 
Brook dike and conduit. Flood Control Act of 1954 modified 
plan for flood control in Connecticut River Basin to 
provide for construction of a reservoir on Otter Brook at 
South Keene, NH, in lieu of any reservoir or reservoirs 
heretofore authorized. This Act further modified plan for 
West River Basin of Connecticut River in Vermont to 
consist of three reservoirs at Ball Mountain, The Island, 
and Townshend sites, in lieu of plan of eight reservoirs 
authorized in Flood Control Act of 1944. Flood Control 
Act of 1958 modified plan for flood control in Connecticut 
River Basin to include construction of Littleville Reservoir 
on Middle Branch of Westfield River, MA, and Mad River 
Reservoir on Mad River, above Winsted, CT. Flood Control 
Act of 1960 included authorization in Connecticut River 
Basin of plan for flood protection on Chicopee River, MA, 
substantially in accordance with House Document 434, 
86th Congress; plan for flood protection on Westfield 
River, MA, substantially in accordance with Senate 
Document 109, 86th Congress; plan for flood control and 
related purposes on Farmington River, CT, substantially 
1-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
in accordance with House Document 443, 86th Congress. 
Flood Control Act of 1968 included authorization in 
Connecticut River Basin of plan for construction of Beaver 
Brook Reservoir, on Beaver Brook in Keene, NH, 
substantially in accordance with Senate Document 60, 
90th Congress; and plan for flood protection on Park 
River, CT, substantially in accordance with Senate 
Document 43, 90th Congress. Flood Control Act of 1970 
deauthorized the construction of a reservoir at Claremont, 
NH. The Water Resources Development Act of 1976 deauthorized 
the construction of Gaysville Lake, Vermont project. 
Flood control projects at Cambridgeport Lake, Brockway 
Lake, Victory Lake, South Tunbridge Lake, Ludlow Lake 
and The Island Lake, Vermont; Honey Hill Lake, West 
Canaan Lake, and the Alternative to Sugar Hill Reservoir, 
New Hampshire were deauthorized in August 1977 in 
accordance with Section 12 of the Water Resource 
Development Act of 1974. The authorization for Beaver 
Brook Lake, New Hampshire project expired in April 
1978 due to lack of local cooperation. Local protection 
projects at Gardner, MA, Hartford, VT and Wethersfield, 
CT authorized and constructed in accordance with section 
205 of 1948 Flood Control Act. (See Table 1-L at end of 
chapter for reservoirs and local protection works proposed 
for construction in modified comprehensive plan). 
43A. BALL MOUNTAIN LAKE, VT 
Location. Dam is on West River, 29 miles above its 
junction with Connecticut River at Brattleboro, VT. It is 
2 miles north of village of Jamaica, VT. (See Geological 
Survey map for Londonderry, VT). 
Existing project. For description of completed improvements 
and authorizing legislation see Annual Report for 
1975. Cost of new work for project was $10,448,000 for 
construction and $350,000 for lands and damages, a total 
of $10,798,000. Recreation facilities to be constructed are 
estimated at $200,000. Project is complete. Construction 
of dam and appurtenant works was initiated in May 1957 
and completed in November 1961. Construction of initial 
recreation facilities was initiated in June 1975 and completed 
in June 1977. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. 
Operations during fiscal year. New work: A contract, 
in the amount of $146,294 for construction of an "A" 
frame restroom at the Winhall Recreation Area, awarded 
in September 1982 was completed in September 1983. 
Maintenance: Ordinary operation and maintenance 
activities. 
43B. BARRE FALLS DAM, MA 
Location. Dam is on Ware River in town of Barre, MA, 
31.9 miles above confluence of Ware and Swift Rivers. It 
is 13 miles, northwest of Worcester, MA. (See Geological 
Survey maps Barre, MA, and Wachusett Mountain, MA). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report for 
1975. Cost of completed new work is $1,928,000 for 
construction and $39,000 for lands and damages including 
highway relocation, a total of $1,967,800. Project is 
complete. Construction of dam and appurtenant works 
was initiated in May 1956 and completed in May 1958. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. 
43C. BIRCH HILL DAM, MA 
Location. Dam is on Millers River, 27.3 miles above its 
junction with Connecticut River. It is 1.3 miles east of 
South Royalston, MA and 7.5 miles northwest of city of 
Gardner, MA. (See Geological Survey maps for Royalston 
and Winchendon, MA- NH and Templeton, MA). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report for 
1975. Cost of new work for completed project was $1,775,500 
for construction and $3,075,000 for land and damages, a 
total of $4,850,500. Total includes $32,000 as local share 
for construction of recreation facilities. Project is complete. 
Construction of dam and appurtenant works was initiated 
in June 1940 and completed in February 1942. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. Local interests have contributed $32,000 as their 
required 50 percent cost sharing of recreational development 
in accordance with 1965 Federal Water Project Recreation 
Act. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. A contract awarded 
in March 1983 to replace heating system was completed in 
July 1983. The contract amount was $13,840. Another 
contract awarded in April 1983 to repair the Operating 
House is scheduled for completion in October 1983. The 
contract amount is $42,385. A contract in the amount of 
$39,513 for repairs to Access Road, awarded in September 
1982, was completed in November 1982. 
43D. COLEBROOK RIVER LAKE, 
CT 
Location. Damsite is in town of Colebrook, Litchfield 
County, CT, on West Branch Farmington River about 3.9 
miles upstream from its confluence with Still River at 
Riverton, CT, and about 1.5 miles upstream from Goodwin 
(Hogback) Dam. (See Geological survey map for Winsted, 
CT). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report for 
1975. Cost of new work for completed project was $8,342,000 
for construction and $5,922,000 for lands, damages, and 
relocations, a total of $14,264,000. Project is complete. 
Construction of dam and appurtenant works was initiated 
in May 1965 and completed in June 1969. Construction of 
recreation facilities was initiated in August 1969 and 
completed in June 1970. 
1-16

NEW ENGLAND DIVISION 
Local cooperation. Water supply contract was signed 
by Hartford Connecticut Metropolitan Water District. 
Repayment will be made in accordance with provisions of 
1958 Water Supply Act. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. 
43E. CONANT BROOK DAM, MA 
Location. Site is in south central part of Massachusetts 
in town of Monson. Damsite, across Conant Brook, is 
about 2 miles southwest of community of Monson. (See 
Geological Survey map for Monson, MA). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report for 
1975. Cost of new work for completed project was $1,936,000 
for construction and $1,015,000 for lands, damages, and 
relocation of roads and utilities, a total of $2,951,000. 
Construction of dam, highway relocations, and appurtenances 
was initiated in June 1964 and completed in December 
1966. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. 
43F. KNIGHTVILLE DAM, MA 
Location. Dam is on Westfield River, 27.5 miles above 
its confluence with Connecticut River. It is 4 miles north 
of town of Huntington, MA, and about 12 miles west of 
city of Northampton, MA. (See Geological Survey map 
for Westhampton, MA). 
Existing project. For description of completed improvements 
and authorizing legislation see Annual Report for 
1975. Cost for new work was $2,594,440 for construction 
and $821,200 for lands and damages, a total of $3,415,640. 
Project is complete. Construction of dam and appurtenant 
works was initiated in August 1939 and completed 
December 1941. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. A contract awarded 
in August 1983 for painting service gates is scheduled for 
completion in fiscal year 1984. 
43G. LITTLEVILLE LAKE, MA 
Location. Dam is on Middle Branch of Westfield River 
1 mile above its confluence with main stem of Westfield 
River and 25.2 miles above confluence of Westfield River 
with Connecticut River, in town of Chester. (See Geological 
Survey map, Chester, MA). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report for 
1975. Total cost of new work was $5,863,400 for construction 
and $1,150,000 for lands and damages, including 
relocation of a highway, utilities, cemeteries, and 
structures, a total of $7,013,400. Project is complete. 
Construction of dam and appurtenances was initiated 
under a multicomponent contract in June 1962 and completed 
in September 1965. 
Local cooperation. Section 2, Flood Control Act of June 
18, 1938, and Title III, Water Supply Act of 1958 applies 
and fully complied with. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. A contract awarded 
in September 1983 to replace the emergency generator is 
scheduled for completion in fiscal year 1984. 
43H. NORTH HARTLAND 
LAKE, VT 
Location. Dam is on Ottauquechee River, 15 miles above 
its junction with Connecticut River and 1 mile northwest 
of North Hartland, VT. Reservoir extends upstream 5.5 
miles. (See Geological Survey map for Hanover, NH - VT). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report for 
1975. Cost for new work is $6,349,500 for construction and 
$963,000 for lands and damages (including highway and 
utility relocations), a total of $7,312,500. Project is complete. 
Construction of dam was initiated in June 1958 and 
completed in June 1961. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. 
43I. NORTH SPRINGFIELD LAKE, 
VT 
Location. Dam is in town of Springfield, VT, on Black 
River, 8.7 miles above its junction with Connecticut River, 
and 3 miles northwest of Springfield, VT. (See Geological 
Survey maps - Ludlow, CT and Claremont NH). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report for 
1975. Cost for new work is $4,782,000 for construction and 
$2,050,000 for lands and damages, including highway, 
cemetery, and utility relocations, a total of $6,832,000. 
Project is complete. Contruction of dam was initiated in 
May 1958 and completed in November 1960. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. A contract awarded 
in June 1982 to replace the intake tower generator was 
completed in November 1982. The contract amount was 
$15,551. 
43J. OTTER BROOK LAKE, NH 
Location. Dam is on Otter Brook, 2.4 miles upstream 
from its junction with The Branch, which flows 2.5 miles 
1-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
to Ashuelot River at Keene. (See Geological Survey maps 
- Keene, NH - VT, and Monadnock, NH). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report for 
1975. Total cost of new work was $2,782,100 for construction 
and $1,378,400 for lands and damages, including 
highway relocation, a total of $4,160,500. An estimate 
of $170,000 for construction of recreation facilities. Project 
is complete. Construction of dam and appurtenant 
works was initiated in September 1956 and completed in 
August 1958. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. A contract awarded 
in June 1983 to repair project roads and parking areas is 
scheduled for completion in November 1983. The contract 
amount is $55,250. Another contract in the amount of 
$124,774 for renovations to the Change House was 
completed in June 1983. 
43K. PARK RIVER, HARTFORD, 
CT 
Location. On the Park River in the City of Hartford, 
Hartford County, CT. (See Geological Survey map of 
Hartford North, CT). 
Existing project. Authorized as a modification to completed 
Hartford, CT local protection project. (For details 
on completed project see Annual Report for 1960). Two 
sections of reinforced concrete conduit totalling 2,569 feet 
with width of 34 feet and height of 26.5 feet on the Park 
River; one section of reinforced concrete conduit 103 feet 
long, 36 feet wide and 27.5 feet high on the South Branch; 
two sections of reinforced concrete conduit 1,364 feet long, 
22 feet wide and 25 feet high on the North Branch; a 
reinforced concrete junction structure to combine the flows 
from the North and South branches and distribute them 
to the Park River and auxiliary conduits and thence to the 
Connecticut River, circular auxiliary conduit approximately 
9,200 feet long to be constructed as a deep tunnel in rock 
with an inside diameter of 22 feet and lined with 9-inch 
thick precast concrete walls, an inlet structure and an 
outlet structure; a concrete headwall at the entrance to 
the North Branch conduit extension; and two pumping 
stations on the banks of the Park River. The latest approved 
cost estimate (September 1983) for new work is $1,300,000 
for lands including relocations and $60,117,000 for 
construction, a total of $61,417,000. Total includes local 
costs of $1,200,000 for lands and $100,000 for relocations, 
a total of $1,300,000. (See Table 1-B at end of chapter for 
Act authorizing existing project). Construction was 
completed in 1981. Resolution of claims and administrative 
close out to be accomplished. 
Local cooperation. Provide all lands, easements and 
rights-of-way for construction and operation of project; 
hold and save the United States free from damages due to 
construction works; maintain and operate all works after 
completion; upon completion of conduit construction replace 
pavements, sidewalks, drainage and other appurtenances, 
including those at Broad Street, Flower Street and Laurel 
Street and bear cost of removal, replacement and 
modification to sewers, drains, utilities or highways beyond 
the area required for excavation and construction of the 
project; prevent changes in headpool ponding areas which 
would decrease the effectiveness of the improvements and 
if ponding areas and capacities are impaired, promptly 
substitute equivalent storage capacity; and undertake all 
practical measures to prevent pollution from entering the 
Park River conduit system. 
Operations during fiscal year. New work: Design of 
remedial work to correct undersized stone at upper end of 
project was initiated. Deficiency was brought to light 
during heavy rains of March-April 1983 when a partial 
failure of the stone slope protection system was suffered 
in an area upstream of the intake structure for the twin 
box conduit. Estimated cost of the work is $240,000 and is 
to be accomplished in fiscal year 1984. 
43L. SALMON RIVER, 
COLCHESTER, CT 
Location. The towns of Colchester and East Hampton 
are located in the western section of New London County, 
approximately 14 miles southeast of Hartford, Connecticut. 
From its headwaters in Bolton, Connecticut, the Salmon 
River flows southeasterly for 20 miles to its confluence 
with the Connecticut River in East Hampton, Connecticut, 
about 4 miles downstream of the problem area at the 
Colchester-East Hampton town line. 
Existing project. Provides for the construction of 250 
feet of "Doublewal" precast concrete block slope protection 
along the right bank of the river adjacent to the Brown's 
Mill Road. (See Table 1-B at end of chapter for Act 
authorizing existing project). Project was completed in 
October 1982. 
Local cooperation. Local interests would provide, without 
cost to the United States, all lands, easements, rights-ofway, 
and utility relocations necessary for project construction, 
operation and maintenance of the project, except 
where such damages are due to the fault or negligence of 
the United States or its contractors; maintain and operate 
the project after completion without cost to the United 
States in accordance with regulations prescribed by the 
Secretary of the Army; annual operation and maintenance 
costs will be equally divided by the two towns. 
Operations during fiscal year. New work: A contract, 
awarded in February 1982, for emergency streambank 
protection was completed in October 1982. Contract 
earnings were $168,354. 
43M. SAXTONS RIVER, ROCKINGHAM, 
VT 
Location. The town of Rockingham is located along the 
west bank of the Connecticut River in southeastern 
Vermont, about 22 miles north of Brattleboro and 8 miles 
south of Springfield. The town is comprised of several 
villages, including Saxtons River which is located along 
1-18

NEW ENGLAND DIVISION 
the banks of the Saxton River, a tributary of the Connecticut 
River. The total drainage area of the Saxton River is 78 
square miles and it flows from its upper watershed in the 
Green Mountains generally west to east for a distance of 
about 20 miles to its confluence with the Connecticut 
River. 
Existing project. Provides for correction of streambank 
erosion problems that endanger town-owned access ramps 
to the Saxtons River which are used during fire emergencies 
to pump water from the river. Work includes providing for 
construction of a precast concrete, modular-type wall about 
175 feet long to protect the primary pumping site. The 
current estimated project cost is $120,000 (September 
1983). (See Table 1-B at end of chapter for Act authorizing 
existing project). Contract for construction was awarded 
in September 1983. Work has not yet begun. 
Local cooperation. Local interests must provide without 
cost to the United States all lands, easements, rights-ofway 
and utility relocations necessary for project construction; 
maintain and operate the project after completion 
without cost to the United States; prevent future 
encroachment which might interfere with proper functioning 
of the project; and assume the responsibility for all 
costs in excess of the Federal cost limitation of $250,000. 
Operations during fiscal year. New work: Preconstruction 
planning was completed and a construction contract 
in the amount of $67,428 was awarded on September 1, 
1983. Hired labor costs were $35,842. Construction will be 
underway in October 1983. 
43N. SURRY MOUNTAIN LAKE, 
NH 
Location. Dam is on Ashuelot River, 34.6 miles above 
its junction with Connecticut River and 5 miles north of 
Keene, NH. (See Geological Survey maps for Keene and 
Bellows Falls, NH - VT). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report for 
1975. Cost of new work for completed project is $2,448,610 
for construction and $385,000 for lands and damages, a 
total of $2,833,610. Total includes $140,00 for additional 
recreation facilities. Construction of dam and appurtenant 
works was initiated in August 1939 and completed in June 
1942. Initial phase of additional recreational facilities 
completed in September 1969, secondary phase in 1980. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. 
430. TOWNSHEND LAKE, VT 
Location. Dam is on West River, 19.1 miles above its 
junction with Connecticut River at Brattleboro, VT, and 
about 2 miles west of Townshend, VT. Reservoir extends 
upstream about 4 miles, (See Geological Survey maps 
- Saxtons River, VT, and Londonderry, VT). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report for 
1975. Cost of new work for completed project was $5,530,000 
for construction and $1,870,000 for lands and damages 
including highway relocations and utilities, a total of 
$7,400,000. Project is complete. Construction of dam and 
appurtenant works was initiated in November 1958 and 
completed in June 1961. Initial phase of additional 
recreational facilities completed in October 1969. Secondary 
phase completed in September 1971. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. A contract awarded 
in February 1983 to repaint spillway bridge was completed 
in June 1983. The contract amount was $17,300. 
43P. TULLY LAKE, MA 
Location. Dam is on East Branch of Tully River, 3.9 
miles above its junction with Millers River. It is 1 mile 
north of Fryville, MA, and 3.5 miles north of Athol, MA. 
(See Geological Survey map for Royalston, MA - NH). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report for 
1975. Total cost of new work is $1,298,800 for construction 
and $368,000 for lands and damages, a total of $1,666,800. 
Total includes $40,000 as local share of recreational facilities. 
Project is complete. Construction of dam and appurtenant 
works was initiated in March 1947 and completed in 
September 1949. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. Local interests must also bear 50 percent of future 
recreational development, in accordance with 1965 Federal 
Water Project Recreational Act. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. 
43Q. UNION VILLAGE, DAM, VT 
Location. Dam is on Ompompanosuc River 4 miles 
above its junction with Connecticut River. It is one-fourth 
mile north of Union Village, VT, and 11 miles north of 
White River Junction, VT. (See Geological Survey maps 
for Strafford, VT and Mount Cube, NH - VT). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report for 
1975. Total cost for new work is $3,186,860 and $908,300 
for lands and damages, a total of $4,095,160. Total includes 
$84,462 for recreation facilities. Project is complete. 
Construction of dam was initiated in March 1947 and 
completed in June 1950. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. A contract awarded 
in May 1983 for repairs to the Operating House masonry 
is scheduled for completion in October 1983. The contract 
amount is $12,429. 
1-19

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
43R. WEST BRANCH, WESTFIELD 
RIVER, HUNTINGTON, MA 
Location. The town of Huntington is located in southern 
Hampshire County in western Massachusetts, about 20 
miles northwest of the city of Springfield. Project is located 
along the right bank of the West Branch near the center of 
town, about one-half mile upstream from its confluence 
with the Westfield River. From its headwaters in Becket, 
the West Branch of the Westfield River flows in a general 
southeasterly direction for about 17 miles to its confluence 
with the Westfield River in Huntington and has a drainage 
area of 96 square miles. 
Existing project. Provides for streambank erosion 
protection measures by placement of riprap slope protection 
in two sections along the right bank of the river: one 
section 100 feet long at the twin 6-inch inverted sewer 
siphon, and one section 50 feet long at the 8-inch gravity 
sewer line manhole. At the inverted siphon, riprap will be 
placed in the riverbed 5 feet on each side of the siphon 
encasement. The current estimated project cost is $95,000. 
(See Table 1-B at end of chapter for Act authorizing 
existing project). Project construction was completed in 
July 1983. 
Local cooperation. Local interests must provide without 
cost to the United States all lands, easements, rights-ofway 
and utility relocations necessary for project construction; 
maintain and operate the project after completion 
without cost to the United States; prevent future 
encroachment which might interfere with proper functioning 
of the project; and assume the responsibility for all 
costs in excess of the Federal cost limitation of $250,000. 
Operations during the fiscal year. New work: Preconstruction 
planning was completed and a construction 
contract was awarded in June 1983. Contract was completed 
in July 1983 at a final cost of $42,070. Hired labor costs of 
$20,454 were incurred for planning and contract 
administration. 
43S. WEST SPRINGFIELD, 
CONNECTICUT RIVER 
BASIN, MA 
Location. The West Springfield local protection works 
are located in the town of West Springfield, MA.The 
project is on the west bank of the Connecticut River, 76 
miles above its mouth. (See U.S. Geological Survey maps 
for Springfield South and West Springfield, MA - CT). 
Existing project. This project consists of a system of 
earth levees and concrete floodwalls approximately 24,500 
feet in length. The system starts at high ground, in the 
vicinity of Harrison Place, and extends downstream along 
the Connecticut River and up the north bank of the 
Westfield River to high ground at the Boston & Albany 
Railroad. The work involved raising 13,700 feet of existing 
levee, constructing 2,300 feet of floodwall, improving 2,400 
feet of river bank, and treating 6,100 feet of existing levee 
foundation. Three pumping stations with appurtenant 
drainage facilities were also constructed for the disposal 
of interior drainage. The project, with the approved plan 
of reservoirs, is designed to protect against a flood greater 
than any of record. The levee and floodwall grades are, at 
all points, above the maximum stage of the greatest flood 
of record, that of March 1936. 
A modification to the project was authorized in October 
1982 providing for the raising of the floodwall sections by 
one foot and the provision of a flood forecasting system. 
The project is a unit of the comprehensive plan of flood 
control and other purposes in the Connecticut River Basin 
and was authorized by the Flood Control Act approved 
June 28, 1938. The project is complete except for the 
modification authorized in 1982 for which a contract has 
just been awarded. Construction of the prior project work 
was initiated in March 1939 and completed in July 1942 
with the exception of foundation treatment along the 
Westfield River south of Agawam Bridge, which was 
initiated in May 1947 and completed in November 1947, 
and the relief well and drainage system, which was initiated 
in August 1952 and completed in July 1953. Total costs 
were $245,000 from Public Works Administration funds 
and $1,333,724 from regular funds, a total of $1,578,724. 
The estimated cost of uncompleted work is $130,000 for 
construction and $50,000 for the flood forecast system, a 
total of $180,000 of which $170,000 would be Federal and 
$10,000 would be non-Federal. 
Local cooperation. Fully complied with for completed 
work. For the project modification authorized in 1982, 
local interests must provide without cost to the United 
States all lands, easements and rights-of-way necessary 
for project construction; maintain and operate the project 
upon completion; provide a cash contribution of 20 percent 
of the total first cost of flood forecast equipment, an 
amount currently estimated at $10,000; and insure an 
adequate evacuation plan through public education, testing 
and updating as required. Formal assurances have been 
received. 
Operations during fiscal year. New work: Floodwall 
modification and flood forecast system were authorized in 
October 1982. Project planning was completed and a 
contract in amount of $67,900 was awarded in September 
1983 for raising of floodwall. Work has not been started. 
44. HOUSATONIC RIVER BASIN, 
CT AND MA 
Authorized improvements in Housatonic River Basin 
are comprised of seven flood control reservoirs on tributaries 
of the Naugatuck River, principal tributary of Housatonic 
River, and seven local protection projects, five of which 
are along Naugatuck River, one on Housatonic River and 
one on Still River. Naugatuck and Housatonic Rivers 
converge 12 miles above mouth of Housatonic River. A 
project for emergency snagging and clearing of the 
Blackberry River, a tributary of the Housatonic River, 
was authorized under authority contained in Section 208 
of the 1954 Flood Control Act. Emergency bank protection 
projects at Alford, Green River, Massachusetts and at 
Sheffield, MA, and Salisbury, CT along the Housatonic 
were authorized under authority provided by Section 14 of 
the 1948 Flood Control Act. A project for local flood 
1-20

NEW ENGLAND DIVISION 
protection along the Housatonic River in Pittsfield, 
Massachusetts was authorized under authority provided 
by Section 205 of the 1948 Flood Control Act. (See Table 
1-B at end of chapter for Acts authorizing existing project; 
also Table 1-M on dams and reservoirs and local protection 
projects for Housatonic River Basin). 
44A. BLACK ROCK LAKE, CT 
Location. Damsite is on Branch Brook about 2 miles 
upstream from its confluence with Naugatuck River in 
towns of Thomaston and Watertown, CT. (See Geological 
Survey map for Thomaston, CT). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report for 
1975. Cost for new work for completed project was 
$5,223,700 for construction and $2,958,600 for lands and 
damages, including roads and utilities relocation, a total 
of $8,182,300. Project is complete. Road relocation completed 
in November 1967. Contract for construction of 
dam and appurtenances was awarded in July 1967 and 
completed in July 1971. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. However, local interests must establish encroachment 
lines downstream of dam to permit efficient reservoir 
operation. State legislation requires establishment of such 
lines. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. 
44B. HANCOCK BROOK LAKE, CT 
Location. Dam is on Hancock Brook in town of Plymouth 
CT, about 3.4 miles above its confluence with Naugatuck 
River. (See Geological Survey map for Waterbury, CT). 
Existing project. For description of completed improvements 
and authorizing legislation see Annual Report for 
1975. Cost of new work for completed project was $1,595,000 
for construction and $2,585,000 for lands and damages 
including relocation of roads and railroads, a total of 
$4,180,000. Project is complete. Construction of dam and 
appurtenant structures was initiated in July 1963 and 
completed in August 1966. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. However, local interests are specifically required 
to establish encroachment lines downstream of dam to 
permit efficient reservoir operation. Fully complied with. 
Operations during fiscal year. Maintenace: Ordinary 
operation and maintenance activities. 
44C. HOP BROOK LAKE, CT 
Location. Damsite is on Hop Brook in city of Waterbury 
and towns of Middlebury and Naugatuck, CT, about 1.4 
miles upstream of confluence of Naugatuck River and 
Hop Brook. (See Geological Survey map for Waterbury, 
CT). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report for 
1975. Latest approved cost estimate for new work is 
$2,708,100 for construction and $3,450,000 for lands, rightsof-
way, and relocation of roads, a total of $6,158,100. 
Total includes $125,000 for recreation facilities. Project is 
complete except for construction of additional recreational 
facilities. Construction of dam and appurtenant structures 
was initated in December 1965 and completed in December 
1968. Construction of a public use facility was completed 
in November 1973. Construction of an additional restroom 
was completed in 1980. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. However, local interests must establish encroachment 
lines downstream of dam to permit efficient reservoir 
operation. State legislation requires establishment of such 
lines. Fully complied with. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. 
44D. HOUSATONIC RIVER, 
PITTSFIELD, MA 
Location. The city of Pittsfield is located in Berkshire 
County, approximately 6 miles east of the Massachusetts- 
New York border and about 40 miles northwest of 
Springfield, Massachusetts, where the confluence of the 
East and West Branch Housatonic Rivers from the 
headwaters of the main stream. 
Existing project. Supplement the existing 8 foot high 
by 15 foot wide stone arch culvert under the Penn Central 
Railroad embankment with a new 15 foot diameter pipe 
culvert. Construct an improved channel by clear cutting 
the existing stream bank extending about 2,000 feet 
upstream from the railroad culvert. The total estimated 
cost is $665,000 of which $85,000 is non-Federal cost. (See 
Table 1-B at end of chapter for Act authorizing existing 
project). Construction was initated in November 1982 and 
is 85 percent completed. 
Local cooperation. Local interests are required to provide, 
without cost to the United States, all lands, easements, 
rights-of-way, utility relocations or alterations, highway 
or highway bridge construction; hold and save the United 
States free from damages due to construction, operation 
and maintenance of the project, except where such damages 
are due to fault of the United States or its contractors; 
maintain and operate the project after completion without 
cost to the United States in accordance with regulations 
prescribed by the Secretary of the Army; prevent future 
encroachment which might interfere with proper functioning 
of the project for flood control. Formal assurances have 
been provided. 
Operations during fiscal year. New work: A contract in 
the amount of $386,000 awarded in September 1982, for 
construction of the local protection project, is scheduled 
for completion in November 1983. The contract earnings 
this fiscal year were $312,130. 
44E. NORTHFIELD BROOK 
LAKE,CT 
Location. Dam is is on Northfield Brook about 1.3 miles 
upstream from its confluence with Naugatuck River, in 
1-21

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
town of Thomaston, CT. (See Geological Survey map for 
Thomaston, CT). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report for 
1975. Cost of new work for completed project was $1,856,000 
for construction and $975,000 for lands and damages, 
including roads and utility relocations, a total of $2,831,000. 
An estimate of $30,000 for recreation facilities to be 
constructed. Project is complete. Construction of dam 
and appurtenances was initiated in May 1963 and completed 
in October 1965. Construction of recreation facilities was 
initiated in November 1966 and completed in August 1967. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. However, local interests must establish encroachment 
lines downstream of dam to permit efficient reservoir 
operation. Fully complied with. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. Contract for water 
distribution system for the picnic and swimming areas 
was completed in April 1983; contract costs were $8,374. 
44F. SQUANTZ POND, NEW 
FAIRFIELD, CT 
Location. New Fairfield is located in western Connecticut 
adjacent to the New York-Connecticut state line and 
immediately north of the city of Danbury, Connecticut. 
Squantz Pond is the westernmost of the Candlewood lakes 
located in New Fairfield and the adjacent communites of 
Sherman, New Milford, Brookfield and Danbury. 
Existing project. Provides for a timber bulkhead varying 
in height up to 4 feet above the beach surface and constructed 
3" X 12" pressure treated timbers. The below 
grade portion of the bulkhead would be back filled with 
gravel and provided with sand on the beach side. The 
total cost was $115,363. (See Table 1-B at end of chapter 
for Act authorizing existing project). Project is complete. 
Local cooperation. Local interests would provide, 
without costs to the United States, all lands, easements, 
rights-of-way and utility relocations necessary for project 
construction; hold and save the United States free from 
damages due to the construction, operation and maintenance 
of the project, except where such damages are due to 
the fault or negligence of the United States or its 
contractors; maintain and operate the project after 
completion without cost to the United States. 
Operations during fiscal year. New work: Work on 
contract, awarded in September 1981, for emergency bank 
stabilization was completed in November 1982. Contract 
earnings were $55,690. 
44G. THOMASTON DAM, CT 
Location. On Naugatuck River about 30.4 miles above its 
junction with Housantonic River and about 1.6 miles north 
of Thomaston, CT. Reservior extends upstream about 6.4 
miles.(See Geological Survey map for Thomaston, CT). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report for 
1975. Cost of new work for completed project was $6,382,000 
for construction and $7,900,000 for lands and damages, 
including highway, railroad, and utility relocations, a total 
of $14,282,000. Project is complete. Construction of dam 
and appurtenant works was started in May 1958 and 
completed in November 1960. 
Local cooperation. Section 3, Flood Control Act of 1944 
applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activites. A contract in the 
amount of $18,700, for replacement of the emergency 
generator, was awarded in February 1983 and completed 
in July 1983. 
45. ISLAND AVENUE, QUINCY, 
MA 
Location. The City of Quincy is located on the coast, 
approximately ten miles southeast of Boston. Island 
Avenue extends along the east side of Quincy Bay on the 
western slope of Great Hill in the Houghs Neck section of 
Quincy. The erosion site is directly south of the Nut 
Island peninsula where the Metropolitan District Commission 
(MDC) Nut Island wastewater treatment plant is 
situated. 
Existing project. Provides for riprap revetment along a 
256-foot long reach of shoreline, roadway and main trunk 
sewer line against a 100-year coastal storm event. Total 
project cost is $171,027. (See Table 1-B at end of chapter 
for Acts authorizing existing project). Project is complete. 
Local cooperation. Local interests must provide lands, 
damages and rights-of-way; hold and save Federal government 
harmless; and operate and maintain upon project 
completion. Formal assurances have been provided. 
Operations during fiscal year. New work: A contract 
awarded in September 1982 for construction of emergency 
shoreline protection project was completed in June 1983. 
Contract earnings were $101,597. 
46. ISLESBORO (THE NARROWS), ME 
Location. The town of Islesboro is an island, located in 
the west-central section of Penobscot Bay about three 
miles east of Lincolnville and about 30 miles south of 
Bangor. The island is about 10 miles long and the project 
is located at the center of the island in a location known as 
The Narrows. 
Existing project. Provides for shoreline erosion protection 
extending along about 325 feet adjacent to Main 
Road which connects the two halves of the island by 
placement of stone slope protection. The current estimated 
project cost is $188,000. (See Table 1-B at end of chapter 
for Acts authorizing existing project). A contract for project 
construction was awarded in September 1983. 
Local cooperation. Local interests must provide without 
cost to the United States all lands, easements, rightsof-
way and utility relocations necessary for project 
construction; maintain and operate the project after con- 
1-22

NEW ENGLAND DIVISION 
struction without cost to the United States; prevent future 
encroachment which might interfere with proper functioning 
of the project; and assume the responsibility for all 
costs in excess of the Federal cost limitation of $250,000. 
Operations during fiscal year. New work: Contract plans 
and specifications were completed and a construction contract 
in the amount of $121,000 was awarded in September 
1983. Hired labor costs were $26,847. Construction work 
should be underway in November 1983 
47. JOHNSON BAY, LUBEC, ME 
Location. The town of Lubec is located in the Maine 
Eastern Coastal Area. It is the easternmost community in 
the continental United States, situated on Holmes Bay 
adjacent to Campobello Island, Canada. It is approximately 
25 miles northeast of Machias, ME and 25 miles 
southeast of Calais, ME. 
Existing project. The emergency bank protection provides 
for removal of the existing timber bulkhead and 
installation of approximately 250 linear feet of steel sheet 
piling to raise the existing ground up to the shoulder of 
Commercial Street. This would provide adequate protection 
for the 250 feet of shoreline, including the shoulder 
of the road. Cost of new work for completed project was 
$105,100. (See Table 1-B at end of chapter for Act authorizing 
existing project). Project is complete except for 
extension now underway. 
Local cooperation. Fully complied with. 
Operations during fiscal year. New work: A contract 
was awarded in September 1983, in the amount of $41,510, 
for construction of extension of shoreline protection project. 
There were no contract earnings in current fiscal year. 
48. PORT 5 FACILITY, 
BRIDGEPORT, CT 
Location. The Naval Veterans Post 5 Facility is located 
in the city of Bridgeport in coastal southwestern Connecticut, 
specifically on a peninsula extending from the right 
bank at the mouth of Cedar Creek and facing south toward 
Black Rock Harbor and Long Island Sound. 
Existing project. Provides for protection of Naval 
Veterans property against further shoreline erosion from 
wave action by placement of 250 linear feet of graded 
riprap slope protection. The current estimated project 
cost (September 1983) is $170,000. (See Table 1-B at 
end of chapter for Acts authorizing existing project). 
Construction has not been initiated. 
Local cooperation. Local interests must provide 
without cost to the United States all private lands, 
easements, rights-of-way and utility relocation necessary 
for project construction; maintain and operate the project 
after completion without cost to the United States; prevent 
future encroachment which might interfere with proper 
functioning of the project; and assume responsibility 
for all project costs in excess of the Federal limitation 
of $250,000. 
Operations during fiscal year. New work: A reconnaissance 
report and contract plans and specifications were 
completed. Contract bids were being solicited at year end. 
Hired labor costs were $27,705. 
49. TRUMBULL LAKE, CT 
Location. On the Pequonnock River in the town of 
Trumbull, Fairfield County, in southwestern Connecticut 
about 4 miles north of Bridgeport. (See Geological Survey 
Map for Long Hill, CT). 
Existing project. Concrete gravity dam about 915 
feet long with maximum height of 129 feet. A chute 
spillway will be incorporated in the eastern end of the 
structure. Dam will impound a multiple-purpose reservoir 
with total storage of 13,850 acrefeet. Of total storage 
capacity, 6,080 acre-feet equivalent to 8 inches of runoff 
from its drainage area of 14 square miles will be allocated 
to flood control, 5,850 acre-feet for water supply, 1,350 
acre-feet for low flow augmentation and 510 acre-feet 
dead storage. Latest approved cost estimate (1983) for 
new work is $8,940,000 for lands including relocations 
and $15,185,000 for construction, a total of $24,125,000. 
Lack of suitable earthfill material within reasonable distance 
of the site necessitated change from rolled earthfill 
to concrete gravity dam for more economical design. 
(See Table 1-B at end of chapter for Act authorizing 
existing project). Project is inactive. 
Local cooperation. Local interests are required to repay 
all the costs allocated to water supply, as determined by 
the Chief of Engineers, in accordance with the provisions 
of the Water Supply Act of 1958, as amended, presently 
estimated at $15,700,000 exclusive of interest; pay or 
repay one-half separable first costs allocated to recreation 
and fish and wildlife presently estimated at $0 due to 
reduction of recreational development to only minimum 
facilities, and administer, operate and maintain, including 
replacement, recreation and fish and wildlife lands and 
facilities, all in accordance with the Federal Water Project 
Recreation Act; protect channels downstream of the reservoirs 
from encroachments which would adversely affect 
operation of the system; at least annually notify interests 
affected that project will not provide complete flood protection; 
hold and save the United States free from all 
damages due to water rights claims resulting from construction 
and operation; and exercise to the full extent of 
their legal capability, control against removal of streamflow 
made available by reservoir storage for low-flow augmentation. 
Estimated cost to local interests is $15,700,000. 
Recreational development has been reduced to a minimum 
as a result of state's action not to support same. The 
State of Connecticut, by letter dated 17 October 1972 
withdrew previous assurances and support of the project. 
Operations during fiscal year. At the request of local 
and State officials, a review of the economic feasibility of 
the authorized project was accomplished. This review 
determined that the project, based on current cost and 
benefit estimates, has a benefit-to-cost ratio of less than one. 
1-23

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
50. MERRIMACK RIVER BASIN, 
NH AND MA 
Works covered by comprehensive plan are on Merrimack 
River and its tributaries in New Hampshire and Massachusetts. 
Flood Control Act of 1936 authorized construction 
of a system of flood control reservoirs in Merrimack 
River Basin for reduction of flood heights in Merrimack 
Valley. Flood Control Act of 1938 approved general comprehensive 
plan for flood control and other purposes as 
approved by Chief of Engineers pursuant to preliminary 
examinations and surveys authorized by Act of June 22, 
1936, and modified project to provide in addition to construction 
of a system of flood control reservoirs, related 
flood works which may be found justified by the Chief of 
Engineers. All operations pertaining to flood control in 
Merrimack River Basin are now carried on under and 
reported under projects for individual units of comprehensive 
plan referred to above. No further expenditures are 
contemplated under general project for flood control in 
Merrimack River Basin. For final cost and financial summary, 
see Annual Report for 1946. 
A comprehensive plan for development of water 
resources of the North Nashua River Basin, a principal 
tributary of the Merrimack River, was authorized by 
1966 Flood Control Act substantially in accordance with 
Senate Document 113, 89th Congress. Plan provides for 
construction of coordinated system in four reservoirs and 
three local protection projects for flood protection, water 
supply, recreation and allied purposes. 
The 1966 Flood Control Act also authorized construction 
of Saxonville local protection project substantially in 
accordance with Senate Document 61, 89th Congress. An 
emergency bank protection project at Amesbury, MA 
was authorized under authority provided by Section 14 of 
the 1948 Flood Control Act. (See Table 1-N at end of 
chapter for reservoirs and related flood control works 
included for construction under comprehensive plan). 
50A. BLACKWATER DAM, NH 
Location. Dam is on Blackwater River, NH, 8.2 miles 
above confluence with Contoocook River and 118.8 miles 
above mouth of Merrimack River. It is in the town of 
Webster, just above village of Swetts Mills, 12.5 miles by 
highway northwest of Concord, NH. (See Geological Survey 
maps for Penacook and Mount Kearsarge, NH). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report for 
1975. Cost of new work for completed project was $767,000 
for construction and $553,000 for lands and damages, a 
total of $1,320, 000. Total includes an estimated $80,000 
for construction of public use facilities. Project is complete 
except for construction of public facilities. Construction 
of dam and appurtenant works was initiated in 
May 1940 and completed in November 1941. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. 
50B. EDWARD MACDOWELL 
LAKE, NH 
Location. Dam is on Nubanusit Brook, a tributary of 
Contoocook River, one-half mile upstream from village of 
West Peterborough, NH and 14 miles east of Keene, NH. 
(See Geological Survey map for Peterboro and Manadnock, 
NH). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report for 
1975. Completed cost of project was $1,708,300 for construction 
and $306,000 for lands and damages, a total of 
$2,014,300. Project is complete. Construction of dam and 
appurtenant works was initiated in March 1948 and completed 
in March 1950. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. 
50C. FRANKLIN FALLS DAM, NH 
Location. Dam is on Pemigewasset River, NH, main 
tributary of Merrimack River, and about 22 miles 
upstream of Franklin, NH. (See Geological Survey maps 
for Penacook and Holderness, NH). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report for 
1975. Cost of new work for completed project was $6,190, 
500 for construction and $1,760,000 for lands and damages, 
total of $7,950, 500. Project is complete. Construction 
of dam and appurtenant works was initiated in 
November 1939 and completed in October 1943. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. A contract awarded 
in September 1983 for removal of debris and sediment is 
scheduled for completion in fiscal year 1984. 
50D. HOPKINTON-EVERETT LAKES, 
NH 
Location. Hopkinton Dam is on Contoocook River, NH, 
17.3 miles above its junction with Merrimack River and 
3 miles above its junction with Merrimack River and 
about one-half mile upstream from village of West 
Hopkinton. Everett dam is on Piscataquog River, NH, 16 
miles above its junction with Merrimack River and about 
1.3 miles southeast of village of East Weare. Two 
interconnecting canals were provided to enable the two 
reservoir areas to function as one. (See Geological Survey 
map for Hillsboro, NH, and Concord, NH). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report for 
1975. Cost of new work for completed project was 
$12,715,400 for construction and $8,737,000 for lands and 
damages, including relocating of roads, railroads, cemeteries, 
and utilities a total of $21,452,400. Project is complete. 
1-24

NEW ENGLAND DIVISION 
Construction of two dams and appurtenant works was 
initiated in November 1959 and completed in December 
1962. Construction of recreation facilities was initiated in 
November 1974 and completed in September 1975. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. Local interests must also bear 50 percent of future 
recreational-development in accordance with 1965 Federal 
Water Project Recreation Act. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. A contract awarded 
in April 1983 for road repairs at Elm Brook Park was 
completed in September 1983. The contract amount was 
$27,025. A contract in the amount of $21,212 to repaint 
the flood control gates at Hopkinton Dam awarded in 
September 1982 was completed in August 1983. 
51. NEW BEDFORD, FAIRHAVEN, 
AND ACUSHNET, MA 
Location. Main harbor barrier is across New Bedford 
and Fairhaven Harbor in vicinity of Palmer Island. 
Supplemental dikes and walls are provided in Clark Cove 
area of New Bedford and Fairhaven. (See Geological survey 
maps for New Bedford North, New Bedford South, Marion, 
and Sconticut Neck, MA and National Ocean Survey 
Charts 13230, 13070 and 13218). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report for 
1975. Cost of completed project is $17,997,900 for 
construction, and $616,500 for lands, rights-of-way and 
relocations, a total of $18,614,400. This total includes 
local costs of $590,560 for lands and relocations and a 
$6,513,763 cash contribution. Project is completed. 
Construction of barrier and appurtenances was initiated 
in October 1962 and completed in January 1966. Construction 
of the pumping station was initiated in October 
1962 and completed in June 1964. 
Local cooperation. Local interests had to contribute 30 
percent of first cost, including lands and rights-of-way; 
contribute capitalized value of annual maintenance and 
operation ($1,520,000) for main harbor barrier; hold the 
United States free from damages; and maintain and operate 
improvement except main harbor barrier after completion. 
Total costs for all requirements of local cooperation were 
$7,014,323. Local requirements fully complied with. 
Operations during fiscal year. Maintenance: Twelve 
new axle and wheel assemblies were procured for the 
Sector Gates that close off the main 150-feet wide 
navigational channel at a cost of $71,469. Contract installation 
of these assemblies was accomplished at a cost of 
$123,435. The stop gates are currently being rehabilitated 
under the same contract at a cost of $94,350. The emergency 
generator has been automated and sound-proofed 
at a cost of $41,950. Fence renovations have been completed 
at a cost of $21,105. Operating costs included; 
$97,272 for Project Operations; $8,608 Administration 
Activities; $39,711 Engineering and Design; $19,395 
preparation of contract drawings and specifications; and 
$52,284 for contract supervision and inspection. 
52. NEW LONDON, CT 
Location. In the city of New London, CT, about 45 
miles southeast of Hartford, CT, and 50 miles southwest 
of Providence, RI. (See Geological Survey map for New 
London, CT). 
Existing project. The hurricane protection project 
consists of approximately 715 feet of rockfaced earth-fill 
dike and 800 feet of I-walls around the northerly shore of 
Shaw Cove and the regrading of approximately 21 acres of 
land along the west shore of the Cove to elevation 12.5 feet 
mean sea level. Top of dike and floodwalls will be 14.5 feet 
mean sea level. Appurtenant structures will include a 
street gate, pressure conduit and a pumping station to 
discharge interior drainage. Latest estimate (September 
1983) for the project is $10,360,000 for construction and 
$1,140,000 for lands and damages including relocations, a 
total of $11,500,000 for new work. Total includes local 
costs of $1,140,000 for lands and relocations and a $2,310,000 
cash contribution. (See Table 1-B at end of chapter for Act 
authorizing existing project). Project is under construction 
and is approximately 85 percent complete. 
Local cooperation. Local interests must: (a)Provide lands 
and rights-of-way for construction; (b) make alterations 
and relocations; (c) bear 30 percent of construction cost 
with credit allowed for (a) and (b); (d) hold the United 
States free from damages; and (e) maintain and operate 
all works. Estimated costs to local interests are $1,140,000, 
for lands and relocations and a cash contribution of 
$2,310,000, a total of $3,450,000. Assurances have been 
provided. 
Operations during fiscal year. New work: A contract, 
awarded in September 1981, for Part III constructionpressure 
conduit was completed in November 1982. Total 
contract earnings were $1,109,381. Another contract, 
awarded in May 1982 for Part IV - Dikes and Walls, is 
scheduled for completion in fiscal year 1984. Earnings to 
date were $673,500. 
53. SAINT JOHN RIVER BASIN, 
ME 
Comprehensive plan for water resources development 
within the basin was comprised of the multiple-purpose 
Dickey and Lincoln School Reservoirs on the upper Saint 
John River. Projects were authorized by Flood Control 
Act of 1965 substantially in accordance with plans included 
in report of Department of Interior and Corps of Engineers 
dated August 1964 which is supplement to July 1963 
report of International Passamaquoddy Tidal Power Project 
and Upper Saint John River Hydroelectric Power Development. 
*The Dickey Dam component of the project was 
deauthorized by P.L. 97-128 on 29 December 1981. Local 
protection project at Fort Kent authorized by Chief of 
Engineers on 25 September 1975 Flood Control Act. (See 
Table 1-F at end of chapter for authorized multiple-purpose 
projects including power). 
1-25

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
53A. DICKEY-LINCOLN SCHOOL 
LAKES, ME 
Location. On Upper Saint John River near village of 
Dickey, ME, about 340 miles north of Boston, MA. (See 
Geological Survey map for Allagash, ME). 
Existing project. Plan consists of Dickey and Lincoln 
school Reservoirs functioning as a single coordinating 
unit. Dickey Dam, on Saint John River immediately above 
its confluence with the Allagash River, would consist of 
two rolled earthfill embankments about 10,200 feet total 
length with maximum height of 335 feet. Five earthfilled 
perimeter dikes acting in conjunction with the dam would 
impound a reservoir with total capacity of 7,700,000 acrefeet 
of which 2,900,000 acre-feet would be actively utilized 
for power and flood control purposes. Reservoir area at 
maximum operating level is 86,000 acres and its upper 
reaches extend into the Canadian Province of Quebec. 
Power facilities would be provided at the dam consisting 
of 4 units at 190,000 kilowatts each, one of which would be 
a reversible unit, for total of 760,000 kilowatts. The outlet 
works would include two 25 foot diameter tunnels; a low 
level diversion tunnel at streambed elevation and an intermediate 
level tunnel approximately 110 feet above streambed. 
A chute-type spillway with 600-foot long curved crest 
would be located between the two embankments. Drainage 
area controlled is 2,725 square miles. Basic provisions 
would be included in the initial project to accomodate 
future installation of two additional 190,000 kilowatt reversible 
units at Dickey. Provisions include excavation of 
forebay and tailrace channels, constructoin of headworks 
and powerhouse foundation, and increasing the height of 
Lincoln School Dam. Lincoln School Dam, 11 miles downstream 
from Dickey Dam, would consist of an earthfill 
embankment, a powerhouse in the right abutment, and a 
gated spillway structure between the embankment and 
powerhouse. Overall length would be 2,100 feet and maximum 
height 90 feet. Power facilities would include two 
30,000 kilowatt units and one 10,000 kilowatt unit for a 
total 70,000 kilowatts. Concrete spillway structure would 
be 294 feet long and contain four 60-by-50-foot taintor 
gates. A public highway would be constructed across the 
dam and spillway. The reservoir would have 32,450 acrefeet 
of usable storage for regulation of Dickey Dam discharges, 
power pondage and afterbay storage for the Dickey 
pumpback operations. Drainage area above Lincoln School 
is 4,086 square miles. Approved estimate (October 1981) 
for new work is $67,110,000 for land including relocations 
and $727,890,000 for construction, a total of $795,000,000. 
(See Table 1-B at end of chapter for Act authorizing 
existing project). Deauthorization of the Dickey Dam component 
was recommended by the Congress and enacted 
into law on December 29, 1981. At the direction of Congress, 
a study was conducted to determine the engineering, 
economic and marketability feasability of a Lincoln School 
only project. 
Local cooperation. No local cooperation requirements 
were stipulated in the authorizing document. 
Operations during fiscal year. New work: The study of 
the economic and financial feasibility of a Lincoln School 
only project was completed. The report, now under Washington 
level review, concludes that while the project is 
questionably feasible economically, it is not feasible financially 
at this time. Estimate (October 1982) for a Lincoln 
School only project is $183,000,000. 
54. BAGADUCE RIVER, 
CASTINE, ME 
Location. The town of Castine is located along the 
northeast side of Penobscot Bay in Hancock County about 
30 miles south of Bangor and 10 miles east of Belfast. The 
town forms the southern end of a peninsula that juts into 
Penobscot Bay where the Penobscot and Bagaduce Rivers 
converge. The specific project location is at historic Fort 
Pentagoet along the Bagaduce River at Castine Harbor. 
Existing project. Provides for protection against further 
shoreline erosion of the archeological remains of Fort 
Pentagoet by the placement of stone slope protection 
along 200 linear feet of shoreline. The current estimated 
project cost is $125,000. (See Table 1-B at end of chapter 
for Act authorizing existing project). A contract for project 
construction was awarded in September 1983. 
Local cooperation. Local interests must provide without 
cost to the United States all lands, easements, rights-ofway 
and utility relocations necessary for project construction; 
maintain and operate the project after completion 
without cost to the United States; prevent future 
encroachment which might interfere with proper functioning 
of the project; and assume responsibility for all costs 
in excess of the Federal cost limitation of $250,000. 
Operations during fiscal year. New work: Contract plans 
and specifications were completed and a construction 
contract in the amount of $76,990 was awarded in 
September 1983. Hired labor costs were $28,360. Construction 
should be underway in early November 1983. 
55. SEBASTICOOK RIVER, 
HARTLAND, ME 
Location. Hartland is situated on the Sebasticook River 
in Somerset County, approximately 50 miles west of Bangor 
and 30 miles north of Augusta, ME. 
Existing project. Provides for a system of earth dikes 
and floodwalls to protect a major tanning company, removal 
of the Right Mill Dam and construction of an earth dike 
across the bypass channel to protect residential and 
commercial properties, and construction of a water supply 
pipeline to ensure continued fire protection and process 
water. Estimated project cost is $1,500,000. Construction 
contract was awarded in September 1982. (See Table 1-B 
at end of chapter for authorizing legislation). 
Local cooperation. Local interests must provide without 
cost to the United States all lands, easements and rights-ofway 
necessary for project construction; hold and save the 
United States free from damages due to construction or 
maintenance of the project; prevent future encroachment 
which might interfere with proper functioning of the project 
for flood control purposes including no new construction 
1-26

NEW ENGLAND DIVISION 
between the Great Moose Lake Dam and Main Street 
below elevation 240 feet NGVD. Formal assurances have 
been provided. 
Operations during fiscal year. New work: A contract 
awarded in September 1982 for construction of the local 
protection project is scheduled for completion in November 
1983. The contract amount is $1,295,000. 
56. STONINGTON HARBOR, ME 
Location. The town of Stonington in Hancock County 
is the southernmost of two municipalities located on Deer 
Isle at the eastern boundary of Penobscot Bay approximately 
90 miles east of Portland and 40 miles south of 
Bangor, ME. (See National Ocean Survey Charts 13315 
and 13308). 
Existing project. Provides for an access channel 10 feet 
deep extending from deep water in Deer Isle Thoroughfare 
525 feet for a width of 100 feet, narrowing to 60 feet in 
width for a length of 275 feet, for a total length of 800 feet; 
and an anchorage basin 10 acres in size, of which 3 acres 
would be dredged to a depth of 8 feet mean low water and 7 
acres dredged to a depth of 6 feet mean low water. The 
current estimated cost (September 1983), all Federal, is 
$700,000. (See Table 1-B at end of chapter for Act 
authorizing existing project). Project construction has 
not been initiated. 
Local cooperation. Local interests must provide without 
cost to the United States all necessary lands, easements 
and rights-of-way required for construction and subsequent 
maintenance of the project including suitable dredged 
material disposal areas with necessary retaining dikes, 
bulkheads and embankments therefor; provide, maintain 
and operate without cost to the United States an adequate 
public landing with provisions for the sale of motor fuel, 
lubricants and potable water open and available to the use 
of all on equal terms; accomplish without cost to the 
United States alterations and relocations as required in 
sewer, water supply, drainage and other utility facilities; 
provide and maintain berths, floats, piers, and similar 
marina and mooring facilities as needed for transient and 
local vessels as well as necessary trailer facilities, access 
roads, parking areas and other needed public use shore 
facilities open and available to all on equal terms; and 
establish regulations prohibiting the discharge of untreated 
sewage, garbage, and other pollutants in the waters of the 
harbor users thereof. 
Terminal facilities. There are presently no public shore 
facilities in Stonington Harbor. There are several private 
commercial piers and wharves where Stonington fishermen 
currently offload. There also are two municipally-owned 
docks which are only accessible at higher stages of the 
tide. 
Operations during fiscal year. New work: The Detailed 
Project Report completed in the prior year was approved 
for construction in April 1983. Plans and specifications 
were completed and contract bids were received. Contract 
award was pending at fiscal year end. Construction funds 
were provided from the Productive Employment Appropriations 
Act of 1983. Hired labor and contract costs of 
$124,499 were incurred for preconstruction planning. 
57. STAMFORD, CT 
Location. In Fairfield County on north shore of Long 
Island Sound, about 30 miles east of New York City and 
20 miles southwest of Bridgeport, CT. (See Geological 
Survey map for Stamford, CT). 
Existing project. For description of completed improvement 
see Annual Report for 1974. Latest approved estimate 
for new work is $12,590,000 for construction, and $1,880,000 
for lands and damages and relocations, a total of 
$14,470,000. Total includes local costs of $1,183,000 for 
lands and damages and a cash contribution of $4,030,000 
(See Table 1-B at end of chapter for Act authorizing 
existing project). Project was completed in 1969. Local 
interests still owe a substantial amount based on recent 
claims settlements, including interest payment under the 
Contract Disputes Act. 
Local cooperation. Local interests will provide lands, 
easements, and rights-of-way; make modifications to 
existing storm drainage system which may be required to 
obtain full benefits or protection plan,all necessary 
modifications to existing sanitary sewer facilities required 
to prevent entry of tidal-waters, and all changes, alterations 
and additions to or relocations of any buildings and utilities 
made necessary by construction of project; bear 30 percent 
of total first cost, estimated at $4,340,000 and consisting 
of cost items listed above plus a cash contribution estimated 
at $3,150,000; contribute in cash, in lieu of cost of annual 
maintenace and operation of tidal portion of East Branch 
barrier which is to be operated and maintained by the 
United States, an amount estimated at $880,000; maintain 
and operate all works after completion with exception of 
tidal portion of East Branch barrier and aids to navigation; 
and hold the United States free from damages. Assurances 
received and cash contributions have been deposited except 
for $662,000 outstanding which is local share of final 
claims settlement including interest payment. 
Operations during fiscal year. New work: Interest 
payment of $121,000 was made on settled claims pursuant 
to Contract Disputes Act of 1978. Maintenance: Ordinary 
operation and maintenance activity. A contract was 
awarded in September 1983 for gate realignment. Work 
will be accomplished next fiscal year. 
58. THAMES RIVER BASIN, CT, 
RI, AND MA 
Works covered by this plan are a series of dams and 
reservoirs on tributaries of Thames River in Massachusetts 
and Connecticut, within a radius of 45 miles from Norwich, 
CT, and a channel enlargement on Shetucket River where 
it discharges into Thames River at Norwich, Flood Control 
Act of August 18, 1941, approved plan for a system of 
reservoirs and channel improvements in Thames River 
Basin in accordance with House Document 885, 76th 
Congress, 3rd session, and authorized $6 million for 
1-27

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
initiation and partial accomplishment of project. Flood 
Control Act of December 22,1944, authorized completion 
of approved plan. Flood Control Act of July 14, 1960, 
authorized project for West Thompson Reservoir, substantially 
as recommended in Senate Document 41, 86th 
Congress, 2nd session. (See Table 1-0 at end of chapter on 
reservoirs and local protection districts, Thames River 
Basin, for projects comprising approved plan). 
58A. BUFFUMVILLE LAKE, MA 
Location. Dam is on Little River, 1.3 miles above its 
junction with French River and 8 miles northeast of 
Southbridge, MA. Reservoir extends upstream about 1.7 
miles northerly and 1.9 miles southerly. (See Geological 
Survey maps- Webster, MA and CT, and Leicester, MA). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report of 
1975. Cost of new work for completed project was $2,157,600 
for construction and $841,000 for lands and damages 
including highway relocations, a total of $2,998,600. Project 
is complete. Construction of dam and appurtenant works 
was initiated in September 1956 and completed in June 
1958. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. A contract awarded 
in June 1983 to repair Davis Road is scheduled for 
completion in November 1983. The contract amount is 
$24,348. Another contract, awarded in September 1982, to 
repair the access road and parking area was completed in 
May 1983 at a cost of $15,266. 
58B. EAST BRIMFIELD LAKE, MA 
Location. Dam is on Quinebaug River, 64.5 miles above 
its confluence with Shetucket River and 1 mile southwest 
of village of Fiskdale, MA. (See Geological Survey maps- 
Whales, MA and CT, Southbridge, MA and CT, East 
Brookfield, MA, and Warren, MA). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report for 
1975. Cost of new work for completed project was $1,337,000 
for construction and $5,720,000 for lands and damages 
including highway relocations, a total of $7,057,000. Project 
is complete. Construction of dam and appurtenant works 
was initiated in May 1958 and completed in June 1960. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. 
58C. HODGES VILLAGE DAM, MA 
Location. Dam is on French River, 15 miles above its 
confluence with Quinebaug River, at Hodges Village in 
town of Oxford, MA, about 5 miles north of Webster, MA. 
(See Geological Survey maps for Webster, MA, and CT, 
Leicester, MA, Worcester South MA, and Oxford, MA). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report for 
1975. Cost of new work for completed project was $1,317,100 
for construction and $3,144,000 for lands and damages 
including highway, railroad, and utility relocation, a total 
of $4,461,100. Project is complete. Construction of dam and 
appurtenant works, initiated in March 1958, was completed 
in December 1959. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. Local interests must also bear 50 percent of future 
recreational development in accordance with 1965 Federal 
Water Project Recreation Act. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activites. 
58D. MANSFIELD HOLLOW LAKE, 
CT 
Location. Dam is at Mansfield Hollow, CT, on Natchaug 
River, 5.3 miles above its confluence with Willimantic 
River. It is 4 miles northeast of city of Willimantic, CT. 
(See Geological Survey maps for Spring Hill and Willimantic, 
CT). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report for 
1975. Cost of new work for completed project was $4,108,000 
for construction and $2,340,000 for lands and damages, a 
total of $6,448,000. Project is complete. Construction of 
dam, initiated in 1949, was completed in May 1952. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. 
58E. WEST THOMPSON LAKE, CT 
Location. Dam is on Quinebaug River in town of 
Thompson, CT. Site is in village of West Thompson, 2 
miles upstream from city of Putnam, CT. (See Geological 
Survey map, Putnam, CT). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report for 
1975. Cost of new work for completed project was $5,008,200 
for construction and $1,965,000 for lands, damages and 
road relocations, a total of $6,973,200. Total includes 
$58,000 for recreation facilities. Project is complete. 
Construction of dam, road relocation, and appurtenances 
was initiated in August 1963 and completed in May 1976. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. A contract awarded 
in May 1983 for water line extensions with hydrants was 
completed in August 1983. The contract amount was 
$13,685. 
1-28

NEW ENGLAND DIVISION 
58F. WESTVILLE LAKE, MA 
Location. Dam is on Quinebaug River, 56.7 miles above 
its confluence with Shetucket River, in towns of Sturbridge 
and Southbridge, MA, and 1.3 miles west of center of 
Southbridge. (See Geological Survey maps-Southbridge, 
MA and RI, and East Brookfield, MA). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report for 
1975. Cost of new work for completed project was $2,285,000 
for construction, and $3,400,000 for lands and damages 
(including relocation of highways, utilities, cemeteries, 
and structures), a total of $5,685,000. Project is complete. 
Construction of dam and appurtenant works was initiated 
in April 1960 and completed in August 1962. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. 
59. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
In accordance with provisions of the flood control Act 
of 1936, as amended, local flood protection works constructed 
with Federal funds are transferred to local interests 
to operate and maintain. To insure compliance with regulations 
prescribed for their operation and maintenance, 
regular inspections of the following projects were made 
during the fiscal year. 
CONNECTICUT: May 1983-Ansonia, Derby, East Hartford, 
Pawcatuck, Stamford, New London; May 1983- 
Hartford; April 1983-North Canaan, Torrington, Winsted, 
Salisbury; May 1983-Danbury, East Branch, Hall Meadow, 
Mad River, Norwalk, Sucker Brook, Waterbury, 
Wethersfield; July 1983-Colchester. 
MAINE: April 1983-Fort Kent, Blaine; May 1983-Beals, 
Cherryfield, Indian Island, Harpswell, Lubec, Whiting. 
MASSACHUSETTS: April 1983-Alford, Lancaster, Lee, 
Sheffield, West Warren, Worcester; October 1982 and April 
1983-Haverhill, Lowell; May 1983-Amesbury, Blackstone, 
Canton, Chicopee Falls, Fitchburg, Gardner, Hayward 
Creek, Scituate, Smelt Brook, Three Rivers, Ware; October 
1982 and May 1983-Chicopee, Holyoke, Northampton, 
Springfield, West Springfield; November 1982 and May 
1983-Charles River Dam, Saxonville. 
NEW HAMPSHIRE: May 1983-Nashua; April 1983- 
Charlestown, Lincoln, Shelburn, Wilton; May 1983-Farmington, 
West Stewartstown; September 1983-North Stratford. 
RHODE ISLAND: May 1983-Upper and Lower Woonsocket. 
VERMONT: April 1983-Weston. 
60. FLOOD CONTROL 
RESERVOIR OPERATIONS 
A coordinated system of reservoirs, many of which are 
multipurpose in nature and all containing significant 
amounts of storage for flood control purposes, has been 
established in five major flood producing basins in New 
England. During periods of floodflows, regulation of 
reservoirs is fully coordinated within each basin dependent 
upon its location in the watershed, its available storage 
capacity and origin of flood. In addition to flood control 
releases, water supply and flow augmentation releases 
were made from selected reservoirs. Operation of Corps 
flood control reservoirs in New England accounted for 
$3.5 million in damages prevented FY1983. 
During the months of March through May 1983, New 
England experienced above normal and in some cases 
record amounts of rainfall. Total precipitation for these 
three months amounted to between 50 and 60 percent of 
the average annual precipitation for many locations; 
however, because of the relatively small amount of snow 
on the ground after March 1st, no significant flooding 
occurred. Nevertheless, releases from Corps reservoirs 
were throttled on several occasions during this period in 
anticipation of storms. 
The only event during this time in which floodflows 
were prevented occurred in late March. Nearly 5 inches of 
rain fell over much of New England during the last 2 
weeks of March resulting in bankfull conditions on the 
Ashuelot, Westfield, Farmington, Merrimack and Piscatquog 
Rivers. Because of the operation of Corps reservoirs 
on these rivers, however, significant damages were 
prevented. Additionally, because of continued regulation 
on the Farmington River, potential agricultural losses 
along the banks of the river were minimized in late April 
and May. 
Connecticut River Basin 
During the unusually heavy spring rainfall, flood control 
storage rose to 68 percent at Colebrook 48 percent at 
Knightville, 32 percent at Littleville and 26 percent at 
Surry Mountain. The Colebrook amount represents 
reservoir elevation of 747.1 feel NGVD, the highest level 
experienced at the project. 
Regulation for canoe activities occurred at Ball Mountain 
- October 1982 and May 1983, Knightville - April 1983 
and June 1983, Littleville - April 1983, Birch Hill - April 
1983 and Tully - April 1983. Water supply and fishery 
releases were made at Colebrook Lake throughout the 
year. 
Thames River Basin 
Peak storage utilized at projects in this basin ranged 
from 22 percent at Hodges Village and Westville to 38 percent 
at Mansfield Hollow in April 1983. 
Other regulation activities of Corps projects in the basin 
were: Mansfield Hollow - releases for canoe races in June 
and raising of reservoir level for canoe races in September; 
Westville and East Brimfield - regulation to combination 
river cleanup and canoe races in April; and West Thompson 
- raising of pool level to accomodate AKC retriever trials 
on several occasions during FY83. 
Merrimack River Basin 
Peak storage capacities utilized by reservoirs in the 
basin ranged from 14 percent at Franklin Falls in April 
1983 to 31 percent at MacDowell during March 1983. 
1-29

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Housatonic River Basin 
Regulation of reservoirs in the Naugatuck River basin 
during March and April resulted in peak storages ranging 
from 10 percent of total at Hall Meadow to 29 percent at 
Hop Brook. 
Blackstone River Basin 
West Hill Dam in the Blackstone River basin utilized 30 
percent of flood storage capacity during March 1983. 
61. HURRICANE BARRIER 
OPERATIONS 
Four hurricane barriers situated along the southern 
coast of New England protect coastal communities from 
tidal flooding associated with hurricanes or severe coastal 
storms. The Corps operates the navigational elements of 
the Stamford, Connecticut and New Bedford-Fairhaven, 
Massachusetts barriers. The Fox Point, Rhode Island and 
Pawcatuck, Connecticut barriers are operated by the local 
communities. A brief resume of operations for the fiscal 
year follows: 
Stamford Barrier. The barrier gates were operated on 9 
occasions for coastal storms, however, all operations were 
marginal in nature and no flood benefits were realized 
from the closures. 
New Bedford-Fairhaven Barrier. On 5 occasions the 
barrier gates were closed. The operations were also marginal 
in nature with no flood benefits associated with the 
closures. 
Fox Point and Pawcatuck Barriers. There were no operations 
at these barriers during fiscal year. 
62. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
(See Table 1-E at end of chapter). 
63. FLOOD CONTROL WORK 
UNDER SPECIAL 
AUTHORIZATION 
Flood control activities pursuant to Section 205, Public 
Law 858, 80th Congress, as amended (preauthorization). 
(See Table 1-J at end of chapter). 
Snagging and clearing activities pursuant to Section 
208 of the 1954 Flood Control Act. 
None 
Emergency Bank Protection activities pursuant to Section 
14 of 1946 Flood Control Act. 
Fiscal year costs were as follows: 
Androscoggin River, Bethel, ME 
Androscoggin River, Brunswick, ME 
Bagaduce River, Castine, ME 
(See Section 54 of Text) 
Broad Sound, Winthrop, MA 
Connecticut River, Rockingham, VT 
$7,246 
2 
Covered Bridge, Sheffield, MA 11,982 
Island Avenue, Quincy, MA 126,562 
(See Section 45 of Text) 
Islesboro Island, ME 26,848 
(See Section 46 of Text) 
Johnson Bay, Lubec, ME 13,728 
(See Section 47 of Text) 
Mill River, Northampton, MA 5,000 
Mill River, Williamsburg, MA 4,500 
Nonnewaug River, Woodbury, CT 27,285 
Penobscot River, Old Town, ME 6,959 
Port 5 Facility, Bridgeport, CT 27,705 
(See Section 48 of Text) 
Salmon River, Colchester, CT 13,274 
(See Section 43L of Text) 
Saxtons River, Rockingham, VT 35,842 
(See Section 43M of Text) 
Squantz Pond, New Fairfield, CT 59,915 
(See Section 44F of Text) 
West Branch, Westfield River, 
Huntington, MA 62,523 
(See Section 43R of Text) 
Emergency flood control activities - repair, flood fighting, 
and rescue work. (Public Law 99, 84th Cong., and 
antecedent legislation). 
Federal costs for fiscal year were $111,219 for disaster 
preparedness; $65,368 for emergency operations and $9,173 
for Rehabilitation Work in Ansonia, CT 
Streambank Erosion Control Evaluation and Demonstration 
Act of 1974 as amended in 1976 (Section 32 of the 
Water Resources Development Act of 1974. P.L. 93-251). 
Costs for fiscal year were $10,522 for demonstration 
project proposals. Total cost to 30 September 1983 
were $1,204,996. 
64. DEAUTHORIZED PROJECTS 
(See Table 1-G at end of chapter). 
General Investigations 
65. SURVEYS 
Costs for the fiscal year for surveys from regular funds 
were $1,861,274 of which $165,559 was for navigation 
surveys; $491,293 for flood damage prevention studies; 
$200,961 for coordination studies; $327,446 for special 
studies; $471,533 for comprehensive studies; $203,933 for 
review of completed projects and $549 for supplemental 
pre-authorization studies. 
66. COLLECTION AND STUDY OF 
BASIC DATA 
65,700 The Division Engineer is the U.S. member on Saint 
X8,359 Croix River Board of Control. Annual inspections are 
made of conditions on the Saint Croix River and a 
4,200 continuing program of compilation of basic hydrologic 
5,800 information is carried out. Division Engineer's representa- 
1-30

NEW ENGLAND DIVISION 
tives during the past year kept closely in touch with 
developments in the basin and cooperated with their 
Canadian counterparts assisting in development of basins' 
resources. Total costs for the fiscal year were $11,935. 
Total costs to 30 September 1983 were $144,371. 
Flood plain studies comprise compilation and dissemination, 
upon responsible local request, of information on 
floods and potential flood damages, including identification 
of areas subject to inundation by floods of various 
magnitudes and frequencies, and general criteria for 
guidance in use of flood plain area; and engineering advice 
to local interests for their use in planning to ameliorate 
flood hazard. Total costs for the fiscal year were $152,207. 
Total costs to 30 September 1983 were $4,440,648. 
Total costs for continuation of Planning and Engineering 
was $215,157 of which $137,396 was for Channels and 
Harbors and $77,761 for local protection. 
Total costs for the National Program of Inspection of 
Dams for the fiscal year were $17,630 for inspection. No 
costs were incurred for inventory. 
67. ADVANCE ENGINEERING 
AND DESIGN 
Advance engineering and design costs were $41,407 for 
the navigation project at Bristol Harbor, RI (See Section 
5 of Text). 
1-31

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 1-A COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY80 FY81 FY82 FY83 Sept. 30, 1983 
1. Aquatic Plant 
Control 
2. Black Rock 
Harbor, CT 
3. Boston Harbor, 
MA 
4. Bridgeport Harbor, 
MA 
5. Bristol Harbor, 
Bristol, RI 
6. Buttermilk 
Bay Channel, MA 
(Contributed 
Funds-Required) 
7. Cape Cod Canal, 
MA 
8. Chatham (Stage) 
Harbor, MA 
9. Clinton Harbor, 
CT 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint 
Approp. 
Cost 
Minor rehab. 
Approp. 
Cost 
Major rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
7,000 
6,582 
10,000 
5,584 
5,000 
9,793 
10,000 
2,093 
175,496 
167,499 
- - - 1,426,000 1,426,000 
- - - 1,244,713 1,244,713 
- - - - 25,313,0831 
- - - - 25,313,0831 
74,675 82,023 834,128 1,858,677 9,341,0622 
13,941 143,195 815,704 1,822,960 9,285,1832 
65,378 
63,856 
100,000 
83,452 
40,931 
44,406 
75,000 
89,372 
- - 4,491,11938 
- - 4,491,11938 
45,906 100,000 1,918,88240 
40,710 104,430 1,918,06940 
13,288 
21,892 
1,654 
1,654 
386 
8,575 
55,000 
29,799 
95,000 
14,363 
60,500 
238,288 
238,288 
1,654 
1,654 
86,676 
61,475 
130,21428 
49,57728 
60,500 
- 53,000 100,000 -9,000 32,786,7504, 5 
- 45,368 22,793 75,308 32,786,2194,s 
3,049,400 3,185,120 4,816,821 4,541,756 69,268,065 
2,532,814 3,149,829 3,965,408 5,043,968 68,247,652 
- - - - 390,677 
- - - - 390,677 
6,850,000 9,240,000 7,475,000 874,000 26,609,000 
6,800,607 9,437,523 7,426,768 930,549 26,594,562 
15,558 
15,558 
22,352 
22,352 
36,623 
6,334 
6,700 
23,479 
33,130 215,100 
22,280 222,200 
- 266,70546 
- 266,7054 
9,511 1,391,4930 
22,341 1,390,813W 
-6,000 
-2,250 
104,957 
104,957 
706,834 
706,834 
1-32

NEW ENGLAND DIVISION 
TABLE 1-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY80 FY81 FY82 FY83 Sept. 30, 1983 
10. Connecticut River New Work 
below Hartford, 
CT 
11. Corea Harbor, 
Gouldsboro, ME 
12. Fall River 
Harbor, MA 
Contributed 
Funds 
(Other) 
13. Fore River, 
Braintree & 
Weymouth, MA 
(Contributed 
Funds-Required) 
14. Gloucester Harbor 
& Annisquam Rvr.,MA 
15. Great Salt Pond 
Block Island, RI 
16. Green Harbor, 
MA 
(Contributed 
Funds) 
17. Guilford Harbor, 
CT 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
1,541,18510,11 
1,541,18510,11 
83,500 790,000 906,650 2,011,524 12,661,34012 
226,380 589,547 815,033 695,246 11,047,50312 
- - - - 60,000 
- - - - 60,000 
30,000 
25,511 
11,005 
30,332 
125,605 
2,050 
26,939 
11,216 
25,000 
34,075 
325,000 
294,647 
27,941 
27,941 
380,000 214,967 
88,845 478,120 
200,000 
212,183 
27,915 
27,915 
275,000 
80,076 
36,221 
36,221 
58,000 193,000 -15,000 
35,352 198,742 -11,314 
25,153 
25,152 
250,000 
94,372 
4,584 141,907 
4,584 141,547 
3,680 
3,680 
11,135 
11,135 
3,999 226,499 
3,999 220,531 
-6,9 
282,000 
204,257 
4,000 
110,0 
167,2 
74,455 
771,374 
743,266 
73,150 
73,150 
6,367,72614 
6,149,09114 
2,028,234s15 
2,028,234's 
37,200 
37,200 
360,739 
325,280 
25,153 
25,153 
250,000 
168,827 
1,296,934" 
1,296,934w 
26,241 1,359,397 
26,357 1,359,153 
-4,000 
1,967 
189,03717 
189,03717 
523,154 
523,153 
88 - - 254,512 
-70 - - 254,512 
00 34,392 305,561 1,297,758 
04 31,535 272,598 1,239,044 
- - 168,000 
73 - - 158,342 
56,900 649,693 
25,281 681,312 
- 137,2224 
- 137,2224 
49,653 1,213,685 
49,653 1,213,685 
1-33

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 1-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY80 FY81 FY82 FY83 Sept. 30, 1983 
18. Harbor of Refuge. New Work 
Block island,- Rl - 
19. Harbor of Refuge 
and Point Judith Pond, 
Point Judith, RI 
20. Housatonic River, 
CT 
21. Island End River, 
Chelsea, MA 
(Contributed Funds- 
Required) 
(Other Contributed 
Funds) 
22. Kennebunk River, 
ME 
23. Mystic River, 
MA 
24. New Haven 
Harbor, CT 
25. Newburyport 
Harbor, MA 
26. Norwalk Harbor, 
CT 
Approp. 
Cost 
Maint 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
743 
743 
21,000 
30,558 
14,222 
14,222 
22,611 
22,611 
75,000 
34,927 
314,500 
779,000 
90,000 
22,876 
65,120 
57,738 
-
31,530 
31,530 
2288,,881188 
135,000 
169,624 
286,893 
50,000 
775,035 
99,400 
166,710 
- 1,018,542 
- 1,009,340 
488,703 
650,976 
40,613 
43,727 
2,141,000 
741,961 
91,588 
111,641 
589,668 
589,732 
60,500 
1,185,231 
1,155,078 
1,075,600 
8,066 
7,776 
88,810 
362,522 
-3,000 
4,381 
2,463,926 
722,522 
11,660 
11,660 
-19,150 
-11,143 
27,607 
53,965 
61,740 
57,095 
50,132 
9,148 
2,678,304 
2,437,301 
697,825 
680,448 
-2,000 
675 
576,856 
576,856 
1,311,186 
1,311,185 
2,714,51057 
2,714,51057 
3,898,465 
2,157,061 
1,926,000 
1,926,000 
859,69158s, 5s9 
859,6918ss,s59 
2,316,354 
2,316,354 
311,850 
311,850 
314,500 
314,500 
829,000 
829,000 
350,334n 
350,33427 
875,629 
870,929 
3,222,777 
3,222,777 
1,915,545 
1,865,359 
4,205,24622 
4,205,24622 
12,012,58923 
11,688,83523 
565,225 
565,225 
4,058,961 
4,027,659 
1,415,524 
1,415,524 
531,12981 
531,12981 
3,640,781w 
3,640,781w 
1-34

NEW ENGLAND DIVISION 
TABLE 1-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY80 FY81 FY82 FY83 Sept. 30, 1983 
27. Patchogue New Work 
River, CT 
(Contributed Funds- 
Required) 
28. Portsmouth Harbor 
and Piscataqua 
River, ME and NH 
29. Saco River, 
ME 
30. Sakonnet Harbor, 
RI 
31. Sesuit Harbor, MA 
(Contributed 
Funds-Required) 
36. Cliff Walk, Newport 
RI 
(Contributed 
Funds) 
- Oakland Beach, 
Warwick, RI 
(Contributed 
Funds) 
37. Sherwood Island 
State Park, 
Westport, CT 
(Contributed 
Funds-Required) 
38. Willard Beach, 
South Portland, ME 
42A. Pawtuxet River, 
Warwick, RI 
42B. West Hill Dam, 
MA 
Approp. 
Cost 
Maint 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
61,719 
61,719 
130,747 
130,461 
-6,199 
45,410 
-43,162 
9,894 
39,000 
36,804 
2,032 
53,288 
55,315 
25,000 
38,348 
11,274 
11,424 
50,000 
33,656 
18,000 
11,903 
49,000 395,000 
30,233 416,515 
- 215,000 
- 170,382 
28,000 130,000 
16,525 139,192 
50,000 85,000 
46,105 81,236 
- 60,000 
- 32,498 
149,000 
333,118 
183,600 
174,244 
-1,242 
-1,242 
4,276 
4,276 
240,000 
34,785 
40,464 
40,714 
-7,824 
14,866 
114,824 
120,829 
106,000 
104,005 
230,000 
79,533 
-8,092 
44,618 
160,000 
48,612 
596,000 
40,000 
38,940 
80,000 
89,094 
187,000 
185,689 
65,000 215,000 
25,298 175,298 
85,000 603,188 
16,293 534,481 
88,518 188,518 
- 100,000 
- 5,384,0433 
- 5,384,4033 
2,200 1,043,845 
1,894 1,043,282 
15,000 1,069,983 
211,293 1,056,790 
- 1,496,371 
316 1,496,371 
- 764,65421 
- 764,65121 
43,000 180,016 
43,000 180,016 
-10,817 226,306 
-8,145 226,306 
18,588 124,588 
20,583 124,588 
- 520,4911s 
6,500 376,524's 
- 955,237 
- 955,237 
-10,800 559,200 
-132 558,988 
- 215,000 
- 215,000 
682,000 1,186,830 
795,670 1,186,829 
- 968,802 
516,528 889,330 
50,000 225,000 
3,834 170,115 
770,000 910,000 
635,554 757,146 
- 2,306,902** 
- 2,306,902** 
150,650 2,065,534 
168,669 2,065,453 
1-35

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 1-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY80 FY81 FY82 FY83 Sept. 30, 1983 
42C. Charles River 
(Natural Valley) 
Storage Areas), MA 
43A. Ball Mountain 
Lake, VT 
43B. Barre Falls Dam, 
MA 
43C. Birch Hill Dam, MA 
(Contributed 
Funds) 
43D. Colebrook River 
Lake, CT 
43E. Conant Brook 
Dam, MA 
43F. Knightville Dam, 
MA 
43G. Littleville Lake, 
MA 
43H. North Hartland 
Lake, VT 
43I. North Springfield 
Lake, VT 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
985,000 1,033,000 1,100,000 615,000 8,150,000 
1,303,469 1,037,653 1,119,443 567,600 8,081,250 
- - 221,000 
- - 60,336 
465,500 274,500 254,000 
355,720 368,174 270,347 
16,000 11,034,9626 
176,430 11,034,72853 
256,800 3,928,939 
255,273 3,917,664 
- - - - 1,967,819 
- - - - 1,967,819 
176,500 234,300 247,200 243,000 2,613,027 
173,823 219,729 254,804 243,211 2,598,303 
- - - - 4,815,67941 
- - - - 4,815,67941 
193,000 234,900 298,000 278,400 3,089,927 
220,530 253,331 239,837 328,596 3,077,148 
- - - - 32,00030 
- - - - 32,00030 
- - - - 14,263,971 
- - - - 14,263,971 
219,800 207,200 176,000 111,500 1,551,544 
196,652 165,219 219,707 129,544 1,539,103 
- - - - 2,950,530 
- - - - 2,950,530 
47,800 
48,119 
60,800 
57,866 
58,000 
54,872 
48,000 
54,350 
813,680 
813,518 
- - - - 3,415,64044 
- - - - 3,415,64044 
237,000 368,400 606,100 231,200 3,695,504 
229,493 271,722 622,331 305,915 3,661,028 
- - - - 7,013,412 
- - - - 7,013,412 
237,900 212,600 221,800 222,000 2,260,091 
242,928 222,372 213,191 216,117 2,236,484 
1,000 
1,000 
483,400 
226,211 
- - - 7,312,22550 
- - - 7,312,22550 
185,500 256,000 229,600 2,863,115 
422,311 272,950 232,025 2,854,121 
- - - - 7,312,22525 
- - - - 7,312,22525 
582,600 297,700 296,000 270,300 3,991,097 
335,301 518,041 313,424 280,799 3,971,826 
1-36

NEW ENGLAND DIVISION 
TABLE 1-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY80 FY81 FY82 FY83 Sept. 30, 1983 
43J. Otter Brook New Work 
Lake, NH 
43K. Park River, 
Hartford, CT 
(Other Contributed 
Funds) 
43L. Salmon River, 
Colchester, CT 
43M. Saxtons River, 
Rockingham, VT 
43N. Surry Mountain 
Lake, NH 
430. Townsend Lake, 
VT 
43P. Tully Lake, MA 
(Contributed 
Funds) 
43Q. Union Village 
Dam, VT 
43R. West Branch, 
Westfield, River, 
Huntington, MA 
43S. West Springfield, 
Connecticut River 
Basin, MA 
44A. Black Rock Lake, 
CT 
44B. Hancock Brook 
Lake, CT 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approx. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
188,000 
203,456 
11,455,000 
14,423,500 
183,000 
139,448 
8,000 
7,916 
-3 
103,494 
256,000 
239,695 
294,500 
249,637 
198,400 
225,408 
4,462 
41,786 
182,100 
240,142 
148,000 
138,047 
52,800 
52,269 
210,100 
196,899 
4,365,000 
4,836,262 
26,000 
61,045 
38,000 
30,736 
4,000 
4,028 
211,600 
217,233 
310,000 
286,020 
236,400 
232,818 
183,200 
173,965 
9,387 
9,387 
137,700 
155,370 
73,600 
74,191 
185,000 
48,856 
302,000 
299,122 
281,919 
864,059 
204,000 
194,516 
580,000 
558,862 
422,000 
471,918 
291,000 
265,168 
280,000 
235,444 
20,654 
20,654 
162,500 
163,710 
61,000 
56,261 
13,000 
148,619 
352,300 
341,681 
75,000 
67,401 
-2,900 
13,273 
127,500 
35,842 
364,000 
369,268 
235,000 
241,188 
244,500 
256,745 
204,700 
241,811 
85,000 
62,523 
215,000 
58,510 
192,200 
186,989 
61,500 
65,798 
4,358,44843 
4,357,92352 
2,623,314 
2,596,021 
59,951,919 
59,876,741 
246,000 
234,993 
247,100 
246,441 
127,500 
35,842 
2,833,61033 
2,833,61033 
3,428,143 
3,398,868 
7,398,41349 
7,398,41349 
3,641,571 
3,624,098 
1,666,7527 
1,666,7527 
2,630,086 
2,612,778 
40,00030 
40,00030 
4,095,16051 
4,095,16051 
2,765,856 
2,746,098 
116,034 
93,556 
215,000 
58,510 
8,182,300 
8,182,300 
1,636,609 
1,629,180 
4,178,911 
4,178,911 
818,249 
817,725 
1-37

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 1-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY80 FY81 FY82 FY83 Sept. 30, 1983 
44C. Hop Brook Lake, 
CT 
44D. Housatonic River 
Pittsfield, MA 
44E. Northfield Brook 
Lake, CT 
44F. Squantz Pond, 
New Fairfield, CT 
44G. Thomaston Dam, 
CT 
45. Island Avenue, 
Quincy, MA 
46. Islesboro (The 
Narrows), ME 
47. Johnson Bay, 
Lubec, ME 
48. Port 5 Facility, 
Bridgeport, CT 
49. Trumbull Lake, CT 
50A. Blackwater Dam, 
NH 
50B. Edward MacDowell 
Lake, NH 
50C. Franklin Falls 
Dam, NH 
50D. Hopkinton-Everett 
Lakes, NH 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
8,538 
95,537 
335,900 
256,604 
13,003 
23,221 
100,300 
106,584 
328,300 
322,949 
4,748 - 
307,300 375,500 
320,967 432,924 
- 460,000 
2,534 72,045 
- 20,000 
- 7,039 
93,700 81,000 
88,620 82,780 
89,000 24,000 
31,044 24,404 
219,100 
241,387 
16,000 
12,695 
279,500 
279,613 
116,000 
31,770 
-17,418 
82,027 
167,000 
169,458 
222,500 
206,652 
478,300 
414,820 
334,000 
331,016 
199,900 
215,952 
200,800 
213,344 
320,400 
377,872 
378,600 
325,239 
167,000 
153,854 
199,000 
187,080 
364,000 
277,490 
507,000 
517,152 
- 6,151,56232 
- 6,151,56232 
307,550 2,642,485 
312,547 2,622,999 
67,000 655,000 
384,636 585,051 
- 2,850,512" 
12,961 2,850,512" 
122,500 1,161,911 
118,349 1,153,817 
3,296 116,296 
59,915 115,363 
- 14,282,112 
- 14,282,112 
237,000 3,107,267 
241,314 3,097,123 
40,000 172,000 
126,562 171,027 
195,500 195,500 
26,848 26,848 
75,000 180,082 
13,728 118,810 
32,500 32,500 
27,705 27,705 
35,000 1,498,799 
35,000 1,498,799 
- 1,319,74637 
- 1,319,74637 
224,000 2,242,785 
234,591 2,239,242 
- 2,014,253w 
- 2,014,2533 
171,600 2,656,792 
169,835 2,639,108 
- 7,950,48735 
- 7,950,48735 
438,000 4,140,037 
434,604 4,040,538 
- 21,452,440" 
- 21,452,440" 
533,900 4,678,240 
564,139 4,659,838 
1-38

NEW ENGLAND DIVISION 
TABLE 1-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY80 FY81 FY82 FY83 Sept. 30, 1983 
51. New Bedford, 
Fairhaven, and 
Acushnet, MA 
(Contributed 
Funds) 
52. New London, CT 
(Contributed 
Funds-Required) 
(Other 
Contributed 
Funds) 
53A. Dickey-Lincoln 
School Lakes, ME 
54. Bagaduce River, 
Castine, ME 
55. Sebasticook River, 
Hartland, ME 
56. Stonington Harbor, 
ME 
57. Stamford, CT 
(Contributed 
Funds) 
(Other 
Contributed 
Funds) 
58A. Buffumville Lake 
MA 
58B. East Brimfield 
Lake, MA 
58C. Hodges Village 
Dam, MA 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
- - - - 11,510,088 
- - - - 11,510,088 
111,000 120,700 527,000 509,000 3,010,114 
103,825 114,792 444,272 475,213 2,875,943 
- - - - 6,513,763" 
- - - - 6,513,763" 
2,000,000 
2,345,703 
850,000 
745,451 
665,000 
667,821 
270,000 
51,000 
131,000 
860,000 1,695,000 
1,560,148 1,262,532 
410,000 
523,521 
250,000 
573,505 
83,894 
1,160,000 8,097,046 
1,018,945 7,952,959 
140,000 1,890,00019 
165,095 1,884,25219 
36,008 
131,000 
119,902 
- -100,000 13,155,300 
418,227 85,477 13,130,822 
132,500 
28,359 
160,500 
56,359 
39 
39 
30,000 
54,398 
20,000 573,475 
25,069 171,361 
900,000 1,603,475 
1,242,753 1,544,099 
700,000 
124,499 
2,037,600 
2,027,900 
133,600 
119,902 
- 2,023 
100,600 118,000 
96,314 121,346 
96 - - 
196,400 198,800 207,000 
181,672 213,059 182,146 
150,500 177,800 166,000 
148,218 175,367 160,056 
700,000 
124,499 
121,000 9,911,300 
120,960 9,900,618 
341,000 1,902,372 
150,264 1,693,144 
- 3,367,9704 
- 3,367,453Z4 
- 210,000 
- 209,969 
- 2,998,603' 
- 2,998,6039 
239,000 2,236,922 
253,141 2,225,103 
- 7,057,0438 
- 7,057,0438 
170,000 1,950,583 
179,248 1,948,690 
- - - - 4,461,07342 
- - - - 4,461,07342 
194,900 128,500 168,000 225,300 2,053,798 
179,642 142,947 162,332 203,446 2,022,353 
1-39

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 1-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY80 FY81 FY82 FY83 Sept. 30, 1983 
58D. Mansfield Hollow New Work 
Lake, CT Approp. - - - - 6,447,16416 
Cost - - - - 6,447,16416 
Maint. 
Approp. 234,800 149,500 206,000 203,000 2,466,297 
Cost 228,251 167,188 179,166 228,848 2,462,179 
58E. West Thompson New Work 
Lake, CT Approp. 2,003 - 25,000 3,000 7,001,2204 
Cost 41,421 - 7,812 19,708 7,000,74055 
Maint. 
Approp. 192,000 188,500 257,000 477,800 2,296,698 
Cost 165,364 200,240 252,752 434,456 2,232,586 
58F. Westville Lake, New Work 
MA Approp. - - - - 5,684,68347 
Cost - - - - 5,684,68347 
Maint. 
Approp. 180,500 168,300 229,000 213,000 2,070,796 
Cost 179,818 165,378 224,705 199,653 2,049,493 
1Includes $1,465,123 for previous projects. Includes 
$935,303 emergency relief funds and $1,030,806 public 
works funds. 
2 Includes $17,879 for previous projects. Excludes $17,767 
contributed funds. 
SExcludes $99,707 expended from Contributed Funds and 
includes $130,393 for previous projects. 
SIncludes $6,138,157 from public works funds and 
$4,849,740 from emergency relief funds. Excludes $115,432 
contributed funds. 
s Includes $389,929 Code 711 funds and $412,988 Code 713 
funds. 
6 Includes $499,724 Code 711 funds. 
7 Includes $3,695 Code 711 funds and $115,138 Code 713 
funds. 
8 Includes $208,100 Code 711 funds. 
9 Includes $71,943 Code 711 funds. 
10 Includes $287,374 for previous projects. Excludes 
$130,410 contributed funds. 
11 Excludes $9,000 for subproject "Eightmile River, CT." 
12 Includes $366,348 for previous projects. 
13 Completed except for inactive portion. 
14 Includes $330,204 for previous project. 
15 Includes $81,410 for previous project. 
16 Includes $68,717 Code 711 funds. 
17 Improvement adequate for commerce. 
19 Excludes $22,517 expended to date for land condem.- 
nations. 
20 Includes $83,276 for maintenance of previous project. 
21 Excludes $21,928 expended from contributed funds. 
22 Includes $331,626 for previous projects. Includes 
$290,877 National Industrial Recovery Funds and $59,207 
public works funds. 
23 Includes $32,570 for previous projects. 
24 Cash for construction only. Excludes $199,410 expended 
to date for land condemnations. 
25 Includes $59,536 Code 711 funds. 
26 Includes $66,120 for previous projects. 
27 Includes $88,914 expended from contributed funds. 
28 Includes $35,214 from previous project. 
Cash for construction only. Excludes $164,020 expended 
to date for land condemnation. 
30 Recreational Cost Sharing. 
31 Includes $162,517 for previous project. Excludes 
$34,500 contributed funds expended. 
32 Includes $143,538 Code 711 funds. 
33 Includes $470,077 Code 711 funds. 
34 Includes $179,728 Code 711 funds. 
35 Includes $4,671 Code 711 funds. 
3 Includes $6,432 Code 711 funds. 
37 Includes $2,881 Code 711 funds. 
38 Includes $378,450 for previous project. Excludes 
$147,887 expended from contributed funds. 
39 Includes $18,310 Code 711 funds. 
40 Includes $11,949 for maintenance of previous project. 
41 Includes $618,469 Code 711 funds and $32,000 Code 713 
funds. 
42 Includes $6,255 Code 711 funds and $40,158 Code 713 
funds. 
43 Includes $362,688 Code 711 funds. 
44 Includes $199,304 Code 711 funds. 
45 Excludes $25,000 contributed funds expended. 
SIncludes $7,889 for previous project. 
47 Includes $67,667 Code 711 funds. 
48 Includes $319,503 Code 711 funds. 
49 Includes $245,168 Code 711 funds. 
50 Includes $228,236 Code 711 funds. 
51 Includes $84,462 Code 711 funds. 
52 Includes $362,163 Code 711 funds. 
ss Includes $499,490 Code 711 funds. 
54 Includes $20,000 Code 711 funds. 
55 Includes $313,801 Code 711 funds. 
s5 Includes $21,000 for previous projects and excludes $25,000 
Contributed Funds. 
5 Includes $12,000 for previous project and excludes $17,587 
expended for new work from Contributed Funds. 
" Excludes $222,010 expended from Contributed Funds. 
59 Excludes costs of $137,583 for local cooperation requirements, 
which includes $104,583 cash contribution. 
1-40

NEW ENGLAND DIVISION 
TABLE 1-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
July 3, 1958 
Oct. 23, 1962 
Oct. 27, 1965 
July 3, 1930 
March 2, 1825 
June 14, 1880 
Aug. 5, 1886 
Sept. 19, 1890 
July 25, 1892 
July 13, 1892 
June 3, 1896 
Mar. 3, 1899 
June 13, 1902 
July 25, 1912 
Aug. 8, 1917 
Aug. 30, 19352 
Do. 
August 26, 1937 
Oct. 17, 1940 
Sept. 7, 1940 
Mar. 2, 19453 
July 24, 1946 
July 3, 1958 
Oct. 23. 1962 
AQUATIC PLANT CONTROL (See Section 1 of Text). 
Control and progressive eradication of obnoxious Aquatic Plant 
growths from the waters and streams in the U.S. 
Research and planning costs to be borne by U.S. 
Provided for continued research. 
BLACK ROCK HARBOR, CT 
(See Section 2 of Text). 
Black Rock Harbor 18 feet deep and 100 to 200 feet wide from 
the 18-foot contour in harbor to the heads of both branches of 
Cedar Creek, about 2.4 miles. 
BOSTON HARBOR, MA (See Section 3 of Text). 
Preservation of islands by seawalls. 
Weir River (Nantucket Beach Channel) 9 ft. deep, 100 ft. wide 
to Steamboat Wharf at Nantasket. 
Fort Point Channel. 
Weir River (Nantasket Beach Channel) 91/2 ft. deep, 150 
ft. wide to Steamboat Wharf at Nantasket. 
Weir River (Nantasket Beach Channel)from mouth of 
Weir River to Steamboat Wharf at Nantasket Beach 
12 ft. deep, 150 ft. wide. 
Channel 15 feet deep from Long Island to Nixes Mate 
Shoal (Nixes Mate of Nubble Channel). 
Channel 27 feet from Nantasket Roads to President 
Roads. 
Dredge Chelsea River channel to 18 feet 
For 30-foot channel from sea to President Roads 
through Broad Sound by less direct route than 35 
and 40-foot channels. 
For 35-foot channel from sea to Boston Naval Shipyard, 
Chelsea and Charles River Bridges. 
Elimination from project of removal of Finns Ledge at 
outer entrance. 
Dredge Chelsea River channel 25 ft. 
Depth of 40 feet (45 feet in rock) in Broad Sound 
Channel. 
Present project dimensions of channel from President 
Roads to Commonwealth pier No. 1, East Boston and 
anchorage area north side of President Roads. 
Present project dimensions of that part of approach 
channel to U.S. Navy drydock No. 3, at South Boston 
between Main Ship Channel and U.S. harbor line. 
Chelsea River, channel 30 feet deep 
Reserved channel 30 feet deep. 
Abandons seaplane channel authorized in 1940 River 
and Harbor Act (H. Doc. 262 76th Cong., 1st sess.) 
Extension of 40-foot channel. 
Extension of President Roads anchorage. 
Reserved channel 35 feet deep, 430 feet wide, extending 1 
mile from 40-foot main channel to L St. 
Chelsea River Channel and Maneuvering Basin 35 feet 
deep. 
H. Doc. 37, 85th Cong., 1st sess. 
Public Law 87-874, 87th Cong. 
H. Doc. 251, 89th Cong. 
H. Doc.281, 71st Cong., 2nd sess. 
Annual Report, 1881, p. 518 
H. Ex. Doc. 206, 48th Cong., 2nd sess. 
Annual Report, 1885, p. 543. 
Annual Report, 1890, p. 503. 
Annual Report, 1893, p. 769. 
Annual Report, 1887, p. 517. 
Annual Report, 1893, p. 766. 
H. Ex. Doc. No. 162 53d Cong., 3rd 
sess., Annual Report 1895, p. 648 
H. Doc. 133, 55th Cong., 2nd sess. 
Annual Report, 1898, p. 886. 
H. Doc. 119, 56th Cong. 2nd sess. 
Annual Report, 1901, p. 1096. 
Authorized by Chief of Engineers, 
Mar. 11, 1913 
H. Doc. 272, 62nd Cong. 2nd sess.' 
H. Doc. 931, 63d Cong., 2nd sess.' 
H. Doc. 244, 72nd Cong., 1st sess.' 
Rivers and Harbors Committee 
Doc. 29., 74th Cong., 1st sess.' 
Rivers and Harbors Committee 
Doc. 24, 74th Cong., 1st sess.' 
H. Doc. 225, 76th Cong., 1st sess.' 
Public Law 420, 78th Cong. 
H. Doc. 733 Cong., 2nd sess.' 
H. Doc. 244, 80th Cong., 1st sess.' 
H. Doc 349, 84th Cong.' 
H. Doc. 350, 87th Cong., 2nd sess.' 
1-41

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 1-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
July 4, 1836 
Mar. 3, 1899 
Mar. 2, 1907 
Mar. 2, 1919 
July 3, 193012 
Aug. 26, 1937 
Mar. 2, 1945 
July 24, 1946 
July 3, 1958 13 
August 13, 1968 
July 14, 1960, 
as amended 
CAPE COD CANAL, MA (See Section 7 of Text). 
Jan. 21, 1927(Sec. 2) Purchase canal from Boston, Cape Cod & New York 
Canal Col., in accordance with contract dated July 29, 
1921, executed by that company. 
Included in Public Construct 3 bridges and widen canal to 250 feet 
Works Administration 
program, 
Sept. 6, 1933 
June 26, 1934 (Perma- Operation and care of works of improvement provided 
nent Appropriations for the funds from War Department appropriations for 
Repeal Act). rivers and harbors. 
Included in Public Construct a mooring basin. 
Works Administration 
program 
Apr. 29, 1935. 
Included in EmergencyDredging and bank protection. 
Relief Program, 
May 28, 1935 
Aug. 30, 1935 Existing project for main canal adopted. 
Mar. 2, 1945 
July 3, 1958 
15-foot channel and turning basin in Onset Bay. 
Extend East Boat Basin for an area of about 4.3 acres to 
a depth of 8 feet 
1-42 
BRIDGEPORT HARBOR, CT (See Section 4 of 
Text). 
Fayerweather Island seawall. 
Shore protection of Fayerweather Island 
West breakwater and present project dimensions of 
east breakwater. 
Present project depths of 18-and 12-foot anchorage 
basins. 
25-foot entrance channel, 25-foot anchorage and an 
18-foot channel through Johnsons River, present 
project dimensions of channels through Poquonock 
River, Yellow Mill Pond, Black Rock Harbor and 
Cedar Creek. 
25-foot channel through main harbor, and present 
project location and extent of 18- and 12-foot 
anchorage basins. 
30-foot channel; elimination of 12-foot anchorage. 
30-foot turning basin and 15- and 9-foot channels in 
Johnsons River. 
Present depth and extent of main channel, and turning 
basin south and southeast of Cilco Terminal; Black 
Rock Harbor breakwater; Burr and Cedar Creek 
anchorage. Upper Johnsons River anchorage; lower 
Johnsons River anchorage. 
BRISTOL HARBOR, BRISTOL, RI 
(See Section 5 of Text). 
Construction of a rubblestone breakwater 1,600 feet long 
BUTTERMILK BAY CHANNEL, MA 
(See Section 6 of Text). 
Channel extension 2,500 feet long, dredging only 
upper 300 feet. Mark jurisdictional channel in lower 
2,200 feet of channel. Channel to be 80 feet wide with a 
depth of -6 feet at MLW. 
Annual Report, 1899, p. 1173. 
H. Docs. 275 and 521, 59th 
Cong., 2nd sess. 
H. Doc. 898, 63rd Cong., 2nd sess. 
H. Doc. 281, 71st Cong., 2nd sess. 
H. Doc. 232, 75th Cong., 1st 
sess. 
H. Doc. 819, 76th cong., 3rd 
sess. 
H. Doc. 680, 79th Cong., 2nd 
sess. 4 
H. Doc. 136, 85th Cong. 
H. Doc. 174, 90th cong., 1st sess. 
P.L. 86-645, Sec. 107. 
Authorized by Chief of Engineers, 
April 7, 1983. 
H. Doc. 139, 67th Cong., 2nd 
sess. 
H. Doc. 795, 71st Cong., 3rd 
sess. 
Do. 
Do. 
Do. 
Rivers and Harbors Committee 
Doc. 15, 74th Cong., 1st sess. 
H. Doc. 431, 77th Cong., 1st 
SeSS. 
H. Doc. 168 85th Cong. 1st 
sess.

NEW ENGLAND DIVISION 
TABLE 1-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Mar. 2, 1945 
Aug. 2, 1882 
Mar. 2, 1945 
June 10, 1872 
Mar. 3, 1881 
June 25, 1910 
Feb. 27, 1911 
Mar. 2, 1919 
Aug. 30, 1935 
May 24, 1937 
Mar. 2, 1945 
May 17, 1950 5 
July 14, 1960 
as amended 
Aug. 30, 1935 
July 14, 1960, 
as amended 
July 3, 1930 
July 24, 1946 
Sept. 3, 1954 
Aug. 13, 1968 
July 14, 1960 
as amended 
CHATHAM (STAGE) HARBOR, MA 
(See Section 8 of Text). 
Entrance Channel 10 feet deep, 150 feet wide from Chatham 
Roads into upper harbor. 
CLINTON HARBOR, CT(See Section 9 of Text) 
Maintenance of a stone dike closing a breach in sandy 
peninsula which separates river from outer harbor. 
8-foot channel and anchorage. 
CONNECTICUT RIVER BELOW HARTFORD, CT 
(See Section 10 of Text). 
Jetties at the mou h. 
The Hartford dike. 
Channel and turnin basin in Eight-mile River. 
Present project dimensions of channel over Saybrook bar. 
Dikes, training walls, and revetments 
Present project dimensions of channel and additional 
dikes, training walls, revetments, and accessory works. 
Park River declared nonnavigable. 
Channel and anchorages, North Cove, Old Saybrook 
Channel, anchorage, and turning basin, Eight-mile River. 
Channel and anchorage in Essex Cove. 
Channel and anchorage in Wethersfield Cove. 
COREA HARBOR, GOULDSBORO, ME 
(See Section 11 of Text). 
Anchorage basin 8 feet deep, 600 feet long and 400 feet 
wide. 
Construction of an access channel 8 feet deep and 100 feet 
wide, extending from deep water to existing anchorage 
basin, a distance of approximately 2,000 feet. In addition 
the existing 5.5 acre anchorage would be expanded 3 acres. 
FALL RIVER HARBOR, MA (See Section 12 of Text). 
30-foot channel including Hog Island Shoals, and maintainence 
of 25-foot anchorage. 
35-foot channel and turning basin. 
Deepening mid bay channel to 35 feet for a width of 400 feet 
between deep water in Mount Hope Bay and Globe Wharf. 
Deepening Mount Hope Bay and Tiverton Channels to 40 feet. 
FORE RIVER, BRAINTREE AND WEYMOUTH, MA 
(See Section 13 of Text). 
A channel 6 feet deep with a width from 60 to 100 feet. It 
would begin at the Federal ship channel in Quincy and 
extend 8,000 feet upstream to the Quincy Ave. Bridge. 
H. Doc. 456, 77th Cong., 1st sess. 
Annual Report 1942. 
S. Ex. Doc. 84, 47th Cong., 1st sess. 
H. Doc. 240, 76th Cong., 1st sess. 
Present project dimensions approved 
by Chief of Engineers, Dec. 22, 1887 
Present project dimensions authorized 
by Chief of Engineers in 1889. 
H. Doc. 327, 60th Cong., 1st sess. 
H. Doc. 1294, 61st Cong., 3rd sess. 
H. Doc. 132, 65th Cong., 1st sess. 4 
H. Doc. 49, 73d Cong., 1st sess. 
Ltr. Sec. War, Apr. 21, 1937. 
H. Doc. 368, 76th Cong., 1st sess. 4 
H. Doc. 666, 80th Cong., 2nd sess. 4 
P.L. 86-645, Sec. 107. Authorized by 
Chief of Engineers, October 18,1961. 
P.L. 86-645, Sec. 107. Authorized by 
Chief of Engineers, Nov. 15, 1960. 
Rivers and Harbors Committee, 
Doc. 27, 74th Cong., 1st sess. 4 
P.L. 86-645, Sec. 107. 
Authorized by Chief of Engineers 
August 14, 1981. 
H. Doc. 158, 71st Cong., 2nd sess. 
H. Doc. 628, 79th Cong., 2nd sess. 
H. Doc. 405, 83rd Cong. 
H. Doc. 175, 90th Cong., 1st sess. 4 
P.L. 86-645, Sec. 107. 
Authorized by Chief of Engineers, 
June 4, 1981. 
1-43

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 1-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Aug. 11, 1888 
Aug. 18, 1894 
June 13, 1902 
June 25, 1910 
Aug. 30, 1935 
Mar. 2, 1945 
Oct. 23, 1962 
June 3, 1896 
June 13, 1902 
Mar. 2, 1945 
July 14, 1960, as 
amended 
Mar. 2, 1945 
July 11, 1870 
Aug. 2, 1882 
Aug. 5, 1886 
June 3, 1896 
July 25, 1912 
GLOUCESTER HARBOR AND ANNISQUAM RIVER, 
MA (See Section 14 of Text). 
Remove ledges and boulders, and dredge in 
Gloucester Harbor. 
Construct breakwater at entrance to Gloucester 
Harbor from Eastern Point to Round Rock shoal. 
Termination at Cat Ledge of breakwater authorized 
by Act of Aug. 18, 1894. 
Remove 8 ledges in Gloucester Harbor. 
Dredge in Annisquam River and removal of a ledge in 
Gloucester Harbor near entrance to Annisquam River. 
Dredge 8 foot anchorage area in Lobster Cove, 
Annisquam River. 
Entrance channel into Inner Harbor 20 feet deep, and 
turning basin. Access channel 20 feet deep along 
waterfront to northwest of Gloucester Fish pier. 
Access channel 20 feet deep along waterfront southeast 
of Gloucester Fish pier. 
Access channel 16 feet deep into Smith Cove. 
An access channel 18 feet deep along waterfront west 
of Harbor Cove and into Harbor Cove. 
A 5-acre anchorage 15 feet deep east of entrance to 
Harbor Cove. 
A 10-acre anchorage 16 feet deep opposite entrance to 
Smith Cove. 
Remove isolated rock shoal adjacent to entrance channel 
south of Harbor Cove to a depth of 24 feet. 
GREAT SALT POND, BLOCK ISLAND, RI 
(See Section 15 of Text). 
Channel and jetties. 
Extending south jetty and dredging 
Channel and basin in inner harbor. 
GREEN HARBOR, MA (See Section 16 of Text). 
Channel 6 feet deep, 100 feet wide from deep water to head 
of navigation; anchorage near town pier; sealing, 
rebuilding in part and extension of existing west jetty. 
GUILFORD HARBOR, CT (See Section 17 of Text). 
Entrance channel 100 feet wide, 6 feet deep, a channel 60 
feet wide, 6 feet deep; an anchorage basin 6 feet deep, 
200 feet wide. 
HARBOR OF REFUGE, BLOCK ISLAND, RI 
(See Section 18 of Text). 
The main breakwater. 
Repairs to basin walls and cliff protection east of 
harbor. 
Breakwater inclosing inner harbor. 
Raising crest of main breakwater and making it 
sandtight. 
Rebuilding basin walls and present project dimensions 
of dredged area. 
Annual Report 1902, p. 89 
H. Ex. Doc. 56, 48th Cong., 
2nd sess. and Annual Report 
1885, p. 534. 
Annual Report 1902, p. 89 
H. Doc. 1112, 60th Cong., 
2nd sess. 
Rivers and Harbors Committee 
Doc. 39, 72nd Cong., 1st sess. 
H. Doc. 329, 77th Cong., 1st 
sess. 
H. Doc. 341, 87 Cong., 2nd 
sess. 
H. Doc. 57, 54th Cong., 1st sess. 
Specified in act. Annual Report 
for 1900, p. 1276. 
H. Doc. 330, 77th Cong., 1st sess. 
Section 107, P.L. 86-645. Authorized 
by Chief of Engineers, Dec. 15, 1965. 
H. Doc. 149, 77th Cong., 1st sess. 
Annual Report 1868, p. 785 
and S. Misc. Doc. 81, 40th 
Cong., 2nd sess. 
S. Ex. Doc. 26, 47th Cong., 
1st sess. 
S. Doc. 27, 48th Cong., 2nd 
sess. and Annual Report 
1885, p. 610. 
H. Doc. 83, 54th Cong., 1st 
sess. 
H. Doc. 828, 60th cong., 1st 
sess. 4,5 
1-44

NEW ENGLAND DIVISION 
TABLE 1-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Sept. 16, 1890 
Mar. 2, 1907 
June 25, 1910 
Mar. 2, 1919 
June 30, 1948 
July 14, 1960, 
as amended 
Mar. 3, 1871 
Aug. 11, 1888 
July 3, 1930 
July 14, 1960, 
as amended 
Mar. 2, 1829 
Aug. 14, 1876 
Sept. 19, 1890 
Oct. 23, 1962 
HARBOR OF REFUGE AND POINT JUDITH POND, 
POINT JUDITH, RI(See Section 19 of Text). 
The main breakwater. 
Present dimensions of eastern shore arm. 
Western shore arm. 
Removing 3 shoals from the harbor arm. 
Abandons project for entrance to Point Judith Ponds, and 
authorizes channels and anchorages in lower pond and 
upper pond. 
Extension of existing 15-foot channel. 
HOUSATONIC RIVER, CT (See Section 20 of Text). 
A jetty at Sow and Pigs Rocks and the present project width 
of the channel across the outer bar. 
Breakwater at the mouth and the present project dimensions 
of the river channel above the lower end of Culvers Bar. 
(Enlargement of outer arm of breakwater and extensions of 
Stratford dike not required. 
The Stratford dike. 
Present project dimensions of channel up to Culvers Bar. 
ISLAND END RIVER, CHELSEA, MA 
(See Section 21 of Text). 
A 100-foot wide access channel extending from Mystic 
River for a length of approximately 2500 feet to the site 
of the proposed marina facility and would allow for an 
overall depth of 6 feet. 
KENNEBUNK RIVER, ME (See Section 22 of Text). 
Repair of pier on east side of channel entrance. 
Deepening at Wading Place and Mitchells Point. 
Jetty at Wading Place. 
8-foot channel. 
6-foot channel. 
6-foot anchorage, west side of channel. 
6-foot anchorage, east side of channel. 
Extension of west jetty, and construction of sand fence. 
H. Doc. 66, 51st Cong., 1st sess. 
H. Doc. 60, 58th Cong., 2nd sess. 
H. Doc. 911, 60th Cong., 1st sess. 
H. Doc. 2001, 64th Cong., 2nd sess. 
S. Doc. 15, 80th Cong., 1st sess. 
PL 86-645 Section 107. Authorized by 
Chief of Engineers, Sept. 29, 1976. 
H. Doc. 95, 41st Cong., 3rd sess. pnd 
Annual Report 1871, p. 781 
S. Doc. 103, 50th Cong., 1st sess. and 
Annual Report 1888, p. 554. 
Authorized by Dept. project submitted 
by the District Engineer, July 15, 1892 
H. Doc. 449, 70th Cong., 2nd sess. 4 
P.L. 86-645, Sec. 107. 
Authorized by Chief of Engineers 
April 6, 1981. 
Annual Report, 1875, p. 115 
H. Ex. Doc. 136, 51st Cong., 1st sess. and 
Annual Report 1890, p. 471. 
H. Doc. 459, 87th Cong., 2nd sess. 4 
July 13, 1892 
June 25, 1910 
Aug. 30, 19358 
June 20, 1938 
May 17, 1950 
MYSTIC RIVER, MA (See Section 23 of Text). 
Improve upper Mystic Annual Report, 1891, p. 672. 
Improve channel downstream from mouth of Island End River H. Doc. 1086, 60th Cong., 2nd sess. 
to 35-foot channel of Boston Harbor. 
Improve channel upstream from mouth of Island End River 
to city playground at Charlestown. 
Improve channel upstream from city playground at 
Charlestown to a point 800 feet above Malden Bridge. 
Improve channel from upper limit of 35-foot Boston 
Harbor channel to Malden Bridge. 
Rivers and Harbors Committee, 
Doc. 33, 74th Cong., 1st sess. 
H. Doc. 542, 75th Cong., 
3rd sess. 
H. Doc. 645, 80th Cong., 
2nd sess. 9 
1-45

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 1-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
NEW HAVEN HARBOR, CT (See Section 24 of Text). 
Aug. 2, 1882 
Mar. 3, 1899 
June 25, 1910 
+Julr 25, 1912 
Do. 
July 3, 1930 
Aug. 30, 193510 
Mar. 2, 1945 
July 24, 1946 
Aug. 16, 1949 
Aug. 9, 1955 
June 14, 1880 
June 25, 1910 
Mar. 2, 1945 
Mar, 2, 1919 
Mar. 2, 1945 
Sept. 3, 1954 
July 14, 1960, 
as amended 
Sept. 3, 1954 
Oct. 23, 1962 
Sandy Point dike. Plans approved by a Board of Engineers, 
Oct. 2, 1882. 
The 16-foot anchorage basin. H. Doc. 82, 55th Cong. 1st sess. 
Brewery Street channel, removal of rocks in Morris Cove H. Doc. 1159, 60th Cong., 2nd sess. 
and present project dimensions of 15-foot basin. 
Present project dimensions of channels in Mill River. H. Doc. 26, 62nd Cong., 1st sess. 
Present project dimensions of West River channel and H. Doc. 535 62nd Cong., 2nd sess. 
anchorage. 
18-and 16-foot channels in Quinnipac River. H. Doc. 686, Cong., 2nd sess. 
25-foot channel 
30-foot channel and anchorage and present location 
of 16-foot anchorage. 
35-foot main channel, elimination of 30-foot anchorage, 
present location and extent of 16-foot anchorage and 
22-foot channel and turning basin in Quinnipiac 
River." 
Brewery Street channel declared nonnavigable. 
Abandonment of upper end of West River. 
NEWBURYPORT HARBOR, MA (See section 
25 of Text). 
Construction of rubblestone jetties. 
Dredging the bar at entrance to harbor. 
Dredging channel from sea to wharves and a widened 
turning basin. 
NORWALK HARBOR, CT (See Section 26 of Text). 
South Norwalk and Norwalk channels 10-foot anchorage. H. Doc. No. 1143, 63d Cong., 2nd sess. 
East Norwalk channel widening and anchorage. H. Doc. 220, 76th Cong., 1st sess. 
PATCHOGUE RIVER, CT(See Section 27 of Text). 
8-foot channel from Duck Island Roads to U.S. Route 
bridge, anchorage and maneuvering area, 600-foot 
jetty. 
Widen existing navigation channel to 125 feet in Long 
Island Sound to confluence of Patchogue and 
Menunketesuck Rivers. Maintain depth of 
8-feet MLW. 
PORTSMOUTH HARBOR & PISCATAQUA RIVER, 
ME and NH 
(See Section 28 of Text). 
Removal of ledge rock; widening 35-foot channel; 
extending channel and maneuvering basins above 
Boiling Rock and at head of project 
Modified existing project for widening and extending 
35-foot channel. 
1H. Doc. 164, 83rd Cong., 1st sess. 
P.L. 86-645, Sec. 107. Authorized by 
Chief of Engineers, April 12, 1983. 
Annual Report 1892 H. Doc. 556, 
82nd Cong., 2nd sess. 
H. Doc. 482, 87th Cong., 2nd 
sess. 
1-46 
H. Doc. 479, 72d Cong., 2nd sess. 
H. Doc. 307, 76th Cong., 1st sess. 
H. Doc. 517,79th Cong., 2nd sess. 4 
Annual Report 1910, p. 59. 
H. Doc. 703, 76th Cong., 3rd sess.

NEW ENGLAND DIVISION 
TABLE 1-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Mar. 2, 1827 
June 23, 1866 
Sept. 19, 1890 
June 25, 1910 
Mar. 3, 1925 
Aug. 30, 1935 
July 14, 1960, 
as amended 
July 4, 1836 
March 3, 1899 
March 2, 1907 
Sept. 4, 1954 
July 14, 1960, as 
amended 
July 14, 1960, as 
amended 
Oct. 27, 1965 
Oct. 23, 1962 
SACO RIVER, ME (See Section 29 of Text). 
Extension of piers, placing of buoys, and removal of 
obstructions at entrance to harbor. 
Breakwater on north side of mouth of river. 
Jetty on north side of mouth of river. S. Ex. Doc. 44, 48th Cong., 
1st sess., and Annual Report 
1884, p. 482 
Channel improvements and jetty extension on south side H. Doc. 752, 61st Cong., 2nd sess. 4 
of mouth of river. 
Present project channel dimensions and extensions of 
north breakwater about 1,600 feet. 
Extension of north breakwater to Sharps ledge. 
Anchorage and maneuvering basin. 
SAKONNET HARBOR, RI (See Section 30 of Text). 
Breakwater 
Prolonging old breakwater and raising it to 8 feet above 
mean low water, to width of 15 feet. 
Rock removal near breakwater. 
Breakwater extension and harbor dredging. 
A 500-foot rubble-mound breakwater and a 110-foot 
wide by 10-foot deep navigation channel. 
SESUIT HARBOR, MA (See Section 31 of Text). 
Channel 6 feet deep and 100 feet wide. 
CLIFF WALK, NEWPORT, RI 
(See Section 36 of Text). 
Improvements for shore protection along the Cliff Walk. 
SHERWOOD ISLAND STATE PARK, WESPORT CT 
(See Section 37 of Text). 
Beach erosion control. 
H. Doc. 477, 68th Cong., 2nd sess. 
Rivers and Harbors Committee. 4 
Doc. 11, 74th Cong., 1st sess. 
P. L. 86-645, Sec. 107. Authorized by Chief 
of Engineers, Nov. 14, 1967. 
H. Doc. 154, 20th Cong., 1st sess. 
H. Doc. 81, 55th Cong., 1st sess. 
and Annual Report 1897, p. 934. 
H. Doc 99, 56th Cong., 2nd sess. 
and Annual Report 1901, p. 1148. 
H. Doc. 436, 82nd Cong., 2nd sess. 
P.L. 86-645, Sec. 107. 
Authorized by Chief of Engineers, 
June 25, 1981. 
P.L. 86-645, Sec. 107. Authorized by 
Chief of Engineers, February 6, 1980. 
H. Doc. 228, 89th Cong., 1st sess. 
Section 103 of the 1962 Rivers and Harbors 
Act. Authorized by Chief of Engineers, 
September 30, 1981. 
October 23, 1962 
WILLARD BEACH, SOUTH PORTLAND, ME 
(See Section 38 of Text). 
Placement of suitable sandfill along 1,700 feet of Willard Section 103 of the 1962 Rivers and Harbors 
Beach to a backshore elevation of 13.0 feet above MLW. Act. Authorized by Chief of Engineers, 
Construct one terminal groin structure approx. 200 feet April 19, 1983. 
north of southern limit of beach. 
June 30, 1948, 
as amended 
PAWTUXET RIVER, WARWICK, RI 
(See Section 42A of Text). 
Flood damage reduction through aquisition of land and 
improvements in the flood plain. Demolition and 
removal of acquired structures. Flood proofing certain 
dwellings and installing a flood forecasting system. 
P.L. 858, Sec. 205. 
Authorized by Chief of Engineers, 
June 1982. 
CHARLES RIVER (NATURAL VALLEY STORAGE 
AREAS) MA (See Section 42C of Text). 
Federal acquisition and perpetual protection of 17 Chief of Engineers report dated 
crucial natural valley storage areas totaling 8,422 acres December 6, 1972. 
in what is known as the Middle and Upper watershed of 
the Charles River. 
1-47 
Mar. 7, 1974

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 1-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Aug. 13, 1968 
July 24, 1946, 
as amended 
July 24, 1946, 
as amended 
July 24, 1946, 
as amended 
June 30, 1948, 
as amended 
June 30, 1948, 
as amended 
July 24, 1946, 
as amended 
July 24, 1946, 
as amended 
July 24, 1946, 
as amended 
July 24, 1946, 
as amended 
July 24, 1946, 
as amended 
PARK RIVER, HARTFORD, CT 
(See Section 43K of Text). 
Flood protection on Park River in Hartford, CT 
SALMON RIVER COLCHESTER, CT 
(See Section 43 L of Text). 
Construct 250 feet of "Doublewal" precast concrete block 
slope protection along the right bank of the river 
adjacent to Brown's Mill Road. 
SAXTONS RIVER, ROCKINGHAM, VT 
(See Section 43M of Text). 
Construct about 175 feet of "doublewal" pre-cast concrete 
cells along enbankment slope. Wall would be approx. 
12 feet high. 
WEST BRANCH, WESTFIELD RIVER, 
HUNTINGTON, MA (See Section 43R of Text). 
Riprap slope-one section 100 feet long at the twin 6-inch 
inverted sewer siphon and one section 50 feet long at the 
8-inch gravity sewer line manhole. 
WEST SPRINGFIELD, CONNECTICUT RIVER 
BASIN, MA. (See Section 43S of Text). 
Raise the floodwall section of the West Springfield 
project by 1 foot in combination with a flood forecasting 
system. 
HOUSATONIC RIVER, PITTSFIELD, MA 
(See Section 44D of Text). 
Supplement the existing 8-foot high by 15-foot wide 
stone arch culvert under Penn Central Railroad 
embankment with four 10-foot diameter concrete pipe 
culverts. 
SQUANTZ POND, NEW FAIRFIELD, CT 
(See Section 44F of Text). 
Provide for a timber bulkhead varying in height up to 4 
feet above the beach surface and constructed of 4" x 6" 
pressure timbers. 
ISLAND AVENUE, QUINCY, MA 
(See Section 45 of Text). 
Remove existing debris & fill eroded area with pervious 
fill & grade slope. Slope protected with riprap revetment 
to height of 17 feet above MLW. Above 17 feet, the 
slope covered with 6 inches of seeded top soil. 
ISLEBORO (THE NARROWS), ME 
(See Section 46 of Text). 
Construct graded quarry stone revetment along 325 feet 
of shoreline. Riprap revetment extend above Main 
Road to height of 18 feet MLW. 
JOHNSON BAY, LUBEC, ME (See Section 47 of Text). 
Emergency bank and shoreline protection. 
PORT 5 FACILITY, BRIDGEPORT, CT 
(See Section 48 of Text) 
250 linear feet of graded riprap slope protection. 
S. Doc. 43, 90th Cong., 1st sess. 
P.L. 79-526, Sec. 14. 
Authorized by Chief Engineers, 
September 24, 1980. 
P.L. 79-526, Sec. 14. 
Authorized by Chief of Engineers, 
February 24, 1983. 
P.L. 79-526, Sec. 14. 
Authorized by Chief of Engineers, 
July 17, 1981. 
P.L. 858, Sec. 205. 
Authorized by Chief of Engineers, 
October, 5, 1982. 
P.L. 80-858, Sec. 205. 
Authorized by Chief of Engineers, 
August 1981. 
P.L. 79-526, Sec. 14. 
Authorized by Chief Engineers, 
November, 3, 1980. 
P.L. 79-526, Sec. 14. 
Authorized by Chief of Engineers, 
June 19, 1981. 
P.L. 79-526 Sec. 14. 
Authorized by Chief of Engineers, 
December 7,1982. 
P.L. 79-526, Sec. 14. 
Authorized by Chief of Engineers, 
May 15, 1979. 
P.L. 79-526 Sec. 14 
Authorized by Chief of Engineers, 
May 26, 1983. 
1-48

NEW ENGLAND DIVISION 
TABLE 1-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Nov. 7, 1966 
July 3, 1958 
Oct. 23, 1962 
Oct. 22, 1976 
Oct. 27, 1965 
July 24, 1946, 
as amended 
June 30, 1948, 
as amended 
July 14, 1960, 
as amended 
July 14, 1960 
TRUMBULL LAKE, CT (See Section 49 of Text). 
Multi-purpose dam on Pequonnock River in town of 
Trumbull. 
NEW BEDFORD, FAIRHAVEN AND ACUSHNET, 
MA. (See Section 51 of Text). 
Hurricane barriers in New Bedford Harbor. 
NEW LONDON, CT (See Section 52 of Text). 
Hurricane barrier protecting city of New London from 
tidal damage. 
DICKEY-LINCOLN SCHOOL LAKES, ME 
(See Section 53A of Text). 
Construction of multi-purpose project on the upper St. 
John River to provide for power, flood control and 
recreation. 
BAGADUCE RIVER, CASTINE, ME 
(See Section 54 of Text). 
Placement of approximately 200 linear feet of stone slope 
protection along the shoreline of Castine Harbor adjacent to 
Fort Pentagoet. 
SEBASTICOOK RIVER, HARTLAND, ME 
(See Section 55 of Text). 
Raise concrete wall near left abutment of Great Moose 
Lake Dam. Construct earthfill dikes outward from left 
and right abutments of Great Moose Lake Dam. Clear 
main river channel at base of Great Moose Lake Dam and 
extending downstream to Main Street Bridge. Repair 
sluice gates in lower dams and reconstruct concrete bridge 
abutment approach wall. 
STONINGTON HARBOR, ME 
(See Section 56 of Text) 
Dredge access channel 10 feet deep extending from deep 
water in Deer Isle Thoroughfare 525 feet for a width of 
100 feet, narrowing to 60 feet in width for a length of 275 
feet. An anchorage basin 10 acres in size (3 acres 
dredged to a depth of 8 feet MLW and 7 acres dredged 
to a depth of 6 feet MLW.) 
STAMFORD, CT(See Section 57 of Text). 
Hurricane barrier protecting areas of Stamford from tidal 
damage. 
S. Doc. 115, 89th Cong., 2nd sess. 
S. Doc. 59, 85th Cong., 1st sess. 
H. Doc. 478, 87th Cong., 2nd sess. 
H. Doc. 236, 89th Cong., 1st sess. 
P.L. 79-526, Sec. 14. 
Authorized by Chief of Engineers, 
February 23, 1983. 
P.L. 858, Sec. 205. 
Authorized by Chief of Engineers, 
March 9, 1982. 
P.L. 86-645, Sec. 107. 
Authorized by Chief of Engineers, 
April 7, 1983. 
H. Doc. 210, 86th Cong., 1st sess. 
'Contains latest published maps. See also Annual Report, 
1911, p. 1178 (seawalls and Nixes Mate Channel) and 
Annual report, 1903, p. 770 (Fort Point Channel). 
2Authorized in part by Public Works Administration, Sept. 
6,, 1933. 
3A portion deferred for restudy. 
4Contains latest maps. 
5Inactive. 
6A portion has been abandoned pursuant to P.L. 624, Dec. 
31, 1970. 
7Rock removal at Hog Island Shoal inactive. 
8Also Emergency Relief Act of 1935. 
9Contains latest published map; a map showing entire river 
is in H. Doc. 2108, 64th Cong. 2nd sess. 
l0Also Public Works Administration, Sept. 6, 1933. 
l"Q uinnipiac River 22 foot channel and turning basin 
deferred for restudy. 
12Removal of rock in Yellow Mill Pond inactive-not 
presently required. 
13Black Rock Harbor breakwater; Burr and Cedar Creek 
anchorage inactive. 
1-49

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 1-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to September 30, 1983 
Full Report Contributed 
See Annual Operation and Funds Expended 
Project Report for Construction Maintenance (Construction) 
Andrews River, MA' 1981 $ 219,04215 $ 385,398 $ 187,500 
Apponaug Cove, RI' 1964 156,8742 20,4536 
Bar Harbor, ME5 1932 406,591 2,187 
Bass Harbor, ME6 1965 188,859 13,187 
Bass Harbor Bar, ME' 1920 4,076 12,175 
Beals Harbor, ME' 1959 184,880 26,687 
Belfast Harbor, ME' 1971 61,561 224,449 
Bellamy River, NH', 3,4 1897 34,643 - 
Beverly Harbor, MA' 1951 246,048 16,821 100,000 
Boothbay Harbor, ME' 1953 18,000 22,983 
Branford Harbor, CT' 1978 9,537 975,345 
Bucks Harbor, Machiasport, ME',6 1976 277,420 16,625 
Bucksport Harbor, ME' 1907 18,421 13,593 
Bullocks Point Cove, RI' 1979 170,902 69,343 123,757 
Bunker Harbor, ME' 1969 95,372 28,406 
Camden Harbor, ME' 1960 102,400 125,936 
Canapitsit Channel, MA',4 1899 9,113 12,279 
Cape Porpoise Harbor, ME' 1977 175,037 347,865 20,000 
Carvers Harbor, Vinalhaven, ME' 1964 190,438 9,021 
Cathance River, ME', 3 1884 21,000 - 
Coasters Island Harbor, RI', 4 1911 5,500 13,161 
Cobscook Bay, ME',3 ,4 1866 4,173 - 
Cocheco River, NHI,3,4 1913 119,089 42,617 
Cohasset Harbor, MA' 1979 267,76738 207,196 127,000 
Connecticut River (above Hartford), 
CT8 1932 116,324 15,822 
Cotuit Harbor, MA'8 1962 8,541 - 
Criehaven Harbor, ME' 1939 40,776 8,125 
Cross Rip Shoals Nantucket Sound, 
MA' 1954 24,200 54,328 
Cuttyhunk Harbor, MA' 1978 27,167 943,42025 11,643 
Damariscotta River, ME', 4 1906 5,000 905 
Deer Island Thoroughfare, ME', 4 1916 40,000 - 
Dorchester Bay and Neponset 
River, MA" 1968 94,584 301,944 
Duck Island Harbor, CT' 1953 482,166 370,617 
Duxbury Harbor, MA' 1978 421,297a 794,388 35,00030 
East Boothbay Harbor, ME' 1953 6,500 17,238 
Eastport Harbor, ME' 1979 638,6753* 182,085 
Edgartown Harbor, MA' 1978 65,614s 32,589 10,000 
Essex River, MA' 1948 21,759 83,938 4 
Exeter River, NHI,4 1913 27,454 3,032 
Falmouth Harbor, MA' 1978 123,763 248,454 35,000 
Fivemile River Harbor, CT' 1969 35,490 152,377 
Frenchboro Harbor, ME' 1978 657,345 24,616 
Georges River,ME' 1978 25,788 224,719 
Greenwich Bay, RI' 1893 2,000 6,527 
Greenwich Harbor, CT' 1969 198,758 204,872 100,000 
Hampton Harbor, NH' 1982 200,000 1,446,574 193,761 
Harraseeket River, ME',4 1896 30,963 5,309 
Hay (West Harbor), Fisher's 
Island, NY' 1931 8,401 3,032 
Hendrick's Harbor, ME' 1957 28,204 6,325 
Hingham Harbor, MA' 1954 28,316 90,759 
Housatonic River, CT2 1979 859,691 2,304,694 222,010 
1-50

NEW ENGLAND DIVISION 
TABLE 1-C (Continued) OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to September 30, 1983 
Full Report Contributed 
See Annual Operation and Funds Expended 
Project Report for Construction Maintenance (Construction) 
Hyannis Harbor, MA l ' 
Ipswich River, MA 
Isle Au Haut Thoroughfare, ME 
Isle of Shoals Harbor, ME and NH' 
Jonesport Harbor, ME 
Josias River, ME' 
Kennebec River, ME5 
Kingston Harbor (North Plymouth), 
MA' 
Lagoon Pond, Martha's Vineyard, 
MA', 6 
Lamprey River, NHI,'4 
Little Harbor, NHI, 4,26 
Little Harbor, Woods Hole, MAI, 14 
Lubec Channel, ME' 
Lynn Harbor, MA"9 
Machias River, ME' 
Malden River, MAI,2� 
Matinicus Harbor, ME' 
Medomak River, ME' 
Menemsha Creek, MA l ' 
Merrimack River, MA' 
Mianus River, CT 
Milford Harbor, Ct 
Moosabec Bar, ME' 
Mystic River, CT' 
Nantucket (Harbor of Refuge), MA 
Narraguagus River, ME' 
New Bedford and Fairhaven 
Harbors, MA s 
New Harbor, ME' 
New Haven Breakwater, CT' 
New London Harbor, CT 
Newport Harbor, RI' 
Niantic Bay and Harbor, CT' 
Northeast Harbor, ME' 
Owl's head Harbor, ME Is 3 
Pawcatuck River, RI & CT' 
Pawtuxet Cove, RI' 
Penobscot River, ME' 
Pepperell Cove, ME5 
Pig Island Gut, ME',6 
Pleasant Bay, MA 
Pleasant River, ME' 
Plymouth Harbor, MA' 
Pollock Rip Shoals, Nantucket 
Sound, MA' 
Portland Harbor, ME' 
Potowomut River, RI' 
Providence River & Harbor, RIs 
Provincetown Harbor, MA' 
Red Brook Harbor, Bourne, MA' 
Richmond Harbor, ME',' 
Richmond's Island Harbor, ME',4 
1975 
1969 
1980 
1977 
1981 
1977 
1982 
1895 
1976 
1913 
1977 
1906 
1956 
1956 
1972 
1922 
1962 
1953 
1981 
1940 
1978 
1981 
1930 
1957 
1965 
1969 
1953 
1966 
1950 
1980 
1953 
1972 
1954 
1968 
1978 
1975 
1969 
1969 
1966 
1971 
1892 
1978 
1956 
1982 
1882 
1976 
1979 
1972 
1883 
1882 
484,499 
5,618 
137,653 
80,691 
222,548 
115,565 
1,599,940' 
8,940 
99,098 
19,980 
133,227 
18,000 
380,322 
755,576 
32,000 
104,853 
14,00021 
17,000 
56,92640 
369,891 
132,435 
90,5064' 
11,400 
197,582 
502,66123 
821,144 
1,857,618 
118,620"' 
1,242,246 
638,774"3 
733,524 
66,464 
138,942 
124,158 
318,78721 
295,356 
501,020 
171,351 
191,753 
3,500 
2,127,2182,33 
1,083,504 
9,588,71047 
5,000 
25,417,022"' 
3,548,95442 
38,764 
20,000 
119,844 
1-51 
250,15912 
32,947 
140,747 
643,364 
122,173 
1,770,753 
6,587 
33,563 
257,685 
5,224 
23,941 
178,866 
185,217 
45,097 
8,989 
92,359 
622,346 
158,224 
177,764 
600,287 
25,227 
104,932 
431,854 
33,965 
708,967 
21,705 
40,273 
278,034 
94,768 
65,604 
17,334 
13,867 
591,600 
143,817 
611,187 
18,958 
33,142 
217 
914,270" 
846,590 
7,393,215 
50 
3,755,642 
298,636 
1,808 
103,001 
26,813 
80,990 
62,000 
12,500 
46,500 
11,380 
14,000 
20,385 
7,015 
67,500 
4,383 
20,000 
295,356 
541,611 
760,000

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 1-C(Continued) OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to September 30, 1983 
Full Report Contributed 
See Annual Operation and Funds Expended 
Project Report for Construction Maintenance (Construction) 
Rockland Harbor, ME 1" 
Rockport Harbor, MA' 
Rockport Harbor, MEi, 3 
Royal River, ME' 
Rye Harbor, NH 1' 
St. Croix River, ME 1' 
Sakonnet River, RI1,o 
Salem Harbor, MA5 
Sandy Bay (Harbor of Refuge), 
Cape Ann, MA 8s 
Sasanoa River, ME', 3, 4 
Scarboro River, ME1' 
Scituate Harbor, MA' 
Searsport Harbor, ME1' 
Seekonk River, RI' 
South Bristol Harbor, ME' 
Southport Harbor, CT' 
Southwest Harbor, ME1' 
Stamford Harbor, CT 
Stockton Harbor, ME', 3,4 
Stonington Harbor, CT' 
Stony Creek, Branford, CT' 
Sullivan Falls Harbor, ME 1' 
Taunton River, MA5 
Tenants Harbor,ME1' 
Thames River, CT5 
Union River, ME3,15 
Vineyard Haven, MA' 
Wareham Harbor, MA5 
Warren River, RI' 
Warwick Cove, RI1,6 
Wellfleet Harbor, MA' 
Wells Harbor, ME' 
Westcott Cove, CT' 
Westport Harbor and 
Saugatuck River, CT' 
Westport River, MA 4,9 
Weymouth Back River, MA' 
Weymouth-Fore & Town Rivs., 
Boston Hbr., MA 
Wickford Harbor, RI', 22 
Wilson Point Harbor, CT1,4 
Winnipesaukee Lake, NH' 
Winter Harbor, ME', 6 
Winthrop Harbor, MA' 
Wood Island Harbor, and 
Pool at Biddeford, ME 1' 
Woods Hole Channel, MA' , 
York Harbor, ME 
1 Completed. 
2 Excludes Costs of $137,583 for local cooperation requirements, 
which includes $104, 583 cash contribution. 
3 Abandonment recommended in H. Doc. 467, 69th 
Congress, 1st session. 
4 No commerce reported. 
5 Completed except for inactive portion. 
s Authorized by the Chief of Engineers (Public Law 86- 
645, Sec. 107). 
7 Includes $37,714 emergency relief funds. Excludes 
$18,525 contributed funds, of which $1,785 was for 
work outside approved project. 
1-52 
1976 
1979 
1915 
1977 
1965 
1950 
1909 
1969 
1922 
1915 
1976 
1971 
1966 
1954 
1971 
1962 
1962 
1980 
1915 
1959 
1978 
1914 
1948 
1920 
1967 
1912 
1943 
1896 
1890 
1975 
1981 
1979 
1978 
1972 
1942 
1944 
1979 
1973 
1895 
1952 
1976 
1895 
1957 
1940 
1977 
1,948,462 
22,000 
32,000 
336,704 
130,342 
179,550 
38,427 
1,693,202 
1,925,553 
35,000 
392,635 
379,851 
572,56816 
672,214 
89,593 
96,9277 
180,042 
892,82437 
33,000 
377,328 
112,487 
19,871 
442,895 
18,750 
1,471,919 
146,855 
27,186 
95,997 
5,000 
155,430 
157,6342 
360,973 
55,960 
19,308 
48,740 
29,875,453@ 
233,410 
54,177 
7,500 
162,937 
8,992 
143,112 
230,000 
239,654 
452,800 
194,963 
256,374 
29,368 
36,392 
1,559 
350,923 
16,060 
124 
1,239,293 
107,726 
23,035 
793,234 
11,052 
215,039 
19,574 
1,669,41845 
23,216 
123,060 
248,452 
32,917 
13,292 
1,422,580 
113,939 
8,699 
10,296 
36,594 
857,408 
1,528,328 
203,834 
180,824 
7,184 
1,239,287" 
70,435 
29,870 
38,515 
14,707 
51,718 
351,090 
255,000 
49,56227 
61,33817 
19,892 
10,000 
69,976 
67,792 
2,663 
18,525 
7,501 
169,636 
107,220 
32,000 
212,000 
21,000 
20,000 
440,237 
49,094 
12,000 
32,161

NEW ENGLAND DIVISION 
TABLE 1-C (Continued) OTHER AUTHORIZED NAVIGATION PROJECTS 
8 Inactive. 
9 Awaiting local cooperation. Improvement to be 
restudied. 
10 Commerce included under Tiverton Harbor, RI. 
" Authorized work remaining on project is comprised 
of an incomplete and an inactive portion. 
12 Excludes $129,757 expended for rehabilitation; 
breakwaters repaired in 1961. 
13 Recommendation for abandonment of exisiting project 
made in H. Doc. 467, 69th Congress 1st session. Portion 
of project authorized by the Chief of Engineers (P.L. 
86-645, Sec. 107) is complete. 
14 Excludes $5,000 contributed funds expended. 
15 Improvement adequate for commerce. 
s1C6o sts to local interests for berth improvements are 
estimated to be $60,000. 
17 Excludes $81,548 contribted funds "other" expended. 
18 Abandonment recommended in H. Doc. 411, 64th 
Congress, 1st session, and in River and Harbor 
Committee Doc. 3, 65th Congress, 1st session. 
19 Improvement to be restudied. 
20 Under State maintenance. 
'2E1 xcludes $114,327 expended for rehabilitation; 
breakwater repaired in 1962 
22 Portion of project authorized by Chief of Engineers. 
2 Excludes $211,649 expended for rehabilitation; jetty 
repaired in 1963. 
24 All assurances of local cooperation have not been 
fulfilled. Public landing at Back Cove has not been 
constructed. Portion of project authorized by Chief of 
Engineers (Public Law 86-645, Sec. 107). 
25 Includes $11,350 for previous project, Excludes 
$32,000 contributed funds expended. 
26 H. Doc. 467, 69th Cong., 1st sess. recommended 
eliminating maintenance dredging. 
27 Excludes $49,562 contributed funds "other" expended. 
28 Final fund adjustment made FY 1978 ($52,323.28). 
29 Includes $37,000 for new work for previous project. 
30 Excludes local requirements of $65,000 consisting of 
$13,000 for public wharf and $52,000 for additional 
construction costs. 
31 Includes $133,357 for previous project. 
32 Includes $188,647 for previous project. 
33 Excludes $894,475 major rehabilitation for Long 
Beach Dike. 
34 Includes $2,013 for previous projects. In addition $400 
was expended for maintenance of contributed funds. 
35 Includes $15,614 for new work for previous projects. 
36 Includes $40,800 for previous project. 
37 Includes $135,143 for previous project. 
38 Includes $10,000 for previous project. 
39 Excludes $141,530 expended contributed funds 
"other". 
40 Excludes $12,500 expended from contributed funds. 
41 Excludes $11,380 contributed funds expended. 
42 Includes $215,801 for previous project. 
43 Includes for previous projects $735,900 (Weymouth, 
Fore R.) and $25,000 (Town R.). 
44 Includes for previous project $5,250 (Weymouth, 
Fore River and $12,577 (Weymouth Town River). 
45 Includes $59,420 for previous project. 
4 Includes $509,411 for previous projects. 
47 Includes $692,435 for previous projects. 
1-53

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 1-D OTHER AUTHORIZED BEACH EROSION CONTROL PROJECTS 
For Last 
Full Report Cost to Amount 
See Annual Sept. 30, 1983 Expended by 
Project Report For Construction Local Interest 
Burial Hill Beach, Westport, CT' 
Calf Pasture Beach Park, Norwalk, CT' 
Clark Point Beach, New Bedford, MA 'l 
Compo Beach, Westport, CT' 
Cove Island, Stamford, CT' 
Cummings Park, Stamford, CT' 
Guilford Point Beach (Jacobs Beach), Guilford, CT' 
Gulf Beach, Milford, CT' 
Hammonasset Beach, Madison, CT' 
Hampton Beach, Hampton, NH' 
Jennings Beach, Fairfield, CT' 
Lighthouse Point Park (Area 9), CT' 
Lynn-Nahant Beach, MA 
Matunuck Beach, South Kingston, RI2 
Middle Beach, CT' 
Misquamicut Beach, Westerly, RI3 
Nantasket Beach, MA 4 
North Hampton Beach, North Hampton, NH4 
North Scituate Beach, Scituate, MA l ' 
Oak Bluffs Town Beach, Martha's Vineyard, MA l ' 
Oakland Beach, Warwick, RI' 
Plum Island, MA I 
Prospect Beach, West Haven, CT' 
Quincy Shore Beach, Quincy, MA l' 
Revere Beach, Revere, MA8 
Sand Hill Cove Beach, RI' 
Sasco Hill Beach, Fairfield, CT' 
Seaside Park, CT' 
Short Beach, CT' 
Silver Beach to Cedar Beach, CT 
Southport Beach, CT' 
Town Beach, Plymouth, MA 
Town Neck Beach, Sandwich, MA 
Wallis Sands State Beach, Rye, NH' 
Wassagusset Beach, Weymouth, MA' 
Winthrop Beach, MA' 
Woodmont Shore, Milford, CT' 
ICompleted. 
2Project is to be included in Point Judith water 
resources development plan authorized by 1962 River 
and Harbor Act. 
3Additional Federal participation will be required 
based on Public Law 87-874. 
4Project inactive. 
5Project completed at no cost to Federal Government 
by using fill from federal navigation improvement 
at Housatonic River. 
6Project is complete. There are three additional 
groins, construction of which is deferred until it is determined 
that they are necessary. 
7Excludes $118,215 expended for work beyond 
scope of project. 
8Excludes $73,800 for previous project. Excludes 
$142,965 contributed. 
1-54 
1958 
1964 
1982 
1962 
1961 
1963 
1961 
1958 
1956 
1966 
1956 
1961 
1961 
1958 
1963 
1971 
1963 
1969 
1976 
1982 
1977 
1958 
1962 
1981 
1959 
1961 
1958 
1964 
1960 
1964 
1961 
1966 
1971 
1960 
1961 
$ 5,810 
56,286 
228,081 
84,544 
47,131 
26,886 
15,620 
21,303 
163,183 
260,868 
14,401 
3,930 
49,884 
8,810 
14,512 
106,552 
273,334 
558,988 
118,882 
104,573 
621,440 
253,713 
40,143 
23,759 
150,000 
_5 
62,560 
17,631 
5,490 
65,131 
180,944 
176,567 6 
53,838 
$ 11,612 
120,179 
228,080 
169,089 
94,262 
53,771 
31,241 
42,606 
326,366 
385,641 
28,802 
7,859 
17,620 
29,024 
106,552 
198,583 
181,175 
104,875 
240,819 
1,242,880 
142,965 
82,000 
47,518 
329,921 
270,695 
35,263 
10,981 
435,942 
200,208 
353,134 
111,6797

NEW ENGLAND DIVISION 
TABLE 1-E OTHER AUTHORIZED FEDERAL FLOOD CONTROL PROJECTS 
For Last Cost to September 30, 1983 
Full Report 
See Annual Contributed 
Project Report for Construction Funds 
Alley Bay, Beals, ME3,'4 
Alford, Green River, MA 3,4 
Amesbury, Powwow River, MA3, 4 
Ansonia-Derby,CT 3 
Bound Brook, Scituate, MA 3,4 
Canton, MA 3,4 
Charles River Dam, MA3 
Charlestown, NH 3,4 
Cherryfield, ME 3,4 
Chicopee, MA6 
Chicopee Falls, MA3 
Cocheco River, NH3,4 
Connecticut River, North Stratford, NH 3,4 
Connecticut River, W. Stewartstown, NH3,4 
Danbury, CT3 
Derby, CT:3 
East Branch Dam, CT3 
East Hartford, CT 3 
Fitchburg, MA (See No. Nashua River) 
Folly Brook, Wethersfield, CT3,4 
Fort Kent, ME3,4 
Fox Point Barrier, RI3 
Gardner, MA 3,4 
Hall Meadow Brook Dam, CT 3 
Hartford, CT3 
Hartford, White River, VT3,4 
Hayward Creek, Quincy-Braintree, MA 3,4 
Holmes Bay, Whiting, ME3 
Holyoke, MA3 
Housatonic River, Salisbury, CT3,4 
Housatonic River, Sheffield, MA3 
Huntington, MA3, 4,' 0 
Johnson Bay, Lubec, ME3 
Keene, NH3,4 
Lancaster, Israel River, NH3,4 
Lee, Housatonic River, MA3 ,io 
Lowell, MA3 
Lower Woonsocket, RI3 
Mad River Lake, CT 3 
Merriconeag Sound, Harpswell, ME3 
Monoosnoc Brook, MA 13 
Monoosnoc Lake, MA'2 
Nashua, NH3 
Nookagee Lake, MA 
Northampton, MA3 
North Canaan, Blackberry River, CT3,4 
North Nashua River, Fitchburg, MA3 
North Nashua River, Lancaster, MA3,4 
Norwalk, CT 3,4 
Norwich, CT3 
Old Town, Penobscot River, ME 3,' 
Pawcatuck, CT3 
Phillips Lake, MA 
Prestile Stream, Blaine, ME3 
1979 
1977 
1978 
1977 
1974 
1964 
1981 
1976 
1963 
1954 
1978 
1963 
1982 
1976 
1978 
1977 
1973 
1951 
1979 
1979 
1976 
1970 
1970 
1960 
1973 
1979 
1980 
1953 
1982 
1981 
1960 
1980 
1955 
1982 
1976 
1945 
1977 
1973 
1980 
1967 
1967 
1950 
1976 
1950 
1977 
1981 
1979 
1952 
1960 
1978 
1966 
1982 
1980 
$ 190,500 
41,419 
132,113 
18,206,040 
47,300 
180,6705 
41,163,031 
113,330 
203,000 
1,433,6007 
2,183,912 
183,100 
180,000 
54,703 
13,143,000 
7,582,642 
1,959,836 
2,135,000 
220,284 
1,997,820 
11,112,801 
495,691 
2,572,357 
6,094,1009 
332,236 
2,235,470 
207,390 
3,418,000 
102,800 
202,608 
3,900 
105,082 
44,100 
551,605 
37,852 
490,60011 
6,600,681 
4,773,020 
107,681 
270,0008 
563,677 
680,0001? 
73,865 
3,235,0002 
81,671 
52,150 
1,209,000 
148,045 
644,311 
300,000 
73,674 
,p -
- 
_ 21 
92,891 
5,544,640's 
385 
411,29222 
-2 
19 
7,637 
3,679,50014 
S15,500 
2,781,100 
24,447 
1,266,63820 
327 
2,800 
214,106 
1-55

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 1-E OTHER AUTHORIZED FEDERAL FLOOD CONTROL PROJECTS 
For Last Cost to September 30, 1983 
Full Report 
See Annual Contributed 
Project Report for Construction Funds 
Riverdale, MA3 1952 1,138,000 25,000 
Saxonville, MA3 1981 4,218,700 _24 
Shelburne, Androscoggin River, NH3,4 1977 37,657 - 
Smelt Brook, Weymouth-Braintree, MA 3,4 1978 1,803,739 - 
Springdale, MA3 1952 700,000 - 
Springfield, MA3 1950 577,00018 5,350 
Stony Brook, Wilton, NH 3,4 1973 19,500 - 
Sucker Brook Dam, CT3 1976 2,227,712 58,800 
Three Rivers, MA3 1970 1,577,18912- 
Torrington, East Branch, CT3,4 1963 389,200 - 
Torrington, West Branch, CT3,4 1963 228,300 - 
Ware, MA3,a 1963 400,00 - 
Waterbury-Watertown, CT3,4 1963 263,300 - 
Westerly, RI 1966 - - 
Weston, VT',4 1957 13,000 1,800 
West Springfield, MA 3 1954 1,334,00016- 
West Warren, MA 3,4 1964 389,200 41,000 
Whitmanville Lake, MA 1979 605,023 - 
Winsted, CT3 1954 245,500 - 
Woonsocket, RI3 1962 4,040,000 224,500 
Worcester Diversion, MA3 1978 5,086,859 79,300 
'Inactive. 14Cash for construction only. Excludes $245,000 expended 
2Excludes $1,147,169 expended from Contributed Funds, for land condemnation. 
Other. '5 Excludes $1,652,212 Contributed Funds, Other. 
3Completed. 16Excludes $245,000 Public Works Administration funds. 
4Authorized by Chief of Engineers. '7 5 Excludes $280,000 Public Works Administration funds. Reflects FY 1967 settlement of outstanding claims. 18Excludes $355,000 Public Works Administration funds. 
6Completed except for inactive portion. '9Excludes $406,653 Contributed Funds, Other. 
7Includes $295,000 Public Works Administration funds. 2oExcludes $488,920 Contributed Funds, Other. 
SExcludes $147,366 flood control and coastal emergency 21Excludes $727,460 Contributed Funds, Other. 
9funds expended. 22Excludes $12,000 expended for land condemnations and Excludes $835,000 Public Work Administration funds. $25,184 Contributed Funds, Other for relocations. 
'0Emergency Bank Protection. 23Excludes $1,370,000 Public Works Administration funds 
"Excludes $794,374 Public Works Administration funds. expended on Fitchburg, MA. 
!2Excludes $565,168 Contributed Funds, Other. 24Excludes $8,503 Contributed Funds, Other. 
13To be restudied. 
TABLE 1-F OTHER AUTHORIZED MULTIPLE-PURPOSE PROJECTS 
INCLUDING POWER 
For Last Cost to September 30, 1983 
Full Report 
See Annual Contributed 
Project Report For Construction Funds 
Passamaquoddy Tidal Power Project, ME' 1935 6,384,394 
'Work discontinued in 1937. Facilities transferred to War Assets Administration. 
1-56

NEW ENGLAND DIVISION 
TABLE 1-G DEAUTHORIZED PROJECTS 
For Last Funds Expended 
Full Report 
See Annual Date Contributed 
Project Report For Deauthorized Federal Funds 
Alternative for Sugar Hill Reservoir - Aug 1977 $ - $ - 
Andover Lake, CT - Aug 1977 - - 
Bagaduce River, ME (uncompleted portion) - Oct 1978 - - 
Baker Brook, MA 1972 Nov 1979 94,000 - 
Beards Brook Reservoir, NH 1949 Aug 1977 78,000 - 
Beaver Brook Lake, NH 1973 Apr 1978 378,300 - 
Bennington Reservoir, NH 1949 Aug 1977 205,000 - 
Brant Rock Beach, Marshfield, MA 1961 Nov 1979 - - 
Bridgeport Harbor, CT (uncompleted portion) 1980 Nov 1979 - - 
Brockway Lake, VT 1946 Aug 1977 - - 
Cambridgeport Lake, VT - Aug 1977 - - 
Chicopee, MA (uncompleted portion) 1954 Aug 1977 - - 
Claremont Lake, NH 1968 Dec 1970 242,700 - 
Clyde, RI 1948 Apr 1951 8,800 - 
Connecticut River below Hartford 1979 Oct 1978 - - 
CT (uncompleted portion) 
Cotuit Harbor, MA 1962 Oct 1978 8,541 - 
Dickey Lake, ME 1983 Dec 1981 13,130,0001- 
Fivemile River Harbor, CT (uncompleted portion) 1969 Oct 1978 - - 
Gaysville Lake, VT 1970 Oct 1976 206,600 - 
Greenwich Point Beach, CT 1959 Oct 1978 - - 
Housatonic River, CT (uncompleted portion) 1979 Nov 1979 - - 
Honey Hill Lake, NH 1949 Aug 1977 92,000 - 
Ludlow Lake, VT - Aug 1977 - - 
Manchester Harbor, MA 1949 Nov 1979 23,986 - 
Marblehead Harbor, MA 1968 Oct 1978 43,711 - 
Mattapoisett Harbor, MA 1950 Oct 1978 - - 
Mountain Brook Dam, NH 1949 Aug 1977 57,000 - 
Mystic, CT 1968 Aug 1972 67,700 - 
Napatree Beach, RI - Nov 1979 - - 
Narrangansett Pier, RI 1966 Nov 1970 115,590 - 
North Andover and Lawrence, MA 1949 Aug 1977 20,000 - 
Norwalk-Wilton, CT 1973 Nov 1979 - - 
Pawcatuck River, RI & CT (uncompleted portion) 1979 Nov 1979 - - 
Pawtucket, RI 1949 Nov 1977 - - 
Point Judith, RI 1968 Nov 1977 198,477 - 
Pontiac Diversion, RI 1948 Apr 1951 24,200 - 
Provincetown Beach (Herring Cove), MA 1961 Oct 1978 - - 
(uncompleted portion) 
Provincetown Harbor, MA (uncompleted portion) 1979 Oct 1978 - - 
Saco River, ME (uncompleted portion) 1979 Oct 1979 - - 
Sakonnet Harbor, RI 1982 Jun 1982 176,000 - 
Sandy Bay, Cape Ann, MA (uncompleted portion) 1922 Oct 1978 - - 
South Coventry Lake, CT 1951 Aug 1977 96,000 - 
South Tunbridge Lake, VT - Aug 1977 - - 
Stamford Harbor, CT (2 projects 
uncompleted portions) 1979 Oct 1978 - - 
Stonington Harbor, ME 1961 Nov 1979 2,543 - 
Stratford, CT 1973 Mar 1977 934,500 - 
Sugar Hill Reservoir, NH 1946 Dec 1944 - - 
The Island Lake, VT - Aug 1977 - - 
Thumperton Beach, Eastham, MA 1961 Nov 1979 - - 
Wareham-Marion, MA 1965 Aug 1977 81,715 - 
Victory Lake, VT 1967 Aug 1977 168,400 - 
1-57

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 1-G (Continued) DEAUTHORIZED PROJECTS 
For Last Funds Expended 
Full Report 
See Annual Date Contributed 
Project Report For Deauthorized Federal Funds 
West Brookfield Reservoir, MA 1948 July 1960 67,000 - 
West Canaan Lake, NH 1948 Aug 1977 92,000 - 
Westfield, MA 1967 Sep 1969 507,200 - 
Westport, CT 1965 Feb 1970 29,634 - 
Westport Harbor and Saugatuck River, CT 1972 Nov 1979 - - 
(uncompleted portion) 
Williamsville Reservoir, VT 1949 Dec 1944 146,500 
'For Dickey-Lincoln School Lakes Project. 
TABLE 1-H NAVIGATION ACTIVITIES PURSUANT TO SECTION 107, 
PUBLIC LAW 86-645 (PREAUTHORIZATION) 
Study Identification Fiscal Year 
Costs 
Basin Cove, South Harpswell, ME 10,050 
Eel Pond, Falmouth, MA 28,886 
Fishermans Cove, Swampscott, MA 42,302 
Gloucester Harbor, Gloucester, MA 20,855 
Green Harbor, Marshfield, MA 6,440 
Kennebunk River, Kennebunkport, ME 855 
Oak Bluffs Harbor, Oak Bluffs, MA 20,383 
Perkins Cove, Ogunquit, ME 11,262 
Pine Point Harbor, Scarborough, ME 27,517 
Pines River, Revere, MA 46,441 
Plymouth Harbour, Plymouth, MA 26,290 
Provincetown Harbor, Provincetown, MA 34,283 
Rockport & Old Harbors, Rockport, MA 72,632 
Saquatucket Harbor, Harwich MA 36,377 
Saugus & Pine Rivers, MA 71,316 
Scituate Harbor, MA 47,577 
Wood Island Harbor, Biddeford, ME 22,256 
TABLE 1-I BEACH EROSION ACTIVITIES PURSUANT TO SECTION 103, 
PUBLIC LAW 78-874 (PREAUTHORIZATION) 
Study Identification Fiscal Year 
Costs 
Bass River Beach, Yarmouth, MA 
Belfast City Park, Belfast, ME 
City Park Beach, Warwick, RI 
Conimicut Beach, Warwick, RI 
Cornhill Beach, Truro, MA 
Sea Gull Beach, Yarmouth, MA 
Seaview & Parkers River, MA 
West Haven Beaches, CT 
38 
47,173 
40,587 
5,110 
82 
15,642 
58,497 
68,737 
1-58

NEW ENGLAND DIVISION 
TABLE 14-J FLOOD CONTROL ACTIVITIES PURSUANT TO SECTION 205, 
PUBLIC LAW 80-858 (PREAUTHORIZATION) 
Study Identification Fiscal Year 
Costs 
Beaver Brook, Ansonia, CT 4,000 
Beaver Brook, Keene, NH 87,689 
Blackstone River, Central Falls, RI 3,900 
Blackstone River, Cumberland, RI 36,344 
Dead ugus R Berlin, NH 1,000 
Falls 50 Yan Westbrook, CT 3,800 
Godfrey Brook, Milford, CT 2,500 
Housatonic River, New Milford, CT 82,962 
Mad River, Waterbury, CT 19,835 
Millers Pond, Quaker Hill CT 5,800 
Moshassuck River, Pawtucket, RI 4,300 
Pawcatuck River, Westerly, RI 10,000 
Point of Pines, Revere, MA 109,049 
Quinnipiac River, Wallingford, CT 14,307 
Saugus River, Saugus, MA 25,000 
Saugus River, Wakefield, MA 5,100 
Wepawaug River, Milford, CT 37,603 
Wepawaug River, Orange, CT 38,735 
West River, New Haven, CT 18,661 
Yantic River, Buzrah, CT 2,500 
Yantic River, Norwich, CT 2,500 
TABLE 1-K BLACKSTONE RIVER BASIN, MA AND RI 
(See Section 42 of Text) 
RESERVOIR 
Miles 
Above Estimated Federal Cost 
Mouth of 
Black- Reservoir Lands 
stone Height Capacity and 
Name Nearest City River (feet) Type (acre-feet) Construction Damages' Total 
West Hill2 Worcester, MA 25.8 51 Earthfill 12,400 $1,367,000 $940,000 $2,307,000 
I Includes highway, railroad, and utility relocations. 
2See individual report for details. 
1-59

REPORT OF THE CHIEF OF ENGINEERS, U.S, ARMY 1983 
TABLE 1-K (Continued) LOCAL PROTECTION PROJECTS 
Miles 
Above Estimated Cost 
Mouth of 
Black- Lands 
stone and 
Location River Type of Structure Construction Damages' Total 
Worcester, MA 48 Diversion tunnel and channel $4,923,500 81,179,0002 $6,102,500 
Woonsocket, RI 15 Channel improvement 3,740,100 1,069,000 4,809,100 
Lower Woonsocket, RI 13 Flood wall, conduits and 
channel improvement 8,356,239 435,000 8,791,239 
'Includes relocations. 
2$158,000 Federal; $1,021,000 non-Federal. 
2$300,000 Federal; $769,000 non-Federal. 
TABLE 1-L CONNECTICUT RIVER BASIN, VT. NH, MA AND CT 
(See Section 43 of Text) 
DAMS AND RESERVOIRS 
Miles 
Above Estimated Federal Cost 
Mouth of 
Conne- Reservoir Lands 
cticut Height Capacity and 
Name Nearest City River (feet) Type (acre-feet) Construction Damages' Total 
Vermont: 
Union Village2 White River 228.4 170 Earthfill 38,000 83,186,860 $ 908,300 $4,095,160 
Junction 
North Hartland2 White River 211.7 185 Earthfill 71,400 6,349,500 963,000 7,312,500 
Junction 
North Springfield2 Springfield 191.3 120 Earthfill 50,600 4,782,000 2,050,000 6,832,000 
Ball Mountain2 Brattleboro 178.2 265 Rockfill- 54,600 10,448,000 350,000 10,798,000 
earth 
Townshend2 Brattleboro 168.3 133 Earthfill 33,200 5,530,000 1,878,000 7,400,000 
New Hampshire: 
Surry Mountain2 Keene 174.4 86 Earthfill 32,500 2,445,000 385,000 2,830,000 
Otter Brook2 Keene 171.2 133 Earthfill 18,300 2,782,100 1,378,400 4,160,500 
Massachusetts: 
Birch Hill2 Gardner 153.3 56 Earthfill 49,900 1,775,500 3,075,000 4,850,500 
Tully2 Athol 148.7 62 Earthfill 22,000 1,339,000 368,000 1,707,000 
Barre Falls2 Worcester 130.2 62 Rockfill- 24,000 1,928,800 39,000 1,967,800 
earth 
Knightville Northhampton 102.8 160 Earthfill 49,000 2,594,440 821,200 3,415,640 
Littleville 2 Northhamton 102.0 150 Earthfill 32,400 5,863,400 1,150,000 7,013,400 
Conant Brook2 Springfield 122.0 85 Rockfill- 3,740 1,936,000 1,015,000 2,951,000 
earth 
Connecticut: 
Colebrook River2 Winsted 116.0 223 Rockfill- 98,500 8,342,00 5,922,000 14,264,000 
earth 
Mad River Winsted 120.0 178 Earthfill 9,700 3,380,000 2,210,0004 5,590,000 
Sucker Brook Winsted 118.5 68 Earthfill 1,480 2,550,000 180,0003 2,730,000 
'Includes highway, railroad, and utility relocations. 
2For details, see individual report. 
sNon-Federal cost. 
4Non-Federal $670,000;Federal 81,540,000. 
1-60

NEW ENGLAND DIVISION 
TABLE 1-L (Continued) 
LOCAL PROTECTION PROJECTS 
Miles 
Above Estimated Cost 
Mouth of 
Conne- Lands 
cticut and 
Location River Type of Structure Construction Damages' Total 
Charlestown, NH 181 Riverbank protection $ 114,000 - $ 114,000 
Chicopee, MA 80 Wall and levee 1,738,000 $ 250,000 1,988,000 
Chicopee Falls, MA 83 Wall and levee 2,600,000 70,000 2,670,000 
East Hartford, CT 52 Wall and levee 2,135,000 271,000 2,406,000 
Folly Brook, Wethersfield, CT 50 Channel improvement 220,300 - 220,300 
Gardner, MA 163 Dam and levee 493,900 35,000 528,900 
Hartford, CT 52 Wall and levee 6,930,0004 1,150,000 8,080,000 
Hartford, VT 216 Channel improvement 332,000 - 332,000 
Holyoke, MA 85 Wall and levee 3,418,000 150,000 3,568,000 
Huntington, MA 100 Riverbank protection 4,000 - 4,000 
Israel R., Lancaster, NH 314 Gabion overflow weir 475,000 - 475,000 
Keene, NH 167 Channel improvement 44,000 - 44,000 
Northampton, MA 94 Wall and levee 960,000 150,000 1,110,000 
North Stratford, NH 345 Slope protection 170,000 - 170,000 
Park River, CT2 51 Conduit 59,877,000 1,300,000 61,177,000 
Riverdale, MA 80 Wall and levee 1,138,000 50,000 1,188,000 
Salmon R., Colchester, CT2 38 Slope protection 235,000 - 235,000 
Springdale, MA 84 Wall and levee 700,000 57,000 757,000 
Springfield, MA 76 Wall and levee 932,000 272,000 1,204,000 
Three Rivers, MA 98 Wall and levee 1,580,000 700,000 2,280,000 
Ware, MA 110 Channel improvement 400,000 85,000 485,000 
Weston, VT 195 Channel improvement 13,000 2,000 15,000 
West Springfield, MA 76 Wall and levee 1,579,0003 30,000 1,609,000 
West Warren, MA 111 Wall and levee 390,000 64,000 454,000 
Winsted, CT 115 Channel improvement 246,000 30,000 276,000 
'To be borne by local interests. Also includes local interests 3lIncludes $245,000 Public Works Administration funds. 
portion of relocation. 4lncludes $835,000 Public Works Administration funds. 
2For details see individual report. 
TABLE 1-M HOUSATONIC RIVER BASIN, CT AND MA 
(See Section 44 of Text) 
DAMS AND RESERVOIRS' 
Miles 
Above Estimated Federal Cost 
Mouth of 
Nagua- Reservoir Lands 
tuck Height Capacity and 
Name Nearest City River (feet) Type (acre-feet) Construction Damages 2 Total 
Hall Meadow4 
East Branch5s 
Thomaston 
Northfield Brook 
Black Rock 
Torrington, CT 
Torrington, CT 
Torrington, CT 
Torrington, CT 
Waterbury, CT 
41.0 73 Rock and 
earthfill 
43.7 92 Earthfill 
30.5 142 Rock and 
earthfill 
30.6 118 Earthfill 
29.0 154 Earthfill 
8,620 $1,852,400 $1,290,0003 $3,142,000 
4,350 1,509,800 1,290,000$ 2,799,800 
42,000 6,382,000 7,900,000 14,282,000 
2,432 1,856,000 
8,700 5,223,700 
975,000 2,831,000 
2,958,600 8,182,300 
1-61

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 1-M (continued) HOUSATONIC RIVER BASIN, CT AND MA 
(See Section 44 of Text) 
DAMS AND RESERVOIRS' 
Miles 
Above Estimated Federal Cost 
Mouth of 
Nagua- Reservoir Lands 
tuck Height Capacity and 
Name Nearest City River (feet) Type (acre-feet) Construction Damages 2 Total 
Hancock Brook Waterbury, CT 25.0 57 Earthfill 4,030 $1,595,000 $2,585,000 $4,180,000 
Hop Brook Waterbury, CT 15.9 97 Earthfill 6,970 2,702,000 3,450,000 6,152,000 
'For details of projects, see individual reports. 4For last full report, see Annual Report for 1970. 
2Includes highway, railroad, and utility relocations. 5For last full report, see Annual Report for 1973. 
3Includes cost of lands borne by local interests. 
LOCAL PROTECTION PROJECT' 
Miles 
Above Estimated Cost 
Mouth of 
Housa- Lands 
tonic and 
Location River Type of Structure Construction Damages 2 Total 
Alford, Green River, 111.0 Earth dike and stone slope $ 41,400 $- $ 41,400 
MA protection 
Ansonia-Derby, CT 13.0 Wall, levee, channel 17,850,000 1,178,000 18,995,000 
improvement and pumping 
station 
Danbury, CT 56.0 Walls, channel improvement 13,182,000 1,862,000 15,044,000 
and bridge replacement 
Derby, CT 12.0 Walls, levees and pumping 7,583,000 647,000 8,230,000 
station 
North Canaan, Blackberry 83.0 Snagging and clearing 73,900 - 73,900 
River, CT project 
Pittsfield, MA 133.0 Stone arch culvert 580,000 85,000 665,000 
Salisbury, CT 76.0 Gabionade with slope 100,000 - 100,000 
protection 
Sheffield, MA 96.0 Stone slope protection 203,000 - 203,000 
Squantz Pond, New 43.0 Timber Bulkhead 116,300 - 116,300 
Fairfield, CT 
Torrington, East Branch, CT 51.0 Dike and channel 389,200 - 389,200 
improvement 
Torrington, West Branch, CT 52.0 Walls, dikes and channel 228,300 - 228,300 
Waterbury-Watertown, CT 32.0 Wall dike and channel 263,300 - 263,300 
IFor details of projects, see individual reports. 
2To be borne by local interests. Includes relocations. 
1-62

NEW ENGLAND DIVISION 
TABLE 1-N MERRIMACK RIVER BASIN, NH, AND MA 
(See Section 50 of Text) 
RESERVOIRS 
Miles 
Above Estimated Federal Cost 
Mouth of 
Merri- Reservoir Lands 
mack Height Capacity and 
Name Nearest City River (feet) Type (acre-feet) Construction Damages' Total 
Franklin Falls2 Franklin, NH 118.2 140 Earthfill 154,000 $ 6,190,500 $ 1,760,000 $ 7,950,500 
Blackwater' Concord, NH 118.8 75 Earthfill 46,000 847,000 553,000 1,400,000 
Hopkinton-Everett, 4 Concord, NH 87.3 115 Earthfill 157,3000 12,715,400 8,737,000 21,452,500 
Edward MacDowell' Keene, NH 161.3 67 Earthfill 12,800 1,708,300 306,000 2,014,300 
Monoosnoc 3 Leominster, MA 100.6 71 Earthfill 2,000 3,430,000 370,000 3,800,0005 
Phillips2 Fitchburg, MA 105.4 48 Earthfill 1,600 13,450,000 7,350,000 20,800,000 
Nookagee Fitchburg, MA 107.9 106 Earthfill 8,100 15,476,000 5,742,000 21,200,000 
Whitmanville Fitchburg, MA 110.6 76 Earthfill 9,350 11,590,000 6,210,000 17,800,000 
'Includes highway, railroad, and utility relocations. 4Substituted for Bennington and Beards Brook. Distance 
2For details, see individual report. and height are for Everett Dam. Distance and height for 
'Project deferred, cost not revised on current price basis. Hopkinton Dam are 118 miles and 76 feet, respectively. 
5lncludes Non-Federal reimbursement. 
6Based on "large" Phillips plan which would eliminate 
Nookagee Lake. 
LOCAL PROTECTION PROJECTS 
Miles 
Above Estimated Cost 
Mouth of 
Merri- Lands 
mack and 
Location River Type of Structure Construction Damages' Total 
Amesbury,Powwow and 3.0 Wall and revetment $ 133,400 $- $ 133,400 
Merrimack Rivers,MA2,4 
Nashua, NH' 55.0 Wall and levee 270,000 3,000 273,0006 
Lowell, NH 2 39.0 Wall and levee 490,600 90,000 580,600 
Monoosnoc Brook, MA' 98.4 Channel improvement 310,000 90,000 400,000 
North Nashua River, MA',4 100.5 Channel improvement 3,235,000 - 3,235,000 
Saxonville, MA' 69.0 Wall, levee, channel 4,218,700 530,000 4,748,700 
'To be borne by local interests. 
2Project completed. 
3Project deferred. Cost has not been revised on current 
price basis. 
4For details, see individual report. 
5Excludes $15,000 expended from contributed funds. 
1-63

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 1-0 THAMES RIVER BASIN, CT, RI AND MA 
(See Section 58 of Text) 
RESERVOIRS 
Miles 
Above Estimated Federal Cost 
Mouth 
of Reservoir Lands 
Thames Height Capacity and 
Name Nearest River (feet) Type (acre-feet) Construction Damages' Total 
Hodges Villagez Webster, MA 74.5 55 Earthfill 13,000 $ 1,337,000 $ 3,144,000 $ 4,481,000 
Buffumville 2 Webster, MA 74.4 66 Earthfill 12,700 2,157,600 841,000 2,998,600 
East Brimfield2 Southbridge, MA 82.8 55 Earthfill 30,000 1,337,000 5,720,000 7,057,000 
Westville 2 Southbridge, MA 75.2 80 Earthfill 11,000 2,285,000 3,400,000 5,685,000 
West Thompson2 Putman, CT 59.3 70 Earthfill 25,600 5,014,300 1,965,000 6,979,300 
Mansfield Hollow2 Willimantic, CT 40.0 70 Earthfill 52,000 4,108,000 2,340,000 6,448,000 
'Includes highway, railroad, and utility relocations. 
2For details, see individual report. 
LOCAL PROTECTION PROJECTS 
Miles Estimated Cost 
Above 
Mouth of Lands 
Thames and 
Location River Type of Structure Construction Damages' Total 
Norwich, CT 15.0 Channel improvements $ 1,209,000 $72,000 $ 1,281,000 
'Borne by local interests. 
TABLE 1-P BOSTON HARBOR, MA 
Total Federal Cost for Existing Project to September 1983 
(See Section 3 of Text) 
Funds New Work Maintenance Total 
Regular $21,881,851 $ 8,765,572 $30,647,423 
Public Works 1,030,806 - 1,030,806 
Emergency Relief 935,303 - 935,303 
$23,847,960 $ 8,765,5721 $32,613,532 
'Excludes $17,767 contributed funds. 
1-64

NEW ENGLAND DIVISION 
TABLE 1-Q RECONNAISSANCE AND CONDITION SURVEYS 
Date Survey Date Survey 
Project Conducted Project Conducted 
Connecticut 
Connecticut River below Hartford 
Mianus River 
Milford Harbor 
Mystic River 
Niantic Harbor 
North Cove 
Stony Creek 
Maine 
Bass Harbor 
Beals Harbor 
Buck Harbor 
Frenchboro Harbor 
Kennebec River 
Kennebunk River 
Machias River 
Penobscot River 
Pig Island Gut 
Portland Harbor 
Saco River 
Southport Harbor 
Southwest Harbor 
York Harbor 
Oct 1982 
Sep 1983 
Feb 1983 
Aug 1983 
Aug 1983 
Apr 1983 
Jul 1983 
Apr 1983 
Apr 1983 
Apr 1983 
Nov 1982 
Jun 1983 
Oct 1982 
Apr 1983 
Jan 1983 
Nov 1982 
Sep 1983 
Sep 1983 
Mar 1983 
Apr 1983 
Apr 1983 
Massachusetts 
Annisquam River 
Boston Harbor 
Chatham (Stage) Harbor 
Duxbury Harbor 
Fall River Harbor 
Green Harbor 
Hyannis 
Newburyport Harbor 
Plymouth Harbor 
Salem Harbor 
Scituate Harbor 
Weymouth-Fore and 
Town Rivers 
Rhode Island 
Little Narragansett Bay 
Pawcatuck River 
Point Judith Harbor 
Providence River 
1-65 
Jan 1983 
Aug 1983 
Apr 1983 
Jan 1983 
Aug 1983 
Dec 1982 
Aug 1983 
Feb 1983 
Jan 1983 
Aug 1983 
Jul 1983 
Jun 1983 
Mar 1983 
Mar 1983 
Fed 1983 
Jul 1983

NEW YORK, N.Y., DISTRICT* 
This district comprises western Vermont, small portions 
of western Massachusetts, Connecticut, and eastern and 
south-central New York, including Long Island, and northeastern 
New Jersey, embraced in the drainage basins tributary 
to Lake Champlain and St. Lawrence River system east 
thereof and to Atlantic Ocean from New York-Connecticut 
State line to but not including Manasquan Inlet, N.J. It exercises 
jurisdiction, however, over all matters pertaining to 
improvement of Great Lakes to Hudson River waterway. 
Under the direction of the Secretary of the Army, the District 
Engineer, as Supervisor of New York Harbor, also exercises 
jurisdicition under the laws enacted for the 
preservation of the tidal waters of New York Harbor, 
its adjacent or tributary water, and the waters of Long 
Island Sound. 
IMPROVEMENTS 
Navigation 
Aquatic Plant Control.................... 
Bay Ridge-Red Hook Channels, N.Y............ 
East Rockaway Inlet, N.Y.................... 
Fire Island to Jones Inlet, N.Y ............... 
Flushing Bay and Creek, N.Y................. 
Hudson River, N.Y......................... 
Jones Inlet, N.Y................. .......... 
Long Island Intra Coastal W/W, N.Y............ 
Moriches Inlet, N.Y......................... 
Narrows of Lake Champlain, N.Y.............. 
Newark Bay Hackensack Passaic Rivers, N.J ... 
New York & New Jersey Channels ............ 
New York Harbor-collection and removal of drift 
New York Harbor-entrance channels & 
anchorage areas........................ 
Shark River, N.J.......................... 
Shoal Harbor & Compton Creek, N.J........... 
Shooters Island, N.Y. & N.J.................. 
Supervisor of New York Harbor............... 
Reconnaissance and conditions surveys........ 
Other authorized navigation projects .......... 
Navigation work under special authorization.... 
Page 
2-2 
2-2 
2-2 
2-3 
2-3 
2-3 
2-4 
2-5 
2-5 
2-6 
2-6 
2-7 
2-8 
2-8 
2-9 
2-9 
2-10 
2-10 
2-11 
2-11 
2-11 
Beach Erosion Control 
22. East Rockaway Inlet to Rockaway Inlet and 
Jamaica Bay, N.Y. (Part I) ................... 2-11 
23. Other authorized beach erosion control projects. 2-11 
24. Beach erosion control work under special 
authorization ............................. 2-11 
Flood Control 
Ardsley, N.Y. .................. ........... 
Elizabeth, N .J........... ...... ..... ...... 
Fire Island Inlet to Montauk Point, N.Y ....... 
Liberty State Park Levee & Seawall, N.J........ 
Passaic River Basin, N.J. & N.Y Phase I ........ 
Sawmill River Elmsford-Greenburg, N.Y........ 
South Ellenville, N.Y....................... 
Staten Island, N.Y. ............. ............ 
Yonkers, N.Y ............................. 
2-11 
2-12 
2-13 
2-15 
2-15 
2-16 
2-17 
2-17 
2-18 
34. Inspection of completed flood control projects... 2-19 
35. Other authorized flood control projects ........ 2-19 
36. Dam Safety Program....................... 2-19 
37. Flood control work under special authorization.. 2-19 
38. Emergency streambank and shoreline protection 
under special authorization.................. 2-19 
39. Debris removal work under special authorization 2-19 
General Investigations 
40. Surveys ....................... 
41. Collection and study of basic data ..... . 
42. Deauthorized projects ................ 
...... 2-19 
...... 2-19 
...... 2-19 
1. 
2. 
3. 
4. 
5. 
6. 
7. 
8. 
9. 
10. 
11. 
12. 
13. 
14. 
15. 
16. 
17. 
18. 
19. 
20. 
21. 
2-1 
Thbles 
Table 2-A Cost & Financial Statement ............ 2-20 
T'able 2-B Authorizing Legislation ............... 2-24 
Table 2-C Hudson River, N.Y. Features of Lock and 
Dam Included in Existing Project........ 2-29 
Table 2-D T'btal Costs for Existing Project ......... 2-29 
T'able 2-E Supervisor of New York Harbor Statement 
of Activities........................ 2-29 
Table 2-F Reconnaissance and Condition Surveys.. 2-30 
Table 2-G Other Authorized Navigation Projects .... 2-31 
T'able 2-H Other Authorized Beach Erosion Control 
Projects...........................2-32 
T'able 2-I Other Authorized Flood Control Projects . 2-33 
T'able 2-J Surveys........................... 2-34 
Table 2-K Flood Plain Studies Completed During the 
Period ............................ 2-34 
Table 2-L Costs for Flood Plain Management 
Services......................... 2-34 
Table 2-M Deauthorized Projects ................ 2-35 
Table 2-N Section 107 Continue Detailed Project 
Report............................ 2-35 
Table 2-0 Section 103 Complete Preauthorization 
Reconnaissance Report ............... 2-35 
Table 2-P Section 205 Continue Preauthorization 
Reconnaissance Report ............... 2-36 
Table 2-Q Section 14 Complete Reconnaissance 
Reports.......................... 2-37 
25. 
26. 
27. 
28. 
29. 
30. 
31. 
32. 
33.

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Navigation 
1. AQUATIC PLANT CONTROL 
Location. Navigable waters, tributary streams, connecting 
channels, and other allied waters in New York District. 
Existing Project. Provides for control and progressive 
eradication of water-hyacinth, alligator-weed, Eurasian 
water milfoil, and other obnoxious aquatic plant growths, 
from the navigable waters, tributary streams, connecting 
channels, and other allied waters of the United States, in 
the combined interest of navigation, flood control, drainage, 
agriculture, fish and wildlife conservation public 
health, and related purposes, including continued research 
for development of the most effective and economic control 
measures (See Table 2-B for Authorizing Legislation.) 
Local cooperation. Local interests must provide 30 percent 
of the cost of the program except as modified by 1962 
River and Harbor Act and agree to hold the United States 
free from damages. 
Operations and results during period. During the 
second year of a ten year control program for removal of 
nuisance aquatic plants in Lake Champlain, a contract for 
removal of 162 acres of these plants was completed at a cost 
of $135,700. The third segment of the control program will 
be undertaken during the summer of 1984. 
Condition as of September 30. Reconnaissance report 
covering the aquatic plant problems of the North Atlantic 
Division area was completed in August 1967. Planning for 
the waterchestnut control in the Hudson-Mohawk basin 
was completed by the New York District, contracts for 
$181,562 accomplished during FY1971 through FY1976. 
Reconnaissance report for Lake Champlain, Vermont and a 
General Design Memorandum have been completed. 
2. BAY RIDGE AND RED HOOK 
CHANNELS, N.Y. 
Location. These channels lie along east shore of Upper 
Bay, New York Harbor and, with Buttermilk Channel, form 
an easterly channel along Brooklyn waterfront from the 
Narrows to East River. (See Coast and Goedetic Survey 
Charts 369 and 541.) 
Previous projects. For details see Annual Reports for 
1915 and 1938, pages 1768 and 195, respectively. 
Existing projects. A channel 1,200 feet wide and 40 
feet deep at mean low water from the Narrows to Bay Ridge 
Avenue, Brooklyn, thence 1,750 feet wide to junction of Bay 
Ridge and Red Hook Channels, thence 1,200 feet wide 
through Red Hook Channel to junction with Buttermilk 
Channel and a channel of same depth extending into Gowanus 
Bay from junction of Bay Ridge Channel with Red 
Hook Channel, narrowing uniformly in width to about 500 
feet at 28th Street, Brooklyn. Section included in project is 4 
miles long. Mean tidal range, 4.7 feet; mean range of spring 
tides, 5.6 feet; irregular fluctuations due to wind and atmospheric 
pressure vary from 3.9 feet below mean low water 
up to 5.2 feet above mean high water. New work for completed 
project cost $4,277,197, exclusive of amounts expended 
on previous projects. (See Table 2-B for Authorizing 
Legislation.) 
Local cooperation. None required. 
Terminal facilities. See Port Series No. 5, revised 1978. 
Vol. 2. 
Operations and results during period. A continuing 
contract for maintenance dredging of channel to restore 
project depths was awarded in FY1982. Work started September 
27, 1982 and was completed November 23, 1982. 
Removed 511,318 cubic yards, place measurement, of material 
in FY1983 at a final cost of $343,044. 
Reconnaissance surveys cost $16,551. 
Condition as of September 30. Work under existing 
project was commenced March 1901 and completed June 
1940.
3. EAST ROCKAWAY INLET, N.Y. 
Location. On south shore of Long Island between main 
body of island and western end of Long beach. It is 10 miles 
east of Rockaway Inlet and about 27 miles by water south 
and east from the Battery, New York City. (See National 
Ocean Survey Chart 12352.) 
Existing project. A channel 12 feet deep at mean low 
water and 250 feet wide from 12-foot contour in Atlantic 
Ocean for about 0.6 mile to 12-foot contour in Long Beach 
Channel protected by a jetty. Mean tidal range, 4.3 feet; 
mean range of spring tides, 5.2 feet; irregular fluctuations 
due to wind and atmospheric pressure vary from 3.9 feet 
below mean low water up to 5.6 feet above mean high water. 
New work for completed project cost $603,969, including 
$100,000 contributed funds. (See Table 2-B for 
Authorizing Legislation.) 
Local cooperation. Complied with. 
Terminal facilities. There are 39 terminals in Oceanside, 
Island Park, Long Beach, and East Rockaway. Nine of 
these are oil terminals, one of which has a railroad spur. 
Other terminals are repair and mooring docks with a berthage 
of 7,655 feet. Of these, 21 have marine railways and 1 
has mechanical-handling facilities. There are public 
wharves at East Rockaway and Woodmere. Waterfront on 
northside of Long Beach has been bulkheaded. Facilities are 
considered adequate for existing commerce. 
Operations and results during period. Operation and 
maintenance funds of $22,754 were expended in FY 1983 
for the channel dredging portion of the Periodic Nourishment 
Contract #2 for the East Rockaway Inlet to Rockaway 
Inlet Beach Erosion and Hurricane Protection Project which 
was accomplished in FY 1982. Operation and Maintenance 
funds of $26,532 were expended on engineering and design 
of maintenance dredging specifications for work which was 
to be accomplished in FY 1983. Reconnaissance surveys 
cost $541. 
Condition as of September 30. Work under existing 
project began February 1933 and is 100 percent complete. 
East jetty, 4,250 feet long, was completed in July 1934. Project 
channel was completed in May 1935. 
2-2

NEW YORK, N.Y. DISTRICT 
4. FIRE ISLAND TO JONES 
INLET, N.Y. 
Location. On south shore of Long Island, about 50 miles 
by water south and east of the Battery, New York City. It is 
the main entrance into Great South Bay from the Atlantic 
Ocean. (See Coast and Geodetic Survey Chart 578.) 
Existing project. A jetty extending generally southwest 
and south for 5,000 feet from high ground on Democrat 
Point at west end of Fire Island, and a channel 10 feet deep 
and 250 feet wide from deep water in ocean to deep water 
within inlet. Mean tidal range at ocean and inlet ends of 
Democrat Point are 4.1 and 2.4, respectively. Mean range of 
spring tides on the ocean side is 5.0 feet. Irregular fluctuations 
due to wind and atmospheric pressure vary from 2.5 
feet below mean low water up to 6.2 feet above mean high 
water on the ocean side. New work for completed project 
cost $684,545, including $90,190 contributed local interests. 
(See Table 2-B for Authorizing Legislation.) 
Local cooperation. Fully complied with. 
brminal facilities. None within area immediately adjacent 
to Federal improvement. In Great South Bay there 
are 28 boat repair and storage yards, 3 commercial fish terminals 
and 3 ferries, with a total berthage of 25,440 feet. 
Twenty-eight terminals have marine railways and 13 are 
public wharves. In addition, Patchogue River has 12 boat 
repair and storage yards, 1 ferry, and 3 fuel oil terminals, 
with a total berthage of 8,380 feet. Fourteen have marine 
railways and 2 are public wharves. Facilities are considered 
adequate for existing commerce. In addition to the commercial 
facilities there are numerous privately-owned terminals. 
Operations and results during period. At the request 
of local interests, maintenance dredging of the Inlet has 
been postponed until an Inlet Dynamic Study is completed. 
The residents of Oak Beach contend that dredging the Inlet 
exposes Oak Beach to direct wave attack, thereby causing 
an erosion problem. The Inlet Dynamic Study is scheduled 
for completion in the spring of 1984, at which time future 
maintenance dredging will be reassessed. Cost of FY 1983 
were $129,780. Reconnaissance surveys cost $3,959. 
Condition as of September 30. Work under existing 
project was commenced June 1939. Jetty was completed in 
1941. Since a November 1953 survey revealed a channel 
with dimensions substantially the same as those authorized, 
work under existing project was considered complete 
November 1953. Jetty has surpassed its capacity as a sand 
entrapping agent and, when examined in June 1969, was 
found to be in poor condition. 
5. FLUSHINGBAY AND CREEK, N.Y. 
Location. On north shore Long Island, opening into East 
River, 12 miles by water northeast of the Battery, New York 
City. Bay is 1.8 miles long in a northwest-southeast direction 
and from 0.4 to 0.8 mile wide. Flushing Creek enters 
bay from southeast and is about 1.1 miles long. (See Coast 
and Geodetic Survey Chart 226.) 
Previous projects. For details see Annual Reports for 
1915, 1932, and 1938; pages 1772, 169, and 168, respectively. 
Existing project. (a) A bay channel with a depth of 15 
feet at mean low water, and 3000 feet wide from deep water 
in East River 1.8 miles to maneuvering area; (b) thence a 
creek channel with a depth of 15 feet at mean low water and 
200 feet wide to Northern Boulevard Bridge, thence decreasing 
uniformly in width to 170 feet at a point 50 feet 
downstream from Van Wyck expressway Bridge, a distance 
of about 1.1 miles; (c) a branch channel with a depth of 15 
feet at mean low water and width of 200 feet from bay channel 
maneuvering area 0.1 mile long; (d) an irregularly 
shaped maneuvering area about 2,000 by 750 feet with a 
depth of 15 feet at mean low water except approach to west 
side of municipal boat basin which will remain at 12 feet at 
mean low water; (e) an anchorage basin about 2,100 by 
1,800 feet, encompassing about 84 acres with a depth of 6 
feet at mean low water; and (f) riprap revetment of 1,400 
feet extension of earth dike. Mean Tidal range, 6.5 feet at 
mouth of Flushing Bay, 6.8 feet at Northern Boulevard 
Bridge; mean range of spring tides 8.1 feet; irregular fluctuations 
due to wind and atmospheric pressure vary from 4 
feet low water to 7.6 feet above mean high water. New work 
for completed project cost $1,894,282, including $419,879 
contributed by local interests; and excluding $8,752 expended 
by local interests for required work, $580,435 contributed, 
other, funds, and amounts expended on previous 
projects. (See Thble 2-B for Authorizing Legislation). 
Local cooperation. Complied with except that local interests 
must furnish lands, easements and rights-of-way for 
maintenance and for aids to navigation upon request of 
Chief of Engineers; hold the United States free from damages; 
make necessary removals or relocations of pipelines, 
cables and other utilities and all necessary protective measures 
to bridges and other structures crossing or adjacent to 
the waterway; and maintain necessary mooring facilities 
and utilities for recreational boating open to all on equal 
terms. 
Trminal facilities. See Port Series No. 5, revised 1965, 
Vol. 2 Part 2, pages 244-248. 
Operations and results during period. A continuing 
contract was awarded Septemer 16, 1983 in the estimated 
amount $2,172,889 for the removal and satisfactory disposal 
of 345,333 cubic yards of all material except ledge rock 
lying above the planes of 15 feet and 6 feet below mean low 
water in specified section of Flushing Bay, N.Y. Contractor 
will commence dredging in FY 1984. Reconnaissance surveys 
cost $7,491. 
Condition as of September 30. Work under existing 
project was commenced April 1963 and was completed October 
1964. 
6. HUDSON RIVER, N.Y. 
Location. Originates in Adirondack Mountains, about 
250 miles in a direct line and 315 miles along its course from 
the Battery, New York City, and flows generally southerly 
into New York Bay. Section under improvement extends 
2-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
from New York City about 156 miles to Waterford. (See 
National Ocean Survey Charts 12335, 12341, 12343, 12347, 
12348 and 14786.) 
Previous projects. For details see Annual Reports for 
1915 and 1938, pages 1764 and 226, respectively. 
Existing project. A channel 600 feet wide from New 
York City to Kingston and thence 400 feet wide to Albany, 
with widening at bends, a turning basin 700 feet wide and 
1,200 feet long at Albany, and 2 anchorages, 1 near Hudson 
and 1 near Stuyvesant, each 400 feet wide and an average 
length of 2,400 feet; all with depths of 32 feet in soft 
material and 34 feet in rock to 2,200 feet south of the Mall 
Bridge; thence 27 feet deep and 400 feet wide to 900 feet 
south of the Mall Bridge; thence 14 feet deep at lower low 
water and generally 400 feet wide to Federal lock at Troy; 
and thence of same depth and 200 feet wide to southern 
limit of State barge canal at Waterford; and removal of State 
dam at Troy and construction of a lock and dam about 2.50 
miles below Waterford. Channel is to be formed by dredging 
and rock excavation, and maintained by dredging and 
constructing new, and raising and repairing old, longitudinal 
dikes, built partly under previous projects and 
partly by the State of New York. Mean range of pool 
elevation above Federal dam at Troy, in seasons of 
moderate rains, is about 2.2 feet, as determined in 1934. 
Mean tidal range is about 4.8 feet between May and October 
and 5.1 feet between July and September at Federal dam at 
Troy and about 4.8 feet between May and October and 5.0 
feet between July and September at Albany, extreme range 
due to freshets is 33.1 and 25.9 feet, respectively normal 
pool level above Federal dam from Troy to Waterford is 
14.33 feet above mean sea level. In tidal section of river 
below dam, assumed lowest low water plane from Troy to 
Albany is 3 feet below mean sea level. (See Table 2-C for 
features of lock and dam included in existing project.) New 
work for completed project cost $39,050,019 exclusive of 
amounts of expended on previous projects. Widening to 
form harbors at Albany and Troy, N.Y., to 12 feet deep at a 
cost of $552,000 (1954) and completion of 27-foot channel at 
Albany at a cost of $458,000 (1957) are inactive. Construction 
of dikes at a cost of $642,000 (1957) was placed in 
deferred for restudy category. All three features of work are 
excluded from foregoing description of existing project and 
cost estimate. Construction of mooring facilities has been 
authorized. (See Table 2-B for Authorizing Legislation.) 
Local cooperation. Complied with except that local 
interests must furnish suitable soil disposal areas for future 
maintenance as required. 
'Terminal facilities. See Port Series No. 6, revised 1979. 
Operations and results during period. A continuing 
contract was awarded September 15, 1983 at a cost of 
$493,081 for removal and satisfactory disposal of all 
material except ledge rock lying above the planes of 32 feet 
and 34 feet below mean low water in the Albany Turning 
Basin, the adjacent channel and opposite Papscanee Island. 
Cost for FY1983 were $516,766, which represents contract 
costs and engineering and design. Dredging will commence 
in FY1984. Reconnaissance surveys cost $25,551. 
By use of Government plant and hired labor, stumps and 
snags which formed a potential menace to navigation, and 
other obstructions, were removed from the shores and 
channel of the river at a cost of $168,585 for maintenance in 
FY1983. 
Government plant and hired labor were employed 
intermittently through the fiscal year in performing surveys 
to restore horizontal and vertical controls at a cost of 
$124,724 for maintenance in FY1983. 
Government plant and hired labor were employed 
intermittently through the fiscal year on repairs to Cedar 
Hill Dike at a cost of $104,627 for maintenance in FY1983. 
The lock and dam on the Hudson River at Troy, N.Y. were 
operated and maintained. Operation of Lock for 1983 
navigation season was suspended December 7, 1982 and 
resumed April 17, 1983. Cost incurred was $426,779 for 
Operation and Maintenance in FY1983. 
Recommendations for major rehabilitation of Troy Lock 
and Dam were reviewed in FY1983. A large-scale repair is 
being considered instead of major rehabilitation at this 
time. Plans will be developed in FY1984. Cost incurred 
during the period were $1,948. 
Condition as of September 30. Work under existing 
project began in July 1910 and was substantially completed 
in November 1965. New lock and dam at Troy, removal of 
dam at Troy and construction of 15,545 linear feet of dikes 
also are complete. In reconstruction of old dikes 39,676 
linear feet were raised to adopted crest height. Channel 
from New York City to Albany is complete to a depth of 32 
feet except for the 1,500 linear-foot section at the northern 
end of the 32-foot project which has never been dredged to 
project depth. Additionally, the 1,300 linear feet of the 27- 
foot project remains undredged. Channel from albany to 
Waterford is complete to a depth of 14 feet except for a small 
part of the widening to form a harbor at Troy. Work 
remaining under the project consists of completion of the 
12-foot harbor at Troy and dredging the 27-foot and the 
remainder of the 32-foot channels at Albany which are not 
deemed necessary at this time; and reconstruction of dikes. 
Started coordination with State regarding mooring 
facilities. (See Table 2-D for total costs of existing project to 
September 30,1983. 
7. JONES INLET,N.Y. 
Location: A small inlet on south shore of Long Island 
connecting Hempstead Bay with Atlantic Ocean, 37 miles 
by water southeast of the Battery, New York City. (See 
National Ocean Survey Chart 12352). 
Existing project. An entrance jetty and a channel 12 
feet deep and 250 feet wide, from that depth in the ocean 
through the inlet to Loop Causeway Bridge over Long 
Creek. Section included in project is about 2.1 miles long. 
Mean tidal range varies from 4.2 feet at ocean entrance to 
3.1 feet at Loop Causeway Bridge; mean range of spring tide 
varies from 5 to 3.7 feet, respectively; irregular fluctuations 
due to wind and atmospheric pressure vary from 3.9 feet 
below mean low water up to 8.5 feet above mean high 
water. (See Table 2-B for Authorizing Legislation.) 
2-4

NEW YORK, N.Y. DISTRICT 
Local cooperation. Complied with except that local 
interests must furnish suitable spoil-disposal areas for 
future maintenance as required, and must maintain a 
channel 12 feet deep and generally 200 feet wide from Loop 
Causeway Bridge over Long Creek to head of navigation in 
Freeport Creek at Mill Road. 
Thrminal facilities. Within area tributary to Jones Inlet 
there are a number of privately owned small wharves and 
40 boat repair and storage yards. The latter are equipped for 
repair of pleasure craft and fishing vessels. In addition, 
there are nine public wharves open to the public free of 
charge, with a total dockage of 2,180 feet. Additional 
terminals would have to be constructed for receipt of 
commercial freight in any sizable quantity. 
Operations and results during period. Reconnaissance 
Surveys cost $5,272. 
Condition as of September 30. Work under existing 
project was commenced August 1953 and completed June 
1959. 
8. LONG ISLAND INTRACOASTAL 
WATERWAY, N.Y. 
Location: Extends from East Rockaway Inlet, on the 
south side of Long Island, to Great Peconic Bay at eastern 
end of Long Island. Section included under this project 
extends from Great South Bay opposite Patchogue to the 
south end of Shinnecock Canal. (See Coast and Geodetic 
Survey Chart 578.) 
Existing project. A channel 100 feet wide and 6 feet 
deep at mean low water from the federally improved 
channel in Great South Bay, opposite Patchogue to south 
end of Shinnecock Canal. Section included in project is 34 
miles long. Mean tidal range varies from 1foot in Shinnecock 
Bay to 0.7 foot in Patchogue Bay; mean range of spring tides 
varies form 1.2 feet to 0.8 foot; irregular fluctuations due to 
wind and atmospheric pressure vary from 1.8 feet below 
mean low water to 12 feet above mean high water. (See 
'able 2-B for Authorizing Legislation.) 
Local cooperation. Complied with except local interests 
must furnish suitable spoil-disposal areas for future 
maintenance as required. 
Thrminal facilities. There are 17 boat repair and storage 
yards within the area immediately adjacent to the Federal 
improvement. There is ample room for expansion and 
development of terminals when future commerce warrants. 
Operations and results during period. A continuing 
contract for maintenance dredging of channel to restore 
project depths was awarded in FY 1982. Work started 
August 26, 1982 and was completed October 15, 1982. A 
total of 3,658 cubic yards, place measurement, of material 
were removed under the contract in FY 1983 at a final cost of 
$70,862. Reconnaissance surveys cost $31,215. 
Condition as of September 30. Work under the 
existing project was commenced October 1939 and 
completed September 1940. 
9. MORICHES INLET, N.Y. 
Location. On the south shore of Long Island, about 80 
miles by water east of the Battery, New York City. It is an 
opening through the narrow sandy barrier beach on the 
south shore of Long Island which separates the Atlantic 
Ocean from a series of interconnected bays. (See Coast and 
Geodetic Survey Chart 12352.) 
Existing project. Provides for a channel, 10 feet deep at 
mean low water and 200 feet wide extending from that 
depth in the Atlantic Ocean to Moriches Bay, a distance of 
0.8 mile; thence a channel 6 feet deep and 100 feet wide to 
the Long Island Intracoastal Waterway, a distance of 1.1 
miles; rehabilitation of the existing jetties and revetments. 
Estimate of cost for new work is $4,760,000 (October 
1983); including $50,000 from Coast Guard and $2,310,000 
to be contributed by local interests. (See T'able 2-B for Authorizing 
Legislation.) 
Local cooperation. The River and Harbor Act of July 
14, 1960 provides that local interests shall, prior to construction, 
agree to contribute in cash 45 percent of the construction 
by the Corps of Engineers andagree to contribute 
in cash 50 percent of the maintenance, operation, and replacement, 
or perform work of equal value when and as 
acceptable to the Chief of Engineers; and, provided further 
that in connection with the improvement of the inlet, local 
interests, prior to construction, agree to (a) make the cash 
contribution either a lump sum prior to commencement of 
the work, or in installments prior to commencement of pertinent 
work items, in accordance with work schedules as 
required by the Chief of Engineers, the final apportionment 
of cost to be made after actual costs have been determined; 
(b) furnish, free of cost to the United States, all lands, easements, 
rights-of-way and suitable spoil-disposal areas for 
the initial work and for subsequent maintenance when and 
as required; and (c) hold and save the United States free 
from damages due to the construction and maintenance of 
the project; (d) provide and maintain suitable terminal facilities 
when and as required for the accommodation of vessels 
that would navigate the inlets and adjacent bays, open to all 
on equal terms; and (e) maintain for the duration of the economic 
life of the project, continued public ownership of the 
publicly owned shores and their administration for public 
use, and continued availability for public use of the privately 
owned shores upon which a portion of the Federal 
share of the cost is based. Minor modifications of local cooperation 
are being coordinated with state. 
Terminal facilities. No terminals are within the area 
immediately adjacent to the Federal improvement. However, 
numerous public and private terminal facilities are 
available in Moriches bay and in the connecting canals. Several 
yacht clubs, boatyards, and public wharves and landings, 
and numerous private landings are located in Moriches 
Bay. The yacht clubs and boatyards have equipment for 
servicing boats. There are boat basins open to the public. 
The facilities existing in the bay are considered adequate for 
present and probable future needs under present conditions 
of Moriches Inlet. There is room for expansion should 
future commerce warrant. 
2-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Operations and results during period. Preconstruction 
planning resumed in October 1977. Coordination continued 
with Federal, State and local agencies on current 
problems and need for all project purposes (i.e, navigation; 
beach erosion control; water quality improvement). Formulated 
plans for single purpose navigation project. 
In January 1980, a breach occurred adjacent to the eastern 
jetty. Emergency funds ($11.3 million) were authorized 
under the authority of PL84-99 to close the breach. About 
1,185,000 cubic yards of sand fill were used to effect closure 
of the breach by March 1981. 
Condition as of September 30. Construction has not 
been initiated. Preconstruction planning (advance engineering 
and design) is continuing with the view to determining 
the best alternative plan for providing navigation 
improvements in view of existing conditions. 
10. NARROWS OF LAKE 
CHAMPLAIN, N.Y. AND VT. 
Location. This waterway, 37 miles long, comprises 
southern end of Lake Champlain and extends from Whitehall 
to Crown Point, N.Y. Project extends 13.5 miles from 
Whitehall, N.Y. at southern extremity of lake, northerly to 
Benson Landing., Vt. (See National Ocean Survey Chart 
14784). 
Previous projects. For details, see Annual Reports for 
1932, and 1963, pages 256 and 177, respectively. 
Existing project. A channel extending from Whitehall, 
N.Y., at head of Lake Champlain, to Benson Landing, 12 feet 
deep at low lake level and generally 150 feet wide, and installation 
of fender booms at Putts Rock, Putts Leap, Narrows 
near Dresden Pulpit Point and Cedar Mountain. 
Reference plane of low lake level is 93 feet above mean sea 
level. Section included in project is about 13.5 miles. Usual 
annual variation of lake level is 5.8 feet and extreme variation 
varies from 0.6 foot below up to 8.8 feet above low lake 
level. 
Widening channel throughout its entire length to project 
width of 200 feet is inactive and excluded from foregoing 
description of existing project and cost estimate. Estimated 
cost of this portion, revised in (1954), was $1,573,000. (See 
T'able 2-B for Authorizing Legislation.) 
Local cooperation. None required. 
Thrminal facilities. In Whitehall Harbor consisting of 
three timber wharves, aggregating 4,200 feet in length. 
State of New York constructed a barge canal terminal at 
Whitehall, just south of terminus of canal, which has been 
equipped with a 5-ton hand-operated derrick and a storehouse. 
Facilities are considered adequate for present 
commerce. 
Operations and results during period. Government 
and hired labor were employed intermittently during the 
fiscal year in removal of stumps and snags at a cost of 
$10,805. 
Government plant and hired labor were employed in replacing 
deteriorated fender booms at a cost of $11,742. Tbtal 
costs for the project were $26,547. 
Condition as of September 30. Work under the existing 
project was commenced June 1919 and is about 77 percent 
complete. A channel 12 feet deep at low lake level and 
least a width of 150 feet has been excavated throughout the 
length of the improvement, except at the Elbow (Putts Leap 
and Putts Rock). (Fender booms opposite the Delaware and 
Hudson Railroad trestle have been removed as they are no 
longer considered necessary for navigation). The work remaining 
to complete the project consists of widening the 
channel throughout its entire length to the project width of 
200 feet. 
11. NEWARK BAY, HACKENSACK 
AND PASSAIC RIVERS, N.J. 
Location. Newark Bay is an estuary about 1.25 miles 
wide and 6 miles long extending southerly from confluence 
of Hackensack and Passaic Rivers to New York and New Jersey 
Channels. Hackensack River rises near Haverstraw, 
Rockland County, N.Y. and flows about 45 miles into Newark 
bay. Passaic River rises in highlands of northeastern 
New Jersey and flows about 80 miles into Newark Bay. (See 
Coast and Geodetic Survey Charts 285 and 287.) 
Previous projects.-For details see 1926 Annual Report, 
pages 265 and 266; and Annual Reports for 1929, 1938, 
1954, and 1976, pages 301, 244,134, and 2-11, 
respectively. 
Existing project. A main channel 700 feet wide to the 
branch channel to Port Newark, thence 500 feet wide to a 
turning basin 1,300 feet long and 900 feet wide at the junction 
of the Hackensack and Passaic River channels, length 
about 4.7 miles; a maneuvering area south of the former 
Central Railroad of New Jersey Bridge 2,200 feet long and 
300 feet wide with depths of 38 feet in the south half and 35 
feet in the north half; a combined bend cutoff and maneuvering 
area at the south side of the junction with Elizabeth 
branch channel; and widening of bends at the Kill Van Kull 
and Port Newark Channels. (Authorized depth 35 feet except 
as noted above) (adopted 1966). 
At Port Newark-A branch channel 800 feet wide leading 
to an inshore channel 400 feet wide 1.6 miles (adopted 
1945). Authorized depth 37 feet in rock and 35 feet in soft 
material; a pierhead channel 200 feet wide along the east 
bulkhead between the Port Newark and Elizabeth branch 
channels, length 4,100 feet Authorized depth 35 feet 
(adopted 1962). 
At Elizabeth Marine Trminal-a branch channel 500 feet 
wide, length about 1.4 miles; a pierhead channel along the 
east bulkhead 290 feet wide, length about 1.1 miles; a south 
channel along the south bulkhead 290 feet wide, length 
about 2,600 feet; a southern approach area just above Central 
Railroad of New Jersey Bridge enlarged for turning and 
maneuvering, with a maximum length of about 2,700 feet 
and width (between the pierhead channel and Newark Bay 
channel) of about 800 feet. Authorized depth 35 feet 
(adopted 1962). 
2-6

NEW YORK, N.Y. DISTRICT 
Local cooperation. River and Harbor Act of 1954 provides 
local interests furnish lands, rights-of-way, and suitable 
spoil-disposal areas for initial construction and future 
maintenance; provide depths commensurate with channel 
depth in approaches and berths at terminals of companies 
which would use improvement; and hold the United States 
free from damages. River and Harbor Act of 1962 provides 
that local interests must provide lands, easements and 
rights-of way for maintenance and construction, hold 
United States free from damages, provide and maintain adequate 
public terminal and transfer facilities, and accomplish 
without cost to the United States, removal or relocation of 
pipelines, cable and other utilities. Assurances were furnished 
by Port of New York Authority and accepted June 12, 
1964. Local cooperation required by previous modifications 
is fully complied with. 
'brminal facilities. See Port Series No. 5, revised 1978, 
Vol. 2. 
Operations and results during period. A contract 
was awarded May 3, 1983 for removal and satisfactory disposal 
of all material except ledge rock lying above the plane 
of 35 feet below mean low water in specified sections of Port 
Newark Inshore Channel and Port Newark Pierhead Channel, 
Newark Bay, N.J. Work commenced May 23, 1983 and 
was completed July 14, 1983. Removed 355,468 cubic 
yards, place measurement, of material at a cost of 
$1,696,482. 
A contract was awarded May 12, 1983 for the removal and 
satisfactory disposal of all material except ledge rock lying 
above the plane of 30 feet below mean low water in specified 
sections of th Passaic River Channel. Work commenced 
July 14, 1983 and was completed September 23, 1983. Removed 
540,000 cubic yards, place measurement, of material 
at a cost of $1,809,653. Reconnaissance surveys cost 
$46,359. 
Condition as of September 30. Work under the active 
portion of project began June 1976 and is 100 percent complete. 
Work remaining to complete existing project consists 
of: deepening the Hackensack River channel to depths of 32 
feet and 15 feet. 
Work was initiated for modification of project consisting of 
additional widening at junction with Kill Van Kull by deepening 
to 37 feet a triangular area at the eastern end of the 30 
foot channel south of Shooters Island. Two contracts for the 
removal of all material including ledge rock to 37 feet mean 
low water were completed at a total cost of $4,402,631. 
12. NEW YORK AND NEW JERSEY 
CHANNELS 
Location. Extends from deep water northwest of Sandy 
Hook, through Lower New York bay and Raritan bay, to 
Perth Amboy, and thence through Arthur Kill, lower Newark 
Bay, and Kill Van Kull to deep water in Upper New York 
Bay. This route is approximately along boundary line between 
States of New York and New Jersey. (See Coast and 
Geodetic Survey Charts 285,286, and 369.) 
Previous projects. For details see 1963 Annual Report 
pages 184 and 185. 
Existing project. A channel through Lower New York 
Bay, Raritan Bay, Arthur Kill, lower Newark Bay, and Kill 
Van Kull to Upper New York Bay, depths of 37 feet in rock 
and 35 feet in soft material throughout, 600 feet wide across 
Lower New York Bay and Raritan Bay and in Arthur Kill to a 
point 1,000 feet north of Smith Creek, widened to 800 feet 
in vicinities of Seguine Point and Wards Point, respectively; 
thence 500 wide to a point 1,000 feet south of Piles Creek; 
thence 500 to 600 feet wide and passing north of Shooters 
Island and protected by a dike on its northern side to junction 
of channel into Newark Bay; thence 800 feet wide 
through Kill Van Kull to Constable Hook; thence 1,000 feet 
wide from a point opposite the east end of Constable Hook to 
a point near the intersection with the channel along New 
Jersey pierhead line; and thence 1,400 feet wide through 
Kill Van Kull to Upper New York Bay; with an anchorage 38 
feet deep to accommodate five vessels south of Perth Amboy, 
all with suitable easing at bends and junctions. Section 
included in project is 30.8 miles long. In addition, construction 
of a dike north of Shooters Island and two secondary 
channels 30 feet deep and 400 feet wide, one south of Shooters 
Island and the other in Raritan Bay connecting with 
Raritan River, were completed under previous projects and 
maintained under existing project. A triangular area at the 
eastern end of the 30 foot channel south of Shooters Island 
was deepened to 35 feet in order to provide additional widening 
in the vicinity of Bergen Point and is included in the 
Newark Bay project. All depths refer to plane of mean low 
water. Mean range of tides varies between 4.7 and 5.1 feet; 
mean range of spring tides, 5.7. to 6.3 feet; irregular fluctuations 
due to wind and atmospheric pressure vary from 3.9 
feet below mean low water up to 6.9 feet above mean high 
water. Anchorage at Sandy Hook, and cutoff at junction of 
Main Ship Channel are deferred for restudy and excluded 
from foregoing description and cost estimate. Estimated 
cost of this portion (1957) is $2,150,000. (See 'Pable 2-B for 
Authorizing Legislation.) 
Local cooperation. Fully complied with except for the 
middle section of Arthur Kill where local interest must furnish 
spoil disposal areas for maintenance. 
T erminal facilities. See Port Series No. 5, revised 
1978, Vol. 2. 
Operations and results during period. A continuing 
contract for maintenance dredging of Perth Amboy Anchorage 
to restore project depths was awarded in FY 1982. Work 
was completed January 11, 1983. Removed 504,377 cubic 
yards, place measurement, of material were removed under 
this contract in FY 1983 at a final cost of $354,834. A 
total of $18,757 were expended in FY 1983 for engineering 
and design of maintenance dredging specifications for work 
to be accomplished in Arthur Kill, N.Y. in FY 1984. 
Adjustment to FY 1982 Annual Report: removed 447,723 
cubic yards, place measurement, of material under a contract 
for dredging of Channel North of Shooters Island, N.Y. 
at a final cost for FY 1983 of $284,963. Reconnaissance surveys 
cost $205,199. 
Conditions as of September 30. Work under active 
portion of existing project began in October 1933. Work 
completed consists of providing authorized project depth 
and widths throughout entire channel from Lower New 
2-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
York Bay to Upper New York Bay and providing depths of 37 
and 25 feet in Perth Amboy Anchorage. In addition to above 
mentioned work, construction of a dike north of Shooters 
Island, two secondary channels 30 feet deep and 400 feet 
wide, one south of Shooters Island, the other in Raritan Bay 
connecting with Raritan River were completed under previous 
projects. Work remaining under existing project consists 
of dredging cutoff at junction of Main Ship Channel to 
dimensions authorized by River and Harbor Acts of August 
30,1935, and May 17, 1950, dredging anchorage in vicinity 
of Sandy Hook. (See Table 2-D for total cost for existing project 
to September 30, 1982.) 
13. NEW YORK HARBOR COLLECTION 
AND REMOVAL OF DRIFT 
Location. Applies to Lower and Upper Bays, New York 
Harbor: East River, Harlem River, Hudson River Channel, 
N.Y, New York and New Jersey Channels, Newark Bay, 
N.J., and their tributaries. 
Existing project. Provides for collection, removal and 
disposal of drift, derelict vessels, deteriorated shore structures 
and debris along shores of New York Harbor and tributary 
waters, and for the repair of certain other piers, 
wharves and shore structures. Work authorized before Act 
of 1970 was restricted solely to removal of drift from waterways 
and was funded as a maintenance activity. Estimate of 
first cost of improvement under Act of 1974 is $80,300,000 
(October 1983) including $26,800.000 cash contribution 
from local interests, plus $55,000,000 to be contributed for 
repair and disposal of deteriorated shore structures in use. 
(See Table 2-B for Authorizing Legislation.) 
Local cooperation. Local cooperation conditions of the 
plans currently under review by the Chief of Engineers provide 
that local interests must furnish all lands, easements 
and rights-of-way required for the improvement; hold the 
United States free from damages; enact and enforce local 
legislation to prevent creation of sources of drift, contribute 
in cash one third of the first cost of the Federal work, and 
make necessary repairs to deteriorated structures in use so 
as to eliminate them as a source of drift. These conditions 
are subject to approval by the Secretary of the Army and 
the President, as stipulated in Section 113 of the authorizing 
law, Public Law 91-611. 
Operations and results during period. New work: 
Liberty State Park Contract IVB was completed at a cost of 
$1,197,974. East River-Manhattan Waterfront contract was 
completed at a cost of $1,477,806. A contract for the removal 
of Piers 17 and 18 on the East River was completed at 
a cost of $219,609. The city of Elizabeth contract was completed 
at a cost of $761,171. A contract for the City of Hoboken 
reach was awarded in August 1983 at an estimated cost 
of $1,663,244. A continuing contract for the Stapleton, Staten 
Island reach was awarded in September 1983 at an estimated 
cost of $2,544,400. Engineering and design for the 
balance of project continued. 
Maintenance. U.S. Debris Boats Driftmaster, Gelberman 
and Hayward and auxiliary plant were assigned the 
work of removing and disposing of drift. Removed and disposed 
of 619,598 cubic feet (4,840 cords) of driftwood, ranging 
in size from small blocks to timbers of large dimensions, 
including piles and pieces of wreckage at a cost of 
$3,254,871 in FY 1983. 
Conditions as of September 30. Work authorized under 
River and Harbor Acts of 1915, 1917 and 1930 is continuous 
maintenance for which no percentage of completion 
exists. For work authorized by the 1974 Water Resources 
Development Act, removal of drift sources has been completed 
in New Jersey at Liberty State Park and the City of 
Elizabeth. In New York City, work has been completed along 
the Manhattan side of the East River inclusive of Piers 17 
and 18. Removal work is currently underway in Hoboken, 
N.J. and Stapleton, Staten Island. 
14. NEW YORK HARBORENTRANCE 
CHANNELS AND 
ANCHORAGE AREAS 
Location. In Upper and Lower bays New York Harbor is 
330 miles southwest by water of Boston Harbor, Mass., and 
165 miles northeast of entrance to Delaware Bay, N.J. The 
Upper Bay extends about 5.5 miles southerly from junction 
of Hudson and East Rivers opposite the Battery, New York 
City; to the Narrows. Lower Bay extends about 9 miles from 
the Narrows to the sea. (See National Ocean Survey Charts 
12327, 12334, 12335, and 12349.) 
Existing project. Ambrose Channel 45 feet deep and 
2,000 feet wide, extending about 10.2 miles from the sea to 
deep water in the Lower bay; Anchorage Channel, an extension 
of Ambrose Channel, with same depth and width, 
in the Upper bay, opposite anchorage grounds, about 5.7 
miles long; a southerly entrance channel, Sandy Hook 
Channel (East Section) 35 feet deep and generally 800 feet 
wide extending 3.4 miles from 35-foot ocean contour to 
Bayside Channel along an alignment generally west of the 
South Channel; and elimination from authorized project of 
that portion of Bayside-Gedney Channel east of junction 
with new southerly entrance channel; for Bayside Channel 
35 feet deep and 800 feet wide, extending about 3.7 miles 
from junction with new southerly entrance to junction with 
Main Ship Channel; Main Ship Channel 30 feet deep and 
1,000 feet wide, extending about 5.3 miles from Bayside 
Channel to deep water in Lower bay; a channel along New 
Jersey pierhead line connecting Kill Van Kull with deep water 
in Anchorage Channel, south of Liberty Island anchorage, 
20 feet deep for 500 feet wide with widening at bends to 
800 feet and about 3 miles long; an anchorage in vicinity of 
Liberty (Bedloes) Island (about 160 acres in extent) 20 feet 
deep; and for removal of Craven Shoal to 30 feet deep; for a 
channel 16 feet deep, 200 feet wide, and about 2.3 miles 
long, extending from bell buoy 23 to Hoffman and Swinburne 
Island; for an anchorage area in Red Hook Flats to 
depths of 45, 40 and 35 feet and an anchorage area in Gravesend 
Bay to 47 feet deep. Project depths refer to mean low 
water. Mean tidal range is 4.7 feet at Fort Hamilton; mean 
range of spring tides, 5.7 feet; irregular fluctuations due to 
wind and atmospheric pressure vary from 3.9 feet below 
mean low water up to 6.2 feet above mean high water. 
Local Cooperation. Fully complied with. 
2-8

NEW YORK, N.Y. DISTRICT 
Trminal facilities. See Port Series No. 5, revised Vol. 
2, 1978. 
Operations and results during period. A contract 
was awarded October 15, 1982 for maintenance dredging of 
Ambrose Channel and Sandy Hook Channel, N.Y. This work 
was performed in conjunction with the Beach Nourishment 
of Sandy Hook Unit Gateway National Recreational Area, 
N.J. Operations and maintenance funds in the amount of 
$5,418,813 were used for the dredging portion of the contract. 
A contract was awarded June 30, 1983 at an estimated 
cost of $1,880,354. Jobs Bill funds in the amount of $50,000 
was expended for dredging to be performed in specified sections 
of Red Hook Flats Anchorage, N.Y. Capping Program 
delayed commencement of work until FY 1984. Reconnaissance 
surveys cost $187,848. 
Condition as of September 30. Work under existing 
project began in 1885 and is 100 percent complete. Main 
Ship and Bayside-Gedney Channels were completed to 30 
feet deep in February 1891. Deepening of Bayside-Gedney 
Channel to 35 feet for a width of 800 feet was completed in 
June 1939. Ambrose Channel was completed to 40 feet deep 
for a width of 2,000 feet in April 1914 and substantially completed 
to 45 feet deep for a width of 2,000 feet in 1951. Relocation 
of Anchorage Channel was completed to 40 feet deep 
in October 1932. Center 800 feet was dredged to 45 feet in 
June 1947 and westerly 600-foot strip in April 1948. Easterly 
600-foot strip was substantially completed in June 
1953. Channel between Staten Island and Hoffman and 
Swinburne Islands was completed in December 1920 up to 
within 300 feet of southerly limits of project. Dredged channel 
meets all needs of navigation and no further work of 
improvement is contemplated for the present. Channel 
along New Jersey pierhead line from Kill Van Kull to Anchorage 
Channel was completed in March 1939. Widening 
at bends near southerly and northerly ends authorized in 
1948 was completed in November 1960. Red Hook Flats anchorage 
was completed to depths of 45, 40 and 35 feet in 
October 1976. Anchorage Channel was relocated to the 
westward in 1982. Red Hook Flats Anchorage was accordingly 
increased in area. No dredging was required. Liberty 
(Bedloes) Island anchorage was completed to 20 feet in October 
1944. Sandy Hook Channel (east section) was completed 
to a depth of 35 feet in June 1963. Gravesend Bay 
Anchorage was completed to a 47-foot depth in November 
1977.
15. SHARK RIVER, N.J. 
Location. A small stream entering Atlantic Ocean 20 
miles south of Sandy Hook on the New Jersey coast. Forty 
miles by water south of the Battery, New York City. (See 
Coast and Geodetic Survey Charts 795 and 1215.) 
Existing project. A 1.7 mile channel 18 feet deep at 
mean low water and 150 feet wide across the bar at entrance 
to inlet; thence 12 feet deep and generally 100 feet 
wide through main channel and south channel to Route 35 
bridge; thence 8 feet deep and 100 feet wide to upper limit 
of the Belmar municipal boat basin, with additional depths 
and widths where necessary and practicable to produce satisfactory 
current velocities at bridges: and an anchorage 12 
feet deep over about 7.3 acres east of Route 4-N bridge. 
Mean tidal range at mouth is 4 feet; mean range of spring 
tides 4.8 feet; irregular fluctuations due to wind and atmospheric 
pressure vary from 2.6 feet below mean low water 
up to 8.4 feet above mean high water. New work for completed 
project cost was $150,000. (See T'able 2-B for Authorizing 
Legislation). 
Local Cooperation. Fully complied with except that local 
interests are required to furnish suitable spoil-disposal 
areas for maintenance. 
Terminal facilities. Two yacht basins are located on 
south shore of lower portion of Shark River. One is publicly 
owned and has a berthage of 2,600 feet. Several boatyards, 
boathouses, and landings for commercial and recreational 
craft are located in the lower portion of Shark River. 
Operations and results during period. Reconnaissance 
surveys cost $1,935. 
Condition as of September 30. Work under the existing 
project was commenced June 1947 and was completed 
October 1947. 
16. SHOAL HARBOR AND COMPTON 
CREEK, N.J. 
Location. Shoal Harbor is on south shore of Sandy Hook 
Bay about 4 miles west of Sandy Hook. Compton Creek is a 
small stream rising on the west side of the Navesink Highlands 
and flowing north through meadows into Shoal Harbor. 
(See Coast and Geodetic Survey chart 369.) 
Previous Projects. For details, see Annual Reports for 
1934 and 1938, pages 211, and 265 respectively. 
Existing project. A 1.8 mile channel 12 feet deep at 
mean low water extending from deep water in Sandy Hook 
Bay to first bend in creek, thence 8 feet deep to the Main 
Street Bridge across Compton Creek with a width of 150 feet 
in the bay and 75 feet inside the mouth of the creek, with 
widening at bends. Mean tidal range, 4.7 feet; mean range 
of spring tides, 5.6 feet; irregular fluctuations due to wind 
and atmospheric pressure vary from 3.8 feet below mean 
low water up to 5.9 feet above mean high water. New work 
for the completed portion of the project cost $107,572, exclusive 
of amounts expended on previous projects and exclusive 
of $77,247 expended from contributed funds. 
Dredging of channel in the creek to a depth of 8 feet to a 
point 1,000 feet upstream from Main Street Bridge is inactive 
and is excluded from foregoing description and cost estimate. 
Estimated cost of this portion (1957) is $52,000. (See 
Table 2-B for Authorizing Legislation.) 
Local Cooperation. The River and Harbor Act of March 
2, 1945, provides that no work shall be undertaken until 
harbor lines have been established by the Secretary of the 
Army along that portion of Compton Creek extending 1,000 
feet upstream from Main Street Bridge and until local interests 
have: (a) Conveyed to the United States, free of cost, a 
perpetual easement to excavate all lands above ordinary 
high water included between said harbor lines; and have 
removed all structures or ports thereof extending chan- 
2-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
nelward of said harbor lines; (b) furnished, free of cost to the 
United States, suitable areas for the disposal of dredged material 
for new work and subsequent maintenance as 
needed; (c) given releases to hold and save the United States 
free from all claims for damages resulting from the improvement; 
and (d) constructed the public wharf, assurances for 
which were furnished under the project of August 30, 1935, 
at location and in accordance with plans to be approved by 
the Chief of Engineers and Secretary of the Army and given 
assurances satisfactory to the Secretary of the Army and 
that they will maintain this wharf open to all on equal and 
reasonable terms. The clerk of Middletown Tbwnship was 
notified of conditions of local cooperation in letter dated 
January 18, 1946. A letter dated July 2, 1946, advised that 
township committee has given assurances that it will comply 
with all of above conditions. The requirements under 
prior acts have been fully complied with. The River and 
Harbor Act of September 3, 1954, further provides that local 
interests contribute in cash 50 percent of first cost of 
work, and agree to: (a) Furnish, without cost to the United 
States all lands, easements, rights-of-way, and suitable 
spoil-disposal areas for initial work and for subsequent 
maintenance when and as required; (b) hold and save the 
United States free from damages due to the construction 
and maintenance of the project; and (c) deepen to 14 feet 
the berths at the terminals along the improved section of 
channel; and provided further that no work shall be undertaken 
until local interests have complied with the outstanding 
condition of local cooperation required under existing 
project which pertains to construction of a public wharf. 
Assurances of compliance by local interests with requirements 
under Act of September 3, 1954, dated July 30, 1956, 
were accepted September 25, 1956 by the District Engineer 
for the United States of America. 
Trminal facilities. See Port Series No. 5, revised 1965, 
Vol. 2, Part 2, page 272. 
Operations and results during period. Jobs Bill funds 
in the amount of $50,000 and Operations and Maintenance 
funds in the amount of $22,616 were expended in FY 1983 
for engineering and design of maintenance dredging specifications 
for work to be accomplished in FY 1984. Reconnaissance 
surveys cost $1,410. 
Condition as of September 30. Work under the entire 
existing project is about 78 percent complete. Work under 
active portion of the existing project was commenced in August 
1936 and completed in November 1956. Work remaining 
to be done under the project consists of extending the 
8-foot channel 1,000 feet upstream from the Main Street 
bridge.
17. SHOOTERS ISLAND, N.Y. & N.J. 
Location. Shooters Island is located in the southernmost 
end of Newark Bay, about 500 feet off Staten Island, with 
largest portion in New York (Richmond County) and 
remainder in New Jersey (Hudson and Union Counties). 
Existing project. The removal of Shooters Island was 
authorized by the Water Resources Development Act of 
1976, PL94-587. The project plan consists of removal of all 
material, exclusive of drift sources, within the area defined 
by the Federal channels north and south of Shooters Island 
to a depth of 35 feet below mean low water, the material to 
be used for fill along the Arthur Kill. It includes the removal 
of soft material (4.5 million cubic yards) and rock (800,000 
cubic yards) with disposal of the material at Howland Hook 
and other landfill areas in the vicinity. Tbtal project cost is 
estimated at $72,600,000 with $1,000,000 estimated for 
preconstruction planning. It is estimated that project 
planning will take 4 years and project construction will take 
4 years. 
Local cooperation. Local interests would provide all 
necessary lands, easements, rights-of-way and disposal 
areas for the project; hold the United States free from 
damages; accomplish any necessary relocations; and make 
a cash contribution if determined appropriate. 
Tbrminal facilities. None. 
Operations and results during period. None. 
Conditions as of September 30. The Senate Appropriations 
Committee Report 95-1069 on FY1979 
Appropriations Bill directed the U.S. Army Corps of 
Engineers to prepare a report on the environmental 
impacts, cost sharing, and other aspects of the project. The 
report was submitted on August 6, 1979 recommending no 
Federal funds be provided. Due to no recent interest the 
study was classified inactive in March 1982. 
18. SUPERVISOR OF NEW YORK 
HARBOR 
(Prevention of Obstruction and Injurious Deposits) 
The District Engineer, New York District, was designated 
Supervisor of New York Harbor under the provisions of the 
River and Harbor Act of June 29, 1888 (33 U.S.C. 441-451), 
as amended July 12, 1952. Under this Act, the Supervisor of 
New York Harbor is charged with the mission of preventing 
the deposit of obstructive and injurious materials in New 
York Harbor and its adjacent and tributary waters, including 
Long Island Sound. The River and Harbor Act of August 18, 
1894 (33 U.S.C. 452) makes it unlawful for any person or 
persons to engage in fishing or dredging for shellfish in any 
of the channels leading to and from New York Harbor, or to 
interfere in any way with the safe navigation of those 
channels by ocean steamships and ships of deep draft; the 
River and Harbor Act of March 3, 1899 (33 U.S.C. 403,407, 
409) prohibits obstructions to navigable waters such as 
unauthorized structures, unauthorized fill, deposit of 
refuse, and willful or negligent abandonment of vessels. 
Other laws relating to the supervision of New York Harbor 
and its tributoary waters are the Clean Water Act, the 
Marine Protection, Research and Sanctuaries Act of 1972, 
the Coastal Zone Management Act of 1969, the Fish and 
Wildlife Act of 1956, the Federal Power Act of 1920, the 
National Historic Preservation Act of 1966, the Endangered 
Species Act of 1973, the Deepwater Port Act of 1972, the 
Wild and Scenic Rivers Act, and the Land and Water 
Conservation Fund Act. 
Direct supervision of the waters under the jurisdiction of 
the New York District was accomplished by means of two 
patrol vessels whose scope of duty includes surveillance of 
2-10

NEW YORK, N.Y. DISTRICT 
the waterfront for unauthorized construction or fill, 
surveillance to the 3-mile limit of tows enroute to dumping 
grounds in the Atlantic Ocean to ensure that material is not 
illegally deposited in the waters of New York Harbor, and 
investigation of wrecks and abandoned vessels. In addition 
to the patrol vessels, whose range of patrol was limited to 
New York Harbor, inspectors utilizing government vehicles 
equipped with two-way radios patrolled shorefront 
facilities and property. These inspectors operate out of field 
offices located at Jersey City, New Jersey, Troy and 
Riverhead, New York. Their duties include inspection of 
authorized construction, fill or excavation in waterways, 
including wetland areas, to ensure that work is performed 
in accordance with the Corps permit. The inspectors also 
patrol all waterways in their respective areas and inform 
the public of the Corps role and jurisdiction as well as 
provide assistance in the preparation of permit 
applications. (See Table 2-E at end of chapter.) 
19. RECONNAISSANCE AND 
CONDITION SURVEYS 
(See Table 2-F at end of chapter.) 
20. OTHER AUTHORIZED 
NAVIGATION PROJECTS 
(See Table 2-G at end of chapter.) 
21. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation Activities pursuant to Section 107, Public Law 
645, 86th congress as amended (Preauthorization). 
(See Table 2-N at end of Chapter.) 
Beach Erosion Control 
22. EAST ROCKAWAY INLET TO 
ROCKAWAY INLET & JAMAICA 
BAY, N.Y. (PT.I) 
Location. Atlantic coast of New York City, between East 
Rockaway and Rockaway Inlets, and the lands within and 
surrounding Jamaica Bay. The coastal area (about 10 miles 
long) is a peninsula in Queens County separating the ocean 
and the bay. (See Coast and Geodetic Survey Charts 12327, 
12350, and 12326.) 
Existing project. The project provides for approximately 
8.7 million cubic yards of sand fill including the 
advanced placement of a two year supply of beach 
nourishment, and Federal participation in the cost of 
periodic beach nourishment of the shore protection works 
for 10 yearsafter completion of the initial beach fill. Federal 
participation (50 percent) includes $8,833,500 (October 
1983) first cost and $17,966,500 for periodic beach 
nourishment, a total of $26,800,000. 
Local cooperation. Local interests must provide lands 
and rights-of-way, including borrow areas; bear 50 percent 
of total first cost presently estimated at $26,800,000 
consisting of a cash contribution of $8,930,000 the final 
apportionment of cost to be made after actual costs and 
values have been determined and $17,966,500 for periodic 
nourishment, total non-Federal cost $26,800,000, hold the 
United States free from damages; maintain, during 
economic life of project, continued public ownership and 
use of non-Federal publicly-owned shores upon which 
Federal participation in beach protection is based; maintain 
and operate all works after completion, control water 
pollution to the extent necessary to safeguard the health of 
bathers; local cooperation agreement was executed by the 
State May 17, 1974 and approved for Secretary of Army May 
31,1974. On May 22, 1974 sent to State an approved Escrow 
Agreement. 
Operations and results during period. Periodic 
Nourishment Contract #2 and groin construction at Beach 
149th Street completed in August and September 1982, 
respectively. 
Condition as of September 30. Advance engineering 
and design is completed. Final Environmental Impact 
Statement on file with Council of Environmental Quality on 
April 16, 1971. Initial beach restoration completed in 
FY1977. Contract for first increment of periodic 
nourishment completed in May 1980. Contract for second 
increment of periodic nourishment was completed in 
August 1982. Contract for construction of stone groin at 
Beach 149th Street was completed in September 1982. 
Contract for third periodic nourishment is scheduled to be 
awarded in May 1984. Completion of 10-year periodic 
nourishment remains. 
23. OTHER AUTHORIZED BEACH 
EROSION CONTROL PROJECTS 
(See Table 2-H at end of chapter.) 
24. BEACH EROSION CONTROL 
WORK UNDER SPECIAL 
AUTHORIZATION 
Beach Erosion Control activities pursuant to Section 
103 Public Law 826, 84th Congress as amended 
(preauthorization). 
(See Table 2-0 at end of chapter.) 
Flood Control 
25. ARDSLEY, N.Y. 
Location. The Village of Ardsley in Westchester County, 
New York is located on the Saw Mill River approximately 5 
miles upstream from its junction with the Hudson River. 
(See U.S. Geological Survey Map, White Plains, N.Y.) 
Existing project. The Federal flood control project 
provides for relocation of the existing channel from the 
upstream limit of the project downstream for approximately 
990 feet, and 240 feet of concrete flume 
upstream of the Ashford Avenue bridge. Upstream of this 
flume along the left bank of the Saw Mill River, 410 feet of 
2-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
floodwall would be constructed along the modified channel 
with an additional 340 feet of closure wall. Between the 
Conrail bridge and Elm Street in the downtown portion of 
the project, 145 feet of floodwall would be constructed on 
the right bank of the river. Ponding areas, drainage ditches 
and other drainage structures will be provided. The total 
estimated Federal cost for the project is $4,720,000 exclusive 
of land, relocations and other work to be provided 
by local interests at an estimated cost of $930,000 (October 
1983). 
Local cooperation. Local interests must provide all 
lands, easements and rights-of-way, including spoil areas, 
within the areas necessary for construction; hold and save 
the United States free from damages; maintain without 
expense to the United States all works after completion; 
provide without cost to the United States for relocation of 
utilities and resurfacing of a parking lot; protect the channel 
and flood control works from future encroachment or 
obstruction, including waste disposal, that would reduce 
their flood-carrying capacity; agree to take appropriate 
measures to control development of the fringe areas not 
protected by the improvement, with a view to preventing 
an undue increase in the flood damage potential; provide a 
pumping station or additional gravity outlets, due to the 
modification of or encroachment upon, such area by local 
interests; agree to adopt and enforce adequate land use and 
control measures in the area within the village along the 
Saw Mill River that will not be protected by the recommended 
project; agree to be bound by and to incorporate 
into any contract for construction the prescribed Equal 
Opportunity Clause, and to cooperate actively in obtaining 
the compliance of contractors and subcontractors with said 
Equal Opportunity Clause, in accordance with Title VI of 
Civil Rights Act of 1964 as it pertains to civil works projects; 
and at least annually notify interests affected that the 
improvements will not provide protection from floods 
greater than the design condition. 
New York State is the local cooperating agency. The New 
York State Department of Environmental Conservation, by 
letter dated January 25, 1982, reaffirmed the State's 
intention to cooperate in the proposed plan. 
Operation and results during period. Preconstruction 
planning continued. 
Condition as of September 30. Plan of Study 
approved in March 1979. Preconstruction planning started 
in February 1979. Preconstruction planning continued 
through Fiscal Year 1982. 
26. ELIZABETH, N.J. 
Location. In city of Elizabeth, N.J. (Union County), extending 
4.2 miles upstream from mouth of Elizabeth River 
at Arthur Kill. The river continues 7.7 miles northward 
through Union and Essex counties to its headwaters in East 
Orange, N.J. (See Geological Surveys quadrangles, Roselle, 
Elizabeth, Caldwall and Orange; and Army Map Service 
quadrangles, similarly designated.) 
Existing project. Includes an improved channel with 
levees and/or walls where necessary between Bridge Street 
and Arthur Kill (2.1 miles); a concrete channel between 
Trotter's Lane and U.S Highway No.1(1.4 miles); closure to 
high ground at upstream and downstream ends; interior 
drainage, including 5 pumping stations and 11 ponding areas; 
reconstruction or replacement of 16 bridges and associated 
street regrading; and utilities relocations. Total 
estimated Federal cost is $54,600,000. Total estimated non- 
Federal cost for all requirements of local cooperation excluding 
maintenance is $12,900,000 including $1,170,000 
cash contribution. (See Table 2-B for Authorizing Legislation.) 
Local cooperation. Local interests must provide lands 
and rights-of-way for construction and subsequent maintenance, 
the costs and values incurred in the interest of hurricane 
tidal flood protection to be credited to required local 
contribution to the project firsts costs allocated to hurricane 
tidal protection; hold the United States free from damages; 
maintain and operate completed works including all dredging 
required in the channel to maintain the design depths in 
the tidal reach; reconstruct all bridges and approaches except 
railroad bridges, and relocate existing sewerage and 
drainage facilities, streets, utilities, and other structures, 
such costs and values incurred in interest of hurricane tidal 
flood protection to be credited to required local contribution 
to protect first costs allocated to hurricane tidal flood protection; 
bear 30 percent of first costs allocated to hurricane 
tidal flood protection, including the two items listed above 
pertaining to lands, reconstruction and alterations, and a 
cash contribution now estimated at $1,170,000 to be paid 
either in a lump sum before starting construction, or in installments 
before starting construction, or in installments 
before starting pertinent work items in accordance with 
construction schedules as required by the Chief of Engineers; 
take necessary action to protect channels from future 
obstruction or encroachment including waste disposal that 
would reduce their flood-carrying capacity; take appropriate 
measures to control development in partially protected 
areas and fringe areas not included in the project with a 
view to preventing an undue increase in flood damage potential; 
maintain existing natural detention areas along the 
Elizabeth River between Union Avenue and Trotters Lane 
free from encroachment so as not to reduce their detention 
capacity; to provide any additional gravity outlets or pumping 
station capacities made necessary by any modifications 
or encroachments on the ponding areas; bearany increased 
Federal costs for the improvement that may result from any 
future requirements for parkway developments; and at 
least annually, notify interests affected that the improvements 
will not provide complete protection for fluvial floods 
greater than in July 1897. Agency responsible for local cooperation 
in City of Elizabeth (with concurrence of Union 
County and State of New Jersey). Signed assurances of local 
cooperation were accepted by the District Engineer on January 
9,1970. 
Operations and results during period. Construction 
of the Downstream Section was completed December 
17,1981. The Upstream Section of the project was awarded 
in March, 1982 at a cost of $20,904,464 through September 
30,1982 and is 32 percent complete. 
Condition as of September 30. Advance planning (begun 
January 1966), leading to first construction (Ursino Ba- 
2-12

NEW YORK, N.Y. DISTRICT 
sin) add the Penn-Central Bridge and downstream dredging 
contracts, has been completed. General design memorandum 
and its supplement submitted. Penn-Central Railroad 
Bridge agreement executed. Environmental Impact Statement 
submitted to the Council on Environmental Quality on 
April 20, 1971. Upstream Ursino Basin construction complete. 
Contract, executed with New Jersey Department of 
Transportation on June 2, 1977 for placement of 132 foot 
section of flume to be accomplished in conjunction wiht 
bridge replacement, has been completed. 
Conract for the Downstream Area Arthur Kill to U.S. 
Highway 1, was awarded September 29, 1978 and completed 
in December 1981. Upstream contract was awarded 
in March 1982. Project scheduled for completion in December 
1985. 
27. FIRE ISLAND INLET TO 
MONTAUK POINT, N.Y. 
Location. That portion of Atlantic Coast of Long Island 
in Suffolk County extending from Fire Island Inlet easterly 
to Montauk Point, N.Y. - about 83 miles long. This frontage, 
comprises about 70 percent of total ocean frontage of Long 
Island. Fire Island Inlet is about 50 miles by water east of the 
Battery, New York City. (See Coast and Geodetic Charts 
13209,12354 and 12353.) 
Existing project. Provides for Federal participation in 
improvement to prevent beach erosion and hurricane damages 
by: widening beaches along developed areas between 
Kismet and Mecox bay to a minimum width of 100 feet at 
elevation 14 feet above mean sea level; raising dunes to an 
elevation of 16 feet above mean sea level from Fire Island 
Inlet to Hither Hills State Park, at Montauk and opposite 
Lake Montauk Harbor; planting grass on dunes; constructing 
gated interior drainage structures at Mecox Bay, Sagaponack 
Lake, and Georgica Pond; constructing not to 
exceed 50 groins, if needed; and Federal participation in 
cost of beach nourishment for not to exceed 10 years from 
year of completion of a useful nourishment unit. Tbtal estimated 
Federal cost is $222,500,000 (October 1983) which 
includes participation in periodic beach nourishment for 10 
years at $200,000 annually. Tbtal estimated non-Federal 
cost for all requirements of local cooperation is 
$125,300,000 inclusive of $86,390,000 cash contribution by 
local interests. Project cost estimate reflects revised cost 
sharing provisions of 1962 River and Harbor Act. Increased 
Federal participation from about 53 percent due to an adjustment 
of cost sharing in accordance with Section 31 of 
the Water Resources Development Act of 1974 to about 70 
percent of first cost of project construction, excluding annual 
nourishment costs. 
Local cooperation. River and Harbor Act of 1960 provides 
that before starting construction, local interests give 
assurance they will (a) provide lands, rights-of-way, including 
borrow areas, for construction; (b) make alterations and 
relocations of buildings, streets, storm drains, utilities, and 
other structures made necessary by construction; (c) bear 
30 percent of total first cost estimated at$125,300,000 to 
consist of items listed in (a) and (b) above and a cash contribution 
estimated at $86,390,000 or, if any section is undertaken 
by separately apportionment of first cost will be as 
shown in District Engineer's report, with due regard to 
change in public use and ownership and other changes before 
construction; provided that cash contribution be paid 
either in a lump sum before starting entire project, or in 
installments before starting pertinent items, in accordance 
with construction schedules as required by Chief of Engineers, 
final apportionment of cost to be made after actual 
costs and values have been determined; (d) hold the United 
States free from damages; (e) maintain all works and undertake 
periodic beach nourishment after completion, except 
that for 10 years after completion of a useful nourishment 
unit Federal Government would contribute, dependent on 
conditions of public use and ownership and other changes 
at time of construction an amount for entire project now 
estimated at $200,000 annually; (f) maintain during economic 
life of project continued public ownership of non- 
Federal publicly owned shores and continued availability 
for public use of privately owned shore equivalent to that 
upon which recommended Federal participation is based; 
(g) adopt appropriate ordinances to provide for reservation 
of dunes and their protective vegetation; (h) control water 
pollution to extent necessary to safeguard health of bathers; 
(i) obtain approval of Chief of Engineers of detailed plans 
and specifications for work contemplated and arrangements 
for its prosecution before starting any work on beach, 
protection phase of project for which Federal participation 
is planned, if undertaken separately from recommended, 
combined project; and (j) contribute in cash toward cost of 
hurricane protection works constructed under this plan, in' 
addition to apportionment required in (c) above, an amount 
equal to increased Federal cost resulting from separate construction 
of beach protection work referred in to (i) above. 
Responsible agency is State of New York. 
On July 30,1963, the State reflected the desires of Suffolk. 
County, requested the inclusion of a minimum of 13 groins. 
in initial construction of Moriches-Shinnecock reach. Chief, 
of Engineers concurred in inclusion of up to 13 groins. Assurances 
were executed by Superintendent of Public Works, 
State of New York, on August 14, and accepted by the Dis 
trict Engineer August 20,1963. On February 5,1964, the, 
State requested consideration of a plan, as proposed by Suffolk 
County, for initial construction of 13 groins of which 11 
would be in the Moriches-Shinnecock reach, and 2 in the 
Southampton-Beach Hampton reach in vicinity of Georgica 
Pond; and that sandfill and dune construction.be withheld 
for the present except for 1 mile on each side of Shinnecock 
Inlet. On Fegruary 27,1964, the Chief of Engineers accepted 
the proposals, in part, and supplemental assurances 
were executed by State of New York on April 20, 1964, and 
accepted by District Engineer April 27,1964, as follows: the 
State of New York now elects to proceed with authorized 
combined beach erosion control and hurricane protection 
project for South Shore of Long Island; that Superintendent 
of Public Works hereby reaffirms his assurance of August 
14,1963, relative to complete project; that State of New 
York, as cooperating agency, will now agree that artificial 
fills will be added when and to extent found necessary by 
the Chief of Engineers, but not earlier than 3 years after 
completion of groins unless both the State of New York and 
the Chief of Engineers mutually agree to an earlier placement; 
that the superintendent agrees for State of New York 
to contribute the full amount of any increase in Federal 
2-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
costs resulting from the separate construction of the groins 
and subsequent fill; and that the State agree that construction 
of the two groins in the Georgica Pond area will depend 
on a favorable finding, following a study by the Chief of Engineers. 
Study was completed July 31,1964, recommending 
construction, and approved by the Chief of Engineers on 
September 22, 1964. By letter dated November 5, 1964, the 
New York State Department of Public Works confirmed that 
title to all properties and interests in properties necessary 
for constructing the 11 groins was fully vested in Suffolk 
County. 
By letter dated December 7, 1964, the Department stated 
that the county had obtained easements or fee title for the 
parcels necessary for constructing the two groins. New York 
State Department of Public Works furnished $884,600 and 
$830,330 required contributed funds October 30, 1964, and 
September 7, 1965, respectively, for construction of 11 
groins in Moriches-Shinnecock reach and $439,900 on January 
22 1965, for construction of 2 groins in Georgica Pond 
area of the Southampton-Beach Hampton reach. The completed 
2 groins and 11 groins were accepted by the New 
York State Department of Public Works for maintenance on 
May 11, 1966 and April 10, 1967, respectively. 
On March 22, 1965, the State recommended that planning 
priority be in the order: Southampton-Beach Hampton 
(drainage structures first); Shinnecock Inlet-Southampton; 
Beach Hampton-Montauk Point; and Fire Island Inlet- 
Moriches Inlet. Planning on the drainage structures was initiated 
but was suspended, based on: meeting of October 
28,1965 with Georgica Pond Association and the Preservation 
Society of East End wherein concern was indicated regarding 
the effects of the proposed drainage structure on 
ecology, salinity, pond level and aesthetic values; meeting 
with the Congressional representatives, State legislators, 
Federal agencies and local officials held on May 26, 1966; 
and resolution of the Suffolk County Board of Supervisors 
adopted June 13,1966 requesting advancement of the planning 
of the Fire Island-Moriches Inlet reach (Fire Island National 
Seashore). On June 16, 1967, the New York State 
Department of Public Works requested that the following 
works be undertaken as immediate priority items: in 
Moriches-Shinnecock reach, beach and dune fill at 11 groin 
site, construction of four groins west of the completed 11 
groins, beach and dune fill east of the 11 groins; in Southampton-
Beach Hampton reach (at East Hampton), construction 
of two additional groins, and the outlet structure 
at Georgica Pond. On March 18, 1968 the Suffolk County 
Board of Supervisors adopted a resolution supporting construction 
of 4 groins in Reach 2 (Moriches-Shinnecock) and 
2 groins in Reach 4 (Southampton-Beach Hampton). On 
April 22, 1968 the Board adopted a more inclusive resolution 
authorizing participation in beach erosion and hurricane 
protection for the Moriches-Shinnecock reach and in 
the Georgica Pond area of the Southampton-Beach Hampton 
reach. 
On December 24, 1968, the Commissioner of the New 
York State Conservation Department executed the second 
supplement to the assurances of local cooperation, which 
was accepted by the District Engineer on January 24, 1969. 
The reaffirmed previous assurances contained provisions 
for constructing four additional groins in an area extending 
6,000 feet west from the most westerly groin in the existing 
eleven-groin field in the Moriches Inlet to Shinnecock Inlet 
Reach, and for placing beach and dune fill in this area to the 
full design cross section as defined in the authorized project 
report, except for the portion of the dune mean sea level 
elevation 16 feet and 20 feet. Thus this stage construction 
established the top of the dune to an elevation of 16 feet 
m.s.l. with a 65 foot width at that elevation and the top of 
berm to 14 feet m.s.1. with a 100 foot width at that elevation. 
These assurances also required that the State obtain 
and provide without cost to the United States all lands, 
easements, and rights-of-way, to permit entry for the period 
of construction, and that the necessary rights will be obtained, 
as required, of lands, easements and rigths-of-way, 
for maintenance and repair of the groins, dunes, and berms, 
and to insure the integrity of the completed structure. (See 
Table 2-B for Authorizing Legislation.) Continued study of 
coastal protection needs for present and future conditions. 
Planning was completed in period for another increment of 
work at Westhampton Beach in the Moriches Inlet to Shinnecock 
Inlet reach consisting of placement of beach and 
dune fill in the initial 11 groin field constructed in 1966 and 
along the 9,500 feet of shore westward of the existing groin 
field. The draft Environmental Impact Statement on the entire 
project was revised and a final Environmental Impact 
Statement prepared for review and approval prior to submission 
to the Council on Environmental Quality. At the 
request of the local cooperating agency a Phase I design 
study was initiated in the Fire Island Inlet to Moriches Inlet 
reach of the project. This was terminated June 6, 1978 
when the Council on Environmental Quality recommended 
the project be reformulated. Active scoping for reformulation 
commenced in July 1979. 
Operations and results during period. Continued 
common base studies for reformulation. Public scoping 
meetings October 1980. Interagency scoping review meeting 
January 1980, with Federal agencies agreeing, but New 
York State having strong reservations. District Engineer of 
New York formalized his decision March 1980. Governor of 
New York and Council on Environmental Quality informed 
May 1980. Plan of study submitted July 1980. Initiation and 
the continuation of reformulation studies. 
Condition as of September 30. Engineering and design 
began November 1962 and project construction commenced 
in January 1965. Two groins in Reach 4: 
Southampton-Beach Hampton, Section 3, were initiated in 
March, and completed in September 1965, at a total cost of 
$720,950 of which $382,109 were incurred against required 
contributed funds. Eleven groins in Reach 2: Moriches- 
Shinnecock, Section 2, were initiated in January 1965, and 
completed in October 1966 at a total cost of $2,854,565 of 
which $1,370,191 were incurred against required contributed 
funds. Initial beach fill placement for 750,000 cubic 
yards in Reach 2, Section 1A was completed on May 23, 
1969. On August 4, 1969 work started on 4 groins and sandfill 
in Reach 2, Section 1A and was completed November 14, 
1970. 3,083 tons of stone and 1,111,000 cubic yards of sand 
was placed. 'Ibtal cost for all Section 1A was $3,663,455 including 
$1,791,428 required contributed funds. Planning 
for another increment of work at Westhampton Beach underway. 
Funds in the amount of $70,000 were alloted on 
2-14

NEW YORK, N.Y. DISTRICT 
April 14, 1977 for initiation of the Phase I study in Reach I, 
Fire Island Inlet to Moriches Inlet. Environmental Impact 
Statement on entire project prepared. The final Environmental 
Impact Statement was filed with Environmental 
Protection Agency on January 28, 1978. On March 7, 1978 
Department of the Interior supported by the other agencies 
referred the Environmental Impact Statement to Council on 
Environmental Quality as unacceptable. On June 6,1978, 
the Council on Environmental Quality agreed with the unacceptable 
finding and recommended project reformulation. 
Subsequent to strong objections on the project's final 
Environmental Impact Statement, meeting were held in 
September 1978, January and July 1979 with Department 
of Interior, Environmental Protection Agency and other interested 
Federal agencies. Subsequently, the Federal agencies 
have agreed to a basis for the reformulation of the Fire 
Island to Montaul Point project, including a general agreement 
on the studies necesary to answer the outstanding 
concerns. 
Public meetings were held in October 1979 in order to 
delineate the full scope and level of effort needed to reformulate 
the project. A final scoping session was held January 
17, 1980 and agreement reached between the Federal agencies 
although New York State had strong objections. A plan 
of study was submitted in July 1980. Reformulation will 
result in a new General Design Memorandum. However, because 
of New York State's inability to financially participate 
in construction at West Hampton Beach, reformulation will 
be indefinitely postponed after FY1983. Completion of the 
remaining scopes of work for reformulation, engineering 
and design, and construction of the project remain. 
Coordination made with the Departments of Interior and 
Commerce and the Environmental Protection Agency to develop 
an acceptable solution to mitigate immediate threats 
to property and human welfare at Westhampton beach 
where serious erosion is occurring. The interim plan has 
been accepted by the Departments of Interior and Commerce 
in letters dated December 22, 1978 and December 
21,1979 respectively. Subsequently, in a letter dated January 
18, 1979, Council on Environmental Quality approved 
the Corps' intention to take interim remedial action in cooperation 
with the interested agencies. 
The supplemental General Design Memorandum and the 
Environmental Analysis have been completed. Plans and 
specifications have been completed. Initiation of construction 
in Westhampton, scheduled for FY1981, has been indefinitely 
postponed due to NY State's inability to 
financially participate in the project at the present time. 
It should be noted that the proposed work at Westhampton 
Beach is a remedial measure to alleviate the present 
erosion problem. Upon completion of the reformulation 
study, the recommended plan of study will be implemented 
for the entire Fire Island Inlet to Montauk Point Reach, including 
Westhampton Beach. 
28. LIBERTY STATE PARK LEVEE 
AND SEAWALL, N.J. 
Location. At Liberty Park, in Jersey City, Hudson 
County, New Jersey, directly behind Ellis Island and the 
Statue of Liberty, in Upper New York Bay. (See Coast and 
Geodetic Survey Chart 12334.) 
Existing project. The Federal project provides for construction 
of a protective levee and seawall and landfill along 
the park shoreline, approximately 7,000 feet long, extending 
from south of Liberty Island to north of Ellis Island. Estimated 
first cost of improvement under the Water Resources 
Development Act of 1976 is $38,300,000 (October 1983) including 
$10,200,000 cash contribution from local interests. 
Local cooperation. Local cooperation conditions provide 
that local interests must furnish all necessary lands, 
easements, and rights-of-way for the project and contribute 
30 per centum of the total project costs exclusive of land 
costs. 
Operations and results during period. A contract 
was completed in 1983 at a cost of $2,785,000 for construction 
of the first area of the project at the southern extremity 
of the park. The costs of this contract were borne entirely by 
the State of New Jersey. Coordination and preconstruction 
planning for the remainder of the project continued. 
Condition as of September 80. Local-financed construction 
of the first area of the project was completed this 
year at an estimated cost of $2,785,000. Preconstruction 
planning for the remaider of the project continued. 
29. PASSAIC RIVER BASIN, 
N.J. & N.Y. 
Location. The Passaic River Basin, comprising 787 
square miles in northeastern New Jersey and 148 square 
miles in southern New York State, is located in the greater 
New York City Metropolitan area. The Passaic River Basin is 
roughly elliptical in shape 26 miles long and 56 miles wideand 
contains portions of Bergen, Essex, Morris, Passaic, 
Hudson, Somerset, Sussex and Union Counties in New Jersey. 
The Basin also includes parts of Orange and Rockland 
Counties in New York. 
Previous projects. Two Federal flood control projects 
have been completed by the Corps of Engineers in Passaic 
River Basin. 
A $67,400 desnagging, debris removal and channel restoration 
project was completed in 1951 along Beaver Brook 
and the Pequannock lbwnship Ditch, tributaries of the 
Pompton River in Pequannock 'Ibwnship, N.J. 
Along the Pompton River, a channel clearing project including 
shoal removal and channel restoration was implemented 
in the two-mile reach from the Delaware, 
Lackawanna and Western Railroad Bridge to the Erie Railroad 
(Greenwood Lake Branch) Bridge. This work, in Pequannock 
'Ibwnship, Wayne 'Ibwnship and Lincoln Park 
Borough, N.J., was completed in 1954 at a cost of $50,000. 
Existing project. The project was authorized for Phase 
I advance engineering and design study in Section 101 (a) of 
the Water Resources Development Act of 1976 in accordance 
with the February 18, 1976 report of the Chief of Engineers. 
The estimate of Federal Cost under the authorizing 
2-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
legislation is $1,200,000,000 (October 1982), plus a 
$2,820,000 cash contribution from local interests, and 
$137,180,000 for items of work to be contributed by local 
interests. The recommended plan for flood protection, navigation, 
hurricane protection and recreation, included a 
flood detention reservoir, channel diversions and modifications, 
levees and floodwalls, and streambank filling and 
grading. These works would provide protection against 
storm with a recurrence interval of 235 years, which is 20 
percent larger than the October 1903 flood of record. Six 
independent tributary local protection plans were also recommended. 
However, because of a lack of public support for 
structural components of the project in the New Jersey portion 
of the Basin, the entire project is being reformulated 
during the Phase I study. 
The House Public Works Committee Report (94-1702) on 
the 1976 Water Resources Development Act directed 
"...the reformulation of the plan for water management 
and flood control for the entire Passaic Basin." This report 
further states that local opposition to any plan which relies 
upon extensive use of dikes, dams and levees, such as those 
proposed in previous survey reports, mandates that the following 
alternatives, or any combination thereof, shall be 
the only ones surveyed and considered: (a) A full range of 
nonstructural flood control alternatives to include land acquisition, 
flood plain mapping, flood-proofing, developing 
early warning systems and relocation of buildings; (b) A 
tunnel diversion plan; (c) A system of tunnels addressing 
the needs of the entire basin; (d) Plans that combine local 
protection works where locally acceptable and nonstuctural 
solutions including improvements to stream carrying capacity 
in accordance with different needs in the Lower Basin 
and in the Central basin; (e) Evaluation of fulfilling 
water supply objectives together with flood control; (f) Aquifer 
recharge and underground storage; and (g) Reservoir 
management in the headwaters. The Phase I Study is evaluating 
these alternatives in the formulation of revised plans. 
Condition as of September 30. The reformulation 
study was initiated in October 1977 under the existing authorization 
and Congressional Guidance in House Report 
94-1702. The Study schedule runs through March 1986 at 
an estimated cost of $15,878,000. During FY 1982, major 
effort was directed toward the continuation of plan formulation 
of Basin-wide alternatives for the major flood damage 
areas along the mainstem Passaic River. This involves the 
analysis of alternatives including channel modifications, 
levees and floodwalls, tunnel diversions, detention basins, 
and preservation of natural storage. Investigations have 
shown that aquifer recharge is not a feasible measure for 
flood damage reduction in the Passaic Basin. Plan formulation 
has been completed for tributary flood damage areas 
along the Ramapo and Mahwah Rivers at Mahwah, N.J., 
and Suffern, N.Y., Molly Ann's Brook at Haledon, Prospect 
Park and Paterson, N.J., the Ramapo River at Oakland, 
N J., and the Lower Saddle River in Bergen County, N.J. 
These areas are being considered under the interim flood 
protection guidance provided by the Congress and are 
scheduled for recommendation prior to the completion of 
the overall study report. Plan formulation continues on the 
local damage area along the Upper Rockaway River. 
30. SAW MILL RIVER AT ELMSFORD 
AND GREENBURGH, N.Y. 
Location. On the Saw Mill River in the town of Greenburgh, 
N.Y. One portion known as Babbitt Court lies along 
the river immediately south of the Village of Elmsford. The 
second portion of the project, known as the Elmsford- 
Greenburgh area, is north of the Village of Elmsford, separated 
from Babbitt Court by approximately 4,000 feet. (See 
U.S. Geological Survey Map, White Plains, N.Y.) 
Existing project. In the Babbitt Court area, the project 
provides for approximately 1,450 feet of levees and flood 
walls with associated ponding and interior drainage facilities. 
Within the Elmsford-Greenburgh area, the existing 
channel is to be widened and deepened for 2,450 feet with 
an additional 600 feet of channel modification on the tributary 
Mine Brook. Levees and flood walls will be constructed 
on both banks of the Saw Mill River totalling approximately 
4,500 feet and extending along Mine Brook to high ground. 
Ponding areas, a pumping station and other drainage structures 
will be provided. The total estimated Federal cost for 
the project is $5,650,000 exclusive of land, relocations and 
other work to be provided by local interests at an estimated 
cost of $1,770,000 (See Table 2-B for Authorizing Legislation.) 
Local cooperation. Local interests must provide lands 
and rights-of-way for construction, including borrow, 
ponding, and waste disposal areas; hold the United States 
free from damages; maintain and operate completed works; 
provide all alterations, relocations, and necessary replacements 
of existing facilities, including bridges, highways, 
sewers, (including those storm sewers and drains required 
to convey interior drainage to improved channels of ponding 
areas) utilities, and railroad modifications and relocations 
other than bridges and bridge approaches; protect the 
channel and other flood works from future encroachment or 
obstruction, including waste disposal, which would reduce 
or otherwise impair their flood-carrying capacity, or provide 
a pumping station or additional gravity outlets, as appropriate, 
to compensate for any loss in ponding area 
effectiveness due to modification of or encroachment upon 
such areas; take appropriate measures to control development 
in partially protected areas and fringe areas not included 
in the project with a view toward preventing an 
undue increase in the flood damage potential; and at least 
annually, notify those affected that flooding will still be possible 
from large floods. New York State is the Local Cooperating 
Agency. The New York State Department of 
Environmental Conservation, by letter dated June 12, 
1974, indicated the State's intention to cooperate in the proposed 
plan. 
Operation and results during period. During Phase I 
preconstruction planning the authorized project was found 
to be no longer economically justified. Project reformulation 
to develop an alternative plan of improvement is continuing. 
Condition as of September 30. Plan of Study approved 
January 28, 1977. Preconstruction planning started 
in February 1977. Indications from Phase I Planning accomplished 
to date, are that some features of the authorized 
2-16

NEW YORK, N.Y. DISTRICT 
project are no longer economically justified. Alternative 
flood control measures are being considered during reformulation. 
31. SOUTH ELLENVILLE, N.Y. 
Location. In Ellenville, N.Y., on North Gully just above 
its confluence with Sandburg Creek, which discharges into 
Rondout Creek at Napanock, N.Y., about 2 miles downstream 
from Ellenville. (See U.S. Geological Survey, Ellenville 
quadrangle; Army Map Service, Ellenville quadrangle.) 
Existing project. Includes: a 2,300 foot concrete chute, 
a crib dam to prevent debris from entering chute; 380 feet or 
walls and a stilling basin; 823 feet of levees to protect 
against backwater from Sandburg Creek; a ponding area, 
drainage ditches and other interior drainage facilities. Physical 
model study to determine design of stilling basin required 
and authorized on August 28, 1970. Existing project, 
also known as "North Gully at Ellenville, N.Y.," is one of 
three physically and functionally independent projects included 
in Rondout Creek and Wallkill River, N.Y. and N.J. 
Survey Report. 
Estimated Federal cost for new work is $7,590,000 (October 
1983), exclusive of lands, relocations and other work to 
be provided by local interests at an estimated cost of 
$740,000. (See Table 2-B for Authorizing Legislation.) 
Local cooperation. Local interests must, prior to construction, 
give assurances they will furnish all lands, easements, 
and rights-of-way necessary for construction of 
improvements; perform all alteration of highways, highway 
bridges, utility and related facilities made necessary for 
construction of project; hold the United States free from 
damages; protect channels, ponding areas and other flood 
works from future encroachment or obstruction that would 
reduce their flood carrying capacity and control development 
of fringe areas not protected by proposed improvement 
with a view to preventing an undue increase in flood 
damage potential; and maintain and operate completed 
works. Agency responsible for local cooperation is State of 
New York. The Commissioner, New York State Department 
of Conservation (now Department of Environmental Conservation) 
executed assurances of local cooperation on 
March 5, 1968 which was accepted by the District Engineer 
for the United States on March 25, 1968. To comply with 
Section 221 of the Flood Control Act of 1970 (PL91-611), the 
preparation of an agreement of Local Cooperation is being 
initiated to replace the signed assurance. Implementation of 
project dependent upon N.Y. State's decision on proposed 
relocation of Route 52 located within project area. 
Operations and results during period. Continued coordination 
with the State of New York. 
Condition as of September 30. Preconstruction planning 
was started in January 1967. Model study completed in 
January 1972 and final report from Waterways Experiment 
Station received on May 4, 1974. General Design Memorandum 
submitted and returned for revisions. Environmental 
Impact Statement submitted to Council on Environmental 
Quality on July 27, 1971. Completion of engineering and 
design and construction remain. 
32. STATEN ISLAND, N.Y. 
Location. About 13 miles of coast along southern and 
eastern coast of Staten Island (a New York City borough) 
from Ft. Wadsworth at the Narrows to Tottenville at the 
mouth of Arthur Kill along Lower New York and Raritan 
Bays. (See National Ocean and Atmospheric Administration 
Charts and Geological Survey maps for New York and vicinity, 
Staten Island and Sandy Hook Bay area.) 
Existing project. Provides shore and hurricane protection 
between Graham and Oakwood Beaches and at Tottenville 
Beach; shore protection at Great Kills Park and 
between Arbutus Lake and Sequine Point. Improvement includes 
2.6 miles of beach fill and dunes at Tottenville Beach 
and between Graham and Oakwood Beaches; 2.2 miles of 
beach fill only at Great Kills Park and between Arbutus Lake 
and Sequine Point; 2.9 miles of levees at Tobttenville Beach, 
Graham Beach and between Oakwood Beach and Great Kills 
Park; two groins at Tottenville Beach and Sequine Point; 
interior drainage facilities including four pumping stations 
between Graham and Oakwood Beaches; and relocations. 
ENGCW-EZ April 7, 1970 5th Indorsement to NANEN-Br 
September 30, 1969 letter submitting Feasibility Study authorized 
continuing Design Memorandum to incorporate 
extension from Graham beach to Ft. Wadsworth. Total estimated 
Federal cost is $21,500,000 (October 1977) which includes 
participation in periodic beach nourishment for 10 
years at $112,000 annually. Total estimated non-Federal 
cost for all requirements of local cooperation is $11,200,000 
including $8,470,000 cash contribution, $1,520,000 for 
lands and relocation, $1,210,000 estimated annual beach 
nourishment cost for a 10-year period, and excludes annual 
nourishment costs thereafter and annual maintenance and 
replacement costs. (See Table 2-B for Authorizing Legislation.) 
Local cooperation. Local interests must provide lands 
and rights-of-way for construction; alter and relocate buildings, 
streets, storm drains, utilities and other structures; 
bear 34 percent of total first cost, estimated at $11,200,000 
to consist of the two items listed above and a cash contribution 
now estimated at $8,470,000 which excludes 
$1,210,000 for 10-year nourishment, or, if any section is 
undertaken separately the apportionment of first cost will 
be as shown in District Engineer's report, with due regard to 
change in public ownership and other changes before construction, 
provided that cash contribution be paid either in 
a lump sum before starting entire project, or in installments 
before starting pertinent items, final apportionment of cost 
to be made after actual costs and values have been determined; 
hold the United States free from damages; maintain 
completed works and provide periodic nourishment during 
economic life of the shore protection works subject to Federal 
participation in cost of periodic nourishment for an initial 
period of 10 years, non-Federal share of such costs for 
the 10-year period is presently estimated at 31 percent for 
Graham Beach to Oakwood Beach reach, 33 percent for Tottenville 
Beach reach, 30 percent for Great Kills Park reach, 
and 62 percent for Arbutus Lake to Sequine Point reach; 
maintain during economic life of project continued public 
ownership and administration of public use of non-Federal 
publicly owned shore upon which recommended Federal 
participation is based; adopt appropriate ordinances to pro- 
2-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
vide for preservation of dunes; and control water pollution 
to safeguard the health of bathers. If local interests elect to 
incorporate features in highway or other developments in 
the waterfront area which serve the purpose of hurricane 
protection. United States shall participate in cost of such 
features on a basis such that overall Federal cost for hurricane 
protection shall not be greater than that which would 
apply in the absence of such features, and such that any 
resultant savings in overall cost of combined features shall 
be shared equitably between the United States and local 
interests on the basis of cost allocation and cost apportionment 
approved by the Chief of Engineers, provided that 
such participation in the combined features shall be subject 
to the undertaking of any necessary remaining hurricane 
protection works by the United States. New York State Department 
of Public Works in letter dated December 1965 
stated it was prepared to execute assurances when plans 
are in final form. 
General Design Memorandum No.1, Ford Wadsworth to 
Great Kills Park, Ft. Wadsworth to Arthur Kill project Staten 
Island, New York submitted for review on June 30, 1976. 
Based on review of General Design Memorandum No. 1, additional 
engineering studies will be required subject to reconfirmation 
of New York State's intent to provide local 
cooperation required. In July 6, 1977 letter, New York State 
requested to reconfirm their intent to provide items of local 
cooperation for the project in light of New York City's fiscal 
condition.On October 30,1977, State of New York requested 
that reconfirmation of local cooperation be deferred one 
year. No answer has been received to date and the project 
has therefore been placed in a deferred status. 
Operations and results during period. None. 
Condition as of September 80. Preconstruction planning 
was started in January, 1966 and is about 99 percent 
complete. Feasibility Study of project extension from Graham 
Beach to Fort Wadsworth was authorized November 
16, 1967 and is complete. Coordination was initiated with 
the National Parks Services in connection with the Gateway 
National Recreation Area. In April 1974 local interest submitted 
their formal intent to support the modified plan. 
Draft Environmental Impact Statement furnished to Council 
on Environmental Quality on March 23, 1976. Public 
meeting on General Design Memorandum design plans for 
Ft. Wadsworth to Great Kills Park portion of project held on 
April 22, 1976. Final General Design Memorandum continued. 
By June 21, 1976 letter to the New York State Department 
of Environmental Conservation advised of the local 
desire for the concrete floodwall plan and their intent to 
support this plan. On October 30, 1977, State of New York 
requested that reconfirmation of the local cooperation be 
deferred one year. Project was place in a deferred status on 
January 31, 1978. Additional engineering studies and Post 
Authorization Change Report required on General Design 
Memorandum No.1 when and if local cooperation reconfirmed 
by New York State. 
33. YONKERS, N.Y. 
Location. On Saw Mill River in Yonkers, N.Y. About 1 
mile upstream from junction of Saw Mill and Hudson Rivers. 
(See Geological Survey, Yonkers quadrangle.) 
Existing project. Project provides for: constructing a 
20-foot wide concrete channel extending 3,781 feet along 
most congested reach of the channel; improving channel in 
other reaches (5,689 feet); constructing floodwalls (5,370 
feet), one closure structure, closure levee, various interior 
drainage facilities; reconstructing or raising of nine bridges, 
and miscellaneous utility changes. Estimated Federal cost 
of new work is $12,530,000 exclusive of land, relocations 
and other work to be provided by local interests at an estimated 
cost of $2,550,000. (See 'Table 2-B for Authorizing 
Legislation.) 
Local cooperation. Local interests must provide lands 
and rights-of-way for construction, including borrow, 
ponding, and waste disposal areas; hold the United States 
free from damages; maintain and operate completed works; 
provide all alterations, relocations, and necessary replacements 
of existing facilities, including bridges, highways, 
sewers, including those storm sewers and drains required 
to convey interior drainage to improved channels or ponding 
areas, utilities, and railroad modifications and relocations 
other than bridges and bridge approaches; protect the 
channel and other flood works from future encroachment or 
obstruction, including waste disposal, which would reduce 
or otherwise impair their flood-carrying capacity, or provide 
a pumping station or additional gravity outlets, as appropriate, 
to compensate for any loss in ponding area 
effectiveness due to modification of or encroachment upon 
such areas; take appropriate measures to control development 
in partially protected areas and fringe areas not included 
in the project with a view toward preventing an 
undue increase in the flood damage potential; and at least 
annually, notify those affected that flooding will still be possible 
from large floods. New York State is the Local Cooperating 
Agency. An agreement of Local Cooperation was 
signed by the Commissioner of the New York State Department 
of Environmental Conservation of April 9, 1974 and 
signed by the New York District Engineer on April 30, 1974 
for the United States and approved by the Secretary of the 
Army on May 17, 1974. The City of Yonkers, through the 
State, furnished $93,000 (contributed, funds "other") for 
non-Federal design costs. 
Operations and results during period. Construction 
of Contract #2 continue. 
Condition as of September 30. Started preconstruction 
planning December 1970. Phase I General Design 
Memorandum completed on October 1, 1973 and approved 
on April 19, 1974. Phase II General Design Memorandum 
completed and approved June 1, 1976. Agreement of Local 
Cooperation executed with New York State. Final Environmental 
Impact Statement and supplement in Federal Register 
on May 13, 1974, and August 13, 1976, respectively. 
Addendum filed with Council on Environmental Quality on 
August 25, 1976. Initial plans an specifications for Contract 
#1 completed and construction contract for this increment 
awarded August 30, 1974. Construction of Contract #1 completed. 
Construction for remaining increment of project 
(Contract #2) continued. Completion scheduled in May 
1984. 
2-18

NEW YORK, N.Y. DISTRICT 
34. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS. 
Inspections of completed flood control works are performed 
semi-annually to determine the extent of compliance 
by local interests with the requirements of operation 
and maintenance. 
35. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
(See Table 2-I at end of chapter.) 
36. DAM SAFETY PROGRAM 
Seismic and seepage investigations are currently underway 
at Waterbury Dam in Vermont. The Seismic investigations, 
begun in October of 1983 are being carried out for the 
New York District by the Baltimore District at an estimated 
cost of $210,000. Completion is scheduled for October of 
1984. Seepage investigations have been underway since 
April of 1980. One phase of the work was carried out by the 
Waterway Experiment Station and completed in early 1983. 
The second phase of investigations has just been initiated 
by the Baltimore District and is expected to be completed in 
two years. Under the Dam Safety Assurance Program, the 
New York District will be reconstructing the failed concrete 
outlet walls of East Barre Dam, also in Vermont. This work 
estimated to cost $200,000 is scheduled for FY1985. Both 
Waterbury Dam and East Barre Dam are operated and maintained 
by the State of Vermont. 
37. FLOOD CONTROL WORK 
UNDER SPECIAL 
AUTHORIZATION 
Flood Control Activities pursuant to Section 205, 
Public Law 858, 80th Congress as amended (Preauthorization) 
(See Table 2-P at end of Chapter.) 
Natural Disaster and Emergency Flood Control Activities 
pursuant to Public Law 84-99 and antecedent legislation - 
advance preparation, emergency operations, rehabilitation,
emergency drinking water and advance measures. 
Under "Advance Preparation," the New York District 
completed revisions of various emergency manuals, attended 
meetings and seminars dealing with emergency 
preparation and response, participated in emergency exercises 
and provided in-house training to District employees 
who would be involved in emergency operations. Under 
"Advanced Preparation" the District also maintained its 
stock of flood fighting supplies and equipment. 
Under "Emergency Operations" the New York District 
monitored the potential for ice jam flooding in Vermont and 
northeastern New York as well as the effects of severe winter 
storms which caused sighnificant shore erosion along 
the New Jersey and southern Long Island, New York coasts. 
The District also monitored the effects of Tropical Storm 
Dean and other extensive low pressure systems which 
caused extensive flooding of low-lying areas. Technical assistance 
and sandbags were provided to Clinton, Saratoga, 
Essex, Otsego and Rensselaer Counties, the City of Plattsburgh 
and the Town of Moreau in New York and the State of 
New Jersey and Morris County, New Jersey. A total of 
33,000 sandbags were dispensed during the fiscal year. 
38. EMERGENCY STREAMBANK 
AND SHORELINE PROTECTION 
Activities pursuant to Section 14, Public Law 526, 
79th Congress as amended (Preauthorization) 
(See Table 2-Q at end of Chapter.) 
39. DEBRIS REMOVAL WORK 
UNDER SPECIAL 
AUTHORIZATION 
Activities pursuant to Section 202, Public Law 
587, 94th Congress as amended (Preauthoriztion) 
The authorization for this work expired in fiscal year 
1979.
40. SURVEYS 
(See Table 2-J at end of chapter.) 
41. COLLECTION AND STUDY OF 
BASIC DATA 
Costs for the period of $162,816 for flood plain management 
services are set forth in' Table 2-L at the end of chapter. 
(See also Table 2-K on completed flood plain studies.) 
42. DEAUTHORIZED PROJECTS 
A total of 23 projects were deauthorized by Congressional 
Action pursuant to Section 12 of Public Law 93-251, Water 
Resources Development Act of 1976. (See Table 2-M at end 
of chapter.) 
2-19

REPORT OF THE CHIEF OF ENGINEERS, U.8. ARMY 1983 
TABLE 2-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in 'Ixt Projects Funding FY 80 FY 81 FY 82 FY 83 September 30,1983 
1. Aquatic Plant 
Control 
2. Bay Ridge & Red 
Hook Channels, N.Y. 
3. East Rockaway, 
N.Y. 
4. Fire Island ib 
Jones Inlet,N.Y. 
5. Flushing Bay and 
Creek, N.Y. 
6. Hudson River, N.Y. 
7. Jones Inlet, N.Y. 
8. Long Island 
Intracoastal 
Waterway, N.Y. 
(Required 
Contributed 
Funds) 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
45,000 
23,198 
1,818,710 
1,818,710 
74,000 
61,635 
84,000 
150,771 
105,000" 
102,224 
- 1,598,000 336,000 
- 1,590,956 343,044 
- -420,000 
- 29,365 
657,000 
957,000 
10,600 1,039,000 
10,600 988,914 
5,614 
-800 
45,349 
100,000 
129,779 
- 1,602,000 1,220,000 
- 1,599,894 1,111,251 
1,151 
867,000 
1,579,814 
1,726,700 
1,721,005 
-31,390 
2,451 
656,400 
661,987 
18 
488,000 1,838,256 
482,930 1,314,247 
284,400 1,315,000 
292,184 1,315,000 
887,000 
816,138 70,862 
618,806 
598,492 
5,523,2973' 
5,523,29731 
21,606,988 
21,606,988 
83,9694 
533,3344 
5,102,702 
5,098,764 
594,35532 
594,35532 
3,004,704 
3,040,097 
2,113,502s," 
2,102,905"11 
3,547,090 
3,436,235 
44,249,80356 
44,249,865 
26,151,415 
25,518,327 
1,822,53010 
1,822,53010 
9,329,210 
9,329,209 
235,964 
235,964 
3,253,862 
3,266,862 
9,182 
9,182 
2-20

NEW YORK, N.Y. DISTRICT 
TABLE 2-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Tbtal Cost to 
in Txt Projects Funding FY 80 FY 81 FY 82 FY 83 September 30,1983 
9. Moriches Inlet, 
N.Y. 
Required 
Contributed 
Funds) 
10. Narrows of Lake 
Champlain, N.Y. 
11. Newark Bay, 
Hackensack & 
Passaic Rivers, N.J. 
12. New York and New 
Jersey Channels 
13. New York Harbor- 
Collection and 
Removal of Drift 
(Required 
Contributed 
Funds) 
14. New York Harbor- 
Entrance Channels 
and Anchorage Areas 
15. Shark River, N.J. 
(Other Contributed 
unds) 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. & Oper. 
Approp. 
Cost 
New Work 
Approp. 
265,867 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
25,000 
62,948 
100,000 
47,534 
3,390,000 
23,000 
23,000 
2,000,000 
2,215,839 
-260,000 
-249,480 
140,500 
140,500 
1,40( 
76 
2,00 
2,02 
42( 
9 
60,390 
43,446 
24,400 
24,400 
16,000 
14,453 
- 2,224,000 
- 2,218,610 
2,617,600 
2,616,513 
0,000 584,000 
4,038 1,251,792 
1,000 2,195,700 
6,585 2,215,037 
- 2,752,200 
- 2,752,459 
0,000 333,000 
3,429 727,405 
8,644 
1,654,726 
2,288,438 
3,632,000 
3,623,281 
1,100,000 
1,293,239 
4,435,000 
4,363,879 
3,025,000 
2,850,030 
286,222 
181,077 
9,626 
20,660 
358,855 
25,000 
26,547 
630,000 
630,000 
7,681,000 
2,615,509 
680,000 
657,732 
2,570,000 
1,654,623 
- 
3,245,344 
470,259 
3,805,300 
970 
- 8,047,000 
- 7,525,976 
100,000 
98,362 
437,500 
2,895 
550,000 
545,294 
332,188 
6,221 
931,000 
930,999 
9,422 
9,422 
3,390,000 
402,301 
681,81112 
681,811 '2 
880,695 
880,674 
29,014,510 
29,014,511 
23,680,036 
18,614,545 
73,052,435'."."7 
73,052,435".'7.. 
29,444,359" 
29,776,761' 
454,773 
454,773 
12,599,0002 
11,458,627 
42,192,896"1 
42,387,718" 
9,891,013" 
9,845,646" 
4,376,282" 
45,009,710" 
45,009,7101" 
24,190,824 
26,430,737' 
150,000 
150,000 
1,125,404 
1,125,281 
437,500 
335,083 
2-21

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 2-A (Continued) COST AND FINANCIAL STATEMENT 
Shoal Harbor and 
aFunding 
Maint. 
Total Cost to 
FY 80 FY 81 FY 82 FY 83 September 30,1983 
Compton Creek, N.J. Approp. - - - 91,000 464,940" 
Cost - - - 72,616 446,556 " 
17. Shooters Islands, New Work 
N.Y. Approp. - - - - 100,000 
Cost 647 75 284 994 100,000 
18. Supervisor of New Maint. 
York Harbor Approp. 1,003,200 745,000 832,000 27,003,447 
Cost 881,233 1,002,417 745,758 784,221 26,955,084 
22. East Rockaway Inlet New Work 
to Rockaway Inlet Approp. 1,250,000 -420,000 3,800,000 - 12,750,356 
and Jamaica Bay, Cost 948,577 29,365 3,664,868 220,088 12,734,494 
N.Y. (Part I) 
(Required New Work 
Contributed Contrib. 751,752 - 3,457,300 127,660 14,804,961 
Funds) Cost 861,766 6,000 3,479,764 186,169 12,378,776 
25. Ardsley, N.Y. New Work 
Approp. 100,000 100,000 - - 300,000 
Cost 83,684 88,736 48,886 846 299,999 
26. Elizabeth, N.J. New Work 
Approp. 5,810,000 3,614,000 7,650,000 9,663,000 45,156,800 
Cost 5,345,348 3,792,146 7,841,068 8,841,979 44,162,821 
Other New Work 
ontributed Approp. 416,444 266,834 1,136,380 1,214,707 3,363,665 
Funds) Cost 721,605 482,853 882,918 1,635,180 4,035,090 
27. Fire Island Inlet New Work 
to Montauk Point Approp. 600,000 1,500,000 1,710,000 800,000 9,551,438 
N. Y. (Federal Cost 627,312 1,478,528 1,723,778 768,695 9,514,523 
Funds) 
Maint. 
Approp. - - - 100,000 113,973 
Cost - - - 129,780 143,753 
Required New Work 
ontributed Contrib. - - - - 4,012,930 
Funds) Cost 42,539 - 138,155 - 3,788,341 
28. Liberty State Park New Work 
Levee & Seawall, Approp. 62,043 78,000 -6,000 - 180,043 
N.J. Cost 26,441 87,078 20,519 - 180,038 
29. Passaic River Basin, New Work 
N.J. & N.Y. Phase I Approp. 2,506,700 2,645,950 1,845,076 1,634,000 11,985,7003 
Cost 2,507,415 2,645,950 1,845,076 1,635,287 11,918,9823 
30. Sawmill River, New Work 
Elmsford-Greenburg, Approp. 71,000 - - - 490,000 
N.Y. Cost 87,849 48,376 5,638 7,600 490,000 
31. South Ellenville, New Work 
N.Y. Approp. -10,000 - - - 289,700 
Cost 1,840 - 1,682 5,055 289,702 
32, Staten Island, N.Y. New Work 
Approp. - - - - 695,000 
Cost 2,272 3,357 2,475 1,210 694,998 
2-22 
See 
Section 
in Thxt Projects 
16.

NEW YORK, N.Y. DISTRICT 
TABLE 2-A (Continued) . COST AND FINANCIAL STATEMENT 
See 
Section Ibtal Coat to 
in Text Projects Funding FY 80 FY 81 FY 82 FY 88 September 80,1988 
33. Yonkers, N.Y. 
Other 
ontributed 
Funds) 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
2,200,000 2,552,000 
2,409,616 2,114,363 
61,200 
81,453 156,081 
1. Of which $12,500 is for North Atlantic Division Accounts. 
2. Of which $12,127 is for North Atlantic Division Accounts. 
3. Includes $1,040,00 for new work and $1,040,000 expended for the 
portion under construction general. 
4. Excludes $100,000 for new work expended from contributed funds 
and includes $82,600 for new work expended from public works funds. 
5. Deferred. 
6. Includes $5,112,594 for new work for previous project. 
7. Inlcudes $238,350 for new work expended from public works funds 
and $31,461 emergency relief funds. Excludes $81,373 expended from 
contributed funds, other. 
8. Excludes $454,273 expended between August 18,1915 and June 30, 
1935, for operation and care of lock and dam at Troy, N.Y., under 
permanent indefinite appropriation. Excludes $23,735 reimbursement for 
repairs to Troy Lock. 
9. Includes $628,502 for new work and $210,365 for maintenance for 
previous projects. 
10. Excludes $1,822,530 for new work expended from contributed 
funds. 
11. Excludes $419,879 for new work expended from contributed funds 
and $58,425 contributed funds from other, and $8,752 expended by the 
Worlds Fair Corp. for riprap protection of rubble dike. 
12. Includes $115,000 for new work for previous projects. 
13. Includes $19,140 for maintenance for previous projects. 
14. Includes $31,166 for U.S. Lake Survey Revisory and Inshore 
Sounding Program. 
15. Includes $12,809,975 for new work for previous projects and $6,621 
for new work for Lemon Creek, Staten Island, N.Y. 
16. Excludes $7,712 for new work expended from contributed funds. 
17. Includes $807,000 for new work expended from public works funmds 
and $2,023,308 for new work expended from emergency relief funds. 
18. Includes $1,160,380 for maintenance for previous project, and 
$1,621 for maintenance of Lemon Creek, Staten Island, N.Y. 
19. Includes $2,491,206 expended to date for construction of a landbased 
overfire air pit incinerator ($1,493,393 in maintenance funds and 
$997,813 in O&M funds). 
20. Includes $116,530 applied to removing wrecks authorized by acts 
prior to adoption of existing project. 
21. Includes $673,155 for new work for previous project. 
22. Includes $1,836,403 for new work expended from contributed 
funds. 
23. Excludes $285,600 for new work expended from contributed funds. 
24. For pilot progra to improve coastal storm warnings. 
25. Includes $1,490,713 for maintenance for previous projects. 
26. Includes $77,182 for new work for previous projects. 
27. Includes $66,000 for maintenance for previous projects. 
28. Includes $673,155 for new work for previous project. 
29. Excludes $292,685 for new work expended from Ordinance fuinds 
and $66,000 for new work expended from contributed funds. 
30. Includes $111,419 for maintenance for previous projects and 
$64,560 extended from public works funds. 
31. Includes $1,246,100 for new work for previous projects and $64,560 
extended from public works funds. 
32. Excludes $90,190 for new work expended from contributed funds. 
33. Includes $400,000 Jobs Bill funds. 
34. Includes $50,000 Jobs Bill funds. 
35. Includes $50,000 Jobs Bill funds. 
36. Includes $200,000 Jobs Bill funds. 
2-23 
1,115,834 
38,850 
141,804 
55,217 
51,004 
12,529,900 
12,477,976 
568,050 
622,871

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 2-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
River and Harbor 
Act of 1958 
Section 104 and Harbor 
Act of 1958 
Section 302 River and 
Harbor Act of 1965 
Mar. 3, 1899 
Mar. 2, 1907 
July 3, 1930 
July 3, 1930 
Aug. 26, 1937 
May 17, 1950 
Oct. 23, 1962 
June 25, 1910 
Mar. 3, 1925 
July 3 1930 
Aug 30, 19353 
June 20, 1938 
AQUATIC PLANT CONTROL (See Section 1 of Text) 
Control and Progressive eradication of obnoxious Aquatic Plant 
growths. 
Provided that all research and Planning cost to be borne fully by 
the United States. 
Modified project to include control of waterchesnut. 
BAY RIDGE AND RED HOOK CHANNELS, N.Y. 
(See Section 2 of Text) 
Channel 40 feet deep and 1,200 feet wide. 
Dredging to obtain first a depth of 35 feet, subsequently 
increasing depth of 40 feet for full width. 
Widening of Bay Ridge Channel to 1,780 feet. 
EAST ROCKAWAY INLET, N.Y. (See Section 3 of Text) 
Channel 12 feet deep and 250 feet wide, and a jetty. 
FIRE ISLAND TO JONES INLET, N.Y. 
(See Section 4 of Text) 
Construction of jetty. 
Channel 10 feet deep. 
FLUSHING BAY AND CREEK, N.Y. 
(See Section 5 of Text) 
15 foot bay, creek and branch channels; 15-foot maneuvering area; 
6-foot anchorage basin; revetment of dike extension; and abandonment 
of portion of creek channel and repair of dike. 
HUDSON RIVER, N.Y. (See Section 6 of Text) 
Channel 12 feet deep from Hudson to Waterford, remove State lock 
and dam at Troy and construct a new lock and dam. 2 
Channel 27 feet deep from Hudson to Albany, N.Y. 
Channel 27 feet deep below Hudson 
Operation and care of lock and dam at Troy were included 
in project July 1, 1935. 
Relocation of 12-foot channel between Troy and Waterford. 
Deepen channel between Albany and Waterford to 14 feet with 
no change in depths for harbors in front of Albany and Troy. 
H. Doc. 37, 85th Cong., 
1st sess. 
H. Doc. 337, 54th Cong. 2d sess. 
(Annual Report 1899, P. 1177). 
Rivers and Harbors Committee 
Doc. 44, 71st Cong., 
2d sess.' 
H. Doc. 19, 71st Cong., 
1st sess.' 
Rivers and Harbors Committee 
Doc. 33, 75th Cong., 1st sess. 
H. Doc. 762, 80th Cong., 
2d sess.' 
H. Doc. 551, 87th Cong., 
2d sess.' 
H. Doc. 719, 61st Cong., 
2d sess.' 
H. Doc. 350, 68th Cong., 
1st sess.' 
H. Doc. 210, 70th Cong., 
1st sess.' 
S. Doc. 155, 72nd Cong., 
2d sess.' 
H. Doc. 572, 75th Cong., 
3d sess.' 
2-24

NEW YORK, N.Y. DISTRICT 
TABLE 2-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Sep. 3, 1954 
P.L. 89-72 
Mar. 2, 1945 
August 26, 1937 
July 14, 1960 
Aug. 8, 1917 
Mar. 2, 1907 
Feb. 27, 1911 
July 25, 1912 
Jan. 21, 1927 
July 3, 1930 
Mar. 22, 1945 
Mar. 2, 1945 
Sept. 3, 1954 
Oct. 23, 1962 
Nov. 7, 1966 
Deepen channel between New York City and Albany to 32 
feet and construct a turning basin and 2 anchorages. 
Mooring facilities. 
JONES INLET, N.Y. (See Section 7 of Text) 
Construction of jetty and channel 12 feet deep and 250 feet wide 
LONG ISLAND INTRACOASTAL WATERWAY, N.Y. 
(See Section 8 of Text) 
Channel 6 feet deep and 100 feet wide. 
MORICHES INLET, N.Y. (See Section 9 of Text) 
Channel 10 feet deep and 200 feet wide. 
NARROWS OF LAKE CHAMPLAIN, N.Y. AND 
VERMONT (See Section 10 of Text) 
Channel 12 feet deep and 150 feet wide. 
NEWARK BAY, HACKENSACK AND PASSAIC 
RIVERS, N.J. (See Section 11 of Text) 
16-foot channel in Passaic River 
Widening 16-foot channel in Passaic River 
20-foot channel in Passaic River.7 
10-foot channel in Passaic River. 
30-foot channel in Passaic River. 
35 and 37 feet in main channel of Newark Bay and branch channel 
to an inshore channel at Port Newark terminal and remove 
portion of rock area at Bergen Point to same depths. 
Modification of local cooperation for 10-foot channel in Passaic 
River. 
34-32-foot channel in Hackensack River including approach 
channel in Newark Bay from branch channel at Port Newark 
Terminal and a 25-foot turning basin. 
35-foot channels at Port Elizabeth. 
Widening 35-foot channel in Newark Bay, provision of two 
maneuvering areas, widening entrance into Port Elizabeth and 
Port Newark branch channels, deepening and widening Newark 
Bay 32-foot channel, and provision of a turning Basin at junction 
of Hackensack and Passaic Rivers; and deepening 12-foot 
channel in Hackensack River to 15 feet. 
2-25 
H. Doc. 228, 83d Cong., 
1st sess.' 
H. Doc. 409, 77th Cong. 
H. Doc. 181, 75th Cong., 
1st sess. 
H. Doc. 126, 86th Cong., 
1st sess.' 
H. Doc. 1387, 62nd Cong., 
3d sess. 
H. Doc. 441, 59th Cong., 
2d sess. 
H. Doc. 441, 59th Cong., 
2d sess. 
H. Doc. 707, 62d Cong., 
2d sess. 
H. Doc. 284, 69th Cong., 
2d sess. 
H. Doc. 156,.71st Cong., 
2d sess.' 
S. Doc. 250, 79th Cong., 
2d sess. 
H. Doc. 430, 76th Cong., 
1st sess. 
H. Doc. 252, 82d Cong., 
1st sess.' 
H. Doc. 289, 88th Cong., 
2d sess. 
H. Doc. 494, 89th Cong., 
2d sess.'

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1988 
TABLE 2-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Sept. 6, 1933* 
Aug. 30, 1935 
May 28, 1935' 
May 17, 1950 
Oct. 27, 1965 
Mar. 4, 1915 
Aug. 8, 1917 
July 3, 1930 
Dec. 31, 1970 
Mar. 7, 1974 
July 5, 1884 
Mar. 3, 1899 
June 25, 1910 
Aug. 8, 1917 
Aug. 8, 1917 
Aug. 8, 1917 
July 3, 1930 
Aug. 30, 1935 
Additional widening at junction with Kill Van Kull by deepening to 
35 feet a triangular area at the eastern end of the 30-foot channel 
south of Shooters Island. 
NEW YORK AND NEW JERSEYS CHANNELS 
(See Section 12 of Text) 
Anchorage off Perth Amboy to 35 feet. 
Channels 35 feet deep from lower bay to upper bay, except 
between vicinity of Smith Creek and vicinity of Piles Creek 
to 30 feet with anchorage 38 feet deep at Sandy Hook and 
Perth Amboy. 
Channel 35 feet deep from vicinity of Smith Creek to vicinity of 
Piles Creek. 
Widen entrance to Kill Van Kull to 1,400 feet narrowing to a 
minimum width of 1,000 feet. 
NEW YORK HARBOR, COLLECTION AND REMOVAL 
OF DRIFT (See Section 18 of Text) 
Allotment from appropiations made for New York Harbor and its 
immediate tributaries may be used for collection and removal of 
drift in these waterways. 
Carrying on this work as a separate and distinct project. 
Increase scope of project to include removal and disposal of 
derelict vessels, some deteriorated shore structures and debris 
along shores; and the repair of other shore structures; all subject 
to approval by Secretary of the Army and the President. 
Removal and disposal of derelict vessels, some deteriorated shore 
structures and debris along shores and the repair of other shore 
structures. 
NEW YORK HARBOR, ENTRANCE CHANNELS AND 
ANCHORAGE AREAS (See Section 14 of Text) 
Main-Ship-Bayside-Gedney to 30 feet for width of 1,000 feet 
(dimensions fixed by Secretary of War, Dec. 27, 1886, by 
authority of act of Aug. 5, 1886). 
Ambrose Channel (East Channel) to 40 feet. 
Maintenance of entrance channel under 1 head. 
Anchorage Channel, extension of Ambrose Channel 
into Upper Bay. 
Removal of Craven Shoal 
Channel between Staten Island and Hoffman and 
Swinburne Islands. 
Relocation of southerly section of Anchorage Channel. 
Dredging south end of Red Hook Flats, Liberty Island Anchorage, 
and channel along New Jersey pierhead line. 
Report on file in the Office of the 
Chief of Engineers. 
Rivers and harbors Committee 
Doc. 17, 71st Cong., 2d sess. 
H. Doc. 133, 74th Cong., 
1st sess. 
H. Doc. 233, 81st Cong., 
1st sess. 
H. Doc. 108, 89th Cong., 
1st sess. 
P.L. 91-611, 91st 
Cong., H.R. 19877. 
P.L. 93-251, 93rd Cong., 
H.R. 10203 
Annual Reports 1887, p.62 and 
1888, p. 63 
H. Doc. 159, 55th Cong., 
3d sess. (Annual Report 
1899, p. 1279) 
H. Doc. 518, 63d Cong., 
2d sess. 
H. Doc. 557, 64th Cong., 
1st sess. 
H. Doc. 625, 64th Cong., 
1st sess. 
Rivers and Harbors Committee 
Doc. 18, 71st Cong., 2d sess. 
H. Doc. 183, 73d Cong., 
2d sess.' 
2-26

NEW YORK, N.Y. DISTRICT 
TABLE 2-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Aug. 30, 1935 
August. 26, 1937 
July 3, 1958 
Oct. 27, 1965 
Mar. 31, 1982 
Mar. 2, 1945 
Aug. 30, 1935 
March 2, 1945 
Sept. 3, 1954 
Water Resources 
Development Act 
1976, P.L. 94-587 
1965 Flood Control Act 
1974 Water Resources 
Development Act 
Section 201 
Flood Control Act 
of 1965 
1965 Flood Control Act 
Deepen Bayside-Gedney Channel to 35 feet for a width 
of 800 feet. 
Deepen Ambrose and Anchorage Channels to 45 feet for a 
width of 2,000 feet. 
Dredging South Channel, Elimination of portion of 
Bayside-Gedney Channel. 
Deepen and expand Red Hook Flats Anchorage. Deepen 
Gravesend Bay Anchorage. 
Further expansion of Red Hook Flats Anchorage and 
the relocation of Anchorage channel. 
SHARK RIVER, N.J. (See Section 15 of Text) 
Channel 18 feet deep, 150 feet wide across entrance bar, 12 feet 
deep 100 feet wide to Route 35 bridge, 8 feet deep 100 feet wide 
to upper limit of Belmar boat basin; and 12-foot anchorage. 
SHOAL HARBOR and COMP'I)N CREEK, N.J. 
(See Section 16 of Text) 
8-foot channel from the first bend in the creek to 
Main St. Bridge 
Extension of 8-foot channel to 1,000 feet upstream from Main St. 
Bridge. 
12-foot channel in bay to the first bend in the creek. 
SHOOTERS ISLAND, N.Y. & N.J. 
(See Section 17 of Text) 
Removal of the island within area defined by Federal channels 
north and south to a depth of 35 feet below mean low water. 
EAST ROCKAWAY INLET TO ROCKAWAY INLET AND 
JAMAICA BAY, N.Y. (PART 1). (See Section 22 of Text) 
Hurricane barrier, dikes, levees, floodwalls, fill placement, stoplog 
structures, stairways, ramps, road raising, fishing platforms, 
annual nourishment. 
Authorized beach erosion control aspect to be constructed 
independent of the hurricane flood protection aspect of 
the project. 
ARDSLEY, N.Y. (See Section 25 of Text) 
Channel improvement, concrete flume, flood walls, levees, 
various drainage structures. 
ELIZABETH, N.J. (See Section 26 of lext) 
Channel improvement, flume, levees, floodwalls, bridges, interior 
drainage facilities. 
H. Doc. 133, 74th Cong., 
1st sess.' 
Senate Commerce Doc., 
75th Cong., 1st sess.' 
S. Doc. 45, 84th Cong., 
1st sess. 
S. Doc. 17, 89th Cong., 
1st sess. 
OCE Leter 31 Mar. 1982 
H. Doc. 102, 76th Cong., 
1st sess.' 
H. Doc. 58, 73d Cong., 
1st Sess. 
H. Doc. 673, 76th Cong., 
3rd Sess. 
H. Doc. 89, 82d Cong., 
1st Sess. 
H. Doc. 215, 89th Cong., 
1st sess.' 
H. Doc. 215/89/1. 
Doc. 249, 89th Cong., 
1st sess. 
2-27

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 2-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
1960 River and Harbor 
Act 
1974 Water Resources 
Development Act 
1976 Water Resources 
Development Act 
1976 Water Resources 
Development Act 
Section 101 (a) 
1965 Flood Control Act 
1962 Flood Control Act 
1965 Flood Control Act 
1965 Flood Control Act 
FIRE ISLAND INLET TO MONTAUK POINT, N.Y. 
(See Section 27 of Text) 
Raising dunes, widening beaches, interior drainage structures, 
groins, beach replenishment, annual nourishment. 
Project modified to provide that non-Federal interest shall 
contribute 30 percent of the first costs. 
LIBERTY STATE PARK LEVEE AND SEAWALL, 
N.J. (See Section 28 of 'Text) 
Approximately 7,000 feet of seawall and elevated pedestrian 
walkway. 
PASSAIC RIVER BASIN, N.J. & N.Y. PHASE I 
(See Section 29 of 'Text) 
Advanced engineering and design study, involving reformulation 
of plans for flood control and water resource management. 
SAWW MILL RIVER at ELMSFORD and GREENBURGH, 
N.Y. (See Section 30 of Text) 
Levees, floodwalls, channel improvement. 
SOUTH ELLENVILLE, N.Y. (See Section 31 of Text) 
Levees, drainage ditches, walls, a concrete chute and a crib dam. 
STATEN ISLAND, N.Y. (See Section 32 of Tebxt) 
Beachfill, groins, drainage facilities, four pumping stations 
YONKERS, N.Y. (See Section 33 of Text) 
Channel improvement, concrete fume, flood walls, closure 
structure, various drainage facilities, reconstruct or raise 
nine bridges. 
H. Doc. 425, 86th Cong., 
2d sess. 
P.L. 93-251, 93rd Cong., 
H.R. 10203 
H. Rpt. 94-1702 
H. Doc. 94-465, 94th Cong., 
2d sess. 
S. Doc. 113, 87th Cong., 
2d sess.' 
H. Doc. 181, 89th Cong., 
1st sess.' 
H. Doc. 258, 89th Cong., 
1st sess.' 
1. Contains latest published maps. 
2. Widening to form harbors at Albany and Troy to 12 feet deep 
considered inactive. 
3. Public Works Administration, Sept. 6, 1933. 
4. Public Works Administration. 
5. Emergency Relief Act of 1935 
6. Portion from 3,000 feet above Lincoln Highway Bridge to Jackson 
Street Bridge complete. From Jackson Street Bridge to Nairn Linoleum 
Works considered inactive. 
2-28

NEW YORK, N.Y. DISTRICT 
TABLE 2-C HUDSON RIVER, N.Y. 
FEATURES OF LOCK AND DAM INCLUDED IN EXISTING PROJECT 
(See Section 6 of lext) 
Location: 
Below Waterford 
Above Battery, New York City 
Locks: 
Clear Width 
Greatest length available for full width 
Lift at lowest stages 
Depth on miter sills: 
Upper at normal pool level) 
Lower (at lowest low water) 
2.2 miles 
153.8 miles 
44.4 feet 
492.5 feet 
17.3 feet 
16.3 feet 
13.0 feet 
Character of foundation: Rock 
Kind of dam: Fixed Crest 
Type of construction: Concrete 
Completed: 1917 
Cost: $1,463,014 
TABEL 2-D TOTAL COSTS FOR EXISTING PROJECT TO 
SEPTERMBER 30, 1983 
See 
Section Operation 
of Thxt Project Funds New Work Rehabilitation Maintenance and Cost Total 
6. Hudson River, Regular $38,560,839 - $956,336 $471,656 $39,988,831 
N.Y. Public Works 238,350 - - - 238,350 
Emergency Relief 311,461 - - - 311,461 
TOTAL $39,110,650 - $956,336 $471,656 $40,538,642 
12. N.Y. and N.J. Regular $57,412,152 - $657,732 - $58,069,884 
Channels Public Works 807,000 - - - 807,000 
Emergency Relief 2,023,308 - - - 2,023,308 
Contributed 7,712 - - - 7,712 
TOTAL $60,250,172 - $657,732 - $60,907,904 
TABEL 2-E SUPERVISOR OF NEW YORK HARBOR 
(See Section 18 of Text 
STATEMENT OF ACTIVITIES-FY 1983 
1. Number of Patrols 
a. Shore 
b. Vessel 
c. Air (helicopter) 
TIbtal 
2. Number of Inspections 
a. Shore Facilities 
b. Vessels 
Ibtal 
3. Disposition of Cases 
a. Voluntary Restoration 
b. After-the-fact Permit Applications Accepted 
c. Permit not required or already under permit 
d. Submitted for litigation to OCE or US Attorney 
e. Cases pending as of October 1, 1982 
Tbtal 
535 
388 
- 
923 
4,815 
1,557 
6,372 
15 
42 
10
3 
32 
102 
2-29

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 2-F RECONNAISSANCE AND CONDITION SURVEYS FY 1983 
Name of Project Date Survey Conducted 
NEW JERSEY 
Keyport Harbor, N.J....................... .......... 
Matawan Creek, N.J................................. 
Newark Bay, Hackensack & Passaic Rivers, N.J............ 
Raritan River, N.J.................. . ........... 
Shark River, N.J................... ........... 
Shoal Harbor and Compton Creek, N.J................... 
Shrewbury River, N.J....................... .......... 
Dec. 1982 
Nov., Dec. 1982 
Feb. 1983 
Jul., Aug. 1983 
Apr. 1983 
Mar., Apr. 1983 
Jun., 1983 
NEW YORK 
Bay Ridge and Red Hook Channels, N.Y. ............. 
East Chester Creek, N.Y ....... ....................... 
East River, N.Y.................... ................ 
East Rockaway Inlet, N.Y............................. 
Fire Island Inlet, N.Y........................... 
Flushing Bay and Creek, N.Y........................... 
Great Lakes to Hudson River Waterway, N.Y.... ........... 
Harlem River, N.Y.................................... 
Hudson River, N.Y. City to Waterford, N.Y................ 
Hudson River Channel, N.Y............................ 
Jamaica Bay, N.Y............................. .. 
Jones Inlet, N .Y ....... .............................. 
Lake Montauk Harbor, N.Y ...... ...................... 
Long Island Intracoastal Waterway, N.Y.................. 
Mattituck Harbor, N.Y ....... ......................... 
Milton Harbor, N.Y ....... ........................... 
Narrows of Lake Champlain, N.Y. and Vt................. 
Newtown Creek, N.Y............. .............. 
New York & New Jersey Channels ...................... 
New York Harbor, N.Y ....... ......................... 
Port Chester Harbor, N.Y ...... ....................... 
Port Jefferson Harbor, N.Y ...... ...................... 
Rondout Harbor, N.Y................. ................ 
Saugerties Harbor, N.Y ................ ............... 
Mar., Apr. 1983 
Oct. 1982 
Apr. 1983 
Mar. 1983 
* 
Jul. 1983 
*
*
Jan., Apr. 1983 
Mar. 83 
*
Aug. 1983 
Dec. 1983 
Sep. 1983 
Aug. 1983 
Jul., Aug. 1983 
*
*
Oct. 1982; May, Jun. July 83 
Oct. 1982; Jan, Feb. Mar. 83 
Sep. 1983 
Jun. 1983 
*
* 
*Items for which no date is furnished reflect costs for gathering data only. 
Tbtal cost of Reconnaissance and Condition Surveys in FY1983 was $807,435. 
2-30

NEW YORK, N.Y. DISTRICT 
TABLE 2-G OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to Sept. 80, 1988 
Full Report 
See Annual Operation and 
Projects Report For Construction Maintenance 
Burlington Harbor, Vt.' 
Buttermilk Channel, N.Y. 
Channel between North and South Hero Island, 
Lake Champlain, Vt.'"2 
Coney Island Inlet, N.Y. 
East Chester Creek, N.Y. 
East River, N.Y. 
Echo Bay Harbor, N.Y.' 
Glen Cove Creek, N.Y. 
Gordons Landing, Lake Champlain, Vt.',2 
Gowanus Creek Channel, N.Y. 
Great Chazy River, N.Y. 
Great Kills Harbor, N.Y.' .2 
Great Lakes to Hudson River Waterway, N.Y. 
Great South Bay, N.Y.' 
Greenport Harbor, N.Y.' 
Harlem River, N.Y.' 
Hempstead Harbor, N.Y. 
Hudson River Channel, N.Y. 
Jamaica Bay, N.Y. 
Keyport Harbor, N.J.' 
Lake Montauk Harbor, N.Y 
Larchmont Harbor, N.Y. 
Lemon Creek, N.Y. (Inactive "3 
Little Neck Bay, N.Y.' 
Mamaroneck Harbor, N.Y. 
Manhasset Bay, N.Y. (Inactivey 
Matawan Creek, N.J. (Active)"6 
Mattituck Harbor, N.Y. 
Milton Harbor, N.Y. 
New Rochelle Harbor, N.Y.'.2 
Newton Creek, N.Y. (Active)'.5 
Northport Harbor, N.Y.' 
Orowoc Creek, N.Y. (Inactive)' 
Otter Creek, Vt. 
Peconic River, N.Y.' 
Peekskill Harbor, N.Y.' 
Plattsburgh Harbor, N.Y.' 
Port Henry Harbor, N.Y.' 
Port Jefferson Harbor, N.Y. 
Raritan River to Arthur Kill Cutoff Channel, N.J.' 
Rondout Harbor, N.Y.' 
Rouses Point, Lake Champlain, N.Y.' 
Sag Harbor, N.Y.' 
St. Albans Harbor, Lake Champlain, Vt."2 
Sandy Hook Bay, N.J.' 
Sandy Hook Bay at Leonardo, N.J." 2 
Saugerties Harbor, N.Y."2 
Sheephead Bay, N.Y.' 
Shinnecock Inlet, N.Y. 
Shrewsbury River, N.J. 
Staten Island Rapid Transit Railway Co. 
bridge across Arthur Kill, N.Y. 
Sumpawanus (Babylon Creek) Inlet, N.Y. "2 
Tarrytown Harbor, N.Y.' 
Wallabout Channel, N.Y.' 
Wappinger Creek, N.Y. " 
Washington Canal and South River, N.J.' 
Waycake Creek, N.J.2'3 
Woodbridge Creek, N.J.' 
1966 
1982 
1909 
1973 
1975 
1981 
1953 
1981 
1892 
1972 
1980 
1962 
1976 
1974 
1953 
1969 
1969 
1980 
1981 
1968 
1976 
1970 
1937 
1969 
1981 
1948 
1968 
1981 
1976 
1971 
1974 
1956 
1949 
1977 
1953 
1951 
1972 
1931 
1977 
1972 
1972 
1895 
1964 
1917 
1957 
1967 
1968 
1948 
1961 
1979 
1973 
1895 
1974 
1953 
1950 
1953 
1949 
1953 
706,414' 
31,000 
111,371 
592,056",3 
32,723,662 
64,584 
29,760T 
34,750 
346,831 
18,000 
137,301's 
5,644'" 
266,857 
74,681 
3,616,119 
39,468 
6,771,87037 
4,545,753 
40,475 
791,680 7 
76,065 
6,621"1 
1,741,21020 
513,764 
21,000 
177,925'" 
151,3732 
73,2148 
1,168,354 
78,644" 
60,254 
25,000 
19,400 
198,415 
69,4062 
221,1288' 
810,500 
142,437 
98,468 
121,8052 
3,125 
508,9362 
56,470 
81,905 
33,828 
1,145,458' 
,2 
7,730,476 
7,000 
69,836 
18,174 
13,000 
206,116' 
49,823 
283,556 
4,239,773 
1,288 
284,109 
755,042' 
3,012,769"'0 
11,571" 
126,820 
115 
255,291 
292,919 
88,029 
457 
1,290,469 
21,720 
480,777 
76,497'" 
24,970,637 
2,604,547" 
215,951 
1,236,709 
267,768 
1,621 
537 
551,677 
4,636 
165,341 
935,786 
525,520 
142,411 
1,626,351" 
1,487 
4,951 
27,059 
116,509 
66,037 
229,111 
1,299 
359,294 
2,019,141 
260,441 
249 
11,710 
385 
154,565 
93,964 
169,181" 
5,364 
22 
1,732,88010 
13 
431,199 
36,312 
44,691 
212,8273 
2,781 
178,398 
2-31

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 2-G (Continued) OTHER AUTHORIZED NAVIGATION PROJECTS 
1. Completed. 
2. No commerce reported. 
3. Awaiting local cooperation. 
4. Costs for previous projects only. 
5. A portion of this project is classified "inactive." 
6. Includes $69,036 for new work and $26,921 for maintenance for previous 
project. Excludes $10,000 for new work expended from contributed 
funds. 
7. Excludes $419,879 for new work expended from contributed funds 
and $58,425 contributed funds other and $8,752 expended by the Worlds 
Fair Corp. for riprap protection of rubble dike. 
8. Includes $43,175 for new work for previous projects. 
9. Includes costs of maintenance prior to July 1, 1986. Excludes 
$1,425,133 for rehabilitation. 
10. Includes $286,606 for maintenance for previous projects. 
11. Includes $10 for maintenance for previous projects. 
12. Excluded $29,774 for new work expended from contributed funds. 
13. Includes $4,813,400 for new work expended from emergency relief 
funds. 
14. Excludes $94,366 for rehabilitation. 
15. Excludes $104,805 for new work expended from contributed funds. 
16. Includes $64,034 for maintenance for previous projects. 
17. Excludes $104,805 for new work expended from contributed funds. 
18. Excludes $19,546 for new work expended from contributed funds 
and $31,454 to be contributed. 
19. This amount also included in costs for New York and New Jersey 
channels. No work has been done on the existing project for Lemon Creek. 
20. Excludes $1,741,210 for new work expended from contributed 
funds. 
21. Includes $220,894 for new work for previous projects. 
22. Excludes $36,311 for new work expended from contributed funds. 
23. Excludes $119,276 for new work expended from contributed funds. 
In addition, excludes $72,619 for new work expended from contributed 
funds, other. 
24. Includes $1,490,713 for maintenance for previous projects. 
25. Excludes $15,000 for new work expended from contributed funds. 
26. Includes $16,369 for maintenance for previous projects. 
27. Excludes $10,000 for new work expended from contributed funds. 
28. Excludes $66,758 for rehabilitation. 
29. Excludes $53,790 for new work expended from contributed funds. 
30. Includes $15,000 for maintenance for previous projects. 
31. Excludes $365 for new work expended from contributed funds. 
32. Includes $84,934 for maintenance for previous projects. 
33. Uncompleted portion deauthorized on August 5, 1977. 
34. Includes costs for new work $171,427 and maintenance $20,646 for 
previous projects. 
35. Deferred. 
36. Excludes $71,423 for rehabilitation. 
37. Includes $346,797 for maintenance for previous project. 
38. Includes $2,961 for maintenance for previous project. 
39. Includes $6,187,694 for new work for previous project. 
40. Includes $37,664 for maintenance for previous project. 
41. Excludes $34,580 for new work expended from contributed funds. 
TABLE 2-H OTHER AUTHORIZED BEACH EROSION 
CONTROL PROJECTS 
For Last Cost to Sept. 30, 1983 
Full Report 
See Annual Operation and 
Projects Report For Construction Maintenance 
Atlantic Coast of N.J., Sandy Hook to Barnegat Inlets' 1959 - - 
Fire Island Inlet to Jones Inlets, N.Y 1981 18,044,667 217,899 
North Shore of Long Island, Suffolk County, N.Y. 1979 8,880,000' 
Perth Amoby, N.J. 1966 - - 
1. Deferred. 
2-32

NEW YORK, N.Y. DISTRICT 
TABLE 2-I OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to Sept. 30, 1983 
Full Report 
Projects See Annual Operation and Report For Construction Maintenance 
Adams, Hoosic River Basin, Mass.' 1964 6,282,3072 - 
Bennington, Vt. 1974 670,000- 
Byram River at Pemberwick, Conn. '" 1959 363,515- 
East Barre Dam, Winooski River, Vt.' 1963 2,832,084- 
East Rockaway Inlet to Rockaway Inlet 
and Jamainca Bay, N.Y. (Part II) 1976 1,185,365- 
Herkimer, N.Y. 1973 1,301,275"- 
Hoosic Falls, Hoosic River Basin, N.Y.' 1956 1,064,626- 
Lamoille River, Vt.: Hardwick Dams4,'
," 1939 -- 
Mississquoi River at Richford, Vt.'' 1965 221,476- 
North Adams, Hoosic River Basin, Mass. 1968 15,409,325- 
North Ellenville, N.Y. 1978 3,900,650- 
Rahway, N.J. 1971 973,142"- 
Rahway, South Branch, N.J. 1979 15,863,723- 
Raritan Bay and Sandy Hook Bay, N.J. 1981 11,061,256 262 
Rosendale, N.Y 1975 3,684,966- 
Rutland, Otter Creek, Vt.4 1963 211,015- 
Sandburg Creek, Spring Glen, N.Y. 1976 109,702- 
South Amsterdam, Mohawk River, N.Y.' 1967 1,564,976- 
South Orange, N.J. 1981 6,857,484 
Wappinger Creek at Pleasant Valley, N.Y.' 1959 142,075- 
Waterbury Reservoir, Winooski River Basin, Vt. 1976 883,769 8,200 
Winooski River, Vt.' 1940 5,897,427- 
Wrightsville Dam, Winooski River Basin, Vt. 1970 1,549,929- 
1. Completed. 
2. Excludes costs of $913,360 under other contributed funds. 
3. Authorized by Chief of Engineers pursuant to Sec. 205, Public Law 
858, 80th Cong., as amended. 
4. Inactive 
5. Includes $23,507 emergency relief funds. 
6. Excludes cost of $2,718,624 under other contributed funds. 
7. Excludes cost of $21,000 under other contributed funds. 
8. Excludes cost of $51,500 under other contributed funds. 
9. Uncompleted portion has been deauthorized on August 5, 1977. 
10. Entire project deauthorized August 5, 1977. 
2-33

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 2-4 SURVEYS 
(See Section 40 of Text) 
Study Class Cost 
Navigation Studies 
Flood Control Studies 
Beach Erosion Studies 
Special Studies' 
'btal Surveys 
$ 2,186,937 
116,793
0 
1,290,261 
$ 3,593,991 
'Includes review of Authorized Projects, Inspection of Dams, Coordination Studies with Other Agencies, Planning Assistance to States, International 
Water Studies Special Investigations, Review of FERC Licenses, Continuation of Planning and Engineers, Advance Engineering and Design and $3,842 by. 
North Atlantic Division. 
TABLE 2-K FLOOD PLAIN STUDIES COMPLETED 
DURING THE PERIOD 
(See Section 41 of 'ext) 
Location Requesting Agency Date Completed Federal Cost 
NONE-PROGRAM TERMINATED 
TABLE 2-L COSTS FOR FLOOD PLAIN MANAGEMENT SERVICES 
(See Section 41 of ext) 
Studies and Services Cost 
Flood Plain 'bchnical Services $ 25,407 
Flood Plain Management Unit 76,110 
Flood Plain Management Unit-North Atlantic Division Office 61,299 
'Ibtal $162,816 
2-34

NEW YORK, N.Y. DISTRICT 
TABLE 2-M DEAUTHORIZED PROJECTS 
(See Section 42 of Text) 
For Last 
Full Report Date Federal Contributed Operation 
See Annual and Funds Funds and 
Projects Report For Authority Expended Construction Expended Maintenance 
Bronx River, N.Y.46 1981 Aug. 1982 1,149,946 1,159,94612 10,000 1,947,8536 
Brown's Creek, N.Y. 1980 Aug. 1977 33,976 33,976 505,369 
Cheesequake Creek, N.J. 4' 1953 Aug. 1982 40,000 40,000 - 30,675 
Coney Island Creek, N.Y " 1952 Aug. 1982 69,489 69,489 - 1,622 
East Rockaway (DEBS) Inlet, N.Y. 1963 Aug. 1977 503,969 603,969'" 100,000 829,421 
Elizabeth River, N.J. 1948 Aug. 1977 60,481 60,481 - 59,391 
Glen Cove Harbor, N.Y. 1966 Aug. 1977 165,882 165,8824," - 2,455 
Hudson River, NYC to Albany4", 1982 Aug. 1982- - - - 
Huntington Harbor, N.Y. 1953 Aug. 1977 49,035 68,5814,,4 19,546 51,566 
Irvington Harbor, N.Y. 1947 Aug. 1977. - - - 
Lamoille River, Vt. 1939 Aug. 1977 49,837 49,837 - 
Newark Bay, Hackensack 
and Passaic Rivers, N.J.7"6 1982 Aug. 1982- - - - 
New York and New Jersey4"7 1982 Aug. 1982- - - - 
Portchester Harbor, N.Y.2 ' 1967 Aug. 1977 433,470 433,4704 - 441,656 
Proctor, Otter Creek, Basin, Vt.".7 1937 Aug. 1977- - - - 
Rahway River, N.J. 7'" 1948 Aug. 1982 - 37,000* - 307' 
Raritan River, N.J.4" 1981 Aug.1982 1,551,470 1,617,470" 66,000 10,113,903 
Rome, Mohawk River, N.Y."'7 1959 Aug. 1982 7,000 7,000 - - 
Swanton Harbor, Vt. (Inactive) " 1888 Aug. 1977 - 70,500k - 235 
Ticonderoga River, N.Y '" 1895 Nov. 1983 17,760 16,500 - 1,260 
Waterbury (1941 Act), Vt.7'" 1951 Nov. 1981 9,253 9,253 - - 
Waterford, N.Y6"' 1939 Aug. 1982- - - - 
Westchester Creek, N.Y. 1981 Aug. 1982 175,933 175,933 - 2,921,311 
1. No commerce reported. 9. Deferred. 
2. Completed. 10. Under Section 12 Public Law 93-251. 
3. A portion of this project is classified "inactive." 11. Includes $93,882 for Rehabilitation. 
4. Uncompleted portion deauthorized. 12. Includes $10,000 expended from contributed funds. 
5. Excludes $19,546 for new work expended from contributed funds and 13. Includes $100,000 expended from contributed funds. 
$31,454 to be contributed. 14. Includes $19,546 expended from contributed funds. 
6. Inactive. 15. Includes $66,000 expended from contributed funds. 
7. Entire project deauthorized. 16. 1912 authorization. 
8. Excludes $71,423 for rehabilitation. 17. 1935 authorization. 
18. 1910 construction dikes. 
TABLE 2-N SECTION 107 CONTINUE DETAILED PROJECT REPORT 
(See Section 21 of Text) 
Name of Project Cost to Sept. 80, 1988 
Sheepshead Bay, N.Y $47,336 
TABLE 2-0 SECTION 103 START AND COMPLETE PREAUTHORIZATION 
EXPANDED RECONNAISSANCE REPORT 
(See Section 24 of 'T1xt) 
Name of Project Cost to Sept. 80, 1983 
Long Island Sound, Orchard Beach, N.Y.C., N.Y. $16,000 
START DETAILED PROJECT STUDY 
Long Island Sound, Orchard Beach, N.Y.C., N.Y. $11,400 
START AND COMPLETE PLANS AND SPECIFICATIONS 
Neptune City, Memorial Park Beach, N.J. $2,815 
2-35

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1988 
TABLE 2-P SECTION 205 COMPLETE PREAUTHORIZATION 
RECONNAISSANCE REPORTS 
(See Section 37 of Text) 
Name of Project Cost to Sept. 80, 1988 
Halsite Area, Huntington, N.Y. $ 100 
Schoharie Creek, Middleburgh, N.Y. 7,500 
START AND COMPLETE PREAUTHORIZATION RECONNAISSANCE REPORT 
Kayaderroseras Creek, Baliston, Spa, N.Y. $ 22,138 
CONTINUE DETAILED PROJECT REPORTS 
Missisquoi River, Vt. $ 68,514 
Sauquoit Creek, Whitesboro, N.Y. 158,961 
Yonkers, Nepera Park, N.Y. 85,709 
COMPLETE DETAILED PROJECT REPORTS 
Nannyhagen Brook, N.Y. $ 2,278 
Patroon Creek, Albany, N.Y. 176 
Schoharie Creek, Fulton, N.Y. 2,266 
COMPLETE PLANS AND SPECIFICATIONS 
Pine Brook, Manalapan, N.J. $ 1,721 
COMPLETE CONSTRUCTION 
Chappaqua, N.Y. (Sawmill River) $267,770 
START AND COMPLETE PREAUTHORIZATION 
EXPANDED RECONNAISANCE REPORTS 
East Canada Creek, Dolgeville, N.Y. $ 9,215 
Elizabeth River, Hillside, N.J. 18,000 
Esopus Creek, Ulster, N.Y. 12,500 
Fulmer Creek, Mohawk, N.Y. 12,950 
Ramapo River, Monroe, N.Y. 8,200 
Sheldon Brook, lTarrytown, N.Y. 13,000 
START DETAILED PROJECT STUDY 
Elizabeth River, Hillside, N.J. 3,302 
Esopus Creek, Ulster, N.Y. 3,600 
Sheldon Brook, lrrytown, N.Y. 2,964 
2-36

TABLE 2-Q 
NEW YORK, N.Y. DISTRICT 
SECTION 14 COMPLETE RECONNAISSANCE REPORTS 
(See Section 38 of 'lText) 
Name of Project Cost to Sept. 30,1983 
Colchester, Vt. $7,500 
Esopus Creek, Shandaken, N.Y. 7,126 
Hudson River, Staatsburg, N.Y. 7,500 
Hudson River, Troy, N.Y. 542 
Kaaterskill Creek, Palenville, N.Y. 356 
Station Road, Irvington, N.Y. 711 
COMPLETE PLANS AND SPECIFICATIONS 
Esopus Creek, Shandaken, N.Y. $30,300 
Sandburg Creek, Ellenville, N.Y. 28,857 
2-37

PHILADELPHIA, PA. DISTRICT. 
This district comprises a portion of southeastern New 
York, eastern Pennsylvania, western and southern New 
Jersey, northern and southeastern Delaware, and a 
small part of northeastern Maryland embraced in the 
drainage basins tributary to the Atlantic Ocean from 
Manasquan River, N.J., inclusive, to south boundary of 
Delaware. It also includes Chesapeake and Delaware 
Canal and approach channel thereto in Chesapeake Bay 
and Elk River, Md. 
IMPROVEMENTS 
Navigation 
Page 
1. Absecon Inlet, N.J .................... 3-2 
2. Barnegat Inlet, N.J.................... 3-2 
3. Cohansey River, N.J .................. 3-3 
4. Cold Spring Inlet, N.J..............3-3 
5. Delaware River between 
Philadelphia, Pa., and Trenton, N.J...... 3-3 
6. Delaware River, Pa., N.J. and Del. 
Philadelphia to the Sea ................ 3-4 
7. Indian River Inlet and Bay, Del.......... 3-5 
8. Inland Waterway, Rehoboth Bay to 
Delaware Bay, Del .................... 3-5 
9. Inland Waterway from Delaware River 
to Chesapeake Bay, Del., and Md ...... 3-6 
10. Manasquan River, N.J................. 3-7 
11. Murderkill River, Del ................. 3-8 
12. Navigation Work Under Special 
Authorization ........................ 3-8 
13. New Jersey Intracoastal Waterway ....... 3-8 
14. Salem River, N.J ..................... 3-9 
15. Schuylkill River, Pa ................... 3-10 
16. Wilmington Harbor, Del............... 3-10 
Beach Erosion Control 
Page 
17. Shoreline Erosion Control 
Demonstration ....................... 3-11 
18. Beach Erosion Control Work 
Under Special Authorization ........... 3-11 
Flood Control Local Protection 
Page 
19. Beltzville Lake, Pa .................... 3-11 
20. Blue Marsh Lake, Pa.................. 3-12 
21. Cape May Inlet to Lower 
Township, N.J........................ 3-12 
22. Delaware Coast Protection, Del.......... 3-13 
Flood Control Local Protection cont. 
Page 
23. Flood Control Work Under 
Special Authorization ................. 3-13 
24. Francis E. Walter Dam, Pa. ............ 3-13 
25. General Edgar Jadwin Dam and 
Reservoir, Pa......................... 3-14 
26. Hay Creek, Birdsboro, 
Schuylkill River Basin, Pa. ............. 3-14 
27. Inspection of Completed Flood 
Control Projects...................... 3-14 
28. Inspection of Non-Federal Levees ........ 3-15 
29. Pottstown and Vicinity, Schuylkill 
River Basin .......................... 3-15 
30. Prompton Lake, Pa ................... 3-15 
31. Tamaqua, Pa......................... 3-16 
32. Reconnaissance and Conditions 
Surveys ............................. 3-16 
General Investigations 
Page 
33. Surveys ............................. 3-16 
34. Collection and Study of Basic Data ...... 3-16 
35. Advance Engineering and Design ........ 3-16 
Tables 
Page 
TABLE 3-A Cost and Financial Statement ... 3-17 
TABLE 3-B Authorizing Legislation ........ 3-21 
TABLE 3-C Other Authorized 
Navigation Projects ........... 3-24 
TABLE 3-D Other Authorized Beach 
Erosion Control Projects ....... 3-26 
TABLE 3-E Other Authorized Flood 
Control Projects.............. 3-26 
TABLE 3-F Multiple Purpose Project 
Including Power.............. 3-27 
TABLE 3-G Deauthorized Projects.......... 3-27 
3-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Navigation 
1. ABSECON INLET, N.J. 
Location. On New Jersey coast about 65 miles 
north of Delaware breakwater, between Brigantine 
Beach on the north and Absecon Beach on the south. It 
forms entrance to harbor at Atlantic City, N.J. (See U.S. 
Coast and Geodetic Survey Charts 826 and 1217). 
Previous project. For details see Annual Report for 
1936, page 319. 
Existing project. This provides for an inlet entrance 
channel 20 feet deep at mean low water and 400 feet 
wide, for an entrance channel 15 feet deep and 200 feet 
wide from the inlet channel into Clam Creek, and for a 
turning basin 15 feet deep within Clam Creek. The act 
authorizing the inlet entrance channel also provides that 
should the channel at any time have deleterious effect on 
the Atlantic City Beach, work upon the improvements 
may cease; it being understood that the project is 
adopted on the basis that the interests of the beach in 
front of the city are superior to those of the inlet. The 
total length of the section included in the project is about 
1.5 miles. The extreme tidal range, due to ocean storms, 
is about 11 feet. 
Project was completed May 1957. Inlet channel was 
completed in 1938. Dredging entrance from inlet 
channel into Clam Creek was completed in 1957. 
The cost for the completed project was $307,712. (See 
Table 3-B at end of chapter for Acts authorizing existing 
project.) 
Local cooperation. Fully complied with except that 
local interests are required to furnish suitable spoildisposal 
areas for maintenance when and as required for 
the dredging of the entrance channel into Clam Creek 
and the turning basin within Clam Creek. 
Terminal facilities. See pages 239 and 240 of 
Annual Report for 1962. 
Operations during fiscal year. Maintenance, hired 
labor: Engineering survey and benefit cost review 
performed. 
2. BARNEGAT INLET, N.J. 
Location. On the east coast of New Jersey about 50 
miles south of Sandy Hook, between Island Beach on 
the north and Long Beach on the south (See U.S. Coast 
and Geodetic Chart Nos. 825 and 1216). This inlet is 
main entrance to Barnegat Bay, largest of the bays on 
New Jersey coast which are separated from the ocean by 
narrow barrier beaches. 
Existing project. Provides for a channel 8 feet deep 
through inlet and 10 feet through outer bar, channel to 
be protected by two converging stone jetties extending 
to 12-foot contour in the ocean and spaced 1,000 feet 
apart at outer ends; a channel of suitable hydraulic 
characteristics extending in a northwesterly direction 
from gorge in inlet to Oyster Creek Channel just northwest 
of Sunset Shoal, thence via Oyster Creek Channel 
to deep water in the bay; and maintenance of a channel 8 
feet deep and 200 feet wide to connect Barnegat City 
harbor with main inlet channel. Total length of section 
included in project is about 4.5 miles. Plane of reference 
is mean low water. Extreme tidal range at inlet is from 
about 2 feet below mean low water to about 3 feet above 
mean high water. Project was completed in 1940. (For 
details, see page 203, Annual Report for 1964). (See 
Table 3-B at end of chapter for Acts authorizing existing 
projects.) 
Recommended modifications. The existing Federal 
project at the inlet, which was completed in 1940, has 
failed to maintain a suitable and safe channel for 
navigation. As a result of the findings of AE&D studies 
on this matter, the Chief of Engineers decided on 20 
January 1983 that modification to the project should be 
implemented to correct a design deficiency. The 
recommended modification would serve to correct the 
design deficiency through the construction of a new 
south jetty aligned more nearly parallel to the existing 
north jetty, the dredging and maintenance of a new realigned 
navigation channel, and the removal of a shoal 
located between the proposed navigation channel and 
the north jetty. 
Local cooperation. Fully complied with. 
Terminal facilities. 
terminals in inner harbor 
furnish adequate facilities 
locality. 
There are four docks or 
at Barnegat Light which 
for present commerce of 
Operations during fiscal year. Maintenance, contract: 
Dredging of Oyster Creek was performed by 
Barnegat Bay Dredging Company during the period of 
20 April to 27 April 1983. Removed a total of 18,200 
cubic yards of material. 
Maintenance, hired labor: Maintenance dredging at 
Barnegat Inlet was performed by U.S. Hopper Dredge 
FRY during the period of 14 April to 25 June, and 21 
August to 30 September 1983. Removed an estimated 
436,700 cubic yards of material. Other work included 
subsurface exploration, design deficiency memorandum, 
general maintenance, engineering surveys, and 
supervision and administration. 
3-2

PHILADELPHIA, PA. DISTRICT* 
3. COHANSEY RIVER, N.J. 
Location. Rises in Salem County, N.J., flows 
southerly and southwesterly 27 miles through 
Cumberland County, and empties into Delaware Bay 
about 62 miles below Philadelphia, Pa. (See Coast and 
Geodetic Survey Chart 1218.) 
Previous projects. For details see page 1785, 
Annual Report for 1915, and page 348, Annual Report 
for 1938. 
Existing project. A channel 12 feet deep, 100 feet 
wide from that depth in Delaware Bay through a neck of 
land at the mouth and within the river to the south side 
of Glass Street in Bridgeton, 19 miles above the mouth; 
thence a channel 8 feet deep, 100 feet wide to Broad 
Street; and thence 75 feet wide to Commerce Street 
Bridge, 19.25 miles above the mouth; and a turning 
basin 12 feet deep and 800 feet long formed by widening 
the channel on the south side to a maximum width of 250 
feet just below Glass Street. Section included in project 
is about 19.5 miles long. All depths refer to the plane of 
mean low water. Extreme tidal range is from about 2 feet 
below mean low water to about 3 feet above mean high 
water. Completed project cost $110,756 for new work, 
exclusive of amounts expended on previous projects. 
(See Table 3-B at end of chapter for Acts authorizing 
existing project.) Existing project was completed in 
1939. 
Local cooperation. Complied with except local 
interests must furnish suitable spoil-disposal areas for 
required maintenance. 
Terminal facilities. Twenty wharves, of which 16 
are at Bridgeton and 4 at Greenwich. Facilities 
considered adequate for existing commerce. 
Operations during fiscal year. Maintenance, contract: 
Environmental assessment prepared. 
Maintenance, hired labor: Environmental assessment 
prepared. 
4. COLD SPRING INLET, N.J. 
Location. In Cape May County, southern New 
Jersey, about 3 miles east of Cape May City and about 
16 miles northeast of Delaware breakwater. Inlet 
connects Cape May Harbor and New Jersey 
Intracoastal Waterway with the Atlantic Ocean and is 
about I mile long. (See Coast and Geodetic Survey 
Charts 234,827 and 1219). 
Existing project. This provides for an entrance 
channel 25 feet deep and 400 feet wide, protected by two 
parallel jetties, and extending from the 25-foot depth 
curve in the Atlantic Ocean to a line 500 feet harborward 
of a line joining the inner ends of the jetties; thence 20 
feet deep and 300 feet wide to deep water in Cape May 
Harbor. The total length of the section included in the 
project is about 2.25 miles. Extreme tidal range, due to 
ocean storms, is about 11 feet. Project was completed in 
1942. (For details see page 238, Annual Report for 
1962.) (See table at end of chapter for Acts authorizing 
existing project.) 
Local cooperation. Complied with Act of 1907, 
except work of deepening and enlarging inner harbor, 
which is 80 percent complete. 
Terminal facilities. See page 238, Annual Report 
for 1962. 
Operations during fiscal year. Maintenance, 
contract: Contract dredging of Cape May Harbor by 
plant rental was performed during the period of 23 May 
to 9 August 1983. Removed a total of 194,400 cubic 
yards of material. 
Maintenance, hired labor: Only work performed was 
dredging plans and specifications and supervision and 
administration. 
5. DELAWARE RIVER BETWEEN 
PHILADELPHIA, PA., AND TRENTON, N.J. 
Location. Rises in southeastern New York, flows 
generally southerly 367 miles, forming boundry line 
between New York and New Jersey on the east and 
Pennsylvania and Delaware on the west, and empties 
into Delaware Bay. (See U.S. Coast and Geodetic 
Survey Charts 1218, 280, 294, 295, and 296.) 
Previous projects. For details see page 1778 of 
Annual Report for 1915, page 311 of Annual Report for 
1924, page 220 of Annual Report for 1934, and page 296, 
Annual Report for 1938. 
Existing project. A channel from Allegheny 
Avenue, Philadelphia, 23.:5 miles to upstream end of 
Newbold Island 40 feet deep and 400 feet wide, with 
suitable widening of bends, including relocation of 
channel at Delair Railroad bridge, and reconstruction of 
bridge, thence 5.5 miles to upper end of Trenton Marine 
Terminal, 35 feet deep and 300 feet wide, with a turning 
basin 800 feet wide and 1,700 feet long at the terminal; 
and maintenance of a channel 12 feet deep and 300 feet 
wide from upper end of 34-foot channel to Penn Central 
Railroad Bridge at Trenton, dredged under a previous 
project. Project also provides for an auxiliary channel 20 
feet deep and 200 feet wide east of Burlington Island, 
extending easterly from main channel to upper end of 
3-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
U.S. Pipe and Foundry Co.'s property at East Burlingtop, 
with a turning basin 450 feet wide at upper end; for 
initial excavation, only, of a cross channel 8 feet deep 
and 200 feet wide through artificial island opposite 
Delanco, N.J., and for construction such bank protection 
works as may be necessary. Section included in 
project is about 30.5 miles long, excluding auxiliary 
channel east of Burlington Island, which is 1.4 miles 
long, and cross channel opposite Delanco. Lower end is 
about 55 miles above river mouth at Liston Point and 
about 105 miles above Harbor of Refuge at mouth of 
Delaware Bay. Freshets, which occur, usually during 
February and March, attain a height of 9 to 20 feet 
above mean low water in vicinity of Trenton. Navigation 
is occasionally suspended during a portion of winter 
months due to ice. Existing project is 90 percent 
complete. A 40-foot channel under the 1954 
modification from Allegheny Avenue to upper end of 
Newbold Island was completed April 1964. Work 
remaining is dredging from upper end of Newbold 
Island to Trenton Marine Terminal and widening 
turning basin at terminal which is in deferred category. 
(See Table 3-B at end of chapter for Acts authorizing 
existing project.) (See Table 3-C at end of chapter for 
total cost for existing project to Sept. 30, 1983.) 
Local cooperation. Modification authorized by 
1954 River and Harbor Act provides local interests must 
provide suitable terminal facilities, furnish lands and 
rights-of-way for construction and future maintenance, 
and hold the United States free from damages. Local 
interests complied with requirements, except city of 
Trenton has not provided suitable terminal facilities. 
Terminal facilities. There are 21 piers, wharves, and 
docks from Allegheny Avenue, Philadelphia, Pa., to 
Trenton, N.J. Facilities are considered adequate for 
existing commerce. (For details see Port Series No. 8 
(revised 1966) Corps of Engineers.) 
Operations during fiscal year. Maintenance, 
contract: Maintenance dredging of shoals in Duck 
Island and Perriwig Range was performed by American 
Dredging Company during the period of 15 September 
to 11 October 1983. Removed a total of 450,000 cubic 
yards of material. Other work included plans and 
specifications, and stream gaging by USGS. 
Maintenance, hired labor: Work included general 
maintenance, engineering surveys, plans and 
specifications and supervision and administration. 
6. DELAWARE RIVER, PA., N.J., AND DEL., 
PHILADELPHIA TO THE SEA 
Location. See U.S. Coast and Geodetic Survey 
Charts 1218, 394, 295, and 280. 
Previous projects. For details see page 1779 of 
Annual Report for 1915, and page 299, Annual Report 
for 1938. 
Existing project. Provides for a channel from deep 
water in Delaware Bay to a point in the bay, near Ship 
John Light, 40 feet deep and 1,000 feet wide; thence to 
Philadelphia Naval Base, 40 feet deep and 800 feet wide, 
with 1,200-foot width at Bulkhead Bar and 1,000-foot 
width at other bends; thence to Allegheny Avenue, 
Philadelphia, Pa., 40 feet deep and 500 feet wide through 
Horseshoe Bend and 40 feet deep and 400 feet wide 
through Philadelphia Harbor, along west side of 
channel; and for anchorages at Reedy Point, Deepwater 
Point, Marcus Hook, and Mantua Creek, each 40 feet 
deep and 2,300 feet wide with respective lengths of 8,000, 
5,200, 13,650, and 11,500 feet; anchorage at Gloucester 
30 feet deep and about 3,500 feet long. Project also 
provides for construction of dikes and training works 
for regulation and control of tidal flow; for maintenance 
of an area on north side of channel opposite 
Philadelphia Naval Base between Shipway 3 and 
Schuylkill River to 40 feet deep and a width of 150 feet 
on Mifflin Range and of 200 feet on West Horseshoe 
Range; and for maintenance of any areas dredged by 
local interests to 35 feet deep between channel and a line 
100 feet channelward of pierhead line between Point 
House wharf and Philadelphia Naval Base, when in 
opinion of Chief of Engineers such areas are so located 
as to be of benefit to generate navigation. Section 
included in project is about 96.5 miles long. All depths 
refer to plane of mean low water. Under influence of 
heavy and long-continued winds extreme tidal range is 
about 14 feet. Normal maximum velocity of'tidal 
currents in the dredged channel varies between 2 and 3.5 
miles per hour. Storm tides may increase maximum to as 
much as 4.5 miles per hour. Estimated cost for new work 
is $71,630,000 (July 1972) exclusive of amounts 
expended on previous projects. Channel to 37 deep and 
500 feet wide through Horseshoe Bend and 37 feet deep 
and 60 feet wide through Philadelphia Harbor along 
east side of channel and Port Richmond anchorage to 37 
feet deep, except for that portion of channel which forms 
a part of 40 feet deep and 400 feet wide channel portion 
of project is to be restudied and excluded from foregoing 
cost estimate. Estimated cost (July 1960) of this portion 
is $2,951,000. Existing project, excluding work deferred 
for restudy, is about 66 percent complete. The 40-foot 
channel from naval base to the sea was completed in 
1942. Dredging Naval Base to Allegheny Avenue to 40 
feet deep was completed in 1962. Enlarging anchorage at 
Marcus Hook was completed in 1967. Work remaining 
is to construct new anchorages at Reedy Point and 
Deepwater Point, and enlarge Mantua Creek 
anchorage, channel dredging from 35 to 37 feet deep 
over a width of 500 feet through Horseshoe Bend and 
about 600 feet through Philadelphia Harbor, and 
deepening Port Richmond Anchorage to 37 feet, all of 
3-4

PHILADELPHIA, PA. DISTRICT 
which have been deferred for restudy. (See Table 3-B at 
end of chapter for Acts authorizing existing project.) 
(See Table 3-C at end of chapter for total costs for existing 
project to Sept. 30, 1983.) 
Local cooperation. Requirements under 1938 River 
and Harbor Act for maintaining channel and anchorage 
in Philadelphia Harbor annually by cities of 
Philadelphia and Camden were removed (see 1962 
Annual Report for details). 
Terminal facilities. There are 217 piers, wharves, 
and docks between Allegheny Avenue, Philadelphia and 
the sea, 135 on waterfront of Philadelphia, Camden, and 
Gloucester, and 82 below Philadelphia. Facilities are 
considered adequate for existing commerce. (For 
further details see Port Series Nos. 7, revised 1967, and 
8, revised 1966 - Corps of Engineers). 
Operations during fiscal year. Maintenance, 
contract: Dredging performed by American Dredging 
Company at New Castle, Cherry Island, and Marcus 
Hook during the period of I October 1982 to 30 January 
1983. Removed a total of 2,050,000 cubic yards of 
material. Rock removal and dredging performed at 
Reedy Island, Chester Monds, and Baker Range during 
the period of 14 December 1982 to 27 March 1983. 
Removed an estimated 2,542,000 cubic yards of material 
from Deepwater Point, Bulkhead Bar, New Castle, 
Marcus Hook, and Liston and Cherry Island during the 
period of 9 May to 30 September 1983. Other work 
included subsurface exploration, ground resistance 
testing, handling shore pipe, raising banks, construction 
of steel sluice, sturgeon study, stream gaging, plans and 
specifications, water quality data collection, 
environmental monitoring, and channel exams. 
Maintenance, hired labor: Dredging performed by U.S. 
Hopper Dredge ESSAYONS at Deepwater Point, 
Bulkhead Bar, Brandywine Range, and Marcus Hook. 
Removed 187,938 cubic yards of material during the 
period of 20 March to 14 May 1983. Other work 
included engineering surveys, general maintenance, 
environmental monitoring, sturgeon study, water 
quality data collection, plans and specifications, maintenance 
of disposal areas, snagging and clearing, stream 
gaging, channel exams, handling shore pipe, raising 
banks, constructing steel sluice, and engineering and 
design, and supervision and administration. 
7. INDIAN RIVER INLET AND BAY, DEL. 
Location. Indian River rises in Sussex County, 
Del., and flows easterly 13 miles into Indian River Bay 
which is a shallow lagoon 6 miles long and 2 miles wide 
on the Delaware Coast about midway between Cape 
Henlopen and the Maryland State line. The inlet is an 
opening through the barrier beach separating Indian 
River Bay and the Atlantic Ocean. (See U.S. Coast and 
Geodetic Survey Chart No. 1219.) 
Previous projects. Adopted by River and Harbor 
Act of August 2, 1882. For further details see page 744, 
Annual Report for 1888. 
Existing project. This provides for the fixation of 
the inlet by the construction of two parallel jetties of 
steel-sheet pile and stone design extending to 
approximately the 14-foot depth curve in the ocean, and 
for dredging an entrance channel 15 feet deep and 200 
feet wide, for a distance of 7,000 feet inshore from the 
jetties; thence a channel 9 feet deep, 100 feet wide in the 
bay, and 80 feet wide in the river, to and including a 
turning basin 9 feet deep, 175 feet wide, and 300 feet long 
at Old Landing; thence a channel 4 feet deep and 60 feet 
wide to the highway bridge at Millsboro. The project 
also provides that the interior channel dimensions may, 
in the discretion of the Chief of Engineers, be modified 
as found desirable to increase the hydraulic efficiency of 
the channel, without increasing the cost. The total length 
of the section included in the project is about 13.75 
miles. All depths refer to the plane of mean low water. 
The extreme tidal range at the highway bridge is about 6 
feet. Existing project was completed in 1951. For details 
see Annual Report for 1963. 
The cost for new work for the completed project was 
$511,210, exclusive of $10,000 expended on previous 
projects and exclusive of $210,000 contributed funds. 
(See Table 3-B at end of chapter for Acts authorizing 
existing project.) 
Local Cooperation. Fully complied with except 
that local interests are required to furnish suitable areas 
for disposal of dredged material during maintenance as 
and when needed, and provide terminal facilities. 
Terminal facilities. There is a privately owned basin 
with berthing facilities for small boats located .75 mile 
west of the highway bridge near the inlet and .25 mile 
north of the inlet channel, connected therewith by a 
channel 6 feet deep and 40 feet wide; a U.S. Coast Guard 
wharf on the north side of the inlet channel in the same 
locality; and two wharves at Oak Orchard in Indian 
River Bay. The facilities are considered adequate for 
existing commerce. 
Operations during fiscal year. Maintenance, hired 
labor: Work included supervision and administration 
on marsh development and reconnaissance report. 
8. INLAND WATERWAY, REHOBOTH BAY TO 
DELAWARE BAY, DEL. 
Location. A tidal canal in southeasterly part of 
3-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Sussex County, Del. It extends 12 miles northward from 
Rehoboth Bay through high land west of town of 
Rehoboth to Gordon Lake; thence through marshes 
back of Cape Henlopen to Lewes River; thence down 
Lewes River to its junction with Broadkill River near its 
mouth. An entrance to the waterway from Delaware 
Bay is about 4 miles above Cape Henlopen. (See U.S. 
Coast and Geodetic Survey Charts 379, 1218, and 1219.) 
Previous projects. A canal along a slightly different 
route formed a part of projected waterway from 
Chincoteague Bay, Va. to Delaware Bay, begun in 1886 
and abandoned in 1905. 
Existing project. This provides for an entrance 
channel near Lewes 10 feet deep and 200 feet wide 
protected by two parallel jetties 500 feet apart; thence a 
channel 10 feet deep and 100 feet wide to South Street 
Bridge at Lewes, and a basin of the same depth 1,200 feet 
long and up to 375 feet in width at the latter point; thence 
a channel 6 feet deep and 50 feet wide (40 feet wide 
through Deep Cut near Rehoboth) to Rehoboth Bay; a 
channel 6 feet deep and 100 feet wide from the entrance 
to Broadkill River; two parallel rubble jetties 725 feet 
long at the Rehoboth Bay entrance; and the 
construction of one highway bridge and one railroad 
Bridge at Rehoboth. The total length of the section 
included in the project is about 12 miles. 
The cost for new work for the completed portion of 
the project was $561,514, exclusive of amounts 
expended on previous projects and $60,000 contributed 
funds. The extension of the jetties at the Delaware Bay 
entrance is considered to be inactive and is excluded 
from the foregoing cost. The cost of the portion was last 
revised in 1960 and was estimated to be $816,000. 
Existing project is about 70 percent complete. For 
details on completed work see page 241 of Annual 
Report for 1963. Work remaining, extension of existing 
jetties at Delaware Bay entrance, is considered inactive. 
(See Table 3-B at end of chapter for Acts authorizing 
existing project.) 
Local cooperation. Complied with except local 
interests must furnish suitable terminal facilities and 
necessary spoil-disposal areas. 
Terminal facilities. See page 228, Annual Report 
for 1962. 
Operations during fiscal year. Maintenance, 
contract: Maintenance dredging performed at 
Roosevelt Inlet by Gwin Dredging and Dock Inc. 
Removed 11,245 cubic yards of material. Dredging 
commenced 29 September and was still in progress at the 
end of fiscal year. 
Maintenance, hired labor: Real estate management 
service only cost incurred during fiscal year. 
9. INLAND WATERWAY FROM DELAWARE 
RIVER TO CHESAPEAKE BAY, DEL., AND 
MD. 
Location. Begins at Reedy Point on Delaware 
River, about 41 miles below Philadelphia, Pa., and 
passes through sea level Chesapeake and Delaware 
Canal, a distance of 14 miles, to Back Creek, at Chesapeake 
City, Md. It then passes for 5 miles down Back 
Creek, thence 9 miles down Elk River to Chesapeake 
Bay and thence 18 miles down Chesapeake Bay to a 
point near Pooles Island. A branch channel connects 
Delaware River at Delaware City, Del., with main 
channel at a point about 1.5 miles west of Reedy Point. 
(See U.S. Coast and Geodetic Survey Charts 294, 1226, 
570, and 572.) 
Previous projects. For details see Annual Report 
for 1934, page 242, and Annual Report for 1938, page 
312. 
Existing project. A channel 35 feet deep and 450 feet 
wide from Delaware River through Elk River and 
Chesapeake Bay to water of natural 35-foot depth in 
Chesapeake Bay including a cutoff at Penn Central 
Railroad crossing, and having a minimum radius of 
curvature of 7,000 feet at bends; a high-level, fixed railroad 
bridge with vertical clearance of 135 feet and horizontal 
clearance of 600 feet at the railroad crossing over 
the cutoff (economic study of railroad crossing 
requested by Office of Management and Budget resulted 
in construction of a single track vertical lift bridge in lieu 
of a high-level fixed railroad bridge); high-level fixed 
highway bridges over canal at Reedy Point, St. Georges, 
Summit, and Chesapeake City; a bascule drawbridge 
across Delaware City Branch Channel; extension of 
entrance jetties at Reedy Point; and anchorage in Elk 
River, 35 feet deep and 1,200 feet wide, with an average 
length of 3,700 feet; enlargement of anchorage and 
mooring basin in Back Creek to afford an area about 400 
feet wide, 1000 feet long, and 12 feet deep; dredging 
Delaware City Branch Channel to 8 feet deep and 50 feet 
wide, and deepening existing basin to same depth; revetment 
of banks of canal as required between Delaware 
and Elk Rivers, and on banks of Delaware City Branch 
Channel east of Fifth Street Bridge; and construction of 
bulkheads. Total of section included in project, excluding 
Delaware City Branch Channel, which is about 2 
miles long, is about 46 miles. All depths refer to plane of 
low water in Delaware River. Extreme tidal range is 
from 6.3 feet above mean high water to 3 feet below 
mean low water. Existing project is about 89 percent 
completed. Channel 27 feet deep and 250 to 400 feet 
wide. Delaware River to Pooles Island, completed in 
1938. High-level fixed highway bridges were completed 
3-6

PHILADELPHIA, PA. DISTRICT 
at St. Georges (4-lane) in 1942; at Chesapeake City (2- 
lane) in 1949; and at Summit (4-lane) in 1960. Relocation 
of Penn Central Railroad bridge was completed 
December 21, 1965. Enlargement to 35 feet deep and 450 
feet wide St. Georges and Summit bridges and Summit 
and Goose Island was completed on June 20, 1972 and 
February 18, 1972, respectively. Removing the old Penn 
Central railroad bridge was completed on January 21, 
1972. Channel work for Part II is about 87 percent complete. 
Work remaining consists of completing channel 
enlargement to 35 feet deep and 450 feet wide between 
Reedy Point Bridge and St. Georges Bridge; widening 
and deepening the channel between Delaware River and 
Reedy Point Bridge, the completion of recreation 
facilities, and miscellaneous completion items. Deepening 
Delaware City Branch Channel from 6 to 8 feet from 
a point 400 feet east of Fifth Street Bridge to its junction 
with the canal has been deferred for study. 
Original cost of canal including purchase was 
$10,709,755; estimated cost of new work for 
modifications of 1935 and 1954 is $139,574,000 (October 
1977). Total estimated cost of new work including 
original purchase is $151,683,755. Portion of project 
comprising completion of Delaware City Branch 
Channel from a point 400 feet east of Fifth Street Bridge 
to its junction with canal is to be restudied and excluded 
from foregoing estimate. Estimated cost of this portion 
is $145,000 (July 1954). (See Table 3-B at end of chapter 
for Acts authorizing existing project.) 
Local cooperation. River and Harbor Act of 1954 
provided that local interests furnish lands and rights-ofway 
required for bridges. Assurances accepted and 
approved February 16, 1955. Requirements for Summit 
and Reedy Point Bridges have been met. 
Terminal facilities. Ample mooring facilities at 
eastern and western ends of canal and bulkheads at 
Delaware City and St. Georges were constructed by the 
United States. A small-boat harbor was provided and a 
wharf constructed at Chesapeake City. Facilities are 
considered adequate for existing commerce. 
Operations during fiscal year. Maintenance, 
contract: Maintenance dredging performed by Great 
Lakes Dredge and Dock Company during the period of 
20 October 1982 to 8 January 1983. Removed a total of 
1,365,511 cubic yards of material. Other work included, 
maintenance of bridges, inspection of bridges, 
maintenance and repair of night lighting, maintenance 
of building and grounds, maintenance of banks and 
disposal areas, construction of disposal areas, debris 
removal, replacement of rip-rap, bridge repairs, 
environmental monitoring, channel exams, and 
operation and ordinary maintenance. 
Maintenance, hired labor: work included, maintenance 
of bridges, operation and ordinary maintenance, 
maintenance of night lighting, building and grounds, 
roadways, TV and electronic equipment, and rip-rap, 
debris removal, construction of disposal areas, channel 
exams, environmental monitoring, surveys, plans and 
specifications, general maintenance of roadways, and 
engineering and design and supervision and 
administration. 
10. MANASQUAN RIVER, N.J. 
Location. This small stream flows in eastern part of 
New Jersey, rises near Freehold, flows easterly and 
empties into the Atlantic Ocean, about 26 miles south of 
Sandy Hook. (See U.S. Coast and Geodetic Survey 
Chart No. 795.) 
Previous projects. For details see Annual Report 
for 1909, page 186, and Annual Report for 1938, page 
269. 
Existing project. A channel 14 feet deep and 250 feet 
wide, protected by jetties and other works, extending 
from the Atlantic Ocean to inner end of north jetty, 
thence 12 feet deep and 300 feet wide to within 700 feet of 
New York and Long Branch Railroad bridge, thence of 
same depth and narrowing to 100 feet wide to within 300 
feet of bridge; for a widening on northerly side of 
channel of 200 feet for 3,150 feet to a depth of 8 feet; for a 
19-acre anchorage to 10 feet deep on south side of channel 
and for a 27.5-acre anchorage to 12 feet deep about 
0.5 miles west of route 35 highway bridge. Section 
included in project is about 1.5 miles long. Mean tidal 
range is 3.7 feet at inner end of inlet and 4 feet at ocean 
end; mean range of spring tides, 4.4 and 4.8 feet, respectively, 
irregular fluctuations due to wind and barometric 
pressure vary from 2.7 feet below to 7.5 feet above mean 
low water at inner end of inlet. Project, excluding 10- 
and 12-foot anchorages, cost $518,243. Estimated cost 
(1958) for 10- and 12-foot anchorages portion of project 
considered inactive is $504,000. Existing project was 
completed in June 1963. Dredging 19 acre anchorage 
south of channel and 27.5 acre anchorage west of highway 
bridge is in the inactive category. (See Table 3-B at 
end of chapter for Acts authorizing existing project.) 
Local cooperation. River and Harbor Act of 1945 
provides that local interests must furnish lands and 
rights-of-way for construction and future maintenance 
and hold the United States free from damages. Assurances 
to date have been complied with. 
Terminal facilities. Five landings with a total 
wharfage of 700 feet used by commercial fishermen, and 
7 landings and boat basins for pleasure craft. Existing 
facilities are considered adequate for present requirements. 
3-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Operations during fiscal year. Rehabilitation, contract: 
Completed contract regarding rehabilitation of 
north jetty. 
Rehabilitation, hired labor: Engineering and design and 
supervision and administration related to rehabilitation 
of north jetty. 
Maintenance, contract: Work included repair of south 
bulkhead and repair of sinkholes. 
Maintenance, hired labor: Work included repair of sinkholes, 
and supervision and administration. 
11. MURDERKILL RIVER, DEL. 
Location. Rises in Kent County, Del., flows northeasterly 
19 miles through county, and empties into Delaware 
Bay about 25 miles above Cape Helopen. (See U.S. 
Coast and Geodetic Survey Chart No. 1218.) 
Existing project. Provides for a channel 7 feet deep 
at mean low water, 150 feet wide in Delaware Bay to 
mouth, and thence 80 feet wide to Frederica, 7.5 miles 
above mouth. Total length of section included in project 
is about 8.5 miles. Extreme tidal range is from about 1 
foot below mean low water to about 2 feet above mean 
high water. 
Estimated cost for new work revised in 1954 is 
$38,000. Portion comprising widening channel to 
project width throughout its length is to be restudied and 
excluded from foregoing cost estimate. Estimated cost 
of this portion last revised in 1954 was $86,000. 
Project was authorized by River and Harbor Act of 
July 13, 1892 (H. Ex. Doc. 21,52d Cong., 1st Sess.). (See 
page 981 Annual Report of 1892.) Latest published map 
is in House Document 1058, 62d Congress 3d Session. 
Existing project about 30 percent complete, including 
revision to be restudied. Channel 7 feet deep and 60 feet 
wide was completed in 1911. Work remaining is 
widening the channel to project width. 
Local cooperation. None required. 
Terminal facilities. There are a number of light 
timber wharves on both 'sides of river near mouth and 
two wharves at Frederica, all privately owned. Facilities 
are considered adequate for existing commerce. 
Operations during fiscal year. Maintenance, hired 
labor: Work included environmental monitoring, plans 
and specifications, and supervision and administration. 
12. NAVIGATION WORK UNDER SPECIAL 
AUTHORIZATION 
Navigation Activities Pursuant to Section 107, Public 
Law 86-645 (Preauthorization). 
Study Identification Fiscal Year Cost 
Dredge Harbor, Delran, N.J., (DPR) 
Little Assawoman Bay, Del (RECON) 
Municipal Marina, Pleasantville, N.J. (DPR) 
Petty Island, Back Channel, Camden, N.J. (DPR) 
Schuylkill River, PA. 
$ 718 
4,385 
13,321 
83,808 
7,500 
13. NEW JERSEY INTRACOASTAL WATERWAY 
Location. A sea level inland water route approximately 
parallel with New Jersey coast, extends from 
Atlantic Ocean at Manasquan Inlet, about 26 miles 
south of Sandy Hook, .N.J., to Delaware Bay about 3 
miles above Cape May point. Waterway extends 
through inlet and up Manasquan River about 2 miles; 
thence by Point Pleasant Canal through high ground for 
2 miles to head of Barnegat Bay. It then passes through a 
series of bays, lagoons, and thoroughfares along New 
Jersey coast to Cape May harbor; thence across Cape 
May County to Delaware Bay through a land cut by way 
of New England Creek basin. (See U.S. Coast and 
Geodetic Survey Charts 234, 795, 825, 826, 827, 1216, 
1217, 1218, and 1219.) 
Existing project. This provides for a channel 12 feet 
deep at mean low water and generally 100 feet wide, 
extending from the Atlantic Ocean at Manasquan Inlet, 
N.J., to Delaware Bay above Cape May, N.J., by the 
further improvement of Manasquan River and Inlet, 
N.J., and the present New Jersey Intracoastal Waterway, 
and by the construction of a canal of similar dimensions 
from Cape May Harbor to Delaware Bay via the 
New England Creek basin, with adequate jetties at the 
Delaware Bay entrance. The total length of the project is 
about 117 miles. Normal tide range in sections of the 
waterway remote from inlets is 0.5 foot. 
Estimated cost for new work is $71,549 (July 1969), 
exclusive of $1,824,940 Navy Department funds and 
$99,000 contributed by localinterests. Portion of project 
extending from Manasquan River to Cape May Harbor 
is to be restudied and excluded from new work costs 
estimate. Estimated cost of this portion is $6,470,000 
(July 1954). Existing project was adopted by 1945 River 
and Harbor Act (H. Doc. 133, 76th Cong., 1st Sess.). 
Latest published map is in project document. River and 
Harbor Act of 1946 (Public Law 525, 79th Cong., 2d 
Sess., as extended by Public Law 240, 82nd Cong.), 
authorized use for a period not to exceed 6 years, of 
funds from appropriations heretofore or hereafter made 
3-8

PHILADELPHIA, PA. DISTRICT 
for maintenance and improvement of rivers and 
harbors, for maintenance of canal from Cape May 
Harbor to Delaware Bay constructed as an emergency 
wartime project with Navy Department funds, including 
cost of maintaining temporary railroad and seashore 
highway bridges over canal. 
Existing project isabout 25 percent complete. A canal 
12 feet deep and 100 feet wide from Cape May Harbor to 
Delaware Bay was completed in 1942; two parallel stone 
jetties at Delaware Bay entrance and a temporary highway 
and a railroad bridge in 1944, all with Navy Department 
funds. Work remaining; dredging a channel 12 feet 
deep and 100 feet wide from Atlantic Ocean at 
Manasquan Inlet to Cape May Harbor, has been 
deferred for restudy; however, the project between 
Ottens Harbor and Richardson Channel and from that 
point to Cape May are being maintained to 10 feet and 
12 feet, respectively, since they were originally dredged to 
these depths by the State. 
Local cooperation. The project is subject to the conditions 
that the State of New Jersey cede to the United 
States all right, title, and interest that it has acquired to 
lands, easements, rights-of-way, and structures other 
than bridges for the Bayhead-Manasquan Canal; that 
the State of New Jersey furnish, free of cost to the United 
States, all lands, easements, rights-of-way, and disposal 
areas require4 for construction of the Cape May Canal 
and for improvement of the proposed waterway and for 
their subsequent maintenance; that local interests 
provide, maintain, and operate suitable bridges over the 
waterway; that the State of New Jersey donate to the 
United States the navigation aids in use on the present 
New Jersey Intracoastal Waterway; and that the State of 
New Jersey hold and save the United States and its 
agents free from any claims for damages resulting from 
the work of improvement. Compliance with these conditions 
was completed January 15, 1954, except that local 
interests are required to furnish disposal areas for the 
construction and the subsequent maintenance of the 
proposed improvement. 
Terminal facilities. See Annual Report for 1962. 
Operations during fiscal year. Maintenance, contract: 
Maintenance dredging performed by plant rental 
during the period of 27 April 1983, and was still in 
progress at the end of fiscal year 1983. Removed an 
estimated 118,500 cubic yards of material. 
Maintenance, hired labor: Work included plans and 
specification on bulkhead erosion, real estate management 
service, general maintenance, monumentation, 
and supervision and administration. 
14. SALEM RIVER, N.J. 
Location. This river rises in Salem County, N.J., 
flows through the county westerly 13 miles, thence 
southerly 7 miles to the City of Salem, and thence 
westerly 3 miles, emptying into Delaware River about 45 
miles below Philadelphia, Pa. It is joined at Salem by 
Little Salem River, or Fenwick Creek, from the east. 
(See U.S. Coast and Geodetic Survey Chart No. 294.) 
Previous projects. The River and Harbor Act of 
July 11, 1870, provided for a survey and the original 
project was adopted by River and Harbor Act of March 
3, 1871, and modified in 1878, and a subsequent project 
adopted by River and Harbor Act of March 2, 1907. For 
further details see page 1784, Annual Report for 1915; 
page 349 of Annual Report for 1924; and page 346 of 
Annual Report for 1938. 
Existing project. This provides for a channel 12 feet 
deep at mean low water, 150 feet wide in Delaware River 
across Salem Cove to the mouth, thence 100 feet wide to 
the fixed highway bridge in Little Salem River at Salem, 
2 miles above the mouth. It also provides for a cutoff 
to eliminate a large horseshoe bend between the mouth 
and Salem. The total length of the section included in the 
project is about 4 miles. The mean tidal range is 5.4 feet. 
The extreme tidal range is from about I foot below mean 
low water to about 2 feet above mean high water. 
The estimate of cost for new work is $51,825 exclusive 
of amounts expended on previous projects and $51,825 
contributed by local interests. The portion of the project 
comprising the deepening of Little Salem River to 12 
feet is to be restudied and is excluded from the foregoing 
estimate. The estimated cost of this portion revised in 
1953 is $28,000 excluding an equal amount to be 
contributed by local interests. 
The existing project is about 64 percent complete. The 
dredging of the channel from Penns Neck Bridge to 
project dimensions, including the cutoff, was completed 
in 1928. The channel from Penns Neck Bridge to the 
fixed highway bridge in Little Salem River was dredged 
to a depth of 9 feet under a previous project. The work 
remaining to be done is the deepening of the channel in 
Little Salem River from 9 feet to 12 feet. 
The controlling depths at mean low water were as 
follows: In January 1961, Delaware River to Penns 
Neck Highway Bridge 12.0 feet; and thence in December 
1956 to the fixed highway bridge at Salem, 0.9 feet. 
The existing project was adopted by the River and 
Harbor Act of March 3, 1925 (H. Doc. 110, 68th Cong. 
1st Sess.). The latest published map is in the document. 
3-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Local cooperation. The existing project required 
that local interests contribute 50 percent of the estimated 
costs of new work and that a right-of-way for the 
proposed cutoff shall be conveyed to the United States 
free of cost. The contributions thus far made provided 
the right-of-way for the cutoff and 50 percent of the cost 
of the 12-foot channel up to a point 225 feet above the 
county (Penns Neck) highway bridge, amounting to 
$51,825. 
Terminal facilities. There are 9 wharves on the river 
all at Salem, N.J. Eight wharves are privately owned and 
one is owned by the City. The facilities are considered 
adequate for existing commerce. 
Operations during fiscal year. Maintenance, 
contract: Environmental assessment prepared. 
Maintenance, hired: Environmental assessment prepared. 
15. SCHUYLKILL RIVER, PA. 
Location. Rises in Schuylkill County, Pa., flows 
generally southeasterly 150 miles, and empties into 
Delaware River at Philadelphia, Pa. (See U.S. Coast 
and Geodetic Survey Charts 295 and 280.) 
Previous project. For details see page 325, Annual 
Report for 1932. 
Existing project. This provides for a channel 33 feet 
deep and 400 feet wide in Delaware River to the mouth 
and within the river to 29th Street, .75 mile above the 
mouth; thence the same depth and 300 feet wide to 
Passyunk Avenue Bridge, 3.5 miles above the mouth; 
thence 26 feet deep and 200 feet wide to Gibson Point, 
4.5 miles above the mouth; and thence 22 feet deep and 
200 feet wide to University Avenue Bridge, 6 miles above 
the mouth, including widening at bends. The total length 
of the section included in the project is about 6.5 miles. 
All depths refer to the plane of mean low water. The 
extreme tidal range, due to freshets and prolonged heavy 
winds, is about 14 feet. 
The cost for new work for the completed existing 
project was $2,809,007. Existing project was completed 
in September 1962. For details see Annual Report for 
1962. (See Table 3-B at end of chapter for Acts 
authorizing existing project.) 
Local cooperation. The River and Harbor Act of 
July 24, 1946, imposed the condition that the city of 
Philadelphia agree to remove 60,000 cubic yards, place 
measurement, of material annually from that portion of 
those portions of the project which the District Engineer 
may designate until such time as adequate municipal 
sewage-treatment works are constructed and placed in 
effective operation. Compliance with this condition has 
been met through the completion of sewage-treatment 
works by the city of Philadelphia. All other 
requirements have been fully complied with. 
Terminal facilities. There are 38 wharves, piers, and 
docks within limits of improvement. Facilities are 
considered adequate for existing commerce. (For 
further details see Port Series No. 7-Revised 1967-Corps 
of Engineers.) 
Operations during fiscal year. Maintenance, 
contract: Dredging of the 26' channel from Passyunk 
Avenue bridge to Gibson Point by Norfolk Dredging 
Company was performed during the period of 31 August 
to 24 September 1983. Removed an estimated 320,000 
cubic yards of material. Stream gaging performed by 
USGS. 
Maintenance, hired labor: Work included general 
maintenance, engineering surveys, environmental 
monitoring, plans and specifications, engineering and 
design on 26' channel and supervision and administration 
on 26' and 33' channel. 
16. WILMINGTON HARBOR, DEL. 
Location. Formed by Christina River, which rises 
in New Castle County, Del., flows north-easterly 16 
miles, passing through city of Wilmington, Del., and 
empties into Delaware River about 29 miles below 
Philadelphia, Pa. (See U.S. Coast and Geodetic Survey 
Chart 294.) 
Previous projects. For details see page 1785 of 
Annual Report for 1915 and page 308 of Annual Report 
for 1938. 
Existing project. This provides for a channel 35 feet 
deep and 400 feet wide from west edge of Delaware 
River ship channel to Lobdell Canal, a distance of about 
1.2 miles; thence 21 feet deep and 250 feet wide for the 
distance of .8 mile to the mouth of Brandywine River; 
thence the same depth and 200 feet wide for a distance of 
about 2.2 miles to a point approximately 4.2 miles from 
the Delaware River ship channel; thence decreasing a 
depth of 10 feet in a distance of 750 feet to Penn Central 
Railroad bridge No. 4; and thence 7 feet and 100 feet 
wide for a distance of about 5.6 miles to Newport, Del., 
approximately 9.9 miles above Delaware River ship 
channel, including a turning basin 35 feet deep opposite 
the Wilmington Marine terminal and extending 
upstream from the mouth to Lobdell Canal, 200 feet 
wide, 2,900 feet long on the north side of the channel and 
decreasing to a length of 2,000 feet on the north side of 
the basin. It also provides for the removal of about 1,200 
3-10

PHILADELPHIA, PA. DISTRICT 
of the outer end of a stone-filled, pile-and-timber crib 
jetty constructed 2,150 feet long on the north side of the 
entrance; for a steel sheet-pile jetty 2,300 feet long, with 
120-foot inshore wing, on the south side of the entrance, 
and for a V-shaped stone-filled pile-and-timber jetty at 
the mouth of Brandywine River 430 feet along the north 
side of Brandywine and 260 feet long on the Christina. 
Depths refer to the plane of mean low water. The 
extreme tidal range, due to prolonged heavy winds, is 
about 13 feet. Existing project was completed in 1962. 
(For details see page 222, Annual Report 1962.) (See 
Table 3-B at end of Chapter for Acts authorizing 
existing project.) 
Local cooperation. Fully complied with. 
Terminal facilities. There are 18 piers, wharves, and 
docks within improvement. Facilities considered 
adequate for existing commerce. (For further details see 
Port Series No. 8, revised 1966, -Corps of Engineers). 
Operations during fiscal year. Maintenance, 
contract: Dredging in the Christina River was 
performed during the period of 15 October to 2 
November 1982, and from 4 June to 25 June 1983, by the 
Norfolk Dredging Company. Removed a combined 
total of 795,687 cubic yards of material. Other work 
included construction of steel sluices, stream gaging by 
USGS, raising banks, at Wilmington Harbor, and 
Edgemoor disposal areas and subsurface investigations. 
Maintenance, hired labor: Work included condemnation 
of land at Cherry Island disposal site, subsurface 
investigations, disposal area management study, 
environmental study of disposal area, plans and specifications, 
construction of steel sluices, raise banks at 
Wilmington Harbor, and Edgemoor disposal areas, and 
engineering and design and supervision and administration. 
Beach Erosion Control 
17. SHORELINE EROSION CONTROL 
DEMONSTRATION 
Location. Demonstration projects were undertaken 
at a total of 16 sites nationwide, 6 of which are located in 
the Delaware Bay and include Pickering Beach, Kitts 
Hummock, Slaughter Bowers Beach, Broadkill Beach, 
and Lewes, Delaware. The latter three sites were only 
monitored as there are presently Federal and State 
projects in progress. 
Existing project. Section 54 of Water Resources 
Development Act of 1974 authorized a nationwide, 5 
year program to test and evaluate low cost shoreline 
erosion control measures, both structural and 
vegetative, which can be implemented by individual 
private property owners. The emphasis of the program 
was not to solve individual problems, so much as to 
explore the effectiveness of various ways to control 
erosion at different types of shorelines, and provide this 
information to private and public landowners. The 
construction and evaluation at all sites are completed 
and information dissemination has been started. 
Operations during fiscal year. New work, hired 
labor: Only costs incurred were in support of information 
dissemination program. Cost during this period 
was $20,897. 
18. BEACH EROSION CONTROL WORK 
UNDER SPECIAL AUTHORIZATION 
Beach erosion control activities pursuant to Section 
103, Public Law 87-874 (Preauthorization). 
Project 
Lewes, Del. 
Port Mahon, Del. 
Fiscal Year Cost 
$36,173 
15,529 
Flood Control 
19. BELTZVILLE LAKE, PA. 
Location. Damsite is on Pohopoco Creek about 4.5 
miles upstream from its confluence with Lehigh River 
and 4 miles east of Lehighton, Pa. (See Geological 
Survey Quadrangle Map for Lehighton, Pa. - 1960.) 
Existing project. A multiple purpose development 
project providing water supply, flood control, and 
recreation. Plan of improvement provides for an earth 
and rock fill dam 4,200 feet long rising 170 feet above 
creekbed; a spillway around north end of dam; and 
gatecontrol outlet works discharging through a conduit 
on rock along right abutment. The lake, a unit of 
comprehensive plan for flood control and other 
purposes of Delaware River Basin, has a reservoir 
capacity of 68,250 acre-feet at spillway crest level with 
1,390 acre-feet of inactive storage, 39,830 acre-feet for 
water supply and recreation, and 27,030 acre-feet for 
flood control. The cost of project was $22,931,400 
including $6,100,000 required non-Federal reimbursement 
for costs allocated to water supply storage during 
life of project. The construction of the dam and 
appurtenances was completed in 1971. 
Local cooperation. Project was approved subject to 
certain requirements of cooperation by local interests as 
defined in approved House Document. Resolution of 
Delaware River Basin Commission providing 
assurances of repayment of water supply and pollution 
control costs was accepted June 7, 1965. A contract for 
repayment of water supply costs was signed October 16, 
1966. 
3-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Operations during fiscal year. Maintenance, 
contract: Work included water quality testing, repair of 
water quality control system, installation of access 
ladder, sealing of control tower, inspection of stilling 
basin, stream gaging, snow surveys, and operation of 
dam and service facilities. Reimbursement received 
from DRBC for water storage. 
Maintenance, hired labor: Work included periodic 
inspections, repair of water quality control system, 
water quality data collection, and processing, survey 
monumentation, water control analysis, sealing of 
control tower, operation of dam and service facilities, 
and engineering and design and supervision and 
administration. 
20. BLUE MARSH LAKE, PA. 
Location. Damsite is on Tulpehocken Creek about 
1.5 miles upstream from its confluence with Plum Creek 
and about 6 miles northwest of Reading, Pa. (See 
Geological Survey Quadrangle Sheet, Bernville, Pa.) 
Existing project. This is a multiple purpose 
development project providing water supply, flood 
control, and recreation. Construction started in 1974 
and was completed in 1980. The dam is 1,775 feet long 
and rises 98 feet above creekbed, with a spillway about 
1,500 feet south of dam, and gate-controlled outlet 
works discharging through a conduit on rock along right 
abutment. The lake, a unit of comprehensive plan for 
flood control and other purposes of Delaware River 
Basin, has a capacity of 50,010 acre-feet at spillway crest 
level, with 3,000 acre-feet of inactive storage, 14,620 
acre-feet for water supply and recreation, and 32,390 
acre-feet for flood control. (For details see H. Doc 522 
87th Cong., 2d Sess.) Cost of project (October 1982), 
$63,042,392 includes $16,132,000 required non-Federal 
reimbursement for costs allocated to water supply 
storage during life of project after use of this storage 
is initiated. Existing project was authorized by 1962 
Flood Control Act (H. Doc. 522, 87th Cong., 2d Sess., 
contains latest published maps). 
Local cooperation. Project was approved subject to 
certain requirements by local interests, as prescribed in 
House Document cited above. Delaware River Basin 
Commission on December 29, 1964, adopted a 
preliminary resolution providing for repayment of water 
supply costs. 
Operations during fiscal year. New work, contract: 
Work included rearrangement and alteration of roads, 
and modification of fire hydrant. 
New work, hired labor: Work included miscellaneous 
work to close out real estate activities, engineering and 
design and supervision and administration. 
Maintenance, contract: Work included drilling of well at 
recreation area, stream gaging, snow survey, water 
quality testing and monitoring, building inspection, 
stilling basin cleanup, mowing and fertilizing recreation 
area, lawn maintenance, law enforcement, operation of 
dam and service facilities and maintenance of Skinner 
camping area. 
Maintenance, hired labor: Work included operation of 
recreation area, periodic inspections, hydrologic data 
collection, building inspection, instrument and 
surveillance pnalysis, water quality data collection, 
operation of dam and service facilities, engineering and 
design and supervision and administration. 
21. CAPE MAY INLET TO LOWER TOWNSHIP 
N.J. 
Location. The proposed project is located in Cape 
May County and extends along the beach front from the 
northern side of Cape May Inlet to the boundary of 
Lower Township, and Cape May City. 
Existing project. The proposed project consists of a 
sand bypassing system on the northeast side of Cape 
May Inlet consisting of a weir-breakwater and 
deposition basin, with construction of the weir-breakwater 
being deferred pending demonstration of need; 
The placement of sand on the beach to provide a berm 
having an elevation of 8 feet above NGVD and a 
maximum width of 180 feet between Cape May Inlet and 
Wilmington Avenue, hence a width of 25 feet to the 
Third Avenue groin in Cape May City; 
Construction of two groin extensions in Cape May 
City; 
Maintenance of two new and seven existing groins in 
Cape May City; 
Periodic nourishment of the beaches to maintain the 
project cross-section during the life of the project. 
Estimated cost of the project (October 1983) is 
$48,800,000. The existing authority is for Phase I studies 
as provided by Section 101 (a) of the Water Resources 
Development Act of 1976 in accordance with the 
provisions of House Document 94-641. Planning and 
Engineering studies were initiated in FY 1978. The 
Phase I GDM was completed in September 1980 with 
release of Division Engineer's notice. Final action on the 
Phase I GDM taken by OCE in December 1981. 
Local cooperation. Assurances of local cooperation 
were furnished by the State of New Jersey Department 
of Environmental Protection in letter dated 20 April 
1972. 
3-12

PHILADELPHIA, PA. DISTRICT 
Operations during fiscal year. Completed Phase II 
Advance Engineering and Design July 1983. 
22. DELAWARE COAST PROTECTION, DEL. 
Location. The project is located in Sussex County, 
Delaware, on the Atlantic Ocean and starts immediately 
south of Delaware Bay extending in a southerly 
direction a distance of 24.5 miles to Fenwick Island on 
the Delaware-Maryland border 
Existing project. Provides a plan of improvement 
which consists of the construction of dunes and beach 
fill; the construction of bulkheads at Rehoboth and 
Dewey beaches; periodic nourishment of the beaches; 
placement of sand fences; planting dune grass and 
maintenance and replacement of existing structures. 
(For details, see S. Doc. 90, 90th Cong., 2d Sess.) 
Estimated cost of project (October 1983) $300,000,000 
includes $177,000,000 required non-Federal costs. The 
construction of the feeder beach north of Indian River 
Inlet was completed in 1973 and nourished in 1978. 
Other work undertaken has been engineering and design 
associated with the rest of the project. 
Local cooperation. Assurances of local cooperation 
were provided by the State of Delaware, January 13, 
1981. 
Operations during fiscal year. New work, hired 
labor: Work included environmental studies, hydraulic 
investigations, design and cost estimates, study 
management, real estate study and engineering and 
design. 
23. FLOOD CONTROL WORK UNDER SPECIAL 
AUTHORIZATION 
Flood control activities pursuant to Section 205, Public 
Law 838, 80th Congress, as amended (preauthorization). 
Study 
Cobbs Creek, Haverford Township, PA 
Darby Creek, Borough of Colwyn,PA 
Darby Creek, Darby Borough, PA 
Pennypack Creek, Hatboro,PA 
Poquessing Creek, Bucks County, PA 
Ridley Creek, Chester, PA 
Wallkill River, (Black Dirt Area),NJ 
Woodbury Creek, NJ 
Fiscal Year Cost 
$ 27 
7,482 
71,750 
56,442 
46,716 
7,500 
165,801 
7,500 
Also feasibility study pursuant to Emergency Bank 
Protection Authority provided by Section 14 of the 1946 
Flood Control Act. 
Study 
Darby Creek, Lansdowne, PA 
Equinunk Creek, Wayne County, PA 
Pennypack Creek, Montgomery County, PA 
Fiscal Year Cost 
$ -2,000 
22,505 
5,000 
Emergency flood control activities - repair, flood 
fighting, and rescue work (Public Law 99, 84th 
Congress, and antecedent legislation). 
Fiscal year costs were $126,249 for advance preparation. 
24. FRANCIS E. WALTER DAM, PA. 
Location. Reservoir is in northeastern Pennsylvania 
on Lehigh River between White Haven and 
Stoddartsville. Dam is about 0.4 mile below mouth of 
Bear Creek, about 60 miles above confluence of Lehigh 
River and Delaware River at Easton, Pa. (See 
Geological Survey Quadrangle Sheet, Stoddartsville, 
Pa.) 
Existing project. Plan of improvement authorized 
by 1946 Flood Control Act (H. Doc. 587, 79th Cong., 2d 
Sess.) provided for a single purpose flood control 
reservoir. Modification of project, authorized by 1962 
Flood Control Act (H. Doc. 522, 87th Cong., 2d Sess.), 
provides for a multiple-purpose development for water 
supply and recreation in addition to present singlepurpose 
flood control project. Plan of improvement 
requires altering spillway increasing height of dam, 
extending outlet tunnel by addition of a concrete 
conduit, and constructing new dikes and raising existing 
dikes.Modified dam will rise 263 feet above riverbed and 
be 3,500 feet long. Reservoir modification, a unit of 
comprehensive plan for flood control and other 
purposes of Delaware River Basin, will have a reservoir 
capacity of 180,000 acre-feet spillway crest level with 
2,000 acre-feet of inactive storage, 70,000 acre-feet for 
water supply and recreation and 108,000 acre-feet for 
flood control. Estimated Federal cost of new work 
(October 1983) is $77,000,000 including $68,900,000 
required non-Federal reimbursement for costs allocated 
to water supply storage during life of project after use of 
this storage is initiated. Project as authorized under the 
1946 Flood Control Act was completed June 1961. 
Settlement for lands was completed October 1962. The 
advance engineering and design for the modified project 
is now underway. 
Local cooperation. None required under 1946 
Flood Control Act. Under 1962 Flood Control Act, 
project was approved subject to certain requirements by 
local interests, as defined in House Document 522 cited 
above. The Delaware River Basin Commission 
reiterated its sponsorship for the modified project in 
August 1982. 
3-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Operations during fiscal year. New work, contract: 
Performed sediment analysis at Harrisburg, Pa. 
Maintenance, contract: Work included minor 
maintenance of recreation area facilities, snow survey, 
water quality testing, stream gaging, and reservoir 
operation and minor maintenance. 
Maintenance, hired labor: Work included minor 
maintenance of recreation area, periodic inspections, 
hydrologic data collection, water quality testing, guard 
rail repairs, instrument and surveillance analysis, slope 
deformation study, repair of stoplogs and monorail, 
reservoir operation and minor maintenance, and general 
engineering and design. 
25. GENERAL EDGAR JADWIN DAM AND 
RESERVOIR, PA. 
Location. In Dyberry Creek valley in central part of 
Wayne County, Pa., between borough of Honesdale and 
village of Tanners Falls. Dam is about 3 miles above 
confluence of Dyberry Creek and Lackawaxen River in 
Honesdale and 29 miles above confluence of 
Lackawaxen and Delaware Rivers. (See Geological 
Survey Quadrangle Sheet, Honesdale, Pa.) 
Existing project. A single-purpose flood control 
reservoir with a capacity of 24,500 acre-feet formed by 
an earth embankment, about 1,225 feet long at crest and 
rising 109 feet above creek bed. It also has a tunnel with 
intake structure and a chute-type spillway with a stilling 
basin in left abutment. Reservoir controls runoff from a 
drainage area of 65 square miles which is 91 percent of 
watershed of Dyberry Creek and 39 percent of 
Lackawaxen River watershed above Honesdale, Pa. 
Construction of project was authorized by 1948 Flood 
Control Act (H. Doc. 113, 80th Cong., 1st Sess.). 
Federal cost of new work was $4,064,510. Non-Federal 
funds not required. Project was completed in June 1960. 
Local cooperation. Assurances of compliance with 
requirements of local cooperation were accepted July 
30, 1956. For details see page 251, Annual Report for 
1962. 
Operations during fiscal year. Maintenance, 
contract: Work performed included cleanup and 
inspection of stilling basin, stream gaging, and reservoir 
operation and minor maintenance. 
Maintenance, hired labor: Work included, cleanup of 
stilling basin, safety inspections, instrument and 
surveillance analysis, hydrologic data collection, dam 
survey, reservoir operation and minor maintenance, and 
engineering and design and supervision and 
administration. 
26. HAY CREEK, BIRDSBORO, SCHUYLKILL 
RIVER BASIN, PA. 
Location. The site of the authorized project is 
within the urban community of Birdsboro, Berks 
County, Pennsylvania, at the confluence of Hay Creek 
and Schuylkill River. The project as recommended by 
the most recent studies starts near the Armorcost Road 
Bridge in Hay Creek and extends upstream to the 
Conrail Railroad Bridge. 
Existing project. The authorized plan of 
improvement includes a 3,750 foot combination earth 
levee and concrete flood wall beginning at a point just 
below East Main Street and proceeding upstream 
approximately 900 feet above First Street. Included also 
are 2 new raised bridges to replace those at East Main 
Street and First Street and modification to an existing 
railroad bridge, as well as interior drainage facilities. 
The project was authorized in 1976 under the provisions 
of Section 201 of the Flood Control Act of 1965. 
However, the project as recommended by the findings of 
the advance engineering and design would consist of 
landfill placed in a redevelopment area along Hay 
Creek. A Post Authorization Change Report was 
submitted to the office of the Chief of Engineers for 
approval of the project as a component of an urban 
renewal program. Subsequently, the decision was 
reached that no further work would be done on the 
project because it could not be economically justified on 
its own merits without being combined with the urban 
renewal program. 
Local cooperation. Assurances of local cooperation 
were received from the Borough of Birdsboro, Pennsylvania, 
in a letter dated 16 January 1973 which was signed 
by the Borough Manager. Continued interest in the 
project had been re-established in letters dated 13 
September 1977, and 26 August 1980. 
Operations during fiscal year. New work, hired 
labor: Work included preparation of the final 
unfavorable AE&D report, AE&D study management, 
and engineering and design. 
27. INSPECTATION OF COMPLETED FLOOD 
CONTROL PROJECTS 
To ascertain whether local interests were maintaining 
and operating completed projects as required, inspections 
were made as follows: 
PROJECT 
Lehigh River at Allentown, PA 
Lehigh River at Bethlehem, PA 
Delaware River at East Branch, NY 
INSPECTION 
DATES 
5 October 1982 
26 April 1983 
12 October 1982 
5 March 1983 
21 October 1982 
3 May 1983 
3-14

PHILADELPHIA, PA. DISTRICT 
Rancocas Creek at Mount Holly. NJ 
Chester River at Chester. PA 
26 October 1982 
5 April 1983 
27 October 1982 
6 April 1983 
Local interests are satisfactorily maintaining and 
operating projects in accordance with regulation. Costs 
during the period were $5,078. Total costs were $85,887. 
28. INSPECTION OF NON-FEDERAL LEVEES 
Inspection of non-Federal levees were conducted at a 
cost of $2,275, at the following sites: 
Stroudsburg/ East Stroudsburg, PA 
Hawley, PA 
7 September 1983 
8 September 1983 
29. POTTSTOWN AND VICINITY, 
SCHUYLKILL RIVER BASIN, PA. 
Location. The site of the authorized project is 
located in Pennsylvania along the Manatawny Creek 
and the Schuylkill River in the City of Pottstown, 
Montgomery County, and the communities of South 
Pottstown and Kenilworth, Chester County, 
Pennsylvania. 
Existing project. The physical construction as 
authorized would consist of channel improvements 
along the Schuylkill River and excavation of an area 
under an arch of the existing High Street bridge on the 
Manatawny Creek. The Schuylkill River channel would 
be widened to a width of 275 feet for a distance of about 
7,600 feet. Stone protection would be provided along the 
channel where flow conditions require it. Excavated 
material would be utilized to develop open space areas 
along the river. Estimated cost of the project (October 
1983) is $5,320,000. The project was authorized in 1974 
under Section 201 of the 1965 Flood Control Act. 
However, the findings of the advance engineering and 
design in 1978 indicated that there were not enough 
benefits to justify any Federal project at Pottstown. 
Those findings were reevaluated in 1982 and the 
conclusion still remained that there were no 
economically justified projects. Congress will be 
apprised of this conclusion. 
Local cooperation. Local interests (the Borough of 
Pottstown, Pennsylvania) furnished assurances of local 
cooperation by letter dated 28 September 1970. The 
borough reaffirmed the assurances by a resolution dated 
8 January 1973. 
Operations during fiscal year. New work, hired 
labor: Stage 2 study management. 
30. PROMPTON LAKE, PA. 
Location. In Lackawaxen River Valley in central 
part of Wayne County, Pa., between borough of 
Prompton and village of Aldenville. Dam is within 
corporate limits of Prompton, 4 miles upstream from 
Honesdale, Pa., and approximately 30 miles above 
confluence of Lackawaxen and Delaware Rivers. (See 
Geological Survey Quadrangle Sheet, Honesdale, Pa.) 
Existing project. Plan of improvement authorized 
by 1948 Flood Control Act (H. Doc. 113, 80th Cong., 1st 
Sess.) provides for a single-purpose flood control 
reservoir. Modification of project authorized by 1962 
Flood Control Act (H. Doc. 522, 87th Cong., 2d Sess.) 
provides for a multiple-purpose development for water 
supply and recreation in addition to present singlepurpose 
flood control project. Plan of improvement 
requires construction of a control tower with gates and 
service bridge, placing an impervious blanket on valley 
walls and floor upstream from dam, widening spillway, 
and clearing land and relocating roads in reservoir. 
Dam, completed under 1948 Flood Control act which 
will not be modified, is 1,230 feet long and rises 140 feet 
above riverbed. Existing spillway, cut into rock of right 
abutment, will be modified and present uncontrolled 
outlet works discharging into a concrete conduit along 
right bank, will be provided with gates and a control 
tower. Reservoir modification, a unit of comprehensive 
plan for flood control and other purposes of Delaware 
River Basin has a capacity of 52,000 acre-feet; 3,500 
acre-feet for inactive storage, 28,200 acre-feet for water 
supply and recreation, and 20,300 acre-feet for flood 
control. Estimated Federal cost of new work (October 
1983) is $39,500,000 including $34,760,000 required 
non-Federal reimbursement for costs allocated to water 
supply storage during life of project after use of this 
storage is initiated. Project as authorized under the 1948 
Flood Control Act was completed in November 1960. 
(For details, see page 358, Annual Report for 1963.) 
Work accomplished under the 1962 Flood Control Act 
was advance engineering and design. 
Local cooperation. Project modification was 
approved subject to certain requirements by local 
interests, as defined in House Document 522 cited 
above. Assurances of compliance under Flood Control 
Act of 1948 have been met. Delaware River Basin 
Commission on March 18, 1966, gave their view that the 
need for water supply was not urgent at that time. 
However recent studies conducted by DRBC have 
determined that there is now a need for water supply. In 
August 1983, DRBC expressed their strong support for 
the project modification. Therefore resumption of planning 
will take place when funds are made available. 
Operations during fiscal year. Maintenance, 
contract: Work included underwater inspection of 
stilling basin, stilling basin cleanup, surveys, stream 
3-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
gaging, reservoir operation and minor maintenance, and 
water quality monitoring. 
Maintenance, hired labor: Work included stilling basin 
cleanup, stilling basin access ladder, safety inspections, 
stream gaging, water quality monitoring, hydrologic 
data collection, rehabilitation of access road, trash rack 
removal, removal of stoplog structure, plans and 
specifications, dam survey, instrument and surveillance 
analysis, reservoir operation and minor maintenance, 
and engineering and design and supervision and 
administration. 
31. TAMAQUA, PA. 
Location. The authorized project is located in 
Tamaqua Borough and Walker Township, Pennsylvania. 
Both municipalities are within Schuylkill County. 
Existing project. The project as authorized would 
provide a 2,930 foot long tunnel, 10 feet in diameter with 
appurtenant structures, through Sharp Mountain. It 
would extend from Wabash Creek on the west boundary 
of Tamaqua to the Little Schuylkill River just south of 
its confluence with Wabash Creek. The proposed 
improvement includes an intake structure, a stilling 
basin, and a 70-foot long highway bridge. Estimated 
cost of project (October 1983) is $8,820,000 including 
$160,000 required non-Federal costs. The Phase I 
portion of the advance engineering and design was 
completed in 1981. The findings from that phase 
resulted in the addition of a small dry detention dam to 
the project plan. Phase II AE&D conducted by Baltimore 
District. For further information see Baltimore 
District Annual Report. 
32. RECONNAISSANCE AND CONDITION 
SURVEYS 
Project 
Cedar Creek after dredging 
Cohansey River 
Mispillion River 
Murderkill River 
Date Survey Conducted 
26-27 August 1982 
14 April 1983 
9 August 1983 
29 September 1983 
General Investigations 
33. SURVEYS 
Costs for the period were $626,879 for navigation 
studies: $482,393 for flood control studies: and $145,736 
for special studies, a total of $1,255,008. 
34. COLLECTION AND STUDY OF BASIC DATA 
Costs and expenditures during the period for flood 
plain information studies were $127,185. 
35. ADVANCE ENGINEERING AND DESIGN 
The total costs for this category amounted to 
$220,643. Of that amount, $118,927 was for the Phase II 
advance engineering and design on the proposed Cape 
May Inlet to Lower Township, N.J. project (see 
paragraph 21 of this report for a full description of the 
project); $101,716 was for the studies associated with the 
Delaware River at Camden, N.J. project (see paragraph 
6 of 1982 Annual Report for a full description). 
3-16

PHILADELPHIA, PA. DISTRICT 
TABLE 3-A COST AND FINANCIAL STATEMENT 
See 
Section 
in Text Projects Funding FYNV FYV1 FYV3 FY3 Sept. 30, 193 
1. Absecon Inlet, 
N.J. 
(Regular 
Funds 
2. Barnegat Inlet, 
N.J. 
(Regular 
Funds) 
(Contributed 
Funds) 
3. Cohansey River, 
N.J. 
(Regular 
Funds) 
4. Cold Spring Inlet, 
N.J. 
(Regular 
Funds) 
(Contributed 
Funds) 
5. Delaware River 
Between Philadelphia, 
Pa. and 
Trenton, N.J. 
(Regular 
Funds) 
(Contributed 
Funds 
6. Delaware River 
Pa., N.J. and 
Del., Philadelphia 
to the Sea 
(Regular 
Funds)* 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
24,400 
23,720 
9,000 
10,908 
6,000 
3,584 
205,400 201,000 362,500 
203,897 210.550 365,491 
i 
84,900 
62,943 
- 
.20,981 
2,427 414 
400,500 3,240,000 3,158,000 
372,082 3,271,657 3,167,472 
62,000 
2.065 
703,000 
680,607 
30,000 
11,049 
396,000 
395,501 
967,000 
968,187 
14,897,900 13,908,163 13,794,188 16,782,000 
14,850,493 13,957,353 13,743,314 16,775,510 
3-17 
534,209' 
534,209' 
5,857,3622 
5,794,8482 
448,849 
448,849 
9,051,135 
9,026,656 
300,000 
300,000 
146,756� 
146,7563 
775,931 
756,980 
879,275 
879,275 
2,279,507 
2.278,953 
1,134,346 
1,134,346 
150,000 
150,000 
72,147,800' 
72,147,800' 
26,210,735' 
26,210,3815 
15,000 
35,000 
57,879,872* 
57,879,8726 
263,050,567' 
262,925,272' 
508,324 
508,324

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 3-A (continued) COST AND FINANCIAL STATEMENT 
See 
Section 
in Text Projects Funding FY80 FY81 FY82 FY83 Sept. 30,1983 
7. Indian River 
Inlet and Bay, 
Del. 
(Regular 
Funds) 
(Contributed 
Funds) 
8. Inland Waterway 
Rehoboth Bay 
to Delaware 
Bay, Del. 
(Regular 
Funds) 
(Contributed 
Funds) 
9. Inland Waterway 
from Delaware 
River to Chesapeake 
Bay, Del. 
and Md. 
(Regular Funds)* 
10. Manasquan 
River, N.J. 
(Regular 
Funds) 
*
(Contributed 
Funds) 
11. Murderkill 
River, Del. 
(Regular 
Funds) 
13. New Jersey 
Intracoastal 
Waterway 
(Regular 
Funds) 
*
(Contributed 
Funds) 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
836,200 403,000 
795,533 442,491 
48,400 
53,407 
2,949 
8,140,300 
7,173,706 
89,700 
107,234 
81,400 
80,925 
634 
11,000 
11,175 
-16,000 
697 
.- - 
114,000 
112,228 
26 - 
8,508,000 7,078,400 12,045,500 
9,472,669 6,836,659 12,225,774 
-169 
172 
2,555,000 3,640,000 
2,346,583 2,263,314 
116,000 
115,710 
4,581 
5,888 
100,000 
4,612 
1,378,056 
170,000 
163,484 
721,000 889,000 1,446,100 
729,452 719,388 1,554,708 
15,000 
94,659 
177,314 
511,2108 
511,2108 
2,737,923 
2,737,752 
1,323,775 
1,323,775 
210,000 
210,000 
561,514 
561,514 
1,274,978 
1,272,406 
60,000 
60,000 
132,535,59112 
132,532,30112 
125,879,43013 
125,626,10013 
557,24921 
557,24921 
3,096,55722 
3,080,82822 
7,410,60025 
7,342,83025 
300,000 
300,000 
_. 37,630 
37,630 
- 956,355 
5,235 955,074 
818,000 
849,876 
71,54914 
71,54914 
17,482,571 's 
17,448,067s5 
1,196,581 
1,196,581 
99,000 
99,000 
3-18

TABLE 3-A (continued) 
PHILADELPHIA, PA. DISTRICT 
COST AND FINANCIAL STATEMENT 
See 
Section 
in Text Projects Funding FY80 FY81 FY82 FY83 Sept. 30, 1983 
14. Salem River, N.J. 
(Regular 
Funds) 
(Contributed 
Funds) 
15. Schuylkill 
River, Pa. 
(Regular 
Funds) 
16. Wilmington 
Harbor, Del. 
(Regular 
Funds) 
*
(Contributed 
Funds) 
19. Beltzville Lake, 
Pa. 
(Regular 
Funds) 
20. Blue Marsh 
Lake, Pa. 
(Regular 
Funds) 
21. Cape May Inlet 
** to Lower Township, 
N.J. 
22. Delaware Coast 
Protection, Del. 
24. Francis E. 
Walter Dam, Pa. 
(Regular 
Funds) 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp, 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
-71,000 
-74,182 
2,129,500 
2,126,142 
1,225,000 
1,226,976 
1,603,300 
1,593,509 
108,000 
104,454 
1,524,100 
1,501,336 
405,800 539,000 342,400 
387,020 532,531 364,321 
700,000 
1,085,782 
704,600 
685,710 
320 
5,600 
169,000 
179,688 
674,000 
673,539 
-93,855 
794,200 
836,190 
27 
1,457 
. 376,000 
S 282,652 
226,500 320,000 
247,578 299,741 
91,375 
423,300 
446,749 
3-19 
35,000 
21,181 
770,100 
768,856 
2,011,000 
1,980,620 
721,000 
691,749 
118,186 
787,000 
742,145 
-5 
50,000 
43,580 
512 
331,000 
330,420 
107,63428 
107,63428 
325,77929 
311,96029 
51,825 
51,825 
3,334,00716 
3,334,00716 
23,062,033 
23,055,036 
1,954,725" 
1,954,725" 
25,565,165 
25,494,042 
60,000 
60,000 
22,931,831 
22,931,130 
3,626,375 
3,566,812 
63,180,300 
63,160,578 
3,321,100 
3,228,271 
150,000 
145,000 
1,478,953 
1,472,484 
I 1,503,432'19 
11,501,97119' 
3,727,821 
3,711,796

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 3-A (continued) COST AND FINANCIAL STATEMENT 
See 
la Test Projects Fundig FYN0 FY31 FY82 FY83 Sept. 36, 1983 
25. General Edgar New Work 
Jadwin Dam and Approp. . ..- - - 4,073,105 
Reservoir, Pa, Cost ..- 4,073,105 
(Regular Maint. 
Funds) Approp. 55,100 49,400 38,000 104,000 1,073,364 
Cost 56,066 46,295 40,266 91,463 1,059,338 
26. Hay Creek, New Work 
Birdsboro, Approp. 100,000 50,000 -1,000 - 364,305 Schuylkill Cost 84,425 22,178 13,622 4,680 333,598 
River Basin, Pa. 
29. Pottstown and New Work 
Vicinity, Schuylkill Approp. .- 125,000 .- - 487,336 
River Basin, Pa. Cost I11..8 ,140 5,133 1,487 487,097 
30. Prompton Lake New Work 
Pa. Approp. - - - 4,609,483k 
(Regular Cost - -. . . 4,609,483a 
Punds)* Maint. 
Approp. 154,400 116,000 149,300 167,000 1,762,162 
Cost 151,749 121,186 147,927 173,611 1,746,916 
31.*** Tamaqua, Pa. New Work 
** Approp. 75,000 525,000 
Cost 70,910 35,149 3,739 4,311 521,520 
3Transferred 
to Baltimore District fiscal year 1982. 
*Total adjusted to correct discrepancies in prior years. 
**For Constructiop, General funds only on legislative Phase I AEAD, or support work for Phase II AE&D. 
1. Includes $226,497 for new work for previous projects. 
2. Includes $235,786 for maintenance for previous projects. 
3. Includes $50,000 Navy Department Funds. 
4. Includes $2,489,173 for new work, for previous projects, 
$105S,000 for preauthorlzatlon studies and minus $142,015 
adjustment (new work) to Delaware River, Philadelphia to Sea 
project from this project under 1954 modification. 
5. Includes $552,720 for maintenance for previous projects. 
6. Excludes SI12,976,058 for new work for previous projects and 
$142,015 adjustment form Delaware River, Philadelphia to 
Trenton, NJ. under 1954 modification. 
7. Includes $1,025,409 for maintenance of previous projects. 
8. Excludes $10,000 for previous project. 
12. Includes $10,709,755 for new work for previous projects. 
13. Includes $6,903,748 for maintenance for previous projects. 
14. Excludes $1,824,940 Navy Department Funds. 
IS. Excludes $286,953 Navy Department funds expended for maintenance. 
16. Includes SS25,000 for previous projects. 
17. Includes $402,121 for new work for previous project, and 
5206,177 emergency relief funds. 
19. Includes $40,000 appropriated and expended under Code 710 
Recreation Pacilities. 
20. Includes $63,000 appropriate and $61,551 expended under Code 
710 Recreation Facilities, excludes $23,600 preauthorization 
studies under 1948 modification. 
21. Includes $39,000 for new work for previous projects. 
22. Includes 52,054 for maintenance for previous projects. 
25. Includes $555,600 for previous project. 
27. Includes $42,301 expended N.Y. Dist. 
28. Includes $55,809 new work funds expended on previous project. 
29. Includes S1,285 for reconnaissance and condition survey in fiscal 
year 1957, 1SI,792 operation and maintenance cost incurred for 
preparation of environmental impact statement, and $48,000 
expended for maintenance on previous project. 
30. Includes $36,000 for new work for previous projects. 
3-20

PHILADELPHIA, PA. DISTRICT 
TABLE 3-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Sept. 22, 1922 
July 24,1946 
Aug. 30, 1935 
Aug. 26, 1937 
July 24, 1946 
Mar. 2, 1907 
Aug. 26, 1937 
March 2, 1907 
March 2, 1945 
ABSECON INLET, N.J. (See Section I of Text) 
An inlet entrance channel 20 feet deep. 
A channel 15 feet deep into Clam Creek and a turning basin. 
BARNEGAT INLET, N.J. (See Section 2 of Text) 
An 8-foot depth through inlet to Oyster Creek Channel across inner bar, 10-foot 
depth through outer bar and for jetties. 
A channel of suitable hydraulic characteristics from gorge to Oyster Creek 
Channel, and thence to deep water in bay. 
Maintenance dredging of channel to connect main inlet channel with Barnegat 
City Harbor. 
COHANSEY RIVER, N.J. (See Section 3 of Text) 
Channel 7 feet deep over entire project. 
Channel 12 feet deep to Glass Street, thence 8 feet to Commerce Street, 
with turning basin. 
COLD SPRING INLET, N.J. (See Section 3 of Text) 
An inlet channel 25 feet deep and jetties. 
A 20-foot channel to deep water in harbor. 
H. Doc. 375, 67th Cong., 
2d sess. 
H. Doc. 504,79th Cong., 
2d sess.' 
Rivers and Harbors 
Committee Doc. 19, 
73d Cong., 2d sess. 
Rivers and Harbors 
Committee Doc. 85, 
74th Cong., 2d sess.' 
H. Doc. 358, 79th Cong., 
2d sess.' 
H. Doc. 645, 59th Cong., 
Ist sess.' 
Senate Committee print, 
75th Cong., 1st sess. 
H. Doc. 388, 59th Cong., 
2d sess. 
H. Doc. 262, 77th Cong., 
Ist sess. 
July 3, 1930 
Aug. 30, 19352 
Aug. 30, 19352 
Aug. 26, 1937 
July 24, 1946 
Sept. 3, 1954 
DELAWARE RIVER BETWEEN PHILADELPHIA, PA., AND TRENTON, N.J. 
(See Section 4 of Text) 
A channel 28 feet deep, 300 feet wide between Allegheny Ave., Philadelphia, Pa. Rivers and Harbors 
and Delair Bridge. Committee Doc. 3, 
71st Cong., Ist sess. 
Channel 25 feet deep from Delair Bridge to Trenton, N.J., and maintenance of Rivers and Harbors 
12-foot channel from upper end of 25-foot project to Penn Central R.R. Bridge Committee Doc. 11, 
at Ferry St., Trenton. 73d Cong., Ist sess. 
Auxiliary channel, 20 feet deep east of Burlington Island. Rivers and Harbors 
Committee Doc. 66, 
74th Cong., Ist sess.' 
A cross channel 8 feet deep, opposite Delanco, N.J. Rivers and Harbors 
Committee Doc. 90, 
74th Cong., 2d sess. 
Anchorage at mouth of Biles Creek H. Doc. 679, 79th 
Cong., 2d sess. 
A channel 40 feet deep and 400 feet wide between Allegheny Ave., Philadelphia, Pa., H. Doc. 358, 83d 
and upstream end of Newbold Island, thence 35 feet deep to Trenton Marine Cong., 2d sess.' 
Terminal and turning basin to 800 feet wide. Relocate channel at railroad 
bridge at Delair and suitably reconstruct bridge. Construct necessary bank 
protection works; and eliminate authorized anchorage near mouth of 
Biles Creek, Pa. 
3-21

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 3-B (continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
DELAWARE RIVER, PA., N.J., AND DEL., PHILADELPHIA TO THE SEA 
June 25, 1910 
July 3, 1930 
Aug. 30, 19353 
June 20, 19384 
Mar. 2, 19455 
Mar. 2, 1945s 
Mar. 2 1945s 
Sept. 3, 1954 
July 3, 1958 
(See Section 5 of Text) 
Channel 35 feet deep from Allegheny Ave., Philadelphia, Pa., to Delaware Bay. 
Anchorages 35 feet deep at Port Richmond and Mantua Creek, a 30 foot 
anchorage at Gloucester, N.J., and extend 1,000 foot channel in Philadelphia 
Harbor to Horseshoe Bend. 
An anchorage 35 feet deep at Marcus Hook, Pa. 
A channel 37 feet deep from Philadelphia - Camden Bridge to Navy Yard, 
thence 40 feet deep to deep water in Delaware Bay. 
A 37-foot depth channel from Allegheny Ave., Philadelphia, Pa., to 
Philadelphia - Camden Bridge and in anchorage at Port Richmond. 
A 37-foot depth in an enlargement of anchorage near Mantua Creek and 
Marcus Hook. 
Maintain enlarged channel opposite Philadelphia Navy Yard. 
A channel from Allegheny Ave., to Naval Base 40 feet deep, 400 feet wide along 
west side of channel through Philadelphia Harbor and 500 feet wide through 
Horseshoe Bend. 
Anchorages at Reedy Point, Deepwater Point, Marcus Hook, and Mantua 
Creek 40 feet deep and 2,300 feet wide with mean lengths of 8,000, 5,200, 
13,650 and 11,500 feet respectively. 
H. Doc. 733, 61st Cong., 
2d sess. 
H. Doc. 304, 71st Cong., 
2d sess.' 
Rivers and Harbors 
Committee Doc. 5, 73d 
Cong., 1st sess. 
S. Doc. 159, 75th Cong., 
3d sess.' 
H. Doc. 580, 76th Cong., 
3d sess.' 
H. Doc. 340, 77th Cong., 
1st sess.' 
Specified in Act. 
H. Doc. 358, 83d Cong., 
2d sess.' 
H. Doc. 185, 85th Cong., 
1st sess. 
Aug. 26, 1937 
Mar. 2, 1945 
July 25, 1912 
Aug. 30, 1935 
Mar. 2, 1945 
Aug. 30, 1935 
Aug. 7, 1939 
Sept. 3, 1954 
INDIAN RIVER INLET AND BAY, DEL. (See Section 8 of Text) 
A 15-foot inlet channel, steel and stone jetties, 6 foot channel from end of inlet Rivers and Harbors 
channel to deep water in the bay and authority to modify interior inlet channel. Committee Doc. 41, 
75th Cong., 1st sess. 
A 9-foot channel from inlet to Old Landing, including basin, and 4-foot channel H. Doc. 330, 76th 
to highway bridge at Millsboro. Cong., 1st sess.' 
INLAND WATERWAY, REHOBOTH BAY TO DELAWARE BAY, DEL. 
(See Section 9 of Text) 
For a 6-foot depth canal to connect Rehoboth Bay and Delaware Bay. H. Doc. 823, 60th Cong., 
1st sess. and Rivers and 
1 Harbors Committee Doc. 
51,61st Cong., 3d sess. 
For a 6-foot depth entrance near Lewes, for jetties, for widening the canal from Rivers and Harbors 
Broadkill River to Lewes, and basin. Committee Doc. 56, 
75th Cong., 1st sess.' 
For a 10-foot depth from Delaware Bay to Lewes and in basin, and for H. Doc. 344, 77th Cong., 
extending jetties.6 1st sess.' 
INLAND WATERWAY FROM DELAWARE RIVER TO CHESAPEAKE 
BAY, DEL. AND MD. (See Section 10 of Text) 
A sea level channel 27 feet deep, 250 feet wide from Delaware River to Elk H. Doc. 201, 72d Cong., 
River and 400 feet wide down Elk River and Chesapeake Bay to deep water at 1st sess. and Rivers and 
or near Pooles Island; alter existing bridges over canal; enlarge Delaware City Harbors Committee 
Branch Channel to 8 feet deep and 50 feet wide, with a basin same depth, and Docs. 18 and 24, 73d 
revetment of both banks east of Fifth Street; enlarge anchorage and mooring Cong., 2d sess.' 
basin in Back Creek to 400 feet wide, 1,000 feet long and 12 feet deep; extend 
jetties at Reedy Point; and construct bulkheads. 
Construct a 4-lane high-level fixed highway bridge at or near St. Georges. Public Law 310, 76th 
Cong., 1st sess. 
A channel 35 feet deep and 450 feet wide from Delaware River through Elk S. Doc. 123, 83d Cong., 
River and Chesapeake Bay at water of that depth in the bay, including a cutoff 2d sess.' 
at Penn Central Railroad crossing, with a minimum radius of curvature of 
7,000 feet at bends; a high level fixed railroad bridge over cutoff; high level 
fixed highway bridge at Reedy Point and Summit; and an anchorage in Elk 
River 35 feet deep and 1,200 feet wide, averaging 3,700 feet long. 
3-22

PHILADELPHIA, PA. DISTRICT 
TABLE 3-B (continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
July 3, 1930 
Aug. 30, 1935 
Mar. 2, 1945 
Aug. 8, 1917 
July 3, 1930 
July 24, 1946 
June 3, 1896 
July 25, 1912 
Sept. 22, 1922 
Mar. 3, 1925 
July 3, 1930 
Aug. 30, 19358 
Oct. 17, 1940 
July 14, 1960 
MANASQUAN RIVER, N.J. (See Section 11 of Text) 
Channel 8 feet deep and provision of works designed to secure channel. 
Widening channel on northerly side. 
Deepening channel to 12 and 14 feet, 10 and 12 foot anchorages.7 
SCHUYLKILL RIVER, PA. (See Section 16 of Text) 
Depths of 35 feet from mouth to Girard Point, thence 30 feet, 26 feet, and 22 
feet to University Avenue Bridge, Philadelphia. 
A depth of 30 feet instead of 35 feet between the mouth and the conditional 
restoration and maintenance of the channel below Passyunk Ave., by the 
United States. 
A depth of 33 feet from the channel in Delaware River to Passyunk Ave., 
restoration of the project channel dimensions between Passyunk Ave., and 
University Ave., and full maintenance of the entire project. 
WILMINGTON HARBOR, DEL. (See Section 18 of Text) 
Depths of 21, 10, and 7 feet and jetties. 
Purchase or construct a dredge and auxiliaries including a wharf and depot, and 
maintenance of project. 
Entrance channel and basin with 25-foot depth and construction by local 
interests of new south jetty. 
A 30-foot depth between Delaware River and Lobdell Canal and modification 
or removal of a portion of north jetty. 
Completion of new south jetty by the United States; subject to provision that 
city of Wilmington reimburse the United States for cost, without interest, of 
any part of structure that may subsequently be occupied and utilized for city 
activities. 
Permit temporary occupancy by city of Wilmington of any part of south jetty 
for city activities under revocable license, provided occupied portion of jetty is 
properly maintained without expense to the United States. 
A 35-foot depth between Delaware River ship channel and Lobdell Canal 
H. Doc. 482, 70th Cong., 
2d sess. 
Senate Committee Doc., 
74th Cong., I1st sess. 
H. Doc. 356, 77th Cong., 
Ist sess.' 
H. Doc. 1270, 64th 
Cong., 1st sess. 
Rivers and Harbors 
Committee Doc. 40, 
71st Cong., 2d sess.' 
H. Doc. 699, 79th Cong., 
2d sess.' 
H. Doc. 66, 54th Cong., 
Ist sess. 
Annual Report, 1896, 
p. 973; 
Annual Report, 1897, 
p. 1250.' 
H. Doc. 359, 62d Cong., 
2d sess. 
H. Doc. 114, 67th Cong., 
1st sess. and S. 
Committee Print, 68th 
Cong., Ist sess. 
Rivers and Harbors 
Committee Doc. 20, 
71st Cong., 2d sess. 
Rivers and Harbors 
Committee Doc. 32, 
73d Cong., 2d sess. 
H. Doc. 658, 76th Cong., 
3d sess. 
S. Doc. 88, 86th Cong., 
including turning basin of same depth, opposite Wilmington Marine Terminal, 2d sess. 
200 feet wide, 2,900 feet long on north side of channel, and 2,000 feet long on 
north side of basin. 
1. Contains latest published maps. 
2. Also Public Works Administration, September 6, 1933, and 
Emergency Relief Administration, May 28, 1935. 
3. Also Public Works Administration, September 6, 1933. 
4. Channel 37 feet deep and 600 feet wide from Naval Base to 
Philadelphia-Camden Bridge, deferred for restudy. 
5. Channel 37 feet deep and 600 feet wide from Philadelphia- 
Camden Bridge to Allegheny Avenue, deferred for restudy. 
6. Extension of jetties considered to be active. 
7. The 10 and 12 foot anchorages are considered inactive. 
8. Also May 28, 1935, under Emergency Relief Administration. 
3-23

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 3-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to September 30, 1983 
Full Report 
See Annual Operation and 
Completed Projects Status Report For Construction Maintenance 
Absecon Creek, N.J.' COMPLETED 1969 11,935 167,682* 
Appoquinimink River, Del. COMPLETED 1931 36,973 41,270 
Big Timber Creek, N.J.' COMPLETED 1962 58,6652 53,986* 
Broadkill River, Del. COMPLETED 1976 68,228 243,641 
Cedar Creek, Sussex City, Del. COMPLETED - 256,100 - 
Cooper River, N.J.' COMPLETED 1962 33,102 379,244* 
Delaware River at Camden, N.J. COMPLETED 1982 464,906 362,79912 
Delaware River, Pennsville, N.J. COMPLETED - 254,897 - 
Double Creek, N.J.' COMPLETED 1912 7,800 -5 
Harbor of Refuge COMPLETED 1982 5,162,23013 l,138,36314 
Inland Waterway from Chincoteague 
Bay to Delaware Bay COMPLETED 1981 168,41218 98,36019 
Little River, Del. COMPLETED 1980 12,016 288,310 
Mantua Creek, N.J. COMPLETED 1966 169,687K 339,340* 
Maurice River, N.J. 1948 -- 
Delaware Bay to Millville fixed bridge COMPLETED - 143,984"o 137,050 
Mispillion River, Del. COMPLETED 1982 377,84823 1,241,62924 
**Neshaminy State Park Harbor COMPLETED 1968 128,20321 54,601 
Oldmans Creek, N.J. COMPLETED 1941 31,188 32,125 
**Pepper Creek, Del.' COMPLETED 1965 138,09422 1,797* 
Racoon Creek, N.J. COMPLETED 1981 83,66520 341,734 
St. Jones River, Del. 1961 - - 
Delaware Bay to Lebanon'," COMPLETED - 207,102 66,093 
Jetties and new entrance at mouth9 - - - 
Schuylkill River above Fairmount Dam, Pa.' COMPLETED 1955 4,291,810 -5 
Smyrna River, Del. 1949 - - 
Delaware River to Wharf at Smyrna Landing's COMPLETED - 198,844 197,327 
Wharf at Smyrna Landing to fixed bridge' SEE TABLE 3-G - - - 
Toms River, N.J. 1950 - - 
Channel 5 feet deep' COMPLETED - 10,050 33,311 
Channel 12 feet deep' SEE TABLE 3-G - - - 
Tuckerton Creek, N.J. COMPLETED 1972 60,242 623,917* 
Waterway from Indian River Inlet to 
Rehoboth Bay, Del. COMPLETED 1981 90,908 241,497 
Woodbury Creek, N.J.' COMPLETED 1940 27,09316 56,474 
For Last Cost to September 30, 1983 
Full Report 
See Annual Operation and 
Inactive Projects Status Report For Construction Maintenance 
Alloway Creek, N.J.' INACTIVE 1931 21,398 35,761 
Aquatic Plant Control 1975 87,594 - 
Chester River, Pa.3 INACTIVE 1931 6,000 1,139 
Dennis Creek, N.J.' INACTIVE 1897 4,701 - 
Goshen Creek, N.J.' INACTIVE 1905 15,359 870 
Ice Harbor at Marcus Hook, Pa.'4 INACTIVE 1928 208,964 14,336 
Ice Harbor at New Castle, Del. 1.6 INACTIVE 1898 224,704 - 
Leipsic River, Del.' INACTIVE 1931 36,956 32,345 
Little Egg Harbor, N.J. '4 INACTIVE -7 15,048 - 
Maurice River, N.J. 1948 
Channel 8 feet deep, Delaware Bay to mouth INACTIVE - - 
3-24

PHILADELPHIA, PA. DISTRICT 
TABLE 3-C OTHER AUTHORIZED NAVIGATION PROJECTS (Cont'd.) 
For Last Cost to September 30, 1983 
Full Report 
See Annual Operation and 
Deferred Projects Status Report For Construction Maintenance 
St. Jones River, Del. 1961 - - 
Delaware Bay to Lebanon," - 207,102 66,093 
Jetties and new entrance at mouth9 DEFERRED - - - 
I. Completed. 
2. Excludes $50,000 contributed funds expended for new work. 
3. Includes $6,000 new work and $63 maintenance funds expended 
on previous projects. 
4. Abandonment recommended in House Document 467, 69th 
Congress, 1st Session. 
5. Maintenance assumed by local interests. 
6. Harbor not now required by commerce. 
7. Last appropriation for project was in 1852. No information is at 
hand relative to work done. 
8. Includes $3,000 for new work for previous projects. 
9. Deferred. 
10. Includes $43,000 new work funds expended on previous 
projects. 
II. Includes $54,590 new work and $28,935 maintenance funds 
expended on previous projects. 
12. Excludes $15,000 contributed funds. 
13. Includes $2,749,452 for new work for previous projects. 
14. Excludes $1,089 for reconnaissance and condition surveys, fiscal 
year 1963. 
15. Includes $55,085 new work and $22,723 maintenance funds 
expended on previous projects. 
16. Includes $2,950 new work funds expended on previous projects. 
18. Entire amount expended on previous project repealed in 1905. 
19. Excludes $2,000 contributed funds and includes $25,330 for 
maintenance for previous projects. 
20. Includes $757 new work funds expended on previous projects. 
21. Excludes $327,957 contributed funds allotted expended for new 
work. 
22. Excludes $38,988 Non-Federal Funds. 
23. Includes $148,798 for new work on previous projects. 
24. Includes $61,172 for maintenance on previous projects. 
*Operation and maintenance figure includes cost incurred for preparation of environmental impact statements. 
**Projects authorized by the Chief of Engineers. 
3-25

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 3-D OTHER AUTHORIZED BEACH EROSION CONTROL PROJECTS 
For Last Cost to September 30, 1983 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Atlantic City, N.J. INACTIVE 1972 2,083,289 -' 
Ocean City, N.J. INACTIVE 1969 395,8313 1-' 
Stone Harbor, N.J. INACTIVE 1961 - -1 
Barnegat Light, N.J. DEFERRED 1964 70,908 -' 
Cape May City, N.J. DEFERRED 1961 22,9572 -I 
Long Beach Island, N.J. DEFERRED 1964 40,665 -' 
North Wildwood, N.J. DEFERRED 1961 - - 
Rehoboth Beach to Indian River Inlet, Del.4 1965 326,116 -I 
Ventnor, Margate and Longport, N.J. DEFERRED 1961 - - 
1. Operation and maintenance required by law to be assumed by 3. Excludes cost of $1,146,325 to local interests and $272,766 
local interests: Federal participation expended under Public Works Acceleration 
2. Excludes $58.585 Accelerated Public Works funds expended for Program for Extension of five existing groins completed 11 May 
extension to two groins. 1964. 
4. This project was included in and modified by the Delaware Coast 
project. 
TABLE 3-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to September 30, 1983 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Allentown, Lehigh River, Pa. COMPLETED 1961 1,615,581 -I 
Bethlehem, Lehigh River, Pa. COMPLETED 1966 4,520,995 - 
Mt. Holly, N.J. COMPLETED 1946 283,655 -' 
Trexler Lake, Pa.3 INACTIVE 1981 
Aquashicola Reservoir, Pa. 2 DEFERRED 1963 - - 
Maiden Creek Reservoir, Pa.2 DEFERRED 1963 - -1 
1. Maintenance assumed by local interest as required by authorizing 
project. 
2. New project deferred. 
3. $1,316,464 expended for preconstruction planning only. 
3-26

PHILADELPHIA, PA. DISTRICT 
TABLE 3-F MULTIPURPOSE PROJECT INCLUDING POWER 
For Last Cost to September 30, 1983 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Tocks Island Lake, Pa., N.J. and N.Y. 2 1979 65,106,260' - 
Tocks Island (Relocation of U.S. Route 
209 only) Pa. 2 1979 195,223 - 
I. Includes $3,489,088 for AE&D. 2. National Parks and Recreation Act of 1978 terminated Corps' 
authority to proceed with the project. Legislation would be 
required to proceed with the project. 
TABLE 3-G DEAUTHORIZED PROJECTS 
For Last Full Date Federal Contributed 
Report See Annual And Funds Funds 
Navigation Projects Report For Authority Expended Expended 
3 Oct 78 
Appoquinmink River, Del' 1931 HD 95-351 $ 78,243 - 
5 Aug 77 
Delaware River, Mouth of Neversink 1917 HD 94-192 - - 
2 Nov 79 
Maurice River, N.J. 1948 Section 12 PL 93-251 
Millville fixed bridge to upper end of project2 
2 Nov 79 
Oldmans Creek, N.J.3 1941 Section 12 PL 93-251 $ 63,313 - 
2 Nov 79 
Rancocas River, N.J.4 1942 Section 12 PL 93-251 $ 57,590 - 
2 Nov 79 
Smyrna River, Del.5 1949 HD 95-157 $396,169 - 
Wharf at Smyrna Landing to fixed bridge 
2 Nov 79 
Toms River, N.J.6 1950 Section 12 PL 93-251 $ 43,361 - 
Channel 12 feet deep 
Flood Control Projects 
2 Nov 79 
Lehigh River at Bethlehem, Pa.7 1966 Section 12 PL 93-251 $4,520,995 - 
1. Includes $36,973 new work, and $41,270 for maintenance. 
2. There is no need now for this portion of the project. 
3. Includes $31,188 new work, and $32,125 for maintenance. 
4. Includes $44,500 new work, and $13,090 for maintenance. 
5. Includes $143,759 new work, $55,085 new work, previous project, 
$174,602 for maintenance, and $22,723 maintenance, previous 
project. 
6. Includes $10,050 new work, and $33,311 for maintenance. 
7. Maintenance assumed by local interest. 
3-27

BALTIMORE, MD DISTRICT* 
This district comprises the watershed of Susquehanna 
River and its tributaries from headwaters in south central 
New York State through central Pennsylvania to its 
mouth in Chesapeake Bay; watershed of the Potomac 
River and its tributaries from headwaters in Maryland, 
eastern West Virginia, and northern Virginia to its mouth 
in Chesapeake Bay; District of Columbia; and southwestern 
portion of Delaware. It includes that portion of 
Chesapeake Bay and its tributaries north of Smith Point, 
MD, on western shore of the bay, and includes that portion 
of Maryland between Chesapeake Bay and Atlantic 
Ocean. 
IMPROVEMENTS 
Navigation Page 
1. Baltimore Harbor and 
Channels, MD and VA ............... 4-3 
2. Baltimore Harbor, MD, 
Collection and Removal of Drift ......... 4-4 
3. Chester River, MD .................... 4-4 
4. Fishing Creek, MD ................... 4-4 
5. Honga River and Tar Bay 
(Barren Island Gaps), MD ............. 4-5 
6. Little Wicomico River, VA............... 4-5 
7. Lowes Wharf, MD .................... 4-5 
8. Muddy Hook/Tyler Cove, MD ........... 4-5 
9. Nanticoke River at Bivalve, MD .......... 4-6 
10. Nanticoke River Including 
Northwest Fork, MD ................. 4-6 
11. Northeast River, MD .................. 4-7 
12. Ocean City Harbor and Inlet and 
Sinepuxent Bay, MD................. 4-7 
13. Pocomoke River, MD ................... 4-7 
14. Potomac River at Mt. Vernon, VA ......... 4-8 
15. Potomac River below 
W ashington, DC .................... 4-8 
16. Potomac and Anacostia Rivers, DC, 
Collection and Removalof Drift ........ 4-8 
17. Prevention of Obstructions & 
Injurious Deposits, 
Baltimore Harbor, MD ............... 4-9 
18. Rhodes Point to Tylerton, MD........... 4-9 
19. St. George Creek, MD..................4-9 
20. St. Patricks Creek, MD................. 4-10 
21. Tilghman Island Harbor, MD ............ 4-10 
22. Warwick River, MD .................. 4-10 
23. Washington Harbor, DC ............... 4-10 
24. Wicomico River, MD .................. 4-11 
25. Reconnaissance and Condition Surveys ..... 4-11 
26. Navigation work under special 
authorization ............. ........... 4-11 
Beach Erosion Control Page 
27. Colonial Beach, VA ..................... 4-12 
Flood Control 
28. Black Walnut Point, MD ................. 4-12 
29. Bloomington Lake, MD and WV .......... 4-12 
30. Bull Run, PA ........................ 4-13 
31. Cumberland, MD, and Ridgeley, WV ....... 4-13 
32. Fourmile Run, VA .................... 4-13 
33. Lackawanna River Basin, PA............. 4-14 
33A. Aylesworth Creek Lake, PA ............. 4-14 
34. Latta Brook Rd., NY .................. 4-14 
35. Raystown Lake, Raystown Branch, 
Juniata River, PA ................... 4-14 
36. Southern New York Flood 
Control Projects ................... . 4-14 
36A. Addison, NY.......................... 4-15 
36B. AlmondLake,NY..................... 4-15 
36C. Arkport Dam, NY .................. .4-15 
36D. Avoca,NY .......................... 4-15 
36E. Binghamton,NY ..................... 4-15 
36F. Canisteo, NY ......................... 4-16 
36G. Corning,NY ......................... 4-16 
36H. East Sidney Lake, NY ................. 4-17 
361. Elmira,NY ........................... 4-17 
36J. Hornell,NY .......................... 4-17 
36K. Lisle,NY............................. 4-18 
36L. Oxford, NY .......................... 4-18 
36M. Whitney Point Lake, NY ................ 4-18 
36N. Whitney Point Village, NY .............. 4-18 
37. Stillwater Lake, Lackawanna River, PA .... 4-18 
38. Susquehanna River Flood Control 
Project,NYandPA.................. 4-19 
38A. Cowanesque Lake, PA ................. 4-19 
38B. Tioga-Hammond Lakes, PA ............. 4-19 
39. West Branch of Susquehanna River, PA .... 4-20 
4-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Flood Control (Cont'd) Page 
39A. Alvin R. Bush Dam, PA ................. 4-20 
39B. CurwensvilleLake, PA.................. 4-20 
39C. Foster Joseph Sayers Dam, PA ........... 4-20 
40. Wyoming Valley, PA ................... 4-20 
41. York Indian Rock Dam, PA .............. 4-21 
42. Inspection of Completed Flood 
Control Projects ..................... 4-21 
43. Scheduling Flood Control Reservoir 
Operations ....................... 4-21 
44. Flood Control Work under Special 
Authorization ..................... 4-21 
Water Supply 
45. Potomac Estuary Pilot Water 
Treatment Plant, DC..................4-21 
46. Washington Aqueduct ................. 4-22 
General Investigations Page 
47. Surveys.............................4-22 
48. Collection and Study of Basic Data ........ 4-22 
General Investigations (Cont'd) Page 
49. Continuation of Planning 
and Engineering .................... 4-22 
50. Advanced Engineering 
and Design ........................ 4-23 
Tables 
Table 4-A Cost and Financial Statement ......... 4-24 
Table 4-B Authorizing Legislation.............. 4-30 
Table 4-C Other Authorized 
Navigation Projects ............... 4-36 
Table 4-D Other Authorized Beach Erosion 
Control Projects .................. 4-38 
Table 4-E Other Authorized Flood 
Control Projects .................. 4-38 
Table 4-F Not Applicable 
Table 4-G Deauthorized Projects ............... 4-39 
Table 4-H Reconnaissance and 
Condition Surveys ................ 4-40 
Table 4-I Inspection of 
Completed Projects ............... 4-41 
4-2

BALTIMORE, MD DISTRICT 
Navigation 
1. BALTIMORE HARBOR AND 
CHANNELS, MD AND VA 
Location. Baltimore Harbor is at the head of the 
navigable portion of Patapsco River about 12 miles from 
Chesapeake Bay. The Patapsco River rises near the town 
of Westminster in Carroll County, MD, and flows 
generally southeast for about 65 miles to enter 
Chesapeake Bay. (See National Ocean Survey Chart 
12278.) 
Existing Project. 
a. A uniform main channel depth of 50 feet between 
Cape Charles, VA, and Fort McHenry at Baltimore, MD, 
with dimensions as follows: (1) Cape Henry Channel: 50 
feet deep and 1,000 feet wide from the 50-foot depth 
curve in the Atlantic Ocean to that depth in Chesapeake 
Bay, a distance of 2.3 miles; (2) York Spit Channel: 50 feet 
deep and 1,000 feet wide connecting the 50-foot depth 
curves in Chesapeake Bay near York Spit, a distance of 
18.2 miles; (3) Rappahannock Shoal Channel: 50 feet deep 
and 1,000 feet wide connecting the 50-foot depth curves 
in the Chesapeake Bay opposite the Rappahannock 
River, a distance of 8.9 miles; and (4) Baltimore Harbor 
Approach Channels: 50 feet deep and generally 800 feet 
wide, widened at the approach and bends, from the 
50-foot depth curve in Chesapeake Bay opposite the 
mouth of the Magothy River to Fort McHenry on the 
Patapsco River, a distance of 19.9 miles. 
b. Branch channels with dimensions as follows: (1) 
Connecting Channel to Chesapeake and Delaware Canal 
Approach Channel: 35 feet deep, 600 feet wide, and 13.0 
miles long from the Cutoff-Brewerton Angle in the main 
channel to the 35-foot depth curves in the natural channel 
on the east side of Chesapeake Bay which is part of the 
inland waterway from Delaware River to Chesapeake 
Bay. The channel includes the Brewerton Extension and 
Swan Point and Tolchester Sections; (2) Curtis Bay: 50 
feet deep, 600 feet wide, and 2.3 miles long from the main 
channel to and including a turning basin at the head of 
Curtis Bay; (3) Curtis Creek: (a) a channel, 35 feet deep 
and generally 200 feet wide, from the 50-foot channel in 
Curtis Bay to 750 feet downstream of the Pennington 
Avenue Bridge; (b) a channel, 22 feet deep and generally 
200 feet wide, from the 35-foot channel to and along the 
marginal wharf of the Curtis Bay Ordnance Depot; (c) an 
irregular shaped 3-acre basin, with a depth of 18 feet, adjacent 
to the head of the 22-foot channel; (d) a basin, 15 
feet deep and 450 feet wide, from the end of the 22-foot 
channel to the end of the marginal wharf; and (e) a 
channel, 22 feet deep and 200 feet wide, from the 22-foot 
channel south of the Baltimore and Ohio Railroad Bridge 
to the vicinity of Arundel Cove, a distance of 2,800 feet, 
thence 100 feet wide in Arundel Cove for a distance of 
2,100 feet, with an anchorage basin, 700 feet square, adjacent 
to the channel and southwest of the wharf of the 
Coast Guard Depot at Curtis Bay; (4) Middle Branch: (a) 
Ferry Bar East Section: a channel, 42 feet deep and 600 
feet wide, from the main channel at Fort McHenry to 
Ferry Bar, a distance of 1.4 miles; (b) Ferry Bar West Section: 
a channel, 35 feet deep and 400 feet wide, from the 
Ferry Bar East Section to Ferry Bar, a distance of 0.8 
mile; (c) Spring Garden Section: a channel, 27 feet deep 
and 250 feet wide, from Ferry Bar to and including a turning 
and anchorage basin immediately below the Western 
Maryland Railway Bridge, a distance of 1.0 mile; and (5) 
Northwest Branch: Federal maintenance of 39-foot or 
35-foot deep channels after either depth has been provided 
by local interests: (a) East Channel: a channel, 49 
feet deep, 600 feet wide, and 1.0 mile long with a turning 
basin at the head of the channel from that depth existing 
at the time of construction; and (b) West Channel: a 
channel, 40 feet deep, 600 feet wide, and 1.2 miles long 
with a turning basin at the head of the channel from that 
depth existing at the time of construction. 
c. The following anchorages: (1) Quarantine Anchorage: 
35 feet deep, 3,500 feet long, and 600 feet wide; (2) 
Riverview Anchorage No. 2:30 feet deep, 2,400 feet long, 
and 1,300 feet wide; (3) Riverview Anchorage No. 1: 35 
feet deep, 4,500 feet long, and 1,500 feet wide; and (4) Fort 
McHenry Anchorage: 35 feet deep, 3,500 feet long, and 
400 feet wide. 
The mean range of tide is 2.8 feet at the Cape Henry 
Channel, 2.3 feet at the York Spit Channel, 1.4 feet at the 
Rappahannock Shoal Channel, 0.8 foot at the Craighill 
Entrance, 0.9 foot in the Cutoff Section, 1.1 feet at Fort 
McHenry, and 1.2 feet at Pooles Island in the upper 
Chesapeake Bay. Depths refer to mean low water. 
Estimated cost for new work is $412,931,000 which 
includes: $8,330,000 for completed work through the 
River and Harbor Act of 1945; $49,601,000 (October 
1983 prices) for work authorized by the River and Harbor 
Act of 1958 of which $45,301,000 is Corps of Engineers, 
$60,000 is U.S. Coast Guard and $4,240,000 is non- 
Federal; and $355,000,000 (October 1983 prices) for work 
authorized by the River and Harbor Act of 1970, of which 
$180,000 is U.S. Coast Guard, and $354,820,000 is Corps 
of Engineers and non-Federal. 
Widening 35-foot depth from Port Covington Channel 
from 150 to 400 feet to Ferry Bar, widening 27-foot depth 
channel from 150 to 250 feet to Hanover Street Bridge, 
and providing a channel 27 feet deep by 250 feet wide to 
Western Maryland Railway Bridge with an anchorage 
and turning basin at upper end is considered inactive and 
is excluded from the foregoing estimate. Estimated cost 
(1954) of this portion is $1,603,000. 
Local cooperations. Fully complied with for improvements 
authorized under River and Harbor Act of 
1945 and prior acts. Local interests have furnished 
assurances that terms of local cooperation under the 
River and Harbor Acts of 1958 and 1970 will be complied 
with. See page 4-3 of the 1982 Annual Report for requirements 
under these two Acts. 
Terminal facilities. The Port of Baltimore has 45 miles 
of waterfront of which 25 miles are industrially developed. 
There are 94 covered and open overseas piers for 
the loading and discharging of 173 ships, providing 84 
general cargo, 65 specialized cargo, and 24 public bulk 
cargo berths. The existing ground storage is equivalent 
to 53,700 railroad cars of cargo. There are 31 public 
general merchandise warehouses, with 4.9 million square 
feet of storage space and 4.7 million cubic feet of cold 
storage space. Eight ship-building, ship repair, and ship 
4-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
dismantling yards are available for handling up to 90 
vessels. The three grain elevators in the port have a 
capacity of about 13 million bushels. Latest description 
of terminal facilities is in "Port Series No. 10 (revised 
1978)" on Port of Baltimore, MD, (issued by Board of 
Engineers for Rivers and Harbors). 
Operations and results during fiscal year. Maintenance 
dredging under the River and Harbor Act of 
1958 is discussed below. Preconstruction planning under 
the River and Harbor Act of 1970 began October 1976 
and continued in FY 1982. 
Maintenance, Baltimore District: Condition surveys of 
the project channel were made. Maintenance dredging of 
the outbound side of the Craighill Entrance and fuel 
channel widths of the Craighill Channel, Angle, and 
Upper Range, by contract, began on December 14, 1982 
and was completed on April 9, 1983. A total of 1,498,730 
cubic yards of material was removed and deposited in the 
Patapsco River Mouth, Eastern Extension open water 
disposal area. 
Maintenance, Norfolk District: Maintenance dredging 
of the Cape Henry Channel, by contract, began on 
September 22, 1982 and was completed on November 14, 
1982. A total of 389, 128 credited cubic yards of material 
was removed and deposited in the Dam Neck open water 
disposal area. 
2. BALTIMORE HARBOR, MD 
COLLECTION AND REMOVAL 
OF DRIFT 
Location. Project applies to Baltimore Harbor, MD, 
and its tributaries. 
Existing project. Provides for collection and removal 
of drift from Baltimore Harbor and its tributary waters, 
and authorizes the Secretary of the Army to allot such 
amounts as may be necessary for work from appropriations 
for maintenance and improvement of existing river 
and harbor works or other available appropriations, and 
that this work shall be carried as a separate and distinct 
project. It is wholly a work of maintenance. Purpose of 
work is to afford relief from variable conditions of 
obstruction. 
Local cooperation. None required. 
Terminal facilities. See Secton 1 of this text. 
Operations and results during fiscal year. Maintenance: 
Operations, by hired labor, consisted of collection 
and disposal of 31,320 cubic feet of driftwood, ranging 
from small blocks up to timbers of large dimensions. 
3. CHESTER RIVER, MD 
Location. Rises in Kent County, DE, flows 50 miles 
generally southwesterly and empties into the Chesapeake 
Bay. Kent Island Narrows is a passage connecting 
Chester River and Eastern Bay. Wells Cove is an indentation 
on easterly side of Kent Island Narrows about 0.4 
mile south of the highway bridge crossing the Narrows. 
(See Coast and Geodetic Survey Charts 548 and 1226.) 
Previous project. For details see page 262 of the 1960 
Annual Report. 
Existing project. Provides for a channel 6 feet deep at 
mean low water and 60 feet wide from Crumpton to Jones 
Landing, section included in project is about 5.5 miles 
long with the lower end of the section being about 37 
miles above mouth of river; for a channel 7 feet deep at 
mean low water and 75 feet wide from Chester River to 
Eastern Bay through Kent Island Narrows; and a channel 
7 feet deep at mean low water and 75 feet wide extending 
from 7-foot deep curve in Kent Island Narrows 800 
feet into Wells Cove with a basin of same depth and 300 
feet square at head of channel. Mean range of tide is 2.4 
feet. Cost of new work for completed project was $32,454, 
exclusive of amounts expended on previous projects. 
Widening 7-foot deep channel from 75 to 100 feet from 
Chester River to Eastern Bay through Kent Island 
Narrows is considered inactive and is excluded from the 
foregoing estimate. 
Local cooperation. Fully complied with except local interests 
are to furnish spoil disposal areas for future 
maintenance of Wells Cove section of the project. 
Terminal facilities. There are two bulkhead wharves on 
Chester River section. Facilities on the Kent Island 
Narrows section of the existing project consist of about 
10,000 linear feet of timber pile bulkheaded wharf. About 
1,350 linear feet of the wharf is owned and operated by 
the Queen Anne's County; the remainder is privately 
owned. The privately owned bulkheaded wharf is 
operated mostly by the 7 marinas located on the Narrows 
with the remainder being owned and operated by the 
seafood packing houses in the area. In addition, to the 
slips of the marinas, there are marine railways, launching 
ramps, and travel-lifts. All of these facilities are in good 
condition and are located adjacent to the proposed improvements. 
In Wells Cove there is a small wharf, a small 
marine railway, and a public landing. All facilities are 
privately owned except the public landing on Wells Cove. 
Facilities are considered adequate for existing commerce. 
Operations and results during fiscal year. Maintenance: 
Engineering and design work in connection with 
proposed maintenance dredging was accomplished. 
4. FISHING CREEK, MD 
Location. A narrow winding tidal stream which enters 
Chesapeake Bay from the west 56 miles south of Baltimore 
and about 26 miles south of Annapolis, MD. (See 
Coast and Geodetic Survey Chart 12266.) 
Existing project. A channel 7 feet deep with widths of 
100 and 60 feet from deep water in the Chesapeake Bay to 
an anchorage of same depth, 120 feet wide and 400 feet 
long, located in marsh 500 feet above mouth of creek, and 
twin stone jetties at entrance; north jetty is about 1,050 
feet long, and south jetty about 1,100 feet long. The mean 
range of tide is about 1 foot. Cost of new work for the completed 
project was $111,242. 
4-4

BALTIMORE, MD DISTRICT 
Local cooperation. Fully complied with except that 
local interests are to furnish spoil disposal areas as needed 
for future maintenance. 
Terminal facilities. Seven hundred feet of bulkhead 
wharf are available on the south side of the entrance 
channel running west from bay shore, and the U.S. Navy 
Department constructed a pile-and-timber wharf on west 
side of basin. 
Operations and results during fiscal year. Maintenance: 
Maintenance dredging of the project channel 
was completed on May 20, 1983. A total of 6,400 cubic 
yards of material was removed. 
5. HONGA RIVER & TAR BAY 
(BARREN ISLAND GAPS), MD 
Location. Honga River is a tidal estuary of Chesapeake 
Bay and penetrates Dorchester County on Eastern Shore 
of Maryland between Hooper Islands and the mainlands; 
Tar Bay lies between Barren Island and the mainland 
and Hooper Islands. Fishing Creek connects Tar Bay and 
Honga River. Back Creek is a branch of Honga River extending 
into Hooper Islands; the mouth is about 2 miles 
south of Fishing Creek. (See Coast and Geodetic Survey 
Chart 1224.) 
Existing project. Provides for a channel 60 feet wide 
and 7 feet deep at mean low water from the 7-foot contour 
in Chesapeake Bay, through Tar Bay and Fishing Creek 
to the 7-foot contour in Honga River, 25,300 feet long, 
and a channel in Back Creek 7 feet deep and 60 feet wide 
from the 7-foot depth curve in Honga River to a point 
near the head of Back Creek with a turning basin of the 
same depth 150 feet long and 200 feet wide at the head of 
channel, about 5,500 feet long. Mean range of tide is 
about 1.4 feet. Federal cost of new work for the completed 
project was $66,119. 
Local cooperation. Fully complied with except that 
local interests are to furnish spoil disposal areas for 
future maintenance as needed. 
Terminal facilities. Numerous small private wharves 
are scattered along Fishing Creek and Back Creek. A 
public wharf is on Fishing Creek. A public wharf, 4 oyster 
houses, and a marine railway are on Back Creek. Facilities 
are adequate for existing and reasonably prospective 
commerce. 
Operations and results during fiscal year. Maintenance: 
Maintenance dredging of the project channel 
was completed on October 18, 1982. A total of 139,000 
cubic yards of material was removed. 
6. LITTLE WICOMICO RIVER, VA 
Location. A tidal estuary 6 miles long in Northumberland 
County, VA, flowing southeasterly to Potomac 
River, which it enters on the right bank one-half mile 
upstream of its mouth and about 108 miles downstream 
from Washington, DC. (See Coast and Geodetic Survey 
Chart 12233.) 
Existing project. A channel 8 feet deep, 150 feet wide, 
and 4,800 feet long, extending from deep water in the 
Potomac River to deep water in the Little Wicomico 
River; two stone jetties, extending to the 8-foot contour 
in Potomac River; and bulkhead walls from the inner 
ends thereof extending sufficiently into Little Wicomico 
River to stabilize the dredged inner channel. Plane of 
reference is mean low water. Tidal ranges in Potomac 
River at the entrance are: Mean 1.2 feet; irregular, 2.5 
feet; and extreme, about 7 feet. Mean tidal range within 
the river is about 1 foot. Federal cost of new work for the 
completed project was $81,885, exclusive of $5,000 contributed 
by local interests. 
Local cooperation. Fully complied with. 
Terminal facilities. Two wharves open to the public 
and numerous small wharves and stagings for private 
use, an oyster shucking and packing plant, and a marine 
railway and boat-building yard. Facilities are considered 
adequate for present commerce. 
Operations and results during fiscal year. Maintenance: 
A contract for replacement of the south timber 
bulkhead was completed on November 10, 1982. 
7. LOWES WHARF, MD 
Location. Lowes Wharf is in Ferry Cove, also known as 
Haddaway Cove, a small indentation on the eastern 
shore of Chesapeake Bay about 6 miles north of the Choptank 
River and 13 miles west of Easton, MD. (See Coast 
and Geodetic Survey Chart 1225.) 
Existing project. Provides for a channel 60 feet wide 
and 7 feet deep at mean low water from the 7-foot depth 
curve in Ferry Cove to and including a basin of the same 
depth, 200 feet wide and 300 feet long on the south side of 
Lowes Wharf. The mean tidal range is 1.4 feet; however, 
greater fluctuations frequently result from prolonged or 
high winds. The cost of new work for the completed project 
was $21,000. 
Local cooperation. Fully complied with except that 
local interests are to furnish spoil disposal areas for 
future maintenance as needed. 
Terminal facilities. Lowes Wharf, a solid-fill pier, with 
a seafood house located on the outer end, is the only terminal 
facility in Ferry Cove. The pier is public and is open 
to watermen at all times. 
Operations and results during fiscal year. Maintenance: 
A contract was awarded on August 22, 1983 for 
maintenance dredging of the project. 
8. MUDDY HOOK/TYLER COVES, MD 
Location. Muddy Hook Cove is a small indentation 
about 0.7 mile south of Hoopersville on the east side of 
Middle Hooper Island. Middle Hooper Island is one of a 
chain of islands separating Honga River from Tar Bay 
and Chesapeake Bay on the Eastern Shore of Maryland. 
Tyler Cove is s small tidal indentation on the north side of 
Fishing Creek which separates Hooper Islands from the 
mainland. (See Coast and Geodetic Survey Chart 12230.) 
4-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Existing project. An entrance channel 60 feet wide and 
6 feet deep from that depth in Honga River to and including 
an anchorage basin of the same depth, 160 feet 
wide and 400 feet long, in Muddy Hook Cove. Project 
also provides an entrance channel, 60 feet wide and 6 feet 
deep, from the existing channel in Fishing Creek (See 
Honga River and Tar Bay project) into Tyler Cove and includes 
an anchorage basin 200 feet wide, 250 feet long, 
and 6 feet deep. Federal cost of new work for the completed 
project was $61,917. Existing project was approved 
for accomplishment under general authority provided 
by section 107, River and Harbor Act of 1960. 
Local cooperation. Local interests must furnish lands, 
pay for dike construction and provide rights-of-way for 
new work and future maintenance; hold the United 
States free from damages; build and maintain a suitable 
public landing with adequate approaches thereto at each 
location; accomplish alterations, relocations, and 
removal, as required, of sewer, water supply, drainage 
and other utility facilities, and piers and stakes. 
Terminal facilities. Local interests have, under terms 
of local cooperation, provided a public landing at Tyler 
Cove. A few privately owned piers are on Muddy Hook 
Cove. Local interests provided a public landing at Muddy 
Hook Cove, in accordance with the terms of local cooperation. 
Operations and results during fiscal year. Maintenance: 
Maintenance dredging of Tyler Cove was completed 
on October 22, 1982. A total of 17,000 cubic yards 
of material was removed. A contract for maintenance 
dredging of Muddy Hook Cove was awarded on August 
22, 1983. The upland disposal area is under construction. 
9. NANTICOKE RIVER AT BIVALVE, MD 
Location. Bivalve is on the east bank of Nanticoke 
River, a tidal arm of Tangier Sound on the east side of 
Chesapeake Bay. It is 6 miles above the mouth of river 
and about 113 miles by water from Baltimore. Jacksons 
Gut is a slough through a marshland about one-quarter 
mile north of Bivalve. (See U.S. Coast and Geodetic 
Survey Chart 1224.) 
Existing project. Provides for a protected anchorage 
basin in Jacksons Gut 7 feet deep at mean low water, 150 
feet wide, and 350 feet long and an approach channel of 
like depth, 60 feet wide and about 1,400 feet long, extending 
from 7-foot depth in Nanticoke River, protected by 
twin rock jetties about 1,000 feet long extending from 
shore to 4-foot depth in river. Mean range of tide in vicinity 
of Bivalve is about 2.5 feet. 
Federal cost of new work for the completed project was 
$240,817. 
Portion of project which provides for extension of anchorage 
basin from 350 to 550 feet long is considered inactive 
and is excluded from foregoing costs. Cost of this 
portion last revised in 1958 was estimated to be $14,000. 
Local cooperation. Fully complied with except that 
local interests are to furnish spoil disposal areas as needed 
for future maintenance. 
Terminal facilities. Local interests have constructed a 
public marina in Jacksons Gut. Complete facilities are 
available for boat operators. The county has constructed 
a park adjacent to the project. 
Operations and results during fiscal year. Maintenance: 
Engineering and design work was accomplished 
in connection with proposed maintenance dredging. 
10. NANTICOKE RIVER (INCLUDING 
NORTHWEST FORK), DE & MD 
Location. Headwaters of Nanticoke River consist} of 
numerous branches rising mainly in the northern portion 
of Sussex County, DE. The river is about 50 miles long 
and flows southwesterly from its source to Tangier 
Sound. 
Northwest Fork is a branch of Nanticoke River which 
rises in Kent County, DE, and flows past Federalsburg, 
MD, generally southerly through Dorchester County, 
MD, to its junction with the main river opposite Riverton, 
MD. It is about 30 miles long. (See Coast and 
Geodetic Survey Chart 77.) 
Existing project. Nanticoke River: Channel 12 feet 
deep and 100 feet wide from the 12-foot depth curve in 
Tangier Sound to the highway bridge at Seaford, DE, 
with a turning basin at the upper end. Disjointed sections 
included in the project is about 4 miles long, extending 
over 32 miles of river; lower end of the first section of the 
project is about 8 miles above the mouth of the river. 
Mean range of tide is 3.4 feet, and the extreme tidal range 
is 4.3 feet. 
Northwest Fork: Dredging a channel 6 feet deep and 60 
feet wide at mean low water from upper Browns wharf to 
within one-half mile of the southern boundary of town of 
Federalsburg, with a turning basin at the upper end. Section 
included in the project is about 4 miles long, and its 
lower end is 11.75 miles above the mouth of the river. 
Mean range of tide is 2.6 feet. 
Local cooperation. Local interests must furnish spoil 
disposal areas for future maintenance and hold the 
United States free from damages. 
Terminal facilities. Waterfront at Seaford consists 
largely of unconnected pile-and-timber bulkhead 
wharves with earthfills. One public wharf is used as a 
launching ramp. Remaining wharves are privately owned. 
A rail siding extends along a considerable portion of 
waterfront and offers facilities for interchange of rail and 
water traffic. Existing terminals are reasonably adequate 
for present and prospective commerce. 
Terminal facilities on Northwest Fork are all privately 
owned and open to general public use. They consist of one 
solid bulkhead wharf of 80-foot frontage and 3 landings 
each with 60-foot frontages. Depths of water are from 2 
to 8 feet. Landings are log revetments backed by earthfill 
and are in poor condition. 
Operations and results during fiscal year. A maintenance 
dredging contract was awarded on July 14, 1983. 
The contract is 50 percent complete. 
4-6

BALTIMORE, MD DISTRICT 
11. NORTHEAST RIVER, MD 
Location. A tidal waterway extending southwestward 
5.5 miles from the junction of its branches in the town of 
North East to the head of Chesapeake Bay, 6 miles north 
of entrance to the Chesapeake and Delaware Canal. (See 
Coast and Geodetic Survey Chart 1226.) 
Existing project. Provides for a channel 60 feet wide 
and 7 feet deep at mean low water from that depth in river 
to foot of Church Street in the town of North East, enlarged 
at its upper end to form a basin 120 feet wide and 
300 feet long. Mean range of tide is 2.25 feet. 
Local cooperation. Fully complied with except that 
local interests are to furnish spoil disposal areas for 
future maintenance as required. 
Terminal facilities. There are a few lightly constructed 
landings for small boats scattered along the waterfront 
in the town of North East. There are two fish-packing 
plants, two marine railways, several bulkhead wharves, 
11 marinas, and a number of small boathouses along the 
length of the waterway. Facilities are considered adequate 
for existing commerce. 
Operations and results during fiscal year. Maintenance: 
A contract was awarded on September 1, 1983 
for maintenance dredging of the project channel. Upland 
disposal area is under construction. 
12. OCEAN CITY HARBOR AND 
INLET AND SINEPUXENT BAY, MD 
Location. Ocean city is on a barrier island between 
Sinepuxent Bay and Atlantic Ocean about 35 miles south 
of entrance to Delaware Bay. (See Coast and Geodetic 
Survey Chart 1220.) 
Existing project. This provides for an inlet channel 300 
feet wide and 16 feet deep from the 16-foot depth curve in 
Atlantic Ocean through the inlet to the channel in the 
Isle of Wight Bay, protected on the south side by a stone 
jetty with a top elevation of 8.8 feet above mean low 
water and a top width of 18 feet, and on the north side by 
a stone jetty with a top elevation of 9 feet above mean low 
water and a top width of generally 20 feet, thence generally 
200 feet wide and 16 feet deep to the project harbor; 
a depth of 14 feet and 150 feet wide to the head of the 
harbor, a length of approximately 3,400 feet; a channel 6 
feet deep and 150 feet wide in Sinepuxent Bay from the 
inlet to Green Point, and thence 100 feet wide in Chincoteague 
Bay; and for a channel 6 feet deep and 125 feet 
wide from the inlet channel to a point opposite North 
Eighth Street in Ocean City, thence 75 feet wide into the 
Isle of Wight Bay. Depths in the inlet channel and harbor 
refer to project datum. Depths in the bay channels refer 
to mean low water. 
The elevation of mean low water in the bays above 
mean low water in the ocean at Ocean City varies from 
about 0.8 foot in the vicinity of the inlet to 1.7 feet at their 
heads. The mean range of ocean tide is 3.4 feet. The extreme 
range is from 3 feet below mean low water to about 
3.5 feet above mean high water, a total of 9.9 feet. In the 
bays the mean range of tide varies from approximately 
2.5 feet at the inlet to 0.3 foot at their heads. Greater fluctuations 
are caused by prolonged high winds. Federal 
cost of new work for the completed project was 
$1,190,530, exclusive of $500,000 contributed by local interests 
and exclusive of $3,700,000 for rehabilitating the 
south jetty. 
Local cooperation. Fully complied with except local interests 
must furnish spoil disposal areas for future 
maintenance as needed. 
Terminal facilities. On bay side of Ocean City: two 
storage basins, for pleasure and small commercial craft, 
and numerous privately owned pile-and-timber piers and 
bulkhead wharves. At project harbor: a public landing 
about 1,000 feet long, several privately constructed 
bulkhead wharves open to the public for transaction of 
business with the owners, and a boat repair yard with a 
marine railway capable of handling boats up to about 150 
tons. All piers and wharves are accessible by highway. 
Port facilities have been expanded to include all available 
space in the Fish Harbor. 
Operations and results during fiscal year. New Work: 
A contract for rehabilitating the south jetty was awarded 
September 15, 1983 with Jobs Act funds. 
Maintenance: The general design memorandum and 
final design of the south jetty rehabilitation were completed. 
A contract combining this work and the filling of 
a fifty foot deep scour hole at the northern ocean side of 
the south jetty was awarded September 15, 1983 as 
noted above. 
13. POCOMOKE RIVER, MD 
Location. Pocomoke River is a tributary of Pocomoke 
Sound, a tidal estuary on the east side of Chesapeake Bay 
about 40 miles north of Cape Charles, VA. 
Existing project. Provides for a channel 11 feet deep at 
mean low water and 150 feet wide from the 11-foot depth 
in Pocomoke Sound to Tulls Point, thence 100 feet wide 
to deep water in Pocomoke River above Williams Point, 
and for construction of a dike along the offshore side of 
channel between Tulls Point and the end of the existing 
dike; and a channel 9 feet deep at mean low water and 100 
to 130 feet wide from Shad Landing to the bridge at Snow 
Hill. Length of project is about 8.7 miles from Pocomoke 
Sound to Williams Point, and about 4.5 miles from Shad 
Landing to Snow Hill, MD. Shad Landing is about 25.7 
miles above the mouth of the river. 
Mean range of tide is 2.4 feet in Pocomoke Sound and 
2.5 feet in the river at Snow Hill. Prolonged high winds on 
Chesapeake Bay frequently cause greater fluctuations. 
Estimated cost (1969) for new work is $1,071,458 exclusive 
of amounts expended under previous projects. 
Extension of channel above the bridge at Snow Hill, 100 
feet wide, 9 feet deep and widened to 150 feet to form a 
turning basin at upper end, is considered inactive and is 
excluded from the foregoing estimate. Estimated cost of 
this portion is $22,000 (1956). 
Local cooperation. Complied with for section of project 
from Pocomoke Sound to Pocomoke River and from Shad 
4-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Landing to the highway bridge at Snow Hill, authorized 
by acts of June 3, 1896, and August 30, 1935, except local 
interests must furnish releases from damage to oyster 
beds and spoil disposal areas as required for future 
maintenance. Terms for the section of the project above 
the highway bridge at Snow Hill, authorized by act of 
March 2, 1945, required local interests to furnish all 
lands, easements, rights-of-way, and spoil disposal areas 
for initial work and future maintenance, hold the United 
States free from damages resulting from the improvement; 
and contribute one-half the initial cost of that portion 
of project, but not to exceed $4,250. This portion is 
considered inactive. Terms for the 11-foot depth channel 
from Pocomoke Sound to deep water in Pocomoke River 
above Williams Point, authorized by act of September 3, 
1954, require local interests provide all lands, easements, 
rights-of-way, and spoil disposal areas for construction 
and future maintenance of the project; and hold the 
United States free from damages due to construction and 
maintenance, including such damages as may occur to 
the public or leased oyster beds. 
Terminal facilities. Waterfronts at Pocomoke City and 
Snow Hill are built up principally with earthfilled timber 
bulkheads, the majority of which are privately owned. A 
few of the warehouses and factories on the river at these 
communities have railroad sidings and mechanical 
freighthandling facilities. Any appreciable increase in 
commerce at Pocomoke City or Snow Hill would necessitate 
construction of new facilities and repair of existing 
structures. Adequate space is available for development 
of additional terminals. 
Operations and results during fiscal year. Maintenance: 
Engineering and Design work was accomplished 
in connection with proposed maintenance dredging. 
14. POCOMOKE RIVER AT 
MOUNT VERNON, VA 
Location. Mount Vernon lies in Fairfax County, VA, 
about 141/ miles below Washington, DC on the right 
bank of the Potomac River, which flows in a southeasterly 
direction into the Chesapeake Bay, 931/2 miles 
downstream from Mount Vernon. (See U. S. Coast and 
Geodetic Survey Chart No. 560.) 
Existing project. This provides for dredging a channel 
200 feet wide and 9 to 10 feet deep, at mean low water, 
between the main channel of the Potomac River and the 
Mount Vernon wharf, a distance of about 2,200 feet, with 
a turning basin of the same depth and a radius of 200 feet 
at the wharf. Tidal ranges are: mean. 2.2 feet; irregular, 3 
feet; and extreme, 9.7 feet. 
The cost estimate of the project to the Federal Government 
made in 1888 was $26,000. There is no approved 
estimate for annual cost of maintenance. 
Local cooperation. None required. 
Terminal facilities. There is one privately owned and 
operated wharf on the Mount Vernon estate at the head 
of the channel. 
Operations and results during fiscal year. Maintenance: 
A condition survey was conducted. An environmental 
assessment and engineering and design for 
maintenance dredging was accomplished. 
15. POTOMAC RIVER BELOW 
WASHINGTON, DC 
Location. Potomac River is formed 21 miles below 
Cumberland, MD, and flows southeasterly about 285 
miles and enters Chesapeake Bay, about 80 miles from 
Atlantic Ocean. Washington, DC is 108 miles upstream 
of mouth, and head of tidewater is at mile 117. (See Coast 
and Geodetic Survey Charts Nos. 557, 558, 559, and 560.) 
Existing project. Provides for a channel 24 feet deep 
and 200 feet wide between the mouth of the river and 
Giesboro Point at Washington, DC a distance of 108 
miles. Plane of reference is mean low water. Tidal ranges 
are: mean, 1.3 feet at mouth, 2.9 feet at Washington; irregular, 
2 feet at mouth, 4.5 feet at Washington; extreme, 
about 6 feet at mouth, 10.7 feet at Washington. Federal 
cost of new work for the completed project was $153,836. 
Local cooperation. None required. 
Terminal facilities. In general, the improvement is a 
main river channel, and terminal facilities are only served 
where the channel runs close to either bank of river. In all, 
11 wharves are thus served. These wharves are of open 
and solid fill construction and bulkhead type. 
Operations and results during fiscal year. Maintenance: 
Engineering and design in connection with proposed 
maintenance dredging of the Potomac River below 
Washington, DC, was initiated. Chemical and physical 
testing of sediment samples was accomplished. 
16. POTOMAC AND ANACOSTIA 
RIVERS, DC COLLECTION AND 
REMOVAL OF DRIFT 
Location. Project applies to the Potomac and 
Anacostia Rivers, Washington, DC and their tributaries. 
Existing project. Collection and removal of drift from 
the waters of the Potomac and Anacostia Rivers and 
their tributaries in the Washington Area from the head of 
tidewater to Mount Vernon, VA. Total length of project, 
considering both sides of the waterway, is about 50 miles. 
Local cooperation. None required. 
Terminal facilities. See Section 23 of this text. 
Operations and results during fiscal year. Maintenance: 
Operations by hired labor consisted of collection 
and disposal of 225,720 cubic feet of driftwood, ranging 
from small blocks up to timbers of large dimensions. 
4-8

BALTIMORE, MD DISTRICT 
17. PREVENTION OF OBSTRUCTIONS & 
INJURIOUS DEPOSITS, 
BALTIMORE, MD 
Location. Project applies to tidal waters of the harbor 
of Baltimore and its adjacent and tributary waters and to 
all tidal waters of Chesapeake Bay and in Maryland. 
Existing project. Patrol and inspection throughout the 
project location to detect violations of sections 13 and 15 
of the River and Harbor Act of March 3, 1899 and to investigate 
obstructions to navigation pursuant to Federal 
regulations (33 CFR 209.109). 
Local cooperation. None required. 
Operations and results during fiscal year. Maintenance: 
Operations, by Supervisor of Harbor of Baltimore 
included inspections of approximately 75 Federal 
navigation channels within the project location to insure 
channels are not obstructed to general navigation by 
debris, sunken vessels/wrecks and/or fishing appurtenance. 
There were 21 detailed investigations of 
sunken vessels/wrecks resulting in 5 declarations of 
"Hazards to Navigation" whereby procedures were initiated 
to have the hazards removed. 
18. RHODES POINT TO TYLERTON, MD 
Location. Rhodes Point and Tylerton are two settlements 
about 1.5 miles apart on Smith Island, between 
Chespeake Bay and Tangier Sound, about 60 miles north 
of Virginia Capes and about 110 miles south of Baltimore. 
(See Coast and Geodetic Survey Chart 1224.) 
Existing project. Channel 6 feet deep, 50 feet wide from 
that depth in Tyler Creek to and including an anchorage 
basin of the same depth 150 feet wide and 400 feet long at 
Tylerton; channel 6 feet deep and 50 feet wide from that 
depth in Shanks Creek to and including an anchorage 
basin of the same depth 100 feet wide and 400 feet long at 
Rhodes Point; channel 6 feet deep and 50 feet wide from 
that depth in Big Thorofare River to Tylerton; channel 6 
feet deep and 50 feet wide from Rhodes Point to Tylerton. 
Mean range of tide is 1.7 feet. On January 22, 1982, the 
Chief of Engineers under authority of Section 107 of the 
1960 River and Harbor Act, as amended, authorized a 
channel 6 feet deep and 50 feet wide a distance of about 
one mile from the anchorage basin at Rhodes Point 
through Sheep Pen Gut to deep water in the Chesapeake 
Bay. 
Local cooperation. Fully complied with for work 
authorized by the Chief of Engineers January 22, 1982. 
See section 19 of 1982 Annual Report for requirement 
details. 
Terminal facilities. There are numerous pile-andtimber 
wharves along waterfronts at Rhodes Point and 
Tylerton. Facilities are privately owned, but open to the 
public without charge when not in use by the owners, and 
are adequate for existing commerce. Sufficient space for 
construction of additional facilities is available, if required. 
Operations and results during fiscal year. New Work: 
The construction contract which was awarded August 
23, 1982 was completed on October 15, 1982. 
19. ST. GEORGE CREEK, MD 
Location. The project is on a tributary of the Potomac 
River located about 90 miles south of Baltimore, 60 miles 
southeast of Washington, DC, and approximately 10 
miles from the mouth of the Potomac River. (See 
National Ocean Survey Chart No. 12233.) 
Existing project. On April 29, 1983 the Chief of 
Engineers under authority of Section 107 of the 1960 
River and Harbor Act, as amended, authorized a channel 
1,500 feet in length, 60 feet wide and 7 feet deep at mean 
low water, from St. George Creek Island Bridge to deep 
water in the Potomac River. 
Local cooperation. Fully complied with for work 
authorized by Chief of Engineers on April 29, 1983 as 
follows (excluding furnishment of lands and rights-ofway 
for future maintenance): 
a. Provide without cost to the United States all 
necessary lands, easements, and rights-of-way required 
for construction and subsequent maintenance of the project 
including suitable spoil disposal areas with necessary 
retaining dikes, bulkheads, and embankments therefore, 
or the cost of such retaining works; 
b. Hold and save the United States free from damages 
that result from construction and maintenance of the 
project, but not including damages due to the fault or 
negligence of the United States or its contractors; 
c. Accomplish without cost to the United States all 
alternations and relocations of buildings, transporation 
facilities, storm drains, utilities, and other structures 
and improvements made necessary by project construction; 
d. Provide and maintain without cost to the United 
States adequate public terminal and transfer facilities 
open to all on equal terms; contribute, in cash, all project 
costs in excess of the Federal cost limitation of 
$2,000,000; establish regulations prohibiting discharge 
of untreated sewage, garbage, and other pollutants in 
navigable waters by users thereof, which regulations 
shall be in accordance with applicable laws or regulations 
of Federal, State, and local authorities responsible for 
pollution prevention and control; comply with applicable 
provisions of the Uniform Relocation Assistance and 
Real Property Acquisition policies Act of 1970 (P.L. 
91-946; 84 Stat. 1894) and implementing regulations; and 
comply with Title VI of the Civil Rights Act of 1964 (P.L. 
88-352, 78 Stat. 241, 252). 
Terminal facilities. Many of the shoreline community 
residents are commercial watermen and seafood processing 
establishments are located on St. George Island. 
Recreational boating is abundant and St. Marys County 
owns a public boat ramp on the north side of St. George 
Island. The Harry Lundeberg School of Seamanship, 
located at St. George Harbor is used to train individuals 
4-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
in the basic seamanship skills required by the United 
States Maritime Industry. 
Operation and results during fiscal year. New Work: 
Plans and specifications were initiated and completed, 
and the construction contract was awarded on 
September 15, 1983 with Jobs Act funds in the amount of 
$74,800. 
20. ST. PATRICKS CREEK, MD 
Location. St. Patricks Creek in St. Marys County, MD 
is a small tidal stream 11/2 miles long which flows in a 
southeasterly direction and enters the west side of St. 
Clement Bay at its junction with the Potomac River. The 
creek is 33 miles upstream from the Chesapeake Bay and 
83 miles downstream from Washington, DC (See U. S. 
Coast and Geodetic Survey Chart No. 558). 
Existing project. Provides for an entrance channel 7 
feet deep, 60 feet wide, and approximately 2,450 feet long 
from deep water in St. Clement Bay to deep water within 
the creek. The plane of reference is mean low water. The 
tidal ranges are: mean, 1.9 feet; irregular, 2.5 feet; and 
extreme, approximately 7 feet. 
The cost to the Federal Government for new work for 
the completed project was $15,752, exclusive of $1,000 
contributed by local interests. The latest (1950) approved 
estimate for the annual cost of maintenance is $4,800. 
Local cooperation. The existing project was approved 
subject to the provisions that (a) local interests contribute 
$1,000 in cash toward the cost of new work; (b) 
hold and save the United States free from any damage 
resulting from construction and maintenance of the improvement; 
(c) furnish releases from damages to oyster 
grounds; (d) furnish free of cost to the United States 
suitable spoil-disposal areas for new work and subsequent 
maintenance, when and as required; and (e) agree 
to provide a suitable public wharf with access road open 
to all on equal terms. Items (a) through (d) have been fully 
complied with. Local interests have initiated action to 
complete item (e). 
Terminal facilities. There are 41 small wharves and 
stagings located in the creek. All are privately owned, 
but one is open to the public. There is also one marine 
railway in the creek. The terminal facilities are considered 
adequate for present commerce. 
Operations and results during fiscal year. Maintenance: 
Engineering and Design work was accomplished in connection 
with proposed maintenance dredging. 
21. TILGHMAN ISLAND HARBOR, MD 
Location. This harbor (also called Dogwood Harbor) is 
about 60 miles southeast of Baltimore Harbor on the 
eastern side of Tilghman Island, which lies between 
Chesapeake Bay and Choptank River. (See Coast and 
Geodetic Survey Chart 78.) 
Existing project. Provides for a channel 60 feet wide 
and 6 feet deep from that depth in Harris Creek to and including 
an anchorage basin of irregular shape 500 feet 
long by 200 feet wide, with a 6-foot depth. On October 20, 
1980, the Chief of Engineers under authority of Section 
107 of the 1960 River and Harbor Act, as amended, 
authorized construction of a breakwater at the harbor 
entrance. The estimated first cost of this work is 
$249,000, of which $245,000 is Federal cost and $4,000 is 
required local cash contribution. 
Local cooperation. Fully complied with for work authorized 
May 13, 1966, except that local interests must 
furnish all lands, and rights-of-way for future maintenance 
as needed and maintain a suitable public landing 
as needed with adequate approaches thereto. For work 
authorized by the Chief of Engineers October 20, 1980, 
local interests have fully complied (excluding furnishment 
of lands and right-of-ways for future maintenance). 
For detail of requirements see section 23 of the 1982 Annual 
Report. 
Terminal facilities. Consists of one pier operated by a 
local seafood packer for transfer of seafood to processing 
plant. Local interests will construct a public landing and 
approach road thereto in accordance with terms of local 
cooperation as part of the project development. 
Operations and results during fiscal year. New work: 
The construction contract which was awarded April 15, 
1982 was completed on November 17, 1982. 
22. WARWICK RIVER, MD 
Location. This river, formerly named Secretary Creek, 
is in Dorchester County, MD, and flows into the Choptank 
River about 25 miles above its mouth. It is a tidal 
estuary about one mile long with little fresh-water inflow 
and practically no drainage area. (See Coast and Geodetic 
Survey Chart 1225.) 
Existing project. Provides for a channel 10 feet deep 
and 100 feet wide at mean low water from the 10-foot contour 
in Choptank River to Secretary Landing and a turning 
basin at the latter point. The length of the section included 
in the project is about 1.5 miles, the lower half 
mile extending into Choptank River. The mean range of 
tide is 2 feet, and the extreme tidal range is 3.7 feet. 
Local cooperation. None required. 
Terminal facilities. There is one canning house, one 
warehouse, and a petroleum products storage terminal. 
There is one solid bulkhead wharf with 450 feet of dockage 
space which is privately owned but open to general 
public use. 
Operations and results during fiscal year. Maintenance: 
Engineering and design work was accomplished 
in connection with proposed maintenance dredging. 
Work was deferred because suitable spoil disposal areas 
could not be located. 
23. WASHINGTON HARBOR, DC 
Location. Within District of Columbia at junction of 
Anacostia River with Potomac River which flows southeasterly 
108 miles to Chesapeake Bay. It is southerly 202 
4-10

BALTIMORE, MD DISTRICT 
miles by water from Baltimore, MD, and northerly 195 
miles from Norfolk, VA. (See Coast and Geodetic Survey 
Chart 12289.) 
Existing projects. A combination and extension of 
latest projects for Potomac River at Washington, DC, 
and Anacostia River, DC. The Washington Harbor project 
provides for a channel in the Potomac River from 
Giesboro Point to Key Bridge, a second channel from 
Giesboro Point to the end of Washington Channel, and a 
third channel from the mouth of the Anacostia River to 
the foot of 15th Street, SE, with turning basins opposite 
the Naval Weapons Plant (800 feet wide and 2,400 feet 
long) and at the head of the Anacostia Channel (400 feet 
square). Channel dimensions are 24 feet deep and 400 feet 
wide except upstream from Anacostia Bridge were the 
width is reduced to 200 feet and from Giesboro Point to a 
point 3,000 feet downstream of Arlington Memorial 
Bridge and above Easby Point where channel dimensions 
are 20 feet deep and 200 feet wide. Channel lengths including 
turning basins are: Virginia Channel, 5,000 feet; 
Washington Channel, 10,000 feet; and Anacostia River, 
15,000 feet; and operation and maintenance of the inlet 
gates and lock and the outlet gates of the Tidal Basin constructed 
under a previous project to flush Washington 
Channel. Plane of reference is low-water datum which is 
0.35 foot below mean low tide as observed from 1932 to 
1942. Tidal ranges are: mean, 2.9 feet; irregular, 4.5 feet; 
and extreme, 10.7 feet. Federal cost of new work for the 
completed project was $162,006. 
Local cooperation. None required. 
Terminal facilities. There are four wharves generally of 
bulkhead type on Virginia Channel that are privately 
owned and not open to the public except by special 
arrangement. On Washington Channel there are four 
piers under jurisdiction of District of Columbia, two of 
which are open to the public and one open to the public by 
special arrangement. In Anacostia River there are four 
privately owned piers and eight governmental piers and 
slips. None of the piers are open to the public except by 
special arrangement. Terminal facilities are considered 
adequate for existing commerce. 
Operations and results during fiscal year. Maintenance: 
The contract for repair of the tidal basin inlet 
gates which was awarded September 17, 1982 is 99% 
complete. 
24. WICOMICO RIVER, MD 
Location. Wicomico River has its source in northern 
part of Wicomico County, MD, and flows generally 
southwardly emptying into Monie Bay, a tributary of 
Tangier Sound on the east side of Chesapeake Bay about 
85 miles southeast of Baltimore. Webster Cove is site of 
improved small-boat harbor on southeast bank of 
Wicomico River about 3 miles above the mouth. (See 
Coast and Geodetic Survey Charts 567 and 1224.) 
Existing project. Channel 14 feet deep and 150 feet 
wide from Chesapeake Bay to Salisbury, section included 
in project is 37 miles long, including about 12 miles from 
mouth of river to Chesapeake Bay; 14 feet deep in channels 
and turning basins in north and south prongs with 
channel widths of 100 feet, and a channel 6 feet deep and 
60 feet wide extending from 6-foot contour in Wicomico 
River to and including a basin in Webster Cove of same 
depth, 100 feet wide and 400 feet long; and extension of 
basin 200 feet long and 100 feet wide on each side. Plane 
of reference is mean low water. Mean range of tide is 
about 3 feet and extreme tidal range is 4.4 feet. Cost of 
new work for completed project was $421,609, exclusive 
of amounts expended on previous project. 
Local cooperation. Fully complied with, except that 
local interests are to furnish spoil disposal areas for 
future maintenance as needed and hold the United States 
free from such damages as may occur to public or leased 
oyster beds. 
Terminal facilities. Present waterfront at Salisbury 
consists of pile-and-timber bulkheads with earthfills. 
Some wharves have warehouses and factories with 
mechanical freight-handling facilities and rail sidings. 
All terminals are privately owned. A shipyard, with two 
marine railways with capacities of 1,200 and 500 tons, 
respectively, is on right bank of river below prongs. 
Areas for development of new terminals on north prong 
are limited. Areas for considerable expansion of terminal 
facilities are available on main river. There is a pile-andtimber 
wharf about 4 miles above mouth of river at 
Mount Vernon. A wharf of similar construction is at 
White Haven. There is a county wharf at head of basin in 
Webster Cove, a pile-and-timber pier at oyster house on 
southwest side of basin, a T-shaped pile-and-timber pier 
at cafe on southwest side of basin and several small 
timber piers on walkways that local interests constructed 
around the basin. Fueling facilities are available 
at the T-shaped pier. Sufficient areas are available for 
construction of additional facilities when required. 
Operations and results during fiscal year. Maintenance: 
Maintenance dredging of the Great Shoals channel 
was completed December 8, 1983. A total of 120,600 
cubic yards of material was removed. A contract for 
maintenance dredging of Sharkfin Shoal was awarded 
August 22, 1983, and the upland disposal area is under 
construction. 
25. RECONNAISSANCE AND CONDITION 
SURVEYS 
(See Table 4-H at end of chapter.) 
26. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation activities pursuant to Section 107, Public 
Law 86-645 (preauthorization). 
Fiscal year costs were $93,633 for Hull Creek, VA, and 
$76,235 for Lower Thorofare, MD. 
4-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Beach Erosion Control 
27. COLONIAL BEACH, VA 
Location. Colonial Beach, Westmoreland County, VA, 
is located on the right bank of the Potomac River 40 miles 
upstream from its mouth at Chesapeake Bay and 69 
miles downstream from Washington, DC. (See U.S. 
Coast and Geodetic Survey Chart No. 558.) 
Existing project. On May 29, 1980, the Chief of 
Engineers under authority of Section 103 of the 1960 
River and Harbor Act, as amended, authorized construction 
of the following work: Extending and widening the 
existing Central Beach area downstream from Hawthorne 
Street southward to provide an additional beach 
area of about 107,200 square feet, stablizing with vegetation 
about 200 feet of the bank behind the beachfill and 
constructing four segments of offshore breakwater with 
estimated lengths of 200 feet each, to stablize the beachfill 
area; and extending and widening the existing beach 
at Castlewood Park to provide an additional beach area 
of about 59,300 square feet; constructing three segments 
of offshore breakwater with estimated lengths of 200 feet 
each for two of the segments and 300 feet for the third 
segment; removing debris in the beachfill area; and constructing 
a 100-foot long terminal groin at the southern 
end of the Castlewood Park beachfill. The estimated cost 
of this work is $1,910,977 of which $1,000,000 is Federal 
cost and $910,977 is required local cash contribution. The 
$1,910,977 includes $992,000 for periodic beach nourishment 
as needed, after FY 1983. 
Local cooperation. Among other requirements, local interests 
must provide all lands, easements, and rights-ofway 
and relocations required for construction including 
periodic nourishment and provide a cash contribution 
equal to 50 percent of the final project construction cost 
(excluding lands and relocations). 
Operations and results during fiscal year. New work: 
The construction contract which was awarded January 
26, 1982 was completed October 29, 1982. 
Flood Control 
28. BLACK WALNUT POINT, MD 
Location. The southern end of Tilghman Island, about 17 
miles south of the William P. Lane Jr. Memorial 
(Chesapeake Bay) Bridge eastern shore landing. (See 
National Ocean Survey Chart Numbers 12266 and 
12263.) 
Existing project. On December 22, 1982 the Chief of 
Engineers under authority of Section 14 of the Flood 
Control Act of 1946, as amended, authorized construction 
for 375 linear feet of 43 foot wide stone revetment to 
stabilze existing shorebank. 
-Local cooperation. Fully complied with for work 
authorized by Chief of Engineers on December 10, 1982 
as follows (excluding $250,000 cost limitation not yet 
exceeded): 
a. Provide without cost to the United States all lands, 
easements, and rights-of-way necessary for the construction 
and maintenance of the project. 
b. Provide without cost to the United States all necessary 
modifications and relocations of buildings, roads, 
bridges, and related utilities. 
c. Maintain and operate all completed works in accordance 
with regulations prescribed by the Secretary of the 
Army. 
d. Hold and save the United States free from all damages 
arising from the construction and operation of the 
completed works, except for damages due to the fault or 
negligence of the United States or its contractors. 
e. Assume responsibility for all cost in excess of the 
Federal limitation of $250,000, under the authority of 
Section 14 of the Flood Control Act of 1946, as amended. 
Operations and results during fiscal year. New Work: 
Plans and specifications were initiated and completed, 
and the construction contract was awarded on 
September 14, 1983 in the amount of $137,086 with Jobs 
Act funds. 
29. BLOOMINGTON LAKE, MD & WV 
Location. Project is located on the North Branch 
Potomac River on the state line between Garrett County, 
MD, and Mineral County, WV. The damsite is located 
approximately 7.9 miles upstream from the confluence 
with Savage River at Bloomington, MD. It is also about 
5 air miles southwest of the tritowns of Luke and 
Westernport, MD, and Piedmont, WV. (See Geological 
Survey Quadrangle sheets, "Kitzmiller" and "Westernport," 
MD.) 
Existing project. The improvement consists of a rolled 
earth and rock fill dam with an impervious core and an 
800-foot long dike on the left bank. Top of dam is 296 feet 
above streambed with a total length of 2,130 feet. When 
filled to spillway crest, the reservoir will extend about 6.6 
miles upstream and inundate 965 acres. Flood control 
storage of 36,200 acre-feet is provided. Storage available 
for low flow augmentation for water supply and water 
quality improvement is 92,000 acre-feet. The reservoir 
controls a drainage area of 263 square miles. Recreation 
facilities are provided for picnicking, camping and 
boating. Estimated cost (October 1983) of new work is 
$174,480,300 of which $57,927,000 is required nonfederal 
reimbursement. 
Local cooperation. See page 4-15 of the 1977 Annual 
Report for requirements. A water supply contract between 
the Federal Government and the Washington 
Suburban Sanitary Commission in concert with the Fairfax 
County Water Authority, VA, and the District of 
Columbia has been executed for repayment of all water 
supply costs. The first of 50 annual payments began in 
July 1981. Federally approved water quality standards 
put into effect by Maryland, Virginia, West Virginia, and 
the District of Columbia are considered satisfactory 
assurances of intent to control pollution. Satisfactory 
assurances have been received from Maryland, Wet 
4-12

BALTIMORE, MD DISTRICT 
Virginia, and Virginia that they will protect downstream 
channels from encroachment that would adversely affect 
operation of the project. 
Operations and results during fiscal year. New work: 
The project became operational for water supply, flood 
control, and for water quality control in July 1981. 
Relocation of West Virginia Route 46 and construction of 
campground and picnic facilities were completed. A contract 
for improving spillway flow was awarded August 5, 
1983 and is 45 percent complete. Work on the operation 
and maintenance manual continued. 
Maintenance: Normal operation and maintenance of 
the project continued. With Jobs Act funds, construction 
of three hiking trails and a playground was completed. 
30. BULL RUN, PA 
Location. In Loyalsock Township which is located on 
the left or north bank of the West Branch of the Susquehanna 
River just downstream from Williamsport, 
PA. The proposed project would provide protection to 
Loyalsock Township from the limit of the Williamsport 
Project at Millers Run aproximately one mile downstream 
along the West Branch of the Susquehanna 
River. 
Existing project. Provides for alteration of 4,100 linear 
feet of highway embankment by providing an impervious 
core which will serve as a levee to provide protection from 
flood stages on the West Branch Susquehanna River, tie 
back levees from the highway embankment to high 
ground, and a pumping facility at Bull Run to provide 
protection from backwater from the West Branch and 
from interior drainage on Bull Run. Estimated Federal 
cost (October 1983) for new work is $2,902,000. 
Local cooperation. Section 3, Flood Control Act of 
June 22, 1936, applies. Local interests must assume 
responsibility for all costs in excess of the Federal cost 
limitation of $3,000,000. An agreement for local cooperation 
complying with Section 221 of the 1970 Flood Control 
Act was accepted for the Secretary of the Army on 
September 21, 1977. 
Operations and results during fiscal year. New work: 
Construction was essentially completed at an FY 83 cost 
of $15,110. 
31. CUMBERLAND, MD, AND 
RIDGELEY, WV 
Location. On North Branch of the Potomac River, 21 
miles upstream from its junction with the South Branch 
of the Potomac River and 197 miles upstream from 
Washington, DC. (See Geological Survey Quadrangles, 
Frostburg and Flintstone, MD, WV, and PA.) 
Existing project. Channel improvements of North 
Branch of Potomac River from the Western Maryland 
Railway bridge in South Cumberland upstream to the 
mouth of Wills Creek, with levees and fill along the left 
bank and levees along the right bank from downstream : 
corporate limits of Ridgeley, WV, to a point about 150 
feet above Johnson Street Bridge; channel improvements 
along Wills Creek from its mouth upstream to a 
point in the Narrows about 500 feet upstream from the 
highway bridge on U.S. Highway 40; levee and floodwall 
in West Cumberland, MD, on the left bank of the North 
Branch of the Potomac River from the mouth of Wills 
Creek upstream to Kelly Boulevard; levee and floodwall 
in Ridgeley, WV, on the right bank of the North Branch 
of the Potomac River from Carpenter Avenue upstream 
to Patapsco Street near the upstream corporate limits of 
Ridgeley, WV; interior drainage facilities in Cumberland 
and West Cumberland, MD, and Ridgeley, WV; removal 
of the Chesapeake and Ohio Canal dam and construction 
of a new industrial dam on the North Branch of the 
Potomac River immediately above mouth of Wills Creek; 
and alteration and reconstruction of highway and 
railroad bridges. Federal costs of new work for the completed 
project were $15,633,970, which includes $49,998 
emergency relief funds and is exclusive of $197,513 
public works acceleration funds. Estimated cost to local 
interests is $2,900,000 of which $1,402,001 is contributed 
funds and $1,497,999 is for lands and damages. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Maintenance: 
Removal of gravel deposits, grass cutting of 
areas channelward of levees, and removal of brush and 
debris from channel were accomplished as required in 
channel area. 
32. FOURMILE RUN, VA 
Location. The project is located in the City of Alexandria 
and in Arlington County, VA, on Fourmile Run 
immediately above its confluence with the Potomac 
River at Washington, DC. (See Geological Survey 
Quadrangle sheets for Alexandria, VA, Annandale, VA, 
Falls Church, VA, and Washington West, DC, MD, and 
VA.) 
Existing project. Provides for construction of a floodwall 
protection system, an improved channel, and replacement 
of two highway and four railroad bridges. 
Total estimated cost (October 1983) of new work is 
$54,219,000 of which $2,439,000 is non-Federal. 
Local cooperation. See page 4-17 of the 1977 Annual 
Report for requirements. 
Agreements for local cooperation complying with Section 
221 of the 1970 Flood Control Act and Subsection 84 
(b) of the 1974 Water Resources Development Act were 
accepted for the Secretary of the Army on April 23, 1974. 
Agreements for local cooperation concerning recreation 
cost sharing were accepted for the Secretary of the Army 
on May 30, 1974. An inter-jurisdictional agreement 
among Alexandria, and Falls Church and Arlington and 
Fairfax Counties was executed in March 1977 for implementing 
a watershed control program. 
Operations and results during fiscal year. New work: A 
contract for removing silt from the downstream reach of 
the channel improvement was completed except for 
modifying an oil retention pond to improve its operation. 
4-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
33. LACKAWANNA RIVER BASIN, PA 
Flood Control Act of 1962 authorized construction of 
Aylesworth Creek Lake, Fall Brook Lake, and local protection 
works on Lackawanna River at Scranton, PA, 
substantially as recommended by the Chief of Engineers 
(S. Doc. 141, 87th Cong., 2d sess.). The Basin includes an 
area of 346 square miles in northeastern Pennsylvania. 
33A. AYLESWORTH CREEK LAKE, PA 
Location. Project is located in Lackawanna County on 
Aylesworth Creek about one mile above its confluence 
with the Lackawanna River, near the community of East 
Jermyn, PA. 
Existing project. Provides for an earthfill dam with a 
maximum height of 90 feet above streambed and a top 
length of 1,200 feet. The spillway located adjacent to the 
left abutment is an open cut channel 80 feet wide with a 
concrete sill. The outlet works consist of a 3-foot 
diameter uncontrolled conduit. Project controls a drainage 
area of 6.2 square miles and provide flood control 
storage of 1,700 acre-feet equivalent to 5.1 inches of runoff 
from the drainage areas. The lake will extend about 
4,600 feet and inundate 87 acres when filled to spillway 
crest. Recreation facilities constructed by local interest 
include a bathing beach, bathhouse, and picnic area. 
Federal cost of new work was $2,268,200 of which 
$2,153,559 was for construction and $114,641 for lands 
and damages. In addition $52,200 Federal and $52,200 
non-Federal funds were expended for construction of 
bathhouse facilities under the recreation facilities for 
completed projects program. 
Local cooperation. None required. The Aylesworth 
Creek Reservoir Park Authority, representing the 
Boroughs of Archbald and Jermyn, operate and maintain 
limited day use facilities including a small beach. In 
September 1978 a cost sharing agreement for construction 
of bathhouse facilities was signed. The cost for the 
facilities which were completed in July 1979 was 
$104,400, of which $52,200 was Federal and $52,200 was 
non-Federal. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the project 
continued. 
34. LATTA BROOK ROAD, NY 
Location. On Newtown Creek is the town of Horseheads 
which is immediately north of the City of Elmira. 
Elmira is 6 miles north of the PA/NY border, about 60 
miles east of Buffalo. (See Geological Survey maps for 
Horseheads and Elmira.) 
Existing project. On December 10, 1982 the Chief of 
Engineers under the authority of Section 14 of the Flood 
Control Act of 1946, as amended, authorized construction 
for 630 linear feet of 30 feet wide stone riprap 
stabilization on the streambank of Newtown Creek. 
as follows (excluding $250,000 cost limitation not yet 
exceeded): ' 
a. Provide without cost to the United States all lands, 
easements, and rights-of-way necessary for the construction 
and maintenance of the project. 
b. Provide without cost to the United States all 
necessary modifications and relocations of buildings, 
roads, bridges, and related utilities. 
c. Maintain and operate all completed works in accordance 
with regulations prescribed by the Secreatry of the 
Army. 
d. Hold and save the United States free from all 
damages arising from the construction and operation of 
the completed works, except for damages due to the fault 
or negligence of the United States or its contractors. 
e. Assume responsibility for all cost in excess of the 
Federal limitation of $250,000, under the authority of 
Section 14 of the Flood Control Act of 1946, as amended. 
Operations and results during fiscal year. New Work: 
Plans and specifications were initiated and completed, 
and the construction contract was awarded August 24, 
1983 with Jobs Act funds in the amount of $63,870. 
35. RAYSTOWN LAKE, RAYSTOWN 
BRANCH, JUNIATA RIVER, PA 
Location. Damsite is on Raystown Branch, about 5.5 
miles upstream from its confluence with Juniata River. 
Project is about 10 miles south of Huntingdon, PA. (See 
Geological Survey Quadrangle sheets, Huntingdon, Mt. 
Union, Broad Top and Everett, PA.) 
Existing project. The rock and earthfill dam rises 225 
feet above streambed with a gated concrete spillway and 
auxiliary spillway in the right abutment. The reservoir 
has a storage capacity of 762,000 acre-feet, of which 
248,000 acre-feet are for flood control, 476,000 acre-feet 
for recreation and water quality control, and the balance 
for sediment reserve. At full flood control pool elevation, 
the reservoir would inundate 10,800 acres and extend 34 
miles upstream. Recreation facilities are provided for 
boating, fishing, camping, swimming, hunting, and picnicking. 
Federal cost for new work was $77,408,700 of 
which $46,120,931 was for construction and $31,287,769 
was for lands and damages including relocations. 
Local cooperation. None required. 
Operations and results during fiscal year. Maintenance: 
operation and maintenance of the project continued. 
With Jobs Act funds, boundary lines were marked, 
access roads were repaved, and miscellaneous buildings 
were repaired and painted. 
36. SOUTHERN NEW YORK FLOOD 
CONTROL PROJECTS 
Local cooperation. Fully complied with for work Authorized plan provides for construction of reserauthorized 
by Chief of Engineers on December 10, 1982 voirs and related flood control works for protection of 
4-14

BALTIMORE, MD DISTRICT 
towns in New York and Pennsylvania. The improvements 
are located in the upper watershed of the Susquehanna 
River to and including the Chemung River. 
36A. ADDISON, NY 
Location. At confluence of Tuscarora Creek and 
Canisteo River in the City of Addison, NY. (See Geological 
Survey map for Addison, NY.) 
Existing project. Provides for construction of about 
3,100 feet of earth levee and 700 feet of concrete floodwall 
on the right bank of the Canisteo River, extending from 
high ground on Steuben Street near the Baltimore & Ohio 
Railroad to the mouth of Tuscarora Creek; removal of 
existing dam, mill, and raceway from the channel; construction 
of about 2,200 feet of earth levee on the left 
bank of Tuscarora Creek, extending from Tuscarora 
Street to Canisteo River; construction of 4,600 feet of 
earth levee on the right bank of Tuscarora Creek, extending 
from high ground at the southwest edge of the village 
to high ground at the southeast edge of the village; and 
appurtenant drainage structures. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the project 
continued. 
36B. ALMOND LAKE, NY 
Location: Dam is located two miles upstream from 
Hornell, NY, on Canacadea Creek, a tributary of the 
Canisteo River. (See Geological Survey map for Hornell, 
NY.) 
Existing project. The dam is an earthfill structure, 
1,260 feet long rising 90 feet above the streambed, with a 
concrete spillway and a gated outlet conduit in the left 
abutment. The outlet works consist of three 5-foot by 
10-foot service gates and three emergency gates of the 
same size. The reservoir has a storage capacity of 14,640 
acre-feet at spillway crest. The project controls a draining 
area of 56 square miles, 36 percent of the watershed of 
the Canisteo River upstream from Hornell, NY. Recreation 
facilities include a boat-launching ramp and dock, 
bathing beach, picnic area, and tent and trailer camping 
area. 
Local cooperation. None required. Local interests have 
developed recreational facilities at the lake in conjunction 
with the Federal Government. These facilities are 
operated and maintained by the Steuben County Board 
of Supervisors. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of project 
continued. With Jobs Act funds, a guardrail was replaced. 
36C. ARKPORT DAM, NY 
Location. Dam is located five miles upstream from 
Hornell, NY, on the Canisteo River, a tributary of the 
Chemung River which flows into the Susquehanna River. 
(See Geological Survey map for Arkport, NY.) 
Existing project. The dam is an earthfill structure, 
1,200 feet long, exclusive of spillway, rises 113 feet above 
the streambed, with a concrete spillway and an ungated 
outlet in the right abutment. The outlet structure consists 
of an 8-foot diameter reinforced concrete lined conduit, 
660 feet long. A cast iron nozzle is placed in the 
lower end of the conduit, reducing the outlet size to 4 feet 
4 inches. The reservoir has a storage capacity of 7,950 
acre-feet at spillway crest. The project controls a 
drainage area of 31 square miles, 20 percent of the watershed 
of the Canisteo River upstream from Hornell. 
Local cooperation. None required. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the project 
continued. 
36D. AVOCA, NY 
Location. On the Cohocton River at the Village of 
Avoca, NY, about 30 miles upstream from the confluence 
of the Cohocton and Chemung Rivers. (See Geological 
Survey map for Avoca, NY.) 
Existing project. Provides for improvement and 
realinement of about 8,300 feet of Cohocton River channel, 
extending from above the Erie Railroad to below the 
junction of Main Street and U.S. Highway 15; construction 
of about 8,500 feet of earth levee on left bank of the 
Cohocton River, extending from high ground above Alexander 
Avenue to about 1,300 feet below the junction of 
Main Street and U.S. Highway 15; and 4,500 feet of earth 
levee on the right bank of Salmon Creek, extending from 
high ground above Alexander Avenue to the Erie Railroad; 
a new highway bridge for U.S. Highway 15 over 
Cohocton River, raising of the Erie Railroad bridge 4 
feet; and appurtenant drainage structures. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the project 
continued. 
36E. BINGHAMTON, NY 
Location. At the confluence of the Chenango and 
Susquehanna Rivers in the City of Binghamton, NY. (See 
Geological Survey map for Binghamton, NY.) 
Existing project. Provides for construction of earth 
levees, concrete floodwalls, and appurtenant drainage 
structures, consisting of about 850 feet of channel excavation 
and about 1,375 feet of earth levee along Phelps 
Creek, Town of Port Dickinson; new concrete wall on the 
right bank of the Chenango River, extending downstream 
from high ground near the city limits to an existing 
floodwall below DeForest Street, a distance of about 
520 feet; about 150 feet of concrete wall just below Cutler 
Dam; about 180 feet of concrete wall at the pumphouse 
near McDonald Avenue; raising existing earth levees on 
the right bank of Chenango River, extending from Cutler 
4-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Dam downstream for about 1,220 feet; about 2,915 feet of 
earth levee on the left bank of Chenango River north of 
the city limits in the Village of Port Dickinson, extending 
from Church Street to high ground just north of the city 
line; about 3,900 feet of earth levee on the left bank of 
Chenango River, extending from DeForest Street to 
Cutler Dam; new concrete floodwalls and riverbank 
revetment for about 5,570 feet extending on the left bank 
of Chenango River from Cutler Dam to the junction with 
the Susquehanna River; about 540 feet of new concrete 
floodwall and raising about 1,085 feet of concrete floodwall 
on the right bank of the Susquehanna River, extending 
from the Delaware, Lackawanna & Western Railroad 
downstream to Tompkins Street Bridge; about 1,940 feet 
of earth levee; about 1,940 feet of concrete floodwall and 
capping about 125 feet of concrete floodwall, on the right 
bank of the Susquehanna River from Stuyvesent Street 
to mouth of Chenango River; about 8,380 feet of earth 
levee, about 2,180 feet of new concrete floodwall and raising 
about 125 feet of existing floodwall on the left bank of 
the Susquehanna River extending from Pierce Creek to 
high ground at State Highway 17; a debris dam and 
flume between Corbett and Hotchkiss Streets and a concrete 
pressure conduit, 1,060 feet long to carry flow of 
Park Creek from Vestal Avenue to the Susquehanna 
River; about 665 feet of levee extending from the Erie 
Railroad to high ground along the right bank of 
Chamberlain Creek near the mouth; closure structures at 
Erie Railroad and at Court Street; a weir, a drop structure, 
and about 1,800 feet of earth levee, about 2,235 feet 
of channel excavation, about 645 feet of channel paving 
and raising, about 470 feet of existing concrete floodwall, 
and about 200 feet of new concrete floodwall for improvement 
of Pierce Creek from its mouth to about 1,000 feet 
above Conklin Avenue; and appurtenant drainage structures. 
Improvement, supplemented by authorized flood 
control dams above the area, will provide protection for 
the City of Binghamton against a flood discharge about 
20 percent greater than the maximum flood of record, 
which occurred in July 1935 on the Chenango River and 
in March 1936 on the Susquehanna River. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the project 
continued. 
36F. CANISTEO, NY 
Location. On Purdy and Bennetts Creeks in the Town 
of Canisteo, NY, situated along the south side of the 
Canisteo River, at the confluence of Bennetts Creek and 
the Canisteo River. (See Geological Survey map for 
Canisteo, NY.) 
Existing project. Provides for construction of about 
8,000 feet of earth levees on the right bank of the 
Canisteo River, extending from high ground 1,570 feet 
west of State Highway Route 21 above the Town to a 
point at the intersection of Ordway Lane and East Main 
Street; about 7,400 feet of earth levee on the left bank of 
:urdy and Bennetts Creeks, extending from the Main 
Street Bridge to high ground above Greenwood Street; 
1,000 feet of earth levee on the right bank of Bennetts 
Creek extending upstream from the Main Street Bridge; 
a concrete check dam with wing levees from Greenwood 
Street; a new highway bridge at Greenwood Street; 
alterations to existing timber check dams in Bennetts 
Creek; channel excavation in Bennetts and Purdy 
Creeks; and appurtenant drainage structures. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the project 
continued. 
36G. CORNING, NY 
Location. On the Chemung River in the City of Corning, 
NY, about 44 miles upstream from the confluence of 
Chemung River and North Branch of Susquehanna 
River. (See Geological Survey map for Corning, NY.) 
Existing project. Flood protection for this community 
was originally authorized by the Flood Control Act of 
1936. Plan of improvement provides for construction of a 
pumping station, earth levees, and concrete floodwalls, 
consisting of: about 4,300 feet of earth levee, enlargement 
of about 8,610 feet of existing earth levee and about 
3,100 feet of concrete floodwall on the right bank of the 
Chemung River, extending from the Erie Railroad 
Bridge to high ground at Park Avenue below the city; 
about 200 feet of concrete floodwalls; about 2,500 feet of 
earth levees and enlargement of about 11,500 feet of 
existing earth levee on the left bank of the Chemung and 
Cohocton Rivers, extending from the Erie Railroad 
Bridge over Cohocton River to the mouth of Post Creek; 
about 2,500 feet of earth levee and enlargement of about 
4,700 feet of existing earth levee on the right bank of Post 
Creek from its mouth to Watkins Street; realinement of 
about 3,000 feet of channel, about 8,800 feet of earth 
levee, about 3,000 feet of channel excavation, a pressure 
conduit about 400 feet long, a drop structure and a weir 
for improvement of Cutler Creek, extending from its 
mouth to high ground at Deckertown Road and Hornby 
Road; and appurtenant drainage structures. Flood protection 
on Monkey Run was authorized by the Flood Control 
Act of 1950. Plan of improvement provides for construction 
of 2,010 feet of open flume, 2,320 feet of 
pressure conduit storm sewers, and appurtenant facilities 
between the existing improved channel above Sixth 
Street and the Chemung River at a point immediately 
east of Pine Street East. Modified improvement will provide 
protection for the City of Corning against a flood 
discharge in Chemung River approximately equal to the 
maximum flood of record, which occurred in May 1945, 
and on tributary streams against floods of greater 
magnitude than known to date. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Maintenance: 
Normal operation and.maintenance of the project 
continued. 
4-16

BALTIMORE, MD DISTRICT 
36H. EAST SIDNEY LAKE, NY 
Location. Dam is located near East Sidney, NY, on the 
Ouleout Creek, about five miles above the confluence of 
the creek with the Susquehanna River. (See Geological 
Survey map for Franklin, NY.) 
Existing project. The dam is an earthfill and concrete 
structure, 2,010 feet long, including spillway, rises 130 
feet above the streambed and consists of a concrete 
gravity-type section with a compacted earth-dike section 
at the right abutment. The outlet works consist of five 
rectangular conduits each 3.5 feet by 5.85 feet and 105 
feet long. The reservoir has a storage capacity of 33,500 
acre-feet at spillway crest. The project controls a drainage 
area of 102 square miles which is 93 percent of the 
Ouleout Creek drainage area, and 5 percent of the watershed 
of the Susquehanna River upstream from Binghamton, 
NY, exclusive of the separately controlled Chenango 
River. Recreation facilities include a bathing beach, picnic 
and camping areas, and boat-launching and docking 
facilities. 
Local cooperation. None required. The Town of Sidney, 
NY, cooperated in the development of recreation facilities 
and operates and maintains all the facilities with the 
exception of the recreational pool, which is the responsibility 
of the Federal Government. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the project 
continued. 
36I. ELMIRA, NY 
Location. On the Chemung River in the City of Elmira, 
NY, about 27 miles upstream from the confluence of the 
Chemung River and North Branch of Susquehanna 
River. (See Geological Survey map for Elmira, NY.) 
Existing project. Provides for about 17,700 feet of 
earth levees, and about 4,100 feet of concrete floodwall on 
the right bank of the Chemung River, extending from 
South Hoffman Street to a point below the city near the 
upper end of Big Island; about 12,100 feet of earth levee 
and about 6,300 feet of concrete wall on the left bank of 
the Chemung River extending from Durland Avenue to 
the Delaware, Lackawanna & Western Railroad at the 
mouth of Newton Creek; about 10,000 feet of earth levee 
on right bank of Newton Creek, extending from about the 
intersection of Delaware, Lackawanna & Western Railroad 
and east Church Street to high ground near intersection 
of Sullivan and Warren Streets; about 4,300 feet 
of earth levee on the right bank of Divan Creek; about 
2,000 feet of concrete conduit inclosing Hoffman Brook 
from West Second Street to the Chemung River; clearing 
islands and riverbanks of trees and brush for about 3.5 
miles in the Chemung River; about 14,300 feet of earth 
levee on the left bank of Seely Creek, extending from the 
Erie Railroad to high ground approximately 1,000 feet 
northwest of the intersection of South Broadway and 
Pennsylvania Avenue; a pumping plant for disposal of interior 
drainage; an interceptor sewer about 6,000 feet 
long varying in size from 48 to 96 inches in diameter; and 
appurtenant structures. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the project 
continued. 
36J. HORNELL, NY 
Location. On the Canisteo River in the City of Hornell, 
NY, about 42 miles upstream from the confluence of the 
Canisteo and Tioga Rivers. (See Geological Survey map 
for Canisteo, NY.) 
Existing project. Provides for channel realinement and 
earth levees, concrete floodwalls, and check dams consisting 
of: realinement of about 4,600 feet of the Canisteo 
River channel, and about 5,800 feet of earth levee on its 
right bank, extending from Seneca Street upstream to 
the junction of the Pittsburgh, Shawmut & Northern 
Railroad and the Erie Railroad; about 4,500 feet of earth 
levee, extending on both sides of Seneca Street from the 
Canisteo River to Wrightman Avenue and the junction of 
Cleveland Avenue and Bethesda Drive; about 7,200 feet 
of earth levee, about 2,500 feet of concrete floodwall, and 
raising about 1,500 feet of existing concrete floodwall, on 
the right bank of the Canisteo River, and about 12,000 
feet of channel improvement, extending from Seneca 
Street to the Erie Railroad; about 2,500 feet of earth 
levee, about 2,100 feet of concrete floodwall on the left 
bank of the Canisteo River extending from a point 
opposite Walnut Street to the Erie Railroad; a ring-earth 
levee about 2,800 feet long around the sewage-disposal 
plant on the left bank of the Canisteo River; about 4,500 
feet of realinement and improvement of the Canisteo 
River Channel with about 4,500 feet of earth levee on its 
right bank extending from Cedar Street downstream to 
about 1,400 feet above East Avenue; about 2,400 feet of 
channel paving, 1,400 feet of earth levee, raising about 
1,900 feet of concrete floodwall, and construction of one 
check dam on Canacadea Creek; about 1,600 feet of channel 
paving and construction of three check dams on 
Chauncey Run with about 300 feet of new wall and about 
300 feet of capping; a weir, a check dam, 3,030 feet of 
channel paving, 4,800 feet of floodwalls and levees, and 
related work on existing walls, on Crosby Creek; removal 
of 6 bridges, erection of 4 bridges, miscellaneous bridge 
structures, and 3 drop structures; and appurtenant 
drainage structures and small stream control works. Improvement, 
supplemented by Arkport and Almond 
Reservoirs above the area, provides protection for the 
City of Hornell against a flood discharge approximately 
double the maximum flood of record, which occurred in 
July 1935. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the project 
continued. A construction contract for repairing the 
concrete wall at Thatcher Street was awarded September 
29, 1983. 
4-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
36K. LISLE, NY 
Location. On the Tioughnioga River in the Village of 
Lisle, NY, about 12 miles upstream from the confluence 
of the Tioughnioga and Chenango Rivers. (See Geological 
Survey map for Lisle, NY.) 
Existing project. Provides for channel realinement and 
construction of earth levees and concrete floodwalls, consisting 
of: relocation of about 3,000 feet of Dudley Creek 
Channel, extending from 1,200 feet west of the intersection 
of Cortland and Main Streets to the confluence with 
Tioughnioga River, realinement of some 5,700 feet of 
Tioughnioga River Channel east of the Village; about 
4,150 feet of earth levee and 970 feet of concrete wall on 
the right bank of Dudley Creek and Tioughnioga River; 
realinement of some 5,700 feet of Tioughnioga Street to 
the railroad crossing on River Street; raising about 1,860 
feet of the Delaware, Lackawanna & Western single 
track railroad over the levee; relocation of about 1,600 
feet of Cortland Street; a new bridge over relocated 
Dudley Creek; and appurtenant drainage structures. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the project 
continued. 
36L. OXFORD, NY 
Location. On the Chenango River in the Village of 
Oxford, NY, about 40 miles upstream from the confluence 
of the Chenango and Susquehanna Rivers. (See 
Geological Survey map for Oxford, NY.) 
Existing project. Provides for earth levees and clearing 
of Chenango River channel, consisting of about 2,100 feet 
of earth levees on the left bank of the Chenango River, 
extending from high ground near Cemetery Drive and 
running mostly along the railroad to high ground near 
Main Street; removal of dam and island below Main 
Street; raising the Delaware, Lackawanna & Western 
Railroad over the levee; and appurtenant closure and 
drainage structures. Improvement provides protection 
for the Village of Oxford on the left bank against a flood 
discharge substantially larger than the maximum flood 
of record, which occurred in July 1935. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the project 
continued. 
36M. WHITNEY POINT LAKE, NY 
Location. Dam is located near Whitney Point, NY, on 
the Otselic River about 0.7 mile upstream from its confluence 
with Tioughnioga River. (See Geological Survey 
map for Whitney Point and Willet, NY.) 
Existing project. The dam is an earthfill structure, 
4,900 feet long, exclusive of a spillway, rises 95 feet above 
the streambed, with a concrete spillway and gated outlet 
in the left abutment. The outlet works consist of three 
5-foot by 10-foot gates and one emergency gate of the 
same size. The reservoir has a storage capacity of 86,440 
acre-feet at spillway crest. The project controls a drainage 
area of 255 square miles, the entire watershed of 
Otselic River, or 16 percent of the Chenango River watershed 
upstream from Binghamton, NY. Recreation facilities, 
constructed in cooperation with local interests, provide 
for swimming, picnicking, camping, boating, 
fishing, and hunting. 
Local cooperation. None required. Local interests 
operate and maintain all of the recreation facilities. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the project 
continued. 
36N. WHITNEY POINT VILLAGE, NY 
Location. On the Tioughnioga River at the confluence 
of the Tioughnioga and Otselic Rivers, tributaries of the 
Susquehanna River. (See Geological Survey map for 
Whitney Point, NY.) 
Existing project. Provides for channel realinement and 
earth levees, consisting of realinement of about 1,800 feet 
of Tioughnioga River channel, above the confluence with 
Otselic River; about 7,100 feet of earth levee along the 
right bank of the Tioughnioga River, extending from 
high ground on Main Street above the village to Collins 
Street just below the Village; and appurtenant drainage 
structures. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the project 
continued. 
37. STILLWATER LAKE 
LACKAWANNA RIVER, PA 
Location. Dam is on the Lackawanna River, 39 miles 
from the mouth of the stream and about 4 miles upstream 
from Forest City, Susquehanna County, PA (See Geological 
Survey Quadrangle sheet: for Honesdale, PA.) 
Existing project. Dam is earthfill type, rising 77 feet 
above the streambed, with a controlled outlet conduit 
and side channel spillway in the left abutment. Reservoir 
capacity is 12,000 acre-feet, of which 11,600 acre-feet is 
flood control storage and the remainder utilized to maintain 
the existing water supply reservoir for Forest City, 
PA, at this site. Reservoir area is 422 acres, and the pool 
extends about 2.1 miles upstream. Reservoir controls 52 
percent of the watershed above Carbondale, 26 percent 
above Olyphant, and 17 percent above Scranton. Federal 
cost of new work, completed in 1965, was $5,725,700 of 
which $4,500,500 was for construction and $1,225,200 
was for lands and damages. 
Local cooperation. None required. Section 2, Flood 
Control Act of June 28, 1938, applies. 
4-18

BALTIMORE, MD DISTRICT 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of project 
continued. 
38. SUSQUEHANNA RIVER FLOOD 
CONTROL PROJECTS, NY AND PA 
Plan of improvement authorized by the 1958 Flood 
Control Act provides for construction of Cowanesque 
Lake, PA, Tioga-Hammond Lakes, PA, local protection 
works at Elkland, PA, and Nichols, NY, and channel 
improvements at Cortland, NY. This project plan supplemented 
the comprehensive flood control program for 
Southern New York and Northern Pennsylvania which 
included the Southern New York flood control project 
and Stillwater, Genegantslet, and South Plymouth 
Reservoirs. 
38A. COWANESQUE LAKE, PA 
Location. Dam is on the Cowanesque River about 2.2 
miles above its confluence with Tioga River at Lawrenceville, 
PA. (See Geological Survey map for Tioga, PA.) 
Existing project. The project constructed under the 
Flood Control Act of 1958 provides for an earth fill dam 
3,100 feet long and rising 151 feet above the streambed, 
an uncontrolled spillway in the right abutment, a gated 
conduit in the Valley floor, and flood control storage is 
82,000 acre-feet. Relocation of the Town of Nelson to a 
new townsite was authorized by Section 121 of the Water 
Resources Development Act of 1976. Estimated Federal 
cost (October 1983) of this new work is $106,030,700 of 
which $61,743,600 is for construction and $44,287,100 is 
for lands and damages and relocations (which includes 
$5,755,000 for relocation of the Town of Nelson). Within 
the discretionary authority of the Chief of Engineers the 
project was modified in March 1983 in accordance with 
the Water Supply Act of 1958, as amended, and the Flood 
Control Act of 1944, as amended. The modification provides 
for reallocating 25,600 acre-feet of present flood 
control storage for water supply storage by raising the 
permanent pool from elevation 1045 to 1080 mean sea 
level. Other features include modifyying the existing 
intake tower, the dam's filter blanket and two access 
ramps, stabilizing the reservoir slope near the relocated 
Town of Nelson, replacing existing day-use recreation 
facilities, and expanding both day-and overnight-use 
recreation facilities to accommodate an expected increase 
in annual visitation due to the larger pool. 
Estimated cost (October 1983) of the modification is 
$70,600,000 of which $1,400,000 is Federal (for expanded 
recreation facilities) and $69,200,000 is non-Federal 
(which includes $55,020,000 for reimbursement of the 
cost of existing flood control storage reallocated to water 
supply storage, $12,780,000 cash contribution for the 
water supply modification, and $1,400,000 cash contribution 
for expanded recreation facilities). 
Local cooperation. The Water Resources Development 
Act of 1976, which authorized relocation of the Town of 
Nelson, provides that before the Secretary of the Army 
acquires any real estate property for the new townsite appropriate 
non-Federal interests shall furnish binding contractual 
commitments that all lots in the new townsite 
will be either occupied when available, will be replacements 
for open space and vacant lots in the existing 
town, or will be purchased by non-Federal interests at the 
fair market value. The required contractual agreement 
for local cooperation was executed with Nelson Township 
on August 25, 1977. The March 1983 project modification 
(discussed above) requires non-Federal interests 
repay 100 percent of the investment cost of project 
modifications allocated to water supply, to terrestial 
wildlife habitat mitigation, and to in-kind replacement 
recreation, plus the allocated share of the project's 
original cost (escalated to current price levels). Additionally, 
they are required to pay annual costs of operation, 
maintenance, and major replacements allocated to 
water supply and to provide 50 percent of the cost of expanded 
recreation facilities as well as all operation, 
maintenance, and replacement costs for the expanded 
facilities. 
Operations and results during fiscal year. New Work: 
Construction of the Tompkins boat launch was completed. 
Preparation of the operation and maintenance 
manual continued. 
Maintenance: Normal operation and maintenance of 
the project continued. With Jobs Act funds, a fence was 
relocated, and a treewalk and bridge within the campground 
were constructed. 
38B. TIOGA-HAMMOND LAKES, PA 
Location. The dams are located in Tioga County, PA, 
upstream from the confluence of the Tioga River and 
Crooked Creek. Tioga Dam is located on the Tioga River 
and Hammond Dam on Crooked Creek, approximately 
opposite the Tioga damsite, about 3.3 miles above its 
mouth and less than one mile from the Village of 
Brooklyn. (See Geological Survey map for Tioga, PA.) 
Existing project. Tioga Dam is 2,600 feet long, rising 
140 feet above the streambed, with a controlled outlet 
conduit. Hammond Dam is 5,900 feet long, and has a 
maximum height of 121.5 feet above the streambed, with 
a concrete spillway. Both dams are of earth and rockfill 
construction. The Tioga-Hammond Lakes project controls 
a total drainage area of 402 square miles, with Tioga 
Dam controlling 280 square miles of the Tioga River 
Basin and Hammond Dam controlling 122 square miles 
of the Crooked Creek Basin. Recreation facilities are provided 
for swimming, camping, picnicking, boating, and 
fishing. Estimated Federal cost (October 1983) of new 
works is $192,870,000 of which $132,279,000 is for construction 
and $60,591,000 is for lands and damages and 
relocations. 
Local cooperation. None required. However, construction 
of the Mill Creek Area recreation facilities has 
been deferred indefinitely until such time local interests 
agree to bear one-half of the construction costs and all of 
the operation and maintenance costs for those facilities. 
4-19

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Operations and results during fiscal year. New work: 
Work on the operation and maintenance manual continued. 
Maintenance: Normal operation and maintenance of 
the project continued. With Jobs Act funds, a sewage 
treatment plant was insulated, a streambank was 
stabilized, miscellaneous buildings were repaired, and an 
archery range, and baseball field were constructed. 
39. WEST BRANCH OF 
SUSQUEHANNA RIVER, PA 
A system of three flood control reservoirs, in the headwaters 
of the West Branch Susquehanna River, PA, are 
known as Curwensville, Alvin R. Bush, (formerly known 
as Kettle Creek), and Foster Joseph Sayers (formerly 
known as Blanchard), on the West Branch about 2.5 
miles upstream from Curwensville, PA; on Kettle Creek 
8.4 miles above the mouth and 17 miles upstream from 
Renovo, PA; and on Bald Eagle Creek about one mile 
upstream from Blanchard, PA, respectively. 
In accordance with the terms of local cooperation, the 
Commonwealth of Pennsylvania furnished assurances 
that it will coordinate operation of George B. Stevenson 
Reservoir, (formerly known as First Fork Reservoir), 
with operation of Curwensville, Alvin R. Bush, and 
Foster Joseph Sayers Reservoirs to secure optimum 
flood control benefits from system operation. George B. 
Stevenson Reservoir on the First Fork Sinnemahoning 
Creek in Cameron and Potter Counties, PA, was constructed 
by the Commonwealth of Pennsylvania at a first 
cost of $12,240,000 and an estimated $30,000 annually 
for operation and maintenance. 
39A. ALVIN R. BUSH DAM, PA 
Location. Alvin R. Bush Dam (formerly Kettle Creek 
Dam) is located on Kettle Creek about 8.4 miles above the 
mouth and 15 miles upstream from Renovo, PA. (See 
Geological Survey map for Keating, PA.) 
Existing project. Dam is an earthfill structure, about 
1,350 feet long, rises 165 feet above the streambed, with 
an uncontrolled spillway located in rock adjacent to the 
right abutment, and has a horseshoe-shaped outlet tunnel 
with 3 service gates. The reservoir has a storage 
capacity of 75,000 acre-feet at spillway crest. The project 
controls a drainage area of 226 square miles or about 92 
percent of the Kettle Creek watershed. 
Local cooperation. None required. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the project 
continued. A contract modifying a bypass valve in 
the outlet works was awarded September 13, 1983. 
39B. CURWENSVILLE LAKE, PA 
Location. Dam is on the West Branch of the Susquehanna 
River approximately 2.5 miles upstream from 
Curwensville, Clearfield County, PA. (See Geological 
Survey map for Curwensville, PA.) 
Existing project. Dam is an earthfill structure, about 
1,850 feet long, rises 131 feet above the streambed, and 
has an open-cut concrete sill 1,750 feet from the left abutment. 
The outlet works, located in the left abutment, consist 
of a 15-foot diameter circular outlet conduit with 3 
slide control gates 5.5 feet wide and 12 feet high. The 
reservoir has a storage capacity of 124,200 acre-feet at 
spillway crest. The project controls a drainage area of 
365 square miles, or about 98 percent of the West Branch 
Susquehanna River at Curwensville and about 75 percent 
at Clearfield. Recreation facilties include a seasonal 
recreational pool of 790 acres, access roads, parking 
areas, beach area, boat dock, and launching ramp. 
Local cooperation. None required. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of project 
continued. 
39C. FOSTER JOSEPH SAYERS DAM, PA 
Location. Dam is located on Bald Eagle Creek in Centre 
County, PA, about one mile upstream from Blanchard 
and about 14 miles above the confluence of Bald Eagle 
Creek with the West Branch Susquehanna River at Lock 
Haven, PA. (See Geological Survey map for Howard, 
PA.) 
Existing project. Dam is an earthfill structure, about 
6,835 feet long, rises 100 feet above the streambed, and 
has an open-cut concrete chute and uncontrolled concrete 
weir 600 feet wide located in rock in a saddle adjacent to 
the left abutment. The outlet works, located in the left 
abutment, consist of a 15-foot diameter circular outlet 
conduit with two hydraulically-operated wheel gates 7 
feet wide and 15 feet high. The reservoir has a storage 
capacity of 99,000 acre-feet at spillway crest. The project 
controls a drainage area of 339 square miles or 88 percent 
of the drainage area above Beech Creek and 43 percent of 
the Bald Eagle Creek drainage area. Recreation facilities 
include a summer recreation pool of 1,730 acres, a conservation 
pool of 630 acres for the preservation of fish 
life, access roads, parking areas, boat docks and launching 
ramps, and camping areas. 
Local cooperation. None required. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the project 
continued. 
40. WYOMING VALLEY, PA 
Location. The project is located in Luzerne County, 
PA, on the Susquehanna River. The project area is 
limited to the four existing Federal flood control projects. 
These levee improvements are in Plymouth, 
Kingston-Edwardsville, Swoyersville-Forty Fort, and 
Wilkes-Barre and Hanover Township. 
Existing project. The four projects were constructed 
during the period 1935 through 1976 and consist of levee, 
4-20

BALTIMORE, MD DISTRICT 
sheet piling, floodwall, and associated interior drainage 
structures along both banks of the Susquehanna River 
which provide flood control benefits estimated at $46.1 
million annually. Remedial measures to protect against 
levee failure under future high discharge conditions consist 
of: weighted filter drains on the landside of the levees 
to protect against erosion due to seepage in certain areas; 
stability berms and toe protection on the riverside of the 
levees in certain areas to stabilize the riverbank and protect 
against erosion due to river flows; stabilization of 
sheet piling in certain areas; and additional relief wells to 
control the underseepage in other areas. 
Local cooperation. Lands and relocations for construction 
of the existing projects at an estimated cost of 
$1,000,000 were provided by the Boroughs of Kingston, 
Edwardsville, Plymouth, the City of Wilkes-Barre, 
Hanover Township, and Luzerne County. These entities 
also operate and maintain the existing projects. Updated 
assurances were obtained during preparation of the 
General Design Memorandum. Additional local costs in 
connection with the proposed remedial work are expected 
to be minor. 
Operations and results during fiscal year. General 
Design Memorandum studies were completed. A contract 
for stabilizing sheet piling at Wilkes-Barre and Forty 
Fort was awarded July 22, 1983, and a contract for 
stability berm and dug toe work at Wilkes-Barre was 
awarded July 27, 1983. 
41. YORK, INDIAN ROCK DAM, PA 
Location. On Codorus Creek 10 miles above its confluence 
with the Susquehanna River. Codorus Creek has 
tributary branches in York County in the south and central 
parts of Pennsylvania (See Geological Survey 
Quadrangle sheets: Pennsylvania-York and Hanover.) 
Existing project. Indian Rock Dam, is an earth and 
rockfill dam about 1,000 feet long at the top, rising 83 
feet above the streambed, with a reservoir providing for 
control storage of 28,000 acre-feet. Dam is on the main 
branch of Codorus Creek about 3 miles above York. Outlet 
works are in the right abutment and the uncontrolled 
spillway is on the right bank. Reservoir will control entire 
drainage area of the main branch of Codorus Creek and 41 
percent of the drainage area above York. Improvements 
in Codorus Creek in the vicinity of and through the City 
of York provide for 22,969 feet of channel extending from 
300 feet above Richland Avenue to a point downstream 
from the Pennsylvania Railroad crossing known as Black 
Bridge. Improvements, which will increase channel 
capacity to 24,000 cubic feet per second, include widening 
and deepening the channel, bank protection, removal 
of York Roller Mill Dam, and a low water channel about 
3,900 feet long in the vicinity of York Roller Mill Dam. 
Cost of new work for the completed project was 
$5,061,167, of which $4,566,446 (regular funds) and 
$11,588 (emergency relief funds) were for construction 
and $483,133 (regular funds) was for lands and damages. 
Local cooperation. Section 2, Flood Control Act of 
June 28, 1938, applies. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the project 
continued. 
42. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Projects in New York, Pennsylvania, Maryland, 
District of Columbia, and Virginia were inspected during 
the period by hired labor. See Table 4-I. 
43. SCHEDULING FLOOD CONTROL 
RESERVOIR OPERATIONS 
Operations and results during fiscal year. The operation 
of George B. Stevenson Dam, PA, was coordinated 
with the operation of Alvin R. Bush, Curwensville, and 
Foster Joseph Sayers Dams in the West Branch Susquehanna 
River Basin in order to secure optimum flood 
control benefits from the system operation. Costs during 
the period were $23,608. 
Supplemental instructions for the operation of Savage 
River Dam, MD, were provided, during periods of high 
water, to insure maximum protection for downstream 
localities. Costs during the period were $65,605. 
44. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Emergency flood control activities-repair, flood 
fighting, and rescue work (Public Law 99, 84th Congress, 
and antecedent legislation). 
Fiscal year costs were $142,066 for the Disaster Preparedness 
Program. 
Flood control activities pursuant to Section 205, 
Public Law 858, 80th Congress, as amended (preauthorization). 
Fiscal year costs were $56,459 for Conklin-Kirkwood, 
NY. Nonstructural study and $14,685 for Herring Creek, 
MD. 
Water Supply 
45. POTOMAC ESTUARY PILOT 
WATER TREATMENT PLANT, DC 
Location. The project is located in Washington, DC, on 
the north side of the District of Columbia's Water Pollution 
Control Plant (Blue Plains), about 600 feet east of 
the Potomac River shoreline. 
4-21

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Existing project. The project consists of a water treatment 
plant with a maximum capacity of one million 
gallons per day that includes advanced treatment processes 
and an evaluation laboratory. 
Local cooperation. On June 28, 1977 the Government 
of the District of Columbia issued a real estate permit for 
the construction of the pilot plant on 1.5 acres of land 
available at the Blue Plains wastewater treatment facility 
in Washington, DC. A review during preconstruction 
planning determined that cost sharing for the pilot plant 
by local governmental entities is not required. 
Operations and results during fiscal year. New work: 
The two year operation and evaluation program, which 
started March 16, 1981 was completed March 16, 1983. 
Preparation of the final report on the feasibility of using 
the Potomac Estuary as a source of potable water supply 
was completed and the plant was deactivated. 
46. WASHINGTON AQUEDUCT 
Location. The diversion dam and raw water supply intakes 
at Great Falls, the two collecting conduits, part of 
Dalecarlia receiving reservoir, the booster pumping station, 
and the Little Falls raw water pumping station are 
located in Maryland. All other structures of the water 
supply system including parts of the raw water collecting 
system, two purification plants, pumping stations, storage 
reservoirs, and transmission mains are in the District 
of Columbia. Federal owned water mains are maintained 
in Virginia and Maryland. 
Existing project. Control of the water supply system is 
vested in Chief of Engineers (See Acts of March 3, 1859, 
and March 2, 1867, November 22, 1973 and Sec. 1800 of 
Revised Statutes). The project includes: administration; 
operation and maintenance of the collection, purification, 
pumping, and transmission facilities; protection of the 
water supply system; engineering; and construction of 
major water system additions and improvements. 
Authority to supply water to Arlington County, the 
City of Falls Church, and other jurisdictions in Virginia 
is contained in Public Law 119, 69th Congress, approved 
April 14, 1926; and Public Law 118, 80th Congress, June 
26, 1947. 
Local cooperation. Requirements are described in full 
on page 4-19 of the Fiscal Year 1981 Annual Report. 
Operations and results during fiscal year: New Work: 
The McMillan Water Treament Plant Replacement work 
authorized with "no year" funds is 65% complete. 
Maintenance (operation): An uninterrupted and adequate 
supply of purified water was furnished to the 
District of Columbia; Arlington County, and Falls 
Church, Virginia; and to Federal establishments in the 
District of Columbia, Arlington County, Virginia and 
Montgomery and Prince Georges Counties in Maryland. 
Total consumption for Fiscal Year 1982 was 74,041 
million gallons; the maximum daily consumption was 
263 million gallons and average daily consumption was 
202.9 million gallons. The amount furnished Arlington 
County and Falls Church, Virginia was 38.9 million 
gallons per day. The Corps of Engineers was reimbursed 
in the amount of $3,324,365 for water furnished to the 
Virginia communities by the Washington Aqueduct. 
The treated water delivered to the 1.1 million consumers 
served by the Washington Aqueduct met or surpassed 
all Water Quality standards promulgated by the 
U.S. Environmental Protection Agency under the Safe 
Drinking Water Act (P.L. 93-523). 
General Investigations 
47. SURVEYS 
Costs for the period were $2,172,466 of which $12 was 
for navigation studies, $138,172 for flood damage prevention 
studies, $1,746,876 for special studies, $67,211 
for comprehensive basin studies, $218,212 for coordination 
with other agencies and non-Federal interests, and 
$1,983 for supplemental preauthorization (Phase I) 
studies. 
48. COLLECTION AND STUDY OF 
BASIC DATA 
Costs for flood plain management activities and 
general planning guidance during the period was 
$199,096. Providing assistance and guidance to local interests 
on methods and procedures for preventing and 
reducing flood damages was in progress at end of fiscal 
year. 
49. CONTINUATION OF PLANNING 
AND ENGINEERING 
Susquehanna Basin at Harrisburg, PA-The plan of 
improvement for the South Harrisburg area recommended 
in an interim report on the Susquehanna River 
Basin study includes a floodwall 3800 feet long, a pump 
station and floodgates for interior drainage, a dry detention 
dam along Asylum Run (a small tributary of Paxton 
Creek), an enlarged earth and concrete channel for 
Paxton Creek about four miles long, and minor recreation 
and fish and wildlife facilities. Preparation of a General 
Design Memorandum continued during the fiscal year. 
Estimated planning and engineering cost is $2,900,000. 
Total costs during the fiscal year were $524,038. 
Lock Haven, PA-The plan of improvement recommended 
in the Phase I General Design Memorandum includes 
24,500 feet of levee, 6,500 feet of floodwall, ten 
closure structures, four pumping stations, diversion of 
Lusk Run, and minor recreation facilities. Preparation of 
a Phase II General Design Memorandum was initiated 
during the fiscal year. Estimated planning and engineering 
cost is $1,700,000. Total costs during the fiscal year 
were $10,113. 
4-22

BALTIMORE, MD DISTRICT 
50. ADVANCED ENGINEERING 
AND DESIGN 
Francis E. Walter Dam, PA-Modification-The 
authorized project would provide for modifying the existing 
single purpose flood control project by raising the 
existing dam 29 feet thereby adding water supply and 
recreation purposes. Preparation of the combined 
General Design Memorandum continued during the 
fiscal year. Estimated preconstruction planning cost is 
$6,000,000. Total costs during the fiscal year were 
$1,065,871. 
Tamaqua, PA-The authorized project would provide 
for a 10-foot diameter diversion tunnel 2,930 feet long, 
that starts at Wabash Creek at the west boundary of 
Tamaqua and terminates at the Little Schuylkill River. 
The project also includes an intake structure, a stilling 
basin, a 70-foot long highway bridge, and a small dry 
detention reservoir on a tributary of Wabash Creek. 
Preparation of a Phase II General Design Memorandum 
was initiated during the fiscal year. Estimated preconstruction 
planning cost is $1,850,000. Total costs during 
the fiscal year were $595,285. 
4-23 
BALTIMORE, MD DISTRICT

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 4-A COST AND FINANCIAL STATEMENT 
See Total 
Section to 
in Text Project Funding FY 80 FY 81 FY 82 FY 83 Sept. 30,1983 
1. Baltimore Harbor 
and Channels, 
MD and VA 
2. Baltimore Harbor 
MD Collection 
& Removal of 
Drift 
3. Chester River, 
MD 
4. Fishing Creek, 
MD 
5. Honga River and 
Tar Bay, (Barren 
Island Gaps), MD 
6. Little Wicomico 
River, VA 
7. Lowes Wharf, 
MD 
8. Muddy Hook/ 
Tyler Cove, MD 
9. Nanticoke River 
at Bivalve, MD 
10. Nanticoke River 
(Including Northwest 
Fork), MD 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Contrib. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
25,000 
86,190 
4,287,438' 
3,799,863' 
197,089 
198,013 
5,879,000 
5,892,023 
2,795,109' 
3,277,146' 
151,300 
150,241 
33,997 
33,677 
3,626,349' 
2,657,421' 
248,200 
240,536 
54,000 
39,604 
17,174 
17,174 
12,339 
12,339 
3,825 
3,825 
57,881 
55,917 
54,390 
54,133 
11,600 
11,600 
1,397,000 
882,730 
277,244 
277,499 
35,707 
35,707 
213,500 
68,123 
28,750 
28,750 
1,300,000 
851,317 
5,769,000' 
6,568,755' 
45,626,7121 
45,168,419' 
37,474,86010 
37,298,03110 
177,000 2,644,210 
186,916 2,643,886 
- 70,495" 
- 70,495" 
5,000 1,111,473 
5,000 1,111,473 
- 111,242 
- 111,242 
318,636 
333,032 
859,199 
859,199 
66,1192 
66,119" 
-48,758 2,317,926 
467,475 2,317,925 
7,078 
7,079 
182,000 
48,900 
103,364 
214,054 
44,000 
30,000 
4,905 
4,905 
235,000 
214,055 
81,885" 
81,885" 
832,453 
832,453 
21,000 
21,000 
256,829 
123,729 
64,001 
64,001 
335,566 
300,879 
72,750 
58,750 
240,817" 
240,817" 
131,878 
131,878 
143,134"15 
143,134"1 
545,946 
525,002 
4-24

BALTIMORE, MD DISTRICT 
TABLE 4-A (Continued) COST AND FINANCIAL STATEMENT 
See Total 
Section to 
in Text Project Funding FY 80 FY 81 FY 82 FY 83 Sept. 30,1983 
11. Northeast River, 
MD 
12. Ocean City Harbor 
and Inlet and Sinepuxent 
Bay, MD 
13. Pocomoke River, 
MD 
14. Potomac River 
at Mt. Vernon, 
VA 
15. Potomac River 
below Washington, 
DC 
16. Potomac and 
Anacostia Rivers, 
DC, Collection & 
Removal of Drift 
17. Prevention of 
Obstructions & 
Injurious Deposits, 
Baltimore Harbor, 
MD 
18. Rhodes Point to 
Tylerton, MD 
19. St. George 
Creek, MD 
20. St. Patricks 
Creek, MD 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Contrib. 
Approp. 
Cost 
10,500 
10,500 
383,859 
383,859 
801,000 
797,873 
33,391 694,000 
33,390 131,173 
28,48916 
28,48916 
866,044 
303,216 
350,1937 
350,19317 
557,500 1,343,000 7,512,908 
480,186 251,452 6,340,919 
- 191,726" 
- 191,72618 
25,000 1,193,035 
25,000 1,193,035 
- 17,00014 
- 17,00014 
10,256 
10,256 
73,465 
73,465 
- 153,836 
- 153,836 
26,300 1,836,673 
26,300 1,836,673 
339,308 
403,024 
248,254 
248,254 
468,300 
452,506 
306,300 
306,191 
20,000 
16,121 
459,800 486,000 5,041,175 
467,292 493,074 5,039,947 
284,000 
243,179 
335,000 
74,181 
9,000 
- 4,159,040 
40,929 4,159,040 
-51,000 
213,698 
138,650 
38,137" 
2,934 
2,934 
304,000 
304,000 
231,424 
231,424 
147,650 
38,137 
15,752 
15,752 
11,622 
11,622 
1,000 
1,000 
4-25

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 4-A (Continued) COST AND FINANCIAL STATEMENT 
See Total 
Section to 
in Text Project Funding FY 80 FY 81 FY 82 FY 83 Sept. 30,1983 
21. Tilghman Island 
Harbor, MD 
22. Warwick River, 
MD 
23. Washington Harbor, 
DC 
24. Wicomico River, 
MD 
27. Colonial Beach, 
VA 
29. Black Walnut 
Point, MD 
29. Bloomington Lake, 
North Branch 
Potomac River 
MD & WV 
30. Bull Run, PA 
31. Cumberland, MD 
and Ridgeley, 
WV 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Contrib. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Contrib. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Contrib. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Contrib. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Contrib. 
Approp. 
Cost 
45,000 
45,574 
367,473 
367,473 
45,000 
33,845 
110,000 
50,439 
4,165 
1,144 
-27,000 
47,025 
-1,956 
1,065 
14,739 
14,739 
81,182 
81,182 
148,952 
151,063 
10,000 
23,402 
31,000 
28,444 
844,000 
831,869 
110,000 
72,424 
581,750 
109,910 
822,079 
330,789 
22,000 
21,999 
370,000 
350,926 
480,000 
370,299 
- 3,191,07721 
- 3,191,07721 
-19,000 4,480,71422,23 
440,826 4,466,14522,2 
824,730 5,098,73725 
547,075 4,317,66125 
- 55,000 
1 55,000 
-64,000 
-7,138 
-65,023 
44,678 
227,5002 227,500" 
37,679 37,679 
27,230,000 18,197,000 
26,746,695 16,978,570 
10,000 311,100 
3,990 316,897 
-350,000 1,473,000 
973,795 1,052,535 
- -260,000 
106,000 -106,000 
1,750,000 
2,928,555 
611,500 
599,866 
-60,000 
317,073 
1,688,000 
1,856,543 
893,200 
885,166 
174,480,300 
173,682,752 
1,825,800 
1,805,91927 
-73,000 2,769,000 
15,110 2,758,970 
- 15,633,97028 
- 15,633,97028 
28,591 
11,591 
37,900 
52,363 
54,000 
54,281 
64,600 
66,856 
- 1,402,001 
- 1,402,001 
4-26 
424,800 
424,800 
368,306 
368,306 
16,409 
16,409 
22,04120 
22,04120so 
106,267 
106,267 
471,60924 
471,60924 
504,000 
504,000 
414,977 
414,977 
477,299 
477,299

BALTIMORE, MD DISTRICT 
TABLE 4-A (Continued) COST AND FINANCIAL STATEMENT 
See Total 
Section to 
in Text Project Funding FY 80 FY 81 FY 82 FY 83 Sept. 30,1983 
32. Fourmile Run, VA 
33A. Aylesworth Creek 
Lake, PA 
34. Latta Brook 
Rd., NY 
35. Raystown Lake, 
Raystown Branch, 
Juniata River, PA 
36A. Addison, NY 
36B. Almond Lake, 
NY 
36C. Arkport Dam, NY 
36D. Avoca, NY 
36E. Binghamton, NY 
36F. Canisteo, NY 
New Work 
Approp. 
Cost 
Contrib. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
3,374,000 
3,334,501 
716,566 
737,930 
666,000 2,735,000 -157,300 
616,904 2,272,844 429,544 
- - 208,074 
67,299 - 208,074 
51,780,000 
51,750,706 
3,132,916 
3,130,857 
- 2,320,400 
- 2,320,400 
153,335 
83,214 
49,700 
119,729 
55,400 
48,757 
67,000 
71,631 
676,177 
673,464 
- - - 135,500" 135,500" 
- - - 37,942 37,942 
- - - - 77,408,700 
111,363 - - - 77,408,700 
1,249,700 1,503,300 1,934,238 2,423,056 11,792,795 
1,243,020 1,348,765 2,053,846 2,447,276 11,755,272' 
9,981 
9,981 
167,543 
166,122 
54,439 
55,397 
10,225 
10,225 
17,197 
17,197 
21,561 
24,134 
21,377 
14,814 
122,600 
124,646 
165,700 
151,227 
23,100 
22,911 
27,900 
25,193 
41,100 
38,538 
20,600 
27,109 
233,600 
221,471 
118,400 
126,940 
23,400 
22,701 
11,100 
13,726 
37,681 
38,020 
- 827,050 
- 827,050 
12,900 130,806 
12,879 130,731 
- 5,760,211 
- 5,760,211 
221,000 2,248,568 
230,101 2,244,417$1 
- 1,910,00082 
- 1,910,00032 
180,800 1,234,111 
178,847 1,225,225 
- 436,37433 
- 436,374" 
15,900 314,535 
16,788 314,535 
- 2,952,00084 
- 2,952,0008 
34,300 332,281 
34,283 332,183 
- 1,183,111" 
- 1,183,11188 
38,100 512,961 
40,321 512,359 
4-27

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 4-A (Continued) COST AND FINANCIAL STATEMENT 
See Total 
Section to 
in Text Project Funding FY 80 FY 81 FY 82 FY 83 Sept. 30, 1983 
36G. Corning, NY 
36H. East Sidney Lake, 
NY 
36I. Elmira, NY 
36J. Hornell, NY 
36K. Lisle, NY 
36L. Oxford, NY 
36M. Whitney Point 
Lake, NY 
36N. Whitney Point 
Village, NY 
37. Stillwater Lake, 
Lackawanna 
River, PA 
38A. Cowanesque Lake, 
PA 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
24,606 
24,606 
149,088 
149,174 
43,900 
43,881 
151,500 
153,272 
44,300 
41,993 
187,600 
172,623 
-5,000 
12,519 
12,519 
664,200 
277,799 
28,081 
28,081 
-_ 
8,536 
8,536 
122,667 
117,866 
10,582 
10,582 
88,204 
88,943 
10,913,000 
10,679,151 
90,700 
82,245 
18,100 
13,994 
60,800 
481,037 
32,300 
30,241 
21,624 
21,624 
161,500 
167,763 
22,900 
18,780 
111,000 
111,920 
2,878,000 
2,438,893 
481,200 
482,553 
15,700 
16,342 
148,419 
150,972 
35,700 
33,824 
12,400 
9,863 
235,900 
195,765 
24,700 
25,794 
114,500 
111,732 
270,000 
1,040,052 
675,350 
680,662 
- 3,322,000k 
- 3,322,000 
24,800 523,558 
27,126 523,558 
- 6,049,504 
- 6,049,504 
347,500 2,555,101 
359,826 2,552,295 
- 6,883,305 
- 6,883,305 
22,800 
26,264 
189,949 
189,949 
- 4,558,6983' 
- 4,558,6983' 
348,200 2,663,012 
257,415 2,572,005 
- 661,19938 
- 661,19938 
22,500 570,822 
26,382 570,769 
- 131,00039 
- 131,00039 
11,200 
13,737 
155,932 
155,932 
- 5,421,539 
- 5,421,539 
259,500 2,880,497 
300,269 2,880,262 
- 424,096 
- 424,096 
26,300 251,561 
29,273 251,508 
- 5,725,700 
- 5,725,700 
158,600 1,429,169 
161,139 1,428,823 
168,891 
851,200 
833,587 
106,030,700 
105,963,442 
2,098,450 
2,079,04740 
4-28

BALTIMORE, MD DISTRICT 
TABLE 4-A (Continued) COST AND FINANCIAL STATEMENT 
See Total 
Section to 
in Text Project Funding FY 80 FY 81 FY 82 FY 83 Sept. 30, 1983 
38B. Tioga-Hammond New Work 
Lakes, PA Approp. 7,455,000 355,000 -30,000 -220,000 185,679,800 
Cost 7,194,556 292,233 286,038 79,419 185,596,313 
Maint. 
Approp. 646,324 819,900 1,095,864 1,269,200 4,439,865 
Cost 656,397 817,049 1,019,593 1,331,830 4,417,086" 
39A. Alvin R. Bush Dam, New Work 
PA Approp. - - - - 7,103,001 
Cost - - - - 7,103,001 
Maint. 
Approp. 135,880 200,600 330,300 488,800 2,836,512 
Cost 142,132 200,761 237,872 413,472 2,667,417 
39B. Curwensville Lake, New Work 
PA Approp. - - - - 20,396,060 
Cost - - - - 20,396,060 
Maint. 
Approp. 510,821 236,400 543,000 360,500 4,464,798 
Cost 519,199 232,284 546,095 361,923 4,463,758 
39C. Foster Joseph New Work 
Sayers Dam, PA Approp. - - - - 30,887,0632 
Cost - - - - 30,887,063"2 
Maint. 
Approp. 331,200 314,000 345,547 412,000 3,563,062 
Cost 266,444 383,567 342,872 412,339 3,560,110 
40. Wyoming Valley, New Work 
PA Approp. - - 800,000 2,390,000 16,415,000 
Cost - - 667,635 1,388,786 15,311,421 
41. York, Indian Rock New Work 
Dam, PA Approp. - - - - 5,061,167" 
Cost - - - - 5,061,167' 
Maint. 
Approp. 279,952 248,100 290,700 294,800 3,411,873" 
Cost 281,082 248,152 267,909 312,558 3,405,679" 
45. Potomac Estuary New Work 
Pilot Water Treat- Approp. 2,100,000 3,500,000 4,200,000 3,074,000 21,270,000 
ment Plant, DC Cost 1,891,094 3,193,963 4,570,942 2,780,850 20,215,431 
1. Includes $8,764,003 for previous projects. 
2. Includes $32,000 for sections of project in Norfolk 
District. 
3. Includes $30,931 for sections of project in Norfolk 
District. 
4. Includes $14,109 for sections of project in Norfolk 
District. 
5. Includes $15,177 for sections of project in Norfolk 
District. 
6. Includes $1,663,300 for sections of project in Norfolk 
District. 
7. Includes $696,090 for sections of project in Norfolk 
District. 
8. Includes $1,085,000 for sections of project in Norfolk 
District. 
9. Includes $1,885,518 for sections of project in Norfolk 
District. 
10. Includes $399,802 for previous projects. 
11. Includes $38,041 for previous project. 
12. Excludes $2,200 contributed and includes $27,668 
emergency relief funds. 
13. Excludes $5,000 contributed funds. 
14. Unconstructed portion of the project was deauthorized 
November 2, 1979. 
15. Includes $5,000 for previous project. 
16. Includes $20,640 for previous projects. 
17. Includes $283,008 public works funds and $67,185 
emergency, relief funds; excludes $500,000 contributed funds. 
18. Unconstructed portion of the project is inactive. Includes 
$20,500 for previous project. 
19. Includes $96,150 for Jobs Act funds, 1983 (P.L. 98-8). 
20. Includes $6,000 for previous project. 
21. Includes $3,029,001 for previous project. 
22. Includes $1,831,609 for previous project. 
23. Excludes $4,000 for emergency dredging under provisions 
of Section 3, 1945 River and Harbor Act. 
24. Includes $50,000 for previous project and excludes 
$14,000 contributed funds. 
25. Includes $99,999 for Jobs Act funds, 1983 (P.L. 98-8). 
26. Includes $185,000 for Jobs Act funds, 1983 (P.L. 
98-8). 
27. Includes $21,994 for Jobs Act funds, 1983 (P.L. 98-8). 
28. Includes $49,998 emergency relief funds. 
29. Includes $88,000 for Jobs Act funds, 1983 (P.L. 98-8). 
30. Includes $221,932 for Jobs Act funds, 1983 (P.L. 
98-8). 
31. Includes $22,558 for Jobs Act funds, 1983 (P.L. 98-8). 
32. Includes $62,577 emergency relief funds. 
4-29

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
33. Includes $109,944 emergency relief funds. 
34. Excludes $163,096 contributed funds. 
35. Includes $207,520 rehabilitation funds. 
36. Excludes $34,729 contributed funds. 
37. Includes $250,899 emergency relife funds and excludes 
$15,000 contributed funds. 
38. Includes $71,557 emergency relief funds. 
39. Includes $73,465 emergency relief funds. 
TABLE 4-B AUTHORIZIN 
See Date 
Section Authorizing 
in Text Act Project and W( 
40. Includes $28,931 for Jobs Act funds, 1983 (P.L. 98-8). 
41. Includes $87,075 for Jobs Act funds, 1983 (P.L. 98-8). 
42. Excludes $263,900 contributed funds in accordance 
with the Tri-party Agreement for construction of sanitary 
system for public use. 
43. Includes $11,588 emergency relief funds. 
44. Includes $15,000 for deferred maintenance. 
G LEGISLATION 
ork Authorized Documents 
Aug. 8, 
1917 
Jan. 21, 
1927 
Jul. 3, 
1930 
BALTIMORE HARBOR AND CHANNELS, MD and VA 
Branch channel 35 feet deep to head of Curtis Bay, and one 35 feet deep and 
400 feet wide from Fort McHenry to Port Covington entrance channel, 
thence 150 feet wide to Ferry Bar, and thence 27 feet deep and 150 feet 
wide to Hanover Street Bridge, widen approaches and bends, and enlarge 
anchorage basin near entrance. Inclusion of Patapsco River and tributaries 
into one project for Baltimore Harbor.2 
Change in location of anchorage near upper end of Fort McHenry Channel. 
Increased anchorage facilities. 
Jul. 3, For 37-foot depth in that portion of channel to Baltimore lying between 37-foot 
1930 depth curve near Baltimore Light to Sparrows Point entrance channel; widen 
angle between Fort McHenry and Ferry Bar Section; and for width of 400 
feet in Curtis Bay section. 
Oct. 17, For 22-, 18-, and 15-foot channels in Curtis Creek from 22-foot depth below 
1940 Pennington Ave. Bridge to upper end of marginal wharf of U.S. Ordnance 
Depot. 
Mar. 2, Uniform main channel 39-feet deep from the ocean through York Spit section 
1945 and Craighill entrance to Fort McHenry, additional anchorage area, 2,400 
feet long, 1,200 feet wide, and 30 feet deep; a connecting channel 400 feet 
wide and 27 feet deep from Cutoff Brewerton Angle in main channel to Inland 
Waterway from Delaware River to Chesapeake Bay; a channel in Curtis 
Creek 200 feet wide and 35 feet deep from head of existing 35-foot project 
channel in Curtis Bay to a point in the creek about 750 feet below Pennington 
Ave. Bridge. 
Mar. 2, A channel 22 feet deep and 200 feet wide from 22-foot depth curve south of 
1945 Baltimore & Ohio R.R. bridge about 2,800 feet to vicinity of Arundel Cove, 
thence 100 feet wide in Arundel Cove for about 2,100 feet; with an anchorage 
basin about 700 feet square adjacent to channel southwesterly of Coast 
Guard wharf. 
July. 3, Main channel 42 feet deep and 1,000 feet wide in Cape Henry section at 
1958 entrance to Chesapeake Bay and in York Spit section; 42 feet deep and 800 
feet wide in Rappahannock Spit section and in approach channel to Baltimore 
Harbor from Craighill entrance to Fort McHenry, with widening at entrance 
and bends; channels 42 feet deep and 600 feet wide in Curtis Bay and Ferry 
Bar sections of harbor; a connecting channel 35 feet deep and 600 feet wide 
from main channel to approach channel to Chesapeake and Delaware Canal; 
and for three disjointed sections of channels of same depth and width in 
Chesapeake Bay leading to Chesapeake and Delaware Canal; and to 
provide Federal maintenance of 39-foot depth in Northwest Branch, in areas 
dredged to that depth by local interests. 
H. Doc. 799, 
64th Cong., 1st sess. 
Rivers and Harbors 
Committee Doc. 11, 
70th Cong., 1st sess. 
H. Doc. 86, 85th 
Cong., 1st sess. 
Adopted as a national 
defense project. (No 
printed report.) 
H. Doc. 741, 
79th Cong., 2nd sess. 
In accordance with 
plans on file in the 
Office, Chief of 
Engineers. 
H. Doc. 86, 
85th Cong., 1st sess. 
4-30

BALTIMORE, MD DISTRICT 
TABLE 4-B (Continued) AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Dec. 31, Deepening of the Cape Henry Channel to 50 feet at the existing width of 
1970 1,000 feet, with widening at bends; deepening of the Spit Channel to 50 feet 
at the existing width of 1,000 feet, with widening at bends; enlargement of 
the Rappahannock Shoal Channel to a depth of 50 feet and a width of 1,000 
feet; deepening of the main ship channel from Chesapeake Bay to Fort 
McHenry to a depth of 50 feet at the existing width of 800 feet, with widening 
at bends and at the Craighill Entrance; deepening of the Curtis Bay Channel 
to a depth of 50 feet at the existing width of 600 feet, and deepening of the 
950-foot wide and 980-foot long turning basin at the head of channel to the 
same depth; deepening of the Northwest Branch-East Channel to a depth 
of 49 feet from the depth existing at the time of construction at a width of 
600 feet, and deepening of the 950-foot wide and 950-foot long turning basin 
at the head of the channel to the same depth; and deepening and extension 
of the Northwest Branch-West Channel to a depth of 40 feet from the 
depth existing at the time of construction, at a width of 600 feet, and with 
an irregularly shaped turning basin at the head of the channel 40 feet deep 
and about 2,000 feet long with a maximum width of 1,150 feet. 
BALTIMORE HARBOR, MD-COLLECTION AND REMOVAL OF 
DRIFT 
Jun. 30, Collection and removal of drift from Baltimore Harbor and its tributary 
1948 waters. 
3. 
Mar 3, 
1873 
Sep. 19, 
1890 
Jun. 30, 
1948 
CHESTER RIVER, MD 
A channel 7 feet deep at mean low water and 100 feet wide from Chester River 
to Eastern Bay through Kent Island Narrows. 
A channel 6 feet deep at mean low water and 60 feet wide from Crumpton to 
Jones Landing. 
A channel 7 feet deep at mean low water and 75 feet wide extending from the 
7-foot depth in Kent Island Narrows 800 feet into Wells Cove with a basin 
of the same depth and 300 feet square at the head of the channel. 
FISHING CREEK, MD 
Aug. 26, A channel 7 feet deep with widths of 100 feet and 60 feet from deep water in 
1937 Chesapeake Bay to an anchorage of the same depth, 120 feet wide 
and 400 feet long, located in the marsh 500 feet above the mouth of the 
creek and twin stone jetties at the entrance. 
HONGA RIVER AND TAR BAY (BARREN ISLAND GAPS), MD 
Aug. 30, Channel 60 feet wide and 7 feet deep from the 7-foot contour in Chesapeake 
1935 Bay through Tar Bay and Fishing Creek to the 7-foot contour in Honga 
River. 
Jun. 30, Modification providing for a channel in Back Creek 7 feet deep and 60 feet 
1948 wide from the 7-foot depth curve in Honga River to a point near the head of 
Back Creek, with a turning basin of the same depth, 150 feet long and 200 
feet wide. 
LITTLE WICOMICO RIVER, VA 
Aug. 30, A channel 8 feet deep and 150 feet wide from Potomac River to deep water in 
1935 Little Wicomico River; two stone jetties 1,000 feet and 1,300 feet long at the 
entrance; and 1,004 linear feet of timber bulkhead to stabilize the dredged 
inner channel. 
LOWES WHARF, MD 
Sep. 3, A channel 60 feet wide and 7 feet deep at mean low water from the 7-foot 
1954 depth curve in Ferry Cove and to including a basin of the same depth, 200 
feet wide and 300 feet long on the south side of Lowes Wharf. 
8. 
Dec. 4, 
1964 
Sec. 107 
Jul. 14, 
1960 
MUDDY HOOK/TYLER COVE, MD 
An entrance channel 60 feet wide and 6 feet deep from that depth in Honga 
River to and including an anchorage basin of same depth, 160 feet wide and 
400 feet long, in Fishing Creek into Tyler Cove and includes an anchorage 
basin 200 feet wide, 250 feet long and 6 feet deep. 
H. Doc. 181, 
94th Cong., 1st sess. 
River and Harbor Act 
of 1948. 
E. Doc. 25, 
42d. Cong., 3d sess. 
H. Ex. Doc. 65, 
51st. Cong., 1st sess. 
H. Doc. 380, 
80th Cong., 1st sess.' 
H. Doc. 241, 
75th Cong., 1st sess. 
Rivers and Harbors 
Committee, Doc. 35, 
74th Cong., 1st sess. 
H. Doc. 580, 
80th Cong., 2nd sess.' 
Rivers and Harbors 
Committee Doc. 24, 
74th Cong., 1st sess. 
H. Doc. 90, 
82d Cong., 1st sess.' 
Detailed Project 
Report, 
May 1964 
4-31 
2. 
4. 
5. 
6. 
7.

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 4-B (Continued) AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
NANTICOKE RIVER AT BIVALVE, MD 
Sep. 3, An Anchorage basin in Jackson Gut 7 feet deep, 150 feet wide and 350 feet 
1954 long initially with ultimate length 550 feet and approach channel of same 
depth 60 feet wide and about 1,400 feet long, protected by twin stone jetties. 
10. 
Jun. 3, 
1896 
Jun. 25, 
1910 
Mar. 2, 
1945 
NANTICOKE RIVER (INCLUDING NORTHWEST FORK), DE & MD 
A 9-foot channel, 100 feet wide up to Seaford, DE, with a turning basin. 
and Annual Report, 
1985, p. 1165. 
Slight widening between bridges in harbor at Seaford, DE. 
A channel 6 feet deep, 60 feet wide in Northwest Fork, together with turning 
basin. 
A channel 12 feet deep, 100 feet wide from 12-foot contour in Tangier Sound to 
highway bridge at Seaford, DE. 
NORTHEAST RIVER, MD 
Aug. 26, Channel 60 feet wide and 7 feet deep from that depth in the river to the foot 
1937 of Church Street in the town of North East, enlarged at its upper end to 
form a basin 120 feet wide and 300 feet long. 
OCEAN CITY HARBOR & INLET & SINEPUXENT BAY, MD 
Aug. 30, Construction of an inlet between the Atlantic Ocean and Sinepuxent Bay, 
1935$ 10 feet deep and 200 feet wide, protected by jetties; a channel 8 feet deep 
and 100 feet wide from the inlet to Ocean City, 6 feet deep and 150 feet 
wide to Green Point, and 100 feet wide into Chincoteague Bay. 
Aug. 30, Modification providing a 10-foot by 100-foot channel from the inlet to the 
1935' west side of the bay with 2 turning basins; a channel 6 feet deep and 125 
feet wide from the inlet channel to opposite North 8th Street, Ocean City, 
and 75feet wide into Isle of Wight Bay. 
Sep. 3, Modification providing for raising the north jetty to an elevation 9 feet above 
1945' mean low water, and a channel 300 feet wide and 16 feet deep from the ocean 
through the inlet to the Isle of Wight Bay channel, thence 200 feet to the 
project harbor, and a depth of 14 feet in the project harbor. Channel depths 
refer to project datum. 
13. 
Jun. 3, 
1896 
Aug. 30, 
1935 
Mar. 2, 
1945 
Sep. 3, 
1954 
POCOMOKE RIVER, MD 
A 9-foot channel from Shad Landing to Snow Hill. 
A channel 7 feet deep and 100 feet wide from Pocomoke Sound to Pocomoke 
River. 
Extend channel above bridge at Snow Hill, 100 feet wide, 9 feet deep, widened 
to 150 feet to form a turning basin at upper end. 
Channel 11 feet deep by 150 feet wide from Pocomoke Sound to Tulls Point, 
thence a channel of the same depth and 100 feet wide to deep water in Pocomoke 
River above Williams Point, and dike construction along south side of 
channel from existing dike to Tulls Point. 
POTOMAC RIVER AT MT. VERNON, MD 
Mar. 3, Channel 6 to 7 feet deep, 150 feet wide, from Potomac River channel to Mount 
1879 Vernon wharf, with turning basin at wharf. 
Channel increased to 9- to 10-foot depth, 200-foot width, turning basin to have 
200-foot radius. 
POTOMAC RIVER BELOW WASHINGTON, DC 
Mar. 3, A channel 24 feet deep and 200 feet wide between mouth at Chesapeake Bay 
1899 and Giesboro Point at Washington, DC, a distance of 108 miles. 
H. Doc. 91, 
82nd Cong., 1st sess.' 
H. Doc. 323, 
53d Cong., 3rd sess., 
H. Doc. 674, 
61st Cong., 2nd sess. 
H. Doc. 869, 
60th Cong., 1st sess. 
S. Doc. 69, 
77th Cong., 1st. sess. 
H. Doc. 248, 
75th Cong., 1st sess. 
Rivers and Harbors 
Committee Doc. 38, 
72d Cong., 1st sess. 
Rivers and Harbors 
Committee Doc. 60, 
74th Cong., 1st sess. 
H. Doc. 444, 
82d Cong., 2nd sess. 
Annual Report for 
1895, p. 1167. 
H. Doc. 227, 
74th Cong., 1st sess.' 
H. Doc. 429, 
76th Cong., 1st sess.' 
H. Doc. 486, 
81st Cong., 2d sess.' 
Annual Report, 1879, 
vol. 1, p. 83. 
Annual Report, 1888, 
vol. 1, p. 814. 
H. Doc. 33, 
52nd Cong. 1st sess. 
4-32 
9. 
11. 
12. 
14. 
15.

BALTIMORE, MD DISTRICT 
TABLE 4-B (Continued) AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
POTOMAC & ANACOSTIA RIVERS, DC-COLLECTION & 
REMOVAL OF DRIFT 
Oct. 27, Collection and removal of drift from waters of the Potomac and Anacostia 
1965 Rivers and their tributaries in the Washington, DC area from the head of 
the tidewater to Mount Vernon, Virginia. 
PREVENTION OF OBSTRUCTIONS & INJURIOUS DEPOSITS, 
BALTIMORE HARBOR, MD 
Aug. 28, Continuous patrol and inspection of Baltimore Harbor, Chesapeake Bay, and 
1958 its tributaries to prevent and detect violations, and issue permits as required 
for transporting and depositing waste materials in navigable waters. (The 
project is limited to the tidal waters of Chesapeake Bay and its tributaries 
that lie within the State of Maryland.) 
18. 
Jan. 22, 
1982 
Sec. 107 
Jul. 14, 
1960 
Sep. 3, 
1954 
Aug 1, 
1968 
Sec. 107 
Jul. 14, 
1960 
19. 
Apr. 29, 
1983 
Sec. 107 
Jul. 14, 
1960 
RHODES POINT TO TYLERTON, MD 
A channel 6 feet deep and 50 feet wide at mean low water from the northern 
limit of existing Rhodes Point to Tylerton Federal navigation channel, a 
distance of about one mile, through Sheep Pen Gut to deep water in the 
Chesapeake Bay. 
A channel 4 feet deep at mean low water and 50 feet wide from Tylerton to 
Rhodes Point via Rhodes Point Gut. 
Modification providing for a channel 6 feet deep and 50 feet wide from that 
depth in Tyler Creek to and including an anchorage basin of the same depth 
150 feet wide and 400 feet long at Tylerton; channel 6 feet deep and 50 feet 
wide from that depth in Shanks Creek to and including an anchorage basin 
of the same depth 100 feet wide and 400 feet long at Rhodes Point; channel 6 
feet deep and 50 feet wide from that depth in Big Thorofare River to Tylerton; 
channel 6 feet deep and 50 feet wide from Rhodes Point to Tylerton. 
ST. GEORGE CREEK, MD 
A channel 1,500 feet in length, 60 feet wide, and 7 feet deep at mean low water, 
from the St. George Island Bridge to deep water in the Potomac River. 
ST. PATRICKS CREEK, MD 
May 17, Entrance channel 7 feet deep, 60 feet wide and approximately 2,450 feet long 
1950 from deep water in St. Clement Bay to deep water within the creek. 
May 13, 
1966 
Sec. 107 
Jul. 14, 
1960 
Oct. 20, 
1980 
Sec. 107 
Jul. 14, 
1960 
TILGHMAN ISLAND HARBOR, MD 
A channel 60 feet wide and 6 feet deep from that depth in Harris Creek to and 
including two anchorage basins of the same depth, 300 feet by 70 feet and 
500 feet by an average width of 110 feet. 
Modification to provide for construction of a breakwater at the harbor 
entrance. 
WARWICK RIVER, MD 
Jul. 13, Provides for a channel 10 feet deep, 100 feet wide, and about 1.5 miles long, from 
1892 the 10-foot depth curve in Choptank River to Secretary, MD, and a turning 
basin at the latter Point. 
WASHINGTON HARBOR, DC 
Aug. 30, Provides for: (a) Virginia Channel, from Giesboro Point to area for 25,000 
1935 square feet; (b) Washington Channel, from Haines Point to head of Washington 
Channel, 24 feet deep and 400 feet wide; (c) Anacostia River from Giesboro 
Point to Anacostia Bridge, 24 feet deep and 400 feet wide, with turning 
17. 
4-33 
16. 
H. Doc. 286, 
89th Cong., 1st sess. 
River and Harbor Act, 
June 29, 1888 as 
amended by Public 
Law 85-802, dated 
August 28, 1958. 
Detailed Project 
Report, 
June 1981 
H. Doc. 51, 
82d Cong., 1st sess.' 
Detailed Project 
Report, 
February 1968 
Expanded Reconnaissance 
Report, 
April 83 
H. Doc. 671, 
80th Cong., 2nd sess.' 
Detailed Project 
Report, 
August 1965. 
Detailed Project 
Report, 
July 1980. 
Annual Report 
1891, p. 1219 
Rivers and Harbors 
Committee Doc. 22, 
74th Cong., 1st sess.' 
20. 
21. 
22. 
23.

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 4-B (Continued) AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
basin 800 feet wide and about 2,400 feet long of same depth opposite Naval 
Weapons Plant; (d) Anacostia River from Anacostia Bridge 24 feet deep and 
200 feet wide to turning basin 400 feet square of same depth at foot of 15th 
Street S.E. Channel lengths including turning basins are: Virginia Channel, 
25,000 feet; Washington Channel, 10,000 feet; and Anacostia River, 15,000 
feet; and (e) operation and maintenance of inlet gates and lock and outlet 
gates of Tidal Basin constructed under a previous project to flush 
Washington Channel. 
24. 
Sep. 19, 
1890 
Jun. 25, 
1910 
Mar. 2, 
1919 
Jul. 3, 
1930 
WICOMICO RIVER, MD 
Channel 9 feet deep from Main Street Bridge to about 2 miles below. 
Extend 9-foot depth into north prong from Main Street Bridge to the Salisbury 
Dam and turning basin. 
Extend 9-foot depth into south prong to head of navigation at Cathell St., 
including a turning basin, and extend project down to mouth of river in 
Monie Bay. 
A 12-foot channel below the Main Street Bridge. 
Aug. 26, A 14-foot channel, 150 feet wide; depths of 14 feet in the north and south prongs 
1937 and a basin 6 feet deep at Webster Cove and approach channel thereto of the 
same depth. 
Sep. 3, Enlarge existing basin at Webster Cove, by dredging an extension 6 feet deep, 
1954 100 feet wide, and 200 feet long on each side of existing basin to form a 
T-shaped harbor. 
COLONIAL BEACH, VA 
Sep. 15, Extending and widening the existing Central Beach area, stabilizing the 
1980 bank behind the beachfill with vegetation, and constructing four segments 
of offshore breakwater; and extending and widening of the existing Castle 
Beach area, constructing three segments of offshore breakwater, removing 
debris in the beachfill area, and constructing a 100-foot long terminal groin 
at the southern end of Castlewood Park beachfill. 
Dec. 22, 
1982 
Sec. 14 
Jul. 24, 
1946 
Oct. 23, 
1962 
BLACK WALNUT POINT, MD 
Construct stone revetment from north end of existing (state) shore protection 
to a point 375 feet north. 
BLOOMINGTON LAKE, MD & WV 
Construction of Bloomington Lake project. 
BULL RUN, PA 
Dec. 2, Consists of an impervious core incorporated in the proposed highway embank- 
1976 ment of the Williamsport Beltway to utilize it as a levees, closure structures, 
pumping stations and tie-back levees. 
CUMBERLAND, MD AND RIDGELEY, WV 
Jun. 22, 
1936 
Jul. 24, 
1946 
Jun. 25, 
1970 
Jul. 17, 
1970 
Levees, retaining walls, movable dam, and channel clearing for Cumberland, 
West Cumberland and South Cumberland, MD, and Ridgeley, WV 
Levees, wall, channel improvement, remove Chesapeake and Ohio Canal 
Dam and construct new industrial dam. 
FOURMILE RUN, VA 
Construction of a levee and floodwall protection system with associated 
interior drainage facilities, an improved channel, and replacement of two 
highway and four railroad bridges. 
H. Doc. 20, 
51st Cong., 1st sess., 
and Annual Report 
1890, p. 947. 
H. Doc. 569, 
61st Cong., 2d sess. 
H. Doc. 1509, 
63rd Cong., 3rd sess. 
Senate Committee 
Print, 75th Cong., 
3rd sess.' 
H. Doc. 619, 
81st Cong., 2d sess.' 
Detailed Project 
Report, May, 1980 
Expanded 
Reconnaissance 
Report 
Sept. 1982 
H. Doc. 469, 
87th Cong., 2d sess. 
Detailed Project 
Report October 1976. 
H. Doc. 101, 
73rd Cong., 1st sess. 
Report on file in 
Office, Chief of 
Engineers. 
H. Doc. 358, 
91st Cong., 2d sess. 
4-34 
27. 
28. 
29. 
30. 
31. 
32.

BALTIMORE, MD DISTRICT 
TABLE 4-B (Continued) AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Mar. 7, Modification providing for channel capacity of 27,000 c.f.s.; increase channel 
1974 bottom widths along Fourmile Run; deletion of pumping stations, ponding 
areas, and levees, except for a short levee on Long Branch; and the addition 
of recreation as a project feature. 
LACKAWANNA RIVER BASIN, PA 
Oct. 23, Construction of Aylesworth Creek Lake, Fall Brook Lake, and local protection 
1962 works on Lackawanna River at Scranton, Pennsylvania. 
Dec. 10, 
1982 
Sec. 14 
Jul. 24, 
1946 
Oct. 23, 
1962 
June 22, 
1936 
modified 
by Acts 
of June 
28, 1938; 
Aug. 18, 
1941; 
Dec. 22, 
1944; 
May 17, 
1950; and 
Jul. 3, 
1958 
Aug. 18, 
1941 
33. 
34. 
SUSQUEHANNA RIVER FLOOD CONTROL PROJECTS, NY AND PA 
Jul. 3, Construction of Cowanesque and Tioga-Hammond reservoirs, local flood 
1958 protection works at Elkland, PA, and Nichols, NY and channel improvement 
at Cortland, NY 
Oct. 22, Modification in connection with the construction of Cowanesque Lake to 
1976 relocate the Town of Nelson, PA, to a new townsite. 
39. 
Sep. 3, 
1954 
WEST BRANCH OF SUSQUEHANNA RIVER, PA 
Construction of three flood control reservoirs. 
WYOMING VALLEY, PA 
Jun. 22, Construct of a levee and floodwall protection system with associated interior 
1936 drainage facilities at Plymouth, Kingston-Edwardsville, Swoyersville- 
Forty Fort, and Wilkes-Barre and Hanover Township. 
YORK, INDIAN ROCK DAM, PA 
June 22, Construction of Indian Rock Dam and channel improvements on Codorus 
1936 Creek. 
POTOMAC ESTUARY PILOT WATER TREATMENT PLANT, DC 
Mar. 7, To construct, operate, and evaluate a pilot project on the Potomac Estuary 
1974 for the treatment of water at an estimated cost of $6,000,000. 
LATTA BROOK ROAD, NY 
Construct 630 feet of rip rap stabilization on stream bank of Newtown Creek. 
RAYSTOWN LAKE, RAYSTOWN BRANCH, JUNIATA RIVER, PA 
Construction of dam and appurtenant facilities. 
SOUTHERN NEW YORK FLOOD CONTROL PROJECTS 
Construction of detention reservoirs and related flood control works for 
protection of Binghamton, Hornell, Comrning and other towns in New York 
and Pennsylvania. 
STILLWATER LAKE, LACKAWANNA RIVER, PA 
Construction of a flood control reservoir. 
See footnotes for Table 4-B on following page. 
4-35 
S. Doc. 141, 
87th Cong., 2d sess. 
Expanded 
Reconnaissiance 
Report 
June 1982 
H. Doc. 565, 
87th Cong., 2d sess. 
H. Doc. 702, 
77th Cong., 2d sess. 
H. Doc. 702, 
77th Cong., 2d sess. 
H. Doc. 394, 
84th Cong., 2d sess. 
H. Doc. 29, 
84th Cong., 1st sess. 
H. Doc. 308, 
69th Cong., 1st sess. 
H. Doc. 702, 
77th Cong., 2d sess. 
H. Doc. 2, 
93rd Cong., 1st sess. 
35. 
36. 
37. 
38. 
40. 
41. 
45.

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
1. Contains latest published maps. 
2. Exclusive of portion considered inactive. Inactive 
portion is widening 35-foot depth channel from 150 to 400 feet 
from Port Covington to Ferry Bar, widening 27-foot depth 
channel from 150 to 250 feet to Hanover Street Bridge, and providing 
a channel 27 feet deep by 250 feet wide to Western 
Maryland Railway Bridge with an anchorage and turning basin 
at the upper end. 
3. Included in Public Works Administration program 
September 16, 1933. The site chosen for the inlet under this 
authorization was that opened just south of Ocean City by 
natural forces during a severe storm in August 1933. This 
eliminated the necessity for an 8-foot channel from the inlet to 
Ocean City. 
4. Included in Emergency Relief program 1935. 
5. Raising of the north jetty to an elevation of 9 feet above 
mean low water was accomplished with maintenance funds in 
1956. 
OTHER AUTHORIZED NAVIGATION PROJECTS 
TABLE 4-C 
Cost To September 30, 1983 
For Last 
Full Report 
See Annual Operation and 
Project Status Report Construction Maintenance 
Accotink Creek, VA1 
Anacostia River and Flats2 
Annapolis Harbor, MD 
Aquia Creek, VA 
Back Creek, MD 
Betterton Harbor, MD 
Black Walnut Harbor, MD 
Bonum Creek, VA 
Branson Cove, 
Lower Machodoc River, VA 
Breton Bay, MD 5 
Broad Creek River, DE 
Broad Creek, MD 
Cambridge Harbor, MD 6 
Choptank River, MD 1o 
Claiborne Harbor, MD 2 
Corsica River, MD 
Crisfield Harbor, MD 
Cypress Creek, MD 
Duck Point Cove, MD 
Elk and Little Elk Rivers, MD"1 
Fishing Bay, MD 
Goose Creek, MD 18 
Herring Bay and Rockhold Creek, MD 
Herring Creek, MD 
Island Creek, MD 
Island Creek, St. Georges Island, MD 
Knapps Narrows, MD 
La Trappe, MD 
Little Creek, Kent Island, MD 
Lower Machodoc Creek, VA 
Lower Thorofare, Deal Island, MD 
Madison Bay, MD 18 
Manokin River, MD2 4 
Middle River and Dark Head Creek, MD 
Monroe Bay and Creek, VA 
Nan Cove, MD 18 
Nanticoke River, MD 
Neabsco Creek, MD 
Neale Sound, MD 
Neavitt Harbor, MD'8 
Nomini Bay and Creek, VA 2' 
Occoquan Creek, VA" 
Parish Creek, MD 
Patuxent River, MD" 
Completed 
Deferred 
Completed 
Inactive 
Completed 
Inactive 
Completed 
Completed 
Completed 
Inactive 
Completed 
Completed 
Inactive 
Completed 
Deferred 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Inactive 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
1878 
1953 
1946 
1928 
1946 
1960 
1982 
1982 
1950 
1950 
1964 
1962 
1979 
1979 
1978 
1948 
1980 
1947 
1982 
1932 
1979 
1973 
1982 
1961 
1948 
1981 
1982 
1980 
1958 
1904 
1980 
1977 
1919 
1947 
1982 
1965 
1971 
1978 
1982 
1968 
1946 
1971 
1963 
1905 
$ 5,000 
3,910,582 
34,250$ 
52,465' 
23,061 
3,482 
32,631 
202,000'6 
15,755 
47,9247 
64,510' 
28,227 
195,974' 
96,796 
42,974 
39,07111 
349,15412 
3,057 
25,289 
90,121" 
33,874 
75,900 
50,591 
284,80020 
6,230 
23,836 
46,12121 
8,064 
23,00022 
9,916 
44,65823 
125,550 
34,78825 
38,71526 
12,460 
34,86127 
73,243 
14,600 
12,60028 
36,500 
78,446 
66,253 s0 
19,17091 
14,00022 
$ - 
15,623 
11,770 
23,072 
412,349 
144,576 
17,675 
12,621 
114,373 
81,219 
654,258 
94,095 
95,604 
80,285 
505,3931s 
3,787 
293,96419 
44,892'" 
665,652 
8,312 
434,93919 
9,258 
5,608 
317,210 
1,280,325 
40,475 
7,327 
15,156 
320,942 
20,854 
43,534 
23,173 
197,741 
22,498 
55,69934 
289,770 
7,548 
42,063 
171,609 
62,856 
4-36

BALTIMORE, MD DISTRICT 
OTHER AUTHORIZED NAVIGATION PROJECTS 
TABLE 4-C (Continued) 
Cost To September 30, 1983 
For Last 
Full Report 
See Annual Operation and 
Project Status Report Construction Maintenance 
Potomac River and Tributaries at and 
below Washington, DC, Elimination 
of Waterchestnut Completed 1977 - 184,394 
Potomac River at Alexandria, VA Completed 1965 95,214 491,500 
Potomac River at Lower Cedar Point, MD Completed 1920 10,234 6,216 
Potomac River North Side 
of Washington Channel, DC' Completed 1956 1,744,692" 27,461s 
Queenstown Harbor, MD Completed 1958 72,858"5 41,979 
Rock Hall Harbor, MD Completed 1982 1,072,500" 77,113 
Shad Landing State Park, MD Completed 1966 33,53187 6,719 
Slaughter Creek, MD Completed 1982 4,140 389,484" 
St. Catherines Sound, MD Completed 1981 29,947" 231,740 
St. George Creek, MD Inactive 1971 - - 
St. Jeromes Creek, MD Completed 1982 44,35740 371,386"' 
St. Michaels Harbor, MD" Completed 1964 16,723"8 7,742 
St. Peters Creek, MD"8 Completed 1963 46,740" 17,084 
Smith Creek, MD Completed 1936 5,252 3,894 
Susquehanna River above and 
below Havre de Grace, MD" Completed 1974 293,570"8 376,289 
Susquehanna River at Williamsport, PA" Completed 1974 57,031" - 
Town Creek, MD Completed 1950 43,220 5,209 
Tred Avon River, MD Completed 1979 523,130 13,843 
Twitch Cove and Big Thorofare, MD Completed 1982 193,175 1,855,242 
Tuckahoe River, MD Completed 1980 9,727 23,489 
Tyaskin Creek, MD Completed 1923 16,297" 39,984 
Upper Machodoc Creek, VA Completed 1971 20,281 34,606 
Upper Thorofare, Deal Island, MD Completed 1980 62,446 327,625 
1. Unconstructed portion of the project was deauthorized 
August 5, 1977. 
2. Project deferred for restudy. 
3. Includes $8,476 for previous project. 
4. Includes $31,065 for previous project. 
5. Unconstructed portion of the project is inactive. 
6. Excludes $3,998 contributed funds. 
7. Includes $37,500 for previous project. 
8. Includes $50,000 for previous project. 
9. Includes $61,321 for previous project. 
10. Authorization for the unconstructed portion of the 
project was withdrawn by the Chief of Engineers January 22, 
1979. 
11. Includes $30,000 for previous project. 
12. Includes $87,740 for previous project. 
13. Includes $2,839 for previous project. 
14. Includes $9,893 for administrative closeout of FY 82 
contract. 
15. Unconstructed portion of the project was deauthorized 
November 2, 1979. 
16. Includes $79,626 for previous project and excludes 
$8,414 contributed funds. 
17. Includes $24,321 for previous project. 
18. Authorized by Chief of Engineers. 
19. Includes $5,383 for administrative closeout of FY 82 
contract. 
20. Excludes $10,306 contributed funds. 
21. Includes $46,121 public works funds. 
22. Excludes $1,100 contributed funds. 
23. Includes $5,000 for previous project. 
24. Abandonment recommended in 1926 (H. Doc. 467, 
69th Cong., 1st sess.) 
25. Includes $2,000 expended outside project limits. 
26. Excludes $111,581 expended by Navy Department 
and $54,000 from contributed funds. 
27. Excludes $565 contributed funds. 
28. Excludes $1,000 contributed funds. 
29. Unconstructed portion of the project was deauthorized 
November 6, 1977. 
30. Includes $25,000 for previous project. 
31. Includes $19,170 Works Progress Administration 
funds. 
32. Includes $10,617 for previous project. 
33. Excludes $389,000 contributed funds. 
34. Excludes $101,162 Public Health Service funds 
expended for waterchestnut removal. 
35. Includes $19,000 for previous project. 
36. Excludes $672,880 contributed funds. 
37. Excludes $24,125 contributed funds. 
38. Includes $6,466 for administrative closeout of FY 82 
contract. 
39. Excludes $600 contributed funds. 
40. Includes $26,500 for previous project. 
41. Includes $3,067 for administrative closeout of FY 82 
contract. 
42. Excludes $6,984 contributed funds. 
43. Includes $22,905 Works Progress Administration 
funds and $97,390 for previous project. 
44. Excludes $40,000 contributed funds. 
45. Includes $10,158 for previous project. 
4-37

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 4-D 
OTHER AUTHORIZED BEACH 
EROSION CONTROL PROJECTS 
Cost To September 30, 1983 
For Last 
Full Report 
See Annual Operation and 
Project Status Report Construction Maintenance 
Oxford, MD.' Completed 1978 $ 97,7502 
1. Authorized by Chief of Engineers. 
2. Excludes $80,648 contributed funds. 
OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
TABLE 4-E 
Cost To September 30, 1983 
For Last 
Full Report 
See Annual Operation and 
Project Status Report Construction Maintenance 
Anacostia River and tributaries, Flood Protection 
and Navigation Improvements, DC and MD Completed 1980 $6,042,325 $ 1,417,655 
Anacostia River and tributaries, 
Prince Georges Co., MD2 Completed 1977 1,000,0003- 
Bainbridge, NY3,4 Completed 1959 382,000 - 
Bath, NY5 Completed 1970 638,332 - 
Bayard, WV4 Completed 1965 55,218 - 
Bridgewater, VA4 Completed 1953 136,500 - 
Conklin-Kirkwood, NY4 Completed 1955 71,000 - 
Cortland, NY7 Completed 1970 324,486 - 
Elkland, PA Completed 1971 1,297,850 - 
Endicott Johnson City and Vestal, NY Completed 1979 7,034,5348 - 
Forest Heights, MD 4 Completed 1964 430,000' - 
Greene, NY4 Completed 1951 37,000 - 
Kingston-Edwardsville, PA Completed 1979 4,731,39410 
Kitzmiller, MD4 Completed 1965 501,500" - 
Lock Haven, PAl2 Active 1980 450,0001" - 
Nichols, NY Completed 1974 1,487,800 - 
Norwich, NY4 Completed 1950 94,500 - 
Painted Post, NY5 Completed 1970 414,181 - 
Plymouth, PA Completed 1958 1,911,689'- 
Savage River Dam, MD Completed 1954 2,271,9396 33,999 
Scranton, PA"' Completed 1971 2,006,800 - 
Sunbury, PA Completed 1953 6,063,000" - 
Swoyersville and Forty Fort, PA Completed 1968 2,728,113 - 
Tyrone, PA'" Deferred 1980 6,401,016 - 
Unadilla, NY Completed 1970 1,000,00019 - 
Upper Marlboro, MD 4 Completed 1965 590,013 - 
Verona Lake, VA 20 Deferred 1978 992,000 - 
Washington, DC and Vicinity Completed 1953 331,927" - 
Wilkes-Barre, Hanover Township, PA Completed 1958 3,853,4572 - 
Williamsport, PA Completed 1979 12,964,8933 - 
1. Local interests will not accept operation and maintenance 
responsibility of the project until the severe erosion and 
sedimentation of the project caused by tropical storm Eloise is 
corrected and the project is restored to design condition. 
2. Excludes $357,022 contributed funds. 
3. Authorized by Chief of Engineers. 
4. Unit of Southern New York Flood Control Projects. 
5. Excludes $182,672 Public Works Acceleration funds 
and $4,290 contributed funds. 
6. Unit of Susquehanna River Flood Control Projects. 
7. Excludes $154,694 contributed funds. 
8. Excludes $87,720 contributed funds. 
9. Includes $1,162,548 emergency relief funds and 
excludes $225,877 emergency relief funds expended prior to 
adoption of project. 
10. Excludes $6,616 contributed funds. 
4-38

BALTIMORE, MD DISTRICT 
11. Authorized for Phase I design memorandum stage of 
advanced engineering and design. 
12. Excludes $481,000 for Phase I funded under General 
Investigations beginning October 1, 1978. 
13. Includes $4,357 emergency relief funds. 
14. Includes $200,000 expended from contributed funds. 
15. Unit of Lackawanna River Basin Projects. 
16. Excludes $140,504 contributed funds. 
17. The unconstructed portion of the project was 
reclassified to the deferred category January 8, 1981. 
18. Excludes $132,578 contributed funds. 
19. Authorized for the design memorandum stage of 
advanced engineering and design. 
20. Cost of previous project. Includes $106,500 emergency 
relief funds. 
21. Includes $872,715 emergency relief funds. Excludes 
$36,375 emergency relief funds expended for new work before 
adoption of project. 
22. Includes $1,887 emergency relief funds and excludes 
$110,835 contributed funds. 
DEAUTHORIZED PROJECTS 
TABLE 4-G 
For Last 
Full Report Date Federal Contributed 
See Annual and Funds Funds 
Project Report For Authority Expended Expended 
Almond Village, NY' .2 
iroadwater Creek, MI) 
Cadle Creek, M 1) 
Channel Connecting Plain Dealing Creek 
and Oak Creek, MD 
Coan River, VA 
Copes Corner Lakes, NY" 
Cuckold Creek, M I) 4 
Cunninghill Cove, MD 4 
D)avenport Center Lake, NY 2 
1970 
1949 
1949 
1940 
1937 
1970 
1978 
1977 
1970 
1970 
1954 
1950 
1937 
1950 
Fall Brook Lake, PA ' 
(enegantslet Lake. NY 
Governor's Run, MD 
Slarpers Ferry, WV 
Iellens Creek. MD 
May 26, 1953 
1941 Flood 
Control Act 
Nov. 6, 1977 
1974 Water 
Res. Dev. Act 
Nov. 6, 1977 
1974 Water 
Res. Dev. Act 
Aug. 5, 1977 
1974 Water 
Res. Dev. Act 
Aug. 5, 1977 
1974 Water 
Res. Dev. Act 
May 6, 1981 
1974 Water 
Res. Dev. Act 
Jan. 22, 1979 
1960 River 
and Harbor Act 
Jan. 22, 1979 
1960 River 
and Harbor Act 
May 6, 1981 
1974 Water 
Res. Dev. Act 
May 6, 1981 
1974 Water 
Res. Dev. Act 
May 6, 1981 
1974 Water 
Res. Dev. Act 
Aug. 5, 1977 
1974 Water 
Res. Dev. Act 
Aug. 5, 1977 
1974 Water 
Res. Dev. Act 
Nov. 6, 1977 
1974 Water 
Res. Dev. Act 
Nov. 6. 1977 
4-39 
$ 24,6223 
212 
112 
106,7003 
5,720 
11,200 
286,4003 
46,100 
214,5783

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
DEAUTHORIZED PROJECTS 
TABLE 4-G (Continued) 
For Last 
Full Report Date Federal Contributed 
See Annual and Funds Funds 
Project Report For Authority Expended Expended 
Lake Ogleton, MD 1950 1974 Water -- 
Res. Dev. Act 
Nov. 6, 1977 
Mill Creek, MD 1949 1974 Water -- 
Res. Dev. Act 
Oct. 3, 1978 
Moorefield, WV 1941 1974 Water 7,9288- 
Res. Dev. Act 
Dec. 29, 1981 
Sixes Bridge Lake, MD & PA' 1974 1974 Water -- 
Res. Dev. Act 
May 6, 1981 
South Plymouth Lake, NY 1953 1974 Water 100,036$- 
Res. Dev. Act 
Waterway from Little Choptank River to Aug. 5, 1977 
Choptank River, MD 1939 1974 Water 305- 
Res. Dev. Act 
May 6, 1981 
West Oneonta Lake, NY2 1970 1974 Water 189,1008- 
Res. Dev. Act 
1. Local cooperation withdrawn, project authorization 5. Unit of Lackawanna River Basin Projects. 
expired May 26, 1953. 6. Authorized for the design memorandum stage of 
2. Unit of Southern New York Flood Control Projects. advanced engineering and design. 
3. Cost for preliminary work only. 
4. Project authorization was withdrawn by the Chief of 
Engineers. 
RECONNAISSANCE AND CONDITION SURVEYS 
TABLE 4-H 
Date Survey 
Project Completed 
DISTRICT OF COLUMBIA 
Anacostia River and tributaries 
MARYLAND 
Back Creek, Anne Arundel County 
Claiborne Harbor 
Corsica River 
Fishing Bay 
Island Creek 
Knapps Narrows 
Little Creek, Kent Island 
Madison Bay 
Manokin River 
Middle River and Dark Head Creek 
Nan Cove 
Neavitt Harbor 
Parish Creek 
Queentown Harbor 
Shad Landing State Park 
St. Michaels Harbor 
St. Peters Creek 
September 1983 
January 1983 
August 1983 
December 1982 
May 1983 
May 1983 
February 1983 
May 1983 
March 1983 
December 1982 
April 1983 
March 1983 
January 1983 
March 1983 
March 1983 
January 1983 
March 1983 
January 1983 
4-40

BALTIMORE, MD DISTRICT 
RECONNAISSANCE AND CONDITION SURVEYS 
TABLE 4-H (Continued) 
Date Survey 
Project Completed 
Tilghman Island Harbor October 1982 
Tyaskin Creek September 1983 
VIRGINIA 
Branson Cove August 1983 
Lower Machodoc Creek July 1983 
Upper Machodoc Creek August 1983 
INSPECTION OF COMPLETED PROJECTS 
TABLE 4-I 
Project Date Inspected 
DISTRICT OF COLUMBIA 
Anacostia River 
Washington, DC & Vicinity 
MARYLAND 
Anacostia River Basin 
Cumberland 
Forest Heights 
Kitzmiller 
Savage 
Upper Marlboro 
NEW YORK 
Bainbridge 
Bath 
Cincinnatus 
Conklin-Kirkwood 
Cortland 
Endicott-Johnson City & Vestal 
Greene 
Nichols 
Norwich 
Oswego 
Painted Post 
Port Dickinson 
Sherburne 
Unadilla 
PENNSYLVANIA 
Kingston and Edwardsville 
Loyalsock 
Milton 
Plymouth 
Scranton 
Sunbury 
Swoyersville-Forty Fort 
Tyrone 
Williamsport 
S. Williamsport 
VIRGINIA 
Bridgewater 
WEST VIRGINIA 
Bayard 
November 1982 
November 1982 
October 1982 
September 1983 
October 1982 
September 1983 
September 1983 
October 1982 
October 1982 
October 1982 
October 1982 
October 1982 
October 1982 
October 1982 
October 1982 
October 1982 
October 1982 
October 1982 
October 1982 
October 1982 
October 1982 
October 1982 
October 1982/September 1983 
September 1983 
September 1983 
September 1983 
October 1982/September 1983 
September 1983 
September 1983 
October 1982/September 1983 
September 1983 
September 1983 
October 1982/March 1983 
September 1983 
4-41 
.. .

NORFOLK, VA., DISTRICT* 
This District comprises the State of Virginia, except 
the Potomac, Roanoke and Ohio River Basins; the 
entire area on the eastern shore of Virginia except for 
the project for Pocomoke River, Maryland and 
Virginia. On the west shore of Chesapeake Bay, all 
waterways south of Smith Point, Virginia, at the 
mouth of the Potomac River except the project for 
Little Wicomico River, Virginia. North Carolina, only 
the Chowan River Basin downstream to and 
including the mouth of the Meherrin River, and the 
Dismal Swamp Canal Route of the Atlantic 
Intracoastal Waterway to the Albemarle Sound. West 
Virginia, only the James River Basin. 
IMPROVEMENTS 
Navigation 
1. Atlantic Intracoastal 
Waterway Between Norfolk, 
VA., and St. Johns River, FL.......... 
2. Baltimore Harbor and 
Channels (Norfolk District) ............ 
3. Broad Creek, VA ....................... 
4. Cape Charles City Harbor, VA ......... 
5. Chincoteague Bay, VA ................. 
6. Chincoteague Inlet, VA ................ 
7. Hampton Roads and Harbors 
of Norfolk and Newport 
News, VA Collection and 
Removal of Drift....................... 
8. James River, VA ...................... 
9. Lynnhaven Inlet, VA.................. 
10. Norfolk Harbor, VA.................... 
11. Oyster Channel, VA ................... 
12. Quinby Creek, VA ..................... 
13. Rappahannock River, VA .............. 
14. Supervision of the Harbor of 
Hampton Roads (Prevention of 
Obstructive and Injurious 
Deposits) .............................. 
15. Tangier Channel, VA .................. 
16. Thimble Shoal Channel, VA ........... 
17. Waterway on the Coast of Virginia...... 
18. Navigation Work Under Special 
Authorization.......................... 
Beach Erosion Control 
19. Virginia Beach, VA.................... 
20. Beach Erosion Control Work Under 
Special Authorization.................. 
Page Flood Control 
21. Gathright Dam and Lake Moomaw, VA. 
22. Rapidan River, VA...................... 
5-2 23. Virginia Beach Streams, Canal 
Number 2, VA ......................... 
5-2 24. Flood Control Work Under 
5.3 Special Authorization.................. 
5-3 25. Emergency Flood Control 
5-4 Activities .............................. 
5-5 
5-5 
5-5 
5-6 
5-7 
5-8 
5-9 
5-9 
5-9 
510 
5-11 
5-11 
5-11 
5-12 
5-12 
General Investigations 
26. Surveys................................. 
27. Collection and Study of Basic Data ..... 
Continuation of Planning and 
28. Engineering ............................ 
Tables 
Table 5-A Cost and Financial Statement. 
Table 5-B Authorizing Legislation ....... 
Table 5-C Data Relative to the Completed 
Locks ......................... 
Table 5-D Other Authorized Navigation 
Projects ....................... 
Table 5-E Other Authorized Beach 
Erosion ....................... 
Table 5F Other Authorized Flood 
Control ....................... 
Table 5-G Reconnaissance and 
Condition Survey ............ 
Page 
5-12 
5-13 
5-13 
5-14 
5-14 
5-14 
5-14 
5-14 
5-15 
5-19 
5-24 
5-24 
5-26 
5-26 
5-26 
5-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Navigation 
1. ATLANTIC INTRACOASTAL 
WATERWAY BETWEEN 
NORFOLK, VA., AND ST. 
JOHNS RIVER, FLA. 
(NORFOLK DISTRICT) 
Location. Two inland water routes approximately 
paralleling Atlantic coast south of Norfolk, Va., 
between a point in Southern Branch of Elizabeth 
River, Va., 2,500 feet upstream of Norfolk & Western 
Railway bridge and Virginia-North Carolina State 
line in North Landing River, a distance of 27.2 miles; 
and 64.6 miles between mouth of Deep Creek, Va., and 
mouth of Pasquotank River, N.C. These routes are 
shown on Coast and Geodetic Survey Chart 12206. 
Existing project. A channel 12 feet deep at mean 
low water and 90 to 250 feet wide following Southern 
Branch of Elizabeth River, 5.2 miles, Virginia Land 
Cut, 8.3 miles, and North Landing River, 13.7 miles; 
and construction of a tidal guard lock at Great Bridge, 
Va. It also provides channels 10 feet deep at mean low 
water and 80 to 100 feet wide in Deep Creek, 3.1 miles, 
Turners Cut, 4.3 miles, and Pasquotank River, 35.1 
miles; maintaining Dismal Swamp Canal, 22.1 miles, 
to about 9 feet deep mean canal level over a width of 50 
feet; protection of banks in Turners Cut with sheet 
piling, and cutting certain sharp points in 
Pasquotank River to shorten its course. (See Table 5-C 
at end of chapter on Data Relative to Completed Locks 
included in Project.) 
Project includes operating and care of completed 
locks, dams and bridges, under maintenance. 
Southern Branch of Elizabeth River and Deep Creek 
sections of the two routes are tidal, mean range being 
about 3 feet with extremes of minus 3.5 and plus 9.6 
feet. Remaining sections are nontidal with 
fluctuations of 1 to 2 feet in level due to winds. Cost for 
new work for completed project was $3,396,276. 
Protection to canal property at Great Bridge portion is 
considered inactive and excluded from foregoing cost. 
Estimated cost of this portion (1954) is $265,000. For 
details of previous projects, see page 476 of Annual 
Report for 1938. (See Table 5-B for Authorizing 
Legislation.) 
Local cooperation. None required. 
Terminal facilities. Existing facilities are 
considered adequate. See Annual Report for 1970. 
Operations during fiscal year. Operation and 
ordinary maintenance of the project consisting of real 
estate management services, condition and operation 
studies, operation and care of locks, bridges, 
spillways, wharves, canal equipment, grounds, roads, 
buildings, etc. with Government plant and hired labor 
were carried on at a cost of $219,171. 
Maintenance repairs to lock valves and hinges 
including painting of the Bridges at Great Bridge 
and North Landing were accomplished by contract. 
Total cost of the contract work amounted to $81,928. 
The following cdntracts were active in FY 1983: 
A contract, funded by the 1983 Jobs Bill Act, for 
bulkhead replacement was awarded August 12,1983 
in the amount of $993,347. By year's end contractor's 
earnings amounted to $175,000. Completion is 
scheduled for FY 1984. 
A contract to operate, maintain and repair 
facilities of the Atlantic Intracoastal Waterway was 
awarded February 1983 in the amount of $4,117,981. 
Contract is effective for a maximum of five years, 
renewable annually. Total contractor's earnings 
amounted to $564,496. 
Maintenance engineering and design and supervision 
and administration costs, less credits for 
damages to government property amounted to 
$375,237. 
2. BALTIMORE HARBOR AND 
CHANNELS 
(NORFOLK DISTRICT) 
Existing project. Provides for deep water 
approach channels in Baltimore Harbor. Northern 
portion including Baltimore Harbor is under 
jurisdiction of Baltimore District. Portion under 
jurisdiction of Norfolk District is more fully described 
below. 
2A. CAPE HENRY CHANNEL, VA. 
Location. At mouth of Chesapeake Bay opposite 
Cape Henry. (See Coast and Geodetic Survey Chart 
No. 12222). 
Existing project. A channel about 2.3 miles long, 
1,000 feet wide, and 50 feet deep at mean low water 
through shoal at mouth of Chesapeake Bay opposite 
Cape Henry. Under ordinary conditions mean range 
of tide 2.5 feet and extreme 3 feet. Extremes of 
irregular fluctuation due to combined effect of wind 
and tides, referred to mean low water, are minus 2 feet 
5-2

NORFOLK, VA DISTRICT 
and plus 9.5 feet. (See Table 5-B for Authorizing 
Legislation.) 
2B. RAPPAHANNOCK SHOAL 
CHANNEL, VA. 
Location. In lower Chesapeake Bay opposite 
mouth of Rappahannock River and about 50 miles 
northerly from Atlantic Ocean at entrance of 
Chesapeake Bay. (See Coast and Geodetic Survey 
Chart No. 12225). 
Existing project. A channel about 9.9 miles long, 
1,000 feet wide, and 50 feet deep at mean low water 
between contours of that depth in Chesapeake Bay, 
opposite Rappahannock River. Under ordinary 
conditions mean tidal range is 2.5 feet and extreme 3 
feet. Extremes of irregular fluctuation due to combined 
effect of wind and tides, referred to mean low 
water, are minus 2 feet and plus 9.5 feet. (See Table 5-B 
for Authorizing Legislation.) 
2C. YORK SPIT CHANNEL, VA. 
Location. In lower Chesapeake Bay opposite 
mouth of York River and about 20 miles northerly 
from Atlantic Ocean at entrance of Chesapeake Bay. 
(See Coast and Geodetic Survey Chart No. 12221). 
Existing project. A channel about 18.2 miles long, 
1,000 feet wide, and 50 feet deep at mean low water 
between contours of that depth in Chesapeake Bay 
opposite York Spit. Under ordinary conditions mean 
tidal range is 2.5 feet and extreme 3 feet. Extremes of 
irregular fluctuation, due to combined effect of wind 
and tides, referred to mean low water, are minus 2 feet 
and plus 9.5 feet. For details of previous projects see 
Annual Report for 1932. (See Table 5-B for 
Authorizing Legislation.) 
Local cooperation. None required. 
Terminal facilities. These three channels form 
the access between lower and upper Chesapeake Bay. 
Operations during fiscal year. Operation of the 
project, including condition surveys, was accomplished 
at a cost of $35,388. 
Maintenance engineering and design and supervision 
and administration amounted to $48,772. 
A combined maintenance dredging contract for 
dredging Cape Henry Channel and Thimble Shoal 
Channel was awarded in late FY 1982, of which 
$2,266,745 was for the Cape Henry Channel. Dredging 
was completed, on this portion of the contract, on 
Nov. 14, 1982. There were 314,128 cubic yards of 
credited material removed, at a direct cost of 
$1,801,358. Periodic maintenance dredging will be 
continued to maintain full project dimensions. 
3. BROAD CREEK, VA. 
Location. Broad Creek is a small tidal estuary in 
Middlesex County, Va., 1 mile long, flowing in a 
northerly direction into the Rappahannock River, 
which it enters on the right bank about 1 mile 
upstream of its mouth at Chesapeake Bay. The creek 
is 61 miles northerly of Norfolk, Va. (See U.S. Coast 
and Geodetic Survey Chart No. 12235). 
Existing project. This provides for a channel 7 
feet deep, 100 feet wide and 4,100 feet long from deep 
water in the Rappahannock River to deep water in 
Broad Creek. The plane of reference is mean low 
water. The tidal ranges are: Mean, 1.2 feet; irregular, 
2 feet; and extreme, approximately 7.5 feet. 
The cost to the Federal Government for new work, 
for the completed project was $27,888. 
The existing project was adopted by the River and 
Harbor Act of March 2, 1945 (H. Doc. 381, 76th Cong., 
1st sess.). The latest published map is in the project 
document. 
Local cooperation. Fully complied with except 
that local interests shall furnish, free of cost to the 
United States, suitable spoil-disposal areas when 
and as required for subsequent maintenance, and 
hold and save the United States free from claims for 
damages that may result from dredging. 
Terminal facilities. There are privately owned 
wharves and landings on the creek, many of which 
are open to the public by special arrangements. There 
is one marine railway on the creek. The terminal facilities 
are considered adequate for present commerce. 
Operations during fiscal year. At the end of the 
fiscal year, an A-E contract was awarded for $14,000 
to prepare the project for maintenance dredging in 
FY 84. In addition, $24,945 was expended on project 
condition surveys. Periodic maintenance dredging 
will continue. 
4. CAPE CHARLES CITY 
HARBOR, VA. 
Location. Town of Cape Charles, Va. is on Chesapeake 
Bay on west side of peninsula separating the 
5-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
bay from Atlantic Ocean. It is about 11 miles north of 
southern extremity of peninsula and 45 miles south 
of Maryland-Virginia State line. Cape Charles City 
Harbor is an artificial land-locked harbor on south 
side of the town. (See Coast and Geodetic Survey 
Chart 12222). 
Existing project. A channel 18 feet deep and 500 
feet wide from that depth in Chesapeake Bay 
through Cherrystone Bar and inlet to the entrance to 
Cape Charles City Harbor, a distance of 2.71 miles, 
thence a basin in the harbor of the same depth 400 to 
800 feet wide and 3,000 feet long, thence a channel 10 
feet deep, 100 to 180 feet wide and 260 feet long 
connecting a basin of same depth 180 feet wide and 
420 feet long at head of Mud Creek, and a harbor or 
refuge on the north side of Mud Creek, 7 feet deep, 200 
to 250 feet wide, and 375 feet long connected to Mud 
Creek with an entrance channel 7 feet deep and 60 
feet wide. Project also provides for protective works 
in form of a stone jetty on north side of harbor entrance 
and sand mole 1,350 feet long south of harbor 
entrance. All depths are referred to mean low water. 
Mean tidal range is 2.3 feet with extremes of 2.5 feet 
below and 8 feet above mean low water. Cost for new 
work for completed project was $628,644, including 
$6,000 from contributed fund. Widening the basin an 
additional 200 feet is considered inactive and 
excluded from foregoing cost. Estimated cost of this 
portion (1954) is $207,000. 
Local cooperation. Conditions imposed by River 
and Harbor Act of 1938 were fully complied with and 
approved by Chief of Engineers on March 30, 1940. 
River and Harbor Act of 1945, in adopting existing 
project dimensions, imposed conditions that local 
interests provide all lands for initial construction 
and future maintenance; provide and maintain substantial 
bulkheads and other terminal facilities adequate 
to permit full utilization of improvement; and 
reserve at least 1,000 linear feet of berthing space 
along such bulkheads for general public use on equal 
and reasonable terms; and agree to hold the United 
States free from damages. Local interests furnished 
all lands necessary for dredging harbor to 800-foot 
width. Items of local cooperation in connection with 
Harbor of refuge have been complied with. 
Terminal facilities. The Pennsylvania Railroad 
owns a wooden pier 200 feet long and two transfer 
ships in the outer harbor. On the south side of the 
harbor, Bay Shore Concrete owns an 800-foot bulkhead. 
A bulkhead providing 200 feet of berthing 
space is on the south side of the main harbor and is 
owned by a fish plant. There are about 1400 feet of 
city-owned bulkhead open to the public. The Coast 
Guard owns a 100-foot pier on Mud Creek. The harbor 
of refuge should accomodate about 50 boats when 
berthing facilities are completed. 
Operations during fiscal year. Maintenance 
engineering and design and condition surveys were 
accomplished at a total direct cost of $8,546. 
5. CHINCOTEAGUE BAY, VA. 
Location. Chincoteague Bay is a shallow sound 
on the Atlantic coast of Maryland and Virginia. 
Greenbackville and Franklin City occupy low-lying 
ground on the westerly shore of the bay 412 miles 
from its southwest end. (See U.S. Coast and Geodetic 
Survey Chart No. 12211.) 
Previous projects. For details, see page 244 of 
Annual Report for 1968. 
Existing project. This provides for an L-shaped 
harbor 5 feet deep, 60 feet wide, and 1,500 feet long, 
with an approach channel of the same depth and 
width in Chincoteague Bay. The mean range of tide 
is about 2 feet. 
The cost of new work for the completed project was 
$25,126. 
The existing project was adopted by the River and 
Harbor Act of August 26, 1937 (H. Doc. 233, 75th 
Cong., 1st sess.) The latest published map is in the 
project document. 
Local cooperation. Fully complied with for 
construction, local interests are to furnish spoildisposal 
areas as required for maintenance. 
Terminal facilities. About 750 feet of public 
bulkhead has been built along the south side of the 
channel which is primarily used by commercial 
boats for berthing and unloading their catch. This 
facility is considered adequate for existing commerce. 
Operations during fiscal year. A maintenance 
dredging contract was awarded February 1983 in the 
amount of $136,489. Dredging was accomplished during 
period March 9 - April 18, 1983. There were 
20,076 cubic yards of credited material removed with 
contractor's earnings amounting to $130,717. 
Engineering and design, supervision and administration 
including condition and quantity surveys, 
less credits for liquidated damages, amounted to 
$61,682. 
5-4

NORFOLK, VA DISTRICT 
6. CHINCOTEAGUE INLET, VA. 
Location. Chincoteague Inlet at the southern end of 
Assateague Island provides access to the Atlantic 
Ocean from the inland waterway near the town of 
Chincoteague, Virginia. (See Coast and Geodetic 
Survey Chart No. 12211). 
Existing project. Provides for a channel 12 feet 
deep and 150 feet wide across the ocean bar in the 
Atlantic Ocean and to the mouth of the inlet; thence, a 
channel 9 feet deep and 100 feet wide from the inlet 
through the canal and then along Chincoteague 
Channel to a point approximately 2,000 feet north of 
the state highway bridge to Chincoteague, a distance 
of about 6.6 miles. Mean range of tide is about 3 feet. 
All depths are referred to mean low water. (See Table 
5-B for Authorizing Legislation.) 
Local cooperation. For details see Annual Report 
for 1974. 
Terminal facilities. Existing facilities at 
Chincoteague are considered adequate for current and 
prospective traffic. 
Operations during fiscal year. Operation and 
ordinary maintenance of the project including condition 
surveys amounted to $11,229. 
A contract, funded by the 1983 Jobs Bill Act, was 
awarded June 30, 1983 in the amount of $606,740. 
There were 85,935 cubic yards of credited material 
dredged at the entrance channel during the period 
August 7 - September 26, 1983. Total contractor's 
earnings amounted to $536,739 by year's end. 
Maintenance engineering and design and supervision 
and administration, including quantity surveys 
amounted to $77,991. Annual maintenance dredging 
will continue. 
7. HAMPTON ROADS AND 
HARBORS OF NORFOLK AND 
NEWPORT NEWS, VA. - 
COLLECTION AND REMOVAL 
OF DRIFT 
Location. Hampton Roads is a natural harbor 300 
miles south of New York and 180 miles south of 
Washington, D.C. Its principal tributaries are James 
River, affording a natural deep harbor at Newport 
News, Virginia; Elizabeth River, with its Southern, 
Eastern, and Western Branches providing harbors for 
Norfolk and Portsmouth, Virginia; and Hampton 
Creek, serving the harbor at Hampton, Virginia. (See 
Coast and Geodetic Survey Charts No. 12248, 12245, 
and 12253.) 
Existing project. Collection and removal of drift 
in Hampton Roads and its tributary waters authorizes 
the Secretary of the Army to allot necessary amounts 
of work from appropriations for maintenance and 
improvement of existing river and harbor works or 
from other available appropriations and that this 
work shall be carried on as a separate and distinct 
project. It is wholly a work of maintenance. The 
purpose of work is to afford relief from variable 
conditions of obstruction. No advance estimate of the 
amount of work is required. (See Table 5-B for 
Authorizing Legislation.) 
Local cooperation. None required. 
Terminal facilities. See Norfolk Harbor, Virginia 
and Channel to Newport News, Virginia. 
Operations during fiscal year. Operation of the 
project incinerator amounted to $19,182. 
Maintenance operations, amounting to $59,672 
consisted of collection and disposal of an estimated 
71,805 cubic feet of a variety of floating refuse, 
ranging from discarded furniture to heavy timber and 
piling. Operation and maintenace and supervision 
and administration costs amounted to $42,056. 
8. JAMES RIVER, VA. 
Location. The river is formed by junction of the 
Cowpasture and Jackson Rivers in Botetourt County, 
Virginia, flows easterly 340 miles, and empties into 
Hampton Roads at Newport News, Virginia. (See 
Coast and Geodetic Survey Charts No. 12248 and 
12251.) 
Existing project. A channel 35 feet deep and 300 
feet wide from the mouth to Richmond Deepwater 
Terminal, and thence a channel 18 feet deep and 200 
feet wide from the deepwater terminal to Richmond 
Lock; a mooring basin 35 feet deep, 180 to 220 feet wide 
and 2,100 feet long along side the channel opposite 
waterfront at Hopewell; enlargement of the turning 
basin at Richmond Deepwater Terminal to 825 feet 
wide, 2,770 feet long and 35 feet deep; a turning basin 
in Richmond Harbor 200 feet wide, 600 feet long and 
18 feet deep; and construction of spur and training 
dikes. Depth of channels are referred to mean low 
water. Total length of channel included in the project 
is 87 miles, which is the navigable section. Mean tidal 
5-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
ranges under ordinary conditions for different parts of 
the river are: mouth, 2.6 feet; Jamestown, 2 feet; City 
Point, 2.6 feet; and Richmond, 3.2 feet. Spring tide 
ranges under ordinary conditions at the same 
localities are mouth, 3.1 feet; Jamestown, 2.4 feet; City 
Point, 3 feet; Richmond, 3.2 feet. Ordinary 
fluctuations of stage at Richmond, due to floods, are 6 
to 12 feet above mean low water. Extreme fluctuations 
are 16 to 32 feet. Flood heights below Richmond 
diminish rapidly. The extreme according to available 
information is about 11 feet lower at Dutch gap, 14 
miles below and 17 to 18 feet lower, 20 miles below. 
The estimated (1971) total cost for new work is 
$71,145,940 including required non-Federal cost for 
conditions of local cooperation imposed by the River 
and Harbor Act of 1930, 1945, and 1950, estimated 
(1939) to be $1,949,700; and by the River and Harbor 
Act of 1962, estimated (1971) to be $2,950,000. For 
previous projects, see Annual Report for 1938. (See 
Table 5-B for Authorizing Legislation). 
Local cooperation. Fully complied with for 
conditions imposed by River and Harbor Acts of 1930, 
1945, and 1950. The conditions imposed by the River 
and Harbor Act of 1962 have not been complied with. 
Terminal facilities. River commerce at 
Richmond is handled by city-owned terminals, city 
wharf, Richmond dock, and 16 privately-owned 
wharves within or in the immediate vicinity of 
Richmond Harbor. The city's Upper Terminal, located 
on the north bank within the manufacturing section 
of Richmond, provides for 750 feet of concrete wharf 
and 80,000 square feet of warehouse and transit shed. 
The other terminal is located approximately 4 miles 
downstream from the Upper Terminal which provides 
about 1,250 feet of wharf and 2 concrete warehouses 
with about 190,000 square feet of floor space. This 
deepwater terminal at the head of the 25-foot deep 
improved channel serves ocean-going vessels and 
larger ships engaged in coastwide trading. Below the 
deepwater terminals the improvement is served by 42 
wharves. Richmond terminals and wharves together 
with wharves between Richmond and the river's 
mouth are adequate for river's commerce. 
Operations during fiscal year. Operation of the 
project including condition surveys and special 
studies and reports, and value engineering amounted 
to $129,203. 
A continuing contract, awarded September 1982 in 
the amount of $1,144,355, was completed January 
1983. Dredging was performed at the Richmond 
Deepwater Terminal and Shoals between Richmond 
Deepwater Terminal and Hopewell, Va. There were 
277,025 cubic yards of credited material removed at a 
direct cost of $955,765. In addition, a maintenance 
dredging contract funded under the 1983 Jobs Bill 
Act, was awarded August 1983 in the amount of 
$559,683. Dredging at Jordan Point was completed in 
September 1983. There were 199,489 cubic yards of 
credited material removed at a direct cost of $316,000. 
Dredging was still in progress at end of the year with 
work to begin in the vicinity of Turkey Island. 
Maintenance engineering and design and supervision 
and administration including quantity surveys 
amounted to $288,732. Maintenance dredging will 
continue. 
9. LYNNHAVEN INLET VA. 
Location. On south shore of Chesapeake Bay, 5 
miles west of Cape Henry, and 10 miles east of 
Norfolk, Va. Inlet connects Lynnhaven Roads, a part 
of Chesapeake Bay, with a network of inland waters 
in northern half of city of Virginia Beach. (See Coast 
and Geodetic Survey Chart 1222). 
Existing project. An entrance channel from 
Chesapeake Bay through Lynnhaven Inlet, 10 feet 
deep and 150 feet wide; a mooring and turning basin, 
inside of Lynnhaven inlet, 10 feet deep, 1,100 feet long, 
and 750 feet wide; a channel 9 feet deep and 90 feet 
wide to extend from the mooring and turning basin 
into Broad Bay; via Long Creek-Broad Bay Canal; 
and a channel through the Narrows connecting Broad 
and Linkhorn Bays, 6 feet deep and 90 feet wide. 
Depths are referred to mean low water. Mean range of 
tide in Lynnhaven Inlet is about 2 feet with extreme 
fluctuations of 1.5 feet below and 9.5 feet above mean 
low water. Range in Lynnhaven Bay is a little more 
than 2 feet, in Broad and Linkhorn Bays, fluctuations 
in water level are caused by local winds. (See Table 5-B 
for Authorizing Legislation.) 
Local cooperation. Complied with, except local 
interests must furnish spoil-disposal areas as needed 
for future maintenance. For details see page 308 of 
Annual Report for 1965. 
Terminal facilities. Existing facilities are 
considered adequate. For details, see Annual Report 
for 1970. 
Operations during fiscal year. Condition 
surveys were completed at a direct cost of $21,315. A 
5-6

NORFOLK, VA DISTRICT 
final payment of $7,278 was paid to the contractor for 
redredging of Lynnhaven Inlet and new work 
dredging of the Long Creek modification accomplished 
in fiscal year 1982. 
Periodic maintenance dredging will be performed 
as required. 
10. NORFOLK HARBOR, VA. 
Location. Norfolk, Virginia is 187 miles south of 
Baltimore, Maryland and 30 miles from entrance to 
Chesapeake Bay at Cape Charles and Cape Henry. 
Harbor extends 18.3 miles from 45-foot contour at 
Hampton Roads to a point 2,500 feet above Norfolk 
and Western Railway Bridge over Southern Branch of 
the Elizabeth River. (See Coast and Geodetic Survey 
Charts Nos. 12245 and 12253.) 
Existing project. A main channel 45 feet deep, 
1,500 feet wide, from that depth in Hampton Roads 
near Fort Wool to a point just south of Norfolk 
International Terminal Piers; thence, at same depth 
800 feet wide to Lamberts Point; thence, 40 feet deep 
and 750 feet wide to mouth of Southern Branch of 
Elizabeth River; and 450 feet wide up this branch to 
the Belt Line Railroad bridge, including an approach 
in turning area to same depth and a maximum width 
of 830 feet opposite Norfolk Naval Shipyard, 
extending downstream 3,250 feet from Belt Line Railroad 
bridge; thence 40 feet wide, 375 feet wide and 1 
mile long to Norfolk and Western (formerly Virginia 
Railway bridge); thence, 35 feet deep, 250 feet wide and 
3.1 miles long to a point 1,900 feet above Norfolk and 
Western Railway (Gilmerton's Bridge); thence, 35 feet 
deep, 250 feet to 500 feet wide to a point 1.6 miles above 
Interstate 64 high level bridge. 
A turning basin at the mouth of St. Julian's Creek, 
35 feet deep and 400-600 feet square, and a turning 
basin at the mouth of Main's Creek 35 feet deep and 
600 feet square, the upstream end of the project. A 
channel in Eastern Branch, 25 feet deep, 500 feet wide 
and 1.09 miles long from 40-foot channel to Norfolk 
and Western Railway bridge; thence, 25 feet deep, 300 
feet wide 0.55 mile long to Campostella Bridge; thence, 
25 feet deep, 200 feet wide and 1.2 mile to Norfolk and 
Western Railway bridge (formerly Virginia Railway 
bridge); and for maintenance at a depth of 25 feet of 
existing turning basin and 5.5 acres in extent at head 
of existing project just below the Norfolk and Western 
(formerly Virginian) Railway bridge. A channel in 
Western Branch, 40 foot channel in Elizabeth River, 
24 feet deep, 300 feet wide and 0.78 mile long; thence, 
24 feet deep and 200 feet wide for 0.37 mile to West 
Norfolk Highway bridge; thence, 18 feet deep, 150 
wide, 0.57 mile long. A channel in Scotts Creek 
between 40-foot channel at mouth and a point 100 feet 
above former location of Atlantic Coast Line Railroad 
bridge (about 0.73 miles upstream), 12 feet deep and 
100 feet wide. Anchorage areas on west side of 40 foot 
channel opposite Lamberts Point and south of Craney 
Island aggregating 173 acres, consisting of 1 
anchorage space 1,500 feet square and 38 feet deep; 1 
anchorage space 1,500 feet square and 35 feet deep; 
and 1 anchorage 1,000 feet wide, 3,000 feet long and 20 
feet deep. Another anchorage of 45 acres and 12 feet 
deep near Pinner Point. Two anchorages opposite 
Sewells Point 45 feet deep over a swinging radius of 
1,200 feet and a trapezoidal shaped disposal area of 
about 2,500 acres of flats adjacent to the north of 
Craney Island, inclosed by stonefaced levees, 3 
sluiceways in west levee, and an access road. 
Facilities for unloading of hopper dredged material 
consisting of mooring dolphins; a mooring barge 
anchorage 100 by 600 feet, 21 feet deep, with approach 
channel 300 to 3,600 feet; 30-feet deep connecting 
anchorage with Norfolk Harbor 45-foot channel; and 
a 28-inch discharge pipe line to the leveed area. 
Facilities for contract rehandling of bucket dredged 
material consisting of a rehandling basin 1,000 by 
1,200 feet, 40 feet deep, protected by a spur levee 
extending 2,350 feet from main levee and provided 
with approach exit channels, 200 feet wide by 18 feet 
deep to Norfolk Harbor 45 foot channel and a pipe line 
trestle from rehandling basin to leveed area. All 
depths arereferred to mean low water. Mean tidal 
range is 2.7 feet, and extreme is 3.4 feet. Extremes of 
irregular fluctuations, due to combined effect of tides 
and winds referred to mean low water on -3.5 feet and 
+9.6 feet. Eastern Branch, 30-foot channel portion is 
considered inactive. For details of previous projects 
see Annual Report for 1938. (See Table 5-B for 
Authorizing Legislation.) 
Local Cooperation. Fully complied with. 
Terminal facilities. Latest published description 
of terminal facilities is in Port Series No. 11 (revised 
1971, part II) on Ports of Hampton Roads, prepared by 
Board of Engineers for Rivers and Harbors. 
Operations during fiscal year. Operation of the 
Craney Island portion of the project including condi- 
5-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
tion and operation studies, office studies and reports, 
care of buildings, grounds, utilities, roads, levees, 
plant and hopper dredge pipeline equipment rental, 
and supervision and administration amounted to 
$573,455. 
A contract awarded in August 1982 in the amount 
of $240,000 for testing embankment material at the 
Craney Island facility was completed. Total contractor 
earnings amounted to $102,291. In addition, a 
contract to raise the west dike at the disposal facility 
awarded in September, 1982 for $183,650 was completed 
January, 1983. Total contractor earnings amounted 
to $144,641. 
Contract work, funded under the 1983 Jobs Bill 
Act, to construct a containment dike, was awarded 
July 1983 in the amount of $1,523,885. Total 
contractor's earnings at year's end, amounted to 
$220,458. 
Other engineering work on the Craney Island 
Management Plan to include Aerial Photography, 
boring and foundation tests, lab analysis, etc. 
amounted to $124,457. 
Operation of the Norfolk Harbor portion of the 
project including condition surveys, care of buildings 
and grounds, commercial statistics and budgeting 
and scheduling, and an O & M study plan amounted 
to $475,726. 
A contract, funded under the 1983 Jobs Bill Act, to 
procure an estimated 223,000 square yards of fabric, 
was awarded in June 1983. By year's end 72 panels 
had been laid. Total contractor's earnings amounted 
to $610,079. 
A maintenance dredging contract in the amount of 
$2,206,155 for the 45-foot channel was awarded in 
September 1982 and completed May, 1983. They were 
an estimated 2,033,402 cubic yards of credited 
material removed at a direct cost of $1,723,616. 
Maintenance dredging of the Craney Island 
Rehandling Basin was completed between the period 
October 1, 1982 - January 16, 1983. There were 
removed 545,177 cubic yards of credited material 
financed by user tolls. Total contractor's earnings 
amounted to $810,617. 
A contract for replacement of Pier No. 1 at the Fort 
Norfolk facility awarded in July 1982 in the amount 
of $731,658 was completed in August 1983. Total 
contractor's earnings reported this fiscal year 
amounted to $33,542. Also, a contract for repair of the 
seawall at Fort Norfolk awarded in September 1982 
in the amount of $128,230 was completed in August 
1983 with contractor's earnings for this fiscal year 
totalling $144,520. 
In progress at the end of the fiscal year was a 
contract awarded September 1983 in the amount of 
$17,150 for alteration of electrical power and lighting 
at Fort Norfolk. Contractor's earnings totalled 
$17,148 this fiscal year. In addition, contract work for 
the dredging of Sewell's Point Anchorage was 
delayed because a bid protest could not be resolved in 
time for substantial contract progress. The contract 
in the amount of $2.2 million is expected to be awarded 
in the first quarter of FY 1984. 
Maintenance engineering and design, supervision 
and administration, including environmental analysis, 
real estate activity and quantity surveys amounted 
to $478,804. Maintenance dredging of project 
channels and maintenance of pertinent project features 
will continue as required. 
11. OYSTER CHANNEL, VA. 
Location. Oyster Channel is located on the lower 
eastern side of the Delmarva Peninsula which 
separates Chesapeake Bay from the Atlantic Ocean. 
The project serves the town of Oyster, Va., about 11 
miles north of Cape Charles. (See U.S. Coast and 
Geodetic Survey Chart No. 12224.) 
Existing project. Provides for a channel 6 feet 
deep at mean low water and 80 feet wide from that 
depth in Liscombes Channel to the town of Oyster, 
Va., and a turning basin the same depth and about 8 
acres in area. The mean range of tide is about 4.4 feet. 
(See Table 5-B for Authorizing Legislation.) 
Local cooperation. Fully complied with for 
construction. For details see page 349 of Annual 
Report for 1956 and page 625 of Annual Report for 
1948. Local interests are to furnish spoil disposal 
areas as required for maintenance. 
Terminal facilities. Existing facilities are considered 
adequate. For details see page 221 of Annual 
Report for 1969. 
Operations during fiscal year. Conditions 
surveys were performed during July 1983 at a cost of 
$10,673. In addition, an A-E contract was awarded for 
$12,000 to prepare the project for maintenance 
dredging in FY 1984. 
5-8

NORFOLK, VA DISTRICT 
12. QUINBY CREEK, VA. 
Location. A natural channel on Atlantic Ocean 
side of Delmarva Peninsula about 32 miles north of 
Cape Charles and about 33 miles south of 
Chincoteague, Va. Creek extends in a generally 
southeasterly direction between Quinby Landing at 
Quinby, Va. and head of Tony Rock Drain, in Upshur 
Bay, a distance of 6,900 feet. (See U.S. Coast and 
Geodetic Survey Chart No. 12210). 
Existing project. Provides for a channel 8 feet 
depth in. Upshur Bay to point 600 feet bayward 
from Quinby Landing, thence 60 feet wide to Quinby 
Landing, a total distance of about 6,900 feet and a 
turning and mooring basin of the same depth, 200 feet 
wide and 400 feet long opposite public terminal and 
landing. Mean range of tide is 4.4 feet. Existing project 
was adopted by River and Harbor Act of 1950. (H. Doc. 
241, 81st. cong., 1st sess. which contains latest 
published map.) Project is complete, for details see 
Annual Report for 1964. 
Local cooperation. Fully complied with for initial 
construction. Local interests must provide spoildisposal 
areas for maintenance. 
Terminal facilities. There are two open-pile 
wooden wharves and about 125 feet of wooden 
bulkhead at Quinby, Va., which are privately owned. 
In addition, a number of berthing spaces, a wooden 
dock and launching ramp were constructed which are 
open to all on equal terms. These facilities are 
connected to the State Highway system by a suitable 
access road and are considered adequate. 
Operations during fiscal year. Quantity surveys 
were performed at a direct cost of $16,323. 
A defaulted maintenance dredging contract, 
awarded in fiscal year 1982 for $192,345 was completed 
October 1982. Total earnings amounted to 
$115,080 with 18,770 cubic yards of credited material 
being removed. 
Liquidated damages assessed the contractor 
resulted in a credit of $5,904. 
Maintenance supervision and inspection amounted 
to $3,005. 
13. RAPPAHANNOCK RIVER, VA. 
ViLrgoicnaiat iaonnd. flRowisse ss oiunt hB-elauset eRrlyid gaeb oMuto 2u1n2 tmaiinless itno 
enter Chesapeake Bay, about 40 miles north of Port 
Royal, Virginia (see Coast and Geodetic Survey Chart 
No. 12237). 
Existing project. A channel 12 feet deep and 200 
feet wide between mouth and Port Royal and 12 feet 
deep and 100 feet wide between Port Royal and Fredericksburg, 
by dredging and construction of 20,401 feet 
of crib and pile dikes and 1,906 feet of riprap of stone 
dikes designed to retain excavated material deposited 
behind them. Plane of reference is mean low water. 
Tidal ranges are mean 2.8 feet at Fredericksburg, 1.6 
feet at Tappahannock, irregular 3.5 feet at Fredericksburg, 
2.5 feet at Tappahannock, extremes 6 feet at 
Fredericksburg, 5 feet at Tappahannock. (See Table 5- 
B for Authorizing Legislation.) 
Local cooperation. None required. 
Terminal facilities. Existing facilities are considered 
adequate. For details see page 222 of Annual 
Report for 1969. 
Operations during fiscal year. Maintenance 
supervision and inspection, including condition 
surveys were performed at a cost of $8,000. 
Periodic maintenance dredging is being done below 
Fredericksburg Bar to maintain full project dimensions. 
14. SUPERVISION OF THE HARBOR 
OF HAMPTON ROADS 
(PREVENTION OF OBSTRUCTIVE 
AND INJURIOUS DEPOSITS) 
Laws enacted for the preservation of the Harbor of 
Hampton Roads, Virginia, its adjacent Chesapeake 
Bay and its tributaries as lies within the State of 
Virginia and so much of the Atlantic Ocean and its 
tributaries as lies within the jurisdiction of the United 
States, within or to the east of the State of Virginia, 
are administered by the Supervisor of the Harbor of 
Hampton Roads. Laws relating to the supervision of 
the Harbor of Hampton Roads and its tributary 
waters are the New York Harbor Act of 1888, as 
amended, the River and Harbor Act of 1899, the Clean 
Water Act, the Marine Protection, Research and 
Sanctuary Act of 1972, the Coastal Zone Management 
Act of 1972, the National Environmental Policy Act of 
1969, the Fish and Wildlife Act of 1956, the Federal 
Power Act of 1966, the Endangered Species Act of 
1973, the Deepwater Port Act of 1974, and the Marine 
5-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Mammal Protection Act of 1972, the Wild and Scenic 
Rivers Act, the Land and Water Conservation Fund 
Act. 
Direct supervision of the harbor was exercised by 
means of four patrol vessels (307 patrols, 2,456 manhours) 
involving debris removal, maintenance of 
buoys and fish stake limits, investigating reports of 
sunken vessels, navigational hazards and providing 
support for Federal dredging projects. Surveillance of 
the harbor, the Chesapeake Bay and its tributaries 
with respect to the regulatory permit program was 
conducted by means of three small outboards, 5-7 
motor vehicles and commercial aircraft for aerial 
surveys. The outboards were involved in 12 patrols (50 
man-hours) involving primarily compliance surveys 
of permitted dredging projects and evaluating navigational 
access to proposed pier projects. The motor 
vehicles were used to investigate 174 complaints of unauthorized 
activities. Commercial aircraft involved 
36 flights (144 man-hours) for the purpose of photographing 
proposed project sites, scoping for pre-application 
meetings and confirmed violations. 
An educational program continued in an effort to 
inform the public of the need and requirements for 
Department of the Army permits. This program was 
effectual through press releases, public notice, public 
talks and personal interviews with interested 
agencies, committees and private industries. 
Agreements and the monthly joint interagency 
meeting were continued with various Federal, State, 
and local agencies having related or similar 
responsibilities and functions to obtain maximum 
results with minimum costs by eliminating 
duplication of effort. The joint permit application and 
the joint public notice adopted between the Norfolk 
District and the State of Virginia have continued to 
result in decreases in the numerous forms of 
paperwork required to process a permit application. 
The Norfolk District's Regulatory Functions 
Branch continued to maintain the Northern Neck Project 
Office and the Eastern Shore Project Office in 
Accomac, Virginia. Each of these project offices 
provide readily available Corps perisonnel to assist 
waterfront owners, contractors, and the general public 
with their questions and problems on waterfront 
construction and the permit requirements of the Corps 
regulatory program. 
Disposition of legal actions during fiscal year: 
Of the 174 complaints of unauthorized activities, 
127 were determined to be valid violations of Federal 
law. When combined with the 79 carried over from last 
fiscal year, 206 unauthorized activities were investigated 
and monitored. Resolution of these violations 
were as follows: 93 through voluntary restoration; 29 
through either the issuance of permit modifications or 
after-the-fact permits; 2 through permit suspension 
and subsequent restoration; 2 through litigation; 3 
through consent decrees with civil penalties totaling 
$3,000; and 17 were referred to the Norfolk District's 
District Counsel or to the U.S. Attorney's Office for 
prosecution. The remaining 55 are in various stages of 
resolution or investigation. 
15. TANGIER CHANNEL VA. 
Location. A tidal channel about 2 miles long 
extending from Tangier Island, Virginia, 
northeasterly to deepwater in Tangier Sound, 
Chesapeake Bay and northwesterly to deep water on 
Chesapeake Bay. (See Coast and Geodetic Chart No. 
12228.) 
Existing project. A channel 8 feet deep at mean 
low water and 100 feet wide from 8-foot contour to 
Tangier Sound to day marker No. 4, and thence 8 feet 
deep and 60 feet wide to the town of Tangier, with an 
anchorage basin adjacent of town 400 feet square and 
7 feet deep. A channel 7 feet deep and 60 feet wide for 
about 4,000 feet from the anchorage basin 
northwesterly across Tangier Island to Chesapeake 
Bay. Mean range of tide is 1.7 feet and extreme tidal 
range is 4.7 feet. (See Table 5-B for Authorizing 
Legislation.) 
Local cooperation. Complied with except that 
local interests must furnish spoil disposal area as 
needed for future maintenance. 
Terminal facilities. Accomack County 
constructed a public dock in 1961. There are four 
privately-owned docks adjacent to existing project 
and two marine railways. 
Operations during fiscal year. A maintenance 
dredging contract awarded in August 1982 in the 
amount of $326,460 was completed October 3, 1982. 
There were 8,991 cubic yards of credited material 
removed at a direct cost of $16,801. 
Operation of the project including aerial photography 
and condition surveys amounted to $1,691. 
Maintenance engineering and design and supervi- 
5-10

NORFOLK, VA DISTRICT 
sion and inspection including A-E services and 
quantity surveys amounted to $48,453. Periodic 
maintenance dredging will continue. 
16. THIMBLE SHOAL CHANNEL, VA. 
Location. In lower portion of Chesapeake Bay 
between Hampton Roads and the ocean, 20 miles 
northeast of center of Norfolk Harbor, extending 
southeasterly 12 miles from a point 1.25 miles east of 
Thimble Shoal Lighthouse toward entrance to 
Chesapeake Bay. (See Coast and Geodetic Survey 
Chart 1222.) 
Existing project. Provides for dredging a channel 
12 miles long, 1,000 feet wide, and 45 feet deep at mean 
low water with auxiliary channels 450 feet wide and 
32 feet deep at mean low water adjoining each side of 
1,000-foot channel. Under ordinary conditions mean 
tidal range is 2.5 feet and extreme 3 feet. Extremes of 
irregular fluctuation, due to combined wind and tides 
referred to mean low water, and minus 3 feet and plus 
7 feet. For details of previous projects see Annual 
Report for 1932. (See Table 5-B for Authorizing 
Legislation.) 
Local cooperation. None required. 
Terminal facilities. Project serves as an entrance 
channel to Hampton Roads. See "Norfolk Harbor, 
Va,." "Channel to Newport News, Va.," etc. 
Operations during fiscal year.Underruns on the 
maintenance dredging contract completed at the end 
of Fiscal Year 1982 amounted to a credit of $59,203. 
Maintenance engineering and design and supervision 
and administration including quantity surveys, 
value engineering and disposal area study amounted 
to $312,029. Periodic maintenance dredging will continue 
as required. 
17. WATERWAY ON THE COAST 
OF VIRGINIA 
Location. Between barrier beach along Atlantic 
Ocean on the east and Virginia portion of mainland 
peninsula on the west. It extends for 83.7 miles from 
south end of Chincoteague Bay through a number of 
creeks, throughfares, and bays to enter Chesapeake 
Bay in the vicinity of Fisherman Island, just south of 
Cape Charles on the southern tip of the peninsula. 
(See Coast and Geodetic Survey Chart Nos. 12211, 
12210, and 12221.) 
Existing projects. An island waterway 6 feet deep 
at mean low water and 60 feet wide from Chesapeake 
Bay to Chincoteague*Bay, Virginia. Mean range of 
tide is about 3 feet. Greater fluctuations in water level 
are caused by high winds and storms. A modification 
of the project approved during 1970 under Section 201 
of the Flood Control Act of 1965 authorizes relocation 
of portions of the waterway and widening to 100 feet. 
(See Table 5-B for Authorizing Legislation.) 
Local cooperation. Complied with except that 
local interests are to furnish spoil disposal areas for 
future maintenance. 
Terminal facilities. Existing facilities are 
considered adequate. For details see Annual Report 
for 1969. 
Operations during fiscal year. A maintenance 
dredging contract, funded under the 1983 Jobs Bill 
Act, was awarded August 2, 1983 in the amount of 
$843,045. White Trout Creek, Bradford, Burton's and 
Swash Bays were dredged between the period August 
21st thru September 30,1983. There were an estimated 
415,359 cubic yards of credited material removed at a 
direct cost of $558,000. 
Condition surveys of 8 separate reaches of the project 
were performed from February -August 1983 at a 
direct cost of $134,536. 
Ordinary operation of the project to include tide 
gauging and a disposal analysis amounted to $92,425. 
Maintenance engineering and design and supervision 
and administration costs amounted to $216,275. Periodic 
maintenance will continue as required. 
18. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Two detailed project reports were in progress at the 
end of the fiscal year: Little Creek, Gloucester County 
and Rudee Inlet, Virginia. 
One detailed project report: Back Creek, York 
County was terminated during the year due to lack of 
local cooperation. 
Two Reconnaissance Reports: Little Machipongo 
River, Northampton County, Va. and Bennett Creek, 
Suffolk, Va., were still in progress at the end of the 
year. 
A negative reconnaissance report was completed on 
Rappahannock River, Va. 
5-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Beach Erosion Control 
19. VIRGINIA BEACH, VA. 
Location. On the Atlantic Seaboard, 22 miles 
north of Virginia-North Carolina State line, 3.5 miles 
south of Cape Henry, and 19 miles east of Norfolk, Va. 
(See Coast and Geodetic Survey Chart 12207.) 
Existing project. Federal participation in 
restoration and protection of shore of Virginia Beach 
between Rudee Inlet and 49th Street by artificial 
placement of sand to provide a minimum beach width 
of 100 feet at elevation 7 feet above mean low water, 
and maintenance of such beach by periodic replenishment 
of losses to insure continuous protection; 
including construction of a groin system to 
be undertaken at such times as estimated annual 
charges therewith would be less than the annual 
cost of beach replenishment alone. The United States 
shall participate in the first cost of the project to the 
full extent of its proportionate share of cost as a 
landowner, plus one third total first cost of restoring 
and protecting all publicly-owned sections of the 
shore. The 1962 modification provided that the United 
States shall further participate in periodic beach 
nourishment of the beach in the amount of one third 
the cost for 25 years from date of commencement of 
operations in placing an initial quantity of 
nourishment material equal to deficiency in the 
design beach at that time. Section 103 of the 1962 
River and Harbor Act increased Federal participation 
to one-half of the cost incurred after October 23, 1962. 
Estimated Federal cost (1982) is $5,500,000. Estimated 
cost to local interests is $5,500,000. Construction of the 
groin system is not included in the above estimate. 
The 1962 estimate for this work was $549,000 Federal 
cost and $531,000 cost to local interests. The 1974 
modification provides for structural and nonstructural 
improvements. Structural measures would 
be provided for the 6 mile reach of shoreline between 
Rudee Inlet and 89th Street. This would include 
raising the beach to elevation 10 feet and a width of 
100 feet, driving a sheet pile wall just seaward of the 
existing bulkhead from Rudee Inlet to 57th Street; and 
raising and strengthening sand dunes from 57th to 
89th Streets. The estimated cost (1982) of the 
structural improvements are Federal $35,000,000 and 
non-Federal $18,200,000. (See Table 5-B for 
Authorizing Legislation.) 
Local cooperation. Requirements are described 
in full on page 5-11 of Fiscal Year 1981 Annual Report. 
Necessary changes in requirements will be made if the 
1974 modification is constructed. 
Operations during fiscal year. Preconstruction 
Planning of the 1974 modification was continued at a 
cost of $360,890. 
Local interests were reimbursed $334,779 for the 
Federal Share of periodic nourishment of the beach, 
and Federal Costs pertinent thereto amounted to 
$28,734. 
Preconstruction planning is continuing on the 1974 
modification and beach replenishment is continuing 
on the 1962 project. 
20. BEACH EROSION CONTROL 
WORK UNDER SPECIAL 
AUTHORIZATION 
None this fiscal year. 
Flood Control 
21. GATHRIGHT DAM AND LAKE 
MOOMAW, VA. 
Location. Site of proposed Gathright Dam is on 
Jackson River, a tributary of James River at mile 43.4 
and Alleghany County. Gathright Dam site is in 
reach of Jackson River known as the Gorge. About 19 
miles upstream from Covington, Va. at the elevation 
at the top of the conservation pool, Gathright 
Reservoir will extend upstream about 9 miles (see 
Falling Spring and Mountain Grove, Virginia-West 
Virginia quadrangles of geological survey.) 
Existing project. Gathright Dam consists of a 
1,172-foot long rolled rock filled dam with an 
impervious core, with a top at elevation 1,684.5; outlet 
works consisting of a concrete intake structure located 
in the right back 500 feet upstream from the axis of the 
dam: a 1,075-foot long outlet tunnel through the right 
abutment and a stilling basin; and a 2,450-foot long 
fixed crest emergency spillway excavated in a low 
saddle in the divide at Fortney Branch, about 2.5 miles 
south of the dam. Discharges through the maximum 
conservation pool elevation 1,582 will be provided for 
water quality control. The reservoir area at elevation 
1,582 will be 2,530 acres. A total of 302,000 acre-feet of 
storage between elevation 1,582 and the spillway crest 
(elevation 1,663.5) will be reserved for flood control. At 
5-12

NORFOLK, VA DISTRICT 
the spillway crest the reservoir will have an area of 
4,540 acres. Last approved estimated Federal cost 
(1979) is $83,000,000. (See Table 5-B for Authorizing 
Legislation.) 
Local cooperation. None required. 
Operations during fiscal year.Contract and in 
house work for project piezometers amounted to 
$43,555. 
Final miscellaneous contract work on the Administration 
Building amounted to $21,817. 
Other contracts, including radio facilities, stream 
gauging and rainfall gauging, were completed at a 
cost of $94,127. 
Engineering and design and supervision and 
administration including real estate costs totalled 
$34,222. 
Operation and maintenance of the completed 
portion of the project amounted to $838,172. 
Project is complete and became operational for flood 
control in December 1979. 
22. RAPIDAN RIVER, VA. 
Location. The town of Orange is located approximately 
50 miles west of Fredericksburg and about 30 
miles northeast of Charlottesville. The project area is 
on the Rapidan River approximately 2 miles northwest 
of the town. 
Previous projects. None. 
Existing project. The Project consists of reconstructing 
the eroded streambank above the intake 
structure to the town's water treatment plant. The 
length of restoration is 100 feet. Removal of an 
abandoned railroad bridge pier and debris jam is also 
included in the project. 
Local cooperation. The local interests will: 
a. Provide without cost to the United States all 
lands, easements, and rights-of-way necessary for 
construction, operation and maintenance of the project, 
inclluding all necessary authorizations and permits 
that may be required to remove structures located 
in the Rapidan River; currently estimated at $7,200; 
b. Hold and save the United States free from damages 
due to the construction, operation and maintenance 
of the project except where such damages are due 
to the fault or negligence of the United States or its 
contractors; 
c. Maintain and operate all the works after completion 
in accordance with regulations prescribed by 
the Secretary of the Army; 
d. Assume full responsibility for all project costs in 
excess of the Federal cost limitation of $250,000; 
e. The town in acquiring lands, easements, and 
rights-of-way for project construction, operation and 
maintenance will comply with the provisions of the 
Uniform Relocation Assistance and Real Property 
Acquisition Policy Act of 1970 (Public Law 91-646, 
approved 2 January 1971); and 
f. The town will comply with Section 601 of Title 
VI of the Civil Rights Act of 1964 (Public Law 88-352) 
to wit: That no person shall be excluded from 
participation in, denied the benefits of, or subjected to 
discrimination in connection with this project on the 
grounds of race, color, or national origin. 
In addition, Section 221 of Public Law 91-611 (Flood 
Control Act of 1970) required that "Construction of 
any water resources project by the Secretary of the 
Army...shall not be commenced until each non- 
Federal interest has entered into a written agreement 
with the Secretary of the Army to furnish its required 
cooperation for the project." The agency responsible 
for the fulfillment of these requirements is the town of 
Orange, Virginia. 
Operations during fiscal year. Project was 
approved for construction in January 1983. Plans and 
specifications were completed this fiscal year at a 
total cost of $15,488. A contract for new construction 
was awarded September 30, 1983 in the amount of 
$24,885, and funded by the 1983 Jobs Bill Act; contract 
completion is scheduled in Fiscal Year 1984. 
23. VIRGINIA BEACH STREAMS 
CANAL NUMBER 2,VA. 
Location. The canal number 2 watershed with a 
drainage area of about 37 square miles lies within the 
city of Virginia Beach. The city consist of 255 square 
miles of primarily low, flat terrain with about 75 
percent of the area below elevation 15-feet, mean sea 
5-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
level. The existing canal, from the Eastern Branch of 
the Lynnhaven River to the North Landing River is 
about 12 miles long and follows a north-south 
alignment. (See Coast and Geodetic Survey Chart No. 
12205.) 
Existing project. The project will provide for 
construction of a new canal for a length of 2.6 miles 
and channelization of an existing canal for a length of 
1.1 miles. The canal bottom width will range from 45 
feet to 80 feet and a depth from -4 feet mean sea level to 
-8 feet mean sea level with a flow capacity great 
enough to carry a 100 year flood. Its construction will 
require dredging 741,000 cubic yards of material. 
Local cooperation. Requirements are described 
in full on page 5-14 of FY 81 Annual Report. 
Requirements may change if legislation is enacted 
regarding new cost-sharing proposals. 
Operations during fiscal year. Plans and 
specifications initiated in FY 1982 were completed at a 
total cost of $57,446. All preconstruction planning is 
complete. 
24. FLOOD CONTROL WORK 
UNDER SPECIAL 
AUTHORIZATION 
A reconnaissance report for Cooper's Ditch, 
Chesapeake, VA initiated October 1982 was terminated 
late in the fiscal year. The City of Chesapeake 
proceeded on its own in solving the flood problem. 
25. EMERGENCY FLOOD 
CONTROL ACTIVITIES 
During the fiscal year, $71,666 was spent on the 
Disaster Preparedness Program. In addition, a 
contract was awarded July 1983 in the amount of 
$238,800 to repair the Jamestown Island Seawall. At 
year's end the contract was 33% complete with 
contractor's earnings totalling $50,000. Other costs 
associated with the project including Real Estate 
activity, supervision and administration and inhouse 
design amounted to a direct cost of $41,859. 
26. GENERAL INVESTIGATIONS 
SURVEYS 
Total cost of surveys during the fiscal year 
amounted to $947,247 of which $136,754 was for 
navigation studies; $397,603 was for flood control 
studies; $26,000 was for special investigations; $4,000 
was for FERC licensing; $2,000 for review of watershed 
plans of the Soil Conservation Service; $22,000 
coordination studies with other agencies and $360,890 
for flood control, local protection, Legislative Phase I 
studies. 
27. COLLECTION AND STUDY OF 
BASIC DATA 
During the fiscal year, cost of collection and study of 
Basic Data was $120,492. Major emphasis during the 
fiscal year was on management and technical 
services under the Flood Plain Management Studies. 
28. CONTINUATION OF 
PLANNING AND ENGINEERING 
During FY 83, work continued on the Norfolk 
Harbor Deepening Project. Extensive environmental 
studies, economic studies, public involvement and 
agency coordination, Channel design, mapping and 
field surveys and other studies for design of the 55-foot 
channel and anchorage plan were accomplished. 
Total cost during the year amounted to $2,816,739. 
Work on this C P & E study is continuing with completion 
scheduled for September 1986. 
5-14

NORFOLK, VA DISTRICT 
TABLE 5-A COST AND FINANCIAL STATEMENT 
See Total Cost To 
Section Project Funding FY 80 FY 81 FY 82 FY 83 Total Cost To 
In Text 30 Sept 1983 
1. Atlantic Intracoastal 
Waterway, between 
Norfolk, Va. and the 
Saint John's River, 
Fla. (Norfolk 
District) 
(Regular Funds) 
2. Baltimore Harbor 
Channels (Norfolk 
District) (Regular 
Funds) 
3. Broad Creek, Va. 
(Regular Funds) 
(Contributed 
Funds) 
4. Cape Charles 
City Harbor, Va. 
(Regular Funds) 
5. Chincoteague Bay, 
Va. (Regular Funds) 
6. Chincoteague Inlet, 
Va. (Regular Funds) 
(Contributed 
Funds) 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major rehab. 
Approp. 
Cost 
Recreation 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
1,688,000 2,444,800 2,025,000 2,077,000 
1,767,686 2,443,074 1,598,261 1,415,832 
479,947 
479,947 
59,871 
59,871 
32,000 14,108 1,663,300 1,079,000 
30,931 15,177 696,090 1,885,518 
14,851 
14,851 
2,271 
2,271 
10,026 112,628 
10,026 112,628 
13,478 
13,916 
8,198 46,945 
8,198 24,945 
- 9,798 
- 8,545 
9,305 290,662 192,980 
9,305 290,662 192,399 
429,000 855,713 639,131 708,366 
435,114 853,155 620,913 625,959 
8,015,0703 
8,015,0703 
8,549,4863 
8,388,7943 
27,888 
27,888 
128,715 
106,715 
622,644 
622,644' 
460,984 
459,731 
25,126 
25,126 
370,536 
369,955 
227,000 
227,000 
3,080,210 
2,976,492 
5-15 
3,688,372' 
3,688,372' 
39,420,4952 
38,286,5072 
500 
500 
3,850 
3,850

TABLE 5-A (Cont.) 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
COST AND FINANCIAL STATEMENT 
See Total Cost To 
Section Project Funding FY 80 FY 81 FY 82 FY 83 30 st To 
In Text 30 Sept 1983 
7. Hampton Roads and 
Harbors of 
Norfolk and Newport 
News, Va. Collection 
and Removal of 
Drift (Regular Funds) 
8. James River, Va. 
(Regular Funds) 
(Contributed 
Funds) 
9. Lynnhaven Inlet, 
Va., (Regular 
Funds) 
(Contributed 
Funds) 
10. Norfolk Harbor, 
Va. (Regular Funds) 
(Contributed 
Funds) 
11. Oyster Channel, 
Va. (Regular Funds) 
12. Quinby Creek, Va. 
(Regular Funds) 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
133,000 177,000 105,493 155,000 
140,867 148,731 117,604 120,910 
�- , -. ,- 
1,597,195 1,124,000 2,811,254 1,440,000 
521,781 1,895,528 2,823,448 1,689,700 
50,000 16,000 
- 66,000 
50,000 
50,000 
5,000 81,000 24,629 - 
4,179 77,949 28,501 - 
47,091 74,724 472,034 28,592 
47,091 74,724 472,033 28,593 
- 7,017 
- 2,620 
- 112,358 
- 102,900 
2,850,000 
2,774,403 
4,313 
9,458 
30,152 60,811 (-)2,548 
2,965,500 2,836,562 6.310,744 7,305,699 
2,946,346 2.315,198 4,777,927 4,648,737 
125,544 
30.000 125,544 
9,747 27,988 30,169 32,666 
9,747 27.988 30,169 10,673 
5-16 
2,408,112 
2,356,044 
7,639,9046 
7,639,9046 
23,858,051 
23,596,307 
294,456 
294,456 
445,354 
445,354 
1,504,165 
1,504,165 
98,664 
98,580 
139,158 
139,158 
36,399,115 
36,393,1026 
61,084,0017 
56,338,738' 
179,480 
179,480 
119,117 
119,117 
328,295 
306,302 
104,176 
104,176

,NORFOLK, VA DISTRICT' 
TABLE 5-A (Cont.) COST AND FINANCIAL STATEMENT 
See 
Section Project Funding FY 79 FY 80 FY 81 FY 82 Total Cost To191 
In Text 30 Sept 1981 
Maint: 
Approp. 
Cost 
13. Rappahannock River, 
Va. (Regular Funds) 
14. Supervision of 
Harbor of Hampton 
Roads, Va. 
(Regular Funds) 
15. Tangier Channel, 
Va. (Regular Funds) 
16. Thimble Shoal 
Channel, Va. 
(Regular Funds) 
17. Waterway on the 
Coast of Va. 
(Regular Funds) 
19. Va. Beach, Va. 
(Regular Funds) 
(Contributed 
Funds) 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major Rehab 
Approp 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
38,326 10,969 286,050 (-)13,418 
38,326 10,969 144,129 128,504 
6,558 
6,558 
4,563 
4,563 
561 
561 
8,000 
8,000 
151,000 235,000 192,000 212,000 
169,070 228,949 190,547 176,835 
254,560 60,864 434,918 (-)7,881 
254,764 60,862 360,094 66,945 
59,693 1,117,000 4,211,000 58,731 
59,693 312,346 4,791,677 252,826 
224,000 460,000 1,696,000 1,354,300 
224,343 461,065 1,678,264 1,001,236 
300,000 326,000 364,000 380,000 
294,771 344,457 352,585 363,513 
5-17 
731,207 
731,207 
414,6338 
414,6338 
1,958,3609 
1,958,3609 
168,091 
168,091 
4,364,928 
4,321,058 
116,550 
116,550 
1,802,082 
1,802,082 
13,534,967 
13,534,967 
10,920,025 
10,890,143 
850,498 
850,498 
9475,632 
9,103,300 
3,510,195 
3,481,936 
204,683 
204,683

TABLE 5-A (Cont.) 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
COST AND FINANCIAL STATEMENT 
See 
Section Project Funding FY 80 FY 81 FY 82 FY 83 Total Cost To 
In Text in Text 30 Sept 1983 
21. Gathright Dam & Lake 
Moomaw, Va. New Work 
(Regular Funds) Approp. 2500,000 1,846,000 (-)14,000 - 80,670,527 
Cost 6,600,227 2,236,333 527,222 193,721 80,670,527 
Maint. 
Approp. 876,000 989,000 729,000 833,000 4,687,000 
Cost 847,395 984,540 683,273 838,172 4,584,933 
22. Rapidan River, New Work 
Va. (Regular Funds) Approp. - - - 52,000 52,000 
Cost - - - 15,489 15,489 
23. Va. Beach Streams, New Work 
Canal Number 2, Va. Approp. 82,000 120,000 85,000 33,000 420,000 
Cost 84,244 24,232 139,577 57,446 402,047 
'Includes $292,096 for previous projects. 2 Includes $52,804 for previous projects. 
3Cost prior to 1942 are included in the project "Baltimore 
Harbor and Channels, MD" (Baltimore District). Cost listed 
are for York Spit Channel, VA, Rappahannock Shoal Channel, 
VA, and Cape Henry Channel, VA. 
4Includes $445,291 military funds expended from new 
work dredging on existing project and $83,041 expended from 
military funds for construction of a wharf. 
5lncludes $763,000 for previous projects. 
6includes $2,561,704 for previous projects and new work. 
'Includes $72,039 for previous projects. 8lncludes $197,146 for previous projects. 
*lncludes $113,500 for previous projects. 
5-18

NORFOLK, VA DISTRICT 
TABLE 5-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Mar. 3, 1899 
July 25, 1912 
July 25, 1912 
Mar. 3, 1925 
July 3, 1930 
June 26, 1934 
Mar. 2, 1945 
July 3, 1958 
Dec. 31, 1970 
July 3, 1958 
Dec. 31, 1970 
Mar. 3, 1905 
Mar. 4, 1913 
July 3, 1930 
Mar. 2, 1945 
July 3, 1958 
Dec. 31, 1970 
Mar. 2, 1945 
Sept. 19, 1890 
ATLANTIC INTRACOASTAL WATERWAY BETWEEN 
NORFOLK, VA. AND ST. JOHNS RIVER, FLA. 
(NORFOLK DISTRICT) (See Section 1 of Text) 
Existing project dimensions and original route, waterway 
from Norfolk, Va. to sounds of North Carolina 
Original route to Norfolk-Beaufort Inlet section 
Purchase of Albemarle & Chesapeake Co. Canal 
Purchase of Lake Drummond Canal (Dismal Swamp Canal) 
Construct a tidal lock at Great Bridge at a cost not to exceed 
$500,000 
Operating and care of works of improvement provided for with 
funds from War Department appropriations for rivers and 
harbors 
Construct dikes for protection of canal property against 
floodtides 
BALTIMORE HARBOR AND CHANNELS (NORFOLK 
DISTRICT) (See Section 2 of Text) 
CAPE HENRY CHANNEL, VA. (See Section 2 of Text) 
A channel 42 feet deep, 1,000 feet wide 
Channel depth increased to 50 feet 
RAPPAHANNOCK SHOAL CHANNEL, VA. 
(See Section 2 of Text) 
Channel 42 feet deep and 800 feet wide 
Channel width increased to 1,000 feet and depth increased 
to 50 feet. 
YORK SPIT CHANNEL, VA. (See Section 2 of Text) 
Channel 35 feet deep, 600 feet wide 
Channel width increased to 1,000 feet 
Channel depth increased to 37 feet 
Channel depth increased to 39 feet 
Channel depth increased to 42 feet 
Channel depth increased to 50 feet 
BROAD CREEK, VA. (See Section 3 of Text) 
Channel 7 feet deep, 100 feet wide 
CAPE CHARLES CITY HARBOR (See Section 4 of Text) 
Dredging a channel through Cherrystone Inlet and bar 
H. Doc. 317, 54th Cong., 1st sess. 
AR 1896 
H. Doc. 131, 55th Congs., 3d sess. 
AR 1899 
H. Doc. 391, 62d Congs., 2d sess. 
H. Doc. 589, 62d Cong., 2d sess. 
Rivers & Harbors Comm. Doc. 
67th Cong., 2d sess. 
S. Doc. 23. 71st Cong., 1st sess.1 
Not available 
H. Doc. 117, 76th Cong., 1st sess. 
H. Doc. 86, 85th Cong., 1st sess. 
Chief of Engineers Report Sept. 21, 1970 
H. Doc. 86, 85th Cong., 1st sess. 
Chief of Engineers Report, Sept. 21, 1970 
H. Doc. 186, 57th Cong., 2d sess. 
H. Doc. 190, 62d Cong., 3d sess. 
H. Doc. 29, 71st Cong., 1st sess. 
H. Doc. 741, 79th Cong., 2d sess. 
H. Doc. 86, 85th Cong., 1st sess. 
Chief of Engineers Report Sept. 21, 1970 
H. Doc. 381, 76th Cong., 1st sess. 
5-19

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 5-B (Cont.) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
June 20, 1938 
Mar. 2, 1945 
Aug. 26, 1937 
July 14, 1960 
(Sec. 107) 
May 17, 1950 
July 5, 1884 
June 13, 1902 
Mar. 3, 1905 
July 3, 1930 
Aug. 26, 1937 
Mar. 2, 1945 
May 17, 1950 
Oct. 23, 1962 
16 feet deep and 100 and 200 feet wide, respectively, 
dredging an entrance channel 100 feet wide, 16 feet 
deep, dredging a harbor 11 acres in area, 14 feet deep; 
and construct stone jetties on each side of entrance to 
harbor. 
Modified to provide a basin 10 feet deep, 180 feet wide, 
and 420 feet long, at head of Mud Creek, with a 
channel 10 feet deep and 100 feet wide, extending 
to that depth in present harbor, flaring through 
its inner 250 feet to a width of 180 feet. 
A channel 18 feet deep and 500 feet wide from that 
depth in Chesapeake Bay to harbor entrance, 
thence a basin in harbor of same depth 600 to 
1,000 feet wide and 3,000 feet long. 
The harbor of refuge was approved in 1966 by the 
Chief of Engineers under authority of Section 
107, River and Harbor Act of 1960. 
CHINCOTEAGUE BAY, VA. (See Section 5 of text) 
L-shaped harbor 5-feet deep, 60 feet wide 
and 1,500 feet long with approach channel of 
same depth and width. 
CHINCOTEAGUE INLET, VA. (See Section 6 of Text) 
Existing project 
HAMPTON ROADS AND HARBORS OF NORFOLK AND 
NEWPORT NEWS, VA. COLLECTION AND REMOVAL 
OF DRIFT (See Section 7 of Text) 
Collection and removal of floating debris in Hampton roads and 
its tributary waters 
JAMES RIVER, VA. (See Section 8 of Text) 
Channel 22 feet deep from mouth of Richmond and construct 
spur and training dikes 
Extension of improvement to Richmond lock gate 
Form a turning basin by widening channel at Richmond 
Channel 25 feet deep mouth to Richmond Deepwater Terminal 
Removal of Trigg cofferdam 
Turning basin at Richmond Harbor 
Maintaining turning basin at Richmond Deepwater Terminal 
Channel depth increased to 35 feet to Richmond Deepwater 
Terminal 
H. Doc.29 51st Cong. 
1st sess. and Annual Report 
1890, p. 971 
H. Doc. 580, 75th Cong., 
3d sess. (Contains latest 
published map.) 
H. Doc. 90, 79th Cong. 
1st sess. (Contains latest 
published map.) 
H. Doc. 23, 75th Cong., 1st sess.2 
Approved in 1972 
Specified in Act 
S. Ex. Doc. 714, 47th Cong., 1st sess. 
H. Doc. 234, 56th Cong., 1st sess. 
H. Doc. 234, 56th Cong., 1st sess. 
H. Doc. 314, 71st Cong., 2d sess. 
Rivers & Harbors Comm. Doc. 68 
74th Cong., 1st sess. 2 
H. Doc. 738, 77th Cong., 2d sess. 
H. Doc. 191, 81st Cong., 1st sess. 
H. Doc. 586, 87th Cong.,2d sess. 
5-20

NORFOLK, VA DISTRICT 
TABLE 5-B (Cont.) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Oct. 23, 1962 
July 14, 1960 
(Sec. 107) 
Mar. 2, 1907 
June 25, 1910 
Aug. 8, 1917 
Sept. 3, 1954 
Oct. 27, 1965 
June 25, 1910 
Aug. 8, 1917 
Mar. 30, 1925 
Aug. 30, 1935 
June 30, 1948 
Oct. 27, 1965 
Oct. 22, 1976 
Mar. 2, 1907 
Mar. 3, 1925 
July 3, 1930 
LYNNHAVEN INLET, VA. (See Section 9 of Text) 
Existing project. 
Long Creek, Lynnhaven Inlet modification 
NORFOLK HARBOR, VA. (See Section 10 of Text) 
Hampton Roads and Elizabeth River 
Channel 30 feet deep to Navy Yard 
Depth of 35 feet to Navy Yard. 
Depth of 40 feet and width of 750 feet to mouth of Southern 
Branch. 
Widen 40-foot channel to 1,500 feet from 40-foot contour in 
Hampton Roads to a point just south of Norfolk 
International Terminal. 
45 feet deep Ft. Wool to Lambert Point, 800 feet wide Norfolk 
International Terminal to Lambert Point. 
SOUTHERN BRANCH 
Channel with a depth of 22 and 25 feet. 
Depth of 40 feet and width of 450 feet from mouth to Belt Line 
RR Bridge. 
Channel 30 feet deep and 375 feet wide to Virginia Ry. bridge: 
thence 25 feet deep and generally 200 feet wide to Norfolk & 
Western RR Bridge. 
Depth of 25 feet and width of 200 feet from Norfolk & Western 
RR bridge to a point 2,500 feet above with a turning basin 500 
feet square. 
Approach and turning area 40 feet deep and a maximum width 
of 830 feet opposite Norfolk Naval Shipyard: thence a channel 
35 feet deep and 375 and 250 feet wide to a point 1900 feet 
above Norfolk & Western RR bridge and a turning basin 35 
feet deep and 600 feet at upstream end. 
45 feet deep Belt Line bridge to Old Virginia bridge, 35-foot 
deep turning basin opposite St. Julians Creek. 
Extend existing 35-foot project to a channel 35 feet deep and 
250 feet wide upstream 1.5 miles to the Norfolk and 
Portsmouth Belt Line RR bridge and a turning basin at the 
mouth of Mains Creek 35 feet deep and 800 feet square. 
EASTERN BRANCH 
Width of 500 feet and depth of 25 and 22 feet. 
Removel of shoals at mouth. 
Depth of 25 feet and width of 200 feet from Norfolk & Western 
RR bridge to Virginia RR bridge. 
30-foot channel to a point opposite terminal of Imperial 
Tobacco Co. in Berkley. 
H. Doc. 580, 87th Cong., 2d sess. 
Approved in 1982 
H. Doc. 381, 59th Cong., 1st sess. 
H. Doc. 551, 61st Cong., 2d sess. 
H. Doc. 140, 65th Cong., 1st sess. 
S. Doc. 122, 83rd Cong., 2d sess. 
H. Doc. 187, 89th Cong., 1st sess. 
H. Doc. 551, 61st Cong., 2d sess. 
H. Doc. 140, 65th Cong., 1st sess. 
H. Doc. 226, 68th Cong., 1st sess. 
H. Doc. 182, 73d Cong., 2d sess.2 
H. Doc. 545, 80th Cong., 2d sess. 
H. Doc. 187, 89th Cong., 1st sess. 
H. Doc. 355, 94th Cong., 2d sess. 
H. Doc. 373, 59th Cong., 1st sess. 
Specified in act 
H. Doc. 226, 68th Cong., 1st sess. 
H. Doc. 37, 71st Cong., 1st sess.3 
5-21

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 5-B (Cont.) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Mar. 2, 1945 
Mar. 4, 1913 
July 3, 1930 
July 3, 1930 
June 25, 1910 
Aug. 8, 1917 
Sept. 3, 1954 
Oct. 27, 1965 
Mar. 2, 1945 
Sept. 3, 1954 
May 17, 1950 
Mar. 3, 1871 
Mar. 3, 1879 
Mar. 3, 1905 
Depth of 25 feet and width of 300 feet from Norfolk & Western 
RR bridge to Campostella bridge. 
WESTERN BRANCH 
Channel 24 feet deep and 300 & 400 feet wide to West 
Norfolk highway bridge. 
For 18-foot channel to a point about 3,000 feet above West 
Norfolk highway bridge. 
SCOTTS CREEK 
Channel 12 feet deep and 100 feet wide to a point 100 feet above 
the Atlantic Coast Line RR bridge. 
ANCHORAGES 
30-foot anchorage at Lambert Point 
12-foot anchorage at Pinner Point 
An anchorage 38 feet deep and 1,500 feet square: anchorage 
35 feet deep and 1,500 feet square: and an anchorage 20 
feet deep, 1,000 feet wide and 3,000 feet long. 
Two anchorages opposite Sewells Point 45 feet deep with 
1,200-foot swinging radius. 
OYSTER CHANNEL, VA. (See Section 11 of Text) 
Channel 6 feet deep from Liscombes Channel to 
Oyster Channel including a turning basin of the 
same depth, 200 feet long and 125 feet wide. 
Existing project dimensions 
QUINBY CREEK, VA. (See Section 12 of Text) 
Existing project. 
RAPPAHANNOCK RIVER, VA. (See Section 13 of Text) 
Channel 8 feet deep through Spottswood 
and Fredericksburg bars 
Channel 150 feet wide and 10 feet deep through 
Fredericksburg bar, channels 100 feet wide and 10 
feet deep through four bars between Fredericksburg 
and Port Royal; channels 200 feet wide and 15 feet 
deep through two bars below Port Royal. 
Channel 100 feet wide and 10 feet deep through 
bars between Fredericksburg and Port Royal, 
channel 200 feet wide and 15 feet deep below 
Port Royal. 
H. Doc. 224, 76th Cong., 1st sess. 
H. Doc. 556, 62nd Cong., 2d sess. 
H. Doc. 265, 70th Cong., 1st sess. 
H. Doc. 189, 70th Cong., 1st sess. 
H. Doc. 551, 61st Cong., 2d sess. 
H. Doc. 605, 63rd Cong., 2d sess.1 
S. Doc. 122, 83rd Cong., 2d sess.1 
H. Docs. 187 & 143, 89th Cong., 1st sess. 
H. Doc. 716, 76th Cong., 3d sess. 
S. Doc. 49, 83d Cong., 1st sess. 
H. Doc. 241, 81st Cong., 1st sess. 
H. Doc. 60, 41st Cong., 3d sess. 
Rivers and Harbor Act of 1879 
H. Doc. 412, 57th Cong., 2d sess. 
5-22

NORFOLK, VA DISTRICT 
TABLE 5-B (Cont.) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
TANGIER CHANNEL, VA. (See Section 15 of Text) 
Mar. 2, 1919 Channel from Tangier Sound and anchorage. H. Doc. 107, 63rd Cong., 1st sess. 
Jan. 3, 1934 Changed channel and anchorage dimensions. Rivers & Harbors Comm. 
(P.W.A. Act) Doc. 51, 72nd Cong., 2d sess. 
and Aug. 30 1935 
Mar. 2, 1945 Modified project dimensions. H. Doc. 141, 77th Cong., 1st sess. 
July 14, 1960 Channel across Tangier Island. Approved in 1964 
(Sec. 107) 
THIMBLE SHOAL CHANNEL, VA. (See Section 16 of Text) 
Aug. 8, 1917 A channel 40 feet deep and 750 feet wide. H. Doc. 140, 65th Cong., 1st sess. 
Sept. 3, 1954 Channel width increased to 1,000 feet with side channels on S. Doc. 122, 83d Cong., 2d sess.' 
either side 32 feet deep and 450 feet wide. 
Oct. 27, 1965 Channel 45 feet deep and 1,000 feet wide. H. Doc. 187, 89th Cong., 1st sess. 
WATERWAY ON THE COAST OF VIRGINIA (See Section 
17 of the Text) 
June 25, 1910 Existing project adopted. H. Doc. 957, 60th Cong., 1st sess. 
Mar. 2, 1945 Project modified. H. Doc. 268, 76th Cong., 1st sess. 
Oct. 27, 1965 Project widened to 100 feet, partially relocated, and Approved in 1970. 
(Sec. 107) incorporated in Delaware Bay-Chesapeake Bay Waterway in 
Delaware-Maryland-Virginia. 
VIRGINIA BEACH, VA. (See Section 19 of Text) 
Sept. 3, 1954 Project authorized. H. Doc. 186, 83rd Cong., 1st sess, 
Oct. 23, 1962 Project modified. H. Doc. 382, 87th Cong., 2d sess. 
Mar. 7, 1974 Project modification authorized for Phase I Advanced H. Doc. 365, 92nd Cong., 2d sess. 
Engineering and Design. 
GATHRIGHT DAM AND LAKE MOOMAW, VA. 
(See Section 21 of Text) 
July 24, 1946 Project authorized. H. Doc. 325, 61st Cong., 2d sess. 
RAPIDAN RIVER, VA. (See Section 22 of Text) 
July 24, 1946 Project authorized. Approved in 1983. 
(Sec. 14) 
VA. BEACH STREAMS, CANAL NO.2, VA. BEACH, VA. 
(See Section 23 of Text) 
Oct. 27, 1965 Project authorized. H. Doc. 640, 94th Cong., 2d sess. 
(Sec. 201) 
'Contains 
21ncluded 
May 23, 1935. 
latest published map. 
in Emergency Relief Administration Program 
3For latest published map, see H. Doc. 1246, 62d Cong., 3d 
sess. 
5-23

TABLE 5-C 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
ATLANTIC INTRACOASTAL WATERWAY BETWEEN 
NORFOLK VA. AND ST. JOHNS RIVER, FLORIDA: 
DATA RELATIVE TO THE COMPLETED LOCKS 
(See Section 1 of Text) 
Dimensions 
Greatest 
WidtLh ength Depth on Year 
of able Miter Sills Opened 
Miles Cham- for Full Character to 
from Location ber Width Lift Upper Lower of Navi- Cost Norfolk, Va. feet (feet) (feet) (feet) (feet) Foundation gation 
12.4 Albemarie and Chesa- 75 600 2.7 1 1 Piles in sand 1932 $499,913 
peake Canal (Great and shells 
Bridge, Va.) 
10.7 Dismal Swamp Canal 52 300 12 12 12 Natural earth 1940 $348,879 
(Deep Creek) with cutoff 
walls 
33.1 Dismal Swamp Canal 52 300 12 12 13 Natural earth 1941 $372,556 
(South Mills, N.C.) with cutoff walls 
116 feet at mean low water. 
TABLE 5-D OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Full Cost to Sept. 30,1983 Additional Expenditure 
Project Report, See For New Work 
Annual Report Expended From 
For Construction Maintenance Contributed Funds 
Appomattox River, Va.' 
Aberdeen Creek, Va.2 
Blackwater River, Va. 
Active portion2 1" 
Deep Creek, Newport News, Va.2 
Carters Creek, Va. 
Active portion2 3 
Channel from Phoebus, Va. 
to deepwater in Hampton Roads2 
Channel connecting York River, Va. 
Back Creek to Slaights Wharf2 
Channel to Newport News, Va.2 
Chesconessex Creek, Va.2 
Chincoteague Harbor of Refuge, Va. 
Chowan River, N.C: 2 
1980 
1975 
1975 
1980 
1951 
1944 
1950 
1982 
1968 
1978 
1975 
$870,341 $863,140 
109,643 200,893 
342,118 151,735 
288,278 2,054,201 
28,398 
11,500 
14,855 
8,955,974 
25,516 
49,396 
107,220 
3,277 
32,442 
36,874 
4,320,634 
31,889 
24,471 
5-24 
19,300 
1,200 
2,500 
5,700

NORFOLK, VA DISTRICT 
TABLE 5-D OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Full Cost to Sept. 30, 1983 Additional Expenditure 
Project Report, See For New Work 
Annual Report Expended From 
For Construction Maintenance Contributed Funds 
Cockrells Creek, Va. 4 
Cranes Creek, Va. 
Davis Creek, Va. 2 
Deep Creek, Accomack Co., Va. 
Dymers Creek, Va.2 
Greenvale Creek, Va. 2 
Hampton Creek, Va. 
Horn Harbor, Va. 2 
Hoskins Creek, Va.2 
Jackson Creek, Va. 2 
Jarvis Creek, Va. 4 
Kings Creek, Va.4 
Lafayette River, Va.2 
Little Machipongo River, Va. 2 
Little River (Creek), Va. 2 13 
Locklies Creek, Va. 2 
Meherrin River, N.C. 2 
Milford Haven, Va. 2 
Mill Creek, Va.2 
Mulberry Creek, Va. 2 
Nandua Creek, Va. 2 
Nansemond River, Va.8 
Newport News Creek, Va. 2 
Nottoway River, Va. 2 
Occohannock, Creek, Va. 
Active portion2 
Onancock River, Va. 2 5 
Pagan River, Va. 2 6 
Pamunkey River, Va. 
Active portion2 
Parker Creek, Va. 2 
Parrotts Creek, Va. 2 
Portsmouth Harbor, Va. Channel to 
Nansemond Ordnance Depot 2 
Queens Creek 2 
Rappahannock River at 
Bowlers Wharf, Va.4 
Starlings Creek, Va. 2 
Taskinas Creek, Va. 
Totuskey Creek, Va. 
Tylers Beach, Va. 2 
Urbanna Creek, Va.2 
7 
Whitings Creek, Va. 
Winter Harbor, Va. 2 
Willoughby Channel, Va. 2 
Wishart Point Channel, Va. 2 
York River, Va. 
Active portion2 
1949 
1978 
1971 
1974 
1953 
1980 
1981 
1964 
1977 
1971 
1979 
1957 
1982 
1972 
1966 
1928 
1950 
1950 
1937 
1950 
1950 
1978 
1962 
1981 
1951 
1963 
1950 
1964 
1974 
1957 
1947 
1979 
1950 
1981 
1975 
1970 
1982 
1963 
1971 
1981 
1953 
1975 
1958 
6,274 
97,612 
83,000 
5,582 
20,003 
186,237 
13,987 
44,100 
8,500 
39,259 
5,593 
242,047 
15,000 
168,623 
11,581 
47,734 
24,568 
5,445 
2,393 
6,988 
167,477 
135,600 
44,295 
13,859 
187,914 
51,425 
31,376 
15,530 
37,045 
165,566 
26,949 
66,242 
7,479 
167,869 
261,201 
55,724 
21,630 
171,334 
8,500 
118,762 
29,198 
158,323 
39,675 
4,610 
198,420 
1,116,952 
88,488 
622,801 
34,437 
153,598 
54,343 
442,033 
9,560 
49,591 
32,322 
4,346 
2,458 
39,804 
426,777 
147,570 
78,283 
427,233 
284,381 
161,183 
140,973 
37,771 
66,162 
101,803 
603,632 
135 
450,693 
404,943 
106,868 
112,333 
291,048 
42,485 
102,243 
180,904 295,212 
5-25 
4,000 
2,910 
62,969 
500 
188,962 
16,955 
43,000 
1,350 
2,000 
500 
2,973 
30,625

TABLE 5-D (Cont.) 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
OTHER AUTHORIZED NAVIGATION PROJECTS 
1lncludes $22,500 for previous projects. 7In addition, $61,087 was expended for rehabilitation. 
2Completed. 8Includes $30,000 for new work and $7,000 for 
i3n addition, $700 for maintenance was expended from maintenance for previous projects. 
contributed funds. 91n addition, $168,091 was expended for rehabilitation. 
4lnactive. 10 lncludes $197,146 for previous new work projects. 5lncludes $33,549 for new work and $24,754 for "Ilncludes $15,000 for new work for previous projects. 
maintenance for previous projects. 12Includes $113,500 for previous maintenance projects. 6Includes $20,671 for new work for previous projects. '3 Federal funds expended by the U.S. Navy for new work. 
TABLE 5-E OTHER AUTHORIZED BEACH EROSION 
For Last Full Cost to Sept. 30, 1983 Additional Expenditure 
Project Report, See For New Work 
Annual Report Expended From 
For Construction Maintenance Contributed Funds 
Anderson Park, 1979 $471,474 - $176,671 
Newport News, Va. 
Hampton Institute 1976 $156,906 - $175,845 
TABLE 5-F OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Full Cost to Sept. 30, 1983 Additional Expenditure 
Project Report, See For New Work 
Annual Report Expended From 
For Construction Maintenance Contributed Funds 
Buena Vista, Va. 1977 $ 417,9001 - 
Newmarket Creek, Va. 1970 1,000,000 12,283 $550,097 
Norfolk Floodwall, Va. 1973 1,851,933 32,877 516,256 
Salem Church Lake, Va. 1976 1,896,7161 2 
Richmond Filtration Plant, Va. 1982 476,820 - - 
'Preconstruction planning terminated. 2lncludes $144,785 for previous projects. 
TABLE 5-G RECONNAISSANCE AND CONDITION SURVEYS 
Name of Project Date Survey 
Name of Project Conducted 
CONDITION SURVEYS 
Aberdeen Creek 
Atlantic Intracoastal Waterway 
Lower Northianding River 
Broad Creek 
Baltimore Harbor 
York Spit Channel 
Oct. 82 - Mar. 83 
Mar. 83 
Jun. 83 
Jun. - Aug. 83 
5-26

NORFOLK, VA DISTRICT 
TABLE 5-G (Cont.) RECONNAISSANCE AND CONDITION SURVEYS 
Date Survey 
Conducted 
CONDITION SURVEYS (Cont.) 
James River 
Dancing Point-Swann Point Channel 
Goose Hill Channel 
James River-Turkey Island Cutoff 
Rocklanding Shoal Channel 
Tribell Shoal Channel 
Little Machipongo River 
Lynnhaven Inlet 
Lynnhaven Inlet - The Narrows 
Newport News Channel 
Norfolk Harbor 
Craney Island Rehandling Basin 
Oyster Channel 
Starlings Creek 
Thimble Shoal Channel 
Waterway on the Coast of VA 
Chesapeake Bay to Magothy Bay Disposal Area 
Goulds Marsh Channel 
Goulds Marsh Channel Disposal Area 
Lower Magothy Bay 
North Channel 
Northam Narrows - Kegotank Bay 
Sloop Channel 
Upper Magothy Bay 
May 83 
Apr. 83 
Feb. - Mar. 83 
Apr. 83 
Nov. - Dec. 82 
Oct. 82 
Aug. 83 
Jul. 83 
Jan. 83 
May 83 & Aug. 83 
Jul. 83 
Jul. 83 
Jun. 83 
May 83 
Jun. 83 
Jun. 83 
Aug. 83 
Jul. 83 
Feb. - Mar. 83 
Jun. 83 
Jul. 83 
RECONNAISSANCE SURVEYS 
York River 
West Point Bar 
Name of Project 
Oct. 82 
5-27

WILMINGTON, N. C., DISTRICT* 
This district comprises central and eastern North 
Carolina and a portion of south-central Virginia, embraced 
in drainage basins tributary to the Atlantic Ocean from 
the southern boundary of Virginia to the Shallotte River, 
inclusive, with exception of the Meherrin River Basin 
above Murfreesboro, N. C., the Chowan River Basin above 
the confluence of the Nottaway and Blackwater Rivers, 
and the Pasquotank River and its tributaries for navigation 
only. Also included are those portions of the Yadkin- 
Pee-Dee and Catawba River basins within the state of 
N. C. as well as a portion of the Atlantic Intracoastal 
Waterway from the northern boundary of North Carolina 
to Little River, S. C., and a portion of the waterway from 
Norfolk, Va., to the Sounds of North Carolina, south of the 
north shore of Albemarle Sound. 
IMPROVEMENTS 
Navigation 
1. Aquatic Plant Control 
(R & H Act of 1965)...................... 
2. Intracoastal Waterway 
Between Norfolk, Va. and St. Johns 
River, Fla. (Wimington District)........... 
3. Beaufort Harbor, N. C................ . 
4. Cape Fear River, N. C. Above Wilmington.. 
Page 
... 6-2 
.. 6-2 
...6 -4 
... 6-4 
5. Channel from Back Sound to 
Lookout Bight, N. C............. .......... 6-5 
6. Lockwoods Folly River, N. C................6-5 
7. Manteo (Shallowbag) Bay, N. C...............6-5 
8. Morehead City Harbor, N. C.................6-6 
9. Ocracoke Inlet, N. C.. ................ 6-7 
10. Roanoke River, N. C.......................6-7 
11. Rollinson Channel, N. C.................... 6-7 
12. Shallotte River, N. C ............ ........... 6-7 
13. Silver Lake Harbor, N. C.................. 6-8 
14. Waterway Connecting Pamlico Sound 
and Beaufort Harbor, N. C...................6-8 
15. Waterway Connecting Swanquarter Bay 
with Deep Bay, N. C.. ......... .......... 6-8 
16. Wilmington Harbor, N. C...................6-9 
Beach Erosion Control 
17. Fort Fisher and Vicinity, N. C..............6-10 
Flood Control 
18. Ararat River, Mount Airy, N. C...... 
19. Black River, Harnett County, N. C.... 
20. Cape Fear River Basin, N. C........ 
20A. B. Everett Jordan Dam and Lake.... 
20B. Randleman Lake, N. C............. 
21. Carolina Beach and Vicinity, N. C.... 
........ 6-10 
........ 6-11 
........ 6-11 
........ 6-11 
........ 6-12 
........ 6-12 
Page 
22. Deep Creek, 
Edgecombe County, N. C...................6-12 
23. Genoa Sewer Facility, Wayne County, N. C.... 6-13 
24. Goldsboro, Neuse River, N. C............ . . . . 6-13 
25. Joyce Creek, Camden County, N. C........... 6-13 
26. Leesville, Va., Roanoke River, 
Sec. 32, Demo. Project ................... 6-14 
27. Neuse River Basin, N. C.. ................ 6-14 
27A. Falls Lake, N. C.............. ............ 6-14 
28. Scuppernong River, N. C..................6-15 
29. Wrightsville Beach, N. C...................6-15 
30. Yadkin River Basin, N. C. and S. C..........6-15 
30A. W. Kerr Scott Dam and 
Reservoir, N. C............. ............. 6-15 
31. Inspection of Completed 
Flood Control Projects....................6-16 
32. Food Control Work Under 
Special Authorization..................... 6-16 
Multiple-Purpose Projects, 
Including Power 
33. Roanoke River Basin, Va. and N. C..........6-16 
33A. John H. Kerr Dam and Reservoir, 
Va. and N. C................... ........... 6-16 
33B. Philpott Lake, Va... ......... ............ 6-17 
34. Scheduling Flood Control 
Reservoir Operations.....................6-17 
General Investigations 
35. Surveys... ............................ 6-18 
36. Collection and Study of Basic Data..........6-18 
37. Advance Engineering and Design........... 6-18 
6-1

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1983 
Tables Page 
Table 6-A Cost and Financial Statement.......... 6-19 
Table 6-B Authorization Legislation............. 6-23 
Table 6-C Other Authorized Navigation 
Projects...........................6-26 
Table 6-D Other Authorized Beach Erosion 
Control Projects....................6-27 
Table 6-E Other Authorized Flood Control 
Projects........................6-28 
Tables (continued) Page 
Table 6-F Not Applicable 
Table 6-G Deauthorized Projects............... 6-29 
Table 6-H Reconnaissance and Condition 
Surveys............................6-29 
Table 6-I Navigation Work Under 
Special Authorization................6-30 
Table 6-J Dams and Reservoirs................. 6-31 
Table 6-K Special Authorization................6-32 
Navigation 
1. AQUATIC PLANT CONTROL (RIVER AND HARBOR 
ACT OF 1965) 
Location. Navigable waters, tributary streams, connecting 
channels, and other allied waters in Wilmington 
District. 
Existing project. The existing project provides for control 
and progressive eradication of water-hyacinth, 
alligatorweed, Eurasian watermilfoil, and other obnoxious 
aquatic plant growths from navigable waters, tributary 
streams, connecting channels, and other allied waters of 
the United States, in the combined interest of navigation, 
flood control, drainage, agriculture, fish and wildlife conservation, 
public health, and related purposes, including 
continued research for development of the most effective 
and economic control measures in cooperation with other 
Federal and State agencies in accordance with the report 
of the Chief of Engineers, House Document 251, 89th Congress, 
1st session. The project was authorized by Section 
302, 1965 River and Harbor Act (H.D. 25, 89th Cong., 1st 
sess.). The Act provides that research and planning costs 
shall be borne fully by the United States. 
Local cooperation. Local interests must agree to hold 
the United States free from damages that may occur from 
operations performed in connection with this project, and 
participate to the extent of 30 percent of the cost of the 
program. Requirements are being met. 
Operations and results during fiscal year. New Work: 
Herbicides were applied to three lakes in the William B. 
Umstead State Park, Wake County, N. C. to control 
hydrilla. Various types of chemicals were used so that the 
most effective could be identified. Planning was accomplished 
at a federal cost of $13,184 and control work 
was accomplished which will be billed in FY 1984. 
Conditions at end of fiscal year. Because control work 
took place late in the fiscal year, the full extent of effectiveness 
is not known. Continued monitoring will allow for 
future treatments with maximum effect. Requests for 
assistance in control of aquatic weeds were received from 
Washington County, N..C. and the City of Wilmington, 
N. C. A response to those requests was not possible due to 
the lack of funds. Investigations will take place in those 
areas in FY 1984. 
2. ATLANTIC INTRACOASTAL WATERWAY 
BETWEEN NORFOLK, VA. AND ST. JOHNS 
RIVER, FLA. (WILMINGTON DISTRICT) 
Location. The project is located on the east coast of the 
United States, between Norfolk, Va., and St. Johns River, 
Florida. The section within Wilmington District begins at 
the Virginia-North Carolina State line and extends 
generally southerly and southwestwardly to Little River, 
S. C., a total of 308 statute miles. (See Coast and Geodetic 
Survey Charts 830 to 842, inclusive.) 
Previous projects. For details see Annual Reports for 
1915, 1926, 1932, and 1938. 
Existing project. The authorized project provides for a 
waterway, 12 feet deep, with widths varying from 90 feet 
in land cuts to 300 feet in open waters; the construction, 
operation and maintenance of suitable bridges; saltwaterintrusion 
preventive measures in the vicinity of Fairfield, 
N. C.; a channel in Peltier Creek, 6 feet deep and 50 feet 
wide from the Intracoastal Waterway in Bogue Sound to 
and including a basin in Peltier Creek, 6 feet deep, 200 feet 
wide, and 600 feet long; a channel, 6 feet deep and 90 feet 
wide between the Intracoastal Waterway and the gorge in 
Bogue Inlet; a channel, 12 feet deep and 90 feet wide to a 
turning basin, 200 feet wide and 350 feet long, at 
Swansboro; a channel, 6 feet deep and 90 feet wide in New 
River Inlet, and a connecting channel of the same dimensions 
to the Intracoastal Waterway near the mouth of New 
River; a channel, 10 feet deep, and 90 feet wide in New 
River, between the Intracoastal Waterway and the 
Seaboard Coastline Railroad bridge at Jacksonville, N. C.; 
a channel through New Topsail Inlet, 8 feet deep and 150 
feet wide and a channel from New Topsail Inlet to the Intracoastal 
Waterway by way of Old Topsail Creek, 7 feet 
deep and 80 feet wide; a channel, 7 feet deep and 80 feet 
wide, in Banks Channel, from New Topsail Inlet, paralleling 
the barrier beach, to the Atlantic Intracoastal Waterway; 
a channel, 14 feet deep and 400 feet wide, across the 
ocean bar at Masonboro Inlet, with suitable jetties at the 
entrance, thence 12 feet deep and 90 feet wide to the channel 
of the Intracoastal Waterway at Wrightsville by way 
of Banks and Motte Channels; a turning basin, 15 feet 
deep, 300 feet wide, and 700 feet long, on the east side of 
Banks Channel near Masonboro Inlet, with three 15-pile 
dolphins therein; a channel, 6 feet deep, 80 feet wide, and 
6-2 
--

WILMINGTON, N. C., DISTRICT 
8,000 feet long, to and including a turning basin of the same 
depth, 130 feet wide and 180 feet long, at Carolina Beach; a 
yacht basin, 230 feet wide, 450 feet long, and 12 feet deep, 
at the town of Southport, connected to the waterway by a 
suitable channel of the same depth; and maintenance of the 
general navigation features of the North Carolina State 
Ports Authority Small-Boat Harbor at Southport, consisting 
of an entrance channel, 150 feet wide and 400 feet 
long, an eastern harbor-access channel, 70 feet wide and 
430 feet long, a western harbor-access channel, 60 feet 
wide and 185 feet long, to a turning basin, 180 feet wide 
and 550 feet long, all to a depth of 6 feet. A modification 
providing for the replacement of five Federally owned and 
operated highway bridges was authorized in December 
1970. A modification providing for 100 percent Federal 
funding for Walter B. Jones (formerly Wilkerson Creek) 
and Coinjock bridges was authorized in October 1976. 
Estimated Federal Cost is $44,000,000 (1983). The six mooring 
basins along the AIWW were deauthorized 5 August 
1977 under authority of Sec. 12, PL 93-251.The south jetty 
at Masonboro Inlet has an estimated Federal cost of 
$8,910,000 (1983) and is complete except for the training 
wall. A Section 111 project to mitigate damages caused by 
the north jetty was authorized in October 1980 and was 
completed in April 1981. A modification to provide for a 
channel 150 feet wide and 8 feet deep extending from the 
seaward side of the ocean bar at Carolina Beach Inlet to 
the intersection of the inlet with the AIWW channel was 
approved by the Chief of Engineers on February 18, 1982, 
under Section 107 of the 1960 River and Harbor Act. A 
modification to provide for a channel 150 feet wide and 8 
feet deep extending from the seaward side of the ocean 
bar at Bogue Inlet to the inlet gorge was approved by the 
Chief of Engineers on September 7, 1983, under Section 
107 of the 1960 River and Harbor Act. The estimated 
Federal construction cost is $91,000 (1983). Length of channels 
and basins total 347.7 miles. Plane of reference is 
mean low water. 
In the waterway north of Neuse River, variations in 
water surface due to winds seldom exceed 2 feet above or 
below mean stage. Between Beaufort and the Cape Fear 
River, normal tidal range varies from 3.5 feet at the inlets 
to 1 foot at points between. Average range of tide is 4 feet 
on the ocean side of Bogue Inlet and 2.5 feet just inside the 
inlet. At New River, tidal range varies from 3.5 feet at the 
inlet to 1 foot at the head of the marshes and zero at Tar 
Landing, 31 miles above. From Cape Fear River, N. C., to 
Little River, S. C., mean tidal range varies between 4.7 
feet in Cape Fear River and 4 feet at the intermediate inlets, 
and 2 feet at points midway between the inlets. On October 
15, 1954 (Hurricane Hazel), the tide at Holden Beach 
reached an elevation of 17.6 feet. (See Table 6-B for 
Authorizing Legislation.) 
Local cooperation. Fully complied with to date except 
for the modifications. The State of North Carolina has 
agreed to keep the bridges toll free and upon completion of 
each bridge, accept maintenance, replacement, and ownership 
responsibilities thereof. They have withdrawn their 
offer to contribute 25 percent of the first cost. The Water 
Resources Act of 1976 modified the terms of local cooperation 
to del i the non-Federal cost-sharing requirement for 
the Walter B. Jones (formerly Wilkerson Creek) and Coinjock 
bridges. The three remaining bridges were not included 
in this modification and are awaiting additional 
authorization to reflect 100 percent Federal funding. 
Terms are fully complied with for the Carolina Beach Inlet 
modification. For the Bogue Inlet modification local interest 
must: (a) pay one-half of the first cost of construction 
(including engineering, supervision and administration 
costs) allocated to recreational boating, an amount presently 
estimated at $27,500; (b) hold and save the United States 
free from damages due to initial channel excavation and 
subsequent maintenance, except in the case of fault or 
negligence on the part of the United States or its contractors; 
and (c) provide without cost to the United States all 
lands, easements, and rights-of-way necessary for the initial 
excavation and subsequent maintenance of the inlet 
channel project and for aids to navigation, upon the request 
of the Chief of Engineers. Fully complied with to 
date. 
Operations and results during fiscal year. New Work: 
Government costs in connection with replacement of two 
highway bridges was $468,192. Litigation on Walter B. 
Jones Bridge cost $26,450. Replacement of the docking 
facility at the Walter B. Jones Bridge cost $59,845. 
Preauthorization studies for Bogue Inlet cost $45,316. 
Preconstruction planning for the Bogue Inlet modification 
cost $4,368. Between September 19-29, 1983, the U. S. hopper 
dredge Currituck removed 6,435 cubic yards from 
shoals in Bogue Inlet at a cost of $17,000. This is the first 
report since authorization. Between October 1 and 
November 3, 1982, the U. S. sidecasting dredge Merritt 
removed 45,483 cubic yards from shoals in Carolina Beach 
Inlet to construct a pilot channel for the U. S. hopper 
dredge Currituck which removed 12,900 cubic yards between 
November 8 and December 9, 1982. Total cost was 
$75,606 Federal and $57,800 non-Federal. Maintenance: 
During intermittent periods the U. S. sidecasting dredge 
Merritt removed 97,307 cubic yards from shoals in New 
River Inlet at a cost of $203,716; 64,223 cubic yards from 
shoals in New Topsail Inlet at a cost of $176,725; and 
107,908 cubic yards from shoals in Carolina Beach Tnlet at a 
cost of $295,286. The Currituck incurred cost of $690 at 
New River Inlet. The Merritt incurred cost of $136 at 
Bogue Inlet. During intermittent periods the U. S. hopper 
dredge Currituck removed 5,300 cubic yards from shoals 
in Carolina Beach Inlet at a cost of $23,250. During intermittent 
periods the U.S. debris boat Snell conducted clearing 
and snagging operations and maintained dredging 
ranges and mooring facilities at a cost of $253,394. Between 
February 11 and May 21, 1983, the contract dredges 
Hampton Roads and Richmond removed 465,872 cubic 
yards from shoals in the through channel between Neuse 
River and the South Carolina state line at a cost of 
$1,471,698. Between July 9 and August 2, 1983, the contract 
dredge Richmond removed 81,532 cubic yards from 
shoals in the through channel at Camp Lejeune at a cost of 
$176,540. Engineering and design for pipeline dredging 
between the Neuse River and the South Carolina state line 
cost $25,363. Costs in connection with prior year pipeline 
dredging were $4,015. Marking of easements along the 
6-3

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1983 
AIWW cost $9,880. Mosquito control in disposal areas cost 
$41,813. Masonboro Inlet monitoring program cost $9,691. 
Inspection of highway bridges cost $35,282. Structural 
repairs to four remaining bridges cost $121,698. Moorings 
for the Merritt at Topsail Inlet cost $136. Waterbird 
survey of dredged material islands cost $1,916. One lane 
traffic signals at Fairfield and Hobucken cost $691. Bridge 
repairs due to accidents cost $106,340. Condition and 
operation studies cost $328,040. Four highway bridges and 
utilities were operated and maintained at a cost of 
$628,451. 
Condition at end of fiscal year. The project was completed 
in September 1983 except for the training wall and three 
tie-up dolphins at Masonboro Inlet and the bridge replacement 
program. A construction contract for Coinjock 
Bridge was awarded on September 15, 1983. Carolina 
Beach Inlet was completed on December 9, 1982 and Bogue 
Inlet on September 29, 1983. Total cost for existing project 
to September 30, 1983 was $80,892,052, of which 
$26,277,735 was for new work including $57,800 in contributed 
funds and $54,614,317 was for maintenance. 
3. BEAUFORT HARBOR, N. C. 
Location. The project is just inside Beaufort Inlet, adjacent 
to Morehead City Harbor. (See Coast and Geodetic 
Survey Chart 420.) 
Previous projects. For details see Annual Reports for 
1915 and 1938. 
Existing project. The authorized project provides for 
stopping erosion at Beaufort Inlet by jetties and sand 
fences at Fort Macon and Shackleford points and other 
shore protection; channels 15 feet deep at mean low water 
and 100 feet wide in Bulkhead and Gallants Channels, except 
for a depth of 12 feet in the upper 5,000 feet of 
Gallants Channel; a harbor of refuge in Town Creek 12 feet 
deep, 400 feet wide, and 900 feet" long connected to 
Gallants Channel by a channel 12 feet deep, 150 feet wide, 
and 1,400 feet long; a basin 12 feet deep, 600 feet wide in 
front of the town of Beaufort except for a channel 15 feet 
deep, 100 feet wide through the basin; a stone bulkhead 
from Town Marsh across Bird Shoal to the west end of 
Carrot Island; and a channel in Taylors Creek 15 feet deep, 
100 feet wide, extending about 2.6 miles easterly from 
about opposite Marsh Street in Beaufort to Lennoxville 
Point at North River, except for an 800-foot-long section at 
the east end which is 12 feet deep. Total length of channels 
is 7.3 miles. A modification to provide for a channel 14 feet 
deep, 70 feet wide, and 1,900 feet long from Bulkhead 
Channel to a turning basin 14 feet deep, 150 feet wide and 
300 feet long near the upper end of Morgan Creek was approved 
by the Chief of Engineers on August 12, 1983, 
under Section 107 of the 1960 River and Harbor Act. The 
estimated Federal construction cost is $205,000 (1983). 
Average tidal range is 2.5 feet at Beaufort and 3.5 feet at 
the inlet. (See Table 6-B for Authorizing Legislation.) 
Local cooperation. Fully complied with to date except 
for the modification. For the Morgan Creek modification 
local interests have agreed to: (a) provide, without cost to 
the United States all land, easements, and rights-of-way 
necessary for the construction and subsequent 
maintenance of the project, and for aids to navigation upon 
the request of the Chief of Engineers, including suitable 
areas determined by the Chief of Engineers to be required 
in the general public interest for initial and subsequent 
disposal of dredged material, and including necessary retaining 
dikes, bulkheads, and embankments therefor, or 
the cost of such retaining works; (b) hold and save the 
United States free from damages due to construction and 
subsequent maintenance, except damages due to the fault 
or negligence of the United States or its contractors; 
(c) prohibit the erection of any structure within 25 feet of 
the bottom edge of the Federal navigation channel and turning 
basin; (d) provide and maintain, without cost to the 
United States, depths in berthing areas and local access 
channels commensurate with depths provided in related 
project areas; (e) provide and maintain, without cost to the 
United States, adequate public terminals and transfer 
facilities, open to all on equal terms; (f) accomplish without 
cost to the United States all alterations and relocations of 
buildings, transportation facilities, storm drains, utilities, 
and other structures and improvements made necessary 
by the construction; and (g) assume responsibility for all 
project costs in excess of $2,000,000 to insure that expenditures 
of Federal funds will result in a complete and fully 
effective project. 
Terminal facilities. There are fifty waterfront facilities 
with a total frontage of 2,000 feet. These facilities are adequate 
for present commerce. 
Operations and results during fiscal year. New Work: 
Preauthorization studies for Morgan Creek cost $25,032. 
Preconstruction planning cost $17,058. This is the first 
report since authorization. Maintenance: Between May 5-8, 
1983, the contract dredge Hampton Roads removed 27,187 
cubic yards from shoals in Gallants Channel at a cost of 
$62,911. Engineering and design for future year pipeline 
dredging cost $1,280. Condition and operation studies cost 
$9,368. 
Condition at end of fiscal year. The project was completed 
in October 1965 except for the Morgan Creek 
modification which was placed under contract on 
September 27, 1983, and is scheduled for completion 
November 10,1983. (For further details see Annual Report 
for 1962.) Costs under existing project to September 30, 
1983, were $624,269 for new work and $2,882,949 for 
maintenance, including $168,833 contributed funds, a total 
of $3,507,218. 
4. CAPE FEAR RIVER, N. C. 
ABOVE WILMINGTON 
Location. The river is formed by confluence of the Deep 
and Haw Rivers at Moncure, Chatham County, N. C., and 
empties into the Atlantic Ocean at Cape Fear, near the 
southern extremity of the State. (See Coast and Geodetic 
Survey Chart 426.) 
Previous projects. For details see Annual Reports for 
1915 and 1938. 
Existing projects. The authorized project provides for a 
channel 25 feet deep and 200 feet wide from Wilmington to 
6-4

WILMINGTON, N. C., DISTRICT 
a turning basin 400 feet wide and 550 feet long at Navassa 
(2.9 miles); a channel 12 feet deep and 140 feet wide from 
Navassa to mileboard 30 at Acme, with five channel 
cutoffs, 12 feet deep and 150 feet wide to eliminate sharp 
bends; a channel 8 feet deep from mileboard 30 to 
Fayetteville by constructing three locks and dams and.by 
dredging river shoals; and recreational facilities at the 
locks and dams. Total length of the project channels is 
113.9 miles. The project was authorized by River and 
Harbor Acts of June 25, 1910; June 26, 1934; August 30, 
1935; August 26, 1937; October 27, 1965; and Section 4, 
Flood Control Act of 1944. For further details see Annual 
Reports for 1962 and 1970. 
Local cooperation. Fully complied with. 
Terminal facilities. There are twelve waterfront 
facilities on the river, with a total frontage of 1,190 feet. 
Operations and results during fiscal year. Maintenance: 
During intermittent periods the U. S. debris boat Snell 
snagged and cleared and maintained the buoy systems at 
the locks at a cost of $45,462. A claim in connection with 
the lock gate sealing system cost $26. Between January 22 
and April 5, 1983, the contract dredge Buxton removed 
20,786 cubic yards from shoals in the river channel at a 
cost of $118,116. Periodic inspections and evaluations of 
three locks and dams cost $3,412. Condition and operation 
studies cost $50,519. Operation and maintenance of three 
locks and dams cost $217,265. 
Condition at end of fiscal year. The project was 
completed in June 1970. Total costs of existing project to 
September 30, 1983, were $14,793,793 of which $3,610,454 
(including $1,226,385 public works) was for new work and 
$11,183,339 for maintenance. 
5. CHANNEL FROM BACK SOUND TO LOOKOUT 
BIGHT, N. C. 
Location. The project is located on the coast of North 
Carolina, 8 miles east of Beaufort Inlet. (See Coast and 
Geodetic Survey Chart 420.) 
Existing project. The authorized project provides for a 
channel 100 feet wide and 7 feet deep from Back Sound, 
through Shackleford Banks to Lookout Bight. The project 
was authorized by River and Harbor Acts of August 26, 
1937, and March 2, 1945. For details see Annual Report for 
1959. 
Local cooperation. Fully complied with. 
Terminal facilities. Not required. 
Operations and results during fiscal year. Maintenance: 
The U. S. sidecasting dredge Merritt incurred cost of 
$136. Condition and operation studies cost $10,933. 
Condition at end of fiscal year. The project was completed 
in May 1965. 
6. LOCKWOODS FOLLY RIVER, N. C. 
Location. The project is located on the south coast of 
North Carolina about 12 miles west of Cape Fear River. 
(See Coast and Geodetic Survey Chart 1236 and Geological 
Survey Map of North Carolina.) 
Existing project. The authorized project provides for a 
channel 100 feet wide and 6 feet deep at low water from 
the ocean to the bridge at Supply 12.5 miles above, to be 
obtained by dredging through oyster rocks and mudflats. 
The completed river portion of the project above the 
waterway was reclassified to the active category in 1971. 
Lunar tidal ranges in Lockwoods Folly River are 4.5 feet 
at the inlet and 2 feet at the head of navigation at Supply. 
The existing project was authorized by the 1890 River and 
Harbor Act. (See Annual Report for 1887, page 1099.) A 
modification to enlarge the channel from 6 to 12 feet deep 
and from 100 to 150 feet wide across the ocean bar for 
distance of 4,700 feet was approved by the Chief of 
Engineers on June 3, 1980, under Section 107 of the 1960 
River and Harbor Act. The estimated Federal construction 
cost is $357,000 (1983). 
Local cooperation. For the new modification local interest 
must: (a) pay, contribute in kind, or repay with interest, 
one-half of the first costs of construction allocated 
to recreational boating, an amount presently estimated at 
$92,650; (b) hold and save the United States free from 
damages resulting from changes in groundwater levels, 
saltwater intrusion, or wave action due to the construction 
works, except damages due to the fault or negligence of 
the United States or its contractor; (c) provide without cost 
to the United States all lands, easements, and rights-ofway 
necessary for the construction and subsequent 
maintenance of the project and for aids to navigation upon 
the request of the Chief of Engineers and (d) provide depths 
in berthing areas commensurate with the project depths, 
and provide service facilities. 
Terminal facilities. Thirty-one piers and wharves on the 
Atlantic Intracoastal Waterway at Holden Beach, about 
1.25 miles west of Lockwoods Folly Inlet, with a total frontage 
of about 1,980 feet available. At Dixons Landing, 
about 2 miles upstream of the inlet, there are five wharves 
with a total frontage of 240 feet. Numerous natural landings 
are used for loading and unloading small boats. Berthing 
space in the vicinity of Lockwoods Folly Inlet totals 
about 2,220 feet. Facilities are considered adequate for 
present commerce. 
Operations and results during fiscal year. New work: 
Engineering and design for Lockwoods Folly Inlet cost 
$12,933. Between October 1 and November 7, 1982, the 
U. S. hopper dredge Currituck removed 37,980 cubic yards 
from shoals in Lockwoods Folly Inlet at a cost of $112,386. 
Maintenance: During intermittent periods the U. S. hopper 
dredge Currituck removed 203,555 cubic yards from 
shoals in the inlet at a cost of $341,988. The Merritt incurred 
cost of $136. The U. S. debris boat Snell snagged and 
cleared and repaired dredging ranges at a cost of $13,145. 
Condition and operation studies cost $5,605. 
Condition at end of fiscal year. The active portion of the 
project was completed in June 1965 except for the latest 
modification. Work was initiated on the latest modification 
on September 23, 1982 and is scheduled for completion in 
December 1983. 
7. MANTEO (SHALLOWBAG) BAY, N. C. 
Location. The project is located on the northeastern side 
6-5

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1983 
of Roanoke Island, North Carolina. (See Coast and 
Geodetic Survey Chart 1229.) 
Existing project. The authorized project provides for a 
channel 14 feet deep and 400 feet wide from the Atlantic 
Ocean through Oregon Inlet with connecting 12-foot channels, 
100 feet wide, to Pamlico Sound, Manteo, and Wanchese; 
and a channel 6 feet deep and 100 feet wide connecting 
the Manteo-Oregon Inlet Channel with Albemarle 
Sound. Length of channels is 25.4 miles. A newly authorized 
modification provides for stabilization of Oregon Inlet 
with a dual rubble-mound jetty system, including means 
for sand transfer to the downdrift beach; a channel, 20 feet 
deep and 400 feet wide, through the ocean bar at Oregon 
Inlet; a channel, 14 feet deep and 120 feet wide, from the 
gorge in Oregon Inlet to and through Roanoke Sound to 
and including a 15-acre basin of the same depth at Wanchese; 
and a channel 10 feet deep and 100 feet wide from 
the 12 foot deep channel in Manteo (Shallowbag) Bay 
through Roanoke and Albemarle Sounds to deepwater 
near the northern end of Croatan Sound. The 12 foot 
Croatan Sound channel has been deferred due to lack of 
economic justification. The estimated Federal cost for the 
modification is $98,300,000 (1983). The project was 
authorized by River and Harbor Acts of June 25, 1910; October 
17, 1940; May 17, 1950; and December 31, 1970; and 
under Section 107 of the 1960 River and Harbor Act. 
Local cooperation. For the new modification, local interests 
must: (a) provide all lands, easements, and rightsof-
way for construction and subsequent maintenance of the 
project, including suitable areas required for initial and 
subsequent disposal of spoil and also necessary retaining 
dikes, bulkheads, and embankments therefor, or the cost 
of such retaining works; (b) hold and save the United 
States free from damages due to the construction works 
and subsequent maintenance; (c) continue to provide and 
maintain adequate terminal and transfer facilities, open to 
all on equal terms, in accordance with plans approved by 
the Chief of Engineers; (d) provide and maintain necessary 
mooring and berthing facilities in any enlarged basin, open 
to all on equal terms, in accordance with plans approved by 
the Chief of Engineers; (e) provide and maintain depths in 
berthing areas and local access channels serving the terminals 
commensurate with depths provided in the related 
projects areas; (f) accomplish such alterations as required 
in sewer, water supply, drainage, electrical powerlines, 
telephone lines, or other utility facilities as well as their 
maintenance; (g) establish a competent and properly constituted 
public body empowered to regulate the use, 
growth, and free development of the harbor facilities, with 
the understanding that said facilities will be open to all on 
equal terms; (h) and establish regulations prohibiting the 
discharge of untreated sewage, garbage, and other 
pollutants in the water of the harbor by the users thereof, 
which regulations shall be in accordance with applicable 
laws or regulations of Federal, State, and local authorities 
responsible for pollution prevention and control. 
Reasonable assurances have been received. The State of 
N. C. has constructed the Wanchese Harbor portion and 
was reimbursed under Sec. 215, PL 90-483. 
Terminal facilities. The project is served by 33 waterfront 
facilities with a total frontage of 3,320 feet. Additional 
wharves and facilities will be provided with the 
enlarged basin at Wanchese. 
Operations and results during fiscal year. New Work: 
Environmental and archeological studies cost $37,874. 
Engineering and design cost $999,531. Maintenance: During 
intermittent periods the U. S. sidecasting dredge 
Schweizer removed 514,160 cubic yards from shoals in 
Oregon Inlet at a cost of $1,197,538. During intermittent 
periods the U. S. sidecasting dredge Merritt removed 
221,019 cubic yards from shoals in Oregon Inlet at a cost of 
$314,697. Between October 29, 1982 and March 24, 1983, 
the U. S. sidecasting dredge Fry removed 152,986 cubic 
yards from shoals in Oregon Inlet at a cost of $535,578. The 
Fry cost $108,527 for prior year dredging. Cost for prior 
year pipeline dredging was $515. During intermittent 
periods the U. S. debris boat Snell repaired dredging 
ranges and moorings at a cost of $68,027. Between October 
30 and December 29, 1982, the contract dredge Richmond 
removed 255,734 cubic yards from shoals in Old House 
Channel at a cost of $442,592. Between July 6 and 
September 27, 1983, the contract dredge Marion removed 
278,855 cubic yards from shoals in Old House Channel at a 
cost of $624,897. Between September 2 - 30, 1983, the contract 
dredge Mermentau removed 146,251 cubic yards 
from shoals in Oregon Inlet at a cost of $878,080. An environmental 
and economic assessment of dredging the 
channel from Wanchese to Manteo cost $12,751. Berthing 
facilities for corps dredges cost $1,403. Oregon Inlet model 
study cost $5,202. Condition and operation studies cost 
$80,362. Contributed funds of $2,200 were expended for 
diking. 
Condition at end of fiscal year. The project is complete 
except for the latest modification. (For further details, see 
Annual Report of 1962.) 
8. MOREHEAD CITY HARBOR, N. C. 
Location. The project is located on the northern shore of 
Bogue Sound, adjacent to Beaufort Inlet. (See Coast and 
Geodetic Survey Chart 420.) 
Previous project. For details see page 470 of Annual 
Report for 1935. 
Existing project. The authorized project provides for 
deepening of the channel, from the 42-foot-depth contour in 
the Atlantic Ocean through the ocean bar to the gorge in 
Beaufort Inlet, to 42 feet over a bottom width of 450 feet, 
thence to a depth of 40 feet in the east leg of the turning 
basin including the 1,200 foot diameter turning area, with 
widths of 600 feet in the cutoff channel, and 400 feet wide 
to the turning basin and connecting shallow-draft channels. 
Project deepening was completed on August 2, 1978. Jetties 
at Beaufort Inlet were reclassified to the "active" 
category on March 8, 1972. The estimated Federal cost is 
$51,900,000 (1983) for the jetties. In general the project as 
it now exists was authorized by the 1958 River and Harbor 
Act (S.D. 54, 84th Cong., 1st sess.) and the River and Harbor 
Act of December 31, 1970. For further details see Annual 
Report for 1962. 
Local cooperation. Fully complied with except for construction 
of the jetties which requires that all lands needed 
for construction be provided without cost to the United 
States. 
Terminal facilities. Twenty-six waterfront facilities 
6-6

WILMINGTON, N. C., DISTRICT 
serve the port, with a total frontage of 1,250 feet. Marine 
terminals provide 5,300 feet of berthing space, with a 
depth alongside of 35 feet, and facilities for transfer of 
cargoes between rail and water carriers. Improvements to 
facilities were completed in 1969. For further details see 
Port Series No. 12, revised 1980, Corps of Engineers. 
Operations and results during fiscal year. Maintenance: 
During intermittent periods the U. S. debris boat Snell 
repaired dredging ranges and moorings at a cost of 
$21,000. Between March 17 and April 26,1983, the contract 
dredge Hampton Roads removed 263,609 cubic yards from 
shoals in the inner harbor at a cost of $625,940. Between 
June 8 and July 8, 1983 and August 16-30, 1983, the contract 
dredge Dodge Island removed 848,933 cubic yards 
from shoals in the ocean bar at a cost of $2,518,081. Cost in 
connection with prior year ocean bar dredging was $1,256. 
Monitoring of Bogue Banks and Shackleford Banks cost $5. 
Maintenance and installation of tide gages cost $956. Environmental 
studies for designation of ocean dredged 
material site cost $4,894. Environmental assessment for 
beach disposal cost $6,877. Condition and operation studies 
cost $168,185. Contributed funds of $40,080 were expended 
for diking. 
Condition at end of fiscal year. The existing project is 
complete except for the jetties. (For further details, see 
Annual Report for 1962.) Total cost of the existing project 
to September 30, 1983 was $35,606,856 of which $6,501,569 
was for new work (including $553,477 public works funds) 
and $29,105,287 for maintenance, including $696,711 contributed 
funds. 
9. OCRACOKE INLET, N. C. 
Location. The inlet connects Pamlico Sound with the 
Atlantic Ocean, about 30 miles southwest of Cape Hatteras 
and 43 miles northeast of Cape Lookout. (See U.S. Coast 
and Geodetic Survey Chart No. 1232.) 
Existing project. The authorized project provides for a 
channel across the ocean bar 18 feet deep and 400 feet 
wide, and construction of a jetty extending from Ocracoke 
Island to the Atlantic Ocean. Construction of the jetty has 
been deferred for restudy. The project was authorized by 
the River and Harbor Act of July 14, 1960. For further 
details, see Annual Report for 1962. 
Local cooperation. Fully complied with. 
Terminal facilities. None required. 
Operations and results during fiscal year. Maintenance: 
Between January 13-16, 1983, the U. S. debris boat Snell 
repaired dredging ranges at a cost of $6,800. The 
U. S. sidecasting dredge Schweizer incurred cost of $183. 
Condition and operation studies cost $13,437. 
Condition at end of fiscal year. Construction was completed 
in August 1971. 
10. ROANOKE RIVER, N. C. 
Location. Rises in Blue Ridge Mountains, west of 
Roanoke, Va., flows southeasterly about 398 miles, and 
empties into westerly end of Albemarle Sound, N. C. (See 
Coast and Geodetic Survey Chart 1228 and Post Route 
Map of North Carolina.) 
Existing project. A channel 12 feet deep and 150 feet 
wide from Albemarle Sound to 1 mile above Plymouth, 
N. C.; thence a channel 10 feet deep and 100 feet wide to 
Hamilton; and thence a channel 8 feet deep and 80 feet 
wide to Palmyra Landing. Project authorized by River and 
Harbor Acts of March 3, 1871; July 3, 1930; and June 20, 
1938. For further details see Annual Report for 1962. 
Local cooperation. Fully complied with. 
Terminal facilities. Thirty-two waterfront facilities 
serve the waterway. Facilities appear adequate for 
existing commerce. 
Operations and results during fiscal year. Maintenance: 
No work was accomplished; however, a funds transfer of 
- $144 was made. 
Condition at end of fiscal year. Project is complete. 
11. ROLLINSON CHANNEL, N. C. 
Location. The project is located about 3.5 miles northeast 
of Hatteras Inlet. (See Coast and Geodetic Survey 
Chart 1232.) 
Existing project. The authorized project provides for a 
channel 12 feet deep, 100 feet wide, and about 5.1 miles 
long from deep water in Pamlico Sound to and including a 
basin of the same depth, 80 to 150 feet wide, and 1,450 feet 
long at Hatteras; a rubble-mound breakwater on each side 
of the channel at the entrance to the basin; and a channel 
10 feet deep and 100 feet wide from that depth in Hatteras 
Inlet gorge to Rollinson Channel, in the vicinity of the 
basin at Hatteras. The project was authorized by the 
River and Harbor Acts of August 30, 1935; March 2, 1945; 
September 3, 1954; and October 23, 1962. (For further 
details see Annual Report for 1961.) 
Local cooperation. Complied with to date. 
Terminal facilities. Six waterfront facilities serve the 
channel, with a total frontage of 926 feet. Existing facilities 
are adequate for present commerce. 
Operations and results during fiscal year. Maintenance: 
A report to determine the economic justification of the 
project cost $5,607. Project condition surveys cost $1,429. 
Condition at end of fiscal year. The project was completed 
August 22, 1966. (For further details, see Annual 
Report for 1961.) 
12. SHALLOTTE RIVER, N. C. 
Location. A small stream in Brunswick County, N. C., 
rising in the large swamp country between Cape Fear and 
Waccamaw Rivers, known as Green Swamp. Stream is 
about 30 miles long and flows southerly into Atlantic 
Ocean and 20 miles west of mouth of Cape Fear River. (See 
Coast and Geodetic Survey Chart 835.) 
Previous project. For details see page 1806 of Annual 
Report for 1915. 
Existing project. A channel 4 feet deep at mean low water 
6-7

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1983 
and 36 feet wide from the mouth to town of Shallotte. Section 
under improvement is 9 miles long. River is tidal, 
range varying from 5 feet at mouth to 3 feet at Shallotte. 
Hurricane Hazel in 1954 caused a tide about 16 feet above 
mean sea level in the river at Shallotte Point. Project 
authorized by River and Harbor Acts of March 4, 1913, and 
January 21, 1917. 
Local cooperation. None required. 
Terminal facilities. A marine railway and shop at 
Shallotte Point and another in town of Shallotte with 
facilities for building and repairing boats up to about 60 
feet long. On Shallotte River, there are 17 docks varying 
from 16 to 321 feet of frontage, providing 1,334 feet of 
wharf and docking space. 
Operation and results during fiscal year. Maintenance: 
Between March 17-22, 1983, the contract dredge Richmond 
removed $13,305 cubic yards from shoals in Shallotte 
River at a cost of $32,707. 
Condition at end of fiscal year. Project completed in 
1929. 
13. SILVER LAKE HARBOR, N. C. 
Location. The project is located at the southwest end of 
Ocracoke Island, a portion of the Outer Banks on the 
southeast coast of North Carolina, separating Pamlico 
Sound from the Atlantic Ocean. (See Coast and Geodetic 
Survey Chart No. 1232.) 
Existing project. The authorized project provides for 
basin depths of 12 feet in Silver Lake Harbor; an entrance 
channel 12 feet deep and 60 feet wide, from the basin to 
Teaches Hole Channel; a channel, 12 feet deep and 150 feet 
wide, from the entrance channel through Big Foot Slough 
Bar to the 12-foot contour in Pamlico Sound; a channel, 12 
feet deep and 150 feet wide, from the entrance channel 
through Teaches Hole Channel to the gorge in Ocracoke 
Inlet; a channel, 12 feet deep and 150 feet wide, across 
Bluff Shoal; and for rubble-mound training walls on the 
north and south sides of the entrance channel, 300 feet and 
400 feet long, respectively. Mean tidal ranges are 1.9 feet 
in the throat of Ocracoke Inlet and 1 foot at Ocracoke. 
Variations in the water surface of Pamlico Sound are 
generally due to winds and seldom exceed 1 or 2 feet above 
or below mean stage. Severe storms have raised the water 
surface as much as 7 feet above normal water level at 
Ocracoke. (See Table 6-B for Authorizing Legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Twelve waterfront facilities serve 
the harbor. These facilities are adequate for existing commerce. 
Operations and results during fiscal year. Maintenance: 
Between October 1-29, 1982,the contract dredge Richmond 
removed 56,033 cubic yards from shoals in Big Foot Slough 
Channel at a cost of $173,794. Between September 10-30, 
1983, the contract dredge Northwood removed 39,505 
cubic yards from shoals in Big Foot Slough Channel at a 
cost of $219,331. Cost for prior year pipeline dredging 
were $3,589. Condition and operation studies cost $10,574. 
Condition at end of fiscal year. The project was completed 
July 28, 1970. (For further details see Annual 
Report for 1961.) 
14. WATERWAY CONNECTING PAMLICO SOUND 
AND BEAUFORT HARBOR, N. C. 
Location. The project is located in Core Sound, west of 
the outer banks of eastern North Carolina. (See Coast and 
Geodetic Survey Charts Nos. 420 and 1233.) 
Existing project. The authorized project provides for a 
through channel to Core Sound 7 feet deep and 75 feet 
wide from Pamlico Sound to Beaufort Harbor; an alternative 
route of the same dimensions through Back Sound 
by way of channels at the east and west ends of Harkers 
Island; a channel 7 feet deep and 70 feet wide from the 
through channel to the local harbor at Cedar Island, including 
the authorized passage and future maintenance of 
a channel through the existing private basin, and an access 
channel 6 feet deep, 50 feet wide and about 400 feet long to 
a basin the same depth, 60 feet by 100 feet; a channel 7 feet 
deep and 75 feet wide from the through channel to Atlantic; 
a channel 7 feet deep and 75 feet wide, with a basin 200 
feet by 500 feet, the same depth, at Sealevel; a channel 7 
feet deep and 75 feet wide, with basin 150 feet by 130 feet, 
the same depth, at Davis; a channel 6 feet deep and 60 feet 
wide with a basin 100 feet by 600 feet, the same depth, at 
Marshallberg; an entrance channel 6 feet deep and 60 feet 
wide, from Back Sound to harbor of refuge 120 feet by 250 
feet, the same depth in Brooks Creek at the west end of 
Harkers Island; and a channel 7 feet deep and 70 feet wide, 
from the existing side channel at Atlantic, N.C., to the 
mouth of Little Port Brook; thence 7 feet deep and 50 feet 
wide, along the Brook to a basin 600 feet long, 180 feet 
wide, and 7 feet deep, with a breakwater, beginning at a 
point between the mouth of Little Port Brook and White 
Point, running along the channel approximately 2,000 feet. 
The project is complete except for 7-foot modification to 
Davis, N. C. which was deauthorized April 6, 1982 by the 
Chief of Engineers due to the inability of local interest to 
provide the terms of local cooperation. Plane of reference 
is mean low water. The length of the authorized channels 
is about 50.6 miles. (See Table 6-B for authorizing legislation.) 
Local cooperation. Fully complied with to date for completed 
portion. 
Terminal facilities. Sixteen small wharves serve the 
waterway. Additional facilities are needed along Core 
Sound. 
Operations and results during fiscal year. Maintenance: 
Between January 12 and February 4, 1983, the contract 
dredge Richmond removed 74,778 cubic yards from shoals 
in Wainwright Slough and Atlantic Harbor of refuge at a 
cost of $256,142. Project condition surveys cost $9,608. 
Condition at end of fiscal year. The project was completed 
in September 1972 except for the modification to 
Davis, N. C. which has been deauthorized. (For further 
details, see Annual Report for 1961.) 
15. WATERWAY CONNECTING SWANQUARTER 
BAY WITH DEEP BAY, N. C. 
Location. On north side of Pamlico Sound, about 10 
6-8

WILMINGTON, N. C., DISTRICT 
miles east of mouth of Pamlico River. (See U. S. Coast and 
Geodetic Survey Chart No. 1231.) 
Existing project. A channel 60 feet wide and 8 feet deep 
from Deep Bay through present waterway to Swanquarter 
Bay, and thence through Swanquarter Canal to a basin of 
the same depth, about 500 feet long and 60 to 300 feet 
wide, at head of canal. Project was authorized by River 
and Harbor Acts of June 25, 1910, and March 2, 1945. For 
further details see Annual Report for 1950. The existing 
project has been modified to provide a channel 10 feet 
deep and 80 feet wide from the State ferry channel to the 
harbor entrance channel, a distance of approximately 4,850 
feet; enlarge the harbor entrance channel from 8 to 10 feet 
deep and 60 to 80 feet wide to the harbor canal, approximately 
1,400 feet; and enlarging the harbor canal from 8 to 
10 feet deep with the existing width of 60 feet to the 
turning basin in Swanquarter Harbor, a distance of 
approximately 2,450 feet. The modification also includes 
Federal maintenance of the State ferry channel 10 feet 
deep and 80 feet wide from the intersection of that channel 
with the Federal improvements to deep water in Swanquarter 
Bay, to be accomplished only if the State 
discontinues maintenance. This modification was approved 
by the Chief of Engineers on June 10, 1983, under Section 
107 of the 1960 River and Harbor Act. The estimated 
Federal construction cost is $704,000 (1983). 
Local cooperation. Fully complied with for the 
completed portion. For the new modification local interest 
must: (a) provide, without cost to the United States all 
lands, easements, and rights-of-way necessary for the 
construction and subsequent maintenance of the project, 
and for aids to navigation upon the request of the Chief of 
Engineers, including suitable areas determined by the 
Chief of Engineers to be required in the general public 
interest for initial and subsequent disposal of dredged 
material, and including necessary retaining dikes, bulkheads, 
and embankments therefor, or the cost of such 
retaining works; (b) hold and save the United States free 
from damages due to construction and subsequent maintenance, 
except damage due to the fault or negligence of 
the United States or its contractors; (c) provide and 
maintain, without cost to the United States, depths in 
berthing areas and local access channels commensurate 
with depths provided in related project areas; (d) provide 
and maintain, without cost to the United States, adequate 
public terminals and transfer facilities, open to all on equal 
terms; (e) accomplish without cost to the United States all 
alterations and relocations of buildings, transportation 
facilities, storm drains, utilities, and other structures and 
improvements made necessary by the construction; 
(f) assume responsibility for all project costs in excess of 
$2,000,000 to insure that expenditures of Federal funds 
will result in a complete and fully effective project. Formal 
assurances have been received. 
Terminal facilities. Six waterway facilities serve the 
waterway, with a total frontage of 355 feet. Existing 
facilities are adequate for present commerce. 
Operations and results during fiscal year. New Work: 
Preauthorization studies for the Swanquarter Bay modification 
cost $8,422. Preconstruction planning cost $28,342. 
This is the first report since authorization. 
Condition at end of fiscal year. Project was completed 
January 24, 1964, except for the modification which will be 
constructed in FY 1984. 
16. WILMINGTON HARBOR, N. C. 
Location. The project is located on the Cape Fear River, 
on southeast coast of North Carolina, between the Atlantic 
Ocean and Wilmington, North Carolina. (See Coast and 
Geodetic Survey Chart No. 426.) 
Previous projects. For details, see page 1804 of Annual 
Report for 1915 and page 533 of Annual Report for 1938. 
Existing project. The authorized project provides for a 
channel 40 feet deep and 500 feet wide from the Atlantic 
Ocean through the ocean bar and entrance channels to 
Southport, thence 38 feet deep and 400 feet wide to the 
upper end of the anchorage basin (foot of Castle Street) at 
Wilmington, thence 32 feet deep and 400 feet wide, to 
Hilton Bridge over Northeast (Cape Fear) River; a 38-footdeep 
anchorage basin at Wilmington; a 32-foot-deep 
turning basin opposite the principal terminals; a channel 
12 feet deep and 100 feet wide, about 3 miles long, in Cape 
Fear River; and a channel 25 feet deep and 200 feet wide 
from Hilton Bridge over Northeast (Cape Fear) River to a 
point 1.66 miles above, including a turning basin of the 
same depth, 700 feet wide and 500 feet long, at a point 1.25 
miles above the bridge. The project was authorized by 
River and Harbor Acts of July 3, 1930; March 2, 1945; May 
17, 1950; October 23, 1962; and March 10, 1964; under 
Section 107 of the 1960 River and Harbor Act. A modification 
to widen the existing anchorage basin by 100 feet 
was authorized on July 13, 1982, under Sec. 5 of the Cong. 
Appro. Act of March 4, 1915. (For further details of 
authorization, see 1962 Annual Report.) 
Local cooperation. Fully complied with to date. 
Terminal facilities. Forty-three principal wharves, piers, 
and docks at port of Wilmington, with a berthing space of 
about 20,000 linear feet serve the harbor. These facilities 
handle general cargo and petroleum products. For further 
details, see Port Series No. 12, revised 1980, Corps of 
Engineers. 
Operations and results during fiscal year. New Work: 
Between October 1 and 26, 1982, the contract dredge 
Dauntless removed 327,995 cubic yards to widen the 
anchorage basin opposite the state ports at a federal cost 
of $425,000 and non-federal cost of $205,371. This work was 
accomplished with maintenance funds. Maintenance: 
During intermittent periods the U. S. debris boat Snell 
repaired survey and dredging ranges at a cost of $48,643. 
Between December 18,1982 and April 3, 1983, the contract 
dredge Dauntless removed 1,058,898 cubic yards from 
shoals in the anchorage basin and channels at a cost of 
$1,195,385. Between November 27 and December 30, 1982, 
the contract dredge Manhattan Island removed 718,528 
cubic yards from shoals in the ocean bar at a cost of 
$1,990,405. Between September 8 and 30, 1983, the 
contract dredge Dodge Island removed 487,252 cubic 
yards from shoals in the ocean bar at a cost of $1,933,548. 
Engineering and design for pipleine dredging cost $14,058. 
Cost in connection with prior year pipeline dredging was 
6-9

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1983 
$828. The feasibility study for enlargement of turning 
basin cost $40. Mosquito control on Eagle Island cost 
$9,815. Government cost for dike construction was $4,555. 
Maintenance of tide gages cost $306. Condition and 
operation studies cost $225,066. Contributed funds of 
$75,000 were expended for diking. 
Condition at end of fiscal year. The active portion of the 
project completed July 1973 except for latest modification 
which was completed on October 26, 1982,with maintenance 
funds. (For further details, see Annual Report for 
1962.) Total cost of the existing project to September 30, 
1983, was $58,121,048 of which $14,089,612 was for new 
work and $44,031,486 was for maintenance, including 
$2,490,701 contributed funds. 
Beach Erosion Control 
17. FORT FISHER AND VICINITY, N. C. 
Location. The project is located in New Hanover County 
about 20 miles south of Wilmington, North Carolina, on the 
peninsula which separates the lower Cape Fear River from 
the Atlantic Ocean. (See U. S. Geological Survey 
quadrangle sheet for Kure Beach, N. C.) 
Existing Project. The project involves construction of a 
stone revetment along the seaward face of the eroding 
upland bluff fronting the Fort Fisher Historic Site. The 
total length of the revetment is 3,200 feet. The revetment 
structure will be comprised of natural stone units. The 
crest of the revetment will be rimmed with a safety zone 
consisting of a pedestrian path, rails, and appropriate 
landscaping to prevent access to the sloping face of the 
structure. Three overlook, gazebo-type platforms will 
permit visitors to view the beach below the revetment, 
and three stairways integrated in the face of the structure 
will allow controlled access to the beach. Estimated 
Federal cost of construction is $4,210,000 (1983). The 
project was authorized under Section 201 of Public Law 
89-298 on November 22, 1976. 
Local cooperation. The State of North Carolina is the 
project sponsor and prior to commencement of construction 
would: (a) Provide without cost to the United 
States all lands, easements, and rights-of-way, including 
suitable beach fill material borrow areas, as determined by 
the Chief of Engineers, necessary for the construction of 
the project. (b) Provide a cash contribution for the shore 
protection project equal to the appropriate percentage of 
the final construction cost exclusive of lands, easements, 
rights-of-way, and alterations, the percentage to be in 
accordance with existing law, which contribution is 
presently estimated at $1,800,000, or 30 percent of project 
first costs. (c) Enter into a written agreement satisfactory 
to the Secretary of the Army concerning accomplishment 
of the above preconstruction requirements and that the 
State will: 
(1) Hold and save the United States free from 
damages due to the construction works. 
(2) Maintain the revetment structure, walkway, 
overlooks, and stairways after completion of construction 
in accordance with regulations prescribed by the 
Secretary of the Army. 
(3) Provide without cost to the United States 
appropriate access and facilities, including parking and 
sanitation, necessary for realization of the public benefits 
upon which Federal participation is based, and administer 
and maintain the site for continued public use during the 
life of the project. 
(4) Control water pollution to the extent necessary to 
safeguard the health of bathers. 
(5) Adopt appropriate ordinances or provide other 
means to insure preservation of the beach areas and the 
dunes. 
Operations and results during fiscal year. New work: 
Advance engineering and design cost $2,228. An additional 
$39,322 was expended under the General Investigations 
program. 
Condition at end of fiscal year. The project is in the 
preconstruction planning stage with completion indefinite 
due to higher priority work by the State of N. C. 
Flood Control 
18. ARARAT RIVER, MOUNT AIRY, N. C. 
Location. Ararat River is a tributary of the Yadkin 
River and is located in Surry County, N. C. The river flows 
through Mount Airy, N. C., to its confluence with the 
Yadkin River. The entire project borders Mt. Airy. (See 
USGS quadrangle sheets, Mount Airy, North, Va. and 
N. C. and Mount Airy, South, N. C.) 
Existing project. The project consists of approximately 
5,100 feet of industrial area dike construction, approximately 
6,700 feet of channel improvement, approximately 
1,800 feet of floodwall/dike at the Pine Street commercial 
area, and a flood warning system. The project was approved 
by the Chief of Engineers on August 10, 1983, under 
Section 205, 1948 Flood Control Act, as amended. The 
estimated Federal construction cost is $3,363,000 (1982). 
Local cooperation. Local interest must: (a) provide 
without cost to the United States all lands, easements, and 
rights-of-way, including suitable borrow and spoil disposal 
areas and suitable conservation lands to partially compensate 
for loss of fish and wildlife resources as determined by 
the Chief of Engineers, necessary for the construction of 
the project; (b) accomplish without cost to the United 
States all alterations and relocations of buildings, 
transportation facilities, storm drains, utilities, and other 
structures and improvements made necessary by the construction; 
(c) hold and save the United States free from 
damages due to the construction works, except damage 
due to the fault or negligence of the United States or its 
contractors; (d) maintain and operate the project after 
completion in accordance with regulations prescribed by 
the Secretary of the Army; (e) prescribe and enforce 
regulations to prevent obstruction or encroachment on 
channels and interior ponding areas which would reduce 
their flood-carrying capacity or hinder maintenance and 
operation, and control development in the project area to 
prevent an undue increase in the flood damage potential; 
6-10

WILMINGTON, N. C., DISTRICT 
and (f) assume full responsibility for all project costs in excess 
of the Federal cost limitation of $4 million. Formal 
assurances have been received. 
Operations and results during fiscal year. New work: 
Preauthorization studies cost $64,372. Preconstruction 
planning cost $74,997. This is the first report since 
authorization. 
Condition at end of fiscal year. Project is in the preconstruction 
planning stage. Construction is scheduled to 
start in March 1984. 
19. BLACK RIVER, HARNETT COUNTY, N. C. 
Location. The river rises near Angier in Harnett County, 
N. C., and flows in a southerly direction about 25 miles 
to its confluence with South River. (See Army Map Service 
quadrangle sheet 5254, Fayetteville, N. C.) 
Existing project. The project provides for 5.5 miles of 
channel excavation on Black River, beginning at a point 
8,000 feet below County Road 1780, with a 35-foot bottom 
width to the Durham and Southern Railroad. The project 
was authorized by the Chief of Engineers on February 9, 
1968, under Section 205,1948 Flood Control Act, as amended.
Local cooperation. Fully complied with to date. 
Operations and results during fiscal year. New work: 
Project monitoring cost $4,291. 
Condition at end of fiscal year. Construction was completed 
in December 1979. 
20. CAPE FEAR RIVER BASIN, N. C. 
Location. Work covered by this project consists of a 
series of dams and reservoirs on tributaries of the Cape 
Fear River in North Carolina within a radius of 100 miles 
from Raleigh, North Carolina. (See Geological Survey Map 
of North Carolina.) 
Existing project. Public Law 88-253, approved 
December 30, 1963, authorized three principal dams and 
reservoirs and a series of smaller reservoirs on tributaries 
of the Cape Fear River in accordance with the comprehensive 
plans in House Document 508, 87th Congress, 2d 
session. The act also provides that the appropriate 
agencies of the Departments of the Army and Agriculture 
shall conduct joint investigations and surveys and prepare 
a report on the upper tributaries of the Cape Fear River in 
the interest of watershed protection and flood prevention, 
and the conservation, development, utilization, and 
disposal of water. The report is to be prepared and 
submitted in compliance with provisions of Public Law 
87-639. A list of the dams and reservoirs included in the 
comprehensive plan follows. (See Table 6-J on Dams and 
Reservoirs). Estimates of cost as given are based on 1960 
price levels, except the ones for B. Everett Jordan Dam 
and Lake, and Randleman Lake, which were revised in 
1983, and Howards Mills Lake in 1980. These three 
projects have been authorized for construction in 
accordance with the above authorization. Howards Mill 
Lake was reclassified to the "deferred" category in 
October 1980 due to the current lack of economic 
justification. The joint study, accomplished by the Departments 
of the Army and Agriculture was unfavorable and 
has been submitted to Congress. No further action will be 
taken. 
Local cooperation. Requirements are given in the 
individual project reports. 
20A. B. EVERETT JORDAN DAM AND LAKE, N. C. 
Location. The project is located on the Haw River, N. C., 
4.3 miles above its mouth, and 2.5 miles north of Moncure, 
N.C. 
Existing project. The project provides for an earth dam 
1,330 feet long with a maximum height of 112 feet above 
the streambed, an uncontrolled, unpaved chute spillway, 
and a controlled 19-foot-diameter outlet structure. Some 
saddle dikes are required beyond the spillway. The 
reservoir will have a gross storage capacity of 778,000 
acre-feet, of which 543,000 acre-feet will be for flood 
control and a conservation pool of 235,000 acre-feet for 
water-quality control, water supply, and sedimentation. 
The reservoir will be operated as a unit of a coordinated 
system for control of floods in the Cape Fear River Basin 
and for water supply, water-quality control, and other 
purposes. Estimated cost for new work is $132,000,000 
(1983), consisting of $73,554,800 for construction, and 
$58,445,200 for lands and damages, including highway, 
railroad, and utility relocations. The existing project was 
authorized by Public Law 88-253 approved December 30, 
1963 (H.D. 508, 87th Cong., 2d sess.) 
Local cooperation. Local interests must protect 
downstream channels from encroachments and obstructions 
which would adversely affect operation of the 
project; reimburse the Federal Government for all costs 
allocated to municipal and industrial water supply, 
presently estimated at $3,900,000 and bear all annual costs 
for operation, maintenance, and major replacements 
allocated to municipal and industrial water supply, an 
amount presently estimated at $35,000 annually. 
Assurances that these obligations for water storage would 
be assumed have been received from the Department of 
Natural and Economic Resources, State of North Carolina. 
In addition, the State of N. C. has leased the project for 
public park, recreational, fish, wildlife, and other natural 
resource management purposes and the estimated cost to 
the State for O&M under this lease is $728,000 annually. 
Operations and results during fiscal year. New work: 
Relocation of N. C. Road 1900 was completed at a cost of 
$138,233. Recreation facilities cost $784,039. Status of 
plans and specs: All relocations, 100 percent; Parkers Creek 
ree area sanitary disposal station, 99 percent; Parker 
Creek rec area, 100 percent; Dam toe riprap, 100 percent; 
intake tower modification, 100 percent; Poplar Point rec 
area, 75 percent; and Ebenezer Church rec. area, 7 percent. 
Total Federal expenditures were $2,407,679. Maintenance: 
Normal operation and maintenance on completed features 
cost $571,995. 
Condition at end of fiscal year. Relocations complete 
except for Public Service Gas Co. Recreation facilities are 
underway. Impoundment was completed in February 1982 
with dedication on May 1, 1982. 
6-11

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1983 
20B. RANDLEMAN LAKE, N. C. 
Location. The project is located on Deep River, N. C., 
about 15 miles south of Greensboro and about 2 miles 
upstream from the town of Randleman. The damsite and 
about two-thirds of the reservoir would lie in Randolph 
County. The upper one-third of the reservoir would lie in 
Guilford County. 
Existing project. The authorized project provides for 
construction of an earth dam 2,400 feet long with a maximum 
height of 110 feet above the streambed to create a 
reservoir with gross storage of 108,000 acre-feet, consisting 
of 46,000 acre-feet for flood control and a conservation 
pool of 62,000 acre-feet for water supply, water-quality 
control and sedimentation. Randleman Lake is the second 
project of the comprehensive plan of development for the 
Cape Fear River Basin, providing reservoir storage for 
flood control, water supply, and recreation. Estimated 
cost of new work is $105,000,000 (1983), consisting of 
$50,219,000 for construction and $54,781,000 for lands and 
damages, including relocations. The existing project was 
authorized by the 1968 Flood Control Act (H.D. 343, 90th 
Cong., 2d sess.). 
Local cooperation. Local interests must: (1) In accordance 
with the Federal Water Project Recreation Act 
(P.L. 89-72): (a) Administer project land and water areas for 
recreation and fish and wildlife and to assure access to 
such development to all on equal terms; (b) pay, contribute 
in kind, or repay (which may be through user fees) with interest, 
one-half of the separable first cost allocated to 
recreation presently estimated at $8,190,000; and (c) bear 
all the costs of operation, maintenance, and replacement of 
recreation facilities, presently estimated at $391,000 annually; 
(2) In accordance with the Water Supply Act of 
1958, as amended, assure payment to the United States of 
all costs allocated to water supply, presently estimated at 
$47,015,000 for construction and $419,000 annually for 
operation, maintenance, and major replacement; (3) Hold 
and save the United States free from damages due to 
water-rights claims resulting from construction and operation 
of the project; (4) Prevent encroachment on downstream 
channels to the extent needed to provide effective 
reservoir operation; and (5) Exercise to the full extent of 
-their legal capability control against removal of streamflow 
made available for preservation of downstream 
fishery habitat. These assurances are subject to the provision 
that Federal participation in measures required to 
safeguard the quality of water in Randleman Reservoir 
shall not be provided as a substitute for the responsiblity 
of local interests to provide adequate treatment in accordance 
with water quality standards established pursuant 
to the Water Quality Amendments of 1972 (P.L. 92-500). 
Reasonable assurances that the requirements miblel 
fulfilled have been received. With the advent of innovative 
financing under the current administration, the terms of 
local cooperation may change. 
Operations and results during fiscal year. New work: 
Advance engineering and design cost $276,193. 
Condition at end of fiscal year. Preconstruction planning 
was completed in FY 1982. Currently awaiting a new construction 
start. 
21. CAROLINA BEACH AND VICINITY, N. C. 
Location. The project is in New Hanover County, about 
15 miles southeast of Wilmington, N. C., on the peninsula 
which separates lower Cape Fear River from the Atlantic 
Ocean. (See Coast and Geodetic Survey Map 834.) 
Existing project. The authorized project provides for 
construction of a dune with a base generally bordering at 
or near the building line, with a crown width of 25 feet at 
an elevation of 15 feet above mean low water, together 
with integral construction of a beach berm with a crown 
width of 50 feet at elevation 12, extending about 25,800 
feet from the northern limits of Carolina Beach to the 
southern limits of Kure Beach; initial deposition of sufficient 
material north of Carolina Beach to serve as a feeder 
beach; and Federal participation in the cost of beach 
nourishment for a period not to exceed 10 years from the 
year of completion of initial placement. The area south of 
Carolina Beach was reclassified to the inactive category, 
February 1975. Approved estimated Federal cost for new 
work is $9,390,000 (1983). The project was authorized by 
the 1962 Flood Control Act (H.D. 418, 87th Cong. 2d sess.). 
Local cooperation. Local interests must: (a) Provide 
lands, easements, and rights-of-way for construction; 
(b) make required relocations and alterations of streets, 
utilities, or structures; (c) contribute 37.9 percent of the 
total first cost, with credit allowed for (a) and (b); 
(d) hold the United States free from damages; (e) maintain 
all works after completion; (f) maintain continued public 
ownership of the shore; (g) adopt and enforce appropriate 
ordinances to provide for preservation of improvement 
and its protective vegetation; (h) control water pollution to 
extent necessary to safeguard health of bathers; and 
(i) at least annually inform interests affected that project 
will not provide any substantial protection from ocean 
surges higher in elevation than that of Hurricane Hazel, 
October 15, 1954. Requirements have been fulfilled to date 
for the town of Carolina Beach portion of the project only. 
Operations and results during fiscal year. New work: 
Dune stabilization for the beach nourishment project cost 
$49,483. Contributed funds of $153,200 were expended for 
beach nourishment and $18,208 for dune stabilization. A 
refund of $400,000 was made to local interests. 
Condition at end of fiscal year. Project construction was 
completed August 12, 1982, except for grassing which was 
completed in September 1983. 
22. DEEP CREEK, EDGECOMBE COUNTY, N. C. 
Location. The stream rises in Halifax County and flows 
southerly to its confluence with Fishing Creek, about 0.5 
mile upstream of the Fishing Creek and Tar River confluence, 
which is about 8.0 miles above Tarboro. All of the 
project is in Edgecombe County, N. C. (See U.S. Geological 
Survey quadrangle sheets, Parmele and Tarboro, N. C.) 
Existing project. The project provides for channel improvement 
and dike construction in the Deep Creek basin, 
consisting of the construction of a dike and drainage appurtenances 
on the north, west, and south sides of the 
town of Speed, for a distance of about 7,400 feet, to a maximum 
height of 9.5 feet, with a 10-foot-top-width; relocation 
6-12

WILMINGTON, N. C., DISTRICT 
and channel excavation of 3,100 feet of Knight Swamp 
along the northern dike segment and 1,800 feet of Longs 
Branch along the southern dike segment, to 20-foot and 
15-foot-bottom widths, respectively, and enlarging 3,200 
feet of Deep Creek to a 65-foot maximum bottom width 
along the western dike segment, utilizing excavated 
material for dike fill. Channel excavation of an additional 
500 feet of both Knight Swamp and Longs Branch upstream 
of the dike to bottom widths of 10 feet have been 
deferred. The estimated Federal construction cost is 
$388,000 (1983). The project was approved by the Chief of 
Engineers on February 18, 1977, under Section 205 of the 
1948 Flood Control Act as amended. 
Local cooperation. Local interests must provide, 
without cost to the United States, all lands, easements, 
rights-of-way, utility relocations or alterations, and road 
and bridge construction and alterations necessary for project 
construction (the acquisition of all lands or interest in 
lands necessary for the project shall be accomplished in accordance 
with provisions of P.L. 91-646, Uniform Relocation 
Assistance and Real Property Acquisition Policies Act 
of 1970); hold and save the United States free from 
damages due to the construction works when not caused 
by the fault or negligence of the United States or its contractor; 
maintain and operate the project after completion, 
without cost to the United States, in accordance with 
regulations prescribed by the Secretary of the Army; 
prescribe and enforce regulations to prevent obstruction 
or encroachment on channels which would reduce their 
flood carrying capacity or hinder maintenance and operation 
and regulate land use in the 100-year improved flood 
plain within the diked area to prevent any development 
which would be subject to flood damage in accordance with 
acceptable flood plain management practices; bear all project 
costs in excess of $2 million; and notify interests affected, 
at least annually, that the improvements will provide 
protection against the 100-year flood within the diked 
area and about the 5-year flood along the cleared and snagged 
reach, but complete flood protection is not provided. 
Fully complied with to date. 
Operations and results during fiscal year. New work: 
Project construction cost $169,000. 
Condition at end of fiscal year. A contract for project 
construction was awarded September 13, 1982, and was 
completed on September 23, 1983, except for grassing. 
23. GENOA SEWER FACILITY, WAYNE COUNTY, 
N.C. 
Location. The facility is located on the south bank of the 
Neuse River across from the City of Goldsboro, N. C., and 
about 1/2 mile downstream from the U. S. 117 bridge over 
the Neuse River. (See USGS quadrangle sheet, Southwest 
Goldsboro, N. C.) 
Existing project. The purpose of the project is to provide 
emergency bank protection at the Genoa sewer facility. 
The project consists of grading the Neuse River bank 
to a 2 horizontal to 1 vertical slope along the 200 linear feet 
of eroded bank, filling the slope as necessary to achieve 
grade, filling the hole in the riverbed at the toe of the eroded 
bank to match existing river grade, placing a 6-inchthick 
layer of crushed stone filter bed from the toe to the 
top of the slope, and providing a 11/z-foot-thick layer of 
riprap armor slope protection; at an estimated Federal 
construction cost of $150,000 (1983). The project was approved 
by the Chief of Engineers on August 30, 1983, 
under Section 14 of the Flood Control Act of 1946, as 
amended. 
Local cooperation. Local interests must provide, 
without cost to the United States, all necessary lands, 
easements, rights-of-way, and relocations required for construction 
and maintenance of the project (all acquisition 
will be in compliance with provisions of the Uniform 
Relocation Assistance and Real Property Acquisition 
Policies Act of 1970 [PL 91-646]); hold and save the United 
States free from damages due to the construction and 
subsequent maintenance of the project, except damages 
due to the fault or negligence of the United States or its 
contractors; maintain and operate the project after completion 
without cost to the United States in accordance 
with regulations prescribed by the Secretary of the Army; 
assume full responsibility for all project costs in excess of 
the Federal cost limitation of $250,000; and comply with Title 
VI of the Civil Rights Act of 1964 (PL 88-352). Formal 
assurances have been received. 
Operations and results during fiscal year. New work: 
Preauthorization studies cost $3,291 including a $3,000 
reimbursement to the revolving fund. Detailed engineering 
and design cost $16,169. This is the first report since 
authorization. 
Condition at end of fiscal year. A construction contract 
is scheduled to be awarded in November 1983 with completion 
in February 1984. 
24. GOLDSBORO, NEUSE RIVER, N. C. 
Location. On that portion of the Neuse River near 
Goldsboro, Wayne County, N. C., between points 94.8 and 
102.5 miles above New Bern, N. C. 
Existing project. Provides for cutoff channel, 12 feet 
deep, 20 feet wide, about 6,400 feet long, across the bend in 
the Neuse River located about 95 miles above New Bern, 
N. C. Project authorized by Flood Control Act of 1941. (See 
H. Doc. 327, 77th Cong. 1st sess., which contains the latest 
published map.) 
Local cooperation. Fully complied with. 
Operations and results durinag fiscal year. Maintenance: 
Construction of bank stabilization measures along the cutoff 
cost $68,213. 
Condition at end of fiscal year. Project is complete. 
25. JOYCE CREEK, CAMDEN COUNTY, N. C. 
Location. Joyce Creek rises in the northeastern part of 
Camden County, N. C., and flows generally southward for 
about 10 miles to Turners Cut near South Mills, North 
Carolina. (See Coast and Geodetic Survey Chart 1227 and 
Army Map Service quadrangle sheet, South Mills, N. C.) 
Existing project. The project provides for excavating a 
channel 40 feet wide, from the confluence with Turners 
Cut to County Road 1235 ,3.2 miles; thence a channel, 30 
6-13

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1983 
feet wide, to the uppermost crossing of SR 1224, 0.8 miles; 
thence a 20 foot bottom width channel to the confluence 
with Mill Run and Cypress Run, 1.7 miles; thence on 
Cypress Run, a channel, 10 feet wide, to County Road 1233, 
1.6 miles; and on Mill Run, a 10-foot-wide channel from confluence 
with Joyce Creek to County Road 1232, 2.2 miles; a 
total of 9.5 miles. Estimated Federal construction cost is 
$505,000 (1983). The project was approved by the Chief of 
Engineers on March 29, 1967, under Section 205 of the 
1948 Flood Control Act, as amended. 
Local cooperation. Local interests must provide all 
lands, easements, rights-of-way, utility relocations and 
alterations, and highway or highway-bridge construction 
and alterations necessary for construction; hold the United 
States free from damages; maintain and operate the project 
after completion; prevent future encroachment; provide 
a cash contribution of 21.5 percent of construction 
costs, now estimated at $106,300; and accomplish 
associated drainage works necessary to realize the 
benefits from the Federal improvement. Camden County 
is project sponsor based on favorable referendum in 1974. 
Operations and results during fiscal year. New work: 
Project construction cost $206,312 Federal and $100,083 
non-Federal. 
Condition at end of fiscal year. A contract for project 
construction was awarded September 23, 1982, with completion 
scheduled for October 1983. 
26. LEESVILLE, VA., ROANOKE RIVER, SEC. 32, 
DEMO. PROJECT 
Location. The project is located on the Roanoke (Staunton) 
River in southwest Virginia near the Town of 
Leesville in Campbell and Pittsylvania counties. (See 
USGS quadrangle sheet, Leesville, Va.) 
Existing project. The project provides for a total of 
about 2,200 linear feet of streambank protection on two 
separate sites along a 3-mile segment of the river between 
Leesville Dam and the town of Leesville. Three methods of 
erosion control were used, they were: stone rubble with 
vegetation, rubber tire mattress and rock windrow. The 
project was funded for construction by the Chief of 
Engineers in February 1978, under Section 32, P.L. 93-251. 
Local cooperation. Local interests must provide all 
lands, easements and rights-of-way; hold and save the 
United States free from damages; and maintain and 
operate project after completion. Fully complied with. 
Operations and results during fiscal year. New work: 
Monitoring of Leesville and Little Rockfish Creek cost 
$1,279. 
Condition at end of fiscal year. Construction was 
completed in March 1981. The project is functioning as 
designed. 
27. NEUSE RIVER BASIN, N. C. 
Location. Works covered by this project consist of a 
series of dams and reservoirs in the Neuse River Basin in 
North Carolina within a radius of 50 miles from Raleigh, 
North Carolina. (See Geological Survey Map of North 
Carolina.) 
Existing project. The Flood Control Act of 1965 
authorized construction of the Falls project as the key project 
in the recommended general plan of development of 
the Neuse River Basin. The plan will serve as a guide for 
immediate and future development of the basin's water 
resources as set forth in House Document 175, 89th Congress, 
1st Session. A list of projects included in the general 
plan of development follows. (See Table 6-J on Dams and 
Reservoirs.) Estimated costs as given are based on 1963 
price levels, except for Falls Lake which was revised in 
1983. 
27A. FALLS LAKE, N. C. 
Location. The project is on the Neuse River about 10 
miles north of the city of Raleigh, North Carolina. 
Existing project. The authorized project provides for an 
earth dam 1,900 feet long with a maximum height of 92 
feet above streambed. The dam will have a 30-foot top width. 
An uncontrolled chute spillway, 100-feet wide, will be 
located in the east abutment. The reservoir will have a 
gross storage capacity of 397,000 acre-feet, of which 
243,000 acre-feet will be for flood control, 45,000 acre-feet 
for water supply for the city of Raleigh, 71,000 acre-feet for 
water-quality control, and 38,000 acre-feet for sediment 
storage. The reservoir will be operated as the initial unit of 
a coordinated system for control of floods in the Neuse 
River Basin for water supply, water quality control, 
recreation, and other purposes. Estimated cost of new 
work is $162,000,000, consisting of $73,042,000 for construction 
and $88,958,000 for lands and damages, including 
highway, railroad, and utility relocations. The project was 
authorized by the 1965 Flood Control Act (H.D. 175, 89th 
Cong., 1st sess.). 
Local cooperation. Local interests must prevent encroachment 
on downstream channels that would interfere 
with the operation of the reservoir; pay the United States 
in accordance with the Water Supply Act of 1958, as 
amended, the entire amount of construction cost allocated 
to water supply, presently estimated at $12,000,000 and 
entire amount of operation, maintenance, and replacement 
costs allocated to water supply, presently estimated at 
$84,000 annually, the final amounts to be determined after 
actual costs are known; administer project land and water 
areas for recreation and fish and wildlife enhancement; 
pay, contribute in kind, or repay (which may be through 
user fees), with interest, one-half of the separable cost of 
the project allocated to recreation and one-fourth of the 
separable cost allocated to fish and wildlife enhancement, 
the amount involved currently being estimated at 
$20,000,000, and, bear all costs of operation, maintenance, 
and replacement of recreation and fish and wildlife lands 
and facilities, the amount involved currently being 
estimated at $1,151,000 on an average annual basis. Formal 
assurances have been received. The N. C. Department 
of Natural and Economic Resources has been authorized 
by an act of legislation to assure payment of all non- 
Federal costs allocable to water supply in all Federal projects 
as required by law. The State will require repayment 
of water supply costs, by the users. A contract between 
the city of Raleigh and the United States for water-supply 
storage space was approved by the Secretary of the Army 
6-14

WILMINGTON, N. C., DISTRICT 
on September 11, 1972. A contract agreement for cost 
sharing of recreational lands and facilities in accordance 
with P.L. 89-72 was approved by the Secretary of the Army 
on September 11, 1972. A contract agreement in accordance 
with Section 221 of P.L. 91-611 was executed on October 
10, 1972. 
Operations and results during fiscal year. New work: 
Land acquisition continued at a cost of $985,472. Slope 
repairs on SR 2002 and 1005 were completed at a cost of 
$179,613. Rip-rapping of 1-85 and construction of the utility 
fill were completed at a cost of $216,557. Construction of 
Southern Railway was completed at a cost of $113,088. 
Cemetery relocations were completed at a cost of $105,424. 
Installation of Public Service Gas Line continued at a cost 
of $562,640. Powerline relocations were completed at a 
cost of $299,707. Dam intake tower modifications were 
completed at a cost of $36,204. The spillway bridge was initiated 
at a cost of $467,539. Recreation facilities continued 
at a cost of $1,388,718. Cultural resources preservation 
continued at a cost of $103,862. Corps O&M facilities continued 
at a cost of $60,975. Status of plans and specs: All 
relocations, clearing and dam specifications, 100 percent; 
and Management Center, 96 percent. Total federal expenditures 
for construction were $6,189,542. Maintenance: 
Normal operation and maintenance on completed features 
cost $576,848. 
Condition at end of fiscal year. Reservoir filling commenced 
in January 1983 and is scheduled for completion in 
December 1983. Dedication ceremonies were held on April 
30, 1983. Recreation facilities and the spillway bridge are 
underway. The fish and wildlife facilities, remaining 
recreation facilities and operation and maintenance 
facilities remain to be constructed. 
28. SCUPPERNONG RIVER, N.C. 
Location. The stream rises in the east-central portion of 
Washington County, N. C., flows east into Tyrrell County, 
and thence north into Albemarle Sound, a total distance of 
about 22 miles. (See Geological Survey quadrangle sheet, 
Creswell, N. C.) 
Existing project. The project provides for excavating a 
70-foot-bottom-width channel, with depths ranging from 9 
feet to 12 feet, along Scuppernong River from Spruills 
Bridge to the confluence with Mauls Creek, a distance of 
2.0 miles, and excavating a 45-foot-bottom-width channel, 
with depths ranging from 6 feet to 8 feet, along Mauls 
Creek from Scuppernong River to County Road 1163, a 
distance of 1.8 miles. Total project length is 3.8 miles. 
Estimated Federal cost of construction is $590,000 (1983). 
Project was approved by the Chief of Engineers, October 
31, 1966 (with modification adding Mauls Creek approved 
June 16, 1967), under Section 205, 1948 Flood Control Act, 
as amended. 
Local cooperation. Local interests must provide lands, 
easements, rights-of-way, utility relocations and alterations, 
and highway or highway-bridge construction and 
alterations necessary for construction; hold the United 
States free from damages; maintain and operate project 
after completion; contribute, in cash, 19.4 percent of construction 
costs, currently estimated at $82,000; and prevent 
future encroachment. Formal request has not been 
made. 
Operations and results during fiscal year. New work: 
Project reanalysis cost $20,007. 
Condition at end of fiscal year. Project reanalysis and 
environmental studies are underway with completion 
scheduled in 1984. A smaller channel on Scuppernong 
River and deletion of Mauls Creek are anticipated. 
29. WRIGHTSVILLE BEACH, N. C. 
Location. A small island about 10 miles east of Wilmington, 
N. C. (See Coast and Geodetic Survey Map p. 834) 
Existing project. Construct a dune with a base bordering 
at or near the building line, with a crown width of 25 
feet at elevation 15 feet above mean low water, together 
with integral construction of a beach berm with a crown 
width of 50 feet at elevation 12, extending about 14,000 
feet from Moores Inlet on the north to Masonboro Inlet on 
the south. Existing project was authorized by 1962 Flood 
Control Act (H.D. 511, 87th Cong., 2d. sess.). 
Local cooperation. Fully complied with to date. 
Operations and results during fiscal year. New work: A 
refund of State sales tax caused a decrease in non-federal 
cost of - $162. A refund of $58,504 in contributed funds 
was made to local interests. 
Condition at end of fiscal year. Project restoration was 
completed April 10, 1981 except for grassing which was 
completed in September 1982. 
30. YADKIN RIVER BASIN, N. C. AND S. C. 
Location. The river rises on the eastern slope of the 
Blue Ridge Mountains in western North Carolina, flows 
generally easterly about 100 miles to the vicinity of Donnaha, 
North Carolina, thence southeasterly 104 miles to its 
confluence with Uwharrie River near Badin, North 
Carolina, where its name changes to Great Pee Dee River. 
(See U.S. Geological Survey map of North Carolina.) 
Existing project. The Flood Control Act of July 24,1946, 
authorized construction of four flood control dams in the 
Upper Yadkin River Basin, two on the Yadkin River above 
Wilkesboro, North Carolina, and two on Reddies River, a 
tributary stream. Studies made subsequent to authorization 
established the economic advantage of providing 
needed flood-control storage in only two reservoirs, one on 
the Reddies and one on the Yadkin. Present planning considers 
only the two-reservoir plan, W. Kerr Scott Dam and 
Reservoir constructed 1962 and Reddies River Lake. W. 
Kerr Scott was transferred to the Wilmington District 
from Charleston in fiscal year 1980 while Reddies River remains 
under Charleston District. (See Table 6-J on Dams 
and Reservoirs.) 
30A. W. KERR SCOTT DAM AND RESERVOIR, N. C. 
Location. W. Kerr Scott Dam and Reservoir is on 
Yadkin River, North Carolina, about 6 miles upstream 
from Wilkesboro. At full flood-control pool elevation (1,075 
feet mean sea level), the reservoir extends 15.7 miles 
upstream to the Wilkes-Caldwell County line. 
6-15

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1983 
Existing project. The project consists of a rolled earthfill 
dam 1,740 feet long, with top of dam at elevation 
1,107.5 feet mean sea level or about 148 feet above 
streambed elevation; a spillway near the north abutment 
of the dam in a rock cut with crest elevation 1,075; and 
outlet works consisting of an intake structure, control 
tower, and a circular concrete conduit 12.25 feet in 
diameter through the base of the dam near the south abutment. 
The reservoir has a gross capacity of 153,000 acrefeet 
of which 112,000 acre-feet are reserved for flood control, 
33,000 acre-feet will be used as required for water 
supply, and 8,000 acre-feet being contained in the 
minimum pool. Estimated cost is $9,110,000 (1983) for new 
work. The existing project was authorized by the 1946 
Flood Control Act. 
Local cooperation. Requirements fully satisfied. For 
details, see page 413 of Annual Report for 1963. 
Operations and results during fiscal year. Maintenance: 
General operation and maintenance cost $982,327. Recreation 
use fees of $7,000 were expended for operation, 
maintenance, and construction of recreation facilities. 
Condition at end of fiscal year. The project was commenced 
in August 1960 and placed in operation for flood 
control and water storage purposes in February 1963. 
31. INSPECTION OF COMPLETED FLOOD CONTROL 
PROJECTS 
To determine the extent of compliance with approved 
regulations for maintenance and operation, inspections 
were made for the following projects during fiscal year 
1983: Ellis Swamp, Gates County, N. C.; Gapway Swamp, 
Columbus County, N. C.; Old Field Swamp, Robeson County, 
N. C.; Gardners Creek, Martin County, N. C.; New 
River, Onslow County, N. C.; Pungo Creek, Beaufort County, 
N. C.; South Creek, Beaufort County, N. C.; Pungo 
River, Beaufort County, N. C.; and Filberts Creek, Edenton, 
N. C.; Pantego and Cucklers Creek, Beaufort County, 
N. C.; White Oak Dike, Bladen and Pender Counties, N. C.; 
Ellerbe Creek, Durham County, N. C.; Pasquotank Dike, 
Pasquotank County, N. C.; Perquimans River, Perquimans 
County, N. C.; Core Creek, Craven County, N. C.; 
Princeville Dike, Edgecombe County, N. C.; Swift Creek, 
Pitt County, N. C.; Carolina Beach, New Hanover County, 
N. C.; Wrightsville Beach, New Hanover County, N. C.; 
Goldsboro, Neuse River, Wayne County, N. C.; Broad 
Creek, Beaufort County, N. C.; Little Rockfish Creek, 
Hope Mills, N. C.; Black River, Harnett County, N. C.; Lick 
Run, Roanoke, Va.; and Leith Creek, Scotland County, 
N. C. Responsible local officials were advised of inadequacies 
in maintenance and operation on local flood protection 
works where appropriate. Cost for the period was 
$26,000. Total cost to September 30, 1983, was $244,559, 
charged to operations. 
32. FLOOD CONTROL WORK UNDER SPECIAL 
AUTHORIZATION 
Flood control activities pursuant to Section 205, Public 
Law 858, 80th Congress, as amended (preauthorizationi. 
(See Table 6-K.) 
Emergency flood control activities and hurricane flood 
and shore-protection activities at Federally authorized 
projects (Public Law 99, 84th Congress, and antecedent 
legislation). 
National Emergency Preparedness Planning cost 
$80,111. Advance Measures were $87,596. Monitoring of 
local corrective measures on faulty dam at Westward 
Lake, Roanoke County, Va. cost $2,350. 
Multiple-Purpose Projects Including Power 
33. ROANOKE RIVER BASIN, VA. AND N. C. 
Location. The project is on the Roanoke River and its 
tributaries in Virginia and North Carolina within a radius 
of 100 miles from Danville, Virginia. 
Existing project. The Flood Control Act of 1944 approved 
a general plan for the comprehensive development of 
the Roanoke River Basin for flood control and other purposes, 
and authorized construction of John H. Kerr and 
Philpott Reservoirs. (See Tables 6-J for a list of dams and 
reservoirs included in the comprehensive plan.) 
Local cooperation. None required. John H. Kerr and 
Philpott Reservoirs are the only projects in the comprehensive 
plan that have been authorized for construction. 
(See Table 6-J on Dams and Reservoirs.) 
33A. JOHN H. KERR DAM AND RESERVOIR, VA. 
AND N. C. 
Location. The project is on Roanoke River, about 178.7 
river miles above its mouth, in Mecklenburg County, 
Virginia, and 20.3 miles downstream from Clarksville, 
Virginia. The reservoir extends upstream on Roanoke 
River 56 miles and on Dan River 34 miles. 
Existing project. The authorized project provides for a 
concrete gravity dam with wing and saddle dikes on the 
right and left banks, with a total length of about 22,285 
feet. The reservoir is operated as a unit of a coordinated 
system of reservoirs in the Roanoke River Basin for 
control of floods, generation of hydroelectric power, 
regulation of low-water flow, and for other purposes. The 
power installation is 204,000 kilowatts. (For further details 
see Annual Report for 1962.) Estimated cost is $67,529,000 
(1983) for construction and $24,521,000 for land and 
damages, including relocation of highways, railroads, and 
utilities, a total of $92,050,000 for new work. The existing 
project was authorized by the 1944 Flood Control Act. 
Local cooperation. None required. 
Operations and results during fiscal year. New work: 
Construction of two comfort stations at Palmer Point and 
Rudds Creek continued at a cost of $126,734. Cost-sharing 
with the state of N. C. at various sites cost $628. Maintenance: 
Geneal operation and maintenance was performed at 
a cost of $3,464,432. Recreation user fees of $77,759 were 
expended for operation and maintenance of recreation 
facilities. 
Condition at end of fiscal year. Project is complete 
except for additional recreational facilities. Production of 
6-16

WILMINGTON, N. C., DISTRICT 
power and protection from floods are provided by project. 
33B. PHILPOTT LAKE, VA. 
Location. On Smith River, Virginia, 44.3 miles above its 
junction with Dan River, and 35 miles upstream from 
Virginia-North Carolina State line in Franklin and Henry 
Counties. 
Existing project. The authorized project provides for a 
concrete gravity dam 892 feet long and with a maximum 
height of 220 feet. Reservoir is operated as a unit of a coordinated 
reservoir system for flood control in the Roanoke 
River Basin, generation of hydroelectric power, regulation 
of low-water flow, and for other purposes. The powerhouse 
has a total installation of 14,000 kilowatts. (For further 
details see Annual Report for 1962.) Federal cost estimate 
is $13,933,000 (1983) for construction and $1,157,000 for 
lands and damages, a total of $15,090,000. Existing project 
was authorized by 1944 Flood Control Act. 
Local cooperation. None required. 
Operations and results during fiscal year. New work: 
Design of a comfort station at Philpott Park cost $39,578. 
Construction of a washhouse at Goose Point and a comfort 
station at Salthouse continued at a cost of $185,131. 
Maintenance: General operation and maintenance of the 
project was performed at a cost of $1,004,106. Recreation 
user fees of $21,000 were expended for operation and 
maintenance of recreation facilities. 
Condition at end of fiscal year. The project is complete 
except for additional recreational facilities, and is providing 
power and flood protection. 
34. SCHEDULING FLOOD CONTROL RESERVOIR 
OPERATIONS 
B. Everett Jordan Dam and Lake, located in the Cape 
Fear River Basin, North Carolina, began fiscal year 
1983 at elevation 213.95 feet, MSL or 2.05 feet below normal 
pool. The lake gradually rose and stayed near normal 
pool level until rainfall produced a lake level rise to elevation 
219.60 feet, MSL or 3.6 feet above normal on 
December 18, 1982. Jordan Lake was gradually pulled 
down and remained near normal pool through mid- 
February 1983. Spring rains produced three major lake 
level peaks, two of which reached 221.05 and 220.95 feet, 
MSL on February 17 and April 17, respectively. The third 
lake level peak of 222.55 feet, MSL on March 22 was the 
maximum elevation for fiscal year 1983. Jordan Lake remained 
near normal pool from late April through mid-July. 
Declining inflows then caused a gradual drawdown 
through the end of fiscal year 1983. On September 30,1983, 
Jordan Lake was at the minimum elevation for fiscal year 
1983 which was 210.20 feet, MSL or 5.8 feet below normal 
pool. Flood damages prevented for fiscal year 1983 and 
since impoundment were equal to $675,000 and $1,245,000, 
respectively. Total cost of functional operation for the 
period was $80,632. 
Falls Lake is a new project which began permanent lake 
impoundment on January 13, 1983. Prior to this time during 
final construction, a partial impoundment was maintained 
near elevation 227 feet, MSL, for water supply use 
by the City of Raleigh, N. C. The project is located on the 
Neuse River in the Neuse River Basin, North Carolina, and 
was at elevation 225.6 feet, MSL, at the beginning of the 
fiscal year. The lake level remained near elevation 227.0 
until November 20, 1982. Falls Lake was drawn down to 
elevation 218.5 on December 11, 1982 to accommodate 
bridge demolition in the reservoir area. Heavy rainfall 
caused Falls Lake to refill rapidly to near elevation 227.0 
and remained there until January 13, 1983 when permanent 
impoundment to elevation 250.0 began. The lake level 
rose gradually to elevation 246.0 on February 16,1983. To 
accommodate work in the project area, the lake was maintained 
near elevation 247.0 until June 23, 1983 when refilling 
to 250.0 began. However, during this holding period, 
rainfall produced several rises in lake levels with the maximum 
elevation of the fiscal year at 253.2 occurring on 
March 22, 1983. Due to below normal rainfall during June 
through September, Falls Lake remained near elevation 
247.0 and ended the fiscal year at elevation 245.6. Flood 
damages prevented in FY 83 were $3,475,000 which is also 
the cumulative total. Total cost of functional operation for 
the period was $38,385. 
John H. Kerr Dam and Reservior, located in the 
Roanoke River Basin, Virginia and North Carolina, began 
fiscal year 1983 at 1.8 feet below rule curve or at elevation 
297.72 feet, MSL. The reservoir level climbed above rule 
curve in late October with several fluctuations continued 
to rise through April attaining the maximum elevation of 
the fiscal year on April 18, 1983 at 314.35 feet, MSL, or 
12.35 feet above rule curve. From the end of April through 
September, the reservoir was gradually drawn down 5.4 
feet below rule curve, reaching elevation 294.10 feet, MSL, 
on September 30 which was the minimum elevation for the 
fiscal year. The 13-foot minimum stage required in the 
lower Roanoke River at Weldon for striped bass spawning, 
was maintained during the entire period by augmentation 
flows from Kerr. All inflows to Kerr Reservoir were controlled 
without having to spill water over the spillway, or 
through the sluices. Gross generation for the fiscal year 
amounted to 527,536,800 kilowatt hours and power 
revenue was $4,740,408, making an accumulative total 
since inception of $105,288,811. Flood damages prevented 
during the fiscal year amounted to $2,187,000 and the 
cumulative flood damages prevented since the project 
began amount to $62,207,000. Total cost of functional 
operations for the period was $117,114. 
Philpott Lake, located on the Smith River - Dan River 
Basin, Virginia, was 2.90 feet below rule curve or at elevation 
968.56 feet, MSL at the beginning of the fiscal year. 
Periods of rainfall caused a gradual rise in the lake level to 
rule curve at elevation 971.50 on December 16, 1982. 
Philpott Lake remained near rule curve until February 2, 
1983. Above normal rainfall caused several significant lake 
fluctuations above rule curve during February, March, and 
April. The maximum elevation of the fiscal year was 981.29 
on April 10, 1983. Philpott Lake was drawn down steadily 
to near rule curve elevation 973.50 on May 13, 1983. With 
6-17

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1983 
minor fluctuations, the lake level remained near rule curve 
until July 19, 1983. Below normal rainfall during July, 
August, and September caused the lake to be drawn down 
steadily to end the fiscal year on September 30 at the 
minimum elevation of the year at 964.04 feet, MSL, or 7.50 
feet below rule curve. Flood damages prevented in FY 83 
were $2,200,000, which makes the cumulative total since 
inception of the project equal to $18,970,000. Gross generation 
amounted to 31,914,800 kilowatt-hours and power 
revenue was $836,542, making a total of $12,163,692 since 
inception. Total cost of functional operation for the period 
was $47,832. 
W. Kerr Scott Dam and Reservoir, located in North 
Carolina on the Yadkin River in the Pee Dee River Basin, 
N.C.-S.C., began fiscal year 1983 at elevation 1,021.7 feet, 
MSL, or 8.3 feet below the normal pool elevation of 1,030.0 
feet, MSL. The reservoir level declined to elevation 1,020.1 
feet, MSL, on September 28, the minimum level for the 
fiscal year. Above normal rainfall during November 
caused the reservoir to rise, reaching normal pool 
elevation on November 30. The reservoir then fluctuated 
near the normal level until heavy rainfall during February, 
March, and April caused several sharp peaks with the 
maximum reservoir level for the fiscal year occurring on 
April 11 at elevation 1047.7 feet, MSL. Rainfall for the 
month of April totaled 9.75 inches (5.66 inches above 
normal) which set a new maximum for the month of April 
since records began. For the remainder of the fiscal year 
the reservoir fluctuated near normal pool level and ended 
the year at elevation 1,026.55 feet, MSL. Flood damages 
prevented during the fiscal year were $14,416,000 which 
makes the cumulative total since inception equal to 
$58,601,000. Total cost of functional operation for the 
period was $34,290. 
General Investigations 
35. SURVEYS 
Cost for the period was $836,389, of which $60,943 was 
for navigation studies, $414,507 was for flood control 
studies, $128,382 was for beach erosion studies, $60,749 for 
review of completed projects, $393 for project deauthorization 
review, $90,275 for Special Investigations, $19,603 for 
FERC licenses review, $3,213 for soil conservation service, 
$50 for water quality management, $1,587 for hydrologic 
studies, $54,988 for cooperation with states, and $1,704 for 
dam inspection and inventory. 
36. COLLECTION AND STUDY OF BASIC DATA 
Flood plain information studies, as authorized by Section 
206, 1960 Flood Control Act, as amended, comprise 
compilation and dissemination, upon the request of a State 
or a political subdivision thereof, of information on floods 
and flood damages, including identification of areas subject 
to inundation by floods of various magnitudes and frequeneies, 
and general criteria for guidance of Federal and non- 
Federal interests and agencies in the use of flood plain 
areas; and provide advice to other Federal agencies and 
local interests for their use in planning to ameliorate the 
flood hazard. Total costs for the period were $207,421. 
Total costs to September 30, 1983 were $3,141,797. 
37. ADVANCE ENGINEERING AND DESIGN 
Advance engineering and design for Fort Fisher and 
Vicinity, N. C. cost $39,322. Fiscal year 1982 was the first 
year of funding under the G. I. program. For additional information 
see the detailed write-up for Fort Fisher and 
Vicinity. 
6-18

WILMINGTON, N.. C., DISTRICT 
TABLE 6-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 80 FY 81 FY 82 FY 83 Sept. 30, 1983 
1. Aquatic Plant Control 
(R&H Act of 1965) 
(Contributed Funds) 
(Regular Funds) 
(Regular Funds) 
2. Atlantic Intracoastal 
Waterway between 
Norfolk, Va. & St. 
Johns River, Fla. 
(Regular Funds) 
(Contributed Funds) 
3. Beaufort Harbor, N.C. 
(Regular Funds) 
(Contributed Funds) 
4. Cape Fear River, 
N. C. above 
Wilmington 
5. Channel from Back 
Sound to Lookout 
Bight, N. C. 
6. Lockwoods Folly 
River, N. C. 
(Regular Funds) 
(Contributed Funds) 
7. Manteo (Shallowbag) 
Bay, N. C. 
(Regular Funds) 
(Contributed Funds) 
8. Morehead City 
Harbor, N. C. 
(Regular Funds) 
(Contributed Funds) 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
Maint: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Maint: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Maint: 
Contrib. 
Cost 
15,000 
3,398,775 s 
3,874,0243 
3,380,400 
3,468,592 
110,585 
153,518 
4,500 
4,500 
2,564,000 4 
2,558,817 ' 
5,501,525 
4,669,699 
13,327 
13,327 
1,153,461 471,611 
972,028 652,010 
445,034 
445,670 
93,545 
84,231 
201,302 
201,302 
1,387,000 
977,550 
1,180,672 
1,230,064 
54,000 
54,000 
-4,411 
1,777,561 
1,794,868 
12,235 
10,633 
21,000 
3,151 
197,857 
196,407 
1,529,000 
1,543,013 
1,850,445 
1,847,785 
3,548,007 
3,335,094 
490,112 
329,534 
7,000 
22,261 
2,369 
725,000 ' 
545,5776 
3,025,300 
3,136,098 
11,560 
340,000 
297,597 
58,755 
58,755 
18,000 
13,184 
3,644,477 ' 
703,951' 
3,783,937 
3,914,751 
73,740 
57,800 
243 
50 
32 
73 
34 
331,000 414 
311,479 434 
195,000 
190,448 
327,000 
57,655 
507,000 
502,490 
820,000 
1,066,908 
2,723,000 
2,204,476 
44,000 
41,800 
-_ 
3,097,000 
3,307,415 
60,962 
221,540 
7 
11 
137,400 
131,539 
31,809 
31,809' 
29,706,893' 
26,418,6422 
55,341,349' 
54,721,951 
85,300 
57,800 
3,500" 841,88910 
),88012 649,2691 
,000 2,727,814 '3 
,559 2,726,97013 
1,000 34,000 
- 168,833 
- 168,833 
- 3,759,57314 
- 3,759,57314 
1,000 11,193,41415 
1,800 11,191,51716 
- 88,328 
- 88,328 
,000 1,973,571 
L,069 1,969,936 
- 93,477 
125,319 
363,000 
360,874 
92,650 
1,000,000 
1,037,405 
4,941,000 
4,270,169 
2,200 
3,418,000 
3,347,194 
40,080 
40,080 
397,817:: 
320,105 
2,043,046 
2,034,960 
92,650 
6,925,9451: 
6,788,5611 
21,791,507 
20,583,559 
98,000 
98,000 
6,546,05319 
6,546,053 
28,788,262" 
28,693,133" 
696,711 
696,711 
6-19

REPORT OF THE CHIEF OF ENGINEERS. U. 8. ARMY 1983 
TABLE 6-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Sectlon Total Cost to 
ia Text Project Funding FY 80 FY 81 FY 82 FY 83 Sept. 30, 1983 
9. Ocracoke Inlet, N. C. 
10. Roanoke River, N. C. 
11. Rollinson Channel, N. C. 
12. Shallotte River, N. C. 
13. Silver Lake 
Harbor, N. C. 
(Regular Funds) 
(Contributed Funds) 
14. Waterway Connecting 
Pamlico Sound and 
Beaufort Harbor, N.C. 
(Regular Funds) 
(Contributed Funds) 
15. Waterway Connecting 
Swanquarter Bay with 
Deep Bay, N. C. 
16. Wilmington Harbor, N. C. 
(Regular Funds) 
(Contributed Funds) 
17. Fort Fisher and 
Vicinity, N. C. 
18. Ararat River, N.C. 
19. Black River, N. C. 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Maint: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Contrib: 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Maint: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
54,832 
54,500 
29,000 
25,457 
4,782 
4,782 
6,542 
6,542 
616 
616 
144,300 
124,210 
75,000 
18,216 
16,696 
5,023 
5,023 
804 
804 
345,526 
364,956 
75,000 
10,826 
12,346 
16,000 
13,740 
1,600 
1,456 
11,985 
5,598 
18,633 
2,633 
18,000 
20,420 
-144 
1,429 
7,036 
16,707 
32,707 
645,000 309,000 
433,285 407,288 
287,921 52,608 
72,810 265,750 
- 709,000 21 
- 119,85622 
400 - 
275 - 
- 963 
4,016,800 
4,048,204 
514,347 
489,834 
260,000 
213,399 
- 23,000 
73,256 
3,074,000 
2,814,849 
475,232 
109,970 
230,000 
155,712 
- 5,000 
3,784 
2,661,000 
2,346,392 
210,535 
429,572 
5,354,000 
5,847,149 
354,367 
280,371 
118,661 2,228 
- 450,000 
- 418,484 27 
548 4,291 
6-20 
346,240 
346,240 
878,044 
874,329 
404,584 
404,584 
550,364 
550,364 
589,105 
589,105 
762,896 
762,116 
18,181 
18,181 
169,976 
169,976 
184,284 
184,284 
3,051,218 
2,937,131 
75,000 
75,000 
502,567 
502,567 
1,951,497 
1,949,528 
2,452 
2,452 
819,799 
230,655 
182,850 
182,725 
18,715,22623 
18,715,22623 
42,233,470 24 
42,143,349"2 
2,749,701 
2,490,70125 
490,000 
490,000 
450,000 
418,484 
476,290 
475,574

WILMINGTON, N. C., DISTRICT 
TABLE 6-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section 
in Text Project 
20A. B. Everett Jordan 
Dam and Lake, N. C. 
(Regular Funds) 
(Contributed Funds) 
20B. Randleman Lake, N. C. 
21. Carolina Beach and 
Vicinity, N. C. 
(Regular Funds) 
(Contributed Funds) 
22. Deep Creek, N. C. 
23. Genoa Sewer Facility 
Wayne County, N. C. 
24. Goldsboro, Neuse River, 
N. C. 
25. Joyce Creek, N. C. 
(Regular Funds) 
(Contributed Funds) 
26. Leesville, Va. - 
Roanoke River, 
Sec. 32, Demo Project 
27A. Falls Lake, N. C. 
28. Scuppernong River, N.C. 
29. Wrightsville Beach, N.C. 
(Regular Funds) 
(Contributed Funds) 
30A. W. Kerr Scott Dam 
and Reservoir, N. C. 
33A. John H. Kerr Dam 
and Reservoir 
ISLeto 
InTx Pret Total Cost to 
FY 80 FY 81 FY 82 FY 83 Sept. 30, 1983 
3,548,000 3,562,000 
3.425.461 3.849,535 
Funding 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
214,028 
238,554 
800,000 
830,789 
275,000 
184,248 
19,000 
17,997 
36,0000 
31,348� 
113,400 
20,556 
24,033,000 
19,557,763 
10,000 u 
5,206" 
24,788 
643,575 
642,344 
-18,000 
92,731 
3,003,740 
2,861,728 
3,384,941 2, 
2,087.925 2 
559,000 
561,223 
27,000 
147,365 
5,128,000 
5,247,893 
3,951,800 
3,136,513 
211,000 
17,252 
409,828 
370,046 
200,000 
199,508 
530,761 
236,332 
12,601 
6,000 
3,578 
63,000 ' 
63,9541 
10,000 
316,424 
16,057,000 
19,276,211 
4-- 
29,000" 
21,739 
850,239 
1,092,800 
986,282 
550000 
690,206 
736,119 
34,100 
203,322 
2,945,520 
2,998,266 
,500,000 94,207,641 
,407,679 91,681,731 
- 1,721,389 
- 1,721,389 
589,000 2,056,656 
571,995 1,993,804 
455,000 3,920,588 
276,193 3,732,122 
- 7,390,533 
49,483 7,174,728 
-- 4,755,389 
571,408 4,487,593 
- 387,555 
169,000 359,002 
115,800" 115,800 
31,960" 31,960 
103,500 
68,213 
206,312 
100,083 
1,279 
7,700,000 
6,189,542 
605,000 
576,848 
20,007 3 
-15,941 
58,342 
1,167,000 
989,327 
9,000 
127,362 
3,747,759 
3,542,191 
50,430 
50,430 
340,687 
304,273 
505,149 
483,664 
106,300 
100,083 
367,755 
362,426 
125,670,996 
121,345,888 
1,009,000 
962,378 
157,906 
147,702 
1,547,100 
1,547,100 
1,466,088 
1,466,088" 
8,841,326 
8,841,326 
9,074,532" 
8,847,395" 
89,622,527 
89,543,492 
44,946,751" 
44,287,277" 
6-21 
1,400 
273 
251,000" 
30,989" 
106,300 
1,382 
12,420,000 
12,317,839 
404,000 
385,530 
35,000" 
16,845" 
-15,941 
850,239 
72,964 
- . 
813,040 
807,774 
393,000. 
390,505 
3,314,160 
3,165,210

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1983 
TABLE 6-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 80 FY 81 FY 82 FY 83 Sept. 30, 1983 
33B. Philpott Lake, Va. New Work: 
Approp. - 50,000 62,400 315,000 184,000 14,771,784 
Cost 5,616 48,038 156,313 224,709 14,625,343 
Maint: 
Approp. 826,616 1,098,531 1,289,240 1,116,000 14,329,906"3 
Cost 836,790 994,694 1,302,184 1,025,106 14,111,123" 
1. Includes $2,369 refund to local interests in FY 82. 
2. Includes $198,707 for previous projects. 
3. Includes $37,763 for preauthorization cost on Masonboro 
Inlet Sec. 111. 
4. Includes $952 preauthorization cost on Masonboro Inlet 
Sec. 111. 
5. Includes preauthorization study funds for Carolina 
Beach Inlet: FY 80, $10,000; FY 81, $4,275; and preconstruction 
and construction funds; FY 81, $2,725; FY 82, $133,000. 
6. Includes preauthorization study costs for Carolina 
Beach Inlet: FY 80, $6,614; FY 81, $6,906; FY 82, $755; and 
preconstruction and construction costs: FY 82, $62,196. 
7. Includes preauthorization study funds for Bogue Inlet: 
FY 82, $14,000; FY 83, $38,490; and preconstruction and construction 
funds: FY 83, $38,510. 
8. Includes preauthorization study costs for Bogue Inlet: 
FY 82, $7,174; FY 83, $45,316; and preconstruction and construction 
costs: FY 83, $21,368. 
9. Includes $107,634 for previous projects. 
10. Includes $25,000 for previous projects. 
11. Includes preauthorization study funds for Morgan 
Creek: FY 82, $15,000; FY 83, $18,822; and preconstruction and 
construction funds: FY 83, $209,678. 
12. Includes preauthorization study costs for Morgan 
Creek: FY 82, $8,790; FY 83, $25,032; and preconstruction and 
construction costs: FY 83, $17,058. 
13. Includes $12,854 for previous projects. 
14. Includes $149,119 for previous projects. 
15. Includes $8,178 for previous projects. 
16. Includes preauthorization study funds: FY 64, $3,000; 
FY 65, -$2,755; FY 71, $8,000; FY 72, $2,000; FY 74, $9,000; FY 
75, $25,000; FY 76 & 76T, $20,000; FY 77, $2,500; FY 78, $8,800; 
FY 79, $3,000; FY 81, $1,680; and preconstruction planning 
funds: FY 80, $15,000 and FY 81, $19,320. 
17. Includes preauthorization study costs: FY 64, $219; FY 
65, $26; FY 71, $8,000; FY 72, $1,448; FY 73, $552; FY 74, $9,000; 
FY 75, $11,925; FY 76 & 76T, $27,977; FY 77, $7,598; FY 78, 
$7,449; FY 79, $4,351; FY 81, $1,680; and preconstruction planning 
costs: FY 80, $5,686 and FY 81, $1,471. 
18. Adjusted by $6,361 to reflect actual cost. 
19. Includes $44,484 for previous projects. 
20. Includes $284,557 for previous projects. 
21. Includes preauthorization study funds for Swanquarter 
Bay: FY 80, $5,000; FY 81, $78,000; FY 82, $8,514 and 
preconstruction and construction funds: FY 82, $7,486; FY 83, 
$610,000. 
22. Includes preauthorization study costs for Swanquarter 
Bay: FY 80, $5,000; FY 81, $64,682; FY 82, $13,410; FY 
83, $8,422 and preconstruction and construction costs: FY 83, 
$28,342. 
23. Includes $4,625,614 for new work on previous projects. 
24. Includes $602,614 for previous projects. 
25. Includes refunds to local interests: FY 78, $92,374; FY 79, 
$8,000; FY 80, $14,007; FY 81, $1,847; FY 82, $2,823. 
26. Includes preauthorization study funds: FY 81, 
$153,000; FY 82, $128,000; FY 83, $62,487 and preconstruction 
funds: FY 83, $106,513. 
27. Includes preauthorization study costs: FY 81, 
$116,322; FY 82, $162,793; FY 83, $64,372 and preconstruction 
costs: FY 83, $74,997. 
28. Includes preauthorization study funds: FY 82, $12,500; 
FY 83, $3,291 and preconstruction and construction funds: FY 
83, $100,009. 
29. Includes preauthorization study costs: FY 82, $12,500; 
FY 83, $3,291 and preconstruction costs: FY 83, $16,169. 
30. Includes $22,556 preauthorization cost. 
31. Includes $9,706 preauthorization cost. 
32. Includes $5,223 preauthorization cost. 
33. Includes monitoring costs: FY 80, $7,414; FY 81, 
$10,842; FY 82, $1,382. 
34. Includes $5,206 preauthorization cost. 
35. Includes $21,739 preauthorization cost. 
36. Includes $16,845 preauthorization cost. 
37. Preauthorization cost. 
38. Includes $61,585 refund to local interests. 
39. Includes Special Recreation Use Fees funds: FY 74, 
$4,000; FY 75, $5,500; FY 76 & 76T, $3,600; FY 77, $5,800; FY 
78, $7,200; FY 79, $8,000; FY 80, $10,000; FY 81, $10,000; FY 82, 
$11,040; FY 83, $7,000. 
40. Includes Special Recreation Use Fees costs: FY 74, 
$4,000; FY 75, $4,400; FY 76 & 76T, $4,666; FY 77, $5,193; FY 
78, $6,824; FY 79, $7,506; FY 80, $11,312; FY 81, $9,688; FY 82, 
$9,727; FY 83, $7,000. 
41. Includes Special Recreation Use Fees funds: FY 74, 
$35,000; FY 76 & 76T, $48,000; FY 77, $51,400; FY 78, $115,100; 
FY 79, $63,000; FY 80, $60,000; FY 81, $80,000; FY 82, $67,160; 
FY 83, $77,759; and maintenance and operation of Dams funds: 
FY 79, $167,646. 
42. Includes Special Recreation Use Fees costs: FY 75, 
$35,000; FY 76 & 76T, $13,606; FY 77, $85,692; FY 78, $114,604; 
FY 79, $1,120; FY 80, $118,718; FY 81, $83,760; FY 82, $67,160; 
FY 83, $77,759; and maintenance and operation of Dams costs: 
FY 79, $167,350; FY 80, $296. 
43. Includes Special Recreation Use Fees funds: FY 75, 
$47,000; FY 78, $40,400; FY 79, $22,000; FY 80, $25,000; FY 81, 
$20,000; FY 82, $20,240. 
44. Includes Special Recreation Use Fees costs: FY 75, 
$13,741; FY 76 & 76T, $31,666; FY 77, $1,593; FY 78, $39,771; 
FY 79, $22,629; FY 80, $24,619; FY 81, $20,381; FY 82, $20,240. 
45. Includes $400,000 refund to local interests. 
6-22

WILMINGTON, N. C., DISTRICT 
TABLE 6-B 
Acts 
AUTHORIZING LEGISLATION 
Work Authorized 
July 25, 1912 
July 25, 1912 
August 8, 1917 
July 18, 1918 
Jan. 21, 1927 
July 3, 1930 
March 4, 19332 
June 26, 19343 
August 26, 1937 
August 26, 1937 
June 20, 1938 
June 20, 1938 
March 2, 1945 
June 30, 1948 
May 17, 1950 
May 17, 1950 
September 3, 1954 
Nov. 29, 1963, 
see. 107 
July 14, 1960 
April 7, 1966, 
sec. 107 
July 14,1960 
Nov. 7, 1966 
Nov. 7, 1966 
Dec. 31, 1970 
ATLANTIC INTRACOASTAL WATERWAY BETWEEN 
NORFOLK, VA., and ST. JOHNS RIVER, 
FLA. (See Section 2 of text) 
Original route of the Norfolk-Beaufort Inlet section. 
Purchase of canal. 
Change in route; following changes approved by 
Secretary of War, April 14, 1919: 
Albemarle Sound-Pamlico Sound section: Changed from 
"Alligator River-Rose Bay route" to "Alligator River- 
Pungo River route." 
Pamlico Sound-Neuse River Section: Changed from 
"Pamlico Sound-Brant Shoal Neuse River route" to 
"Goose Creek-Bay River route." 
Alligator River-Pungo route (proposed land cut connecting 
the rivers): Changed from a straight line to a bent 
line approaching nearer town of Fairfield, N. C. 
A 12-foot channel 90 feet wide from Beaufort to Cape 
Fear River, N. C., including highway bridge and tidal 
lock.4 
An 8-foot channel 75 feet wide from Cape Fear River to 
Winyah Bay, S. C. 
Construct a suitable bridge near Fairfield, N. C. 
Operating and care of works of improvements provided 
for with funds from War Department appropriations for 
rivers and harbors. 
Increasing dimensions of waterway to 12 feet deep and 
90 feet wide. 
A 12-foot side channel 90 feet wide to Swansboro. 
A yacht basin near Southport, 12 feet deep, 230 feet 
wide, and 450 feet long, with connecting channel. 
A 6-foot channel 90 feet wide from New River Inlet to 
Inland Waterway. 
Six mooring basins. 
A 12-foot channel in New River 
Vicinity of Fairfield, drainage. 
Masonboro Inlet and connecting channels, including jetties 
at the inlet. 
A 12-foot channel and basin in Peltier Creek.' 
A 6-foot channel 90 feet wide from Intracoastal Waterway 
to Bogue Inlet gorge. 
An 8-foot channel 150 feet wide through New Topsail Inlet, 
thence a 7-foot channel 80 ft. wide to Intracoastal 
Waterway by way of Old Topsail Creek; and a 7-foot 
channel 80 feet wide in Banks Channel from New Topsail 
Inlet, paralleling barrier beach, to Intracoastal 
Waterway. 
Maintenance of a channel, 6 feet deep, 80 feet wide, and 
8,000 feet long, from the through channel of the waterway 
to and including a basin of the same depth, 130 feet 
wide and 180 feet long at Carolina Beach. 
Maintenance of general navigation features of N. C. 
State Ports Authority Small Boat Harbor at Southport. 
Replacement of Federally-owned and operated highway 
bridges at Coinjock, Fairfield, Wilkerson Creek, 
Hobucken, and Core Creek. 
H. D. 391, 62d Cong., 2d sess. 
H. D. 589, 62d Cong., 2d sess. 
H. D. 1478, 63d Cong., 3d sess. 
and H. D. 1136, 64th Cong., 1st 
sess.' 
Approved by Secretary of War, 
May 15, 1919. 
H. D. 450, 69th Cong., 1st sess. 
H. D. 41, 71st Cong., 1st sess. 
Rivers and Harbors Committee 
Doc. 5, 72d Cong., 1st sess. 
Rivers and Harbors Committee, 
Doc. 6, 75th Cong., 1st sess.' 
Rivers and Harbors Committee 
Doc. 75th Cong., 1st sess.' 
H. D. 549, 75th Cong., 3d sess.' 
H. D. 691, 75th Cong., 3d sess.' 
H. D. 660, 76th Cong., 3d sess.' 
H. D. 421, 80th Cong., 1st sess.' 
H. D. 723, 80th Cong., 2d sess.' 
H. D. 341, 81st Cong., 1st sess.' 
H. D. 379, 81st Cong., 1st sess.' 
Detailed Project Report 
April 1963. 
Detailed Project Report 
July 1965. 
H. D. 515, 89th Cong., 2d sess.' 
H.D. 514, 89th Cong., 2d sess.' 
H. D. 142, 92nd Cong., 1st sess. 
6-23 
Documents

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1983 
TABLE 6-B (Continued) 
Acts 
AUTHORIZING LEGISLATION 
Work Authorized 
October 22, 1976 
August 13, 1968 
February 18, 1982 
see. 107 
July 14, 1960 
September 7, 1983 
see. 107 
July 14, 1960 
March 3, 1881 
March 2, 1907 
March 3, 1925 
July 3, 1930 
March 2, 1945 
May 17, 1950 
May 21, 1965 
see. 107 
July 14, 1960 
August 12, 1983 
see. 107 
July 14, 1960 
July 3, 1930 
Oct. 17, 1940 
Feb. 7, 1967 
sec. 107 
July 14, 1960 
August 30, 19358 
August 26, 1937 
March 2, 1945 
March 2, 1945 
Modification of terms of local cooperation to allow for 
full Federal funding of Wilkerson Creek and Coinjock 
Bridges. 
Mitigation of damages caused by north jetty at Masonboro 
Inlet. 
An 8-foot channel 150 feet wide through Carolina Beach 
Inlet to the Intracoastal Waterway. 
An 8-foot channel 150 feet wide from the gorge in 
Bogue Inlet through the ocean bar. 
BEAUFORT HARBOR, N. C. (See Section 3 of text) 
A 9-foot channel 200 feet wide through Bulkhead Channel 
to Beaufort; a 6-foot channel 100 feet wide to North 
River and Core Sound; and construct jetties on 
Shackleford Point. 
Repairs to Fort Macon jetties and additional jetties and 
shore protection. 
Bulkhead across Bird Shoal. 
Increase in depth to 12 feet in Bulkhead Channel, 
Gallants Channel, and in front of Beaufort. 
Increase in width and length of basin in front of 
Beaufort, all to 12 feet deep. 
Increase in depth to 12 feet and in width to 100 feet in 
Taylors Creek; transfer to Beaufort Harbor project. 
Channels 15 feet deep, 100 feet wide in Bulkhead, 
Gallants and Taylors Creek channels, and through turning 
basin in front of Beaufort; and harbor of refuge in 
Town Creek, 12 feet deep, 400 feet wide, and 900 feet 
long connected to Gallants Channel by channel 12 feet 
deep, 150 feet wide, and 1,400 feet long. 
A channel 14 feet deep, 70 feet wide, and 1,900 feet long, 
from Bulkhead Channel to a turning basin 14 feet deep, 
150 feet wide, and 300 feet long near the upper end of 
Morgan Creek. 
SILVER LAKE HARBOR, N. C. (See Section 13 of 
text) 
Entrance channel, 5 feet deep and 50 feet wide, from 
Pamlico Sound to the 3-foot contour in the lake, and 
training wall at entrance. 
Channel, 10 feet deep, and anchorage basin of same depth, 
100 feet wide across Big Foot Slough and 60 feet 
wide in entrance. 
Basin depth of 12 feet in Silver Lake Harbor; channels 
12 feet deep, 150 feet wide, in Teaches Hole and Big 
Foot Slough Channels and across Bluff Shoal; entrance 
channel, same depth, 60 feet wide; and training wall on 
south side of entrance channel. 
WATERWAY CONNECTING PAMLICO SOUND AND 
BEAUFORT HARBOR, N. C. (See Section 14 of text) 
A 7-foot channel 75 feet wide from Pamlico Sound to 
Beaufort Harbor via Wainright Channel. 
A 7-foot channel 75 feet wide to Atlantic. 
Channels 7 feet deep, 75 feet wide, at east and west 
ends of Harkers Island and side channel 5 feet deep, 75 
feet wide, with basin 150 by 130 feet, same depth, at Davis. 
A 7-foot side channel 75 feet wide, with basin 200 feet by 
500 feet, same depth, at Sealevel. 
H. D. 597, 94th Cong., 2d sess. 
Approved by OCE Oct. 2, 1980 
Detailed Project Report. 
June 1980 
Detailed Project Report 
May 1983 
Annual Report, 1881, p. 1013 
Specified in act. 
Rivers and Harbors Committee 
Doc. 8, 68th Cong., 2d sess.1 
H. D. 776, 69th Cong., 2d sess. 
H. D. 334, 76th Cong., 1st sess.' 
H. D. 111, 81st Cong., 1st sess. z 
Detailed Project Report 
April 1965 
Detailed Project Report 
June 1983 
Rivers and Harbors Committee 
Doc. No. 3, 70th Cong., 1st sess. 
H. D. 325, 76th Cong., 1st sess.' 
Detailed Project Report 
July 9, 1965 
H. D. 485, 72d Cong., 2d sess.1 
Rivers and Harbors Committee 
Doc. 92, 74th Cong., 2d sess.' 
H. D. 99, 77th Cong., 1st sess.' 
S. D. 247, 77th Cong., 2d sess.' 
6-24 
Documents

WILMINGTON, N. C., DISTRICT 
TABLE 6-B (Continued) 
Acts 
AUTHORIZING LEGISLATION 
Work Authorized 
May 17, 1950 
July 11, 1963, 
sec. 107 
July 14, 1960 
Sept. 22, 1967 
see. 107 
July 14, 1960 
Feb. 24, 1969, 
sec. 107 
July 14, 1960 
April 3, 1975, 
see. 107 
July 14, 1960 
A 6-foot side channel 60 feet wide, with basin 100 feet by 
about 600 feet, same depth, at Marshallberg. 
A side channel 7 feet deep, 70 feet wide to local harbor at 
Cedar Island and an access channel 6 feet deep, 60 feet 
wide and about 400 feet long to a basin same depth, 60 by 
100 feet. 
An entrance channel 6 feet deep, 60 feet wide, from Back 
Sound to harbor of refuge 120 by 250 feet, same depth, at 
west end of Harkers Island in Brook Creek. 
A channel 7 feet deep, 70 feet wide, from existing side 
channel at Atlantic to a basin 600 by 180 feet, same depth, 
with a breakwater, between mouth of Little Port Brook 
and White Point. 
Deepening the existing 5-foot channel and basin at Davis 
to 7 feet. 
H. D. 68, 81st Cong.; 1st sess.1 
Detailed Project Report 
Dec. 12, 1968 
Detailed Project Report 
March 13, 1967 
Detailed Project Report 
Dec. 21, 1967 
Detailed Project Report 
Feb. 8, 1974 
1. Contains latest published maps. 6. Jetties on each side of Masonboro Inlet. 
2. Public Law No. 443, 72d Cong. 7. A 6- by 50-foot channel provided under Section 3, River 
3. Permanent Appropriations Repeal Act. and Harbor Act of March 2,1945; 12 by 90-foot project classified as 
4. Tidal lock in land cut between Myrtle Sound and Cape inactive. 
Fear R5.i vAer . 8. Included in the Public Works Administration Program, 12-foot by 90-foot channel in New River from In- Jan. 3, 1934. 
tracoastal Waterway to and including a basin at Jacksonville, 
N.C. 
6-25 
Documents 
_. 
_.

TABLE 6-C 
REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1983 
OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to September 30, 1983 
Full Report 
Project See Annual Operation and Report for Construction Maintenance 
Aquatic Plant Controls' 
& H Act of 1958 and 1962) 1969 70,664 - 
Atlantic Beach Channels, N. C. 1976 29,101' 66,630 
Avon Harbor, N. C.' 1975 74,096 89,779 
Bay River, N. C.' 1950 44,382 49,627 
Belhaven Harbor, N. C.' 1982 126,687 39,500 
Black River, N. C. 1969 12,358 124,846 
Cashie River, N. C. 1950 40,403 15,905 
Channel Connecting Thoroughfare Bay 
with Cedar Bay, N.C. 1975 69,610 25,615 
Channel from Pamlico Sound to Rodanthe, N. C.' 1975 42,029 5,685 
Chowan River, N. C. 1950 - - 
Contentnea Creek, N. C.' 1941 64,395 32,247 
Drum Inlet, N. C.' 1979 166,119 1,050,579 
Edenton Harbor, N. C.' 1960 73,750 47,642 
Far Creek, N. C.' 1982 164,642 545,764 
Fishing Creek, N. C.' 1922 22,715 8,633 
Knobb's Creek, N. C.', 2 19613 80,500 47,664 
Mackay Creek, N. C.' 1938' 13,375 6,273 
Neuse River, N. C.' 1982 477,223� 326,673 
Newbegun Creek, N. C. 1928 4,802 247 
Northeast (Cape Fear) River, N. C.' 1950 10,688 61,139 
Pamlico and Tar Rivers, N. C.1 1982 674,651 770,678 
Pembroke Creek, N. C. 1976 60,000 - 
Perquimans River, N. C.' 1910 13,750 414 
Scuppernong River, N. C.' 1950 81,164 80,682 
Smiths Creek, Pamlico County, N. C.' 1982 113,273 36,387 
Smiths Creek (Wilmington), N. C.' 1950 . 8,507 18 
South River, N. C.' 1936 12,452 23,686 
Stumpy PointBay, N. C.' 1982 392,381 612,815 
Swift Creek, N. C.1 1940 1,600 5,422 
Trent River, N. C.', * 1968 115,199 143,579 
Wallace Channel, Pamlico Sound, N. C. 1965 132,834 85,221 
Waterway - Norfolk, Va. to Sounds of N. C. 1976 751,196 2,893,812 
Wrights Creek, N. C.' 1982 68,325 166,602 
1. Completed. 
2. Transferred from Norfolk District (FY 1970); Meherrin 
River, N. C., Transferred to Norfolk District. 
3. Report of Norfolk District. 
4. Includes $2,055 refund to local interests. 
5. 8-foot modification deauthorized August 5, 1977 under 
authority of Sec. 12, PL 93-251. 
6. Includes $1,959 refund to local interests on Dawson 
Creek, N.C. 
6-26

WILMINGTON, N. C., DISTRICT 
OTHER AUTHORIZED BEACH EROSION CONTROL PROJECTS 
Project 
Fort Macon State Park, N. C. 
For Last 
Ful Report 
See Annual 
Report For 
1973 
Cost to September 30, 1983 
Operation and 
Construction Mainteancee 
620,000- 
6-27 
TABLE 6-D

TABLE 6-E 
REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1983 
OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to September 30, 1983 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Broad Creek, Beaufort County, N. C.' 
Brunswick County Beaches, N. C. 
(Cape Fear to North Carolina - 
South Carolina State Line)"' 
Conetoe Creek, N. C.' 
Contentnea Creek, N. C.' 
Core Creek, N. C.1' 
Ellerbe Creek, Durham County, N. C.' 
Ellis Swamp, Gates County, N. C.' 
Filberts Creek, N. C.1 
Gapway Swamp, N. C. & S. C. 1,1' 
Gardners Creek, N. C.' 
Howards Mill Lake, N. C.12 
Lick Run, Roanoke, Va.' 
Little Rockfish Creek, Hope Mills, N. C.' 
Little Sugar Creek, Charlotte, N. C.',10 
New River, N. C. 1 
New River, Onslow County, N. C.' 
Northeast (Cape Fear) River, N. C.' 
Ocracoke Island, N. C.'3 
Old Field Swamp, N. C.', 1o 
Pantego Creek and Cucklers Creek, N. C. 
Pasquotank River, N. C. 
Perquimans River, N. C.' 
Pungo Creek, N. C.' 
Pungo River, N. C.', 2 
Simmons Bay, N. C.1o 
South Creek, N. C.' 
Swift Creek, Pitt and Craven Counties, N. C.' 
Tar River, N. C 
Tar River, N. C.' 
Tar River and tributaries, N. C.' 
Tar River, Princeville, N. C. 
Tranters Creek, N. C.' 
Trent River, N. C.' 
Waccamaw River & Seven Creeks, N.C. & S.C.', 10 
White Oak Dike, Bladen and Pender 
Counties, N. C.' 
1972 
1976 
1960 
1939-1943 & 1958 
1965 
1963 
1971 
1970 
1969 
1972 
1980 
1974 
1978 
1979 
1950 & 1956 
1972 
1961 
1975 
1969 
1963 
1960 
1961 
1972 
1971 
1963 
1971 
1966 
1964 
1947 
1943 
1967 
1974 
1953 
1961 
1963 
1. Project authorized by Chief of Engineers under special 
continuing authority. 
2. Includes $17,356 refund to local interests. 
3. Adjusted to reflect actual cost. 
4. Includes $3,081 refund to local interests. 
5. Includes $116,508 refund to local interests. 
6. Includes $1,519 refund to local interests. 
7. Includes $387 refund to local interests. 
8. Includes $338 refund to local interests. 
9. Adjusted $3,000 to include preauthorization cost prior to 
FY 1960. 
10. Transferred from Charleston District, FY 1980. 
11. Reclassified to inactive category February 3, 1976. 
12. Reclassified to deferred category October 2, 1980. 
13. Reclassified to inactive category November 25, 1974. 
6-28 
283,846 
572,114k 
29,867 
50,889 
236,223' 
223,413 
138,117' 
37,7773 
339,197 
54,5978 
698,400 
1,280,317 
113,657 
763,022 
51,896 
580,977 
95,873 
129,592 
86,600 
517,948 
80,931 
6,366 
582,270 
296,602* 
186,435 
194,367' 
611,096 
81,266 
18,624 
22,660 
390,249 
139,339 
64,769 
67,821 
61,473 
-
-
-
-
-
-
-
-
-
-
-
-147 
-. 
-. 
- 
214,286

WILMINGTON, N. C., DISTRICT 
DEAUTHORIZED PROJECTS 
TABLE 6-G 
For Last Fll Report Federal Centrbuted 
See Annual Report Date Funds Funds 
Project Far Deantheorized Expended Expended 
Adkin Branch, N. C. 1982 8 Sep. 812 219,477 - 
AIWW - Mooring Basins None 5 Aug. 77' - - 
Bodie Island, N. C. None 5 Aug. 77' - - 
Cape Lookout, N. C. None 5 Aug. 77' - - 
Conoho Creek, N. C. 1974 31 Mar. 782 79,782 - 
Contentnea Creek, N. C. 1972 31 Mar. 78 4,250 - 
Davis, N. C. 1982 81 Mar. 82' 25,419 - 
Harbor of Refuge, N. C. 1934 1 Nov. 81' 1,396,853 - 
Hominy Swamp, N. C. 1973 31 Mar. 782 107,472 - 
Hyde County Dike, N. C. None 5 Aug. 77' - - 
MacKay Creek, N. C. 1976 81 Mar. 782 130,900 - 
Mann's Harbor, N. C. 1973 31 Mar. 78 7,265 - 
Mill Creek, N. C. 1973 31 Mar. 782 116,895 - 
Mocassin Swamp, N. C. 1973 81 Mar. 782 36,680 - 
Moyock Creek, N. C. 1973 31 Mar. 782 64,416 - 
Nahunta Swamp, N. C. 1973 31 Mar. 782 65,878 - 
Neuse River, N. C. None 31 Mar. 784 30,911 - 
Neuse River Barrier, N. C. None 5 Aug. 77' - - 
Neuse River, 300 ft.-wide None 5 Aug. 771 - - 
channel in front of 
New Bern 
North River Dike, N. C. None 5 Aug. 77' - - 
Rockfish Creek, N. C. 1976 31 Mar. 782 157,721 - 
Six Runs Creek, N. C. 1971 31 Mar. 782 64,977 - 
Sweetwater Creek, N. C. 1973 31 Mar. 782 64,584 - 
Thoroughfare Swamp, N. C. 1976 31 Mar. 782 132,767 - 
Topsail Beach and None S Aug. 77' - - 
Surf City, N. C. 
Trent River, Basins and None 5 Aug. 77' - - 
Access Channels at 
New Bern, N. C. 
1. Deauthorized under authority of Sec. 12, PL 93.251. ed the Chief of Engineers under Sec. 208 of the 1954 Flood Control 
2. Deauthorized pursuant to the continuing authority provid- Act. 
ed the Chief of Engineers under Sec. 205 of the 1948 FC Act, as 4. Deauthorized pursuant to the continuing authority providamended. 
ed the Chief of Engineers under Sec. 107 of the R&H Act of 1960 
3. Deauthorized pursuant to the continuing authority provid- as amended. 
RECONNAISSANCE AND CONDITION SURVEYS 
Project 
Rollinson Channel, N. C. 
Waterway Connecting Pamlico Sound and Beaufort Harbor, N. C. 
November 1982 
January, May, June 1983 
6-29 
TABLE 6-H 
Date Survey Conducted

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1983 
NAVIGATION WORK UNDER SPECIAL AUTHORIZATION 
Navigation Activities Pursuant to Section 107, Public Law 80645 (preauthrisation~ 
TABLE 6-I 
Study Identification Fiscal Period Cost 
Atlantic Beach Channels 37,723 
Belhaven Harbor, N. C. 6,712 
Calico Creek, N. C. 2,035 
Harkers Island Harbor, N. C. 7,500 
Walters Slough, N. C. 609 
White Oak River, N. C. 3,414 
Wrights Creek, N. C.' 3,909 
1. Includes $3,392 reimbursement to revolving fund. 
6-30

TABLE 6-J DAMS AND RESERVOIRS 
See Miles Height Reservr Power Estimated 
Seets Project Name Nearest City River Above of Type Capacity Development Costre Cost Lands Total 
l Test Mouath Dam (ft) (aere4eet) (kilowatts) tie and Damages' 
20. Cape Fear B. Everett Jordan2 
River Basin. Howarde M 2.14 
N.C Ramdemaa 2 
Small reservcrs 
!l. Name River Fa&s2 
Basin. N.C. Whom MMs 
Bedsahows 
Baers M s 
Iltle B tnal 
addtkhor 
Was Ml 
8tasteestmrg 
Great Swamp 
Mack Creek 
Ayeock Swamp 
H~obere 
Orange 
80. Yadkia River W. Kerr 8eott, N.C 
Baia, NC.&S.C. 
8. Ronake River Jokn H. Kerr, Vs., and 
basi, Va. and NC.2 
N.C. Ppott, Va2 
Gastoa, Va. and N.C6 
Roasoke Rapids, NC 7 
Smith Mouptino, Vs.8 
Leesvie, Vs.9 
Taber, Vs. 
Meirose, Va. 
Randolph, Va. 
Stuart, Va. and N.C. 
Schooleld, Va. and N.C. 
Moncure, N.C. 
Carthage, N.C. 
Randleman, N.C. 
Falls, N.C. 
Wilsona MHlleN~.C . 
Kenly, N.C. 
Princeton, N.C. 
Kely,. N.C. 
Wilson, NC. 
Wso, NC. 
Stantembarg. N.C. 
Fremont. N.C. 
Wnon. NC. 
Fremnt, NC 
Durham, N.C. 
Durham, NC. 
Wkeebore. NC. 
Boydton, Va. 
Bassett, Va. 
Roanoke Rapids, N.C. 
Roanoke Rapids, N.C. 
Altavista. Vs. 
Altavista, Vs. 
Altavista. Va. 
Brookeel, V s. 
Chase City, Vs. 
Spray, N.C. 
Danvile, Vs. 
Haw 
Deep 
Deep 
Various 
Nese 
Neuse 
Uttle 
IUttle 
ULttle bfalo Creek 
Conteame Creek 
Contentse. Creek 
Tisnot Swamp 
Great Swamp 
B ac Creek 
Aycock Swamp 
Eno
i Pttle 
Yadkin-Pe Dee 
Ranomke 
Roanoke 
Roanoke 
Roanoke 
Roanoke 
Roanoke 
Roanoke 
RRooasnnookkee 
4.3 
55.0 
85.0 
404.0 
178.7 
860.2 
-j 
144.9 
137.0 
314.2 
293.7 
275.0 
262.9 
227.8 
297.2 
265.9 
112 E 778,000 
106 E 288,000 
110 E 108,000 
20 to 70+ E 928,000 
92 E 897,000 
81 CGE 201,000 
50 E 81,000 
58 E 86,000 
51 E 18,000 
68 E 119,000 
42 E 865.000 
86 E 48,000 
89 � E 18,000 
88 E 17,000 
87 E 7,000 
186 E 1238.000 
107 E 57,000 
148 E 158,000 
78,554,800 
18,874,000 
50,219,000 
73,042,000 
5,749,343 
58,445,200 
14.726,000 
54,781,000 
88.958,000 
5,860.657 
- Uo 
-o 
182,000,000' 
8,600,000' 
105,000,000' 
88.454,000 
162,000,000' 
13,.000,000 
9.300,000 
6,600,000 
1,100.000 
17,800,000 
6.700,000 
5,100,000 r 
1,800,000 
1,500.000 
550,000 
8,100,000 ,O 
9,500.000 , 
9,110,000 
144 CGE 2,806,000 204,000 67,529,000 24,521,000 92,050,000' 
220 CG1 1 249,800 14,000 13,988,000 1,157,000 15,090,000 
108 CG.E 4832,000 54,000 27,000,000 8.500.000 80,500,000 
75 CG 50.800 88,000 31,800,000 800,000 32.100.000 
244 CG 825,000 41,000 28,000,000 3,800,000 31,800,000 
95 CG.E 76.900 20,000 9.100.000 1,000.000 10.100.000 
54 CG 84.000 12,000 8,000,000 1,700,000 9,700,000 
110 CG,E 120,000 48,000 17.700,000 6.,000000 23,700.000" 
147 CG,E 850,000 48,000 22,100,000 4.700,000 26,800,000 
138 E 163.8,000 15,000 9.000,000 1.100.000 10.100,000 
126 CG,.E 248,000 80,000 27,800.000 6.400.000 368000.000 
1. Includes highway, railroad, and utility relocations. 
2. For detals,see individual report. 
S3.Includes $3 00,000 presently allocated to water supply to be reimbursed in the future 
by local interests. 
4. Includes $12,000,000 presently allocaeted to water supply and $20,000;000 recreation 
and fish and wiklife 
&E5x.l usive of trammiesion lines. 
SConstruction comapleted in 1968 by Virginia Electric and Power Co. 
7. bsed on modified plan developed in iscal year 1949. Construction completed June 
I1s by Virginia Electri and Power Co. 
8 Coastruction completed in Fetruary 1966 by Appalachian Power Co. 
9. Construction completed in June 1968 by Appalachian Power Co. 
10 . Includes cost of earth dam on Whipping Creek. 
11 Authorising legislation provided for earth dam concrete pgravity dam constructed. 
12. Includes $1,000,000 presently allocated to recreation and fish and wildlife. 
18. Includes $47,015,000 presently allocated to water supply and $8.190000 allocated to 
rceation. 
14 Reclassified to the deferred category 2 October 1960. 
Key 
E - Earth 
CG - Concrete Gravity

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1983 
TABLE 6-K 
FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION 
Flood Control Activities Pursut to Section 065, 
Public Law 858, 80th Congress, as ameaded 
iPreathorizationl 
Study Identification Fisecal Period Cost 
Columbia, N. C.' 4,776 
Great Coharie Creek, N. C. 76,218 
Grissett Swamp, Tabor City, N. C. 7,259 
Little Gunpowder Creek, N. C. 4,719 
Lower Creek, N. C. 3,957 
Silas Creek, N. C. 4,367 
Stuart, Va. 42,496 
1. Reimbursement to revolving fund. 
6-32

CHARLESTON, S.C., DISTRICT* 
The district comprises all of South Carolina (except local 
watersheds draining into the Savannah River). Due to a recent 
realignment work underway in western-central North 
Carolina, formerly in our district, will be carried through 
its current phase before being turned over to Wilmington. 
It embraces the drainage basins tributary to the Atlantic 
Ocean between Little River and Port Royal Sound, except 
watersheds of Mackey and Skull Creeks, and excluding 
Hilton Head Island. 
IMPROVEMENTS 
Beach Erosion Control 
1. Aquatic Plant Control, S.C ...................... 7-2 
2. Atlantic Intracoastal Waterway Between 
Norfolk, Va. and St. Johns River, Fla ........... 7-2 
3. Charleston Harbor, S.C ......................... 7-2 
4. Cooper River, Charleston Harbor, S.C ........... 7-3 
5. Cooper River Seismic Modification, 
Charleston Harbor, S.C ......................... 7-4 
6. Folly River, S.C ................................ 7-4 
7. Georgetown Harbor, S.C ........................ 7-4 
8. Jeremy Creek, S.C......... .............. 7-4 
9. Little River Inlet, N.C. and S.C. ............ :.... 7-5 
10. Murrells Inlet, S.C ............................. 7-5 
11. Shipyard River, S.C ............................ 7-6 
12. Town Creek, S.C ............................... 7-6 
13. Village Creek, S.C .............................. 7-6 
14. Reconnaissance and Condition Surveys...........7-6 
15. Other Authorized Navigation Projects ............ 7-6 
16. Navigation Work Under Special 
Authorization...................................7-7 
17. Hunting Island Beach, S.C ...................... 7-7 
Flood Control 
18. Cow Castle Creek, S.C .......................... 7-7 
19. Eagle Creek, S.C ............................... 7-7 
20. Wilson Branch, S.C ............................. 7-7 
21. Inspection of Completed Flood 
Control Projects ................................ 7-8 
22. Other Authorized Flood 
Control Projects ................................ 7-8 
23. Flood Control Work Under 
Special Authorization...........................7-8 
General Investigations 
24. Active Investigations............................7-8 
*All costs and financial statements for projects are listed at the end of this chapter. All other tables are referenced in text and 
also appear at the end of this chapter. 
7-1 
Navigation Page

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
1. AQUATIC PLANT CONTROL, S.C. 
Location. The project areas include navigable waters, 
tributary streams, connecting channels, and other allied 
waters in the State of South Carolina. 
Existing Projects. The project provides for control and 
progressive eradication of water hyacinth, alligator weed, 
Eurasian watermilfoil, and other noxious aquatic plant 
growth from navigable waters, tributary streams, connecting 
channels, and other allied waters of the United 
States, in combined interest of navigation, flood control, 
drainage, agriculture, fish and wildlife conservation, public 
health and related purposes, including continued research 
for development of most effective and economic control 
measures in cooperation with other Federal and State 
agencies in accordance with report of Chief of Engineers. 
The act provides that research and planning cost shall be 
borne fully by the United States. (See table at end of chapter 
for acts authorizing existing project.) 
Local Cooperation. Local interests must agree to hold the 
United States free from damages that may occur from 
operations performed in connection with this project and 
contribute 30 percent of the cost of field operations. The 
South Carolina Water Resources Commission is designated 
as the State's lead agency for aquatic plant mariagement 
and meets the local interest requirement of paying 30 percent 
of the cost of field operations. 
The project provides for a comprehensive plan of 
chemical, biological, and integrated control measures or 
managing noxious aquatic plants within the state waters of 
South Carolina. 
Operations and Results During Fiscal Year. Aquatic 
plants now infest approximately 40,000 acres, with the 
worst problems being in Lake Marion and Goose Creek 
Reservoir. The FY 83 treatment program included 1,477 
acres of brazilian elodea, water primrose, water hyacinth, 
and hydrilla. Flea beetles were distributed around the 
coastal region in an effort to establish populations which 
would spread out from the release sites to provide seasonal 
control of alligator weed. Approximately 18,000 beetles 
were released at ten sites supporting vigorous growths of 
alligator weed. 
Condition at End of Fiscal Year. The cost of field 
operations in FY 83 was $155,427 in Lake Marion and $4,445 
in Goose Creek Reservoir for a total of $159,872. The cost of 
planning and reconnaissance surveys was $31,102. 
2. ATLANTIC INTRACOASTAL WATERWAY 
BETWEEN NORFOLK, VA. AND ST. JOHNS 
RIVER, FLA. (CHARLESTON DISTRICT) 
Location. The project starts at Little River at the North 
Carolina-South Carolina state line and extends generally. 
south along the coast of South Carolina 62 miles to Winyah 
Bay; thence 63.5 miles to Charleston; thence 84.5 miles to 
and including Port Royal Sound; a total of 210 miles. (See 
National Ocean Survey Charts Nos. 11513, 11521, 11531, 
11534, and 11535.) 
Previous Projects. For further details see page 613 of 
Annual Report for 1932. 
Existing Project. The project provides for a waterway 
12 feet deep and not less than 90 feet wide with a branch 
channel of the same dimensions to McClellanville and construction 
of three bridges crossing the waterway in Horry 
County, South Carolina. (See table at end of chapter for acts 
authorizing existing project.) 
Local Cooperation. Requirements fully satisfied. 
Terminal Facilities. There are rail-water terminals at 
Georgetown, Charleston, Johns Island and Port Royal and 
numerous open-pile wharves mostly for shipping agricultural 
products, fish, oysters, pulpwood, wood products, and 
petroleum products. Marinas are located at convenient 
intervals along the waterway where limited supplies and 
repair facilities are available for both commercial vessels 
and pleasure craft. Facilities are considered adequate for 
existing commerce and recreation requirements. 
Operations and Results During Fiscal Year. Maintenance: 
Contract maintenance dredging was performed by 
the pipeline dredge Cherokee during June-September 1983 
from Charleston and Little River, South Carolina, removing 
1,421,130 cubic yards of material at a cost of $1,059,581. 
Mosquito abatement control contract costs were $39,009. 
Clearing and Snagging by the U.S. maintenance vessel Snell 
was performed at a cost of $262,125. Additional debris removed 
was under O&M contract at a cost of $60,950. Costs of 
$103,941 were incurred for contract dike assignment. Condition 
and operation studies, water control management, 
engineering, and design supervision and administration 
costs were $583,648. 
Condition at End of Fiscal Year. Existing project was 
completed in 1940; three bridges were completed in 1936. 
Federal costs of existing project to date have been $7,345,898 
for new work and $36,554,054 for maintenance, for a total of 
$43,899,942. 
3. CHARLESTON HARBOR, S.C. 
Location. The harbor is located on the coast of South 
Carolina about 15 miles south of the midpoint of the 
coastline, 50 miles southwest of Winyah Bay, S.C., and 80 
miles northeast of the mouth of Savannah River. (See 
National Ocean Survey Charts Nos. 11521 and 11524.) 
Previous Projects. For further details see page 1808 of 
Annual Report for 1915; page 579 of Annual Report for 
1926; and page 562 of Annual Report for 1938. 
Existing Project. The authorized project provides for a 
channel 35 feet deep with varying widths from the Atlantic 
Ocean to the mouth of Goose Creek, a total of 26.3 miles, 
together with a 35-foot depth by 500-foot width channel via 
Town Creek, and also, a 10-foot depth by 110-foot width 
channel on the Mount Pleasant side of the harbor into Shem 
Creek to U.S. Highway 17 Bridge, and a 30-foot anchorage 
basin in the lower harbor between Castle Pinckney and Fort 
Moultrie. A 40-foot channel estimated to cost $6,060,000 
(1960) was authorized to be executed when found necessary 
in the interests of national defense from the 40-foot contour 
in Atlantic Ocean to U.S. Naval Base. For further details see 
page 425 of Annual Report for 1962. The Phase I Design 
Memorandum stage of Advance Engineering and Design 
for deepening of the 35-foot channel to 40 feet (42 feet in the 
7-2

CHARLESTON, S.C., DISTRICT 
odean bar and entrance channel) from the 42-foot ocean 
contour to Goose Creek, a total distance of 26.9 miles, 
construction of one turning basin, modification of existing 
turning basins, deepening and modification of the 
anchorage basin, and deepening Shipyard River to 38 feet 
have been authorized. (See table at end of chapter for acts 
authorizing existing project.) 
Local cooperation. Local interests have fully complied 
with their responsibility to date but are experiencing 
difficulty in securing disposal areas for dredged material 
for continued future maintenance. 
Terminal facilities. Piers and slips extend for about one 
mile along the eastern waterfront of the City of Charleston 
with an additional mile of marginal wharves.The South 
Carolina State Ports Authority operateseight piers for fruit, 
wood, cold storage facilities and general cargo, a grain 
elevator and a beltline railway which serves the entire 
Cooper River waterfront. Modern facilities are also at 
wharves of seven major petroleum companies including 
storage tank farms. Modern facilities for marine repairs 
and servicing are available at Detyens Shipyard, located 
approximately 10 miles northeast of Charleston on the 
Wando River. The U.S. Navy Department has modern 
facilities for construction and maintenance of naval vessels 
including nuclear-powered submarines. Loading docks and 
storage areas for missile-carrying type vessels have also 
been constructed and are being operated by the U.S. Navy. 
For further details see Port Series No. 13, 1970, Corps of 
Engineers. 
Operations and Results During Fiscal Year. Maintenance: 
Contract maintenance dredging was performed in (a) 
the Upper and Lower Harbor by pipeline dredges the 
Florida, Dauntless, and Pullen during October-March 1983 
removing 1,407,294 cubic yards of material, (b) by the pipeline 
dredges Clinton, Pullen, and Enterprise in the Anchorage 
Basin during August-September 1983 removing 
913,488 cubic yards of material, and (c) on Shem Creek by 
the pipeline dredge Cherokee during June 1983 removing 
119,571 cubic yards resulting in an overall total dredging 
cost of $1,047,428. Government furnished materials for dike 
management cost $11,323. Contract dike management costs 
were $709,970. Costs of Riverine Utility Craft operation 
were $29,068. Condition and operation studies, water control 
management, engineering and design, supervision and 
administration costs were $912,353. 
Condition at end of fiscal year. Jetties protecting the 
entrance channel across the bar were completed in 1895. The 
existing project was completed in October 1962 except for 
the national defense portion. Federal costs under the 
existing project to date have been $3,328,349 for new work 
and $73,942,556 for maintenance, a total cost of $77,270,905. 
4. COOPER RIVER, CHARLESTON HARBOR, S.C. 
Location. Cooper River is located in Charleston and 
Berkeley Counties, S.C., and empties into the Atlantic Ocean 
at Charleston (See National Ocean Survey Charts Nos. 
11521 and 11524.) 
Existing project. The major cause of the shoaling 
problem in Charleston Harbor isthe diversion of fresh water 
from the Santee River through Pinopolis Dam into the salt 
water of Charleston Harbor, causing density currents which 
trap sediments resulting in a phenomenal rate of deposition. 
The most practical solution of the shoaling problem is to 
redivert most of the Santee River waters above Pinopolis 
Dam back into the lower Santee River through a canal 
beginning at Lake Moultrie and extending to the Santee 
River in the vicinity of St. Stephen, South Carolina. The 
project for Cooper River as authorized by the 1968 River and 
Harbor Act provides that the discharge through the existing 
Pinopolis Hydro Plant be reduced to a weekly average of 
3,000 cubic feet per second. This flow will not establish a 
density current in the harbor. The excess water then 
impounded in Lake Moultrie will be directed through a new 
canal above St. Stephen, South Carolina, to enter the Santee 
River at a point well below the Lake Marion Spillway 
(Wilson Dam). A new hydroelectric facility will be 
constructed on the new canal where the ground elevations 
decrease to become swampland adjacent to the Santee River. 
This plant will replace those features made less effective at 
Pinopolis through curtailment of flows. The average flow of 
12,600 cfs at the new powerplant, plus the proposed 3,000 cfs 
average release planned for Pinopolis, will approximate the 
existing average Pinopolis flow. The three generators at the 
new plant will be rated at 28,000 kilowatts each, for a total of 
84,000 kilowatts. In the interest of fish and wildlife 
resources of the area, the'plan provides for construction of a 
herring lift at the new powerhouse site and a relocated fish 
hatchery. 
Estimated cost of the project (1982) is $167,000,000, all 
Federal. (See table at end of chapter for acts authorizing 
existing project.) 
Local cooperation. None required. 
Operations and results during fiscal year. New Work: 
Funds were received for initiation of construction during 
FY 75. Costs during FY 83 were $44,587 for lands and 
damages, $1,877,835 for relocations, $8,367,923 for power 
plant, $348,843 for turbines, $186,154 for generators, $1,541 
for governors, $2,140 for main control switchboards, $18,956 
for microwave facilities, $1,752 for 480 V switchgear, $4,027 
for 15 KV switchgear, $3,897,546 for cooling water facilities 
- towers, $12,392 for cooling water facilities - 84" and 96" 
valves, $560,792 for cooling water facilities - pumps and 
motors, $215,156 for electrical work on cooling water 
towers, $5,017,003 for cooling water facilities - general 
construction, $6,433 for Powerhouse crane, $24,448 for 
intake crane contract, $3,685,650 for tailrace canal, $7,129 
for cultural resources preservation, $60,477 for permanent 
operating equipment and $1,502,595 for the fish lift, 
engineering and design and supervision and administration 
costs were $3,992,579. 
Condition at end of fiscal year. Preconstruction planning 
was completed at the end of FY 74. The General Design 
Memorandum was completed in January 1972 and work is 
proceeding on schedule on other phases of the project. Construction 
was initiated March 1977. The project is 90% 
complete. 
7-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
5. COOPER RIVER SEISMIC MODIFICATION 
Location. The Santee Cooper Project is located in 
Berkeley, Orangeburg, Calhoun, Sumter, and Clarendon 
Counties, South Carolina, about 50 miles north of 
Charleston, South Carolina. 
Existing Project. The Santee Cooper Project was 
constructed in the early 1940's using the latest state-of-theart 
design for that time. The project is currently licensed by 
the Federal Energy Regulatory Commission (FERC) as 
Project No. 199.The FERC requires that the project receive 
independent inspections at least once every five years. It was 
during the 1977 inspection that the seismic deficiency of 
both the West and North Dams were noted. This was 
confirmed again in their 1982 inspection. As a result of 
studying the possible consequences of the loss of both dams, 
the S.C. Congressional Delegation introduced legislation 
which was approved in the 1983 Supplemental Appropriation 
to provide $2 million for design and $22 million for 
construction of remedial measures. The design and 
construction responsibility was assigned to the U.S. Army 
Corps of Engineers. The Corps began in August 1983 to 
study various alternatives to provide a closure structure in 
the canal between the two lakes of the project and to provide 
remedial measures for the liquifiable foundation of the West 
Dam. 
Local Cooperation. None required. 
Conditions at end of fiscal year. At the end of FY 83 the 
initial enginnering evaluation of the project had just begun. 
6. FOLLY RIVER, S.C. 
Location. Folly River project begins in Folly River and 
Folly Creek north of the Town of Folly Beach and follows a 
southwesterly course into the Atlantic Ocean. (See National 
Ocean Survey Chart No. 11521.) 
Existing project. The project provides: an entrance 
channel, 11 feet deep by 100 feet wide extending from the 
Stono River one mile through the ocean bar; a channel 
within Folly River nine feet deep and 80 feet wide, extending 
three miles downstream from U.S. Highway 171 to the 
confluence of Folly and Stono Rivers; and a channel within 
Folly Creek nine feet deep by 80 feet wide extending three 
miles downstream from Highway 171 to the confluence with 
Folly River. 
Local cooperation. Requirements fully satisfied. 
Operations and results during fiscal year. Maintenance: 
No dredging was performed. Condition and operations, 
water control management, and engineering and design 
costs were $20,776. 
Conditions at end of fiscal year. The existing project 
was completed in FY 1979. Federal costs for the existing 
project to date have been $337,736 for new work and 
$337,156 for maintenance, a total of $674,892. 
7. GEORGETOWN HARBOR, S.C. 
Location. The harbor is located on the coast of South 
Carolina 50 miles northeast of Charleston Harbor and 90 
miles southwest of the entrance to Cape Fear River, North 
Carolina. (See National Ocean Survey Chart No. 11532.) 
Previous projects. For further details see page 1806 of 
Annual Report for 1915; page 549of Annual Report for 1938; 
and page 442 of Annual Report for 1944. 
Existing project. The authorizations provide for a 
channel 27 feet deep with varying widths of 400 feet to 600 
feet from the Atlantic Ocean to and including a turning 
basin at the U.S Highway 17 bridge over Sampit River, with 
a side channel 2,400 feet long and not less than 200 feet wide 
leading to a turning basin at the upper end of the built-up 
portion of the city waterfront, a total of 17.9 miles. The 
project also provides for the continued maintenance to a 
depth of 18 feet and a width of 400 feet for the bypassed 
portion of Sampit River opposite the City of Georgetown. 
(See table at end of chapter for acts authorizing existing 
project.) 
Local cooperation. Biannual dredging has been authorized, 
but local interests have not been able to provide the 
required disposal areas. 
Terminal facilities. Terminal facilities at the Port of 
Georgetown, suitable for oceangoing vessels, consist of one 
marginal concrete pier and one of creosoted-timber 
construction. For intracoastal waterway traffic there are a 
number of smaller wharves and landings along the 
Georgetown waterfront on the cold channel. For further 
details, see Port Series No. 13, 1970, Corps of Engineers. 
Operations and results during fiscal year. Maintenance: 
Disposal area dike management was performed by 
contracts at a cost of $277,387. Government furnished materials 
for dike management cost $36,229. The pipeline 
dredge Arlington performed maintenance dredging in the 
inner channel from October 1982 - November 1982 and the 
pipeline dredge Clinton performed maintenance dredging 
on the inner channel removing a total of 1,133,095 cubic 
yards of material at a cost of $881,602. Condition surveys, 
water control management, engineering and design, and 
supervision and administration costs were $294,943. 
Condition at end of fiscal year. The existing project was 
completed in 1951. The jetties were completed in 1903 - 04. 
Federal costs for the existing project to date have been 
$4,615, 903 for new work and $35,257,465 for maintenance, a 
total of $39,873,368. 
8. JEREMY CREEK 
Location. Jeremy Creek is located at McClellanville, S.C. 
approximately 40 miles northeast of Charleston and 20 miles 
southwest of Georgetown. (See National Ocean Survey 
Charts Nos. 11531 and 11518). 
7-4

CHARLESTON, S.C., DISTRICT 
Existing project. The dredging of Jeremy Creek or "Side 
Channel to McClellanville" was authorized as a part of the 
channel from Charleston to McClellanville (or part of what is 
now the Atlantic Intracoastal Waterway) by the River and 
Harbor Act of 2 March 1907. The project provides for a 
waterway 12 feet deep at mean low water and a width of not 
less than 90 feet. 
Local cooperation. Local requirements have been met 
by the S.C. Coastal Council. 
Terminal Facilities. There are three shrimping facilities, 
one oyster packing shed, a crabbing operation, an 
icehouse, a fuel dock, and a public launching ramp located 
on Jeremy Creek. The commercial facilities are privately 
owned, but are open to all on an equal basis. The existing 
facilities are considered adequate for present and near 
future commerce. There are areas along the east bluff shore 
available for the expansion of existing facilities or the 
construction of new ones. 
Operations and results during fiscal year. Engineering 
and design costs were $848. 
Conditions at end of fiscal year. Federal costs of 
existing project to date have been $49,297 for new work and 
$848 for maintenance for a total of $50,145. 
9. LITTLE RIVER, N.C. AND S.C. 
Location. The project is located near the North Carolina- 
South Carolina state line. Little River enters the Atlantic 
Ocean at Little River Inlet at the state line and affords the 
only connection between the Atlantic Intracoastal Waterway 
and the ocean along 68 miles of coastline from Shalotte, 
N.C. to Georgetown, S.C. (See National Ocean Survey Chart 
No. 11535.) 
Existing Project. The project provides for an entrance 
channel 12 by 300 feet across the ocean bar; thence a 10 by 
90-foot inner channel to the Atlantic Intracoastal Waterway. 
The entrance channel has been stabilized by jetties extending 
seaward 3,200 feet and 3,000 feet long on the north and 
south sides of the inlet, respectively. 
Emergency dredging on an annual basis was authorized 
by the Water Resources Act of 1974. Previous work was done 
under the authority of the River and Harbor Act of 1945, 
Section 3, P. L. 79-14. 
Estimated costs of the project (1981) are $18,300,000 
Federal cost and $2,790,000 non-Federal cost ($1,640,000 
contributed funds and $1,150,000 for lands). (See table at 
end of chapter for acts authorizing existing project.) 
Local cooperation. In a letter dated 28 December 1976, 
the Horry County (South Carolina) Planning and Promotion 
Commission gave assurances of cooperation. Since certain 
lands to be furnished by non-Federal interests lie in North 
Carolina, a letter dated 18 April 1977 has been supplied by 
the Brunswick County (North Carolina) Commissioners, 
agreeing to provide to the United States the necessary 
project lands lying in North Carolina. Local interests have 
met their responsibilities to date. 
Terminal facilities. There are eight marinas, numerous 
private docks, and several public boat ramps located in or 
near Little River. It is expected that existing facilities will 
expand and new ones will be added as demands for services 
exceed current capacity. 
Operations and results during fiscal year. New 
Work: Channels and canals cost $35,800, breakwaters 
and seawalls cost $4,944,211, supervision and administration 
costs were $152,214 and engineering and design costs 
were $168,771. 
Maintenance: No maintenance dredging was performed. 
Condition and operations studies, engineering and 
design, and water control management costs were $24,988. 
Conditions at end of fiscal year. Emergency dredging 
operations performed annually until the project is 
constructed. The initial construction contract was awarded 
14 January 1981. The project is 90% complete. 
10. MURRELLS INLET, S.C. 
Location. The project is located on the coast of South 
Carolina, in Georgetown County, about 13 miles southwest of 
the City of Myrtle Beach. The inlet is the ocean entrance 
through a barrier beach to several tidal streams in the 
Murrells Inlet-Garden City estuarine area. (See National 
Ocean Survey Chart No. 11535.) 
Existing project. The project provides for an entrance 
channel 12 by 300 feet across the seaward bar; thence a 10 by 
90-foot inner channel to a turning basin at the old Army 
crashboat dock. The entrance channel has been stabilized by 
ocean jetties extending seaward 3,445 feet and 3,319 feet on 
the north and south sides of the inlet, respectively. The recreational 
project includes a walkway on the south jetty with 
access road and parking area. Emergency dredging on an 
annual basis was authorized by the Water Resources Act of 
1974. Previous work was done under the authority of the 
River and Harbor Act of 1945, Section 3, P. L. 79-14. 
Estimated cost of the project (1979) was $12,700,000 
Federal cost and $2,380,000 non-Federal cost ($1,380,000 
contributed funds and $1,000.00 for lands). (See table at end 
of chapter for acts authorizing existing project.) 
Local cooperation. A letter of intent to provide local 
cooperation dated 4 November 1975 has been received for 
the Georgetown County Board of Commissioners. Local 
interests have met their responsibilities to date. 
Terminal facilities. There are five marinas and numerous 
private docks located about the Murrells Inlet 
Harbor. There are several public boat ramps in the area. 
Facilities are expected to be expanded and new ones added 
as demands for services outstrip capacity. 
Operations and results during fiscal year. New work: 
Expenditures for engineering and design and supervision 
and administration costs were $32,452. 
Maintenance: No maintenance dredging performed. 
Water control management costs and engineering and 
design costs were $99,637. 
7-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Conditions at end of fiscal year. The jetty construction 
contract was awarded 2 September 1977. The recreational 
facilities (comfort station and parking lot) contract was 
awarded 25 July 1980 and physically completed 7 August 
1981. 
11. SHIPYARD RIVER, S.C. 
Location. This waterway is a tidal tributary of Charleston 
Harbor, South Carolina. It has its source about one-half 
miles below the U.S. Naval Base, whence it flows southerly 
about three miles and empties into the Cooper River about 
three-fourths above Drum Island. (See National Ocean 
Survey Chart No. 11524.) 
Previous projects. For details, see page 610 of Annual 
Report for 1932 and page 463 of Annual Report for 1944. 
Existing project. The authorized project provides for a 
channel 30 feet deep from Cooper River to Macalloy, Inc.'s 
plant, including two turning basins, one opposite Gulf Oil 
Corporation Terminal and another at the upper end of 
project. (See table at end of chapter for acts authorizing 
existing project.) 
Local cooperation. Requirements fully satisfied. 
Terminal facilities. In the lower three-quarters of a mile 
of the channel are large marginal wharves of the Gulf Oil 
Corporation and Shipyard River Terminal Company. These 
wharves accommodate deep-draft, oceangoing vessels for 
handling petroleum products and fertilizer materials. In the 
upper channel is Macalloy, Inc.'s wharf for handling ores. 
For further details see Port Series No. 13, 1970, Corps of 
Engineers. 
Operations and results during fiscal year. Maintenance: 
Contract maintenance dredging costs were $42,871 
for work performed in FY 82. Condition and operations 
studies, water control management, supervision and administration, 
and engineering and design costs were 
$23,072. 
Condition at End of Fiscal Year. The existing project 
was completed in 1951. Federal costs under the existing 
project to date have been $487,824 for new work and 
$7,651,818 for maintenance, a total of $8,139,642. 
12. TOWN CREEK, S.C. 
Location. Town Creek Channel begins at the AIWW 
directly south of the Town of McClellanville in Charleston 
County, S.C. The channel follows Five Fathom Creek in a 
southerly direction to the Atlantic Ocean. (See National 
Ocean Survey Chart No. 11531.) 
Existing project. The project provides a channel 10 feet 
deep by 80 feet wide from the AIWW to the mouth of Five 
Fathom Creek, a distance of 6.2 miles. The project includes 
an entrance channel 12 feet deep by 100 feet wide across the 
ocean bar, a distance of 4.0 miles. (See table atendof chatper 
for acts authorizing existing projects.) 
Local cooperation. Requirements fully satisfied. 
Operations and results during fiscal year. Maintenance: 
Maintenance dredging was performed by the 
sidecaster dredge Schweizer during May - July removing 
70,776 cubic yards of material at a cost of $214,136. Engineering 
and design, supervision and administration, 
condition and operation studies, and water control 
management costs were $29,444. 
Condition at end of fiscal year. The existing project was 
completed in 1975. Federal costs under the existing project 
to date have been $219,521 for new work and $1,270,614 for 
maintenance, a total of $1,490,135. 
13. VILLAGE CREEK, S.C. 
Location. Village Creek is located on the northeastern 
end of St. Helena in Beaufort County, approximately 12 
miles from the Town of Beaufort. This creek which is about 
600 feet wide at its confluence with Morgan River and St. 
Helena Sound at a point 7 miles from the Atlantic Ocean, 
extends in a southwesterly direction adistance of 6.8 miles to 
its headwaters. (See National Ocean Survey Chart No. 
11513.) 
Existing project. The authorized project provided for a 
channel 8 feet deep and 80 feet wide from the mouth of 
Village Creek upstream to the Porpoise Fish Company 
Terminal for a distance of 2.2 miles. (See table at end of 
chapter for acts authorizing existing project.) 
Local cooperation. All items of local cooperation have 
been complied with except the present requirement that a 
diked disposal area be furnished. In the past, a deep water 
disposal area has been used and maybe used in the future. In 
environmental assessment of these areas is being prepared. 
If this assessment supports a negative determination for 
both areas, all items of cooperation will be fully satisfied. 
Operations and results during fiscal year. Maintenance: 
No maintenance dredging was performed. Water 
control management and condition operation studies costs 
were $3,171. 
Condition at end of fiscal year. The project was 
completed in April 1966. Federal costs under the existing 
project to date have been $26,500 for new work and $99,683 
for maintenance, a total of $126,183. 
14. RECONNAISSANCE AND CONDITION 
SURVEYS 
Cost of $3,620 were incurred for condition surveys as 
follows: 
Adams Creek, SC 
Ashley River, SC 
$3,100 
$ 520 
15. OTHER AUTHORIZED NAVIGATION 
REPORTS 
(See Table 7-C.) 
7-6

CHARLESTON, S.C., DISTRICT 
16. NAVIGATION WORK UNDER SPECIAL 
AUTHORIZATIONS 
Navigation Work under Special Authorization. Pursuant 
to Section 107, Public Law 86-645, as amended (Preauthorization) 
and Section 111, Public Law 90-433, as amended. 
(See Table 7-G.) 
Snagging and clearing for navigation (Sec. 3 of 1934 
River and Harbor Act, Public Law 14, 79th (Cong.) 
Engineering and design, surveys, and supervision and 
administration costs were $797 for Calabash Creek. 
17. HUNTING ISLAND BEACH, S.C. 
Location. Hunting Island is a state park comprising 
about 1,850 acres of wooded land located along the 
southeastern shore of South Carolina in Beaufort County, 16 
miles east of the Town of Beaufort, nine miles southwest of 
Edisto Beach, and 35 miles northeast of Tybee Roads at the 
mouth of Savannah River. (See National Ocean Survey 
Chart Nos. 11513 and 11517.) 
Existing project. The authorized project provides for 
periodic nourishment of about 10,000 feet of beach on the 
northern part of the island with initial placement of 750,000 
cubic yards of sand for advance nourishment, and construction 
of one pre-stressed concrete groin at the north end 
of the island. Federal participation in periodic nourishment 
is limited to a period of 15 years. (See table at end of chapter 
for acts authorizing existing project.) 
. 
Local cooperation. All requirements of local cooperation 
have been met by the State of South Carolina and accepted 
by the Chief of Engineers. The State has contributed 30 
percent of construction costs. The initial construction was 
completed in June 1969, and two additional periodic 
nourishments (construction) were completed in August 1971 
and June 1975. 
Operations and results during fiscal year.Engineering 
and design costs were $1,969. 
Condition at end of fiscal year. The first three 
nourishments were designed to restore the feeder beach to 
the condition prevailing after the initial beach nourishment. 
The third nourishment was completed 30 April 1980. 
18. COW CASTLE CREEK, S.C. 
Location. Cow Castle Creek is located entirely within the 
limits of Orangeburg County, South Carolina. The creek 
flows from its headwaters in the City of Orangeburg to its 
confluence with Four Hole Swamp. 
Existing project. The authorized project consists of 
clearing and snagging approximately 8,000 feet of the 
channel located near Bowman, S.C. The project was 
authorized under general authority contained in Section 208 
of the Flood Control Act of 1954, as amended. 
Local cooperation. Local interest must provide lands, 
easements, and rights-of-way; clean-out approximately 1.7 
miles of the Even Branch tributary to Bowman; hold and 
save the United States free from damages; maintain the 
project after completion; prevent future encroachments; 
notify affected interests annually that improvements will 
not provide complete flood protection; and prevent unwise 
future floodplain development. 
Operations and results during fiscal year. Contract 
was awarded on 22 September in the amount of $178,000. 
Scheduled completion date is 3 April 1984. Total engineering 
and design costs were $34,616. 
Condition at the end of the FY. Contractor awaiting 
notice-to-proceed. 
19. EAGLE CREEK, S.C. 
Location. The Eagle Creek project is located entirely 
within the limits of Dorchester County, South Carolina. The 
creek flows from its headwaters in the subdivisions near 
Summerville to the Ashley River. 
Existing project. The authorized project consists of 
clearing and channel excavation of approximately four 
miles of Chandler Bridge Creek and Eagle Creek. The 
project was authorized under general authority contained in 
Section 205 fo the 1948 Flood Control Act, as amended. 
Local cooperation. Local interests must (a) provide 
lands, easements, rights-of-way, utility relocations and alterations 
and highway bridge alterations necessary for 
construction; (b) hold and save the United States free from 
damages; (c) maintain and operate the project after completion; 
prevent future encroachments; (d) notify affected 
interests annually that improvement will not provide complete 
flood protection; and prevent unwise future floodplain 
development. 
Operations and results during Fiscal Year.Contract 
was awarded on 28 September 1983 in the amount of 
$1,245,063. Construction period is 480 calendar days. Engineering 
and design costs were $12,222. 
Condition at the end of the FY. Contractor awaiting 
notice-to-proceed. 
20. WILSON BRANCH, S.C. 
Location. Wilson Branch is located almost entirely 
within the corporate limits of the Town of Cheraw in 
Chesterfield County, South Carolina. The creek flows from 
its headwaters in a residential area to its confluence with 
Huckleberry Branch, then to the Pee Dee River approximately 
1/4 miles away. 
Existing Project. The authorized project consists of a 
"non-structural" solution of removing six houses from the 
floodplain. The project was authorized under general 
authority contained in Section 205 of the 1948 Flood Control 
Act, as amended. 
Local cooperation. Local interest must provide a cash or 
in-kind contribution equal to 20% of the project first cost; 
hold and save the United States free frdm damages; maintain 
the project after completion; prevent future encroachments; 
notify affected interests annually that improvements 
will not provide complete flood protection; and prevent unwise 
future floodplain development. 
Operations and results during Fiscal Year. Three of 
the six houses were purchased (one was purchased 
previously), the residents of the four houses were relocated. 
7-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
the four houses were auctioned off, and preparations were 
made by the bidders to remove the four structures from the 
floodplain. Funds in the amount of $114,700 were expended 
during the fiscal year toward the Wilson Branch Project. 
Condition at the end of the Fiscal Year. Four of the six 
houses have been purchased and auctioned for relocation. 
The residents of the four houses have been relocated. 
21. INSPECTION OF COMPLETED FLOOD 
CONTROL PROJECTS 
To determine the extent of compliance with approved 
regulations for maintenance and operation, inspections 
were made of the following projects during the period: 
Cowpens Swamp, S.C., Crabtree Swamp, S.C., Simpson 
Creek, S.C., Todd Swamp, S.C., Buck Creek, S.C. and N.C., 
Edisto River, S.C., Sawmill Branch, S.C., Shot Pouch Creek, 
S.C., Turkey Creek, S.C., Kingstree Branch, S.C. Responsible 
local officials were advised of inadequacies in 
maintenance and operation on local flood protection works 
when appropriate. Cost for the period was $13,434. 
22. OTHER AUTHORIZED FLOOD CONTROL 
PROJECTS 
(See Table 7-E.) 
23. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood Control Activities Pursuant to Sect. 205, Public 
Law 858, 80th Congress, as amended (Preauthorization). 
(See Table 7-D) 
Emergency Flood Control Activities - Repair, Flood 
Fighting and Rescue Work (Public Law 99, 84th 
Congress, and Antecedent Legislation). 
Federal costs for FY 1983 were $151,818 for the Flood 
Control and Coastal Emergencies and $51,957 for the 
National Emergency Preparedness Program. 
General Investigations 
24. ACTIVE INVESTIGATIONS 
See Table 7-F which covers: Surveys, Collections, and 
Study of Basic Data, and Research and Development 
Activities. 
7-8

CHARLESTON, S.C., DISTRICT 
TABLE 7-A 
COST AND FINANCIAL STATEMENT DURING PERIOD 
See 
Sect. 'otal Cost to 
in Text Project Funding FY 80 FY 81 FY 82 FY 83 Sept. 30, 1983 
1 Aquatic Plant New Work: 
Control, SC 
(Regular Funds) 
(Contributed Funds) 
2 Atlantic Intracoastal 
Waterway 
Between Norfolk, 
Va. and the St. 
Johns River, Fla.. 
3 Charleston Harbor, 
SC 
4 Cooper River, 
Charleston Harbor, 
SC 
5 Cooper River 
Seismic 
Modification, 
Chas. Hbr 
6 Folly River, SC 
7 Georgetown Harbor, 
SC 
8 Jeremy Creek 
McClellanville, 
SC 
9 Little River Inlet, 
NC and SC 
(Regular Funds) 
Approp. 
Cost 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
45,000 
49,174 
3,435 
101,900 
128,391 
80,605 
78,122 
186,000 
190,974 
675,605 
484,597 
52,028 
52,028 
- - - - 7,455,3781 
- - - - 7,455,3781 
2,035,000 2,320,000 2,320,000 1,742,000 36,788,3042 
2,435,663 2,261,584 1,973,663 2,109,254 36,623,4762 
- - - 26,563,000 10,165,5643 
17 - - 29,835,958 10,165,5643 
7,375,299 4,236,000 4,498,000 3,921,200 76,642.0874 
7,673,599 3,479,697 4,215,123 2,710,142 74,344,5454 
32,370,000 40,242,000 33,780,000 26,563,000 161,602,583 
32,382,778 38,213,576 31,588,183 29,835,958 160,536,430 
295,000 
85,345 
100,000 
39,575 
-18,000 
54,685 
-1,191 
176,000 157,000 
0 54,012 262,368 
152,000 
20,776 
295,000 
85,345 
100,000 
39,575 
337,736 
337,736 
485,000 
337,156 
- - - - 7,061,7555 
- - - - 7,061,7555 
2,375,000 2,596,000 4,577,805 1,315,400 36,010,2806 
2,851,550 2,576,534 3,868,776 1,490,161 35,372,0216 
26,000 
21,352 
23,987 
27,945 
3,000 
848 
124,000 
160,367 
188,000 
299,050 
49,987 
49,297 
3,000 
848 
2,480,000 7,120,000 5,800,000 16,739,428 
2,473,240 7,112,543 5,300,996 16,203,219 
200,000 115,000 
184,217 148,798 
585,000 
24,988 
2,240,124 
1,657,831 
7-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 7-A (Continued) 
COST AND FINANCIAL STATEMENT DURING PERIOD 
See 
.Sect. Total Cost to 
in Text Project Funding FY 80 FY 81 FY 82 FY 83 Sept. 30, 1983 
(Contributed Funds) 
10 Murrells Inlet, SC 
(Regular Funds) 
(Contributed Funds) 
11 Shipyard River, 
SC 
12 Town Creek, SC 
(Regular Funds) 
(Contributed Funds) 
13 Village Creek, SC 
17 Hunting Island 
Beach, SC 
(Regular Funds) 
(Contributed Funds) 
18 Cow Castle Creek, SC 
19 Eagle Creek, SC 
20 Wilson Branch, SC 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Apptop. 
Cost 
New Work: 
Approp. 
Cost 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
3,075,000 
2,778,842 
660,000 
660,000 
107 
450,000 400,000 
0 849,999 
370,000 -175,000 
1,308,457 27,346 
- 0 
154,928 0 
279,000 
128,593 
405,000 442,000 430,000 
398,634 446,475 254,613 
640,000 
499,994 
32,452
0 
99,637 
316,000 
65,943 
110,000 253,000 218,000 280,000 
212,909 235,056 166,443 243,580 
200,000 
1,293,280 
100,000 
612,000 
75,000 
79,038 
31,372 
30,947 
16,000 
5,738 
12,660 
38,000 
21,583 
30,811 
30,566 
0
1 
-6,300 
3,171 
0 0 
5,999 1,969 
0 - 
51;500 
25,568 
50,000 
64,846 
23,600 
34,616 
258,000 
12,222 
100,000 293,000 
73,614 114,700 
1,590,000 
1,349,993 
13,419,240 
13,357,810 
1,380,000 
1,274,923 
980,5697 
929,7997 
491,9748 
491,9748 
8,080,192 
7,651,818 
219,521 
219,521 
8,600 
8,600 
1,373,000 
1,270,614 
26,5009 
26,5009 
100,473 
99,683 
2,881,117 
2,868,681 
1,249,336 
1,249,336 
75,100 
61,184 
1,475,372 
222,514 
423,811 
218,881 
'Includes $109,490 for new work for previous project. 
2Includes $69,422 for maintenance of previous projects. 
3Includes $6,586,455 for previous projects. $3,328,349 for 
the existing project, and $250,760 for Phase I to deepen 
harbor. 
4Includes $401,989 for maintenance of previous projects. 
In addition, $600 for maintenance expended from contributed 
funds. 
5Includes $2,445,852 for new work for previous projects. 
6Includes $114,556 for maintenance of previous projects. 
7Includes $67,000 accomplished under authority of 
Section 3, P.L. 79-11 incurred through FY 73. 
"Includes $4,150 for new work on previous projects. 
9Excludes $3,000 in FY 69 for reconnaissance study to 
determine economic feasibility of modifying. the existing 
project. 
7-10 
--

CHARLESTON, S.C., DISTRICT 
TABLE 7-B 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
R&H Act of Oct. 27, 1965 
R&H Act of Sep. 19, 1890 
R&H Act of June 13, 1902 
R&H Act of Mar. 2, 1907 
R&H Act of Mar. 2, 1919 
R&H Act of Mar. 3, 1925 
R&H Act of Mar. 3, 1925 
R&H Act of July 3, 1930 
R&H Act of Aug. 30, 1935' 
R&H Act of Aug. 30, 19352 
R&H Act of Aug. 30, 19352 
R&H Act of Aug. 26, 1937 
R&H Act of Mar. 2, 1945 
R&H Act of June 18, 1978 
R&H Act of Aug. 8, 1917 
R&H Act of July 18, 1918 
R&H Act of Jan. 21, 1927 
AQUATIC PLANT CONTROL (See Section 1 of 
text.) 
Provides for control and progressive eradication 
of water hyacinth, alligatorweed, Eurasian watermilfoil 
and other obnoxious aquatic plant growths 
from navigable waters, tributary streams, connecting 
channels, and other allied waters of the U.S., in combined 
interest of navigation, flood control, drainage, 
agriculture, fish and wildlife conservation, public 
health and related purposes, including continued research 
for development of most effective and economic 
control measures in cooperation with other Federal 
and state agencies. 
ATLANTIC INTRACOASTAL WATERWAY 
BETWEEN NORFOLK, VA., AND ST. JOHNS 
RIVER, FLA. (See Section 2 of text.) 
Channel from Minim Creek to Winyah Bay. 
Channel from Charleston to a point opposite 
McClellanville. 
Branch channel to McClellanville. 
Extending the channel to Minim Creek, thence through 
the Esterville-Minim Canal to Winyah Bay. 
Cut across the Santee Delta at Four Mile Creek. 
Widening and deepening the waterway from Charleston 
to Beaufort. 
A waterway 8 feet deep and 75 feet wide from Cape 
Fear River to Winyah Bay. 
Construction of bridges across the waterway in Horry 
County, S.C. 
Cutoff between Ashepoo and Coosaw Rivers. 
Enlarging the canal from Winyah Bay to Charleston 
including the branch channel to McClellanville, to depth 
of 10 feet and bottom width of 90 feet. 
Increasing dimensions of waterway to 12 feet deep 
90 feet wide. 
Anchorage Basin 125 feet wide, 335 feet long, 12 feet 
deep, near Myrtle Beach, S.C. 4 
CHARLESTON HARBOR, S.C. (See Section 3 of 
text.) 
2 jetties.5 
Increase in depth to 30 feet width of 500 feet between 
the jetties and 1,000 feet seaward thereof. 
The 40-foot channel to the Naval Base. Act provided that 
the 40-foot channel should not be undertaken "until the 
the proposed new drydocks at this navy yard, carrying a 
depth of 40 feet of water over the blocks, has been 
authorized." This dock was authorized in the Naval 
Appropriations Act approved July 1, 1918 (40 Stat. L 
723). 
A 30-foot channel from the sea to Goose Creek via Cooper 
River, together with a 30-foot channel through Town 
Creek for commercial purposes. The act also provided 
that the 40-foot channel be prosecuted only as found 
necessary for national defense. 
Sec. 302, 1965 River and 
Harbor Act (H.D. 251, 89th 
Cong. 1st sess.) 
Annual Report, 1889, p 1184. 
H.D. 84, 56th Cong., 1st sess. 
and Annual Report, 1900, p. 
1908. 
Annual Report 1903, p. 1133. 
H.D. 178, 63rd Cong., 1st sess. 
H.D. 237, 68th Cong., 1st sess. 
S.D. 178, 68th Cong., 2nd sess. 
H.D. 41, 71st Cong., 1st sess. 
Rivers and Harbors Committee 
Doc. 14, 72nd Cong., 1st sess. 
H.D. 129, 72nd Cong., 1st sess. 
Rivers and Harbors Committee 
Doc. 11, 72nd Cong. 1st sess. 
Rivers and Harbors Committee, 
Doc. 6, 75th Cong., 1st sess. 3 
H.D. 327, 76th Cong., 1st sess. 
Annual Report 1878, pp. 553- 
572. 
H.D. 288, 62nd Cong., 2nd sess. 
H.D. 1946, 64th Cong., 2nd 
sess., pt. 1, pp. 21-29,57,58, and 
61-63. 
H.D. 249, 69th Cong., 1st sess. 
7-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 7-B (Continued) 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
R&H Act of Oct. 17, 1940 
R&H Act of Mar. 2, 1945 
R&H Act of Sep. 3, 1954 
R&H Act of July 14, 1960 
Water Resources Development 
Act of Oct. 22, 1976 
R&H Act of Aug. 13, 1968 
P.L. 98-63, 1983 
Authorized by Chief of Engrs. 
on Dec. 23, 1977 under authority 
of Section 107 R&H Act of 
1960, as amended. 
R&H Act of Aug. 5, 1886 
R&H Act of June 25, 1910 
R&H Act of Mar. 2, 1945 
R&H Act of June 30, 1948 
R&H Act of Mar. 2, 1907 
The 35-foot channel depth from the sea to the head of the 
project via Cooper River and Town Creek, also a channel 
in Shem Creek to Mount Pleasant, 110 feet wide and 10 
feet deep, including a turning basin at the upper end. 
An anchorage area 30 feet deep in the water area between 
Castle Pinckney and Fort Moultrie.6 
Deepen the 30-foot channel north and east of Drum 
Island to 35 feet. 
Shem Creek Channel modified by extending 1,150 feet 
upstream and downstream from mouth to Atlantic 
Intracoastal Waterway. 
Project is authorized for the Phase I design memorandum 
stage of Advance Engineering and Design. 
COOPER RIVER, CHARLESTON, S.C. (ST. 
STEPHEN PROJECT) (See Section 4 of text.) 
Redivert most of the Santee River waters above 
Pinopolis dam into the lower Santee River through a 
canal beginning at Lake Moultrie and extending to the 
Santee River in the vicinity of St. Stephen, South 
Carolina. 
COOPER RIVER SEISMIC MODIFICATION, 
CHARLESTON HARBOR, S.C. (See Section 5 of 
text.) 
Install a closure structure in the diversion canal between 
Lake Marion and Lake Moultrie and construct such 
measures as necessary to improve the seismic stability of 
the Pinopolis West Dam on the Cooper River. 
FOLLY RIVER, S.C. (See Section 6 of text.) 
Consists of stable all-tide channel 9 feet deep and 80 
feet wide in Folly River and an entrance channel at Stono 
Inlet 100 feet wide and 11 feet deep. 
GEORGETOWN HARBOR, S.C. (See Section 7 of 
text.) 
Jetties and earthen dike to protect south jetty. 
Previous project channel dimensions and training wall. 
27-foot channel from ocean, including a turning basin 
in Sampit River. 
Cutoff and side channel in Sampit River. 
JEREMY CREEK, McCLELLANVILLE, S.C. (See 
Section 8 of text.) 
To provide a waterway 12 feet deep at mean low water 
and a width of not less than 90 feet. 
H.D. 259, 76th Cong., 1st sess. 
H.D. 156, 77th Cong., 1st sess. 
S.D. 136, 83rd Cong., 2nd sess.7 
H.D. 35, 86th Cong., 1st sess. 
H.D. 436, 94th Cong., 2nd sess. 
River and Harbor Act of 1968 
S.D. 88, 90th Cong. 
H.D. 3069, 98th Cong., 1st sess. 
Detailed Project Report 
H. Ex. Doc. 258, 48th Cong., 
2nd sess, and Annual Report 
1885, pp. 1154-1170, and H. Ex. 
Doc. 117. 50th Cong., 2nd sess, 
and Annual Report 1889, pp. 
1110-1111. 
H.D. 395, 58th Cong., 2nd sess. 
and Annual Report 1904, pp. 
1591-1605. 
H.D. 211, 76th Cong., 1st sess. 
H.D. 21, 81st Cong., 1st sess. 
Detailed Project Report 
7-12

CHARLESTON, S.C., DISTRICT 
TABLE 7-B (Continued) 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
R&H Act of 1945, Sec. 3 
Auth. by Senate Public Works 
Comm. and the House of Public 
Work Comm. on Oct. 12, 1972, 
under auth. of Sec. 201, PL 
89-298, 1965 FC Act. 
Water Resources Development 
Act of 1974. 
R&H Act of 1945, Sec. 3 
Auth. by the House Committee 
on Public Works on Nov. 10, 
1971 and the Senate Committee 
on Public Works on Nov. 18, 
1971, under auth. or Sec. 201, 
PL 89-298, 1965 FC Act. 
Water Resources Development 
Act of 1974. 
R&H Act of July 25, 1912 
R&H Act of Mar. 3, 1925 
R&H Act of July 3, 1930 
R&H Act of Aug. 30, 1935 
R&H Act of Aug. 26, 19378 
R&H Act of Mar. 2, 1945 
Auth. by Chief of Engrs. 
on Feb. 12, 1974 under Auth. 
of Sec. 107 of R&H Act of 
R&H Act of 1960, as 
amended 
LITTLE RIVER INLET, N.C. AND S.C. (See 
Section 9 of text.) 
Provides for an entrance channel 12 feet by 300 feet 
across the ocean bar; thence 10 feet by 90-foot inner 
channel to the Atlantic Intracoastal Waterway 
Authorized emergency dredging operations as the 
Chief of Engineers determines necessary to maintain 
channel depths sufficient to permit free and safe 
movement of vessels until sich time as the authorized 
project is constructed. 
MURRELLS INLET, S.C. (See Section 10 of text.) 
Provides for an entrance channel 12 feet by 300 feet 
across the seaward bar, thence 10-foot by 90-foot inner 
channel to a turning basin at the old Army crash boat 
dock. 
Authorized emergency dredging operations as the 
Chief of Engineers determines necessary to maintain 
channel depths sufficient to permit free and safe 
movement of vessels until such time as the authorized 
project is constructed. 
SHIPYARD RIVER, S.C. (See Section 11 of text) 
Channel depth of 15 feet and width of 100 feet. 
Deepening of channel to 18 feet from deep water in 
Cooper River upstream 1-1/16 miles. 
Channel depths of 12 and 20 feet. 
28-foot from Cooper River to Gulf Oil Corp's terminal, 
and the deepening of the channel above that point to 20 
feet from the depth of 12 above that point to 20 feet from 
from the depth of 12 feet previously authorized without 
local cooperation. 
Enlargement of the channel to a depth of 30 feet and a 
width of 200 feet up to the Gulf Oil Corp's terminal, with 
a turning basin 30 feet deep at the latter point. 
Extension of the existing 30-foot channel to vicinity 
of the Pittsburg Metallurgical Co. plant, with a turning 
basin at the upper end. 
TOWN CREEK, S.C. (See Section 12 of text.) 
An entrance channel 12 feet deep by 100 feet wide 
across the ocean bar a distance of 4.0 miles and a 
channel 10 feet deep by 80 feet wide from the mouth 
of Five Fathom Creek to the AIWW, a distance of 6.2 
miles. 
P.L. 79-14 
H.D. 362, 92nd Cong. 
H.D. 10203, 93rd Cong. 2nd 
sess. 
P.L. 79-14 
H.D. 137, 92nd Cong. 
H.D. 10203, 93rd Cong. 
2nd sess. 
S.C. 350, 62nd Cong., 2nd sess. 
H.D. 288, 68th Cong., 1st sess. 
Rivers & Harbors Committee 
Doc. 13, 71st Cong., 2nd sess. 
Rivers and Harbors Committee 
Committee Doc. 43, 73rd Cong., 
2nd sess. 
Rivers and Harbors Committee 
Doc. 38, 75th Cong., 1st sess. 
H.D. 93, 79th Cong., 1st sess. 
Detailed Project Report. 
7-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 7-B (Continued) 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
VILLAGE CREEK, S.C. (See Section 13 of text.) 
Auth. on Nov. 24, 1965 by A channel 8 feet deep and 80 feet wide from the mouth Detailed Project Report. 
Chief of Engrs. under of Village Creek upstream to Porpoise Fish Company 
the Auth. of Sec. 107 of terminal for a distance of 2.2 miles. 
R&H Act of 1960, as amended. 
HUNTING ISLAND BEACH, S.C. (See Section 
17 of text.) 
R&H Act of Oct. 27, 1965 Provides for periodic nourishment for about 10.000 H.D. 323, 88th Cong., 2nd sess. 9 
feet of beach on the northern part of the island with 
initial placement of 75,000 cubic yards of sand for 
for advance nourishment, and construction of one prestressed 
concrete groin at the north end of the island. 
Water Resources Development Extended length of periodic nourishment from 10 to P.L. 94-587 
Act of Oct. 22, 1976 15 years. 
COW CASTLE CREEK, S.C. (See Section 18 
of text.) 
Auth. under Sec. 208 of the Provides for clearing and snagging approximately Reconnaissance Report. 
1954 Flood Control Act, as 8,000 feet of channel. 
amended. 
EAGLE CREEK, S.C. (See Section 19 of text.) 
Auth. under Sec. 205 of the Provides for clearing and channel excavation of 4 miles Detailed Project Report. 
1948 Flood Control Act, as of Chandler Bridge Creek and Eagle Creek. 
amended. 
WILSON BRANCH, S.C. (See Section 20 of text.) 
Auth. under Sec. 205 of the Provides for nonstructural solution of removing 6 Detailed Project Report. 
1948 Flood Control Act, as homes from the flood plain. 
amended. 
'Included in Public Works Administration Program September 
6, 1933. 
2Included in Emergency Relief Administration Program 
May 28, 1935. 
3Contains latest published maps. 
4Inactive. 
5Completed under previous projects. 
6For national defense. 
7Contains latest published maps. 
8Included in Emergency Relief Administration Program 
May 28, 1935. 
9Contains latest published maps. 
7-14

CHARLESTON, S.C., DISTRICT 
TABLE 7-C 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY FY 1983 
OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last 
Full Report 
See Annual Operation & 
Project Report for Construction Maintenance 
Adams Creek, S.C. 1 1978 $ 125,697 $ 13,908 
Aquatic Plant Control, N.C. and S.C. 1 1968 379,680- 
Archers Creek, S.C. 1914 20,646 - 
Ashley River, S.C. 1 1955 260,996 525,142 
Edisto River, S.C. 1 2 1938 33,103 900 
Great Pee Dee River, S.C. 1 8 1950 188,712 269,673 
Lynches River and Clark Creek, S.C. 1 1982 9,500 84,170 
Mingo Creek, S.C. 1 2 1950 29,050 7,150 
Port Royal Harbor, S.C. 1 1982 1,706,100 5,891,927 
Salkahatchie River, S.C.1 2 4 1896 15,841 -. 
Santee River, N.C. & S.C. 1 1950 99,750 178,544 
Waccamaw River, N.C. & S.C. 1 1978 262,814 277,700 
Wateree River, S.C. 1 1940 60,000 151,784 
1Completed. 'Abandonment recommended in 1926 (H.D., 69th Cong., 
2No commerce reported. 1st session). 
8Curtailment recommended in 1926 (H.D. 467, 69th Cong., 5Pilot Program. 
1st session). 
TABLE 7-D 
FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Preauthorization studies (See Section 23 of Text) 
STUDY IDENTIFICATION SECTION FISCAL YEAR COSTS 
Bear Swamp, Lakeview, N.C. 205 $22,974 
Congaree River, Cayce, S.C. 205 54,766 
Crabtee Swamp Canal, S.C. 205 22,928 
Cramerton, S. Fork, Catawba, N.C. 205 11,209 
Goose Creek, Berkeley County, S.C. 205 52,537 
Langston Creek, S.C. 205 15,671 
Scotts Creek, N.C. 205 25,532 
Smiths Branch, S.C. 205 7,262 
Socastee Creek, Horry County, S.C. 205 66,203 
Stoop Creek, S.C. 205 5,888 
7-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 7-E 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY FY 1983 
OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last 
Full Report 
See Annual Operation & 
Project Report For Construction Maintenance 
Buck Creek, N.C. & S.C. 1 2 1970 $298,167 - 
Cowpens Swamp, S.C. 1 2 1960 18,679 - 
Crabtree Swamp, S.C. 1 2 1969 97,000 - 
Edisto River, S.C. 1 3 1947 6,379 - 
Edisto River, North Fork, S.C. 1 2 1969 127,660 - 
Edisto River, Vicinity Canadays Landing, S.C. 1 2 1958 3,160 - 
Leith's Creek, S.C. 1 2 5 1982 430,951 - 
Kingstree Branch, Williamsburg County, S.C. 1 1978 247,242 - 
Reddies River Lake 1980 985,800 - 
Reedy River, S.C. 1 3 1974 4,500 - 
Roaring River, Wilkes County, N.C. 1 4 1978 370,000 - 
Saluda River, S.C. 1 2 1963 99,000 - 
Sawmill Branch, S.C. 1 2 1971 248,605 - 
Shot Pouch Creek, Sumter Co., S.C. 1 2 1971 77,400 - 
Simpson Creek, S.C. 1 2 1957 81,000 - 
Todd Swamp, S.C. 1 2 1964 29,000 - 
Turkey Creek, Sumter County, S.C. 1 2 1974 319,669 - 
'Authorized by Chief of Engineers. 
2Completed. 
3Discontinued due to lack of interest. 
4Phase I only. 
5Revised. 
7-16

CHARLESTON, S.C., DISTRICT 
TABLE 7-F 
ACTIVE GENERAL INVESTIGATIONS 
ITEM FISCAL YEAR COSTS 
NAVIGATION (110) 
Charleston Harbor, S.C. $ 41,631 
Georgetown Harbor, S.C. 504 
FLOOD DAMAGE PREVENTION STUDIES (CATEGORY 120) 
Gills Creek, S.C. $309,565 
Little Pee Dee & Pee Dee Rivers, N.C. & S.C. 51,411 
Lumber River, N.C. & S.C. 139,984 
Sugar Creek Basin, N.C. & S.C. 13,916 
Waccamaw River Basin, N.C. & S.C. 56 
SHORELINE PROTECTION STUDIES (CATEGORY 130) 
Myrtle Beach, S.C. $111,893 
COORDINATION STUDIES WITH OTHER AGENCIES (CATEGORY 180) 
Department of Agriculture, SCS $ 3,000 
Planning Assistance to States 26,407 
National Wildlife & Scenic Rivers System 28 
SUPPLEMENTAL PRE-AUTHORIZATION STUDIES (CATEGORY 190) 
Nay. Channel & Harbors $ 290 
TOTAL (CATEGORY 100) $698,685 
COLLECTION AND STUDY OF BASIC DATA (CATEGORY 200) 
Inspection of Dams (Category 230) $ 401 
FLOOD PLAIN MGMT SERVICES (CATEGORY 250) $145,903 
HYDROLOGIC STUDIES (CATEGORY 260) 
Hydrologic Studies 3,616 
TOTAL (CATEGORY 200) 149,920 
TOTAL GENERAL INVESTIGATIONS $848,605 
TABLE 7-G
NAVIGATION WORK UNDER SPECIALAUTHORIZATIONS 
STUDY IDENTIFICATIONS SECTION FISCAL YEAR COSTS 
Calabash Creek, N.C. 107 $35,880 
Jeremy Creek, S.C. 107 689 
Charleston Harbor, S.C. 111 695 
7-17

SAVANNAH, GA, DISTRICT* 
The District comprises drainage basins tributary to 
the Atlantic Ocean between Port Royal Sound, SC, and 
Cumberland Sound, GA and FL, including the Atlantic 
Intracoastal Waterway between these points. This area 
covers the headwaters of the Savannah River in southwestern 
North Carolina, a considerable portion of western 
South Carolina, eastern Georgia, and a small portion 
of northeastern Florida. 
IMPROVEMENTS 
Navigation 
1. Altamaha, Oconee, and Ocmulgee 
Rivers, GA ...................................... 
2. Aquatic Plant Control ........................ 
3. Atlantic Intracoastal Waterway 
Between Norfolk, VA, and St. Johns 
River, FL (Savannah District) ............ 
4. Brunswick Harbor, GA ...................... 
5. Savannah Harbor, GA ....................... 
6. Savannah River Below 
Augusta, GA ................................... 
7. Reconnaissance and Condition 
Surveys ........................................... 
8. Other Authorized Navigation 
Projects ........................................... 
9. Navigation Work Under Special 
Authorization ........................... 
Beach Erosion Control 
10. Tybee Island, GA ............................ 
Flood Control 
11. Broadway Lake, Anderson County, 
SC ....... :........................................... 
12. Inspection of Completed Flood 
Control Projects............................... 
13. Other Authorized Flood Control 
Projects ........................................... 
14. Flood Control Work Under Special 
Authorization ................................... 
Page Multiple-Purpose Projects 
Including Power 
8-1 15. Savannah River Basin, GA 
8-2 and SC ............................................. 
15A. Clarks Hill Lake, GA and SC ............... 
15B. Hartwell Lake, GA and SC .................. 
8-2 15C. Richard B. Russell Dam and Lake, 
8-3 GA and SC (Formerly Trotters 
8-4 Shoals Lake, GA and SC) ................... 
16. West Point Lake, Chattahoochee 
8-5 River Basin, GA and AL ................. 
8-6 General Investigations 
17. Surveys .......................................... 
8-6 18. Collection and Study of Basic Data .... 
19. Research and Development ............... 
8-6 20. Continuation of Planning 
and Engineering .............................. 
8-6 Tables 
Table 8-A Cost and Financial Statement ....... 
Table 8-B Authorizing Legislation................ 
Table 8-C Other Authorized Navigation 
8-7 
8-7 
8-7 
8-7 
Projects ...................................... 
Table 8-D Other Authorized Flood Control 
Projects ..................................... 
Table 8-E Savannah River Basin, GA and SC 
Dams and Lakes ........................ 
Page 
8-8 
8-8 
8-8 
8-9 
8-10 
8-10 
8-10 
8-10 
8-10 
8-11 
8-12 
8-16 
8-16 
8-17 
Navigation 
1. ALTAMAHA, OCONEE, AND 
OCMULGEE RIVERS, GA 
Location. These Rivers are entirely within the State 
of Georgia. (See National Oceanic and Atmospheric Administration 
Survey Map of Georgia, formerly U.S. 
Geological Survey map of Georgia.) For full description 
of these rivers, see page 636, Annual Report for 1932. 
Previous projects. Prior projects for the Altamaha 
River have been adopted, and expenditures made under 
them, by River and Harbor Acts of March 3, 1881, and 
September 19, 1890; for the Oconee River by River and 
Harbor Acts of June 18, 1878, September 19, 1890, and 
March 3, 1905; for the Ocmulgee River, by River and 
Harbor Acts of August 14, 1876, and September 19, 
1890. 
For further details, see page 1815, Annual Report for 
1915, and page 589, Annual Report for 1938. 
Existing project. The authorized project provides 
for an appropriation of $40,000 annually for the Altamaha, 
Oconee, and Ocmulgee Rivers, to maintain a 
8-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
3-foot depth during ordinary summer low water and to 
gradually increase channel depth, so far as practicable 
without sacrificing the maintenance work. This project 
covers the entire Altamaha River (including a channel 
between the river and Dariern, GA), a length of 137 
miles, the lower 139 miles of the Oconee River, and the 
lower 199 miles of the Ocmulgee River. The Altamaha 
River has a mean tidal range of 6.4 feet at its mouth 
which gradually decreases to mile 33 above, where there 
is no perceptible tidal effect. At Doctortown, mile 5), 
ordinary floods attain a height of about 10 feet above 
low water, and extreme floods, a height of about 15 feet 
above low water. 
On the Oconee River at Dublin the ordinary fluctuations 
attain a height of 22 feet, and the extreme fluctuations 
a height of 32 feet, above low water. On the Ocmulgee 
River at Macon the ordinary fluctuations attain 
a height of 15 feet, and the extreme fluctuations a 
height of 25 feet, above low water. There is no approved 
estimated cost for improvement or for 
maintenance. 
Published maps of these rivers are in the following 
documents: Altamaha River, House Executive Document 
283, Fifty-first Congress, second session; Oconee 
River, House Executive Document 211, Fifty-first Congress, 
first session; Ocmulgee River, House Executive 
Document 215, Fifty-first Congress, first session; and 
Lower Altamaha River and Darien Harbor, GA, House 
Document 610, Seventy-seventh Congress, second session. 
(See Table 8-B for Authorizing Legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Along these rivers there are 
numerous natural shore landings which are considered 
ample for existing commerce. Facilities for recreational 
boats have been constructed in recent years at several 
points. 
Operations and results during fiscal year. Maintenance: 
No maintenance was performed during the fiscal 
year. The Toxic Substance Study was completed, 
and the fiscal year cost was $191, thus making the total 
study cost $6,012. (See Table 8-A for Cost and Financial 
Statement.) 
Condition at end of fiscal year. The existing project 
is such that the percentage of completion cannot be 
stated. Channel depths have been increased by excavating 
rock shoals and sandbars, by constructing contraction 
and bank-protection works, and by closing cutoffs. 
Navigation has been rendered safer by removing 
obstructions. Many of the closing dams and contractions 
and bank-protection works need repairs. The notice of 
availability on the Final Environmental Statement appeared 
in the Federal Register October 21, 1977. 
To September 30, 1983, costs under the existing project 
were $60,847 for new work and $1,871,363 for 
maintenance, of which $69,356 were contributed funds, 
a total of $1,932,210. (See Table 8-A for Cost and Financial 
Statement.) 
2. AQUATIC PLANT CONTROL 
Location. Navigable waters, tributary streams, connecting 
channels, and other allied waters in Savannah 
District. 
Existing project. The project provides for control 
and progressive eradication of water-hyacinth, alligatorweed, 
Eurasian water milfoil, and other noxious aquatic 
plants from navigable waters, tributary streams, connecting 
channels, and other allied waters of the United 
States, in the combined interests of navigation, flood 
control, drainage, agriculture, fish and wildlife conservation, 
public health, and related purposes. The project 
provides for continued research for developing the most 
effective and economic control measures in cooperation 
with other Federal and State agencies in accordance 
with report of Chief of Engineers, House Document 251, 
89th Congress, 1st session. The authorizing act provides 
that research and planning costs shall be borne fully by 
the United States. (See Table 8-B for Authorizing 
Legislation.) 
Local cooperation. Local interests must agree to 
hold the United States free from damages that may 
occur from operations performed in connection with this 
project and participate to the extent of 30 percent of the 
cost of the program. Requirements are being met. 
Operations and results during fiscal year. Georgia 
Game and Fish Division, Department of Natural Resources, 
who maintain surveillance of potential aquatic 
plant problem areas, reported aquatic plant infestation 
in the Satilla River and in other river basins in the 
State of Georgia. Actual control work under the Aquatic 
Plant Control Cost Sharing Program with the Georgia 
Game and Fish Division was not accomplished in FY 83. 
Certain parts of a proposed new contract were not acceptable 
to the State. Savannah District pursued the 
possibility of contracting with counties under the program. 
Advice from SAD was that the District had authority 
to contract only with the State. The District assisted 
the public in FY 83 by answering inquiries about 
the program and providing contacts with the State. Cost 
during the fiscal year was $36,731. The Final Environmental 
Statement was filed with ERA on August 6, 
1979, and its notice of availability appeared in the Federal 
Register August 17, 1979. (See Table 8-A for Cost 
and Financial Statement.) 
3. ATLANTIC INTRACOASTAL 
WATERWAY BETWEEN NORFOLK, 
VA, AND THE ST. JOHNS 
RIVER, FL (SAVANNAH DISTRICT) 
Location. This 161-mile section of waterway connects 
Port Royal Sound, SC, with Cumberland Sound, 
GA and FL (See NOAA charts 11489 - 11507, formerly 
Coast and Geodetic Survey Charts 838-841, inclusive.) 
Previous project. (Between Savannah, GA, and 
Fernandina, FL.) For details see pages 1814, 1821-1823 
of Annual Report for 1915 and page 585 of Annual Report 
for 1938. 
8-2

SAVANNAH, GA, DISTRICT 
Existing project. The project provides for a waterway 
12 feet deep at mean low water and not less than 
90 feet wide between Port Royal Sound, SC, and Savannah, 
GA; 12 feet deep at mean low water, with widths 
of 90 feet in land cuts and narrow streams and 150 feet 
in open waters between Savannah, GA, and Cumberland 
Sound, GA and FL; and a suitable anchorage basin at 
Thunderbolt, GA. Mean tidal range between Port 
Royal, SC, and Cumberland Sound, GA and FL, is from 
6 to 8 feet with fluctuations from 1.5 to 2.5 feet, due to 
winds and lunar phases. (See Table 8-B for Authorizing 
Legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Exclusive of adequate terminal 
facilities at ports of entry, this improvement serves 
numerous wharves, some of which are open to the public 
on equal terms. Facilities are considered ample for 
existing commerce. 
Operations and results during fiscal year. Maintenance: 
A contract for maintenance dredging of the Atlantic 
Intracoastal Waterway was awarded June 18, 
1982. The contract dredges Dauntless and Cherokee removed 
539,025 cubic yards of material from Hell Gate 
and Umbrella Cut during the period of October 1, 1982, 
through January 5, 1983, at a total cost of $350,436, including 
inspection, administration, and other government 
cost. The government cost for surveys and inspection 
reports, and condition and operation studies 
amounted to $121,090. Real estate inspection cost and 
administration activities cost amounted to $4,209. Distribution 
of Engineer Yard cost amounted to $1,630. The 
50-year long-range Maintenance Study was completed 
during FY 82, but $3,799 was expended during FY 83. 
(The total cost of the study, including previous fiscal 
years, was $64,859.) Total cost for the fiscal year 
amounted to $481,164. (See Table 8-A for Cost and Financial 
Statement.) 
Condition at end of fiscal year. The main channel 
of the existing project, completed in 1941, is maintained 
at 12 feet. The former main channel, now an alternate 
route through the westerly end of the south channel and 
northerly end of Wilmington River, will be maintained 
to a depth of 7 feet mean low water for traffic points 
north and south of Savannah Harbor. Relocation of the 
main channel from the Frederica to Mackay River near 
St. Simons Island, GA, will be accomplished after construction 
of the new bridges for the Torras Causeway 
are completed. The notice on the Final Environmental 
Impact Statement appeared in the Federal Register October 
29, 1976. 
Costs of the existing completed project to September 
30, 1983, were $763,599 for new work and $13,779,863 
for maintenance, a total of $14,543,462. (See Table 8-A 
for Cost and Financial Statement.) 
4. BRUNSWICK HARBOR, GA 
Location. The harbor entrance is 70 statute miles 
south of the entrance to Savannah Harbor, GA, and 25 
statute miles north of the entrance to Fernandina Harbor, 
FL. (See NOAA Chart 11215, formerly Coast and 
Geodetic Survey Chart 447.) 
Previous projects. For details see page 1818 of Annual 
Report for 1915 and page 591 of Annual Report for 
1938. 
Existing project. The project provides for a stone 
jetty 4,350 feet long at the entrance to East River and 
the following channels: 32 feet deep and 500 feet wide 
across the bar; 30 feet deep and 400 feet wide through 
St. Simons Sound, Brunswick River, and East River to 
the foot of Second Avenue; 30 feet deep and 300 feet 
wide in Turtle River to the Allied Chemical Co. wharf, 
formerly the Atlantic Refining Co.; 27 feet deep and 350 
feet wide in East River from Second Avenue to its confluence 
with Academy Creek; 24 feet deep and 150 feet 
wide in Academy Creek; a channel in Back River 20 feet 
deep and 150 feet wide from St. Simons Sound to the 
mouth of Mill Creek; and a channel in Terry Creek 10 
feet deep and 80 feet wide from its mouth to a point immediately 
above the wharf of Glynn Canning Company. 
All depths refer to mean low water. Mean tidal range 
on the bar is 6.5 feet, at the city of Brunswick 7.3, and 
7.6 feet at the upper end of the harbor. For further details 
see Annual Report for 1962. 
Local cooperation. Complied with to date. 
Terminal facilities. Eighteen wharves and piers, almost 
all privately owned, have a berthing space of 7,530 
feet. The Port of Brunswick and the State of Georgia 
have a transit shed and modern docks with 1,640 feet of 
berthing space on East River. For further details see 
Port Series No. 14, Corps of Engineers (revised 1982). 
Operations and results during fiscal year. Maintenance: 
A contract for maintenance dredging of the bar 
channel and St. Simons Sound was awarded July 8, 
1983. The contract dredge Dodge Island removed 
695,902 cubic yards of material from the sound and bar 
channel (sta 16+000 to 23+000 and sta 8+000 B to 
46+000 B) during the period of July 10, 1983, through 
August 31, 1983. The total cost (of which $2,149,999 was 
expended from 1983 Job Bill Act) was $2,270,445 including 
inspection, administration, and other government 
cost. The maintenance dredging contract for East River 
was awarded July 26, 1983. The contract dredge Clinton 
removed 347,390 cubic yards of material from East 
River (sta 70 + 00 to 108 + 00) during August 5, 1983, to 
August 23, 1983, at a total cost of $258,214, including inspection, 
administration and other government costs. A 
contract for dredging in the East River and Terry 
Creek was awarded September 24, 1983. The contract 
dredge Cherokee removed 1,349,589 cubic yards of material 
from sta 27+20 to 41+80 and sta 24+00 to 
126 + 00 during the period of October 27, 1982, through 
March 3, 1983, at a total cost of $870,496 including inspection, 
administration and other government costs. A 
contract for rock dredging in the inner harbor was 
awarded August 20, 1982. During the period of 
November 10, 1982 through September 30, 1983, the 
dredges Savannah, Mogul, Michigan, Minnesota, and 
Moody Barge, removed 368,000 cubic yards of material 
8-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
from sta 23 + 260 to 33 +010 and sta 33 +630 to 35+ 940 
at a total cost of $1,356,989 including inspection, administration 
and other government costs. St. Andrews Island 
spoil dikes engineering and design cost amounted 
to $58,259. The contract to raise the dikes in the Terry 
Creek disposal area was completed September 14, 1982. 
During FY 83 an additional cost of $4,355 for engineering 
and design was expended. 
Routine condition surveys, water, air, and environmental 
studies, inspection and reports, and other essential 
activities amounted to $372,638. Mosquito control in 
disposal areas cost amounted to $55,064. Distribution of 
Engineer Yard was $5,758. Other year end adjustments 
amounted to $11,509. Credits received for dredging 
berthing spaces of Georgia Ports Authority, Brunswick 
Ports Authority, and the city of Brunswick amounted to 
$42,474. Total operation and maintenance cost amounted 
to $5,221,253. (See Table 8-A for Cost and Financial 
Statement.) 
Condition at end of fiscal year. The existing project 
was completed in December 1960. General condition 
of the harbor works is satisfactory, providing maintenance 
dredging continues. The notice on the Final Environmental 
Impact Statement appeared in the Federal 
Register October 3, 1975. 
Costs for existing completed project to September 30, 
1983, were $39,197,820, of which $3,929,968 was for new 
work and $35,267,852 for maintenance. (See Table 8-A 
for Cost and Financial Statement.) 
5. SAVANNAH HARBOR, GA 
Location. Harbor entrance is 75 statute miles south 
of Charleston Harbor, SC, and 70 statute miles north of 
Brunswick Harbor, GA (See NOAA Chart 11512, formerly 
Coast and Geodetic Survey Chart 440.) 
Previous projects. For details see page 1810 of Annual 
Report for 1915 and page 578 of Annual Report for 
1938. 
Existing project. The project provides for a channel 
40 feet deep and 600 feet wide across the ocean bar 
about 7.0 miles; 38 feet deep and 500 feet wide to the 
Seaboard Coast Line terminal; 38 feet deep and 400 feet 
wide to the vicinity of Garden City (Georgia Ports Authority 
terminal); and 36 feet deep and 400 feet wide to 
the vicinity of Savannah Sugar Refinery of Savannah 
Foods and Industries, Inc. about 22.6 miles; and 30 feet 
deep and 200 feet wide to a point 1,500 feet below the 
Atlantic Coastal Highway bridge, about 1.5 miles, a 
total length of 31.1 miles; Fig Island and Marsh Island 
Turning Basins 34 feet deep by 900 feet wide by 1,000 
feet long in the vicinity of the Seaboard Coast Line terminal, 
and American Oil Company terminal; Kings Island 
Turning basin 38 feet deep by 1,500 feet wide by 
1,600 feet long in the vicinity of Garden City terminal 
of the Georgia Ports Authority; Argyle Island and Port 
Wentworth Turning Basins 30 feet deep by 600 feet 
wide by 600 feet long near Savannah Sugar Refinery 
terminal and at the extreme upper limit of the project 
near Continental Can Company terminal; and Oyster 
Bed Island Turning Basin in the vicinity of Georgia 
Ports Authority LASH facility. The project also provides 
for sediment control works consisting of a tide 
gate structure across Back River; a sediment basin 40 
feet deep, 600 feet wide, about 2 miles long, with an entrance 
channel 38 to 40 feet deep and 300 feet wide; a 
drainage canal across Argyle Island 15 feet deep and 
300 feet wide; control works and canals for .supplying 
fresh water to the Savannah National Wildlife Refuge; 
and facilities to mitigate damages to presently improved 
areas other than refuge lands. Mean range of tide is 7.9 
feet at the upper end of the harbor and 6.9 feet at the 
lower end. Extreme ranges are about 11.1 and 10.7 feet, 
respectively. Latest (FY 82) estimate of total Federal 
cost for new work modification is $34,219,000 
($11,932,000 for Sediment Basin and Appurtenant 
Works, $8,660,000 for LASH and Kings Island Turning 
Basins, $13,400,000 for the Widening and Deepening of 
Channels and Turning Basin and $227,000 U.S. Coast 
Guard costs). Estimated local cost for LASH and Kings 
Island Turning Basins is $2,102,000 and $367,000 for 
Widening and Deepening of Channels and Turning 
Basin, and $455,000 for Sediment Basin and Appurtenant 
Works. 
Local cooperation. Local interests must provide 
suitable spoil areas and retaining dikes for construction 
and future maintenance of the project. The Chatham 
County Commissioners, as local assurers, have met all 
requirements to date. 
Terminal facilities. Sixty-one piers and wharves 
adequately serve existing waterborne commerce of the 
port. These facilities, with use of dolphins, have a combined 
berthing space of 39,493 feet with water depths 
alongside ranging up to 38 feet at mean low water. Included 
in the berthing space are six container berths 
with 271 acres of handling area. All have railway and 
highway connections. LASH facilities are located at the 
entrance to the harbor and have depths ranging up to 
38 feet mean low water. The berthing space of LASH 
facilities is included in the above combined berthing 
space. For further details, see Port Series No. 14, 
Corps of Engineers (revised 1982) and Annual Report 
for 1962. 
Operations and results during fiscal year. New 
Work: Under Savannah Harbor Extension, a construction 
contract for Kings Island Turning Basin was 
awarded August 28, 1980. The pipeline dredge Stuart, 
completed the contract in July 1982 at a total cost of 
$1,938,034 for FY 82. Due to contract modifications and 
underruns, an adjustment (credit) of $112,480 was made 
in FY 83. The total cost for new work during the fiscal 
year amounted to a credit of (minus) $112,480. (See 
Table 8-A for Cost and Financial Statement). 
Maintenance: A contract for the removal of material 
from the bar channel was awarded November 22, 1982. 
During the period of April 20, 1983, through June 6, 
1983, the dredge Dodge Island removed 644,940 cubic 
yards of material between sta 5 + 000 and 60 + 000 B at 
a cost of $2,369,686 including inspection, overhead and 
other government cost. A contract for removal of mate- 
8-4

SAVANNAH, GA, DISTRICT 
rial from the sediment basin was awarded June 11, 
1982. Contract pipeline dredge Clinton removed 78,033 
cubic yards of material from the sediment basin (sta 
0+500 to 13+ 300) during the period from October 1, 
1982, to November 16, 1982, at a total cost of $103,822, 
including inspection, overhead and other government 
cost. A new contract was awarded May 11, 1983, for 
maintenance dredging in the sediment basin and inner 
harbor. During the period from June 2, 1983, through 
September 30, 1983, the dredges Hampton Roads and 
Clinton removed 3,039,545 cubic yards of material between 
sta 0 + 500 and 13+ 300 in the sediment basin and 
sta 102 + 000 and 102 + 750 and sta 40 + 000 and 70 + 000 
in the channel at a total cost of $1,439,890 including inspection, 
overhead and other government cost. A contract 
was awarded February 4, 1982, to dredge the 
inner harbor. The pipeline dredge Clinton removed 
546,074 cubic yards between October 1, 1982, and 
November 17, 1982, from sta 35 + 000 to 112 + 500 and 
sta 80+250 to 81+250 at a total cost of $1,563,938, including 
inspection, overhead, and other government 
cost. A contract for maintenance dredging in the Kings 
Island Turning Basin was awarded August 28, 1980. 
Dredging under this contract was continued into FY 82. 
The pipeline dredge Stuart completed its work in March 
1982, and the final payment of $41,548 was made in FY 
83. (A credit of $4,288 was applied to the contract for 
Oyster Bed Island bank protection which was completed 
in FY 82.) The cost of repairs to Engineer Yard dock 
was $65,012. The cost for removal of obstructions on 
edge of the bar channel was $11,285. (A credit of 
$63,466 was received for reimbursement of dredging for 
the Georgia Ports Authority.) Mosquito control in disposal 
areas cost $160,902. Operation and maintenance of 
the tide gate system cost $655,172. (Credits received 
from agitation dredging of private shipping interest slips 
amounted to $272,951.) Distribution of Engineer Yard 
cost amounted to $101,359. The cost for dragging and 
sweeping for the fiscal year amounted to $16,327. Condition 
surveys, water quality monitoring, water and air 
pollution studies, environmental studies, testing, inspection 
and reports, and government supervision and administration 
costs were $618,902. Miscellaneous operation 
and maintenance cost amounted to $179,776. Total 
operation and maintenance costs for the fiscal year 
amounted to $6,986,914. (See Table 8-A for Cost and Financial 
Statement.) 
Condition at end of fiscal year. The existing project 
is incomplete. Training walls, jetties, and other 
structures are in fair condition. Authorized channels are 
maintained by a planned dredging program with work at 
critical areas when necessary. The notice on the Final 
Environmental Impact Statement appeared in the Federal 
Register June 25, 1976. Notices of availability on 
two Final Supplements to the Environmental Impact 
Statement appeared in the Federal Register September 
25, 1978, and January 8, 1980. 
Costs of existing project to September 30, 1983, were 
$38,925,359 Federal cost and $1,886,413 contributed 
funds for new work and $120,774,688 Federal cost and 
$852,858 contributed funds for maintenance, a total of 
$162,439,318. (See Table 8-A for Cost and Financial 
Statement.) 
6. SAVANNAH RIVER BELOW 
AUGUSTA, GA 
Location. Savannah River is formed by the confluence 
of the Tugaloo and Seneca Rivers on the boundary 
line between South Carolina and Georgia. It flows 
southeast 314 miles, forming the boundary line between 
the two states, and empties into the Atlantic Ocean 16.6 
miles below Savannah, GA (See NOAA Charts 11514 
and 11515, formerly Geological Survey maps of South 
Carolina and Georgia.) 
Previous project. For details see page 1813 of Annual 
Report for 1915 and page 581 of Annual Report for 
1938. 
Existing project. The authorized project provides 
for a channel 9 feet deep and 90 feet wide (at ordinary 
summer flow of 5,800 second-feet at Augusta, GA) from 
the upper end of Savannah Harbor to the head of navigation 
at Augusta, 3 miles above Fifth Street Bridge, a 
total distance of about 181 miles. A lock and dam is located 
approximately 15 miles below the upper limit of 
the project at New Savannah Bluff. Improvement is to 
be obtained by construction of contraction works, closure 
of cutoffs, bank protection, dredging, removal of 
snags, overhanging trees and wrecks, and open-river 
regulation. Mean tidal variation at the mouth of the 
river is 7 feet. Freshet variation above the normal pool 
level (elevation 114.5 mean sea level) of New Savannah 
Bluff Lock and Dam at miles 187 is ordinarily about 13 
feet with an extreme of 34 feet. Latest approved project 
cost estimate for providing a 9-foot channel (September 
1963) is $6,576,000 exclusive of amounts expended on 
previous projects. Recreation facilities at New Savannah 
Bluff Lock and Dam cost $17,000. For further details 
see Annual Report for 1962. 
Local cooperation. Complied with to date. The City 
Council of Augusta, GA, and the Georgia and South 
Carolina Ports Authorities have agreed to act as local 
assurer. 
Terminal facilities. The only water terminals served 
by this improvement are at Augusta, Sylvania, and at 
or near Savannah. Augusta provided a municipal dock 
valued at $50,000 and Georgia Ports Authority constructed 
a State port at Augusta, GA, costing about 
$418,000. These facilities were expanded in 1965 at an 
additional cost of about $250,000. In addition, Koch Refining 
Company maintains a terminal below Augusta and 
Allied Chemical Co. maintains a terminal at Sylvania. 
These are supplemented by natural landings along the 
river and extensive facilities at Savannah. 
Operations and results during fiscal year. Maintenance: 
Routine maintenance and operation of the New 
Savannah Bluff Lock and Dam and its recreational area, 
which accommodated 268,712 visitors, amounted to 
$77,869. Routine condition surveys, water pollution and 
environmental studies, inspection and reports and other 
8-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
administrative costs amounted to $21,959. Miscellaneous 
cost including service facilities and radio system microwave 
equipment amounted to $75,541. Credits received 
for housing of lock employees amounted to $3,917. Total 
operation and maintenance cost for the fiscal year 
amounted to $171,452. (See Table 8-A for Cost and Financial 
Statement.) 
Condition at end of fiscal year. In general, openchannel 
works are in good condition. The notice on the 
Final Environmental Impact Statement appeared in the 
Federal Register February 18, 1977. 
Costs of existing project to September 30, 1983, were 
$20,481,707 of which $6,646,551 was for new work and 
$13,835,156 for maintenance. (See Table 8-A for Cost 
and Financial Statement.) 
7. RECONNAISSANCE AND 
CONDITION SURVEYS 
No reconnaissance and condition surveys were conducted 
during the FY. (See Table 8-C.) 
8. OTHER AUTHORIZED 
NAVIGATION PROJECTS 
(See Table 8-C.) 
9. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation activities pursuant to Section 107, Public 
Law 86-645, as amended (Preauthorization 
Studies.) FY costs for preauthorization studies were 
$155,668. A detailed project study was continued on 
Bellville Point, GA, at a cost of $80,149. A draft Environmental 
Impact Statement on the Bellville Point 
project was released on July 16, 1982. The Valona, GA, 
detailed project study was also continued and the fiscal 
year cost was $75,481. A negative report was completed 
on Meridian, GA, in FY 82, but an additional cost of $38 
was charged in FY 83. The Torras Causeway, 
Brunswick, GA, project was approved in early FY 82. 
It provides for the main channel of the AIWW, in the 
vicinity of Torras Causeway, to be relocated from 
Frederica River to Mackay River. This relocation is to 
take place when the new Torras Causeway bridges, now 
under construction, are completed. 
Beach Erosion Control 
10. TYBEE ISLAND, GA 
Location. Tybee Island is located directly south of 
Savannah River entrance, about 17 miles east of the city 
of Savannah, GA (See NOAA Charts 11512, 11513 and 
11509, formerly U.S. Coast and Geodetic Survey Charts 
Nos. 440, 1240, and 1241, and on maps included in H.D. 
92-105, 92d Cong.) The only portion of the island that 
has been developed is bounded on the north by the 
south channel of the Savannah River, on the east by the 
Atlantic ocean, and on the south and west by Tybee 
Creek and other small tidal streams. This area, 
hereinafter referred to as "Tybee Island," is occupied by 
the city of Tybee Island. The ocean face of this area has 
had a wide sandy beach. Tybee Island is about 3.5 miles 
long from its northerly tip to the mouth of Tybee Creek 
with an average width of about 0.5 mile. Behind the 
beach lies a line of sand dunes, a number of which have 
been removed during the years to make room for improvements 
and for various other reasons. Those that 
remain are from 10 to 20 feet high. The ground elevation 
west of the dunes is from 10 to 18 feet and slopes 
westward to the salt marsh. 
Existing project. The approved project plan of improvement 
provides for an 800-foot rock groin at the 
north end of the island, with a 225-foot tie-in to high 
ground. An additional 1,200-foot extension of this groin 
is deferred, as are two additional, intermediate groins 
(480 feet long); these will be added at a later date, if 
needed. Plans now call for the addition of a groin at the 
south end and modification and rehabilitation of the 
north rock groin. The plan also provides for the initial 
restoration of approximately 13,300 feet of beach, from 
the vicinity of 18th Street to the new terminal groin located 
at the northern end of the island. Periodic 
nourishment will be provided as needed to maintain 
suitable beach dimensions. 
Local cooperation. Local interests must: (a) contribute 
in cash the required percentage of the first cost, 
including costs for construction, engineering, and design, 
and administration; and excluding the cost of 
lands, easements, rights-of-way; and relocations; of all 
items of work to be provided by the Corps of Engineers, 
presently estimated at 51.0 percent or 
$6,070,000 (FY 82 estimate) to be paid in a lump sum 
prior to start of construction or in installments prior to 
the start of pertinent work items in accordance with 
construction schedules as required by the Chief of Engineers, 
the final apportionment of cost to be made after 
the actual costs have been determined; (b) provide 
maintenance and repair of the groins, and provide, after 
the first 15 years of project life, periodic nourishment of 
the restored beach as may be required to serve the intended 
purpose during the life of the project; (c) provide 
without cost to the United States all lands, easements, 
rights-of-way, and relocations required for construction 
and subsequent nourishment of the project; (d) hold and 
save the United States free from claims for damages 
that may result from construction, maintenance, and 
nourishment of the project; (e) control water pollution to 
the extent necessary to safeguard the health of bathers; 
and (f) provide without cost to the United States access 
and facilities necessary for realizationof the public benefits 
upon which Federal participation is based, and 
maintain continued public use of the beach and administer 
it for public use during the life of the project; and 
provided further, that construction on the project shall 
not be started until local interests furnish lands for 
beach access and parking, satisfactory to the Chief of 
Engineers, for the reach from 1st Street to the terminal 
groin. To date, local cooperation is being provided as 
required. 
8-6

SAVANNAH, GA, DISTRICT 
Operations and results during fiscal year. Federal 
cost of activities during the fiscal year amounted to 
$4,542, and no funds were expended from non-Federal 
contributions. (See Table 8-A for Cost and Financial 
Statement.) 
Condition at end of fiscal year. The Final Environmental 
Impact Statement was filed with CEQ on 
November 13, 1973. The initial construction contract for 
the terminal groin was awarded September 13, 1974 in 
the amount of $980,642. The groin was completed and 
formally accepted on June 17, 1975. The second contract, 
for initial beach fill and advance nourishment, was 
awarded June 18, 1975 in the amount of $2, 175,000. 
This resulted in the placement of 2.3 million cubic yards 
of sandfill along most of the entire length (13,300 feet) 
of ocean beach front. The sand was removed by hydraulic 
pipeline dredge from a massive sandbar borrow area 
off the south end of Tybee Island. Completed in March 
1976, the project provides approximately 124 feet of 
beach seaward of the seawall (accessible at average high 
tide), doubling the public beach area. Erosion has occurred 
along the beach front. Results of prior years 
beach monitoring indicate a decreasing or stabilizing 
erosion rate. The southernmost section south of 13th 
Street has experienced the most critical erosion. However, 
the available beach surface for recreation purposes 
has increased since project completion. Total project 
cost is estimated to be $11,900,000, which includes 
$6,070,000 in non-Federal, contributed funds. Costs to 
date of existing project were $2,527,095 (Federal funds) 
and $2,024,856 (contributed funds). (See Table 8-A Cost 
and Financial Statement.) 
Flood Control 
11. BROADWAY LAKE, ANDERSON 
COUNTY, SC 
Location. The Broadway Lake is located about 4 
miles southeast of Anderson, South Carolina. It is 
formed at the junction of Broadway Creek and Neals 
Creek in the headwaters of Rocky River, a tributary of 
the Savannah River. 
Existing project. The authorization provides for the 
Corps of Engineers to undertake a demonstration project 
for the removal of silt and aquatic growth from an 
existing lake known as Broadway Lake, owned by Anderson 
County, South Carolina. This lake has a surface 
area of about 1 square mile and a tributary area of 
about 44 square miles with an existing dam and concrete 
spillway. The spillway is 50 feet wide, about 19 feet 
high, and flanked by an earth embankment on the west 
side. The total length of the dam is about 610 feet. The 
National Dam Safety Inspection Program determined 
that the dam did not meet the safety criteria. Since the 
repairs of the dam, spillway, and low-level outlet are 
not within the authority of the demonstration project, 
the U.S. Army Corps of Engineers will withhold implementation 
of the project pending repairs to the dam 
by State or local authorities. 
Local cooperation. The local interests are now 
making the necessary repairs to the dam. Local interests 
have expressed a willingness to provide necessary 
easements, and rights-of-way for removal of silt and 
aquatic weeds, as well as provide lands for disposal 
areas. They will be required to hold and save the 
United States free from damages due to the construction 
works other than damages due to the fault or negligence 
of the United States or its contractors. The 
United States should be relieved of any liability due to 
dam failure from construction activity in the lake. The 
local assurer is Anderson County. 
Operations and results during fiscal year. The 
project is inactive, pending completion of repairs to the 
dam by local interest. The Office of the Chief of Engineers 
is preparing a Significant Post Authorization 
Change Report for submittal to Congress. Draft Environmental 
Impact Statement appeared in the Federal 
Register August 29, 1977. (See Table 8-A for Cost and. 
Financial Statement.) 
12. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Physical inspections of the Augusta and Macon levees 
were not completed during the fiscal year. Inspections 
were made of Dunn Branch August 10, 1983, and 
Peacock Creek September 14, 1983. The total cost of the 
fiscal year amounted to $4,731. (See Table 8-A Cost and 
Financial Statement.) 
13. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
(See Table 8-D.) 
14. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control activities pursuant to section 205, 
Public Law 858, 80th Congress, as amended 
(preauthorization studies). Preauthorization studies 
continued through FY 83 on Casey Canal, GA, at a cost 
of $52,016; Federal Prison Creek, GA ($70,463); Placentia 
Canal, GA ($75,881); and Springfield Canal, GA 
($28,304). Studies on Conley Creek, GA, and Pettit 
Creek, GA, were terminated in FY 82, but additional 
costs reported in FY 83 were $272 and $73, respectively. 
A negative reconnaissance report on Shoal 
Creek, GA, completed in FY 82 has an additional cost 
of $6. The total cost for preauthorization studies for the 
fiscal year was $227,015. 
Emergency flood control activities - repair, flood 
fighting, and rescue work, (Public Law 99, 84th Congress 
and antecedent legislation). Revisions to 
emergency manuals, emergency planning, inspection, 
supplies, emergency operations, and other expenditures 
costs for coastal emergencies were $173,522. National 
emergency preparedness cost amounted to $93,065. 
8-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Multiple-Purpose Projects Including Power 
15. SAVANNAH RIVER BASIN, GA 
AND SC 
Location. Works covered by this project consist of a 
series of 11 dams and lakes on Savannah River and its 
tributaries in Georgia and South Carolina. (See Geological 
Survey maps of GA and SC.) 
Existing project. The Flood Control Act of 1944 approved 
the general plan for comprehensive development 
of the Savannah River Basin for flood control and other 
purposes (H. D. 657, 78th Cong., 2d sess.) and authorized 
construction of the Clarks Hill Project on the 
Savannah River in Georgia and South Carolina as the 
initial step of this development. The Flood Control Act 
of 1950 authorized construction of Hartwell Lake under 
the general plan. Trotters Shoals which will replace 
Goat Island and Middleton Shoals was authorized for 
construction by the Flood Control Act of 1966 at an estimated 
cost of $84,900,000. Clarks Hill and Hartwell 
Lakes are the only projects in the comprehensive plan 
that have been constructed. (See Table 8-E on Dams 
and Lakes at end of chapter.) 
Duke Power Company has completed constructed on 
the Keowee-Toxaway power complex on the Keowee 
River in the headwaters of Hartwell Lake and construction 
of the Jocassee pump-storage power project in the 
headwaters of the Keowee-Toxaway project. The 
Keowee-Toxaway power complex is located on the 
Newry - Old Pickens site identified in the approved 
comprehensive plan. Individual reports on Clarks Hill, 
Hartwell, and Richard B. Russell (formerly Trotters 
Shoals) Lakes follow. 
Local cooperation. None required. 
15A. CLARKS HILL LAKE, GA AND SC 
Location. Clarks Hill Lake is located at mile 237.7 
on Savannah River about 22 miles upstream from Augusta, 
GA (See Geological Survey maps of Georgia and 
South Carolina.) 
Existing project. The authorized project provides 
for construction of Clarks Hill Dam and Lake, the final 
cost of which was $79,156,300. The dam has a concrete 
section 2,282 feet long with a maximum height of 200 
feet, and a controlled spillway 1,096 feet long. The concrete 
section is flanked on the west side by a rolledearth 
embankment of 2,069 feet, and on the east side by 
a similar embankment of 1,329 feet. Total length of the 
dam is 5,680 feet. At maximum power pool elevation 
330, the lake covers 70,000 acres. It provides a total 
storage capacity of 2,900,000 acre-feet allocated as follows: 
flood control 390,000 acre-feet; hydroelectric 
power 1,045,000 acre-feet; and dead storage 1,465,000 
acre-feet. Seven 40,000-kilowatt generators have a combined 
generating capacity of 280,000 kilowatts, with an 
average annual output of 700 million kilowatt-hours of 
electrical energy. 
Local cooperation. None required. 
Operations and results during fiscal year. New 
work: Cost of recreational activities during the period 
from Construction General funds (Code 710) amounted 
to $460,252. Under the 1983 Job Bill Act $132,948 was 
expended for temporary employment. The total fiscal 
year cost for new work amounted to $593,200. Gross 
generations of electric energy for the period was 
824,060,000 kilowatt-hours, most of which was delivered 
to the Southeastern Power Administration. Flood damages 
prevented amounted to $1,891,800. 
Maintenance: Operation and maintenance costs during 
the fiscal year amounted to $5,629,293 of which 
$368,298 was expended for temporary employment 
under the 1983 Job Bill Act. The notice of availability 
on the Final Environment 'Impact Statement on Clarks 
Hill Lake Operation and Maintenance appeared in the 
December 18, 1981, Federal Register. 
Condition at end of fiscal year. Construction is 
complete except for providing additional recreational development. 
(See Table 8-A for Cost and Financial 
Statement.) 
15B. HARTWELL LAKE, GA AND SC 
Location. Hartwell Lake is on the Savannah River 
305 miles above its mouth and 89 miles' upstream from 
Augusta, Georgia. (See Geological Survey maps of GA 
and SC.) 
Existing project. The dam is a concrete gravity-type 
structure, 1,900 feet long with a maximum height of 204 
feet and a controlled spillway 568 feet in length. The 
concrete section is flanked on the east and west abutments 
by earth embankments totaling 13,390 feet in 
length and by a saddle dike 2,590 feet long also on the 
west side. Total length of the dam is 17,880 feet. At 
maximum power pool elevation of 660 feet the lake 
covers 55,950 acres. Total capacity of the lake is 
2,843,000 acre-feet of storage allocated as follows: flood 
control 293,000 acre-feet; hydroelectric power 1,416,000 
acre-feet; and dead storage 1,134,000 acre-feet. Four 
66,000-kilowatt generators having generating capacity of 
264,000 kilowatts were installed initially with provisions 
for a future unit. A fifth 80,000 kilowatt generating unit 
presently being installed which will increase the rated 
capacity to 344,000 kilowatts. All major supply contracts 
have been awarded. The general construction contract 
was awarded April 30, 1981. The scheduled completion 
of the fifth unit is December 1983 at a total estimated 
cost of $18,100,000. The notice of availability on the 
Final Environmental Statement covering this aspect of 
Hartwell appeared in the Federal Register June 15, 
1979 . Latest approved project estimate (August 1968) 
is $88,300,000. 
Local cooperation. None required. 
Operations and results during fiscal year. New 
work: Cost of activities during the fiscal year 
amounted to $6,383,095. Of this amount $668,084 was 
expended from Construction General funds (Code 710) 
for the construction of miscellaneous recreational facilities, 
and under the 1983 Job Bill Act $508,316 was ex- 
8-8

SAVANNAH, GA, DISTRICT 
pended for temporary employment. Also $3,313,119 was 
expended for construction for the additional fifth unit to 
the power dam. Major rehabilitation of the lower diversion 
dam at Clemson University was completed in FY 
83 with the upper dam work scheduled for completion in 
September 1984. The fiscal year rehabilitation cost 
amounted to $1,893,576. Gross generation of electrical 
energy for the period amounted to 523,185,000 kilowatthours, 
most of which was delivered to the Southeastern 
Power Administration. Flood damages prevented during 
the fiscal year amounted to $709,000. 
Maintenance: Operation and maintenance costs during 
the fiscal year amounted to $4,938,210 of which 
$92,972 was expended for temporary employment under 
the 1983 Job Bill Act. The notice on the Final Environmental 
Impact Statement on the operation and maintenance 
of Hartwell Dam and Lake appeared in the Federal 
Register August 21, 1978. 
Condition at end of fiscal year. Construction is 
complete except for providing additional recreational development. 
(See Table 8-A for Cost and Financial 
Statement.) 
15C. RICHARD B. RUSSELL DAM AND 
LAKE, GA AND SC, (FORMERLY 
TROTTERS SHOALS LAKE, 
GA AND SC) 
Location. Richard B. Russell Dam is on the Savannah 
River 275.1 miles above its mouth, 29.9 miles below 
Hartwell Dam and about 37.4 miles above Clarks Hill 
Dam. (See NOAA Survey maps of GA and SC.) 
Existing project. The authorized project provides 
for construction of Richard B. Russell Dam and Lake 
substantially in accordance with the recommendations of 
the Chief of Engineers at an estimated cost of 
$84,900,000. The latest approved (FY 83) cost estimate 
for the project is $525,000,000, of which $430,453,000 is 
for construction, $29,107,000 for lands and damages, and 
$65,440,000 for engineering and design and supervision 
and administration. Approval was received January 1977 
to include minimum provisions for pumped storage. A 
notice of availability of a Final Environmental Impact 
Statement covering pumped storage was published in 
the Federal Register February 18, 1977, and October 
26, 1979. A notice of availability on the Final Supplement 
to the Environmental Impact Statement on Fish 
and Wildlife Mitigation for the Russell project appeared 
in the Federal Register on December 11, 1981. 
Operations and results during fiscal year. New 
Work: Contracts were awarded during the fiscal year 
as follows: Calhoun Falls permanent pump station 
awarded December 3, 1982; oxygenation distribution 
system awarded January 12, 1983; conventional and 
pump storage SCADA equipment awarded March 31, 
1983; Abbeville pump station awarded April 8, 1983; reservoir 
topping and flotation removal awarded April 8, 
1983; Georgia State roads awarded June 7, 1983; initial 
recreational facilities, Georgia, awarded June 7, 1983; 
breakwater and shoreline protection awarded June 7, 
1983; South Carolina accessroads to boat ramps 1, 2, 3, 
awarded June 22, 1983; and Abbeville dewatering facilities 
awarded September 15, 1983. Fiscal year cost for 
land acquisition and associated cost amounted to 
$621,800. Relocation of Georgia State roads cost was 
$818,700. Relocation of South Carolina State roads 
amounted to $249,100. Relocation of Elbert County 
roads cost $232,500. Road relocation agreements cost 
amounted to $75,000. Relocation of Seaboard Coast Line 
Railroad was $617,100. Seaboard Coast Line relocation 
agreement cost was $16,200. Relocation of group IV 
cemeteries cost amounted to $56,200. Electrical and 
telephone relocation agreements cost $118,700. Relocation 
of Abbeville pump station amounted to $498,200. 
Relocation of Calhoun Falls pump station cost amounted 
to $336,000. Other relocation costs amounted to $60,400. 
Group I reservoir clearing cost was $608,700. Group II 
reservoir clearing amounted to $2,041,300. Reservoir 
topping and flotation removal cost was $900,000. 
Oxygenation distribution and diffusion system was 
$1,000,000. Earth embankment cost amounted to 
$12,143,700. Instrumentation cost was $182,200. Powerhouse 
cost amounted to $28,519,900. Turbines 
amounted to $5,559,300. Concrete dam cost was 
$4,205,100. Generators amounted to $2,000,000. Governors 
cost amounted to $510,700. Switchgear and phase 
bus amounted to $710,000. Main control switchboards 
amounted to $450,000. Repair contraction joint end seals 
cost was $56,200. Repair contraction joint waterstops 
cost amounted to $204,400. Powerhouse crane cost was 
$103,000. Draft tube gantry crane cost amounted to 
$127,000. Conventional and pump storage SCADA 
amount was $700,000. Motor control centers amounted 
to $73,200. Oil Circuit breakers and disconnect cost was 
$1,100,000. Transformers cost amounted to $1,700,000. 
All other powerplant equipment amounted to $32,200. 
Bobby Brown State Park road cost amounted to 
$91,900. Initial recreational facilities in South Carolina 
was $2,300,200. South Carolina access road to boat 
ramps amounted to $300,000. Initial recreational facilities 
in Georgia cost was $500,000. Cultural resources 
amounted to $350,200. Operational boat ramps cost 
amounted to $261,100. Permanent operating equipment 
was $115,700. Engineering and design and supervision 
and administration amounted to $7,050,201. Undistributed 
construction cost for the fiscal year amounted to 
$343,400. Design memorandums submitted during the 
fiscal year were: Georgia boat ramps, South Carolina 
boat ramps, and Lake Secession dewatering structures. 
Total cost for the fiscal year amounted to $77,939,501. 
Maintenance: The operation and maintenance cost 
for the fiscal year amounted to $371,704. 
Condition at end of fiscal year. The project is 67 
percent complete. 
Costs of project to" September 30, 1983, were 
$359,469,788 of which $358,799,952 is for new work and 
$669,836 for maintenance. (See Table 8-A for Cost and 
Financial Statement.) 
8-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
16. WEST POINT LAKE 
CHATTAHOOCHEE RIVER 
BASIN, GA AND AL 
The West Point Lake located on the Chattahoochee 
River, 2.8 miles upstream from West Point, GA, was 
authorized by the Flood Control Act of 1962 (H. D. 570, 
87th Cong., 2d sess.). The project was designed and 
constructed for flood control, power, recreation, fish and 
wildlife development and streamflow regulation for 
downstream navigation. Design and construction was 
accomplished by Savannah District for Mobile District. 
For complete information see Mobile District. 
General Investigation 
17. SURVEYS 
Fiscal year cost was $1,148,203, of which $353,546 
was for navigation studies; $665,575 for flood control 
studies; and $72,365 for special investigations; $56,581 
for coordination with other agencies; and $136 for supplemental 
preauthorization studies. 
18. COLLECTION AND STUDY 
OF BASIC DATA 
Work was continued under the Flood Plain Management 
Services on the compilation of information on 
floods, potential flood damages, and identification of 
those areas subject to inundation. Fiscal year expenditures 
for these activities were as follows: guides, pamphlets, 
and supporting studies, $4,580; flood plain management 
services, $111,308, and technical services, 
$114,847. Flood plain management services included responses 
to other Federal agencies to aide them in fulfilling 
the requirements of Executive Order 11988 (Management 
of Base Flood Area). Through the Technical 
Sevices Program, flood problems in several areas were 
analyzed and possible improvements were identified. 
Through a Memorandum of Agreement with Centers for 
Disease Control (CDC), flood plain data for their 
Chamblee, Georgia, property was developed. Study 
costs were shared with CDC paying for required field 
data ($5,000) and the District's FPMS Technical Services 
program paying for the technical analysis. During 
the latter part of the fiscal year, the Flood Plain Management 
'Services Branch began the Atlanta, Georgia, 
Flood Insurance Study for the Federal Emergency Management 
Agency. The estimated cost of the study is 
$313,000 and is expected to take 18 months to complete. 
The national program for inspection of non-Federal 
dams cost $5,551. The cost for hydrologic studies was 
$14,847. The total fiscal year cost for collection and 
study of basic data was $251,133. 
19. RESEARCH AND DEVELOPMENT 
No funds were expended for research and development 
during the fiscal year. 
20. CONTINUATION OF PLANNING 
AND ENGINEERING 
The Savannah Harbor Widening Study under Continuation 
of Planning and Engineering was continued 
during the fiscal year and the cost amounted to 
$155,075. The recommended plan provides for modification 
of the harbor by widening the navigation channel 
between the present upstream limit of the 500-foot 
channel (Fig Island Turning Basin) and the Kings Island 
Turning Basin from 400 to 500 feet. This will decrease 
the hazard of handling large vessels and reduce shipping 
transit time. Cost of the study to September 30, 1983, 
was $311,140. 
8-10

SAVANNAH, GA, DISTRICT 
TABLE 8-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 80 FY 81 FY 82 FY 83 Sept. 30, 1983 
1. Altamaha, Oconee 
and Ocmulgee Rivers, 
GA 
2. Aquatic Plant 
Control (1965 
R&H ACT) 
3. Atlantic Intracoasal 
Waterway between 
Norfolk, VA, and the 
St. Johns River, FL 
4. Brunswick Harbor, 
GA 
5. Savannah Harbor, 
GA 
6. Savannah River 
below Augusta, 
GA 
10. Tybee Island, GA 
11. Broadway Lake, 
SC 
12. Inspection of 
Completed Flood 
Control Works 
15A. Clarks Hill Lake, 
GA and SC 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
- 6,000 
- 5,821 
85,000 
30,004 
863,000 
905,951 
142,000 
184,067 
3,612,200 
3,588,806 
450,000 
130,732 
6,454,000 
5,997,994 
1,286,200 
1,156,639 
95,885 
10,000 
9,623 
374,900 
146,287 
4,641,000 
4,346,877 
43,000 
69,207 
207,200 
203,626 
18,800 
64,801 
894,000 
493,921 
191 
40,000 
36,731 
75,000 
481,164 
849 - 
1,261,000 5,691,000 3,491,( 
731,353 3,339,781 5,221, 
2,748,000 
1,963,949 
8,107,000 
8,108,330 
542,000 
677,332 
15,000 
85,433 
15,000 
13,414 
200,000 
350,856 
1,100,000 -319, 
1,938,034 -112, 
6,636,000 9,418, 
5,642,853 6,986,E 
404,000 
362,725 
821,4571 
821,4571 
1,916,1822,3 
1,913,9572,3 
252,159 
245,636 
958,0964 
958,0964 
13,926,9215 
13,914,6615 
- 4,573,6086 
- 4,573,4336 
000 36,499,1017 
253 35,322,2667 
000 46,187,7218 
480 46,185,7438 
000 125,010,9409 
914 121,073,5829 
- 6,740,03110 
- 6,740,03110 
348,000 14,101,492 
171,452 13,835,156 
- 4,542 
1,000 
1,838 
85,000 
4,731 
727,000 1,050,000 
332,011 593,200 
4,841,500 4,885,360 6,397,700 
4,573,710 5,397,853 5,629,293 
2,530,30013 
2,527,09513 
99,000 
99,000 
167,518 
86,923 
84,841,29011 
83,901,80811 
48,277,154's15 
46,693,68115 
8-11

TABLE 8-A 
REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1983 
COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 80 FY 81 FY 82 FY 83 Sept. 30, 1983 
15B. Hartwell Lake, GA New Work: 
and SC Approp. 2,043,300 3,865,000 8,950,000 5,334,000 110,564,30712,14 
Cost 1,223,614 4,448,634 8,232,445 4,489,519 108,350,91012,14 
Maint. 
Approp. 4,875,000 4,826,500 4,768,760 4,411,359 43,732,12616 
Cost 4,709,332 5,267,740 4,471,416 4,938,210 43,098,97816 
Major Rehab. 
Approp. - - 3,500,000 1,700,000 5,200,000 
Cost - - 1,974,609 1,893,576 3,868,185 
15C. Richard B. Russell New Work: 
Dam and Lake, GA Approp. 67,191,000 67,717,000 75,030,000 78,469,000 359,789,509 
and SC (Formerly Cost 66,838,820 68,346,895 75,048,353 77,939,501 358,799,952 
Trotters Shoals) Maint. 
Approp. - - 328,000 396,000 724,000 
Cost - - 298,132 371,704 669,836 
1. Includes $760,610 for previous projects. Funds. Includes $4,558,613 appropriated under Code 710 of 
2. Includes $111,950 for previous projects. which $4,485,553 has been expended. Also includes $1,000,000 
3. Does not include $69,356 contributed funds. appropriated and $132,948 expended under the '83 Job Bill 
4. Includes $194,497 for previous projects. Act. 
5. Includes $134,798 for previous projects. 12. Does not include $276,200 accelerated Public Works 
6. Includes $643,465 for previous projects and includes Funds. Includes $4,174,000 appropriated under Code 710 of 
$97,521 expended from Public Works Funds for existing pro- which $4,048,424 has been expended. Also includes $545,000 
ject. Does not include $10,000 contributed funds. appropriated and $508,316 expended under the '83 Job Bill 
7. Includes $54,414 for previous projects. Includes Act. 
$4,995 expended from Public Works Funds for existing pro- 13. Does not include $2,024,856 contributed funds. 
ject. Excludes $252,557 contributed by Brunswick and Ga. 14. Includes $210,000 appropriated for AE&D for 5th 
Port Authorities. Also includes $2,150,000 appropriated and unit of which $210,000 has been expended and $12,895,000 ap- 
$2,149,999 expended under '83 Job Bill Act. propriated for construction of 5th Unit of which $11,381,006 
8. Includes $7,260,384 for previous projects. Does not in- has been expended. 
clude $46,847 for removal of sunken vessels and $1,886,413 15. Includes $75,360 appropriated and $95,978 expended 
contributed funds. under special recreation use fees. Also includes $736,000 ap- 
9. Includes $298,894 for previous projects. Does not in- propriated and $368,298 expended under the '83 Job Bill Act. 
dude $852,858 contributed funds. 16. Includes $132,519 appropriated and $139,633 ex- 
10. Includes $93,480 for previous projects. Includes pended under special recreation use fees. Also includes 
$1,634,562 from Public Works Fund. $93,000 appropriated and $92,972 expended under the '83 Job 
11. Does not include $395,634 accelerated Public Works Bill Act. 
TABLE 8-B AUTHORIZING LEGISLATION 
See Date of 
Section Authorized 
in Text Act Project and Work Authorized Documents 
1. July 25, 1912 
and March 2, 1945 
2. Oct. 27, 1965 
Section 302 
ALTAMAHA, OCONEE AND OCMULGEE RIVERS, GA. 
Channel 3 feet deep and 60 to 100 feet wide. 
Provides for control and progressive eradication of noxious" 
aquatic plant growths. 
HD 443,62d Cong., 2d sess. 
HD 610,77th Cong., 2d sess. 
HD 251, 89th Cong., 1st sess. 
8-12

SAVANNAH, GA, DISTRICT 
TABLE 8-B (continued) AUTHORIZING LEGISLATION 
See Date of 
Section Authorized 
in Text Act Project and Work Authorized Documents 
3. June 3, 1896 
Mar. 3, 1899 
July 13, 1892 
Mar. 3, 1905 
July 25, 1912 
Aug. 8, 1917 
Mar. 2, 1919 
Mar. 2, 1919 
Mar 3., 1925 
July 3, 1930 
Aug. 26, 1937 
Aug. 26, 1937 
June 20, 1938 
Mar. 2, 1945 
Oct. 15, 1981 
4. Mar. 3, 1879 
Mar 2, 1907 
Mar. 2, 1919 
July 3, 1930 
July 3, 1930 
June 20, 1938 
May 17, 1950 
Oct. 22, 1976 
ATLANTIC INTRACOASTAL WATERWAY 
BETWEEN NORFOLK, VA., AND ST. JOHNS 
RIVER, FLA., (SAVANNAH DISTRICT) 
Section from Beaufort, S.C. to Savannah, Ga. Route No. 2 
adopted. 
Route No. 1 adopted. 
Section from Savannah, Ga. to Fernandina, Fla. Original 
7-foot channel. 
Provided for Skidaway Narrows. 
Incorporated alternative routes previously improved as 
separate projects and the auxiliary channels. 
Section from Cumberland Sound, Ga. and Fla. to St. Johns 
River, Fla. Consolidation of the 3 sections shown above, 
into "Waterway between Beaufort, S.C. and St. Johns River, 
Fla." 
Section from Beaufort, S.C. to Cumberland Sound, Ga. and 
Fla. Removing logs and snags from Generals Cut. 
Improving Back River to provide a channel 7 feet deep and 
150 feet wide. 
Channel 75 feet wide between Beaufort, S.C., and Savannah, 
Ga. 
Channel from Baileys Cut to Dover Creek. 
A 7-foot protected channel around St. Andrews Sound. 
A 12-foot channel between Beaufort, S.C., and Savannah, Ga. 
via Beaufort River and Port Royal Sound. 
A 12-foot channel between Savannah, Ga., and Fernandina, 
Fla., various cutoffs; and anchorage basin at Thunderbolt, 
Ga. 
An alternate route 9 feet deep and 150 feet wide in that 
part of Frederica River, Ga., not now traversed by the main 
route, at no additional cost to the United States. 
Main channel relocated from Frederica River to 
Mackay River in the vicinity of Torras Causeway. 
BRUNSWICK HARBOR, GA 
Construction of East River jetty. 
Channels in the inner and outer harbors of 30-foot depth 
at mean high water, with widths varying from 150 
feet in Academy Creek to 400 feet across 
the outer bar, extension of training wall in East River 
and construction of two spurdikes. 
Channels 27 feet deep at mean low water over the 
bar and at Brunswick point; and 24 feet deep at 
mean low water in the inner harbor and provides 
for a cut from Academy Creek to Turtle River, if 
deemed advisable. 
A channel in Back River 20 feet deep and 150 feet wide. 
Increased Channel dimensions of the bar, Brunswick Point, 
East River, and Turtle River, as given in the then 
existing project. 
A 10-foot channel in Terry Creek. 
Increased channel dimensions of the bar, St. Simons 
Sound, Brunswick River, East River, and Turtle River, 
as given in the existing project. 
Provides for Phase I AE&D studies for deepening portions 
of existing harbor (East River and Entrance Channel) and 
for provision of a navigation channel to Colonels Island. 
HD 295, 53d Cong., 3d sess. 
HD 295, 53d Cong., 3d sess. 
HD 41, 52d Cong., 1st seas. 
HD 450, 58th Cong., 2d sess. 
HD 1236, 60th Cong., 2d sess. 
HD 581, 63d Cong., 2d sess. 
HD 1391, 62d Cong., 3d sess. 1 
SD 178, 68th Cong., 2d sess. 
SD 43, 71st Cong., 2d sess.' 
Senate committee print, 74th 
Cong., 1st sess. 
Rivers and Harbors Committee 
Doc. 6, 75th Cong., 1st sess. 
HD 618, 75th Cong., 3d sess. 
HD 114, 77th Cong., 1st sess. 
Project authorized by 
Chief of Engineers under the 
Small Navigation Project 
Authority, Sec. 107, PL 
86-645 as amended. 
Annual Report, 1880, p. 959 
HD 407, 59th Cong., 1st sess. 
HD 393, 64th Cong., 1st sess. 
SD 57, 71st Cong., 2d sess. 1 
SD 132, 71st Cong., 2d sess. 1 
HD 690, 75th Cong., 3d sess. 1 
HD 110, 81st Cong., 1st sess.1 
Report of Chief of Engineers 
dated Aug. 18, 1976. 
8-13

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1983 
TABLE 8-B (continued) AUTHORIZING LEGISLATION 
See Date of 
Section Authorized 
in Text Act Project and Work Authorized Documents 
5. Mar. 2, 1907 
June 25, 1910 
July 25, 1912 
Aug. 8, 1917 
Jan. 21, 1927 
Jan. 21, 1927 
July 3, 1930 
Aug. 30, 1935 
Mar. 2, 1945 
Nov. 7, 1945 
July 24, 1946 
Sep. 3, 1954 
Oct. 23, 1962 
Oct. 27, 1965 
SAVANNAH HARBOR, GA. 
Tentative provisions for a 26-foot channel from the 
Quarantine Station to the Seaboard Air Line Ry. Bridge. 
Definite provision for the 26-foot channel. 
A 21-foot channel from the Seaboard Air Line Ry. Bridge 
to the foot of Kings Island. 
A 30-foot depth from the sea to the Quarantine Station. 
A 21-foot channel above Kings Island. 
Channel 30 feet deep, with general width 50 feet, from the 
ocean to the Quarantine Station, thence 26 feet deep, 
general width 400 feet, to the Seaboard Air Line Ry. Bridge, 
thence 21 feet deep and 300 feet wide to Kings Island. 
Widening at West Broad and Barnard Streets; anchorage 
basin; mooring dolphins; regulating dam across South 
Channel; relocation of the Inland Waterway; dredging Drakies 
Cut to 13 feet; widening to 525 ft. at Kings Island; extension 
of training walls, revetments, and jetties. Consolidation of 
projects relating to Savannah Harbor. 
Channel 26 feet deep and 300 feet wide from the Seaboard 
Air Line Ry. Bridge to the foot of Kings Island. 
Authorized the 30-foot project and eliminated from the project 
(a) the relating dam across South Channel; (b) the 
relocation of the Inland Waterway; and (c) the further 
extension of training walls, revetments, and jetties. 
Deepening the channel and turning basin above the Seaboard 
Air Line Ry. Bridge from 26 to 30 feet and widening the 
channel opposite the Atlantic Coast Line Terminals to a 
maximum of 550 feet for a length of 5,000 feet. 
Deepening the channels to 36 feet deep and 500 feet wide 
across the ocean bar; 34 feet deep and generally 400 feet 
wide, increased to 550 feet opposite the Atlantic Coast 
Line Terminals, with a turning basin 34 feet deep at the 
Mexican Petroleum Corp. Refinery; and with such modifications 
thereof as the Secretary of War and the Chief of 
Engineers may consider desirable. 
Extending channel 30 feet deep, 200 feet wide, upstream 
from Atlantic Creosoting Terminal to a point 1,500 feet 
below the Atlantic Coastal Highway Bridge, with turning 
basin 30 feet deep at upper end. 
Deepening the channel to 34 feet and widening to 400 feet 
from the upper end of the presently authorized 34-foot 
channel in the vicinity of the American Oil Company 
Refinery wharf, to the Savannah Sugar Refining Corp. 
with a turning basin at the upper end of the proposed 
improvement, made by widening the channel to 600 feet 
for a length of 700 feet and providing approaches. 
Enlargement of turning basin near Kings Island to a width 
of 900 feet and a length of 1,000 feet, with suitable 
approaches, at a depth of 34 feet. 
Deepening the bar channel from 36 feet to 40 feet, the 
channel between the bar channel and Garden City Terminal 
from 34 feet to 38 feet, and the channel from the Garden 
City Terminal to the vicinity of the Savannah Sugar Refining 
Corp., from 30 feet to 36 feet; widening the bar channel 
from 500 feet to 600 feet, the channel between Fort Pulaski 
and Atlantic Coast Line Terminal from 400 feet to 500 feet, 
and the channel between Garden City Terminal and the 
Savannah Sugar Refining Corp. from 200 feet to 400 feet; 
providing necessary wideners of the bends; constructing a 
new turning basin 900 feet wide by 1,000 feet long by 34 
feet deep opposite the Atlantic Coast Line Terminals; and 
enlargement of existing turning basin at the American Oil 
Company Terminal from 600 feet wide by 600 feet long to 
900 feet wide by 1,000 feet long. 
8-14 
HD 181, 59th Cong., 1st sess. 
HD 563, 62d Cong., 2d sess. 
HD 1471, 64th Cong., 2d sess. 
HD 261, 69th Cong., 1st sess. 
HD 262,69th Cong., 1st sess. 
SD 39, 71st Cong., 1st sess. 
HD 276, 73d Cong., 2d sess. 
HD 283, 76th Cong., 1st sess. 1 
HD 227, 79th Cong., 1st sess. 1 
HD 678, 79th Cong., 2d sess. 1 
HD 110, 83d Cong., 1st sess. 1 
SD 115, 87th Cong., 2d sess. 
HD226,89th Cong., 1st sess.

SAVANNAH, GA, DISTRICT 
TABLE 8-B (continued) AUTHORIZING LEGISLATION 
See Date of 
Section Authorized 
in Text Act Project and Work Authorized Documents 
Oct. 27, 1965 
SPWC Resolution 
June 15, 1976 
and HPWTC of 
June 9, 1976 
under authority 
of Sec. 201 of 
Flood Control 
Act of 1965 
6. Sep. 19, 1890 
June 25, 1910 
July 3, 1930 
Aug. 30, 1935 
Aug. 26, 1937 
May 17, 1950 
10. SPWC Resolution 
June 22, 1971 and 
Providing sediment control works consisting of tide 
gate structure across Back River; sediment basin 40 
feet deep, 600 feet wide about 2 miles long, 
with entrance channel 38 to 40 feet deep and 300 feet wide; 
drainage canal across Argyle Island 15 feet deep and 300 
feet wide; control works and canals for supplying fresh 
water to Savannah National Wildlife Refuge; and 
facilities to mitigate damages to presently improved 
areas other than refuge lands. 
Provided for modification of the existing project to include 
(1) incorporation of the LASH Turning Basin as an 
element of the existing Federal navigation project for 
maintenance purposes, (2) enlargement of Kings Island 
Turning Basin to 1,500 feet by 1,600 feet by 38 feet. 
SAVANNAH RIVER BELOW AUGUSTA, GA. 
For a 5-foot channel. 
Special improvement by bank protection work of 20 or 25 
miles of the river immediately below Augusta. 
The present 6-foot channel project and Lock and Dam. 
Provision made for locating the lock and dam at New 
Savannah Bluff. 
Conditions of local cooperation modified. 
Provides for a 9-foot channel 
TYBEE ISLAND, GA. 
Project will provide for beach erosion control, consisting 
of beach restoration, groin system, and periodic beach 
HPWC of June 23, nourishment. 
1972 under authority 
of Sec. 201 
of FC Act of 
1965. 
HD 223, 89th Cong., 1st sess. 
HD 94-520, 94th Cong. 
dated June 8, 1976. 
HD 255, 51st Cong., 2d sess. 
and Annual Report, 1890; 
p. 1328 
HD 962, 60th Cong., 1st sess. 
HD 101, 70th Cong., 1st sess. 
Senate Committee Print, 
73d Cong., 2d sess. 
Rivers and Harbors Comn., 
Doc. 39, 75th Cong., 1st sess. 
SD 6, 81st Cong., 1st sess. 
HD 105, 92d Cong. 
11. Water Resources 
Development Act 
of March 7, 1974. 
15A. Flood Control Act 
of Dec. 22, 1944 
15B. Flood Control Act 
of May 17, 1950. 
Flood Control Act 
of July 3, 1958. 
Water Resources 
Development Act 
of 1976. 
15C. Flood Control Act 
of Nov. 7, 1966. 
BROADWAY LAKE, S.C. 
Provided for undertaking a demonstration project for the 
removal of silt and aquatic growth from Broadway Lake. 
CLARKS HILL LAKE, GA. AND S.C. 
Approved the general plan for the comprehensive development 
of the Savannah River Basin and provided for construction 
of the Clarks Hill Project. 
HARTWELL LAKE, GA. AND S.C. 
Provided for construction of Hartwell Project. 
Provided for the completion of the Harwell Project. 
Provides for installation of 5th unit. 
RICHARD B. RUSSELL DAM AND LAKE, GA. 
Provided for construction of the Trotters Shoals Project. 
PL 93-251, 93rd Cong. 
HD 657, 78th Cong., 2d sess. 
PL 534, 78th Cong., 2d sess. 
HD 657, 78th Cong., 2d sess. 
PL 516, 81st Cong., 2d sess. 
PL 85-500, 85th Cong., 
2d sess. 
PL 94-587, Sec. 182b. 
85th Cong. 
SD 52, 89th Cong., 1st sess. 
1. Contains latest published maps. 
8-15

TABLE 8-C 
REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1983 
OTHER AUTHORIZED NAVIGATION PROJECTS 
(See Section 8 in text) 
For Last Cost to Sep. 30, 1983 
Full Report 
See Annual Operation and 
Project Status Report for Construction Maintenance 
Aquatic Plant Control (R&H Act 1962) Completed 1968 25,700- 
Cedar Point, GA Completed 1982 656,233 
Darien Harbor, GA Completed 1975 199,723 185,433 
Fancy Bluff Creek, GA1 Completed 1935 8,000 7,200 
St. Marys River, GA and FL, and North Completed 1951 15,688 69,936 
River; GA 
Sapelo Harbor, GA2 ,3 Completed 1929 17,906 19,594 
Satilla River, GA1 Completed 1951 9,452 57,172 
Savannah River above Augusta, GA2'3'4 See Notes 1929 69,600 5,870 
Savannah River at Augusta, GA2'3 '5 See Notes 1929 200,556 17,444 
1. Channel adequate for commerce. two power dams which submerged much of the work under 
2. Project recommended for abandonment in H.D. 467, the present and former projects, this improvement cannot be 
69th Cong., 1st sess. completed as originally planned. 
3. No commerce reported. 5. Excludes $185,000 contributed funds ($172,151 for 
4. About 84 percent completed. Owing to construction of construction and $12,849 for operation and maintenance). 
TABLE 8-D OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(See Section 13 In text) 
For Last Cost to Sep. 30, 1983 
Full Report 
Project See Annual Operation and Status Report for Construction Maintenance 
Augusta, Savannah River, GA Completed 1941 643,016 38,242 
Curry Creek Dam and Lake, GA1 See Note 1974 - - 
Dunn Branch, Woodbine, Camden Completed 1977 132,640 5,219 
County, GA 
Macgn, GA Completed 1955 380,043 38,243 
Peacock Creek, Liberty County, GA Completed 1976 582,163 5,219 
1. Feasibility report completed. Project not authorized 
for construction. 
8-16

TABLE 8-E 
SAVANNAH, GA, DISTRICT 
SAVANNAH RIVER BASIN, GA AND SC 
DAMS AND LAKES 
(See Section 15 In text) 
Estimated Cost 
Name River Federal Non-Federal Total 
Clarks Hill, GA and S.C. Savannah $79,156,0004 $79,156,0001,4 
Hartwell, GA and S.C. Savannah 89,240,000 89,240,0002 
Goat Island, GA and S.C.5 Savannah 36,400,000 36,400,000( 
Middleton Shoals, GA and S.C.s Savannah 16,500,000 16,500,0003 
Chattooga Units (4), GA and S.C. Chattooga 41,700,000 41,700,0003 
Tallow Hill, GA Broad 39,000,000 39,000,000 
Anthony Shoals, GA Broad 18,100,000 18,100,000 
Newry-Old Pickens, S.C. 6 Keowee 29,500,000 29,500,0003 
1. Final cost. (Excludes $127,000 for preauthorization 
study.) 
2. Approved Aug. 1963. (Excludes $73,000 for preauthorization 
study.) 
3. Approved July 1954. 
4. Excludes Code 710 funds. 
5 Replaced by Richard B. Russell Dam and Lake (formerly 
Trotters Shoals Lake). 
6. Site of Duke Power Co. Keowee-Toxaway Project. 
8-17

JACKSONVILLE, FLA. DISTRICT* 
With the exception of a small area in the 
northeastern section of Florida, this district comprises 
a portion of south-central Georgia and all of 
peninsular Florida, embracing the watersheds 
tributary to the Atlantic Ocean and the Gulf of 
Mexico from, and including the harbor at Fernandina, 
Florida, to and including the Aucilla River. 
It also includes Puerto Rico and the Virgin 
Islands. 
IMPROVEMENTS 
Navigation Page 
1. Aquatic Plant Control (R&H Act of 
1965) .............................. 9-2 
2. Arecibo Harbor, P.R ................. 9-2 
3. Atlantic Intracoastal Waterway 
between Norfolk, Va. and St. 
Johns River, Fla..................... 9-2 
4. Canaveral Harbor, Fla ................ 9-3 
5. Channel from Naples to Big Marco Pass, 
Fla. ................................ 9-3 
6. Charlotte Harbor, Fla................. 9-4 
7. Clearwater Pass, Fla..................9-4 
8. Cross Florida Barge Canal............ 9-5 
9. Fernandina Harbor, Fla .............. 9-5 
10. Fort Myers Beach, Fla................ 9-5 
11. Fort Pierce Harbor, Fla .............. 9-6 
12. Intracoastal Waterway, 
Caloosahatchee River to 
Anclote River, Fla ................... 9-6 
13. Intracoastal Waterway, Jacksonville 
to Miami, Fla......................... 9-7 
14. Jacksonville Harbor, Fla............9-8 
15. John's Pass, Fla...................... 9-8 
16. Longboat Pass, Fla .................. 9-9 
17. Mayaguez Harbor, P.R ............... 9-9 
18. Miami Harbor, Fla ........... ... 9-9 
19. New Pass, Sarasota, Fla. ............. 9-10 
20. Okeechobee Waterway, Fla........... 9-11 
21. Oklawaha River, Fla ................. 9-11 
22. Palm Beach Harbor, Fla. ............. 9-12 
23. Ponce de Leon Inlet, Fla.............. 9-12 
24. Ponce Harbor, P.R....................9-12 
25. Port Everglades Harbor, Fla.......... 9-13 
26. Removal of Aquatic Growth 
From Navigable Waters in the 
State of Florida ...................... 9-14 
27. St. Augustine Harbor, Fla............. 9-14 
28. St. Johns River, Jacksonville 
to Lake Harney, Fla................... 9-15 
29. St. Lucie Inlet, Fla................... 9-15 
30. St. Petersburg Harbor, Fla........... 9-16 
31. San Juan Harbor, P.R. ................ 9-16 
32. Tampa Harbor, Fla. .................. 9-17 
33. Navigation Projects on which 
Reconnaissance and Condition 
Surveys only were Conducted 
during Period ...................... 9-19 
Navigation (cont.) Page 
34. Other Authorized Navigation 
Projects ........................ ... 9-19 
35. Navigation Work under Special 
Authorization ....................... 9-19 
Beach Erosion Control 
36. Brevard County, Fla. ................ 9-19 
37. Broward County, Fla. Beach 
Erosion Control and Hillsboro 
Inlet, Fla., Navigation Project ......... 9-19 
38. Dade County, Fla..................... 9-20 
39. Duval County, Fla. .................. 9-21 
40. El Tuque Beach, P.R ................. 9-21 
41. Fort Pierce, Fla. .................... 9-22 
42. Manatee County, Fla. ................ 9-22 
43. Palm Beach County, Fla. from 
Martin County line to Lake Worth 
Inlet and from South Lake Worth 
Inlet to Broward County line ......... 9-23 
44. Pinellas County, Fla ................. 9-23 
45. Punta Salinas, P.R.................... 9-23 
46. Other Authorized Beach Erosion 
Control Projects .................... 9-24 
47. Beach Erosion Control Activities 
under Special Authorization........... 9-24 
Flood Control 
48. Central and Southern Florida ......... 9-24 
49. Four River Basins, Fla. .............. 9-26 
50. Portugues and Bucana Rivers, P.R...... 9-27 
51. Inspection of Completed Flood 
Control Projects ................. 9-27 
52. Other Authorized Flood Control 
Projects ........................... 9-27 
53. Flood Control Work under Special 
Authorization ...................... 9-27 
General Investigations 
54. Surveys ........................... 9-28 
55. Collection and Study of Basic Data...... 9-28 
*All cost and financial statements for projects are listed at the end of this chapter. All other tables are referenced in text and 
also appear at the end of this chapter. 
9-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Navigation 
1. AQUATIC PLANT CONTROL 
(R&H ACT OF 1965). 
Location Navigable waters, tributary streams, 
connecting channels, and other allied waters in 
Florida. 
Existing project. The authorized project provides 
for control and progressive eradication of 
water hyacinth, alligatorweed, Eurasian watermilfoil, 
and other obnoxious aquatic plant 
growths from navigable waters, tributary 
streams, connecting channels, and other allied 
waters of the United States, in combined interest 
of navigation, flood control, drainage, agriculture, 
fish and wildlife conservation, public health, and 
related purposes, including continued research 
for development of most effective and economical 
control measures in cooperation with other 
Federal and State agencies in accordance with 
report of Chief of Engineers, House Document 
251, 89th Congress, 1st session. The authorizing 
act provides that research and planning costs 
shall be borne fully by the United States. (See 
Table 9-B for Authorizing Legislation.) 
Local cooperation. Local interests must hold 
the United States free from damages that may occur 
from operations performed in connection with 
this project and contribute 30 percent of cost of 
operations. Compliance with requirements of 
local cooperation is on schedule. 
Operations and results during fiscal year. New 
work: There were 7,433 acres of hyacinth, 5,885 
acres of hydrilla, 1,33885 acres of minor plant and 
4,769 acres of hyacinth and waterlettuce mix controlled 
during the period. Costs incurred were 
$165,905 for engineering and $1,908,815 for operations. 
Condition at end of fiscal year. Operations by 
the Corps and the State of Florida are in progress, 
water hyacinths within Florida are under 
maintenance control. Hydrilla is continuing to 
spread throughout the state and is causing major 
problems in some areas. 
2. ARECIBO HARBOR, P. R. 
Location. The harbor is located on the north 
shore of Puerto Rico about 40 miles west of San 
Juan Harbor. (See Coast and Geodetic Survey 
Chart No. 908.) 
Previous project. For details see page 504 of 
1956 Annual Report. 
Existing project. The project provides for a 
channel 25 feet deep and 400 feet wide, with flare 
at entrance and widening at inner end to form a 
maneuvering area, and a stone breakwater 1,200 
feet long. Place of reference is mean low water. 
Mean tidal range is 1.1 feet. (See Table 9-B for 
Authorizing Legislation.) 
Local cooperation. Fully complied with to date. 
Non Federal contribution for new work was 
$288,000. 
Terminal facilities. A bulkhead wharf 688 by 
220 feet providing a deep water berthing space of 
approximately 500 feet, and a 300 by 100 foot 
transit shed. Facilities are considered adequate 
for existing commerce. 
Operations and results during fiscal year. 
Maintenance: Condition and operation studies for 
the year cost $1,914. Dredging by contract 
amounted to - $43,622. Engineering and design 
and supervision and administration costs were 
$78,075 and $5,907 respectively. 
Condition at end of fiscal year. Project was 
completed in 1944. Breakwater was repaired in 
1952. Wave action has since caused minor 
damage. Total Federal costs under existing project 
through September 30, 1983 were $1,128,075 
for new work and $1,769,901 for maintenance, a 
total of $2,897,976. 
3. ATLANTIC INTRACOASTAL WATERWAY 
BETWEEN NORFOLK, VA. AND 
ST. JOHNS RIVER, FLA. (JACKSONVILLE 
DISTRICT) 
Location. That part of Intracostal Waterway 
between southerly limit of Fernandina Harbor, 
Florida, at junction of Lanceford Creek and 
Amelia River, and St. Johns River, Fla. (See 
Coast and Geodetic Survey Chart No. 841-SC.) 
Previous project. For Details see page 605 of 
1938 Annual Report. 
Existing project. Channel 12, 90 to 150 feet 
widefrom Fernandina Harbor to St. Johns River 
about 22 miles long. Plane of reference is mean 
low water. Mean tidal range is 6 feet at Fernandina 
and 3.8 feet at St. Johns River. (See Table 
9-B for Authorizing Legislation.) 
Existing project was authorized by River and 
Harbor Acts of 1913 (HD 898/62/2) and 1938 (HD 
618/75/8). 
Local cooperation Fully complied with to date. 
Terminal facilities. There is a commercial 
marina located at Sisters Creek. No other 
facilities exist along this section of the waterway 
and none are currently required. 
Operations and results during fiscal year. 
Maintenance: Dredging by contract amounted to 
$2,967,517. Engineering and design and supervision 
and administrative costs were $42,579 and 
$111,007, respectively. 
9-2

JACKSONVILLE, FLA. DISTRICT 
Condition at end of fiscal year. Project was 
completed in 1941. Total costs under the existing 
project to September 30, 1983, have been 
$263,659 for new work and $4,831,654 for 
maintenance, a total of $5,095,313. 
4. CANAVERAL HARBOR, FLA. 
Location The harbor is located on the east 
coast of Florida in Canaveral Bight, about 146 
miles south of the entrance to Jacksonville Harbor 
and 69 miles north of the entrance to Fort 
Pierce Harbor. (See Coast and Geodetic Survey 
Charts Nos. 456 and 1245.) 
Existing project. The authorized project provides 
for maintenance of the 37-foot and 36-footdepth 
entrance channel and 35-foot-depth turning 
basin; construction and operation of a sand 
transfer plant; relocation of the perimeter dike 
about 4,000 feet westward and extension of the 
harbor westward; two entrance jetties 100 feet 
long (constructed of native stone core and granite 
sides and cap); a lock; a channel and turning basin 
31 feet deep near the relocated dike; and a barge 
canal 12 by 125 feet from the turning basin to the 
Atlantic Intracoastal Waterway. Plane of 
reference is mean low water (ocean) for harbor 
dike and lock, and mean low water (Banana River) 
for barge canal. The project is about 11.5 miles 
long. 
Mean tidal range is 3.5 feet at the entrance and 
practically non-tidal in Banana and Indian Rivers. 
(See Table 9-C for Data Relative to Lock.) 
Estimated cost (Oct. 1982 price levels) of the 
1962 modification to the project is $24,400,000 
Federal cost and $1,214,000 non-Federal cost 
($305,000 contributed funds and $909,000 other 
costs); $700,000 costs to NASA and $47,000 costs 
to U.S. Coast Guard. (See Table 9-B for Authorizing 
Legislation.) 
Local cooperation Local interests must: provide 
all lands, rights-of-way, spoil-disposal areas, 
retaining dikes, and embankments; hold United 
States free from damages; provide and maintain 
four-lane bridge and roadway subject to Federal 
contribution of 65.3 percent of cost of constructing 
bridge and 51.2 percent of constructing roadway; 
provide public terminal and transfer 
facilities; and make alterations as required in 
berthing facilities. For further details see Senate 
Document 140, 87th Congress, 2d session. Non- 
Federal contribution for new work is $289,000. 
Terminal facilities. On the south side of the 
port, there is a 1,060-foot marginal wharf supported 
by 108,000 square feet of general cargo 
warehouse space and 100,000 square feet of 
freezer warehouse space. 
Drafts along the wharf are 35 feet at the east 
end and 31 feet at the west end. Two tanker 
berths on the south side are utilized for bunkers, 
petroleum products offloading and bulk cement. 
Draft is 35 feet at both piers. 
Two cruise ship berths totaling 1200 feet long 
by 41-foot depth and two 8800 square foot cruise 
terminals are also located on the south side. The 
western cruise ship berth is equiped with a roll 
on/off ramp and is adjacent to 20 acres of trailer 
storage area. 
The north side has three general cargo 
wharves totalling 1,240 linear feet, with 35-foot 
draft at all three. These facilities are used for 
general cargo, fresh citrus, scrap, visiting 
passenger vessels and lay berths for military 
vessels. One berth is dedicated to a home-ported 
cruise line offering daily service. Another bulk cement 
facility is located on the north side. 
Existing facilities are becoming saturated and 
rapid commercial expansion in the area will soon 
require the construction of additional facilities. 
Operations and results during fiscal year. New 
Work: Engineering and design and supervision 
and administration costs were $124,129 and 
$8,525, respectively, for the harbor extension. 
Maintenance: Maintenance and operation of 
locks amounted to $232,055 for the fiscal year. 
Operation and maintenance of district communications 
network cost $23,389. Condition and 
operation studies for the year cost $69,115. 
Dredging by contract of the Canaveral Harbor 
turning basin and the U.S. Navy Trident Areas 
Channel amounted to $888,318. Dredging of the 
Canaveral Harbor Entrance Channel by hopper 
dredge amounted to $3,582,898. Costs for the Sea 
Turtle task force were $14,399. Cost for operation 
of service facilities amounted to $6,839. Cost for 
removal of sunken vessel $50,747. Real estate 
management costs were $3,313. Operations of 
buildings and ground by contract cost $1,782. 
Engineering and design and supervision and administration 
costs were $37,840 and $103,995 
respectively. 
Condition at end of fiscal year. The existing 
project is about 80 percent completed. The 
perimeter dike and jetties are in good condition. 
Work remaining to complete the project is completion 
of the harbor extension and construction 
of the sand transfer plant. 
5. CHANNEL FROM NAPLES TO BIG 
MARCO PASS, FLA. 
Location Naples Bay is on the southwestern 
side of the Florida peninsula about 35 miles south 
of the mouth of the Caloosahatchee River and approximately 
1 mile inland and parallel to the Gulf 
9-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
of Mexico coastline. (See Coast and Geodetic 
Survey Chart No. 1254.) 
Existing project. The authorized project provides 
for an interior channel 6 by 70 feet from 
Naples to Big Marco Pass; a channel 12 by 150 
feet from the Gulf of Mexico to Gordon Pass, 
thence 10 by 100-70 feet to a 10-foot-depth turning 
basin in the upper Naples Bay; and an 8-footdepth 
turning basin at the municipal yacht basin. 
Plane of reference is mean low water. Mean tidal 
range is 2.1 feet. (See Table 9-B for Authorizing 
Legislation.) 
For further details see Annual Report of 1962. 
Local cooperation. Fully complied with to date. 
Contributed funds for new work were $159,975. 
Terminal facilities. Four seafood packing 
houses, 4 marine repair yards; a municipal pier 
and basin for use by recreational boats; and 
numerous private piers and slips for both commercial 
and recreational craft are available. 
Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal year. 
Maintenance: Condition and operation studies 
cost $9,063. Supervision and administration costs 
were $261. 
Condition at end of fiscal year. The project is 
complete. 
6. CHARLOTTE HARBOR, FLA. 
Location. The Harbor is located on the west 
coast of Florida about 68 miles south of the entrance 
to Tampa Bay and 150 miles north of Key 
West. (See Coast and Geodetic Survey Chart No. 
1255.) 
Previous projects. For details, see page 457 of 
1959 Annual Report. 
Existing project. The authorized project provides 
for a channel 32 by 300 feet, increased to 
700 feet at the bend, from the Gulf of Mexico to 
Port Boca Grande, thence 10 by 100 feet from 
deep water at Port Boca Grande to and including 
a turning basin 200 feet square at the municipal 
terminal at Punta Gorda. Plane of reference is 
mean low water. The project is about 29.5 miles 
long. 
Mean tidal range is one foot at Port Boca 
Grande and 1.4 feet at Punta Gorda. Extreme 
range is about 3 feet at Port Boca Grande and 3.8 
feet at Punta Gorda. Strong southwesterly winds 
raise water level about 1.5 feet; strong northerly 
and easterly winds lower it about one foot. (See 
Table 9-B for Authorizing Legislation.) 
Local cooperation. Local cooperation is fully 
complied with to date. Non-Federal contribution 
for new work was $15,563. 
Terminal facilities. Existing facilities consist of 
a phosphate wharf at Port Boca Grande and a 
municipal earthfill pier about 850 feet long at 
Punta Gorda, both open to the public. Railway 
connections are available at Port Boca Grande, 
and highway and railway connections are 
available at Punta Gorda. There is a tank farm at 
Port Boca Grande for storage and rehandling of 
bunker fuel oil and numerous facilities are 
available in the area for docking and servicing 
small craft. Facilities are considered adequate for 
existing commerce. 
Operations and results during fiscal year. 
Maintenance: Dredging amounted to - $103,708. 
Operation and maintenance of district communications 
network cost $5,827. Condition and 
operation studies cost $29,142. Engineering and 
design and supervision and administration costs 
were $73,378 and $2,246 respectively. 
Condition at end of fiscal year. The project was 
completed in 1959. 
Total costs under existing project through 
September 30, 1983, have been $533,169 for new 
work and $8,533,946 for maintenance, a total of 
$9,073,999. In addition, $15,563 was expended 
from contributed funds for new work in Boca 
Grande entrance channel. 
7. CLEARWATER PASS, FLA. 
Location. Clearwater Pass is a natural inlet 
connecting Clearwater Bay with the Gulf of Mexico. 
The pass is located about 25 miles north of the 
entrance to Tampa Harbor and 14 miles south of 
the mouth of Anclote River. (See Coast and 
Geodetic Survey Charts Nos. 858 and 1257.) 
Existing project. The authorized project provides 
for a channel 10 by 150 feet in the Gulf of 
Mexico through Clearwater Pass, thence 8 by 100 
feet eastward to the Intracoastal Waterway; a 
side channel 8 by 100 feet; and a turning basin 8 
feet deep by 100 feet to 450 feet wide by 850 feet 
long. Plane of reference is mean low water. The 
mean range of tide is 1.8 feet at Clearwater 
Marina. Length of the project is 3 miles. For further 
details see 1961 Annual Report. (See Table 
9-B for Authorizing Legislation.) 
Local cooperation. Local cooperation is fully 
complied with to date. Non-Federal contribution 
for new work amounted to $42,783. 
Terminal facilities. The city of Clearwater 
operates a recreational pier. There are several 
marinas providing service for charter boats and 
small recreational craft and one marine railway. 
All facilities are accessible by highway connec- 
9-4

JACKSONVILLE, FLA. DISTRICT 
tions. Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal year. 
Maintenance: Condition and operation studies 
cost $25,814. Engineering and design and supervision 
and administration costs were - $350 and 
$527 respectively. 
Condition at end of fiscal year. The project was 
completed in 1961. 
8. CROSS FLORIDA BARGE CANAL 
Location. The proposed canal extends up the 
St. Johns River, past Palatka, thence up the 
valley of the Oklawaha River across the divide 
south of Ocala, and down the valley of the 
Withlacoochee River to the Gulf of Mexico, about 
95 miles north of Tampa, Florida. 
Existing project. The authorized project provides 
for a lock canal with project depth of 12 feet 
and a minimum bottom width of 150 feet, with 
five locks and two earth dams. Project including 
the section in the St. Johns River is 184 miles 
long. (See Table 9-D for Locks and Dams.) 
Operation and maintenance of the locks and 
dams is a Federal responsibility. Estimated cost 
of new work (1970) is $179,000,000 Federal, and 
$19,500,000 non-Federal for lands, rights-of-way, 
and other costs. (See Table 9-B for Authorizing 
Legislation.) 
Local cooperation. Local interests must furnish 
lands and rights-of-way for construction of canal; 
hold the United States free from damages; and 
operate and maintain all highway bridges and 
roadways built in connection with project. 
Terminal facilities. None. 
Operations and results during fiscal year. (See 
Table 9-E for work accomplished.) 
Regulation. 
a. Lake Ocklawaha. During the period the lake 
continued to be regulated at 18.0 feet, NGVD by 
discharging through the Rodman spillway. 
b. Lake Rousseau. During the period, the lake 
continued to be regulated at 27.5 ft., NGVD by 
discharging through the Inglis Main and Bypass 
Spillways. 
Condition at end of fiscal year. Construction of 
project commenced February 25, 1964, and is 36 
percent completed. Inglis Lock, Dam, and 
Spillway; Rodman Dam and Spillway, Eureka 
Lock, Dam, and Spillway; Henry H. Buckman 
Lock; and canal from Palatka to Lake Oclawaha 
and from Withlacoochee River to Gulf of Mexico, 
including Inglis Bypass Channel, are completed. 
Construction work on the project was terminated 
in FY 1971 by order of the President. A restudy 
report and environmental impact statement were 
completed in February 1977. 
9. FERNANDINA HARBOR, FLA. 
Location. Entrance to the harbor is located on 
the northeast coast of Florida about 95 miles 
south of the entrance to Savannah Harbor, 
Georgia, and 22 miles north of the entrance to 
Jacksonville Harbor, Florida. (See Coast and 
Geodetic Survey Chart No. 453.) 
Existing project. The authorized project provides 
for a 32-foot-depth channel (maximum channel 
in active status: 28 feet) generally 300-400 feet 
wide from deep water in the ocean to the junction 
of Lanceford Creek with Amelia River; an 
800-foot-wide turning basin at the first bend 
below Lanceford Creek; and two jetties, 19,150 
and 11,200 feet long. Plane of reference is mean 
low water. The project is 7 miles long. Mean tidal 
range is 5.8 feet on the bar and 6 feet in the inner 
harbor. (See Table 9-B for Authorizing Legislation.) 
Local cooperation. Fully complied with to date. 
Terminal facilities. There are two large 
wharves operated by industrial plants; twelve 
wharves serving fishing boats, recreational craft, 
and other vessels; three oil handling wharves 
with pipelines; and a Municipal Marina and 
Sportsman's Wharf with public facilities for small 
craft. Total berthing space is approximately 4,065 
feet. Most terminals are served by rail, and all 
have highway access. Facilities are considered 
adequate for existing commerce. (See Port Series 
No. 16 (Part 2), 1964.) 
Operations and results during fiscal year. New 
Work: Supervision and administration of recreational 
facilities at Fort Clinch incurred costs of 
$7,141. 
Maintenance: Dredging cost $953,083. Condition 
and operation studies cost - $34,308. Operation 
and maintenance of district communications 
net work cost $2,821. Real estate management 
costs were $2,044. Engineering and design and 
supervision and administration costs were 
$18,476 and $23,394, respectively. 
Condition at end of fiscal year. The active portion 
of the existing project is complete. Jetties 
are in poor condition and are badly in need of 
repair. Remaining work is to deepen the inner 
harbor channel and turning basin to 32 feet when 
and if the presently inactive 1950 authorization is 
reactivated. The outer harbor channel has been 
deepened to 34 feet in development of a military 
project. 
10. FORT MYERS BEACH, FLA. 
Location Fort Myers Beach is on Estero Island 
9-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
near the mouth of the Caloosahatchee River, 
about 20 miles below Fort Myers and 110 miles 
south of Tampa, Florida. (See Coast and Geodetic 
Survey Charts Nos. 855-SC and 1255.) 
Existing project. The authorized project provides 
for a channel 12 by 150 feet from that depth 
in San Carlos Bay into Matanzas Pass, thence 11 
by 125 feet in Matanzas Pass to and including a 
turning basin 2,000 feet upstream from the upper 
shrimp terminals. Plane of reference is mean low 
water. Project is 2.5 miles long. 
Mean tidal range is 1.7 feet. Spring range is 
about 2.8 feet. Strong northerly winds lower the 
water surface 1 to 2 feet; strong southerly winds 
have an opposite effect. (See Table 9-B for 
Authorizing Legislation.) 
Local cooperation. Fully complied with to date. 
Non-Federal contribution for new work was 
$1,095. 
Terminal facilities. There are three shrimppacking 
houses and several fish-packing houses, 
two marine railways, a fuel terminal and an ice 
manufacturing plant in the area. There are 
several commercial facilities for servicing shrimp 
boats. Recreational-craft facilities include nine 
marinas, a boat motor testing laboratory which is 
closed, and numerous privately owned piers and 
wharves. All terminals have highway access. 
Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal year. 
Maintenance: Dredging surveys and inspection 
were performed at a cost of $133. Condition and 
operation studies cost $13,521. 
Condition at end of fiscal year. The project is 
complete. 
11. FORT PIERCE HARBOR, FLA. 
Location. On east coast of Florida, about 218 
miles south of entrance to St. Johns River and 
about 124 miles north of entrance to Miami Harbor. 
(See Coast and Geodetic Survey Chart No. 
582.) 
Existing project. A channel 350 feet wide at the 
27-foot contour in the ocean, tapering to a width 
of 200 feet at Sta. 100 + 00, thence 200 feet wide to 
Sta. 30 + 00, and thence flaring to a turning basin 
900 feet wide. Entrance channel is 27 feet deep to 
Sta. 130 + 00 and thence 25 feet deep to and including 
the turning basin. Project includes the 
maintenance of two jetties and shore revetments 
at the inlet. Length of project is about 3.5 miles. 
Mean tidal range is 2.6 feet at the entrance and 
0.7 foot at terminals. (See Table 9-B for Authorizing 
Legislation.) 
For further details see 1961 Annual Report. 
Local Cooperation. Fully complied with to date. 
Non-Federal contribution for new work was 
$18,574. 
Terminal facilities. Two earth-filled piers forming 
a slip 200 feet by 300 feet, with bulkhead 
wharf at inner end, affording berthing space of 
about 1,653 feet. The south pier and bulkhead 
wharf are municipally owned. Facilities also include 
a cooling plant, a warehouse and a fruit 
packing house. The north pier is served by 
railway and both piers by highway connnections. 
North of the turning basin local interests have 
provided deep-draft berthing and pier facilities. 
Also available is a bulkhead wharf with a depth of 
25 feet with ample room for open storage and 
with tank storage for petroleum in the rear. 
Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal year. 
Maintenance: Condition and operation studies 
cost $12,880. Dredging by contract cost $896,697. 
Engineering and design and supervision and administration 
costs were $2,601 and $73,385 
respectively. 
Condition at end of fiscal year. The project was 
completed in 1938 except for the fishing walkway 
atop the south jetty which was completed by local 
interest in 1968. Local interests installed lighting 
atop the jetty in 1969. 
Jetties and revetments are in good condition. 
12. INTRACOASTAL WATERWAY, CALOOSAHATCHEE 
RIVER TO ANCLOTE 
RIVER, FLA. 
Location. The Waterway extends from the 
mouth of the Caloosahatchee River at Punta 
Rassa, Florida, to the mouth of Anclote River, 
Florida, following in general an almost continuous 
series of protected inside waterways along the 
gulf coast of Florida. (See Coast and Geodetic 
Survey Charts Nos. 856-SC, 857-SC, and 858.) 
Previous projects. For details see page 767 of 
1945 Annual Report. 
Existing project. The authorized project provides 
for a channel 9 by 100 feet from Caloosahatchee 
River to Anclote River; deepening the existing 
channel at Caseys Pass to 9 feet; a channel 
6 by 80 feet (Cats Point Channel) along the 
southeastern side of Boca Ciega Bay past Frenchman 
Creek and Gulfport; maintenance of 
bulkheads, revetments, and two jetties built at 
Caseys Pass under previous project; and improvement 
and maintenance of Sunshine Skyway Channel. 
Plane of reference is mean low water. The 
project includes about 160 miles of channels. 
Mean ranges of tide are 1.7 feet at Punta Rassa, 
9-6

JACKSONVILLE, FLA. DISTRICT 
1 foot at Port Boca Grande, 1.4 feet in Tampa Bay 
at Anna Maria, and 2 feet at entrance to Anclote 
River. Extreme ranges are about 4.5 feet at Punta 
Rassa, about 3 to 4 feet between Port Boca 
Grande and Corey Causeway over Boca Ciega 
Bay, and about 5.5 feet at entrance to Anclote 
River. Southerly winds over the area generally 
raise water level by 1 to 1.5 feet; northerly winds 
lower water level by 1 to 2 feet. (See Table 9-B for 
Authorizing Legislation.) 
Local cooperation. Fully complied with to date. 
Non-Federal contribution for constructing Cats 
Point and Sunshine Skyway Channels was $9,707 
and $4,766, respectively. 
Terminal facilities. Existing facilities include 
one municipal concrete pier, one railway pier, one 
freight wharf, one marginal wharf 500 feet long 
on terminal island, and eleven privately owned 
landings, all at Sarasota. Municipal pier and 
freight wharf are open to the public. All piers 
have highway connections. There are six wharves 
along Boca Ciega Bay and a number of small 
privately owned piers and wharves at various 
points along waterway for use of commercial 
fishing boats and recreational craft. Facilities are 
considered adequate for existing commerce. 
Operations and results during fiscal year. 
Maintenance: Maintenance of channel slopes and 
berms was performed by hired labor for $24,269. 
Operation and maintenance of district communications 
network cost $12,185. Real estate 
management costs were $7,182. Condition and 
operation studies cost $60,830. Engineering and 
design and supervision and administration costs 
were $1,862 and $8,783, respectively. 
Condition at end of fiscal year. Existing project 
is complete. A contract to maintain the jetties at 
Casey's Pass was awarded in F.Y. 83. 
Total Federal costs under existing project 
through September 30, 1983 were $7,597,078 for 
new work and $4,378,500 for maintenance, a total 
of $11,975,578. In addition, $14,473 contributed 
funds were expended for Sunshine Skyway and 
Boca Ciega Bay channels. 
13. INTRACOASTAL WATERWAY, JACKSONVILLE 
TO MIAMI, FLA. 
Location The waterway extends from Jacksonville 
to Miami, Florida, following the St. Johns 
River to the mouth of Pablo Creek and thence 
following in general an almost continuous series 
of protected inside waterways along the Atlantic 
coast of Florida to Miami. (See Coast and 
Geodetic Survey Charts Nos. 841-SC, 843-SC, 
845-SC, and 847-SC.) 
Previous projects. For details, see pages 
618-619 of 1938 Annual Report. 
Existing project. The authorized project provides 
for a channel 12 by 125 feet from Jacksonville 
to Miami, modified to 10-foot-depth from 
Fort Pierce to Miami by Chief of Engineer's 
report of July 22,1960; side channels at Sebastian 
and Daytona Beach and turning basins at Sebastian 
and Vero Beach, all to an 8-foot-depth; and 
operation and maintenance of the Palm Valley 
highway bridge. Project is 370 miles long, including 
21 miles in Jacksonville Harbor. Mean 
range of the tide is 3.8 feet at St. Johns River, 0.7 
foot in the Indian River at Fort Pierce, 1.8 feet in 
Lake Worth at Port of Palm Beach terminals, 2.3 
feet at the Port Everglades terminals, and 2 feet 
in Biscayne Bay. The extreme range is about 7 
feet at St. Johns River, 1.5 feet at Fort Pierce, 
and 3 feet in Biscayne Bay. Plane of reference is 
mean low water. Tidal effect is imperceptible at 
points along waterway distant from inlets. (See 
Table 9-B for Authorizing Legislation.) 
Local cooperation. Fully complied with to date. 
Terminal facilities. There are a number of 
privately owned piers, wharves, and landings at 
various points along waterway. Terminals with 
railway connections are available at Jacksonville, 
Fort Pierce, West Palm Beach, Port Everglades, 
and Miami. Municipal piers or wharves have been 
constructed at Titusville, Cocoa, Melbourne, and 
Vero Beach for handling general freight and at St. 
Augustine, Daytona Beach, New Smyrna Beach, 
Eau Gallie, West Palm Beach, Delray Beach, Fort 
Lauderdale, and Miami for use of recreational 
craft. Yacht basins, open to the public, have been 
provided at Jacksonville Beach, Daytona Beach, 
Titusville, Eau Gallie, Vero Beach, Fort Pierce, 
West Palm Beach, Fort Lauderdale, Hollywood, 
and Miami. Facilities are considered adequate for 
existing commerce. (For further details on 
facilities at Jacksonville, see Port Series No. 15, 
1969, and at Palm Beach, Port Everglades, and 
Miami, see Port Series No. 16, Revised 1972.) 
Operations and results during fiscal year. 
Maintenance: The cost of dredging was $785,873. 
Operation and maintenance of the district communications 
network cost $18,347. Condition and 
operation studies cost $130,002. Real estate 
management cost $42,517. Engineering and 
design and supervision and administration costs 
were $13,596 and $130,078, respectively. Operation 
and care: The highway bridge near Palm 
Valley was operated and maintained at a cost of 
$164,134. 
Condition at end of fiscal year. The existing 
project as modified by the Chief of Engineers is 
complete except for construction of the channel 
and turning basin at Sebastian, Florida, which is 
in an inactive status. 
Total Federal costs under existing project 
9-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1988 
through September 30,1983, were $16,956,271 for 
new work: $1,054,430 for maintenance and 
$280,143 for operation and care, a total of 
$40,871,855, regular funds. In addition, $2,199,842 
has been expended from public works funds for 
new work. 
14. JACKSONVILLE HARBOR, FLA. 
Location. The authorized project comprises the 
lower 24.9 miles of St. Johns River which empties 
into the Atlantic Ocean near the northeasterly 
corner of the Florida peninsula. (See Coast and 
Geodetic Survey Chart No. 636-SC.) 
Previous projects. For details, see page 607 of 
Annual Report, 1938. 
Existing project. The authorized project provides 
for a channel 38 by 400-1,200 feet from the 
ocean to mile 20 via Dame Point - Fulton Cutoff, 
thence 34 feet to Commodore Point, and thence 30 
feet deep to the F.E.C. Railway bridge at 
Jacksonville, including a 30-foot channel in Arlington 
Cut and in the Old Dame Point -Fulton 
Channel; maintenance of the existing 42 and 
40-foot-depth entrance channel; maintenance of 
jetties at channel entrance; and construction of 
training walls and revetments. Plane of reference 
is mean low water. The project is about 26.8 miles 
long. 
Mean tidal range is 5.3 feet on the bar, 4.9 feet 
at Mayport, 2.6 feet at Dame Point, and 1.1 feet at 
Jacksonville. The extreme range varies from 
about 9 feet on the bar to about 1.5 feet at 
Jacksonville. Strong northeasterly winds raise 
the water level about 2 feet at Mayport and 
Jacksonville. Strong southwesterly winds lower 
the water about 1.5 feet at Mayport and 1 foot at 
Jacksonville. (See Table 9-B for Authorizing 
Legislation.) 
Local cooperation. Local interests have fully 
complied with requirements of local cooperation 
for work performed to date. For work authorized 
by the 1965 River and Harbor Act, local interests 
were required to contribute 2.6 percent of the 
contract price plus supervision and administration 
for work provided by the Corps; provide all 
lands and rights-of-way; save the United States 
free from damages; and provide and maintain 
public terminal and transfer facilities. 
Assurances of local cooperation for this work 
were accepted February 11, 1966. 
Terminal facilities. There are approximately 
100 waterfront facilities serving the port, including 
29 commercially operated, four of which 
are open to the public. There are 12 commercial 
oil terminals and four oil docks operated by the 
Navy. Rail connections are available to all but one 
of the oil terminals and to most commercial 
facilities. A superphosphoric acid storage and 
handling facilitiy is located at Jacksonville Bulk 
Terminal. Jacksonville Shipyards have facilities 
for building and repairing large vessels, and 
numerous facilities are available for repairing 
and servicing small craft. 
Jacksonville Port Authority operates municipal 
docks at two locations, Talleyrand and 
Blount Island. Available at Talleyrand are over 
500,000 square feet of warehousing, 4,700 feet of 
marginal wharf, 130 acres of paved open storage, 
two container cranes, two container straddle carriers, 
and a 50-ton gantry crane. The facility has 
extensive rail and highway connections. 
At Blount Island Terminal there are a total of 
4,700 feet of marginal wharf, over 220 acres of 
paved open storage, 25 acres of container storage 
area, three automobile processing plants, three 
transit sheds, four cranes and a 900-ton capacity 
gantry crane. There are also three 1000-foot container 
berths, a concrete and steel roll on/roll off 
platform, and two mobile roll on/roll off ramps for 
servicing container vessels. 
Facilities are considered adequate for existing 
commerce. (See Port Series No. 15, Rev. 1978, 
Corps of Engineers.) 
Maintenance: Operation and maintenance of 
district communications network cost $19,013. 
Real estate management costs amounted to 
$1,628. Condition and operation studies cost 
$267,038. Maintenance dredging costs were 
$7,866. Engineering and design and supervision 
and administration costs were $47,845 and 
- $3,839, respectively. 
Condition at end of fiscal year. Construction of 
the modification to the project, authorized by 
1965 River and Harbor Act, is completed. The 
north jetty is in fair condition and partially 
submerged at high tide. The south jetty is in good 
condition; revetments and restraining walls are 
in poor condition. 
Total Federal costs under existing project 
through September 30,1988, were $43,786,128 for 
new work, $38,764,586 for maintenance, a total of 
$82,550,714 regular funds. In addition $290,013 
has been expended from public works funds for 
new work. 
15. JOHNS PASS, FLA. 
Location. A natural inlet on the west coast of 
Florida connecting Boca Ciega Bay with Gulf of 
Mexico. The pass is located about 8 miles northwest 
of lower Tampa Bay directly across Boca 
Ciega Bay from St. Petersburg, Fla. (See Coast 
and Geodetic Survey Chart No. 1257.) 
Existing project. Channel 10 by 150 feet in the 
9-8

JACKSONVILLE, FLA. DISTRICT 
gulf, thence 8 by 100 feet inside pass, and 6 by 100 
feet to the Intracoastal Waterway, and suitable 
protective measures over a frontage of approximately 
one thousand linear feet of shore along 
the north end of Treasure Island. Plane of 
reference is mean low water. Mean range of tide 
is 1.5 feet. Project is about 2.6 miles long. 
Project was authorized December 2, 1964 by 
Chief of Engineers under Section 107 of the 1960 
River and Harbor Act and by Section 110 of the 
1966 River and Harbor Act. 
Local cooperation. Fully complied with to date. 
Non-Federal contribution for new work was 
$53,732. 
Terminal facilities. Only small marinas and 
repair yards for recreational craft in the general 
vicinity. Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal year. 
Maintenance: Conditions and operation studies 
amounted to $7,966. Supervision and administration 
costs were $170. 
Condition at end of fiscal year. Project was 
completed in 1968. As of June 1968 authorized 
depths were available throughout the project. 
16. LONGBOAT PASS, FLA. 
Location. Longboat Pass is located on the west 
coast of Florida about 11 miles northwest of 
Sarasota and 23 miles south of St. Petersburg. 
Located in Manatee County, it is one of several 
natural inlets connecting Sarasota Bay, a tidal 
estuary, with the Gulf of Mexico. (See Coast and 
Geodetic Survey Chart No. 1256.) 
Existing project. The authorized project provides 
for an entrance channel 12 by 150 feet from 
the Gulf to Longboat Pass Bridge, thence a channel 
10 by 100 feet from Longboat Pass Bridge 
along a north to northeasterly alinement to the 
Intracoastal Waterway and extending along 
Intracoastal Waterway to Cortez Bridge. The 
mean tidal range is 2.2 feet and the maximum 
tidal range is about 5 feet. Currents are 
predominantly tidal. 
(See Table 9-B for Authorizing Legislation.) 
Local cooperation. Fully complied with. See 
1978 Annual Report for detailed local cooperation 
requirements. Contribued funds for new work 
were $172,324. 
Terminal facilities. From Sarasota north to 
Tampa Bay there are about 28 small craft 
facilities including marinas, boat repair yards, 
and boat basins along the Intracoastal Waterway. 
Nine of them are located within 2 miles of Longboat 
Pass. Numerous private mooring piers and 
boat Pass. Numerous private mooring piers and 
wharves also exist in the area. The marina and 
repair facilities appear adequate for the general 
boating needs of the area. 
Operations and results during fiscal year. 
Maintenance: Condition and operation studies 
amounted to $3,229. 
Condition at end of fiscal year. Construction of 
the project is complete. 
17. MAYAGUEZ HARBOR, P.R. 
Location. The project is on the west cost of 
Puerto Rico, about 110 miles by water from San 
Juan Harbor. (See Coast and Geodetic Survey 
Chart No. 931.). 
Existing project. The authorized project provides 
for a 30-by 1,000 foot approach channel to 
the deep water terminal, decreasing to a 500 foot 
width opposite westerly end of terminal, thence 
the same width to easterly end of terminal. (See 
Table 9-B for Authorizing Legislation.) 
Local cooperation. Fully complied with to date. 
Terminal facilities. A modern deep water terminal 
is located in the northeast section of the 
harbor consisting of a bulkhead wharf about 1,270 
feet long with a storage transit shed 800 by 60 
feet immediately shoreward. The Puerto Rico Industrial 
Development Company, an agency of the 
Commonwealth of Puerto Rico, owns a bulk-head 
wharf of about 200 feet in line with the existing 
deep water terminal plant located within the industrial 
harbor area. In addition, Bumble Bee 
Packing Company, Inc., owns and operates a dock 
of about 200 feet for docking tuna fish boats. 
Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal year. 
Maintenance: Dredging by contract cost $649. 
Supervision and administration costs were $62. 
Condition at end of fiscal year. Project was 
completed in 1934. 
18 MIAMI HARBOR, FLA. 
Location. Miami is near the northern end of Biscayne 
Bay, about 71 miles south of the entrance to 
Palm Beach Harbor. Miami River has its source in 
the Everglades and flows southeasterly to enter 
Biscayne Bay at Miami. (See Coast and Geodetic 
Survey Charts Nos. 547 and 1248.) 
Existing project. The authorized project provides 
for a 38 by 500-foot channel from the ocean 
to the outer end of the north jetty, thence 36 by 
400 feet through the entrance and across Biscayne 
Bay to and including a turning basin at the 
municipal terminals; a 36-foot depth turning basin 
9-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
at Fisher Island; two rubblestone jetties at the 
entrance; a channel 15 by 200 feet from the mouth 
of Miami River to the turning basin at the 
municipal terminals; a channel 8 by 200 feet from 
the mouth of Miami River to the Intracoastal 
Waterway and thence 100 feet wide to Government 
Cut; a channel 15 deep in Miami River varying 
in width from 250 feet at mouth to 90 feet inland; 
and a channel 12 by 100 feet from Miami to a 
harbor of refuge in Palmer Lake. Plane of 
reference is mean low water, except for 15-foot 
channel in Miami River where depths are basedon 
flood conditions. Total length of the project is 
about 15.3 miles. 
Mean tidal variation is 2.5 feet at entrance and 
2 feet in the bay. Extreme variation is about 4.5 
feet at entrance and 3 feet in Biscayne Bay. 
Strong easterly winds raise the water level about 
1.5 feet at entrance and 1 foot in the bay. Strong 
westerly winds lower water level about 1 foot at 
entrance and about 0.5 foot in the bay. (See Table 
9-B for Authorizing Legislation.) 
Local cooperation. Fully complied with. See 
1978 Annual Report for detailed local cooperation 
requirments. 
Assurances of local cooperation for the 1968 
modification to the project were accepted 
December 18, 1968. 
Terminalfacilities. Existing facilities consist of 
82 piers and wharves, of which two are on Fisher 
Island, 12 at Miami Beach, four along the south 
side of MacArthur Causeway, one along the west 
side of Biscayne Bay at Miami, and 43 on Miami 
River. Nineteen facilities are open to the public 
for handling general cargo, eleven of which accommodate 
deep-draft vessels. All general cargo 
wharves have highway and railway connections 
except the causeway terminal which has highway 
connections only. A municipal yacht anchorage 
basin and wharf are open to the public for recreational 
craft. Of the remaining piers and wharves, 
five are used for handling petroleum products, 22 
are used in connection with ship repair activities, 
and 19 are used for mooring vessels or handling 
private freight. In addition, numerous landing 
facilities in and around Miami are designed for 
and used exclusively by recreational craft. 
Metropolitan Dade County is actively engaged 
in developing port facilities on Dodge Island in 
Biscayne Bay. Completed and in-use are approximately 
3.44 miles- eal berthing space. Nine 
passenger terminals can each accommodate and 
process 1,000 persons daily through customs. 
There are 7 transit cargo sheds with a total of 
823,558 square feet (635,742f' net). There are 
presently in use ten berths for roll-on trailer 
ships. A slip of 800 feet by 400 feet on the south 
side of the island is being utilized for 
oceanographic research vessels. An additional 70 
acres of open storage has been added to space 
already available, and two 40 long ton gantry 
cranes, with 20 acres of backup area, will be 
operational by the end of 1982. Current expansion 
program will add 210 more acres for cargo use, 
and four passenger terminals. 
Upon completion, facilities are expected to be 
adequate for current commerce. (See Port Series 
No. 16, Revised 1972, Corps of Engineers.) 
Operations and results during fiscal year. New 
work: Engineering and design and supervision 
and administration costs preparatory to constuction 
of recreation facilities at Bay Front Park 
were $246,357 and $25,059, respectively. 
Maintenance: Hired labor surveys, inspections 
and reports cost $29,868 for the fiscal year. 
Condition at end of fiscal year. Construction of 
the modification to the project, authorized by 
River and Harbor Act of 1968, is complete. South 
and north jetties are in good condition. Maintnenance 
dredging is required in the turning basin 
at the municipal terminals. 
19. NEW PASS, SARASOTA, FLA. 
Location. Sarasota Bay is a tidal lagoon along 
the west coast of Florida immediately south of 
Tampa Bay. New Pass is a gulf inlet across the 
bay from Sarasota, Fla. (See Coast and Geodetic 
Survey Chart No. 857-SC.) 
Existing project. The authorized project provides 
for an entrance channel 10 feet deep and 150 
feet wide in the Gulf of Mexico diminishing to 8 
by 100 feet through New Pass and extending 
across Sarasota Bay to the Intracoastal Waterway 
with side channels to, and turning basins at, 
Payne Terminal and city pier. Plane of reference 
is mean low water. Mean range of tide is 1.3 feet 
in Sarasota Bay; mean spring range is 1.7 feet. 
Project is about 4 miles long. (See Table 9-B for 
Authorizing Legislation.) 
Local cooperation. Fully complied with to date. 
Non-Federal contribution for new work amounted 
to $45,811. 
Terminal facilities. Consist of Payne Terminal, 
a slip 200 by 650 feet, and city pier, 400 feet long 
with two finger piers equipped with adequate 
facilities at each location. 
Operations and results during fiscal year. 
Maintenance: Operation and condition surveys 
cost $9,119 for the fiscal year. 
Condition at end of fiscal year. Project was 
completed in 1964. 
9-10

JACKSONVILLE, FLA. DISTRICT 
20. OKEECHOBEE WATERWAY, FLA. 
Location. The waterway traverses the 
southern part of the Florida peninsula via the 
Caloosahatchee River, Lake Okeechobee, and St. 
Lucie Canal, connecting coastal waterways along 
the Gulf and Atlantic Shores. (See Coast and 
Geodetic Survey Charts Nos. 11428 and 11427.) 
Previous projects. For details, see page 785 of 
1949 Annual Report. 
Existing project. The authorized project provides 
for replacing the old locks on the St. Lucie 
Canal by a single new lock; a channel 10 by 100 
feet from Ft. Myers for about 5 miles upstream, 
thence 8 by 80 to 100 feet to the Intracoastal 
Waterway, Jacksonville to Miami; near Stuart; an 
8-foot depth basin at Stuart; a side channel at Ft. 
Myers; operation and care of St. Lucie Lock; and 
maintenance of features completed under 
previous projects as follows: a 12 by 200-foot 
channel from the Gulf to Punta Rassa, thence 10 
by 100 feet to Fort Myers with a 10-foot depth 
basin at Fort Myers; a 6 by 80-foot channel along 
the south shore of Lake Okeechobee from 
Clewiston to St. Lucie Canal; a 6 by 60-foot channel 
in Taylor Creek from the town of Okeechobee 
to the Lake; and operation and' care of Moore 
Haven and Ortona Locks. 
(See Table 9-B for Authorizing Legislation.) 
For further details see 1962 Annual Report. 
Local cooperation. Fully complied with for completed 
portion of project. Non-Federal contribution 
amounted to $503,700. 
Terminal facilities. There are 3 freight piers, 1 
municipal recreation pier, 4 privately owned 
piers, and a municipal yacht basin on the 
Caloosahatchee River near Fort Myers. The 
Corps has provided a boat basin, launching ramp, 
and a 120-foot wharf on the Caloosahatchee River 
about one-quarter mile below Ortona Lock. There 
are tie-up dolphins above and below all 5 locks. 
Commercial yacht basins are provided on the 
south side of the Caloosahatchee River about 
halfway between Ortona and Moore Haven Locks 
and about 3 miles east of LaBelle. A commercial/
municipal yacht basin is provided on the 
north side of the St. Lucie Canal at Indiantown. 
There are numerous small wooden-pile landings 
along the Caloosahatchee River on St. Lucie 
Canal, and on the St. Lucie River, including one 
railroad terminal pier, a municipal pier, and a pier 
for handling petroleum products at Stuart. Also, 
550 feet of wharves have been provided on the 
west side of Taylor Creek immediately landward 
of Hurricane Gate No. 6 and 150 feet on the east 
side of the creek. A yacht basin has been provided 
on the west side of the creek immediately landward 
of the hurricane gate. The installations of 
Taylor Creek are privately owned, but are open 
to the public. A breakwater protected harbor is 
available at Pahokee. There is a 440-foot marginal 
wharf on the Industrial Canal at Clewiston; a 
125-foot wharf at LaBelle; a 150-foot wharf at 
Belle Glade; a 125-foot wharf at Moore Haven; a 
50-foot wharf at Alva; and a 30-foot wharf on 
Taylor Creek at the town of Okeechobee. A docking 
facility for loading raw sugar was constructed 
in 1967 on Herbert Hoover Dike near Belle Glade. 
All have highway and/or railway connections. 
Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal year. (See 
Table 9-F for work accomplished.) 
Condition at end of fiscal year. The project is 
complete except for providing the 8-foot depth 
basin at Stuart, which is inactive. 
Total Federal costs under the existing project 
through September 30, 1983, were $5,175,614 for 
new work, $10,416,793 for maintenance, and 
$7,940,953 ($67,558 excluded which represents 
services rendered without reimbursement) for 
operation and care, a total of $23,533,360. 
21. OKLAWAHA RIVER, FLA. 
Location. The river has its source in a system 
of large lakes in the central part of the Florida 
peninsula and flows generally northerly, then 
easterly, emptying into St. Johns River 22 miles 
above Palatka. The extreme head of the system is 
considered to be Lake Apopka, 120 miles above 
the river's mouth. 
Previous projects. For details, see page 613 of 
1938 Annual Report. 
Existing project. The authorized project provides 
for a channel 6 feet deep from the river 
mouth to the head of Silver Springs Run; clearing 
a channel to Lake Griffin; maintaining dikes to obtain 
a navigable depth of about 4 feet to Leesburg 
and construction of a lock and dam at Moss Bluff. 
The project length is about 85.7 miles in the river 
and 5.4 miles in Silver Springs Run. 
(See Table 9-B for Authorizing Legislation.) 
Local cooperation. Fully complied with to date. 
Terminal facilities. Numerous private and 
public landings and boat-launching ramps are 
located along the river. Public recreation-craft 
basins and boat launching ramps are near Silver 
Springs and State Road 40 and 316 bridges. There 
is a municipal wharf on Lake Griffin at Leesburg. 
A dam has created Lake Ocklawaha (13,000 acres) 
with egress to the St. Johns River through 
Buckman Lock. Along the lake are 4 launching 
ramps; Payne's Landing, Orange Springs, Ken- 
9-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
wood Landing, and Rodman Recreation Area. Access 
below the dam is at the Oklawaha Boat 
launch ramp and at State Road 19. Facilities are 
considered adequate for existing commerce. 
Operations and results during fiscal year. 
Maintenance: Condition and operation studies 
cost $1,731. Snagging and clearing cost $26,282. 
Real estate management costs were $622. Supervision 
and administration costs were $2,796. 
Condition at end of fiscal year. The project is 
complete except for providing a 6-foot depth 
channel from the mouth of the river to the head of 
Silver Springs run, which is in an inactive status. 
The Moss Bluff lock and dam structure was 
replaced under the Four River Basins, Fla., flood 
control project. 
Total Federal costs under the existing project 
through September 30, 1983 have been $311,352 
for new work and $1,959,292 for maintenance (excluding 
$11,414 under provisions of the permanent 
indefinite appropriation), a total of 
$2,270,644. 
22. PALM BEACH HARBOR, FLA. 
Location. The authorized project is located on 
the east coast of Florida about 71 miles north of 
the entrance to Miami Harbor and about 264 
miles southeasterly from the entrance to Jacksonville 
Harbor. (See Coast and Geodetic Survey 
Charts Nos. 291 and 1248). 
Existing project. The authorized project provides 
for an entrance channel 35 by 400 feet merging 
with an inner channel 33 by 300 feet to and including 
a turning basin; tank revetment; and 
restoring jetties. Plane of reference is mean low 
water. The project is about 1.6 miles long. 
Mean range of tide in the ocean at the entrance 
is 2.8 feet and at the turning basin, 2.2 feet. Extreme 
range of tide is about 4.5 feet at the inlet 
and 3 feet at the terminals. Seven-foot tidal 
ranges have occurred during storms. For details, 
see 1962 Annual Report. (See Table 9-B for 
Authorizing Legislation.) 
Local cooperation. Fully complied with to date. 
For requirements, see 1961 Annual Report. Non- 
Federal contribution for new work was $509,506. 
Terminal facilities. The port has two slips, four 
marginal wharves containing 25 berths along 
5,165 feet of bulkheading, six roll-on/roll-off 
ramps, nearly 183,775 square feet of transit shed 
space and 40 acres of open storage space, with an 
additional 17 acres of container marshalling yard. 
There are seven petroleum storage tanks connected 
by pipeline to terminals, a bulk sugar 
facility and terminal and cement storage 
warehouse. A new five-story Port Authority office 
building has been completed. Demolition of 
the old facility will provide additional operating 
space. All facilities are owned by the Port of Palm 
Beach District. 
Facilities are considered adequate for existing 
commerce. (See Port Series No. 16, revised 1972, 
Corps of Engineers.) 
Operations and results during fiscal year. 
Maintenance: Dredging cost $617,220. Condition 
and operation studies for the project totaled 
$31,085. Operation and maintenance of the 
district communications network cost $1,260. 
Engineering and design and supervision and administration 
costs were $18,179 and $34,973, 
respectively. 
Condition at end of fiscal year. The Project was 
completed in 1967. Jetties and revetment are in 
good condition. 
23. PONCE DE LEON INLET, FLA. 
Location. Ponce de Leon Inlet is on the Atlantic 
coast of Florida about 65 miles south of St. 
Augustine Harbor and 57 miles north of 
Canaveral Harbor. (See Coast and Geodetic 
Survey Chart No. 1245.) 
Existing project. The authorized project provides 
for an entrance channel 15 by 200 feet 
across the ocean bar, thence 12 by 200 feet and 12 
by 100 feet through the inlet; thence southward in 
Indian River North, 12 by 100 feet, and northward 
in Halifax River, 7 by 100 feet, each leg continuing 
to the Intracoastal Waterway; ocean jetties 
on the north and south of the inlet 4,200 and 
2,700 feet long, respectively, and a weir in the 
north jetty with an impoundment basin inside the 
jetty. Plane of reference is mean low water. Mean 
range of tide is 4.1 feet in the ocean and 2.3 feet 
inside the inlet. The project is about 5 miles long. 
Local cooperation. Fully complied with to date. 
Non-Federal contribution for new work was 
$2,415,600. 
Terminal facilities. None in the immediate 
area. 
Operations and results during fiscal year. 
Maintenance: Real estate management costs 
were $1,361. Condition and operation studies cost 
$84,888. Engineering and design and supervision 
and administration costs were $65,955 and $9,027, 
respectively. 
Condition at end of fiscal year. Construction of 
the project is complete. Ocean jetties and weir 
are in good condition. 
24. PONCE HARBOR, P. R. 
Location. Ponce Harbor is an open bay about 
9-12

JACKSONVILLE, FLA. DISTRICT 
midway on the south coast of Puerto Rico. From 
the center of the city of Ponce, the harbor is about 
3 miles south. (See Coast and Geodetic Survey 
Chart Nos. 927 and 902.) 
Previous project. For details, see page 12 of 
Annual Report for 1975. 
Existing project. The authorized project provides 
for a seawall 362 feet long extending northwesterly 
across the rock reef from near the landward 
end of the municipal pier; dredging an area 
off the municipal pier, 30 feet deep and containing 
about 18 acres; a breakwater 2400 feet long extending 
southwesterly from Punta Carenero; a 
channel 36 feet deep by 600 feet wide extending 
from the Caribbean Sea approximately 2.8 miles 
up to the port, thence a channel 400 feet wide by 
36 feet deep into the harbor, and a 36-foot-deep, 
irregularly shaped turning basin with a diameter 
of 950 feet. Plane of reference is mean low water. 
Mean tidal range is 0.6 foot, extreme varies between 
about 1 foot below and 2 feet above mean 
low water. Estimated Federal cost of new work 
(Oct. 1982 price levels) is $8,580,000 with no local 
contribution required. (See Table 9-B for 
Authorizing Legislation.) 
Local cooperation. Should provide all lands, 
easements and rights-of-way; provide and maintain 
at local expense depths in berthing areas and 
local access channels; hold United States free 
from any damages resulting from construction 
and maintenance of the project; relocate without 
cost to the United States all cables, sewer mains, 
water supply, drainage and other utility installations 
as required; provide adequate public terminal 
and transfer facilities open to all on equal 
terms. A letter has been received from local interests, 
assuring compliance with local requirements. 
Further assurances are not required 
until completion of Phase I GDM. No contribution 
is required from locals. 
Terminal facilities. The municipality of Ponce 
owns and operates the only deep-draft terminal 
facilities in Ponce Harbor, which consist of a 
municipal pier 515 feet long and 108 feet wide, 
and a bulkhead wharf 3,811 feet long. Both are 
equipped for transfer and storage of freight. A 
72.5 ton container lift shore crane is available for 
the handling of loaded containers. The municipal 
pier has a steel transit shed 386 by 85 feet. The 
bulkhead wharf has four steel transit sheds totaling 
over 103,000 square feet. Three concrete and 
steel warehouses are available providing 800,000 
square feet for general storage. Open storage 
areas for structural steel, lumber, and other bulk 
and package commodities are also provided. Bulk 
cement is handled and loaded into cement cargo 
ships by the use of a private pipeline loading 
facility. A tuna fish processing and canning factory 
is located on the premises, with direct access 
to the bulkhead wharf. Existing facilities are 
open to the public. 
Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal year. New 
Work: Engineering and design and supervision 
and administration costs were $5,895 and $82, 
respectively. 
Maintenance: Dredging by contract cost $622. 
Condition at end of fiscal year. Construction of 
the 1976 modification of the project has not commenced. 
South and north jetties are in fair condition. 
Maintenance dredging is required in the turning 
basin at the municipal terminals. 
25. PORT EVERGLADES HARBOR, FLA. 
Location. The harbor is on the east coast of 
Florida about 23 miles north of Miami and about 
48 miles south of Palm Beach Harbor, Florida. 
(See Coast and Geodetic Survey Chart No. 546.) 
Existing project. The authorized project provides 
for an ocean entrance channel 45 by 500 feet 
through an ocean bar tapering to 40 by 450 feet 
between rubblestone entrance jetties, and continuing 
at that depth to an irregularly flared entrance 
and turning basin of same depth; enlarging 
Pier 7 channel to 36 by 400 feet for distance of 
about 1,600 feet; maintenance of the locally dredged 
channel opposite Berth 18 to 36 feet deep over 
a length of 700 feet with varying widths of 200 to 
150 feet; planning for a south jetty fishing 
walkway with construction contingent upon need 
as developed by detailed postauthorization 
studies; and, maintenance of the jetties. Plane of 
reference is mean low water. The project is about 
1.9 miles long. Mean range of tide is 2.5 feet at the 
entrance and 2.3 feet at the terminals; extreme 
range is about 4.5 feet with storm tides of about 
6.5 feet. 
Estimated cost of new work (Oct. 1980 price 
levels) of the 1974 authorization is $33,800,000 
Federal (Corps of Engineers) cost and $7,062,000 
non-Federal cost, $160,000 contributed funds and 
$6,902,000 other costs). (See Table 9-B for 
Authorizing Legislation.) 
Local cooperation. Local Cooperation has been 
fully complied with for work completed to date. 
For work under House Document 144/93/1, local 
interest must: provide all lands, easements, and 
rights-of-way; save United States free from 
damages; accomplish utility and other relocations 
or alterations; provide depths in berthing areas 
and local access channels serving the terminals 
commensurate with depths provided in the 
related project areas; establish regulations pro- 
9-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
hibiting discharge of pollutants into waters of the 
channel by users thereof; prohibit erection of any 
structure within 100 feet of project channel as 
authorized at time of construction; provide and 
maintain public terminal and transfer facilities; 
contribute 50 percent of total first costs of recreational 
jetty fishing facility; and operate and maintain 
jetty fishing facility. Assurances of local 
cooperation for the 1974 authorization have been 
furnished by the local sponsor. 
Terminalfacilities. All public port facilities are 
owned and operated by Port Everglades Authority. 
There are 27 commercial ship berths providing 
a total berthing space of over 16,000 linear 
feet. Ten berths are in three slips ranging from 
900 to 1200 feet long and about 300 feet wide. 
Depth is 44 feet mean low water at two of the 
900-foot berths and 33-37 feet mean low water at 
the remaining berths. There are seven transit 
warehouses with a capacity of 412,000 square 
feet, and over 100 acres of open storage. Private 
companies maintain over 200 storage tanks for 
petroleum products, and operate piping facilities 
extending from the port south to Miami. Two 30 
Long Ton Container Cranes are in service at the 
port. 
All wharves are served by railway and 
highway connections. Marine repair and drydocking 
facilities are available for small and medium 
size vessels. A large passenger pier and modern 
cruise terminal facilities can accommodate five 
large cruise ships simultaneously. A Foreign 
Trade Zone, containing 140,000 square feet of 
warehouse space, is located less than /z mile from 
dockside. 
Facilities are considered adequate for existing 
commerce. (See Port Series No. 16, Revised 1972, 
Corps of Engineers.) 
Operations and results during fiscal year. New 
work: Dredging for Section 2 was performed by 
contract at a cost of $3,081,455. Engineering and 
design and supervision and administration costs 
were $107,944 and $452,596, respectively. 
Maintenance: Hired labor surveys, inspections 
and reports cost $212. 
Condition at end of fiscal year. Work required 
to complete the project is construction authorized 
in House Document 144/93/1. 
26. REMOVAL OF AQUATIC GROWTH 
FROM NAVIGABLE WATERS IN THE 
STATE OF FLORIDA. 
Location. Waterhyacinth, hydrilla and water 
lettuce are found in freshwater streams and lakes 
in various parts of the district. 
Existing project. The authorized project provides 
for destruction or removal of aquatic 
growth in navigable waters of the State so far as 
they constitute an obstruction to navigation and 
commerce, using any mechanical, chemical or 
other means not injurious to cattle, and use of log 
booms to close sloughs and backwaters as an auxiliary 
means. No estimate of the final cost of work 
has been made. (See Table 9-B for Authorizing 
Legislation.) 
For further details, see 1962 Annual Report. 
Local cooperation. None required. 
Operations and results during fiscal year. 
Maintenance: Operations continued during the 
year. (See Table 9-B for Authorizing Legislation.) 
(See Table 9-G for spraying operations.) 
Condition at end of fiscal year. The project is 
for maintenance of navigable waterways. During 
the year 11,419 acres of hyacinths, 3,398 acres of 
hydrilla, 545 acres of minor plant and 10,671 acres 
of waterlettuce and hyacinth mix were controlled 
in approximately 2,200 miles of waterways. Hyacinths 
in Lake Okeechobee and in St. Johns River 
Watershed are under maintenance control. 
27. ST. AUGUSTINE HARBOR FLA. 
Location. The harbor is on the east coast of 
Florida, about 35 miles south of the entrance to 
St. Johns River and about 180 miles north of Fort 
Pierce Harbor. (See Coast and Geodetic Survey 
Charts Nos. 1243 and 1244.) 
Previous project. For details see page 412 of 
Annual Report for 1958. 
Existing project. The authorized project provides 
for a channel 16 feet by 200 feet along the 
best natural alinement as may exist from time to 
time across the new inlet bar, thence 12 feet deep 
to the Intracoastal Waterway; a sandtrap groin 
on the north side of the inlet extending seaward 
from the shore of Vilano Beach, and a sand-tight 
jetty on the south side of the channel extending 
seaward from the shore of Conch Island parallel 
to and coexstensive with the groin, future landward 
extension of the groin and jetty; and a channel 
10 by 100 feet in San Sebastian River from the 
Intracoastal Waterway to King Street Bridge, 
with a turning basin near the upper end. Length 
of the inlet channel is about 1.5 miles, and length 
of the San Sebastian River channel is about 2.6 
miles. Plane of reference is mean low water. The 
mean tidal range is 4.5 feet in the ocean at St. 
Augustine Inlet and 4.2 feet at the city waterfront. 
Strong northerly winds, mostly in the 
winter, lower the water surface about 1 foot. (See 
Table 9-B for Authorizing Legislation.) 
Local cooperation. Fully complied with to date. 
Non-Federal contribution for new work amounted 
to $137,500. 
9-14

JACKSONVILLE, FLA. DISTRICT 
Terminal facilities. There are several timber 
docks on the Matanzas waterfront of St. 
Augustine. In this area of the harbor is a concrete 
dock which serves as a municipal yacht pier. It 
has fuel facilities, 19 slips and accommodates 
boats up to 60 ft. in length. A large public boat 
ramp is also available. The principal terminals are 
the numerous shrimp docks in the San Sebastian 
River which flows southward through the city into 
the Matanzas River south of the bridge; these 
consist of timber wharves, with frame and corrugated 
iron warehouses thereon, and 9 marine 
railways for small boats. There is also a marine 
supply facility and several boat yards. The present 
terminals have highway connections and 
several of the shrimp docks have rail connections. 
They are considered adequate for existing commerce 
and recreational craft. 
Operations and results during fiscal year. 
Maintenance: Contract surveys, inspections and 
reports cost $8,128. 
Condition at end of fiscal year. Project is completed 
except for the North Jetty which is in a 
deferred status. The groin is in good condition except 
for the 300 feet which has subsided to about 
elevation 3.0 feet, mean low water. The jetty is in 
good condition, but is submerged at high tide. 
Total Federal costs under the existing project 
through September 30, 1983 were $1,405,131 for 
new work and $4,177,058 for maintenance, a total 
of $5,582,189. 
28. ST. JOHN'S RIVER, FLA., JACKSONVILLE 
TO LAKE HARNEY 
Location. Rises in marshes of Brevard County, 
Fla., near east coast, and flows northwesterly to 
Jacksonville, thence easterly into the Atlantic 
Ocean, 122 miles south of Savannah River. River 
is about 285 miles long, of which 161.5 miles are 
included in project. (See U.S. Coast and Geodetic 
Survey Charts Nos. 685-688.) 
Previous projects. Adopted by River and Harbor 
Acts of June 14, 1880 and July 5, 1884. For 
further details see Annual Reports for 1915 and 
1938. 
Existing project. Channel 13 feet deep and 200 
feet wide from Florida East Coast Railway bridge 
at Jacksonville to Palatka, thence 12 by 100 feet 
to Sanford, and thence 5 by 100 feet to Lake 
Harney, with side channel to Enterprise and 
maintenance of two jetties. 
Existing project was authorized by River and 
Harbor Acts of March 2, 1945 (H. Doc. 445, 78th 
Cong., 2d sess.) and July 24,1946 (S. Doc. 208, 79th 
Cong., 2d sess.). For further details see Annual 
Report for 1962. 
Terminal facilities. There are 36 piers and 
wharves along project, including municipal piers 
and wharves at Green Cove Springs and Palatka, 
12 Navy piers at Green Cove Springs, a municipal 
recreational pier at Sanford, and 19 privately 
owned piers, 5 of which have nearby tank storage 
facilities for petroleum projects. Facilities are 
considered adequate for existing commerce. 
Operations and results during fiscal year. 
Maintenance: Condition and operation studies 
costs were $9,977. 
Condition at end of fiscal year. Active portion 
is complete. Condition of project as a whole is adequate 
for present needs of navigation. (For more 
detailed information refer to Annual Report for 
F.Y. 1963). 
29. ST. LUCIE INLET, FLA. 
Location. The inlet is on the east coast of 
Florida about 19 miles south of the entrance to 
Fort Pierce Harbor, Florida, and 100 miles north 
of the entrance to Miami Harbor, Florida. (See 
Coast and Geodetic Survey Chart No. 1247.) 
Previous project. For details see page 764 of 
Annual Report for 1949. 
Existing project. The authorized project provides 
for extending the north jetty about 500 feet 
and modifying existing jetty to provide a sand 
bypass weir section about 500 feet long; excavation 
of a sand impoundment basin adjacent to the 
bypass weir in the north jetty; construction of a 
south jetty consisting of a rubblemound structure 
about 2,400 feet long with a walkway for recreational 
fishing; channel between existing bar cut 
and the Intracoastal Waterway 10 by 500 feet 
through the bar cut, tapering to 150 feet through 
the inlet, and 100 feet wide and 7 feet deep to the 
Intracoastal Waterway; and transfer of 380,000 
cubic yards of material to the south beach during 
each two year maintenance period. Plane of 
reference is mean low water. Total project length 
is about 1.9 miles. Mean tidal range is 2.6 feet on 
the ocean side and about 1 foot on the land side of 
the inlet. 
The estimated cost of the 1974 modification 
(Oct. 1979 price levels) to the project is $6,290,000 
Federal cost and $2,525,000 non-Federal cost 
($2,260,000 contributed funds and $265,000 other 
costs). (See Table 9-B for Authorizing 
Legislation.) 
Local cooperation. Local interests must: contribute 
19.9 percent of construction cost allocated 
to navigation in the combined project, 23.2 percent 
allocated to beach erosion, and 50 percent of 
construction cost of jetty fishing walkway; provide 
39.8 percent of the annual maintenance cost 
9-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
allocated to navigation and 23.2 percent of the annual 
costs for maintenance dredging allocated to 
beach erosion control for periodic beach nourishment 
and 100 percent of the annual jetty 
maintenance costs allocated to beach erosion control; 
maintain jetty fishing walkway; agree that 
each five years the amount of local cost sharing 
for maintenance is to be adjusted; provide all 
lands, easements, and rights-of-way; hold United 
States free from damages; provide marina with 
mooring facilities and utilities; provide and maintain 
depths in berthing area and local access and 
feeder channels commensurate with the depths 
provided in the project; accomplish such alterations 
as required in sewer, water supply, 
drainage, and other utility facilities, and take action 
to place in effect statutes and/or regulations 
which will protect the water quality for the 
authorized uses of the project. Assurances of 
local cooperation for the 1974 modification have 
not yet been requested from the local sponsor. 
Terminal facilities. A municipal pier provides 
facilities for docking and servicing charter fishing 
and small recreational craft. At Stuart there is a 
dock for handling bulk petroleum products and 
several marinas which provide facilities for mooring, 
servicing and minor repair of small craft. 
Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal year. New 
work: A dredging and jetty construction contract 
underway at a cost of $691,557. Engineering and 
design and supervision and administration costs 
were $11,231 and $56,031, respectively. 
Maintenance: Condition and operation studies 
cost $70,312. Supervision and administration 
costs were $1,486. 
Condition at end of fiscal year. Work required 
to complete the project is construction authorized 
in House Document 294/93/1. Total Federal costs 
under existing project through September 30, 
1983 were $9,738,790 for new work (including 
$2,452,420 contributed funds) and $2,294,305, for 
maintenance, a total of $12,033,095. 
30. ST. PETERSBURG HARBOR, FLA. 
Location. St. Petersburg is on west shore of 
Tampa Bay 8.75 miles southwest of Port Tampa 
City. Entrance from Gulf of Mexico to Tampa Bay 
is about midway of west coast of Florida, about 
330 miles southeast of Pensacola, Fla., and 65 
miles north of Charlotte Harbor, Fla. (See Coast 
and Geodetic Survey Charts 586 and 1257.) 
Previous projects. For details, see Annual 
Report of 1938. 
Existing project. An entrance channel 24 by 
300 feet from Tampa Bay southwesterly and 
thence westerly along south side of Port of St. 
Petersburg basin to Bayboro Harbor: a 24-foot 
depth in the port basin and in the area between 
the entrance channel and the Maritime Service 
south bulkhead; a channel 15 by 100 feet in 
Bayboro Harbor along southwesterly 300 feet of 
the Maritime Service bulkhead; a basin 12 by 800 
by 700 feet -1,400 feet in Bayboro Harbor, a 
channel 12 by 75 by 300 feet in the mouth of Salt 
Creek; an entrance channel 20 by 200 feet extending 
northerly about 5.5 miles from deep water in 
lower Tampa Bay; and thence a channel 19 by 250 
feet leading westward to the 24-foot depth entrance 
channel, and a channel 16 by 200 by 6,200 
feet on the easterly side of the Point Pinellas 
lighted beacon. 
Local cooperation. Local interests must furnish 
lands, rights-of-way, and spoil-disposal areas; hold 
United States free from damages; and strengthen 
or move structures necessary to safeguard the 
channels and adjacent lands and structures. Requirements 
for active part fully complied with. 
Terminal facilities. A 1,500-foot-long municipal 
wharf and two warehouses at the Port of St. 
Petersburg turning basin. From turning basin to 
Bayboro Harbor the U.S. Maritime training station 
has 1,360 feet of wharfage space. On Bayboro 
Harbor, there are 5 oil company wharves, 2 
marine repair and supply plants, a sand and shell 
wharf, 6 marine railways, steam-electric plant 
and fuel wharf of the Florida Power Corp., and 4 
privately owned marginal wharves. Two oil companies 
have terminals on Salt Creek and there 
are three municipal yacht basins north of Port of 
St. Petersburg. Facilities considered adequate for 
existing commerce and are open to all equally. 
Operations and results during fiscal year. 
Maintenance: Engineering and design costs were 
$77. 
Condition at end of fiscal year. Project is complete 
except for 24-foot-depth channel and basin 
from Tampa Bay to Bayboro Harbor which is considered 
inactive. Controlling depths: 20.5 feet in 
20-foot channel leading northward from Tampa 
Bay in April 1966; 19 feet in 19-foot entrance channel 
and 17 feet throughout Port of St. Petersburg 
basin in March 1963; 14.5 feet in Point Pinellas 
Channel in May 1938; and 12 feet in Bayboro Harbor 
and in mouth of Salt Creek in August 1957. 
Total Federal costs for existing project through 
September 30, 1983 were $255,608 for new work 
and $1,522,990 for maintenance, a total of 
$1,778,598. 
31. SAN JUAN HARBOR, P. R. 
Location. San Juan Harbor is on the north coast 
9-16

JACKSONVILLE, FLA. DISTRICT 
of Puerto Rico about 35 miles from the island's 
east end and 1100 miles southeast of Miami, 
Florida. (See Coast and Geodetic Survey Chart 
No. 908.) 
Previous projects. For details see Annual 
Reports for 1915, 1916, 1938. 
Existing project. Provides for a bar channel 48 
by 800 feet, shifting the centerline 350 feet west; 
deepening Anegado Channel in steps from 46 to 
40 feet while reducing its width to 800 feet; 
deepening Army Terminal Channel and turning 
basin to 40 feet while widening the channel to 450 
feet; deepening Puerto Nuevo Channel to 40 feet 
and widening it to 400 feet; deepening Graving 
Dock Channel to 40 feet at existing 400 foot 
width; an advance maintenance area 500 feet 
wide, 1,200 feet long and 44 feet deep at the 
mouth of Cano de Martin Pena.; deepening San 
Antonio Channel to 38 feet at varying widths, 
minimum of 500 feet; deepening cruise ship basin 
to 36 feet at an irregular width; maintaining 
Sabana Approach Channel at 30 by 250 feet; provide 
a 38-foot depth in Anchorage Area "E" with 
irregular width and six mooring dolphins for 
vessels using the area. Mean tidal range is 1.1 
feet. (See Table 9-B for Authorizing Legislation.) 
Local cooperation. Should provide all lands, 
easements and rights-of-way; hold the United 
States free from any damages; provide and maintain 
depths in berthing areas and local access and 
feeder channels; provide alterations as required 
in sewer water supply, and other utility facilities. 
It is further recommended that local interests be 
reimbursed for work performed by them on the 
project subsequent to project authorization. 
Local interests have complied with authorization 
requirements to date. There is no non-Federal 
contribution required. 
Terminal facilities. There are 28 piers and 
bulkhead wharves in the harbor capable of docking 
deep-draft vessels, which have an aggregate 
berthing length of about 23,700 feet. Eleven piers 
and bulkhead wharves are on the north shore, 
two piers and a three-level ramp facility for rollon/
roll-off operations at Front Graving Dock turning 
basin and channel, nine at the eastern side 
and three at the western side of the Army Terminal 
basin and channel, and three on the south 
shore of San Antonio Channel. One pier and 
bulkhead wharf are privately owned, seven are 
U.S. Government property, and 24 owned by the 
Commonwealth of Puerto Rico. Twenty piers and 
wharves are equipped with mechanical crane 
transfer facilities. Five wharves are equipped 
with a special crane for the handling of loaded 
containers. Twenty-four are open to general 
public. 
There is an aggregate length of about 1,339 feet 
of berthing space at Catano Point used principally 
by small vessels within the 18-foot draft range. 
This space is also open to the public. In addition, 
there are 10 piers and bulkhead wharves with approximately 
6,910 feet of berthing space owned 
and operated by different agencies of the Federal 
Government. This space is not open to the public. 
Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal year. 
Maintenance: Condition and operation studies 
cost $4,239. Dredging by contract cost $4,410. 
Supervision and administration costs were 
$14,890. 
Condition at end of fiscal year. Remaining work 
to complete project is modification authorized in 
1976. 
Total Federal costs under the existing project 
through September 30, 1983 were $13,027,284 for 
new work and $11,618,898 for maintenance, a 
total of $24,646,182 regular funds. In addition, 
$427,068 was expended for new work and $24,737 
for maintenance from public works funds and 
$100,000 for new work from contributed funds. 
Existing project includes the entrance channel 
and turning basin to Army Terminal which cost 
$1,543,712; this expenditure was made from 
military appropriations and is not included in 
above costs. 
32. TAMPA HARBOR, FLA. 
Location. Tampa Harbor is in a large natural indentation 
of the Gulf of Mexico about midway of 
the west coast of Florida. The entrance is about 
220 miles north of Key West and about 330 miles 
southeast of Pensacola. (See Coast and Geodetic 
Survey Charts Nos. 586, 587, and 1257.) 
Previous projects. For details see page 665 of 
1938 Annual Report. 
Existing project. The authorized project provides 
for a channel from the Gulf of Mexico to 
Port Sutton and Tampa; 46 by 700 feet from the 
Gulf of Mexico to Mullet Key; 44 by 600 feet in 
Mullet Key Cut Channel; 44 by 500 feet in Tampa 
Bay from Mullet Key Cut to Hillsborough Bay and 
Port Tampa Channels; 44 by 500 feet in 
Hillsborough Bay from junction with Tampa Bay 
and Port Tampa Channels to the junction with 
Port Sutton entrance channel, thence 42 by 400 
feet to the junction with Seddon and Garrison 
Channels; 44 by 400 feet in Port Sutton entrance 
channel; 42 by 400 feet in Sparkman Channel; 40 
by 300 feet in Ybor Channel; 42 by 400 feet in Port 
Tampa Channel; 44 by 400-500 feet in East Bay entrance 
channel; 44 by 300 feet in East Bay approach 
channel; 30 by 300 feet in Seddon and Gar- 
9-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
rison Channels; 30 by 200 feet in Alfia River; 9 by 
100 feet in Hillsborough River to a point 2,000 
feet above Columbus River bridge; a breakwater; 
turning basins at Port Sutton, Ybor Channel, Port 
Tampa, East Bay, mouth of Hillsborough River, 
and in Alafia River; and maintenance of a channel 
12 by 200 feet in Hillsborough River, and 44 by 
200 feet in Port Sutton terminal channel. (The 
46-foot and 44-foot depth portions of the project 
include a 5-foot underkeel clearance. Special 
studies on the project concluded that a 4-foot 
underkeel is sufficient. Therefore, a 1-foot 
overdepth has been placed in an inactive status, 
resulting in active project depths of 45 and 43 
feet, respectively.) Plane of reference is mean low 
water. The project is about 67 miles long, including 
10 miles in Hillsborough River and 3.6 
miles in Alafia River. 
Mean range of tide is 1.3 feet at the lower end 
of the bay, 1.6 feet at Port Tampa, and 1.8 feet at 
Tampa. Extreme range is about 3.8 feet at the 
lower end of the bay and 4.8 feet at Tampa. 
Strong southwesterly winds raise the water level 
about 1.5 feet. Strong northerly winds, which 
usually occur in the winter, lower the water level 
about 2 feet. Estimated cost of new work (Oct. 
1982 price levels) of the 1970 modification to the 
project is $230,204,000. Federal ($223,000,000 
Corps and $1,917,000 U.S. Coast Guard) cost and 
$5,287,000 non-Federal cost ($1,400,000 contributed 
funds and $3,887,000 other costs). (See 
Table 9-B for Authorizing Legislation.) 
For further details, see 1962 Annual Report. 
Local cooperation. Local cooperation has been 
fully complied with for work completed to date. 
See 1978 Annual Report for requirements for 
work authorized by the River and Harbor Act of 
1970, HD 401/91/2 and HD 150/91/1. Assurances 
of local cooperation for the 1970 authorization 
were approved by the Secretary of the Army on 
January 10, 1973. 
Terminal facilities. There are 93 commercial 
piers and wharves at Tampa, including those on 
Hillsborough River and Old Tampa Bay at Rattlesnake, 
Florida. Most facilities have railway 
connections. Municipal terminals (called 
Metroport) on Ybor Channel consist of a slip 750 
by 350 feet with a total of 2,255 feet of berthing 
space and a steel-framed transit shed. The Tampa 
Port Authority operates an 800-head capacity 
cattle-loading wharf on the east side of Sparkman 
Channel. Ship repair facilities including a 900-foot 
drydock are available. There are 19 commercial 
oil terminals, 11 dry bulk terminals, 16 terminals 
for handling phosphate and phosphate related 
products, two privately owned cement storage 
facilities and a dockside cold storage facility. 
At Holland terminal on the west side of the 
East Bay Channel and Turning Basin there are 
four general cargo facilities, one single wharf 600 
feet in length and a continuous wharf 1800 feet in 
length; a roll-on/roll-off platform adjacent to the 
single 600-foot wharf; and a combined cruise 
passenger terminal and warehouse. Located on 
the west side of Hookers Point on Cut D Channel 
is a liquid bulk facility. Also at.Hookers Point are 
ammonia storage tank facilities which are connected 
by pipeline to fertilizer plants in Polk and 
Hillsborough counties. 
Facilities are considered adequate for existing 
commerce. (See Port Series No. 17 revised 1979, 
Corps of Engineers.) 
Operations and results during fiscal year. New 
work: Construction of the 43-foot dredging project 
Mangrove Point to Alafia River, Section 4 
continue at a cost of $996,566. Construction of the 
43-foot dredging project Section 2C (portion) and 
Section 4 remainder continue at a cost of 
$1,866,319. Purchase a transponder for offshore 
disposal positioning at a cost of $23,927. Construction 
of the 43-foot project Mariposa Key to Piney 
Point Section 2C remainder and Piney Point to 
Mangrove Point Section 3A continue at a cost of 
$6,183,824. Construction of the 43-foot dredging 
project Gulf of Mexico, Egmont Channel Cut 1, 
Section 1B, remainder continue at a cost of 
$421,281. Construction of the 43-foot dredging 
project Piney Point to Mangrove Point Section 
3C continue at a cost of $8,878,907. Engineering 
and design and supervision and administration 
costs were $694,311 and $905,845, respectively. 
Maintenance: Operation and maintenance of 
district communications network cost $17,247. 
Real estate management costs were $3,631. Condition 
and operation studies cost $163,925. Contract 
dredging costs amounted to $745,007. 
Engineering and design and supervision and administration 
costs were $59,664 and $47,394, 
respectively. 
Condition at end of fiscal year. Work authorized 
by the River and Harbor Act of 1970 (HD 
401/91/2 is 57 percent complete.) 
Total Federal costs under the existing project 
through September 30, 1983 were: Main project: 
$165,073,610 for new work and $18,309,988 for 
maintenance, a total of $183,383,598 regular 
funds. In addition, $1,329,300 was expended for 
new work from public works funds, $1,463,000 
from emergency relief funds, and $842,666 from 
contributed funds. On Hillsborough River 
$270,466 was expended for new work. 
9-18

JACKSONVILLE, FLA. DISTRICT 
33. NAVIGATION PROJECTS ON WHICH 
RECONNAISSANCE AND CONDITION 
SURVEYS ONLY WERE CONDUCTED 
DURING PERIOD. 
(See Table 9-H.) 
34. OTHER AUTHORIZED NAVIGATION 
PROJECTS 
(See Table 9-I.) 
35. NAVIGATION WORK UNDER SPECIAL 
AUTHORIZATION 
Navigation Activities Pursuant to Section 107, 
Public Law 86-645 (Preauthorization) 
Fiscal year costs for Aguadilla Harbor, PR; 
Benner Bay - Mangrove Lagoon, V.I.; Cedar 
Island-Keaton Beach Channel, Florida; Dunedin 
Pass, Florida; Pahokee Harbor, Florida; 
Willoughby Creek, Florida were $85,344, $51,870, 
$841, - $350, $6,886 and $708, respectively. 
Snagging and clearing for navigation (Sec. 3 of 
1945 River and Harbor Act, Public Law 14, 79th 
Congress.) 
No costs incurred. 
Beach Erosion Control 
36. BREVARD COUNTY, FLA. 
Location. The project is on the east coast of 
Florida at approximately the midpoint of the 
peninsula. (See Coast and Geodetic Survey 
Charts Nos. 1245 and 1246.) 
Existing project. The authorization provides 
for a protective and recreational beach with a 
berm 50 feet wide at elevation 10 feet above mean 
low water and a natural seaward slope as would 
be shaped by wave action, along 14,600 feet of 
beach at the city of Cape Canaveral and 10,600 
feet of beach at Indialantic and Melbourne beach, 
and for periodic nourishment of the restored 
beach at Indialantic and Melbourne Beach limited 
initially to a period of 10 years. Nourishment of 
the restored beach at the city of Cape Canaveral 
would be provided by the authorized sandtransfer 
plant for construction at Canaveral Harbor. 
The project also provides for improvement of 
the Federally owned shores for beach erosion control 
or hurricane protection to be accomplished 
by the Federal agencies involved, subject to their 
own determination of economic justification. The 
areas involved include 4.9 miles of shore at Kennedy 
Space Center, 4.0 miles at Cape Kennedy 
Air Force Station, and 2.3 miles at Patrick Air 
Force Base. 
Mean tidal range in the area is 3.5 feet. 
Estimated cost of the project (Oct. 1982 price 
levels) is $7,850,000 Federal costs and $7,939,000 
non-Federal cost ($7,850,000 cash contribution 
and $89,000 for lands). (See Table 9-B for 
Authorizing Legislation.) 
Local cooperation. Local interests must contribute 
50 percent of all first costs of the work 
and 50 percent of the nourishment cost at Indialantic 
and Melbourne Beach for the first 10 
years of the project life; provide lands and rightsof-
way; provide, after the first 10 years of project 
life, periodic nourishment of the restored beach 
at Indialantic and Melbourne Beach during project 
life; maintain continued public ownership of 
the shore upon which the amount of Federal participation 
is based; control water pollution; and 
hold the United States free from damages. 
Assurances of local cooperation were approved 
by the Secretary of the Army on July 9, 1973. 
Operations and results during fiscal year. New 
work: Engineering and design and supervision 
and administration for the fiscal year cost $1,203 
and $118, respectively. 
Condition at end of fiscal year. Initial beach fill 
has been provided at Indialantic and Melbourne 
beaches. 
37. BROWARD COUNTY, FLA. BEACH EROSION 
CONTROL AND HILLSBORO INLET, 
FLA., NAVIGATION PROJECT 
Location. Broward County is on lower east 
coast of Florida, 300 miles south of Jacksonville 
and about 30 miles north of Miami. Hillsboro Inlet 
is in northern part of Broward County. (See Coast 
and Geodetic Survey Chart No. 1248.) 
Existing project. The authorization provides 
for Federal participation toward cost of a shore 
restoration and protection project and a project 
to provide and maintain a channel adequate for 
small craft navigation. Plan provides for restoration 
of a protective and recreational beach at four 
locations generally 100 feet wide with berm elevation 
of 10 feet above mean low water, a navigation 
channel 8 by 100 feet from the Intracoastal 
Waterway to a point 1,500 feet oceanward in 
Hillsboro Inlet, thence 10 by 150 feet in the ocean; 
jetties on north and south sides of ocean entrance; 
a permanently based floating dredge; and on a 
deferred basis, a trestle-mounted sand-transfer 
plant, if needed. Navigation portion of the project 
is in an inactive status. Mean range of tide in 
areas is 2.5 feet. Plane of reference is mean low 
water. Cost estimate for new work (Oct. 1982 
9-19

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
price levels) is $13,800,000 Federal and 
$19,800,000 non-Federal contribution. (See Table 
9-B for Authorizing Legislation.) 
Local cooperation. Local interests must contribute 
90.5 percent of the first cost of beach 
restoration in the reach between north county 
line and Hillsboro Inlet, 90 percent of first cost 
allocated to beach restoration, and 50 percent of 
first cost allocated to navigation for reach between 
Hillsboro Inlet and Port Everglades and 
72.4 percent of beach restoration in reach between 
Port Everglades and south county line; provide 
all lands and rights-of-way; obtain approval 
of Chief of Engineers of plans and specifications if 
local interests construct beach erosion features; 
and furnish assurances that they will hold the 
United States free from damages, provide and 
maintain adequate public landing or wharf at 
Hillsboro Inlet, establish a public body to 
cooperate financially and to provide and operate 
local facilities for navigation, control water pollution, 
maintain ownership of publicly owned 
shores, and maintain all project works except the 
jetties (maintenance of the channel to revert to 
the United States if sand-transfer plant is constructed). 
Assurances of local cooperation were 
accepted November 22, 1968. 
Operations and results during fiscal year. New 
work: Engineering and design and supervision 
and administration costs for the fiscal year were 
$3,821 and $513, respectively. 
Maintenance: Hired labor surveys, inspections 
and reports cost $614. 
Condition at end of fiscal year. Project was constructed 
by local interests and is complete. 
38. DADE COUNTY, FLA. 
Location. Dade County is on the southeast 
coast of Florida. Project area consists of that part 
of the Atlantic shoreline of the county from 
Government Cut north to Bakers Haulover Inlet 
and at Haulover Beach Park. (See Coast and 
Geodetic Survey chart No. 1248.) 
Existing project. Project provides for a protective 
and recreational beach having a dune at 
elevation 11.5 feet and a level berm 50 feet wide 
at elevation 9 feet; mean low water, for beach erosion 
control and hurricane protection between 
Government Cut and Bakers Haulover Inlet; a 
protective and recreational beach with a berm 
elevation of 9 feet for beach erosion control at 
Haulover Beach Park; and Federal participation 
in the initial construction and in periodic nourishment 
of both the above reaches for the first 10 
years of project life. Plane of reference is mean 
low water. Mean range of tide in the area is 2.5 
feet. 
Estimated cost of the project (Oct. 1982 price 
levels) is $44,000,000 Federal cost and $37,134,000 
non-Federal cost $35,400,000 cash contribution 
and $1,734,000 other costs). 
Project was authorized by Flood Control Act of 
1968 (HD 335/90/2). 
Local cooperation. Local interests must (a) contribute 
for the first cost of the work: between 
Government Cut and Bakers Haulover Inlet 
amounts ranging from 60.2 percent of the cost of 
the fill within the project limit with existing 
shorefront ownership, and 100 percent of the cost 
of fill required landward of the project limit; and 
for the work at Haulover Beach Park, contribute 
21.3 percent of the entire first cost excluding 
costs for lands, easements, rights-of-way, relocations, 
and preproject work, but including credit 
for preproject work; (b) contribute in cost for the 
first 10 years of project life, amounts ranging 
from 88.9 percent of the nourishment cost for the 
beach, with existing ownership, to 60.7 percent 
with public ownership, and the entire 
maintenance cost for the dune, all between 
Government Cut and Bakers Haulover Inlet; (c) 
provide all lands and rights-of-way; (d) hold 
United States free from damages; (e) assure continued 
public ownership and use of the shore upon 
which the amount of Federal participation is based: 
(f) assure maintenance of the groin, and after 
the first 10 years of project life, periodic nourishment 
of the protective beach and maintenance of 
the dune during the economic life of the project; 
(g) assure that water pollution will not be permitted; 
(h) prevent removal or relocation by man of 
fill from the beach berm and dune; (i) prevent the 
erection of barriers to the littoral movement of 
material that would interfere with the nourishment 
of the beach; (j) maintain at the parks qualifying 
for 70 percent Federal participation a zone 
that excludes permanent human habitation; (k) at 
least annually inform interests affected that the 
project will not provide complete protection from 
a hurricane tide level equal to or higher in elevation 
than that of the hurricane of September 1926; 
and (1) establish in public ownership for public use 
the beaches within project limits as a requirement 
for Federal participation in the allocated 
beach erosion control costs of improvement of 
shores presently in private ownership. 
Assurances of local cooperation have been requested 
from the local sponsor. 
Operations and results during fiscal year. New 
work: A contract for sand tightening of the North 
Jetty at Government Cut was awarded on 
January 26, 1983, and costs for this fiscal year are 
$541,185. Engineering and design and superivi- 
9-20

JACKSONVILLE, FLA. DISTRICT 
sion and administration costs were $86,685 and 
$106,555, respectively. 
39. DUVAL COUNTY, FLA. 
Location. On upper east coast of Florida, within 
20 miles of Florida-Georgia line. Ocean shoreline 
is about 16 miles long. (See Coast and Geodetic 
Survey Chart No. 1243.) 
Existing project. Provides for Federal participation 
toward cost of constructing with artificial 
fill, a beach 60 feet wide at elevation 11 
feet above mean low water with a natural slope 
seaward, and for periodic nourishment for 10 
years. Federal participation to be 100 percent of 
the first cost of construction applicable to the 
Federal shore and 50 percent applicable to the 
other publicly owned shore and 55.5 percent of 
periodic nourishment cost for first 10 years of 
project life. Men tidal range at south jetty in St. 
Johns River is 4.9 feet. 
Estimated cost of new work (Oct. 1982 price 
levels) $10,800,000 Federal and $9,859,000 non- 
Federal ($7,700,000 contributed funds and 
$2,159,000 for other costs). 
Project was authorized by River and Harbor 
Act of 1965 (HD 273/89/1). 
Local cooperation. Local interests must contribute 
50 percent of first cost of constructing 
non-Federal publicly owned shores; contribute 
44.5 percent of periodic nourishment costs for 
first 10 years of project life; provide all lands, 
rights-of-way, and relocations; hold the United 
States free from damages; control water pollution; 
and furnish assurances that they will maintain 
continued public ownership of the shore upon 
which the amount of Federal participation is 
based during economic life of project. Assurances 
of local cooperation were accepted on November 
29, 1973. 
Operations and results during fiscal year. New 
work: Engineering and design and supervision 
and administration costs were $54,017 and 
$30,591, respectively. 
Condition at end of fiscal year. Initial beach fill 
and four year advance nourishment has been completed. 
40. EL TUQUE BEACH, P.R. 
Location. The project area is located at El Tuque 
Beach on the south coast of Puerto Rico about 
5 miles west of the city of Ponce. 
Existing project. The authorization provides 
for a protective and recreational beach by the 
placement of about 60,000 cubic yards of fill 
material along the eroded shoreline of El Tuque 
Beach. The new fill will be stabilized by the construction 
of a shore-connected rubble breakwater 
at the south end of the beach fill and by an offshore 
breakwater parallel to the northerly section 
of shore under consideration. The shoreconnected 
breakwater would extend seaward a 
distance of about 900 feet from a point on the 
shore 300 feet north of the south-west corner of 
the park. The offshore breakwater would be 
located about 500 feet offshore, be 1,000 feet in 
length, and run generally parallel to the northwestern 
shore. Estimated cost of the project (Jul. 
1981 price level) is $968,800 Federal costs and 
$415,200 non-Federal constribution. (See Table 
9-B for Authorizing Legislation.) 
Local cooperation. Local interests must (a) provide 
without cost to the United States all 
necessary lands, easements, rights of way, and 
relocations required for construction and subsequent 
mainenance of the project. (b) Hold and 
save the United States free from all claims for 
damanges which may result from construction 
and subsequent mainenance of the project, except 
damages due to the fault or negligence of the 
United States or its contractors. (c) Provide 
without cost to the United States appropriate access 
and facilities including parking and sanitation, 
necessary for realization of the public 
benefits upon which Federal participation is based, 
and administer and maintain the beach for 
continued public use during the economic life of 
the project. (d) Assume maintenance and repair 
during the economic life of the project as required 
to serve the intended purpose. (e) Provide a cash 
contribution for beach erosion control equal to 
the appropriate percentage of the final construetion 
cost allocated. This function exclusive of 
lands, easements, rights-of-way, alterations, and 
relocations. The percentage to be in accordance 
with existing law and based on shore ownership 
and existing at the time of construction, which 
contribution is presently estimated at $415,200 
(30 percent). (f) Assume full responsibility for all 
project costs in excess of the Federal cost limitations 
of $1,000,000 for the Corps of Engineers portion 
of the work. (g) Comply with the provisons of 
the Uniform Relocation Assistance and Real Property 
Acquisition Policies Act of 1970 (Public 
Law 91-646). 
Operations and results during fiscal year. New 
work: Contract for beach restoration, groin and 
breakwater was awarded August 1982. Costs this 
fiscal year were $321,314. Engineering and design 
and supervision and administration costs for the 
year were $3,770 and $150,239, respectively. 
9-21

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
41. FORT PIERCE, FLA. 
Location. Fort Pierce Beach erosion project 
fronts the Atlantic Ocean and is on coastal barrier 
island in St. Lucie County which separates Indian 
River from the ocean. Area is 120 miles north of 
Miami and about 225 miles south of Jacksonville. 
(See Coast and Geodetic Survey Chart 582.) 
Existing project. Provides for Federal participation 
in the cost of a shore restoration and 
protection project which involves construction 
and periodic nourishment for 10 years. Federal 
participation amounts to one-half such costs for 
that part of the ocean shoreline extending 1.2 
miles southward of Fort Pierce navigation inlet, 
and 70 percent of such costs for the adjacent 0.1 
mile shoreline known as Lions Club Beach Park. 
Mean range of tide in area is 2.6 feet. Cost 
estimate (Oct. 1982 price levels) is $3,230,000 
Federal and $3,020,000 non-Federal. Project was 
authorized by 1965 River and Harbor Act (HD 
84/89/1) as modified by section 102 of 1968 River 
and Harbor Act. 
(See Table 9-B for Authorizing Legislation.) 
Local cooperation. Local interests must contribute 
one-half the costs of protecting and 
periodically nourishing for 10 years the reach of 
shoreline starting at and extending 1.2 miles 
south of Fort Pierce Inlet and 30 percent of cost 
of protecting and periodically nourishing 0.1 mile 
of shoreline known as Lions Club Beach Park; obtain 
approval by Chief of Engineers of detailed 
plans and specifications for the project; establish 
in public ownership and beach within project 
limits prior to reimbursement; furnish all lands 
and rights-of-way; furnish assurances that they 
will maintain continued public ownership of the 
publicly owned shores; exclude permanent human 
habitation and provide full park facilities at the 
Lions Club Beach Park; provide periodic nourishment 
of the beach; control water pollution; hold 
United States free from damages; and execute 
such further assurances and agreements as may 
be necessary to carry out the intent of Congress 
expressed in the acts authorizing or modifying 
the project. River and Harbor Act of 1965 
authorized construction of the project by local interests. 
Section 102 of 1968 River and Harbor Act 
modified the project to provide for construction 
by Secretary of Army and section 215 of the same 
act permitted construction by local interests. 
Local interests have elected to construct the project. 
Assurances of local cooperation were accepted 
January 2, 1969. 
Operations and results during fiscal year. New 
work: Engineering and design costs were $69. 
Condition at end of fiscal year. Initial beach 
nourishment has been completed. 
42. MANATEE COUNTY FLA. 
Location. Manatee County is on the west coast 
of Florida just south of the entrance to Tampa 
Bay. (See Coast and Geodetic Survey Chart No. 
1256.) 
Existing project. The authorization provides 
for Federal participation toward cost of a shore 
restoration and protection project. The plan provides 
for the entire 7.5 mile shoreline of Anna 
Maria Key and will consist of 3.2 miles of gulf 
shore beach to elevation 6 feet above mean low 
water with a 50 foot berm width and a natural 
slope seaward as would be shaped by wave action. 
Also, the project consists of periodic nourishment 
of the restored beach and such adjacent shoreline 
as may be needed and justified for the 50-year 
project life. Plane of reference is mean low water. 
Cost estimate for new work (Oct. 1981 price 
levels) is $8,100,000 Federal and $8,444,000 non- 
Federal ($8,100,000 contributed funds and 
$344,000 for other costs). If public ownership of 
the private beaches is established before construction 
of the improvements the local share of 
the estimated first cost of construction and 
periodic nourishment would be reduced from 85.8 
percent to 48.9 percent. (See Table 9-B for 
Authorizing Legislation.) 
Local cooperation. Local interest must: (a) provide 
without cost to the United States all lands, 
easements, and rights-of-way, including borrow 
areas, and relocations necessary for construction 
of the improvements; (b) provide a cash contribution 
equal to 85.8 percent of the first cost of construction, 
subject to any credit for eligible construction 
costs incurred by local interests, and exclusive 
of costs for lands, easements, rights-ofway, 
relocations and alterations, the final percentage 
to be based on shore ownership and use existing 
at the time of construction; (c) provide a 
cash contribution for periodic beach nourishment 
equal to 85.8 percent of the annual nourishment 
cost, such contribution to be made prior to each 
nourishment operation, and the final percentage 
to be based on shore ownership and use existing 
at the time of construction; (d) hold and save the 
United States free from damages due to the construction; 
(e) assure continued public ownership 
and administration of the shore upon which the 
amount of Federal participation is based; (f) provide 
without cost to the United States appropriate 
access and facilities, including parking 
and sanitation, necessary for realization of the 
public benefits upon which Federal participation 
is based; (g) adopt appropriate ordinances, or provide 
other means, to insure the intended use of 
the beach fill areas; and (h) control water pollution 
to the extent necessary to safeguard the 
health of bathers. 
9-22

JACKSONVILLE, FLA. DISTRICT 
Operations and results during fiscal year. New 
work: Engineering and design costs for the year 
were $15. 
43. PALM BEACH COUNTY, FLA., FROM 
MARTIN COUNTY LINE OF LAKE 
WORTH INLET AND FROM SOUTH 
LAKE WORTH INLET TO BROWARD 
COUNTY LINE. 
Location. Palm Beach County is on east coast of 
Florida about 300 miles south of Jacksonville and 
70 miles north of Miami. Northerly reach of the 
project is separated from the southerly reach by 
Palm Beach Island. Project consists of about 12.2 
miles of ocean coastline. (See Coast and Geodetic 
Survey Charts 1247 and 1248.) 
Existing project. Provides for Federal participation 
toward the cost of local shore project 
for restoration of beaches to a general width of 
100 feet with a berm elevation of 10 feet above 
mean low water, and periodic nourishment for 10 
years from the year of initial nourishment, as 
follows: 4.8 percent of the cost for the Martin 
County line- Jupiter Inlet segment; 11.6 percent 
of cost for Jupiter Inlet-Lake Worth Inlet segment; 
and 5.1 percent for South Lake Worth Inlet 
-Boca Raton Inlet segment. Mean range of 
tide is 2.8 feet in the Atlantic Ocean at Palm 
Beach and 2.3 feet at Boca Raton Inlet. Estimated 
cost (Oct. 1982 price levels) is $6,900,000 Federal 
and $20,600,000 cash contribution. (See Table 9-B 
for Authorizing Legislation.) 
Local cooperation. Local interests must obtain 
approval by Chief of Engineers of plans and 
specifications prior to commencement of work 
and furnish assurances that they will maintain 
public ownership of publicly owned shores, maintain 
protective measures and provide periodic 
nourishment of protective beaches, and control 
water pollution. 
Operations and results during fiscal year. New 
work: Engineering and design and supervision 
and administration costs were $38,130 and $6,774, 
respectively. 
Condition at end of fiscal year. Local interests 
provided initial beach fill at Delray Beach which 
was completed in August 1973. A periodic 
nourishment contract at Delray Beach was 
awarded in FY1978 by local interests and the contract 
has been completed. 
44. PINELLAS COUNTY, FLA. 
Location Pinellas County is on the Gulf coast of 
Florida, about midway of the peninsula. It extends 
northerly about 39 miles from the main entrance 
to Tampa Bay to the vicinity of the mouth 
of Anclote river. (See Coast and Geodetic Charts 
Nos. 858 and 1257.) 
Previous project. For details see page 429 of 
Annual Report for 1965. 
Existing project. The authorized project provides 
for Federal participation in preserving and 
protecting the shores of Pinellas County, Florida, 
by: restoration of 5,000 feet of beach at Clearwater 
Beach Island; restoration of 49,000 feet of 
beach at Sand Key; restoration of 9,200 feet of 
beach at Treasure Island; construction of 600 feet 
of revetment at Long Key; and advance nourishment 
of Long Key and periodic nourishment of 
each island. Estimated cost (Oct. 1982 price levels) 
is $13,300,000 Federal funds and $14,762,000 non- 
Federal funds. (See Table 9-B for Authorizing 
Legislation.) 
Local cooperation. Local interests must: (a) contribute 
in cash the required percentages of the 
first costs of work provided by the Corps of 
Engineers, the percentages varying with the type 
of beach ownership; 94.1 to 50 percent of the 
beach restoration at Clearwater Beach; 98.1 to 50 
percent of the improvement at Sand Key; 94.3 to 
50 percent of the improvement at Treasure 
Island; and 50 percent of the first cost of the 
revetment at Long Key; (b) contribute in cash an 
amount computed in accordance with the cost 
sharing provision contained in P.L. 826, 84th Congress 
as amended by P.L. 87-874, for beach 
nourishment cost for the first 10 years of the project 
life; (c) provide lands, easements, and rightsof-
way; (d) assure maintenance and repair of the 
stone revetment of Long Key; (e) assure periodic 
nourishment of the restored beaches; (f) assure 
public ownership of beaches; (g) assure against 
water pollution; (h) hold the United States free 
from damages; and (i) provide beach for public 
use. Assurances of local cooperation were accepted 
March 22, 1967. 
Operations and results furing fiscal year. New 
work: Contract for Treasure Island 4th periodic 
beach nourishment and groin extension was 
awarded September 1982. Costs for this fiscal 
year were $866,354. Engineering and design and 
supervision and administration costs for the fiscal 
year were $82,227 and $99,455, respectively. 
Condition at end of fiscal year. Construction of 
the project commenced in 1969 and is 20 percent 
completed. Total costs under existing project 
through September 30, 1983 were $2,064,748 
Federal funds and $1,929,780 contributed funds 
for new work and $5,625 for maintenance. 
45. PUNTA SALINAS, P.R. 
Location. The project is located on the north 
coast of Puerto Rico on the Punta Salinas Penin- 
9-23

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
sula about five miles west of San Juan, Puerto 
Rico. (See Coast and Geodetic Survey Chart No. 
903.) 
Existing project. Provides for Federal participation 
in the cost of shore restoration of the 
east and west shores of the Punta Salinas Recreation 
Area. The selected plan consists of beach fill 
(about 58,000 cubic yards) which will provide an 
average 140,foot protective and recreational 
beach at MHW for the west peninsula shoreline; 
two anchor groins 225-feet long and both consisting 
of 10,500 tons of stone at each end of the 
west shore to anchor and retard the movement of 
the fill material and; a stone revetment for 2,500 
feet of the east peninsula shore consisting of 5,500 
tons of stone and 25,000 square feet of filter cloth 
to eliminate shoreline recession along this sector. 
The Federal share for initial construction cost is 
70%. The project cost is $1,008,000, including 
engineering and design and supervision and administration. 
(See Table 9-B for authorizing 
legislation.) 
Local cooperation. Local interests must (a) provide 
without cost to the United States all lands, 
easements, and rights of way necessary for the 
construction and subsequent maintenance and 
nourishment of the project. (b) accomplish 
without cost to the United States all alterations 
and locations of buildings, transportation 
facilities, storm drains, utilities, and other structures, 
and improvements made necessary by the 
contruction. (c) Hold and save the United States 
free from all claims for damages due to constuction 
and subsequent maintenance of the project, 
except damages due to the fault of negligence of 
the United States or its contractors. (d) Provide a 
cash contribution for beach erosion control equal 
to the appropriate percentage of the final construction 
cost allocated to this function exclusive 
of lands, easements, rights of way, alterations, 
and relocations. The percentage to be in accordance 
with shore ownership. The Commonwealth 
of Puerto Rico has contributed $300,000 which 
represents 30 percent of the project cost. (e) Provide 
an additional cash contribution for the cost 
of periodic beach nourishment every 5 years, 
presently estimated at $11,900. (30.0 percent) annually, 
until the $1,000,000 limitation of the Section 
103A Small Projects Authority is reached. 
These percentages also to be revised in accordance 
with shore ownership and use at the time of 
construction. (f) Provide without cost to the 
United States appropriate access and facilities, 
including parking and sanitation, necessary for 
realization of the public benefits upon which 
Federal participation is based, and administer 
and maintain the beach for continued public use 
during the life of the project. (g) Adopt appropriate 
ordinances or provide other means to 
insure preservation of the beach fill areas, control 
water pollution to the extent necessary to 
safeguard the health of bathers, maintain and 
operate all structures after completion in accordance 
with regulations prescribed by the 
Secretary of the Army and comply with the provisions 
of the Uniform Relocation Assistance and 
Real Property Acquisition Policies Act of 1970 
(Public Law 91-646). 
Operations and results during fiscal year. New 
work: A contract for beach nourishment was 
awarded 15 April 1981 and incurred costs of 
$48,294 for the fiscal year. Engineering and 
design and supervision and administration costs 
were $25 and $1,764 respectively. 
Condition at end of fiscal year. Construction of 
project was essentially completed in March 1982. 
Restoration of storm damage to the stone revetment 
is scheduled for completion in early fiscal 
year 1984. 
46. OTHER AUTHORIZED BEACH EROSION 
CONTROL PROJECTS 
(See Table 9-J.) 
47. BEACH EROSION CONTROL 
ACTIVITIES UNDER SPECIAL 
AUTHORIZATION 
Beach erosion control activities pursuant to section 
103, Public Law 87-874 (preauthorization) 
Reports incurring costs during the fiscal year 
were Dunedin Shores, Fla., $46, Ft. Clinch State 
Park, Fla., $5, and Key Biscayne, Fla., $30,392. 
Beach erosion control activities pursuant to section 
III, Public Law 90-483 Mitigation of Shore 
Damages Attributable to Navigation Projects 
No costs were incurred under the above 
authorization. 
Beach erosion control activities pursuant to 
Shoreline Erosion Control Act of 1974, Public 
Law 93-251. 
The Shoreline Erosion Control Demonstration 
Program included costs of $48 for Key West, Fla. 
and $24 for demonstration. - 
Flood Control 
48. CENTRAL AND SOUTHERN FLORIDA 
Location. The project is located generally 
within the southeastern eighteen counties of 
Florida covering an area of about 15,200 square 
miles. It is comprised of the Upper St. Johns 
River basin in the northeastern section of project, 
Kissimmee River basin in central section above 
the Lake Okeechobee-Everglades area in the cen- 
9-24

JACKSONVILLE, FLA. DISTRICT 
tral and southwestern section, and the east coast 
Everglades area in southeastern section. 
Previous projects. Completed works for control 
of Lake Okeechobee were included in and constructed 
under the navigation project for 
Okeechobee Waterway, Fla. (formerly Caloosahatchee 
River and Lake Okeechobee drainage 
area, Fla.) and under provisions of River and Harbor 
Acts of July 3, 1930, and August 30, 1935. For 
further information, see Annual Reports, 1948 
and 1949. 
Existing project. The authorized project is for 
flood relief and water conservation and provides 
principally for: an east coast protective levee extending 
from the Homestead area north to the 
eastern shore of Lake Okeechobee near the St. 
Lucie Canal; three conservation areas for water 
impoundment in the Everglades area west of the 
east coast protective levee with control structures 
to effect transfer of water as necessary; 
local protective works along the lower east coast; 
encirclement of the Lake Okeechobee agricultural 
area by levees and canals; enlargment of 
portions of Miami, North New River, Hillsboro, 
and West Palm Beach Canals; enlargement of the 
existing Lake Okeechobee levees and construction 
of new levees on the northeast and northwest 
shore of the lake; increased outlet capacity for improved 
control of Lake Okeechobee; floodway 
channels in the Kissimmee River basin, with 
suitable control structures to prevent overdrainage; 
an interrelated system of canals, 
levees, pumping stations, and structures in 
southwest Dade County to control water levels; 
and facilities for regulating floods in the Upper 
St. Johns River basin; a system of canals and control 
structures for gravity drainage of Martin 
County and distribution of available water supplies 
to portions of Martin and St. Lucie Counties; 
and works to improve the supply, distribution, 
and conservation of water resources in central 
and southern Florida, including the Lake 
Okeechobee agricultural area, Everglades National 
Park, and other related areas. The project 
will provide water control and protection from 
recurrence of the devastating floodwaters from 
the Everglades and local sources, for the highly 
developed urban area along the lower east coast 
of Florida and for the productive agricultural 
areas around Lake Okeechobee (including towns 
around lake), in the Upper St. Johns and Kissimmee 
River basins, and in South Dade County. Project 
also provides for navigation improvements 
suitable for recreational craft, consisting of locks 
and channel dredging in the upper Kissimmee 
and St. Johns basins. 
The project includes a total of 897 miles of 
levees, 954 miles of canals, 30 pumping plants, 194 
floodway control and diversion structures, 55 
railroad bridge relocations, and 2 highway bridge 
relocations. 
The project also provides that upon completion, 
local interests assume operation and 
maintenance of all completed works except 
levees, channels, locks, and control works for 
regulation of Lake Okeechobee and the main control 
structures of conservation areas, which will 
be operated and maintained by the United States. 
The principal features of the hurricane gates, 
constructed under previous projects for 
Okeechobee Waterway and maintained under existing 
project since July 1, 1950, are set forth in 
Table 9-K. See also Table 9-L for principal 
features of locks and dams. 
Estimate of cost for new work (Oct. 1982 price 
levels) is $767,050,000 Federal funds ($765,000,000 
Corps and $2,050,000 U.S. Coast Guard) and 
$206,000,000 contributed funds, exclusive of river 
and harbor funds expended on previous projects. 
Local interests' costs in reviewing plans and 
specifications are expected to be $625,000. In addition, 
estimated cost to local interests of lands, 
rights-of-way, and relocations is $190,105,000. 
(See Table 9-B for Authorizing Legislation.) 
Local cooperation. (See Table 9-M for local cash 
contribution.) Local interests must also: provide 
lands, rights-of-way, and spoil disposal areas; hold 
the United States free from damages; bear the 
cost of maintenance and operation of all works except 
those having to do with regulation of Lake 
Okeechobee and the main control structures of 
conservation areas; construct and maintain 
lateral drainage facilities; prohibit encroachment 
on flood-carrying capacity of the improved channels; 
and assume cost of all new highway bridges, 
relocations of existing bridges and alterations to 
utilities incident to construction of the project. In 
addition, for small boat navigation channels, local 
interests must provide, maintain, and operate 
adequate public landings, sanitary and access 
facilities, and establish regulations prohibiting 
discharge of pollutants into the waters of the 
locks and channels by users thereof. 
Assurances of local cooperation have been accepted 
by the District Engineer for all items of 
work authorized to date except those for the 
Small Boat Navigation feature added in 1970 
under Section 201 of the Flood Control Act of 
1965. 
Operations and results during fiscal year. (See 
Table 9-N for work accomplished.) 
Operations and care. a. Features completed 
under previous navigation project for 
Okeechobee Waterway and being maintained 
9-25

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
under this project are: a levee about 70 miles long 
following in general the south shore of Lake 
Okeechobee and a north shore levee 15.8 miles 
long; spillways at Ortona and St. Lucie locks; 5 
hurricane gates; 20 gated drainage culverts 
through the levee; and 16 spillways along St. 
Lucie Canal. 
b. Features completed under existing project 
that are to be maintained with operation and 
maintenance funds are: (1) Levees 47, 48, 49 and 
50 - total length 63 miles and enlargement of existing 
levees L-D1, L-D2, L-D3, L-D4, and L-D9, (2) 
spillway structures S-10, S-11, S-12, S-18C, S-77, 
and S-78 (3) C-43, Sec. 4 (Caloosahatchee River), 
and (4) W. P. Franklin Lock and Dam. 
In addition to the actual facilities listed above 
it is necessary under operation and maintenance 
to continue meteorological studies, water level 
records, stream gaging stations, etc., for proper 
regulation of the level of Lake Okeechobee and 
storage of water in Conservation Areas 1,2 and 3. 
REGULATION 
Corps o Engineers - The Corps of Engineers 
operates aid maintains the major outlets to Lake 
Okeechobee\ and Water Conservation Area Nos. 
1, 2A and 3A'n central and southern Florida. During 
the period, Lake Okeechobee continued to be 
regulated under a regulation schedule ranging 
from 15.5 feet to 17.5 feet, NGVD. Regulatory 
discharges were made from January 21 to May 13 
through the Caloosahatchee River and from 
January 31 to May 12 through the St. Lucie 
Canal. Culvert 10A was also used between April 6 
and 26. The Conservation Areas were regulated 
under the following regulation schedules: a. WCA 
#1: from 14.0 to 17.0 feet, NGVD., b. WCA #2A: 
from 9.5 to 12.5 feet, NGVD., c. WCA #3A: from 
9.5 to 10.5 feet, NGVD. The Water Conservation 
Area 2A drawdown was suspended during the year 
due to heavy rains in the area. As a consequence, 
the drawdown period was extended to two years. 
South Florida Water Management District - 
SFWMD is responsible for operation and 
maintenance of the remainder of the project 
facilities, including major pumping stations, 
spillways, locks (except on Okeechobee Waterway), 
levees and culverts. 
Condition at end of fiscal year. The project was 
about 45 percent complete. Planning for the en. 
tire project began in November 1948 and has 
been continued. For construction completed prior 
to Fiscal Year 1980 see Annual Reports for 
1960-1979. Construction completed under existing 
project during the fiscal year is set forth in Table 
9-0. All Federally maintained features of the project 
were generally in good condition at the end of 
the fiscal year. (For status of work under contract 
at end of fiscal year see Table 9-P.) 
Total Federal costs under the existing project 
through September 30, 1983 were $264,453,681 
for new work, $37,458,630 for maintenance, a total 
of $301,912,311. In addition, $49,064,817 has been 
expended from contributed funds for new work. 
49. FOUR RIVER BASINS, FLA. 
Location. The Four River Basins area covers 
about 6,000 square miles within 14 counties in 
central and southwest peninsular Florida. Project 
includes all or part of the four main stream 
basins-the Hillsborough, Oklawaha, Withlacoochee, 
and Peace Rivers-and all of three 
smaller coastal basins north of Tampa, Florida, 
drained by the Pithlachascotee and Anclote 
Rivers and Lake Tarpon. 
Existing project. The authorized project provides 
for improvements for control of floods and 
drainage, and for water conservation through 
construction of necessary canals, levees, reservoirs, 
and control structures. More specifically, 
the project provides for: Green Swamp Area-a 
conservation area and three storage reservoirs 
with necessary canals and control structures; 
Hillsborough River-four flood-storage reservoirs, 
with necessary channels, control structures, 
and levees; Oklawaha River-a levee on 
the north shore of Lake Apopka, improvement of 
part of the river channel and a west bank levee 
below Moss Bluff lock and dam, and replacement 
of the lock and dam; Withlacoochee River-one 
flood-storage reservoir with outlet canals and 
control structures; Peace River-Peace Creek 
canal and control structures and improvements to 
the existing water control and drainage features; 
Gulf Coastal Areas-Lake Tarpon: outlet canal 
and control structure; Anclote River: control 
structure and channel improvement; 
Pithlachascotee River: reservoir with outlet 
canals and control structures. (See Table 9-Q on 
Moss Bluff Lock.) 
Estimated cost for new work (Oct. 1982 price 
levels) is $197,000,000 Federal funds and 
$123,000,000 non-Federal cost. $41,000,000 contributed 
funds; $48,142,000 for lands and 
damages; and $33,858,000 for relocations. (See 
Table 9-B for Authorizing Legislation.) 
Local cooperation Local interests must furnish 
all lands, and rights-of-way; provide all alterations 
or replacements of public and private 
utilities, roads, bridges (except railroad bridges), 
etc.; hold the United States free from damages; 
operate and maintain all project works after completion; 
construct and maintain such associated 
works as are necessary to realize benefits made 
9-26

JACKSONVILLE, FLA. DISTRICT 
available by the project works; and contribute in 
cash 17 percent of the first cost of construction. 
Operations and results during fiscal year. New 
work: Contract costs for construction of 5-159 Upper 
Structure and C-135, S-155 bypass closure and 
S-159 (upper) wingwall stabilization for the year 
were $220,100. Contract for construction of 
recreation area, Morris Bridge and Flint Creek 
sites was awarded December 6, 1982. Contract 
costs for the year were $638,441. Contract costs 
this year for construction of Moss Bluff Lock and 
Dam Recreation were $213. Hired labor operation 
cost $1,085. Engineering and design and supervision 
and administration costs were $347,622 and 
$218,000, respectively. 
Condition at end of fiscal year. Construction of 
the project commenced April 18, 1966 and is 38 
percent complete. See Table 9-R for construction 
of major features of the project completed to 
date. 
50. PORTUGUES AND BUCANA RIVERS 
P.R. 
(This project authorized as Lago de Cerrillos, 
Lago de Portugues, and Channel Improvement at 
Ponce.) 
Location. Portugues and Bucana Rivers 
originate on the southern slopes of Cordillera 
Central divide of Puerto Rico and flow from this 
central ridge of the island to the Carribean Sea. 
Their drainage areas are 22.6 and 31.4 square 
miles, respectively. Ponce, the second largest city 
in Puerto Rico, is located in the lower coastal area 
along Portugues River and is the only urban community 
in the two basins. 
Existing project. The authorized project provides 
for two multiple-purpose reservoirs for 
flood control, water supply, general recreation, 
and fish and wildlife enhancement-one on Portugues 
River and the other on Cerrillos River, a 
tributary to the Bucana River; enlargement of 
about 5.7 miles of the Bucana River, with an additional 
0.2-mile tieback levee at the upstream terminus 
of the improvement; enlargement of 2.1 
miles of the Portugues River, with an additional 
0.5 mile of tieback levee at the upstream terminus 
of the improvement; and a 1.3 mile diversion channel 
connecting Portugues River to lower Bucana 
River. Estimated cost of the project (Oct. 1982 
price levels) is $261,000,000 Federal cost and 
$77,500,000 non-Federal cost ($53,006,000 for 
lands and damages; $14,190,000 for relocations; 
and $10,304,000 for highway bridges). (See Table 
9-B for Authorizing Legislation.) 
Local cooperation. Local interests must provide 
all lands, easements and rights-of-way; hold 
the United States free from damages; operate 
and maintain all project works after completion; 
repay construction cost allocated to water supply 
in accordance with Water Supply Act of 1958; pay 
one-half of the separable cost allocated to recreation 
and fish and wildlife enhancement; prohibit 
discharge of inadequately treated sewage and 
other pollutants into the reservoir; and prevent 
encroachment on downstream channels. 
Assurances of local cooperation have not been accepted. 
Operations and results during fiscal year. New 
work: Contract work for improvement on the Upper 
Bucana Channel, Section 3, Section 5C, Section 
6A and Section 6B continued with costs for 
the year of $982,263, $554,189, $1,965,438 and 
$1,370,351. A contract for improvement on the 
Upper Bucana Channel, Section 4 was completed 
in August 1982 at a cost of - $52,211. Contract for 
landscape development and fencing of lower channel 
improvements continued with costs for the 
year of $88,714. Contract for Portugues Channel 
improvements Section 6C was awarded 
September 30, 1983. No costs were incurred during 
year. Contract for Upper Bucana Channel improvement 
Bucana debris basin control structure 
was awarded September 20, 1982. Costs incurred 
during the fiscal year were $1,749,557. Contract 
for Cerrillos Dam River Divertion and foundation 
preparation was awarded September 22, 1982. 
Costs incurred during the fiscal year were 
$5,493,384. Engineering and design and supervision 
and administration costs were $4,011,353 and 
$2,160,073, respectively. 
Condition at end of fiscal year. Construction of 
the project commenced in September 1975 and is 
29 percent complete. 
51. INSPECTION OF COMPLETED FLOOD 
CONTROL PROJECTS 
Features transferred to the Central and 
Southern Florida Flood Control District and 
Southwest Florida Water Management District 
were inspected quarterly during the fiscal year at 
a total cost of $20,815. 
52. OTHER AUTHORIZED FLOOD CONTROL 
PROJECTS 
(See Table 9-S.) 
53. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control activities pursuant to section 
205, Public Law 685, 84th Congress, as amended 
(preauthorization). 
9-27

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
(See Table 9-T.) General Investigations 
Emergency flood control activities-repair, 
flood fighting, and rescue work (Public Law 99, 
84th Congress and antecedent legislationi. 
Federal costs for the fiscal year were $182,981 
for the Disaster Preparedness Program, $71,225 
for national emergency preparedness program, 
$85,630 for emergency operations, and $18,054 for 
a rehabilitation report for Central and Southern 
Florida project for a total of $802,889. 
Emergency streambank and shoreline protection 
activities pursuant to Section 14, Public Law 
526, 79th Congress as amended (preauthorisation) 
Federal costs for the fiscal year were $7,500 for 
Route AIA, Bethune Beach, Florida, and $7,500 
for Route AlA, Flagler Beach, Florida. 
54. SURVEYS 
Hired labor costs during the fiscal year (all 
Federal funds) were: navigation studies, $342,219, 
flood damage prevention studies $1,638,939, 
shoreline protection studies, $118,952 and special 
studies $218,570 for a total of $2,318,680. 
55. COLLECTION AND STUDY OF BASIC 
DATA 
Costs for Inspection of Dams amounted to $64. 
The requirement for preparation of regular 
flood plain information studies has been rescinded. 
FPI studies that deal with land use changes 
will continue to be prepared. FPMS Unit Jacksonville, 
Fla., $82,672. Gold coast hurricane evacuation 
study, $71,800. Technical services, $77,096. 
9-28

JACKSONVILLE, FLA. DISTRICT 
TABLE 9-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 80 FY 81 FY 82 FY 83 Sept. 30, 1983 
Aquatic Plant New Work: 
Control (R&H Approp. 
Act of 1965) Cost 
(Federal Funds) 
Arecibo Harbor, New Work: 
P.R. Approp. 
(Federal Funds) Cost 
Maint: 
Approp. 
Cost 
Atlantic New Work: 
Intracoastal Approp. 
Waterway Cost 
between Maint: 
Norfolk, Va. and Approp. 
St. John's River, Cost 
Fla. 
(Federal Funds) 
Canaveral 
Harbor, Fla. 
(Federal Funds) 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
2,225,000 2,028,100 1,415,400 1,991,000 
2,339,816 2,077,761 1,329,420 2,074,745 
14,762,670 
14,666,502 
- - - 1,128,075' 
- - - 1,128,075" 
571,742 48,153 451,914 2,181,446 
31,172 586,784 42,308 1,769,901 
141,000 
148,660 
126,784 2,642,645 1,073,000 
126,804 63,907 3,121,103 
5,061,000 1,447,700 
4,342,280 3,468,328 
361,225 
361,225' 
5,362,313 
4,831,654 
80,000 200,000 7,621,9103 
79,956 132,655 7,554,521 
554,990 4,924,000 25,877,821 
445,286 5,014,000 25,849,047 
Channel from New Work: 
Naples to Big Approp. 
Marco Pass, Fla. Cost 
(Federal Funds) Maint: 
Approp. 
Cost 
(Contrib. Funds) New Work: 
Approp. 
Cost 
Charlotte New Work: 
Harbor, Fla. Approp. 
(Federal Funds) Cost 
Maint: 
Approp. 
Cost 
Clearwater New Work: 
Pass, Fla. Approp. 
(Federal Funds) Cost 
Maint: 
Approp. 
Cost 
Cross-Florida New Work: 
Barge Canal Approp. 
(Federal Funds) Cost 
Maint: 
Approp 
Cost 
Fernandina New Work: 
Harbor, Fla. Approp. 
(Federal Funds) Cost 
Maint: 
Approp. 
Cost 
(Contrib. Funds) New Work: 
Approp. 
Cost 
Fort Myers New Work: 
Beach, Fla. Approp. 
(Federal Funds) Cost 
Maint: 
Approp. 
Cost 
525,255 
561,201 
770,800 
771,152 
68,700 
68,639 
7,131 
5,631 
1,837 
3,146 
788,200 2,613,000 
757,998 2,642,802 
- 177 
9,063 
9,324 
82,438 
6,884 
25,814 
25,991 
- - 20,000 - 
- - 1,655 20,685 
1,865,800 1,262,308 1,655,000 2,240,347 
1,324,473 1,313,848 1,407,447 1,995,672 
- 254,000 - - 
554,528 20,494 325 
2,343,300 4,040,000 2,328,000 
2,343,679 4,037,075 1,474,260 
105,000 - - 
524,765 72,130 7,116 
371,700 
407,661 
5,365 
5,293 
7,141 
716,000 
965,781 
7,000 
7,141 
229 13,521 
229 13,654 
805,290 
305,290 
921,698 
921,698 
159,975 
159,975 
533,169 
533,1694 
8,609,964 
8,533,946 
46,3494' 
46,349' 
1,192,532 
1,192,532 
62,862,473 
62,860,810 
14,757,463 
14,250,203's 
4,149,8168 
4,095,0828 
16,126,439 
15,524,542 
812,000 
810,903 
158,140' 
158,140' 
662,421 
662,421 
9-29 
1. 
2. 
4. 
6. 
7. 
8. 
9. 
10.

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 9-A COST AND FINANCIAL STATEMENT 
See 
Sects.. Total Cost to 
k Text Project 
Fort Pierce 
Harbor, Fla. 
(Federal Funds) 
(Contrib. Funds) 
12. Intracoastal 
Waterway, 
Caloosahatchee 
River to Anelote 
River, Fla. 
(Federal Funds) 
13. Intracoastal 
Waterway, 
Jacksonville to 
Miami, Fla. 
(Federal Funds) 
14. Jacksonville 
Harbor, Fla. 
(Federal Funds) 
(Contrib. Funds) 
15. Johns Pass, Fla. 
(Federal Funds) 
16. Longboat 
Pass, Fla. 
(Federal Funds) 
(Contrib. Funds) 
17. Mayaguesz 
Harbor, P.R. 
(Federal Funds) 
18. Miami Harbor, 
Fla. 
(Federal Funds) 
(Contrib. Funds) 
19. New Pass 
Sarasota, Fla. 
(Federal Funds) 
11. 
Feadig FY 80 FY 81 FY 82 FY88 Sept. 30, 1983 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
ost 
New Work: 
pprop. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
92,262 
58,026 
69,127 
60,139 
761,000 
668,579 
1,215,646 
985,514 
773,000 
115,111 
1,207,620 
1,284,573 
8356,056 
356,056 
8,711,780 
3,444,143 
18,574 
18,574 
8,112,557' 
8,112,5578 
5,496,288' 
4,829,249' 
19,251,59810 
19,250,88910 
24,165,423" 
24,131,986" 
173,015 
169,816 
52,500 
55,625 
688,908 
759,084 
2,441,000 
3,471,285 
4,500 
4,431 
185,000 
186,8330 
287 
798,000 
828,885 
- 68,613 
- 68,404 
4,711,635 
2,819,143 
43,986 
268,800 
301,415 
41,887 
41,869 
6,657 
8,136 
-414 
3,229 
-708 
711 
82,098" 
81,755" 
759,557 
759,557 
1,020,2833 
1,020,283 
827,962 
827,962 
172,324 
172,324 
168,187 
168,187 
984,479 
984,479 
130,000 24,696,066' 
271,416 24,685,677a 
29,868 2,208,843 
29,868 2208,843 
- 2,262,710" 
- 2,262,710"' 
8,239 
9,119 
45,8111" 
45,8111 
2,138,411 
2,138,411 
41,184 
85,128 
85,726 
47,595 
5,327 
266,900 
24,865 
150,000 
24,282 
25,047 
25,047 
94,300 
93,935 
95,000 
33,911 
54,205 
294,822 
150,000 
128,913 
32,663 
32,6683 
695,000 
755,574 
9-30 
- - 47,596,2781" 
- - 47,596,278"s 
1,928,000 3,007,099 42,009,685" 
2,754,261 339,545 39,307,986" 
- - 102,813 
- - 102,818 
- - 927,654"' 
- - 927,654" 
338,000 
342,621 
687,000 
721,506

JACKSONVILLE, FLA. DISTRICT 
TABLE 9-A COST AND FINANCIAL STATEMENT 
in Text Project 
Okeechobee 
Waterway, Fla. 
(Federal Funds) 
(Contrib. Funds) 
21. Oklawaha 
River, Fla. 
(Federal Funds) 
22. Palm Beach 
Harbor, Fla. 
(Federal Funds) 
23. Ponce de Leon 
Inlet, Fla. 
(Federal Funds) 
(Contrib. Funds) 
24. Ponce Harbor, 
P.R. 
(Federal Funds) 
25. Port Everglades 
Harbor, Fla. 
(Federal Funds) 
26. Removal of 
Aquatic Growth 
(Federal Funds) 
27. St. Augustine 
Harbor, Fla. 
(Federal Funds) 
28. St. Johns 
River, Fla. 
Jacksonville 
to Lake Harney 
(Federal Funds) 
29. St. Lucie 
Inlet, Fla. 
(Federal Funds) 
(Contrib. Funds) 
20. 
See 
Section Total Cost to 
FY 80 FY 81 FY 82 FY83 Sept. 30, 1983 
28,848 
1,206,000 
1,968,713 
- 72,000 
898,921 
1,469,000 
1,818,044 
1,298 
1
I 
Funding 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint:
pprop. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
18,805 
1,958,000 
1,792,820 
41,000 
82,912 
447,000 
431,138 
110,084 
189,086 
15,624 
- 8,000 
16,029 
82,000 
281,654 
18,058,000 6,245,000 18,982,000 
9,025,007 7,868,824 10,738,178 
1865 385,906 11 
188 85,906 11 
80,000 
77,577 
1,387,000 
1,690,383 
40,000 
31,430 
875,000 
702,717 
828,000 
161,230 
23,600 
23,588 
366,700 
367,465 
161,400 
164,888 
125,000 
81,803 
1,825 
1,325 
21,400,59017 
21,397,889" 
26,081,6668 
25,938,89618 
508,700 
503,700 
315,26419 
815,264" 
1,988,686"0 
1,970,70840 
6,904,021" 
6,904,0211 
4,754,209" 
4,565,965" 
1,953,277 
1,953,277 
6,062,548 
5,890,143 
2,415,600 
2,415,600 
1,879,000 
612,663 
482,882" 
387,945" 
1,266,233 
1,266,233 
40,755,7783 
38,264,192" 
1,040,781 
1,040,781 
2,400,000 2,848,000 2,022,000 2,092,000 20,450,870 
2,312,108 2,569,449 1,981,456 2,192,273 20,245,592 
- - - - 1,476,434" 
- - - - 1,476,434" 
402,200 48,100 24,431 8,112 4,177,058 
1,014,901 48,122 24,431 8,128 4,177,058 
- - - - 1,171,2434� 
- - - - 1,171,2434� 
- 21,000 17,329 9,968 925,654"1 
- 20,949 17,871 9,977 925,654" 
1,400,000 8,110,000 700,000 900,000 7,863,602" 
1,088,350 8,897,422 864,477 758,819 7,318,059" 
68,700 66,400 82,262 32,094 2,294,305 
63,629 42,425 46,604 71,798 2,294,805 
- 1,200,000 507,000 136,000 2,458,000 
346,935 1,266,817 386,512 250,909 2,452,420 
9-31 
22,000 
20,690 
- 
256,900 
256,842 
253,700 
214,089 
37,887 
20,829 
- 20,000 
19,850 
261,300 
19,636 
50,000 
5,977 
-21,388 
622 
8,841,995 
212 
212

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 80 FY 81 FY 82 FY 83 Sept. 30, 1983 
30. St. Petersburg 
Harbor, Fla. 
(Federal Funds) 
81. San Juan 
Harbor, P. R. 
(Federal Funds) 
32. Tampa Harbor, 
Fla. (Main 
Project) 
(Federal Funds) 
(Contrib. Funds) 
36. Brevard County, 
Fla. 
(Federal Funds) 
(Contrib. Funds) 
37. Broward County. 
Fla. Beach Erosion 
Control and Hillsboro 
Inlet, Fla., 
Navigation Project 
(Federal Funds) 
(Contrib. Funds) 
38. Dade County, 
Fla. 
(Federal Funds) 
(Contrib. Funds) 
39. Duval County. 
Fla. 
(Federal Funds) 
(Contrib. Funds) 
40. El Tuque Beach 
Ponce, 
Puerto Rico 
(Federal Funds) 
(Contrib. Funds) 
41. Ft. Pierce, Fla. 
(Federal Funds) 
(Contrib. Funds) 
New Work: 
Approp. 
Cost 
Maint: 
Approp 
Cost 
New Work; 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Costp 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
1,875,000 
58,753 
2,208,000 
2,210,328 
11,298,100 
10,208,797 
837,100 
884,640 
150,000 
58,746 
425,000 
204,992 
12,833 
12,88833 
1,701,000 
19,204 
2,850,000 
2,857,832 
12,951 
12,951 
95,000 
1,416,793 
1,457,000 
24,189 
14,171,000 
13,377,011 
2,818,200 
35856,616 
84,224 
1,521,026 
184 
184 
- 65,000 
1,697,918 
550,000 
495,094
6
86 
-137,858 
- 137,406 
- 220,000 
1,129,302 
29,899,000 
31,755,233 
2,658,000 
5,113,608 
165,000 
187,912 
3,109 
3808 
308 
19,990 
13,347 
7,974 
7,974 
- 255,95727 
- 255,60827 
- 1,522,990" 
77 1,522,990"8 
- 13,774,968"9 
- 13,774,96829 
- 60,159 11,663,6253s0 
23,539 11,663,62530 
21,502,000 167,619,643' 
19,855,010 165,926,660' 
1,290,000 18,586,82232 
1,036,867 18,327,09532 
135,000 869,962 
116,418 842,666 
- 2,346,492 
1,321 2,256,521 
- 29,001 
- 29,001 
- 2,262,000 
576 2,255,241 
4,334 
614 
614 
2,720,000 9,800,000 8,195,000 510,000 
3,097,753 9,823,362 7,509,369 - 487,351 
2,201,600 7,661,454 5,050,000 230,000 
2,276,480 7,094,928 4,707,158 1,221,775 
-400,750 90,000 
1,275,084 107,293 
- - 300,000 
844,575 152,123 
41,000 
45,112 
200,000 
-1,331 
23,132 
- 7,000 360,000 
27,110 - 19,246 
773,000 - 
749,324 -3,469 
295 850 
295 850 
908,000 - 135,000 
732,098 23,780 
520,000 
40,364 
-333 
6,012 
100,000 
55,449 
29,159 
330,000 
378,703 
96,620 
6,253,100 
6,209,218 
26,884 
26,884 
1,758,8411 
1,758,8411 
32,643,956" 
30,913,306" 
22,424,085" 
22,410,04934 
6,068,900 
5,805,096 
4,142,400 
4,114,430 
841,500 
510,773 
520,000 
136,984 
1,175,448" 
69 1,146,4673b 
31,734 
31,734 
773,000 
761,890 
9-32 
TABLE 9-A

JACKSONVILLE, FLA. DISTRICT 
TABLE 9-A COST AND FINANCIAL STATEMENT 
See 
Section 
in Text Project Funding 
42. Manatee County, New Work: 
Fla. Approp. 
(Federal Funds) Cost 
43. Palm Beach New Work: 
County, Fla. from Approp. 
Martin County line Cost 
to Lake Worth Maint: 
Inlet to Broward Approp. 
County line Cost 
(Federal Funds) 
44. Pinellas County, New Work: 
Fla. Approp. 
(Federal Funds) Cost 
Maint: 
Approp. 
Cost 
(Contrib. Funds) New Work: 
Approp. 
Cost 
45. Punta Salinas New Work: 
Puerto Rico Approp. 
(Federal Funds) Cost 
Maint: 
Approp. 
Cost 
(Contrib. Funds) New Work: 
Approp. 
Cost 
48. Central and New Work: 
Southern Florida Approp. 
(Federal Funds) Cost 
Maint: 
Approp. 
Cost 
(Contrib. Funds) New Work: 
Approp. 
Cost 
49. Four River New Work: 
Basins, Fla. Approp. 
(Federal Funds) Cost 
(Contrib. Funds) New Work: 
Approp. 
Cost 
50. Portugues and New Work: 
Bucana Rivers, Approp. 
P. R. Cost 
(Federal Funds) 
FY 80 
25,000 
21,066 
112,621 
18,115 
13,115 
306,710 
1,761 
1,761 
FY 81 
67 
36,252 
32,235 
7 
FY 82 
-4,400
9 
16,950 
1,000,000 
54,950 
69 
69 
9nn nn 
Total Cost to 
FY 83 Sept. 30, 1983 
- 217,600 
15 217,600 
40,000 1,870,834 
44,904 1,870,834 
- 13,621 
- 13,621 
542,817 
-_ 
- , UV,VVV - 
290,803 19,221 - 505,218 
590,000 150,000 - 42,000 
61,596 250,376 420,520 85,892 
- 330,000 - 80,000 
- 111,891 212,663 14,690 
6,070,000 6,040,000 6,780,000 9,000,000 
5,891,260 5,721,682 4,859,723 6,865,717 
4,681,500 2,910,600 8,774,000 3,980,000 
4,872,350 8,353,047 8,218,709 8,953,714 
- 900,500 200,000 1,271,700 
1,222,880 992,533 622,179 756,016 
7,476,000 6,015,000 1,420,000 3,595,000 
7,395,814 6,037,006 1,332,526 1,076,456 
1,007,225 1,182,970 115,000 852,148 
1,295,292 1,148,446 191,461 389,206 
9,940,000 11,600,000 14,600,000 18,990,000 
9,978,955 10,694,708 183,535,452 19,476,203 
2,539,698 
2,064,748 
5,625 
5,625 
2,325,755 
1,929,780 
884,000 
854,705 
360,000 
338,744 
269,056,397" 
264,453,681" 
38,185,961 
37,458,630 
50,101,275 
49,064,817 
72,027,095" 
69,197,847" 
11,404,448 
11,828,587 
79,125,568 
77,550,680 
9-33 
_

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
1. Excludes work-in-kind. 
2. Includes $97,566 for previous project. 
8. Excludes $700,000 contributed by NASA in connection 
with construction of lock and $1,008,000 contributed funds for 
new work. 
4. Includes $118,000 for new work on previous project; excludes 
$15,568 expended for new work on existing project from 
contributed funds. 
5. Includes $2,202,126 expended from public work funds 
for new work. Includes costs of $723,916 for recreation 
facilities. 
6. Includes $142,827 expended for recreation facilities. 
7. Includes $10,128 cost for reconnaissance and detailed 
project report prepared under Sec. 107 modification to the project. 
Excludes $1,095 contributed funds for new work. 
8. Includes $515,479 for new work for previous projects: 
$8,472 for new work on Sunshine 8kyway Channel; and $9,707 
for new work for Cats Point Channel. Excludes $14,478 contributed 
funds for new work. 
9. Includes $450,749 for maintenance for previous project. 
10. Includes $94,776 for work for previous projects. 
11. Includes $218,222 for maintenance on previous projects 
and $3,179 operating and care under provisions of permanent 
indefinite appropriation. 
12. Includes $8,520,187 new work on previous project and 
$290,018 for new work expended from public works funds. 
18. Includes $543,899 maintenance on previous projects. 
14. Includes unused contributed funds of $64,186 returned 
to local interests. 
15. Project authorized December 2, 1964, by Chief of 
Engineers under Section 107 of 1960 R&H Act and by Section 
110 of the 1966 R&R Act. Cost of new work excludes $58,782 
contributed funds. 
16. Excludes $45,811 contributed funds for new work. 
17. Includes $16,222,275 for new work under previous project, 
$626,925 for recreational facilities (Code 710), and $27,574 
for reconnaissance and detailed project report prepared under 
Section 107 modification to the projet. 
18. Includes $7,581,150 for maintenance for previous pro 
jects. Excludes $1,000 for maintenance from contributed funds 
on previous projects, $67,558 which represents services 
rendered without reimbursement, and $118,744 for 
maintenance and operations of dams. 
19. Includes $8,912 for new work for previous projects. 
20. Includes $11,414 for operating and care under provisions 
for the permanent indefinite appropriation. 
21. Includes $80,000 new work from public works funds. 
Excludes $509,506 contributed funds. 
22. Includes $80,000 for maintenance from public works 
funds. 
23. Includes $11,588 expended for restudy, but excludes 
$21,960 expended for new work from contributed funds. 
24. Excludes $828,456 contributed funds. 
26. Includes $71,308 for new work on previous project. Excludes 
$187,500 contributed funds. 
26. Includes $26,689 for new work under previous project. 
27. Includes $82,689 under previous project. 
28. Includes $20,582 under previous project. 
29. Includes $747,684 for new work under previous project. 
Excludes $100,000 expended for new work from contributed 
funds. 
80. Includes $44,780 in maintenance under previous projeet. 
81. Includes $858,050 for new work under previous project. 
Excludes $270,466 for new work for Hillsborough River and 
$18,989 for new work from contributed funds. 
jee8r2. Includes $17,107 for maintenance under previous pro- 
3388In. cludes $2,299,526 for reimbursement costs to Bal 
Harbor. 
34. Excludes unused contributed funds of $17,969 returned 
to local interests. 
85. Excludes $800,088 in property for services furnished by 
local interests in lieu of cash contribution. 
86. Excludes $15,548 for property received without reimbursement 
and R&H Funds, expended on previous projects 
(see cost and financial statement for Okeechobee Waterway, 
Fla., project for these costs). Excludes $100,000 advanced by 
local interests toward federal costs. 
87. Includes costs of $70,671 for recreation facilities at 
Moss Bluff and $2,688,272 at Lake Tarpon. 
88. Excludes $288,000 contributed funds for new work. 
89. Includes $843,479 work-in-kind and $160,429 in costs for 
north jetty recreation facility. 
40. Baresford cutoff and completion of cutoffs and easing of 
bends in Putnam Lake and Volusia Counties in inactive status. 
Includes $29,566 for new work under previous project. 
41. Includes $25,88 under previous project. 
42. Excludes $42,788 contributed funds for new work. 
48. Excludes $118,744 for maintenance and operation of 
dams. 
9.34

JACKSONVILLE, FLA. DISTRICT 
AUTHORIZING LEGISLATION 
Aets Work Authorized Documents 
October 27, 1965 
August 26, 1987 
March 4, 1918 
June 20, 1989 
March 2, 1945 
October 28, 1962 
June 20, 1988 
July 14, 1960 
July 25, 1912 
March 8, 1925 
July 8, 1980 
August 26, 1987 
May 17, 1950 
July 14, 1960 
P.L. 675/77 
July 28, 1942 
June 14, 1880 
July 18, 1892 
March 2, 1907 
June 25, 1910 
March 8, 1925 
June 20, 1988 
AQUATIC PLANT CONTROL (See Seetion 1 of Text) 
Control and progressive eradication of obnoxious aquatic plants, and 
continued research to develop best method of control 
ARECIBO HARBOR, P.R. (See Section 2 of Test) 
Construction of breakwater 1,200 feet long and dredging channel 
25 feet deep and 400 feet wide with flare at entrance and widening 
at inner end to form a maneuvering area. 
ATLANTIC INTRACOASTAL WATERWAY BETWEEN 
NORFOLK, VA. AND THE ST. JOHNS RIVER, FLA. 
(See Section 3 of Text) 
Channel 7 x 100 feet 
Channel 12 feet deep and 90-150 feet wide with cut-offs 
CANAVERAL HARBOR, FLA. (See Section 4 of Text) 
Entrance channel jetties, a turning basin enclosed by a dike, and a 
barge canal with a lock 
Maintain improved channel, turning basin, enlarge barge channel and 
lock, relocate dike, provide channel and turning basin west of 
85-foot turning basin, construct and operate sand-transfer plant 
CHANNEL FROM NAPLES TO BIG MARCO PASS, FLA. 
(See Section 5 of Text) 
Interior channel 6 x 70 feet 
Channel 12 x 150 feet from the Gulf to Gordon Pass, thence 
10 x 100 feet to a point 400 feet south of U.S. Highway 41 Bridge, 
thence 10 x 70 feet to bridge and two turning basins 
CHARLOTTE HARBOR, FLA. (See Section 6 of Text) 
Channel 24 x 800 feet through Gulf through Boca Grande entrance 
Depth of 27 feet at entrance and width of 500 feet at the bend 
Channel 10 x 100 feet to Punta Gorda and a turning basin 
Depth of 30 feet at entrance and width of 700 feet at bend 
Depth of 82 feet in entrance channel 
CLEARWATER PASS, FLA. (See Section 7 of Text) 
Entrance channel 10 x 150 feet, inside channel 8 x 100 feet, and a 
turning basin 
CRO88-FLORIDA BARGE CANAL (See Section 8 of Text) 
Barge Canal 12 x 150 feet 
FERNANDINA HARBOR, FLA. (See Section 9 of Text) 
Entrance jetties 
Raising and extending jetties to provide 19-foot depth 
Improvement of inner harbor to obtain 20- to 24-foot depth and 400- to 
600-foot channel width 
Combining improvement of Fernandina Harbor and Cumberland Sound 
under the general heading of Fernandina Harbor 
Provided for a 26-foot channel 
Provided for the 28-foot channel and turning basin 
H. Doe. 251, 89th Cong., 
1st sees. 
Rivers & Harbors Committee 
Doe. 48, 75th Cong., 1st sees. 
H.Doc. 898, 62nd Cong., 
2d seas. 
H.Doc. 618, 75th Cong., 
8d seas. 
H.Doc. 867, 77th Cong., 
1st seas. 
S.Doc. 140, 87th Cong., 
2d sess. 
H.Doc. 596, 75th Cong., 
8d sees. 
H.Doc. 188, 86th Cong., 
1st sees. 
H.Doe. 699, 62nd Cong., 
2d seas. 
H.Doc. 118, 66th Cong. 
1st seas. 
Rivers and Harbors Committee 
Doe. 1, 70th Cong., 1st seas. 
Rivers and Harbors Committee 
Doc. 95, 74th Cong., 2d seas. 
H.Doc. 186, 81st Cong., 
1st ses. 
H.Doc. 298, 86th Cong., 
2d sess. 
H.Doc. 109, 79th Cong., 
1st seas. 
Annual Report 1879 
Annual Report 1891 & 1896 
H.Doc. 888, 59th Cong., 
1st seas. 
H.Doc. 227, 68th Cong., 
1st sees. 
H.Doc. 284, 77th Cong., 
1st sess. 
9-35 
TABLE 9-B

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 9-B (Contined) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
March 2, 1945 
May 17, 1950 
July 14, 1960 
Auth. by Chief of 
Engineers 
December 6, 1968, 
under See. 107 of 
1960 R&H Act. 
Def. Act of 
March 4, 1931 
War Dept. Approp. 
Act, March 4, 1933 
August 30, 1985 
March 2, 1945 
June 30, 1948 
May 17, 1950 
September 3, 1954 
May 10-16, 1957 
Auth. March 1, 1962 
By Senate 
and House 
Public Works 
Committee 
Auth. by Chief of 
Engineers 
March 1, 1968, 
under Sec. 107 of 
1960 R&H Act 
Provided for reducing the maximum width of turning basin from 
1,000 to 800 feet, for shifting channel line in this vicinity 50 feet 
northwesterly and for including in authorized project small area 
dredged by Rayonier, Inc. 
Provided for 32.foot channel and turning basin 
FORT MYERS BEACH, FLA. (See Section 10 of Text) 
12- x 150 foot channel in San Carlos Bay, thence 11 x 125 feet 
in Matanzas Pass to upper shrimp terminals 
Extension of 11- x 125-foot channel easterly about 2,000 feet to and 
including a turning basin adjacent to natural deep water in 
Matanzas Pass 
FORT PIERCE HARBOR, FLA. (See Section 11 of Text) 
Expenditure of $20,000 for dredging channel, maintenance by 
local interests 
Expenditure of up to $80,000 for dredging channel 
Maintaining channels, jetties, and revetments, and enlarging channels 
and turning basin to existing project dimensions 
INTRACOASTAL WATERWAY, CALOOSAHATCHEE RIVER 
TO ANCLOTE RIVER, FLA. (See Section 12 of Text) 
9- x 100-foot channel; deepening channel at Caseys Pass to 9 feet and 
construction of highway bridge at Venice 
Original route may be modified at no excess cost to U. S. 
Any route in Venice-Lemon Bay area may be used 
Use of alternate Route C-1 in Venice-Lemon Bay area 
Local interests to bear costs of Venice Avenue highway bridge and 
any other necessary crossing over Route C-1 
Sunshine Skyway Channel to be improved and maintained to 
9 x 100 feet 
H.Doc. 284, 87th Cong., 
1st sess. 
H.Doc. 662, 80th Cong., 2d sess. 
H.Doc. 183, 86th Cong., 
1st sess. 
Specified in Act 
Specified in Act 
H. Doc. 252, 72nd Cong., 
1st sess. and Rivers and 
Harbors Committee Doc. 21, 
74th Cong., 1st sess. 
H. Doc. 371, 76th Cong., 
1st sess. 
Specified in Act 
Specified in Act 
Specified in Act 
H.Doc. 109, 85th Cong., 
1st sess. 
6- x 80-foot channel in Boca Ciega Bay 
January 21, 1927 
July 8, 1980 
PARA June 26, 1934 
August 26, 1937 
March 2, 1945 
Do. 
INTRACOASTAL WATERWAY, JACKSONVILLE TO 
MIAMI, FLA. (See Section 13 of Text) 
Channel 8 x 75 feet from Jacksonville to Miami 
Channel width of 100 feet 
Operation and care of Palm Valley Bridge 
Turning basin at Jacksonville Beach 
Channel 12 x 125 feet 
Side channel and turning basin at Sebastian 
H.Doc. 586, 69th Cong., 
2d sess. 
S.Doc. 71, 71st Cong., 
2d sess. 
Specified in Act 
H.Doc. 180, 75th Cong., 
1st sess. 
H.Doc. 740, 79th Cong., 
2d sess. 
H.Doc. 336, 76th Cong., 
1st sess. 
9-36

TABLE 9-B (Contined) 
JACKSONVILLE, FLA. DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Atlerised Documents 
Do. Turning basin at Vero Beach 
July 8, 1958 
Chief of Engineers 
Report of July 22, 
1960, Mod. 12-foot 
channel 
March 2, 1907 
June 14, 1880 
June 3, 1896 
June 25, 1910 
June 5, 1920 
July 3, 1930 
August 80, 1985 
March 2, 1945 
Do. 
Do. 
October 27, 1965 
Auth. by Chief of 
Engineers 
December 2, 1964 
Under Sec. 107 of 
1960 R&H Act and 
Sec. 110 of 1966 
R&H Act. 
Auth. by Chief of 
Engineers 
April 20, 1976 
under Sec. 107 of 
1960 R&H Act, as 
amended 
August 30, 1935 
Maintenance of side channel at Daytona Beach 
Channel 10 x 125 feet from Ft. Pierce to Miami 
JACKSONVILLE HARBOR, FLA. IS.. Section 14 of Text) 
ST. JOHNS RIVER, FLA. OPPOSITE THE CITY OF 
JACKSONVILLE 
The 24-foot area from Hogan Creek to Florida East Coast 
Railroad bridge 
ST. JOHNS RIVER, FLA. 
Jetties at entrance (maintenance only) 
Extension of jetties, etc. (maintenance only) 
Main channel 30 by 800-600 feet; anchorage basin at Mayport; 
and training walls and revetments 
ST. JOHNS RIVER, FLA., JACKSONVILLE TO THE OCEAN 
Consolidation of above projects 
Widening bend at Dame Point to 900 feet 
Widening Drummond, Trout, and Six Mile (now Long Branch) Creeks 
Cut to 400 feet; and Terminal Channel 80 by 400 feet 
Maintenance of existing channel widths; widening Terminal Channel to 
590 feet; the 28-foot area between Laura St. and St. Elmo W. 
Acosta Bridge; channel along south side of Commodore Point; and 
basin at Naval Reserve Armory 
Main channel 84 feet deep via Terminal Channel 
Dame Point-Fulton Cutoff 34 by 500 feet 
Maintain existing entrance channel depths of 40 and 42 feet; deepen 
main ship channel to 88 feet to Mile 20 and widen channel near 
Mile 5 and near Mile 7 
JOHN'S PASS, FLA. (See SectIn 15 of Text) 
Channel 10 x 150 feet in the gulf, 8 x 100 feet inside pass, 
6 x 100 feet to IWW-2.6 miles long 
LONGBOAT PASS, FLA. (SeSee ectlims 16 Text) 
12- x 150-foot entrance channel from Gulf of Mexico to Longboat 
Bridge; 10- x 100-foot channel from Longboat Bride northeasterly 
to IWW; channel from north channel to Cortez Bridge 
MAYAGUEZ HARBOR P.R. (See See ee1I7 e Test) 
Approach channel 80 feet deep to and along deep water terminal 
H.Doc. 261, 76th Cong., 
1st sess. 
H.Doc. 222, 85th Cong., 
1st sess. 
H.Doc. 663, 59th Cong., 
1st sess. 
Annual Report 1879, p. 767 
H.Ex.Doc. 346, 58rd Cong., 
3d sess., and Annual Report 
1895, p. 1586 
H.Doc. 611, 61st Cong., 
2d sess. 
Specified in Act 
H.Doc. 483, 70th Cong. 
2d sess. 
S.Comm. print, 74th Cong., 
1st sess. 
H.Doc. 822, 77th Cong., 
1st sess. 
8.Doc. 230, 78th Cong. 
2d sess. 
S.Doc. 179, 79th Cong., 
2d sess. 
H.Doc. 214, 89th Cong., 
1st sess. 
H.Doc. 215, 72nd Cong. 
1st sess. & River and 
Harbor Committee Doc. 1, 
78rd Cong., 1st sess. 
9-87

TABLE 9-B (Contined) 
REPORT OF THE CHIEF OF ENGINEERS, U.8S. ARMY 1983 
AUTHORIZING LEGISLATION 
Acts Work Authorised Documents 
July 8, 1980 
PWA Program 
September 6, 1988 
June 18, 1902 
March 2, 1907 
March 4, 1918 
March 8, 1925 
July 8, 1980 
August 80, 1985 
August 26, 1987 
March 2, 1945 
March 2, 1945 
July 14, 1960 
August 18, 1968 
Auth. by Chief of 
Engineers 
April 20, 1964 
under See. 107 of 
1960 R&H Act 
PARA June 26, 1934 
August 26, 1987 
March 2, 1945 
Do. 
March 2, 1945 
Do. 
MIAMI HARBOR, FLA. IS.. Section 18 of Text) 
MIAMI RIVER 
The 15-foot channel in Miami River, 150 feet wide at the mouth 
The channel at the Dinner KIey Airport 
An 18-foot channel in a landcut across the peninsula and construction 
of the north jetty 
Construction of the south jetty and increase of channel width 
to 100 feet 
Modification of local cooperation requirements imposed by the Act of 
July 25, 1912 
A channel 25 feet deep with present widths from the ocean to 
Biseayne Bay, thence 200 feet wide across the bay to but not 
including the municipal turning basin, and extension of both jetties 
A channel width of 800 feet across the bay and enlarging the 
municipal turning basin, with expenditures thereon limited to 
$200,0 
A depth of 80 feet from the ocean to and in the turning basin, with 
the existing authorized project widths, including the 800-foot width 
in the channel across the bay 
Extending the turning basin 200 feet to the southward 
The Virginia Key improvement 
For incorporation of the project for Miami River in that for Miami 
Harbor, the widening at the mouth of Miami River to existing project 
widths; the channels from the mouth of Miami River to the turning 
basin and to Government Cut; and the channel from Miami 
River to the harbor of refuge, provided that local interest contribute 
one-third of the cost 
Deletion of Virginia Key development and the Dinner Key approach 
channel, widening the existing ship channel by easing the ocean 
bend and increasming the width of the 800-foot-wide section to 400 
feet, enlarging the existing turning basin 800 feet along both the 
south and northeasterly sides, and dredging a turning basin along 
the north side of Fisher Island about 89 acres in extent and 30 feet 
in depth 
Enlarging existing entrance channel to 38 x 500 feet, deepening 
existing 400-foot-wide channel across Biscayne Bay to 36 feet; 
deepenming existing turning basins at Biscayne Blvd. terminal and 
Fisher Island to 36 feet 
NEW PASS, SARASOTA, FLA. (See Section 19 of Text) 
10- x 150-foot entrance channel; 8- x 100-foot inner channels; and 8-footdeep 
turning basins at Payne Terminal and City Pier 
OKEECHOBEE WATERWAY, FLA. (See Section 20 of Text) 
Operation and care of locks and dams provided for with funds 
from R&H appropriations 
New lock and weir structure in St. Lucie Canal 
Deepening to 8 feet from Ft. Myers to Jacksonville-Miami waterway 
near Stuart via channel across lake from Clewiston 
Channel to yacht basin at Ft. Myers and a basin at Stuart 
Deepening to 8 feet from Ft. Myers to Jacksonville-Miami waterway 
near Stuart via channel across lake from Clewiston 
Channel to yacht basin at Ft. Myers and a basin at Stuart 
Specified in Act 
S.Doc. 95, 72d Cong., 1st sess. 
and specified in Act 
H.Doc. 622, 56th Cong., 
1st seas. (Annual Report 
1900, p. 1987) 
Specified in Act 
Specified in Act 
H.Doc. 516, 67th Cong., 
4th sess. 
Rivers and Harbors Committee 
Doc. 15, 71st Cong., 2d sess. 
Sen. Comm. Print. 
73d Cong., 2d sess. 
Rivers and Harbors Committee 
Doc. 86, 74th Cong., 2d sess. 
S.Doc. 251, 79th Cong., 2d sess. 
H.Doc. 91, 79th Cong., 
1st sess. 
S.Doc. 71, 85th Cong., 
2d sess. 
S.Doc. 98, 90th Cong., 
2d sess. 
Specified in Act 
Rivers and Harbors Committee 
Doc. 28, 75th Cong., 1st sess. 
H.Doc. 696, 76th Cong., 
3d seas. 
H.Doc. 736, 79th Cong., 
2d sess. 
H.Doc. 696, 76th Cong., 
3d sess. 
H.Doc. 786, 79th Cong., 
2d sess. 
9-38

TABLE 9-B (Contined) 
JACKSONVILLE, FLA. DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Auth. by Chief of 
Engineers 
November 5, 1968, 
under Sec. 107 of 
1960 R&H Act 
September 19, 1890 
March 2, 1907 
June 25, 1910 
July 25, 1912 
July 27, 1916 
PARA June 26, 1934 
March 13, 1934 
December 10, 1934 
August 30, 1935 
March 2, 1945 
May 17, 1950 
July 14, 1960 
October 27, 1965 
March 3, 1925 
August 30, 1935 
March 2, 1945 
H.R. September 
23, 1976 
S.R. October 1, 
1976 
Enlarge existing 8- x 90-foot section of Okeechobee Waterway for 
about 5 miles upstream from Ft. Myers to 10 x 100 feet 
OKLAWAHA RIVER, FLA. (See Section 21 of Text) 
Clearing obstructions for channel 4 feet deep from mouth to Leesburg 
Channel 6 feet deep from mouth to head of Silver Springs Run 
Maintenance of levels in the lakes at head of river 
Acceptance of certain artificial waterways in lieu of portions 
of natural river bed 
Operation and care of lock and dam provided for with funds from 
appropriations for rivers and harbors 
PALM BEACH HARBOR, FLA. (See Section 22 of Text) 
Maintenance of improvement previously constructed by local interests 
Deepening the channels and turning basin, as constructed by local 
interests, to 20 feet 
Authorized the work previously approved by Public Works 
Administration, and widening the channels to existing project 
dimensions, enlarging the 700-foot-square turning basin eastward 
removing the obstructive point on south side of the inlet, revetting 
the banks of the inlet, and restoring existing jetties 
Deepening the chaIinels and turning basin to 25 feet 
Extend' the turning basin 550 feet southward over a 900-foot width, 
a flare to the east; provided that local interests may be reimbursed 
not to exceed $305,000 for work done by them on this 
modification subsequent to July 1, 1949 
An entrance channel 35 feet deep, 400 feet wide, and 0.8 mile long, 
merging with an inner channel 33 feet deep, 300 feet wide and 0.3 
mile long, thence flaring into a turning basin, 1,400 feet north-south 
by a minimum of 1,200 feet east-west 
PONCE DE LEON INLET, FLA. (See Section 23 of Text) 
Widening and deepening channels; jetties on north and south side 
of inlet; a weir in the north jetty and an impoundment basin inside 
the weir 
PONCE HARBOR, P.R. (See Section 24 of Text) 
Dredging 3 continuous areas, aggregating 153 acres, to depths of 30, 
18, and 9 feet, and construction of a seawall, costs to be shared by 
U.S. and local interests 
Modified conditions of local cooperation to provide that U.S. undertake 
all dredging at Federal expense and return local funds previously 
contributed for dredging, all other portions of the improvement 
hereafter to be at the expense of local interests 
Eliminate previously authorized 9-foot dredging area, and provided for 
dredging 30-foot-depth area and 18 acres off the municipal pier and 
for construction of the breakwater off Punta Carenero 
Eliminate previously authorized 18-foot and a portion of the 30-foot 
project outside the proposed 36-foot and a portion of the adjacent 
to the municipal bulkhead. Channel 36 x 600 feet from Caribbean 
Sea to harbor; channel 36 x 400 feet into harbor; and a 36-foot 
turning basin. 
Annual Report 1889, p. 1360 
H.Doc. 782, 59th Cong., 
1st sess. 
Specified in Acts 
Specified in Act 
Specified in Act 
H.Doc. 185, 73d Cong., 
2d sess. 
Recommended by Chief of 
Engineers to Public 
Works Administration 
October 17, 1934 
H.Doc. 185. 73d Cong., 
2d sess. and Rivers and 
Harbors Committee Doc. 42, 
74th Cong., 1st sess. 
H.Doc. 530, 78th Cong., 
2d sess. 
H.Doc. 704, 80th Cong., 
2d sess. 
H.Doc. 283, 86th Cong., 
1st sess. (contains latest 
published map) 
H.Doc. 74, 89th Cong., 
1st sess. 
H.Doc. 532, 67th Cong., 
4th sess. 
Rivers and Harbors Committee 
Doc. 18, 72d Cong., 1st sess. 
H.Doc. 745, 79th Cong., 
2d sess. 
H.Doc. 532, 94th Cong., 
2d sess. 
9-39

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 9-B (Contined) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
July 3, 1930 
August 30, 1935 
June 20, 1938 
July 24, 1946 
July 8, 1958 
H.R. May 9, 1974 
S.R. May 31, 1974 
March 3, 1899 
June 18, 1902 
March 8, 1905 
June 20, 1938 
May 17, 1950 
March 8, 1899 
March 2, 1919 
June 14, 1880 
June 25, 1910 
July 3, 1930 
March 2, 1945 
March 2, 1945 
July 24, 1946 
March 2, 1945 
'4ovember 7, 1966 
PORT EVERGLADES HARBOR, FLA. (See Section 25 of Text) 
Maintenance of harbor constructed by local interests 
Enlarge entrance channel and complete turning basin to 
1,200 feet square 
Widen turning basin 350 feet on north side 
Widen turning basin 200 feet on north side, 500 feet on south side and 
enlarge flare at entrance channel 
Deepen and widen entrance channel on a new alinement and increase 
turning basin in size and depth 
Deepen and widen entrance channel, enlarge turning basin, widen 
Pier 7 channel, maintenance of Berth 18 channel, and planning for a 
south jetty fishing walkway with construction contingent upon 
need as developed by detailed postauthorization studies 
REMOVAL OF AQUATIC GROWTH FROM NAVIGABLE 
WATERS IN THE STATE OF FLORIDA (See Section 26 of Text) 
Construction and operation of a suitable vessel and use of log booms 
for removal of water hyacinths in the navigable waters of the State 
Extermination and removal of water hyacinths by any mechanical, 
chemical, or other means 
Prohibits use of any chemical process injurious to cattle 
ST. AUGUSTINE HARBOR, FLA. (See Section 27 of Text) 
Channel 27 x 200 feet protected by a groin 
Channel 16 x 200 feet across bar, and thence 12 feet deep to 
Intracoastal Waterway; jetty on south side of inlet; future landward 
extension of groin and jetty; and channel 10 x 100 feet in San 
Sebastian River 
ST. JOHNS RIVER, FLA., JACKSONVILLE TO 
LAKE HARNEY (See Section 28 of Text) 
A channel 13 feet deep and 200 feet wide from Jacksonville 
to Palatka 
The improvement of Deep Creek 
Two jetties at Volusia Bar (Maintenance only; new work completed 
under previous project.) 
A channel 100 feet wide, 8 feet deep from Palatka to Sanford with a 
side channel to Enterprise, and thence 5 feet deep to Lake Harney 
Cutoffs at Butcher Bend, Shake Creek, and Starks Landing, and 
easing bends at other points 
A channel 10 feet deep and 100 feet wide from Palatka to Sanford, 
with a side channel to Enterprise and with cutoffs and easing of 
bends 
Combining the two projects above into a single project for St. Johns 
River,Fla., Jacksonville to Lake Harney, and for a cutoff 5 feet 
deep and 75 feet wide between Lake Monroe and the vicinity of Osteen 
Bridge (Woodruff Creek Cutoff) 
A channel 12 feet deep and 100 feet wide from Palatka to Sanford, 
and in the branch to Enterprise 
ST. LUCIE INLET, FLA. (See Section 29 of Text) 
Channel 10 x 200 feet 
Modification to maintain existing channel 6 x 100 feet 
H.Doc. 357, 71st Cong., 
2d sess. 
Rivers and Harbors Committee 
Doc. 25, 74th Cong., 1st sess. 
H.Doc. 545, 75th Cong., 
3d sess. 
H.Doc. 768, 78th Cong., 
2d sess. 
H.Doc. 346, 85th Cong., 
2d sess. 
H.Doc. 144, 93d. Cong., 
1st sess. 
Annual Report 1899 
Specified in Act 
Specified in Act 
H.Doc. 555, 75th Cong., 
3d sess. 
H.Doc. 133, 81st Cong., 
1st sess. 
H.Doc. 528, 55th Cong., 2d sess. 
and Annual Report for 
1989, p. 1343 
H.Doc. 699, 68rd Cong., 2d sess. 
Annual Report for 1879, 
pp. 795-798 
H.Doc. 1111, 60th Cong., 
2d sess. 
H.Doc. 691, 69th Cong., 
2d sess. 
H.Doc. 608, 76th Cong., 
3d sess. 
H.Doc. 445, 78th Cong., 
2d sess. 
S.Doc. 208, 79th Cong., 
2d sess. 
H.Doc. 891, 77th Cong., 
1st sess. 
H.Doc. 508, 89th Cong., 
2d seas. 
9-40

TABLE 9-B (Contined) 
JACKSONVILLE, FLA. DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
H.R. May 9, 1974 
8.R. May 81, 1974 
Def. Act of 
March 4, 1929 
July 3, 1930 
August 26, 1937 
May 17, 1950 
August 8, 1917 
September 22, 1922 
July 3, 1930 
August 80, 1935 
August 26, 1937 
October 17, 1940 
March 2, 1945 
July 3, 1958 
August 4, 1976 
March 8, 1899 
March 3, 1905 
Extending north jetty and modifying existing jetty to provide a sand 
bypass weir section; excavation of sand impoundment basin; 
construction of south jetty with walkway for recreational fishing; 
channel 10 x 500 feet thru bar cut, tapering to 150 feet thru the inlet, 
and 100 feet and 7 feet deep to the Intracoastal Waterway; and 
transfer of 380,000 cubic yards of material to the south beach during 
each two-year maintenance period 
ST. PETERSBURG HARBOR, FLA. (See Section 30 of Text) 
Dredging Point Pinellas Channel 16 x 200 feet 
Channel 19 x 250 feet westward from Tampa Bay into and including 
the basin at the port of St. Petersburg 
Channel 20 x 200 feet leading southward from previous authorization 
to Tampa Bay 
Entrance channel 24 x 300 feet from Tampa Bay to and including a 
12-foot basin in Bayboro Harbor; Maritime Service channel 15 x 100 
x 800 feet; channel 12 x 75 x 300 feet in mouth of Salt Creek 
SAN JUAN HARBOR, P.R. (See Section 31 of Text) 
Anchorage (inner harbor) area of 206 acres and San Antonio Channel 
to 30-foot depth 
Substitution of a 68-acre area 80 feet deep along southeasterly side of 
anchorage area, for one 25 acres in extent and of same depth extending 
easterly from eastern end of the San Antonio project channel 
Modified condition of local cooperation 
Entrance channel across outer bar 88 feet deep and 800 feet wide, and 
thence across bay to anchorage area (Anegado Reach Channel) 80 
feet deep and 700 feet wide and increasing anchorage area to 289 
acres to 30-foot depth 
Widening Anegado Reach Channel and increasing anchorage area to 
329 acres 
Removal to 8-foot depth of Anegado, Largo, and Capitanejo Shoals, 
and dredging to 30-foot depth the entrance channel and turning 
basin to the Graving Dock 
Maintenance of the 30-foot depth entrance channel and turning basin 
to the Army Terminal 
Deepening portions of entrance and approach channels and basins to 
Army Terminal and San Antonio Pier areas to 85-45 feet; new 
32-foot depth Puerto Nuevo Channel; new 36-foot depth anchorage 
A bar channel 48 by 800 feet, shifting the centerline 350 feet west; 
deepening Anegado Channel in steps from 46 to 40 feet while 
reducing width to 800 feet; deepemng Army Terminal Channel and 
turning basin to 40 feet while widening the channel to 450 feet; 
deepening Puerto Nuevo Channel to 40 feet and widening itto 400 
feet; deepening Graving Dock Channel to 40 feet at existing 
400-foot width; deepening San Antonio Channel to 88 feet at 
varying widths, minimum of 500 feet; deepening cruise ship basin 
to 36 feet at an irregular width; maintaining Sabana Approach 
Channel at 30 by 250 feet; provide a 88-foot depth in Anchorage 
Area "E" with irregular width; six mooring dolphins for vessels using 
the area. 
TAMPA HARBOR, FLA. (See Section 32 of Text) 
TAMPA BAY 
For a channel 27 feet deep from the Gulf of Mexico to Port Tampa, 500 
feet wide across the bar and 300 feet wide in the bay 
For a channel depth of 26 feet with sufficient width from the Gulf of 
Mexico to Port Tampa 
H.Doc. 294, 93rd Cong., 
1st sess. 
Specified in Act 
8.Doc. 229, 70th Cong., 
2d sess. 
R.&H. Committee 
Doc. 71, 74th Cong., 
2d sess. 
H.Doc. 70, 81st Cong., 
1st sess. 
H.Doc. 865, 63d Cong., 
2d sess. 
Specified in Act 
H.Doc. 45, 71st Cong., 
2d seass. 
R&H Comm. Doe. 88, 
74th Cong., 1st sess. 
R&H Comm. Doe. 42, 
75th Cong., 1st sess. 
H.Doc. 864, 76th Cong., 
1st seas. 
Specified in Act 
H.D)oc. 88, 85th Cong., 
1st seas. 
H.Doc. 574, 94th Cong., 
2d seas. 
H.Doc. 52, 55th Cong., 
3d seas. (Also prminted in 
Annual Report 1899, p. 1640) 
Channel dimensions specified 
in Act 
Specified in Act 
9-41

TABLE 9-B IContined) 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
June 25, 1910 
August 8, 1917 
March 8, 1899 
September 22, 1922 
July 3, 1980 
August 80, 1985 
June 20, 1938 
Do. 
March 2, 1945 
Do. 
Do. 
May 17, 1950 
September 3, 1954 
October 23, 1962 
December 81, 1970 
Do. 
Do. 
TAMPA AND HILLSBOROUGH BAYS 
For a depth of 24 feet in Hillsborough Bay 
For a 27-foot depth from Gulf of Mexico up to and in the several 
channels of Hillaborough Bay, the widths to be 500 feet on the bar, 
300 feet in Tampa Bay, Ybor, and Garrison Channels, and 200 feet 
in Hillsborough Bay, Sparkman, and Seddon Channels, with turning 
basins at the mouth of Hllsborough and at Ybor Estuary 
HILLSBOROUGH RIVER 
For a 12-foot channel to within 100 feet of the Lafayette St. highway 
bridge (maintenance only; new work completed under a previous 
project under the title Improving Hillsborough Bay, Fla.) 
TAMPA HARBOR 
Consolidation of the above projects to form a single project for 
Tampa Harbor 
Increasing the depth of Egmont Channel to 29 feet and the width of 
Sparkman Channel to 800 feet 
For a depth of 82 feet and a width of 600 feet on Egmont Bar, a depth 
of 80 feet and a width of 400 feet in Mullet Key Cut, and a depth of 
30 feet and a width of 800 feet in all other project channels in Tampa 
Harbor (except in Hillsborough River and in the channel leading 
to Alafia River); and for a turning basin 2,000 feet long and 500 feet 
in maximum width at the entrance to the Port Tampa terminals 
For widening the bend between Sparkman Channel and Cut D of 
Hillsborough Bay Channel by 250 feet; widening Ybor Channel to 
400 feet and extending the turning basin at the west end of Garrison 
Channel (mouth of Hillsborough River) easterly for 300 feet 
For construction of a breakwater at Peter O. Knight Field, Davis 
Islands, its maintenance to be assumed by local interest 
For widening Sparkman Channel to 400 feet and Ybor Channel to 
500 feet; widening the bend between Sparkman and Garrison Channels 
an additional 250 feet to extend the turning basin westerly; 
and widening the bend between Seddon and Garrison Channels by 
150 feet (in lheu of 300 feet previously authorized) to extend the turning 
basin easterly 
For a channel 9 feet deep and 100 feet wide in the Hillsborough River 
for about 2.4 miles above the upper end of the existing 12-foot 
channel, and for the removal of obstructions thence to the Florida 
Avenue Bridge 
For a channel 25 feet deep and 150 feet wide from the Hillsborough 
Bay channel to and including a turning basin in the Alafla River 
(Revoked by Act of May 17, 1950) 
For deepening Egmont Channel to 86 feet; enlarging Mullet Key Cut, 
Tampa Bay Channel, Hillsborou h Bay Channel, Port Tampa Channel 
and Port Tampa turning basin to present project dimensions; 
deepening Sparkman Channel and Ybor turning basin to 34 feet; a 
channel 80 feet deep and 200 feet wide from Hillsborough Bay 
Channel to and including a turning basin in Alafia River, 700 feet 
wide and 1,200 feet long (in lieu of the improvement previously 
authorized); and substantial widening at entrance, bends, and turns 
Extended removal of obstructions in Hillsborough River to City Water 
Works Dam. Maintenance of cleared channel to be assumed by local 
interests 
Channel and turning basin at Port Sutton 30 feet deep, Ybor Channel 
34 x 400 feet 
For federal maintenance of Port Sutton Channel, 280 feet wide and an 
irregularly shaped turning basin both to a depth of 34 feet 
Enlarge entrance channel across Egmont Bar to 46 x 700 feet from the 
Gulf to Mullet Key 
Enlarge Mullet Key Cut Channel to 44 x 600 feet 
H.Doc. 634, 61st Cong., 
2d sess. 
H.Doc. 634, 61st Cong., 
1st sess. 
H.Doc. 545, 55th Cong., 
2d sess. and Annual Report 
1898, pp. 1857-1360 
Specified in Act 
H.Doc. 100, 70th Cong., 
1st sess. 
S.Doc. 22, 72d Cong., 
1st sess. 
S.Doc. 164, 75th Cong., 
3d sess. 
Sen. Comm. Print. 
76th Cong., 1st sess. 
S.Doc. 183, 78th Cong., 
2d sess. 
H.Doc. 119, 77th Cong., 
1st sess. 
S.Doc. 16, 77th Cong., 
1st sess. 
H.Doc. 258, 81st Cong., 
1st sess. 
H.Doc. 567, 81st Cong., 
2d sess. 
H.Doc. 529, 87th Cong., 
2d sess. 
H.Doc. 150, 91st Cong., 
1st sess. 
H.Doc. 401, 91st Cong., 
2d sess. 
Do. 
9-42

TABLE 9-B (Contined) 
JACKSONVILLE, FLA. DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authborisod Documents 
Do.' 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
BEACH EROSION 
CONTROL PROJECTS 
August 18, 1968 
October 27, 1965 
August 18, 1968 
October 27, 1965 
December 19, 1979 
By Chief of 
Engineers under 
sction 108 of the 
1962 River and 
Harbor Act 
October 27, 1965 
BREVARD COUNTY, FLA. (See Section 86 of Text) 
Federal participation in cost of shore protection project 
BROWARD COUNTY, FLA., BEACH EROSION CONTROL AND 
HILLSBORO INLET, FLA., NAVIGATION PROJECT (See Section 
37 of Text) 
Improvement for beach erosion control in Broward County, Fla. and a 
combined beach erosion and navigation improvement to 
Hilsborough Inlet and the shore south thereof to Port Everglades 
DADE COUNTY, FLA. (See Section 38 of Text) 
Federal participation in cost of shore protection and hurricane-flood 
control project 
DUVAL COUNTY, FLA. (See Section 39 of Text) 
Federal participation in cost of shore protection project 
EL TUQUE BEACH, PONCE, P. R. (See Section 40 of Text) 
Placement of about 60,000 cubic yards of fill material along eroded 
shoreline. Build a shore connected rubble breakwater and offshore 
breakwater to stabilize the fill material 
FORT PIERCE, FLA. (See Section 41 of Text) 
Federal participation in cost of local shore protection projects 
H.Doe. 852, 90th Cong., 
2d sess. 
H.Doc. 91, 89th Cong., 
1st sess. 
H.Doc. 3388950, th Cong., 
2d sess. 
H.Doc. 278, 89th Cong., 
1st seas. 
H.Doc. 84, 89th Cong., 
1st sess. 
9-43 
Enlarge Tampa Bay Channel to 44 x 500 feet from Mullet Key Cut 
through Tampa Bay to the junction of Hillsborough Bay and Port 
Tampa Channels 
Enlarge Hillsborough Bay Channel to 44 x 500 feet from the junction 
with Tampa Bay and Port Tampa Channels to the junction with 
Port Sutton entrance channel, and thence deepening to a depth of 
42 feet at the existing width of 400 feet to the junction with 
Seddon and Sparkman Channels 
Enlarge Port Sutton entrance channel to 44 x 400 feet 
Enlarge Port Sutton turning basin to a depth of 44 feet and a turning 
diameter of 1,200 feet 
Deepening Sparkman Channel to 42 x 400 feet 
Deepening Ybor Channel to 40 x 800 feet 
Enlarge turning basin at the entrance to Ybor Channel to a depth of 
42 feet and an additional width of 200 feet on the southwest edge of 
the present basin 
Deepening Port Tampa Channel to 42 feet at its existing width from 
the junction with Hillsborough and Tampa Bay Channels to the 
turning basin 
Deepening the Port Tampa turning basin to 42 feet over its existing 
length of 2,000 feet and width of 900 feet 
An entrance channel in East Bay 44 x 400 feet and 500 feet north from 
the Port Sutton turning basin for a distance of about 2,000 feet 
A turning basin in East Bay at a depth of 44 feet and with a turning 
diameter of 1,200 feet 
An approach channel in East Bay 44 x 800 feet north from the East 
Bay turning basin for a distance of about 2,500 feet 
Maintenance of Port Sutton Terminal channel to 44 x 200 feet for a 
distance of 4,000 feet 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do.

TABLE 9-B (Contined) 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
S.R. May 81, 1974 
H.R. November 20, 
1975 
October 28, 1962 
November 7, 1966 
September 4, 1979 
By Chief of 
Engineers under 
Section 103 of the 
1962 River and 
Harbor Act 
FLOOD CONTROL 
PROJECTS 
June 30, 1948 
September 8, 1954 
July 14, 1960 
October 23, 1962 
Do. 
Do. 
Do. 
Do. 
October 27, 1965 
Do. 
August 13, 1968 
Do. 
Approved 
December 17, 1970 
under the 
provisions of 
Section 201 of the 
Flood Control Act 
of 1965 
MANATEE COUNTY, FLA. (8ee Sectione 42 of Text) 
Federal participation in cost of shore protection project 
PALM BEACH COUNTY, FLA., FROM MARTIN COUNTY LINE 
TO LAKE WORTH INLET AND FROM SOUTH LAKE WORTH 
INLET TO BROWARD COUNTY LINE (See Section 43 of Text) 
Federal participation in cost of local shore protection project and 
sand-transfer plant 
PINELLAS COUNTY, FLA. (See Secteion 44 of Text) 
Federal participation in cost of shore protection project 
PUNTA SALINAS RECREATION AREA, P.R. (See Secteion 45 of 
Text) 
Shore restoration of the east and west shores of the Punts Salinas 
Recreation Area 
CENTRAL AND SOUTHERN FLORIDA (See Section 48 of Text) 
First phase of comprehensive plan for flood control and other purposes 
Modification and expansion of authorization to include entire 
comprehensive plan of improvement 
Canals, levees, and water-control and drainage structures in the 
Nicodemus Slough area, Glades County 
Flood protection on Boggy Creek, near Orlando 
Flood protection in the Cutler Drain area, near Miami 
Flood control and drainage works for South Dade County 
Project for Shingle Creek between Clear Lake and Lake Tohopekaliga 
for flood control and major drainage, including development of 
Reedy Creek Swamp 
Improvement of easterly section of West Palm Beach Canal for flood 
control and major drainage 
Primary works for flood control and major drainage in southwest 
Dade County 
Primary works for flood control and major drainage in Hendry County 
Gravity drainage in Martin County and distribution of available water 
supplies to portions of Martin and St. Lucie Counties 
Improvement of supply, distribution, and conservation of water 
resources in Central and Southern Florida, including Lake 
Okeechobee agricultural area, Everglades National Park and other 
related areas. 
Navigation improvements suitable for recreational craft 
S.Doc. 93, 37th Cong., 
1st sess. 
H.Doc. 164, 87th Cong., 
1st sess. 
H.Doc. 519, 89th Cong., 
2d sess. 
H.Doc. 643, 80th Cong., 
2d sess. (Contains latest 
published map) 
H.Doc. 643, 80th Cong., 
2d sess. 
S.Doc. 53, 86th Cong. 
1st sess. 
S.Doc. 125, 87th Cong., 
2d sess. 
S.Doc. 123, 87th Cong., 
2d sess. 
S.Doc. 138, 87th Cong., 
2d sess. 
S.Doc. 139, 87th Cong., 
2d sess. 
S.Doc. 146, 87th Cong., 
2d sess. 
S.Doc. 20, 89th Cong., 
1st sess. 
H.Doc. 102, 88th Cong., 
1st sess. 
S.Doc. 101, 90th Cong., 
2d sess. 
H.Doc. 369, 90th Cong., 
2d sess. 
H.Doc. 394, 91st Cong., 
2d sess. 
9-44

TABLE 9-B (Contin 
Acts 
October 23, 1962 
December 31, 1970 
JACKSONVILLE, FLA. DISTRICT 
ed) AUTHORIZING LEGISLATION 
Work Authorized 
FOUR RIVER BASINS, FLA. (See Section 49 of Text) 
Control of floods and improvement of drainage, and for water 
conservation through construction of necessary canals, levees, 
reservoirs, and control structures 
PORTUGUES AND BUCANA RIVERS, P.R. (See Section 50 of 
Text) 
LAGO de CERRILLOS, P.R. 
Multiple purpose dam and lake for flood control, water supply, 
and recreation 
LAGO de PORTUGUES, P.R. 
Multiple purpose dam and lake for flood control, water supply 
and recreation 
PONCE, P.R. 
Diversion and enlargement of existing channels through Ponce for 
flood control 
Documents 
H.Doc. 585, 87th Cong., 
2d sess. 
H.Doc. 422, 91st Cong., 
2d sess. 
9-45

TABLE 9-C 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1988 
CANAVERAL HARBOR, FLA. PROJECT 
DATA RELATIVE TO LOCK 
(See Section 8 of Text) 
Distance to nearest town 9.9 miles via 12-foot barge canal and 
Intracoastal Waterway 
Name of nearest town Cocoa, Fla. 
Distance from Intracoastal Waterway 6.5 miles 
Lock Dimensions 90' wide; 600' long' 
Lift Varies with tide 
Depth of sills (mlw, ocean) 14 feet 
Character of foundation Piles in sand 
Year completed and opened to navigation 1965 
Contract cost $2,966,589 
'56 x 400 feet authorized. At request of NASA lock was increased width. Operation and maintenance of lock is a Federal 
constructed 90 feet wide with NASA bearing additional cost responsibility. 
($700,000). Length increased to 600 feet to be compatible with 
TABLE 9-D CROSS-FLORIDA BARGE CANAL PROJECT 
Heary H. Buekmas 
Leek 
LOCKS AND DAMS 
(See Section 7 of Text) 
RN. 
Eureka Leek Bert Desh 
sad Dm Leek 
Nearest town 
(miles) 
Miles from Atlantic 
Intracoastal 
Waterway 
Lock dimensions (ft.)' 
Normal lift (ft.) 
Depth over sills 
at normal pool levels: 
Upper (ft.) 
Lower (ft.) 
Character of 
foundation 
Kind of dam 
Type coast. 
Percent complete 
Estimated contract 
cost 
'Clear width and greatest available length. 
sPool level varies with natural ground water profile from 
minimum elevation of 40 feet to maximum elevation of 55 feet. 
*With concrete spillway and movable gates. 
9-46 
Dunnelaen 
Leek 
Inglis Loek 
and Dam 
Palatka, 
11.2 
90.4 
84 x 600 
20 
14 
15 
Piles in 
sand 
Movable 
Earths 
100 
$6,094,000 
Sparr, 
15.8 
111.4 
84 x 600 
20 
17 
14 
Piles in 
sand 
Movable 
Earths 
100 
$7,975,000 
Ocala, 
8.9 
127.7 
84 x 600 
0-15s' 
16-81s' 
16 
Piles in 
sand 
None 
0
$7,480,000 
Dunnellon, 
2.5 
156.5 
84 x 600 
12-27' 
16-812 
18 
Rock 
None 
0
$9,500,000 
Inglis, 
8.2 
168.6 
84 x 600 
28 
18 
15 
Rock 
Movable 
Earth3 
100 
$7,800,000

JACKSONVILLE, FLA. DISTRICT 
TABLE 9-E CROSS-FLORIDA BARGE CANAL 
OPERATIONS AND RESULTS DURING FISCAL YEAR 
(See Section 8 of Text) 
Work Performed Cost 
New Work: 
Engineering and Design $ 20,685 
Maintenance: 
Operation and maintenance of communications 
network 20,033 
Removal of debris, mosquitoes, and aquatic plant life 
from reservoirs 89,024 
Analysis of hydrologic and meteorologic data for 
scheduling releases from Lake Ocklawsha and 
Inglis Bypass 26,875 
Reimbursement to USGS for cooperative stream gauging 29,900 
Water quality surveillance 24,356 
Maintenance of tools and permanent equipment 46,407 
Maintenance of canal and dam slopes and berms 149,802 
Maintenance of dams 279,021 
Collection for quarters - 8,874 
Income from recreation fees - 10,649 
Clearing and snagging, Lake Ocklawaha 188,187 
Real Estate 6,900 
Condition and operation studies 85,787 
Engineering and design 84,083 
Supervision and Administration 40,781 
Maintenance of roads 14,707 
Trash removal 3,941 
Visitor Assistance 10,315 
Repair to slope revetment 2,393 
Service and maintain traffic counters 715 
Sub-Total 1,089,244 
Operation and care: 
Inglis Eureka and Buckman Locks, Rodman Dam 
Inglis Dam and Spillway, Inglis Bypass and Spillway, 
and buildings and grounds, and recreational facilities 
maintained by hired labor 777,833 
Buildings and grounds maintained by contract 20,856 
Sanitary facilities at recreation areas 18,819 
Sub-Total 812,508 
Jobs Bill 93,920 
Total 2,016,357 
9-47

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 9-F OKEECHOBEE WATERWAY 
OPERATIONS AND RESULTS DURING FISCAL YEAR 
(See Section 20 of Text) 
Work Performed Cost 
Maintenance: 
District communications network 54,192 
Repair and replacement of project signs 3,811 
Snagging and clearing 171,587 
Operation and maintenance of recreation facilities 90,724 
Natural resource facilities 10,624 
Collection for Quarters - 15,284 
Service and maintain traffic counters -9,276 
Visitor Assistance 26,693 
Real Estate 52,464 
Reevaluate and update master plan 165 
Condition and operation studies 36,302 
Contract Maintenance of Locks 323,952 
Dredging, St. Lucie Inlet -28,600 
Engineering and design 56,374 
Supervision and administration 67,711 
Hired labor surveys, inspections, and reports 9,485 
Total applied cost 850,924 
Operation and care: 
Hired labor cost of operating Moore Haven, Ortona 
and St. Lucie Locks and maintenance of structures 
and grounds 673,455 
Jobs Bill 165,954 
9-48

JACKSONVILLE, FLA. DISTRICT 
TABLE 9-G REMOVAL OF AQUATIC GROWTH FROM NAVIGABLE WATERS 
IN THE STATE OF FLORIDA 
CONTROL OPERATIONS 
(See Section 26 of Text) 
Locality Acres Controlled Cost 
St. John's River and tributaries and 
Withlacoohee, Kissimmee and Crystal Rivers 18,064 $1,282,663 
Okeechobee Waterway and tributaries 7,939 531,536 
White Amur study 44,816 
Acquisition and maintenance of airboats, 
engines, and work tools 57,202 
Rodman Dam Drawdown Study 25,737 
Operation of communications network 10,807 
Engineering design 107,409 
Supervision and Administration 132,903 
Total 26,033 2,192,273 
TABLE 9-H NAVIGATION PROJECTS ON WHICH RECONNAISSANCE AND 
CONDITION SURVEYS ONLY WERE CONDUCTED DURING FISCAL YEAR 
(See Section 33 of Text) 
Date Cost Incurred 
Survey D 
Project Conducted Per 
Anclote River. Fla. January 1983 $ 18,304 
Arecibo Harbor, P.R. October 1982 1,914 
Bakers Haulover Inlet, Fla. July 1983 5,942 
Broward County/Hillsboro Inlet November 1982 614 
Cedar Keys Harbor, Fla. April 1983 9 
Charlotte Harbor, Fla. May 1983 20,438 
Clearwater Pass, Fla. April 1988 25,814 
Eau Gallie Harbor, Fla. December 1982 17,384 
Fort Myers Beach, Fla. February 1988 18,521 
Fort Pierce Harbor April 1988 1,646 
Intracoastal Waterway, Jacksonville to Miami February 1988 10,620 
Intracoastal Waterway, Miami to Key West September 1988 71 
Johns Pass September 1988 7,966 
Key West Harbor, Fla. July 1988 47,787 
Kissimmee River, Fla. September 1988 89,727 
Lake Crescent and Dunns Creek December 1982 869 
Longboat Pass September 1988 8,229 
Manatee River June 1988 2,886 
Melbourne Harbor, Fla. December 1982 16,700 
Miami Harbor, Fla September 1988 29,868 
Channel from Naples to Big Marco Pass, Fla. September 1988 9,068 
New Pass January 1988 9,259 
New River, Fla. September 1988 746 
Pass-A-Grille Pass, Fla. December 1982 47 
Port Everglades Harbor, Fla. March 1988 212 
St. Augustine Harbor, Fla. September 1988 8,112 
St. Lucie Inlet, Fla. May 1988 82,094 
St. Johns River, Jacksonville to Lake Harney, Fla. February 1988 9,968 
San Juan Harbor, P.R. October 1982 4,221 
Supervision and Administration 5,282 
9-49

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
OTHER AUTHORIZED NAVIGATION PROJECTS 
(See Section 34 of Text) 
For Last Cost to Sept. 30, 1983 
Fual Report 
See annual Operation and 
Project Report For Construction Maintenance 
Anclote River, Fla. 1974 267,427 607,465 
Aquatic Plant Control, Fla. 
(R&H Acts of 1958 & 1962) 1968 2,619,700' - 
Atlantic Gulf Ship Canal, Fla. 1939 5,099,158 
Bakers Haulover Inlet. Fla.' 1965 243,235 87,124 
Bayport, Fla4 1972 58,495s 
- 
Cedar Keys Harbor, Fla 1977 168,5698 49,336 
Christiansted Harbor. St. Croix. V.I.,' 1964 308,817 38,891 
Clearwater Pass, Fla."1 1980 46,349 1,205,298 
Courtenay Channel, Fla.' 1940 22,846 18,254 
Crystal River, Fla.' 1941 25,000 90,899 
Eau Gallie Harbor, Fla.' 1970 9,627 84,914 
Everglades Harbor, Fla.' 1964 221,5098 49,106 
Fajardo Harbor, P.R.' 1945 - - 
Guayanes Harbor, P.R.' 1945 - - 
Gulf Intracoastal Waterway 
St. Marks to Tampa Bay, Fla. 1974 88,850- 
Homosassa River, Fla.' 1987 8,999o 10,590 
Horseshoe Cove, Fla. 1977 347,521 122,847 
Hudson River, Fla.' 1974 9,889- 
Intracoastal Waterway, Miami to Key West, Fla.' 1963 243,079 15,198 
Key West Harbor, Fla.' 1972 1,548,89210 519,229 
Kissimmee River, Fla.' 1981 23,479 89,021 
Lake Crescent and Dunns Creek, Fla." 1981 10,276 9,035 
Largo Sound Channel, Fla. "1 " 1966 117,443' s 41,340 
Little Manatee River, Fla. 4'," 1949 11,908"- 
Manatee River, Fla."a 1970 123,350 184,207 
Melbourne Harbor, Fla.' 1970 17,696 77,532 
New River Fla.' 1956 86,518 28,556 
Orange River, Fla.' 1962 2,000 28,567 
Ozona, Fla., channel and turning basin' 1963 105,527 14,783 
Palm Beach, Fla., side channel and basin' 1946 - - 
Pass-A-Grille Pass, Fla. , "s 1966 41,297' 50,577 
Pithlachascotee River, Fla. 1978 400,000" 253,516 
Rice Creek, Fla.' 1957 85,20818 17,777 
St. Thomas Harbor. V.I.4 1949 1,989- 
Steinhatchee River, Fla.' 1940 185,053 40,456 
Suwannee River, Fla." 1977 76,418" 195,959 
Withlacoochee River, Fla."a. 1969 614,912so 365,858 
1. Complete. 
2. Excludes $918,205 contributed funds. 
8. Excludes $2483,235 for contributed funds. 
4. Inactive. 
5. Includes $41,222 for reconnaissance and detailed project 
reports under Section 107 of the R&H Act of 1960. 
6. Includes $82,500 expended under previous project. Ex-. 
cludes $1,478 contributed funds. 
7. Project as modified by Chief of Engineers in report of June 
80, 1961, is complete. Previously authorized depth of 25 feet in in. 
active status. 
8. Excludes $36,000 contributed funds. 
9. In addition, $1,000 expended from contributed funds. 
10. Includes $27,500 for new work under previous project. Excludes 
$35,371 contributed funds. 
11. Deauthorized by Public Law 98-251, Section 12. 
11a. Inactive portion of project deauthorized by Public Law 
983.251, Section 12. 
12. Authorized April 20, 1964 by Chief of Engineers under Section 
107 of 1960 R&H Act. 
18. Includes $25,008 for detailed project report but excludes 
$86,716 expended from contributed funds. 
14. Expended on restudy. 
15. Authorized November 19,1964 by Chief of Engineers under 
Sections 107 of R&H Act of 1960. 
16. Excludes $41,297 contributed funds. 
17. Excludes $215,723 contributed funds. 
18. Excludes $98,000 contributed funds. 
19. Includes $10,154 expended under previous project. 
20. Includes $30,000 expended under previous project. 
21. Balance of $61 from prior year and transfer has been made 
during FY 1981. 
9-50 
TABLE 9-I

JACKSONVILLE, FLA. DISTRICT 
TABLE 9-J 
OTHER AUTHORIZED BEACH EROSION PROJECTS 
(See Section 46 of Text) 
For Last Cost to Sept. 30, 1983 
Ful Report 
See annual Operation and 
Project Report For Construction Mintenance 
Cape Florida State Park 1969 84,862' 
Key West, Fla. 1968 96,840' 8,794 
Lee County, Fla. 1971 - - 
Lido Key, Fla. 1971 
Mullet Key, Fla. 1978 486,201' 1,656 
Palm Beach County, Fla., from Lake Worth Inlet to 
South Lake Worth Inlet 1970 195,140 6,257 
San Juan, Puerto Rico 1965 
Virginia Key and Key Biscayne, Fla. 1978 1,667,220' 1,022 
1. Includes $2,462 cost of reconnaissance and detailed project 4. Excludes $781,188 in property or services furnished by 
reports but excludes $18,818 contributed funds. local interests in lieu of cash contribution. 
2. Excludes $192,168 contributed funds. 5. Excludes $714,522 contributed funds. 
3. Excludes $187,188 contributed funds. 
TABLE 9-K CENTRAL AND SOUTHERN FLORIDA PROJECT 
PRINCIPAL FEATURES OF HURRICANE GATES 
(See Section 48 of Text) 
Depth Character 
Over of Year 
Gate' Nearest Town Distance Sills Founds- Com- Actual 
No. Name (miles) (ft.) tion pleted Cost 
2. Clewiston, Fla. 0.5 10 Pile 1985 $809,748 
8. Lake Harbor, Fla. 0.5 10 Rock 1985 316,988 
4. Belle Glade, Fla. 4.0 10 Rock 1985 350,025 
5. Canal Point, Fla. 0.0 10 Rock 1985 262,465 
6. Okeechobee, Fla. 0.5 7 Pile 1986 878,273 
'All are 50 feet wide with available length unlimited. They are 
constructed of concrete with steel sector gates and have no lift. 
Gate No. 6 has an auxiliary culvert spillway with automatic control. 
Moore Haven Lock serves as Hurricane Gate Structure 1. 
9-51

CENTRAL AND SOUTHERN FLORIDA PROJECT 
PRINCIPAL FEATURES OF LOCKS AND DAMS 
(See Section 48 of Text) 
Miles Elevation 
From Lock Normal of Normal Character Kind Kind 
Nearest Nearest Dimensions lift Pool Depth of of of of Percent Contract 
Town Town (ft.) (ft.) surface (ft.) sills (ft.) foundation Dam Construction Complete Cost 
S-6L5o Lcko caknd Dam 
S-65A Lock 
S-65B Lock 
S-65C Lock 
S-65D Lock 
S-65E Lock 
to Moore Haven 
Lock (HGS-1 
Mod.) 
8-310 
(HGS-2 Mod.) 
S-193 
(HGS-6 Mod.) 
S-308B 
(Port Mayaca) 
S-57 
S-58 
S-59 
8.60 
S-61 
8.62 
8 -63 
S-63A 
S-96 
S-96A 
S-53 
S-55 
8-157 
8-158 
W.P. Franklin At Olga 0 56 x 400 2.5 3.0 14 Piles in 
Frostproof 
Avon Park 
Sebring 
Sebring 
Okeechobee 
Okeechobee 
Hoore Haven 
Clewiston 
Okeechobee 
Pahokee 
Ashton 
Ashton 
Kissimmee 
Ashton 
St. Cloud 
Ashton 
Ashton 
Ashton 
Sebastian 
Sebastian 
Eau Gallie 
Christmas 
Sebastian 
Titusville 
23 
26 
20 
25 
14 
10 
0.5 
0.5 
0.5 
11
9
566 
6 
10 
12 
14 
14 
16 
8 
12 
4 
15 
30 x 90 
30 x 90 
30 x 90 
30 x 90 
30 x 90 
30 x 90 
50 x 250 
50 x 60 
50 x 60 
56 x 400 
20 x 90 
20 x 90 
20 x 90 
20 x 90 
30 x 90 
20 x 90 
20 x 90 
20 x 90 
20 x 60 
20 x 60 
20 x 60 
20 x 60 
20 x 60 
20 x 60 
4.2 
6.3 
6.0 
7.2 
5.8 
4.6 
9.4 
5.0 
7.5 
4.0 
1.0 
2.0 
3.0 
2.0 
2.0 
3.0 
5.0 
4.5 
4.0 
7.5 
3.5 
10.0 
20.0 
4.5 
48.5-52.3' 
46.3 
40.0 
34.0 
26.8 
21.0 
15.5-17.53 
15.5-17.53 
15.5-17.53 
15.5-17.53 
62.0 
64.0 
58.0 
64.0 
55.0 
61.0 
62.0 
57.0 
24.0 
25.0 
17.5 
14.0 
20.0 
4.0 
6
6
6
6
6
6 
11 
12.9 
7.5 
18
6
6666666666666 
clay 
Earth 
foundation, 
sand 
Earth 
foundation, 
sand 
Earth 
foundation, 
sand 
Earth 
foundation, 
sand 
Earth 
foundation, 
sand 
Earth 
foundation, 
sand 
Piles in 
sand 
Slab on 
sand 
Piles in 
sand and 
slab on sand 
Slab on 
sand 
Earth 
foundation, 
sand
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Movable Reinforced 
concrete 
None Reinforced 
concrete 
rigid frame 
None Reinforced 
concrete 
rigid frame 
None Reinforced 
concrete 
rigid frame 
None Reinforced 
concrete 
rigid frame 
None Reinforced 
concrete 
rigid frame 
None Reinforced 
concrete 
None Steel sheet pile 
lockwalls 
None Reinforced 
concrete 
None Reinforced 
concrete 
Fixed Reinforced 
concrete 
None Concrete and 
steel sheet 
pile 
None Do. 
None Do. 
None Do. 
None Do. 
None Do. 
None Do. 
None Do. 
None Do. 
None Do. 
None Do. 
None Do. 
None Do. 
None Do. 
'Operation and care of W.P. Franklin Lock and Dam (8-79) is a Federal responsibility. 3The normal pool level varies seasonally between the two elevations. 
'Operation and care of W.P. Franklin Lock and Dam (S-79) is a Federal responsibility. 
"Estimated. !The normal pool level varies seasonally between the two elevations. 
TABLE 9-L 
100 $3,803,655 
100 $1,191,574.70 
100 $1,513,693.91 
100 $1,050,600.69 
100 $1,326,073.12 
100 $1,213,248.51 
100 $1,320,039.84 
0 $301,000'2 
100 $3,448,406 
0 $427,3002 
100 $8,308,700 
0 $1,632,000' 
0 $1,632,0002 
0 $1,632,0002 
0 $1,632,000' 
100 $689,217 
0 $1,632,000' 
0 $1,632,0002 
0 $1,598,000' 
0 $1,431,0002 
0 $1,362,0002 
0 $1,322,000' 
0 $1,355,0002 
0 $1,723,0002 
0 $1,558,000' 
O
y
tol 
O
0
A'El 
. 
t l 
x
G
rE 
t~l 
tCl 
CC.

JACKSONVILLE, FLA. DISTRICT 
TABLE 9-M CENTRAL AND SOUTHERN FLORIDA PROJECT 
LOCAL COOPERATION 
(See Section 48 of Text) 
Flood Control Act Work Authorised % Cash Comtributions' 
June 30, 1948 First phase of comprehensive plan 15.0 
Sept. 3, 1954 Second phase of comprehensive plan 20.0 
July 14, 1960 Nicodemus Slough area 81.5 
Oct. 23, 1962 West Palm Beach Canal 12.8 
Bogy Creek Basin 29.7 
Shingle Creek Basin 25.9 
South Dade County area 19.2 
Reedy Creek Swamp 50.0 
Oct. 27, 1965 Southwest Dade County 46.0 
Hendry County area 19.5 
Aug. 18, 1968 Martin County 
Flood Control Features 84.0 
Irrigation Features 49.0 
Recreation Features 42.0 
Water Resources 20.0 
Approved Dec. 17, 1970 Navigation improvements suitable for 50.0 
under Provisions of recreational craft 
Section 201 of 1965 
Flood Control Act 
'Computed on total contract cost and supervision and administration 
except for Reedy Creek Swamp which is computed on 
all costs, including engineering and design and land. 
9-53

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 9-N CENTRAL AND SOUTHERN FLORIDA PROJECT 
OPERATIONS AND RESULTS DURING FISCAL YEAR 
(See Section 48 of Text) 
Work Performed Cost 
New Work: 
Construction of: 
Pumping Stations $ 22,170 
Channels and canals 1,506,001 
Levees 109,181 
Floodway control and diversion structures 2,558,630 
Building, Grounds and Utilities 586,778 
Depreciation - 830 
Engineering and design 1,530,955 
Supervision and administration 552,831 
Total applied cost 6,865,716 
Maintenance: 
Operation of district communications network 45,214 
Repair or replacement of project signs 119,466 
Patrol, inspections, and maintenance of Herbert Hoover Dike 558,444 
Irepair and stabilize crown road, Herbert Hoover Dike 58,268 
Remove weed growth and replant grass on levee slopes, 
Herbert Hoover Dike 80,196 
Rebuild and regrade levee slopes, Herbert Hoover Dike 37,281 
Clean out landslide toe ditches and berms on Herbert Hoover Dike 12,800 
Repair or replace culverts, Herbert Hoover Dike 66,830 
Repair fences, Herbert Hoover Dike, LD-3 97,819 
Recreation area, W.P. Franklin Lock 88,922 
Berms, fences and shrubs on C-43 11,556 
Clear debris from landslide entrance channel to all 
culverts, approach channels at HGS and floodway channels 7,035 
Repair and riprap eroded berms, Herbert Hoover Dike 988,388 
Remove trees and riprap slopes, Herbert Hoover Dike 24,768 
Operations W.P. Franklin Lock and Spilway (S-79) 214,484 
Operations and maintenance of spillways: 
St. Lucie (8-80); Moore Haven (S-77); 
Ortona (8-78); S-10, 11, & 12 158,463 
Sandblast and paint 8-77, Moore Haven Spillway 765 
Operation of four hurricane gate structures 4,363 
Mowing grass on levee slopes Herbert Hoover Dike 109,038 
Collection for quarters and damages -4,856 
Operation of Port Mayaca Lock and Spillway 171,270 
Reimbursement to U.S.G.S. for cooperative stream gaging 41,091 
Analysis of data for scheduling releases 183,894 
Water quality studies 193,839 
Real Estate Management 1,976 
Dam Safety Studies 136,378 
Service and maintain traffic counters 5,724 
Dewater, repair, sandblast and paint S-12, HGS-3 34,998 
Periodic Surveys 75,494 
Reevaluate and update master plan 455 
Performance momnitoring 17,122 
Maintenance of Airboat 598 
Study by Waterway Experiment Station 6,746 
Regulatory of Lake Okeechobee and 3 construction areas 
Collection of data by CAO 87,636 
Maintenance of hydrometeorological network 69,659 
Visitor Assistance 50,244 
Snapging and Riprap 14,750 
Engineering and design 45,243 
Supervision and admnistration 147,353 
Total applied cost 3,958,713 
9-54

JACKSONVILLE, FLA. DISTRICT 
TABLE 9-0 CENTRAL AND SOUTHERN FLORIDA PROJECT 
CONSTRUCTION COMPLETED UNDER EXISTING PROJECT DURING FISCAL YEAR 
(See Section 48 of Text) 
Date transferred to 
Flood Control District 
Construction for Operation and 
Feature Period Maintenance 
Channels and Canals: 
C-103 March 1979 - February 1983 Pending 
Structures: 
8-135 January 1980 - November 1982 June 1988 
8-153 January 1980 - November 1982 June 1988 
8-341 September 1981- November 1982 1 
Pumping Plants: 
S-3831 March 1979 - February 1983 Pending 
Levees: 
L-18 & 19 April 1980 - May 1982 May 1982 
L-24 & 25 January 1980 - December 1982 January 1983 
L-65 January 1980 - November 1982 June 1983 
'Transferred to National Park Service. 
TABLE 9-P CENTRAL AND SOUTHERN FLORIDA PROJECT 
STATUS OF WORK UNDER CONTRACT AT END OF FISCAL YEAR 
(See Section 48 of Text) 
Construction Approx. 0/% 
Feature Started Complete 
Channels and Canals: 
C-51 May 1982 67 
Levees: 
L-28 Modification June 1988 9 
L-67 Modification December 1983 0 
Herbert Hoover Dike Revetment 
1st Contract (4 miles) March 1983 16 
2nd Contract (4.5 miles) September 1983 5 
Structures: 
S-343A & B June 1983 9 
S-344 June 1983 9 
S-155 May 1982 67 
9-55

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
FOUR RIVER BASINS, FLORIDA PROJECT 
MOSS BLUFF LOCK 
(See Section 49 of Text) 
Nearest town 
Name of nearest town 
Distance above mouth of River 
Lock dimensions 
Normal lift 
Elevation of normal pool surface 
Depth of sills 
Character of foundation 
Kind of dam 
Type of construction 
Percent complete 
Estimated Cost (including dam and spillway) 
20 miles 
Ocala, Fla. 
65.5 miles 
30 x 125 feet 
18.0 feet 
58 feet 
12 feet 
Piles in sand 
None 
Reinforced concrete 
100 
$1,990,138 
TABLE 9-R FOUR RIVER BASINS, FLORIDA PROJECT 
CONDITION AT END OF FISCAL YEAR 
(See Section 49 of Text) 
Date transferred to 
Construction Southwest Florida 
Feature Period for Operation and Maintenance 
Bridges: 
B-194 July 1968 - Mar. 1970 Not transferred 
Alteration of Facilities B-195 May 1971 - Jan. 1973 Do. 
B-594 Jan. 1978 - Jan. 1974 Do. 
Alteration of Facilities B-196 Oct. 1972 - Jan. 1975 Do. 
SCL RR Br., B-196 Dec. 1972 - July 1975 July 1975 
Channels and Canals: 
C-185 May 1967 - Dec. 1968 Dec. 1968 
C-185, See. 1A July 1966 - Aug. 1967 Oct. 1967 
C-135, Sec. 1B May 1968 - Sep. 1972 Not transferred 
C-185, Sec. 1C & 2 Jan. 1971 - Dec. 1978 Not transferred 
C-135, See. 8A Dec. 1972 - Apr. 1975 Oct. 1977 
C-185, See. SB Feb. 1975 - Aug. 1977 Not transferred 
C-185, See. 4A Apr. 1976 - Jan. 1979 Not transferred 
C-186 Aug. 1975 - May 1977 Nov. 1977 
C-281, Phase I July 1978 - Apr. 1975 Dec. 1975 
C-281, Phase II July 1978 - Jan. 1974 Dec. 1975 
C.881 July 1967 - Sep. 1968 Sep. 1968 
C-5831 Apr. 1966 - Jan. 1969 Apr. 1969 
C-584 June 1970 - July 1971 Nov. 1971 
C-185 March 1977 - Oct. 1980 
Structures: 
8.160 May 1967 - Dec. 1968 Dec. 1968 
8-161 Aug. 1975 - May 1977 Nov. 1977 
8-182 Apr. 1975 - June 1977 Apr. 1977 
8-858 July 1967 - Sep. 1968 Nov. 1968 
Moss Bluff Lock and Spillway Apr. 1967 - Mar. 1969 Dec. 1975 
8-551 July 1970 - Feb. 1972 Not transferred 
Levees: 
L-212, Sec. 1 June 1968 - July 1970 Dec. 1975 
L-212, Sec. 2 July 1970 - Sep. 1971 Dec. 1975 
L-112 March 1977 - Oct. 1980 Oct. 1980 
L-112 & Floodway May 1978 - July 1981 Jan. 1988 
8-15 May 1978 - July 1981 Jan. 1988 
8-168 May 1978 - July 1981 Jan. 1988 
8-159 Middle & Lower April 1979 - Aug. 1981 Oct. 1981 
8-159 Upper June 1979 - Sep. 1981 
9-56 
TABLE 9-Q

JACKSONVILLE, FLA. DISTRICT 
TABLE 9-S OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(See Section 52 of Text) 
For Last Cost to Sept. 30, 1983 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Arch Creek, Dade County, Fla. 1960 $66,4851 
Biscayne Bay, Fla., Hurricane Protection 1966 
Hillsborough Bay, Fla. 1969 - - 
Phillippi Creek Basin, Fla.' 1966 
1. Excludes $11,734 cost of preauthorization studies. Project 2. Inactive. 
was authorized February 20, 1959, by Chief of Engineers under 
Section 205 of the 1948 Flood Control Act as Modified by P.L. 685, 
84th Congress. 
TABLE 9-T FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION 
PURSUANT TO SECTION 205, PUBLIC LAW 685, 
(PREAUTHORIZATION) 
(See Section 53 of Text) 
Study Identification Period Costs 
Detailed Project Report: 
Alligator Creek Basin, CL Fla. $ 31,296 
Estate Mon Bijou, V.I. $71,392 
Naguabo River, P.R. 5,237 
Rio Cibuco, Vega Baja, PR. 42,122 
Sabana Grande, P.R. 2,8332 
Savan Gut-St. Thomas, V.I. 3,760 
Seminole Basin, Fla. 35,439 
Whitaker Bayou, Sarasota, Fla. 88,274 
9-57

MOBILE, AL., DISTRICT* 
This district comprises a small portion of southeastern 
Tennessee, western Georgia, western Florida, 
all of Alabama south of Tennessee River Basin, eastern 
Mississippi, and a small portion of southeastern Louisiana 
embraced in drainage basins tributary to the Gulf of 
Mexico, west of Aucilla River Basin, to and including 
the Pascagoula River Basin. The Pearl River Basin, 
Mississippi was included as part of the Mobile District 
until 1 October 1981, when responsibilities were transferred 
to Vicksburg District, Lower Mississippi Valley 
Division. A section of the Gulf Intracoastal Waterway 
from St. Marks, Florida, to Lake Borgne Light No. 29, 
Louisiana is also within Mobile District. 
IMPROVEMENTS 
Navigation 
1. Apalachicola Bay, FL .................. 
2. Aquatic Plant Control (R&H Act 
of 1965) ............................. 
3. Bayou Coden, AL .................... 
4. Bayou La Batre, AL .................. 
5. Biloxi Harbor, MS .................... 
6. Black Warrior and Tombigbee 
Rivers, AL ........................... 
7. Bon Secour River, AL ................. 
8. Cadet Bayou, MS .................... 
9. Dauphin Island Bay, AL .............. 
10. Dog and Fowl Rivers, AL ............. 
11. East Pass Channel from Gulf 
of Mexico into Choctawhatchee 
Bay, FL ............................. 
12. Gulf Intracoastal Waterway 
between Apalachee Bay, FL 
and Mexican Border (Mobile 
District) ............................ 
13. Gulfport Harbor, MS ................. 
14. Mobile Harbor, AL ................... 
15. Panama City Harbor, FL ............. 
16. Pascagoula Harbor, MS ............... 
17. Pensacola Harbor, FL ................ I 
18. Perdido Pass Channel, AL ............ I 
19. Port St. Joe Harbor, FL ............. 1 
20. Removing Water Hyacinths, 
Mobile District ..................... I 
21. Waterway Connecting Tombigbee 
and Tennessee Rivers, AL 
andM S ............................ 1 
22. Reconnaissance and Condition 
Surveys ............................ 1 
23. Other Authorized Navigation 
Projects ............................ I 
24. Navigation Work Under Special 
Authorization ..................... 1
Page 
10-2 
Beach Erosion Control 
25. Authorized Beach Erosion Control 
Project ............................ 
Deauthorized Projects 
26. Deauthorized Projects ............... 
Flood Control 
10-4 27. Okatibbee Lake, MS ................. 
10-5 28. Tallahala Creek Lake, Pascagoula 
10-6 River, M S ......................... 
10-6 29. Burketts Creek, 
10-6 Amory, MS ......................... 
30. Gordons Creek, 
Hattiesburg, MS ...................... 
10-7 31. Murder Creek, 
East Brewton, AL ................... 
32. Sun Creek, 
Oktibbeha County, MS .............. 
10-7 33. Tombigbee River Tributaries, 
10-8 MS and AL ........................ 
10-8 34. Trim Cane Creek, 
10-9 Oktibbeha County, MS .............. 
10-9 35. Inspection of Completed Flood 
10-10 Control Projects .................... 
0-10 36. Other Authorized Flood Control 
0-11 Projects ............................ 
37. Flood Control Work Under Special 
0-11 Authorization ...................... 
Multiple Purpose Projects 
Including Power 
10-12 38. Alabama-Coosa Rivers, AL 
and GA ............................ 
0-12 38A. Carters Lake, GA ................... 
38B. Claiborne Lock and Dam, 
0-12 AL ................................ 
10-1 
Page 
10-12 
10-12 
10-12 
10-13 
10-13 
10-13 
10-13 
10-14 
10-14 
10-14 
10-14 
10-15 
10-15 
10-15 
10-16 
10-16 
1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
38C. Robert F. Henry 
Lock and Dam, AL .................. 10-16 
38D. Millers Ferry Lock and Dam, 
AL ................................. 10-17 
38E. Coosa River Navigation ............... 10-17 
39. Allatoona Lake, Coosa River 
Basin, GA ........................... 10-17 
40. Apalachicola, Chattahoochee, 
and Flint Rivers, 
AL, GA, and FL .................... 10-18 
40A. Buford Dam, GA ................... 10-19 
40B. George W. Andrews Lock and 
Dam, AL and GA ..................... 10-19 
40C. Jim Woodruff Lock and Dam, GA 
and FL ............................. 
40D. Spewrell Bluff Lake, GA............. 
40E. Walter F. George Lock and Dam, 
AL and GA ......................... 
40F. West Point Lake, Chattahoochee 
River Basin, GA and AL ............. 
41. Scheduling Flood Control 
Reservoir Operations ................ 
General Investigations 
42. Surveys ............................ 
43. Collection and Study of Basic 
D ata ............................... 
Tables 
Table 10-A 
Table 10-B 
Table 10-C 
Table 10-D 
Table 10-E 
Table 10-F 
Table 10-G 
Table 10-H 
Table 10-I 
Cost & Financial 
Statement .................. 
Authorizing Legislation ...... 
Black Warrior & 
Tombigbee Rivers, AL........ 
Reconnaissance & 
Condition Surveys ............ 
Other Authorized Navigation 
Projects .................... 
Navigation Work Under 
Special Authorization........ 
Other Authorized Beach 
Erosion Control Project ....... 
Deauthorized Projects........ 
Other Authorized Flood 
Control Projects ............. 
10-23 
10-28 
Table 10-J 
Table 10-K 
10-37 
10-37 Table 10-L 
10-38 
10-38 
10-39 
10-39 
10-39 
Table 10-M 
Flood Control Work Under 
Special Authorization ........ 
Alabama-Coosa Rivers, 
AL and GA Development 
Proposed Under Existing 
Project ...................... 
Apalachicola, Chattahoochee, and 
Flint Rivers, AL, GA and 
FL, Locks and Dams and 
Multiple-Purpose Development 
Included in Existing 
Project ..................... 
Completed Flood Insurance 
Studies and Flood 
Hazard Information 
Reports .................... 
Navigation 
1. APALACHICOLA BAY, FL. 
Location. The project is on the coast of northwest 
Florida 160 miles east of Pensacola Harbor. (See Coast 
and Geodetic Survey Chart 11401.) 
Previous project. For details, see page 1833, Annual 
Report for 1915, and page 689, Annual Report for 
1938. 
Existing project. The authorized project provides 
for: (a) A channel 10 feet deep and 100 feet wide from 
the 10-foot depth in Apalachicola Bay, across St. 
George Island, to within 300 feet of the gulf shore, 
thence increasing uniformly in width to 200 feet at the 
shore and continuing with that width to the 10-foot 
depth in the Gulf of Mexico, with twin jetties extending 
from the dune line to the outer end of the channel; (b) 
an inner bar channel, 10 feet deep and 100 feet wide, in 
Apalachicola Bay; (c) a boat basin 200 feet by 880 feet 
and nine feet deep at Apalachicola, Florida, with a 
connecting channel nine feet deep and 80 feet wide 
through Scipio Creek to Apalachicola River; (d) a 
channel known as Link Channel, 10 feet deep and 150 
feet wide, in Apalachicola Bay; (e) a channel generally 
parallel to the shore at Eastpoint, Florida, six feet deep, 
100 feet wide, and about 6,000 feet long, with a connecting 
channel six feet deep and 100 feet wideto water at 
the same depth in St. George Sound; (f) a channel ten 
feet deep and 100 feet wide through Bulkhead Shoals, 
connecting Apalachicola Bay with St. George Sound; 
and (g) a 6-foot by 100-foot channel about one mile 
long, generally parallel to the shore at Two Mile, Florida, 
with a 6-foot by 100-foot connecting channel to 
water of the same depth in Apalachicola Bay. (See 
Table 10-B for authorized modifications of Two Mile 
project.) Mean range of tide throughout this harbor is 
1.6 feet. Extreme range, except during storms, is about 
three feet. Plane of reference is mean low water. (See 
Table 10-B for authorizing legislation.) 
10-2 
Page 
10-20 
10-20 
10-20 
10-21 
10-21 
10-22 
10-22 
10-40 
10-41 
10-42 
10-43

MOBILE, ALABAMA DISTRICT 
Local cooperation. Requirements have been fully 
complied with. 
Terminal facilities. Facilities consist of pile-and-timer 
wharves which are considered adequate for existing 
commerce. 
Operations and results during fiscal year. New work: 
None. 
Maintenance: Normal operation and maintenance 
cost amounted to $55,370. 
Condition at end of fiscal year. The existing project, 
authorized by the 1954 River and Harbor Act, was 
completed in 1959, including reimbursement to local 
interests for approved work, as authorized by the 1958 
River and Harbor Act. Improvements at Two Mile 
except for modifications authorized in 1975 were completed 
in September 1964. Construction of the breakwater 
and channel improvements authorized in 1975 at 
Two Mile were completed in September 1977. Total 
Federal costs under existing project as of September 30, 
1983 were $1,898,848 for new work and $2,194,884 for 
maintenance, a total of $4,093,732. 
2. AQUATIC PLANT CONTROL (RIVER 
AND HARBOR ACT OF 1965) 
Location. Navigable water, tributary streams, connecting 
channels and other allied waters in Mobile 
District. 
Existing project. The authorized project provides for 
management and control of water hyacinth, alligatorweed, 
Eurasian watermilfoil, hydrilla, and other obnoxious 
aquatic plant growths from navigable water, tributary 
streams, connecting channels, and other allied 
waters of the United States, in the combined interest of 
navigation, flood control, drainage, agriculture, fish 
and wildlife conservation, public health, and related 
purposes, including continued research for development 
of the most effective and economical control measures 
to be administered by the Chief of Engineers, 
under the direction of the Secretary of the Army, in 
cooperation with other Federal and State agencies. 
Research and planning cost prior to construction shall 
be borne fully by the United States. (See Table 10-B for 
authorizing legislation.) 
Local cooperation. Local interests shall agree to hold 
and save the United States free from claims that may 
occur from control operations and to participate to the 
extent of 30 percent of such operations. Requirements 
are being met in the state of Alabama. 
Operations and results during fiscal year. None. 
Condition at end of fiscal year. Total Federal costs 
under the existing project as of September 30, 1983 were 
$413,442. Contributed funds for maintenance amount 
to $21,225. 
3. BAYOU CODEN, AL 
Location. The project is located in a small tidal 
stream on the southern coast of Mobile County, Alabama, 
emptying into Mississippi Sound about 7.6 miles 
northwest of Cedar Point, the southern tip of western 
mainland shore of Mobile Bay. (See Coast and Geodetic 
Survey Chart 11376.) 
Previous project. For details see Annual Report for 
1945, page 843. 
Existing project. The project provides for a channel 
eight feet deep by 60 feet wide extending from La Belle 
Avenue bridge south for about 3,000 feet through the 
bayou to Portersville Bay, thence eight feet deep by 100 
feet wide extending about 2.3 miles westward across 
Portersville Bay to connect with the Bayou La Batre 
channel, and a turning basin eight feet deep by 60 feet 
wide by 100 feet long on the west side of the bayou 
channel about 500 feet south of the La Belle Avenue 
bridge. Mean tidal range is 1.75 feet, and extreme, 
except during storms, is 3.5 feet. Plane of reference is 
mean low water. (See Table 10-B for authorizing 
legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Small privately-owned pile-andtimber 
piers used in connection with fishing industry in 
this locality are adequate for existing commerce. A 
marina which will accommodate about 12 small recreational 
craft, and a slip with facilities for loading oyster 
shells are located near the mouth of the bayou, and are 
maintained by the Alabama Department of Conservation. 
Operations and results during fiscal year. New work: 
None. 
Maintenance: Surveys and miscellaneous costs amounted 
to $15,357. 
Condition at end of fiscal year. That portion of the 
project authorized prior to the 1969 modification was 
completed in 1956. Construction authorized in 1969 was 
initiated 31 March 1975 and completed 26 March 
1976.Total Federal costs under existing project as of 
September 30, 1983 were $325,051 for new work and 
$284,846 for maintenance, a total of $609,897. Contributed 
funds expended for new work amount to $100,000 
and $50,000 for maintenance. 
4. BAYOU LA BATRE, AL 
Location. Bayou La Batre is a tidal stream about 10 
miles long, emptying into Mississippi Sound on the 
southern coast of Mobile County, Al., about 10 miles 
northwest of Cedar Point, the southern tip of the western 
mainland shore of Mobile Bay. (See Coast and 
Geodetic Survey Chart 11373.) 
Previous project. For details see Annual Report for 
1945, page 844. 
Existing project. The authorized project provides for 
a 12-foot by 100-foot channel from the 12-foot depth in 
Mississippi Sound to a point about 2,800 feet south of 
the highway bridge, thence a channel 12 feet deep by 75 
feet wide to the bridge, an overall distance of about 
10-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
33,500 feet, with the channel widened at a point 0.6 mile 
below the bridge to provide a turning basin 12 feet deep 
and about 2.6 acres in area. Mean tidal range is 1.75 feet, 
and extreme, except during storms, is 3.75 feet. Plane of 
reference is mean low water. (See Table 10-B for authorizing 
legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Wooden wharves have been provided 
at seafood processing plants and public launching 
ramps are available. Facilities are considered adequate 
for existing commerce. 
Operations and results during fiscal year. Maintenance: 
Contract dredging removed 136,716 cubic yards 
of material from the Mississippi Sound Channel at a 
cost of $691,450. Condition surveys, contract administration, 
water control management and other costs 
amounted to $62,446. 
Condition at end of fiscal year. The existing project 
was modified December 30, 1966 under the discretionary 
authority of the Chief of Engineers to include a 
turning basin. The project was completed in March 
1967. Total Federal costs under existing project as of 
September 30, 1983 were $311,095 for new work and 
$2,442,044 for maintenance, a total of $2,753,139. Contributed 
funds from local interests for new work amount 
to $10,500. 
5. BILOXI HARBOR, MS 
Location. The project is located on Mississippi 
Sound in southeastern Mississippi, 32 miles by water 
west of Pascagoula Harbor, Mississippi, and 14 miles 
east of Gulfport Harbor, Mississippi (See Coast and 
Geodetic Survey Chart 11373.) 
Previous project. For details see page 584, Annual 
Report for 1962. 
Existing project. The authorized project provides for 
a continuous channel 12 feet deep, 150 feet wide and 23 
miles long from the Gulf Intracoastal Waterway through 
Mississippi Sound east of Deer Island, Biloxi Bay, Back 
Bay, Cranes Neck, and a land cut to Gulfport Lake, 
including a 500-foot by 2,600-foot basin in the lake, 
thence a 12-foot deep by 100-foot wide channel for 
about two miles westward from the west end of the lake, 
terminating in a 300-foot by 500-foot basin; a 12-foot by 
100-foot channel from the main channel in Big Lake to 
and up Bayou Bernard to the Air Force oil terminal at 
about mile 2.6; a 12-foot by 150-foot spur channel from 
the main channel in Biloxi Bay for about one mile, 
terminating in a 400-foot by 600-foot lateral channel 
westward about 2.2 miles to Biloxi's south waterfront; a 
10-foot by 150-foot channel from Mississippi Sound, 
passing west of Deer Island to a point where it connects 
to the 12-foot by 150-foot lateral channel at Biloxi's 
south waterfront. Construction for the modifications 
authorized by River and Harbor Act of Nov. 7, 1966 
was commenced in FY 1974 and completed in Feb. 
1975. Further modifications to the project were authorized 
by the Chief of Engineers on 28 March 1979, which 
provided for a channel 10 feet deep, 100 feet wide and 
300 feet long extending northward from the Biloxi Lateral 
Channel, and into a rectangular basin, approximately 
300 by 370 feet. 
Cost of modification as authorized by the 1966 River 
and Harbor Act was $664,390. That portion of the 
project providing for an entrance channel six feet deep, 
50 feet wide, and about 1,800 feet long into Old Fort 
Bayou, as authorized by the 1945 River and Harbor 
Act, is inactive. Estimated cost (1954) of this portion 
was $6,000. (See Table 10-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. A number of wooden piling-andtimber 
piers for small craft and fishing boats, a bulk 
gasoline terminal, several boat ways, and concrete products 
plant are available. 
Operations and results during fiscal year. New work: 
None. 
Maintenance: Condition and operation studies amounted 
to $39,065. Engineering and design and other 
miscellaneous costs amounted to $11,024. 
Condition at end of fiscal year. The existing project, 
prior to the modification authorized in 1966, was commenced 
in 1931 and completed in 1962. This 1966 authorized 
modification was completed in FY 1975. The 
1979 modification was completed in FY 1980. Total 
Federal costs under existing project as of 30 September 
1983 were $1,171,054 for new work and $4,912,164 for 
maintenance, a total of $6,083,218. Contributed funds 
for new work amount to $102,600. 
6. BLACK WARRIOR AND 
TOMBIGBEE RIVERS, AL 
Location. Black Warrior River rises in northern Alabama 
above Birmingham and flows generally southwesterly 
to unite with the Tombigbee River at Demopolis, 
Alabama. Thence, the Tombigbee flows south, uniting 
with the Alabama River to form the Mobile River 45 
miles above the head of Mobile Bay. Distance by water 
from Mobile to the vicinity of Birmingham is about 415 
miles. 
Previous project. For details see page 732, Annual 
Report for 1938. 
Existing project. The authorized project provides essentially 
for a canalized channel nine feet deep and 200 feet 
wide from the mouth of the Tombigbee River, 45 miles 
above Mobile, to the vicinity of Birmingham, via the 
Tombigbee and Black Warrior Rivers, to mile 430.4 on 
Sipsey Fork, mile 429.6 on Mulberry Fork and mile 
407.8 on Locust Fork, and for maintenance by snagging 
of Mobile River above the mouth of Chickasaw Creek, 
a total waterway distance of about 408 miles. The total 
lift of 255 feet is accomplished by six locks and dams. 
The original construction program, consisting of 17 
dams with 18 lifts, was completed in 1915. Replacement 
of the original structures with new locks and dams, 
10-4

MOBILE, ALABAMA DISTRICT 
under the modernization program is as follows: William 
Bacon Oliver replaced locks 10, 11, and 12; Demopolis 
replaced locks 4, 5, 6, and 7; Warrior replaced locks 8 
and 9; Coffeeville (Jackson) replaced locks 1, 2, and 3; 
and Holt replaced locks 13, 14, 15, and 16. Thus,16 of 
the original locks have been replaced by five new locks. 
Bankhead Lock and Dam (Lock 17) rehabilitation to 
replace the original double lift lock with a single lift lock 
was completed in 1980. The Jackson Lock and Dam 
wildlife refuge, authorized in 1960, includes 4,250 acres 
within the reservoir area and along its boundaries. (See 
Table 10-B for authorizing legislation.) 
Tidal influence extends upstream from Mobile 101.6 
miles to the old lock 1, where tidal effect is apparent 
only at low stages of the river. At Mobile the mean and 
extreme tidal ranges are 1.5 and 3.6 feet, respectively. 
These are at times slightly increased by the effect of 
winds. The greatest fluctuation of river stages is at 
Demopolis, Ala., the maximum being 59.7 feet. Maximum 
fluctuations at other points are 40 feet at lock 
1,100.6 miles from Mobile; 57.8 feet at Tuscaloosa, 
346.1 miles from Mobile; 13 feet at Birmingport, 404.9 
miles from Mobile; and 27 feet at Cordova, 424.3 miles 
from Mobile. Ordinary fluctuations at these points are 
at old lock 1, 20 feet; at Demopolis, 35 feet; at Tuscaloosa, 
40 feet; at Birmingport, four feet; and at Cordova, 
seven feet. Works of improvement reduced the 
amount of fluctuations at different points by three to 10 
feet. Estimated 1981 cost of providing recreation facilities 
at completed projects (Code 710) is $1,510,000. 
Local cooperation. Requirements of local cooperation 
have been fully complied with to date. 
Terminal facilities. Docks, storage facilities, and 
handling equipment have been provided as required at 
most loading and unloading points along the waterway. 
These include facilities for handling petroleum and petroleum 
products, coal, ores, sand and gravel, pulpwood, 
manufactures, and various other commodities. 
While most terminal facilities are privately owned, 
many are available for use by the general public. Facilities 
are considered adequate for existing commerce. 
(See Table 10-C for existing locks and dams.) 
Operations and results during fiscal year. 
New work: Engineering and design for replacement 
span on Franklin Ferry Bridge across navigation channel 
cost $30,776. Recreation facilities cost $165,047 at 
Demopolis Lock and Dam. 
Maintenance: Contractors' dredges removed 
1,585,950 cubic yards of material and 1,693 cubic yards 
of rock from the river system at a cost of $5,946,388. 
Other general charges for the overall river project 
totaled $3,244,842. 
Other maintenance costs for the system include: 
Jackson Lock and Dam, $441,671; Demopolis Lock 
and Dam, $314,444; Warrior Lock and Dam, $658,321; 
Oliver Lock and Dam, $680,564; Bankhead Lock and 
Dam, $1,091,061; Holt Lock and Dam, $382,025; and 
reservoir operation, $1,103,303. 
Condition at end of fiscal year. Work on the project, 
commenced in 1887, was essentially completed in 1915. 
Since then three of the original locks and dams (10, 11 
and 12) were replaced by William Bacon Oliver (Tuscaloosa) 
Lock and Dam which was opened to navigation 
in August 1939; four original locks and dams (4,5,6 and 
7) were replaced by Demopolis Lock and Dam which 
was opened to navigation in August 1954; two original 
locks and dams (8 and 9) were replaced by Warrior Lock 
and Dam which was opened to navigation in October 
1957; three original locks and dams (1, 2 and 3) were 
replaced by Coffeeville Lock and Dam which was 
opened to navigation in August 1960; and four original 
locks and dams (13, 14, 15, and 16) were replaced by 
Holt Lock and Dam which was opened to navigation in 
June 1966. Rehabilitation of the spillway at John Hollis 
Bankhead Lock and Dam commenced in 1966, and 
physically completed 6 February 1970. Replacement of 
the double lift lock with a single lift lock at John Hollis 
Bankhead Lock and Dam commenced in April 1970 
and was completed in 1980. The cost to September 30, 
1983 for replacement of the lock was $49,828,429. The 
power plant at John Hollis Bankhead Lock and Dam 
was built and is operated by the Alabama Power Co. 
Total Federal costs under existing project as of September 
30, 1983 were $153,124,403 for new work and 
$138,063,214 for maintenance, a total of $291,187,617. 
7. BON SECOUR RIVER, AL 
Location. Rises 2 miles south of Foley, Ala., and 
flows southerly about 8 miles, emptying into Bon 
Secour Bay, an arm of Mobile Bay in southwest 
Alabama. 
Existing project. A 10- by 80-foot channel from Gulf 
Intracoastal Waterway through Bon Secour Bay to 
mouth of Bon Secour River and extending up river to 
vicinity of Swifts Landing, thence 6 by 80 feet up river to 
a point about 600 feet above Oak Landing with two 
turning and maneuvering areas 150 feet wide and 1,100 
to 1,200 feet long opposite Swifts Landing and ice loading 
dock. Plane of reference is mean low water. Overall 
length of improvement is about 4.7 miles. Mean tidal 
range is about 1.5 feet and extreme, except during 
storms, is 3.5 feet. Existing project was authorized by 
Chief of Engineers, May 16, 1963, under authority in 
Section 187, River and Harbor Act of 1960. 
Local cooperation. Fully complied with. 
Terminal facilities. A number of pile-and-timber 
marginal, wharves used by seafood industry and a 
marine ways located along existing project. These, 
together with numerous privately owned piers, are considered 
adequate for existing commerce. 
Operations and results during fiscal year. Maintenance: 
Operation studies, surveys and, supervision and 
administration cost $17,891. 
Condition at end of fiscal year. Project was commenced 
in July and completed in October 1964. Total 
Federal costs under existing project as of September 
10-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
30, 1983 were $118,615 for new work and $131,954 for 
maintenance, a total of $250,569. Contributed funds for 
new work amounted to $9,700. 
8. CADET BAYOU, MS 
Location. Cadet Bayou (also known as Bayou Caddy) 
is a small tidal stream in southwest Hancock County, 
Mississippi, which flows easterly through marshland 
and empties into Mississippi Sound about 10 miles 
southwest of Bay St. Louis, Mississippi. (See Coast and 
Geodetic Survey Chart I11371). 
Existing project. The existing project provides for an 
8-by 100-foot channel from the 8-foot depth in Mississippi 
Sound for about 7,800 feet to the mouth of Cadet 
Bayou, thence an 8- by 80-foot channel extending 700 
feet into the bayou to a 6- by 60-foot turning basin (in 
addition to the 80-foot channel width) 130 feet long, 
thence a 6- by 60-foot channel continuing upstream for 
8,800 feet to a second turning basin 110 feet wide (in 
addition to the 60-foot channel width) and 100 feet long 
thence a 6- by 60-foot channel approximately 870 feet to 
the end of the project. The total length of improved 
channel is about 18,400 feet. Plane of reference is mean 
low water. Mean range of tide is about 1.6 feet in the 
vicinity of Cadet Bayou. Extreme range, except during 
storms is about 3.5 feet. (See Table 10-B for authorizing 
legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Several privately-owned pile-andtimber 
wharves, a boatyard, marine ways near the 
mouth, and several natural landings are located along 
the bayou. A fishing camp at mile 2 provides necessary 
facilities for recreational boating needs, including about 
250 feet of marginal wharf. Local interests will be 
required to provide, maintain, and operate a public 
wharf for commercial boating interests near the mouth 
of the bayou, and another for recreational boating 
interests in the upper reaches. 
Operations and results during fiscal year. Maintenance: 
Surveys and miscellaneous costs amounted to 
$32,145. 
Condition at end of fiscal year. The existing project 
was commenced and completed in December 1970. 
Total Federal costs under existing project as of September 
30, 1983 were $87,921 for new work and 
$704,424 for maintenance, a total of $792,345. Contributed 
funds for new work amount to $31,000. 
9. DAUPHIN ISLAND BAY, AL 
Location. The project is located between Dauphin 
and Little Dauphin Island on the west side of the 
entrance to Mobile Bay, about 30 miles south of 
Mobile, Alabama and 55 miles west of Pensacola, Florida. 
(See Coast and Geodetic Survey Chart 11376.) 
Existing project. The authorized project provides for: 
(a) A channel seven feet deep and 150 feet wide from 
Mobile Bay to a anchorage basin of the same depth, and 
about seven acres in area, in the marsh just north of Fort 
Gaines on Dauphin Island; a channel four feet deep and 
40 feet wide from the anchorage basin to Dauphin 
Island Bay; and a jetty and revetment to protect the 
entrance channel; and (b) an anchorage basin seven feet 
deep and 500 feet square at Dauphin Island Village, 
with an entrance channel of like depth, 100 feet wide and 
about 8,300 feet long, extending to the 7-foot hydrographic 
contour in Mississippi Sound. Mean tidal range is 
1.1 feet, and extreme, except during storms is about four 
feet. Plane of reference is mean low water. (See Table 
10-B for authorizing legislation.) 
Local cooperation. Requirements of local cooperation 
have been fully complied with to date. 
Terminal facilities. Several privately-owned wharves 
for handling seafood, a public dock and mooring slip, 
and a pier for recreational craft are located on the 
village basin. A marina, public launching ramp, and a 
number of private piers are located on the bay. Facilities 
are considered adequate for existing commerce. 
Operations and results during fiscal year. New Work: 
None. 
Maintenance: Hired labor costs included $66,153 for 
operation studies, engineering, design, supervision and 
administration and other costs. 
Condition at end of fiscal year. The project was completed 
in July 1959. Total Federal costs under existing 
project as of September 30, 1983 were $292,864 for new 
work and $1,015,543 for maintenance, a total of 
$1,308,407. 
10. DOG AND FOWL RIVERS, AL 
Location. Dog and Fowl Rivers are primarily tidal 
streams emptying into the west side of Mobile Bay, 8.5 
and 17 miles, respectively, south of central Mobile. (See 
Coast and Geodetic Survey Chart 11376). 
Existing project. The Dog River project provides for 
an 8-foot deep by 150-foot wide channel from about 
3,000 feet east of the Mobile Bay ship channel to and up 
Dog River, a total distance of 26,200 feet, thence six feet 
by 100 feet for 12,300 feet to a point about 2,400 feet 
above the mouth of Halls Mill Creek, and a 6-foot by 
100-foot spur channel from the main channel to the 
mouths of Perch and Halls Mill Creeks. Overall length 
of the proposed improvement is about 7.8 miles. This 
portion of the project has not been constructed due to 
local interest's inability to comply with cost-sharing 
responsibilities. 
The Fowl River project provides for a channel eight 
feet deep and 100 feet wide from Mobile Bay into and up 
Fowl River to deep water about 6,700 feet above its 
mouth. Total length of the channel is about 2.6 miles. 
Plane of reference is mean low water. Mean range of 
tide is about 1.5 feet in Dog River. Extreme range 
during storms is about 3.6 feet. This segment of the 
project was completed in November, 1973. (See Table 
10-6

MOBILE, ALABAMA DISTRICT 
10-B for authorizing legislation.) 
Local cooperation. Fully complied with for the Fowl 
River portion. 
Terminal facilities. Existing facilities consist of a 
boatyard for fabricating steel vessel hulls, nine marinas, 
four marine ways, a yacht basin on Dog River; two 
marinas on Fowl River, and numerous timber piers and 
docks on both rivers. Facilities are considered adequate 
for existing commerce. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance costs amounted 
to $16,930. 
Condition at end of fiscal year. The existing project 
was commenced in August 1973 and completed in 
November 1973. Total Federal costs on the existing 
project as of September 30, 1983 were $880,437; $190,695 
for new work and $689,742 for maintenance. Contributed 
funds for new work amounted to $114,100. 
11. EAST PASS CHANNEL FROM 
GULF OF MEXICO INTO 
CHOCTAWHATCHEE BAY, FL 
Location. East Pass Channel is located in the entrance 
from the Gulf into Choctawhatchee Bay at eastern end 
of Santa Rosa Island, 48 miles east of the entrance into 
Pensacola Bay and 49 miles west of the new entrance to 
St. Andrews Bay. (See Coast and Geodetic Survey 
Chart 11388.) 
Previous project. For details see page 672 of Annual 
Report for 1937. 
Existing project. The authorized project provides for 
a 12-foot by 180-foot channel from the Gulf of Mexico 
into Choctawhatchee Bay, and a 6-foot by 100-foot 
channel from East Pass Channel into Old Pass Lagoon. 
The project consists also of two converging jetties 
spaced 1,000 feet apart at the seaward end. The west 
jetty is provided with a low weir section 1,000 feet long 
to permit passage of littoral drift into a dredged deposition 
basin 500 feet by 1,500 feet located between the west 
jetty and the navigation channel. Mean range of tide is 
1.3 feet; extreme range, except during storms, is 2.5 feet. 
Plane of reference is mean low water. (See Table 10-B 
for authorizing legislation.) 
Local cooperation. Responsibilities of local cooperation 
have been complied with to date. 
Terminal facilities. Small privately-owned pile-andtimber 
piers used in connection with the fishing industry 
in this locality are considered adequate for existing 
commerce. 
Operations and results during fiscal year. Maintenance: 
Contractors dredges operating in the entrance 
channel to Old Pass Lagoon and East Pass removed 
237,257 cubic yards of material at a cost of $399,832. 
Hired labor costs for condition studies, water control 
management, contract administration, engineering, design, 
supervision, administration and other costs amounted 
to $206,932. 
Condition at end of fiscal year. Construction of the 
1965 modification was commenced October 1967 and 
completed January 1969. Total Federal costs under 
existing project as of September 30, 1983 were $916,715 
for new work and $4,962,652 for maintenance, a total of 
$5,879,367. Contributed funds for new work from local 
interests amount to $398,000. 
12. GULF INTRACOASTAL 
WATERWAY BETWEEN 
APALACHEE BAY, FL 
AND MEXICAN BORDER 
(MOBILE DISTRICT) 
Location. The project extends westward from Apalachee 
Bay, Florida, along the Gulf coast to the Rigolets, 
Louisiana, via a series of coastal lakes, bays, sounds, 
and land cuts. (For further details see Annual Report 
for 1962.) 
Previous project. For details see page 906, Annual 
Report for 1930. 
Existing project. The authorized project provides for 
a waterway 12 feet deep and 125 feet wide at mean low 
water from Apalachee Bay, Florida, to Mobile Bay, 
Alabama, and 12 feet deep and 150 feet wide from 
Mobile Bay, Alabama, to Rigolets, Louisiana (Lake 
Borgne Light No. 29), and for a tributary channel (Gulf 
County Canal), 12 feet deep, 125 feet wide and about six 
miles long connecting Intracoastal Waterway at White 
City, Florida, with St. Joseph Bay. The waterway 
between the 12-foot depth contours in Apalachee Bay 
and Lake Borgne Light No. 29 at the Rigolets is 379 
miles long. (See Table 10-B for authorizing legislation.) 
Local cooperation. Responsibilities of local cooperation 
have been fully complied with for the work authorized 
prior to 1966. For modification of the Gulf County 
Canal which was authorized by the 1966 River and 
Harbor Act, local interests must provide without cost to 
the United States all lands, easements, and rights-ofway 
required in connection with disposal of spoil, or the 
costs of such retaining works; hold and save the United 
States free from all damages due to construction and 
maintenance of the project including damages to 
wharves, piers, bridges, and other structures; provide 
and maintain at local expense adequate terminal and 
transfer facilities open to all on equal terms; provide and 
maintain without cost to the United States depths in 
berthing areas commensurate with depths provided in 
related project area; and accomplish without cost to the 
United States such alterations as required in sewer, 
water supply, drainage, and other facilities as well as 
their maintenance. 
Terminal facilities. Facilities are available for public 
use at Carrabelle, Apalachicola, Panama City, and Pensacola, 
Florida; Mobile and Bayou LaBatre, Alabama; 
and Pascagoula, Biloxi, Gulfport, Pass Christian, and 
Bay St. Louis, Mississippi. Facilities are considered 
10-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
adequate for existing commerce. 
Operations and results during fiscal year. 
Maintenance: 
Carrabelle-Apalachicola Bay section: Studies to determine 
impacts of dredged material cost $326,252. 
Apalachicola Bay - St. Andrew Bay section: Hired 
labor costs included $40,045 for condition studies and 
$18,081 for miscellaneous work. 
St. Andrew Bay - Choctawhatchee Bay section: Hired 
labor cost for the year included: bank stabilization, 
$148,789; permanent operating equipment, $1,328; 
canals and channels, $64,447; and $26,920 for miscellaneous 
work. 
Choctawhatchee Bay - Pensacola Bay section: Costs 
for the year include condition and operation studies and 
miscellaneous work of $17,401. 
Pensacola Bay - Mobile Bay section: Costs for the 
year included condition and operation studies, $112,244; 
channels and canals, $114,921; and miscellaneous, 
$16,785. 
Mobile Bay - Rigolets section: Hired labor costs 
included $52,303 for condition and operation studies 
and $117,529 for channels and canals. In addition, 
compliance inspections cost $230,874; direct charges to 
Mobile Area Office cost $108,005; and direct charges to 
Panama City Area Office were $5,517. 
Condition at end of fiscal year. The existing project is 
complete except for the portion between Apalachicola 
Bay and St. Marks, Florida, which is deferred for restudy. 
Modification of the Gulf County Canal to provide 
foot by 125-foot channel was commenced July 1968 
a 12-and completed June 1969. Total costs of the existing 
project to September 30, 1983 were $38,361,497, of 
which $6,434,694 was for new work and $31,926,803 for 
maintenance. 
13. GULFPORT HARBOR, MS 
Location. The project is located on Mississippi 
Sound in southeastern Mississippi, about 44 and 90 
miles by water west of Pascagoula Harbor, Mississippi, 
and Mobile Harbor, Alabama, respectively, and 78 
miles east of New Orleans (via Gulf Intracoastal Waterway). 
(See Coast and Geodetic Survey Chart 
11373.) 
Previous project. For details see page 747, Annual 
Report for 1938, and page 995, Annual Report for 1948. 
Existing project. The authorized project provides for: 
(a) A channel 32 feet deep, 300 feet wide, and about 
eight miles long across Ship Island Bar, a channel 30 feet 
deep, 220 feet wide, and about 11 miles long through 
Mississippi Sound, and an anchorage basin at Gulfport 
30 feet deep, 1,320 feet wide, and 2,640 feet long; and (b) 
maintenance of the existing commercial smallboat harbor 
about 26 acres in area, and a straight-approach 
channel, 100 feet wide and about 4,300 feet long, from 
deep water in Mississippi Sound to a small-boat basin, 
all at a depth of eight feet. Under ordinary conditions 
mean tidal range is about 1.75 feet, and extreme range, 
except during storms, is about 3.5 feet. Plane of reference 
is mean low water. (See Table 10-B for authorizing 
legislation.) 
Local cooperation. Conditions of local cooperation 
have been fully complied with to date. 
Terminal facilities. Existing modern rail-connected 
terminal facilities at this port are considered adequate 
for existing commerce. (See Port Series 19, revised in 
1979.) 
Operations and results during fiscal year. Maintenance: 
The contractors' pipeline dredge, Mike Hooks 
removed a total of 2,530,004 cubic yards of material 
from the harbor channel at a cost of $841,353. Hired 
labor included condition and operation studies, and 
engineering, design, supervision and administration, all 
at a cost of $141,176. 
Condition at end of fiscal year. The main harbor was 
commenced 1932 and completed April 1950. Maintenance 
for small boat harbor and approach channel, 
constructed by local interests in 1950, was authorized by 
1958 River and Harbor Act. Total Federal costs under 
existing project as of September 30, 1983 were $635,758 
for new work and $23,544,766 for maintenance, a total 
of $24,180,524. 
14. MOBILE HARBOR, AL 
Location. The project is located along the lower five 
miles of Mobile River, in southwestern Alabama, 91 
miles by water west of Pensacola Harbor, Florida, 90 
miles east of Gulfport Harbor, Mississippi, and 144 
miles by water northeast of mouth of Mississippi River. 
(See Coast and Geodetic Survey Chart 11376.) 
Previous project. For details see page 503, Annual 
Report for 1963. 
Existing project. The authorized project provides for: 
(a) A 42-foot by 600-foot channel about 1.5 miles long 
across Mobile Bar; (b) a 40-foot by 400-foot channel in 
Mobile Bay to mouth of Mobile River; (c) a 40-foot 
channel in Mobile River to highway bridge, varying 
from 500 to 775 feet wide; (d) a 25-foot channel from 
highway bridge to and up Chickasaw Creek to a point 
400 feet south of mouth of Shell Bayou, widths being 
500 feet in Mobile River and 250 feet in Chickasaw 
Creek; (e) a turning basin 40 feet deep, 2,500 feet long, 
and 800 to 1,000 feet wide, opposite Alabama State 
Docks; (f) a turning basin 40 feet deep, 1000 feet wide, 
and 1,600 feet long opposite Magazine Point; (g) a 
27-foot by 150-foot channel from Mobile Bay Channel 
along Arlington pier to a turning basin 800 feet long and 
600 feet wide opposite Brookley Air Force Base ocean 
terminal, and continuing thence to a turning basin 250 
feet wide and 800 feet long in Garrows Bend, thence a 
22-foot by 150-foot channel to the causeway linking 
McDuffie Island to the mainland; (h) a channel 40 feet 
deep and 400 feet wide from the main ship channel in 
10-8

MOBILE, ALABAMA DISTRICT 
Mobile Bay and extending northwesterly for about 5.3 
miles to the shore of Mobile Bay, including an anchorage 
and turning basin near the shoreline, thence a land 
cut 40 feet deep, 300 feet wide and 1.9 miles long to and 
including a 42 acre trapezoid turning basin 40 feet deep, 
and a barge channel 12-by 100-feet, extending 6500 feet 
and terminating in a 300-by 300-foot turning basin; and 
(i) maintenance of Three Mile Creek by snagging, from 
its intersection with Industrial Canal to Mobile River. 
The project provides also for an anchorage area 32 feet 
deep, 100 feet wide, and 2,000 feet long opposite site 
formerly occupied by the U. S. Quarantine Station at 
McDuffie (Sand) Island. Prior to widening the Mobile 
Bay Channel as authorized in 1954, the Quarantine 
Station anchorage area was maintained to a project 
width of 200 feet. Construction by local interests of a 
solid-fill causeway across Garrows Bend Channel between 
McDuffie Island and the mainland is also provided 
for under existing project. Total length of the bay 
and river channels is about 41.7 miles. Plane of reference 
is mean low water. Under ordinary conditions 
mean tidal range at the lower end of the improvement is 
1.2 feet and at the upper end 1.5 feet. Extreme tidal 
range is 3.4 feet at the lower end and 3.6 feet at the upper 
end. (See Table 10-B for authorizing legislation.) 
Local cooperation. Requirements of local cooperation 
have been fully complied with to date. 
Terminal facilities. Modern rail-connected terminal 
facilities at this port are considered adequate for existing 
commerce. (See Port Series No. 18, revised in 1979.) 
Operations and results during fiscal year. New work: 
Continuing work on Theodore Channel cost $723,834. 
Maintenance: Contract dredging removed 391,910 
cubic yards of material from Arlington Channel, 219,665 
cubic yards of material from Outer Bar Channel and 
2,479,778 cubic yards of material from Mobile Bay and 
Theodore Channel, all at a cost of $2,511,095. Hired 
labor cost for surveys, engineering, design, supervision 
and administration and miscellaneous work amount to 
$430,687. 
Condition at end of fiscal year. The existing project 
was commenced in 1931 and completed in July 1965 
except for the Theodore Channel portion, presently 
under construction. For details see Annual Report for 
1965. Total Federal costs under existing project as of 
September 30, 1983 were $61,367,528 for new work and 
$59,582,811 for maintenance, a total of $120,950,339. 
Contributed funds expended for new work amounted to 
$3,447,568. 
15. PANAMA CITY HARBOR, FL 
Location. The project is located on the northwest 
coast of Florida, 102 miles east of entrance to Pensacola 
Harbor. (See Coast and Geodetic Survey Chart 11389.) 
Previous project. For details see page 710, Annual 
Report for 1938. 
Existing project. The authorized project (as modifled) 
provides for a channel about 3.7 miles long extending 
from deep water in the bay (intersection of Bay 
Harbor and Dyers Point Channel) across Lands End to 
the Gulf of Mexico, 300 feet wide and 40 feet deep in the 
bay and across Lands End, and 450 feet wide, 42 feet 
deep and about 1.1 miles long in the approach channel 
in the Gulf, protected by two jetties, each about 700 feet 
long; branch channels 38 feet deep and 300 feet wide, 
leading from the inner end of the main entrance channel 
westward to the Port Authority terminal at Dyers Point 
and eastward to the Bay Harbor terminal, about 3.4 and 
3.6 miles in length, respectively; turning and maneuvering 
areas comprising about 55 acres opposite Dyers 
Point, and 42 acres opposite Bay Harbor, both at a 
depth of 38 feet; and an anchoring and loading basin for 
LASH type intermodal carriers, 40 feet deep and containing 
about 177 acres in St. Andrew Bay near the inner 
end of the main entrance channel; a channel in Watson 
Bayou, 100 feet wide and 10 feet deep from that depth in 
St. Andrew Bay to the highway bridge, about 1.75 miles; 
channel 100 feet wide and 8 feet deep in Grand Lagoon 
to a point about 2,400 feet east of State Highway 392 
Bridge, with branches to serve terminal facilities. The 
east and west jetties have been reworked and are presently 
about 2,075 and 2,896 feet long, respectively. 
Mean tidal range 1.3 feet and extreme 3.0 feet. (See 
Table 10-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Available terminal facilities are 
considered adequate for existing commerce. (See Port 
Series No. 19, revised in 1979.) 
Operations and results during fiscal year. New work: 
None. 
Maintenance: Contract dredging removed 108,654 
cubic yards of material from the entrance channel at a 
cost of $243,796. Condition and operation studies; 
supervision and administration; and, other miscellaneous 
costs amounted to $100,033. 
Condition at end of fiscal year. The existing project 
(prior to modifications) was completed in November 
1949. Repairs to jetties were commenced in June 1961 
and completed October 1968. Modifications to the project 
at Grand Lagoon were completed in January 1972. 
Total Federal costs under existing project as of September 
30, 1983 were $1,434,485 for new work and 
$4,759,368 for maintenance, a total of $6,193,853. Contributed 
funds expended for new work amount to 
$80,000. 
16. PASCAGOULA HARBOR, MS 
Location. The project is located along lower 6.8 miles 
of Pascagoula River, the lower six miles of Dog River, 
and in Bayou Casotte (about four miles east of the 
mouth of Pascagoula River), in southeastern Mississippi, 
about 61 miles by water west of Mobile Harbor, 
Alabama, and about 44 miles by water east of Gulfport 
Harbor, Mississippi. (See Coast and Geodetic Survey 
Chart 11373.) 
Previous project. For details see page 741, Annual 
10-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Report for 1938. 
Existing project. The authorized project provides for 
(a) An entrance channel 40 feet deep and 350 feet wide 
from the Gulf of Mexico through Horn Island Pass, 
including an impounding area for littoral drift, 40 feet 
deep, 200 feet wide, and about 1,500 feet long adjacent 
to the channel at the west end of Petit Bois Island; (b) a 
channel 38 feet deep and 350 feet wide in Mississippi 
Sound and Pascagoula River to the railroad bridge at 
Pascagoula, including a turning basin 2,000 feet long 
and 950 feet wide (including channel area) on the west 
side of the river below the railroad bridge; (c) a channel 
38 feet deep and 225 feet wide from the ship channel in 
Mississippi Sound to the mouth of Bayou Casotte, 
thence 38 feet deep and 300 feet wide for about one mile 
to a turning basin 38 feet deep, 1,000 feet wide, and 
1,750 feet long; (d) a 22-foot deep by 150-foot wide 
channel up Pascagoula River from the railroad bridge 
to the mouth of Dog River, thence up Dog River to 
Highway 63 bridge; and (e) a 12-foot by 125-foot channel 
from the highway bridge, via Robertson and Bounds 
Lakes, to mile 6 on Dog River. Under ordinary conditions 
mean tidal range is 1.75 feet, and extreme range is 
3.75 feet. Plane of reference is mean low water. (See 
Table 10-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Modern rail-connected terminal 
facilities at this port are considered adequate for existing 
commerce. (See Port Series No. 19, revised in 1979.) 
Operations and results during fiscal year. Maintenance: 
Contract dredging removed 1,740,866 cubic 
yards of material from the channel at a cost of 
$1,624,874. Hired labor costs for surveys, supervision 
and administration and other miscellaneous work 
amounted to $361,942. 
Condition at end of fiscal year. The existing project 
was completed in August 1965. Total Federal costs of 
existing project to September 30, 1983 were $5,668,543 
for new work and $25,019,614 for maintenance, a total 
of $30,688,157. Contributed funds expended for maintenance 
amounted to $449,115. 
17. PENSACOLA HARBOR, FL 
Location. The project is located in a landlocked bay 
on the coast of northwest Florida about 50 miles east of 
the entrance to Mobile Bay. (See Coast and Geodetic 
Survey Charts 490 and 11382.) 
Previous project. For details see Annual Report for 
1938. 
Existing project. The authorized project provides for: 
(a) A 35-foot by 500-foot entrance channel about five 
miles long, from the Gulf of Mexico to lower Pensacola 
Bay; (b) a 33-foot by 300-foot bay channel; (c) two 
33-foot by 300-foot parallel approach channels to opposite 
ends of the inner-harbor channel; (d) an innerharbor 
channel 500 feet wide, 33 feet deep, and 3,950 
feet long; (e) a 30-foot by 250-foot approach channel to 
the pierhead line south of Muscogee wharf; and (f) a 
15-foot by 100-foot entrance channel into Bayou Chico, 
thence a channel 14 feet deep, 75 feet wide, and about 
4,400 feet long to a turning basin 14 feet deep and 500 
feet square. Mean range of tide throughout the harbor is 
about 1.1 feet near the entrance and about 1.6 feet at the 
head of bay. Extreme tidal range, except during storms, 
is about three feet. Plane of reference is mean low water. 
Modification of the Bayou Chico project to provide for 
enlarging the entrance channel to 21 by 100 feet, the 
bayou channel to 20 feet by 100 feet, and deepening the 
turning basin to 20 feet has been deferred for restudy. 
(See Table 10-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Modern rail-connected terminal 
facilities at this port are considered adequate for existing 
commerce. (See Port Series No. 19, revised in 1979.) 
Operations and results during fiscal year. Maintenance: 
Surveys and ordinary maintenance amounted to 
$42,145. 
Condition at end of fiscal year. New work is completed 
except those features which are deferred for restudy. 
The modification authorized in 1962 was commenced 
in March and completed in May 1965. Total 
Federal costs of the existing project to September 30, 
1983 were $875,005 for new work and $3,915,803 for 
maintenance, a total of $4,790,808. 
18. PERDIDO PASS CHANNEL, AL 
Location. The project is located about midway 
between Pensacola, Florida and Mobile, Alabama. (See 
Coast and Geodetic Chart 11378.) 
Existing project. The existing project provides for a 
channel 12 feet deep and 150 feet wide for about 1,300 
feet from the Gulf of Mexico into the inlet, thence nine 
feet deep and 100 feet wide for about 2,200 feet to the 
highway bridge, where the channel branches into two 
arms, each having dimensions of 9 by 100 feet, one of 
which extends about 3,400 feet into Terry Cove and the 
other about 3,200 feet into the southern arm of Perdido 
Bay. The project also provides for two jetties spaced 600 
feet apart at the seaward end. The east jetty has a low 
weir section, 1,000 feet long to permit passage of littoral 
drift into a dredged deposition basin 800 feet by 1,200 
feet located between the east jetty and the navigation 
channel. Mean tidal range is 1.1 feet and extreme is 2.8 
feet. (See Table 10-B for authorizing legislation.) 
Local cooperation. Requirements of local cooperation 
have been fully complied with to date. 
Terminal facilities. Six marinas, numerous timber 
piers, docks, and several launching ramps are available. 
These facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal year. Maintenance: 
The contractors dredges operating north of the 
highway, removed 190,649 cubic yards of material at a 
cost of $421,680. Cost of surveys, supervision and ad- 
10-10

MOBILE, ALABAMA DISTRICT 
ministration and miscellaneous work amounted to 
$62,660. 
Condition at end of fiscal year. The existing project 
was commenced in May 1968 and completed in March 
1969. Total Federal costs of the existing project to September 
30, 1983 were $629,860 for new work and 
$4,207,533 for maintenance, a total of $4,837,393. Contributions 
from local interest amount to $510,000 for 
new work and $10,325 for maintenance. 
19. PORT ST. JOE, FL 
Location. The project is located on the northwest 
coast of Florida, 115 miles east of Pensacola Harbor. 
(See U. S. Coast and Geodetic Survey Chart No. 11389.) 
Existing project. The authorized project provides for: 
(a) An entrance channel 37 feet deep, 500 feet wide at its 
outer end and diminishing progressively in width to 400 
feet at the first bend, a distance of 3.6 miles, thence 
continuing at a depth of 37 feet and a width of 400 feet, 
through the second and third bend for 3.3 miles, thence 
continuing at a depth of 35 feet and a width of 300 feet 
2.4 miles to a point in St. Joseph Bay where the entrance 
channel joins the north channel, a total overall distance 
of 9.3 miles, thence continuing in the north channel at a 
depth of 35 feet and a width of 300 feet to the north end 
of the turning basin at Port St. Joe, a distance of about 
4.7 miles; (b) a turning basin 32 feet deep, 1,000 feet 
wide, and 2,000 feet long, and a harbor channel therein 
35 feet deep, 250 feet wide, and 2,000 feet long, adjacent 
to the waterfront at Port St. Joe; and (c) a channel 27 
feet deep, 200 feet wide and about 1 mile long leading 
from the south end of the turning basin to deep water in 
St. Joseph Bay. Average tidal variation is 1.4 feet and 
extreme, except during storms, is about 4 feet. (See 
Table 10-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Rail and highway-connected terminal 
facilities available at this port are considered 
adequate for existing commerce. (See Port Series No. 
19, revised in 1979.) 
Operations and results during fiscal year. Maintenance: 
Ordinary maintenance and care amounted to 
$20,501. 
Condition at end of fiscal year. The project was completed 
in July 1962. Total Federal costs for the project as 
of September 30, 1983 were $1,960,862 for new work 
and $2,194,196 for maintenance, a total of $4,155,058. 
Contributed funds for new work amount to $20,000. 
20. REMOVING WATER HYACINTHS, 
MOBILE DISTRICT 
Location. The project is for all streams tributary to 
the Gulf Coast in Mobile District. 
Existing project. The authorized project provides for 
extermination or removal of plants from navigable 
waters of Florida, Alabama, Mississippi, Louisiana, 
and Texas, so far as they are or may become an obstruction 
to commerce, by any mechanical, chemical, or 
other means whatsoever; for construction and operation 
of boats equipped with suitable machinery for such 
removal, and construction and operation of log booms 
to prevent plants drifting from one stream to another. 
(See Table 10-B for authorizing legislation.) 
Local cooperation. None required. 
Operations and results during fiscal year. None. 
Condition at end of fiscal year. The existing project, 
which is for maintenance, was commenced about 1899, 
and work has been carried on since that time. Total 
Federal costs for the project through September 30, 
1983 amount to $1,099,266. 
21. WATERWAY CONNECTING 
TOMBIGBEE AND TENNESSEE 
RIVERS, AL AND MS 
Location. The waterway extends from mile 215 in 
Pickwick poolon the Tennessee River, southerly through 
northeastern Mississippi and western Alabama, a total 
of 234 miles, to the confluence of the Black Warrior and 
Tombigbee Rivers at Demopolis, Alabama. 
Location. For details see Annual Report for 1953. 
Existing project. The authorized project provides for 
a waterway 234 miles long, connecting the Tennessee 
and Tombigbee Rivers via the East Fork of Tombigbee 
River and Mackeys and Yellow Creeks. The plan of 
improvement consists of three sections. (1) the river 
section, a 9-foot by 300-foot channel for 149 miles 
between Demopolis and Amory, Mississippi; (2) the 
lateral canal section, 12 feet by 300 feet for 46 miles from 
Amory to Bay Springs; and (3) the divide section, a 
12-foot by 300-foot channel (except in the 27 mile-long 
divide cut in which the bottom width would be 280 feet) 
for 39 miles from Bay Springs through the dividing 
ridge to the Tennessee River; the total lift of 341 feet to 
be accomplished by 10 locks. Estimated (1983) Federal 
cost for new work is $1,839,000,000, including $9,600,000 
for work by the U.S. Coast Guard, and $9,400,000 for 
National Park Service; plus, $155,000,000 non-Federal 
cost for relocations. (See Table 10-B for authorizing 
legislation.) 
Local cooperation. Local interests must make and 
maintain alterations in highways and highway bridges 
and in sewer, water-supply, and drainage facilities and 
provide and maintain suitable and adequate river and 
canal terminals. Officials of the State of Mississippi 
were notified of these requirements on December 13, 
1949, and officials of the State of Alabama were notified 
on December 20, 1949. Legislation enabling boards of 
supervisors of the various counties concerned to enter 
into agreements with the United States relative to navigation 
projects was adopted by the State of Mississippi 
in 1950. A compact between the States of Alabama, 
Mississippi, Tennessee, Kentucky, and Florida has been 
formed for the purpose of promoting the project. The 
name of this organization is the Tennessee-Tombigbee 
10-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Waterway Development Authority. 
During its 1962 session the Mississippi Legislature 
authorized the formation of the Tombigbee River Valley 
Water Management District. The District was 
organized in accordance with the enabling legislation 
and is empowered to fulfill the requirements of local 
cooperation for the portion of the project in Mississippi. 
A satisfactory resolution has been furnished. During its 
1967 session the Alabama Legislature authorized formation 
of a public corporation to be named the Tombigbee 
Valley Development Authority for the purpose 
of further development of the Tombigbee River and 
tributary streams. The organization was formed in 
accordance with the enabling legislation and in a referendum 
held 5 December 1967 the voters of Alabama 
authorized a bond issue not to exceed $10,000,000 to 
finance participation in this project and the Tombigbee 
River and Tributaries project. A satisfactory resolution 
has been furnished. 
Terminal facilities. None. 
Operations and results during fiscal year. New work: 
Total cost of new work during the fiscal year was 
$103,645,625 of which $1,407,871 was for work on 
Demopolis Lake; $2,523,061 for Gainesville Lock and 
Dam; $7,252,514 for Aliceville Lock and Dam; 
$18,913,722 for Columbus Lock and Dam; $8,539,735 
for Aberdeen Lock and Dam. Canal section cost included: 
Lock A, $8,275,606; Lock B, $8,188,309; Lock 
C, $5,275,858; Lock D, $21,688,189; Lock E, 
$18,359,554. Engineering, design, supervision, administration 
and other costs associated with the overall project 
amounted to $3,221,206. Maintenance: Cost for 
operation of the completed portion of the project during 
the year amounted to $5,430,959, which included general 
charges of $2,507,964; Gainesville Lock and Dam, 
$249,558; Aliceville Lock and Dam, $251,706; Columbus 
Lock and Dam, $256,450; Aberdeen Lock and 
Dam, $96,167; Lock A, $87,115; Lock B, $46,755; Lock 
C, $911; Bay Springs, $32,939; lake charges of$1,715,977 
and navigation charges of $185,417. Recreation attendance 
for CY 1982 totaled 840,000 user days. 
Condition at end of fiscal year. Total Federal costs 
under the existing project as of September 30, 1983 were 
$817,271,190 for new work, and $15,274,554 for maintenance 
for a total of $832,545,744. Construction formally 
began December 12, 1972 and overall project is 
about 82 percent complete, including work being performed 
by Nashville District, which costs are not 
reported by Mobile District. 
22. RECONNAISSANCE AND 
CONDITION SURVEYS 
(See Table 10-D.) 
23. OTHER AUTHORIZED 
NAVIGATION PROJECTS 
(See Table 10-E.) 
24. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation activities pursuant to Section 107, Public 
Law 86-645, as amended (Preauthorization). Studies 
conducted under this authority amounted to $229,834. 
(See Table 10-F.) 
Studies conducted under Section 103,1962 River and 
Harbor Act, as amended, amounted to $14,473. (See 
Table 10-F.) 
Studies conducted under Section 54, Shoreline Erosion 
Control Evaluation and Demonstration Act of 
1974, Public Law 93-251, amounted to $30. Studies 
conducted under Section 55 WRD Act of 1974 Public 
Law 93-251, for providing technical and engineering 
assistance to non-Federal public interests for developing 
methods for the prevention of shore and stream 
bank erosion control cost $5,556. 
Emergency channel work for navigation under authority 
of Section 3, 1945 River and Harbor Act, as 
amended, amounted to $20,031. (See Table 10-F.) 
Beach Erosion Control 
25. AUTHORIZED BEACH EROSION 
CONTROL PROJECT 
(See Table 10-G.) 
26. DEAUTHORIZED PROJECTS 
Projects deauthorized under Section 12, Public Law 
251, 93rd Congress, as amended. (See Table 10-H) 
Flood Control 
27. OKATIBBEE LAKE, MS 
Location. The project is located on Okatibbee Creek 
37.7 miles above its mouth, in Lauderdale County, Mississippi, 
seven miles northwest of Meridian. 
Existing project. The project provides for a dam and 
reservoir for flood control, water supply, water quality 
control, fish and wildlife, and recreation. The dam consists 
of a compacted earth fill 6,540 feet long with the top 
elevation 369.8 feet above national geodetic datum, 
with top width of 18 feet. The spillway, which is located 
1,500 feet east of the east end of the dam, is an unpaved 
free overflow type, 1,500 feet long with a fixed crest at 
elevation 359. A sluice intake structure near the center 
of the dam serves a 9.0-foot diameter concrete conduit. 
Storage allocated for water supply and water quality 
control varies seasonally from 21,400 acre-feet to 34,300 
acre-feet between a minimum elevation of 328 and topof-
conservation-pool elevation varying from 339 to 343. 
Storage varying from 46,500 acre-feet to 59,500 feet 
between the top of the conservation pool and elevation 
352 has been reserved exclusively for storage of flood 
waters. (See Table 10-B for authorizing legislation.) 
Local cooperation. Complied with to date. 
Operations and results during fiscal year. New Work: 
10-12

MOBILE, ALABAMA DISTRICT 
Engineering and design of public use facilities cost 
$22,505. Maintenance: Costs for the year for ordinary 
maintenance and recreational management amount to 
$825,795. Benefits attributed to flood control storage 
and regulation amounted to $154,200. Recreation attendance 
at the reservoir during CY 1982 totaled 
874,000 recreational user days. 
Condition at end of fiscal year. Construction began in 
June 1965, and was completed in November 1968. Total 
Federal costs of the existing project as of September 30, 
1983 were $9,111,079 for new work and $5,397,594 for 
maintenance, a total of $14,508,673. 
28. TALLAHALA CREEK LAKE, 
PASCAGOULA RIVER, MS 
Location. The project is on Tallahala Creek, 81.1 
miles above its mouth, in Jasper County, Mississippi, 13 
miles north of Laurel. 
Existing project. The project provides for a dam and 
reservoir for flood control, water supply, water quality 
control, recreation, and fish and wildlife enhancement. 
The dam will consist of a compacted earth fill 8,000 feet 
long, with top elevation 343.5 feet above national geodetic 
datum, or a maximum 71.5 feet above streambed 
elevation, with a top width of 18 feet, and a 300-foot 
long saddle dike with maximum height of 15 feet in the 
left abutment. The spillway which is 6,000 feet northeast 
of the left abutment, will consist of an unpaved, freeoverflow 
type, 500 feet long, with fixed crest at elevation 
335.0. A sluice intake structure near the center of the 
dam will serve an 8-foot diameter, horseshoeshaped 
concrete conduit. The reservoir at maximum pool elevation 
306.5 will have an area of 4,000 acres and a total 
capacity of 63,000 acre-feet of which 35,900 acre-feet 
between elevations 288.5 and 302.0 will be used for 
water supply, 20,000 acre-feet between elevations 302.0 
and 306.5 will be used for water quality improvement, 
and 7,100 acre-feet below elevation 288.5 will consist of 
dead storage. A volume varying seasonally from 50,000 
to 70,000 acre-feet between elevations 306.5 and 315.0 
will be reserved for flood storage. Estimated Federal 
cost (1982) is $113,000,000. (See Table-B for authorizing 
legislation.) 
Local cooperation. Local interests will be required to 
reimburse the United States for all costs allocated to 
water supply in accordance with the Water Supply Act 
of 1958, as amended; and one-half of the separable first 
cost of the project allocated to general recreation and 
fish and wildlife enhancement. In addition, local interests 
are required to reimburse the United States for the 
annual operation, maintenance and replacement cost 
allocated to water supply, and bear all cost of operation, 
maintenance and replacement of recreation and fish and 
wildlife areas and facilities for initial development. 
Operations and results during fiscal year. New work: 
Engineering and design cost, $60,967. 
Condition at end of fiscal year. Construction has not 
been initiated. 
29. BURKETTS CREEK, AMORY, MS 
Location. The project is located in the northeast portion 
of the city of Amory and lies between Burketts 
Creek and the Tennessee-Tombigbee Canal Section 
near Lock A. 
Existing project. The project provides for an earthfilled 
diversion structure and a 60 foot wide bottom 
width diversion canal to intercept Burketts Creek at 
station 100+55 and direct flow in a northerly direction 
for about 4,000 feet to enter Lock A pool at canal 
station 2+00. Side slopes will be one vertical on three 
horizontal. In addition, provisions are made for a concrete 
baffled chute as an energy dissipator and a riprap 
blanket at the toe. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. New work: 
Construction of the project cost $1,074,914. 
Condition at end of fiscal year: Construction of the 
project was initiated and essentially completed during 
the fiscal year. Total cost to date is $1,340,054 for new 
work. 
30. GORDONS CREEK, 
HATTIESBURG, MS 
Location. The project is located along the lower 
12,320 feet of Gordons Creek between its mouth at Leaf 
River and Broad Street Bridge, within the city limits of 
Hattiesburg, Ms. 
Existing project. The authorized project provides for 
flood damage reduction along and upstream of the project 
limits by clearing, snagging, widening and the removal 
of debris. 
Local cooperation. Fully complied with. Project has 
been turned over to local interest to maintain. 
Operations and results during fiscal year. New work: 
Miscellaneous costs amounted to $1,713. Flood control 
benefits attributed to the project for FY 1983 amounted 
to $2,085,300. 
Condition at end of fiscal year. Construction commenced 
in June 1979 and was essentially completed in 
June 1980. Total Federal costs for the project as of 
September 30, 1983 were $775,638 all for new work. 
31. MURDER CREEK, 
EAST BREWTON, AL 
Location. The project is located in the city of East 
Brewton along the left bank of Murder Creek in the 
vicinity of Forrest and Snowden Avenues. 
Existing project. The project consists of non-structural 
measures of flood plain evacuation and flood proofing 
of selected buildings for the reduction of flood damages. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Land 
acquisition was completed and relocation assistance 
initiated for three families and five businesses at a cost 
10-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
of $404.47 I. 
Condition at end of fiscal year. Completion of this 
non-structural plan is scheduled for July 1984. Total 
costs to date have amounted to $798,365. 
32. SUN CREEK, 
OKTIBBEHA COUNTY, MS 
Location:The project is located in the northwest part 
of Oktibbeha County about 3 miles northwest of the city 
of Starkville. Mississippi. 
Existing project. The project consists of the removal 
of accumulated logs, debris, and sediment which obstructs 
normal stream flow along a 0.6 mile reach of the 
Sun Creek Channel. 
Local cooperation: Fully complied with. 
Operations and results during fiscal year. New work: 
Construction of the project during fiscal year cost 
$6,163. 
Condition at end of fiscal year. Construction was 
initiated during fiscal year and is about 10 percent complete. 
Total cost for the project as of September 30, 1983 
was $6.163. The construction funds were provided 
under the FY 1983 Jobs Bill. Productive Employment 
Appropriations Act. 1983. (PL 98-8). 
33. TOMBIGBEE RIVER 
TRIBUTARIES, MS AND AL 
Location. The Tombigbee River rises in extreme 
northeast Mississippi and flows southerly through eastern 
Mississippi and western Alabama. emptying into 
the Mobile River about 45 miles above its mouth at 
Mobile, Alabama. Tributaries to be improved for flood 
control are all in northeast Mississippi and northwest 
Alabama. 
Existing project. The authorized project provides for 
improvement of 22 tributaries of the Tombigbee River 
by means of channel clearing and snagging. Approved 
estimate of cost (1983) for new work is $121,516,600; 
consisting of $109,000,000 Federal funds, and 
$12.516,600 non-Federal funds. (See Table 10-B for 
authorizing legislation.) 
Local cooperation. Local interests must furnish lands 
and rights-of-way for construction; make all roads, 
highway bridge, and utility changes, alterations, additions, 
and relocations necessary for the project; hold the 
United States free from damages; prevent future encroachments 
along the improved channels; maintain all 
works after completion; and contribute $12,146,600 in 
cash or equivalent work. 
Operations and results during fiscal year. Repairs to 
three bridges over Twenty Mile. Wolf, and Osborne 
Creeks and repairs to grade stabilization structures on 
Twenty Mile Creek cost $1,289,170. 
Condition at end of fiscal year. Construction commenced 
in July 1965, and the overall project is about 10 
percent complete. Federal cost of existing project as of 
September 30, 1983 was $1 1,446,308 for new work. 
Contributed funds for new work amounted to $49,752.) 
34. TRIM CANE CREEK, 
OKTIBBEHA COUNTY, MS 
Location: The project is located in the northwest part 
of Oktibbeha County about 3 miles northwest of the city 
of Starkville, Mississippi. 
Existing project. The project consists of the removal 
of accumulated logs, debris, and sediment which obstructs 
normal stream flow along a 1.0 mile reach of the 
Trim Cane Creek Channel. 
Local cooperation: Fully complied with. 
Operations and results during fiscal year: New work: 
Construction of the project during fiscal year cost 
$13,563. 
Condition at end of fiscal year. Construction was 
initiated during fiscal year and is about 10 percent complete. 
Total cost for the project as of September 30. 1983 
was $13,563. The construction funds were provided 
under the FY 1983 Jobs Bill, Productive Employment 
Appropriations Act, 1983. (PL 98-8). 
35. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Local flood-protection works for which inspection is 
performed under this heading consist of levee projects at 
West Point, Georgia, on the Chattahoochee River; 
Montezuma, Georgia, in the Flint River Basin; Elba 
and Geneva, Alabama, in the Choctawhatchee River 
Basin; Rome, Georgia, and Collinsville, Alabama. in 
the Alabama-Coosa River Basin; and channel rectification 
projects on Black Creek, Gadsden. Alabama. in the 
Alabama-Coosa River Basin; Old Town Creek. Tupelo. 
Mississippi; Big Brown Creek, Donovan Creek. Twenty 
Mile Creek, and Mantachie Creek. Fulton. Mississippi; 
Houlka Creek, Chickasaw and Clay Counties; and 
Luxapalila Creek, Alabama, in the Tombigbee River 
Basin; Gordons Creek, Hattiesburg. Mississippi, Pascagoula 
River Basin; Murder and Burnt Corn Creeks. 
Brewton, Alabama, Conecuh River Basin; Sowashee 
Creek, Meridian, Mississippi, in Chickasawhay River 
Basin; Clanton, Alabama; Little Cove Creek, 
Glencoe, Alabama; Autauga Creek, Prattville. Alabama; 
Armuchee Creek, Armuchee, Georgia; Town 
Creek, Americus, Georgia; and Lake Douglas at Bainbridge, 
Georgia, in the Apalachicola-Chattahoochee- 
Flint Rivers Basin; and a drainage project in Jackson 
County, Florida. Projects at Rome and Montezuma. 
Georgia, and Collinsville, Alabama. include pumping 
stations. Inspections were made during FY 1983 to 
determine the extent of compliance with approved regulations 
for maintenance and operation of the projects. 
Responsible local officials were advised of inadequacies 
in maintenance and operation of the local flood protection 
works under their jurisdiction where appropriate. 
10-14

MOBILE, ALABAMA DISTRICT 
Follow-up for compliance of the deficient projects continued 
during the year. Fiscal year costs were $47,640. 
Total cost to September 30, 1983 was $313,754 charged 
to maintenance. 
36. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
(See Table 10-1) 
37. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood Control activities pursuant to Section 205, 
Public Law 858, 80th Congress, as amended (Pre-authorization). 
Snagging and Clearing for flood control pursuant to 
Section 208 of Flood Control Act of 1954, as amended. 
Emergency streambank and shoreline protection pursuant 
to Section 14 of the Flood Control Act of 1946, as 
amended. 
(See Table 10-J) 
Emergency flood control activities-repair, flood 
fighting, and rescue work (Public Law 99, 84th Congress, 
and antecedent legislation, and disaster relief and 
assistance under Public Law 288, 93d Congress. 
(See Table 10-i) 
Multiple-Purpose Projects Including Power 
38. ALABAMA-COOSA RIVERS, 
AL AND GA 
Location. Alabama River is formed 18 miles above 
Montgomery, Alabama, by the junction of the Coosa 
and Tallapoosa Rivers. It then flows southwesterly 
through Alabama 318 miles and unites with the Tombigbee 
River about 45 miles north of Mobile, in southwestern 
Alabama, to form the Mobile River. (See Geological 
Survey maps for central and southwest Alabama.) 
The Coosa River is formed at Rome, Georgia, in 
northwest Georgia, by the junction of the Oostanaula 
and Etowah Rivers, which have their sources in southeastern 
Tennessee and northern Georgia. From Rome 
the Coosa River flows southwesterly through Georgia 
and Alabama 286 miles and unites with the Tallapoosa 
River near Montgomery, Alabama, at about the center 
of the State, to form the Alabama River. (See Geological 
Survey maps for northeast Alabama, southeast 
Tennessee, and northwest Georgia.) 
Previous project. Projects for Alabama River: for 
details see page 1837, Annual Report for 1915; page 725, 
Annual Report for 1938: and page 592. Annual Report 
for 1944. Projects for Coosa River: for details see page 
1837. Annual Report for 1915; page 728, Annual 
Report for 1938; and page 594, Annual Report for 1944. 
Existing project. The authorized project provides for 
full development of the Alabama-Coosa Rivers and 
tributaries for navigation, flood control, power, recreation, 
and other purposes, in accordance with plans 
under preparation by Chief of Engineers, subject to 
modifications thereof which may be advisable for 
increasing development of hydroelectric power. (See 
Table 10-B for authorizing legislation.) Public Law 436, 
83rd Congress, suspended authorization of the comprehensive 
plan, insofar as it provides for development of 
hydroelectric power for Coosa River, to permit non- 
Federal interests to develop the Coosa River by construction 
of a series of dams in accordance with conditions 
of a license issued pursuant to Federal Power Act 
and in accordance with certain other provisions and 
requirements of the aforementioned public law. The 
present phase of improvement, now under construction, 
provides for construction of Robert F. Henry and 
Millers Ferry multiple-purpose improvements. Claiborne 
Lock and Dam, and supplemental channel work 
providing for a nine-foot deep navigation channel from 
the mouth of the Alabama River to Montgomery. Alabama, 
and for construction of Carters Dam, a multiplepurpose 
improvement on Coosawattee River, Georgia. 
The total estimated cost (1983) for new work on the 
present phase of Alabama-Coosa Rivers (exclusive of 
Coosa River navigation) is $260,358,546. consisting of 
$256,973,146 for structures, and $3,385,400 for supplemental 
channel improvements, exclusive of amounts 
expended on previous projects and $35,457,308 for 
Allatoona Lake. 
Local cooperation. Requirements of local cooperation 
will be determined as formulation of plans for 
development of projects progress. No action in the matter 
of local cooperation has been initiated. 
Terminal facilities. On the east bank of the river a 
natural landing connects with city streets at Montgomery. 
Wofford Oil Company has a small wharf about 10 
miles below Montgomery equipped for handling petroleum 
products. There are also various natural landings 
along the river. Facilities and natural landings on Alabama 
River are considered adequate for existing commerce. 
Operations and results during fiscal year. New work: 
Recreation facilities and engineering, design, supervision 
and administration at Robert F. Henry Lock and 
Dam cost $164,544. Public use areas at Millers Ferry 
Lock and Dam cost $22,500. Engineering and design for 
Coosa River navigation segment amounted to $224.213. 
Modification to distribution system at Carters cost 
$43,083. Total cost of new work amounted to $454,340. 
Maintenance: Contract dredging removed 630,000 
cubic yards of material from the river system at a cost of 
$1,466,156. General charges for recreation, supervision 
and administration and miscellaneous costs amounted 
to $1,030,899. Coosa River Reservoir operations cost 
$157,860 and lock operations $218,634. In addition. 
operation of Robert F. Henry Lock and Dam cost 
$1,843,208, Millers Ferry Lock and Dam. $2,364,854, 
Carters Lake. $1,952,950, all for a total maintenance 
cost of $9,034.561. 
Condition at end of fiscal year. Construction was 
10-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
initiated on Carters Dam in April 1962 on Millers Ferry 
Lock and Dam in April 1963, Claiborne Lock and Dam 
in May 1965, and Robert F. Henry Lock and Dam in 
March 1966. Carters Dam was essentially completed in 
FY 1980. The authorized nine-foot navigation channel 
to Montgomery, Alabama was opened to traffic in January 
1972. Overall construction is essentially complete 
at Millers Ferry Lock and Dam. Construction of 
Robert F. Henry Lock and Dam is about 99 percent 
complete with completion scheduled for 1984. Total 
Federal costs of the existing project as of September 30, 
1983 are $378,496,463, including $304,994,028 for new 
work and $73,502,435 for maintenance. (See Table 
10-K.) 
38A. CARTERS LAKE, GA 
Location. The damsite is in Murray County, Georgia, 
on the Coosawattee River 26.8 miles above its junction 
with Conasauga River, one of the headwater tributaries 
of the Alabama-Coosa system. It is 60 miles north of 
Atlanta near the town of Carters, Georgia. The reservoir 
is in both Murray and Gilmer Counties. 
Existing project. The authorized project consists of a 
1,950-foot long rockfill dam across the river, three saddle 
dikes on the left bank, a 258-foot long high-level, 
gated spillway on the left bank, a power house on the 
right bank having two conventional units with a generating 
capacity of 125,000 kilowatts each and two pumpgenerating 
units of the same size, and a regulating dam 
2,855 feet long with a gated spillway 208 feet long 1.5 
miles downstream from the main dam. The lake has an 
area of 3,220 acres, at maximum power pool elevation 
1,072, total capacity of 472,800 acre-feet, of which 
134,900 acre-feet is usable for power and 95,700 acrefeet 
reserved for flood control and 242,200 acre-feet 
dead storage. For other information see description of 
Alabama-Coosa project. 
Operations and results during fiscal year. Total cost 
of new work amounted to $43,083 for modifications to 
distribution system. 
Maintenance: Operation and ordinary maintenance 
of the dam, reservoir, powerhouse, service and recreational 
activities and administration incidental thereto 
cost $1,952,950. Gross power generation amounted to 
613,221,000 kilowatt hours during FY 1983, of which 
241,881,000 were delivered to Southeastern Power 
Administration. Recreation attendance during CY 1982 
totaled 712,000 recreational user days. Reduced flood 
damages attributed to the Carters project and to the 
joint operation with Allatoona were $2,937,300 during 
FY 1983. 
Condition at end of fiscal year. Construction which 
commenced in April 1962 was essentially completed in 
September 1980. Total Federal costs of the existing 
project as of September 30, 1983 are $124,814,116, 
including $111,139,162 for new work and $13,674,954 
for maintenance. 
38B. CLAIBORNE LOCK AND DAM, AL 
Location.The site is in Monroe County at mile 81.8 
on the Alabama River, 15 miles northwest of Monroeville 
and 5.7 miles upstream from the U. S. Highway 84 
bridge. 
Existing project. The authorized project consists of a 
short earth dike on the right bank, a combination of a 
fixed-crest and gated spillway extending across the river 
channel and into the left bank, a navigation lock and 
mound on the left bank, and an earth dike extending 
across the left overbank to high ground. Normal upper 
pool is at elevation 35 and the minimum pool will be 
elevation 32 to provide storage for reregulation of 
Millers Ferry powerplant releases. The 60-mile long 
reservoir has an area of 5,850 acres and a volume of 
96,360 acre-feet. For other information see description 
of Alabama-Coosa projects. 
Operations and results during fiscal year. New work: 
none. Maintenance: none. Recreation attendance during 
CY 1982 totaled 681,000 user days. 
Condition at end of fiscal year. Construction began in 
May 1965 and was completed in FY 1976 at a total cost 
of $28,151,450. 
38C. ROBERT F. HENRY LOCK AND 
DAM, AL 
Location. The site is in Lowndes and Autauga Counties 
at mile 245.4 on the Alabama River, 26 miles west of 
Montgomery. 
Existing project. The authorized project provides for 
a navigation lock, a gated spillway, and a power plant 
located at mile 245.4. The normal upper pool is at 
elevation 125.0 and the minimum lower pool due to the 
Millers Ferry Lock and Dam is at elevation 80.0. The 
structures consist of earth dikes and a power plant on 
the right bank, a gated spillway in the river channel, a 
lock and mound on the left bank, and an earth dike 
extending upstream parallel to the Western Railway of 
Alabama. The total length of the structures is about 
14,962 feet with maximum height above the foundation 
at the power plant intake about 101 feet. The power 
plant contains four 17,000-kw. units. The 88-mile long 
reservoir has an area of 12,300 acres at normal pool level 
and a total capacity of 234,200 acre-feet. The lock has a 
chamber 84 feet wide and 600 feet long and provides a 
12-foot depth over the lower miter sill. The approved 
estimated (1983) cost is $84,100,000. For other information 
see description of Alabama-Coosa project. 
Operations and results during fiscal year. Total cost 
of new work amounted to $164,544 for recreation facilities 
and engineering, design, supervision and administration. 
Maintenance: Operation and maintenance cost amounted 
to $1,843,208. Gross power generation amounted 
to 363,831,000 kilowatt-hours during FY 1983, of 
which 358,030,000 were delivered to Southeastern Power 
Administration. Recreation attendance at R.E. "Bob" 
10-16

MOBILE, ALABAMA DISTRICT 
Woodruff Lake during CY 1982 totaled 2,365,000 user 
days. 
Condition at end of fiscal year. Construction began in 
March 1966 is 99 percent complete, and is scheduled for 
completion in FY 1984. The first powerhouse unit was 
placed in operation in June 1975, with the last unit on 
line in November 1975. Total Federal costs of the project 
as of September 30, 1983 were $94,309,035, including 
$83,108,684 for new work and $11,200,351 for 
maintenance. 
38D. MILLERS FERRY LOCK AND 
DAM, AL 
Location. The site is in Wilcox County at mile 142.2 
on the Alabama River, 10 miles northwest of Camden, 
Alabama, and 30 miles southwest of Selma. 
Existing project. The project consists of an earth dike 
on the right bank, a concrete, gravity-gated spillway in 
the river channel, a lock and mound on the left bank, an 
earth dike extending downstream paralleling the lock, 
to the powerhouse intake structure; a powerhouse, and 
an earth dike extending to high ground on the left bank. 
Normal upper pool is at elevation 80. The powerplant 
contains three 25,000 kilowatt units. The 103-mile long 
reservoir has an area of 17,200 acres at normal pool level 
and a total capacity of 331,800 acre-feet. The lock 
chamber is 84 by 600 feet with a 13-foot depth over the 
miter sills. For other information see description of 
Alabama-Coosa project. 
Operations and results during fiscal year. Total cost 
of new work amounted to $22,500 for public use 
facilities. 
Maintenance: Operation and maintenance of lock, 
dam, powerhouse, reservoir, and administration incidental 
thereto cost $2,364,854. Gross power generation 
amounted to 386,292,000 kilowatt-hours during FY 
1983, of which 383,841,000 kilowatt-hours were delivered 
to Southeastern Power Administration. Recreation 
attendance at William "Bill" Dannelly Reservoir 
during CY 1982 totaled 2,421,000 user days. 
Condition at end of fiscal year. Construction began in 
April 1963. The lock was placed in temporary operation 
in June 1968 and opened to full use in November 1969. 
The powerhouse units were placed on line during April 
and May 1970. The project was essentially completed in 
1980. Total Federal costs of the project as of September 
30, 1983 were $62,725,300 for new work and $20,115,961 
for maintenance, a total of $82,841,261. 
38E. COOSA RIVER NAVIGATION 
Location. The Coosa River is one of the two major 
tributaries forming the Alabama River approximately 
18 miles northeast of Montgomery, Alabama. From its 
source at the juncture of the Etowah and Oostanaula 
Rivers in northwest Georgia, it flows southwesterly 
about 286 miles to join with the Tallapoosa River in 
forming the Alabama River. 
Existing project. The improvement of the Alabama- 
Coosa River or navigation to Rome, Georgia was 
authorized by Congress in the River and Harbor Act of 
1945. A report in House Document 320, transmitted to 
Congress on 27 January 1960, recommended that the 
navigation project for the Coosa River from Montgomery 
to Gadsden be accomplished after the waterway to 
Montgomery was assured. The plan of improvement 
identified in House Document 320 provided for a 
waterway 9 feet deep with widths of 200 feet to Montgomery, 
Alabama, and 150 feet to Rome, Georgia. The 
water-way to Montgomery has essentially been completed. 
The estimated 1983 cost is $1,303,320,000 of 
which $1,252,320,000 is Federal and $51,000,000 non- 
Federal. 
Operations and results during fiscal year. Funding 
was initiated in FY 1978 for preconstruction planning. 
FY 1983 costs were $244,213 for engineering, design, 
supervision and administration. In addition, general 
investigations funds expended amounted to $2,880,154 
for advanced engineering and design. 
39. ALLATOONA LAKE, COOSA 
RIVER BASIN, GA 
Location. The project is on Etowah River in Bartow 
County, Georgia, about 48 miles upstream from Rome, 
Georgia, about five miles due east of Cartersville, Georgia, 
and about 2,000 feet downstream from mouth of 
Allatoona Creek. The reservoir extends about 28 miles 
up the Etowah River at maximum power-pool elevation 
of 840 feet above mean sea level. 
Existing project. The authorized project provides for 
a dam and reservoir for flood control, regulation of 
streamflow for navigation, and development of hydroelectric 
power. Height above the river bottom of the 
concrete, gravity-type dam is about 190 feet from elevation, 
690 feet to 880 feet national geodetic datum. The 
spillway, with crest at elevation 835, is controlled by 
nine tainter gates, 40 feet wide by twenty-six feet high, 
and two tainter gates, 20 feet wide by twenty-six feet 
high; having a combined discharge capacity of 321,000 
cubic feet per second with the water surface at elevation 
870.3. One 48-inch diameter sluicing conduit with a free 
discharge valve and four sluices, 5 feet-8 inches wide by 
10 feet high, are included in dam. Installed generating 
capacity consists of two 36,000 kilowatt units and one 
2,000 kilowatt unit, or a total of 74,000 kilowatts. Ultimate 
installed capacity will be 110,000 kilowatts. The 
reservoir, covering 19,200 acres at elevation 860, has a 
storage capacity of 670,000 acre-feet. The initial construction 
cost was $31,424,738, excluding the addition 
of recreation facilities at the completed project. (See 
Table 10-B for authorizing legislation.) 
Local cooperation. None required (Sec. 2, Flood 
Control Act of June 28, 1938, applies). 
Operations and results during fiscal year. New work: 
Additional recreational facilities cost $668,140. 
Maintenance: Operation and ordinary maintenance 
10-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
of the dam, reservoir, powerhouse, service and recreational 
activities, and administration incidental thereto 
cost $3,996,293. Gross power generation at Allatoona 
Reservoir amounted to 196,056,700 kilowatt-hours during 
FY 1983 of which 192,201,000 kilowatt-hours were 
delivered to Southeastern Power Administration. Recreational 
attendance at Allatoona Lake during CY 1982 
totaled 8,100,000 recreational user days. Benefits attributed 
to flood control storage and regulation amounted 
to $451,600. In addition, joint flood control operation 
with Carters Dams resulted in reduced damages of 
$2,901,000 in the vicinity of Rome, Georgia. 
Condition at end of fiscal year. Construction of the 
existing project began in March 1944 and was completed 
in October 1955. Total Federal costs under existing 
project as of September 30, 1983 were $35,466,308 
for new work and $36,605,092 for maintenance, a total 
of $72,071,400. 
40. APALACHICOLA, 
CHATTAHOOCHEE, AND FLINT 
RIVERS, AL., GA., AND FL 
Location. The Apalachicola River is formed at the 
southwest corner of the State of Georgia by the junction 
of the Chattahoochee and Flint Rivers and flows south 
108 miles emptying into Apalachicola Bay. Florida 
River enters the Apalachicola River from the east at 
mile 45.4 and the River Styx also enters from the east at 
mile 36.7 and Chipola River enters from the west at mile 
28.2. (See Coast and Geodetic Survey Chart 11401.) The 
Chattahoochee River, 418 miles long, rises in northeast 
Georgia and flows southwesterly to West Point, and 
thence southerly to join the Flint River at the southwest 
corner of Georgia, forming the Apalachicola River. 
(See Geological Survey maps for northwest 
Georgia.) The Flint River, 330 miles long, rises in 
west central Georgia, flows generally southeasterly to 
Albany, and thence southwest to the southwest corner 
of the State, where it joins the Chattahoochee River to 
form the Apalachicola River. (See Geological Survey 
maps for southwest Georgia.) 
Previous project. For details see page 484 for Annual 
Report for 1963. 
Existing project. The authorized project provides for 
development of the Apalachicola, Chattahoochee, and 
Flint Rivers for navigation, flood control, hydropower, 
and recreation. Navigation features of the existing project 
consist of a continuous 9-foot by 100-foot channel 
in the Apalachicola River from the intersection of the 
Gulf Intracoastal Waterway to the confluence of the 
Chattahoochee and Flint Rivers, 104 miles, thence to 
Columbus, Georgia, on the Chattahoochee River, 164 
miles, and to Bainbridge, Georgia, on the Flint River, 29 
miles, and a 3-foot by 100-foot channel on the Flint 
River from Bainbridge to Albany, Georgia, 74 miles, 
thence a channel suitable for light draft vessels at moderate 
stage to Montezuma, Georgia, 79 miles, to be 
accomplished by dredging, contraction works, and construction 
of three locks and dams (Jim Woodruff, 
George W. Andrews, and Walter F. George) along the 
9-foot depth channel, two multipurpose dams (West 
Point and Buford) on the Chattahoochee River, three 
multipurpose dams (Lower Auchumpkee Creek, Lazer 
Creek, and Spewrell Bluff) on the Flint River, and 
minor improvements of certain streams tributary to the 
Apalachicola River, including a nine by 100-foot side 
channel, approximately 2,000 feet long, from Apalachicola 
River to Apalachicola River Industrial Park at 
Blountstown, Fla. Plane of reference is mean low water. 
Hydropower and flood control storage is provided at 
Sidney Lanier, Walter F. George, and West Point, and 
hydropower is provided at Jim Woodruff. The authorized 
but unconstructed projects of Lazer Creek, Lower 
Auchumpkee Creek and Spewrell Bluff would have 
storage for hydropower and flood control. For further 
details see Annual Report for 1962. (See Table 10-B for 
authorizing legislation.) 
Mean range of tide at the mouth of Apalachicola 
River is 1.6 feet. At the point where the river is formed 
the variation between low and high water is about 37 
feet. On the Chattahoochee River, variation between 
average low and high water is about 20 feet, and extreme 
fluctuation is 65.3 feet at Eufaula. On the Flint River the 
extreme fluctuation of stage due to flood is 40 feet, while 
average variation between low and high water is about 
21.5 feet. 
Local cooperation. Fully complied with to date. 
Terminal facilities. About 200 feet of public docks, in 
addition to private wharves, are available at Apalachicola, 
Florida. There are numerous constructed and natural 
landings along the entire system for launching small 
craft. For details of other terminal facilities, which are 
considered adequate for existing commerce, see individual 
project descriptions. See also Table 10-L on locks 
and dams and multiple-purpose development included 
in existing project. 
Operations and results during fiscal year. New work: 
Initiation of construction of cut off wall under Walter F. 
George Dam to correct seepage cost $1,234,848. 
Recreation facilities for various reservoirs cost 
$923,386. 
Maintenance: The contractor's dredge removed 
774,978 cubic yards (net) of material from the river 
system at a cost of $1,873,501. Other costs incidental to 
the overall project amounted to $1,738,940. Operation 
of George W. Andrews Lock and Dam cost $276,731. 
Operations and maintenance locks and dams:Buford 
Dam cost $4,553,188; Jim Woodruff Lock and Dam, 
$3,205,787; Walter F. George Lock and Dam, $3,561,801; 
and West Point Lake, $2,952,188. Total FY 1983 cost 
for entire project was $20,320,370, of which $2,158,234 
was for new work and $18,162,136 was for operation 
and maintenance. Detailed information on operations 
and costs applicable to the individual dam projects is 
10-18

MOBILE, ALABAMA DISTRICT 
presented under their respective project titles elsewhere 
mitnh is report. 
Condition at end of fiscal year. Improvement of 
Apalachicola River channel by dredging to provide project 
dimensions throughout is complete. All major construction 
on Lake Sidney Lanier Dam, George W. 
Andrews Lock and Dam, Jim Woodruff Lock and 
Dam, and Walter F. George Lock and Dam, is complete. 
West Point is essentially complete with the exception 
of adding recreation facilities. Channel rectification 
in Apalachicola River was completed December 
1970. More detailed information concerning condition 
at the end of fiscal year for individual locks and dams 
and multiple-purpose developments comprising the system 
is presented under their respective project titles 
elsewhere in this report. Work remaining to complete 
the project consists of completion of recreational facilities 
at Lake Sidney Lanier, George W. Andrews Lock 
and Dam, Jim Woodruff Lock and Dam, and Walter F. 
George Lock and Dam; design and construction of 
Lazer Creek, Spewrell Bluff and Lower Auchumpkee 
Creek Dam; and completion of construction of West 
Point Dam. (See Tables 10-A and 10-L for fiscal year 
costs and summaries of overall project. 
40A. BUFORD DAM, GA 
Location. Buford Dam is on the Chattahoochee 
River about 348.9 miles above its mouth, 50 miles above 
Atlanta and five miles northwest of Buford, Georgia. 
The reservoir, Lake Sidney Lanier, extends about 47 
miles upstream along the Chattahoochee River, and 
about 21 miles up the Chestatee River, which enters the 
Chattahoochee River 14.5 miles above the dam. 
Existing project. The authorized project provides for 
a rolled-earth dam 1,630 feet long with crest at elevation 
1,106 feet national geodetic datum, or about 192 feet 
above streambed elevation; three earth saddle dikes 
with a total length of 5,406 feet; a chute spillway with 
crest at elevation 1,085; a powerhouse in a deep cut with 
steel penstocks in tunnels, and concrete intake structure 
at the upstream end of the tunnels; and a flood control 
sluice tunnel paralleling the power funnels. The Lake 
Sidney Lanier reservoir has a gross capacity of 
2,554,000 acre-feet of which 637,000 acre-feet of storage 
is reserved for flood control storage. The power installations 
consist of one generating unit of 6,000 
kilowatts and two units of 40,000 kilowatts each, or a 
total of 86,000 kilowatts. The project provides for maintenance, 
including operation and care. (See Table 10-B 
for authorizing legislation.) 
Local cooperation. None required. 
Operations and results during fiscal year. New work: 
Construction of recreational facilities at the completed 
project cost $471,532, including engineering, design, 
supervision, and administration. 
Maintenance: Operation and maintenance cost 
$4,553,188. Gross power generation amounted to 
221,084,000 kilowatt-hours during FY 1983, of which 
217,628,000 were delivered to Southeastern Power 
Administration. Recreational attendance at Lake Sidney 
Lanier during CY 1982 totaled 14,341,000 recreational 
user days. Flood control benefits attributed to the 
project for FY 1983 amounted to $137,900. 
Condition at end of fiscal year. Construction commenced 
in March 1950 and was completed in June 1960. 
The reservoir was in useful operation for flood control 
in February 1956. The first power generating unit was 
placed on the line June 19, 1957; the second on July 26, 
1957; and the third on October 10, 1957. The project is 
essentially complete except for adding additional recreational 
facilities. 
40B. GEORGE W. ANDREWS LOCK AND 
DAM, AL AND GA 
Location. The project is on the Chattahoochee River 
about 46.5 miles above its mouth and about one mile 
below the town of Columbia, Alabama, near the head of 
Jim Woodruff Reservoir. (See Geological Survey maps 
for southeast Alabama.) The pool extends up the navigation 
channel about 28 miles upstream to Walter F. 
George Lock and Dam. 
Existing project. This single-purpose project provides 
for a concrete fixed-crest spillway 340 feet long extending 
into the right bank with a crest at elevation 102 feet 
national geodetic datum, a concrete gate spillway adjacent 
to the lock 280 feet long with crest at elevation 82 
feet national geodetic datum, a single-lift lock with usable 
chamber dimensions of 82 feet by 450 feet, and a 
maximum lift of 25 feet. Depths are 13 feet over the 
lower sill and 19 feet over the upper sill at normal pool 
elevation. The underlying foundation is limestone. The 
project provides for maintenance and care. The House 
Committee on Public Works, by resolution adopted 
May 19, 1953, approved the plan as proposed by the 
Chief of Engineers for a high dam at Walter F. George 
site and a low dam at the Fort Benning site and a high 
dam at the upper Columbia site, construction of which 
was authorized by the 1946 River and Harbor Act as the 
initiation and partial accomplishment of the plan for 
full development of the Apalachicola, Chattahoochee, 
and Flint River system. (See Table 10-B for authorizing 
legislation.) 
Local cooperation. Local interests must operate all 
movable span bridges, provide suitable public terminals, 
and hold the United States free from damages. 
These conditions are being complied with. 
Terminal facilities. At Columbia, Alabama, there is a 
public wharf with concrete deck for handling general 
cargo and a bulk petroleum terminal with an unloading 
dock. Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal year. Recreational 
attendance at George W. Andrews Lock and 
Dam during CY 1982 totaled 319,000 recreational user 
10-19

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
days. Maintenance: Operation and maintenance cost 
included under overall Apalachicola, Chattahoochee 
and Flint project. 
Condition at end of fiscal year. Construction of the 
lock and dam began in March 1959 and was completed 
in November 1963. Work remaining consists of construction 
of recreational facilities. 
40C. JIM WOODRUFF LOCK AND DAM, 
GA AND FL 
Location. The project is located on the Apalachicola 
River 107.6 miles above its mouth, about 1,000 feet 
below confluence of the Chattahoochee and Flint Rivers, 
and 1.5 miles northwest of Chattahoochee, Florida. 
Reservoir extends about 46.5 miles upstream along the 
Chattahoochee River to the vicinity of Columbia, Alabama, 
and about 47 miles upstream along Flint River, 
or 17 miles above Bainbridge, Georgia. (See Geological 
Survey maps for southwest Georgia.) 
Existing project. The authorized project provides for 
a concrete open-crest spillway 1,634 feet long on the 
right bank, with a crest at elevation 79 feet national 
geodetic datum; a single-lift lock with usable chamber 
dimensions of 82 by 450 feet, a maximum lift of 33 feet, 
and depth over the sills of 14 feet; a gated spillway 766 
feet long with the bridge at elevation 107 feet national 
geodetic datum, or about 67 feet above the streambed 
elevation; a powerhouse with an intake section constituting 
a portion of the dam; an earth section 506 feet 
long to accommodate the switchyard and substation; 
and an overflow dike section 2,130 feet long on the left 
bank, with a crest at elevation 85. The underlying foundation 
is limestone. At the normal pool elevation of 77, 
the reservoir has a total capacity of 406,160 acre-feet. 
The power installation consists of three units of 10,000 
kilowatts each, or a total of 30,000 kilowatts. Project 
provides for maintenance, including operation and 
care. (See Table 10-B for authorizing legislation.) 
Local cooperation. Required cooperation is being 
fulfilled. Easements for rights-of-way and spoildisposal 
areas were provided as required along the Apalachicola 
River. Adequate public terminals were constructed 
by local interests at Bainbridge, Georgia, on the 
Flint River; and at Columbia, Alabama, on the 
Chattahoochee River. Facilities are being planned for 
other localities on the project. 
Terminal facilities. A public wharf with concrete deck 
for handling general cargo, a bulk storage terminal for 
petroleum, a grain elevator, and private riverside facilities 
at Bainbridge, Georgia, on the Flint River, are 
considered adequate for existing commerce. 
Operations and results during fiscal year. New work: 
Recreational facilities provided at completed project 
amounted to $40,247. Maintenance: Operation and 
maintenance cost $3,205,787. Gross power generation 
amounted to 235,086,000 kilowatt-hours during FY 
1983, of which 230,560,000 were delivered to Southeastern 
Power Administration. Recreational attendance at 
Lake Seminole during CY 1982 totaled 4,018,000 
recreational user days. 
Condition at end of fiscal year. Construction of the 
lock was commenced in 1947, and completed in 1957. 
The lock was opened to navigation in May 1954, and the 
pool was raised to project level in January 1957. The 
first power-generating unit was placed on-the-line on 
February 1, the second on March 1, and the third on 
April 26, 1957. 
40D. SPEWRELL BLUFF LAKE, GA. 
Location. The dam site is on the Flint River in Talbot 
and Upson Counties, Georgia, about nine miles west of 
Thomaston. The lake will extend into Meriwether, 
Pike, and Spalding Counties. 
Existing project. The authorized project provides for: 
a dam 2,475 feet long with maximum height of 211.0 
feet, a 326-foot long gated spillway with six tainter gates 
38 feet high and 45 feet wide, concrete non-overflow 
abutments 1,149 feet across the main channel including 
268 feet for the power intake, with an earth-rock fill dike 
580 feet long to high ground on the left bank, a 420-foot 
saddle dike on the left bank, and a power plant with 
three 50,000-kw units located in the left bank. The 
reservoir would have an area of 13,330 acres at maximum 
power pool elevation of 695 national geodedic 
datum. Usable storage of 241,510 acre-feet would be 
provided for power generation between elevations 665 
and 695 and 195,010 acre-feet would be reserved 
between elevations 695 and 706.5 for flood storage. 
Approved estimated (1983) cost is $411,000,000, of 
which 291,210,000 is for construction and design, and 
$119,790,000 for lands, damages, and relocations. (See 
Table 10-B for authorizing legislation.) 
Local cooperation. Local interest must maintain and 
operate all utility and highway facilities which may be 
relocated or otherwise altered as part of the improvement, 
provide suitable public terminal facilities, and 
hold the United States free from damages. Local agencies 
and organizations have indicated their willingness 
and ability to comply. 
Operations and results during fiscal year. None. 
Condition at end of fiscal year. Construction has not 
been initiated. 
40E. WALTER F. GEORGE LOCK AND 
DAM, AL. AND GA. 
Location. The project is on the Chattahoochee River 
about 75.2 miles above its mouth and about 1.5 miles 
above Fort Gaines, Georgia. (See Geological Survey 
maps for southwest Georgia.) 
Existing project. The authorized project provides for 
a concrete dam, gated spillway, and single-lift lock, with 
earth embankments at either side. The non-overflow 
section of the dam includes a powerhouse and an intake 
structure. The gated spillway is 708 feet long with a fixed 
crest at elevation 163 feet national geodetic datum. The 
10-20

MOBILE, ALABAMA DISTRICT 
two earth embankments, of almost equal lengths, have a 
total length of 12,128 feet, with a crest elevation at 215, 
and a maximum height of about 68 feet. The nonoverflow 
section of the concrete dam is 200 feet long, 
with the deck of the powerhouse section at elevation 
208. The lock, with usable chamber dimensions of 82 
feet by 450 feet, has a lift of 88 feet with the normal 
upper pool elevation at 190. Depths are 13 feet over the 
lower sill and 18 feet over the upper sill at normal pool 
elevation. The underlying foundation is limestone. 
Total reservoir capacity is 934,400 acre-feet, with 244,400 
acre-feet reserved for power. The power installation 
consists of four units of 32,500 kilowatts each, or a total 
of 130,000 kilowatts. The project provides for maintenance, 
including operation and care. The approved 
(1983) cost of rehabilitation work to control seepage is 
estimated to be $16,000,000. (See Table 10-B for authorizing 
legislation.) 
Local cooperation. Local interests must maintain and 
operate all utility and highway facilities which may be 
relocated or otherwise altered as part of the improvement, 
provide suitable public terminal facilities, and 
hold the United States free from damages. Local agencies 
and other organizations have indicated their willingness 
and ability to comply. 
Terminal facilities. Public wharves at Eufaula and 
Phenix City, Alabama, and Columbus, Georgia, are 
considered adequate for existing commerce. 
Operations and results during fiscal year. New work: 
Initiation of construction of cutoff wall under dam to 
correct seepage cost $1,234,848. Recreation facilities 
cost $402,094. Maintenance of the project for operation 
and care was $3,561,801. Gross power generation 
amounted to 568,868,000 during FY 1983, of which 
561,458,000 were delivered to Southeastern Power 
Administration. Recreational attendance during CY 
1982 totaled 6,367,000 recreational user days. 
Condition at end of fiscal year. Construction was 
completed in 1963. The lock was opened to navigation 
in June 1963. The first power generating unit was placed 
on-the-line in March, the second in May, the third in 
September, and the fourth in November 1963. 
40F. WEST POINT LAKE, 
CHATTAHOOCHEE RIVER BASIN, 
GA AND AL 
Location. The damsite is on the Chattahoochee River 
2.8 miles upstream from West Point, Georgia, 201.4 
miles above the mouth of the Chattahoochee River, and 
309.2 miles above the mouth of the Apalachicola River. 
At the full power pool elevation of 635 feet above 
national geodetic datum, the reservoir would lie in 
Troup and Heard Counties, Georgia, and in Chambers 
and Randolph Counties, Alabama (See Geological 
Survey maps of Georgia and Alabama.) 
Existing project. The authorized project provides for 
flood control, power, recreation, fish and wildlife 
development, and streamflow regulation for downstream 
navigation. The project provides for a gravitytype 
concrete dam 896 feet long with earth embankments 
at either end 1,111 feet long on the east end and 
5,243 feet long on the west end. The total length of the 
dam and spillway is 7,250 feet. The main dam consists of 
a concrete non-overflow section, 185 feet long on the 
west side and an earth embankment retaining wall on 
the east side; a gravity concrete spillway 390 feet long, 
including piers and abutments, with six tainter gates, 
each 50 feet by 41 feet. A monolith intake-powerhouse 
section and erection bay 321 feet long is constructed 
directly west and adjacent to the spillway. At the full 
power-pool elevation of 635 the reservoir provides a 
total storage of 605,000 acre-feet of which 307,000 acrefeet 
is usable. During the critical flood season the reservoir 
is operated with maximum power pool elevation at 
625 feet to provide flood storage between elevations 625 
and 635. The initial power installation of 73,375 kilowatts 
consisting of units 1, 2 and 3 were placed in 
operation in March and April, 1975. The ultimate 
installation is 108,375 kilowatts. 
Approved estimated cost of new work (1983) is 
$132,700,000, of which $90,555,000 is for construction 
and design; $19,420,000 for lands and damages; and 
$22,725,000 for relocations. (See Table 10-B for authorizing 
legislation.) 
Local cooperation. None required. 
Operations and results during fiscal year. New work: 
Miscellaneous costs amounted to $9,513. 
Maintenance: Operation and care of the project cost 
$2,952,188. Gross power generation amounted to 
255,033,000 kilowatt-hours during FY 1983 of which 
250,976,000 were delivered to Southeastern Power 
Administration. Recreational attendance during CY 
1982 totaled 4,205,000 recreational user days. 
Condition at end of fiscal year. Construction of the 
project, which was initiated in June 1966, was about 98 
percent complete at the end of the fiscal year. 
41. SCHEDULING FLOOD CONTROL 
RESERVOIR OPERATIONS 
Mobile District monitors flood control operations of 
Alabama Power Company's Weiss, H. Neely Henry, 
and Logan Martin Dams on Coosa River, Alabama, 
and their Lewis Smith Dam on Sipsey Fork (headwaters 
of Black Warrior River, Alabama), for compliance with 
regulation plans prepared in accordance with Public 
Law 436, 83rd Congress, and Federal Power Commission 
licenses. Fiscal year cost for these activities on the 
Weiss, H. Neely Henry, and Logan Martin Dams are 
included under operation and maintenance costs for the 
Alabama-Coosa Rivers. Fiscal year cost for the Lewis 
Smith Dam is included under the overall operation and 
maintenance costs for the Black Warrior-Tombigbee 
Rivers System. 
10-21

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
General Investigations 
42. SURVEYS 
Fiscal year cost was S3,789,648 of which $1,865,124 
was for navigation studies, $457,621 for flood control 
studies, $5,688 for shoreline protection studies, 
$1,208,503 for special studies, $30,877 for special 
investigations, $13,591 for coordination with the Federal 
Energy Regulatory Commission, $2,800 for planning 
assistance to states, $3,589 for National Wild and 
Scenic River System, $5,556 for technical assistance on 
shore and streambank erosion and $196,299 for supplemental 
pre-authorization studies. 
Continuation of planning and engineering for Mobile 
Harbor cost $909,518, and advanced engineering and 
design for the Montgomery to Gadsden, Coosa River 
Channel project cost $2,880,154. 
43. COLLECTION AND STUDY OF 
BASIC DATA 
Collection and study of basic data continued during 
the fiscal year with the initiation of Flood Insurance 
studies, the cost of which was reimbursable by HUD. In 
addition, Flood Plain Management services were performed 
at a cost of $146,264. (See Table 10-M for 
listings of studies completed during FY 1983.) For listing 
of previous reports see page 10-50 Annual Report 
for 1974, page 10-44 of FY 1975 Annual Report, page 
10-46 of FY 1977 Annual Report, and page 10-48 of FY 
1978 Annual Report. 
The National Program for inspection of non-Federal 
dams cost $1,546. 
10-22

MOBILE, ALABAMA DISTRICT 
TABLE 10-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY80 FY81 FY82 FY83 Sept. 30, 1983 
(Contributed Funds) 
5. Biloxi Harbor, Ms. 
(Contributed Funds) 
6. Black Warrior & 
Tombigbee Rivers, 
Al. 
Maint: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Bon Secour River, New Work: 
Al. Approp. 
Cost 
Maint: 
Approp. 
Cost 
(Contributed Funds) New Work: 
Approp: 
Cost 
Cadet Bayou, Ms. New Work: 
(Regular Funds) Approp. 
Maint: 
Approp. 
Cost 
-- - - 2,033,461' 
-- - - 2,033,461' 
56,800 
53,698 
17,000 
18,295 
1. Apalachicola Bay New Work: 
Fl. Approp. 
Cost 
Maint: 
Approp. 
Cost 
2. Aquatic Plant New Work: 
Control Approp. 
(Regular Funds) Cost 
(Contributed Funds) Maint: 
Contrib. 
Cost 
3. Bayou Coden, Al. New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
(Contributed Funds) New Work: 
Contrib. 
Cost 
(Contributed Funds Maint: 
Contrib. 
Cost 
4. Bayou La Batre, Al. New Work: 
(Regular Funds) Approp. 
Cost 
13,400 
6,456 
26,000 
7,436 
17,000 
14,217 
13,000 
8,088 
2,000 
12,690 
51,000 
48,810 
20,400 
26,938 
214,155 
205,111 
50,000 
50,000 
1,300,466 
550,156 
115,281 
225,848 
247,000 
250,984 
24,000 
24,000 
-11,000 
549,453 
11,426,000 
12,149,695 
987,577 
994,121 
84,171 
124,729 
13,014,800 
13,113,823 
84,000 
81,142 
265,000 
152,622 
10,277,901 
9,534,333 
32,000 
55,370 
44,000 
-3,884 
2,364,8072 
2,363,6502 
467,687 
409,558 
- 21,225 
- 21,225 
- 330,7013 
- 330,7013 
25,000 309,533 
15,357 284,846 
- 100,000 
- 100,000 
- 50,000 
- 50,000 
- 311,095 
- 311,095 
4,000 2,446,852 
753,896 2,442,044 
- 10,5004 
- 10,5004 
- 1,215,4363 
- 1,215,436s 
52,000 5,023,1066 
50,089 5,008,6736 
- 102,600 
- 102,600 
704,505 154,516,2427 
195,823 153,731,3347 
14,137,473 139,610,4978 
13,862,619 138,113,5148 
- 118,615 
- 118,615 
28,048 
18,796 
1,700 
2,108 
21,000 
6,400 
39,000 
16,837 
182,101 
175,872 
17,891 
12,000 
32,145 
145,478 
131,954 
9,700 
9,700 
87,921 
705,118 
704,424 
10-23 
7. 
8. 
11,832 
12,899

TABLE 10-A 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY80 FY81 FY82 FY83 Sept. 30, 1983 
(Contributed Funds) New Work: 
Approp. 
Cost 
9. Dauphin Island, Bay,New Work: 
Al. Approp. 
Cost 
Maint: 
Approp. 
Cost 
10. Dog and Fowl New Work: 
Rivers, Al. Approp. 
(Regular Funds) Cost 
Maint: 
Approp. 
Cost 
(Contributed Funds) New Work: 
Contrib. 
Cost 
11. East Pass Channel New Work: 
From Gulf of Approp. 
Mexico into Chocta- Cost 
whatchee Bay, Fl. 
(Regular Funds) Maint: 
Approp. 
Cost 
(Contributed Funds) New Work: 
Approp. 
Cost 
12. Gulf Intracoastal New Work: 
Waterway between Approp. 
Apalachee Bay, Fl. Cost 
and Mexican Border 
Maint: 
Approp. 
Cost 
13. Gulfport Harbor, New Work: 
Ms. Approp. 
Cost 
Maint: 
Approp. 
Cost 
14. Mobile Harbor, Al. New Work: 
Approp. 
Cost 
(Contributed Funds) New Work: 
Approp. 
Cost 
(Regular Funds) Maint: 
Approp. 
Cost 
(Contributed Funds) Maint: 
Approp. 
Cost 
15. Panama City New Work: 
Harbor, Fl. Approp. 
Cost 
Maint: 
Approp. 
Cost 
(Contributed Funds) New Work: 
Contrib. 
Cost 
- 31,000 
- 31,000 
- 292,864 
- 292,864 
231,018 
244,234 
256,800 
257,593 
576,000 
569,269 
3,040,200 
3,002,607 
1,707,000 
1,734,630 
22,700,000 
21,967,612 
1,050,000 
1,037,345 
10,228,000 
8,521,963 
30,577 
34,518 
60,000 
56,245 
12,000 
2,914 
363,000 
362,586 
1,268,000 
1,320,430 
2,981,000 
2,651,941 
23,600,000 
23,730,997 
1,150,000 
1,161,761 
2,053,000 
3,088,041 
118,717 
110,334 
54,000 
26,852 
44,000 
1,385 
926,000 
854,843 
1,673,000 
1,663,687 
1,465,000 
1,126,519 
230,000 
843,794 
850,000 
235,456 
6,294,000 
6,422,224 
1,323,000 
979,049 
38,000 
66,153 
1,020,026 
1,015,543 
- 190,695 
- 190,695 
-32,000 692,593 
16,930 689,742 
- 114,100 
- 114,100 
- 916,715 
- 916,715 
625,000 5,060,160 
606,764 4,962,652 
- 398,000 
- 398,000 
- 6,480,2999 
- 6,480,2999 
2,914,000 33,576,72210 
1,400,841 31,991,94010 
- 904,77511 
- 904,77511 
1,418,000 26,967,50812 
982,529 25,857,06312 
84,000 
723,834 
280,000 
553,146 
68,102,937'3 
68,050,632' 
3,847,500 
3,447,568 
4,793,000 66.166,48314 
2,941,782 63,679,48214 
- 12,000 
- 12,000 
- 1,638,045's 
- 1,638,045'S 
-8,000 
343,829 
5,274,33416 
5.272,97216 
80,000 
80.000 
10-24

TABLE 10-A (Continued) 
See 
Section 
SeScetieon 
MOBILE, ALABAMA DISTRICT 
COST AND FINANCIAL STATEMENT 
Total Cost to 
in Text Project Funding FY80 FY81 FY82 FY83 Sept. 30, 1983 
16. Pascagoula Harbor, New Work: 
Ms. Approp. 
Cost 
(Regular Funds) Maint: 
Approp. 
Cost 
(Contributed Funds) Maint: 
Contrib. 
Cost 
17. Pensacola Harbor, New Work: 
Fl. Approp. 
Cost 
Maint: 
Approp. 
Cost 
18. Perdido Pass New Work 
Channel, Al. Approp. 
Cost 
(Regular Funds) Maint: 
Approp. 
Cost 
(Contributed Funds) New Work: 
Contrib. 
Cost 
Maint: 
Contrib. 
Cost 
19. Port St. Joe New Work: 
Harbor, Fl. Approp. 
Cost 
(Contributing Funds)New Work: 
Contrib. 
Cost 
(Regular Funds) Maint: 
Approp. 
Cost 
20. Removing Water Maint: 
Hyacinths Approp. 
(Mobile District) Cost 
21. Waterway Con- New Work: 
necting Tombigbee Approp. 
& Tennessee Rivers Cost 
Al., and Ms. Maint: 
Approp. 
Cost 
27. Okatibbee Lake, Ms. New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
28. Tallahala Creek New Work: 
Lake, Pascagoula Approp. 
River, Ms. Cost 
29. Burketts Creek, New Work: 
Amory, Ms. Approp. 
Cost 
30. Gordon's Creek, New Work: 
Ms. Approp. 
Cost: 
4,268,500 
4,246,186 
191,000 
175,000 
51,200 
53,248 
261,800 
159,447 
672,794 
664,732 
21,800 
22,859 
124,348,000 
112,719,590 
2,477,000 
2,183,192 
3,000 
546,800 
522,072 
-190,000 
51,263 
64,000 
60,630 
79,594 
2,186,000 
1,451,652 
25,000 
338,268 
315,114 
192,000 
300,028 
53,994 
51,795 
7,000 
972 
108,185,000 
117,448,766 
3,228,000 
3,368,455 
65,000 
31,020 
602,000 
570,387 
190,000 
147,694 
1179,,151373 
-15,000 
10,836 
2,203,174 
2,555,403 
25,000 
67,000 
33,226 
427,000 
413,904 
50,253 
22,315 
49,000 
118,490,000 
118,990,981 
4,624,000 
3,598,169 
14,000 
39,926 
691,000 
573,918 
100,313 
650,000 
98,578 
670 
10-25. 
- 6,572,98517 
- 6,572,9857 
4,143,000 27,794,42018 
1,986,816 25,232,23818 
196,590 665,940 
565 449,115 
- 1,469,693'19 
- 1,469,693'19 
- 4,058,23820 
42,145 4,042,45220 
- 629,860 
- 629,860 
1,271,000 5,014,217 
484,340 4,207,533 
- 510,000 
- 510,000 
- 10,325 
- 10,325 
- 1,960,862 
- 1,960,862 
- 20,000 
- 20,000 
- 2,212,090 
20,501 2,194,196 
-54,000 1,100,471 
- 1,099,266 
120,684,000 838,425,20021 
103,645,625 817,271,19021 
5,474,000 16,776,33122 
5,430,959 15,508,86522 
20,000 9, I 19,628 
22,505 9,111,079 
874,000 5,627,892 
825,795 5,397,594 
- 3,945,757 
60,967 3,920,293 
700,000 1,522,553 
1,074,914 1,340,054 
9,000 784,623 
1,713 775,638

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 10-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section 
SeScetieon 
Total Cost to 
FY80 FY81 FY82 FY83 Sept. 30, 1983 
5,974 
99,038 
450,000 
295,201 
in Text Project 
31. Murder Creek, 
East Brewton, Al. 
32. Sun Creek, 
Oktibbeha County, 
Ms. 
33. Tombigbee River 
Tributaries 
Ms. and Al. 
(Regular Funds) 
(Contributed Funds) 
34. Trim Cane Creek, 
Oktibbeha County, 
Ms. 
38. Alabama-Coosa 
Rivers, Al. and Ga. 
38A. Carters Dam and 
Reservoir, Ga. 
38B. Claiborne Lock and 
Dam, Al. 
38C. Robert F. Henry 
Lock and Dam, Al. 
38D. Millers Ferry Lock 
and Dam, Al. 
38E. Coosa River, 
Montgomery to 
Gadsden, Al. 
39. Allatoona Lake, 
Coosa River Basin, 
Ga. 
40. Apalachicola, 
Chattahoochee, 
and Flint Rivers, 
Al. and Ga. 
Funding 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
215,000 
207,920 
800,000 
1,669,031 
2,350,000 
649,352 
12,190,000 
10,209,325 
10,003,100 
9,565,378 
1,050,000 
1,201,528 
1,860,600 
1,735,269 
1,900,000 
2,127,375 
1,835,000 
1,828,692 
40,000 
18,130 
2,453,000 
2,024,013 
9,200,000 
6,862,288 
582,931 
175,420 
4,006,000 
3,881,048 
1,677,899 
1,471,173 
542,500 
404,471 
55,000 
6,163 
1,495,000 
1,289,170 
120,000 
13,563 
514,522 
454,340 
9,775,000 
9,034,561 
-84,000 
43,083 
2,235,000 
1,952,950 
600,000 
164,544 
1,891,000 
1,843,208 
-1,478 
22,500 
2,302,000 
2,364,854 
244,213 
98,000 
668,140 
4,298,000 
3,996,293 
5,008,973 
2,158,234 
943,474 
798,365 
55,000 
6,163 
12,909,225 
11,446,308 
80,700 
49,752 
120,000 
13,563 
309,690,63023 
308,686,51123 
78,332,45424 
76,276,76524 
111,246,340 
111,139,162 
14,185,800 
13,674,954 
27,997,450 
27,997,450 
83,847,800 
83,108,684 
11,565,778 
11,200,351 
62,725,300 
62,725,300 
20,651,965 
20,115,961 
15,035,400 
14,897,575 
35,543,08525 
35,466,30825 
37,886,523 
36,605,092 
342,193,59326 
338,239,71226 
16,231,700 20,918,300 20,870,960 19,006,000 198,690,36427 
17,203,131 20,154,974 20,440,078 18, 162,136 195,049,40027 
10-26 
3,835,000 
5,939,040 
7,872,700 
7,737,239 
-1,100,000 
150,720 
1,462,800 
1,485,797 
2,799,000 
3,533,201 
1,390,800 
1,319,160 
-14,000 
3,160 
1,866,300 
1,903,222 
2,150,000 
2,251,959 
164,700 
149,422 
3,220,800 
3,231,770 
2,922,000 
3,598,176 
2,651,400 
5,261,664 
9,898,480 
9,549,915 
37,053 
2,010,000 
1,991,853 
2,660,000 
2,703,377 
1,876,000 
1,693,988 
6,000 
4,422 
2,687,480 
2,615,655 
-14,600 
2,516,812 
972,000 
836,857 
3,813,480 
3,070,212 
917,000 
1,101,493

MOBILE, ALABAMA DISTRICT 
TABLE 10-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY80 FY81 FY82 FY83 Sept. 30, 1983 
40A. Lake Sidney New Work: 
Lanier, Ga. Approp. 2,208,000 337,000 386,000 155,782 53,028,53828 
Cost 2,458,356 452,439 502,277 471,532 52,860,82828 
Maint: 
Approp. 3,441,800 4,956,000 5,009,480 5,078,500 43,401,907 
Cost 4,013,988 4,560,430 4,685,414 4,553,188 42,105,307 
40B. George W. Andrews New Work: 
Lock and Dam, Approp.- - - - 13,038,42729 
Al. and Ga. Cost - - - 13,038,42729 
Maint: 
Approp. 30 30 30 30 30 
Cost 30 30o 30o 30 30 
40C. Jim Woodruff Lock New Work: 
and Dam, Ga. and Approp. 12,000 81,348 -3,000 -1,500 48,018,85831 
Fl. Cost -13,246 48,661 19,902 40,247 47,974,1563' 
Maint: 
Approp. 3,152,400 3,099,000 3,049,000 3,062,000 37,555,08 I 
Cost 3,320,360 3,210,277 2,707,678 3,205,787 36,996,858 
40D. Spewrell Bluff Lake New Work: 
Ga.. Approp. - - - - 2,169,600 
Cost - 177 - - 2,158,652 
44E. Walter F. George New Work: 
Lock and Dam, Approp. -7,000 532,551 527,000 4,854,691 93,095,77932 
Al. and Ga. Cost 7,563 216,672 508,510 1,636,942 89,507,86432 
Maint: 
Approp. 2,906,300 5,407,700 6,825,440 3,583,000 44,707,564 
Cost 3,006,667 4,445,259 7,440,475 3,561,801 44,128,261 
40F. West Point Lake, New Work: 
Chattahoochee River Approp. 659,000 500,000- - 129,846,411 
Basin, Ga. and Al. Cost 1,095,949 541,721 51,922 9,513 129,715,788 
Maint: 
Approp. 1,887,700 2,620,000 2,573,000 3,040,500 17,328,300 
Cost 2,332,469 2,596,982 2,452,152 2,952,188 16,989,523 
1. Includes $134,613 for previous projects and $28,500 for DPR 
on Two-Mile. 
2. Includes $168,766 for previous projects. 
3. Includes $5,650 for previous projects. 
4. Cost for providing spoil dikes for work authorized by 1965 
River and Harbor Act. 
5. Includes $44,382 for previous projects of which $5,000 was 
contributed funds. 
6. Includes $96,509 for previous projects of which $10,200 was 
contributed funds. 
7. Includes $606,931 for previous projects and $725,430 for 
recreational facilities on completed projects. 
8. Includes $50,000 for previous projects. 
9. Includes $45,605 for previous projects. 
10. Includes $65,137 for previous projects. 
II. Includes $269,017 for previous projects. 
12. Includes 2,312,297 for previous projects and $442,836 Special 
O and M funds. 
13. Includes $6,683,104 for previous projects, $14,000 Public 
Work funds, and $41,242 Emergency Relief funds. 
14. Includes $4,096,681 for previous projects and $494,136 Special 
O and M funds. 
15. Includes $203,560 for previous projects, $581,959 Public 
Works funds, $457,467 rehabilitation of jetties under existing project 
and $48,001 for Grand Lagoon modification. 
16. Includes $513,604 for previous projects. 
17. Includes $904,442 for previous projects. 
18. Includes $412,624 for previous projects, $124,565 Special O 
and M funds, and $829,472 Emergency Work Funds. 
19. Includes $594,688 for previous projects. 
20. Includes $126,649 for previous projects. 
21. Includes $2,100,000 transferred to National Park Service; 
$210,249 GI funds expended during FY 1957 thru FY 1961. Previous 
project cost amounted to $197,651. 
22. Includes $234,331 for previous projects. 
23. Includes $3,692,483 for previous projects. 
24. Includes $2,978,050 for previous projects. 
25. Includes $3,104,713 for recreational facilities. 
26. Includes $1,883,193 Federal funds, $1,924 contributed funds 
for previous projects; and $809,553 for Lazer Creek design Rysco 
Channel. 
27. Includes $2,246,233 for previous projects. 
28. Includes $8,056,734 for recreational facilities. 
29. Includes $84,014 for recreational facilities. 
30. Included under maintenance for overall Apalachicola, Chattahoochee 
and Flint Rivers project. 
31. Includes $1,511,229 for recreational facilities. 
32. Includes $2,418,266 for recreational facilites. 
10-27

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 10-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Mar. 2, 1907 
Jan. 21, 1927 
Sept. 3, 1954 
Sept. 3, 1954 
July 3, 1958 
Nov. 21, 1963' 
Feb. 5, 1975' 
July 3, 1958 
Oct. 23, 1962 
Oct. 27, 1965 
Mar. 2, 1945 
June 2, 1969' 
Oct. 27, 1965 
APALACHICOLA BAY, FL. (See Section 1 of Text) 
Channel 18 feet deep through West Pass and Link Channels, 
10 feet deep across the inner bar, and 9 feet deep 
through Bulkhead Shoals. 
Modify project to provide for channel 10 feet deep from 
mouth of inner bar channel to Gulf via Link and West 
Pass Channels, and 10-foot depth in Bulkhead Shoals 
Channel. 
At Eastpoint, Fl., a channel 6 feet deep, 100 feet wide, 
and about 6,000 feet long, parallel to shore, with 
connecting channel 6 feet deep and 100 feet wide to St. 
George Sound, and at Apalachicola, Fl., a small-boat 
basin 200 feet and 9 feet deep, with a connecting 
channel 9 feet deep and 80 feet wide through Scipio 
Creek to the Apalachicola River. 
Modify project to provide for a channel 10 feet deep and 
100 feet wide from the 10-foot depth in Apalachicola 
Bay across St. George Island to within 300 feet of the 
Gulf shore, thence increasing uniformly in width to 200 
feet at shore and continuing at this width to the 10-foot 
depth in the Gulf, with two jetties extending from the 
dune line on St. George Island to the outer end of 
channel, and for abandonment of West Pass Channel upon 
completion of channel through St. George Island. 
Modify improvement of Apalachicola Bay, Fl., authorized 
by River and Harbor Act of Sept. 3, 1954 to provide 
that the Secretary of the Army shall reimburse local 
interests for such approved work as they may have done 
based upon the reduction in the amount of material 
which will have to be removed to provide project 
dimensions at such time as Federal dredging of the 
channels is undertaken. 
A channel 6 feet deep, 100 feet wide and about I mile long, 
parallel to shore at Two Mile, Fl., with a 6-by 100-foot 
connecting channel to water of the same depth in 
Apalachicola Bay. 
A channel 6 feet deep and 100 feet wide extending from the 
eastern end of the existing Two Mile channel and 
generally paralleling the shoreline for a distance of 
about 9,000 feet to intersect with the Gulf Intracoastal 
Waterway about 1,650 feet south of Gorrie Bridge at 
Apalachicola, and a breakwater built to elevation 4.0 
feet above mean low water along the seaward side of the 
existing channel parallel to the shore at Two Mile. The 
total length of the breakwater would be about 6,150 
including two 860-foot legs paralleling the existing 
entrance channel. 
AQUATIC PLANT CONTROL (See Section 2 of Text) 
Aquatic plant control for N.C., S.C., Ga., Fl., Al., Ms., 
and La. 
Research and planning costs to be borne by U.S. 
Provided for continued research. 
BAYOU CODEN, AL. (See Section 3 of Text) 
Channel 4 by 40 feet. 
Channel 8 by 60 feet to connect with Bayou La Batre 
channel. 
BAYOU LA BATRE, AL. (See Section 4 of Text) 
A 12- by 100-foot channel from that depth in Mississippi 
Sound to a point about 2,800 feet south of the highway 
bridge, thence a channel 12 by 75 feet to the bridge, an 
overall distance of about 33,500 feet. 
H. Doc. 422, 59th Cong., 
1st Sess. 
H. Doc. 106, 69th Cong., 
Ist Sess. 
H. Doc. 156, 82d Cong., 
Ist Sess. 
H. Doc. 557, 82d Cong., 
2d Sess. 
DPR(Sec. 107) 
DPR(Sec. 107) 
H. Doc. 37, 85th Cong., 
1st Sess. 
Public Law 87-874 
87th Cong. 
H. Doc. 251, 89th Cong., 
Ist Sess. 
H. Doc. 824, 77th Cong., 
2d Sess. 
DPR (Sec. 107) 
H. Doc. 327, 88th Cong., 
2d Sess. 
10-28

MOBILE, ALABAMA DISTRICT 
TABLE 10-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
July 3, 1930 
June 20, 1938 
Mar. 2, 1945 
Mar. 2, 1945 
May 17, 1950 
July 14, 1960 
Nov. 7, 1966 
Mar. 28, 1979' 
July 5, 1884 
Mar. 3, 1899 
Sept. 19, 1890 
Sept. 19, 1890 
Mar. 2, 1907 
Mar. 3, 1909 
Aug. 22, 1911 
Mar. 2, 1919 
BILOXI HARBOR, MS. (See Section 5 of Text) 
Channel 10 feet deep and 150 feet wide from Mississippi 
Sound west and north of Deer Island to deep water in 
Back Bay of Biloxi. 
Relocation of channel. 
Entrance channel 6 feet deep and 50 feet wide into Old 
Fort Bayou. 
Entrance channel 8 feet deep and 100 feet wide through 
Cranes Neck into Bayou Bernard. 
Maintain channel 6 feet deep and 40 feet wide from Biloxi 
Harbor to Ott Bayou. 
Continuous channel 12 feet deep from Mississippi Sound 
the Air Force terminal on Bayou Bernard via Back Bay 
and Cranes Neck. 
A 23-mile-long through channel 12 feet deep and 150 feet 
wide from the Gulf Intracoastal Waterway through: 
Mississippi Sound, Biloxi Bay (east of Deer Island), Back 
Bay, Big Lake, and via land cut to Gulfport Lake, 
including a 500- by 2,600-foot turning basin in the lake, 
thence, a channel 12 by 100 feet from the western end of 
Gulfport Lake for about 2 miles to a 300- by 500-foot 
turning basin; adoption for maintenance of a 12- by 150- 
foot spur channel from the main channel in Biloxi Bay, 
westward about 1 mile to a 400- by 600-foot turning basin 
opposite Ott Bayou, and abandonment of the existing 6- by 
40-foot channel into Ott Bayou; continuation of maintenance 
of the 12- by 150-foot lateral channel westward about 2.2 
miles from the main channel in Biloxi Bay to a point 
opposite Oak Street; continuation of maintenance of the 
channel west of Deer Island. 
A channel 10 feet deep; 100 feet wide and 300 feet 
long extending northward from the Biloxi Lateral Channel, 
and, into a rectangular basin approximately 300 feet 
by 370 feet. 
BLACK WARRIOR AND TOMBIGBEE RIVERS, AL. 
(See Section 6 of Text) 
Original appropriation for improving Black Warrior River. 
Original project for slack-water improvement authorized by 
Secretary of War, Apr. 19, 1887. 
Construction of the first locks between Tuscaloosa and 
Demopolis. 
(Maintenance of the section of Tombigbee River below 
lock I to its mouth (66 miles) included in the existing 
project.) 
Construction of locks and dams 1, 2, and 3. Merging of 
the individual project for the Black Warrior and Warrior 
Rivers and the Tombigbee River below Demopolis. 
Construction of locks and dams 14, 15, 16, and 17. 
Provides for reconstruction of obsolete structures, modified 
in plan and location, to provide efficient and economical 
maintenance and operation. 
Lift of lock 17 changed to 63 feet, and construction of locks 
and dams 18 and 19 eliminated from the project. 
Extension of slack-water improvement to Sanders Ferry 
on Mulberry Fork and Nichols Shoal on Locust Fork. 
Raising of various dams 2 feet and raising the lock walls 2 
feet at lock I to provide a minimum depth of 8 feet at 
H. Doc. 754, 69th Cong., 
2d Sess. 
H. Doc. 639, 75th Cong., 
3d Sess. 
H. Doc. 258, 76th Cong., 
1st Sess. 
H. Doc. 326, 76th Cong., 
1st Sess. 
H. Doc. 256, 81st Cong., 
1st Sess. 
H. Doc. 271, 86th Cong., 
2d Sess. 
H. Doc. 513, 89th Cong., 
2d Sess. 
DPR (Sec. 107) 
Annual Report, 1887, 
pt. 2, p 1302. 
H. Doc. 178, 56th Cong., 
2d Sess., and Annual 
Report, 1901, pt. 3, 
p. 1858 
H. Doc. 165, 57th Cong., 
Ist Sess., and Annual 
Report, 1902, p. 1293 
Public Law 317 
H. Doc. 72, 62d Cong., 
1st Sess. 
Annual Report, 1918, 
p. 876 
10-29

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 10-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
low water, widening the channel to 150 feet where 
practicable. 
Aug. 30, 1935 
Aug. 30, 1935 
Aug. 30, 1935 
June 26, 1934 
Dec. 22, 1944 
Mar. 2, 1945 
Mar. 2, 1945 
July 14, 1960 
Dec. 21, 1982 
July 30, 1983 
May 16, 1963' 
May 20, 1969' 
Mar. 2, 1945 
Sept. 3, 1954 
May 19, 1969' 
July 3, 1930 
For snagging Mobile River from the mouth of Chickasaw 
Creek to the junction of the Alabama and Tombigbee 
Rivers. 
Increase channel dimensions to 9 by 200 feet; construct 
crest gates at lock and dam 17; add flashboards at all 
dams; Sunflower Bend Cutoff. 
Construction of a lock and dam below Tuscaloosa to replace 
original locks and dams 10, I1i, and 12 
Operation and care of locks and dams provided for with 
funds from War Department appropriations for rivers 
and harbors. 
Recreation facilities. 
Construction of a lock and dam near Demopolis to replace 
existing dams 4, 5, 6, and 7. 
Provide increased spillway capacity at dam 1. 
Coffeeville Lock and Dam Wildlife Refuge. 
Provides for a wider navigation opening at the Franklin 
Ferry Bridge, Jefferson County, Al. 
Authorized to widen, as necessary for safe passage, 
the navigation opening of Franklin Ferry Bridge, Jefferson County, Al. 
BON SECOUR RIVER, AL. (See Section 7 of Text) 
A 10- by 100-foot channel from Gulf Intracoastal 
Waterway through Bon Secour Bay to mouth of Bon Secour 
River and extending up river to vicinity of Swift's 
Landing, thence 6 by 80 feet up river to a point 
600 feet above Oak Landing, with two turning and 
maneuvering areas 150 feet wide and 1,100 to 1,200 
feet long opposite Swift's Landing and ice loading 
dock. Overall length of improvement is about 4.7 
miles. 
CADET BAYOU, MS. (See Section 8 of Text) 
An 8- by 100-foot entrance channel extending from the 8-foot 
depth contour in Mississippi Sound to the mouth of the 
bayou, thence an 8- by 80-foot channel for a distance 
of about 1,900 feet into the bayou to a turning basin 
8 feet deep, and a channel continuing therefrom 6 feet 
deep and 60 feet wide upstream for 8,750 feet with a 
second turning basin 6 feet deep located 900 feet downstream 
from the upper limit of the improvement. 
DAUPHIN ISLAND BAY, AL. (See Section 9 of Text) 
A channel 7 feet deep and 150 feet wide from Mobile Bay to 
an anchorage basin of same depth, about 7 acres in area, in 
marsh just north of Fort Gaines on Dauphin Island; a 
channel 4 feet deep and 40 feet wide from anchorage basin 
to Dauphin Island Bay; and a jetty and revetment to protect 
entrance channel; and (b) an anchorage basin 7 feet deep 
and 500 feet square at Dauphin Island Village, with 
an entrance channel of like depth, 100 feet wide and 
about 8,300 feet long, extending to 7-foot hydrographic 
contour in Mississippi Sound. 
DOG AND FOWL RIVERS, AL. (See Section 10 of Text) 
To provide small craft navigation on west side of Mobile Bay. 
EAST PASS CHANNEL FROM GULF OF MEXICO INTO 
CHOCTAWHATCHEE BAY, FL. (See Section 11 of Text) 
Maintenance of 6-foot channel by 100-foot channel from 
Choctawhatchee Bay into Gulf. 
H. Doc. 728, 71st Cong., 
3d Sess. 
H. Doc. 56, 73d Cong., 
Ist Sess., and Rivers 
and Harbors Committee 
Doc.45, 73d Cong. 
Rivers and Harbors 
Committee Doc. 26, 
74th Cong., I1st Sess. 
H. Doc. 276, 76th Cong., 
Ist Sess. 
H. Doc. 382, 76th Cong., 
Ist Sess. 
S. Doc. 50, 86th Cong., 
Ist Sess. 
Public Law 97-377 
Public Law 98-63 
DPR (Sec. 107) 
DPR (Sec. 107) 
H. Doc. 333, 76th Cong., 
Ist Sess. 
H. Doc. 394, 82d Cong., 
2d Sess. 
DPR (Sec. 107) 
H. Doc. 209, 70th Cong., 
1st Sess. 
10-30

MOBILE, ALABAMA DISTRICT 
TABLE 10-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Oct. 24, 1951 
Oct. 27, 1965 
Aug. 26, 1937 
June 25, 1910 
Aug. 30, 1935 
June 25, 1910 
Aug. 30, 1935 
July 3, 1930 
July 3, 1930 
July 3, 1930 
July 23, 1942 
June 17, 1943 
Mar. 2, 1945 
May 17, 1950 
Nov. 7, 1966 
Mar. 3, 1899 
Mar. 2, 1907 
Maintenance of 12-foot channel from Choctawhatchee Bay 
into Gulf, and maintenance of 6-foot channel into Old 
Pass Lagoon. 
Construction of twin jetties. 
(Present project dimensions.) 
GULF INTRACOASTAL WATERWAY BETWEEN 
APALACHEE BAY, FL., AND MEXICAN BORDER 
(Mobile District) (See Section 12 of Text) 
APALACHICOLA BAY TO ST. MARKS RIVER, FL. 
A channel 9 feet deep and 100 feet wide at mean low water 
from Apalachicola Bay, Fl., via St. George Sound, 
Carrabelle, Crooked, and Ochlockonee Rivers and 
Ochlockonee and Apalachee Bays to St. Marks River, Fl. 
APALACHICOLA RIVER TO ST. ANDREW BAY, FL. 
A channel 5 feet deep at mean low water and 65 feet 
wide at the bottom. 
A channel 9 feet deep at mean low water and 100 feet 
wide at the bottom. 
CHOCTAWHATCHEE BAY TO WEST BAY, FL. 
A channel 9 feet deep at mean low water and 100 feet wide 
at the bottom. 
A channel 6 feet deep at mean low water, with no 
reference to width. 
CHOCTAWHATCHEE BAY TO PENSACOLA BAY, FL. 
A channel 9 feet deep at mean low water and 100 feet 
wide at the bottom. 
PENSACOLA BAY, FL., TO MOBILE BAY, AL. 
A channel 9 feet deep at mean low water and 100 feet 
wide at the bottom. 
MOBILE BAY, AL., TO NEW ORLEANS, LA. 
A channel 300 feet wide and 10 feet from the 10 
foot contour in Mobile Bay to the 10-foot contour 
in Mississippi Sound. 
A channel 100 feet wide and 9 feet deep from Lake 
Pontchartrain to Mississippi Sound. 
APALACHEE BAY, FL., TO NEW ORLEANS, LA. 
A channel 12 feet deep and 125 feet wide at mean low 
water, except in the section between Mobile, Al., 
and New Orleans, La., where the width is to be 
150 feet. 
Conditional acquisition of Gulf County Canal, Fl. 
and enlargement of the canal to 9 feet deep and 100 
feet wide. 
Construction of a movable span in the Georgia, Florida 
& Alabama R.R. bridge crossing the Ochlockonee River. 
Abandonment and closure of original channel between 
Big Lagoon and Pensacola Bay and construction of a 
new channel to enter the bay north of original 
entrance. 
Authorized enlargement of Gulf County Canal to 12 by 
125 feet. 
GULFPORT HARBOR, MS. (See Section 13 of Text) 
A channel 19 feet deep and 300 feet wide from the 
anchorage basin at Ship Island to Gulfport, Ms., and an 
anchorage basin next to the shore end 19 feet deep and not 
less than 2,640 feet by 1,320 feet in area. 
Combined Ship Island Pass with Gulfport Harbor project. 
H. Doc. 470, 81st Cong., 
2d Sess. 
H. Doc. 194, 88th Cong., 
2d Sess. 
H. Doc. 291, 75th Cong., 
Ist Sess. 
H. Doc. 670, 61st Cong., 
2d Sess. 
Rivers and Harbors 
Committee Doc. 52, 
72d Cong., 2d Sess. 
H. Doc. 259, 72d Cong., 
1st Sess. 
H. Doc. 565, 61st Cong., 
2d Sess. 
Rivers and Harbors 
Committee Doc. 42, 
73d Cong., 2d Sess. 
H. Doc. 42, 71st Cong., 
1st Sess. 
Rivers and Harbors 
Committee Doc. 4, 
71st Cong., Ist Sess. 
H. Doc. 341, 71st Cong., 
2d Sess. 
Public Law 675, 77th 
Cong., 2d Sess., and 
H. Doc. 96, 79th 
Cong., Ist Sess. 
H. Doc. 257, 76th Cong., 
1st Sess., and Public 
Law 75, 78th Cong. 
1st Sess. 
H. Doc. 442, 76th Cong., 
1st Sess. 
H. Doc. 325, 81st Cong., 
Ist Sess. 
Public Law 89-789, 89th 
Cong. 2d Sess. 
H. Doc. 120, 55th Cong., 
3d Sess. 
10-31

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 10-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Feb. 27, 1911 
Jan. 21, 1927 
July 23, 1930 
June 30, 1948 
July 3, 1958 
Aug. 26, 1937 
Mar. 2, 1945 
Sept. 3, 1954 
Sept. 3, 1954 
July 26, 1970 (SR) 
Dec. 15, 1970 (HR) 
Aug. 30, 1935 
Mar. 2, 1945 
10-32 
Increased depth to 26 feet and width to 300 feet across 
Ship Island Bar and depth to 19 feet in channel from 
anchorage basin at Ship Island to anchorage basin at 
Gulfport. 
Authorized relocation of channel across Ship Island Bar. 
Increased depth to 27 feet and width to 300 feet across 
Ship Island Bar, 26 feet deep and 220 feet wide through 
Ms. Sound and depth of 26 feet in the anchorage basin 
at Gulfport. 
Increased depth of 32 feet and width to 300 feet across 
Ship Island Bar, 30 feet deep and 220 feet wide through 
Ms. Sound, and a depth of 30 feet in the anchorage 
basin at Gulfport. 
Maintenance of the existing commerccial small-boat harbor 
and an approach channel 100 feet wide and 4,300 feet 
long, from deep water in Ms. Sound to the small-boat 
basin, all at a depth of 8 feet. 
MOBILE HARBOR, AL. (See Section 14 of Text) 
For improvement of Threemile Creek by snagging from 
Mobile River to the Industrial Canal. 
Adoption of existing channel through Garrows Bend from 
Choctaw Point to Arlington pier, 27 feet deep and 150 
feet wide, with 2 turning basins. Adoption of the 
existing channel alongside Arlington pier from the 
Mobile Bay Channel to turning basin at the inner end 
of Garrows Bend Channel, 27 feet deep and 150 feet wide. 
A channel 25 feet deep and generally 500 feet wide in 
Mobile River from the highway bridge to the mouth of 
Chickasaw Creek, then 25 feet deep and 250 feet wide in 
Chickasaw Creek to a point about 400 feet below Shell 
Bayou. 
Enlarging Mobile Bar Channel to 42 by 600 feet, 
Enlarging Mobile Bay Channel to 40 by 400 feet. 
Deepening Mobile River Channel below highway bridge to 
40 feet over present widths, including existing 
turning basins and anchorage areas. Widening river 
channel opposite Magazine Point to provide a 40- by 800- 
by 1,400-foot turning basin. The turning basin was 
further modified for maintenance by SAD letter of 
27 November 1973 under authority contained in 
ER-1130-2-307 to increase the turning basin's 
dimensions to 1000' x 1600'. 
Closure of Garrows Bend Channel by construction and 
operation of an earth-filled causeway across said channel 
(work to be done by local interests). 
To provide a channel 40 feet deep and 400 feet wide from 
the main ship channel in Mobile Bay and extending 
northwesterly for about 5.3 miles to the shore of Mobile 
Bay including an anchorage and turning basin 
near the shoreline, thence a land-cut 40 feet deep, 300 feet 
wide and about 1.9 miles long to and including a 
trapezoidal turning basin 40 feet deep and 
approximately 42 acres, 40 feet deep; a barge 
channel 12- by 100-feet extending 6500-feet 
and terminating in a 300-foot by 300-foot 
terminal basin. 
PANAMA CITY HARBOR, FL. (See Section 15 of Text) 
Channels 27 and 29 feet deep. Abandonment of project 
adopted by act of June 25, 1910. 
Maintenance of a channel in Watson Bayou 100 feet wide 
and 10 feet deep from that depth in St. Andrew Bay to 
the highway bridge. 
H. Doc. 2, 60th Cong., 
1st Sess. 
H. Doc. 692, 69th Cong., 
2d Sess. 
H. Doc. I112, 81st Cong., 
Ist Sess. 
S. Doc. 123, 84th Cong., 
2d Sess. 
Rivers and Harbors 
Committee Doc. 69, 
74th Cong., I1st Sess. 
H. Doc. 739, 79th Cong., 
2d Sess. 
H. Doc. 74, 83d Cong., 
1st Sess. 
H. Doc. 74, 83d Cong., 
2d Sess. 
(Under provision of 
Section 201 of the 
1965 Flood Control 
Act) 
H. Doc. 33, 73d Cong., 
1st Sess. 
H. Doc. 555, 76th Cong., 
3d Sess.

MOBILE, ALABAMA DISTRICT 
TABLE 10-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Athilor Documents 
June 30, 1948 
Mar. 23, 1967' 
June 14, 1972 
Mar. 4, 1913 
Mar. 4, 1915 
May 17, 1950 
Sept. 3, 1954 
July 3, 1958 
July 14, 1960 
July 14, 1967 
Oct. 23, 1962 
June 13, 1902 
Aug. 30, 1935 
Aug. 26, 1937 
Mar. 2, 1945 
Aug. 27, 1962 
Channels 32 and 34 feet deep. 
A channel 8 by 100 feet in Grand Lagoon from St. Andrew 
Bay to a point about 2,400 feet east of State Highway 
392. Bridge with branches to serve shore facilities 
which terminate at the bridge. 
Channels 38, 40, 42 feet deep. 
PASCAGOULA HARBOR, MS. (See Section 16 of Text) 
Provides for through channel from the Gulf to mile 4 on 
Dog River, 25 by 300 feet through Horn Island Pass, 
thence 22 by 225 feet across Mississippi Sound and up 
Pascagoula River to the railroad brid'e, thence 22 by 
150 feet in Pascagoula River above bridge, and up Dog 
River to mile 4, all subject to financial participation 
by local interests. 
Waived requirement for financial participation by local 
interests. 
Cutoff channel, 12 by 125 feet, from State Highway 63 
bridge to mile 4 on Dog River, via Robertson and 
Bounds Lakes. 
Modification to provide for channel dimensions of 35 by 
325 feet through Horn Island Pass, thence 30 by 275 feet 
across Mississippi Sound and up Pascagoula River to the 
railroad bridge, and a turning basin just below the 
bridge. 
Reimbursement of local interests for work done on Dog 
River cutoff ($44,000). 
Modification to provide for maintenance of 12- by 125-foot 
channel to mile 6 on Dog River, and maintenance of 30- by 
225-foot side channel from main ship channel in 
Mississippi Sound to the mouth of Bayou Casotte, thence 
30 by 300 feet in Bayou Casotte to a turning basin of the 
same depth I mile above the mouth. 
Deepening the Horn Island Pass channel to 38 feet and 
deepening the main ship channel in Mississippi Sound, 
the river channel to the railroad bridge, and the 
turning basin all to 33 feet. 
Enlarging Horn Island Pass Channel to 40 by 350 feet 
provision of an impounding area adjacent to and east of 
channel 40 feet deep, 200 feet wide, and about 1,500 feet 
long, enlarging main channel in Mississippi Sound and 
river channel to railroad bridge to 38 by350 feet, and 
deepening turning basin in river and Bayou Casotte 
channels and basin to 38 feet. 
PENSACOLA HARBOR, FL. (See Section 17 of Text) 
A channel 30 feet deep at mean low water and 500 feet 
wide from the Gulf of Mexico to the dock line at the 
east end of the city of Pensacola, and also provided 
that $150,000 may be used in constructing or purchasing 
a seagoing suction dredge. 
Modified the existing project for the present inner 
channels and the deepenmng of the entrance channel 
to 32 feet. 
Improvement of Bayou Chico. 
Modified improvement of Bayou Chico, Fl. 
Maintenance of the entrance channel from the Gulf of 
Mexico to lower Pensacola Bay, a distance of about 5 
miles to dimensions of 35 feet deep and 500 feet wide; 
H. Doe. 559, 80th Cong., 
2d Sess. 
DPR (Sec. 107) 
H. Doc. 196, 92d Cong., 
2d Sess. 
H. Doc. 682, 62d Cong., 
2d Sess. 
River and Harbor 
Committee Doc. 12, 
63d Cong., 2d Sess. 
H. Doc. 188, 81st Cong., 
Ist Sess. 
H. Doc. 98, 86th Cong., 
lit Sess. 
H. Doc. 98, 86th Cong., 
Ist Seas. 
Chief of Engineers Report 
dated Nov. 3, 1960. 
H. Doc. 560, 87th Cong., 
2d Sess. 
H. Doc. 253, 72d Cong., 
Ist Sess. 
Rivers and Harbors 
Committee Doc. 96, 
74th Cong., 2d Seas. 
H. Doc. 743, 79th Cong., 
2d Sess. 
H. Doc. 528, 87th Cong., 
2d Sess. 
10-33

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 10-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
maintenance of a channel along the south side of the 
aircraft carrier mooring basin, a distance of about 2.5 
miles, to dimensions of 33 feet deep and 300 feet wide; 
a bay channel 33 feet deep, 300 feet wide, and about 2.1 
miles long; parallel approach channels to opposite ends 
of the inner-harbor channel, about 1.3 and 1.4 miles in 
length, each 33 feet deep, 300 feet wide, and flared at 
the junctions with the inner-harbor channel; and 
deepening the existing 500-foot wide inner-harbor channel 
to a depth of 33 feet and lengthening it to 3,950 feet. 
PERDIDO PASS CHANNEL, AL. (Section 18 of Text) 
A 12- by 150-foot channel stabilized by twin rubblemound 
jetties, from the Gulf of Mexico into Perdido Pass, 
thence 9 by 100 feet into Perdido Bay with a spur channel 
of the same dimensions into Terry Cove. 
PORT ST. JOE, FL. (See Section 19 of Text) 
A channel 24 feet deep and 300 feet wide across 
the bar at the entrance to the bay. 
An entrance channel 300 feet wide and 29 feet 
deep, and a bay channel 200 feet wide and 27 feet deep, 
with a turning basin at the proposed municipal pier 
at Port St. Joe. 
Adoption of south channel 27 feet deep 
and 200 feet wide from bay to turning basin, provision 
of a 32- by 300-foot entrance channel, a 32- by 200-foot 
north bay (inner) channel, and a 32- by 1,000-by 
2,000-foot turning basin. 
Enlargement of the channel to provide for a depth of 37 
feet and a width of 500 feet at the Gulf end, diminishing 
in width to 400 feet over a distance of 3.6 miles, 
thence 37 by 400 feet over a distance of 3.3 miles 
thence 35 by 300 feet in St. Joseph Bay to the 
turning basin, a distance of 7.1 miles, and a harbor 
channel in the basin 35 feet deep, 250 feet wide, and 
2,000 feet long. 
REMOVING WATER HYACINTHS, MOBILE DISTRICT 
(See Section 20 of Text) 
Appropriations made for the States of Florida and Louisiana 
and provided for the extermination or removal of plants, 
the building of boats, and the establishment of booms. 
Appropriation made for Florida, provided that no chemical 
process injurious to cattle shall be used. 
And also made available for use in that State the 
operating plan pertaining to the work of Louisiana. 
Appropriation made available for the State of Alabama. 
WATERWAY CONNECTING TOMBIGBEE AND 
TENNESSEE RIVERS, AL. AND MS. 
(See Section 21 of Text) 
A waterway connecting Tennessee and Tombigbee Rivers via 
East Fork of Tombigbee River, Mackeys and Yellow Creeks. 
Plan of improvement consists of three sections: river 
section, 9- by 300-foot channel for 149 miles between 
Demopolis and Amory, Ms.; canal section, 12 by 300 
feet for 46 miles from Amory to Bay Springs: divide section 
12 by 300 feet (except in the 27 mile-long divide cut in 
which bottom width would be 280 feet) for 39 miles from 
Bay Springs through dividing ridge to Tennessee. Total 
lift of 341 feet to be accomplished by 10 locks. Total 
length of project is 234 miles. 
OKATIBBEE LAKE, MS. (See Section 27 of Text) 
Provides for a dam and reservoir for flood control, 
water supply, water quality control, and recreation. 
Oct. 27, 1965 
July 25, 1912 
Aug. 26, 1937 
Mar. 2, 1945 
Sept. 3, 1954 
Mar. 3, 1899 
Mar. 2, 1907 
July 27, 1916 
July 24, 1946 
Oct. 23, 1962 
10-34 
S. Doc. 94, 88th Cong., 
2d Sess. 
H. Doc. 660, 62d Cong., 
2d Sess. 
Rivers and Harbors 
Committee Doc. 10, 
6th Cong., Ist Sess. 
S. Doc. 17, 77th Cong., 
1st Sess., and report 
of Chief of 
Engineers. 
H. Doc. 595, 81st 
Cong., 2d Sess. 
H. Doc. 91, 55th Cong., 
Ist Sess. 
H. Doc. 486, 79th Cong., 
2d Sess. 
H. Doc. 549, 87th Cong., 
2d Sess.

MOBILE, ALABAMA DISTRICT 
TABLE 10-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
June 7, 1968 
Nov. 6, 1981 
Feb. 20, 19772 
February 17, 19823 
Oct. 22, 19823 
July 23, 1958 
July 8, 1980 
Oct. 22, 19822 
Mar. 2, 1945 
June 28. 1954 
May 25. 1982 
Aug. 18, 1941 
Dec. 22. 1944 
TALLAHALA CREEK LAKE, PASCAGOULA RIVER, 
MS. (See Section 28 of Text) 
Provides for a dam and reservoir for flood control, water 
supply, water quality control, recreation, and fish and 
wildlife enhancement. 
BURKETTS CREEK, AMORY, MS. 
(See Section 29 of Text) 
Provides for an earth filled diversion structure with side 
slopes of one vertical on three horizontal, and, a 60 foot 
bottom width canal about 4,000 feet long to connect Burketts 
Creek to Lock A pool of the Tennessee-Tombigbee Waterway. 
In addition, provisions were made for a concrete baffled chute 
with a rip rap blanket along its toe. 
GORDON'S CREEK, HATTIESBURG, MS. 
(See Section 30 of Text) 
Flood control improvements along Gordon's Creek consisting of 
channel enlargement by excavation to a bottom width of 40 
feet for a distance of 6,489 feet, and, clearing and 
snagging of an additional 5,831 feet for a total project 
length of 12,320 feet. 
MURDER CREEK, EAST BREWTON, AL. 
(See Section 31 of Text) 
Provides for nonstructural measures for the reduction of flood 
damages by flood plain evacuation and flood proofing of selected 
buildings along the left bank of Murder Creek. 
SUN CREEK, OKTIBBEHA COUNTY, MS. 
(See Section 32 of Text) 
Provides for removal of accumulated logs, 
debris, and sediment. 
TOMBIGBEE RIVER TRIBUTARIES, MS. AND AL. 
(See Section 33 of Text) 
Provides for improvement of 22 tributaries of Tombigbee 
River. 
Extends project limits on Twenty Mile Creek and 
eliminates local cooperation for this remedial work. 
TRIM CANE CREEK, OKTIBBEHA COUNTY, MS. 
(See Section 34 of Text) 
Provides for removal of accumulated logs, 
debris, and sediment. 
MULTIPLE PURPOSE PROJECTS INCLUDING POWER 
ALABAMA-COOSA RIVERS, AL. AND GA. (See Section 
38 of Text) 
Provides for full development of Alabama-Coosa Rivers 
and tributaries for navigation, flood control, 
power, recreation, and other purposes. 
Authorized construction of Carters Lake, Ga. 
Claiborne Lock and Dam, Al., Jones Bluff Lock 
and Dam, Al., and Millers Ferry Lock and Dam, Al. 
Suspended comprehensive plan to permit non-Federal 
interests to develop Coosa River by constructing 
series of dams. 
Designated change of name from Jones Bluff to 
Robert F. Henry Lock and Dam. 
ALLATOONA LAKE, COOSA RIVER BASIN, GA. 
(See Section 39 of Text) 
Provides for dam and reservoir for flood control, regulation 
of stream flow for navigation, development of hydroelectric 
power and recreation. 
H. Doc. 143, 90th Cong., 
Ist Sess. 
DPR (Sec. 205) 
DPR (Sec. 205) 
DPR (Sec. 208) 
H. Doc. 167, 84th Cong., 
1st Sess. 
PL (96-304) 
DPR (Sec. 205) 
H. Doc. 414, 77th Cong., 
Ist Sess. 
Public Law 436, 83rd 
Cong. 
S.2034 97th 
Cong., 2d Sess. 
Public Law 228, 77th 
Cong., Ist Sess. 
H. Doc. 674. 76th Cong., 
3d Sess. 
10-35

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 10-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
APALACHICOLA, CHATTAHOOCHEE, AND FLINT 
RIVERS, AL., GA. AND FL. (See Section 40 of Text) 
Mar. 2, 1945 Development of Apalachicola, Chattahoochee, and Flint H. Doc. 324, 7th Cong., 
Rivers for navigation, flood control, hydropower, and I1st Sess. 
recreation. 
July 24, 1946 Modified general plan for full development of H. Doc. 300, 80th Cong., 
Apalachicola, Chattahoochee, and Flint River System Ist Sess. 
and authorized construction of Lake Sidney Lanier 
multipurpose reservoir. 
Dec. 22, 1944 Authorized recreation facilities. 
Jan. 27, 1981' Modified the existing project to provide for DPR (Sec. 107) 
nine foot deep by I 00-foot wide side channel 
into the Apalachicola River Industrial Park, 
Blountstown, Fl. 
LAKE SIDNEY LANIER, GA. (See Section 40A of Text) 
July 24, 1944 Provision of recreation facilities. 
GEORGE W. ANDREWS LOCK AND DAM, AL. AND GA. 
(See Section 40B of Text) 
July 24, 1946 Construction of high dam at Walter F. George site H. Doc. 300, 80th Cong., 
and low dam at George W. Andrews site. Ist Sess. 
Dec. 22, 1944 Provided recreation facilities. 
JIM WOODRUFF LOCK AND DAM, GA. AND FL. 
(See Section 40C of Text) 
Dec. 22, 1944 Provided recreation facilities. 
SPEWRELL BLUFF LAKE, GA. (See Section 40D of Text) 
Dec. 30, 1965 Authorized construction. H. Doc. 567, 87th Cong., 
2d Sess. 
WALTER F. GEORGE LOCK AND DAM, AL., AND GA. 
(See Section 40E of Text) 
May 19, 1953 Authorized construction of high dam at Walter F. George H. Comm. on 
site and low dam at Columbia site. Public Works 
WEST POINT LAKE, CHATTAHOOCHEE RIVER 
BASIN, GA. AND AL. (See Section 40F of Text) 
October 23, 1963 Authorized construction for flood control, power H. Doc. 570, 87th Cong., 
recreation, fish and wildlife development, and 2d Sess. 
streamfiow regulation for downstream navigation. 
I. Authorized by Chief of Engineers under Section 107 of 1960 Control Act of 1948. 
River and Harbor Act. 3. Authorized by Chief of Engineers under Section 208 of Flood 
2. Authorized by Chief of Engineers under Section 205 of Flood Control Act of 1954. 
10-36

MOBILE, ALABAMA DISTRICT 
TABLE 10-C BLACK WARRIOR AND TOMBIGBEE RIVERS, ALA. 
(See Section 6 of Text) 
William John Hollis 
Coffeeville Demopols Warrior Bacon Oliver Holt Bankhead 
Lock Lock Lock Lock Lock Lock 
and Dam and Dam and Dam and Dam and Dam and Dam' 
Miles above Mobile 2 116.7 213.2 261.1 338.2 347.0 365.5 
Nearest town (Alabama) Coffeeville Demopolis Eutaw Tuscaloosa Tuscaloosa Oak Grove 
Distance (miles) 3)within city) 6 15 
Lock: 
Greatest length available 
for full width (feet) 600.0 600.0 600.0 450.0 600.0 600.0 
Width of chamber (feet) 110 110 110 95 110 110 
Maximum lift (feet) 34 40 22 28 64 68 
Depth over sills at low 
water (feet) 13.0 13.0 13.2 12.0 13.0 14.0 
Character of foundation Rock Rock Sand, clay Hard shale Shale, Sandstone 
sandstone 
Kind of spillway Fixed-Gated Fixed Gated Fixed Gated Gated 
Type construction 
Lock Concrete Concrete Concrete Concrete Concrete Concrete 
Dam Concrete Concrete Earth- Concrete Concrete Concrete 
Concrete 
Year completed 1965 1962 1962 1940 1969 Under const. 
Year opened to navigation 1960 1954 1957 1939 1966 1975 
Actual cost of lock and dam $21,597,2643 $19,774,5833 $l3,295,5533 $4,450,874 S28,100,0003 $49,828,6724 
I. Single lift lock. 4. Cost to date (FY 83) for replacement of single lift lock which 
2. Navigation mileage from foot of Government Street, Mobile, was essentially completed in FY 80. Excludes $1,435,636cost of land 
Al. submerged, damage to structures, and cost of spillway. Also 
3. Excludes cost of adding recreation facilities, excludes $3,824,859 cost of original double lift lock. 
TABLE 10-D RECONNAISSANCE AND CONDITION SURVEYS 
(See Section 22 of Text) 
Cost During 
Project Date of Survey Fiscal Year 
Blackwater River, FL. 
Carrabelle Harbor, FL. 
Escambia Bay, FL. 
Fly Creek, AL. 
Grand Lagoon, Panama City, FL. 
LaGrange Bayou, FL. 
Panacea Harbor, FL. 
Pass Christian, MS. 
St. Mark's River, FL. 
Wolf and Jordan Rivers, MS. 
January, 1983 
July, 1983 
August, 1983 
April, 1983 
September, 1983 
September, 1983 
July, 1983 
August, 1983 
July, 1983 
May, 1983 
Total 
10-37 
$ 4,725 
6,028 
14,385 
3,371 
258 
2,324 
1,505 
11,963 
6,243 
6,111 
$56,913

TABLE 10-E 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
OTHER AUTHORIZED NAVIGATION PROJECTS 
(See Section 23 of Text) 
For Last Cost to September 30, 1983 
Full Report 
See Annual Operation and 
Report For Construction Maintenance 
Blackwater River, Fl. 1981 $41,650 $266,368 
Bluff Creek, Ms.' 1963 1,000 6,883 
Bon Secour River, Al.2 1979 I 18,615 91,194 
Cahaba River, Al.2 1894 45,000- 
Carrabelle Bar and Harbor, Fl. 1979 481,627 379,413 
Choctawhatchee River, Fl. and Al. 1973 171,885 291,694 
Escambia-Conecuh Rivers, Al. and Fl. 1981 208,499 1,092,223 
Fly Creek, Al. 1981 29,000 200,250 
Holmes Creek, Fl. 1931 8,562 36,800 
LaGrange Bayou, Fl. 1972 289,496 78,974 
Leaf and Chickasawhay River, Ms.2 1919 23,090 42,676 
Noxubee River, Ms.' 1902 47,528 14,472 
Ochlockonee (Ochlockney) River, Ga. and Fl.' 2 1900 5,000- 
Old Town Creek, Ms.' 2 1887 3,000- 
Oostanaula and Coosawattee River, Ga.' 2 1907 32,656- 
Panacea Harbor, Fl. 1979 122,383 92,352 
Pascagoula River, Ms. 1956 15,000 179,535 
Pass Christian Harbor, Ms. 1976 59,313 139,653 
St. Marks River, Fl. 1965 1,710,809 84,115 
Tallapoosa River, Al.2 1893 43,972 - 
Upper Chipola River, Fl., from Marianna to 
its mouth' 2 1941 36,781 63,193 
Wolf and Jordan Rivers, Ms. 1979 29,195 461,515 
1. Abandonment recommended in H. Doc. 467, 69th Cong. 96-157, 1st Session. 
2. Uncompleted portion of project deauthorized by H. Doc. 
TABLE 10-F NAVIGATION WORK UNDER SPECIAL AUTHORIZATION 
(See Section 24 of Text) 
Fiscal Year 
Study Authority 1983 Costs 
Bayou Cumbest, Jackson County, MS 107 $ 6,284 
Biloxi Harbor, East Harrison County Canal, MS 107 13,180 
Carrabelle Harbor, FL 107 21,673 
Dog River Channel, AL 107 20,554 
East Point, Breakwater, FL 107 27,108 
GIWW to Port Bienville, FL 107 10,843 
Lake Krebs, MS 107 31,100 
Old Pass Lagoon, FL 107 6,429 
Shell Point, Wakulla County, FL 107 64,042 
Liza Jackson State Park, Ft. Walton, FL 103 14,473 
Total $244,307' 
1. Excludes construction costs of $273,355 for East Point Break- and $80,031 for Bayou Texar, FL, including $60,000 contributed 
water, FL; $34,040 for Lake Krebs, MS under Section 107 authority funds under Section 3 authority. 
10-38

MOBILE, ALABAMA DISTRICT 
TABLE 10-G OTHER AUTHORIZED BEACH EROSION CONTROL PROJECT 
(See Section 25 of Text) 
For Last Cost to September 30, 1983 
Ful Report 
See Annual Operation and 
Report For Construction Maintenance= 
Harrison County, Ms., shore protection' 1953 S1,133,000 
i. Completed. 
2. Operation and maintenance is the responsibility of local 
interests. 
TABLE 10-H DEAUTHORIZED PROJECTS 
(See Section 26 of Text) 
Year of Last Desuthorization Date 
Project Type Full Report Document' Deauthorized 
Bayou Galere, Miss. Navigation 1946 H. Doc. 192, 94th Cong., 5 Aug. 1977 
1st Sess., as amended. 
1. H. Doc. 96-157 deauthorized uncompleted portions of 
certain projects as shown in Table 10-E. 
TABLE 10-I OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(See Section 36 of Text) 
For Last Cost to September 30, 1983 
Full Report 
See Annual Operation and 
Report For Construction Maintenance 
Alabama River at Montgomery, Al.' 1965 $144,194 2 
Armuchee Creek, Ga. 1966 115,547 -2 
Beaver Creek, Montezuma, Ga. 1958 149,815 -2 
Black Creek, Gadsden, Al. 1953 125,389 -2 
Clanton, Al. 1964 274,024 -2 
Collinsville, Al. 1940 71,119 .2 
Houlka Creek, Chickasaw & Clay Counties, Ms. 1982 238,219 -2 
Jackson and East Jackson, Ms. 1979 7,190,200 -2 
Lake Douglas, Decatur County, Ga. 1970 164,998 .2 
Little Cove Creek, Glencoe, Al. 1965 113,849 -2 
Murder and Burnt Corn Creeks, Brewton, Al. 1980 190,974 -2 
Prattville, Autauga Creek, Al. 1946 649,280 -2 
Rome, Coosa River, Ga. 1955 384,550 -2 
Sowashee Creek, Meridian, Ms. 1956 142,637 -2 
Tombigbee River, Ms. and Al. 1982 134,801 1,226,086 
Town Creek, Americus, Ga. 1965 340,409 -2 
Trussville, Al. 1965 141,334 2 
West Point, Chattahoochee River, Ga. 1955 599,637 -2 
Yellow Jacket Creek, Hogansville, Ga. 1966 330,734 . -2 
1. Engineering, design, supervision, and administration (no construction 
work has been done. Includes $17,000 for preauthorization 
studies. 
2. Operation and maintenance is the responsibility of local 
interests. 
10-39

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 10-J FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION 
(See Section 37 of Text) 
Study Authority Fiscal Year Costs 
Bayou Sara, Saraland, Al. 205 $18,884 
Choctawhatchee River, Daleville, Al. 205 7,487 
Conecuh River, Union Springs, Al. 205 4,682 
Cribbs Mill Creek, Tuscaloosa, Al. 205 56,277 
Eslava Creek, Mobile, Al. 205 21,442 
Greens Creek, Petal, Ms. 205 21,457 
Mill Creek, Dalton, Ga. 205 103,150 
Norton Creek, Saraland, Al. 205 22,667 
Orange Grove Community, Ms. 205 85,775 
Patton Creek, Hoover & Vestavia, Al. 205 7,446 
Sellers Creek, Mendenhall, Ms. 205 30,300 
Silver Creek, Rome, Ga. 205 60,149 
Sope Creek, Marietta, Ga. 205 6,533 
Threemile Creek, Mobile, Al. 205 -565 
Upper Gordons Creek, Hattiesburg, Ms. 205 114,641 
Lorraine Road, Biloxi River, Lorraine, Ms. 14 582 
Wastewater Treatment Plant, Emerson, Ga. 14 19,802 
Total $580,709' 
I. Excludes construction costs of $1,074,914 for Burketts Creek, 
Amory, Ms; $404,471 for East Brewton, Al.: $1,713 for Gordons 
Creek, Ms.; $13,563 for Trim Cane Creek, Oktibbeha County, Ms.; 
and $6,163 for Sun Creek, Ms. 
10-40

MOBILE, ALABAMA DISTRICT 
TABLE 10-K ALABAMA-COOSA RIVERS, ALA. AND GA. 
DEVELOPMENT PROPOSED UNDER EXISTING PROJECT 
(See Sections 38 and 39 of Text) 
Claiborne Millers Ferry Robert F. Henry Carters Allatoona 
Proposed Structures Lock and Dam Lock and Dam Lock and Dam Lake Dam3 Dam 
Miles above mouth of river 81.1' 142.2' 245.4' 26.82 47.84 
Nearest town Claiborne, Ala. Camden, Ala. Benton, Ala. Carters, Ga. Cartersville, Ga 
Distance (miles) 7 10 3 2 4 
Greatest lock length available 
for full width (feet) 600 600 600 - - 
Width of lock chamber (feet) 84 84 84 - - 
Maximum lift (feet) 30 48 47 - - 
Elevation of normal pool surface 
(mean sea level) 35 80 125 1072 Varies seasonally 
Depth over sills at low water 13 upper 15 Upper 15 - - 
(feet) Lower 13 Lower 12 
Character of foundation Rock Rock Rock Rock Rock 
Kind of spillway Gated and Gated Gated Gated Gated 
Fixed Crest 
Height of dam (feet) 95.5 99.5 94 451 190 
Type of construction Concrete Concrete Concrete Rock-fill Concrete 
Earth Core 
Total reservoir capacity 
(acre-feet) 96,360 331,800 234,200 472,800 670,050 
Power development (kw) - 75,000 68,000 500,000 74,000 
Percent complete 100 100 99 100 100 
Cost to date:5 $27,997,450 $62,725,300 $83,108,684 $111,139,162 $34,798,168 
I. Above mouth of Alabama River (river miles). 
2. Above mouth of Coosawattee River (river miles). 
3. Reregulation dam (Carters) 25.3 (river miles). 
4. Above mouth of Etowah River (river miles). 
5. Includes cost of added recreation facilities as shown in Table 
10-A. 
10-41

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 193 
TABLE 10-L 
APALACHICOLA, CHATTAHOOCHEE, AND FLINT RIVERS, ALA., GA., 
AND FLA., LOCKS AND DAMS AND MULTIPLE-PURPOSE 
DEVELOPMENT INCLUDED IN EXISTING PROJECT 
(See Section 40 of Text) 
Existing Projects Autheorled Projects 
Jim George W. Walter F. lutord Dam Lower 
Woodruff Andrews George Lake Auchumpkee Laser Spewrell 
Lock Lock Lock West Point Sidney Creek Creek Bluff 
and Dam and Dam and Dam Lake Lanier Lake Lake Lake 
Miles above mouth 107.6' 46.52 75.02 201.42 348.32 233.43 255.83 263.43 
Nearest town Chattahoochee, Columbia, Al. Ft. Gaines, West Point, Buford, Ga. Roberta, Ga. Thomaston, Manchester, 
Fl. Ga. Ga. Ga. Ga. Ga. 
Distance (miles) I I 2 2.8 5 7 8 8 
Greatest lock length 450 450 450 - - - - - 
available for full width 
(feet) 
Width of chamber (feet) 82 82 82 - - - - - 
Maximum lift (feet) 33 25 88 - - - - - 
Elevation of normal pool 77 102 190(Summer) 635(Summer) 1070 417 543 700 
surface (msl) 185(Winter) 625(Winter) 
Depth over sills at low 14 13 13 - - - - - 
water (feet) 
Character of foundation Limestone Limestone Limestone Rock Rock Rock Rock Rock 
Kind of spillway Fixed-gated Fixed-gated Gated Gated Fixed Gated Gated Gated 
Height of dam (feet) 67 62 114 95 192 130 142 180 
Type of construction Concrete Concrete Concrete Concrete Earth Concrete Concrete Concrete 
and Earth and Earth and Earth and Earth and Earth and Earth 
Total reservoir capacity 367,300 18,180 934,400 604,500 2,554,000 548,000 342,000 486,200 
(acre-feet) 
Power development 30,000 - 130,000 73,875 86,000 81,000 87,000 150,000 
(kilowatts) 
Percent complete 100 100 100 98 100 - - - 
Year opened to navigation 1954 1962 1963 - - - - - 
Estimated cost: - - - - - 5222,000,000 5258,000,000 5360,000,000 
Cost to date:4 $47,974,156 $13,038,427 $88,273,016s 5129,715,788 $52,851,828 - - 52,158,652 
I. Above mouth of Apalachicola River (river miles). 
2. Above mouth of Chattahoochee River (river miles). 
3. Above mouth of Flint River (river miles). 
4. Includes cost of added recreational facilities as shown in Table 10-A. 
5. Includes $333,198 cost of land for wildlife refuge. 
10-42

MOBILE, ALABAMA DISTRICT 
TABLE 10-M COMPLETED FLOOD INSURANCE STUDIES AND FLOOD 
HAZARD INFORMATION REPORTS FOR FY 1979 THRU FY 1983' 
(See Section 43 of Text) 
Date Federal 
Study Requesting Agency Completed Cost 
Flood Insurance Studies 
Ft. Payne, Alabama 
Geneva, Alabama 
Picayune, Mississippi 
Kennesaw, Georgia 
Powder Springs, Georgia 
Montgomery, Alabama 
Fulton Co., Georgia 
Montgomery Co., Alabama 
Roanoke, Alabama 
Wedowee, Alabama 
Heflin, Alabama 
Randolph County, Alabama 
Hobson City, Alabama 
Oxford, Alabama 
Weaver, Alabama 
Flood Insurance Studies 
Anniston, Alabama 
Calhoun County, Alabama 
Special Flood Hazard Information 
Chattahoochee River, Walter 
F. George to West Pt. Dam, Ga. 
Mulberry Fork and Cane Creek, Ala. 
Coldwater Creek, Ala. 
Yellowjacket Creek & 
Hogansville Branch, Ga. 
Dowling Branch, Ala. 
Gum Creek, Ga. 
Choctawhatchee River, Fla. 
Chattahoochee River, Supplefor 
Buford to Whitesburg Report 
Oothcalooga Creek 
Canton Creek, Ga. 
Oktasasi Creek, Ala. 
Cordele Creek & 
Malcolm Branch, Ga. 
(Prepared for Federal Insurance 
Administration, HUD) 
(Prepared for Federal Insurance 
Administration, HUD) 
(Prepared for Federal Insurance 
Administration, HUD) 
(Prepared for Federal Insurance 
Administration, HUD) 
(Prepared for Federal Insurance 
Administration, HUD) 
(Prepared for Federal Insurance 
Administration, HUD) 
(Prepared for Federal Insurance 
Administration, HUD) 
(Prepared for Federal Insurance 
Administration, HUD) 
(Prepared for Federal Insurance 
Administration, HUD) 
(Prepared for Federal Insurance 
Administration, HUD) 
(Prepared for Federal Insurance 
Administration, HUD) 
(Prepared for Federal Insurance 
Administration, HUD) 
(Prepared for Federal Insurance 
Administration, HUD) 
(Prepared for Federal Insurance 
Administration, HUD) 
(Prepared for Federal Insurance 
Administration, HUD) 
FEMA 
FEMA 
Lower Chattahoochee Area Planning 
and Development Commission 
Birmingham Regional Planning Commission 
Coldwater United Methodist Church 
City of Hogansville, Ga. 
City of Hartford, Ala. 
Housing Authority, Cordele, Ga. 
Board of County Commissioners 
Holmes County, Fla. 
Atlanta Reg. Planning 
Commission 
Gordon Co., GA Board of 
Commissioners 
City of Canton, Ga. 
Alexander City, Ala. 
City of Cordele, Ga. 
Oct 78 
Oct 78 
Oct 78 
Jan 79 
Jan 79 
Feb 79 
Sep 79 
Apr 80 
Feb 81 
Feb 81 
Mar 81 
Mar 81 
Sep 81 
Sep 81 
Sep 81 
Apr 82 
Apr 82 
Apr 79 
July 79 
July 79 
July 79 
Jan 80 
Sep 80 
Jan 81 
Mar 82 
Jun 82 
Dec 82 
Jan 83 
May 83 
$40,200 
32,800 
46,000 
4,100 
5,500 
186,500 
209,000 
104,600 
19,400 
21,900 
20,700 
34,400 
14,200 
30,000 
6,400 
80,900 
61,200 
133,000 
50,000 
10,000 
10,000 
10,000 
10,000 
10,000 
5,000 
10,000 
3,000 
3,000 
4,000 
1. For list of reports completed by Mobile District for FY 1965 for reports completed in FY 1976 and FY 1977, see FY 1977 Annual 
thru FY 1974, see FY 1974 Annual Report, page 10-50; reports Report, page 10-46. See page 10-48 FY 1978 Annual Report for FY 
completed in FY 1975 see FY 1975 Annual Report, page 10-44; and 1978 reports. 
10-43

NEW ORLEANS, LA, DISTRICT* 
District comprises a portion of Louisiana, including 
trainage area of Red River south of Fulton, AR, 
embraced in drainage basins tributary to Mississippi 
River and Gulf of Mexico, except Mississippi River 
above mile 325.5 above Head of Passes, drainage area of 
Ouachita-Black River Basin, and small eastern and 
western portions of Louisiana tributary to Pearl River 
mnd Sabine River and Lake. 
It includes sections of the Gulf Intracoastal Waterway 
From Lake Borgne Light 29 at the mouth of Pearl River 
to Sabine River, and the Passes of the Mississippi 
River. It exercises jurisdiction over flood control work 
on Mississippi River from mile 325.5 AHP to Gulf of 
Mexico; on Red River including its south bank levees 
and tributaries from Index, AR, to its junction with 
Old River and Atchafalaya River; Atchafalaya River; 
and in Atchafalaya Basin; and maintenance of project 
navigation channel of Mississippi River below mile 
325.5 AHP, under supervision of President, Mississippi 
River Commission (MRC), and Division Engineer, 
Lower Mississippi Valley Division. 
IMPROVEMENTS 
Navigation Page 
1. Aquatic Plant Control Program, LA ...... 11-2 
2. Atchafalaya River and Bayous 
Chene, Boeuf, and Black, LA ............ 11-2 
3. Barataria Bay Waterway, LA ........... 11-3 
4. Bayou Lafourche and Lafourche- 
Jump Waterway, LA ................... 11-3 
5. Bayou Teche and Vermilion River, LA .... 11-4 
6. Bayou Teche, LA ....................... 11-5 
7. Calcasieu River and Pass, LA ............ 11-6 
8. Freshwater Bayou, LA ................. 11-7 
9. Gulf Intracoastal Waterway between 
Apalachee Bay, Fla., and Mexican 
Border (New Orleans Dist.) ............. 11-7 
10. Houma Navigation Canal, LA ............ 11-10 
11. Leland Bowman Lock, LA 
(Replacement of Lock) 
(Formerly Vermilion Lock, LA ........... 11-10 
12. Mermentau River, LA .................. 11-10 
13. Mississippi River, Baton Rouge 
to Gulf of Mexico, LA ................... 11-11 
14. Mississippi River-Gulf Outlet, LA ........ 11-13 
15. Mississippi River Outlets, 
Venice, LA ............................ 11-13 
16. Removal of Aquatic Growth, LA .......... 11-14 
17. Tangipahoa River, LA .................. 11-14 
18. Waterway from Intracoastal Waterway 
to Bayou Dulac, LA (Bayous Grand Caillou 
and LeCarpe, LA ....................... 11-15 
19. Navigation work under 
special authorization ................... 11-15 
Flood Control Page 
20. Grand Isle & vicinity, LA ............... 11-15 
21. Lake Pontchartrain and vicinity, 
LA, (hurricane protection) .............. 11-16 
22. Larose to Golden Meadow, LA 
(hurricane protection) .................. 11-17 
23. McKinney Bayou, AR and TX ........... 11-17 
24. Morgan City and vicinity, LA 
(hurricane protection) .................. 11-18 
25. New Orleans to Venice, LA, 
(hurricane protection) .................. 11-18 
26. Inspection of connected flood 
control projects ........................ 11-19 
27. Flood control work under special 
authorization .......................... 11-20 
General Investivations 
28. Active Investigations ................... 11-20 
Tables 
Table 11-A 
Table 11-B 
Table 11-C 
Table 11-D 
Table 11-E 
Table 11-F 
Table 11-G 
Cost and Financial Statement .... 11-21 
Authorizing Legislation ......... 11-26 
Bayou Teche, LA, Locks ......... 11-31 
Gulf Intracoastal Waterway 
Between Apalachee Bay, FL 
and Mexican Border (New Orleans 
Dist.)-Locks .................... 11-32 
Other Authorized Navigation 
Projects ........................ 11-34 
Other Authorized Flood 
Control Projects ................ 11-36 
Active General Investigations .... 11-38 
11-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Navigation 
1. AQUATIC PLANT CONTROL 
PROGRAM, LA 
Location. Lakes and streams in State of Louisiana. 
Existing project. Provides for control and progressive 
eradication of water-hyacinth, alligatorweed, and 
other obnoxious aquatic plant growth from navigable 
waters, tributary streams, connecting channels, and 
other allied waters in North Carolina, South Carolina, 
Georgia, Florida, Alabama, Mississippi, Louisiana, and 
Texas, in combined interests of navigation, flood 
control, drainage, agriculture, fish and wildlife conservation, 
public health, and related purposes, including 
continued research for development of most effective 
and economic control measures. 
The modification of the 1965 Act provides for comprehensive 
program for control and progressive eradication 
of water-hyacinth, alligatorweed, Eurasian water 
milfoil, and other obnoxious plant growths from navigable 
waterways, tributary streams, connecting channels, 
and other allied waters of the United States, in 
combined interest of navigation, flood control, drainage, 
agriculture, fish and wildlife conservation, public 
health, and related purposes, including continued 
research for development of most effective and economic 
control measures. Research and planning costs 
undertaken pursuant to 1965 Act shall be borne fully 
by the United States and shall not be included in costs 
to be shared by local interests. 
Local cooperation. Local interests must hold and 
save the United States free from claims and participate 
in project to extent of 30 percent of cost of 
operations. State of Louisiana, Office of Public Works, 
and Louisiana Department of Wild Life and Fisheries 
furnished a joint assurance of local cooperation, which 
was approved Apr. 29 and accepted May 4, 1959. 
Under provisions of continuing contract, local agencies 
are performing work in kind, exceeding 30 percent of 
cost of program. 
Operations and results during fiscal year. Combined 
efforts by Corps of Engineers crews and crews of 
the State of Louisiana, Department of Wild Life and 
Fisheries, continued against aquatic vegetation problems 
throughout the State. Water-hyacinth control 
maintenance requires work in all areas, and waterhyacinth 
persists as the most serious aquatic pest. 
Control maintenance by the Corps of cleared areas 
continued in the Mermentau River, Bayou Lacassine, 
Bayou Queue de Tortue, in the Bayou Teche Basin 
south of U.S. Highway 190, including the lakes west of 
the Atchafalaya Floodway, in the feeder areas of the 
Port Allen-Morgan City Route of the Gulf Intracoastal 
Waterway, and in the feeder areas to the Gulf Intracoastal 
Waterway in Coastal Louisiana. Louisiana 
Department of Wild Life and Fisheries crews continued 
maintenance efforts in the major lakes and streams of 
north Louisiana, in the Atchafalaya Floodway, in the 
Louisiana portion of the Toledo Bend Reservoir, and 
the Pearl River Basin within Louisiana. During the 
fiscal year, 66,400 acres of water-hyacinths were destroyed 
in the State of Louisiana under this funding. 
Louisiana Department of Wild Life and Fisheries crews 
destroyed 48,447 acres and Corps of Engineers crews 
destroyed 17,953 acres primarily by herbicide treatment. 
The alligatorweed flea beetle (Agasicles hygrophila) 
population has increased to the point that they 
are again exercising significant control of this plant in 
many areas of the state. In addition, the stem boring 
moth (Vogtia malloi) has spread to such an extent that 
it is found associated with alligatorweed in all locations. 
The water-hyacinth weevils (Neochetina eichhorniae 
and Neochetina bruchi) have been spread throughout 
all areas of the state that water-hyacinth infest and 
adult feeding scars are more prevalent everywhere. 
Submersed weed problems in Toledo Bend Reservoir 
have reached serious proportions and Caddo Lake is 
also experiencing interference with boating and fishing. 
Hydrilla verticillata, an introduced exotic submersed 
weed species, continues to spread along the Gulf Intracoastal 
Waterway and poses a threat to water-related 
activities. 
Condition as of Sep. 30. Operations under 1958 
River and Harbor Act, initiated May 1959, are complete. 
Operations under 1965 Act were initiated in FY 
1968. Waterways are being cleared, then maintained 
as required. 
2. ATCHAFALAYA RIVER AND 
BAYOUS CHENE, BOEUF, AND 
BLACK, LA. 
Location. The improvement is located in the parishes 
of Assumption, Terrebonne, and St. Mary, LA, in the 
vicinity of Morgan City, along Bayous Chene, Boeuf, 
and Black, and the Lower Atchafalaya River to the 
Gulf of Mexico. (Refer to MRC alluvial maps, Morgan 
City, Belle Isle, and Point au Fer quadrangles, NOAA 
Coast Charts Nos. 11351 and 11355 of Intracoastal 
Waterway, and Coast Chart No. 11354 for the Atchafalaya 
River system.) 
Existing project. Provides for enlargement and 
extension of project, Atchafalaya River, Morgan City 
to the Gulf of Mexico, LA, to obtain navigation channels 
20 feet deep over a bottom width of 400 feet from 
vicinity of U.S. Highway 90 crossing over Bayou Boeuf 
to the Gulf of Mexico via Bayou Boeuf, Gulf Intracoastal 
Waterway, Bayou Chene, Avoca Island Cutoff, the 
lower Atchafalaya River, Atchafalaya Bay to the Gulf 
of Mexico, and from near U.S. Highway 90 to Bayou 
Chene via Bayou Black and the Gulf Intracoastal 
Waterway. The 400-foot channel extends into the Gulf 
of Mexico to the 20-foot contour, and the width in 
Bayou Boeuf would be reduced to 300 feet where 
necessary because of industrial development on both 
sides of the bayou. Estimated cost for new work 
(October 1983) is $30,850,000 Federal and $2,000,000 
non-Federal, including $1,000,000 contributed funds. 
In addition, Coast Guard is to provide navigation aids 
at an estimated cost of $220,000. 
11-2

NEW ORLEANS, LA, DISTRICT 
Local cooperation. For details see page 11-3, Annual 
Report for FY 1980. 
Assuring Agency: Morgan City Harbor and Terminal 
District. 
Basic assurance was approved on behalf of United 
States on Dec. 10, 1973, and amended assurance containing 
the applicable provisions of Public Law 91-646 
and Public Law 91-611 was approved on behalf of 
United States on Feb. 25, 1974. 
In an effort to expedite the project, local interests 
have accomplished the surveys, soil borings, testing, 
and the basic mapping at an estimated cost of $250,000, 
for which they will not be reimbursed. As a convenience 
to local interests and to avoid confusion in 25 percent 
and 75 percent acquisition cost, the New Orleans 
District agreed to acquire all lands, with local interests 
reimbursing the Government for their 25 percent 
portion. An escrow agreement has been executed 
between the local interests and the Government, whereby, 
they will advance funds in a sufficient amount to 
provide for their portion of the acquisition and diking 
cost. To date original advance of $518,000 has been 
withdrawn; however, local interests will be required to 
deposit in escrow an additional $456,000. Local interests 
have asked that the Government invoke the navigation 
servitude under the Commerce Clause of the Constitution, 
thereby requiring pipeline owners to relocate 
their pipeline at no expense to local interests or the 
Government. 
Terminal facilities. Two large and three small public 
wharves at Morgan City are open for use by all without 
charge. In addition, there are numerous privately 
owned facilities on both banks of the lower Atchafalaya 
River in Morgan City and Berwick, LA, and along 
Bayou Boeuf and the Gulf Intracoastal Waterway. 
Fabrication and repair facilities are located on Bayous 
Boeuf and Black. Adequate acreage is available for 
expansion of existing terminals and construction of 
new terminals along Bayous Chene, Boeuf, and Black, 
and the Gulf Intracoastal Waterway. Public and private 
terminals in the project area are adequately connected 
with rail, water, and highway transportation facilities. 
No additional public wharves are required. 
Operations and results during fiscal year. Contract 
for maintenance dredging of the bar and bar channel, 
from stations 25+00 to 190+00, commenced Jun. 26, 
1983, and is 83 percent complete with the removal of 
9,500,000 cubic yards of material. 
Condition as of Sep. 30. Construction was initiated 
on the Atchafalaya Bay and gulf reach in April 1974. 
The project is 100 percent complete. 
3. BARATARIA BAY WATERWAY, LA 
Location. In Jefferson Parish, LA, and extends 
about 37 miles southerly from junction of Gulf Intracoastal 
Waterway and Bayou Barataria near Lafitte 
Post Office. From its origin it extends southerly through 
Bay Barataria, Bayou Dupont, a land cut (known as 
Dupre Cut) through marsh area, Bayou Cutler, Bayou 
St. Denis, and Barataria Bay to east end of Bayou 
Rigaud. At its southerly terminus it also connects with 
Barataria Pass and through that pass with the Gulf of 
Mexico. (Refer to NOAA Coast Charts Nos. 11352, 
11340, and 11535 and Geological Survey quadrangles, 
Barataria, Bay Dogris, Wilkinson Bay, and Barataria 
Pass.) 
Previous project. For details see page 562 of Annual 
Report for 1963. 
Existing project. A channel about 37 miles long 
with a 12-foot depth and 125-foot width from its beginning 
at Gulf Intracoastal Waterway to Grand Isle, LA, 
following route of previous project to mile 15.5 in 
Bayou St. Denis; thence by a relocated channel along 
western shore of Barataria Bay and through Barataria 
Pass to 12-foot-depth contour in the gulf, with an 
extension of project to include westerly 4.3 miles of 
Bayou Rigaud. Normal range of tide is 30 inches at 
mouth and 6 inches at head. Elevation of water surface 
near mouth, due to hurricanes, has been over 6 feet. 
Existing project was completed at a cost of $1,499,648. 
Local cooperation. Fully complied with. For details 
see page 563, Annual Report FY 1963. 
Terminal facilities. Six privately-owned wharves at 
Lafitte; three privately owned facilities at Grand Isle; 
and wharfage in Bayou Rigaud at Grand Isle constructed 
by shrimping industry are available to all 
boats without charge. About 7 miles below Lafitte 
there is a large oil terminal for transferring production 
of Lafitte field to barges. Adjacent to Bayou Barataria 
and along Bayou Rigaud adequate sites are available 
for future use. 
Operations and results during fiscal year. Hired 
labor continued condition and operation studies, stream 
gaging, and water quality studies. 
Maintenance by contract: Dredging under two 
contracts included removing 674,509 cubic yards from 
mile 14.5 to mile 2.5 and 1,075,000 cubic yards from 
Bayou Rigaud and bar channel. 
Condition as of Sep. 30. Construction was initiated 
in May 1960 and completed in November 1963.. 
4. BAYOU LAFOURCHE AND 
LAFOURCHE-JUMP WATERWAY, LA 
Location. Prior to 1902, Bayou Lafourche was an 
outlet of Mississippi River, its head being at Donaldsonville, 
LA, 80 miles above New Orleans. It flows southerly 
107 miles to Gulf of Mexico. (Refer to NOAA Coast 
Charts Nos. 11340 and 11357; MRC alluvial valley 
maps; Donaldsonville, White Castle, Napoleonville, 
Thibodaux, and Lac des Allemands quadrangles; and 
Geological Survey maps, Houma, Cutoff, Lake Felicity, 
Mink Bayou, Leeville, and Belle Pass quadrangles.) 
Previous projects. For details see page 564 of 1963 
Annual Report. 
Existing project. Provides for permanent closure of 
head of bayou without a lock, a channel 6 feet deep and 
60 feet wide from Canal Boulevard in Thibodaux to 
11-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Lockport, and from Larose to Gulf of Mexico with a 
jettied entrance at Belle Pass, and the closure of Pass 
Fourchon. These improvements are about 50.5 miles 
long, and the modification of Jul. 14, 1960, provides for 
an additional 66 miles of improvement as follows: a 12- 
by 125-foot channel, extending from Gulf Intracoastal 
Waterway at mile 37.2 west of Harvey Lock to enter 
Bayou Lafourche below highway bridge at Leeville at 
about mile 12; a 12- by 125-foot channel in Bayou 
Lafourche from point of junction with proposed 12- by 
125-foot channel to 12-foot-depth contour in gulf; modification 
and extension of existing jetties from 6-by 12-foot 
contour, if found advisable to reduce maintenance 
dredging in the gulf; and a channel 9 by 100 feet in 
Bayou Lafourche from Leeville to vicinity of lower limits 
of Golden Meadow; and a 12- by 125-foot channel from 
Bayou Lafourche at Leeville from point where auxiliary 
channel connects with Bayou Lafourche through Southwestern 
Louisiana Canal to and through Bayou Rigaud 
to connect with enlargement of Bayou Rigaud recommended 
under project "Barataria Bay Waterway, LA." 
Normal range of tide is 10 inches at mouth and 3 inches 
at head; from severe rains, 3 to 10 feet at head; from 
hurricanes, up to 10 feet at mouth. Estimated cost for 
new work (October 1980) is $10,500,000 Federal and 
$6,050,000 non-Federal. In addition, Coast Guard is to 
provide navigation aids at an estimated cost of $43,000. 
Excavation of a channel 6 feet deep and 60 feet wide 
from Thibodaux to Gulf Intracoastal Waterway at 
Lockport is considered inactive and excluded from foregoing 
cost estimate. Estimated cost of this portion (July 
1974) is $733,000. 
Local cooperation. Original assurances received 
and accepted on all items of work in the project. 
Provisions of Public Law 91-611 are not applicable; 
however, provisions of Public Law 91-646 are applicable. 
Supplemental assurances covering Public Law 
91-646 have been executed by the Jefferson Parish 
Council and Lafourche Parish Police Jury; however, 
the Louisiana Office of Public Works has not executed 
supplemental assurances. 
Golden Meadow to gulf: Local agency has acquired 
all rights-of-way and furnished rights-of-entry. 
Leeville to Grand Isle: No action is apparent on this 
stretch by either the Lafourche Parish Police Jury, the 
Jefferson Parish Council, the local assurers, or the 
State of Louisiana, Office of Public Works. Rightsof-
way are not available due to multiplicity and other 
complications of ownership. 
The "Jump" portion of the project was classified as 
inactive on May 4, 1977. The Jefferson Parish Council 
and the Lafourche Parish Police Jury were requested 
to provide information as to whether they still favor 
construction on this part. If reactivation is favored, it 
should be with the understanding that they would have 
to provide required rights-of-way when requested. The 
Greater Lafourche Port Commission stated that they 
may provide assurances for that portion of the project 
located in Lafourche Parish. These assurances were 
forwarded to the Greater Lafourche Port Commission 
on Jan 22, 1979. On Mar. 9, 1979, we requested information 
as to the status of their execution of the assurances. 
The Greater Lafourche Port Commission appears 
to be reluctant to execute the required assurances. 
Terminal facilities. There are numerous private 
warehouses, wharves, and stiff-leg derricks for handling 
cane along bayou. At Lockport, Barker Barge Line has 
a barge wharf with covered shed, and Southern Pacific 
Railroad maintains a large wharf with covered shed. 
At Golden Meadow each of the seafood canneries has 
docking facilities suitable for its needs. Four oil 
companies have docks at Leeville for transferring 
production of Leeville oil fields to barges. Facilities are 
considered adequate for existing commerce. 
Operations and results during fiscal year. New 
work by hired labor consisted of engineering studies. 
Condition as of Sep. 30. Construction of existing 
projects was initiated in FY 1939 and is 10 percent 
complete. Dredging between Larose, LA, and Gulf of 
Mexico was completed in 1939, and that segment 
between Lockport and Napoleonville, LA, is in an 
inactive status due to lack of right-of-way and spoil 
area. Jetties at mouth of Belle Pass were completed in 
1939, and later damaged by storm action, which 
required placement of additional stone adjacent to both 
sides of steel sheet pile jetties in 1940, and repair and 
extension of jetties in 1941. During FY 1948, stone 
jetties were repaired and extended inland about 700 
feet from shoreline; and steel sheet pile section was 
strengthened for about 250 feet gulfward of stone 
jetties, by placement of stone on both gulf and bayou 
sides. On May 31, 1949, an automatic tide gage for 
recording hurricane and storm tides was installed. 
Modification of Jul. 14, 1960, was initiated in February 
1963 and is 10 percent complete, with 12- by 125-foot 
channel completed in September 1963 from Leeville to 
12-foot contour in Gulf of Mexico, the 9- by 100-foot 
channel completed in August 1966 from Golden Meadow 
to Leeville, and the 9- by 100-foot channel from Golden 
Meadow to Leeville completed in August 1966. 
The Greater Lafourche Port Commission requested, 
and was granted, a permit to dredge a new channel 20 
by 300 feet wide west of the existing channel from mile 
0.76 in Bayou Lafourche to the 20-foot depth in the 
gulf, and to close the existing jettied channel after 
completion of the new channel. This work was completed 
in March 1968 and the Port Commission must 
maintain the channel at no less than 12 by 125 feet. 
5. BAYOU TECHE AND 
VERMILION RIVER, LA 
Location. Bayou Teche has its source in Bayou 
Courtableau, in St. Landry Parish, and flows southeasterly 
125 miles to its confluence with lower Atchafalaya 
River, about 10.5 miles above Morgan City, LA 
Vermilion River, also called Bayou Vermilion, is formed 
by junction of Bayous Fusilier and Bourbeau, west of 
Arnaudville, LA, and flows southwesterly 72 miles to 
western end of Vermilion Bay. Bayou Teche is connected 
with Vermilion River by Bayou Fusilier at Arnaudville; 
11-4

NEW ORLEANS, LA, DISTRICT 
and by Ruth Canal, an artificial, privately-owned, 
nonnavigable waterway, constructed for diversion of 
water from Bayou Teche to Vermilion River for rice 
irrigation. (Refer to NOAA Coast Charts No. 11340 
and 11349; MRC alluvial valley maps; and Geological 
Survey maps.) 
Existing project. A navigable channel 51 miles long 
and 8 by 80 feet from 8-foot-depth contour in Vermilion 
Bay to Gulf Intracoastal Waterway, thence 9 by 100 
feet to head of navigation (mile 52) at Lafayette, LA 
(fixed bridge at Louisiana State Highway 729, formerly 
State Highway 1092), with additional enlargement 
below Abbeville necessary to provide adequate capacity 
for floodflows; improvement of Vermilion River from 
Lafayette, LA, mile 52, to its junction with lower end of 
Ruth Canal, mile 57.2, by both widening and deepening 
to provide a channel 6 by 60 feet, mean gulf level, in 
order to provide adequate capacity for flood discharges 
from upper Vermilion River Basin, and also serve 
irrigation interests by conducting flow of Ruth Canal 
to lower Vermilion River during rice season. Clearing 
and enlargement of channel from Ruth Canal to Bayou 
Fusilier by both widening and deepening to provide a 
cross section about 50 percent larger than that of 
existing channel. This improvement is required in 
interest of flood control in upper Vermilion Basin. 
Enlargement of channel of Bayou Teche from its head 
in Bayou Courtableau to a point about 21 miles downstream 
thereof, by widening and deepening to provide 
a channel of 35-foot bottom width at minus 2 and minus 
3, mean gulf level. Increasing height of Keystone Dam 
by 3 feet (later revised to 1.5 feet) by installation of a 
fixed crest spillway. (See individual report for Bayou 
Teche, LA.) In connection with these improvements, the 
project also provides for replacement of an existing 
pontoon bridge at Woodlawn over Vermilion River 
with a vertical-lift structure and lengthening and 
strengthening approaches to five existing movable 
bridges over Vermilion River below Lafayette, LA, 
located at Louisiana State Highway 43 at Perry, LA; 
Southern Pacific Railroad at Abbeville, LA; Louisiana 
State Highway 25 at Abbevile, LA; Milton, LA; and 
U.S. Highway 90 (Pinhook Bridge) just below Lafayette, 
LA. Similar work on existing fixed spans over nonnavigable 
streams is provided for on 11 bridges over 
Bayou Vermilion above Lafayette, LA, and three over 
upper Bayou Teche. New work completed in 1957 cost 
$2,891,922. Project was reclassified "Operation and 
Maintenance, General" under category, "Navigation 
(Locks, Dams, Reservoirs, and Canals)" by authority of 
Chief of Engineers, Apr. 23, 1956. 
Local cooperation. Fully complied with. For details 
see page 687, Annual Report FY 1944. 
Terminal facilities. Privately-owned, publiclyoperated 
terminals are located on Bayou Teche at 
Franklin, Jeanerette, New Iberia, and Arnaudville. 
Other privately-owned boat landings are located at 
frequent intervals throughout the bayou and public 
landing is permitted without charge. Facilities on the 
Vermilion River include a public wharf and two 
privately-owned barge landing piers at Abbeville 
equipped for barge truck transfers of general commodities, 
seven landings for the transfer of petroleum 
products, and several private landings all along the 
waterway suitable for small craft. The Vermilion Sugar 
Company maintains a barge slip at its mill. Present 
facilities are adequate for existing commerce and there 
is ample space available for construction of more 
wharfage. 
Operations and results during fiscal year. Hired 
labor forces continued condition and operation studies, 
stream gaging, and snagging and clearing above 
Lafayette, LA. 
Condition as of Sep. 30. Construction commenced 
March 1944 and was completed March 1957, when 
Keystone Dam was raised to provide an increase of 1.5 
feet in pool elevation, in order to increase flow through 
Ruth Canal into Vermilion River. This work was 
accomplished under navigation improvement "Bayou 
Teche, LA." 
6. BAYOUTECHE,LA. 
Location. Has its source in Bayou Courtableau, in 
St. Landry Parish, flow southeasterly for 125 miles, 
and joins lower Atchafalaya River about 10.5 miles 
above Morgan City, LA (Refer to NOAA Sailing Chart 
No. 11340, and MRC alluvial valley maps, and Palmetto, 
Opelousas, Carencro, Arnaudville, St. Martinville, 
Loreauville, Derouen, Jeanerette, Foster, and Belle 
Isle quadrangles.) 
Previous projects. For details see page 569, 1963 
Annual Report. 
Existing project. Provides for a channel 8 feet deep 
and 80 feet wide on the bottom from mouth of stream to 
New Iberia, LA, mile 54.5, thence 6 feet deep and 60 
feet wide on the bottom to Keystone Lock, 18 miles, and 
thence 6 feet deep and 50 feet wide on the bottom from 
Keystone Lock to Arnaudville, LA, 34 miles, to be 
secured by dredging, removing snags and overhanging 
trees, and construction of a lock and dam and regulating 
works. (See Table 11-C on Keystone Lock.) 
Raising pool level by 1.5 feet above Keystone Dam by 
installation of a fixed crest spillway on dam is provided 
for in flood control project for Bayou Teche and 
Vermilion River, LA. Under project, flood control, 
Mississippi River and tributaries, East and West 
Calumet floodgates, with a width of 45 feet and sill 
elevation of minus 9.02 feet, mean low gulf level, were 
constructed in Bayou Teche at east and west approaches 
to Wax Lake Outlet from February 1949 to September 
1950, and a lock was constructed in lower Atchafalaya 
River in vicinity of Berwick, LA, from November 1948 
to September 1951. (See Table 11-C on Berwick Lock.) 
Normal range of tide is 10 inches at mouth; 4 inches 
just below Keystone Lock; extreme, 12 inches at mouth; 
6 inches just below Keystone Lock; and zero above lock; 
due to freshets 4 to 5 feet at mouth; 12 to 15 feet just 
below Keystone Lock, and 2 to 7 feet above Keystone 
Lock. 
11-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Estimated cost for new work (1954) is $1,080,000, 
exclusive of amount expended on previous projects and 
estimated cost (1954), $371,400 for widening and 
deepening channel between miles 50.06 and 72, Keystone 
Lock and Dam, which is inactive. 
Local cooperation. Fully complied with. For details 
see page 687, Annual Report FY 1944. 
Terminal facilities. Small, privately-owned wharves 
are available at all towns along bayou; public landing 
is permitted without charge. There are privatelyowned 
terminals for transferring crude oil to barges 
near towns of Charenton, Jeanerette, Oliver, and St. 
Martinville. Facilities considered adequate for existing 
commerce. 
Operations and results during fiscal year. Hired 
labor continued operation and maintenance of Keystone 
Lock and facilities, condition and operation studies, 
and stream gaging. 
Condition as of Sep. 30. Construction was initiated 
in 1891 and completed July 1928, except widening 
channel to bottom width of 80 feet from mile 50.06 to 
New Iberia, and to bottom width of 60 feet from New 
Iberia to Keystone Lock, which is inactive. For further 
details see Annual Report for 1966. 
7. CALCASIEU RIVER 
AND PASS, LA 
Location. Calcasieu River has its source in southwestern 
Louisiana, and flows southerly to the gulf. 
About 25 miles from the gulf it debouches into Calcasieu 
Lake, which is about 18 miles long. Connection between 
lake and gulf, about 7 miles long, is known as Calcasieu 
Pass. (See Geological Survey maps, Edna, Thompson 
Bluff, Hecker, Moss Bluff, Lake Charles, West Lake, 
Moss Lake, Hackberry, Sweet Lake, Brown's Lake, 
Holly Beach, Grand Bayou, and Cameron quadrangles; 
and NOAA Small-Craft Charts Nos. 11341 and 11348 
of Intracoastal Waterway and NOAA Small-Craft 
Chart No. 11347 of Calcasieu River and Lake.) 
Previous project. For details see 1936 and 1938 
Annual Reports, pages 719 and 819, respectively. 
Existing project. Provides for a channel 40 by 400 
feet (35.9 miles long) from Lake Charles to sea end of 
jetties in Gulf of Mexico; an approach channel 42 by 
800 feet from sea end of jetties to 42 feet deep in the 
gulf; extension of 35- by 250-foot channel from its 
present upsteam limit at mile 34 to vicinity of U.S. 
Highway 90 Bridge (mile 36.2); a 750- by 1,000-foot 
turning basin at upper end with a 35-foot depth; 
improvement of river from Lake Charles to Phillips 
Bluff (52.6 miles) by removing logs, snags, overhanging 
trees, and by dredging; maintenance of existing 12- by 
200-foot channel in old channel of Calcasieu River at 
Cameron, LA, which connects with project at mile 2.25; 
and reconstruction and extension of existing jetties 
initially to seaward end of east jetty, and further 
extension to 15-foot-depth contour if found advisable to 
reduce maintenance dredging costs. Improvement is 
113.6 miles long. Normal range of tide is 10 inches at 
mouth, diminishing to zero at Phillips Bluff; extremes 
range from 14 inches to zero. 
Estimated cost for new work (July 1975) is $19,518,000 
Federal, and $1,409,000 non-Federal. In addition, Coast 
Guard is to provide navigation aids at an estimated cost 
of $404,700. 
Local cooperation. Local interest furnished all 
rights-of-way and spoil-disposal areas for completed 
features. For construction and future maintenance of 
modification authorized by 1960 River and Harbor 
Act, local interests must furnish lands, rights-of-ways, 
and spoil-disposal areas; alter pipelines, cables, wharves, 
oil wells, and any other facilities and hold and save the 
United States free from damages. Assurances were 
accepted and right-of-entry was furnished for the 
modification. The local agency is presently finalizing 
transfer to the United States of the few remaining 
tracts with acceptable title evidence. 
Assurance Agency: Lake Charles Harbor and Terminal 
District. 
Terminal facilities. Facilities at Port of Lake Charles 
are owned by Lake Charles Harbor and Terminal 
District and operated by a board of commissioners. In 
addition to municipally-owned terminals, there are 
several privately-owned and operated wharf structures 
on existing ship channel. (For further details, see Port 
Series No. 19, vol. 1, "Port St. Joe, FL, Pensacola, FL, 
Baton Rouge, LA, Panama City, FL, Pascagoula, MS, 
Lake Charles, LA, Gulfport, MS," revised 1957, and 
Folio of Navigation Maps Intracoastal Waterway, New 
Orleans to Port Arthur, 1968, 13th edition, published 
by the MRC.) 
Operations and results during fiscal year. Hired 
labor continued operation and maintenance of the saltwater 
barrier, stream gaging, and condition and 
operation studies. 
Maintenance by contract: Dredging under two contracts 
included removing 7,720,964 cubic yards from 
mile 1.5 to mile -10 and 9,894,523 cubic yards of 
material from mile 22.7 to mile 5.0. 
Condition as of Sep. 30. Construction under the 
existing project was initiated in FY 1939 and completed 
October 1968, except extension of the jetties to 15- 
foot-depth contour, which has been deferred until found 
advisable to accomplish same. Construction of modifications, 
described in Table 11-B, was as follows: Work 
authorized by Mar. 2, 1945, R&H Act was initiated in 
September 1948 and completed in June 1949; Work 
authorized by Jul. 24, 1946, FC Act was initiated in 
September 1948 and completed in April 1953; and 
Work authorized by Jul. 14, 1960, R&H Act was 
initiated in April 1962 and completed in October 1968. 
A turning basin or ship anchorage for vessels using 
waterway was constructed from April to June 1952, 
between St. Johns Island and vicinity of Cameron, LA, 
about 1.1 miles. Calcasieu Pass jetties, initiated under 
previous project and completed in May 1942, extended 
to 10-foot-depth contour. East jetty about 8,620 feet 
long, was built to about 6 feet above mean low gulf and 
extends seaward from existing gulf shoreline for 6,820 
11-6

NEW ORLEANS, LA, DISTRICT 
feet. West jetty, 8,050 feet long was built to about 4 feet 
above mean low gulf and extends seaward from existing 
gulf shoreline for 6,795 feet. 
8. FRESHWATER BAYOU, LA 
Location. In Vermilion Parish, LA, between Atchafalaya 
and Calcasieu Rivers, from Gulf Intracoastal 
Waterway, mile 161.2 west of Harvey Lock, to 12-foot 
contour in Gulf of Mexico near Freshwater Bayou. 
Waterway is routed 22.6 miles along Schooner Bayou 
Cutoff, Schooner Bayou, Six Mile Canal, Belle Isle 
Canal, and Freshwater Bayou. (Refer to NOAA Small- 
Craft Chart No. 11350 of Intracoastal Waterway.) 
Existing project. Provides for dredging a new 12-by 
125-foot channel from Gulf Intracoastal Waterway, 
mile 161.2 west of Harvey Lock, to 12-foot contour in 
Gulf of Mexico near Freshwater Bayou, construction of 
an 84- by 600-foot lock with a depth of 16 feet over sill 
near Gulf of Mexico; and construction of jetties from 
shoreline to 6-foot-depth contour in Gulf of Mexico, if 
maintenance dredging of channel without jetties proves 
to be more expensive than construction and maintenance 
of jetties. Until such determination has been 
made, offshore channel should be dredged and maintained 
to provide a 12- by 250-foot channel. In event 
jetties are provided, offshore section should then be 
maintained to 12- by 125-foot project in jettied reach, 
and 250 feet beyond. Existing project was completed in 
1968, except for construction of jetties at a later date, if 
necessary. Estimated cost of construction of jetties 
(July 1971) is $3,118,100. Estimated total Federal cost 
is $10,400,000 (1971) and the total non-Federal cost for 
the existing project is $171,000. In addition, the Coast 
Guard is to provide navigational aids at an estimated 
cost of $19,100. 
Local cooperation. Fully complied with. For details 
see page 649, Annual Report FY 1962. 
Terminal facilities. Extensive public and private 
terminal and transfer facilities do not exist in area, and 
none would be required for improved channel. Private 
terminals exist at site of oil and gas operations in area 
and sufficient private and public wharf facilties are 
along Gulf Intracoastal Waterway and its connecting 
waterways. Sites are available along proposed improvement 
for construction of any additional private and 
public terminals that might be required for utilization 
of channel. 
Operations and results during fiscal year. Maintenance 
by hired labor consisted of operation and 
ordinary repairs to lock, condition and operation studies, 
reconnaissance surveys, water quality studies, and 
channel patrol. 
Conditions as of Sep. 30. Construction was initiated 
April 1963 and completed August 1968, except for 
construction of jetties at a later date, if required to 
reduce the cost of maintenance dredging. 
9. GULF INTRACOASTAL WATERWAY 
BETWEEN APALACHEE BAY, FL, 
AND MEXICAN BORDER 
(NEW ORLEANS DIST.) 
Location. Section of Gulf Intracoastal Waterway 
within New Orleans District extends from Lake Borgne 
Light 29 near mouth of Rigolets, to Sabine River, LA, 
and TX. Section from Lake Borgne Light 29 to Mississippi 
River follows Rigolets and Lake Pontchartrain to 
lake end of State-owned Inner Harbor Navigation 
Canal, thence via this canal to Mississippi River, a 
distance of 40.5 miles. Public Law 675, 77th Cong., 
modified project to provide for a land cut through 
marsh from Rigolets to a point on Inner Harbor Navigation 
Canal about 22.5 miles from Mississippi River, 
eliminating passage through Lake Pontchartrain and 
five drawbridges, a distance of 30.8 miles to Mississippi 
River by this route. From Inner Harbor Navigation 
Canal to entrance of Harvey Lock, route follows Mississippi 
River for 5.5 miles. Section from Mississippi 
River to Atchafalaya River, LA, leaves Mississippi 
River through Harvey Lock about 3.3 miles above 
Canal Street and follows Harvey Canal No. 1 and 
Bayou Barataria to Bayou Villars, a land cut south of 
Lake Salvador to Harvey Canal No. 2, Harvey Canal 
No. 2 to Larose, LA, and a land cut to Houma, LA, 
thence over a land cut south of Bayous Black and 
Cocodrie, thence through Bayou Cocodrie and a land 
cut to Bayou Black; thence through Bayous Black, 
Chene, and Boeuf to Atchafalaya River, about 0.5 mile 
south of Morgan City, LA, a total of 95.5 miles. Alternative 
connection with Mississippi River near Algiers, 
LA, about 10.3 miles below Harvey Lock, consisting of 
a lock and land cut about 9 miles long intersecting 
Intracoastal Waterway at about mile 6 is complete. An 
alternative route from Mississippi River follows Bayou 
Plaquemine passing Indian Village, LA, and continuing 
on through lower Grand River to and through a lock at 
Bayou Sorrel in East Atchafalaya Basin protection 
levee, thence through levee borrow pit to Berwick Bay; 
and thence through Berwick Bay to Morgan City, LA, 
a total of 56 miles. This alternative route was enlarged 
from vicinity of Morgan City to Indian Village, LA, 
and extended from Indian Village, LA, through Bayou 
Grosse Tete and a new land cut to and through a new 
terminal lock and entrance channel to Mississippi 
River near Port Allen, LA, a total of 65 miles. Section 
from Atchafalaya River to Vermilion River, LA, begins 
at western end of Mississippi-Atchafalaya section and 
follows Atchafalaya River about 2.5 miles, portions of 
Little Wax Bayou, Possum Bayou, cutoffs, a land cut 
passing through North Bend Plantation to Bayou 
lBaanrdt hcoulto mskeiwrti, ngB anyoortuh eBdagreth oofl oCmoteew B laton cLheit tIlsel anBda ya,n da 
west edge of Weeks Island to Vermilion River, about 24 
miles below Abbeville, LA, a total of about 63.6 miles. 
Franklin Canal, St. Mary Parish, LA, extends southwesterly 
from Franklin, LA, on Bayou Teche, for 5.5 
miles to Bayou Portage, a section of "The Inland 
Waterway from Franklin to the Mermentau River, 
LA," and through bayou for 0.75 mile to Gulf Intra- 
11-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983. 
coastal Waterway, 121 miles west of Harvey Lock. 
Section from Vermilion River to Mermentau River, 
LA, begins at western end of Atchafalaya-Vermilion 
section and follows Vermilion River 1.3 miles, a part of 
Schooner Bayou Cutoff canal, and a land cut running 
generally northwesterly to Mermentau River at a point 
about 0.5 mile above its entrance into Grand Lake and 
about 16 miles below town of Lake Arthur, LA, a total 
of about 42.7 miles. Vermilion Lock was constructed 
Sabout 1.75 miles west of Vermilion River to prevent 
ingress of saltwater from Vermilion Bay. Section from 
Mermentau River to Calcasieu River, LA, begins at 
western end of Vermilion-Mermentau section and 
follows Mermentau River upstream for about 1.5 miles, 
a land cut running west-southwesterly to Lake Misere, 
passing north of lake and Bayou Misere, westerly to 
Sweet Lake, south and west of Sweet Lake, northwesterly 
to Bayou Tete Bois, through Bayou Tete Bois, 
Black Bayou, and cutoffs to a point on Calcasieu River 
about 16.6 miles below city of Lake Charles, LA, a total 
of about 37.1 miles. Calcasieu Lock was constructed 
near intersection of Calcasieu River and Intracoastal 
Waterway, mile 238 west of Harvey Lock, Calcasieu 
Parish, about 16.6 miles below Lake Charles, LA. 
Section from Calcasieu River to Sabine River, LA and 
TX, begins at western end of Mermentau-Calcasieu 
section, and follows Calcasieu River upstream about 
1.6 miles, a land cut running southwesterly 2.8 miles, 
thence west 22 miles to Sabine River at a point about 3 
miles below Orange, TX, a total of about 27.1 miles. 
(Refer to MRC alluvial valley map and Rigolets, Chef 
Menteur, St. Bernard, New Orleans, Barataria, Baton 
Rouge, Grosse Tete, Chicot Lake, Foster, Napoleonville, 
Morgan City, Belle Isle, Bayou Sale, Jeanerette, and 
Derouen quadrangles; Geological Survey maps, Cutoff, 
Houma, Gibson, Abbeville, Forked Island, Grand Lake 
East, Grand Lake West, Lake Charles, Sulphur, and 
Orange quadrangles; and NOAA Small-Craft Charts 
of Intracoastal Waterway, gulf section, Galveston Bay, 
TX, to Waveland, MS) 
Previous projects. For details see page 544 of 1963 
Annual Report. 
Existing project. Provides for a waterway, within 
the district, from Lake Borgne to Sabine River by the 
following improvements; a channel 16 feet deep and 
150 feet wide, from Mississippi River to Atchafalaya 
River, except in vicinity of Houma, miles 50.5 to 63.5, 
which is to be maintained at 12 by 125 feet; a channel 
16 by 150 feet through bypass route around Houma, 
LA, miles 50.5 to 63.5, and through alternative connection 
in Mississippi River below Algiers, LA, about 9 
miles long, a channel 16 by 200 feet from Atchafalaya 
River to Sabine River; a channel 12 by 150 feet in 
section between Lake Borgne Light 29 and New Orleans 
(via land cut through marsh and Inner Harbor Navigation 
Canal), 33.1 miles long; an alternative route 9 feet 
deep and 100 feet wide between Lake Borgne Light 29 
and New Orleans (via Rigolets, Lake Pontchartrain, 
and Inner Harbor Navigation Canal), 40.5 miles long; a 
channel 12 feet deep and 125 feet wide for Plaquemine- 
Morgan City alternative route from Mississippi- 
Atchafalaya section of waterway, in vicinity of Morgan 
City, through lower Atchafalaya River (Berwick Bay) 
and borrow pit of East Atchafalaya protection levee to 
and through Bayou Sorrel Lock which was constructed 
under existing project "Flood Contol, Mississippi River 
and Tributaries," thence through Lower Grand River 
to Indian Village, and thence by way of Bayou Grosse 
Tete and a new land cut to and through a new terminal 
lock and entrance channel to Mississippi River near 
Port Allen, LA, opposite lower limit of Port Baton 
Rouge; a channel 9 feet deep and 100 feet wide from 
Indian Village on Plaquemine-Morgan City alternative 
route through Bayou Plaquemine and Plaquemine Lock 
to Mississippi River at Plaquemine, LA, improvement 
of Franklin Canal as a connecting channel from Gulf 
Intracoastal Waterway (mile 121) to Franklin, LA, to 
afford a channel 8 feet deep and generally 60 feet wide 
with a width of 100 feet in its upper 300 feet; and a 
saltwater guard lock (Calcasieu Lock) in waterway at 
mile 238 west of Harvey Lock. Project also provides 
for: widening at bends; passing places, mooring basins; 
locks or guard locks; such railroad bridges over 
artificial cuts as are necessary; purchase of pipeline 
dredge; construction and operation of new drainage 
canals and pumping facilities to restore parish drainage 
systems where intercepted; construction of movable 
bridges at Missouri Pacific Railroad and State Highways 
31 and 996 (in lieu of State Highway Bridge 31, a 
tunnel was constructed, and additional cost over estimated 
cost of bridge was borne by local interest); 
fixed-trestle bridges for crossing proposed landside 
drainage canals; lift bridges at Louisiana Highway 
168, Port Allen, LA, at Texas & Pacific Railway, Port 
Allen, LA, and at Texas & Pacific Railway, Morley, 
LA; and for annual payments to Board of Commissioners 
of Port of New Orleans for use of a portion of 
Inner Harbor Navigation Canal. Length of waterway 
within district is 384.1 miles via northerly or Port 
Allen route, and 299.4 miles via southerly or Harvey 
Canal route. Normal range of tide, 10 inches; extreme 
range, 14 inches. A severe storm may cause a high tide 
of from 6 to 9 feet. 
Estimated cost for new work, exclusive of amounts 
expended on previous projects, is $157,833,827 Federal 
and $27,535,000 non-Federal, divided as follows; Algiers 
Lock and canal, completed June 1961, $15,895,924 
Federal and $2,185,000 non-Federal; Plaquemine- 
Morgan City route, completed October 1963, $26,869,372 
Federal and $2,250,000 non-Federal; and remainder of 
waterway (October 1980), $115,068,531 Federal and 
$23,100,000 non-Federal, including $73,700,000 Federal 
and $21,500,000 non-Federal for modification (authorized 
by Public Law 87-874), October 1962. In addition, 
the Coast Guard is to provide navigation aids at an 
estimated cost of $32,000. 
Construction of bulkheads and jetties at Lake Borgne 
and Chef Menteur, LA, is considered inactive and 
excluded from foregoing cost estimate. Estimated cost 
(1956) of this item is $440,000. Construction of a doubleleaf 
bascule, four-lane highway bridge provided for 
under this project has become unnecessary because 
11-8

NEW ORLEANS, LA, DISTRICT 
portion of project over which bridge was to be constructed 
was incorporated in project "Mississippi River- 
Gulf Outlet" which provides for a larger bridge. Bayou 
Sorrel and Bayou Boeuf Locks were constructed and 
are being maintained and operated with "Flood Control, 
Mississippi River and Tributaries" funds. Therefore, 
construction, maintenance, and operation costs are not 
included in approved estimates referred to heretofore. 
(See Table 11-D for locks on Gulf Intracoastal Waterway 
in New Orleans District.) 
Local cooperation. Algiers Lock and Canal: All 
assurances required for construction were furnished. 
Local agency has failed to convey all fee and easement 
tracts with acceptable title evidence to the United 
States. However, authority has been received to accept 
the interests conveyed as best available from local 
agency with the understanding that the United States 
rely upon assurances of local cooperation should any 
claims against the United States occur as a result of 
failure of local agency to complete transfer of title. 
Plaquemine-Morgan City alternative route: All 
assurances required for construction were furnished. 
Title by United States has been acquired to all but 35 
tracts, for which local agency failed to comply fully 
with curative requirements in title certificate. Authority 
was given to accept the tracts conveyed as best available 
from local interests and to rely upon assurances of local 
cooperation furnished by local agency should any claims 
against the United States occur as a result of failure of 
local agency to complete transfer of title. Louisiana 
Office of Public Works has furnished assurances for 
maintenance and improvement. 
Modification authorized by River and Harbor Act of 
1962: Local interests must furnish lands, rights-of-way, 
and spoil-disposal areas for enlargement and future 
maintenance of project, make alterations to utilities; 
construct, maintain, and operate all bridges desired in 
connection with bypass channel around Houma, LA, 
and hold the United States free from damages. Assurances 
were requested in April 1963; however, none of 
the 11 local agencies involved has furnished assurances 
requested. Main objection to participation is requirement 
that local interests be responsible for alteration of 
utilities. 
Replacement of Vermilion Lock: The Vermilion 
Parish Police Jury was requested to execute an Agreement 
of Local Cooperation on Oct. 26, 1972, agreeing to 
provide without cost to the United States all lands, 
easements, and rights-of-way required for construction 
and subsequent maintenance of the replacement lock 
and approach channels thereto, and hold and save the 
United States free from damages due to construction 
and maintenance of the project, including erosion of 
the channel beyond the rights-of-way furnished for the 
replacement lock and the approach channels thereto 
and comply with the provisions of Public Law 91-646 
and Sec. 221 of Public Law 91-611. They furnished 
formal assurances covering all requirements of local 
cooperation, including Public Law 91-611 and Public 
Law 91-646, on Mar. 19, 1975. These assurances were 
in the process of being accepted by the United States, 
when the Water Resources Development Act of 1976 
was enacted authorizing the 110-foot-wide lock. The 
assurances were executed by the Police Jury on Dec. 6, 
1976, and were accepted by the District Engineer on 
behalf of the United States on Feb. 8, 1977. The Acting 
Director of Real Estate for the Secretary of the Army 
approved the assurances on Jul. 5, 1977. The project 
was renamed "Leland Bowman Lock (Replacement)" 
by House Resolution 4284 dated Sep. 21, 1981 (House 
Report 97-234). 
Terminal facilities. Large terminal and transfer 
facilities, suitable for receiving and shipping commodities 
by barge, are available at principal cities in 
Louisiana; namely, New Orleans, Baton Rouge, Harvey, 
Morgan City, and Lake Charles. Facilities at New 
Orleans are on Inner Harbor Navigation Canal. Canal 
and facilities were leased from Board of Commissioners, 
Port of New Orleans, Apr. 1, 1944, and are now 
operated by the United States, toll free, 24 hours per 
day. At Morgan City, on Atchafalaya River, there are 
two large and three small wharves open to all without 
charge. Otherwise, facilities are considered adequate 
for existing commerce. 
Operations and results during fiscal year. Maintenance 
by hired labor: Real estate activities, condition 
and operation studies, condition surveys, stream gaging, 
and channel patrol. Locks, bridges, and waterways 
were operated and maintained. 
Fender systems were repaired at Algiers, Calcasieu, 
Harvey, Port Allen, and Vermilion Locks. Work by 
hired labor consisted of major repairs to the Algiers 
Lock. Miscellaneous repairs were made to the Florida 
Avenue Bridge, Vermilion, Harvey, and Port Allen 
Locks. 
Maintenance by contract: Dredging under two contracts 
included removing 381,870 cubic yards from 
below Bayou Sorrel Lock and 3,408,505 cubic yards 
from Mermentau Calcasieu River Section. Dredge 
operations in the New Orleans Harbor included removing 
338,060 cubic yards of material. 
Construction was initiated on Oct. 15, 1981 for replacement 
of Leland Bowman Lock (Vermilion) and is 
65 percent complete. 
Condition as of Sep. 30. Construction was initiated 
July 1929 and project, as modified, is 55 percent 
complete. For information on completion of segments 
of waterway, see 1965 Annual Report, pages 523 and 
524. 
Work remaining to complete the project consists of 
enlarging waterway as provided by 1962 River and 
Harbor Act. Construction of bulkheads at Lake Borgne 
and Chef Menteur are inactive features as this work 
has not been necessary. President Carter, as a result of 
his review of water resource projects in April 1977, 
changed the site of the proposed new shiplock to the 
Industrial Canal in Orleans Parish and recommended 
that the existing lock be replaced and expanded at the 
existing site. This is a new concept and requires re- 
11-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
institution of General Design planning with attendant 
slips in the schedule components. 
10. HOUMA NAVIGATION 
CANAL, LA 
Location. Extends from Gulf Intracoastal Waterway 
at mile 59.5 west of Harvey Lock southerly about 16 
miles, thence southeasterly 10.5 miles to Terrebonne 
Bay, and 9.5 miles across bay to deep water in Cat 
Island Pass. At mile 11.3 above Cat Island Pass, Houma 
Navigation Canal crosses Bayou Petit Caillou, and 20 
miles above Cat Island Pass it crosses Bayou Grand 
Caillou. No other major waterways are crossed by 
Houma Navigation Canal. (See Army Engineer and 
Geological Survey quadrangle maps, NOAA Nos. 11352 
and 11340 Sailing Charts; and NOAA Nos. 11357 and 
11356 Small-Craft Charts on the Intracoastal Waterway. 
Existing project. Provides that United States assume 
maintenance and operation of Houma Navigation Canal, 
constructed by Parish of Terrebonne, to dimensions of 
15 by 150 feet. Normal range of tide is 10 inches at 
mouth and 4 inches at Houma; extreme range is 14 
inches at mouth and 6 inches at Houma; wind and tide, 
1 to 3 feet at mouth; flood, 3 to 4 feet in upper section. 
Local cooperation. Fully complied with. For details 
see page 11-13, Annual Report FY 1980. 
Terminal facilities. Privately-owned and operated 
facilities are adequate for existing commerce which is 
mainly seafood plants; oil companies and oil company 
supplies; sugar refining; and marine repair shops and 
towing. Southern Pacific Lines has dock facilities in 
Houma, LA. Ample space exists for expansion of existing 
facilities, or for the construction of new wharves and 
appurtenances. 
Operations and results during fiscal year. Hired 
labor work consisted of reconnaissance surveys, stream 
gaging, and condition and operation studies. 
Maintenance dredging under one contract, stations, 
19+99 to 1310+00, was completed Apr. 11, 1983, with 
2,024,039 cubic yards of dike construction and stations 
1373+00 to 2141+00, was initiated Jul. 7, 1983, with the 
removal of 1,790,720 cubic yards of material. 
Condition as of Sep. 30. Maintenance by the United 
States commenced in November 1964. 
11. LELAND BOWMAN LOCK, LA 
(REPLACEMENT OF LOCK) 
(FORMERLY VERMILION 
LOCK, LA) 
Location. In the Louisiana section of the Gulf Intracoastal 
Waterway near Abbeville, Vermilion Parish, 
LA, about 163 miles west of Harvey Lock. 
Existing project. The present Leland Bowman Lock, 
located in the most heavily utilized section of the Gulf 
Intracoastal Waterway, is the controlling structure in 
both width and depth. The lock is used for navigation 
and flood control (prevention of salt water intrusion). 
The tumbler-type gates are unsatisfactory for the dual 
purpose. (Flood Control-Navigation) operation required, 
since once the gates are lowered to pass flood flows, 
they cannot be safely raised until the differential stage 
across the lock is reduced to about 0.5 foot. The replacement 
lock also will provide a larger and more efficient 
outlet for floodwaters. Estimated cost for new work 
(October 1982) is $32,200,000 Federal and $240,000 
non-Federal. The project was renamed "Leland Bowman 
Lock (Replacement)" by House Resolution 4284 
dated Sep. 21, 1981 (House Report 97-234.) 
Local cooperation. Provide all lands, easements and 
rights-of-way for construction of the project and hold 
and save the United States free from damages due to 
construction and maintenance works. The Vermilion 
Parish Police Jury furnished assurances covering all 
requirements of local cooperation, including PL 91-611 
and PL 91-646, on Mar. 19, 1975. These assurances 
were in the process of being accepted by the United 
States, when the Water Resources Development Act of 
1976 was enacted authorizing the 110-foot-wide lock. 
Amended assurances of local cooperation were accepted 
on behalf of the United States by the Secretary of the 
Army on Jul. 5, 1977. The Vermilion Parish Police 
Jury on May 26, 1981 granted right of entry for 
construction of project. 
Terminal facilities. None. 
Operations and results during fiscal year. Construction 
was initiated Oct. 15, 1981. 
Condition as of Sep. 30. The project is 30 percent 
complete. 
12. MERMENTAU RIVER, LA 
Location. Work covered by this project is 35 to 70 
miles southeast of Lake Charles, LA, along lower 
Mermentau River below Grand Lake, mile 25, to Gulf 
of Mexico; Inland Waterway from Vermilion Bay to 
White Lake, White Lake to Grand Lake, and from 
Schooner Bayou to Intracoastal Waterway-Gulf section 
(Schooner Bayou Cutoff); North Prong of Schooner 
Bayou; and waterway from White Lake to Pecan Island, 
LA, and artificial canal, extending from 5-foot-depth 
contour in White Lake, almost due south for about 1.8 
miles to Pecan Island. (Refer to Coast Charts Nos. 
11344 and 11349, NOAA Small-Craft Chart No. 11348 
on the Intracoastal Waterway, Geological Survey maps, 
Sweet Lake, Hog Bayou, Grand Lake West, Grand 
Lake East, Constance Bayou, Forked Island, Pecan 
Island, and Abbeville quadrangles.) 
Existing project. Flood control, navigation, irrigation, 
and salinity control in coastal marsh of lower 
Mermentau River Basin and channel enlargement of 
lower Mermentau River below Grand Lake, mile 25, to 
a minimum section of 3,000 square feet below mean 
low gulf level for discharge of flood flows; construction 
of a sector-gated control structure at Catfish Point, 
mile 24 above mouth of Mermentau River, for discharge 
of flood flows and control of tidal flows and saltwater 
11-10

NEW ORLEANS, LA, DISTRICT 
intrusion in Mermentau River; channel enlargement 
and realinement of Inland Waterway from Vermilion 
Bay to White Lake, 12.04 miles, and from White Lake 
to Grand Lake, 6.14 miles, to a minimum section of 
3,000 square feet below mean low gulf level or interflow 
between lakes and discharge of flood flows; construction 
of a sector-gated control structure in enlarged channel 
immediately north of abandoned Schooner Bayou Lock 
reservation for discharge of flood flows and control of 
tidal flows and saltwater intrusion; channel enlargement 
of North Prong of Schooner Bayou and Schooner 
Bayou Cutoff, 6.69 miles, to 6 by 60 feet, mean low gulf 
level, for navigation purposes; and maintenance of 
existing 5- by 40-foot, mean low gulf level, waterway 
from White Lake to Pecan Island, LA, 1.8 miles long, 
for navigation. In addition, project provides for incorporation 
of that section of project, "Inland Waterway 
from Franklin, LA, to Mermentau River," west of 
Vermilion Bay, a waterway that includes Schooner 
Bayou Lock. Project was reclassified as an "Operation 
and Maintenance, General" project under category, 
"Navigation (Locks, Dams, Reservoirs, and Canals)" by 
authority of Chief of Engineers, Apr. 23, 1956. Because 
of failure of both east and west gates, Schooner Bayou 
Lock was closed by a dike across east approach channel 
and traffic routed through new control structure. Under 
ordinary conditions mean range of tide on Mermentau 
River near mouth is 1.6 feet and near head about 3 
inches. Variation of water surface near the mouth may 
be as much as 7 or 8 feet, due to hurricanes on the gulf, 
and near head from 8 to 12 feet, due to freshets. New 
work was completed in 1956. Estimated cost for new 
work (October 1982) is $6,570,000 Federal and $840,000 
non-Federal, including $250,000 contributed funds. 
Local cooperation. Fully complied with. For details 
see page 1022, Annual Report FY 1948. 
Terminal facilities. Privately-owned and operated 
facilities are adequate along the Mermentau River and 
Bayous Nezpique and des Cannes for the principal 
commodities transported, which are petroleum and its 
products. A public wharf is located at Lake Arthur, 
LA, but due to insufficient use it has not been maintained 
and in its present condition is not usable. Sites 
for future expansion of these facilities are available 
and will be provided by non-Federal interests as 
required. 
Operations and results during fiscal year. Hired 
labor continued operation and maintenance of Schooner 
Bayou and Catfish Point Control Structures, condition 
and operation studies, reconnaissance surveys, channel 
patrol, and water quality studies. 
Other work by hired labor forces during the fiscal 
year: Schooner Bayou Control Structures; construction 
of a new boat landing, and maintenance repairs to the 
guidewalls. 
Condition as of Sep. 30. Construction of project 
began April 1947 and completed July 1952. New work 
dredging was accomplished from April 1947 to June 
1952. Catfish Point Control Structure was constructed 
from November 1948 to August 1951. Reservation 
comprises 9.7 acres. Schooner Bayou Lock and Control 
Structures: Schooner Bayou Lock and Dam were completed 
in 1913 and 1914, respectively, and the Lockmaster's 
house in 1917. Lock was closed to navigation 
May 7, 1951, and abandoned by authority of Chief of 
Engineers on Oct. 9, 1951. Permanent closure of lock 
channel and tie-in dikes was completed September 
1951. Construction of control structures was accomplished 
from August 1949 to May 1951. Reservation 
comprises 6.9 acres. 
13. MISSISSIPPI RIVER, BATON ROUGE 
TO GULF OF MEXICO, LA 
Location. This reach of the river flows southeasterly 
through southeastern portion of Louisiana. At Head of 
Passes, approximately 233.1 miles below Louisiana 
Highway Commission bridge at Baton Rouge, river 
branches into three main passes: Southwest Pass, South 
Pass, and Pass a Loutre, two of which, Southwest Pass 
and South Pass, are improved under existing project. 
Head of Passes to mouths of Southwest and South 
Passes are 20.1 and 13.5 miles, respectively. Mouth of 
Southwest Pass is 141 miles west of Mobile, AL, and 
349 miles east of Galveston, TX. Mouth of South Pass is 
18.5 miles northeast of mouth of Southwest Pass. (Refer 
to NOAA Coast Charts Nos. 11361, 11364, and 11369; 
MRC alluvial valley map, and Zachary, Baton Rouge, 
White Castle, Donaldsonville, Thibodaux, Mount Airy, 
Bonnet Carr6, Hahnville, New Orleans, St. Bernard, 
Barataria, Pointe a la Hache, Black Bay, Empire, 
Forts, West Delta, East Delta, and Southwest Pass 
quadrangles and 1980 (48th edition) folio of flood control 
and navigation maps, Mississippi River, Cairo, IL, to 
Gulf of Mexico, LA, published by the MRC.) 
Previous projects. For details see page 552 of Annual 
Report for 1963. 
Existing project. Provides for channel dimensions 
as follows: Between a line one-tenth mile below Louisiana 
Highway Commission bridge at Baton Rouge 129.3 
miles to upper port limits of New Orleans, 40 by 500 
feet mean low water; within limits of port of New 
Orleans, where that authority has jurisdiction over 
both banks of river, a distance of 17.8 miles, 35 by 1,500 
feet, measured from a line generally 100 feet from face 
of left bank wharves, but not closer than 100 feet to 
wharves on right bank; within 35- by 1,500-foot channel 
in port limits of New Orleans, 40 by 500 feet; from 
lower limits of port of New Orleans 86.7 miles to Head 
of Passes, 40 by 1,000 feet; Southwest Pass, 17.5 miles 
from Head of Passes to jetty channel, 40 by 800 feet; 4.1 
miles in the Southwest Pass bar and jetty channel, 40 
by 600 feet; South Pass from Head of Passes to outer 
ends of jetties, 13.5 miles, 30 by 450 feet; and 1.2 miles 
in the South Pass bar channel, 30 by 600 feet. Plane of 
reference through New Orleans and below is mean low 
gulf. Plane of reference above New Orleans is low 
water reference plane. General plan of improvement of 
Southwest Pass provides for constructing pass to 
uniform cross section with about 1,420-foot surface 
width by means of jetties, spur dikes, and bulkheads; 
11-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
for channel maintenance by dredging from Cubits 
Gap, mile 3.5 AHP through the gulf entrance channel, 
mile 21.5 BHP; for construction of small revetted 
openings through narrow portions of banks of pass for 
purpose of strengthening and nourishment of banks; 
for closure of minor outlets not required for maintenance 
of banks; for construction of sills to prevent 
enlargement of the Venice Jump and Cubits Gap; for 
repairs to sill across Pass a Loutre and bank revetment 
at Head of Passes; for construction of dikes with a view 
to reducing width of river above Head of Passes; for 
construction of a submerged deflecting dike above 
Head of Passes; and for other minor work. East jetty is 
about 24,950 feet long and west jetty 19,699 feet. Jetties 
are composed of a substructure of brush mattresses, 
orginally built to about elevation of mean low gulf, 
surmounted with a superstructure of concrete blocks 
and large riprap and/or stone rubble mound of core 
and cover stone. Spur dikes are composed of cribwork 
of round piling filled with willows and stone, or with a 
curtain of round piles along upstream face. General 
plan of improvement of South Pass provides for construction 
and maintenance of jetties and spur dikes; for 
channel maintenance by dredging from Head of Passes 
through the Gulf Entrance Channel beyond mile 13.5 
BHP; maintenance of a sill across Pass a Loutre, and 
for seaward extension of east jetty at mouth of pass; 
removal of west dike and construction of spur dikes 
and bank revetment at Head of Passes; removal of false 
point at head of South Pass to bottom elevation of 
minus 45 feet and revetment of new bank line and 
construction and maintenance of east and west headland 
structure at Head of Passes. East jetty foundation is 12, 
070 feet long; inner east jetty is 11,170 feet long; west 
jetty is 7,820 feet long; and inner west jetty is 4,710 feet 
long. Jetties are composed of a substructure of brush 
mattresses surmounted by a superstructure of stone 
and/or concrete blocks and large riprap. Spur dikes 
are composed of cribwork of round piling filled with 
willows and stone. Plane of reference is mean low gulf. 
Variation of water surface is 16 inches at mouths and 
10 inches at head of the passes, due to tides. Extreme 
range of tides at mouths of passes due to hurricanes in 
about 10 feet. At New Orleans extreme range of water 
surface is about 20 feet due to floods. At Baton Rouge 
extreme range is about 45 feet due to floods. 
Estimated cost of existing project (October 1983) is 
$244,000,000 Federal. In addition, Coast Guard is to 
provide navigation aids at an estimated cost of 
$1,222,800. 
Local cooperation. None required, except for modification 
of project in connection with Mississippi River- 
Gulf Outlet, which is reported separately. 
Terminal facilities. Piers, wharves, or docks serve 
the Port of New Orleans. Most wharves on east or left 
bank parallel riverbank forming nearly a continuous 
covered quay about 10 miles long. Public wharves 
controlled by Board of Commissioners, Port of New 
Orleans (the Dock Board), cover 62 percent of improved 
waterfront. These facilities include a shipside grain 
elevator, general cargo and cotton wharves, fruit 
landings, bunkering facilities, terminal warehouses, 
railroad terminals, marine railways, and drydocks. 
(For further details see Port Series No. 20, "The Port of 
New Orleans, LA" revised 1977.) A foreign trade zone 
is located in Port of New Orleans. City of Baton Rouge 
has a reinforced concrete dock for deep-sea vessels with 
mechanical-handling facility. Attached to downstream 
end of wharf is a floating wharf boat 231 by 40.5 feet, of 
2,000-ton capacity. Facilities are served by a transfer 
boat and municipal terminal having a capacity of 40 
cars per day. Private terminals for handling oil, grain, 
bauxite ore, and other products are at points on both 
sides of river between New Orleans and Baton Rouge. 
Facilities are considered adequate for existing commerce. 
(For further details, see "Port Facilities" included 
in "Flood Control and Navigation Maps of the Mississippi 
River, Cairo, IL, to the Gulf of Mexico, LA," 
published annually by the MRC, and Port Series No. 
19, vol. 1, "Port St. Joe, FL, Pensacola, FL, Baton 
Rouge, LA, and Lake Charles, LA," revised 1979.) 
Operations and results during fiscal year. The 
draft Supplement II to the GDM was completed in 
September 1983, and the draft environmental impact 
statement (EIS) for this supplement was also completed 
in September 1983. 
Maintenance: (a) Baton Rouge to New Orleans: The 
U.S. dustpan dredge Jadwin and one hopper dredge 
removed 9,685,638 cubic yards of shoal material at a 
cost of $8,278,100. 
(b) New Orleans Harbor: One leased dredge contract 
removed 3,599,803 cubic yards of material at a cost of 
$1,873,200. 
(c) Head of Passes and Southwest Pass: The U.S. 
Hopper dredge Wheeler removed 2,737,665 cubic yards 
of shoal material from the lower jetty and bar channels 
at a cost of $2,846,100. Four leased hopper dredges 
removed 9,123,826 cubic yards of shoal material at 
Head of Passes and the lower jetty and bar channels 
under two contracts at a total cost of $14,178,300. Two 
cutterhead dredges, under one unit price contract, 
removed 9,239,673 cubic yards of shoal material at a 
cost of $7,500,000. 
(d) Southwest Pass: Work was completed on one 
bank stabilization contract for repairs to ten pile dikes 
on the left descending bank between miles 10.77 and 
17.80 BHP. Total cost of this contract was $3,085,100. 
In addition, hired labor units repaired pile dikes 
between Head of Passes and mile 12.6 BHP on the 
right descending bank at a total cost of $917,900, and 
dredging targets in the lower bar and jetty channels at 
a cost of $97,800. 
(e) Southwest Pass: Hired labor repairs were made 
to pile dike structures at a cost of $917,900. 
(f) Langfitt wharf: Repairs made to wharf at a cost of 
$22,100. 
Condition as of Sep. 30. The existing project is 40 
percent complete. Deepening Southwest Pass to 40 feet 
mean low gulf, as authorized by the modification of 
Mar. 2, 1945, was completed in September 1963. 
Deepening the channel to 40 feet mean low water from 
11-12

NEW ORLEANS, LA, DISTRICT 
Baton Rouge to New Orleans and to 40 feet mean low 
gulf in New Orleans Harbor, as authorized by the 
modifications of Oct. 23, 1962, was completed in August 
1963. 
14. MISSISSIPPI RIVER-GULF 
OUTLET, LA 
Location. In State of Louisiana and extends from 
existing Inner Harbor Navigation Canal at a point 
7,500 feet north of existing lock and about 11,000 feet 
from Mississippi River, to a turning basin south of 
Michoud, LA, and then as a land and water cut from 
turning basin south of Michoud, LA, southeasterly to 
and along south shore of Lake Borgne and through 
marshes to and through Chandeleur Sound to 38-foot 
contour in Gulf of Mexico. (Refer to NOAA Coast 
Charts Nos. 11340, 11360, 11363, 11369, 11371, and 
11373. Also see MRC 1980 (48th edition) folio of maps, 
Mississippi River-Cairo, IL, to Gulf of Mexico, LA.) 
Existing project. Provides for a seaway canal, 36 by 
500 feet, extending 76 miles as a land and water cut 
from Michoud southeasterly to and along south shore of 
Lake Borgne, and across Chandeleur Sound to Chandeleur 
Island and increasing gradually to 38 by 600 
feet in Gulf of Mexico, with protective jetties at 
entrance, a permanent retention dike through Chandeleur 
Sound, and a wing dike along islands as required. 
It also provides for an inner tidewater harbor consisting 
of 1,000- by 2,000-foot turning basin 36 feet deep at 
landward end of seaway canal, and a connecting channel 
36 by 500 feet wide extending westerly along Gulf 
Intracoastal Waterway from turning basin to Inner 
Harbor Navigation Canal, including construction of a 
suitable highway bridge with approaches to carry 
Louisiana State Highway 47 (formerly 61) over channel. 
Plan further provides for future construction of a 
channel and lock in the vicinity of Meraux to furnish an 
additional connection between tidewater harbor and 
Mississippi River. Estimated cost for new work (October 
1983) is $499,000,000 Federal and $208,000,000 
non-Federal. This does not include modification for 
Mississippi River-Gulf Outlet, Michoud Canal, which is 
reported separately. The Federal cost excludes $45,000 
for aids to navigation by U.S. Coast Guard. 
Local cooperation. Original assurances furnished 
and accepted. Local agency has furnished Supplemental 
Assurance covering Public Law 91-646. Rights-of-entry 
for entire project were furnished by local agency which 
is in process of actively conveying to the United States 
title to remaining tracts. Supplemental assurances 
reflecting the changes made necessary by enactment of 
the Water Resources Development Act of 1976 were 
requested on Jan. 12, 1977. The Board of Commissioners 
of the Port of New Orleans, by letter dated Sep. 18, 
1978, stated that they are unable to provide the required 
supplemental assurances at this time. They are concerned 
about the possible effects of the proposed new 
Inner Harbor Navigation Canal Lock on this project 
and pending legislation concerning local assurances 
for the Inner Harbor Navigation Canal project. Local 
interests have provided right of entry for construction 
for the Baptiste Collette Bayou portion of this project. 
Terminal facilities. The only facility on the waterway 
is the Public Bulk Terminal of New Orleans constructed 
by Board of Commissioners, Port of New Orleans, on 
left descending bank at mile 63. Two new-container 
ship berths have begun operation at the Industrial 
Canal end of the seaway. 
Operations and results during fiscal year. New 
work by hired labor: Engineering environmental and 
economic studies were completed for the new lock and 
connecting channels feature. One contract for foreshore 
protection test section, south bank, Chalmette Area, 
station 475 to 501 was completed December 1982. 
Condition as of Sep. 30. Construction was initiated 
March 1958 and entire project is 75 percent complete. 
The channel was opened to navigation Jul. 25, 1963, 
and completed Jan. 20, 1968. Paris Road Bridge was 
opened to traffic Jul. 21, and completed Nov. 14, 1967. 
Approximately 3 miles of first- and second-lift stone 
dikes have been constructed on north side of channel 
and approximately 8.27 miles of first-lift and 7.34 
miles of second-lift stone dikes have been constructed 
on south side of channel in Breton Sound. Principal 
work required to complete project is construction of 
new ship lock, raising and extending dikes, and 
construction of foreshore protection. The site for the 
lock remained the major problem. President Carter, as 
a result of his review of water resource projects in 
April 1977, changed the site for the proposed shiplock 
to the Industrial Canal in Orleans Parish and recommended 
that, if justified, the existing lock should be 
replaced and expanded in place and that care should be 
taken to minimize dislocation of residents living adjacent 
to the site. These recommendations are being 
addressed in an Evaluation Report scheduled for 
completion in FY 1984. 
15. MISSISSIPPI RIVER OUTLETS, 
VENICE, LA 
Location. In the coastal marsh area and in the 
vicinity of the Mississippi River at about miles 10 to 11 
above the Head of Passes. (Refer to NOAA Coast Chart 
No. 1361.) 
Existing project. Provides for additional navigation 
outlets in the vicinity of Venice, LA, by enlargement of 
the existing channels of Baptiste Collette Bayou and 
Grand-Tiger Passes to 14 by 150 feet with entrance 
channels in open water 16 by 250 feet and jetties to the 
6-foot-depth contour, if and when justified, to reduce 
cost of maintenance dredging. Existing project was 
completed at a cost of $10,008,400. 
Local cooperation. For details see page 11-17, 
Annual Report, FY 1980. 
Assuring Agency: Plaquemines Parish Commission 
Council. Basic assurances for the project have been 
furnished. Amended assurances covering Public Laws 
91-646 and 91-611 were received on Aug. 5, 1977. 
11-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Terminal facilities. In the Venice area, each operator 
of a construction, repair, or supply facility provides 
dock and transfer facilities to meet his own needs or 
arranges to use those of another. These facilities are 
considered adequate for the anticipated traffic. If new 
industry or supply facilities are established, they would 
provide any needed terminal facilities for their use. 
Ample areas for future expansion are available. 
Operations and results during fiscal year. Hired 
labor work consisted of reconnaisance surveys, condition 
and operation, stream gaging and engineering studies. 
Contract work for maintenance dredging at Baptiste 
Collette Bar Channel, was completed Jul. 1, 1983, with 
a total of 956,545 cubic yards of material removed: 
maintenance dredging at Tiger Pass was also completed 
on Jul. 18, 1983, with 2,214,838 cubic yards of 
material removed. 
Condition as of Sep. 30. The project is 90 percent 
complete. 
16. REMOVAL OF 
AQUATIC GROWTH, LA 
Location. Lakes and streams tributary to the gulf 
coast. 
Existing project. Removal of plants from navigable 
waters of Florida, Alabama, Mississippi, Louisiana, 
and Texas, so far as they are or may become an 
obstruction to navigation, by any mechanical, chemical, 
or other means whatsoever; for construction and operation 
of boats equipped with suitable machinery for 
such removal; and construction and operation of booms 
to prevent plants drifting from one stream to another. 
Local cooperation. None required. 
Operations and results during fiscal year. Maximum 
use of funds available was made by using chemical 
methods of destruction. Maintenance continued in main 
waterways and principal tributaries to prevent waterhyacinth 
obstructions and damage to navigation. Preventive 
maintenance work was carried out in secondary 
streams and feeder areas whenever possible. In some 
cases where alligatorweed has previously kept waterhyacinth 
fringes confined along the banks, attack of 
the alligatorweed flea beetles (Agasicles) has reduced 
its competitiveness and water-hyacinths are multiplying 
and spreading in the waterways. A total of 30,792 acres 
of water-hyacinth were treated by chemical in Bayou 
Black, Lake Cataouatche and feeder streams, Lake des 
Allemands area, the Port Allen-Morgan City Route 
and Alternate Route of the Gulf Intracoastal Waterway, 
Lake Dauterive and Grand Lake areas, Bayou Penchant- 
Bayou Copasaw area, the Gulf Intracoastal Waterway, 
Bayou Lafourche, Bayou Lacassine, and Bayou Teche. 
Aerial spraying by helicopter controlled 4,831 acres. A 
mild winter, excessive rainfall, and extreme summer 
water-hyacinth weevil (Neachetina eichhorniae) has 
been made and populations are increasing. A large 
scale operations management test using the waterhyacinth 
weevil and the most promising plant pathogen 
(Cercospora rodmanii) has begun and will be monitored 
for effectiveness of control. A moth (Samoedes albiguttalis) 
has recently been introduced to assist in the 
control of water-hyacinth. 
Condition as of Sep. 30. From 1900 to 1902 a boat 
with suitable machinery for destroying hyacinth by 
crushing was operated. From that time until 1937 
hyacinths were destroyed through use of a solution of 
arsenic and caustic soda which was sprayed on vegetation. 
The vegetation was removed by hand crews, and 
vegetation movement was controlled by booms and 
barricades. Use of arsenic was discontinued and hand 
removal supplanted by use of mechanical equipment in 
conjunction with chemical spray (2,4-dichlorophenoxyacetic 
acid). Use of booms and barricades has been 
discontinued. Use of the quarterboat Tambour was 
discontinued in September 1981. Present methods of 
control are by means of chemical spraying supplemented 
by the use of insects and pathogens for biological 
control. Waterways Experiment Station is conducting 
a large-scale operations management test of 
insects and pathogens for control of water-hyacinth in 
Louisiana. 
17. TANGIPAHOA RIVER, LA 
Location. The river originates in the State of Mississippi 
and flows southerly to Lake Pontchartrain, LA, 
about 119 miles. (Refer to NOAA Coast Chart No. 
11369 and MRC alluvial valley map, Ponchatoula 
quadrangle.) 
Existing project. Improvement by removing overhanging 
trees, snags, and obstructions to navigation 
for 53.5 miles above mouth, and provide an 8- by 
100-foot entrance channel from the 8-foot depth contour 
in the lake to the 8-foot depth in the river. Variation in 
water surface is from 3 to 20 feet in the upper reaches 
due to freshets and from 2 to 5 feet in the lower reach 
due to winds and tides. The cost of existing project was 
$61,211, Federal (including $11,500 for previously 
completed portion and $49,711 for preauthorization 
studies and modification adopted under Sec. 107, 1960 
River and Harbor Act, as amended) and $29,346 contributed 
funds for the modification. 
Local cooperation. Fully complied with for completed 
work. 
Terminal facilities. None required. 
Operations and results during fiscal year. Hired 
labor forces conducted reconnaissance surveys and 
prepared plans and specifications. 
temperatures prevented additional areas from being 
placed in a maintenance status. The introduction of the
11-14

NEW ORLEANS, LA, DISTRICT 
18. WATERWAY FROM 
INTRACOASTAL WATERWAY TO 
BAYOU DULAC, LA 
(Bayous Grand Caillou and 
LeCarpe, LA) 
Location. Bayou LeCarpe is a tidal stream which 
rises about 1.5 miles southeast of Houma in Terrebonne 
Parish and flows southerly into Bayou Pelton, thence 
into Bayou Grand Caillou, which flows southwesterly 
into Caillou Bay, a total distance of about 40 miles. 
(Refer to Coast and Geodetic Survey Chart, No. 1116 
and Geological Survey maps of Houma, Dulac, Bayou 
DuLarge, and Dog Lake quadrangles.) 
Existing project. As modified, provides for a 10- by 
45-foot channel in Bayou LeCarpe from Gulf Intracoastal 
Waterway 2.6 miles to Houma navigation canal; 
a 5- by 40-foot channel through Bayou Pelton and 
Bayou Grand Caillou to Bayou Dulac, a distance of 
about 13.7 miles. Between miles 2.6 and 5, this project 
coincides with or is adjacent to 15- by 150-foot Houma 
navigation canal. Normal range of tide is 3 to 10 inches; 
from winds, 1 to 3 feet. Cost of new work, completed in 
August 1964, was $129,662. 
Local cooperation. Local interests must furnish 
lands, easements, and rights-of-way necessary for 
enlargement and subsequent maintenance of Bayou 
LeCarpe and of aids to navigation, and provide alterations 
to facilities, and hold the United States free from 
damage. Assurances were furnished and accepted. 
Local agency made available spoil areas for maintenance 
dredging of Bayou LeCarpe. None of these areas 
will be transferred to the United States. Meeting are 
continuing with local interests to resolve problems 
with their required cash contribution on total project 
cost. 
Terminal facilities. Many terminal and transfer 
facilities are in Houma and along waterways which 
flow through area between Houma and Gulf of Mexico. 
All facilities are privately owned and operated. Facilities 
are adequate for existing commerce and for 
reasonably prospective commerce. Ample space exists 
for expansion of existing facilities or for construction of 
new wharves and appurtenances. 
Operations and results during fiscal year. Hired 
labor consisted of real estate activities, reconnaissance 
surveys, water quality studies and maintenance dredging. 
Condition as of Sep. 30. The 5- by 40-foot channel 
was constructed from January 1938 to August 1938, 
and modification of October 23, 1962, for enlargement 
of 2.54 miles of Bayou LeCarpe to 10 feet by 45 feet was 
initiated in May and completed August 1964. 
19. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation activities pursuant to Sec. 107, Public 
Law 86-645, as amended (preauthorization.) 
Preauthorization studies costs as of Sep. 30, 1983, 
were $111,102 for Bayou Grand Caillou. 
Flood Control 
20. GRAND ISLE AND VICINITY, LA 
Location. In south Jefferson Parish, LA, along the 
Gulf of Mexico, about 50 miles south of New Orleans 
and 45 miles northwest of southwest pass (Mississippi 
River). 
Existing project. The project provides protection 
from waves driven by hurricanes that have a frequency 
of recurrence of up to once in every 50 years. The plan 
consists of a berm and vegetated dune extending the 
length of Grand Isle's gulf shore and a jetty to stabilize 
the western end of the island at Caminada Pass. The 
dune would have a 10-foot-wide crown at an elevation 
of 11.5 feet mean sea level, 1 on 5 side slopes, and 
protective vegetation. The sandfill berm would slope 
from an elevation of 8.5 feet mean sea level at the toe of 
the dune 180 feet gulfward to an elevation of 3 feet 
mean sea level and, from this point, would assume its 
natural slope to the offshore bottom. The jetty provided 
by the plan has a top width of 6 feet at an elevation of 4 
feet mean sea level, 1 on 2 side slopes, and extends 
approximately 2,600 feet along the western end of the 
island at Caminada Pass. Estimated cost of project 
(October 1983) is $7,910,000 Federal and $7,450,000 
non-Federal, including $2,040,000 contributed funds. 
Local cooperation. Provide without cost to the 
United States, all lands, easements, and rights-of-way 
for construction of the project, currently estimated to 
cost $4,410,000; accomplish without cost to the United 
States all relocations and alterations of buildings, 
streets, utilities, and other structures and improvements 
made necessary by the construction of the project; 
hold and save the United States free from claims for 
damages due to the construction works; assure maintenance, 
repairs, and periodic beach nourishment of 
the project after completion as may be required to 
serve the intended purposes in accordance with regulations 
prescribed by the Secretary of the Army, except 
that the Federal Government will contribute, for an 
initial period of 15 years, a sum currently estimated at 
$39,000 annually toward the cost of beach nourishment 
associated with beach erosion prevention, subject to a 
final determination on the basis of conditions of public 
use and ownership at the time of construction; provide 
a cash contribution for the hurricane protection function 
in an amount sufficient to insure that local investment 
in cash, equivalent work, and fair market value of 
lands and relocations are at least equal to 30 percent of 
all first costs allocated to that function, which cash 
contribution is presently estimated at $1,150,000; contribute 
cash or equivalent work an amount sufficient to 
pay the non-Federal share of construction costs allocated 
to beach erosion control, that amount presently estimated 
at $3,040,000 less $1,000,000 credit for completed 
work, west end jetty, or $2,040,000, the final amount to 
11-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
be determined at the time of project construction in 
accordance with cost-sharing procedures for beach 
erosion control as defined in the report; obtain approval 
by the Chief of Engineers, prior to commencement of 
any work on shore and beach protection phases of the 
project if undertaken separately from the recommended 
combined project, of detailed plans and specifications 
for the work contemplated and also the arrangements 
of prosecuting such work, excluding the preauthorization 
jetty construction; assure continued public ownership 
of the shore upon which the amount of Federal 
participation in the beach protection phase is based, 
and its administration for public use during the life of 
the project, and assure continued availability for public 
use of privately owned shores; assure that water pollution 
which would endanger the health of bathers will 
not be permitted; adopt and enforce appropriate ordinances 
to provide for the preservation of the improvement 
and its protective vegetation; at least annually, 
inform interests affected that the project will not 
provide any substantial protection from hurricane 
flooding on the bay side, or from hurricane surges 
higher in elevation than those of Hurricane Betsy of 
Sep. 9, 1965; comply with the provisions of the Uniform 
Relocation Assistance and Real Property Acquisition 
Policies of 1970, Public Law 91-646; agree to the 
requirements of Section 221 of the Flood Control Act of 
1970, Public Law 91-611. Comply with section 601 of 
Title VI of the Civil Rights Act of 1964 (Public Law 
88-352) that no person shall be excluded from participation 
in, denied the benefits of or subjected to discrimination 
in connection with the project on the grounds of 
race, creed, or national origin. Formal assurances 
requested of Jefferson Parish Council, and the Mayor, 
Town of Grand Isle, LA, on Aug. 12, 1981. The Town of 
Grand Isle is not financially capable to be the sole local 
assurer. The Louisiana Office of Public Works co-signed 
an agreement with the town of Grand Isle to assure 
complete financial responsibility on Jun. 1, 1983. 
Operations and results during the fiscal year. The 
dredging contract for beach erosion was awarded Jul. 
25, 1983, but construction was not initiated during 
FY 83. 
Condition as of Sep. 30. Construction is to be initiated 
on Nov. 15, 1983. 
21. LAKE PONTCHARTRAIN 
AND VICINITY, LA 
(HURRICANE PROTECTION) 
Location. In southeastern Louisiana, vicinity of New 
Orleans, in St. Charles, Jefferson, Orleans, St. Bernard, 
and St. Tammany Parishes, comprising lower land and 
water area between Mississippi River alluvial ridge 
and the Pleistocene escarpment to north and west. The 
dominant topographic feature is Lake Pontchartrain, a 
shallow landlocked tidal basin, about 640 square miles 
in area and averaging 12 feet deep, connecting with 
lesser Lake Maurepas to the west and through Lake 
Borgne and Mississippi Sound to the gulf to the east. 
The lake drains about 4,700 square miles of tributary 
area. (Refer to Geological Survey quadrangles Yscloskey 
and Malheureaux Point, Drum Bay, Door Point, Lake 
Eugenie, Oak Mound Bayou, Mitchell Keys, Lake Eloi, 
and Morgan Harbor; Engineer quadrangles Slidell, 
Covington, Ponchatoula, Springfield, Denham Springs, 
Donaldsonville, Mt. Airy, Bonnet Carrd, Spanish Fort, 
Chef Menteur, Rigolets, St. Bernard, New Orleans, 
and Hahnville; and Coast and Geodetic Survey Charts 
No. 1115 and 1116. 
Existing project. Provides for control of hurricane 
tides by construction of two independent units; the 
Lake Pontchartrain barrier plan involves construction 
of a barrier levee along eastern boundary of the lake 
with navigation and hurricane flood control structures 
in Chef Menteur Pass, the Rigolets, and at Seabrook. 
These protective works, together with strengthening 
and extension of existing protective works and the 
construction of the Seabrook Lock, will afford full 
protection to the south shore of Lake Pontchartrain 
from Bonnet Carre Spillway to the eastern limit of 
Orleans Parish levee along the Gulf Intracoastal Waterway 
and the Inner Harbor Navigation Canal. The 
Chalmette area plan consists of improving existing 
protection along east bank Inner Harbor Navigation 
Canal from the lock to Florida Avenue, then constructing 
a new levee to Mississippi River-Gulf Outlet, 
thence along south bank of gulf outlet to Bayou Lawler, 
then turning south and tieing into Mississippi River 
levee at Violet, LA. The approved Chalmette area plan 
was modified, under the discretionary authority of the 
Chief of Engineers, to provide for enlargement of the 
protected area by construction of a levee from the 
Mississippi River levee near Caernarvon, LA, to the 
vicinity of Verret, LA, thence to and along the Mississippi 
River-Gulf Outlet to a junction with the approved 
levee at the Bayou Lawler crossing of the Mississippi 
River-Gulf Outlet, and elimination of the levee in the 
approved plan from the Bayou Lawler and Mississippi 
River-Gulf Outlet to Violet, LA. Navigable drainage 
structures will be provided at Bayous Bienvenue and 
Dupre. Strengthening existing seawall at Mandeville 
on the north shore will insure that future hurricanes 
will not seriously damage this resort community. Estimated 
cost for new work (October 1983) is $594,000,000 
Federal and $282,000,000 non-Federal, including cash 
contribution of $202,540,000 which includes $23,500,000 
estimated to be capitalized value of operation and 
maintenance of Rigolets navigation lock and appurtenant 
channel. 
Local cooperation. Provide all rights-of-way; bear 
30 percent of the first cost, consisting of fair market 
value of providing all lands, easements, and rightsof-
way, including borrow and spoil disposal areas for 
construction, accomplish alteration and relocation of 
roads, railroads, pipelines, cables, wharves, drainage 
structures, and other facilities; maintain and operate 
all works after completion; and hold and save the 
United States free from damages. See H. Doc. No. 231, 
89th Cong., 1st sess. for more detailed requirements of 
local cooperation. 
11-16

NEW ORLEANS, LA, DISTRICT 
Assuring Agency: The Orleans Levee District, Lake 
Borgne Basin Levee District, St. Bernard Parish Police 
Jury, Louisiana Office of Public Works, and Pontchartrain 
Levee District. Basic assurances were received 
from the following: Orleans Levee District for the 
entire barrier plan and that portion of the Chalmette 
area plan in Orleans Parish; Pontchartrain Levee 
District for the barrier plan; Lake Borgne Levee 
District and St. Bernard Parish Police Jury for the 
Chalmette area plan in St. Bernard Parish. Supplemental 
assurances covering Public Law 91-646 have 
been received from the Orleans Levee District and the 
Pontchartrain Levee District. Lake Borgne Basin Levee 
District and St. Bernard Parish Police Jury have 
executed the supplemental assurance. The Governor of 
Louisiana executed an assurance containing all required 
provisions of local cooperation, including Public Law 
91-646, for and on behalf of St. Tammany Parish. 
Approval of this assurance is being delayed pending 
receipt of supporting documents. Louisiana Office of 
Public Works is assisting in obtaining the required 
documents. 
Operations and results during fiscal year. Preparation 
of design memorandums and plans and specifications 
continued by hired labor. Preparation of four 
design memorandums is underway. All four are 
scheduled for completion in FY 84. 
Condition as of Sep. 30. Construction started May 
1967 and is 51 percent complete. 
Contract work continued on six contracts. Construction 
was initiated on four more contracts: Bayou Bienvenue 
to Bayou Dupre levee closures; Chalmette area, 
second enlargement; Inner Harbor Canal, east and 
west levee and Citrus Back levee to Paris road, capping 
floodwall; Chalmette extension, first enlargement. 
22. LAROSE TO GOLDEN MEADOW, 
LA (HURRICANE PROTECTION) 
Location. In coastal section of Louisiana, along Bayou 
Lafourche, and includes lands on both banks of the 
bayou from Larose to 2 miles south of Golden Meadow. 
(Refer to Geological survey quadrangles Cut-off, Lke 
Felicity, Bay Dosgris, Golden Meadow Farms, Bay 
Tambour, Mink Bayou, Caminada Pass, Leeville, Belle 
Pass, Pelican Pass, and Calumet Island; Engineer 
quadrangles New Orleans, Hahnville, Point-a-la-Hache, 
Barataria, and Fort Livingston; and Coast and Geodetic 
Survey Charts Nos. 1115 and 1116 
Existing project. Provides a loop levee about 40 miles 
long along both banks of Bayou Lafourche from Larose 
to South Golden Meadow; enlargement of 3 miles of 
existing levee at Golden Meadow; floodgates for navigation 
and hurricane protection in Bayou Lafourche at 
upper and lower bayou crossings; about 8 miles of low 
interior levees to regulate intercepted drainage and 
seven multibarreled culverts controlled by flapgates. 
Estimated cost for new work (October 1983) is $61,300,000 
Federal and $26,300,000 non-Federal. 
Local cooperation. Provide without cost to the 
United States all lands, easements, and rights-of-way, 
including borrow areas and spoil disposal areas, and 
accomplish alterations to roads, pipelines, cables, 
wharves, oil wells, and any other facilities necessary 
for the construction of the project; all at an estimated 
cost of $10,430,000; bear 30 percent of the total project 
cost, a sum presently estimated at $26,300,000 consisting 
of the items listed above, and a cash contribution 
presently estimated at $15,870,000 or equivalent work 
specifically undertaken as an integral part of the 
project after authorization and in accordance with 
construction schedules as required by the Chief of 
Engineers; hold and save the United States free from 
damages due to the construction works; maintain and 
operate all the works after completion in accordance 
with regulations prescribed by the Secretary of the 
Army; and prevent any encroachment on ponding 
areas unless substitute storage capacity or equivalent 
pumping capacity is provided promptly without cost to 
the United States; comply with the provisions of the 
Uniform Relocations Assistance and Real Property 
Acquisition Policies Act of 1970 (Public Law 91-646) 
and with the provisions of Section 221 of the Flood 
Control Act of 1970 (Public Law 91-611) in acquiring 
real property. 
The Board of Commissioners of the South Louisiana 
Tidal Water Control Levee District executed the 
required Agreement of Local Cooperation on Nov. 13, 
1972, which was executed by the United States on Jul. 
10, 1973 and approved on behalf of the Secretary of the 
Army on Aug. 29, 1973. Section 38, Paragraph 1051 et 
seq., Louisiana Revised Statutes created the South 
Lafourche Levee District. The South Lafourche Levee 
District assumed the rights and obligations of the 
South Louisiana Tidal Water Control Levee District 
with respect to this project. 
Operations and results during fiscal year. One 
design memorandum was submitted to LMVD for 
review during the year. One contract for Larose Floodgate 
was awarded Jun. 30, 1983. 
Condition as of Sep. 30. Construction commenced in 
February 1975 and is 38 percent complete. 
23. MCKINNEY BAYOU, AR 
AND TX 
Location. The McKinney Bayou watershed covers 
approximately 360 square miles and is located in 
southwestern Arkansas and northeastern Texas in the 
vicinity of the city of Texarkana, AR and TX, within 
the flood plain of the Red River. 
Existing project. Provides improvements for three 
major elements; improvement of the McKinney Bayou 
channel, construction of a diversion channel into Red 
River and control structure at Buzzard Bluff, and 
construction of a diversion channel into Red River and 
control structure about one-half mile west of the 
Arkansas-Texas state line. Mitigation of project-induced 
11-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
wildlife losses are included in the project. Estimated 
cost of new work (October 1983) is $6,570,000 Federal 
and $4,520,000 non-Federal, including cash contribution 
of $728,000. 
Local cooperation. For details see pages 11-29 and 
30, Annual Report for FY 1980. 
Operations and results during fiscal year. A draft 
General Reevaluation Report and Environmental Impact 
Statement was distributed for review by Federal 
and State agencies and others on Jul. 28, 1983. The 
reevaluation disclosed changed conditions and attitudes 
to modify the authorized plan. The portion of the 
project located west of the Arkansas-Texas state line 
was deleted because of lack of support by local interests. 
This portion of the project was reclassified to inactive 
in November 1982. The Buzzard Bluff portion was 
deleted for economic reasons. All alternative investigations 
of the Buzzard Bluff portion of the project had 
benefit-cost ratios less than unity. The tentatively 
selected plan now consists of channel improvements of 
McKinney Bayou to the same dimension as authorized 
and a reduced mitigation plan of 2,550 acres of greentree 
reservoir along the periphery of the Bois d'Arc 
Wildlife Management Area near Fulton, Arkansas. 
Condition as of Sep. 30. The draft General Reevaluation 
was under review by local interest who requested 
an extension of the review period to Oct. 30, 1983. 
24. MORGAN CITY AND 
VICINITY, LA 
(HURRICANE PROTECTION) 
Location. In south-central Louisiana, Morgan City 
proper, and the adjacent areas. It includes the land 
south of Grand Lake, Six Mile Lake, and Lake Palourde 
extending from Morgan City westward to Charenton 
drainage and navigation canal. Lower Atchafalaya 
River and Wax Lake Outlet, the principal outlets for 
Atchafalaya Basin Floodway, traverse the area. Gulf 
Intracoastal Waterway crosses the area in an east-west 
direction. Numerous bayous and artificial canals excavated 
for drainage purposes or for access to oil developments 
exist throughout the area. (See Engineer 
quadrangles Bayou Sale, Jeanerette, Foster, Belle Isle, 
Point Au Fer, Morgan City, and Lake Decade; and 
Coast and Geodetic Survey Chart 1116.) 
Existing project. Morgan City: Construction of 
about 5.6 miles of new levees along shore of Lake 
Palourde and west bank of Bayou Ramos and about 0.5 
mile of new levee from Southern Pacific railroad 
embankment near Wyandotte to tie in with Bayou 
Boeuf lock levee, and construction of three gravity 
drainage structures. 
Franklin and vicinity: Enlargement of about 21.6 
miles of back levee and construction of about 3.5 miles 
of new levees to effect a complete closure of area to be 
protected, construction of one floodgate and eight 
gravity drainage structures, and alteration of existing 
drainage facilities where necessary. Normal range of 
tide is 1.6 feet. Storm and hurricane tide have produced 
elevations up to 10 feet while northerly storms 
during winter depress the gulf level as much as 3 feet 
below mean sea level. During low water periods on 
Atchafalaya River, generally September through 
November, the effect of tide extends about 35 miles 
above Morgan City. Estimated cost for total project 
(October 1983) is $25,800,000 Federal and $13,930,000 
non-Federal. 
Local cooperation. Local interest must furnish 
lands, easements, and rights-of-way for construction 
and future maintenance, provide relocations and alterations 
required for project; provide all interior drainage 
and pumping plants required for reclamation and 
development of protected areas; maintain and operate 
all project works after completion, provide assurances 
that encroachment on existing ponding areas will be 
prevented unless substitute storage capacity or equivalent 
pumping capacity is provided promptly, without 
cost to the United States; contribute in cash or equivalent 
work not less than 30 percent of project cost, the 
final determination to be made after construction is 
complete; and hold and save the United States free 
from damages due to construction works. 
Assuring Agency: The act of assurance and supporting 
resolution from the St. Mary Parish Police 
Jury were accepted for and on behalf of the United 
States on Jul. 18, 1968. Supplemental assurances were 
furnished by the St. Mary Parish Police Jury for the 
Morgan City Area separable feature of the project. 
These supplemental assurances include the additional 
items of local cooperation required by PL 91-611 and 
PL 91-646 and were accepted on behalf of the United 
States on Jul. 23, 1980. The Franklin Area feature was 
specifically excluded in the supplemental assurances. 
Operations and results during period. General 
engineering only was accomplished by hired labor 
forces during the fiscal year. The GDM for the Morgan 
City area progressed approximately 30 percent in FY 
1983. The remainder of work on the GDM will be 
accomplished in FY 1985. 
Condition as of Sep. 30. Construction has not 
commenced. 
25. NEW ORLEANS TO VENICE, LA, 
HURRICANE PROTECTION 
Location. Includes land subject to inundation by 
hurricane tides extending along both banks of the 
Mississippi River below New Orleans from vicinity of 
Phoenix to Venice, LA. 
Existing project. Provides for improvements along 
Mississippi River below New Orleans, LA, for prevention 
of hurricane tidal flood damages by increasing 
heights of existing back levees and modifying existing 
drainage facilities where necessary in three separate 
reaches: Reach A, on the west bank from City Price to 
Empire, 15 miles, 4;340 acres protected; Reach B, on 
the west bank from Empire to Venice, 21 miles, 4,900 
acres protected; and Reach C, on the east bank from 
Phoenix to Bohemia (construction recently completed 
11-18

NEW ORLEANS, LA, DISTRICT 
by local agency with credit given as equivalent work), 
16 miles, 5,470 acres protected, and construction of a 
barrier levee on the east bank of the Mississippi River 
from Bohemia to mile 10 AHP with enlargement of the 
west bank Mississippi River levee from Fort Jackson to 
Venice, generally called the East Bank Barrier Levee 
plan. Reach B was later divided into two units, Reach 
B-1 from Empire to Fort Jackson and Reach B-2 from 
Fort Jackson to Venice, LA, as a result of a request 
made by the local agency. 
Estimated cost of new work (October 1983) is 
$132,300,000 Federal and $56,700,000 non-Federal, 
including $45,481,000 cash contributions or equivalent 
work. 
Local cooperation. Provide all lands, easements and 
rights-of-way including borrow areas and spoil disposal 
areas necessary for the construction of the project, at 
costs presently estimated at $4,427,000; accomplish all 
necessary alterations and relocations to roads, pipelines, 
cables, wharves and other facilities required by the 
construction of the project at costs presently estimated 
at $6,792,000; bear 30 percent of the first cost, a sum 
presently estimated at $56,700,000, and cash contribution 
presently estimated at $45,481,000 to be paid 
either in a lump sum prior to initiation of construction 
or in installments prior to start of pertinent work 
items, in accordance with construction schedules as 
required by the Chief of Engineers, or as a substitute 
for any part of the cash contribution, accomplish in 
accordance with approved construction schedules items 
of work of equivalent value as determined by the Chief 
of Engineers, the final apportionment of costs to be 
made after actual costs and values have been determined; 
hold and save the United States free from 
damages due to the construction works; maintain and 
operate all works after completion in accordance with 
regulations prescribed by the Secretary of the Army; 
prevent any encroachment on ponding areas unless 
substitute storage capacity or equivalent pumping is 
provided promptly; and at least annually, notify those 
affected that the project will not provide complete 
protection from tidal flooding and that further local 
actions must be taken during hurricane emergencies. 
Local interests are also required to comply with the 
provisions of the Uniform Relocation Assistance and 
Real Property Acquisition Policies Act of 1970 (PL 
91-646), in acquiring real property. 
PL 91-611. Not applicable. Construction started prior 
to Jan. 1, 1972. 
PL 91-646. A constitutional amendment was provided 
by the Louisiana legislature on Feb. 1, 1972 allowing 
local interests to comply. The estimated cost to local 
interests is $48,000. 
Assurances of local cooperation for Reaches A, B-i, 
B-2 and C, requested on Jan. 7, 1963, were furnished by 
the Plaquemines Parish Commission Council on Mar. 
6, 1964. Required supporting papers were furnished on 
Mar. 16, 1965 and accepted. Supplemental assurances 
covering the requirements of PL 91-646 were received 
from Plaquemines Parish Commission Council on May 
23, 1973 and accepted on Jun. 20, 1973. 
Assurances for the entire project have been furnished 
and accepted, although they do not specifically mention 
the East Bank Barrier Levee Plan. The scope of the 
project has not changed; however, local interests were 
requested to furnish separate assurances for the East 
Bank Barrier Levee. These assurances have not yet 
been received. 
There was a delay of approximately 26 months in the 
furnishing of assurances by local interests primarily 
because they desired that agreement on levee alinement 
be consummated as fully as possible before giving their 
assurance. Problems of assurance of local cooperation 
have been resolved and rights-of-way were furnished 
for the first two Reach B-1 items of work on Aug. 23, 
1968 and May 20, 1970, respectively. 
All negotiations for relocations are the responsibility 
of local interests. These mainly consist of raising several 
petroleum and natural gas pipelines to the levee configuration 
and relocation of privately owned frame 
structures used as fishing and boating camps. To 
assure that there will be no delay in construction of 
levees, local interests are notified well in advance so 
that the owners of the pipelines can be advised. 
Assuring Agency: Plaquemines Parish Commission 
Council. Assurances for all reaches of the project, except 
the East Bank Barrier levee, have been furnished. 
Operations and results during fiscal year. New 
work by hired labor: Planning for this project and 
engineering studies continued. 
Reach B-2, second enlargement, was awarded Jul. 
29,1982, and completed May 4, 1983. A second contract 
for Reach B-2, Sta. 244+000 to Sta. 473+58, second 
enlargement, was initiated May 11, 1983. Grand Liard 
floodwall Reach B-1, was awarded Jul. 18, 1983. 
Condition as of Sep. 30. Construction began on the 
project in September 1968 and the total project is 
approximately 40 percent complete. First lift construction 
is complete on Reaches B-1 and B-2 and the first 
enlargement is completed for a portion of Reach B-1. 
Second lift construction is complete on Reach C. Initial 
construction on Reach A is scheduled to begin in FY 
1985. Initial construction on the East Bank Barrier is 
not scheduled, pending the furnishing of assurances by 
local interest. 
26. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Various hurricane protection projects, as well as 
small flood control projects, were inspected during FY 
1983. Also, periodic inspection and continuing evaluation 
of completed civil works structures was conducted 
in accordance with ER 1110-2-100, at various times 
during the year on an as-needed basis. 
Fiscal year costs for the period were $221,916. Total 
costs to Sep. 30, 1983, were $1,260,978. 
11-19

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
27. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Disaster preparedness, FY costs for the period were 
$126,899. Emergency Operations: Total costs to Sep. 
30, 1983, were 126,899. 
General Investigations 
28. ACTIVE INVESTIGATIONS 
See Table 11-J which covers: Surveys, Collections 
and study of basic data, and Research and Development 
activities. 
11-20

NEW ORLEANS, LA, DISTRICT 
TABLE 11-A COST AND FINANCIAL STATEMENT 
See 
Section Total Funds to 
in Text Project Funding FY 80 FY 81 FY 82 FY 83 Sep. 30, 1983 
1. Aquatic Plant 
Control Program, 
LA 
2. Atchafalaya 
River Bayous 
Chene, Boeuf, 
and Black, LA 
(Contrib. Funds) 
3. Barataria Bay 
4. Bayou Lafourche 
and Lafourche- 
Jump Waterway, 
LA 
5. Bayou Teche & 
Vermilion 
River, LA 
6. Bayou Teche, 
LA 
7. Calcasieu River 
and Pass, LA 
(Contrib. Funds) 
8. Freshwater 
Bayou, LA 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
$ 445,000 
549,853 
$ 450,000 
424,684 
$ 300,000 
312,947 
550,000 15,500,000 1,150,000 
351,901 15,644,334 704,955 
1,202,100 3,565,000 
2,299,847 3,576,990 
- 628,000 
138,866 630,835 
2,053,000 
1,994,623 
148,750 
150,540 
$ 487,000 
499,145 
43,957 
4,592,000 
4,633,396 
$ 9,369,460 
9,366,872 
30,850,000 
30,322,4411 
28,866,9812 
28,842,8392 
1,483,8125 
1,483,8124 
1,572,6855 
1,572,6855 
184,220 
182,149 
-30,600 
199 
125,970 
131,865 
116,910 
123,167 
10,552,980 
8,699,203 
282,774 
2,665,265 
1,825,010 
305,000 2,320,000 
307,580 224,389 
490,000 
2,598,462 
2,817 
40,000 
55,498 
137,000 
128,135 
8,285,000 
11,262,008 
155,000 
437,774 
39,000 
39,291 
202,000 
110,272 
152,130 
240,600 
1,885,000 9,125,130 
914,539 10,066,491 
814,000 1,670,000 
1,392,685 1,693,519 
320,000 
598,300 
13,836,8566 
13,802,4666 
1,624,424? 
1,624,424? 
829,7568 
829,7568 
2,891,822 
2,891,822 
1,627,724 
1,627,725 
754,3309 
754,33010 
3,751,715 
3,733,569 
27,807,31011 
27,807,310" 
74,571,87912 
74,472,13712 
437,774 
437,774 
7,116,22418 
7,116,2241" 
12,513,765 
12,513,706 
11-21

TABLE 11-A 
(Continued) 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1988 
COST AND FINANCIAL STATEMENT 
in 
Total Funds to 
FY 80 FY 81 FY 82 FY 83 Sep. 30, 1983 
63,654,535a11.16 
63,284,47014,1.16 
Text Project 
9. Gulf Intracoastal 
Waterway 
between 
Apalachee Bay, 
FL & Mexican 
Border (New 
Orleans Dist.) 
10. Houma Navigation 
Canal, LA 
11. Leland Bowman 
Lock, LA 
(Replacement 
of lock) 
12. Mermentau River, 
LA 
13. Mississippi 
River, Baton 
Rouge to the 
Gulf of 
Mexico, LA 
14. Mississippi 
River-Gulf 
Outlet, LA 
(Regular Funds) 
(Contrib. Funds) 
15. Mississippi 
River Outlets, 
Venice, LA 
Overton-Red River 
Waterway, LA 
Red River 
Emergency Bank 
Protection 
(Contrib. Funds) 
Funding 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
7,660,000 
7,122,203 
1,350,000 
1,344,029 
50,000 
389,709 
29,204 
501,250 
623,433 
910,000 
658,241 
27,363,000 
27,449,447 
1,300,000 
901,609 
1,572,500 
1,522,856 
- 
-4,000 
36,320 
892,800 
1,004,548 
5,600,000 
5,763,945 
5,000,000 
5,037,194 
- 
4,875,000 
6,837,829 
2,540,000 
2,505,334 
495,200 
544,814 
3,766 
700,000 
743,669 
884,800 
977,150 
24,122,100 
24,581,150 
1,780,000 
1,758,067 
7,109,200 
7,134,791 
- 
11-22 
See 
Section 
16,900 -578 340 
196,000 926,000 2,196,000 
190,910 863,216 2,227,642 
3,419,000 4,974,500 - 
3,283,472 5,129,335 9,299 
5,890,000 6,000,000 -164,000 
5,917,017 4,101,980 1,669,746 
. - , 
-. -, - 
15,876,100 
13,242,263 
2,888,000 
284,901 
6,029,800 
6,058,840 
1,050,900 
1,013,415 
30,268,000 
29,826,943 
1,235,200 
1,472,670 
8,754,000 
4,349,480 
-
- 
10,524,486 
12,391,442 
1,744,900 
4,181,328 
14,000,000 
12,697,628 
555,000 
562,024 
900,000 
1,545,117 
45,611,260 
43,786,783 
2,005,000 
1,027,035 
11,048,000 
14,717,186 
) --] f Mla 
148,062,73217 19 
147,205,557 1819 
15,466,634 
15,263,526 
21,875,0100 
20,529,6440 
4,561,91021 
4,672,57921 
12,334,312w 
12,293,00322 
40,111,79726 
40,531,4066 
355,496,32424.6 
353,059,466626 
78,640,200 
77,431,167 
81,516,580 
80,745,812 
1,118,9772 
1,118,977V 
10,008,093 
10,008,100 
4,395,800 
4,356,130 
27,427,022u 
27,427,022w 
46,784,000$ 
46,561,9508 
6,825 
6,825

NEW ORLEANS, LA, DISTRICT 
TABLE 11-A 
(Continued) 
COST AND FINANCIAL STATEMENT 
See 
Section Total Funds to 
in Text Project Funding FY 80 FY 81 FY 82 FY 83 Sep. 30, 1983 
Red River 
Waterway- 
Mississippi 
River to Shreveport, 
LA 
(Contrib. Funds) 
16. Removal of Aquatic 
Growth, LA 
17. Tangipahoa 
River, LA 
18. Waterway from 
Intracoastal 
Waterways to 
Bayou Dulac, 
LA (Bayou 
Grand Caillou & 
LeCarpe, LA) 
Bayou Bodcau 
and tributaries, 
AR & LA 
Bayou Bodcau 
Reservoir, LA 
Bayou Pierre, LA 
Brush Bayou, LA 
(Contrib. Funds) 
Caddo Lake, 
LA 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
66,700,000 88,500,000 36,500,000 
66,088,853 74,633,085 50,445,943 
36,497 
210,986 
216,720 
217,943 
144,000 
2,181,516 
1,015,000 1,327,800 
1,382,191 1,355,419 
1,163,000 976,000 1,158,000 1,387,200 
984,300 1,177,002 1,084,984 1,440,032 
20,840 
20,833 
190,000 
39,613 
300,000 
129,196 
275,050 
265,025 
9,370 
14,142 
-120,000 
35,853 
49,424 
91,860 
115,636 
159,000 
158,404 
35,000 
37,242 
135,000 
295,526 
120,000 
274,326 
370,000 
365,191 
21,000 
20,768 
182,000 
194,071 
460,000 
496,062 
127,000 
119,642 
130,000 
86,341 
200,000 
201,472 
500,000 
459,713 
184,000 
211,580 
12,600 
12,832 
34,315 
304,000 
306,913 
104,200 
114,316 
75,000 
111,102 
11,000 
152,937 
2,100 
22,316 
3,816 
332,332,00032 
332,332,00232 
4,700,947 
4,700,866 
483,461 
483,461 
19,122,808 
19,101,114 
568,154 
567,551 
369,622 
364,307 
888,762 
888,762 
4,418,000 
4,418,000 
4,208,41732 
4,208,41732 
2,841,807 
2,841,807 
299,529 
,' 32 
299,529' 32 
552,680 
552,680 
966,660s 
996,59929 
1,134,200* 
1,134,199 
3,587,14332 
3,587,14332 
520,060 
520,059 
11-23

TABLE 11-A 
(Continued) 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
COST AND FINANCIAL STATEMENT 
See 
Section Total Funds to 
in Text Project Funding FY 80 FY 81 FY 82 FY 83 Sep.30, 1983 
20. Grand Isle 
and Vicinity, 
LA 
21. Lake Pontchartrain 
and vicinity, 
LA (Hurricane 
Protection) (Regular 
Funds) 
(Contrib. Funds) 
22. Larose to Golden 
Meadow, LA 
Hurricane 
Protection) 
(Contrib. Funds) 
23. McKinney Bayou, 
AR, and TX 
24. Morgan City and 
vicimnity, LA 
(Hurricane 
Protection) 
25. Mississippi 
River Delta at 
and below New 
Orleans, LA (New 
Orleans to Venice, 
LA, Hurricane 
Protection) (Regular 
Funds) 
(Contrib. Funds) 
Red River below 
Denison Dam, 
Levees and Bank 
Stabilization (New 
Orleans Dist.) 
Red River Waterway, 
Shreveport, 
LA, to Index, AR 
Wallace Lake, LA 
New Work 
Approp. Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
182,000 
174,535 
13,320,000 
12,672,174 
209,400 
122,400 
100,000 
111,558 
105,000 3,000,000 
41,937 226,231 
8,800,000 13,000,000 13,716,000 
8,811,248 13,720,371 13,510,392 
140,950 
205,564 
166,000 
186,400 
313,124 
356,602 
2,885,000 815,000 2,100,000 9,870,000 
2,931,867 1,075,688 1,407,390 7,734,710 
298,721 1,101,000 
218,191 1,146,938 
155,000 
118,085 
255.000 
284,162 
200,000 
198,700 
6,139 
13,482 
250,000 
71,500 
384,000 
541,000 
638,000 1,830,000 1,535,000 3,450,000 
534,233 1,994,914 1,864,215 2,515,286 
86,569 
4,365,000 2,000,000 2,379,300 
5,568,162 1,067,597 2,576,517 
150,000 
112,393 
160,740 
162,454 
23,000 
94,340 
133,000 
132,832 
3,050,000 
2,600,000 
796,243 
5,057 
277,800 
285,901 3,962 
3,749,500 
902,090 
141,280,000 
140,580,443 
3,290,184 
3,331,676 
26,402,000 
23,536,95430 
2,089,721 
2,061,268 
1,622,263 
1,631,263 
1,365,000 
1,365,000 
48,639,000 
47,657,946 
3,416,430 
2,966,430 
50,389,3001 . 
3 50,389,30031.32 
688,00032 
688,9993 
1,219,37132 
1,219,3712 
1,717,240 
1,717,240 
11-24

NEW ORLEANS, LA, DISTRICT 
TABLE 11-A 
(Continued) 
COST AND FINANCIAL STATEMENT 
See 
Section Total Funds to 
in Text Project Funding FY 80 FY 81 FY 82 FY 83 Sep. 30, 1983 
West Agurs, LA New Work 
Approp. 50,000 137,000 - - 187,000* 
Cost 48,939 101,334 - - 150,27382 
1. Includes $37,348 for advance engineering and design. 
2. Includes any maintenance costs on Atchafalaya 
River, Morgan City to Gulf of Mexico, LA. 
3. Includes allotment of $340,000 for Code 300 
4. Includes expenditures of $335,375 for Code 300. 
5. Includes $73,037 for previous project. Excludes 
$2,000 contributed funds expended. 
6. Includes $47,551 for previous project. 
7. Includes $252,935 for previous projects; excludes 
$75,563 expended for rehabilitation (Code 820) in Fiscal Year 
1961. 
8. Includes $15,445 for previous projects. 
9. Includes $45,704 for previous projects. 
10. Includes $91,389 permanent indefinite appropriation. 
11. Includes $495,914 for previous project; excludes 
$107,837 expended for minor rehabilitation in Fiscal Year 
1963.
12. Includes $194,851 for previous project. 
13. Excludes $16,060 contributed funds. 
14. Includes $4,320,698 for new work onprevious project. 
Included in these totals are $353,541 N.I.R.A. funds (new 
work); and $1,070,433 permanent indefinite appropriation. 
Included is repayment of advance funds for construction of 
Franklin Canal in the amount of $35,103. In addition, 
$1,413,133 was expended for transfer to drainage district of 
ownership of Plaquemines Parish pumping station, and 
drainage canals and all drainage responsibility and obligations 
vested in the United States by Public Law 14, 79th 
Cong., 1st sess. 
15. Excludes contributed funds of $340,159. 
16. Inner Harbor Navigation Canal Lock was constructed 
at a cost of $8,648,492 (non-Federal). 
17. Does not include allotment of $60,000 (9613123). 
18. Does not include expenditures of $36,630 (9613123). 
19. Includes $454,259 for maintenance and $548,948 for 
operation and care for previous project, including $75,000 
from appropriation for maintenance and operation of dam 
and other improvements of navigable waters. Excludes $7,005 
contributed funds. 
20. Includes AE&D funds for replacement of Vermilion 
Lock.
21. Excludes $10,904 for new work on White Lake to 
Pecan Island section of existing project. 
22. Excludes $10,742 for maintenance on White Lake to 
Pecan Island section of existing project. Excludes $2,000 
contributed funds. Includes $13,163 of R&H funds and 
$109,714 accelerated Public Works Act funds. 
23. Includes $1,729,989 for previous project. 
24. Does not include allotment of $40,000 (9613123). 
25. Does not include expenditures of $63,370 (9613123). 
26. Includes $169,055 for previous projects and $3,379,676 
from permanent indefinite appropriation. 
27. Contributed by Board of Commissioners, Port of 
New Orleans, for providing fill for future industrial sites 
adjacent to turning basin and for dredging cable and pipeline 
crossings. 
28. Includes $38,529 from emergency relief funds. 
29. Includes $80,500 for preauthorized studies. 
30. Includes $67,823 for advance engineering and design. 
31. Includes $212,105 expended by Tulsa District for 
cost of Index, Ark., Tex. unit. Excludes $100,000 contributed 
funds expended. 
32. Projects transferred to Vicksburg District in FY 82. 
Costs reflect New Orleans portion only. Vicksburg District 
will furnish their costs for the remainder of FY 82 (See 
Chapter 12). 
11-25

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 11-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Jul. 3, 1958 
Oct. 23, 1962 
Oct. 27, 1965 
Aug. 13, 1968 
Water Resources 
Development 
Act, Mar. 7, 
1974 
Jul. 3, 1958 
Aug. 30, 1935 
Jul. 14, 1960 
Nov. 22, 1967 
Aug. 18, 1941 
Sep. 19, 1890 
Mar. 2, 1907 
Mar. 2, 1919 
AQUATIC PLANT CONTROL PROGRAM, LA (See Sec. 1 of 
Text) 
Control and progressive eradication of water-hyacinth alligator 
weed, and other obnoxious aquatic plant growth from navigable 
waters in tributary streams, connecting channels, and other 
allied waters in southeastern United States. 
Research and planning costs prior to construction to be borne 
fully by the United States and not included in costs shared by 
local interests. 
Provides for comprehensive program for control and progressive 
eradication of water-hyacinth, alligatorweed, Eurasian water 
milfoil, and other obnoxious plant growths from navigable 
waterways, tributary streams, connecting channels, and other 
allied waters of the United States. 
ATCHAFALAYA RIVER, BAYOUS CHENE, BOEUF, 
AND BLACK, LA (See Sec. 2 of Text) 
20- by 400-foot navigation channels connecting Gulf Intracoastal 
Waterway, Gulf of Mexico, and Bayous Chene, Boeuf, and Black. 
The non-Federal interests shall contribute 25 percentum of the 
costs of areas required for initial and subsequent disposal of 
spoil, and of necessary retaining dikes, bulkheads, and 
embankments therefor. This requirement shall be waived if 
applicable waste treatment facilities are constructed and water 
quality standards are not being violated. 
BARATARIA BAY WATERWAY, LA (See Sec. 3 of Text) 
A channel about 37 miles long with a 12-foot depth and 125-foot 
width from Gulf Intracoastal Waterway to Grand Isle, LA, to 
mile 15.5 in Bayou St. Denis; a channel along western shore of 
Barataria Bay and through Barataria Pass to 12-foot depth 
contour in the gulf, with an extension of project to include 
westerly 4.3 miles of Bayou Rigaud. 
BAYOU LAFOURCHE AND LAFOURCHE-JUMP 
WATERWAY, LA (See Sec. 4 of Text) 
Permanent closure of head of bayou, without a lock; a channel 6 
feet deep and 60 feet wide from Gulf Intracoastal Waterway at 
Larose to Gulf of Mexico by Belle Pass; closure of Pass 
Fourchon; and a jettied entrance at mouth of Bell Pass. 
Auxiliary channel 12 by 125 feet from Gulf Intracoastal 
Waterway (mile 37.2) to Bayou Lafourche vicinity Leeville 12-by 
125-foot channel improvement in Bayou Lafourche from 
Leeville to 12-foot contour in Gulf of Mexico; 9- by 100-foot 
channel improvement in Bayou Lafourche from Leeville to 
Golden Meadow; 12- by 125-foot channel from Leeville through 
Southwestern Louisiana Canal to and through Bayou Rigaud; 
and restore and extend jetties from 6- by 12-foot contour when 
justified to effect reduction in maintenance dredging. 
Bayou Lafourche, between Canal Boulevard in Thibodaux, 
Lafourche Parish, LA, and the head of the bayou at its junction 
with the Mississippi River levee and Donaldsonville, Ascension 
Parish, LA, is declared nonnavigable. 
BAYOU TECHE AND VERMILION RIVER, LA (See Sec. 5 
of Text) 
A navigable channel 51 miles long and 8 by 80 feet from 8-footdepth 
contour in Vermilion Bay to Gulf Intracoastal Waterway, 
thence 9 by 100 feet to head of navigation (mile 52) at Lafayette, 
LA, with additional enlargement below Abbeville necessary to 
provide adequate capacity for flood flows. 
BAYOU TECHE, LA (See Sec. 6 of Text) 
Improve stream from its mouth to St. Martinville by removing 
obstructions and dredging. 
Construct lock and dam and extend improvement to Arnaudville, 
LA. 
Increase channel dimensions from mouth to Keystone Lock. 
H. Doc. 37, 85th Cong., 1st 
sess. 
Public Law 874, 87th Cong., 
2d sess. 
Public Law 298, 89th Cong., 
2d sess. 
H. Doc. 155, 90th Cong., 1st 
sess. 
Public Law 93-251. Sec. 58, 
93rd Cong., 2d sess. 
H. Doc. 82, 85th Cong., 1st 
sess. 
H. Doc. 45, 73d Cong., 1st 
sess. 
H. Doc. 112, 8th Cong. 1st 
sess.' 
Public Law 90-149. 
S. Doc 93, 77th Cong., 1st 
sess. 1 
Annual Report, 1889, p. 
1532. 
H. Doc. 527, 59th Cong., 1st 
sess. 
H. Doc. 1329, 62d Cong., 3d 
sess. 2 
11-26

NEW ORLEANS, LA, DISTRICT 
TABLE 11-B 
(Continued) 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
June. 26, 19343 
Aug. 26, 1937 
Mar. 2, 1945 
Jul. 24, 1946 
Jul. 14, 1960 
Jul. 14, 1960 
Mar. 3, 1925 
Jan. 21, 1927 
Jul. 3, 1930 
Jun. 26, 1934 s 
Jul. 23, 1942 
Mar. 2, 1945 
Jul. 24, 1946 
Operation and care of lock and dam provided for with funds from 
War Department appropriations for rivers and harbors. 
CALCASIEU RIVER AND PASS, LA (See Sec. 7 of Text) 
Channel 30 by 250 feet from Lake Charles docks to gulf, repair 
and extend existing jetties to about 10-foot-depth contour, with a 
channel 30 by 250 feet between jetties; dredging approach 
channel 32 by 400 feet in gulf from sea ends of jetties to 32-footdepth 
contour; and provision for extension of jetties to 15-footdepth 
contour, if such action would be more economical than 
maintenance of approach channel by dredging. 
Channel 30 by 250 feet around Clooney Island. 
Channel depth of 35 feet from wharves of Lake Charles Harbor 
and terminal district, including Clooney Island Loop, to jetty 
channel, a uniformly increasing depth of 35 to 37 feet in jetty 
channel, and a depth of 37 feet in approach channel in Gulf of 
Mexico. 
An approach channel 42 by 800 feet from end of jetty to 42-foot 
contour in gulf; a jetty channel 400 feet wide, varying from 40 
feet deep at shoreline to 42 feet deep at seaward end of jetty; a 
channel 40 by 400 feet from shoreline (mile 0) to Port of Lake 
Charles (mile 34.4); enlarge existing turning basin at mile 29.6 
to 40 feet deep; a mooring basin (mile 3) 350 by 2,000 by 40 feet; a 
35- by 250-foot extension of existing ship channel from Port of 
Lake Charles (mile 34.4) to vicinity of U.S. Highway 90 Bridge; 
a turning basin at upper terminus, 750 by 1,000 by 35 feet; and 
maintenance of 12- by 200-foot channel from ship channel to 
Cameron, LA. 
FRESHWATER BAYOU, LA (See Sec. 8 of Text) 
A new 12- by 125-foot channel from Gulf Intracoastal Waterway, 
mile 161.2 west of Harvey Lock to 12-foot contour in Gulf of 
Mexico near Freshwater Bayou; construction of an 84- by 600- 
foot lock with a depth of 16 feet over sill near Gulf of Mexico; and 
construction of jetties from shoreline to 6-foot-depth contour in 
Gulf of Mexico, if maintenance dredging of channel without 
jetties proves to be more expensive than construction and 
maintenance of jetties. Until such determination has been made, 
offshore channel should be dredged and maintained toprovide a 
12- by 250-foot channel. In event jetties are provided, offshore 
section should then be maintained to 12- by 125-foot project in 
jettied reach, and 250 feet beyond. 
GULF INTRACOASTAL WATERWAY BETWEEN 
APALACHEE BAY, FL, AND MEXICAN BORDER 
(NEW ORLEANS DISTRICT) (See Sec. 9 of Text) 
Construct waterway from New Orleans, LA, to Galveston Bay, 
TX 
Extension of waterway to Corpus Christi, TX 
A channel 9 by 100 feet from Lake Pontchartrain to Mississippi 
Sound. 
Operation and care of locks and dams provided for with funds 
from War Department appropriations for rivers and harbors. 
Enlarge waterway from 9 by 100 feet to 12 by 125 feet from 
Apalachee Bay, FL, to Corpus Christi, TX, and its extension to 
vicinity of Mexican border, except between Mobile Bay, AL, and 
New Orleans, LA, where width shall be 150 feet; and rental of 
Inner Harbor Navigation Canal facilities. 
Alternative connection with Mississippi River in vicinity of 
Algiers at New Orleans. 
Enlarge and extend Plaquemine-Morgan City route from 
Mississippi-Atchafalaya section of waterway, in vicinity of 
Morgan City, to and through a new terminallock and entrance 
channel to Mississippi River in vicinity of Port Allen, opposite 
lower limit of Port of Baton Rouge. 
H. Doc. 299, 75th Cong., 1st 
sess. 
H. Doc. 465, 77th Cong., 1st 
sess. 
S. Doc. 190, 79th Cong., 2d 
sess. 
H. Doc. 436, 86th Cong., 2d 
sess. 
H. Doc. 435, 86th Cong., 2d 
sess. 1 
H. Doc. 238, 68th Cong., 1st 
sess. 
H. Doc. 238, 68th Cong., 1st 
sess. 
H. Doc. 341, 71st Cong., 2d 
sess. 
H. Doc. 96, 79th Cong., 1st 
sess.; H. Doc 230, 76th 
Cong., 1st sess.5 
S. Doc. 188, 78th Cong., 2d 
sess. 
S. Doc. 242, 79th Cong., 2d 
sess. 
11-27

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 11-B 
(Continued) 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Jul. 24, 1946 
Jul. 24, 1946 
Oct. 23, 1962 
Oct. 22, 1976 
Oct. 23, 1962 
WRD Act of 
1976, dated 
Oct. 22, 1976 
(PL 94-587) 
Aug. 18, 1941 
Jul. 24, 1946 
Mar. 2, 1945 
Oct. 23, 1962 
Restore, improve, and maintain Franklin Canal as a terminal 
branch channel, 8 by 60 feet, from its confluence with Gulf 
Intracoastal Waterway to Franklin, LA. 
A salt-water guard lock in waterway at mile 238 west of Harvey 
Lock. 
Enlarge waterway to 16 by 150 feet from Mississippi River to 
Atchafalaya River, except in vicinity of Houma (mile 50.5 to 
63.5); of Houma bypass (mile 50.5 to 63.5) and of Algiers 
alternative canal; and enlarge waterway from Atchafalaya 
River to Sabine River to 16 by 200 feet. 
Replacement of Vermilion Lock, in accordance with the 
recommendations of the Chief of Engineers in the report dated 
Aug. 3, 1976, recommending a lock size of 110 feet wide by 1,200 
feet long by 15 feet deep. 
HOUMA NAVIGATION CANAL, LA (See Sec. 10 of Text) 
Assumption of maintenance and operation of Houma Navigation 
Canal, constructed by Terrebonne Parish, to dimensions of 15 by 
150 feet. 
LELAND BOWMAN LOCK, LA (REPLACEMENT OF 
LOCK) (FORMERLY VERMILION LOCK) (See Sec. 11 of 
Text) 
A replacement lock, 110 feet wide and 1,200 feet long, to 
accommodate present and projected marine traffic. 
MERMENTAU RIVER, LA (See Sec. 12 of Text) 
Channel enlargement, lower Mermentau River, from mile 15 to 
Gulf of Mexico, and construction of a lock and control spillway at 
Catfish Point, mile 24. 
Channel enlargement; lower Mermentau River below Grand 
Lake, mile 25; construct a gated-control structure at or near 
Grand Cheniere, mile 7; enlarge and realine Inland Waterway 
from Franklin, LA, to Mermentau River, LA, from Vermilion 
Bay to White Lake, via new channel, and from White Lake to 
Grand Lake; enlarge channel of North Prong of Schooner 
Bayou; construct a gated-control structure in new channel near 
Schooner Bayou lock; and include project "Waterway from 
White Lake to Pecan Island, LA," and portion of project "Inland 
Waterway from Franklin, LA, to Mermentau River," west of 
Vermilion Bay in modified project "Mermentau River, LA." 
MISSISSIPPI RIVER, BATON ROUGE TO GULF OF 
MEXICO, LA (See Sec. 13 of Text) 
Combines projects of Mississippi River, Baton Rouge to New 
Orleans, Mississippi River, South Pass, and Southwest Pass, 
adding thereto project for Mississippi River from New Orleans 
to Head of Passes, to provide a single project, "Mississippi River, 
Baton Rouge to the Gulf of Mexico," with channel dimensions as 
follows: Baton Rouge to New Orleans, 35 by 500 feet; port limits 
of New Orleans, 35 by 1,500 feet; New Orleans to Head of Passes, 
40 by 1,000 feet, Southwest Pass, 40 by 800 feet; Southwest Pass 
Bar Channel, 40 by 600 feet; South Pass, 30 by 450 feet; South 
Pass Bar Channel 30 by 600 feet. 
Deepen existing channel from 35 to 40 feet by 500 feet wide from 
one-tenth mile below Louisiana Highway Commission bridge at 
Baton Rouge to upper limits of Port of New Orleans, and also 40 
by 500 feet within presently authorized 35- by 1,500-foot channel 
in port limits of New Orleans. 
S. Doc. 189, 79th Cong., 2d 
sess. 
S. Doc. 231, 79th Cong., 2d 
sess. 
H. Doc. 556, 87th Cong., 2d 
sess. 
Sec. 114 Water Resources 
Development Act of 1976 
(PL 94-587) 2d sess. 
H. Doc. 583, 87th Cong., 2d 
sess.' 
Approved by Secretary of 
the Army, May 1967, 
under authority of the 
R&H Act of 1909. 
S. Doc. 94, 77th Cong., 1st 
sess. 
S. Doc. 231, 79th Cong., 2d 
sess. 
H. Doc. 215, 76th Cong., 1st 
sess.' 
S. Doc. 36, 87th Cong., 1st 
sess. 
11-28

NEW ORLEANS, LA, DISTRICT 
TABLE 11-B 
(Continued) 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Mar. 29, 1956 
Oct. 22, 1976 
Aug. 13, 1968 
Mar. 3, 1899 
Jun. 13, 1902 
Jul. 25, 1912 
Jun. 10, 1872 
Jun. 14, 1880 
Jun. 14, 1960 
Aug. 30, 1935 
Oct. 23, 1962 
Adopted by 
Committee 
Resolutions 
Sep. 23, 1976, 
and Oct. 1, 
1976 
Oct. 27, 1965 
MISSISSIPPI RIVER-GULF OUTLET, LA (See Sec. 14 of 
Text) 
Construct a seaway canal 36 feet deep and 500 feet wide from 
Michoud to 38-foot contour in gulf and an inner tidewater 
harbor consisting of a 1,000- by 2,000-foot turning basin 86 feet 
deep and a connecting channel 36 feet deep and 500 feet wide to 
Inner Harbor Navigation Canal and provides, when 
economically justified for construction of a lock to Mississippi 
River in the vicinity of Meraux, LA. 
Amends above Act making the construction of bridge relocations 
a Federal responsibility when required by the construction of 
the Mississippi River-Gulf Outlet channel. 
MISSISSIPPI RIVER OUTLETS, VENICE, LA (See Sec. 15 
of Text) 
Enlargement of existing channels of Baptiste Collette Bayou and 
Grand-Tiger Passes to 14 by 150 feet with 16 by 250-foot 
entrance channels in open water and jetties, if justified. 
REMOVAL OF AQUATIC GROWTH, LA (See Sec. 16 of 
Text) 
Appropriations for Florida and Louisiana for extermination or 
removal of plants, building of boats, and establishment of 
booms. 
Authorized use of mechanical, chemical, or other means 
whatsoever. 
Made appropriation available for State of Mississippi and also 
made available for use in that State operating plant pertaining 
to work in Louisiana. 
TANGIPAHOA RIVER, LA (See Sec. 17 of Text) 
Improvement, without dredging, by removing overhanging trees, 
snags, and obstructions to navigation from Wells to mouth. 
Present project above entrance channel. 
8- by 100-foot entrance channel from 8-foot depth contour in Lake 
Pontchartrain to 8-foot depth in River. 
WATERWAY FROM INTRACOASTAL WATERWAY TO 
BAYOU DULAC, LA (Bayous Grand Caillou and LeCarpe, 
LA) (See Sec. 18 of Text) 
Channel 5 by 40 feet from Intracoastal Waterway at Houma 
through Bayou LeCarpe, Bayou Pelton, and Bayou Grand 
Caillou to Bayou Dulac, about 16,3 miles. 
Channel 10 by 45 feet in Bayou LeCarpe from Gulf Intracoastal 
Waterway to Houma navigation canal. 
GRAND ISLE AND VICINITY, LA (See Sec. 20 of Text) 
To provide hurricane protection by placement of a berm and 
vegetated dune extending the length of Grand Isle's gulf shore 
and a jetty to stabilize the western end of the island at Caminada 
Pass. 
LAKE PONTCHARTRAIN AND VICINITY, LA 
(HURRICANE PROTECTION) (See. Sec. 21 of Text) 
Control of hurricane tides by construction of two independent 
units, the Lake Pontchartrain Barrier plan and the Chalmette 
Area plan. 
H. Doc. 245, 82d Cong., 1st 
sess. 
Sec. 186, Water Resources 
Development Act of 1976 
(PL 94-587) 2d ses. 
H. Doc. 804, 90th Cong., 2d 
seas. 
H. Doc. 91, 55th Cong., 3d 
sess. 
H. Ex. Doc. 54, 46th Cong., 
2d sess., and Annual 
Report, 1871, p. 558. 
Annual Report, 1879, p.946. 
Authorized by Chief of 
Engineers Jul. 28, 1967, 
under Sec. 107 of 1960 
River and Harbor Act, as 
amended. 
H. Doc. 206, 72d Cong., 1st 
seas. 
H. Doc. 639, 94th Cong., 2d 
seas. 
H. Doc. 231, 89th Cong., 1st 
sess. 
11-29

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 11-B 
(Continued) 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
LAROSE TO GOLDEN MEADOW, LA (HURRICANE 
PROTECTION) (See Sec. 22 of Text) 
Oct. 27, 1965 A loop levee about 36 miles long along both banks of Bayou H. Doc. 184, 89th Cong., 1st 
Lafourche from Golden Meadow to Larose; enlargement of 3 sess.' 
miles of existing levee at Golden Meadow; floodgates for 
navigation and hurricane protection in Bayou Lafourche at 
upper and lower bayou crossings; about 8 miles of low interior 
levees to regulate intercepted drainage; and seven 
multibarreled culverts controlled by flapgates. 
MCKINNEY BAYOU, AR AND TX (See Sec. 23 of Text) 
Oct. 22, 1976 Provides channel enlargement of McKinney Bayou; outlet H. Doc. 647, 94th Cong., 2d 
channels to Red River; interior drainage channels; and four sess. 
flood flow structures by USDA. 
MORGAN CITY AND VICINITY, LA, HURRICANE 
PROTECTION (See Sec. 24 of Text) 
Oct. 27, 1965 Construction of new levees along Lake Palourde and Bayou H. Doc. 167, 89th Cong., 1st 
Ramos, levee to tie-in with Bayou Boeuf lock levee and three sess. 
gravity drainage structures in Morgan City unit and 
enlargement of bank levee, construction of new levee, and 
construction of one floodgate and five gravity drainage 
structures in Franklin and vicinity unit. 
NEW ORLEANS TO VENICE, LA, HURRICANE 
PROTECTION (See Sec. 25 of Text) 
Oct. 23, 1962 Improvements along Mississippi River below New Orleans, LA, H. Doc. 550, 87th Cong., 2d 
for prevention of hurricane tidal flood damages by increasing sess. 
heights of existing back levees and modifying existing drainage 
facilities where necessary in five separate reaches. 
1. Contains latest published map. 
2. For latest published map, see H. Doc. 288, 66th Cong., 
1st sess. 
3. Permanent Appropriation Repeal Act. 
4. Authorized under provision of Sec. 201 of Flood 
Control Act of 1965. 
5. Not mentioned in authorizing act. 
11-30

TABLE 11-C 
NEW ORLEANS, LA, DISTRICT 
BAYOU TECHE, LA, LOCKS 
(See See. 6 of Text) 
Pertinent Data 
Miles from 
Miles from 
Width of chamber 
Length available for full width 
Lift 
Depth on miter sill at mean low gulf level 
Character of foundation 
Kind of dam 
Type of construction 
Completed 
Open to navigation 
Cost 
Keystone L ck 
18 (New Iberia) 
82.5 (Intracoastal Waterway) 
86 feet 
160 feet 
8 feet 
8 feet 
Timber piles 
Timber, rockfill 
Concrete 
1913 
$257,720 
Berwick Lock 
1.7 (Berwick, LA) 
9 (Below mouth of Bayou Teche) 
45 feet 
300 feet 
0-14.5 feet 
9
Timber piles 
- 
Reinforced concrete 
September 1951 
November 1950 
$2,100,000 
11-31

TABLE 11-D GULF INTRACOASTAL WATERWAY BETWEEN 
APALACHEE BAY, FL, AND MEXICAN 
BORDER (NEW ORLEANS DIST.)--LOCKS 
(See Sec.9of Text) 
Pertinent Data Pertinent Data 
Bayou Bayou Harbor Plaque- 
Algiers Boeuf Sorrel Calcasieu Harvey Navit mine Port Allen Vermiln 
lack Lack Lock Lock lack Cal ack Lock Lack lack 
Miles from 
New Orleans, 
LA (Canal St.) 
Miles below 
Lake Charles, 
LA 
Miles from 
Abbeville, LA 
Miles from 
Mississippi 
River 
Miles from 
Caleasieu River 
96.6 (via Har- 135 (via Harvey 
Leock) vey Lock) 
16.6 
0.38 56.7 (via 18 (via 
Plaquemine Plaquemine 
Lock) Lk)0.5 
" - 0.5 
Miles from 
Vermilion River 
Width of 
chamber 
Width between 
abutments 
lngth available 
for full width 
Lift 
75 feet 5- feet 
75 feet 
800 feet 
75 feet 
75 feet 
1,156 feet 797 feet 
0-18 feet 0-11.3 feet 0-21 feet 
Depth on sill at 13 feet 
mean low gulf 
level 
13 feet 14 feet 
1,206 feet 425 feet 
0-4 feet 
13 feet 
640 feet 
0-19.6 feet 0-17.4 feet 
12 feet 13.5 feet 
(miter sill) (miter sill) - 
75 feet - 84 feet 
56 feet 
- 1,202 feet 1,182 feet 
- X-45 feet 0-5 feet 
(either direction) 
- .75 feet 
,, miter sill) 
11.3 feet 
Concrete slab 
on medium of 
stiff clay 
Timber piles Concrete 
slab on preconstructed 
stiff clay 
Timber piles Timber piles Concrete slab 
on clay 
Timber piles 
3.3 2.9 132.5 
0.13 0.6 
26 
- 0.23 
LTJ 
y0 
sq 
'Ti 
y
4m8 A
q 
0
LxIj 
xLI 
LI 
a 
1.75 
Character of 
foundation 
Timber 
piles

Type of 
construction 
Kind of dam 
Reinforced Reinforced 
concrete concrete 
gate bays 
and earth 
chamber 
Opened to April 
navigation 1956 
Reinforced 
concrete 
gate bays 
and earth 
chamber 
19September June 
1954 1951 
Reinforced 
concrete 
gate bays 
and earth 
chamber 
December 
1950 
Reinforced Reinforced 
concrete concrete 
1934 February 
1923 
- Reinforced Reinforced 
- concrete concrete 
1909' July 
1961 
Reinforced 
concrete 
spillway dam, 
vertical cast 
steel gates, 
timber pile 
foundation 
1933 
$5,215,700 $2754,000 ,700,948 $2,133,527 
(Flood Control (Flood Control 
R&T Funds) R&T Funds) 
October 1952 
$1,775,132 $8,648,492 
(non- 
Federal) 
- 1935 
$1,302,006 $13,902,222 
1909 July 1961 
Cost 
Completed 
1. Closed permanently September 29,1961. 
2. Replacement of lock approved by the Secretary of Army, May 16, 1967; estimated Federal cost $25,900,000. 
3. Transferred to project status. Contruction of replacement lock, scheduled for January 1980. 
$330,7652 
1934$

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 11-E OTHER AUTHORIZED NAVIGATION PROJECTS 
Cost to Sep. 1983 
For Last Mo. and Yr. 
Full Report Operation Completed 
See Annual and Deauthorized 
Project Status Report For: Construction Maintenance or Reclassified 
Alteration of Berwick Bay Bridge' 
Amite River and Bayou Manchac, LA 
Atchafalaya River, Morgan City to Gulf 
of Mexico, LA 
Baton Rouge Harbor, 
Segment between Mi. 2.5 and 5.02 
Bayou Bonfouca, LA 
Bayou Dorcheat, Loggy Bayou and 
Lake Bisteneau, LA3' 4' 5' 6 
Bayou Dupre, LA7 
Bayou Grosse Tete, LA8 
Bayou Lacombe, LA 
Bayou La Lautre, St. Malo, and 
Yscolskey, LA 
Bayou Plaquemine Brule, LA 
Bayou Queue de Tortue, LA 
Bayou Segnette Waterway, LA 
Bayou Terrebonne, LA4' 9 
Bayou Vermilion, LA4 
Big Pigeon and Little Pigeon 
Bayous, LA3 
Calcasieu River at Coon Island, LA1� 
Calcasieu River at 
Devil's Elbow, LA 
Cascasieu River Salt Water 
Barrier, LA" 
Cane River, LA3' 6 
Chefuncte River and Bogue Falia, LA 
Cypress Bayou and Waterway between 
Jefferson, TX, and Shreveport, LA' 2 
Grand Bayou Pass, LA 
Inland Waterway from Franklin 
to Mermentau River, LA"' 13 
Intracoastal Waterway from the 
Mississippi River to 
Bayou Teche, LA'4 
Lake Borgne and Chef Menteur- 
Bulkheads and Jetties 
Lake Charles Deep Water Channel, LA' 5 
Little Caillou Bayou, LA 
Mermentau River, Bayou Nezpique, and 
Bay Des Cannes, LA 
Mississippi River-Gulf Outlet, 
Michoud Canal, LA 
Navigation work under special 
authorization (Calcasieu Pass 
channel in Old River Bend 
at Cameron, LA)'7 
Pass Manchac, LA 
Petite Anse, Tigre, and 
Carlin Bayous, LA 
Sulphur River, AR and TX 3'6 
Tickfaw, Natalbany, Ponchatoula, 
and Blood Rivers, LA4 
Vinton Waterway, LA2' 
Complete 
Complete 
Deauthorized 
Complete 
Complete 
Deauthorized 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Deauthorized 
Complete 
Complete 
Complete 
Complete 
Inactive 
Complete 
Deauthorized 
1967 
1978 
1981 
19462 
1974 
1887 
1968 
1967 
1970 
1950 
1970 
1958 
1961 
1947 
1936 
1976 
1981 
1973 
1910 
1967 
1971 
1950 
1960 
1956 
19422 
1950 
1973 
1977 
1976 
1957 
1950 
1981 
199 
1973 
1950 
$- 
28,234 
501,963 
30,997 
5,000 
38,915 
1969 
4,716 
96,916 
33,410 
33,355 
238,828 
120,089 
34,900 
1,015,81410 
5,856,200 
4,197,262 
2,500 
58,342 
202,817 
7,676 
249,052 
77,761 
5,197,97516 
2,499,555 
1,374 
45,989 
8,115 
69,087 
290,192 
104,1877 
123,454 
92,276 
223,616 
36,780 
28,315 
213,455 
251,691 
200,169 
37,169 
2,000 
192,011 
452,611 
14,48012 
552,780 
11,699 
241,896 
751,485 
114,519 
139,755 
10,039 
811,172 
92,163 
1928 
1914 
Nov. 1979 
1931 
1939 
May 1981 
1938 
May 1956 
1915 
March 1923 
1916 
1896 
3 
April 1974 
Sep. 1978 
Jan. 1968 
1959 
Dec. 1914 
1939 
Nov. 1979 
1929 
Nov. 1974 
1912 
Nov. 1980 
1921 
Nov. 1979 
11-34

NEW ORLEANS, LA, DISTRICT 
TABLE 11-E OTHER AUTHORIZED NAVIGATIONPROJECTS 
(Continued) 
Cost to Sep. 1983 
For Last Mo. and Yr. 
Full Report Operation Completed 
See Annual and Deauthorized 
Project Status Report For: Construction Maintenance or Reclassified 
Waterway from White Lake to 
Pecan Island, LA18 1948 10,904 10,742 
Waterway from Empire, 
LA, to Gulf of Mexico Complete 1981 1,068,142 835,252 Jun. 1950 
1. Transferred to Departmentof Transportation. Authorized 
under Truman-Hobbs Act. 
2. Date authorized. 
3. Completed. Date will be furnished when available. 
4. Includes previous project costs. 
5. No commerce reported. 
6. Abandonment recommended in H. Doc. 467, 69th 
Cong., 1st sess. 
7. Includes $56 cost incurred in 1969. 
8. Completed except that portion above mile 10.3 
providing for widening from 40 feet to 60 feet, which is 
minactive. 
9. By Public Law 88-404, that portion of Bayou Terrebonne 
between point where Barrow Street crosses said stream 
and a line determined by prolonging and extending eastern 
right-of-way line of New Orleans Boulevard southerly to 
south bank of said stream was declared nonnavigable. 
10. Includes $66,000 contributed funds. 
11. Operation and maintenance of the structure reported 
under project "Calcasieu River and Pass, LA." 
12. Excludes $50,000 contributed funds. 
13. Not completed; incorporated in navigation project 
"Mermentau River, LA." 
14. Not completed; superseded for most of its length by 
present 12- by 125-foot Gulf Intracoastal Waterway, which 
coincides with or parallels it. 
15. Maintenance project; no future work schedules. 
16. Includes $57,555 ($29,974 of which was from Public 
Works funds) for new work on previous project. Includes 
$114,519 for maintenance of previous project. 
17. Work is under continuing authority. 
11-35

TABLE 11-F 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
OTHER AUTHORIZED FLOOD CONTROL 
PROJECTS 
For Last Cost to Sep. 1983 
Full Report Operation 
Mo. and Yr. See Annual and Mo. and Yr. 
Project Deauthorized Report For: Construction Maintenance Completed 
Aloha-Rigolette Area, Grant and 
Rapides Parishes, LA' 
Amite River and Tributaries, LA 
Bayou Bodcaul Red Chute, and Loggy 
Bayou, LA . 2 
Bayou Choupique, LA 
Bayou Nicholas, Coushatta, LA3 
Bayou Pierre in vicinity of 
Shreveport, LA1 2" 2 
Bayou Rapides, LA3 
Black Bayou Reservoir, LA1' 4 5.12 
Black Bayou-Pine Island Area, LA3 
Campti-Clarence Area in Natchitoches 
Parish, LA 
Choctaw Bayou and Tributaries, LA" 7. 12 
Colfax, Grant Parishes, LA" 7 
Cooper Lake and Channels, TX8 
East Point, LA 
Ferrells Bridge Dam-Lake O' the Pines, TX9 
Garland City, AR.'2 
Grant Parish below Colfax, LA" 9 
Harvey Canal, Bayou Barataria Levee, LA 
Hempstead County Levee District No. 1, 
AR.x, 
Maniece Bayou, AR." 2 
McKinney Bayou, Finn Bayou 
Segment, AR. o 
Natchitoches Parish, LA" 2 
Pineville, Red River, LA" 3. 12 
Posten Bayou, AR.11, 12 
Red River Parish, LA" 9. 12 
Red River in vicinity of Shreveport, LA" 12 
Saline Point, LA" 9 
Twelvemile Bayou, LA3 
Aug. 1977 
1956 
1964 
1948 
1954 
1964 
1951 
1952 
1945 
1963 
1978 
1977 
1938 
1979 
1969 
1979 
1976 
1941 
1979 
1941 
1970 
196310 
1956 
1953 
1973 
1939 
1953 
1945 
1966 
$ 1,653,189 
3,034,2552 
319,200 
129,930 
70,717 
243,3362 
95,179 
3364063 
1,655,700 
741,892 
70,348 
20,839,300 
486,069 
14,175,197 
1,335,842 
38,809 
1,018,005 
88,006 
970,9322 
1,529,478 
232,426 
8,301,021 
149,435 
3,908,000 
124,111 
335,433 
- Mar. 1953 
- May 1965 
11-36 
Apr. 1955 
Feb. 1964 
Jan. 1948 
Mar. 1954 
Jun. 1964 
Jun. 1939 
Dec. 1951 
May 1963 
Jul. 1978 
Apr. 1976 
Aug. 1968 
Jul. 1974 
9
9 
Aug. 1969 
Aug. 1955 
Dec. 1951

NEW ORLEANS, LA, DISTRICT 
TABLE 11-F 
(Continued) 
OTHER AUTHORIZED FLOOD CONTROL 
PROJECTS 
For Last Cost to Sep. 1983 
Full Report Operation 
Mo. and Yr. See Annual and Mo. and Yr. 
Project Deauthorized Report For: Construction Maintenance Completed 
Wright Patman Dam and Lake, TX8 - 1979 35,659,176 11,195,021 - 
1. Authorized under project "Red River Below Denison 
Dam."
2. In addition, the following was expended from contributed 
funds: 
Amite River and tributaries .............. $ 430 
Bayou Pierre in vicinity of 
Shreveport, LA ......................... 89,047 
Choctaw Bayou and Tributaries, LA ...... 170,799 
Harvey Canal, Bayou Barataria 
Levee, LA ............................. 425,209 
Maniece Bayou, AR ..................... 39,293 
Natchitoches Parish, LA ................. 250,000 
3. Authorized by Chief of Engineers. (Sec. 205, 1948 
Flood Control Act, as amended.) 
4. Construction not initiated. 
5. Inactive. 
6. Includes $92,000 for preauthorization studies. 
7. Completed under provisions of Sec. 7 Flood Control 
Act 1928, as amended by Sec, 9, Flood Control Act 1936, and 
included in 1939 Annual Report of President, Mississippi 
River Commission, p. 2214. 
8. These projects transferred to the Fort Worth District, 
Southwestern Division, during FY 1979. 
9. Completed. Date will be furnished when available. 
10. Date authorized. 
11. Posten Bayou Project, authorized by Senate and 
House Resolutions, Dec. 17 and 15, 1970, deleted the plan 
authorized by the Flood Control Act dated Aug. 3, 1955. 
12. These projects transferred to the Vicksburg District 
during FY 1983. 
11-37

TABLE 11-G 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
ACTIVE GENERAL INVESTIGATIONS 
(96x3121) 
Federal Cost Totals by 
Item and CWIS Number FY 83 Categories 
SURVEYS (Category 100) 
Navigation (110) 
GIWW LA & TX Section -10032 
Flood Control Studies (120) 
Aloha-Rigolette Area, LA -12123 
Amite River & Tributaries, LA -50100 
Louisiana Coastal Area, LA -61610 
Mermentau, Vermilion & Calcasieu Rivers & Bayou Teche, LA -34014 
West Bank of Miss. River in vicinity of New Orleans, LA -59360 
Comprehensive Basin Studies (150) 
Red River Authorization Report -81129 
Miscellaneous Activities (170) 
Special Investigations -17250 
Coordination Studies with Other Agencies (180) 
Planning Assistance to States (186) -51850 
Tech. & Engr. Assist. Shore & Streambank Erosion (188) -51731 
TOTAL (Category 100) 
Collection and Study of Basic Data (Category 200) 
Inspection and Inventory of Dams (236) -53843 and -53842 
Flood Plain Management Services (250) 
Flood Plain Management Services 
Hydrologic Studies (260) 
Hydrologic Studies -53820 
TOTAL (Category 200) 
Research and Development (Category 300) 
Continuation of Planning and Engineering (Category 400) 
Mississippi River-Ship Channel, Gulf to Baton Rouge, LA (55270) 
TOTAL (Category 400) 
Advance Engineering and Design (Category 600) 
McKinney Bayou, AR and TX (75353) 
West Agurs Levee, LA (75345) 
TOTAL (Category 600) 
GRAND TOTAL GENERAL INVESTIGATIONS 
$ 392,724 
392,724 
228,671 
26,492 
251,226 
618,371
0 
1,124,760 
5,751 
39,575 
36,469 
92 
36r,561
0 
149,431
0
0 
1,543,879 
220,360 
43,711 
$1,599,371 
149,431 
None 
1,543,879 
264,071 
$3,556,752 
11-38

VICKSBURG, MS, DISTRICT* 
This district comprises western Mississippi, southern 
Arkansas, northern Louisiana, and a very small portion 
of southwestern Tennessee, embraced in drainage basins 
of eastern tributaries of Mississippi River south of 
Horn Lake Creek to and including Buffalo River; Pearl 
River Basin in Mississippi; independent tributaries of 
the Gulf of Mexico south of the Buffalo River Basin to 
the Mississippi-Louisiana state line; western tributaries 
of Mississippi River between White and Atchafalaya 
Rivers including Arkansas River Basin below a point 3 
miles upstream from Pine Bluff and Arkansas River 
below mile 36.1 near Pendleton, Arkansas; Ouachita 
and Black Rivers in Arkansas and Louisiana; and Red 
River in Louisiana and Arkansas to the Texas-Louisiana 
state line. 
IMPROVEMENTS 
Navigation 
1. Claiborne County Port, MS ......... 
2. Lake Providence Harbor, LA ....... 
3. Madison Parish Port, LA.......... 
4. Ouachita and Black Rivers below 
Camden, AR .................... 
5. Overton-Red River Waterway, LA . .. 
6. Pearl River, MS and LA ........... 
7. Red River emergency bank 
protection ....................... 
8. Red River Waterway-Mississippi 
River to Shreveport, LA ........... 
9. Rosedale Harbor, MS............. 
10. YazooRiver, MS................ 
11. Navigation work under special 
authorization .................... 
Flood Control 
12. Bayou Bartholomew and 
Tributaries, AR and LA........... 
13. Bayou Bodcau and tributaries, 
AR and LA ..................... 
14. Bayou Bodcau Reservoir, LA....... 
15. Bayou Pierre, LA................ 
16. Blakely Mountain Dam-Lake 
Ouachita, Ouachita River, AR...... 
17. CaddoLake, LA.................. 
18. DeGray Lake, Caddo River, AR ..... 
19. Lead Bayou, MS ................. 
20. Monroe Floodwall, LA............ 
21. Narrows Dam-Lake Greeson, Little 
Missouri River, AR.............. 
22. Ouachita River Levees, LA......... 
23. Ouachita River and Tributaries 
AR and LA .................... 
24. Porter Bayou, MS............... 
25. Red River below Denison Dam 
(Vicksburg Dist.)................ 
Page Flood Control (cont) 
12-2 26. Red River below Denison Dam, levees 
12-2 and bank stabilization 
12-2 (Vicksburg Dist.)................ 
27. Red River Waterway-Shreveport, 
12-2 LA, to Index, AR................. 
12-3 28. Wallace Lake, LA............... 
12-3 29. Inspection of completed Flood 
Control ......................... 
12-4 30. Flood control work under 
special authorization............. 
12-5 
12-5 
12-5 Tables 
Table 12-A Cost and Financial 
12-6 Statement.................. 
Table 12-B Authorizing Legislation....... 
Table 12-C Ouachita and Black Rivers, 
AR and LA (9-Foot Project), 
Locks and Dams............ 
12-6 Table 12-D Locks in Pearl River 
Project ................... 
12-6 Table 12-E Other Authorized Navigation 
12-7 Projects .................. 
12-7 Table 12-F Ouachita River and Tributaries 
Existing Project............. 
12-7 Table 12-G Reservoir Operations 
12-8 Fiscal Year 1983............ 
12-8 Table 12-H Red River Below Denison Dam 
12-8 (Vicksburg Dist.) 
12-8 New Projects.............. 
Table 12-I Red River Below Denison Dam 
12-8 (Vicksburg Dist.) 
12-9 Incorporated Projects........ 
Table 12-J Other Authorized Flood 
12-9 Control Projects............ 
12-9 Table 12-K Active General Investigations . . 
12-10 
12-1 
Page 
12-10 
12-10 
12-11 
12-12 
12-12 
12-13 
12-16 
12-19 
12-20 
12-21 
12-22 
12-22 
12-23 
12-24 
12-25 
12-26

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Navigation 
1. CLAIBORNE COUNTY PORT, MS. 
Location. A slack-water harbor on the east bank of 
the Mississippi River at mile 405 above Head of Passes, 
and about 4 miles west of Port Gibson, MS. 
Existing project. A dredged access channel 800 feet 
long and 150 feet wide with a 400- by 800-foot turning 
basin and an additional 50 feet of fleeting and berthing 
on the north and south bank. 
Local cooperation. Fully complied with. Provided a 
diked disposal area for placement of dredged material 
for industrial development. 
Operations and results during fiscal year. Leased 
dredged completed 95 percent of channel and harbor. 
Condition as of Sep. 80. Due to high Mississippi 
River stages, 5 percent of the dredging remains to be 
completed. 
2. LAKE PROVIDENCE HARBOR, LA 
Location. In Hagaman Chute, a secondary channel of 
the Mississippi River at mile 483.4 above Head of 
Passes, and about 3 miles south of Lake Providence, LA. 
Existing project. A dredged harbor channel about 
0.7 mile long and 150 feet wide with a project depth of 9 
feet in Hagaman Chute from the Mississippi River. 
Channel was widened to 400 feet in front of and 
upstream from port area, a distance of 800 feet, to 
provide a turning basin. Local interests constructed 
retaining dikes to provide the disposal area for material 
excavated from channel and turning basin. Resulting 
hydraulic fill provides a raised port area. Federal cost 
of completed work was $198,859, excluding preauthorization 
study costs of $9,678. Total non-Federal cost was 
$233,400, including cost of retaining dikes, and a cash 
contribution of $35,000. In addition, local interests have 
spent $1,022,000 for port facilities. Restudy of port for 
expansion, completed under continuing authority 
program. No further expansion is recommended. 
Local cooperation. Fully complied with. 
Terminal facilities. Local interests provided port 
facilities. 
Operations and results during fiscal year. No 
maintenance dredging was performed during this 
fiscal year. 
Condition as of Sep. 30. No major navigation 
problems exist at the present time. 
3. MADISON PARISH PORT, LA 
Location. A "fast-water" dredged channel located 
near the right descending bank of the Mississippi River 
at mile 457.2 above Head of Passes, and about 6 miles 
north of Tallulah, Louisiana. 
Existing project. A dredged harbor channel about 
0.5 mile long and 150 feet wide with a project depth of 9 
feet. A turning basin within this channel was constructed 
by widening the harbor channel to 350 feet for 
a distance of 1,000 feet. Dredged material was used in 
construction of two hydraulic fills on property owned by 
the Madison Parish Port Commission for future development. 
Channel construction was completed in October 
1980. 
Local cooperation. Fully complied with. 
Terminal facilities. Madison Parish Port Commission 
has constructed a multipurpose loading dock, rail 
facilities, and storage building on hydraulic fill. Two 
private interests are engaged in grain handling facilities 
on adjacent properties. 
Operations and results during fiscal year. No 
maintenance dredging was performed during this 
fiscal year. 
Condition as of Sep. 30. No major navigation 
problems exist at the present time. 
4. OUACHITA AND BLACK RIVERS 
BELOW CAMDEN, AR 
Location. Ouachita River rises in Polk County, AR, 
and flows southeasterly and southerly about 600 miles. 
Below its confluence with the Tensas and Little Rivers 
at Jonesville, LA, it is called Black River, which enters 
Red River 35.5 miles from the Mississippi River. 
Previous projects. See page 683 of Annual Report 
for 1962 for details. 
Existing project. See page 684 of Annual Report for 
1962 for details of existing 6.5-foot navigation project. 
New work for completed project costs $4,574,551, exclusive 
of amounts expended under previous projects. 
Modified project and project for Red River below 
Fulton, AR, provide for a channel 9 feet deep and 100 
feet wide in Red River between Old River and mouth of 
Black River, and in Black and Ouachita Rivers from 
mouth of Black River to Camden, AR. This is being 
accomplished by construction of four new locks, 84 feet 
by 600 feet; new dams; channel realinement; and 
measures to preserve Catahoula Lake for migratory 
waterfowl. Jonesville Lock and Dam replaced existing 
Lock and Dam No. 2; Columbia Lock and Dam replaced 
existing Lock and Dams Nos. 3, 4, and 5; Felsenthal 
Lock and Dam will replace existing Lock and Dam No. 
6; and Calion Lock and Dam will replace existing Lock 
and Dam No. 8. The Felsenthal Canal was deauthorized 
as of Aug. 5, 1977, in accordance with Section 12 of the 
Water Resources Development Act of 1974. The River 
and Harbor Act of 1970 authorized establishment of 
wildlife refuges along Bayou D'Arbonne (14,700 acres) 
in connection with Columbia Lock and Dam and at 
Felsenthal Lock and Dam (65,000 acres). The Bayou 
D'Arbonne refuge was increased to 18,000 acres at the 
request of the Bureau of Sport Fisheries and Wildlife. 
Approved (1983) estimated cost for new work for 
9-foot navigation project is $262,852,000 including 
$253,000,000 Federal and $9,852,000 non-Federal for 
lands, damages, and relocations. 
12-2

VICKSBURG, MS, DISTRICT 
Local cooperation. Local cooperation for all completed 
work in Louisiana has been furnished in a timely 
manner. It is anticipated that local interests in Louisiana 
will be able to supply the necessary rights-of-way 
for construction of the cutoffs and bend widenings. 
Local interests in Arkansas have furnished the rightsof-
way for the Felsenthal and Calion Locks and Dams 
and it is anticipated that the remaining rights-of-way 
will be furnished when needed. The city of Camden, AR, 
has furnished land for the Sandy Beach recreation area. 
All assurances from local interests in Arkansas including 
supplemental assurances (Public Law 91-646) 
have been accepted. The State of Louisiana has not 
furnished supplemental assurances; however, they are 
anticipated in the near future. 
Terminal facilities. Public loading docks are at 
Columbia, LA, and Camden, AR. Privately owned 
docks and loading and unloading facilities are at 
Columbia, Monroe, and Sterlington, LA, and El Dorado, 
Calion, and Camden, AR. Two grain-handling facilities 
and a petroleum-loading facility are in the vicinity of 
Jonesville, LA, and a grain-handling facility is in the 
vicinity of Acme, LA. 
Operations and results during fiscal year. Construction 
of Felsenthal Lock and Dam is complete. 
Construction of Calion Lock and Dam is scheduled for 
completion in early FY 84. Contracts were awarded for 
construction of both the Felsenthal and Calion Access 
Channels and Closure Dams in FY 82 with completion 
scheduled in late FY 84. A construction contract was 
also awarded for Crossett Harbor, AR, on Sep. 30, 1982, 
and construction is scheduled for completion in early 
FY 84. During FY 81 a channel alignment review was 
conducted in response to public opposition to the channel 
realignment features of the project. As a result of the 
alignment review, an amendment was included in 1982 
Appropriations Act directing the Chief of Engineers to 
restudy the navigation options above Crossett, AR, with 
a view of reducing the realignment features. The 
restudy is complete and was submitted to the Appropriations 
Committees of Congress in July 1983. The 
leased dredge, Lewis James, removed 1,102,400 cubic 
yards of material from the Ouachita-Black waterway 
between October 1982 and September 1983. 
Condition as of Sep. 30. The 6.5-foot project is 
complete and is being maintained. Planning and design 
for the 9-foot navigation project started in FY 
1962 are continuing. Construction at Columbia Lock 
and Dam started in February 1964. The dam was completed 
in November 1968, and the lock was completed 
in January 1970 and was placed in service in May 1972. 
Construction at Jonesville Lock and Dam started in 
May 1967. The lock and dam were completed in January 
1972 and were placed in service in March 1972. A 
9-foot navigation channel to Lock and Dam No. 5 at 
Sterlington, LA, was established in June 1972. (See 
Table 12-C on locks and dams, Ouachita and Black 
Rivers, AR and LA.) 
The contract for removal of four abandoned locks and 
dams which proved hazardous to navigation in the 
Columbia and Jonesville pools is completed. Construction 
of Felsenthal Lock and Dam is complete and 
construction of Calion Lock and Dam is nearing completion. 
There have been 17,421 acres acquired for the 
Bayou D'Arbonne Wildlife Refuge and 64,976 acres 
acquired for the Felsenthal Wildlife Refuge. Acquisition 
of the lands for both refuges is complete. Acquisition 
of mineral interest and relocations assistance in the 
Felsenthal Wildlife Refuge is continuing. 
5. OVERTON-RED RIVER 
WATERWAY, LA 
Location. In the State of Louisiana between junction 
of the Old and Mississippi Rivers and Shreveport, LA, 
along the Old and Red Rivers, through land cuts and 
natural channels on the south bank of Red River. 
(Refer to Geological Survey State maps and the MRC 
alluvial valley quadrangle maps.) 
Existing project. Provides for a navigation route 
from the Mississippi River at its junction with Old 
River, through Old River to mile 31 of the Red River; 
developing a channel about 31 miles long, 200 feet 
wide, and 9 feet deep. Improvements consist of revetments, 
dikes, and dredging designed to preserve 
favorable and correct unfavorable channel alinement 
and depth. In addition to the existing project, the 
authorized work included a navigation route from mile 
31 of the Red River to Shreveport, LA, via a lateral 
canal excavated along the south bank of the Red River. 
However, the portion of the authorized project above 
mile 31 was reclassified to inactive status as approved 
by Office of the Chief of Engineers, letter dated Oct. 18, 
1971. 
Local cooperation. Fully complied with. For details 
see page 11-18, Annual Report FY 1980. 
Terminal facilities. None. Will be furnished if 
necessary. 
Operations and results during fiscal year. The 
leased cutterhead dredges, Butcher and Lewis James, 
performed channel maintenance during FY 1983. A 
total of 566,000 cubic yards were removed from the 
channel. 
Condition as of Sep. 30. Construction of the lower 31 
miles was initiated Nov. 12, 1968, and is 100 percent 
complete with 68,923 linear feet of bank protected. 
6. PEARL RIVER, MS AND LA 
Location. Pearl River rises in east central Mississippi 
and flows southwest about 172 miles to Jackson, MS, 
thence southeast about 269 miles to the head of its delta, 
where it divides into West Pearl and East Pearl Rivers. 
West Pearl River flows about 34 miles to the Rigolets, a 
tidal pass connecting Lake Pontchartrain with Lake 
Borgne, an arm of the Gulf of Mexico. 
Previous project. For details see page 750, Annual 
Report for 1938 and page 463, Annual Report for 1965. 
12-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Existing project. The authorized project provides 
for a channel from the mouth of West Pearl River for 58 
miles to the mouth of Bogalusa Creek at Bogalusa, 
LA, 7 feet deep at low water with a bottom width of 
100 feet in the river sections and 80 feet in the canal 
section, with locks 65 by 310 feet clear inside dimensions. 
The plan of improvement may be divided into 
three sections as follows: the river section from the 
mouth of West Pearl River to mile 28.5 at Holmes Bayou 
with a channel 7 feet deep and 100 feet wide to be 
obtained by dredging, snagging, and construction of 
cutoffs and easement of critical bends at eight locations 
below Lock One along Pearl River in its reach from its 
mouth to mile 26, all at a depth of 7 feet; the canal 
section from mile 28.5 to 48.7 at Pools Bluff with a 
channel 7 feet deep and 80 feet wide to be obtained by 
construction of three locks in the canal with sills across 
Bogue Chitto at mile 44 and across the river at mile 48.7; 
the river section from mile 48.7 to 58 at the mouth of 
Bogalusa Creek to be obtained by dredging, snagging, 
and easing of bends. At Bogalusa the mean variation of 
water surface is 10 feet and extreme, 23 feet. Plane of 
reference is mean low water. 
Estimated cost of the project (1980) is $8,429,100 
including $8,274,494 for improvements completed prior 
to 1966, and $154,800 cost for providing recreational 
facilities (Code 710). (See Table 12-D for features of 
locks included in existing projects.) 
Local cooperation. Fully complied with. 
Terminal facilities. The city of Bogalusa provides a 
barge terminal consisting of a wharf, transit shed, and 
access road at Richardson's Landing at the head of the 
project. A privately owned wharf at the Pearl River 
Highway Bridge near Pearl River Station, LA, is used 
for unloading logs. Only natural landings exist at 
various locations on the river. Facilities are considered 
adequate for existing commerce. 
Operations and results during fiscal year. General 
Operation Locks--$44,900; Lock #1 Operation- 
$21,000; Lock #2 Operation and Maintenance- 
$61,800; Lock #3 Operation and Maintenance- 
$45,000; Reservoir Operation Non Fee Area- 
$14,900; Collection for Quarters-$6,300.06. 
Condition at end of fiscal year. The existing project, 
prior to adoption of modifications authorized by the 
1966 River and Harbor Act, was commenced in October 
1938 and completed in January 1956. All locks were 
opened to navigation in November 1953. No work has 
been initiated on modifications (cutoffs and easements 
of bends below Lock 1) authorized by the 1966 Act. 
Total Federal costs under existing project as of Sep. 
30, 1981, were $8,418,465 for new work and $4,702,099 
for maintenance, a total of $13,120,564. Contributed 
funds for new work amount to $65,000. 
The responsibility of this project was transferred to 
Vicksburg District, Lower Mississippi Valley Division, 
on Oct. 1, 1981. Routine maintenance was performed at 
each of the three lock sites during the year. 
4 Point Plan, Vicinity of Jackson, MS. The plan of 
improvement consists of clearing approximately 3.3 
miles of the floodway, cutoff of a channel bendway 
downstream of 1-20, limited modification of the Ross 
Barnett Reservoir to allow operation for interim flood 
control purposes, and enlarging the opening at the 
Highway 25 bridge (completed by local interests). Also 
included in the authorized improvements in the vicinity 
of Jackson is the extension of the west bank levee at 
Fortification Street. 
Project sponsors for the 4 Point Plan are as follows: 
Clearing the floodway - Rankin-Hinds Pearl River 
Flood Control and Drainage District and the Pearl 
River Basin Development District. 
Modification of the Ross Barnett Reservoir - Pearl 
River Water Supply District. 
Highway 25 Bridge - Pearl River Basin Development 
District. 
Fortification Street Levee Extension in Rankin - 
Hinds Pearl River Flood Control and Drainage District. 
A report showing the general plan for flood control 
at Jackson is scheduled to be submitt2d to Assistant 
Secretary of the Army in December 1983. 
A GDM covering the 4 Point Plan is scheduled to be 
completed in Jan. 84. Construction on all items of work 
is scheduled to be initiated in FY 84 and FY 85 with 
the levee extension to be completed in FY 84, the 
clearing and the reservoir modification to be completed 
in FY 85 and the cutoff to be completed in FY 86. 
7. RED RIVER EMERGENCY 
BANK PROTECTION 
Location. In northwest Louisiana, southwest Arkansas, 
and northeast Texas, along the Red and Old Rivers 
between the Mississippi River and the head of the levee 
system above Index, TX. 
Existing project. Provides for realining the banks 
by means of cutoffs and training works and for stabilizing 
banks by means of revetments, dikes, and other 
methods as emergency conditions may require in 
advance of developing the design for the entire Red 
River Waterway project. Estimated cost for new work 
(October 1983) is $59,600,000 Federal and $220,000 
Non-Federal, including a cash contribution of $25,000. 
Local cooperation. Fully complied with. For details 
see pages 11-19 to 11-20, Annual Report FY 1980. 
Operations and results during fiscal year. Work 
by hired labor consisted of preparing plans and 
specifications, surveys, and general engineering. 
Stabilization work was completed at Little River Phase 
I, mile 405.5-L. 
Work was initiated and is continuing on three items: 
Boyd revetment, mile 383-L; Little River revetment 
Phase II, mile 405.5-L; and Clipper revetment, mile 
406-R. A construction contract was awarded on Mo- 
Pac revetment, mile 403-R, on Sep. 29, 1983. 
Condition as of Sep. 30. Construction was initiated 
in October 1972 and is 87 percent complete. 
12-4

VICKSBURG, MS, DISTRICT 
8. RED RIVER WATERWAYMISSISSIPPI 
RIVER TO 
SHREVEPORT, LA 
Location. From east central to northwest Louisiana 
along the Red and Old Rivers between the Mississippi 
River and Shreveport, LA. 
Existing project. Provide a navigation route from 
the Mississippi River at the junction with Old River via 
Old and Red River to Shreveport, LA, developing a 
channel approximately 210 miles long, 9 feet deep, and 
200 feet wide. The development will include five locks 
and dams, realinement and contraction of the river as 
necessary to develop an efficient channel, and bank 
stabilization as necessary to hold the newly developed 
channel in position. Facilities to provide opportunities 
for recreation and for fish and wildlife development 
are an integral part of the project. Estimated cost for 
new work (October 1983) is $1,484,000,000 Federal 
and $75,500,000 non-Federal, including $36,350,000 
contributed funds. The Federal cost excludes $274,000 
for aids to navigation by U.S. Coast Guard. 
Local cooperation. For details see page 11-21, 
Annual Report FY 1980. 
The Red River Waterway Commission, governing 
body of the Red River Waterway District, executed an 
act of assurance for all project features in Louisiana on 
Feb. 26, 1969, supported by resolution dated Jan. 30, 
1969. The assurances were accepted for and on behalf 
of the United States on Apr. 15, 1969. The Commission 
furnished amended assurances covering the provisions 
of PL 91-646 on May 23, 1973, for the portion of the 
project within Louisiana which were accepted for and 
on behalf of the United States on Nov. 14, 1973. 
Terminal facilities. Local interests are to provide 
adequate terminal facilities along the waterway and 
the first application for port construction was received 
this FY. The City of Alexandria, LA has applied for a 
permit for port construction at mile 109. 
Operations and results during fiscal year. Hired 
labor continued work on Design Memoranda, preparation 
of Plans and Specifications, Surveys, General 
Engineering, and Model Studies. Phase III construction 
at Lock and Dam 1 reached 85 percent completion, 
and construction on the John H. Overton Lock and 
Dam was initiated and reached 19 percent completion. 
Additionally, seven channel realignment and stabilization 
contracts were awarded for work in Pools 1&2, 
and are in various stages of construction. 
Condition as of Sep. 30. Construction was initiated 
in July 1973, and project is 26 percent complete. 
9. ROSEDALE HARBOR, MS 
Location. In Log Loader Chute, a secondary channel 
of the Mississippi River at mile 584.5 above Head of 
Passes, and about 2 miles south of Rosedale, MS. 
Existing project. A dredged harbor channel about 
2.4 miles long and 150 feet wide with a project depth of 9 
feet. A turning basin consists of a dredged channel 
1,000 feet long and 400 feet wide. Local interests 
constructed retaining dikes to provide the disposal area 
for material excavated from the channel and turning 
basin. Resulting hydraulic fill provides a 20-acre port 
area. Channel construction was completed in February 
1978 at a cost of $2 million. Local interests are continuing 
construction on port terminal, dock facilities, and 
additional dredging. 
Local cooperation. Fully complied with. 
Terminal facilities. Local interests provided port 
facilities. 
Operations and results during fiscal year. The 
dredge, Ockerson, and the contract dredge, Lewis 
James, removed 315,900 cubic yards of material during 
FY 83. 
Condition as of Sep. 30. No major problems were 
experienced with navigation. 
10. YAZOO RIVER, MS 
Location. Formed by junction of Tallahatchie and 
Yalobusha Rivers in Leflore County, MS, flows about 
169 miles southerly and southwesterly, and enters 
Mississippi River at Vicksburg, MS. (See Mississippi 
River alluvial valley quadrangle maps.) 
Previous projects. See page 681 of Annual Report 
for 1961 for details. 
Authorized project. The Yazoo River Navigation 
project consists of a 9-foot channel from its mouth to 
Greenwood, MS, mile 164.9 (present mileage), with a 
minimum width of 150 feet. The project includes a 
single lock (84 feet by 600 feet) and a dam located near 
Vicksburg, dredging and channel realinement; 600,000 
acre-feet of additional storage in Sardis Lake to augment 
low flows in the Yazoo River, and recreation 
features. Total estimated (1983) Federal cost of 9-foot 
project is $215,000,000 which includes $407,000 for the 
U.S. Coast Guard. Total estimated non-Federal cost is 
$2,786,000. These figures do not include the total 
estimated (1983) Federal cost of Belzoni Bridge relocation 
which is $8,570,000 and the total estimated non- 
Federal cost which is $252,000. 
Local cooperation. Requirements of local cooperation 
are fully described on page 12-3 of FY 80 Annual 
Report. 
Terminal facilities. At Greenwood there is a 
privately owned dock and a grain-loading facility. 
There are privately owned facilities for loading grain at 
Belzoni and Satartia. At Yazoo City there is a privately 
owned grain-loading facility, a private log-loading 
facility, a private dock to handle dry and liquid 
fertilizer, and a public terminal. 
Operations and results during fiscal year. The 
construction of Belzoni Bridge was about 99 percent 
complete at the end of the fiscal year. 
Condition as of Sep. 30. Entire river is navigable. No 
work done on new authorization, except for construction 
12-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
work connected with the relocation of State Highway 
No. 12 Bridge at Belzoni, MS. Phase I studies are 
continuing on the 9-foot project. 
11. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation activities pursuant to Sec. 107, Public 
Law 87-645, as amended (preauthorization). 
During FY 1983, detailed studies were completed on 
Bastrop Port, LA, at a cost of $69,637; continued on 
Yellow Bend Port, AR, at a cost of $125,920, and 
started on Union County Port, AR, at a cost of $104,254. 
A negative reconnaissance study was completed at 
Yazoo City, MS, at a cost of $6,510. 
Flood Control 
12. BAYOU BARTHOLOMEW AND 
TRIBUTARIES, AR AND LA 
Location. Bayou Bartholomew rises in Jefferson 
County, AR, about 10 miles northwest of Pine Bluff and 
flows southerly about 370 miles to join the Ouachita 
River upstream from Sterlington, LA. 
Authorized project. Project includes ten waterretention 
lakes in the western tributaries of Bayou 
Bartholomew in Arkansas and six local levee units 
along the main stem of Bayou Bartholomew in Louisiana. 
However, because of public opposition to construction 
of the loop levees, preconstruction planning of 
the six loop levees has been deferred until such time as 
there is sufficient support for such levees by local 
interests. Channel improvements previously authorized 
are deferred until it is determined that the quality and 
quantity of water downstream will not be adversely 
affected. Latest approved (1979) estimated cost of new 
work is $46,913,000 including $44,800,000 Federal and 
$2,113,000 non-Federal. 
Local cooperation. Requirements of local cooperation 
are fully described on page 12-5 of Fiscal Year 80 
Annual Report. 
Operations and results during fiscal year. Preconstruction 
planning and design have been deferred 
pending favorable benefit-cost ratios. 
Condition as of Sep. 30. Preparation of general 
design memorandum has been deferred due to lack of 
economic justification. 
13. BAYOU BODCAU AND 
TRIBUTARIES, AR AND LA 
Location. In left bank flood plain of Red River. 
Bayou Bodeau rises in vicinity of Hope, AR, and flows 
southerly through Bayou Bodcau Reservoir and Bodcau 
Lake to join Cypress Bayou and form Red Chute Bayou, 
continues through Red Chute Bayou, Flat Lake, and 
Loggy Bayou to Red River, about 40 miles below 
Shreveport, LA. 
Existing project. Cypress Bayou-Red Chute Bayou 
levee: Extend existing levee from about 8 miles southeast 
of Benton, LA, proceeding southerly to junction of 
Cross and Red Chute Bayous, and then parallel to Red 
Chute Bayou on the right descending bank to its 
junction with Cutoff Bayou for a total distance of 
approximately 25 miles; construct landside drainage 
channel and several culverts with flap gates to Red 
Chute Bayou; construct cutoff on Red Chute Bayou just 
south of Louisiana Highway 527; construct approximately 
5 miles of levee on left descending bank of Red 
Chute Bayou extending south from Louisiana Highway 
612, and relocate utility lines as needed. 
Flat River-Loggy Bayou levee: Extend from lower 
end of existing Red River levee in vicinity of Ninock, 
LA, along high (left descending) bank of Red River to a 
point on right descending bank of Loggy Bayou, about 
1 mile above its mouth, thence generally along right 
descending bank of Loggy Bayou, Red Chute, Cutoff 
Bayou, and Flat River to Taylortown to tie into existing 
Red River levee; close Flat River near its junction with 
Cutoff Bayou and install one 36-inch round corrugated 
metal pipe with automatic flap gate to drain isolated 
pockets and provide uninterrupted drainage; construct 
drainage structures on Flat River near its junction 
with Red Chute Bayou and along alinement of the 
Loggy Bayou in the vicinity of Grassy Lake; and make 
necessary utility relocations. 
Flat River channel improvement: Enlarge to average 
bottom width of 50 feet with flat side slopes and deepen 
by 2 to 6 feet from the confluence with Cutoff Bayou to 
junction with Cooper Bayou, 11.6 miles, including 
required relocations and modifications of utilities. Estimated 
cost for new work (October 1982) is $34,700,000 
Federal and $7,600,000 non-Federal; however, this is 
subject to change pending outcome of the reevaluation 
study currently underway. 
The subject project was one of the Water Resources 
projects reviewed in March 1977 in accordance with 
the President's request. As a result of this review, the 
President recommended to deauthorize this project. 
Congress subsequently directed the Corps to take the 
following two actions: Construct levees on Red Chute 
Bayou below Cutoff Bayou that are required to prevent 
induced flood damage that would otherwise result 
from the abandonment of partly completed project. 
Initiate studies to determine if modifications to the 
authorized project would permit its completion in a 
form consistent with the current executive policy. 
Engineering and design work for the induced flood 
fpirceavtieonnt iostnu dpileasn wbeerloew b eCinugto fcfo Bndayuocute da nwdh perno jPecrte smidoedni-t 
Reagan signed, on Dec. 4, 1981, the Energy and Water 
Development Appropriations Bill of 1982, which contained 
language that "reconfirmed without further 
study and analysis" the plan for flood control for the 
project as approved by the Flood Control Act of 1965. 
12-6

VICKSBURG, MS, DISTRICT 
Additional documents concerning environmental and 
socioeconomic impacts are currently being prepared 
and will be available to the public prior to further 
construction. There is clear evidence of a marked shift 
in land use within the project area over the past several 
years, from rural to urban-suburban. Because of this 
shift, we now find it necessary to expand our studies 
beyond those initially envisioned. The expanded studies 
will cover the areas of alternatives and economics, in 
addition to the natural environment. We are presently 
assessing the impacts of the expanded studies on the 
scheduled date for resuming construction on the project. 
Local cooperation. For details see pages 11-24 and 
25, Annual Report for FY 1980. 
Operations and results during fiscal year. New 
work by hired labor forces consisted of preparation of 
plans and specifications, for design deficiency, and 
engineering studies. 
Condition as of Sep. 30. Construction was initiated 
in October 1974 and is 17 percent complete. 
14. BAYOU BODCAU 
RESERVOIR, LA 
Location. In Red River Basin on Bayou Bodcau in 
Bossier Parish, LA, 72 miles above mouth of Loggy 
Bayou and 35 miles northeast of Shreveport, LA. (Refer 
to Geological Survey State map, scale 1:500,000.) 
Existing project. An earth-fill dam rising 76 feet 
above streambed with a reservoir providing a flood 
damage prevention storage capacity of 357,000 acrefeet. 
Outlet works are in south abutment, and an. 
uncontrolled spillway is on north abutment. Reservoir 
controls 656 square miles, or 53 percent, of entire 
drainage area of Bayou Bodcau. Construction of a 
floodway for diversion of Bayou Bodcau and Cypress 
Bayou to improve flood protection was authorized by 
1936 Flood Damage Prevention Act. This authorization 
was modified by 1938 Flood Control Act, which authorized 
construction of a reservoir and other flood damage 
prevention works in lieu of construction of a floodway 
for diversion of Bayou Bodcau and Cypress Bayou, LA 
to improve protection, and further modified by War 
Department Civil Appropriation Act of 1939 which 
provided that reservoir and other flood control works 
on Bayou Bodcau and Cypress Bayou, LA, authorized 
by Flood Control Act of 1938 shall be constructed in 
accordance with revised plans and cost estimates in 
Office, Chief of Engineers. New work was completed in 
1961. 
Local cooperation. None required. 
Operations and results during fiscal year. Hired 
labor forces continued operation and ordinary maintenance 
of the dam and reservoir, real estate activities, 
stream gaging, surveys and economic studies. Number 
of visitor-days of recreational use, 285,000 (Calendar 
Year 1980). (See Table 12-G for reservoir operations.) 
Condition as of Sep. 30. Construction was initiated 
April 1947 and completed April 1961. 
15. BAYOU PIERRE, LA 
Location. In Red River Basin below Shreveport, LA, 
along channel of Bayou Pierre from its mouth at Grand 
Ecore, La., upstream 30 miles to its confluence with 
Bayou Wincy. (Refer to Geological Survey State map, 
scale 1:500,000.) 
Existing project. Provides for widening channel at 
intervals, totaling 12.9 miles, and snagging of 29.7 
miles, to reduce flood damage and improve sanitary 
and living conditions over a wide area. Cost of new 
work, completed in 1939, was $299,529. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Hired 
labor forces continued condition and operations studies 
as required. 
Condition as of Sep. 30. Construction was initiated 
in FY 1938 and completed in FY 1939. 
16. BLAKELY MOUNTAIN DAMLAKE 
OUACHITA, OUACHITA 
RIVER, AR 
Location. This project is on Ouachita River, AR, at 
head of Lake Hamilton (pool of Carpenter Dam), 486 
miles above mouth of Black River, and approximately 
10 miles northwest of Hot Springs, AR. 
Previous project. See page 693 of Annual Report 
for 1962 for details. 
Existing project. A lake of 2,768,500 acre-feet 
storage capacity for flood control and other purposes 
with an installed power capacity of 75,000 kilowatts. 
Remaining work consists of completion of public-use 
facilities. Latest approved (1983) estimated project 
cost is $44,100,000. 
Local cooperation. None required. 
Operations and results during fiscal year. Power 
production totaled 270,517,000 kilowatt-hours of which 
268,731,000 kilowatt-hours were delivered to Arkansas 
Power and Light Co., under contract between that 
company and Southwestern Power Administration. 
The maximum pool elevation of 590.10 feet above 
NGVD, or 12.1 feet above the maximum power pool, 
occurred on Dec. 5, 1982. Storage in the flood control 
pool at this time amounted to 526,700 acre-feet. Peak 
24-hour inflow of 210,102 cubic feet per second 
occurred on Dec. 3, 1982. On Sep. 30, 1983, the pool 
elevation was 573.79 feet above NGVD and storage in 
the power pool was 1,286,200 acre-feet. 
Condition as of Sep. 30. Project was started in 
August 1947 and was completed for beneficial use in 
October 1955, except for public-use facilities. Power 
generation, operation, and maintenance activities are 
continuing. Remote control equipment has been installed 
and is operating the power plants at DeGray 
Lake and Narrows Dam-Lake Greeson. 
12-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
17. CADDO LAKE, LA 
Location. In Caddo Parish, about 19 miles northwest 
of Shreveport, LA, at the foot of Caddo Lake and at 
head of Twelve Mile Bayou. 
Existing project. Replacement of the original dam 
was completed in Jun. 1971, having same flow characteristics 
and located as near as practicable downstream 
of the old dam, built under navigation project "Cypress 
Bayou and Waterway between Jefferson, TX, and 
Shreveport, LA." New dam will be capable of being 
raised in the future if desirable and justified. Estimated 
cost of new work (October 1976) was $3,587,800 Federal 
and $28,000 non-Federal. 
Local cooperation. Fully complied with. Public Law 
94-587, Section 174, amended the Flood Control Act of 
1965 (PL 89-298) to provide that operation and maintenance 
of Caddo Lake Dam be the responsibility of the 
Secretary of the Army, acting through the Chief of 
Engineers. Conveyance of title to the United States 
from the Caddo Levee District is being reviewed. 
Operations and results during fiscal year. Maintenance 
by hired labor consisted of condition and 
operation studies, stream gaging, and water quality 
studies. Maximum pool elevation was 183.2 feet NGVD 
on Jan. 5, 1983, when storage in the flood control pool 
was 115,640 acre-feet. On Sep. 30, 1983, the pool 
elevation was 158.6 feet NGVD and storage in flood 
control pool was 431 acre feet. 
pool elevation was 402.43 feet above NGVD and storage 
in the power pool was 321,800 acre-feet. 
Condition as of Sep. 30. Construction started in June 
1962 and was essentially complete in December 1971. All 
major construction is complete including the remote 
control for the power plant from Blakely Mt. Dam-Lake 
Ouachita. 
Power generation, operation, and maintenance are 
continuing. 
19. LEAD BAYOU, MS 
Location. Lead Bayou is a tributary of the Sunflower 
River in Bolivar and Sunflower Counties, MS, approximately 
30 miles from the Mississippi River near 
Cleveland, MS. 
Existing project. The plan of improvement calls for 
enlarging the existing Lead Bayou channel to provide a 
1.5-year degree of protection to agricultural areas and a 
10-year degree of protection to the small developed area 
near Cleveland, MS. Total estimated Federal cost is 
$1,526,000. 
Local cooperation. Fully complied with. 
Condition as of Sep. 30. A construction contract was 
awarded Mar. 10, 1982, and as of Sep. 30, 1983, the 
project was 98 percent complete. Construction is 
scheduled for completion in October 1983. 
18. DEGRAYLAKE,CADDORIVER,AR 20. MONROE FLOODWALL, LA 
Location. On Caddo River (mile 8), a tributary of 
Ouachita River, in a narrow, rocky gorge in Clark and 
Hot Springs Counties, approximately 7 miles north of 
Arkadelphia, AR. 
Existing project. Provides for a lake of 881,900 acrefeet 
storage capacity for flood control, water supply, 
pollution abatement, and power with an installed power 
capacity of 68,000 kilowatts (one conventional 40,000- 
kilowatt generating unit and one 28,000-kilowatt generating 
unit with reversible pump-type turbine). Latest 
approved (1980) estimated first cost is $72,034,000, 
including $5,800,000 for water supply, to be reimbursed 
by local interests, exclusive of interest. 
Local cooperation. None required for flood control 
and power features. Fully complied with for water 
supply feature. 
Operations and results during fiscal year. Power 
production totaled 122,415,000 kilowatt-hours, of 
which 121,192,000 kilowatt-hours were delivered to 
Arkansas Power and Light Co., under contract between 
that company and Southwestern Power 
Administration. The maximum pool elevation of 420.54 
feet above NGVD, or 12.54 feet above the maximum 
power pool, occurred on Dec. 4, 1982. Storage in the 
flood control pool at this time amounted to 186,300 
acre-feet. Peak 24-hour inflow of 89,270 cubic feet per 
second occurred on Dec. 3, 1982. On Sep. 30, 1983, the 
Location. Monroe, LA, lies within the alluvial valley 
of the Mississippi River and on the east bank of the 
Ouachita River. The city is located in the north-central 
part of Louisiana, in Ouachita Parish. 
Existing project. Provides for construction of 
floodwall to close the 1,750-foot opening extending from 
Bry Avenue to Grammont Street. Floodwall will provide 
complete flood protection to the city of Monroe. 
Total Federal cost of new work was $2,561,000. Non- 
Federal cost was $206,000. 
Local cooperation. Requirements of local cooperation 
are fully described on page 12-6 of Fiscal Year 80 
Annual Report. 
Condition as of Sep. 30. Work on the floodwall is 
complete. 
21. NARROWS DAM-LAKE GREESON, 
LITTLE MISSOURI RIVER, AR 
Location. Narrows Dam is on the Little Missouri 
River, AR, 105 miles above the mouth and 5 miles 
northwest of Murfreesboro, AR. 
Existing project. Provides a lake of 407,900 acre-feet 
storage capacity for flood control and other purposes 
with power installation of 25,500 kilowatts in three units 
of 8,500 kilowatts each. Remaining work consists of 
12-8

VICKSBURG, MS, DISTRICT 
completion of public-use facilities. Latest approved 
(1983) estimated cost is $20,900,000, excluding 
$1,738,700 for third generating unit and remote 
control equipment. 
Local cooperation. None required. 
Operations and results during fiscal year. Power 
production totaled 60,192,500 kilowatt-hours, of which 
59,533,830 kilowatt-hours were delivered to Texas- 
Louisiana Electric Cooperative, Inc., under contract 
between that company and Southwestern Power 
Administration. The maximum pool elevation of 561.62 
feet above NGVD, or 13.62 feet above the maximum 
power pool, occurred on Dec. 6, 1982. Storage in the 
flood control pool at this time amounted to 114,800 
acre-feet. Peak 24-hour inflow of 50,620 cubic feet per 
second occurred on Dec. 3, 1982. On Sep. 30, 1983, the 
pool elevation was 534.25 feet above NGVD and storage 
in the power pool was 115,600 feet. 
Condition as of Sep. 30. Project was started in May 
1947 and was completed for beneficial use in May 
1950. The third power generating unit was completed 
in January 1970. Installation of remote control 
equipment was completed in June 1972. Power 
generation, operation, and maintenance are continuing. 
Remote control equipment has been installed 
for operation of the power plant from Blakely Mt. 
Dam-Lake Ouachita. 
22. OUACHITA RIVER LEVEES, LA 
Location. East bank of Ouachita River between 
Bastrop, LA, and Sandy Bayou. Loop levees on the west 
bank at West Monroe, Columbia, and Bawcomville. 
Existing project. There are 105.9 miles of levee on 
the east bank and 11.6 miles of levee in the three loops on 
the west bank. A letter report, approved by the Chief of 
Engineers, authorized gravel surfacing 37.8 miles of 
levee, enlargement of 40.4 miles of levee, and a 5.7-mile 
southward extension of the east bank levee. Approved 
(1979) estimated Federal cost is $9,400,000. Estimated 
non-Federal cost is $25,000. 
Local cooperation. Requirements and assurances of 
local cooperation are fully described on page 12-6 of FY 
80 Annual Report. 
Condition as of Sep. 30. Completion of the authorized 
work would not correct all project deficiencies. Enlargement 
of the Bawcomville levee, enlargement of the 
east bank levee above Monroe, and replacement of 
numerous drainage structures are not authorized. 
Therefore the construction of the present Ouachita 
River levee project has been deferred. A complete study 
of the Ouachita River levee system is being accomplished 
as an interim study of the ongoing comprehensive 
Ouachita River Basin study. Item I of the 
Monroe to Sandy Bayou Levee enlargement project was 
completed Jul. 7, 1978; additional work is being 
deferred. 
23. OUACHITA RIVER AND 
TRIBUTARIES, AR AND LA 
Location. Improvements comprising comprehensive 
projects are on main stem Ouachita River, AR and LA, 
on its tributaries, Caddo and Little Missouri Rivers, and 
in Pine Bluff, AR. Description of Ouachita River Basin 
is presented in greater detail on page 690 of Annual 
Report for 1962. 
Existing project. The authorized general plan for 
flood control and other purposes in the Ouachita River 
Basin includes the projects listed in Table 12-F. The 
1966 Flood Control Act modified the Bayou Bartholomew 
and Tributaries, AR and LA, project to 
include ten water-retention lakes in the western 
tributaries of Bayou Bartholomew in Arkansas and six 
local levee units along the main stem of the bayou in 
Louisiana. 
Local cooperation. Fully complied with for completed 
features of comprehensive project. (See individual 
statements for further details.) 
Operations and results during fiscal year. 
Operations for Blakely Mt. Dam-Lake Ouachita, 
DeGray Lake, Narrows Dam-Lake Greeson, Bayou 
Bartholomew and Tributaries, Monroe Floodwall, and 
Ouachita River Levees are shown in individual reports 
herein. 
Condition as of Sep. 30. Pertinent data on those 
features which are complete or not started are in Table 
12-F. Conditions of Blakely Mt. Dam-Lake Ouachita, 
DeGray Lake, and Narrows Dam-Lake Greeson are 
given in the individual reports. 
An overall basin study including interim studies of 
the Monroe-West Monroe area, the Ouachita River 
Levees, the Arkansas Lakes, and extension of navigation 
to Arkadelphia is ongoing. 
24. PORTER BAYOU, MS 
Location. Porter Bayou is located in Bolivar and 
Sunflower Counties, MS. It lies approximately 25 miles 
east of the Mississippi River, is approximately 5 miles 
south of Cleveland, MS, and travels through the town of 
Shaw, MS. 
Existing project. The plan of improvement calls for 
selective snagging and clearing of Porter Bayou from 
mile 12.5 to mile 32.3. This plan provides a 0.5-year 
frequency protection for the Porter Bayou area. All 
construction is being performed from one side of the 
stream, leaving the other side undisturbed. The total 
estimated Federal cost of the project is $1,214,000. 
Local cooperation. Fully complied with. 
Condition as of Sep. 30. A construction contract 
was awarded Sep. 22, 1982. As of Sep. 30, the contract 
was 45 percent complete. Construction is scheduled for 
completion in May 1984. 
12-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
25. RED RIVER BELOW DENISON 
DAM (VICKSBURG DISTRICT) 
Location. On Red River and its tributaries below 
Denison Dam, in Oklahoma, Arkansas, Texas, and 
Louisiana. (Refer to Geological Survey State maps and 
folio "Maps of Red River"-1958 edition.) 
Existing project. Flood Control Act of 1946 approved 
general plan for flood control on Red River below 
Denison Dam, TX and OK, which provides for construction 
of six flood control reservoirs in combination 
with existing or authorized Federal and non-Federal 
levee improvements, modified as required, and channel 
stabilization at locations where levee setbacks are 
impossible or uneconomical. This act further authorized 
incorporation of several separate existing projects for 
flood damage prevention along Red River below Denison, 
above jurisdiction of the MRC, into this project. By 
Public Law 780, 83d Cong., 2d sess., as amended by 
Public Law 218, 84th Cong. 1st sess., and Public Law 
645, 86th Cong., 1st sess., plan of improvement was 
amended to include additional projects as indicated in 
following lists of reservoirs and local protection works 
considered in general flood control plan for the Red 
River below Denison Dam, and existing flood control 
projects incorporated into project in Vicksburg District. 
(See Table 12-H for new projects and Table 12-I 
for incorporated projects.) 
Local cooperation. See individual reports herein. 
26. RED RIVER BELOW DENISON 
DAM, LEVEES AND BANK 
STABILIZATION 
(VICKSBURG DISTRICT) 
Location. Along the main stem of the Red River 
from the head of the levee system immediately above 
Index, AR, through the southwest corner of Arkansas 
to the vicinity of Boyce, LA, on the right bank, and 
Pineville, LA, on the left bank. 
Existing project. Raising and strengthening existing 
and authorized Red River levees to provide protection 
against flooding and bank protection works at 
locations where levee setbacks are impossible or uneconomical. 
The plan consists of raising and strengthening 
existing and authorized Red River levees to provide 
against a flood approximately 20 percent greater than 
the flood of 1945, the flood of record, as modified by 
authorized reservoirs. Bank protection works are to be 
constructed at locations where levee setbacks are 
impossible or uneconomical. Estimated cost for new 
work (October 1983) is $59,000,000 Federal and 
$1,560,000 non-Federal. 
Local cooperation. Local interests must furnish 
lands, easements, rights-of-way, and spoil disposal areas 
necessary for construction; hold and save the United 
States free from damages; and maintain and operate 
works after completion. Local interests have been 
prompt in furnishing levee rights-of-way upon request, 
except for the following three items of low priority: 
McKinney Bayou Drainage District, enlargement of 
approximately 4 miles of intermittently low levee; 
Garland Levee District, enlargement of approximately 
1.3 miles of levee; and Red River Levee District No. 1, 
enlargement of approximately 4.3 miles of levee. The 
local agencies are convinced that the flow line lowering 
produced by completed reservoirs has made this work 
unnecessary. 
Assuring Agencies: Red River Levee and Drainage 
District, North Bossier Levee District, Red River Water 
Commission, Bossier Levee District, Caddo Levee 
District, Cane River Levee and Drainage District, 
Garland Levee District, Hempstead County Levee 
District No. 1, Miller County Levee District No. 2, Red 
River Levee District No. 1, Nineteenth Louisiana Levee 
District, and Long Prairie Levee District. All basic 
assurances received. Supplemental assurances covering 
Public Law 91-646 have been received from all agencies 
except the North Bossier Levee District. 
Operations and results during fiscal year. Hired 
labor forces continued investigations, surveys, and 
preparation of plans and specifications. 
Bank stabilization was completed at First Old River 
Lake, AR, mile 393-R on Apr. 29, 1983, and Tobe, AR, 
mile 408-R on May 3, 1983. One construction contract 
at Lucas Bend, LA, mile 266-R, was awarded Sep. 29, 
1983, but construction was not initiated. 
Condition as of Sep. 30. Construction was initiated 
in February 1948 and the levees are complete and 
bank stabilization is 85 percent complete. 
27. RED RIVER WATERWAYSHREVEPORT, 
LA, TO INDEX, AR 
Location. In northwest Louisiana, southwest Arkansas, 
and northeast Texas, along the Red River between 
Shreveport, LA, and Index, AR. 
Existing project. To provide for realining the 
channels of Red River from Shreveport, LA, to the 
levee system near Index, AR, by means of dredging, 
cutoffs, and training works and for stabilizing its 
banks by means of revetments, dikes, and other methods. 
Facilities to provide opportunities for recreation and 
for fish and wildlife development are an integral part 
of the project. Estimated cost for new work (October 
1982) is $186,000,000 Federal and $24,000,000 non- 
Federal, including $2,780,000 contributed funds. 
Local cooperation. Provide prior to construction 
and without cost to the United States all lands, easements, 
and rights-of-way necessary for construction 
and subsequent maintenance of the project, including 
suitable areas determined by the Chief of Engineers to 
be required in the general public interest for disposal 
of spoil, and provide necessary retaining dikes, bulkheads, 
and embankments, therefor, or the cost of such 
retaining works and also including all additional lands, 
or rights in land, required to insure public control of 
the recreational development; and hold and save the 
United States free from damages due to the construction 
12-10

VICKSBURG, MS, DISTRICT 
and subsequent maintenance of the project, maintain 
all the project works upstream of the navigation 
improvement at Shreveport, LA, after completion in 
accordance with regulations prescribed by the Secretary 
of the Army. 
Provide without cost to the United States all relocations 
of utilities, bridges (except railroads), sewers, 
pipelines, and any other alterations of existing improvements 
which may be required for construction of the 
project; where the appraised value of the land provided 
for recreation development amounts to less than 50 
percent of the total first cost of recreational development, 
make additional contributions sufficient to bring 
the non-Federal share to at least that level; which 
additional contribution may consist of the actual cost of 
carrying out an agreed-upon portion of the development, 
or a cash contribution, or a combination of both; operate 
and maintain for the life of the Federal project the 
recreational areas and all facilities installed pursuant 
to the agreement, except that facilities which are 
integral parts of a structure operated and maintained 
by the Federal Government shall be operated and 
maintained under whatever cost-sharing arrangement 
applies to the operation and maintenance of the basic 
structure; and assure access to recreational developments 
to all on equal terms. 
appropriated $750,000 in the 1977 session to be held as 
a trust fund for payment of local cost sharing on this 
project. Further, they anticipated that additional 
funding will be added in future years to enable them to 
have on hand the required funds at the time construction 
begins. 
Texas: On Dec. 17, 1969, the Governor of Texas 
furnished a statement of willingness to provide local 
cooperation for bank stabilization. A meeting was held 
in Austin, TX, on Mar. 1, 1977, concerning sponsors of 
the Texas portion of the project. The purpose of the 
meeting was to discuss the status of the waterway 
project and the type of organization needed to accomplish 
project assurances, the powers required by such 
an organization may be established. The Texas Water 
Development Board (TWDB) stated that they would 
take the lead in obtaining an organization with the 
ability to provide the local cooperation requirements. 
In the third quarter of 1980 the State of Texas moved 
closer to achieving that goal by action taken by the 
three Texas counties of Bowie, Lamar, and Red River, 
who have petitioned the State to enact legislation 
permitting them to join the Red River Authority of 
Texas. By this action, the Red River Authority of Texas 
will become legally empowered to act as sponsor for the 
Waterway. 
Local interests are required to comply with the Terminal facilities. Adequate facilities are to be 
provisions of the Uniform Relocation Assistance and provided and maintained by local interests. 
Real Property Acquisition Policies Act of 1970 (Public 
Law 91-646) and with the provisions of Sec. 221 of the Operations and results during fiscal year. Ad- 
Flood "Control" Act of 1970 (Public Law 91-611), in vanced engineering and design work was accomplished 
acquiring real property. by hired labor forces. Preparation of Phase 1 of the 
GDM is approximately 52 percent complete. 
Section 187 of the Water Resources Development Act 
of 1976 (Public Law 94-587) modifies the requirement Condition as of Sep. 30. Construction has not been 
of local cooperation to provide that non-Federal interests initiated. 
shall contribute 25 percent of the construction costs of 
retaining dikes, bulkheads, and embankments required 
for initial and subsequent disposal of dredged material. 2288.. WALLACE LLAAKKEE,, LLAA 
Assuring Agencies: Louisiana: Formal assurances Location. In Red River Basin on Cypress Bayou, 
for the project in Louisiana were executed by the Red Caddo and Soto Parish sLA, 66mm es abo moyu th 
aRcicveepr teWd aotne rwbeahya lCf oomf mthises iUonn itoend FSetba.t e2s 6o, n1 9A6p9r, . a1n5d, oBCaaudPdiroe annddb tD1e4 mSolstoo thPsatroishes, LA, 66 miles above mouth 
Shreveport, LA. (Refer to Geological Survey map, scale 
1969. Amended assurances covering the provisions of , . (Refer y mapsc 
Public Law 91-646 and Public Law 91-611 were 1:500,000.) 
executed by the commission on May 23, 1973, and Existing project. An earth-fill dam 4,940 feet long 
accepted on behalf of the United States on Nov. 14, at top, including 644 feet of spillway and outlet works, 
e1x9p7r3e. sTshlye Red River Waterway Commission was formed rising 48 feet above streambed, with a reservoir pro- to provide the local cooperation for the project viding storage of 96,100 acre-feet, including a conserand 
has an adequate tax base to fulfill its objectives. vation pool of 7,800 acre-feet. Outlet works and uncon- 
Arkansas: On Oct. 16, 1969, the Arkansas Soil and 
Water Conservation Commission furnished a statement 
of willingness to provide local cooperation on the proposed 
plan. In July 1976, the Soil and Water Resources 
Division of the Arkansas Department of Commerce 
stated that they would approach the Arkansas Legislature 
to obtain funds on a recurring yearly basis 
sufficient to insure its portion of the project funds by 
start of construction in Arkansas. By letter dated Jun. 
20, 1977, the Director of the Soil and Water Resources 
Division advised that the Arkansas General Assembly 
trolled spillway are centered about 1,250 feet north of 
south abutment. Reservoir controls 260 square miles, 
or about 20 percent of total drainage area of Bayou 
Pierre, Cypress Bayou, and tributaries combined, and 
affords protection against floods for an area of about 
90,000 acres of valley below dam. Cost for new work 
completed in 1946 was $1,219,371, including $17,164 
for Code 711. 
Local cooperation. Fully complied with. For details 
see page 1024, Annual Report Fiscal Year 1946. 
12-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Operations and results during fiscal year. Hired 
labor work consisted of condition and operation studies, 
stream gaging, and operation and maintenance of the 
dam as required. Maximum pool elevation in the lake 
was 151.3 feet NGVD on Feb. 11, 1983, when storage in 
the flood control pool was 45,900 acre feet. On Sep. 30, 
1983, the pool elevation was 142.1 feet NGVD and 
storage in the flood control pool was 0 acre feet. (See 
Table 12-G for reservoir operations.) 
Condition as of Sep. 30. All construction work on 
project was completed in December 1946. 
Main portion of dam was constructed during Fiscal 
Year 1943; stabilization of railroad embankment was 
accomplished from June to November 1946; and placing 
of fill in closure section of dam was accomplished from 
November to December 1946. Recreational facilities at 
the lake were closed in May 1972. 
29. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Inspection of completed work was accomplished at a 
cost of $112,632 for the fiscal year. Total cost as of Sep. 
30, 1983 is $1,135,780. 
30. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Emergency flood control activities-repair, flood 
fighting, and rescue work. (Public Law 99, 84th 
Cong., and antecedent legislation.) 
Disaster preparedness, FY costs for the period were 
$148,171. 
Emergency operations, total expenditures during 
FY 83 were $2,213,137 which involved flooding in 
Ouachita, Yazoo and Red River Basins in December 
1982 - March 1983; Pearl River Basin, April 1983; and 
Mississippi River Basin, May-June 1983. 
Rehabilitation, total expenditures during FY 83: 
Red River, mile 123.0L, Upper Urania, $35,790; Red 
River, mile 232.0R, Robinson Place, $28,660; Ascalmore 
Creek, $27,900. 
Advance measures, total expenditures in FY 83: Red 
River, mile 211.0R, $9,786; Ouachita River, Rilla, LA, 
$10,000; Ouachita River Columbia, LA, $9,197; 
Palusha/Jennings Bayou, Greenwood, MS, $139,100; 
Red River Below Denison Dam Levee Setback, $493. 
Total Public Law 99 costs through Sep. 30, 1983, 
were $2,622,234. 
Snagging and clearing of navigable streams and 
tributaries in the interest of flood control (Sec. 208 
of 1954 Flood Control Act, Public Law 780,83d 
Cong.). 
No activity during the period. 
Emergency bank protection (Sec. 14 of 1956 
Flood Control Act, Public Law 780.83d Cong.). 
No activity during the period. 
Flood control activities pursuant to Sec. 205, 
Public Law 858, 80th Cong., as amended 
(preauthorization).. 
During FY 1983, reconnaissance studies were 
completed on West Sterlington, LA, at a cost of $3,900; 
Chatman Creek and Industrial Area, Malvern, AR, at 
a cost of $7,500; and Town Creek, Malvern, AR, at a 
cost of $7,500. 
Detailed studies on Little Mound Bayou, Bolivar 
County, MS, at a cost of $86,986; Canal 43, Desha and 
Lincoln Counties, AR, at a cost of $72,598 and Pearl- 
Flowood Area, MS (Expanded Recon), at a cost of 
$59,223. 
Detailed studies were terminated on: (1) Dowling 
Bayou, Humphreys and Sharkey Counties, MS, in Feb. 
83. Expenditures for FY 83 were $241. (2) New Albany, 
MS, in Aug. 83. Expenditures for FY 83 were 
$42,132. 
Construction continued on Lead Bayou, MS, FY83 
expenditure of $685,325; and Porter Bayou, MS, FY 83 
expenditure of $506,187. 
12-12

VICKSBURG, MS, DISTRICT 
TABLE 12-A COST AND FINANCIAL STATEMENT 
See 
Section Total Funds to 
in Text Project Funding FY 80 FY 81 FY 82 FY 83 Sep. 30, 1983 
1. Claiborne 
County Port, MS 
2. Lake Providence 
Harbor, LA 
3. Madison Parish 
Port, LA 
4. Ouachita and Black 
Rivers below Camden, 
AR (6.5-foot 
navigation project) 
Ouachita and Black 
Rivers below Camden, 
AR (9-foot 
navigation project) 
5. Overton-Red River 
Waterway, LA 
6. Pearl River 
MS 
7. Red River 
Emergency Bank 
Protection 
(Contrib. Funds) 
8. Red River 
Waterway- 
Mississippi 
River to Shreveport, 
LA 
(Contrib. Funds) 
9. Rosedale Harbor, 
MS 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
$ 100,000 
122,558 
163,600 
65,190 
520,000 
478,276 
250,000 
17,900 
$ 30,000 
39,730 
268,800 
154,377 
-24,000 
36,372 
250,000 
208,977 
480,000 $1,305,000 
33,297 1,717,787 
160,000 
252,518 
-29,000 
66,247 
-111,000 
-10,579 
-129,000 
44,500 
19,900,000 19,200,000 18,211,000 20,406,000 
17,157,320 21,665,779 13,939,425 13,638,600 
3,494,400 3,362,700 2,849,000 4,232,756 
3,110,838 3,217,854 3,211,608 4,035,654 
-350,500 
161,000 
182,196 
00 
587,000 
209,676 
3,362,000 
2,942,895 
325 
325 
60,736,000 
58,456,160 
216,720 
217,943 
90,200 
545,000 
510,042 
164,273 
103,139 
296,900 
164,589 
97,000 
101,815 
78,000 
212,185 
12-13 
$ 2,000,000 
1,965,130 
208,537' 
208,5371 
1,620,500 
1,600,591 
656,000 
655,999 
342,000 
337,624 
5,248,6192 
5,248,6192 
193,824,000 
181,914,847 
56,315,163 
55,751,380
0 
-350,500b 
748,000$ 
341,872 
3,362,0006 
2,942,895 
6,825 
6,825 
60,736,000? 
58,456,160? 
545,0007 
510,0427 
647,7347 
586,6007 
2,000,000 
2,000,000 
962,100 
878,362

TABLE 12-A 
(Continued) 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
COST AND FINANCIAL STATEMENT 
See 
Section Total Funds to 
in Text Project Funding FY 80 FY 81 FY 82 FY 83 Sep. 30, 1988 
10. Yazoo River, MS New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
164,000 
317,050 
54,500 
52,996 
2,760,000 
3,073,265 
34,000 
32,967 
3,900,000 
4,000,402 
50,000 
26,624 
12. Bayou Bartholomew New Work 
and Tributaries Approp. 
AK and LA Cost 
13. Bayou Bodcau 
and tributaries, 
AR & LA 
14. Bayou Bodcau 
Reservoir, LA 
15. Bayou Pierre, LA 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
16. Blakely Mt. Dam- New Work 
Lake Ouachita, Oua- Approp. 
chita River, AK Cost 
Maint. 
Approp. 
Cost 
Code 713 Funds New Work 
Approp. 
Cost 
17. Caddo Lake, 
LA 
18. DeGray Lake 
Caddo River, AK 
19. Lead Bayou, 
MS 
20. Monroe Floodwall, 
LA 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
21. Narrows Dam-Lake New Work 
Greeson, Little Mis- Approp. 
souri River, AK Cost 
Maint. 
Approp. 
Cost 
231,000 
11,815 
19,400 
13,434 
186,919 
3,983,000 
3,231,158 
7,920 
835,000 
1,164,447 
2,506,400 
2,470,062 
75,000 
21,076 
10,272 
76,029 
1,941,300 
1,813,572 
145,000 
49,017 
2,828,000 
3,806,951 
1,725 
25,256 
87,524 
2,210,000 
2,316,783 
870,000 
890,722 
2,958,000 
3,188,349 
470 
1,798 
321,800 
56,955 
2,254,000 
2,351,889 
- 1,000,000 
56,083 436,009 
145,000 
32,741 
2,128,000 
2,145,519 
625,000 
579,042 
1,660,000 
1,986,615 
12-14 
916,000 
465,295 
48,000 
7,700 
489,000 
982 
9,589,6614 
9,121,3734 
1,194,315 
1,128,102 
974,000 
974,000 
489,000? 
9827
00 
883,3007 
416,1157
00 
49,4007 
27,6917 
34,044,944 
34,023,715 
33,990,092 
33,852,673 
474,095 
474,046
0
0 
454,0007 
231,4377 
72,033,992 
72,033,992 
20,080,683 
19,823,504 
1,594,685 
1,353,613 
2,560,500 
2,560,500 
16,533,229 
16,516,486 
24,657,437 
24,457,446 
652,300 
404,300 
30,000 
14,257 
105,484 
3,309,000 
3,290,852 
132,200 
231,437 
12,611 
2,608,000 
2,457,043 
358,000 
685,325 
147,786 
2,433,700 
2,284,608

VICKSBURG, MS, DISTRICT 
TABLE 12-A 
(Continued) 
COST AND FINANCIAL STATEMENT 
See 
Section Total Funds to 
in Text Project Funding FY 80 FY 81 FY 82 FY 83 Sep. 30,1983 
Code 713 Funds New Work 
Approp. - -1,725 -470 - 331,505 
Cost 77,783 - - - 308,088 
22. Ouachita River New Work 
Levees, LA Approp. - - 54,000 -6,000 2,682,000 
Cost 999 - - 48,000 2,682,000 
24. Porter Bayou, New Work 
MS Approp. 30,000 - 355,000 500,000 1,050,278 
Cost 20,479 19,808 52,273 506,187 758,503 
26. Red River below New Work 
Denison Dam, Approp. - - 5,110,700 550,000 5,660,700' 
Levees and Bank Cost - - - 1,505,639 1,505,6397 
Stabilization 
27. Red River Water- New Work 
way, Shreveport Approp. - - - -0' 
LA, to Index, Al Cost - - - 4,335 4,3357 
28. Wallace Lake, LA New Work 
Approp. - - - - 0' 
Cost - - - - O' 
Maint. 
Approp. - - 22,200 142,300 164,500' 
Cost - - - 44,113 44,113' 
1. Actual costs include $198 859 Public Works Acceleration 
Act funds and $9,678 expended for planning and design; 
excludes $35,000 contributed funds, $198,400 cost of retaininmg 
dikes, and $1,022,000 local interests' costs for port facilities. 
2. Includes $674,068 for new work on previous projects. 
3. Excludes $21,884 carryover from Mobile District. 
4. Includes $359,661 for previous projects. Present 
propriations include funds for Advance Participation on 
elzoni Bridge. 
5. $350,500 cost credit from Memphis on New Orleans 
District expenditures. 
6. Includes $3,312,000 PL 98-8 Jobs Bill. Excludes 
$47,828 000 previously allocated to New Orleans District. 
7. Excludes New Orleans District allocation and cost. 
12-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 12-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Jul. 14, 1960, as 
amended 
Jul. 14, 1960, as 
amended 
Jul. 14, 1960, as 
amended 
May 17, 1950 
Jul. 14, 1960 
Dec. 31, 1970 
Jul. 24, 1946 
May 17, 1950 
Aug. 13, 1968 
June 14, 1880 
Apr. 21, 1900 
Aug. 30, 1935 
Nov. 7,1966 
Jun. 13, 1983 
Jul. 20, 1983 
Aug. 13, 1968 
CLAIBORNE COUNTY PORT, MS (See Section 1 of Text) 
A dredged slack-water harbor 800 feet long and 150 feet wide 
with a 400 by 800 foot turning basin. 
LAKE PROVIDENCE HARBOR, LA (See Section 2 of Text) 
Dredging 0.7-mile channel and turning basin in an old chute of 
the Mississippi River, with the dredged material used to fill in a 
port area provided by local interests. 
MADISON PARISH PORT, LA (See Section 3 of Text) 
The project consists of constructing a navigation channel 150 feet 
wide and 1,000 feet long, transitioning into a 200-foot-wide 
channel 400 feet long with a 350-by 1,100-foot turning basin 
adjacent to the port area. Dredged material will be disposed into 
lands furnished by local interests. 
OUACHITA AND BLACK RIVERS BELOW CAMDEN, 
AR (See Section 4 of Text) 
Modification of existing project toprovide for 9-foot channel and 
deepening canal to Felsenthal, AR. 
Modification of 9-foot project to provide four new locks and dams 
and channel improvements. 
Migratory waterfowl refuges on Bayou D'Arbonne in connection 
with the pool of the Columbia Lock and Dam and in the pool of 
the Felsenthal Lock and Dam. 
OVERTON-RED RIVER WATERWAY, LA (See Sec. 5 of 
Text) 
Construct 9-by 100-foot channel for 206 miles from Mississippi 
River, mile 301 AHP, through Old and Red Rivers to mile 31, 
thence by lateral canal through land cuts and existing 
waterways across Mississippi-Red River backwater area along 
south bank of Red River floodplain to Shreveport, and construct 
nine locks and pumping plant on Red River near Shreveport. 
Extend Overton-Red River Waterway 9- by 100-foot channel 
from Mississippi River to north bank of Black River, mile 35.5. 
Provides for the navigation channel to be 200 feet wide. 
PEARL RIVER, MS AND LA (See Section 6 of Text) 
Provided for a 5-foot channel. 
Legalized construction of a fixed highway bridge at Rockport 
A channel from the mouth of West Pearl River for 58 miles to the 
mouth of Bogalusa Creek at Bogalusa, LA, 7 feet deep at low 
water with a bottom width of 100 feet in the river sections and 80 
feet in the canal section; with locks 65 by 310 feet clear inside 
dimensions. 
Construction of cut-offs and easement of critical bends at eight 
locations below lock 1 with no increase in project depth. 
Accomplish the 4-PT plan improvements on the Pearl River in 
the vicinity of Jackson, MS. 
Design and construct protection to prevent flooding along the 
Pearl River in the vicinity of Jackson, MS. 
RED RIVER EMERGENCY BANK PROTECTION (See Sec. 
7 of Text) 
Realining the banks by dredging cut-offs and training works and 
stabilizing banks by means of revetments and dikes. 
Approved Sep. 11, 1978, 
under authority of Sec. 107 
of the River and Harbor 
Act of 1960, as amended 
Approved Sep. 12, 1962, 
under authority of Sec. 107 
of the River and Harbor 
Act of 1960, as amended 
Approved Sep. 12, 1962, 
under authority of Sec. 107 
of the River and Harbor 
Act of 1960, as amended 
S. Doc. 117, 81st Cong., 1st 
sess. 
S. Doc. 112, 86th Cong., 2d 
sess. 
Report of the Chief of 
Engineers dated Nov. 25, 
1970, and H. Doc. 92-109, 
92d Cong., 1st sess. 
H. Doc. 320, 80th Cong., 1st 
sess. 
S. Doc. 117, 81st Cong., 1st 
sess. 
H. Doc. 304, 90th Cong., 2d 
sess.l 
H. Doc. 98, 45th Cong., 3d 
Sess. 
H. Doc. 145, 65th Cong., 1st 
Sess. 
H. Doc. 408, 75th Cong., 2d 
seas. 
H. Doc. 482, 89th Cong., 2d 
sess. 
S. Doc. 153, 98th Cong., 1st 
sess. 
H. Doc. 5363, 98th Cong., 1st 
sess. 
H. Doc. 304, 90th Cong., 2d 
sess. 
12-16

VICKSBURG, MS, DISTRICT 
TABLE 12-B 
(Continued) 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Aug. 13, 1968 
Jul. 14, 1960, as 
amended 
Mar. 3, 1875 
Aug. 13, 1968 
May 17, 1950 
Nov. 7, 1966 
Oct. 27, 1965 
Jun. 28, 1938 
Jun. 22, 1936 
Oct. 27, 1965 
Jun. 30, 1948, as 
amended 
RED RIVER WATERWAY-MISSISSIPPI RIVER TO 
SHREVEPORT, LA (See Sec. 8 of Text) 
Develop a 9 by 200 feet, approximately 210 miles long from 
Mississippi River at junction of Old River via Old River and Red 
River to Shreveport, LA, consisting of realinement, bank 
stabilization, and construction five locks and dams. 
ROSEDALE HARBOR, MISS. (See Section 9 of Text) 
The harbor channel is 150 feet wide and 2.7 miles long with a 
turning basin 1,000 feet long and 400 feet wide. A minimum 
operatinmg depth of 9 feet below the lowest water of record (102.5 
feet, NGVD) was maintained in both the channel and turning 
basin and provided a 20-acre landfill to a net elevation of 162.9, 
NGVD. The landfill is 1,250 feet long and 700 feet wide. An 
access roadfill was constructed from Mississippi Highway 1 to 
the port site. 
YAZOO RIVER, MS (See Section 10 of Text) 
Removal of obstructions to navigation from mouth to Greenwood, 
MS, 189 miles. 
Nine-foot channel from mouth to Greenwood, mile 154.9 (present 
mileage), with a lock and dam near Vicksburg, channel 
improvements, alteration of bridges, additional storage space in 
Sardis Lake to augment low river flows, and recreation features. 
BAYOU BARTHOLOMEW, AR AND LA (See Section 12 of 
Text) 
Authorized channel improvements on Bayou and Tributaries (see 
above). 
Modified 1950 authorization to include 10 lakes in the west 
escarpment in Arkansas and 6 local levees in Louisiana, and 
acquisition of lands for mitigation of fish and wildlife losses. The 
previously authorized channel improvement was deferred until 
it is determined that the quality and quantity of water 
downstream will not be adversely affected. 
BAYOU BODCAU AND TRIBUTARIES, AR AND LA (See 
Sec. 13 of Text) 
Extend Cypress Bayou-Red Chute Bayou levee, construct stream 
closure landside drainage channel and three culverts on Red 
Chute Bayou, and clearing and snagging channel; extend Flat 
River-Loggy Bayou levee, close Flat River near junction with 
Cutoff Bayou, and construct control structures on Flat River 
near junction with Red Chute Bayou; and enlarge Flat River 
channel to 20 to 35 feet, a distance of 11.6 miles. 
BAYOU BODCAU RESERVOIR, LA (See Sec. 14 of Text) 
Provides for construction of a reservoir and other flood control 
works. 
BAYOU PIERRE, LA (See Sec. 15 of Text) 
Widening channel at intervals totaling 12.9 miles, and snagging 
of 29.7 miles. 
CADDO LAKE, LA (See Sec. 17 of Text) 
Maintenance Work. 
LEAD BAYOU, MS (See Section 19 of Text) 
Channel enlargement. 
12-17 
H. Doc. 304, 90th Cong., 2d 
sess. 
Approved Sep. 12, 1962, 
under authority of Sec. 107 
of the River and Harbor 
Act of 1960, as amended. 
H. Doc. 342, 90th Cong., 2d 
sess. 
S. Doc. 117, 81st Cong., 1st 
sess. 
H. Doc. 506, 89th Cong., 2d 
sess. 
H. Doc. 203, 89th Cong., 1st 
sess. 
H. Doc. 378, 74th Cong., 2d 
sess. 
H. Doc. 378, 74th Cong., 2d 
sess. 
S. Doc 39, 89th Cong., 1st 
sess. 
Sec. 205 of the Flood Control 
Act of 1948, as amended. 
Authorized by Chief of 
Engineers Jun. 10, 1980.

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 12-B 
(Continued) 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
May 17,1950 
Oct. 27, 1965 
Nov. 7,1966 
May 17,1950 
Jun. 80, 1948, as 
amended 
Jul. 24,1946 
Aug. 18,1968 
Aug. 13, 1968 
Jun. 22,1986 
MONROE FLOODWALL, LA (See Section 20 of Text) 
Partial closure of gap in floodwall. 
Closure of gap in floodwall (Plan C). 
Closure of gap in floodwall (Plan B). 
OUACHITA RIVER AND TRIBUTARIES, AR AND LA 
(See Section 23 of Text) 
Authorized DeGray Lake; Murfreesboro Lake; extension of 
floodwall at Monroe to partially close the existing gap; local 
protection at Bawcomville, LA (subsequently constructed under 
Sec. 6, Act of May 15 1928, with local interests contributing one 
third of cost); Bayou bartholomew channel improvement, 
including Deep Bayou and Overflow Creek; Pine Bluff local 
ipnrtoot ethctei oOnu; alochcaitla p rotection at Calion, AR; and incorporation, River and Tributaries project, of all existing 
projects and portions thereof in the basin above the lower end of 
the levees on the east bank of the Ouachita River. In addition, 
the Chief of Engineers authorized on Nov. 14, 1966, additional 
work on the levees. 
PORTER BAYOU, MS (See Section 24 of Text) 
Selective snagging and clearing of Porter Bayou, MS from mile 
12.5 to mile 32.3. 
RED RIVER BELOW DENISON DAM LEVEES AND 
BANK STABILIZATION (VICKSBURG DIST.) (See Sec. 
26 of Text) 
Levee and bank stabilization. 
Deauthorization of Morringsport Dam and Reservoir on Cypress 
Creek; realining and stabiizing the banks of the Red River; and 
recreational facilities from thelMississippi River to Denison 
Dam, OK and TX. 
RED RIVER WATERWAY-SHREVEPORT, LA, TO 
INDEX, AR (See Sec. 27 of Text) 
Provides for realinement of the channels of the Red River from 
Shreveport, LA, to Index, AR. 
WALLACE LAKE, LA (See See. 28 of Text) 
Construction of an earth-fill dam and a reservoir. 
S. Doc. 117, 81st Cong., 2d 
sess. 
H. Doc. 328, 88th Cong., 2d 
sess. 
H. Doc. 328, 88th Cong., 2d 
sess. 
S. Doc. 117, 81st Cong., 1st 
sess. 
Sec. 205 of the Flood Control 
Act of 1948, as amended. 
Authorized by Chief of 
Engineers, Feb. 18, 1982. 
H. Doc. 602, 79th Cong., 2d 
sess. 
H. Doc. 304, 90th Cong., 2d 
sess. 
H. Doc. 304, 90th Cong., 2d 
sess. 
H. Doc. 378, 74th Cong. 2d 
sess. 
1. Portion of existing project above mile 31 was reclassified 
to inactive status as approved by Office, Chief of 
Engineers, letter dated Oct. 18, 1971. 
12-18

TABLE 12-C OUACHITA AND BLACK RIVERS, AR AND LA 
(9-FOOT PROJECT), LOCKS AND DAMS 
(See Section 4 of Text) 
Min. 
Depth 
Greatest on 
Available Lower 
Miles Length Max. Elev. Miter 
Above Width for Full Lift Normal Sill at 
Miles Mouth of Width at Pool Normal Perfrom 
of Lock of Lock Low Surface Pool Character cent 
Nearest Black Chamber Chamber Water (feet Level or Kind of Type of Com- Estimated 
Location Town River (feet) (feet) (feet) msl) (feet) Foundation Dam Construction plete Cost 
Jonesville, LA 10 25 84 600 30 34 14 Piling Movable Tainter gated dam; 80 $ 50,700,000" 
bascule gated 
navigation pass; 
steel mitering lock 
gates 
Columbia, LA 5 117 84 600 18 52 13 do do Tainter gated dam; 70 44,200,000 
fixed crest 
navigation pass; 
steel mitering lock 
gates 
Felsenthal, 1 227 84 600 18 702 13 Earth do Tainter gated dam; 71 90,900,00 
AR navigation pass 
with inflatable 
dam on crest; steel 
mitering lock 
gates 
Calion, AR 7 283 84 600 12 77 13 do do Tainter gated dam; 678 67,200,000 
hinged crest gated 
navigation pass; 
steel mitering lock 
gates 
Total $253,000,000 
1. Includes $6,113,700 for Catahoula Lake diversion 
channel and control structure. 
2. Fish and wildlife impoundment level. 
3. The percent complete last shown reflects only Lock 
and Dam construction. The new percent complete reflects all 
work within the pool. This now corresponds to estimated 
costs. 
4. The decrease in estimated costs from that last shown 
reflects full funding price leveling and some reductions 
based on actual contract awards.

TABLE 12-D 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
LOCKS IN PEARL RIVER PROJECT 
(See Section 6 of Text) 
Lock 
Miles above mouth 
Nearest town 
Miles to nearest town 
Width of Chamber 
.Greatest length available 
for full width (feet) 
Lift (feet) 
Depth over sills at low 
water (feet) 
Character of foundation 
Type of construction 
Year completed 
Date opened for navigation 
Actual cost of lock 
Pearl River Lock No. 1 
29.7 
Pearl River, LA 
65 
310 
26.7 
10 
Sand, gravel, silt, clay 
Concrete and steel 
1949 
November 1968 
$2,119,100 
Pearl River Lock No. 2 
40.8 
Bush, LA 
3
65 
310 
14 
10 
Sand, gravel, silt, clay 
Concrete and steel 
1950 
November 1958 
$1,967,537 
Pearl River Lock No. 3 
44.0 
Sun, LA 
2
65 
310 
11 
10 
Sand, gravel, silt, clay 
Concrete and steel 
1950 
November 1958 
$1,497,539 
Note: The responsibility of maintaining this project was 
transferred to the Vicksburg District, Lower Mississippi 
Valley Division on Oct. 1, 1981. District boundaries 
have been changed. 
12-20 
_

VICKSBURG, MS, DISTRICT 
TABLE 12-E OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to Sep. 1983 
Full Report Operation 
See Annual and Mo. and Yr. 
Project Status Report For: Construction Maintenance Completed 
Bayou Bartholomew, LA and AR"2 , 4 - 1931 $ 45,874 $ 42,857 1 
Bayous D'Arbonne and Corney, LA1" 2.4 - 1941 19,000 37,804 1 
Big Black River, MS1' 4'.5 - 1895 15,000 - 1 
Big Sunflower River, MS1' 4.e.7 - 1942 560,027 459,328 1 
Boeuf River, LA1' 3. 4, 7, 8, 9 - 1949 30,000 103,7371 
Cypress Bayou and Waterway between 
Jefferson, TX, and Shreveport, LA15 Complete 1971 202,817 452,611 Dec. 1914 
Homochitto River, MS4 - 1910 15,482 8,518 1 
Little Missouri River, AR1' 4. 5 - 1873 19,992 - 1 
Little River, LA,1' 4. 5. o10 - 1890 1,500 - 1 
Little Tallahatchie River, MS 1 ' - 1913 19,000 - 1 
Mouth of Yazoo River, MS1' .11 - 1953 1,179,211 145,217 1 
Ouachita and Black Rivers, AR and LA, 
Felsenthal Canal - 193712 - - 1 
Red River below Fulton, AR1'1 7 . 1.
8 - 1978 1,963,806 2,147,890 1 
Red River Waterway 
LA, AR, OK, and TX1 17.1i8s - 1969 - - 1 
Red River Waterway, Shreveport, LA 
to Daingerfield, TX1 - 1976 70,000 - 1 
Removing snags and wrecks from - 1948 - 272,500 1 
Mississippi River below mouth of 
Missouri River and from 
Old and Atchafalaya Rivers" 
Saline River, AR, 3' 4, 5 - 1931 26,900 12,792 1 
Tallahatchie and Coldwater Rivers, MS"' .5 - 1939 43,481 173,0661 
Tensas River and Bayou Macon, LA1" 8' 12 - 1949 38,367 85,352 1 
Yalobusha River, MS' 4. . 14 - 1937 7,000 15,9361 
1. Status and Date unavailable. 
2. Abandonment recommended in H. Doc. 1962, 64th 
Cong., 2d sess., and H. Doc. 467, 69th Cong., 1st sess. 
3. Channels adequate for existing commerce. 
4. Inactive project. No commerce. 
5. Abandonment recommended in H. Doc. 467, 69th 
Cong., 1st sess. 
6. Project curtailment recommended by elimination of 
work between Pentecost and mouth of Hushpuckena River. 
(Abandonment of entire project erroneously recommended in 
H. Doc. 467, 69th Cong., 1st sess.) 
7. See report of Mississippi River Commission for 
operations in connection with Yazoo Basin. 
8. Report of New Orleans District, pp. 919-920 for 
Fiscal Year 1949. 
9. Project curtailment recommended by elimination of 
work above Girard, LA (Abandonment of entire project 
recommended erroneously in H. Doc. 467, 69th Cong., 1st 
sess.)
10. Due to decline of traffic, local interests not sufficiently 
interested to provide rights-of-way and dumping privileges. 
11. No additional funds available under this project. 
Work is being carried on under appropriation flood control, 
Mississippi River and tributaries. 
12. Year authorized. 
13. Inactive. Channel adequate for commerce. 
14. See report of Mississippi River Commission for 
operations in connection with Yazoo Basin flood control 
Grroejnecatd ai ncluding channel clearing and rectification and Lake on Yalobusha River. 
15. Excludes $50,000 contributed funds. 
16. Includes $1,553,878 for previous projects. 
17. Incorporated in the project "Red River Waterway- 
Mississippi River Shreveport, LA" Sept. 30, 1976. 
18. Emergency bank protection on this project is reported 
separately as "Red River Emergency Bank Protection." 
Two reaches, "Red River Waterway-Mississippi River to 
Shreveport, LA" and "Red River Waterway-Shreveport, LA, 
Daingerfield, TX," are also reported separately. 
12-21

TABLE 12-F 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
OUACHITA RIVER AND TRIBUTARIES: 
EXISTING PROJECT 
(See Section 23of Text) 
For Last Estimated 
Full Report Federal 
See Annual New Work 
Project Report for: Cost 
Blakely Mt. Dam-Lake Ouachita, AR (1) $ 44,100,000 
DeGray Lake, AR (1) 72,034,0002 
Narrows Dam-Lake Greeson, AR (') 20,900,000 
Calion, AR 1960 970,996 
Columbia, LA 1941 204,7402 
Existing levees and extensions thereto from Bastrop, LA, to mouth of 
Boeuf River and at West Monroe, LA 1961 3,025,1818 
Little Missouri River below Murfreesboro, AR 1957 354,802 
Ozan Creek, AR 1957 57,742w 
Terre Noire Creek, AR 1948 123,70 
Pine Bluff, AR, local protection 1954 172,582 
Monroe, LA, floodwall extension (Plan B) (1) 2,561,0002 
Bayou Bartholomew and Tributaries, AR and LA (1) 44,800,000 
Ouachita River Levees (additional work) (1) 9,400,000 
TABLE 12-G RESERVOIR OPERATIONS 
FISCAL YEAR 1983 
See 
Section Storage 
in Text Project (acre feet) Inflow' Outflow 
24. Bayou Bodcaus Oct. 1, 1981 249 - - 
Reservoir, LA Sep. 30, 1982 310 - - 
Jul. 2, 1982 (Max) 11,340 - - 
Jun. 29, 1982 (Max) - 1,664 - 
Jul. 2, 1982 (Max) - - 1,125 
36. Wallace Lake, LA Oct. 1, 1981 7,655 - - 
Sep. 30, 1982 7,319 - - 
Apr. 24, 1982 (Max 11,739 - - 
Apr. 23, 1982 (Max - 1,013 - 
Apr. 24, 1982 (Max - 634 
1. Cubic feet per second. 
12-22

VICKSBURG, MS, DISTRICT 
TABLE 12-H RED RIVER BELOW DENISON DAM 
(VICKSBURG DISTRICT): NEW PROJECTS 
(See See. 25 of Text) 
Drainage Conserva- Flood 
(sAqrueaar e Stotiroang e C(oanctrreo-l Estimated Federal 
Project Stream miles) (acre-feet) feet) Cost 
Bayou Bodeau and tributaries, AR' 2 - 1,158 - - $ 24,100,000s 
Bayou Nicholas-Coushatta, LA - - - 70,717 
Bayou Pierre in vicinity of Shreveport, LA - - - 248,38 
Caddo Lake, LAS Caddo Lake - - - 8,587,800' 
Campti-Clarence Area in 
Natchitoehes Parish, LA Red River - - - 1,950,000' 
Garland City, AR' - - - 1,450,000' 
Maniece Bayou, AR - - - - 970,082 
McKinney Bayou, AR'' - - - 5,610.000s 
Posten Bayou, AR and LA' - - - - 560,000 
Red River below Denison Dam 
levees and bank stabilization, 
TX, AR, and LA New- 
Orleans District)' - - 69,000,00 
Total 97,541,885 
1. Details presented in individual report herein. 
2. Construction on this project not started. 
3. In addition, non-Federal funds are: 
Bayou Bodeau and tributaries,A R and LA .............. .......................................... $5,800,000 
Bayou Pierre in vicinity of Shreveport, LA (cash contribution) ..................................... 89,047 
Caddo Lake, LA ................................... . ................................... ..... 28,000 
ECaasmtpPt oi-iCntla r.e.n.c.e. .A..r.e.a. i.n. .N.a.t.c.h.i.t.o.c.h.e.s. P..a.r.i.sh.., .L.A.. ............................ �................................................................. . 46870.,000000 
Garland City, Ark .............................................................................. 6,000 
Maniece Bayou, AR (cash contribution) ..................... 118.,0. 0.0.................................. 
McKinney Bayou AR (cash contribution) ........................................................ 508,000 
Red River below benison Dam, levees and bank stabilization, TX, AR, and LA .................. 1,560,000 
4. For last full report, see Annual Report for 1964. 
5. For last full report, see Annual Report for 1951. 
6. Inactive. 
7. Includes $4,330,200, Code 711, and $899,739 accelerated Public Work funds. 
8. Joint-use pool (sediment). 
9. Deauthorized by resolution Dec. 17, 1970, which also authorized new project "Posten Bayou, AR," under provision of 
See. 201 of Flood Control Act of 1965. 
12-23

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 12-I RED RIVER BELOW DENISON DAM 
(VICKSBURG DISTRICT): INCORPORATED PROJECTS 
(See Sec. 25 of Text) 
For Last 
Flood Estimated Full Report 
Project Control Federal See Annual Type of Work Act Cost Report For 
Aloha-Rigolette Area, Grant and Rapides 
Parishes, LA Levee and appurtenances 1941 $ 1,653,2371 1956 
Bayou Bodcau Reservoir, LA2 Flood-control reservoir 1938 5,120,7401. 3 4 
Bayou Bodcau, Red Chute, and 
Loggy Bayou, LA Channel improvement 1941 319,200' 1948 
Bayou Pierre, LA Channel enlargement 1936 299,529' 4 
Black Bayou Lake, LA5' 6 Flood-control reservoir 1936 714,000 1945 
Colfax, Grant Parish, LA Cutoff 1938 70,348''1 1938 
Grant Parish, below Colfax, LA Levees 1938 38,809' 1941 
Hempstead County levee district 
No. 1, AR Levee enlargement 1938 88,006' 1941 
Natchitoches Parish, LA Levee and appurtenances 1936 1,529,927" s 1956 
Pineville, Red River, LA Levee and appurtenances 1941 232,426' 1953 
Red River in vicinity of 
Shreveport, LA Bank protection 1944 3,908,000' 1953 
Red River Parish, LA Levee enlargement 1936 149,435' 1939 
Saline Point, LA Cutoff 1936 124,111' 1945 
Wallace Lake, LA Flood-control reservoir 1936 1,219,3711 3 4 
Total $15,467,134 
1. Actual cost. 
2. Project transferred to Vicksburg District August, 
1982.
3. Includes amounts indicated for recreational facilities 
under Code 711, Bayou Bodcau Reservoir, LA, $1,027,000; 
Wallace Lake, LA, $17,164. 
4. Included in this report. 
5. Work not started. 
6. Inactive. 
7. Completed under provisions of Sec. 7 of Flood Control 
Act of 1928, as amended by Sec. 9 of Flood Control Act of 
1936, and included in 1939 Annual Report of President, 
Mississippi River Commission, p. 2214. 
8. In addition, $25,000 was expended from contributed 
funds. 
12-24

VICKSBURG, MS, DISTRICT 
TABLE 12-J OTHER AUTHORIZED 
FLOOD CONTROL PROJECTS 
Mo. and Yr. 
Deauthorized 
For Last 
Full Report 
See Annual 
Report For: 
Cost to Sep. 1983 
Operation 
and 
Construction Maintenance 
Mo. and Yr. 
If 
Completed 
Aloha-Rigolette Area, Grant and 
Rapides Parishes, LA'- 
Bayou Bodcau, Red Chute, and 
Loggy Bayou, LA'- 
BaSyhoure Pveieprorret, i nL Avi*cinity of 
Big Black River, MS3 - 
Big Choctaw Bayou, LA3' - 
Black Bayou Reservoir, LA" 5. 6- 
Buffalo River, MS7 - 
Campti-Clarence Area in 
Natchitoches Parish, LAColfax, 
Grant Parishes, LA"8 - 
East Point, LA 
Garland City, ARGrant 
Parish below Colfax, LA' 3 a- 
Hempstead County Levee District 
No.1, AR1' 
Homochitto River, MS3- 
Maniece Bayou, AR1' 2 - 
MScKeginmneenyt ,B AayRo9u , Finn Bayou Aug. 1977 
Murfreesboro Dam and Lake'- 
Natchez Port Area, MS3' 4- 
Natchitoches Parish, LA" 2 - 
Pineville, Red River, LA3'" - 
Posten Bayou, AR'� - 
Red River Parish, LA" 3 
Red River in vicinity of 
Shreveport, LA' 
Saline Point, LA" 3 - 
Twelvemile Bayou, LA'- 
1. Authorized under project "Red River Below Denison 
Dam."
2. In addition, the following was expended from contributed 
funds: 
Amite River and tributaries ........... $ 430 
Bayou Pierre in vicinity of 
Shreveport, LA..................... 89,047 
Choctaw Bayou and Tributaries, LA ... 170,799 
Harvey Canal, Bayou Barataria Levee, 
LA .................................. 425,209 
Maniece Bayou, AR ................... 39,293 
Natchitoches Parish, LA .............. 250,000 
3. Completion Date Unavailable. 
$1,653,189 
319,200 
243,3362 
910,185 
248,823 
1956 
1948 
1951 
1956 
1966 
1945 
1940 
1978 
1938 
1969 
1976 
1941 
1941 
1956 
1970 
19639 
1951 
1969 
1956 
1953 
1973 
1939 
1! 
1
1 
1,655,700 
70,348 
286,069 
1,335,841 
38,809 
88,006 
205,000 
970,9322 
Apr. 1955 
Jan. 1948 
Jun. 1939 
670,750 
144,650 
538,000 
1,529,478 
232,426 
149,435 
Jul. 1978 
Aug. 1968 
Jul. 1974 
3
3
3 
Aug. 1969 
Aug. 1955 
Dec. 1951 
953 3,908,000 - Mar. 1953 
945 124,111- 
966 335,433 - May 1965 
4. Authorized by Chief of Engineers under authority of 
Sec. 205. Flood Control Act of 1948, as amended. 
5. Construction not initiated. 
6. Inactive. 
7. Deferred indefinitely because of insufficient justification 
under present conditions. 
8. Completed under provisions of Sec. 7, Flood Control 
Act 1928, as amended by Sec. 9, Flood Control Act 1936, and 
included in 1939 Annual Report of President, Mississippi 
River Commission, p. 2214. 
9. Date authorized. 
10. Posten Bayou Project, authorized by Senate and 
House Resolutions, Dec. 17 and 15, 1970, deleted the plan 
authorized by the Flood Control Act dated Aug. 3, 1955. 
12-25 
Project 
_ __ __ ___ __ 
_ __ ___ __ _ _ _

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 12-K ACTIVE GENERAL INVESTIGATIONS 
(96x8121) 
Federal Cost Totals by 
Item and CWIS Number FY 83 Categories 
($) ($) 
SURVEYS (Category 100) 
Flood Control Studies (120) 
Ouachita River Basin AR & LA -12046 1,116,494 
Pearl River Basin, MA and LA- 12284 841,680 
Pine Bluff Metro Area, AR- 12015 12,527 
Subtotal 1,970,651 
Comprehensive Studies (150) 
Red River Below Denison Dam (153)- 81129 244,291 
Miscellaneous Activities (170) 
Special Investigations (171)- 17250 9,100 
Review of FERC Licenses (172)- 58857 33887 
Subtotal 9,487 
Coordination Studies with Other Agencies (180) 
Department of Agriculture, Soil Conservation Service (181)- 51840 2,146 
Planning Assistance to States (186) -51850 0 
Technical and Engineering Assistance on Shoreline 
and Streambank (188)- 51781 . 6,824 
Subtotal 8,970 
TOTAL (Category 100) 2,233,349 
COLLECTION AND STUDY OF BASIC DATA (Category 200) 
Inspection of Dams (230) 
Inventory of Dams 172 
Flood Plain Management Services (250) 
Flood Plain Management Services 199,006 
Hydrologic Studies (260) 
Hydrologic Studies (260) - 53820 5,584 
Subtotal 204,762 
TOTAL (Category 200) 204,762 
ADVANCE E&D (Category 600) 
Navigation Projects (620) 
Locks and Dams, Yazoo River, MS (622) 
00083 323,158 
Flood Control Projects (650) 
Local Protection, Red River Waterway, 
Shreveport to Index (651) - 75023 4,335 
Subtotal 327,493 
TOTAL (Category 600) 327,493 
GRAND TOTAL GENERAL INVESTIGATIONS 2,765,604 
12-26

MEMPHIS, TN, DISTRICT* 
This district comprises a portion of southeastern 
Missouri and southern Illinois, western portions of 
Kentucky and Tennessee, a small portion of northern 
Mississippi, and the northeastern portion of Arkansas; 
includes area embraced in drainage basins of eastern 
tributaries of the Mississippi River south of Ohio River 
Basin to Nonconnah and Horn Lake Creeks, inclusive, 
and those of western tributaries south of Little River 
diversion channel and Commerce, MO, including St. 
Francis River Basin and White River and tributaries 
below Peach Orchard Bluff, AR, on the right bank and 
below Augusta, AR, on the left bank; also includes left 
bank Mississippi River levee from vicinity of Memphis 
south to about mile 620, and right bank levees from 
Cape Girardeau, MO, to about mile 605. 
IMPROVEMENTS 
Navigation 
1. Caruthersville Harbor, MO........... 
2. Helena Harbor, AR ................ 
3. Hickman Harbor, KY.............. 
4. New Madrid Harbor, MO........... 
5. Osceola Harbor, AR................ 
6. White River, AR (below 
Newport)......................... 
7. Wolf River (Memphis Harbor), TN ..... 
8. Navigation work under special 
authorization ...................... 
Flood Control 
9. Bradford, TN.................... 
10. Drinkwater Sewer, MO............. 
11. Huntington, TN ................... 
12. Long Lake area, Helena, AR......... 
13. Nonconnah Blvd., Nonconnah 
Creek, TN ................... 
Page Flood Control (cont.) 
13-1 14. North Second Street, Memphis, TN 
13-2 (Wolf River Bridge) ................ 
13-2 15. US Hwy 51, Nonconnah Creek, TN .... 
13-2 16. West Hickman area, Hickman, KY .... 
13-2 17. Inspection of completed flood control 
projects ......................... 
13-3 18. Flood control work under special 
13-3 authorization ...................... 
13-3 Tables 
Table 13-A 
13-3 
13-4 
13-4 
13-4 
Table 13-B 
Table 13-C 
Table 13-D 
13-4 Table 13-E 
Cost & Financial 
Statement ................. 
Authorizing Legislation ....... 
Other Authorized 
Navigation Projects ......... 
Other Authorized Flood 
Control Projects ............. 
Active General Investigations ... 
Page 
13-4 
13-4 
13-5 
13-5 
13-5 
13-6 
13-8 
13-10 
13-10 
13-11 
Navigation 
1. CARUTHERSVILLE HARBOR, MO. 
Location. In Pemiscot, MO, in an old river chute 3 
miles north of the town of Caruthersville, MO, on the 
right bank of the Mississippi River, 349.5 miles above 
Head of Passes, LA. 
Existing project. Authorized by the Chief of Engineers 
Nov. 4, 1980, under the authority of Sec. 107 of the 
River and Harbor Act of 1960, as amended. Harbor 
channel construction consisted of removal of 600,000 
cubic yards of material from a 300- by 300-foot turning 
basin and provision of a 9- by 150-foot navigation channel, 
4,680 feet long. The excavated material was placed 
on top bank, between retainer dikes and the mainline 
Mississippi River levee to form a flood-free fill to be 
developed as an industrial park by local interests. 
Local cooperation. Fully complied with. 
Terminal facilities. Facilities are being provided by 
the Pemiscot County Port Authority. 
Operations and results during fiscal year. Leased 
dredge, Natchez, removed 250,030 cubic yards of material 
at a cost of $277,765 in August 1983 in maintaining 
project channel. 
Condition as of Sep. 30. Federal participation in the 
project is complete except for expected future maintenance 
dredging. 
13-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
2. HELENA HARBOR, AR 
Location. In Phillips County, AR, on right bank of 
Mississippi River about 663 miles above Head of Passes, 
LA. (AHP). 
Existing project. Authorized by Chief of Engineers, 
Sep. 20, 1962, under authority of Sec. 107 of the River 
and Harbor Act of 1960, as amended. Provides for 
maintenance of access channel with a depth of 9 feet 
below low water, between miles 659 and 663 APH, by 
dredging, and for enlarging the upstream 0.6 mile to 
dimensions of 9 feet deep by approximatly 450 feet 
wide. Remainder of channel conforms to project width 
of the main channel of Mississippi River. River stages 
recorded at Helena gage (zero is 141.70 feet msl) since 
1871 have ranged between minus 3.0 and plus 60.21 feet 
with an average annual fluctuation of 40.6 feet. 
Local cooperation. Fully complied with. 
Terminal facilities. There are ten terminals within 
the harbor, two of which are publicly-owned. Others are 
a rail incline, a small boat dock, grain terminals, a 
petroleum products terminal, a midstream grocery and 
refueling service, a fuel unloading facility, and a 
fertilizer-loading facility. 
Operations and results during fiscal year. No 
dredging was performed during FY 83 in Helena 
Harbor. 
Condition as of Sep. 30. Project is complete and is 
being maintained to dimensions. 
3. HICKMAN HARBOR, KY 
Location. In Fulton County, KY, on left bank of 
Mississippi River about 922 miles APH. 
Existing project. Authorized by Chief of Engineers, 
Jul. 12, 1962, under authority of Sec. 107 of the River 
and Harbor Act of 1960, as amended. Provides for 
dredging and maintaining harbor channel 250 feet 
wide with depth of 9 feet below low water, from main 
channel of Mississippi River at mile 922 AHP along 
former city waterfront about 1.1 miles, with the upper 
600 feet forming a turning basin 500 feet wide. New 
work was completed in Fiscal Year 1963. River stages 
recorded since 1929 at Hickman gage (zero is 264.73 
feet msl) have ranged between minus 0.4 and plus 51.5 
feet with average annual fluctuation of 38 feet. 
Local cooperation. Fully complied with. 
Terminal facilities. Within harbor are terminals for 
handling petroleum products, sand and gravel, and 
timber and grain, which are publicly and privately 
owned; there is about 0.2 mile of surfaced, public 
mooring and launching area. 
Operations and results during fiscal year. Leased 
dredge, Natchez, removed 387,918 cubic yards of material 
in July 1983 in maintaining project channel. 
Expenditure was $407,961. 
Condition as of Sep. 30. Project was completed Jan. 
20, 1961, and is being maintained to project dimensions. 
4. NEW MADRID HARBOR, MO 
Location. New Madrid County, MO, on right bank of 
the Mississippi River about 889 miles AHP. 
Existing project. Construction and subsequent maintenance 
of a harbor channel 150 feet wide with a depth 
of 9 feet below low water from the head of New Madrid 
Bar, about mile 889 AHP, along the city waterfront 
downstream for a distance of about 9,400 feet, with a 
250-foot-radius turning basin at the downstream end. 
The project was authorized by the Chief of Engineers, 
Feb. 21, 1968, under Sec. 107 of the River and Harbor 
Act of 1960, as amended. 
Local cooperation. Fully complied with. 
Terminal facilities. Within the harbor are privately 
owned terminals for handling petroleum products, logs 
and lumber, and soybeans and grain. Terminal facilities 
are considered adequate for present and immediately 
foreseeable commerce. 
Operations and results during fiscal year. 
Expended $19,688 for Construction and Operation 
studies. 
Condition as of Sep. 30. Project was completed Oct. 
2, 1970, and is being maintained to project dimensions. 
5. OSCEOLA HARBOR, AR 
Location. Mississippi County, AR, on the right bank 
of the Mississippi River at about 784 miles AHP. 
Existing project. The project was authorized by the 
Chief of Engineers, Sep. 30, 1971, under Sec. 107 of the 
River and Harbor Act of 1960, as amended. Harbor 
channel construction consisted of removal of 689,705 
cubic yards of material from the harbor channel to 
provide a navigation channel 250 feet wide and 9 feet 
deep from the Mississippi River navigation channel at 
the downstream end of the old chute of Island 30, 
upstream along the old bendway channel for a line 
distance of 6,500 feet. A 250-foot-radius turning basin is 
provided at the upstream end of the harbor channel. 
The excavated material removed from the channel was 
placed on the top bank between the old bendway 
channel and the main line Mississippi River levee to 
form a flood-free industrial park to be developed by 
local interests. Latest published map is in 1980/48th 
edition, Flood Control and Navigation Maps of the 
Mississippi River, prepared under the direction of 
President, Mississippi River Commission. 
Local cooperation. Fully complied with. 
Terminal facilties. Public terminal facilities have 
been provided by Osceola Riverport Authority. 
Operations and results during fiscal year. Leased 
dredge, Natchez, removed 528,984 cubic yards of material 
for channel maintenance during August 1983. 
Total expenditure was $649,006. 
Conditionasof Sep. 30. Project, begun Sep. 30,1970, 
was completed Nov. 13, 1974, and is being maintained 
to project dimensions. 
13-2

MEMPHIS, TN, DISTRICT 
6. WHITE RIVER, AR 
(BELOW NEWPORT) 
Location. Rises in northwestern Arkansas and flows 
686 miles first north into Missouri, thence southeasterly 
through Arkansas to the Mississippi River 64 miles 
below Helena, AR. (See Mississippi River Commission 
alluvial valley maps, scales 1:62,500 and 1:500,000 and 
map folio, May 1973, of White River, vicinity of Batesville, 
AR, to Mississippi River, scale 1:24,000.) White 
River enters Memphis District at foot of Peach Orchard 
Bluff, AR, 165 miles above its mouth; but Memphis 
District is responsible for maintenance of navigation 
channel from mile 10.0 to mile 254.0, Newport, AR. 
Previous projects. For details, see page 1874, Annual 
Report for 1915, and page 938, Annual Report for 
1938. 
Existing project. Maintenance of a channel 4.5 feet 
deep by 100 feet wide between mouth of river and 
Batesville, 296 miles, by snagging, dredging, and contraction 
works. Maintenance discontinued after Fiscal 
Year 1951 due to negligible traffic; dredging and 
snagging resumed in 1962. White River channel from 
mouth to mile 10 has been improved and is being 
maintained as part of the Arkansas River Project. The 
existing project was modified by OCE, Mar. 11, 1968, 
under authority of Sec. 107 of the 1960 River and 
Harbor Act, as amended, to provide a 125-foot-wide 
channel with minimum depth of 5 feet and a depth of 8 
feet at a stage of 12 feet on the Clarendon gage. This 
modification has been completed and increased dimensions 
extend from the mouth to Augusta, at mile 199. In 
February 1971, OCE authorized resumption of maintenance 
from Augusta to Newport. 
Local cooperation. Fully complied with. 
Terminal facilities. Consist of terminals for handling 
riprap stone, sand and gravel, logs, soybeans, 
wheat, and rice at Augusta (mile 198); logs, soybeans, 
wheat, and rice at Des Arc (mile 143); logs, lumber, 
soybeans, and rice at Clarendon (mile 99); soybeans at 
Crocketts Bluff (mile 68); soybeans, rice, sand, gravel, 
and crushed stone at St. Charles (mile 57); riprap stone 
at Benzal (mile 7.5); and public launching ramp at 1-40 
bridge. 
Operations and results during fiscal year. Dredging 
was performed at various locations between mile 10 
and mile 255 to provide project width and depth. Leased 
dredge, Tulsa, moved 1,343,570 cubic yards of material 
in maintaining project channel. Snagging operations 
were resumed June 1983 by hired labor. Total project 
Fiscal Year 1983 cost was $944,596. 
Conditions as of Sep. 30. Project is complete and is 
being maintained to project dimensions. 
7. WOLF RIVER 
(MEMPHIS HARBOR), TN 
Location. Rises near western edge of Tippah County, 
MS, and flows generally northwesterly through Shelby 
County, TN, entering the Mississippi River above Memphis, 
TN (mile 738.7 AHP). The lower 3.5 miles of 
channel, parallel to the Mississippi River along the 
Memphis waterfront, became a slack-water harbor 
when Wolf River was diverted through Mud Island to 
the Mississippi River by a flood control project, Wolf 
River and tributaries, under the Flood Control Act of 
1958. (See Mississippi River Commission alluvial valley 
maps, scales 1:62,500 and 1:500,000, and folio of Flood 
Control and Navigation Maps of the Mississippi River, 
Cairo, IL, to Gulf of Mexico, scale 1:62,500, revised 
annually.) 
Previous projects. For details see pages 701 and 702, 
Annual Report for 1962. 
Existing project. The project provides a channel 9 
feet deep at low water from mouth to mile 3, with 
bottom widths of 250 feet from mouth to Keel Avenue 
(mile 1.75) and 200 feet from Keel Avenue to mile 3. 
Local cooperation. Fully complied with. 
Terminal facilities. Twenty terminals along project 
channel. One terminal is operated by Coast Guard, two 
by contract carriers, and 17 are operated privately. 
Operations and results during fiscal year. Leased 
dredge, Natchez, removed 114,718 cubic yards of material 
in September 1983, in maintaining the channel. 
Total Fiscal Year 1983 expenditure was $151,407. 
Condition as of Sep.30. Project began May 15, 1928, 
and is maintained to project dimensions. 
8. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation activities pursuant to Sec. 107, Public 
Law 86-645, as amended (preauthorization). 
No work done under this authorization. 
Flood Control 
9. BRADFORD, TN 
Location. Bradford is located in Gibson County, TN. 
Existing project. Authorized July 18, 1983, under 
the authority of Section 208 of the 1954 Flood Control 
Act, as amended. The plan of improvement consists of 
the clearing and snagging of approximately 5500 feet of 
channel and riprap protection for two street bridges 
and one railroad bridge. The estimated construction 
cost is $95,700. Flood protection for approximately 88 
structures including residences, businesses and schools 
will be provided and no significant adverse environmental 
effects will result. 
Local cooperation. Local interests have furnished 
the required assurances. 
Condition as of Sep. 30. Contract awarded in fourth 
quarter of FY 83. Construction to be completed in the 
second quarter of FY 84. 
13-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
10. DRINKWATER SEWER, MO 
Location. The Big Lake Basin is located immediately 
north of Charleston in Scott and Mississippi Counties, 
MO, and approximately 4.5 miles west of Cairo, IL. 
Existing project. Authorized under authority of 
Section 205 of the Flood Control Act of 1948, as 
amended. Construction of a 150-cubic-feet-per-second 
pumping plant just north of the existing gravity outlet, 
with an 855-foot inlet channel to connect the pumping 
plant with the existing Big Lake Ditch, and an energy 
dissipator (baffled outlet) at the pumping plant outfall. 
This will provide relief during the Mississippi River 
flood stages, for 8.5 square miles of agricultural land 
from a watershed totaling 27.6 square miles. 
Local cooperation. Local interests have furnished 
the required assurances. 
Operations and results during fiscal year. The 
design of the vacuum breaker valve was modified to 
allow pump operation at low tailwater conditions. 
Construction on this modification is complete. 
Condition as of Sep. 30. Complete June 30, 1980. 
11. HUNTINGDON, TN 
Location. In Carroll County, TN. 
Existing project. Authorized Aug. 11, 1976, under 
authority of Sec. 205 of the 1948 Flood Control Act, as 
amended. The plan consists of 1,110 feet of channel 
enlargement, 1,870 feetof vertical wall concrete channel 
and 3,320 feet of grouted riprap channel. First cost 
is $1,837,000. Protection to approximately 90 acres of 
highly developed urban lands will be provided and no 
significant adverse environmental effects will result. 
Local cooperation. Fully complied with. For details, 
see Page 13-5, Annual Report for FY 1980. 
Condition as of Sep. 30. Construction was completed 
Sep. 11, 1981. 
12. LONG LAKE AREA, HELENA, AR 
Location. The project is located immediately south of 
Helena, Phillips County, AR. The area is protected from 
flooding by the Mississippi River by the project levee, 
and primary drainage of the area through Long Lake 
Bayou. 
Existing project. Authorized Dec. 16, 1975, under 
authority of Sec. 205 of the 1948 Flood Control Act, as 
amended. The authorized improvements consist of enlargement 
and cleanout of Long Lake Bayou, extending 
from the culvert upstream 5.6 miles to a point about 3/4 
mile below Rabb Lake or some 10 miles below Helena. 
The plan also provides for revegetation of rights-of-way 
(about 100 acres) not required to remain open for 
channel maintenance purposes; and the project sponsor 
will be required to maintain the revegetated area after 
project construction. 
Local cooperation. Fully complied with. For details, 
see Page 13-5, Annual Report for FY 1980. 
Condition as of Sep. 30. Project was deauthorized 
July 1983. 
13. NONCONNAH BLVD., 
NONCONNAH CREEK, TN 
Location. The project site is on the left bank of 
Nonconnah Creek in a reach extending from about 550 
feet upstream to 150 feet downstream of the Nonconnah 
Blvd. Bridge in Shelby County, Memphis, TN. 
Existing project. Authorized under the authority of 
Section 14 of the Flood Control Act of 1946. This project 
provides protection for the Nonconnah Blvd. Bridge 
from streambank caving. The improvements consist of 
grading and placing riprap on about 700 feet of eroding 
streambank. 
Local cooperation. Local interests have furnished 
the required assurances. 
Condition as of Sep. 30. Construction began in Sep. 
1981 and was completed in November 1981. 
14. NORTH SECOND STREET, 
MEMPHIS, TN (WOLF RIVER 
BRIDGE) 
Location. The project site is on the left bank of the 
Wolf River approximately one mile above its confluence 
with the Mississippi River at the North Second Street 
Bridge in Shelby County, Memphis, TN. 
Existing project. Authorized under the authority of 
Section 14 of the Flood Control Act of 1946. This project 
provides protection for the North Second Street Bridge 
from streambank caving. The improvements consist of 
grading and placing riprap on the eroding river bank, 
approximately 250 feet downstream and 800 feet upstream 
from the bridge. 
Local cooperation. Local interests have furnished 
the required assurances. 
Condition as of Sep. 30. Complete. 
15. US HWY 51, NONCONNAH 
CREEK, TN 
Location. The project site is on the left bank of 
Nonconnah Creek in a reach extending from the US 
Hwy 51 bridge upstream about 500 feet, in Shelby 
County, Memphis, TN. 
Existing project. Authorized under the authority of 
Section 14 of the Flood Control Act of 1946. This project 
provides protection for the US Hwy 51 bridge from 
streambank caving. The improvements consist of filling 
and grading the bank and providing protection for the 
bank via rock-filled gabions. 
Local cooperation. Local interests have furnished 
the required assurances. 
13-4

MEMPHIS, TN, DISTRICT 
Condition as of Sep. 30. A contract for construction 
of the project was awarded on Sep. 30, 1982, and work 
was completed in March 1983. 
16. WEST HICKMAN AREA, 
HICKMAN, KY 
Location. This project is located in the western 
section of the city of Hickman, Fulton County, KY. The 
area is protected from flooding by the Mississippi River 
by a levee and floodwall on the west. 
Existing project. Authorized Aug. 9, 1973, under 
authority of Sec. 205 of the 1948 Flood Control Act, as 
amended. The plan of improvement consists of installing 
a flap gate on the existing box culvert through the 
old levee to prevent backwater flooding from Bayou du 
Chien, excavation of a 3.8-acre sump area, and construction 
of a 190-cfs pumping plant to reduce flooding 
from interior runoff. About 800 feet of interior channel 
will be reshaped through the excavated sump area, 190 
feet of new outlet ditch will be built from the pump 
discharge to the existing outlet ditch, and 300 feet of the 
existing ditch is to be cleaned out and/or enlarged. 
Local cooperation. Fully complied with. For details, 
see Page 13-5, Annual Report for FY 1980. 
Condition as of Sep. 30. Completed Oct. 15, 1976. 
17. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Inspected completed projects at a cost of $81,853 in 
the period. Total cost as of Sep. 30, 1983, was $847,110. 
This included in-depth inspection of projects. 
18. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control activities pursuant to Sec. 205, 
Public Law 858, 80th Cong., as amended 
(preauthorization). 
During the period $87,925 was expended for detailed 
studies on Little Hatchie and Kise Creeks, TN; $49,746 
on Humboldt, TN; $69,816 on Caney Creek, AR; and 
$7,500 on Cane Creek, Jackson, TN; and $7,782 on 
Martin Beach, Clarendon, AR 
Emergency bank protection (Sec. 14 of 1956 Flood 
Control Act, Public Law 526, 79th Cong.). During FY 
1983, a reconnaissance study was completed on Sandy 
Creek, Jackson, TN, at a cost of $5,766. 
Emergency flood control activities-repair, flood 
fighting, and rescue work (Public Law 99, 84th Cong., 
and antecedent legislation). Federal cost was 
$1,232,021.58 for disaster preparedness. 
13-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 13-A 
See 
Section 
in Text Project 
1. Caruthersville 
Harbor, MO 
2. Helena Harbor, 
AR 
3. Hickman Harbor, 
KY 
4. New Madrid 
Harbor, MO 
5. Osceola Harbor 
AR 
6. White River, 
AR 
(below Newport) 
7. Wolf River 
(Memphis Harbor), 
TN 
9. Bradford, TN 
10. Drinkwater 
Sewer, MO 
11. Huntingdon, 
TN 
12. Long Lake area, 
Helena, Ark. 
13. Nonconnah Blvd.; 
Nonconnah Creek, 
TN 
COST AND FINANCIAL STATEMENT 
FY 82 
$ 
252,000 
229,758 
Funding 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
FY 80 
$ 70,000 
53,017 
66,400 
199,782 
200,900 
347,859 
1,000 
451 
274,900 
570,780 
917,000 
674,208 
213,000 
59,473 
35,000 
535 
1,395,000 
1,651,613 
-39,000 
3,629 
13-6
FY 81 
$ 618,500 
636,305 
280,000 
278,311 
303,000 
283,522 
282,000 
277,569 
513 
555,000 
694,079 
878,200 
1,258,457 
630,000 
783,129 
37,000 
60,581 
1,032,000 
1,030,028 
55,000 
21,237 
362,000 
360,390 
252,000 
249,585 
11,000 
1,366 
541,000 
554,773 
1,933,000 
1,871,545 
441,000 
410,893 
37,500 
36,790 
47,000 
39,975 
2,500 
14,903 
195,000 
228,762 
Total Funds to 
FY 83 Sep. 30, 1983 
- $ 748,500 
- 768,992 
318,000 850,000 
277,765 785,834 
- 90,847 
- 90,847 
214,000 2,245,400 
15,861 2,019,835 
- 149,827 
- 149,827 
419,000 2,197,748 
407,961 2,179,649 
- 196,373 
- 196,373 
10,000 387,500 
19,688 385,509 
- 269,115 
- 269,115 
717,000 3,688,000 
649,006 3,613,397 
- 169,9941 
- 169,9942 
875,000 12,164,603 
944,596 11,857,286 
- 586,500 
- 586,500 
473,000 6,475,488 
151,407 6,112,216 
132,500 170,000 
23,283 60,073 
- 1,991,000 
23,818 1,491,891 
- 2,899,500 
- 2,900,281 
- 62,000 
- 61,281 
- 250,000 
- 249,999

MEMPHIS, TN, DISTRICT 
TABLE 13-A 
(Continued) 
COST AND FINANCIAL STATEMENT 
See 
Section Total Funds to 
in Text Project Funding FY 80 FY 81 s FY 82 FY 83 Sep. 30, 1983 
14. North Second New Work 
Street, Approp. 219,000 - - 250,000 
Memphis, TN Cost 220,105 10,714 - - 249,999 
(Wolf River Bridge) 
15. US Hwy 51, New Work 
Nonconnah Approp. - 7,000 230,000 -25,000 212,000 
Creek, TN Cost - 6,224 169,403 192,905 368,532 
16. West Hickman New Work 
area, Hickman, KY Approp. 42,000 - - - 1,656,6928 
Cost 24,410 33,194 8,131 - 1,674,2808 
1. Excludes $25,000 expenditures for early construction; 
includes $20,245 for preauthorization studieson Sec. 107 Project. 
2. Excludes $17,500 contributed funds expended. 
3. Includes $40,992 for preauthorization studies on Sec. 
205 Project. 
13-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 13-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Jul. 14, 1960, 
as amended 
Jul. 14, 1960, 
as amended 
Jul. 14, 1960, 
as amended 
Jul. 14, 1960, 
as amended 
Jul. 14, 1960, 
as amended 
Jul. 13, 1892 
Jul. 14, 1960, 
as amended 
Aug. 30, 1935 
Jul. 3, 1958 
Sep. 3, 1954, 
as amended 
Jun. 30, 1948, 
as amended 
Jun. 30, 1948, 
as amended 
June. 30, 1948, 
as amended 
Jul. 24, 1946, 
as amended 
Jul. 24, 1946, 
as amended 
Jul. 24, 1946 
as amended 
CARUTHERSVILLE HARBOR, MO 
(See Sec. 1 of Text) 
Channel 9 feet deep at low water and 150 feet wide, 4,680 
feet long in a right bank chute at mile 849.5 AHP 
HELENA HARBOR, AR (See Sec. 2 of Text) 
Channel 9 feet deep at low water between miles 659 and 
663 AHP. 
HICKMAN HARBOR, KY (See Sec. 3 of Text) 
Channel 9 feet deep at low water and 250 feet wide at 
mile 922 AHP along former city waterfront 1.1 miles, 
with upper 600 feet forming turning basin 500 feet wide. 
NEW MADRID HARBOR, MO (See Sec. 4 of Text) 
Channel 9 feet deep at low water and 150 feet wide at 
mile 889 AHP, along city waterfront 9,400 feet with a 
turning basin 250 feet wide. 
OSCEOLA HARBOR, AR (See Sec. 5 of Text) 
Channel 9 feet deep at low water and 250 feet wide, 6,500 
feet upstream along the old bendway channel. 
WHITE RIVER, ARK(below Newport) (See Sec. 6 of Text) 
Open channel work, mouth to Batesville. 
Channel enlargement, mile 10 to Augusta. 
WOLF RIVER (Memphis Harbor), TN (See Sec. 7 of Text) 
Channel 9 feet deep at low water and 250 feet wide to mile 
1.75; 200 feet wide to mile 3.5; thence 125 feet wide to 
mile 5.5. 
Flood control work in lieu of navigation improvements 
above mile 3. 
BRADFORD, TN (See Sec. 9 of Text) 
Channel improvement within the City of Bradford. 
DRINKWATER SEWER, MO (See Sec. 10 of Text) 
Pumping station. 
HUNTINGDON, TN (See Sec. 11 of Text) 
ChanneF improvement within the city of Huntingdon. 
LONG LAKE AREA, HELENA, AR (See Sec. 12 of Text) 
Approximately 5 miles of channel improvement on Long 
Lake Bayou. 
NONCONNAH BLVD., 
NONCONNAH CREEK, TN (See Sec. 13 of Text) 
Stabilization of stream bank caving. 
NO. SECOND ST, MEMPHIS, TN 
(WOLF RIVER BRIDGE). (See Sec. 14 of Text) 
Stabilization-Stream bank caving. 
U.S. HWY 51 
NONCONNAH CREEK, TN (See Sec. 15 of Text) 
Stabilization of stream bank caving. 
Approved Nov. 4, 19801 
Approved Sep. 20, 1962.1 
Approved Jul. 12, 1962.1 
Approved Feb. 21, 1968.1 
Approved Sep. 30, 1971.1 
Annual Report, 1893, 
page '112. 
Approved Mar. 11, 1968.1 
H. Does. 26, 72d Cong., 
1st sess., and 45, 74th 
Cong., 1st sess. 
H. Doc. 76, 85th Cong., 
1st sess. 
Approved July 18, 19835 
Approved Jan. 5, 1977.2 
Approved Aug. 11, 1976.2 
Approved Dec. 16, 1975.2 
Approved Dec. 24, 19804 
Approved Jul. 23, 19794 
Appoved Nov. 10, 1980 
13-8

TABLE 13-B 
(Continued) 
MEMPHIS, TN, DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
WEST HICKMAN AREA, HICKMAN, KY. 
(See Sec. 16 of Text) 
Jun. 30, 1948, Installation of flap gate on existing culvert; 190-cfs Approved Nov. 9, 1973.2 
as amended pumping station; and minor channel work. 
1. Authorized under authority of Sec. 107 of the River 
and Harbor Act, as amended. 
2. Authorized under authority of Sec. 205 of the 1948 
Flood Control Act, as amended. 
3. Contains latest published map. 
4. Authorized under authority of Sec. 14 of the 1946 
Flood Control Act. 
5. Authorized under authority of Sec. 208 of the 1954 
Flood Control Act, as amended. 
13-9

TABLE 13-C 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to Sep. 1983 
Full Report Operation 
Mo. and Yr. See Annual and Mo. and Yr. 
Project Deauthorized Report For: Construction Maintenance Completed 
Forked Deer River, TN, including South 
Fork1' 2 - 1912 $25,000 $ 12,818- 
Obion River, Tenn." 3 a - 1911 28,716 -- 
Removing snags and wrecks from 
Mississippi River below mouth of Missouri 
River and from Old and Atchafalaya 
Rivers4' 5 - 1948 - 318,833 4 
St. Francis and L'Anguille Rivers and 
Blackfish Bayou, AR1 2 - 1942 92,000 300,449 
1. No commerce. 4. Completion date not available. 
2. Existing project is for maintenance only. 5. No funds available under this project. Work being 
3. Recommended for abandonment in H. Doc. 467, 69th carried on under "Appropriation, Flood Control, Mississippi 
Cong., 1st sess. River and tributaries. 
TABLE 13-D OTHER AUTHORIZED 
FLOOD CONTROL PROJECTS 
For Last Cost to Sep. 1983 
Full Report Operation 
Mo. and Yr. See Annual and Mo. and Yr. 
Project Deauthorized Report For: Construction Maintenance Completed 
Big Creek Canal, Millington, TN - 1977 $ 70,363 $ - 
Big Creek and L'Anguille River, White 
River Basin, AR' 6 May 81 1937 - - 
Clarendon to Laconia Circle, 
White River Basin, AR' 6 May 81 - - 
Cottonwood Slough pumping plant, IL2 - 1964 147,000 - Feb 1964 
Dyersburg, TN2 - 1962 229,649s - Jun 1962 
Dyersburg, TN (SW) - 1981 1,820,869 - Oct 1976 
Memphis, Wolf River, and 
Nonconnah Creek, TN - 1960 11,141,199 - May 1959 
Mounds and Mound City, 
Ohio River Basin, IL' - 1955 1,132,704 - Oct 19596 
Nixon Creek, TN2 - 1952 62,821 - Dec 1951 
Treasure Island, MO - 1981 861,528 - Mar 1978 
1. Inactive, awaiting local cooperation. 
2. Authorized by Chief of Engineers under small project 
authority, Sec. 205, Flood Control Act of 1948, as amended. 
3. Includes $21,863 contributed funds. 
4. Work being completed under Mississippi River and 
Tributaries project. 
5. Exclusive of Cache River Pumping Station. 
13-10

MEMPHIS, TN, DISTRICT 
TABLE 13-E ACTIVE GENERAL INVESTIGATIONS 
(96x3121) 
Federal Cost Totals by 
Item and CWIS Number FY 83 Categories 
SURVEYS (Category 100) 
Navigation (110) 
St. Francis River Navigation, AR -10036 $ 1,172 
White River Navigation to Batesville, AR -60740 0 
1,172 
Flood Control Studies (120) 
Memnphis Metropolitan Area, AR, TN, & MS -12135 194 
194 
Coordination Studies with Other Agencies (180) 
Tech. & Engr. Assist. Shore & Streambank Erosion (188)-51731 0
0 
$ 1,366 
COLLECTIONS AND STUDY OF BASIC DATA (Category 200) 
Flood Plain Management Services (250) 
Flood Plain Management Services 158,870 
TOTAL (Category 200) $158,870 
GRAND TOTAL GENERAL INVESTIGATIONS $160,236 
13-11

ST. LOUIS, MO, DISTRICT* 
This district comprises those portions of southwestern 
Illinois and eastern Missouri embraced in 
drainage basin of Mississippi River and its western 
tributaries, exclusive of the Missouri River, from the 
mouth of the Ohio River to mile 300, and of its eastern 
tributaries to Hamburg Bay at mile 261 on left bank, 
exclusive of tributary basin of Illinois Waterway upstream 
of new La Grange Lock and Dam at mile 80.15 
above confluence of the Illinois and Mississippi Rivers. 
District also includes drainage basin in Missouri 
tributary to the Little River diversion channel. Report 
on the Mississippi River between the Missouri River 
and mile 300 is included in separate report on the 
Mississippi River between the Missouri River and 
Minneapolis, MN. Report on the portion of the Illinois 
River downstream of new La Grange Lock and Dam is 
included in report of the Chicago District on the Illinois 
Waterway, Illinois and Indiana. 
IMPROVEMENTS 
Navigation 
1. Illinois Waterway, IL 
(St. Louis Dist.) ................. 
2. Kaskaskia River, IL.............. 
3. Mississippi River between Missouri 
and Minneapolis, MN (St. Louis Dist.) 
(Includes L&D 26 Replacement) ..... 
4. Mississippi River between Ohio 
and Missouri Rivers, MO, and IL .... 
Flood Control 
5. East St. Louis and vicinity, IL...... 
6. Eldred and Spankey Drainage and 
Levee District, IL ................ 
7. Hartwell Drainage and Levee 
District, IL ..................... 
8. Hillview Drainage and Levee 
District, IL .................... 
9. Kaskaskia Island Drainage and 
Levee District, IL ................ 
10. Meramec River Basin, MO . ........ 
10A. Meramec Park Lake, MO .......... 
10B. Pine Ford Lake, MO .............. 
11. McGee Creek Drainage and Levee 
District, IL .................... 
12. Meredosia, IL, and Meredosia, 
Willow Creek, and Coon Run 
Drainage and Levee District, IL ..... 
13. Meredosia Lake and Willow Creek 
Drainage and Levee District, IL ..... 
14. Mississippi River Agricultural 
Area8, MO ..................... 
15. Nutwood Drainage and Levee 
District, IL .................... 
Page Flood Control (cont.) 
16. Perry County Drainage and Creek 
14-2 Districts Nos. 1, 2, and 3, MO....... 
14-2 17. Rend Lake, Big Muddy River, IL .... 
18. Wood River Drainage and 
Levee District, IL ................ 
14-2 19. Inspection of completed flood 
control projects .................. 
14-2 20. Navigation work under 
14-3 
special authorization .............. 
21. Flood control work under 
special authorization .............. 
14-3 Multiple-Purpose Project 
Including Power 
14-3 22. Clarence Cannon Dam and Mark Twain 
Salt River, MO .................. 14-414-4 General Investigations 
14-4 23. Active investigations ................ 
14-4 
14-4 
14-5 
Tables 
Table 14-A 
14-5 Table 14-B 
Table 14-C 
14-5 
14-5 
14-6 
14-6 
Table 14-D 
Table 14-E 
Table 14-F 
Cost and Financial 
Statement ................. 
Authorizing Legislation ...... 
Other Authorized 
Navigation Projects ......... 
Lakes, Levees, and 
Recreational Facilities ....... 
Other Authorized Flood 
Control Projects ............ 
Active General 
Investigations (96X3121) ..... 
Page 
14-6 
14-6 
14-7 
14-7 
14-7 
14-7 
14-7 
14-8 
14-9 
14-11 
14-13 
14-13 
14-14 
14-16 
14-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Navigation 
1. ILLINOIS WATERWAY, IL 
(ST. LOUIS DIST.) 
See report on Illinois Waterway, IL and IN, under 
Chicago District. 
2. KASKASKIA RIVER, IL 
Location. The river rises in Champaign County, IL, 
about 5 miles northwest of Urbana, in east-central part 
of State. It flows southwesterly about 325 miles and 
empties into Mississippi River about 8 miles above 
Chester, IL, or about 118 miles above mouth of Ohio 
River. (See Cincinnati sheet of maps of United States 
published by Army Map Service, scale 1:500,000.) 
Previous project. For details see Annual Report for 
1896, page 171. 
Existing project. Improvement for navigation 
provides a channel 9 feet deep and 225 feet wide from 
mouth to Fayetteville, IL. Improvement consists of 
enlarging present channel where required, making 
overbank cutoffs to eliminate sharp bends, and construction 
of a dam at mile 0.8 with a single lock 84 feet wide 
and 600 feet long, at an estimated total Federal project 
cost (1983) of $152,725,000. Non-Federal project cost is 
$7,665,000, of which $1,500,000 is local contribution. 
Local cooperation. State of Illinois passed legislation 
authorizing Illinois Department of Public Works and 
Buildings to enter into assurances of local cooperation 
with the United States. These assurances have been 
furnished and were accepted Nov. 23, 1965. 
Operations and results during fiscal year. Work is 
complete on the lock and dam, railroad relocations, and 
the grade control structure. Engineering and design 
continued on remaining construction items. Project is 
about 84 percent complete. 
Maintenance. Hired labor performed operation and 
maintenance of the project. 
3. MISSISSIPPI RIVER BETWEEN 
MISSOURI RIVER AND MINNEAPOLIS, 
MN. (ST. LOUIS DIST.) 
(INCLUDES L&D 26 REPLACEMENT) 
See separate section entitled "Mississippi River between 
Missouri River and Minneapolis, MN," printed in 
the Annual Report of the Chief of Engineers. 
4. MISSISSIPPI RIVER BETWEEN 
OHIO AND MISSOURI RIVERS, 
MO AND IL 
Location. Mississippi River rises in Lake Itasca, MN, 
and from that lake flows southerly about 2,340 miles 
and empties into the Gulf of Mexico. Portion included in 
this report embraces the 195-mile section known as 
middle Mississippi, between tributary Ohio and Missouri 
Rivers about 974 to 1,169 miles from the gulf. See 
folder by Corps of Engineers of Navigation Charts, 
Middle and Upper Mississippi River, Cairo, IL, to 
Minneapolis, MN. 
Previous projects. For details see page 1879 of 
Annual Report for 1915, and page 1014 of Annual 
Report for 1938. 
Existing project. The existing project provides for 
obtaining and maintaining a minimum channel depth 
of not less than 9 feet, a minimum width of not less than 
300 feet at low water, with additional widths in bends 
from mouth of Ohio River (about 974 miles from gulf) to 
northern boundary of city of St. Louis, mile 191, thence 
200 feet wide, with additional width in bends to mouth 
of Missouri River, mile 195; to be obtained: (1) by 
regulating works, for closing secondary channels, contracting 
river by building new banks where river width 
is excessive and protecting new and old banks from 
erosion where necessary to secure permanency at an 
estimated total Federal cost (1983) of $186,000,000. (2) 
by dredging to maintain project channels; (3) by construction 
of works authorized for Chain of Rocks reach 
in 1945 River and Harbor Act, which approved a 
comprehensive plan for development of the river at 
Chain of Rocks to provide for construction of a lateral 
canal at a cost of $59,720,600; and (4) by construction of 
a fixed-crest rock-fill dam about 900 feet below Chain of 
Rocks Bridge, authorized by 1958 River and Harbor 
Act, at cost of $4,353,000, excluding $7,000 costs to 
Coast Guard for aids to navigation. Estimated total 
Federal project cost (1983) is $250,073,600. A small boat 
harbor opposite Chester, IL, was deauthorized and 
excluded from foregoing cost estimate. See H. Doc. 669 
(76th Cong., 3d sess.) for report of Chief of Engineers 
dated Feb. 27, 1940, containing a general plan for 
improvement of Mississippi River between Coon Rapids 
Dam and mouth of Ohio River for purposes of navigation, 
power development, flood control, and needs of 
irrigation. 
Local cooperation. None required. 
Terminal facilities. Existing facilities are considered 
adequate for existing commerce. 
Operations and results during fiscal year. Regulating 
Works: Contract was continued on stone dike 
and revetment construction as was engineering and 
design and supervision and administration. Construction 
on existing project began in 1881 and project has 
been in beneficial use practically from its inception. 
Projects on Dam 27 and Chain of Rocks are complete. 
Work on the project is about 65 percent complete. 
Channel as a whole has been greatly improved by the 
work completed to date. Dredging is required at low 
stages to remove temporary shoals and maintain required 
channel depths. River is generally above 10-foot 
stage, St. Louis gage, from latter part of February to 
the latter part of August, during which time project 
channel depths generally prevail without dredging. 
Maintenance. Work consisted of 6,575 feet of dike 
and 8,856 feet of revetment repair. U.S. plant and hired 
labor performed channel dredging at 18 locations, 
14-2

ST. LOUIS, MO, DISTRICT 
removing 4,900,000 cubic yards of material from main 
channel. Channels dredged had a combined length of 
11.4 miles, an average width of 290 feet, and an average 
gain in depth of 6 feet. Condition and operation studies, 
recreation planning, engineering and design, and 
operation and maintenance of Lock and Dam 27 
continued. 
Flood Control 
5. EAST ST. LOUIS AND VICINITY, IL 
. Location. Project is in St. Clair and Madison 
Counties, IL, on the left bank of the Mississippi River 
between river miles 175 and 195 above the Ohio River. 
Project includes all bottomlands between bluffs on the 
east and Mississippi River and Chain of Rocks Canal on 
the west, and extends from Cahokia diversion channel 
on the north to Prairie du Pont Creek on the south. (See 
Corps of Engineers Navigation Charts, Middle and 
Upper Mississippi River, Cairo, IL, to Minneapolis, 
MN.) 
Existing project. The 1936 Flood Control Act 
authorized raising and enlarging existing levee systems 
by construction or reconstruction of 19.8 miles of levee, 
including 3.1 miles of floodwall, together with necessary 
appurtenant works consisting of gravity drainage 
structures, highway and railroad closure structures, 
alterations and reconstruction of existing pumping 
plants, alterations to railroad bridges and approaches 
at levee crossings, service roads on levee crown, and 
seepage control measures. Work under this authorization 
provides the area protection against a flood of about 
200-year frequency. The completed 10 miles of levee 
along Chain of Rocks Canal and Lock 27 provide flood 
protection on the landward side integral with and to the 
same degree as the East St. Louis levee. Final cost of 
work under this authorization is $22,550,100. The Flood 
Control Act of 1965 modified existing project to provide 
for channel improvements, diversion ditches, flood 
plain detention areas, a reservoir on Little Canteen 
Creek, and a pumping plant to considerably reduce 
damages resulting from interior flooding. This act also 
authorized reconstruction of a channel stabilization 
dam in Cahokia Creek diversion channel to provide 
protection to adjacent levees and bridges from scour 
and eventual loss. Estimated total Federal project cost 
of work under this authorization is $34,900,000 (1983), 
$22,020,000 for Cahokia-Harding Ditch Area, and 
$12,880,000 for Blue Waters Ditch. Non-Federal cost is 
$20,760,000. 
Local cooperation. Local interests have fully complied 
with the requirements of local cooperation for 
work under the 1936 authorization. For work authorized 
by Flood Control Act of 1965 requirements of local 
cooperation are fully described on page 14-4 of Fiscal 
Year 1980 Annual Report. Formal assurances were 
accepted on the Blue Waters Ditch area on Jun. 25, 1981. 
Formal assurances for the Cahokia-Harding Areas will 
be requested upon approval of the plan of improvement 
currently scheduled after FY 88, due to lack of funding 
for FY 84 through FY 88. 
Operations and results during fiscal year. Planning 
was continued on project modifications authorized 
by Flood Control Act of 1965 and construction was 
continued on ditching contracts. Work authorized by 
Flood Control Act of 1936 is complete. 
6. ELDRED AND SPANKEY DRAINAGE, 
AND LEVEE DISTRICT, IL 
Location. The levee district is in Greene County, Ii, 
on the left bank of the Illinois River between miles 23.8 
and 32.3 above the Mississippi River. (See Quincy, ILMO, 
sheet of maps of the United States, published by 
Army Map Service, scale 1:250,000.) 
Existing project. Project provides for raising and 
enlarging 15.9 miles of levees, altering discharge line of 
pumping station, and construction of two highway 
closure structures and seepage control measures. 
Project will provide protection to 10,470 acres of land, 
9,735 of which are highly productive agricultural lands, 
against a flood of 50-year frequency. Estimated total 
Federal project cost (1983) is $6,000,000. Non-Federal 
cost is $940,000. Project was authorized by the 1962 
Flood Control Act (H. Doc. 472, 87th Cong., 2nd sess.). 
Local cooperation. Requirements of local cooperation 
are fully described on page 14-4 of Fiscal Year 1980 
Annual Report. Local interests have indicated a willingness 
to meet the terms of local cooperation. 
Operations and results during fiscal year. Preconstruction 
planning was continued under the general 
investigation appropriation. Construction has not 
begun. 
7. HARTWELL DRAINAGE AND 
LEVEE DISTRICT, IL 
Location. The levee district is in Greene County on 
the left bank of the Illinois River between miles 38.2 and 
43.1 above the Mississippi River. (See Quincy, IL-MO, 
sheet of maps of the United States, published by Army 
Map Service, scale 1:250,000.) 
Existing project. Project provides for construction 
of 12.3 miles of new or enlarged levees, altering discharge 
line of pumping station and construction of 
seepage control measures. Project will provide protection 
to 9,630 acres of land, 8,955 of which are highly 
productive agricultural lands against a flood of 50-year 
frequency. Estimated total Federal project cost (1983) 
is $11,600,000. Non-Federal cost is $1,120,000. Project 
was authorized by the 1962 Flood Control Act (H. Doc. 
472, 87th Cong., 2d sess.) 
Local cooperation. Requirements of local cooperation 
are fully described on page 14-5 of Fiscal Year 1980 
Annual Report. Local interests have indicated a willingness 
to meet the terms of local cooperation. 
Operations and results during fiscal year. Preconstruction 
planning was continued under the general 
investigation appropriation. Construction has not 
begun. 
14-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
8. HILLVIEW DRAINAGE AND 
LEVEE DISTRICT, IL 
Location. The levee district is in Greene and Scott 
Counties, IL, on the left bank of the Illinois River 
between miles 43.2 and 50.0 above the Mississippi 
River. (See Qunicy, IL-MO, sheet of maps of the United 
States, published by Army Map Service, scale 
1:250,000.) 
Existing project. Project provides for construction 
of 14.3 miles of levee, alteration of discharge lines for 
three existing pumping stations, construction of a 
railroad closure structure, and seepage control measures. 
Project will provide protection the the Village of 
Hillview and to 13,070 acres of agricultural land against 
a flood of 50-year frequency. Estimated total Federal 
project cost (1983) is $11,500,000. Non-Federal cost is 
$1,220,000. Project was authorized by the 1962 Flood 
Control Act (H. Doc. 472, 87th Cong., 2d sess.) 
Local cooperation. Requirements of local cooperation 
are fully described on page 14-6 of Fiscal Year 1980 
Annual Report. Local interests have indicated a willingness 
to meet the terms of local cooperation. 
Operations and results during fiscal year. Preconstruction 
planning was continued under the general 
investigation appropriation. Construction has not 
begun. 
9. KASKASKIA ISLAND 
DRAINAGE AND LEVEE 
DISTRICT, IL 
Location. In Randolph County, IL, on the right bank 
of the Mississippi River between miles 111 and 116 
above the mouth of the Ohio River. (See Paducah, KY, 
IL, MO, IN, map published by Army Map Service, scale 
1:250,000.) 
Previous project. For details, see page 1375 of 
Annual Report for 1950. 
Existing project. Project area contains about 9,460 
acres only partially protected against flood stage of 38.5 
feet on the Chester, IL, gage. Flooding occurs about 
once in every 7.3 years with an average duration of 26 
days, causing substantial damage. The 1962 Flood 
Control Act (H. Doc. 519, 87th Cong., 2d sess.) provides 
for enlarging and raising the existing levee about 8 feet 
to provide protection against a flood having a frequency 
of once in 50 years. Estimated total Federal project cost 
(1983) is $15,700,000. Non-Federal cost is $2,080,000. 
Local cooperation. Requirements of local cooperation 
are fully described on page 14-6 of Fiscal Year 1980 
Annual Report. Formal assurances from the Kaskaskia 
Island Drainage and Levee District were accepted on 
behalf of the United States on Jan. 23, 1980. 
Operations and results during fiscal year. Preconstruction 
planning is complete. Construction was 
completed on the gravity drains. Plans and specifications 
for raising and enlarging the levee are complete 
and construction will be initiated in the near future. 
10. MERAMEC RIVER BASIN, MO 
Location. The basin lies within the State of Missouri 
and comprises 3,980 square miles. The river is a west 
bank tributary of the Mississippi River at mile 161 
above mouth of Ohio River. Major streams in the basin 
include the Meramec, Big, and Bourbeuse Rivers. The 
basin extends about 100 miles southwesterly from St. 
Louis into the Ozark Highlands. (See St. Louis, MO, and 
Rolla sheets of maps of the United States, published by 
Army Map Service, scale 1:250,000.) 
Existing project. The project provides for the construction 
of Meramec Park and Union Lakes, authorized 
by the 1938 Flood Control Act; and Pine Ford, 
Irondale, and 1-38 Lake projects, and 19 angler-use 
sites, authorized by the 1966 Flood Control Act. Under 
the plan, Irondale and 1-38 Lakes will reduce flood 
damages in the upper Big and Bourbeuse Rivers. 
Meramec Park, Union, and Pine Ford Lakes will 
substantially reduce flooding in the lower basin area 
and will lower flood crests on the Mississippi River. 
Project will also provide water supply, water quality 
control, recreation, and fish and wildlife conservation. 
(See Table 14-D for additional data on this comprehensive 
project.) 
10A. MERAMEC PARK LAKE, MO 
Location. Dam will be at mile 108.7 on Meramec 
River in Franklin County near Sullivan, MO. Reservoir 
will be mainly in Crawford, Franklin, and Washington 
counties, MO. (See St. Louis, MO, sheet of maps of the 
United States, published by Army Map Service, scale 
1:250,000.) 
Existing project. Project as authorized by 1938 
Flood Control Act provides for construction of an earth 
dam about 167 feet high with a crest length of 3,000 feet. 
Reservoir will provide 1 million acre-feet of storage and 
provide flood protection for 11,862 acres of flood plain in 
the Meramec River valley above the mouth of Bourbeuse 
River, and partial protection for 20,209 acres of 
land below the Bourbeuse. Project will also provide 
water supply, water quality control, storage, and 
recreation, and fish and wildlife benefits. Estimated 
total project cost (1981) is $220,000,000, including 
$22,506,000 local reimbursement for water supply. 
Local cooperation. Local interest must contribute 
toward cost of project for storage allocated to water 
supply in accordance with the Water Supply Act of 
1958. State of Missouri, acting through its State Water 
Resources Board and under authority of the General 
Assembly of State of Missouri, executed assurances for 
water supply on Aug 23, 1967. The assurances were 
reviewed by the Office of the Attorney General, State of 
Missouri, and it is his opinion that the State of Missouri 
has the legal authority and financial capability to 
execute said assurances. These assurances have been 
approved by the Chief of Engineers. A water-supply 
contract will be entered into with the sponsor before any 
use of the water-supply storage provided under this 
contract. 
14-4

ST. LOUIS, MO, DISTRICT 
Operations and results during fiscal year. Project 
was deauthorized by Public Law 97-128. Land is being 
disposed of in accordance with deauthorizing act. 
Maintenance. Hired labor forces performed operations 
and maintenance of existing facilities. 
10B. PINE FORD LAKE, MO 
Location. Dam is on Big River at mile 43.8, about 45 
miles southwest of St. Louis. The Big River is a tributary 
of the Meramec. Lake will extend about 34 miles up 
Big River. (See St. Louis, MO, sheet of maps of the 
United States, published by Army Map Service, scale 
1:250,000.) 
Existing project. Project provides for construction 
of a compacted earth-fill dam with a concrete chute 
spillway. Dam will be 141 feet high and 2,070 feet long. 
Construction of new roads, improvements of existing 
roads, alterations to pipeline, power and telephone 
lines, and construction of recreational facilities are 
included. Maximum storage capacity will be 285,000 
acre-feet. Estimated total project cost (1981) is 
$133,000,000, of which $7,394,800 and $20,801,200 are 
local reimbursements for water supply and recreation 
and fish and wildlife respectively. 
Local cooperation. Local interests must contribute 
toward cost of project for storage allocation to water' 
supply in accordance with the Water Supply Act of 
1958. The State of Missouri demonstrated sufficient 
interest and approval of the basin plan to warrant the 
assumption at this time that necessary local cooperation 
will be forthcoming. 
Operations and results during fiscal year. Preconstruction 
planning continued. The project is being 
reformulated. Construction has not begun. 
11. MCGEE CREEK DRAINAGE 
AND LEVEE DISTRICT, IL 
Location. The levee district is in Brown and Pike 
Counties, IL, on the right bank of Illinois River between 
miles 67.2 and 75.1 above the Mississippi River. (See 
Kansas City sheet of maps of United States, published 
by Army Map Service, scale 1:500,000.) 
Existing project. Project provides for reconstruction 
of 14.7 miles of levee, construction of a new pumping 
plant, closure structure, and seepage control measures. 
Project will provide protection to about 12,080 acres of 
agricultural land against a flood of about 50-year 
frequency. Estimated total Federal project cost (1983) 
is $25,500,000. Non-Federal cost is $930,000. Project 
was authorized by 1962 Flood Control Act (H. Doc. 472, 
87th Cong., 2d sess.). 
Local cooperation. Requirements of local cooperation 
are fully described on page 14-9 of Fiscal Year 1980 
Annual Report. Local interests have executed assurances 
in compliance with Public Law 91-611 and Public 
Law 91-646. 
Operations and results during fiscal year. Preconstruction 
planning is complete. The pumping station, 
the riverfront levee and the lower part of the lower 
flank levee are under construction. Construction is 
complete on the upper flank levee, and will be initiated 
in the near future on remainder of the lower levee. 
12. MEREDOSIA, IL, AND MEREDOSIA, 
WILLOW CREEK, AND 
COON RUN DRAINAGE AND 
LEVEE DISTRICTS, IL 
Location. The levee district is in Morgan and Scott 
Counties, IL, on the left bank of the Illinois River 
between miles 67.0 and 72.2 above the Mississippi 
River. (See Quincy, IL-MO sheet of maps of the United 
States, published by Army Map Service, scale 
1:250,000.) 
Existing project. Project provides for construction 
of 11.0 miles of new or enlarged levee, a pumping plant, 
closure structure, and seepage control measures. Project 
will provide protection to 8,215 acres of land, 7,640 
of which are highly productive agricultural lands, and 
575 acres of noncrop and farmsteads against a flood of 
50-year frequency. Estimated total Federal project 
cost (1983) is $11,200,000. Non-Federal cost is 
$1,030,000. Project was authorized by the 1962 Flood 
Control Act (H. Doc. 472, 87th Cong., 2d sess.). 
Local cooperation. Requirements of local cooperation 
are fully described on page 14-9 of Fiscal Year 1980 
Annual Report. Local interests have indicated a willingness 
to meet the terms of local cooperation. 
Operations and results during fiscal year. Preconstruction 
planning was continued under the general 
investigation appropriation. Construction has not 
begun. 
13. MEREDOSIA LAKE AND WILLOW 
CREEK DRAINAGE AND 
LEVEE DISTRICT, IL 
Location. The project is in Cass and Morgan Counties, 
IL, on the left bank of the Illinois River between 
miles 72.2 and 79.0 above the Mississippi River. (See 
Qunicy, IL-MO sheet of maps of the United States, 
published by Army Maps Service, scale 1:250,000.) 
Existing project. Project provides for construction 
of 15.9 miles of new or enlarged levee, closure structure, 
drainage facilities, and seepage control measures. 
Project will provide protection to 7,510 acres of land, 
6,980 of which are highly productive agricultural lands, 
and 530 acres of noncrop and farmsteads against a flood 
of 50-year frequency. Estimated total Federal project 
cost (1983) is $9,300,000. Non-Federal cost is $560,000. 
Project was authorized by the 1962 Flood Control Act 
(H. Doc. 472, 87th Cong., 2d sess.). 
Local cooperation. Requirements of local cooperation 
are fully described on page 14-10 of Fiscal Year 
1980 Annual Report. Local interests have indicated a 
willingness to meet the terms of local cooperation. 
Operations and results during fiscal year. Preconstruction 
planning was continued under the general 
investigation appropriation. Construction has not 
begun. 
14-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
14. MISSISSIPPI RIVER AGRICULTURAL 
AREA 8, MO 
Location. Area 8 is in Lincoln and Pike Counties, 
MO, on west bank of Mississippi River between river 
miles 249 and 261 above the Ohio River. Small community 
of Elsberry lies within the area. (See Quincy 
sheet of maps of the United States, published by Army 
Map Service, scale 1:250,000.) 
Existing project. The 1966 Flood Control Act (H. 
Doc. 510, 89th Cong., 2d sess.) authorized the raising 
and enlarging of existing levees to provide 24.4 miles of 
riverfront, flank, and back levees and construction of 
appurtenant works consisting of drainage structure, 
highway and railroad closure structures, and alterations 
to existing pumping plants. The project has been 
reduced in scope to consist of replacing one existing 
drainage structure, replacing an obsolete stream driven 
pump unit with a new one of 150 cubic feet per second 
capacity, and rehabilitation of the pump station. Project 
will afford protection to the area against a flood of 
50-year frequency. Estimated total Federal project cost 
(1980) is $2,400,000. Non-Federal cost is $20,000. 
Local cooperation. Fully complied with. See page 
14-10 of FY 1980 Annual Report. 
Operations and results during fiscal year. Local 
interests have been reimbursed under Sec. 215, Public 
Law 90-483, for cost they incurred for pumping plant 
improvement. Construction of gravity drain and 
pumping station rehabilitation is complete. Operation 
and maintenance manual is being prepared. 
15. NUTWOOD DRAINAGE AND 
LEVEE DISTRICT, IL 
Location. The levee district is in Greene and Jersey 
Counties, IL, on the left bank of the Illinois River 
between miles 15.2 and 23.7 above the Mississippi 
River. (See Quincy, IL-MO, sheet of maps of the United 
States, published by Army Map Service, scale 
1:250,000.) 
Existing project. Project provides for raising and 
enlarging 11.4 miles of levee, construction of 1.0 mile of 
new levee, altering discharge line of pumping station, 
and construction of seepage control measures. Project 
will provide protection to 10,360 acres of land, 9,635 of 
which are highly productive agricultural lands against 
a flood of 50-year frequency. Estimated total Federal 
project cost (1982) is $9,000,000. Non-Federal cost is 
$840,000. Project was authorized by the 1962 Flood 
Control Act (H. Doc. 472, 87th Cong., 2d sess.). 
Local cooperation. Requirements of local cooperation 
are fully described on page 14-11 of Fiscal Year 
1980 Annual Report. Local interests have indicated a 
willingness to meet the terms of local cooperation. 
Operations and results during fiscal year. Preconstruction 
planning was continued under the general 
investigation appropriation. Construction has not 
begun. 
16. PERRY COUNTY DRAINAGE 
AND LEVEE DISTRICTS 
NOS. 1,2, & 3, MO 
Location. Districts are in Perry County, MO, and 
Randolph County, IL, on the right bank of the Mississippi 
River between river miles 95 and 111 above the 
mouth of the Ohio River. (See Paducah, KY, IL, MO, IN, 
map published by Army Map Service, scale 1:250,000.) 
Previous project. For details, see page 475 of Annual 
Report for 1968. 
Existing project. Project area contains about 26,881 
acres protected from floods of the Mississippi River by 
levees. However, when Mississippi River stage exceeds 
13 feet on the Chester, IL, gage, substantial damage 
results from impoundment of precipitation or seepage, 
or a combination thereof. Authorized project provides 
for construction of four pumping stations to reduce 
interior flooding. Estimated total Federal project cost 
(1982) is $8,812,000. 
Local cooperation. Requirements of local cooperation 
are fully described on page 14-11 of Fiscal Year 
1980 Annual Report. Assurances were furnished by 
local interests (presently, Boil Brule Levee District, 
MO). on Nov. 16,1978, and were accepted Nov. 27, 1978, 
by the District Engineer under delegated authority. 
Operations and results during fiscal year. Construction 
was continued on Missouri Chute and Bois 
Brule pumping stations and is complete on the Cinque 
Hommes and Jones Cutoff stations. 
17. REND LAKE, BIG MUDDY 
RIVER, IL 
Location. The lake is in Franklin and Jefferson 
Counties in southern Illinois. The dam is on Big Muddy 
River, 103.7 miles upstream from its confluence with 
the Mississippi River, and about 3 miles northwest of 
Benton, IL. (See Belleville sheet of maps of United 
States, published by Army Map Service, scale 1:250,000, 
and Geological Survey quadrangle maps, 1:62,500.) 
Existing project. The project provides for construction 
of an earth dam, ungated concrete spillway, 
relocation of roads and utilities, recreational facilities, 
access roads, and service facilities. In addition, two 
subimpoundment dams were constructed on upper 
arms of reservoir to enhance fish and wildlife value of 
project. Reservoir has an area of 24,800 acres, and a 
storage capacity of 294,000 acre-feet. Project provides 
flood control, water supply, low-flow regulations, conservation 
of fish and wildlife, recreation, and area 
development. Estimated total Federal project cost 
(1983) is $43,100,900, of which $12,197,700 is for lands 
and damages. Non-Federal local contribution for water 
supply is $9,941,300. Federal cost for code 711 recreation 
facilities is $1,060,900. 
Local cooperation. Requirements of local cooperation 
are fully described on page 14-12 of Fiscal Year 
1980 Annual Report. Assurance of local cooperation 
14-6

ST. LOUIS, MO, DISTRICT 
and water supply contract have been executed and 
approved by the Secretary of the Army. 
Operations and results during fiscal year. Real 
estate activities in connection with project completion 
were performed. Lands acquired to date are 39,819 
acres in fee and 906 acres in easements. Project is 
essentially complete. 
Maintenance. Hired labor forces performed operation 
and maintenance of Rend Lake Reservoir. 
18. WOOD RIVER DRAINAGE AND 
LEVEE DISTRICT, IL 
Location. In Madison County, IL, on left bank of 
Mississippi River between river miles 195 and 203 
above Ohio River. District includes bottom lands between 
river and bluffs and extends from Cahokia 
diversion channel on the south to opposite lock and dam 
No. 26 at Alton, IL, on the north. Small industrial cities 
of Hartford, Wood River, Roxana, and East Alton and 
part of Alton riverfront, lie within the district. (See 
Corps of Engineers Navigation Charts, Middle and 
Upper Mississippi River, Cairo, IL, to Minneapolis, 
MN.) 
Existing project. The 1938 Flood Control Act authorized 
raising, enlarging, and extending existing levee 
system to provide 20.8 miles of levees and construction 
of appurtenant works consisting of gravity drainage 
structures, highway and railroad closure structures, 
alterations to existing or construction of new pumping 
plants; surfacing service road on levee crown, making 
necessary alterations to railroad tracks and bridges at 
levee crossings, seepage corrective measures and construction 
of a low-water dam at mouth of Wood River. 
Project will afford protection to this district against a 
flood of about 200-year frequency. Estimated total 
construction cost (1982) is $18,600,000 (excluding 
$23,000 contributed funds). Flood Control Act of 1965 
modified 1938 Flood Control Act to provide for construction 
of a pumping station with collector ditches 
and necessary appurtenant facilities for removal of 
water impounded by existing levee. This portion of the 
project has been declared inactive. 
Local cooperation. Fully complied with for work 
authorized by 1938 Flood Control Act. 
Operations and results during fiscal year. Work 
authorized by the 1938 Flood Control Act is complete 
except for 1200 feet of levee and two closure structures. 
Design of these items is progressing. Construction has 
not begun. 
19. INSPECTION OF COMPLETED 
FLOOD PROJECTS CONTROL 
Inspection of completed work was accomplished at a 
cost of $382,962 for the fiscal year. Total cost as of end of 
fiscal period is $4,555,088. 
20. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation activities pursuant to Sec. 107, Public 
Law 86-645, as amended (preauthorization). 
Preauthorization studies cost for fiscal year were 
$85,307 for Southeast Missouri Port study. 
21. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control activities pursuant to Sec. 
205, Public Law 858, 80th Cong., as amended 
(preauthorization). 
Preauthorization study costs for fiscal year were 
$2,013 for East Cape Girardeau Main Ditch, IL; $7,500 
for Kaskaskia River, Carlyle, IL; and $5,943 for St. 
Peters, MO. 
Emergency flood control activities-repair, flood 
fighting, and rescue work (Public Law 99, 84th 
Cong., and antecedent legislation). 
Federal costs for the fiscal year were $102,258 for 
disaster preparedness, $2,768,435 for emergency operations, 
and $278,265 for rehabilitation. 
Multiple-Purpose Project 
Including Power 
22. CLARENCE CANNON DAM AND 
RESERVOIR, SALT RIVER, MO 
Location. Salt River rises in Schuyler County, about 
12 miles south of Missouri-Iowa State line. It flows 
southeasterly about 192 miles and empties into Mississippi 
River about 2 miles above Louisiana, MO, or 
about 284 miles above mouth of Ohio River. (See Kansas 
City and Quincy sheets of maps of United States 
published by Army Map Service, scale 1:500,000, and 
Geological Survey quadrangle maps, 1:250,000.) 
Previous project. For details, see page 645 of Annual 
Report for 1968. 
Existing project. Project provides for construction 
of a multiple-purpose reservoir, including power, flood 
control, water supply, navigation storage, pollution 
abatement, fish and wildlife conservation, and recreation. 
Dam consists of a compacted earth embankment 
with a concrete spillway controlled by tainter gates. 
Dam and spillway are about 1,700 feet long. Spillway 
structure consists of an ogee overflow section surmounted 
by four 50- by 30-foot tainter gates. Reservoir 
will have a storage capacity of 1,428,000 acre-feet for 
use of flood control, future domestic and industrial 
water supply, sediment storage, and power generation. 
Project document plan provides for installation of two 
27,000 kilowatt units, one conventional and one reversible, 
to be used for pumped storage operations. Total 
Federal project cost estimate (1983) is $326,000,000 of 
which $21,320,000 is for lands and damages, and 
$14,200,000 is for water supply. 
14-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Local cooperation. Requirements of local cooperation 
are fully described on page 14-13 of Fiscal Year 
1980 Annual Report. Assurances have been received 
from the State of Missouri and approved by the Chief of 
Engineers. 
Operations and results during fiscal year. Major 
items of work completed during the fiscal year consisted 
of sluice closure operations in August 1983 and 
topping out the main embankment in September 1983. 
The county highway relocations were essentially 
completed. Remaining work consists of completing the 
state highway relocation across the main dam, installing 
the microwave system to the Harry S. Truman 
project, final testing of the two hydropower turbines 
and generators, completion of electrical service to 
existing recreation areas, and purchase of remaining 
permanent operating equipment. Lands acquired to 
date are 55,277 acres in fee and 10,049 acres in 
easements. Project is 95 percent complete. 
General Investigations 
23. ACTIVE INVESTIGATIONS 
See Table 14-F which covers: Surveys, Collection and 
study of basic data, and Research and development 
activities. 
14-8

TABLE 14-A 
ST. LOUIS, MO, DISTRICT 
COST AND FINANCIAL STATEMENT 
See 
Section Total Funds to 
in Text Project Funding FY 80 FY 81 FY 82 FY 83 Sep. 30, 1983 
2. Kaskaskia River New Work 
IL (Regular 
Funds) 
(Contrib. Funds) 
4. Mississippi River 
Between Ohio and 
Missouri Rivers 
(Includes Chain 
of Rocks) 
5. East St. Louis and 
Vicinity, IL 
6. Eldred & Spankey 
Drainage and Levee 
District, IL 
7. Hartwell Drainage 
& Levee District, 
IL 
8. Hillview Drainage 
& Levee District 
IL 
9. Kaskaskia Island 
Drainage & Levee 
District, IL 
10A. Meramec Park 
Lake, MO 
10B. Pine Ford 
Lake, MO 
11. McGee Creek 
Drainage & 
Levee District, 
IL 
12. Meredosia, IL, 
and Meredosia, 
Willow Creek and 
Coon Run Drainage 
& Levee Districts, 
IL 
13. Meredosia Lake 
and Willow Creek 
Drainage & Levee 
District, IL 
14. Mississippi River 
Agricultural Area 
No. 8, IL 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
$5,000,000 
5,009,434 
779,400 
710,908
00 
3,450,000 
3,838,008 
9,017,900 
9,675,719 
580,000 
699,638 
105,000 
100,453 
230,000 
156,347 
190,000 
193,215 
400,000 
366,150
0 
63,716 
185,000 
178,516 
550,000 
447,699 
975,000 
746,149 
150,000 
124,026 
170,000 
122,351 
106,000 
95,295 
$3,635,000 
3,478,872 
929,000 
1,025,322
00 
3,075,000 
3,051,785 
9,121,000 
8,919,608 
725,000 
432,485 
400,000 
369,419 
250,000 
190,624 
183,000 
147,733 
1,363,000 
1,160,083
0 
63,796 
287,000 
271,948 
545,000 
521,842 
5,600,000 
5,110,855 
180,000 
151,945 
140,000 
67,865 
760,000 
763,571 
$1,800,000 
1,883,090 
1,200,000 
973,968
0 
42,000 
2,000,000 
1,759,811 
9,269,000 
8,443,093 
275,000 
515,776
0 
64,620
0 
137,251
0 
58,771 
725,000 
797,320
0 
28,285 
567,000 
415,026 
15,000 
120,033 
2,285,000 
1,134,848
0 
70,166 
-15,000 
121,430 
172,000 
173,441 
$400,000 
388,140 
1,131,856 
1,036,248
00 
2,437,000 
1,574,639 
8,010,656 
10,191,370 
950,000 
1,011,724
00 
0 
10,021
0 
572 
500,000 
375,659
0 
-42,325 
595,000 
670,277
0 
-5,815 
8,012,900 
8,793,102
0 
1,408
0 
845
0 
6,190 
$122,591,0001 
122,480,1001 
8,402,256 
8,050,988 
1,244,078 
1,118,160 
164,156,0002 
162,839,5432 
185,657,1338 
185,314,6238 
31,572,3884 
31,483,725b 
875,000 
875,000 
622,000 
622,000 
433,000 
433,000 
3,943,000 
3,562,282 
30,568,0006 
30,462,6646 
2,384,600 
2,272,156 
3,680,001 
3,642,573 
17,720,300 
16,628,560 
370,000 
370,000 
345,000 
345,000 
2,137,000 
2,127,133 
14-9

TABLE 14-A 
(Continued) 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
COST AND FINANCIAL STATEMENT 
See 
Section Total Funds to 
in Text Project Funding FY 80 FY 81 FY 82 FY 83 Sep. 30,1983 
15. Nutwood Drain- New Work 
age & Levee Approp. 180,000 295,000 0 0 670,000 
District, IL Cost 159,354 267,610 50,079 8,993 669,880 
16. Perry County New Work 
Drainage & Levee Approp. 1,347,000 1,944,000 1,558,000 1,503,000 8,223,0007 
District Nos. 1, Cost 1,551,162 1,845,151 943,491 1,807,562 7,654,4957 
2, & 3, MO 
17. Rend Lake, Big New Work 
Muddy, (RegularI L Approp. $ 0 $ 0 $ 0 0 43,700,9008 Funds) Cost -18,714 2,104 19,141 81,753 43,593,766 
Maint. 
Approp. 1,861,000 1,500,000 2,203,000 2,537,900 15,458,800 
Cost 1,904,092 1,656,264 2,107,010 2,533,327 15,235,847 
Code 711 Funds New Work 
CAopspt rop. 318,000 0 0 0 1,060,900 412,636 16,375 0 0 1,060,900 
(Contrib. Funds) New Work 
Contrib. 0 0 0 0 9,941,2789 
Cost 2 0 0 0 9,941,2789 
Maint. 
Contrib. 400,000 400,000 0 0 2,581,955 
Cost 385,879 416,656 140 0 2,581,955 
18. Wood River New Work 
Drainage & Levee Approp. 0 225,000 285,000 450,000 15,589,8210 
District, IL Cost 0 93,322 354,171 386,143 15,463,4580 
22. Clarence Cannon New Work 23,123,000 20,950,000 23,500,000 33,849,700 297,336,728" 
Dam and Reservoir, Approp. 23,758,152 19,196,644 24,029,076 34,463,424 295,996,788 
Salt River, MO Cost 
Maint. 
Approp. 1,228,500 917,000 1,426,000 1,891,100 6,816,560 
Cost 1,032,809 1,080,977 1,285,921 1,937,491 6,636,910 
1. Excludes $10,461 expended on previous project. 
2. Excludes previous project cost of $1,416,620. 
3. In addition $3,109 was expended for rehabilitation. 
4. Includes $8,072,326 for work authorized by Flood 
Control Act of 1965. 
5. Includes $7,921,939 for work authorized by Flood 
Control Act of 1965. 
6. Includes $200,000 for definite project under 1938 
Flood Control Act. 
7. Excludes $6,800,700 for previous project. 
8. Excludes $550,000 Area Development Administration 
Funds allotted to the State of Illinois for increased 
construction costs of Interstate Highway 57 to meet project 
requirements, and excludes $449,093 Area Redevelopment 
Administration Funds allotted to the Corps. 
9. Includes $6,103,711 credit to State of Illinois for 
work in kind. 
10. Funds are for work authorized by Flood Control Act 
of 1938. 
11. Includes $216,628 for definite project study under 
1938 Flood Control Act. 
14-10

ST. LOUIS, MO, DISTRICT 
TABLE 14-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Oct. 23, 1962 
Jun. 3, 1896 
Jun. 13, 1902 
Mar. 2, 1907i 
Mar. 3, 1905i 
Jun. 25, 1910 
Jan. 21, 1927 
Jul. 3, 1930 
Mar. 2, 1945 
Sep. 3, 19543 
Jul. 3, 19584 
Jun. 22, 1936 
Oct. 27, 1965 
Oct. 22, 1976 
Oct. 23, 1962 
Oct. 23, 1962 
Oct. 23, 1962 
Oct. 23, 1962 
Jun. 28, 1938 
Nov. 7, 1966 
KASKASKIA RIVER, IL (See Section 2 of Text) 
Construct canal, lock, and dam to provide a 9-foot navigation 
channel from mouth to Fayetteville, IL. 
MISSISSIPPI RIVER BETWEEN OHIO AND MISSOURI 
RIVERS (See Section 4 of Text) 
Project for regulating works in 1881. (To obtain a minimum 
depth of 8 feet.) 
Dredging introduced as part of the project. 
These acts practically abrogated that part of project for middle 
Mississippi which proposed regulating works. 
Regulating works restored to project and appropriations begun 
with a view to completion of improvement between Ohio and 
Missouri Rivers within 12 years at an estimated cost of $21 
million, exclusive of amounts previously expended. 
For 9 feet deep and 300 feet wide from Ohio River to northern 
Rivers and Harbors boundary of city of St. Louis. 
Project between northern boundary of St. Louis and Grafton 
(mouth of Illinois River) modified to provide a channel 9 feet 
deep and generally 200 feet wide with additional width around 
bends. 
Modified to provide construction of a lateral canal with lock at 
Chain of Rocks. 
Modified to provide construction of a small-boat harbor opposite 
Chester, IL. 
Modified to provide construction of a fixed crest rockfill dam 900 
feet below Chain of Rocks Bridge. 
EAST ST. LOUIS AND VICINITY, IL (See Section 5 of Text) 
Raise and enlarge existing levee. 
Construct pumping plant and other modifications to reduce 
interior flooding. 
Construct Blue Waters Ditch as independent section. 
ELDRED AND SPANKEY DRAINAGE AND LEVEE 
DISTRICT, IL (See Section 6 of Text) 
Raise and enlarge existing levee and other modifications. 
HARTWELL DRAINAGE AND LEVEE DISTRICT, IL 
(See Section 7 of Text) 
Raise and enlarge existing levee and other modifications. 
HILLVIEW DRAINAGE AND LEVEE DISTRICT, IL (See 
Section 8 of Text) 
Raise and enlarge existing levee and other modifications. 
KASKASKIA ISLAND DRAINAGE AND LEVEE 
DISTRICT, IL (See Section 9 of Text) 
Raise and enlarge existing levee. 
MERAMEC RIVER BASIN, MO (See Section 10 of Text) 
Construct reservoirs and local protection project. 
Construct Pine Ford, Irondale, and 1-38 dams and 19 Angler-use 
sites. 
S. Doc. 44, 87th Cong., 1st 
sess. 
Annual Report, 1881, p. 
1536. 
Committee Doc. 9, 69th 
Cong., 2d sess. 
Rivers and Harbors 
Committee Doc. 12, 70th 
Cong., 1st sess. 
H. Doc. 231, 76th Cong., 1st 
sess. 
H. Doc. 230, 83d Cong., 1st 
sess. 
Special report on record in 
OCE. 
H. Doc. 329, 88th Cong., 2d 
sess. 
Public Law 94-587, 94th 
Cong. 
H. Doc. 472, 87th Cong., 2d 
sess. 
" 
H. Doc. 472, 87th Cong., 2d 
sess. 
H. Doc. 472, 87th Cong., 2d 
sess. 
H. Doc. 519, 87th Cong., 2d 
sess. 
Flood Control Committee 
Doc. 1, 75th Cong., 1st sess. 
H. Doc. 525, 89th Cong., 2d 
sess. 
14-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 14-B 
(Continued) 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Oct. 23, 1962 
Oct. 23, 1962 
Oct. 23, 1962 
Nov. 7, 1966 
Oct. 23, 1962 
Adopted by 
Senate and 
House 
Committee 
resolutions, 
Oct. 12, 1972' 
Oct. 23,1962 
Jun. 28, 1938 
Oct. 23, 1962 
Oct. 27, 1965 
MCGEE CREEK DRAINAGE AND LEVEE DISTRICT, IL 
(See Section 11 of Text) 
Reconstruct existing levee and construct pumping plant to 
reduce flooding. 
MEREDOSIA IL, AND MEREDOSIA WILLOW CREEK 
AND COON *UN DRAINAGE AND LEVEE DISTRICTS, 
IL (See Section 12 of Text) 
Raise and enlarge existing levee and other modifications. 
MEREDOSIA LAKE AND WILLOW CREEK DRAINAGE 
AND LEVEE DISTRICT, IL (See Section 13 of Text) 
Raise and enlarge existing levee and other modifications. 
MISSISSIPPI RIVER AGRICULTURAL AREA 8, MO (See 
Section 14 of Text) 
Raise and enlarge existing levee and alter pumping plant to 
reduce flooding. 
NUTWOOD DRAINAGE AND LEVEE DISTRICT, IL (See 
Section 15 of Text) 
Raise and enlarge existing levee and other modifications. 
PERRY COUNTY DRAINAGE AND LEVEE DISTRICTS 
NOS. 1, 2, & 3, MO (See Section 16 of Text) 
Construct pumping plants and other modifications to reduce 
interior flooding. 
REND LAKE, BIG MUDDY RIVER, IL (See Section 17 of 
Text) 
Construct dam at Benton, Ill., and subimpoundment dams on 
upper arms of reservoir. 
WOOD RIVER DRAINAGE AND LEVEE DISTRICT, IL 
(See Section 18 of Text) 
Construct reservoirs and local protection projects. 
CLARENCE CANNON DAM AND RESERVOIR, SALT 
RIVER, MO (See Section 22 of Text) 
Modified act of 28 Jun. 1938 by deleting the reservoir therefrom 
and reauthorizing it as a separate multiple-purpose project. 
Changes name of project from Joanna Dam to present 
designation. 
H. Doc. 472, 87th Cong., 2d 
sess. 
H. Doc. 472, 87th Cong., 2d 
sess. 
H. Doc. 472, 87th Cong., 2d 
sess. 
H. Doc. 472, 87th Cong., 2d 
sess. 
H. Doc. 360, 92nd Cong., 2d 
sess. 
H. Doc. 541, 87th Cong., 2d 
sess. 
Flood Control Committee 
Doc. 1, 75th Cong., 1st sess. 
H. Doc. 507, 87th Cong., 2d 
sess. 
Public Law 89-298, 89th 
Cong. 
1. Also joint resolution; Jun. 29, 1906. 
2. Contains latest pubhlished map. 
8. Inactive. 
4. All work completed. 
5. Authorized under provision of Sec. 201 of the Flood 
Control Act of 1965. 
14-12

ST. LOUIS, MO, DISTRICT 
TABLE 14-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to Sep. 1983 
Full Report Operation 
Mo. and Yr. See Annual and Mo. and Yr. 
Project Deauthorized Report For: Construction Maintenance Completed 
Cuivre River, MO - 1883 $ 12,000 $ - 
Grafton Small Boat Harbor, IL Nov. 1977 19622 - 
Mississippi River at Alton, IL 
Small Boat Harbor Nov. 1977 19582 - - 
Moccasin Springs, MO - 1969 76,436s 
Small Boat Harbor opposite Chester, IL Nov. 1977 19542 - 
Small Boat Harbor opposite Hamburg, IL Nov. 1977 19502 
Wabash Railroad Bridges, Illinois River, 
Meredosia, and Valley City, IL - 1961 2,653,194 1961 
1. Inactive. River declared nonnavigable by act of Mar. 2. Year authorized. 
23, 1900. 3. Excludes $56,605 contributed funds. 
TABLE 14-D LAKES, LEVEES, AND 
RECREATIONAL FACILITIES 
Estimated 
See Required Total Estimated 
Section Estimated Non-Federal Cost (Date to 
ieTne xt Project Name Federal Cost Cost Revision) 
10. Meramec River Basin, MO Lakes: 
Meramec Park' 197,494,000 22,506,000 220,000,000 (1981) 
Union' 101,305,000 11,695,000 113,000,000 (1982) 
Pine Ford' 111,896,000 30,104,000 142,000,000 (1982) 
Irondale2 8,744,370 66,700,000 (1982) 
1-382 27,294,000 2,306,000 29,600,000 (1982) 
Recreation facilities: 
Angler-use sites2 2,140,000 2,140,000 4,280,000 (1982) 
1. Separate reports are included herein. 2. See 1967 Annual Report for details. 
14-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 14-E OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
Cost to Sep. 1983 
For Last 
Full Report Operation 
Mo. and Yr. See Annual and Mo. and Yr. 
Project Deauthorized Report For: Construction Maintenance Completed 
Angler-use sites, Meramec Basin, MO 
Big Swan Drainage and Levee District, 
Illinois River, IL' 
Cache River Diversion, IL 
Cape Girardeau, MO, 
reaches Nos. 1, 3, and 4 
Cape Girardeau, MO, No. 2 
Carlyle Lake, IL 
Chouteau, Nameoki, and Venice Drainage 
and Levee District, IL 
Clear Creek Drainage and 
Levee District, IL 2 
Columbia Drainage and Levee 
District No. 3, IL 
Degognia and Fountain Bluff Levee and 
Drainage District, IL 
Dively Drainage & Levee District, IL 
East Cape Girardeau and Clear Creek 
Drainage District, IL 
Eldrid, IL 
Emergency bank protection for certain 
highway and railroad facilities at Price 
Landing, MO (see Flood Control 
Act of 1944)4 
Emergency repairs to levees on Mississippi, 
Illinois, and Kaskaskia Rivers and flood 
fighting and rescue work (Sec. 5, Flood 
Control Act of 1941, as amended)4 
Emergency protection for certain highway 
and railroad facilities at Chester, IL, bridge 
(Sec. 12, Flood Control Act of 1944) 
Emergency protection for Illinois approach, 
Chain of Rocks Bridge (Sec. 12, Flood 
Control Act of 1944) 
Fort Chartres and Ivy Landing Drainage 
District No. 5, IL 
Fort Chartres and Ivy Landing Drainage 
District No. 5 and Stringtown Drainage 
and Levee District No. 4, IL 
Grand Tower Drainage and 
Levee District, IL 
Harrisonville Levee and 
Drainage District IL 
Indian Creek Area, Illinois River, IL' 
Kaskaskia Island Drainage and 
Levee District, IL 
Keach Drainage and Levee District, IL 
Lake Shelbyville, IL 
Levee Districts between Carlyle and 
New Athens, IL, Nos. 2, 5, 6, and 7 
Levee Districts between Carlyle and 
New Athens, IL, Nos. 3, 4, 8, 10, and 13 
Levee Districts between Cowden 
and Vandalia, IL 
Meredosia Lake and Willow Creek Drainage 
and Levee District, IL* 
Miller Pond Drainage District, IL 
1967 $ - 
1953 2,837,114 
Oct. 1978 
Nov. 1979 
Nov. 1979 
Nov. 1979 
Oct. 1978 
1959 
1965 
1981 
1955 
1964 
22,000 
5,157,805 
42,819,400 
185,700 
4,984,500 
1981 2,818,000 
1959 5,889,500 
1976 1,720,000 
1963 1,920,600 
1962 t - 
1950 
1953 
1952 
1946 
1970 
1971 
1959 
1981 
1959 
1981 
1979 
1979 
1978 
1944 
1955 
55,415 
1,033,279 
50,000 
25,000 
1,154,800 
4,677,900 
5,829,000 
297,460 
44,000,000 
496,000 
249,738 
164,183 
14-14 
28,625,807 
1953 
1964 
Oct. 1976 
1955 
1963 
Aug. 1981 
1959 
1976 
1963 
Oct. 1949 
1951 
Jan. 1952 
Aug. 1945 
1958 
1959 
Mar. 1981 
1949 
26,377,956 Sep. 1978 
1944 
1955

ST. LOUIS, MO, DISTRICT 
TABLE 14-E 
(Continued) 
OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
Cost to Sep. 1983 
For Last 
Full Report Operation 
Mo. and Yr. See Annual and Mo. and Yr. 
Project Deauthorized Report For: Construction Maintenance Completed 
Mississippi River at St. Louis, MO - 1980 79,265,166 - Jan. 1980 
Mississippi River Agricultural Area 
No. 10, MO . Nov. 1979 1967 - - 
Mississippi River Agricultural Area 
No. 12, MO - 1967 - - 
Mississippi River, Alton to Gale, IL, 
underseepage measures - - 85,422 - Oct. 1962 
North Alexander Drainage and 
Levee District, IL - 1957 939,569 - 1957 
Prairie du Pont Levee and 
Sanitary District, IL5 - 1970 6,005,127 - 1970 
Prairie du Rocher and vicinity, IL - 1959 3,882,600 - 1959 
Preston Drainage and Levee District, IL - 1959 1,866,910 - 1959 
Richland Creek, IL - 1969 401,000 - 
Riverland Levee District, MO Aug. 1977 1936- - - 
Scott County Drainage and Levee District, 
Illinois River, IL' - - - 
Ste. Genevieve County Drainage and 
Levee District No. 1, MO Nov. 1977 1936 - - 
St. Louis County Drainage and 
Levee District No. 1, MO Nov. 1977 1936- - - 
Strington, Ft. Chartres and Ivy Landing, IL - 1957 2,123,700 - Aug. 1956 
Union Lake, MO6 - 1979 4,917,359 - 
Urban areas at Alton, IL - 1960 192,000 -- 
Village of New Athens, IL - 1981 1,983,000 - Sep. 1981 
Valley City Drainage & Levee District, IL - 1967 91,952 - 1967 
Wiedmer Chemical Drainage and Levee 
District, MO Nov. 1977 1936- - - 
1. Projects authorized or modified by Flood Control Act 
of Oct. 23, 1962 (see H. Doc. 472, 87th Cong., 2d sess., for 
details). 
2. Completed except for seepage control measures, which 
are inactive. 
3. Year authorized. 
4. Work complete, now performed under Public Law 99. 
5. Includes $5,235,927 for previous project. 
6. Includes $183,638 for definite project study under 
1938 Flood Control Act. Includes Highway 185 funds. 
7. Authorized by Chief of Engineers (Sec. 205, 1948 
Flood Control Act, as amended). 
14-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 14-F ACTIVE GENERAL INVESTIGATIONS 
(96x3121) 
Federal Cost Totals by 
Item and CWIS Number FY 83 Categories 
SURVEYS (Category 100) 
Navigation (110) 
St. Louis Harbor, MO & IL -58330 $ 51,666 
Miss. R. Mooring Facilities -81181 13,785 
Sub-Total 65,451 
Flood Control Studies (120) 
Alexander and Pulaski Counties, IL -12217 177,275 
Cape Girardeau-Jackson Metropolitan Area, MO -12053 70,432 
Plattin Creek, MO -12137 362 
St. Louis Metropolitan Area, MO & IL-55040 1,193,909 
Ste. Genevieve, MO -80061 207,583 
Richland Creek, IL-12174 146,341 
Sub-total 1,795,902 
Special Studies (140) 
Great River Resource Mgmt Study -14028 12,314 
Carlyle Lake - Shelbyville Lake, Ill. -12160 35,858 
Sub-total 48,172 
Miscellaneous Activities (170) 
Special Investigations -17250 17,000 
Coordination Studies with Other Agencies (180) 
Dept. of Agric. - Soil Cons. Service -51840 1,653 
Tech. & Engrg. Asst. - Shore & Streambank Eros. -51731 165 
Sub-total 1,818 
TOTAL (Category 100) $1,928,343 
COLLECTION AND STUDY OF BASIC DATA (Category 200) 
Inspection and Inventory of Dams (286) -53843 and 53842 209 
Flood Plain Management Services (250) -82030,83400, and 82040 138,801 
TOTAL (Category 200) $ 139,010 
RESEARCH AND DEVELOPMENT (Category 300) 
None 
ADVANCE ENGINEERING AND DESIGN (Category 600) 
Eldred & Spankey D&LD, IL -00071' 47,891 
Hartwell D&LD, IL -00073 187,843 
Hillview D&LD, IL - 00075 201,410 
Meredosia Lake & Willow Creek D&LD, IL -00079 108,443 
Meredosia IL, and Meredosia, 
Willow Creek & Coon Run D&LD, IL -00069 186,873 
Meremac River Basin, MO -75412 490,049 
Nutwood D&LD, IL -00623 78,659 
Pine Ford Lake, MO -00091 2,726 
TOTAL (Category 600) $1,303,894 
GRAND TOTAL GENERAL INVESTIGATIONS $3,371,247 
14-16

GALVESTON, TX DISTRICT* 
Galveston District comprises drainage basins of all 
short streams arising in coastal plain of Texas and 
flowing into the Gulf of Mexico, including the entire 
basin of Buffalo Bayou, San Jacinto, San Bernard, 
Lavaca, Navidad, Mission, and Aransas Rivers. It 
embraces Agua Dulce, San Fernando, and Olmos Creek 
Basins draining into Baffin Bay, and coastal area south 
thereof to the Rio Grande and east of western Boundary 
of Starr County, Texas. It includes lower basins of major 
streams flowing into the Gulf of Mexico: Sabine River, 
Texas and Louisiana, downstream from U.S. Highway 
190 crossing at Bon Wier, Texas; Neches River 
downstream from Town Bluff gaging station; Trinity 
River downstream from Texas State Highway 19 
crossing at Riverside, Texas; Brazos River downstream 
from confluence with Navasota River; Colorado River 
downstream from northern boundary of Fayette County; 
Guadalupe River downstream from confluence with San 
Marcos River; San Antonio River downstream from 
confluence with Escondido Creek; Nueces River 
downstream from confluence with Frio and Atascosa 
River. 
IMPROVEMENTS 
Navigation 
1. Aquatic Plant Control 
(Southwestern Division) ................ 
2. Brazos Island Harbor, TX .............. 
3. Channel to Port Bolivar, TX ........... 
4. Corpus Christi Ship Channel, TX ........ 
5. Double Bayou, TX ................... 
6. Freeport Harbor, TX .................. 
7. Galveston Harbor and Channel, TX ...... 
8. Gulf Intracoastal Waterway between 
Apalachee Bay, FL, and the Mexican 
Border............................... 
9. Houston Ship Channel, TX .............. 
10. Matagorda Ship Channel, TX ........... 
11. Sabine-Neches Waterway, TX.......... 
12. Texas City Channel, TX ............... 
13. Trinity River and Tributaries, TX ....... 
13A. Anahuac Channel, TX ................. 
13B. Channel to Liberty, TX ................ 
13C. Wallisville Lake, TX ................. 
14. Reconnaissance and Condition Surveys.... 
15. Navigation Work Under Special 
Authorization......................... 
Beach Erosion Control 
16. Corpus Christi Beach, TX............... 
Page 
15-2 
15-2 
15-2 
15-2 
15-3 
15-3 
15-4 
15-5 
15-6 
15-6 
15-7 
15-7 
15-7 
15-8 
15-8 
15-8 
15-9 
15-9 
15-9 
Flood Control 
17. Arroyo Colorado, Rio Hondo, TX ......... 15-9 
18. Buffalo Bayou and Tributaries, TX....... 15-9 
19. Freeport and Vicinity, TX, 
Hurricane-Flood Protection ............ 15-10 
Flood Control (cont) Page 
20. Highland Bayou, TX ................. 15-10 
21. Port Arthur and Vicinity, TX, 
Hurricane-Flood Protection ............. 15-10 
22 Taylors Bayou, TX ................... 15-10 
23. Texas City and Vicinity, TX, 
Hurricane-Flood Protection ............. 15-11 
24. Vince and Little Vince Bayous, TX ...... 15-11 
25. Inspection of Completed Flood Control 
W orks ............................. 15-11 
26. Flood Control Work Under Special 
Authorization ........................ 15-11 
General Investigations 
27. Surveys ............................ 
28. Advance Engineering and Design ........ 
29. Planning and Engineering ............. 
30. Collection and Study of Basic Data ....... 
Tables 
Table 15-A 
Table 15-B 
Table 15-C 
Table 15-D 
Table 15-E 
Table 15-F 
Table 15-G 
Table 15-H 
Table 15-I 
15-11 
15-12 
15-12 
15-12 
Cost and Financial Statement ... 15-13 
Authorizing Legislation ........ 15-16 
Other Authorized Navigation 
Projects ...................... 15-27 
Other Authorized Flood Control 
Projects ..................... 15-27 
Total Cost of Existing 
Projects..................... 15-28 
Channel Dimensions ........... 15-29 
Channel Dimensions, GIWW 
Tributary Channels ............ 15-32 
Dredging Operations ........... 15-34 
Jobs Act Contracts ............ 15-35 
15-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Navigation 
1. AQUATIC PLANT CONTROL 
(SOUTHWESTERN DIVISION) 
1965 ACT 
Location. Navigable waters, tributary streams, 
connecting channels, and other allied waters in Texas 
and the Sabine River Watershed of Louisiana. 
Previous project. For details see page 699 of Annual 
Report for 1963. 
Existing project. A comprehensive project to provide 
for control and progressive eradication of waterhyacinth, 
alligatorweed, Eurasian watermilfoil, and 
other obnoxious aquatic plant growths, from navigable 
waters, tributary streams, connecting channels, and 
other allied waters in Texas in the combined interest of 
navigation, flood control, drainage, agriculture, fish and 
wildwife conservation, public health, and related 
purposes, including continued research for development 
of the most effective and economic control measures. 
Eradication work continues in the Nueces River Basin, 
North Coastal Area, Guadalupe River Basin, Sabine 
River Basin, Trinity River Basin, Cypress Creek Basin, 
Neches River Basin, South Coastal Area, San Jacinto 
River Basin and Rio Grande Basin. Planning, to include 
hydrilla control in the existing program, is underway. 
Estimated cost for new work is $2,019,000 Federal 
(Corps) and $693,000 non-Federal. 
Local cooperation. Sec. 302, 1965 River and Harbor 
Act, applies. 
Operations during fiscal year. Reimbursement to 
State of Texas for Government's share of cost was 
$67,285. In addition, the State performed $43,114 of 
eradication work for which credit as work-in-kind was 
given. 
2. BRAZOS ISLAND HARBOR, TX 
Location. At extreme south end of coast of Texas, 
about 7 miles north of mouth of Rio Grande and about 5 
miles east of Brownsville, Texas. (See National Ocean 
Survey Chart 11301.) 
Previous project. For details see page 1017 of 
Annual Report for 1932. 
Existing project. Provides for channel dimensions in 
various sections of the waterway as shown in Table 15F. 
Project also provides for dual jetties at the gulf 
entrance, a north jetty 6,330 feet long, a south jetty 5,092 
feet long, and 1,000-foot extension to existing north jetty 
and for maintenance of 3rd fishing harbor constructed by 
local interests. Under ordinary conditions, mean tidal 
range is about 1.5 feet, and extreme range is about 2 feet. 
All depths refer to mean low tide. To some extent, height 
of tides is dependent on the wind, and during strong 
"northers" in winter season, water surface in southern 
end of Laguna Madre may be raised 4 feet or mure above 
mean low tide in the gulf. 
Widening Brownsville Channel from Goose Island to 
Brownsville turning basin and deepening southeast 
corner of Brownsville turning basin to 36 feet was 
completed in April 1980. The 1,000-foot extension to 
existing north jetty was placed in the inactive category 
in 1980. (See Table 15-E for total cost of existing project 
to September 30, 1983.) 
Local cooperation. Complied with. 
Terminal facilities. Numerous terminal facilities for 
bulk and liquid cargo are available. (See Port Series No. 
26, revised 1980.) Facilities are adequate for existing 
commerce. 
Operations during fiscal year. Routine 
maintenance. (See Table 15-H for dredging operations.) 
3. CHANNEL TO PORT BOLIVAR, TX 
Location. Port Bolivar is at end of Bolivar Peninsula 
and 4 miles north of city of Galveston. Channel connects 
the port with channel in Galveston Harbor. (See 
National Ocean Survey Chart 11324.) 
Previous project. For details see page 1856 of 
Appendix to Annual Report for 1915. 
Existing project. Existing project dimensions for 
channel are shown in Table 15-F. (Also see Table 15-B for 
authorizing legislation.) 
Under ordinary conditions mean tidal range is about 
1.3 feet and extreme range about 2 feet. Height of tides is 
dependent largely on the wind, and during strong 
"northers" in the winter season water surface may be 
depressed as much as 2 feet below mean low tide. 
Enlargement of turning basin from 1,000 to 1,600 feet is 
inactive. A channel 14 feet deep, 200 feet wide, and 
approximately 950 feet long is maintained across the 
east end of the turning basin to accommodate the 
Galveston-Port Bolivar ferry. Project is complete except 
for inactive portion. Project dimensions have not been 
maintained in the completed part since lesser 
dimensions are adequate for existing commerce. (See 
Table 15-E for total cost of existing project to September 
30, 1983.) 
Local cooperation. None required. 
Terminal facilities. Terminals are privately owned 
and consist of 2 slips and 2 piers. The piers, 400 feet wide 
by 1,200 feet long and 210 feet wide by 1,200 feet long, 
are badly deteriorated and not in use. The slips are used 
as anchorage by shallow-draft vessels. A highway ferry 
landing owned by the State of Texas is located at south 
end of turning basin. Facilities are considered adequate 
for existing commerce. 
Operations during fiscal year. Routine 
maintenance. (See Table 15-H for dredging operations.) 
4. CORPUS CHRISTI SHIP 
CHANNEL, TX 
Location. This project, formerly known as the Port 
Aransas-Corpus Christi Waterway, Texas, was changed 
to Corpus Christi Ship Channel, Texas, by 1968 River 
and Harbor Act. This is a consolidation of old 
improvements of Port Aransas, Texas, and channel from 
Aransas Pass to Corpus Christi, Texas. Aransas Pass is 
on southern portion of Texas Coast, 180 miles southwest 
of Galveston and 132 miles north of mouth of Rio Grande. 
Aransas Pass connects Corpus Christi Bay and Aransas 
15-2

GALVESTON TEXAS DISTRICT 
Bay with the gulf. Waterway extends from deep water in 
the gulf through Aransas Pass jettied entrance, thence 
westerly 20.75 miles to and including a turning basin at 
Corpus Christi, thence westerly 1.75 miles through 
Industrial Canal to and including turning basin at Avery 
Point, thence westerly 4.25 miles to and including a 
turning basin near Tule Lake, thence northwesterly 1.8 
miles to and including a turning basin at Viola, Texas. 
(See National Ocean Survey Charts 11308,11309,11311, 
and 11314.) 
Previous project. For details see page 1861 of Annual 
Report for 1915. 
Existing project. (See Table 15-F for existing project 
dimensions provided for in various channels and basins 
comprising this waterway.) 
Project also provides for two rubblestone jetties at 
Aransas Pass entrance, extending into the gulf from St. 
Joseph and Mustang Islands, project lengths of which are 
11,190 and 8,610 feet, respectively. Project further 
_provides for a stone dike on St. Joseph Island about 
20,991 feet long, connecting with north jetty and 
extending up this island to prevent a channel being cut 
around jetty. Project also provides for a breakwater at 
the entrance to the harbor area at Port Aransas, and for 
the realignment of the existing 12-foot by 100-foot project 
channel to Port Aransas. The breakwater consists of two 
overlapping sections. The one on the east side of the 
realigned entrance channel has a length of 830 feet and 
the second, located on the west side of the entrance 
channel, has a length of 1,290 feet. The channel to Port 
Aransas was relocated in the 300-foot clear distance 
between the overlapping sections. The portion of the 
channel remaining inside the breakwaters was widened 
to 150 feet. Under ordinary conditions, mean tidal range 
at Aransas Pass is about 1.1 feet and extreme range 
about 2 feet, and at Corpus Christi mean range about 1 
foot and extreme about 1.5 feet. Heights of tides are 
dependent largely on strength and directions of winds, 
and during strong "northers" in the winter season water 
surface may be depressed as much as 3 feet below mean 
low tide. Estimated cost for new work is: Federal (Corps) 
$87,924,515, including $456,515 for Port Aransas 
Breakwaters and exclusive of amount expended on 
previous projects; and non-Federal $17,360,068 (includes 
$768 for Port Aransas Breakwaters) including 
$6,027,840 contributed funds and value of useful work 
performed, $3,320,228 lands, $6,027,000 relocations and 
$1,985,000 other cost. (October 1, 1983 base price.) 
The Port Aransas-Corpus Christi 40-foot project was 
completed in 1966. The Jewel Fulton Canal was 
completed in 1963. The Port Aransas Breakwaters were 
completed in July 1973. Work remaining consists of 
deepening deep-draft channels to 45 feet from Beacon 82 
through Viola Turning Basin; widening of channels and 
basins; and constructing a mooring area at Port Ingleside 
with dolphins. Entrance and jetty channels have been 
dredged to project depth and width, and dredging of 
channel from Harbor Island to Beacon 82 at 45-foot depth 
has been completed. Initial mooring dolphins were 
completed in May 1979. (See Table 15-E for total cost of 
existing project to September 30, 1983.) 
Local cooperation. Fully complied with except for 
provisions of Sec. 101 of 1968 River and Harbor Act and 
Sec. 124 of Water Resources Development Act of 1976. 
Terminal facilities. Terminal facilities on Harbor 
Island at head of Aransas Pass, Ingleside, Corpus 
Christi, La Quinta, Avery Point, and Viola, are 
considered adequate for existing commerce. (See Port 
Series, No. 25, revised 1979, Corps of Engineers.) 
Operations during fiscal year. New Work: 
Construction of mooring anchors for existing mooring 
dolphins was completed at a fiscal year cost of 
$1,108,843. 
Maintenance: Routine maintenance. (See Table 15-H 
for dredging operations.) 
5. DOUBLE BAYOU, TX 
Location. Enters upper Galveston Bay on the east side 
about 30 miles north of Galveston and about 8.25 miles 
south of Anahuac, Texas. 
Existing project.Project provides for a channel 7 feet 
by 125 feet from the mouth of Double Bayou to the 7-foot 
contour in Trinity Bay, a length of 3.9 miles; and a 
channel, known as West Fork, 7 feet by 100 feet for a 
length of 2.0 miles. The project was completed in 1971. 
Under ordinary conditions mean tidal range is about 
0.5 feet and extreme range is about 1.2 feet. Height of 
tides is dependent largely on winds, and during strong 
north winds in the winter season, water surface may be 
depressed 1.5 feet below mean low tide. (See National 
Ocean Survey Chart 11326.) 
Local cooperation. Fully complied with. 
Terminal facilities. Facilities are privately owned. At 
the mouth of the bayou is a timber wharf for loading oil 
barges. Between miles 1 and 1.5 above the mouth are 
timber wharf, a boat slip, and a marine railway owned by 
the Brown and Root Corporation. At mile 3 above the 
mouth is a small depot for handling oystershell. The 
facility consists of a timber bulkhead and hoppers for 
loading trucks. One half mile above the mouth are 
several fishing vessel docks. 
Operations during fiscal year. Routine 
maintenance. Fiscal year cost for dredging Double Bayou 
Channel was $27,106. 
6. FREEPORT HARBOR, TX 
Location. Formed by improvement of Brazos River, 
Texas, from mouth to about 6 miles upstream to 
Freeport, Texas. (See National Ocean Survey Charts 
11321 and 11322.) 
Previous projects. For details see page 1860 of 
Annual Report for 1915, and page 872 of Annual Report 
for 1938. 
Existing project. Existing project dimensions for 
various channels and basins are shown in Table 15-F on 
channel dimensions at end of chapter. 
Existing project also provides for: Dual jetties and a 
diversion canal for the Brazos River, including a dam, a 
lock in the dam and necessary auxiliary equipment. Also 
15-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
provides for rehabilitation of southwest jetty and the 
relocation of the northeast jetty (about 640 feet to the 
northeast); realignment of the channel between the Jetty 
Channel and Brazosport Turning Basin; realignment of 
the channel between Brazosport Turning Basin and 
Upper Turning Basin; relocation of Upper Turning 
Basin; and public use facilities adjacent to the Freeport 
Jetties. The 30-foot channel from Upper Turning Basin 
to Stauffer Chemical Plant, including the turning basin, 
was deauthorized by Sec. 12 of PL 93-251. Construction 
of lock in diversion dam at local expense is considered 
inactive. 
The 38-36 foot project was completed in 1962. Work 
remaining consists of realigning, deepening and 
widening the Outer Bar and Jetty Channels; relocating 
the northeast jetty; rehabilitating the southwest jetty; 
realigning and deepening the harbor channel between 
the jetty channel and the Upper Turning Basin; 
relocating and enlarging the Upper Turning Basin; 
constructing a turning point near the northwesterly end 
of the jetty channel; enlarging Brazosport Turning 
Basin; deepening Brazos Harbor Channel; and enlarging 
and deepening Brazos Harbor Turning Basin. 
Preconstruction planning on this remaining work is 
complete. (See Table 15-E for total cost of existing project 
to September 30, 1983.) 
Under ordinary conditions mean tidal range is about 
1.5 feet and extreme range is about 2.5 feet. Except under 
extreme conditions, rises on river and in diversion 
channel do not cause greater variations in water surface 
than those caused by tidal action. Estimated cost of new 
work is: $80,100,000 Federal (Corps); and $10,581,000 
non-Federal, including $1,105,303 contributed funds, 
$360,249 contributed work, $6,023,448 lands, 
$2,577,000 levees and spillways, and $515,000 
relocations. (October 1, 1983 base price.) 
Local cooperation. Fully complied with except for 
Section 101 of River and Harbor Act of 1970. River and 
Harbor Act of 1970 requires local interests provide 
necessary lands, easements, and rights-of-way required 
for public use facilities; and when the appraised value of 
land, easements, and rights-of-way amounts to less than 
50 percent of the total first cost of the development, make 
additional contributions sufficient to bring the non- 
Federal share to at least that level. The cash 
contribution is presently estimated at $347,000 which 
combined with land, estimated $672,000 is 50 percent of 
the cost of public use facilities. Cash contribution at time 
of authorization estimated at $95,000 in addition to 
providing land estimated at $70,000. 
Terminal facilities. Small privately owned wharves, 
two oil docks, one acid dock, two shell unloading docks 
and one caustic dock. Brazos River Navigation District 
has one large dock with four transit sheds over rail 
facilities permitting all-weather work. Facilities 
considered adequate for existing commerce. (See Port 
Series No. 26, revised 1980, for additional facilities.) 
Operations during fiscal year. New Work: 
Preconstruction planning continued on the 45-foot 
project. 
Maintenance: Routine maintenance. (See Table 15-H 
for dredging operations.) 
7. GALVESTON HARBOR AND 
CHANNEL, TX 
Location. A consolidation of authorized 
improvements at Galveston, Texas, which includes 
projects formerly identified as Galveston Harbor, Texas; 
Galveston Channel, Texas; and Galveston seawall 
extension. Entrance to Galveston Harbor is on Gulf of 
Mexico on the northern portion of the Texas Coast. 
Galveston Channel extends from a point in Galveston 
Harbor between Bolivar Peninsula and Fort Point to and 
along wharf front of Galveston, Texas, and is about 5 
miles long and 1,200 feet wide. (See National Ocean 
Survey Chart 11324/5.) 
Previous projects. For details see page 1854 of 
Annual Report for 1915. 
Existing project. Provides for channel dimensions in 
sections of the waterway shown in Table 15-F. 
Also provided are: two rubble-mound jetties, the south 
one extending from Galveston Island and the north one 
extending from Bolivar Peninsula, for distances of 
35,900 feet and 25,907 feet, respectively, into the Gulf of 
Mexico; a concrete seawall from the angle at Sixth Street 
and Broadway, in the city of Galveston, to the south jetty, 
and a 16,300-foot extension of the concrete seawall in a 
southwesterly direction from 61st Street; for 11 groins 
along the gulf shore between 12th Street and 61st Street; 
and for maintenance of seawall from the angle at 6th 
Street and Broadway to the south jetty. Under ordinary 
conditions, mean tidal range in Galveston Harbor is 1.6 
feet on outer bar and 1.4 feet on inner bar with extreme 
ranges of 2.3 and 2.1 feet, respectively. Mean range in 
Galveston channel is about 1.3 feet and extreme range 
about 2 feet under ordinary conditions. Height of tides in 
both Galveston harbor and channel is dependent largely 
on the wind, and during strong "northers" water surface 
may be depressed 2 feet below mean low tide. 
Existing project is complete. Dredging of Galveston 
channel to 36 foot depth was completed in November 
1966. Dredging of the realigned entrance and Outer Bar 
Channel was completed in October 1967. Rehabilitation 
of the Beach Front Groins was completed June 1970. 
Dredging of Galveston channel to 40 feet was completed 
in March 1976. (See Table 15-E for total cost of existing 
project to September 30, 1983.) 
Local cooperation. Complied with. 
Terminal facilities. None on Galveston Harbor, 
which is entrance channel leading to terminal facilities 
on Galveston, Texas City, and Houston Ship Channels. 
Galveston Channel terminal facilities are mostly on 
south side of channel. Principal wharves, owned by the 
city of Galveston, extend from 10th to 41st Street (see 
Port Series No. 23, revised 1979). A containership 
terminal equipped with a crane capable of stacking 
containers three units high on the deck of any normal 
containership has been completed and placed into 
operation by the city of Galveston at Piers 10 and 11, on 
the south side of Galveston Channel. The city of 
Galveston has also placed into operation a barge 
terminal equipped with two 35-ton and one 5-ton cranes 
for loading and unloading barges on Lash and Seabee 
15-4

GALVESTON TEXAS DISTRICT 
ships at Pier 35 and a docking and holding area for Lash 
and Seabee barges on Pelican Island, directly across the 
channel from Piers 35 and 36. Present facilities are 
considered adequate for existing commerce. 
Operations during fiscal year. Routine 
maintenance. 
8. GULF INTRACOASTAL WATERWAY 
BETWEEN APALACHEE BAY, FL, 
AND MEXICAN BORDER 
(GALVESTON DIST.) 
Location. Extends from a point on Sabine River about 
3 miles below Orange, Texas, to Brownsville, Texas, 
about 421 miles; a navigation channel, about 7 miles 
long, in Colorado River, extending from Matagorda, 
Texas, to Gulf of Mexico; a tributary channel in San 
Bernard River, extending from Intracoastal Waterway 
crossing to State highway bridge some 30 miles above 
crossing; a tributary channel in Colorado River 
extending from Intracoastal Waterway upstream 15.5 
miles; a tributary channel extending about 14 miles from 
Intracoastal Waterway to Palacios, Texas; a tributary 
channel extending about 2 miles from Intracoastal 
Waterway to Rockport, Texas; a tributary channel 
extending about 6 miles from Intracoastal Waterway 
near Port Aransas, Texas, to town of Aransas Pass, 
Texas; a tributary channel about one-fourth mile long 
extending from Intracoastal Waterway near Port 
O'Connor, Texas, into Barroom Bay; a tributary channel 
extending about 38.8 miles from Intracoastal Waterway 
via Seadrift to a point in Guadalupe River 5.5 miles 
below Victoria, Texas; a harbor of refuge for small craft 
at Seadrift; a channel extending from gulf to Port 
Mansfield, Texas, about 11 miles; and a tributary 
channel in Arroyo Colorado extending from Intracoastal 
Waterway to a point near Harlingen, Texas, about 31 
miles; side channels in vicinity of Port Isabel, Texas, and 
a small boat basin at Port Isabel, Texas, and a tributary 
channel extending from Intracoastal Waterway main 
channel at a point in West Galveston Bay into Offatts 
Bayou about 2.2 miles with a west turnout (wye 
connection) 12 feet deep and 125 feet wide between 
Offatts Bayou Channel and the Gulf Intracoastal 
Waterway. (See National Ocean Survey Charts 11302, 
11303,11305, 11306,11308,11309,11314,11315,11317, 
11319, 11322, 11326, and 11331.) 
Previous project. For details see page 1859 of Annual 
Report for 1915. (West Galveston Bay and Brazos River 
Canal, Texas.) 
Existing project. Existing project dimensions 
provided for in main channel of waterway: A channel 12 
feet deep (below mean low tide) and 125 feet wide from 
the Sabine River to Brownsville, Texas. Relocation of 
channel 12 feet deep by 125 feet wide in Matagorda Bay, 
miles 454.3 to 471.3, relocation of channel 12 feet deep by 
125 feet wide in Corpus Christi Bay, miles 539.4 to 549.7 
(mileage is west of Harvey Lock, Louisiana); and 
alternate channel, 12 feet deep (below mean low tide) and 
125 feet wide via Galveston Channel and Galveston Bay 
to the Galveston causeway; maintenance of existing 
channel 12 feet deep by 125 feet wide through Lydia Ann 
Channel, between Aransas Bay and Aransas Pass; 
provisions of such passing places, widening of bends, 
locks and guard locks, railway bridges over artificial cuts 
as are necessary, and the tributary channels shown in 
tabulation. The authorized channel 16 feet deep and 125 
feet wide from Sabine River to Houston Ship Channel 
and the 9 feet deep and 100 feet wide channel from mile 
8.2 to mile 13.2 in Chocolate Bayou are inactive. (See 
Table 15-G on existing project dimensions provided for in 
tributary channels.) 
Removal of the railroad bridge across the canal at Mud 
Bayou was completed and operation and care of the 
facility was discontinued on April 14, 1969. Deepening 
the existing 6 foot by 60 foot side channels at Port Isabel 
to 12 feet was completed February 22, 1972, Offatts 
Bayou channel was completed January 1974. Relocation 
of main channel across Corpus Christi Bay was 
completed in September 1976. The 14 foot by 175 foot 
Channel to Aransas Pass was completed in April 1979. 
Dredging Chocolate Bayou Channel was completed in 
January 1981. Construction of a saltwater barrier in 
Chocolate Bayou was completed in February 1981. The 
12 foot by 125 foot channel relocation route in Matagorda 
Bay has been placed in the inactive category. The Harbor 
of Refuge at Seadrift, Texas, has been placed in the 
inactive category. Active authorized work remaining 
consists of the following: construction ofjetties at mouth 
of Colorado River; dredging a navigation channel from 
gulf to the GIWW; constructing a turning basin at 
Matagorda, Texas; construction of a diversion dam and 
channel; construction of an oyster cultch; and recreation 
facilities. (See Table 15.E for total cost of existing project 
to September 30, 1983.) 
Mean tidal variation is 0.5 foot at Orange, 1 foot at Port 
Arthur, 1.3 feet in Galveston Bay, 1.5 feet at Freeport, 1 
foot in Matagorda Bay, 1 foot in San Antonio Bay, 1 foot 
at Corpus Christi, 1.5 feet at Port Isabel, and 1.5 feet at 
Brownsville. Extreme ranges of tide under ordinary 
conditions are 1 foot at Orange, 1.5 feet at Port Arthur, 2 
feet in Galveston Bay, 2 feet at Freeport, 1.5 feet in 
Matagorda and San Antonio Bays, 1.5 feet at Corpus 
Christi, 2 Feet at Port Isabel, and 1.5 feet at Brownsville. 
Height of tides is dependent largely on wind. Strong 
north winds have depressed water surface as much as 2 
feet below mean low tide. Estimated cost for new work is: 
$73,664,000, Federal (Corps), including $8,414 for Port 
Isabel Side Channel, $46,559 for Port Isabel Small Boat 
Basin, $356,466 for Offatts Bayou, and $658,573 for 
Channel to Aransas Pass and excluding expenditures on 
previous projects; non-Federal $17,361,174 ($395,000 
voluntarily expended on Gulf Intracoastal Waterway, 
$46,559 contributed funds for Port Isabel, $49,665 
contributed funds for Offatts Bayou, $347,950 
contributed funds for channel to Aransas Pass, 
$2,993,000 contributed funds for Mouth of Colorado 
River, $6,039,000 lands for Gulf Intracoastal Waterway, 
$11,000 lands for Port Isabel, $4,242,000 relocations for 
Gulf Intracoastal Waterway and $3,237,000 other costs 
Gulf Intracoastal Waterway). (October 1, 1983 base 
price.) 
Local cooperation. Fully complied with except for 
inactive portions, and provisions of Section 101, 1968 
15-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
River and Harbor Act. Non-Federal contributions are 
$395,000 for Gulf Intracoastal Waterway, $46,559 for 
Port Isabel, Texas, $49,665 for Offatts Bayou, Texas, 
$347,950 for Channel to Aransas Pass, Texas, and 
$2,993,000 for Mouth of Colorado River, Texas. 
Terminal facilities. There are terminal facilities at 
Aransas Pass, Port Arthur, Galveston, Port Isabel, and 
Brownsville. See Port Series No. 22 (revised 1981), Port 
Series No. 23 (revised 1979), Port Series No. 25 (revised 
1979) and Port Series No. 26 (revised 1980), Corps of 
Engineers. Local interests constructed terminal 
facilities at Port Mansfield and Port Harlingen. There 
are numerous privately owned piers and wharves along 
the waterway. A 330-foot navigation district owned 
general cargo dock, a 770-foot private dock and a 760-foot 
private timber trestle have recently been completed at 
the upper end of the Channel to Victoria. Facilities are 
adequate for existing commerce. 
Operations during fiscal year. New work: Planning 
continued on Mouth of Colorado River. 
Maintenance: The Brazos River Floodgates were 
operated and maintained at a cost of $830,557, including 
engineering and design, supervision and administration, 
and real estate activities. In addition, resurfacing of 
access road cost $361,166 and erosion control cost 
$168,617. The Colorado River Locks were operated and 
maintained at a cost of $828,907, including engineering 
and design and supervision and administration. (See 
Table 15-H for dredging operations.) 
9. HOUSTON SHIP CHANNEL, TX 
Location. Connects Galveston Harbor, at a point 
opposite Port Bolivar, with city of Houston, Texas, 
extending 50 miles northwesterly across Galveston Bay 
through San Jacinto River and Buffalo Bayou to a 
turning basin at head of Long Reach with light-draft 
channel 7 miles long from turning basin to Main Street, 
Houston. (See National Ocean Survey Charts 11324/5, 
11327, 11328, and 11329.) 
Previous project. For details see page 1856 of Annual 
Report for 1915. 
Existing project. Provides for channel dimensions in 
sections of the waterway shown in Table 15-F. 
Also provides for certain cut-offs, for easing sharp 
bends, an earthen dam across the upper end of Turkey 
Bend, and for off-channel silting basins as deemed 
necessary by the Chief of Engineers. Construction of 
26,000 linear feet of pile dike to protect the channel in 
upper Galveston Bay was deauthorized by Sec. 12 of PL 
93-251. The 40-foot project was completed in March 1966. 
Dredging a channel in Greens Bayou to Mile 1.57 was 
completed in 1970. Only work remaining is dredging 
Greens Bayou, Mile 1.57 to Mile 2.73, which is in the 
inactive category. (See Table 15-E for total cost of 
existing project to September 30, 1983.) 
Mean tidal range under ordinary conditions is 0.6 foot 
to 1.3 feet in lower part of Galveston Bay; 0.6 foot to 1.3 
feet in upper bay; and 0.5 to 1 foot in San Jacinto River 
and Buffalo Bayou. Extreme ranges under ordinary 
conditions are about 2 feet, 1.2 feet and 1 foot, 
respectively. Freshets caused rises of over 12 feet in 
Buffalo Bayou; however, this condition has not occurred 
since completion of Addicks and Barker Dams for flood 
control on upper watershed of Buffalo Bayou. Height of 
tides is dependent largely on the wind, and during strong 
"northers" in winter season the water surface may be 
depressed 2 feet below mean low tide. 
Local cooperation. Complied with except for inactive 
portions of Greens Bayou. 
Terminal facilities. City of Houston and Port of 
Houston Authority operate modern terminals which 
supplement privately owned wharves, piers, and docks, 
as described in Port Series No. 24 (revised 1980), Corps of 
Engineers. Facilities are considered adequate for 
existing commerce. 
Operations during fiscal year. Routine 
maintenance. Disposal areas were sprayed for mosquito 
control at a cost of $48,150. Rehabilitation of disposal 
area levees cost $1,870,451. (See Table 15-H for dredging 
operations.) 
10. MATAGORDA SHIP CHANNEL, TX 
SLocation. This is a consolidation of shallow draft 
channel improvements of "Channel from Pass Cavallo to 
Port Lavaca, Texas," and deep draft channel 
improvements authorized under "Matagorda Ship 
Channel, Texas." Bar at Pass Cavallo is 125 miles 
southwest of Galveston entrance and 54 miles north of 
SAransas Pass. It connects Matagorda Bay with the gulf. 
Project extends across Matagorda Bay and Lavaca Bay to 
towns of Port Lavaca and Point Comfort. These two 
towns are on opposite sides of Lavaca Bay and both are 
about 26 miles northwest from Pass Cavallo. (See 
National Ocean Survey Chart 11316.) 
Existing project. Existing project dimensions 
provided for in various channels and basins are listed in 
Table 15-F on channel dimensions. 
Project also provides for dual jetties at entrance, south 
jetty extending 6,000 feet to 24-foot depth in the gulf and 
north jetty extending 5,900 feet to 24-foot depth. Under 
ordinary conditions mean tidal range is about 1 foot and 
extreme range about 2 feet. Height of tide is dependent 
largely on the wind, and during strong "northers" in 
winter season the water surface may be depressed 2 feet 
below mean low tide. Estimated cost for new work is: 
$18,058,777 Federal (Corps), and $12,859,000 non- 
Federal, including $12,259,619 contributed funds, 
$182,000 for lands, $220,000 for relocations, and 
$196,581 other costs. The project was completed in 
March 1967 
Local cooperation. Fully complied with. 
Terminal facilities. Privately owned facilities at Port 
Lavaca, municipally owned facilities at mouth of Lynn 
bayou, privately owned and pdiblicly owned facilities at 
Point Comfort, Texas. These facilities are considered 
adequate for present commerce. Facilities at Point 
Comfort consist of a channel, turning basin with wharfs, 
oil dock and loading equipment, all owned by Aluminum 
Company of America; and a wharf built by local interest 
at Point Comfort turning basin. 
Operations during fiscal year. Routine 
maintenance. (See Table 15-H for dredging operations.) 
15-6

GALVESTON TEXAS DISTRICT 
11. SABINE-NECHES WATERWAY, TX 
Location.This is a consolidation of old improvements 
of "Harbor at Sabine Pass and Port Arthur Canal" and 
"Sabine-Neches Canal, including Sabine River to 
Orange and Neches River to Beaumont, Texas." Sabine 
Pass is on Gulf of Mexico about 58 miles east Qf Galveston 
and 280 miles west of Southwest Pass, Mississippi River. 
It connects Sabine Lake with gulf. Port Arthur canal 
extends 7 miles from near upper end of Sabine Pass to 
Port Arthur docks at mouth of Taylors Bayou. Near its 
upper end, Sabine-Neches canal joins and extends to 
mouths of Neches and Sabine Rivers. Waterway next 
extends up Neches River to Beaumont and up Sabine 
River to Orange. (See National Ocean Survey Charts 
11341, 11342, and 11343.) 
Previous projects. For details see page 1863 of 
Annual Report for 1915, page 985 of Annual Report for 
1916, and page 873 of Annual Report for 1926. 
Existing project. Existing project dimensions 
provided for in various channels and basins are set forth 
in Table 15-F on channel dimensions. Project also 
provides for two stone jetties at Sabine Pass entrance 
from the gulf, western jetty to be 21,905 feet long and 
eastern jetty 25,310 feet long. Project further provides for 
removal of guard lock in Sabine-Neches Canal, 
construction of suitable permanent protective works 
along Sabine Lake frontage owned by city of Port Arthur 
to prevent dredged material from entering Sabine Lake 
and to prevent erosion of material deposited, 
reconstruction of Port Arthur Bridge, and relocation of 
Port Arthur field office. Mean tidal variation at entrance 
is about 1.5 feet, at Port Arthur about 1 foot, and at 
Orange and Beaumont about 0.5 foot. Prolonged north 
winds during winter season have depressed water 
surface as much as 3.4 feet below mean low tide while 
tropical disturbances have caused heights as much as 8 
feet above mean low tide. 
Existing project is complete except for inactive 
portions. Removal of obstructive bridge at Port Arthur 
was completed May 1969. The high level fixed bridge 
across Sabine-Neches Canal was completed October 
1970. Deepening project to 40 feet was completed April 
1972. (See Table 15-E for total cost of existing project to 
September 30, 1983.) 
Local cooperation. Complied with except for inactive 
portions. 
Terminal facilities. See volume 2, Port Series No. 22 
(revised 1981), Corps of Engineers. Facilities are 
considered adequate for present commerce. 
Operations during fiscal year. Routine 
maintenance. (See Table 15-H for dredging operations.) 
12. TEXAS CITY CHANNEL, TX. 
Location. Texas City is on the mainland of Texas on 
west side of Galveston Bay, about 10 miles northwest of 
city of Galveston. (See National Ocean Survey Charts 
11324/5.) 
Previous projects. For details see page 1856 of 
Annual Report for 1915. 
Existing project. Provides for channel 40 feet deep, 
400 feet wide and about 6.75 miles long, from Bolivar 
Roads to a turning basin at Texas City, 40 feet deep, 
1,000 feet to 1,200 feet wide and 4,253 feet long; and an 
Industrial Canal, 40 feet deep and 300-400 feet wide 
extending a distance of 1.7 miles southwestward from 
the south end of Texas City Turning Basin, and a turning 
basin, 40 feet deep, 1,000 feet wide and 1,150 feet long. 
Project also provides for easing the approach to the 
turning basin; a pile dike 28,200 feet long, parallel to and 
north of the channel; and a rubble-mound dike, 27,600 
feet long, along the southerly side of the pile dike. 
The 40-foot channel was completed in June 1967. 
Widening the Texas City Turning Basin; realigning the 
Texas City Turning Basin to a location 85 feet easterly 
from its present position; and enlargement through 
widening and deepening of the Industrial Canal and 
basins was initiated in July 1980 and completed in June 
1982. The only work remaining is deferred construction 
consisting of widening the Industrial Canal from 250 feet 
to 300 feet at 40 foot depth. (See Table 15-E for total cost 
of existing project to September 30, 1983.) 
Under ordinary conditions mean tidal range is about 
1.3 feet and extreme range is about 2 feet. Height of tide 
is dependent largely on the wind and during strong 
"northers" water surface may be depressed 2 feet below 
mean low tide. Estimated cost for new work is 
$14,300,000 Federal (Corps), excluding expenditures on 
previous projects, and $1,793,700 non-Federal, including 
$127,741 contributed funds, $248,000 work contribution, 
$427,959 lands, $984,000 levees and spillways and 
$6,000 for removal of barge mooring facilities from 
Snake Island. 
Local cooperation. Fully complied with. 
Terminal facilities. Privately owned terminal 
facilities are on the mainland at inner end of this channel 
and are considered adequate for existing commerce. A 
deep-draft channel and turning basin extend about 1.9 
miles southwestward from south end of Texas City 
Turning Basin have been constructed by local interests. 
See Port Series No. 23 (revised 1979), Corps of Engineers. 
Operations during fiscal year. Maintenance: 
Environmental studies were conducted. 
13. TRINITY RIVER AND 
TRIBUTARIES, TX 
Location. The main stem of the Trinity River is 
formed at Dallas by the confluence of the West Fork and 
the Elm Fork at river mile 505.5. The mouth of the 
Trinity is about one-half mile west of Anahuac, Texas. 
(See Geological Survey base map, Texas, scale 
1:500,000.) 
Previous project. For details of abandoned locks and 
dam construction see page 986 of Annual Report for 
1932. 
Existing project. See individual detailed reports on 
Anahuac Channel, Channel to Liberty and Wallisville 
Lake. Project includes the existing Federal project 
designated as "Mouth of Trinity River, Texas," which 
15-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
was completed in 1907 at a cost of $80,000 (no cost to local 
interest). Project is not being maintained. (See Table 
15-E for total cost of existing project to September 30, 
1983.) 
Local cooperation. See individual detailed reports on 
Channel to Liberty and Wallisville Lake. There is no 
local cooperation required for Anahuac Channel. 
Terminal facilities. Privately owned wharves and 
piers at Anahuac, Moss Bluff, Wallisville, and Liberty, 
Texas, are adequate for existing commerce. 
13A. ANAHUAC CHANNEL, TX 
Location. Extends from 6-foot depth in Galveston Bay 
to Anahuac, Texas, opposite mouth of Trinity River 38 
miles north of Galveston, Texas. (See National Ocean 
Survey Chart 11323.) 
Existing project. No project dimensions authorized by 
1905 River and Harbor Act. A 6- by 80-foot channel, 
16,000 feet long was dredged in 1905. At present a 6- by 
100-foot channel is maintained. Under ordinary 
conditions tidal range is 0.6 to 1.2 feet. Height of tide is 
dependent largely on wind. Strong north winds depress 
water surface 1.5 feet below mean sea level. Latest 
published map is in House Document 440, 56th 
Congress, 1st Session. Project was completed in 1911. 
Local cooperation. None required. 
Terminal facilities. Privately owned wharves and 
piers are the only terminal facilities at Anahuac. 
Operations during fiscal year. Routine 
maintenance including mosquito control spraying. 
13B. CHANNEL TO LIBERTY, TX 
Location. Improvement is located in Galveston Bay 
and tidal reach of lower Trinity River. (See Geological 
Survey Maps for Anahuac, Cove, Moss Bluff, and 
Liberty, Texas.) 
Previous projects. For details see page 986 of Annual 
Report for 1932. 
Existing project. Provides for a 6-foot channel from 
Anahuac to Liberty which was completed in 1925. A 
navigable channel from the Houston Ship Channel near 
Red Fish Bar in Galveston Bay to Liberty, Texas, with 
depth of 9 feet and width of 150 feet, extending along the 
east shore of Trinity Bay to the mouth of the Trinity 
River at Anahuac, thence in the river channel to a 
turning basin at Liberty, Texas, and a protective 
embankment along the west side of the channel in 
Trinity Bay. 
The 6-foot Channel to Liberty was completed in 1925, 
The 9-foot Channel to Liberty has been dredged from 
junction with Houston Ship Channel to a point one mile 
below Anahuac, Texas. Work remaining consists of 
dredging a 9- by 150-foot channel from one mile below 
Anahuac, Texas to Liberty, Texas. 
Local cooperation. Fully complied with for portion of 
"Channel to Liberty" between Houston Ship Channel 
and 1 mile below Anahuac, Texas, as required by 1946 
River and Harbor Act (H. Doc. 634, 79th Cong., 2nd 
Sess.), but not complied with for remaining portion of 
"Channel to Liberty" as required by River and Harbor 
Act of 1945 (H. Doc. 403, 77th Cong., 1st Sess.) at an 
estimated total cost of $550,000, of which $460,000 is for 
lands and rights-of-way and $90,000 for pipeline 
relocations for 9- by 150-foot channel. 
Terminal facilities. Privately owned wharves and 
docks at Anahuac, Wallisville, Texas Gulf Sulphur Co.'s 
slip, Moss Bluff and Liberty, Texas, are adequate for 
existing commerce. 
Operations during fiscal year. Routine 
maintenance including mosquito control spraying. 
13C. WALLISVILLE LAKE, TX 
Location. Dam is at river mile 3.9, about 4 miles 
northwest of Anahuac, Texas. (See National Ocean 
Survey Chart 11323.) 
Existing project. Provides for construction of a dam 
and overflow spillway approximately 8 miles long to 
prevent salinity intrusion and create a 5,600-acre 
reservoir. The maximum pool elevation will be 4 feet 
above National Geodetic Vertical Datum. Project 
provides for an 84 foot by 600-foot navigation lock to 
facilitate navigation on Channel to Liberty. The sill has 
a depth of minus 16 feet below National Geodetic 
Vertical Datum. Project also provides for two 
recreational areas. Dam controls a drainage area of 1,262 
square miles below Livingston Dam (non-Federal project 
at channel mile 99.2) and has a storage capacity of 58,000 
acre-feet. Under ordinary conditions mean tidal range in 
bay is from 0.6 foot to 1.2 feet. Height of tide is dependent 
largely on wind. Strong northerly winds depress water 
surface 1.5 feet below mean sea level. Total estimated 
cost of authorized project is $62,500,000 Federal (Corps). 
(October 1, 1983 base price.) 
A contract for construction of access road, Big Hog 
intake structure, intake canal and access bridge was 
completed in October 1968. Work started in July 1970 on 
construction of the lock and dam, roads, diversion 
channel, and navigation channel. Work was suspended 
in February 1973 because of an injunction halting 
construction. Protective work on the lock and dam was 
permitted and was completed in April 1973. An 
exception to the injunction was granted for plugging oil 
wells which was completed in August 1973. Notice of 
appeal to the Court of Appeals for the Fifth Circuit was 
filed in April 1973. In August 1974, the Court of Appeals 
reversed the judgment and remanded the case with 
directions that a revised or supplemental statement be 
prepared and judged anew. Final supplement to the 
Environmental Impact Statement for the modified 
project authorized in the Supplemental Appropriations 
Act, 1983 (PL 98-63) was submitted to the 
Environmental Protection Agency on September 21, 
1983. The schedule for the completion of construction for 
the modified project is dependent on the time required to 
coordinate with the courts to lift the injunction, and the 
availability of construction funds. 
Local cooperation. Local interest must contribute an 
amount equal to cost allocated to water supply, one-half 
of cost allocated to salinity control and cost allocated to 
recreation less cost of basic facilities and less 15 percent 
15-8

GALVESTON TEXAS DISTRICT 
of total project cost. Local interest contribution is 
estimated at $8,427,000. 
Operations during fiscal year. New Work: The Post 
Authorization Change Report was completed, modified 
project was authorized, and final supplement to the 
Environmental Impact Statement was submitted to the 
Environmental Protection Agency. 
Maintenance: Ranger surveillance, administration of 
project, and administration of duck blind permit 
program was conducted.. 
14. RECONNAISSANCE AND 
CONDITION SURVEYS 
Reconnaissance and Condition Surveys were 
conducted on the following projects: 
Fiscal Year 
Project Date of Survey Cost 
Cedar Bayou 
Double Bayou 
Total 
Jan 1983 
Jul 1983 
$ 84 
42 
$126 
15. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation activities pursuant to Section 107, Public 
Law 86-645 (preauthorization). 
Reconnaissance study to investigate extending Sabine 
River Channel to accommodate a lay berth facility for 
the Orange County Navigation District was terminated 
in Fiscal Year 1983. Fiscal year cost was $153. 
Reconnaissance study to investigate providing a 12 
foot by 125 foot channel to connect Rockport, Texas with 
the Gulf Intracoastal Waterway was terminated in 
Fiscal Year 1983. Fiscal year cost was $1,546. 
Beach Erosion 
16. CORPUS CHRISTI BEACH, TX 
(RESTORATION PROJECT) 
Location. Corpus Christi Beach, a shore area having a 
length of about 2 miles, is located on the west side of 
Corpus Christi Bay in Nueces County at Corpus Christi, 
Texas. (See National Ocean Survey Charts 11309 and 
11311.) 
Existing project. The plan of improvement provided 
for initial restoration of eroded areas of Corpus Christi 
Beach, over a shore length of 1.4 miles, located on the 
easterly side of Rincon Peninsula, with periodic 
nourishment as required. Construction was completed in 
March 1978; however, erosion and/or littoral movement 
of the beach will be monitored during ten years following 
completion to determine periodic nourishment 
requirements. Estimated cost of new work is $2,550,000 
Federal (Corps) and $2,665,000 non-Federal consisting of 
$2,550,000 contributed funds, $43,000 relocations, and 
$72,000 lands. (October 1, 1983 base price.) 
Local cooperation. Fully complied with except for 
periodic nourishment. 
Operations during fiscal year. No construction 
performed in Fiscal Year 1983. 
Flood Control 
17. ARROYO COLORADO, 
RIO HONDO, TX 
Location. The project is located on Arroyo Colorado at 
Rio Hondo, Texas which is approximately ten miles 
northeast of Harlingen, Texas and 30 miles north 
northwest of Brownsville, Texas. 
Existing project. The project provides for bank 
protection to 400 feet of the east bank of Arroyo Colorado 
downstream of Farm-to-Market Road 106. Estimated 
cost for new work is $201,300 Federal (Corps) and $7,000 
non-Federal. Contract for construction was awarded in 
September 1983. 
Local cooperation. Fully complied with. 
Operations during fiscal year. Plans and 
specifications were completed. Contract was advertised, 
bids opened, and contract awarded. 
18. BUFFALO BAYOU AND 
TRIBUTARIES, TX 
Location. Improvements are on Buffalo Bayou 
watershed, a part of San Jacinto River watershed, in 
Harris County, west and northwest of city of Houston, 
Texas. (See Geological Survey quadrangle sheets for 
Harris County.) 
Existing project. Provides for improvement of Buffalo 
Bayou and its tributaries above turning basin of Houston 
Ship Channel to control floods for protection of city of 
Houston, and prevent deposition of silt in turning basin 
of ship channel by construction of detention reservoirs, 
enlargement and rectification of channels and 
construction of control works. Estimated cost of new 
work is $136,500,000 Federal (Corps) including 
$11,500,000 for recreational facilities at completed 
projects (Code 713 funds), and $96,417,000 non-Federal, 
consisting of $84,917,000 for lands and relocations, and 
$11,500,000 contributions for recreational facilities. 
(October 1, 1983 base price.) 
Construction of Barker Dam was completed in 
February 1945. Construction of Addicks Dam and 7.4 
miles of channel rectification downstream from Addicks 
and Barker Dams was completed in October 1948. 
Modification of Barker and Addicks Dams consisting of 
gating of two uncontrolled conduits in each dam, was 
completed in 1969. Channel rectification on White Oak 
Bayou was completed in 1976. Major rehabilitation of 
Addicks and Barker Dams to prevent seepage through 
the embankment was completed in 1982. Work 
remaining consists of rectification of approximately 22 
miles of main stem of Buffalo Bayou. Negotiations are in 
progress with the city of Houston for construction of the 
recreation facilities. 
Local cooperation. Section 203, 1954 Flood Control 
Act applies. Local interests have accomplished all 
required local cooperation on Brays Bayou and White 
Oak Bayou. On Buffalo Bayou, local interests purchased 
interests that the United States had in 7 miles of 
rectified channel below Barker and Addicks Dams for 
$256,651. Of the remaining required rights-of-way on 
15-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Buffalo Bayou, local interests have acquired about 40 
percent. About 53 percent of required bridge relocations 
and 3 percent of the required utility relocations have 
been accomplished. Advance of $4,400,000 by the Harris 
County Flood Control District was refunded in 
September 1956. Public Law 86-53 authorized 
reimbursement of $38,726 to Galveston, Houston and 
Henderson Railroad Company for bridge alterations at 
Brays Bayou. Non-Federal contributions totaled $63,661 
for project betterments. Recreation development is 
subject to conditions of non-Federal cost-sharing under 
Federal Water Project Recreation Act of 1965. A cost 
sharing contract covering the work proposed was 
approved by the Secretary of the Army in 1982. 
Operations during fiscal year. Routine operations 
and maintenance at Addicks and Barker Dams. 
19. FREEPORT AND VICINITY, TX 
(HURRICANE-FLOOD 
PROTECTION) 
Location. Freeport is in southern part of Brazoria 
County on Gulf of Mexico at mouth of Brazos River, 
about 43 miles southwest of Galveston, Texas. 
Existing project. Authorized project provides for 
hurricane-flood protection for a highly industrialized 
area and community of about 39,000 persons. Major 
features of project consist of improvements to 42.8 miles 
of existing levees, two interior drainage pumping plants 
and 2.1 miles of new levee. The project was completed in 
February 1982. Estimated cost of new work is 
$29,311,000 Federal (Corps) and non-Federal 
$12,562,000 consisting of $8,709,000 cash, $1,127,000 
lands, and $2,726,000 relocations. 
Local cooperation. Fully complied with. 
Operations during fiscal year. Operating manuals 
were completed. 
20. HIGHLAND BAYOU, TX 
Location. Rises near Arcadia, in Galveston County, 
Texas, and flows into Jones Bay, an arm of West Bay. The 
watershed, with an area of about 38 square miles lies 
entirely within Galveston County and is about 14 miles 
long and varies in width from about 0.3 miles at its lower 
end to a maximum of about 5 miles near its midpoint. 
Existing project. Plan of improvement provides for 
enlargement and rectification of Highland Bayou 
Channel and construction of a diversion dam in 
Highland Bayou, with a diversion channel extending 
southerly from the diversion dam and emptying into 
Jones Bay, which lies on the north side of West Bay. 
Initial construction contract was awarded in June 1974. 
Work completed consists of a diversion dam, 8.2 miles of 
diversion channel, a railroad bridge crossing the 
diversion channel, and 3.1 miles of upper Highland 
Bayou Channel. Estimated cost of new work is 
$20,500,000 Federal (Corps) and $6,120,000 non-Federal 
consisting of $3,020,000 lands and $3,100,000 for 
relocations. (October 1, 1983 base price.) 
Local cooperation. Section 204, 1965 Flood Control 
Act applies. 
Operations during fiscal year. A contract for 
construction of drainage structures, Mile 9.3 and 9.4, was 
initiated at a fiscal year cost of $59,340. A contract for 
repair of eroded areas was completed at a fiscal year cost 
of $1,801. 
21. PORT ARTHUR AND VICINITY, 
TX, (HURRICANE-FLOOD 
PROTECTION) 
Location. Port Arthur is on west shore of Sabine Lake 
in extreme southeast part of Texas, about 14 miles from 
the gulf. Area under consideration is comprised of about 
38,500 acres, and includes cities of Port Arthur and 
Groves, towns of Griffing Park, Pearl Ridge, and 
Lakeview, and adjacent industrial areas. 
Existing project. Authorized plan provides for raising 
and reconstructing 6.3 miles of existing concrete and 
steel sheet-pile seawall; constructing 0.3 mile of new 
concrete and sheet-pile seawall; raising and improving 
3.0 miles of existing earth levees; constructing 20.3 miles 
of new earth levees and constructing five interior 
drainage pumping plants. Raising and strengthening of 
levees surrounding Gulf Oil Company's fresh water 
reservoir was placed in the "inactive" category in 
December 1980. The project was initiated in March 1966 
and the active portion of the project is 99 percent 
complete. Estimated cost for new work, excluding 
"inactive" portion, is $59,979,000 Federal (Corps) and 
$26,154,000 non-Federal consisting of $16,134,000 cash 
contributions, $3,403,000 for lands, $6,168,000 for 
relocations, and $449,000 for pumping station 
betterments and levee realignment betterments. 
Local cooperation. Fully complied with. 
Operation during fiscal year. Prior year cost on 
contract for construction of levees, final stage, Sabine 
Tank Farm and Taylors Bayou Area was adjusted at a 
fiscal year cost of (-)$3,297. A study was initiated to 
evaluate the impact of modifying the operation of 
Alligator Bayou Pumping Plant. 
22. TAYLORS BAYOU, TX 
Location. Watershed of Taylors Bayou is in extreme 
southeast corner of Texas adjoining basins of Neches 
River and Sabine Lake on the east. City of Port Arthur is 
about 8 miles from the main stream of Taylors Bayou. 
Existing project. Improvement consists of enlarging 
and rectifying approximately 53 miles of natural and 
artificial channels on Taylors Bayou and tributary water 
courses. Phase I consists of constructing a gated 
structure to prevent saltwater intrusion and 2.9 miles of 
new diversion channel and enlarging 1.8 miles of Gulf 
Intracoastal Waterway and a 1.9 mile section of the 
Outfall Canal. Phase II consists of enlarging 6.0 miles of 
Taylors Bayou, 14.3 miles of Hillebrandt Bayou, 1.5 miles 
of Pivotot Bayou, 2.3 miles of Bayou Din, and 3.5 miles of 
Willow Marsh Bayou. Phase III consists of enlarging 7.0 
miles of North Fork Taylors Bayou, 7.8 miles of South 
Fork Taylors Bayou and 4.4 miles of Mayhaw Bayou. The 
Phase III portion of the project was placed in the 
"inactive" category in November 1980. Initial contract 
15-10

GALVESTON TEXAS DISTRICT 
on the "active" portion of the project was awarded in 
August 1982. Estimated cost for new work, excluding 
inactive portion, is $53,700,000 Federal (Corps) and 
$26,190,000 non-Federal, including $18,307,000 cash 
contribution, $4,277,000 lands, and $3,606,000 for 
relocations. (October 1, 1983 base price.) 
Local cooperation. Section 204, 1965 Flood Control 
Act, applies. 
Operation during fiscal year. The Outfall Canal was 
completed at a fiscal year cost of $2,048,313. 
23. TEXAS CITY AND VICINITY, TX 
(HURRICANE-FLOOD 
PROTECTION) 
Location. On the west and southwest shore of 
Galveston Bay, about 9 miles northwest of Galveston, 
Texas. Project fronts on the west side of Galveston Bay 
and protects a land area of about 36 square miles. 
Existing project. Plan provides for construction of 
improvements for control of storm tides. Improvements 
consist of 15.9 miles of new levees, 1.3 miles of concrete 
floodwall, related drainage and stoplog structures, one 
tide control structure, and two pumping plants. The 
project was initiated in 1962. All work is complete except 
for the La Marque Pumping Plant and drainage 
structures. Construction of the La Marque Pumping 
Plant was initiated in September 1982. Estimated cost 
for new work is $37,560,000 Federal (Corps) and 
$16,354,000 non-Federal, including $13,678,000 cash 
contribution, $1,071,000 work contribution, and 
$1,349,000 for lands, and $256,000 for ramps in lieu of 
closure structures and increased low flow pumping 
capacity for La Marque Pumping Plant. 
Local cooperation. Fully complied with. 
Operations during fiscal year. Contract for 
construction of levee and closure structures, Southwest 
Leg, was continued at a fiscal year cost of $19,480. 
Supply contract for the La Marque Pumping Plant cost 
$236,562. Contract for construction of La Marque 
Pumping Plant was initiated at a fiscal year cost of 
$864,110. Modifying hoisting devices on Moses Lake tide 
gate cost $38,200. 
24. VINCE AND LITTLE VINCE 
BAYOUS, TX 
Location. Watershed of Vince Bayou and tributary, 
Little Vince Bayou, has an area of about 17 square miles 
and lies entirely within Harris County. Vince Bayou is a 
minor tributary of Buffalo Bayou in San Jacinto River 
Basin on upper gulf coast of Texas. 
Existing project. Project provides for enlarging and 
rectifying channel of Vince Bayou from mouth to a point 
about 7.3 miles upstream and Little Vince Bayou from 
mouth to a point about 4.2 miles upstream, a total 
distance in both streams of about 11.5 miles. The project 
was initiated in 1968. All work on Vince Bayou is 
complete. Planning is in progress on Little Vince Bayou. 
Estimated cost for new work is $19,100,000 Federal 
(Corps) and $17,040,000 non-Federal, consisting of 
$5,040,000 for lands and $12,000,000 for relocations. 
(October 1, 1983 base price.) 
Local cooperation. Sec. 203, 1962 Flood Control Act, 
applies. Local interests have acquired all real estate and 
accomplished all required relocations on Vince Bayou. 
On Little Vince Bayou, local interests have acquired 80 
percent of the real estate and accomplished 10 percent of 
the required relocations. 
Operations during fiscal year. Engineering and 
design continued on Little Vince Bayou. 
25. INSPECTION OF COMPLETED 
FLOOD CONTROL WORKS 
Inspections of completed projects operated and 
maintained by local interests were made on the following 
projects at a total cost of $44,710. 
Project 
Lavaca River Flood Protection 
project, Halletsville, TX 
Little Cypress Bayou Levee, TX 
Port Arthur and Vicinity, TX 
Texas City and Vicinity, TX 
Date of Inspection 
Jul 1983 
Jun 1983 
Jun 1983 
Feb 1983 
26. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control activities pursuant to Section 205 of 1970 
Flood Control Act, Public Law 858, 80th Congress, as 
amended. 
Reconnaissance study of flood problems on Chocolate 
Bayou, Calhoun and Victoria Counties, cost $25. 
Reconnaissance study of flood problems on Lavaca 
River at Hallettsville, Texas cost $12,425. 
Preparation of detailed project report for flood 
problems at Kirbyville, Texas was continued at a fiscal 
year cost of $62,322. 
Preparation of detailed project reports for flood 
problems at East and West Edinburg, Texas were 
continued at fiscal year costs of $124,770 and $77,018, 
respectively. 
Emergency flood control activities - repair, flood 
fighting, and rescue work (Public Law 99, 84th Congress 
and antecedent legislation). 
Costs were $121,140 for disaster preparedness and 
$608 for emergency operations. 
General Investigations 
27. SURVEYS 
Fiscal year costs were $1,877,622 of which $280,151 
was for navigation studies, $1,533,771 was for flood 
damage prevention studies, $22,188 was for shoreline 
protection studies, $10,437 was for coordination with 
other agencies, $28,249 was for Special Investigations, 
and 2,826 for preauthorization studies Phase I (Lower 
Rio Grande Basin). 
15-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
28. ADVANCE ENGINEERING AND 
DESIGN 
Neches River and Tributaries, Salt Water Barrier at 
Beaumont, Texas - The project will provide for an 
overflow dam in the Neches River, a gated salt water 
barrier consisting of five 56 feet by 24.5 feet tainter 
gates; a gated navigation bypass channel with a clear 
opening of 56 feet and a depth of 16 feet; an access road 
and levee; and an auxiliary dam across a canal which 
drains an adjacent bayou. Estimated preconstruction 
planning cost is $1,655,000. Preconstruction planning 
was initiated in 1978. The Phase I General Design 
Memorandum was completed in 1982. A Feature Design 
Memorandum for the access road and levee was 
completed in 1983. Fiscal year costs were $27,765. 
Clear Creek, Texas - The project will provide for 
enlargement and rectification of the existing Clear 
Creek channel from the upper end of Clear Lake at Mile 
3.8 to improved channel Mile 26.05, a distance of 
approximately 22 miles; and an additional outlet with a 
gated structure from Clear Lake to Galveston Bay. A 
number of bridges, pipelines and other structures which 
now obstruct flood flows will require relocation or 
alteration. Estimated preconstruction planning cost is 
$2,830,000. Preconstruction planning was initiated in 
1972. The Combined General Design Memorandum and 
the Final Environmental Impact Statement were 
completed in 1982. Fiscal year costs were $177,349. 
29. PLANNING AND ENGINEERING 
Upper White Oak Bayou and Tributaries, vicinity of 
Houston, Texas - The project will provide for channel 
improvements on White Oak Bayou from Mile 10.7 to 
Mile 19.9; on Cole Creek from Mile 0 to Mile 4.9; and on 
Vogel Creek from Mile 0 to Mile 4.5, for a total of 18.6 
miles. Project also provides for flood plain zoning and 
regulation on the residual 100-year flood plains on White 
Oak Bayou from Mile 19.9 to near Mile 25.5; on Cole 
Creek form Mile 4.9 to near Mile 6.9; and on Vogel Creek 
from Mile 4.5 to near Mile 6.5; and includes recreational 
development along White Oak Bayou from near Mile 
14.6 to near Mile 18.3. Estimated planning and 
engineering estimate is $3,415,000. Planning and 
engineering studies were initiated in 1982. Fiscal year 
costs were $456,969. 
30. COLLECTION AND STUDY OF 
BASIC DATA 
Flood plain management and technical services were 
performed at a cost of $15,892 and $74,294, respectively. 
Anticipated studies cost $2,523. 
Hydrologic studies cost $3,056. 
15-12

GALVESTON TEXAS DISTRICT 
TABLE 15-A 
See 
Section 
in Text Project 
1. Aquatic Plant 
Control (Southwestern 
Division) 1965 Act 
2. Brazos Island 
Harbor, TX 
3. Channel to Port 
Bolivar, TX 
4. Corpus Christi 
Ship Channel, TX 
(Regular Funds) 
(Contributed Funds) 
5. Double Bayou, TX 
6. Freeport Harbor, TX 
7. Galveston Harbor 
and Channel, TX 
8. Gulf Intracoastal 
Waterway between 
Apalachee Bay, FL 
and the Mexican 
Border 
(Galveston Dist.) 
COST AND FINANCIAL STATEMENT 
15-13 
Funding 
New Work: 
Approp. 
Cost 
New Work; 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major rehab. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maor rehab. 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Minor rehab. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major rehab. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maor rehab. 
Approp. 
Cost 
Total Cost To 
FY 80 FY 81 FY 82 FY 83 Sep. 30, 19832 
125,000 140,000 60,000 140,000 1,157,1001 
143,181 145,705 97,972 95,390 1,109,5241 
884,900 - (-)3,877 - 11,857,5022 
944,261 - (-)3,877 - 11,857,5022 
3,970,800 2,017,038 1,518,000 4,593,000 34,313,385w 
3,979,481 2,013,558 1,510,837 2,961,443 32,670,029* 
- - - - 2,170,080 
- - - - 2,170,080 
- - - - 133,925' 
- - - - 133,9254 
174,125 540 - 45,000 1,075,7225 
174,041 531 - 40,531 1,071,159� 
285,000 1,100,000 2,191,491 3,500,000 47,372,3596 
271,749 1,099,502 1,441,665 2,081,707 45,185,3486 
7,658,074 9,084,000 7,300,000 3,306,300 70,519,028' 
8,400,775 9,666,964 7,372,185 1,972,610 69,159,977' 
- - - - 3,576,684 
- - - - 3,576,684 
- (-)127,433 - 400,000 1,892,088 
- (-)152,346 6,735 682 1,474,592 
- - - - 226,558 
- - - - 226,558 
18,750 357,000 - 27,000 1,121,978' 
18,537 350,279 6,413 27,107 1,121,564' 
85,000 25,000 - 100,000 2,867,152' 
39,710 44,816 19,853 8,628 2,766,403' 
4,258,500 2,528,000 2,080,000 4,243,200 33,805,465 10o 
4,451,698 2,539,513 2,070,483 3,742,067 33,294,31210 
- - - - 8,935 
- - - - 8,935 
- - - - 29,096,39211 
- - - - 29,096,39211 
4,141,100 695,000 6,165,000 381,000 59,449,00312 
3,407,144 921,444 6,708,009 105,968 59,167,53112 
- - - - 7,969,329 
- - - - 7,969,329 
2,103,500 1,530,000 (-)1,491 600,00 50,588,3033 
2,156,246 1,327,915 125,098 114,177 50,000,06313 
7,522,800 13,853,956 12,081,000 17,523,000 161,479,43014 
7,444,379 14,378,786 9,693,675 16,141,134 157,451,14814 
- - - - 434,638 
- - - - 434,638

TABLE 15-A 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
COST AND FINANCIAL STATEMENT 
See 
Section 
in Text Project 
9. Houston Ship 
Channel, TX 
(Regular Funds) 
10. Matagorda Ship 
Channel, TX 
(Regular Funds) 
11. Sabine-Neches 
Waterway,TX 
(Regular Funds) 
12. Texas City Channel, 
TX 
13. Trinity River and 
Tributaries, TX 
(Includes Wallisville) 
16. Corpus Christi Beach, 
TX (Restoration Project) 
(Contributed Funds) 
17. Arroyo Colorado, 
Rio Hondo, TX 
18. Buffalo Bayou and 
Tributaries, TX 
19. Freeport and Vicinity, 
TX Hurricane Flood 
Protection 
(Regular Funds) 
(Contributed Funds) 
Funding 
Minor rehab. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major rehab. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Recreation 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major rehab. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Contrib 
Cost 
Total Cost To 
FY 80 FY 81 FY 82 FY 83 Sep. 30, 198328 
- - - - 835,873 
- - - - 835,873 
- - - - 35,760,38215 
- - - 35,760,38215 
3,683,747 6,701,900 1,150,000 6,945,000 84,319,14316 
3,970,774 7,335,604 1,100,243 5,090,215 82,377,84016 
- - - - 18,058,77717 
- - - - 18,058,77717 
3,336,300 4,465,000 1,770,000 1,677,000 30,179,243 
3,853,102 2,282,888 3,958,543 1,360,493 29,857,795 
- - - - 56,136,81518 
- - - - 56,136,81518 
635,625 8,590,000 5,873,000 4,560,200 105,592,42016 
735,933 8,326,011 6,191,822 3,267,663 104,283,595 19 
111,100 6,875,000 282,000 - 13,325,47220 
382,394 6,313,649 843,251 7,733 13,325,47220 
293,000 1,834,000 3,260,000 - 17,315,66121 
336,870 1,182,621 3,867,333 25,864 17,296,89421 
- - - - 726,158 
- - - - 726,158 
- 210,000 255,000 300,000 28,199,67622 
284,297 185,244 212,946 156,232 27,981,90522 
386,550 95,460 903,000 165,000 7,002,30323 
385,934 88,068 902,018 138,496 6,966,64123 
- - - - 1,555,641 
4,648 2,921 - 5 1,555,035 
- - - - 1,573,345 
4,648 2,921 - 5 1,555,036 
- - - 201,300 201,300 
- - - 24,712 24,712 
150,000 200,000 - - 57,206,32424 
177,806 203,409 - - 57,206,32424 
(-)610,000 (-)785,000 115,600 250,204 377,804 
- 2,326 413 4,160 15,408 
433,700 981,000 1,461,000 1,702,000 12,823,513 
483,948 907,545 1,304,922 1,566,899 12,405,613 
825,000 50,000 - - 12,475,000 
851,116 388,262 17,137 (-)91 12,474,873 
1,458,000 180,000 - - 29,310,042 
1,823,689 268,718 13,912 10,910 29,284,949 
600,000 
391,679 79,052 4,080 4,675 
8,715,00025 
8,695,45925 
15-14

GALVESTON TEXAS DISTRICT 
TABLE 15-A COST AND FINANCIAL STATEMENT 
SSeecetion Total Cost To 
in Text Project Funding FY 80 FY 81 FY 82 FY 83 Sep. 30, 198328 
20. Highland Bayou, TX New Work: 
Approp. 460,000 3,300,000 703,877 300,000 12,138,390 
Cost 819,590 3,304,700 637,183 207,696 11,964,773 
21. Port Arthur and New Work: 
Vicinity, TX Hurricane Approp. 985,000 2,230,000 1,600,000 - 59,978,509 
Flood Protection Cost 1,847,566 1,645,839 1,937,833 (-)8,648 59,522,669 
(Regular Funds) 
(Contributed Funds) New Work: 
Contrib. - 450,000 430,000 230,000 16,291,97526 
Cost 467,340 494,712 668,456 130,069 16,168,87726 
22. Taylors Bayou, TX New Work: 
(Regular Funds) Approp. 11,500 215,000 1,175,000 1,900,000 4,743,198 
Cost 93,786 210,011 400,587 2,574,097 4,634,223 
(Contributed Funds) New Work: 
Contrib. - - 400,000 600,000 1,000,000 
Cost - - 55,872 614,494 670,366 
23. Texas City and New Work 
Vicinity, TX Hurricane- Approp. 2,050,000 4,183,000 2,960,000 2,870,000 37,560,400 
Flood Protection Cost 2,094,828 4,073,009 1,703,584 1,419,324 34,671,246 
(Regular Funds) 
(Contributed Funds) New Work: 
Contrib. 400,000 1,250,000 700,000 700,000 12,935,10027 
Cost (-)53,782 1,620,725 729,981 608,280 12,611,33527 
24. Vince and Little Vince New Work: 
Bayous, TX Approp. 712,000 117,000 450,000 1,500,000 8,368,100 
Cost 1,005,641 143,669 274,907 420,002 7,108,178 
1 Excludes $286,380 credit for contributed work. 
2Includes $675,855 for previous projects. In addition, 
$1,806,619 expended from contributed funds, of which 
$123,361 was for previous projects. 
3 In addition, $1,117 expended from contributed funds. 
4 Includes $48,711 for previous projects. 
s Includes $46,101 for previous projects. 
a Includes $1,372,534 for previous projects. Includes 
$456,515 for Sec. 107 project for Port Aransas Breakwaters. 
In addition $768 expended from contributed funds for Port 
Aransas Breakwaters. 
SIncludes $62,452 for previous projects. In addition, 
$434,611 expended from contributed funds. 
a In addition $5,366 expended from contributed funds. 
'Includes $147,098 for previous projects. In addition, 
$758,303 expended from contributed funds. 
1o In addition, $229,311 expended from contributed funds. 
" Includes $8,421,996 for previous projects. In addition, 
$3,648,932 expended from contributed funds. 
12 Includes $86,126 for previous projects. In addition, 
$1,959,849 expended from contributed funds. 
13 Includes $706,709 for previous projects. Includes Sec. 
107 projects for Port Isabel Small Boat Basin ($46,559); Port 
Isabel Side Channel ($8,414); Offatts Bayou ($356,466); and 
Channel to Aransas Pass ($658,573). In addition contributed 
funds expended for Port Isabel Small Boat Basin ($46,559); 
Offatts Bayou ($49,665)" Channel to Aransas Pass ($347,950); 
and Chocolate Bayou ($658,310). 
14 Includes $1,526,564 for previous projects. In addition, 
$22,672 expended from contributed funds. 
1s Includes $4,105,157 for previous projects. In addition, 
$2,591,939 expended from contributed funds, of which 
$1,209,179 was for previous projects. 
16 Includes $1,213,142 for previous projects. In addition, 
$363,360 expended from contributed funds, of which 
$200,000 was for previous projects. 
17In addition $12,259,619 expended from contributed 
funds and $182,800 for contributed lands. 
* Includes $5,180,832 for previous projects. In addition, 
$2,680,942 expended from contributed funds, of which 
$577,507 was for previous projects. 
"9 Includes $2,379,677 for previous projects. In addition, 
$2,052,999 expended from contributed funds. 
20Ion cludes $366,823 for previous projects. In addition, 
$1,023,819 expended from contributed funds, of which 
$99,000 was for mitigation measures. 
21 Includes $195,083 for previous projects. 
SIncludes $1,966,306 for previous projects. In addition, 
$66,2030 0 expended from contributed funds. Includes $543,662 for previous projects. 
24 Includes $4,400,000 of advanced funds repaid to Harris 
County Flood Control District. In addition, $63,661 
contributed funds expended for Brays Bayou and $12,900 
Federal funds and $19,104 contributed funds expended for 
enlargement of Clodine Ditch. 
25 Excludes $1,126,905 estimated value of contributed 
lands and $2,726,446 for relocations. 
26 Excludes $3,402,588 estimated value of contributed 
lands, $6,168,360 for relocations, and $217,000 credit given 
local sponsor for work-in-kind. 
2'
7 Excludes $1,349,069 estimated value of contributed 
lands and $1,070,959 credit given local sponsor for work-inkind. 
a Includes funds provided by the Jobs Act (P:L. 98-8, 
dated March 24, 1983) for projects listed in Table 15-I. 
15-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 15-B AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
2. 
Oct. 27, 1965 
Jul. 3, 1930 
May 24, 1934 
(PA) 
Aug. 30, 1935 
Aug. 26, 1937 
Mar. 2, 1945 
Mar. 2, 1945 
Jul. 24, 1946 
May 17, 1950 
Jul. 14, 1960 
Jun. 25, 1910 
Mar. 4, 1919 
Mar. 3, 1899 
Jun. 13, 1902 
Mar. 3, 1905 
Mar. 2, 1907 
Feb. 27, 1911 
Mar. 4, 19132 
Sep. 23, 1922 
AQUATIC PLANT CONTROL 
Provides for control of progressive eradication of aquatic 
plant growth from the navigable waters and streams in 
the U.S. 
BRAZOS ISLAND HARBOR, TX 
Jetties and jetty channel, inside channels and basins. 
Local cooperation requirement modified to provide 
contribution of funds to cover cost of original dredging of 
all inside channels and basins. 
Deepen jetty channel to 31 feet and inner channels and 
Brownsville and Port Isabel turning basins to 28 feet. 
Enlarge Port Isabel turning basin. 
Deepen entrance channel to 35 feet; deepen to 33 feet 
channel across Laguna Madre; deepen to 32 feet 
channels from Laguna Madre to turning basins at 
Brownsville and Port Isabel; widen turning basins; and 
dredging present shallow-draft channel south of Port 
Isabel from railroad bridge to Laguna Madre and 
connecting channel to Port Isabel turning basin. 
Additional connecting channel between Port Isabel and 
Brownsville channels; and transfer shallow-draft 
channels at Port Isabel to GIWW. 
Deepen to 38 feet in outer bar channels and 36 feet in all 
other authorized channels and basins; extend existing 
turning basins at Brownsville and Port Isabel; and 
construct small-boat basin with a connecting channel 
next to Brownsville ship channel 
Widen Brownsville Channel to 300 feet at a depth of 36 
feet from former Goose Island passing basin to turning 
basin extension, thence at a width of 500 feet and same 
depth to turning basin proper, deepen to 36 feet in area 
in southeast corner of turning basin, maintain two 
existing basins of fishing harbor, and a connecting 
channel, and construct a third basin, with necessary 
connecting channel and extend Brazos Island Harbor 
north jetty seaward 1,000 feet. 27 
CHANNEL TO PORT BOLIVAR, TX 
A channel 30 feet deep and 200 feet wide from deep water 
in Galveston Harbor extending to a turning basin 1,000 
feet square and 30 feet deep. 
Enlargement, extension, and protection of turning 
basin. 
CORPUS CHRISTI SHIP CHANNEL, TX 
Acquisition of old curved portion of north jetty 
previously constructed by private parties. 
Complete north jetty in accordance with builder's plans. 
Complete north jetty in accordance with builder's plans. 
Connect old curve to St. Joseph Island, and construct 
south jetty. 
Dredge roadstead in Harbor Island Basin to 20 feet deep 
and construct 10,000 linear feet of stone dike on St. 
Joseph Island. 
Channel between jetties and Harbor Island Basin to 25 
feet deep, extend jetties seaward, extend dike on St. 
Joseph Island 9,100 feet, and dredge approach channel 
12 feet deep to town of Port Aransas. 
Dredging channel from Aransas Pass to Corpus Christi, 
25 feet deep, 200 feet bottom width. 
15-16 
H. Doc. 251, 89th Cong., 
1st Sess. 
Rivers and Harbors 
Committee Doc. 16, 
71st Cong., 2nd Sess. 
Rivers and Harbors 
Committee Doc. 10, 
71st Cong., 1st Sess. 
Rivers and Harbors 
Committee Doc. 32 
75th Cong., 1st Sess. 
H. Dc. 335, 76th Cong., 
1st Sess. 
H. Doc. 347, 77th Cong., 
1st Sess. 
H. Doc. 627, 79th Cong., 
2nd Sess. 
H. Doc. 192, 81st Cong., 
1st Sess. 
H. Doc. 428, 86th Cong., 
2nd Sess.' 
H. Doc. 328, 61st Cong., 
2nd Sess. 
H. Doc. 1122, 65th Cong., 
2nd Sess.' 
Specified in Act. 
Specified in Acts. 
Specified in Act. 
Rivers and Harbors 
Committee Doc. 5, 
59th Cong., 2nd Seas. 
H. Doc. 1094, 61st Cong., 
3rd Sess. 
H. Doc. 1125, 62nd 
Cong., 3rd Seas. 
H. Doc. 321, 67th Cong., 
2nd Sess. 
3. 
4.

GALVESTON TEXAS DISTRICT 
TABLE 15-B AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Jul. 3, 1930w 
Jul. 3, 1930 
Aug. 30, 19354 
Aug. 30, 1935 
Aug. 30, 1935 
Aug. 30, 1935 
Jun. 20, 1938 
Mar. 2, 1945 
Jun. 30, 1948 
Sep. 3, 1954 
Sep. 3, 1954a 
Sep. 3, 1954 
Jul. 3, 1958 
Jul. 3, 1958 
Jul. 3, 1958 
Deepen entrance channel from gulf to Harbor Island and 
provide an inner basin at Harbor Island of reduced area 
but greater depth. 
Channel from Aransas Pass to Corpus Christi Channel 
with depth 30 feet. 
Enlarge all channels from gulf to western end of basin 
dredged by Humble Oil and Refining Co., at its docks on 
Harbor Island.g 
Maintain channel and maneuvering basin between 
breakwater and western shoreline of Corpus Christi Bay. 
Maintain 30-foot depth of approach channel, turning 
basin at Corpus Christi, Industrial Canal and turning 
basin at Avery Point. 
Maintain and deepen to 32 feet channel from deep water 
at Port Aransas to and including turning basin at 
Corpus Christi. 
Extend main turning basin at Corpus Christi westward 
2,500 feet at its present width and depth, deepen existing 
Industrial Canal and turning basin to 32 feet and extend 
this canal at a depth of 32 feet and general width of 150 
feet, westward along Nueces Bay shore to a turning 
basin 32 feet by 900 feet, and 1,000 feet long near Tule 
Lake. 
Provide depth of 34 feet in all project channels and 
basins from Port Aransas to and including Tule Lake 
turning basin, for a width of 250 feet from Port Aransas 
to breakwater at Corpus Christi, for a width of 200 feet in 
Industrial Canal and in channel between Avery Point 
and Tule Lake turning basins, and widen Avery Point 
turning basin to 1,000 feet. 
Deepen entrance channel to 38 feet from gulf to outer end 
of jetty; 38 feet decreasing to 36 feet thence to station 90 
north jetty; and 36 feet in all other deep water channels 
and basins except 2,000-foot undredged part of inner 
basin at Harbor Island, and a width of 400 feet in 
channel from Port Aransas to Maneuvering basin at 
Corpus Christi. 
An anchorage basin 12 feet deep, from 300 to 400 feet 
wide, and 900 feet long in Turtle Cove at Port Aransas, 
Texas. 
Branch channel 32 feet by 150 feet, extending northerly 
from main channel in vicinity of Port Ingleside, along 
north shore of Corpus Christi Bay to Reynolds Metals 
Co. plant and turning basin 32 feet deep and 800 feet 
square near plant in general vicinity of LaQuinta, Texas. 
An entrance channel 36 by 400 feet on a tangent 
alignment from 400-foot channel in Corpus Christi Bay, 
near Corpus Christi breakwater, to flared approach 
channel to Corpus Christi turning basin. 
Deepen and widen LaQuinta Channel to 36 by 200 feet; 
enlarge LaQuinta turning basin to 36 by 800 by 1,000 
feet; a flared entrance to channel; and widening at 
curves. 
Deepen entrance channel to 42 feet from gulf to outer end 
of jetty; 40 feet in all other deep-water channels and 
basins except undredged northward extension to inner 
basin at Harbor Island and branch channel to LaQuinta; 
and widen Industrial Canal to 400 feet with flared 
entrances to Corpus Christi and Avery Point turning 
basins. 
Channel 40 by 200 feet extending 2.2 miles from Tule 
Lake turning basin to a turning basin 40 feet deep, 700 to 
900 feet wide, 1,000 feet long at Viola, Texas. 
H. Doc. 214, 70th Cong., 
1st Sess. 
Rivers and Harbors 
Committee Doc. 9, 
71st Cong., 1st Sess. 
Rivers and Harbors 
Committee Docs. 35, 
72nd Cong., 1st Sess., 
and 40, 73rd Cong., 
2nd Sess. 
H. Doc. 130, 72nd Cong., 
1st Sess. 
Rivers and Harbors 
Committee Doc. 13, 
74th Cong., 1st Sess. 
Rivers and Harbors 
Committee Doc. 63, 
74th Cong., 1st Sess. 
H. Doc. 574, 75th Cong., 
3rd Sess. 
H. Doc. 544, 78th Cong., 
2nd Sess. 
H. Doc. 560, 80th Cong., 
2nd Sess. 
H. Doc. 654, 81st Cong., 
1st Sess. 
H. Doc. 89, 83rd Cong., 
1st Sess. 
H. Doc. 487, 83rd Cong., 
2nd Sess. 
S. Doc. 33, 85th Cong., 
1st Sess. 
H. Doc. 361, 85th Cong., 
2nd Sess. 
H. Doc. 361, 85th Cong., 
2nd Sess. 
15-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 15-B AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized 
Jul. 3, 1958 
Jul. 14, 1960 
(As amended by 
Dec. 31, 1970) 
Aug. 13, 1968 
Oct. 22, 1976 
Mar. 3, 1899 
Jul. 14, 1960 
(As amended by 
Oct. 25, 1965) 
Mar. 3, 1899 
Mar. 2, 1907 
Feb. 27, 1911 
Mar. 4, 1913 
Aug. 8, 1917 
Mar. 3, 19256 
Jul. 3, 1930 
Aug. 30, 1935' 
Aug. 30, 1935 
May 17, 1950 
Jul. 3, 1958 
Oct. 5, 1961 
Depth of 12 feet and a width of 100 feet in locally 
dredged Jewel Fulton Canal from LaQuinta Channel to 
a turning basin 12 by 200 by 400 feet, and assumption of 
maintenance by United States. 
Construction of a breakwater at entrance to harbor area 
at Port Aransas, and realignment of existing 12-foot by 
100-foot project channel. 
Provides for a project depth of 45 feet in the existing 
deep-draft channels and basins, for construction of a 
new deep-draft turning point, for construction of a deepdraft 
mooring area and mooring facilities and for 
widening of the channels and basins at certain locations. 
The Act also deauthorized the undredged northward 
extension of Inner Basin at Harbor Island and the 
undredged west turnout (Wye connection) between the 
LaQuinta Channel and the main channel of the waterway. 
Modified local cooperation requirements for 1968 Act. 
Shifted responsibility for cost of disposal areas and 
confinement works from sponsor to joint 75 percent 
Federal and 25 percent non-Federal responsibility. 
DOUBLE BAYOU, TX 
A channel 6-foot deep and 100-feet wide through the bar 
at mouth of Double Bayou. 
7-foot by 125-foot channel from the 7-foot depth in Trinity 
Bay to the intersection of Double Bayou Channel with 
the channel to Liberty; and thence a 7- by 100-foot 
channel upstream for 2.0 miles. 
FREEPORT HARBOR, TX 
Dredging and other work necessary in judgment of 
Secretary of War for improving harbor; for taking over 
jetties and privately built works at mouth of river. 
Examination authorized. Work later confined to maintenance 
of jetties. 
Repairs to jetties and dredging. 
Construct seagoing hopper dredge. 
Purchase of one 15-inch pipeline dredge and equipment, 
its operation of 3 years, operation of seagoing dredge 
one-half time for 3 years, and repairs to jetties. 
Diversion dam, diversion channel, and necessary auxiliary 
works. 
Maintenance of diversion channel at expense of local 
interest. 
Deepening channels and basins. 
Maintenance of present project dimensions of channels 
and basins at Federal expense. 
Deepen outer bar channel to 38 feet from gulf to a 
point within jetties, thence 36 feet in authorized channels 
to and including upper turning basin. 
Relocate outer bar channel on straight alignment with 
jetty channel and maintain Brazos Harbor entrance 
channel and turning basin (constructed by local 
interests). 
Modification of HD 1469. Revoking certain provisions of 
local cooperation. 
Documents 
H. Doc. 361, 85th Cong., 
2nd Sess. 
Sec. 107, PL 86-645 
S. Doc. 99, 90th Cong., 
2nd Sess. 1 
Sec. 124, PL 94-587 
H. Doc. 387, 55th Cong., 
2nd Sess. 
Sec. 107, PL 86-645 
Specified in Act. 
H. Doc. 1087, 60th Cong., 
2nd Sess. 
Specified in Act. 
Specified in Act. 
Specified in Act. 
Rivers and Harbors 
Committee Doc. 10, 
68th Cong., 2nd Sess. 
Rivers and Harbors 
Committee Doc. 18, 
70th Cong., 1st Sess. 
Rivers and Harbors 
Committee Doc. 15, 
72nd Cong., 1st Sess. 
Rivers and Harbors 
Committee Does. 15, 
72nd Cong., 1st Sess., 
and 29, 73rd Cong., 
2nd Sess. 
H. Doc. 195, 81st Cong., 
1st Sess. 
H. Doc. 433, 84th Cong., 
2nd Sess. 
PL 394, 87th Cong. 
15-18

GALVESTON TEXAS DISTRICT 
TABLE 15-B AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Dec. 31, 1970 
7. 
Relocation of entrance channel and deepen to 47 feet; 
enlargement to a depth of 45 feet and relocation of jetty 
channel and inside main channel; deepening to 45 feet of 
channel to Brazosport; enlargement of the widened area 
of Quintana Point to provide a depth of 45 feet with a 
750-foot diameter turning area; Brazosport turning basin 
to 45 feet deep with a 1,000 foot turning area; a new 
turning basin with a 1,200 foot diameter turning area 
and 45 feet deep; deepening Brazosport channel to 36 by 
750 feet diameter; flared approaches from Brazos Harbor 
Channel; relocation of north jetty and rehabilitation of 
south jetty. 
GALVESTON HARBOR AND CHANNEL, TX 
Construct 2 rubblestone jetties at entrance to Galveston 
Harbor. 
A channel 1,200 by 30 feet from Bolivar Roads (outer 
end of old inner bar near Fort Point) at 51st Street.8 
Purchase or construct hydraulic pipeline dredge. 
Extension of jetties to present project length and 
construction and operation of a dredge. 
Extension of Galveston Channel from 51st to 57th Sts., 
with depth of 30 feet and width of 700 feet. 
Conditional extension of Galveston Channel between 51st 
and 57th Sts., 30 feet deep and 1,000 feet wide. 
Extend seawall at Galveston from angle at 6th St. and 
Broadway to vicinity of Fort San Jacinto. 
Deepen harbor channel to 35 feet and widen to 800 feet. 
Further extension of seawall at Galveston to a junction 
with south jetty; and repairing seawall in front of Fort 
Crockett reservation. 
Deepen Galveston Channel to 32 feet; and maintain 
Galveston Harbor channels to dimensions of 800 feet 
wide, 35 feet deep on outer bar and 34 feet deep in inner 
bar.10 
Maintain State Highway Ferry Landing Channels to 
dimensions of 12 by 100 feet. 
Construct 13 groins along gulf shore from 12th to 61st Sts. 
in city of Galveston at a limited cost of $234,000 (10 
groins constructed). 
Deepen Galveston Channel to 34 feet (Bolivar Roads to 
43rd St.). 
Deepen Galveston entrance channel to 36 feet. 
Completion of project for construction of 13 groins. 
Deepen Glaveston Harbor to 38 feet from gulf to a point 
2 miles west of seaward end of north jetty; thence 36 feet 
to Bolivar Roads; revoking authority for maintenance of 
ferry channels; and Galveston channel to 36 feet deep 
from Bolivar Roads to 43rd Street. 
Construct extension of Galveston Seawall from 61st 
Street, southwesterly 16,300 feet along gulf shore. 
Deepen Galveston Harbor to 42 feet from gulf to point 2 
miles west of seaward end of north jetty and 40 feet 
thence to Bolivar Roads. 
Deepen Galveston Channel to 40 feet from Bolivar Roads 
to 43rd Street. 
H. Doc. 289, 93rd Cong., 
2nd Sess.'1 
H. Doc. 85, 49th Cong., 
1st Sess., and Annual 
Report, 1886, p. 1311. 
H. Doc. 264, 56th Cong., 
2nd Sess. 
Specified in Act. 
H. Doc. 340, 59th Cong., 
2nd Sess., and 
Rivers and Harbors 
Committee Doc. 11, 
59th Cong., 2nd Sess. 
H. Doc. 768, 59th Cong., 
2nd Sess. 
H. Doc. 328, 61st Cong., 
2nd Sess. 
H. Doc. 1390, 62nd 
Cong., 3rd Sess. 
H. Doc. 758, 65th Cong., 
2nd Sess. 
H. Doc. 693, 66th Cong., 
2nd Sess. 
H. Doc. 307, 69th Cong., 
1st Sess. 
River and Harbors 
Committee Doc. 31, 
72nd Cong., 1st Sess. 
H. Doc. 400, 73rd Cong., 
2nd Sess. 
Rivers and Harbors 
Committee Doc. 61, 
74th Cong., 1st Sess. 
Rivers and Harbors 
Committee Doc. 57, 
74th Cong., 1st Sess. 
PL 463, 75th Cong. 
H. Doc. 561, 80th Cong., 
2nd Sess. 
H. Doc. 173, 81st Cong., 
1st Sess. 
H. Doc. 350, 85th Cong., 
2nd Sess. 
H. Doc. 121, 92nd Cong., 
1st Sess. 
(Sec. 201, PL 89-298) 
15-19 
Aug. 5, 1886 
Jun. 13, 1902 
Mar. 3, 1905 
Mar. 2, 1907 
Mar. 2, 1907 
Jun. 25, 19109 
Jul. 27, 1916 
Jul. 18, 1918 
Sep. 22, 1922 
Jan. 21, 1927 
Aug. 30, 193511 
Aug. 30, 1935 
Aug. 30, 1935 
Aug. 30, 1935 
Apr. 4, 1938 
Jun. 30, 1948 
May 17, 1950 
Jul. 3, 1958 
Jun. 23, 1971 
(House Res.) 
(Nov. 18, 1971 
(Sen. Res.)

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 15-B AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Mar. 2, 1907 
Mar. 3, 1925 
Jan. 21, 1927 
Aug. 26, 1937 
Jun. 20, 193813 
Jun. 20, 1938 
Jun. 20, 1938 
Jun. 20, 1938 
Jun. 20, 1938 
Mar. 23, 1939 
Jul. 23, 1942 
Mar. 2, 1945 
Mar. 2, 1945' 
Mar. 2, 1945 
Mar. 2, 1945 
Mar. 2, 194514 
Jul. 24, 1946 
Jul. 24, 1946 
May 17, 1950 
May 17, 1950 
May 17, 1950 
Jul. 12, 1952 
Sep. 3, 195415 
GULF INTRACOASTAL WATERWAY BETWEEN 
APALACHEE BAY, FL AND MEXICAN BORDER 12 
Channel 4 by 100 feet from West Galveston Bay across 
Chocolate Bay to 4 feet of water in Chocolate Bay. 
Channel 9 by 100 feet, Sabine River to Galveston Bay, 
and a 20-inch pipeline dredge. Such passing places, 
widening at bends, locks or guard locks and railway 
bridges over artificial cuts as are necessary. 
Channel 9 by 100 feet, Galveston Bay to Corpus Christi. 
Maintenance of a flood-discharge channel in Colorado 
River. 
Channel 9 by 100 feet in San Bernard River, Texas. 
Channel in Colorado River, 9 by 100 feet, with basin. 
Channel 9 by 100 feet from Palacios through Trepalacios 
and Matagorda Bays. 
Channel 9 by 200 feet from main channel to harbor at 
Rockport and improve harbor to 9-foot depth. 
Channel 6 by 100 feet from main channel to Aransas 
Pass, Texas. 
Enlarge waterway to depth of 12 feet and a width of 125 
feet from Sabine River to Corpus Christi. 
Enlarge waterway from Corpus Christi to vicinity of 
Mexican border to provide a depth of 12 feet and width of 
125 feet throughout. 
Channel 6 by 60 feet from GIWW to a point in Chocolate 
Bayou near Liverpool. 
Channel 6 feet deep and 60 feet wide from main channel 
near Port O'Connor, Texas, into Barroom Bay. 
Enlarge channel from main channel to Aransas Pass, 
Texas, providing a depth of 9 feet and width of 100 feet. 
Channel 12 by 125 feet from main channel to Red Fish 
Landing, Texas, with basin. 
Channel 12 feet deep and 125 feet wide from main channel 
to vicinity of Harlingen, Texas, via Arroyo Colorado 
with basin. 
Fill a portion of shallow-draft channel adjacent to Port 
Isabel Turning Basin, construct a channel to connect 
shallow-draft channel with main channel near shoreline 
of Laguna Madre, and enlarge shallow-draft channel 
west of this connection, all to 12-foot depth and 
bottom width of 125 feet. 
Reroute main channel to north shore of Red Fish Bay 
between Aransas Bay and Corpus Christi Bay; deepen 
tributary channel from Port Aransas to Aransas Pass, 
Texas, 12 feet and extended basin at same depth. 
Deauthorized 6 by 60 foot channel in Chocolate Bayou 
and reauthorized the 4 by 100-foot channel. 
Alternate channel across South Galveston Bay between 
Port Bolivar and Galveston causeway. 
"Red Fish Landing" changed to "Port Mansfield, 
Texas." 
Incorporate as part of Intracoastal Waterway a channel 9 
by 100 feet from main channel via Seadrift to point on 
Guadalupe River 3 miles above Victoria, Texas, 
authorized by River and Harbor Act of 1945. 
Small craft harbor 9 by 200 by 1,000 feet at Seadrift with 
an entrance channel 9 by 100 feet. 
H. Doc. 445, 56th Cong., 
1st Sess. 
H. Doc. 238, 68th Cong., 
1st Sess. 
H. Doc. 238, 68th Cong., 
1st Sess. 
S. Committee print, 
75th Cong., 1st Sess. 
H. Doc. 640, 75th Cong., 
3rd Sess. 
H. Doc. 642, 75th Cong., 
3rd Sess. 
H. Doc. 564, 75th Cong., 
3rd Sess. 
H. Doc. 641, 75th Cong., 
3rd Sess. 
H. Doc. 643, 75th Cong., 
3rd Sess. 
H. Doc. 230, 76th Cong., 
1st Sess. 
PL 675, 77th Cong. 
H. Doc. 337, 76th Cong., 
1st Sess. 
H. Doc. 428, 76th Cong., 
1st Sess. 
H. Doc. 383, 77th Cong., 
1st Sess. 
S. Doc. 248, 78th Cong., 
2nd Sess. 
H. Doc. 402, 77th Cong., 
1st Sess. (See Public 
Law 14, 79th Cong.) 
H. Doc. 627, 79th Cong., 
2nd Sess. 
H. Doc. 700, 79th Cong., 
2nd Sess. 
H. Doc. 768, 80th Cong., 
2nd Sess. 
H. Doc. 196, 81st Cong., 
1st Sess. 
PL516, 81st Cong. 
PL 527, 82nd Cong., 
2nd Sess. 
H. Doc. 478, 81st Cong., 
2nd Sess. 
15-20

GALVESTON TEXAS DISTRICT 
TABLE 15-B AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Sep. 3, 1954 
Sep. 9, 1959 
Jul. 14, 1960 
Jul. 14, 1960 
(As amended 
Dec. 31, 1970) 
Jul. 14, 1960 
(As amended 
Dec. 31, 1970) 
Jul. 14, 1960 
(As amended 
Dec. 31, 1970) 
Oct. 23, 196216 
Oct. 23, 1962 
Oct. 23, 1962 
Oct. 27, 1965"17 
Aug. 13, 1968 
Widen tributary channel between Port Aransas and 
Aransas Pass, Texas, to 125 feet; straighten and widen 
to 125 feet connecting channel to Conn Brown Harbor, 
and maintain Conn Brown Harbor at Federal expense, 
all to 12 feet deep. 
Improve channels and basins comprising channel to Port 
Mansfield constructed in part by Federal Government 
and in part by local interest; constructing turnout curves 
at Gulf Intracoastal Waterway intersection and bend 
easing at entrance to turning basin; construct parallel 
jetties at gulf entrance; maintenance of locally dredged 
jetty channel 16 by 250 feet; and maintenance of small 
craft basin. 
Entrance channel 7 feet deep by 75 feet wide from main 
channel to Gulf of Mexico to inside shoreline at Port 
Isabel, Texas, an inner channel 6 feet deep by 50 feet 
wide from entrance channel to East Harbor Basin, and 
an irregular-shaped harbor basin 6 feet deep having a 
surface area of about 7 acres. 
Deepen the existing 6-foot channel at Port Isabel to 12 feet 
and removing the submerged bars at each end of the 
island to a depth of -12 feet MLT. 
Deepening the existing channel to 12 by 125 feet, and 
extend southeasterly from the Gulf Intracoastal Waterway 
main channel in West Galveston Bay, into Offatts 
Bayou, a distance of 2.2 miles, and a west turnout 12 
by 125 feet between the proposed Offatts Bayou Channel 
and the Gulf Intracoastal Waterway. 
Deepening Aransas Pass tributary channel to 14 feet from 
mile 0 at Harbor Island to mile 6.1 at the city of Aransas 
Pass; widening to 175 feet between miles 3.5 and 4.6; 
and deepening Conn Brown Harbor, turning basin and 
connecting channel between Conn Brown Harbor and 
turning basin. 
Improve main channel 16 feet deep and 150 feet wide 
from Sabine River to Houston Ship Channel; with two 
relocations; relocate main channel in Matagorda Bay 
and Corpus Christi Bay; and maintaining existing 
Lydia Ann Channel. 
Deepen and widen channel to Palacios; construct two 
protective breakwaters; maintain and deepen existing 
basins; and deepen, enlarge and maintain existing 
approach channel to basin No. 2. 
Eliminates requirement of local interest to construct bridge 
at mile 29.2 turning basin at Victoria, and maintain 
turning basins at Victoria and Seadrift; provide: Federal 
construction of vertical-lift railroad bridge at Missouri- 
Pacific Railroad mainline crossing, mile 29.2; construction 
and future maintenance of basin near Victoria, 
Texas, and maintenance of basin constructed by local 
interests at Seadrift, Texas. 
Modify existing Federal navigation project to provide a 
channel extending from Gulf Intracoastal Waterway 
through Chocolate Bay and Chocolate Bayou to project 
channel mile 8.2, thence to a turning basin near channel 
mile 13.2 and for salt water barrier in Chocolate Bayou 
about 3.7 miles upstream from basin (channel mile 16.9). 
Entrance channel 15 feet deep and 200 feet wide at the 
mouth of Colorado River Channel protected by an east 
jetty 3,500 feet long extending to 12-foot depth and 
a west jetty 2,900 feet long extending to 5-foot contour; 
make channel 12 feet by 100 feet from gulf shore to 
Matagorda, including recreation facility, a turning basin 
12 feet by 300 feet wide and 1,450 feet long, and a new 
diversion channel 250 feet wide and varying in depth 
from 20 to 23 feet including a closure dam across the 
present river channel. 
H. Doc. 376, 83rd Cong., 
2nd Sess. 
S. Doc. 11, 86th Cong., 
1st Sess. 
Sec. 107, PL 645, 
86th Cong. 
Sec. 107, PL 86-645 
Sec. 107, PL 86-645 
Sec. 107, PL 86-645 
H. Doc. 556, 87th Cong., 
2nd Sess. 
H. Doc. 504, 87th Cong., 
2nd Sess. 
H. Doc. 288, 87th Cong., 
2nd Sess. 
H. Doc. 217, 89th Cong., 
1st Sess. 
S. Doc. 102, 90th Cong., 
2nd Sess. 
15-21

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 15-B AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
9. Mar. 5, 1905 
Mar. 2, 1919 
Mar. 3, 1925 
Jul. 3, 1930 
Aug. 30, 193511 
Aug. 30, 1935 
Mar. 2, 1945 
Mar. 2, 1945 
Mar. 2, 1945 
Jun. 30, 1948 
Jul. 3, 195820 
Jul. 14, 1960 
Oct. 27, 1965 
Jun. 25, 1910 
Aug. 30, 1935 
Aug. 26, 1937 
Mar. 2, 1945 
Mar. 2, 1945 
Jul. 3, 1958 
Jul. 3, 1958 
Jul 25, 1912 
HOUSTON SHIP CHANNEL, TX 
Easing or cutting off sharp bends and construction of a 
pile dike.18 
A channel 30 feet deep, widen bend at Manchester and 
enlarge turning basin. 
A light-draft extension of channel to mouth of White Oak 
Bayou.1" 
Widen channel through Morgan Point and to a point 
4,000 feet above Baytown and widen certain bends. 
Deepen to 32 feet in main channel and turning basin, and 
a 400-foot width through Galveston Bay. 
Deepen to 34 feet in main channel and widen from Morgan 
Point to turning basin. 
Branch channel 10 by 60 feet behind Brady Island. 
Widen channel from Morgan Point to lower end of 
Fidelity Island with turning points at mouth of Hunting 
Bayou and lower end of Brady Island. 
Widen channel from lower end of Fidelity Island to 
Houston turning basin and dredge off-channel silting 
basins. 
Deepen to 36 feet from Bolivar Roads to and including 
main turning basin at Houston, Texas, including turning 
points at Hunting Bayou and Brady Island. 
Deepen to 40 feet from Bolivar Roads to Brady Island, 
construct Clinton Island turning basin, a channel 8 by 
125 feet at Five Mile Cut, and improve shallow-draft 
channel at Turkey Bend. 
Barbour Terminal at Morgan Point. 
Restoring existing locally dredged channel from mile 0 to 
0.34 to 36 feet deep and dredging a 15-12 ft. channel from 
mile 0.34 to 2.81, in Greens Bayou.21 
MATAGORDA SHIP CHANNEL, TX 
Channel to Port Lavaca, Texas 7 feet deep and 89 feet 
bottom width. 
Extend 7-foot channel to shoreline of Lavaca Bay at 
mouth of Lynns Bayou. 
Deepen and widen channel to present project dimensions. 
Extend channel 6 by 100 feet from Port Lavaca via 
Lavaca Bay, Lavaca and Navidad Rivers to Red Bluff, a 
distance of 20 miles. 
A harbor of refuge 9 feet deep near Port Lavaca and an 
approach channel 100 feet wide and equal depth. 
Deepen to 12 feet and widen to 125 feet Port Lavaca 
Channel and approach channel to harbor of refuge; 
deepen to 12 feet Port Lavaca turning basin and basins 
at harbor of refuge. 
An entrance channel 38 by 300 feet, a channel 36 by 200 
feet, 22 miles long across Matagorda and Lavaca Bays 
to Point Comfort, Texas, a turning basin 36 feet deep and 
1,000 feet square at Point Comfort, and dual jetties at 
entrance from gulf. 
SABINE-NECHES WATERWAY, TX 
Existing project dimensions of jetties, a 26-foot channel 
through Sabine Pass, Port Arthur Canal and Port 
Arthur turning basin; and a 26-foot turning basin at Port 
Arthur. A depth of 25-feet in Sabine-Neches Canal, 
15-22 
Rivers and Harbors 
Committee Doc. 35, 
61st Cong., 2nd Sess. 
H. Doc. 1632, 65th Cong., 
3rd Sess. 
H. Doc. 93, 67th Cong., 
1st Sess. 
H. Doc. 13, 71st Cong., 
1st Sess. 
Rivers and Harbors 
Committee Doc. 28, 
72nd Cong., 1st Sess. 
Rivers and Harbors 
Committee Doc. 58, 
74th Cong., 1st Sess. 
H. Doc. 226, 76th Cong., 
1st Sess. 
H. Doc. 256, 76th Cong., 
1st Sess. 
H. Doc. 737, 79th Cong., 
2nd Sess. 
H. Doc. 561, 80th Cong., 
2nd Sess. 
H. Doc. 350, 85th Cong., 
2nd Sess.'1 
Sec. 107, PL 86-645 
R. Doc. 257, 89th Cong., 
1st Sess. 
H. Doc. 1082, 60th Cong., 
2nd Sess. 
Rivers and Harbors 
Committee Doc. 28, 
74th Cong., 1st Sess. 
Rivers and Harbors 
Committee Doc. 37, 
75th Cong., 1st Sess. 
H. Doc. 314, 76th Cong., 
1st Sess. 
H. Doc. 731, 79th Cong., 
2nd Sess. 
H. Doc. 131, 84th Cong., 
1st Sess. 
H. Doc. 388, 84th Cong., 
2nd Sess. 1 
H. Doc. 773, 61st Cong., 
2nd Sess. 
10. 
11.

GALVESTON TEXAS DISTRICT 
TABLE 15-B AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Sep. 22, 1922 
Sep. 22, 1922 
Mar. 3, 1925 
Jan. 21, 1927 
Aug. 30, 193511 
Aug. 30, 193511 
Aug. 30, 1935 
Aug. 26, 1937 
Aug. 26, 1937 
Jun. 20, 193822 
Oct. 17, 1940 
Mar. 2, 1945 
Mar. 2, 1945 
Mar. 2, 1945 
Jul. 24, 194623 
Neches River to Beaumont and Sabine River to Orange, 
including cutoffs and widening channels. 
Deepen channels to 30 feet from gulf to Beaumont, with 
increased widths and an anchorage basin in Sabine 
Pass. 
Deepen Port Arthur east and west turning basins and 
approach channel to 30 feet. Take over and deepen 
to 30 feet channel connecting west turning basin with 
Taylors Bayou turning basin. For a 30-foot depth in 
channel from mouth of Neches River to cutoff in Sabine 
River near Orange. 
Removal of guard lock in Sabine-Neches Canal. 
Widen Sabine Pass and jetty channel, Port Arthur 
Canal, and Sabine-Neches Canal. For dredging 2 
passing places in Sabine-Neches Canal, easing of 
bends, removal and reconstructing Port Arthur field 
office, extending Beaumont turning basin upstream 
200 feet above new city wharves, and an anchorage 
basin in Sabine Pass. 
A depth of 32 feet in channels from gulf to Beaumont 
turning basin, including all turning basins at Port 
Arthur. 
Deepen channels to 34 feet with increased widths from 
gulf to Beaumont turning basin. 
Construct suitable permanent protective works along 
Sabine Lake. Maintain Taylors Bayou turning basin. 
Maintain channel from Sabine River to Orange 
Municipal wharf. 
Dredging 500 feet from eastern end of Harbor Island 
and abandonment of channel south and west of Harbor 
Island. 
Increased widths of channels from gulf to Beaumont 
turning basin and channel connecting Port Arthur west 
turning basin and Taylors Bayou turning basin, deepen 
Beaumont turning basin and Beaumont turning extension 
to 34 feet; and dredge a new cutoff from Smith's 
Bluff cutoff to McFadden Bend. 
Abandon Orange turning basin; dredge a channel 25 by 
150 feet, suitably widened on bends to highway bridge, 
and dredge a cutoff channel opposite Orange. 
Extend Beaumont turning basin upstream 300 feet. 
Widen Port Arthur west turning basin to 600 feet. 
Dredge a channel from Beaumont turning basin to 
vicinity of Pennsylvania Shipyard. 
Deepen Sabine Pass outer bar channel to 37 feet, Sabine 
Pass jetty channel to 36 feet at inner end, deepen to 
36 feet Sabine Pass Channel, Port Arthur Canal, Port 
Arthur east and west turning basins, Taylors Bayou 
turning basin and channel from Port Arthur west 
turning basin to Taylors Bayou turning basin, deepen 
to 36 feet and widen to 400 feet Sabine-Neches Canal 
from Port Arthur Canal to mouth of Neches River 
except through Port Arthur Bridge; deepen Neches 
River channel from mouth to Beaumont turning basin 
to 36 feet widening to 350 feet from Smith's Bluff 
to Beaumont turning basin; deepen junction area on 
Neches River at Beaumont turning basin to 36 feet; 
and widen Sabine-Neches Canal between Neches and 
Sabine Rivers to 150 feet. 
H. Doc. 975, 66th Cong., 
3rd Sess. 
S. Doc. 152, 67th Cong., 
2nd Sess. 
H. Doc. 234, 68th Cong., 
1st Sess. 
H. Doc. 287, 69th Cong., 
1st Sess. 
Rivers and Harbors 
Committee Doc. 27, 
72nd Cong., 1st Sess. 
Rivers and Harbors 
Committee Doc. 12, 
74th Cong., 1st Sess. 
Specified in Act. 
Rivers and Harbors 
Committee Doc. 3, 
75th Cong., 1st Sess. 
Rivers and Harbors 
Committee Doc. 20, 
75th Cong., 1st Sess. 
H. Doc. 581, 75th Cong., 
3rd Sess. 
S. Doc. 14, 77th Cong., 
1st Sess. 
H. Doc. 685, 76th Cong., 
3rd Sess. 
S. Doc. 60, 77th Cong., 
1st Sess. 
S. Doc. 158, 77th Cong., 
2nd Sess. 
H. Doc. 571, 79th Cong., 
2nd Sess. 
15-23

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 15-B AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Jul. 24, 194624 
Jul. 24, 1946 
May 17, 1950 
Sep. 3, 195425 
Oct. 23, 196226 
Mar. 4, 1913 
Jul. 3, 1930 
Aug. 30, 193511 
Aug. 30, 1935 
Aug. 30, 1935 
Aug. 26, 1937 
Jun. 30, 1948 
Jul. 14, 1960 
Oct. 12, 1972 
(Sen. Res.) 
Oct. 12, 1972 
(House Res.) 
Improve Cow Bayou, Texas, by construction of a channel 
100 feet wide and 13 feet deep extending from navigation 
Channel in Sabine River to a point 0.5 mile above county 
bridge at Orangefield, Texas, with a turning basin. 
Improve Adams Bayou, Texas, to provide a channel 12 
feet deep and 100 feet wide extending from 12-foot depth 
in Sabine River to first county highway bridge across 
bayou. 
Deepen to 36 feet and widen to 400 feet the Sabine- 
Neches Canal near Port Arthur bridge; reconstruct Port 
Arthur Bridge and relocate Port Arthur field office. 
Rectification of certain reaches of existing Sabine Pass 
Channel, Sabine-Neches Canal, and Neches River and 
Sabine River Channel; widen to 350 feet entrance 
channel to Port Arthur turning basins; widen curve at 
junction of Port Arthur and Sabine-Neches Canals; 
relocate and enlarge Sabine Pass anchorage basin to 34 
by 1,500 by 3,000 feet; widen to 200 feet Sabine-Neches 
Canal from mouth of Neches River to mouth of Sabine 
River and Sabine River Channel to upper end of existing 
project at Orange, except for channel around Harbor 
Island at Orange; deepen to 30 feet Sabine River 
Channel from cutoff near Orange municipal slip to upper 
end of project, except around Harbor Island; and enlarge 
area at entrance to Orange municipal slip to provide a 
maneuvering basin. 
Improve outer bar channel to 42 and 40 feet for all inland 
channels to Port Arthur and Beaumont; width of 500 feet 
in Port Arthur Canal and 400 feet in Neches River 
Channel to Beaumont with three turning points in 
Neches River; a channel, 12 by 125 feet, extending in 
Sabine River to Echo; and replace an obstructive bridge 
at Port Arthur, Texas. Deauthorization of uncompleted 
portion of channel between Port Arthur west turning 
basin and Taylors Bayou turning basin and enlargement 
of entrance channel to Port Arthur turning basins. 
TEXAS CITY CHANNEL, TX 
A channel 300 by 30 feet and construct a pile dike 28,200 
feet long north to channel. 
A harbor 800 by 30 feet at Texas City, and construct a 
rubblemound dike. 
Extension of rubblemound dike to shoreline. 
Deepen channel and harbor to 32 feet. 
Deepen channel and harbor to 34 feet. 
Extend harbor 1,000 feet southward, 800 by 34 feet. 
Deepen channel and harbor to 36 feet, widen channel to 
400 feet and harbor to 1,000 feet and changing name of 
project to "TEXAS CITY CHANNEL, TEXAS.' 
Deepen channel and turning basin to 40 feet and 
construct 16-foot Industrial Barge Canal. 
Widen the existing main turning basin to 1,200 feet 
including relocation of the basin 85 feet to the east; 
providing a 40-foot deep channel in the Industrial Canal 
at widths of 300-400 feet, with a turning basin at the 
head of the canal 40 feet deep, 1,150 feet long, and 1,000 
feet wide, and easing of the bend at the entrance to the 
canal, and deauthorization of shallow-draft Industrial 
Barge Canal not incorporated in the plan of 
improvement above. 
H. Doc. 702, 79th Cong., 
2nd Sess. 
H. Doc. 626, 79th Cong., 
2nd Sess. 
H. Doc. 174, 81st Cong., 
1st Sess. 
S. Doc. 80, 83rd Cong., 
2nd Sess. 
H. Doc. 553, 87th Cong., 
2nd Sess. 1 
H. Doc. 1390, 62nd Cong., 
3rd Sess. 
H. Doc. 107, 71st Cong., 
1st Sess. 
Rivers and Harbors 
Committee Doc. 4, 
73rd Cong., 1st Sess. 
Rivers and Harbors 
Committee Doc. 46, 
73rd Cong., 2nd Sess. 
Rivers and Harbors 
Committee Doc. 62, 
74th Cong., 1st Sess. 
Rivers and Harbors 
Committee Doc. 47, 
75th Cong., 1st Sess. 
H. Doc. 561, 80th Cong., 
2nd Sess. 1 
H. Doc. 427, 86th Cong., 
2nd Sess. 
H. Doc. 199, 92nd Cong., 
2nd Sess. 
(Sec. 201, PL 89-298) 
15-24 
12.

GALVESTON TEXAS DISTRICT 
TABLE 15-B AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
13. 
Dec. 15, 1970 
(House Res.) 
Dec. 17, 1970 
(Sen. Res.) 
Jul. 24, 1946 
(As amended) 
Jun. 20, 1938 
Sep. 3, 1954 
Oct. 27, 1965 
Oct. 23, 1962 
Oct. 27, 1965 
Oct. 23, 1962 
Mar. 3, 1905 
Jul. 25, 1912 
Sep. 22, 1922 
Mar. 2, 1945 
Jul. 24, 1946 
Oct. 23, 1962 
Oct. 27, 1965 
Jul. 30, 1983 
TRINITY RIVER AND TRIBUTARIES, TX 
Anahuac Channel. 
Six-foot channel to Liberty. 
Abandon improvements above Liberty and terminate all 
improvements by lock and dam, leaving a 6-foot channel 
from Liberty to mouth. 
Provides for a navigable channel from the Houston Ship 
Channel near Red Fish Bar in Galveston and Trinity 
Bays to the mouth of Trinity River and 9 feet deep and 
150 feet wide in the river section, with a turning basin at 
Liberty. 
Modification of the project to provide for a channel 9 feet 
deep and 150 feet wide from the Houston Ship Channel 
near Red Fish Bar in Galveston Bay extending along 
the east shore of Trinity Bay to the mouth of the Trinity 
River at Anahuac, including protective spoil 
embankment on the bay side of the channel in lieu of the 
9 by 200-foot channel in Galveston and Trinity Bays. 
Provides for the multiple-purpose Wallisville Reservoir, 
including a navigation lock in the Wallisville Dam at 
Channel Mile 28.30 and advancement of the Channel to 
Liberty from one mile below Anahuac (Mile 23.2) to the 
Texas Gulf Sulphur Company's slip at Channel Mile 
35.8, and incorporation into existing project Anahuac 
Channel and mouth of Trinity River projects. 
Reevaluation of navigation benefits. 
Modified Wallisville Reservoir by reducing the size to 
5,600 acres and confining the reservoir to east side 
of Trinity River. 
CORPUS CHRISTI BEACH, TX 
(RESTORATION PROJECT) 
Restoration and periodic nourishment of 1.4 miles of 
beach. 
ARROYO COLORADO, RIO HONDO, TX 
Bank protection of 400 feet of east bank of Arroyo 
Colorado downstream of Farm-to-Market Road 106. 
BUFFALO BAYOU AND TRIBUTARIES, TX 
Barker and Addicks Reservoirs, Texas. 
Clearing, straightening, enlarging and lining of Buffalo 
Bayou, Brays, and White Oak Bayous. 
Extend upper limits of White Oak Bayou upstream about 
2.1 miles from BRI RR bridge to mouth of Cole Creek. 
FREEPORT AND VICINITY, TX 
(HURRICANE-FLOOD PROTECTION) 
Improvements to 42.8 miles of existing levees, 2.1 miles 
of new levees and 2 interior drainage pumping plants. 
HIGHLAND BAYOU, TX 
Enlargement and rectification of Highland Bayou 
Channel, construction of diversion dam, and diversion 
channel. 
PORT ARTHUR AND VICINITY, TX 
(HURRICANE-FLOOD PROTECTION) 
Raising and reconstructing 6.3 miles of existing seawall; 
constructing 0.3 mile of new seawall, 20.3 miles new 
levees and five pumping plants; and raising and 
improving 7.5 miles of existing levees. 28 
15-25 
H. Doc. 989, 66th Cong., 
3rd. Sess. 
H. Doc. 403, 77th Cong., 
1st Sess. 
H. Doc. 634, 79th Cong., 
2nd Sess. 
H. Doc. 215, 87th Cong., 
1st Ses. 
H. Doc. 276, 89th Cong., 
1st. Ses. 
PL 98-63 
H. Doc. 415, 91st Cong., 
2nd Seas. 
(Sec. 201, PL 89-298) 
Sec. 14, PL 79-526 
H. Doc. 456, 75th Cong., 
2nd Sess. 
H. Doc. 250, 83rd Cong., 
2nd Seas. 1 
H. Doc. 169, 89th Cong., 
1st Seas. 
H. Doc. 495, 87th Cong., 
2nd Sess. 
H. Doc. 168, 89th Cong., 
1st Seas. 1 
H. Doc. 505, 87th Cong., 
2nd Sess.1 
16. 
17. 
18. 
19. 
20. 
21.

REPORT OF THE CHIEF OF ENGINERS, U.S. ARMY 1988 
TABLE 15-B 
See Date 
Section Authc 
in Text Act 
22. 
AUTHORIZING LEGISLATION 
priZing 
Oct. 27, 1965 
23. Jul. 3, 1958 
24. Oct. 23, 1962 
Project and Work Authorized 
TAYLORS BAYOU, TX 
Enlarging and rectifying channels; construction of 
diversion channel; a salt water gate; enlargement 
of GIWW 1.3 miles and alteration of State Highway 
87 bridge.2' 
TEXAS CITY AND VICINITY, TX 
(HURRICANE-FLOOD PROTECTION) 
Construction of improvements for control of storm tides, 
consisting of new and enlarged levees and floodwalls 
approximately 14.1 and 2.1 miles in length; related 
drainage and stoplog structures; a navigation opening 
and pumping plants. 
VINCE AND LITTLE VINCE BAYOUS, TX 
Enlarging and rectifying channel of Vince Bayou and 
Little Vince Bayou upstream for a total of 11.5 miles 
for both streams. 
Documents 
H. Doc. 206, 89th Cong., 
1st Sess.' 
H. Doc. 347, 85th Cong., 
2nd Sess.' 
H. Doc. 441, 87th Cong., 
2nd Sess.' 
I Contains latest published maps. 
2 Extension of north jetty 1,950 feet and south jetty 1,265 
feet considered inactive 3 Dredging 2,000 by 650-foot northerly extension of inner 
basin deauthorized. 
"Included in Public Works Administration program 
September 6, 1933 and February 16, 1935. 
West leg of Wye junction with main channel 
deauthorized. 
' Construction of lock in diversion dam at local expense 
considered inactive. 
7 Dredging upper .5 mile of channel to vicinity of Stauffer 
Chemical plant was deauthorized under Sec. 12 of PL 93-251. 
Included in Public Works Administration program 
September 6, 1933. 
* Dredging 43rd to 51st Streets was deauthorized under 
Sec. 12 of PL 93-251. 
' Deauthorized under Sec. 12 of PL 93-251. 
1 Deepening 43rd to 57th Streets was deauthorized 
under Sec. 12 of PL 93-251 
11 Previously authorized September 6, 1933 by Public 
Works Administration. 
12H. Doc. 230, 76th Cong., 1st Sess. and project 
documents contain latest published maps. 
13 Dredging upper 3.5 miles was deauthorized under Sec. 
12 of PL 93-251. 
14 Dredging upper 5 miles is inactive. 
15 Inactive. 
16 Portion of 16-foot by 150-foot channel from Sabine 
River to Houston Ship Channel and relocation of channel in 
Matagorda Bay are in inactive category. 
" The 9 feet by 100 feet channel from Mile 8.2 to Mile 
13.2 in Chocolate Bayou is inactive. 
1 Construction of pile dike was deauthorized under Sec. 
12 of PL 93-251. 
1* Hill Street Bridge to mouth of White Oak Bayou was 
deauthorized under Sec. 12 of PL 93-251. 
2o Deepening channel to 40 feet from Southern Pacific 
Slip to Brady Island was deauthorized under Sec 12 of PL 
93-251. 
21 The 12-foot channel from mile 1.65 to mile 2.81 is 
inactive. 
2 Complete widening of channel between Port Arthur 
west turning basin and Taylors Bayou turning basin 
authorized by 1962 R&H Act. 
"s Complete deepening of channel between Port Arthur 
west turning basin and Taylors Bayou turning basin 
deauthorized by 1962 R&H Act. 
4 Channel extension above Cow Bayou turning basin 
near Orangefield was deauthorized under Sec. 12 of PL 
93-251. 
S Widening to 350 feet entrance channel to Port Arthur 
turning basin deauthorized by 1962 R&H Act. 
as The 12-foot channel in Sabine River from Orange to 
Echo, Texas is inactive. 
2' Jetty extension inactive. 
" Raising and strengthening of levees surrounding Gulf 
Oil Company's fresh water reservoir is inactive. 
" Enlarging 7.0 miles of North Fork Taylors Bayou, 7.8 
miles of South Fork Taylors Bayou and 4.4 miles of Mayhaw 
Bayou are inactive. 
15-26

GALVESTON TEXAS DISTRICT 
OTHER AUTHORIZED NAVIGATION PROJECTS 
TABLE 15-C 
For Last Cost To September 30, 1983 
Full Report 
Project See Annual Operation and Report For Construction Maintenance 
Aquatic Plant Control (1958 and 1962 River and 
Harbor Acts)6 1967 38,252' - 
Bastrop Bayou, TX2 
3 1931 9,920 27,129 
Brazos River, TX, Velasco to Old Washington 3 1924 216,989 s 223,010 
Cedar Bayou, TX 1982 681,2634 2,033,275' 
Clear Creek and Clear Lake, TX 1982 66,934 537,139 
Corpus Christi, TX, Channel to Navy Seaplane Base 
Encinal Peninsula6 1968 1,194,344 26,467 
Dickinson Bayou, TX6 1954 33,942 57,553 
East Bay (Hanna Reef), TX6 1922 2,476 847 
Johnson Bayou, LA6 0 1933 2,261 54,042 
Little Bay, TX1� 1979 - 252,728 
Oyster Creek, TX6 11 1922 6,942 7,556 
Sabine River and Tributaries, TX (Echo to Morgan Bluff)3 1971 - - 
1 Excludes $1,672 work contributions. Includes $69,784 for previous projects. 
2 Widening from 60 feet to 100 feet at 4-foot depth was * In inactive category for maintenance. 
deauthorized under Sec. 12 of PL 93-251. ' Channel adequate for existing commerce. 3 Inactive. 10Aransas County Navigation District, Rockport, TX, 4 Includes $39,087 for previous projects. In addition, $25,000 constructed project as authorized by 1950 River and Harbor Act 
expended from contributed funds. (H.D. 114, 81st Cong., 1st Sess.) in 1955 under Departmnt of 
5 Includes $123,676 for previous projects. Army permit. 
6 Completed. " No commerce reported. 
OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
TABLE 15-D 
For Last Cost to September 30, 1983 
Full Report 
Project See Annual Operation and Report For Construction Maintenance 
Baytown, Texas' 1980 245,400 - 
Colorado River, Matagorda, Texas2 1963 273,757 - 
Guadalupe River 
(Remove Log Jams), Texas2 1978 505,749- 
Lavaca-Navidad River, Texas: 
Hallettsville Project 1961 256,043 - 
General channel project 1952 21,086 - 
Liberty Local Protection Project, Texas' 1971 98,517 - 
Mill Creek, Texas' 1952 24,753 - 
Peyton Creek, Texas1 1975 66,377 - 
San Diego Creek, Alice, Texas2 1963 135,175 - 
Tranquitas Creek, Kingsville, Texas2 1956 130,239 - 
1 Inactive. 
2 Completed. 
15-27

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TOTAL COST OF EXISTING PROJECTS TO SEPTEMBER 30, 1983 
TABLE 15-E 
See 
Section 
in Text Project Funds New Work Maintenance Rehabilitation Total 
2. Brasos Island Harbor, TX 
8. Channel to Port Bolivar, TX 
4. Corpus Christi Ship 
Channel, TX 
6. Freeport Harbor, TX 
7. Galveston Harbor and 
Channel, TX 
8. Gulf Intracoastal Waterway 
between Apalachee Bay, FL 
and the Mexican Border 
(Galveston District) 
9. Houston Ship Channel, TX 
11. Sabine-Neches Waterway, TX 
12. Texas City Channel, Tx 
18. Trinity River and 
Tributaries, TX 
Regular 
Public Works 
Contributed 
Total cost of project 
Regular 
Total cost of project 
Regular 
Public Works 
Contributed 
Total 
Value of useful work 
performed 
Contributed land 
Total cost of project 
Regular 
Public Works 
Contributed 
Total 
Value of useful work 
performed 
Total cost of project 
Regular 
Channel 
Seawall 
Public Works 
Contributed 
Total cost of project 
Regular 
Public Works 
Contributed 
Total 
Value of useful work 
performed 
Contributed land 
Total cost of project 
Regular 
Public Works 
Contributed 
Total cost of project 
Regular 
Public Works 
Contributed 
Total 
Value of useful work 
performed 
Contributed land 
Total cost of project 
Regular 
Public Works 
Contributed 
Total cost of project 
Regular 
Contributed 
Total cost of project 
$ 8,333,087 
2,848,560 
1,683,258 
12,864,905 
85,214 
85,214 
43,488,527 
324,287 
1,475,360 
45,288,174 
1,716,695 
276,720 
47,281,589 
2,502,730 
116,575 
758,303 
3,377,608 
360,249 
3,737,857 
11,920,187 
8,754,209 
3,648,932 
24,323,328 
48,826,877 
466,477 
1,102,484 
50,395,838 
395,000 
139,776 
50,930,614 
29,042,293 
2,612,932 
1,382,760 
33,037,985 
49,592,331 
1,363,652 
2,103,435 
53,059,418 
32,000 
116,760 
53,208,178 
12,822,353 
136,296 
1,023,819 
13,982,468 
26,015,599 
66,000 
26,081,599 
$ 2,1 
2,1' 
3,5 
3,5 
$ 32,670,029 
1,117 
32,671,146 
1,025,058 
1,025,058 
69,097,525
- 
434,611 
69,532,136 
- 
69,532,136 
33,294,312
- 
229,311 
33,523,623 
33,523,623 
58,901,897 
166,387 
13,121 
1,959,849 
61,041,254 
155,924,584 
- 
22,672 
155,947,256 
155,947,256 
81,164,698 
163,360 
81,328,058 
101,903,918 
2,052,999 
103,956,917 
103,956,917 
17,101,811 
17,101,811 
6,422,979 
6,422,979 
3,5 
10,080 $ 43,173,196 
- 2,848,560 
- 1,684,375 
70,080 47,706,131 
- 1,110,272 
- 1,110,272 
76,684 116,162,736 
- 324,287 
- 1,909,971 
76,684 118,396,994 
- 1,716,695 
- 276,720 
76,684 120,390,409 
8,935 35,805,977 
- 116,575 
- 987,614 
8,935 36,910,166 
- 360,249 
8,935 37,270,415 
7,373,356 
595,973 
7,969,329 
1,270,511 
1,270,511 
1,270,511 
726,158 
726,158 
78,195,440 
9,516,569 
13,121 
5,608,781 
93,333,911 
206,021,972 
466,477 
1,125,156 
207,613,605 
395,000 
139,776 
208,148,381 
110,206,991 
2,612,932 
1,546,120 
114,366,043 
151,496,249 
1,363,652 
4,156,434 
157,016,335 
32,000 
116,760 
157,165,095 
30,650,322 
136,296 
1,023,819 
31,810,437 
32,438,578 
66,000 
32,504,578 
15-28

GALVESTON TEXAS DISTRICT 
TABLE 15-F CHANNEL DIMENSIONS 
Section of Waterway 
2. Brazos Island 
Harbor, TX 
4. Corpus Christi 
Ship Channel, 
TX 
6. Freeport 
Harbor, Tx 
7. Galveston 
Harbor and 
Channel, TX 
See 
Section 
in Text Project 
Outer Bar and Jetty Channel 
Padre Island to Long Island 
Long Island to Goose Island 
Goose Island to Turning Basin 
Extension 
Turning Basin Extension 
Brownsville Turning Basin 
Port Isabel Channel via East 
Turnout 
West Wye, from Brownsville 
Channel 
Port Isabel Turning Basin 
Fishing Boat Harbor: 
West Basin 
Middle Basin 
East Basin 
Connecting Channel 
Entrance Channel 
Aransas Pass Outer Bar 
Channel 
Aransas Pass Jetty Channel 
Inner Basin at Harbor Island 
Channel to Port Aransas 
Port Aransas Turning Basin 
Anchorage Basin at Port 
Aransas 
Inner Basin to Mile 8.5 
Mile 8.5 to LaQuinta Junction 
LaQuinta Junction to Corpus 
Christi Turning Basin 
Corpus Christi Turning Basin 
Industrial Canal 
Avery Point Turning Basin 
Channel to Chemical Turning 
Basin 
Chemical Turning Basin 
Tule Lake Channel 
Tule Lake Turning Basin 
Viola Channel 
Viola Turning Basin 
Channel to LaQuinta 
LaQuinta Turning Basin 
Turning Point at LaQuinta 
Channel Junction 
Jewel Fulton Canal 
Jewel Fulton Turning Basin 
Mooring Area at Ingleside: 
Mooring Area (a) 
Mooring Area (b) 
Outer Bar Channel 
Jetty Channel 
Quintana Turning Basin 
Channel to Brazosport 
Turning Basin 
Brazosport Turning Basin 
Channel to Upper Turning 
Basin 
Upper Turning Basin 
Channel to Stauffer Chemical 
Plant 
Stauffer Turning Basin 
Brazos Harbor Channel 
Brazos Harbor Turning Basin 
Entrance Channel 
Outer Bar Channel 
Inner Bar Channel 
Anchorage Basin 
Bolivar Roads Channel 
700 
600-730 
730-1,720 
100-150 
2004002 
300-400 
600-500 
500 
400 
800 
400 
975 
400 
1,200 s 
300 
1,200 
300-350 
1,200 
300-400 
1,200 
1,2502 
100 
200 
150 
150 
400 
400 
750' 
400 
1,000' 
375 
1,200' 
200 
500 
200 
750' 
800 
800 
800 
2,875' 
800 
Adopted Project Dimensions 
Depth in Feet Bottom 
(Below Mean Width 
Low Tide) (Feet) 
38-36 300 
36 200 
36 200 
36 300 
36 500 
36 1,000 
36 200 
36 200 
36 1,000 
15 370-305 
15 370-305 
15 370 
15 270 
15 100 
47 
45 
45 
12 
12 
12 
45 
45 
40-45 
40 
40 
40 
40 
40 
40 
40 
40 
40 
45 
45 
45 
12 
12 
45 
38 
36 
36 
36 
36 
36 
30 
25 
30 
30 
42 
42 
40 
36 
40 
700 
600 
Irregular 
100 
2002 
300400 
600-500 
500 
400 
1,000 
400 
1,000 
350 
1,050 s 
200 
900 
200-250 
700-900 
300-400 
1,200 
1,250a 
100 
200 
150 
300 
200 
200-350 
744-800 
350-375 
600 
200 
500 
200 
525-675 
800 
800 
800 
2,875 
800 
1.8 
1.0 
1,550 - 
0.1 
200 - 
900 0.2 
8.5 
3.6 
8.6 
5,423 1.0 
1.1 
1,150 0.2 
0.6 
1,690 0.3 
3.1 
1,000 0.2 
1.8 
1,000 0.2 
5.6 
800 0.1 
1,250 0.2 
- 0.8 
400 0.1 
- 0.8 
- 3.0 
- 0.8 
- 1.2 
667 0.1 
- 1.4 
600 0.1 
- 1.1 
500 0.1 
- 0.5 
675 0.1 
- 4.7 
- 1.7 
- 3.2 
- 1.8' 
- 1.0 
15-29 
Improved Project Dimensions 
Depth in Feet Bottom 
(Below Mean Width Length 
Low Tide) (Feet) Feet Miles 
38-36 300 2.5 
36 200 2.1 
36 200 9.6 
36 200 3.2 
36 500 1.3 
36 1,000 2,670 0.5 
36 200 1.4 
36 200 0.8 
36 1,000 1,300 0.2 
15 370-305 1,470 0.3 
15 370-305 1,200 0.2 
15 370 1,470 .03 
15 265 1,230 0.2 
15 100 770 0.1 
47 
45 
45 
12 
12 
12 
45 
45 
45 
45 
45 
45 
45 
45 
45 
45 
45 
45 
45 
45 
45 
12 
12 
45 
45 
47 
45 
45 
45 
45 
45 
45 
30 
30 
36 
36 
42 
42 
40 
36 
40 
__ 
_____ __

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 15-F CHANNEL DIMENSIONS 
Adopted Project Dimensions Improved Project Dimensions 
See Depth in Feet Bottom Depth in Feet Bottom 
Section (Below Mean Width (Below Mean Width Length 
in Text Project Section of Waterway Low Tide) (Feet) Low Tide) (Feet) Feet Miles 
Galveston Channel: 
Bolivar Roads Channel 
To 43rd St. (cont'd) 40 1,125 40 1,125 - 3.9 
9. Houston Ship Bolivar Roads to Morgan Point 40 400 40 400 - 26.2 
Channel, TX Morgan Point to Boggy Bayou 40 400 40 400 - 12.8 
Boggy Bayou to Greens Bayou 40 300 40 300 - 2.4 
Greens Bayou to Sims Bayou 40 300 40 300 - 5.3 
Hunting Bayou Turning 
Point 40 900-1,000' 40 948-1,000' 1,375 - 
Clinton Island Turning Basin 40 800' 40 965-1,070' 1,592 - 
Sims Bayou to Southern 
Pacific Slip 40 300 40 300 - 0.6 
Southern Pacific Slip to 
Houston Turning Basin 36 300 36 300 - 2.9 
Houston Turning Basin 36 400-1,000 36 400-1,000 3,100 0.6 
Upper Turning Basin 36 150 36 150 1,000 0.2 
Brady Island Channel 10 60 10 60 - 0.9 
Barbour Terminal Channel 16 100 16 100 - 1.5 
Turning Basin 16 1,100 16 1,100 1,000 0.2 
Five-Mile Cut Channel 8 125 8 125 - 1.9 
Light-Draft Channel: 
Upper Turning Basin to 
Jensen Drive 10 60 10 60 - 4.1 
Turkey Bend Channel 10 60 10 60 - 0.8 
Greens Bayou Channel: 
Mile 0 to Mile 0.36 36 175 36 175 - 0.3 
Mile 0.36 to Mile 1.57 15 100 15 100 - 1.3 
10. Matagorda Ship Outer Bar and Jetty Channel 38 300 38 300 - 3.2 
Channel, TX Channel to Point Comfort 36 300-200' 36 300-200' - 20.9 
Approach Channel to Turning 
Basin 36 200-300 36 200-300 - 1.1 
Turning Basin 36 1,000 36 1,000 1,000 0.2 
Channel to Port Lavaca 12 125 12 125 - 4.1 
Lynn Bayou Turning Basin 12 27-340 12 27-340 532 0.1 
Channel to Harbor of Refuge 12 125 12 125 - 1.9 
North-South Basin 12 300 12 300 1,682 0.3 
East-West Basin 12 250 12 250 1,750 0.3 
Channel to Red Bluff 6 100 6 100 - 20.2 
11. Sabine-Neches Sabine Bank Channel 42 800 42 800 - 14.7 
Waterway, TX Sabine Pass Outer Bar 
Channel 42 800 42 800 - 3.4 
Sabine Pass Jetty Channel 40 800-500 40 800-500 - 4.1 
Sabine Pass Anchorage Basin 40 1,500 40 1,500 3,000 - 
Sabine Pass Channel 40 500 40 500 - 5.6 
Port Arthur Canal 40 500 40 500 - 6.2 
Entrance to Port Arthur 
Turning Basins 40 275-678 40 275-678 - 0.3 
Port Arthur East Turning 
Basin 40 420 40 370-547 1,765 0.3 
Port Arthur West Turning 
Basin 40 600 40 350-550 1,610 0.3 
Channel connecting Port 
Arthur West Turning Basin 
and Taylors Bayou Turning 
Basin 40 200-250 40 200-250 - 0.6 
Taylors Bayou Turning Basin 40 150-1,000 40 90-1,233 3,470 0.7 
Sabine-Neches Canal, Port 
Arthur Canal to Neches River 40 400 40 400 - 11.2 
Turning Point at Mile 19.5 40 9004 40 9004 - 
Neches River, Mouth to 
Maneuvering Area at 
Beaumont Turning Basin 40 400 40 400 - 18.3 
Turning Point, Mile 31.1 40 1,000' 40 1,000 700 
Turning Point, Mile 36.6 40 1,000' 40 1,000 930 ' 
Turning Point, Mile 40.3 40 1,0004 40 1,300 1,530 ' 
Channel Extension, 
Mile 40.3 36 350 36 350 1,265 0.2 
15-30

GALVESTON TEXAS DISTRICT 
TABLE 15-F CHANNEL DIMENSIONS 
Adopted Project Dimensions Improved Project Dimensions 
See Depth in Feet Bottom Depth in Feet Bottom 
Section (Below Mean Width (Below Mean Width Length 
in Text Project Section of Waterway Low Tide) (Feet) Low Tide) (Feet) Feet Miles 
Sabine-Neches Maneuvering Area at 
Waterway, Beaumont Turning Basin 40 Irregular 40 Irregular 1,300 0.2 
TX (cont) Beaumont Turning Basin 34 500 34 160-535 1,500 0.3 
Beaumont Turning Basin 
Extension 34 350 34 300 - 0.4 
Beaumont Turning Basin 
Extension to End of Project 
Channel Vicinity 
Bethlehem Steel Company 30 200 30 200 - 0.7 
Sabine-Neches Canal, Neches 
River to Sabine River 30 200 30 200 - 4.4 
Sabine River Channel, Mouth 
to Foot of Green Ave. 30 200 30 200 - 9.5 
Orange Turning Basin 30 Irregular 30 Irregular 1,550 0.3 
Orange Municipal Slip 30 200 30 150-200 2,435 0.5 
Old Channel Around Harbor 
Island 25 150-200 25 150-200 - 2.4 
Channel to Echo7 12 125 - - - - 
Adams Bayou 12 100 12 100 - 1.7 
Cow Bayou 13 100 13 100 - 7.0 
Orangefield Turning Basin 13 300 13 300 500 0.1 
SAverage. 
2 Includes 100-foot channel width. 
3 Includes 450-foot channel to Corpus Christi. 
'Diameter. 
s Includes 350-foot channel width. 
a 300-foot width through Matagorda Peninsula. 
SInactive Category. 
* Included in channel length. 
' Includes 300-foot channel width. 
15-31

TABLE 15-G 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
GULF INTRACOASTAL WATERWAY 
APALACHEE BAY, FLORIDA TO MEXICAN BORDER 
EXISTING PROJECT DIMENSIONS, PROVIDED 
FOR IN TRIBUTARY CHANNELS 
Authorized Improved 
Project Dimensions Project Dimensions 
Depth Depth 
(Feet Below Bottom (Feet Below Bottom 
Mean Width Mean Width Length 
Tributary Channel Low Tide) (Feet) Low Tide) (Feet) Miles Feet 
Offats Bayou 
Main Channel 
West Wye 
Chocolate Bayou Channel 
12-Foot Channel via East 
Turnout 
West Turnout 
9-Foot Channel 
Turning Basin 
San Bernard River Channel 
Colorado River Channel 
Turning Basin 
Silting Basin 
Mouth of Colorado River 
Navigation Channel, GIWW 
to Gulf 
Turning Basin at Matagorda 
Channel to Palacios 
Turning Basin No. 1 
Turning Basin No. 2 
Connecting Channel 
Channel to Barroom Bay 
Channel to Victoria 
Main Channel via east 
Turnout 
Turning Basin 
West Turnout Channel 
Channel to Seadrift via South 
Turnout 
Turning Basin 
North Turnout from Channel to 
Victoria 
Harbor of Refuge at Seadrift 
Channel 
Basin 
Channel to Rockport 
Turning Basin 
Channel to Aransas Pass 
Turning Basin 
Channel to Conn Brown Harbor 
Conn Brown Harbor 
Channel to Port Mansfield 
Entrance Channel 
Approach Channel to Hopper 
Dredge Turning Basin 
Hopper Dredge Turning Basin 
Channel Across Padre Island 
and Laguna Madre 
Turnout Channels, East Side of 
Main Channel, GIWW 
North Turnout 
South Turnout 
Channel West Side of Main 
Channel, GIWW, to P.T. of 
Turnout Channels 
Turnout Channels, West Side of 
Main Channel, GIWW 
North Turnout 
South Turnout 
12 
12 
12 
12
999999 
15-12 
12 
* 12 
12 
12 
12 
* 6
999 
99 
9
9999 14 
14 
14 
14 
10 
16 
16 
16 
14 
12 
12 
14 
12 
12 
12 
12 
12 
12
9999 
12 
12 
12 
12 
125 
125 
125 
125 
100 
100 
400 
150 
125 
200 
300 
130-400 
2.3 
0.4 
8.2 
0.8 
26.0 
15.5 
0.1 
1.0 
16.1 
0.1 
0.2 
0.1 
34.8 
0.1 
0.8 
2.0 
0.5 
- 
2,200 
500 
635 
1,130 
800(avg) 
230 
125 
125 
125 
125 
100 
600 
100 
100 
400 
150 
200-100 
350 
125 
200 
300 
150-480 
60 
100 
600(avg) 
100 
100 
250 
100 
100 
200 
200 
475 
175 
300 
125 
300 
250 
100 
300 
100 
100 
100 
100 
200 
200 
100 
500(avg) 
100 
100 
200 
100 
� - - 
2.1 - 
0.2 1,225 
!
99 
14 
14 
14 
14 
2613 
2613 
2613 
14 
200 
342(avg) 
125-175 
300 
125 
300 
250 
100 
300 
100 
2,212 
1,800 
300 
6.1 
0.4 
0.2 
0.3 
0.8 
0.4 
0.1 
7.7 
0.6 
0.6 
0.3 
0.6 
0.6 
12 
12 
14 
12 
12 
100 
100 
100 
200 
200 
15-32

TABLE 15-G 
Tributary Channel 
GALVESTON TEXAS DISTRICT 
GULF INTRACOASTAL WATERWAY 
APALACHEE BAY, FLORIDA TO MEXICAN BORDER 
EXISTING PROJECT DIMENSIONS, PROVIDED 
FOR IN TRIBUTARY CHANNELS 
Authorized Improved 
Project Dimensions Project Dimensions 
Depth Depth 
(Feet Below Bottom (Feet Below Bottom 
Mean Width Mean Width 
SLow Tide) (Feet) Low Tide) (Feet) 
Channel from P.T. of Turnout 
Channels to Approach Channel 
to Main Turning Basin 
Approach Channel to Main 
Turning Basin 
Main Turning Basin 
Turning Basin Extension 
Small Craft Basin 
Shrimp Basin 
Channel to Harlingen via South 
Turnout from Main 
Channel, GIWW 
Turning Basin near Rio Hondo 
North Turnout from Main 
Channel 
Port Isabel Side Channels 
Main Channel 
Main Channel 
South Leg 
Port Isabel Small Boat Harbor 
Entrance Channel 
Harbor Channel 
Boat Basin 
14 
14 
14 
14 
8 
12 
12 
12 
12 
12 
12 
12
766 
125 
200 
400 
1,000 
160 
350 
233 
Varia 
I Includes the construction of a salt water barrier at Mile 
16.9.
SConstructed 10 feet deep by 100 feet wide by local 
interests. East turnout channel constructed 150 feet wide. 
4 Constructed by local interests. 
SAuthorized to mile 13.2. Mile 8.2 to Mile 13.2 is in 
inactive category. 
' Authorized to Mile 81 above mouth (channel mile 
29.41). Upper 3.4 miles was deauthorized under Section 12 of 
PL 93-251. 
* Includes a discharge channel from Matagorda, Texas, to 
the gulf which was dredged by local interests in 1939. 
(Maintenance will be discontinued upon completion of 
improvements authorized by R&H Act of 1968.) 
SAuthorized by R&H Act of 1968. Also provides for a 
dam across the present discharge channel, a new 250-foot 
14 
14 
14 
14
8 
12 
125 
200 
400 
1,000 
160 
850 
0.6 
0.83 
0.2 
0.1 
0.2 
0.3 
1,250 
580 
860 
1,450 
125 12 125" 25.812 - 
400 12 400 0.1 500 
200 12 200 0.7 - 
125 12 125-90 0.6 - 
3-60 12 233-60 0.4 - 
125 12 125 0.2 - 
75 7 75 1.4 - 
50 6 50 0.3 - 
able 6 72-501 0.2 1,308 
wide by 20 to 28-feet deep discharge channel into Matagorda 
Bay, and a 15-foot by 200-foot wide entrance channel with 
parallel jetties from the gulf shoreline into the Gulf of 
Mexico. East jetty to be 3,500 feet long and west jetty 2,900 
feet long. 
* Includes two protective breakwaters at entrance to 
turning basins. 
' In the inactive category for maintenance. 
ao Also provides for two stone jetties at the gulf entrance 
about 1,000 feet apart. (North et constructed 2,800 feet 
long and south jetty constructed 2,270 feet long.) 
"South turnout is 200 feet wide. 
SAuthorized to mile 81. Mile 25.8 to Mile 81 is in 
inactive category. 
"* Dredged 26 feet deep to accommodate U.S. Hopper 
Dredge A. ACKENZIE. 
15-33 
Length 
Miles Feet
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983

TABLE 15-H

__

Brazos Island
Harbor, TX
(Maintenance)

Entrance Channel

August 2, 1983 to September 8, 1983

886,343

1,854,510

Brownsville Channel and
Port Isabel Channel
Highway Ferry Slip

June 27, 1983 to September 30, 1983

198,095

925,353
Channel to 
Port Bolivar, TX
(Maintenance)

Highway Ferry Slip

December 22, 1982 to July 21, 1983

68,846

40,531

Corpus Christi Ship
Channel, TX
(Maintenance)

La Quinta Junction to 
Beacon 82

October 1, 1982 to October 18, 1982

2,407,390

1,222,400

Bay Channel and Main
Turning Basin

August 9, 1983 to September 30, 1983

363,537

715,700

Freeport Harbor, TX

Entrance Channel

June 9, 1983 to September 30, 1983

1,225,205

2,004,321

Inside Channels and
Basins

October 1, 1982 to January 8, 1983

1,034,914

1,650,815

Gulf Intracoastal Waterway
between Apalachee Bay, FL
and the Mexican Border
(Galveston District)
(Maintenance)

High Island to Port
Bolivar

December 22, 1982 to July 21, 1983

3,811,219

3,465,580

Channel to Palacios and
Matagorda Bay Channel

March 9, 1983 to June 8, 1983

2,160,884

783,480

Port Mansfield Entrance
Channel

May 10, 1983 to July 5, 1983

372,765

1,020,977

Cedar Lakes to Colorado
River

June 11, 1983 to September 30, 1983

2,461,700

2,237,310

Corpus Christi Bay to
Mud Flats

August 8, 1983 to September 30, 1983

613,655

428,000

Emergency dredging,
Channel to Victoria

August 15, 1983 to September 30, 1983

4,613

33,741

Turnstake Island to Live
Oak Point

August 30, 1983 to September 30, 1983

876,873

357,050

North Deer Island to
Bastrop Bayou

October 1, 1982 to October 16, 1982

607,873

516,211

Port Isabel to Mud
Flats, Channel to
Harlingen, and Channel
to Port Mansfield

October 1, 1982 to January 30, 1983

1,581,155

1,166,697

Emergency dredging,
Brazos River Crossing

October 1, 1982 to October 19, 1982

53,688

168,607

Channel to Victoria and
Channel to Seadrift

October 1, 1982 to April 21, 1983

1,333,929

1,154,103

Houston Ship Channel,
TX (Maintenance)

Carpenter Bayou to
Greens Bayou

May 2, 1983 to September 30, 1983

960,000

2,283,700

Matagorda Ship
Channel, TX
(Maintenance)

Matagorda Peninsula
to Point Comfort

June 27, 1983 to
September 30, 1983

1,864,023

1,169,620

Sabine-Neches
Waterway, TX
(Maintenance)

Outer Bar and Jetty
Channel (U.S. Hopper
Dredge Wheeler)

July 24, 1983 to August 7, 1983

200,000

280,930

Sabine-Neches Canal
and Lower Reach
Neches River Channel

October 1, 1982 to January 15, 1983

1,957,554

1,335,610

Port Arthur Turning
Basin and Junction Area

March 28, 1983 to July 3, 1983

1,365,774

1,073,069

15-34


TABLE 15-I 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
JOBS ACT CONTRACT AWARDED DURING FY-83 
(P. L. 98-8, March 24, 1983) 
Project Funding FY 83 
Arroyo Colorado River, 
Rio Hondo, TX 
Brazos Island Harbor, TX 
Buffalo Bayou and 
Tribs, TX 
Corpus Christi Ship 
Channel, TX 
Freeport Harbor, TX 
Galveston Harbor and 
Channel, TX 
Sabine Neches Waterway, TX 
Gulf Intracoastal Waterway 
Matagordo Ship Channel 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
(Contr not awarded) 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
15- 35 
170,000 
0 
2,800,000 
2,473,028 
254,000 
42,132 
31,000 
27,308 
2,516,200 
2,030,076 
281,000 
30,219 
1,547,200 
324,325 
4,940,000 
3,498,040 
5,000 
3,205

FORT WORTH, TX DISTRICT* 
District includes that portion of Texas south of Red 
River drainage basin exclusive of drainage basin of Rio 
Grande and its tributaries above and including Pecos 
River; exclusive of drainage basins to all short streams 
arising in coastal plain of Texas and flowing into the Gulf 
of Mexico, including entire basins of Buffalo Bayou, San 
Jacinto, San Bernard, Lavaca, Navidad, Mission, and 
Arkansas Rivers; exclusive of lower basins of major 
streams flowing into the gulf as follows: Sabine River, 
Texas and Louisiana, downstream from U.S. Highway 
190 crossing at Bon Wier, Texas; Neches River 
downstream from Town Bluff gaging station; Trinity 
River downstream from Texas State Highway 45 crossing 
at Riverside, Texas; Brazos River downstream from 
confluence with Navasota River; Colorado River 
downstream from gaging station at Austin; Guadalupe 
River downstream from confluence with San Marcos 
River; San Antonio River downstream from confluence 
with Escondido Creek; Nueces River downstream from 
confluence with Frio and Atascosa Rivers; and exclusive 
of Agua Dulce, San Fernando, and Olmos Creek basins 
draining into Baffins Bay and coastal area south thereof 
to Rio Grande and east of western boundary of Starr 
County, Texas. District also includes those portions of the 
Sulphur River and Cypress Creek Watershed located in 
the State of Texas; that portion of western Louisiana in 
Sabine River drainage basin upstream from U.S. 
Highway 190 crossing at Bon Wier, Texas. 
IMPROVEMENTS 
Navigation Page 
1. Trinity River Project, TX ............... 16-2 
Flood Control 
2. Aquilla Lake, TX ..................... 
3. Bardwell Lake, TX .................... 
4. Belton Lake, TX ..................... 
5. Benbrook Lake, TX .................... 
6. Big Sandy Lake, TX ................... 
7. Boggy Creek, TX ..................... 
8. Canyon Lake, TX ..................... . 
9. Cooper Lake and Channels, TX ......... 
10. Duck Creek Channel Improvement, TX ... 
11. Elm Fork Floodway, TX ................ 
12. Ferrells Bridge Dam-Lake O' The Pines, TX 
13. Grand Prairie, TX (Landfill) ............. 
14. Grapevine Lake, TX ................... 
15. Greenville, TX ........................ 
16. Hords Creek Lake, TX ................. 
17. Joe Pool Lake, TX (formerly Lakeview Lake) 
18. Lake Brownwood Modification, TX ....... 
19. Lavon Lake, TX ....................... 
20. Lavon Lake Modification and East Fort 
Channel Improvement, TX .............. 
21. Lewisville Dam, TX ................... 
22. Millican Lake, TX ..................... 
23. Navarro Mills Lake, TX ................ 
24. O. C. Fisher Dam and Lake, TX ......... 
25. Proctor Lake, TX ..................... . 
26. Ray Roberts Lake, TX (Aubrey) ......... 
27. San Antonio Channel Improvement, TX .. . 
28. San Gabriel River, TX ................. 
29. Somerville Lake, TX ................... 
30. Stillhouse Hollow Dam, TX ............. 
31. Three Rivers, TX ...................... 
16-2 
16-3 
16-3 
16-3 
16-3 
16-4 
16-4 
16-5 
16-5 
16-6 
16-6 
16-6 
16-7 
16-7 
16-7 
16-7 
16-8 
16-8 
16-8 
16-9 
16-9 
16-9 
16-10 
16-10 
16-10 
16-10 
16-11 
16-11 
16-12 
16-12 
Flood Control (cont) Page 
32. Waco Lake, TX ....................... 16-12 
33. Wheeler Creek, Gainsville, TX .......... 16-12 
34. Wright Patman Dam and Lake, TX ...... 16-13 
35. Zacate Creek, TX ...................... 16-13 
36. Inspection of completed flood control 
projects ............................. 16-13 
37. Scheduling flood control reservoir 
operations ............................ 16-13 
38. Other authorized flood control projects .... 16-13 
39. Flood control work under special 
authorization ......................... 16-14 
Multiple-Purpose Projects Including Power 
40. Belton Lake Modification, TX ........... 
41. Dam "A" Lake, TX .................... 
42. Rockland Lake, TX ................... 
43. Sam Rayburn Dam and Reservoir, TX .... 
44. Town Bluff Dam-B. A. Steinhagen Lake, TX 
45. Whitney Lake, TX ..................... 
16-14 
16-14 
16-14 
16-14 
16-14 
16-14 
General Investigations 
46. Surveys .............................. 16-15 
47. Collection and study of basic data ........ 16-15 
Tables 
Table 16-A 
Table 16-B 
Table 16-C 
Table 16-D 
Table 16-E 
Table 16-F 
Cost and Financial Statement .... 16-16 
Authorizing Legislation ......... .16-20 
Other Authorized Flood Control 
Projects ...................... 16-23 
Inspecation of Completed Flood 
Control Projects ................ 16-23 
Flood Control Work Under 
Special Authorization ........... 16-24 
Jobs Bill, Special Authorization 
PL 98-8 ....................... 16-25 
16-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Navigation 
1. TRINITY RIVER PROJECT, TX 
The project authorized by the River and Harbor Act of 
1965 (H. Doc 276, 89th Cong., 1st Sess.) consists of five 
major components: Multiple-Purpose Channel, 
Tennessee Colony Lake, Dallas Floodway Extension, 
West Fork Floodway, and Water Conveyance Facilities. 
For the last full report on the project as authorized, see 
Annual Report of 1978. The project information present 
herein is based on the tentatively selected project plan 
presented in the Draft General Design Memorandum. 
The plan consists of three structural components: Dallas 
Floodway Extension, Tennessee Colony Lake, and a 
Channel to Liberty in the lower basin. The estimated 
cost of the improvements is $1,220,000,000 including 
$80,000,000 non-Federal cost for land acquisition and 
relocation required for the local protection features (Oct. 
1, 1983, base price). 
Operations during fiscal year. Preconstruction 
planning continued. 
CHANNEL TO LIBERTY: 
Location. The Channel to Liberty begins at the 
Houston ship channel, crosses the bay area in an easterly 
direction to intersect the existing Double Bayou channel 
turns northward along the coastline to Wallisville Lake 
and then continues northward through the lake area 
along the course of the Trinity River to RM 45 above 
Liberty, Texas. 
Existing project. The navigation portion of the 
channel will have a width of 200 feet with a depth of 12 
feet and will extend from the Houston ship channel in 
Galveston Bay to the port of Liberty, Texas. The flood 
control portion of the channel will have a bottom width of 
320 feet with a depth of 30 feet, and will extend from 
Wallisville Lake to RM 45 above Liberty, Texas. 
Estimated Federal cost of the improvements is 
$159,000,000 and estimated non-Federal cost is 
$17,000,000 for a total estimated cost of $176,000,000 
(Oct. 1, 1983, base price). 
Local cooperation. Local interests are required to: (a) 
provide, without cost to the Federal Government, all 
lands, easements and rights-of-way required for 
construction, operation and maintenance of the project, 
(b) accomplish, without cost to the Federal Government, 
all relocations and alterations to existing improvements, 
other than highway bridges over new land cuts and 
railroad bridges required for the construction of the 
project, (c) maintain and operate the flood control portion 
of the channel upstream of Liberty, Texas, and (d) 
reimburse the Federal Government for one-half of the 
separable costs allocated to recreation and fish and 
wildlife enhancement. This reimbursement is presently 
estimated at $238,000, exclusive of interest. 
TENNESSEE COLONY LAKE: 
Location. The Tennessee Colony dam site is located at 
River Mile 341.7 on the Trinity River about 22 miles 
west of Palestine, Texas. The lake would extend into 
Freestone, Anderson, Henderson, and Navarro Counties, 
and would control a drainage area of 12,302 square 
miles. 
Existing project. The plan of improvement provides 
for the construction of an earthfilled dam with a 
maximum height of 123 feet above the streambed and a 
total embankment length of 42,350 feet with a gated 
concrete spillway. The lake will have a total controlled 
storage of 3,455,000 acre-feet and a water surface area of 
114,400 acres at the top of the flood control pool and 
68,100 acres at the top of the conservation pool. The total 
storage includes 2,269,500 acre-feet for flood control, 
1,040,000 acre-feet for conservation, and 145,500 acrefeet 
for sediment reserve. Estimated Federal cost of the 
improvement is $913,000,000 (Oct. 1, 1983, base price). 
Local cooperation. Local interests are required to 
reimburse the Federal Government for costs allocated to 
water supply storage and one-half of the separable cost 
allocated to recreation and fish and wildlife 
enhancement. This reimbursement is presently 
estimated at $461,754,000 for water supply and 
$9,533,000 for recreation (excluding future recreation 
facilities), for a total cost of $471,287,000, exclusive of 
interest. 
DALLAS FLOODWAY EXTENSION: 
Location. Dallas Floodway Extension is located on the 
Trinity River in the City of Dallas, Dallas County, Texas. 
Existing project. The plan of improvement provides 
for extending the existing Floodway downstream about 9 
miles to the confluence of the Trinity River and Five Mile 
Creek. The plan consists of a leveed floodway and flood 
conveyance improvement (channel) along the main stem, 
Five Mile Creek and White Rock Creek. Maintained free 
of encroachments, the levees and channels would provide 
Standard Project Flood protection for approximately 
7,300 acres of urban lands currently subject to flooding. 
The estimated Federal cost is $68,000,000 and estimated 
non-Federal cost is $63,000,000 for a total estimated cost 
of $131,000,000 for the improvement (Oct. 1, 1983, base 
price). 
Local cooperation. Local interests are required to: (a) 
provide, without cost to the Federal Government, all 
lands, easements and rights-of-way necessary for 
construction, maintenance and operation of the project, 
(b) accomplish, without cost to the Federal Government, 
all alterations to existing improvements, other than 
railroad bridges required for the construction of the 
project, (c) maintain and operate the project after 
completion, and (d) reimburse the Federal Government 
for one-half of the separable costs allocated to recreation 
and fish and wildlife enhancement. This reimbursement 
is presently estimated at $1,878,000 (excluding future 
recreation) exclusive of interest. 
Flood Control 
2. AQUILLA LAKE, TX 
Location. On Aquilla Creek in Hill County, Texas, 
with the dam at River Mile 23.3, about 6.8 miles 
southwest of Hillsboro, Texas, and about 24.0 miles 
north of Waco, Texas. (See U.S. Geological Survey maps, 
Aquilla and Peoria, Texas, quadrangle scale 1:24,000.) 
Existing project. Plan of improvement provides for an 
earthfill dam 104.5 feet high and 11,800 feet long with an 
16-2

FORT WORTH TEXAS DISTRICT 
uncontrolled concrete spillway 1,200 feet long on the left 
abutment, creating a lake with a total storage capacity of 
146,000 acre-feet, including 86,700 acre-feet for flood 
control, 33,600 acre-feet for water supply, and 25,700 
acre-feet for sediment reserve. Drainage area above 
damsite is 294 square miles. Estimated cost is 
$46,100,000. Construction was started March 1977, with 
award of contract for relocation of FM Road 310. 
Contracts for Completion of Embankment and Spillway 
and Construction of Services Bridge, Access Roads, 
Project Buildings, Visitors Center Overlook, FM-310 and 
other Appurtenances awarded January 21, 1981. 
Revegetation contract awarded August 9,1982; Sanitary 
and Safety Facilities contract awarded July 23, 1982, 
and Boundary Fencing, Pt. II contract awarded 
September 16, 1982, continue. 
Local cooperation. The Water Supply Act of 1958, as 
amended, and the Federal Water Project Recreation Act 
of 1965 and Section 221, Flood Control Act of 1970 apply. 
A contract with the Brazos River Authority for water 
supply storage was approved by the Secretary of the 
Army, June 29, 1976. To date, the Authority has paid 
$56,834 toward principal and $4,742 to operation and 
maintenance. 
Operations during fiscal year. A contract for 
Surface Drainage-Embankment was awarded March 1, 
1983. Contract for Relocation, Rearrange or Alter 
Telephone Facilities was awarded June 29, 1983. 
Deliberate Impoundment of water began April 29, 1983. 
3. BARDWELL LAKE, TX 
Location. Dam is on Waxahachie Creek, 5 river miles 
upstream from its confluence with Chambers Creek, a 
tributary of the Trinity River, and about 5 miles south of 
Ennis, Ellis County, Texas. 
Existing project. For a description of completed 
improvement and authorizing act see Annual Report of 
1969. Construction of project was started August 1963 
and completed for beneficial use in November 1965. 
Estimated cost of project is $12,941,000. 
Local cooperation. Local interests must reimburse 
the Federal Government for costs allocated to increased 
water supply storage under the terms of the Water 
Supply Act of 1958. In Contract approved by the 
Secretary of the Army on June 24, 1963 the Trinity River 
Authority, a State agency, agreed to fulfill all 
requirements of local cooperation. To date the authority 
has paid $213,628 toward principal and $323,057 toward 
annual cost of operation and maintenance of project, 
including cost of operating 10-foot conduit. 
Operations during fiscal year. Routine operation 
and maintenance continued. Recreation facilities under 
Code 710 remain. 
Benefits accured to Bardwell project: Accumulated 
flood damages prevented through FY 1983 were 
$8,659,700. 
4. BELTON LAKE, TX 
Location. Dam is on Leon River about 16.7 miles 
above confluence of Leon and Lampasas Rivers and 
about 3 miles north of Belton, Texas. (See Geological 
Survey base map, scale 1:500,000 and Geological Survey, 
Belton sheet, scale 1:62,500.) 
Existing project. For a description of completed 
improvement and authorizing acts see Annual Report of 
1962. Estimated cost of project is $18,410,000. 
Construction started June 1949 and project was ready for 
beneficial use in March 1954. Raising water supply pool: 
Construction started in July 1970 and the pool raise is 
complete. 
Local cooperation. Section 2, Flood Control Act of 
1938, applies. A contract with Brazos River Authority, a 
State agency, for remaining water supply storage in 
reservoir was approved by Secretary of the Army on 
January 15, 1958, at an estimated cost of $1,602,822. To 
date $921,990 has been paid. Under the contract Brazos 
River Authority must also pay annually 11.2 percent of 
actual annual cost of operation and maintenance. To date 
$774,723 has been paid. An interim contract with Brazos 
River Authority for emergency use of water supply 
storage in project was approved by Secretary of the Army 
on January 2, 1957. Amount of $152,435 paid by 
authority on March 21, 1957 for use of these facilities 
was credited to interest and principal payable under 
formal water supply contract. 
Operations during fiscal year. Routine operation 
and maintenance continued. Recreation facilities under 
Code 710 regular remain. 
Benefits accrued to Belton project: Accumulated 
damages prevented through FY 1983 were $105,983,100. 
5. BENBROOK LAKE, TX 
Location. Dam is in Tarrant County, Texas, on Clear 
Fork of Trinity River 15 river miles upstream from its 
confluence with West Fork of Trinity River about 10 
miles southwest of downtown Fort Worth, Texas. 
Existing project. For description of completed 
improvement and authorizing acts see Annual Report for 
1962. Estimated cost of project is $14,544,000. 
Construction of project was started May 1947 and ready 
for beneficial use in September 1952. 
Local cooperation. Section 2, Flood Control Act of 
1938, applies. No water supply storage is included in 
project. 
Operations during fiscal year. Routine operation 
and maintenance continued. Construction of recreation 
facilities under Code 710 continued including recreation 
facilities under a cost-sharing contract with the City of 
Benbrook, Texas, paid May 10, 1983. 
Benefits accrued to system consisting of Benbrook 
Lake, Clear Fork and West Fork Floodways: 
Accumulated flood damages prevented through FY 1983 
are estimated at $48,303,500. 
6. BIG SANDY LAKE, TX 
Location. The project is located on Big Sandy Creek, a 
tributary of the Sabine River, and is virtually contained 
in Wood County, with a small area extending into 
16-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Upshur County. The damsite is located at River Mile 
15.3 about 6 miles northwest of Big Sandy, Texas. 
Existing project. The project provides for 
construction of an earth and rock fill dam with a 
maximum height of 94.5 feet above streambed and a 
total length of 6,200 feet, including the concrete 
spillway. Big Sandy Lake would have a total controlled 
storage of 418,200 acre-feet and a water surface area of 
16,580 acres at elevation 382.0, top of flood control pool. 
At elevation 367.5, top of conservation pool, the lake 
would have an area of 10,810 acres and a storage 
capacity of 221,200 acre-feet. Project was authorized by 
the Flood Control Act of 1970 (PL 91-611) and is a unit in 
the comprehensive basin-wide plan of water resource 
development. Estimated cost of project is $99,100,000. 
Local cooperation. Water Supply Act of 1958, as 
amended, and the Federal Water Project Recreation Act 
of 1965 apply. The Sabine River Authority of Texas and 
the Texas Water Development Board are the local project 
sponsors. 
Operations during fiscal year. March 25, 1982, Ph I 
GDM was recommended for termination due to lack of 
present Federal interest in the project. Project was 
recommended to be reclassified to inactive status 
December 28, 1982, based on the infeasibility of the 
project. 
7. BOGGY CREEK, TX - COLORADO 
RIVER AND TRIBUTARIES 
Location. In southeast portion of the city of Austin, 
Texas, which is about 160 miles north of Houston and 
approximately 200 miles south of Dallas-Fort Worth 
area. 
Existing project. The recommended plan consists of 
concrete trapezoidal channel on Boggy Creek beginning 
just above Webberville Road and extending downstream 
about 2.2 miles to just below Jain Lane. From there, a 
grass lined channel would extend further downstream 
and transition into the natural channel at Ed Bluestein 
Boulevard, a distance of about 0.7 miles. New bridges 
would be required at four street crossings and two 
railroad crossings. Two small ponds, about one acre in 
size and a maximum depth of three feet, will be formed by 
weirs located between Ed Bluestein Boulevard and Jain 
Lane and also upstream of Webberville Road. The plan 
calls for acquisition of 54 acres of land adjacent to the 
lower end of the channel to mitigate habitat losses and 
also to provide for environmental quality enhancement. 
About 3.25 miles of trails along the channel and 0.95 
miles in the EQ/mitigation area will also be provided. 
Estimated Federal cost is $20,900,000 including 
$6,600,000 non-Federal cost (Oct. 1, 1983, base price). 
The proposed flood control channel will provide 
capacities for the 100 year flood. Design will provide for 
containment of flows within the banks of the improved 
channels. Bottom widths for the concrete channel will 
vary from 80 feet to 120 feet, and top widths from 90 feet 
to 180 feet. 
Local cooperation. In accordance with the 
President's 1978 Cost Sharing Policy and the 
recommendations contained in the reporting document, 
the State of Texas is required to make a cash 
contribution of 5 percent of construction costs associated 
nonvendible outputs. The city of Austin is required to 
provide a cash or in-kind contribution equal to 20 percent 
of the project first costs associated with flood control 
benefits and 20 percent of the associated mitigation 
lands. The city is also required to provide 50 percent of 
the recreational development cost and 25 percent of the 
EQ enhancement lands. The city will also be required to 
hold and save the United States free from damages due to 
the construction work, operate and maintain all works 
after completion, prevent any obstruction or 
encroachment that would reduce the flow capacity of the 
project, provide and maintain adequate lateral drains 
and channels, publicize flood plain information for all 
streams in the watershed and adopt and enforce 
regulations to minimize damages to future developments 
within the 100-year flood plain, and administer and 
assure access to the recreational facilities and lands to 
all on an equal basis. 
Operations during fiscal year. A reevaluation of the 
Interim Survey Report was submitted May 5, 1982, and 
approved May 18, 1982. The Phase II GDM is scheduled 
for submission in September 1984. Specific authorization 
for construction of Boggy Creek is pending. 
Preconstruction planning continued. 
8. CANYON LAKE, TX 
Location. Dam is on Guadalupe River, 303 miles 
above its mouth, and about 12 miles northwest of New 
Braunfels, Comal County, Texas. 
Existing project. For a description of completed 
improvement and authorizing act see Annual Report of 
1969. Construction started April 1958 and project 
completed for beneficial use June 1964. Estimated cost of 
project is $21,732,000, including $1,400,000 contributed 
by local interests. 
Local cooperation. Local interests (Guadalupe- 
Blanco River Authority) will utilize water impounded for 
water supply and streamflow regulation for development 
of electric power. In a formal contract approved by Chief 
of Engineers on October 24, 1957, Guadalupe-Blanco 
River Authority agreed to fulfill all requirements of local 
cooperation. Required contribution of $1,400,000 was 
made in full by Guadalupe-Blanco River Authority. The 
estimated cost of the Water Storage contract is about 
$9,000,000. To date $897,303 has been paid. In addition, 
$22,848 was contributed for installation and operation of 
reservoir leakage gages. Under the contract the 
authority must pay 34.8 percent of actual annual cost of 
operation and maintenance. To date $757,334 has been 
paid. 
Operations during fiscal year. Regular funds: 
Routine operation and maintenance continued. 
Recreation facilities under Code 710 remain. 
Benefits accrued to Canyon project: Accumulated 
damages prevented through FY 1983 were $49,624,100. 
16-4

FORT WORTH TEXAS DISTRICT 
9. COOPER LAKE AND 
CHANNELS, TX 
Location. Cooper Dam and Reservoir is located in 
northeast Texas about 4 miles southeast of Cooper, 13 
miles north of Sulphur Springs, and is at river mile 23.2 
on the South Sulphur River. The South Sulphur River 
rises in Fannin County, Texas, and flows generally east 
for about 80 miles to its confluence with the North 
Sulphur River to form the Sulphur River. 
Existing project. The authorized plan of 
improvement consists of a multipurpose reservoir with 
levee and channel improvements on the Sulphur River. 
The reservoir consists of a rolled earthfill dam with a 
maximum height of about 73 feet, 15,882 feet long at its 
crest, one controlled (service) spillway, and an 
emergency uncontrolled spillway. The reservoir surface 
area will be 22,740 acres at the top of the flood control 
pool, 19,305 acres at the top of the water supply pool, and 
5,084 acres at the top of the sediment pool. The reservoir 
will contain 131,400 acre-feet of flood control storage, 
273,000 acre-feet of municipal and industrial water 
supply storage, and 37,000 acre-feet of sediment storage. 
Construction of the project began in July 1958 and, to 
date, approximately 98 percent of the lands required for 
project construction have been acquired and 64 percent of 
the levees and 85 percent of the channel work have been 
completed. Approximately 14.8 miles of the South 
Sulphur River and 6.3 miles of the Middle Sulphur River 
channels have been excavated. Approximately 3.4 miles 
of levee embankment on the South Sulphur River and 7.3 
miles on the Middle Sulphur River have been 
constructed upstream of the Cooper Reservoir. About 
10.5 miles of levee on the North Sulphur River, 8.2 miles 
of levee on the Sulphur River, 14 miles of levee on 
Cuthand Creek, and 4.2 miles of levee on Brushy Creek 
were strengthened; 0.5 mile of levee on Kickapoo Creek 
was enlarged; and 15.3 miles of new channel in Cuthand 
Creek, 0.8 mile of new channel in Brushy Creek, and 0.2 
mile ofcutoffchannel in Kickapoo Creek were excavated; 
all downstream from Cooper Reservoir. 
Lack of funds and spending limitations prevented 
construction of the levees and channel work between 
April 1964 and February 1971. Construction was started 
again, however, in May 1971. The Texas Committee on 
Natural Resources, et al, secured an injunction to halt 
construction on the project pending preparation of an 
Environmental Impact Statement (EIS), required by the 
National Environmental Policy Act of 1969. A statement 
was prepared and filed on June 24, 1977. The plan 
recommended, in the Final EIS, minimized further 
construction of the authorized channels and provided for 
construction of the reservoir and downstream levees. The 
sufficiency of the Final EIS was challenged in the court 
and in December 1978 the U.S District Court for the 
Eastern District of Texas ruled the statement 
inadequate, citing five deficiencies and hatting all 
further construction. A Supplemental EIS to comply 
with the court's decision was prepared and filed with the 
Environmental Protection Agency in March 1981. The 
recommended plan of improvement consists of the 
multipurpose lake, 0.9 mile of levee, and the acquisition 
of 25,500 acres of wildlife mitigation lands. All 
remaining channel and levee work was deleted from the 
recommended plan. The Supplemental EIS was filed 
with the court in July 1981 and numerous motions, 
documents, affidavits, and briefs were subsequently 
filed. The project is still in litigation at this time. 
Estimated Federal cost (Oct. 1, 1983, base price) is 
$138,227,000 which includes $56,003,000 to be 
reimbursed by water supply users over a 50-year period 
and $227,000 non-Federal cost for land for the levees. 
Local cooperation. Except for Cooper Reservoir, local 
interest must furnish lands and rights-of-way and alter 
and relocate highways and related facilities and utilities, 
except railroads, for construction; hold and save the 
United States free from damages; maintain and operate 
all works after completion, and preserve channel 
capacities by preventing encroachment. Local agencies 
furnished rights-of-way for the first two phases of work 
on the levees and channel downstream from Cooper 
Dam. Right-of-way acquisition for the second phase was 
also essentially complete when construction was halted. 
Assuring agencies are the following counties in Texas: 
Delta, Hunt, Franklin, Lamar, Morris, Hopkins, Titus, 
and Red River. Basic assurances have been received. 
Supplemental assurances covering Public Law 91-646 
have not been received from Delta, Lamar, Morris, or 
Hunt Counties. 
Operations during fiscal year. After the 
Supplemental EIS was filed in July 1981, numerous 
motions, documents, affidavits, and briefs were filed 
through October 1982. On December 30, 1982, the U.S. 
District Court issued a 95-page order continuing the 
permanent injunction. On March 22,1983, the order was 
revised and Judge William Wayne Justice issued an 
Amended Memorandum Opinion and a Permanent 
Injunction against the construction of Cooper Lake. The 
Government filed a Notice of Appeal with the court in 
May 1983. Since that time, several briefs have been filed 
with the New Orleans Fifth Circuit Court of Appeals. 
Current action centers on the Appeal and resolution of 
the litigation. 
The project was transferred to the Fort Worth District 
at the end of FY 1979. 
10. DUCK CREEK CHANNEL 
IMPROVEMENT, TX 
Location. In Garland, Dallas County, Texas on Duck 
Creek, a tributary of the Trinity River between River 
Mile 10.4 and 17.5. 
Existing project. Provides for realignment and 
enlargement of 6.6 miles of channel improvement 
consisting of concrete walls, modification of drainage 
facilities, 2 railroad bridges, 9 street bridges and 
relocation of all utilities. Estimated Federal cost of these 
modifications is $9,000,000 and estimated cost to local 
interests is $6,500,000, a total of $15,500,000. Existing 
project was authorized by River and Harbor Act of 1965 
in House Document 276, 89th Congress, 1st Session. 
Construction started in June 1972, and the project is 4 
percent complete. Construction has been suspended 
pending local interests providing items required for local 
cooperation. 
16-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Local cooperation. Local interests must provide 
without cost to the United States all lands, easements 
and rights-of-way necessary for construction, and all 
alterations and relocations of existing buildings, 
utilities, bridges (except railroad bridges), sewers, 
pipelines, and any other existing improvements; hold the 
United States free from damages due to the construction 
work, operate and maintain all features after completion 
of the project. 
Operations during fiscal year. Recommended for 
deauthorization H.R. 3678, 98th Congress, 1st Session, 
August 23, 1983. 
11. ELM FORK FLOODWAY, TX 
Location. The project is located in Dallas and Denton 
Counties, Texas. A portion of the improvement will be in 
and adjacent to the Cities of Dallas, Irving and Farmers 
Branch, Texas. 
Existing project. Improvement of the Elm Fork of the 
Trinity River from the mouth to Lewisville Dam and 
along Denton Creek, a tributary of the Elm Fork to 
Grapevine Dam. The plan of improvement provides for 
enlargement and realignment of about 22 miles of the 
Elm Fork, enlargement and realignment of about 20 
miles of tributary channels, construction of about 39 
miles of new levee, rehabilitation of about 2 miles of 
existing levees, modification of 14 street and highway 
bridges, 4 railroad bridges and alteration of utilities. 
Estimated Federal cost of these modifications is 
$60,700,000, and non-Federal estimated cost is 
$88,600,000, a total of $149,300,000 (Oct. 1, 1983, base 
price). 
Local cooperation. Local interests are required to 
provide (without cost to the Federal Government) except 
for the main channel thereof, all lands, easements, 
utilities and bridge relocations (except railroad bridges) 
necessary for construction and operation of the project. 
Assurances were signed March 20, 1969 by the Trinity 
River Authority, a State agency, that they would provide 
items required of local interests. 
Operations during fiscal year. Preconstruction 
planning was suspended in 1973. Further studies have 
been delayed until a definite plan has been accepted by 
local interests. 
12. FERRELLS BRIDGE DAM-LAKE 
O' THE PINES, TX 
Location. On Cypress Creek in Marion, Harrison, 
Upshur, Morris, Camp, and Titus Counties, Texas, 8 
miles west of Jefferson, Texas. 
Existing project. An earth-fill dam 10,600 feet long 
and 77 feet high includes a 200-foot spillway with a 
capacity of 68,200 cubic feet per second. Reservoir 
controls runoff from 850 square miles of drainage area, 
and has a gross storage capacity of 842,100 acre-feet, 
including 587,200 acre-feet flood control storage, 3,800 
acre-feet conservation storage, and 251,100 acre-feet for 
municipal and industrial water supply. Reservoir 
extends 28 miles upstream. Project affords substantial 
flood protection of Cypress Creek Valley from damsite to 
confluence with Red River and, together with operation 
of other reservoirs proposed in Red River Basin, will 
provide flood protection along main stem of Red River 
below Denison Dam. Construction commenced in 
January 1955 and was completed in June 1960. 
Estimated Federal cost of project is $17,231,700 (Oct. 1, 
1983, base price), including $4,349,200 for Code 711 and 
$399,739 accelerated Public Works fund. 
Local cooperation. None required. 
Operations during fiscal year. Routine operation 
and maintenance continued. Recreation facilities under 
Code 710 regular remain. 
Benefits accrued to Ferrells Bridge Dam-Lake O' The 
Pines project: Accumulated damages prevented through 
FY 1983 were $6,139,000. 
This project transferred to the Fort Worth District as of 
the end of FY 1979. 
13. GRAND PRAIRIE, TX, SANITARY 
LANDFILL 
Location. The project is located at a bend of the West 
Fork of the Trinity River, Texas, approximately 19,500 
feet upstream of the confluence of the West Fork and Elm 
Fork of the Trinity River. This bend in the river is 
adjacent and north of the city of Grand Prairie sanitary 
landfill which lies within Dallas County and is located in 
northeast Grand Prairie. 
Existing project. The project provides for the 
construction of a cutoff channel which will eliminate an 
oxbow in the river, and prevent future damage to the 
city's sanitary landfill. The cutoff channel will have a 
bottom width of 30 feet with side slopes of 1 vertical to 3 
horizontal. Excavated material from the cutoff channel 
will be used to plug each end of the oxbow and to restore 
the damaged levee at the sanitary landfill. Culverts 
placed through the plugs will allow for minor flows 
through the oxbow thus maintaining the water quality. 
The total Federal and non-Federal cost of the project is 
$595,000 (Oct. 1, 1983, base price). 
Local cooperation. In accordance with Section 14 of 
the Flood Control Act of 1946 as amended, the city of 
Grand Prairie is required to assume full responsibility 
for all project costs in excess of the Federal cost 
limitation of $250,000. In addition, the city is required to 
provide without cost to the United States all lands, 
easements, and rights-of-way necessary for construction 
and maintenance; bear the cost of all alteration and 
relocations of utilities, storm drains, roads, highway 
bridges, and community services; hold and save the 
United States free from damages due to construction 
work; operate and maintain all works after completion 
and prevent any obstruction or encroachment that would 
reduce the flow capacity of the project; publicize and 
notify all interested parties that the project will not 
provide protection from the occurrence of storms greater 
than the project design flood; comply with Public Law 
91-646, approved January 2, 1971, and with the 
requirements of Section 221, Public Law 91,611, 
approved December 31, 1970, as amended. 
16-6

FORT WORTH TEXAS DISTRICT 
Operation during fiscal year. Contract for Channel 
Realignment and Fence Restoration at Sanitary Landfill 
was awarded September 29, 1983. 
14. GRAPEVINE LAKE, TX 
Location. Dam is in Tarrant County, Texas, on 
Denton Creek, 11.7 river miles upstream from its 
confluence with Elm Fork of Trinity River and about 20 
miles northwest of City of Dallas, Texas. 
Existing project. For description of completed 
improvement and authorizing act, see Annual Report for 
1962. Estimated cost of project is $18,896,000, including 
$2,040,000 contributed by local interests. Construction 
of project was started December 1947 and ready for 
beneficial use in July 1952. 
Local cooperation. A contract with Dallas County 
Park Cities Water Control and Improvement District No. 
2 for 50,000 acre-feet of water supply storage was 
approved by Secretary of the Army on March 21, 1955. 
Park Cities paid the required $607,000. A contract with 
City of Dallas for 85,000 acre-feet of water supply storage 
was approved by Secretary of the Army on March 17, 
1954. Dallas paid the required $1,433,026. A contract 
with City of Grapevine, Texas, for 1,250 acre-feet of 
water supply storage was approved by Secretary of the 
Army on September 14, 1953, at an estimated cost of 
$22,654. A contract for Interim Use of Navigation 
Storage with city of Grapevine was approved by 
Secretary of the Army on February 27, 1981, at an 
estimated cost of $684,000. To date, $57,058 has been 
paid. Above contracts include payment of operation and 
maintenance costs as follows: Dallas County Park Cities 
Water Control and Improvement District No. 2, a pro 
rata part of the actual annual cost, which part to be not 
less than $2,000 nor more than $3,000; Dallas, 9.2 
percent of actual annual cost; and Grapevine, its pro rata 
part of actual annual cost (estimated at $79.55 annually 
and included in total annual payment). Following 
operation and maintenance payments have been made: 
Park Cities $93,939, Dallas $411,894, and Grapevine 
$36,654. 
Operations during fiscal year. A contract for 
modification of Embankment and Spillway was awarded 
September 30, 1983. The proposed plan of improvement 
provides for spillway modification by construction of 
spillway chute and stilling basin and a berm on the 
downstream side of the main embankment. Also, 
contracts for Relocation, Rearrange or Alter City Streets 
awarded September 13, 1983; Repair of Outlet Works 
and Maintenance Painting (Gates) awarded August 8, 
1983; and Park Road Paving awarded August 25, 1983. 
Recreation facilities under Code 710 remain. 
Benefits accrued to system comprised of Lewisville 
Lake, Grapevine Lake and Dallas Floodway: 
Accumulated flood damages prevented through FY 1983 
were $801,008,400. 
15. GREENVILLE, TX 
Location. In Greenville, Hunt County, Texas, on Long 
Branch of the Sabine River. 
Existing project. Provides for realignment and 
enlargement of 3.34 miles of improved channel along 
Long Branch. Estimated Federal cost is $910,000, and 
estimated cost to local interests was $320,000, a total of 
$1,230,000. Existing project was authorized by the 
Rivers and Harbors Act of 1970. 
Local cooperation. Local interests must provide 
without cost to the United States all lands, easements 
and rights-of-way necessary for construction, and all 
alterations and relocations of existing buildings, 
utilities, bridges (except railroad), sewers, pipelines and 
any other existing improvements; hold the United States 
free from damages due to construction work; and operate 
and maintain all features after completion of the project. 
Operations during fiscal year. All work is complete. 
Recreation facilities remain. 
16. HORDS CREEK LAKE, TX 
Location. On Hords Creek, a tributary of Pecan 
Bayou, about 13.5 miles west of Coleman, Texas, and 
about 27.8 miles upstream from mouth of Hords Creek. 
(See Geological Survey sheets, Grosvenor and Zephyr, 
scale 1:62,500.) 
Existing project. For description of completed 
improvement and authorizing acts see Annual Report for 
1962. Estimated cost of project is $4,337,000 including 
$105,000 contributed by local interests. Construction of 
project was started January 1947 and completed for 
beneficial use in April 1948. 
Local cooperation. Fully complied with. 
Operations during fiscal year. Routine operation 
and maintenance continued. Recreation facilities under 
Code 710 remain. 
Benefits accrued to Hords Creek project: Accumulated 
flood damages prevented through FY 1983 were 
$937,200. 
17. JOE POOL LAKE, TX 
(formerly Lakeview Lake) 
Location. Dam site is located at River Mile 11.2 on 
Mountain Creek, a right bank tributary of the West Fork 
of the Trinity River, and is adjacent to the city limits of 
Grand Prairie, Dallas County, Texas, which is one of the 
rapid growing cities in the Dallas-Fort Worth 
Metropolitan area. 
Existing project. The project provides for 
construction of an earthfill dam with a maximum height 
of 108.5 feet above the streambed and a total length of 
24,200 feet, including 50-foot uncontrolled ogee type 
spillway, which will control 232 square miles of drainage 
area. The reservoir will have a total controlled storage of 
304,000 acre-feet and a water surface area of 10,940 
acres at the top of the flood control pool and 7,470 acres at 
the top of the conservation pool. The total storage 
includes 123,100 acre-feet for flood control, 142,900 acrefeet 
for conservation and 38,000 acre-feet for sediment 
reserve. Estimated cost of the project is $195,800,000 
(Oct. 1, 1983, base price) including $8,800,000 non- 
Federal first cost. Project is a unit in the general 
comprehensive plan for development and control of the 
water resources of the Trinity River basin. 
16-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Local cooperation. The Water Supply Act of 1958 as 
amended, and the Federal Water Project Recreation Act 
of 1965 apply. Contracts for water supply storage and 
recreation with the Trinity River Authority were 
approved by the Acting Secretary of the Army, June 15, 
1977. The recreation contract with Trinity Valley 
Authority was modified March 28, 1979, to allow the 
Corps to participate with the State of Texas and 
approved by the Assistant Secretary of the Army March 
21, 1980. Recreation development contract with the 
State of Texas was approved by the Assistant Secretary 
of the Army March 21, 1980. Reimbursement is 
currently estimated at $47,150,000 for supply and 
$11,206,000 for recreation (excluding future recreation 
facilities) for a total of $58,356,000 exclusive of interest. 
Operations during fiscal year. The project has been 
under construction since FY 1975 and through FY 1983 
is approximately 62 percent complete overall. The costreimbursable 
contract for relocation of TP&L Trans. 
Lines was awarded May 2, 1983, and contract for 
Boundary Fencing Pt II was awarded April 13, 1983. 
Land Acquisition and Engineering and Design continue. 
Public Law 97-400, H.R. 7377, 97th Congress, effective 
December 31, 1982, changed the name of Lakeview Lake 
to Joe Pool Lake. 
18. LAKE BROWNWOOD 
MODIFICATION, TX 
Location. The dam will be located at River Mile 57 on 
Pecan Bayou, a tributary of the Colorado River, eight 
miles north of Brownwood, Texas. The lake will be 
located in Brown and Coleman counties. 
Existing project. The project will insure the safety of 
the existing non-Federal Lake Brownwood and preserve 
its flood control, water supply, and related values. 
Modification measures consist of a new embankment 130 
feet high and 1,870 feet long, new outlet works, and 
erosion control measures in the spillway channel. The 
total controlled storage of the existing lake is 118,900 
acre-feet including 85,900 acre-feet for water supply and 
33,000 acre-feet for sediment reserve. Storage capacity 
will not be altered by this project. The modification 
project was authorized by the Flood Control Act of 1968 
(P.L. 90-483). Estimated cost of project is $29,480,000 
including $20,000,000 non-Federal cost. 
Local cooperation. Water Supply Act of 1958 and 
Section 221 of the Flood Control Act of 1970 apply. 
Brown County Water Improvement No. 1 is the local 
sponsor. 
Operations during fiscal year. Preconstruction 
planning suspended. Recommended for deauthorization 
H.R. 3678, 98th Congress, 1st Session, August 23, 1983. 
19. LAVON LAKE, TX 
Location. Dam is in Collin County, Texas, on East 
Fork of Trinity River 55.9 miles above its confluence 
with Trinity River and about 22 miles northeast of 
Dallas, Texas. 
Existing project. For description of completed 
improvement and authorizing acts see Annual Report for 
1962. Estimated cost of project is $15,470,000. For 
information concerning Lavon Lake Modification and 
East Fork Channel Improvement project, see individual 
project. Construction of project was started January 1948 
and ready for beneficial use in September 1953. Project is 
complete. See following section for Lavon Lake 
Modification and East Fork Channel Improvement 
authorized by Flood Control Act of 1962. 
Local cooperation. Section 2, Flood Control Act of 
1938, applies. A contract with North Texas Municipal 
Water District for water supply storage, including cost of 
intake structure, was approved by Secretary of the Army 
July 8, 1954, at an estimated cost of $1,405,753. Contract 
was revised in 1973 and final revised contract amount is 
$1,445,261.67. To date the district has paid $583,587. 
Under the contract North Texas Municipal Water 
District must pay annually 13.6 percent of actual annual 
cost of operation and maintenance. To date the district 
has paid $448,948. 
Operations during fiscal year. Routine operation 
and maintenance continued. 
Benefits accrued to Lavon project: Accumulated flood 
damages prevented through FY 1983 were $81,704,300. 
20. LAVON LAKE MODIFICATION 
AND EAST FORK CHANNEL 
IMPROVEMENT, TX 
Location. Existing dam is in Collin County, Texas, on 
East Fork of Trinity River, 55.9 miles above its 
confluence with Trinity River and about 22 miles 
northeast of Dallas, Texas. Channel improvement of 
East Fork extends from its mouth to River Mile 31.8. 
Existing project. Reservoir modification provides for 
raising top of existing dam from elevation 502.0 to 514.0 
and lengthening existing dam from about 9,499 feet to 
about 19,493 feet; modification of existing concrete 
spillway structure; enlargement of existing reservoir 
area, involving acquisition of additional rights-of-way; 
relocation and alteration of highways, county roads, 
railroads and utilities; and provision of recreational 
facilities. East Fork Channel and floodway 
improvements consist of 25 miles of channel 
enlargement and straightening of the East Fork between 
River Mile 0.0 and 31.8; replacement of inadequate 
levee-sluice structures; rehabilitation of existing levees; 
acquisition and clearing of land areas as required for 
rights-of-way along improved channel and existing 
levees; alteration of existing railroad, highway and 
county road bridges crossing the improved channel as 
well as relocation of existing utility lines; and 
strengthening and raising about 202,400 linear feet of 
levees of seven existing levee districts. Reservoir will 
provide a total storage capacity of 748,200 acre-feet 
(275,600 are for flood control, 380,000 for water supply 
storage, and 92,600 for sedimentation reserve.) 
Estimated Federal cost of the modification and 
improvement is $69,750,000 and estimated cost to local 
interests is $220,000 for lands and damages and 
relocations, a total of $69,970,000. Construction was 
initiated in May 1970 and ready for beneficial use in 
December 1975. 
16-8

FORT WORTH TEXAS DISTRICT 
Local cooperation. Local interests must reimburse 
the Federal Government for costs allocated to increased 
water supply storage under the terms of the Water 
Supply Act of 1958. The North Texas Municipal Water 
District has contracted for 43 percent of the water supply 
(approved September 22, 1967, by the Secretary of the 
Army) and to date $1,082,640 has been paid. North Texas 
Municipal Water Supply District has submitted 
assurance to contract for the 57 percent for future water 
supply. Reimbursement is currently estimated at 
$37,511,047. 
Levee Districts 4 and 5, which comprise the lower 10 
miles of the East Fork Channel, entered into agreements 
as required by Section 221 of the Flood Control Act of 
1970 on January 28, 1972 and have furnished all 
necessary construction easements. 
Levee Districts 6,8, 10, 13, and 15, which comprise the 
upper 15 miles of the East Fork Channel, have declined 
to provide the necessary assurances. On December 8, 
1972, this portion of the project was reclassified from 
"active" to "inactive" category. 
Operations during fiscal year. A construction 
contract for Levee Improvement, Increment I, East Fork 
was awarded May 1, 1981, and continues. Improvement 
of the lower ten miles of the East Fork Channel and 
Levees and total project are 99 percent complete. 
21. LEWISVILLE DAM, TX 
Location. In Denton County, Texas, on Elm Fork of 
Trinity River 30 river miles above its confluence with 
Trinity River and about 22 miles northwest of City of 
Dallas, Texas at a site downstream from old Garza Dam. 
Existing project. For description of completed 
improvement and authorizing acts see Annual Report for 
1962. Estimated cost of project is $25,902,000 (Oct. 1, 
1983, base price), including $3,677,000 contributed by 
local interests. Construction of project was started 
November 1948 and ready for beneficial use in 
November 1954. 
Local cooperation. A contract with City of Dallas for 
415,000 acre-feet of water supply storage land rights and 
interests to Garza Dam and Reservoir was approved by 
the Secretary of the Army on July 16, 1953. Local 
contributions have been made in full. A contract with 
city of Denton, Texas, for remaining 21,000 acre-feet of 
water supply storage was approved by the Secretary of 
the Army on May 20, 1954, with an estimated cost of 
$250,064. To date Denton has paid $250,064. Under 
above contracts, cities of Dallas and Denton must pay 
annually 21.9 and 1 percent, respectively, of actual 
annual cost of operation and maintenance. To date 
Dallas has paid $2,287,774 and Denton $99,391. 
Operations during fiscal year. Major rehabilitation 
of the existing embankment continued. Rehabilitation 
consists of upstream and downstream stability berms. 
Estimated Federal cost is $5,330,000. Contract for 
Rehabilitation of Upper Slopes was awarded June 21, 
1983. Recreation facilities under Code 710 remain. 
Benefits accrued to system comprised of Lewisville 
Lake, Grapevine Lake, and Dallas Floodway: 
Accumulated flood damages prevented through FY 1983 
were $801,008,400. 
22. MILLICAN LAKE, TX 
Location. Dam is on the Navasota River at mile 24.1, 
approximately 7 miles north of Navasota, Texas in 
Grimes and Brazos Counties, Texas. This project would 
be the first of a two-stage development consisting of 
Millican and Navasota Dams, both of which would be 
units in the overall plan of improvement for the Brazos 
River Basin. 
Existing Project. The project provides for 
construction of a concrete and earthfill dam 25,300 feet 
long including a 472-foot gate-controlled spillway, rising 
83 feet above the streambed. Without Navasota Lake in 
operation, the top of flood control pool (elevation 234.0) 
would provide 1,557,400 acre-feet of storage space and 
cover a surface area of 66,000 acres. There would be 
784,800 acre-feet of flood control; 680,200 acre-feet for 
water supply (surface area 42,400 acres), and 92,400 
acre-feet for sediment reserve. 
With Navasota Lake in operation, the top of flood 
control elevation and total storage would remain the 
same. The flood control pool would be 359,600 acre-feet, 
water supply storage would be 1,125,800 acre-feet 
(surface area 55,500 acres) and sediment reserve would 
be 72,000 acre-feet. Estimated Federal cost of the project 
is $336,000,000 (Oct. 1, 1983, base price). 
Local cooperation. The Water Supply Act of 1958 as 
amended and the Federal Water Project Recreation Act 
of 1965. By letter dated December 9, 1974, the Brazos 
River Authority stated that they would be the state 
agency to cost share for both water supply and 
recreation. 
Operations during fiscal year. Preconstruction 
planning continued. Overall preconstruction planning 
67 percent complete, Ph. I, GDM and EIS 98 percent 
complete. 
23. NAVARRO MILLS LAKE, TX 
Location. Dam is in Navarro County, Texas, at River 
Mile 63.9 on Richland Creek, a tributary of Trinity 
River, about 16 miles southwest of Corsicana, Texas. 
Existing project. For description of completed 
improvement and authorization acts see Annual Report 
for 1965. Estimated cost of project is $13,154,000 (Oct. 1, 
1983, base price), including $300,000 contributed by 
local interests. Construction started December 1959 and 
project completed for beneficial use March 1963. 
Local cooperation. The Water Supply Act of 1958, as 
amended applies. A formal contract with the Trinity 
River Authority was approved March 3, 1966, by the 
Secretary of the Army at an estimated cost of $2,260,800. 
To date the Authority has paid $544,095 for water supply 
and $551,174 for operation and maintenance. 
Operations during fiscal year. Routine operation 
and maintenance continued. Recreation facilities under 
Code 710 remain. 
Benefits accrued to Navarro Mills project: 
Accumulated flood damages prevented through FY 1983 
were $25,576,000. 
16-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
24. O. C. FISHER DAM 
AND LAKE, TX 
Location. Dam is on North Concho River, a tributary 
of Concho River, about 6.6 miles above mouth of North 
Concho River near city of San Angelo, Texas. (See 
Geological Survey base map, Texas, scale 1:500,000, and 
sheet Wall, scale 1:62,500.) 
Existing project. For description of completed 
improvement and authorizing acts see Annual Report for 
1962. Name was changed from San Angelo Dam and 
Reservoir January 3, 1975 by Public Law 93-634. 
Estimated cost of project is $17,111,000. Construction of 
project was started May 1947 and ready for beneficial use 
February 1952. 
Local cooperation. Section 2, Flood Control Act of 
1938, applies. A water-supply contract with Upper 
Colorado River Authority for water-supply storage in 
reservoir was approved by Secretary of the Army on 
October 11, 1948. The Authority has contributed 
$860,444 toward cost of project and $64,324 toward 
operation and maintenance for a 50-year period. The 
Authority must pay additional consideration of $1 a year 
for useful life of project, beginning January 1, 1965. 
Operations during fiscal year. Regular funds: 
Routing operation and maintenance continued. 
Benefits accrued to O. C. Fisher Dam and Lake project: 
Accumulated flood damages prevented through FY 1983 
were $2,375,600. Recreation facilities under Code 710 
remain. 
25. PROCTOR LAKE, TX 
Location. Dam is at River Mile 238.9 on Leon River, a 
tributary of Brazos River, about 8 miles northeast of 
Comanche in Comanche County, Texas. 
Existing project. For description of completed 
improvement and authoriation act see Annual Report of 
1969. Estimated cost of project is $16,249,000. 
Construction of project was started July 1960 and 
completed for beneficial use 1963. 
Local cooperation. The Water Supply Act of 1958 
applies. A formal contract with the Brazos River 
Authority, a State agency, was approved by Secretary of 
the Army, July 1, 1960, and was modified and was 
approved May 9, 1966, at an estimated cost of 
$1,707,900. To date the Authority has paid $253,116 for 
water supply and $204,211 for operation and 
maintenance. 
Operations during fiscal year. Routine operation 
and maintenance were continued. Recreation facilities 
under Code 710 remain. 
Benefits accrued to Proctor project: Accumulated flood 
damages prevented through FY 1983 were $5,166,700. 
26. RAY ROBERTS LAKE, TX 
(formerly Aubrey Lake) 
Location. Damsite is located at River Mile 60.0 on the 
Elm Fork of the Trinity River, Denton County, between 
Sanger and Aubrey, Texas and 30 miles upstream from 
Lewisville Dam. 
Existing project. The plan of improvement provides 
for construction of an earthfilled dam with a maximum 
height of 141 feet above the streambed, a length of 15,250 
feet including an uncontrolled broadcrested spillway 100 
feet long, controlling 682 square miles of drainage area. 
The lake will have a total controlled storage of 1,064,600 
acre-feet. with a water surface area of 36,900 acres. The 
total storage includes 260,800 acre-feet for flood control, 
749,200 acre-feet for water supply, and 54,600 acre-feet 
for sediment reserve. Estimated Federal cost of the 
project is $269,000,000 (Oct. 1, 1983, base price). Public 
Law 96-384, 96th Congress, H.R. 8024, effective January 
4, 1981, changed the name of Aubrey Lake to Ray 
Roberts Lake. 
Local cooperation. The Water Supply Act of 1958 as 
amended and the Federal Water Project Recreation Act 
of 1965 and Section 221, Flood Control Act of 1970 apply. 
Contracts with the cities of Dallas and Denton, Texas, for 
water supply storage and recreation were approved by 
the Secretary of the Army September 16, 1980. 
Operations during fiscal year. The project is about 
23 percent complete overall. Acquisition of real estate 
continues. FY 1983 funds were used to continue 
boundary monumentation, construction of embankment, 
spillway and outlet works and cultural resources 
mitigation, award contracts for Farm to Market Roads 
455 Pts I and II and 922, Enserch and Arco Pipelines. At 
the request of the city of Denton and the approval of the 
Secretary of the Army, the penstock was added to the 
embankment as a minimum facility for future 
hydropower. Engineering and design continue. 
27. SAN ANTONIO CHANNEL 
IMPROVEMENT, TX 
Location. Floodway is in city of San Antonio, Bexar 
County, Texas, on San Antonio River and San Pedro, 
Apache, Alazan, Martinez Creeks, and Espada Acequia 
Aqueduct located in vicinity of Six Mile Creek. 
Existing project. Provides for clearing, widening, 
deepening, and straightening about 31 miles of river and 
creek channels to carry standard project flood 
discharges, construction of channel walls, and paving, 
conduit, and construction and alteration of railroad 
bridges. Estimated Federal cost of these modifications is 
$82,000,000 (Oct. 1, 1983, base price), and estimated cost 
to local interests is $65,700,000 which includes 
$2,200,000 cash contributions and $63,500,000 for lands, 
damages, and construction, a total of $147,700,000. 
Existing project was authorized by 1954 Flood Control 
Act. Latest published map is in project document. The 
Water Resources Act of 1976 added authorization to the 
existing project for construction of flood control measures 
needed to preserve and protect the Espada Acequia 
Aqueduct located in the vicinity of Six Mile Creek. 
Construction was started in October 1957 and the project 
is about 43 percent complete. 
Local cooperation. Local interests must furnish 
lands and rights-of-way for construction, including 
purchase and removal of buildings, relocation or 
reconstruction of bridges (exclusive of railway bridges), 
channel dams where applicable, and utility lines; hold 
16-10

FORT WORTH TEXAS DISTRICT 
the United States free from damages; maintain and 
operate all works after completion; and provide a cash 
contribution for enhancement benefits of 2.65 percent of 
actual Federal construction cost. San Antonio River 
Authority furnished assurances that it will comply with 
all requirements of local cooperation. These assurances 
were accepted by the District Engineer on April 15, 1957. 
To date $999,525 has been contributed by San Antonio 
River Authority. In addition, $30,000 has been 
contributed and accepted, under the authority of Civil 
Functions Appropriations Act of 1958, for vehicular 
crossings over the San Antonio channel. 
Operations during fiscal year. Construction 
contract for Channel Improvement, Schedule I, Unit 
8-3-2 was awarded September 14,1981, and a contract for 
Channel Paving, Unit 8-3-1, Schedule II was awarded 
September 28, 1981. A contract for seepage and erosion 
control - 6 mi Creek diversion canal awarded July 28, 
1982, are physically complete. Engineering and design 
studies continued. 
Benefits accrued to San Antonio project: Accumulated 
damages prevented through FY 1983 were $44,055,500. 
28. SAN GABRIEL RIVER, TX 
Location. System of three reservoirs in Williamson 
County in the central portion of Brazos River Basin. 
Granger Dam at River Mile 31.9 on San Gabriel River, 
about 7 miles east of Granger, Texas; North San Gabriel 
Dam at River Mile 4.3 on North Fork of San Gabriel 
River, about 3.5 miles northwest of Georgetown, Texas; 
and South Fork Dam at River Mile 4.7 on South Fork of 
San Gabriel River, about 3 miles southwest of 
Georgetown, Texas. 
Existing project. Granger Lake was authorized by 
1954 Flood Control Act, and North (North San Gabriel 
Dam and Lake Georgetown) and South Fork Lakes were 
authorized by 1962 Flood Control Act. Estimated total 
Federal cost of project is $155,000,000 (Oct. 1, 1983, base 
price). Plan of improvement provides for the following: 
Granger: An earthfilled dam 16,320 feet long, including 
spillway with maximum height of 115 feet above 
streambed, which controls 709 square miles of drainage 
area. Reservoir provides a total storage capacity of 
244,200 acre-feet, of which 162,200 acre-feet are for flood 
control, 37,900 acre-feet for water supply storage, and 
44,100 acre-feet for sediment reserve. Estimated cost of 
project is $61,845,000. North San Gabriel Dam: A rockfill dam 6,700 feet long, including spillway with 
maximum height of 164 feet above streambed, which 
controls 246 square miles of drainage area. Reservoir 
provides a total storage capacity of 130,800 acre-feet of 
which 87,600 acre-feet are for flood control, 29,200 acrefeet 
for water supply storage, and 14,000 acre-feet for 
sediment reserve. Estimated cost of project is 
$38,780,000. South Fork: A rockfill dam 5,620 feet long, 
including spillway with maximum height of 152 feet 
above streambed, which controls 123 square miles of 
drainage area. Reservoir provides a total storage 
capacity of 82,600 acre-feet (45,700 for flood control, 
28,900 for water supply storage, and 8,000 for sediment 
reserve). Estimated cost of project is $54,375,000. Public 
Law 96-575, 96th Congress, H.R. 4941 effective January 
4, 1981, changed the name of North Fork Lake to North 
San Gabriel Dam and Lake Georgetown. 
Local cooperation. Construction is. subject to 
condition that local interests reimburse the Federal 
Government for costs allocated to water supply at 
Granger, Lake Georgetown, and South Fork Lakes. 
Reimbursement currently estimated at $13,303,000 for 
Granger, $6,303,000 for Lake Georgetown, and 
$15,988,000 for South Fork, for a total of $35,594,000 
exclusive of interest. Brazos River Authority, a State 
agency, is the local interests' sponsor of project, and by 
letter dated April 18, 1966, indicated its acceptance of 
the proposed plan of development and its willingness to 
pay for the costs allocated to water supply in each 
reservoir in the ultimate plan. Such water supply 
assurances for Granger and Lake Georgetown Lakes 
were approved May 24, 1968 as satisfactory in 
accordance with requirements of the Water Supply Act of 
1958, as amended. Contract negotiations for South Fork 
Lake will be deferred until the need for water supply 
develops and the reservoir is scheduled for construction. 
Operations during fiscal year. Through 1983 all 
work has been completed. Deliberate impoundment of 
water commenced at Granger and Lake Georgetown 
Lakes on January 21, 1980 and March 3, 1980, 
respectively. In FY 1982, studies on South Fork Lake 
were resumed in preparation of General Design 
Memorandum to provide reaffirmation prior to 
construction. This reaffirmation is currently scheduled 
for submission in July 1984 and to be fully coordinated 
by April 1985. 
Benefits accrued to project consisting of Granger and 
Lake Georgetown: Accumulated damages prevented 
through FY 1983 were $10,186,700. 
29. SOMERVILLE LAKE, TX 
Location. Dam is on Yegua Creek 20 miles upstream 
from its confluence with Brazos River and about 2 miles 
south of Somerville, Texas. 
Existing project. For description of completed 
improvements and authorization act see Annual Report 
of 1969. Estimated cost of project is $30,227,000. 
Construction started in June 1962 and project was ready 
for beneficial use in January 1967. 
Local cooperation. The Water Supply Act of 1958, as 
amended, applies. A contract with the Brazos River 
Authority, a State agency, for water supply storage 
approved May 10, 1962, by the Secretary of the Army, at 
an estimated cost of $4,871,815. Also under the contract, 
the authority must pay annually 28.655 percent of the 
actual annual cost of operation and maintenance. 
Operations during fiscal year. Routine operation 
and maintenance continued. Construction of 
recreationwasfacilities under a contract with the State of 
Texas, under Code 710 cost-sharing continued. 
Recreation facilities under Code 710 remain. 
Benefits accrued to Somerville project: Accumulated 
damages prevented through FY 1983 were $30,436,700. 
16-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
30. STILLHOUSE HOLLOW DAM, TX 
Location. Dam is on Lampasas River 16 miles 
upstream from its confluence with Little River, a 
tributary of the Brazos River, and about 5 miles 
southwest of Belton, Texas. 
Existing project. For description of completed 
improvements and authorization act see Annual Report 
of 1969. Estimated cost of project is $23,670,000. 
Construction was initiated in July 1962 and the project 
was ready for beneficial use in February 1968. 
Local cooperation. The Water Supply Act of 1958 
applies. A contract with the Brazos River Authority, a 
State agency, for water supply storage was approved 
April 13, 1962, by the Secretary of the Army, at an 
estimated cost of $6,912,430. To date the Authority has 
paid $793,165. Also under the contract the Authority 
must pay annually 27.748 percent of the actual annual 
cost of operation and maintenance. To date the Authority 
has paid $301,270. 
Operations during fiscal year. Routine operation 
and maintenance continued. Recreation facilities under 
Code 710 regular were constructed. 
Benefits accrued to Stillhouse Hollow Project: 
Accumulated estimate of flood damages prevented 
through FY 1983 is $20,596,800. 
31. THREE RIVERS, TX 
Location. The project is located in and adjacent to the 
city of Three Rivers, Live Oak County, Texas, midway 
between San Antonio and Corpus Christi, Texas, on the 
left bank of the Frio River, two miles below the mouth of 
the Atascosa River and two miles above the confluence 
with the Nueces River. 
Existing project. The local flood protection project 
consists of an earthfill levee 4.5 miles in length and 
appurtenant water control measures. The project was 
authorized in 1971 under Section 201 of the 1965 Flood 
Control Act in accordance with the recommendations of 
the Chief of Engineers as contained in House Document 
92-153. Estimated cost of the project is $6,363,000 
including $473,000 non-Federal cost. 
Local cooperation. The City of Three Rivers, Texas, 
gave assurances satisfactory to the Secretary of the 
Army that they will: (a) Provide without cost to the 
United States all lands, easements, rights-of-way, and 
borrow areas necessary for construction, maintenance; 
and operation of the project; (b) Provide without cost to 
the United States all bridge relocations, except railroad 
bridges, and all buildings, structures, and any other 
alterations of existing structures or improvements which 
may be required for construction of the project; (c) Hold 
and save the United States free from damages due to 
construction of the project; (d) Acquire without cost to the 
United States, easements on lands adjacent to the city to 
allow flooding on some lands not now in the flood plain, 
and hold and save the United States free from claims as 
a result of this additional flooding; (e) Provide assurances 
that encroachment on exterior drainage and ponding 
areas will not be permitted without offsetting the 
encroachment by substitute storage or equivalent 
pumping capacity, without cost to the United States; (f) 
Agree to publicize flood plain information in the area 
concerned and to provide this information to zoning and 
other regulatory agencies and public information media 
for their guidance and appropriate action, including 
adoption of such regulations as may be necessary to 
insure compatibility between future developments and 
protection levels provided by the project; and (g) 
Maintain and operate all works after completion in 
accordance with regulations prescribed by the Secretary 
of the Army. The assurances were accepted by the 
Federal Government July 26, 1979. 
Operations during fiscal year. All construction is 
essentially complete. 
32. WACO LAKE, TX 
Location. Dam is on Bosque River, 4.6 river miles 
above its confluence with Brazos River, at City of Waco, 
McLennan County. Texas. 
Existing project. For description of completed 
improvements and authorization act see Annual Report 
of 1969. Estimated cost of project is $50,853,000 
including $250,000 contributed by local interests and 
$2,500,000 other non-Federal cost. Construction was 
started in July 1958, and project was ready for beneficial 
use in February 1965. 
Local cooperation. Section G of the Flood Control Act 
of December 1944 applies. A contract with the Brazos 
River Authority, a State agency, for water supply storage 
and the contract with the City of Waco transferring the 
existing Lake Waco to the Government for their water 
storage, was approved by the Secretary of the Army on 
April 15, 1958. To date the Authority for their portion of 
the water supply storage has paid $1,264,847. Also under 
the contract the Authority and the City must pay 14.706 
and 2.087 percent respectively of the actual cost of 
operation and maintenance. To date the Authority has 
paid $503,119 and the City has paid $83,791. 
Operations during fiscal year. Regular funds: 
Routine operations and maintenance continued. 
Recreation facilities under Code 710 remain. 
Benefits accrued to Waco project: Accumulated 
damages prevented through FY 1983 were $58,731,900. 
33. WHEELER CREEK, GAINSVILLE, 
TX 
Location. Wheeler Creek is a left bank tributary of 
Pecan Creek which, in turn, is a tributary of Elm Fork of 
the Trinity River. Wheeler Creek is located 
approximately 2 miles east of Gainsville, Texas, and 
flows in a northeasterly direction. 
Existing project. The project consists mainly of flush 
clearing the existing creek with some minor excavation 
to straighten the meanders. The excavation will result in 
a trapezoidal grass-lined channel, 20-foot bottom with 1 
on 3 side slopes. The project will extend approximately 
1,500 feet downstream of FM 678 and about 3,550 feet 
upstream of FM 678. Estimated cost of project is 
$235,000 (Oct. 1, 1983, base price), of which $12,000 is a 
16-12

FORT WORTH TEXAS DISTRICT 
a non-Federal cost for acquiring the necessary real 
estate. Construction will begin in November 1983. 
Local cooperation. The project is under the authority 
of the Flood Control Act of 1948 (Public Law 858). The 
city of Gainsville is the local sponsor. 
Operations during fiscal year. Prepared plans and 
specifications, and awarded construction contract for 
Channel Improvemeht September 29, 1983. Completion 
of project is scheduled for May 1984. 
34. WRIGHT PATMAN DAM 
AND LAKE, TX 
Location. On Sulphur River in Cass and Bowie 
Counties, Texas. Dam is 45 miles above mouth of 
Sulphur River, and about 8 miles southwest of 
Texarkana, Texas. 
Existing project. An earth-fill dam 18,500 feet long 
and 100 feet high, including a spillway 200 feet wide and 
outlet works with a capacity of 27,600 cubic feet per 
second. Reservoir controls runoff from 3,400 square 
miles of drainage area, and has a storage capacity of 
2,654,300 acre-feet, of which 145,300 acre-feet are for 
conservation and remainder for flood control. Estimated 
cost for work (October 1978) is $51,945,000 which 
includes $5,449,100 Code 711, $399,939 accelerated 
public works funds, and $13,138,004 to be reimbursed by 
local interests, over a period not to exceed 50 years, for 
water supply storage, and including $2,092,040 for pro 
rata share of original reservoir cost. Construction was 
initiated in August 1948 and completed in March 1962, 
except real estate activities, construction under Code 
711, and conversion of 120,000 acre-feet to water supply 
storage after completion of Cooper Reservoir. 
Local cooperation. None required. 
Operations during fiscal year. Routine operation 
and maintenance continued. Recreation facilities under 
Code 710 remain. 
Benefits accrued to Wright Patman project: 
Accumulated damages prevented through FY 1983 were 
$13,697,000. 
This project transferred to the Fort Worth District as of 
the end of FY 1979. 
35. ZACATE CREEK CHANNEL 
IMPROVEMENT, TX 
Location. The project is located on Zacate Creek in the 
Rio Grande River Basin at Laredo, Webb County, Texas, 
approximately 150 miles south of San Antonio, Texas. 
Existing project. Provides for realignment and 
enlargement of approximately 3.9 miles of channel 
improvement from Corpus Christi-Washington, up to 
Canal Street. New bridges were constructed at Clark 
Park, Saunders-LaFayette and the Missouri-Pacific 
Railroad. Bridge modifications were made at Corpus 
Christi-Washington, Sanchez-Gustavus and the Texas- 
Mexican Railroad. Estimated Federal cost of this project 
is $2,882,000, and estimated cost to local interests is 
$1,300,000. The project was authorized under Section 
205, Projects Not Specifically Authorized by Congress. 
Local cooperation. Local interests must provide 
without cost to the United States all lands, easements, 
and rights-of-way necessary for construction of all 
alterations and relocations of existing buildings, 
utilities, bridges (exclusive of railroad bridges), sewers, 
pipelines, and any other existing improvements; hold the 
United States free from damages due to the construction 
work, operate and maintain all features after completion 
of the project. 
Operations during fiscal year. Construction 
initiated in August 1980, and the project is complete. 
36. INSPECTION OF COMPLETED 
. FLOOD CONTROL PROJECTS 
Inspection of completed local flood protection projects is 
made periodically in compliance with section 208.10, of 
title 33, Code of Federal Regulations, which contains 
regulations for operation and maintenance of local floodprotection 
works approved by Secretary of the Army in 
accordance with authority in section 3. Flood Control Act 
of June 22, 1936. See Table 16-D for inspections made 
this fiscal year. 
Inspection costs for FY from regular funds for 
maintenance were $57,000. Total costs to September 30, 
1983 were $485,583. 
37. SCHEDULING FLOOD CONTROL 
RESERVOIR OPERATIONS 
In accordance with Flood Control Act of 1944 
expenditures were made for scheduling flood control 
reservoir operations and preparation of reservoir 
regulation manual for Marshall Ford Dam, on the 
Colorado River, near City of Austin, Texas, and for 
preparation of reservoir regulation manual for Twin 
Buttes Dam, on Middle and South Concho Rivers near 
City of San Angelo, Texas. Marshall Ford Dam was 
authorized by 1937 River and Harbor Act. Project was 
constructed jointly by Bureau of Reclamation and Lower 
Colorado River Authority and was completed during FY 
1942. Twin Buttes Reservoir was authorized for 
construction by Department of Interior by Public Law 
152, 85th Congress. Construction was initiated in June 
1960; closure of dam started in June 1962; deliberate 
impoundment was started January 23, 1963. 
Accumulated damages prevented by Marshall Ford 
Reservoir through FY 1983 were $178,550,600 and by 
Twin Buttes through FY 1983 were $417,500. Twin 
Buttes Reservoir consists of two separate pools, one on 
South Concho River and the other on Middle Concho 
River and Spring Creek. Equalizing channel between 
these two pools is at elevation 1925.0. Costs for fiscal 
year from regular funds for operation of both reservoirs 
were $78,352. 
38. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
(See Table 16-C.) 
16-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
39. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
(See Table 16-E.) 
Flood control activities pursuant to section 205, Public 
Law 858, 80th Congress, as amended (preauthorization); 
emergency streambank protection under section 14, 
Public Law 526, 79th Congress, as amended. 
Emergency flood control, hurricane-flood, and shore 
protection activities (Public Law 99, 84th Congress, and 
antecedent legislation). 
Fiscal year costs were $154,801 for disaster 
preparedness, $38,355 for advance measures, flood alerts 
$40,699, and levee repair $493,637. 
Multi-Purpose Projects Including Power 
40. BELTON LAKE MODIFICATION, 
TX 
Location. For location of completed dam see Belton 
Lake, Texas in this chapter. 
Existing project. The modification of Belton Lake to 
provide installation of hydroelectric power generating 
facilities was authorized by the Flood Control Act of 1954 
(H.Doc. 535, 81st Cong., 2nd Sess.). The plan of 
improvement provides for reallocation of the gross 
storage capacity in Belton Lake to provide a power pool 
and the installation of hydroelectric power generating 
facilities. 
Operations during fiscal year. The modification is 
classified as deferred until the Chief of Engineers 
determines it is advisable 
41. DAM A LAKE, TX 
Location. The dam would be located approximately 18 
miles west of Jasper and about 4 miles west of Horger, 
Texas. 
Existing project. The project is designed to be used as 
a run-of-river plant for the generation of power and to reregulate 
power surges from the proposed Rockland Lake. 
The last estimate of project cost was $3,220,000 in 1954. 
For last full report see Annual Report of 1952. 
Operations during fiscal year. The project is 
classified as deferred. 
42. ROCKLAND LAKE, TX 
Location. The dam would be located approximately 3 
miles west of Rockland, Texas, on the Neches River. 
Existing project. The project would control floods, 
generate hydroelectric power, and provide water supply 
for various uses. The last estimate of project cost was 
$46,300,000 in 1954. For the last full report see Annual 
Report of 1952. 
Operations during fiscal year. The project was 
reclassified to active status December 2, 1982. 
43. SAM RAYBURN DAM AND 
RESERVOIR, TX 
Location. Dam is on Angelina River 25.2 miles 
upstream from its confluence with Neches River and 
about 10 miles northwest of Jasper, Texas. 
Existing project. For description of completed 
improvements and authorization act see Annual Report 
1969. Estimated cost of project is 168,863,000 including 
$3,000,000 contributed by local interests. Construction 
was started August 1956 and project was ready for 
beneficial use in March 1965. 
Local cooperation. A contract with the Lower Neches 
Valley Authority, a State agency, to contribute 
$3,000,000 toward the first cost and an additional 
$200,000 annually for 50 years after completion of the 
project was approved by the Secretary of the Army on 
January 22, 1957. Contribution of $3,000,000 was made 
in full and annual payments to date of $3,600,000 have 
been made by the Authority. 
A contract with the City of Luikin for water supply 
storage was approved May 27, 1969 by the Secretary of 
the Army at an estimated cost of $525,600. To date the 
City has paid $88,534. Also under the contract the City of 
Lufkin must pay annually 0.692 percent of the annual 
cost of operation and maintenance. To date the City has 
paid $88,314. 
Operations during fiscal year. Continued routine 
operation and maintenance. Recreation facilities under 
Code 710 continued. 
Benefits accrued to Sam Rayburn project: 
Accumulated damages prevented through FY 1983 were 
$66,020,200. 
44. TOWN BLUFF DAM - 
B. A. STEINHAGEN LAKE, TX 
Location. Dam is on Neches River about 12.4 miles 
below mouth of Angelina River, one-half mile north of 
Town Bluff, Texas, and 93 river miles north of 
Beaumont, Texas. 
Existing project. For description of completed 
improvement and authorizing acts see Annual Report for 
1962. Estimated cost of project is $9,888,000, including 
$2 million contribution by local interests. Construction 
started March 1947 and project was ready for beneficial 
use in April 1951. 
Local cooperation. Completed as required. 
Operations during fiscal year. Regular funds: 
Routine operation and maintenance continued. 
Recreation facilities under Code 710 remain. Studies 
began in FY 1982 to determine the feasibility of 
modifying the existing project to incorporate 
hydropower, and continue.1962. 
45. WHITNEY LAKE, TX 
Location Dam is on Brazos River, about 442 miles 
above mouth of river, 5.5 miles southwest of Whitney, 
16-14

FORT WORTH TEXAS DISTRICT 
Texas, and about 38 miles upstream from City of Waco, 
Texas. (See Geological Survey sheets: Waco, Cleburne, 
and Granbury scale 1:125,000, and Whitney, Blum, and 
Morgan scale 1:62,500.) 
Existing project. For description of completed 
improvement and authorizing acts see Annual Report for 
1962. Estimated cost of project is $46,306,000. 
Construction of project was started June 1946 and ready 
for flood control use in December 1951. First power was 
placed on-the-line in June 1953. Raise power pool is 
complete. 
Local cooperation. Section 2, Flood Control Act of 
1938, applies. 
Operations during fiscal year. Continued routine 
operation and maintenance. Recreation facilities under 
Code 710 remain. 
Benefits accrued to Whitney project: Accumulated 
damages prevented throuth FY 1983 were $131,516,200. 
General Investigations 
46. SURVEYS 
Fiscal year costs were $910,255 for flood damage 
prevention studies, $62,603 for coordination with other 
agencies, and $167,897 for preauthorization studies 
Phase I for a total of $1,087,047. 
47. COLLECTION AND STUDY OF 
BASIC DATA 
Work was continued under the Flood Plain 
Management Services on the compilation of information 
on floods and potential flood damages, including 
identification of those areas subject to inundation. Fiscal 
year expenditures for these activities totaled $285,997. 
Fiscal year costs were $4,984 for hydrologic studies. The 
national program of inspection of dams, authorized by 
Public Law 92-367, was continued in FY 1983. 
Expenditures under this program for inventory of dams 
were $721. 
16-15

TABLE 16-A 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
COST AND FINANCIAL STATEMENT 
See 
Section 
in Text Project 
1. Trinity River 
Project, TX 
Includes Channel to 
Liberty, Tennessee 
Colony Lake, and Dallas 
Floodway Extension 
2. Aquilla Lake, TX 
3. Bardwell Lake, TX 
4. Belton Lake, TX 
5. Benbrook Lake, TX 
6. Big Sandy Lake, TX 
7. Boggy Creek, TX 
8. Canyon Lake, TX 
(Federal Funds) 
9. Cooper Lake and 
Channels, TX 
10. Duck Creek Channel 
Improvement, TX 
11. Elm Fork Floodway, 
TX 
12. Ferrells Bridge Dam 
Lake O' The Pines, TX 
13. Grand Prarie, TX 
Landfill 
(Contributed Funds) 
Total Cost To 
FY 80 FY 81 FY 82 FY 83 Sep. 30, 1983 1 
840,000 700,000 500,000 248,000 22,187,866 
516,712 680,184 678,572 94,078 21,869,130 
Funding 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
515,900 
515,502 
2,563 
3,345 
686,700 
828,738 
1,531 
147,789 
487,500 
781,720 
350,000 
311,826 
(-)3,600 
(-)3,600 
585,900 
613,781 
350,000 
677,824 
(-)44,000 
(-)27,550 
666,800 624,600 
704,472 600,648 
7,010 60,000 
6,850 9,765 
702,200 1,140,900 
750,667 864,927 
13,000 92,000 
17,813 15,649 
767,400 994,600 
784,450 880,233 
250,000 65,000 
275,431 77,041 
- 270,000 
- 245,452 
624,400 
620,445 
400,000 
288,535 
(-)29,600 
(-)28,978 
732,800 
716,764 
700,000 
205,401 
(-)30,095 
(-)30,095 
1,054,0 
661,5 
20,9 
55,0 
1,148,0 
1,017,8 
13,6 
1,781,5 
1,463,1 
1,0 
1,7 
350,0 
373,9 
1,141,6 
701,5 
1,000,0 
95,4 
(-)32,4 
(-)32,4 
(-)2,165 - - 
1,066,900 1,483,100 950,400 2,876,6 
1,023,979 975,229 1,756,338 1,825,9 
- - - 250,0 
- - - 25,8 
- - - 345,0 
--- -=. 
6,242,000 8,425,000 13,300,000 3,049,0 
5,731,069 7,226,026 12,441,014 5,261,4 
- - - 136,0 
- - - 75,1 
16-16 
00 45,506,300 
04 45,099,741 
00 136,000 
09 75,109 
- 10,934,505 
- 10,934,505 
00 7,713,687 
74 7,255,305 
04 16,912,549 
35 16,896,2851 
00 11,070,003 
94 10,638,585 
- 13,149,286 
47 13,067,5342 
00 11,352,455 
97 10,909,277 
00 741,000 
92 741,000 
00 620,000 
33 619,385 
- 19,088,5243 
- 19,088,524 
00 8,601,084 
92 8,137,535 
00 23,653,000 
48 22,106,508 
00 474,200 
44 474,156 
- 662,400 
- 662,400 
- 14,175,1974 
- 14,175,197 * 
84 15,084,451 
91 13,882,558 
00 250,000 
26 25,826 
00 345,000 
- -

TABLE 16-A 
FORT WORTH TEXAS DISTRICT 
COST AND FINANCIAL STATEMENT 
See 
Section 
in Text Project 
14. Grapevine Lake, TX 
15. Greenville, TX 
16. Hords Creek Lake, 
TX 
17. Joe Pool Lake, TX 
18. Lake Brownwood 
Modification, TX 
19. Lavon Lake, TX 
20. Lavon Lake 
Modification & East 
Fork Channel 
Improvement, TX 
21. Lewisville Dam, TX 
22. Millican Lake, TX 
23. Navarro Mills Lake, 
TX 
24. O. C. Fisher Dam 
and Lake, TX 
25. Proctor Lake, TX 
26. Ray Roberts Lake, TX 
43. Sam Rayburn Dam 
and Reservoir, TX 
Total Cost To 
Funding FY 80 FY 81 FY 82 FY 83 Sep. 30, 1983 17 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Apjrop. 
New Work: 
App~rop. 
Cost 
New Work: 
Approp. 
Cost 
814,700 
807,839 
49,000 
50,774 
328,300 
347,437 
19,689,000 
18,677,800 
1,141,800 
1,091,786 
12,649 
774,900 
1,011,242 
1,297 
(-)528 
325 
376,300 
388,095 
19,785,000 
19,460,419 
1,400,0 
333,8 
2,019,6 
1,308,3
5 
1,122,6 
587,2 
27,800,0 
29,007,0 
8 
- 309,000 
- 276,544 
904,800 962,900 
902,713 883,200 
6,900,000 2,601,000 
6,729,155 2,716,402 
2,300,000 1,775,000 
2,059,628 1,989,569 
1,017,000 991,100 
1,187,391 1,171,036 
300,000 490,000 
294,536 418,158 
24,000- 
23,947 53 
577,100 621,500 
630,573 659,377 
617,300 420,800 
617,011 469,500 
- 7,000 
- 7,000 
507,600 514,700 
578,781 518,437 
(-)425,000 5,500,000 
667,048 5,363,835 
(-)5,813 3,000 
2,608 2,557 
64,096 
38,949 
1,241,800 
1,130,811 
2,413,000 
1,729,262 
1,409,000 
226,286 
1,535,600 
1,295,291 
315,000 
375,026 
5,904 
5,891 
696,800 
665,859 
471,900 
447,689 
30,000 
11,556 
706,500 
659,991 
18,600,000 
17,530,776 
89,000 
39,529 
(-)23,0 
19,7 
2,454,3 
1,547,2 
76,0 
709,2 
(-)13,6 
498,7 
2,556,5 
1,790,0 
232,0 
234,7
73 
1,001,5 
611,8 
954,7 
496,7 
23,0 
27,3 
1,406,3 
733,9 
37,700,0 
37,414,8 
(-)1,3 
48,4
00 11,367,790 
95 10,301,685' 
00 13,108,018 
82 12,324,549 
- 896,900 
58 868,150 
- 2,711,0898 
- 2,711,089 
50 5,908,709 
77 5,285,979 
00 125,088,000 
40 122,437,608 
- 840,000 
- 840,000 
00 12,878,796 
91 12,863,984 
19 13,361,628 
75 12,247,721 
00 69,576,862 
86 69,468,900 
63 24,719,916 
32 24,056,375' 
47 16,045,388 
64 15,021,84910 
00 3,557,000 
15 3,542,433 
67 9,846,759 
00 9,846,27911 
00 8,023,405 
06 7,588,894 
- 16,027,467 
- 16,027,467 
76 7,701,831 
06 7,213,820 
00 14,469,585 
35 14,455,476 
00 7,740,472 
46 6,961,018 
00 66,094,700 
50 64,262,415 
00 60,670,956 
71 60,670,81312 
16-17 
495,800 
426,750 
17,324,000 
14,890,100

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 16-A COST AND FINANCIAL STATEMENT 
See 
Section 
in Text Project Funding 
Maint. 
Approp. 
Cost 
27. San Antonio Channel New Work: 
Improvement, TX Approp. 
(Federal Funds) Cost 
(Contributed Funds) New Work: 
Contrib. 
Cost 
28. San Gabriel River, New Work: 
TX Approp. 
Cost 
Granger Maint. 
Approp. 
Cost 
Lake Georgetown Maint. 
Approp. 
Cost 
29. Somerville Lake, TX New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
30. Stillhouse Hollow New Work: 
Dam, TX Approp. 
Cost 
Maint. 
Approp. 
Cost 
31. Three Rivers, TX New Work: 
Approp. 
Cost 
44. Town Bluff Dam- New Work: 
B. A. Steinhagen Approp. 
Lake, TX Cost 
Maint. 
Approp. 
Cost 
32. Waco Lake, TX New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
33. Wheeler Creek, TX New Work: 
Approp. 
Cost 
45. Whitney Lake, TX New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
34. Wright Patman Dam New Work: 
and Lake, TX Approp. 
Cost 
Maint. 
Approp. 
Cost 
35. Zacate Creek, TX New Work: 
Approp. 
Cost 
Total Cost To 
FY 80 FY 81 FY 82 FY 83 Sep. 30, 1983 " 
1,471,7 
1,524,5 
2,570,0 
2,563,2 
12,826,0 
12,372,9 
319,7 
406,4 
274,2 
353,9 
21,5 
202,0 
837,7 
1,291,2 
(-)2
00 3,838,5 
29 1,706,8 
00 1,150,0 
24 937,5 
- 96,4 
- 65,2 
00 1,607,0 
88 1,758,8 
00 668,1 
30 621,9 
00 591,3 
27 567,0 
66 134,9 
)76 146,3 
00 990,7 
07 978,2 
20 
650,300 
718,939 
115,000 
768,8 
742,1 
2,000,0 
1,878,4 
472,500 541,700 
470,173 528,612 
11 
00 1,714,400 2,405,5 
68 3,181,584 2,249,1 
00 4,750,000 3,300,0 
93 4,212,286 2,631,7 
50 141,775 71,5 
50 172,975 71,5 
00 2,080,000 2,150,0 
23 2,158,550 2,216,3 
00 615,900 1,269,6 
82 609,162 656,7 
00 667,000 1,042,4 
67 620,044 764,8 
90 151,000 (-)1,3 
13 137,380 4,5 
00 1,315,200 1,969,1 
03 1,003,973 1,136,7 
- 20,000 (-)1,9 
- 12,319 5,7 
00 993,100 820,5 
89 789,229 777,7 
00 3,169,000 90,0 
78 3,197,970 173,9 
594,900 1,045,3 
582,686 570,1 
820,400 778,200 1,074,300 1,889,2 
817,001 782,059 1,010,122 1,219,8 
- - 25,000 140,0 
- - 7,502 20,5 
14,813 128,000 - (-)18,4 
108,737 103,337 7,723 (-)5 
,494,000 1,434,400 1,760,400 2,558,3 
,425,105 1,447,788 1,667,889 1,897,5 
(-)1,146 - 41,000 
31,450 - 41,000 
884,700 808,000 1,466,000 1,781,0 
988,791 854,738 1,328,404 1,432,0 
552,000 1,705,000 405,000 (-)54,6 
221,342 1,623,719 728,216 36,1
00 23,458,894 
97 22,589,006 
00 37,718,048 
68 36,268,710 
50 999,525 
50 999,525 
00 101,402,100 
66 101,166,286 
00 2,976,196 
93 2,294,367 
36 2,664,532 
40 2,305,878 
37 27,680,438 
88 27,620,995 
09 11,680,856 
43 10,520,253 
'60 20,522,08413 
'21 20,510,642 
00 7,765,326 
'58 7,406,863 
00 5,980,500 
'25 5,822,340 
- 6,602,737 
- 6,602,737'14 
15 8,754,129 
70 8,234,820 
- 49,521,12115 
- 49,521,121 
00 10,900,926 
86 10,159,075 
'00 165,000 
08 28,010 
.11 42,952,938 
88 42,952,93816 
00 22,431,780 
42 21,592,086 
- 35,731,626 
- 35,731,626 
00 16,414,790 
'24 15,799,119 
3Q 2,717,370 
47 2,717,370 
16-18

FORT WORTH TEXAS DISTRICT 
TABLE 16-A COST AND FINANCIAL STATEMENT 
SExcludes $47,309 receipts from reconveyance of land 
deposited to miscellaneous receipts. 
2 Excludes $322,346 receipts from reconveyance of land 
deposted to miscellaneous receipts. 
3 Excludes $1,422,848 expended for new work from 
contributed funds, including $22,848 "Contributed Funds 
Other" for installation and operation of gages for leakage study. 
4 Includes $1,378,486 for Code 711, $52,808 for Code 713, 
and $399,739 accelerated Public Works Act funds. Excludes 
$1,711,200 contributed funds. 
5 Includes $1,376,322 for Code 711, $52,808 for Code 713, 
and $399,739 accelerated Public Works Act funds. Excludes 
$4,137 reimbursed in Fiscal Year 1973. 
a Claim Northeast Texas Municipal Water District $16,546. 
Three payments of $12,410 less real estate charges of $1,325, 
making a total of $2,811 reimbursed in Fiscal Year 1972, Fiscal 
Year 1973, and Fiscal Year 1974. 
SExcludes $146,795 receipts from reconveyance of land 
deposited to miscellaneous receipts, and $2,040,026 for new work 
expended from contributed funds. 
8 Excludes $105,079 expended from contributed funds. 
' Excludes receipts from reconveyance of land of $426,606 
which were deposted to miscellaneous receipts, and $3,676,661 
for new work expended from contributed funds. 
o1I0n cludes $130,000 under appropriation 96X5125. 
" Excludes $300,000 expended from contributed funds. 
12 Excludes $3 million expended from contributed funds. 
13 Includes receipts from disposals and revocation of funds 
related thereto. 
14 Excludes $2,000,000 contributed funds expended. 
15 Excludes $2,750,000 expended for contributed funds. 
* Excludes $188,282 receipts from reconveyance of lands 
deposited to miscellaneous receipts. 
17 Includes funds provided by the Jobs Act (PL 98-8, dated 
March 24, 1983) for projects listed in Table 16-F. 
16-19 
___ __

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 16-B AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
2. 
3. 
4. 
Aug. 13, 1968 
Mar. 31, 1960 
Jul. 24, 1946 
Sep. 3, 1954 
Mar. 2, 1945 
Dec. 31, 1970 
Jun. 22, 1936 
Mar. 2, 1945 
Sep. 3, 1954 
Aug. 3, 1955 
Mar. 2, 1945 
Oct. 27, 1975 
Oct. 27, 1965 
Jul. 24, 1946 
Jul. 24, 1946 
Mar. 2, 1945 
AQUILLA LAKE, TX 
Construction of a dam on Aquilla Creek, about 6.8 miles 
southwest of Hillsboro, Texas and about 24 miles north 
of Waco, Texas. 
BARDWELL LAKE, TX 
Construction of a dam on Waxahachie Creek about 5 miles 
south of Ennis, Texas. 
BELTON LAKE, TX 
Construction of a dam on the Leon River about 3 miles 
north of Belton, Texas. 
Modification (see Sec. 36 of Text) of the dam to provide for 
generation of hydroelectric power. 
BENBROOK LAKE, TX 
Construction of a dam on the Clear Fork of the Trinity 
River about 10 miles southwest of Fort Worth, Texas. 
BIG SANDY LAKE, TX 
Construction of a dam on Big Sandy Creek about six miles 
northwest of Big Sandy, Texas. 
BOGGY CREEK, TX 
Interim Survey Report. 
CANYON LAKE, TX 
Construction of a dam on the Guadalupe River about 12 
miles northwest of New Braunfels, Texas. 
COOPER LAKE AND CHANNELS, TX 
Construction of earth-fill dam and reservoir area; channel 
clearing, realignment, and enlargement; enlargement 
and extension of existing levees; construction of appurtenant 
drainage works along main stem of Sulphur River 
above mile 126; channel clearing, realignment, and 
enlargement and levee enlargement and modification of 
appurtenant drainage works on Cuthand Creek below 
mile 24, on Sulphur River below mile 70, except in 
proposed Cooper Reservoir, miles 29 to 42, and on Middle 
Sulphur River below mile 8; channel clearing and 
realignment of Brushy Creek below mile 5; and levee 
enlargement on North Sulphur River between miles 1 
and 5. 
DAM "A" LAKE, TX 
Construction of a dam on the Neches River about 18 miles 
west of Jasper, Texas. 
DUCK CREEK CHANNEL IMPROVEMENT, TX 
Realignment and enlargement of about 7 miles of Duck 
Creek in the urban area of Garland, Texas. 
ELM FORK FLOODWAY, TX 
Realignment and enlargement of the Elm Fork of the 
Trinity River and Denton Creek, and a parallel levee 
system from the existing Dallas levee system upstream 
to near the Dallas and Denton county lines. 
FERRELLS BRIDGE DAM-LAKE O' THE 
PINES, TX 
Provides for construction of an earth-fill dam and reservoir 
area. 
GRAND PRAIRIE LANDFILL, TX 
Construction of a cutoff channel to eliminate an oxbow in 
the West Fork of the Trinity River. 
GRAPEVINE LAKE, TX 
Construction of a dam on Denton Creek, a tributary of the 
Trinity River, about 20 miles northwest of Dallas, Texas. 
16-20 
S. Doc. 52, 90th Cong., 
1st Sess. 
H. Doc. 424, 82nd Cong., 
2nd Sess. 
H. Doc. 88, 81st Cong., 
1st Sess. 
H. Doc 535, 81st Cong., 
2nd Sess. 
H. Doc. 403, 77th Cong., 
1st Sess. 
H. Doc. 429, 91st Cong., 
2nd Sess. 
Flood Control Act 
of 1936 (PL 738) 
H. Doc. 247, 76th Cong., 
1st Sess. 
H. Doc. 488, 83rd Cong., 
2nd Sess. 
S. Doc. 98, 76th Cong., 
1st Sess. 
H. Doc. 276, 89th Cong., 
1st Sess. 
H. Doc. 276, 89th Cong., 
1st Sess. 
H. Doc. 602, 79th Cong., 
2nd Sess. 
Flood Control Act of 
1946 
H. Doc. 403, 77th Cong., 
1st Sess. 
5. 
6. 
7. 
8. 
9. 
41. 
10. 
11. 
12. 
13. 
14.

TABLE 16-B 
FORT WORTH TEXAS DISTRICT 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
15. 
16. 
17. 
18. 
19. 
20. 
Dec. 31, 1970 
Aug. 18, 1941 
Oct. 27, 1965 
Aug. 13, 1968 
Mar. 2, 1945 
Oct. 23, 1962 
Mar. 7, 1974 
Mar. 2, 1945 
Aug. 13, 1968 
Sep. 3, 1954 
Dec. 31, 1970 
Aug. 18, 1941 
Sep. 3, 1954 
Oct. 27, 1965 
Mar. 2, 1945 
Mar. 2, 1945 
Sep. 3, 1954 
Sep. 3, 1954 
GREENVILLE LOCAL FLOOD PROTECTION 
Realignment and enlargement of Long Branch, a tributary 
of the Sabine River, in the city of Greenville, Texas. 
HORDS CREEK LAKE, TX 
Construction of a dam on Hords Creek, a tributary of 
Pecan Bayou, near the city of Coleman, Texas. 
JOE POOL LAKE, TX 
Construction of a dam on Mountain Creek, adjacent to the 
city limits of Grand Prairie, Texas, about 3 miles above 
the existing Mountain Creek Dam. 
LAKE BROWNWOOD MODIFICATION, TX 
Modification of the existing Lake Brownwood located on 
Pecan Bayou about 8 miles north of Brownwood, Texas. 
LAVON LAKE, TX 
Construction of a dam on the East Fork of the Trinity 
River about 22 miles northeast of Dallas, Texas. 
LAVON LAKE MODIFICATION AND EAST FORK 
CHANNEL IMPROVEMENT, TX 
Enlarge Lavon Dam and enlargement and realignment of 
the lower 25 miles of the East Fork of the Trinity River, 
including rehabilitation of existing levees. 
Improvement of Collin County Road 115. 
LEWISVILLE DAM, TX 
Construction of a dam on the Elm Fork of the Trinity River 
near the city of Lewisville, Texas. 
MILLICAN LAKE, TX 
Construction of a dam on the Navasota River about seven 
miles north of Navasota, Texas. 
NAVARRO MILLS LAKE, TX 
Construction of a dam on Richland Creek, a tributary of 
the Trinity River, about 16 miles southwest of Corsicana, 
Texas. 
Alteration of FM Highway 3164 in Wolf Creek Park. 
O. C. FISHER DAM AND LAKE, TX 
Construction of a dam on the North Concho River just 
above San Angelo, Texas. 
PROCTOR LAKE, TX 
Construction of a dam on the Leon River about 8 miles 
northeast of Comanche, Texas. 
RAY ROBERTS LAKE, TX 
Construction of a dam on the Elm Fork of the Trinity River 
between Sanger and Aubrey, Texas, about 30 miles 
upstream from the existing Lewisville Dam. 
ROCKLAND LAKE, TX 
Construction of a dam on the Neches River approximately 
three miles west of Rockland. 
SAM RAYBURN DAM AND RESERVOIR, TX 
Construction of a dam on the Angelina River about 10 
miles northwest of Jasper, Texas. 
SAN ANTONIO CHANNEL IMPROVEMENT, TX 
Channel improvement of the San Antonio River and 
tributaries in and near the city of San Antonio, Texas. 
SAN GABRIEL RIVER PROJECT, TX 
Construction of: (1) a dam (Granger Dam and Lake) on the 
San Gabriel River about 7 miles east of Granger, Texas, 
(2) a dam (North Fork Lake) on the north Fork of the 
San Gabriel River about 3.5 miles northwest of 
16-21 
H. Doc. 91429, 91st 
Cong., 2nd Sess. 
H. Doc. 370, 76th Cong., 
1st Sess. 
H. Doc. 276, 89th Cong., 
1st Sess. 
H. Doc. 350, 90th Cong., 
2nd Sess. 
H. Doc. 533, 78th Cong., 
2nd Sess. 
H. Doc. 554, 87th Cong., 
2nd Sess. 
H. Doc. 403, 77th Cong., 
1st Sess. 
H. Doc. 341, 90th Cong., 
2nd Sess. 
H. Doc. 498, 83rd Cong., 
2nd Sess. 
H. Doc. 315, 76th Cong., 
1st Sess. 
H. Doc. 535, 81st Cong., 
2nd Sess. 
H. Doc. 276, 89th Cong., 
1st Sess. 
S. Doc. 98, 76th Cong., 
1st Sess. 
S. Doc. 98, 76th Cong., 
1st Sess. 
H. Doc. 344, 83rd Cong., 
2nd Sess. 
H. Doc. 535, 81st Cong., 
2nd Sess., and 
H. Doc. 591, 87th Cong., 
2nd Sess. 
21. 
22. 
23. 
24. 
25. 
26. 
42. 
43. 
27. 
28.

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 16-B AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
29. 
30. 
31. 
44. 
Jan. 3, 1975 
Sep. 3, 1954 
Sep. 3, 1954 
Jul. 29, 1971 
Mar. 2, 1945 
Oct. 27, 1965 
Sep. 3, 1954 
Jun. 30, 1948 
Aug. 18, 1941 
Jul. 24, 1946 
Jun. 30, 1948 
Georgetown, Texas and (3) a dam (South Fork Lake) on 
the South Fork of the San Gabriel River about 3 miles 
southwest of Georgetown, Texas. 
SOMERVILLE LAKE, TX 
Construction of a dam on Yegua Creek about 2 miles south 
of Somerville, Texas. 
STILLHOUSE HOLLOW DAM, TX 
Construction of a dam on the Lampasas River about 5 
miles southwest of Belton, Texas. 
THREE RIVERS FLOOD CONTROL PROJECT, TX 
Construction of a levee to provide flood protection to the 
city of Three Rivers, Texas, on the Frio River. 
TOWN BLUFF DAM-BA. STEINHAGEN LAKE, TX 
Construction of a dam on the Neches River near Jasper, 
Texas. 
TRINITY RIVER PROJECT, TX 
Construction of Tennessee Colony Dam located at river 
mile 339.2 on the Trinity River about 16 miles west of 
Palestine, Texas; a multiple purpose channel from the 
Houston, Texas ship channel to Fort Worth, Texas; a 
distance of approximately 363 miles, an extension of the 
existing Dallas, Texas, Floodway downstream approximately 
9.0 miles; a realignment and enlargement of the 
West Fork of the Trinity River from the mouth of the 
West Fork to the existing Fort Worth, Texas, Floodway, 
a distance of approximately 31 miles; and water 
conveyance facilities involving construction of about 98 
miles of pipeline from Tennessee Colony Lake to the 
existing Benbrook Lake. 
WACO LAKE, TX 
Construction of a dam on the northwest edge of Waco, 
Texas, below the confluence of the North, South, and 
Middle Bosque Rivers. 
WHEELER CREEK, TX 
Channel improvement of Wheeler Creek at Gainsville, 
Texas. 
WHITNEY LAKE, TX 
Construction of a dam on the Brazos River, about 19 miles 
southwest of Hillsboro, Texas. 
Raise the power pool 13.0 feet. 
WRIGHT PATMAN DAM AND LAKE, TX 
Construction of an earth-fill dam and reservoir. 
ZACATE CREEK CHANNEL, TX 
Construction of channel improvement. 
16-22 
H. Doc. 535, 81st Cong., 
2nd Sess. 
H. Doc. 535, 81st Cong., 
2nd Sess. 
H. Doc. 92-153, 
92nd Cong. 
S. Doc. 98, 76th Cong., 
1st Sess. 
H. Doc. 276, 89th Cong., 
1st Sess., and 
H. Doc. 364, 90th Cong., 
2nd Sess. 
H. Doc. 535, 81st Cong., 
2nd Sess. 
Flood Control Act of 
1948 (PL 858). 
H. Doc. 390, 76th Cong., 
1st Sess. 
H. Doc. 602, 79th Cong., 
2nd Sess. 
H. Doc. 6419, 80th 
Cong., 2nd Sess. 
PL 858 
1. 
32. 
33. 
45. 
34. 
35.

FORT WORTH TEXAS DISTRICT 
TABLE 16-C 
OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(See Section 38 of Text) 
For Last Cost to September 30, 1983 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Big Fossil Creek, TX3 1969 - - 
Big Spring, TX2 1979 - - 
Brownwood Channel Improvement, TX1 - - - 
Carl L. Estes Dam and Lake, TX2 1979 - - 
Fort Worth Floodway (Clear Fork), TX3 1971 - - 
Fort Worth Floodway (West Fork), TX3 1971 - - 
Lake Fork Lake, Sabine River, TX' - - - 
Navasota Lake, Navasota River, TX' - - - 
Pecan Bayou Lake, Pecan Bayou, TX' - - - 
Plainview Local Flood Protection Project, TX' 1979 - - 
Roanoak Lake, TX' 1979 - - 
Rutledge Hollow Creek Channel Improvement, Poteet, TX3 1969 - - 
1 Awaiting availability of funds. 
2 Inactive. 
3 Completed. 
4 Recommended for deauthorization, H.R. 3678, August 23, 1983, 98th Congress, 1st Session. 
INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS 
TABLE 16-D (See Section 36 of Text) 
Location Dates of Inspection 
Munday Floodway Nov. 29, 1982 
Dallas Floodway Nov. 30, 1982 
Fort Worth Floodway Dec. 15, 1982 
Big Fossil Creek Dec. 28, 1982 
East Fork Jun. 8, 1983 
San Antonio Floodway Aug. 2, 1983 
Pleasanton Aug. 4, 1983 
Poteet Floodway Aug. 4, 1983 
Sulphur River Levees Aug. 15, 1983 
Greenville Floodway Sep. 30, 1983 
16-23

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION 
TABLE 16-E (See Section 39 of Text) 
Project Cost 
Big Fossil Creek, Haltom City, TX $ 6,962 
Briar Creek, Bryan, TX 7,500 
Burton Creek, Bryan, TX 9,254 
California Creek, Hamlin, TX 106,299 
Calloway Branch, Hurst, TX 61,253 
Chacon Creek, Laredo, TX 37,595 
Cibolo Creek, Shertz, TX 13,620 
Elm Fork, Gainsville, TX 14,711 
Grand Prairie, TX 12,603 
Myers Road 
Hickory Creek, Balch Springs, TX 60,691 
Lake Creek, Round Rock, TX 52,605 
Lake Creek, Williamson County, TX 996 
Lorean Branch, Hurst, TX 34,219 
Lynchburg Creek, Corinth, TX 5,912 
Pecan Creek, Gainesville, TX 96,734 
Pecan and Cooper Creeks, Denton, TX 163 
Roscoe, TX 38,119 
San Felipe Creek, Del Rio, TX 6,326 
Zacate Creek, Laredo, TX 36,147 
16-24

TABLE 16-F 
Projec 
Bardw 
Belton 
Benbro 
Canyot 
San GE 
Grang 
Grapes 
Hords 
San Ge 
Lake C 
Lake C 
Lavon 
Lewisv 
Navarr 
0. C. F 
Proctor 
Sam R 
Somer 
Stillho 
Town I 
Waco I 
Whitne 
FORT WORTH TEXAS DISTRICT 
JOBS ACT CONTRACTS AWARDED DURING FY 1983 
(PL 98.8 March 24, 1983) 
t Funding F 
ell Lake, TX Maint. 
Approp. 4 
Cost 
Lake, TX Maint. 
Approp. 2 
Cost 
)ok Lake, TX Maint. 
Approp. 7 
Cost 5 
n Lake, TX Maint. 
Approp. 2 
Cost 
abriel, 
er Lake, TX Maint. 
Approp. 2 
Cost 
ine Lake, TX New Work 
Approp. 1,4 
Cost 3 
Maint. 
Approp. 7 
Cost 
Creek, TX Maint. 
Approp. 5 
Cost 
abriel, 
eorgetown, TX Maint. 
Approp. 
Cost 
)' The Pines, TX Maint. 
Approp. 3 
Cost 
Lake, TX Maint. 
Approp. 6 
Cost 1 
ille Lake, TX Maint. 
Approp. 7 
Cost 
o Mills Lake, TX Maint. 
Approp. 3 
Cost 
isher Dam & Lake, TX Maint. 
Approp. 2 
Cost 
r Lake, TX Maint. 
Approp. 6 
Cost 
ayburn Dam & Reservoir, TX Maint. 
Approp. 8 
Cost 1 
ville Lake, TX Maint. 
Approp. 6 
Cost 
use Hollow Dam Maint. 
Approp. 1 
Cost 
Bluff Dam, TX Maint. 
Approp. 2 
Cost 
Lake, TX Maint. 
Approp. 6 
Cost 
ey Lake, TX Maint. 
Approp. 5 
Cost 
Y 1983 
07,700 
2,329 
87,100 
59,052 
34,500 
52,298 
45,500 
5,402 
28,600 
29,218 
00,000 
33,895 
44,600 
43,441 
74,700 
32,233 
84,400 
76,102 
25,000 
22,208 
73,200 
64,608 
91,300 
71,800 
308,500 
2,420 
00,000 
4,065 
79,300 
48,840 
90,500 
22,641 
28,100 
92,963 
44,000 
32,141 
96,100 
12,529 
24,300 
44,635 
13,700 
84,090 
16-25

TABLE 16-F 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
JOBS ACT CONTRACTS AWARDED DURING FY 1983 
(PL 98.8 March 24, 1983) 
Project 
Wright Patman Lake, TX 
Wheeler Creek, Gainsville, TX 
Grand Prairie Lake, TX 
Funding FY 1983 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
316,000 
12,638 
130,000
0 
250,000 
25,826 
16-26

ALBUQUERQUE, NM, DISTRICT* 
The district comprises watershed of Canadian River 
and tributaries and the watershed of Arkansas River and 
tributaries in Colorado and New Mexico; the watershed 
of Rio Grande and tributaries including Pecos River and 
its tributaries upstream of Amistad Lake; and watershed 
of Mimbres River and its tributaries in New Mexico. 
Note: The district watershed boundaries were revised in 
July 1982 to include all of New Mexico west of the Texas 
state line and the southwest corner of Colorado west of 
the Kansas state line. 
IMPROVEMENTS 
Flood Control 
1. Albuquerque Diversion Channels, NM .... 
2. Cibolo Creek, TX........................ 
3. Conchas Lake, NM ...................... 
4. El Paso, TX........................ 
5. Highway 12, CO ........................ 
6. Holly, CO.......... ..................... ...... 
7. John Martin Reservoir, CO............... 
8. Larned, Pawnee River, KS ............... 
9. Rio Grande Basin, NM ................... 
9A. Abiquiu Dam, NM....................... 
9B. Cochiti Lake, NM ....................... 
9C. Galisteo Dam, NM ..................... 
9D. Jemez Canyon Dam, NM................ 
9E. Rio Grande Floodway, NM ............... 
9F. Truth or Consequences 
Page 
17-1 
17-2 
17-2 
17-2 
17-3 
17-3 
17-3 
17-3 
17-4 
17-4 
17-4 
17-5 
17-5 
17-5 
(Hot Springs) Unit, NM ................. 17-6 
10. Santa Fe River and Arroyo 
M ascaras, NM .......................... 17-6 
11. 
12. 
13. 
14. 
15. 
16. 
17. 
18. 
Santa Rosa Dam and Lake, NM........... 17-6 
Smith Creek, CO........................ 17-7 
Trinidad Lake, CO ..................... 17-7 
Two Rivers Dam, NM....................17-7 
Inspection of completed flood 
control projects....................... 17-8 
Scheduling flood control 
reservoir operations ...................... 17-8 
Other authorized flood 
control projects....................... 17-8 
Flood control work under 
special authorizations................... 17-8 
General Investigations 
19. Surveys ............................... 17-9 
20. Collection and study of basic data ......... 17-9 
Flood Control 
1. ALBUQUERQUE DIVERSION 
CHANNELS, NM 
Location. In an area which comprises watersheds of 
ephemeral streams entering a 15-mile reach of Rio Grande 
from the east at Albuquerque, NM, and vicinity. Combined 
drainage area of tributaries is about 276 square 
miles. Sandia range of the Rocky Mountains, which is 
about 12 miles east of Rio Grande, forms eastern border 
of watersheds. Crest of mountain range rises more than 
a mile over river to elevation of 10,692 feet above mean 
sea level. (See Geological Survey Map, Albuquerque, NM, 
quadrangle, scale 1:62,500.). 
Existing project. Plans of improvement consists of 
north and south diversion channels on high ground east 
of and parallel to valley. Channels are designed to carry 
floods equal in magnitude to standard project flood from 
all tributaries. For description of complete improvement 
and authorizing legislation see page 17-15 of Annual Report 
for FY 1973. 
Local cooperation. Section 2 Flood Control Act of 
1938 applies. For details of local cooperation requirements 
see page 17-2 of Annual Report for FY 1973. 
Operations and results during fiscal year. The 
North and South Diversion Channels did not prevent 
annual flood damages during FY. The estimated total 
accumulated flood damages prevented were $36,768,300. 
Peak flood flows recorded during FY 1983 were North 
Diversion Channel near Alameda, 1,290 c.f.s. on June 24, 
*All cost and financial statements for projects are listed at the end of.this chapter. All other tables are referenced in text and also appear 
at the end of this chapter. 
17-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
1983, and for South Diversion Channel 340 c.f.s. on 
July 29, 1983. 
Condition at end of fiscal year. Construction of the 
north and south diversion channels began in March 1965, 
and was completed in March 1972. Channels are in good 
condition and well maintained by local interests. 
2. CIBOLO CREEK, TX 
Location. Presidio, TX, Presidio County, at the confluence 
with the Rio Grande in southwest Texas. 
Existing Project. Consists of left bank levee 1.4 miles 
long to protect the town of Presidio TX and a right bank 
swing levee 0.7 miles long to protect a housing development 
area. The levee system is designed for a peak flow of 
67,000 c.f.s. on Cibolo Creek with a coincident flow in the 
Rio Grande of 44,000 c.f.s. Appurtences consist of ramps 
for existing road and 18 inch rip-rap for both levees on 
Cibolo Creek. 
Local Cooperation. Section 3 Flood Control Act of 
June 22, 1936 applies. Local interests are in compliance 
with Section 221, 1970 FC Act and Public Law 91-646 
Uniform Relocation Act of 1970. 
Operations and results. N/A 
Conditions at the end of the year. Construction was 
started in April 82 and was be completed in November 
1982. 
3. CONCHAS LAKE, NM 
Location. Dam is in San Miguel County, NM, on 
Canadian River, about one-fourth mile downstream from 
confluence of Canadian and Conchas Rivers. (See Geological 
Survey State map of New Mexico, scale 1:500,000, 
and Geological Survey topographic map. Tucumcari quadrangle, 
scale 1: 125,000). 
Existing project. A concrete gravity main dam section 
1,250 feet long with a maximum height of 200 feet above 
streambed located in Canadian River Canyon together 
with earth dikes on each side having an overall length 
of about 3.7 miles. Main section contains conduits in its 
base for release of water to maintain low flows and for 
drainage of reservoir, and an overflow, ungated spillway 
300 feet long. Earth dikes vary in height up to 100 feet 
and north dike contains a concrete ogee-type emergency 
spillway 3,000 feet long. Reservoir has a gross storage 
capacity of 529,000 acre-feet (198,900 for flood control, 
259,600 for water conservation and irrigation, and 70,500 
dead storage). Dam controls 7,409 square miles of drainage 
area. (See page 17-16 of Annual Report of 1973 for 
authorizing legislation.) 
Local cooperation. None required. 
Operations and results during fiscal year. Operation 
of reservoir continued. Reservoir was operated for 
storage of floodwaters and releases for irrigation purposes. 
$158,000 in sediment damages were prevented 
during FY 1983 while no flood damages were prevented. 
Estimated total accumulated flood and sediment damages 
prevented by project through FY 1983 were $2,103,400. 
Estimated irrigation benefits for FY 1983 were $274,500. 
Estimated total accumulated irrigation benefits through 
FY 1983 were $8,261,100. Pool elevation at start of FY 
1983 was 4,190.75 feet with corresponding storage of 
242,644 acre-feet. Total releases for reporting period were 
79,681 acre-feet. Releases of 76,119 acre-feet were made 
to Arch Hurley Conservancy District and 2,321 acre-feet 
to Bell Ranch. Pool elevation on September 30, 1983, was 
4,190.29 feet with corresponding storage of 239,242 acrefeet. 
Sediment deposition during the fiscal year was 
1,411 acre-feet. 
Condition at end of fiscal year. Existing project was 
essentially complete in 1940. Reservoir and appurtenances 
are in good condition and in operation. Irrigation 
of some lands under project was begun in November 1945. 
A cost sharing agreement between the Government and 
the State of New Mexico for additional Recreation Development 
at Conchas Lake was approved in August 1977. 
Costs of the facilities are 50 percent State of New Mexico 
and 50 percent Federal. Construction of these recreation 
facilities was initiated in FY 1978 and completed in FY 
1983. 
4. EL PASO, TX 
Location. At El Paso, El Paso County, TX, which is 
on left bank of Rio Grande in the reach that forms part of 
international boundary between United States and Republic 
of Mexico. (Geological Survey map for El Paso, 
TX; New Mexico quadrangle, scale 1:250,000.) 
Existing project. Consists of a single-purpose flood 
control system of detention dams, diversion dikes, conduits 
and channels to collect, regulate and discharge 
arroyo runoff into Rio Grande. Runoff from tributary 
arroyos on eastern, southern, and western slopes of adjacent 
Franklin Mountains often inundates sections of 
city and its outlying suburban developments. Project is 
divided into three independent elements: Northwest area, 
Central area, and Southeast area. The project plan 
satisfies the 1933 U.S. and Mexico agreement on limited 
tributary discharge into the Rio Grande in El Paso, Texas. 
(See Table 17-B for authorizing legislation.) 
Local cooperation. Section 2 Flood Control Act of 
June 28, 1938 applies. 
Operations and results during fiscal year. Flood 
control dams in operation during FY 1983 and dates of 
completion of construction are as follows: Northgate and 
Range Dams (February 1973); Sunrise and Mountain 
Park Dams (October 1974); and Pershing Dam (March 
1977); Fort Bliss Diversion Channel (November 1978); 
Oxidation Pond and Buena Vista Diversion and Oxidation 
Pond Outlet Conduit (November 1980); Mulberry and 
Thorn Drive Dams (June 1982); Mesa Dam (September 
1982); McKelligon Canyon Dam was completed in October 
1982 and Keystone Dam was completed in September 
1983. During FY 1983 flood flows and flood control storage 
were minimal; however, damages which would have 
resulted from these flows were prevented. The estimated 
total flood damages prevented since completion of Northgate 
and Range Dams in 1973 through FY 1983 were 
$22,700. 
Condition at end of fiscal year. Construction has 
temporarily ended in the Central Area. Remaining projects 
include the Fillmore-Van Buren Dams System and 
17-2

ALBUQUERQUE, NM, DISTRICT 
Dam Safety Assurance Program modifications to the 
existing Range and Northgate Dams. The Central Area 
of the project is about 78 percent complete. 
In the Northwest Area, construction of Keystone Dam 
was completed. The construction of Keystone Dam Outlet 
Conduit was awarded in March 1983 and was approximately 
30 percent complete at the end of the fiscal year. 
Remaining works consist of the Borderland Diversion and 
Highway Diversion projects. The Northwest Area is approximately 
53 percent complete. 
The Reconnaissance Report on the Southwest Area was 
completed in December 1982 and the preparation of the 
General Design Memorandum is approximately 45 percent 
complete. 
5. HIGHWAY 12, CO 
Location. Highway 12, along the Purgatoire River, 
Las Animas County, CO approximately 7 miles above 
Trinidad, CO to Weston, CO. (See Geological Survey Map 
Madrid CO quadrangle scale 1:24,000.) 
Existing project. Three locations on the left bank of 
the Purgatoire River are protected from bank erosion 
during flood flows by an approximate total of 1950 feet 
of Kelner jacks spaced at 12.5 feet on centers. 
Local cooperation. Section 3 of FC Act of June 22, 
1936 applies. Local interests are in compliance with 
Section 221 1970 FC Act and PL 91-646 Uniform Relocation 
Act of 1970. 
Operation and results. N/A 
Condition of the end of the year. Construction was 
started in September 1982 and was completed in January 
1983. 
6. HOLLY, CO 
Location. Holly, CO, Cheyenne County, is situated on 
the north bank of the Arkansas River at the confluence of 
Wild Horse Creek, a north bank tributary and Two Butte 
Creek a south bank tributary and the Arkansas River at 
river mile 1,105. (See Geological Survey map Holly East 
CO & KS quadrangle, scale 1:24,000). 
Existing project. A levee 4.3 miles in length begins 
at a high point north of Holly extending south along the 
left bank of Wild Horse Creek to its junction with the 
Arkansas River then east 4,300 feet below the confluence. 
Appurtences consist of 2 gravity flow drainage structures 
for interior ditches and ponding areas with closure structures 
at the railroad and highway crossings. Contributing 
drainage area is 5,508 square miles with design flows of 
62,000 c.f.s. for Wild Horse Creek and a peak flow of 
160,000 c.f.s. for the combined flows on the Arkansas 
River at Holly, CO. 
Local cooperation. Section 3, Flood Control Act of 
June 22, 1936 applies. Local interests are in compliance 
with Section 221, 1970 FC Act and Public Law 91-646 
Uniform Relocation Act of 1970. 
Operations and results. Operations by local interests. 
Condition at the end of the year. Construction was 
started in June 1979 and placed in operation in 1982. 
Project structures are in good condition and in operation. 
7. JOHN MARTIN RESERVOIR, CO 
Location. On Arkansas River 1,159 miles upstream 
from its mouth, 300 miles downstream from its source, 
in Bent County, about 18 miles upstream from city of 
Lamar, CO. (See Geological Survey maps for Lamar and 
Las Animas, CO quadrangles, scale 1:125,000.) 
Existing project. A concrete and earthfill structure 
about 2.6 miles long with a maximum height of 106 feet 
above streambed and an overflow, gated spillway 1,174 
feet long. Total capacity of reservoir at spillway crest is 
615,500 acre-feet (270,200 for flood control and 345,300 
for conservation and recreation storage). Reservoir controls 
a contributing drainage area of 18,130 square miles 
and is operated as a unit of coordinated reservoir system 
for flood control in Arkansas River Basin. Public Law 
89-298 modified the act of June 22, 1936 (49 Stat. 1570) 
to authorize 10,000 acre-feet of reservoir flood control 
storage space for fish and wildlife and recreation purposes. 
For detail of completed improvement and authorizing 
legislation see page 17-16 of Annual Report for FY 1973. 
Local cooperation. Section 3 Flood Control Act of 
June 22, 1936, applies. 
Operations and results during fiscal year. Routine 
maintenance and operation continued. Regulation of 
conservation storage continued under rules and regulations 
of Arkansas River Compact. No flood damages were 
prevented during FY 1983; however, $219,200 sediment 
damages were prevented. Estimated total flood and sediment 
damages prevented by project through FY 1983 were 
$74,772,700. Estimated irrigation benefits for FY 1983 
were $570,600. Estimated total accumulative irrigation 
benefits were $21,173,600. Maximum pool elevation of 
3,838.33 feet with corresponding storage of 218,321 acrefeet 
occurred on July 12, 1983. Total releases for FY 
1983 were 282,129 acre-feet. Releases attributed to irrigation 
benefits amounted to 145,192 acre-feet. Sediment 
depositions was 1,957 acre-feet. 
Condition at end of fiscal year. Storage and operation 
of reservoir for irrigation began in March 1943. Resevoir 
and appurtenances are in good condition and in operation. 
8. LARNED, KS 
Location. Larned KS, Pawnee County at river mile 
896 on the Arkansas River at the confluence of the Pawnee 
River, a major tributary that enters the Arkansas River 
from the west. (See Geological Survey Map, Lamed quadrangle, 
scale 1:24,000.) 
Existing project. Consists of a levee about 1.9 miles 
long beginning on the left bank of the Pawnee River, extending 
east past the confluence of the Arkansas River to 
a point below the municipal sewage treatment plant, a 
sufficient distance to prevent backwater from entering 
the urban area behind the levee. Appurtenent works include 
an interior drainage system with 3 gravity drainage 
17-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
outlet structures. Stop-log structures are located where 
the levee intersects the US Highway 56 and AT & SF 
Railroad and at Kansas Highway 19. The project design 
is to protect Lamed, KS from a peak flow of 46,000 c.f.s. 
in the Arkansas River. Contributing drainage area of the 
Arkansas River is 7,887 square miles, while the Pawnee 
River watershed contains 2,549 square miles. 
Local cooperation. Section 3 FC Act of June, 22, 1936 
applies. Local interests are in compliance with Section 
221, 1970 FC Act and Public Law 91-646. Uniform Relocation 
Assistance Act of 1970. 
Operations and results. Operations are by local interests. 
Condition at the end of the year. Construction was 
started in December 1980 and placed in operation in 
May 1982. 
9. RIO GRANDE BASIN, NM 
Location. Improvements are on Rio Grande and tributaries 
in New Mexico. More definite locations and 
descriptions of individual projects are in following paragraphs 
and individual reports by projects. 
Existing project. Flood Control Act of 1948 authorized 
flood control phase of comprehensive plan of development 
of water resources of Rio Grande basin in New Mexico (H. 
Doc. 243, 81st Cong., 1st sess.).with exception of Chiflo 
Dam and Reservoir and spillway gate structure at Chamita 
Dam. Although recommended Chiflo Dam and Reservoir 
was deleted from authorized plan, it was excluded without 
prejudice to future consideration by Congress. It was requested 
at that time, by States of Colorado and Texas, that 
project be deferred for restudy regarding required storage 
and methods of operation. By same act, Congress also authorized 
for construction irrigation phase of comprehensive 
plan as recommended by Bureau of Reclamation (H. 
Doc. 653, 81st Cong., 2nd sess.). The act also stipulated 
that work should be prosecuted in accordance with joint 
agreement approved by Secretary of the Army and Acting 
Secretary of the Interior on November 21, 1957. In addition, 
under that agreement Bureau of Reclamation was 
given responsibility for construction, operation, and 
maintenance of channel rectification, and drainage rehabilitation 
and extension phases of unified plan of improvement. 
Authority for Chamita Dam and Reservoir 
was abrogated when Cochiti Dam and Reservoir was authorized. 
(See Table 17-B for authorizing legislation and 
Table 17-C for existing projects.) 
All operations and costs for projects in authorized plan 
are in individual reports on the following pages. 
9A. ABIQUIU DAM, NM 
Location. Project is one unit of flood control phase of 
comprehensive plan for Rio Grande and tributaries, New 
Mexico. Abiquiu Dam is on Rio Chama near town of Abiquiu, 
NM, about 32 miles upstream from confluence of Rio 
Chama and Rio Grande. (See Geological Survey Map for 
plan and profile of Rio Chama, NM, from mouth to mile 
103, sheet 1, and Army Map Service, Aztec, NM; Colorado 
NJ 13-10, scale 1:250,000.) 
Existing project. An earthfill dam 1,540 feet long, 
325 feet high, with a 12-foot diameter controlled outlet, 
and an uncontrolled spillway in a natural saddle about 
one mile north of left abutment. Reservoir provides 
565,000 acre-feet of flood control and sediment storage. 
Total capacity at spillway crest is 1,212,000 acre-feet. 
For detail description of completed improvements and 
authorizing legislation see Annual Report of 1973. A 
major rehabilitation project was completed in September, 
1980 and the recreation facilities were completed in 
FY 1981. 
Local cooperation. None required. 
Operations and results during fiscal year. Routine 
maintenance and operation continued. Storage and flows 
were regulated in accordance with regulations prescribed 
by Rio Grande Compact Commission. On October 1, 1983, 
the pool elevation was 6,159.34 feet. The maximum pool 
(6,213.89 feet) and storage (175,460 acre-feet) occurred 
on June 14, 1983. On September 30, 1983, the pool elevation 
was 6,193.49 feet with a corresponding storage 
of 105,070 acre-feet. There was 1,970 acre-feet of sediment 
deposition during FY 1983. 
There were $22,653,900 in flood damages prevented 
during FY 1983. 
Sediment damages prevented were $220,600. Accumulated 
flood and sediment damages prevented by the 
project since completion were $56,015,300 through FY 
1983. 
Condition at end of fiscal year. Project was placed 
in operation in February 1963. Project structures are in 
good condition and in operation. 
9B. COCHITI LAKE, NM 
Location. Dam is at river mile 340 on Rio Grande 
(river mile 0 being at intersection of New Mexico-Texas 
State line with international boundary at El Paso, TX), 
near Pueblo de Cochiti, which is about 50 miles upstream 
from Albuquerque, NM. (See Geological Survey Maps, 
Cochiti Dam, NM, quadrangle and Santo Domingo Pueblo, 
NM, quadrangle, scale 1:24,000.) 
Existing project. Consists of an earthfill dam about 
5.4 miles long with a maximum height of 251 feet above 
streambed. Project extends generally in an east-west line 
across Rio Grande to a point about 2 miles east of Rio 
Grande and then southward across Santa Fe River. An 
uncontrolled spillway with a 460-foot-long ogee-weir and 
a 160-foot notch 10.5 feet deep in the center is at the embankment 
on south side of Santa Fe River. Operational 
releases for flood control and irrigation are made through 
a 3-barrel gated conduit in left abutment on Rio Grande. 
Reservoir has a storage capacity of 492,500 acre-feet for 
flood control, 103,800 acre-feet for sediment and 45,700 
acre-feet for recreation within the sediment space, for a 
total of 596,300 acre-feet. The project controls flood waters 
from a 11,695 square mile drainage area. For more improvements 
details see page 17-7 of Annual Report for 
1980. See page 17-14 of fiscal year 1981 Annual Report 
for Authorizing Legislation. 
17-4

ALBUQUERQUE, NM, DISTRICT 
Local cooperation. None required. 
Operations and results during fiscal year. The 
project was completed in June 1975. On October 1, 1982, 
the pool elevation was 5,322.65 feet with a corresponding 
storage of 41,779 acre-feet. The maximum pool elevation 
was 5,348.68 feet with a storage of 78,569 acre-feet on 
June 5, 1983. There was 1,570 acre-feet of sediment 
deposition during FY 1983. There were $1,009,100 in 
flood damages prevented during FY 1983. Sediment 
damages prevented were $175,800. Accrued total damages 
prevented are $35,664,200. 
Conditions at end of fiscal year. The dam and appurtenances 
were placed in operation in 1975. The Cochiti 
Recreation area was completed in 1976, with the Visitors 
Center completion in 1977. The Tetilla Peak Recreation 
area was re-advertised and awarded in 1980 and completed 
in 1981. Project structures are in good condition 
and in operation. 
9C. GALISTEO DAM, NM 
Location. Dam is at river mile 12 on Galisteo Creek, 
a tributary of Rio Grande. Definite project site is about 8 
miles upstream of project document site. Reservoir will 
extend upstream from dam for about 4 miles to near 
village of Waldo, NM. (See Geological Survey Map, San 
Pedro 1, NM quadrangle, scale 1:24,000.) 
Existing project. Consists of an earthfill dam 2,820 
feet long with a maximum height of 158 feet above 
streambed. The outlet works consist of a 10-foot diameter 
uncontrolled outlet with a discharge capacity of 4,980 
cubic feet per second with pool at spillway crest elevation. 
The spillway is a broad crested weir 250 feet long in 
right abutment. The flood control storage is 89,000 acrefeet. 
For more details of completed improvements and 
authorizing legislation see page 17-17 of Annual Report 
for 1973. 
Local cooperation. None required. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. Operation of the 
project began on October 11, 1970. The reservoir was 
empty on October 1, 1983. Outflow from the project 
ranged from zero to the maximum inflow and discharge 
of 790 c.f.s. on August 2, 1983. There was 56 acre-feet 
of sediment deposition during the year and the reservoir 
was empty on September 30, 1983. Sediment damages 
prevented during FY 1983 were $6,300 totaling $96,000 
through FY 1983. 
Condition at end of fiscal year. Project was placed 
in operation in October 1970. Project structures are in 
good condition and in operation. 
9D. JEMEZ CANYON DAM, NM 
Location. in Sandoval County, NM, on Jemez River 
about 2 miles upstream from confluence of Jemez River 
and Rio Grande, about 5 miles northwest of Bernalillo, 
NM (See Geological Survey map for Bernalillo quadrangle, 
scale 1:125,000.) 
Existing project. An earthfill dam 780 feet long with 
a maximum height of 135 feet above streambed, and offchannel 
uncontrolled saddle spillway 400 feet wide, and 
a 13-foot diameter gated outlet in left abutment with discharge 
capacity of 8,340 cubic feet per second with pool 
at spillway crest elevation. Reservoir has a capacity of 
106,100 acre-feet (73,000 acre-feet for flood control and 
33,100 acre-feet for sediment control). For more detailed 
description of completed improvements and authorizing 
legislation see page 17-17 of Annual Report for 1973. 
Local cooperation. None required. 
Operations and results during fiscal year. On October 
1, 1982, the pool elevation was 5,160.10 feet with a 
corresponding storage of 2,013 acre-feet. The maximum 
pool elevation was 5,172.60 feet with a storage of 7,831 
acre-feet on April 27, 1983. The reservoir was regulated 
for sediment control during Fiscal Year 1983. Sediment 
deposition during the year was 1,340 acre-feet. There 
were no flood damages prevented during FY 1983. Sediment 
benefits during FY 1983 were $150,100. Estimated 
total accumulated flood and sediment damages prevented 
by the project through FY 1983 were $4,146,400. 
Condition at end of fiscal year. Project was placed 
in operation in October 1953. Project structures are in 
good condition and in operation. 
9E. RIO GRANDE FLOODWAY, NM 
Location. Project is one unit of flood control phase of 
comprehensive plan of improvement for Rio Grande Basin 
in New Mexico. It is on the Rio Grande and covers a 
section of the river commencing near Truth or Consequences 
(formerly Hot Springs) at about river mile 123 
and extends upstream to Espanola, NM, about river mile 
394.(See Table 17-D on Rio Grande Floodway.) 
Existing project. Consists of flood protection and 
major drainage improvements by channel rectification, 
levee enlargement and construction, and bank stabilization 
work where needed to protect levees. Construction of 
project is a joint undertaking by Bureau of Reclamation 
and the Corps. Portions to be done by Corps will consist 
of levee enlargement, construction, and bank protection 
work, with channel-rectification and drainage-rehabilitation 
work the responsibility of Bureau of Reclamation. 
Levees constructed by local interests exist through reach 
of river involved, but are not uniform as to grade, section, 
or standard of construction, and in many places are 
threatened by meandering river. (See Table 17-D on 
existing project and Table 17-B for authorizing legislation.) 
Local cooperation. In addition to usual requirements, 
local interests are responsible for all highway, bridge, and 
public utility relocations or replacements required in construction 
of project. Local interests will also be required to 
comply with requirements of Section 221, 1970 Flood Control 
Act and PL 91-646 Uniform Relocation Assistance Act 
of 1970. Total costs for all requirements for completed 
Albuquerque unit under terms of project authorization 
were $75,000. There were no non-Federal costs in connection 
with construction of Cochiti to Rio Puerco unit 
17-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
of floodway. Espanola Valley unit is in the deferred category. 
The city of Espanola or Santa Clara Pueblo has not 
given indication they plan positive action to solve the 
flooding problem. For more details see page 17-8 of Annual 
Report for 1980. 
Operations and results during fiscal year. There 
were $3,919,200 in flood damages prevented by the completed 
floodway project during FY 1983. Estimated total 
accumulated flood damages prevented by the floodway 
project through FY 1983 amounted to $40,469,000. The 
peak flow of the Rio Grande through the middle valley 
was 7,700 c.f.s. at Albuquerque on June 10, 1983. The 
peak at San Acacia was 6,980 c.f.s. 
Condition at end of fiscal year. Construction of 
Albuquerque unit and Cochiti to Rio Puerco units of Rio 
Grande Floodway project is complete. San Acacia to 
Bosque del Apache unit is deferred for restudy. The 
Truth or Consequences (Hot Springs) unit was reclassified 
to the active category on July 18, 1973, based on a 
letter of intent to cooperate from the city of Truth or 
Consequences dated May 31, 1973. The Espanola Valley 
unit was reclassified to deferred category on 17 October 
1973. 
9F. TRUTH OR CONSEQUENCES 
UNIT, NM 
Location. Vicinity City of Truth or Consequences, 
New Mexico. 
Existing project. Plan of improvement will include 4 
miles of 20-foot-high levees with positive seepage control, 
an interior drainage system, and 5 miles of diversion 
channels. The diversion channels would be required for 
control of floods on tributary arroyos at and in the vicinity 
of Truth or Consequences. Estimated Federal cost is 
not available pending project reformulation. (See Table 
17-B for authorizing legislation.) 
Location cooperation. Section 2 Flood Control Act 
of 1938 applies. 
Letters of intent have been received from the City of 
Truth or Consequences (dated June 8, 1983) and the 
County of Sierra (dated June 8, 1983). 
Operations and results during fiscal year. Preconstruction 
planning was initiated in FY 1979 and continued 
during FY 1983. 
10. SANTA FE RIVER AND ARROYO 
MASCARAS, NM 
Location. Santa Fe, New Mexico, and Vicinity, within 
Santa Fe County, First Congressional District. (See Geological 
Survey map, Santa Fe South and McClure Reservoir 
quadrangles, scale 1:24,000.) 
Existing project. The recommended plan is located in 
Santa Fe, capital of New Mexico. The city of Santa Fe is 
experiencing new growth and development throughout 
the city. The confluence of Arroyo Mascaras with the 
Santa Fe River is near the downtown area of Santa Fe. 
Studies to date indicate that the Arroyo Mascaras segment 
of the project is not justifiable. Accordingly, a report 
recommending no Federal construction on the Arroyo 
Mascaras portion of the project was approved by the Division 
Engineer on 1 October 1979. The authorizing legislation 
for the project prohibits construction of any 
impoundment on the Santa Fe River above the existing 
Nichols Dam and therefore precluded further consideration 
of the originally recommended Granite Point Dam 
as a means of providing flood damage protection for the 
Santa Fe River. Accordingly, the project is being reformulated. 
The most likely plan of improvement for the 
Santa Fe River will provide 100-year flood protection by 
combination of channel modifications, within the existing 
channel, replacement and/or modification of 6 
bridges; and construction of low architecturally treated 
walls, to preserve the unique river park setting. Estimated 
cost of the reformulated project is approximately 
$6,430,000 (base estimate October 1, 1983). 
Local cooperation. Section 2 Flood Control Act of 1938 
applies. Further requirements include an agreement with 
the local interests to prevent encroachments in the existing 
Santa Fe River channel below any dam project and 
maintain a minimum channel capacity of 5,000 c.f.s.: and 
bear all costs of operation and maintenance of the flood 
control works presently estimated at $5,500 on an average 
annual basis. Requirements are described in full on 
page 17-8 of Fiscal Year 1981 Report. 
Operations and results during fiscal year. Studies 
were suspended in FY 1983 due to withdrawal of local 
support.
SANTA ROSA DAM AND LAKE, NM 
Location. Lake is in Guadalupe County, on Pecos 
River, at river mile 766.4 approximately 7 miles north of 
Santa Rosa, NM (See U.S. Geological Survey map, Corazon, 
NM, sheet, scale 1:125,000.) 
Existing project. Project operation began in November 
1979. Authorized plan of improvement consists of an 
earth and rock fill dam 1,950 feet long and 212 feet maximum 
height above the streambed. Project purposes are 
flood control, irrigation and sediment retention. An 
unlined, open rock cut about 1,000 feet back from the left 
abutment serves as an uncontrolled spillway. The outlet 
works, located in the left abutment, consists of a control 
tower, intake structure with gates, and a 10-foot diameter 
concrete lined tunnel with a terminal flip bucket 
energy dissipater. Storage capacity at the spillway crest 
is 447,100 acre-feet which includes 80,100 acre-feet sediment 
reserve, 200,000 acre-feet irrigation and 167,000 
acre-feet flood control storage. Surface area of the reservoir 
at the spillway crest is 10,685 acres. Contributing 
drainage area at the dam site is 2,434 square miles. 
For a more detailed report of the authorized project 
including the modification to existing Summer Lake see 
page 17-8 of fiscal year 1981 Annual Report. For authorizing 
legislation see page 17-14 of fiscal year 1981 Annual 
Report. 
Local cooperation. In addition to first costs, operation 
and maintenance of both reservoirs will be responsibility 
of Federal Government; however, Carlsbad Irrigation 
District will be required to contribute to operation and 
17-6
11.

ALBUQUERQUE, NM, DISTRICT 
maintenance costs an annual amount equal to what they 
now pay toward Sumner Lake. Carlsbad Irrigation District 
also will be required to agree to use of Sumner Lake 
for flood-control purposes. Because they will realize 
equivalent benefits from storage capacity in Santa Rosa 
Dam and Lake, they will be required to continue to fulfill 
their repayment obligation. The New Mexico Division 
of Parks to manage Santa Rosa Dam and Lake. Activities 
include camping, picnicking, boating and hiking. 
For more requirements and details on final approval 
in 1974, for transfer of irrigation storage from Sumner 
Lake to Santa Rosa Dam and Lake (formerly Los Esteros 
Lake) see page 17-5 of Annual Report for 1980. 
Operations and results during fiscal year. The 
project was completed in late 1979. Reservoir operation 
for irrigation was started in March 1980 and the reservoir 
was operated for irrigation purposes only during 
FY 1983. No flood damages were prevented during FY 
1983. Pool elevation at start of fiscal year was 4,716.66 
feet with storage of 29,308 acre-feet. Total releases for 
the fiscal year were 108,233 acre-feet. Pool elevation on 
September 30, 1983 was 4,695.62 feet with a storage of 
8,734 acre-feet. The maximum elevation was 4,738.43 
feet with a storage of 79,450 acre-feet on June 9, 1983. 
There was 680 acre-feet of sediment deposition during 
the fiscal year. Sediment damages prevented during the 
fiscal year were $76,200. Releases attributed to irrigation 
benefits were 84,699 acre-feet. Irrigation benefits 
for the fiscal year were $296,400 with an accumulative 
total of $670,800 through FY 1983. 
Condition at end of fiscal year. Construction contract 
for the recreation area was awarded in September 
1979 and completed in October 1980. Design studies for 
spillway modification were initiated in FY 1979 and construction 
was completed in FY 1982. 
12. SMITH CREEK, CO 
Location. Smith Creek, Pleasant View Estates, El1 
Paso County, CO is located 15 miles north of Colorado 
Springs, CO. (See Geological Survey Map, Monument CO 
quadrangle scale 1:24,000.) 
Existing project. The construction of 8 gabion weirs 
in the channel on Smith Creek to protect existing sewage 
lagoons for the Pleasant View Estates during flood 
flows. The upper most gabion weir 35 feet in width, would 
act as a collection structure, the remaining 7 weirs, 15 
feet in width would reduce flood flows to about 3 feet per 
second during flood design stage. 
Local cooperation. Section 3 FC Act of June 22, 1936 
applies. Local Interests are in compliance with Section 
221, 1970 FC Act and PL 91-646 Uniform Relocation Act 
of 1970. 
Operations and results. N/A 
Condition at the end of the year. Construction was 
started in June 1982 and was completed in December 
1982. 
13. TRINIDAD LAKE, CO 
Location. On Purgatoire River about 161 miles above 
its junction with Arkansas River. Project is about 4 miles 
upstream from city of Trinidad, CO. (See Geological Survey 
map. Trinidad, CO, quadrangle, scale 1:24,000.) 
Existing project. Consists of an earthfill dam 6,610 
feet long, with a maximum height of 200 feet above 
streambed, an uncontrolled spillway 1,000 feet wide in 
left abutment, and a 10-foot diameter, gate-controlled conduit 
in right abutment with discharge capacity of 5,870 
c.f.s. with water surface at top of flood control pool. Reservoir 
provides for storage of 60,000 acre-feet for flood 
control, 39,000 acre-feet for sediment, 20,000 acre-feet 
irrigation, and 4,500 acre-feet for recreation, a total of 
123,500 acre-feet. Reservoir controls a drainage area of 
671 square miles and will be operated for flood and sediment 
control, irrigation, and recreation purposes. For 
authorizing legislation see page 17-14 of fiscal year 1981 
Annual Report. 
Local cooperation. Assurances of local cooperation 
received from City of Trinidad and Purgatoire River 
Water Conservancy District were formally accepted May 
11, 1967, after execution of irrigation repayment contract. 
For complete details of requirements and costs pertaining 
to the execution of the irrigation repayment contract 
and the addition of permanent storage for recreation facilities 
see page 17-9 of fiscal year 1980 Annual Report. 
Operations and results during fiscal year. The 
reservoir was operated for flood control and irrigation 
releases during the fiscal year. On October 1, 1982 the 
pool elevation was 6,206.71 feet with a corresponding 
storage of 43,358 acre-feet. The maximum pool elevation 
was 6,222.64 feet with a corresponding storage of 61,797 
acre-feet on April 25 & 26, 1983. On September 30, 
1983, the pool elevation was 6,204.58 feet with a corresponding 
storage of 41,208 acre-feet. Sediment deposition 
during FY 1983 was 873 acre-feet. Sediment damages 
prevented during FY 1983 was $326,500. Accrued sediment 
benefits are $1,152,300. Irrigation benefits for FY 
1983 were $87,100. Accrued irrigation benefits through 
FY 1983 were $664,800. Irrigation releases for the year 
were 22,157 acre-feet. 
Conditions at end of fiscal year. The project was 
placed in operation in 1977. The recreation facilities 
were completed in 1980. The Dam Safety Assurance Contract 
was awarded in September 1982. Project features 
are in good condition and in operation. 
14. TWO RIVERS DAM, NM 
Location. About 14 miles southwest of Roswell, NM, 
on Rio Hondo and Rocky Arroyo. Rio Hondo is formed at 
confluence of Rio Ruidoso and Rio Bonito, near village of 
Hondo, NM, in foothills region of Sierra Blanca in southeastern 
part of Lincoln County, NM, and flows generally 
easterly to its confluence with Pecos River near Roswell, 
NM (See Geological Survey map, Hondo Reservoir quadrangle, 
scale 1:24,000.) 
Existing project. Diamond "A" Dam is an earthfill 
structure, 4,885 feet long and 98 feet high, with a gated 
outlet. Rocky Dam is an earthfill structure 2,940 feet long 
and 118 feet high with an uncontrolled outlet. No provision 
is made for storage except for flood control. Flood 
17-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
releases will be controlled, so that flows through Roswell 
will not exceed channel capacity Rio Hondo which is about 
1,000 c.f.s. Capacity of Two Rivers Reservoir at spillway 
crest is 168,000 acre-feet, of which 18,000 acre-feet are 
provided for sediment reserve. Together these dams regulate 
runoff from 1,027 square miles of drainage area. 
For details of completed improvement and authorizing 
legislation see page 17-18 of Annual Report for 1973. 
Local cooperation. Section 2 Flood Control Act of 
1938 applies and compliance is satisfactory. 
Operations and results during fiscal year. Routine 
maintenance and operation continued. The reservoir was 
empty on October 1, 1982. The maximum flow was 5,300 
c.f.s. on October 1, 1983. There were $2,335,300 in flood 
damages prevented during 1983. Sediment damages prevented 
were $10,500. Estimated total accumulated flood 
and sediment damages prevented through FY 1983 were 
$5,913,400. There were 94 acre-feet of sediment deposition 
during FY 1983. The accrued sediment benefits 
through FY 1983 are $433,000. 
Condition at end of fiscal year. Project is complete 
and was placed in operation July 1963. Project features 
are in good condition and in operation. 
15. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Included under this heading is inspection of completed 
flood control projects transferred to local interests for 
operation and maintenance. Projects in Texas, Colorado, 
and New Mexico were inspected. Federal costs for the 
fiscal year were $78,559. 
16. SCHEDULING FLOOD CONTROL 
RESERVOIR OPERATIONS 
Pursuant to Section 7, Flood Control Act of 1944, three 
projects are operated by others for flood control. These 
projects are Platoro, Pueblo, and Sumner. 
Platoro Dam on Conejos River above the town of 
Platoro, Conejos County, CO controls runoff from 40 
square miles of high mountain area. Authorized purposes 
are irrigation storage and flood control. Total storage is 
60,000 acre-feet with the top 6,000 acre-feet for flood 
control. The 54,000 acre-feet is dual purpose storage with 
flood-control on a forecast basis during spring runoff. 
Platoro Dam was authorized by Interior Appropriation 
Act of 1941, (see H Doc 693, 76th Cong., 3rd Sess.) Construction 
of project was completed by Water and Power 
Resources Service (Bureau of Reclamation) in FY 1952. 
On October 1, 1982, storage in Platoro reservoir was 
19,977 acre-feet; elevation 9,982.9 feet. There was no flood 
control releases during FY 1983. Maximum storage of 
19,977 acre-feet, elevation 9,982.9 feet occurred on October 
1, 1982. On September 30, 1983, storage was 14,442 
acre-feet, elevation 9,972.5 feet. Peak flow at Mogote gage 
was 2,550 c.f.s. on June 19, 1982. No flood damages were 
prevented by the project during the FY 1983. Total flood 
damages prevented to date are at $2,714,400. Total cost 
for activity during FY 1983 was $11,867. 
Pueblo Dam is part of the Fryingpan-Arkansas project 
which was authorized under Public Law 87-590, 87th 
Congress, HR 2206 on August 16, 1962. The project was 
completed in August 1975. Pueblo is operated by the 
Water and Power Resources Services and is located at 
river mile 1,293.7 on the Arkansas River in Pueblo County 
Colorado. Pueblo reservoir has 27,000 acre-feet exclusive 
flood space and 66,000 acre-feet joint use space. 
Operation of Pueblo Reservoir began on February 10, 
1974. Storage on October 1, 1982 was 61,237 acre-feet, 
elev. 4,816.16 feet. Maximum storage during the year was 
261,925 acre-feet, elev. 4879.94 feet on August 5, 1983. 
Storage on September 30,1983 was 221,181 acre-feet, elev. 
4870.61 feet. There were $46,800 in flood damages prevented 
in FY 1983. Total cost for FY 1983 activity was 
$11,324. Total flood damages prevented to date are 
$1,489,900. 
Sumner Dam is located on the Pecos River at river mile 
710.8 in DeBaca County, New Mexico. Sumner Dam was 
authorized as Alamogordo Dam by the Secretary of the 
Interior under a Finding of Feasibility approved by the 
President of the USA on 6 November 1935, under the 
Federal Reclamation laws. The original project was completed 
in 1937. Modification work of raising the dam 16 
feet, adding a spillway and limiting the service spillway 
floor to 56,000 c.f.s. was completed in 1957. A twentyfour 
inch bypass line was installed in 1977 to pass flows 
less than 100 c.f.s. Storage on October 1, 1982 was 11,809 
acre-feet, elevation 4,239.4 feet. Maximum storage for 
FY 1983 was 38,905 acre-feet, elevation 4,256.2 feet on 
April 17, 1983. Storage on September 30, 1983 was 5,512 
acre-feet, elevation 4,231.3 feet. Total cost for FY 1983 
activity was $9,776. 
17. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
See Table 17-E. 
FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control activities pursuant to section 205, 
Public Law 858, 80th Congress, as amended (preauthorization). 
Costs during FY 1983 were: Belen, NM, Rio Grande, 
$61,892; Santo Domingo Pueblo, NM, $23,420; Starksvill, 
CO, $6,105. 
Emergency flood control activities repair, flood 
fighting, and rescue work. (Public Law 99, 84th 
Cong., and antecedent legislation.) 
Federal costs for fiscal year 1983 were $139,179 for 
advance preparation, and $2,471 for flood emergency operations, 
and $9,284 for repair and restoration. 
Emergency bank protection (Sec. 14, 1946 Flood 
Control Act, Public Law 526, 79th Cong.) 
Federal costs during FY 1983 were: 4th Street Bridge, 
Canon City, CO, $8,515; Brazos River, NM, $5,822; Rio 
Grande, Alamosa, CO, $12,880; Fountain Creek, Colorado 
17-8
18.

ALBUQUERQUE, NM, DISTRICT 
Springs, CO, $16,000; Fountain Creek, Pinon Bridge, 
Pueblo, CO, $8,692; Fountain Creek, Fountain, CO, 
$26,717; HWY 1-25, Fountain Creek, CO, $23,074; King 
Arroyo, La Junta, CO, $54,562; Lyons Estates, Dona Ana, 
NM, $7,073; Raynolds Ave. Bridge, Canon City, CO, 
$44,938; HWY 9, Canon City, CO, $17,069; Fountain 
Creek, El Paso County, CO, $8,903; Fountain Creek, 
Security, CO, $24,812; HWY 101, Las Animas, CO, 
$19,502; Stratmoor Hills, Colorado Springs, CO, $12,954; 
Truchas Creek, Fort Sumner, NM, $11,786; US HWY 25, 
Colorado Springs, CO, $1,044. 
General Investigations 
19. SURVEYS 
Costs for the fiscal year were $695,633 for flood damage 
TABLE 17-A 
prevention studies, $9,980 for special studies (coordination 
studies with other agencies), and $441,738 for preauthorization 
studies, Phase I (Arkansas River and 
Tributaries above John Martin Dam, Colorado, $324,701 
and Rio Grande and Tributaries (Rio Puerco/Rio Salado), 
New Mexico, $117,036). 
20. COLLECTION AND STUDY 
OF BASIC DATA 
Fiscal year costs were $130,402 for flood plain management 
and technical services. 
Hydrologic studies involving collection and study of 
basic data, such as stream flow data, collection of suspended 
sediment samples, recording rain gage data, hydrometeorological 
studies, and sedimentation studies 
continued. Costs during the fiscal year were $11,466. 
See Total Costs 
Section to 
In Text Project Funding FY 80 FY 81 FY 82 FY 83 Sept. 30, 1983 
1. Albuquerque New Work 
Diversion Channels 
Project, NM 
(Federal Funds) 
(Contributed 
Funds) 
(Other Contributed 
Funds) 
2. Cibolo, TX 
3. Conchas Lake, NM 
4. El Paso, TX 
5. Highway 12, CO 
6. Holly, CO 
7. John Martin 
Reservoir, CO 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
- 17,268,450 
- 17,268,450 
518,356 
518,356 
854,644 
854,644 
2,170 
69,130 
68,571 
23,900 1,020,000 
215 1,001,799 
503 
32,976 
15,000 1,123,900 
57,705 1,123,900 
- -58,423 13,765,3861 
14,589 2,648 13,789,0591 
532,000 579,000 691,000 1,364,200 10,124,172 
545,723 628,895 602,238 710,414 9,303,059 
3,931,000 5,563,000 6,878,000 5,150,000 43,029,294 
3,315,190 4,447,994 5,542,583 6,026,141 40,716,654 
1,359,900 
1,406,623 
29,610 
92,398 
15,000 
8,960 
103,583 
21,368 
37,001 
15,000 
9,102 
68,454 
90,500 
102,319 
120,500 
120,381 
44,000 2,016,400 
68,804 2,012,942 
39,000 15,485,3582 
3,601 15,449,9592 
1,187,000 726,700 859,000 712,500 11,784,700 
964,294 1,090,652 793,550 684,579 11,641,768 
17-9 
COST AND FINANCIAL STATEMENT

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 17-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section 
In Text Project 
8. Lamed, Pawnee 
River, KS 
9. Rio Grande Basin, NM 
9A. Abiquiu Dam, NM 
9B. Cochiti Lake, NM 
9C. Galisteo Dam, NM 
9D. Jemez Canyon 
Dam, NM 
9E. Rio Grande, 
Floodway, T. or C. 
Unit, NM 
10. Santa Fe River 
and Arroyo 
Mascaras 
11. Santa Rosa Dam 
& Lake, NM 
12. Smith Creek, CO 
13. Trinidad Lake, CO 
14. Two Rivers Dam, NM 
Funding 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
26 
23t 
4,77 
4,52; 
27! 
22 
FY80 
65,000 
54,040 
2,453,000 
2,168,642 
534,000 
481,865 
2,380,000 
739,072 
1,033,800 
1,259,753 
87,000 
119,943 
A 27 
4,770 - 
5,000 246,000 
1,243 293,304 
- 150,000 
- 167,964 
0,000 140,000 
8,817 112,864 
2,000 1,570,000 
2,362 2,249,340 
8,000 323,000 
6,714 369,106 
- 17,500 
- 10,511 
1,447,000 
1,789,677 
315,000 
420,326 
-70
73 
167,000 
140,381 
119,274 
748,000 
814,676 
146,000 
163,806 
'Includes $3,492,696 maintenance and improvement costs 
and $869,978 for emergency relief, excludes $2,279,326, cost of 
initiating project under the authority of Emergency Relief 
Appropriation Act of 1935 and $222,669, the cost for work performed 
with funds transferred to the Corps under Public Works 
acceleration Act of 1962. 
2 Excludes $59,977 emergency relief funds for new work. Includes 
$30,000 for Code 710. 
3 Includes funds for completed Albuquerque and Cochiti to 
Rio Puerco units and for preconstruction planning of Espanola 
Valley unit. Excludes $1,000,011 appropriated funds transferred 
to Bureau of Reclamation under memorandum agreement 
between that agency and the Corps. 
4 Starting in FY 1982, AE&D programs are funded through 
GI appropriations. 
5 Includes funds provided by Jobs Act (PL 98-8 March 24, 
1983) for projects listed in Table 17-F. 
17-10 
r 
FY 81 
1,600,000 
964,616 
13,629 
228,015 
434,000 
596,559 
1,971,819 
988,000 
916,827 
100,000 
112,607 
FY 82 
297,000 
943,111 
28,162 
593,000 
508,427 
84,000 
94,303 
925,000 
883,462 
40,000 
12,027 
136,000 
106,041 
35,000 
4,059 
374,000 
206,379 
92,000 
100,886 
111,000 
127,383 
2,300,000 
1,898,670 
416,000 
386,535 
192,000 
83,664 
1,516,000 
298,985 
383,000 
323,109 
20,000 
2,434 
160,000 
148,098 
FY 83 
200,000 
26,504 
134,000 
33,519 
997,100 
771,334 
109,900 
415,245 
1,578,500 
1,273,598 
10,000 
1,875 
129,000 
123,904 
-20,400 
9,731 
331,100 
320,473 
45,000 
37,505 
39,122 
108,000 
320,612 
507,200 
395,478 
9,500 
123,364 
3,592,000 
4,122,547 
420,000 
390,795 
-2,000 
10,927 
158,100 
137,317 
Total Costs 
to 
Sept. 30, 1983 
2,309,800 
2,108,737 
26,890,128 
26,583,044 
7,815,206 
7,485,211 
97,094,159 
97,031,008 
6,992,800 
6,455,717 
14,270,053 
14,233,955 
1,176,477 
1,139,373 
4,227,747 
4,226,937 
4,686,451 
4,504,681 
5,186,8683-4 
5,206,2233-4 
829,5004 
829,5004 
41,101,562 
40,801,658 
1,539,200 
1,380,575 
219,000 
217,539 
55,714,758 
54,256,470 
2,579,500 
2,470,628 
4,850,869 
4,846,231 
1,619,012 
1,559,782 
44; 
92

ALBUQUERQUE, NM, DISTRICT 
TABLE 17-B AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
In Text Act Project and Work Authorized Documents 
2. June 30, 1948 
as amended. 
4. Oct. 27, 1965 
5. July 24, 1946 
6. June 30, 1948 
as amended. 
8. June 30, 1948 
as amended. 
9. June 30, 1948 
May 17, 1950 
July 14, 1960 
9. June 30, 1948 
and 
May 17, 1950 
9. June 30, 1948 
May 17, 1950 
10. Oct. 22, 1976 
12. July 24, 1946 
CIBOLO, TX 
Consists of right bank levee 0.7 miles long left bank levee 1.4 miles 
long to protect the town of Presidio, TX from a peak flow of 67,000 
c.f.s. on Cibolo Creek. 
EL PASO, TX 
A single-purpose flood control system of detention dams, diversion 
dikes and channels to collect, regulate and discharge arroyo runoff 
in the Rio Grande. Consists of four independent units (NW Area, 
Central Area, and two units, Copper System and Bluff Channel 
of the SE Area.) 
HIGHWAY 12, CO 
Three locations on left bank of Purgatoire River are protected from 
peak flows by Kelner Jacks. 
HOLLY, CO 
Consists of a levee 4.3 miles in length along the left bank of Wild 
Horse Creek to its junction with the Arkansas River thence 
4,300 feet below the confluence. Appurtences include interior 
drainage facilities, closure structures at RR and highway crossings. 
LARNED PAWNEE RIVER, KS 
Consists of a levee 1.9 miles long on the left bank of the Pawnee 
River extending past the confluence of the Arkansas River to a 
point below the municipal sewage plant. Appurtences include 
interior drainage facilities and stop-log structures at Hwy. and 
RR crossings. 
RIO GRANDE BASIN, NM 
Authorized to be appropriated $3,500,000 to be expended by the 
Dept. of the Army for partial accomplishment of approved general 
comprehensive plan for the Rio Grande Basin in NM and Colorado. 
Authorized to be appropriated an additional $39,000,000 for Dept. 
of the Army for prosecution of comprehensive plan for the Rio 
Grande Basin. 
Authorized Cochiti Dam on Rio Grande and Galisteo Dam on Galisteo 
Creek as additions to authorized comprehensive plan for Rio 
Grande Basin (Cochiti Dam was authorized in lieu of Low Chamita 
Dam of Chamita Reservoir Project on Rio Chama under "substitute 
plan"). Also authorized to be appropriated an additional $58,300,000 
or Dept. of the Army for this addition to comprehensive plan for 
the Rio Grande Basin. 
RIO GRANDE FLOODWAY, NM 
Channel rectification, levee enlargement and construction, and bank 
stabilization on Rio Grande between river mile 123 and 394 
(See Table 17D.) 
TRUTH OR CONSEQUENCES (HOT SPRINGS), NM 
Approved comprehensive plan for Rio Grande Basin is set forth in 
the Report of the Chief of Engineers dated April 15, 1948, for flood 
control of Rio Grande Basin. 
In addition to previous authorizations, the completion of the plan 
approved in the Flood Control Act of 1948, for the Rio Grande 
Basin, at an estimated cost of $39,000,000. 
SANTA FE RIVER AND ARROYO MASCARAS, NM 
Consists of flood control improvements on the Santa Fe River, 
excluding any impoundment east of the existing Nichols Dam, 
and channel improvement on Arroyo Mascaras, and non-structural 
measures. 
SMITH CREEK, CO 
Consists of 8 gabion weirs on Smith Creek to protect two sewage 
lagoons from erosion during flood flows on Smith Creek. 
Sec. 205, PL 858, 80th 
Cong. as amended. 
Authorized by C of E 
July 1, 1977 
H. Doc. 207, 89th Cong., 
1st sess. 
Sec. 14, PL 79-526 of 
1946 FC Act. Authorized 
by C of E April 22,1981. 
Sec. 205, PL 858, 80th 
Cong. as amended. 
Authorized by C of E 
Sept. 9, 1977. 
Sec. 205, PL 858, 80th 
Cong. as amended. 
Authorized by C of E 
January 4, 1979 
H. Doc. 243, 81st Cong., 
1st sess. 
Public Law 516, 81st 
Cong., 2nd sess. 
S. Doc. 94, 86th Cong. 
H. Doc. 243, 81st Cong., 
1st sess.' and Public 
Law 516, 81st Cong., 
2nd sess. 
H. Doc. 243, 81st Cong., 
1st sess. 
H. Doc. 243, 81st Cong., 
1st sess. 
Public Law 94-587, 94th 
Cong. 
Sec. 14, PL 79-526 of 
1946 FC Act. Authorized 
by C of E April 22, 1981. 
'Contains latest published maps. 
17-11 
_~r -

TABLE 17-C 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
RIO GRANDE BASIN, NM 
RIO GRANDE BASIN, NM: EXISTING PROJECT 
(See Section 9 of Text) 
Drainage 
Miles Area Total 
Above Nearest (square Estimated 
Project River Mouth Town mile) Description Cost 
Abiquiu Dam Rio Chama 32 Espanola, 2,147 Earthfil 325 feet high, 1,212,000 26,797,0963 
NM acre-feet capacity 
Jemez Canyon Jemez 2 Bernalillo, 1,034 Earthfill 136 feet high, 106,100 4,217,206 
Dam NM acre-feet capacity 
Rio Grande Rio Grande 123 to 3941 - - Channel rectification, levee 25,744,0002 
Floodway enlargement and construction 
Cochiti Lake Rio Grande 3401 Cochiti, 11,695 Earthfill 251 feet high, 596,300 96,900,000 
NM acre-feet capacity 
Galisteo Dam Galisteo Creek 8 Waldo, 596 Earthfill 158 feet high, 89,000 14,340,280 
NM acre-feet capacity 
'River mile 0 is at intersection of New Mexico-Texas State Line with international boundary at El Paso, Texas. 
2Does not include non-Federal costs. 
Includes $5,383,000 major rehabilitation, $138,900 for recreation facilities. 
RIO GRANDE FLOODWAY, NM: 
TABLE 17-D EXISTING PROJECT 
(See Section 9E of Text) 
Location Estimated 
Reach. (river miles)' Cost 
Truth or Consequences unit (formerly Hot Springs) 123 to 129 $14,200,000 
San Acacia to Bosque del Apache unit 155 to 226 6,200,000 
(1960)2 
Cochiti to Rio Puerco unit (not including Albuquerque unit) 236 to 340 2,658,0004 
Albuquerque unit 286 to 305 3,130,0004 
Espanola Valley unit 366 to 394 (1970)5 
456,0002 
'River mile 0 being at intersection of New Mexico-Texas State line with international boundary at El Paso, Texas. 2Deferred for restudy. 
31n addition, $1,650,000 incurred by the Bureau of Reclamation in this reach. 
4In addition, $75,000 incurred by local interest in this reach. 
5In addition, estimated cost to local interests is $69,000 (1970). 
TABLE 17-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to September 30, 1983 
Full Report 
See Annual Operation & 
Project Report For Construction Maintenance 2 
Alamogordo diversion channel, Tularosa (closed) Basin, New Mexico 4 1966 189,356 - 
Alpine, Texas3 1977 130,488 - 
Colorado Springs, Fountain que Bouille River, CO 
(Templeton Gap Floodway)' 1959 881,262 - 
Creede, Willow Creek, CO (floodway)' 1952 219,789 - 
Dodge City, KS2 1980 6,323,420 - 
Las Animas, CO2 1980 4,956,000 - 
Las Cruces, NM2 1980 4,752,310 - 
Pecos, Texas3 1977 480,273 - 
Pinon Canyon Dam, Trinidad, CO (Sec. 212)' - 130,678 - 
Pueblo Arkansas River, CO (floodway levee extension)' 1954 201,958 - 
Socorro diversion channel, tributaries of Rio Grande, New Mexico' 1965 2,259,328 - 
'Completed. 2Responsibility of local interests. 3Inactive. 4Deferred. 
17-12

AL 
JOBS A 
TABLE 17-F 
Project 
Alamosa, CO - Rio Grande, Sec. 14 
Canon City, CO - Four mile Cr., Hwy 9, Sec. 14 
Canon City, CO - Raynolds Ave. Bridge, Sec. 14 
CO Springs, CO - Stratmoor Hills, Sec. 14 
CO Springs, CO - U.S. Hwy 25, Sec. 14 
Ft. Sumner, NM - Truchas Cr., Sec. 14 
Fountain, CO - Fountain Cr., Sec. 14 
La Junta, CO - King Arroyo, Sec. 14 
Las Animas, CO - St. Hwy 101, Sec. 14 
Security, CO - Fountain Cr., Sec. 14 
Abiquiu Dam, N.M. 
Cochiti Lake, N.M. 
Conchas Lake, NM 
Galisteo Dam, NM 
Jemez Canyon Dam, NM 
John Martin Reservoir, CO 
Santa Rosa Dam and Lake, NM 
Two Rivers Dam, NM 
iBUQUERQUE, NM, DISTRICT 
CT CONTRACTS AWARDED 
DURING FY 1983 
BUDQUCUEORRINQNUTGER, ANFMCY,T D1SI9S 8TA3RWICATRDED 
17-13 
Funding 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
FY 1983 
113,000 
2,781 
75,000 
1,288 
35,000 
34,988 
97,000
0 
218,546 
1,044 
88,000 
1,786 
170,000 
26,716 
45,000 
44,562 
81,000 
1,001 
177,000 
24,812 
134,000 
5,204 
383,100 
196,295 
50,000
0 
537,500 
358,517 
33,000 
1,751 
721,200 
89,670 
15,000 
124 
58,100 
11,640 
39,000 
3,601 
59,500 
23,927 
41,200 
14,861 
8,100 
2,714

LITTLE ROCK, AR, DISTRICT* 
This District comprises northern, western, and southwestern 
portions of Arkansas and a portion of southern 
Missouri embraced in drainage basins of Arkansas River 
and tributaries above and exclusive of Pine Bluff, AR, 
and below mouth of Poteau River, near Fort Smith, AR, 
drainage basins of the Arkansas portion of Little River 
and tributaries above its mouth near Fulton, AR, and 
drainage basins of White River and tributaries above 
Peach Orchard Bluff, AR. In addition, Little Rock 
District has responsibility for planning, design, construction, 
and operation and maintenance of that portion 
of McClellan-Kerr Arkansas River Navigation System 
below Pine Bluff. Memphis District is responsible for 
navigation maintenance on White River below Newport, 
AR, and mouth of Wild Goose Bayou. White River 
downstream from mouth of Wild Goose Bayou is a part of 
McClellan-Kerr Arkansas River Navigation System. 
IMPROVEMENTS 
Navigation Page 
1. Arkansas River Basin, AR, OK, and KS .... 18-2 
2. Bank Stabilization & Channel 
Rectification AR .......................... 18-2 
3. David D. Terry Lock and Dam 
(No. 6), AR ........ ........................ 18-2 
4. Lock and Dam No. 2, AR .................. 18-3 
5. Lock and Dam No. 3, AR ................ 18-3 
6. Lock and Dam No. 4, AR ................. 18-3 
7. Lock and Dam No. 5, AR ................. 18-3 
8. Lock and Dam No. 9, AR .................. 18-3 
9. Lock and Dam No. 13, AR ................ 18-3 
10. Maintenance and Repair Fleet and 
Marine Terminals, AR .................... 18-3 
11. Murray Lock and Dam (No. 7), AR ........ 18-3 
12. Norrell Lock and Dam (No. 1) and 
Entrance Channel, AR .................... 18-3 
13. Toad Suck Ferry Lock and Dam 
(No. 8), AR ............................... 18-4 
14. Other Authorized Navigation Projects ..... 18-4 
Flood Control 
15. Little River Basin (Little Rock District), 
A R ....................................... 18-4 
16. White River Basin (Little Rock District) 
AR & MO ................................ 18-4 
17. Blue Mountain Lake, AR .................. 18-5 
18. Clearwater Lake, MO ..................... 18-5 
19. DeQueen Lake, AR ....................... 18-5 
20. Dierks Lake, AR ......................... 18-5 
21. Gillham Lake, AR ........................ 18-6 
22. Millwood Lake, AR ....................... 18-6 
23. Nimrod Lake, AR ........................ 18-6 
24. Pine Mountain Lake, AR .................. 18-6 
25. Inspection of Completed Flood 
Control Projects ........................... 18-6 
26. Other Authorized Flood Control Projects .... 18-7 
Flood Control (cont) 
27. Flood Control Work under Special 
Authorization ............................. 18-7 
Multiple-Purpose Projects Including Power 
28. Beaver Lake, AR ......................... 18-7 
29. Bull Shoals Lake, AR ..................... 18-7 
30. Dardanelle Lock and Dam (No. 10), AR ..... 18-7 
31. Greers Ferry Lake, AR ................... 18-8 
32. Norfork Lake, AR ........................ 18-8 
33. Ozark-Jeta Taylor Lock and Dam 
(No. 12), AR .............................. 18-8 
34. Table Rock Lake, MO ..................... 18-8 
General Investigations 
35. Surveys ................................... 18-9 
36. Collection and Study of Basic Data ....... 18-9 
37. Advance Engineering and Design .......... 18-9 
Tables 
Table 18-A 
Table 18-B 
Table 18-C 
Table 18-D 
Table 18-E 
Table 
Table 
Table 
18-F 
18-G 
18-H 
Table 18-I 
Table 
Table 
Table 
18-J 
18-K 
18-L 
Table 18-M 
Cost & Financial Statement ...... 18-10 
Authorized Legislation ........... 18-13 
Other Authorized 
Navigation Projects .............. 18-15 
Not Applicable 
Other Authorized Flood 
Control Projects ................. 18-16 
Not Applicable 
Deauthorized Projects ............ 18-17 
Arkansas River Basin; AR, OK, 
and KS: Navigation .............. 18-18 
Arkansas River Basin; AR, OK, 
and KS: Lakes .................. 18-21 
Little River Basin, AR ........... 18-22 
White River Basin, AR and MO ... 18-23 
Flood Control Work Under 
Special Authorization ............. 18-24 
Jobs Act Contracts Awarded 
During FY 83 ................... 18-25 
18-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Navigation 
1. ARKANSAS RIVER BASIN, AR, 
OK, AND KS 
Location. Arkansas River rises in Rocky Mountains 
near Leadville, CO, and flows southeastward 1,396 miles 
through Colorado, Kansas, Oklahoma, and Arkansas to 
join Mississippi River 559 miles above Head of Passes, 
LA. (See Geological Survey state maps, 1:24,000, and 
flood control and navigation maps of Mississippi River, 
Cairo, IL, to Gulf of Mexico, 1970 edition scale 1:62,500.) 
Previous projects. For details see page 1066, Annual 
Report for 1932, and pages 744, 864, and 881, Annual 
Report for 1943. 
Existing project. Provides for improvement of Arkansas 
River Basin by construction of coordinated developments 
for navigation, hydroelectric power, flood control, 
water supply, sediment control, recreation, and fish 
and wildlife propagation. McClellan-Kerr Arkansas 
River Navigation System provides a channel of 9 feet 
deep and 445.3 miles long, beginning at mouth of White 
River, which enters Mississippi River 599 miles above 
Head of Passes, LA, thence 9.8 miles upstream to mouth 
of Wild Goose Bayou; thence 9.2 miles by a land cut, 
designated as Arkansas Post Canal to mile 42 (1943 
survey) on Arkansas River; thence 376.0 miles along 
channel of latter stream to mouth of Verdigris River at 
navigation mile 395.0; thence 50.3 miles up Verdigris 
River to head of navigation at Catoosa, OK Waterway is 
canalized throughout its length by 17 locks and dams 
with total lift of 420 feet. Dardanelle, Ozark-Jeta Taylor, 
Robert S. Kerr, and Webbers Falls are multiple-purpose 
projects including power. Lock chambers are 110 by 600 
feet. A minimum channel width of 150 feet is provided 
for Verdigris River, 225 feet for San Bois Creek, 250 feet 
for Arkansas River, and 300 feet for Arkansas Post Canal 
and White River. Other coordinated developments consist 
of 15 lakes, of which 13 are in Tulsa District, Kansas 
and Oklahoma, and two in Little Rock District. Pertinent 
data and estimated Federal cost are summarized in 
Tables 18-H and 18-I, and Arkansas River Basin; AR, 
OK, and KS: Navigation Lakes. For authorization see 
Table 18-B, Authorizing Legislation. 
Local cooperation. For McClellan-Kerr Arkansas 
River Navigation System, local interests must provide 
adequate terminal and transfer facilities and bear increased 
cost of maintenance and operation of all altered 
rail and highway routes, including bridges and appurtenances, 
utilities, and other existing improvements, 
other than federally owned. For lakes see requirements 
for each individual lake. 
Terminal faelities. Public port facilities were in 
operation at Pine Bluff-Jefferson County, Little Rock, 
and Fort Smith, AR, and Muskogee and Catoosa (Tulsa- 
Rogers County), OK. Port authorities have been organized 
to develop public facilities at North Little Rock, 
Dardanelle-Russellville, Morrilton, Clarksville, Ozark 
and Van Buren, AR, and Sallisaw, OK. Private and 
commercial port facilities are complete and in operation 
or being built at 32 locations in Arkansas and at 19 
locations in Oklahoma along the improved waterways. 
Operations and results during fiscal year. Blue 
Mountain, Canton, Dardanelle Lock and Dam (No. 10), 
Dardanelle Marine Terminal, David D. Terry Lock and 
Dam (No. 6), Elk City, Eufaula, Fall River, Fort Gibson, 
Keystone, W. D. Mayo Lock and Dam (No. 14), Chouteau 
Lock and Dam (No. 17), Newt Graham Lock and Dam 
(No. 18), Robert S. Kerr Lock and Dam and Reservoir 
(No. 15), Webbers Falls Lock and Dam (No. 16) and 
Oologah; Locks and Dams Nos. 2, 3, 4, 5, 9, and 13. 
Markham Ferry, Murray Lock and Dam (No. 7), 
Nimrod, Norrell Lock and Dam (No. 1), Ozark-Jeta 
Taylor Lock and Dam (No. 12), Pensacola, Pine Bluff 
Marine Terminal, Robert S. Kerr Marine Terminal, 
Tenkiller Ferry, Toad Suck Ferry Lock and Dam (No. 8), 
Toronto, and Wister were in operation. Construction is 
complete on bank stabilization. For details of McClellan- 
Kerr Arkansas River Navigation System and lakes in 
Oklahoma and Kansas, see report of Tulsa District. 
Details of McClellan-Kerr Arkansas River Navigation 
System and lakes in Arkansas are shown on following 
pages. 
Condition at end of fiscal year. See Tables 18-H and 
18-I, Arkansas River Basin; AR, OK, and KS: Navigation/
Lakes for status for individual items, navigation 
project, lakes, and basin plan. The overall project is 99 
percent complete. Remaining work in this District is the 
Holla Bend Closure Structure, land acquisition, Dardanelle 
Office and design of four new items: Bank 
Stabilization in Entrance Channel, Modification to Dam 
No. 2, and Raise North Little Rock Floodwall and Levee. 
2. BANK STABILIZATION & 
CHANNEL RECTIFICATION, AR 
Location. Several bank stabilization and channel 
rectification projects are laid out in various reaches 
extending from fixed point to fixed point on Arkansas 
River from 33.7 to 362 miles above mouth and across the 
Arkansas-White cutoff, a 4- to 5-mile natural channel 
joining Arkansas and White Rivers about 18 and 12 miles 
above their respective mouths. 
Existing project. Bank stabilization and channel 
rectification is a part of McClellan-Kerr Arkansas River 
Navigation System. For a complete description of reach 
and location of each bank stabilization and channel 
rectification project, see the Annual Report FY 81. Total 
Federal cost to date is $119,300,184 for existing project in 
Little Rock District. For authorization see Table 18-B, 
Authorizing Legislation. 
3. DAVID D. TERRY LOCK AND 
DAM (NO. 6), AR 
Location, existing project, local cooperation, and 
terminal facilities. See Section 1. 
Operations and results during fiscal year. Operation 
and maintenance continued. 
Condition at end of fiscal year. Construction began 
in January 1965 and lock and dam was placed in 
operation in August 1968. 
18-2

LITTLE ROCK, AR, DISTRICT 
4. LOCK AND DAM NO.2, AR 
Location, existing project, local cooperation, and 
terminal facilities. See Section 1. 
Operations and results during fiscal year. During 
the high flows on December 4, 1982, 36 barges broke 
loose from their moorings several miles upstream of Dam 
No. 2. Sixteen hit the dam; of these, two went through the 
gates and 14 sank or lodged in and around the gate bays 
on the upstream side of the dam. Removal of these barges 
was accomplished by salvage contract with the U.S. 
Naval Sea Command in February 1983 at a cost of $4.7 
million. The barges which hit the dam damaged several 
of the gates making them inoperable for flow regulation. 
High flows, with the erratic uneven discharge through 
the damaged gates, resulted in considerable scouring of 
the streambed immediately upstream and downstream 
of the dam. Preliminary investigations indicate the cost 
of replacing the scoured material and repair of the gates 
and piers on the dam to be from $4 to $6 million. Routine 
operation and maintenance continued. 
Condition at end of fiscal year. Construction began 
in May 1963. Lock was placed in operation in April 1967 
and dam was placed in operation in March 1968. 
5. LOCK AND DAM NO.3, AR 
Location, existing project, local cooperation, and 
terminal facilities. See Section 1. 
Operations and results during fiscal year. Operation 
and maintenance continued. 
Condition at end of fiscal year. Construction began 
in May 1963 and lock and dam was placed in operation in 
December 1968. 
6. LOCK AND DAM NO.4, AR 
Location, existing project, local cooperation, and 
terminal facilities. See Section 1. 
Operations and results during fiscal year. An 
addition to the resident office was completed in April 
1982 for $214,293. Operation and maintenance continued. 
Condition at end of fiscal year. Construction began 
in May 1964 and lock and dam was placed in operation in 
December 1968. 
7. LOCK AND DAM NO. 5, AR 
Location, existing project, local cooperation and 
terminal facilities. See Section 1. 
Operations and results during fiscal year. Operation 
and maintenance continued. 
Condition at end of fiscal year. Construction began 
in November 1964 and lock and dam was placed in 
operation in December 1968. 
8. LOCK AND DAM NO. 9, AR 
Location, existing project, local cooperation, and 
terminal facilities. See Section 1. 
Operations and results during fiscal year. Operation 
and maintenance continued. 
Condition at end of fiscal year. Construction began 
in April 1965 and lock and dam was placed in operation 
in July 1969. 
9. LOCK AND DAM NO. 13, AR 
Location, existing project, local cooperation, and 
terminal facilities. See Section 1. 
Operations and results during fiscal year. Operation 
and maintenance continued. 
Condition at end of fiscal year. Construction began 
in October 1965 and lock and dam was placed in 
operation in April 1969. Bridge across dam was completed 
in July 1968. 
10. MAINTENANCE AND REPAIR 
FLEET AND MARINE 
TERMINALS, AR 
Location, existing project, local cooperation, and 
terminal facilities. See Section 1. 
Operations and results during fiscal year. Operation 
and maintenance continued. 
Condition at end of fiscal year. Construction of Pine 
Bluff Marine Terminal began March 1968 and it was 
placed in operation in April 1969. Construction of Dardanelle 
Marine Terminal began June 1968 and it was 
placed in operation in November 1969. 
11. MURRAY LOCK AND DAM 
(NO. 7), AR 
Location, existing project, local cooperation, and 
terminal facilities. See Section 1. 
Operations and results during fiscal year. Recreation 
facilities are complete except for cost sharing 
items under the 710 program. Operation and maintenance 
continued. 
Condition at end of fiscal year. Construction began 
in November 1964 and lock and dam was placed in 
operation in October 1969. 
12. NORRELL LOCK AND DAM 
(NO. 1) AND ENTRANCE 
CHANNEL, AR 
Location, existing project, local cooperation, and 
terminal facilities. See Section 1. 
Recommended modifleation. A Supplement to the 
General Design Memorandum on the Entrance Channel 
presenting the results of design and planning studies to 
modify the existing entrance channel was submitted in 
June 1981 and approved in August 1981. The recommended 
modification would consist of construction of 
additional contraction works to relieve restrictions to 
navigation in this reach of the waterway during low-flow 
conditions on the White River and low stages on the 
Mississippi River. The project is estimated to cost 
18-3

REPORT OF THE CHIEF OF ENGINEERS, US. ARMY 1368 
$6 million. Model study of this reach is being tested to 
determine alternatives. 
Operations and results during fiscal year. Operation 
and maintenance continued. 
Condition at end of fiscal year. Construction began 
in May 1963 and lock and dam was placed in operation in 
June 1967. 
13. TOAD SUCK FERRY LOCK AND 
DAM (NO. 8), AR 
Location, existing project, local cooperation, and 
terminal facilities. See Section 1. 
Operations and results during fiscal year. Operation 
and maintenance continued. A contract was awarded 
in June 1980 for construction of the dam spillway, and 
outlet works for a reservoir to provide a source of water 
supply for the city of Conway, AR, which will replace 
existing source adversely affected by construction of the 
McClellan-Kerr Arkansas River Navigation System. 
Estimated cost of the reservoir is $32,944,000. The work 
is complete except for the road relocations, recreation 
facilities, and financial completion of contracts and real 
estate. The facilities will then be turned over to the city of 
Conway to operate and maintain. 
Condition at end of fiscal year. Construction began 
in July 1965 and lock and dam was placed in operation in 
November 1969. 
14. OTHER AUTHORIZED 
NAVIGATION PROJECTS 
See Table 18-C, Other Authorized Navigation Projects. 
Flood Control 
15. LITTLE RIVER BASIN 
(LITTLE ROCK DISTRICT), AR 
Location. Improvements are on Little River and 
tributaries, Arkansas. More definite location of individual 
items is shown in Table 18-J4, Little River Basin. 
Existing project. Part of a six-lake system for flood 
control and other purposes in the Little River Basin. The 
system consists of four lakes in Arkansas: Millwood on 
the main stem, Dierks on the Saline River, DeQueen on 
the Rolling Fork River, and Gillham on the Caesatot 
River, and two lakes in Oklahoma Broken Bow on the 
Mountain Fork River and Pine Creek on the Little River. 
Under a District boundary change, effective in October 
1980, the four projects in this system in Arkansas were 
reassigned from the Tulsa District to the Little Rock 
District. 
Local cooperation. Section 2, Flood Control Act of 
1988, and Section 301, Water Supply Act of 1968, as 
amended, apply. Tri-Lakes (DeQueen, Gillham, and 
Dierks) Water District furnished a resolution of intent to 
repay costs allocated to water supply storge. The Southwest 
Arkansas Water District is currently repayingcosts 
allocated to water supply storage at Millwood Lake. 
Operations and results during fiscal year. Operation 
and maintenance of projects continued. See individual 
projects for details. 
Condition at end of fiscal year. Millwood, DeQueen, 
Gillham, and Dierks Lakes are complete and in operation. 
16. WHITE RIVER BASIN 
(LITTLE ROCK DISTRICT), 
AR & MO 
Location. Improvements are on White River and 
tributaries, Arkansas and Missouri. More definite location 
of individual items is shown in Table 18-K, White 
River Basin. 
Existing project. A general comprehensive plan for 
flood control and other purposes in White River Basin. 
Plan now includes seven lakes, of which two are flood 
control only projects and five are multiple-purpose 
projects. Beaver, Table Rock, Bull Shoals, Norfork, 
Clearwater, Greers Ferry and Bell Foley Lakes were 
selected and approved for construction by Chief of 
Engineers, and individual reports on these seven lakes 
are presented on subsequent pages. Bell Foley Lake was 
reclassified to inactive in June 1977. Lakes in plan are 
listed in Table 18-K, White River Basin. For authorization 
see Table 18-B. 
Local cooperation. Section 2, Flood Control Act of 
1938 applies, Water Supply Act of 1958, as amended, 
applies to Beaver, Greers Ferry, and Norfork. 
Operations and results during fiscal year. Operation 
and maintenance of projects continued. Estimated 
monetary flood control benefits for fiscal year attributed 
to Beaver, Table Rock, Bull Shoals, Norfork, Greers 
Ferry Lake, and Clearwater Lakes for prevention of 
flood damages were $1,381,000, $3,699,000, $10,640,000, 
$4,674,000, $7,941,000, and $15,831,000, respectively, a 
total of $44,166,000. Total flood damages prevented by 
lakes through September 30, 1983, amounted to 
$167,079,000 of which $11,731,000 accrues to Beaver, 
$81,672,000 to Table Rock $46,811,000 to Bull Shoals, 
$16,766,000to Norfork, $13,900,000toGreers Ferry, and 
$46,199,000 to Clearwater. 
Delivered 2,548,968,700 kilowatt-hours of electric energy 
to Southwestern Power Administration for marketing: 
1783,228,900 from Beaver, 680,245,000 from Table 
Rock; 1,064,785,000 from Bull Shoals; 260,868,500 from 
Norfork; 844,881,800 from Greers Ferry powerplants. 
Water releases for fish hatcheries were: 28,960 acrefeet 
from Norfork Lake for Fish and Wildlife Service 
trout hatchery, 14,480 acre-feet from Table Rock Lake 
for Missouri Conservation Commission trout hatchery, 
and 14,480 acre-feet from Greens Ferry Lake for U.S. 
Fish and Wildlife Service trout hatchery. 
Withdrawals for water supply purposes were: Beaver 
Water District, 24,926 acre-feet from Beaver Lake; 
Water and Sewer Improvement District No. 3 of Mountain 
Home, AR, 2,106 acre-feet from Norfork Lake; the 
Community Water System, Cleburne County, AR, and 
18-4

LITTLE ROCK, AR, DISTRICT 
the city of Clinton, AR, 1,523 acre-feet from Greers Ferry 
Lake. 
Condition at end of fiscal year. Beaver, Table Rock, 
Bull Shoals, Norfork, Clearwater, and Greers Ferry 
Lakes are complete and in operation. Progress on these 
lakes is in individual reports. Preconstruction planning 
has been discontinued on Bell Foley. Water Valley and 
Lone Rock Lakes have been deauthorized. 
The White River Fish Hatchery authorized by the 
Water Resources Development Act of 1976 would be 
located on White River in Carroll County, AR about 9 
miles northwest of the city of Eureka Springs to provide 
a plan of improvement for construction of trout production 
facilities including a fish hatchery downstream from 
Beaver dam. Total estimated cost is $6,000,000. 
17. BLUE MOUNTAIN LAKE, AR 
Location. See Table 18-I, Arkansas River Basin, AR, 
OK, and KS: Lakes. 
Existing project. Estimated cost is $5,069,974, of 
which $551,000 is Code 710 funds. For further information 
see pages 906 and 907 of 1962 Annual Report. For 
authorization see Table 18-B. 
Local cooperation. Section 2, Flood Control act of 
1938 applies. 
Operations and results during fiscal year. Operation 
and maintenance of project continued. Estimated 
monetary benefits at end of fiscal year attributed to Blue 
Mountain Lake for prevention of flood damages were 
$1,059,000, a total of $14,554,200 to September 30, 1983. 
Condition at end of fiscal year. Project is complete 
except for additional recreation sanitary facilities. Construction 
of project began in May 1940, and it was ready 
for beneficial use in March 1947. 
18. CLEARWATER LAKE, MO 
Location. See Table 18-K White River Basin, AR & 
MO. 
Existing project. Estimated cost is $11,395,000, of 
which $1,666,000 is Code 710 funds. For further information 
see pages 897 and 898 of 1962 Annual Report. For 
authorization see Table 18-B, Authorizing Legislation. 
Recommended modification. A reconnaissance report 
under the Dam Safety Assurance Program was 
submitted in August 1979 and approved subject to 
comment in April 1980. The report recommends further 
planning and design to lengthen the emergency spillway 
by 350 feet at an estimated cost of $23,200,000 and to 
continue studies to determine the extent of the underseepage 
problem and seismic stability. A Comprehensive 
Seepage Analysis and Report and a Seismic Analysis 
Report were submitted in August 1981. 
Local cooperation. Section 2, Flood Control Act of 
1938 applies. 
Operations and results during fiscal year. Operation 
and maintenance of project continued. Estimated 
monetary benefits attributed to Clearwater Lake for 
prevention of flood damages were $15,831,000, a total of 
$46,199,000 to September 30, 1983. Releases made from 
lake during low-water periods were sufficient to supply 
municipal water for Poplar Bluff and other usages. 
Condition at end of fiscal year. Project is complete 
except for addition and improvement to existing sanitary 
recreational facilities. Construction of project began in 
June 1940 and was ready for beneficial use in March 
1948. 
19. DEQUEEN LAKE, AR 
Location. On Rolling Fork River, river mile 22.8, a 
tributary of Little River, in Sevier County, about 6 miles 
northwest of DeQueen, AR (See Geological Survey map 
for Chapel Hill, AR, quadrangle, scale 1:24,000.) 
Existing project. An earthfill dam, 2,360 feet long, 
constructed to 160 feet above streambed. An uncontrolled 
spillway, 200 feet wide, is about 1,400 feet east of 
main embankment. Outlet works consist of a gated 
conduit, 12 feet in diameter. The lake controls 169 square 
miles of drainage area and provides a total storage of 
136,100 acre-feet (101,200 for flood control storage and 
34,900 for conservation and sedimentation reserve.) Federal 
cost of project is $19,618,853 of which $30,000 is for 
Code 710 funds. (See Table 18-B for authorizing legislation.) 
Local cooperation. Section 2, Flood Control Act of 
1938, and Section 301, Water Supply Act of 1958, as 
amended, apply. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. Estimated monetary 
benefits attributed to DeQueen Lake for prevention 
of flood damages were $337,000, a total of $3,900,000 to 
September 30, 1983. 
Condition at end of fiscal year. Construction began 
April 1966 and project placed in useful operation in 
August, 1977. 
20. DIERKS LAKE, AR 
Location. On Saline River, river mile 56.6, a tributary 
of Little River, about 5 miles northwest of Dierks, 
Howard County, AR. (See Geological Survey map for 
Dierks Dam, AR, quadrangle, scale 1:24,000.) 
Existing project. An earthfill dam, 2,760 feet long, 
about 153 feet above streambed. An uncontrolled spillway 
800 feet wide is in a saddle at west end of dam. Outlet 
works consisting of a gated 6- by 9-foot oblong conduit, 
one 24-inch low-flow pipe, and one 80-inch water supply 
pipe are provided. The lake controls a drainage area of 
114 square miles and provides for storage of 67,100 acrefeet 
for flood control and 29,700 acre-feet for water 
supply, conservation, and sedimentation reserve, a total 
of 96,800 acre-feet. Federal cost of project is $16,014,904 
of which $96,000 is Code 710 funds. (See Table 18-B for 
authorizing legislation.) 
Local cooperation. Section 2, Flood Control Act of 
1988, and Water Supply Act of 1958, as amended, apply. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. A total of 218 
acre-feet was made available for water supply for Tri- 
18-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 19N8 
Lakes Water District. Estimated monetary benefits 
attributed to Dierks Lake for prevention of flood damages 
were $594,000, a total of $2,488,000 to September 30, 
1983. 
Condition at end of fiscal year. Construction began 
in June 1968. The embankment closure was made on May 
8, 1975 and the project placed in useful operation. 
21. GILLHAM LAKE, AR 
Location. Damsite is on Cossatot River, river mile 
49.0, in Howard County, about 5 miles northeast of 
Gillham, Sevier County, AR. (See Geological Survey map 
for Gillham Dam, quandrangle, AR, quandrangle, scale 
1:24,000.) 
Existing project. For description of completed improvement 
see Page 19-12 of Annual Report for 1977 
(Tulsa District). Federal cost of project is $17,828,711 of 
which $29,000 is for Code 710 funds. (See Table 18-B for 
authorizing legislation.) 
Local cooperation. Section 2, Flood Control Act of 
1938, and Water Supply Act of 1958, as amended, apply. 
Tri-Lakes Water District furnished a resolution of intent 
to repay costs allocated to water supply storage. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. Estimated monetary 
benefits attributed to Gillham Lake for prevention 
of flood damages were $666,000, a total of $4,230,000 to 
September 30, 1983. 
Condition at end of fiscal year. Construction began 
in June 1963. The embankment closure was made on May 
8, 1975 and the project placed in useful operation. 
22. MILLWOOD LAKE, AR 
Location. On Little River, river mile 16.0, approximately 
7 miles east of Ashdown, Little River County, 
AR, and about 2 miles northeast of Millwood, Little River 
County, AR. (See Geological Survey map for Red Bluff, 
AR, quadrangle, scale 1:24,000.) 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1969 (Tulsa District). Federal cost of project is 
$46,100,082, of which $2,756,000 is Code 710 funds. (See 
Table 18-B for authorizing legislation.) 
Local cooperation. Completed as required. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. A total of 46,441 
acre-feet of water was released from the lake for water 
supply to Southwest Arkansas Water District. Estimated 
monetary benefits attributed to Millwood Lake 
for prevention of flood damages were $262,000, a total of 
$5,416,000 to September 30, 1983. 
Condition at end of fiscal year. Construction began 
in September 1961 and the project was placed in full 
flood control operation in August 1966. Work required to 
complete project consists of additional recreational facilities 
under cost sharing program. 
23. NIMROD LAKE, AR 
Locasn. See Table 18-I, Arkansas River Basin, AR, 
OK, and KS: Lakes. 
Exzilig project. Estimated cost is $4,00627, of 
which $558,000 is Code 710 funds. For further information 
see pages 908 and 909 of 1962 Annual Report. For 
authorization see Table 18-B. 
Local cNpeu s. Section 2, Flood Control Act of 
1968 applie. 
Operatism and results during fisclal year. Operation 
and maintenance of project continued. Addition and 
improvement to existing recreation sanitary facilities 
were continued. Flooding was prevented on an average of 
1,978 acres of improved land during fiscal year. 
Estimated monetary benefits at end of fiscal year 
attributed to Nimrod Lake for prevention of flood damages 
were $1,234,000 making a total of $8,091,000 to 
September 1983. 
Seventy-one acre-feet of water were withdrawn by the 
city of Plainview, AR, from Nimrod Lake. 
Condition at end of fiscal year. Project is complete 
except for addition and improvement to existing sanitary 
recreation facilities. Construction of project began in 
January 1940 and was ready for beneficial use in 
January 1942. 
24. PINE MOUNTAIN LAKE, AR 
Location. Damsite is at mile 35.7 on Lee Creek and 12 
miles north of Van Buren, AR. (See Geological Survey 
map Rudy NE, AR, quandrangle, scale 1:24,000.) 
Existing project Provides for construction of a lake 
for flood control, water supply, and recreation. The lake 
would control runoff from 168 square miles. Capacity 
would be 261,000 acre-feet, of which 93,100 would be for 
flood control, 168,000 for water supply, fish and wildlife 
mitigation and recreation. Estimated cost is $71.200,000, 
of which local interests will repay $50,900,000 for water 
supply storage. Project was authorized by Flood Control 
Act of 1965. 
Local cooperation. Section 2, Flood Control Act of 
1938, Water Supply Act of 1958, as amended, and 
Federal Water Project Recreation Act apply. 
Operations and results during fiscal year. Preconstruction 
planning is being held pending receipt of local 
assurance for cost sharing. 
Condition at end of fiscal year. Preconstruction 
planning is 75 percent complete. Project is 2 percent 
complete. 
25. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Approved regulations for operation and maintenance 
of flood control works, Part 208 of Title 33, Code of 
Federal Regulations, provide for periodic inspection of 
completed projects transferred to local interests for 
operation and maintenance. Inspections of local flood 
protection projects, shown in Section 26 as completed 
projects, were made to determine extent of compliance 
18-6

LITTLE WICK, AR, DISTRICT 
with approved regulations for maintenance and operation 
of these projects. Responsible officials of improvement 
districts concerned were advised of inadequacies in 
maintenance and operation of local flood protection 
works under their jurisdiction where appropriate. Cost 
for fiscal year was $58,319. Total cost to September 30, 
1983, was $843,597. 
26. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
See Table 18-E, Other Authorized Flood Control 
Projects. 
27. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Heavy December 1982 rains and tornadoes caused 
serious emergency problems in Arkansas and Missouri. 
Thirteen levee systems were damaged and more than 39 
urban areas received significant flooding. Therefore, 
work under this authority became very active. 
Emergency flood control activities - repair, floodfighting 
and rescue work (Public Law 99, 84th Cong. and 
antecedent legislation). Flood events and levee rehabilitation 
projects costs in FY 1983 were $771,273. Ten 
damaged levee systems were investigated with five of 
these rehabilitated, using a total of $407,658 of these 
funds. The rehabilitated levees were Bateman Levee No. 
3, Curia Creek Levee, Jackson Levee No. 2, Little Red 
River Levee No. 1 and Point Remove Levee. 
Emergency streambank protection (Section 14 of 1946 
Flood Control Act, Public Law 526, 79th Cong). Emergency 
bank stabilization at White County Road Bridge, 
Little Red River, Judsonia, AR, was completed and 
accepted by the County for operation and maintenance in 
April 1983. Costs for the project totaled $63,355. Emergency 
bank protection, Rolling Fork River, Sevier County 
Road No. 12, AR, construction contract for $64,500 
was awarded in February 1981. The work was physically 
completed in July 1981, but there is an outstanding claim 
by the contractor. When the claim is settled, the work will 
again be jointly inspected by the local sponsor and the 
Corps and then turned over to the County for O&M. A 
study of a bank caving problem along the Black River at 
County Road 607, Butler County, MO, was initiated in 
June 1983. 
Small navigation projects (Section 107, River and 
Harbor and Flood Control Act of 1960). The development 
of two slack water harbors on the Arkansas River at 
Little Rock and North Little Rock, AR, are being studied. 
Expanded reconnaissance reports should be completed 
in FY 1984. FY 1983 costs total $48,317. 
Small flood control projects (Section 205, Flood Control 
Act of 1948, as amended). Twenty new studies were 
initiated under this authority during FY 1983. Fifteen 
reconnaissance studies were completed during the fiscal 
year. Nine studies recommended economically feasible 
solutions to the flooding problems. There are 11 studies in 
the reconnaissance stage, 8 studies in the expanded recon 
stage, 2 projects in the detailed project report (DPR) and 
plans and specifications stage, and 3 projects under 
construction. (For more details, see Table 18-L) A total of 
$824,359 was expended on the Section 205 program in 
FY 1983. 
Multiple-Purpose Projects Including Power 
28. BEAVER LAKE, AR 
Location. See table 18-K. White River Basin. 
Existing project Estimated cost is $50,797,000, of 
which $5,799,000 is Code 710 funds. For further information 
see pages 788 and 789of 1966 Annual Report. For 
authorization see Table 18-B. 
Local Cooperation. Section 2, Flood Control Act of 
1938 and Water Supply Act of 1958, as amended, apply. 
Operations and results during fiscal year. Results 
of operation of Beaver Lake are shown in Section 16. 
Operation and maintenance continued. 
Condition at end of fiscal year. Project is complete 
except for addition and improvement to existing recreation 
sanitary facilities. Construction of project began in 
October 1959 and was placed in operation for flood 
control in December 1963, hydroelectric power generation 
with both units in May 1965, and water supply in 
January 1966. 
29. BULL SHOALS LAKE, AR 
Location. See Table 18-K, White River Basin, AR & 
MO. 
Existing project. Estimated cost with eight generating 
units is $96,356,000, of which $10,886,000 is Code 
710 funds. For further information see pages 725 and 726 
of 1965 Annual Report. For authorization see Table 18-B. 
Local cooperation. Section 2, Flood Control Act of 
1938 applies. 
Operations and results during fiscal year. Operation 
and maintenance of project continued. Results of 
operation of Bull Shoals Lake are shown in Section 16. 
Condition at end of fiscal year. Project is complete 
except for addition and improvement to existing recreation 
sanitary facilities. Construction of project began in 
April 1946 and was ready for beneficial use for flood 
control in June 1951 and generation of electrical energy 
in September 1952. Units 1 through 8 were placed in 
operation September 1952, September 1952, December 
1952, June 1953, January 1962, February 1962, August 
1963, and September 1963, respectively. 
30. DARDANELLE LOCK AND DAM 
(NO. 30), AR 
Location. See Table 18-H, Arkansas River Basin; AR, 
OK, and KS: Navigation. 
Existing project. Project is a unit of McClellan-Kerr 
Arkansas River Navigation System. Dam is 2,683 feet 
18-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1988 
long and 68 feet high. It has a spillway with 20 tainter 
gates 50 feet long and 39 feet high. Navigation lock is 110 
by 600 feet with a lift of 54 feet. Powerhouse contains four 
31,000 kilowatt generators. Lake has a storage capacity 
of 486,200 acre-feet. Estimated cost is $86,507,000, of 
which $1,708,000 is Code 710 funds. (See Table 18-B for 
authorizing legislation.) 
Local cooperation. See Section 1. 
Operations and results during fiscal year. Pool 
fluctuated within 2-foot power pondage, elevation 336.00 
to 338.00. Power generation continued. Installed capacity 
is 124,000 kilowatts. Delivered 657,698,200 kilowatt 
hours of electrical energy to Southwestern Power Administration 
for marketing. Operation and maintenance 
continued at cost of $2,827,026. A new visitor's center and 
residentoffice is planned; the estimated cost is $1,169,385. 
Condition at end of fiscal year. Project is complete 
except for addition and improvement to existing recreation 
sanitary facilities. Construction began June 1957. 
Power units were placed on line April, May, and September 
1965, and January 1966. Lock was placed in 
operation in December 1969. Lock was unwatered, inspected, 
and repaired September 14-23, 1981. 
31. GREERS FERRY LAKE, AR 
Location. See table 18-K, White River, AR & MO. 
Existing project. Estimated cost is $55,125,000, of 
which $8,080,000 is Code 710 funds. For further information 
see page 740 of 1964 Annual Report. (See Table 
18-B for authorizing legislation.) 
Local cooperation. Section 2, Flood Control Act of 
1938 and Water Supply Act of 1958, as amended, apply. 
Operations and results during fiscal year. Operation 
and maintenance continued. A contract to construct 
the visitors center was awarded September 18,1981.The 
park is essentially complete at an estimated cost of 
$833,137. 
Condition at end of fiscal year. Project is complete 
except for addition and improvement to existing recreation 
sanitary facilities. Construction of project began in 
June 1957, was ready for beneficial use for flood control 
in January 1962, and power units 1 and 2 were placed in 
operation in March and May 1964, and water supply was 
placed in operation in April 1971. 
82. NORFORK LAKE, AR 
MOL.ocation. See Table 18-K, White River Basin, AR & 
Existing project. Estimated cost is $111,624,000, of 
which $4,125,000 is Code 710 funds, $88,700,000 is for 
addition of power units 3 and 4, and $40,000,000 is for 
highway bridge construction. For further information 
see page 896 of 1962 Annual Report. (See Table 18-B for 
authorizing legislation.) 
Local cooperation. Section 2, Flood Control Act of 
1938 and Water Supply Act of 1958, as amended, apply. 
Operations and results during fiscal year. Operation 
and maintenance of project continued. Results of 
operation of Norfork Lake are shown in Section 16. 
Condition at end of fiscal year. Project is complete 
except for addition and improvement to existing recreation 
sanitary facilities, highway bridges, and addition of 
power units 3 and 4. Construction of project began in 
October 1940, ready for beneficial use for flood control in 
June 1943, and for generation of electrical energy with 
one unit in June 1944. Second unit was added in February 
1950. Water supply was added as a purpose in 
December 1969. A contract was awarded in April 1979 
for construction of two highway bridges over Norfork 
Lake to replace ferries. Bridge contract was completed in 
November 1982 and the contract work on the bridge 
approaches is 92 percent complete. Preconstruction 
planning for addition of power units 3 and 4 continued 
and a draft preauthorization report is being revised. 
33. OZARK-JETA TAYLOR LOCK AND 
DAM (NO. 12), AR 
Location. See Table 18-H, Arkansas River Basin, AR, 
OK, and KS: Navigation. 
Existing project. Project is a unit of McClellan-Kerr 
Arkansas River Navigation System. Dam is 2,480 feet 
long and 58 feet above streambed. It has a spillway with 
15 tainter gates 50 feet long and 46 feet high. Navigation 
lock is 110 by 600 feet with a lift of 34 feet. Powerhouse 
contains five 20,000 kilowatt generators. Lake has a 
storage capacity of 148,400 acre-feet. In addition, 1 footof 
power pondage is provided in Pool No. 13 between 
elevations 391.00 and 392.00. Estimated cost is 
$86,167,000 of which $400,000 is Code 710 funds. For 
authorization see Table 18-B. 
Local cooperation. See Section 1. 
Operations and results during fiscal year. Delivered 
134,716,300 kilowatt-hours of electrical energy to Southwestern 
Power Administration for marketing. Continued 
operation and maintenance. 
Condition at end of fiscal year. Construction began 
in December 1964 and is complete. Project is complete 
except for addition and improvement to existing recreation 
sanitary facilities. Lock and dam was placed in 
operation in November 1969. Power units were placed on 
line as follows: Unit 1, November 1972; unit 2, August 
1973; unit 3, October 1973; unit 4, December 1973, and 
unit 5, May 1974. Work remaining consists principally of 
modifications to powerplant. 
34. TABLE ROCK LAKE, MO 
Location. See Table 18-K, White River Basin, AR & 
MO. 
Existing project. Estimated cost is $71,283,000, of 
which $5,793,000 is Code 710 funds. For further information 
see page 893 of 1962 Annual Report. For authorization 
see Table 18-B. 
Local cooperation. Section 2, Flood Control Act of 
1988 applies. 
Operations and results during fiscal year. Opera- 
18-8

LITTLE ROCK, AR, DISTRICT 
tion and maintenance continued. Equipment for injection 
of oxygen in the power generation releases has been 
installed. Results of operation of Table Rock Lake are 
shown in Section 16. 
Condition at end of fiscal year. Project is complete 
except for addition and improvement to existing recreation 
sanitary facilities. Construction of project began in 
October 1954, was ready for beneficial use for flood 
control in November 1958, and for generation of electrical 
energy with units 1 and 2 in May 1959. Units 3 and 
4 were added in April and June 1961. 
General Investigations 
35. SURVEYS 
The total costs for the fiscal year was $1,336,247: 
special navigation studies (Arkansas River and Tributaries 
Hydropower Studies) $410,207; flood damage 
prevention studies (Clarksville, AR, Fort Smith-Van 
Buren, AR, and County Line, MO) $690,852; review of 
authorized projects (Village Creek, Taylor Bay) $158,503; 
special investigations $43,994, and planning assistance to 
states and other agencies $32,691. 
36. COLLECTION AND STUDY OF 
BASIC DATA 
Cost for the fiscal year was $202,592 of which $201,882 
was for flood plain management services, and $709 was 
for general hydrologic studies relating to streamflow 
frequency and distribution. 
Flood plain management services (FPMS). The 
FPMS program is under Section 206 of the 1960 Flood 
Control Act, PL 86-645, as amended. Through technical 
services and planning guidance, the program encourages 
comprehensive flood plain management planning at 
all levels to reduce the potential for losses to life and 
property from floods. Federal and non-Federal agencies 
and the private sector are assisted with planning and 
development information for flood hazard areas. This 
assistance is in the form of local flood plain regulations, 
Federal Insurance Program requirements, and Executive 
Order 11988 guidelines. Such assistance may include 
factual flood information (available or determined) and 
interpretation on flood frequencies, extent of flooding, 
flood-water velocity, duration of flooding and floodway 
limits. Services accomplished during fiscal year: Technical 
services and planning guidance responses furnished 
totaled 8,500. This total included services to 
Federal and non-Federal agencies, individuals, realtors, 
corporations, lending institutions, engineers, architects, 
and others. Cost for providing these services during FY 
1983 totaled $201,882. 
Hydrologic studies. During the fiscal year, 110 stations 
were operated, 75 cooperatively with USGS and 35 
by the Corps. The total cost for streamflow and some 
sediment data from all sources of funding for FY 1983 
was $477,740, of which $280,480 was transferred to 
USGS. The District also participated in a cooperative 
program with National Weather Service for rainfall 
and/or river reporting stations for use in forecasting 
streamflow for flood warning and operation of lake 
projects. Records were also collected at certain hydroclimate 
rainfall stations under a cooperative program 
between the two agencies. For these services, $26,487 
was transferred to the National Weather Service. 
37. ADVANCE ENGINEERING 
AND DESIGN 
During this fiscal year, $50,452 was expended on Pine 
Mountain Lake, AR, and Norfork Lake Units 3 and 4. 
18-9

TABLE 18-A 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
COST AND FINANCIAL STATEMENT1,2 
See 
Section Total to 
in Text Project Funding FY 80 FY 81 FY 82 FY 838 Sept.30, 1988 
1. Arkansas River 
Basin, AR, 
OK, & KS 
2. Bank Stabilization 
& Channel 
Rectification, AR 
3-13. Navigation 
Locks & Dams, 
AR 
15. Little River Basin, 
(Little Rock Dist.) 
16. White River 
Basin (Little 
Rock District) 
New Work 
A pprop. 
Dams 
Navigation 
Cost 
Dams 
Navigation 
Maint. 
Approp. 
Dams 
Navigation 
Cost 
Dams 
Navigation 
Rehab. 
Approp. 
Cost. - 
New Work 
Contrib. 
Cost 
S ial Funds 
t 
Other 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Wnrk 
Contrib. 
Cost. 
Other 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
$ 5,672,433 
342,322 
5,330,111 
6,169,941 
266,723 
5,903,218 
32,863,209 
6,159,147 
26,704,062 
32,725,494 
6,471,861 
26,253,633 
4,230,000 
4,626,391 
11,058,300 
9,939,392 
96,100 
584,458 
2,561,280 
2,092,845 
10,721,700 
11,711,320 
12,217,000 
12,759,439 
$11,261,061 
-28,500 
11,289,561 
10,602,360 
255,868 
10,346,492 
40,003,400 
7,167,600 
32,835,800 
40,303,566 
7,696,923 
32,606,643 
11,290,000 
10,332,435 
11,546,800 
12,815,340 
15,850 
91,374 
1,898,834 
2,332,510 
11,780,000 
11,717,083 
13,288,000 
13,910,820 
$ 9,614,000 
253,000 
9,361,000 
7,508,211 
121,201 
7,387,010 
38,403,821 
9,036,800 
29,367,021 
35,266,411 
7,967,122 
27,299,289 
9,330,000 
7,365,152 
11,064,121 
11,043,182 
205,000 
40,526 
3,146,600 
2,944,422 
12,195,000 
11,342,114 
16,098,500 
14,877,509 
- 
-==. 
-/ 
- I 
-/ 
9,330,000 
7,365,152 
11,064,121 
11,043,182 
205,000 
40,526 
3,146,600 
2,944,422 
12,195,000 
11,842,114 
16,098,500 
14,877,509 
$ 2,872,( 
138, 
2,734,( 
5,024, 
120, 
4,904 , 
42,620,( 
9,051,( 
33,569,( 
42,359, 
9,316, 
32,998, 
2,652,0 
4,868,8 
13,973,2 
13,111,1 
122,7 
3,342,( 
3,149,1 
2,601,5 
2,390,(0 
17,349,3 
17,678,0
052 $1,454,641,127 
052 150,390,533 
000 1,304,250,594 
761 1,453,473,955 
404 150,200,392 
357 1,303,273,563 
015 455,025,225 
008 101,677,833 
007 353,347,392 
344 448,742,058 
208 100,670,220 
136 348,071,838 
- 291,106 
- 291,106 
- 1,609,842 
- 1,609,842 
- 19,926,755 
- 19,926,755 
- 531,336 
- 531,336 
- 119,300,184 
- 119,300,184 
- 4,561,666 
- 4,561,666 
)00 416,709,473 
X15 415,881,416 
Z56 146,352,364 
152 142,592,691 
- 973,385 
- 963,567 
- 531,336 
- 531,336 
- 99,562,550 
753 99,479,051 
)00 23,853,560 
L12 22,688,967 
500 335,011,173 
)10 333,364,358 
300 182,414,569 
)80 180,379,558 
18-10 
.

LITTLE ROCK, AR, DISTRICT 
TABLE 18-A(Continued) COST AND FINANCIAL STATEMENT,2 
See 
Section Total to 
in Tezt Project Funding FY 80 FY 81 FY 82 FY 83 Sept. 80, 1983 
17. Blue Mountain 
Lake, AR 
18. Clearwater 
Lake, MO 
19. DeQueen Lake, 
Little River 
Basin, AR 
20. Dierks Lake, 
Little River 
Basin, AR 
21. Gillham Lake, 
Little River 
Basin, AR 
22. Millwood Lake, 
Little River 
Basin, AR 
28. Nimrod Lake, 
AR 
24. Pine Mountain 
Lake, AR 
28. Beaver Lake, 
AR 
29. Bull Shoals 
Lake, AR 
New Work 
Approp. 
Cost 
Maint 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New York 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
1,221 
446,092 
514,307 
2,000 
10,982 
2,002,000 
1,863,180 
35,000 
36,462 
365,550 
377,116 
184 
345,592 
416,151 
- 
3,815 
275,941 
319,598 
15,850 
63 
911,751 
1,219,645 
11,146 
530,067 
569,606 
617,000 
600,249 
60,000 
59,749 
1,886,(000X) 
2,403,920 
568,000 
531,940 
499,000 
454,364 
39 
402,000 
404,694 
14.606 
11 
750,800 613,4 
654,769 634,8 
53,000 
3,469 49,7 
1,425,200 1,460,(0 
1,249,609 1,571,1 
85,000 12,0 
3,322 92,5 
667,500 572,0 
582,271 619,5 
71,000 -12,(0 
26,415 19,3 
491,000 602,0 
536,957 457,2 
4,000 
10,789 3 
526,500 526,( 
419,132 471,6 
32,300 
-- 10.4 
,341,000 1,462,600 1,642,0 
,097,759 1,406,062 1,600,6 
- 25,000 
- 1,228 23,6 
571,000 640,300 759,0 
570,168 577,573 777,7 
61,920 
62,399 191 
1,397,000 1,661,000 
1,702,171 1,644,640 
- 30,000 
- 31,845 
2,803,000 2,487,000 
2,448,917 3,053,396 
43,000 -16,5 
9,834 10,(6 
1,609,800 2,284,0 
1,589,268 2,164,1 
1,100 
3,6303 
4,218,600 4,580,6 
3,556,928 4,737,8 
- 5,069,974 
- 5,069,974 
100 7,882,694 
303 7,818,636 
- 10,453,403 
781 10,440,204 
100 15,914,822 
L50 15,735,629 
00 19,630,853 
39 19,623,715 
)00 3,100,150 
551 3,002,665 
00 16,002,904 
388 15,987,816 
)00 3,634,683 
56 3,476,378 
- 17,828,711 
361 17,824,697 
X00 2,979,025 
113 2,506,329 
- 46,100,082 
65 46,042,823 
)09 14,139,702 
i92 13,703,595 
- 4,005,627 
i23 4,005,478 
)00 8,961,142 
27 8,903,206 
- 1,432,331 
- 1,432,331 
500 46,112,333 
375 46,106,150 
X00 22,372,759 
L57 22,165,400 
- 88,860,511 
385 88,858,707 
300 41,844,273 
94 41,213,485 
18-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 18-A (Continued) COST AND FINANCIAL STATEMENT,z 
See 
Section Total to 
in Text Project Funding FY 80 FY 81 FY 82 FY 83 Sept. 830,1988 
30. Dardanelle Lock New Work 
& Dam (No. 10), Approp. 1,127,000 - - - 84,270,124 
AR Cost 1,173,061 - - - 84,261,240 
Maint. 
Approp. 2,470,000 2,810,800 2,802,600 3,002,256 32,789,169 
Cost 2,549,462 - 2,775,065 2,916,825 32,514,670 
31. Greers Ferry New Work 
Lake, AR Approp. -156,000 - 77,000 - 48,865,512 
Cost 3,698 -2,021 1,290 77,853 48,865,512 
Maint. 
Approp. 2,364,000 2,638,000 3,412,500 3,424,000 31,625,218 
Cost 2,521,094 2,528,971 3,164,279 3,579,102 31,299,731 
32. Norfork Lake, New Work 
AR Approp. 11,074,000 11,690,000 11,959,000 2,618,000 70,972,929 
Cost 11,627,263 11,627,319 11,288,966 2,231,986 69,708,575 
Maint. 
Approp. 1,749,000 2,190,000 2,432,300 2,469,900 31,737,991 
Cost 1,826,434 1,911,510 2,582,827 2,497,243 31,479,995 
33. Ozark-Jeta Taylor New Work 
Lock & Dam (No. Approp. - - 2,000 - 85,629,412 
12), AR Cost - - - 10,532 85,629,323 
Maint. 
Approp. 1,906,000 5,249,000 3,100,500 3,820,256 27,750,598 
Cost 2,281,417 3,527,631 4,197,864 3,768,288 26,850,625 
34. Table Rock New Work 
Lake, MO Approp. -197,400 - 39,000 - 67,077,875 
Cost 6,978 - - 19,330 67,058,205 
Maint. 
Approp. 1,902,000 2,436,000 3,000,100 3,130,800 38,919,505 
Cost 2,397,643 2,368,383 2,734,598 3,132,535 38,489,319 
1. For more details on project funds, see text for individual projects. 
2. For distribution of Jobs Bill funds, see Table 18-B. 
18-12

LITTLE ROCK, AR, DISTRICT 
TABLE 18-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
ARKANSAS RIVER BASIN, AR, OK, & KS 
(See Section 1 of Text) 
Approved General comprehensive plan: 
Mannford Reservoir, OK 
Oologah Lake, OK 
Cantop Lake, OK 
Tenkiller Ferry Lake, OK 
Wister Lake, OK 
Blue Mountain Lake, AR 
Nimrod Lake, AR 
Flood Control Com. 
Doc. 1, 75th Cong., 
1st sess. 
Modified comprehensive plan to include reservoirs in 
Grand (Neosho) River Basin, OK, and MO, and in 
Verdigris River Basin: 
Markham Ferry Reservoir, OK 
Fort Gibson Lake, OK 
Pensacola Reservoir Lake O' The Cherokees, OK 
Fall River Lake KS 
Elk City Lake, kS 
Toronto Lake, KS 
Neodosha Lake, KS 
Authorized Chief of Engineers to provide in the Canton 
Lake 69,000 acre-feet of irrigation storage, subject to 
certain conditions. 
A proved multiple-purpose plan: 
Oologah Lake, OK 
Markham Ferry Reservoir, OK 
Fort Gibson Lake, OK 
Blackburn Reservoir, OK 
Mannford Reservoir, OK 
Taft Reservoir, OK 
Bank stabilization 
Dardanelle Lock and Dam, AR 
Eufaula Lake, OK 
Navigation locks and dams 
Ozark Lock and Dam, AR 
Short Mountain Lock and Dam, OK 
Webbers Falls Lock and Dam, OK 
Tenkiller Ferry Lake, OK 
H. Doc. 107 and 440, 
76th Cong. 1st seas. 
H. Doc. 758, 79th Cong., 
2d sess. 
June 30, 1948 
May 17, 1950 
July 14, 1960 
Modified Arkansas River navigation comprehensive plan to 
include bank protection works at Bradens Bend, OK. 
Modified comprehensive plan authorized in 1988 Flood 
Control Act and multiple-purpose plan authorized in 
River and Harbor Act of 1946 to provide for substituting 
Keystone Lake for Mannford, Blackburn and Taft 
Reservoirs. 
Authorized incorporation of River and Harbor and Flood 
Control plans into a single plan of development and made 
all previous authorizations applicable to combined 
plan .of development. 
S. Doc. 107, 81st Cong., 
1st sess. 
Pine Mountain Dam and Lake authorized 
for construction. 
H. Doe. 270, 89th Cong., 
Flood Control Act of 
1965 (Title II, Public 
Law 89298) 
18-13 
June 28, 1938 
August 18, 1941 
July 24, 1946 
July 24, 1946 
1965

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 18-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
LITTLE ROCK LEVEE, AR (EAST END-FOURCHE 
BAYOU 
June 22, 1936 Levees to provide flood protection to people and city H. Doc. 308, 74th Cong., 
property. 1st sess. 
December 22, 1944 Modified local flood protection project to raise grade H. Doc. 447, 78th Cong., 
and protect additional areas. 2d sess. 
October 27, 1965 Authorized 45,000 g.p.m. pump station and excavated S. Doc. 55, 89th Cong., 
storage area of 164 acre-feet 1st sess. 
WHITE RIVER BASIN (LITTLE ROCK DISTRICT) 
(See Section 16 of Text) 
June 28, 1938 Approved comprehensive plan for White River Basin: Flood Control Cornm. 
Lone Rock Lake, AR, Norfork Lake, AR, Doc. 1, 75th Cong., 
Clearwater Lake, MO, Water Valley Lake, AR, 1st sess. 
Bell Foley Lake, AR, Greers Ferry Lake., AR, 
and White River emergency. 
August 18, 1941 Modified comprehensive plan to include Bull Shoals H. Doc. 917, 76th Cong., 
Lake, AR, and MO, Table Rock Lake, MO, and 3d sess. 
AR, and Norfork Lake, AR, and MO (power). H. Doc. 290, 77th Cong., 
1st sess. 
September 3, 1954 Authorized power in Greers Ferry Reservoir and added H. Doc. 499, 83d Cong. 
Beaver Lake to the plan. 2d sess. 
1960 Jacksonport State Park in Jackson County, River and Harbor Act 
Arkansas. Improvements along the White River of 1960 as amended 
for recreation and navigation and the protection Section 107 
of the park which is historically significant. 
October 23, 1962 Authorizing clearing and straightening of channel for H. Doc. 352, 87th Cong., 
Village Creek, Jackson and Lawrence Counties. 2d sess. 
March 1, 1974 Authorizing highway bridge construction across Flood Control Conm. 
Norfork Lake. Doc. 1, 75th Cong., 
1st sess. 
October 22, 1976 White River Fish Hatchery, Arkansas provides for Water Resources 
trout production facilities downstream frnm Dvl.. Act of 
Beaver Dam. 1976, .L 94-587, 
Sec. 105 
VILLAGE CREEK WHITE RIVER, AND MAYBERRY 
LEVEE DISTRICT, AR 
June 22, 1936 Approved levee protection. H. Doc. 102, 73d Cong., 
1st sess. 
July 14, 1960 Modified existing project to add interior drainage in H. Doc. 225, 86th Cong., 
accordance with plan I, and directed study of plan III. 1st sess. 
October 23, 1962 Modified project to provide a pumping plant. H. Doc. 577, 87th Cong. 
2d sess. 
RED RIVER BELOW DENISON DAM INCLUDING 
LITTLE RIVER BASIN, OK AND AR 
(See Section 15 of Text) 
July 24, 1946 Construct Boswell, Hugo, and Millwood Lakes, and Bank H. Doc. 602, 79th Cong., 
Stabilization. 2d sess. 
July 3, 1958 Modified Millwood: Construct Pine Creek, Lukfata, H. Doc. 170, 85th Cong., 
Broken Bow, DeQueen, Gillham, Dierks Lakes 1st sess 
18-14

LITTLE ROCK, AR, DISTRICT 
TABLE 18-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to Sept. 30, 1983 
Ful Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Black River, AR, and MO ' 1960 $ 80,000 $ 930,324 
Current River, AR, and MO 1 1964 17,000 132,178 
Upper White River, AR 4 1952 813,197 1,788,374 
White River, AR, (above Peach 
Orchard Bluff) 5 1950 - 785,666 
1. Channel adequate for existing commerce. Completion 
not contemplated. 
2. Includes $7,000 for previous project. 
3. Federal operation and maintenance terminated June 
30,1952, due to lack of commerce. Facilities at Locks and Dams 
Nos. 1, 2, and 3 disposed of in accordance with authority in 
Public Law 996, 84th Cong. 
4. Completed. 
5. Responsibility for maintenance of project downstream 
from Newport, AR, transferred to Memphis District in FY 62. 
18-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 18-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to Sept 30, 1988 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Bell Foley Lake, White River, AR' Inactive 1975 $1,407,116 - 
Black River, Poplar Bluff, MO, to 
Knobel, AR Completed 1958 584,315- 
Carden's Bottom Drainage District No. 2, 
Arkansas River, AR Completed 1951 919,955 - 
Clarksville, AR Completed 1962 271,717 - 
Conway County Drainage and Levee District 
No. 1, Arkansas River, AR Completed 1959 187,440 - 
Conway County Levee Districts Nos. 1, 
2, and 8, Arkansas River, AR Completed 1952 1,018,840 - 
Conway County Levee District No. 6, 
Arkansas River, AR Completed 1952 390,952 - 
Crawford County Levee District, Arkansas 
River, AR Completed 1954 2,001,820 - 
Crooked Creek, Lake and Levee, AR2 Inactive 1969 - - 
East Poplar Bluff and Poplar Bluff, MO Completed 1958 304,699 - 
Faulkner County Levee District No. 1, 
Arkansas River, AR Completed 1941 99,511 - 
Fort Smith, Arkansas River, AR Completed 1951 1,077,546 - 
From North Little Rock to Gillett, AR 
(above Plum Bayou) Completed 1954 845,300 - 
Fourche Creek, Little Rock, AR - 1973 22,890 - 
Little Rock Levee, AR, East End 
Fourche Bayou - 1975 1,901,899 - 
McLean Bottom Levee District No. 3, 
Arkansas River, AR Completed 1950 422,549 - 
Near Dardanelle, Arkansas River, AR Completed 1953 198,069 - 
Newport, White River, AR Completed 1941 314,276 - 
North Little Rock, Arkansas River, AR Completed 1958 512,001 - 
Petit Jean River. AR C omplctc'd 1 ,4,350 
Roland Drainage District, Arkansas River, 
AR Completed 1950 269,907 - 
Skaggs Ferry, Black River, AR Completed 1941 81,023 - 
South Bank Arkansas River (Head Fourche 
Island to Pennington Bayou), AR Completed 1964 1,404,852 - 
South Bank, Arkansas River, Little Rock to 
Pine Bluff, AR, Tucker Lakes Completed 1961 409,115 - 
Van Buren, Arkansas River, AR Completed 1952 438,222 - 
Village Creek, White River, and Mayberry 
Levee Districts, AR - 1972 1,567,156 - 
Village Creek, Jackson and 
Lawrence Counties, ARx Inactive 1977 510,217 - 
West of Morrilton, Arkansas River, AR Completed 1962 1,269,959 - 
1. Reclassified as inactive in June 1977. 3. See H Doc. 577, 87th Cong., 2d sess., for description of 
2. Recommended to continue in deferred category in project. 
August 1977. 4. Authorized by Chief of Engineers. 
18-16

LITTLE ROCK, AR, DISTRICT 
TABLE 18-G DEAUTHORIZED PROJECTS 
For Last Funds Expended 
Full Report See Annual Date Federal Contributed 
Project Authority Report For Deauthorized Funds Funds 
Lone Rock, Buffalo 
River, AR 1938 FCA - 1977 - - 
Water Valley, Eleven 
Point River, AR & MO 1968 FCA - 1977 - - 
18-17

TABLE 18-H ARKANSAS RIVER BASIN; AR, OK, AND KS: NAVIGATION 
(See Section 1 of Text) 
Miles Elevation Char- Year 
Up Lock Uper Depth on Miter ter Opened 
stream Lock of Kind to Total 
from Miles to Dimension Lift (feet, Upper Lower Founda- of Type of Navi Estimated 
Feature Mouth - Nearest Town (feet) (feet) MSL) (feet) (feet) tion Dam Conruction gation Cost 
LITTLE ROCK 
DISTRICT 
Norrell L&D No. 1 
Lock No. 2 
Dam No. 2 
L&D No. 3 
L&D No. 4 
L&D No. 5 
David D. Terry 
L&D No. 6 
Murray L&D No. 7 
Toad Suck Ferry 
L&D No. 8 
L&D No. 9 
10.3 
13.3 
40.5 
50.2 
66.0 
86.3 
108.1 
125.4 
155.9 
8 east of Arkansas 
Post, AR 
6 east of Arkansas 
Post, AR 
3 southeast Arkansas 
Post, AR 
5 north of Grady, AR 
7 east of Pine Bluff, 
AR 
4 southeast of 
Redfield, AR 
12 southeast of Little 
Rock, AR 
6 northwest of Little 
Rock, AR 
6 west of Conway, AR 
176.9 3 southwest of 
Morrilton, AR 
110 by 600 
110 by 600 
110 by 600 
110 by 600 
11) by 600 
114) by 600 
110 by 600 
110 by 600 
30 max. 
20 nom. 
28 max. 
20 
14 
17 
18 
18 
16 
142 
162 
182 
196 
213 
231 
249 
265 
110 by 600 19 -287 
16 
18 
18 
18 
18 
18 
18 
18 
15 
14 
14 
14 
14 
14 
14 
14 
Piles in 
sand 
Piles in 
sand 
Piles in 
sand 
Piles in 
sand 
Piles in 
sand 
Clay 
Piles in 
sand 
Shale 
Shale 
Fixed 
overflow 
Movable 
Movable 
Movable 
Movable 
Movable 
Movable 
Movable 
Concrete 
Gated concrete 
spillway with 
embankment 
ends 
Gated concrete 
spillway with 
embankment 
ends 
Gated concrete 
spillway with 
embankment 
ends 
Gated concrete 
spillway with 
embankment 
ends 
Gated concrete 
spillway with 
embankment 
ends 
Gated concrete 
spillway with 
embankment 
ends 
Gated concrete 
spillway with 
embankment 
ends 
18 14 Shale Movable Gated concrete 
spillway with 
embankment 
ends 
1967 
1967 
1968 
1968 
1968 
1968 
1968 
1969 
1969 
1969 
$37,801,000 
40,971,000 
33,791,000 
40,831,000 
29,589,000 
62,634,000 
33,059,000 
61,504,000 
34,370,000 
0
Ia 
r~ 
90

TABLE 18-H 
(Continued) 
ARKANSAS RIVER BASIN; AR, OK, AND KS: NAVIGATION 
(See Section 1 of Text) 
Mile Elevation Char- Year 
Ulp U Depth on Miter acter Opened 
stream Loek of Kind to Total 
from Miles to Dhnenion Lift (feet, Upper Lower Founds- of Type of Navi- Estimated 
Feature Mouth - Nearest Town (feet) (feet) MSL) (feet) (feet) tion Dam Construction gation Cost 
Dardanelle 
LAD No. 10 
lAD No. 11 
OzarkJeta Taylor 
lAD (No.12) 
IAD No. 13 
TULSA DISTRICTX 
LAD No.13 (part) 
W. D. Mayo 
L&D No. 14 
Robert S. Kerr 
LAD No. 15 
Webbers Falls 
LAD No. 16 
Chouteau LAD 
No. 17 
Newt Graham 
LAD No. 18 
205.5 2 northwest of 
Dardanelle, AR 
256.8 
292.8 
319.6 
386.2 
366.6 
401.4 
421.6 
1 emast of Ozark, AR 
7 east of Fort Smith, 
AR 
4 east of Redland, 
OK 
1 north of Cowlington, 
OK 
1 northwest of Gore, 
OK 
4 northwest of Okay, 
OK 
8 southwest of Inola, 
OK 
110 by 600 54 338 
110 by 600 
110 by 600 
110 by 600 
110 by 600 
110 by 600 
110 by 600 
110 by 600 
34 
20 
20 
48 
30 
21 
21 
370 
392 
412 
460 
490 
511 
532 
18 14 Movable Sandstone Gated concrete 
spillway with 
embankment 
ends 
18 
18 
14 
18 
19 
15 
15 
15 
14 
15 
14 
16 
14 
14 
Sandstone Movable 
and shale 
Sandstone Movable 
and shale 
Rock 
Rock 
Rock 
Rock 
Rock 
Movable 
Movable 
Movable 
Movable 
Movable 
Movable 
Gated concrete 
spillway with 
embankment 
ends 
Gated concrete 
spillway with 
embankment 
ends 
Gated concrete 
spillway with 
embankment 
ends 
Gated concrete 
spillway with 
embankment 
ends 
Gated concrete 
spillway with 
embankment 
ends 
Gated concrete 
spillway with 
embankment 
ends 
Gated concrete 
spillway with 
embankment 
ends 
1969 
1969 
1969 
1970 
1970 
1970 
1970 
1970 
1970 
$84,270,124 
85,629,412 
47,882,000 
6,858,000 
32,655,000 
94,578,237 
83,738,277 
31,619,000 
44,355,000 
r 
v
y 
d 
A
y 
1

TABLE 18-H 
(Continued) 
ARKANSAS RIVER BASIN; AR, OK, AND KS: NAVIGATION 
(See Section 1 of Text) 
Additional features entering into cost of project 
Little Rock Ditict 
Bank stabilization and channel rectification, mile 33.7 to 862 and 
Arkanmse-White Cutoff, 100 per cent complete ......... ..... $119,300,184 
Maintenance and repair fleet and marine terminals, 
99 per cent complete.. ..... . ............ 7,529,000 
TItal, Little Rock D is ...t.r..i.c..t. ..................... 719,160.720 
Navigationa ids (US Coast Guard)........................... 2,268,000 
Tra Dsrc 
Bank stabilisation and dannel rectification, Short Mountaiin 
t Fort Smith, complete .............................. ..... 12,700,038 
Maintenance and repair fleet and marine terminals, 
complete ................................................... 2,70,000 
u tot ...... ...... ....................... .. ...... 3~09 , 56 
Upatream Laka 
olgah,90.2 miles upstream from mouth, Verdigris River 
ompete ............... ................................ s$ 46,726,329 
Ketone, 88.8 miles upstream from mouth, Arkansas River, 
complete................................................ 123,171,173 
Eusfaula, 27 miles upstream from mouth, Canadian River, 
complee................................................ 121,830,747 
Smubotal .............................................. 291,728,249 
'tal. Tulsa District................................... 600.981,801 
'ital Project Cost 99.8 percent complete ............... $1,322,410,321 
Lii 
Lii 
Ci 
_ I __

TABLE 18-I ARKANSAS RIVER BASIN; AR, OK, AND KS: LAKES 
(See Section 1of Text) 
MeDrainage e Reserveir Power Year or Total 
AbArea o CapaIty Develp Percet E ated 
Lake aid State River Meuth Nears Tmw (sq mul) (Suet) Type (aerefeet) (kiewalls) Canmplete Cost 
Blue Mountain, AR Petit Jean 74.4 Paris, AR 488 115 Earthfill 257,900 - 1947 $ 5,060,974 
Canton, OK North Canadian 384.3 Canton, OK 12,488 68 Earthfill 383,300 - 1948 10,920,727 
Elk City, KS Elk 8.7 Independence, KS 634 
(Table Momd) 107 Earthfill 284,300 - 1966 19,057,562 
Eufaula, OK' s Canadian 27.0 Eufaula, OK 47,522 114 Earthfill 3,798,000 90,000 1964 121,830,747 
Fall River, KS Fall 54.2 Fall River, KS 585 94 Earthfill 256,400 - 1949 10,550,873 
Fort Gibson, OK' 7 Grand (Neosho) 7.7 Fort Gilmbson,. OK 12,498 110 Concrete-gravity 1,284,400 45,000 1953 43,713,378 
Kaone, OK si Arkansas 538.8 Sand Springs, OK 74,506 121 Earthfill 1,836,500 70,000 1964 123,171,173 
Markham Ferry, OK' Grand (Neosho) 47.4 Pryor, OK 11,533 90 Earthfll 444,500 100,000 1968 6,908,756 
Neodeh, KP Verdigris 222.8 Neodesha, KS 1,152 74 Earthfill 90,000 - 0 97,910 
Nimrod, AR Forche La Fave 62.6 Plainview, AR 680 1083 Concrete-gravity 336,010 - 1942 4,005,627 
Oologah, OK= Verdigrais 90.2 Claremore, OK 4,339 137 Earthfill 1,519,000 - 1974 46,689,329 
Penesaola, OK * Grand (Neosh) 77.0 Disney, OK 10,298 147 Concrete arch 2,197,000 86,400 1940 52,126 
Tenkiller Ferry, OK" Ilinois 12.8 Gore, OK 1,610 197 Earthfill 1,230,800 34,000 1968 24,115,719 
Toronto, KS Verdigris 271.5 Toronto, K8 730 90 Earthfill 199,700 - 1960 13,896,33 
Wister, OK Peau 60.9 Wister, OK 993 99 Earthfill 427,900 - 1949 10,501,226 
Subtotal, exclive ot Efaa, Ka stone, and Oologkah,. 98 percent complete 148,80,202 
Total, Arkansas River Basin, 98 percent complete 1,471,300,523 
1. Prict includes faeilities for production of bydrodAi 
pa. 
2. Cot included in navigation pauct. 
3. Estimate includes Code 710 funds. 
4, Comstructed by State of Oklahoma under the name d 
Robert &. Kerr Dam (Lake Hudson). Estimate shown is for 
Federal participation. 
& Inactive. Estimate is based on 1964 price levels. 
&. Constructed by State of Oklahoma under the name 
GrandRiver Dam(LakeO'TheCherokees). Estimateshown is 
for Federal participation. 
7. Estimate includes Code 710 funds and presentestimate 
cost of power units. 
1
1
1
I
I
1

REPORT OF THE CHIEF OF ENGINEERS U.S. ARMY 1988 
TABLE 18-J LITTLE RIVER BASIN ARKANSAS 
(See Section 15 ok Text) 
Plneet Rier Site' Neart Town 
DeQu Lake' Rolling Fork River 228 DeQuen, AR 
Gillhan Lake Coeastot River 49.0 Gillhan, AR 
Dierks Lake' Saline River 56.6 Dierks, AR 
Millwood Lake' Little River 18.0 Millwood, AR 
1. Project is reported separately herein. 
18.n

TABLE 18-K WHITE RIVER BASIN; AR, AND MO 
(See Section 16 of Text) 
Miles Dralage Rmerve r Pwer Ttal 
Above AresHeght of Dam aCapiy Devepent E nated 
Lake River Meuth Nearest Town (sq ml) and Type (wre-feet) (kwats) Cet- 
Beavere White 609.0 Eureka Springs, AR 1,186 228 feet concrete-gravity and earthfill 1,962,000 112,000 $ 50,797,000 
Bell Foley Strawberry 27.2 Poughkeepsie, AR 519 136 feet mcncrete-gravity and earthfill 518,000 () 60,000,000 
Bull Slmais' White 418.6 Mountain Home, AR 6,086 258 feet concrete-gravity 5,408,000 340,000 96,356,000 
Clearwater Black 257.4 Piedmont, MO 898 154 feet emrthfll 413,000 () 11,395,000 
Greens Ferry' Little Red 79.0 Heber Springs, AR 1,146 243 feet conerete-gravity 1,844,000 96,000 55,125,00 
Norbrk' North Fork 4.8 Norfork, AR 1,806 216 feet concrete-gravity 1,983,000 80,560 111,884,000 
Table Rocks White 528.8 Branson, MO 4,020 252 feet concrete-gravity and earthfill 3,4862,000 200,000 71,288,000 
Village Creek, 
Jackson and Village Creek, 
Counties, AR* White River 0-61.2 Walnut Ridge, AR 283 
White River 
Fish Hatchery White 608.3 Eureka Springs, AR - - - () 6,000,000 
Total 15,580,000 828,550 472,110,000 
1. Current FY price levels unless otherwise noted. 
2. For details of this project, see individual report. 
3. None. 
4. Inactive-reclassified June 1977. 
f

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1988 
TABLE 18-L FLOOD CONTROL WORK 
UNDER SPECIAL AUTHORIZATION 
(Section 205, PL 858, 80th Cong., as mended (Preauthorizatlon) 
(See Section 27 of Text) 
Fiscal Year 
Study Identifieation Date Status Costs 
Bentonville, Southeast AR Aug 1988 Reconnaissance1 
Black River, South Poplar Bluff, MO Aug 1968 Recon 
Black River, Leeper, MO Aug 1968 Negative $ 7.500 
Blossom way Creek Rogers, AR Aug 1988 Expanded boon 7,500 
Clear Crek Wahinjton Co AR Sep 1988 NegatIve 7,500 
Crooked Cre Harrlson, AA Aug 1963 Reon 
Dry Jordan Creek, Harrison AR Aug 1963 Recon1 
Holly & Dierks Creeks, Dierks, AR Aug 1968 Recon 
Howell Creek & TrIbutarie, West Plains, MO Sep1982 DPR/P&S 13695 
Hurricane Creek, Ashdown, AR Sep 1988 boon 
Kellekv Creek, Monett, AR ep 1988 Expanded Recon 7,500 
Little Mmsard Creek, Fort Smith, AP p 1983 Construction 1600 
Little Red River Tributare Clinton AR Feb1983 DPR/P&S 194758 
a& Dickson Creeks, Ellnston, MO Feb 1963 Expanded Reon 5885 
MeKSl e Creek, Piedmont, MO Sep 1988 Expanded Reon 7,500 
Mill Spring MO Aug 1983 Negative 7,500 
Mine & D cisCornee ks, Nashville, AR Aug 1963 EpandeRd con 14949 
Newport, Eastide Drainage, AR Dec 1982 ve 8,445 
Otter Creek & Trib. Shannon Hills, AR Se 1963 C 69,042 
Pike Creek, Pplar bluff, MO Feb 1968 Expanded Reon 50996 
Polk Bayou, Bateaville, AR Jun 1968 Negative 4.874 
Prairie Creek, Russellville, AR Nov 1988 Reon 7,500 
Rose City, North Little Rock, AR Sep 1988 Negative 7,500 
Spring River, Hardy, AR Aug 1988 Reon 
Sulphur Creek, Heber Springs, AR Aug 1988 Recon 
Tributarv2, Bentonville, AR Mar 1988 Expanded Recon 54,99 
White , Batesville, AR Aug 1968 Expanded Recon 10700 
White River, Jacksonport, AR Sep 1988 Construction 284,948 
White River, Norfork, AR Apr 1968 Negative 4,000 
L Initiated under District Commander's delegated authority to use the Revolving Fund. 
2. Project evolved from the Fort Smith/Van Buren general investigation study. 
18-24

LITTLE ROCK, AR, DISTRICT 
TABLE 18-M JOBS ACT CONTRACTS AWARDED 
DURING FY 83 (P.L 98-8, March 24, 1983) 
Project Funding FY 8 
McClellan-Kerr Arkansas River Navigation System (Little Rock District) Maint 
Ap p. $1,842,000 
Caop 1,087,700 
Dardanelle Lock & Dam, Arkansas River Basin, Arkansas Maint. ~159,000 Approp. 159,0 
Cuit 89,80 
Ozark-Jeta Taylor Lock & Dam, Arkansas River Basin, Arkansas M eaiMt. 
Apprep 139,00 
Cit 189,000 
Blue Mountain Lake, Arkansas River Basin, Arkansas Maint. 
Approp 87,400 
Cost 34,600 
Nimrod Lake, Arkansas River Basin, Arkansas Maint. 
Approp. 45,000 
Cost 4,000 
Beaver Lake, White River Basin, Arkansas Maint. 
Approp. 53,000 
Cost 53,000 
Bull Shoals Lake, White River Basin, Arkansas and Missouri Maint. 
Approp.C luit157,900 415,00 
Clearwater Lake, White River Basin, Missouri Maint. 
Approp. 45,000 
Cost 45,000 
Greers Ferry Lake, White River Basin, Arkansas Maint 
Approp. 128,000 
Cost 106,700 
Norfork Lake, White River Basin, Arkansas MaAinptrop. 75,900 
Cost75,90 
Table Rock Lake, White River Basin, Missouri Maint. 
Approp. 460,800 
Cost 165,800 
DeQueen Lake, Little River Basin, Arkansas Maint 
Approp. 2,000 
Cost26,000 
Dierks Lake, Little River Basin, Arkansas Maint. 
Approp. 120,000 
Cost 29,600 
Gillham Lake, Little River Basin, Arkansas Maint. 
Approp. 143,000 
Cost 56,900 
Millwood Lake, Little River Basin, Arkansas Maint. 
Approp. 162,000 
Cost 62,100 
Little Massard Cresk. Arkamas River Basin, Fort Smith, Arkansas New Work 
Aprop. 80,00 Cost 1,100 
Otter Creek & Tributaries Arkansas River Basin, Shannon Hills, Arkansas New Work 
ACpopt0rop. 257,000 
18-25

TULSA, OKLAHOMA, DISTRICT* 
The civil works portion of this District covers an area of 
approximately 160,000 square miles including Oklahoma 
and parts of Kansas and Texas within the Arkansas 
and Red River Basins. The District's responsibilities 
within the Arkansas River Basin cover southern Kansas, 
northern Oklahoma, and the Txas Panhandle in northern 
Thxas. These areas are embraced in the drainage 
basin of the Arkansas River and its tributaries above the 
mouth of the Poteau River, inclusive, and below the 
mouth of the Walnut Creek near Great Bend, KS, extending 
to the Kansas-Colorado state line, exclusive of that 
portion of the South Canadian Basin and its tributaries 
west of the Thxas-New Mexico state line. The District's 
responsibilities within the Red River Basin cover the 
northern portion of Thxas, and the southern portion of 
Oklahoma embraced in the Red River drainage basin and 
its tributaries above Fulton, AR. The District also has 
responsibility for the planning, design, construction, and 
operation and maintenance of the McClellan-Kerr 
Arkansas River Navigation System in Oklahoma. 
IMPROVEMENTS 
Navigation Page 
1. Big and Little Sallisaw Creeks Navigation 
Project, OK ............................ 19-2 
2. Arkansas River Basin, AR, OK, and KS... 19-2 
3. Bank Stabilization and Channel 
Rectification, Arkansas River, AR and OK 19-3 
4. Maintenance and Repair Fleet and Marine 
Terminals, OK ........................ 19-3 
5. Red River Waterway, LA, AR, OK, and TX, 
Index, AR to Denison Dam, TX ........... 19-3 
6. Other Authorized Navigation Projects .... 19-4 
7. Navigation Work under Special 
Authorization (Poteau River)............ 19-4 
Flood Control 
8. Arcadia Lake, Deep Fork River Basin, 
OK ................................... 19-4 
9. Arkansas-Red River Basins Chloride 
Control ................................ 19-4 
9A. Arkansas-Red River Basins Chloride Control, 
Part I- Wichita River Basin, TX ........ 19-5 
9B. Arkansas-Red River Basins Chloride Control, 
Part II- Remaining Red River Basin, 
OK and TX ............................ 19-5 
9C. Arkansas-Red River Basins Chloride Control, 
Part II- Arkansas River Basin, OK ..... 19-5 
10. Big Pine Lake, Red River Basin, TX ...... 19-6 
11. Birch Lake, Verdigris River Basin, OK ... 19-6 
12. Candy Lake, Verdigris River Basin, OK... 19-6 
13. Canton Lake, Arkansas River Basin, OK.. 19-6 
14. Copan Lake, Verdigris River Basin, OK... 19-7 
15. Council Grove Lake, Grand (Neosho) 
River Basin, KS ....................... 19-7 
16. El Dorado Lake, Walnut River Basin, KS . 19-7 
17. Elk City Lake, Verdigris River Basin, KS . 19-7 
18. Fall River Lake, Verdigris River Basin, 
K S ................................... 19-8 
Flood Control (cont) Page 
19. Fort Supply Lake, North Canadian River Basin, 
OK ................................... 19-8 
20. Great Salt Plains Lake, Arkansas River Basin, 
OK ................................... 19-8 
21. Heyburn Lake, Arkansas River Basin, 
OK ................................... 19-8 
22. Hugo Lake, Kiamichi River Basin, OK .... 19-8 
23. Hulah Lake, Verdigris River Basin, OK ... 19-9 
24. John Redmond Dam and Reservoir, 
Grand (Neosho) River Basin, KS ......... 19-9 
25. Kaw Lake, Arkansas River Basin, OK .... 19-9 
26. Lake Kemp, Wichita River Basin, TX ..... 19-9 
27. Lukfata Lake, Little River Basin, OK 
and AR ............................... 19-9 
28. Marion, KS ........................... 19-10 
29. Marion Lake, Grand (Neosho) River Basin, 
K S ................................... 19-10 
30. Oologah Lake, Verdigris River Basin, OK. 19-10 
31. Optima Lake, North Canadian River 
Basin, OK ............................ 19-10 
32. Pat Mayse Lake, Red River Basin, TX .... 19-10 
33. Pearson-Skubitz Big Hill Lake, Verdigris 
River Basin, KS ....................... 19-11 
34. Pine Creek Lake, Little River Basin, TX .. 19-11 
35. Red River Below Denison Dam 
(Tulsa District) ......................... 19-11 
36. Sardis Lake, Little River Basin, OK ...... 19-11 
37. Shidler Lake, Arkansas River Basin, OK.. 19-12 
38. Skiatook Lake, Verdigris River Basin, 
OK ................................... 19-12 
39. Toronto Lake, Verdigris River Basin, KS.. 19-12 
40. Waurika Lake, Red River Basin, OK ...... 19-12 
41. Wister Lake, Poteau River Basin, OK ..... 19-13 
42. Inspection of Completed Flood Control 
Projects ............................... 19-13 
19-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Flood Control (cont) Page 
43. Scheduling Flood Control Reservoir 
Operations ............................ 19-13 
43A. Altus Reservoir, Red River Basin, OK .... 19-13 
43B. Arbuckle Reservoir, Red River Basin, OK. 19-13 
43C. Cheney Reservoir, Ninnescah River 
Basin, KS ............................. 19-13 
43D. Fort Cobb Reservoir, Washita River Basin, 
OK ................................... 19-13 
43E. Foss Reservoir, Washita River Basin, OK . 19-13 
43F. Mountain Park Reservoir (Tom Steed Lake), 
Red River Basin, OK ................... 19-13 
43G. Norman Reservoir (Lake Thunderbird), 
Red River Basin, OK ................... 19-13 
43H. Sanford Dam (Lake Meredith), Canadian 
River Basin, OK ....................... 19-13 
44. Other Authorized Flood Control Projects.. 19-14 
45. Flood Control Work under Special 
Authorization ......................... 19-14 
Multiple-Purpose Projects Including Power 
46. Broken Bow Lake, Little River Basin, OK. 19-14 
47. Denison Dam-Lake Texoma, Red River 
Basin, TX and OK ..................... 19-14 
48. Eufaula Lake, Canadian River Basin, OK. 19-14 
49. Fort Gibson Lake, Grand (Neosho) 
River Basin, OK ....................... 19-15 
50. Keystone Lake, Arkansas River Basin, 
OK ................................... 19-15 
51. Markham Ferry Reservoir (Lake Hudson), 
Grand (Neosho) River Basin, OK ......... 19-15 
52. Pensacola Reservoir (Grand Lake), 
Grand (Neosho) River Basin, OK ......... 19-15 
53. Robert S. Kerr Lock and Dam and Reservoir, 
Arkansas River Basin, OK.............. 19-16 
54. Tenkiller Ferry Lake, Illinois River 
Basin, OK ............................ 19-16 
Multiple-Purpose Projects Including Power (cont) 
55. Webbers Falls Lock and Dam, Arkansas River 
Basin, OK ............................ 19-16 
General Investigations 
56. Surveys...............................19-16 
57. Collection and Study of Basic Data ....... 19-17 
58. Continuation of Planning and 
Engineering .......................... 19-17 
59. Advanced Engineering and Design ....... 19-17 
Tables 
19-A Cost and Financial Statement........... .19-18 
19-B Authorizing Legislation ................. 19-22 
19-C Not Applicable 
19-D Not Applicable 
19-E Other Authorized Flood Control Projects .. 19-24 
19-F Not Applicable 
19-G Not Applicable 
19-H Arkansas River Basin: Multiple Purpose 
Plan .................................. 19-25 
19-I Arkansas-Red River Basins Chloride Control, 
Part I - Wichita River Chloride Control 
Plan, TX .............................. 19-25 
19-J Arkansas-Red River Basins Chloride Control, 
Part II- Red River Plan, OK and TX ..... 19-26 
19-K Red River Below Denison Dam Flood Control 
Plan (Tulsa District) ................... 19-26 
19-L Inspection of Completed Flood Control 
Projects................................ 19-27 
19-M Flood Control Work Under Special 
Authorization ......................... 19-27 
19-N Jobs Act Contracts Awarded During 
FY 83 (P.L. 98-8) ...................... 19-28 
Navigation 
1. BIG AND LITTLE SALLISAW 
CREEKS, OK 
Location. About 3 miles southwest of Sallisaw, 
Sequoyah County, OK, approximately 5 miles from the 
existing navigation sailing line upstream on Big Sallisaw 
Creek and Little Sallisaw Creek (about navigation 
mile 341.6). 
Existing project. The plan of improvement consists of 
a 9-foot-deep, 100-foot-wide navigation channel extending 
from near Sallisaw, OK, to the existing McClellan- 
Kerr Arkansas River Navigation System and of a 400- by 
500-foot turning basin. (See table 19-B for authorizing 
legislation.) Estimated Federal cost is $5,700,000 (October 
1983 price levels). Preconstruction Phase I General 
Design Memorandum approved 12 July 1982. 
Local cooperation. See section 2 of this report. 
Operations and results during fiscal year. Not 
applicable. 
2. ARKANSAS RIVER BASIN, AR, OK, 
AND KS 
Location. The Arkansas River rises in the Rocky 
Mountains near Leadville, Colorado, and flows southeastward 
1,396 miles through Colorado, Kansas, Oklahoma, 
and Arkansas to join the Mississippi River 599 
miles above Head of Passes, LA. (See Geological Survey 
state maps, scale 1:500,000; and flood control and navigation 
maps of the Mississippi River, Cairo, IL, to the Gulf of 
Mexico, 1980 edition, scale 1:62,500.) 
Existing project. Provides for improvement of the Arkansas 
River Basin by construction of coordinated developments 
for navigation, hydroelectric power, flood 
control, water supply, water quality control, sediment 
control, recreation, and fish and wildlife propagation. 
McClellan-Kerr Arkansas River Navigation System provides 
a channel 9 feet deep and 445.2 miles long beginning 
at the mouth of the White River, which enters the 
Mississippi River 599.0 miles above Head of Passes, LA; 
thence 9.8 miles upstream to mouth of the Wild Goose 
19-2

TULSA, OKLAHOMA DISTRICT 
Bayou; thence 9.2 miles by a land cut, designated as 
Arkansas Post Canal, to mile 42.0 (1943 survey) on the 
Arkansas River; thence 376.0 miles along the channel of 
the latter stream to the mouth of the Verdigris River at 
navigation mile 395.0; thence 50.3 miles up the Verdigris 
River to the head of navigation at Catoosa, OK. The 
waterway is canalized throughout its length by 17 locks 
and dams with a total lift of 420 feet. Dardanelle, AR, 
Ozark-Jeta Thylor, AR, Robert S. Kerr, OK, and Webbers 
Falls, OK are multiple-purpose projects including power. 
Lock chambers are 110 by 600 feet. A minimum channel 
width of 150 feet is provided for the Verdigris River, and 
300 feet for the Arkansas Post Canal and White River. 
Other coordinated developments consist of 15 lakes, 13 of 
which are in the Tlhisa District, KS and OK, and two in 
the Little Rock District, AR. The authorized projects of 
the multiple-purpose plan within the Thlsa District are 
listed in table 19-H. Federal costs for combined comprehensive 
and multiple-purpose plan total 
$1,317,607,935. Status of individual items are reported 
separately in this chapter. 
Local cooperation. For the navigation system, local 
interest must provide adequate terminal and transfer 
facilities and bear increased cost of maintenance and 
operation of all altered rail and highway routes, including 
bridges and appurtenances, utilities, and other existing 
improvements, other than federally owned. Requirements 
for each individual lake are designated in 
each project write-up beginning with Section 8 of this 
report. 
'Ibrminal facilities. Public port facilities were in operation 
at Pine Bluff, Little Rock, Dardanelle and Fort 
Smith, AR, and Muskogee and Catoosa (Thlsa), OK. Port 
authorities have been organized to develop public 
facilities at North Little Rock, Dardanelle-Russellville, 
Clarksville, and Van Buren, AR, and at Sallisaw, OK. 
Private commercial port facilities are complete and in 
operation at seven locations in Arkansas and at eight 
locations in Oklahoma. 'Tbn additional private port 
facilities are being developed along improved waterways 
in Arkansas. 
Operations and results during fiscal year. The following 
navigational projects in the McClellan-Kerr Arkansas 
River Navigation System were in operation: Blue 
Mountain, Dardanelle Lock and Dam (No. 10), Dardanelle 
Marine Thrminal, David D. Thrry Lock and Dam 
(No. 6), Locks and Dams Nos. 2, 3, 4, 5, 9, and 13, Murray 
Lock and Dam (No. 7), Nimrod, Norrell Lock and Dam 
(No. 1), Ozark-Jeta Thylor Lock and Dam (No. 12), Pine 
Bluff Marine 'Ibrminal, and 'bad Suck Ferry Lock and 
Dam (No. 8) in the Little Rock, AR District; Canton, 
Chouteau Lock and Dam (No. 17), Elk City, Eufaula, Fall 
River, Fort Gibson, Keystone, Markham Ferry, Newt 
Graham Lock and Dam (No. 18), Oologah, Pensacola, 
Robert S. Kerr Lock and Dam and Reservoir (No. 15), 
Robert S. Kerr Marine 'Irminal, 'Tnkiller Ferry, 'Ironto, 
W.D. Mayo Lock and Dam (No. 14), Webbers Falls 
Lock and Dam (No. 16), and Wister in the Thlsa, OK 
District. Lakes in Oklahoma and Kansas are described in 
the following pages. Chouteau Lock and Dam (No. 17), 
Newt Graham Lock and Dam (No. 18), and W.D. Mayo 
Lock and Dam (No. 14) are detailed with other projects in 
appendix C under McClellan-Kerr Arkansas River Navigation 
System. 
3. BANK STABILIZATION AND 
CHANNEL RECTIFICATION, 
ARKANSAS RIVER, AR AND OK. 
Location. On the Arkansas River between Robert S. 
Kerr Damsite, OK, river mile 336.2, and Fort Smith, AR, 
river mile 308.0. (See Geological Survey maps for Sans 
Bois, OK, Sallisaw, OK, and Fort Smith, AR, quadrangles, 
scale 1:125,000.) 
Existing project. Bank stabilization and channel rectification 
is a part of the McClellan-Kerr Arkansas River 
Navigation System. For description of completed improvement 
and authorizing legislation see Annual Report 
for FY 1970. Federal cost was $12,700,038 for the 
portion of the project located in the Thlsa District. Construction 
began in May 1952 and was completed December 
1969. 
Local cooperation. See section 2 of this report. 
Operations and results during fiscal year. Operation 
and maintenance of project structures is reported 
and under appropriate navigation locks and dams. 
4. MAINTENANCE AND REPAIR 
FLEET AND MARINE TERMINALS, 
OK. 
Consists of one terminal in the Thlsa District (near 
Sallisaw, OK), and two terminals in the Little Rock District. 
(See table 19-B for authorizing legislation.) Information 
on this project follows: 
ROBERT S. KERR MARINE TERMINAL, OK. 
Location. Five miles south of Sallisaw, OK, on the left 
side of the Robert S. Kerr Lock and Dam (No. 15) and 
Reservoir. 
Existing project. Consists of wharf, office and storage 
building, storage space, operating areas for servicing 
floating plant and storage of machinery, equipment, and 
supplies to maintain the navigation facilities. Federal 
cost was $2,760,000 excluding the cost of facilities to be 
provided for the US Coast Guard on a reimbursable basis. 
Construction began in May 1967 and the terminal became 
operational in October 1970. 
Local cooperation. See section 2 of this report. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. 
5. RED RIVER WATERWAY, LA, AR 
OK, AND TX; INDEX, AR TO LAK~E 
TEkOMA-DENISON DAM, TX 
('Ilsa District). 
Location. On the Red River in Arkansas, Oklahoma, 
and 'Ibxas, between Index, AR, and Lake Texoma- 
Denison Dam, TX. (See Geological Survey State maps 
and folio maps of Red River, 1958 edition.) 
Existing project. Plan of improvement provides for 
channel realignment and river bank stabilization by 
dredging, cutoffs, and training works, including revetments, 
dikes, and steel jetties. The overall length of the 
Red River channel in this reach would be reduced from 
19-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
about 250 river miles to 200 miles. In addition, the authorized 
project provides for public use recreational development 
at various river cutoffs formed by the 
realigned channel. Estimated Federal cost is 
$209,000,000 (October 1983 price levels). (See table 19-B 
for authorized legislation.) Preconstruction planning 
studies were initiated in December 1980. A review of the 
potential for extending navigation to Denison Dam concluded 
that project costs would exceed project benefits 
and that further navigation studies are not warranted at 
this time. No funds are budgeted to continue preconstruction 
planning for the authorized bank stabilization project 
in fiscal year 1984. Preconstruction planning studies 
will resume when funds are appropriated. 
Local cooperation. Section 3, Flood Control Act of 
June 22, 1936 applies. In addition, non-Federal interests 
are required to make a cash contribution equal to onehalf 
the cost of recreation development, and 26.1 percent 
of the total construction cost for bank stabilization and 
channel works. The total estimated non-Federal cost is 
$88,000,000. 
Operations and results during fiscal year. Not 
applicable. 
6. OTHER AUTHORIZED 
NAVIGATION PROJECTS. 
Red River from Fulton, AR, to the mouth of the Washita 
River. For description of completed improvement and authorization 
see Annual Report for 1924. Cost for construction 
was $378,574 and operation and maintenance cost 
was $182,157. Curtailment of project was recommended 
in H. Doc. 947, 64th Congress, 1st Session. 
7. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION. 
Navigation activities pursuant to Section 107, Public 
Law 86-645. 
Poteau River, AR and OK. 
Location. The Poteau River Small Navigation Project 
is located at Fort Smith, AR. 
Existing project. The project provides for a 130-footwide, 
9-foot-deep channel on the Poteau River extending 
from its confluence with the Arkansas River 1.7 miles 
upstream to the Port of Fort Smith. A turning basin is 
provided a short distance upstream of the port. (See table 
19-B for authorizing legislation.) Cost for the project was 
$536,952 Federal and $25,000 non-Federal. Project completed 
and placed in operation in November 1979. 
Local cooperation. Section 107, River and Harbor Act 
of 1960 applies. 
'brminal facilities. 'Ibrminal facilities are owned by 
the Fort Smith Port Authority. 
Operations and results during fiscal year. Contract 
was completed in October 1979 in the amount of 
$434,740. 
Flood Control 
8. ARCADIA LAKE, DEEP FORK 
RIVER BASIN, OK. 
Location. On the Deep Fork River, river mile 213.8, in 
the metropolitan area of Oklahoma City and Edmond, 
OK, about 1.5 miles west of Arcadia, in Oklahoma 
County, OK. (See Geological Survey map for Arcadia, 
OK, quadrangle, scale 1:24,000.) 
Existing project. The plan of improvement provides 
for flood control, water supply, and recreation by construction 
of an earthfill dam approximately 104 feet high 
and 5,200 feet long with a high-level uncontrolled spillway. 
Outlet works will consist of gate tower and conduit. 
The lake will have a total capacity of 92,000 acre-feet 
(27,570 for conservation, 64,430 for flood control, and 190 
for sedimentation reserve), and will control a drainage 
area of 105 square miles. Estimated cost is $82,600,000 
(October 1983 price levels). (See table 19-B for authorizing 
legislation.) Construction began in October 1980. The 
project is 51 percent complete. 
Local cooperation. Section 2, Flood Control Act of 
1938, Water Supply Act of 1958, Federal Water Project 
Recreation Act of 1965, and Section 221, Flood Control 
Act of 1970 apply. 
Operations and results during fiscal year. Major 
accomplishments with regular funds: land acquisition 
and damages $4,688,000; embankment and spillway 
$3,352,000; relocations $3,092,000; outlet works 
$5,548,624; county roads $1,675,000. 
9. ARKANSAS-RED RIVER BASINS 
CHLORIDE CONTROL. 
Location. On certain tributary streams of the Arkansas 
and Red Rivers in the western half of the 'lThlsa 
District. 
Existing project. Provides for construction of project 
features to control the natural water pollution caused by 
the fifteen natural salt sources identified in 1957 by the 
US Public Health Service. The Arkansas and Red Rivers 
represent a major national and regional water resource 
which is severely limited because of poor water quality 
primarily caused by a natural pollutant, sodium chloride. 
The Arkansas River is polluted by five naturally occurring 
salt sources located in northwestern Oklahoma and 
southwestern Kansas. Those areas contribute an estimated 
7,900 tons per day of chlorides to the river. The Red 
River is polluted by ten naturally occurring salt sources 
located in northwestern Thxas and southwestern Oklahoma. 
Those sources contribute an estimated 3,600 tons 
per day of chlorides to the river. 
Preauthorization studies were completed in 1966 and 
1970 and recommended construction of project features at 
thirteen of the fifteen sites. Area V, located on Prairie Dog 
bwn Fork of the Red River in Hall County, TX, was 
constructed as an experimental project. It has been operational 
since 1964. Construction was authorized on the 
remaining twelve sites in two parts. Construction of the 
project for three salt areas in the Wichita River Basin 
(Part I) was authorized by the Flood Control Act of 1966 
(SD 110/89/2). During the early stage of the AE&D work 
performed after authorization, an administrative decision 
was made to separate further project development 
work on Part II by basin. Project features on Part I, 
Wichita River Basin, Part II, remaining Red River Basin 
and Part II, Arkansas River Basin are reported respectively 
under Sections 9A, 9B, and 9C. 
19-4

TULSA, OKLAHOMA DISTRICT 
Local cooperation. Prior to construction of chloride 
control projects, responsible non-Federal interests will 
furnish satisfactory assurances to the Secretary of the 
Army. These interests will continue and strengthen efforts 
to reduce manmade salt pollution, to hold and save 
the United States free from damages due to water rights 
claims and to construction and operation of the project 
works, and to participate in the cost of recreation and fish 
and wildlife enhancement as a part of the Arkansas 
Basin project in accordance with the Federal Water Project 
Recreation Act. Both the states of Oklahoma and 
Tbxas have provided necessary assurances and have 
made significant progress toward reducing manmade 
pollution. 
9A. ARKANSAS-RED RIVER BASINS 
CHLORIDE CONTROL PART IWICHITA 
RIVER BASIN, TX. 
Location. The Wichita River Basin, a major sub-basin 
within the Red River Basin, contains three salt source 
areas and two disposal areas. Area VII is located on the 
North Fork of the Wichita River in Cottle County, TX. 
The disposal area for Area VII, Crowell Brine Lake, is 
located on Canal Creek, a Pease River tributary in Foard 
County, TX. Area VIII is located on the South Fork of the 
Wichita River in King County, TX. Area X is located on 
the Middle Fork of the Wichita River in King County, TX. 
The disposal area for Areas VIII and X, TIkuscott Brine 
Lake, is located on Bluff Creek, a tributary of the Wichita 
River in Knox County, TX. 
Existing project. The plan of improvement consists of 
low-flow dams with attendant pumping stations and 
pipeline facilities located at each salt source area. The 
collented brine will be discharged into two off-channel, 
total retention, brine storage reservoirs. Each low-flow 
dam will be equipped with a inflatable fabric-type weir 
located in the spillway section which would be deflated to 
pass relatively good quality high flows downstream. 
Additional information on the plan is presented in table 
19-I. Estimated cost of the Wichita River Basin project 
including Areas VII, VIII, and X and 'Iuscott Brine Lake 
and Crowell Brine Lake is $108,923,000 (October 1983 
price levels). Preconstruction planning for Area VII and 
X is essentially complete and construction is awaiting 
approval from the Secretary of the Army and subsequent 
funding from Congress. Construction was initiated at 
Area VIII and 'fruscott Brine Lake in 1976. Construction 
of Area VIII is 97 percent complete. 
Local cooperation. See section 9 of this report. 
Operations and results during fiscal year. Major 
accomplishments with regular funds: Approximately 
$5,300,000 was expended in FY 83 for construction at 
Tuscott Brine Lake. These funds were used to continue 
construction of the pumps and controls for the Bateman 
Pump Station, to initiate construction of the Knox 
County road relocation, and to complete 'Iruscott Brine 
Dam. 
9B. ARKANSAS-RED RIVER BASIN 
CHLORIDE CONTROL, PART IIREMAINING 
RED RIVER BASIN, 
OK AND TX. 
Location. The remaining Red River Basin contains 
five salt source areas and two disposal areas. Area VI and 
its disposal area are located on the Elm Fork of the north 
fork of the Red River in Harmon County, OK. Area IX is 
located on the Middle Pease River in Cottle County, TX. 
Areas XIII- XIV are located on tributaries of the Prairie 
Dog 'Ibwn Fork of the Little Red River in Childress 
County, TX. Area XV is located on the Little Red River in 
Hall County, TX. The other disposal area, Crowell Brine 
Lake, is located in Canal Creek, a tributary of the Pease 
River in Foard County, TX. Crowell Brine Lake is also the 
disposal area for Area VII as discussed in Section 9A. 
Existing project. Design efforts for Area XV have 
been deferred at this time due to economic conditions. 
The plan of improvement for Area IX consists of a lowflow 
weir and an attendant pumping station and pipeline 
facility to pump the collected brine to Crowell Brine 
Lake, a total retention brine storage reservoir. The collection 
facilities for Areas XIII and XIV will be shallow 
wells and accompanying collection pipelines to collect the 
brine in the subsurface aquifer. The collected brine will 
be disposed of by deep well injection. The plan of improvement 
for Area VI consists of a system of dikes and 
channels for surface collection of the brine and attendant 
pumping facilities to transmit the brine to the total retention 
reservoir at the disposal site. Additional information 
on the plan is presented in Table 19-J. Estimated cost 
of the remaining Red River Basin (Areas VI, IX, XIIIXIV) 
is $72,600,000 (October 1983 price levels) which 
excludes the Crowell Brine Lake (see estimated cost, 
Section 9A) and Area XV and a portion of Area IX which 
have been deferred. Preconstruction planning for Area 
VI is essentially complete and construction is waiting 
approval from the Secretary of the Army and subsequent 
funding from Congress. The Phase II GDM for Areas IX, 
XIII-XIV is complete. 
Local cooperation. See section 9 of this report. 
Operations and results during fiscal year. Major 
accomplishments with regular funds: Approximately 
$140,000 was expended in FY 83 for analyses of the feasibility 
of salt gradient solar ponds and coordination with 
state and local interests on cost sharing. 
9C. ARKANSAS-RED RIVER BASINS 
CHLORIDE CONTROL, PART IIARKANSAS 
RIVER BASIN, OK. 
Location. There are four salt areas on tributaries of 
the Arkansas River in Oklahoma: Area I, Great Salt 
Plains, located on the Salt Fork of the Arkansas River, in 
Alfalfa County, OK; Areas II-III, Big and Little Salt 
Plains, located on the main stem of the Cimarron River 
and its tributary, Buffalo Creek, in Woods, Woodward, 
and Harper Counties, OK; and Area IV located on Salt 
19-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Creek, a tributary of the Cimarron River in Blaine 
County, OK. 
Existing project. The selected chloride control plan 
consists of the freshwater diversion concept for Area I, 
with division of the existing Great Salt Plains Lake into a 
brine lake and a freshwater lake. The freshwater diversion 
concept uses a series of dams, dikes, and channels to 
divert the freshwater around the brine source. The 
freshwater diversion concept is also selected for Areas 
II-III, with a multipurpose component, Englewood Lake. 
The selected plan for Area IX is based on the collect and 
dispose concept. Brine is collected behind an inflatable 
dam then pumped to a brine lake for storage. Additional 
information on the plan is presented in table 19-J. Estimated 
Federal cost is $663,800,000 (October 1983 price 
levels) for the control of the four areas. The final of the 
Phase I GDM No. 32 for Areas I, II-III and IV was submitted 
in September 1981. In GDM No. 32, it was recommended 
that further studies for the Arkansas River 
Basin portion of the Arkansas-Red River Basin Chloride 
Control Project be deferred until a significant change 
occurs in present or projected conditions that would 
clearly demonstrate a greater need and probable use of 
the improved water. The Arkansas River portion was 
deferred in December 1982. 
Local cooperation. See section 9 of this report. 
Operations and results during fiscal year. None. 
10. BIG PINE LAKE, RED RIVER 
BASIN, TX. 
Location. On Big Pine Creek, river mile 16.5, approximately 
22 miles northwest of Clarksville, Red River 
County, TX. (See Geological Survey maps for WOODLAND, 
Manchester, and Kiomatia, TX, quadrangles, 
scale 1:62,500; and Defense Mapping Agency map, 
Thxarkana, TX, scale 1:25,000.) 
Existing project. The plan of improvement provides 
for an earthfill dam 10,190 feet long, including an uncontrolled 
concrete chute spillway. Outlet works will consist 
of a 6-foot-diameter inlet conduit and a stilling basin. A 
30-inch water supply pipe and a 24-inch low-flow pipe 
will be constructed through the dam. The lake will have a 
total capacity of 174,400 acre-feet, of which 74,450 acrefeet 
will be allocated for flood control and 99,950 acre-feet 
for conservation and sedimentation reserve. The lake 
will control a drainage area of 95 square miles. Estimated 
cost is $58,600,000 (October 1983 price levels). (See table 
19-B for authorizing legislation.) Phase II of the General 
Design Memo is complete. 
Local cooperation. Section 2, Flood Control Act of 
1938, Water Supply Act of 1958, as amended, and Section 
221, Flood Control Act of 1970 apply. 
Operations and results during fiscal year. None. 
11. BIRCH LAKE, VERDIGRIS RIVER 
BASIN, OK. 
Location. On Birch Creek, river mile 0.8, about 1.5 
miles south of Barnsdall in Osage County, OK. (See 
Geological Survey map for Barnsdall, OK, quadrangle, 
scale 1:24,000.) 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for FY 1979. Federal cost is $13,548,848. Construction 
began in November 1973. Project placed in useful 
operation in March 1977. 
Local cooperation. Section 2, Flood Control Act of 
1938, Water Supply Act of 1958, as amended, and Section 
221, Flood Control Act of 1970 apply. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. Two noteworthy 
rises occurred above the lake. Operation of the lake prevented 
flooding on 1,600 acres of land. Estimated monetary 
benefits attributed to Birch Lake operations for the 
prevention of flood damages total $1,587,000 to September 
30,1983. 
12. CANDY LAKE, VERDIGRIS RIVER 
BASIN, OK. 
Location. On Candy Creek, river mile 1.9, a tributary 
of Bird Creek in Verdigris River Basin. Damsite is about 1 
mile northeast of Avant, Osage County, OK. (See Geological 
Survey map for Avant, OK, quadrangle, scale 
1:24,000.) 
Existing project. The plan of improvement provides 
for an earthfill dam about 4,200 feet long, including an 
uncontrolled concrete spillway, with a maximum height 
of 103 feet above streambed. Outlet works will consist of a 
gated intake structure, a 10- by 11.25-foot conduit, and a 
stilling basin. An 18- by 30-inch low-flow pipe and an 
18-inch water supply pipe will be provided. The lake will 
have a total capacity of 75,420 acre-feet (44,160 for conservation 
and sediment reserve and 31,260 for flood control). 
Drainage area above the damsite is 43 square miles. 
Candy Lake will be operated as a unit of a seven-lake 
system for flood control in the Verdigris River Basin in 
Oklahoma. Estimated cost of the project is $38,300,000 
(October 1983 price levels). (See table 19-B for authorizing 
legislation.) Construction began in September 1976. 
The project is about 15 percent complete. Construction 
has been delayed because of the US Justice Department's 
decision to withdraw condemnation proceedings to acquire 
mineral rights. 
Local cooperation. Section 2, Flood Control Act of 
1938, Water Supply Act of 1958, and Section 221 of the 
Flood Control Act of 1970 apply. 
Operations and results during fiscal year. None. 
13. CANTON LAKE ARKANSAS 
RIVER BASIN, 6K. 
Location. On the North Canadian River, about 394 
miles above its mouth and about 2 miles north of Canton, 
Blaine County, OK. (See sectional aeronautical chart, 
Wichita sheet, scale 1:500,000.) 
Existing project. For description of completed improvement 
and authorizing legislation see page 590 of 
Annual Report for FY 1969. Federal cost is $10,912,323, of 
which $533,682 are Code 710 funds. Construction began 
in December 1940 and project placed in useful operation 
in April 1948. 
19-6

TULSA, OKLAHOMA DISTRICT 
Local cooperation. Completed as required. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. 'vo noteworthy 
rises occurred above the lake. Estimated monetary benefits 
attributed to Canton Lake operations for prevention 
of flood damages total $6,475,000 to September 30, 
1983. Hydraulic studies were completed under the Dam 
Modernization Program to determine feasibility of 
modification of the project as a result of the Dam Safety 
Inspection Program. Final recommendations are being 
held in abeyance until other projects in the District and 
nationwide are analyzed for priorities. No water was 
released for water supply. 
14. COPAN LAKE, VERDIGRIS RIVER 
BASIN, OK. 
Location. On Little Caney River, river mile 7.4, a 
tributary of the Caney River in the Verdigris River Basin, 
about 2 miles west of Copan, Washington County, OK. 
(See Geological Survey maps of Nowata, OK, and Sedan 
and Independence, Kansas, quadrangles, scale 1:125,000; 
and Defense Mapping Agency maps, 'Thllsa, OK, Wichita, 
KS, and Joplin, MO, scale 1:125,000.) 
Existing project. The earthfill dam is 7,730 feet long, 
including a gated spillway section; a levee 17,000 feet 
long, for protection of Caney, KS. Maximum height of the 
dam above streambed is 73 feet. A concrete spillway, 
controlled by four 50- by 35.5-foot tainter gates, provides 
for operation of the lake for flood control. Outlet works 
include a 36-inch low-flow pipe and a 12-inch future water 
supply pipe. The lake has a total capacity of 227,700 
acre-feet (43,400 for conservation and sediment reserve, 
and 184,300 for flood control). The drainage area above 
the damsite is 505 square miles. Copan Lake is operated 
as a unit of a seven-lake system for flood control in the 
Verdigris River Basin in Oklahoma. Relocated Oklahoma 
State Highway 10 crosses the top of the dam. The 
estimated cost is $86,800,000 (October 1983 price levels), 
including deferred recreational development estimated 
at $2,800,000. (See table 19-B for authorizing legislation.) 
Construction began in November 1972. The project 
was placed in useful operation on April 1,1983. 
Local cooperation. Section 2, Flood Control Act of 
1933, Water Supply Act of 1953, and Section 221, Flood 
Control Act of 1970 apply. 
Operations and results during fiscal year. Major 
accomplishments with regular funds: railroad relocations 
$1,360,000; north end of railroad and Caney Levee 
$500,000; recreational development $1,000,000. Three 
noteworthy rises occurred above the lake. Estimated 
monetary benefits attributed to Copan Lake operations 
for the prevention of flood damages total $4,962,000 to 
September 30,1983. 
15. COUNCIL GROVE LAKE GRAND 
(NEOSHO) RIVER BASIN, KS. 
Location. On the Grand (Neosho) River about 450 
miles above the mouth and about 1.5 miles northwest of 
Council Grove, Morris County, KS. (See Geological Survey 
maps for Parkerville and Eskridge, Kansas, quadrangles, 
scale 1:125,000.) 
Existing project. For description of completed improvement 
and authorizing legislation see page 519 of 
Annual Report for FY 1969. Federal cost is $11,604,732, of 
which $163,829 is Code 710 funds. Construction began in 
July 1960 and project placed in useful operation in October 
1964. 
Local cooperation. Completed as required. 
Operations and results during fiscal year. Routine 
operations and maintenance continued. 'Iw\vo noteworthy 
rises occurred on Grand (Neosho) River above the lake. 
Estimated monetary benefits attributed to Council Grove 
Lake operations for prevention of flood damages total 
$10,968,000 to September 30, 1983. 
16. EL DORADO LAKE, WALNUT 
RIVER BASIN, KS. 
Location. On the Walnut River, river mile 100.2, a 
tributary of the Arkansas River, about 2 miles northeast 
of El Dorado, Butler County, KS. (See Geological Survey 
maps for El Dorado and DeGraff, KS, quadrangles, scale 
1:24,000.) 
Existing project. The earthfill dam is 21,000 feet long, 
including a 350-foot uncontrolled spillway. The 
maximum height of the dam is 99 feet above streambed. 
The lake will control 234 square miles of drainage area 
and provide a total storage of 236,200 acre-feet of water 
(79,200 for flood control storage, 154,100 for conservation, 
and 2,900 for sedimentation reserve). Outlet works consist 
of an 11.5- by 15.75-foot oblong conduit, a 24- by 
36-inch low-flow sluice and a 36-inch water supply pipe. 
El Dorado Lake will be operated as a unit of a three-lake 
system for flood control in the Walnut River Basin. Estimated 
Federal cost of project is $90,300,000 (October 
1983 price levels). Estimated non-Federal cost is 
$11,600,000. (See table 19-B for authorizing legislation.) 
Construction began in October 1973. The project is 99 
percent complete. Remaining work consists of completing 
public-use facilities and boundary fencing. Impoundment 
began in June 1981. 
Local cooperation. Section 2, Flood Control Act of 
1938, Water Supply Act of 1958, Federal Water Recreation 
Act of 1965, and Section 221 of the Flood Control Act 
of 1970 apply. 
Operations and results during fiscal year. Major 
accomplishments with regular funds: recreation 
facilities $5,462,000. One noteworthy rise occurred above 
the dam. Estimated monetary benefits attributed to El 
Dorado Lake operations for prevention of flood damages 
total $48,000 to September 30,1983. 
17. ELK CITY LAKE, VERDIGRIS 
RIVER BASIN, KS. 
Location. On Elk River, river mile 8.7, about 7 miles 
northwest of Independent, Montgomery County, KS. (See 
Geological Survey maps for Caney-NE, NW, and SW, and 
Benton, KS, quadrangles, scale of 1:24,000.) 
Existing project. For description of completed improvement 
and authorizing legislation see page 593 of 
Annual Report for FY 1969. Federal cost is $19,042,990. 
Construction began in February 1962 and project placed 
in useful operation in March 1966. Studies to evaluate the 
19-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
feasibility of adding hydropower at the existing facility 
are in progress. 
Local cooperation. Completed as required. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. Three noteworthy 
rises occurred above the lake. Estimated monetary benefits 
attributed to Elk City Lake operations for prevention 
of flood damages total $36,529,000 to September 30, 
1983. 
18. FALL RIVER LAKE, VERDIGRIS 
RIVER BASIN, KS. 
Location. On Fall River about 54 miles above its confluence 
with the Verdigris River and about 4 miles 
northwest of Fall River, Greenwood County, KS. (See 
Geological Survey map for Eureka, KS, quadrangle, scale 
1:125,000; and Severy, KS, quadrangle, scale 1:62,500.) 
Existing project. For description of completed improvement 
and authorizing legislation see page 953 of 
Annual Report for FY 1969. Federal cost is $10,512,382, of 
which $13,000 are Code 710 funds. Construction of the 
dam began in May 1946 and the project placed in full 
operation in April 1949. Studies to evaluate the feasibility 
of adding hydropower to the existing facility are in 
progress. 
Local cooperation. Completed as required. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. 'Ivo noteworthy 
rises occurred above the lake. Estimated monetary benefits 
attributed to Fall River Lake operations for prevention 
of flood damages total $28,386,000 to September 
30, 1983. Hydraulic studies were completed under the 
Dam Modernization Program to determine feasibility of 
modification of the project as a result of the Dam Safety 
Inspection Program. Final recommendations are being 
held in abeyance until other projects in the District and 
nationwide are analyzed for priorities. 
19. FORT SUPPLY LAKE, NORTH 
CANADIAN RIVER BASIN, OK. 
Location. On Wolf Creek, river mile 5.5, a tributary of 
the North Canadian River, about 12 miles northwest of 
Woodward, Woodward County, OK. (See sectional 
aeronautical chart, Wichita sheet, scale 1:500,000.) 
Existing project. For description of completed improvement 
and authorizing legislation see page 594 of 
Annual Report for FY 1969. Federal cost is $7,723,127, of 
which $132,941 are Code 710 funds. Construction began 
in October 1938 and the project was placed in full flood 
control operation in May 1942. 
Local cooperation. Completed as required. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. A total of 254 
acre-feet of water was wittdrawn for water supply. No 
noteworthy rises occurred above the lake. Estimated 
monetary benefits attributed to Fort Supply Lake operations 
for prevention of flood damages total $3,060,000 to 
September 30, 1983. Hydraulic studies were completed 
under the Dam Modernization Program to determine 
feasibility of modification of the project as a result of the 
Dam Safety Inspection Program. Final recommendations 
are being held in abeyance until other projects in the 
District and nationwide are analyzed for priorities. 
20. GREAT SALT PLAINS LAKE 
ARKANSAS RIVER BASIN, 6K. 
Location. On Salt Fork of the Arkansas River, river 
mile 103.3, about 12 miles east of Cherokee, Alfalfa 
County, OK. (See sectional aeronautical chart, Wichita 
sheet, scale 1:500,000.) 
Existing project. For description of completed improvements 
and authorizing legislation see page 594 of 
Annual Report for FY 1969. Federal cost was $4,626,270. 
Construction of the dam was initiated September 1938 
and completed July 1941. Project placed in full flood control 
operation in May 1941. 
Local cooperation. Completed as required. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. No noteworthy 
rises occurred above the lake. Estimated monetary benefits 
attributed to Great Salt Plains Lake operations for 
prevention of flood damages total $13,240,000 to September 
30,1983. 
21. HEYBURN LAKE ARKANSAS 
RIVER BASIN, OK. 
Location. On Polecat Creek, a minor tributary to the 
Arkansas River at river mile 48.6, about 11 miles west of 
Sapulpa, Creek County, OK. (See Geological Survey 
maps for Nuyake, Hominy, and Claremore, OK, quadrangles, 
scale 1:250,000; and Bristow and Kiefer, OK, 
quadrangles, scale 1:62,500.) 
Existing project. For description of completed improvement 
and authorizing legislation see page 599 of 
Annual Report for FY 1969. Federal cost is $2,518,673 
(including $135,300 for construction of channel improvement 
on Polecate and Rock Creeks and $151,500 
Code 710 funfls). Construction was started in March 1948 
and the project was placed in useful operation in September 
1950. Channel improvements below the lake were 
completed in September 1952. 
Local cooperation. Completed as required. 
Operations and results during fiscal year. Routine 
operation, maintenance, and repaired embankment slope 
protection continued. Rural Water District No. 1, Creek 
County, OK, used 1,634 acre-feet of water from the lake. 
Three noteworthy rises occurred above the lake. Estimated 
monetary benefits attributed to Heyburn Lake 
operations for prevention of flood damages total 
$4,237,000 to September 30,1983. 
22. HUGO LAKE, KIAMICHI RIVER 
BASIN, OK. 
Location. On the Kiamichi River, river mile 17.6, 
about 7 miles east of Hugo, Choctaw County, OK. (See 
Geological Survey map for Alikchi, OK, quadrangle, 
scale 1:125,000.) 
Existing project. For description of completed improvement 
see page 19-12 of the Annual Report for FY 
1977. Federal cost is $37,659,102, of which $22,171 are 
Code 710 funds. (See table 19-B - Red River below Denison 
Dam ('Tlsa District) - for authorizing legislation.) 
Construction began in October 1967 and the project was 
19-8

TULSA, OKLAHOMA DISTRICT 
placed in useful operation in January 1974. 
Local cooperation. Section 2, Flood Control Act of 
1938, and Water Supply Act of 1958, as amended, apply. 
The State of Oklahoma, through its Water Resources 
Board, and local interests furnished resolutions of intent 
to repay costs allocated to water supply storage. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. A total of 6,002 
acre-feet of water was used from the lake for water supply. 
The highest lake level of record (elevation 425.09) occurred 
in May 1982. Four noteworthy rises occurred on 
the Kiamichi River above the lake. The project reduced 
the damaging effects of floods on 4,300 acres of land below 
the damsite. Estimated monetary benefits attributed to 
Hugo Lake operations for prevention of flood damages 
total $5,678,000 to September 30,1983. 
23. HULAH LAKE, VERDIGRIS RIVER 
BASIN, OK. 
Location. On the Caney River, river mile 96.2, about 
15 miles northwest of Bartlesville, near Hulah, Osage 
County, OK. (See Geological Survey maps for Pawhuska, 
OK, and Sedan, KS, quadrangles, scale 1:125,000.) 
Existing project. For description of completed improvement 
and authorizing legislation see page 595 of 
the Annual Report for FY 1969. Federal cost is 
$11,133,333, of which $264,727 are Code 710 funds. Construction 
began in May 1946 and completed in June 1950. 
Project placed in full flood control operation in September 
1951. 
Local cooperation. Completed as required. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. An elevation of 
755.9 was reached on June 6, 1982, the fifth highest of 
record. Estimated monetary benefits attributed to Hulah 
Lake operations for prevention of flood damages total 
$67,872,000 to September 30, 1983. A total of 8,076 acrefeet 
of water was withdrawn from the lake for water 
supply. 
24. JOHN REDMOND DAM AND 
RESERVOIR GRAND (NEOSHO) 
RIVER BASIN, KS. 
Location. The dam is located on the Grand (Neosho) 
River, river mile 343.7, about 2 miles northwest of Burlington, 
Coffey County, KS. (See Geological Survey maps 
for Burlington and Emporia, KS, quadrangles, scale 
1:125,000.) 
Existing project. For description of completed improvement 
and authorizing legislation see page 581 of the 
Annual Report for FY 1970. Federal cost is $28,151,515, of 
which $170,651 are Code 710 funds. Construction was 
initiated in July 1959 and completed in December 1965. 
Project placed in flood control operation in July 1964. 
Local cooperation. Completed as required. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. No water supply 
releases were made during the fiscal year. Two noteworthy 
rises occurred above the reservoir. Estimated 
monetary benefits attributed to John Redmond Reservoir 
operations for prevention of flood damages total 
$55,200,000 to September 30, 1983. 
25. KAW LAKE, ARKANSAS RIVER 
BASIN, OK. 
Location. On the Arkansas River, river mile 653.7, 
about 8 miles east of Ponca City, Kay County, OK. (See 
Geological Survey map for Charley Creek, OK, quadrangle, 
scale 1:24,000.) 
Existing project. For description of completed improvement 
and authorizing legislation see page 19-13 of 
the Annual Report for FY 1977. Federal cost is 
$108,672,964. Construction began in June 1966 and project 
placed in operation in May 1976. Studies to evaluate 
the feasibility of adding hydropower at the existing 
facilities are in progress. The proposed plan considers 
adding 95 megawatts of power and has a benefit-to-cost 
ratio of 2.8 to 1. 
Local cooperation. Section 2, Flood Control Act of 
1938, and Water Supply Act of 1958 apply. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. '1vo noteworthy 
rises occurred above the lake. Estimated monetary benefits 
attributed to Kaw Lake operations for prevention of 
flood damages total $12,121,000 to September 30,1983. 
26. LAKE KEMP, WICHITA RIVER 
BASIN, TX. 
Location. On the Wichita River, river mile 126.7, about 
40 miles southwest of Wichita Falls, TX. (See aeronautical 
chart, Dallas, TX, scale 1:500,000; and Defense Mapping 
Agency map, Wichita Falls, TX, scale 1:250,000.) 
Existing project. For description of completed improvement 
and authorizing legislation see page 19-14 of 
the Annual Report for FY 1977. Cost of completed project 
was $7,637,702 Federal and $3,130,000 non-Federal. 
Construction began in April 1970 and the project placed 
in useful operation in October 1972. 
Local cooperation. Completed as required. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. A total of 60,937 
acre-feet of water was released for irrigation and water 
supply. No noteworthy rises occurred above the lake. The 
first flood control releases from the lake were made in 
June 1982. Estimated monetary benefits attributed to 
Lake Kemp operations for prevention of flood damages 
total $2,930,000 to September 30, 1983. 
27. LUKFATA LAKE, LITTLE RIVER 
BASIN, OK AND AR. 
Location. On Glover Creek, river mile 17.3, about 6 
miles north of Glover, McCurtain County, OK. (See 
Geological Survey map for Lukfata, OK, quadrangle, 
scale 1:250,000; and Bethel, Smithville, Golden, and 
Broken Bow, OK, quadrangles, scale 1:62,500.) 
Existing project. The plan provides for construction of 
a rockfill dam about 2,600 feet long, rising 176 feet above 
the original streambed. An uncontrolled, 600-foot saddle 
spillway will be near the left end of the embankment. 
Outlet works will provide for a 12-foot conduit and a 
19-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
stilling basin. The lake will provide a total storage of 
252,100 acre-feet (208,630 for flood control, 43,470 for 
conservation and sedimentation reserve), and will control 
a drainage area of 252 square miles. Lukfata Lake 
will be operated as a unit of a seven-lake system for flood 
control in the Little River Watershed, thereby reducing 
Red River floodflows. Estimated cost of project is 
$39,900,000 (1979 price levels). (See table 19-B - Red 
River below Denison Dam (Thlsa District) - for authorizing 
legislation.) Construction has not started. 
Local cooperation. Section 2, Flood Control Act of 
1938, Water Supply Act of 1958, as amended, and Section 
221, Flood Control Act of 1970 apply. 
Operations and results during fiscal year. None. 
28. MARION, KS. 
Location. On Mud Creek at Marion, the county seat of 
Marion County, KS. 
Existing project. Construction of a diversion channel 
9,026 feet in length, an overflow protection levee 17,875 
feet in length, and structures to control interior drainage 
and low streamflow. Railroad and highway bridges were 
altered or relocated as required. Federal cost is 
$5,519,200 and $900,000 non-Federal cost. (See table 
19-B for authorizing legislation.) Construction started in 
June 1975 and was completed in April 1980. 
Local cooperation. Local interests must provide 
lands, easements, and rights-of-way; hold the United 
States free from damages; maintain and operate all 
works after completion; perform all relocations except 
railroads; acquire fee title to lands for borrow and ponding 
purposes and flowage easements over lands for ponding 
only; and prevent encroachment on existing and improved 
channel. 
Operations and results during fiscal year. The City 
of Marion, KS assumed project operation and maintenance 
responsibility. 
29. MARION LAKE, GRAND (NEOSHO) 
RIVER BASIN, KS. 
Location. On the Cottonwood River, river mile 126.7, 
about 3 miles northwest of Marion, Marion County, KS. 
(See Geological Survey map for Newton, KS, quadrangle, 
scale 1:125,000.) 
Existing project. For description of completed improvement 
and authorizing legislation see page 597 of 
the Annual Report for FY 1969. Federal cost of project is 
$13,335,317 of which $17,779 are Code 710 funds. Construction 
began in June 1964 and the project placed in 
flood control operation in February 1968. 
Local cooperation. Completed as required. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. A total of 400 
acre-feet of water was withdrawn from the lake for water 
supply. 'wo noteworthy rises occurred above the lake. 
Estimated monetary benefits attributed to Marion Lake 
operations for prevention of flood damages total 
$26,571,000 to September 30, 1983. 
30. OOLOGAH LAKE, VERDIGRIS 
RIVER BASIN, OK. 
Location. On the Verdigris River about 10 miles 
northwest of Claremore, Rogers County, OK, and about 2 
miles southeast of Oologah, Rogers County, OK. (See 
Geological Survey maps for Claremore and Nowata, OK, 
quadrangles, scale 1:125,000.) 
Existing project. For description of completed improvement 
and authorizing legislation, see page 19-15 of 
the Annual Report for FY 1972. Federal cost of project is 
$46,688,556 of which $13,994 are Code 710 funds. After 
construction of the right abutment access road, the project 
was placed in standby status in October 1951. Construction 
was resumed in December 1955 and completed 
in May 1963 for initial development. Construction for 
ultimate (second stage) development was initiated July 
1967, and was completed in 1974. Studies to evaluate the 
feasibility of adding hydropower at the existing facility 
are in progress. 
Local cooperation. Completed as required. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. A total of 43,361 
acre-feet of water was withdrawn from the lake for water 
supply. Three noteworthy rises occurred above the lake. 
Estimated monetary benefits attributed to Oologah Lake 
operations for prevention of flood damages total 
$44,314,000 to September 30, 1983. 
31. OPTIMA LAKE NORTH 
CANADIAN RIVER BASIN, OK. 
Location. On the North Canadian River, river mile 
623.2, about 4.5 miles northeast of Hardesty, Texas 
County, OK. (See Geological Survey map for Optima 
Dam, Oklahoma, quadrangle, scale 1:24,000.) 
Existing project. For description of existing improvement 
and authorizing legislation see page 19-16 of 
the Annual Report for FY 1979. Federal cost is 
$47,224,665. Construction began in March 1966. Impoundment 
began in October 1978. Project is complete. 
Local cooperation. Section 2, Flood Control Act of 
1938, applies. 
Operations and results during fiscal year. Routine 
operation and maintenance began. No noteworthy rises 
occurred above the lake. Estimated monetary benefits 
attributed to Optima Lake operations for prevention of 
flood damages total $7,000 to September 30,1983. 
32. PAT MAYSE LAKE, RED RIVER 
BASIN, TX. 
Location. On Sanders Creek, river mile 4.6, a tributary 
of the Red River, about 12 miles north of Paris, 
Lamar County, TX. (See Geological Survey map for 
Grant, TX, quadrangle, scale 1:62,500 and Defense Mapping 
Agency map, Texarkana, TX, scale 1:250,000.) 
Existing project. For description of completed improvement 
and authorizing legislation see page 584 of 
the Annual Report for FY 1970. Federal cost of the project 
is $9,310,661, of which $819,404 are Code 710 funds. Con- 
19-10

TULSA, OKLAHOMA DISTRICT 
struction began in March 1965 and was placed in full flood 
control operation in September 1967. 
Local cooperation. Completed as required. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. Five noteworthy 
rises occurred above the lake. Flooding was prevented on 
an average of 1,100 acres of land. Estimated monetary 
benefits attributed to Pat Mayse Lake operations for prevention 
of flood damages total $3,513,000 to September 
30, 1983. A total of 9,900 acre-feet of water was released 
for water supply to the city of Paris, Txas. 
33. PEARSON-SKUBITZ BIG HILL 
LAKE, VERDIGRIS RIVER BASIN, 
KS. 
Location. On Big Hill Creek, river mile 33.3, about 5 
miles east of Cherryvale, KS. (See Geological Survey 
maps for Mound Valley and Parsons, KS, quadrangles, 
scale 1:62,500.) 
Existing project. Consists of an earthfilled dam about 
3,900 feet long, 83 feet above streambed. The 400-foot 
uncontrolled spillway is located in the right abutment. 
Outlet works include a drop inlet intake structure, a 
5-foot 8-inch-diameter conduit, and a stilling basin. A 
30-inch-diameter pipe is provided for water supply releases 
along with two 2-foot by 5-foot low flow openings. 
The lake has a total capacity of 40,600 acre-feet (13,100 
for flood control and 27,500 for conservation and 
sedimentation reserve), and controls runoff from a drainage 
area of 37 square miles. Federal cost is $17,120,000. 
(See table 19-B for authorizing legislation.) Construction 
began in April 1974. Impoundment began in March 1981. 
Local cooperation. Section 2, Flood Control Act of 
1938, Water Supply Act of 1958, as amended, and Section 
221, Flood Control Act of 1970 apply. 
Operations and results during fiscal year. All major 
items of construction are complete. The project was officially 
dedicated on July 24, 1982. 'wo noteworthy rises 
occurred above the dam. Major accomplishments with 
regular funds: Recreational facilities improvements 
$161,000; routine operation and maintenance. Estimated 
monetary benefits attributed to Pearson-Skubitz Big Hill 
Lake operations for prevention of flood damages total 
$24,000 to September 30,1983. 
34. PINE CREEK LAKE, LITTLE 
RIVER BASIN, OK. 
Location. On Little River, river mile 145.3, about 5 
miles northwest of Wright City, McCurtain County, OK. 
(See Geological Survey maps for Alikchi, OK, quadrangle, 
scale 1:125,000; and Wright City and Pickens, 
OK, quadrangles NE, NW, SE, and SW, scale 1:24,000.) 
Existing project. For description of completed improvement 
and authorizing legislation see page 584 of 
the Annual Report for FY 1970. Federal cost of the project 
is $20,304,909 of which $3,500 are Code 710 funds. Construction 
began in February 1963 and the project was 
placed in useful operation in June 1969. 
Local cooperation. Completed as required. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. A total of 33,648 
acre-feet of water was released for water supply. Five 
noteworthy rises occurred above the lake. Flooding was 
prevented on an average of 11,000 acres of land. The lake 
reached its second highest pool level of record (elevation 
462.29). Estimated monetary benefits attributed to Pine 
Creek Lake operation for prevention of flood damages 
total $8,852,000 to September 30,1983. 
35. RED RIVER BELOW DENISON 
DAM (TULSA DISTRICT). 
Location. On the Red River and its tributaries below 
Lake Txoma-Denison Dam, in Oklahoma, Arkansas, 
Txas, and Louisiana. (See Geological Survey State maps 
and folio maps of Red River -1958 edition.) 
Existing project. Provides for construction of eleven 
flood control lakes in combination with existing or authorized 
Federal and non-Federal levee improvements, 
modified as required, and channel stabilization at locations 
where levee setbacks are impossible or uneconomical. 
(See table 19-K for water control projects included 
in general flood control plan for Red River below 
Denison Dam within Tlsa District.) (See table 19-B for 
authorizing legislation.) Preconstruction planning 
completed. 
Local cooperation. See individual reports. 
36. SARDIS LAKE, LITTLE RIVER 
BASIN, OK. 
Location. On Jackfork Creek, river mile 2.8, a tributary 
of the Kiamichi River, about 2.5 miles north of 
Clayton, Pushmataha County, OK. (See Geological Survey 
map for Thskahoma, OK, quadrangle, scale 1:125,000 
and Defense Mapping Agency map, McAlester, OK, scale 
1:125,000.) 
Existing project. Consists of a rolled earthfill dam 
about 14,138 feet long, with a maximum height of 101 feet 
above the streambed. An uncontrolled spillway 215 feet 
wide is constructed near the right abutment. Outlet 
works consist of an oblong conduit, 9-foot by 12.25-foot, 
and a 2.5-foot by 5.25-foot sluice was installed for lowflow 
regulation. The lake will provide 128,200 acre-feet of 
storage for flood control and 302,400 acre-feet for conservation 
and sediment reserve, a total of 430,600 acre-feet, 
and controls a drainage area of 275 square miles. Sardis 
Lake will be operated as a unit of a three-lake system for 
flood control in the Kiamichi River Basin, including 
Hugo and T'uskahoma Lakes thereby reducing Red River 
floodflows. Estimated cost of the project is $55,459,000 
(October 1983 price levels). (See table 19-B - Red River 
below Denison Dam (tilsa District) for authorizing legislation.) 
Construction began in August 1975 and the project 
is 98 percent complete. Impoundment began in 
January 1983. A total of 1,290 acre-feet of water was 
released from the lake for water supply. 
Local cooperation. Section 2, Flood Control Act of 
1938, Water Supply Act of 1958, as amended, and Section 
221, Flood Control Act of 1970 apply. 
Operations and results during fiscal year. Major 
accomplishments with regular funds: land acquisition 
and damages $215,000; embankment and outlet works 
$420,000; relocations $260,000; recreation $475,000. Es- 
19-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
timated monetary benefits attributed to Sardis Lake operations 
for the prevention of flood damages total 
$1,257,000 to September 30, 1983. Sardis Lake operated 
as a detention lake and reduced peak flood flows 
downstream of the dam on several occasions. 
37. SHIDLER LAKE, ARKANSAS 
RIVER BASIN, OK. 
Location. On Salt Creek, river mile 39.2, a tributary of 
the Arkansas River, about 1 mile east of Shidler, Osage 
County, OK. (See Geological Survey map for Fairfax, OK, 
quadrangle, scale 1:24,000.) 
Existing project. Provides for an earthfilled dam 
6,050 feet long, with a maximum height of 117 feet above 
streambed. An uncontrolled spillway 200 feet wide will 
be east of the dam. Outlet works will include a gate tower 
with gated wet well inlet with a 10.5-foot by 115-foot 
controlled conduit. A 30-inch low-flow bypass and a 24- 
inch water supply line will be provided. A roadway will be 
located along the crest of the dam. The total lake capacity 
of 108,100 acre-feet will be allocated, 49,900 acre-feet for 
flood control and 58,200 acre-feet for conservation, and 
will control runoff from 99 square miles. Shidler Lake 
will be operated as a unit of the coordinated lake system 
for flood controlin the Arkansas River Basin. Estimated 
cost of the project is $34,600,000 (October 1983 price 
levels). (See table 19-B for authorizing legislation.) Preconstruction 
planning has been completed. 
Local cooperation. Section 2, Flood Control Act of 
1938, Water Supply Act of 1958, as amended, and Section 
221, Flood Control Act of 1970 apply. 
Operations and results during fiscal year. None. 
38. SKIATOOK LAKE, VERDIGRIS 
RIVER BASIN, OK. 
Location. On Hominy Creek, mile 14.3, a tributary of 
Bird Creek, in the Verdigris River Basin about 5 miles 
west of Skiatook, Osage County, OK. (See Geological 
Survey Map for Avant, OK, quadrangle, SE, scale 
1:24,000 and Defense Mapping Agency map, Enid, OK, 
scale 1:250,000.) 
Existing project. Provides for an earthfilled dam 
3,590 feet long, 136 feet high with a crown width of 32 
feet. The uncontrolled 100-foot spillway will be located in 
the right abutment. Outlet works will consist of a controlled 
intake structure, 10.5-foot diameter tunnel, stilling 
basin, 2.5-foot by 5-foot low-flow sluice, and a 36-inch 
water supply pipe. The lake will provide a total storage of 
500,700 acre-feet (302,600 for conservation storage, 
178,000 for flood control, and 22,000 for sedimentation 
reserve), and will control a drainage area of 354 square 
miles. Skiatook Lake will be operated as a unit of a 
seven-lake system for flood control in the Verdigris River 
Basin in Oklahoma. Estimated cost of the project is 
$110,000,000 (October 1983 price levels), including deferred 
recreational development at $6,705,000. (See table 
19-B for authorizing legislation.) Construction began in 
January 1974. The project is 90 percent complete. Studies 
to evaluate the feasibility of adding hydropower at the 
existing facility are in progress. 
Local cooperation. Section 2, Flood Control Act of 
1938, Water Supply Act of 1958, and Section 221, Flood 
Control Act of 1970 apply. 
Operations and results during fiscal year. Major 
accomplishments with regular funds: completed second 
stage embankment, spillway, and outlet works 
$2,932,000; mineral subordination $2,150,000; relocations 
$668,000; initiated clearing $536,000. Estimated 
monetary benefits attributed to Skiatook Lake operations 
for the prevention of flood damages total $3,499,000 
to September 30, 1983. 
39. TORONTO LAKE VERDIGRIS 
RIVER BASIN, KS. 
Location. On the Verdigris River about 271.5 miles 
above its mouth and 4 miles south and east of Tronto, 
Woodson County, KS. (See Geological Survey map for 
Fredonia, KS, quadrangle, scale 1:125,000.) 
Existing project. For description of completed improvement 
and authorizing legislation see page 600 of 
the Annual Report for FY 1969. Federal cost is 
$13,896,324 of which $922 are Code 710 funds. Construction 
began November 1954 and project placed in full operation 
March 1960. Studies to evaluate the feasibility of 
adding hydropower at the existing facility are in 
progress. 
Local cooperation. Completed as required. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. The city of 
Tronto, Kansas, used 73 acre-feet of water from the lak'e. 
One noteworthy rise occurred above the lake. Flooding 
was prevented on 16,200 acres of land. Estimated monetary 
benefits attributed to operation of Tronto Lake for 
prevention of flood damages total $24,408,000 to September 
30,1983. 
40. WAURIKA LAKE, RED RIVER 
BASIN, OK. 
Location. On Beaver Creek, river mile 27.0, a tributary 
of the Red River, about 6 miles northwest of Waurika, 
Jefferson County, OK. (See Geological Survey map for 
Hastings, OK-TX, quadrangle, scale 1:62,500.) 
Existing project. An earthfilled dam 16,600 feet long, 
including an uncontrolled spillway 300 feet wide, and 106 
feet above streambed. Outlet works include a gated conduit 
13.5 feet in diameter, a 14-inch water supply pipe, 
and a 12-inch low-flow pipe. The lake provides a total 
storage of 343,500 acre-feet (199,700 for conservation 
storage, 140,400 for flood control, and 3,400 for sedimentation 
reserve), and controls a drainage area of 562 
square miles. Waurika Lake is operated as a unit of a 
coordinated lake system for flood control in Red River 
Basin. Federal cost is $67,080,000. (See table 19-B for 
authorizing legislation.) Construction began in July 
1971. Impoundment began in August, 1977. All major 
items of construction are complete. 
Local cooperation. Section 2, Flood Control Act of 
1938, and Water Supply Act of 1958, as amended, apply. 
19-12

TULSA, OKLAHOMA DISTRICT 
Operations and results during fiscal year. Routine 
operation and maintenance continued. A total of 4,430 
acre-feet was withdrawn for water supply. The conservation 
pool filled and flood control releases were made for 
the first time. One noteworthy rise occurred above the 
lake. Estimated monetary benefits attributed to Waurika 
Lake operations for prevention of flood damages total 
$4,395,000 to September 30,1983. 
41. WISTER LAKE, POTEAU RIVER 
BASIN, OK. 
Location. On the Poteau River, river mile 60.9, about 2 
miles south of Wister, LeFlore County, OK. (See Geological 
Survey map for Winding Stair, OK, quadrangle, scale 
1:125,000.) 
Existing project. For description of completed improvement 
and authorizing legislation see page 601 of 
Annual Report for FY 1969. Federal cost was $10,501,226. 
Construction began April 1946 and was completed May 
1949. Project placed in full flood control operation in October 
1949. 
Local cooperation. Completed as required. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. Three noteworthy 
rises occurred above the lake. Flooding was prevented on 
an average of 11,000 acres of land. Estimated monetary 
benefits attributed to Wister Lake operations for prevention 
of flood damages total $59,763,000 to September 30, 
1983. A total of 2,812 acre-feet of water was withdrawn 
from the lake for water supply. 
42. INSPECTION OF COMPLETED 
FLOOD PROTECTION PROJECTS. 
Semiannual inspection of completed local flood protection 
projects operated and maintained by local interests 
are made to determine the extent of compliance with 
approved regulations for operations and maintenance. 
The inspections assist the Corps of Engineers to determine 
if the project provides the flood protection for which 
it was constructed. (See table 19-L for inspection of local 
flood protection projects.) Fiscal year cost was $184,187. 
lbtal cost to September 30,1983 was $1,092,930. 
43. SCHEDULING FLOOD CONTROL 
RESERVOIR OPERATIONS. 
The Flood Control Act of 1944 authorized the Secretary 
of War to prescribe regulations for use of storage allocated 
for flood control or navigation at all reservoirs constructed 
wholly or in part with Federal funds. Under the 
purview of this act, operation of the flood control storage 
included in reservoirs shown below in items 43A through 
43H is prescribed by the Corps. Work accomplished consists 
of operating activities necessary in basin-wide coordination 
of functional scheduling of releases from reservoirs 
operated by other agencies and preparations of flood 
control operation and maintenance manuals for projects 
underway. Fiscal year cost from regular funds for 
maintenance was $329,613. 
43A. ALTUS RESERVOIR, RED RIVER 
BASIN, OK. 
Located on the North Fork of the Red River, 16 miles 
north of Altus, OK, the project was completed in 1948 by 
the Bureau of Reclamation (now Water and Power Resource 
Service). Flood damages prevented total 
$3,260,000 through September 30, 1983. 
43B. ARBUCKLE RESERVOIR, RED 
RIVER BASIN, OK. 
Located on Rock Creek, a tributary of the Red River, 6 
miles southwest of Sulphur, OK, the project was completed 
in 1967 by the Bureau of Reclamation (now Water 
and Power Resource Service). Flood damages prevented 
total $374,000 through September 30,1983. 
43C. CHENEY RESERVOIR, 
NINNESCAH RIVER BASIN, KS. 
Located on the Ninnescah River, about 23 miles west of 
Wichita, KS, the project was completed in 1965 by the 
Bureau of Reclamation (now Water and Power Resource 
Service). Flood damages prevented total $7,014,000 
through September 30,1983. 
43D. FORT COBB RESERVOIR, 
WASHITA RIVER BASIN, OK. 
Located on Cobb (Pond) Creek, a tributary of the 
Washita River, in Caddo County, OK, the project was 
completed in 1959 by the Bureau of Reclamation (now 
Water and Power Resource Service). Flood damages prevented 
total $300,000 through September 30, 1983. 
43E. FOSS RESERVOIR, WASHITA 
RIVER BASIN, OK. 
Located on the Washita River, about 7 miles north of 
Foss, OK, the project was completed in 1961 by the 
Bureau of Reclamation (now Water and Power Resource 
Service). Flood damages prevented through September 
30,1983 total $830,000. 
43E MOUNTAIN PARK RESERVOIR 
(TOM STEED LAKE), RED 
RIVER BASIN, OK. 
Located on Otter Creek, a tributary of the North Fork 
of the Red River, about 6 miles north of Snyder, OK, the 
project was completed in 1977 by the Bureau of Reclamation 
(now Water and Power Resource Service). Flood 
damages prevented through September 30, 1983 total 
$390,000. 
43G. NORMAN RESERVOIR (LAKE 
THUNDERBIRD), RED RIVER 
BASIN, OK. 
Located on the Little River, about 12 miles east of 
Norman, OK, the project was completed in 1965 by the 
Bureau of Reclamation (now Water and Power Resource 
Service). Flood damages prevented through September 
30,1983 total $3,126,000. 
43H. SANFORD DAM (LAKE 
MEREDITH), CANADIAN RIVER 
BASIN, OK. 
Located on the Canadian River about 8 miles northwest 
of Borger, TX, the project was completed in 1965 by 
the Bureau of Reclamation (now Water and Power Resource 
Service). Flood damages prevented through September 
30, 1983 total $6,000. 
19-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
44. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS. 
See table 19-E. 
45. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION. 
Small flood control projects not specifically authorized 
by Congress (Section 205, 1948 Flood Control Act, as 
amended Public Law 858, 80th Congress), 
(preauthorization). 
See table 19-M. 
Emergency flood control activities-repair, flood fighting, 
and rescue work (Public Law 99, 84th Congress, and 
antecedent legislation). 
Federal cost for FY 83 was $138,801, of which $16,936 
was for advance preparation, $6,478 for advance flood 
control measures at Larned Private Levee, Pawnee 
County, KS, and $115,387 for rehabilitation of the following: 
McLeod Private Levee ($54,047); Nation Private 
Levee, Neosho County, KS ($17,882); Rising Brothers Inc, 
Levee, Choctaw, OK ($25,761); and 'bmmylu Coleman 
Plant, Lamar County, TX ($17,787). 
Emergency bank protection (Section 14, Flood Control 
Act of 1946, Public Law 526, 79th Congress). 
Federal cost for FY 83 was $128,527 as follows: Fourth 
Street Bridge, Florence, KS, $11,967; Fall River, 
Neodesha, KS, $59,488; Verdigris River, Coffeyville, KS, 
$51,679; Verdigris River, Montgomery County, KS, 
$4,572; and Walnut River, Cowley County, KS, $821. 
Flood insurance activities (Section 1301-1377, Housing 
and Urban Development Act of 1968, Public Law 90-448, 
as amended). 
In coordination with flood control activities, twelve 
flood insurance studies were in progress in accordance 
with various Interagency Agreements at a fiscal year cost 
of $477,200 under Housing and Urban Development 
reimbursable orders. 
Multiple-Purpose Projects Including 
Power 
46. BROKEN BOW LAKE, LITTLE 
RIVER BASIN, OK. 
Location. On the Mountain Fork River, river mile 
20.3, about 9 miles northeast of Broken Bow, McCurtain 
County, OK. (See Geological Survey maps for Broken 
Bow and Smithville, OK, quadrangles, scale 1:62,500.) 
Existing proj.ct. For description of completed improvements 
and authorizing legislation see page 19-17 of 
the Annual Report for FY 1971. Federal cost was 
$41,222,692. Construction began in November 1961 and 
the project placed in useful operation in October 1968. 
Power units 1 and 2 were placed in operation in January 
and June 1970, respectively. Generator 1 experienced a 
stator winding failure on June 15, 1982. 'Ibmporary repairs 
allowed the unit to be returned to service. 
Additional testing indicates both generators require replacement 
of the stator winding. Funding is being sought 
to accomplish this work. 
Local cooperation. Section 2, Flood Control Act of 
1938, and Water Supply Act of 1959, as amended, apply. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. Five noteworthy 
rises occurred above the lake. Operation of the lake prevented 
downstream flooding on an average of 11,000 acres 
of land. Estimated monetary benefits attributed to Broken 
Bow Lake operations for prevention of flood damages 
total $11,171,000 to September 30, 1983. During low-flow 
water periods, releases totaling 4,344 acre-feet were 
made to supplement water for a State park. Other low 
flow requirements were met by power releases. An 
additional 1,097,320 acre-feet of water was released 
through turbines, delivering 194,704,800 kilowatt-hours 
of electric energy to Southwestern Power Administration 
for distribution and sale. 
47. DENISON DAM -- LAKE 
TEXOMA, RED RIVER BASIN, TX 
AND OK. 
Location. On the Red River, river mile 725.0, about 5 
miles northwest of Denison, TX. (See Geological Survey 
maps for Denison, TX, and Tishomingo, OK, quadrangles, 
scale 1:125,000; and Denison Dam and Gordonville, 
TX, quadrangles, scale 1:62,500.) 
Existing project. For description of completed improvement 
and authorizing legislation see page 603 of 
the Annual Report for FY 1969. Hydroelectric development 
consists of two units having an installed capacity of 
70,000 kilowatts. Planned ultimate installation is for five 
units with a total of 175,000 kilowatts. Lake 'bxoma- 
Denison Dam is operated as a unit of a coordinated lake 
system for flood control in the Red River Basin. Federal 
cost is $67,864,473 of which $3,394,828 are Code 710 
funds. Non-Federal cost was $1,256,068. Construction 
was started in August 1939 and was completed for the 
dam, spillway, and outlet works in February 1944. Impoundment 
of the power pool began in January 1944 and 
commercial power generation was started in March 1945 
with the first unit operating. Authorized work is completed 
except for installation of the third and fourth 
power units, and additional perimeter access roads. 
(Work discontinued on access roads, has been recommended 
for deferral.) 
Local cooperation. Completed as required. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. No noteworthy 
rises occurred above the lake. Estimated monetary benefits 
attributed to Denison Dam-Lake 'bxoma operation 
for prevention of flood damages downstream to Fulton, 
AR, total $57,590,000 to September 30, 1983. A total of 
1,190 acre-feet was withdrawn for water supply. An 
additional 2,011,200 acre-feet of water was released 
through turbines, delivering 188,550,000 kilowatt-hours 
of electric energy to Southwestern Power Administration 
for distribution and sale. 
48. EUFAULA LAKE, CANADIAN 
RIVER BASIN, OK. 
Location. On the Canadian River, at river mile 27.0, 
about 12 miles east of Eufaula, McIntosh County, OK. 
(See Geological Survey maps for Okmulgee, Canadian, 
McAlester, and Sans Bois, OK, quadrangles, scale 
1:125,000.) 
19-14

TULSA, OKLAHOMA DISTRICT 
Existing project. For description of completed improvement 
and authorizing legislation see page 588 of 
the Annual Report for FY 1970. Federal cost is 
$121,801,719, of which $551,900 are Code 710 funds. Construction 
began in December 1956 and the project placed 
in full flood control operation in February 1964. Project is 
complete except for additional recreation facilities. 
Commercial power was generated on unit 1 July 1964, on 
unit 2 September 1964, and on unit 3 August 1964. 
Local cooperation. Completed as required. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. Three noteworthy 
rises occurred above the lake. Estimated monetary benefits 
attributed to Eufaula Lake operations for prevention 
of flood damages total $45,258,000 to September 30, 
1983. A total of 2,578 acre-feet of water was withdrawn 
for water supply. An additional 2,842,200 acre-feet of 
water was released through turbines, delivering 
239,458,000 kilowatt-hours of electric energy to Southwestern 
Power Administration for distribution and sale. 
49. FORT GIBSON LAKE, GRAND 
(NEOSHO) RIVER BASIN, OK. 
Location. On the Grand (Neosho) River, river mile 7.7, 
about 5 miles north and east of Fort Gibson, Muskogee 
County, OK. (See Geological Survey map for Muskogee 
and Pryor, OK, quadrangles, scale 1:125,000; and 
Wagoner, OK, quadrangle, scale 1:62,500.) 
Existing project. For description of completed improvement 
and authorizing legislation see page 604 of 
the Annual Report for FY 1969. Federal cost is 
$43,596,858, of which $1,140,596 are Code 710 funds. 
Construction began in March 1942 with construction of 
temporary field office buildings, but further construction 
at project was held in abeyance during World War II. 
Construction of concrete dam and spillway, the largest 
single feature of the project, started in May 1946 and was 
completed in June 1950. Fourth generator installed and 
the project placed in full operation in September 1953. 
Additional studies are being conducted to determine the 
feasibility of adding additional hydropower units. The 
estimated cost for the addition of power units 5 and 6 is 
$24,100,000 (October 1983 price levels). During FY 83, 
$5,881 was expended for advanced engineering and design 
of these power units. 
Local cooperation. Completed as required. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. Three noteworthy 
rises occurred above the lake. Estimated monetary benefits 
attributed to Fort Gibson Lake operations for prevention 
of flood damages total $33,617,000 to September 
30, 1983. A total of 14,025 acre-feet was released to the 
city of Muskogee, Oklahoma, for water supply. An 
additional 4,011,600 acre-feet of water was released 
through turbines, delivering 216,152,800 kilowatt-hours 
of electric energy to Southwestern Power Administration 
for distribution and sale. 
50. KEYSTONE LAKE ARKANSAS 
RIVER BASIN, OK4. 
Location. On the Arkansas River, river mile 538.8, 
near Sand Springs, OK, and about 15 miles west ofTl hlsa, 
OK. (See Geological Survey map for Hominy, OK, quadrangle, 
scale 1:125,000; Skedee and Yale, OK, quadrangles, 
scale 1:62,500; and Keystone Dam, quadrangle, scale 
1:24,000.) 
Existing project. For description of completed improvement 
and authorizing legislation see page 589 of 
the Annual Report for FY 1970. Federal cost is 
$123,126,175, of which $448,656 are Code 710 funds. Construction 
began in January 1957 and the project was 
placed in flood control operation in September 1964. No.1 
generating unit became operational on May 21,1968 and 
No. 2 on May 2, 1968. 
Local cooperation. Completed as required. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. Low flow release 
requirements were met by power releases. An additional 
819,475 acre-feet of water was released through turbines, 
delivering 231,165,200 kilowatt-hours of electric energy 
to Southwestern Power Administration for distribution 
and sale. Three noteworthy rises occurred above the lake. 
Water supply usage totaled 5,736 acre-feet. Estimated 
monetary benefits attributed to operation of Keystone 
Lake for prevention of flood damages total $89,716,000 to 
September 30,1983. 
51. MARKHAM FERRY RESERVOIR 
(LAKE HUDSON) GRAND 
(NEOSHO) RIVER BASIN, OK. 
Location. On the Grand (Neosho) River, river mile 
47.4, about 8 miles southeast of the city of Pryor, Mayes 
County, OK. (See Geological Survey map for Pryor and 
Vinita, OK., quadrangles, scale 1:125,000.) 
Existing project. For description of completed improvement 
and authorizing legislation see page 605 of 
Annual Report for FY 1969. Federal cost was $6,908,756. 
Federal participation in the project is completed. 
Local cooperation. None required. 
Operations and results during fiscal year. Flood 
control storage in the project was operated by the Grand 
River Dam Authority (an agency of the State of Oklahoma) 
under the direction of the Corps of Engineers. 
Three noteworthy rises occurred above the reservoir. Estimated 
monetary benefits attributed to the operation of 
Markham Ferry Reservoir for flood damage prevention 
total $5,564,000 to September 30,1983. 
52. PENSACOLA RESERVOIR 
(GRAND LAKE) GRAND 
(NEOSHO) RIVER BASIN, OK. 
Location. On the Grand (Neosho) River, river mile 
77.0, near the town of Disney, Mayes County, OK. (See 
Geological Survey maps for Pryor, Wyandotte, and 
Vinita, OK, and Siloam Springs, AR, quadrangles, scale 
1:125,000.) 
Existing project. For description of completed improvement 
and authorizing legislation see page 606 of 
the Annual Report for FY 1969. Federal cost was $52,126. 
Project is complete. 
Operations and results during fiscal year. Estimated 
benefits attributed to the operation of Pensacola 
Reservoir for flood damage prevention total $38,845,000 
to September 30,1983. 
19-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
53. ROBERT S. KERR LOCK AND 
DAM AND RESERVOIR 
ARKANSAS RIVER BASIN, OK. 
Location. On the Arkansas River at navigation mile 
336.2, about 8 miles south of Sallisaw, LeFlore County, 
OK. (See Geological Survey maps for Robert S. Kerr 
Dam, Keota, Vian, Sallisaw, Stigler NE, and Webbers 
Falls, OK, quadrangles, scale 1:24,000 and Defense Mapping 
Agency map, Fort Smith, AR, scale 1:125,000.) 
Existing project. For description of completed improvement 
and authorizing legislation see page 19-21 of 
the Annual Report for FY 1972. Robert S. Kerr Lock and 
Dam and Reservoir is a unit of the McClellan-Kerr Arkansas 
River Navigation System. Federal cost is 
$94,578,237 of which $24,004 is Code 710 funds. Construction 
began in April 1964 and closure was completed 
in October 1970. Lock and dam became operational for 
navigation in December 1970. Power units number 1, 
number 2, number 3, and number 4 were placed in operation 
in October, July, September, and November 1971, 
respectively. 
Local cooperation. See section 2 of this report. 
'Trminal facilities. Seven sites have been developed 
for handling coal, grain, construction aggregates, and 
miscellaneous cargo. The facilities are considered 
adequate for present traffic. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. An additional 
15,523,100 acre-feet of water was released through turbines, 
delivering 577,891,200 kilowatt-hours of electric 
energy to Southwestern Power Administration for distribution 
and sale. 
54. TENKILLER FERRY LAKE, 
ILLINOIS RIVER BASIN, OK. 
Location. On the Illinois River, river mile 12.8, about 7 
miles northwest of Vian and 7 miles northeast of Gore, 
Sequoyah County, OK. (See Geological Survey maps for 
Muskogee and Thhlequah, OK, and AR, quadrangles, 
scale 1:125,000; and Webbers Falls, OK, quadrangle, 
scale 1:62,500.) 
Existing project. For description of completed improvement 
and authorizing legislation see page 606 of 
the Annual Report for FY 1969. Federal cost is 
$23,954,780, of which $1,295,322 are Code 710 funds. 
Construction began in June 1947 and completed in July 
1953. Commercial sale of power started November 1953, 
with unit number 2. Unit number 1 was installed in 
December 1953. Repair and extension of the spillway 
apron began in July 1960 and was completed in August 
1961. 
Local cooperation. Completed as required. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. Additional recreation 
facilities were constructed. Four noteworthy rises 
occurred above the lake. Estimated monetary benefits 
attributed to 'bnkiller Ferry Lake operations for prevention 
of flood damages total $11,926,000 to September 30, 
1983. An additional 712,500 acre-feet of water was released 
through turbines, delivering 94,807,100 
kilowatt-hours of electric energy to Southwestern Power 
Administration for distribution and sale. A total of 6,969 
acre-feet of water was released for water supply 
55. WEBBERS FALLS LOCK AND 
DAM, ARKANSAS RIVER BASIN, 
OK. 
Location. On the Arkansas River at navigation mile 
366.6, about 5 miles northwest of Webbers Falls, Muskogee 
County, OK. (See Geological Survey maps for Webbers 
Falls, Keefeton, and Wagoner, OK, quadrangles, 
scale 1:62,500 and Defense Mapping Agency map, Fort 
Smith, AR, scale 1:250,000.) 
Existing project. For description of completed improvement 
and authorizing legislation see page 19-23 of 
the Annual Report for FY 1977. Project is a unit of the 
McClellan-Kerr Arkansas River Navigation System. 
Federal cost is $83,736,701. Construction began in 
January 1965, and the project was placed in useful operation 
in November 1970. The lock and dam became operational 
for navigation in December 1970. Power units 
number 1, number 2, and number 3 were placed in operation 
in August, September, and November 1973, respectively 
The project is complete. Studies to evaluate the 
feasibility of expanding hydropower at the facility are in 
progress. 
Local cooperation. See section 2 of this report. 
Thrminal facilities. Cargo pier, mooring dolphins, 
warehouse, terminal building, and fuel facility were built 
by the Muskogee City-County Port Authority; liquid 
cargo loading facility and steel unloading facility we'e 
built by Frontier Steel Company to serve existing traffic. 
Operations and results during fiscal year. Generating 
Unit No.1 was returned to full service on February 4, 
1983 after repairs to cracked turbine shaft welds were 
completed. Generating units No. 2 and No. 3 were not in 
service because of cracked turbine shaft welds. The repaired 
turbine shafts will be returned for installation 
during FY 1984. An additional 3,676,300 acre-feet of 
water was released through Unit No. 1 delivering 
91,272,700 kilowatt-hours of electric energy to Southwestern 
Power Administration. 
General Investigations 
56. SURVEYS 
Fiscal year cost was $2,299,551 of which $25,083 was 
for special navigation studies (Arkansas River and 
tributaries hydropower studies), $336,157 for coordination 
with other agencies (includes planning assistance to 
states), $1,484 for preauthorization studies (Prosperity 
Lake, MO), and $244,696 for the review of the completed 
Hugo and Pine Creek Lakes in Oklahoma, and $24,730 
for special investigations on inventory of dams. 
$1,620,054 was used for the following local protection 
flood control projects: Arkansas River at Great Bend, KS 
- John Martin Dam ($507); Arkansas River, Great Bend, 
KS to Thlsa, OK ($519,486); Canadian River, OK, TX, and 
NM ($146,966); Lake 'lxoma, OK and TX ($3,336); 
Poteau River, OK ($324,696); Red River above Denison, 
TX and OK ($113,430); 'Ibnkiller Ferry Dam and Reser- 
19-16

TULSA, OKLAHOMA DISTRICT 
voir ($15,834); Tlilsa Urban Study, OK ($12,288); and Verdigris 
River Basin ($483,511). 
In addition, $47,347 was used for the restudy of the 
deferred Lukfata Lake, OK project for hydropower 
studies. 
57. COLLECTION AND STUDY OF 
BASIC DATA. 
Fiscal year cost was $276,443 of which $258,359 was 
for flood plain management services, $5,751 for inspection 
of dams, and $12,333 for hydrological studies. 
58. CONTINUATION OF PLANNING 
AND ENGINEERING. 
Fiscal year cost was $700,466 for two local protection 
flood control projects: 
The Arkansas River Project from Great Bend, KS to 
Thlsa, OK at Halstead, KS ($361,457) and the Lake 
Wichita, Holliday Creek project at Wichita Falls, TX 
($339,009). 
59. ADVANCED ENGINEERING AND 
DESIGN. 
Fiscal year cost was $170,356 for the Arkansas-Red 
River Chloride Control local flood control project in 
lbxas, Oklahoma, and Kansas ($91,501) and Big and 
Little Sallisaw Creeks navigation project in Oklahoma 
($78,855). 
19-17

TABLE 19-A 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
COST AND FINANCIAL STATEMENT 
See 
Section 
in 
Ibtal to 
FY 80 FY 81 FY 82 FY 83 Sep 30,19831 
$ 75,000 
89,746 
bxt Project Funding 
1. Big and Little Sallisaw New Work 
Creeks Navigation, Approp. 
Arkansas River Basin, OK Cost 
3. Bank Stabilization & New Work 
Channel Rectification, Approp. 
Arkansas River, Cost 
AR & OK Maint. 
Approp. 
Cost 
4. Maintenance & Repair New Work 
Fleet & Marine Approp. 
Terminals, OK Cost 
Maint. 
Approp. 
Cost 
5. Red River Waterway New Work 
LA, AR, OK and TX, Approp. 
Index, AR to Denison Cost 
Dam, TX 
7. Poteau River Navigation New Work 
Arkansas River Basin, OK Approp. 
Cost 
8. Arcadia Lake, Deep Fork New Work 
River Basin, OK Approp. 
Cost 
9. Ark-Red River Basins New Work 
Chloride Control Approp. 
Cost 
Maint. 
Approp. 
Cost 
9A. (AREA VIII) New Work 
Approp. 
Cost 
10. Big Pine Lake, Red River New Work 
Basin, TX Approp. 
Cost 
11. Birch Lake, Verdigris New Work 
River Basin, OK Approp. 
Cost 
Maint. 
Approp. 
Cost 
12. Candy Lake, Verdigris New Work 
River Basin, OK Approp. 
Cost 
13. Canton Lake, Arkansas New Work 
River Basin, OK Approp. 
Cost 
Maint. 
Approp. 
Cost 
14. Copan Lake, Verdigris New Work 
River Basin, OK Approp. 
Cost 
15. Council Grove Lake, New Work 
Grand (Neosho) River Approp. 
Basin, KS Cost 
Maint. 
Approp. 
Cost 
16. El Dorado Lake, New Work 
Walnut River Approp. 
Basin, KS Cost 
Maint. 
Approp. 
Cost 
$ - $ -159 
5,360 570 
128,214 
132,218 
76,000 
50,451 
3,122,000 
2,317,627 
2,140,000 
1,826,999 
124,692 
123,494 
9,310,000 
9,425,096 
25,000 
101,778 
154,200 
467,396 
112,962 
-230,000 
112,962 
113,000 
126,861 
709,876 
744,757 
10,405,000 
11,308,037 
459,607 
381,161 
13,060,000 
1,682,428 
219,500 
213,377 
379 
12,820 
- $ 270,348 
78,855 349,202 
- 12,700,038 
12,700,038 
- 2,689,734 
- 2,689,734 
- 2,750,000 
- 2,750,000 
232,000 2,016,465 
190,348 2,200,861 
- 105,379 
7 105,378 
17,989,780 20,430,000 
15,600,626 12,765,430 
252,245 
61,000 
59,985 
10,840,000 
9,791,605 
49,104 
2,000 
2,703 
4,923,000 
5,317,748 
182,200 
180,479 
105,000 
92,551 
604 
9,799,000 
10,342,119 
1,900,000 
2,311,281 
189,500 
199,522 
8,660,000 
8,671,380 
506 
9,168 
558,800 
677,051 
186,000 
295,161 
4,000 
6,889 
853,400 
967,804 
8,050,000 
8,422,582 
12,221 
6,124 
474,500 
575,342 
5,612,000 
5,280,005 
-735 
591,900 
566,802 
6,905 
5,776 
830,600 
827,823 
11,900,000 
7,832,339 
202,500 
196,999 
541,200 
533,241 
2,550,000 
3,075,030 
74,100 247,500 
70,967 245,029 
1,006 
575,000 
555,974 
27,026 
-1,000 
508 
896,000 
844,568 
300,000 
3,801,718 
120 
11,652 
656,500 
634,417 
6,700,000 
6,806,749 
330,000 
302,618 
586,952 
586,952 
53,764,289 
43,354,132 
25,705,208 
25,698,858 
3,575,247 
3,574,667 
43,754,000 
42,939,451 
1,701,670 
1,700,617 
13,549,170 
13,549,119 
3,083,1019 
6,329,7309 
4,949,922 
4,858,996 
11,209,834 
10,918,607 
11,623,2729 
11,536,0379 
76,471,999 
79,303,286 
11,813,449 
11,813,383 
6,343,9769 
6,303,109� 
82,701,469 
82,428,536 
651,600 
618,614 
19-18 
744

TULSA, OKLAHOMA DISTRICT 
TABLE 19-A COST AND FINANCIAL STATEMENT 
(Continued) 
See 
Section 'Ibtal to 
in 'Ixt Project 
17. Elk City Lake, 
Verdigris River 
Basin, KS 
18. Fall River Lake, 
Verdigris River 
Basin, KS 
19. Fort Supply Lake, 
North Canadian 
River Basin, OK 
20. Great Salt Plains Lake, 
Arkansas River Basin, 
OK 
21. Heyburn Lake, Arkansas 
River Basin, OK 
22. Hugo Lake, Kiamichi 
River Basin, OK 
23. Hulah Lake, Verdigris 
River Basin, OK 
24. John Redmond Dam & 
Reservoir, Grand 
(Neosho) River, KS 
25. Kaw Lake, Arkansas 
River Basin, OK 
26. Lake Kemp, Wichita 
River Basin, TR 
27. Lukfata Lake, Little 
River Basin, OK 
Funding 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Minor Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
FY 80 FY 81 FY 82 FY 83 Sep 30,198 3 1 
538,000 5: 
633,308 5 
31 
321,158 
441,332 
43,000 
114,676 
371,984 
438,546 
215,828 
246,614 
12,369 
384,411 
673,450 
232,000 
296,684 
716,000 
681,381 
-16,300 
13,021 
460,799 
446,663 
- 
688 
980,475 
619,647 
780,000 
1,525,126 
1,703,498 
1,362,054 
- 
88,964 
90,348 
46 
- 15,000 -5,000 19,052,990 
- 8,033 1,226 19,052,249 
31,900 461,500 605,708 6,140,940 
43,923 499,174 560,188 6,080,258' 
11,000 34,000 -520 10,550,873 
5,989 38,491 - 10,550,873 
16,100 534,800 630,500 6,254,775 
68,571 526,590 591,195 6,378,476' 
-90 - - 7,724,134 
5,034 - - 7,723,127 
36,300 533,500 487,000 6,309,7739 
49,162 534,126 459,474 6,266,966 
- - - 4,626,270 
- -- -- 4,626,270 
59,000 333,000 331,000 3,955,207 
60,913 336,770 314,860 3,923,922 
-22 41,000 2,800 2,562,472 
2,268 37,710 219 2,556,602 
82,800 604,600 446,000 5,234,805 
94,637 606,469 418,474 5,189,885 
20,000 35,000 - 37,739,742 
15,930 40,642 1,848 37,701,592 
'53,300 886,200 1,347,912 6,815,637' 
15,829 849,445 898,884 6,307,594' 
581 31,500 20,000 11,390,550 
960 3,480 27,990 11,164,803 
95,300 504,400 617,000 7,331,893' 
72,020 501,655 574,892 7,264,815P 
- - - 135,718 
- - - 135,718 
- - - 28,151,515 
- - - 28,151,515 
12,700 637,700 807,000 8,612,453s 
126,866 640,266 736,018 8,520,561' 
00,000 200,000 490,000 109,502,650 
182,621 173,051 361,641 109,207,656 
)99,500 1,263,900 1,517,000 8,582,008' 
182,798 1,151,085 1,300,194 8,214,972� 
- -- -- 7,637,702 
- - - 7,637,702 
89,700 146,900 119,000 1,120,634 
97,267 134,656 116,978 1,104,884 
- - - 1,424,685 
162 - - 1,424,685 
44 
22 
33 7
8
56 
7 
1,I 
-2
2 
11,,04 
19-19

TABLE 19-A 
(Continued) 
See 
Section 
in Tbxt Project 
28. Marion, KS 
29. Marion Lake, Grand 
(Neosho) River 
Basin, KS 
30. Oologah Lake, Verdigris 
River Basin, OK 
31. Optima Lake, North 
Canadian River 
Basin, OK 
32. Pat Mayse Lake, 
Red River Basin, TX 
33. Pearson-Skubitz 
Big Hill Lake, 
Verdigris River 
Basin, KS 
34. Pine Creek Lake, 
Little River Basin, OK 
36. Sardis Lake, Little 
River Basin, OK 
37. Shidler Lake, Arkansas 
River Basin, OK 
38. Skiatook Lake, 
Verdigris River 
Basin, OK 
39. Toronto Lake, 
Verdigris River 
Basin, KS 
40. Waurika Lake, Red 
River Basin, OK 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
COST AND FINANCIAL STATEMENT 
Funding 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cos 
Maint. 
Approp. 
Cost 
ToIbtal to 
FY 80 FY 81 FY 82 FY 83 Sep 30,19831 
-- 450,000 
-370,778 
665 
440,064 
528,212 
6,000 
552 
961,983 
989,024 
210,000 
754,067 
243,054 
268,568 
618,000 
599,608 
3,900,000 
3,837,763 
393 
463,918 
455,755 
14,132,000 
13,900,317 
25,000 
20,526 
15,187,000 
14,715,818 
-5,078 
943 
178,627 
186,032 
1,611,000 
2,194,211 
691,514 
513,241 
75,000 
70,848 
12,779 
12,779 
488,800 
916,471 
-93 
5,222 
796,600 
875,917 
3,000 
259,501 
427,500 
438,420 
-29 
1,350 
425,300 
521,751 
3,220,000 
2,972,698 
98,000 
95,437 
510,100 
521,602 
7,785,000 
5,743,329 
-10,896 
17,873,000 
13,014,349 
104 
291,000 
308,472 
920,000 
945,501 
586,600 
776,517 
11,474 
20,000 
10,644 
636,000 
627,795 
928,600 
914,460 
20,000 
47,431 
453,200 
430,439 
583,400 
521,601 
2,113,000 
2,247,338 
355,400 
350,650 
614,100 
611,646 
3,565,000 
4,707,433 
234 
15,806,000 
19,991,981 
314,600 
306,165 
489,000 
734,340 
648,100 
644,391 
19-20 
-81,000 5,519,200 
- 5,447,868 
- 5,500 13,349,817 
3,781 13,349,742 
650,500 6,811,632� 
632,428 6,763,2739 
37,000 46,726,3292 
2,951 46,691,5072 
1,218,995 12,035,8069 
1,176,623 11,964,825 
- 47,183,438 
141 47,272,237 
512,000 1,854,754 
488,318 1,793,900 
- 9,310,661 
- 9,310,661 
756,000 5,723,5839 
704,206 5,590,0359 
- 17,120,116 
275,827 16,981,680 
498,000 951,400 
519,559 965,646 
- 20,304,909 
- 20,304,909 
623,000 5,664,2589 
599,668 5,613,1839 
1,050,000 52,137,479 
2,159,987 52,017,317 
305,000 305,000 
286,000 286,000 
- 568,190 
22,105 568,191 
9,355,000 91,143,282 
7,730,104 87,813,615 
- 13,896,324 
- 13,896,324 
256,500 3,607,503 
239,636 3,572,941 
- 67,080,050 
122,799 66,914,327 
759,630 3,154,944 
751,347 3,124,6789

TULSA, OKLAHOMA DISTRICT 
TABLE 19-A 
(Continued) 
COST AND FINANCIAL STATEMENT 
See 
Section Ibtal to 
in bxt Project Funding FY 80 FY 81 FY 82 FY 83 Sep 30,1983' 
41. Wister Lake, 
Poteau River 
Basin, OK 
46. Broken Bow Lake, 
Little River Basin, OK 
47. Denison Dam-Lake 
Texoma, Red River 
Basin, TX & OK 
48. Eufaula Lake, 
Canadian River 
Basin, OK 
49. Fort Gibson Lake, 
Grand (Neosho) 
River Basin, OK 
50. Keystone Lake, 
Arkansas River 
Basin, OK 
51. Pensacola Lake, 
Grand (Neosho) 
River Basin, OK 
52. Robert S. Kerr Lock 
& Dam & Reservoir, 
Arkansas River 
Basin, OK 
53. Tenkiller Ferry 
Lake, Illinois 
River Basin, OK 
54. Webbers Falls Lock 
& Dam, Arkansas 
River Basin, OK 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Minor Rehap. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
- - - - 10,501,226 
- - - - 10,501,226 
337,164 391,400 403,100 468,000 6,479,545 
334,963 432,384 405,482 445,128 6,439,465 
- - - - 41,222,692 
- - - - 41,222,692 
781,343 855,400 1,102,100 2,030,000 9,863,257 
806,147 872,268 1,073,248 1,229,088 9,016,346 
26,000 
59,867 
2,990,716 
3,396,576 
300 
142,574 
2,161,112 
2,308,543 
27,400 
17,110 
1,713,098 
1,697,614 
1,797,605 
2,027,357 
4,950 
5,593 
-35,800 
7,199 
1,669,802 
1,586,863 
207,000 
47,846 
1,374,064 
1,319,942 
49,000 
58,358 
3,245,200 
3,369,946 
-
-301 
1,325 
2,079,800 
2,477,739 
-14,224 
67,873 
1,871,500 
1,970,187 
- 32 
596 
1,864,200 
1,899,774 
- 
6,900 
6,952 
-13 
4,838 
1,671,600 
1,738,902 
-29,276 
174,926 
1,617,400 
1,678,213 
8,000 
17,726 
3,580,300 
3,494,114 
29,000 
17,625 
2,429,000 
2,365,469
5 
2,606,600 
2,549,760 
1,880,200 
1,910,704 
11,500 
8,892 
1,769,900 
1,728,877 
154,000 
27,114 
2,436,500 
2,017,534 
-.- - - 
- - 1,577 
1,615,260 4,515,700 2,592,300 
1,586,864 3,356,093 2,363,668 
92,319 68,114,5603 
10,591 67,875,1633 
4,884,242 49,302,5839 
3,873,331 48,200,473' 
- 46,237 
- 46,237 
- 121,830,7474 
11,203 121,830,574 
2,635,900 29,956,0739 
2,534,823 26,664,2919 
70,000 42,605,2985 
23,146 43,455,7565 
2,455,300 28,493,6859 
2,710,333 28,634,3479 
45,000 123,171,1736 
21,000 123,147,1756 
2,133,000 22,092,7879 
2,042,790 21,926,5419 
- 52,126 
- 52,126 
9,000 219,208 
10,933 218,375 
- 94,578,237 
- 94,578,237 
2,104,832 24,010,4369 
2,073,891 23,545,3859 
- 24,075,720' 
40,575 24,022,4699 
2,440,000 21,870,461 
2,591,698 21,524,534 
- 83,738,277 
- 83,738,701 
2,928,256 24,371,5789 
3,528,602 23,610,841' 
1. Includes funds provided by the Jobs Act (P.L. 98-8, dated 
March 24,1983) for projects listed in Table 19-N. 
2. Excludes $81,460 contributed funds and $1,348,816 special 
funds. 
19-21 
- --

TABLE 19-A 
(Continued) 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
COST AND FINANCIAL STATEMENT 
3. Includes $433,539 Emergency Relief funds. Exchange 
$1,256,068 from special contributed funds. 
4. Excludes $299,803 contributed funds and $13,211,728 
special funds. 
5. Excludes $134,919 contributed funds. Includes $49,581 
Public Works acceleration funds. 
6. Excludes $5,366,231 special funds. 
7. Excludes $946 contributed funds. Includes $39,999 Public 
Works acceleration funds. 
8. Excludes $4,470,000 contributed funds. 
9. Excludes $3,183,567 special recreation use fees funds as 
follows: 
Birch Lake 17,400 
Canton Lake 193,100 
Chouteau Lock & Dam 7,760 
Council Grove Lake 53,380 
Elk City 10,000 
Eufaula Lake 391,700 
TABLE 19-B 
Fall River 
Fort Gibson Lake 
Fort Supply Lake 
Heyburn Lake 
Hugo Lake 
Hulah Lake 
John Redmond Reservoir 
Kaw Lake 
Keystone Lake 
Lake Texoma 
Marion Lake 
Newt Graham Lock & Dam 
Oologah Lake 
Pat Mayse Lake 
Pine Creek Lake 
Robert S. Kerr Reservoir 
Tenkiller Lake 
Waurika Lake 
Webbers Falls 
AUTHORIZING LEGISLATION 
See 
Section 
in T'xt Acts Work .Authorized Documents 
8. ARCADIA LAKE. OK 
December 31,1970 
October 22,1976 
October 23,1962 
November 7,1966 
December 31,1970 
March 7,1974 
October 22,1976 
July 24, 1946 and 
October 22,1976 
October 23,1962 
October 23,1962 
October 23, 1962 
Construction of reservoir for flood control, water supply 
water quality control, and recreation purposes. 
Delete water quality benefits and include water supply 
benefits. 
ARK-RED RIVER BASINS CHLORIDE CONTROL 
Construction of experimental water quality study projects 
near Estelline and Guthrie, Tx. 
Project for water quality control, designated as Part I. 
Project for water quality control, designated as Part II. 
Modify 1966 and 1970 Acts -- Initiated construction of Area 
VIII features of the project consisting of low-flow dam 
pumping station, pipeline, and brine dam. 
Modify 1970 Act -- Gave construction approval to the 
Secretary of the Army. 
BIG AND LITTLE SALLISAW CREEKS NAVIGATION, OK 
Construction of navigation channel 9 feet deep with 
a minimum width of 100 feet from Robert S. Kerr Lock 
& Dam & Reservoir to near Sallisaw, OK, and a 
400-foot by 500-foot turning basin. 
BIG PINE LAKE, OK 
Construction of reservoir for flood control, water supply, 
recreation, and fish and wildlife purposes. 
CANDY LAKE, OK 
Construction of reservoir for flood control, water supply, 
water quality control, recreation, and fish and wildlife 
purposes. 
COPAN LAKE, OK 
Construction of reservoir for flood control, water supply, 
water quality control, recreation, and fish and wildlife 
purposes. 
H. Doc. 229, 91st Cong., 
2d sess. 
PL 94-587 
S. Doc. 110, 89th Cong., 
2d sess. 
S. Doc. 110, 89th Cong., 
2d sess. 
Chief of Engineers 
Report, May 6,1970 
PL 91-611 
PL 93-251 
PL 94-587 
H. Doc. 6407, 79th Cong., 
2d sess. 
PL 525, 79th Cong., as 
amended by PL 94-587 
H. Doc. 71, 88th Cong., 
1st sess. 
H. Doc. 563, 87th Cong., 
2d sess. 
H. Doc. 563, 87th Cong., 
2d sess. 
19-22 
13,400 
342,500 
69,300 
9,348 
71,270 
19,116 
56,336 
104,860 
251,880 
555,080 
61,280 
11,560 
110,000 
59,427 
22,200 
40,880 
670,500 
4,600 
7,760 
1. 
10. 
12. 
14.

TULSA, OKLAHOMA DISTRICT 
TABLE 19-B (Continued) AUTHORIZING LEGISLATION 
See 
Section 
in TIxt Acts Work Authorized Documents 
October 27,1965 
December 12,1970 
4. 
July 24, 1946 
October 23,1962 
July 4, 1960 
(as amended 
Dec. 31,1970) 
July 24,1946 
August 3,1955 
July 3,1958 
October 23,1962 
August 13,1968 
October 27,1965 
October 23,1962 
December 30,1963 
16. 
28. 
EL DORADO LAKE, KS 
Construction of reservoir to provide flood control, water supply, 
water quality, and recreation. 
MARION, KS 
Local protection works for flood control, diversion channel, 
levee, and appurtenant structures. 
MAINTENANCE & REPAIR FLEET & MARINE 
TERMINALS 
Wharf, office and storage building, storage space, and 
operating areas for floating maintenance and repair fleet. 
PEARSON-SKUBITZ BIG HILL LAKE, KS 
Construction of reservoir for flood control, water supply, 
and recreation purposes. 
POTEAU RIVER NAVIGATION, AR & OK 
Construction of navigation channel 9 feet deep and 130 
feet wide from the confluence of the Poteau River and 
the Arkansas River upstream on the Poteau 1.7 miles to 
Fort Smith, Ark., with a turning basin just upstream from 
Fort Smith. 
RED RIVER BELOW DENISON DAM 
(TULSA DISTRICT) 
Construct Boswell, Hugo, and Millwood Lakes, and Bank 
Stabilization 
Walnut Bayou Channel Improvements. 
Modify Millwood; construct Pine Creek, Lukfata, Broken 
Bow, DeQueen, Gillham, and Dierks Lakes. 
Construct Sardis and 'lTiskahoma Lakes. 
Modify 1946 Act - Construct bank stabilization, Index, 
AR, to Denison Dam, TX 
SHIDLER LAKE, OK 
Construction of reservoir for flood control, water supply, 
water quality control, and recreation purposes. 
SKIATOOK LAKE, OK 
Construction of reservoir for flood control, water supply, 
water quality control, recreation, and fish and wildlife 
purposes. 
WAURIKA LAKE, OK 
Construction of reservoir for flood control, irrigation, 
and conservation purposes. 
19-23 
H. Doc. 232, 89th Cong., 
1st sess. 
H. Doc. 256, 91st Cong., 
2d sess. 
H. Doc. 758, 79th Cong., 
2d sess. 
H. Doc. 572, 87th Cong., 
2d sess. 
Section 107, PL 86-645. 
H. Doc. 602, 79th Cong., 
2d sess. 
H. Doc. 488, 83rd Cong., 
2d sess. 
H. Doc. 170, 85th Cong., 
1st sess. 
S. Doc. 145, 87th Cong., 
2d sess. 
H. Doc. 304, 90th Cong., 
2d sess. 
H. Doc. 242, 89th Cong., 
1st sess. 
H. Doc. 563, 87th Cong., 
2d sess. 
S. Doc. 33, 88th Cong., 
1st sess. 
33. 
7. 
35. 
37. 
38. 
40.

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 19-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(See Section 44 of 'Ibxt) 
For Last Cost to September 30,1983 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Ark-Red River Basins Chloride Control, 
Supplemental Studies3 1980 9,791,805 - 
Augusta Levee, KS1 2 1938 - 84,217 
Bank Stabilization, Red River Below Denison' 1953 222,105 - 
Boswell Lake, OK6 1952 - - 
Cedar Point Lake, KS6 1980 - - 
Cherry and Red Fork Creeks Channel Improvement, OK3 1970 261,448 - 
Cow Creek Channel Improvement, KS6 1971 363,720 - 
Crutcho Creek Channel Improvement, OK4 6 1972 213,016 - 
Douglass Lake, KS5 1966 - - 
El Dorado KS West Branch, Walnut River, 
Channel Improvement 4 7 1977 92,319 - 
Enid Levee Floodway, OK3 1963 743,612 14,599 
Experimental Chloride Control Project, 
Red River Basin, Estelline and 
Guthrie, TX8 1975 300,028 135,444 
Flat Rock Creek Channel Improvement, 
Tulsa, OK3 9 1975 1,741,000 - 
Florence Levee, KS3 1965 369,782 - 
Hutchinson Levee and Channel, KS3 1956 3,497,718 - 
Iola Levee, KS3 1939 22,290 - 
Jenks Levee, OK3 1950 344,797 - 
Mud Creek Channel Improvement, OK4 1977 173,020 - 
Neodesha Lake, KS4 1952 97,910 - 
Oklahoma City Floodway, OK3 1960 8,047,512 - 
Sand Creek Channel Improvement, KS3 1968 545,996 - 
Sand Lake, OK3 1963 - - 
Spring Creek Channel Improvement, Springdale, AR 9 * 1975 1,371,000 - 
Towanda Lake, Walnut River Basin, KS4 7 1981 78,700,000 - 
Tulsa/West Tulsa Levees, OK3 1954 2,785,070 - 
Turtle Creek Channel Improvement, Yukon, OK4 1o 1975 144,853 - 
Tuskahoma Lake, OK6 1963 - - 
West Branch Chisholm Creek Channel Improvement, KS3 1965 364,200 - 
Wichita and Valley Center Channel Improvement, KS3 1960 12,247,379 - 
Winfield Levee, KS2 1937 - - 
Winfield Levee Modification, KS7 1977 98,897 - 
1. Reported by Memphis District in 1937; by Little Rock 7. Not economically justified at this time. 
District in 1938 and 1939. 
2. Completed by Kansas Works Progress Administration. 
3. Completed. 
4. Inactive. 
5. Awaiting appropriation of funds. 
6. Placed in deferred status 8 Oct 1981. 
8. Local assurances received but not economically justified 
at this time. 
9. Federal cost limited to $1,000,000. 
10. Notice of expiration of authorization after 5 years 
issued 24 August 1976. 
19-24

TULSA, OKLAHOMA DISTRICT 
TABLE 19-H ARKANSAS RIVER BASIN: MULTIPLE-PURPOSE PLAN 
(See Section 2 of Thxt) 
Feature River River Mile Nearest Ibwn 
Locks and Dams: 
W. D. Mayo, No.14 Arkansas 319.61 Redland, OK 
Robert S. Kerr, No.15 Arkansas 336.21 Cowlington, OK 
Webbers Falls, No.16 Arkansas 366.61 Gore, OK 
Chouteau, No.17 Verdigris 401.51 Okay, OK 
Newt Graham, No.18 Verdigris 421.61 Inola, OK 
Appurtenant Navigation Features: 
Channel cutoffs and enlargements Verdigris (2) Muskogee to Catoosa, OK 
Dredging Arkansas (2) 
Bank stabilization and channel 
rectification Arkansas 295.4 to Fort Smith, AR, to 
336.2 Robert S. Kerr Lock & Dam 
Robert S. Kerr Marine Tbrminal Arkansas 339.01 Sallisaw, OK 
Lakes: 
Canton North Canadian 394.3 Canton, OK 
Elk City Elk River 8.7 Elk City, KS 
Eufaula Canadian 27.0 Eufaula, OK 
Fall River Fall River 54.2 Fall River, KS 
Fort Gibson Grand (Neosho) 7.7 Fort Gibson, OK 
Keystone Arkansas 538.8 Sand Springs, OK 
Markham Ferry Grand (Neosho) 47.4 Locust Grove, OK 
Neodesha3 Verdigris 222.8 Neodesha, KS 
Oologah Verdigris 90.2 Oologah, OK 
Pensacola Grand (Neosho) 77.0 Disney, OK 
Thnkiller Ferry Illinois 12.8 Gore, OK 
'Ibronto Verdigris 271.5 Ibronto, KS 
Wister Poteau 60.9 Wister, OK 
1. Navigation miles - McClellan-Kerr 
Navigation System. 
2. As required for channel 9 feet deep. 
Arkansas River 3. See 
Projects." 
Table 19-E, "Other Authorized Flood Contro 
TABLE 19-I 
ARKANSAS-RED RIVER BASINS CHLORIDE CONTROL, PART I - 
WICHITA RIVER CHLORIDE CONTROL PLAN, TX 
(See Section 9A of 'bxt) 
ta04 Project River Sites Nearest Tbwn 
Area VII North Fork of the Wichita 213.0 Paducah, TX 
Area VIII South Fork of the Wichita 74.9 Guthrie, TX 
1huscott Brine Lake Bluff Creek 3.6 'Iuscott, TX 
Area X Middle Fork of the Wichita 19.7 Paducah, TX 
1. Approximate River Mile Above Mouth 
19-25

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 19-J ARKANSAS-RED RIVER BASINS CHLORIDE CONTROL, 
PART II-- RED RIVER PLAN, OK AND TX 
(See Section 9B of Txt) 
Project River Site' Nearest 'Ibwn 
Area VI Elm Fork River 54.0 Erick, OK 
Area VI, Brine Lake Fish Creek 1.6 Erick, OK 
Area IX Middle PPeeaassee River 5.0 Childress, TX 
Area XIII Jonah Creek 2.2 Childress, TX 
Area XIV Salt Creek 1.0 Childress, TX 
Area XV Little RRe d iver 14.0 Estelline, TX 
Crowell Brine Lake Fish Creek 1.6 Erick, TX 
Area I Salt Fork, Arkansas River 103.3 Jet, OK 
Area II-III Cimarron River 290.4 Freedom, OK 
Englewood Lake Cimarron River 346.5 Englewood, KS 
Area IV Salt Creek 25.3 Southard, OK 
1. Approximate River Miles Above Mouth 
TABLE 19-K
RED RIVER BELOW DENISON DAM FLOOD CONTROL PLAN 
(TULSA, DISTRICT) 
(See Section 35 of Thxt) 
Project River Site' Nearest 'bwn 
Bank Stabilizations Red River 485.3 Index, AR 
Boswell Lake2 Boggy Creek 18.9 Boswell, OK 
Broken Bow Lakes Mountain Fork River 20.3 Broken Bow, OK 
Hugo Lake3 Kiamichi River 17.6 Hugo, OK 
Lukfata Lakes Glover Creek 24.5 Glover, OK 
Pine Creek Lakes Little River 145.3 Wright City, OK 
Thskahoma Lakes Kiamichi River 118.5 'lhskahoma, OK 
1. River mile above mouth 
2. See 'lible 19-E "Other Authorized Flood Control 
Projects." 
3. Project is reported separately herein. 
19-26

TULSA, OKLAHOMA DISTRICT 
TABLE 19-L
INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS 
(See Section 42 of Txt) 
Inspection Date 
Project 1981 1982 
Carthage Levee, MO1 March/October - 
Cherry and Red Fork Creeks, OK March/October October 
Deep Fork Channel Improvement, OK April/October September 
Dodge City, KS' March/October October 
Enid Diversion Canal and Levee, OK May/November November 
Flat Rock Creek, OK March/November October 
Florence Levee, KS May/October October 
Hutchinson Levee, KS April/November October 
Iola Levee, KS April/October October 
Jenks Levee, OK March/October October 
Joe Creek Channel Improvement, OK March/October October 
Lamed, KS2 .March/October - 
Marion Diversion Channel and Levee, KS May/October October 
Oklahoma City Floodway, OK May/November November 
Polecat Creek Channel Improvement, OK March/October - 
Sand Creek Channel Improvement, KS May/October October 
South Deer Creek Levee, OK April/October October 
Springdale Levee, AR1 - - 
Thlsa/West ililsa Levees, OK March/October October 
Walnut Bayout Channel Improvement, AR1 - - 
1. T'fransferred to Little Rock District October 1, 1980. 2. fransferred to Thlsa District July 1, 1982. 
TABLE 19-M
FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION 
Section 205, PL 858, 80th Cong., as amended (Preauthorization) 
(See Section 45 of bxt) 
Fiscal Year 
Study Identification Cost 
$ 
Anderson Creek, Sand Springs, OK4 9,777 
Cat Creek, Claremore, OK1 10,631 
Coal Creek, Henryetta, OK1 14,918 
Coody, Corta, and Sam Creeks, Muskogee, OK3 7,500 
Haikey Creek, Tulsa, OKe 414,060 
Kingfisher and Uncle John's Creek, Kingfisher, OK4 96,336 
Main Branch Chisholm Creek, Park City, KS4 6 64,628 
McGrath Creek, Wichita Falls, TX3 7,500 
Merkle Creek, Norman, OK1 13,975 
North Canadian Wastewater Treatment Plant, Oklahoma City, OK4 57,911 
Willow Creek, Duncan, OK2 7,500 
(1) Reconnaissance Report and Detailed Project Report 
(2) Reconnaissance Report 
(3) Revolving Fund to be Reimbursed 
(4) Detailed Project Report 
(5) Plans and Specifications 
(6) Plans and Specifications and Construction 
19-27

TABLE 19-N 
--- 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
JOBS ACT CONTRACTS AWARDED 
DURING FY 83 
(P.L. 98-8, March 24, 1983) 
See 
Section 
in TIxt 
11. 
46. 
13. 
15. 
47. 
17. 
48. 
18. 
49. 
42. 
21. 
23. 
24. 
25. 
19-28 
Project 
Birch Lake, Verdigris River Basin, OK 
Broken Bow Lake, Little River Basin, OK 
Canton Lake, Arkansas River Basin, OK 
Council Grove Lake, Grand (Neosho) River Basin, KS 
Denison Dam - Lake Texoma, Red River Basin, TX & OK 
Elk City Lake, Verdigris River Basin, KS 
Eufaula Lake, Canadian River Basin, OK 
Fall River Lake, Verdigris River Basin, KS 
Fort Gibson Lake, Grand (Neosho) River Basin, OK 
Fourth Street Bridge, Florence, KS (Sec 14) 
Heyburn Lake, Arkansas River Basin, OK 
Hulah Lake, OK 
John Redmond Dam & Reservoir, Grand (Neosho) River, KS 
Kaw Lake, Arkansas River Basin, OK 
_ 
Type 
of 
Funding 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
FY 83 
$ 4,000 
25,000 
18,000 
15,500 
12,700 
100,000 
825,400 
49,200 
63,700 
31,100 
110,900 
36,600 
52,500 
31,500 
70,000 
30,900 
51,000 
42,000 
28,000 
2,500 
6,000 
200 
19,000 
11,200 
20,000 
15,000 
4,800 
75,000 
2,400 
28,000 
3,600

TABLE 19-N 
(Continued) 
19-29 
TULSA, OKLAHOMA DISTRICT 
JOBS ACT CONTRACTS AWARDED 
DURING FY 83 
(P.L. 98-8, March 24, 1983) 
See 
Section 
in Ibxt 
52. 
50. 
45. 
28. 
30. 
31. 
53. 
39. 
40. 
Project 
Robert S. Kerr Lock & Dam & Reservoir, 
Arkansas River Basin, OK 
Keystone Lake, Arkansas River Basin, OK 
Main Branch Chishom Creek, Park City, KS (Sec 205) 
Marion, KS 
Oologah Lake, Verdigris River Basin, OK 
Optima Lake, North Canadian River Basin, OK 
Tenkiller Ferry Lake, Illinois River Basin, OK 
Toronto Lake, Verdigris River Basin, KS 
Waurika Lake, Red River Basin, OK 
Type 
of 
Funding 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
FY 83 
207,600 
191,600 
46,000 
21,500 
351,800 
34,300 
15,500 
15,500 
37,000 
3,000 
119,000 
67,600 
20,000 
7,900 
27,300 
19,500 
12,500 
500 
41,600 
28,100

KANSAS CITY, MO., DISTRICT* 
The district comprises a portion of southwestern 
Iowa; northwestern, central, and western Missouri; 
northern Kansas; southern Nebraska; and a portion of 
northeastern Colorado embraced in drainage basin of 
the Missouri River and tributaries from Rulo, Nebraska, 
to the mouth. Report on navigation project for section 
of Missouri River from Sioux City, Iowa, to Rulo, 
Nebraska, is in report of Omaha District. 
IMPROVEMENTS 
Navigation 
1. Missouri River, Sioux City, IA, to 
Mouth (Rulo, Nebraska, to Mouth) .. 
2. Blue River Basin Plan, Vicinity 
of Kansas City (Kansas City District). 
Page Flood Control (cont.) 
25. Inspection of Completed Flood 
....... 20-2 Control Projects ............... 
26. Flood Control Work Under Special 
....... 20-2 Authorization ................. 
Page 
....... 20-8 
....... 20-9 
Flood Control 
3. Blue River Channel, Kansas City, MO ...... 20-2 
4. Clinton Lake, Wakarusa River, KS ......... 20-3 
5. Gypsum, Gypsum Creek, KS .............. 20-3 
6. Harlan County Lake, Republican 
River, N E .............................. 20-3 
7. Hillsdale Lake, Big Bull Creek, KS ......... 20-3 
8. Kanopolis Lake, Smoky Hill River, KS ...... 20-4 
9. Kansas City, Kansas River, KS (1962 Mod.).. 20-4 
10. Lawrence, Kansas River, KS ............... 20-4 
11. Little Blue River Channel, MO ............. 20-5 
12. Little Blue River Lakes, MO .............. 20-5 
13. Long Branch Lake, Little Chariton 
River, M O ............................. 20-5 
14. Melvern Lake, Marais des Cygnes 
(Osage) River, KS ..................... 20-6 
15. Milford Lake, Republican River, KS ......... 20-6 
16. Missouri River Levee System, IA, NE, 
KS, and MO (Rulo, NE to Mouth) ........... 20-6 
17. Perry Lake, Delaware River, KS ........... 20-6 
18. Pick-Sloan Missouri Basin Program 
(Kansas City Dist.) ....................... 20-7 
19. Pomme de Terre Lake, Pomme de 
Terre River, M O ......................... 20-7 
20. Pomona Lake, One Hundred Ten 
Mile Creek, KS ......................... 20-7 
21. Rathbun Lake, Chariton River, IA .......... 20-7 
22. Smithville Lake, Little Platte River, MO ..... 20-8 
23. Tuttle Creek Lake, Big Blue River, KS ...... 20-8 
24. Wilson Lake, Saline River, KS ............. 20-8 
Multiple Purpose Projects Including Power 
27. Harry S. Truman Dam and 
Reservoir, Osage River, MO .......... 
28. Stockton Lake, Sac River, MO ........ 
General Investigations 
29. General Investigations .............. 
Tables 
Table 20-A 
Table 20-B 
Table 20-C 
Table 20-D 
Table 20-E 
Table 20-F 
Table 20-G 
Table 20-H 
Table 20-I 
Table 20-J 
Table 20-K 
Table 20-L 
Table 20-M 
..... 20-9 
..... 20-9 
..... 20-10 
Cost & Financial Statement ........ 20-11 
Authorizing Legislation ........... 20-14 
Other Authorized Navigation 
Projects ........................ 20-18 
Not Applicable 
Other Authorized Flood Control 
Projects ........................ 20-19 
Not Applicable 
Deauthorized Projects ............ 20-20 
Missouri River, Sioux City, IA, 
to Mouth (Rulo, NE to Mouth) 
Total Cost of Existing Project ...... 20-20 
Missouri River Sioux City to 
Mouth: Terminal Facilities ......... 20-21 
Missouri River Levee System ...... 20-22 
Kansas City District Projects 
Included in Pick-Sloan Missouri 
Basin Program .................. 20-23 
Inspection of Completed Flood 
Control Projects ................. 20-24 
Active General Investigations ...... 20-25 
20-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Navigation 
1. MISSOURI RIVER, SIOUX CITY, IA, 
TO MOUTH (RULO, NE, TO MOUTH) 
Location. Jefferson, Madison, and Gallatin Rivers 
conjoin at Three Forks, Mont., to form the Missouri 
River, which flows southeasterly 2,315 miles (1960 
mileage) across or along seven states to the Mississippi 
River, 17 miles above St. Louis. For description see page 
1149, Annual Report for 1932. The river is commercially 
navigable from Sioux City, Iowa to the mouth, a 
distance of 732 miles. The portion of project in Kansas 
City District extends from Rulo, Nebraska to the 
mouth, a distance of 498 miles. 
Previous projects. For details see page 1891 of Annual 
Report for 1915, and pages 1153 and 1175 of Annual 
Report for 1938. 
Existing project. A channel of 9-foot depth and width 
not less than 300 feet, obtained by revetment of banks, 
construction of permeable dikes to contract and 
stabilize waterway, cutoffs to eliminate long bends, closing 
minor channels, removal of snags, and dredging as 
required. Improved section (mouth to upper end of Rulo 
Bend) is 498.4 miles (1960 mileage) long. Bank stabilization 
work on this section of the project (Rubo, NE, to 
mouth) is essentially complete. River access sites have 
been completed at 11 locations. Ordinary and extreme 
fluctuations of stage are 16 and 38 feet, respectively. 
Local cooperation. Cooperation from benefited 
localities may be required where any improvement may 
confer special benefit. The receipt of contributions from 
private parties are to be expended along with Government 
funds upon authorized work where such work 
would be in the interest of navigation, as authorized by 
1915 Rivers and Harbors Act. Secretary of the Army 
approved general principle of cooperative construction 
on Missouri River below Kansas City on basis that 25 
percent of cost of any special installation shall be paid 
by the United States and 75 percent by local interests. 
Total contributed by local interests in cooperation with 
the United States from 1918 to June 30, 1964, was 
$675,663, of which $8,647 was returned to contributors. 
Local interests must share in cost of recreation facilities 
in accordance with provisions of the Federal Water Project 
Recreation Act of 1965. Local interests have contributed 
$164,185 for cost sharing on construction of 
recreation in addition to facilities. constructing portions of the 
Terminal facilities. Facilities for transferring 
agricultural, petroleum, and other commodities are 
maintained by private interests at various locations on 
this section of the river. Present facilities, listed in Table 
20-H, are adequate for existing commerce. 
Operations during fiscal year. The 1974 Base Line 
Study of the reach of the Missouri River in the Kansas 
City District estimated recreation use on the river at 
1,250,000 recreation days annually. The projected tonnage 
on the river for FY 1983 is approximately 2.6 
million. Maintenance: Repair of dikes and revetments 
by contract. In addition, following work was accomplished 
by hired labor: Construction of environmental 
gaps and dike and revetment repair, maintenance of 
U.S. Government dredge in standby status, real estate 
management, channel reconnaissance, condition 
studies, surveys and mapping, stream gaging, environmental 
studies and special working data, engineering 
and design, surveys and layout of construction, and 
supervision and administration. There was no dredging 
because no significant bars or shoals developed. 
2. BLUE RIVER BASIN PLAN, VICINITY 
OF KANSAS CITY (KANSAS CITY DIST.) 
Location. The Blue River is a right-bank tributary of 
the Missouri River which drains a 272 square-mile basin 
within the Kansas City Standard Metropolitan 
Statistical Area. Approximately 60 percent of the basin 
is in Johnson County, Kansas, and 40 percent is divided 
between Jackson and Cass Counties, Missouri. The 
authorized plan is for four multiple-purpose lakes on 
tributaries to the Blue River and channel modification 
on approximately 12 miles of the main stem from 63rd 
Street in Kansas City, Missouri, to the mouth. 
Existing project. The four lakes form a system which 
would provide flood control, low streamflow supplementation 
and recreation and fish and wildlife. In addition, 
each of the lakes was recognized as a potential source of 
municipal and industrial water supply. The channel 
modification would provide improved flood protection 
to a highly developed segment of the floodplain 
downstream of the lakes. 
Operations during fiscal year. Preconstruction planning 
of the channel modification is essentially complete 
and the project has received a construction appropriation 
in each of the last five fiscal years. However, the 
local sponsor, Kansas City, Missouri, has experienced 
difficulty in implementing the local sponsorship requirements. 
These difficulties have now been resolved 
and the channel project is expected to be under construction 
early this fiscal year. Because of a lack of local 
support the three lakes in Kansas, Indian, Tomahawk, 
and Wolf-Coffee, were placed in the inactive category. 
Indian and Tomahawk were reclassified in 1976 and 
Wolf-Coffee was reclassified in 1978 after all potential 
non-Federal sponsors indicated no further interest in 
sponsoring either water supply or recreation development. 
Mill Lake in Missouri is in the deferred category 
pending the availability of funds for restudy. 
Flood Control 
3. BLUE RIVER CHANNEL, 
KANSAS CITY, MO 
Location. Along the Blue River and tributaries in 
Jackson County, Missouri. 
Existing project. Preliminary plans consist of 12.5 
miles of improved channel along the Blue River within 
Kansas City, Missouri. Estimated Federal cost through 
construction of the project (1983) is $129,000,000 and 
estimated non-Federal cost of lands, damages and 
relocations is $19,100,000. 
20-2

KANSAS CITY, MO., DISTRICT 
Local cooperation. Section 2, Flood Control Act of 
June 22, 1936, applies. The city of Kansas City, 
Missouri, passed a resolution of intent on 9 December 
1975 to provide the required assurances of local cooperation 
when requested. A Section 221 agreement was 
signed by the city October 8, 1979, but review by the 
Corps was delayed until the city's sources of funding 
could be established. 
Operations during fiscal year. Preconstruction planning 
is complete and plans and specs are underway. 
Plans and specifications for the second contract were 
completed. Construction of the first and second contracts 
will be initiated early this FY. Problems with a 
major landowner prevented right-of-way acquisition by 
the end of fiscal year. This problem has now been resolved 
and the 221 Agreement was approved 8 
September 1983. 
4. CLINTON LAKE, WAKARUSA 
RIVER, KS 
Location. Damsite is on Wakarusa River about 4 
miles southwest of Lawrence, Kansas, in Douglas County. 
Lake extends into Shawnee and Osage Counties, 
Kansas. 
Existing project. An earthfill dam about 9,250 feet 
long constructed to a maximum height of about 114 feet 
above riverbed, with an uncontrolled spillway in left 
abutment. Total reservoir storage capacity 397,200 
acre-feet (258,300 for flood control, 28,500 for sediment 
reserve, and 110,400 of multipurpose storage for 
municipal and industrial water supply and recreation). 
The estimated Federal cost (1983) is $57,521,533. Construction 
was initiated in January 1972 and the project 
was placed in operation in November 1977. 
Local cooperation. Section 2, Flood Control Act of 
June 28, 1938, applies. Reimbursement in the estimated 
amount of $7,249,000 is required for water supply 
storage in accordance with Water Supply Act of 1958. A 
contract was signed by the State on September 6, 1978 
and was approved by the Secretary of the Army on October 
30, 1978. Utilization of storage was initiated in 
December 1979. Repayment also began at that time. 
Operations during fiscal year. Visitation for FY 1983 
was 1,239,100 visitor days. Project is 99 percent complete. 
Work remaining consists of completing administrative 
buildings and interpretive program, providing 
cathodic protection for service gates, and improvement 
of an access road intersection. Maintenance: 
Activities consisted of boundary monumentation, 
forestation and ordinary operation and maintenance. 
5. GYPSUM, GYPSUM CREEK, KS 
Location. At Gypsum, Saline County, Kansas, on the 
left bank of Gypsum Creek, 10 miles south of its confluence 
with Smoky Hill River, 15 miles southeast of 
Salina, Kansas. 
Existing project. A levee around the city, a diversion 
channel, and channel improvement work. Total Federal 
cost to essentially complete the project was approximately 
$2,651,952, and estimated non-Federal cost of 
lands, damages, and relocations was $278,000. 
Local cooperation. Section 3, Flood Control Act of 
June 22, 1936 applies. A Section 221 agreement was 
signed by the City of Gypsum on June 14, 1976 and by 
the Secretary of the Army on August 31, 1976. 
Operations during fiscal year. Inspection indicated 
sod cover on the high-flow channel had not been 
established. Removal of channel block in the fall of 1983 
was premature, and another plant growing season is required. 
Current plans call for removal of channel block 
after spring 1984 flood season. The project is scheduled 
for completion on 30 June 1984. 
6. HARLAN COUNTY LAKE, 
REPUBLICAN RIVER, NE 
Location. Dam is on main stem of Republican River 
about 235 miles above confluence of stream with Smoky 
Hill River. Site is in Harlan County, about 3 miles east 
of Republican City and 13 miles west of Franklin, 
Nebraska. 
Existing project. An earthfill dam about 107 feet 
above streambed with a total length of 11,827 feet, including 
a gate-controlled, concrete, gravity-type 
spillway section near center of dam. Reservoir provides 
storage capacity of 850,000 acre-feet (500,000 for flood 
control and 350,000 for irrigation and sedimentation 
allowance). Initial cost of constructing the project was 
$45,279,532. Total estimated Federal cost of project 
(1983), including $1,017,623 for major rehabilitation 
work and $3,126,000 supplemental recreation development 
(Code 710), is $49,423,155. Construction of the 
project was initiated in August 1946. Project was 
placed in operation in December 1952. Major rehabilitation 
work was completed in FY 1968. Future supplemental 
recreation facilities remain to be designed and 
constructed. 
Local cooperation. Section 2, Flood Control Act of 
1938, applies. 
Operations during fiscal year. Visitation for FY 1983 
was 953,200 visitor days. Supplemental recreational 
development activity during the year consisted of construction 
by hired labor of waterlines and vault toilets 
in the Methodist Cove, Gremlin and Hunter Cove areas. 
Also, the Patterson Harbor sewage treatment facility 
contract was completed. Maintenance: Activities included 
forestation, initiation of overhaul of gates, resurfacing 
of roads, and ordinary operation and 
maintenance. 
7. HILLSDALE LAKE, BIG BULL 
CREEK, KS 
Location. The project is located approximately 12 
miles above the mouth of Big Bull Creek, a tributary of 
the Marais des Cygnes River and about 15 miles 
southwest of the Kansas City metropolitan area in 
Miami County, Kansas. 
20-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Existing project. An earthfill embankment about 
11,600 feet long (including approximately 3,300 feet of 
dike section) about 75 feet above rising valley flood 
plain. The spillway is gravity type uncontrolled and the 
outlet works are controlled. The total reservoir storage 
capacity is 160,000 acre-feet (81,000 for flood control, 
11,000 for sediment reserve, and 68,000 for multipurpose 
storage for water supply, water quality control, 
and recreation). Construction was initiated in December 
1974 and project was placed in operation in October 
1982. Estimated Federal cost (1983) through construction 
of the project is $63,981,800. 
Local cooperation. Section 2, Flood Control Act 1938, 
applies. Local interests must make reimbursement of 
$21,091,814 for water supply storage in accordance with 
Water Supply Act of 1958. The Kansas Water 
Resources Board signed a contract in January 1974, approved 
by the Secretary of the Army in April 1974, for 
the entire 53,000 acre-feet of water supply storage. 
Local interests have shown no interest in sponsoring 
recreational development at this time. Therefore, only 
minimum recreational facilities have been built. 
Operations during fiscal year. Financial completion of 
several contracts was accomplished. Also, installation 
of the stilling basin guardrail and repair of clay blanket 
were completed. 
8. KANOPOLIS LAKE, SMOKY 
HILL RIVER, KS 
Location. Dam is on Smoky Hill River about 19 miles 
west and 16 miles south of Salina, Kansas, and about 
205 river miles above mouth of stream. 
Existing project. An earthfill dam about 131 feet 
above streambed, having a total length of 15,360 feet, 
including 4,070 feet of dike section on left abutment and 
2,550 feet of dike section on right abutment. The reservoir 
provides storage capacity of 450,000 acre-feet, 
(400,000 for flood control and 50,000 for recreation and 
streamflow regulation). Outlet works and spillway are in 
right abutment. Initial cost of constructing the project 
was $12,327,735. Total Federal cost of project (1983), including 
$822,000, supplemental recreational development 
(Code 710), is $13,149,735. Construction was initiated 
in June 1940 and project was placed in operation 
in May 1948. Future supplemental recreation facilities 
remain to be designed and constructed. 
Local cooperation. Section 2, Flood Control Act of 
1938, applies. 
Operations during fiscal year. Visitation for FY 1983 
was 479,200 visitor days. Maintenance: Activities consisted 
of installation of seepage drains, riprap repair, 
resurface roads, and ordinary operation and 
maintenance. 
9. KANSAS CITY, KANSAS RIVER, KS 
(1962 MOD.) 
Location. Along the Kansas River at Kansas City, 
Kansas. 
Existing project. Provides for raising existing levees 
and floodwall protection in Argentine, Armourdale, and 
Central Industrial units, and includes necessary bridge 
alterations and modification of appurtenant facilities. 
Existing project was authorized by 1962 Flood Control 
Act, P.L. 87-874 (S. Doc. 122, 87th Cong., 2d sess.). The 
downstream section of the Argentine unit and the 
Bridge and Approach Alterations unit have been assigned 
to inactive status. Estimated Federal cost of construction 
(1983) is $25,100,000 and estimated non- 
Federal cost of lands, damages, and relocations is 
$1,181,000. Construction of the upstream portion of 
Argentine unit was initiated in May 1971 and completed 
in February 1974. The Armourdale unit was initiated in 
November 1973 and completed in September 1976. Construction 
of the Central Industrial unit was initiated in 
April 1977 and completed in October 1979. 
Local cooperation. Section 3, Flood Control Act of 
June 22, 1936, applies. Assurances of local cooperation 
were received December 4, 1968. Rights-of-way for the 
Argentine unit upstream section, the Armourdale unit 
and Central Industrial unit have been furnished. 
Operations during fiscal year. Regular funds, new 
work: Contract for floodwall strengthening in the Armourdale 
unit was initiated in September 1983. 
10. LAWRENCE, KANSAS RIVER, KS 
Location. On Kansas River about 50 miles above its 
mouth at Lawrence, Douglas County, Kansas. 
Existing project. Levees along both banks of Kansas 
River and right bank of Mud Creek, channel improvement 
for Mud Creek, bank protection and appurtenant 
facilities for protection of North Lawrence, Kansas. 
Since the city of Lawrence is no longer interested in 
sponsoring the South Lawrence unit, this unit was 
deleted from the project cost estimate and reclassified 
to an inactive status. By letter dated 9 January 1970, 
the city of Lawrence indicated an interest in developing 
a recreational facility on lands obtained for the 
Lawrence Flood Protection Project. Estimated Federal 
cost of construction (1983) is $8,636,111 and estimated 
non-Federal cost of lands, damages, and relocations is 
$2,130,000. Construction of the project was initiated 
June 30, 1967. The Kansas River portion was completed 
in March 1972 and the Mud Creek portion in July 1978. 
Government construction of the riverfront recreation 
facilities was completed on 9 July 1981. The city of 
tLioanw roenn cet heixs preecctsr etaot ioconm aprleeate their portion of construc- in the spring or summer 
of 1984. 
Local cooperation. Section 3, Flood Control Act of 
June 22, 1936, applies, Board of Commissioners of city 
of Lawrence furnished required assurances June 8, 
1965. All required rights-of-way for construction have 
been furnished. Right-of-way for the recreational facility 
is available and the city of Lawrence signed a Section 
221 agreement on 13 September 1979. The agreement 
stated Government costs to be $204,305 and city costs 
to be $88,901 for construction. 
20-4

KANSAS CITY, MO., DISTRICT 
Operation during fiscal year. Financial completion of 
the Union Pacific Railroad was finalized. 
11. LITTLE BLUE RIVER CHANNEL 
IMPROVEMENT, LITTLE BLUE 
RIVER, MO 
Location. The project is located along the Little Blue 
River and extends from the head of Missouri River 
Levee Unit R 351, 22 miles upstream to the vicinity of 
Wildwood Creek in Jackson County, Missouri. 
Existing project. The improvements consist of 
straightening and enlarging the Little Blue River channel 
from the head of Missouri River Levee Unit R 351, 
near Blue Mills Road, upstream to the vicinity of 
Wildwood Creek, reducing the length of this section 
from 20.4 to about 15 miles. Alteration of six highway 
bridges and construction of five new highway bridges 
and one railroad bridge were required. Improvements in 
the vicinity of Lake City Army Ammunition Plant consists 
of diversion of West Fire Prairie Creek into the Little 
Blue River and construction of a levee. Estimated 
Federal cost through construction of the project (1983) 
is $27,400,000 and estimated non-Federal cost is 
$3,390,000. Construction was initiated in December 
1974. 
Local cooperation. Section 3, Flood Control Act of 
June 22, 1936, applies to the Little Blue River channel 
improvement works. Jackson County, Missouri, passed 
a bond issue for sponsorship of the project. Assurances 
of local cooperation were furnished July 31, 1973. 
Operations during fiscal year. Project is 78 percent 
complete. Stage 5, Phase II, Lake City, was underway. 
12. LITTLE BLUE RIVER LAKES, MO 
Location. This project consists of two lakes in 
Jackson County, Missouri, located in Kansas City, 
Missouri, and suburban communities. The Blue Springs 
Lake site is on the East Fork of the Little Blue River 
about one-half mile south of U.S. Highway 40 and the 
Longview Lake site is on the main stem at approximately 
109th Street. 
Existing project. The Blue Springs dam will be an 
earthfill embankment about 2,500 feet long and rising 
about 78 feet above the streambed, with an uncontrolled 
service spillway and uncontrolled outlet conduit. The 
total reservoir storage capacity will be 26,600 acre-feet 
(15,700 for flood control, 10,600 for multipurpose 
storage for water quality and recreation, and 300 for 
sedimentation). 
The Longview dam will be an earthfill embankment 
about 1,900 feet long and rising about 120 feet above 
the streambed, with an uncontrolled service spillway 
and an uncontrolled outlet conduit. The total reservoir 
storage capacity will be 46,900 acre-feet (24,300 for 
flood control and 20,600 for multipurpose storage for 
water quality and recreation and 2,000 for sedimentation). 
Estimated Federal cost (1983) through construction 
of the project is $139,000,000. Construction was initiated 
in September 1977. 
Local cooperation. Section 2 of the Flood Control Act 
of June 28, 1938, applies. Local interests must share in 
separable cost allocated to recreation in accordance with 
Federal Water Project Recreation Act of 1965. The 
Jackson County Legislature approved a recreation costsharing 
contract on July 5, 1974 which was approved by 
the Secretary of the Army on June 24, 1976. A supplemental 
agreement, signed by Jackson County officials 
on June 5, 1978, and approved by the Secretary of 
the Army January 10, 1979, revised the existing contract 
to include additional costs involved in raising the 
multipurpose pool elevation at the Blue Springs Lake. 
Estimated reimbursement for recreation is $14,661,000. 
Operations during fiscal year. Contracts were underway 
for Longview and Blue Springs Lakes for relocation 
of roads, utility, access roads, and dam contracts. Also, 
Longview and Blue Springs recreation facilities were 
underway. Project is 69 percent complete. Land acquisition 
is complete. 
13. LONG BRANCH LAKE, LITTLE 
CHARITON RIVER, MO 
Location. Damsite is on East Fork of Little Chariton 
River in north-central Missouri about 1 mile west of 
Macon in Macon County. 
Existing project. An earthfill dam about 3,800 feet 
long and about 71 feet high with an uncontrolled outlet 
conduit and an uncontrolled service spillway in right 
abutment. Total reservoir storage capacity will be 
65,000 acre-feet (29,000 for flood control, 4,000 for sediment 
reserve, and 32,000 of multipurpose storage for 
water supply, water quality control, fish and wildlife, 
and recreation). Estimated Federal cost (1983) is 
$20,200,000, and estimated non-Federal cost is 
$3,500,000. Construction was initiated in March 1973. 
Project was placed in useful operation for flood control 
on September 1, 1980. 
Local cooperation. Section 2, Flood Control Act of 
June 28, 1938, applies. Local interests must make reimbursement 
of $5,579,000 for water supply storage in accordance 
with Water Supply Act of 1958 and share in 
separable cost of $3,500,000 allocated to recreation in 
accordance with Federal Water Project Recreation Act 
of 1965. On September 15, 1972 the Secretary of the Army 
approved a contract signed by the city of Macon, 
Mo. for water supply and recreation development. 
Missouri State agencies indicated their intent to sponsor 
future water supply and signed a contract on June 
17, 1977 to sponsor recreational development in lieu of 
city of Macon. After review by the Office of the 
Secretary of the Army, the state signed the contract in 
December 1979 and it was approved by the Secretary of 
the Army on April 18, 1980. 
Operations during fiscal year. Visitation for FY 1983 
was 602,700 visitor days. Contract was completed for 
Stage 2 recreation facilities. Contract for modification 
to the aministration sewer system was essentially completed. 
Project is 95 percent complete on scheduled 
work. Maintenance: Activities consisted of ordinary 
operation and maintenance. 
20-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
14. MELVERN LAKE, MARAIS DES 
CYGNES (OSAGE) RIVER, KS 
Location. Damsite is on Marais des Cygnes (Osage) 
River in Osage County, Kansas, about 2 miles west of 
Melvern, Kansas. 
Existing project. An earthfill dam about 9,700 feet 
long and about 98 feet high with an uncontrolled chutetype 
spillway in left abutment. Total reservoir storage 
capacity is 363,000 acre-feet (200,000 for flood control, 
26,000 for sediment reserve, and 137,000 of multipurpose 
storage for water quality control and recreation). 
Initial cost of constructing the completed project was 
$37,436,530. Construction was initiated in July 1967 
and the project was placed in operation in August 1972. 
Local cooperation. Section 2, Flood Control Act of 
1938, applies. 
Operations during fiscal year. Visitation for FY 1983 
was 1,074,100 visitor days. Maintenance: Activity consisted 
of road resurfacing, modification to administration 
building and ordinary operation and maintenance. 
15. MILFORD LAKE, REPUBLICAN 
RIVER, KS 
Location. Damsite is on Republican River near village 
of Alida and about 8 miles downstream from Milford, 
Geary County, Kansas, and about 10 miles above confluence 
of Republican and Smoky Hill Rivers which 
form Kansas River near Junction City, Kansas. 
Existing project. An earthfill dam about 6,300 feet 
long and 126 feet high with an uncontrolled servicechute 
spilway in a saddle on right abutment. Total 
reservoir storage capacity is 1,160,000 acre-feet 
(700,000 for flood control, 160,000 for sediment reserve 
and 300,000 of multipurpose storage for water supply, 
water quality control, and recreation). Water supply 
storage is included in project at request of Governor of 
Kansas under provisions of Federal Water Supply Act 
of 1958. Initial cost of constructing the completed project 
was $48,268,843. Total estimated Federal cost of 
project (1982), including $1,298,000 supplemental recreational 
development (Code 710), is $49,566,843. Construction 
was initiated in July 1961. Project was placed 
in operation in June 1965. Construction of supplemental 
recreation facilities is underway. 
Local cooperation. Section 2, Flood Control Act of 
1938, applies. Local interests must make reimbursement 
of $13,467,000 for water supply storage in accordance 
with Water Supply Act of 1958. Utilization of 
storage has not been initiated. Reimbursement was initiated, 
at the option of the State, in September 1976. 
Operations during fiscal year. Visitation for FY 1983 
was 1,303,400 visitor days. Supplemental recreational 
development consisted of initiation of well house, 
pressure tank and water line by hired labor. 
Maintenance: Activities included continuation of 
seismic reevaluation, modification of administration 
building and ordinary operation and maintenance. 
16. MISSOURI RIVER LEVEE 
SYSTEM, IA, NE, KS, AND MO 
(RULO, NE, TO MOUTH) 
Location. On both banks of Missouri River from Sioux 
City, Iowa, about 760 miles to mouth near St. Louis, 
Missouri. Portion of project in Kansas City District extends 
from Rulo, Nebraska, 498 miles to mouth. 
Existing project. A series of levee units and appurtenant 
works along both sides of Missouri River from 
Sioux City, Iowa, to the mouth, for protection of 
agricultural lands and small communities against 
floods. Estimated Federal cost (1983) for the active portion 
of the project from Rulo, Nebraska to mouth is 
$157,200,000. Costs of $16,800,000 for lands and 
damages to be borne by local interests. Remaining portion 
of project consists of units on which planning and 
construction are being delayed pending completion of 
restudy to assure that additional levee construction is 
economically justified. Cost estimate for deferred and 
inactive portion of project Rulo, Nebraska, to mouth is 
$298,082,500 (1964 price level except Unit L 15 which is 
1975 price level) of which $274,098,000 is Federal cost 
for construction and $23,984,500 for lands and damages 
to be borne by local interests. Construction of the project 
was initiated in June 1948. 
Local cooperation. Section 3, Flood Control Act of 
1936, applies. Fully complied with for all completed 
units and units under construction. Sponsor for Unit L 
345-330 has optioned the major part of lands for rightsof-
way. Because of anticipated changes as a result of the 
National Environmental Policy Act of 1969, the District 
advised the sponsor to suspend condemnation proceedings 
for remaining requirements pending development 
of an alternate plan. Local sponsors provide all 
operation and maintenance. 
Operations during fiscal year. Status of individual 
units of active portion of project at end of fiscal year is 
shown in Table 20-J on Missouri River levee system. 
Remedial work on L 246 was essentially completed. 
Planning on remaining active units continued. 
17. PERRY LAKE, DELAWARE 
RIVER, KS 
Location. Damsite is on Delaware River about 5 miles 
above mouth in Jefferson County, Kansas, and about 3 
miles north of Perry, Kansas. 
Existing project. An earthfill dam about 7,750 feet 
long constructed to an elevation about 95 feet above 
valley floor with gated-outlet works and an uncontrolled 
spillway in left abutment. Total reservoir storage 
capacity is 770,000 acre-feet (480,000 for flood control, 
140,000 for sediment reserve and 150,000 of multipurpose 
storage for water supply, water quality control, 
and recreation). Water supply storage is included in 
project plan at request of State of Kansas under provisions 
of Federal Water Supply Act of 1958. Initial cost 
of constructing the completed project was $48,371,706. 
20-6

KANSAS CITY, MO., DISTRICT 
Total Federal cost of project, including $1,068,000 
(1983) supplemental recreational development (Code 
710), is $49,439,706. Construction was initiated in 
March 1964 and the project was placed in operation in 
January 1969. Future supplemental recreation facilities 
remain to be designed and constructed. 
Local cooperation. Section 2, Flood Control Act of 
1938, applies. Local interests must make reimbursement 
of $8,290,000 for water supply storage in accordance 
with Water Supply Act of 1958. Utilization of 
storage has not been initiated. Reimbursement was initiated 
at the option of the State in September 1978. 
Operations during fiscal year. Visitation for FY 1983 
was 1,664,800 visitor days. Maintenance: Activity included 
road resurfacing and ordinary operation and 
maintenance. 
18. PICK-SLOAN MISSOURI BASIN 
PROGRAM (KANSAS CITY DIST.) 
Location. Flood control improvements included in this 
project are on and along the Missouri River and several 
of its principle tributaries, in States comprising the 
Missouri River Basin. 
Existing project. The Pick-Sloan Missouri Basin program 
for flood control and other purposes in Missouri 
River Basin provides for levees along Missouri River 
between Sioux City, Iowa, and the mouth, floodprotection 
works at certain municipalities, and reservoirs 
on main stem of Missouri River and on tributaries 
for control of flooding. (See Table 20-B for authorizing 
legislation and Table 20-K on Kansas City District projects 
included in Pick-Sloan Missouri Basin program.) 
See individual project reports. 
Operations during fiscal year. Operations are shown 
in individual reports for those project expenditures on 
which plans were in preparation or construction was initiated. 
Under sections 7 and 9, 1944 Flood Control Act, 
the Corps is responsible for detailed scheduling of operations 
concerning storage capacity reserved for or assigned 
to flood control in reservoirs constructed by 
Bureau of Reclamation as well as those constructed by 
the Corps. 
19. POMME DE TERRE LAKE, 
POMME DE TERRE RIVER, MO 
Location. Dam is on main stem of Pomme de Terre 
River, about 44 miles above mouth of stream in Hickory 
County, Missouri. The lake extending upstream into 
Polk County, Missouri. Site is about 3 miles south of 
Hermitage, Missouri, and 20 miles north of Bolivar, 
Missouri. 
Existing project. An earth and rockfill dam about 
4,630 feet long constructed to about 155 feet above 
riverbed and a dike section on left abutment about 2,790 
feet long, providing storage capacity of 650,000 acrefeet 
(407,000 for flood control and 243,000 for sedimentation 
and multi-purpose). Initial cost of constructing 
the completed project was $14,946,784. Total estimated 
Federal cost of project (1983), including $329,140 area 
redevelopment and $3,368,000 supplemental recreational 
development (Code 710), is $18,643,924. Construction 
was initiated in January 1957 and the project 
was placed in useful operation in October 1961. Future 
supplemental recreation facilities remain to be designed 
and constructed. 
Local cooperation. Section 2, Flood Control Act of 
1938, applies. 
Operations during fiscal year. Visitation for FY 1983 
was 1,185,100 visitor days. Maintenance: Activities included 
road resurfacing and ordinary operation and 
maintenance. 
20. POMONA LAKE, ONE HUNDRED 
TEN MILE CREEK, KS 
Location. Dam is on One Hundred Ten Mile Creek, a 
tributary of Marais des Cygnes (Osage) River, 7 miles 
above mouth of stream in Osage County, Kansas, about 
7 miles northwest of Pomona, Kansas, and 34 miles 
upstream from Ottawa, Kansas. 
Existing project. An earthfill dam 7,750 feet long constructed 
to an average height of about 85 feet above 
streambed, with gated-outlet works and an ungated 
chute-type spillway near left abutment. Total reservoir 
storage capacity is 230,000 acre-feet (160,000 for flood 
control, 14,000 for sediment reserve, and 56,000 of 
multipurpose storage for water quality control and 
recreation). Initial cost of constructing the completed 
project was $13,272,108. Total estimated Federal cost 
of project (1983), including supplemental recreational 
development $1,543,000 (Code 710), is $14,815,108. Construction 
began in July 1959 and the project was placed 
in operation in October 1963. Future supplemental 
recreation development remain to be designed and constructed. 
Local cooperation. Section 2, Flood Control Act of 
1938, applies. 
Operations during fiscal year. Visitation for FY 1983 
was 586,100 visitor days. Maintenance: Activities consisted 
of road resurfacing and relocation and ordinary 
operation and maintenance. 
21. RATHBUN LAKE, CHARITON 
RIVER, IA 
Location. Damsite is on Chariton River about 7 miles 
north of Centerville and 1 mile north of town of 
Rathbun, Appanoose County, Iowa. 
Existing project. An earthfill dam 10,600 feet long 
constructed to an elevation about 86 feet above valley 
floor, with gated-outlet works and an uncontrolled service 
chute with paved sill spillway about a mile 
upstream from left abutment. Total reservoir storage 
capacity is 552,000 acre-feet (339,000 for flood control, 
24,000 for sediment reserve and 189,000 of multipurpose 
storage for navigation, water quality control, and 
recreation). Initial cost of constructing the project was 
$27,033,210. Total estimated Federal cost of project 
(1983), including $1,871,000 supplemental recreation 
20-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
development (Code 710), is $28,904,210. Construction of 
the project was initiated in September 1964 and completed 
in November 1969. The operating plan for this 
project was revised to reduce flood control releases during 
critical times of the year to allow local farmers bet. 
ter access during planting and harvesting and to 
facilitate field drainage and drying out. The revised plan 
has resulted in more frequent high pool elevations than 
anticipated, which has inundated roads and recreation 
facilities. A shoreline erosion study was accomplished 
and a supplement to the master plan has been approved 
recommending relocation of recreation facilities and 
bank stabilization affected by the higher lake levels. 
Future supplemental recreation facilities remain to be 
designed and constructed. 
Local cooperation. Section 2, Flood Control Act of 
1938, applies. 
Operations during fiscal year. Visitation for FY 1983 
was 865,700 visitor days. Supplemental recreation 
development this FY consisted of preparation of award 
of contract for construction of the Bridgeview shower 
building. Maintenance: Activities included continuation 
of a cultural resource survey, relocation of recreation 
facilities, bank stabilization in recreation areas and ordinary 
operation and maintenance activities. 
22. SMITHVILLE LAKE, LITTLE 
PLATTE RIVER, MO 
Location. Damsite is on Little Platte River about 1 
mile northeast of Smithville and about 5 miles north of 
Kansas City, in Clay and Clinton Counties, Missouri. 
Existing project. Earthfill dam about 4,200 feet long 
and 95 feet high with an uncontrolled service spillway. 
A dike about 2,400 feet long crosses a saddle in left 
abutment. Total reservoir storage capacity is 246,500 
acre-feet (92,000 for flood control, 52,300 for sediment 
reserve, and 102,200 of multipurpose storage for water 
supply, water quality control, and recreation). 
Estimated Federal cost (1983) through construction of 
the project is $86,458,000. Construction was initiated in 
November 1973 and the project was placed in operation 
in March 1982. 
Local cooperation. Section 2, Flood Control Act of 
June 28, 1938, applies. Reimbursement of $24,000,000 
will be required for water supply storage in accordance 
with Water Supply Act of 1958 and reimbursement of 
$7,500,000 will be required for recreation development 
in accordance with Federal Water Project Recreation 
Act of 1965. Additional non-Federal contribution for 
recreation amounts to $600,000. All contracts for local 
cooperation were approved by the Secretary of the Army 
on November 27, 1972. 
Operations during fiscal year. Visitation for FY 1983 
was 1,555,300 visitor days. Project is 98 percent complete. 
Land acquisition, relocations and recreation 
facilities. Project is complete except for administrative 
facilities. Maintenance: Activities consisted of ordinary 
operation and maintenance. 
23. TUTTLE CREEK LAKE, BIG 
BLUE RIVER, KS 
Location. Dam is on main stem of Big Blue River, 
about 12 miles above mouth of stream in Riley and Pottawatomie 
Counties, Kansas. Site is about 12 miles 
northwest of Manhattan, Kansas. 
Existing project. An earth and rock dam 7,500 feet 
long and 157 feet high. Total reservoir storage capacity 
is 2,346,000 acre-feet (1,933,000 for flood control, 
228,000 for sediment reserve and 185,000 for multipurpose 
storage, for low flow regulation, navigation, and 
recreation). Initial cost of constructing the completed 
project was $80,051,031. Total estimated Federal cost 
of project (1983), including $533,048 supplemental 
recreational development (Code 710), is $80,584,079. 
Construction began in October 1952. Project was placed 
in operation in July 1962. 
Local cooperation. Section 2, Flood Control Act of 
1938, applies. 
Operations during fiscal year. Visitation for FY 1983 
was 949,200 visitor days. Maintenance: Activity included 
seismic reevaluation, boundary monumentation and 
ordinary operation and maintenance. 
24. WILSON LAKE, SALINE RIVER, KS 
Location. Dam is on Saline River about 130 miles 
above its mouth, near eastern edge of Russell County, 
Kansas, about 50 miles west of Salina, 10 miles north of 
Wilson, and 20 miles east of Russell, Kansas. 
Existing project. An earthflll dam about 5,600 feet 
long and 160 feet high with a gated-outlet works, chute 
spillway, and structural provision for irrigation. Total 
reservoir storage capacity is 776,000 acre-feet (511,000 
for flood control, 40,000 for sediment reserve and 
225,000 multipurpose storage for irrigation, navigation, 
and low flow regulation). Initial cost of constructing the 
project was $20,015,023. Total estimated Federal cost 
of project (1983), including $848,000 supplemental 
recreational development (Code 710), is $20,863,023. 
Construction began in April 1961 and the project was 
placed in operation in December 1964. Future supplemental 
recreation facilities to be designed and constructed. 
Local cooperation. Section 2, Flood Control Act of 
1938, applies. 
Operations during fiscal year. Visitation for FY 1983 
was 794,500 visitor days. Maintenance: Activity consisted 
of construction of a wind turbine, modification to 
adminstration building, and ordinary operation and 
maintenance. 
25. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Flood Control Act of June 22, 1963, P.L. 738, and 
subsequent acts require local interests to furnish 
assurances that they will maintain and operate certain 
local protection projects after completion in accordance 
20-8

KANSAS CITY, MO., DISTRICT 
with regulations prescribed by the Secretary of the Army. 
District Engineers are responsible for administration 
of these regulations within boundaries of their 
respective district. (See table 20-L on inspection of completed 
flood control projects.) 
26. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Emergency flood control activities-repair, flood 
fighting, and rescue work (Public Law 99, 84th Congress, 
and Antecedent Legislation). 
Federal cost for period October 1, 1981 thru 
September 30, 1982 for operations under this heading 
were as follows: 
Disaster Preparedness Program, including planning, 
training, inspection, supplies and equipment and personnel 
cost: $221,241. 
Flood Fighting and Rescue Work, for four major flood 
events on the Missouri River and tributaries: $294,960. 
Rehabilitation of both non-federal farm levees, and 
federal authorized levees and control works damaged as 
a direct result of flooding: $1,170,284. 
Emergency Bank Protection (Sec. 14,1946 Flood Control 
Act, Public Law 526, 79th Cong., July 24, 1946) as 
amended. 
Operations during this period under this heading were 
as follows: 
Big Blue River, Seward County, Nebraska-Construction 
was completed on a project to provide protection of 
a church camp building, Methodist Church Nebraska 
Annual Conference. Costs for the period was $23,422. 
Cross Creek, Rossville, Kansas-Design underway 
with plans and specifications being prepared for protection 
of sewage lift station, City of Rossville, Kansas. 
Costs for the period were $5,004. 
Weldon Fork River, Mercer County, Missouri- 
Design completed and plans and specifications prepared 
and construction initiated for protection of a county 
road bridge in Mercer County, Missouri. Costs for the 
period were $20,461. 
Snagging and Clearing (Sec. 208, 1954 Flood Control 
Act, Public Law 780, 83d Cong.) 3 September 1954, as 
mended. 
No operations during this period. 
Small Flood Control Projects Not Specifically 
Authorized by Congress (Sec. 205, 1948 Flood Control 
Act, Public Law 858, 80th Cong., June 30, 1948) as 
amended. 
Funds were expended for the following Section 205 
projects during FY 1983: Carrollton, Missouri, $7,296; 
Cross Creek, Rossville, Kansas, $39,717; Elk Creek, 
Clyde, Kansas, $65,671. See detailed report for operation 
at Gypsum, Kansas. 
Multiple Purpose Projects 
Including Power 
27. HARRY S. TRUMAN DAM AND 
RESERVOIR, OSAGE RIVER, MO 
Location. Damsite is on main stem of Osage River 
about 1.5 miles northwest of Warsaw, Benton County, 
Missouri. Reservoir extends into Bates, Henry, 
Hickory, St. Clair, and Vernon Counties, Missouri. 
Existing project. An earthfill dam about 5,000 feet 
long constructed to an average height of about 96 feet, 
including a gate-controlled overfall spillway section and 
a power installation consisting of six inclined pumpgenerating 
units with total capacity of 160,000 
kilowatts. Total reservoir storage capacity is 5,202,000 
acre-feet (3,918,000 for flood control, 244,000 for sediment 
reserve, and 1,040,000 multipurpose storage for 
power, low-flow regulation, and recreation). Public Law 
91-267, approved May 26, 1970, authorized a change in 
project name from Kaysinger Bluff Dam and Reservoir, 
Osage River Basin, Missouri to the Harry S. Truman 
Dam and Reservoir. Estimated cost (1983) is $544 
million. Construction of relocation of Missouri Highway 
M-13 was initiated September 1964 and completed May 
1966. Construction of the dam and reservoir was initiated 
in October 1964. The embankment has been completed 
including paving the top of the dam roadway. 
The spillway was completed in October 1979. The 
Southwestern Power Admimistration powerline needed 
for final testing and commercial operation of the 
generators was completed in December 1979. The first 
power unit was placed on line on 22 December 1979. 
Subsequent problems with the turbine bearing required 
remedial design on the bearing. Restricted commercial 
power production began in April 1982. Through 
September 1983, power generation totaled 623,095,800 
kilowatt hours. Of the gross income from the sale of 
power by Southwestern Power Administration, 
$3,468,046 was allocated to the Corps of Engineers for 
project power operating costs, interest, investment 
recovery. 
Local cooperation. Section 2, Flood Control Act of 
1938 applies. 
Operation during fiscal year. Visitation for FY 1983 
was 1,999,000 visitor days. Work was continued on acquisition 
of land and rights-of-way; relocation of roads, 
utilities and municipal facilities; reservoir clearing; 
boundary surveying and marking; construction of the 
powerplant; and construction of public use facilities. 
Construction of measures to protect downstream areas 
from power operation were continued. Project is 91 percent 
complete. During FY 1983 309,828,000 kilowatthours 
of electrical power were generated. Maintenance: 
Activities consisted of ordinary operation and 
maintenance. 
28. STOCKTON LAKE, SAC RIVER, MO 
Location. Damsite is on Sac River about 49.5 miles 
above its confluence with Osage River, and about 2 
miles east of Stockton, Cedar County, Missouri, lake extending 
into Dade and Polk Counties. 
20-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Existing project. A rock-shell dam with impervious 
core about 5,100 feet long constructed to an average 
height of about 128 feet, with a gated overfall spillway 
and a 45,200-kilowatt power installation. Total reservoir 
storage capacity is 1,674,000 acre-feet (774,000 for flood 
control, 25,000 for sediment reserve and 875,000 
multipurpose storage for power and recreation). Initial 
cost of constructing the completed project was 
$75,628,300. Estimated cost of the project, including 
$3,466,700 for downstream channel work and 
$1,152,000 for supplemental recreational development 
(Code 710), is $80,247,000 (1983). Construction was initiated 
in October 1963 and the project was placed in 
operation in December 1969. Power operation problems 
were encountered with the initial operation in March 
1973 because the downstream channel did not have the 
capacity which earlier observations and computations 
indicated. As a result, it has been necessary to restrict 
the power operation to about the 30,000 kilowatt level. 
Remaining work consists of completion of protection 
from power operation downstream to Caplinger Mills. 
Right-of-way for construction of a channel cutoff and 
bridge at Horseshoe Bend has been acquired and a contract 
for construction has been awarded and work is 
underway. Acquisition of the remaining sloughing 
easements downstream to Caplinger Mills is underway. 
Completion will assure downstream channel capacity to 
Caplinger Mills of 8,000 c.f.s. for powerplant operation. 
Discharge in this range will accommodate power operations 
at a 39,500 kilowatt level. Through September 
1983 power generation totaled 544,846,800 kilowatthours. 
Of the gross income from the sale of power by 
Southwestern Power Administration, $11,389,443 was 
allocated to the Corps of Engineers for project operating 
costs, interest, investment recovery. 
Local cooperation. Section 2, Flood Control Act of 
1938, applies. 
Operations during fiscal year. Visitation for FY 1983 
was 1,789,400 visitor days. The project is complete and 
in operational status. Construction right-of-way was obtained 
for downstream channel cutoff and bridge and 
construction initiated: Acquisition of sloughing 
easements downstream to Caplinger Mills was initiated. 
The net amount of power marketed with Southwestern 
Power Administration was 76,201,000 kilowatt-hours. 
Maintenance: Activities consisted of initiation of Cedar 
Ridge PUA renovation and ordinary operation and 
maintenance. 
General Investigations 
29. GENERAL INVESTIGATIONS 
Fiscal year 1983 costs totaled $1,069,886 for all 
General Investigation activities. See Table 20-M which 
covers Surveys, Collection and Study of Basic Data, 
Research and Development, Continuation of Planning 
and Engineering, Planning and Engineering under Proposed 
Program Legislation, and Advance Engineering 
and Design. 
20-10

TABLE 20-A 
KANSAS CITY, MO., DISTRICT 
COST AND FINANCIAL STATEMENT 
See 
Section 
in Text Project 
Missouri River, 
Sioux City, Iowa 
to Mouth (Rulo, 
Nebr., to Mouth) 
(Federal Funds) 
(Contributed 
Funds) 
(Consolidated 
Summary) 
3. Blue River Channel 
Kansas City, 
Mo. 
4. Clinton Lake, 
Wakarusa 
River, Kans. 
(Contributed 
Funds) 
(Consolidated 
Summary) 
5. Gypsum, Gypsum 
Creek, Kans. 
(Contributed 
Funds) 
(Consolidated 
Summary) 
6. Harlan County 
Lake, Republican 
River, Nebr. 
7. Hillsdale Lake, 
Big Bull 
Creek, Kans. 
1. 
Total Cost to 
Funding FY 80 FY 81 FY 82 FY 83 Sept. 30, 1983 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
32,253 
1,348,000 
1,909,672 
5,841,500 
5,897,687 
695,000 
710,532 
923,033 
1,916,752 
574,500 
574,381 
923,033 
1,916,752 
310,000 
678,681 
125,574 
310,000 
804,255 
15,984 
274,019 
876,000 
849,000 
33,587 
6,401,400 
6,401,102 
839,000 
882,756 
773,000 
758,487 
853,700 
853,482 
-
- 
773,000 
758,587 
-54,000 
67,801 
-10,835 
-54,000 
56,966 
900 
10,174 
1,431,300 
1,376,607 
12,550,000 7,891,000 
13,339,102 6,850,206 
-... - 
1,348,000 
1,909,672 
5,841,500 
5,897,687 
2011 
1,334 
6,401,400 
6,401,102 
- 237,942,1901 
- 237,942,1901 
5,157,500 6,098,600 251,690,814 , ' 
4,797,635 6,380,386 251,584,1142, ' 
- - 816,190 
- - 816,190 
- - 22,642 
- - 22,642 
- - 238,758,380$ 
- - 238,758,380' 
5,157,500 6,098,600 251,713,456' ' 
4,797,635 6,380,386 251,606,7564 ' 
300,000 8,200,000 11,945,171 
244,266 170,989 3,852,873 
1,628,000 - 57,521,533 
872,952 540,171 57,266,807 
951,500 1,114,900 3,831,300 
952,396 1,112,529 3,825,983 
- - 118,805 
- - 118,805 
1,628,000 - 57,640,338 
872,952 540,171 57,385,612 
104,000 -44,000 2,645,952 
55,213 5,132 2,645,952 
- - 130,841 
16,102 - 130,841 
104,000 -44,000 2,776,793 
71,315 5,132 2,776,793 
174,000 -26,000 47,119,9266 
41,942 98,058 47,111,926 
1,000,400 1,594,000 13,638,961' 
1,077,446 1,572,440 13,600,355' 
- - 1,017,623 
- - 1,017,623 
3,355,000 1,900,000 63,981,800 
4,089,541 2,115,958 63,803,223 
349,500 445,300 794,800 
348,860 445,047 793,907

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 20-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section 
in Text Project 
8. Kanopolis Lake, 
Smoky Hill 
River, Kans. 
9. Kansas City, 
Kansas River, 
Kans. (62 Mod.) 
10. Lawrence, Kansas 
River, Kans. 
(Contributed 
Funds) 
(Consolidated 
Summary) 
11. Little Blue River 
Channel Improvement, 
Little Blue 
River, Mo. 
12. Little Blue River 
Lakes, Little Blue 
River, Mo. 
(Contributed 
Funds) 
(Consolidated 
Summary) 
13. Long Branch Lake 
Little Chariton 
River, Mo. 
(Contributed 
Funds) 
(Consolidated 
Summary) 
14. Melvern Lake, 
Osage (Marais des 
Cygnes) River, 
Kans. 
15. Milford Lake, 
Republican River, 
Kans. 
16. Missouri River 
Levee System, 
Iowa, Nebr., 
Kans., and Mo. 
Total Cost to 
Funding FY 80 FY 81 FY 82 FY 83 Sept. 30, 1983 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
39,000 
38,996 
732,200 
730,683 
90,000 
26,056 
105,000 
160,732 
20,010 
35,988 
125,010 
196,720 
1,522,000 
1,647,911 
4 
945,400 
958,933 
-1,653 
- 
10,056 
8,403 
2,259,000 
520,777 
11,557,000 18,280,000 21,243,000 
10,893,293 17,972,213 18,968,228 
- - 892,500 
225,000 35,000 97,475 
11,557,000 18,280,000 21,243,000 
11,118,293 18,007,213 19,003,228 
-158,000 -100,000 350,000 
-141,460 490,325 279,820 
255,500 317,100 341,100 
253,633 314,949 345,045 
321,014 197,874 17,566 
321,014 128,311 39,966 
163,014 97,874 367,566 
179,554 618,636 319,786 
-24,280 
26,019 
682,500 
676,941 
311,000 
89,926 
1,329,000 
1,302,600 
4,552,000 
3,907,735 
500 
825,000 
822,987 
-111,900 
278,876 
1,473,300 
1,488,610 
1,747,000 
1,873,014 
937,138 
946,783 
15,000 
28,014 
1,067,700 
1,077,854 
656,000 
955,769 
1,533,400 
1,530,989 
47,161 
19,123 
63,663 
548,000 
538,020 
78,000 
438,092 
135,000 
101,847 
37,415 
11,722 
172,415 
113,569 
2,429,967 
3,341,757 
12,577,2276 
12,577,2276 
9,759,810' 
9,752,367' 
25,036,600 
24,983,438 
8,636,111 
8,636,111 
136,616 
136,616 
8,772,727 
8,772,727 
21,525,083 
21,465,153 
17,795,000 98,803,200 
18,471,209 96,107,124 
- 1,187,500 
268,645 626,120 
17,500,000 98,803,200 
18,176,209 96,107,124 
275,000 17,685,577 
328,345 17,554,307 
433,100 1,469,700 
431,597 1,467,584 
-4,682 531,77211 
6,056 495,34712 
270,318 18,217,34918 
334,401 18,049,6542 
- 37,436,530 
- 37,436,530 
914,400 7,498,698' 
916,835 7,494,723' 
26,000 49,566,492 
10,995 49,550,687 
1,193,300 11,472,324' 
1,201,212 11,464,852' 
320,000 55,594,851 
569,816 55,576,426 
20-12 
19,123 
63,663 
2,300,000 
4,095,833

KANSAS CITY, MO., DISTRICT 
TABLE 20-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section 
in Text Project 
17. Perry Lake, 
Delaware River, 
Kans. 
18. Pick-Sloan Mo. 
Basin Program 
19. Pomme de Terre 
Lake, Pomme de 
Terre River, Mo. 
20. Pomona Lake, One 
Hundred Ten Mile 
Creek, Kans. 
21. Rathbun Lake, 
Chariton River, 
Iowa 
22. Smithville Lake, 
Little Platte 
River, Mo. 
23. Tuttle Creek Lake, 
Big Blue 
River, Kans. 
24. Wilson Lake, 
Saline River, 
Kans. 
25. Inspection of 
Completed Flood 
Control Projects 
27. Harry S.Truman 
Dam & Reservoir 
Osage River, Mo. 
Funding 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Total Cost to 
FY 80 FY 81 FY 82 FY 83 Sept. 30, 1983 
75,408 
944,000 
938,548 
140,500 
142,302 
-13,000 
190,195 
1,125,000 
1,121,864 
-2,984 
705,000 
705,797 
830,000 
811,000 
8,965,000 
9,649,068 
361,000 
359,141 
862,500 
815,593 
- 
553,500 
555,558 
228,500 
228,456 
34,048,000 
34,374,314 
1,785,500 
1,761,331 
-11,000 
4,508 
1,502,500 
1,415,974 
145,000 
145,514 
1,000 
9,045 
1,271,200 
1,275,130 
1,000 
1,000 
895,700 
886,503 
1,119,900 
1,064,023 
3,580,000 
3,356,263 
426,000 
425,787 
220,000 
52,215 
774,300 
826,742 
381,000 
97,922 
672,500 
658,408 
308,000 
308,158 
28,970,000 
28,625,025 
2,587,800 
2,571,700 
-24,340 
1,156,100 
1,252,008 
- 
164,000 
165,340 
54,417 
54,417 
1,004,200 
1,006,162 
5,000 
4,735 
952,100 
962,341 
69,000 
56,439 
1,074,800 
1,133,069 
2,963,000 
1,437,562 
569,900 
566,805 
-13,389 
154,395 
673,500 
688,167 
-27,028 
256,050 
746,600 
758,161 
241,000 
241,170 
14,500,000 
13,549,322 
2,928,600 
2,935,717 
-26,000 
1,285,600 
1,288,440 
- 
149,000 
149,401 
1,630,600 
1,621,547 
265 
1,304,000 
1,296,852 
441,000 
101,859 
2,019,300 
1,734,316 
357,877 
1,476,459 
584,800 
589,584 
1,198,900 
1,194,485 
-
- 
1,257,600 
1,246,720 
300,000 
299,731 
14,923,000 
12,929,266 
3,834,200 
3,836,394 
49,095,918 
49,095,918 
11,367,684' 
11,367,434' 
55,5697 
55,5697 
4,484,6238 
4,483,2778 
17,350,452 
17,350,452 
12,127,612' 
12,116,328' 
14,003,238 
14,003,238 
10,061,933' 
10,048,407', 10 
27,637,159 
27,285,457 
10,388,418' 
10,083,425' 
86,458,315 
85,543,065 
2,150,500 
2,149,599 
80,584,079 
80,584,079 
11,347,179' 
11,337,784' 
20,463,367 
20,463,367 
8,261,846' 
8,244,739' 
2,939,975 
2,939,706 
499,864,900 
495,403,163 
11,818,000 
11,784,060 
20-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 20-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 80 FY 81 FY 82 FY 83 Sept. 30, 1983 
28. Stockton Lake, New Work: 
Sac River, Mo. Approp. -960,000 432,000 - 2,820,000 79,822,357 
Cost 50,990 55,878 370,441 1,276,067 78,260,328 
Maint. 
Approp. 1,478,500 1,825,100 1,483,800 1,786,300 14,770,600' 
Cost 1,478,509 1,768,669 1,542,330 1,789,410 14,758,157' 
1. Includes $8,665,594 costs of new work for previous 8. Covers 96X3123 operation and maintenance, general 
2. Includes $738,109 for maintenance of previous project. Operations.' 
3. Includes $8,665,594 for new work for previous project 9. Includes funds from Maintenance and Operation of 
and $816,190 from contributed funds. Dams and Other Improvements of Navigable Waters ap- 
4. Includes $738,190 for maintenance of previous project propriation for FY 1979. 
$22,642 from contributed funds and $200,000 Fiscal Year 10. Reflects $10 expenditure of undelivered order after 
1968 Supplemental Appropriation Funds. close of 1978 cost records. 
5. Excludes cost of materials furnished without charge in 11. Correct total is $527,091, which includes $31,664 inthe 
amount of $24,198. terest during construction. Correction pending. 
6. Excludes cost of materials furnished without charge in 12. Unable to verify. 
the amount of $7,885. 13. Overstated by $4,681. Correction pending. 
7. Covers 96X3122 construction, general, funds allotted 
to the 'Republican River Basin Reservoirs (Medicine Creek 
Reservoir) CO, NE and KS.' 
TABLE 20-B AUTHORIZING LEGISLATION 
See Section Date of 
in Text Act Project and Work Authorized Documents 
MISSOURI RIVER, SIOUX CITY, IA TO 
MOUTH (RULO, NE, TO MOUTH) 
July 25, 1912 
Aug. 8, 1917 
Mar. 3, 1925 
Jan. 12, 1927 
July 3, 1930 
Aug. 30, 1935 
Mar. 2, 1945 
Project adopted for securing a permanent navigable 
channel of 6-foot depth from Kansas City, MO to 
mouth. 
Fixed upstream limit of improvement at upper 
end of Quindaro Bend (374.8 miles from mouth) and 
provided for dredging. 
For a minimum width of 200 feet, with a reasonable 
additional width around bends. 
Appropriation of $12 million authorized for existing 
project. 
Appropriation of $15 million additional authorized; 
additional allotments totaling $29,153,108 were 
made by Public Works Administration under provisions 
of National Industrial Recovery Act of 1938, 
and $9,669,791 allotted under provisions of 
Emergency Relief Appropriation Act of 1935. 
Completion of improvement from mouth to Sioux 
City, Iowa. 
Securing a navigable channel of 9-foot depth and 
a minimum width of 300 feet. 
H. Doc. 1287, 61st Cong., 
3d sess. (contains latest 
published map). 
P.L. 241-62 
H. Doc. 463, 64th Cong., 
1st sess. (contains latest 
published map). 
P.L. 585-68 
H. Doc. 1120, 60th Cong., 
2d sess. P.L. 560-70. 
H. Doc. 238, 73d Cong., 
2d sess. (contains latest 
published map). 
H. Doc. 214, 76th Cong., 
1st sess. (contains latest 
published map) 
P.L. 14-79. 
20-14 
1.

KANSAS CITY, MO., DISTRICT 
TABLE 20-B (Continued) AUTHORIZING LEGISLATION 
See Section Date of 
in Text Act Project and Work Authorized Documents 
2. 
3. 
Dec. 31, 1970 
Dec. 31, 1970 
Oct. 23, 1962 
June 30, 1948 
June 28, 1938 
Aug. 18, 1941 
Dec. 22, 1944 
Sep. 3, 1954 
June 28, 1938 
Aug. 18, 1941 
Dec. 22, 1944 
Oct. 23, 1962 
Sep. 3, 1954 
20-15 
BLUE RIVER BASIN (KANSAS CITY DISTRICT) 
Adopted plan for Blue River Basin and authorized 
$40,000,000 for initiation and partial 
accomplishment. 
BLUE RIVER CHANNEL, KANSAS CITY, MO 
Adopted plan for Blue River Basin and authorized 
$40,000,000 for initiation and partial 
accomplishment. 
CLINTON LAKE, WAKARUSA RIVER, KS 
The project for the Kansas River, KS, NE, and CO 
is authorized at an estimated cost of $88,070,000. 
GYPSUM, GYPSUM CREEK, KS 
Authorized construction of small floodcontrol projects 
not specifically authorized by Congress. 
HARLAN COUNTY LAKE, REPUBLICAN 
RIVER, NE 
Adopted general comprehensive plan for Missouri 
River Basin and authorized $9 million for initiation 
and partial accomplishment. 
Modified general comprehensive plan to include Harlan 
County Dam and Reservoir on Republican River, NE, 
other supplemental flood control works on upper 
Republican River, and authorized $7 million additional 
expenditure. 
Expanded general comprehensive plan for Missouri 
River Basin and authorized $200 million additional 
expenditure. 
HILLSDALE LAKE, BIG BULL CREEK, KS 
The comprehensive plan for the Missouri River Basin, 
approved by the Act of June 28, 1938, and as 
amended and supplemented is further modified to 
include the project for flood protection on the Kansas 
River and tributaries. It is further modified to include 
the project for flood protection on the Osage River 
and tributaries. 
KANOPOLIS LAKE, SMOKY HILL RIVER, KS 
Adopted general comprehensive plan for Missouri 
River Basin and authorized $9 million for initiation 
and partial accomplishment. 
Modified general comprehensive plan to include Harlan 
County Dam and Reservoir on Republican River, NE, 
other supplemental flood control works on upper 
Republican River, and authorized $7 million additional 
expenditure. 
Expanded general comprehensive plan for Missouri 
River Basin and authorized $200 million additional 
expenditure. 
KANSAS CITY, KANSAS RIVER, KS (1962 MOD.) 
The project for the Kansas River, Kansas, Nebraska, d 
and Colorado, is authorized at an estimated cost 
of $88,070,000. 
LAWRENCE, KANSAS RIVER, KS 
Expanded general comprehensive plan for Missouri 
River Basin and authorized $217,710,000 
additional expenditure. 
H. Doc. 91-332, 
91st Cong., 2d sess. 
P.L. 91-611. 
H. Doc. 91-332, 
91st Cong., 2d sess. 
1962 Flood Control Act 
S. Doc 122, H. Doc. 578, 
87th Cong., 2d sess., 
P.L. 87-874. 
Section 205, 1948 Flood 
Control Act, P.L. 858. 
Flood Control Committee 
Doc. 1, 75th Cong., 
1st sess., P.L. 761. 
H. Doc. 842, 76th Cong., 
3d sess., P.L. 228. 
H. Doc. 475 and S. Docs. 
191 and 247, 78th 
Cong., 2d sess., 
P.L. 534. 
P.L. 780, 83rd Cong., 
2d sess. 
Flood Control Committee 
Doc. 1, 75th Cong., 
1st sess., P.L. 761. 
H. Doc. 842, 76th Cong., 
3d sess., P.L. 228. 
H. Doc. 475 and S. Docs. 
191 and 247, 78th 
Cong., 2d sess., 
P.L. 534. 
1962 Flood Control Act 
S. Doc. 122, 87th Cong. 
2d sess., P.L. 87-874. 
H. Docs. 642,5491, and 
561, 81st Cong., 2d sess. 
P.L. 780. 
5. 
6. 
7. 
8. 
9. 
10.

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 20-B AUTHORIZING LEGISLATION 
See Section Date of 
in Text Act Project and Work Authorized Documents 
11. 
12. 
Sept. 3, 1954 
June 28, 1938 
Aug. 18, 1941 
Dec. 22, 1944 
July 24, 1946 
May 17, 1950 
Sept. 3, 1954 
Aug. 13, 1968 
Aug. 13, 1968 
Oct. 27, 1965 
Sep. 3, 1954 
Sep. 3, 1954 
Aug. 18, 1941 
Dec. 22, 1944 
13. 
20-16 
LITTLE BLUE RIVER CHANNEL 
Additional $38,000,000 for prosecution of general 
comprehensive plan for Missouri River Basin. 
LITTLE BLUE RIVER LAKES, MO 
Additional $38,000,000 for prosecution of general 
comprehensive plan for Missouri River Basin. 
LONG BRANCH LAKE, LITTLE CHARITON 
RIVER, MO 
The project for flood protection on the Chariton and 
Little Chariton Rivers and tributaries, Iowa and Missouri, 
is authorized at an estimated cost of 89,167,000. 
MELVERN LAKE, MARAIS DES CYGNES (OSAGE) 
RIVER, KS 
Expanded general comprehensive plan for Missouri 
River Basin and authorized $217,710,000 
additional expenditure. 
MILFORD LAKE, REPUBLICAN RIVER, KS 
Expanded general comprehensive plan for Missouri 
River Basin and authorized $217,710,000 
additional expenditure. 
MISSOURI RIVER LEVEE SYSTEM, IA, NE, KS, 
AND MO 
Levees along both sides of river from Sioux City 
to Kansas City. 
Extended project from Kansas City to the mouth 
provided for increased protection. 
PERRY LAKE, DELAWARE RIVER, KS 
Expanded general comprehensive plan for Missouri 
River Basin and authorized $217,710,000 
additional expenditure. 
PICK-SLOAN MISSOURI BASIN PROGRAM 
(KANSAS CITY DIST.) 
Adopted general comprehensive plan for Missouri 
River Basin and authorized 89 million for initiation 
and partial accomplishment. 
Modified general comprehensive plan to include Harlan 
County Dam and Reservoir on Republican River, NE, 
other supplemental flood control works on upper 
Republican River, and authorized $7 million 
additional expenditure. 
Expanded general comprehensive plan for Missouri 
River Basin and authorized $200 million 
additional expenditure. 
Additional expenditure of $150 million for prosecution 
of general comprehensive plan for Missouri River 
Basin. 
Additional expenditure of $250 million for prosecution 
of general comprehensive plan for Missouri River 
Basin. 
Expanded general comprehensive plan for Missouri 
River Basin and authorized $217,710,000 
additional expenditure. 
P.L. 90-483 (H. Doc. 169, 
90th Cong., 1st sess. 
P.L. 90-483 (H. Doc. 169, 
90th Cong., 1st sess. 
1965 Flood Control Act, 
P.L. 89-298, (H. Doc. 
238 & 262, 89th Cong., 
1st sess.) 
H. Docs. 642, 5491, and 
561, 81st Cong., 
2d sess. P.L. 780. 
H. Docs. 642, 5491, and 
561, 81st Cong., 
2d sess. P.L. 780. 
H. Doc. 821, 76th Cong., 
3d sess. 
H. Doc. 475 and S. Docs. 
191 and 347, 78th 
Cong., 2d sess. 
H. Docs. 642, 5491, and 
561, 81st Cong., 
2d sess. P.L. 780. 
Flood Control Committee 
Doc. 1, 75th Cong., 
1st sess. 
H. Doc. 842, 76th Cong., 
3d sess. 
H. Doc. 475 and S. Docs. 
191 and 247, 78th 
Cong., 2d sess. 
H. Docs. 642 and 5491 
81st Cong., 2d sess. 
14. 
15. 
16. 
17. 
18.

KANSAS CITY, MO., DISTRICT 
TABLE 20-B (Continued) AUTHORIZING LEGISLATION 
See Section Date of 
in Text Act Project and Work Authorized Documents 
May 2, 1956 
July 3, 1958 
July 14, 1960 
Dec. 30, 1963 
June 18, 1965 
May 12, 1967 
Aug. 13, 1968 
Dec. 24, 1970 
Dec. 23, 1971 
Mar. 7, 1974 
June 28, 1938 
Dec. 22, 1944 
Sep. 3, 1954 
Sept. 3, 1954 
Sept. 3, 1954 
Oct. 27, 1965 
Modified general comprehensive plan for Missouri River 
Basin by deletion of construction of Red Willow Dam 
and Reservoir, NE, and addition of construction of 
Wilson Dam and Reservoir, KS. 
Expanded general comprehensive plan for Missouri 
River Basin and authorized $200 million 
additional expenditure. 
Additional expenditure of $207 million for prosecution 
of general comprehensive plan for Missouri River 
Basin. 
Additional expenditure of $80 million for prosecution of 
general comprehensive plan for Missouri River Basin 
and modified plan to include bank protection or 
rectification works below Garrison Dam. 
Additional $116 million for prosecution of general 
comprehensive plan for Missouri River Basin. 
Additional $20 million for prosecution of general 
comprehensive plan for Missouri River Basin. 
Additional $38,000,000 for prosecution of general 
comprehensive plan for Missouri River Basin. 
Change comprehensive plan name to Pick-Sloan 
Missouri Basin program. 
Additional $101,000,000 for prosecution of general 
comprehensive plan for Pick-Sloan Missouri 
Basin program. 
Additional $72,000,000 for prosecution of general 
comprehensive plan for Pick-Sloan Missouri 
Basin program. 
POMME DE TERRE LAKE, POMME DE TERRE 
RIVER, MO 
Adopted general comprehensive plan for Missouri 
River Basin and authorized $9 million for initiation 
and partial accomplishment. 
Expanded general comprehensive plan for Missouri 
River Basin and authorized $200 million 
additional expenditure. 
Expanded general comprehensive plan for Missouri 
River Basin and authorized $217,710,000 
additional expenditure. 
POMONA LAKE, ONE HUNDRED TEN 
MILE CREEK, KS 
Expanded general comprehensive plan for Missouri 
River Basin and authorized $217,710,000 
additional expenditure. 
RATHBUN LAKE, CHARITON RIVER, IA 
Expanded general comprehensive plan for Missouri 
River Basin and authorized $217,710,000 
additional expenditure. 
SMITHVILLE LAKE, LITTLE PLATTE RIVER, MO 
The project for flood protection on the Platte River 
and tributaries, MO and IA is authorized at an 
estimated cost of $26,889,000. 
H. Doc. 409, 84th 
Cong., 2d sess. 
S. Doc. 91-1100, 91st 
Cong., 2d sess. 
S. Doc. 92-222, 92nd 
Cong., 1st sess. 
Flood Control Committee 
Doc. 1, 75th Cong., 
1st sess., P.L. 761. 
H. Doc. 475 and S. Does. 
191 and 247, 78th 
Cong., 2d sess., 
P.L. 534. 
H. Docs. 642, 5491, and 
561, 81st Cong., 
2d sess., P.L. 780. 
H. Docs. 642, 5491, and 
561, 81st Cong., 
2d sess., P.L. 780. 
H. Docs. 642, 5491, and 
561, 81st Cong., 
2d sess., P.L. 780. 
1965 Flood Control Act, 
P.L. 89-298 (H. Docs. 
238 & 262, 89th Cong., 
1st sess.) 
20-17 
19. 
20. 
21. 
22.

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 20-B (Continued) AUTHORIZING LEGISLATION 
See Section Date of 
in Text Act Project and Work Authorized Documents 
TUTTLE CREEK LAKE, BIG BLUE RIVER, KS 
23. June 28, 1938 Adopted general comprehensive plan for Missouri Flood Control Committee 
River Basin and authorized $9 million for initiation Doc. 1, 75th Cong., 
and partial accomplishment. 1st sess. P.L. 761. 
Aug. 18, 1941 Modified general comprehensive plan to include Harlan H. Doc. 842, 76th Cong., 
County Dam and Reservoir on Republican River, NE, 3d sess., P.L. 228 
other supplemental flood control works on upper 
Republican River, and authorized $7 million additional 
expenditure. 
Dec. 22, 1944 Expanded general comprehensive plan for Missouri H. Doc. 475 and S. Docs. 
River Basin and authorized $200 million 191 & 247, 78th Cong., 
additional expenditure. 2d sess., P.L. 534 
WILSON LAKE, SALINE RIVER, KS 
24. Dec. 22, 1944 Expanded general comprehensive plan for Missouri H. Doc. 475 and S. Docs. 
River Basin and authorized $200 million 191 & 247, 78th Cong., 
additional expenditure. 2d sess., P.L. 534 
July 14, 19602 Additional expenditure of $207 million for prosecution S. Doc. 96, 86th Cong. 
of general comprehensive plan for Missouri River P.L. 645. 
Basin. 
HARRY S. TRUMAN DAM AND RESERVOIR, 
OSAGE RIVER, MO 
27. Sept. 3, 1954 Expanded general comprehensive plan for Missouri H. Docs. 642, 5491, and 
River Basin and authorized $217,710,000 561, 81st Cong., 
additional expenditure. 2d sess., P.L. 780. 
Oct. 23, 1962 The Kaysinger Bluff Reservoir is hereby modified in 1962 Flood Control Act, 
aEcncgorindeaenrcse with recommendations of the Chief of H. Doc. 578, 87th Cong., in H. Doc. 578, 87th Cong., at an estimated 2d sess., P.L. 87-874. 
additional cost of $43,245,000: provided, that nothing 
in this Act shall be construed as authorizing the 
acquisition of additional lands for the establishment 
of a national wildlife refuge at the reservoir. 
STOCKTON LAKE, SAC RIVER, MO 
28. Sept. 3, 1954 Expanded general comprehensive plan for Missouri H. Docs. 642, 5491, and 
River Basin and authorized $217,710,000 561, 81st Cong., 
additional expenditure. 2d sess., P.L. 780. 
1. Contains latest published maps of Missouri River. 2. Report of Chief of Engineers on justification of Wilson 
Dam and Reservoir, submitted in compliance with Public Law 
505, 84th Congress, published as Senate Document 96, 86th 
Congress, was approved July 14, 1960 (Public Law 645). 
TABLE 20-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost To September 30, 1983 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Fort Leavenworth Bridge removal Complete 1965 270,393 - 
Gasconade River, MO1, 2 Complete 1931 139,003 85,077 
Kansas River Navigation Inactive 1980 259,900 - 
Osage River, MO, lock and dam8 Complete 1952 658,076 850,495 
1. Improvement adequate for existing needs. Project for 
maintenance only. 
2. Curtailment of project in H. Doc. 467, 69th Cong., 1st 
ses8. 
3. Operation of lock and dam placed in standby status. 
20-18

KANSAS CITY, MO., DISTRICT 
TABLE 20-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost To September 30, 1983 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Abilene, KS. Completed 1965 1,099,350 - 
Atchison, KS. Completed 1973 4,099,590 - 
Barnard, KS' Completed - 127,860 - 
Bartley, NE Completed 1953 118,269 - 
Bedford, East Fork, 102 River, IA1 Completed 1974 652,414 - 
Big Blue River, Seward, NE1 Completed - 126,887 - 
Big Stranger Creek, KS' Completed - 337,131 - 
Braymer Lake, Shoal Creek, MO Inactive 1966 - - 
Brookfield Lake, Yellow Creek, MO Inactive 1976 451,400 - 
Chariton-Little Chariton Basin, MO (1965 Act)2 1977 692,706 - 
Chariton River, MO (1944 Act) Completed 1973 8,052,990 - 
Dry Fork and East Fork Lakes, 
Fishing River, MO Deferred 1974 51,989 - 
East Muddy Creek, MO Inactive 1966 - - 
Elk Creek, Clyde, KS Completed 1975 881,415 - 
Fairbury, Little Blue River, NE Completed 1973 726,966 - 
Fort Scott Lake, Marmaton River, KS Active 1976 757,500 - 
Frankfort, Black Vermilion River, KS Completed 1966 1,271,025 - 
Garnett Lake, Pottawatomie Creek, KS Inactive 1973 71,466 - 
Grove Lake, Soldier Creek, KS Inactive 1977 1,754,019 - 
Indian Lake, Blue River, KS Inactive 1976 127,297 - 
Indianola, NE Completed 1950 67,275 - 
Kansas Citys on MO and KS Rivers, 
MO and KS8 1980 42,434,197 - 
Kansas River Navigation Inactive 1980 259,900 - 
Lower Grand River, MO Active 1966 - - 
Manhattan, Kansas River, KS Completed 1967 2,488,585 - 
Mercer Lake, Weldon River, MO Inactive 1976 432,245 - 
Mill Lake, Blue River, MO Deferred 1971 - - 
Missouri River at New Haven, MO1 Completed - 139,883 - 
Onaga Lake, Vermillion Creek, KS Inactive 1982 2,178,261 - 
Osawatomie, Pottawatomie Creek, KS Completed 1973 2,036,624 - 
Ottawa, Osage (Marais des Cygnes) 
River, KS Completed 1966 4,462,661 - 
Pattonsburg Lake, Grand River, MO Inactive 1976 - - 
Pattonsburg Lake, Grand River, MO 
(Advance Highway Relocation) Inactive 1976 390,763- 
Pattonsburg Lake, Grand River, MO 
(Advance Town Relocation) Inactive 1976 91,929 - 
Perry Lake Area (Road Improvements), KS Completed 1982 5,315,168 - 
Platte River, MO, Channel Improvement Deferred 1973 222,193 - 
Rathbun Lake Fish Hatchery Completed 1975 700,000 - 
Salina, Smoky Hill River, KS Completed 1967 3,878,668 - 
Salt Creek, Barnard, KS1 Completed - 127,860 - 
Seward, NE1 Completed - 126,887 - 
Smithville Channel, Little Platte River, MO Deferred 1973 6,896 - 
Stonehouse Creek, Jefferson Co., KS1 Completed 1972 246,995 - 
Tomahawk Lake, Blue River, KS Inactive 1976 77,189 - 
Topeka, Kansas River, KS Completed 1974 21,174,593 - 
Trenton Lake, Thompson River, MO Inactive 1966 - - 
Upper Grand River, MO Inactive 1966 - - 
Wolf-Coffee Lake, Blue River, KS Inactive 1976 1,095,019 - 
1. Authorized by the Chief of Engineers under section 3. The project as a whole is complete except for Turkey 
205, Public Law 858, 80th Congress, as amended. Creek facilities in Central Industrial District Unit. 
2. Little Chariton River (East and Middle Fork) and 
Mussell Fork classified inactive. Construction cost includes 
$481,106 cost of completed Shoal Creek Unit and $211,600 
cost for inactive units, Little Chariton River and Mussell 
Fork. 
20-19

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 20-G DEAUTHORIZED PROJECTS 
For Last 
Full Report Federral Contributed 
See Annual Funds Funds 
Project Report For Date and Authority Expended Expended 
Arlington Lake, MO 1948 Flood Control Act approved 88,651 - 
June 28, 1938, as modified by 
Flood Control Act approved 
August 18, 1941, and expanded 
by Flood Control Act approved 
December 22, 1944 
Beatrice, Big Blue River, NE 1965 Flood Control Act approved 16,317 - 
September 3, 1954 
Hackleman Corners Lake, - Authorized by Flood Control Act - - 
Cedar Creek, MO approved September 3, 1954 
Hays, Big Creek, KSi 1974 Flood Control Act of 1965 499,200 - 
approved October 27, 1965 
Marysville, KS - Flood Control Act of 133,682 - 
September 3, 1954 
Merriam, Turkey Creek, KS 1970 Flood Control Act approved 39,708 - 
September 3, 1954 
Pioneer Lake, KS 1952 Flood Control Act approved 95,692 - 
June 28, 1938, as modified by 
Flood Control Act of August 
18, 1941, and expanded by 
Flood Control Act approved 
December 22, 1944 
Richland Lake, MO 1948 Flood Control Act approved 8,548 - 
June 28, 1938, as modified by 
Flood Control Act approved 
August 18, 1941, and expanded 
by Flood Control Act approved 
December 2, 1944 
1. A study of water supply and flood problems at Hays, 
KS, is being studied under Kansas and Osage Rivers, KS, 
study. 
MISSOURI RIVER, SIOUX CITY IA, TO MOUTH 
(RULO, NE, TO MOUTH) 
TABLE 20-H TOTAL COST OF EXISTING PROJECT 
TO SEPTEMBER 30, 1983 
(See Section 1 of Text) 
Funds New Work Maintenance Total 
Regular $209,732,851 $249,346,663 $459,079,514 
Emergency 2,362,599 190,401 2,553,000 
Public works 17,181,146 114,180 17,295,326 
Accelerated public works - 393,261 393,261 
Maintenance and operation 
of dams and other improvements 
of navigable waters 801,500 801,500 
Total $229,276,596 $250,846,005 $480,122,601 
20-20

KANSAS CITY, MO., DISTRICT 
TABLE 20-I MISSOURI RIVER SIOUX CITY TO MOUTH: 
TERMINAL FACILITIES 
(See Section 1 of Text) 
Miles 
Description of Facility1 Above Bank Nearest Town 
Mouths 
Existing facilities: 
Grain loading dock 
Rock loading dock 
Rock loading dock 
Ramp, gas, and restaurant (fee) 
Sand and gravel unloading dock 
Grain loading dock 
Grain and vegetable oil loading dock 
Chemical unloading 
Rock loading dock 
Fertilizer unloading dock 
Grain loading dock 
Loading dock 
Transfer of materials dock 
Grain loading dock 
Municipal Dock 
Fertilizer unloading and grain loading dock 
Shipyard and dry dock 
Grain loading dock 
Molasses unloading dock 
Material transfer and rock loading dock 
Sand and gravel unloading dock 
Bulk Petroleum Storage 
Loading and unloading dock 
Grain loading dock 
Bulk and Liquid Unloading Dock 
Fertilizer unloading dock 
Grain loading dock 
Loading and unloading dock 
Loading and unloading dock 
Loading and unloading dock 
Scrap steel loading dock 
Sand and gravel unloading dock 
Excursion dock 
Grain loading dock 
Fuel loading dock 
Grain loading dock 
Grain loading dock 
Chemical loading and unloading dock 
Coke loading and unloading dock 
Haydite loading dock 
Sand and gravel unloading dock 
Steel unloading dock 
Oil unloading dock and barge refueling 
Fertilizer unloading dock 
Cement loading dock 
Rock loading dock 
Rock loading dock 
Dock 
Rock loading dock 
Grain loading dock 
Sand and gravel loading dock 
Sand and gravel loading dock 
Grain loading dock 
Grain loading dock 
Sand and gravel unloading dock 
Rock loading dock 
Grain loading dock 
Grain and fertilizer, loading and unloading dock 
Rock loading dock 
Grain loading dock 
488.0 
478.0 
473.6 
452.0 
447.6 
446.6 
446.1 
445.4 
432.8 
423.2 
423.1 
423.0 
421.1 
420.9 
396.1 
396.0 
395.7 
386.5 
386.4 
385.0 
378.3 
376.3 
375.6 
373.0 
372.4 
368.2 
367.7 
367.7 
367.1 
367.1 
366.9 
365.8 
365.6 
364.2 
364.1 
361.6 
361.0 
360.6 
360.4 
360.1 
360.1 
357.6 
356.7 
355.8 
354.8 
350.3 
345.7 
345.3 
333.5 
318.2 
317.9 
317.1 
293.3 
293.0 
286.9 
263.0 
262.7 
256.3 
245.2 
226.4 
Right 
Right 
Right 
Left 
Left 
Left 
Left 
Left 
Right 
Right 
Right 
Right 
Right 
Right 
Right 
Right 
Right 
Right 
Right 
Left 
Left 
Left 
Left 
Right 
Right 
Right 
Right 
Right 
Right 
Right 
Right 
Right 
Right 
Right 
Right 
Left 
Left 
Left 
Left 
Left 
Left 
Right 
Right 
Right 
Right 
Right 
Left 
Left 
Left 
Right 
Right 
Left 
Right 
Right 
Left 
Right 
Right 
Left 
Right 
Left 
White Cloud, KS 
White Cloud, KS 
White Cloud, KS 
St. Joseph, MO 
St. Joseph, MO 
St. Joseph, MO 
St. Joseph, MO 
St. Joseph, MO 
St. Joseph, MO 
Atchison, KS 
Atchison, KS 
Atchison, KS 
Atchison, KS 
Atchison, KS 
Leavenworth, KS 
Leavenworth, KS 
S. Leavenworth, KS 
Wolcott, KS 
Wolcott, KS 
Waldron, MO 
Parkville, MO 
Parkville, MO 
Parkville, MO 
Kansas City, KS 
Kansas City, KS 
Kansas City, KS 
Kansas City, KS 
Kansas City, KS 
Kansas City, MO 
Kansas City, MO 
Kansas City, MO 
Kansas City, MO 
Kansas City, MO 
Kansas City, MO 
Kansas City, MO 
Kansas City, MO 
Randolph, MO 
Randolph, MO 
Randolph, MO 
Randolph, MO 
Randolph, MO 
Sugar Creek, MO 
Sugar Creek, MO 
Sugar Creek, MO 
Sugar Creek, MO 
Sugar Creek, MO 
Missouri City, MO 
Missouri City, MO 
Sibley, MO 
Lexington, MO 
Lexington, MO 
Lexington, MO 
Waverly, MO 
Waverly, MO 
Carrollton, MO 
Miami, MO 
Miami, MO 
Brunswick, MO 
New Franklin, MO 
Glasgow, MO 
20-21

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 20-I (Cont.) MISSOURI RIVER SIOUX CITY TO MOUTH: 
TERMINAL FACILITIES 
(See Section 1 of Text) 
Miles 
Description of Facility1 Above Bank Nearest Town 
Mouth" 
Sand and gravel unloading dock 226.2 Left Glasgow, MO 
Rock loading dock 219.1 Left Glasgow, MO 
Sand, gravel & fertilizer unloading dock 197.0 Right Boonville, MO 
Fertilizer unloading and grain loading dock 196.4 Left Boonville, Mo. 
Loading and unloading dock 196.4 Left Boonville, MO 
Sand and gravel unloading dock 186.3 Left Rocheport, MO 
Rock loading dock 185.5 Left Rocheport, MO 
Sand and gravel unloading dock 181.6 Left Huntsdale, MO 
Rock loading dock 181.6 Left Huntsdale, MO 
Rock loading dock 177.2 Right Lupus, MO 
Rock loading dock 164.2 Right Sandy Hook, MO 
Rock loading dock 157.5 Right Marion, MO 
Oil unloading dock 148.7 Left Jefferson City, MO 
Sand and gravel unloading dock 143.4 Left Jefferson City, MO 
Coal loading dock 143.3 Left Jefferson City, MO 
Rock loading dock 126.2 Right St. Aubert, MO 
Sand and gravel unloading dock 124.5 Left Mokane, MO 
Coal unloading dock 117.1 Right Chamois, MO 
Barge dock 115.5 Left Portland, MO 
Rock loading dock 109.7 Left Portland, MO 
Sand and gravel unloading dock 96.9 Left Hermann, MO 
Rock loading dock 85.3 Left New Haven, MO 
Unloading dock 81.7 Right New Haven, MO 
Sand and gravel unloading dock 68.1 Right Washington, MO 
Rock loading dock 56.1 Left Augusta, MO 
Rock loading dock 47.4 Left Monarch, MO 
Sand and gravel unloading dock 43.9 Right Chesterfield, MO 
Rock loading dock & sand & gravel unloading dock 31.4 Left St. Charles, MO 
Sand, salt and gravel unloading dock 28.1 Right St. Charles, MO 
Sand and gravel unloading dock 27.8 Right St. Charles, MO 
Rock loading dock and gravel unloading dock 16.7 Right Musicks Ferry, MO 
Rock loading dock & sand & gravel unloading dock 8.4 Right Ruegg, MO 
1. Privately owned and operated unless indicated. 2. 1960 adjusted mileage. 
TABLE 20-J MISSOURI RIVER LEVEE SYSTEM 
(See Section 14 of Text) 
Miles of 
Unit Levee Status 
R 513-512 Richardson Co. D. D. #7 19.1 Complete-1958 
R 500 Iowa Point D. D. #4 4.1 Complete-1954 
Kimsey Holly Creek 4.4 Complete-1970 L 497 Forest City L. D. 16.0 Complete-1962 
L 488 Holt Co. D. D. #7 11.5 Complete-1955 
R 482 Burr Oak D. D. 13 8.2 Complete-1954 
L 476 Amazonia L. D. 10.8 Complete-1956 
R 471-460 Elwood-Gladden L. D. 13.8 Complete-1968 
L 455 S. St. Joseph L. D. 15.6 Complete-1967 
L 448-443 Halls L. D. 17.3 Complete-1957 
R 440 Atchison & Doniphan Co. D. D. 10.7 Complete-1959 
L 408 Farley-Beverly D. D. 12.2 Complete (Levee raise modification)-1972 
L 400 Waldron L. D. 7.6 Complete-1957 
L 385 Riverside-Quindaro D. D. 6.5 Planning underway 
R 351 Atherton L. D. 15.9 Complete-1966 
L 345-330 Orrick L. D. 43.4 Planning underway 
L 325-319 Henrietta-Crooked River D. D. 35.0 Planning underway 
L 246 Brunswick-Dalton D. D. 20.0 Complete.- 1983 
Remaining units Detailed planning not initiated 
20-22

KANSAS CITY, MO., DISTRICT 
TABLE 20-K KANSAS CITY DISTRICT PROJECTS INCLUDED IN 
PICK-SLOAN MISSOURI BASIN PROGRAM 
(See Section 18 of Text) 
Estimated Estimated 
Project Federal Non-Federal 
Cost Cost 
Abilene, Smoky Hill River, Kansas $ 1,099,350 $ 287,000 
Bartley, Republican River, Nebraska 118,269 9,500 
Fort Scott Lake, Marmaton River, Kansas5 78,500,000 2,616,000 
Garnett Lake, Pottawatomie Creek, Kansas2 38,600,000 - 
Harlan County Lake, Republican River, Nebraska 49,423,199- 
Harry S. Truman Dam and Reservoir, Osage River, Missouri 543,000,000 126,071,000 
Hillsdale Lake, Big Bull Creek, Kansas 63,981,800 20,260,000 
Indianola, Republican River, Nebraska 67,275 7,592 
Kanopolis Lake, Smoky Hill River, Kansas 13,149,735 - 
Lawrence, Kansas River, Kansas4 8,626,111 2,130,000 
Manhattan, Kansas River, Kansas 2,488,585 265,000 
Melvern Lake, Osage (Marais des Cygnes) River, Kansas 37,436,530- 
Melvern Lake and Pomona Lake (Road Improvement), 
Kansas (1974 Authorization) 500,000 214,300 
Milford Lake, Republican River, Kansas 49,566,843 - 
Missouri River Levee System, Rulo to the Mouth1 157,200,000 16,800,000 
Osawatomie, Osage (Marais des Cygnes) River, Kansas 2,036,624 348,300 
Ottawa, Osage (Marais des Cygnes) River, Kansas 4,462,661 876,000 
Perry Lake, Delaware River, Kansas 49,439,706 - 
Pomme de Terre Lake, Pomme de Terre River, Missouri' 18,643,924 - 
Pomona Lake, Osage River Basin, Kansas 14,815,108 - 
Salina, Smoky Hill River, Kansas 3,878,668 1,960,000 
Stockton Lake, Sac River, Missouri 80,052,000 17,391,000 
Topeka, Kansas River, Kansas 21,174,593 10,383,492 
Tuttle Creek Lake, Big Blue River, Kansas 80,584,079 - 
Tuttle Creek Lake, Kansas-Road and Bridge (1976 Act) 630,000 500,000 
Tuttle Creek Lake (Road Improvement), Kansas 
(1974 Modification) 500,000 214,300 
Wilson Lake, Saline River, Kansas 20,863,023 - 
1. Active portion of project. Deferred portion of project 
is currently estimated to cost (1964) $1,690,000 Federal and 
$122,000 non-Federal. Inactive portion of project is currently 
estimated to cost (1964) $272,408,000 Federal and $23,862,500 
non-Federal. 
2. 1969 Estimate. 
3. Active portion of project. Inactive portion of the 
project for power modification is currently estimated to cost 
(1954) $7,300,000. 
4. 1976 estimate. 
5. 1981 estimate. 
20-23

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 20-L INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
(See Section 25 of Text) 
Location Month Inspected 
Missouri River Main Stem 
Missouri River Levees: R 513-512, R 500, Kimsey Holly Creek, L 497, L 488, 
R 482, L 476, R 471-460, L 455, L 448-443, R 440, L 408, L 400 and R 351, L 246 
Kansas Citys, Missouri and Kansas: Argentine, Armourdale, 
Birmingham, CID (Mo & Kans), East Bottoms, Fairfax-Jersey 
Creek, North Kansas City Units, and GSA Federal Complex 
Osage River, Kansas and Missouri 
Ottawa, Kansas 
Osawatomie, Kansas 
Kansas River and Minor Tributaries 
Topeka, Kansas; Auburndale, North Topeka, Oakland, Soldier 
Creek, South Topeka, and Waterworks Units 
Republican River, Nebraska and Kansas 
Bartley, Nebraska 
Smoky Hill, Saline, and Solomon Rivers 
Abilene, Kansas 
20-24 
Oct-Nov 83 
Oct-Nov 83 
Oct 83 
Oct 83 
Nov 83 
Oct 83 
Sep 83 
U~ 
_ __

TABLE 20-M 
KANSAS CITY, MO., DISTRICT 
ACTIVE GENERAL INVESTIGATIONS 
(See Section 29 of Text) 
TOTAL (Category 100) 
COLLECTION AND STUDY OF BASIC DATA (Category 200) 
Inspection and Inventory of Dams (236) - 53842/3 
Flood Plain Management Services (250) - 82030/40/60 
Hydrologic Studies (260) - 53820 
TOTAL (Category 200) 
RESEARCH AND DEVELOPMENT (Category 300) 
None 
CONTINUATION OF PLANNING AND ENGINEERING 
(Category 400) 
None 
PLANNING AND ENGINEERING UNDER PROPOSED 
LEGISLATION (Category 500) 
None 
ADVANCE ENGINEERING AND DESIGN (Category 600) 
None 
GRAND TOTAL GENERAL INVESTIGATIONS 
Federal Cost 
FY 83 
20-25 
Totals By 
Item and CWIS Number Categories 
SURVEYS (Category 100) 
Flood Damage Prevention Studies (120) 
Kansas and Osage Rivers, Kansas - 12204 
Nemaha and Little Nemaha Rivers and Tributaries, 
Nebraska and Kansas - 12268 
Subtotal 
Review of Authorized Projects (160) 
Fort Scott Lake, Kansas - 06470 
Miscellaneous Activities (170) 
Special Investigations 
FERC Licensing 
Subtotal 
Coordination Studies with Other Agencies (180) 
Soil Conservation Service, Dept. Agric. (181) - 51840 
Bureau of Reclamation, Dept. Interior (182) - 51820 
Missouri River Basin Commission (183) - 50615 
Planning Assistance to States (186) - 51850 
Technical Assistance for Streambank Erosion (188) - 51731 
Subtotal 
$ 887,627 
$ 1,392 
157,907 
22,960 
$ 182,259 
$1,069,886 
$667,495 
1,280 
$668,775 
$ 65,588 
58,382 
5,134 
$ 63,516 
$ 8,516 
40,545 
246 
40,248 
193 
$ 89,748

OMAHA, NE, DISTRICT* 
This district comprises portions of Montana, Wyo- drainage basin of Missouri River along main stem and 
ming, North Dakota, South Dakota, Minnesota, Colo- tributaries to Rulo, NE. 
rado, Nebraska, Iowa, and Missouri, all embraced in 
IMPROVEMENTS 
Navigation Page Multiple Purpose Projects Including Power Page 
1. Missouri River, Sioux City, IA 27. Big Bend Dam-Lake Sharpe, 
to Rulo, NE.........................21-2 Missouri River Basin, SD ................ 21-7 
2. Navigation Work Under Special 28. Fort Peck Lake, MT ..................... 21-7 
Authorization ............................ 21-2 29. Fort Randall Dam-Lake Francis Case, 
Missouri River Basin, SD ................ 21-8 
Flood Control 30. Garrison Dam-Lake Sakakawea, 
3. Bear Creek Lake, CO ...................... 21-2 Missouri River Basin, ND ................ 21-8 
4. Bowman-Haley Lake, ND .................. 21-2 31. Gavins Point Dam-Lewis and Clark Lake, 
5. Chatfield Lake, CO.......................21-2 Missouri River Basin, NE and SD .......... 21-8 
6. Cherry Creek Lake, CO ......... . ......... 21-3 32. Oahe Dam-Lake Oahe, Missouri 
7. East Fork of the Boyer River River Basin, SD and ND ................. 21-8 
at Vail, IA........................21-3 Miscellaneous 
8. East Nishnabotna River 33. Streambank Erosion Control 
at Red Oak, IA ........................... 21-3 Evaluation and Demonstration Project ...... 21-9 
9. Fall River Basin, SD ...................... 21-4 
10. Great Falls, MT .......................... 21-4 General Investigations 
11. Indian Creek at Emerson, IA .............. 21-4 34 Surveys 21-9 
12.1 L iietitolex .S..i.o..u..x.. ..R...i.v. er, IA 435. Collection & Study of Basic Data..........21-9 ................... 21-4 36. Research and Development ............... 21-9 
13. Lost Creek at Columbus, NE ................ 21-4 37. Continuation of Planning and Engineering ... 21-9 
14. Missouri National Recreational 38. Planning and Engineering 
River, NE and SD ....................... 21-5 Under Proposed Legislation ............... 21-9 
15. Missouri River, Garrison Dam 39. Advanced Engineering and Design ......... 21-9 
to Lake Oahe, ND ......................... 21-5 40. Transportation Systems ................. 21-9 
16. Missouri River, Kenslers Bend, Tables 
NE to Sioux City, IA .................. 21-5 21-A Cost and Financial Statement .......... 21-10 17. Missouri River Levee System, 21-B Authorizing Legislation ............... 21-12 
Sioux City, IA to Rulo, NE ................. 21-5 21-C Other Authorized Navigation Projects .... 21-16 
18. Papillion Creek and Tributaries 21-D Not Applicable 
Lakes, NE .......................... .21-5 21-E Other Authorized Flood Control Projects.. 21-16 
19. Pick-Sloan Missouri River Basin 21-F Not Applicable 
Program (Omaha Dist)....................21-6 21-G Deauthorized Projects ................. 21-17 
20. Pipestem Lake, ND ..... ................ 21-6 21-H Missouri River, Sioux City, IA 
21. Salt Creek & Tributaries, NE ............. 21-6 to Rulo, NE .......................... 21-18 
22. Shoshone River at Byron, WY ............ 21-6 21-I Missouri River Levee System, 
23. South Platte River Basin, CO .............. 21-6 Sioux City, IA to Rulo, NE ............. 21-18 
24. Inspection of Completed Flood 21-J RMuisloso, uNrEi TReivremr,i nSailo Fuxa cCiliittiye,s I..A.. ..t.o..... 21-19 
Control Works ....................... 21-7 21-K Pick-Sloan Missouri Basin Program .. .... 21-19 
25. Scheduling Flood Control 21-L Inspection of Completed Local 
Reservoir Operations .................. 21-7 Protection Projects....................21-20 
26. Flood Control Activities Under 21-M Flood Control Activities 
Special Authorization ..................... 21-7 Under Special Authorization ............ 21-22 
21-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Navigation 
1. MISSOURI RIVER, SIOUX CITY, IA 
TO MOUTH (SIOUX CITY, IA 
TO RULO, NE) 
Location. Channel of the Missouri River extending 
from Sioux City, IA to Rulo, NE. 
Previous projects. For details see page 1893, Annual 
Report for 1915, and page 1175, Annual Report for 
1938. 
Existing project. Provides for a navigation channel of 
9-foot depth and width not less than 300 feet, obtained 
by revetment of banks, rock dikes to contract and stabilize 
waterway, cutoffs to eliminate long bends, closing 
minor channels, and removal of snags and dredging as 
required. Construction was initiated on this section of 
the project (Sioux City to Rulob) in fiscal year 1928, and 
the bank stabilization work was completed in April 
1979. Work remaining to complete this section of the 
project consists of construction of fish and wildlife facilities. 
A reliable channel suitable for navigation is available 
through this section. Controlling depth at ordinary 
stages of the river is 9 feet, with additional depths available 
during high stages. Commercial navigation was inaugurated 
on this section in May 1939, and common carrier 
transportation service was inaugurated in October 
1946. Seven riverside recreation sites are complete and 
in operation. Estimated total cost of new work Sioux 
City, IA to Rulo, NE is $189,629,000 (1983), of which 
$188,042,000 is the Federal cost of construction and 
$1,587,000 is the non-Federal cost, exclusive of amounts 
expended on previous projects. 
Local cooperation. Local interests must share in cost 
of recreation facilities in accordance with provisions of 
the Federal Water Project Recreation Act of 1965. Local 
interests have contributed for cost sharing on construction 
of recreation by constructing portions of the facilities. 
Terminal facilities. Terminal facilities for loading 
and unloading grain, liquids and dry bulk products are 
maintained by private interests at various locations on 
this section of the river. These terminals are listed in 
Table 21-J and are adequate for the current demands. 
Sites are available for construction of additional wharfage. 
Operations during fiscal year. Maintenance: Contract 
maintenance work consisted of revetment and dike 
repair. Work by hired labor forces included removal of 
debris from environmental notches, repairing dikes and 
revetments. 
Local interests have assumed operation and maintenance 
of the recreation sites. (See Table 21-H for total 
cost of work under existing project to September 1983). 
2. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Small Navigation Projects Not Specifically Authorized 
by Congress (Sec. 107 of the River and Harbor Act 
of 1960, as amended, Public Law 645, 86th Congress). 
No work during the period. 
Flood Control 
3. BEAR CREEK LAKE, CO 
Location. Damsite is on Bear Creek in Jefferson 
County, CO about 8 miles above the confluence of Bear 
Creek with the South Platte River at Denver. 
Existing project. Earthfill dam 180 feet high, with a 
crest length of about 5,300 feet, and a supplementary 
earthfill dike with a height of 65 feet and a crest length 
of 2,100 feet, to the south of the main dam, and an uncontrolled 
earth and rock-cut emergency spillway. The 
lake provides storage capacity of 28,560 acre-feet for 
flood control and 2,000 acre-feet for sediment and recreation. 
Construction of the project was initiated in October 
1973 and was completed in September 1982, exclusive 
of recreation facilities. Estimated cost through 
construction is $61,503,600 (1982). Recreation facilities 
are proposed using Code 710 cost sharing funds at an 
additional cost of $500,000. 
Local cooperation. Requirements are described in full 
on page 21-3 of fiscal year 1981 Annual Report. 
Operations during fiscal year. Maintenance: Spillway 
erosion control maintenance work was accomplished by 
contract. Work by hired labor included miscellaneous 
items of ordinary repair and maintenance. Annual project 
visitation was estimated at 95,200. 
4. BOWMAN-HALEY LAKE, ND 
Location. Damsite is on North Fork of Grand River in 
southwestern North Dakota, about 6 miles above 
Haley, ND. 
Existing project. A dam 79 feet high, with a crest 
length of 5,730 feet, and reservoir with a storage capacity 
of about 19,780 acre-feet for sediment storage, 
fish and wildlife conservation, recreation, and future 
water supply for communities of Bowman, Reeder, 
Scranton, and Gascoyne, ND. Construction was initiated 
in July 1964, and the project was completed in 
1970. Supplemental cost sharing recreational facilities 
are proposed using Code 710 funds at a cost of $353,000. 
Local cooperation. Local interests must prevent encroachment 
on capacity of North Fork channel below 
reservoir; obtain water rights for storage; pay the 
United States for costs allocated to water supply; and 
hold the United States free from damages. Assurances 
of local cooperation were approved June 19, 1964. With 
respect to water rights, requirements have been complied 
with. A contract with the Bowman County Water 
Management District for water storage space was 
signed November 10, 1981. 
Operations during fiscal year. Maintenance: Operation 
and maintenance activities included sedimentation 
and reservoir regulation studies and intermittent inspections 
of the dam and structures. Project boundary 
fencing was completed. Annual project visitation was 
estimated at 33,100. 
5. CHATFIELD LAKE, CO 
Location. On the South Platte River, just below the 
21-2

OMAHA, NE, DISTRICT 
mouth of Plum Creek, about eight miles upstream from 
Denver, CO. 
Existing project. Consists of rolled earth-fill dam 
with a maximum height of 148 feet, a crest length of 
12,500 feet, and a reservoir with flood control capacity 
of 215,000 acre-feet and sediment capacity of 20,000 
acre-feet, which will be used for recreation, and an enlarged 
channel from the dam downstream to Denver to 
accommodate reservoir flood releases. 
The Corps is participating with local interests in acquisition 
of lands and development of recreation facilities 
immediately downstream of the Chatfield Dam in 
lieu of a portion of the channel improvement. Construction 
of the project was initiated in August 1967 and is 
94 percent complete, with a scheduled completion date 
in FY 1987. Construction is essentially complete at the 
project with the exception of the downstream channel 
improvement, associated recreation facilities and fish 
and wildlife mitigation measures. Estimated cost 
through construction of the project is $104,840,000 
(1983) of which $95,100,000 is the Federal cost for construction, 
$6,840,000 local cost in connection with the 
downstream channel improvement, and $2,900,000 is 
the local cost for acquisition of water for the recreation 
pool. 
Local cooperation. Section 3, Flood Control Act of 
June 22, 1936 applies to the downstream channel improvement. 
The Colorado Water Conservation Board 
provided assurances of local cooperation for the downstream 
improvement on December 13,1967. Local interests 
must provide water for filling the sediment reserve 
pool for recreation use which the state agreed to on 
April 25, 1967. 
Operations during fiscal year. Continued design by 
hired labor. Continued construction on repairs to recreation 
facilities, visitor center floor, installation of spillway 
security fencing, and data collection platforms. Initiated 
repair to outlet works remote control and landscaping 
of the visitor center. Maintenance: continued 
routine operation and maintenance activities. Annual 
project visitation was estimated at 1,196,200. 
6. CHERRY CREEK LAKE, CO 
Location. Damsite is on Cherry Creek in Arapahoe 
County, CO, approximately 6 miles southeast of Denver, 
CO. just outside of city limits. Cherry Creek joins 
South Platte River within city limits of Denver. 
Existing project. A rolled-earthfill dam with maximum 
height of 141 feet above streambed and 14,300 
feet long. Project includes a reinforced concrete outlet 
works and an uncontrolled side channel spillway canal 
discharging into adjacent Toll Gate Creek. Cherry Creek 
project provides reservoir storage capacity of 93,920 
acre-feet below spillway canal invert and, in addition, a 
surcharge storage of 134,470 acre-feet. Plan of operation 
in ultimate development for multiple-purpose uses includes 
13,960 acre-feet for sediment storage and 79,960 
acre-feet for conservation purposes. Construction began 
in fiscal year 1946 and was completed in June 1961. exclusive 
of recreation facilities. Estimated cost of project 
is $15,214,350 (1983) including $544,450 Code 710 
funds. 
Local cooperation. None required except for recreation 
cost-sharing under the Code 710 program. 
Operations during fiscal year. Operation and maintenance 
activities include administration of project area, 
emergency spillway study, stream gaging activities, initiation 
of outlet works maintenance, emergency gate installation, 
spillway channel tree removal, containment 
dike and dredging, and miscellaneous items of ordinary 
repair and maintenance. Annual project visitation was 
estimated at 1,664,600. 
7. EAST BOYER RIVER AT VAIL, IA 
Location. The project is located in Crawford County 
along the East Fork of the Boyer River just south of the 
city of Vail, IA. 
Existing Project. The project provides bank stabilization 
along the East Fork of the Boyer River which is adjacent 
to the city's sewage lagoons. The purpose of the 
project is to prevent erosion and bank sloughing from 
encroaching into the sewage lagoon containment embankment. 
The estimated total cost of the project is 
$160,000 (1983). 
Local cooperation. The city of Vail, IA, the project 
sponsor, provided the required local assurances on October 
1, 1980. 
Operations during fiscal year. Plans and specifications 
were completed. A construction contract was 
awarded June 21, 1983, and was completed on September 
15, 1983, at a total cost of $142,000. The O&M 
manual is underway and is scheduled to be completed 
during the second quarter of Fiscal Year 1984. 
8. EAST NISHNABOTNA RIVER AT 
RED OAK, IA 
Location. On the East Nishnabotna River on the 
western edge of Red Oak in Montgomery County, IA. 
Existing Project. The work on the original project 
was initiated in April 1962 and completed in October 
1962. The work consisted of 10,500 feet of levee along 
the west edge of Red Oak. The cost when completed 
(1962) was $443,000, of which $400,000 was Federal and 
$43,000 non-Federal. Flooding subsequent to completion 
of the project raised concerns about the adequacy of 
the project. A study was made and the recommendation 
to raise the existing project to standard project flood 
protection was approved February 1981. The work is 
currently estimated at $1,857,000, of which $1,757,000 
is the Federal cost for construction and $100,000 is the 
non-Federal cost for necessary rights of way and utility 
relocations. 
Local cooperation. A 221 contract to sponsor the 
project was furnished by the City of Red Oak and was 
approved on September 21, 1981. 
Operations during fiscal year. Construction was completed 
during July 1983. 
21-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
9. FALL RIVER BASIN, SD 
Location. In Custer and Fall River Counties, in and 
near the town of Hot Springs, SD. Hot Springs unit is in 
the town of Hot Springs, immediately south of the junction 
of Cold Brook and Hot Brook which combine to 
form the Fall River. Cold Brook Lake unit is approximately 
1.25 miles north of the town of Hot Springs on 
Cold Brook; and Cottonwood Springs Lake unit is approximately 
4.5 miles west of the town of Hot Springs 
on Cottonwood Springs Creek, one-half mile upstream 
from its confluence with Hot Brook. 
Existing project. The general plan of improvement 
provides flood protection for Hot Springs, SD. The Hot 
Springs channel improvement unit consisted of widening, 
deepening and straightening 6,000 feet of channel 
of Fall River. The Cold Brook Lake unit, an earth-fill 
dam with appurtenant structures, controls an area of 
70.5 square miles. The Cottonwood Springs Lake unit 
consists of an earth-fill dam with appurtenant structures 
and controls an area of 26 square miles. Construction 
of Hot Springs unit was completed during fiscal 
year 1951. Construction of Cold Brook unit dam and appurtenances 
was completed in fiscal year 1953 with exception 
of a road and parking area which were completed 
in fiscal year 1955. Construction of the Cottonwood 
Springs unit dam was completed in fiscal year 
1970, with the exception of the recreation facilities 
which were completed in fiscal year 1972. 
Local cooperation. Local cooperation requirements 
have been fully complied with. 
Operations during fiscal year. Maintenance: Routine 
operation and maintenance activities were continued on 
the Cottonwood Springs and Cold Brook Dams and 
structures. Annual project visitation was estimated for 
Cold Brook Lake and Cottonwood Springs Lake at 
66,800 and 16,100 respectively. 
10. GREAT FALLS, MT 
Location. In Great Falls, Cascade County, MT at confluence 
of the Sun and Missouri Rivers. 
Existing project. Provides for levees along the left 
bank of the Sun River and an interceptor ditch and 
closed conduit to collect and convey side-hill runoff to 
the Sun River. Estimated cost through construction of 
the project is $13,252,000 (1983) of which $11,200,000 is 
the Federal cost of construction and $2,052,000 is the 
local cost for lands, relocations and a cash contribution 
for replacement of a storm sewer conduit desired by 
local interests. 
Local cooperation. Section 3. Flood Control Act of 
June 22, 1936 applies. In addition local interests must 
zone the unleveed portion of the flood channel through 
the damage area to preserve its capacity and to prevent 
further encroachments and contribute in cash $179,000 
representing the estimated cost of replaced storm drainage 
facilities which will be incorporated into the closed 
conduit of the.Watson Coulee Interceptor. West Great 
Falls Flood Control and Drainage District provided assurances 
on January 17, 1968. State Supreme Court decision 
on assessments required a change in state law, 
which was enacted in 1973. The final court ruling on 
compliance was made April 1, 1981, and the local sponsor 
was instructed to proceed toward project construction. 
Operations during fiscal year. Work was completed 
on the Watson Coulee Interceptor Conduit contract. 
Work continued on the Sun River left bank levees and 
channels contract and is 83% complete. Engineering 
and design continued by hired labor. 
11. INDIAN CREEK AT EMERSON, IA 
Location. The project is located in Mills County along 
the right bank of Indian Creek just east of the city of 
Emerson, Iowa. 
Existing project. This project consists of raising old 
Highway 34 and constructing a levee 180 feet long. This 
project provides protection to commercial and residential 
areas. The estimated cost of construction is 
$242,500 (1983). 
Local cooperation. The local sponsor is responsible 
for all necessary rights-of-way and utility relocations. 
The city of Emerson, IA is the local sponsor. Assurances 
of local cooperation were provided by the local 
sponsor on June 24, 1983. 
Operations during fiscal year. Plans and specifications 
were completed. A contract for construction was 
awarded on September 18, 1983 and is scheduled for 
completion during the third quarter of fiscal year 1984. 
12. LITTLE SIOUX RIVER, IA 
Location. The project is located in the lower portion 
of the Little Sioux River Basin in Harrison and Monona 
Counties, IA, near the confluence of the Little Sioux and 
Missouri Rivers. 
Previous Project. For details see page 646, Annual 
Report for 1970. 
Existing project. Construction of the original project 
was completed in June 1966. Sill No. 4 was identified as 
a design deficiency in a June 17, 1981 report by the 
Omaha District, approved by OCE. Based on that report, 
design studies for a permanent solution to the 
problem have been initiated. Estimated cost of the new 
work is $4,817,000 (1983). 
Local cooperation. The Little Sioux Inter-County 
Drainage District was sponsor of that portion of the 
original project where the remedial work will be accomplished. 
Remedial work is to be 100 percent Federally 
funded. 
Operations during fiscal year. Design studies and 
surveys were initiated using regular funds. Model testing 
by Waterways Experiment Station (WES) is underway. 
Preconstruction planning is in progress. A General 
Design Memorandum is scheduled for completion in 
March 1984. 
13. LOST CREEK AT COLUMBUS, NE 
Location. On Lost Creek just north of the City of Columbus 
in Platte County, NE. 
21-4

OMAHA, NE, DISTRICT 
Existing project. This project provides levee and 
channel improvements on the north side of Columbus 
and provides protection to commercial and residential 
areas. The estimated cost of the construction is 
$3,800,000 (1983) of which $3,040,000 is the Federal 
cost of construction, and $760,000 is non-Federal contributed 
funds - other, that provides for all necessary 
right of way, utility, and bridge relocations. 
Local cooperation. A contract with the City of Columbus 
to sponsor the project was approved on February 
18, 1982. 
Operations during fiscal year. Plans and specifications 
for Stage 2 were completed and a contract was 
awarded for construction on July 27,1983. Construction 
of a drop structure and channel alignment was completed 
for Stage 1. 
14. MISSOURI NATIONAL RECREATIONAL 
RIVER, NE, AND SD 
Location. NE and SD. The Missouri River between 
Gavins Point Dam and Ponca State Park, NE. This includes 
Cedar and Dixon Counties in Nebraska, and 
Yankton, Clay, and Union Counties in South Dakota. 
Existing project. The designation as a National Recreational 
River will preserve outstanding and important 
scenic values and will provide additional opportunities 
for river access and recreation use. Erosion control, consisting 
of bank stabilization and river management 
techniques designed to preserve the existing environment, 
will at the same time preserve high bank flood 
plain lands. Federal cost of the project is limited by the 
authorization to $21,000,000. 
Local cooperation. None required. 
Operations during fiscal year. Continued coordination 
with the National Park Service. 
15. MISSOURI RIVER, GARRISON DAM 
TO LAKE OAHE, ND 
Location. Along the channel of Missouri River between 
Garrison Dam and headwaters of Oahe Reservoir 
in North Dakota. 
Existing project. Consists of bank stabilization and 
rectification works required to stabilize banks of Missouri 
River in specific areas and prevent further loss of 
agricultural lands through erosion. Construction was initiated 
January 1965 and project is 99 percent complete. 
Estimated total cost is $9,711,000 (1983) of which 
$9,441,000 is the Federal cost of construction and 
$270,000 is the non-Federal cost for all lands, easements, 
and rights of way. 
Local cooperation. Section 3, Flood Control Act of 
June 22, 1936, applies. 
Operations during fiscal year. The existing corrective 
construction contract was completed in July 1983. 
O&M manuals were completed by hired labor. 
16. MISSOURI RIVER, KENSLERS 
BEND, NE, TO SIOUX CITY, IA 
Location. Project is along Missouri River between 
Ponca Bend, NE, and combination bridge at Sioux City, 
IA.
Existing project. Construction of dikes, revetments 
and channel improvement along Missouri River from 
Miners Bend and vicinity, SD and NE, to Sioux City, 
IA. Project was started in June 1946 and completed in 
June 1961. 
Local cooperation. Fully complied with. 
Operations during fiscal year. Maintenance consisted 
of rehabilitation of environmental notches. 
17. MISSOURI RIVER LEVEE SYSTEM, 
IOWA, NEBRASKA, KANSAS AND 
MISSOURI (SIOUX CITY, IA 
TO RULO, NE) 
Location. On both banks of the Missouri River from 
Sioux City, IA to St. Louis, MO. Active portion of the 
project in Omaha District extends from Council Bluffs, 
IA to Rulo, NE. 
Existing project. A series of levee units and appurtenant 
works along both sides of Missouri River from 
Sioux City, IA, to mouth, for protection of agricultural 
lands and small communities against floods. Construction 
was initiated June 1948. (See Table 21-I for status 
of active units). Construction was initiated on Levee 
Unit L-611-614 in September 1980 and is 85 percent 
complete. Construction of Unit R-616 was initiated in 
May 1983 and is 45 percent complete. Cost estimate for 
active portion of project from Council Bluffs, IA to 
Rulo, NE is $41,400,000 (1983) of which $36,800,000 is 
Federal cost for construction and $4,600,000 local costs 
for lands and damages. 
Local cooperation. Section 3, Flood Control Act of 
June 22, 1936 applies. Fully complied with for all completed 
units. Local interests have furnished assurances 
of their willingness and ability to fulfill local cooperation 
requirements for the remaining active units. 
Operations during fiscal year. Levee Unit L-611-614, 
Stage 3, construction continued. Construction of Levee 
Unit R-616 was initiated. 
18. PAPILLION CREEK AND 
TRIBUTARIES LAKES, NE 
Location. The Papillion Creek basin is located in 
Washington, Douglas, and Sarpy Counties, NE. Big Papillion 
Creek rises west of Blair, flows southeasterly 
through metropolitan Omaha area where it is joined by 
the Little Papillion Creek just above Offutt AFB, forming 
Papillion Creek. The combined creek flows along the 
side of Offutt AFB to its confluence with the Missouri 
River. 
Existing project. The active project consists of a 
series of four dams and reservoirs on tributaries of Papillion 
Creek. Construction of the project was initiated 
in FY 1972. Construction 'was completed on Standing 
Bear Lake (Site 16) in December 1978 and Glenn Cunningham 
Lake (Site 11) in December 1979. Construction 
at Site 20 is 77 percent complete. Construction at Site 
21-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
18 is 34 percent complete. Estimated Federal appropriation 
requirement through construction of the project 
is $46,000,000 (1983). Estimated non-Federal cost 
sharing for recreation facilities is $3,362,000, which includes 
Federal reimbursement of $2,045,000. 
Local cooperation. Requirements are described in full 
on page 21-6 of fiscal year 1981 Annual Report. 
Operations during fiscal year. Design for Sites 18 and 
20 continued by hired labor. Construction continued at 
Sites 18 and 20; land acquisition continued at Site 18. 
Maintenance: Routine operations and maintenance activities 
continued at Sites 11 and 16. Annual project visitation 
was estimated at 892,500. 
19. PICK-SLOAN MISSOURI BASIN 
PROGRAM (OMAHA DISTRICT) 
Location. Flood control improvements in this project 
are along Missouri River and several of its principal 
tributaries and in states comprising Missouri River 
Basin. 
Existing project. General comprehensive plan for 
flood control and other purposes in Missouri River 
Basin provides for levees along Missouri River between 
Sioux City, IA, and mouth and reservoirs on main stem 
of Missouri River and tributaries. See individual reports 
and Table 21-K for projects in the Omaha District included 
in the comprehensive plan. 
20. PIPESTEM LAKE, ND 
Location. On Pipestem Creek in Stutsman County, 
ND, 3 miles upstream from where Pipestem Creek joins 
the James River at Jamestown, ND. 
Existing project. The project consists of a rolled 
earth-fill dam approximately 108 feet high with a crest 
length of 4,000 feet and outlet works of a gated reinforced 
concrete conduit. The reservoir provides 146,880 
acre-feet of storage. The multipurpose pool provides 
space for silt storage and 885 acres of water surface for 
fish, wildlife and recreation needs. Construction of the 
project was initiated in FY 1970 and completed in FY 
1977. 
Local cooperation. Local interests are required to administer 
project land and water areas for recreation and 
fish and wildlife enhancement and to bear the first cost 
of associated improvements in the wildlife management 
area; pay, contribute in kind, or repay, with interest, 
one-half of the separable cost of the project allocated to 
recreation and fish and wildlife enhancement; and bear 
all costs of operation, maintenance, and replacement of 
recreation and fish and wildlife lands and facilities. 
Operations during fiscal year. Routine operation and 
maintenance activities continued. Annual project visitation 
was estimated at 150,200. 
21. SALT CREEK AND TRIBUTARIES, NE 
Location. Salt Creek Basin comprises an area of 
about 1,627 square miles in and around Lincoln in 
southeastern Nebraska. 
Existing project. The authorized project consists of a 
system of 10 dams and reservoirs, channel clearing, enlarging 
and realignment, levees and necessary bridge alterations. 
Pursuant to Senate Resolution adopted 
August 7, 1964, which authorized a review of Salt Creek 
survey report, remaining units were placed in 
"inactive" classification. Construction of the project began 
in the spring of 1962. All work under the active portion 
of the project, consisting of the 10 dams and reservoirs 
and the channel improvements and levees through 
Lincoln, was completed in 1969. Funds were transferred 
to the project in FY 1980 with concurrence of Congressional 
Committees. These funds were used to determine 
an effective method of correction for the dispersive clay 
problem in the completed downstream levees through 
Lincoln. Initial corrective construction on the levee was 
completed in September 1980. 
Local cooperation. Fully complied with for the completed 
levee and channel improvement part of the project. 
For the dams, local interests are required to operate 
and maintain the permanent pools for fish and wildlife 
conservation and assume all costs related to utilization 
of the permanent pools for recreational purposes and insure 
public access to the pools. 
Operations during fiscal year. An interim report was 
forwarded during FY 1983, to higher authorities and 
guidance was requested prior to recommending any further 
repairs. Maintenance: Operation and maintenance 
activities included sedimentation and reservoir regulation 
studies, intermittent inspections of the dams and 
structures, and rehabilitation of the outlet works. Annual 
visitation to the system of dams was estimated at 
1,861,200. 
22. SHOSHONE RIVER AT BYRON, WY 
Location. The project is located in Big Horn County 
along the left bank of the Shoshone River southeast of 
Byron, WY. 
Existing project. Severe erosion occurred along the 
left bank of the Shoshone River adjacent to the city's 
sewage lagoon. The work consists of 830 feet of stonefill 
revetment along the lagoon with a 50 foot refusal at the 
upstream end of the revetment. The work is currently 
estimated to cost $153,000 (1983). 
Local cooperation. A Section 221 contract to sponsor 
the project was furnished by the City of Byron and was 
approved on January 7, 1982. 
Operations during fiscal year. Design of the streambank 
erosion project was initiated in July 1981. Fiscal 
Year 1983 Jobs Bill funding provided funds for the construction 
of this project. A construction contract was 
awarded on September 8, 1983, and is approximately 
11% complete. 
23. SOUTH PLATTE RIVER BASIN, CO 
Location. Flood control improvements in this project 
are along the South Platte River and its tributaries in 
Colorado. 
Existing project. General plan for flood control and 
.21-6

OMAHA, NE, DISTRICT 
other purposes provides for construction of Chatfield 
Lake on the South Platte River, Bear Creek Lake on 
Bear Creek, and levee and channel improvements on the 
South Platte River. (See individual reports and Table 
21-B for authorizing legislation). 
24. INSPECTION OF COMPLETED 
FLOOD CONTROL WORKS 
Flood Control Act of June 22, 1936, and subsequent 
acts require local interests to furnish assurances that 
they will maintain and operate certain local protection 
projects after completion, in accordance with regulations 
prescribed by Secretary of the Army. District Engineers 
are responsible for administration of these regulations 
within the boundaries of their respective districts. 
Inspections of completed local protection projects 
which have been turned over to local interests for maintenance 
and operation during the fiscal year are set 
forth in Table 21-L, Inspections of Completed Local Protection 
Projects. Fiscal year costs were $203,197. 
25. SCHEDULING FLOOD CONTROL 
RESERVOIR OPERATIONS 
Under sections 7 and 9, Flood Control Act of December 
22, 1944, Corps of Engineers is responsible for detailed 
scheduling of operations involving storage capacity 
reserved for or assigned to flood control in reservoirs 
constructed by Bureau of Reclamation as well as those 
constructed by Corps of Engineers. Costs for FY 1983 
were $220,935 and total costs to September 30, 1983 
were $4,058,472. 
26. FLOOD CONTROL ACTIVITIES 
UNDER SPECIAL AUTHORIZATION 
Emergency Flood Control Activities - Repair, Flood 
Fighting and Rescue Work (Public Law 99, 84th Cong., 
and antecedent legislation). 
Federal costs for FY 1983 were $181,644 for disaster 
preparedness, $236,470 for emergency operations, and 
$20,652 for repair and restoration. 
Small Flood Control Projects Not Specifically Authorized 
by Congress (Sec. 205, 1948 Flood Control Act 
as mended, Public Law 858,80th Cong., June 30, 1948). 
See Table 21-M for preauthorization studies on potential 
projects. 
Emergency Bank Protection (Sec. 14, 1946 Flood Control 
Act, Public Law 526, 79th Cong., July 24, 1946). 
Operations under this heading were as follows: Two 
projects, E. Fork of the Boyer River at Vail, IA and Shoshone 
River at Byron, WY, were approved by OCE in 
FY 1982 for construction; however, funds were not 
available at that time. Construction funds were provided 
during FY 1983 by the Civil Works Jobs Bill, see 
Sections 7 and 22 in the text respectively. No negative 
reconnaissance reports were submitted during FY 1983. 
Multiple-Purpose Projects Including Power 
27. BIG BEND DAM-LAKE SHARPE, 
MISSOURI RIVER BASIN, SD 
Location. On Missouri River, 987.4 miles above 
mouth, near Fort Thompson, SD, and approximately 20 
miles upstream from Chamberlain, SD. Dam is located 
in the upstream reach of Fort Randall Reservoir. Big 
Bend Reservoir extends upstream to Pierre, SD. 
Existing project. A rolled-earthfill dam 95 feet high, 
with a crest length of 10,570 feet, a hydroelectric generating 
plant consisting of eight 58,500 kilowatt units, 
and a chute-type gated spillway. Reservoir provides 
gross storage of 1,883,000 acre-feet. Estimated cost is 
$107,490,000 (1983) including $369,000 Code 710 funds. 
Construction began in September 1959 and was completed 
in September 1977, except for Code 710 recreation 
facilities. On September 30, 1983, reservoir pool 
was at elevation 1420.2 feet mean sea level and a total 
volume of 1,703,000 acre-feet of water was impounded. 
Local cooperation. None required. 
Operations during fiscal year. Public use facilities 
were constructed with Code 710 funds. Maintenance: 
Project was operated in conjunction with other Missouri 
River reservoirs for flood control, power production and 
other multiple uses. During the period, 945,433,000 net 
kilowatt-hours of electricity were produced. Installation 
of a power plant controller system for the Missouri 
River dams continued. Annual project visitation was 
estimated at 889,700. 
28. FORT PECK LAKE, MT 
Location. Reservoir is in Missouri River Valley in Mc- 
Cone, Valley, Garfield, Phillips, Petroleum, and Fergus 
Counties, MT. Dam is approximately 1,771.5 miles 
above mouth of Missouri River. Nearest towns are Glasgow, 
17 miles northwest, and Nashua, 9 miles north. 
Existing project. A hydraulic earthfill dam with a 
maximum height of 251 feet, with a crest length of 
21,026 feet, and a reservoir for flood control, irrigation, 
navigation, hydroelectric power, and other purposes, 
with a gross storage capacity of 18,909,000 acre-feet at 
maximum operating pool. Work started on original project 
in October 1933 and on second power plant in August 
1956. The project was completed in 1965. The 
power installations at the project were uprated in FY 
1979. The 5 generators have a total output of 185,250 
KW, 2 generators at 40,000 KW each, 2 generators at 
43,500 KW each and 1 generator at 18,250 KW. See 
page 818 of 1965 Annual Report and page 905 of 1958 
Annual Report for project details. Estimated cost of 
overall project (1983) is $158,487,000 including 
$1,936,000 Code 710 funds. 
Local cooperation. None required. 
Operations during fiscal year. Maintenance: Installation 
of a powerplant controller system for the six Missouri 
River dams and contracts for rehabilitation of the 
townsite continued. Fort Peck Lake was operated in 
conjunction with the other Missouri River reservoirs for 
flood control, navigation, power production, and other 
21-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
multi-purpose uses. Generating facilities produced 
1,073,107,000 net kilowatt hours of electricity. Total 
cost of Operation and Maintenance during the period 
was $5,719,500, however, reimbursement from the 
Western Area Power Administration for the prorata 
share of Operation and Maintenance cost of the power 
plant, reimbursement for furnishing operator's village 
facilities, and property disposals reduced net cost to 
$2,197,900. Annual project visitation was estimated at 
454,100. 
On September 30, 1983, the pool was at elevation 
2239.8 and 16,485,000 acre-feet of water was impounded 
in the reservoir. 
29. FORT RANDALL DAM-LAKE FRANCIS 
CASE, MISSOURI RIVER BASIN, SD 
Location. On Missouri River in Charles Mix and 
Gregory Counties, SD, about 82 miles above Yankton, 
SD. Site is 880 miles above mouth of Missouri River and 
148 miles above Sioux City, IA. 
Existing project. A rolled-earthfill dam with a maximum 
height of 165 feet, a crest length of 10,700 feet, 
and a reservoir for flood control, irrigation, navigation, 
hydroelectric power, and other purposes, with a gross 
storage capacity of 5,603,000 acre-feet at maximum operating 
pool. The power installation consists of eight 
units rated at 40,000 kilowatts each. Construction began 
in May 1946 and was completed in 1969, except for 
ode 710 recreation facilities. On September 30, 1983, 
reservoir pool was at elevation 1351.8 feet mean sea 
level, and a total volume of 3,423,000 acre-feet of water 
was impounded. Estimated Federal cost of project is 
$199,072,000 (1983), of which $197,402,000 is the Federal 
cost for construction, and $1,670,000 is Code 710 
funds. Non-Federal contribution for constructing approaches 
to the Platte-Winner Bridge was $720,000. 
Local cooperation. None required. 
Operations during fiscal year. Public use facilities 
were constructed with Code 710 funds. Maintenance: 
Project was operated in conjunction with other Missouri 
River reservoirs for flood control, navigation, power production, 
and other multiple uses. Generating facilities 
produced 1,781,234,000 net kilowatt-hours of electricity. 
Installation of a power plant controller system 
for the Missouri River dams continued. The contract 
that was awarded for sanitary sewers and a water distribution 
line in conjunction with rehabilitation of the government 
townsite at Pickstown was completed. Annual 
project visitation was estimated at 1,539,800. 
30. GARRISON DAM-LAKE SAKAKAWEA, 
MISSOURI RIVER BASIN, ND 
Location. On Missouri River in McLean and Mercer 
Counties, ND, about 11 miles south of Garrison, ND, 
and 9 miles west of Coleharbor, ND. 1,389.9 miles above 
mouth of river and 75 miles above Bismarck, ND. 
Existing project. A rolled-earthfill dam 11,300 feet 
long with a maximum height of 210 feet and a reservoir 
for flood control, irrigation, navigation, hydroelectric 
poWer, and other purposes, with a gross storage capacof 
24,137,000 acre-feet. It provides five power units, 
three units rated at 80,000 kilowatts each, and two units 
rated at 95,000 kilowatts each, three flood control tunnels 
and a gated spillway. Estimated Federal cost is 
$300,046,000 (1983) including $1,380,000 Code 710 
funds and $4,208,000 for major rehabilitation. Non-Federal 
contribution in connection with widening Snake 
Creek Embankment was $687,000. Construction of the 
project was initiated in April 1946 and completed in 
1966, except for recreational development using Code 
710 funds. On September 30, 1983, pool elevation was 
1843.1 and 20,140,000 acre-feet of water was impounded. 
Local cooperation. None required except cost sharing 
with the State of North Dakota for widening the Snake 
Creek Embankment. 
Operations during fiscal year. Public use facilities 
were constructed with Code 710 funds. Maintenance: 
Project was operated in conjunction with the other Missouri 
River reservoirs for flood control, navigation, 
power production, and other multiple purpose uses. Normal 
operation and maintenance procedures were accomplished 
during the fiscal year. Generating facilities produced 
2,458,152,000 net kilowatt-hours of electricity. 
Installation of a power plant controller system for the 
Missouri River dams and contracts for rehabilitation of 
the townsite continued. Annual project visitation was 
estimated at 2,580,600. 
31. GAVINS POINT DAM-LEWIS AND 
CLARK LAKE, MISSOURI RIVER 
BASIN, NE AND SD 
Location. On Missouri River in Yankton County, SD, 
and Knox County, NE, about 4 miles upstream from 
Yankton, SD, and 811.1 miles above mouth of river. 
Existing project. A concrete and rolled-earth-fill dam 
with a maximnum height of 74 feet and a reservoir for 
flood control, irrigation, navigation, hydroelectric 
power, and other purposes with a gross storage capacity 
of 504,000 acre-feet at maximum operating pool. The 
power installation consists of three units rated at 33,333 
kilowatts each. Cost estimate is $49,388,000 (1983), including 
$1,331,000 Code 710 funds. Construction of 
original project was initiated in March 1952 and was 
completed in 1964. Project is providing its multiple purpose 
benefits for flood control, navigation, power, and 
other uses. On September 30, 1983, pool elevation was 
1207.9 and a total volume of 439,000 acre-feet of water 
was impounded. 
Local cooperation. None required. 
Operations durin fiscal year. Public use facilities 
were constructed with Code 710 funds. Maintenance: 
Project was operated in conjunction with other Missouri 
River reservoirs for flood control, navigation, power production 
and other multiple purpose uses. Generating 
units produced 778,261,000 net kilowatt-hours of electricity 
during fiscal year. Installation of a power plant 
controller system for the Missouri River dams continued. 
Annual project visitation was estimated at 
2,216,100. 
32. OAHE DAM-LAKE OAHE, MISSOURI 
RIVER BASIN, SD AND ND 
Location. Dam is on Missouri River in Hughes and 
Stanley Counties, SD, about 6 miles northwest of 
Pierre, SD, and 1,072.3 miles above mouth of river. 
Existing project. A rolled-earthfill dam with maximum 
height of 245 feet, a crest length of 9,300 feet, and 
reservoir for flood control, irrigation, navigation, hydroelectric 
power, and other purposes, with a gross storage 
capacity of 23,337,000 acre-feet at maximum operating 
21-8

OMAHA, NE, DISTRICT 
pool. It contains seven power units rated at 85,000 kilowatts 
each. Estimated cost is $347,373,000 (1983) including 
$3,197,000 Code 710 funds. Construction was 
initiated August 1948 and project placed in operation 
June 1963. Land acquisition is 97 percent complete. On 
September 30, 1983, pool elevation was 1612.6 and a 
total volume of 20,649,000 acre-feet of water was impounded. 
Operations during fiscal year. Public use facilities 
were constructed with Code 710 funds. Maintenance: 
Project was operated in conjunction with the other Missouri 
River reservoirs for flood control, navigation, 
power production and other multiple purpose uses. Generating 
facilities produced 2,701,344,000 net kilowatthours 
of electricity. Installation of a power plant controller 
system on the Missouri River dams continued. 
Annual project visitation was estimated at 2,642,900. 
Miscellaneous 
33. STREAMBANK EROSION CONTROL 
EVALUATION AND 
DEMONSTRATION PROJECT 
Location. Along the Missouri River between Garrison 
Dam and Lake Oahe, ND and between Fort Randall 
Dam and Sioux City, IA; along the Yellowstone River in 
Montana and North Dakota; and along undesignated 
rivers and streams in the Omaha District. 
Existing project. The project provides for development 
of new methods and techniques for bank protection. 
It consists of various experimental bank stabilization 
structures designed to stabilize the river banks and 
prevent further loss of land through erosion. Construction 
was initiated in November 1976 on the Missouri 
River between Garrison Dam and Lake Oahe and between 
Gavins Point Dam and Sioux City, IA. Construction 
was initiated in August 1978 on the Missouri River 
between Fort Randall Dam and Lewis & Clark Lake. 
Construction was initiated in October 1980 on the Yellowstone 
River between Intake, MT and the mouth. 
Construction has been completed at a total Federal cost 
of $17,485,000. 
Local cooperation. The sponsor is the North Dakota 
State Water Commission for the North Dakota portion 
of the Yellowstone River as well as the Missouri River, 
Garrison Dam to Lake Oahe portion. The sponsors for 
the Missouri River, Fort Randall Dam-Lewis & Clark 
Lake portion are the Lower Niobrara Natural Resources 
District, NE and the Charles Mix County Conservation 
District, SD. The sponsors for the Missouri River, 
Gavins Point Dam-Sioux City, IA portion are the Lewis 
and Clark Natural Resource District, NE, and Clay, 
Union, and Yankton Counties, SD. The sponsor for the 
Montana portion of the Yellowstone River are the Richland 
County Commissioners. The sponsor for the Powder 
River at Arvada, WY, is the Sheridan County Board 
of County Commissioners. The local sponsor is responsible 
for necessary lands, easements and rights of way 
and O&M after completion. 
Operations during fiscal year. Structural rehabilitation 
continued on the Missouri River in North Dakota 
between Garrison Dam and Lake Oahe, in South Dakota 
and Nebraska between Fort Randall to Ponca, and on 
the Yellowstone River in North Dakota in the Cheney 
Creek Area. 
General Investigations 
34. SURVEYS 
Costs for FY 1983 amounted to $2,107,565 of which 
$1,749,857 was for flood control studies, $169,501 review 
of authorized projects, and $188,201 for coordination 
studies with other agencies. 
35. COLLECTION AND STUDY OF BASIC 
DATA 
(Precipitation Studies) 
No work during the period. 
(Inspection of Dams) 
National Dam Safety Program 
Inspection of Dams - The inspection of all Non-Federal 
dams in the five state area of Colorado, Nebraska, 
North Dakota, South Dakota and Wyoming is complete. 
Inventory of Dams - Work on the inventory of dams 
is complete. The total cost of this program since inception 
was $733,050. There are approximately 7,383 dams 
in the five state area assigned to the Omaha District. 
(Flood Plain Management Services) 
Flood Plain Information Reports - None. 
Flood Plain Management 
Flood plain management service costs for the Omaha 
District were $94,893 and the costs for the Missouri 
River Division office were $54,105 during the fiscal 
year. 
Technical Services 
The costs for providing site investigations and flood 
hazard evaluations to military and non-military Federal 
agencies, state and local government agencies, and to individuals 
and businesses were $86,755. 
Hydrologic Studies 
Costs for hydrologic studies for the fiscal year were 
$27,045. 
36. RESEARCH AND DEVELOPMENT 
No work during the period. 
37. CONTINUATION OF PLANNING 
AND ENGINEERING 
No work during the period. 
38. PLANNING AND ENGINEERING 
UNDER PROPOSED LEGISLATION 
No work during the period. 
39. ADVANCED ENGINEERING 
AND DESIGN 
No work during the period. 
40. TRANSPORTATION SYSTEMS 
The Corps of Engineers is the lead agency in the recently 
completed ational Waterways Study. This 
Study examines the characteristics of the National 
Waterways System, its past and present role in commerce 
and in meeting national needs, along with projections 
and recommendations for future development, and 
its relationship to other modes of transportation. 
21-9

TABLE 21-A 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
COST AND FINANCIAL STATEMENT 
See 
Section 
in Text Project 
Missouri River, 
Sioux City, IA 
to Rulo, NE 
3. Bear Creek Lake, 
CO 
4. Bowman-Haley 
Lake, ND 
5. Chatfield Lake, 
CO 
6. Cherry Creek 
Lake, CO 
7. East Fork of the 
Boyer River at 
Vail, IA 
8. East Nishnabotna 
River at Red Oak, 
IA 
9. Fall River 
Basin, SD 
10. Great Falls, MT 
11. Indian Creek, 
Emerson, IA 
12. Little Sioux River 
and Tributaries, IA 
13. Lost Creek, 
Columbus, NE 
14. Missouri National 
Recreational River 
NE & SD 
15. Missouri River, 
Garrison Dam 
to Lake Oahe, 
ND 
1. 
Total Thru 
FY 80 FY 81 FY 82 FY 83 Sep 30, 1983 
1
I
I
1
i Funding 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
83 
1,691,000 
1,697,737 
242,000 
254,530 
197,000 
209,971 
177,000 
189,624 
633,000 
608,748 
262,000 
270,880 
218,000 
193,201 
2,645,000 
2,426,596 
1,158,000 
791,523 
107,000 
96,470 
78,000 
73,757 
772,000 
1,678,085 
155,000 
180,579 
238,000 
255,230 
11,000 
11,000 
22,000 
22,863 
1,000 
1,500 
127,000 
117,287 
--266,000 
73,772 
48,0' ) 
50,310 
500,000 
391,189 
60,000 
268,994 
92,000 1,207 
86,732 1,145 
176,000 
181,577 
128,000 
130,205 
65,000 
25,190 
100,000 
177,481 
60,000 
48,399 
207 
203 
3,250 
2,858 
225 
144 
30 
3,045,000 
2,569,622 
48,333 
274,000 
171,428 
150,000 
139,705 
442,000 
509,808 
291,000 
291,525 
20,000 
50,234 
2,003,000 
2,480,742 
584,000 
906,602 
194,000 
181,266 
238,000 
227,011 
721,000 
793,341 
47,000 
45,604 
276,000 
257,390 
x,000 316,000 
,571 288,836 
),000 6,950,000 
,217 6,217,952 
- 375,000 
- 47,276 
- 250,000 
- 245,482 
x,000 1,300,000 
1,535 1,165,133 
800 
16,260 
120,000 
144,138 
8,957 
35,650 
189,225,9911 
189,224,3311 
98,257,419 
97,778,874 
61,533,600 
61,501,151 
772,000 
659,135 
4,372,174 
4,372,174 
1,276,043 
1,261,848 
86,976,700 
86,938,895 
1,220,800 
1,217,890 
15,053,364 
15,053,364 
3,818,511 
3,495,138 
162,000 
155,977 
2,143,016 
2,130,366 
5,538,432 
5,538,432 
2,229,141 
2,188,653 
10,992,1124 
9,855,5294 
375,000 
47,276 
15,732,920 
15,728,402 
1,823,518 
1,578,433 
600,800 
593,887 
9,441,000 
9,374,464 
21-10 
282 
305
,000 744,000 
,660 421,538 
- 151,000 
- 144,977 
,000 344,000 
,430 402,380

OMAHA, NE, DISTRICT 
TABLE 21-A (Continued) 
SSe in
me 
ection 
Text Project 
16. Missouri River, 
Kenslers Bend, 
NE, to Sioux 
City, IA 
17. Missouri River, 
Levees, IA, 
NE, KS & MO 
18. Papillion Creek 
and Tributaries 
Lakes, NE 
20. Pipestem Lake, 
NDI 
21. Salt Creek and 
Tributaries, NE 
22. Shoshone River, 
Byron, WY 
27. Big Bend Dam- 
Lake Sharpe, 
Missouri River 
Basin, SD 
28. Fort Peck, Lake 
MT 
29. Fort Randall 
Dam-Lake Francis 
Case, Missouri 
River Basin, SD 
30. Garrison Dam- 
Lake Sakakawea, 
Missouri River 
Basin, ND 
(Federal Funds) 
(Contributed 
Funds) 
COST AND FINANCIAL STATEMENT 
Total Thru 
Funding FY 80 FY 81 FY 82 FY 83 Sep 30, 1983 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major Rehab 
Approp. 
Cost 
Major Rehab 
Contrib. 
Cost 
- 
33,000 
38,533 
286,000 
279,727 
-70,000 
6,720 
135,000 
130,749 
- 
206,000 
201.530 
280,000 
201,244 
924,000 
911,943 
- 
2,542,000 
2,536,990 
-4,344 
-4,344 
1,534,000 
1,841,824 
1,604 
3,839,000 
3,757,013 
185,206 
4,373,000 
4,469,665 
50,000 
48,714 
7,955,000 
7,774,971 
900,000 
610,001. 
196,000 
179,918 
206,000 
205,168 
70,000 
97,201 
549,000 
647,745 
37,000 
30,819 
2,640,400 
2,734,561 
11,000 
8,521 
2,029,600 
2,092,682 
4,438,900 
4,627,201 
33,000 
18,930 
4,494,200 
4,546,174 
53,000 
57,358 
2,830,000 
2,263,149 
4,186,000 
4,343,351 
171,000 
192,609 
229,000 
234,438 
22,456 
462,000 
472,104 
7,450 
7,450 
6,000 
181 
2,898,400 
2,871,804 
98,000 
76,531 
2,998,844 
3,005,514 
4.803,960 
4,758,168 
512,000 
488,465 
5,629,880 
5,662,105 
30,000 
29,873 
4,233,000 
2,581,157 
7,230,000 
4,786,701 
209,000 
187,375 
332,000 
261,478 
13,539 
495,000 
493,631 
130,000 
13,952 
59,000 
59,000 
3,669,400 
3,304,557 
145 
5,558,000 
4,460,663 
433,000 
420,623 
7,996,000 
7,021,679 
29,163 
8,639,300 
7,157,839 
21-11 
.. , 
11,294,414 
11,294,414 
4,277,000 
4,276,209 
37,545,388 
35,102,251 
35,907,7625 
32,493,7965 
972,000 
950,290 
9,277,545 
9,277,545 
1,717,000 
1,645,611 
12,197,6222 
12,182,0612 
5,322,475 
5,317,360 
137,450 
21,402 
107,246,597 
107,246,597 
32,424,9743 
32,002,7903 
158,450,080 
158,426,277 
42,180,9143 
41,035,1073 
198,498,883 
198,486,442 
61,440,8513 
60,340,7593 
295,442,613 
295,432,934 
69,524,7003 
67,961,4673 
4,208,310 
4,208,310 
686.961 
686,961

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 21-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Thru 
in Text Project Funding FY 80 FY 81 FY 82 FY 83 Sep 30, 1983 
31. Gavins Point New Work: 
Dam-Lewis & Approp. -1,000 - 8,000 7,000 49,246,239 
Clark Lake, Cost 6 - 8,000 7,000 49,246,239 
Missouri River Maint. 
Basin, SD Approp. 3,008,000 3,183,200 4,147,676 5,408,659 47,695,1503 
and NE Cost 2,974,868 3,248,304 4,126,591 5,291,305 47,521,6043 
32. Oahe Dam-Lake New Work: 
Oahe, Missouri Approp. - 9,000 - 1,501,000 346,091,603 
River Basin, Cost 49,479 42,388 13,912 1,496,536 346,070,272 
SD & ND Maint. 
Approp. 4,761,000 4,602,800 5,752,920 7,886,700 59,880,4993 
Cost 5,307,687 4,689,058 5,682,119 6,386,350 58,223,6223 
33. Streambank New Work: 
Erosion Control Approp. 5,049,000 2,305,000 436,000 15,000 17,485,000 
Evaluation and Cost 4,296,517 3,723,222 678,286 577,115 17,448,185 
Demonstration Project 
1. Includes $18,325,581 National Industrial Recovery 3. Includes Special Recreation Use Fees. 
$A1c,t1 81f,u1n2d5s , for$ 8p,6r2ev5i,7o1u8s prEomjeecrtg. ency Relief Funds, and for pl4a. nInnicnlgu dceoss t.$110,000 transferred to inactive portion 
2. Includes $123,000 of government cost applicable 5. Does not include $1,854,338 cost of inactive sites. 
to that portion of the project which is currenlty being 
carried in a deferred status. 
TABLE 21-B AUTHORIZING LEGISLATION 
See Date of 
Section Authorizing Project and Work 
in Text Act Authorized Documents 
1. MISSOURI RIVER, SIOUX CITY, IA TO RULO, NE 
Jan 12, 1927 Appropriation of $12 million authorized for existing H. Doc. 1120, 60th Cong., 
project. 2nd Sess. 
July 3, 1930 Appropriation of $15 million additional allotments 
totaling $29,153,108 made by Public Works 
Admimstration under provisions of National 
Industrial Recovery Act of 1938, and $9,669,791 
allotted under provisions of Emergency Relief 
Appropriations Act of 1935. 
Aug 30, 1935 For completion of project from mouth to Sioux H. Doc. 238, 73rd Cong., 2nd 
City, IA. Sess. 
Mar 2, 1945 For a channel of 9-foot depth and 300-foot width. H. Doc. 214, 76th Cong., 1st 
Sess. 
3. BEAR CREEK LAKE, CO 
Aug 13, 1968 A flood control reservoir for protection of S. Doc. 87, 90th Cong., 2nd 
metropolitan Denver, CO. Sess. 
4. BOWMAN-HALEY LAKE, ND 
Flood Control Flood control reservoir and water supply. H. Doc. 574, 87th Cong., 2nd 
Act of 1962 Sess. 
5. CHATFIELD LAKE, CO 
Flood Control Flood control reservoir and channel improvements PL 516, 81st Cong., 2nd Sess. 
Act of 1950 to provide downstream protection for Denver, CO. 
6. CHERRY CREEK LAKE, CO 
Aug 18, 1941 Initiation and partial accomplishment of project. H. Doc. 426, 76th Cong., 1st 
Sess. 
Dec 22, 1944 Completion of plan approved in Act of H. Doc. 426, 76th Cong., 1st 
Aug 18, 1941. Sess. 
Dec 22, 1944 General comprehensive plan, Missouri River Basin. H. Doc. 475, and S. Does. 
191 and 247, 78th Cong., 
2nd Sess. 
21-12

OMAHA, NE, DISTRICT 
TABLE 21-B (Continued) AUTHORIZING LEGISLATION 
See Date of 
Section Authorizing Project and Work 
in Text Act Authorized Documents 
7. EAST FORK OF THE BOYER RIVER AT VAIL, IA 
July 24, 1946 Streambank erosion protection - Section 14 PL 526, 79th Cong., 2nd Sess. 
9. 
EAST NISHNABOTNA RIVER AT RED OAK, IA 
Levee and appurtenant structures on left bank of 
the East Nishnabotna River at Red Oak, IA. 
Section 205. 
FALL RIVER BASIN, SD 
Provide flood control to the town of Hot 
Springs, SD. 
GREAT FALLS, MT 
Levees and channel improvement for local 
protection. 
INDIAN CREEK AT EMERSON, IA 
Levee and channel improvement for local 
protection - Section 206. 
LITTLE SIOUX RIVER, IA 
Correction of design deficiency. 
LOST CREEK AT COLUMBUS, NE 
Levee and channel improvement for local 
protection - Section 205. 
PL 858, 80th Cong., 2nd Sess. 
H. Doc. 655, 76th Cong., 
3rd Sess. 
H. Doc. 343, 85th Cong., 2nd 
Sess. 
PL 858, 80th Cong., 2nd Sess. 
PL 341, 80th Cong., 1st Sess. 
PL 858, 80th Cong., 2nd Sess. 
June 30, 1948 
Aug 18, 1941 
Flood Control 
Acts of 1955, 1965 
June 30, 1948 
Flood Control 
Act of 1954 
June 30, 1948 
National Parks 
and Recreation 
Act of 1978 
Flood Control 
Acts of 1963, 1968 
Aug 18, 1941 
June 30, 1948 
Aug 18, 1941 
Dec 22, 1944 
Flood Control 
Act of 1968 
June 28, 1938 
Aug 18, 1941 
Dec 22, 1944 
July 24, 1946 
Expanded general comprehensive plan for 
Missouri River Basin and authorized additional 
$200 million. 
Authorized additional $150 million for prosecution 
of general comprehensive plan for Missouri 
River Basin. 
H. Doc. 475, and S Does. 191 
and 247, 78th Cong., 2nd Sess. 
21-13 
8. 
10. 
11. 
12. 
13. 
14. MISSOURI NATIONAL RECREATIONAL RIVER, NE AND SD 
Preservation and enhancement of the Missouri PL 95/625 
River between the reaches from Gavins Point 
Dam, NE & SD to Ponca State Park, NE. 
MISSOURI RIVER, GARRISON DAM TO LAKE OAHE, ND 
Bank stabilization and rectification. H. Doc. 343, 85th Cong., 2nd 
Sess. 
MISSOURI RIVER, KENSLERS BEND, NE TO SIOUX CITY, IA 
Construction of dike, revetments. H. Doc. 821, 76th Cong., 3rd 
Sess. 
MISSOURI RIVER LEVEE SYSTEM, IA, NE, KS, AND MO. 
Levees along both sides of river from H. Doc. 821, 76th Cong., 3rd 
Sioux City, IA to Kansas City, MO. Sess. 
Extended project from Kansas City, MO to mouth H. Doc. 475, 78th Cong., 2nd 
and provided for increased protection. Sess. 
S. Docs. 191 and 247, 78th 
Cong., 2nd Sess. 
PAPILLION CREEK AND TRIBUTARIES LAKES, NE 
Series of flood control reservoirs, providing pro- H. Doc. 349, 90th Cong. 
tection for the metropolitan areas of Omaha, NE. 
PICK-SLOAN MISSOURI BASIN PROGRAM (OMAHA DIST.) 
Adopted general comprehensive plan for Missouri Flood Control Committee 
River Basin and authorized $9 million for Doc. 1, 75th Cong., 1st Sess. 
initiation and partial accomplishment. 
Modified general comprehensive plan to include H. Doc. 842, 76th Cong., 3rd 
Harlan County Dam and Reservoir on Sess. 
Republican River, NE and authorized 
additional $7 million. 
15. 
16. 
17. 
18. 
19. 
..

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 21-B (Continued) AUTHORIZING LEGISLATION 
See Date of 
Section Authorizing Project and Work 
in Text Act Authorized Documents 
May 17, 1950 
Sep 3, 1954 
Sep 3, 1954 
May 2, 1956 
July 3, 1958 
July 14, 1960 
Dec 30, 1963 
June 18, 1965 
May 12, 1967 
Aug 13, 1968 
June 19, 1970 
Dec 24, 1970 
Dec 23, 1971 
Mar 7, 1974 
July 8, 1976 
Nov 16, 1977 
Flood Control 
Act of 1965 
July 3, 1958 
July 24, 1946 
May 17, 1950 
May 12, 1967 
Aug 13, 1968 
Authorized additional $250 million for prosecution 
of general comprehensive plan for Missouri 
River Basin. 
Expanded general comprehensive plan for Missouri 
River Basin and authorized additional 
$217,710,000. 
Authorized $5,384,014 to compensate Sioux 
Indians for reservation lands required for Oahe, 
South Dakota project. 
Modified general comprehensive plan for Missouri 
River Basin by deletion of construction of Red 
Willow Dam and Reservoir, NE, and addition of 
construction of Wilson Dam and Reservoir, KS. 
Expanded eneral comprehensive plan for Missouri 
River Basin and authorized additional 8200 
million 
Authorized additional $207 million for prosecution 
of general comprehensive plan for Missouri River 
Basin. 
Authorized additional $80 million for prosecution of 
general comprehensive plan for Missouri River 
Basin and modified the plan to include work protection 
and rectification works below Garrison Dam. 
Authorized additional $116 million for prosecution 
of general comprehensive plan for Missouri River 
Basin. 
Authorized additional $20 million for prosecution 
of general comprehensive plan for Missouri River 
Basin. 
Authorized additional $38 million for prosecution 
of general comprehensive plan for Misosuri River 
Basin. 
Authorized additional $109 million for prosecution 
of general comprehensive plan for Misosuri River 
Basin. 
Change comprehensive plan name to Pick-Sloan 
Missouri Basin Program. 
Authorized additional $101 million for prosecution 
of Pick-Sloan Missouri Basin Program. 
Authorized additional $72 million for prosecution 
of Pick-Sloan Missouri Basin Program. 
Authorized additional $85 million for prosecution 
of Pick-Sloan Missouri Basin Program. 
Authorized additional $59 million for prosecution 
of Pick-Sloan Missouri Basin Program. 
PIPESTEM LAKE, ND 
Provide flood control for Jamestown, ND and 
downstream areas. 
SALT CREEK AND TRIBUTARIES, NE 
Series of dams and channel improvements for flood 
control around Lincoln, NE. 
SHOSHONE RIVER AT BYRON, WY 
Streambank erosion protection - Section 14. 
SOUTH PLATTE RIVER BASIN, CO 
Adopted plan of improvement for South Platte 
River Basin and authorized $26.3 million for 
initiation and partial accomplishment. 
Authorized additional $2 million for prosecution 
of plan. 
Authorized additional $12 million for prosecution 
of plan and Bear Creek Lake. 
H. Docs. 549 and 642, 81st 
Cong., 2nd Sess. 
H. Doc. 409, 84th Cong., 2nd 
Sess. 
H. Doc. 91-748 and 
S. Doc. 91-895. 
S. Doc. 91-1100, 91st Cong., 
2nd Sess. 
H. Doc. 266, 89th Cong., 1st 
Sess. 
H. Doc. 396, 84th Cong., 2nd 
Sess. 
PL 526, 79th Cong., 2nd Sess. 
H. Doc. 669, 80th Cong., 2nd 
Sess. 
21-14 
20. 
21. 
22. 
23.

OMAHA, NE, DISTRICT 
TABLE 21-B (Continued) AUTHORIZING LEGISLATION 
See Date of 
Section Authorizing Project and Work 
in Text Act Authorized Documents 
June 19, 1970 
Dec 23, 1971 
Mar 7, 1974 
July 8, 1976 
Nov 16, 1977 
Dec 22, 1944 
Aug 30, 1935 
May 18, 1938 
Dec 22, 1944 
June 3, 1948 
Authorized additional $21 million for prosecution 
of plan. 
Authorized additional $37 million for prosecution 
of plan. 
Authorized additional $15 million for prosecution 
of plan. 
Authorized additional $22 million for prosecution 
of plan. 
Authorized additional $3 million for prosecution 
of plan. 
BIG BEND DAM - LAKE SHARPE, SD 
Expanded general comprehensive plan for flood 
control and other purposes in the Missouri 
River Basin. 
FORT PECK LAKE, MT 
Construction of earth dam. Included in Public 
Works Administration program in 1933. 
Completion, maintenance, and operation of a 
hydroelectric powerplant, subject to certain 
provisions in act respecting transmission and sale 
of electric energy. Also authorizes installation 
of additional power-generating facilities by 
Secretary of War when deemed necessary in 
judgment of Bureau of Reclamation. 
Modified authorization to provide for full multiple 
purpose operation. 
Payments to be made to school districts serving 
project as reimbursement for educational facilities 
(including transportation to and from school) 
for pupils who are dependents of persons engaged 
in construction, operation, and maintenance of 
projects. 
H. Doc. 842, 76th Cong., 3rd 
Sess. 
H. Doc. 238, 73rd Cong., 
2nd Sess. 
H. Doc. 475 and S. Docs. 191 
and 247, 78th Cong., 2nd Sess. 
Dec 22, 1944 
Dec 22, 1944 
PWA 1968 
Dec 22, 1944 
Dec 22, 1944 
Water Resource 
Development Acts 
of 1974 & 1976 
FORT RANDALL DAM - LAKE FRANCIS CASE, SD 
Expanded general comprehensive plan for flood H. Doc. 842, 76th Cong., 3rd 
control and other purposes in the Missouri Sess. 
River Basin. 
GARRISON DAM - LAKE SAKAKAWEA, ND 
Expanded general comprehensive plan for flood 
control and other purposes in the Missouri 
River Basin. 
H. Doc. 842, 76th Cong., 3rd 
Sess. 
GAVINS POINT DAM - LEWIS AND CLARK LAKE, NE & SD 
Expanded general comprehensive plan for flood H. Doc. 842, 76th Cong., 3rd 
control and other purposes in the Missouri Sess. 
River Basin. 
OAHE DAM - LAKE OAHE, SD & ND 
Expanded general comprehensive plan for flood 
control and other purposes in the Missouri 
River Basin. 
H. Doc. 842, 76th Cong., 3rd 
Sess. 
STREAMBANK EROSION CONTROL EVALUATION AND 
DEMONSTRATION PROJECT 
Experimental bank stabilization methods to PL 93/251 
prevent losses due to erosion. 
21-15 
27. 
28. 
29. 
30. 
31. 
32. 
33.

TABLE 21-C 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
OTHER AUTHORIZED NAVIGATION PROJECTS 
Full Report Cost to September 30, 1983 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Missouri River, Sioux City, IA to 
Fort Benton, MT Complete 1948 3,123,141 644,863 
Small Navigation Project at 
Sioux City, IA Complete 1970 43,582 
TABLE 21-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last 
Full Report Cost to September 30, 1983 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Belle Fourche, Cheyenne River, SD1 
Big Sioux River at Sioux City, IA 
Blackbird Creek Near Macy, NE 2 
Boulder Creek, Boulder, CO 
Buffalo Creek, 
Meadow Grove, NE 2 
Buffalo Creek, Scranton, ND 2 
Buffalo, WY 
Castlewood Lake, Cherry Creek and 
Tributaries, CO 
Cedar Canyon Dam, Rapid City, SD 
City of Aurora, 
Westerly Creek, CO 
Clarkson, NE, Maple Creek 
Council Bluffs, IA (Act of 1936) 
Council Bluffs, IA (Act of 1944) 
Davids Creek Lake, IA 
(Act of 1968) 
Dry Creek, Hawarden, IA 
Eagle Bay and Fort Yates 
Highway Bridges, N.D. 
Floyd River, Sioux City, IA 
Forsyth, MT 
Frazer-Wolf Point, MT 
Gavins Point Dam-Lewis and Clark 
Lake Relocation of Niobrara, NE 
Gering Valley, NE 
Glasgow, MT 
Greybull, WY 
Havre, MT 
Herreid, Spring Creek, SD 
Hooper, NE 2 
Ida Grove, IA 2 
Jamestown Reservoir, ND 
Linton, ND2 
Little Papillion Creek, NE 
Little Nemaha River, NE 
Loup River, Columbus, NE 2 
Lower Big Sioux River, IA and SD 
Lower Heart River, ND 
Madison, NE, union and 
Taylor Creeks' 
Mandan, Heart River, ND 
Marmarth, ND 
Complete 
Complete 
Complete 
Inactive 
Complete 
Complete 
Inactive 
Inactive 
Complete 
Complete 
Complete 
Complete 
Complete 
Inactive 
Complete 
Inactive 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Inactive 
Complete 
Inactive 
Complete 
Inactive 
Complete 
Complete 
Complete 
Complete 
1940 
1982 
1970 
1976 
1974 
1960 
1961 
1943 
1960 
1955 
1967 
1939 
1954 
1972 
1964 
1978 
1970 
1950 
1982 
1980 
1971 
1939 
1960 
1958 
1954 
1968 
1972 
1950 
1973 
1976 
1973 
1973 
1966 
1964 
1967 
1960 
1960 
37,410 
7,458,934 
262,479 
142,666 
293,016 
102,980 
- 
120,482 
150,000 
191,282 
2,557,680 
400,000 
616,639 
11,556,667 
255,177 
435,000 
13,516,459 
5,989,663 
16,832 
248,507 
1,825,881 
50,216 
326,667 
522,344 
3,643,111 
1,000,000 
1,961,173 
234,839 
676,916 
169,498 
21-16

OMAHA, NE, DISTRICT 
TABLE 21-E (Continued) OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
Full Repor t Cost to September 30, 1983 
See Annual Operation and 
Project Status Report For Construction Maintenance 
McCook Lake, SD Complete 1958 147,627 - 
Miles City, MT Inactive 1956 - - 
Missouri River, Aten, NE Complete 1951 578,791 - 
Missouri River, Niobrara, NE Complete 1945 99,370 5,633 
Mott, ND Inactive - - - 
Mud Creek, Broken Bow, NE 2 Complete 1976 1,000,000 - 
Nishnabotna River at 
Hamburg, IA Complete 1948 236,000 - 
Norfolk, NE Complete 1971 3,400,504 - 
Omaha, NE Complete 1954 5,903,640 - 
Pierce, NE Complete 1967 296,597 - 
Platte River Near Schuyler, NE 2 Complete 1948 74,940 - 
Platte River and Lost Creek, 
Schuyler, NE Complete 1971 257,398 - 
Platte River and Tributaries, NE Inactive - 1,538,269 - 
Saco, MT Complete 1958 67,793 - 
Sacred Heart Hospital, 
Yankton, SD Complete 1978 184,380 - 
Sheridan, WY3 Complete 1976 2,618,809 - 
Shields River, 
Near Clyde Park, MT2 Complete 1951 25,747 - 
Shoshone River, Lovell, WY Complete 1963 40,706 - 
Sioux Falls, SD Complete 1966 5,288,707 - 
South Platte River Levees and 
Channel Improvements, Chatfield 
Lake to Ft. Morgan, CO Inactive 1957 - - 
Vaughn, MT, Sun River2 Complete 1971 457,582 - 
Waterloo, NE Complete 1970 237,883 - 
West Point, NE Complete 1966 149,596 - 
Yellowstone River, 
W. Glendive, MT Complete 1960 230,294- 
1. Completed as a Public Works Administration project. 
2. Authorized by Chief of Engineers. 
3. Includes inactive segment. 
TABLE 21-G DEAUTHORIZED PROJECTS 
For Last 
Full Report Date Federal Contributed 
See Annual and Funds Funds 
Project Report For Authority Expended Expended 
Billings, MT 1976 Sec. 201, FC Act 1950 75,000 - 
23 Mar 81 
Dayton, WY 1956 Sec. 12, PL 93-251 - - 
WRDA of 1974 
5 Aug 77 
Giles Creek, Elkhorn, NE 1952 Sec. 12, PL 93-251 - - 
WRDA of 1974 
6 Nov 77 
Indian Creek Lake, IA 1969 Sec. 12, PL 93-251 135,000 - 
WRDA of 1974 
4 Jan 74 
Morrison, Bear Creek, CO 1950 Sec. 12, PL 93-251 30,000 - 
WRDA Of 1974 
5 Aug 77 
Redwater River and 1966 Sec. 12, PL 93-251 1,000 - 
Hay Creek, Bell Fourche, SD WRDA of 1974 
4 Jan 74 
21-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 21-G (Continued) DEAUTHORIZED PROJECTS 
For Last 
Full Report Date Federal Contributed 
See Annual and Funds Funds 
Project Report For Authority Expended Expended 
Shell Creek, NE 1962 Sec. 12, PL 93-251 71,000 - 
WRDA of 1974 
3 Oct 78 
Vermillion River and Tribs, SD 1968 Sec. 12, PL 93-251 208,000 - 
WRDA of 1974 
4 Jan 74 
TABLE 21-H MISSOURI RIVER, SIOUX CITY, IA TO RULO, NE 
TOTAL COST OF EXISTING PROJECT TO SEPTEMBER 30, 1983 
(See Section 1 of Text) 
Cost 
Funding New Work Maintenance Total 
Regular Funds 162,273,032 97,778,874 260,051,906 
Public Works Funds 18,325,581 - 18,325,581 
Emergency Relief Funds 8,625,718 - 8,625,718 
Total Funds 189,224,331 97,778,874 287,003,205 
TABLE 21-I MISSOURI RIVER LEVEE SYSTEM, SIOUX CITY, IA TO RULO, NE 
(See Section 17 of Text) 
Miles of 
Unit Levee Status 
L627-624 Mosquito Creek Levee 14.2 Complete 1950 
L601 Watkins-Waubonsie Ditch Levees 15.0 Complete 1966 
L594 Pleasant Valley Levee 11.4 Complete 1964 
R580 Nebraska City Levee 0.2 Complete 1950 
L575 Thurman-Hamburg Levee 45.8 Complete 1950 
R573 Otto County Drainage District No. 2 5.9 Complete 1950 
R562 Peru Dike 7.6 Complete 1950 
L561-550 Atchison County Levee District No. 1 41.3 Complete 1952 
R548 Brownville-Nemaha Levee 19.5 Complete 1952 
L536 Mill Creek Levee 13.6 Complete 1952 
R520 Richardson County Drainage Dist. No. 8 6.3 Complete 1960 
R613 Papillion Creek-Platte River Levee 14.0 Complete 1971 
R616 Bellevue-Papillion Creek Levees 4.5 Under Construction 
L611-614 Mosquito-Keg Creek Levees 22.0 Under Construction 
L627, L624, Remedial Studies on Completed Units Studies Complete 
L561-550 
21-18

OMAHA, NE, DISTRICT 
MISSOURI RIVER, SIOUX CITY, IA TO RULO, NE 
TERMINAL FACILITIES 
(See Section 1 of Text) 
As of September 30, 1983 
Description of Facility 
Sioux City Municipal Dock 
Kay Dee Feed Co. (Nutra Flo) 
Big Soo Terminal Dock 
Jebro Inc. 
Sioux By-Products 
Terra Chemical International 
Farmland Industries 
Farmland Industries 
Blencoe (N.F.O.) 
Spencer Chemical (Gulf Oil Corp. Term) 
Consolidated Blenders Inc. 
Agrico Chemical Co. 
Ft. Calhoun Stone Co. Terminal 
Far-Mar-Co. 
Pentzien, Inc. 
Missouri Portland Cement Co. 
Heartland Terminal 
Greater Omaha Marina 
Cargill, Inc. Molasses Terminal 
Omaha Municipal Dock, Sioux City & New Orleans 
MacMillan Oil Co., Inc. 
Farmland Industries, Inc. 
Cargill Inc. Terminal 
Terminal Packaging Corp. 
Namalco, Inc. 
Allied Chemical Corp. 
Far-Mar-Co. 
Steinhart Bulk Plant Terminal 
Nebraska City Municipal Dock 
Bartlett Grain Co. Terminal 
Steinhart Terminal Dock 
Consolidated Blenders, Inc. 
Continental Grain Company 
Kentopp Grain Co. Terminal 
Quad State Terminal, Inc. 
PICK-SLOAN MISSOURI BASIN PROGRAM 
TABLE 21-K (See Section 19 of Text) 
Estimated Estimated 
Project Federal Cost Non-Federal Cost 
Fort Peck Lake, MT1,2 158,487,426 1,103,000 
Garrison Dam, Lake Sakakawea, ND1 300,045,651 1,624,000 
Missouri River Levee System, IA, NE, KS and MO 
(Sioux City, IA to Rulb, NE)L, 3 36,800,000 4,600,000 
Oahe Dam-Lake Oahe SD and ND1 347,373,204 2,865,000 
Big Bend Dam-Lake Sharpe, SDL,2 107,489,596 302,000 
Fort Randall Dam, Lake Francis Case, SD 1 ,2 199,072,140 1,600,000 
Gavins Point Dam, Lewis & Clark Lake, SD & NE1, 2 49,387,550 138,000 
Gavins Point Dam, Lewis & Clark Lake, SD 
& NE-Relocation of Niobrara, NE 13,516,459 - 
Omaha, NE 2 5,903,640 362,000 
Council Bluffs, IA 2 2,557,680 145,800 
Missouri River, Garrison Dam to Lake Oahe, ND 1 9,441,000 270,000 
Cherry Creek Lake, CO 1 ,2 15,214,364 161,000 
1Details presented on individual report. 2 Completed. 
21-19 
3Active portion of project. 
TABLE 21-J 
Miles 
Above 
Mouth 
731.3 
731.2 
727.8 
727.5 
727.0 
718.7 
717.0 
716.6 
680.6 
648.5 
648.2 
647.7 
640.4 
624.8 
624.5 
624.2 
624.0 
617.9 
616.3 
616.3 
614.55 
614.45 
614.4 
614.1 
612.2 
595.3 
584.5 
562.6 
562.4 
562.4 
562.3 
561.8 
535.5 
535.25 
503.0 
Bank 
Left 
Left 
Left 
Left 
Left 
Left 
Left 
Left 
Left 
Right 
Right 
Right 
Right 
Right 
Right 
Right 
Right 
Right 
Right 
Right 
Left 
Left 
Left 
Left 
Right 
Right 
Right 
Right 
Right 
Right 
Right 
Right 
Right 
Right 
Left 
Nearest Town 
Sioux City, IA 
Sioux City, IA 
Sioux City, IA 
Sioux City, IA 
Sioux City, IA 
Sioux City, IA 
Sioux City, IA 
Sioux City, IA 
Blencoe, IA 
Blair, NE 
Blair, NE 
Blair, NE 
Ft. Calhoun, NE 
Omaha, NE 
Omaha, NE 
Omaha, NE 
Omaha, NE 
Omaha, NE 
Omaha, NE 
Omaha, NE 
Council Bluffs, IA 
Council Bluffs, IA 
Council Bluffs, IA 
Council Bluffs, IA 
Omaha, NE 
Omaha, NE 
Rock Bluff, NE 
Nebraska City, NE 
Nebraska City, NE 
Nebraska City, NE 
Nebraska City, NE 
Nebraska City, NE 
Brownville, NE 
Brownville, NE 
Mound City, MO

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
INSPECTION OF COMPLETED LOCAL PROTECTION PROJECTS 
TABLE 21-L (See Section 24 of Text) 
Location Month Inspected 
Montana 
Glasgow, Milk River Aug 83 
Saco, Beaver Creek Oct 83 
Havre, Milk River Oct 83 
Havre, Scott Coulee-Bull Hook Dam Oct 83 
Clyde Park, Shields River Oct 83 
Three Forks, Lower Madison River Jun 83 
Forsythe, Yellowstone River Aug 83 
West Glendive, Yellowstone River Aug 83 
Vaughn, Sun River Oct 83 
*Yellowstone River, Water Plant. Livingston Jun 83 
*Yellowstone River, Reedpoint Bridge Inactive 
*Yellowstone River, Greycliff Bridge Jun 83 
*Yellowstone River, Springdale Bridge Inactive 
*Yellowstone River, Near Miles City 
Water Intake & Sewage Lagoon Inactive 
*Yellowstone River, Bank Protection, Billings Inactive 
*Yellowstone River, Yellowstone Co. Bridge, Near Billings Jun 83 
*Yellowstone River, Voges Bridge, Near Big Timber Jun 83 
*Jefferson River, Willow Creek Bridge, Near Three Forks Jun 83 
*Jefferson River, Bank Protection, Near Waterloo Jun 83 
*Big Hole River. Pennington Bridge, Near Twin Bridges Jun 83 
*Ruby River. Wheatly Bridge. Near Twin Bridges Jun 83 
*Big Horn River. Two Leggin Bridge. Near Hardin Inactive 
*Missouri River, Bank Stabilization. Fort Benton Jun 83 
Wyoming 
Greybull,. Big Horn River Aug 83 
Sheridan. Big and Little Goose Creeks Aug 83 
*Shoshone River, Bank Protection. Lovell Jun 83 
North Dakota 
Mandan. Lower Heart River Jun 83 
Marmarth. Little Missouri River Jun 83 
Scranton, Buffalo Jun 83 
South Dakota 
Sioux Falls. Big Sioux River Aug 83 
Belle Fourche. Belle Fourche River Sep 83 
Rapid City. Cedar Canyon Dam Sep 83 
Hot Springs. Fall River Channel Sep 83 
Herreid. Spring Creek Aug 83 
*Missouri River. Bank Protection. Greenwood May 83 
*Bad River. Bank Protection. Fort Pierre Jun 83 
*Big Sioux River, Schofield Bridge. Near Flandreau Aug 83 
*Big Sioux River. Fink Bridge. Near Flandreau Aug 83 
Rapid Creek. Rapid City Sep 83 
Sacred Heart Hospital. Yankton Jun 83 
2 1-20

OMAHA, NE, DISTRICT 
INSPECTION OF COMPLETED LOCAL PROTECTION PROJECTS 
TABLE 21-L (Continued) (See Section 24 of Text) 
Location Month Inspected 
Colorado 
Aurora, Westerly Creek-Kelley Road Dam Jul83 
*Plum Creek, Bank Stabilization, Aurora Jul 83 
*South Platte River, Bank Protection, Denver Jul83 
*Cache La Poudre River, Ft. Collins Jul 83 
Nebraska 
Omaha, Missouri River Jul 83 
Waterloo, Elkhorn River Aug 83 
West Point, Elkhorn River Jun 83 
Pierce, Elkhorn River Jun 83 
Clarkson, Middle Fork, Maple Creek Jul83 
Hooper, Elkhorn River Jun 83 
Norfolk, North Fork, Elkhorn River Jun 83 
Madison, Union & Taylor Creeks Aug 83 
*Platte River, M.U.D. Protection, Cedar Island Sep 83 
*Platte River, Bank Protection, Louisville Aug83 
*Elkhorn River, Q Street Bridge, Near Gretna Sep 83 
*Elkhorn River, Ray Bridge, Near Norfolk Jun 83 
*North Platte River, Bank Stabilization, Minatare Sep 83 
*Logan Creek, Bank Protection, Near Bancroft Jun 83 
*Battle Creek, Bank Protection, Battle Creek Jun 83 
Schuyler, Platte River Aug 83 
Schuyler, Lost Creek & Platte River Aug 83 
Little Papillion, Little Papillion Creek Jul83 
Gering Valley, Gering Drain & Tributaries Sep 83 
Macy, Blackbird Creek Sep 83 
Lincoln, Salt Creek & Tributaries Aug 83 
Meadow Grove, Buffalo Creek Jun 83 
Columbus, Loup River Apr 83 
Broken Bow, Mud Creek Apr 83 
*Tangeman, Little Nemaha River Jul 83 
*Julian, Rock Creek Jul83 
Iowa 
Council Bluffs, Missouri River Sep 83 
Ida Grove, Maple River-Odebolt Creek Jun 83 
Sioux City, Floyd River Aug 83 
Hawarden, Dry Creek Sep 83 
Hamburg L575, Nishnabotna River Aug 83 
Intercounty D.D., Little Sioux River Aug 83 
Nagel D.D., Little Sioux River Aug 83 
Bennett-McDonald-Smithland D.D., Little Sioux River Aug 83 
*West Nishnabotna River, Mills Co. Bridge, Near Malvern Mar 83 
*West Nishnabotna River, Mills Co. Bridge, Near Hastings Mar 83 
*East Nishnabotna River, Page Co. Bridge, Near Essex May 83 
*Missouri River, Marina, Sioux City Aug 83 
*West Nishnabotna River, Near Hancock Mar 83 
*East Nishnabotna River, Near Griswold Jul83 
21-21

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
INSPECTION OF COMPLETED LOCAL PROTECTION PROJECTS 
TABLE 21-L (Continued) (See Section 24 of Text) 
Location Month Inspected 
Missouri River Levees 
L624 & L627, Mosquito Creek & Sieck Levees 
L601, Watkins Levee District 
L601, Miller-Sturgeon Levee District 
L601, Missouri River Levee District #1 
L594, Waubansie Drainage District 
L594, Pleasant Valley Levee District 
L675, Benton-Washington Levee District 
L575, Northwest Atchison Levee District 
L575, McKissock Island Levee District 
L575, Buchannan Levee District 
L561, L550, L536, Atchison County Levee District 
R613, Sarpy Co. Soil & Water Cons. D. 
R562, Peru Levee District 
R548, Brownville-Nemaha Levee District 
R548, Little Nemaha Levee District 
R520, Richardson Co. Levee Dist. #8 
R573, Otoe County Drainage Dist. #2 
*Denotes Section 14 Projects 
FLOOD CONTROL ACTIVITIES UNDER SPECIAL AUTHORIZATION 
TABLE 21-M (See Section 26 of Text) 
Study 
Fiscal Year 
Cost 
(Flood Control Activities Pursuant to Section 205, Public Law 858, 
80th Congress, as Amended) (Preauthorization) 
Lost Creek, Columbus, NE $1,165,133 
Pebble Creek, Scribner, NE $39,681 
West Nishnabotna River, Red Oak, IA $402,380 
Lodgepole Creek, Sidney, NE $78,959 
Indian Creek, Emerson, IA $29,507 
Indian Creek, Emerson, IA - Jobs Bill $17,769 
TOTAL $1,733,329 
21-22 
Aug 83 
Jul 83 
Jul 83 
Jul 83 
Jul 83 
Jul 83 
Aug 83 
Aug 83 
Aug 83 
Aug 83 
Sep 83 
Sep 83 
Aug 83 
Jun 83 
Sep 83 
Aug 83 
Aug 83

OHIO RIVER 
For actual construction of locks and dams, and 
operation and care of completed structures, riveris divided 
into three sections under immediate supervision and 
direction of district engineers at Pittsburgh, Huntington 
and Louisville. Pittsburgh section extends 127 miles from 
head of river at Pittsburgh, Pa., to a point immediately 
upstream from New Martinsville, W. Va., and includes 
Emsworth, Dashields, Montgomery, New Cumberland, 
Pike Island and Hannibal locks and dams. Huntington 
section extends 311 miles from mile 127 to 438 immediately 
upstream from Foster, Ky., and includes Willow 
Island, Belleville, Racine, Gallipolis, Greenup and Captain 
Anthony Meldahi locks and dams. Louisville section 
extends 543 miles from mile 438 to mouth of river, and 
includes Markland and McAlpine locks and dams (with 
Louisville and Portland Canal) Cannelton, Newburgh, 
Uniontown and Smithland locks and dams and locks and 
dams 52 and 53. 
IMPROVEMENTS 
Navigation 
1. Construction of locks and dams on Ohio 
River .......................... 22-1 
2. Open channel work, Ohio River ...... 22-3 
Tables 
Table 22-A Cost & Financial Statement... 22-5 
Table 22-B Authorizing Legislation ...... 22-6 
Table 22-C Not Applicable 
Table 22-D Not Applicable 
Table 22-E Not Applicable 
Table 22-F Not Applicable 
Table 22-G Not Applicable 
Table 22-H Construction of Locks and Dams 
on Ohio River, Total Cost 
of Existing Project ........ 22-6 
Table 22-I Federal Energy Regulatory 
Commission Licenses of 
Locks and Dams, Ohio River .. 22-6 
Table 22-J Ohio River Locks and Dams 
Statistics ................. 22-7 
Navigation 
1. CONSTRUCTION OF LOCKS 
AND DAMS ON OHIO RIVER 
Location. Ohio River is formed by junction of Allegheny 
and Monongahela Rivers at Pittsburgh, Pa., and flows 
generally southwesterly for 981 miles to join Mississippi 
River near Cairo, Ill. For description of river see page 
1227, 1932 Annual Report. 
Previous projects. For details see page 1907 of Annual 
Report for 1915. 
Existing project. Provides for improvement of entire 
river by construction of locks and dams to provide a 
channel depth of 9 feet and for widening Louisville and 
Portland Canal at Louisville, Ky. Project provides for a 
lock with usable dimensions of 110 by 600 feet at each of 
the dams and, in addition, an auxiliary lock 56 by 360 feet 
is available at Emsworth, Dashields, Montgomery, and 
McAlpine locks and dams with an auxiliary lock at 
Gallipolis being 110 by 360 feet. Dashields is a fixed dam, 
while Emsworth, Montgomery, and Gallipolis are fixed 
dams with movable crests. Remaining dams are movable 
type, with navigable pass varying in width from 600 to 
1,248 feet. In addition to navigable pass, movable-type 
dams are also provided with one or more regulating weirs. 
At McAlpine locks and dam a canal (Louisville, and 
Portland) extends along left bank for 2 miles, with locks at 
lower end. Modifications to existing project under purview 
of Section 6, March 3, 1909 Act, provide for fixed dams 
with movable crests with two locks (110 by 1,200 feet and 
110 by 600 feet) at New Cumberland, Pike Island, 
Hannibal, Willow Island, Belleville, Racine, Greenup, 
Captain Anthony Meldahl, Markland, Cannelton, 
Newburgh and Uniontown, two locks 110 by 1,200 feet at 
Smithland, 110 by 1,200 foot temporary locks in addition 
to the existing locks at locks and dams 52 and 53, and 
reconstruction to provide a 110 by 1,200 foot lock in 
addition to existing locks and a fixed dam with two 
sections of movable crest at McAlpine locks and dam, 
widening Louisville and Portland Canal to 500 feet. 
Rehabilitation of existing locks and dams 52 and 53 was 
started in September 1979 under the purview of Section 6, 
March 1909 Act. Mound City was also considered 
authorized under purview of 1909 Act, and 
preconstruction planning was performed in the period 
1965 to 1972. The ruling of the U.S. District Court, 
District of Columbia, on September 6, 1974, with reference 
to Lock and Dam 26, Mississippi River, would also apply 
to this project. Consequently, it is no longer considered 
22-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
authorized. Operation and care of locks and dams were 
included in project July 1, 1935, under provisions of 
Permanent Appropriations Repeal Act of June 26, 1934. 
Estimated Federal cost of new work (existing 
project)(1983), exclusive of Gallipolis locks and dam 
reported under Kanawha River project is $1,778,840,999, 
estimated non-Federal cost is $14,999,000. Foregoing 
estimate does not include expenditures on previous 
projects. Various items previously included in this project 
are considered inactive or unnecessary and are excluded 
from foregoing cost estimate. See page 693, Annual 
Report, 1968 for items and estimated cost. Under 
authority of 1910 River and Harbor Act, Louisville and 
Portland Canal was widened to 200 feet; locks and dams 
40 and 42 eliminated; locks and dams 1 and 2 replaced by 
Emsworth locks and dam; lock and dam 3 replaced by 
Dashields locks and dam; and locks and dams 4,5 and 6 replaced 
by Montgomery locks and dam. Locks and dams 
24, 25 and 26 were replaced by Gallipolis locks and dam 
authorized by August 30,1935 Act, and constructed under 
project for improving lower Kanawha River. Locks and 
dams 7, 8 and 9 were replaced by New Cumberland locks 
and dam, locks and dams 10 and 11 were replaced by Pike 
Island locks and dam, locks and dams 12, 13 and 14 were 
replaced by Hannibal locks and dam, locks and dams 15, 
16 and 17 were replaced by Willow Island locks and dam, 
locks and dams 18, 19 and 20 were replaced by Belleville 
locks and dam, locks and dams 21,22 and 23 were replaced 
by Racine locks and dam, locks and dams 27, 28, 29 and 30 
were replaced by Greenup locks and dam, locks and dams 
31, 32, 33 and 34 were replaced by Captain Anthony 
Meldahl locks and dam, locks and dams 35, 36, 37, 38 and 
39 were replaced by Markland locks and dam, the 
Louisville and Portland Canal at McAlpine locks and dam 
was widened to 500 feet. Locks and dams 43, 44 and 45 
were replaced by Cannelton locks and dam, presently 
under construction, locks and dams 46 and 47 were 
replaced by Newburgh locks and dam presently under 
construction, locks and dams 48 and 49 were replaced by 
Uniontown locks and dam presently under construction, 
and locks and dam 50 and 51 were replaced by Smithland 
locks and dam, presently under construction, as 
modifications to existing project under purview of Section 
6, March 3, 1909 Act, reducing total number of structures 
to 20. The Water Resources Development Act of 1974 
combined the Newburgh Bank Protection Works project 
with the Newburgh locks and dam project. A December 
1981 Act established the Falls of the Ohio National 
Wildlife Conservation Area near McAlpine locks and dam 
to protect and preserve existing fossilized coral and a 
diversity of wildlife. Table 22-J contains data relative to 
various features of locks and dams included in existing 
projects. For list of principal towns and cities along Ohio 
River with their mileage below Pittsburgh, PA, see page 
1060, 1962 Annual Report. See Table 21-I for licenses. 
Navigation system of 21 locks and dams is in operation 
and 9-foot navigation throughout length of river is 
generally available at all times. At certain unstable bars 
project depth is maintained by dredging, supplemented by 
contraction works. (See "Open Channel Work, Ohio 
River.") Table 22-J shows cost and year completion of 
locks and dams now in operation. Existing project does 
not provide adequate facilities for present day navigation 
due to obsolescence of structures. Since repair and 
modernization of these facilities would be extremely 
costly, replacement and reconstruction is being 
accomplished as rapidly as funds are made available for 
the purpose. Construction of lock and dam replacement 
program was initiated in fiscal year 1955. New 
Cumberland, Pike Island, Hannibal, Willow Island, 
Belleville, Racine, Greenup, Captain Anthony Meldahl, 
Markland, McAlpine, Cannelton, Newburgh, Uniontown 
and Smithland replacement locks and dams are in 
operation, replacing 39 old low-lift locks and dams. For 
Total cost of existing project, see Table 22-H. 
Terminal facilities. Modern public terminals, with 
warehouses, equipped with operating machinery for 
transferring materials, have been constructed by private 
interests at some of the larger cities and towns. A list of 
terminals on Ohio River is revised annually and can be 
obtained from Division Engineer, U.S. Army Engineer 
Division, Ohio River, Cincinnati, Ohio. 
Operations during fiscal year. New work by contract 
and hired labor: 
Emsworth locks an dam (Rehabilitation): Upper lock 
miter gates, 110-goot chamber, were installed by hired 
labor in October 1981. Contract for Locks and Dams 
Rehabilitation, awarded Oct 15, 1981, progressed to 89 
percent completion. Dam work included: placing stone 
erosion protection downstream of both back channel and 
main channel, structurally rehabilitating all 14 dam gates, 
painting of the service bridge on main channel dam and 
painting dam gates on the back channel. Lock work 
included: rehabilitation of the river chamber and land 
chamber including all lock machinery. Expenditures 
during FY 1983 for real estate acquisition and 
coordination, construction and engineering and design of 
remaining project was $14,723,736. 
Montgomery locks and dam (Rehabilitation): A supply 
contract was awarded in August 1983 for $1,354,116 for 
fabrication of lock miter gaes, 110-foot chamber. 
Remaining work includes awarding contracts for: Upper 
guard wall cells, 56-foot lock gate fabrication, emergency 
bulkhead fabrication for dam and major rehabilitation of 
locks and dam with an overall scheduled completion date 
of September 1987. Expenditures during FY 83 for 
construction and engineering and design of remaining 
project was $25,000. 
Willow Island locks and dam: Construction initiated in 
January 1967 is complete. A total of $210,976 was 
expended during the fiscal year for engineering studies 
and real estate settlements. 
Belleville locks and dam: Construction work complete 
except for additional recreation facilities under the 
completed projects program. 
Racine locks and dam: Construction initiated in June 
1964 is complete. 
Gallipolis locks and dam: The existing project, 
constructed under project for improving lower Kanawha 
River, was placed in operation in August 1937. The 
dimensions of the existing lock chambers and poor 
approach conditions, particularly to downstream traffic, 
have created a higher than normal accident rate to the 
22-2

OHIO RIVER 
structure with corresponding hazards and delays to traffic. 
The Water Resources Development Act of 1976 authorized 
Phase I studies for a single 1,200 foot lock in a bypass 
canal. These studies are underway. 
Greenup locks and dam: Construction work complete 
except for additional recreation facilites under the 
completed projects program. During the period $393,140 
was expended under the recreation at completed projects 
program. 
Captain Anthony Meldahl locks and dam: Construction 
work complete. 
Markland locks and dam: Project is complete including 
a public highway bridge across the navigation structure, 
as authorized by the Federal-Aid Highway Act of 1970 
(Public Law 91-606). For details of bridge see page 22-3 of 
Annual Report for 1978. 
Falls of the Ohio National Wildlife Conservation Area 
was authorized by (Public Law 97-137) on December 29, 
1981. The Conservation Area will protect 1,000 acres 
which consists of birdlife and other wildlife. Planning 
Development was initiated in September 1983. 
McAlpine locks and dam: Project is complete except for 
alteration of lift section of railroad bridge that spans the 
upper end of the Louisville and Portland canal which work 
is presently deferred. 
Cannelton locks and dams: Project was completed 
except for settlement of a inverse condemnation case: 
$67,071. 
Newburgh locks and dams: Project was completed 
except for extended warranty for the centralized remote 
control and surveillance system: $136,008. 
Uniontown locks and dams: Project remained at 99 
percent complete. Land acquisition is complete except for 
continuing action on Declarations of Taking on several 
tracts. One remaining contract at a boat ramp for 
landscaping was advanced to 46 percent completion. 
$87,105. 
Smithland locks and dams: All major construction 
features are complete and the project was advanced to 96 
percent completion. Land acquisition advanced to 97 
percent completion. Final payment on the completed dam 
contract has not been made pending settlement of all 
claims. Contract for fabrication of floating mooring bitt 
extensions was completed. Contract for replacement 
bridge access road - Dyer Hill Creek awarded in October 
1982 was completed. Alterations to Rosiclare, IL drainage 
and water structures and Millstone, IL Water District 
facilities were advanced to 92 percent and 64 percent 
completion respectively. Contracts for paving access road 
and relocation of Golconda, IL boat launching ramp were 
awarded in August and September 1983 respectively. 
Engineering and design of remaining project features was 
continued: $3,202,884. 
Locks and Dam No. 52 (New Lock): Construction 
initiated in December 1967 is complete 
Locks and Dam No. 53 (Temporary Lock): Construction 
initiated in December 1972 is complete. 
Locks and Dam No. 52 (Rehabilitation): Project is 82 
percent complete. Four supply contracts for wicket 
assemblies and hurters were completed. Contract for 
fabrication of miter gates was completed; however final 
payment has not been made pending completion of minor 
corrections. Contract to restore dam pier No. 1 and lock 
structures was advanced to 84 percent completion. 
Contract for storage building was awarded in April 1983 
and advanced to 90 percent completion. Hired labor 
installation of dam wicket assemblies and hurters and 
locks miter gates were initiated and advanced to 10 
percent and 29 percent completion respectively. 
Engineering and design of remaining project features was 
continued: $1,786,035. 
Locks and Dam No. 53 (Rehabilitation): Project is 51 
percent complete. Four supply contracts for wicket 
assemblies and hurters were completed. Contract for 
fabrication of miter gates was completed; however, final 
payment has not been made penidng completion of minor 
corrections. Contract to restore machinery and equipment 
for 600-foot lock was advanced to 60 percent completion. 
Hired labor installation of dam wicket assemblies and lock 
miter gates were initiated and advanced to 4 percent and 
53 percent completion respectively. Engineering and 
design of remaining project features was continued: 
$801,077. 
Operation and maintenance, general. Locks and dams 
operated as required and necessary repairs and 
improvements made thereto and to operator's quarters, 
grounds and esplanades. A contract was awarded for 
$1,303,684 in August 1983 for fabrication of lock miter 
gates, 110-foot chamber, Dashields locks and dam, and a 
feature design memorandum for construction of an access 
road at Dashields was approved by OCE on July 11, 1983. 
Costs were $8,061,083 for Pittsburgh District, $9,884,343 
for Huntington District and $12,365,645 for Louisville 
District. 
2. OPEN CHANNEL WORK, OHIO RIVER 
Location. Under jurisdiction of district engineer in 
whose district the work is located. Portion of river 
included in project extends 974.7 miles from head of river 
at Pittsburgh, Pa., to mouth of Cache River (Mound City, 
Ill.). Open channel improvement from mouth of Cache 
River to mouth of Ohio River is under jurisdiction of 
Mississippi River Commission. 
Existing project. Before completion of canalization 
project, no project depth had been fixed by Congress 
under project for open channel work, but in order to 
properly aid packet and barge navigation it was necessary 
to secure a low-water channel with a minimum depth of 
from 4 to 6 feet, and a width, depending upon difficulty of 
running channel, of from 400-600 feet; also to permit 
movement of large coal tows, which movement occurred at 
stages of water exceeding 10 feet, it was necessary to 
remove points of projecting bars which formed at various 
locations along river. Accomplishment of this purpose 
involved concentration of current by closing back channels 
at islands with low dams, contraction and straightening 
wide open channels by low dikes, dredging bars and 
shoals, and removal of snags and wrecks. Incidental to 
direct improvement of Ohio River is construction and 
maintenance of ice piers as required for protection of river 
craft. Stage of extreme high water on Ohio River varies 
from 46 feet at Pittsburgh, Pa., to 80 feet at Cincinnati, 
Ohio, with 57.2 feet at Louisville, Ky. (head of falls), 53.8 
22-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
feet at Evansville, Ind., and 59.5 feet at Cairo, Ill. (mouth 
of river). Estimated cost of new work (1960) is $16,160,000, 
exclusive of following items which are considered inactive: 
Ice piers authorized by 1927 River and Harbor Act; 
reforestation of sloughs on Kentucky Peninsula near 
Evansville, Ind., authorized by 1930 River and Harbor 
Act; dredging to widen channel at certain points; and 
placing revetment at various points. Estimated cost of 
these items (1954) is $6,565,000. Operation of snag boats 
on Ohio River below Pennsylvania State line was included 
in project July 1, 1935, under provisions of Permanent 
Appropriations Repeal Act of June 26, 1934. See Table 
22-B for authorizing legislation. 
New Work under this project is substantially complete, 
since it is not anticipated that work on inactive portion of 
project will be accomplished. In addition to dredging, local 
stabilization of channel has been effected at various points 
by construction of dikes and revetment. Work which 
remains consists of dredging to widen channels at certain 
points to project depth. 
Local cooperation. River and Harbor Act of January 21, 
1927, authorizing construction of ice piers for general open 
channel work, imposes condition that before work is begun 
on any pier, local interests convey to the United States 
free of cost such riparian rights as may be deemed necessary 
in connection with the improvement at locality (H. 
Doc. 187, 67th Cong., 2nd sess.). Existing ice piers are 
adequate for present purposes and local cooperation is not 
needed since no additional construction is under consideration. 
River and Harbor Act of July 3, 1930, provides for 
reforestation of sloughs of Kentucky Peninsula and bank 
protection and that no expense shall be incurred by the 
United States for acquiring lands required for purpose of 
this improvement (H. Doc. 409, 69th Cong., 1st sess.). 
However, since no serious overbank erosion has occurred 
since bank revetment in 1933-34, reforestation is not 
considered justifiable at this time and no local cooperation 
is required. 
Operations during fiscal year. Operation and 
maintenance, general: Dredging was done where required 
to provide an adequate and dependable channel of project 
depth at minimum pool condition. Dikes and revetments 
were maintained and routine work of maintaining navigation 
aids, removing snags, making channel studies, 
hydrographic surveys and mapping was performed as 
required. Channel soundings, hydrographic surveys, 
stream gaging operations, channel inspections and aids to 
navigation, and miscellaneous inspections and reports cost 
$1,007,929. There was no dredging by hired labor on the 
Ohio River in FY 83. Dredging by contract: Pittsburgh 
District 60,800 cubic yards at $342,695. Huntington 
District 642,065 cubic yards at $1,814,446 and Louisville 
District 652,730 cubic yards at $1,314,138. 
22-4

OHIO RIVER 
TABLE 22-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost To 
In Text Project Funding FY 80 FY 81 FY 82 FY 83 Sept. 30, 1983 
1. Construction of New Work 
Locks and Dams Approp. 12,511,848 12,298,533 7,457,298 2,350,759 1,380,144,262 8 s1 10 17 
on Ohio River Cost 15,780,604 13,090,919 6,156,450 4,099,831 1,377,619,971 1 8 6 1112 1 16 18 
Maint. 
Approp. 24,895,869 22,960,200 28,416,500 31,744,300 489,339,030 2 4 19 
Cost 24,027,531 23,594,858 27,648,805 30,311,071 486,729,681 2 18 14 s0 21 
Rehab. 
Approp. 1,924,000 8,709,000 15,400,000 15,897,572 42,570,572 
Cost 1,325,554 6,348,682 15,059,290 17,335,848 40,079,667 
2. Open Channel New Work 
Work, Ohio River Approp. - - - - 15,962,260 6 
Cost - - - - 15,962,260 8 
Maint. 
Approp. 4,252,076 4,345,200 5,378,100 4,440,300 93,813,663 ' 
Cost 4,654,642 3,776,592 5,759,040 4,479,208 93,141,467 ' 
Rehab. 
Approp. - - - - 944,649 
Cost - - - - 944,649 
1. Includes $17,003,761 for previous 6-foot canalization 
project. 
2. Includes $36,943,217 expended from 1885 to 1937 on 
operation and care of work of improvement under provisions 
of permanent indefinite appropriations for such purposes. 
3. Includes $215,812 public works acceleration, executive 
1963. 
4. Includes $38,766 public works acceleration, executive 
1963. 
5. Excludes $251,769 contributed funds for new work. 
6. Excludes $250,102 contributed funds for new work. 
7. Excludes $1,621,349 expended in operation of snag boats 
under provisions of permanent indefinite appropriation for 
such purposes, and $267 transferred to project without 
reimbursement. 
8. Includes $1,040,236 Public Works funds. 
9. Includes $1,000 for removal of obstructions in Licking 
River under authority of Section 3, R&H Act of 1930. 
10. Includes $100,000 placed in FY 1971 Budget Reserve. 
11. Excludes $3,899 transferred from project without 
reimbursement. 
12. Surplus property valued at $3,553 transferred to project 
without reimbursement. 
13. Excludes $2,140 transferred to project without 
reimbursement. 
14. Excludes surplus property valued at $73,832 transferred 
to project without reimbursement. 
15. Includes $87,724,158 prior construction cost. 
16. Excludes surplus property valued at $297,385 
transferred to project without reimbursement. 
17. Includes $549,392 Code 710 Funds, $572,162 Code 711 
Funds, $532,677 Code 712 Funds and $1,759,812 Code 713 
Funds. 
18. Includes $549,392 Code 710 Funds, $342,162 Code 711 
Funds, $532,677 Code 712 Funds and $1,365,952 Code 713 
Funds. 
19. Includes $2,383,000 Funds provided from The 
Productive Employment Appropriations Act of 1983 
(PL 98-8). 
20. Includes $1,164,465 Funds provided from The 
Productive Employment Appropriations Act of 1983 
(PL 98-8). 
21. Includes $920,945 cost for operations and care of 
previous projects. 
22-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 22-B AUTHORIZING LEGISLATION 
See Date of 
Section Authorizing 
In Text Act Project and Work Authorized Documents 
2. Open Channel Work, Ohio River 
March 3, 1827 Project adopted by this act originally covered entire length 
of Ohio River from its mouth near Cairo to Pittsburgh, a 
distance of 981 miles. It provided for removal of all obstructions 
which tend to endanger steamboat navigation. 
Jan. 21, 1927 Construct ice piers as a part of project, with funds allotted H. Doc. 187, 67th Cong., 2nd sess. 
from appropriations for general open channel work. 
July 3, 1930 Reforestation of sloughs on Kentucky Peninsula near Evans- H. Doc. 409, 69th Cong., 1st sess. 
ville, Ind., and a 200-foot strip along bank and for 
bank protection, at an estimated cost of $200,000. 
July 3, 1958 Act of Mar. 3, 1827 modified to include maintenance of exist- H. Doc 434, 84th Cong., 2nd sess. 
ing Licking River Channel within lower 3-mile limit of River 
slack water, at an estimated increase of $1,000 in cost of 
average annual maintenance. 
Locks and Dams, Ohio River 
Dec. 29, 1981 Act of Dec. 29, 1981 established the 1,000 acre falls of the H.R. 2241, PL 97-137, Title II, 
Ohio National Wildlife Conservation Area, at a cost not to 95 Stat. 1710 
exceed $300,000. 
CONSTRUCTION OF LOCKS AND DAMS ON OHIO RIVER 
TOTAL COST OF EXISTING PROJECT TO SEPTEMBER 30, 1983 
TABLE 22-H (See Section 1 of Text) 
O~erations and 
Maintenance 
Funds New Work General Rehabilitation Total 
Regular 1,285,222,796 445,983,064 40,079,667 1,771,285,527 
Public Works 3,258,368 3,258,368 
Emergency Relief 1,198,837 19,000 1,217,837 
Maintenance & Operation 2,824,689 2,824,689 
Public Works Acceleration 215,812 38,766 254,478 
Executive 1963 
Total 1,289,895,813 1 6 8 448,865,519 2 " 40,079,667 1,778,840,999' 
1. Excludes surplus property valued at $297,385 transferred 5. Excludes $902,945 cost for operation and care of previous 
to project without reimbursement projects. 
2. Excludes surplus property values at $73,832 transferred 6. Excludes $3,899 transferred from project without 
to project without reimbursement. reimbursement. 
3. Excludes $250,118 contributed funds for new work. 7. Excludes $2,140 transferred to project without 
4. Excludes $36,943,217 expended from 1885 to 1937 under reimbursement. 
permanent indefinite appropriation. 8. Excludes $87,724,158 prior construction cost. 
FEDERAL ENERGY REGULATORY COMMISSION LICENSES 
TABLE 22-I AT LOCKS AND DAMS, OHIO RIVER 
Markland Dam McAlpine Dam Racine Dam Greenup Dam 
F.E.R.C. License 2,211 289:1,000 2,570 2,614 
License Public Service Co. Louisville Gas and Ohio Power Co. City of Vanceburg, 
of Indiana Electric Co. Kentucky 
Annual Charge $45,950.00 $95,000.00 $50,000.00 $227,900.00 
Collections to end of 
Fiscal Year 1983 $733,311.64 $5,225,311.20 $14,326.00 -0- 
22-6

TABLE 22-J OHIO RIVER LOCKS AND DAMS 
(See Section 1 of Text) 
Lock Dimensions Upper 
Normal 
Greatest Pool 
Length Elevation Depth on 
Width Available (feet, Miter Sills Actual Cost 
Lock Miles of For Full mean Character of Foundation Year to Date of 
and Below Distance From Chamber Width Lift sea Upper Lower Percent Opened to Each Lock 
Dam Pittsburgh Nearest Town (feet) (feet) (feet) level) (feet) (feet) Lock Dam Complete Navigation and Dam 
1. - Replaced 
6.2 Emsworth locks and dam, 110 
Emsworth, PA 56 
2. - Replaced 
3. - Replaced 
13.3 Dashields locks and dam, 110 
1.6 miles below 56 
Sewickley, PA 
- Replaced 
- Replaced 
- Replaced 
31.7 Montgomery locks and dam, 110 
1.4 miles above 56 
Industry, PA 
- Replaced 
- Replaced 
54.4 New Cumberland locks and 110 
dam, Stratton, OH 110 
- Replaced 
- Replaced 
- Replaced 
84.3 Pike Island locks and dam, 110 
2 miles upstream from 110 
Warwood, WV 
- Replaced 
- Replaced 
14. - Replaced 
126.4 Hannibal locks and dam, 
1.6 miles upstream from 110 
New Martinsville, WV 110 
15. - Replaced 
16. - Replaced 
161.7 Willow Island locks and 
dam, 2.7 miles above 110 
Waverly, WV 110 
600 
360 
18.0 710.0 
600 
360 10.0 692.0 
600 
360 17.5 682.0 
17.0' 4 12.9 
15.5' 12.9' 
13.4' 17.5' 
Rock Rock and piles 100 
Rock Rock 
- $ 870,034 
1921 35,741,975 2 4 
100 1929 
16.0' 14.6 Rock and piles Rock and piles 100 1936 
976,767 
1,144,588 
3,533,076 
1,071,472 
1,080,132 
1,123,442 
5,762,611 4* 
1,075,000 
1,167,456 
1,200 
600 20.5 664.5 
1,200 
600 21.0 644.0 
7.0' 14.8' 
17.0' 18.0' 
Rock 
Rock 
Rock 
Rock 
100 1959 39,099,688 
- -1,177,100 
- -1,138,000 
- -1,162,165 
100 1968 56,623,946 
1,166,104 
1,222,389 
1,133,371 
1,200 
600 21.0 623.0 
o .- � 
38.0 17.0 Rock Rock 
1,200 
600 20.0 602.0 35.0 15.0 Rock and piles Rock 
99 1972 87,574,520 
- 1,180,478 
- 1,275,532 
98 1972 76,454,393 
O
0 
4. 
5. 
6. 
7. 
8. 
9. 
10. 
11. 
12. 
13.

TABLE 22.J 
(Continued) 
OHIO RIVER LOCKS AND DAMS 
(See Section 1 of Text) 
Lock Dimenelons Upper 
Normal 
Greatest Pool 
Length Elevation Depth on 
Width Available (feet, Miter Sills Actual Cost 
Lock Miles of For Full mean Character of Foundation Year to Date of 
and Below Distance From Chamber Width Lift sea Upper Lower Percent Opened to Eaeh ck 
Dam Pittsburgh Nearest Town (feet) (feet) (feet) level) (feet) (feet) Lock Dam Complete Navigation and Dam 
17. - Replaced - - - - $ 1,362,591 
18. 
19. 
20. 
927,091 
1,213,848 
936,696 
110 
110 
1,200 
600 22.0 582.0 37.0 15.0' Rock and piles Rock 100 1968 62,591,255 
1,484,562 
1,218,798 
1.851.488 
110 
110 
1,200 
600 22.0 560.0 18.0 15.0 Rock and piles Rock 98 1971 64,922,680 
1,187,542 
1,925,205 
1,307,241 
110 
110 
600 
360 26.0 538.0 18.0 12.0 Rock Rock 100 1937 
- Replaced 
103.9 Bellevlle locks and dam, 
0.3 mile below 
Reedsville, OH 
- Replaced 
- Replaced 
- Replaced 
237.5 Racine locks and dam, 
1.5 miles below 
Letart Falls, OH 
- Replaced 
- Replaced 
279.2 Gallipolis locks and dam, 
0.7 mile below 
Hogsett, WV 
Gallipolis Modernization 
- Replaced 
- Replaced 
-Replaced 
- Replaced 
341.0 Greenup locks and dam, 
4.9 miles below 
Greenup, KY 
Replaced 
- Replaced 
- Replaced 
110 
110 
21. 
22. 
23. 
24. 
25. 
26. 
27. 
28. 
29. 
30. 
31. 
32. 
33. 
34. 
1,200 
600 30.0 515.0 18.0' 13.0 Rock Rock 100 1959 56,840,331 
1,359,231 
2,951,216 
1,937,166 
3,437,057 
1,200 
600 30.0 485.0- 18.0' 15.0 Rock Rock 100 1962 74,188,216 
1,436,465 
2,015,601 
1,063,133 
1,088,802 
1,579,618 
- Replaced 
436.2 Captain Anthony Meldahl 110 
locks and dam, 2.2 miles 110 
above Foster, KY 
0
OE

TABLE 22-J 
(Continued) 
OHIO RIVER LOCKS AND DAMS 
(See Section 1 of Text) 
Lock Dimensions Upper 
Normal 
Greatest Pool 
Length Elevation Depth on 
Width Available (feet, Miter Sills Actual Cost 
Lock Miles of For Full mean Character of Foundation Year to Date of 
and Below Distance From Chamber Width Lift sea Upper Lower Percent Opened to Each Lock 
Dam Pittsburgh Nearest Town (feet) (feet) (feet) level) (feet) (feet) Lock Dam Complete Navigation and Dam 
35. - Replaced- 
36. - Replaced- 
37. - Replaced- 
38. - Replaced- 
531.5 Markland locks and dam, 110 
1 mile above Markland, IN 110 
39. - Replaced- 
40. - Eliminated 
41. - - - 
Falls of the Ohio, 1 mile N/A 
above McAlpine 
604.0 McAlpine locks and dams 110 
(Reconstruction of locks 110 
and dam 41.) 56 
42. - Eliminated- 
43. - Replaced- 
44. - Replaced- 
45. - Replaced- 
720.7 Cannelton locks and dam 110 
3 miles above 110 
Cannelton, IN 
46. - Replaced- 
776.1 Newburgh locks and dam, 110 
16 miles above 110 
Evansville, IN 
47. - Replaced- 
48. - Replaced- 
49. - Replaced- 
846.0 Uniontown locks and dam, 110 
3.5 miles below 110 
Uniontown, KY 
50. - Replaced- 
51. - Replaced- 
918.5 Smithland locks and dam, 110 
2 miles above 110 
Smithland, KY 
52. 938.9 1.4 miles below Brookport, IL 110 
938.9 1.4 miles below Brookport, IL 110 
(New lock) 
1,200 
600 35.0 455.0 50.0 15.0 
N/A N/A N/A N/A N/A 
1,200 
600 
360 
37.0 420.0 
- - 
1,200 25.0 
600 
383.0 
1,200 
600 16.0 358.0 
1,200 
600 22.0 342.0 
1,200 
1,200 22.0 324.0 
600 12.0 302.0 
1,200 12.0 302.0 
49.0 12.0 
19.0 11.0 
19.0 11.0 
Rock 
N/A 
Rock 
38.0 13.0 Rock 
32.0 16.0 Rock 
34.0 12.0 Rock 
34.0 12.0 
15.4 11.0 
15.4 11.0 
Rock 
Pile 
Pile 
Piles 
N/A 
Rock 
Rock 
100 1963 63,019,403 
- - 2,222,448 
- - 7,658,134 ' 
0 N/A 2,690 
100 1961 45,726,189' 
- - 2,592,242 
- - 2,819,930 
- - 3,202,890 
99 1972 98,956,114 1 
Pile 99 1975 104,308,659 
Rock 
Rock 
Pile 
Pile 
99 1975 
95 
100 
100 
1980 266,408,276 
1928 11,569,147 " 
1969 10,197,516 
1,894,942 
3,704,535 
1,297,924 
2,857,040 
0gMa 
3,129,028 
4,415,526 
3,062,710 
3,325,964 
100,043,581 
3,751,762 
4,370,566 
*

TABLE 22-J 
(Continued) 
OHIO RIVER LOCKS AND DAMS 
(See Section 1 of Text) 
Lock Dimensions Upper 
Normal 
Greatest Pool 
Length Elevation Depth on 
Width Available (feet, Miter Sills Actual Cost 
Lock Miles of For Full mean Character of Foundation Year to Date of 
and Below Distance From Chamber Width Lift sea Upper Lower Percent Opened to Each Lock 
Dam Pittsburgh Nearest Town (feet) (feet) (feet) level) (feet) (feet) Lock Dam Complete Navigation and Dam 
53. 962.6 10.8 miles above 110 600 13.4 290.0 15.4 9.6' Pile Pile 100 1929 $ 8,477,725 " 
Mound City, IL 15.4 9.6 Pile - 98 - 38,570,920 
962.6 10.8 miles above 110 1,200 13.4 290.0 - - - - 1,539,470 " 
Mound City, IL (New lock) 
974.2 Mound City lock and dam, - - - - - 
1 mile below Mound City, IL - - - . 
54. 974.2 Mound City, IL - - 1,410,705,403 " 
TOTAL 
1. Depths are on emergency dam foundation and are controlling depths. 
2. Change from fixed dam to lift-gate dam completed in 1938. 
3. Depths are on poiree dam foundation and are controlling depths. 
4. Land chamber. 
5. River chamber. 
6. Rollergate dam. Cost not included in total. Constructed under project for 
improving lower Kanawha River. 
7. Lock and dam 41 completed with 110- by 600-foot lock in 1921. Completed 
with new dam and raised canal and lock wall in 1928. Auxiliary 56- by 360-foot lock 
constructed in 192930. Reconstruction and modernization began 1956, renamed 
McAlpine locks and dam in 1960. Operation of auxiliary lock suspended in 1971. 
8. Completed except for deferred alteration of railroad bridge. 
9. Dam below not yet constructed. Depth on lower miter sill at lower water. 
10. Reflects reduction of $2,219,975 payment for settlement of damage to dam 
caused by barge accident in April 1978. 
11. Includes $7,107,400 for major rehabilitation project initiated in FY 1979. 
12. Includes $3,067,057 for major rehabilitation project initiated in FY 1979. 
13. For preconstruction planning 1965 to 1972. No longer considered authorized. 
See Section 1 of text. 
14. Includes $29,880,211 for major rehabilitation initiated in FY 1980. 
14* Includes $25,000 for major rehabilitation initiated in FY 1983. 
15. Exclusive of $6,994,235 details below. 
Additional Features Entering into Cost of Project 
Louisville and Portland Canal and Indiana chute $ 5,359,203 
(under previous project) 
Examinations, survey contingencies, plants and miscellaneous 966,232 
Recreation facilities, pool area, Gallipolis locks and dams 668,800 
TOTAL 6,994,235 
0
0
'Ej 
GRAND TOTAL $1,417,699,683

NASHVILLE, TN, DISTRICT* 
This district comprises portions of southern Kentucky, 
southwestern Virginia, western North Carolina, 
northern Georgia and Alabama, northeastern 
Mississippi and practically all of Tennessee except 
western portion, and embraces drainage basins of 
Tennessee and Cumberland Rivers and their tributaries. 
IMPROVEMENTS 
Page General Investigations 
1. Cumberland River, TN and KY ........ 23-2 
2. Tennessee River, TN, AL and KY ...... 23-3 
3. Tennessee-Tombigbee Waterway, AL 
and MS ........................... 23-4 
4. Navigation Work Under Special 
Authorization ...................... 23-4 
Alteration of Bridges 
5. Authorized Alteration of Bridges ...... 23-4 
Page 
18. Surveys .......................... 23-8 
19. Collection and study of basic data ...... 23-8 
Tables 
Table 23-A Cost & Financial Statement ..... 
Table 23-B Authorizing Legislation ........ 
Table 23-C Other Authorized Navigation 
Projects ...................... 
Flood Control 
6. Big South Fork National River and 
Recreation Area, KY and TN .......... 23-4 
7. Martins Fork Lake, KY .............. 23-5 
8. Middlesboro, Cumberland River 
Basin, KY .......................... 23-5 
9. Tug and Levisa Forks of the Big Sandy 
River and Cumberland River, W VA, 
VA and KY ....................... . 23-6 
10. Ohio River Basin (Nashville Dist.) .... 23-6 
11. Inspection of completed flood 
control projects .................... 23-6 
12. Flood control work under special 
authorization ...................... 23-6 
Multiple-Purpose Projects, Including Power 
13. Center Hill Lake, Ohio River 
Basin, TN ........................ . 23-6 
14. Dale Hollow Lake, Ohio River Basin, 
TN and KY ........................ 23-7 
15. J. Percy Priest Dam and Reservoir, 
Ohio River Basin, TN ................ 23-7 
16. Laurel River Lake, Ohio River 
Basin, KY ......................... 23-7 
17. Wolf Creek Dam-Lake Cumberland, 
Ohio River Basin, KY ................ 23-8 
Table 23-D Not Applicable 
Table 23-E 
Table 23-F 
Other Authorized Flood Control 
Projects ...................... 
Other Authorized Multiple- 
Purpose Projects, Including 
Pow er ........................ 
Table 23-G Deauthorized Projects .......... 
Table 23-H 
Table 23-I 
Table 23-J 
Table 23-K 
Cumberland River, TN & KY, 
Principle Features ............. 
Tennessee River Lock 
Dimensions ................... 
23-9 
23-11 
23-13 
23-13 
23-14 
23-14 
23-15 
23-17 
Tennessee River Total Cost of 
Existing Project............... 23-18 
Ohio River Basin (Nashville 
District) Local Protection ...... 
Table 23-L Reservoirs................... . 
Table 23-M 
Table 23-N 
23-18 
23-18 
Inspection of Completed Flood 
Control Projects ............... 23-19 
Flood Control Work Under 
Special Authorization .......... 23-19 
23-1 
Navigation

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Navigation 
1. CUMBERLAND RIVER, TN AND KY 
Location. Formed by junction of Poor and Clover 
Forks in Harlan County, Ky., about 694.2 miles above 
its mouth, and flows west to Burnside, Ky., from 
whence it makes a loop southwestward into Tennessee, 
passes Nashville, and returns northwestward to 
Kentucky, emptying into Ohio River near Smithland, 
Ky. (See Geological Survey base maps of Tennessee 
and Kentucky.) 
Previous projects. For details see pages 1898 and 
1901 of Annual Report for 1915, and page 1208 of 
Annual Report for 1938, and pages 1069 and 1070 of 
Annual Report for 1962. 
Existing project. Below Nashville: Improvement of 
Cumberland River between mouth and Nashville was 
authorized for 9-foot navigation; increased project 
depth to be obtained by construction of three moderate 
height dams with lockage facilities, designated as 
Kuttawa (Eureka), Dover, and Cheatham, to replace 
existing locks A to F inclusive below Nashville and 
lock 1 above Nashville. (See table 23-B for authorizing 
legislation.) Subsequent authorities provided for 
construction of hydroelectric power-generating facilities 
at Cheatham Dam, river mile 148.7, and modification 
of project for navigation on Cumberland River, 
Tenn. and Ky., to provide, in lieu of previously authorized 
works at Kuttawa, mile 32.2, and Dover, mile 
100.1, for construction of a multiple-purpose improvement 
consisting of a dam, lock, and powerplant near 
mile 30.6 on lower Cumberland River and a canal for 
navigation and other purposes connecting this reservoir 
with reservoir formed by Kentucky Dam on the 
Tennessee River. The project is known as Barkley 
Dam and Lake Barkley. Provision of interconnecting 
canal, involving excavation of a channel through narrow 
watershed divide about 2.5 miles upstream from 
damsite, permits alternative routes available for navigation 
between either Cumberland or Tennessee 
Rivers and Ohio River, and affords integrated operation 
of Barkley and Kentucky Reservoirs through 
diversion of flows in interests of flood control and 
power production. Estimated cost of modified project 
for 9-foot navigation and multiple-purpose development 
is $180,525,800. Federal funds and $102,966 non- 
Federal funds for recreation facilities under the 
completed projects program (October 1983). (See 
table 23-H for listing of principal features.) 
Under flood conditions as regulated by upstream 
reservoirs, extreme fluctuation in stage of river below 
Nashville, Tenn., varies at different localities from 
about 16 to 55 feet above minimum pool levels. Ordinary 
fluctuations vary with power flows from as 
much as the allowable 3-foot drawdown below normal 
pool elevation 385 at Cheatham Lock and Dam to a 
range of about 7 feet at Nashville. Seasonal variation 
in normal headwater levels at Lake Barkley is 5 feet, 
which in combination with power flows produces 
fluctuations up to 10 feet below Cheatham Lock and 
Dam. 
Above Nashville: See pages 1693 thru 1696 of 
Annual Report for 1950 for information including 
statistical data on locks and dams 1 to 17 and 21. 
Completion information is shown on pages 1454 of the 
report for 1951. See Table 23-B for Authorizing Legislation. 
Construction of Old Hickory, Carthage, and 
Celina Dams above Nashville was also authorized for 
navigation and power. The dam and reservoir authorized 
for construction on Cumberland River near 
Carthage, Tenn., has been redesignated as Cordell 
Hull Dam and Reservoir. Cost of Old Hickory and 
Cordell Hull projects, including locks, is estimated at 
$137,685,100 (October 1983). Estimated cost of Celina 
Dam (1983) is $205,000,000. (See table 23-H at end 
of chapter for listing of principal features.) 
Under flood conditions as presently regulated, including 
effect of surcharge operation of Old Hickory 
project, extreme fluctuations of stage in this section 
of river vary from a range of 35 feet at Nashville 
(mile 191) to a maximum of 46 feet immediately below 
Old Hickory Dam (mile 216.2), and from an 
8-foot variation in headwater at dam to 36 feet in 
vicinity of Carthage, Tenn., (mile 313.5), present 
head of navigation; with variations up to 35 feet at 
Celina, Tenn. (mile 380.8) and 29 feet in tailwater at 
Wolf Creek Dam (mile 460.9). Maximum fluctuations 
under ordinary conditions from power flows vary 
from about 7 feet at Nashville to 14 and 3 feet, respectively, 
in tailwater and headwater of Old Hickory 
Dam, and at other key points as follows: 13 feet at 
Carthage; 18 feet at Celina; and 19 feet at Wolf Creek 
Dam. 
Further details on project authorization for river 
sections below and above Nashville are shown on 
Table 23-B. 
Local cooperation. Under modified project for 9- 
foot navigation and multiple-purpose development, 
recreation features of reservoir components are subject 
to certain conditions of non-Federal cost-sharing 
under Federal Water Project Recreation Act of 1965. 
Terminal facilities. There are 49 terminals on the 
Cumberland River (1 municipally owned and open for 
public use; 5 government owned facilities and 42 privately 
owned facilities). A total of 27 terminals have 
railroad connections. Principal commodities handled 
are petroleum products, stone, sand, gravel, coal, coke, 
23-2

NASHVILLE, TN, DISTRICT 
iron, steel, chemicals, and grain. Nineteen terminals 
are set up to handle various types of commodities. 
Facilities considered adequate for existing commerce. 
For further information see page 695 of Annual Report 
for 1969. 
Operations during fiscal year. New work: Below 
Nashville: Recreation facilities provided at Barkley 
project under (Code 711) cost $71,795 and Cheatham 
(Code 713) cost $133,290. Contract was awarded for 
Lock A washhouse at Cheatham under (Code 711). 
Above Nashville: Recreation facilities provided at 
Cordell Hull and Old Hickory under (Code 711) cost 
$30,000, $175,328, respectively. Contract was awarded 
for a restroom at Cedar Creek at Old Hickory under 
(Code 711). 
Maintenance: Barkley, Cheatham, Cordell Hull, and 
Old Hickory locks and dams were operated as required. 
Operation and Maintenance improvements at 
Barkley included contracts awarded for painting spillway 
gates, paving recreation areas, and to continue 
survey and marking boundary lines. Work at Cheatham 
included award of contracts to replace power 
plant roof, and to replace tainter gate chains. Work at 
Cordell Hull included contracts awarded for boundary 
line surveying and property line marking, and for 
paving access areas. Work at Old Hickory included 
award of contract for service base building. 
Total net energy generated at Barkley Dam 
(792,809,167 kw-hr) was made available through Department 
of the Interior to the Tennessee Valley Authority, 
Southern Illinois power Cooperative, Big 
Rivers Rural Electric Cooperative Corporation, and 
Indiana Statewide Rural Electric Cooperative, Inc., 
Hoosier Energy Division. Total net energy generated 
at Cheatham Dam (206,363,721 kw-hr), Cordell Hull 
(448,121,511 kw-hr), and Old Hickory (585,070,550 
kw-hr) was made available for distribution. Activities 
under reservoir management program comprising 
malaria control, shoreline sanitation, land management 
and disposal, and maintenance of public-use facilities 
continued. Flood damages prevented at Barkley 
amounted to $1,021,000. 
2. TENNESSEE RIVER, TN, AL AND KY 
Location. Formed by junction of French Broad and 
Holston Rivers in eastern Tennessee, 4.4 miles above 
Gay Street Bridge at Knoxville, flows southwest into 
northern Alabama, thence in a generally westerly 
course across north Alabama, to northeast boundary 
of Mississippi, thence nearly due north across Tennessee 
and Kentucky, entering Ohio River at Paducah, 
652.1 miles from junction of French Broad and Holston 
Rivers. (See Geological survey base map of Tennessee 
River Basin.) 
Previous projects. For details see pages 1902-1906, 
Annual Report for 1915; pages 1190-1194, 1196-1216, 
and 1220-1222, Annual Report for 1929; and page 
1216, Annual Report for 1988. 
Existing project. Originally provided for permanent 
improvement of river for a navigable depth of 9 feet 
at low water from mouth about 650 miles to Knoxville, 
Tenn. Only work performed by the Corps was construction 
of lock at General Joe Wheeler Dam and 
miscellaneous appurtenant improvements at a new 
work cost of $2,244,236. Tennessee Valley Authority 
program provided for obtaining authorized 9-foot 
project by construction of high dams and locks and 
utilization of certain locks and dams previously constructed 
under jurisdiction of the Corps. (See Table 
23-B for Authorizing Legislation.) Subsequent construction 
by that agency of Melton Hill Dam extends 
navigable channel of Tennessee River system up the 
Clinch River about 88 miles above damsite (mile 23.1) 
to vicinity of Clinton, Tenn. (See table 23-I on Tennessee 
River.) 
In accordance with general navigation laws placing 
control and supervision over navigable waters under 
direction of Secretary of the Army, the Corps of 
Engineers operates and maintains all locks, and maintains 
navigation channels and safety harbors by performing 
all necessary maintenance dredging and 
snagging operations. For information concerning 
other functions of the Corps under division of responsibilities 
for Tennessee River since adoption of Tennessee 
Valley Authority Act of 1933, see page 1084 of 
Annual Report for 1962. 
Local cooperation. Authorization requires no local 
cooperation in construction of alternate system of low 
dams. It does, however, provide that if high dams are 
built before the United States builds projected locks 
and low dams which are to be replaced, the United 
States shall contribute to cost of substituted structures 
an amount equal to estimated cost of works of 
navigation for which substitution is made. 
Terminal facilities. There are 165 terminals on the 
Tennessee River (7 municipally owned, 27 government 
owned facilities and 131 privately owned facilities). 
A total of 79 terminals have railroad connections. 
Principal commodities handled are petroleum products, 
stone, sand, gravel, coal, coke, grain, chemicals, 
iron, and steel. Seventy two terminals handle various 
types of commodities. Facilities considered adequate 
for existing commerce. A list of terminals is revised 
annually and can be obtained from Division Engineer, 
23-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Ohio River Division, Corps of Engineers, Cincinnati, 
Ohio. For further information see page 698 of Annual 
Report for 1969. 
Operations during fiscal year. Channel work by government 
plant and hired labor consisted of dredging 
and snagging at various locations, and maintenance 
of mooring facilities and safety harbors. Cost of channel 
maintenance was $400,703. Maintenance: All locks 
were operated and lock appurtenances and standby 
plant maintained as required. Major maintenance 
work items were dewatering and repair at Wilson 
Lock and repairing, and revising Wheeler switchboard 
and controls. Contracts awarded to paint miter gates 
and miscellaneous items at Wilson Main and Auxiliary 
Locks, paint miter gates at Nickajack, Ft. Loudoun, 
and Wheeler Locks. See tabe 23-J for total cost of 
existing project to September 30, 1983. 
3. TENNESSEE-TOMBIGBEE 
WATERWAY, AL AND MS 
Location. West Central Alabama and Northeastern 
Mississippi; in Marengo, Sumter, Greene and Pickens 
Counties, Alabama, and Noxubee, Lowndes, Clay, 
Monroe, Itawamba, Prentiss and Tishomingo Counties, 
Mississippi. 
Existing project. Provides for a waterway 234 miles 
in length, connecting the Tombigbee and Tennessee 
Rivers by way of the East Fork of Tombigbee River, 
Mackeys and Yellow Creeks, affording a channel not 
less than 9 feet deep and 280 feet in bottom width, 
with 10 locks each having clear chamber dimensions 
of 110x600 feet. Construction of the divide section, 
including Bay Springs lock and dam, is assigned to 
the Nashville District; whereas, the prosecution of 
work on the river and canal sections is under the jurisdiction 
of the Mobile District. Only activities of the 
Nashville District are reported hereon. Estimated 
Federal cost of new work under jurisdiction of the 
Nashville District is $721,000,000. (See 23-B for authorizing 
legislation.) 
Local cooperation. Authorization requires local interests 
to construct, maintain and operate all highway 
bridges, construct and maintain all highway relocations 
or alterations, make and maintain alterations as 
required to sewer, water supply and drainage facilities, 
assume cost of operation and maintenance of 
utility crossings, provide and maintain as required 
suitable and adequate river and canal terminals in 
accordance with plans approved by the Secretary of 
the Army and the Chief of Engineers. 
Operations during fiscal year. Engineering and design 
continued. Work continued on Bay Springs Lock, 
Dam, and Access Road contract; Clearing contracts 
Areas B and C. Area D Clearing contract was completed. 
Contracts for Mooring Facilities, Crows Neck 
Initial Facilities, and Damsite Initial Facilities were 
awarded. Work continued on Divide Cut Tishomingo 
County Roads, Southern Railway Agreement, Roadway 
with By-Pass (South End), DC4/2/A Plug, DC2, 
and Erosion control contracts. Contracts were awarded 
for Testing 5 Wells, Remedial Work-Navigation Section 
4B, Tie-Dike, Vegetation Maintenance and Erosion 
Control. Construction remains ahead of schedule. 
The project is 93% complete. Navigation features are 
99% complete. 
4. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation activities pursuant to Sec. 107, Public 
Law 86-645, as amended (preauthorization). 
During the period $19,700 was expended for a study 
of Port of Florence, AL. 
Alteration of Bridges 
5. AUTHORIZED ALTERATION OF 
BRIDGES 
Work on Woodland Street bridge, under Truman- 
Hobbs Act, was initiated in 1965 and completed in 
1966. Costs were $987,632. For details see page 922 of 
Annual Report for 1967. 
Flood Control 
6. BIG SOUTH FORK NATIONAL RIVER 
AND RECREATION AREA, KY AND TN 
Location. The proposed project is located in Northeastern 
Tennessee and Southeastern Kentucky along 
the Big South Fork River and its tributaries in Pickett, 
Scott, Fentress, and Morgan Counties, Tennessee, and 
McCreary County, Kentucky. 
Existing project. A National Recreation Area will 
be established in accordance with the concept included 
in the interagency report prepared pursuant to section 
208 of Flood Control Act of 1968. Total acreage is not 
to exceed 125,000 acres. The act specifically establishes 
the National Area for the purpose of preserving 
and interpreting the scenic, biological, archaeological 
23-4

NASHVILLE, TN, DISTRICT 
and historical resources of the river gorge area and 
developing the natural recreational potential of the 
area. The area is divided into two categories, gorge 
and adjacent areas, with no construction permitted 
except limited clearing for establishment of day-use 
facilities, historical sites, primitive campgrounds and 
access roads. Lodges and other facilities will be provided 
in the adjacent areas. The project was authorized 
by the Water Resources Development Act of 1974 
as amended by Water Resources Development Act of 
1976. (See table 23-B for authorizing legislation.) The 
present authorized cost (ceiling) for the project is 
$103,522,000. The National Park Service will operate 
and maintain the useable units of the area upon completion 
of land acquisition and construction of basic 
facilities by the Corps of Engineers. The first construction 
contract was awarded in June 1981. The 
project is 59% complete. 
Local cooperation. None required. 
Operations during fiscal year. Engineering and design 
continued. Acquired 5,743.48 acres fee. Construction 
continued on Leatherwood Ford Road and Bridge, 
and NRRA Development, General. Contract awarded 
for Bandy Creek Road and Recreation Facility. 
7. MARTINS FORK LAKE, KY 
Location. Dam located at mile 15.6 on Martins Fork 
of Clover Fork, Cumberland River, about 10 miles 
southeast of city of Harlan, with reservoir extending 
about 6 miles upstream within Harlan County, southeastern 
Kentucky. 
Existing project. Multiple-purpose improvement 
combining flood control with water quality control 
and recreation development adopted by 1965 Flood 
Control Act (H. Doc. 244, 89th Cong.), in general 
accordance with recommendations. Dam will be concrete 
type, about 504 feet long and rising 97 feet above 
streambed. Outlet works provide for release of water 
from reservoir at varying levels. Drainage area above 
damsite is 55.7 square miles. At full pool level, spillway 
crest at elevation 1341 above mean sea level, 
reservoir will cover 578 acres and contain 21,120 acrefeet 
of storage capacity. Provision is made for 17,450 
acre-feet of reservoir capacity between elevations 
1341 and 1300 for control of floods in winter and 
spring season, and 14,360 acre-feet (El. 1341-1310) 
during summer and fall, in conjunction with which 
storage of 3,090 acre-feet would be available on a 
seasonal basis to meet streamflow requirements for 
water quality control and fish life below the dam. A 
minimum permanent pool of 3,670 acre-feet, 274 acres 
in extent, will thus be provided during potential flood 
seasons; and during late spring and summer when 
flood storage can be reduced, the lake is to be operated 
generally at a higher level (El. 1310) to maintain a 
larger surface area of 340 acres for recreation and to 
provide the required seasonal storage for releases of 
water during critical low-flow periods. Project will 
prevent major portion of average annual flood losses 
at Harlan and result in significant stage reductions 
with related benefits along rural reaches and at other 
urban areas downstream. Estimated cost of project 
including $830,400 code 710 funds is $21,222,100 
(October 1983). First construction contract awarded 
in December 1972. Project completed for beneficial 
use in September 1978. 
Local cooperation. Federal Water Project Recreation 
Act of 1965 (P.L. 89-72) applies in regard to 
non-Federal participation in recreation development, 
in addition to which local interests are to provide certain 
safeguards to ensure functioning of reservoir as 
intended. In May 1981 a final recreation cost-sharing 
contract with Harlan County was approved and certain 
recreation facilities have been jointly developed 
by the Corps and the County. These facilities, consisting 
of a swimming beach and a picnic area are 
now operated and maintained by Harlan County. 
Recreation investment to date (Corps and Local) is 
about $100,000. 
Operations during fiscal year. New work: Recreation 
facilities under Code 713 cost $64,253. Maintenance: 
Dam was operated and structures operated as 
required. 
8. MIDDLESBORO, CUMBERLAND 
RIVER BASIN, KY 
Location. At Middlesboro, Ky., on Yellow Creek, a 
tributary entering Cumberland River about 660 miles 
above its mouth. 
Existing project. A system of canals and levees 
around one side of town, arranged so as to divert most 
headwaters of Yellow Creek away from present channel 
through heart of city. Protection is thus afforded 
in large measure to life and property within business 
district and a large part of residential section. For 
project details, see page 1088 of Annual Report for 
1962. 
Local cooperation. None required. 
Operations during fiscal year. 
Maintenance: Work on levees, canals, and appurtenances 
was accomplished by hired labor. 
23-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
9. TUG AND LEVISA FORKS OF THE 
BIG SANDY RIVER AND UPPER 
CUMBERLAND, WV, VA AND KY 
Location. The proposed project is located in the 
State of West Virginia and the Commonwealths of 
Kentucky and Virginia. The Cumberland portion consists 
of the Upper Cumberland River Basin, above 
Cumberland Falls, Ky. The basin is approximately 
100 miles in length, averaging 30 miles in width at 
the lower portion and 10 miles in width upstream at 
Harlan, Ky. The Big Sandy Basin is within the Huntington 
District and the Cumberland within the Nashville 
District. 
Existing project. Provides for flood control measures 
for communities in the Tug and Levisa Forks 
and Upper Cumberland River Basins. The Cumberland 
portion has been assigned to the Nashville District. 
Only activities of the Nashville District are 
reported hereon. Estimated Federal cost of new work 
under jurisdiction of the Nashville District is currentby 
being formulated. The project was authorized by 
the Energy and Water Development Appropriation 
Act of 1981, Section 202 of PL 96-367. 
Local cooperation. Authorizing legislation requires 
that non-federal interests shall hold and save the 
United States free from damages due to construction 
works and maintain and operate all such works after 
their completion in accordance with regulations by 
the Secretary of the Army. 
Operations during fiscal year. Engineering and design 
continued. Acquired 3.84 acres-fee. 
10. OHIO RIVER BASIN 
(NASHVILLE DISTRICT) 
Location. A series of levees, floodwalls, channel 
improvements, and reservoirs in Ohio River Basin 
within Nashville District. 
Existing project. The general comprehensive plans 
approved for flood control and other purposes in Ohio 
River Basin is set forth in legislation listed in Table 
23-B. Individual projects, local protection projects 
and lakes, considered in comprehensive plan within 
Nashville District are listed in Table 28-K. 
11. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Flood Control Act of June 22, 1986, and subsequent 
acts, requires local interests furnish assurances they 
will maintain and operate certain local protection 
projects after completion in accordance with regulations 
prescribed by Secretary of the Army. District 
Engineers are responsible for administration of these 
regulations within their respective districts. Maintenance 
inspections were made during fiscal year of 
completed protective works in localities transferred to 
local interests for maintenance and operation. Local 
interests were advised, as necessary, of measures required 
to maintain projects in accordance with standards 
prescribed by regulations. Fiscal year cost was 
$39,364. Total cost to September 30, 1983 was 
$203,601. For project inspection data see table 23-M. 
12. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control and coastal emergencies (Public Law 
99, 84th Cong., and antecedent legislation). 
Actual Federal cost for fiscal year were $168,268 
for disaster preparedness. 
Multiple-Purpose Projects, Including Power 
13. CENTER HILL LAKE, OHIO RIVER 
BASIN, TN 
Location. Dam is on Caney Fork River, 26.6 miles 
above its confluence with Cumberland River (mile 
309.2) at Carthage, Tenn. It is in DeKalb County, 
Tenn., about 55 miles east of Nashville, and 14 miles 
southeast of Carthage, Tenn. Reservoir extends about 
64 miles up main stream and about 10 miles up Falling 
Water River and lies within DeKalb, Putnam, 
White, and Warren Counties, Tenn. 
Existing project. A combination earth and concrete 
gravity-type dam, hydroelectric powerplant, and reservoir 
for primary purposes of flood control and 
power production, with a permanent pool for public 
use and conservation purposes. In addition to main 
dam structure, provision was made for a rolled-earth 
dike to close a saddle in reservoir rim near damsite. 
For further details, see page 1099 of 1962 Annual Report. 
Estimated cost of project including $10,327,700 
code 710 funds is $54,799,100 (October 1983). 
Local cooperation. None required on completed 
project. Recreation development subject to certain 
conditions of non-Federal cost-sharing under Federal 
Water Project Recreation Act of 1965. 
Operations during fiscal year. New work: Recreation 
facilities provided under (Code 711) cost $8,767. 
Maintenance: Dam was operated and structure and its 
appurtenances maintained as required. Operation of 
powerplant was continuous except for normal interruptions 
and necessary shutdowns for inspection and 
maintenance purposes. Contract awarded for Dam 
Foundation Exploration. Total net energy generated 
(432,288,400 kw-hr) was made available through 
23-6

NASHVILLE, TN, DISTRICT 
Department of the Interior to Tennessee Valley Authority 
for distribution. Activities under reservoir 
management involved land management, public relations, 
and maintenance of public use facilities. Flood 
damages prevented amounted to $840,000. 
14. DALE HOLLOW LAKE, OHIO RIVER 
BASIN, TN AND KY 
Location. Dam is on Obey River, 7.3 miles above its 
confluence with Cumberland River (mile 380.9) at 
Celina, Tenn. It is in Clay County, Tenn., and about 
80 miles northeast of Nashville, Tenn., 28 miles north 
of Cookeville, Tenn., and 3 miles east of Celina, Tenn. 
Reservoir extends about 51 miles up main stream, 10 
miles up East Fork, and 6 miles up West Fork of Obey 
River, and lies within Cumberland and Clinton Counties, 
Ky., and Clay, Pickett, Overton, and Fentress 
Counties, Tenn. 
Existing project. A concrete gravity-type dam, hydroelectric 
powerplant, and reservoir for primary 
purposes of flood control and power production with 
a permanent pool for public use and conservation purposes. 
See page 1096 of 1962 Annual Report for 
project details. Estimated cost of project including 
$15,477,300 code 710 funds and $150,000 non-Federal 
funds for recreation facilities under the completed 
projects program is $41,569,700 (October 1983). 
Local cooperation. None required on completed 
project; future recreation development subject to certain 
conditions of non-Federal cost-sharing under 
Federal Water Project Recreation Act of 1965. 
Operations during fiscal year. New work: Recreation 
facilities provided under (Code 711) cost $30,437. 
Contract has been awarded for comfort station at 
Lillydale and washhouse at Willow Grove under (Code 
711). Maintenance: Dam was operated and structures 
and appurtenances maintained as required. Operation 
of powerplant was continuous except for normal interruptions 
and necessary shutdowns for inspection and 
maintenance purposes. Total net energy generated 
(157,870,300 kw-hr) was made available through 
Department of the Interior to Tennessee Valley Authority 
for distribution. Activities under reservoir 
management program involved public relations, land 
management, and maintenance of public-use facilities. 
Contract for replacing turbine parts completed. Flood 
damages prevented amounted to $946,000. 
15. J. PERCY PRIEST DAM AND 
RESERVOIR, OHIO RIVER BASIN, TN 
Location. Damsite is on Stones River, 6.8 miles 
above its confluence with Cumberland River (mile 
205.9); in Davidson County, Tenn.; and about 7 miles 
east of Nashville, Tenn. Reservoir extends southeasterly 
from dam about 32 miles along main stream, 10 
miles up East Fork, 6.5 miles up West Fork, and for 
shorter distances up other tributaries of Stones River; 
and lies within Davidson, Rutherford, and Wilson 
Counties, Tenn. 
Existing project. A combination earth and concrete 
gravity-type dam, hydroelectric powerplant, and reservoir 
for primary purposes of flood control, power 
production and recreation. For further details see 
page 703 of 1969 Annual Report. Estimated cost of 
project including $4,374,400 under code 710 funds and 
$46,000 non-Federal funds for recreation facilities 
under the completed projects program is $58,028,100 
(October 1983). 
Local cooperation. Recreation development subject 
to certain conditions of non-Federal cost-sharing under 
Federal Water Project Recreation Act of 1965. 
Operations during fiscal year. New work: Recreation 
facilities provided under (Code 711) cost $3,902. 
Maintenance: Dam was operated and structures and 
appurtenances maintained as required. Total net 
energy generated (88,857,800 kw-hr) was made available 
through Department of the Interior to Tennessee 
Valley Authority for distribution. Activities under 
reservoir management program involved public relations, 
fish and wildlife management, and maintenance 
of public-use facilities. Flood damages prevented 
amounted to $837,000. 
16. LAUREL RIVER LAKE, OHIO RIVER 
BASIN, KY 
Location. Damsite is at mile 2.3 on Laurel River, a 
tributary of Cumberland River, in southcentral Kentucky. 
The two streams meet about 9 miles below 
Cumberland Falls, a prominent physiographic feature 
at head of Lake Cumberland which is formed by Wolf 
Creek Dam. Reservoir extends 19.2 miles upstream to 
site of Corbin, Ky. water-supply dam and lies within 
Laurel and Whitley Counties. 
Existing project. Project approved in general accordance 
with recommendations of House Document 
413, 86th Congress, by 1960 Flood Control Act, as 
amended by Public Law 88-253, was designed for 
purposes of flood control, power, and recreation as an 
integral unit of a coordinated plan for development of 
water resources of Cumberland River Basin. With the 
view of a net gain in power potential on a system 
basis, the plan of improvement incorporated appropriate 
flood control storage in the proposed project 
and corresponding adjustment in operations of Wolf 
23-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Creek Dam-Lake Cumberland for flood control and 
power, which in effect constituted a transfer of reservoir 
capacity without entailing a change in flood 
control benefits. Further detailed study giving full 
consideration to power capabilities and marketing arrangements 
indicated the advantage of maintaining 
present storage allocation at Wolf Creek and use of 
all available storage capacity of Laurel River Lake 
for power. The power plant is complete. Recreation is 
under construction. Total estimated cost is $60,000,000 
(October 1983). 
Local cooperation. None required. 
Operations during fiscal year. New work: Construction 
on Grove Access Road and Recreation Area is 
99% complete. Forest Service continued work on recreation 
sites under agreement. The project is 99% 
complete. Maintenance: Dam was operated and structures 
and appurtenances maintained as required. Contract 
awarded for Emergency Escape Route. Total net 
energy generated (78,197,000 kw-hr) was made available 
through Department of the Interior for distribution. 
17. WOLF CREEK DAM-LAKE 
CUMBERLAND, OHIO RIVER 
BASIN, KY 
Location. Wolf Creek Dam is on Cumberland River 
at mile 460.9 (above mouth) in Russell County, Ky., 
about 10 miles southwest of Jamestown and 12 miles 
north of Albany, Ky. Lake Cumberland extends 101 
miles up main stream, 48 miles up South Fork of 
Cumberland River, in Russell, Clinton, Wayne, 
Pulaski, McCreary, Laurel, and Whitley Counties, Ky. 
Existing project. A combination earth and concrete 
gravity-type dam, hydroelectric powerplant, and reservoir 
for primary purposes of flood control and 
power production, with a permanent pool for publicuse 
and conservation purposes. See page 1094 of 1962 
Annual Report for project details. Estimated cost of 
project is $189,728,637 (October 1983). This estimate 
includes $4,207,500 code 710 funds, $880,000 non-Federal 
funds for recreation facilities under the completed 
program, and $105,034,237 for major rehabilitation. 
Local cooperation. None required on completed 
project; future recreation development subject to certain 
conditions of non-Federal cost-sharing under 
Federal Water Project Recreation Act of 1965. 
Operations during fiscal year. New work: Activity 
involving the integrity of the structure began in 1968 
when a leak or seepage developed in the embankment. 
The major rehab embankment contract was physically 
completed in September 1982. Recreation facilities 
provided under (Code 711) cost $5,190 and facilities 
under (Code 713) cost $8,804. Maintenance: Dam 
was operated and structures and appurtenances maintained 
as required. Operation of powerplant was continuous 
except for normal interruptions and necessary 
shutdowns for inspection and maintenance purposes. 
Contract awarded to pave Beaver Lodge Launching 
Facility. Total net energy generated (1,012,551,000 
kw-hr) was made available through Department of 
the Interior for distribution. Activities under reservoir 
management program involved land management 
activities, public relations, and maintenance of publicuse 
facilities. Flood damages prevented amounted to 
$3,400,000. 
General Investigations 
18. SURVEYS 
Costs for this period were $1,016,244 for which 
$275,247 was for navigation, $439,236 for flood damage 
prevention studies, $198,847 for review of completed 
projects, $40,910 for special investigations, and 
$62,004 for coordination studies with other agencies. 
19. COLLECTION AND STUDY OF 
BASIC DATA 
Costs for this period were $44,013 for technical 
services to others, and $36,949 for flood plain management 
services, totalling $80,962. 
23-8

NASHVILLE, TN, DISTRICT 
TABLE 23-A COST AND FINANCIAL STATEMENT 
See 
Section 
in Text Project 
1. Cumberland River, 
TN and KY 
2. Tennessee River, 
TN, AL and KY 
3. Tenn.-Tombigbee 
Waterway, AL and MS 
5. Big South Fork National 
River and Rec. Area, 
KY and TN 
6. Martins Fork Lake, KY 
7. Middlesboro, Cumberland 
River Basin, KY 
8. Tug & Levisa Forks of the 
Big Sandy & Cumberland 
River, WV, VA and KY 
11. Cumberland, KY 
12. Center Hill Lake, 
Ohio River Basin, TN 
13. Dale Hollow Lake, 
Ohio River Basin, 
TN and KY 
14. J. Percy Priest Dam and 
Reservoir, Ohio River 
Basin, TN 
15. Laurel River Lake, 
Ohio River Basin, KY 
Funding 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
FY 80 FY 81 
430,500 
705,904 
9,900,000 
9,708,780 
4,750,000 
4,755,596 
- 
133,300,000 
133,493,093 
4,440,900 
4,438,717 
- 
537,851 
355,000 
343,729 
41,000 
26,488 
88,805 
142,642 
2,235,000 
2,116,901 
- 3,923 
2,335,000 
1,827,710 
140,618 
213,969 
1,390,000 
1,376,104 
2,140,000 
2,231,740 
640,000 
605,855 
4,016 
185,052 
11,962,325 
11,878,926 
5,255,000 
5,276,536 
121,765,000 
119,325,924 
15,770,131 
10,093,287 
10,000 
109,146 
355,000 
352,256 
130,000 
123,929 
2,500,000 
1,408,093 
- 93,000 
- 1,714 
2,137,000 
2,192,593 
1,963,000 
2,424,393 
40,000 
52,874 
1,993,000 
1,937,975 
2,094,000 
2,349,517 
615,000 
638,017 
FY 82 
390,000 
65,642 
12,715,140 
11,954,181 
7,027,000 
6,958,972 
104,390,000 
105,650,243 
8,958,124 
15,036,650 
26,876 
100,729 
357,000 
354,482 
55,000 
70,428 
2,200,000 
1,733,344 
14,200 
21,715 
2,155,880 
2,178,280 
2,529,880 
2,584,1483 
68,000 
71,607 
1,756,880 
1,847,366 
3,650,000 
3,735,017 
773,000 
811,751 
FY 83 
466,319 
417,163 
14,049,349 
13,918,143 
7,153,000 
7,004,232 
65,516,000 
65,822,382 
10,975,000 
10,731,095 
100,000 
64,253 
491,000 
500,189 
39,000 
36,553 
8,270,000 
2,854,007 
146,947 
8,767 
3,605,000 
3,268,063 
365,441 
30,437 
2,988,000 
2,828,213 
- 6,907 
3,902 
1,985,000 
1,959,925 
2,170,000 
2,522,143 
773,000 
716,769 
Total to 
Sep 30, 1983 
319,247,1161.2s.3 
318,846,895 1.2,4 
146,114,237 s 
144,375,223 
16,251,428 7 
16,251,428 7 
84,784,4518 
84,391,504 9 
400,000 
400,000 
680,000,050 
677,932,657 
62,354,155 o10 
61,624,360 11 
20,536,676 
20,486,431 
1,799,000 
1,781,893 
817,830 12 
817,830 12 
1,608,844 
1,599,760 
12,970,00018 
5,995,444 14 
66,642 
66,642 
53,403,022 15s 
53,256,56716 
30,209,96717 
29,807,785 1s 
28,305,445 19 
27,970,441 o20 
30,290,807 21 
30,090,310 22 
56,914,040 23 
56,909,758 24 
17,919,086 25 
17,859,087 28 
56,138,231 
56,000,955 
3,522,000 
3,450,865 
23-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 23-A COST AND FINANCIAL STATEMENT 
(Continued) 
See 
Section Total to 
in Text Project Funding FY 80 FY 81 FY 82 FY 83 Sep 30, 1983 
16. Wolf Creek Dam and New Work 
Lake Cumberland, Approp. 1,170,000 86,110 223,000 - 28,051 83,202,457 27 
Ohio River Basin, KY Cost 1,727,245 280,850 271,052 13,994 83,177,152 27 
Maint. 
Approp. 2,103,000 2,225,000 2,403,880 3,059,000 41,245,441 28 
Cost 2,145,076 2,232,648 2,358,456 2,858,455 40,933,849 29 
Rehab. 
Approp. 3,834,000 920,000 - 90,000 - 105,034,237 
Cost 3,344,381 612,001 765,037 22,686 104,991,988 80 
1. Includes $9,707,354 for abandoned and/or replaced works 
under the old Cumberland River system. (Amount includes 
$826,253 for new work and $3,266,706 for maintenance on previous 
projects.) 
2. Includes $61,733 public works acceleration funds, and 
$102,966 contributed by the State of Kentucky and $6,750 contributed 
by Metropolitan Nashville, TN. 
3. Includes $298,000 funds provided from the Productive 
Employment Appropriation Act (PL 98-8) of 1983. 
4. Includes $32,040 funds provided from the Productive 
Employment Appropriation Act (PL 98-8) of 1983. 
5. Includes $835,889 for special recreation use fees, and 
$1,314,279 for maintenance and operation of dams and other 
improvements of navigable waters, and $1,892,000 funds provided 
from the Productive Employment Appropriation Ace (PL 
98-8) of 1983. 
6. Includes $835,250 for special recreation use fees and 
$1,314,279 for maintenance and operation of dams and other 
improvements of navigable waters, and $664,801 funds provided 
from the Productive Employment Appropriation Act (PL 98-8) 
of 1983. 
7. Includes $14,007,193 for new work and $4,005,175 for 
maintenance on previous projects. 
8. Includes $424,063 for maintenance and operation of dams 
and other improvements of navigable waters, and $764,000 
funds provided from the Productive Employment Appropriation 
Act (PL 98-8) of 1983. 
9. Includes $424,063 for maintenance and operation of dams 
and other improvements of navigable waters, and $458,332 
funds provided from the Productive Employment Appropriation 
Act (PL 98-8) of 1983. 
10. Includes $300,000 funds provided from the Productive 
Employment Appropriation Act (PL 98-8) of 1983. 
11. Includes $175,000 funds provided from the Productive 
Employment Appropriation Act (PL 98-8) of 1983. 
12. Includes $33,876 Emergency Relief Funds. 
13. Includes $770,000 contributed by the State of Kentucky. 
14. Includes $655,261 contributed by the State of Kentucky. 
15. Includes $35,896 public works acceleration funds, and 
$148,000 funds provided from the Productive Employment Appropriation 
Act (PL 98-8) of 1983. 
16. Includes $35,896 public works acceleration funds, and 
$1,544 funds provided from the Productive Employment Appropriation 
Act (PL 98-8) of 1983. 
17. Includes $248,280 funds for special recreation use fees, 
and $91,000 funds provided from the Productive Employment 
Appropriation Act (PL 98-8) of 1983. 
18. Includes $248,162 funds for special recreation use fees, 
and $89,663 funds provided from the Productive Employment 
Appropriation Act (PL 98-8) of 1983. 
19. Includes $51,789 public works funds and $150,000 contributed 
by the State of Tennessee, and $341,000 funds provided 
from the Productive Employment Appropriation Act (PL 98-8) 
of 1983. 
20. Includes $51,789 public works funds and $150,000 contributed 
by the State of Tennessee, and $5,996 funds provided 
from the Productive Employment Appropriation Act (PL 98-8) 
of 1983. 
21. Includes $266,480 funds for special recreation use fees, 
and $482,000 funds provided from the Productive Employment 
Appropriation Act (PL 98-8) of 1983. 
22. Includes $263,463 funds for special recreation use fees, 
and $322,083 funds provided from the Productive Employment 
Appropriation Act (PL 98-8) of 1983. 
23. Includes $46,000 contributed by the Metropolitan Government, 
Nashville, TN. 
24. Includes $41,719 contributed by the Metropolitan Government, 
Nashville, TN. 
25. Includes $215,680 for special recreation use fees, and 
$40,000 funds provided from the Productive Employment Appropriation 
Act (PL 98-8) of 1983. 
26. Includes $215,636 for special recreation use fees, and 
$35,088 funds provided from the Productive Employment Appropriation 
Act (PL 98-8) of 1983. 
27. Includes $96,920 public works acceleration funds, and 
$880,000 contributed by the State of Kentucky. 
28. Includes $82,048 public works acceleration funds and 
$228,780 funds for special recreation use fees, and $293,000 
funds provided from the Productive Employment Appropriation 
Act (PL 98-8) of 1983. 
29. Includes $82,048 public works acceleration funds and 
$228,596 funds for special recreation use fees, and $67,506 
funds provided from the Productive Employment Appropriation 
Act (PL 98-8) of 1983. 
30. Includes $203,757 for claim paid on initial construction 
of switchyard. 
23-10

1. 
NASHVILLE, TN, DISTRICT 
AUTHORIZING LEGISLATION 
Date of 
uthorized Act 
Jul 18, 1892 
Jun 25, 1910 
Aug 30, 1935 
Jul 24, 1946 
Jun 19, 1952 
Sep 3, 1954 
Jul 14, 1960 
Project and Work Authorized 
CUMBERLAND RIVER BELOW NASHVILLE 
Provision made for lock A 
Provision made for locks B to F, and for dredging below 
lock F. 
Repairing dams A to F, inclusive, and surmounting same 
with movable crests. 
Provision of 9-foot channel by the construction of 8 
moderate height dams below Nashville; via, Kuttawa 
(Eureka), Dover, and Cheatham. 
Provision for hydroelectric power production as a function 
of Cheatham Dam. 
Construction of Barkley (Lower Cumberland) dam and 
reservoir project for navigation, flood control, hydroelectric 
power, and related purposes in lieu of Kuttawa 
and Dover navigation-only structures. 
Authorized change in alignment of Illinois Central Railroad. 
CUMBERLAND RIVER ABOVE NASHVILLE 
Aug 5, 1886 Provision made for locks and dams; the Secretary of War 
to determine the final plan of improvement. 
Dimensions of the locks fixed in accordance with reports 
of Mar. 30, 1887, and Nov. 25, 1890. 
Mar 2, 1907 Adoption of the report of the Board of Engineers, dated 
Feb. 26, 1906, limiting the lock and dam construction to 
locks and dams 1 to 7, and 21. 
Mar 2, 1919 Provision made for locks and dams 8 to 17. 
Jun 5, 1920 
Jul 3, 1930 
Jun 26, 1934 2 
Jul 24, 1946 
Oct 1, 1980 
2. 
Jul 8, 1980 
May 18, 1933 
Authorizes work to proceed in Tennessee without waiting 
for action of local interests in Kentucky. 
Raising dam 1, 8 feet. 
Operation and care of locks and dams provided for with 
funds from War Department appropriations for rivers 
and harbors. 
Construction of Old Hickory, Cordell Hull (Carthage), and 
Celina Dams above Nashville for navigation and the 
development of power resources. 
Design and construct flood control measures for communities 
in the Upper Cumberland River basins. 
TENNESSEE RIVER 
Authorized navigable depth of 9 feet from mouth about 
650 miles to Knoxville, Tennessee to be obtained by 
construction of low dams. 
Authorized TVA to construct such dams in the Tennessee 
River as will provide a 9 foot channel. 
Documents 
Annual Report, 1890, p. 
2151 
H. Does. 758, 60th Cong., 
1st seas.; and 1481, 60th 
Cong., 2d seas.x 
H. Doc. 38, 73d Cong., 1st 
seas. 
H. Doe. 761, 79th Cong., 
2d sess. 
S. Doc. 81, 83d Cong., 2d 
seas. 
H. Doc. 56, 86th Cong., 2d 
seas. 
Annual Report 1884, p. 
1663. 
Annual Report 1888, p. 
1622, and Annual Report 
1892, p. 1933. 
H. Doc. 699, 59th Cong., 
slest eas. 
Rivers and Harbors Committee 
Doe. 10, 63d 
Cong., 2d seas. 
Rivers and Harbors Committee 
Doc. 26, 70th 
Cong., 2d seas. 
H. Doe. 761, 79th Cong., 
2d seas. 
Sec. 202, PL 96-367 
H. Doc. 328, 71st Cong., 
2d seas. 
23-11 
TABLE 23-B 
See Section 
in Text A 
1. 

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 23.B 
(Continued) 
AUTHORIZING LEGISLATION 
See Section Date of 
in Text Authorized Act Project and Work Authorized Documents 
9. OHIO RIVER BASIN, NASHVILLE DISTRICT 
Construct levees, floodwalls, and drainage structures for 
protection of cities and towns in Ohio River Basin. 
Project to be selected by Chief of Engineers with 
approval of Secretary of War at a cost not to exceed 
$24,877,000 for construction. 
Approved general comprehensive plan for flood control and 
other purposes in Ohio River Basin as may be advisable 
at discretion of Secretary of War and Chief of Engineers, 
and for initiation and partial accomplishment of plan, 
authorized $75 million for reservoirs and $50,300, for 
local flood protection works. 
Additional $45 million for prosecution of comprehensive 
plan for Ohio River Basin. 
Dec 22, 1944 Additional $70 million for further prosecution of 
comprehensive plan for Ohio River Basin. 
Jul 24, 1946 Additional $125 million for further prosecution of 
comprehensive plan. 
Flood Control Committee 
Doc. 1, 75th Cong., 1st 
sess. 
Flood Control Committee 
Doe. 1, 75th Cong., 1st 
sess. 
H. Doe. 762, 77th Cong., 
2d sess. 
H. Doe. 506, 78th Cong., 
1st sess. 
Additional $100 million for prosecution of comprehensive 
plan for Ohio River Basin. 
Additional $150 million for further prosecution of 
comprehensive plan for flood control and other purposes 
in Ohio River Basin. 
Jun 18, 1965 Additional $89 million for further prosecution of 
comprehensive plan for Ohio River Basin. 
Aug 13, 1968 Additional $35 million for further prosecution of 
comprehensive plan for Ohio River Basin. 
Jun 19, 1970 Additional $69 million for further prosecution of 
comprehensive plan for Ohio River Basin. 
Mar 7, 1974 Authorized establishing Big South Fork National River and 
Recreation Area, KY and TN. Total area not to exceed 
125,000 acres. 
Mar 7, 1974 Additional $120 million for further prosecution of 
comprehensive plan for Ohio River Basin. 
TENNESSEE-TOMBIGBEE WATERWAY 
Jul 24, 1946 Construction of waterway to connect above rivers and 
provide a 9 foot channel and minimum bottom width 
of 170 feet in river and canal sections and 150 feet in 
the divide cut, with locks 110 by 600 feet clear inside 
dimensions. 
Subsequent studies determined most practical plan consists 
of channel with bottom width of 300 feet (280 feet in 
divide cut), fewer locks with higher lifts resulted in 
reducing number of lifts from 18 to 10 and reduced 
length from 260 to 253 miles. 
H. Doc. 6755, 89th Cong., 
1st sess. 
S. 3710, 90th Cong., 2d 
sess. 
H. R. 15166 91st Cong., 
2d sess. 
H. R. 10203 93rd Cong. 
Water Resources Develop. 
Act of 1974 Amended by 
PL 94-587, 94th Cong. 
H. R. 10203 93rd Cong. 
River Basin Monetary 
Authorization Act of 
1974. 
H. Doc. 486, 79th Cong., 
2d sess. 
Page 1343, Part I, FY 
1968 House Hearings. 
1. Contains latest published maps. Included in Public 
Works Administration program Sept. 6, 1933. 
2. Permanent Appropriation Repeal Act. 
23-12 
Aug 28, 1937 
Jun 28, 1938 
Aug 18, 1941 
May 17, 1950 
Dec 30, 1963 
3.

NASHVILLE, TN, DISTRICT 
TABLE 23-C OTHER AUTHORIZED NAVIGATION PROJECTS 
(All Projects mt Speeifeially Identified in Text) 
For last Full Cost to Sep 30, 1983 
Project Statm Report see Operation and Annual Report Construction Maintenance 
Caney Fork River, TN abandoned 1895 $ 27,828 - 
Clinch River, TN and VA abandoned 1923 53,949 $ 7,873 
Duck River, TN abandoned 1887 18,000 - 
Elk River, AL and TN abandoned 1904 4,000 - 
French Broad and Little Pigeon Rivers, TN abandoned 1981 249,605 33,554 
Hiwassee River, TN abandoned 1923 113,311 9,754 
Holston River, TN abandoned 1911 5,714 - 
Little Tennessee River, TN abandoned 1888 5,510 - 
Obey River, TN abandoned 1887 11,500 - 
Red River, TN abandoned 1884 5,000 - 
South Fork of Cumberland River, KY abandoned 1892 11,967 - 
TABLE 23.E OTHER AUffIORIZED FLO)OD CONTROL PROJECTS 
(All Pejects set Speecifcally Identified in Text) 
For last Full Cost to Sep 30, 1983 
Report see Operation and 
Project Status Annual Report Construction Maintenance 
Barbourville, KY completed 1963 $2,088,147 - 
Chattanooga, TN and Rossville, GA completed 1949 180,997 - 
Coal Creek and Tributaries (Lake City), TN completed 1962 460,134 - 
Corbin (Lynn Camp Creek), KY completed 1969 567,703 - 
Middlesboro (Yellow Creek), KY completed 1949 26,309 - 
Paint Rock River, AL completed 1967 544,173 - 
Pineville, KY completed 1963 1,679,126 - 1 
Rossview Reservoir, Ohio River Basin, TN and KY inactive - 6,779 - 
1. Includes $9,950 contributed funds. 
28-18

TABLE 23-F 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
OTHER AUTHORIZED MULTIPLE-PURPOSE PROJECTS 
INCLUDING POWER 
For last Full Cost to Sep 30, 1983 
Report see Operation and 
Project Status Annual Report Construction Maintenance 
Barkley Dam and Lake Barkley, KY and TN beneficial use - $146,068,058 $41,618,512 1 
Celina Dam, KY active - 222,575 - 1 
Cheatham Lock and Dam, TN beneficial use - 80,878,251 28,807,0731 
Cordell Hull Lock and Dam, TN beneficial use - 79,854,492 18,088,0921 
Old Hickory Lock and Dam, TN beneficial use - 52,121,164 38,583,1851 
1. Details given under "Cumberland River, TN and KY." See Table 2-3H. 
TABLE 23.G DEAUTHORIZED PROJECTS 
For last Full Federal Contributed 
Report see Funds Funds 
Project Annual Report for Date and Authority Expended Expended 
Three Islands Reservoir, Ohio 1970 Authorized: PC Act 1988, PL 761, 75 $111,855 - 
River Basin, TN Cong., 3rd sees.; FC Act 1946, PL 525, 
79th Cong., 2d sess. 
Deauthorized: 5 Aug 1977. 
23-14

NASHVILLE, TN, DISTRICT 
TABLE 23-H CUMBERLAND RIVER, TN AND KY: PRINCIPLE FEATURES 
(See Section 1 of Text) 
Dam and Reservoir Barkley Cheatham Old Hiekory 
Nearest town 
Miles above mouth of river 
Lock dimensions (feet) 1 
Lift at normal pool levels (feet) 
Depths on guardsills at 
minimum pool levels (feet) 
Character of foundation 
Dam: 
Type 
Height 
Length, exclusive of lock section 
(feet) 
Spillway: 
Gross length (feet) 
Net length opening (feet) 
Crest gates: 
Type 
Number 
Size (feet) 
Operating levels at dam 
(feet, mean sea level) : 
Maximum regulated 
Normal operation: 
Full pool 
Minimum pool 
Minimum pool in advance of floods 
Reservoir area (acres) 
Reservoir capacity (acre-feet) : 
Flood control 
Power drawdown 
Dead storage 
Total 
Canal: 
Length (miles) 
Bottom width (feet) 
Depth at minimum pool level (feet) 
Power development: 
Number of units 
Generator rating (kilowatts) 
Total installation (kilowatts) 
Kuttawa, KY, 
11 miles. 
30.6 
110 by 800 
57 
11, upper; 
13, lower 
Rock 
Concrete 
gravity and 
earthfill 
157 
9,959 
804 
660 
Tainter 
12 
55 by 50 
Ashland City, 
TN, 9 miles. 
148.7 
110 by 800 
26 
14, upper; 
17, lower 
Rock 
Conerete 
gravity 
75 
800 
480 
420 
Tainter 
7
60 by 27 
375 
359 
354 
346 
98,430 
1,213,000 s.4 
259,000 
610,000 
2,082,000 
385 
382 
7,450 
19,800 Z 
84,200 
104,000 
Old Hickory, 
TN, 3 miles. 
216.2 
84 by 400 
60 
14, upper; 
13, lower 
Rock 
Concrete 
gravity and 
earthfill 
98 
8,605 
325 
270 
Tainter 
6
45 by 41 
450 ' 
442 
27,450 
125,000 s 
63,000 
357,000 
545,000 
Carthage, TN, 
5 miles. 
318.5 
84 by 400 
59 
14, upper; 
13, lower 
Rock 
Concrete 
gravity and 
earthfill 
93 
1,188' 
291 
225 
Tainter 
5
45 by 41 
508 ' 
508 
501 
499 
13,920 
85,600 5.6 
20,500 
204,800 
310,900 
1.75 
400 
11 
4
32,500 
130,000 
8
12,000 
86,000 
4
25,000 
100,000 
3
33,333 
100,000 
28-15 
Cordell Hull Celina 
Celina, TN, 
5 miles. 
385.4 
Rock 
Concrete 
gravity and 
earthfill 
86 
2,298 
290 
250 
Tainter 
5
50 by 87 
564 
560 
559 
559 
16,960 
55,950 
14,700 
287,800 
357,950 
3
36,000 
108,000 
1 ! / 
- --

TABLE 23-H 
(Continued) 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
CUMBERLAND RIVER, TN AND KY: PRINCIPLE FEATURES 
(See Section 1 of Text) 
Dam and Reservoir Barkley Celina Cheatham Cordell Hull Old Hickory 
Percent of project completion a - a a s 
Year opened to navigation 1964 - 1952 1978 1954 
Estimated cost ' $147,046,800 $205,000,000 $33,479,000 $84,980,800 $52,704,300 
1. Clear width and length available for full width. 
2. Exclusive of lock section. 
8. Surcharge. 
4. Normal operation (elev. 375-859) during nonflood season; 
flood control allowance to be increased to 1,472,000 acrefeet 
(elev. 375-854) during season of major floodflows. 
5. Surcharge storage. 
6. During flood season (elev. 508-501); minimum 51,800 
acre-feet (elev. 508-504) with normal operation during nonflood 
season. 
7. Daily pondage allowance; run-of-river project. 
8. Completed for full beneficial use. 
9. Includes recreation facility costs. 
283-16

TABLE 23-I TENNESSEE RIVER 
(See Section 2 of Text) 
Lock Dimensions 
Length Minimum Depth 
Width Avail. Lift on Guard Sills 
of able for Year 
Miles Chainm- Full Nor- Mai- Opened Cost of 
Above Miles from her Width mal mum Lower Upper Character Navi* Kind Type of Each Lock 
Project ' Mouth Nearest Town (feet) (feet) (feet) (feet) (feet) (feet) of Foundation gation of Dam Construction and Dam 
Kentucky 22.4 0.5 above Gilbertsville, 110 
KY 
Pickwick Landing 206.7 4.4 above Hamburg, 110 
TN 
Wilson: 
Auxiliary lock 259.4 2.9 above Florence, 60 
AL 
Main lock 259.4 2.9 above Florence, 110 
AL 
General Joe Wheeler: 
Auxiliary lock 274.9 18.4 above Florence 60 
AL 
Main lock 274.9 18.4 above Florence, 110 
AL 
Gunteraville: 
Auxiliary lock 849.0 9.1 below Gunteraville, 60 
AL 
Main lock 849.0 9.1 below Guntersville, 110 
AL 
Nickajack: 
Auxiliary lock 424.7 39.4 below Chatta- 110 
nooga, TN 
Main lock 424.7 39.4 below Chatta- 110 
nooga, TN 
Chickamauga 471.0 6.9 above Chatta- 60 
nooga, TN 
Watts Bar 529.9 6.8 above Breedenton, 60 
TN 
Fort Loudon 602.3 1.3 above Lenoir City, 60 
TN 
Melton Hill 23.1 22.1 above Kingston, 75 
(Clinch R.) TN 
600 56 78.8 
600 55 68.0 
292 94 100.0 
800 
600 94 100.0 
400 48 51.5 
600 48 51.5 
360 39 45.0 
600 39 45.0 
600 
800 
360 
860 
360 
400 
39 41.0 
39 41.0 
49 58.0 
58 70.0 
72 80.0 
54 60.0 
12.7 11.0 Limestone 
12.8 10.0 Limestone 
11.0 11.2 Limestone 
18.0 18.0 Limestone 
13.2 14.7 Limestone 
13.0 13.0 Limestone 
11.8 13.0 Limestone 
12.7 18.0 Limestone 
18.0 13.0 Limestone 
18.0 18.0 Limestone 
13.0 10.0 Limestone 
11.8 12.0 Shale 
11.8 12.0 Limestone 
13.0 13.0 Limestone 
1942 Fixed Concrete and 
earthfill 
1937 Fixed Concrete and 
earthfill 
1927 Fixed Concrete and 
earthfll 
1959 - - 
1934 Fixed Concrete and 
earthfill 
1968 Fixed Concrete and 
earthfill 
1987 Fixed - 
1965 Fixed Concrete and 
earthfill 
1967 Fixed Concrete 
Fixed Concrete 
1939 Fixed - 
1941 Fixed Concrete and 
earthfill 
1943 Fixed Concrete and 
earthfill 
1968 Fixed Concrete 
2 
$46,973,540 s 
z 
1,796,295 ~ 
3&T 
7 
7 
3*? 
3
8 
I 
1. H. Doc. 828, 71st Cong., 2d mess., contains table, pp. 98 
and 99, giving pertinent information concerning low dams contemplated 
under 1980 project. Annual Report for 1938, pp. 1218 
and 1219, contains similar information pertaining to low dams 
in addition to existing locks and dams, including those constructed 
or under construction by Tennessee Valley Authority. 
2. Lock and dam constructed by Tennessee Valley Authority. 
3. Lock and dam constructed by Tennessee Valley Authority. 
Design for lock prepared with Corps forces and funds. 
4. Tailwater in canal; flight of 2 locks. 
5. Constructed by the Corps under authority of see. 124, 
National Defense Act of June 3, 1916 (H. Doc. 1262, 64th 
Cong., 1st sess.). Actual cost of lock and dam. 
6. Actual cost of lock only as constructed by the Corps; 
dams constructed by Tennessee Valley Authority. 
7. Constructed by Tennessee Valley Authority. 
--

TABLE 23-J 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TENNESSEE RIVER, TN, AL, AND KY 
TOTAL COST OF EXISTING PROJECTS TO SEP 30, 1983 
(See Section 2 of Text) 
Channel Operation & 
Funds New Work Maintenance Maintenance Total 
Regular $2,244,236 $6,635,821 $73,738,838 $82,618,895 1.2 
Maintenance - - 11,665 11,665 
Increase of compensation, - 5 - 5 
rivers and harbors, 1919 
(certified claims) 
Total $2,244,236 $6,635,826 $73,750,503 $82,630,565 1,2 
1. In addition, surplus property value at $54,336 was tion and care of works of improvement under provisions of 
transferred from the project without reimbursement. Excludes appropriation for such purposes. 
$4,005,175 expended between 1890 and June 30, 1935, on opera- 2. Excludes $14,007,192 previous construction cost. 
TABLE 23-K OHIO RIVER BASIN (NASHVILLE DISTRICT) 
LOCAL PROTECTION PROJECTS
Estimated Cost 
Type of 
Location Protection Federal Non-Federal Total 
Middlesboro Levees $581,000 $161,000 $742,000 1 
(Yellow Creek, KY) 
Cumberland, KY Channel 520,000 240,000 760,000 1 
Improvement 
1. Deferred. 
TABLE 23-L RESERVOIRS 
Total 
Estimated 
Tributary Basin and Reservoir Stream Cost 
Center Hill Lake, TN Caney Fork River $54,799,1001 
Dale Hollow Lake, TN and KY Obey River 41,419,7001 
J. Percy Priest Dam & Reservoir, TN Stones River 57,982,100 1, 
Laurel River Lake, KY Laurel River 60,000,000 8 
Martins Fork Lake, KY Martins Fork 21,222,100 
Rossview, TN & KY Red River 12,590,000 4,s 
1. Details of this project are in individual report. 
2. Formerly Stewarts Ferry Reservoir. 
3. See "Other authorized multiple-purpose projects." 
4. See "Other authorized flood control projects." 
5. Deferred. 
23-18

NASHVILLE, TN, DISTRICT 
TABLE 23-M INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS 
(See Section 10 of Text) 
Pro-ct Date of Inspection 
Barbourville, KY 
Corbin, KY 
Lake City, TN 
Middlesboro, KY (Yellow Creek) 
Middlesboro, KY (Diversion Canal) 
Paint Rock River, KY 
Pineville, KY 
Spring City, TN 
Oct. 1982 and May 1983 
Oct. 1982 and May 1988 
Oct. 1982 and May 1983 
Oct. 1982 and May 1983 
Oct. 1982 and May 1988 
Apr. 1983 and Sep. 1983 
Oct. 1982 and May 1988 
Oct. 1982 and May 1983 
TABLE 23-N FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION 
Flood Control activities pursuant to Section 205 
P.L. 858, 80th Congress, as amended 
Project FY 83 Cost 
Browns Creek, Nashville, TN $ 81,681 
Dry Creek, Goodlettsville, TN 480 
East Fork, Yellow Creek, TN 5,956 
Little Harpeth River, Brentwood, TN 60,725 
Whiteoak Creek, Sunbright, TN 298,619 
Emergency Bank Protection (Section 14 of the 1946 
Flood Control Act, P.L. 526, 79th Congress) 
Project FY 83 Cost 
Concord Park, Fort Loudoun, TN $ 24,869 
Lenoir City, TN 18,770 
Louisville Point Park, Fort Loudoun Lake, TM 76,444 
North Chickamauga Creek, TN 7,500 
Tennessee River, Adamaville, TN 22,156 
Valley River, NC 88,8691 
Wheeler Lake, Tennessee River, Decatur, AL 217,061 2 
1. Includes $600 contributed funds from the city of Valley River, NC. 
2. Includes $10,000 contributed funds from the city of Decatur, AL. 
23-19

LOUISVILLE, KY, DISTRICT* 
This district comprises a portion of southwestern Ohio, 
west central Kentucky, a small portion of north central 
Tennessee, Indiana except northern part, and 
southeastern Illinois except Cairo-Mounds-Mound City 
area, all included in drainage basin of Ohio River and its 
tributaries (exclusive of Tennessee and Cumberland 
Rivers) from mile 438 (below Pittsburgh) immediately 
upstream from Foster, KY. to mouth. 
All cost and financial statements for projects are listed 
at the end of this chapter. All other tables are referenced 
in text and also appear at the end of this chapter. 
IMPROVEMENTS 
Navigation - Locks and Dams Page 
1. Construction of Locks and Dams, 
Ohio River.............................24-2 
2. Green and Barren Rivers, KY............24-2 
3. Kentucky River, KY....................24-2 
4. Open Channel Work, Ohio River........... 24-3 
5. Other Authorized Navigation 
Projects ............................... 24-3 
6. Navigation Work Under Special 
Authorization ............................ 24-3 
Flood Control - Local Protection 
7. Dayton, KY............................24-3 
8. Evansville, IN ........................... 24-3 
9. Levee Unit No. 5, 
Wabash River, IN.......................24-3 
10. Mason J. Niblack Levee, 
Wabash River, IN.......................24-4 
11. Mill Creek, OH. ........................ 24-4 
12. Southwestern Jefferson 
County, KY............................24-5 
Flood Control - Reservoirs 
13. Barren River Lake, KY................... 24-5 
14. Brookville Lake, IN.....................24-5 
15. Buckhorn Lake, KY...................... 24-6 
16. Caesar Creek Lake, OH.................. 24-6 
17. Cagles Mill Lake, IN....................24-6 
18. Camp Ground Lake, KY.................. 24-7 
19. Carr Fork Lake, KY..................... 24-7 
20. Cave Run Lake, KY.....................24-7 
21. Cecil M. Harden Lake, IN................ 24-8 
22. Clarence J. Brown Dam 
& Reservoir, OH......................... 24-8 
23. Green River Lake, KY.................... 24-8 
24. Huntington Lake, IN....................24-9 
25. Louisville Lake, IL ..................... .24-9 
26. Mississinewa Lake, IN..................24-10 
27. Monroe Lake, IN ...................... 24-10 
28. Nolin Lake, KY.......................24-10 
29. Ohio River Basin 
(Louisville Dist.)........................ 24-11 
30. Patoka Lake, IN...................... . 24-11 
31. Rough River Lake and Channel 
Improvements, KY.....................24-11 
Page 
32. Salamonie Lake, IN....................24-12 
33. Taylorsville Lake, KY..................24-12 
34. Wabash River Basin....................24-13 
35. West Fork of Mill Creek Lake, OH........ 24-13 
36. William H. Harsha Lake, OH............. 24-13 
37. Inspection of Completed Flood 
Control Projects........................ 24-14 
38. Other Authorized Flood Control 
Projects.............................. 24-14 
39. Flood Control Works Under 
Special Authorization...................24-14 
40. Streambank Erosion Control 
Evaluation and Demonstration 
Act of 1974...........................24-14 
General Investigations 
41. Surveys..............................24-14 
42. Collection and Study of Basic Data........ 24-14 
43. Advance Engineering and Design.........24-14 
Tables 
Table 24-A Cost and Financial 
Statement.....................24-15 
Table 24-B Authorizing Legislation.......... 24-19 
Table 24-C Other Authorized Navigation 
Projects........................24-20 
Table 24-D Not Applicable 
Table 24-E Other Authorized Flood 
Control Projects................24-21 
Table 24-F Not Applicable 
Table 24-G Deauthorized Projects............ 24-23 
Table 24-H Principal Features of Green 
and Barren Rivers and Kentucky 
River Navigation Systems........24-24 
Table 24-I Ohio River Basin - Total 
Cost of Basin Plan..............24-25 
Table 244 Wabash River Basin - Total 
Cost of Basin Plan..............24-29 
Table 24-K Inspection of Completed 
Flood Control Projects............ 24-30 
Table 24-L Flood Control Work Under 
Special Authorization........... 24-32 
24-1

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1983 
Navigation - Locks and Dams 
1. CONSTRUCTION OF LOCKS AND 
DAMS, OHIO RIVER 
For report on this improvement, see the heading under 
Ohio River. 
2. GREEN AND BARREN RIVERS 
KY. 
Location. Green River rises in Casey County, KY, 
flows northwesterly 370 miles, and empties into Ohio 
River about 8 miles above Evansville, IN. Barren River 
rises in Monroe County, KY, flows northwesterly 130 
miles, and empties into Green River 1/2 mile above Lock 
4 and 149.5 miles above mouth of Green River. 
Existing project. Six locks and dams on Green River 
and one on Barren River to give, with channel work in 
pools of dams, a navigable depth of 9 feet and width of 
200 feet from Ohio River to mile 103 Green River, 3.2 
miles upstream from Paradise, KY; a navigable depth of 
5.5 feet from mile 103 Green River to Mammoth Cave, 
KY, mile 197.8 Green River, and from mouth of Barren 
River mile 149.5 Green River, to Bowling Green, KY, mile 
30.1, Barren River. 
Fluctuations in stage vary considerably at different 
locks. At Lock 3, Green River, ordinary high stages are 
from 12 to 15 feet above pool level, and at Lock 1, Barren 
River, from 7 to 10 feet above pool. Maximum stages of 
record are 34 feet above normal pool stage at Lock 3, 
Green River, and 29 feet at Lock 1, Barren River, obtained 
during floods of 1937 and 1913, respectively. (See Table 
24-B for authorizing legislation and Table 24-H for principal 
features of the locks and dams.) 
Local cooperation. Fully complied with. 
Terminal facilities. Coal handling facilities located 
on the Green River between miles 81.5 and 108.1 near 
South Carrollton, Rockport, Paradise and Rochester, 
Kentucky, are considered adequate for existing 
commerce. 
Operations during fiscal year. Consisted of operation 
and maintenance of Locks and Dams 1 and 2, Green 
River, and removal of shoals, snags, and slides as required 
to maintain adequate channel for existing traffic between 
mouth of Green River and Dam 3 at mile 108.5 Green 
River. Maintenance: Routine maintenance was 
performed. 
Locks and Dams 1 and 2, Green River, and Lock and 
Dam 1, Barren River, are in good condition. Lock and 
Dam 3, Green River, is in fair condition, and Lock 4, 
Green River, is in poor condition. Dam 4, Green River, 
failed May 24, 1965, when 120 feet washed out. Breach 
later widened, and repairs are deferred pending completion 
of survey report for navigation on Green River. Pool 
of Dam 1, Barren River, is maintained for local small boat 
use, but navigation through lock is suspended because of 
loss of lower pool. Operation activity was discontinued at 
Lock 4 Green River and Lock and Dam 1 Barren River 
in January 1974 and at Lock 3, Green River in September 
1981. The residences and associated buildings and certain 
real estate at Lock 4 Green River and Lock and Dam 
1 Barren River were disposed of in January 1975. Operation 
of Locks 5 and 6, Green River, was discontinued 
August 1951, as they were no longer used by river traffic. 
Controlling project depth in lower 103 miles of Green 
River is 9 feet; controlling depth from mile 103 to Bowling 
Green, KY, is 5.5 feet. Under permit issued by District 
Engineer on August 20, 1963, private interests dredged 
channel of Green River to extend 9-foot depth to coal 
loading teminal at mile 105.7. Channel of Green River 
above Lock 3 is no longer maintained. 
3. KENTUCKY RIVER, KY 
Location. Formed by confluence of its North and Middle 
Forks about 4 miles east of Beattyville in east central 
Kentucky, (South Fork joins the main stream at that 
location), flows northwesterly and empties into Ohio River 
at Carrollton, KY, mile 545.8 below Pittsburgh, PA. 
Existing project. Provides for 14.locks and fixed dams 
to give, in connection with improvement of Ohio River, 
slack water navigation of 6 feet minimum depth from 
Ohio River to places on the three forks that are short 
distances above Beattyville, KY. Length of 6-foot-depth 
project on main stem of Kentucky River is 258.6 miles 
to confluence of Middle and North Forks. Cost of completed 
new work is $4,176,749. River frequently rises to 
35 feet or higher. Extreme height at Lock 1 due to flood 
backwater from Ohio River is 60.3 feet, while extreme 
floods reach height of 47.6 feet at Lock 4, and 35.5 feet 
at Lock 14. At some intermediate locks extreme height 
of floods exceeds 40 feet. All flood heights refer to upper 
pool gages. Existing project was adopted by 1879 River 
and Harbor Act (H. Ex. Doc. 47, 45th Cong., 3d Sess., and 
Annual Report, 1879, p. 1398). Operation and care of locks 
and dams were included in project July 1, 1935, under 
provision of Permanent Appropriations Repeal Act of 
June 26, 1934. (See Table 24-H for principal features of 
the locks and dams.) 
On December 19, 1976 the lock operation schedules for 
commercial traffic and recreational craft on the Kentucky 
River System were reduced from continuous 24-hour yearround 
operation to two shift year-round operation of Locks 
1 through 4, intermittent daily operation of Locks 5 
through 10, and intermittent operation five days weekly 
of Locks 11 through 14. Since that time the hours for 
operation of Locks 5 through 14 have been reduced in 
several increments. During the fiscal year Locks 1 
through 4 continued a two-shift year-round operation, and 
Locks 5 through 14 were closed to traffic for the entire 
year and placed in caretaker status. 
Licenses. Federal Regulatory Commission License 
No. 539, to Kentucky Utilities Co., at Dam 7, Kentucky 
River, Annual charge, $4,708; total collections through 
September 30, 1982, $253,605. (Collection amount for 
fiscal year 1983 not available from Department of 
Energy.) 
Terminal facilities. Facilities for bulk commodities 
and gasoline are considered adequate for existing traffic. 
Operations during fiscal year. Consisted of operation 
and maintenance of locks and dams 1 through 4 and 
24-2

LOUISVILLE, KY. DISTRICT 
removal of shoals, snags, and slides as required to maintain 
an adequate channel for existing traffic between 
mouth of river and Dam 5 at mile 82.2 Kentucky River. 
Maintenance: Routine maintenance was performed. 
Existing project was completed in 1917. Work accomplished 
was rehabilitation of the five old State locks 
and dams and construction of new Locks and Dams 6 to 
14 inclusive. Repairs have been made to deteriorated 
locks and dams as required to keep locks in operation and 
maintain pool levels above dams except in extreme dry 
weather, when some pools fall below normal levels, details 
in Annual Reports for 1963,1964 and 1965. Channel work 
was performed as required to provide for existing river 
traffic. Controlling navigable depth in length of river 
covered by existing project was 6 feet at end of fiscal year. 
4. OPEN CHANNEL WORK, 
OHIO RIVER 
For report on this improvement, see this heading under 
Ohio River. 
5. OTHER AUTHORIZED NAVIGATION 
PROJECTS 
See Table 24-C. 
6. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
None. 
Flood Control - Local Protection 
7. DAYTON, KY 
Location. In Campbell County, Kentucky, on left 
bank of Ohio River from mile 467.0 to mile 469.2 and 
across the river from Cincinnati, Ohio. (See U. S. 
Geological Survey map of Newport, KY.) 
Existing project. Provides for construction of 8,170 feet 
of levee, two pumping stations with gravity drainage 
structures, and major relocations of storm and sanitary 
sewers serving the community. Estimated cost of new 
work (1983) is $12,866,500 Federal and $2,043,000 
non-Federal. 
Local cooperation. Section 3 of the Flood Control Act 
of June 22, 1936 applies. Preliminary assurances of 
cooperation were received from City of Dayton, Kentucky, 
on May 3, 1966. City has acquired all rights-of-way for 
the project. 
Operations during fiscal year. Completed engineering 
and design studies. Levee, floodwall and pumping 
plants that are physically complete were transferred to 
the City of Dayton for operation and maintenance 
December 30, 1982. Contract for stairs, walkways, 
overlook areas and landscaping was awarded in 
September 1983. 
Project is about 96 percent complete overall and operational 
for flood control purposes. Remaining work involves 
settlement of two contractors' claims and final payment 
for levee and floodwall and pumping plants, and completion 
of contract for landscaping and related items. 
8. EVANSVILLE, IN 
Location. In Vanderburgh County, IN, on right bank 
of Ohio River, 792.2 miles below Pittsburgh, PA. (See U.S. 
Geological Survey map of Evansville-South, IN.) 
Existing project. Construction of a system of levees 
and concrete floodwalls, together with pumping plants for 
disposal of interior drainage, at Evansville. For further 
details, see Annual Report for 1962, page 1127. Project 
will provide protection for City of Evansville, IN, against 
Ohio River floods equal to 1937 flood (maximum of record), 
with a 3-foot freeboard. Estimated total cost of new work 
(1983) is $55,400,000 Federal, including $7,900,000 (Oct 
1977) for Howell Section, Unit 2, that is in "inactive" 
category, and $7,982,000 non-Federal, including $352,000 
(Oct 1977) for the said Howell Section, Unit 2. Existing 
project selected for construction under general authorization 
for Ohio River Basin in 1937 Flood Control Act. 
Howell Section, Unit 2, was reclassified from the "active" 
category to the "inactive" category July 7, 1977 based 
on current studies that indicated this part of the project 
is not economically justified. 
Local cooperation. Section 3 of Flood Control Act of 
June 22, 1936, as amended, applies. Fully complied with 
for Howell Unit 1 and Knight Township sections. 
Assurances for Pigeon Creek Section, Unit 1, were executed 
February 11, 1963. Authorizations-of-entry for 
Pigeon Creek Section, Unit 2, Parts 1 and 2 have been 
furnished. 
Operations during fiscal year. Engineering and 
design studies continued. Design Memorandum for North 
1st Avenue, Diamond Avenue, and Stringtown Road 
pumping plants was completed. Contract for levee and 
flood wall Cedar Street to Stringtown Road was advanced 
to about 76 percent completion. Flood damages estimated 
at $1,082,000 were prevented during the 1983 flood 
season. 
Knight Township, Howell, Unit 1 and Pigeon Creek, 
Unit 1 Sections are complete. Howell Section, Unit 2, is 
in the "inactive" category. Construction of Pigeon Creek 
Section, Unit 2, was started in April 1974 and is about 
39 percent complete. General Design Memorandum and 
Supplement on Pigeon Creek Unit 2, and Design 
Memorandum and plans and specifications for Delaware, 
Dresden and North 6th Avenue pumping plants are approved. 
Project is about 69 percent complete overall. 
9. LEVEE UNIT NO. 5, WABASH 
RIVER, IN 
Location. In Gibson and Posey Counties, IN, on left 
bank of Wabash River, from 58 to 94.5 miles above mouth. 
Existing project. Provides for construction of 41.9 
miles of earth levee, drainage structures, pumping plants, 
together with alterations to three railroad bridges crossing 
Wabash River. Project provides protection for 44,000 
acres of farm land and towns of Lyle, Skelton, and Griffin, 
24-3

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1983 
IN, against a flood equal to that expected on an average 
of 7 times in each 100-year period. Estimated total cost 
of new work (1983) is $8,478,500 of which $905,000 is non- 
Federal cost for lands and damages and road utility 
relocations. Project was authorized by Flood Control Acts 
of 1936 and 1946. 
Local cooperation. Section 3, Flood Control Acts of 
June 22, 1936, applies. Assurances were executed by 
Superintendent of Levee District on January 8, 1962. 
Completed portions of project (levees) were transferred to 
the Levee District for operation and maintenance 
October 15, 1969. Emerson Ditch pumping plant was 
transferred to the Levee District for operation and 
maintenance November 24, 1975. 
Operations during fiscal year. Construction contract 
for Coffee Bayou pumping plant was advanced to 
47 percent completion. Flood damages estimated at 
$4,814,000 were prevented during the 1983 flood season. 
All sections of levee, Emerson Ditch pumping plant, and 
required alterations of the Penn Central Railroad, 
Southern Railroad, and Illinois Central Railroad are complete. 
Construction is in progress on the Coffee Bayou 
pumping plant. Project is about 90 percent complete 
overall. 
10. MASON J. NIBLACK LEVEE, 
WABASH RIVER, IN 
Location. In Knox and Sullivan Counties, IN, on left 
bank of Wabash River, between miles 134.8 and 151.8 
above mouth. 
Existing project. Construction of two sections of 
earth levee totaling 18 miles in length, three pumping 
plants for disposal of interior drainage, and other 
necessary appurtenances. Length of protection, including 
high ground between the two levee sections, is 18.9 miles 
long. Project protects 15,900 acres of agricultural land 
against a flood equal to that expected to occur 7 times in 
a 100-year period. Esimated Federal cost of the pumping 
plants (1983) is $2,784,000. Cost of the completed levee 
was $1,663,912 of which $109,200 was non-Federal cost 
and $1,554,712 was Federal cost. The levee project was 
authorized by the 1946 Flood Control Act; pumping 
facilities were authorized by the 1968 Flood Control Act. 
Local cooperation. Section 3 of the Flood Control Act 
of June 22, 1936, as amended, applies. Fully complied 
with for levees and pumping plants. 
Operations during fiscal year. Remedial work on 
the ventilation systems for the pumping plants was completed. 
Operation by local interests for flood control 
prevented damages estimated at $1,010,000 during 1983 
flood season. 
Construction of levees complete and transferred to 
Mason J. Niblack Levee District in January 1965 for 
operation and maintenance. Construction of the pumping 
plants and channel improvements complete and 
transferred to the local sponsor in May 1980. 
11. MILL CREEK, OH 
Location. Proposed project is located along the 
18-mile length of Mill Creek and three-fourths mile length 
of East Fork in Hamilton County, Ohio. Lower Mill Creek 
is in the commercial and industrial heart of the 
Cincinnati metropolitan area in the southwestern portion 
of the State. 
Existing project. Eighteen miles of channel improvement, 
2 miles of levees, two pumping plants, modification 
of 29 bridges, and the addition of two pumping units 
at the present Mill Creek Barrier Dam, located near the 
Ohio River, are included in the project. Acquisition and 
development with appropriate landscaping of 620 acres 
along the creek will be provided for high-density urban 
oriented recreational use. Estimated cost of new work 
(1983) is $176,422,000, of which $38,735,000 is 
non-Federal. 
Local cooperation. Section 3, Flood Control Act of 
1936 as amended, applies. In addition, local interests 
must provide without cost to the United States all 
modifications and relocations of buildings, utilities, street 
and foot bridges, sewers, and related and special facilities 
as necessary for construction of project; prevent encroachment 
on improved channels and on ponding areas which 
would impair capacities; at least annually inform interests 
affected as to degree of protection afforded by project, 
and provide guidance and leadership in preventing 
unwise and uneconomical development of flood plain 
areas by encouraging prudent use of floodproofing, land 
regulation planning, or other flood plain management 
techniques to reduce flood losses. Further, with respect 
to the recreational aspects of the project, local interests 
are required to furnish assurances that they will, if 
necessary, pay or contribute in kind, a portion of the cost 
of recreational facilities which, when added to the cost 
of recreation land, would amount to at least 50 percent 
of the total first cost of the recreation land and recreational 
facilities, and assure access to the recreation 
facilities to all on equal terms. An assurance agreement 
covering local cooperation requirements for the project 
consistent with Section 221 of the 1970 Flood Control Act 
and the Uniform Relocation Assistance and Real Property 
Acquisition Policies Act of 1970 was executed by the 
Millcreek Valley Conservancy District February 6, 1975, 
and for the Secretary of the Army March 28, 1975. A 
recreation cost sharing contract was executed by the Conservancy 
District February 25, 1975, and approved by the 
Secretary of the Army May 28, 1975. 
Operations during fiscal year. Engineering studies 
continued. Construction contract for channel and levee 
Section 3 advanced to 90 percent completion. 
Design Memoranda, Hydrology & Hydraulics, Concrete 
Aggregate and Stone Protection Sources, and Railroad 
Relocations, General Design Memoranda, Phase I and 
Phase II, Design of Channel - Sections 5 and 7 are complete. 
Construction of channel and levee - Section 7A, 
Phase I, is complete. Project is about 8 percent complete 
overall. 
24-4

LOUISVILLE, KY. DISTRICT 
12. SOUTHWESTERN JEFFERSON 
COUNTY, KY 
Location. In Jefferson County, KY, on left bank of 
Ohio River from mile 616 to 628.6. 
Existing project. Provides for the construction of 
68,500 feet of levee, 1,550 feet of concrete wall, four 
pumping plants, and other necessary appurtenances. 
Project will provide protection fo 24,100 acres against 
Ohio River floods equal to 1937 flood of record with 3-foot 
freeboard. Estimated cost of new work (1983) is 
$70,812,000, of which $60,895,000 is Federal, and 
$9,917,000 is non-Federal. Project was authorized under 
Flood Control Act of August 1968. Recreation as a project 
purpose has been deferred until such time as a water 
quality problem on Pond Creek is corrected. 
Local cooperation. Section 3 Flood Control Act of 
1936 as amended applies. In addition, local interests must 
agree to administer project land and water areas for 
recreation and fish and wildlife enhancement; and to pay, 
contribute in kind or repay (which may be through user 
fees) with interest, one-half of the separable first cost of 
the project allocated to recreation and fish and wildlife 
enhancement; and bear all costs of operation, 
maintenance and replacement of lands and facilities for 
recreation and fish and wildlife enhancement. Jefferson 
County Fiscal Court expressed intent to fulfill requirement 
by resolution dated April 4, 1967. Formal 
assurances of local cooperation for the flood protection portion 
of the project was executed by resolution of Jefferson 
County Fiscal Court, adopted September 17, 1971, and 
assurances for the recreation portion of the project were 
executed by similar resolution, adopted September 14, 
1971. Authorization-of-entry for levee and floodwall sections 
1, 2, 3, 4 and 4A have been furnished. 
Operations during fiscal year. Engineering studies 
continued. Contracts for relocation of Texas Gas Pipeline, 
construction of levee and floodwall Section 4A were completed. 
Two contracts for construction of Upper Mill Creek 
pumping plant and for installation of power service were 
advanced to 99 percent complete and 54 percent complete, 
respectively. Two contracts for construction of railroad 
closure at levee Section 4 and for construction of levee 
and floodwall Section 4 were both awarded in October 
1982 and advanced to 32 percent complete and 44 percent 
complete, respectively. 
Engineering studies are about 90 percent complete. 
Construction of levee and floodwall Sections 1, 2, 3 and 
4A; electric service for gatewells; Riverport and Lower 
Mill Creek pumping plants; and relocation of Texas Gas 
pipeline are complete. Project is 52 percent complete 
overall. 
Flood Control - Reservoirs 
13. BARREN RIVER LAKE, KY 
Location. Dam is on Barren River, 79.5 miles above 
its confluence with Green River and 10 miles northeast 
of Scottsville, KY. At flood control pool reservoir extends 
upstream about 40 miles in Barren and Allen Counties, 
KY. (See U.S. Geological Survey map of Lucas, KY.) 
Existing project. A reservoir for flood control and 
allied purposes. Dam is rolled earth and rockfill, 146 feet 
high and 3,970 feet long, with gate-controlled outlet works 
and uncontrolled open-cut spillway. Total storage capacity 
is 815,200 acre-feet (768,000 for flood control and 46,600 
for water supply storage). For further details, see page 
1125 of Annual Report for 1962. Estimated cost of new 
work (1983) is $27,479,717 including $2,335,055 Federal 
funds and $108,418 non-Federal funds for construction of 
recreation facilities under the completed projects program. 
Project was authorized by Flood Control Act of 
1938. 
Local cooperation. None required by authorizing act. 
Under provision of Water Supply Act of 1958, contract 
with City of Glasgow for water supply storage was 
approved by Secretary of Army on October 4, 1965. Terms 
require City to pay $23,433, which is project cost allocated 
to water storage plus capitalized prepayment of proportionate 
share of operation, maintenance, and major 
replacement costs. A contract, with the Commonwealth 
of Kentucky for development of additional campsites, 
shoreline protection and breakwater extension at Barren 
River Lake State Park under the cost-sharing category 
of the completed projects program was approved by the 
Secretary of the Army November 4, 1977. 
Operations during fiscal year. New work: None. 
Maintenance: Routine maintenance was performed. 
Operation for flood control during the 1983 flood season 
prevented damages of $5,389,000. 
Construction started in March 1960 and all major construction 
and relocation items were completed in October 
1964. Project was placed in operation in March 1964. 
Land acquisition is complete. 
14. BROOKVILLE LAKE, IN 
Location. Damsite is on East Fork of Whitewater 
River, 2.4 miles above confluence with West Fork, and 
about 1-1/2 miles north of Brookville, Indiana. The reservoir 
lies in Franklin and Union Counties, Indiana. (See 
U.S. Geological Survey map of Brookville, IN.) 
Existing project. A reservoir for flood control and 
allied purposes. Dam is earthfill, 182 feet high and 3,004 
feet long, with gate-controlled outlet works, and uncontrolled 
open spillway. Total storage capacity is 359,600 
acre-feet (214,700 for flood control, 89,300 for water supply, 
and 35,500 for conservation). A minimum pool of 
20,100 acre-feet is maintained. Estimated cost of new 
work (1983) is $53,125,889 of which $45,533,889 is 
Federal cost and $7,592,000 is non-Federal contribution 
for water supply storage. Project was authorized by 1938 
Flood Control Act. 
Local cooperation. None required by authorizing act. 
Contract with State of Indiana for water supply storage 
under provisions of Water Supply Act of 1958 was 
approved by Secretary of Army, August 5, 1965. Under 
terms of contract, State paid initial costs allocated to 
water supply feature of project plus capitalized prepay- 
24-5

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1983 
ment of proportionate share of operation and maintenance 
costs. 
Operation during fiscal year. New work: Pump 
modification and force main connection to regional sewer 
system were completed. Maintenance: Contract for installation 
of hydropower unit remained at 99 percent completion. 
Routine maintenance was performed. Operation 
for flood control during the 1983 flood season prevented 
damages estimated at $670,000. 
Construction started in November 1965 and all major 
construction and relocation items are complete. Land acquisition 
is complete and the project was placed in operation 
January 1974. 
15. BUCKHORN LAKE, KY 
Location. Dam is on Middle Fork of Kentucky River, 
43.4 miles above mouth, and 0.5 mile upstream from 
Buckhorn, Perry County, KY. Reservoir extends 
upstream about 34 miles and lies in Leslie and Perry 
Counties, Kentucky. (See U.S. Geological Survey map of 
Buckhorn, KY.) 
Existing project. A reservoir for flood control and 
recreation. Dam is earth and rockfill type, with gate controlled 
outlet works. Total storage capacity is 168,000 
acre-feet, of which 157,600 is for flood control. For further 
details, see page 1120 of Annual Report for 1962. 
Cost of completed new work (1983) is $11,766,206 including 
$386,707 for construction of recreation facilities 
under the completed projects program. Existing project 
was authorized by general authorization for Ohio River 
Basin in 1938 Flood Control Act. 
Local cooperation. Department of Parks of the Commonwealth 
of Kentucky has undertaken management of 
lands and recreational facilities in accordance with license 
granted by Secretary of the Army on June 29, 1962. 
Operations during fiscal year. New work: None. 
Maintenance: Routine maintenance was performed. 
Operation for flood control during the 1983 flood season 
prevented damages estimated at $343,000. 
Construction started in September 1956 and project was 
placed in operation in August 1960. All construction and 
land acquisition is complete. 
16. CAESAR CREEK LAKE, OH 
Location. Damsite is on Caesar Creek, about 3.0 
miles above its confluence with Little Miami River, in 
Warren County, Ohio, about 3.5 miles southeast of 
Waynesville, Ohio, and 10.5 miles northeast of Lebanon, 
Ohio. Reservoir lies in Warren, Clinton, and Green 
Counties, Ohio. (See U.S. Geological Survey map of 
Oregonia, OH.) 
Existing project. Provides for construction of a reservoir 
for flood control and allied purposes. It includes an 
earth and rockfill dam, four saddle dams, outlet works 
and an uncontrolled saddle spillway. Total storage capacity 
of reservoir is 242,200 acre-feet, of which 148,500 acrefeet 
is reserved for flood control storage. Estimated cost 
of new work (1983) is $64,850,000 including $5,033,000 
non-Federal reimbursement for water supply storage. Existing 
project was authorized by general authorization for 
Ohio River Basin in 1938 Flood Control Act. 
Local cooperation. None required. However, the 
State of Ohio requested inclusion in the project of storage 
for future municipal and industrial water supply uses. 
Contract with State of Ohio for water supply storage 
under provisions of Water Supply Act of 1958, as amended, 
was approved by Secretary of the Army, May 20, 1970. 
Under terms of contract, State will reimburse the Federal 
Government for costs allocated to water supply storage 
over a period not to exceed 50 years after use of this 
storage is initiated plus estimated annual amount for cost 
of operation, maintenance and major capital replacements 
required for the water supply facilities. 
Operations during fiscal year. New work: Engineering 
and design studies continued. Final condemnation action 
for land acquisition on one tract continued. Contract 
for tailwater comfort station was completed. Contract for 
sewer connection charge with Warren County as modified 
to include enlargement of waste water treatment plant 
at Waynesville was advanced to 35 percent completion. 
Contract for Warren County water connection charge was 
awarded in May 1983 and advanced to 86 percent completion. 
Contract for repair utility ducts at Highway 73 
bridge was awarded in July 1983 and advanced to 99 percent 
completion. Maintenance: Routine maintenance was 
performed. Operation for flood control during the 1983 
flood season prevented damages of $3,875,000. 
Construction of the project started in January 1968 and 
it is now complete except final condemnation action on 
one real estate tract, corrective work on utility ducts at 
a relocated highway bridge, and final utility connections 
to the recreation facilities. Project is about 95 percent complete 
overall. 
17. CAGLES MILL LAKE, IN 
Location. Dam is on Mill Creek, 2.8 miles above its 
confluence with Eel River, in Putnam County, IN, and 
about 25 miles east of Terre Haute, IN. Reservoir extends 
upstream about 11 miles and is in Putnam and Owen 
Counties, IN. (See U.S. Geological Survey map of Poland, 
IN.) 
Existing project. A reservoir for flood control and 
recreation. Dam is earth and rockfill embankment. Total 
storage capacity is 228,100 acre-feet, of which 201,000 
acre-feet are for flood control. For details see Annual 
Report for 1962, page 1136. Estimated cost of new work 
(1983) is $4,568,183 including $255,416 Federal funds and 
$205,000 non-Federal funds for construction of recreation 
facilities under the completed projects program. Existing 
project was selected for construction under general 
authorization for Ohio River Basin in 1938 Flood Control 
Act. 
Local cooperation. None required. State of Indiana 
has undertaken development and management of recreation 
facilities for use of the public in reservoir area in accordance 
with license granted by Secretary of the Army 
on January 17, 1952. A contract with the Indiana Department 
of Natural Resources for expanding the boat ramp 
24-6

LOUISVILLE, KY. DISTRICT 
and parking area at Site 3, Lieber State Park, under the 
cost sharing category of the completed projects program 
was signed by the State of Indiana on August 26, 1981 
and approved by the Deputy Chief of Engineers on 
March 26, 1982. 
Operations during fiscal year. New work: None. 
Maintenance: Routine maintenance was performed. 
Operation for flood control during the 1983 flood season 
prevented damages of $2,508,000. 
Construction started in July 1948 and completed in 
June 1953. 
18. CAMP GROUND LAKE, KY 
Location. The damsite is in central Kentucky on 
Beech Fork, about 49.1 miles above its confluence with 
Rolling Fork, which stream is a tributary to Salt River, 
in Washington County about 11 miles northeast of 
Bardstown and and about 34 miles southeast of Louisville, 
KY. (See U.S. Geological Survey map of Maud, KY.) 
Existing project. A reservoir for flood control and 
allied purposes. The project consists of a rolled-earth dam 
with an uncontrolled open-cut spillway through the left 
abutment, and a gate controlled outlet conduit. A 
detached dam is required in a saddle between the main 
dam and the spillway. Total storage capacity will be 
360,740 acre-feet for flood control, water supply, water 
quality and recreation. Estimated cost of new work (1981) 
is $124,227,000 of which $113,047,000 would be 
reimbursed by non-Federal interests. Project was 
authorized for Phase I design memorandum stage of advanced 
engineering and design by the Water Resources 
Development Act of 1974 (Section 1). 
Local cooperation. Local interests must agree to administer 
project lands, facilities, and water areas for 
recreation, including fish and wildlife enhancement; pay, 
contribute in kind, or repay (which may be through user 
fees) with interest, no less than one-half of the separable 
first costs allocated to recreation; bear all costs of operation, 
maintenance and replacement of fish and wildlife 
and recreation use lands and facilities; repay all cost 
allocated to water supply; effect proper measures for control 
of pollution at the source to assure the effectiveness 
of the water quality storage provided;.exercise, to the full 
extent of their legal capability, control against removal 
of streamflow resulting from the reservoir storage provided 
for water quality control; prevent encroachment of 
flow-carrying capacities of stream channels below the 
reservoir to the extent needed to provide reasonably effective 
reservoir operations; and periodically (at least annually) 
notify interests affected that the project will not 
provide complete flood protection and that backwater 
floods from the Ohio River will not be substantially reduced 
by the project. 
Operations during fiscal year. None. 
Phase I supplemental preauthorization studies were initially 
funded under the Construction, General appropriation 
category in fiscal year 1974 which financing continued 
through fiscal year 1978, after which it was assigned 
to the General Investigations appropriation category. 
A Report on Economics recommending continuation of 
Phase I studies was approved May 29, 1979. These studies 
were discontinued in fiscal year 1982 because the responsible 
agencies of the Commonwealth of Kentucky indicated 
they do not anticipate the Commonwealth's participation 
in either the recreation aspects or water supply 
aspects of the project and the project is not economically 
feasible without such participation. Construction has not 
started. 
19. CARR FORK LAKE, KY 
Location. Damsite is 8.8 miles above mouth of Carr 
Fork, a tributary of North Fork of Kentucky River, 16 
miles upstream from Hazard, Kentucky. The reservoir 
lies entirely within Knott County. (See U.S. Geological 
Survey maps of Carrie and Vicco, KY.) 
Existing project. Provides for construction of a reservoir 
for flood control and allied purposes. Dam is rock and 
earth fill with impervious core, 720 feet long and 130 feet 
high, with uncontrolled open cut spillway through left 
abutment. Outlet works has two control gates and 8-foot 
diameter conduit to stilling basin. Total storage capacity 
is 47,700 acre-feet (31,600 for flood control and 4,300 
for water quality control). A higher level seasonal pool 
for recreation is provided. Estimated Federal cost of new 
work (1983) is $52,253,900 including $76,724 for recreation 
facilities under the completed projects program. Project 
was authorized by the 1962 Flood Control Act. 
Local cooperation. None required for reservoir 
project. Division of Flood Control and Water Usage of 
Commonwealth of Kentucky gave assurance that encroachments 
on downstream channel capacity will be 
prevented. 
Operations during fiscal year. New work: Real 
estate administrative action required for condemnation 
of remainaing tracts was continued. Construction, by 
hired labor, of sanitary dump station in conformance with 
EPA and State standards, at Irishmen Creek site was 
completed under the completed projects program. 
Maintenance: Routine maintenance was performed. 
Operation for flood control during the 1983 flood season 
prevented damages of $41,000. 
Condition at end of fiscal year. Project was placed 
in operation January 1976. Construction started in 
January 1966 is complete. All land required for the project 
has been acquired; however, a number of condemnation 
actions remain unsettled. 
20. CAVE RUN LAKE, KY 
Location. Damsite is on Licking River, about 4 miles 
upstream from U. S. Highway 60 near Farmers, 
Kentucky, and 7 miles southwest of Morehead, Kentucky. 
Reservoir will be in Rowan, Bath, Morgan, and Menifee 
Counties, Kentucky, (See U.S. Geological Survey maps 
of Salt Lick and Morehead, KY,) 
Existing project. Plan provides for construction of a 
reservoir for flood control and allied purposes. Dam is rolled 
earthfill, with gate controlled outlet works and uncontrolled 
open spillway. Total storage capacity is 614,100 
24-7

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1983 
acre-feet (438,500 for flood control and 28,300 for water 
quality control). Estimated Federal cost of new work 
(1983) is $114,908,000 of which $35,213,000 is U. S. Forest 
Service cost. Project was authorized by Flood Control Acts 
of June 22, 1936 and June 28, 1938. 
Local cooperation. None required. 
Operations during fiscal year. New work: Engineering 
and design studies continued. Real estate administrative 
action required for acquisition of remaining 
tracts was continued. Contract for repair of relocated 
Morgan County Road 1009A was completed, and contract 
for remaining recreation facilities at the Twin Knobs site 
was advanced to 99 percent completion. Maintenance: 
Routine maintenance was performed. Operation for flood 
control during the 1983 flood season prevented damages 
of $1,823,000. 
Project has been in operation since February 1974. Construction 
started in June 1965 and is about 89 percent 
complete overall. Land acquisition is complete except for 
outstanding condemnation actions. All relocation and construction 
features are complete except remedial work on 
control tower and recreation facilities. 
21. CECIL M. HARDEN LAKE, IN 
Location. Dam is on Raccoon Creek, 32.4 miles above 
its confluence with Wabash River, and 25 miles northeast 
of Terre Haute, IN. At flood control pool, reservoir extends 
upstream about 15 miles in Parke and Putnam Counties, 
Indiana. (See U. S. Geological Survey Map of Mansfield, 
IN.) 
Existing project. A rolled earth dam and reservoir, 
for flood control and allied purposes. Total storage 
capacity is 132,800 acre-feet of which 116,600 acre-feet 
are for flood control. For details, see Annual Report for 
1962, page 1132. Estimated Federal cost of new work 
(1983) is $6,987,807 including $373,678 Federal funds and 
$353,995 non-Federal funds for construction of recreation 
facilities under the completed projects program. Project 
was selected for construction under general authorization 
for Ohio River Basin in 1938 Flood Control Act. Project 
name was changed from Mansfield Lake to Cecil M. 
Harden Lake by Public Law 93-521, December 14, 1974. 
Local cooperation. State of Indiana has undertaken 
management of lands and recreational facilities in 
accordance with license granted by Secretary of the Army 
on April 19, 1961. A contract with the Indiana Department 
of Natural Resources, approved by the Secretary of 
the Army in May 1974, provided for that agency to design 
and construct certain additional recreation facilities at 
Cecil M. Harden, Huntington, Mississinewa, Monroe and 
Salamonie Lakes under the cost sharing category of the 
completed projects program. 
Operations during fiscal year. New work: Cost 
shared recreation facilities being constructed by the State 
of Indiana under the completed projects program were 
completed. Maintenance: Boundary monumentation continued. 
Routine maintenance was performed. Flood 
damages of $1,206,000 were prevented during the 1983 
flood season. 
Construction started in October 1956 and all major 
items of work were completed December 1961. Land acquisition 
is complete. Project has been in operation since 
August 1960. 
22. CLARENCE J. BROWN DAM & 
RESERVOIR, OH 
Location. Damsite is just east of Springfield, Clark 
County, Ohio, at mile 7.3 of Buck Creek, a tributary of 
Mad River. (See U. S. Geological Survey maps of New 
Moorefield and Springfield, KY.) 
Existing project. A reservoir for flood control and 
allied purposes. It includes an earthfill dam, 6,620 feet 
long and 72 feet high, with gated outlet.works and open 
cut spillway with concrete chute through right abutment. 
Total storage capacity of reservoir is 63,700 acre-feet 
(32,900 for flood control and 20,800 for water quality control). 
Federal cost of completed project (1981) is 
$22,083,660. Project was authorized by 1962 Flood Control 
Act. Project name was changed from Buck Creek Dam 
and Reservoir to Clarence J. Brown Dam and Reservoir 
by Public Law 90-46, July 4, 1967. 
Local cooperation. Assurances from City of 
Springfield, Springfield Conservancy District, and Clark 
County, Ohio, covering protection against detrimental 
channel encroachment below dam to mouth of Buck 
Creek, were accepted March 5, 1964. 
Operations during fiscal year. New work: None. 
Maintenance: Routine maintenance was performed. Flood 
damages of $13,000 were prevented during the 1983 flood 
season. 
Construction started in September 1966. Land acquisition 
and all major project features were completed in 
November 1973. The project was placed in operation in 
January 1974. 
23. GREEN RIVER LAKE, KY 
Location. Damsite is 305.7 miles above mouth of 
Green River in Taylor County, KY, about 8 miles south 
of Campbellsville. Reservoir lies in Taylor and Adair 
Counties. (See U. S. Geological Survey map of Cane 
Valley, KY.) 
Existing project. A reservoir for flood control and 
allied purposes. Dam is earth and rock-fill, 141 feet high 
and 2,350 feet long. Outlet works is slide gate-controlled 
and spillway open and uncontrolled. Total storage 
capacity is 723,200 acre-feet (560,600 for flood control and 
64,500 for low-flow augmentation). Estimated cost of new 
work (1983) is $33,612,542, including $317,145 Federal 
funds and $190,213 non-Federal funds for construction of 
recreation facilities under the completed projects program. 
Existing project was authorized under general 
authorization for Ohio River Basin in 1938 Flood Control 
Act. 
Local cooperation. None required by authorizing act. 
Taylor County, by lease approved by Secretary of Army 
February 15, 1968, undertook operation and maintenance 
of Smith Ridge public access area. In May 1980, the lease 
24-8

LOUISVILLE, KY. DISTRICT 
was amended to turn back responsibility for maintenance, 
and operation of 99 percent of the site to the Corps, with 
the County retaining responsibility for the marina area. 
Under provision of Water Supply Act of 1958, contract 
with City of Campbellsville for water supply storage was 
approved by Secretary of Army April 23, 1969. Terms require 
city to repay, with interest and annual charges for 
operation, maintenance and major replacement, the investment 
cost of $85,765 allocated to its water supply 
storage space. Total payments received through fiscal 
year 1983 was $19,712. The Department of Parks of the 
Commonwealth of Kentucky, by lease approved by 
Secretary of Army, October 4, 1971, has undertaken the 
management of the Lone Valley public access area. 
Operations during fiscal year. New work: Hired 
labor construction of sanitary dump station for boats at 
Dam Site in conformance with EPA and State standards 
and rehabilitation of sewage treatment facilities, 
washhouses and restrooms at Smith Ridge site were completed 
under the completed projects program. 
Maintenance: Contracts for security fence and painting 
water tower were completed. Routine maintenance was 
performed. Operation for flood control prevented damages 
estimated at $4,684,000 during the 1983 flood season. 
Construction began in August 1965 and all major construction 
and relocation items were completed in 1972. 
Project has been in operation since February 1969. Project 
including all land acquisition complete in 1973. 
24. HUNTINGTON LAKE, IN 
Location. Damsite is on Wabash River, about 2 miles 
from Huntington, IN, and 411.4 miles above mouth. 
Reservoir is in Huntington and Wells Counties, IN. (See 
U. S. Geological Survey maps of Majenica and Mt. Etna, 
KY.) 
Existing project. A reservoir for flood control and 
recreation. Dam consiste of a rolled earth embankment 
4,700 feet long and 89 feet high, a concrete spillway and 
outlet section 155 feet long, and a concrete gravity section 
310 feet long. Spillway is controlled by three gates, 
and outlet works by six sluices. Project also provides local 
flood protection for Markle, IN. Total storage capacity of 
reservoir is 153,100 acre-feet, of which 149,000 acre-feet 
is reserved for flood control storage. Estimated project cost 
for new work (1983) is $19,466,000 of which $193,800 is 
non-Federal responsibility. Project was authorized by 
Flood Control Act of 1958. 
Local cooperation. Local interests must contribute 
in cash an amount equal to one percent of project first 
cost. State of Indiana has met this obligation. Contract 
with the Indiana Department of Natural Resources, 
approved by the Secretary of the Army May 17,1974, provided 
for that agency to design and construct certain 
additional recreational facilities at Cecil M. Harden, 
Huntington, Mississinewa, Monroe and Salamonie Lakes 
under the cost shared category of the completed projects 
program. 
Operations during fiscal year. New work: None. 
Maintenance: Contract for resurfacing in the operations 
area was completed. Contract to paint dam gates and install 
pipe drainage system was awarded in July 1983 and 
advanced to 70 percent completion. Routine maintenance 
was performed. Operation for flood control prevented 
damages estimated at $2,848,000 during the 1983 flood 
control season. 
Land acquisition and all major construction complete. 
Project was placed in operation January 9, 1969. 
25. LOUISVILLE LAKE, IL 
Location. Damsite is on the Little Wabash River 
164.8 miles above the mouth and about 3.5 miles 
northwest of Louisville, and 23 miles south of Effingham, 
IL. The lake area lies in Clay and Effingham Counties. 
(See U. S. Geological Survey map of Edgewood, IL.) 
Existing project. A reservoir for flood control and 
allied purposes. The project will consist of a gatecontrolled 
concrete overflow spillway section located at 
the face of the right abutment flanked by random rock 
and earth fill embankment with impervious center core 
extending across the valley to the left abutment. A small 
dike along the right abutment will parallel an existing 
railroad. Total length of dam is about 21,400 feet with 
a maximum height of 69 feet. Total storage capacity is 
230,769 acre-feet, of which 168,531 acre-feet will be for 
flood control. Estimated Federal cost of new work (1982) 
is $113,000,000 including $14,435,000 reimbursable by 
non-Federal interests for water supply and recreation. 
Project was authorized by 1968 Flood Control Act. 
Local cooperation. Local interests must agree to administer 
project land and water areas for recreation and 
fish and wildlife enhancement; pay, contribute in kind, 
or repay with interest (which may be through user fees) 
one-half of the separable costs allocated to recreation and 
fish and wildlife enhancement; bear all costs of operation, 
maintenance, and replacement of recreation and fish and 
wildlife lands and facilities; reimburse the allocated construction 
costs allocated to water supply storage; bear all 
costs of operation, maintenance and replacement of water 
supply storage facilities, prevent channel encroachments 
tending to reduce present channel capacities; hold and 
save the United States free from damages from water 
rights claims resulting from construction and operation 
of the reservoir; exercise, to the full extent of their legal 
capability, control against removal from stream flow 
made available by reservoir storage for water quality control 
purposes; and contribute to the control of pollution 
of the stream subject to low-flow augmentation by adequate 
treatment or other methods of controlling wastes 
at their source. The State of Illinois will be the responsible 
cooperating agency for all required assurances. 
Operations during fiscal year. Alternative water 
supply studies were completed. Regular preconstruction 
planning has been discontinued due to the State of 
Illinois' failure to provide up-to-date reaffirmation of State 
support for the project. Design Memoranda, Hydrology 
and Hydraulics, Draft and Final General Design 
Memorandum, Phase I, Plan Formulation and Appendices 
and Final Environmental Impact Statement are complete. 
24-9

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1983 
Relocation of U. S. Route 45 (Advance Participation) is 
complete. 
26. MISSISSINEWA LAKE, IN 
Location. Damsite is 7.1 miles above mouth of 
Mississinewa River, which flows into Wabash River about 
2 miles upstream from Peru, IN. At flood control pool 
level, reservoir extends upstream about 28 miles, in 
Wabash, Grant, and Miami Counties, IN. (See U.S. 
Geological Survey map of Peoria, IN.) 
Existing project. Provides for construction of a reservoir 
for flood control and allied purposes. It includes an 
earthfill dam 137 feet high and 8,100 feet long, gatecontrolled 
outlet works, and an uncontrolled open 
spillway through right abutment. Total storage capacity 
of reservoir is 368,400 acre-feet, of which 345,100 acrefeet 
are reserved for flood control storage. Estimated project 
cost for new work (1983) is $24,206,737, of which 
$23,578,145 is Federal cost and $628,592 non-Federal 
responsibility including recreation facilities under the 
completed projects program. Project was authorized by the 
Flood Control Act of 1958. 
Local cooperation. Local interests must contribute 
in cash an amount equal to 1 percent of project first cost. 
State of Indiana assumed this obligation. A contract with 
the Indiana Department of Natural Resources, approved 
by the Secretary of the Army in May 1974, provided for 
that agency to design and construct certain additional 
recreation facilities at Cecil M. Harden, Huntington, 
Mississinewa, Monroe and Salamonie Lakes under the 
cost sharing category of the completed projects program. 
Operations during fiscal year. New work: Construction 
of additional cost shared recreation development by 
the State of Indiana at Miami and Frances Slocum sites 
under the completed projects program was completed. 
Maintenance: Contract for resurfacing at the operations 
area was completed. Routine maintenance was performed. 
Operation for flood control prevented damages of 
$5,443,000 during 1983 flood season. 
Construction and land acquisition is complete. Project 
was placed in operation in May 1968. 
27. MONROE LAKE, IN 
Location. Dam is on Salt Creek, a tributary of White 
River, 25.9 miles above mouth, and 2 miles each of 
Harrodsburg, Monroe County, IN. At flood control pool 
level, reservoir will extend upstream 44 miles in Monroe, 
Brown, and Jackson Counties. (See U.S. Geological 
Survey map of Clear Creek, IN.) 
Existing project. A reservoir for flood control and 
allied purposes. Dam is earth core and rock shell, with 
gate-controlled outlet works and uncontrolled open 
spillway. Total storage capacity is 441,000 acre-feet 
(258,800 for flood control and 159,900 for low flow 
augmentation.) Estimated cost of new work (1983) is 
$16,570,774 of which $7,797,604 is non-Federal contribution 
for low-flow regulation storage and $870,343 non- 
Federal funds for construction of recreation facilities 
under the completed projects program. Project was 
authorized by 1958 Flood Control Act, modifying comprehensive 
plan for Ohio River Basin. 
Local cooperation. Section 3, 1944 Flood Control Act 
applies. Local interests must contribute 54.1 percent of 
project cost, this being the proportion allocated to low-flow 
regulation feature, plus a capitalized amount 
representing that part of average annual maintenance 
and operation cost allocated to low-flow regulation. State 
of Indiana assumed this cost sharing obligation. A contract 
with the Indiana Department of Natural Resources, 
approved by the Secretary of the Army in May 1974, provided 
for that agency to design and construct certain 
additional recreation facilities at Cecil M. Harden, 
Huntington, Mississinewa, Monroe and Salamonie Lakes 
under the cost sharing category of the completed projects 
program. 
Operations during fiscal year. New work: None. 
Maintenance: Contract for removal of rock outcrop and 
access road repair was awarded in July 1983. Routine 
maintenance was performed. Operation for flood control 
prevented damages of $1,768,000 during 1983 flood 
season. 
Project is complete and was placed in operation in 
February 1965. 
28. NOLIN LAKE, KY 
Location. Dam is on Nolin River 7.8 miles above its 
confluence with Green River, about 70 air miles 
southwest of Louisville, KY. Reservoir extends upstream 
about 57 miles and is in Edmonson, Grayson, Hart, and 
Hardin Counties, KY. (See U.S. Geological Survey maps 
of Nolin Reservoir and Dickeys Mill, KY.) 
Existing project. A reservoir for flood control and 
allied purposes. Dam is rockfill-earth core type with gatecontrolled 
outlet works, and uncontrolled open spillway. 
Total storage capacity is 609,400 acre-feet, of which 
545,600 acre-feet is for flood control. For further details 
of project see Annual Report for 1962, page 1124. 
Estimated Federal cost of new work (1983) is $17,195,841 
including $2,598,777 for construction of recreation 
facilities. Project was selected for construction under 
general authorization for Ohio River Basin in 1938 Flood 
Control Act. 
Local cooperation. None required for authorized 
project. State of Kentucky contributed $18,195 for 
increased width of dam for public road. 
Operations during fiscal year. New work: Construction 
by hired labor on sanitary dump station for boats at 
Moutardier site in conformance with EPA and State 
standards, under the completed projects program, was 
completed. Maintenance: Routine maintenance was performed. 
Operation for flood control during the 1983 flood 
season prevented damages estimated at $2,173,000. 
Construction started in January 1959. Project was completed 
and placed in operation in March 1963. 
24-10

LOUISVILLE, KY. DISTRICT 
29. OHIO RIVER BASIN 
(Louisville District) 
Location. Works covered by this project are a series 
of levees, floodwalls, channel improvements, and reservoirs 
in Ohio River Basin within Louisville District. 
Existing project. Individual projects considered in 
comprehensive plan within the Louisville District. (See 
Table 24-B for authorizing leglsiation, and Table 24-I for 
cost and listing of projects in the basin plan.) 
Operations during fiscal year. No costs were 
incurred except for this projects for which individual 
reports are given. 
30. PATOKA LAKE, IN 
Location. Damsite is in Dubois County, IN, 118.3 
miles above mouth of Patoka River, and 50 miles westnorthwest 
of New Albany, IN. Reservoir extends into 
Dubois, Orange and Crawford Counties. (See Geological 
Survey map of Cuzco, IN.) 
Existing project. Reservoir for flood control and allied 
purposes. Dam is earth and rock fill, 1,550 feet long and 
85 feet high, with gate-controlled outlet works and uncontrolled 
open spillway. Total storage capacity is 301,600 
acre-feet (121,000 for flood control and 167,500 for water 
supply and water quality control). Estimated cost of new 
work (1983) is $78,417,700 of which $1,361,200 is Federal 
cost for emergency remedial measures and to clear and 
snag the Patoka River downstream of Patoka Lake, which 
work was directed by Congress in 1981; $51,507,800 is 
Federal cost for other construction, and $25,548,700 is 
non-Federal contribution for water supply storage and 
recreation-facilities. Project was authorized by 1965 Flood 
Control Act, and emergency measures and snagging and 
clearing the Patoka River downstream of Patoka Lake 
to insure effective operation of the project for flood control 
was directed by 1981 Appropriation Act for Energy 
and Water Development. 
Local cooperation. Local interests are required to 
reimburse the Federal Government for costs allocated to 
water supply storage over a period not to exceed 50 years 
after use of this storage is initiated, presently estimated 
at 29.316 percent of the joint-use facilities cost, exclusive 
of interests, plus $287,000 for the cost of operating and 
maintaining water supply storage for a period of 50 years, 
plus $42,000 for the cost of major capital replacements 
required for water supply storage space for a period of 50 
years. Local interests are also required to pay, contribute 
in kind, or repay (which may be through user fees) with 
interest, one-half of the separable first cost of the project 
allocated to recreation. Present laws of the State of 
Indiana require that agency to make cash contributions 
during construction of the project. Local interests must 
also agree to prevent encroachments on channel of Patoka 
River from dam to mouth, and to pay allocated initial and 
annual maintenance and operation costs for water supply 
storage. Formal assurances of local cooperation, executed 
by the Indiana Natural Resources Commission, were accepted 
August 27, 1970. Contracts with State of Indiana 
for water supply and recreation were approved by the 
Secretary of the Army November 2, 1970. 
Operations during fiscal year. New work: Engineering 
studies and land acquisition continued. Three utility 
relocation contracts for Orange County REMC, Indiana 
Telephone Corporation, and Public Service of Indiana 
were completed. Emergency remedial measures and snagging 
and clearing the Patoka River, accomplished with 
leased equipment and hired labor, was also completed. 
Contract for repairs to Highways 145 and 164 was 
awarded in September 1983. Maintenance: Routine 
maintenance was performed. Operation for flood control 
during the 1983 flood season prevented damage estimated 
at $4,126,000. 
Construction was started in July 1972. Engineering 
studies are about 99 percent complete. Land acquisition 
is about 99 percent complete. Construction of all relocations 
are complete, except minor repairs to a relocated 
road. All other major features. with the exception of 
recreation facilities are also complete. Permanent impoundment 
was started in February 1978 and the project 
was placed in operation about August 1980. The project 
is about 99 percent complete overall. 
31. ROUGH RIVER LAKE AND 
CHANNEL IMPROVEMENT, KY 
Location. Dam is on Rough River, 89.3 miles above 
its confluence with Green River 160.3 miles above. Ohio 
River, and about 60 miles southwest of Louisville, KY. 
Reservoir extends upstream about 30 miles and is in 
Breckinridge, Hardin, and Grayson Counties, KY. Channel 
improvement work is on Rough River, Barnett Creek, 
and West Fork of Barnett Creek. (See U.S. Geological 
Survey maps of McDaniels and Falls of Rough, KY.) 
Existing project. Reservoir is for flood control and 
allied purposes. Dam is rolled earthfill type, with gatecontrolled 
outlet works. Storage capacity is 334,380 acrefeet, 
of which 314,210 acre-feet is for flood control. Project 
also includes channel clearing of lower Rough River, and 
channel improvement on Barnett Creek, a tributary of 
Rough River. For further details see page 1126 of Annual 
Report for 1962. Estimated cost of new work (1983) is 
$10,643,001 including $890,008 Federal funds and 
$22,612 non-Federal funds for construction of recreation 
facilities under the completed projects program. Existing 
project was selected for construction under general 
authorization for Ohio River Basin in 1938 Flood Control 
Act. Modification of previously approved plan to include 
channel improvement items was authorized by the 
1944 Flood Control Act. 
Local cooperation. None required for construction of 
reservoir unit. Provisions of Section 3, Flood Control Act 
of 1936, are applicable to channel improvements. 
Assurances were obtained from Ohio County for channel 
improvement. Department of Parks, Commonwealth of 
Kentucky, has undertaken management of certain lands 
and recreation facilities in accordance with license 
granted by Secretary of the Army on August 18, 1961. 
A contract with the Commonwealth of Kentucky to improve 
and pave road at the Below Dam Area - State Park 
under the cost sharing category of the completed projects 
program was approved by the Secretary of the Army 
November 4, 1977. 
24-11

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1983 
Operations during fiscal year. New work: Construction 
by hired labor on sanitary dump station for boats at 
North Fork site in conformance with EPA and State 
standards under the completed projects program was completed. 
Maintenance: A contract for a storage building 
was awarded in June 1983 and advanced to 92 percent 
complete. Routine maintenance was performed. Operation 
for flood control during the 1983 flood season 
prevented damages estimated at $2,708,000. 
Construction started in November 1955 and reservoir 
was placed in operation in June 1959. Land acquisition 
and all major items of construction and relocation are 
complete. 
32. SALAMONIE LAKE, IN 
Location. Damsite is 3.1 miles above mouth of 
Salamonie River which enters Wabash River about 6 
miles upstream from Wabash, IN. Reservoir extends 
upstream about 27 miles at flood control pool and lies in 
Wabash and Huntington Counties, IN. (See U. S. 
Geological Survey maps of Lagro and Majenica, IN.) 
Existing project. Provides for construction of a reservoir 
for flood control and allied purposes. It includes an 
earthfill dam with a maximum height of 133 feet and and 
length of 6,100 feet, gate-controlled outlet works with a 
16-foot diameter conduit and an uncontrolled open 
spillway through right abutment. Total storage capacity 
of reservoir is 263,600 acre-feet, of which 250,500 acrefeet 
is for flood control storage. Estimated project cost for 
new work (1983) is $17,046,149 of which $16,559,904 is 
Federal cost and $486,245 is non-Federal responsibility 
including recreation facilities under the completed projects 
program. Project was authorized by Flood Control 
Act of 1958. 
Local cooperation. Local interests must contribute 
in cash an amount equal to one percent of project first 
cost. State of Indiana assumed this obligation. A contract 
with the Indiana Department of Natural Resources, approved 
by the Secretary of the Army in May 1974, provided 
for that agency to design and construct certain 
additional recreation facilities at Cecil M. Harden, 
Huntington, Mississinewa, Monroe, and Salamonie Lakes 
under the cost sharing category of the completed projects 
program. 
Operations during fiscal year. New work: Construction 
of additional cost shared recreation development by 
the State of Indiana at the Dora-New Holland and Lost 
Bridge sites under the completed projects program was 
completed. Maintenance: Routine maintenance was performed. 
During the 1983 flood season, operation for flood 
control prevented damages of $4,730,000. 
Land acquisition and all major construction and relocation 
contracts are complete. Reservoir was placed in 
operation in spring 1967. 
33. TAYLORSVILLE LAKE, KY 
Location. Damsite is in Spencer County, KY, 60.0 
miles above the confluence of Salt River and Ohio River, 
4 river miles above Taylorsville and 36.9 river miles 
above Shepherdsville, KY. (See U. S. Geological Survey 
map of Taylorsville, KY.) 
Existing project. A reservoir for flood control and 
allied purposes. Dam will be an earth and rock fill structure, 
164 feet high and 1,280 feet long. Outlet works will 
be slide gate controlled and spillway will be uncontrolled 
open cut. Total storage capacity will be 291,670 acre-feet 
(211,230 for flood control, winter months), and 52,245 for 
water quality and fish and wildlife. Estimated Federal 
cost of new work (1983) is $97,774,000, of which 
$5,292,000 is for recreation facilities under the completed 
projects program, and $20,600,000 is non-Federal responsibility 
for recreation facilities. Project was authorized by 
1966 Flood Control Act. 
Local cooperation. Local interests must agree to administer 
project land and water areas for recreation; pay, 
contribute in kind, or repay (which may be through user 
fees) with interest one-half of the separable first costs of 
the project allocated to recreation; bear all costs of operation, 
maintenance, and replacement of recreation lands 
and facilities. Local interests must also agree to prevent 
encroachments on flow-carrying capacities of stream 
channels below the reservoir to the extent needed to provide 
reasonably effective reservoir operation. Commonwealth 
of Kentucky has indicated intent to fulfill requirements 
for recreation cost sharing and has assumed 
responsibility for channel encroachments and pollution 
control. The Commonwealth furnished assurance 
agreements covering prevention of encroachment on 
capacity of stream channels in April and May 1973 and 
executed the recreation cost sharing contract in April 
1973. On April 2, 1980 the U. S. District Court for the 
Western District of Kentucky ruled that the 1973 recreation 
cost sharing contract between the Commonwealth 
and the United States that provded for repayment after 
completion was invalid under the Kentucky Constitution 
which prohibits one General Assembly from obligating 
future appropriations that would be binding on a subsequent 
legislature. In response to the Court's ruling, the 
Commonwealth and the United States entered into a new 
contract providing for cash contributions. Contract was 
approved by the Secretary of the Army June 11, 1980. The 
contract was found to be valid and enforceable by the 
Court July 14, 1980. 
Operations during fiscal year. New work: Engineering 
and design studies and land acquisition continued. 
Dedication ceremony was on 28 May 1983. Contracts for 
two road relocations, one utility relocation, final pool 
clearing, dam and spillway, Settlers Trace, Phase I recreation 
facilities and utilities to the operations area were 
completed. Two contracts for Van Buren, Phase II recreation 
facilities were awarded in January and March 1983 
and were completed. Contract for Ashes Creek, Possum 
Ridge and Chowning Lane, Phase II recreation facilities 
was awarded in July 1983 and advanced to 4 percent completion. 
Two road relocation contracts for Anderson County 
road, Site A-2, and Nelson-Anderson Counties road, 
Site NA-1 and Kentucky Highway 44, Site K-1 were 
awarded in July and August 1983, respectively. Contract 
for Anderson County and Nelson-Anderson Counties road 
advanced to 6 percent completion. Contract for paving ac- 
24-12

LOUISVILLE, KY. DISTRICT 
cess road was awarded in April 1983 and advanced to 74 
percent completion. Contract for shop-office storage 
building was awarded in September 1983. During the 
1983 flood season operation for flood control prevented 
damages of $1,065,000. 
Engineering and design studies are about 85 percent 
complete and land acquisition is about 92 percent complete. 
Construction was started in June 1974. All major 
construction items are complete except several road 
relocations, final paving of state highways and recreation 
facilities. The dam gates were closed in January 1983 for 
permanent impoundment and the project is about 69 percent 
complete overall. 
34. WABASH RIVER BASIN 
Location. Works covered by this project are located 
in the Wabash River Basin, a drainage area of 33,100 
square miles, covering parts of Indiana, Illinois and Ohio. 
Existing project. One local protection project and five 
reservoir projects were authorized for this basin plan. (See 
Table 24-B for authorizing legislation and Table 24-J for 
project list and total cost of basin plan.) 
35. WEST FORK OF MILL 
CREEK LAKE, OH 
Location. Dam is on West Fork of Mill Creek 6.5 
miles above its junction with Mill Creek and 2 miles 
northeast of Mount Health, Ohio, and 10 miles north of 
downtown Cincinnati. Reservoir extends upstream about 
3 miles and is in Hamilton County, Ohio. (See U. S. 
Geological Survey map of Glendale, OH.) 
Existing project. An earth embankment dam and a 
reservoir for flood control, recreation, and reduction of 
pumping requirements at Mill Creek barrier dam in 
Cincinnati. Total storage capacity of reservoir is 11,300 
acre-feet, of which 9,850 acre-feet is for flood control. For 
further details see page 1119 of Annual Report for 1962. 
Estimated cost of new work (1983) is $4,895,663 including 
non-Federal cost of $520,800 for sewer relocation and 
dam, $50,000 non-Federal contribution in fulfillment of 
project authorization, and $615,961 Federal funds and 
$615,961 non-Federal funds for construction of recreation 
facilities under the completed projects program. Existing 
project selected for construction under additional 
authorization for Ohio River Basin in 1946 Flood Control 
Act. 
Local cooperation. Local interests were to release 
necessary land under their control and give assurance 
that future channel encroachment below damsite would 
be prevented. For enlargement of reservoir to include a 
conservation pool, local interests would contribute onehalf 
additional cost of such pool, including one-half cost 
of relocation of sanitary sewer, and agree to hold the 
United States free from damages resulting from its provision. 
Board of County Commissioners of Hamilton 
County, Ohio, adopted a resolution October 8, 1947, signifying 
willingness to fulfill requirements including provision 
of conservation pool. Assurances were executed on 
same date. A contract with the United States for relocation 
of sanitary sewer outside reservoir area in order to 
include conservation pool in project was accepted by 
Hamilton County, in which the United States paid onehalf 
cost of such relocation work. Hamilton County Commissioners 
furnished $50,000, required as a local contribution 
toward additional cost of providing conservation 
pool. Hamilton County Park District has undertaken 
development and management of recreation facilities in 
reservoir area for use of the public in accordance with the 
license granted by Secretary of the Army on October 31, 
1951. Contract for cost shared recreation development 
under the completed works program was executed by the 
Board of Park Commissioners, Hamilton County Park 
District, Ohio, in September 1975 and approved by the 
Chief of Engineers in December 1975. 
Operations during fiscal year. New work: Cost 
shared recreation development under the completed 
projects program was completed. Maintenance: Contracts 
for repairs to the stilling basin were completed. Routine 
maintenance was performed. Operation for flood control 
during 1983 flood season prevented damages estimated 
at $25,000. 
Construction started in March 1949 and reservoir was 
placed in operation in December 1952. Project is complete. 
36. WILLIAM H. HARSHA LAKE, OH 
Location. Damsite is on East Fork of Little Miami 
River between Batavia and Williamsburg, Ohio, about 6.0 
miles above Batavia and 32.6 miles above mouth of the 
Little Miami River. Entire project lies in Clermont 
County, Ohio. (See U. S. Geological Survey map of 
Batavia, OH.) 
Existing project. A reservoir for flood control and 
allied purposes. It includes an earthfill dam, outlet works, 
an uncontrolled saddle spillway, and a dike to close a saddle 
north of spillway. Total storage capacity of reservoir 
is 294,800 acre-feet, of which 210,600 acre-feet is reserved 
for flood control storage. Estimated cost of new work 
(1983) is $54,755,000 including $3,487,000 non-Federal 
reimbursement for water supply storage. Existing project 
was authorized by general authorization for Ohio River 
Basin in 1938 Flood Control Act. Project name was 
changed from East Fork Lake to William H. Harsha Lake 
effective January 4, 1981 by Public Law 96-383, 
October 6, 1980. 
Local cooperation. None required. However, the 
State of Ohio requested inclusion in the project of storage 
for future municipal and industrial water supply uses. 
Contract with State of Ohio for water supply storage 
under provisions of Water Supply Act of 1958, as amended, 
was approved by Secretary of the Army, May 20, 1970. 
Under terms of contract, State will reimburse the Federal 
Government for costs allocated to water supply storage 
over a period not to exceed 50 years after use of this 
storage is initiated plus estimated annual amount for cost 
of operation, maintenance and major capital replacements 
required for the water supply facilities. 
Operations during fiscal year. New work: Engineering 
and design studies continued. Contracts for Tailwater 
comfort station, electric service to Greenbrier Site, and 
remaining landscapaing were completed. Four contracts 
24-13

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1983 
for rehabilitation of industrial type recreation buildings, 
sewer connection at Tate Site, electric service to Tate Site, 
and bathhouse with landscaping were advanced to 90 percent, 
85 percent, 80 percent and 35 percent completion, 
respectively. Maintenance: Routine maintenance was performed. 
Operation for flood control during 1983 flood 
season prevented damages of $1,703,000. 
Construction was started in May 1970. Engineering 
studies are 93 percent complete. All land required for 
project has been acquired. Major relocation and construction 
features are complete, except several recreation 
items. Project is about 95 percent complete overall and 
was placed in operation in February 1978. 
37. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Flood Control Act of June 22, 1936, and subsequent acts 
require local interests to maintain and operate local protection 
projects in accordance with regulations prescribed 
by Secretary of the Army. Inspections were made to determine 
extent of compliance and to advise interests as 
necessary to measures required to correct deficiencies. 
(See Table 24-K for local protection projects and channel 
improvements inspected.) 
Fiscal year costs were $187,673. Total costs to 
September 30, 1983 were $2,389,882. 
38. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
See Table 24-E. 
39. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Emergency flood control activities pursuant to Public 
Law 99, 84th Congress, and antecedent legislation. 
Costs for fiscal year were $105,521 for disaster 
preparedness and $59,860 for repair work on Russell and 
Allison Levee. 
Flood control activities pursuant to Section 205, 1948 
Flood Control Act, Public Law 858, 80th Congress, as 
amended. Costs for fiscal year were $349,612 for preparation 
of reconnaissance report and detailed project reports 
on 11 projects, and $91,380 for plans and specifications 
and construction on two projects. 
See Table 24-L. 
Snagging and clearing navigable streams and 
tributaries in interest of flood control (Section 208, 1954 
Flood Control Act, Public Law 780, 83rd Congress). Costs 
for fiscal year were $27,325 for preparation of detailed 
project reports on three projects. 
See Table 24-L. 
Emergency bank protection (Section 14, 1946 Flood Control 
Act, Public Law 526, 79th Congress). Costs for fiscal 
year were $22,436 for preparation of reconnaissance 
reports on three projects, $220,664 for plans and specifications 
on 14 projects and $357,204 for construction on 12 
projects. 
See Table 24-L. 
40. STREAMBANK EROSION 
CONTROL EVALUATION AND 
DEMONSTRATION ACT OF 1974 
Costs for fiscal year were $33,907 for completion of 
rehabilitation of the Moscow, OH, Ohio River project. 
General Investigations 
41. SURVEYS. 
Fiscal year costs were $2,395,153, of which $261,105 
was for one navigation study, $1,555,482 for three flood 
damage prevention studies, $293,610 for the Wabash 
River Basin Authorization Report, $5,835 for review of 
completed projects, $79,945 for Special Investigations, 
$22,392 for Federal Energy Regulatory Commission, 
$176,692 for planning assistance to Federal agencies and 
states, and $92 for supplemental preauthorization studies 
(Phase I) on Camp Ground Lake, KY. 
42. COLLECTION AND STUDY 
OF BASIC DATA 
Fiscal year costs were $171,745 for flood plain management 
services. 
43. ADVANCE ENGINEERING 
AND DESIGN 
Fiscal year costs were $168,308 for General Design 
Memorandum studies on Frankfort, Kentucky (South 
Frankfort Section) and $21,948 for alternative water 
supply studies on Louisville Lake, Illinois. 
24-14

TABLE 24-A 
LOUISVILLE, KY. DISTRICT 
COST AND FINANCIAL STATEMENT 
See 
Section Total to 
in Text Project Funding 1980 1981 1982 1983 Sep 30, 1983 
1
1
1 
Navigation - Locks and Dams 
2 Green and Barren New Work 
Rivers, KY Approp. 
Cost 
Maint. 
Approp. 
Cost 
3 Kentucky River, KY New Work 
Approp 
Cost 
Maint. 
Approp. 
Cost 
Minor Rehab. 
Approp. 
Cost 
Flood Control - Local Protection 
7 Dayton, KY New Work 
Approp. 
Cost 
8 Evansville, IN New Work 
Approp. 
Cost 
9 Levee Unit No. 5, New Work 
Wabash River, IN Approp. 
Cost 
0 Mason J. Niblack New Work 
Levee, IN Approp. 
Cost 
1 Mill Creek, OH New Work 
Approp. 
Cost 
2 Southwestern New Work 
Jefferson County, Approp. 
KY Cost 
Flood Control - Reservoirs 
13 Barren River Lake, KY New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
(Contributed Funds) New Work 
Contrib. 
Cost 
14 Brookville Lake, IN New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
(Contributed Funds) New Work 
Contrib. 
Cost 
15 Buckhorn Lake, KY New Work 
Approp. 
Cost 
Maint. 
Approp, 
Cost 
$ - 
1,127,000 
1,212,991 
2,592,000 
2,194,532 
4,885,000 
3,972,216 
1,925,000 
1,384,776 
-100 
16,394 
41,000 
97,460 
50,400 
202,163 
6,050,000 
4,860,517 
-173,712 
603,710 
655,000 
635,202 
68,051 
70,763 
-427,000 
275,178 
411,000 
260,441 
24,841 
482,000 
494,837 
$ - 
1,070,000 
1,014,016 
2,240,000 
2,640,907 
2,841,000 
2,737,531 
1,300,000 
2,369,557 
13,300 
96,544 
-4,000 
13,032 
2,103,000 
1,842,086 
5,000,000 
4,914,329 
14,768 
188,838 
838,000 
853,504 
235,683 
325,000 
405,958 
26,862 
655,000 
552,706 
$ - 
1,279,000 
1,106,928 
790,000 
772,727 
350,000 
1,542,969 
3,500,000 
2,113,939 
600,000 
175,535 
3,080 
8,112 
6,536,000 
2,839,732 
2,995,000 
4,348,890 
895,800 
875,375 
12,100 
5,208 
321,000 
358,813 
166 
586,840 
654,627 
$ - 
2,069,000 
1,695,152 
1,049,000 
881,140 
153,953 
2,381,000 
3,691,346 
790,000 
362,983 
10,825 
16,453 
2,683,600 
5,252,537 
7,028,710 
5,883,989 
1,030,000 
1,054,768 
134,096 
123,811 
360,000 
373,597 
569,000 
577,485 
$13,808,2221 
13,808,2221 
23,358,8482 3 
22,739,4142 4 
4,176,749 
4,176,749 
43,877,0895 6 
43,659,9776 7 
556,956 
556,956 
12,790,2458 
12,419,1388 
25,949,8569 
25,517,7359 
7,679,587 
6,822,082 
4,338,617 
4,336,944 
13,531,842 
12,133,693 
35,011,183 
32,721,615 
27,371,29910 
27,371,29910 
9,882,426" 12 
9,845,11311 13 
108,41814 
108,41814 
37,941,889 
37,876,040 
2,663,189 
2,641,271 
7,592,000 
7,578,738 
11,766,206's 
11,766,20615 
6,772,41016 
6,723,12016 . 
24-15

i 
Total to 
n Text Project Funding 1980 1981 1982 1983 Sep 30, 1983 
Flood Control - Reservoirs 
16 Caesar Creek Lake, OH 
17 Cagles Mill Lake, IN 
18 Camp Ground Lake, KY 
19 Carr Fork Lake, KY 
20 Cave Run Lake, KY 
21 Cecil M. Harden Lake, 
IN 
22 Clarence J. Brown 
Dam & Reservoir, 
OH 
23 Green River Lake, KY 
24 Huntington Lake, IN 
(Contributed Funds) 
25 Louisville Lake, IL 
$3,613,800 $3,574,700 $1,436,000 $ 804,600 $62,992,882 
2,910,844 2,893,288 1,585,052 1,421,753 61,281,165 
245,000 302,000 
242,822 291,592 
-10,200 -28,398 
942 7,960 
262,000 250,000 
243,482 264,505 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp, 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
438,000 
649,378 
623,000 
602,565 
4,181,361 
4,197,084 
360,000 
361,481 
-1,632 
175,081 
337,000 
436,607 
174 
292,000 
287,019 
-68 
61,645 
796,000 
728,675 
-1,032 
101,784 
308,000 
308,931 
103 
503 
-90,000 
-4,450 
362,000 539,000 2,081,463 
354,471 557,474 2,072,352 
- 210,701 4,363,18417 
- 32,054 4,184,53718 
320,000 259,000 3,763,506 
288,677 286,789 3,750,031 
- - 160,773 
- - 160,773 
267,600 1,279,469 48,267,22619 
316,881 1,196,546 48,112,98720 
719,040 676,114 4,310,90021 
663,000 752,337 4,282,18421 
3,026,000 1,704,800 71,805,782 
2,990,290 1,525,688 70,837,266 
405,000 420,000 2,720,546 
375,755 450,667 2,702,780 
- -24,994 6,633,81222 
636 - 6,633,81222 
335,000 285,000 4,439,396 
321,031 294,817 4,429,167 
-40 - 22,083,660 
-40 - 22,083,660 
386,000 291,000 2,463,347 
364,421 318,305 2,456,829 
- -87 33,422,32923 
63,915 5,557 33,422,32923 
839,780 955,000 8,523,24924 
886,496 967,808 8,465,73424 
-8,614 -53,594 19,428,60625 
2,730 -402 19,428,20425 
310,000 419,000 3,331,012 
261,496 387,059 3,240,865 
- - 193,903 
-92 - 193,811 
- - 2,335,81226 
451 - 2,316,22927 
TABLE 24-A 
CONTINUED 
See 
Section 
REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1983 
COST AND FINANCIAL STATEMENT 
885,500 
773,200 
541,000 
522,064 
2,826,300 
3,607,628 
305,000 
290,995 
98,000 
8,400 
472,000 
387,396 
2,000 
17,159 
243,000 
238,878 
129,300 
1,908 
744,000 
706,572 
5,405 
293,000 
285,290 
-2,368 
103,678 
24-16

LOUISVILLE, KY. DISTRICT 
TABLE 24-A COST AND FINANCIAL STATEMENT 
CONTINUED 
See 
Section Total to 
In Text Project Funding 1980 1981 1982 1983 Sep 30, 1983 
Flood Control- Reservoirs 
26 Mississinewa Lake, IN 
(Contributed Funds) 
27 Monroe Lake, IN 
(Contributed Funds) 
28 Nolin Lake, KY 
29 Ohio River Basin, 
Louisville District 
30 Patoka Lake, IN 
(Contributed Funds) 
31 Rough River Lake & 
Channel Improvement, 
KY 
(Contributed Funds) 
32 Salamonie Lake, IN 
(Contributed Funds) 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
$ -40,000 
20,471 
288,000 
283,060 
-3 
27,000 
39,822 
280,000 
269,094 
-72,500 
47,500 
728,000 
707,743 
$ -3,982 
310,560 
282,000 
274,215 
-190 
306,023 
320,000 
303,880 
26,604 
928,000 
876,364 
$ -8,987 
-7,458 
334,000 
300,547 
-13 
$- 4,914 $23,967,53728 
- 23,967,53728 
275,000 3,305,105 
322,806 3,293,695 
- 239,200 
- 237,871 
217,150 -24,373 7,902,82729 
234,343 - 7,902,8279 
352,000 391,000 3,818,36530 
340,491 349,406 3,733,255 
- -217,719 7,797,604 
-217,719 - 7,797,604 
338 
920,920 
944,754 
-5,336 17,195,84131 
-969 17,195,84131 
1,050,000 11,477,41532 
1,052,033 11,404,68232 
- 1,526,142 
- 1,526,142 
1,300,000 2,800,000 
3,939,944 2,073,045 
245,000 227,000 
237,736 231,368 
765,500 833,400 
2,020,856 445,820 
-39,888 2,570 
33,201 19,228 
877,000 1,017,000 
857,706 966,177 
383,270 48,200 53,037,390 
1,340,798 -2,240 52,560,458 
330,000 257,000 1,405,131 
294,910 285,712 1,390,897 
- 325,639 20,229,139 
433,719 214,515 19,876,952 
1,489 
996,240 
967,164 
1,018 
- -26 
74,908 61,925 
262,000 258,000 
262,015 260,106 
- -103 
- -268 
896 
-1,079 
315,000 
257,736 
-46 
-8 10,620,38933 
18 10,620,3893 
1,213,000 11,827,81034 
1,280,131 11,765,99234 
- 22,61214 
- 22,61214 
-208 16,559,905m 
1,956 16,559,9053 
302,000 3,477,313 
349,336 3,462,254 
- 170,697 
- 163,867 
24-17

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1983 
TABLE 24-A COST AND FINANCIAL STATEMENT 
CONTINUED 
See 
Section Total to 
in Text Project Funding 1980 1981 1982 1983 Sep 30, 1983 
Flood Control - Reservoirs 
33 Taylorsville Lake, KY 
(Contributed Funds) 
35 West Fork of Mill 
Creek Lake, OH 
(Contributed Funds) 
36 William H. Harsha 
Lake, OH 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
$7,905,998 
7,427,796 
37,139 
175,000 
162,642 
3,738,000 
2,223,600 
275,000 
266,338 
$17,390,000 
13,684,349 
518,000 
168,013 
$ -5,039 
214,077 
230,000 
233,748 
1,511,000 
2,861,045 
336,000 
342,312 
$14,282,000 
16,510,393 
437,000 
381,940 
55,786 
380,000 
218,997 
1,330,485 
673,045 
378,000 
361,394 
$8,140,081 
7,486,233 
290,000 
257,702 
S816,838 
370,071 
-55,000 
280,000 
428,961 
550,103 
428,000 
440,066 
$77,252,078 
73,739,687 
290,000 
257,702 
1,771,838 
920,024 
3,708,9023 
3,622,24437 
2,915,889 
2,891,152 
50,000 
50,000 
52,000,657" 
51,157,102" 
1,895,366 
1,874,627 
1. Includes $85,000 public works funds. 
2. Includes $2,000 emergency relief funds, $132,744 
"maintenance and operation of dams and other improvements 
of navigable waters" and $3,842,667 expended from 1888 to 
30 June 1936, for operation and care from permanenteindefinite 
appropriation. 
3. Includes $695,000 from Productive Employment 
Appropriation Act (PL 98-8) of 1983. 
4. Includes $156,463 from Productive Employment 
Appropriation Act (PL 98-8) of 1983. 
5. Includes $316,871 under "maintenance and operation of 
dams and other improvements of navigable waters," and 
$6,405,372 expended between July 5, 1885 and June 30, 1937 
on operation and care from permanent indefinite appropriation. 
6. Includes $119,000 from Productive Employment 
Appropriation Act (PL 98-8) of 1983. 
7. Includes $118,988 from Productive Employment 
Appropriation Act (PL 98-8) of 1983. 
8. Includes $12,426 allotted to Bellevue-Dayton and used in 
study of that project. 
9. Includes $11,812 emergency relief funds. 
10. Includes $2,224,948 Code 711 funds and $110,107 Code 
713 funds. 
11. Includes $100,000 Supplemental funds. 
12. Includes $266,900 Special Recreation Use Fees. 
13. Includes $264,064 Special Recreation Use Fees. 
14. Cost sharing for Code 713 recreation facilities. 
15. Includes $61,451 public work acceleration executive 1963 
funds, $143,088 Code 711 funds, and $243,619 Code 712 funds. 
16. Includes $50,240 Special Recreation Use Fees. 
17. Includes $35,814 Code 711 funds and $219,603 Code 713 
funds. 
18. Includes $35,814 Code 711 funds and $40,956 Code 713 
funds. 
19. Includes $76,724 Code 711 funds. 
20. Includes $76,550 Code 711 funds. 
21. Includes $41,854 Special Recreation Use Fees. 
22. Includes $19,683 Code 711 funds and $353,995 Code 713 
funds. 
23. Includes $133,413 Code 711 funds and $183,732 Code 713 
funds. 
24. Includes $100,780 Special Recreation Use Fees. 
25. Includes $155,354 Code 713 funds. 
26. Includes $685,632 advance funding for Government participation 
in the construction of U.S. Route 45 relocation by the 
State of Illinois. 
27. Includes $666,049 for Government participation in the 
construction of U.S. Route 45 relocation by the State of Illinois. 
28. Includes $389,392 Code 713 funds. 
29. Includes $1,185 Code 711 funds and $869,158 Code 713 
funds. 
30. Includes $51,000 from Productive Employment Appropriation 
Act (PL 98-8) of 1983. 
31. Includes $21,897 public works acceleration executive 
1963 funds and $2,598,777 Code 711 funds. 
32. Includes $173,420 Special Recreation Use Fees and includes 
$52,000 Supplemental Funds. 
33. Includes $196,306 public works acceleration executive 
1963 funds, $867,396 Code 711 funds, and $22,612 Code 713 
funds. 
34. Includes $191,640 Special Recreation Use Fees. 
35. Includes $315,549 Code 713 funds. 
36. Includes $615,961 Code 713 funds. 
37. Includes $529,283 Code 713 funds. 
38. Includes $58,571 for preconstruction planning, engineering 
and design completed before FY 1953. 
24-18 
--

LOUISVILLE, KY. DISTRICT 
TABLE 24-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
GREEN AND BARREN RIVERS, KY (See Section 2 of Text) 
Purchase of original improvement 
Construction of Lock 2, Green River 
Construction of Lock 5, Green River 
Construction of Lock 6, Green River 
Appropriated $5,000 for continuing improvements of Green 
River above mouth of Big Barren River, with provision "That the 
Secretary of War may, in his discretion, expend such portion of 
said amount as may be necessary for removal of snags in 
Nolin River" 
Construct new Lock 1 and new Lock and Dam 2, Green River 
Construct new locks at Dam 5, Green River and Dam 1, 
Barren River; modification of Dam 5, Green River, 
widens bends in Bear Creek, KY 
Operation and care of locks and dams with War Department 
Appropriations for rivers and harbors 
Improvement of Nolin River 
Channel enlargement of lower 103 miles of Green River 
Recovation of authorities for improvement of 
Bear Creek and Nolin River 
OHIO RIVER BASIN (Louisville Dist.) (See Section 42 of Text) 
Aug 28, 1937 Construct levee, floodwalls, and drainage structures for protection 
of cities and towns in Ohio River Basin, projects to be selected 
by Chief of Engineers with approval of Secretary of War, at a cost 
not to exceed $24,877,000 for construction 
Jun 28, 1938 Approved general comprehensive plan for flood control and other 
purposes in Ohio River Basin as may be advisable in discretion 
of Secretary of War and Chief of Engineers, and for initiation 
and partial accomplishment of plan, authorized $75 million for 
reservoirs and $50.3 million for local protection works, individual 
projects to be selected and approved by Chief of Engineers subject 
to provision that authorization shall include diversion of Cache River 
above Cairo, Illinois, and protection of area north of Cairo 
drainage district by levees at an estimated cost of $2 million 
Aug 18, 1941 Additional $45 million for further prosecution of comprehensive 
plan for Ohio River Basin 
Dec 22, 1944 Additional $70 million for further prosecution of comprehensive 
plan for Ohio River Basin, including plan of improvement for 
flood control and other purposes in Kentucky River Basin 
Flood protection works at Taylorsville, Kentucky at an 
estimated cost of $129,350 
Channel improvement of lower Rough River and Barnett Creek 
at an estimated cost of $360,000 
Jul 24, 1946 Additional $125 million for further prosecution of comprehensive 
plan, including plan of improvement for flood control in 
Wabash River Basin, Illinois and Indiana, at an estimated cost 
of $9,629,000 
Also, West Fork of Mill Creek at an estimated cost of $1,527,000. 
May 17, 1950 Additional $100 million for prosecution of comprehensive plan 
for Ohio River Basin, including necessary bank stabilization 
measures at New Harmony Bridge, Indiana, at an estimated 
cost of $500,000 
Jul 3, 1958 Flood control Act of 1958 modified comprehensive plan to provide 
for Monroe Reservoir on Salt Creek, White River Basin, Indiana, 
at an estimated cost to the United States of $4,350,000; cost to 
local interests, $5,141,000 
Oct 23, 1962 Flood Control Act of 1962 deleted Jessamine Creek Reservoir 
on Kentucky River, Kentucky, from comprehensive plan for 
Ohio River Basin 
Dec 30, 1963 Additional $150 million for further prosecution of 
comprehensive plan for Ohio River Basin 
Jun 18, 1965 Additional $89 million for further prosecution of 
comprehensive plan for Ohio River Basin 
May 12, 1967 Additional $38 million for further prosecution of 
comprehensive plan for Ohio River Basin 
Aug 13, 1968 Additional $35 million for further prosecution of 
comprehensive plan for Ohio River Basin 
Aug 11, 1888 
Mar 3, 18931 
Jul 13, 1892 
Jul 13, 1902 
Mar 3, 19052 
Mar 3, 1909 
Jul 3, 19302 
Jun 26, 19343 
Aug 30, 19352 
Sep 3, 1954 
24-19 
H. Ex. Doc 111, 49th Cong., 
2d Sess., Annual Report 
1887, p. 1903 
Annual Report, 1891, p.2439 
Annual Report, 1891, p.2478 
S. Doc. 82, 83d Cong., 2d Sess. 
Rivers and Harbors Committee 
Doc. 2, 71st Cong., 1st Session, 
and H. Doc. 685, 69th Cong., 
2d Session" . 
H.D. 480, 72d Congress, 2d Sess. 
S.D. 82, 83d Congress, 2d Sess. 
Flood Control Committee 
Document 1, 75th Congress., 
1st Session 
Flood Control Committee 
Document 1, 75th Cong., 
1st Session 
H. Doc. 504, 78th Congress, 
2d Session 
S.D. 105, 78th Congress, 
1st Session 
H. D. 535, 78th Congress, 
2d Session 
H. D. 197, 80th Congress, 
1st Session 
H.D.198, 80th Congress, 1st Sess 
H. D. 192, 85th Congress, 
1st Session 
H. D. 423, 87th Congress, 
2d Session 
Public Law 88-253, 88th Cong., 
1st Session 
Public Law 89-42, 89th Cong. 
1st Session 
Public Law 90-17, 90th Cong., 
1st Session 
Public Law 90-483, 90th Cong., 
2d Session

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1983 
TABLE 24-B 
CONTINUED 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
OHIO RIVER BASIN (Louisville Dist.) (Cont'd.) 
Jun 19, 1970 Additional $69 million for further prosecution of comprehen- Public Law 91-282, 91st Congress, 
sive plan for Ohio River Basin 2d Session 
Mar 7, 1974 Additional $120 million for further prosecution of comprehen- Public Law 93-251, 93rd Congress, 
sive plan for Ohio River Basin 2d Session 
Mar 7, 1974 Fifty-four local protection projects and one reservoir project in Public Law 93-251, 93rd Congress, 
comprehensive plan for Ohio River Basin were deauthorized 2d Session 
August 5, 1977, under Section 12, Water Resources 
Development Act of 1974 
Two additional local protection projects in comprehensive 
plan for Ohio River Basin were deauthorized November 6, 
1977, under Section 12, Water Resources Development 
Act of 1974 
WABASH RIVER BASIN (See Section 46 of Text) 
Aug 13, 1968 Construction of five multiple purpose reservoirs and one S.D. 96, 90th Congress, 2d Session 
local protection project in Wabash River Basin, IL & IN, with 
proviso that construction of Big Walnut Lake, IN, project 
must be approved by the President. Authorization of $50 
million for initiation and partial accomplishment of project. 
Dec 29, 1981 Two multiple purpose reservoirs in Wabash River Basin were Public Law 97-128, 97th Congress, 
deauthorized 2d Session 
1. Deficiency act. 
2. Authorization for Nolin River and Bear Creek revoked by 
Act of Sep. 3, 1954. 
3. Permanent Appropriations Repeal Act. 
TABLE 24-C OTHER AUTHORIZED NAVIGATION PROJECTS 
(See Section 5 of Text) 
For Last Cost to Sep 30, 1983 
Full Report 
See Annual Operation and 
Name of Project Status Report Construction Maintenance 
Licking River 
Rough River, KY 
Tradewater River, KY 
White River, IN 
Completed 
Completed 
Completed 
Completed 
1901 
1951 
1858 
1909 
$ 13,045 
105,500 
18,568 
119,312 
$ 
101,196 
33,331 
24-20

LOUISVILLE, KY. DISTRICT 
TABLE 24-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to Sep 30, 1983 
Full Report 
See Annual Operation and 
Project and Status' Report For Construction Maintenance 
Local Protection: 
Completed: 
Boone County, KY (Bank Protection & Repair Roads) 
Brookport, IL 
Cannelton, IN 
Cincinnati, OH 
Covington, KY 
Delphi, IN (Wabash River) 
England Pond Levee, IL (Wabash River) 
English, IN (Little Blue River)2 
Gill Township Levee, IN (Wabash River) 
Golconda, IL 
Grassy Creek, Jackson County, IN 
(Muscatatuck River)2 
Harrisburg, IL 
Hawesville, KY 
Indianapolis, IN (Fall Creek Section) 
(White River) 
Indian Creek, Corydon, IN 2 
Jackson, KY (Kentucky River Basin) 
Jeffersonville-Clarksville, IN 
Lawrenceburg, IN 
Lebanon Junction, KY (Salt River Basin)2 
Levee Unit 8, IN (White River) 
Louisville, KY3 
Lyford Levee Unit, IN (Wabash River) 
Mason J. Niblack Levee, IN (Wabash River) 
Mill Creek, Jefferson County, KY2 
Mount Carmel, IL (Wabash River) 
Muncie, IN (White River) 
Neon-Fleming, KY (Kentucky River) 
New Albany, IN 
Newburgh, IN4 
Newport, KY 
Paducah, KY 
Panther Creek, KY (Green River Basin)2 
Portland, IN (Salamonie River)2 
Reevesville, IL (Cache River) 
Rochester & McCleary's Bluff Levee, IL 
(Wabash River) 
Rosiclare, IL 
Saline River & Tribs, IL 
Sturgis, KY 
Taylorsville, KY (Salt River) 
Tell City, IN 
Terre Haute (Conover Levee), IN (Wabash River) 
Town Creek, Harrodsburg, KY2 
Triplett Creek, Morehead, KY (Licking River)2 
Uniontown, KY 
Vincennes, IN (Wabash River)5 
West Terre Haute, IN (Wabash River) 
Active: 
Chaplin River, Perryville, KY2 
Clear Creek, Franklin, OH2 
Dicks Creek, Amanda Station, OH2 
Russell & Allison Levee, IL (Wabash River) 
1977 
1958 
1959 
1957 
1965 
1953 
1972 
1965 
1948 
1960 
1953 
1952 
1955 
1953 
1964 
1957 
1959 
1953 
1967 
1952 
1975 
1944 
1965 
1973 
1972 
1956 
1963 
1957 
1974 
1959 
1959 
1970 
1962 
1954 
1972 
1954 
1981 
1972 
1952 
1956 
1965 
1967 
1972 
1956 
1964 
1977 
$ 392,443 
597,493 
2,068,391 
10,150,935 
7,862,937 
144,563 
734,498 
372,353. 
561,200 
565,333". 
70,304 
870,015 
969,318 
1,859,363 
300,143 
130,952 
4,226,331 
2,433,414 
130,417 
700,534 
26,721,438 
267,391 
1,554,712 
292,710 
1,980,675 
887,835 
86,532 
5,375,471 
52,061 
7,512,987 
4,761,552 
254,031 
237,657 
600,300 
1,079,236 
622,544 
7,826,219 
1,826,776 
373,050 
932,229 
14,913 
56,505 
893,094 
1,070,926 
3,308,940 
1,095,704 
232,960 
161,474 
121,193 
52,088 
24-21

TABLE 24-E 
CONTINUED 
REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1983 
OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to Sep 30, 1983 
Full Report 
See Annual Operation and 
Project and Status' Report For Construction Maintenance 
Inactive: 
Anderson, IN (White River) 
Brevoort Levee, IN (Wabash River) 
Caseyville, KY 
Cloverport, KY 
Concordia, KY 
Frankfort, KY (Kentucky RiverXBenson Creek, 
North Frankfort and South Frankfort Sections)6 
Greenfield Bayou Levee, IN (Wabash River) 
Indianapolis, IN (Warfleigh Section) 
(White River) 
Island Levee, IN (Wabash River) 
Levee Unit 1, IL (Wabash River) 
Lewisport, KY 
Marion, IN (Wabash River) 
Metropolis, IL 
New Harmony Bridge, IL & IN (Wabash River)2 
Owensboro, KY 
Salyersville, KY (Licking River) 
Shawneetown, IL 
Smithland, KY 
Tolu, KY 
West Point, KY 
Reservoirs: 
Active - no FY 1983 expenditure 
Downeyville Lake, IN (Wabash River Basin) 
Inactive: 
Big Pine Lake, IN (Wabash River Basin) 
Big Walnut Lake, IN (Wabash River Basin) 
Booneville Lake, KY (Kentucky River) 
Eagle Creek Lake, KY 
Falmouth Lake, KY (Licking River) 
Lafayette Lake, IN (Wabash River Basin) 
Mining City Lake, KY (Green River) 
Red River Lake, KY (Kentucky River) 
1940 
1954 
1979 
1979 
1976 
1979 
1973 
1979 
1959 
1946 
1977 
1980 
1976 
1975 
1981 
1977 
1976 
$ 5,724 
1,230,873 
2,960,970 
157,935 
153,410 
355,963 
60,000 
209,975 
10,575 
297,624 
12,000 
27,287 
4,490 
1,270,590 
1,009,188 
1,038,595 
702,471 
944,386 
1,200,920 
350,474 
1,794,308 
1. All projects are on Ohio River unless otherwise noted. 
2. Authorized by Chief of Engineers under Section 205, 1948 
Flood Control Act, as amended. 
3. Cost includes $1,716,301 cash contribution from City of 
Louisville. 
4. The Water Resources Development Act of 1974 modified 
the Newburgh Locks & Dam project to include the bank protection 
works at Newburgh, IN. 
5. Partially completed to form a useful unit. Remaining portion 
of project deferred. 
6. Cost includes $161,098 contributed funds. 
24-22

LOUISVILLE, KY. DISTRICT 
TABLE 24-G DEAUTHORIZED PROJECTS 
For Last 
Full Report Federal Contributed 
See Annual Date Funds Funds 
Project Report For Deauthorized Expended Expended 
Flood Control- Local Protection 
Adams Levee, IN (Wabash River) - 1978 $ . 
Alton, IN - 1977-. 
Aurora, IN 1977 35,420- 
Bellevue, KY 1977 12,853. 
Bonpas Creek, IL (Wabash River) 1981. 
Bromley, KY 1977- 
California (Cincinnati) OH - 1977 16,465. 
Carrollton, KY - 1977 9,713 
Cave-in-Rock, IL - 1977. 
Cincinnati, OH (Unit 2) - 1977- 
Cincinnati, OH (Unit 4) - 1977- 
Cleves, OH - 1977 6,343- 
Clinton, IN- 1977 6,848- 
Deer Creek, Prairie, Levee, IN - 1977 - - 
Derby, IN - 1977 - - 
Elizabethtown,, IL - 1977 - - 
Fletcher & Sunshine Gardens Levee, IN - 1977 3,361- 
Grandview, IN- 1977 8,497- 
Honey Creek Levee, IN- 1977 - - 
Leavenworth, IN - 1977 - - 
Levee Unit 1, Eel River, IN - 1977- 
Levee Unit 2, Eel River, IN - 1977- - 
Levee Unit 2, East Fork White River, IN - 1977 - - 
Levee Unit 3, East Fork White River, IN 1938 1977 275- 
Levee Unit 1, Little Wabash River, IL - 1977 - - 
Levee Unit 2, Little Wabash River, IL - 1977 - - 
Levee Unit 2, Wabash River, IL - 1977 - - 
Levee Units 3 and 4, Wabash River, IL 1938 1977 216- 
Levee Unit 6, Wabash River, IL - 1977 9,922- 
Levee Unit 17, Wabash River Basin, IN - 1977 - - 
Levee Unit 1, White River, IN - 1977 - - 
Orleans, IN 1972 1977 13,158- 
Shoals, IN (East Fork White River) 1938 1977-. 
Utica, IN - 1978 - - 
Levee Unit 7, White River, IN - 1977-- 
Levee Unit 9, White River, IN - 1977- 
Levee Unit 10, White River, IN - 1977 - - 
Ludlow, KY- 1977 14,503- 
Madison, IN - 1977 - - 
Mauckport, IN - 1977 - - 
McGinnis Levee, IN 1950 1977 71,049- 
Milton, KY - 1977 - - 
Moscow, IN - 1977 - - 
New Amsterdam, IN - 1977 - - 
New Harmony, IN - 1977- 
New Richmond, IN - 1977 7,104- 
Patriot, IN - 1977 - - 
Prestonville, KY - 1977 - - 
Raccoon Creek Levee, IN - 1977 - - 
Rising Sun, IN - 1977 
Rockport, IN - 1977 
Rome, IN - 1977 
Shufflebarger Levee, IN 1950 1977 64,487 
Sugar Creek Levee, IN 1961 1977 28,061 
Tri Pond Levee, IL 1972 1977 65,510 
Troy, IN - 1977 
Vevay, IN - 1977 
Westport, KY - 1977 
Flood Control - Reservoirs 
Big Blue Lake, IN 1980 1981 1,079,867- 
Clifty Creek Lake, IN 1979 1981 1,016,358- 
Helm Lake, IL 1976 1981 41,616- 
Lincoln Lake, IL 1979 1981 1,331,844- 
Metamora Lake, IN- 1977- 
24-23

TABLE 24-H NAVIGATION LOCKS AND DAMS 
PRINCIPAL FEATURES - GREEN & BARREN RIVERS 
AND KENTUCKY RIVER NAVIGATION SYSTEMS 
Lock Dimensions 
Miles Greatest Length 
Lock above Available Upper Depth of Year 
and Mouth of Distance from Width of For Full Normal Pool Miter Sills Character of Percent Opened to Cost of 
Dam River Nearest Town Chamber Width Lift Elevation Upper Lower Foundation Complete Navigation Lock and Dam 
(feet) (feet) (feet msl) (feet) (feet) 
CONSTRUCTION OF LOCKS AND DAMS, OHIO RIVER- For report on this improvement see this heading under 
Ohio River. 
GREEN AND BARREN RIVERS, KY (See Section 2 of Text) 
Green 
River 
New 1 9.1 Spottsville, KY 84.0 600.0 11.8' 349.1 12.1 11.3 Shale and Coal 100 19562 $5,101,978' 
New 2 63.1 0.3 miles below 84.0 600.0 14.3 363.4 15.0 11.7 Shale 100 19564 4,799271s 
Calhoun, KY 
3 108.5 0.3 miles below 35.8 137.5 17.0 380.4 7.3 5.6 Rock 100 1836 121,377 
Rochester, KY 
4 149.0 Woodbury, KY 35.8 138.0 16.4 396.8 7.1 6.5 Rock 100 1839' 125,718 
5 168.1 0.3 miles below 56.0 360.0 15.2 412.0 a 12.0 9.3 Piles and Rock 100 1905 1,020,868" 
Glenmore, KY 
6 181.7 2.8 miles above 36.0 145.0 9.2 421.1 8.0 8.8 Gravel 100 1905' 168415 
Brownsville, KY 
Barren Barren 
River River 
1 15.0" 0.3 miles above 56.0 360.0 15.2 412.0 12.0 9.3 100 1934 871,5652 
Greencastle, KY 
KENTUCKY RIVER, KY (See Section 3 of Text) Kentucky 
River 
Kentucky 
River 
1 4.0 3.8 miles above 38.0 145.0 8.2 430.0 8.2" 14.8 Rock and Clay 100 1839" 
Carrollton, KY 
2 31.0 Lockport, KY 38.0 145.0 13.9 443.9 7.6 6.1 Rock 100 1839" 
3 42.0 Gest, KY 38.0 145.0 13.2 457.1 8.6 6.5 Rock 100 1844" 1,350,385' 
4 65.0 1.0 mile below 38.0 145.0 13.2 470.3 6.4 7.4 Rock 100 1844" 
Frankfort, KY 
5 82.2 2.8 miles below 38.0 145.0 15.0 485.3 10.0 6.5 Rock 100 1844" 
Tyrone, KY 
6 96.2 21.6 miles below 52.0 147.0 14.0 499.3 9.4 6.4 Rock and Piles 100 1894 314,847 
High Bridge, KY 
7 117.0 0.8 mile below 52.0 147.0 15.3 514.6 9.1 6.9 Rock 100 1897 290788 
High Bridge, KY 
8 139.9 4.7 miles above 52.0 146.0 18.7 533.6 10.6 6.0 Rock 100 1900 275,463 
Camp Nelson, KY 
9 157.5 Valley View, KY 52.0 148.0 17.3 550.6 10.0 6.6 Rock 100 1907 237,646 
10 176.4 1.0 mile below 52.0 148.0 17.0 567.6 9.0 6.0 Rock 100 1907 221,500 
Ford, KY 
11 201.0 17.2 miles below 52.0 148.0 18.0 585.6 10.0 6.0 Rock 100 1906 296,593 
Irvine, KY 
12 220.0 Ravenna, KY 52.0 148.0 17.0 602.6 9.6 6.0 Rock 100 1910 425,693 
13 239.9 2.2 miles below 52.0 148.0 18.0 620.6 9.6 6.0 Rock 100 1915 461,476 
Willow, KY 
14 249.0 Heidelberg, KY 52.0 148.0 17.0 637.6 8.6 6.0 Rock 100 1917 392,902 
1. At normal pool Dam 48, Ohio River, Elev. 337.3, Green 
River datum (Elev. 338.0 Ohio River datum). 
2. New Lock 1 placed in operation May 25, 1956; old Dam 
1, completed 183540, replaced with new cellular concrete 
masonry dam constructed 1970-71 with O&M General funds at 
cost of $822,000. 
3. Does not include $179,110 cost of old Lock and Dam 1. 
4. New Lock and Dam 2, placed in operation June 18, 1956. 
5. Does not include $295,696 cost of old Lock and Dam 2. 
6. Operation discontinued September 30, 1981. 
7. Breaching of dam on May 24,1965, stopped through traffic 
to Bowling Green, KY. 
8. With movable A frame crest 3 feet high. 
9. Operation discontinued Aug. 1, 1951. 
10. Does not include $179,434 cost of old Lock and Dam 5. 
11. Distance from mouth of Green River is 164.5 miles. Lock 
closed to navigation as the result of loss of pool at Green River 
Lock and Dam 4 on May 24, 1965. 
12. Includes $729,269 for new large lock completed in 1934. 
13. At normal pool McAlpine Dam, Ohio River elev. 421.8 
Kentucky River datum (Elev. 420 Ohio River datum). 
14. Reconstruction completed by United States in 1882. 
15. Built by State of Kentucky. Cost given is for repairs by 
United States to Locks and Dams 1 through 5. Original construc 
tion costs to State were: L&D 1, $220,300; L&D 2, $151,983; 
L&D 3, $135,857; L&D 4, $131,607; and L&D 5, $137,436. 
Oi 
0
~i 
Oi 
0
Oi 
x
vi

LOUISVILLE, KY. DISTRICT 
TABLE 24-I OHIO RIVER BASIN 
TOTAL COST OF BASIN PLAN 
(See Section 29 of Text) 
LOCAL PROTECTION 
Type of Estimated Cost2 
Project and Status1 Construction Federal Non-Federal Total 
Completed: 
Barnett Creek, KY (Rough River Basin)3 4 
Brookport, IL5s6 
Cannelton, IN5 7 
Cincinnati, OH5 8 
Covington, KY5 9 
Delphi, IN (Wabash River)5 1o 
England Pond Levee, IL (Wabash River)' 
Golconda, IL5 12 
Harrisburg, IL5 1 o 
Hawesville, KY 513 
Jackson, KY (Kentucky River Basin)5 8 
Jeffersonville-Clarksville, IN 
Lawrenceburg, IN5 
Louisville, KY5 14 
New Albany, IN5 8 
Newport, KY5 7 
Paducah, KY5 7 
Reevesville, IL (Cache River)5 15 
Rochester and McCleary's Bluff Levee, IL 
(Wabash River) 1 
Rough River, KY3 4 
Sturgis, KY (Tradewater River)11 
Taylorsville, KY (Salt River)5 16 
Tell City, IN5 14 
Uniontown, KY5 17 
Vincennes, IN (Wabash River)a 
West Terre Haute, IN (Wabash River) 
Active: 
Dayton, KY4 5 
Evansville, IN4 
Mason J. Niblack Levee, IN 
(Wabash River)4 5 
Russell & Allison Levee, IL 
(Wabash River)5 
Inactive: 
Caseyville, KY5 
Cloverport, KY5 
Concordia, KY5 
Frankfort, KY (Kentucky River)5 
South Frankfort, Area 
Benson Creek Areas 
North Frankfort Area5 
Greenfield Bayou Levee, IN (Wabash River)5 
Island Levee, IN (Wabash River)5 
Lewisport, KY5 
Metropolis, IL5 
New Harmony Bridge, IL and IN 
(Wabash River)5 
Owensboro, KY5 
Shawneetown, IL5 
Smithland, KY5 
Tolu, KY5 
West Point, KY5 
Wilders, KY 
Channel improvement 
Wall and levee 
Wall and levee 
Wall and barrier dam 
Wall and levee 
Levee 
Levee 
Wall and levee 
Wall and levee 
Levee 
Cutoff channel 
Wall and levee 
Wall and levee 
Wall and levee 
Wall and levee 
Wall and levee 
Wall and levee 
Levee 
Levee 
Channel improvement 
Levee 
Levee 
Wall and levee 
Levee 
Wall and levee 
Levee 
Wall and levee 
Wall and levee 
Levee and pump plants 
Levee 
Levee 
Wall and levee 
Levee 
Wall 
Wall and levee 
Wall and levee 
Levee 
Levee 
Wall and levee 
Wall and levee 
Bank protection 
Wall and levee 
Wall and levee 
Wall and levee 
Levee 
Wall and levee 
Wall and levee 
$ 
597,493 
2,068,391 
10,150,935 
7,866,300 
144,563 
734,498 
565,333 
870,015 
969,318 
130,952 
4,226,361 
2,433,414 
2,540,000 
5,375,471 
7,512,987 
4,761,532 
600,300 
1,079,236 
1,826,778 
373,050 
932,229 
1,070,926 
6,426,000 
1,095,704 
8,500 
29,105 
1,309,146 
1,051,102 
17,164 
107,000 
10,900 
20,000 
42,593 
3,000 
590,888 
284,725 
745,000 
740,000 
298,506 
232,000 
40,000 
100,000 
93,000 
63,309 
32,707 
72,153 
285,000 
150,000 
1 
605,993 
2,097,496 
11,460,081 
8,917,402 
161,727 
841,498 
576,233 
890,015 
1,011,911 
133,952 
4,817,249 
2,718,139 
3,285,000 
6,115,471 
7,811,493 
4,993,532 
640,300 
1,179,236 
1,919,778 
436,359 
964,936 
1,143,079 
6,711,000 
1,245,704 
12,866,500 2,043,000 14,909,50018 
54,400,000 7,982,000 63,382,00018 
5,001,000 109,200 5,110,20019 
19,400,000 2,340,000 21,740,000 
396,000 
728,000 
590,000 
6,300,000 
3,340,000 
2,961,000 
4,600,000 
4,630,000 
610,000 
3,070,000 
962,000 
886,000 
1,810,000 
864,000 
303,000 
3,283,000 
10,800,000 
35,000 
193,000 
55,000 
630,000 
1,150,000 
272,100 
1,087,000 
528,000 
243,000 
431,000 
99,000 
195,000 
361,000 
414,000 
35,000 
400,000 
959,000 
431,000 
921,000' 
645,000 
6,930,00018 21 
4,490,00019 
3,233,10022 
5,687,00023 
5,158,00023 
853,00024 
3,501,000 
1,061,0005 
1,081,000 
2,171,000 
1,278,000 
338,000 
3,683,00024 
11,759,000" 
24-25

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1983 
TABLE 24-I 
CONTINUED 
OHIO RIVER BASIN 
TOTAL COST OF BASIN PLAN 
(FLOOD CONTROL) 
(See Section 29 of Text) 
LOCAL PROTECTION 
Type of Estimated Costs 
Project and Status1 Construction Federal Non-Federal Total 
Deauthorized August 5, 1977 under 
Section 12, Water Resources Development 
Act of 1971 (Public Law 93-251): 
Alton, IN 
Bellevue, KY 
Bromley, KY 
Carrollton, KY 
Cave-in-Rock, IL 
Cincinnati, OH (Unit 2) 
Cincinnati, OH (Unit 4) 
Cleves, OH 
Clinton, IN (Wabash River) 
Deer Creek Prairie Levee, IN 
(Wabash River) 
Derby, IN 
Elizabethtown, IL 
Fletcher and Sunshine Gardens Levee, 
IN (Wabash River Basin) 
Grandview, IN 
Honey Creek Levee, IN 
(Wabash River) 
Leavenworth, IN 
Levee Unit 1, Eel River, IN 
(Wabash River Basin) 
Levee Unit 2, Eel River, IN 
(Wabash River Basin) 
Levee Unit 1, Little Wabash River, IL 
(Wabash River Basin) 
Levee Unit 2, Little Wabash River, IL 
(Wabash River Basin) 
Levee Unit 6, Wabash River, IL 
(Wabash River Basin) 
Levee Unit 17, IN 
(Wabash River Basin) 
Levee Unit 1, White River, IN 
(Wabash River Basin) 
Levee Unit 2, White River, IN 
(Wabash River Basin) 
Levee Unit 7, White River, IN 
(Wabash River Basin) 
Ludlow, KY 
Madison, IN 
Mauckport, IN 
McGinnis Levee, IN (Wabash River Basin) 
Milton, KY 
Moscow, OH 
New Amsterdam, IN 
New Harmony, IN (Wabash River) 
New Richmond, OH 
Patriot, IN 
Prestonville, KY 
Raccoon Levee, IN (Wabash River) 
Rising Sun, IN 
Rockport, IN 
Rome, IN 
Shufflebarger Levee, IN 
(Wabash River Basin) 
Sugar Creek Levee, IN 
(Wabash River) 
Tri-Pond Levee, IL (Wabash River) 
Troy, IN 
Vevay, IN 
Westport, KY 
Levee 
Wall and Levee 
Wall and Levee 
Wall and Levee 
Levee 
Wall and Levee 
Wall 
Levee 
Levee 
Levee 
Wall and Levee 
Wall and Levee 
Levee 
Levee 
Levee 
Wall and Levee 
Levee 
Levee 
Levee 
Levee 
Levee 
Levee 
Levee 
Levee 
Levee 
Wall and Levee 
Levee 
Levee 
Levee 
Wall 
Levee 
Levee 
Levee 
Wall and Levee 
Levee 
Wall and Levee 
Levee 
Wall and Levee 
Wall and Levee 
Levee 
Levee 
Levee 
Levee 
Wall and Levee 
Levee 
Wall 
$ 255,000 
1,570,000 
1,250,000 
2,220,000 
661,000 
16,800,000 
14,900,000 
1,240,000 
77,000 
213,000 
553,000 
559,000 
548,000 
580,000 
653,000 
1,470,000 
204,000 
2,090,000 
2,850,000 
3,410,000 
1,160,000 
1,580,000 
2,180,000 
724,000 
1,490,000 
2,540,000 
3,820,000 
506,000 
1,820,000 
2,480,000 
1,170,000 
476,000 
161,000 
3,200,000 
753,000 
1,710,000 
426,000 
896,000 
466,000 
359,000 
2,380,000 
418,000 
2,050,000 
502,000 
1,170,000 
1,610,000 
$ 40,000 
400,000., , 
925,000 
97,000 
125,000 
2,900,000 
621,000 
67,000 
9,000 
10,000: 
67,000 
153,000 
26,000 
133,000 
32,000 
266,000 
40,000 
715,000 
164,000 
136,000 
56,000 
118,000 
116,000 
73,000 
88,000 
745,000 
360,000 
105,000 
104,000 
41,000 
372,000 
13,000 
25,000 
720,000 
372,000 
55,000 
37,000 
280,000 
133,000 
67,000 
90,000 
29,000 
191,000 
133,000 
146,000 
41,000 
$ 295,000 
1,970,000 
2,175,000 
2,317,000 
786,000 
19,700,000 
15,521,000 
1,307,000 
86,000 
223,00024 
620,000 
712,000 
574,00024 
713,000 
685,000 
1,736,000 
244,000 
2,805,000 
3,014,00027 
3,546,00022 
1,216,000 
1,698,00022 
2,296,00027 
797,00027 
1,578,00027 
3,285,000 
4,180,000 
611,000 
1,924,000 
2,521,000 
1,542,000 
489,000 
641,000 
3,920,000 
1,125,000 
1,765,000 
463,0004 
1,176,000 
599,000 
426,000 
2,470,000 
447,000" 
2,241,00020 
635,000 
1,316,000 
1,651,000 
24-26

LOUISVILLE, KY. DISTRICT 
TABLE 24-I 
CONTINUED 
OHIO RIVER BASIN 
TOTAL COST OF BASIN PLAN 
(FLOOD CONTROL) 
(See Section 29 of Text) 
LOCAL PROTECTION 
Type of Estimated Cost' 
Project and Status' Construction Federal Non.Federal Total 
Deauthorized November 6, 1977 under 
Section 12, Water Resources Development 
Act of 1974 (Public Law 93-251) 
Aurora, IN Wall and Levee $4,300,000 $1,190,000 $5,490,000 
California (Cincinnati), OH Wall and Levee 1,750,000 720,000. 2,470,000 
Deauthorized October 3, 1978 under 
Section 12, Water Resources Development 
Act of 1974 (Public Law 93-251) 
Adams Levee, IN (Wabash River) Levee 292,000 14,000 306,00020 
Utica, IN5 Levee 1,570,000 120,000 1,690,000 
Deauthorized May 6, 1981 under 
Section 12, Water Resources Development 
Act of 1974 (Public Law 93-251) 
Bonpas Creek, IL (Wabash River Basin)5 Channel 1,080,000 630,000 1,710,00020 
improvement 
1. All projects are on an Ohio River unless otherwise noted. 
2. Latest cost estimate revision 1954 unless otherwise noted. 
3. Part of Rough River Reservoir and Channel Improvement 
Project, KY. 
4. Details of this project are in individual report. 
5. Also see "Other authorized flood control projects." 
6. See Annual Report for 1958 for details. 
7. See Annual Report for 1959 for details. 
8. See Annual Report for 1957 for details. 
9. See Annual Report for 1965 for details. 
10. See Annual Report for 1953 for details. 
11. See Annual Report for 1972 for details. 
12. See Annual Report for 1960 for details. 
13. See Annual Report for 1955 for details. 
14. See Annual Report for 1962 for details. 
15. Substitute project for Belknap, Karnak, and Ullin, IL, complete. 
See Annual Report for 1954 for details. 
16. See Annual Report for 1952 for details. 
17. See Annual Report for 1956 for details. 
18. Latest cost estimate revision 1983. 
19. Latest cost estimate revision 1979 for pump plants and 1968 
for levee. 
20. Latest cost estimate revision 1973. 
21. Active. 
22. Complete. 
23. Latest cost estimate revision 1978. 
24. Latest cost estimate revision 1960. 
25. Latest cost estimate revision 1971. 
26. Latest cost estimate revision 1977. 
27. Latest cost estimate revision 1961. 
24-27

TABLE 24-I 
CONTINUED 
REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1983 
OHIO RIVER BASIN 
TOTAL COST OF BASIN PLAN 
(FLOOD CONTROL) 
(See Section 29 of Text) 
RESERVOIRS 
Tributary Basin & Estimated Cost' 
Reservoirs Status Stream Federal Non-Federal Total 
Great Miami River: 
Brookville Lake, IN2 
Metamora Lake, IN 
Green River: 
Barren River Lake, KY2 
Green River Lake, KY2 
Mining City Lake, KY 
Nolin Lake, KY2 
Rough River Kentucky2 
Kentucky River 
Booneville Lake, KY2 
Buckhorn Lake, KY2 
Carr Fork Lake, KY2 
Licking River 
Cave Run Lake, KY2 
Falmouth Lake, KY 
Little Miami River: 
Caesar Creek Lake, OH2 
William H. Harsha 
Lake, OH2 
Mill Creek: 
West Fork of 
Mill Creek Lake, OH2 
Wabash River: 
Cagles Mill Lake, IN 2 
Cecil M. Harden Lake, IN2 
Monroe Lake, IN2 
Patoka Lake, IN2 
Active 
Deauthorized 
Active 
Active 
Inactive 
Active 
Active 
Inactive 
Active 
Active 
Active 
Inactive 
Active 
Active 
Active 
Active 
Active 
Active 
Active 
East Fork of Whitewater 
River 
West Fork of Whitewater 
River 
Barren River 
Green River 
Green River 
Nolin River 
Rough River 
South Fork of Kentucky 
River 
Middle Fork of Kentucky 
River 
North Fork of Kentucky 
River 
Licking River 
Licking River 
Caesar Creek 
East Fork of Little Miami 
River 
West Fork of Mill Creek 
Mill Creek 
Raccoon Creek 
Salt Creek 
Patoka River 
$45,533,889 
35,300,000 
27,371,299 
33,422,329 
69,100,000 
17,195,841 
10,620,389 
60,700,000 
11,766,206 
52,253,900 
114,908,000 
165,000,000 
$7,592,0003 
108,418 
186,747 
22,612 
$53,125,889 
35,300,0004 
27,479,7175 
33,609,0765 
69,100,0004 
17,195,841 
10,643,0015 
60,700,0006 
11,766,206 
52,253,900 
- 114,908,0007 
- 165,000,000 
59,817,000 5,033,0008 64,850,000 
51,268,000 3,487,0008 54,755,000 
3,708,902 1,186,7619 4,895,663 
4,363,184 
6,633,812 
7,902,827 
205,000 
353,995 
4,568,1845 
6,987,8075 
8,667,9471� 16,570,774 
52,869,000 25,548,700" 78,417,700 
Latest cost estimate revision 1983 unless otherwise noted. 
Details of this project given in individual report. 
Cash contributions for water supply storage. 
Latest cost estimate revision 1954. 
For Code 713 recreation development. 
Latest cost estimate revision 1975. 
Includes $35,213,000 United States Forest Service cost. 
Reimbursement for water supply storage. 
9. Includes $520,000 for non-Federal cost for sewer relocation 
and dam, $50,000 for contributed funds in fulfillment of project 
authorization, and $615,961 for Code 713 recreation 
development. 
10. Includes $7,797,604 cash contribution for storage for lowflow 
regulation and $870,343 for Code 713 recreation 
development. 
11. Includes $14,173,500 cash contribution for water supply 
storage, and $11,375,200 for initial recreation development. 
24-28 
1. 
2. 
3. 
4. 
5. 
6. 
7. 
8.

TABLE 24-J 
LOUISVILLE, KY. DISTRICT 
WABASH RIVER BASIN 
TOTAL COST OF BASIN PLAN: 
(FLOOD CONTROL) 
(See Section 34 of Text) 
Type of 
Construction Estimated Cost' 
Project or Stream Status Federal Non-Federal Total 
LOCAL PROTECTION 
Marion, IN Wall and Levee Inactive $ 3,900,000 $ 854,000 $ 4,754,0002 
RESERVOIRS 
Big Blue Lake, IN Big Blue River Deauthorized 87,200,000 53,846,0003 141,046,0004 
Big Walnut Lake, IN Big Walnut Creek Inactive 81,800,000 45,069,000s 126,869,0004 
Downeyville Lake, IN Flatrock and Little 
Flatrock Rivers Active 71,200,000 61,833,000 133,033,000 
Helm Lake, IN Skillet Fork Deauthorized 25,171,000 14,829,0007 40,000,0008 
Louisville, Lake, IL9 Little Wabash River Active 102,731,000 15,435,00010 118,166,000 
1. Latest cost revision 1983 unless otherwise noted. 
2. Latest cost estimate revision 1977. 
3. Includes $38,190,000 reimbursable by non-Federal interests 
for water supply and $15,656,000 reimbursable for initial recreation 
facilities. 
4. Latest cost estimate revision 1979. 
5. Includes $26,663,000 reimbursable by non-Federal interests 
for water supply and $18,406,000 reimbursable for initial recreation 
facilities. 
6. Includes $53,084,000 reimbursable by non-Federal interests 
for water supply, $8,749,000 reimbursable for initial recreation 
facilities. 
7. Includes $12,696,000 reimbursable by non-Federal interests 
for water supply and $2,133,000 for recreation facilities. 
8. Latest cost estimate revision 1975. 
9. Details of this project given in individual report. 
10. Includes $8,402,000 reimbursable by non-Federal interests 
for water supply and $6,033,000 reimbursable for initial recreation 
facilities. 
11. Latest cost estimate revision 1982. 
24-29

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 24-K INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
(See Section 37 of Text) 
Fall Spring Fall 
Local Protection Projects Inspection 1982 Inspection 1983 Inspection 1983 
Brevoort Levee, IL Sep May Sep 
Brookport, IL Oct Jun- 
Cannelton, IN Oct Jun- 
Cincinnati, OH Sep Apr Sep 
Covington, KY Sep May Sep 
Dayton, KY - May Sep 
Delphi, IN Aug Apr Aug 
England Pond Levee, IL Sep May Sep 
Evansville, IN Sep May Sep 
Frankfort, KY Sep May Sep 
Gill Township Levee, IN Aug Apr Aug 
Golconda, IL Nov Jun- 
Harrisburg, IL Nov May- 
Hawesville, KY Oct Jun- 
Indianapolis, IN Aug Apr Aug 
Jeffersonville-Clarksville, IN Oct Jun- 
Lawrenceburg, IN Sep Apr Sep 
Lebanon Junction, KY Nov Jun- 
Levee Unit No. 5, IN Oct May- 
Levee Unit No. 8, IN Aug Apr Aug 
Louisville, KY Nov Jul- 
Lyford Levee, IN Sep Apr Aug 
Mt. Carmel, IL Oct May. 
Muncie, IN Aug Apr Aug 
New Albany, IN Nov Jun 
Newport, KY Sep May Sep 
Niblack Levee, IN Sep May Sep 
Paducah, KY Oct Jun 
Reevesville-Cache River, IL Oct Jun- 
Rochester-McCleary's Bluff 
Levee, IL Oct May- 
Rosiclare, IL Nov Jun- 
Shawneetown, IL Nov Jun- 
Sturgis, KY Sep May Sep 
Taylorsville, KY Nov Jun- 
Tell City, IN Oct Jun- 
Terre Haute (Conover Levee), IN Aug Apr Aug 
Uniontown, KY Sep May Sep 
Vincennes, IN Sep May Sep 
West Terre Haute, IN Aug Apr Aug 
24-30

LOUISVILLE, KY. DISTRICT 
TABLE 24-K INSPECTION OF COMPLETED 
CONTINUED FLOOD CONTROL PROJECTS 
(See Section 37 of Text) 
Dates of 
Channel Improvements Inspection 
Cypress Creek, McLean County, KY Mar 1983 
Eel River, Brazil Waterworks, IN Apr 1983 
English, IN (Little Blue River) Jul 1983 
Grassy Creek, Jackson County, IN Dec 1981 
Harrodsburg, KY (Town Branch) Mar 1983 
Indian Creek, Corydon, IN Aug 1983 
Jackson, KY (North Fork Kentucky River) Mar 1983 
Mill Creek, KY Jul 1983 
Morehead, KY (Triplett Creek) Mar. 1983 
Muscatatuck River, Crothersville, IN .Sep 1982 
Neon-Fleming, KY Mar 1983 
Nicholasville (Town Fork) Vicinity, KY Jul 1982 
Panther Creek, Curdsville, KY Mar 1983 
Plum Creek, Spencer County, KY Aug 1983 
Portland, IN (Salamonie River) Aug 1983 
Saline River and Tributaries, IL Nov 1982 
Troublesome Creek, Hindman, KY Mar 1983 
Whitesburg, KY (North Fork Kentucky River) Mar 1983 
Bank Revetments 
Boone County, KY (Ohio River) Apr 1983 
Brandenburg, KY (Ohio River) Aug 1983 
Brownstown, IN (White River) Jul 1983 
Cloverport, KY (Ohio River) Oct 1983 
Eighteen Mile Island, Oldham Co., KY Jul 1983 
Evansville, IN (Ohio River) Sep 1983 
Hawesville, KY (Ohio River) Oct 1982 
Indian Hills, OH (Little Miami River) Apr 1983 
Madison, IN (Ohio River) Apr 1983 
Merom, IN (Wabash River) Sep 1982 
Newburgh, IN (Ohio River) Sep 1983 
New Harmony, IN (Wabash River) Oct 1981 
North Middletown, KY (Stoner Creek) Mar 1983 
Otter Creek Park, KY (Ohio River) Dec 1982 
Patoka River at Jasper, IN Sep 1982 
Rockport, IN (Ohio River) Jun 1983 
South Bank White River, Petersburg, Pike County, IN Apr 1983 
Troy, IN (Ohio River) Sep 1983 
Upper River Rd., Jefferson Co., KY Jul 1983 
24-31

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1983 
TABLE 24-L FLOOD CONTROL WORK 
UNDER SPECIAL AUTHORIZATION 
(See Section 39 of Text) 
Fiscal Year Cost 
"Jobs Bill ' Total 
Flood Control: 
Bee Branch, West Point, KY2 - $ 7,500 
Bonpas Creek, IL3 - 9,235 
Canoe Creek, Henderson, KY2 45 34,008 45,182 
Chaplin River at Perryville, KY4 5 10,700 57,372 
Duck Creek, Elwood, IN3 - 78,103 
Lancassage Creek, Clark Co., IN2 3 127,895 
Lilly Creek, Montgomery Co., OH3 - 34,129 
Little Beaver Creek, Kettering, OH2 3 - 7,512 
Lyford Levee, IN2 - 775 
Melbourne Creek, Melbourne, KY2 - 7,500 
Sugar Creek, Bellbrook, OH2 - 539 
Whitewater River, Hagerstown, IN3 - 65,250 
Snagging and Clearing for Flood Control: 
Lick Creek, Hartford City, IN3 - 13,857 
Salamonie River, Montpelier, IN3 - 13,017 
White River, Rockford, IN3 - 451 
Emergency Bank Protection: 
Great Miami River, Sidney, OH4 5 55,637 66,299 
Licking River, Butler, KY4 5 - 48,452 
Lusk Creek, Golconda, IL4 5 - 68,327 
Ohio River, Daviess Co., KY4 5 752 24,134 
Ohio River, Lewisport, KY4 5 35,798 49,237 
Ohio River, Owensboro, KY4 5 3,231 22,944 
Ohio River, Rockport Landing, IN4 5 32,593 44,284 
Ohio River, Sellersburg, IN4 5 - 15,988 
Ohio River, SR66, Cannelton, IN 4 5 59,475 80,822 
Ohio River, Vanderburgh Co., IN4 5 715 20,435 
Patoka River, Winslow, IN4 5 35,348 48,051 
Skillet Fork, Wayne Co., IL2 - 7,472 
White River, Pike Co., IN4 5 33,885 54,196 
Whitewater River, Levee Rd.,IN2 4 - 19,782 
Whitewater River, St. Mary's Road, IN2 - 7,464 
WTP, Great Miami River, Ross, OH4 5 6 22,416 
1 Productive Employment Appropriation Act (PL 98-8) of 1983 
2 Reconnaissance Report 
3 Detail Project Report 
4 Plans and Specifications 
5 Construction Funds Received 
24-32

HUNTINGTON, WV DISTRICT* 
All cost and financial statements for projects are listed 
at the end of this chapter. All other tables are referenced 
in the text and also appear at the end of this chapter. 
The Huntington District includes central and southeastern 
Ohio, all of West Virginia except the northern 
panhandle and northeastern portion, the eastern portion 
of Kentucky, a portion of midwestern Virginia, a very 
small portion of midwestern Virginia, a very small portion 
of northwestern North Carolina, embraced in the 
drainage basin of the Ohio River and its tributaries from 
approximate river mile 127 (below Pittsburgh, Pa.) to 
approximate river mile 438, immediately upstream from 
Foster, KY. The drainage area of the Huntington 
District is approximately 44,914 square miles. 
IMPROVEMENTS 
Navigation 
1. Construction of Locks and 
Dams on Ohio River .............. 
2. Kanawha River, WV ............ 
3. Open Channel Work, Ohio River ..... 
4. Other Authorized 
Navigation Projects .. .... ..... 
Flood Control 
5. Alum Creek Lake, OH ........... 
6. Beech Fork Lake, WV .... ........ 
7. Bluestone Lake, Ohio 
River Basin, WV ......... 
8. Burnsville Lake, Ohio 
River Basin, WV ............ 
9. Chillicothe, OH ............... 
10. Deer Creek Lake, 
Ohio River Basin, OH . . ......... 
11. Delaware Lake, Ohio 
River Basin, OH ................ 
12. Dewey Lake, Ohio 
River Basin, KY. . . . ............ 
13. Dillon Lake, Ohio 
River Basin, OH ................ 
14. East Lynn Lake, 
Ohio River Basin, WV ........... 
15. Fishtrap Lake, Ohio River Basin, KY . . 
16. Grayson Lake, KY ................ 
17. John W. Flannagan Dam and 
Reservoir, Ohio River Basin,VA ....... 
18. Levisa and Tug Forks of the 
Big Sandy River and Cumberland 
River, KY, WV and VA ........... 
19. Martin, KY ............... . 
20. Massillon, OH . . . . ............ 
21. Muskingum River Lakes, OH ........ 
22. Newark, OH . . . . . ............ 
23. North Branch of Kokosing 
River Lake, OH ................. 
24. 
25. 
North Fork of Pound River Lake, VA 
Ohio River Basin (Huntington District) 
25-2 26. Paint Creek Lake, Ohio 
River Basin, Ohio . . . . . . . . . . . . . . 
25-2 27. Paintsville Lake, KY . . . .... . . . . 
28. R.D. Bailey Lake, WV .............. 
25-2 29. Roseville, OH .......... ...... 
25-2 30. Summersville Lake, Ohio 
River Basin, WV ............. 
25-3 31. Sutton Lake, Ohio River 
Basin, WV . . . ........... . . . 
25-3 32. Tom Jenkins Dam, Ohio 
25-3 River Basin, OH .............. 
33. Yatesville Lake, KY .............. 
25-3 34. Inspection of Completed 
Flood Control Projects .. . .. . .. . . . . 
25-4 35. Flood Control Work Under 
Special Authorization . . . .. . . . ..... 
25-4 General Investigations 
25-4 36. Surveys .................... 
37. Collection and Study of Basic Data 
Tables 
Table 25-A 
Table 25-B 
Table 25-C 
Table 25-D 
Table 25-E 
Table 
Table 
Table 
25-F 
25-G 
25-HI 
Page 
25-7 
25-7 
25-8 
25-8 
25-8 
25-8 
25-9 
25-9 
25-9 
25-9 
25-10 
25-10 
25-10 
. . 25-10 
Cost & Financial Statement . . 25-11 
Authorization Legislation . . . . 25-15 
Other Authorized 
Navigation Projects . 
Not Applicable 
Other Authorized Flood 
Control Projects .. 
Not Applicable 
Deauthorized Projects 
Inspection of Flood 
Control Projects .. . 
...... 25-18 
.. ... 25-19 
...... 25-20 
...... 25-21 
25-1 
.

REPORT OF THE CHIEF OF ENGINEERS, US. ARMY 1988 
Navigation 
1. CONSTRUCTION OF LOCKS AND 
DAMS ON THE OHIO RIVER 
See this heading under Chapter 22- Ohio River 
2. KANAWHA RIVER, WV 
Location. The Kanawha River is approximately 97 
miles in length and is formed by the junction of the 
New and Gauley Rivers, a short distance above 
Kanawha Falls, WV, and flows generally northwesterly 
to the confluence with the Ohio River at Point Pleasant, 
WV. 
Previous projects. For details of previous projects 
see the Annual Reports for 1875,1915 and 1938. 
Existing project. The existing project consists of 
three navigation structures on the Kanawha River. 
London Locks and Dam are located approximately 83 
miles above the mouth of the Kanawha River and 
approximately two miles downstream from 
Montgomery, WV. Marmet Locks and Dam are located 
approximately 68 miles above the mouth of the 
Kanawha River at Marmet, WV. Winfield Locks and 
Dam are located approximately 31 miles above the 
mouth of the Kanawha River at Winfield, WV. Each 
structure has twin locks with usable dimensions of 56 
feet by 360 feet. Another structure is located on the 
Ohio River at approximate river mile 279 and 
approximately nine miles below Gallipolis, OH. This 
structure has two parallel locks, the main lock is 110 
feet by 360 feet. This system of locks and dams provides 
a navigable depth of nine feet from the mouth of the 
Kanawha River to a point approximately 91 miles 
upstream. The existing project was completed at a cost 
of $23,403,201. Construction was initiated in 1931 and 
completed in 1937. For further cost details see Table 
25-B, see also, Appendix C. 
Local cooperation. None required. 
Terminal facilities. There are 79 terminals along the 
Kanawha River located from the mouth of the river to 
30 miles east of Charleston, WV. These terminals are 
constructed principally of steel and wood mooring piles 
and steel pile mooring cells. Seventeen of these 
terminals have railroad connections. One terminal, a 
paved wharf, is owned by the City of Charleston, WV. 
The remaining terminals are privately owned. The 
principal commodities handled are coal, chemicals, 
acids, cement, gasoline and oil, and sand and gravel. 
For further details see the 1962 Annual Report. 
Operations during the fiscal year. The Locks and 
Dams were operated as required and necessary repairs 
and improvements were made to the locks and dams 
as well as to the appurtenant structures and grounds. 
Channel inspections were conducted periodically. A 
contract was awarded for construction of Daniel Boone 
State Park, under the recreation at completed projects 
program was completed in September 1983. 
3. OPEN CHANNEL WORK, 
OHIO RIVER 
See this heading under Chapter 22-Ohio River. 
4. OTHER AUTHORIZED 
NAVIGATION PROJECTS 
See Table 25-C. 
5. ALUM CREEK LAKE, OH 
Location. The damsite is located in Delaware 
County, OH, on Alum Creek, a tributary of Big Walnut 
Creek, approximately 26 miles above the mouth of Alum 
Creek and 15 miles north of Columbus, OH, and 
approximately 157 miles above the mouth of the Scioto 
River. 
Existing project. The existing project consists of a 
rolled earthfill dam 93 feet in height and 10,000 feet 
in length with a gate controlled spillway located in the 
right abutment. The reservoir provides a total storage 
of 134,800 acre-feet and controls a drainage area of 
approximately 123 square miles. See also Appendix A. 
Construction of the dam and appurtenant works was 
initiated in August 1970 and completed in July 1974. 
The 405 tracts of land required for the project have been 
acquired. The full funding estimate for new work 
is $56,640,000 which is to be appropriated and expended 
by the Federal Government. The Sponsor will reimburse 
the Government an estimated $27,910,000, exclusive of 
interest, for cost allocated to water supply. 
Local cooperation. For details of required local 
cooperation see the 1981 Annual Report. 
Operations during the fiscal year. New Work: 
Engineering activities for the remaining work items 
continued. The project is essentially complete, except 
for minor work items such as landscaping and cleanup. 
Operations and Maintenance. The project was 
operated for the benefit of flood control as required, and 
necessary repairs were made to the structure and 
appurtenances. During the fiscal year the project 
prevented flood damages estimated to be $305,000. To 
date, the project has prevented an estimated $35,847,000 
in flood damages. 
6. BEECH FORK LAKE , WV 
Location. The damsite is located in Wayne County, 
WV., on Beech Fork Creek, a tributary of Twelvepole 
Creek, approximately four miles above the mouth of 
Beech Fork Creek and 20 miles above the confluence 
of Twelvepole Creek and the Ohio River. 
Existing project. The existing project consists of a 
rolled earth-fill dam 86 feet in height and 1,080 feet 
in length, an uncontrolled spillway landward of the left 
abutmuent of the dam with a control structure at the 
upstream end. The reservoir provides a total storage 
of 37,540 acre-feet and controls a drainage area of 
approximately 78 square miles. Construction of the dam 
was initiated in December 1972 and completed in 
February 1977. See also Appendix A. The 485 tracts 
of land required for the project have been acquired. The 
full funding estimate for new work is $48,500,000. 
Local cooperation. None required. 
25-2

HUNTINGTON WEST VIRGINIA DISTRICT 
Operations during the fiscal year. New Work: 
Engineering activities for remaining work items 
continued. The project is essentially complete, except 
for remaining recreation facilities, landscaping and 
cleanup. 
Operations and maintenance. The project was 
operated for flood control as required and necessary 
repairs were made to the structure and appurtenances. 
During the fiscal year the project prevented flood 
damages estimated at $14,000. To date the project has 
prevented an estimated $2,481,000 in flood damages. 
7. BLUESTONE LAKE, OHIO RIVER 
BASIN, WV 
Location. The damsite is located on the New River 
in Summers County, WV., approximately three miles 
above Hinton, WV and one mile from the confluence 
of the New and Greenbrier Rivers. The reservoir is 
located in Summers County, WV and Giles County, VA. 
Existing-project. The existing project consists of a 
concrete gravity dam 180 feet in height and 2,048 feet 
in length. Appurtenant structures consist of a gated 
spillway 790 feet in length located in the channel section 
of the dam. The stilling pool is formed by a 23 foot 
highweir located 364 feet downstream of 16 gated sluices 
through the spillway section and discharging into the 
stilling pool. Penstocks were installed at the time of 
construction to permit the future installation of hydropower. 
The reservoir provides for a total storage of 
631,000 acre-feet. See also Appendix A. Construction 
of the dam was initiated in January 1942 and completed 
in April 1952. A total of 338'tracts of land was acquired 
for the project. The Federal cost of the project was 
$29,457,603, which includes expenditures under the 
recreation at completed projects program. For further 
details see the 1939 and 1962 Annual Reports. 
Local cooperation. None required. 
Operations during the fiscal year. Operations and 
Maintenance. The entire project is complete. The 
reservoir was operated for flood control as required and 
necessary repairs were made to the structure and 
appurtenances. The project prevented flood damages 
estimated to be $9,780,000 during the fiscal year. To 
date, the project has prevented an estimated 
$529,900,000 in flood damages. 
8. BURNSVILLE LAKE, OHIO 
RIVER BASIN, WV 
Location. The damsite is located in Braxton County 
WV, on the LIttle Kanawha River, approximately two" 
miles above Burnsville, WV, and 124 miles above the 
confluence of the Little Kanawha River and the Ohio 
River. 
Existing project. The existing project consists of an 
earth embankment dam 80 feet in height and 1,000 feet 
in length with a gated spillway in the left abutment. 
The outlet works is an integral part of the spillway, 
consisting of five sluice gates and one low flow sluice. 
The reservoir provides for a total storage of 65,400 acrefeet 
and controls a drainage area of approximately 165 
square miles. Construction of the dam was initiated in 
June 1973 and completed in February 1976. See also 
Appendix A. The 357 tracts of land required for the 
project have been acquired. The full funding estimate 
for new work is $56,620,000. 
Local cooperation. None Required. 
Operations during the fiscal year. The project is 
essentially completed except for remaining recreation 
facilities, landscaping and cleanup. The project was 
operated for flood control as required and necessary 
repairs were made to the structure and appurtenances. 
To date, the project has prevented an estimated 
$16,605,000 in flood damage. 
9. CHILLICOTHE, OH 
Location. The project is located in Ross County, OH, 
along the right bank of the Scioto River, approximately 
69 miles above the confluence with the Ohio River. 
Existing project. The existing project provides for 
the construction of 10,805 feet of earth levee, four gate 
openings and four pump stations. The full funding 
estimate for new work is $20,750,000 which is to be 
allocated and expended by the Federal Government. 
The project is complete except for landscaping and final 
clean up. The estimated non-Federal cost is $2,390,000. 
Construction of the project was initiated in June 1975 
and became operation for flood control in May 
1983. 
Local cooperation. All requirements for local 
cooperation are complete. For further details see the 
1978 Annual Report. 
Operations during the fiscal year. New Work: 
Engineering and design of the recreation facilities and 
landscaping were completed. The project prevented flood 
damages estimated to be $10,000 during the fiscal year. 
10. DEER CREEK LAKE, 
OHIO RIVER BASIN, OH 
Location. The damsite is located in Pickaway County, 
approximately seven miles south of Mount Sterling, OH 
on Deer Creek, a tributary of the Scioto River, 
approximately 21 miles above the mouth of Deer Creek 
and approximately 106 miles above the mouth of the 
Scioto River. 
Existing project. The existing project consists of a 
rolled earth-filled dam 93 feet in height and 3,880 feet 
in length, a 741 foot concrete gravity channel section 
controlled by three tainter gates, an outlet works 
consisting of five gated sluices through a concrete 
spillway section discharging into a stilling basin and 
an earth dike 15 feet by 4,600 feet in a saddle located 
approximately four miles southwest of the damsite. The 
reservoir provides a total storage of 102,540 acre-feet 
and controls a drainage area of approximately 278 
square miles. Construction of the dam was completed 
25-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
in May 1968. The 138 tracts of land required for the 
project have been acquired. For further project details 
see the 1965 Annual Report. See also Appendix A. The 
Federal cost of the project is $20,406,545, including 
expenditures under the recreation at completed projects 
program. 
Local cooperation. For details of required local 
cooperation see the 1981 Annual Report. 
Operations during the fiscal year. Operations and 
Maintenance. All construction work is complete. The 
reservoir was operated for flood control as required and 
necessary repairs were made to the structure and 
appurtenances. The project prevented an estimated 
$795,000 in flood damages during the fiscal year. To 
date, the project has prevented an estimated $15,653,000 
in flood damages. 
11. DELAWARE LAKE, OHIO 
RIVER BASIN, OH 
Location. The damsite is located on the Olentangy 
River, approximately six miles above and north of 
Delaware, OH, and approximately 32 miles above the 
confluence of the Olentangy and Scioto Rivers at 
Columbus, OH. The reservoir is located in Delaware, 
Marion and Morrow Counties, OH. 
Existing project. The existing project consists of a 
rolled earth-fill dam with a gate controlled ogee type 
spillway and five outlet conduits in the channel. The 
dam is 18,600 feet in length and 92 feet in height. The 
project provides for storage of 132,800 acre-feet and 
controls a drainage area of approximately 381 square 
miles. Construction of the dam was initiated in April 
1946 and completed in July 1948. For further details 
see the 1962 Annual Report. See also Appendix A. Total 
real estate requirements of 7,703 acres of fee acquisition 
and 2,428 acres of flowage easements have been 
completed. The Federal cost for the project was 
$7,631,821. 
Local cooperation. None required. 
Operations during the fiscal year. Operations and 
Maintenance. All construction work is complete. The 
reservoir was operated for the benefit of flood control 
as required, and necessary repairs were made to the 
structure and appurtenances. The project prevented an 
estimated $758,000 in flood damages during the fiscal 
year. To date, the project has prevented an estimated 
$52,063,000 in flood damages. 
12. DEWEY LAKE, OHIO RIVER 
BASIN, KY 
Location. The damsite is located on Johns Creek, 
approximately seven miles southeast of Paintsville, KY 
and approximately six miles above the confluence of 
Johns Creek and the Levisa Fork of the Big Sandy River. 
Existing project. The existing project consists of an 
earthfill dam 118 feet in height and 913 feet in length, 
a controlled outlet works discharging through a channel 
excavated in the left abutment, and a rolled earth-fill 
dike blocking a low divide to Brandykeg Creek and the 
Levisa Fork. The reservoir provides a total storage of 
93,300 acre-feet and controls a drainage area of 
approximately 207 square miles. Construction of the 
dam was initiated in March 1946 and completed in July 
1949. For further project detail see the 1965 Annual 
Report. See also Appendix A. Total real estate 
requirements for the project were 12,458 acres in fee 
and 1,170 acres in flowage easements. The Federal cost 
of the project was $7,845,547, including expenditures 
for recreation under the completed project program. 
Local cooperation. None required. 
Operations during the fiscal year. Operations and 
Maintenance. All construction activities are complete. 
The reservoir was operated for the benefit of flood control 
as required and necessary repairs were made to the 
structure and appurtenances. The project prevented an 
estimated $1,000 in flood damages during the fiscal year. 
To date, the project has prevented an estimated 
$40,699,000 in flood damages. 
13. DILLON LAKE, OHIO RIVER 
BASIN, OH 
Location. The damsite is located on the Licking 
River, approximately six miles above the confluence of 
the Licking and Muskingum Rivers at Zanesville, Ohio. 
Existing project. The existing project consists of a 
rolled earth-fill dam 118 feet in height and 1,400 feet 
in length, a controlled outlet works discharging through 
a 20-foot conduit in the right abutment, and an ungated 
280-foot spillway adjacent to the left abutment of the 
dam, and two rolled earthfill dikes. The reservoir 
provides for a total storage of 261,110 acre-feet and 
controls a drainage area of approximately 748 square 
miles. Construction of the dam was completed in July 
1959. For further project details see the 1962 Annual 
Report. See also Appendix A. Total real estate required 
for the project consists of 8,232 acre in fee and 5,380 
acres of flowage easements. See also Appendix A. 
Federal cost of the project was $30,218,135, including 
expenditures under the recreation at completed projects 
program. 
Local cooperation. None required. 
Operations during the fiscal year. Operations and 
Maintenance. All construction work is complete. The 
project was operated as required for flood control, and 
necessary repairs were made to the structure and 
appurtenances. The project prevented an estimated 
$4,164,000 in flood damages during the fiscal year. To 
date, the project has prevented an estimated $89,215,000 
in flood damages. 
14. EAST LYNN LAKE, OHIO RIVER 
BASIN, WV 
Location. The damsite is located in Wayne County, 
WV approximately six miles southeast of Wayne, WV, 
10 miles above the mouth of East Fork and 42 miles 
above the confluence of Twelvepole Creek and the Ohio 
River. 
Existing project. The existing project consists of an 
earth-fill dam 113 feet in height and 638 feet in length, 
an uncontrolled spillway near the left abutment of the 
25-4

HUNTINGTON WEST VIRGINIA DISTRICT 
dam, and a 13-foot reinforced concrete tunnel in the right 
abutment with a control structure at the upstream end. 
The reservoir provides for a total storage of 82,500 acrefeet 
and controls a drainage area of approximately 133 
square miles. The required 552 tracts of land have been 
acquired. See also Appendix A. The estimated Federal 
costs of the project is $37,026,000. 
Local cooperation. None required. 
Operations during the fiscal year. Operations and 
Maintenance. All major construction work is complete. 
Remaining items include minor recreation, and cleanup. 
The project was operated for flood control as required 
and necessary repairs were made to the structure and 
appurtenances. During the fiscal year the project 
prevented flood damages estimated to be $14,000. To 
date, the project has prevented an estimated $33,431,000 
in flood damages. 
15. FISHTRAP LAKE, OHIO RIVER 
BASIN, KY 
Location. The damsite is located in Pike County, KY, 
on the Levisa Fork of the Big Sandy River, 
approximately 15 miles upstream from Pikeville, KY, 
approximately three miles above the confluence of 
Levisa and Russell Forks and 103 miles above the mouth 
of the Levisa Fork. 
Existing project. The existing project consists of a 
rock-fill dam 195 feet in height and 1,100 feet in length, 
a controlled spillway containing four tainter gates 
located in the valley wall adjacent to the left abutment 
of the dam, the outlet works consists of an intake 
structure with three conduits controlled by slide gates 
and discharging into a horseshoe shaped tunnel. The 
reservoir provides for a total storage of 164,360 acre-feet 
and controls a drainage area of approximately. 395 
square miles. The dam was completed in February 1969. 
The 1,301 tracts of land required for the project have 
been acquired. See also Appendix A. The Federal costs 
for new work, to date, has been $54,662,321, which 
includes expenditures under the recreation at completed 
projects program. 
Local cooperation. None required. 
Operations during the fiscal year. Operations and 
Maintenance. All construction work is complete. The 
project was operated for flood control as required, and 
necessary repairs wer made to the structure and 
appurtenances. To date, the project has prevented an 
estimated $179,361,000 in flood damages. 
16. GRAYSON LAKE, KY 
Location. The damsite is located in Carter County, 
Kentucky on the Little Sandy River approximately 49 
miles above the confluence with the Ohio River, and 
11 miles upstream from Grayson, KY. 
Existing project. The existing project consists of a 
random earthfill dam 120 feet in height and 1,460 feet 
in length, a controlled outlet works discharging through 
a 14-foot spillway beyond the left abutment. The 
reservoir provides for a total storage of 119,000 acre-feet 
and controls a drainage area of approximately 196 
square miles. The dam was completed in January 1968. 
The 484 tracts of land required for the project have been 
acquired. See also Appendix A. Federal costs for the 
project to date have been $19,162,741, which includes 
expenditures for recreation facilities under the 
completed projects program. 
Local cooperation. None required. 
Operations during the fiscal year. Operations and 
Maintenance. All construction work is complete. The 
reservoir was operated for flood control as required and 
necessary repairs were made to the structure and 
appurtenances. During the fiscal year the project 
prevented flood damages estimated to be $300,000. To 
date, the project has prevented an estimated $29,227,000 
in flood damages. 
17. JOHN W. FLANNAGAN DAM AND 
RESERVOIR, OHIO RIVER BASIN, VA 
Location. The damsite is located in Dickenson 
County, VA, approximately four miles northwest of 
Haysi, VA, on the Pound River approximately two miles 
above the confluence of the Pound River and Russell 
Fork and approximately 150 miles above the mouth of 
the Big Sandy River. 
Existing project. The existing project consists of a 
rock-fill dam 252 feet in height and 970 feet in length, 
an outlet tunnel located near the left abutment of the 
dam with a control structure at the upstream end, a 
spillway controlled by six tainter gates located in a 
saddle just upstream from' the damsite. The reservoir 
provides for a total storage of 145,700 acre-feet and 
controls a drainage area of approximately 222 square 
miles. The project was modified to include water quality 
control by adding control gates to the previously 
uncontrolled spillway, which increased the total storage 
capacity by 39,000 acre-feet. The dam was 
completed in December 1963. The 382 tracts of land 
required for the project have been acquired. See also 
Appendix A. The Federal cost for the project, to date 
has been $20,443,623, which includes expenditures for 
recreation under the completed projects program. 
Local cooperation. None required. 
Operations during the fiscal year. Operations and 
Maintenance. All construction work is complete. the 
project was operated for flood control as required and 
necessary repairs were made to the structure and 
appurtenances. To date, the project has prevented an 
estimated $108,320,000 in flood damages. 
18. LEVISA AND TUG FORKS OF 
THE BIG SANDY RIVER AND 
CUMBERLAND RIVER, WV, 
VA, AND KY 
25-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Location. The Levisa and Tug Forks form the Big 
Sandy River at Louisa, KY. The Cumberland portion 
is the Upper Cumberland River Basin above 
Cumberland Falls, KY. The basin is approximately 100 
miles in length and averages approximately 30 miles 
in width in the lower portion and approximately 10 miles 
in width above harlan, KY. The Big Sandy Basin is 
within the Huntington District, and the Cumberland 
Basin is within the Nashville District. This report covers 
that portion of the project located in the Huntington 
District. 
Existing project. The authorization language directs 
the Corps of Engineers to design and construct, at full 
Federal expense, such flood control measures as are 
determined to be necesssary and advisable for the 
communities in the Tug and Levisa Forks and Upper 
Cumberland River basins. The authorization further 
states that such flood control measures would be located 
at or in the vicinity of Pikeville, KY; and Grundy, VA 
on the Levisa Fork; Pineville, KY, on the Cumberland 
River; and Williamson and Matewan on the Tug Fork, 
in order to afford the named communities and other flood 
damaged locations and their immediate environs a level 
of protection against flooding at least sufficient to 
prevent any future losses from the likelihood of flooding 
such as occurred in April 1977. The full funding estimate 
for that portion of the authorized areas consisting of 
the Williamson, WV area, Pineville, KY, Barboursville, 
KY and other detailed studies is $195,700,000. Which 
includes $12,200,000 non-Federal contributions. 
Local cooperation. None required. 
Operations during the fiscal year. Additional 
engineering studies are now underway to determine 
what is necessary and advisable to address the flooding 
problems in both the Levisa Fork Basin and in the Tug 
Fork tributary stream areas. The contract for 
construction of the Pump Station at West Williamson, 
WV was awarded in April 1983 and is 20% complete. 
The overall project is 1% complete. 
19. MARTIN, KY 
Location. The project is located in Floyd County, KY, 
approximately six miles above the mouth of Beaver 
Creek, a tributary of the Levisa Fork of the Big Sandy 
River. 
Existing project. The existing project provides for 
the construction of approximately 4.5 miles of channel 
improvement along Beaver Creek beginning at a point 
approximately 2.3 miles above the junction of the Right 
and Left forks. The improved channel will have a bottom 
width of 75 feet, riprap will be placed along the outside 
of all channel bends and on both sides and the channel 
bottom through three existing bridges. The total 
estimated cost of the project (1981) is $10,190,000. The 
Federal portion of the estimate is $9,850,000 and the 
non-Federal portion is $340,000 for lands and damages 
and utility adjustments. To date, the local sponsor has 
acquired approximately 67% of the real estate required 
for the project. 
Local cooperation. For details of required local 
cooperation see the 1981 Annual Report. 
Operations during the fiscal year. All engineering 
studies are complete and no further activities are 
planned pending fulfillment of local cooperation 
requirements. 
20. MASSILLON, OH 
Location. The project is located in Stark County, on 
the Tuscarawas River, approximately 200 miles above 
the mouth of the Muskingum River. 
Existing project. The existing project consists of 
channel improvement to the Tuscarawas River, 
combined with the construction of drainage facilities, 
levees and pump stations. For further details see the 
1962 Annual Report. Construction was initiated in July 
1940 and completed in October 1951. 
Local cooperation. None required. See the 1962 
Annual Report for details of local contribution of work 
beyond the scope of the project. 
Operations during the fiscal year. Routine 
inspections were conducted to determine that the 
improved channel was maintained in satisfactory 
condition. 
21. MUSKINGUM RIVER LAKES, OH 
Location. The Muskingum River lies in Southeast 
Ohio and including tributaries, drains approximately 
8,000 square miles. The headwaters rise about 25 miles 
south of Lake Erie and flow into the Ohio River at 
Marietta, OH, 172 miles below Pittsburgh, PA. 
Existing project. The existing project consists of the 
construction and operations and maintenance of 14 
reservoirs and appurtenant works in the Muskingum 
River Basin. The existing project originally authorized 
by the Public Works Administration in February 1934. 
Construction of the system was initiated in January 
1935 and completed in November 1938. The system was 
initially operated and maintained by the Muskingum 
Watershed Conservancy District of Ohio, the sponsoring 
agency, from July 1938 to August 1939 when operation 
and maintenance became the responsibility of the Corps 
of Engineers in accordance with the provisions of the 
1939 Flood Control Act. For further project details, see 
the 1962 Annual Report. See also Appendix A. The cost 
of new work to date is $41,247,815, which includes 
expenditures , for recreation facilities under the 
completed project program. A significant Major 
Rehabilitation program was approved in December 1977 
in order to assure the integrity of the existing 14 
structures under the originally designed maximum pool 
conditions. Underseepage and abutment seepage 
problems are being corrected through the installation 
of downstream blankets and/or relief wells and grouting. 
The estimated full funding cost of the rehabilitation 
program is $46,500,000. A related but separate program 
entitled Dam Safety Assurance has been initiated. 
Under current hydrologic design standards, deficiencies 
exist in the spillways at all the 14 projects in the system. 
25-6

HUNTINGTON WEST VIRGINIA DISTRICT 
Corrective measures include widening present 
spillways, constructing new spillways and installing 
parapet walls on top the dams. The full funding estimate 
for the Dam Safety Assurance Program is $111,000,000. 
Local cooperation. All requirements for local 
cooperation have been met. For further details see the 
1942 Annual Report. 
Operations during the fiscal year. New Work. The 
Major Rehabilitation is continuing as scheduled. Thus 
far, sixteen contracts have been awarded and the 
program is 35% complete. The Dam Safety Assurance 
program was initiated during FY 1982 when the initial 
construction contract was awarded. The Dam Safety 
Assurance program is 4% complete. 
Operations and Maintenance. The reservoirs were 
operated for flood control as required, and the necessary 
repairs were made to the structures and appurtenances. 
The system prevented an estimated $58,564,000 in flood 
damages during the fiscal year. To date, the system has 
prevented an estimated $974,250,000 in flood damages. 
22. NEWARK, OHIO 
Location. The project is located in Licking County 
at the junction of the North and South Forks of the 
Licking River, approximately 29 miles above the 
confluence with the Muskingum River at Zanesville, 
OH. 
Existing project. For details of the existing project 
see the 1981 Annual Report. Construction of the existing 
project was initiated in July 1940 and completed in 
November 1941. As a result of the 1968 Flood Control 
Act the existing project was modified to include 
improvement of the interior drainage facilities, 
construction of Log Pond Run diversion channel and 
modification of the North Fork Channel. Construction 
of the Log Pond Run diversion channel was awarded 
in September 1980 and completed in December 1981. 
The full funding estimate for the project is $10,500,000 
Federal cost and $785,000 non-Federal. 
Local cooperation. For details of required and 
completed local cooperation see the 1981 Annual Report. 
Operations during the fiscal year. New Work: 
North Fork Channel - As a result of withdrawal of State 
support for the Utica Lake project (now inactive) and 
the interdependency of the operation of Utica with the 
North Fork Channel, the North Fork Channel portion 
of the project required re-formulation. A reanalysis is 
complete. Interior Damage - considerable change has 
occurred in city storm drainage due to road construction 
and a newly constructed interceptor sewer. Current 
drainage patterns must be determined before feasibility 
of additional pumping can be analyzed. 
Operations and Maintenance: Routine inspections 
were conducted to determine that the improved channel 
was maintained in satisfactory condition. 
23. NORTH BRANCH OF KOKOSING 
RIVER LAKE, OH 
Location. The damsite is located in Knox County, 
OH, on the North Branch of Kokosing River, 
approximately nine miles above the confluence of the 
Kokosing and North Branch Rivers, and 2 miles 
northwest of Fredericktown, OH. 
Existing project. The existing project consists of a 
rolled-earth dam, 70 feet in height and 1,400 feet in 
length with an uncontrolled spillway adjacent to the 
right abutment, and an uncontrolled, reinforced concrete 
outlet work located in the right abutment of the dam. 
The reservoir provides for a total storage of 14,885 acrefeet 
and controls a drainage area of approximately 45 
square miles. the 56 tracts of land required for the project 
have been acquired. Construction of the dam was 
completed in May 1972. See also Appendix A. The 
Federal cost for new work to date is $6,266,186, which 
includes expenditures under the recreation at completed 
projects program. 
Local cooperation. None required. 
Operations during the fiscal year. Operations and 
Maintenance. All construction work is complete. 
Necessary repairs were made to the structure and 
appurtenances. 
24. NORTH FORK OF POUND RIVER 
LAKE, VA 
Location. The damsite is located in Wise County, VA, 
on the North Fork of Pound River, approximately one 
mile upstream from the confluence of the North and 
South Forks which form the Pound River and 
approximately three miles upstream from Pound, VA. 
Existing project. The existing project consists of a 
rockfill dam, 130 feet in height and 600 feet in length, 
an uncontrolled spillway in a saddle upstream from the 
dam, and an outlet tunnel in the right abutment with 
a control structure at the upstream end. The reservoir 
provides a total storage of 11,300 acre-feet and controls 
a drainage area of approximately 17 square miles. The 
127 tracts of land required for the project have been 
acquired. Construction of the dam was completed in 
January 1966. See also Appendix A. The Federal costs 
for the project to date is $6,186,901, which includes 
expenditures for recreation under the completed projects 
program. 
Local cooperation. None required. 
Operations during the fiscal year. Operations and 
Maintenance. All construction is complete. The project 
was operated as required for flood control and the 
necessary repairs were made to the structure and 
appurtenances. To date, the project has prevented an 
estimated $2,293,000 in flood damages. 
25. OHIO RIVER BASIN 
(HUNTINGTON DISTRICT) 
Location. The work covered by this project consists 
of a series of levees, floodwalls, channel improvements 
and dams and lakes in the Ohio River Basin within 
the Huntington District. 
25-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Existing project. The existing project consists of the 
individual projects considered in the Ohio River Basin 
comprehensive plan within the Huntington District. 
Operations during the fiscal year. The completed 
local protection porjects, which are operated and 
maintained by local interest, except for those local 
protection projects for which individual reports have 
been included, prevented flood damages of an estimated 
aggregate total of $7,202,000. 
26. PAINT CREEK LAKE,OHIO 
RIVERBASIN,OH 
Location. The damsite is located in Ross County, 
Ohio, on Paint Creek, a tributary of the Scioto River, 
approximately 37 miles above the mouth of Paint Creek 
and 100 miles above the mouth of the Scioto River and 
approximately four miles east of New Parkersburg, OH. 
Existing project. The existing project consists of a 
rock and random earth fill dam, 118 feet in height and 
700 feet in length, a gale controlled spillway located 
near the right abutment, an outlet tunnel located in 
the right abutment with a control structure at the 
upstream end, and a random rockfill dike located at the 
right abutment of the spillway. The reservoir provides 
for a total storage of 145,000 arcre-feet and controls a 
drainage area of approximately 576 square miles. 
Construction of the dam was completed in July 1973. 
The 257 tracts of land required for the project have been 
acquired. See also Appendix A. Federal costs for the 
project to date have been $26,969,962, which includes 
expenditures under the recreation at completed projects 
program. 
Local cooperation. For details of required local 
cooperation see the 1981 Annual Report. 
Operations during the fiscal year. Operations and 
Maintenance. All construction work is complete. The 
reservoir was operated for flood control as required and 
the necessary repairs were made to the structure and 
appurtenances. During the fiscal year the project 
prevented an estimated $1,958,000 in flood damages. 
To date, the project has prevented flood damages 
estimated to be $35,044,000. 
27. PAINTSVILLE LAKE, KY 
Location. The damsite is located in Johnson County, 
KY, on Paint Creek, a tributary of the Levisa Fork of 
the Big Sandy River, approximately eight miles above 
the mouth of Paint Creek, and four miles west of 
Paintsville, KY. 
Existing project. The existing project consists of a 
rockfill dam 153 feet in height and 1,560 feet in length, 
an uncontrolled spillway located southwest of the right 
abutment of the dam, and an outlet tunnel in the right 
abutment with a control structure at the upstream end. 
The reservoir provides for a total storage of 76,642 acrefeet 
and controls a drainage area of approximately 93 
square miles. The 635 tracts of land required for the 
project have been acquired. Construction of the dam was 
initiated in September 1976 and was completed in 
September 1980. The full funding estimate for new work 
is $61,000,000, which is to be appropriated and expended 
by the Federal Government. The local sponsor will 
reimburse the Government an estimated $3,365,000 for 
the cost sharing portion of recreation development. 
Operations during the fiscal year. New Work: The 
project is well advanced in the construction phase. 
Remaining work items include completion of reservoir 
clearing, remaining highway relocations, recreation 
items, landscaping and cleanup. Pool impoundment was 
initiated in September 1982. To date, involuntary 
impoundments have prevented an estimated $3,913,000 
in flood damages. 
28. R.D. BAILEY LAKE, WV 
Existing project. The damsite is located in Wyoming 
County, WV, on the Guyandotte River approximately 
108 miles above the confluence with the Ohio River and 
one mile east of Justice, WV. 
Existing project. The existing project consists of a 
rolled rockfill dam with a concrete face, 305 feet in 
height and 1,330 feet in length, an uncontrolled spillway 
located in a saddle in the right abutment of the dam, 
and an outlet tunnel in the left abutment with a control 
structure located at the upstream end. The reservoir 
provides for a total storage of 203,700 acre-feet and 
controls a drainage area of approximately 540 square 
miles. Construction of the dam was initiated in 
November 1973 and completed in December 1979. See 
also Appendix A. The full funding estimate for new work 
is $193,650,000. 
Local cooperation. None required. 
Condition at the end of the fiscal year. New Work: 
Construction of the project is well advanced. The 
remaining work items include remaining recreation, 
landscaping and cleanup. 
Operations and Maintenance. The reservoir was 
operated for flood control as required and necessary 
repairs were made to the structure and appurtenances. 
To date, the project has prevented flood damages 
estimated to be $28,180,000. 
29. ROSEVILLE, OH 
Location. The project is located in Muskingum and 
Perry Counties, on Moxahala Creek, approximately six 
miles the confluence with Jonathan Creek, a tributary 
of the Muskingum River. 
Existing project. The existing project consists of 
7,291 feet of channel improvement; 6,400 feet of levee 
and railroad embankment enlargements; and the 
necessary appurtenances for interior drainage. Total 
Federal cost of the project was $910,785. Construction 
was initiated in August 1959 and completed in October 
1960. 
Local cooperation. All requirements for local 
cooperation have been completed. See also the 1962 
Annual Report. Total costs of local requirement were 
$62.000. 
25-8

HUNTINGTON WEST VIRGINIA DISTRICT 
Operations during the fiscal year. Routine 
inspections of the improved portion of the project were 
conducted to determine that the project was maintained 
in satisfactory condition. 
30. SUMMERSVILLE LAKE, OHIO 
RIVER BASIN, WV 
Location. The damsite is located at Ruckers Bend 
in Nicholas County on the Gauley River approximately 
35 miles above the confluence of the Gauley and New 
River at Gauley Bridge, WV. 
Existing project. The existing project consists of a 
rockfill dam having a height of 357 feet and a length 
of 2,280 feet, an outlet tunnel in the right abutment 
with a control structure located at the upstream and, 
an uncontrolled spillway located west of the right abutment 
and two earthfill dikes. The reservoir provides for 
a total storage of 413,800 acre-feet and controls a drainage 
area of 803 square miles. See also Appendix A. Construction 
of the dam was initiated in March 1960 and 
completed in March 1966. A total of 9,346 acres of land 
were acquired for the project. The Federal costs of the 
project, to date, have been $48,350,422, which includes 
expenditures under the recreation at completed projects 
program. 
Local cooperation. None required. 
Operations during the fiscal year. All construction 
work is complete, except for minor sanitary facilities 
under the recreation at completed projects program. The 
project was operated for flood control as required and 
necesssary repairs were made to the structures and 
appurtenances. The project prevented an estimated 
$2,008,000 in flood damages during the fiscal year. To 
date, the project has prevented an estimated 
$219,329,000 in flood damages. 
31. SUTTON LAKE, OHIO RIVER 
BASIN, WV 
Location. The damsite is located on the Elk River 
in Braxton County approximately one mile above Sutton, 
WV and 101 miles above the mouth of the Elk River. 
Existing project. The existing project consists of a 
concrete gravity dam having a height of 220 feet and 
a length of 1,178 feet, a gated spillway in the channel 
section of the dam, comprised of six tainter gates supported 
by piers, an outlet works comprised of five gate 
sluices through the spillway section. The reservoir provides 
for a storage of 265,300 acre-feet and controls a 
drainage area of 537 square miles. See also Appendix 
A. Construction of the dam was initiated in September 
1956 and completed in June 1960. A total of 13,154 acres 
of land were acquired for the project. The Federal costs 
of the project, to date, have been $38,839,961, which 
includes expenditures under the recreation at completed 
projects program. 
Local cooperation. None required. See the 1981 
Annual Report for contributed funds. 
Operations during the fiscal year. All construction 
work is complete. The project was operated for flood 
control as required and necessary repairs were made 
to the structure and appurtenances. The project 
prevented an estimated $7,850,000 in flood damages 
during the fiscal year. To date, the project has prevented 
an estimated $143,074,000 in flood damages. 
32. TOM JENKINS RESERVOIR, 
OHIO RIVER BASIN, OH 
Location. The damsite is located in Athens County, 
on the East Branch of Sunday Creek, a tributary of the 
Hocking River, approximately three miles north of 
Glouster, Ohio and 57 miles above the mouth of the 
Hocking River. 
Existing project. The existing project consists of a 
rolled-earth dam, 84 feet in height and 944 feet in length, 
a controlled works discharging through a tunnel in the 
left abutment, and an uncontrolled spillway in the ridge 
running south from the damsite. The reservoir, known 
as Burr Oak Lake, provides for a total storage of 26,900 
acre-feet and controls a drainage area of approximately 
33 square miles. See also Appendix A. Construction of 
the project was initiated in March 1948 and completed 
in February 1950. A total of 100 acres of land were 
acquired for the project. The Federal costs of the project 
were $2,116,503, which includes expenditure for 
recreation at completed project. 
Local cooperation. All requirements of local 
cooperation have been met, see also the 1962 Annual 
Report. Contributed funds in the amount of $575,000 
have been received from the State of Ohio. 
Operations during the fiscal year. All construction 
work is complete. The project was operated for flood 
control as required and necessary repairs were made 
to the structure and appurtenances. During the fiscal 
year the project prevented flood damages estimated to 
be $352,000. To date, the project has prevented an 
estimated $8,911,000 in flood damages. 
33. YATESVILLE LAKE, KY 
Location. The damsite is located in Lawrence County, 
on Blaine Creek, a tributary of the Big Sandy River, 
approximately five miles west of Louisa, KY and 18 
miles above the mouth of Blaine Creek. 
Existing project. The existing project provides for 
the construction of an earthfill dam, 104 feet in height 
and 770 feet in length, an uncontrolled spillway located 
approximately one-half mile east of the right abutment 
of the dam, and an outlet tunnel through the left 
abutment of the dam with a control structure at the 
upstream end. The reservoir will provide a total storage 
of 86,951 acre-feet and control a drainage area of 208 
square miles. The estimate for new work is $89,600,000 
(1983), which will be allocated and expended by the 
Federal Government. The sponsor will reimburse the 
Government an estimated $5,170,000 for the cost 
sharing portion of the recreation development. To date, 
281 of the required 499 real estate tracts have been 
acquired. A contract for construction of the dam was 
awarded in January 1977 and was terminated for the 
convenience of the Government in August 1977. 
Operations during the fiscal year. New Work: 
Congress appropriated funds in fiscal year 1981 to 
25-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1988 
resume project construction, and work progressed until 
March 1981 when the administration directed a deferral 
action which resulted in a substantial reduction in 
project funds and the elimination of any 
recommendation for funding in fiscal year 1982 and 
1983. Congressional action provided fiscal year 1982 
funding for the project and funds were made available 
to the district with guidance restricting the application 
of dollars. No funds are contained in the 
Administration's Budget Recommendation to Congres 
for fiscal year 1984. However, funds were added to the 
FY-1984 Appropriations Bill by the Congress, with 
language which stated in part the funds would remain 
available to the project until expended. The language 
is currently being reviewed by Army Counsel. 
34. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
The flood control act of June 22, 1936 and subsequent 
acts require local interest to furnish assurances that 
they will operate and maintain certain local protection 
projects after completion in accordance with 
regulationsprescribed by the Secretary of the Army. 
District Engineers are responsible for the 
administration of these regulations within their 
respective districts. Maintenance inspections were made 
during the fiscal year of those completed units 
transferred to local interests for operation and 
maintenance. Local interests were advised, as necessary, 
of measures required to maintain the projects in 
accordance with the standards prescribed by 
regulations. Total costs for fiscal year 1983 were 
$102,536. Total cost to September 30, 1983 were 
$1,051,364. The flood control works. inspected and the 
dates of inspection are tabulated in Table H. 
35. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Emergency bank protection activities pursuant to 
Section 14 of the 1946 Flood Control Act, Public Law 
526, 79th Congress are tabulated as follows: 
Location FY 1983 Cost 
Apple Creek, Apple Creek, OH $ 9,426 
Gnadenhutten, OH 20,269 
Ohio River and Duck Creek, Marietta, OH 60,110 
Flood control activities pursuant to Section 205 of the 
1948 Flood Control Act, Public Law 853, 80th Congress 
are tabulated as follows: 
Location FY 1983 Cost 
Blacklick Creek, Reynoldsburg, OH 
Blacklick Creek, Franklin County, OH 
Laurel Fork, Matheny, WV 
Marsh Fork, Fairdale, WV 
Sandy Creek, Malvern, OH 
Upper Scioto River, Marion County, OH' 
$ 41,955 
8,970 
43,821 
80 
1,532 
15,756 
Stream erosion control, evaluation, demonstration 
pursuant to Section 32 of the 1974 Water Resources 
Development Act, Public Law 251, 93rd Congress are 
tabulated as follows: 
Demonstration Projects at Undesignated Sites $ 67 
Ohio River Demonstration Projects 298 
Rehab ofStreambank Demonstration Projects 211,728 
Flood control and coastal emergency activities 
pursuant to Public Law 99, 84th Congress were 
conducted as required during FY 1983 at a cost of 
$77,871. 
National emergency management activities were 
accomplished by the district as required. The costs for 
these activities during FY 1983 were $114,668. 
36. SURVEYS 
Fiscal year 1983 costs were $5,316,239 itemized as 
follows: 
Navigation Studies $ 1,574,489 
Flood Damage Prevention Studies 799,004 
Comprehensive Basin Studies 343,719 
Review of Authorized Projects 9 
Miscellaneous Activities 99,910 
Coordination Studies 156,853 
Supplemental Pre-Authorization 2,821 
Continuation of Planning and Engineering 2,339,434 
37. COLLECTION AND STUDY OF 
BASIC DATA 
Fiscal year costs were $161,612. 
25-10

HUNTINGTON WEST VIRGINIA DISTRICT 
TABLE 25-A COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY 80 FY 81 FY 8 FY 83 Sept.30,1983 
2. Kanawha River, 
WV 
5. Alum Creek Lake, 
OH 
6. Beech Fork Lake, 
WV 
7. Bluestone Lake, 
Ohio River Basin, 
WV 
8. Burnsville Lake, 
Ohio River Basin, 
WV 
9. Chillicothe, OH 
10. Deer Creek Lake 
Ohio River Basin, 
OH 
11. Delaware Lake, 
Ohio River Basin, 
OH 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
- 45,000 619,317 0 27,831,6991 
- 36,203 63,936 430,292 27,697,813' 
2,511,273 4,328,000 4,290,000 4,996,000 54,389,584 s 
2,551,386 4,195,100 3,945,120 5,156,126 53,711,054' 
- - - 130,394' 
- - - 130,394' 
1,470,000 1,870,000 2,130,000 165,591 56,333,655 
1,453,947 1,946,955 266,351 1,265,550 55,396,401 
270,715 404,000 493,900 462,000 2,698,065 
275,565 380,678 489,002 466,979 2,669,487 
825,000 880,000 1,245,000 1,700,000 38,691,500 
1,001,244 755,144 1,084,855 1,812,526 38,371,840 
438,556 502,500 562,000 486,000 2,880,039 
435,941 498,904 562,079 502,334 2,874,564 
120,000 
72,194 
-803 
6,851 
-9,461 
487,618 645,000 669,000 
586,224 630,392 660,586 
- 29,458,652' 
29,457,6036 
763,000 8,892,078 
749,878 8,822,330 
540,000 760,000 7,000,000 4,200,000 55,695,265 
683,890 639,185 6,816,907 3,394,211 54,370,206 
453,117 523,200 622,000 
421,624 532,657 613,160 
434,000 7,550,000 5,600,000 
362,619 7,637,269 5,134,146 
664 - - 
4,793 - - 
389,802 373,000 445,000 
418,619 365,310 407,829 
288,348 307,000 433,000 
290,102 284,545 440,228 
565,000 3,061,505 
575,697 3,033,843 
696,000 20,750,099 
385,470 19,943,564 
- 20,406,545' 
- 20,406,545' 
621,000 4,337,3648 
633,824 4,288,748' 
- 7,631,821 
- 7,631,821 
884,000 4,727,71910 
561,287 4,380,6641 
25-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 25-A (CONT'D) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY 80 FY 81 FY 82 FY 83 Sept.30, 1983 
12. Dewey Lake, 
Ohio River Basin, 
KY 
13. Dillon Lake, 
Ohio River Basin, 
OH 
14. East Lynn Lake, 
Ohio River Basin, 
WV 
15. Fishtrap Lake, 
Ohio River Basin, 
KY 
16. Grayson Lake, 
KY 
17. John W. Flannagan 
Dam and Reservoir, 
Ohio River Basin, 
VA 
18. Levisa and Tug Forks 
of the Big Sandy River 
and Cumberland River, 
KY, WV, and VA 
19. Martin, KY 
20. Massillon, OH 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
-2,020 7,845,54712 
7,845,54712 
586,916 556,000 624,200 
596,546 550,024 646,564 
774,500 8,380,97618 
794,093 8,375,64814 
- - - - 30,218,135 
- - - - 30,218,135 
187,556 209,000 228,000 425,000 3,148,84315 
190,062 214,476 225,591 373,508 3,090,14616 
1,764,000 700,000 
1,356,942 852,489 
- 2,200,000 37,025,968 
201,205 2,348,307 36,942,057 
670,645 705,000 809,920 850,100 
597,963 681,167 791,773 855,404 
-2,384 
6,409 
- 106,000 
4,652 22,818 
6,358,907 
6,314,402 
- 54,672,09318 
73,410 54,662,32119 
1,045,198 573,000 685,000 945,000 3,286,1982 
1,020,942 574,633 658,909 861,546 3,157,96620 
336,473 -125,924 
45,458 249,041 
7,143 
75,556 
0 19,162,74121 
13 19,162,74121 
513,303 604,500 630,000 649,400 
523,570 568,937 624,091 682,100 
147,000 
44,791 
5,920,070 
5,905,641 
- 20,458,59822 
87,234 20,443,623" 
472,167 609,000 798,200 753,010 
483,082 579,537 712,410 807,226 
- 4,000,000 
- 3,001,393 
-2,900 
3,911 
10,924 
20,922 
580 
9,000 
8,997 
7,158,862" 
7,088,9392" 
3,800,000 8,800,000 16,600,000 
2,548,242 3,595,244 9,134,870 
960 
11,000 
11,004 
-1,352 
209 
17,000 
16,988 
212,048 
212,048 
8,139,406" 
8,139,406" 
250,508 
250,495 
25-12

TABLE 25-A (CONT'D) 
HUNTINGTON WEST VIRGINIA DISTRICT 
COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY 80 FY 81 FY 82 FY 83 Sept.30, 1983 
21. Muskingum River 
Dams and Lakes, 
OH 
22. Newark,OH 
(Previous project) 
(Existing project) 
23. North Branch of 
Kokosing River 
Lake, OH 
24. North Fork of Pound 
River Lake, 
Ohio River Basin, 
VA 
25. Ohio River Basin 
26. Paint Creek Lake, 
Ohio River Basin, 
OH 
27. Paintsville Lake, 
KY 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
Dam Safety 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
. New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
5,384 
10,639 8,413 
3,263,068 3,321,000 
3,024,326 3,245,321 
2,200,000 3,730,000 
2,204,626 3,611,151 
-2,879 
1,501 
41,247,81527 
41,247,81527 
4,459,300 3,750,000 44,347,011 
4,613,985 3,950,351 44,347,011 
3,720,000 1,425,000 15,356,94528 
4,182,532 1,144,622 14,706,44428 
- 1,430,000 2,950,000 4,389,000 
- 1,293,342 2,240,704 3,534,046 
9,516 
19,475 
14,000 
14,000 
16,000 
15,997 
23,000 
23,001 
845,916 
845,916 
658,765 
658,763 
381,700 2,820,000 760,000 291,352 5,040,727 
320,167 2,712,807 785,454 272,524 4,870,996 
49,000 
17,470 
-3,823 
27,707 
60,823 119,500 131,000 126,000 
62,770 105,526 144,677 109,505 
~- 
295,189 
344,094 
6,266,18629 
6,266,18629 
1,088,017 
1,067,592 
- - - 6,186,90180 
- - - 6,186,90150 
343,000 331,200 199,000 4,073,35951 
335,337 329,040 206,535 4,067,31131 
355,86132 
355,86132 
9,153 
20,889 -5,939 6,891 
-15,591 26,969,962" 
15,182 26,969,9623 
353,184 455,000 439,000 496,700 3,342,956"' 
365,410 432,816 433,330 457,113 3,258,651' 
7,298,000 4,850,000 
7,655,776 5,341,654 
4,080,000 6,285,000 
3,401,394 7,019,206 
143,000 314,000 420,500 
139,639 314,166 416,231 
52,271,788 
52,144,289 
877,500 
870,036 
25-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 25-A (CONT'D) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY 80 FY 81 FY 82 FY 83 Sept.30,1988 
28. R.D. Bailey Lake, 
WV 
29. Roseville, OH 
30. Summersville Lake, 
Ohio River Basin, 
WV 
31. Sutton Lake, 
Ohio River Basin, 
WV 
32. Tom Jenkins Dam, 
OH 
33. Yatesville Lake, 
KY 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
4,871,000 2,700,000 6,000,000 5,800,000 191,122,233' 
5,101,980 2,816,128 5,793,813 6,017,764 190,573,216u 
372,131 594,000 642,000 
359,095 564,155 643,987 
9,560 
9,560 
-30,000 
42,441 
10,000 
10,000 
124,585 
6,000 
5,998 
42,879 
81,223 
735,000 2,931,814' 
759,759 2,912,530" 
5,000 
4,999 
910,785 
910,785 
111,968 
111,965 
- 48,378,732u 
11,682 48,350,422 " 
545,409 951,000 1,789,920 1,940,000 10,304,9140 
580,337 852,417 1,667,124 2,103,955 10,225,311' 
- - - - 38,839,961" 
- - - - 38,839,961'* 
2,514,929 870,000 969,920 1,377,700 13,635,487" 
2,532,998 830,473 921,281 1,272,293 13,400,115" 
- - - - 2,116,503" 
- - - - 2,116,503" 
172,506 295,200 231,000 
178,076 184,738 293,149 
243,000 
243,648 
2,773,475 
2,761,217 
50,000 800,000 4,000,000 4,000,000 20,044,500 
100,015 603,357 481,415 1,401,135 13,667,083 
25-14

TABLE 25-B 
HUNTINGTON WEST VIRGINIA DISTRICT 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Proect and Work Authorized Documents 
2. Aug. 30,1935 
5. Oct. 23, 1962 
6. Oct. 23, 1962 
7. Jun. 28, 1938 
Dec. 22,1944 
8. Jun. 28, 1938 
Dec. 22,1944 
9. Oct. 23, 1962 
10. Jun. 28, 1938 
11. Jun. 28, 1938 
Dec. 22,1944 
12. Jun. 28, 1938 
Dec. 22,1944 
13. Jun. 28, 1938 
Dec. 22,1944 
14. Jun. 28, 1938 
Dec. 22,1944 
KANAWHA RIVER LOCKS AND DAMS, WV 
Construction of three locks and dam on the Kanawha River and 
one on the Ohio River. 
ALUM CREEK LAKE, OH 
Construction of Flood Control Reservoir. 
BEECH FORK LAKE, WV 
Construction of Flood Control Reservoir. 
BLUESTONE LAKE, OHIO RIVER BASIN, WV 
Construction of Flood Control Reservoir. 
Added Recreation 
Deleted Power 
BURNSVILLE LAKE, OHIO RIVER BASIN,WV 
Construction of Flood Control Reservoir. 
Added recreation 
CHILULICOTHE, OH 
Construction of Levees and Pump Stations. 
DEER CREEK LAKE, OHIO RIVER BASIN, OH 
Construction of Flood Control Reservoir. 
DELAWARE LAKE, OHIO RIVER BASIN, OH 
Construction of Flood Control Reservoir. 
Added Recreation 
DEWEY LAKE, OHIO RIVER BASIN, OH 
Construction of Flood Control Reservoir. 
Added Recreation 
DILLON LAKE, OHIO RIVER BASIN, OH 
Construction of Flood Control Reservoir. 
Added Recreation 
EAST LYNN LAKE, OHIO RIVER BASIN, WV 
Construction of Flood Control Reservoir. 
Added Recreation 
H. Doc. 31, 73rd Cong., 
1st Sess. 
H. Doc. 587, 87th Cong., 
2nd Sess. 
H. Doc. 520, 87th Cong., 
2nd Sess. 
H. Doc. 91, 74th Cong., 
2nd Sess. 
P.L. 534, 78th Cong., 
2nd Sess. 
Flood Control Comm. 
Doc. 1, 75th Cong., 
lst Sess. 
P.L. 534 78th Cong., 
2nd. Sess. 
H. Doc. 587, 8th Cong., 
2nd Sess. 
Flood Control Comm. 
Doc. 1, 75th Cong., 
1st Sess. 
Flood Control Comm. 
Doc. 1, 75th Cong., 
1st Sess. 
P.L. 534, 78th Cong., 
2nd Sess. 
Flood Control Comm. 
Doc. 1,75th Cong. 
1st Sess. 
P.L. 534, 78th Cong., 
2nd Sess. 
Flood Control Comm. 
Doc. 1, 75th Cong., 
1st Sess. 
P.L. 534, 78th Cong., 
2nd Sess. 
Flood Control Comm. 
Doc. 1, 75th Cong., 
1st Sess. 
P.L. 534, 78th Cong., 
2nd Sess. 
25-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY, 1983 
TABLE 25-B (CONT'D) AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
15. Jun. 28, 1938 
Dec. 22,1944 
16. Jul. 14, 1960 
17. Jun. 28, 1938 
Dec. 22,1944 
18. Oct. 1,1980 
19. Oct. 27, 1965 
20. Jun. 28, 1938 
21. Feb. 20, 1934 
Jun. 28,1938 
Aug. 11, 1939 
22. Jun. 28, 1938 
Aug. 13, 1968 
23. Oct. 23, 1962 
24. Jul. 14,1960 
FISHTRAP LAKE, OHIO RIVER BASIN, KY 
Construction of Flood Control Reservoir. 
Added Recreation 
GRAYSON LAKE, KY 
Construction of Flood Control Reservoir. 
JOHN W. FLANNAGAN DAM AND RESERVOIR, 
OHIO RIVER BASIN, VA 
Construction of Flood Control Reservoir. 
Added Recreation. 
TUG AND LEVISA FORKS OF THE BIG 
SANDY RIVER, AND CUMBERLAND RIVER, KY, WV 
Construction of such Flood Control Measures as Deemed 
Necessary and Advisable. 
MARTIN, KY 
Construction of Channel Improvement Project. 
MASSILLON, OH 
Construction of Channel Improvement Project. 
MUSKINGUM RIVER LAKES, OH 
Construction of 14 Flood Control Reservoirs. 
Reimbursement to the Muskingum Conservancy District 
a sum not to exceed actual expenditures for project construction. 
Operations and Maintenance assigned to the Corps of Engineers 
NEWARK, OHIO 
Construction of Channel Improvement Project. 
Modification to Existing Project and Additional Channel 
Improvement and Drainage Facilities. 
NORTH BRANCH OF KOKOSING RIVER LAKE, OH 
Construction of Flood Control Reservoir. 
NORTH FORK OF POUND RIVER LAKE, VA 
Construction of Flood Control Reservoir 
Flood Control Comm. 
Doc. 1, 75th Cong., 
1st Sess. 
P.L. 534, 78th Cong., 
2nd Sess. 
H. Doc. 440, 86th Cong., 
2nd Sess. 
Flood Control Comm. 
Doc. 1, 75th Cong., 
1st Sess. 
P.L. 534, 78th Cong., 
2nd Sess. 
Sect. 202, P.L. 367, 
96th Cong., 2nd Sess. 
H. Doc. 246, 89th Cong., 
1st Sess. 
Flood Control Comm. 
Doc. 1, 75th Cong., 
1st Sess. 
Public Works Admin. 
Flood Control Comm. 
Doc. 1, 75th Cong., 
1st Sess. 
P.L. 396, 76th Cong., 
1st Sess. 
Flood Control Comm. 
Doc. 1, 75th Cong., 
1st Sess. 
H. Doc. 337, 90th Cong., 
2nd Session 
H. Doc. 220, 87th Cong., 
2nd Sess. 
H. Doc. 645, 86th Cong., 
2nd Sess. 
25-16

TABLE 25-B (CONT'D) 
HUNTINGTON WEST VIRGINIA DISTRICT 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act 
26. Jun. 28,1938 
Dec. 22,1944 
27. Oct. 27, 1965 
28. Oct. 23, 1962 
29. Jun. 28, 1938 
Dec. 22,1944 
30. Jun. 28, 1938 
31. Jun. 28, 1938 
Dec. 22,1944 
32. Dec. 22,1944 
33. Oct. 27,1965 
34. Jun. 22, 1936 
. Project and Work Authorized 
PAINT CREEK LAKE, OHIO RIVER BASIN, OH 
Construction of Flood Control Reservoir. 
Added Recreation 
PAINTSVILLE LAKE, KY 
Construction of Flood Control Reservoir. 
R.D. BAILEY LAKE, WV 
Construction of Flood Control Reservoir. 
ROSEVILLE, OH 
Construction of Channel Improvement Project. 
Added Recreation 
SUMMERSVILLE LAKE, OHIO RIVER BASIN, WV 
Construction of Flood Control Reservoir 
SUTTON LAKE, OHIO RIVER BASIN, WV 
Construction of Flood Control Reservoir. 
Added Recreation 
TOM JENKINS DAM, OHIO RIVER BASIN, OH 
Construction of Flood Control Reservoir. 
YATESVILLE LAKE, KY 
Construction of Flood Control Reservoir. 
INSPECTIONS OF COMPLETED FLOOD CONTROL 
PROJECTS. 
Inspection of Local maintenance of Federally 
Constructed Local Protection Projects. 
Documents 
Flood Control Comm. 
Doc. 1, 75th Cong., 
1st Sess. 
P.L. 534, 78th Cong., 
2ndSess. 
H. Doc. 246, 89th Cong., 
1st Sess. 
H. Doc. 569, 87th Cong., 
2nd Sess. 
Flood Control Comm. 
Doc. 1, 75th Cong., 
1st Sess. 
P.L. 534, 78th Cong., 
2nd Sess. 
Flood Control Comm. 
Doc. 1, 75th Cong., 
1st Sess. 
Flood Control Comm. 
Doc. 1, 75th Cong., 
1st Sess. 
P.L. 534, 78th Cong., 
2nd Sess. 
H. Doc. 762, 78th Cong., 
2ndSess. 
H. Doc. 246, 89th Cong., 
2nd Sess. 
P.L. 738, 74th Cong., 
1st Sess. 
25-17 
' "

TABLE 25-C 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY, 1988 
OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last 
Full Report Operation Contributed 
See Annual and Funds 
Project Report For Construction Maintenance Expended 
Big Sandy River 
WV and KY including 
Levisa and Tug Forks2 1952 1,586,236 1,569,8111 131,473 
Elk River, WV8 19083 30,259 
Gauley River, WV' 1908 14,761 
Guyandotte River, WVb 1915 27,500 
Little Kanawha River, WVe 1960 470,586 1,028,854 
Muskingum River, OH7 1955 301,912 6,171,897 6,041 
New River, WA and VA' 1899 109,691 
Scioto River at Portsmouth, OH6 1953 10,951 16,593 
1ln addition, $140,068 expended from funds transferred 
from Department of Commerce, under accelerated public 
works program, for repairs of eroded bank at lock 3 on Big 
Sandy River, at Louisa, KY. 
2Operation and Maintenance suspended June 30,1952. 
3Work closed September 1902. Property transferred to 
Kanawha River improvements. 
'Work closed September 1902. Abandonment recommended 
in H. Doc. 467, 69th Congress. 
5Work suspended. 
6Operation and maintenance suspended June 30,1951. 
7Collections from license non-Federal hydroelectric 
utilities for use of dams on Muskingum River for fiscal years 
1923-1953 were $79,154. 
8Private Law 954, August 31, 1954, authorized Secretary 
of Treasury to pay Portsmouth sand and Gravel Co. $75,000 
in full settlement of claims against Government for damages 
resulting from change in Scioto River Channel. 
25-18

HUNTINGTON WEST VIRGINIA DISTRICT 
TABLE 25-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last 
Full Report Operation Contributed 
See Annual and Funds 
Project Report For Construction Maintenance Expended 
Completed Local Protection Projects 
Ashland, KY 1954 3,718,839 - - 
Athens, OH 1979 5,313,700 - - 
Cattletsburg, KY 1963 3,854,361 - - 
Ceredo-Kenova, WV 1955 2,753,551 - - 
East Rainelle, WV 1962 614,598 - - 
Galax, VA 1953 480,536 - - 
Huntington, WV 1956 7,172,840 - - 
Ironton, OH 1952 2,604,646 - - 
Maysville, KY 1959 6,493,747 - - 
Parkersburg, WV 1955 6,652,827 - - 
Pt. Pleasant, WV 1955 6,652,827 - - 
Portsmouth-New Boston, OH 1956 9,806,424 - - 
Princeton, WV 1962 808,750 - - 
Russell, KY. 1953 237,193 - - 
Williamson, WV 1964 1,056,166 - - 
Inactive Local Protection Projects 
Augusta, KY - 11,577 
Burlington, OH - - 
Chesapeake, OH - - - - 
Coal Grove, OH - 3,389 - - 
Coal River, WV 1979 472,229 - - 
Dover, KY - - - - 
Fullerton, KY - - - - 
Greenup, KY - 4,962 - - 
Lower Guyandotte River Basin, WV - 17,721 - - 
Miller, OH - - - - 
Normal, KY - - - - 
Proctorville, OH - - - - 
Ravenswood, WV - - - - 
South Point, OH - - - - 
South Portsmouth, KY - - - - 
Vanceburg, KY - - - - 
Inactive Reservoirs and Lakes 
Haysi, VA - 2,656 - - 
Leading Creek, WV 1974 272,880 - - 
Panther Creek, WV 1976 22,879 - - 
Salt Creek, OH 1975 1,089,943 - - 
Utica, OH 1975 757,550 - - 
West Fork, WV 1974 663,192 - - 
Deferred Reservoir and Lakes 
Birch, WV -... 
Logan, OH -... 
Moores Ferry, WV -... 
Active Authorized Projects with no current year expenditures. 
Kehoe Kake, KY 1981 1,272,740 
Oceana, WV. 1981 611,000 
25-19

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY, 1983 
TABLE 25-G DEAUTHORIZED PROJECTS 
All projects listed in this table have been deauthorized in accordance with Section 12 of the Water Resources Development 
Act of 1974, P.L. 251, 93rd Congress. 
For Last 
Full Report Federal Contributed 
See Annual Funds Funds 
Report For Date Expended Expended 
Local Protection 
Projects 
Aberdeen, OH 
Athalia, OH 
Belpre, OH 
Brooklyn, WV 
Buena Vista, OH 
Chambersburg, OH 
Cheshire, OH 
Chilo, OH 
Clifton, WV 
Columbus, OH 
Friendly, WV 
Gallipolis, OH 
Hanging Rock, OH 
Hartford, WV 
Henderson, WV 
Higginsport, OH 
Hockingport, OH 
Letart, WV 
Letart Falls, OH 
Manchester, OH 
Mapleshade, OH 
Marietta, OH 
Mason, WV 
Middleport, OH 
Millwood, WV 
New Martinsville, WV 
New Matamoras, OH 
Newport, OH 
Pomeroy, OH 
Portland, OH 
Racine, OH 
Ripley, OH 
Riverview, WV 
St. Mary's, WV 
Sardis, OH 
Sciotoville, OH 
Sistersville, OH 
Syracuse, OH 
Waverley, WV 
Williamstown, WV 
Zanesville, OH 
Reservoirs and Lakes 
Big Bend, WV 
Big Darby, OH 
Frazeysburg, OH 
Millersburg, OH 
Mill Creek, OH 
Mud River, WV 
Poca, WV 
Rocy Fork, OH 
White Oak Creek, OH 
1969 
1981 
1950 
May 1981 
Aug 1977 
Nov 1977 
Nov 1979 
Aug 1977 
Aug 1977 
Nov 1977 
Aug 1977 
Aug 1977 
Aug 1977 
Aug 1977 
Aug 1977 
Aug 1977 
Aug 1977 
Aug 1977 
Oct 1978 
Aug 1977 
Aug 1977 
Aug 1977 
May 1981 
Oct 1978 
Nov 1981 
Aug 1977 
May 1981 
Aug 1977 
Nov 1979 
Aug 1977 
Aug 1977 
Aug 1977 
Aug 1977 
Aug 1977 
Oct 1978 
Aug 1977 
Aug 1977 
Aug 1977 
Aug 1977 
Aug 1977 
Aug 1977 
Aug 1977 
Nov 1979 
May 1981 
Aug 1977 
Nov 1979 
May 1981 
May 1981 
Nov 1981 
Nov 1979 
May 1981 
Aug 1977 
Nov 1981 
1,334 
- 
11,237 - 
9,783 
7,523 
- 
3,349,568 
5,000 
1,602,702 
91,321 
25-20

HUNTINGTON WEST VIRGINIA DISTRICT 
TABLE 25-H INSPECTION OF FLOOD CONTROL PROJECTS - See Section 34 of Text 
Flood Control Works Inspected Datgs of Inspection 
Ashland, KY 
Athens, OH 
Bramwell, WV 
Cairo, WV 
Canton (Nimishillen), OH 
Cattletsburg, KY 
Ceredo-Kenova, WV 
East Rainelle, WV 
Fishing Creek, Pine Grove, WV 
Fourpole Creek, WV 
Galax, VA 
Grahn, KY 
Griffithsville-Yawkey, WV 
Hitchins, KY 
Huntington, WV 
Inez, KY 
Ironton, OH 
Jacksonsburg, Fishing Creek, WV 
Maysville, KY 
Montcalm, WV 
Newark, OH 
Olive Hill, KY 
Paint Creek at Chillicothe, OH 
Paint Creek at Washington Court House, OH 
Parkersburg, WV 
Pax, WV 
Point Pleasant, WV 
Portsmouth-New Boston, OH 
Prestonsburg, KY 
Princeton, WV 
Richwood and Fenwick, WV 
Right and Left Forks of Beaver Creek, KY 
Ripley, WV 
Roseville, OH 
Russel, KY 
Smithfield, WV 
South Wiliamson, KY 
Utica, OH 
West Union, Middle Island, WV 
Williamson, WV 
Apr 1983 
Sep 1982 
Aug 1983 
Aug 1983 
Nov 1982 
May 1982 Sep 1982 
Apr 1983 Sep 1983 
July 1983 
Aug 1983 
Dec 1979 
Aug 1983 
Oct 1982 
Jan 1982 
Oct 1982 
May 1983 Jun 1983 Aug 1983 
Oct 1982 
Apr 1983 May 1983 
Aug 1983 
Sep 1982 Mar 1983 
Aug 1983 
Dec 1982 Aug 1983 
Oct 1982 
Dec 1982 
Dec 1982 
May 1983 Jun 1983 
Jul 1983 
May 1983 Sep 1983 
Apr 1983 Sep 1983 
Jan 1983 Jul 1983 
Aug 1983 
Jul 1983 
Jan 1983 
Aug 1983 
Dec 1982 Jul 1983 
Apr 1983 Aug 1983 
Aug 1983 
May 1982 
Sep 1983 
Aug 1983 
Aug 1982 May 1983 
25-21 
_

PITTSBURGH, PA DISTRICT* 
This District comprises part of eastern Ohio, western age basin of Ohio River and tributaries above mile 127 
Pennsylvania, southwestern New York, northern West (below Pittsburgh), immediately upstream from New 
Virginia, and northwestern Maryland embraced in drain- Martinsville, W. Va. 
IMPROVEMENTS 
Navigation - Locks and Dams 
1. Allegheny River, PA ............... 
2. Construction of locks and dams, 
Ohio River ....................... 
3. Monongahela River, PA and WV ..... 
4. Open-channel work, Ohio River...... 
5. Tygart Lake, WV ............... 
6. Other authorized navigation projects .. 
Flood Control- Local Protection 
7. Allegheny River, Oil City, PA....... 
8. Chartiers Creek, PA ............... 
9. Elkins, WV .................... 
10. Girty's Run, Millvale, PA ........... 
11. Johnstown, PA ................. 
12. Punxsutawney, Ohio River 
Basin, PA ....................... 
13. Root Creek, Bolivar, NY ............ 
Flood Control - Reservoirs 
14. Berlin Lake, Ohio River 
Basin, OH .................... 
15. Conemaugh River Lake, 
Ohio River Basin, PA .............. 
16. Crooked Creek Lake, 
Ohio River Basin, PA .............. 
17. East Branch, Clarion River Lake, 
Ohio River Basin, PA .............. 
18. Kinzua Dam and Allegheny Reservoir, 
Ohio River Basin, PA and NY ........ 
19. Loyalhanna Lake, Ohio River 
Basin, PA ....................... 
20. Mahoning Creek Lake, 
Ohio River Basin, PA .............. 
21. Michael J. Kirwan Dam and 
Reservoir, OH .................... 
22. Mosquito Creek Lake, Ohio 
River Basin, OH ................ 
23. Ohio River Basin (Pittsburgh 
District)..................... 
Page Flood Control (Continued) Page 
....... 26-2 24. Shenango River Lake, Ohio 
River Basin, PA and OH ................... 26-9 
....... 26-2 25. Stonewall Jackson Lake, WV ............... 26-9 
....... 26-2 26. Tionesta Lake, OH 
....... 26-3 River Basin, PA............... ........... 26-10 
....... 26-3 27. Union City Dam, PA ..................... 26-11 
....... 26-3 28. Woodcock Creek Lake, PA ................ 26-11 
29. Youghiogheny River Lake, Ohio Rivqr 
....... 26-3 Basin, PA and MD ..................... 26-12 
....... 26-3 
...... .26-3 30. Inspection of completed flood control 
....... 26-4 projects .................... ........... 26-12 
....... 2266-4-431. Other authorized flood control projects ....... 26-12 
.26-532. Flood control work under special 
.....2..6-5authauothroirzizaattioino n. ....... ..... ....... ......... ....... ..... ...2. 6-. 216-212 
....... 26-5 
....... 26-5 
....... 26-5 
........ 26-6 
....... 26-6 
....... 26-6 
....... 26-7 
....... 26-7 
....... 26-8 
....... 26-8 
....... 26-9 
....... 26-9 
General Investigations 
33. Surveys................. ............. 26-13 
34. Collection and study of basic data ........... 26-13 
35. Research and development ................ 26-13 
Tables 
Table 26-A Cost & Financial Statement .......... 26-14 
Table 26-B Authorizing Legislation ............ 26-18 
Table 26-C Other Authorized Navigation Projects .26-22 
Table 26-D Not Applicable ........................ 
Table 26-E Other Authorized Flood Control 
Projects ............. ........... 26-23 
Table 26-F Not Applicable ........................ 
Table 26-G Deauthorized Projects .............. 26-24 
Table 26-H Allegheny River Statistics ........... 26-25 
Table 26-I Monongahela River Statistics ........ 26-26 
Table 26-J Monongahela River Total Costs ....... 26-27 
Table 26-K Ohio River Basin Local Protection 
Projects .. t.......................26-27 
Table 26-L Ohio River Basin Reservoirs ......... 26-28 
Table 26-M Inspection of Completed Flood Control 
Projects ........................ 26-29 
Table 26-N Flood Control Work Under Special 
Authorization....................26-30 
26-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Navigation - Locks and Dams 
1. ALLEGHENY RIVER, PA 
Location. The Allegheny River is 325 miles long. It rises 
in northern Pennsylvania, flows northwestward into New 
York, thence generally southwestward to Pittsburgh, PA, 
where it joins with Monongahela River to form the Ohio. 
(See Geological Survey Charts for western Pennsylvania 
and southwestern New York.) 
Existing project. The project consists of eight locks and 
dams to afford slack-water navigation for a length of 72 
miles from Pittsburgh, PA to above East Brady, PA. Controlling 
depth through canalized portion is 9 feet at normal 
pool level. Channel width varies from a minimum of 200 feet 
to full width of river at mouth. Existing project is complete, 
the last lock, No. 9, was placed in service in 1938. All locks 
and dams are in fair condition. Navigation channel has been 
widened at certain points and, in general, maintained to 
project depth, thus affording adequate depth for passage of 
commercial tows. 
Local cooperation. Fully complied with. 
Terminal facilities. City of Pittsburgh constructed a 
modern wharf for river freight. There are numerous privately 
maintained terminals and docks, consisting of tipples, 
various types of hoists, chutes, and pipelines for use in 
loading and unloading coal, stone, sand, gravel, petroleum 
products, steel products, and other commodities. 
Transshipment of freight between river and railroads is 
handled at privately owned river-to-rail terminals. Existing 
private terminals are adequate for shipments and receipt in 
Pittsburgh District of type of commerce now in existence. 
Operations during fiscal year. Operation and maintenance, 
general: Locks were operated as required and 
necessary repairs were made to structures to maintain them 
in a serviceable condition. 
2. CONSTRUCTION OF LOCKS AND 
DAMS, OHIO RIVER 
See this heading under Ohio River portion. 
3. MONONGAHELA RIVER, PA AND WV 
Location. Formed by junction of Tygart and West Fork 
Rivers about 1 mile south of Fairmont, WV, and flows 
northerly for 128.7 miles to its junction with Allegheny 
River, forming Ohio River at Pittsburgh, PA (See Geological 
Survey Charts for southwestern Pennsylvania and 
northern West Virginia.) 
Previous project. For details see Annual Report for 1963, 
page 1070. 
Existing project. Provides for improvement of river by 9 
locks and dams to afford slack-water navigation for its 
entire length from Pittsburgh to above Fairmont, WV. 
Original locks and dams 7, 8 and 9 were replaced by new 
locks and dams 7 and 8 in 1925. Increased traffic necessitated 
enlargement and improvement of locks and dams 1 
to 6 between Pittsburgh and Rices Landing, PA, by 
building two parallel chambers and fixed concrete dams 
during 1905 and 1932. Locks and dam 1 were eliminated in 
1938 by raising Emsworth Dam, Ohio River. Reconstruction 
of lock 2 was completed in 1953 to provide two modern 
navigation chambers. The existing locks and dam 2 were 
originally completed in 1907; major modifications were 
made in 1923 and 1924, and in 1926 the upper guard and 
guide walls were extended. Construction of Maxwell locks 
and dam and the reconstruction of dam 4 have allowed for 
removal of obsolete locks and dams 5 and 6. Small and 
antiquated original locks and dams 10 to 15, inclusive, have 
been replaced by three modern structures. Morgantown 
lock and dam, initial step in replacement program, was 
completed in 1950 replacing locks and dams 10 and 11. 
Hildebrand lock and dam, next upstream, was completed in 
1959 replacing locks and dams 12 and 13. Raising crest of 
dam 8 was also completed in 1959 as part of upper river 
improvement and eliminates restricted depth in upper reach 
of pool. Opekiska lock and dam was completed in 1967 
replacing locks and dams 14 and 15. Completion of this link 
in upper river replacement program provides for entire river 
length of minimum channel depth of 9 feet, varying in width 
from a minimum of 250 feet to practically full width at 
mouth. 
Locks and dam 3 showed advanced stages of deterioration 
and, because of its strategic location and its importance 
to industry throughout the Greater Pittsburgh area 
and the nation, emergency remedial work had to be done in 
1977. Major rehabilitation of locks and dam 3 was 
completed on Oct. 27, 1980. 
Local cooperation. None required. 
Terminal facilities. City of Pittsburgh constructed a 
modern wharf for freight. Boat landings are maintained by 
some municipalities along the river. A large number of tipples 
at mines and various types of hoists at manufacturing 
plants and sand and gravel supply companies are maintained 
for private use in loading and unloading coal, coke, 
billets, steel products, sand, gravel, and other commodities. 
These terminals and docks are not available for general 
commerce. A number of docks and pipelines are also 
privately maintained for petroleum and acid products. 
Marine ways are maintained by some of the larger industries. 
There are also several terminals for rail-to-river and 
river-to-rail transfer. Facilities are considered adequate for 
existing commerce. 
Operations during fiscal year. New work: Study for 
replacement of locks and dams for middle and lower reach 
of river is being conducted as part of the continuing study 
of the entire Monongahela River Basin. The Reconnaissance 
Report on the Monongahela River Navigation 
System, Stage I Studies was submitted in Jan. 1981. A 
feasibility study draft report was submitted in Aug. 1983 
with a final report scheduled for submission in Feb. 1984. A 
public meeting is scheduled to be held in October 1984. 
Contract for Additional Armor Protection, Locks and Dam 
3, was awarded in June 1982 and completed in Nov 1982 for 
$81,100. Operation and maintenance, general: Locks were 
operated as required and necessary repairs were made to 
structures maintain them in a serviceable condition. 
26-2

PITTSBURGH, PA., DISTRICT 
4. OPEN-CHANNEL WORK, OHIO 
RIVER 
See this heading under Ohio River portion. 
5. TYGART LAKE, WV 
Location. Tygart Lake is located on the Tygart River in 
Taylor and Barbour Counties, northcentral WV. The lake is 
approximately 26 road miles due east of Clarksburg, WV 
and 30 road miles south of Morgantown. The dam is 
situated 22.7 river miles above the mouth of the Tygart 
River at Fairmont, or 2.25 miles upstream from Grafton, 
WV, and about 78 miles south of Pittsburgh, PA. (See Geological 
Survey Charts for Fairmont, Thornton, and 
Belington, WV.) 
Existing project. A reservoir for low water regulation and 
flood control Dam is concrete gravity type with an 
uncontrolled center spillway flanked by abutment sections 
joining valley sides. Project was authorized by Public 
Works Administration January 11, 1934, and adopted by 
1935 River and Harbor Act. For further project description 
see Annual Report for 1962. Authorized project is complete. 
Reservoir is in operation for low water control in 
Monongahela River and for purpose of flood protection in 
Monongahela and Ohio Valleys. Construction of dam was 
started in 1935 and placed in operation in 1938. Land 
acquired for project consists of 2,662.9 acres in fee, flowage 
easements over 1,216.9 acres and 1,731.9 acres of other 
easements. 
Current estimate for construction of recreation facilities 
at completed project is $826,247.62 of which $413,123.81 
are non-Federal costs. 
Local cooperation. The State of West Virginia has 
assumed responsibility for the development and operation 
of hunting and fishing areas as well as the Tygart Lake 
State Park. Controlled releases for downstream navigation 
and recreation are also coordinated with others to the 
extent feasible. No local cooperation is required at 
completed project; however, future recreational developments 
are subject to certain conditions of non-Federal costsharing 
under Federal Water Project Recreation Act of 
1965. A cost-sharing agreement was executed with the 
West Virginia Department of Recreation in May 1981. 
Operations during fiscal year. New work: Cost-sharing 
contract for Construction of Water Supply, Sewage Collection 
System and Sewage Treatment Plant, Right Bank 
Facilities awarded in Sep 1981 for $517,629.25 was 
completed in Jan 1983. Contract for Construction of Restrooms, 
Day Use Area awarded in Mar 1982 was completed 
in Feb 1983 for $153,428. Operation and maintenance, 
general: Reservoir was operated for benefit of flood control 
and low water regulation, as required, and project 
structures were operated and maintained in a serviceable 
condition throughout the year. Estimated flood control 
benefits achieved by this reservoir for this period were 
$799,000. Total flood control benefits for this reservoir 
through September 30, 1983 are $228,551,000. Activities 
under reservoir management program comprising 
sanitation measures, conservation, land management, and 
operation and maintenance of public-use facilities 
continued. This work was limited in scope as State of West 
Virginia has jurisdiction over recreation in reservoir area. 
6. OTHER AUTHORIZED NAVIGATION 
PROJECTS 
See Table 26-C on other authorized navigation projects. 
Flood Control - Local Protection 
7. ALLEGHENY RIVER, OIL CITY, PA 
Location. Oil City is located in Venango County, PA at 
the junction of Oil Creek and the Allegheny River 
(Allegheny river mile 132.1). (See Geological Survey Chart 
for Oil City, PA.) 
Existing project. To alleviate the long-standing ice jam 
flooding problems in Oil City, a floating ice control 
structure has been located on the Allegheny River about 
one-half mile upstream from the mouth of Oil Creek. It will 
consist of a series of 23 floating steel pontoons (each 20' x 3' 
x 1.25') and 24 steel cylindrical floats connected together by 
2 1/4 inch diameter corrosion resistant steel cables. The 
cables are attached to a junction plate in the center of the 
Allegheny River and four anchors (two on each side) on the 
river banks. During non-winter months, the right bank half 
of the structure is disengaged from its anchor to permit 
navigation. To complete the project, a second ice control 
structure will be built in 1984 on Oil Creek. Preliminary 
plans provide for a single cable strung across the creek, 
using timber floats. 
Estimated first cost for project is $741,000 of which 
$720,000 is Federal cost and $21,000 is non-Federal cost. 
Local cooperation. The City of Oil City is responsible for 
the acquisition of required project land interests and the 
operation and maintenance of the ice control structures. By 
early Sep. 1982, the City had acquired all the necessary 
rights-of-way for the Allegheny River structure. Land 
necessary for construction of floating ice control structure 
on Oil Creek is expected to be available by early Nov 1983. 
Operations during fiscal year. New work: Contract for the 
fabrication of the components (pontoons, floats, cables, 
chains and attachments) of the structure was awarded Aug 
6, 1982 for $154,190 and completed. Contract for 
construction of the anchors, storage pads, and assembly 
and installation of the floating ice control structure was 
awarded Sep 7, 1982 and completed in Feb 1983. Engineering 
and design continued on remaining project features. 
8. CHARTIERS CREEK, PA 
Location. Within Washington and Allegheny Counties, 
southwestern Pennsylvania, a tributary of Ohio River. 
(See Geological Survey Chart for Carnegie, PA) 
Existing project. Provides for channel widening, deepening 
and realignment, construction of a major channel 
cutoff, and relocations in two separate and independent 
reaches. James G. Fulton project in Allegheny County 
26-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
would be about 13.4 miles long and Canonsburg-Houston 
reach in Washington County about 4.7 miles long. Completed 
improvements would contain within banks, all 
floods up to the 1912 maximum of record, but with some 
residual damage, and would greatly reduce flood stages 
and damages resulting from higher floods. James G. 
Fulton Flood Control Project-Construction of Unit 1 was 
started in July 1968, completed in September 1970, and 
turned over to local interests for operation and maintenance 
on June 25, 1971. Construction of Unit 2 was 
started in April 1970, completed in April 1973, and turned 
over to local interests on November 22,1974. Construction 
of Unit 3 was started in July 1971 and was completed in 
December 1974. Construction of Unit 5 was started in 
June 1972 and was Completed in December 1973. Construction 
of Unit 4 channel improvement was started in 
July 1978 and was completed in June 1981. A contract for 
Environmental Improvement, Unit 4, James G. Fulton, 
was awarded in Sep 1981 and completed in Dec 1981. 
Canonsburg-Houston Reach-Construction of Unit 1 was 
started in December of 1968, completed in March 1970, 
and turned over to local interests for operation and 
maintenance on August 10,1970. Construction of Unit 2A 
was started January 17, 1976, completed December 16, 
1976, and turned over to local interests on June 9, 1977. 
Construction plans and specifications for Unit 2B, the remai 
ing unit of the reach, are 99% complete. Remaining 
work on project has been delayed due to the inability of 
local cooperating agency to provide the necessary rightsof-
way. Project was authorized by Flood Control Act of 
1965. 
Estimated cost for new work (1983) is $41,600,000 of 
which $32,500,000 is Federal cost and $9,100,000 non- 
Federal cost. 
Local cooperation. Requirements are described in full on 
page 26-3 of FY 1981 Annual Report. Local cooperating 
agency (Washington County) has been unable to provide 
the necessary rights-of-way for the remaining Unit 2B. 
Direct non-Federal contributions have been made in the 
amount of $4,225,188. 
Operations during fiscal year. Regular inspections were 
made at completed units. Estimated flood control benefits 
achieved by the Chartiers Creek project through 
September 30, 1983, totaled $12,163,000. 
9. ELKINS, WV 
Location. On Tygart River in north-central Randolph 
County, WV, about 155 miles south of Pittsburgh, PA. It 
is at downstream end of a long, broad reach of upper 
Tygart Valley, about 75 miles above mouth of river. (See 
Geological Survey Chart for Elkins, WV) 
Existing project. Provides flood protection by diverting 
flood discharges from upstream arm of loop of natural 
river channel into an artificial cutoff channel, thereby 
bypassing City of Elkins. Improvement is designed to 
accommodate discharges equivalent to maximum flood of 
reasonable expectancy. Project construction was started 
May 1946 and completed May 1949. Completed works, 
except that portion of channel maintained by Federal 
Government, has been operated and maintained by City of 
Elkins since March 31, 1949. Land acquired for project 
consists of 32.04 acres in fee and 526.01 acres in 
easements. Project was authorized by 1938 Flood Control 
Act. For further project description see Annual Report for 
1962, page 1222. Federal cost of completed project was 
$1,772,627; estimated non-Federal cost for lands, 
easements, and rights-of-way was $40,000. 
Local cooperation. Fully complied with. 
Operations during fiscal year. Operation and maintenance, 
general: Routine inspections were made. Cumulative 
total flood damages prevented to September 30, 1983, 
$4,156,000. 
10. GIRTY'S RUN, MILLVALE, PA 
Location. Girtys Run rises in the Fox Ridge area of the 
southern portion of McCandless Township, Allegheny 
County, and flows generally southeast through Ross and 
Shaler Townships and the Borough of Millvale to enter the 
Allegheny River from the right bank at River Mile 3.6 
above the "Point" at Pittsburgh. (See U.S Geological 
Survey chart for Pittsburgh, PA, East.) 
Existing project. To decrease flooding conditions in the 
Borough of Millvale area, project consists of lowering the 
existing channel bottom within the limits of the existing 
walls. The lowering was accomplished by a 16-foot average 
bottom width of cut in rock or overburden averaging 
4 feet in depth in the lower 2,750 feet of the project and 2 
1/2 feet in depth for the remaining portion. Existing 
masonry walls of the channel were replaced and/or 
stabilized where required. Construction of project 
complete on June 26, 1980. Project was authorized for 
construction by the Chief of Engineers under authority of 
Section 205 of the 1948 Flood Control Act as amended. 
Federal cost is $2,000,000; estimated non-Federal cost 
of lands, easements and rights-of-way, utility 
adjustments, and amount in excess of $2 million 
limitation established by Section 205 of the 1948 Flood 
Control Act as amended, is estimated at $1,361,722. 
Local cooperation. Requirements are described in full 
on page 26-4 of FY 1981 Annual Report. The Commonwealth 
of Pennsylvania and the County of Allegheny, 
Pennsylvania, have each agreed to provide to the 
Borough of Millvale 50% of all estimated non-Federal 
costs, currently estimated at $1,361,722. To date, nonfederal 
contributions have totaled $701,722; a formal 
request for the additional $660,000 has been presented to 
the Borough of Millvale. 
Operations during fiscal year. Work on the project 
started July 11, 1976 with a scheduled completion date of 
November 22, 1977; however, by that date the contract 
work had progressed to only about 50% of completion 
and it was found necessary to terminate that contract for 
default due to unsatisfactory and untimely performance. 
Subsequently, a new contract for completion of the remaining 
work was made on May 4, 1978 and work was 
completed July 26, 1980 at a cost of $2,091,522.95. 
Formal hearings were held on July 26, 1978 before the 
Division Engineer and July 8-15, 1980, inclusive, before 
the Engineer Board of Contract Appeals regarding the 
26-4

PITTSBURGH, PA., DISTRICT 
appeal of the defaulted contractor. In July 1982, an 
agreement was reached with the surety and default contractor 
regarding the liability resulting from the 
termination. Modification effecting settlement and release 
stipulation was finalized, resulting in payment to 
Government of $464,340.66. 
11. JOHNSTOWN, PA 
Location. Project is located in southwestern Cambria 
County, PA, about 58 miles east of Pittsburgh, PA. It is in 
a deep and comparatively narrow valley at junction of 
Stoney Creek and Little Conemaugh River, which unite to 
form Conemaugh River. (See Geological Survey Chart for 
Johnstown, PA.) 
Existing project. Provides for increased channel capacity 
by enlarging and realigning channels and protecting banks 
with concrete pavement. Improvement designed to accommodate 
discharges equivalent to those of March 1936 flood, 
maximum natural flow of record, minimum of overbank 
flow and to practically eliminate damages therefrom. 
Project construction began in August 1938 and was 
completed November 1943. Footer protection for Unit 4 
was completed in November 1949. Land acquired for project 
consists of easements over 192 acres. Project was 
authorized by Flood Control Acts of 1936 and 1937. For 
further project description see Annual Report for 1962, 
page 1215. 
Local cooperation. Section 2, Flood Control Act of June 
28, 1938, applies. 
Operations during fiscal year. Operation and maintenance, 
general: Contract awarded Sep 14, 1983 for 
$211,410.93 for Removal of Bar Deposits, Conemaugh and 
Stonycreek Rivers, and Clearing, Stonycreek River. Work is 
scheduled to be completed by Jan 15, 1984. Operation 
activities and routine investigations and inspections were 
made. Cumulative flood damages prevented by project were 
estimated to be $414,792,000 to end of September 1983. 
12. PUNXSUTAWNEY, OHIO RIVER 
BASIN, PA 
Location. Borough of Punxsutawney is on Mahoning 
Creek in Jefferson County, PA, about 85 miles northeast 
of Pittsburgh, PA. It is on a comparatively wide, alluvial 
flood plain about 52 miles above mouth of stream and 30 
miles above Mahoning Creek flood control dam. (See 
Geological Survey Charts for Punxsutawney and 
Smicksburg, PA.) 
Existing project. Provides flood protection by channel 
enlargement, dikes, and walls. Improvement is designed to 
accommodate discharges 20% greater than that of maximum 
flood of record. Construction was accomplished by 
construction of four units. Construction started May 1946 
and was completed June 1950. Land acquired for project 
consists of perpetual easements over 72.6 acres. 
Completed works, except that portion of channel maintained 
by the Federal Government, have been operated 
and maintained by Borough of Punxsutawney since July 
31, 1950. Project was authorized by 1938 Flood Control 
Act. For further project description see Annual Report for 
1962, page 1209. 
Local cooperation. Fully complied with. 
Operations during fiscal year. Operation and maintenance, 
general: Contract awarded Aug 12, 1983 for 
$229,450 for Removal of Bar Deposits in Channel and 
Clearing and is scheduled for completion Dec 13, 1983. 
Operation activities and routine investigations and 
inspections were made. Cumulative flood damages 
prevented by project were estimated to be $28,328,000 to 
end of September 1983. 
13. ROOT CREEK, BOLIVAR, NY 
Location. The problem area is located in the 
southwestern portion of the State of New York in the 
Village of Bolivar, Allegany County, about 17 road miles 
east of Olean, New York. (See Geological Survey Chart of 
Olean, NY.) 
Existing project. Flooding of the Village of Bolivar from 
Root Creek causes estimated annual damages in the 
amount of about $53,000. The project will consist of 3,230 
feet of Root Creek channel modification, including moderate 
widening, deepening and slope protection. The plan 
will provide Bolivar with protection against a flood having 
a frequency of once in 100 years. Total first cost of the plan 
is estimated to be $1,250,000. Project was authorized for 
construction by the Chief of Engineers under authority of 
Section 205 of the 1948 Flood Control Act as amended. 
Final EIS filed with CEQ on March 11, 1976. The Detailed 
Project Report was approved April 29, 1976. Plans and 
specifications are complete. Assurances were executed by 
the State of New York Department of Environmental 
Conservation and accepted by the Department of the 
Army on March 23, 1977. All interests in real estate 
required for project construction are available. Utility 
adjustments were completed by NYDEC. Land acquired 
for project consists of 7.809 acres. 
Local cooperation. Requirements are described in full on 
page 26-5 of FY 1981 Annual Report. 
Operations during fiscal year. Contract for 
construction of Bolivar Flood Protection Project was 
awarded Sep 17, 1979 for $945,077.71. Construction 
progressed to approximately 98% completion at end of 
fiscal year. 
Flood Control - Reservoirs 
14. BERLIN LAKE, OHIO RIVER 
BASIN, OH 
Location. Dam is on Mahoning River about 73 miles 
above its confluence with Shenango River. It is about 10 
miles above existing Milton Reservoir Dam and 35 miles 
upstream from Warren, Ohio. Reservoir is in Portage, 
Mahoning and Stark Counties, OH. (See Geological 
Survey charts for Warren, Ravenna. and Alliance, OH.) 
26-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Existing project. A reservoir for flood control and water 
supply. Dam consists of a partially controlled, concrete 
gravity, center spillway flanked by rolled-earthfill 
abutment sections joining valley sides. Authorized project 
is complete and in operation for flood control and low 
water regulation purposes in industrialized Mahoning 
Valley below. Construction of dam was started January 
1942 and completed June 1943. Present project lands 
consists of 6,885.3 acres in fee and 1,098.7 acres in 
easements. For further project description, see Annual 
Report for 1962, page 1233. 
Current estimate for construction of recreational and 
sanitary facilities at completed project is $2,977,700 of 
which $100,000 were non-Federal costs. 
Local cooperation. None required at completed project; 
however, future recreational developments are subject to 
certain conditions of non-Federal cost-sharing under 
Federal Water Project Recreation Act of 1965. 
Operations during fiscal year. Operation and 
maintenance, general: Contract for preparation of Master 
Plan Design Memorandum No. 1 was 100% complete at 
end of fiscal year and submitted to division for approval. 
Reservoir was operated as required and necessary repairs 
were made to structures and appurtenances. Estimated 
flood control benefits achieved by this reservoir for this 
period were $4,318,000; total benefits through September 
30, 1983, $195,703,000. Activities under reservoir 
management program comprising sanitation measures, 
conservation, land management, and operation and 
maintenance'of public-use facilities continued. 
15. CONEMAUGH RIVER LAKE, 
OHIO RIVER BASIN, PA 
Location. Dam is on Conemaugh River in Indiana and 
Westmoreland Counties, PA, 7.5 miles above junction of 
Conemaugh River and Loyalhanna Creek, which form the 
head of the Kiskiminetas River. It is about 2 miles 
northeast of Tunnelton, PA, and about 42 miles east of 
Pittsburgh, PA. Reservoir is in Westmoreland and 
Indiana Counties, PA. (See Geological Survey Charts for 
Latrobe, New Florence, and Elders Ridge, PA.) 
Existing Project. A flood control reservoir dam of 
concrete gravity type with a gate-controlled center spillway 
flanked by abutment sections joining valley sides and 
an earth embankment ending in right abutment. 
Authorized project is complete. Reservoir system 
designed for protection of Pittsburgh and reduction of 
flood heights in upper Ohio Valley, generally. Land 
acquired for dam, reservoir and railroad relocation consists 
of 7,635.1 acres in fee and 518.5 acres in easements. 
Project authorized by Flood Control Acts of 1936 and 
1938. For further project description see Annual Report 
for 1962, page 1217. 
Local cooperation. None required by law. 
Operations during fiscal year. New work: Contract for 
construction of Restrooms, Damsite Area, awarded in Apr 
1982 was completed in Feb 1983 for $211,682. Operation 
and maintenance, general: Reservoir was operated for 
benefit of flood control as required, and necessary repairs 
were made to structures and appurtenances. Estimated 
flood control benefits achieved by this reservoir for this 
fiscal year were $103,000; total flood control benefits 
through September 30, 1983 are $524,431,000. Activities 
under reservoir management program comprising 
sanitation measures, conservation, land management and 
operation and maintenance of public-use facilities were 
continued. 
16. CROOKED CREEK LAKE, OHIO 
RIVER BASIN, PA 
Location. Dam is on Crooked Creek 6.7 miles above 
junction of creek with Allegheny River near Ford City, 
PA, and about 32 miles northeast of Pittsburgh, PA. (See 
Geological Survey Charts for Freeport and Elders Ridge, 
PA.) 
Existing project. A flood control reservoir dam of 
earthfill type with separate uncontrolled saddle spillway 
and tunnel outlet works. Authorized project is complete. 
Reservoir is in operation as a unit of a coordinated reservoir 
system designed for protection of Pittsburgh and 
reduction of flood heights in upper Ohio Valley, generally. 
Construction of dam was started in March 1938 and completed 
October 1940. Present project lands consist of 
2,563.6 acres in fee and 99.98 acres in easements. Project 
was authorized by Flood Control Acts of 1936 and 1938. 
For further project description see Annual Report for 
1962, page 1213. 
Current estimated cost of sanitary facilities, required to 
upgrade area and comply with state sanitary codes, is 
$3,310,000. 
Local cooperation. None required by law. 
Operations during fiscal year. Operation and 
maintenance, general: Master Plan Design Memorandum 
No. 2 was initiated in FY 82 and progressed to 45% 
completion. Reservoir was operated for benefit of flood 
control, as required, and necessary repairs were made to 
structures and appurtenances. Estimated flood control 
benefits achieved by this reservoir for this period were 
$79,000; total benefits through September 30, 1983 are 
$118,595,000. Activities under reservoir management 
program comprising sanitation measures, conservation, 
land management, and operation and maintenance of 
certain public-use facilities continued. By letter dated Aug 
14, 1981, the Commonwealth of PA relinquished their 
lease having jurisdiction over recreation in reservoir area 
effective Oct 1, 1981. 
17. EAST BRANCH, CLARION RIVER 
LAKE, OHIO RIVER BASIN, PA 
Location. Dam is in Elk County, PA, on East Branch of 
Clarion River above Middle Fork, 7.3 miles above junction 
of East and West branches of Clarion River at 
Johnsonburg, PA, and about 105 miles northeast of 
Pittsburgh, PA. Reservoir is in Elk County, PA. (See 
Geological Survey Chart for Mount Jewett, PA.) 
26-6

PITTSBURGH, PA., DISTRICT 
Existing project. A reservoir for flood control and lowwater 
regulation. Dam is rolled-earthfill type with gatecontrolled 
concrete tunnel under right abutment and a 
paved uncontrolled spillway on left abutment slope. 
Authorized project is complete. Reservoir is in operation for 
low-water regulation purposes in Clarion River Valley below 
and for flood control as a unit of a coordinated reservoir 
system for protection of Pittsburgh and upper Ohio Valley, 
generally. Construction of dam was started in June 1947 
and completed in July 1952. Present project lands consist of 
287.2 acres in fee and 1,296.7 acres in easements. Project 
was selected for construction under general authorization 
for Ohio River Basin in Flood Control Acts of 1938 and 
1944. For further project description see Annual Report for 
1962, page 1206. 
Estimated cost of construction of additional sanitary 
facilities, required to upgrade area and comply with state 
sanitary codes, is $235,000; current total estimate of 
recreation facilities at completed project, $376,800. 
Local Cooperation. None required by law. 
Operations during fiscal year. Operations and 
maintenance, general: Reservoir was operated for flood 
control and low-water regulation, as required; and necessary 
repairs were made to structures and appurtenances. 
Estimated flood control benefits achieved by this reservoir 
during this fiscal year were $58,000, total benefits through 
September 30, 1983, $30,012,000. Some reservoir 
management activity was performed throughout the year 
comprising sanitation measures, conservation, land 
management and operation of public-use facilities. Work 
was limited in scope as bulk of reservoir lands are owned by 
Commonwealth of Pennsylvania. 
18. KINZUA DAM AND ALLEGHENY 
RESERVOIR, OHIO RIVER BASIN, 
PA AND NY 
Location. Dam site is on Allegheny River 9 miles above 
Warren, PA, and 198 miles above mouth of river at Pittsburgh, 
PA. Reservoir is in Warren and McKean Counties, 
PA., and Cattaraugus County, NY. (See Geological Survey 
Charts for Warren and Kinzua, PA - NY, and Randolph and 
Salamanca, NY.) 
Existing project. Reservoir provides flood control, low 
water regulation, and recreation. Dam consists of a 
combination concrete gravity structure and rolled earth 
embankment with gate-controlled spillway and discharge 
conduits controlled by slide-gates in gravity section. Construction 
of project, initiated in February 1960, is complete. 
Construction of dam was started in September 1960 and 
completed in December 1965. Development of recreation 
area at Onoville under a cost-sharing agreement with 
Cattaraugus County was completed in June 1978. Land 
acquired for project consists of 2,646.6 acres in fee and 
easements over 22,420.4 acres. For further details see 
Annual Report for 1962, page 1202. Project was authorized 
by Flood Control Acts of 1936, 1938 and 1941. 
Current estimate for construction of recreation facilites at 
completed project is $1,023,000 of which $504,000 are non- 
Federal costs. A major rehabilitation plan was approved for 
repairs to the dam stilling basin. Current cost estimate for 
this work is: $2,800,000. 
Local cooperation. None required by law. 
Licenses. The Federal Power Commission granted a 
license to Pennsylvania Electric Company and Cleveland 
Electric Illuminating Company on December 28, 1965, for 
the joint construction, operation and maintenance of a 
325-megawatt pumped-storage installation (FPC Project 
No. 2280). The project is complete. 
Operation during fiscal year. New Work: Plans and 
specifications were initiated and completed in fiscal year 
1983 for Stilling Basin Rehabilitation with a contract 
awarded for the same in June 1983 for $1,278,600. Construction 
progressed to 13% completion by end of fiscal 
year. Operation and maintenance, general: Feature design 
memorandum was initiated in fiscal year 1981 and completed 
in Nov 1982. Reservoir was operated for benefit of 
flood control and low water regulation, as required, and 
necessary repairs were made to structures and appurtenances. 
Estimated flood control benefits achieved by this 
reservoir for this period were $2,372,000, total to end of this 
fiscal year, $304,550,000. Of 2,212 surface tracts authorized 
for acquisition, all have been acquired. Final judgments 
remain to be entered on 16 surface tracts acquired by 
condemnation. Activities under reservoir management 
program comprising sanitation measures, conservation, 
land management, and operation and maintenance of 
public-use facilities continued. 
19. LOYALHANNA LAKE, OHIO 
RIVER BASIN, PA 
Location. Dam is on Loyalhanna Creek, 4.5 miles above 
junction of creek with Conemaugh River at Saltsburgh, PA, 
and about 29 miles east of Pittsburgh, PA. Reservoir is in 
Westmoreland County, PA. (See Geological Survey Chart 
for Latrobe, PA). 
Existing project. A flood control reservoir dam of 
concrete gravity type with a gate-controlled center spillway 
flanked by abutment sections joining valley sides, and an 
earth embankment section ending in left abutment. 
Authorized project is complete. Reservoir is in operation as 
a unit of a coordinated reservoir system designed for 
protection of Pittsburgh and reduction of flood heights in 
upper Ohio Valley, generally. Construction of dam was 
started in October 1939 and completed in June 1942. Land 
acquired for project consists of 3,334.7 acres in fee and 
easements over 86.7 acres. Project was Control authorized by Flood Acts of 1936 and 1938. For further project 
description see Annual Report for 1962, page 1219. 
Current estimated cost of recreation and sanitary facilities 
at completed project is $2,896,000. Of this amount, 
$1,298,000 would be non-Federal costs. 
Lclcooperation. None required by law. 
Operations during fiscal year. Operation and 
maintenance, general: Contract for Construction of 
Resource Manager's Office and Restrooms awarded in Jan 
1982 was completed in Jan 1983. Contract for Master Plan 
Design Memorandum No. 1 progressed to 77% comple- 
26-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
tion. An environmental impact assessment delayed master 
plan completion date 'to Mar 5, 1984. Reservoir was 
operated for benefit of flood control, as required, and 
necessary repairs were made to structures and 
appurtenances. Estimated flood control benefits achieved 
by this reservoir for this fiscal year were $204,000; total 
benefits to September 30, 1983, $158,392,000. Activities 
under reservoir management program comprising 
sanitation measures, conservation, land management and 
operation and maintenance of public-use facilities 
continued. 
20. MAHONING CREEK LAKE, 
OHIO RIVER BASIN, PA 
Location. Dam is on Mahoning Creek in Armstrong 
County, PA, 21.6 miles above junction of creek with 
Allegheny River. It is about 6.50 miles southeast of New 
Bethlehem, PA, and about 51 miles northeast of Pittsburgh, 
PA. Reservoir is in Armstrong, Indiana, and 
Jefferson Counties, PA. (See Geological Survey Charts for 
Rural Valley and Smicksburg, PA.) 
Existing project. A flood control reservoir dam of 
concrete gravity type with a gate-controlled center 
spillway flanked by abutment sections joining valley 
sides. Authorized project is complete. Reservoir is in 
operation as a unit of a coordinated reservoir system 
designed for protection of Pittsburgh and reduction of 
flood heights in upper Ohio Valley, generally. Construction 
of dam was started in February 1939 and completed in 
June 1941. Land acquired for project consists of 2,532.6 
acres in fee and easements over 83.5 acres. Project was 
authorized by Flood Control Acts of 1936 and 1938. For 
further project description see Annual Report for 1962, 
page 1210. 
Current estimated cost of recreation and sanitary 
facilities at completed project is $1,108,000. Of this 
amount, $505,326.01 are non-Federal costs. 
Local cooperation. None required at completed project. 
On November 4, 1977 a contract for wildlife development 
at Mahoning Creek Lake was executed between the U.S. 
Government and the Pennsylvania Game Commission. 
Each party will payor contribute in kind 50% of the first 
costs of initial wildlife development. On June 7, 1979, a 
contract for fishing and boating development at Mahoning 
Creek Lake was executed between the U.S. Government 
and the Pennsylvania Fish Commission. Each party will 
pay or contribute in kind 50% of the first costs of initial 
fishing and boating development. On September 9, contract 1980, a for camping and day-use recreational development 
was executed between the U.S. Government and the 
County of Armstrong. Each party will pay or contribute in 
kind 50% of the first costs of initial camping and day-use 
recreational development and 50% of the costs for future 
development. Each cooperating authority is responsible 
for operation, maintenance and replacements without cost 
to the Government of all facilities developed with their 
support. 
Operations and results during fiscal year. New work: 
Cost-sharing for Construction of Fishing Access Area 
awarded in Sep 1980 was completed in Jul 1981 for 
$335,405.75. Cost-sharing contract for Construction of 
Hunting Access Areas awarded Jul 30, 1980 was 
completed on Nov 25, 1981 at a final cost of $44,540. Costsharing 
contract for Construction of Milton Loop 
Recreation Area awarded Jul 29, 1981 was completed on 
Sep 17, 1982 for approximately $402,500. $456,611 has 
been contributed by local interests towards cost-sharing 
developments. Operations and maintenance, general: 
Reservoir was operated for benefit of flood control as 
required, and necessary repairs were made to structures 
and appurtenances. Estimated flood control benefits 
achieved by this reservoir for this fiscal year were 
$152,000; total to September 30, 1983, $147,480,000. 
Activities under reservoir management and maintenance 
for public-use facilities continued. 
21. MICHAEL J. KIRWAN DAM AND 
RESERVOIR, OH 
Location. Dam site is on West Branch of Mahoning 
River which joins Mahoning River at Newton Falls, OH. 
It is 11 miles above mouth of branch and about 15 miles 
upstream from Warren, OH. Reservoir is in Portage 
County, OH. (See Geological Survey Charts for Ravenna, 
Garrettsville, Chagrin Falls, and Kent, OH.) 
Existing project. Reservoir provides flood control, lowwater 
regulation and recreation. Dam consists of a rolledearth 
embankment structure with gate-controlled outlet 
works and an uncontrolled side-hill spilway through left 
abutment. Authorized project is complete and in operation 
for flood control and low water regulation purposes. Construction 
of dam and access road was started in May 1963 
and completed in November 1966. Land acquired for 
project consists of 6,298.9 acres in fee and easements over 
27.9 acres. For further description see Annual Report for 
1962, page 1231 (West Branch Reservoir, Mahoning 
River, Ohio). Project was authorized by 1958 Flood Control 
Act (H. Doc. 191, 85th Cong. 1st sess.), with local 
contribution requirements modified by Flood Control Act 
of 1960. Federal cost of completed project was 
$17,370,000. Local interests contributed $3,230,000 
during period of contruction bringing initial project cost to 
$20,600,000. 
Local Cooperation. Local interests must contribute 
$5,200,000 for water pollution abatement and for municipal 
and industrial water supply purposes, of which 
$b3a,l2a3n0ce,0 0a0t twimaes ppraoidje cint icsa pshla cdeudr iinng o cpoenrasttriuonct, io$n1., 97U0n,0p0a0id, 
will be paid in cash at that time or on an annual basis. Of 
the unpaid balance of contributed funds due and payable, 
payment in full of Trumbull County's share in the amount 
of $663,040 has been received. Mahoning County elected 
to pay their share ($1,306,960) in 50 annual installments of 
$50,323.32, including interest, and has paid $418,227.20 
toward principal to date. Local interests have now 
contributed $4,311,267.20 towards total of $5,200,000 
non-Federal costs. 
Operations during fiscal year. Operation and 
maintenance, general: Contract for Master Plan Design 
Memorandum No. 8 was completed in Dec 1982 and 
26-8

PITTSBURGH, PA., DISTRICT 
approved by division in Jan 1983. Reservoir was operated 
for benefit of flood control and low-flow augmentation, as 
required, and necessary repairs were made to structures 
and appurtenances. Estimated flood control benefits 
achieved by this dam for this fiscal year were $620,000. 
Total flood control benefits for this reservoir through 
September 30, 1983 are $67,040,000. Activities under 
reservoir management program comprising sanitation 
measures, conservation, land management, and operation 
and maintenance of public-use facilities continued. 
22. MOSQUITO CREEK LAKE, OHIO 
RIVER BASIN, OH 
Location. Dam is on Mosquito Creek, 9 miles above 
junction of creek with Mahoning River at Niles, OH, and 
about 18 miles northwest of Youngstown, OH. (See Geological 
Survey Charts for Bristolville and Kinsman, OH, 
and Pennsylvania.) 
Existing project. A reservoir for flood control, low-water 
regulation and water supply storage. Dam is rolledearthfill 
type with outlet facilities through dam, and an 
uncontrolled natural wasteway to discharge overflow from 
reservoir. Authorized project is complete and in operation 
for flood control and low-water regulation purposes in 
industrialized Mahoning and Beaver Valleys below. Construction 
of dam was started in July 1943 and was ready 
for beneficial use in January 1944. Land acquired for 
project consists of 11,180.4 acres in fee and easements 
over 276.0 acres. State of Ohio has a license from Secretary 
of the Army for development and operation of recreation 
facilities in reservoir area. Project was selected for 
construction under general authorization for Ohio River 
Basin in 1938 Flood Control Act. For further project 
description see Annual Report for 1962, page 1228. 
Current estimate of total recreation and sanitary 
facilities required to upgrade areas and comply with 
sanitary codes is $2,155,000 of which $795,000 would be 
non-Federal costs. 
Local cooperation. None required at completed project; 
however, future recreational developments are subject to 
certain conditions of non-Federal cost-sharing under 
Federal Water Project Recreation Act of 1965. 
Operations results during fiscal year. Operation and 
maintenance, general: Reservoir was operated for benefit 
of flood control and low-flow regulation as required, and 
necessary repairs were made to structures and appurtenances. 
Estimated flood control benefits achieved by this 
dam for this fiscal year were $1,047,000. Total flood 
control benefits for this reservoir through September 30, 
1983 are $54,831,000. Activities under reservoir management 
program comprising sanitation measures, conservation, 
land management and operation and maintenance of 
certain public-use facilities continued. This work was 
limited in scope as State of Ohio has jurisdiction over 
recreation in reservoir area. 
23. OHIO RIVER BASIN 
(PITTSBURGH DISTRICT) 
Location. A series of dikes, floodwalls, channel improvements, 
and reservoirs/lakes in Ohio River Basin within 
Pittsburgh District. 
Existing project. Individual projects considered in 
comprehensive plan within Pittsburgh District. (See 
Tables 26-B, 26-K and 26-L on Acts authorizing existing 
projects, local protection projects and reservoirs.) 
Operations during fiscal year. New work: None by the 
United States except as stated in individual projects. 
Completed local protection projects operated and maintained 
by local interests, including those projects for 
which individual reports have been included, prevented 
flood damages of an estimated $3,942,000 during this 
fiscal year. Total flood damages prevented through 
September 30, 1983 are $647,436,000. 
24. SHENANGO RIVER LAKE, OHIO 
RIVER BASIN, PA AND OH 
Location. Dam is on Shenango River about 0.8 mile 
above Sharpsville, PA, and about 33 miles above junction 
of river with Mahoning River, which unite near New 
Castle, PA, to form Beaver River. Reservoir is in Mercer 
County, PA, and Trumbull County, Ohio. (See Geological 
Survey Chart for Kinsman, Ohio, and Shenango, PA.) 
Existing project. A reservoir for flood control, low-flow 
augmentation and recreation. Dam consists of a concrete 
gravity structure with gate-controlled outlet works and an 
uncontrolled center spillway section. Authorized project is 
complete. Reservoir is in operation for low-water regulation 
purposes in Shenango River valley below and for 
flood control as a unit. of a coordinated reservoir system 
for protection of Shenango River valley and the Beaver 
and upper Ohio River Valley, generally. Construction of 
dam was started in March 1963 and completed May 1965. 
Land acquired for project consists of 14,632.2 acres in fee 
and easements over 197.7 acres. Future work consists of 
completion of project lands of any additional recreation 
facilities as required to serve the public needs. For further 
project description, see Annual Report for 1962, page 
1230. Project was authorized by 1938 Flood Control Act. 
Local cooperation. None required by law. 
Operations during fiscal year. Operation and 
maintenance, general: Reservoir was operated for benefit 
of flood control and low-flow augmentation, as required, 
and necessary repairs were made to structures and appurtenances. 
Estimated flood control benefits achieved by 
this reservoir for this period were $376,000. Total flood 
control benefits for this dam through September 30, 1983 
are $14,591,000. Activities under reservoir management 
program comprising sanitation measures, conservation, 
land management and operation and maintenance of 
public-use facilities continued. 
25. wSTvONEWALL JACKSON LAKE, 
Location. In Lewis County, North Central West 
Virginia, on the West Fork River, which joins the Tygart 
River at Fairmont, West Virginia to form the Monon- 
26-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
gahela River. Damsite is located at Brownsville, West 
Virginia, about 4 miles south of Weston and 72 miles 
above mouth of West Fork. River at Fairmont, WV. (See 
Geological Survey Charts for Weston and Crawford, WV.) 
Existing project. Provides for construction of a reservoir 
for flood control, water supply, water quality control, area 
redevelopment and recreation. Dam would be of the concrete 
gravity type, 95 feet high and 620 feet long. Outlet 
works will consist of five multi-level sluices, spillway will 
be uncontrolled. Storage capacity will be 74,650 acre-feet 
controlling an area of 102 square miles. Project was 
authorized by 1966 Flood Control Act. Estimated initial 
Federal cost for new work (1983) is $198,000,000 (includes 
$19,765,000 reimbursement by non-Federal interests.) 
Local cooperation. Local interests are required to make 
arrangements for repayment, under the provisions of the 
Water Supply Act of 1958, as amended, of that part of the 
construction cost and annual operation, maintenance and 
replacement costs allocated to municipal and industrial 
water supply, an amount presently estimated at 
$4,300,000 for construction; and $15,000 annually for 
operations, maintenance and replacements. Also, in 
accordance with Federal Water Project Recreation Act, 
local interests are required to administer project land and 
water areas for recreation and fish and wildlife enhancement, 
pay, contribute in kind or repay (which may be 
through user fees) with interest, one-half of the separable 
first cost of the reservoir project allocated to recreation 
and fish and wildlife enhancement, an amount presently 
estimated at $15,465,000; bear all costs of operation, 
maintenance and replacement of recreation and fish and 
wildlife land and facilities, the amount involved being 
currently estimated on an average annual basis to be 
$1,117,500, exercise to the full extent of their legal 
capability, control against removal of streamflow made 
available for water quality control; and contribute to the 
control of pollution of streams subject to low-flow 
augmentation by adequate treatment or other methods of 
controlling wastes at their source. The requirements of 
Section 221 were amended in 1971 to exempt assurances 
for future demands for water supply pursuant to the 
Water Supply Act of 1958 from the contractual requirements 
of the Act. Accordingly, the City of Weston, West 
Virginia, has provided assurances that it will enter into a 
water supply contract with the Department of the Army 
within a period of time which will permit paying out the 
costs allocated to the water supply storage within the life 
of the project. A recreation cost-sharing contract, in 
accordance with the requirements of the Federal Water 
Project Recreation Act, P.L. 89-72, was executed by the 
State of West Virginia on March 27, 1977. Local cooperation 
assurances for recreation cost-sharing were 
executed by the Governor and Attorney General of West 
Virginia on May 29, 1973. In this connection, Section 8 of 
P.L. 92-222 deleted the requirement that the State of West 
Virginia "hold and save the United States free from 
damages resulting from water rights claims due to construction 
and operation of the project." Legislation 
relieving Stonewall Jackson Lake, WV, project of the 
requirements of Section 221, P.L. 96-611 was contained in 
Water Resources Development Act of 1974 signed by the 
President on March 7, 1974. 
Operations during fiscal year. New work: Contract with 
Equitable Gas Co. for Gas Storage Replacement Wells 
awarded in Mar 1982 was completed in Nov 1982. 
Relocation of US Rt. 19, Section 1 contract awarded Jan 
26, 1982 was 82% complete and Relocation of US Rt. 19, 
Section 2 contract awarded Mar 4, 1982 was 88% complete 
at end of fiscal year. 
A cost-reimbursable contract for relocation of power 
facilities to accommodate the Stonewall project - State 
Rt. 23 was awarded in Sep 1982 and completed in Oct 
1982. Cost-reimbursable contract for relocation of certain 
pipeline facilities awarded in Sep 1982 was completed in 
Dec 1982. 
Relocation Rt. 19, Sec. 3 contract was awarded Nov 16, 
1982 and 44% complete at end of fiscal year. Supply 
contract for Slide Gates, Hydraulic Cylinders, Sluice 
Liners and Deflector Plates awarded Sep 29, 1982 for 
$996,732 progressed to 67% completion and Construction 
of Dam Access Roads contract awarded Sep 29, 1982 for 
$1,003,062.38 progressed to 61% completion by end of 
fiscal year. Contract for Cemetery Relocations, Sec. 3, 
awarded Mar 31, 1983, was 100% complete at end of fiscal 
year. 
Construction of Equitable Gas Access Roads, Section 1, 
awarded Jun 17, 1983 progressed to 99% completion and a 
cost-reimbursable contract with Equitable for Relocation, 
Subordination, Removal or Abandonment of Section 1 
Access Roads was negotiated in May 1983 and is 
scheduled to be completed by July 1986. Contract for 
Construction of Dam was awarded July 29, 1983 for 
$15,985,063.75 and is scheduled for completion by Sep 6, 
1987. Dam construction contract progressed 5% by end of 
fiscal year. 
Design Memorandum (DM) No. 7, Public-Use Plan was 
completed in Sep 1982 and approved by division on Nov 
29, 1982. The WV Dept. of Natural Resources approved 
DM 7 by letter dated Jul 9, 1982. Design Memorandum 
No. 10, School Relocation was completed by Huntington 
District Real Estate and approved by Office of the Chief 
on Jan 8, 1982. DM No. 11, Concrete Materials was 
completed in Sep 1982 and approved by division on May 
26, 1983. An agreement was executed in FY 1982 with 
Lewis County School Board covering the new school site 
acquisition and the arrangements for the preparation of 
plans and specifications. Plans and specifications were 
initiated in FY 1983 and progressed to 40% completion by 
end of fiscal year. 
acq6u4i4r edof an estimated 800 surface tracts have been 
Land acquisition, detailed engineering work and 
construction continued and all items of work were 
progressing on schedule. 
26. TIONESTA LAKE, OHIO RIVER 
BASIN, PA 
Location. Dam is on Tionesta Creek, 1.25 miles above 
junction of creek with Allegheny River at Tionesta, PA, 
and about 78 miles northeast of Pittsburgh, PA. Reservoir 
is entirely in Forest County, PA. (See Geological Survey 
Charts for Tionesta, Tidioute and Sheffield, PA.) 
26-10

PITTSBURGH, PA., DISTRICT 
Existing project. A flood control reservoir dam of 
earthfill type with separate uncontrolled saddle spillway 
and tunnel outlet works. Authorized project is complete. 
Reservoir is in operation as a unit of a coordinated 
reservoir system designed for protection of Pittsburgh and 
reduction of flood heights in upper Ohio Valley, generally. 
Construction of dam was started in May 1938 and completed 
January 1941. Land acquired for project consists of 
2,797.3 acres in fee and easements over 13.1 acres. Future 
work consists of provision on project lands of additional 
recreational facilities as required to serve public needs. 
Project was authorized by Flood Control Acts of 1936 and 
1938. For further project description see Annual Report 
for 1962, page 1203. 
Current estimate for construction of recreation and 
sanitary facilities required to upgrade areas and comply 
with sanitary codes is $2,833,700. 
Local cooperation. None required by law. 
Operations during fiscal year. New work: Contract for 
Replacement of Water System at Dam awarded May 26, 
1982 was completed Nov 28, 1982. $518,509.66 was 
obligated to aid in construction of a treatment plant and 
for connection charges to tie-in camping area below the 
Tionesta Regional Sewage Treatment Plant. The 
Borough of Tionesta awarded their contract for 
construction of treatment plant in May 1982 and all work 
was completed in August 1983. A contract was awarded 
Aug 29, 1983 for an estimated $187,207.50 for 
Construction of Sanitary Facilities, Spillway Boat 
Launching Area and is scheduled for completion Aug 8, 
1984. Operation and maintenance general: Reservoir was 
operated for benefit of flood control and low-flow 
augmentation, as required, and necessary repairs were 
made to structures and appurtenances. Estimated flood 
control benefits achieved by this reservoir for this period 
were $442,000. Total flood control benefits for this 
reservoir through September 30, 1983 are $159,384,000. 
Activities under reservoir management program 
comprising sanitation measures, conservation, land 
management and operation and maintenance of publicuse 
facilities continued. 
27. UNION CITY DAM, PA 
Location. In Erie County, northwestern Pennsylvania, 
on French Creek, a tributary of Allegheny River. Damsite 
is 24 miles upstream from Cambridge Springs, PA, 
and 41 miles upstream from Meadville, PA. (See 
Geological Survey Chart for Union City, PA - NY.) 
Existing project. A flood control reservoir dam of earth 
embankment nongated type with uncontrolled sidechannel 
spillway. Outlet works consist of a lower outlet 
located in valley floor constructed of reinforced concrete 
conduit 8 feet by 4.5 feet and an upper outlet consisting 
of an uncontrolled slot 9.5 feet wide through the north 
end of the ogee weir in the spillway. Dam is 1,420 feet 
long at top rising 88 feet above streambed and provides 
gross capacity of 47,640 acre-feet from a drainage area of 
222 square miles. Project authorization was modified to 
provide for a conservation pool and addition of recreation 
facilities. On November 5, 1974, a referendum proposal 
was defeated by the constituents of Erie County in 
regard to the cost-sharing for construction of recreation 
facilities. In view of the foregoing, all action toward 
implementation of the authorized project modification 
was discontinued. Reservoir is operated as one of a tworeservoir 
system for reduction of flood stages in French 
Creek Basin between damsite and mouth, Allegheny 
River from Franklin, PA, to Pittsburgh, PA, inclusive, 
and upper Ohio River Valley. Initial highway relocations 
were completed in October 1968 and remaining highway 
relocations were completed in May 1972. Construction of 
the dam was started in July 1968 and completed in 
September 1971. Land acquired for project consists of 
465.2 acres in fee and easements over 2,154.6 acres. 
Existing project was authorized by 1962 Flood Control 
Act. 
Local cooperation. Local interests are required to 
inform affected interests in French Creek Basin at least 
annually, that the system of reservoirs of which Union 
City Dam is a part, will not provide protection against 
maximum floods. November 10, 1964 the Department of 
Forests and Waters of the Commonwealth of Pennsylvania 
furnished formal assurances of local cooperation in 
respect to notifying local interests at least annually that 
the system of reservoirs will not provide protection 
against maximum floods. A referendum on the ballot 
during the November 1974 election regarding the 
approval to cost-share the maintenance of a summer pool 
was defeated by the local voters. 
Operations during fiscal year. Operation and 
maintenance, general: Maintenance of the structure and 
appurtenances was performed as required. This dam 
acted as an uncontrolled detention type dam during the 
fiscal year. Estimated flood control benefits achieved by 
this reservoir for this period were $155,000. Total flood 
control benefits for this reservoir through September 30, 
1983 are $9,748,000. 
28. WOODCOCK CREEK LAKE, PA 
Location. In Crawford County, northwestern 
Pennsylvania, on Woodcock Creek, a tributary of French 
Creek. Damsite is about 4.1 miles above mouth of 
Woodcock Creek and about 5 miles northeast of Meadville, 
PA. (See Geological Survey Chart for Meadville, PA.) 
Existing project. A flood-control reservoir dam of rolledearth 
embankment type, gate-controlled outlet works with 
a 6 foot-wide by 7.75 foot-high conduit and uncontrolled 
saddle spillway on the left abutment. Dam is 4,650 feet 
long at top rising 90 feet above streambed and provides for 
gross capacity of 20,000 acre-feet from a drainage area of 
46 square miles. Reservoir is operated as one of a tworeservoir 
system for reduction of flood stages in French 
Creek Basin between damsite and mouth, Allegheny River 
from Franklin, PA, to Pittsburgh, PA, inclusive, and 
upper Ohio River Valley. Authorized project is complete. 
Construction of dam was started in July 1970 and 
completed in July 1973. Land acquired for project consists 
of 1,731.4 acres in fee and easements over 1.2 acres. 
Project was authorized for flood control and recreation by 
1962 Flood Control Act. Storage for water quality control 
26-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
was added to the project during the preconstruction 
planning stage. 
Current estimate for construction of sanitary facilities, 
required to comply with state sanitary codes, at completed 
project is $1,811,000. 
Local cooperation. Local interests must inform affected 
interests in French Creek Basin at least annually, in a 
manner satisfactory to District Engineer, that a system of 
reservoirs of which Woodcock Creek Lake is a part, will 
not provide protection against maximum floods. Pennsyl-. 
vania Department of Forests and Waters assumed responsibility 
of local cooperation for project. 
Operations during fiscal year. New work: Contract for 
Construction of Bossard Area Restrooms awarded Sep 30, 
1982 for $157,776 was completed Aug 5, 1983. $713,100 
was obligated to aid in construction of Saegertown 
Treatment Plant and connection charges to tie-in 
recreation sanitary facilities. Borough of Saegertown 
awarded their contract for construction of treatment plant 
in Feb 1982 with a scheduled completion of Oct 19, 1983. 
Construction of plant was 90% complete at end of fiscal 
year. Operation and maintenance, general: Maintenance of 
the structure and appurtenances was performed as 
required. Estimated flood control benefits achieved by this 
reservoir for this period were $21,000, total through 
September 30, 1983 is $1,270,000. 
29. YOUGHIOGHENY RIVER LAKE, 
OHIO RIVER BASIN, PA AND MD 
Location. Dam is on Youghiogheny River about 74.2 
miles above its junction with Monongahela River at 
McKeesport, PA. It is 1.2 miles upstream from 
Confluence, PA, and about 57 miles southeast of 
Pittsburgh, PA. Reservoir is in Fayette and Somerset 
Counties, PA, and Garrett County, MD. (See Geological 
Survey Charts for Confluence, PA, Accident, MD, West 
Virginia and Pennsylvania.) 
Existing project. Reservoir for flood control, low-flow 
augmentation, and pollution abatement purposes. Dam is 
rolled-earthfill type with separate uncontrolled side 
channel spillway and tunnel outlet works. Authorized 
project is complete. Reservoir is in operation for flood 
control, low-flow augmentation, and pollution abatement 
purposes. For flood control, reservoir is operated as a unit 
of a coordinated reservoir system designed for protection 
of Pittsburgh and reduction of flood heights in upper Ohio 
Valley, generally. Construction of dam was started in June 
1940 and completed May 1944. Land acquired for project 
consists of 3,914.9 acres in fee and easements over 0.48 
acre. A license was issued Commonwealth of Pennsylvania 
covering fish conservation and management in Pennsylvania 
portion of reservoir. Future work consists of 
provision on project lands of additional recreational and 
sanitary facilities as required to serve public needs. 
Project was selected for construction under general 
authorization for Ohio River Basin in 1938 Flood Control 
Act. For further project description see Annual Report for 
1962, page 1223. 
Current estimate of recreation and sanitary facilities at 
completed project is $4,245,400. 
Local cooperation. None required. 
Operations during fiscal year. Operations during fiscal 
year. New work: A contract was awarded Aug 10, 1983 for 
$221,617.40 for Construction of Comfort Station #3 and 
Sanitary Trailer Station; contract is scheduled to be 
completed by Sep 11, 1984. Operation and maintenance, 
general: Design Memorandum No. 1, Master Plan was 
completed in Aug 1981 and approved by division on Nov 
15, 1982. Reservoir was operated for benefit of flood 
control, as required, and necessary repairs were made to 
structures and appurtenances as required. Estimated 
flood control benefits achieved by this reservoir for this 
period were $434,000. Total flood control benefits for this 
dam through September 30, 1983 are $124,899,000. 
Activities under reservoir management program 
comprising sanitation measures, conservation, land 
management, and operation and maintenance of public-use 
facilities were continued. 
30. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Flood Control Act of June 22,1936, and subsequent acts 
require local interests to furnish assurances that they will 
maintain and operate certain local protection projects 
after completion in accordance with regulations prescribed 
by Secretary of the Army. District Engineers are responsible 
for administration of these regulations within 
boundaries of their respective districts. Inspections were 
made of completed units transferred to local interests for 
maintenance and operation and local interests were 
advised, as necessary, of measures required to maintain 
these projects in accordance with standards prescribed by 
regulations. (See Table 26-M for dates of inspections.) 
Costs for this fiscal year, $67,180. Total cost to 
September 30, 1983 was $748,849. 
31. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
See Table 26-E on other authorized flood control 
projects. 
32. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
For flood control activities pursuant to Section 
205, Public Law 858, 80th Congress, as mended 
(preauthorization) 
See Table 26-N. 
For emergency bank protection (Sec. 14 of 1946 Flood 
Control Act, Public Law 526, 79th Cong.) 
See Table 26-N. 
For Streambank Erosion Control Evaluation and 
Demonstration Act of 1974 (Sec. 32, Public Law 251, 
93rd Cong.) 
See Table 26-N. 
For Shoreline Erosion Control Demonstration Act of 
1974 (See. 54, Public Law 251, 93rd Congress) 
See Table 26-N. 
26-12

PITI'IURGiH. PA., DISFMUCF 
Flood control and coastal ergemeacies (Puie Law so 
84th Cong., and antecedent leglelatise). 
Advance preparation $124,304 
Total cost for fiscal year:. $124,804 
General Investigations 
33. SURVEYS 
Flood control studies 
Review of authorized projects 
Coordination with other agencies 
Inventory of dams 
(P.L. 92-367) 
Total cost for fiscal year 
$1,888,812 
52 
210 
107,692 
$1,991,766 
34. COLLECTION AND STUDY OF 
BASIC DATA 
Costs this fiecal year waie $154,254 for flood plain 
management services and 81,416 for related hydrologic 
5. RESEARCH AND DEVELOPMENT 
No expenditures this fiscal year. 
2613

TABLE 26-A 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
COST AND FINANCIAL STATEMENT 
See Total Cost to 
Section Sep 30, 
In Text Project Funding FY 80 FY 81 FY 82 FY 831983 
Navigation - Locks and Dams 
1. Allegheny River New Work 
PA Approp. 
Cost 
Maint. 
Approp. 
Cost 
3. Monongahela New Work 
River, PA and Approp. 
WV Cost 
Maint. 
Approp. 
Cost 
Major Rehab. 
Approp. 
Cost 
5. Tygart Lake, New Work 
WV Approp. 
Cost 
Maint. 
Approp. 
Cost 
Flood Control- Local Protection 
7. Allegheny River New Work 
Oil City, PA Approp. 
Cost 
8. Chartiers New Work 
Creek, PA Approp. 
(Federal Funds) Cost 
New Work 
(Contributed Contrib. 
Funds) Cost 
9. Elkins, WV New Work 
Approp. 
" Cost 
Maint. 
Approp. 
Cost 
10. Girty's Run, New Work 
Millvale, PA Approp. 
(Federal Funds) Cost 
New Work 
(Contributed Contrib. 
Funds) Cost 
11. Johnstown, PA New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
12. Punxsutawney, New Work 
Ohio River Approp. 
Basin, PA Cost 
Maint. 
Approp. 
Cost 
13. Root Creek, New Work 
Bolivar, NY Approp. 
Cost. 
Flood Control - Reservoirs 
14. Berlin Lake 
Ohio River Basin, 
OH 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
- 
3,093,800 
3,090,667 
5,777,000 
5,899,630 
5,146,800 
4,972,781 
5,777,000 
5,892,733 
60,000 
25,078 
514,600 
476,838 
3,419,700 
3,096,229 
2,180,000 
2,718,722 
6,194,000 
6,207,403 
2,180,000 
2,712,043 
514,588 
129,285 
502,800 
507,623 
- 55,000 
- 39,365 
2,299,000 1,602,983 
2,574,399 1,524,356 
119,906 
73,900 
32,188 
75,000 
744,510 
231,451 
7,000 
7,064 
13,400 
13,412 
661,035 
727,192 
35,000 
32,764 
948,800 
900,415 
-17,846 
25, 
60, 
28, 
2,693,000 
3,100,425 
2,657 
6,290,000 
5,968,529 
115,139 
489,000 
584,004 
583,500 
583,113 
1
76 
620,000 349,0 
215,428 620,1 
82,727 
1,329 
000 6,000 
324 6,597 
-470,000 
586 -451,892 
417 - 
47,000 
43,525 
5,000 
4,856 
251,000 
428,012 
-2,889 
15,827 
1,015,300 
984,740 
83,000 
74,974 
6,000 
5,081 
100,000 
157,472 
2,708 
902,600 
897,342 
- 18,157,860' 
- 18,157,860' 
270,300 45,601,8622 
248,945 45,525,8188 
- 129,203,085 
80 129,203,046 
165,440 118,977,654' 
160,530 117,991,2626 
- 15,977,000 
66,402 15,810,506 
- 19,495,432' 
03,046 19,273,257" 
T10,000 6,705,339' 
42,587 6,590,629'0 
)00 1,024,000 
143 874,936 
26,586,186 
176 26,486,781 
221 4,225,188 
X21 4,199,499 
1,772,627 
1,772,627 
214,487 
188 214,161 
2,665,000 
19 2,648,849 
701,722 
701,722 
8,865,388" 
8,865,388" 
)00 3,471,796 
12 3,469,176 
3,586,10712 
3,586,10712 
)00 1,018,900' 3 
711 738,535' 
)00 1,597,385 
)47 1,570,051 
-8 
119,0 
127,9 
308,(0 
28,7 
-5,0 
102,0 
-2,500 
56 
1,048,000 
1,110,833 
8,739,978 ' 
8,739,978"6 
10,837,78316 
10,789,51116 
26-14 
3,2

PITTSBURGH, PA., DISTRICT 
TABLE 26-A 
(Continued) 
COST AND FINANCIAL STATEMENT 
See Total Cost to 
Section Sep 30, 
In Text Project Funding FY 80 FY 81 FY 82 FY 831983 
15. Conemaugh 
River Lake, Ohio 
River Basin, PA 
16. Crooked Creek 
Lake, Ohio 
River Basin, PA 
17. East Branch, 
Clarion River 
Lake, Ohio 
River Basin, PA 
18. Kinzua Dam and 
Allegheny 
Reservoir, Ohio 
River Basin, PA 
and NY 
19. Loyalhanna 
Lake, Ohio River 
Basin, PA 
20. Mahoning Creek 
Lake, Ohio 
River Basin, PA 
21. Michael J. Kirwan 
Dam and 
Reservoir, OH 
22. Mosquito Creek 
Lake, Ohio River 
Basin, OH 
23. Ohio River Basin, 
Pittsburgh, PA 
District 
Consolidated 
24. Shenango River 
Lake, Ohio River 
Basin, PA 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Minor Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
441,300 
403,274 
9,383 
109,636 
460,500 
452,913 
15,000 
14,984 
411,000 
402,723 
-30,378 
10,904 
737,100 
760,141 
-2,331 
764,900 
711,562 
61,000 
43,693 
346,800 
305,466 
434,100 
390,939 
-1,271 
294,300 
290,850 
2,995 
1,244,700 
1,201,999 
52,000 
51,566 
514,600 
508,659 
-1,748 
803 
753,800 
552,917 
-16 
409,700 
455,494 
-1,735 
5,135 
795,600 
785,849 
15,000 
11,422 
643,600 
705,277 
273,706 
400,112 
487,800 
453,571 
17,374 
480,600 
492,385 
421,800 
404,245 
8,529 
1,632,600 
1,551,254 
280,000 
78,631 
529,000 
519,823 
1,166,300 
1,221,024 
574,700 
560,055 
-50 
958,600 
951,570 
185,000 
104,826 
175,000 
52,647 
1,031,500 
809,831 
-8,238 
99,952 
662,900 
705,652 
21,000 
3,584 
506,100 
498,645 
394,400 
385,562 
1,411,400 
1,367,677 
190,398 
476,000 
529,107 
33,500 
1,041 
1,125,000 
1,217,561 
892,617 
703,184 
-5,162 
1,129,000 
1,120,473 
1,050,000 
948,001 
-20,000 
100,519 
1,131,100 
1,146,746 
84,066 
531,000 
540,383 
42 
765,000 
455,236 
536,000 
513,256 
72 
1,357,000 
1,391,237 
46,016,41117 
46,005,00618 
5,136,713 
5,126,262 
4,368,523'19 
4,336,06420 
6,799,72121 
6,729,66422 
9,539,58523 
9,539,58583 
5,441,45224 
5,180,95788 
109,309,076" 
109,288,705" 
11,143,778 
11,055,163 
1,235,000 
1,052,827 
5,732,53127 
5,727,12028 
7,551,274" 
7,321,3153 
7,304,81331 
7,204,09732 
5,363,816 
5,330,919 
47,033 
47,033 
17,376,09733 
17,376,09733 
5,089,8893' 
4,735,48535 
4,253,029" 
4,253,029" 
4,724,364 
4,662,754 
985,197" 
985,197"5 
40,227,201 
40,220,394" 
11,293,617"� 
11,120,142w 
26-15

TABLE 26-A 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
COST AND FINANCIAL STATEMENT 
(Continued) 
See Total Cost to 
Section Se30, 
In Text Project Funding FY 80 FY 81 FY 82 FY 831983 
25. Stonewall New Work 
Jackson Lake Approp. 12,300,000 15,505,000 20,455,000 21,500,000 88,010,200 
WV Cost 11,234,875 15,585,738 20,917,297 20,229,662 85,736,726 
26. Tionesta Lake New Work 
Ohio River Approp. 7,000 18,701 350,000 278,000 7,824,706" 
Basin, PA Cost 187,586 25,377 106,733 436,326 7,528,81242 
Maint. 
Approp. 708,600 647,600 729,120 898,000 8,367,953"4 
Cost 721,146 676,637 698,626 785,005 8,207,329"4 
27. Union City New Work 
Dam, PA Approp. - - - - 14,559,800 
Cost - - - - 14,559,800 
Maint. 
Approp. 209,200 204,200 215,000 246,000 1,748,668 
Cost 211,746 197,002 209,590 244,224 1,729,842 
28. Woodcock Creek New Work 
Lake, PA Approp. 43,000 - 1,068,000 - 19,984,700"4 
Cost 36,588 6,061 583,988 313,216 19,813,553' 
Maint. 
Approp. 364,900 383,700 454,100 538,500 3,254,37147 
Cost 368,436 377,938 435,069 537,291 3,219,592' 
29. Youghiogheny New Work 
River Lake, Approp. -56,004 80,000 - 277,000 12,533,238" 
Ohio River Cost 233,521 263,134 18,679 27,096 12,232,342" 
Basin, PA and Maint. 
MD Approp. 937,100 1,004,200 1,239,100 1,527,500 11,448,189"' 
Cost 944,663 1,050,372 1,224,065 1,119,522 10,991,937" 
1. Includes $2,453,737 from emergency relief funds and 
$1,250,049 from public works funds. 
2. Includes $64,365 public works acceleration, executive 
funds (1963) and $191,400 provided from the Productive 
Employment Appropriations Act (PL 98-8) 1983 funds. 
3. Includes $64,365 public works acceleration, executive 
funds (1963) and $163,041 provided from the Productive 
Employment Appropriations Act (PL 98-8) 1983 funds. 
4. Includes $5,420,541 for new work for previous projects. 
5. Includes $22,549 public works acceleration, executive 
funds (1963), $742 for maintenance for previous project and 
$646,000 provided from the Productive Employment 
Appropriations Act (PL 98-8) 1983 funds. 
6. Includes $22,549 public works acceleration, executive 
funds (1963), $742 for maintenance for previous project and 
$77,745 provided from the Productive Employment 
Appropriations Act (PL 98-8) 1983 funds. 
7. Includes $1,999,995 emergency relief funds $10,000,000 
public works funds, $246,000 Code 711 funds and $817,588 
Code 713 funds; excludes $402,998 contributed by local 
interest. 
8. Includes $1,999,995 emergency relief funds, $10,000,000 
public works funds, $233,755 Code 711 funds and $607,658 
Code 713 funds; excludes $214,000 contributed by local 
interest. 
9. Includes $115,000 provided from the Productive 
Employment Appropriations Act (PL 98-8) 1983 funds. 
10. Includes $67,060 provided from the Productive 
Employment Appropriations Act (PL 98-8) 1983 funds. 
11. Includes $33,423 from emergency relief funds. 
12. Excludes $180,485 for new work expended from 
contributed funds. 
13. Includes $305,000 provided from the Productive 
Employment Appropriations Act (PL 98-8) 1983 funds. 
14. Includes $25,568 provided from the Productive 
Employment Appropriations Act (PL 98-8) 1983 funds. 
15. Includes $1,542,500 Code 711, $809,700 Code 712 funds 
and $99,111 Code 713 funds; excludes $100,000 contributed 
by local interest. 
16. Includes $40,000 provided from the Productive 
Employment Appropriations Act (PL 98-8) 1983 funds. 
17. Includes $5,351 from emergency relief funds and 
$332,000 Code 711 funds. 
18. Includes $5,351 from emergency relief funds and 
$320,532 Code 711 funds. 
19. Includes $63,788 from emergency relief funds and 
$163,634 Code 711 funds. 
20. Includes $63,788 from emergency relief funds and 
$131,175 Code 711 funds. 
21. Includes $45,000 provided from the Productive 
Employment Appropriations Act (PL 98-8) 1983 funds. 
22. Includes $44,250 provided from the Productive 
Employment Appropriations Act (PL 98-8) 1983 funds. 
23. Includes $156,812 Code 711 funds. 
24. Includes $322,000 provided from the Productive 
Employment Appropriations Act (PL 98-8) 1983 funds. 
25. Includes $108,433 provided from the Productive 
Employment Appropriations Act (PL 98-8) 1983 funds. 
26. Includes $2,791 from emergency relief funds, $14,622 
Code 711 funds and $568,265 Code 713 funds; excludes 
$389,370 contributed by local interest. 
27. Includes $7,339 from emergency relief funds and 
$279,669 Code 711 funds. 
28. Includes $7,339 from emergency relief funds and 
$274,258 Code 711 funds. 
29. Includes $256,000 provided from the Productive 
Employment Appropriations Act (PL 98-8) 1983 funds. 
30. Includes $57,477 provided from the Productive 
Employment Appropriations Act (PL 98-8) 1983 funds. 
31. Includes $25,671 emergency relief funds, $132,221 Code 
711 funds and $751,247 Code 713 funds; excludes $456,611 
contributed by local interests. 
26-16

PITTSBURGH, PA., DISTRICT 
TABLE 26-A 
(Continued) 
COST AND FINANCIAL STATEMENT 
32. Includes $25,671 emergency relief funds, $132,221 Code 
711 funds and $586,858 Code 713 funds; excludes $361,169 
contributed by local interests. 
33. Includes $74,900 Code 711 funds; excludes 
$4,311,267.20 for new work contributed by local interest. 
34. Includes $315,500 provided from the Productive 
Employment Appropriations Act (PL 98-8) 1983 funds. 
35. Includes $15,476 provided from the Productive 
Employment Appropriations Act (PL 98-8) 1983 funds. 
36. Includes $122,729 Code 711 funds and $94,900 Code 713 
funds. 
37. Includes $8,914 from emergency relief funds. 
38. Includes $1,730,100 Code 711 funds and $1,618,300 
Code 713 funds. 
39. Includes $165,000 provided from the Productive 
Employment Appropriations Act (PL 98-8) 1983 funds. 
40. Includes $151,718 provided from the Productive 
Employment Appropriations Act (PL 98-8)1983 funds. 
41. Includes $2,335,405 Code 711 funds, $275,900 Code 712 
funds, $24,201 emergency relief funds and $278,000 provided 
from the Productive Employment Appropriations Act 
(PL 98-8) 1983 funds. 
42. Includes $2,039,510 Code 711 funds, $275,900 Code 712 
funds, $24,201 emergency relief funds and $13,659 provided 
from the Productive Employment Appropriations Act 
(PL 98-8) 1983 funds. 
43. Includes $190,000 provided from the Productive 
Employment Appropriations Act (PL 98-8) 1983 funds. 
44. Includes $72,463 provided from the Productive 
Employment Appropriations Act (PL 98-8) 1983 funds. 
45. Includes $1,111,000 Code 711 funds. 
46. Includes $939,853 Code 711 funds. 
47. Includes $85,000 provided from the Productive 
Employment Appropriations Act (PL 98-8) 1983 funds. 
48. Includes $83,590 provided from the Productive 
Employment Appropriations Act (PL 98-8) 1983 funds. 
49. Includes $2,858,334 Code 711 funds and $288,000 
provided from the Productive Employment Appropriations 
Act (PL 98-8) 1983 funds. 
50. Includes $2,557,409 Code 711 funds and $17,103 
provided from the Productive Employment Appropriations 
Act (PL 98-8) 1983 funds. 
51. Includes $479,000 provided from the Productive 
Employment Appropriations Act (PL 98-8) 1983 funds. 
52. Includes $88,618 provided from the Productive 
Employment Appropriations Act (PL 98-8) 1983 funds. 
26-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 26-B AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
1. 
Aug 5, 1886 
Jun 3, 1896 
Jul 25, 1912 
Jul 3, 1930 
Aug 30, 19351 
Aug 30, 19351 
Jun 26, 19342 
3. 
Mar 3, 1899 
Jun 13, 1902 
Mar 3, 1905 
Mar 3, 1905 
Mar 2, 1907 
Mar 4, 1913 
Sep 22, 1922 
Jul 3, 1930 
Jan 31, 1931' 
Jun 26, 1934' 
3. May 17, 1950 
ALLEGHENY RIVER, PA. (See Section 1 of Text) 
For lock and dam 1. (Fixed dam contemplated. Sep 29, 1891 Annual Report 1886, p. 1545, 
Secretary of War authorized change to a movable dam.) Annual Report 1891, p. 2366 
For locks and dams 2 and 3. H. Doc. 204, 54th Cong., 
1st sess., and Annual Report 
1896, p. 2212 
For locks and dams 4 to 8, inclusive. H. Doc. 540, 62d Cong., 
2d sess. 
For a depth of 9 feet in the lower 61 miles. H. Doc. 356, 71st Cong., 
2d sess. 
Replace lock and dam 1 by a dredged channel, 9 feet deep and Rivers and Harbors 
200 feet wide up to lock 2, and construct new locks and Committee, Doc. 16, 
dams 2 and 3, to replace existing locks and dams 2 and 3. 72d Cong., 1st sess. 
Construct lock and dam 9, raising crest of dam 8, and H. Doc. 721, 71st Cong., 
dredging a navigable channel to head of pool 8. 3d sess., and Rivers and 
Harbors Committee, Doc. 27, 
73d Cong., 2d sess. 
Operation and care of locks and dams provided for with funds 
from War Department appropriation for rivers and harbors. 
MONONGAHELA RIVER, PA AND WV 
Enlarge and improve lock and dam 6; additional works at Annual Report 1897, p. 2423 
lock 3; new repair steamer and new dredge boat with 
equipment; all at an estimated cost of $185,556. 
Rebuild lock and dam 2 at estimated cost of $655,961. Annual Report 1909, p. 1756 
(Estimate increased in 1910 to $698,961.) 
Acquisition of land and additional improvements at 5 and 6 Annual Report 1904, p. 460 
at a cost of $7,850. 
Rebuild lock and dam 3 at estimated cost of $589,196. H. Doc. 209, 58th Cong., 
2d sess. 
Reconstruct lock and dam 5 at estimated cost of $756,042. H. Doc. 209, 58th Cong., 
2d sess. 
Reconstruct lock and dam 6 at estimated cost of $356,400. H. Doc. 1217, 62d Cong., 
(Estimate increased in 1916 to $418,860.) 3d sess. 
Additional improvements at estimated cost as follows: H. Doc. 288, 67th Cong., 
Guide walls and guard walls, 1 to 6, $1,255,130; 2d sess. 
Lengthen land chamber of lock 3 to 720 feet, $787,722; 
New chamber (360 feet long), lock 4, $699,786; 
Lock and dam 7, $1,161,241; Lock and dam 8, $1,165,758; 
Lock and dam 7 (second chamber), $419,126; 
Lock and dam 8 (second chamber), $504,465; 
Reconstruct dam 4, $397,211; Marine ways, repair plant, 
office and warehouse, $250,000, for a total of $6,640,439. 
Construct new locks and dam 2.5 miles below existing Rivers and Harbors 
structure, at estimated cost of $2,175,000 in lieu of work Committee, Doc 22, 
authorized at old lock and dam 4. 70th Cong., 2d sess. 
Chief of Engineers authorized to locate new locks and dam 4 
above existing structure and on such site as they may deem 
most desirable. 
Operation and care of locks and dams provided for with funds 
from War Department appropriations for rivers and harbors. 
Modification of existing project as follows: S. Doc. 100, 81st Cong., 
Provide 2 new locks and dams similar to Morgantown lock 1st sess. 
and dam to replace existing locks and dams 12 to 15, inclusive. 
Provide a movable crest on existing dam 8 to raise existing 
pool-full elevation 4 feet. 
Provide a navigation channel of 300-foot minimum bottom 
width and a 9-foot project depth above lock and dam 8. 
Provide an extension of navigable channel of upper 
Monongahela River, into lower Tygart River for 2.1 miles at a 
maximum bottom width of 200 feet and a 9-foot project depth. 
26-18

PITTSBURGH, PA., DISTRICT 
TABLE 26-B 
(Continued) 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
9. 
11. 
12. 
14. 
15. 
16. 
5. 
26-19 
Jan 11, 1934 
Aug 30, 1935 
Jun 28, 1938 
Jun 28, 1938 
Jun 28, 1938 
Jun 28, 1938 
Dec 22, 1944 
as amended 
Jun 22, 1936 
amended by 
Jun. 28, 1938 
Dec 22, 1944 
as amended 
Jun 22, 1936 
amended by 
Jun. 28, 1938 
Dec 22, 1944 
as amended 
Jun 28, 1938 
Dec 22, 1944 
as amended 
TYGART RIVER LAKE, WV 
Construction of a dam and reservior for low water regulation H. Doc. 1792, 64th Cong. 
and flood control 2nd Sess. 
H. Doc. 106, 76th Cong. 
1st Sess. 
ELKINS, WV 
For construction of local flood protection projects. H. Doc. 306, 74th Cong. 
1st Sess. 
FCC Doc. No. 1, 75th Cong. 
1st Sess. 
JOHNSTOWN, PA 
For construction of local flood protection projects. H. Doc. 306, 74th Cong. 
1st Sess. 
FCC Doc. No. 1, 75th Cong. 
1st Sess. 
PUNXSUTAWNEY, OHIO RIVER BASIN, PA 
For construction of local flood protection projects. H. Doc. 306, 74th Cong. 
1st Sess. 
FCC Doc. No. 1, 75th Cong. 
1st Sess. 
BERLIN LAKE, OHIO RIVER BASIN, OH 
Construction of a dam and reservoir for flood control and low H. Doc. 306, 74th Cong. 
water regulation. 1st Sess. 
FCC Doc. No. 1, 75th Cong. 
1st Sess. 
Construction, operation & maintenances of recreation facilities. Sec. 4, Flood Control Act 
of 1944 
CONEMAUGH RIVER LAKE, OHIO RIVER BASIN, PA 
Construction of a dam and reservoir for flood control. H. Doc. 306, 74th Cong. 
slet Sess. 
FCC Doc. No. 1, 75th Cong. 
1st Sess. 
Construction, operation & maintenance of recreation facilities. Sec. 4, Flood Control Act 
of 1944 
CROOKED CREEK LAKE, OHIO RIVER BASIN, PA 
Construction of a dam and reservoir for flood control. H. Doc. 306, 74th Cong. 
slet Sess. 
FCC Doc. No. 1, 75th Cong. 
1st Sess. 
Construction, operation & maintenance of recreation facilities. Sec. 4, Flood Control Act 
of 1944 
EAST BRANCH CLARION RIVER LAKE, 
OHIO RIVER BASIN, PA 
Construction of a dam and reservoir for flood control and low H. Doc. 306, 74th Cong. 
water regulation. 1st Sess. 
FCC Doc. No. 1, 75th Cong. 
1st Sess. 
Construction, operation & maintenance of recreation facilities. Sec. 4; Flood Control Act. 
of 1944 
17.

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 26-B 
(Continued) 
AUTHORIZING LEGISLATION' 
See Date 
Section Authoridung 
in Text Act Project and Work Authorized Documents 
Jun 22, 1986 
amended by 
Jun 28, 1988 
modified by 
Aug 18, 1941 
Dec 22, 1944 
as amended 
Jun 22, 1986 
amended by 
Jun 28, 1988 
Dec 22, 1944 
as amended 
Jun 22, 1986 
amended by 
Jun 28, 1938 
Dec 22, 1944 
as amended 
KINZUA DAM AND ALLEGHENY RESERVOIR, 
OHIO RIVER BASIN, PA AND NY 
Construction of a dam and reservoir for flood control and low 
water regulation and recreation. 
Construction of a dam and reservoir for flood control, pollution 
abatement, low water regulation and recreation. 
Construction, operation & maintenance of recreation facilities. 
LOYALHANNA LAKE, OHIO RIVER BASIN, PA 
Construction of a dam and reservoir for flood control. 
Construction, operation & maintenance of recreation facilities. 
MAHONING CREEK LAKE, OHIO RIVER BASIN, PA 
Construction of a dam and reservoir for flood control. 
Construction, operation & maintenance of recreation facilities. 
H. Doc. 306, 74th Cong.. 
1st Sess. 
FCC Doc. No. 1, 75th Cong. 
1st Sess. 
H. Doc. 300, 76th Cong. 
1st Sess. 
Sec. 4, Flood Control Act 
of 1944 
H. Doc. 306, 74th Cong. 
1st Sess. 
FCC Doc. No. 1, 75th Cong. 
1st Sess. 
Sec. 4, Flood Control Act 
of 1944 
H. Doc. 306, 74th Cong. 
slet Sess. 
FCC Doc. No. 1, 75th Cong. 
1st Sess. 
Sec. 4, Flood Control Act 
of 1944 
MICHAEL J. KIRWAN DAM AND RESERVOIR, OH 
Jul 3, 1958 Construction of a dam and reservoir for flood control, water 
supply, low water, regulation and recreation. 
Jul 14, 1960 To define cost-sharing arrangement for municipal & industrial 
water supply & water for pollution abatement purposes. 
Jun 28, 1988 
Dec 22, 1944 
as amended 
Aug 28, 1987 
Jun 28, 1938 
Aug 18, 1941 
Dec 22, 1944 
Jul 24, 1946 
May 17, 1950 
Dec 80, 19683 
Jun 18, 1965 
MOSQUITO CREEK LAKE, OHIO RIVER BASIN, OH 
Construction of a dam and reservoir for flood control, low water 
regulation and water supply storage. 
Construction, operation & maintenance of recreation facilities. 
H. Doc. 191, 85th Cong. 
1st Sess. 
Pub. Law 86-645 
H. Doc. 306, 74th Cong. 
1st Sess. 
FCC Doc. No. 1, 75th Cong. 
1st Sess. 
Sec. 4, Flood Control Act 
of 1944 
OHIO RIVER BASIN. Pittsburgh District 
Construct levees, floodwalls, and drainage structures for protection Flood Control Committee, 
of cities and towns in Ohio River Basin. Projects to be selected by Doc. 1, 75th Cong., 1st sess. 
Chief of Engineers with approval of Secretary of War at a cost not 
to exceed $24,877,000 for construction. 
Approved general comprehensive plan for flood control and other Flood Control Committee, 
rposm Ohio River Basin as may be advisable in discretion of Doc. 1, 75th Cong., slet sees. 
Sec ryof War and Chief of Engineers, and for initiation and 
partial acomphment of plan, authorized $75 million for 
reservoirs and $50,800,000 for local flood protection works. 
Additional $45 million for prosecution of comprehensive plan for H. Doc. 300, 76th Cong. 
Ohio River Basin. 1st Sees. 
Additional $70 million for further prosecution of comprehensive H. Doc. 762, 77th Cong., 
pla-nr bfotra Oybhiao sRiinvser. Basin, including additional projects in 2d sess. 
Additional $125 million for further prosecution of comprehensive H. Doc. 506, 78th Cong., 
plan Including additional projects mitnr ibutary basins. 1st sess. 
Additional $100 million for prosecution of comprehensive plan for S. Doc. 20, 81st Cong. 
Ohio River Basin. 1st Sess. 
Additional $150 million for further prosecution of comprehensive Public Law 88-253, 
plan for flood control and other purposes in Ohio River Basin. 88th Cong., 1st sess. 
Additional $89 million for further prosecution of comprehensive H. Doc., 6755, 89th Cong., 
plan for Ohio River Basin. 1st sess. 
26-20 
18. 
19. 
20. 
21. 
22. 
28.

PITTSBURGH, PA., DISTRICT 
TABLE 26-B AUTHORIZING LEGISLATION 
(Continued) 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
May 12, 1967 
Aug 13, 1968 
Jun 19, 1970 
Mar 7, 1974 
Oct 22, 1976 
Jun 28, 1938 
Dec 22, 1944 
as amended 
Nov 7, 1966 
Jun 22, 1936 
amended by 
Jun 28, 1938 
Additional $38 million for further prosecution of comprehensive Public Law 90-17, 
plan for Ohio River Basin. 90th Cong., e1sste ss. 
Additional $35 million for further prosecution of comprehensive Public Law 90483, 
plan for Ohio River Basin. 90th Cong., 2d sess. 
Additional $69 million for further prosecution of comprehensive H. Doc. 15166, 91st Cong., 
plan for Ohio River Basin. 2d sess. 
Additional $120 million for further prosecution of comprehensive H. Doc. 10203, 93rd Cong., 
plan for Ohio River Basin. River Basin Monetary 
Authorization Act of 1974. 
Authorized phase I design memorandum stage of advanced Water Resources Development 
engineering and design of the project for abatement of acid mine Act of 1976; Public Law 
drainage in the Clarion River Basin, Pa. 94-587, Sec. 101(a). 
SHENANGO RIVER IAKE, OHIO RIVER BASIN, PA AND OH 
Construction of a dam and reservoir for flood control, low water H. Doc. 306, 74th Cong. 
regulation and recreation. 1st Sees. 
FCC Doc. No. 1, 75th Cong. 
1st Sess. 
Construction, operation & maintenance of recreation facilities. Sec. 4, Flood Control Act 
of 1944 
STONEWALL JACKSON LAKE, WV 
Construction of a dam and reservoir for flood control, water supply, S. Doc. 109, 89th Cong. 
water quality control, area redevelopment and recreation. 2nd Sess. 
TIONESTA LAKE, OHIO RIVER BASIN, PA 
Construction of a dam and reservoir for flood control and low 
water regulation. 
Dec 22, 1944 Construction, operation & maintenance of recreation facilities. 
as amended 
Oct 23, 1962 
Oct 23, 1962 
Jun 28, 1938 
Dec 22, 1944 
as amended 
UNION CITY DAM, PA 
Construction of a dam and reservoir for flood control 
WOODCOCK CREEK LAKE, PA 
Construction of a dam and reservoir for flood control, recreation 
and storage for water quality controL 
YOUGHIOGHENY RIVER LAKE, OHIO RIVER BASIN, 
PA AND MD 
Construction of a dam and reservoir for flood control, low-flow 
augmentation, and pollution abatement purposes. 
Construction, operation & maintenance of recreation facilities. 
H. Doc. 306, 74th Cong. 
1st Sess. 
FCC Doc. No. 1, 75th Cong. 
1st Sess. 
Sec. 4, Flood Control Act 
of 1944 
S. Doc. 95, 87th Cong. 
2nd Sees. 
S. Doc. 95, 87th Cong. 
2nd Sess. 
H. Doc. 306, 74th Cong. 
1st Sess. 
FCC Doc. No. 1, 75th Cong. 
1st Sess. 
Sec. 4, Flood Control Act 
of 1944 
1. Included in the Emergency Relief Administration program 
April 8, 1935. 
2. Permanent Appropriations Repeal Act. 
3. Public Res. 117, 71st Cong., 3d Sees. 
26-21 
25. 
26. 
7. 
28. 
29.

TABLE 26-C 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
OTHER AUTHORIZED NAVIGATION PROJECTS 
(See Section 6 of Text) 
For Last Cost to September 30, 1983 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Allegheny River, PA, open-channel work Completed 1934 197,000 133,940 
Beaver and Mahoning Rivers, PA and 
OH' * Inactive 1938 - - 
Buckhannon River, WV2 8 Completed 1893 5,500 - 
Cheat River, WV2 S Completed 1895 12,997 - 
Pittsburgh Harbor, PA Completed 1922 110,663 81,613 
Youghiogheny River, PA and MD Inactive 1971 47,195' 185,6685 
1. January 23, 1939, Chief of Engineers recommended 
constructing a waterway from Ohio River through Beaver, 
Mahoning, and Grand River Valleys to Lake Erie (H. Doc. 
178, 76th Cong., 1st Sess.) 
2. Abandonment recommended in H. Doc. 467, 69th Cong., 
1st Sess. 
3. No Commerce reported. 
4. Previous project data. 
5. Includes $1,700 expended under previous project. 
6. Eligible for deauthorization. 
26-22

PITTSBURGH, PA., DISTRICT 
TABLE 26-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(All Projects Not Specifically Identified in Text) 
For Last Cost to September 30, 1983 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Allegany, NY, unit I (Allegheny River) Deferred - 4,100 - 
Allegany, NY, unit II (Five Mile Creek Area) Deferred 1975 64,851 - 
Amsterdam, OH' Completed 1964 183,072 - 
Benwood, WV2 Deferred 1954 81,028 - 
Big Run, PA' Completed 1965 364,208 - 
Black Fork at Hendricks, WV' Completed 1972 6,800 - 
Brackenridge, Tarentum and Natrona, PA Inactive - - - 
Bradford, PA Completed 1962 7,601,763 - 
Brookville, PA Completed 1963 964,976 - 
Buckhannon, WV Completed 1972 1,568,661 - 
Burgettstown, PA' Completed - 83,129 - 
Butler, PA Completed 1970 1,556,181 - 
Dubois, PA Completed 1979 4,464,607 - 
Eagle Creek Reservoir, OH2 Inactive - 100,000 - 
Empire-Stratton, OH 2 Inactive - 33,031 - 
Friendsville, MD' Completed - 41,529 - 
Granville, PA' Completed - 75,908 - 
Johnsonburg, PA Completed 1958 674,664 - 
Kittanning, PA, part I Completed 1949 130,317 - 
Latrobe, PA Completed 1951 207,659 - 
Latrobe, PA Completed 1970 2,556,652 - 
Leetonia, OH' Completed - 89,299 - 
Leetsdale, PA Inactive - - - 
Martins Ferry, OH 2 Inactive 1941 25,164 - 
Moundsville, WV2 Inactive - - 
Muddy Creek Dam, PA4 Inactive 1977 402,459 - 
Neville Island, PA Inactive - - - 
New Kensington and Parnassus, PA Inactive - - - 
Oakdale, PA' Inactive - 14,127 - 
Oil City, PA' Completed - 43,595 - 
Olean, NY Completed 1954 3,217,531 - 
Portage, PA4 Completed 1965 150,386 - 
Portville, NY Completed 1954 2,070,484 - 
Powhatan Point, OH 2 Inactive - - - 
Proctor, WV2 Inactive - - - 
Reynoldsville, PA Completed 1959 385,494 - 
Ridgway, PA (Elk Creek) Completed 1964 628,888 - 
Ridgway and vicinity, PA (on Clarion River)' 4 Active 1979 132,464 - 
Rochester, PA Inactive - - - 
Rouseville, PA' Inactive - 1,642 - 
Rowlesburg Lake, WV' Inactive 1977 2,857,575 - 
Salamanca, NY Completed 1972 2,880,535 - 
Slovan, PA' Completed - 57,811 - 
Sykesville, PA' Completed - 184,246 - 
Tarentum, PA' Completed 1964 136,591 - 
Tenmile Creek at Marianna, PA' 6 Completed 1981 1,554,428 - 
Turtle Creek, PA Completed 1972 15,350,552 - 
Wallace, WV' g Inactive - 11,035 - 
Warwood, WV2 Inactive - - - 
Washington, PA Completed 1964 789,093 - 
Wellsville, OH, Sec. I Completed 1956 483,910 - 
Wellsville, OH, Sec. II Completed 1956 157,633 - 
Weston Mills, Olean, NY' ' Active - ! 50,100 - 
Weston Mills, Portville, NY' ' Active - I 52,100 - 
Wheeling, WV (North Wheeling)' Inactive - - - 
Wheeling, WV (Wheeling Island)2 Inactive - 21,700 - 
Wheeling, WV' Inactive 1954 189,067 - 
Wilmore, PA4 
6 Completed - 96,853 - 
Woodlands, WV' Inactive - 
Youngstown, OH Completed 1976 3,621,134 - 
1. Authorized by Chief of Engineers. 3. Lacks local support. 
2. Eligible for deauthorization. 4. No longer economically justified. 
26-23

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 26-G DEAUTHORIZED PROJECTS 
For Last 
Full Report Federal Contributed 
See Annual Date Funds Funds 
Project Report For Deauthorized Expended Expended 
Adena, OH (Short Creek) - Aug 5, 1977 13,452 - 
Bellaire, OH - May 6, 1981 76,487" - 
Brilliant, OH - Aug 5, 1977 - - 
Brockway, PA (Allegheny River Basin) - Aug 5, 1977 194 - 
Buckhannon, WV' - Feb 20, 1951 37,488 - 
Clarington, OH - Aug 5, 1977 - - 
Coraopolis, PA - Aug 5, 1977 - - 
Dillonvale, OH (Short Creek) - Aug 5, 1977 16,884 - 
Follansbee, WV - Aug 5, 1977 - - 
Freeport, PA (Allegheny River) - Aug 5, 1977 - - 
Industry, PA - Aug 5, 1977 - - 
Kittanning, PA, part II (Allegheny River) - Nov 6, 1977 - - 
Lake Chautaugua and Chadakoin River, NY' 1956 Mar 2, 1970 190,722 - 
Lake Erie,-Ohio Canal, OH and PA 1972 May 6, 1981 1,342,000 - 
McKees Rocks, PA - Oct 3, 1978 - - 
Mingo Junction, OH - Aug 5, 1977 - - 
New Cumberland, WV - Aug 5, 1977 - - 
Pittsburgh, PA (Golden Triangle) - Oct 3, 1978 - - 
Pittsburgh, PA (North Side) - Oct 3, 1978 - - 
Pittsburgh, PA (The Strip) - Oct 3, 1978 - - 
Redbank Creek Lake, PA - Aug 5, 1977 156,337 - 
St. Marys, PA (Allegheny River Basin) - Aug 5, 1977 13,529 Smith Ferry, PA - - Aug 5, 1977 - - 
Uniontown, PA (Monongahela River Basin) 1956 Oct 3, 1978 - - 
Wellsburg, WV - Aug 5, 1977 6,387 - 
West Bridgewater, PA - Aug 5, 1977 - - 
Wilcox, PA - Mar 5, 1955 16,761 - 
1. Local interests failed to meet requirements of cooperation, 
authority for project expired Feb 20, 1951. 
2. Local interests failed to meet requirements of cooperation, 
authority for project expired Mar 2, 1970. 
3. Local interests failed to meet requirements of cooperation, 
authority for project expired Mar 5, 1955. 
26.24

TABLE 26-H ALLEGHENY RIVER, PA.: LOCKS AND DAMS 
(See Section 1 of Text) 
Dimensions 
Upper 
Avail- Normal Depths on Miter 
Width able Lift at Pool Sills at Normal Character of Type of Year 
of Length Normal Elevation Pool Level' Foundation Construction Per- Opened 
Miles Chamin- to Full Pool (feet, cet to 
Above bher Width Level mean sea Lower Upper Kind of Com- Navi- 
No. Mouth Nearest Town (feet) (feet) (feet) level) (feet) (feet) Lock Dam Dam Lock Dam plete gation Actual Cao 
2 6.7 Aspinwall, PA 56 360 11.0 721.0 12.0 10.9 Rock Rock Fixed Concrete Co 100 1934 $ 1,763,48 
3 14.5 Cheswick, PA 56 360 13.5 734.5 10.8 11.8 Rock Pile-rock Fixed Concrete Concrete 100 1934' 1,875,66 
4 24.2 Natrona, PA 56 360 10.5 745.0 10.0 8.5 Rock Rock Fixed Concrete Concrete 100 1927 1,707,69 
5 30.4 Freeport, PA 56 360 11.8 756.8 10.5 10.3 Piling Crib-Pile Fixed Concrete Concrete 100 1927 1,940,53 
6 36.3 Clinton, PA 56 360 12.2 769.0 10.6 10.8 Rock Crib-Pile Fixed Concrete Concrete 100 1928 1,523,95 
7 45.7 Kittanning, PA 56 360 13.1 782.1 9.8 10.9 Piling Steel Sheet Fixed Concrete Concrete 100 1930 1,460,00 
Piling 
8 52.6 Templeton, PA 56 360 17.9 800.0 10.4 13.8 Rock Rock Fixed Concrete Concrete 100 1931 2,848,92 
9 62.2 Rimer, PA 56 360 22.0 822.0 10.5 11.3 Rock Rock Fixed Concrete Concrete 100 1938 2,510,37 
Total $15,630,63 
Abandoned lock and dam 1 591,18 
Abandoned lock and dam 2 544,92 
Abandoned lock and dam 3310,10 
Demolishing old dam 1 26,00 
Dredging channel 1,055,00 
Total $18,157,86 
1. All depths as shown are on guard sills and 
are controlling depth. 
t
5
5
0
7
9
0 
3
7 M 
P3 ,F 
1 d 
3
0 
2. Dates shown represent replacem t structures.

TABLE 26.I MONONGAHELA RIVER, PA. AND W. VA.: LOCKS AND DAMS 
(See Section 3 of Text) 
Dhaealm 
Upper 
Avail- Normal s on Miter 
Width able Lift at Pool Sills at Normal Character of Type of Year 
of lngth Normal Elevation Pool evel' Foundation Construction Pe Opened 
Miles Chasm- to Full Pool (feet, cent to 
Above her Width Level mean sea l wer Upper Kind of Com- Navi- 
No. Mouth Nearest Town (feet) (feet) (feet) level) (feet) (feet) Lack Dam Dam lack Dam plete gation Actual Cos 
2 11.2 Braddock, PA 56 360 8.7 718.7 16.0 15.95 Rock Crib pile Fixed Concrete Concrete 100 19532 $17,872,21 
110 720 
3 23.8 Elizabeth, PA 56* 360 8.2 726.9 16.0 15.95 Rock Crib Pile Fixed Concrete Concrete 100 1953 17,658,53 
720 
4 41.5 Monessen, PA 56' 360 16.6 743.5 10.7 20.0 Piles Piles Movable Concrete Concrete 100 19322 17,254,07 
720 
S 61.2 Maxwell locks and dam. 842 720 19.5 763.0 15.0 20.5 Rock Rock Movable Concrete Concrete 100 1964 30,110,88 
Maxwell, PA 
S 82.2 Grays Landing lock 84 720 15.0 778.0 15.0 26.0 Rock Rock Fixed Concrete Concrete - - 802,99 
and dam, Grays 
Landing, PA 
7 85.0 Greensboro, PA 56 360 15.0 778.0 10.0 10.5 Rock Rock Fixed Concrete Concrete 100 1925' 2,639,80 
8 90.8 Point Marion, PA 56 360 19.0 797.0 10.0 14.5 Rock Rock Movable Concrete Concrete 100 1925' 6,027,21 
- 102.0 Morgantown lock and 84 600 17.0 814.0 14.5 17.8 Rock Rock Movable Concrete Concrete 100 1950 8,778,00 
dam, Morgantown, 
WV 
108.0 Hildebrand lock and 84 600 21.0 835.0 15.0 14.0 Rock Rock Movable Concrete Concrete 100 1959 12,506,82 
dam, 6 miles above 
Morgantown, WV 
- 115.4 Opekiska lock and dam, 84 600 22.0 857.0 14.0 17.75 Rock Rock Movable Concrete Concrete 100 1964 25,179,62 
13.4 miles above 
Morgantown, WV 
Marine ways, etc. 250,00 
Abandoned lock and dam 1 1,019,90 
Abandoned lock and dam 4 780,81 
Abandoned lock and dam 5 1,074,81 
Abandoned lock and dam 6 770,44 
Abandoned lock and dam 7 213,77 
Abandoned lock and dam 8 245,90 
Abandoned lock and dam 9 191,00 
Abandoned lock and dam 10 210,44 
Abandoned lock and dam 11227,66 
Abandoned lock and dam 12 200,55 
Abandoned lock and dam 13 190,69 
Abandoned lock and dam 14 210,12 
Abandoned lock and dam 15 175,82 
Dredging 5878 
Total 145,180,04 
t 
2' 
8 8 
156 
95 
59 
45 
94 
0' 
9' 
2' 
0' 
7' 
6' 
2' 
9' 
6' 
0' 
0
5' 
8' 
0' 
1' 
7' 
9' 
96 
85 
1. All depths as shown are on guard sills and are controlling depths. 
2. Dates shown for locks and dams No. 2 to 8, inclusive, represent 
reconstruction. 
3. 2 Chambers 
4. Includes $3,322,057 for raising crest of dam, (1958-9), $2,086,438 for 
original reconstruction (1923-1926) and $618,724 AE&D costs for 
replacement of lock. 
5. Actual cost; may include estimated costs which have been 
footnoted as necessary. 
6. Includes $2,173,767 for original reconstruction (1931-2), and 
$15,080,304 for reconstruction of dam (1977). 
7. Includes $16,967,114 for reconstruction of locks. 
8. Includes estimated $15,977,000 for major rehabilitation. 
9. AE&D costs for proposed lock. 
0
OE 
Cu

PITTSBURGH, PA., DISTRICT 
TABLE 26-J MONONGAHELA RIVER, PA AND WV: 
TOTAL COSTS OF EXISTING PROJECT TO END OF FISCAL YEAR 
(See Section 3 of Text) 
Operation and 
Maintenance, 
Funds New Work General Total 
Regular $139,593,011" $97,140,4612 $236,733,472'1 
Maintenance and operation - 380,923 380,923 
Public Works acceleration, executive (1963) - 22,549 22,549 
Total $139,593,011" $97,543,9332 $237,136,944'1 3 
1. Excludes $5,420,541 for new work for previous projects. 2. Excludes $20,446,587 expended between July 7, 1897 
and June 30, 1937, on operation and care of works of 
improvement under provisions of permanent appropriation foz 
such purposes and excludes $742 for maintenance of previous 
projects. 
3. Includes $15,810,506 for major rehabilitation. 
TABLE 26-K OHIO RIVER BASIN (PITTSBURGH DISTRICT): 
LOCAL PROTECTION PROJECTS 
(See Section 23 of Text) 
Estimated Cost' 
Type of 
Location' Protection Federal Non-Federal Total 
Allegany, NY, unit I (Allegheny River)2 
Allegany, NY, unit II (Five Mile Creek area)2 
Benwood, W V2 
7 16 
Brackenridge, Tarentum and Natrona, PA 
(Allegheny (RiverP) 
Elkins, W V (Monongahela River Basin)' 5 
Empire-Stratton, OH" 16 
Johnsonburg, PA (Allegheny River Basin)2 ' 
Johnstown, PA (Allegheny River BasinP '5 
Kittanning, PA, part I (Allegheny River) 5 
Lake Chautauqua and Chadakoin River, NY 
(Allegheny River Basin) 
Latrobe, PA (Allegheny River Basin) " 
Leetsdale, PA' 
Martins Ferry, OH' 6 6 
Moundsville, WV' 16 
Neville Island, PA' 
New Kensington and Parnassus, PA 
(Allegheny River) 
Olean, NY (Allegheny RiverP)Z 
Portville, NY (Allegheny River) " 
Powhatan Point, OH "' 
Proctor, WV' 16 
Punxsutawney, PA (Allegheny River Basin)' 
Ridgway, PA (Allegheny River BasinP)5 
Rochester, PA' 
Warwood, WVs ' 
Wellsville, OH, sec. I " 
Wellsville, OH, sec. I I' s 
Wheeling, WV' 7 6 
Levee 
Channel and levee 
Wall 
Wall 
Channel diversion 
Internal drainage 
facilities 
Wall 
Channel 
Wall 
Channel 
Channel 
Levee 
Wall and levee 
Wall and levee 
Wall and levee 
Wall 
Levee 
Levee 
Levee 
Levee 
Channel and levee 
Channel 
Wall 
Wall 
Wall and levee 
Wall and levee 
Wall and levee 
697,000 
980,000 
8,500,000 
11,800,000 
1,772,627$ 
933,000 
674,6648 
8,865,388' 
130,3178 
6,640,000 
207,659' 
1,270,000 
8,630,000 
3,070,000 
3,210,000 
7,900,000 
3,217,531' 
2,070,484' 
4,720,000 
334,000 
3,586,107' 
628,888' 
3,350,000 
1,740,000 
483,910' 
157,633' 
19,700,000 
65,000 
133,000 
3,180,000 
3,080,000 
762,000"1 
1,113,000"1 
11,680,00010 
14,880,000 
40,000 1,812,627 
28,000 961,000"15 
130,000 804,664 
- 8,865,388s 
2,000 132,317 
1,310,000 7,950,000"11 
44,400 
141,000 
836,000 
605,000 
1,830,000 
148,000 
252,059 
1,411,000 
9,466,000 
3,675,000 
5,040,000 
8,048,000 
597,000 3,814,531 
353,000 2,423,484 
397,000 5,117,000 
121,000 455,000 
180,485' 3,766,592' 
72,000 700,888 
622,000 3,972,000 
376,000 2,116,000 
113,000 596,910 
- 157,633' 
3,460,000 23,160,000 � 
26-27

TABLE 26K 
(Continued) 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
OHIO RIVER BASIN (PITTSBURGH DISTRICT): 
LOCAL PROTECTION PROJECTS 
(See Section 21 of Text) 
Estimated Cost' 
Type of 
Location' Protection Federal Non-Federal Total 
Wheeling, WV (North Wheeling)' 6 Wall 11,700,000 2,700,000 14,400,000 
Wheeling, WV (Wheeling Island)' 16 Wall and levee 13,300,000 2,470,000 15,770,000 
Woodlands, WV' 16 Levee 206,000 28,000 234,000 
1. All projects are on the Ohio River unless otherwise 9. Latest cost estimate revision 1959. 
noted. 10. Latest cost estimate revision 1960. 
2. Also see "Other authorized flood control projects." 11. Latest cost estimate revision 1965. 
3. Actual cost. 12. Latest cost estimate revision 1966. 
4. Reported in detail in an individual report. 13. Latest cost estimate revision 1974. 
5. Completed. 14. Latest cost estimate revision 1977. 
6. Reported in detail in Annual Report for 1941. 15. Latest cost estimate revision 1978. 
7. Reported in detail in Annual Report for 1954. 16. Eligible for deauthorization. 
8. Latest cost estimate revision 1954 unless otherwise 
noted. 
TABLE 26.L OHIO RIVER BASIN (PITTSBURGH DISTRICT): RESERVOIRS 
(See Section 21 of Text) 
Total 
Estimated 
Tributary Basin and Reservoir Stream Cost 
Allegheny: 
Conemaugh River, PA1 Conemaugh River $ 46,016,400' 
Crooked Creek, PA' Crooked Creek 7,514,900 1s 
East Branch Clarion River, PA' Clarion River 9,759,600 1 5 
Kinzua Dam and Allegheny Reservoir, PA and NY' Allegheny River 112,549,200 ' 
Loyalhanna, PA' LoyalannaCreek 8,348,900 ' " 
Mahoning Creek, PA' Maho' Creek 7,529,300 ' ' 
Tionesta, PA' Tionesta Creek 8,047,100"1 
Union City, PA' French Creek 14,729,800 ' 
Woodcock Creek, PA' Woodcock Creek 20,684,700 '' 
Beaver. 
Berlin, OH' Mahoning River 9,266,400" 
Eagle Creek, OH' Eagle Creek 12,700,000 * 
Michael J. Kirwan, OH' Maning River 21,754,000 
Mosquito Creek, OH' Mosquito Creek 6,190,000" 
Shenango River, PA and OH' Shenango River 41,528,000 4 
Youghiogheny River, PA and MD' Youghiogheny River 13,920,30015 
1. Reported in detail in an individual report. 
2. Al see "Other authorized flood control projects." 
3. Latest cost estimate revision 1954. 
4. Latest cost estimate revision 1982. 
5. Latest cost estimate revision in 1983. 
6. Includes $2,800,000 cost estimate for Dam Rehabilitation 
plus $2,556,000 for total recreational and sanitary facilities to 
upgrade area and comply with sanitary codes. 
26-28

PITTSBURGH, PA., DISTRICT 
TABLE 26-M INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS 
(See Section 30 of Text) 
Project Dates of Inspection Project Dates of Inspection 
Amsterdam, OH October 1982 Leetonia, OH June 1983 
Big Run, PA July 1983 Oil City, PA April 1983 
Bradford, PA June 1983 Olean, NY September 1983 
Brookville, PA July 1983 Portage, PA August 1982 
Buckhannon, WV October 1983 Portville, NY September 1983 
B tstown-Slovan, PA March 1976 Reynoldsville, PA July 1983 
Butler, PA May 1983 Ridgway, PA April 1983 
Chartiers Creek, PA Salamanca, NY September 1983 
Cannonsburg-Houston Reach March 1976 Stonewood-Nutter Fort, 
James G. Fulton Reach October 1983 WV July 1983 
Colliers, WV October 1982 Sykesville, PA July 1983 
Dubois, PA September 1983 Tarentum, PA November 1976 
Eldred, PA June 1983 Turtle Creek, PA August 1983 
Friendsville, MD May 1983 Washington, PA March 1976 
Granville, PA March 1982 Wellsville, OH October 1979 
Johnsonburg, PA April 1983 Weston, WV October 1982 
Kittanming, PA Augus t 1983 Wilmore, PA August 1982 
Latrobe, PA May 1982 Youngstown, PA April 1983 
26-29

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 26-N FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION 
(See Section 32 of Text) 
Flood Control Activities pursuant to Section 205, 
Public Law 858, 80th Congress, as amended (preauthorization) 
Project/Study Identification Fiscal Year Costs 
Allegheny River, Oil City, PA (plans, specifications and construction) $620,143 
Catfish Creek, Washington Co., PA (preliminary project report 
and detailed project report) 54,736 
Clarion River, Ridgway, PA (construction) 106 
Girty's Run, Millvale, PA (construction) 19 
Root Creek, Bolivar, NY (construction) 102,047 
West Little Pine Creek, Etna, PA (detailed project report) 9,126 
Weston Mills, Olean, NY (preliminary project report) 15 
Weston Mills, Portville, NY (preliminary project report) 79 
Total cost for current fiscal year: T786,271 
Emergency Bank Protection - Section 14 of the 
1946 Flood Control Act, Public Law 526, 79th Congress 
Project/Study Identification Fiscal Year Costs 
Allegheny River, Wattersonville, PA (construction) $ 13,098 
Allegheny River, Tionesta, PA (reconnaissance report, 
plans, specifications and construction 30,081 
Mahoning River, Highway 139A, Trumbull Co., OH 
(reconnaissance report) 7,500 
Monongahela River, Newell Borough, PA (construction) 36 
Ohio River, Chester, WV (construction) 2,029 
Ohio River, McMechen, WV (plans and specifications) 1,871 
Plum Creek, Penn Hills, PA (reconnaissance report, plans 
specifications and construction) 18,506 
Roberto Clemente Park, PA (construction) 54,592 
Thompson Run, West Mifflin, PA (construction) 194 
Trout Run, Portage, PA (reconnaissance report, plans 
and specifications 18.012 
Total cost for current fiscal year: $145,919 
Streambank Erosion Control, Evaluation and 
Demonstration - Section 32, of the 1974 Water Resources 
Development Act, Public Law 251, 93rd Congress 
Ohio River Project/Study Identification Fiscal Year Costs Main Stem Demonstration Projects $-4,183 
Rehabilitation of Streambank Demonstration Projects, 
Ohio River 4.484 
Total cost for current fiscal year: 
Shoreline Erosion Control Demonstration - 
Section 54, of the 1974 Water Resources 
Development Act, Public Law 251, 93rd Congress 
No Expenditures 
this 
Activity Fiscal Year 
Architect/Engineer Contract for Preparation of Three Reports for the 
Purpose of Disseminating Information on the Section 54 Program. 
Three Guides to Low Cost Shore Protection for: 
1. Engineers and Contractors 
2. Local government officials 
3. Property owners 
26-30

ST. PAUL, MN DISTRICT* 
District comprises western Wisconsin, major 
portion of Minnesota, northern and eastern North 
Dakota, and small portions of northeastern South 
Dakota and northern and northeastern Iowa 
embracing drainage basins of Mississippi River and 
tributaries from its source to mile 614 above mouth of 
Ohio River; Red River of the North and tributaries; 
those streams north of Missouri River Basin in North 
Dakota; and U.S. waters of Lake of the Woods and its 
tributaries. That section of Mississippi River above 
mile 614 is included in report on Mississippi River 
between Missouri River and Minneapolis, Minnesota. 
IMPROVEMENTS 
Navigation Page 
1. Minnesota River, MN ................... 27-2 
2. Mississippi River between 
Missouri River and Minneapolis, MN .... 27-2 
3. Reservoirs at Headwaters of 
Mississippi River, MN .................. 27-2 
4. St. Croix River, MN & WI..............27-2 
5. Warroad Harbor and River, MN.........27-3 
Flood Control 
6. Bassett Creek, MN ..................... 27-3 
7. Big Stone Lake and Whetstone 
River, MN and SD ..................... 27-4 
8. Burlington Dam, Souris River, ND ...... 27-4 
9. Chaska, MN ............................ 27-5 
10. Devils Lake, ND........................27-5 
11. Eau Galle River, WI .................... 27-5 
12. Enderlin, Maple River, ND ............. 27-6 
13. Grafton, ND ............................ 27-6 
14. Homme Lake and Dam, ND ............ 27-7 
15. Irving Township, Jackson County, WI. . . 27-7 
16. Lac qui Parle Lake, Minnesota 
River, M N .............................. 27-7 
17. LaCrosse, W I ........................... 27-8 
18. La Farge Lake and channel 
improvement, WI.......................27-8 
19. Lake Ashtabula and Baldhill Dam, 
Sheyenne River, ND .................... 27-8 
20. Lake Darling, Souris River, ND ........ 27-9 
21. Lake Traverse and Bois de Sioux 
River, SD and MN ..................... 27-10 
22. Mankato and North Mankato, MN ...... 27-10 
23. Minot, ND .............................. 27-10 
24. Pembina River, ND.....................27-11 
25. Prairie du Chien, WI ................... 27-11 
26. Red Lake River at Huot, MN ........... 27-11 
27. Red Lake River at Red Lake Falls, MN .27-12 
28. Red Lake River, MN, including 
Clearwater River, MN .................. 27-12 
29. Red River of the North drainage 
basin, MN, SD & ND...................27-13 
30. Red River of the North at Halstad, MN .27-13 
31. Red River of the North at Oslo, MN .... 27-14 
32. Rochester, MN .......................... 27-14 
33. Roseau River, MN ...................... 27-14 
34. Shepard Road, Mississippi River, 
St. Paul, MN ........................... 27-15 
35. Sheyenne River, ND .................... 27-15 
36. State Road and Ebner Coulees, WI ...... 27-16 
37. Veteran's Memorial Levee, Mississippi 
River, Hastings, MN....................27-16 
38. Wild Rice River-South Branch and 
Felton Ditch, MN.......................27-17 
39. Winona, MN ............................ 27-17 
40. Inspection of completed flood 
control projects ......................... 27-18 
General Investigations 
41. Surveys.................................27-18 
42. Collection and study of basic data......27-18 
43. Advance engineering and design ....... 27-18 
44. Other work under special authority......27-18 
Tables 
Table 27-A 
Table 27-B 
Table 27-C 
Table 27-D 
Table 27-E 
Table 27-F 
Table 27-G 
Table 27-H 
Table 27-I 
Table 27-J 
Table 27-K 
Table 27-L 
Cost & Financial 
Statement......................27-19 
Authorizing Legislation ........ 27-22 
Other Authorized 
Navigation Projects ............ 27-23 
Not Applicable 
Other Authorized 
Flood Control Projects ......... 27-24 
Not Applicable 
Deauthorized Projects .......... 27-25 
Reservoirs at Headwaters 
of Mississippi River............27-26 
Navigation Work Under 
Special Authorization .......... 27-27 
Red River of the North 
Drainage Basin: Active 
Units in Comprehensive Basin 
Plan ........................... 27-27 
Inspection of Completed 
Flood Control Projects ......... 27-28 
Flood Control Work Under 
Special Authorization .......... 27-29 
27-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Navigation 
1. MINNESOTA RIVER, MN 
Location. Rises in Big Stone Lake, MN and SD, 
and flows southeasterly about 224 miles to Mankato, 
MN, thence northeasterly about 106 miles to join the 
Mississippi River opposite St. Paul, MN. (For general 
location see Geological Survey map of Minnesota.) 
Previous projects. For details see page 1890 of 
Annual Report for 1915, and page 1105 of Annual 
Report for 1938. 
Existing project. Provides 9-foot depth below flat 
pool level of Mississippi River lock and dam 2 from 
mouth to mile 14.7, one-half mile above the railway 
bridge at Savage, MN, and 4-foot depth from mile 
14.7 to 25.6 at Shakopee, MN. For details see page 
1018 of Annual Report for 1965. (See table 27-B for 
authorizing legislation.) 
Local cooperation. Fully complied with. See also 
page 1074 of Annual Report for 1967. 
Terminal facilities. There are privately owned 
terminals at miles 9, 13.1, 14.5, and two at mile 14.7. 
Operations and results during fiscal year. 
Maintenance: Condition surveys cost $-12,333. 
Dredging by contract cost $392,341. Snagging and 
clearing by hired labor cost $27,736 and dredging and 
berming cost $1,273. Engineering and administrative 
costs amounted to $10,022. 
Condition at end of fiscal year: Work on project for 
4-foot depth was completed in 1931. The United 
States owns 10 acres of land in fee 2 miles east of 
Savage, MN and easements on 123.08 acres of land. 
46.20 acres have been transferred from the Department 
of the Army and Department of the Air Force to 
the project. Navigation from mouth to Shakopee was 
practicable for drafts not in excess of 3 feet. A contract 
for work under 1958 authorization for a 9-foot 
channel started in May 1966 was terminated in January 
1967 when 56 percent complete. A channel dredging 
contract awarded in June 1967 was completed in 
August 1968. Total costs for existing project to 
September 30, 1983 were $3,764,778, of which 
$1,940,180 was for new work and $1,824,598 for maintenance. 
In addition, cost from contributed funds was 
$139,671 for dredging to 9-foot depth under provisions 
of section 4, River and Harbor Act of 1915, and 
$219,531 for work done for the State of Minnesota 
relative to modification of the project. 
2. MISSISSIPPI RIVER BETWEEN 
MISSOURI RIVER AND 
MINNEAPOLIS, MN 
For report on this improvement see chapter on 
Mississippi River between Missouri River and Minneapolis, 
Minnesota. 
3. RESERVOIRS AT HEADWATERS OF 
MISSISSIPPI RIVER, MN 
Location. Reservoirs are on the Mississippi River 
and several of its tributaries in Itasca, Beltrami, 
Hubbard, Aitkin, Cass and Crow Wing Counties, 
MN. (See table 27-H on reservoirs.) 
Previous projects. For details see page 1888 of 
Annual Report for 1915, and page 1098 of Annual 
Report for 1938. 
Existing project. Provides for reconstruction 
from timber to concrete at Winnibigoshish, Leech 
Lake, Pokegama, Sandy Lake and Pine River Dams, 
and construction of a concrete dam at Gull Lake. 
Pokegama was built on bedrock and the others on 
pile foundations. A portion of Leech Lake Dam from 
piers 26 to 39 was replaced with an earth fill. Constructed 
three dikes at Winnibigoshish, four at Pokegama, 
two at Sandy Lake, and 16 at Pine River. 
Sandy Lake Dam includes a lock 160 feet long, 30 feet 
wide, with a maximum lift of 9.5 feet and a depth of 
2.5 feet on lower sill at low water which was converted 
to use as a spillway. (See table 27-B for authorizing 
legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. None. 
Operations and results during fiscal year. 
Maintenance: Reservoirs were operated as required, 
recreation facilities were maintained, real estate 
managed and miscellaneous inspections, surveys, 
repairs, and reports were made by hired labor at a 
cost of $839,939. Discharge observation, gage reading 
and pool regulation cost $32,035 by hired labor. 
Miscellaneous engineering and design cost $6,044. 
Construction of recreation facilities at Gull Lake 
including a boat ramp, access roads, beach and 
support facilities cost $170,147. An archeological 
survey contract cost $20,043, a paving contract, 
$175,000 and discharge observation contracts, 
$1,080. Work by other Corps of Engineer districts for 
periodic inspection, a stability study, and a recreation 
use workshop cost $740, $24,999 and $4,888, 
respectively. Cooperative stream gaging with U.S. 
Geological Survey cost $26,030. Supervision and 
administration and other miscellaneous costs were 
$196,001. 
Condition at end of fiscal year: Existing project 
was completed in 1937. Flowage rights were acquired 
on all lands affected by construction, maintenance, 
and operation of reservoirs. A total of 1,672.26 acres 
in fee are owned by the United States. The United 
States has easements, flowage rights, and other 
rights of use on another 296,334.44 acres. Structures 
are in fair condition. Recreation facilities for public 
use are being constructed intermittently at all reservoir 
areas. (See table 27-H for capacities and costs by 
reservoir.) 
4. ST. CROIX RIVER, MN & WI 
Location. From source in northwestern Wisconsin, 
flows southwesterly and then southerly about 
164 miles to Mississippi River at Prescott, WI, about 
41.7 miles below lower Burlington Northern railway 
bridge, Minneapolis, MN. For its greater part, forms 
boundary between Minnesota and Wisconsin. (See 
27-2

ST. PAUL MINNESOTA DISTRICT 
Geological Survey map of Minnesota.) 
Existing project. Provides for maintenance of a 
channel, 9 feet in depth and of suitable width from 
mouth to Stillwater, MN, 24.5 miles, created by 
improvement of upper Mississippi River; a channel 3 
feet deep at mean low water between Stillwater and 
Taylors Falls (27.3 miles); improvement of harbor 
and waterfront at Stillwater; and a small-boat harbor 
at Hudson, WI currently classified "inactive." Estimated 
(1981) Federal cost of new work is $820,400. 
Latest authorization (1954) for maintenance work on 
reach between Stillwater and Taylors Falls is limited 
to an expenditure not exceeding $5,000 per year. (See 
table 27-B for authorizing legislation.) 
Local cooperation. Fully complied with for completed 
portion. For Hudson Harbor, see the annual 
report of 1970 for requirements. 
Terminal facilities. At Stillwater there is a concrete 
paved levee and a piling-and-timber trestle 
wharf on right bank. At other points along river, 
landing may be made on banks. Facilities are considered 
adequate for existing commerce. 
Operations and results during fiscal year. 
Maintenance: Sounding surveys cost $-8,099 and 
administrative costs were $143. 
Condition at end of fiscal year: All new work was 
completed in 1930, except subsequently authorized 
harbor at Hudson which was reclassified to 
"inactive" on April 20, 1982. The United States owns 
2.75 acres of land in fee at Taylors Falls and has easements 
over 7.57 acres of land at Bayport, MN. Extension 
to provide a 9-foot channel from mouth to Stillwater 
was completed August 12, 1938 when full pool 
at dam 3 of Mississippi River canalization project 
was reached. Minimum draft from Stillwater to 
Taylors Falls is about 1 foot at extreme low water, 
and from mouth to Stillwater, 9 feet. Maintenance of 
the 3 foot channel is limited to requests by the 
National Park Service which manages this reach 
under the Wild and Scenic Waterways classification. 
5. WARROAD HARBOR AND RIVER, MN 
Location. At southwestern extremity of Lake of 
the Woods, 36 miles west of mouth of Rainy River. 
(See NOAA Nautical Chart 14999.) 
Existing project. Provides for a channel 8 feet 
deep from landing at Warroad to deep water in lake, 
channel being 9,200 feet long, 200 feet wide within 
harbor, and 300 feet wide out in lake; for a turning 
basin 500 by 900 feet to a depth of 8 feet; and for a 
pile-brush stone jetty on north side of channel 
extending from shore 700 feet into the lake. For additional 
details see page 1027 of Annual Report of 1965. 
Portion of dredging of entrance channel and turning 
basin to complete project width and depth was considered 
unnecessary to meet present navigation 
requirements, and classified inactive was deauthorized 
on August 5, 1977 under Section 12 of Public 
Law 93-251. Estimated cost (1954) of this portion was 
$355,200. (See table 27-B for authorization legislation.) 
Local cooperation. None required. 
Terminal facilities. There is one publicly owned 
wharf. There are two commercial fish wharves, one of 
which is served by a spur track, and a number of 
minor wharves, all privately owned. Facilities are 
adequate for existing commerce. 
Operations and results during fiscal year. 
Maintenance: Condition surveys cost $7,938. Dredging 
by contract cost $173,693. Environmental review 
cost $2,766 by hired labor. Other engineering and administrative 
costs were $15,509. 
Condition at end of fiscal year: Project is complete. 
Prospective jetty completed in 1910 and reconstructed 
as a rubble mound in 1929 is in good condition. 
Turning basin at Warroad wharves was completed 
in 1911, and a channel 200 feet wide and 8 feet 
deep in 1915. Controlling depth in river channel and 
lake approach channel was 6 feet below low-water 
datum for a minimum width of 100 feet. A walkway 
on the jetty is provided for public use. A revetment 
wall, constructed under Section 2 of Public Law 269, 
69th Congress, in accordance with Article VIII of the 
Lake of the Woods Treaty, has deteriorated and will 
require future maintenance. 
Flood Control 
6. BASSETT CREEK, MN 
Location. In Hennepin County and Minneapolis, 
Minnesota, on Bassett Creek, a tributary of the 
Mississippi River. (For general location, see Geological 
Survey map of Minnesota.) 
Existing project. The proposed project consists of 
nonstructural and structural flood control measures. 
Nonstructural measures include continuation of 
existing floodplain regulations, flood insurance and 
forecasting, and flood warning. Principal structural 
measures consist of six small control structures in the 
upper watershed to temporarily impound floodwaters 
and a new tunnel (part of which is being constructed 
on a cooperative basis with the Minnesota Department 
of Transportation) in a highly urbanized area 
of Minneapolis to replace the existing tunnel outletting 
Bassett Creek to the Mississippi River. Also 
included in the plan are a limited reach of channel 
widening, bridge removals, culvert replacements, a 
weir structure, a flood storage area, and a railroad 
bridge replacement. Estimated Federal cost (1983) for 
new work is $20,400,000 and $6,360,000 is to be contributed 
by local interests. Project was authorized by 
the 1976 Water Resources Development Act. 
Local cooperation. See annual report for 1977 for 
requirements. A local assurance agreement will be 
required after determination of cost sharing policies. 
By resolutions approved September 12, 1974, 
October 31, 1975, and December 11, 1981, the city of 
Minneapolis has indicated its willingness and intention 
to meet the requirements of local cooperation. By 
27-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
letter dated August 17, 1982 the city of Minneapolis 
indicated an interest to discuss innovative project 
financing. 
Operations and results during fiscal year. 
New work: Preconstruction planning was continued 
at a cost of $416,333. 
Condition at end of fiscal year: Preconstruction 
planning is in progress. 
7. BIG STONE LAKE AND WHETSTONE 
RIVER, MN AND SD 
Location. On Minnesota River near Ortonville 
and Odessa, MN, and Big Stone City, SD, at the 
outlet of Big Stone Lake and in Big Stone and Lac qui 
Parle Counties, MN, and Grant County, SD. (For 
general location, see Geological Survey map of 
Minnesota.) 
Existing project. Provides for a dam and reservoir 
on Minnesota River above U.S. Highway 75, 
modification of Big Stone Lake outlet dam and silt 
barrier, bank stabilization along lower reach of Whetstone 
River, channel improvement on Minnesota 
River for 3 miles below outlet control dam at Big 
Stone Lake along with necessary relocations and 
acquisition of lands. These improvements would be 
made for wildlife conservation and development, 
flood control, and recreation. For additional details 
see Annual Report for 1970. Estimated Federal cost 
(1983) for new work is $12,300,000 and $153,000 to be 
contributed by local interests. Project was authorized 
by 1965 Flood Control Act (H. Doc. 579, 87th Cong., 
2d sess., contains latest map; and H. Doc. 193, 88th 
Cong., 2d sess.). 
Local cooperation. See Annual Report for 1968 
for requirements. The project requires sponsorship 
from both the States of Minnesota and South Dakota. 
Formal resolution of assurances adopted by the 
Upper Minnesota River Watershed District on 
June 10, 1969 and accepted by the District Engineer 
on November 3, 1969. Formal resolution of assurances 
adopted by the East Dakota Conservancy Sub- 
District for South Dakota on October 23, 1969 was 
furnished on November 18, 1969 and accepted by the 
District Engineer on November 19, 1969. Supplemental 
assurances covering the requirements of 
Public Law 91-646 were provided by the Upper 
Minnesota Watershed District on August 13, 1974 
and by the East Dakota Conservancy Sub-District on 
April 15, 1976. Rights-of way for construction on the 
Whetstone River and the entire cash contribution of 
$153,000 for the project were furnished by the local 
sponsors on December 21, 1981. 
Operations and results during fiscal year. 
New Work: Contract costs for the upstream works on 
the Whetstone River were $180,569. Minnesota River 
channel construction contract costs were $111,393. 
Engineering and design, supervision and administration 
and other miscellaneous costs were $181,078. 
Maintenance: Structure was operated and maintained 
and inspections and evaluations performed at 
a cost of $80,300. Construction of a rock berm fill to 
stabilize the upstream face of the embankment was 
completed at a cost of $662,357. Engineering and 
design cost $11,611. Supervision and administration 
cost $46,304. 
Condition at end of fiscal year: Construction of the 
new dam above Highway 75 and roads are completed. 
Surveys for land lines are complete, and the land 
acquisition program is complete. The first land payment 
was made on November 28, 1969 and 128 tracts 
have been purchased. A general plan between the 
Secretary of the Army and the Secretary of the 
Interior for administering the use of waters, land, or 
interests therein has been consummated, and a cooperative 
agreement between the Corps of Engineers 
and the U.S. Fish and Wildlife Service was approved. 
On March 31, 1975 the Secretary of the Army transferred 
lands in the project not required for Corps of 
Engineers operation and maintenance to the Department 
of the Interior. The transfer of property was 
accepted by the Department of the Interior on 
May 21, 1975. Construction on the Whetstone River 
portion of the upstream works is nearing completion. 
A construction contract for the Minnesota River work 
was awarded in May 1983 and work is in progress. 
8. BURLINGTON DAM, SOURIS RIVER, ND 
Location. In Ward County in northwestern North 
Dakota above Burlington, ND, on the Souris River. 
The damsite is north of Burlington about 1V2 miles 
northwest of the confluence of the Souris and Des 
Lacs Rivers and about 10 miles above Minot, ND. 
(For general location see Geological Survey Map of 
North Dakota.) 
Existing project. Authorized plan of improvement 
as modified by the phase I design memorandum 
provides for a single-purpose flood control reservoir 
near Burlington on the Souris River; modification of 
nine fish and wildlife refuge dams including a 4-foot 
raise of Lake Darling Dam; a diversion tunnel adjoining 
the Des Lacs River to the Burlington reservoir; 
improvements at the community of Velva and 
improvements by local interests in seven subdivision 
areas between Burlington and Minot and at the community 
of Sawyer, and regulation of future floodplain 
land use downstream from the dam site. Estimated 
Federal cost (1981) for new work is $124,000,000. 
Project was authorized by 1970 Flood Control Act. (H. 
Doc. 321, 91st Cong., 2d sess., contains latest published 
map.) 
Local cooperation. Requirements are described 
in full on page 27-4 of FY 1981 Annual Report. 
Operations and results during fiscal year. 
New work: Preconstruction planning was continued 
at a cost of $574. 
Condition at end of fiscal year: Project has been 
deferred with authorization of Lake Darling project. 
Additional authorization required for implementation 
of recommended plan. The Senate Report 97-256 
states that the Corps is to take no further action to 
27-4

ST. PAUL MINNESOTA DISTRICT 
construct Burlington Dam until expressly directed to 
do so by Congress. 
9. CHASKA, MN 
Location. In Carver County in south-central 
Minnesota on the Minnesota River. (For general location, 
see Geological Survey map of Minnesota.) 
Existing project. The plan of improvement consists 
of a levee and interior drainage works along the 
Minnesota River and flood diversion channels on 
Chaska Creek and East Creek at Chaska, together 
with appropriate floodplain regulation measures. 
Principal project features include approximately 1.1 
miles of upgraded levee, 0.6 mile of new levee, one 
pumping station, 0.9 mile of diversion channel on 
Chaska Creek, and 1.1 miles of flood bypass channel 
and a 1,400-foot tunnel on East Creek. Approximately 
1.6 miles of paved recreation trails on top of 
the levee and around Courthouse Lake are also 
included in the proposed plan. Estimated Federal 
cost (1983) for new work is $18,100,000 and $42,000 is 
to be contributed by local interests. Project was 
authorized by the 1976 Water Resources Development 
Act. (H. Doc. 644, 94th Congress, 2d sess., contains 
latest published map.) 
Local cooperation. See annual report for 1977 for 
requirements. A local assurance agreement will be 
required after completion of the design memorandum. 
By letter of August 19, 1982 the city of Chaska 
indicated its willingness and intention to meet the 
requirements of local cooperation. 
Operations and results during fiscal year. 
New work: Preconstruction planning was continued 
at a cost of $242,018. 
Condition at end of fiscal year: Preconstruction 
planning is in progress. 
10. DEVILS LAKE, ND 
Location. In Ramsey County in north central 
North Dakota about 80 miles west of Grand Forks, 
North Dakota. (For general location, see Geological 
Survey Map of North Dakota.) 
Existing Project. Provides for a system of levees 
and interior flood control facilities at the head of 
Creel Bay. The main embankment across Creel Bay 
will be 1,810 feet long and vary from 0 to 27 feet high. 
The south Creel Bay tieback embankment will be 
1,030 feet long and vary from 0 to 3 feet high. The 
north Creel Bay tieback embankment will be 2,400 
feet long and would vary from 0 to 8.5 feet high. The 
south embankment will be 3,100 feet long and vary 
from 0 to 9.5 feet high. 
The interior flood control system will consist of 
large holding ponds immediately north and south of 
the city's sewage lagoons, a 12,000 gallon per minute 
pumping station and a system of ditches and culverts 
linking the ponds to the pumping station. 
Total Federal cost (1983) for the proposed project is 
estimated at $1,767,000. The project was approved by 
the Chief of Engineers for construction August 15, 
1983, under the authority contained in Section 205 of 
the 1948 Flood Control Act, as amended. 
Local Cooperation. Local interests are required 
to provide without cost to the United States all lands, 
easements, and rights-of-way, including ponding and 
borrow areas, necessary for the construction, operation, 
and maintenance of the project; accomplish, 
without cost to the United States, all alterations and 
relocations of buildings, streets, and utilities except 
those utilities that are an integral part of project 
structures, necessary for the construction, operation 
and maintenance of the project; hold and save the 
United States free from damages caused by the construction 
and subsequent operation and maintenance 
of the project, except damages due to the fault or 
negligence of the United States or its contractors; 
provide all project costs in excess of the $4,000,000 
Federal statutory cost limitation; maintain and 
operate the project after completion, without cost to 
the United States, in accordance with regulations prescribed 
by the Secretary of the Army; prevent any encroachment 
on constructed works and ponding area 
that would interfere with the proper functioning of 
the project and, if ponding is impaired, provide 
promptly and without cost to the United States, substitute 
storage or equivalent pumping capacity; 
comply with the applicable provisions of the Uniform 
Relocation Assistance and Real Property Acquisition 
Policies Act of 1970, Public Law 91-646, approved 
January 2, 1971; comply with Section 601 of Title VI 
of the Civil Rights Act of 1964 (Public Law 88-352) 
and Department of Defense Directive 5500.11. 
A local assurance agreement required by Public 
Law 91-611 was adopted by the City of Devils Lake in 
August 1983. 
Operation and results during fiscal year. 
New Work: Engineering and design and supervision 
and administration costs were $159,656. 
Condition at end of fiscal year: A first feature construction 
contract for the access road and lakeside 
cofferdam at the head of Creel Bay was awarded in 
September 1983. Work on the plans and specifications 
for the remaining features of the project was 
also initiated. 
11. EAU GALLE RIVER, WI 
Location. At and in vicinity of Spring Valley, WI, 
on Eau Galle River 30 miles above its mouth at 
Chippewa River, and its tributary, Mines Creek, 
which flows through the village. Spring Valley is 
about 45 miles east of St. Paul, MN, and 36 miles west 
of Eau Claire, WI. (See Geological Survey map for 
Wisconsin for general location.) 
Existing project. Authorized plan of improvement 
as modified by further studies includes a 
retarding dam and reservoir on Eau Galle River immediately 
upstream from Spring Valley, and 
remedial works on Mines Creek including channel 
27-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
enlargement, a low levee, and a drop structure. Project 
provides for earth and rock-fill dam, an uncontrolled 
outlet and an uncontrolled spillway emerging 
above Mines Creek. See page 1030 of Annual Report 
for 1965 for further details. Proposed improvements 
on Burghardt Creek were eliminated. Improvements 
provide complete protection near Spring Valley for 
standard project flood, and below that point in 
decreasing value in proportion to distance from reservoir. 
Permanent conservation pool will serve a local 
need for a recreational area. Project was authorized 
by 1958 Flood Control Act (S. Doc. 52, 84th Cong., 1st 
sess., contains latest published map.) 
Local cooperation. Fully complied with. See page 
1083 of Annual Report for 1967. 
Operations and results during fiscal year. 
Maintenance: Structure and recreation facilities were 
operated and maintained, and inspections, investigations 
and evaluations were performed at a cost of 
$168,833 by hired labor and $12,591 by contract. Real 
estate management by the North Central Division 
cost $4,200 and dam failure planning by other Corps 
districts, $31,999. A conduit liner installation contract 
cost $5,001. Cooperative stream gaging cost 
$14,150. Administrative and other miscellaneous 
engineering costs were $24,305. 
Condition at end of fiscal year: Mines Creek 
improvements were substantially completed in 1964; 
minor work was accomplished in 1966. A contract for 
dam, spillway, and discharge channel, started 
July 1, 1965, was completed in October 1968. Recreational 
facilities have been provided. Remedial work 
to repair eroded gutters and road ditches was completed 
in September 1973. Repair of failing discharge 
conduit by installing a steel liner was completed in 
April 1982. 
12. ENDERLIN, MAPLE RIVER, ND 
Location. In Ransom County in southeastern 
North Dakota on the Maple River about 45 miles 
southwest of Fargo, North Dakota. (For general location, 
see Geological Survey Map of North Dakota.) 
Existing project. The proposed project at 
Enderlin provides for a system of levees along the 
right bank of the main stem and the left bank of the 
South Branch of the Maple River. The total levee 
system would be about 1.2 miles long and would have 
an average height of about 8 feet. Other features of 
the project include channel improvements on the 
south branch, replacement of the Soo Line railroad 
bridge, and interior drainage facilities consisting of 
three ponding areas with gated outlet conduits. To 
prevent failure of the channel and levee by erosion, 
rip-rapping would be provided in selected reaches. 
Total Federal cost (1983) for the proposed project 
is estimated at $3,555,000. The project was 
approved by the Chief of Engineers for construction 
August 11, 1982 under the authority contained in 
Section 205 of the 1948 Flood Control Act, as 
amended. 
Local cooperation. See page 27-5 of Annual 
Report for 1982 for requirements. 
A local assurance agreement required by Public 
Law 91-611 was adopted by the City of Enderlin in 
July 1982. 
Operations and results during fiscal year: 
New work: A riprap protection contract for the State 
Highway 46 bridge cost $50,264 and a main stem 
levee contract cost $6,675. Engineering and design by 
contract cost $61,472 and by hired labor, $231,368. 
North Central Division real estate costs were $4,167. 
Supervision and administration cost $32,981. 
Condition at end of fiscal year: A Phase I construction 
contract involving riprap protection of the State 
Highway 46 bridge at Enderlin was completed in 
July 1983. A Phase II contract involving the levee 
along the main stem Maple River was awarded in 
September 1983. Work on the plans and specifications 
for the remaining features of the project is continuing. 
13. GRAFTON, ND 
Location. In Walsh County in northeastern North 
Dakota on the Park River, a tributary of the Red 
River of the North. (For general location, see Geological 
Survey map of North Dakota.) 
Existing project. The plan of improvement 
proposed in the Phase I GDM is designed to protect 
present and future development at Grafton from 
damages due to floods of magnitudes up to and 
including the standard project flood. The plan 
consists of a grass-lined flood bypass channel 3.75 
miles long with a levee to the north of Grafton and a 
tieback levee extending upstream and to the west 
along the south branch, Park River. There would be a 
diversion structure at the upstream end of the bypass 
channel and a gated control structure where the 
tieback levee crosses the Park River at the diversion 
structure, limiting the flow in the existing channel to 
2,000 cfs. Estimated Federal cost (1983) for new work 
exclusive of Phase I costs is $16,000,000. The Phase I 
study was authorized by the 1976 Water Resources 
Development Act. (H. Doc. 645, 94th Congress, 2d 
sess., contains latest published map.) 
Local cooperation. Local interests are required to 
provide without cost to the United States all lands, 
easements, and rights-of-way, including suitable 
borrow and dredged and excavated material disposal 
areas, as determined by the Chief of Engineers to be 
necessary for the construction and maintenance of 
the project; hold and save the United States free from 
damages due to the fault or negligence of the United 
States or its contractors; maintain and operate the 
project after completion in accordance with regulations 
prescribed by the Secretary of the Army; accomplish 
without cost to the United States all alterations 
and relocations of buildings, transportation facilities 
except railroad bridges and approaches, storm 
drains, utilities, and other structures and improvements 
made necessary by the construction; prescribe 
27-6

ST. PAUL MINNESOTA DISTRICT 
and enforce regulations to prevent obstruction or encroachment 
on channels which would reduce their 
flood-carrying capacity or hinder maintenance and 
operation; publicize floodplain information in the 
areas concerned and provide this information to 
zoning and other regulatory agencies for their guidance 
and leadership in preventing unwise future 
development in the floodplain and in adopting such 
regulations as may be necessary to insure compatibility 
between future development and protection levels 
provided by the project; and at least annually inform 
affected interests regarding the limitations of the protection 
afforded by the project. 
A local assurance agreement will be required prior 
to construction. By letter dated December 27, 1982, 
the city has indicated its support of the proposed 
local flood protection project. 
Operations and results during fiscal year. The 
Final Phase I general design memorandum stage of 
advance engineering and design under the General 
Investigations program was completed. 
Condition at end of fiscal year: The study was completed 
and is in the review process. 
14. HOMME LAKE AND DAM, ND 
Location. Dam is on South Branch of Park River 
about 4 miles upstream from Park River, ND, and 
62.1 miles above mouth of Park River. South, Middle, 
and North Branches, headwater streams of Park 
River, rise in Cavalier County in northeastern North 
Dakota and flow easterly to an almost common confluence 
near Grafton, ND, forming main stream 
which flows easterly 35 miles to join Red River of the 
North about 35 miles south of the international 
boundary. (For general location, see Geological 
Survey map of North Dakota.) 
Existing project. See page 1285 of Annual Report 
for 1962. Project was authorized as Park River Reservoir 
by 1944 Flood Control Act (S. Doc. 194, 78th 
Cong., 2d sess.), and redesignated Homme Reservoir 
and Dam by Public Law 435, 80th Congress, 2d 
session. Latest published map is in project document. 
Local cooperation. Fully complied with. Total 
costs for all requirements of local cooperation under 
terms of project authorization, including required 
non-Federal contributions, were $62,800. In addition, 
local interests contributed $16,220 for construction of 
a water supply outlet through dam and incurred 
other costs of $19,600. 
Operations and results during fiscal year. 
Maintenance: Structure was operated and maintained, 
and inspections and evaluations performed at 
a cost of $57,991. 
Condition at end of fiscal year: Project completed 
in June 1956 except for additional recreational facilities 
which have been done intermittently since that 
time. Construction began in April 1948 and major 
structures completed in May 1951. Structures are in 
good condition. Government has acquired 395 acres 
of land in fee and easements over 7.8 acres of land for 
project. An additional 6.3 acres of land have been 
donated for recreational development and 3.75 acres 
have been acquired due to bank erosion bordering the 
project. 
15. IRVING TOWNSHIP, JACKSON COUNTY, 
WI 
Location. In Jackson County in west central Wisconsin 
on the Black River about 9 miles southwest of 
Black River Falls, Wisconsin. 
Existing Project. Provides for erosion control 
along a 1,100 foot reach on the right bank of the 
Black River. The site lies along Sunnyvale Road 0.3 
mile south of its junction with State Highway 54. The 
protection consists of rock riprap placed on a 1 
vertical on 2 horizontal slope with a 10-foot wide 
berm at the top of the riprap. 
Total Federal cost (1983) for the project is estimated 
at $189,600. The project was approved by the Chief of 
Engineers for construction August 11, 1981, under 
the authority contained in Section 14 of the 1946 
Flood Control Act, as amended. 
Local Cooperation. Local interests are required 
to provide without cost to the United States all lands, 
easements, and rights-of-way necessary for construction 
of the project; accomplish without cost to the 
United States all required alterations and relocations 
in utility facilities; hold and save the United States 
free from damages caused by the construction works, 
not including damages during construction, operation, 
and maintenance which are caused by the fault 
or negligence of the United States or its contractors; 
maintain the project after completion; assume full 
responsibility for all project costs in excess of the 
Federal cost limit of $250,000; provide a cash contribution 
for project costs in proportion to any special 
benefits to nonpublic property; comply with the 
applicable provisions of the Uniform Relocation 
Assistance and Real Property Acquisition Policies 
Act of 1970, Public Law 91-646, approved January 2, 
1971. A local assurance agreement required by Public 
Law 91-611 was adopted by the town of Irving in May 
1982. 
Operations and results during fiscal year. 
New work: Construction contract costs for the year 
were $146,229. Engineering and design costs were 
$13,202 and supervision and administration costs 
were $4,658. 
Condition at end of fiscal year. A contract for slope 
protection was awarded in September 1982. Construction 
of the project is substantially complete. 
16. LAC QUI PARLE LAKE, 
MINNESOTA RIVER, MN 
Location. Works covered by this project lie along 
Marsh Lake and Lac qui Parle and the Minnesota 
River between head of Marsh Lake and Granite 
Falls, MN. (For general location, see Geological 
27-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Survey map of Minnesota.) 
Existing project. See page 1291 of Annual Report 
for 1962. 
Local cooperation. None required. 
Operations and results during fiscal year. 
Maintenance: Project was operated and maintained, 
and inspections and evaluation performed at a cost of 
$168,297. 
Condition at end of fiscal year: Project has been 
operated by the Government since transfer from 
State of Minnesota to the United States in September 
1950. The United States owns fee title to 517.62 acres 
of land and easements on 19,859.47 acres of land. In 
1957, 60.1 acres were withdrawn from public lands 
for use by the Department of the Army. Land acquisition 
is complete. Construction under present plan of 
improvement was started in September 1941 and 
completed in December 1951 except for recreational 
facilities. All structures are in good condition. 
17. LA CROSSE, WI 
Location. In La Crosse County in southwestern 
Wisconsin on the Mississippi River. (For general 
location, see Geological Survey map of Wisconsin.) 
Existing project. The plan of improvement 
consists of seven miles of levee and one mile of street 
raise, road and rail closure structures, necessary 
interior drainage collection facilities, floodplain regulation, 
permanent evacuation and relocation of 40 
residential structures and flood proofing several businesses. 
Also, a paved hiking and bicycling trail 
would be provided on some portions of the levee 
system to meet identified recreation demands in the 
area. Estimated Federal cost (1983) for new work 
exclusive of Phase I costs is $25,900,000 and $63,000 
is to be contributed by local interests. Project was 
authorized for Phase I studies by the 1976 Water 
Resources Development Act. (H. Doc. 598, 94th 
Congress, 2d sess., contains latest published map.) 
Local cooperation. See Annual Report for 1977 
for requirements. A local assurance agreement will 
be required after completion of the design memorandum. 
By resolution adopted June 21, 1973 the county 
of La Crosse has indicated its willingness and intention 
to meet the requirements of local cooperation. 
The city provided their continued support for the 
study in a letter dated January 20,1982. In the spring 
of 1983, the city officials met with the Corps and indicated 
a desire to proceed with the flood control project 
as soon as possible. 
Operations and results during fiscal year. 
None. 
Condition at end of fiscal year: Preconstruction 
planning has not started. 
18. LA FARGE LAKE AND CHANNEL 
IMPROVEMENT, WI 
Location. Rises in Monroe County in southwestern 
Wisconsin and flows south and southwest 
through Vernon, Richland, and Crawford Counties 
emptying into Wisconsin River about 16 miles above 
junction of latter stream with Mississippi River. (For 
general location see Geological Survey map of 
Wisconsin.) 
Existing project. Provides for a dam and 
impoundment of the Kickapoo River about 1 mile 
upstream from village of La Farge, operated for flood 
control, fish and wildlife conservation, general recreation, 
and a reduction of aggradation downstream 
from the dam, and supplemental protection at 
Soldiers Grove and at Gays Mills by means of levees, 
supplementary channel improvement, and interior 
drainage facilities. See Annual Report for 1975 for 
details. 
Estimated Federal cost (1976) for new work is 
$55,400,000. Project was authorized by 1962 Flood 
Control Act (H. Doc. 557, 87th Cong., 2d sess., 
contains latest published map.) 
Local cooperation. None required for construction 
of La Farge Lake. See page 1087 of Annual 
Report for 1967 for requirements for local protection 
works. Local interests have not been requested to 
furnish assurances. 
Operations and results during fiscal year. 
New work: Relocation utility contracts and an 
archaeological survey contract cost $5,802 and $956, 
respectively. Engineering and design by hired labor 
cost $222,971. Wisconsin DNR participation, Buffalo 
District support, U.S. Fish and Wildlife Service and 
NCD real estate cost $10,996, $51,598, $19,730 and 
$1,393 respectively. Administrative and miscellaneous 
costs were $23,403. Maintenance: Project was 
operated and maintained at a cost of $17,656. 
Condition at end of fiscal year: General and Real 
Estate design memorandums and detailed plans for 
the La Farge Dam and spillway and for relocations 
have been completed. Land acquisition negotiations 
began in December 1968. The first land payment was 
made on January 15, 1969 and the land acquisition 
program is 80 percent complete. Contracts for 
excavation of the left abutment, for test wells, and for 
construction of the outlet works and right abutment 
have been completed. A study of alternatives has 
been completed. Funds to complete the authorized 
project have been withheld and all further construction 
has been indefinitely suspended. Work has been 
accomplished to provide for completion of relocation 
work left partially completed when construction was 
suspended. Soldiers Grove has begun relocation out 
of the floodplain area after receiving funds from 
other agencies. A study of a modified dry dam is in 
progress and a report will be completed in FY 1984. 
19. LAKE ASHTABULA AND BALDHILL 
DAM, SHEYENNE RIVER, ND 
Location. Baldhill Dam is on the Sheyenne River, 
16 miles upstream from Valley City, ND, and about 
271 miles above mouth. Sheyenne River rises in 
central North Dakota and flows 500 miles generally 
27-8

ST. PAUL MINNESOTA DISTRICT 
southeast to enter Red River of the North about 10 
miles north of Fargo, ND. (For general location see 
Geological Survey map of North Dakota.) 
Existing project. See page 1287 of Annual Report 
for 1962. Project was authorized by Flood Control Act 
of 1944 (S. Doc. 193, 78th Cong., 2d sess., contains 
latest published map). Reservoir above Baldhill Dam 
was designated as Lake Ashtabula by Public Law 
772, 81st Congress, 2d session. 
Local cooperation. See page 1288 of Annual 
Report for 1962. Complied with except for construction 
of Fargo diversion dam and ditch for which 
assurances furnished by city of Fargo were approved 
by the Secretary of War on June 26, 1947. Necessity 
for this feature will be reviewed. 
Operations and results during fiscal year. 
New work: A contract for materials and services cost 
$13,261. Administrative and engineering costs were 
$3,007. Maintenance: Project was operated and maintained, 
and inspections and evaluations performed at 
a cost of $395,306. Real estate management cost 
$13,996. Dam instrumentation, stability and safety 
assurance, and failure planning cost $125,807. Dam 
failure planning by other Corps districts cost $33,999 
and Missouri River Division soils testing cost 
$40,507. Cooperative stream gaging with the U.S. 
Geological Survey cost $40,500. Water quality monitoring 
by other Corps districts cost $11,999. A survey 
contract and a bank protection contract cost $10,147 
and $975, respectively. Contract for cultural resource 
investigation cost $27,577. Contract for law enforcement 
cost $14,204. Administrative and other miscellaneous 
costs were $71,031. 
Condition at end of fiscal year: Project completed 
in March 1956 except construction of recreational 
facilities which is being accomplished intermittently. 
United States owns 7,816.5 acres of land in fee and 
easements on 666.2 acres. Construction initiated in 
July 1947 and major features completed in November 
1950. Dam was placed in permanent operation in 
spring of 1951. Structures are in good condition. 
20. LAKE DARLING, SOURIS RIVER, ND 
Location. On the Souris River in Ward, Renville, 
McHenry, and Bottineau Counties in northwestern 
North Dakota. The existing Lake Darling Dam, 
which is to be raised, is located about 20 miles northwest 
of Minot, North Dakota. The project also 
includes features at the communities of Sawyer and 
Velva and at various locations along the 358-mile 
U.S. portion of the Souris River. (For general location 
see Geological Survey Map of North Dakota.) 
Existing project. The Lake Darling project 
provides for raising Lake Darling Dam by approximately 
4 feet. The project also provides for other work 
on the Souris River such as levee improvements at 
Velva, Sawyer, and six subdivision areas between 
Burlington and Minot, floodproofing of rural residences, 
modification of refuge structures in the Upper 
Souris and J. Clark Salyer Refuges, and bridge 
relocations in the reservoir. The work is a portion of 
the Burlington Dam project which required postauthorization 
approval prior to construction. However, 
Congress has directed the Corps not to take 
further actions to construct the Burlington Dam until 
expressly directed to do so. Estimated Federal Cost 
(1983) for new work is $64,000,000. Project was 
authorized by 1982 Energy and Water Development 
Appropriations Act, Public Law 97-88 approved 
December 4, 1981. 
Local cooperation. Under the local cooperation 
items now considered for the Lake Darling project 
local interests would be required to provide without 
cost to the United States all lands, easements and 
rights-of-way necessary for construction and subsequent 
maintenance of that part of the project lying 
downstream of the Lake Darling Dam; hold and save 
the United States free from damages resulting from 
the construction, operation and maintenance of that 
part of the project lying downstream of the Lake 
Darling Dam, except damages due to the fault or 
negligence of the United States or its contractors; 
maintain and operate all of the project works lying 
downstream of the Lake Darling Dam, the protective 
levees at McKinney Cemetery, Eckert Ranch and 
Renville Park and the diversion channel at Renville 
Park, after completion, in accordance with regulations 
prescribed by the Secretary of the Army; accomplish 
without cost to the United States all necessary 
changes to buildings, highway bridges (including 
approaches), streets, dams, sewers and utilities, as 
required for construction of that part of the project 
lying downstream of the Lake Darling Dam; prescribe 
and enforce regulations to prevent encroachment 
on downstream channel capacities for regulation 
of the reservoirs; and, if drainage channel 
capacities and ponding areas for interior drainage 
are impaired, provide substitute storage capacity or 
equivalent pumping capacity promptly without cost 
to the United States; inform affected interests at least 
annually that the project will not provide complete 
flood protection; provide guidance and leadership in 
preventing unwise future development of the flood 
plain by use of appropriate flood plain management 
techniques to reduce flood losses from the Lake 
Darling damsite downstream to the Canadian 
border; adjust all water-rights claims resulting from 
the construction and operation of the project, and 
hold and save the United States free from damages 
resulting from such claims; comply with the 
applicable provisions of the Uniform Relocation 
Assistance and Real Property Acquisition Policies 
Act of 1970, Public Law 91-646, approved 2 January 
1971, in acquiring lands, easements, and rights-of-way 
for construction and subsequent maintenance of the 
project and inform affected persons of pertinent benefits, 
policies, and procedures in connection with said 
Act; comply with Section 601 of Title VI of the Civil 
Rights Act of 1964 (Public Law 88-352) and Department 
of Defense Directive 5500.11 issued pursuant 
thereto and published in Part 300 of Title 32, Code of 
Federal Regulations, in connection with the construc- 
27-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
tion and subsequent maintenance and operation of 
the project; and hold and save the United States free 
from damages which result from the overtopping of 
the McKinney Cemetery, Eckert Ranch and Renville 
County Park levees to be constructed upstream of the 
Lake Darling Dam. Overtopping of these levees shall 
not be construed as a result of negligence or fault on 
the part of the United States or its contractors. 
Representatives of the water resource districts from 
Ward, Renville, McHenry, and Bottineau Counties 
and the Oak Creek drainage area agreed to become 
members of a Souris River Joint Board for flood 
control, which would serve as local sponsor for the 
project. The general letter of intent to serve as a local 
sponsor was signed by their president on June 14, 
1983. 
Operations and results during fiscal year. 
New work: Preconstruction planning was continued 
at a cost of $1,176,694. 
Condition at end of fiscal year: Preconstruction 
planning is in progress. 
21. LAKE TRAVERSE AND BOIS DE SIOUX 
RIVER, SD AND MN 
Location. Works covered by this project lie along 
Lake Traverse and Bois de Sioux River between 
upper end of Lake Traverse at Browns Valley, MN, 
and the mouth of Bois de Sioux River at Breckenridge, 
MN. Lake drains through river to Red River of 
the North, and the two waters form a portion of 
boundary between State of Minnesota and States of 
North and South Dakota. (For general location, see 
Geological Survey map of Minnesota.) 
Existing project. See page 1289 of Annual Report 
for 1962. Existing project was authorized by Flood 
Control Act of June 22, 1936. 
Local cooperation. None required. 
Operations and results during fiscal year. 
Maintenance: Project and related facilities were 
operated and maintained, and inspections and evaluations 
performed at a cost of $186,053. 
Condition at end of fiscal year: Existing project 
was completed in June 1948, except for minor recreation 
facilities. Fee title to 1,144.13 acres and easements 
on 6,172.25 acres of land have been acquired. 
White Rock Dam and Reservation control structures 
are in operation, and structures and appurtenances 
are in good condition. Remedial work for repair of 
apron at White Rock Dam was completed in 
November 1968. Roadways across structures are 
open to public travel. 
22. MANKATO AND NORTH MANKATO, MN 
Location. Along Minnesota River between miles 
103.5 and 109.5 near Mankato, North Mankato, and 
Le Hillier, in south-central Minnesota. (For general 
location see Geological Survey map of Minnesota.) 
Existing project. As modified as a result of severe 
1965 flood, provides for protection of communities of 
Mankato, North Mankato, and Le Hillier by means of 
levees and floodwalls with pumping plants and interior 
drainage facilities. See page 1090 of Annual 
Report for 1967 for further details. Additional 
channel improvement, levees, pumping, and interior 
drainage features have been included in the Mankato 
unit of the project for protection from the high flows 
of Indian Creek. Expansion of Indian Creek improvements 
were made during detailed studies as a result 
of updated hydrologic data. Highway bridge relocations 
made necessary by the project have been 
authorized at Federal expense. Estimated Federal 
cost (1983) for new work is $92,700,000. Project was 
authorized by 1958 Flood Control Act (H. Doc. 437, 
84th Cong., 2d sess., contains latest published map.) 
Project was modified by 1965 Flood Control Act, and 
by the Water Resources Development Acts of 1974 
and 1976. 
Local cooperation. Fully complied with for work 
under contract. See Annual Report for 1973 for 
requirements. Resolutions agreeing to provide formal 
assurances of local cooperation, when requested, 
were passed by the city council of North Mankato, 
Mankato, and South Bend Township (Le Hillier), 
respectively, on November 12, 1968. 
Operations and results during fiscal year. 
New work: Construction of stage 3B-1 (Mankato) was 
completed. Construction of Stage 3C-1 (Mankato) 
was initiated. Construction costs for improvements 
at Mankato were $3,514,435, at North Mankato were 
$567,410 and at Le Hillier were $395. Engineering 
and design by contract cost $347,756 and by hired 
labor cost $478,588, and by other agencies cost 
$1,604. Supervision and administration cost 
$259,303. 
Condition at end of fiscal year: Construction of 
stage 1, 1-H.P., 4A and 4B (North Mankato), stage 2A 
(Mankato along the Blue Earth River), stage 2B (Le 
Hillier), stage 3A-1, 3A-2, 3B-1, 3B-2A and 3B-2B 
(Mankato) is complete. Construction of stage 3C-1 
(Mankato) is underway. Detailed design for 
remaining features to complete standard project 
flood protection is in progress. 
23. MINOT, ND 
Location. In Ward County in northwestern North 
Dakota on the Souris River, extending from Burlington 
through Minot to the village of Logan. The river 
meanders through Minot, flowing generally from 
west to east and divides the community into two 
parts. (For general location, see Geological Survey 
map of North Dakota.) 
Existing project. Project provides for channel 
improvement within a 37.0-mile reach of the Souris 
River extending from Burlington to Logan. For 
details see Annual Report for 1973. 
Project was authorized in 1970 under section 201 of 
the Flood Control Act of 1965. (H. Doc. 321, 91st 
Cong., 1st sess., contains latest published map). Reso- 
27-10

ST. PAUL MINNESOTA DISTRICT 
lutions were adopted by the Public Works Committees 
of the Senate on June 25, 1970 and the House on 
July 14, 1970. Project has been modified by the Water 
Resource Development Acts of 1974 and 1976. 
Local cooperation. Fully complied with for work 
under contract. See Annual Report for 1971 for 
requirements. On May 26, 1971 the Ward County 
Water Management Board approved the motion to 
provide assurances of local cooperation. The resolution 
was furnished by letter dated June 16, 1971 and 
accepted by the District Engineer on August 9, 1971. 
Operations and results during fiscal year. 
New work: Construction costs by contract for the 
year amounted to $13,999. Supervision and administration 
costs were $20. 
Condition at end of fiscal year: The project was 
completed in September 1979 and was officially 
turned over to the local sponsor for operation and 
maintenance December 1981. 
24. PEMBINA RIVER, ND 
Location. In Pembina County in northeastern 
North Dakota south of the international boundary. 
Existing project. Plan of improvement proposed 
in the 1976 feasibility report provided for a multiplepurpose 
impoundment located on the Pembina River 
for flood control, water supply and recreation. The 
Phase I study was authorized by the 1976 Water 
Resources Development Act. (H. Doc. 116, 96th Congress, 
1st sess.) The study found that the Pembilier 
Dam is not an economically feasible plan. The only 
flood control plan found to be economically feasible is 
a floodway designed to carry up to 2,000 cfs of flood 
flows from just upstream of Neche, North Dakota to 
the Red River of the North downstream of Pembina. 
The floodway would be located on the south side of 
the international boundary and would be 21 miles 
long and vary from 50 to 100 feet in width. Design 
water depth would be 7 feet. Estimated Federal cost 
(1983) for new work exclusive of Phase I costs is 
$6,740,000. 
Local cooperation. A local assurance agreement 
would be required prior to the initiation of construction. 
A letter of intent from a non-Federal sponsor 
and Congressional authorization are necessary in 
order to proceed with more detailed design and subsequent 
construction. 
Operations and results during fiscal year. 
Phase I design memorandum stage of advance engineering 
and design was completed under the General 
Investigations program. 
Condition at end of fiscal year: Phase I study was 
completed and sent to higher authority for review. 
25. PRAIRIE DU CHIEN, WI 
Location. In Crawford County in southwestern 
Wisconsin on the left bank of the Mississippi River. 
(For general location, see Geological Survey map of 
Wisconsin.) 
Existing project. Combines total evacuation with 
flood proofing and land use control measures to 
provide the desired reduction of potential flood 
damages within design limits. Evacuation would be 
accomplished by purchase and relocation of structures 
in the lowest portions of the floodplain. Estimated 
cost (1983) to the United States for new work is 
$4,020,000. Project was authorized by Water 
Resources Development Act of 1974. 
Local cooperation. See Annual Report for 1974 
for requirements. A local assurance agreement in 
accordance with Section 221 of the Flood Control Act 
of 1970 was entered into with the city of Prairie du 
Chien on May 2, 1978 and signed by the Chief of 
Engineers on September 11, 1978. 
Operations and results during fiscal year. 
New work: Costs for property acquisition and relocation 
activities were $162,642. Contracts for floodproofing 
and site restoration cost $11,024 and 
$36,292, respectively. Engineering and design cost 
$22,663 by hired labor and $7,230 by contract, and 
supervision and administration cost $6,337. Contributions 
in lieu of cash were $-216,639. 
Condition at end of fiscal year: Property acquisitions 
and relocations are in progress. 
26. RED LAKE RIVER AT HUOT, MN 
Location. In Red Lake County in northwestern 
Minnesota on the Red Lake River about 30 miles east 
of East Grand Forks, Minnesota (for general location, 
see Geological Survey Map of Minnesota). 
Existing Project. The project at Huot involves the 
placement of rock revetment along approximately 
400 feet of the eroding Red Lake River channel bank 
to protect adjacent County-State-Aid Highway 
(CSAH) 17. 
The total Federal cost (1983) of the project is 
$64,500. The project was approved by the Chief of 
Engineers for construction April 12, 1983 under the 
authority contained in Section 14 of the 1946 Flood 
Control Act, as amended. 
Local Cooperation. Local interests are required 
to provide without cost to the United States all lands, 
easements and rights-of-way necessary for the construction, 
operation and maintenance of the project; 
accomplish without cost to the United States all 
required alterations and relocations in utility facilities; 
hold and save the United States free from 
damages due to the construction, operation and 
maintenance of the project except where such 
damages are due to the fault or negligence of the 
United States or its contractors; maintain the project 
after completion; assume full responsibility for all 
project costs in excess of the Federal cost limit of 
$250,000; provide a cash contribution for project costs 
in proportion to any special benefits to nonpublic 
property; comply with the applicable provisions of 
the Uniform Relocation Assistance and Real 
Property Acquisition Policies Act of 1970, Public Law 
91-646, approved January 2, 1981, in acquiring lands, 
27-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
easements, and rights-of-way for construction and 
subsequent maintenance of the project, and inform 
affected persons of pertinent benefits, policies and 
procedures in connection with said Act, and comply 
with Section 601 of Title VI of the Civil Rights Act of 
1964 (P.L. 88-352) and Department of Defense Directive 
5500.11 issued pursuant thereto and published in 
Part 300 of Title 32, Code of Federal Regulations, in 
connection with the construction and subsequent 
maintenance and operation of the project. 
A local assurance agreement required by Public 
Law 91-611 was adopted by the Red Lake County 
Board of Commissioners in May 1983. 
Operations and results during fiscal year. 
New work: Engineering and design and supervision 
and administration costs were $11,626. 
Condition at the end of the fiscal year: A construction 
contract was awarded in August 1983 and construction 
is in progress. 
27. RED LAKE RIVER AT RED LAKE FALLS, 
MN 
Location. In Red Lake County in northwestern 
Minnesota on the Red Lake River. (For general 
location, see Geological Survey Map of Minnesota.) 
Existing Project. The project at Red Lake Falls 
involves the protection of the County-State-Aid Highway 
(CSAH) 13 bridge where erosion along the right 
bank of the Red Lake River threatens the abutment 
and approach to the bridge. Protective measures 
include the placement of rock revetment along the 
right bank of the river within a reach extending from 
about 20 feet downstream of the bridge to about 650 
feet upstream of the bridge. 
Total Federal cost (1983) of the project is $131,000. 
The project was approved by the Chief of Engineers 
for construction June 6, 1983 under the authority contained 
in Section 14 of the 1946 Flood Control Act as 
amended. 
Local Cooperation. Local interests are required 
to provide without cost to the United States all lands, 
easements, and rights-of-way necessary for the construction, 
operation, and maintenance of the project; 
accomplish without cost to the United States all 
required alterations and relocations in sewer, water 
supply, drainage, and other utility facilities; hold and 
save the United States free from damages due to the 
construction, operation, and maintenance of the 
project except where such damages are due to the 
fault or negligence of the United States or its contractors; 
maintain the project after completion; assume 
full responsibility for all project costs in excess of the 
Federal cost limit of $250,000; provide a cash contribution 
for project costs in proportion to any special 
benefits to non-public property; comply with the 
applicable provisions of the Uniform Relocation 
Assistance and Real Property Acquisition Policies 
Act of 1970, Public Law 91-646, approved January 2, 
1971, in acquiring lands, easements, and rights-ofway 
for construction and subsequent maintenance of 
the project, and inform affected persons of pertinent 
benefits, policies and procedures in connection with 
said Act, and; comply with Section 601 of Title VI of 
the Civil Rights Act of 1964 (Public Law 88-352) and 
Department of Defense Directive 5500.11 issued 
pursuant thereto and published in Part 300 of Title 
32, Code of Federal Regulations, in connection with 
the construction and subsequent maintenance and 
operation of the project. 
A local assurance agreement required by Public 
Law 91-611 was adopted by the Red Lake County 
Board of Commissioners in June 1983. 
Operations and results during fiscal year. 
New Work: Engineering and design and supervision 
and administration costs were $17,582. 
Condition at end of fiscal year: A construction contract 
was awarded in September 1983 and construction 
is in progress. 
28. RED LAKE RIVER, MN, 
INCLUDING CLEARWATER RIVER, MN 
Location. Works covered by this project lie along 
upper reach of Red Lake River and also along Clearwater 
River, a tributary of Red Lake River, between a 
point near Plummer, MN, and a point just above the 
mouth of Ruffy Brook. Red Lake River, principal 
tributary of Red River of the North, has its source at 
the outlet of Lower Red Lake in northwestern portion 
of Minnesota and flows westerly about 196 miles to 
its junction with Red River of the North at East 
Grand Forks, MN. Clearwater River has a general 
westerly course from its source near Ebro, MN, about 
205 miles to its junction with Red Lake River at Red 
Lake Falls, MN. (For general location, see Geological 
Survey map of Minnesota.) 
Existing project. See page 1281 of Annual Report 
for 1962. Project was authorized by 1944 Flood 
Control Act (H. Doc. 345, 78th Cong., 1st sess., 
contains latest published map.) 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Maintenance: Structures were operated and maintained 
and inspections and evaluations performed at 
a cost of $34,383. 
Condition at end of fiscal year: Construction of 
major improvements on Red Lake River initiated in 
February and the Clearwater River initiated in 
October 1948 were completed in June 1956. Replacement 
of a rock and brush dam on Red Lake River at 
Indian boundary with a concrete structure and 
appurtenant work was completed in June 1959 to 
restore marshes in the area to better wildlife conditions. 
Construction of a bridge on Clearwater Road 
was completed by the Indian Service in July 1965. A 
contract for improvements on Red Lake River was 
completed in November 1966, and a contract for 
restoration of water levels in Red Lake River marshes 
was completed in July 1967. Increased slope protection 
downstream of the control structure was 
completed in November 1968. Operation of Red Lake 
27-12

ST. PAUL MINNESOTA DISTRICT 
Dam was assumed by the Corps on April 1, 1951. 
Channels are in good condition and indicate effectiveness 
of project as a flood control measure. 
29. RED RIVER OF THE NORTH DRAINAGE 
BASIN, MN, SD & ND 
Location. Red River of the North basin, within the 
United States, includes northeastern corner of South 
Dakota and much of eastern North Dakota and 
northwestern Minnesota. Red River of the North, 
formed by confluence of Otter Tail and Bois de Sioux 
Rivers, flows northward through this region, forming 
boundary between North Dakota and Minnesota. 
(For general location of basin, see Geological Survey 
maps of Minnesota and South Dakota.) 
Previous project. See page 1278 of Annual 
Report for 1962 for navigation and flood control 
projects in the basin, not part of this project. 
Existing project. Project includes improvements 
for local protection in interests of flood control and 
major drainage accomplished by channel improvement, 
levees, etc., in addition to construction of a 
multiple purpose reservoir on Otter Tail River to 
control floods and, in conjunction with previously 
authorized Federal reservoir project at Baldhill site of 
Sheyenne River and at Red Lake, to increase low 
flows for water supply and pollution abatement. (See 
table 27-J for active units in comprehensive basin 
plan.) 
Project was authorized by Flood Control Acts of 
1948 and 1950. Public Works Authorization Act, 1957, 
authorized Chief of Engineers to acquire such lands 
as were beyond legal authority of city of Grand Forks 
to acquire. Section 205 of the Flood Control Act of 
1970 provided for extension of the expiration date for 
the East Grand Forks project. Authorization of the 
Sheyenne River (Kindred Lake) project by the 1970 
Flood Control Act provided for the deletion of 
channel improvement on the lower 48.8 miles of the 
Sheyenne River authorized under the Flood Control 
Acts of 1948 and 1950. Latest published map is in 
House Document 185, 81st Congress, 1st session. 
Local cooperation. See page 1039 of Annual 
Report for 1965. Following the flood of 1965, the city 
of East Grand Forks requested reactivation of the 
project and furnished a resolution adopted May 11, 
1965, indicating its willingness to meet the requirements 
of local cooperation. Expiration date for the 
East Grand Forks project was extended to April 17, 
1975 permitting local interests additional time to 
furnish assurances of local cooperation. A local 
assurance agreement was passed by the city on 
March 27, 1975 and accepted by the acting Director 
of Real Estate, OCE for the Secretary of the Army on 
April 9, 1975. 
Operations and results during fiscal year. 
New work: Preconstruction planning was continued 
for the East Grand Forks project at a cost of $174,255. 
Maintenance: Orwell Lake and Dam were operated 
as required and miscellaneous inspections, reports, 
and repairs were made at a cost of $78,842. Real 
estate management by the North Central Division 
and foundation testing by Missouri River Division 
cost $4,200 and $4,280, respectively. Discharge observation 
and gages and pool regulation cost $11,387. 
Dam failure planning by other Corps districts cost 
$22,033 and cooperative stream gaging with the U.S. 
Geological Survey cost $12,330. Supervision and 
administration and other miscellaneous costs were 
$19,316. 
Condition at end of fiscal year: Major construction 
for all active units except for East Grand Forks, MN, 
is complete. Preconstruction planning is underway at 
East Grand Forks. A total of 1,985 acres of land for 
Orwell Lake and Dam is owned in fee by the United 
States. See page 1281 of Annual Report for 1962 for 
periods of completion at active units of project other 
than Fargo. Work at Fargo, ND, started in May 1959, 
was completed in July 1963. (See table 27-J at end of 
chapter for total costs of new work to date.) 
Costs to date for operation and maintenance of 
Orwell Lake and Dam are $2,311,011. Total costs for 
active portion of project are $9,328,054. In addition, 
$350,034 was expended from contributed funds for 
work done for local interests. 
30. RED RIVER OF THE NORTH AT 
HALSTAD, MN 
Location. In Norman County in western Minnesota 
on the Red River of the North about 36 miles 
north of Moorhead, Minnesota. (For general location 
see Geological Survey Map of Minnesota.) 
Existing Project. Provides for a system of levees 
and interior flood control facilities along the right 
bank of the Red River of the North. The total levee 
system is about 2.4 miles long and varies from 0 to 
over 20 feet high. Most of the levee is 5 to 12 feet high. 
The levee rings the city except for about 0.6 mile of 
high ground. Other features include 4 ponding areas 
and a system of gatewells, pipes and ditches to 
provide interior flood control. 
Total Federal cost (1983) for the proposed project is 
estimated at $1,813,000. The project was approved by 
the Chief of Engineers for construction April 5, 1983, 
under the authority contained in Section 205 of the 
1948 Flood Control Act, as amended. 
Local Cooperation. Local interests are required 
to provide without cost to the United States all lands, 
easements, and rights-of-way, including ponding and 
borrow areas, necessary for the construction, operation, 
and maintenance of the project; accomplish all 
alterations and relocations of buildings, streets, and 
utilities, except for those utilities which are an 
integral part of project structures; hold and save the 
United States free from damages caused by the construction 
and subsequent operation and maintenance 
of the project, except damages due to the fault or 
negligence of the United States or its contractors; 
provide all costs in excess of the $4,000,000 Federal 
cost limitation; maintain and operate the project 
27-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
after completion without cost to the United States in 
accordance with regulations prescribed by the Secretary 
of the Army; prevent any encroachment on constructed 
works and ponding areas that would interfere 
with the proper functioning of the project; and, if 
ponding is impaired, provide promptly and without 
cost to the United States, substitute storage or 
equivalent pumping capacity; comply with the 
applicable provisions of the Uniform Relocation 
Assistance and Real Property Acquisition Policies 
Act of 1970, Public Law 91-646, approved January 2, 
1971; comply with Section 601 of the Title VI of the 
Civil Rights Act of 1964 (Public Law 88-352) and 
Department of Defense Directive 5500.11. 
A local assurance agreement required by Public 
Law 91-611 was adopted by the city of Halstad in 
April 1983. 
Operations and results during fiscal year. 
New work: Engineering and design and supervision 
and administration costs were $156,373. 
Condition at end of fiscal year. A first feature construction 
contract involving a storm water outlet and 
sanitary sewer modifications was awarded in 
September 1983. Work on the plans and specifications 
for the balance of the project was also initiated. 
31. RED RIVER OF THE NORTH AT OSLO, 
MN 
Location. In Marshall County in northwestern 
Minnesota on the Red River of the North about 20 
miles north of Grand Forks, North Dakota. (For 
general location, see Geological Survey map of 
Minnesota.) 
Existing project. Provides for a levee encircling 
the village of Oslo and an agricultural tract north of 
the village. Wherever possible, the levee has been 
constructed contiguously with an existing emergency 
levee, and is about 10 feet high and 3.2 miles long 
with a top width of from 10 to 12 feet. The project also 
provides interior drainage facilities, including a 
pumping station, two ponding areas, interceptor and 
outfall sewers, and drainage ditches; highway and 
street ramps; temporary sandbag closures; and landscape 
measures. Total Federal costs (1983) for new 
work are estimated at $1,960,200. Project was 
approved by the Chief of Engineers for construction 
on August 2, 1972 under the authority contained in 
section 205 of the 1948 Flood Control Act, as 
amended. 
Local cooperation. See Annual Report for 1973 
for requirements. A local assurance agreement 
required by Public Law 91-611 was adopted by the 
village of Oslo on October 15, 1972. 
Operations and results during fiscal year. 
New work: A bank stabilization contract cost 
$343,441. Engineering and design and supervision 
and administration costs were $22,618. 
Condition at end of fiscal year: A construction 
contract was awarded in June 1974. Project is 
complete except for bank stabilization measures 
which are substantially complete. 
32. ROCHESTER, MN 
Location. In Olmstead County in southeastern 
Minnesota on the South Fork of the Zumbro River. 
(For general location, see Geological Survey map of 
Minnesota.) 
Existing project. Provides for channel modifications 
supplemented by levees at and in the vicinity of 
Rochester, together with appropriate flood warning 
and floodplain regulation measures. Principal project 
features include approximately 0.9 mile of verticalwalled 
channel, 6.6 miles of riprap, gabion or rocklined 
channel, 0.5 mile of grass-sloped channels, 2.4 
miles of levees, drop structures, bridge modifications, 
and interceptor sewers and ditches for interior 
drainage. A river corridor hiking and biking trail 
system, and other environmental treatment measures 
are also included in the proposed plan. Estimated 
cost (1983) to the United States for new work is 
$51,400,000. Project was authorized by the Water 
Resources Development Act of 1974 (H. Doc. 156, 93rd 
Cong., 1st sess., contains latest published map.) 
Local cooperation. See Annual Report for 1974 
for requirements. By resolution approved on September 
29, 1981 the city of Rochester, the local sponsor, 
indicated its willingness and intention to meet the 
requirements of local cooperation for flood control 
and recreation. Formal assurances will be requested 
prior to initiation of construction. 
Operations and results during fiscal year. 
New work: Preconstruction planning was continued 
at a cost of $259,351. 
Condition at end of fiscal year: Phase I design 
memorandum stage of preconstruction planning was 
completed and forwarded to Congress on April 27, 
1979 which was the basis for authority to proceed 
with the Phase II design memorandum stage of 
advance engineering and design. Phase II studies 
and plans and specifications for the first stage of 
project construction (stage 1A) have been completed. 
33. ROSEAU RIVER, MN 
Location. In Roseau County and northeastern 
Kittson County, in northwestern Minnesota, and in 
south-central Manitoba, Canada. (For general location 
of the works in United States see Geological 
Survey map of Minnesota.) 
Existing project. Provides for improvement of 
Roseau River for flood control consisting of 44.4 miles 
of channel improvement, two sections of earth levees 
with lengths of 1.9 and 5.9 miles, respectively, 76 side 
ditch inlet transitions; remedial works along 16.6 
miles of channel in Canada or an acceptable alternative 
therefor; one new bridge; and alteration of the 
existing dam in Roseau Village. Remedial works will 
be constructed in Canada at the expense of the 
United States. Estimated cost (1983) to the United 
27-14

ST. PAUL MINNESOTA DISTRICT 
States for new work is $28,700,000, including 
$6,367,000 for cost of work in Canada to be accomplished 
with United States funds. Project was authorized 
by Flood Control Act of 1965 (H. Doc. 282, 89th 
Cong., 1st sess., contains latest published map.) 
Local cooperation. See Annual Report for 1968 
for requirements. Local interests have formed a 
Roseau River Watershed District to provide local cooperation 
requirements and acquire rights-of-way. 
Operations and results during fiscal year. 
New work: Planning activities were continued 
relative to coordination of the project plan with 
Canadian interests. Engineering and design and 
supervision and administration cost $114,116. 
Condition at end of fiscal year: Planning is in 
progress and coordination with Canadian interests is 
underway. The general design memorandum was 
submitted in October 1971 and approved in March 
1972. Design memorandum supplements which 
contain dimensions of environmental features added 
to the project were submitted in October 1975 and 
June 1980 and approved in November 1975 and July 
1980, respectively. An EIS supplement was filed with 
the EPA in October 1981. 
34. SHEPARD ROAD, MISSISSIPPI RIVER, 
ST. PAUL, MN 
Location. In Ramsey County along the Mississippi 
River in downtown St. Paul, Minnesota. 
Existing Project. The proposed project to protect 
the streambank from erosion which threatens 
Shepard Road is authorized under Section 14 of the 
1946 Flood Control Act, as amended. A reconnaissance 
report dated March 1983 recommended 
breaking existing grouted slope protection, placing 
approximately 6,700 cubic yards of rock fill and 
modifying existing storm sewer outfalls along the left 
bank of the Mississippi River from Wabasha Street to 
300 feet above Robert Street, a distance of about 900 
linear feet. 
Total Federal cost for the project is estimated at 
$250,000 (1983) which is the maximum permissible 
under Section 14. The project was approved by the 
Chief of Engineers for construction on June 6, 1983. 
The city of St. Paul has contributed $40,000 to the 
project. Final adjustment of the city's share will be 
made upon completion of the project. 
Local Cooperation. Local interests are required 
to provide without cost to the United States all lands, 
easements, and rights-of-way necessary for construction, 
operation, and maintenance of the project; 
accomplish without cost to the United States all 
required alterations and relocations in sewer, water 
supply, drainage, and other utility facilities; hold and 
save the United States free from damages due to the 
construction, operation, and maintenance of the 
project except where such damages are due to the 
fault or negligence of the United States or its contractors; 
maintain the project after completion; assume 
full responsibility for all project costs in excess of the 
Federal cost limit of $250,000; provide a cash contribution 
for project costs in proportion to any special 
benefits to non-public property; comply with 
applicable provisions of the Uniform Relocation 
Assistance and Real Property Acquisition Policies 
Act of 1970, Public Law 91-646, approved January 2, 
1971, in acquiring lands, easements, and rights-ofway 
for construction and subsequent maintenance of 
the project and inform affected persons of pertinent 
benefits, policies and procedures in connection with 
said Act; comply with Section 601 of Title VI of the 
Civil Rights Act of 1964 (Public Law 88-352) and 
Department of Defense Directive 5500.11 issued 
pursuant thereto and published in Part 300 of Title 
32, Code of Federal Regulations, in connection with 
the construction and subsequent maintenance and 
operation of the project. 
A local cooperation agreement required by Public 
Law 91-611 was adopted by the city of St. Paul in 
July 1983. 
Operations and results during fiscal year: 
New work: Engineering and design and study costs 
were $33,132. 
Condition at end of fiscal year: The construction 
contract for the erosion protection work was 
awarded in September 1983. 
35. SHEYENNE RIVER FLOOD CONTROL, 
ND (Formerly Kindred Lake) 
Location. The Sheyenne River basin is included in 
16 counties in the southeastern portion of North 
Dakota and drains an area of 7,140 square miles into 
the Red River of the North near Fargo, North Dakota. 
The principal area of flood damages in the basin is 
located at the lower end within Cass County and the 
city of West Fargo. The authorized Kindred Lake 
project is in Richland County, ND, on the Sheyenne 
River, about 70 miles above its mouth and 5 miles 
above Kindred, ND. (For general location, see Geological 
Survey map of North Dakota.) 
Existing project. The authorized project provides 
for a multiple-purpose impoundment for flood 
control, water quality control, recreation, and fish 
and wildlife purposes to control the runoff from 3,014 
square miles. The improvements would be coupled 
with a revised operating plan for the existing 
Baldhill Dam and with appropriate flood plain management 
measures at communities along the river. 
See Annual Report for 1973 for details. Project was 
authorized by 1970 Flood Control Act (H. Doc. 330, 
91st Cong., 2d sess., contains latest published map.) 
The General Reevaluation Report, completed in 1982, 
recommends implementation of a plan other than the 
authorized plan. The plan recommended in the 
General Reevaluation Report includes levees and 
diversions at West Fargo/Riverside, a flood diversion 
channel from Horace to West Fargo, and a five foot 
raise of the Baldhill Dam. The report also recommends 
deauthorization of the Kindred Lake project. 
The estimated Federal cost (1983) of the plan, based 
27-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
on traditional cost-sharing requirements, is 
$25,700,000. 
Local cooperation. See Annual Report for 1971 
for requirements of the project as authorized. On 
July 7, 1982, the North Dakota State Water Commission 
furnished a letter of support for the recommended 
plan for flood control in the lower Sheyenne 
River basin and also expressed its willingness to act 
as a non-Federal sponsor. On August 2, 1982 and 
July 30, 1982, respectively, the city of West Fargo and 
the Southeast Cass Water Resource District 
furnished letters of support and indicated their 
willingness to cooperate with the North Dakota State 
Water Commission. Formal assurances of local cooperation 
will be requested after completion of the 
Phase II General Design Memorandum. 
Operations and results during fiscal year. 
New work: Preconstruction planning was continued 
at a cost of $34,565. 
Condition at end of fiscal year: Preconstruction 
planning is in progress. Due to local concerns, a 
changed set of planning criteria, and potential 
changed conditions, a complete reformulation and reevaluation 
of alternatives was undertaken during 
preconstruction planning. The reevaluation studies 
showed that another alternative plan is more favorable 
than the authorized project. This alternative 
plan consists of a raise of Baldhill Dam, levees and a 
flood diversion channel at West Fargo, and a flood 
diversion channel from Horace to West Fargo. Other 
actions are also identified that could be taken by non- 
Federal interests to enhance the degree of flood 
damage reduction provided by the overall plan. This 
new plan represents a significant change from the 
authorized project and should be ready for recommendation 
to Congress for authorization in FY 1984. 
36. STATE ROAD AND EBNER COULEES, WI 
Location. In La Crosse County in west-central 
Wisconsin, on the south side of the city of La Crosse. 
(For general location, see Geological Survey map of 
Wisconsin.) 
Existing project. The plan of improvement for 
State Road Coulee provides for channel deepening 
and enlarging downstream from Hagen Bridge to the 
mouth, and includes 12,300 feet of concrete-lined, 
trapezoidal-shaped channel, 700 feet of riprap 
channel, a stilling basin, three new street bridges, 
and a new railroad bridge. The city recently replaced 
a fourth bridge, previously included in the authorized 
plan. Estimated cost (1983) to the United States for 
new work, exclusive of the Ebner Coulee portion of 
the project which was deleted due to lack of economic 
feasibility, is $24,700,000. Project was authorized by 
1968 Flood Control Act (H. Doc. 360, 90th Cong., 2d 
sess., contains published map.) 
Local cooperation. See page 826 of Annual 
Report for 1969. The local sponsor withdrew support 
for the project in 1976 citing increased non-Federal 
costs and lack of agreement on local cost sharing 
between three local units of government located 
within the project area. The project was reclassified 
as inactive on April 7, 1977 but was reactivated on 
November 8, 1978 after the La Crosse County Board 
of Supervisors, the La Crosse City Council, and the 
Town of Shelby passed separate resolutions on 
September 17, 1978, July 13, 1978, and July 10, 1978, 
respectively, which requested continuance of the 
project. All three groups reaffirmed their support by 
letter in July 1981. On October 4, 1982 the city of 
LaCrosse furnished a letter in further support for the 
project and acknowledged that it would serve as the 
local sponsor. 
Operations and results during fiscal year. 
New work: Preconstruction planning was continued 
at a cost of $178,742. 
Condition at end of fiscal year: Preconstruction 
planning is in progress. Ebner Coulee has been 
recommended for reclassification to "inactive" due to 
lack of economic feasibility. 
37. VETERAN'S MEMORIAL LEVEE, 
MISSISSIPPI RIVER, HASTINGS, MN 
Location. In Dakota County on the Mississippi 
River approximately 20 miles southeast of St. Paul, 
Minnesota. 
Existing Project. A section of bank along the 
Mississippi River between Highway 61 and 
Milwaukee Railroad bridges in Hastings is being 
threatened by erosion. Located within this 1,300 foot 
reach is a park (Veteran's Memorial Levee) which is 
historically significant because of the role of the area 
played during the riverboat era. Part of the park is 
occupied by a road which is an alternate route for 
emergency vehicles. The proposed project consists of 
placement of a 15 inch thick layer of riprap over 9 
inches of bedding for a distance of 1030 feet. 
Total Federal cost (1983) for the proposed project is 
estimated at $182,000. The project was approved by 
the Chief of Engineers for construction June 29, 1983 
under the authority contained in Section 14 of the 
1946 Flood Control Act, as amended. 
Local Cooperation. Local interests are required 
to provide without cost to the United States all lands, 
easements, and rights-of-way necessary for construction, 
operation and maintenance of the project; 
accomplish without cost to the United States all 
required alterations and relocations in sewer, watersupply, 
drainage, and other utility facilities; hold and 
save the United States free from damages caused by 
the construction, operation and maintenance of the 
project except where such damages are due to the 
fault or negligence of the United States or its contractors; 
maintain the project after completion in accordance 
with regulations prescribed by the Secretary of 
the Army; assume full responsibility for all project 
costs in excess of the Federal cost limit of $250,000; 
comply with the applicable provisions of the Uniform 
Relocation Assistance and Real Property Acquisition 
Policies Act of 1970, Public Law 91-646, approved 
27-16

ST. PAUL MINNESOTA DISTRICT 
January 2, 1971, in acquiring lands, easements and 
right-of-way for construction and subsequent maintenance 
of the project and inform affected persons of 
pertinent benefits, policies and procedures in connection 
with said Act; comply with Section 601 of Title 
VI of the Civil Rights Act of 1964 (P.L. 88-352) and 
Department of Defense Directive 5500.11 issued 
pursuant thereto and published in Part 300 of Title 
32, Code of Federal Regulations, in connection with 
the construction and subsequent maintenance and 
operation of the project. 
A local assurance agreement required by Public 
Law 91-611 was adopted by the city of Hastings in 
June 1983. 
Operations and results during fiscal year: 
New work: Contract costs for construction of bank 
protection measures cost $20,050. Engineering and 
design and supervision and administration costs 
were $7,498. 
Condition at end of fiscal year: A construction contract 
was awarded in September 1983. 
38. WILD RICE RIVER-SOUTH BRANCH 
AND FELTON DITCH, MN 
Location. In Clay and Norman Counties in westcentral 
Minnesota northeast of the city of Moorhead, 
MN. The South Branch of the Wild Rice River and 
Felton Ditch drain areas of 253 and 122 square miles 
and enter the Wild Rice River at points 29.5 and 20.5 
miles, respectively, above its confluence with the Red 
River of the North. (For general locations, see Geological 
Survey map of Minnesota.) 
Existing project. Provides for increasing the 
capacities of the South Branch and Felton Ditch 
channels by widening the existing channels through 
the floodplain. Debris removal would be accomplished 
in the lower reaches of both streams. In 
addition, short reaches of low dikes would be constructed 
on both banks of Felton Ditch near the upper 
limit of improvement. The plan also includes bridge 
and culvert structure alterations, new bridges, multiplate 
pipe arches, side ditch inlet and lateral ditch 
entry modifications, and a drop inlet structure. The 
project would provide flood protection in both 
watersheds for a 6-percent chance flood and outlets 
necessary for removal of crop-damaging surface 
waters from lateral and on-farm drainage systems. 
Project was authorized by 1968 Flood Control Act (H. 
Doc. 98, 90th Cong., 1st sess., contains latest published 
map.) 
Local cooperation. See page 826 of Annual 
Report for 1969 for requirements. A local assurance 
agreement in accordance with Section 221 of the 
Flood Control Act of 1970 was executed by the Wild 
Rice Watershed District on October 18, 1978. 
Operations and results during fiscal year. 
New work: Contract for channel modification cost 
$436,259 and a contract for levee modification cost 
$201,527. Engineering and design cost $19,952 and 
supervision and administration cost $48,406. 
Condition at end of fiscal year: Construction of the 
project is substantially complete. 
39. WINONA, MN 
Location. At Winona County in southeastern 
Minnesota on the right bank of the Mississippi River 
about 725 miles above mouth of Ohio River. (For 
general location see Geological Survey map of Minnesota.) 
Existing project. See page 833 of Annual Report 
for 1968 for completed upstream improvements 
authorized by the Flood Control Act of 1958 
providing for a continuous flood barrier about 6.1 
miles long with related pumping and interior 
drainage facilities. Federal costs amounted to 
$2,147,131 of which $111,500 was expended for the 
portion then deferred for restudy and $17,316 was 
contributed by local interests. 
Improvement authorized in 1971 under Section 201 
of the Flood Control Act of 1965 (H. Doc. 152, 92d 
Cong., 1st sess., contains latest published map) 
provides for levee and floodwall protection with 
necessary interior drainage works for the riverfront 
and the Lake Winona closure reaches, as well as a 
sound floodplain management program to prevent 
unwise development of the area bordered by U.S. 
Highway 61 and Burns Valley and Pleasant Valley 
Creeks. The plan would also provide the downstream 
flood barrier needed to prevent Mississippi River 
backup flows from entering Lake Winona and 
inundating the area now only partially protected by 
the completed segment of the project authorized by 
the 1958 Flood Control Act. The selected plan would 
also provide control of Burns Valley Creek by means 
of channel improvement, raising and extending the 
existing levee system, a drop structure, an erosion 
control structure, alteration of two highway bridges, 
and a sewer line modification. Earth levees averaging 
10 feet in height total approximately 3.1 miles in 
length. Concrete floodwalls, also averaging about 10 
feet in height, total about 2,025 feet in length. Estimated 
Federal cost (1983) for new work is $30,000,000 
and $570,000 is to be contributed by local interests. 
Resolutions authorizing the project were adopted by 
the Public Works Committees of the House on 
July 29, 1971, and the Senate on November 18, 1971. 
Local cooperation. Fully complied with for completed 
work. See page 833 of Annual Report for 1968 
for requirements. 
For improvements authorized in 1971 see Annual 
Report for 1972 for requirements. A local cooperation 
agreement required under Section 221 of the 1970 
Flood Control Act was executed by the city of Winona 
on October 6, 1978. 
Operations and results during fiscal year. 
New work: Construction contracts for Reaches A, B, 
C, D and E cost $617, $293,371, $508,949, $698,131 
and $357,321, respectively, and a railroad relocation 
contract for Reach B cost $100,000. Pumping station 
contracts cost $1,792,452 and a dredge fill contract 
27-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
cost $2,139,999. Engineering and design cost $96,064 
by contract $11,738 by other government agencies, 
and $181,975 by hired labor. Supervision and administration 
and other miscellaneous costs were 
$289,511. 
Condition at end of fiscal year: The upstream 
improvement except for a portion of the project 
raising and extending the existing levee downstream 
from the Lake Winona outlet was completed in 
August 1967. At the request of local interests, the uncompleted 
portion of the project authorized in 1958 
was not constructed in order that the scope of the 
project could be reconsidered to allow for the protection 
of additional lands needed by the city for 
industrial expansion. This work was deferred for 
restudy and now has been deauthorized by approval 
and authorization in 1971 of additional protection for 
Winona. Preconstruction planning for the improvement 
authorized in 1971 is complete. Construction on 
Reaches A, C, D, E-1 and E-2 is completed. Construction 
on Reaches B-1 and B-2 is in progress. 
40. INSPECTION OF COMPLETED FLOOD 
CONTROL PROJECTS 
Flood control projects turned over to local interests 
were inspected to determine that project channels are 
kept clean and unobstructed, dikes and revetments 
are in good condition, and structures are in good 
repair and operable. Deficiencies, if any, were minor 
unless noted. (See table 27-K on inspection of completed 
flood control projects.) 
Cost for the period was $70,620. Total cost to 
September 30, 1983 is $637,287. 
General Investigations 
41. SURVEYS 
Navigation studies continued at a cost of $19,318. 
Flood control studies continued at a cost of 
$2,282,319. Coordination studies with other agencies, 
miscellaneous activities, and Phase I preauthorization 
studies at Pembina River, ND and Grafton, ND 
were conducted at a cost of $574,315. See sections 13 
and 24 in text for details of Grafton and Pembina 
River projects. Total cost of surveys for the period 
was $2,875,952. 
42. COLLECTION AND STUDY OF BASIC 
DATA 
Costs during the period were $32,556 for International 
Water Studies and $172,276 for Flood Plain 
Management Services. Costs were $49,972 for stream 
flow data obtained by Corps gaging beyond cooperative 
stream-gaging program, and for hydraulic laboratory 
work in measurement and analysis of sediment 
load in streams. Costs were $856 for inspection 
and inventory of dams in conjunction with the 
national program of inspection of non-Federal dams. 
Total cost for collection and study of basic data was 
$255,660. 
43. ADVANCE ENGINEERING AND DESIGN 
Costs during the period were $1,305,265 for 
advance engineering and design projects. For details 
of individual projects see sections 6, 9, 29, 32, 35, and 
36 in text. 
44. OTHER WORK UNDER SPECIAL 
AUTHORITY 
In the Aquatic Plant Control program (Section 302, 
Public Law 298, 89th Congress) a contract with the 
Waterways Experiment Station to evaluate mechanical 
methods of plant control operations in Buffalo 
Lake, WI cost $9,675, coordination with the state of 
Wisconsin and aerial photography cost $4,644 and 
administrative costs were $112. 
27-18

ST. PAUL MINNESOTA DISTRICT 
TABLE 27-A COST AND FINANCIAL STATEMENT 
See Total Cost to 
Section September 30 
In Text Project Funding FY80 FY81 FY82 FY83 1983 
1. Minnesota River, 
MN 
3. Reservoirs at 
Headwaters of 
Mississippi 
River, MN 
4. St. Croix River 
MN and WI 
5. Warroad Harbor 
and River, MN 
6. Bassett Creek, 
MN 
7. Big Stone Lake 
and Whetstone 
River, MN and 
SD 
8. Burlington Dam 
Souris River, 
ND 
9. Chaska, MN 
10. Devils Lake, ND 
11. Eau Galle River, 
WI 
12. Enderlin, Maple 
River, ND 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Maj. Rehab: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
22,000 
21,944 
30,000 
122,195 
1,095,000 
1,197,737 
- 
178,000 
171,072 
31,100 
27,945 
387,000 
382,567 
109,000 
115,313 
102,000 
102,569 
149,568 
244,000 
261,605 
55,000 
33,221 
- 
398,000 
456,089 
75,000 
53,446 
143,000 
142,178 
-14,200 
7,649 
1,146,000 
1,134,443 
1,000 
7,938 
15,000 
17,249 
250,000 
300,621 
125,000 
108,599 
100,500 
97,295 
25,000 
53,971 
240,000 
248,430 
100,000 
102,911 
773,800 
545,148 
40,000 
68,804 
- 
434,000 
37,251 
4,000 
4,218 
1,122,000 
1,073,719 
- 
106,000 
9,025 
221,020 
48,225 
425,000 
415,765 
490,000 
365,467 
803,000 
189,512 
17,508 
200,000 
183,115 
60,000 
54,547 
- 
219,000 
468,855 
160,000 
33,900 
- $2,057,7221 
- 2,057,7221 
420,000 2,223,186 
419,039 1,824,598 
- 4,398,6282 
-- 4,398,6282 
1,548,000 18,023,8583 
1,496,946 17,856,4363 
- 425,000 
- 425,000 
- 150,410 
- 150,410 
-97,000 " 947,255 
-7,956 939,324 
- 86,105 
- 86,105 
44,0004 1,045,400 
199,9064 1,027,605 
435,000 1,675,000 
416,333 1,640,966 
575,000 10,390,000 
473,040 10,143,8716 
208,000 1,574,200 
800,572 1,549,578 
- 5,568,500 
574 5,567,535 
225,000 1,109,000 
242,018 1,107,220 
275,000 490,000 
159,656 350,335 
- 9,039,250 
- 9,039,250 
263,000 3,449,105 
261,079 3,422,711 
910,000 1,472,000 
386,927 820,611 
27-19

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 27-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost to 
Section September 30 
In Text Project Funding FY80 FY81 FY82 FY83 1983 
14. Homme Lake and 
Dam, ND 
15. Irving Township, 
Jackson County, 
WI 
16. Lac qui Parle 
Lakes, MN 
18. La Farge Lake 
and Channel 
Imp., WI 
19. Lake Ashtabula 
and Baldhill 
Dam, Sheyenne 
River, ND 
20. Lake Darling, 
Souris River, ND 
21. Lake Traverse 
and Bois de Sioux 
River, SD 
and MN 
22. Mankato and 
North Mankato, 
MN 
23. Minot, ND 
25. Prairie du Chien, 
WI 
26. Red Lake River at 
Huot, MN 
27. Red Lake River at 
Red Lake Falls, MN 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
97,000 268,000 113,000 
77,467 267,360 133,026 
9,000 
- 8,993 
97,000 
57,991 
70,000 110,600 
10,708 164,089 
320,000 203,000 203,000 184,000 
318,827 187,895 176,117 168,297 
- 120,000 
5,792 339,802 
744 
200 
200 
1,396,0976 
1,396,0976 
1,950,421 
1,909,498 
189,600 
183,790 
$964,873 
964,873 
3,208,163 
3,148,072 
- 550,000 18,642,000 
12,810 336,849 18,428,014 
18,000 
15,864 
18,000 
1,551 
22,000 
17,656 
16,268 
1,685,000 366,000 513,000 842,000 
1,141,031 1,008,809 931,357 786,048 
- - 800,000 1,150,000 
- - 660,376 1,176,694 
180,000 174,000 180,000 190,000 
154,650 196,171 143,241 186,053 
40,000 
33,520 
3,325,6387 
3,325,4577 
9,836,112 
9,701,199 
1,950,000 
1,837,070 
1,339,727 
1,339,727 
2,465,619 
2,419,799 
5,000,000 4,150,000 6,016,000 5,950,000 49,149,500 
5,043,149 4,293,918 6,316,353 5,169,491 48,202,171 
- 160,000 
111,989 285,810 24,726 
-- 21,479,500 
14,019 21,479,2068 
875,000 1,000,000 1,050,000 161,000 
859,040 992,811 888,843 29,549 
- - - 64,500 
- - - 11,626 
- - - 131,000 
- - - 17,582 
4,020,000 
3,699,615 
64,500 
11,626 
131,000 
17,582 
27-20

ST. PAUL MINNESOTA DISTRICT 
TABLE 27-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost to 
Section September 30 
In Text Project Funding FY80 FY81 FY82 FY83 1983 
28. Red Lake River, New Work: 
MN, including Approp. 
Clearwater Cost 
River, MN Maint: 
Approp. 
Cost 
29. Red River of the New Work: 
North Drainage Approp. 
Basin, MN, Cost 
SD and 
ND Maint: 
Approp. 
Cost 
30. Red River of the New Work: 
North at Halstad, MN Approp. 
Cost 
31. Red River of the New Work: 
North at Oslo, Approp. 
MN Cost 
32. Rochester,MN New Work: 
Approp. 
Cost 
33. Roseau River, New Work: 
MN Approp. 
Cost 
34. Shepard Road, New Work: 
Mississippi River, Approp. 
St. Paul, MN Cost 
35. Sheyenne River, New Work: 
ND (formerly Approp. 
Kindred Lake) Cost 
36. State Road & New Work: 
Ebner Coulees, Approp. 
WI Cost 
37. Veteran's Memorial New Work; 
Levee, Mississippi Approp. 
River, Hastings, MN Cost 
38. Wild Rice River, New Work: 
South Branch Approp. 
and Felton Cost 
Ditch, MN 
39. Winona, MN New Work: 
Approp. 
Cost 
- 3,120,079y 
- 3,120,079 ' 
32,000 
32,000 
141,000 
104,374 
48,100 
48,009 
50,000 
41,747 
161,000 124,000 
196,973 121,593 
153,000 172,000 139,000 
222,273 164,830 159,738 
80,000 60,000 
28,827 109,998 
17,2-1075,205 
54,000 
34,383 
175,000 
174,255 
152,000 
152,388 
75,000 296,000 
67,370 156,373 
- 450,000 
17,517 35,321 
-25,000 
366,059 
550,000 330,000 535,000 316,000 
486,812 487,806 515,705 259,351 
145,000 
145,482 
100,000 500,000 
82,644 354,867 
691,802 
663,841 
7,098,984 " 
7,095,179' " 
2,318,534 
2,311,011 
516,000 
367,568 
1,960,200 
1,935,738 
2,380,000 
2,301,308 
- $1,878,000 
114,116 1,827,408 
- 250,000 
- 33,132 
387,000 250,000 178,000 
394,317 271,488 142,475 
150,000 254,000 195,000 
139,641 220,423 238,956 
34,565 
202,000 
178,742 
- - - 182,000 
- -- -- 27,548 
150,000 1,815,000 1,859,000 225,000 
149,510 1,331,793 1,826,389 706,144 
250,000 
33,132 
2,275,000 
2,273,580 
1,107,000 
1,083,691 
182,000 
27,548 
4,534,700 
4,498,379 
3,600,000 4,345,000 7,844,000 6,850,000 27,594,131 
4,405,217 4,368,053 7,858,873 6,470,128 27,185,80311 
'Includes $117,542 for new work for previous project. 
Excludes $359,202 contributed funds. 
'Includes $681,805 for new work for previous projects. 
3Includes $100,857 for maintenance for previous 
projects. 
4Includes $11,000 appropriated and $10,249 expended in 
FY 1983 for condition surveys. 
5Excludes $145,541 contributed funds. In addition, 
$18,879 in other contributed funds have been expended for 
work under Government contract paid for by the Ottertail 
Power Company. 
6Excludesa $56,220 contributed funds. 
7Excludes $208,000 contributed funds. 
TExcludes $2,052 contributed funds. 
9Excludes $30,020 contributed funds. 
1�Includes cost of the Wahpeton-Breckenridge unit, 
$11,239, which is classed as "inactive" and the units on 
which authorization has expired: Maple River, $1,241; 
Moorhead, $27,700; Sheyenne, $37,956. In addition, 
$203,874 special deposit funds and $146,160 in other 
contributed funds have been expended for work under 
Government contract paid for by local interests. 
"Excludes $490,803 contributed funds. In addition, 
$69,540 in other contributed funds have been expended for 
work under Government contract paid for by local interests. 
27-21 
-

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 27-B AUTHORIZING LEGISLATION 
See 
Sec. Date of 
in Authorizing 
Text Act Project and Work Authorized " Documents 
MINNESOTA RIVER, MN 
1. July 13, 1892 
July 3, 1958 
3. Mar. 3, 1899 
Mar. 2, 1907 
June 25, 1910 
July 27, 1916 
June 26, 19342 
4. June 18, 1878 
June 3, 1896 
Jan. 21, 1927 
Aug. 30, 1935 
May 17, 1950 
5. Mar. 3, 1899 
June 6, 1900 
June 13, 1902' 
Mar. 3, 1905 
June 25, 1910 
July 25, 1912 
Open-channel improvement from mouth to Shakopee to obtain 
a channel of 4-foot depth to accommodate vessels with 3-foot 
draft. 
Dredging to provide channel of 9-foot depth from mouth to mile 
14.7 
RESERVOIRS AT HEADWATERS OF MISSISSIPPI 
RIVER, MN 
Reconstruct 4 of the 5 original dams and surveys to determine 
extent of lands overflowed by reservoirs. 
Reconstruct Sandy Lake Dam and construct Gull Lake 
Reservoir. 
Construct an equalizing canal between Winnibigoshish and 
Leech Lake Reservoirs (no work was done and this part of the 
project abandoned in Act of Mar. 4, 1915.) 
Abandonment of ditches connecting Long Lake, Round Lake, 
and Gull Lake. 
Operation and maintenance provided for with funds from War 
Department appropriations for rivers and harbors. 
ST. CROIX RIVER, MN AND WI 
Dredging, etc., for a 3-foot channel between mouth and Taylors 
Falls. 
Harbor and waterfront at Stillwater. 
A 6-foot channel to Stillwater. 
The 9-foot channel from mouth to Stillwater. 
Small-boat harbor at Hudson. 
WARROAD HARBOR AND RIVER, MN 
Dredging bar at mouth of Warroad River. 
Entrance channel 300 feet wide and 7 feet deep. 
Enlarging turning basin 
Annual Report 1891. p. 2209 
S. Doc. 144. 84th Cong., 2d 
sess.' 
H. Doc. 363, 61st Cong., 2d 
sess. 
H. Doc. 413, 64th Cong., 1st 
sess. 
1 
H. Ex. Doc. 75, pt. 6, 43rd 
Cong., 2d Sess;4 Annual 
Report 1875, p. 372. 
H. Doc. 378, 69th Cong., 1st 
sess. 4 
H. Doc. 184, 72nd Cong., 1st 
sess.4 
H. Doc. 184, 81st Cong., 1st 
sess.4 
Specified in Act. 
H. Doc. 92, 56th Cong., 2d 
sess88. 5 
H. Doc. 703, 61st Cong., 2d 
sess88. 5 
Deepening to 8 feet. 
'Contains latest published map. 
2Permanent Appropriations Repeal Act. 
'Appropriation. 
4See H. Doc. 462, 71st Congress, 2d sess., for latest 
published map. 
5Latest published map is opposite p. 1984 in Annual 
Report for 1911. 
27-22

ST. PAUL MINNESOTA DISTRICT 
TABLE 27-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost To September 30,1983 
Full Report 
See Annual Operation And 
Project Status Report For Construction Maintenance 
Baudette Harbor, MN Completed 1961 $36,415 $57,768 
Black River, WI 1 1950 67,585 - 
Lake Traverse, MN and SD . 1921 92 - 
Mississippi and Leech Rivers, MN Completed' 1929 277,615 40,251 
Mississippi River between Brainerd and 
Grand Rapids, MN s 1925 47,794 3,891 
Pine Creek, Angle Inlet, MN Completed 1978 38,700 102,196 
Red Lake and Red Lake River, MN Completed3 1923 9,070 - 
Red River of the North, MN and ND 3.6 1921 293,344 76,209 
Wisconsin River, WI .3 1888 -- -- 
Zippel Bay Harbor, MN Inactive5 1928 27,941 11,139 
i,IQtw 1 i /-1h,,q A . .. l .d, . A f.... . . . . M.. ' .a"AIN T . .. . . .... .... _. _11 
xisung cnannei aaequate or commerce (see table 27- G for deauthorized portion of project). 
2Originally included in project 'Fox and Wisconsin 
Rivers, WI'. Abandonment of improvement of Wisconsin 
River by channel contraction works recommended in 1886 
and 1887 (H. Ex. Doc. 65, 49th Cong., 2d sess.). Expenditures 
included under 'Fox and Wisconsin Rivers, WI'. No breakdown 
available. 
"N4o commerce reporteu. 
4Abandonment recommended in 1915 (H. Doc. 439, 64th 
Cong., 1st sess.) and June 24, 1926 (H. Doc. 467, 69th Cong., 
1st seas.). 
5Abandonment recommended June 24, 1926 (H. Doc. 
467, 69th Cong., 1st sess.). 
6Abandonment recommended in 1915 (H. Doc. 1666, 63d 
Cong., 3d sess.). 
27-23

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 27-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost To September 30,1983 
Full Report 
See Annual Operation And 
Project Status Report For Construction Maintenance 
Dry Run, IA Completed 1966 $1,790,7598 - 
Elk River, MN Completed 1970 259,7002 - 
Guttenberg, IA Completed 1974 2,361,915 - 
Lost River, MN Completed 1967 517,5193 - 
Lower Branch Rush River, ND' Completed 1974 1,000,0004 - 
Marshall, MN Completed 1964 1,802,866 - 
Minneota, MN' Completed 1963 161,545 - 
Mississippi River near Aitkin, MN Completed 1957 1,675,835 - 
Pembina River Lake, ND Inactive6 1950 50,000 - 
Red River of the North at Pembina, ND' Completed 1979 2,000,000 - 
Redwood River below Marshall, MN' Completed 1960 202,400 - 
Rushford, MN Completed 1980 3,192,333 - 
St. Paul and South St. Paul, MN Completed 1974 8,476,0127 - 
Tongue River Lake, ND Inactive6 1950 23,695 - 
Twin Valley Lake, Active/no FY83 1982 1,911,700 - 
Wild Rice River, MN expenditure 
Upper Iowa River, IA Completed 1964 888,445 - 
Velva, ND' Completed 1970 334,628 - 
Vermillion River, Hastings, MN' Completed 1980 999,900 - 
Warroad River and Bull Dog Creek, MN Inactive5 1974 182,000 - 
Zumbro River, MN Completed 1975 1,284,100 - 
'Project authorized by Chief of Engineers under small 
project authority, section 205, 1948 Flood Control Act, as 
amended. 
2In addition $87,878 was expended from Public Law 99 
funds in the spring of 1969 for emergency protection and 
incorporation into the permanent project. 
;Excludes $46,034 for the Ruffy Brook unit for which 
authorization expired in April 1966 (see table 27-G). 
Excludes $246,911 contributed funds. 
4Excludes $35,000 contributed funds. 
5Preconstruction planning suspended. Local interests 
requested the project be reclassified to inactive due to a 
limitation of their funding capability. The project was classified 
inactive on April 5, 1974. 
6Further work deferred pending review of project 
document (inactive). 
7Excludes $545,637 contributed funds for new work and 
$38,000 expended by South St. Paul for work in lieu of 
required cash contribution. Excludes an additional $206,629 
expended for work done at request of local interests. 
8Excludes $42,766 contributed funds. 
27-24

TABLE 27-G 
ST. PAUL MINNESOTA DISTRICT 
DEAUTHORIZED PROJECTS 
For Last 
Full Report Federal Contributed 
See Annual Date Funds Funds 
Project Report For Deauthorized Expended Expended 
Black River, WI' 1950 Aug. 5, 1977 - - 
Black River Lake, WI 1950 Aug. 5, 1977 - - 
Maple River, ND2 1981 Oct. 26, 1961 $1,241 - 
Moorhead, MN2 1981 Oct. 30, 1961 27,700 - 
Ruffy Brook, MN 1967 Apr. 1966 46,034 - 
Sheyenne River, ND2 1981 Dec. 31, 1970 37,956- 
Warroad Harbor and River, MN 3 1981 Aug. 5, 1977 - - 
'Portion of project for removal of obstructions at Section 29 in text and table 27-J for costs for active units of 
various points outside the dredged area to clear channel to the project). 
full project width (see table 27-C for costs for completed 3Portion of dredging of entrance channel and turning 
portion of project). basin to complete project width and depth (see table 27-A for 
2Part of Red River of the North Drainage Basin (see costs for completed portion of project). 
27-25

TABLE 27-H RESERVOIRS AT HEADWATERS OF 
MISSISSIPPI RIVER 
(See Section 3 of Text) 
Outlet Watershed Area (square miles) Capacity Previous Projects Existing Projects 
at 
Minimum Above Watershed Maximum 
Stages St. Paul (square Original Stage Com- Com- Total 
Reservoir (feet)' River (miles) miles) Lake Reservoir (acre-feet) pleted Cost pleted Cost Cost 
Winnibigoshish 6 Mississippi 408 1,442 117 179.4 967,930 1884 $214,000 1900 $173,470 $387,470 
Leech Lake 0 Leech 410 1,163 173 250.9 743,320 1884 171,805 1902 84,380 256,185 
Pokegama 6 Mississippi 344 6602 24 35.0 120,750 1884 85,000 1904 126,030 211,030 
Sandy Lake 7 Sandy 267 421 8 16.6 72,500 1895 114,000 1909 117,020 231,020 
Pine River 9 Pine 199 562 18 23.7 177,520 1886 97,000 1907 133,320 230,320 
Gull Lake 5 Gull 168 287 20 20.5 70,820 - - 1913 86,826 86,826 
Surveys and flowage rights - - - - 160,939 160,939 
Recreational facilities - - - 2,834,838 2,834,838 
Total new work - - 681,805 - 3,716,823 4,398,628 
Total operating and care - - 100,857 - 16,788,382 16,889,239 
Permanent indefinite appropriation 
for operatmng and care, web. 1, 1895 
to end of fiscal year 1936 - - - 967,197 967,197 
Rehabilitation - - - 425000 425,000 
Total 2,152,840 - $782,662 - $21,897,402 $22,680,064 
'Lower operating limits by regulations approved February 4, 1936, as modified December 29, 1944. 
2Exclusive of area controlled by 'Winnibigoshish and Leech Lake Dams.

ST. PAUL MINNESOTA DISTRICT 
TABLE 27-I NAVIGATION WORK UNDER SPECIAL AUTHORIZATION 
Navigation Activities Pursuant to Section 107 Public Law 86-645 
(preauthorization) 
Study identification Fiscal Year Costs 
Zippel Bay, Lake of the Woods Co., MN $79,090 
TABLE 27-J RED RIVER OF THE NORTH DRAINAGE BASIN: 
ACTIVE UNITS IN COMPREHENSIVE BASIN PLAN 
(See Section 29 of Text) 
Total 
Cost to Estimated 
Name of Unit State Type September 30, 1983 Federal Cost 
Orwell Reservoir (Otter Tail River) Minnesota Reservoir $1,916,758 $1,916,700' 
Wild Rice and Marsh Rivers Minnesota Channel improvement 405,056 405,100 
Rush River North Dakota Channel improvement 287,686 287,000 
Sand Hill River Minnesota Channel improvement 548,778 548,800 
Mustinka River Minnesota Channel improvement 440,788 440,800 
Otter Tail River Minnesota Channel improvement 174,768 174,800 
Red River at Grand Forks North Dakota Levees and floodwall 948,895 948,900 
Red River at East Grand Forks Minnesota Levees, floodwall, 
pumping plants 654,395 12,900,000 
Red River at Fargo North Dakota Channel improvement, 
levees 1,639,924 1,639,900 
Total cost to date 7,017,043' 
Total estimated cost 19,262,0004 
'Includes $178,000 for lands and $25,000 for recreation 
facilities. 
2Includes $67,900 for lands. 
3Costs of $11,239 for the Wahpeton-Breckenridge 
inactive unit not included. Authorization of the Sheyenne 
River, Moorhead, and Maple River units has expired. Cost 
of these units also not included total $66,897. 
4The Wahpeton-Breckenridge unit of the project is 
classed as 'inactive' and is excluded from the estimate. The 
cost of this unit, last revised in 1955, was estimated to be 
$996,000. The Flood Control Act approved December 31, 
1970 (H. Doc. 330-91-2) provided for deletion of the 
Sheyenne River unit, and authorization of the Maple River 
and Moorhead units expired at the end of the 5-year period 
within which local interests were required to furnish 
assurances of local cooperation. Authorization of these 
units, not included, expired on the dates indicated in table 
27-G. 
27-27

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 27-K INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS 
(See Section 40 of Text) 
Project Date Inspected 
Arcadia, W I................................ ............................... Novem ber 1982 
Black River (North Bend), WI..............................................November 1982 
Clearwater River, MN......................................................November 1982 
Cochrane, W I ............................................................... November 1982 
Decorah, IA ................................................................... August 1983 
Elk River, MN ............................................................. November 1982 
Enderlin, ND ................................................................. August 1983 
Fargo, ND .................................................................... August 1983 
Grand Forks, ND ............................................................. August 1983 
Guttenberg, IA ................................................................ August 1983 
Hastings, M N .............................................................. Septem ber 1983 
Lost River, M N ............................................................ November 1982 
Lower Branch Rush River, ND............................................. November 1982 
Mankato, MN .............................................................. September 1983 
M arshall, M N .............................................................. September 1983 
Marsh River, MN .......................................................... November 1982 
M ines Creek, W I .............................................................. October 1982 
Minneota, MN ............................................................. Septem ber 1983 
M inot, ND .................................................................... August 1983 
Mustinka River, MN ....................................................... November 1982 
North Mankato, MN ....................................................... September 1983 
Ottertail River, MN ........................................................ November 1982 
Park River, ND .................................................. November-December 1982 
Pembina, ND ................................................................. August 1983 
Red Lake River, MN ....................................................... November 1982 
Redwood River, MN......................................................... November 1982 
Rushford, MN.............................................................November 1982 
Rush River, ND............................................................ November 1982 
Sand Hill River, MN ....................................................... November 1982 
Sheyenne River, ND ....................................................... November 1982 
South St. Paul, MN ........................................................ September 1983 
St. Paul, M N .................................................................. August 1983 
Upper Iowa River, IA ......................................................... August 1983 
Velva, ND ................................................................. Novem ber 1982 
Wild Rice River, MN ....................................................... November 1982 
Winona, M N ............................................................... November 1982 
Zumbro River, MN ......................................................... November 1982 
27-28

ST. PAUL MINNESOTA DISTRICT 
TABLE 27-L FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control activities pursuant to section 205, Public Law 858, 
80th Congress, as amended (preauthorization) 
Study Identification Fiscal Year Costs 
Argyle, MN, Middle River $46,394 
English Coulee, Grand Forks, ND 16,469 
Red River of the North, Argusville, ND 55,178 
Snake River below Warren, MN 54,056 
Emergency bank protection (Section 14 of 
the 1946 Flood Control Act, Public Law 526, 79th Congress). 
Project and Location Fiscal Year Costs 
Warner Road, Mississippi River, St. Paul, MN $8,173 
Emergency flood control activitiesrepair, 
flood fighting, and rescue work 
(Public Law 99 84th Cong., and antecedent legislation). 
Project Fiscal Year Costs 
Disaster preparedness $108,244 
Emergency operations 3,391 
Total emergency flood control activities 111,635 
Snagging and clearing navigable streams and 
tributaries in the interest of flood control 
(Section 208, 1954 Flood Control Act, Public Law 780, 83rd Congress). 
Project and Location Fiscal Year Costs 
Plum Creek, New Haven Township, MN $19,924 
27-29

ROCK ISLAND, IL, DISTRICT* 
This district comprises most of the northern half of 
Illinois, portions of southern Wisconsin, southern and 
southwestern Minnesota, eastern and central Iowa, 
and northeastern Missouri, embraced in drainage 
basin of Mississippi River and its eastern and western 
tributaries between mile 300 (above mouth of Ohio 
River) and 614, and of its eastern tributaries only, 
between Hamburg Bay, at mile 261 and 300. This district 
also includes the Illinois Waterway above mile 80 
with its tributaries and drainage basins. The section.. 
of the Mississippi River between river miles 300 and 
614 is included in the report on Mississippi River 
between Missouri River and Minneapolis, MN. 
IMPROVEMENTS 
Navigation Page 
1. Illinois Waterway, IL and IN .............. 28-2 
2. Illinois and Mississippi Canal, IL ......... 28-2 
3. Mill Creek and South Slough at Milan, IL... 28-3 
4. Mississippi River between Missouri River 
and Minneapolis, MN ..................... 28-3 
5. Other Authorized Navigation Projects ...... 28-3 
6. Navigation Work Under Special 
Authorization.............................28-3 
Flood Control 
7. Ackerman Creek, Tazewell County, IL ...... 28-3 
8. Appanoose Township, 
Hancock County, IL.......................28-3 
9. Bettendorf, IA ............................ 28-3 
10. Burlington, IA ............................ 28-4 
11. Coralville Lake, IA ........................ 28-4 
12. Davenport, IA ............................. 28-4 
13. DePue, IL ................................. 28-4 
14. East Moline, IL ........................... 28-4 
15. Evansdale, IA ............................ 28-5 
16. Farm Creek, IL ........................... 28-5 
17. Fort Madison, IA .......................... 28-5 
18. Fulton, IL ................................ 28-5 
19. Hannibal, MO ............................ 28-5 
20. M ilan, IL ................................. 28-6 
21. M oline, IL ................................ 28-6 
22. Monroe County, IA, Highway Bridges ..... 28-6 
23. Muscatine, Mad Creek, IA.................28-6 
24. Red Rock Dam and Lake Red Rock, IA ....... 28-6 
25. Rockford, IL .............................. 28-7 
26. Rock River Agricultural Levees, IL ........ 28-7 
27. Saylorville Lake, IA.......................28-7 
28. South Fabius River, Knox County, MO ..... 28-8 
29. Waterloo, IA .............................. 28-8 
Flood Control (Cont'd) Page 
30. Inspection of Completed Flood 
Control Projects...........................28-8 
31. Other Authorized Flood Control Projects .... 28-8 
32. Flood Control Work Under Special 
Authorization.............................28-8 
General Investigations 
33. Surveys...................................28-8 
34. Collection and Study of Basic Data ........ 28-9 
Tables 
Table 28-A 
Table 28-B 
Table 28-C 
Table 28-D 
Table 28-E 
Table 28-F 
Table 28-G 
Table 28-H 
Table 28-I 
Table 28-J 
Table 28-K 
Table 28-L 
Table 28-M 
Table 28-N 
Cost and Financial Statement ..... 28-10 
Authorizing Legislation...........28-12 
Other Authorized Navigation 
Projects .......................... 28-15 
Not applicable 
Other Authorized Flood 
Control Projects .................. 28-16 
Not applicable 
Deauthorized Projects............28-18 
Inspection of Completed Flood 
Control Projects ................. 28-18 
Flood Control Work Under Special 
Authorization....................28-20 
Illinois Waterway: Existing 
Locks and Dams ................. 28-21 
Illinois Waterway: Lock and Dam 
Construction, Foundations, Cost .. 28-22 
Illinois Waterway: Additional 
Features Entering into Cost ....... 28-23 
Illinois Waterway: Existing 
Project .......................... 28-24 
Illinois Waterway: Total Cost of 
Existing Project ................. 28-24 
28-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Navigation 
1. ILLINOIS WATERWAY, IL AND IN 
Location. Illinois River (entirely within State of 
Illinois), formed by confluence of Kankakee and Des 
Plaines River, flows southwesterly and enters Mississippi 
at Grafton, IL, about 38 miles above St. Louis. 
Illinois Waterway comprises Illinois River from its 
mouth to confluence of Kankakee and Des Plaines 
Rivers (273 miles); Des Plaines River to Lockport (18.1 
miles) and Chicago Sanitary and Ship Canal and 
South Branch of Chicago River to Lake Street, Chicago 
(34.5 miles). Also from a point 12.4 miles above 
Lockport, IL, waterway comprises Calumet-Sag Channel 
and Little Calumet and Calumet Rivers to turning 
basin 5, near entrance to Lake Calumet (23.8 miles); 
and Grand Calumet River from junction to 141st 
Street, deep (lake) draft navigation (9 miles) and to 
Clark Street, Gary, IN (4.2 miles). 
Previous Projects. For details, see page 1945 of 
Annual Report for 1915 and page 1172 of Annual 
Report for 1932. 
Existing project. See table 28-K and page 1255 of 
Annual Report for 1963. Cost of new work is 
$124,041,436 and includes $445,000 for Recreation 
Facilities under Code 711. Calumet-Sag Modification, 
Part II, placed in the inactive category in June 1973, 
cost of $132,000,000 (July 1972) Federal and 
$16,300,000 (July 1972) non-Federal; Calumet-Sag 
Modification, Part III, placed in the deferred-forrestudy 
category in March 1972, cost of $33,000,000 
(July 1971) Federal and $20,700,000 (July 1971) non- 
Federal; widen Pekin Bend, a portion of work authorized 
by River and Harbor Act of 1935, placed in the 
inactive category, cost of $1,360,700 (July 1972) Federal; 
and widen Marseilles Canal to 300 feet, a portion 
of work authorized by River and Harbor Act of 1935, 
placed in the deferred category, cost of $1,859,300 
(July 1972) Federal, are all excluded from present cost 
estimate. 
(See also tables 28-J through 28-N on authorizing 
legislation; existing locks and dams; lock and dam 
construction, foundations, cost and additional features 
entering into cost of project.) 
Local cooperation. Complied with for completed 
modifications and Part I of Calumet-Sag Modification. 
All pools above Alton Pool: 
Maintenance: Channel dredging by Government 
cutterhead pipeline dredge WILLIAM A. THOMPSON 
was performed at three locations in LaGrange 
pool at a cost of $439,500, with a total of 322,808 cubic 
yards of material being removed. Strike removal and - 
snagging was accomplished with hired labor at various 
locations at a cost of $353,300. Contract and S&I 
expenditures at the Lucas-Berg Disposal Area, a containment 
area for contaminated dredged material 
from the Calumet-Sag Channel, were $1,175,300. 
Structural repairs to dams were performed by hired 
labor at a cost of $388,100, and hired labor repairs to 
eight lock structures was performed at a cost of 
$716,400. Contractors earned $247,000 for resurfacing 
access roads at Dresden Island and Marseilles Locks 
and Dams. Another contractor earned $191,800 for 
repair and replacement of mooring cells at Dresden 
and Starved Rock Locks and Dams. Other maintenance 
work items totaled $195,000 and Engineering 
and Design work totaled $489,800. Supervision and 
administration and district overhead for the maintenance 
features totaled $356,200. Total cost of maintenance 
was $4,552,400. Net credits to the project for 
miscellaneous receipts amounted to $19,500. 
Operation and Care: Operation of the locks and 
dams and routine maintenance and minor repairs 
thereto were made at a cost of $4,002,600. Operation of 
the Illinois Waterway Project Office at Peoria was 
continued at a cost of $568,700. Real estate management 
services were provided at a cost of $91,100; Visitors' 
Center at Starved Rock Lock and Dam was 
operated at a cost of $123,900; surveys, studies and 
structural inspections were performed at a cost of 
$380,000; and water control management costs were 
$423,600. Supervision and administration and district 
overhead for the operations features totaled $708,000. 
Total cost of operation was $6,297,900. 
Total operation and maintenance costs were 
$10,830,802 for all pools above Alton pool. 
Rehabilitation: Rehabilitation work at Dresden 
Island, Starved Rock, and Lockport Locks and Dams 
was in progress. Costs at Dresden Island were 
$3,235,183, at Starved Rock were $2,167,018, and at 
Lockport were $279,752, a total of $5,681,952. 
Alton Pool Operation: Costs by hired labor for 
condition and operation studies were $222,597; water 
control management $28,240; and supervision and 
administration $17,522. 
Alton Pool Maintenance: Costs for the year were 
$370,093 for dredging and $2,456 for supervision and 
administration. 
Total cost for work in Alton Pool was $640,908. 
2. ILLINOIS AND MISSISSIPPI 
CANAL, IL 
Location. This canal extends for 75 miles from the 
Illinois River near LaSalle, IL, to the Mississippi 
River at Rock Island, IL. A feeder canal, 29 miles in 
length, extends from the summit level of the canal to 
the Rock River at Rock Falls, IL. 
Existing project. See pages 1306-1308 of Annual 
Report for 1962 for details regarding project. The 
canal was constructed in the period 1892-1918. The 
canal has not been operated for navigation since June 
1951 in accordance with Corps policy to discontinue 
operation of waterways affording little or no benefit to 
navigation. The River and Harbor Act of 1958 authorized 
the appropriation of $2,000,000 for the purpose of 
placing the canal in proper condition for public recreational 
use and to convey and transfer the canal to the 
State of Illinois as part of the State park system. The 
28-2

ROCK ISLAND, IL, DISTRICT 
repair and modification program was initiated in 
1961, and a number of canal features have been 
repaired or modified. In connection with this program, 
fee title to 1,062 acres and recreational flowage easements 
over 309 acres of land in Rock River at Rock 
Falls, formerly under navigation flowage easement, 
have been acquired. The State of Illinois accepted title 
to the canal as of August 1, 1970. The River and Harbor 
Act of 1970 authorized the additional appropriation 
of $6,528,000 to be expended for the repair, modification, 
and maintenance of bridges, title transfer, 
modification or rehabilitation of hydraulic structures, 
fencing, clearing auxiliary ditches, and for the repair 
and modification of other canal property appurtenances. 
During fiscal year 1982, a judgment of the Court of 
Appeals, 7th Circuit, directed that a fund of $2,812,658 
plus interest at 12 percent per annum computed from 
Feb. 23, 1979, be established by the United States in 
the District Court from which payments are to be 
made to plaintiffs for required repairs to Illinois and 
Mississippi Canal bridges. Actual payment for the 
judgment award was $3,722,572, which included 
interest at 12 percent through Nov. 4, 1981. Engineering 
and design work in connection with this matter 
cost $2,423. Total costs were $3,727,338. 
3. MILL CREEK AND SOUTH SLOUGH 
AT MILAN, IL 
Location. Mill Creek and South Slough are small 
streams, tributary to the Rock River, at Milan, Rock 
Island County, IL. 
Existing project. The existing project provided for 
flood protection at the village of Milan necessitated by 
the construction of the Illinois and Mississippi Canal. 
The project consisted of diversion of Mill Creek into 
South Slough, flood gates in the walls of the Illinois 
and Mississippi Canal to carry Mill Creek flood waters 
across the canal right-of-way into Rock River, levees, 
and other works for flood protection. The project was 
constructed in 1931-1932. In 1962-1963, $73,366 was 
expended from Illinois and Mississippi Canal maintenance 
funds for restoration of the Mill Creek outlet 
into Rock River. See Table 28-B for authorizing 
legislation. 
Local cooperation. Fully complied with. 
Operations during fiscal year. Minor channel 
maintenance was performed at a cost of $1,500. 
4. MISSISSIPPI RIVER BETWEEN 
MISSOURI RIVER AND 
MINNEAPOLIS, MN 
For report on this improvement see chapter on 
"Mississippi River between Missouri River and Minneapolis, 
MN." 
5. OTHER AUTHORIZED NAVIGATION 
PROJECTS 
See Table 28-C. 
6. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation activities pursuant to Sec. 107, 
Public Law 86-645, as amended (Preauthorization). 
Preauthorization study cost for fiscal year was 
$15,238 for small-boat harbor in Muscooten Bay, Illinois 
River, near Beardstown, IL. 
Flood Control 
7. ACKERMAN CREEK, TAZEWELL 
COUNTY, IL 
Location. Ackerman Creek is a small stream tributary 
to Farm Creek, which, in turn, is tributary to the 
Illinois River, near East Peoria in Tazewell County, 
IL. 
Existing project. High flows on Ackerman Creek 
have eroded the creek's left bank and washed out a 
reach of township road. The existing project consists 
of placing fill and riprap protection along a 1,600-foot 
reach of the creek bank. See Table 28-B for project 
authorization. 
Local cooperation. Fully complied with. 
Operations during fiscal year. Construction of 
the project was accomplished at a cost of $194,633. 
8. APPANOOSE TOWNSHIP, 
HANCOCK COUNTY, IL 
Location. Appanoose Township is located on the 
left bank of the Mississippi River at river mile 380, in 
Hancock County, IL. 
Existing project. Mormon Springs Road in Appanoose 
Township is located along the bank of the Mississippi 
River and is subject to erosion during Mississippi 
River high-water conditions, due primarily to 
wave action resulting from prevailing winds. The 
road is an important traffic artery to re idents of the 
area. The existing project consists of placing riprap at 
five locations along the riverbank for a total distance 
of approximately 1,900 feet to relieve the threat of 
undermining Mormon Springs Road. See Table 28-B 
for authorizing legislation. 
Local cooperation. Section 3 of the Flood Control 
Act of June 22, 1936, applies. In addition, the township, 
the local sponsor, must comply with the applicable 
provisions of the Uniform Relocation Assistance 
and Real Property Acquisition Policies Act of 1970, 
must contribute any funds required in excess of the 
$250,000 Federal cost limitation, and grant the Federal 
Government the right to enter upon the project 
lands. The requirements of local cooperation have 
been complied with by Appanoose Township. 
Operations during fiscal year. The project was 
constructed during the fiscal year at a cost of $219,169. 
9. BETTENDORF, IA 
Location. The city of Bettendorf is located on the 
right bank of the Mississippi River, 485.7 miles above 
the mouth of the Ohio River. in Scott County, IA. 
28-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Existing project. Local flood protection from the 
Mississippi River to be provided by construction of 3 
miles of earth levee, railroad raises, closure structures, 
and street raises and ramps. Construction was started 
in July 1982. Estimated project cost is $16,030,000, 
including $1,530,000 non-Federal cost for lands and 
relocations. See Table 28-B for authorizing legislation. 
Local cooperation. Fully complied with. 
Operations during fiscal year. New work: Construction 
continued. The project is 23 percent completed. 
Costs were $1,859,754. 
10. BURLINGTON, IA 
Location. The project site is an industrial area at 
the confluence of Flint Creek with the Mississippi 
River at the city of Burlington, Des Moines County, 
IA, 405 miles above the mouth of the Ohio River. 
Existing project. Local protection from floods on 
the Mississippi River and Flint Creek to be provided 
the industrial area by construction of earth levees, a 
concrete floodwall, interior drainage facilities, and 
two railroad closure structures. Construction was 
started in July 1982. The estimated project cost is 
$2,687,000, including $477,000 non-Federal cost for 
lands and relocations. See Table 28-B for authorizing 
legislation. 
Local cooperation. Fully complied with. 
Operations during fiscal year. New work: Construction 
continued, the principal work item being 
placing levee fill. The project is 93 percent completed. 
Costs were $7,667,175. 
11. CORALVILLE LAKE, IA 
Location. Coralville Lake is formed by the Coralville 
Dam on the Iowa River, several miles upstream 
from Iowa City, Johnson County, IA, about 83 miles 
above the confluence of the Iowa River with the Mississippi 
River. 
Existing project. See page 28-4, Annual Report for 
1981, for project details. Construction began in July 
1949 and project has been in operation since February 
1958. About 24,130 acres of land were acquired in fee, 
and flowage easements obtained for 9,581 acres. The 
project was modified to provide for construction of a 
highway bridge crossing the lake at the Mehaffey site, 
which was begun in June 1964 and completed in 
October 1966. See Table 28-B for authorizing 
legislation. 
Local cooperation. None required, except in connection 
with the Mehaffey Bridge, which has been 
fully complied with. 
Operations during fiscal year. New work: Additional 
land acquisition to provide for the present plan 
of reservoir operation and damage payments to Johnson 
County, IA, for past and future damages to certain 
flowage easement roads in the upper limits of the 
reservoir and construction of additional recreation 
facilities were performed at a cost of $1,199,041. Maintenance: 
Routine maintenance activities continued at 
a cost of $2,420,000. Expenditures from return of 
recreation use fees: $49,000. 
12. DAVENPORT, IA 
Location. The city of Davenport is located on the 
right bank of the Mississippi River, 482.4 miles above 
the mouth of the Ohio River, in Scott County, IA. 
Existing project. Local protection to the city from 
floods on the Mississippi River to be provided by construction 
of levees, floodwall, interior drainage facilities 
and pump plants, closure structures, and recreational 
facilities. The project also provides for the 
enhancement and preservation of Nahant Marsh at 
the downstream edge of the city as a wetland area 
with important contribution to environmental quality. 
Estimated project cost is $35,500,000, including 
$11,000,000 non-Federal cost for land and relocations. 
Construction has not been started. See Table 28-B for 
authorizing legislation. 
Local cooperation. Section 3, Flood Control Act of 
June 22, 1936, applies. Local interests also to bear the 
cost of relocations, bear not less than one-half of the 
separable first cost for recreational development, 
obtain legal control to prevent encroachment on project 
features, and provide pressurized sewers at three 
locations. Negotiations are under way with the city of 
Davenport. 
Operations during fiscal year. New work: Preconstruction 
planning and engineering were continued 
at a cost of $100,458. 
13. DEPUE, IL 
Location. The village of DePue is located on the 
Illinois River in Bureau County, IL. 
Existing project. A small unnamed creek runs 
through the community and intermittent flows are 
eroding an access road to the village. The existing 
project consists of placing of riprap to divert the current 
away from the road. See Table 28-B for authorizing 
legislation. 
Local cooperation. Section 3 of the Flood Control 
Act of June 22, 1936, applies. In addition, the village of 
DePue, the local sponsor, must comply with the applicable 
provisions of the Uniform Relocation Assistance 
and Real Property Acquisition Policies Act of 
1970, must contribute any funds required in excess of 
the $250,000 Federal cost limitation; and grant the 
Federal Government the right to enter upon the project 
lands. The requirements of local cooperation have 
been complied with by the village. 
Operations during fiscal year. Construction of 
the project was accomplished at a cost of $42,505. 
14. EAST MOLINE, IL 
Location. East Moline is located on the left bank of 
the Mississippi River, 489.3 miles above the mouth of 
the Ohio River, in Rock Island County, IL. 
Existing project. Local protection from Mississippi 
River and Rock River floods to be provided by 
28-4

ROCK ISLAND, IL, DISTRICT 
construction of 4.8 miles of levee, 960 linear feet of 
floodwall, a closure structure, a pumping station, two 
railroad raises, and three street raises. Construction 
was initiated in July 1979. The estimated project cost 
is $11,170,000, including $1,490,000 non-Federal cost 
for lands, relocations, and alterations of buildings 
and utilities. See Table 28-B for authorizing legislation. 
Local cooperation. Fully complied with. 
Operations during fiscal year. New work: Construction 
was continued with the placing of levee fill, 
railroad track raises, and the pumping station at a 
cost of $1,769,692. The project is about 98 percent 
completed. 
15. EVANSDALE, IA 
Location. Evansdale is located on the left bank of 
the Cedar River, about 194 miles above the confluence 
of that stream with the Iowa River, in Black Hawk 
County, IA. 
Existing project. Local protection from the Cedar 
River and Elk Run Creek to be provided the city of 
Evansdale and the adjoining community of Elk Run 
Heights by the construction of a 3.2-mile long system 
of levees with appurtenant closures, ramps, and interior 
drainage facilities. About 1.1 miles of the 
embankment for the 1-380 Highway through Evansdale 
will also serve as part of the levee system. Construction 
was initiated in January 1981. See Table 
28-B for authorizing legislation. 
Local cooperation. Fully complied with. 
Operations during fiscal year. New work: Construction 
continued, with grading and shaping the 
levee, and clean-up work, at a cost of $309,641. The 
project was completed in October 1982. 
16. FARM CREEK, IL 
Location. Farm Creek watershed in Tazewell 
County, IL, is 60 square miles in extent. Stream empties 
into Illinois Waterway at Mile 162 above mouth. 
Existing project. Two compacted-earth flooddetention 
dams, Fondulac Dam on Fondulac Creek, 
Tazewell County, IL, about 1.5 miles easterly of East 
Peoria, IL, and Farmdale Dam on Farm Creek, Tazewell 
County, IL, about 2.5 miles easterly of East 
Peoria, IL, and improvements to Farm Creek, Cole 
Creek, and Kerfoot Creek channels in East Peoria, IL. 
Fondulac Dam has a maximum height of 67 feet above 
riverbed and a reservoir capacity of 3,780 acre-feet. 
Farmdale Dam has a maximum height of 80 feet 
above riverbed and a reservoir capacity of 15,500 acrefeet. 
Linear feet of channel improvements are: Farm 
Creek, 12,000 feet; Cole Creek, 1,875 feet; Kerfoot 
Creek, 900 feet. Project provides complete protection to 
residential, business, and highly developed industrial 
areas in East Peoria against design flows in Farm, 
Cole, Kerfoot, and Dempsey Creeks of expected frequency 
once in about 100 years. The project is completed. 
See Table 28-B for authorizing legislation. 
Local cooperation. Fully complied with. 
Operations during fiscal year. Maintenance: 
Routine maintenance activities were continued at a 
cost of $109,008. 
17. FORT MADISON, IA 
Location. The city of Fort Madison, IA, is located 
on the left bank of the Mississippi River at river mile 
383 above the mouth of the Ohio River. 
Existing project. The existing project consists of 
removing accumulated silt in Fork Creek, French 
Creek, and Dry Creek, three small tributaries of the 
Mississippi River, which flow through the city of Fort 
Madison and have caused extensive flood damage 
from creek overflow, storm-water ponding, and sewer 
backup. Construction was initiated in December 1981 
and completed in June 1982. See Table 28-B for authorizing 
legislation. 
Local cooperation. Fully complied with. 
Operations during fiscal year. The project was 
completed. Costs during the year were $4,587.. 
18. FULTON, IL 
Location. The city of Fulton is located on the left 
bank of the Mississippi River, 520.1 miles above the 
mouth of the Ohio River, in Whiteside County, IL. 
Existing project. Local protection from Mississippi 
River floods to be provided by construction of 12 
miles of earth levee, railroad raises, road ramps, closure 
structures, gravity drainage outlets, ponding 
areas, storm sewer interceptors, and pumping plants. 
The improvements will also protect an adjacent rural 
area in the Cat Tail Drainage District, thereby providing 
access for the city to high ground. Construction 
was initiated in January 1978. The estimated project 
cost is $20,550,000, including $2,150,000 non-Federal 
cost for lands and relocations. See Table 28-B for 
authorizing legislation. 
Local cooperation. Fully complied with. 
Operations during fiscal year. New work: Construction 
continued at a cost of $3,473,034. Work 
remaining consists principally of the completion of 
the main Mississippi River levees and the construction 
of the two pumping plants. The project is about 98 
percent completed. 
19. HANNIBAL, MO 
Location. The project area is on the right bank of 
the Mississippi River at the city of Hannibal, MO, 309 
miles above the mouth of the Ohio River. 
Existing project. The authorized project provides 
for flood protection to the business and industrial area 
of the city of Hannibal by the construction of a system 
of levees and floodwalls. The plan also included a 
pumping plant, closure structures for railroads and 
streets, alteration of the existing sewage sytem, and a 
tainter gate closure at the mouth of Bear Creek. 
Advance planning on the project was begun in 1962; 
however, in 1965 further work was discontinued 
because of lack of local support. Local interest revived 
in 1979, and the project was reclassified from "In- 
28-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
active" to the "Active" category. A study has been 
undertaken to reformulate the project to meet existing 
needs of the project area and to reflect current Federal 
and State criteria for water resources projects. See 
Table 28-B for authorizing legislation. 
Local cooperation. Section 3 of the Flood Control 
Act of June 22, 1936, applies. Local interests would 
also be required to modify or relocate buildings, utilities, 
and other facilities where necessary in the construction 
of the project. No action toward the fulfillment 
of local cooperation requirements has been 
taken. 
Operations during fiscal year. New work: Detailed 
studies for reformulation of the project and 
evaluation of alternatives were continued at a cost of 
$153,304. 
20. MILAN, IL 
Location. The village of Milan is located on the 
south bank of the Rock River several miles upstream 
from the confluence of that stream with the Mississippi 
River at mile 479.1 above the mouth of the Ohio 
River, in Rock Island County, IL. 
Existing project. Local protection against direct 
flooding from Rock River and Mill Creek and against 
backwater flooding from the Mississippi River to be 
provided the community by construction of levees, 
flood walls, closure structure, bridges, pumping stations, 
drainage facilities, and street ramps. Construction 
was initiated in March 1981. The estimated project 
cost is $17,700,000, including $3,400,000 non- 
Federal cost for land and relocations. See Table 28-B 
for authorizing legislation. 
Local cooperation. Fully complied with. 
Operations during fiscal year. New work: Construction 
of the project continued at a cost of 
$3,522,286. The principal work items were levee construction 
and utilities relocations. The project is about 
46 percent completed. 
21. MOLINE, IL 
Location. The city of Moline is located on the left 
bank of the Mississippi River, 485.7 miles above the 
mouth of the Ohio River, in Rock Island County, IL. 
Existing project. Local protection at Moline from 
Mississippi River floods to be provided by construction 
of 4 miles of earth levee and flood wall, closure structures, 
aesthetic and recreational development, and 
interior drainage facilities consisting of gravity 
outlets, storm sewer interceptors, and pumping plants. 
Construction has not yet been initiated. The estimated 
project cost is $21,110,000, including $1,210,000 for 
land and relocations. See Table 28-B for authorizing 
legislation. 
Local cooperation. Section 3, Flood Control Act of 
June 22, 1936, applies. Local interests will also provide 
relocations, bear not less than one-half of the separable 
first cost for recreational development, and prevent 
encroachment on ponding areas. Local interests 
will be requested to furnish assurances after a firm 
project plan is established. 
Operations during fiscal year. Preconstruction 
planning continued at a cost of $172,217. 
22. MONROE COUNTY, IA, 
HIGHWAY BRIDGES 
Location. The sites of this project are seven highway 
bridges on North Cedar Creek, Cedar Creek, 
Whites Creek, English Creek, and Morman Branch 
Creek, all small streams in Monroe County, IA. 
Existing project. The existing project consists of 
restoring streambanks to their original configurations 
at bridge locations where floodwaters have eroded the 
banks, precluding use of the bridges. Construction 
was initiated in February 1982. See Table 28-B for 
authorizing legislation. 
Local cooperation. The requirements of local 
cooperation have been complied with. 
Operations during fiscal year. The project was 
completed. Costs during the fiscal year were $282,500. 
23. MUSCATINE, MAD CREEK, IA 
Location. The project area is located on the right 
bank of Mad Creek, a short distance upstream from 
the confluence of that stream with the Mississippi 
River at mile 455.8 above the mouth of the Ohio River, 
in the city of Muscatine, Muscatine County, IA. 
Existing project. The project provides local protection 
to a 75-acre industrial area at Muscatine from 
coincidental floods on Mad Creek and the Mississippi 
River. The site is upstream from a previous Federal 
flood control project on Mad Creek, but some modification 
of that project is required. The current project 
consists mainly of earth levees and concrete flood 
walls. Stage I of the project, which consisted of 1,010 
feet of earth levee, 240 feet of concrete floodwall, a 
ponding area, a street closure, gatewells, a bridge 
raise, and railroad track modifications, was initiated 
in November 1977 and completed in February 1979. 
Stage II, which consists of raising 2,000 feet of existing 
railroad embankment, was initiated in October 
1981. See Table 28-B for authorizing legislation. 
Local cooperation. Fully complied with. 
Operations during fiscal year. New work: Construction 
of Stage II of the project was continued at a 
cost of $4,634. The principal work item was the placement 
of fill for raising the railroad embankment. The 
project is completed. 
24. RED ROCK DAM AND LAKE RED 
ROCK, IA 
Location. The site of this project is on the Des 
Moines River, chiefly in Marion County, but extending 
into Jasper, Warren, and Polk Counties. The dam 
is 142.9 miles above the mouth of the Des Moines 
River, which empties into the Mississippi River at 
mile 361.4 above the mouth of the Ohio River. The city 
28-6

ROCK ISLAND, IL, DISTRICT 
of Des Moines lies northwesterly from the site, about 
60 miles upstream. 
Existing project. See page 28-6, Annual Report for 
1981 for description of the project. Construction began 
in May 1960, and the dam was placed in beneficial use 
for storage of flood water in January 1969. Land 
acquired for the project consisted of 47,610 acres in fee 
and 28,214 acres in flowage easement. See Table 28-B 
for authorizing legislation. 
Local cooperation. None required. 
Operations during fiscal year. New work: Construction 
of recreational facilities and incidental work 
was performed at a cost of $489,056. Maintenance: 
Routine maintenance activities were continued at a 
cost of $2,886,214. Expenditures from the return of 
recreation use fees were $41,000. 
25. ROCKFORD, IL 
Location. The city of Rockford is located along 
both banks of the Rock River, in Winnebago County, 
IL. Kent Creek is a small stream, tributary to the Rock 
River, which flows through the right-bank portion of 
the city. 
Existing project. The project provides flood protection 
for the right-bank portion of the city from 
floods on Kent Creek. It consists of a rolled earth dam 
with outlet works and spillway on North Branch Kent 
Creek in Page Park; 12,000 feet of channel cleanout 
and straightening on North Branch Kent Creek; raise 
of Levings Lake Dam on South Branch Kent Creek 
and construction of spillway and diversion channel; 
10,800 feet of channel cleanout and straightening on 
South Branch Kent Creek; and relocations. Construction 
was initiated in October 1978. The estimated project 
cost is $16,110,000, including $6,390,000 for land 
and relocations. See Table 28-B for authorizing 
legislation. 
Local cooperation. Fully complied with. 
Operations during fiscal year. New work: Construction 
of the project was continued at a cost of 
$866,122. The principal work items were channel 
cleanout and straightening on North Branch Kent 
Creek and construction of the diversion channel on 
South Branch Kent Creek. The project is about 60 
percent completed. 
26. ROCK RIVER AGRICULTURAL 
LEVEES, IL 
Location. The project area lies along both banks of 
the Rock River in Rock Island, Henry, and Whiteside 
Counties, IL. 
Existing project. The project provides for construction 
of levees and appurtenant works with incidental 
channel improvements for flood control in five 
areas along the lower Rock River, mainly agricultural 
in character; as follows: 
Area 1, Carbon Cliff to Canoe Creek, right bank, 
15.8 miles 
Area 2, Canoe Creek to Rock Creek, right bank, 
16.2 miles 
Area 3, Rock Creek to Lyndon, right bank, 15 miles 
Area 4, Near Spring Hill to Prophetstown, 
left bank, 10.2 miles 
Area 5, Penny Slough Levee and Drainage 
District, left bank, 9.1 miles 
Estimated project cost is $41,270,000, including 
$8,170,000 non-Federal cost for land and relocations. 
No construction has been performed. The project was 
authorized in 1958, but remained unfunded until FY 
1979 when local interest in the project developed. A 
study has been undertaken to reformulate the project 
to meet existing needs of the project area and to reflect 
current Federal and State criteria for water resources 
projects. See Table 28-B for authorizing legislation. 
Local cooperation. Section 3 of the Flood Control 
Act of June 22, 1936, applies. Local interests would 
also bear the cost of relocations, except railroad 
bridges, and contribute in cash. No action toward fulfilling 
the requirements of local cooperation has been 
taken at this time. 
Operations during fiscal year. New work: Detailed 
studies for reformulation of the project and 
evaluation of alternatives were continued at a cost of 
$70,815. 
27. SAYLORVILLE LAKE, IA 
Location. The project site is chiefly in Polk County, 
IA, but portions extend into Dallas and Boone Counties. 
The dam is about 213.7 miles above the mouth of 
the Des Moines River and about 5 miles upstream 
from the city of Des Moines, IA. 
Existing project. The dam is an earth embankment 
6,750 feet long at crest with a height of 120 feet. 
Outlet works are a single circular concrete conduit, 22 
feet in diameter, located at the toe of the west bluff. 
Control structure is at upstream end of conduit and 
houses three gates. A stilling basin is provided to dissipate 
energy of discharge from outlet conduit. Spillway 
is in west bluff, weir 430 feet long. Water flowing 
over the spillway weir discharges into a paved chute 
and thence into an excavated earth channel to the Des 
Moines River. Top of spillway is about 31 feet below 
top of earth embankment section, and flow over weir is 
uncontrolled when water in reservoir reaches its crest. 
Watershed area above dam site is 5,823 square miles. 
With pool at spillway crest elevation, lake area is 
16,700 acres and contains about 676,000 acre-feet of 
water at that height (602,000 for flood control and 
74,000 for a conservation pool to maintain minimum 
flows at downstream points). Lake supplements 
capacity of downstream Lake Red Rock at river mile 
142.9. The two lakes provide a high degree of flood 
protection to the lower Des Moines River Valley. 
Reaches along the Mississippi River downstream from 
the mouth of the Des Moines River are also benefited. 
A project modification plan to minimize the adverse 
environmental effects at Ledges State Park, located 
upstream from the dam, was authorized in 1976. The 
project modification includes relocation of affected 
park facilities, acquisition of additional park land, 
and the development of a floodway corridor, with 
28-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
recreational facilities, from the dam downstream to 
Sixth Avenue in Des Moines. 
Construction began in June 1965, and the dam was 
placed in operation for the storage of flood water in 
April 1977. Remedial work in Big Creek Valley, consisting 
of a diversion dam and channel and a barrier 
dam, for the protection of the town of Polk City was 
completed in December 1974. The land acquisition 
program involved 25,919 acres acquired in fee, flowage 
easements for 1,416 acres, and roadway easements for 
40 acres. The estimated project cost is $119,666,000, 
excluding $2,600,000 non-Federal cost as a cash contribution 
from the State of Iowa toward recreational 
development. See Table 28-B for authorizing legislation. 
Local cooperation. Fully complied with. 
Operations during fiscal year. New work: The 
principal work item was the construction of recreational 
facilities. Work was also continued on the 
archeological program and on engineering and design 
work for the downstream floodway corridor. New 
work costs were $491,088. Maintenance: Routine 
maintenance activities were continued at a cost of 
$2,654,132. Expenditures from return of recreation use 
fees were $49,000. The project is about 92 percent 
completed. 
28. SOUTH FABIUS RIVER, KNOX 
COUNTY, MO 
Location. The project site is at the Pleasant Valley 
highway bridge on the South Fabius River, in Knox 
County, MO. 
Existing project. The existing project consists of 
repairs to a bridge wingwall and a part of the bridge 
approach which had been damaged by floods on the 
South Fabius River. Construction of the project was 
accomplished in January 1982. See Table 28-B for 
authorizing legislation. 
Local cooperation. The requirements of local 
cooperation have been complied with by the county. 
Operations during fiscal year. The project was 
under construction. Costs were $10,306.. 
29. WATERLOO, IA 
Location. The city of Waterloo is located along 
both banks of the Cedar River in Black Hawk County, 
IA.
Existing project. The project provides local protection 
to the city of Waterloo from floods on the Cedar 
River, Black Hawk Creek, Virden Creek, and Blowers 
Creek. It consists of 15.4 miles of earth levee, 2 miles of 
flood wall, 11,330 feet of channel improvement, an 
impounding dam on Virden Creek, and interior drainage 
facilities including 8 pumping plants. Extensive 
urban renewal, undertaken by the city, has been coordinated 
with the flood control project. Construction 
was initiated in August 1972. The estimated project 
cost is $66,500,000, including $14,900,000 non-Federal 
cost for land and relocations. See Table 28-B for authorizing 
legislation. 
Local cooperation. Fully complied with. 
Operations during fiscal year. New work: Construction 
of the project was continued at a cost of 
$1,124,975. The principal work items were continuation 
of construction of levees and flood walls along the 
Cedar River. The project is about 89 percent completed. 
30. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Federal flood-control regulations (part 208 of title 
33, Code of Federal Regulations) provide that the 
structures and facilities constructed by the United 
States for local flood protection shall be continuously 
maintained in such a manner and operated at such 
times and for such periods as may be necessary to 
obtain the maximum benefits. Costs during the period 
for inspections of projects turned over to local interests 
to ascertain compliance with Federal requirements 
were $112,106. (See Table 28-H for list of completed 
flood control projects inspected.) 
31. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
See Table 28-E. 
32. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control activities, Section 205, Public 
Law 84-685. See Table 28-I. 
Snagging and clearing of navigable streams 
and tributaries in interest of flood control, Section 
208, Public Law 83-780. See Table 28-I. 
Emergency Flood Control Activities, Public 
Law 99, 84th Congress. See Table 28-I. 
Steambank Erosion Control Evaluation and 
Demonstration Act of 1974. A bank erosion problem 
on the Iowa River at Wapello, IA, was selected by 
the Chief of Engineers as a demonstration site under 
the above-cited act. The project consists of a combination 
of permeable timber jetties, erosion control mat, 
and steel jacks. Construction was accomplished in 
1978, to be monitored for five years to evaluate its 
success. Flowing ice damaged the project in the winter 
of 1978-1979, and repairs were made in 1979-1980. On 
February 23, 1982, the project, except for the steel 
jacks, was transferred to the city of Wapello for operation 
and maintenance. At the request of the city, the 
steel jacks were later removed at Federal expense. 
Costs during the fiscal year were $5,031. 
General Investigations 
33. SURVEYS 
Flood control studies in progress included the Fox 
River and Tributaries, WI; the Iowa-Cedar Rivers, IA 
and MN; the Mississippi River, Coon Rapids to Ohio 
2&8

ROCK ISLAND, IL, DISTRICT 
River, the Quad Cities Urban Study, IA and IL; the 
Rock River at Rockford and Vicinity, IL. Total cost of 
flood control studies was $1,068,721. Review of completed 
projects cost $88,060. Inventory of dams cost 
$41,317. Coordination studies with other agencies on 
soil conservation, water quality management, planning 
assistance to States, and technical assistance on 
shore and streambank erosion cost $81,049. Total cost 
of surveys was $1,279,147. 
34. COLLECTION AND SURVEY OF 
BASIC DATA 
Flood plain management services cost $160,008. 
Hydrologic studies, including general studies, sedimentation 
studies, steamflow studies, and rainfall 
studies cost $4,855. Total cost for collection and study 
of basic data was $164,863. 
28-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 28-A COST AND FINANCIAL STATEMENT 
See 
Section 
in Text Project 
1. Illinois Waterwa 
IL and IN 
2. Illinois and 
Mississippi Canal, 
IL 
3. Mill Creek and 
South Slough at 
Milan, IL 
7. Ackerman Creek, 
Tazewell County, IL 
8. Appanoose 
Township, 
Hancock County, IL 
9. Bettendorf, IA 
10. Burlington, IA 
Cont 
11. Coralville Lake, IA 
12. Davenport, IA 
13. DI)ePue, IL 
14. East Moline, IL 
Cont 
15. Evansdale, IA 
16. Farm Creek, IL 
y, 
Total Cost to 
FY 80 FY 81 FY 82 FY 83 September 1983 
-1,332 
14,766,600 
12,056,579 
745,000 
990,201 
11,585,500 
10,867,623 
5,490,000 
4,356,755 
Funding 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Rehab: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
tributed Funds 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
tributed Funds 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
20,700 
20,658 
150,000 
141,276 
40,000 
60,832 
711,000 
957,812 
1,856,000 
1,517,151 
100,000 
102,075 
1,055,000 
1,043,728 
150,000 
298,377 
101,088 
88,515 
180,000 
120,335 
9,000 
9,101 
280,000 
267,248 
15,000 
18,591 
277,000 
193,756 
1,307,000 
1,172,257 
1,397,000 
1,791,140 
200,000 
126,707 
1,870,000 
1,882,196 
21,909 
2,682,000 
2,590,925 
58,600 
81,991 
9,994,000 
12,686,905 
9,520,000 
5,094,245 
3,722,572 
3,724,915 
10,213,929 
11,471,710 
1,735,000 
5,681,952 
1,100,000 
2,423 
,- ,- 
2,900 1,000 
3,509 1,500 
97,500 108,000 
10,867 194,633 
- 220,000 
- 219,169 
620,000 2,440,000 
539,682 1,859,754 
1,456,600 1,400,000 
978,757 1,667,175 
7,950 - 
50,150 1,169 
2,183,000 3,491,700 
2,056,279 1,199,040 
1,653,000 2,715,000 
1,579,421 2,420,201 
- 200,000 
89,162 100,458 
- 51,000 
- 50,005 
4,030,000 1,230,000 
3,283,610 1,769,692 
1,496,000 
1,189,781 
66,000 
98,838 
309,641 
107,000 
109,008 
28-10 
-505 
126,707,7511 
126,706,4191 
187,418,8412 
187,121,9192 
29,414,625 
27,689,248 
7,605,1433 
7,605,1433 
17,896,8104 
16,796,6364 
63,7195 
63,7195 
349,553 
248,636 
105,500 
105,500 
220,000 
219,169 
3,766,980 
3,080,662 
3,116,100 
2,904,860 
284,950 
245,075 
25,967,4886 
23,326,5426 
16,566,005 
16,143,522 
1,689,717 
1,589,876 
51,000 
50,005 
9,680,300 
9,470,292 
328,090 
328,0909 
4,409,088 
4,408,495 
9,859,0207 
9,859,0207 
2,411,421 
2,408,891

ROCK ISLAND, IL, DISTRICT 
TABLE 28-A (Continued) 
See 
Section 
in Text Project 
17. Fort Madison, I,A 
18. Fulton, IL 
19. Hannibal, MO 
20. Milan, IL 
21. Moline, IL 
22. Monroe County, IA 
Highway Bridges 
23. Muscatine, Mad 
Creek, IA 
24. Red Rock Dam and 
Lake Red Rock, IA 
25. Rockford, IL 
Con 
26. Rock River 
Agricultural 
Levees, IL 
27. Saylorville Lake, 
IA 
28. South Fabius River, 
Knox County, MO 
29. Waterloo, IA 
Con 
Funding 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
tributed Funds 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
tributed Funds 
Approp. 
Cost 
COST AND FINANCIAL STATEMENT 
Total Cost to 
FY 80 FY 81 FY 82 FY 83 September 1983 
11,759 
7,906 
1,890,000 
2,061,901 
2
3 
270,000 
241,435 
237,000 
203,299 
19,000 
24,112 
700,000 
942,713 
1,480,000 
1,435,729 
1,750,000 
1,738,763 
150,000 
147,852 
1,490,000 
1,415,079 
1,454,000 
1,362,790 
4,035,000 
4,016,039 
12,000 165,000 
17,349 143,951 
,803,000 6,070,000 
,091,254 3,759,499 
- 50,000 
- 41,217 
935,000 1,500,000 
805,074 1,527,638 
34,180 
25,000 
28,916 
843,000 
761,068 
2,145,400 
1,750,624 
246,000 
202,876 
245,000 
245,669 
2,896,000 
3,250,480 
2,547,000 
2,619,103 
4,530,000 
4,693,230 
209 
49,100 
49,100 
500,000 
478,125 
1,750,000 
1,397,449 
1,633,000 
1,966,265 
1,400,000 
117,433 
229,032 
85,125 
175,000 
167,998 
2,499,000 
2,305,398 
1,788,000 
1,632,312 
29,300 
29,300 
5,060,000 
4,664,103 
-17,000 
4,587 
1,375,000 
3,473,034 
150,000 
153,304 
3,400,000 
3,522,286 
281,000 
172,217 
282,500 
282,500 
6,000 
4,634 
50,000 
489,056 
2,968,500 
2,927,214 
400,000 
866,122 
-84,262 
40,448 
68,000 
70,815 
1,960,000 
491,088 
3,953,837 
2,703,132 
53,000 
10,306 
1,253,000 
1,124,975 
183,759 
183,759 
18,050,200 
17,791,865 
310,933 
305,454 
6,715,400 
6,458,398 
1,350,000 
1,239,731 
331,600 
331,600 
1,152,600 
1,129,300 
95,302,484 
95,202,484 
16,478,193 
16,236,180 
6,828,736 
5,952,672 
144,770 
125,573 
698,000 
694,213 
98,382,200 
96,697,0078 
13,475,538 
11,986,426 
82,300 
39,606 
46,200,100 
45,672,383 
83,300 
83,300 
1. Includes $2,569,102 for previous projects. 
2. Includes $1,028,468 for previous projects. 
3. Includes $25,000 Emergency Relief Funds. 
4. Includes $4,143,282 for Operating and Care under the 
"Permanent Indefinite Appropriation." 
5. Includes $85 for previous project. 
6. Includes cost of Mehaffey Bridge, $1,365,074 (excluding 
$100,000 contributed funds). 
7. Excludes $161,813 contributed funds. 
8. Excludes $950,000 non-Federal cost. 
9. Refunded $21,909 to City of East Moline. 
28-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 28-B AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
1. Jan. 21, 1927 
July 3, 1930 
June 26, 1934' 
Aug. 30, 1935 
Aug. 30, 1935 
June 14, 1937 
June 20, 1938 
Oct. 23, 1943 
Mar. 2 1945 
Rivers and Harbors 
Committee Doc. 69th 
Cong., 1st sess., and S. Doc. 
130, 69th Cong., 1st sess. 
S. Doc. 126, 71st Cong., 
2nd sess. 
ILLINOIS WATERWAY, IL AND IN 
(See Section 1 of Text) 
Channel 9 feet deep and 200 feet wide from mouth 
of Illinois River to Utica, 231 miles, modification 
of 2 U.S. locks and dams, removal of 2 State 
dams. (Act authorized appropriation of not to 
exceed $3,500,000 for carrying on work.) 
Channel 9 feet deep from Utica, IL to heads of 
present Federal projects on Chicago and Calumet 
Rivers, 94.6 miles to Lake Street, and 96.3 miles to 
turning basin 5, respectively, to be secured by 
means of completed dams, locks, lateral canals, 
and dredging begun by State of Illinois in general 
accordance with present plans of state for that 
work. Act adopting project authorized 
appropriation of not to exceed $7,500,000 for 
carrying on work. 
Operation and care of locks and dams provided 
for with funds from War Department 
appropriation for rivers and harbors. 
Construct modern locks and dams at LaGrange and 
Peoria and a channel 9 feet deep and 300 feet wide 
below Lockport, exact location and details of design 
of all structures to be left to discretion of Chief 
of Engineers, and, for time being, that no change 
be made in water authorized for navigation 
of Illinois River by act of July 3, 1930. 
Also provides for 3 passing places along Sag 
Channel and authorized channel in Calumet-Sag 
route to turning basin 5, and dredging at entrance 
of Lake Calumet. 
Realign portion of Calumet River and abandonment 
of bypassed section of Calumet River. 
Modifies local cooperation requirements in 1935 act. 
Pay damages to levee and drainage districts due to 
seepage and other factors, not to exceed $503,500. 
Enlarge Calumet-Sag Channel to 160 feet wide and a 
usable depth of 9 feet. Dredge a barge channel 160 
feet wide with a usable depth of 9 feet in Grand 
Calumet and Little Calumet River Branch of 
Indiana Harbor Canal to deep (lake) draft through 
141st St., East Chicago, IN. Construct in Little 
Calumet River a lock of suitable dimensions for 
large navigation. Rebuild or otherwise alter at 
Federal expense all obstructive railroad bridges 
across Calumet-Sag Channel, Little Calumet 
River, Calumet River, Grand Calumet River, and 
Indiana Harbor Canal, so as to provide suitable 
clearance, except that no Federal funds shall be 
expended for removal or alteration of Illinois 
Central R.R. bridge at mile 11.20 of Little Calumet 
River. 
28-12 
H. Doc. 184, 73rd Cong., 
2nd sess.2 
H. Doc. 180, 73rd Cong., 
2nd sess. 
Rivers and Harbors 
Committee Doc. 19, 75th 
Cong., e1sste ss. 
H. Doc. 711, 77th Cong., 
2nd sess. 
H. Doc. 145, 76th Cong., 
1st sess.

TABLE 28-B (Continued) 
ROCK ISLAND, IL, DISTRICT 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
July 24, 1946 
July 24, 1946 
July 17, 1953 
July 3, 1958 
Aug. 18, 1968 
3. July 3, 1930 
7. July 24, 1946 
(Section 14) 
8. July 24, 1946 
(Section 14) 
9. August 13, 1968 
10. June 30, 1948 
(Section 205) 
Substitute following work for that authorized by H. Doc. 677, 79th Cong., 
act of Mar. 2, 1945; replace emergency dam in 2nd sess. 
Chicago Sanitary and Ship Canal; enlargement 
of that canal thence to Sag Junction and of 
Calumet-Sag Channel to afford channels 225 feet 
wide and usable depth of 9 feet; construct along 
general route depth of 9 feet to 225 feet wide 
between Little Calumet River and junction with 
Indiana Harbor Canal and 160 feet wide thence to 
Clark St., Gary, IN with a turning basin at Clark 
St., enlarge Indiana Harbor Canal to 225 feet wide 
and usable depth of 9 feet between Grand 
Calumet River and vicinity of 141st St., inclusive; 
remove Blue Island lock and construct a lock 
and control works in Calumet River near its 
head, and similar structures in proposed Grand 
Calumet Channel west of Indiana Harbor Canal; 
alter or eliminate railroad bridges across three 
channels lakeward of Chicago Sanitary and 
Ship Canal, or construct new railroad bridges 
to provide suitable clearance. 
A small-boat harbor in vicinity of Peoria, IL by H. Doc. 698, 79th Cong., 
construction of a basin 510 by 250 feet, dredged 2nd sess. 
to 7 feet deep. 
$48,933 to reimburse Nutwood Drainage and Levee H. Doc. 144, 81st Cong., 
District for additional pumping operation; 1st sess. 
supplementing $58,750 authorized in Oct. 1943 act. 
Federal participation in alteration of highway H. Doc. 45, 85th Cong., 
bridges, Calumet-Sag Modification, Part I, which 1st sess. 4 
constitute unreasonable obstructions to 
navigation, in accordance with Public 
Law 647, 76th Cong., as amended. 
Federal participation in alteration of highway Specified in Act. Also 
bridges, Calumet-Sag Modification, Part II, which H. Doc. 45, 85th Cong., 
constitutes unreasonable obstructions to 1st sess. 
navigation, in accordance with Public 
Law 647, 76th Congress as amended. 
MILL CREEK AND SOUTH SLOUGH AT 
MILAN, IL 
Channel diversion, flood gates, and other work Rivers and Harbors 
for flood protection. Committee Doc. 19, 
71st Cong., 2nd sess. 
ACKERMAN CREEK, TAZEWELL COUNTY, IL 
Fill and riprap to prevent erosion of county road. None 
APPANOOSE TOWNSHIP, 
HANCOCK COUNTY, IL 
Riprap streambank to protect road. None 
BETTENDORF, IA 
Levees, railroad raises, closure structures, and H. Doc. 348, 89th Cong., 
street raises and ramps for flood control. 2nd sess. 
BURLINGTON, IA 
Levee, floodwall, interior drainage, and railroad None 
closures for flood control. 
28-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 28-B (Continued) AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
11. June 28, 1938 
July 14, 1960 
12. December 31, 1970 
13. July 24, 1946 
(Section 14) 
14. August 13, 1968 
15. October 27, 1965 
(Section 201) 
Approved by Committees 
on Public Works of House 
of Representatives and 
Senate, Sept. 23, 1976 and 
Oct. 1, 1976, respectively 
16. 1944 Flood Control Act 
17. September 3, 1954 
18. August 13, 1968 
CORALVILLE LAKE, IA 
Reservoir for flood control and recreation. 
Highway bridge across Coralville Lake at or 
near the Mehaffey site. 
DAVENPORT, IA 
Levee, floodwall and pumping plants. 
Flood Control Committee 
Doc. 1, 75th Cong., 1st sess. 
None 
H. Doc. 161, 92nd Cong., 
1st sess. 
DEPUE, IL 
Riprap streambank to protect road. None 
EAST MOLINE, IL 
Levee, railroad raises, street raises, closure H. Doc. 348, 90th Cong., 
structure, gravity drainage outlets, open ditches, 2nd sess. 
ponding areas, and pumping plants for flood control. 
EVANSDALE, IA 
Levees, ponding areas, interior drainage, and road H. Doc. 563, 94th Cong., 
ramps for flood control. 2nd sess. 
FARM CREEK, IL 
Two flood detention dams and channel H. Doc. 802, 78th Cong., 
improvements. 2nd sess. 
FORT MADISON, IA 
Remove accumulated silt from Fork Creek, French None 
Creek, and Dry Creek for flood control. 
FULTON, IL 
Levee, railroad raises, road ramps, closure structures, H. Doc. 348, 90th Cong., 
gravity drainage outlets, ponding areas, storm 2nd sess. 
sewer interceptors, and pumping plants for flood 
control. 
19. October 23, 1962 
20. August 13, 1968 
21. October 27, 1965 
(Section 201) 
Approved by Committees 
on Public Works of 
House of Representatives 
and Senate June 14, 1972, 
and June 21, 1972, 
respectively. 
22. July 24, 1946 
(Section 14) 
HANNIBAL, MO 
Levee, floodwall, closure structures, and 
pumping plant for flood control. 
MILAN, IL 
Levee closure structures, gravity drainage outlets 
ditches, ponding areas, and pumping plants for 
flood control. 
MOLINE, IL 
Levee, closure structures, and interior 
drainage facilities for flood control, and 
aesthetic and recreational development. 
MONROE COUNTY, IA, HIGHWAY BRIDGES 
Restore streambank at seven highway bridges for 
flood control. 
H. Doc. 564, 87th Cong., 
2nd sess. 
H. Doc. 348, 90th Cong., 
2nd sess. 
H. Doc. 161, 92nd Cong., 
1st sess. 
None 
28-14

ROCK ISLAND, IL, DISTRICT 
TABLE 28-B (Continued) AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
MUSCATINE, MAD CREEK, IA 
23. June 30, 1948 Levee, wall, interior drainage facilities, and None 
(Section 205) closure structures for streets and a railroad for 
flood control. 
RED ROCK DAM AND LAKE RED ROCK, IA 
24. June 28, 1938 Reservoir for flood control and recreation. Flood Control Committee 
Doc. 1, 75th Cong., 1st sess. 
ROCKFORD, IL 
25. October 23, 1962 Channel enlargement and realignment, levees, and S. Doc. 142, 87th Cong., 
appurtenant works for flood control. 2nd sess. 
ROCK RIVER AGRICULTURAL LEVEES, IL 
26. July 3, 1958 Levees and appurtenant works for flood control. H. Doc. 173, 85th Cong. 
SAYLORVILLE LAKE, IA 
27. July 3, 1958 Reservoir for flood control and recreation. S. Doc. 9, 85th Cong., 
1st sess. 
October 22, 1976 Modification to minimize adverse project impact H. Doc. 487, 94th Cong., 
on Ledges State Park. 2nd sess. 
SOUTH FABIUS RIVER, KNOX COUNTY, MO 
28. July 24, 1946 Repair bridge wingwall and bridge approach None 
(Section 14) for flood control. 
WATERLOO, IA 
29. October 27, 1965 Levees, floodwalls, pumping plants, and closure H. Doc. 166, 89th Cong., 
structures for flood control. 1st sess. 
1. Permanent Appropriations Repeal Act. Program Oct. 31, 1934, and Feb. 28, 1935. 
2. Contains latest published map of Illinois and Des 4. Contains latest published maps of Calumet-Sag 
Plaines Rivers. portion. 
3. Included, in part, in Public Works Administration 
TABLE 28-C OTHER AUTHORIZED NAVIGATION PROJECTS 
(See Section 5 of Text) 
For Last Cost To September 30, 1983 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Squaw Chute at Quincy, IL Completed 1967 70,9791 9,345 
Quincy, IL, Harbor Access Channel Completed 1970 35,4772 37,700 
1. Excludes $25,851 contributed funds. 2. Excludes $35,350 contributed funds. 
28-15

TABLE 28-E 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(See Section 31 of Text) 
For Last Cost To September 30, 1983 
Full Report Operation Contributed 
See Annual and Funds 
Project Report For Construction Maintenance Expended 
Completed Projects 
Banner Special Drainage and Levee Districts, IL 
Bear Creek Dam (City of Hannibal, MO) 
Big Lake Drainage and Levee District, IL 
Canton, MO' 
Clinton, IA 
Coal Creek Drainage and Levee District, IL 
Crane Creek Drainage and Levee District, IL 
Des Moines and Mississippi Levee District 
No. 1, MO 
Des Moines, IA 
Drury Drainage District, IL 
Dubuque, IA 
East Liverpool Drainage and Levee District, IL 
East Peoria Drainage and Levee District, IL 
Elkport, IA 
Fabius River Drainage District, MO 
Fabius River Drainage District, MO 
Farmers Levee and Drainage District, IL 
Galena, IL 
Green Bay Levee and Drainage District No. 2, IA 
Green Bay Levee and Drainage District No. 2, IA 
Gregory Drainage District, MO 
Gregory Drainage District, MO 
Henderson County Drainage District No. 1, IL 
Henderson County Drainage District No. 2, IL 
Henderson County Drainage District No. 3, IL 
Hennepin Drainage and Levee District, IL 
Hunt Drainage District and Lima Lake Drainage 
District, IL 
Indian Grave Drainage District, IL 
Iowa River-Flint Creek Levee District No. 16, IA 
Kishwaukee River at DeKalb, IL' 
Lacey, Langellier, West Mantanzas and Kerton 
Valley Drainage and Levee District, IL 
Liverpool Drainage and Levee District, IL 
Lost Creek Drainage and Levee District, IL 
Marengo, IA' 
Marion County Drainage District, MO 
Marshalltown, IA 
Mason and Menard Drainage District, IL 
Meredosia Levee and Drainage District, IL' 
Muscatine, Iowa (Mad Creek)' 
Muscatine Island Levee District and Muscatine- 
Louisa County Drainage District No. 13, IA 
Near Springfield on Sangamon River, IL 
Oakford Special Drainage District, IL 
Okabena Creek at Worthington, MN' 
761,050 
23,323 
145,415 
1943 
1962 
1943 
1964 
1981 
1954 
1941 
1969 
1972 
1964 
1974 
1941 
1946 
1951 
1941 
1963 
1942 
1952 
1949 
1967 
1940 
1972 
1968 
1968 
1949 
1940 
1972 
1972 
1972 
1957 
1954 
1943 
1938 
1981 
1967 
1978 
1940 
1977 
1962 
1970 
1941 
1940 
1957 
274,822 
1,679,056 
144,910 
1,496,555 
26,001,996 
1,923,145 
68,898 
1,492,016 
4,993,224 
1,144,875 
10,861,170 
207,826 
279,963 
34,200 
60,500 
1,621,841 
155,562 
844,100 
299,000 
1,727,711 
77,100 
1,538,963 
1,453,217 
1,043,902 
42,700 
109,593 
4,772,498 
3,551,961 
6,044,693 
123,300 
1,290,000 6 
117,731 
152,000 
2,447,001 
873,748 
8,437,511 
93,808 
1,995,322 
1,193,154 
3,293,276 
38,417 
72,432 
118,000 
20,626 
252,136 
269,739 
220,000 
28-16

ROCK ISLAND, IL, DISTRICT 
TABLE 28-E 
(Continued) 
OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(See Section 31 of Text) 
For Last Cost To September 30,1983 
Full Report Operation Contributed 
See Annual and Funds 
Project Report For Construction Maintenance Expended 
Ottumwa, IA 1977 233,145 - 
Pekin and La Marsh Drainage and Levee 
District, IL 1955 158,383 - 
Penny Slough, Rock River, IL 1940 85,800 - 
Rock Island, IL 1979 7,582,373 - 
Rocky Ford Drainage and Levee District, IL 1941 108,797 - 
Sabula, IA 1958 411,915 - 
Sangamon River (mouth) IL 1980 1,048,990 272,848 15,122 
Seahorn Drainage and Levee District, IL 1945 32,281 - 
Sid Simpson Project, IL 1968 5,789,800 - 
Sny Basin, IL 1972 14,003,560 - 
Sny Island Levee Drainage District, IL 1942 61,400 - 
Sny Island Levee Drainage District, IL 1968 4,956,749 - 
South Beardstown and Valley Drainage and 
Levee District, IL 1942 220,729 - 
South Beardstown Drainage and Levee District, IL 1942 171,839 - 
South Quincy Drainage and Levee District, IL 1940 61,200 - 
South Quincy Drainage and Levee District, IL 1968 1,231,243 - 
South River Drainage District, MO 1941 55,300 - 
South River Drainage District, MO 1966 1,106,056 - 
Spring Lake Drainage and Levee District, IL 1941 185,980 - 
Subdistrict No. 1 of Drainage Union No. 1 and Bay 
Island Drainage and Levee District No. 1, IL 1967 3,306,695 - 
Union Township Drainage District, MO 1947 116,576 - 
Van Meter, IA' 1965 113,842 - 
Inactive Projects 
Ames Lake, IA' 1974 1,791,800 - 
Farmers Levee and Drainage District, IL -- -- -- 
Freeport, IL 1979 286,000 - 
Peoria, IL 1973 534,580 - 
South Beloit, IL 1979 270,000 - 
William L. Springer Lake, IL 1979 4,911,310 - 
1. Authorized by Chief of Engineers (sec. 205, 1948 
Flood Control Act. 
2. Includes $885,000 for disbursement in connection 
with realignment of Interstate Highway 35. 
28-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TALT . Q F AT TTTURT7fl PRFlWT~ 
A lv.A AL.,.JJJLLFZ , J l L L A A.~.. . A 
For Last 
Full Report Federal Contributed 
See Annual Date Funds Funds 
Project Report For Deauthorized Expended Expended 
Campbells Island, 
Mississippi River, IL 1969 1979 $ 76,664 - 
Carroll County Levee 
and Drainage District, IL 1938 1977 - - 
Central City Lake, 
Wapsipinicon River, IA 1970 1977 55,664 - 
Green Island Levee and 
Drainage District, IA 1938 1977 - - 
Henderson River, IL 1964 1977 102,310 - 
Illinois Waterway, IL and IN 
Duplicate Locks 8 1982 1981 - - 
Janesville and Indian 
Ford Dams, WI 1938 1977 - - 
Keithsburg Drainage 
District, IL 1938 1977 - - 
Pecatonica River at 
Darlington, WI - 1977 - - 
Rochester Lake, 
Cedar River, IA - 1977 - - 
TABLE 28-H INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS 
(See Section 30 of Text) 
Date 
Project Inspected 
Alpine Dam, Rockford, IL 
Banner Special DI)rainage and Levee District, IL 
Bear Creek, Hannibal, MO 
Big Lake I)rainage and Levee District, IL 
Blackhawk Creek, Davenport, IA 
Canton, MO 
Clinton, IA 
Coal Creek Drainage and Levee District, IL 
Crane Creek Drainage and Levee District, IL 
DeKalb, IL 
Des Moines, IA 
Des Moines and Mississippi Levee District No. 1, MO 
D)rury Drainage District, IL 
DI)ubuque, IA 
East Liverpool Drainage and Levee District, IL 
East Peoria Drainage and Levee District, IL 
East Peoria Sanitary District, IL 
Elkport, IA 
Fabius River Drainage District, MO 
Farmers D)rainage and Levee District, IL 
Galena, IL 
Green Bay Levee and Drainage District No. 2, IA 
September 1982 
November 1982 
January 1983 
January 1983 
October 1982 
January 1983 
October 1982 
February 1983 
February 1983 
September 1982 
November 1982 
January 1983 
October 1982 
October 1982 
February 1983 
November 1982 
January 1983 
October 1982 
January 1983 
February 1983 
October 1982 
October 1982 
28-18

ROCK ISLAND, IL, DISTRICT 
TABLE 28-H 
(Continued) 
Project 
INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS 
(See Section 30 of Text) 
Date 
Inspected 
Gregory Drainage District, MO 
Henderson County Drainage District No. 1, IL 
Henderson County Drainage District No. 2, IL 
Hennepin Drainage and Levee District 
Hergot Drainage and Levee District 
Hunt Drainage District & Lima Lake Drainage District, IL 
Indian Grave Drainage District, IL 
Iowa River-Flint Creek Levee District No. 16, IA 
Kerton Valley Drainage and Levee District, IL 
Lacey Drainage and Levee District, IL 
Langellier Drainage and Levee District, IL 
Liverpool Drainage and Levee District, IL 
Littleport, IA 
Lost Creek Drainage and Levee District, IL 
Mad Creek, Muscatine, IA 
Marengo, IA 
Mason and Menard Drainage District, IL 
Marion County Drainage District, MO 
Marshalltown, IA 
Meredosia Levee and Drainage District, IL 
Muscatine Island L&DD, & Louisa DD No. 13, IA 
Oakford Special Drainage and Levee District, IL 
Pekin-LaMarsh Drainage and Levee District, IL 
Penny Slough Drainage and Levee District, IL 
Rock Island, IL 
Sabula, IA 
Sanitary District of Beardstown, IL 
Seahorn Drainage and Levee District, IL 
Sny Island Levee Drainage District, IL 
South Beardstown Drainage and Levee District, IL 
South Quincy Drainage and Levee District, IL 
South River Drainage District, MO 
Spring Lake Drainage and Levee District, IL 
Subdistrict No. 1 of Drainage Union No. 1, and Bay Island L&DD No. 1, IL 
The Sny Basin, IL 
Valley Drainage and Levee District, IL 
Van Meter, IA 
West Matanzas Drainage and Levee District, IL 
January 1983 
October 1982 
October 1982 
September 1982 
February 1983 
January 1983 
January 1983 
November 1982 
January 1983 
January 1983 
January 1983 
November 1982 
October 1982 
February 1983 
October 1982 
November 1982 
February 1983 
January 1983 
November 1982 
October 1982 
October 1982 
February 1983 
November 1982 
September 1982 
October 1982 
October 1982 
February 1983 
January 1983 
January 1983 
February 1983 
January 1983 
January 1983 
November 1982 
October 1982 
January 1983 
February 1983 
November 1982 
January 1983 
28.19 
~ __

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 28-I FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION 
Flood Control Activities pursuant to section 205, Public Law 
858, 80th Congress, as amended (preauthorization) 
(See Section 32 of Text) 
Study Identification Fiscal Year Costs 
Cedar River, Waverly, IA $12,710 
Coal Run Creek, Streator, IL 1,049 
DePue, IL 7,500 
Horse Creek, Pawnee, IL 76 
LaPorte City, IA 14,325 
Union Township Drainage District, MO 212 
Vermilion River, Pontiac, IL 87,146 
TABLE 28-I Snagging and Clearing Navigable Streams and 
Tributaries in the Interest of Flood Control (preauthorization) 
(Sec. 208, 1954 Flood Control Act, P.L. 780, 83rd Congress) 
Project and Location Fiscal Year Costs 
Buckhart Creek, Stonington, IL $ 797 
Honey Creek, Henderson County, IL 64 
Partridge Creek, Woodford County, IL 13,123 
Wolf Creek, Black Hawk County, IA 7,500 
TABLE 28-I Emergency Bank Protection (Section 14 of 
the 1946 Flood Control Act, Public Law 526, 79th Congress) 
Project and Location Fiscal Year Costs 
Canal Bridge, North Fabius River, MO $ 7,017 
Mahaska County Road, Des Moines River, IA 7,500 
TABLE 28-I FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION 
Emergency flood control activities - repair, flood fighting, and 
rescue work (Public Law 99, 84th Cong., and antecedent legislation) 
(See Section 32 of Text) 
Project and Location Federal Cost 
Advance Preparation 
Emergency Operations 
Rehabilitation: 
Bell Levee, IL 
Big Lake Drainage District, IL 
Billmeyer-Connell-Cullinan Levee, IL 
Brennan and Wheeler Levee, MO 
Carl Spurgeon Levee, MO 
Cassell Levee, IL 
Cincinnati Levee, IL 
C. Frank No. 1 Levee, IL 
Clear Lake Levee, IL 
$ 131,124 
82,692 
24,964 
4,857 
28,615 
2,231 
2,352 
24,511 
65,800 
17,616 
70,918 
28&20

ROCK ISLAND, IL, DISTRICT 
TABLE 28-I 
(Continued) 
FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION 
Emergency flood control activities - repair, flood fighting, and 
rescue work (Public Law 99, 84th Cong., and antecedent legislation) 
(See Section 32 of Text) 
Project and Location Federal Cost 
David Winters Levee, IL 
Dobey Levee, IL 
East of Lynn Ditch, IL 
East of Middle Creek, IL 
E. Franks No. 1 Levee, IL 
Elmer Munzlinger Levee, MO 
George Levee, IL 
Gertrude Bash Levee, MO 
Globe Levee, IL 
Gluek Levee 
Goeken-Garman Levee, IL 
Hager Slough Levee, IL 
Hale-Vogler Levee, IL 
Hanes Levee, IL 
Herman Levee, IL 
Hoffman Levee, IL 
lungerich No. 1 Levee, IL 
lungerich No. 3-Fluegel Levee, IL 
John Reiff Levee, MO 
Judy Dunham Levee 
Kahler-Dixon Levee, IL 
Lantz-Dickinson Levee, IL 
Mauer-Woodrow Levee, IL 
Moorhead Levee, IL 
Morris Cullinan Levee, IL 
Morris-Winkler-Cullinan Levee, IL 
Murphy Levee, IL 
North Edwards River-West Mud Creek, IL 
Proehl-Velde Levee, IL 
Rhodes-Cromister Levee, IL 
Riverdale Farms, IL 
Steffenville Drainage District, MO 
Stout-Lipkin Levee, IL 
Thompson Drainage and Levee District, IL 
West of Middle Creek, IL 
Storm Investigations 
Miscellaneous Levees, IL and MO 
Total Rehabilitation 
$ 25,006 
10,883 
31,333 
43,112 
10,956 
42,502 
12,593 
23,698 
57,251 
15,881 
18,694 
362,106 
7,723 
9,094 
71,036 
8,750 
13,003 
21,055 
6,657 
26,869 
8,808 
11,169 
38,326 
21,583 
12,790 
15,923 
17,474 
124,401 
25,406 
8,228 
18,027 
3,223 
10,656 
240,990 
39,921 
46,544 
13,585 
$1,727,130 
TABLE 28-J ILLINOIS WATERWAY: 
EXISTING LOCKS AND DAMS 
(See Section 1 of Text) 
Depth on 
Dimensions Miter Sills 
at Low Water 
Available Lift at 
Miles Width of Length for Low 
Above Chamber Full Width Water' Lower Upper 
Lock Mouth Miles to Nearest Town (feet) (feet) (feet) (feet) (feet) 
LaGrange Lock 
Peoria Lock 
Starved Rock Lock 
80.2 
157.7 
231.0 
7.8 below Beardstown, IL 
4.1 below Peoria, IL 
Utica, IL 
110 
110 
110 
600 
600 
600 
10.0 
11.0 
18.5 
13.0 
12.0 
14.0 
28-21 
15.5 
15.5 
16.8

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 28-J 
(Continued) 
ILLINOIS WATERWAY: 
EXISTING LOCKS AND DAMS 
(See Section 1 of Text) 
Depth on 
Dimensions Miter Sills 
at Low Water 
Available Lift at 
Miles Width of Length for Low 
Above Chamber Full Width Water' Lower Upper 
Lock Mouth Miles to Nearest Town (feet) (feet) (feet) (feet) (feet) 
Marseilles Lock 244.6 Marseilles, IL 110 600 24.45 14.0 18.6 
Dresden Island Lock 271.5 8 above Morris, IL 110 600 21.75 12.25 16.85 
Brandon Road Lock 286.0 Joliet, IL 110 600 34.0 13.8 17.85 
Lockport Lock 291.1 Lockport, IL 110 600 30.5-39.52 15.0 11.0.20.02 
T.J. O'Brien Lock 326.5 Chicago, IL 110 1,000 - 14.0 14.0 
Grand Calumet River 329.5 Hammond, IN 110 1,000 - 14.0 14.0 
1. Lifts and depth on miter sills are those obtained with port is due to fluctuation of water surface in the sanitary 
flat pools. district canal. 
2. Variation in lift and depth on upper miter sill at Lock- 
TABLE 28-K ILLINOIS WATERWAY, IL AND IN 
LOCK AND DAM CONSTRUCTION, FOUNDATIONS, COST 
(See Section 1 of Text) 
Lock Dam Estimated 
Federal Cost 
Under 
Type of Character of Type of Character of Year Existing 
Name Construction Foundation Kind Construction Foundation Complete Project 
Illinnia Rir, - - - - - - $ 9 739 A-I 
mouth to Utica; 
channel improvement 
by dredging 
in Illinois River 
below Starved 
Rock, modification 
of two U.S. 
locks and dams, 
and removal of 
two State dams. 
LaGrange 
Peoria 
Starved Rock 
Marseilles 
Dl)resden Island 
Concrete Piles in sand 
Concrete Piles in sand 
Concrete Rock 
Concrete Rock 
Concrete Rock 
Movable 
(wicket 
with Aframe-
crest) 
Movable 
(wicket 
type) 
Movable 
(tainter 
gates) 
Movable 
Concrete 
and timber 
Concrete 
and timber 
Piles in sand 
Piles in sand 
Concrete Rock 
and 
structural 
steel 
Concrete 
and. 
(tainter structural 
gates) steel 
Movable Concrete 
and 
(tainter structural 
gates) steel 
Rock 
Rock 
28-22 
1939 
1939 
1933 
1933 
1933 
2,744,592' 
3,381,0301 
885,315' 
1,853,725' 
2,503,376' 
, ,d -V

ROCK ISLAND, IL, DISTRICT 
TABLE 28-K 
(Continued) 
ILLINOIS WATERWAY, IL AND IN 
LOCK AND DAM CONSTRUCTION, FOUNDATIONS, COST 
(See Section 1 of Text) 
Lock Dam Estimated 
Federal Cost 
Under 
Type of Character of Type of Character of Year Existing 
Name Construction Foundation Kind Construction Foundation Complete Project 
Brandon Road Concrete Rock Movable Concrete Rock 1933 2,031,6831 
and 
(tainter structural 
gates) steel 
Lockport Concrete Rock Movable Concrete Rock 1933 133,608' 
and 
(Bear trap) structural 
steel 
T.J. O'Brien Concrete Piles in clay Fixed3 Concrete Piles in clay 1960 6,954,700' 
and sheet and sheet 
piling piling 
Lock and dam - - - - - 1,250,304' 
equipment 
Total Locks - - - - - $ 24,471,832 
and dams 
1. Actual cost. 
TABLE 28-L ILLINOIS WATERWAY, IL AND IN 
ADDITIONAL FEATURES ENTERING INTO COST 
(See Section 1 of Text) 
Dredging: 
Little Calumet and Calumet Rivers $ 2,135,358' 
Calumet-Sag, 3 passing places 813,418' 
Starved Rock to Lockport 3,650,635 
Starved Rock to Grafton 2,686,307 
Calumet-Sag Channel 19,238,200 
Peoria small boat harbor 24,937' 
Protection piers at all locks 77,613' 
Calumet-Sag modification engineering and design 5,141,474 
Calumet-Sag modification, supervision and administration 5,466,804 
Rebuild highway bridges 19,327,850 
Rebuild railway bridges: 
Calumet-Sag Channel 20,828,435' 
Little Calumet and Calumet Rivers 18,362,041' 
Recreation Facilities, Code 711 445,000 
Removal of Blue Island lock 288,6001 
Grand Calumet River controlling works2 
St. Louis District 1,081,600' 
Total additional features $ 99,569,604 
Total existing project $124,041,436 
1. Actual cost. 2. Placed in inactive status 19 November 1974. 
2&23

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 28-M EXISTING PROJECT 
See 
Section 
in Text Project Item Length (feet) Width (feet) Depth (feet) 
1. Illinois Waterway, Nine locks and six dams 
IL and IN 
Grafton to Lockport, IL 291.1 miles 300 9 
Lockport to controlling works 2.0 miles 200-300 9 
Controlling works to junction with 10.0 miles 225 9 
Calumet-Sag Channel 
Calumet-Sag Channel to lock in Blue 16.0 miles 225 9 
Island 
Calumet and Little Calumet Channel, 7.7 miles 300 9 
from Blue Island to turning basin 5 
Grand Calumet River Channel from 9.0 miles 9 - 
junction with Little Calumet River 
to and in Indiana Harbor Canal to 
141st, East Chicago, IN 
Also, Grand Calumet River Channel 4.2 miles 160 9 
from junction of Indiana Harbor 
Canal and Grand Calumet River to 
Clark St. in Gary, IN, with a 
turning basin at Clark St. 
A channel in Chicago Sanitary and 22.1 miles 175-300 9 
Ship Canal and South Branch 
Chicago River from Sag-Junction 
to Lake St. in Chicago, IL 
TABLE 28.N ILLINOIS WATERWAY, IL AND IN 
TOTAL COST OF EXISTING PROJECT 
TO SEPTEMBER 30, 1983 
(See Section 1 of Text) 
New Work Maintenance Rehabilitation Total 
Regular Funds $118,317,640 $186,093,451 $27,689,248 $332,100,339 
Public Works Funds 3,960,735 - - 3,960,735 
Emergency Relief Funds 1,858,936 - - 1,858,936 
Total $124,137,311 $186,093,451 $27,689,248 $337,920,010 
1. Includes $1,735,890 expended between 1927 and 1936 under the provisions of the permanent indefinite appropriaon 
the operation and care of the works of improvement tion for such purposes. 
28-24

MISSISSIPPI RIVER 
BETWEEN MISSOURI RIVER 
AND MINNEAPOLIS, MN 
thSreeec trieoanc hoef sr,i vuenrd ceorv seurepde rivni stihoins report is divided into Rock Island District extends about 314 miles from mile and direction of Dis- 300 to 614; and St. Paul District extends about 244 
trict Engineers at St. Louis, Rock Island, and St. Paul. miles from mile 614 to Soo Line Railroad bridge, Min- 
Section in St. Louis District extends 105 miles from neapolis (mile 857.6). 
Mouth of Missouri River to mile 300 above Ohio River; 
Location. Mississippi River rises in northern part 
of Minnesota, flows about 2,360 miles southerly and 
empties into Gulf of Mexico. Portion included in this 
report extends about 663 miles from mouth of Missouri 
River to Soo Line Railroad bridge, Minneapolis. Latest 
map and profile showing this section of river is in 
House Document 669, 76th Congress, 3d session. A 
map showing Lake Pepin is in House Document 511, 
79th Congress, 2d session. A map of section Minneapolis 
to Dubuque is in House Document 515, 79th 
Congress, 2d session. A map showing location of 
drainage districts (Bellevue, Iowa, to Missouri River) 
is in Rivers and Harbors Committee Document 34, 
75th Congress, 1st session. 
Previous projects. See page 1199 of Annual 
Report for 1963. 
Existing project. Provides for a channel of 9-foot 
depth and adequate width between mouth of Missouri 
River (1,179 miles from the gulf) and Soo Line Railroad 
at Minneapolis, by construction of a system of locks 
and dams, supplemented by dredging. Project also 
provides for further improvements at St. Paul to provide 
a basin extending downstream from Robert 
Street Bridge for 2.7 miles, and at Minneapolis to provide 
adequate terminal facilities, and for other harbor 
improvements and miscellaneous work. Pertinent 
data on locks and dams, harbor improvements, additional 
features entering into cost of project, and authorizing 
legislation are given in Tables 29-C, 29-D, 29-E 
and 29-G. All dams are concrete. Three dams (Upper 
St. Anthony Falls, 1 and 19) are fixed, remainder are 
movable. Estimated cost for new work (1982) is 
$894,157,300 exclusive of amounts expended on previous 
projects. See House document 669, 76th Congress, 
3d session, for a report of Chief of Engineers 
dated February 27,1940, containing a general plan for 
improvement of Mississippi River between Coon Rapids 
Dam and mouth of Ohio River for purposes of 
navigation, power development, flood control, and 
irrigation needs. 
Local cooperation. Small-boat harbors authorized 
in the River and Harbor Act of 1962 are subject to 
conditions that local interests make a cash contribution 
toward cost of construction (except in case of 
Quincy Harbor which involves maintenance only of 
an existing harbor); furnish lands and rights-of-way 
for construction and future maintenance; hold the 
United States free from damages; provide and maintain 
mooring facilities and utilities; reserve accommodations 
for transient small boats; accomplish all 
necessary relocations and alterations; and establish 
public bodies empowered to regulate use, growth, and 
development of the harbors. 
Rectification of seepage damages to privately 
owned lands in the Sny Island Levee Drainage District, 
IL, is subject to the conditions that local interests 
acquire all lands, easements, and rights-of-way necessary 
for construction and maintenance of the project; 
comply with applicable provisions of the Uniform 
Relocation Assistance and Real Property Acquisition 
Policies Act of 1970; accept, operate, and maintain the 
project upon its completion; and hold and save the 
United States free from damages arising from the construction 
and operation of the completed project; provided 
further that the local public entity shall be reimbursed 
by the Government in the amounts actually 
expended by it in the acquisition of real estate and for 
payments required under Public Law 91-646 if said 
amounts have been previously submitted to and 
approved by the Government. 
Local cooperation requirements for improvement of 
commercial harbor at Dubuque, IA; for improvement 
of Beaver Slough at Clinton, IA, for navigation; and 
for general navigation facilities at small-boat harbors 
at Rock Island, IL; Hannibal, MO; Fort Madison, IA, 
Davenport (Lindsay Park), IA; Muscatine, IA (including 
freight terminal approach channel); Andalusia, 
IL; Warsaw, IL; Moline, IL; Clinton, IA; and Savanna, 
IL, have been complied with. 
Licenses. Federal Energy Regulatory Commission 
collects from non-Federal licensees annually to 
recompensate the United States for use of Government 
dams for generation of hydroelectric power. Amounts 
collected are returned to U.S. Treasury. (See table at 
29-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
end of chapter for license fees collected through the 
end of the fiscal year.) 
Terminal facilities. Considered adequate for 
existing commerce. 
Operations during fiscal year. St. Paul District. 
New Work: Studies were continued under Section 
107, small navigation project authority, for establishment 
of small-boat harbors at Lake City, MN, at a 
cost of $21,137 and at Pike Island, MN, at a cost of 
$42,048. A contract was awarded in September 1983 
for construction of the Lake City small-boat harbor. 
Construction of sanitary facilities at Blackhawk Park 
in pool 9 cost $23,576 by contract and $1,574 by hired 
labor. Construction by contract for recreation facilities 
at Lake Rebecca in pool 2 was completed at a cost of 
$16,975. Engineering and design cost $15,378 and 
supervision and administration cost $682. Total costs 
for recreation facilities at Lake Rebecca were $33,035. 
Total cost of new work was $121,370. 
Maintenance: Channel dredging to remove shoal 
areas was performed. Government pipeline dredge 
WILLIAM A. THOMPSON removed 368,000 cubic 
yards of material at 7 locations at a cost of $929,559. 
Government derrick barge HAUSER removed 94,900 
cubic yards of material at 4 locations for $275,789. 
Mechanical dredging contract costs were $338,308. 
Other dredging and snagging cost $111,472. Water 
quality testing for dredging cost $128,966. 
Painting at locks and dams cost $690,733. Scour 
repair contracts at Locks and Dams 3, 5A, 6, 7, 9 and 10 
cost $449,999, $5,000, $1,092,027, $286,982, $577,658 
and $279,999, respectively. Contracts for repair of 
locks and guidewalls at Locks and Dams 4, 5 and 5A 
cost $169,285, $100,703, and $131,008, respectively. 
Contracts for bridge rehabilitation and roads at Lock 
and Dam No. 1 cost $34,521 and $152,776, respectively. 
Contracts to replace a water line and to repair gates at 
Lower St. Anthony Falls cost $38,387 and $98,013, 
respectively. Engineering work and miscellaneous 
surveys, reports, and other work were carried on by 
hired labor for $1,402,925 and by contract for $218,868. 
Contracts for rehabilitation of auxiliary gates at Lock 
and Dam No. 8, modification of the upper approach at 
Lock and Dam No. 5, construction of a loading dock at 
Lock and Dam No. 2 and construction of a loading 
dock and Lock and Dam No. 6 cost $144,723, $19,999, 
$125,000, and $29,999, respectively. Total cost of maintenance 
was $11,306,601. 
Rehabilitation: Stage 2 work for rehabilitation of 
Lock and Dam No. 1 was accomplished by contract at 
a cost of $524,929. Contract work Stage 3 - Sewer and 
Water Line, Stage 5B - Roads and Drainage and 
Stage 5C - Security Fencing was accomplished by 
contract at a cost of $21,669, $113,203, and $64,483, 
respectively. Government furnished materials for 
lower miter gate bulkhead cost $139,170. Other miscellaneous 
contracts and hired labor for construction cost 
$83,261. Engineering and design cost $69,257 by contract 
and $103,807 by hired labor. Supervision and 
administration cost $94,777. Total rehabilitation costs 
were $1,214,556. 
Operating and care: Locks and dams were operated 
as required, and necessary repairs were made to 
those and appurtenant structures. Other studies, 
reports, and miscellaneous engineering work were 
also accomplished. Total cost of operating and care 
was $8,381,981. 
Costs to St. Paul District were $121,370 for new 
work, $19,688,582 for operation and maintenance, and 
$1,214,556 for rehabilitation, for a total of $21,024,508. 
Rock Island District. New Work: Costs in connection 
with rectification of seepage damages in the 
Sny Island Levee Drainage District, IL, were $15. 
Recreational improvements at public use areas along 
the Mississippi River cost $204,123. Costs in connection 
with small-boat harbor at Savanna, IL, were 
-$427. Total new work costs were $203,711. 
Rehabilitation: Rehabilitation of auxiliary lock at 
Locks and Dam 14 was completed at a cost of $70,954. 
Construction of permanent closure at old Lock 19 was 
completed at a cost of $74. Total rehabilitation: 
$71,028. 
Maintenance: Channel dredging by Government 
cutterhead pipeline dredge WILLIAM A. THOMPSON 
was performed at various locations in pools 17, 
18, 19, 20, 21, and 22 at a cost of $1,213,500, with 
631,568 cubic yards of material being removed. Snagging, 
clearing, and excavation was performed by hired 
labor at various locations at a cost of $321,500. Preand 
post-dredge disposal and other environmental 
concerns in connection with dredging and channel 
maintenance activities cost $376,300. In accordance 
with Public Law 97-257, which provided for lump-sum 
compensation to the Sny Island Levee Drainage District, 
IL, for seepage damages caused by construction 
and operation and maintenance of the Mississippi 
River Nine-Foot Channel Navigation Project, a payment 
in the amount of $2,146,800 was made to the 
drainage district on December 27, 1982, and a Release 
and Indemnity Agreement was executed by the Commissioners 
of the drainage district on the same date 
which released the Government from all future claims 
and liabilities for damages. Repair of regulating 
works structures was performed at a cost of $1,035,400. 
Structural repairs, including sandblasting and painting, 
were performed by hired labor at locks and dams 
at a cost of $1,788,300. Contractor earned $1,426,300 
on contract for replacing service bridge cranes on the 
dams at eleven locations, and another contractor 
earned $376,300 for installation of two guide cells at 
Lock and Dam 22. Contractor earned $83,800 for 
painting dam roller gates at Lock and Dam 15, and 
another contractor earned $11,800 for painting dam 
roller and tainter gates and service bridge at Lock and 
Dam 17. Contractor earned $89,300 for completion of 
maintenance and shop building at Lock and Dam 15. 
Other buildings, grounds, and utility maintenance 
totaled $25,000. Permanent operating equipment costs 
were $341,300. Maintenance of public use areas was 
performed at a cost of $750,800. Maintenance of levees 
cost $17,900. Engineering and design work totaled 
$467,600. Supervision and administration and district 
29-2

MISSISSIPPI RIVER BETWEEN MISSOURI RIVER AND MINNEAPOLIS, MN 
overhead for the maintenance features totaled 
$884,000. Total maintenance costs were $11,355,900. 
Net credits to the project were $202,900, primarily as a 
result of collection of damages from towboat companies 
to lock and dam structures. 
Operating and care: Operation of the locks and 
dams and routine maintenance and minor repairs 
thereto were performed at a cost of $5,943,500. Real 
estate management services were performed at a cost 
of $120,300. Natural resources activities cost $106,000, 
and operation of public use areas cost $705,300, with 
contract law enforcement provided at a cost of $73,400. 
Surveys, various studies and structural inspections 
cost $865,000. The sum of $73,200 was expended on 
Master Plans; water control management costs were 
$575,100; and other operation activities cost $71,100. 
Supervision and administration and district overhead 
for operation features totaled $1,240,400. Total operation 
costs were $9,773,300. Total operation and maintenance 
costs were $20,926,317. 
Costs to Rock Island District were $203,711 for new 
work and $20,926,317 for operation and maintenance 
for a total of $21,130,028. 
St. Louis District. New work: Costs incurred for 
New Lock and Dam 26 were $665,704 for real estate 
management, $5,799 for relocations, $53,016,622 for 
dams, $237,804 for channels and canals, $1,657,974 for 
levees and floodwalls, $347,443 for buildings, grounds 
and utilities, $778 for permanent operating equipment, 
$7,686,780 for engineering, and $3,137,745 for 
supervision and administration. Total cost of new 
work was $66,756,649. 
Maintenance: Costs incurred for the year were 
$6,989,178, including $5,129,337 for dredging 2,573,718 
cubic yards. 
Operating and care: The locks and dams were 
operated as required, and necessary repairs were made 
thereto and to appurtenant structures at a cost of 
$3,353,085. GREAT studies totaled $18,324. 
Costs to St. Louis District were $66,756,649 for new 
work and $10,360,587 for operation and maintenance 
for a total of $77,117,236. 
Condition at end of fiscal year. For information 
pertaining to locks, dams and harbors, see tables at 
end of chapter. 
St. Paul District. Work completed: Locks and 
Dams at St. Anthony Falls and Nos. 1 to 10, inclusive, 
except for relatively minor appurtenant work; major 
improvements of channels and harbors at St. Paul and 
Minneapolis; commercial harbors at Lake City, Red 
Wing, and Winona, MN; and Prairie du Chien, WI; 
small-boat harbors at St. Paul, Hastings, Red Wing, 
Wabasha, and Winona, MN; Lansing, IA; and Bay 
City, Pepin, and Prairie du Chien, WI; a remedial 
drainage ditch at Cochrane, WI; miscellaneous channel 
dredging and realignment; channel markers; pool 
clearing; and construction of various facilities for 
recreation use. Seepage damages totaling $90,027 
were paid to 210 claimants. 
Status of land and flowage acquisition: 
Approximately 50,293.54 acres of land in fee, including 
47,305 acres used by the Department of the Interior 
in accordance with a cooperative agreement and general 
plans, and easements of 15,549.63 acres of land 
are owned and controlled in pools 1 to 10, inclusive, at 
end of fiscal year. In addition, fee title to 12.46 acres 
and perpetual easements on 2.98 acres of land for St. 
Anthony Falls and perpetual easements over 244.39 
acres of land for harbors have been obtained and 
Department of the Army holds special rights over 
62,954.74 acres owned by Department of the Interior in 
pools Nos. 3 to 10, inclusive. Land acquisition is 
complete. 
Work remaining to complete portion of project 
in St. Paul District: Guidewall extension at Lock No. 
3 (the uncompleted guidewall extensions at Locks Nos. 
4, 5, 5A, 7, 8, 9 and 10 were reclassified from the 
"active" to the "inactive" category on April 13, 1973); 
realignment of channel at Wilds Bend; construction of 
small-boat harbor at St. Paul (Harriet Island), MN; 
and construction of additional recreational facilities. 
Condition of channel at end of fiscal year was such 
that controlling depths of 9 feet at low water and minimum 
widths for long-haul common carrier service 
were available in all pools. Except for Lock No. 1 
which is in poor condition due to age and obsolescence, 
structures are in good condition. Rehabilitation of 
Lock No. 1 is underway. 
Rock Island District. Work completed: Major 
construction items, including all locks and dams, are 
completed and in operation. The following related 
work has also been completed: Construction of smallboat 
harbors at Rock Island, IL; Moline, IL; Andalusia, 
IL; Warsaw, IL; Fort Madision, IA; Davenport 
(Lindsay Park), IA; Muscatine, IA; Clinton, IA; and 
Hannibal, MO; improvement of Beaver Slough at 
Clinton, IA, for navigation; improvement of commercial 
harbor at Dubuque, IA; rehabilitation of Locks 
and Dams 11 through 14; rehabilitation of old auxiliary 
lock at Lock and Dam 14; permanent closure of old 
Lock 19 and drydock; rock and conglomerate excavation 
in Pool 16; rectification of seepage damage in the 
Sny Island Levee Drainage District, IL; recreational 
facilities: and construction of visitors c'ii cer at Lock 
15.
Work remaining to complete portion of project 
in Rock Island District: Construction of guide wall 
extensions at 16, 18, and 21; mooring facilities at 11, 
12, 14, 15, 16, 17, 18, and 22; upper approach improvement 
at 19; upper approach dike at 20; removal of 
remainder of lateral dam in Pool 14; rock and/or conglomerate 
excavation in Pools 14, 15, 18, and 21; and 
construction of small-boat harbors at Keokuk, IA, and 
New Boston, IL, and commercial harbor at Fort Madison, 
IA. Planning for the small-boat harbor at 
Savanna, IL, is currently under way. Small-boat harbors 
at Bellevue, IA, Cassville, WI, and Davenport 
(Credit Island), IA, are inactive or have been 
deauthorized. 
29-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Status of land and flowage acquisition: Acquisition 
of land in Pools 11 to 22, inclusive, consisting of 
93,601 acres in fee and 10,541 acres in flowage easement, 
has been completed. 
Condition of the channel at end of fiscal year, was 
such that controlling depths of 9 feet at low water and 
widths suitable for long-haul common carrier service 
were being maintained in all pools. 
St. Louis District. Work completed: Locks and 
Dams Nos. 24, 25, and 26 (Henry T. Rainey Dam), 
except for guidewall extensions at Locks Nos. 24 and 
25, have been completed as have recreation facilities 
at the three pools. Payments for rectification of damages 
have been completed. Other work remaining consists 
of construction of guidewall extensions at Locks 
Nos. 24 and 25 and replacement of Lock and Dam 26. 
Status of land and flowage acquisitions. Acquisition 
of lands in Pools Nos. 24, 25, and 26, involving 
41,451 acres of land in fee and flowage easements over 
6,600 acres, is complete. A total of 1,742 acres have 
been acquired for Lock and Dam No. 26 replacement 
project. 
Condition of channel at end of fiscal year was such 
that controlling depth of nine feet at low water and 
generally suitable widths for long-haul common carrier 
services were maintained in all pools and between 
Locks and Dam, No. 26 and Missouri River. 
Total Federal cost of existing project to end of fiscal 
year for the three Districts was $1,027,560,205 of 
which $426,427,265 was for new work, ($351,680,961 
regular funds, $51,895,959 public works funds and 
$22,850,345 emergency relief funds), $543,701,163 regular 
funds for maintenance and $57,431,777 regular 
funds for rehabilitation. 
29-4

MISSISSIPPI RIVER BETWEEN MISSOURI RIVER AND MINNEAPOLIS, MN 
TABLE 29-A COST AND FINANCIAL STATEMENT 
Total Cost to 
Project Funding FY 80 FY 81 FY 82 FY 83 Sept. 30, 1983 
Mississippi River New work1 
between Missouri Approp.2 32,788,912 24,347,000 79,335,000 70,105,398 472,545,407 
River and Costs 32,145,428 21,018,262 81,990,472 67,081,730 467,897,198 
Minneapolis, Maint.4 
Minnesota Approp. 35,160,441 37,176,200 43,131,000 58,946,856 564,319,486 
(Federal Funds) Cost 36,254,582 37,840,349 41,288,859 50,975,486 545,650,464 
Rehab. 
Approp. 17,417,000 17,867,000 8,040,000 0 57,533,035 
Cost 17,850,815 18,943,007 6,927,351 1,214,556 57,431,777 
(Contributed New Work 
Funds) Approp. 0 0 0 400,000 1,687,541 
Cost 42,338 0 0 0 1,287,540 
'Includes $41,469,956 for new work on previous projects. 
2Includes replacement Lock and Dam 26 funds $215,207,000 appropriation. 
3lncludes replacement Lock and Dam 26 funds $211,152,168 cost. 
4Includes $6,554,725 for maintenance on previous projects. 
TOTAL COSTS OF EXISTING PROJECT 
TABLE 29-B TO SEPTEMBER 30,1983 
Regular Public Work Emergency 
District Cost Funds Funds Relief Funds Total 
St. Paul New Work1 $ 59,277,5792 $24,210,071 $ 9,071,214 $ 92,558,864 
Maintenance3 211,399,162 - - 211,399,162 
Rehabilitation 44,498,580 - - 44,498,580 
Total 315,175,321 24,210,071 9,071,214 348,456,606 
Rock Island New Work4 64,796,7696 17,403,322 11,338,865 93,538,956 
Maintenance 193,105,817 - - 193,105,817 
Rehabilitation 12,933,197 - - 12,933,197 
Total 270,835,783 17,403,322 11,338,865 299,577,970 
St. Louis New Work7 227,606,613 10,282,5666 2,440,266 240,329,445 
Maintenance 139,196,184 - - 139,196,184 
Total 366,802,797 10,282,566 2,440,266 379,525,629 
'Excludes $1,228,541 contributed funds. Includes $7,673 
expended in pool No. 11. 
2Includes $159,359 transferred from Rock Island District 
covering pro rata share of cost of derrick boat Hercules. 
3Includes $762,196 expended between 1930 and 1936 on 
operating and care of works of improvement under provisions 
of permanent indefinite appropriation for such 
purposes. 
4Excludes $58,999 contributed funds. 
5$687,709 was transferred to St. Louis District in fiscal 
year 1958. Excludes $201,167 transferred to St. Paul and St. 
Louis Districts covering their pro rata shares of cost of derrick 
boat Hercules. 
6Includes $47,800 transferred from Rock Island District 
covering pro rata cost of derrick boat Hercules and $687,709 
transferred from Rock Island District. 
7Includes $211,152,168 for replacement of Lock and Dam 
26. 
29-5

TABLE 29-C LOCKS AND DAMS 
Lock Dimensions 
Greatest Estimated 
Length Percent Cost of 
Width Avail- Upper Depth on Character of Foundation Complete Year Each Lock 
Miles of able for Normal Miter Sill Locks, Opened and Dam 
Lock Above Miles from Cham- Full Pool Dams, to Including and Ohio Nearest ber Width Lift Eleva- Upper Lower and Work Navi- Work 
Dam River Town (feet) (feet) (feet) tion' (feet) (feet) Lock Dam in Pool gation in Pool 
St. Anthony 853.9 In city of 
Falls, upper 
lock 
St. Anthony 
Falls, lower 
lock and dam 
Lock and dam 
1 
Lock and dam 
2 
Lock and dam 
3 
Lock and dam 
4 
Lock and dam 
5 
Lock and dam 
5A 
Lock and dam 
6 
Lock and dam 
7 
Lock and dam 
8 
Lock and dam 
9 
Lock and dam 
10 
Lock and dam 
11 
Lock and dam 
12 
Lock and dam 
13 
Lock and dam 
14 
Le Claire lock 
(Canal) 
Minneapolis, 
MN 
853.3 In city of 
Minneapolis, 
MN 
847.6 Minneapolis- 
St. Paul 
815.2 1.3 above 
Hastings, MN 
796.9 6.1 above Red 
Wing, MN 
752.8 Alma, WI 
738.1 Minneiska, MN 
728.5 3 above 
Winona, MN 
714.3 Trempealeau, 
WI 
702.5 Dresbach, MN 
679.2 Genoa, WI 
3.3 below 
Lynxville, WI 
Guttenberg, 
IA 
3.7 above 
Dubuque, IA 
Bellevue, IA 
4.3 above 
Clinton, IA 
3.7 below 
Le Claire, IA 
3.9 below 
Le Claire, IA 
647.9 
615.1 
583.0 
556.7 
522.5 
493.3 
493.1 
1 56 400 49.2 799.2 15.7 13.7 Some lime- Limestone 1002 - $18,203,000 
* stone, mainly 
sandstone. No 
piles. 
56 400 26.94 750.0 13.7 10.3 Sandstone. No Sandstone 
piles. 
56 400 35.94 725.1 13.54 10.1 Rock and piles Piles in gra 
56 400 35.9 - 12.57 7.6 in gravel. 
110 500 12.2 - 16.0 15.1 Piles in sand, Piles in san 
1108 6008 12.2 687.2 22.2 13.0 silt and clay. silt and cl 
110 600 8.0 675.0 17.0 14.0 Piles in sand, Piles in san 
silt and clay. 
110 600 7.0 667.0 17.0 13.0 Piles in sand Piles in san 
and gravel, and grave 
110 600 9.0 660.0 18.0 12.0 Piles in sand Piles in san 
and gravel. 
110 600 5.5 651.0 18.0 12.5 Piles in sand. Piles in sar 
110 600 6.5 645.5 17.0 12.5 Piles in sand, Piles in sar 
gravel and and clay 
silt. 
110 600 8.0 639.0 18.0 12.0 Piles in sand Piles in sar 
and gravel. 
110 600 11.0 631.0 22.0 14.0 Piles in sand, Piles in san 
gravel, and and grave 
broken rock. 
110 600 9.0 620.0 16.0 13.0 Piles in sand. Piles in san 
110 600 8.0 611.0 15.0 12.0 Piles in sand. Piles in san 
110 600 11.0 603.0 18.5 12.5 Piles in sand, Piles in san 
gravel and 
silt. 
110 600 9.0 592.0 17.0 13.0 Piles in sand Piles in san 
and gravel, and grave 
110 600 11.0 583.0 19.0 13.0 Piles in sand, Piles in san 
clay and and grave 
gravel. 
110 600 11.0 572.0 20.5 13.5 Rock. Rock 
80 320 11.0 - 17.6 10.9 Rock. Rock 
100 
100 
100 
100 
64 
100 
100 
57 
100 
100 
100 
100 
100 
99 
99 
100 
92 
100 
id 
id 
l 
0 
1959 12,382,0005 
O 
1917 2,358,0006 
1930 6,492,0009 n 
1948 
1938 8,706,000 
'Ti 
1935 4,865,000* 
1935 5,081,000* 
1936 8,009,000* Zz 
1936 4,874,000 
50 
1937 5,574,000* 
1937 6,061,000* 
1938 6,539,000* 
1936 4,750,000* 
1937 7,428,000 
1938 
1938 
1939 
1922 
5,580,000 
7,502,000 
6,284,000
SIt) 
vel 
id, 
ay 
nd 
nd 
l
1d 
id 
nd 
nd 
nd l
rd 
id 
id 
3b

TABLE 29-C (Cont'd) LOCKS AND DAMS 
Lock Dimensions 
Greatest Estimated 
Length Percent Cost of 
Width Avail- Upper Depth on Character of Foundation Complete Year Each Lock 
Miles of able for Normal Miter Sill Locks, Opened and Dam 
Lock Above Miles from Chain- Full Pool Dams, to Including 
and Ohio Nearest ber Width Lift Eleva- Upper Lower and Work Navi- Work 
Dam River Town (feet) (feet) (feet) tion (feet) (feet) Lock Dam in Pool gation in Pool 
Lock and dam 482.9 Foot of Arsenal 110 600 16.0 561.0 24.011 11.0 Rock. Rock 95 1934 10,525,00( 
15 Island Rock 110 360 16.0 - 17.011 11.0 
Island, IL 
Lock and dam 457.2 1.8 above 110 600 9.0 545.0 17.0 12.0 Piles in sand Piles in sand 98 1937 9,788,000 
16 Muscatine, IA and gravel, and gravel 
Lock and dam 437.1 4.2 above New 110 600 8.0 536.0 16.0 13.0 Piles in sand Piles in sand 99 1939 5,843,000 
17 Boston, IL and gravel. 
Lock and dam 410.5 6.5 above 110 600 9.8 528.0 16.5 13.7 Piles in sand. Piles in sand 90 1937 10,308,00C 
18 Burlington, IA 
Lock and dam 364.2 Keokuk, IA 110 358 38.2 518.2 4.5 9.2 Rock. Rock 100 1913 
19 110 1,200 5.0 13.0 99 1957 14,813,000 
Lock and dam 343.2 0.9 above 110 600 10.0 480.0 15.0 12.0 Rock. Rock and piles 97 1936 6,281,000 
20 Canton, MO in sand and 
gravel 
Lock and dam 324.9 2.1 below 110 600 10.5 470.0 16.5 12.0 Piles in sand Piles in sand 95 1938 8,065,000 
21 Quincy, IL and gravel, and gravel 
Lock and dam 301.2 1.5 below 110 600 10.2 459.5 18.0 13.8 Rock. Rock 99 1938 5,275,000 
22 Saverton, MO 
Lock and dam 273.4 Clarksville, MO 110 600 15.0 449.0 19.0 12.0 Rock and piles. Piles in sand 994 1940 10,337,00( 
24 
Lock and dam 241.4 Cap Au Gris, 110 600 15.0 434.0 19.0 12.0 Piles in sand Piles in sand 9914 1939 13,694,00 
25 MO and gravel, and gravel 
Lock and dam 202.9 Alton, IL 110 600 24.0 419.0 19.0 10.0 Piles in sand. Piles in sand 100 1938 12,824,000 
26 (Henry T. 110 360 24.0 - 16.0 10.0 
Rainey Dam) 
New Lock and 200.8 Alton, IL 110 1,200 24.0 419.0 23.0 18.0 Piles in Piles in 8 - 845,050,00 
dam 26 bedrock. bedrock 
Total, Locks $1,073,491,00 
and dams 
)
)
)
)
12 
)
)
)
0
0 
Elevation of pools 1 to 22 and at St. Anthony Falls are 
mean sea level 1912 adjustment; pools 24, 26 are mean sea 
level 1929 adjustment. 
2Includes existing dam, owned by Northern States 
Power Co. 
3Includes dredging above upper lock. (Federal cost only.) 
4Based on pool elevation 723.1 in pool 1 which is crest of 
dam. Pool is normally maintained at elevation 725.1 by 
flashboards. 
5Includes lower approach dredging and dredging 
between upper and lower rock. (Federal cost only.) 
6In addition $1,948,000 expended from previous projects 
and $1,349,600 from O & C appropriation for first of twin 
locks. Excludes lock and dam rehabilitation program. 
'Old upper guard sill. 
8Landward lock. 
91n addition, $1,965,300 expended from previous 
projects. 
'�Existing Le Claire Canal lock is used as auxiliary to 
lock 14; previous project cost $540,000. 
"Depth over upper poiree sill. Depth over upper miter 
sill is 27 feet, at lock 15. 
12$640,868 for first lock was reported by Mississippi 
River Power Company, transferred to Government free in 
lieu of improvements destroyed. (Annual Report, 1928, pp. 
1118-1119.) Present estimate includes $13,132,600 for main 
lock and appurtenant work. 
l :Includes cash contribution of $4,050,000. 
"4Complete except for guidewall extensions. 
*Excludes uncompleted guidewall extensions 
$10,339,000 (1972) reclassified from active to inactive on 
April 13, 1973.

TABLE 29-D HARBOR IMPROVEMENTS 
Miles above Project Approximate size (feet) Actual or 
Name Ohio River Location Type depth Percent Estimated 
(feet) Width Length Complete Cost 
Harriet Island Harbor, 
St. Paul, MN 
St. Paul Harbor, MN 
Hastings Harbor, MN 
Red Wing Harbor, MN. 
Red Wing Harbor, MN 
Bay City Harbor, WI 
Lake City Harbor, MN 
Pepin Harbor, WI 
Wabasha Harbor, MN 
Alma Harbor, WI 
Winona Harbors, MN 
Lansing Harbor, IA 
Prairie du Chien 
Harbor, WI 
Cassville Harbor, WI 
Dubuque Harbor, IA 
Savanna Harbor, IL 
Clinton Harbor, IA 
Moline Harbor, IL 
Davenport Harbor, IA 
(Lindsay Park) 
Rock Island Harbor, IL 
840.2 In city of St. Paul, MN 
836.5-839.2 In city of St. Paul, MN 
839.7 Channel improvement, 
Small-boat harbor and 
channel enlargement. 
813.2 Lower end of city of 
Hastings, MN 
791.4 In city of Red Wing, MN 
791.1 In city of Red Wing, MN 
785.9 Uper end of Bay City, 
773.0 In city of Lake City, MN 
767.1 In city of Pepin, WI 
760.0 Upper end of city of 
Wabasha, MN 
751.3 Upper end of Alma, WI 
726.0 In city of Winona, MN 
Latsch Island 
726.2 Crooked Slough 
663.3 Upper end of city of 
Lansing, IA 
635.5 Upper end of city of 
Prairie du Chien, WI 
635.0 In Marais de St. Friol 
East Channel below 
Hwy bridges. 
606.6 At Cassville, WI 
579.4 At Dubuque, IA 
537.3 At Savanna, IL 
519.0 At Clinton, IA 
488.0 At Moline, IL 
484.2 At Lindsay Park 
479.8 At Rock Island, IL 
Small-boat 
Commercial 
Small-boat 
Small-boat 
Commercial 
Small-boat 
Small-boat 
Small-boat 
Commercial 
Small-boat 
Small-boat 
Small-boat 
Small-boat 
Commercial 
Small-boat 
Small-boat 
Commercial 
Small-boat 
Commercial 
Small-boat 
Small-boat 
Small-boat 
Small-boat 
Entrance channel 
small-boat harbor. 
70 925 
9 400-1,000 2.7 (mile) 
300 400 
5
9
5
5
595 
5
55 
95 
200 
300 
450 
50-100 
400 
500 
50 
175-400 
300 
200 
200 
400 
400 
120 
340 
280 
400 
230 
200 
59 
5 
12
5
5
55 
6 100 
500 
1,200 
800 
5,990 
600 
1,000 
600 
800 
500 
1,000 
6,000 
800 
800 
1,000 
frontage 
565 
1,500 
910 
1,400 
660 
1,150 
0 $270,000 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100
0 
100
0 
78 
100 
217,100 
230,200 
74,300 
146,8002 
8,700 
39,500; 
93,500 
205,5004 
41,700 
56,300 
89,800 
84,700 
95,300 
85,500 
93,100 
178,000 
55,200 
310,000 
101,912 
110,328 
262,100 
1,100 100 31,000 
L~a 
0
0
La Ax 
L'a 
CO

TABLE 29-D (Cont.) HARBOR IMPROVEMENTS 
Project Approximate size (feet) Actual or 
Miles above depth Percent Estimated 
Name Ohio River Location Type (feet) Width Length Complete Cost 
Andalusia Harbor, IL 473.0 Andalusia Slough Small-boat 5 40 435 100 21,000 
Muscatine Harbor, IA 455.5 At Muscatine, IA Small-boat 5 150 950 100 353,000 
455.6 Freight terminal 9 200 1,890 100 J 
approach 
channel 
New Boston Harbor, IL 433.1 In Boston Bay Small-boat 5 90-135 600 0 23,000 
Fort Madison Harbor, 383.7 At Fort Madison, IA Small-boat 5 250 900 100 184,200 
IA 
Fort Madison Harbor, 378.3 At Fort Madison Commercial 9 200 10,300 0 1,070,000 
IA 
Keokuk Harbor, IA 363.5 At Keokuk, IA Small-boat 5 100-160 1,015 0 394,000 
Warsaw Harbor, IL 359.1 At Warsaw, IL Small-boat 5 100 600 100 73,000 
Quincy Harbor, IL 327.3 In Quincy Bay Small-boat 5 200-300 9,000 0 6 
Hannibal Harbor, MO 308.8 At Hannibal, MO Small-boat 5 180-260 600 100 129,000 
Total $5,127,740 
'In addition, local interests will contribute $270,000. 
2In addition, local interests contributed $3,455. 
;In addition, local interests contributed $9,533. 
4In addition, local interests contributed $32,344. 
6Maintenance only, estimated at $5,000 annually. 
1 1 
z
0
0
hO 
C
zd
z
z
0 
I
i

TABLE 29-E 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
ADDITIONAL FEATURES ENTERING INTO 
COST OF PROJECT 
Facilities for public use, convenience and safety 
Rectification of damages caused by seepage and backwater 
Regulating works between lock and dam 26 (Henry T. Rainey Dam) 
and Missouri River 
Improvement of Beaver Slough at Clinton, Iowa, for navigation 
Miscellaneous 
Total additional features 
Total existing project (new work) 
$ 3,359,600 
8,046,000 
545,000 
193,600 
1,312,9002 
13,457,100 
$431,075,451 
'Includes a lump-sum payment of $2,146,800 (O&M 
appropriation) paid to the Sny Island Levee Drainage District, 
IL, for rectification of seepage damages. Also includes 
$140,000 Construction General funds for project studies, 
evaluation, and report preparation. 
2Includes $686,500 for repairs to Stone Arch bridge, 
Minneapolis, MN. (FY 1969) 
3Excludes $227,000 (1965) for inactive remedial measures 
at Sandy Slough, MO. 
TABLE 29-F 
LICENSE FEES COLLECTED 
THROUGH FISCAL YEAR 1983 
Annual Collections to 
Dam Licensee Charge Sept. 30, 1981 
St. Anthony Falls Northern States $ 3,300 $ 70,177 
Lower Lock and Dam Power Co. (No. 2056) 
Lock and Dam No. 1 Ford Motor Co. 95,400 5,535,240 
(No. 362) 
Total project $5,605,417 
29-10

MISSISSIPPI RIVER BETWEEN MISSOURI RIVER AND MINNEAPOLIS, MN 
TABLE 29-G AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
MISSISSIPPI RIVER BETWEEN MISSOURI RIVER 
AND MINNEAPOLIS, MN 
Sept. 22, 1922 Dredging channels to landing places. None 
July 3, 1930 as amended Project adopted from Illinois River to Minneapolis; Chief of H. Doc. 290, 71st Cong., 
by P.R. No. 10, Engineers granted discretionary authority to make such 2d sess. 
Feb. 24, 1932 modification in plan as may be deemed advisable. 
June 26, 1934 Operation of snag boats and operation and care of locks and None 
dams to be provided for with funds from Department of the 
Army appropriations for rivers and harbors. 
Aug. 30, 1935 Missouri River established as lower limit of project. H. Doc. 137, 72nd Cong., 
1st sess. 
Aug. 26, 1937 Extension of 9-foot channel above St. Anthony Falls, MN, H. Doc. 137, 72nd Cong., 
including adequate terminal facilities for Minneapolis, MN 1st sess. 
Aug. 30, 1935 St. Paul, MN, harbor. Rivers and Harbors 
Aug. 26, 1937 
Dec. 22, 1944 
Mar. 2, 1945 
Mar. 2, 1945 
Mar. 2, 1945 
Mar. 2, 1945 
None 
Mar. 2, 1945 
Mar. 2, 1945 
Mar. 2, 1945 
July 24, 1946 
July 24, 1946 
July 24, 1946 
July 24, 1946 
July 24, 1946 
June 30, 1948 
May 17, 1950 
May 17, 1950 
May 17, 1950 
May 17, 1950 
May 17, 1950 
May 17, 1950 
Determine damages to drainage and levee districts caused by 
seepage and backwater, and cost of making rectification thereof. 
Public park and recreational facilities. 
Red Wing, MN, harbor. 
Remedial works to correct damages caused by seepage and 
backwater at Cochrane, WI 
Such changes or additions to payments, remedial works, or land 
acquisitions authorized by River and Harbor Act of Aug. 26, 
1937 (River and Harbor Committee Doc. 34, 75th Cong., 1st 
sess.), as Chief of Engineers deems advisable. 
St. Paul, MN, channel enlargements small boat harbor, and 
roadway. 
Vertical bridge clearance at Minneapolis to 26 feet above 
estimated stage for discharge of 40,000 c.f.s. 
Winona, MN, basin. 
Future modification of lock and dam No. 2 for 
power development 
Provides for cash contribution by local interests in lieu of 
alteration of privately owned bridges and utilities for 
St. Anthony Falls project. 
Lake City, MN, harbor. 
Wabasha, MN, harbor. 
Payment of damages caused by backwater and seepage, 
pools 3 to 11. 
Hastings, MN, harbor. 
Lansing, IA, harbor. 
Fort Madison, IA, harbors 
Payment of damages caused by pool No. 14 at Clinton, IA. 
Davenport, IA, harbor. 
Muscatine, IA, harbor. 
Alma, WI, harbor. 
Hannibal, MO, harbor. 
Prairie du Chien, WI, harbors. 
Committee Doc. 44, 
74th Cong., 1st sess. 
Rivers and Harbors 
Committee Doc. 34, 
75th Cong., 1st sess. 
None 
H. Doc. 103, 76th Cong., 
1st sess. 
H. Doc. 137, 76th Cong., 
1st sess. 
None 
H. Doc. 547, 76th Cong., 
3rd sess. 
S. Doc. 54, 77th Cong., 
1st seas. 
H. Doc. 263, 77th Cong., 
1st sess. 
H. Doc. 432, 77th Cong., 
1st sess. 
H. Doc. 449, 78th Cong., 
2d sess. 
H. Doc. 511, 79th Cong., 
2d sess. 
H. Doc. 514, 79th Cong., 
2d sess. 
H. Doc. 515, 79th Cong., 
2d sess. 
H. Doc. 559, 79th Cong., 
2d sess. 
S. Doc. 192, 79th Cong., 
2d sess. 
H. Doc. 661, 80th Cong., 
2d sess. 
S. Doc. 197, 80th Cong., 
2d sess. 
H. Doc. 642, 80th Cong., 
2d sess. 
H. Doc. 733, 80th Cong., 
2d sess. 
H. Doc. 66., 81st Cong., 
1st seas. 
H. Doc. 67, 81st Cong., 
1st sess. 
H. Doc. 71, 81st Cong., 
1st sess. 
29-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 29-G (Cont'd) AUTHORIZING LEGISLATION I 
Acts Work Authorized Documents 
May 17, 1950 Opposite Hamburg, IL, harbor.' H. Doc. 254, 81st Cong., 
1st sess. 
May 17, 1950 Permits such change in location of Winona, MN, small boat None 
basin authorized by River and Harbor Act of Mar. 2, 1945 (H. 
Doc. 263, 77th Cong., 1st sess.), as Chief of Engineers deems 
advisable. 
Sept. 3, 1954 Construction of Crooked Slough Harbor at Winona, MN, in lieu H. Doc. 347, 83rd Cong., 
of previously authorized commercial harbor. 2d sess. 
Sept. 3, 1954 Payment of damages caused by pool No. 24 at Louisiana, MO. H. Doc. 251, 82nd Cong., 
1st sess. 
July 3, 1958 Permits modification of vertical bridge clearances and H. Doc. 33, 85th Cong., 
authorizes completion of St. Anthony Falls project. 1st sess. 
July 3, 1958 Small boat and commercial harbors at Alton, IL?2 H. Doc. 136, 84th Cong., 
1st sess. 
July 3, 1958 Payment of lump sum amounts for damages to drainage and H. Doc. 135, 84th Cong., 
levee districts caused by operation of navigation pools. 1st sess. 
July 3, 1958 Improvement and maintenance of Beaver Slough at Clinton, IA. H. Doc. 345, 84th Cong., 
2d sess. 
Mar. 3, 1909 Reconstruction of structures as may be necessary to provide None 
adequate facilities for existing navigation. 
July 14, 1960 Construction of Industrial Harbor at Red Wing, MN. H. Doc. 32, 86th Cong., 
1st sess. 
Oct. 23, 1962 Construction of small-boat harbors at Savanna,' Moline, H. Doc. 513, 87th Cong., 
Andalusia, New Boston, Warsaw, Quincy, and Grafton, IL; 2d sess. 
Bellevue,' Clinton, Davenport, and Keokuk, IA; St. Paul 
(Harriet Island), MN; and Bay City, Pepin, and Cassville,' WI. 
Oct. 23, 1962 Payment of damages caused by pool 24 at Clarksville, MO. H. Doc. 552, 87th Cong., 
2d sess. 
Oct. 23, 1962 Remedial works at Sandy Slough, MO. H. Doc. 419, 87th Cong., 
2d sess. 
Nov. 7, 1966 Repair of Stone Arch bridge at Minneapolis, MN. None 
Nov. 7, 1966 Commercial Harbor facilities at Fort Madison, IA? H. Doc. 507, 89th Cong., 
2d sess. 
Oct. 21, 1978 Replacement of Lock and Dam 26 Public Law 95-502 
'Deferred. 
2Inactive. 
29-12

CHICAGO, ILLINOIS, DISTRICT* 
This district comprises Cook, McHenry, Lake, Kane, Porter Counties in Indiana, including a portion of 
DuPage and Will Counties in Illinois, and Lake and LaPorte County along Lake Michigan. 
IMPROVEMENTS 
Navigation Page 
1. Burns Waterway Harbor, IN ............ 30-2 
2. Calumet Harbor and River, IL 
and IN ............................... 30-2 
3. Chicago Harbor, IL ..................... 30-3 
4. Chicago River, IL ....................... 30-3 
5. Indiana Harbor, IN ..................... 30-4 
6. Michigan City Harbor, IN ............... 30-4 
7. Waukegan Harbor, IL .................. 30-5 
8. Reconnaissance and Condition 
Surveys .............................. 30-5 
9. Navigation Work Under 
Special Authorization .................. 30-5 
Alteration of Bridges 
10. Other Authorized Bridge 
Alteration ........................... 30-5 
Beach Erosion Control 
11. Mount Baldy, Indiana Dunes 
National Lakeshore, IN ............... 30-6 
12. 
13. 
14. 
Page 
Indiana Dunes National Lakeshore 
Bank Protection 
Beverly Shores, IN ................... 30-6 
Other Authorized Beach Erosion 
Control Projects ....................... 30-6 
Beach Erosion Control Under 
Special Authorization ................. 30-6 
Flood Control 
15. Chicago River, IL (North Branch) ........ 30-6 
16. Little Calumet River, IL ................ 30-7 
17. Other Authorized Flood Control 
Projects .............................. 30-7 
18. Flood Control Work Under 
Special Authorization ................. 30-7 
General Investigations 
19. Surveys ................................. 30-7 
20. Collection and Study of Basic Data ....... 30-7 
21. Research and Development .............. 30-8 
22. National Emergency Preparedness ....... 30-8 
30-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Navigation 
1. BURNS WATERWAY HARBOR, IN 
Location. Northwestern Indiana, on the southern 
shore of Lake Michigan in Porter County, 28 miles 
south-east of Chicago Harbor. (See NOAA Nautical 
Charts Numbers 14905 and 14926). 
Existing Project. Provides for (a) a north breakwater 
4,646 feet long; (b) an outer west bulkhead 1,176 
feet long; (c) a west bulkhead shore connection 2,300 feet 
long; (d) an approach channel 30 feet deep and 400 feet 
wide; (e) an outer harbor 28 feet deep; (f) an east harbor 
arm 27 feet deep and 620 feet wide; (g) a west harbor 
arm 27 feet deep and 620 feet wide. The project was 
authorized by the River and Harbor Act of 27 October 
1965 (Public Law 89-298; House Document Number 
160, 88th Congress, 1st Session). The authorizing act 
also provided the Secretary of the Army to reimburse 
the State of Indiana for expenditure of funds used to 
construct such portions of the project as approved by the 
Chief of Engineers and constructed under supervision of 
the Chief of Engineers. See table 30-C. 
Local Cooperation. Fully complied with. 
Terminal Facilities. Seven berths and docks are 
available, three on the west harbor arm, one on the 
harbor basin, and three on the east harbor arm. One 
dock on the west harbor arm is used for shipment and 
receipt of steel products. One dock on the east harbor 
arm is used for receipt of iron ore pellets and limestone 
and shipment of steel products. Five facilities are administered 
by the Indiana Port Commission and are 
used for handling general cargo. 
Operations and results during period. Maintenance: 
A project map is being updated at a cost of 
$12,162. A credit for condition surveys was received in 
the amount of $11,377. A credit from USEPA for a water 
quality assurance program was received in the amount 
of $19,999. A credit for stone placement during 1982 was 
received in the amount of $25,756. Supervision and inspection 
of these activities were performed by hired labor 
at a cost of $617. 
Condition at end of fiscal year. The existing project 
is complete. Total costs of existing project to September 
30, 1983 were $17,310,051, of which $13,599,990 
was for new work ($13,584,000 Federal and $15,990 
non-Federal), and $3,710,061 for maintenance. 
2. CALUMET HARBOR AND RIVER, 
IL AND IN 
Location. Northeastern Illinois, on the southwest 
shore of Lake Michigan in Cook County, 15 miles south 
of Chicago Harbor, within corporate limits of the city of 
Chicago, except for breakwaters, an approach channel, 
and an anchorage area which are in Illinois and Indiana. 
(See NOAA Nautical Charts Numbers 14926 and 
14929). 
Previous projects. For details see page 1400 of Annual 
Report for 1962. 
Existing Project. Provides for (a) a stone filled timber 
crib breakwater 6,714 feet long; (b) a stone filled 
double row steel sheet pile detached breakwater 5,007 
feet long; (c) a north pier 2450 feet long; (d) an approach 
channel 29 feet deep and 3,200 feet wide; (e) an outer 
harbor anchorage area 28 feet deep and 3,000 feet wide; 
(f) an entrance channel 27 feet deep and 230 to 290 feet 
wide, (g) a channel in the Calumet River 27 feet deep 
and at least 200 feet wide to the north side of 130th 
street, (h) three turning basins designated as numbers 
1, 3 and 5; (i) a channel extending into Lake Calumet at 
a width of about 1,000 feet. The project was authorized 
by the River and Harbor Acts of 3 March 1899, 13 June 
1902, 30 August 1935, 14 July 1960, 23 October 1962, 
and 27 October 1965. See table 30-C. 
Local cooperation. Fully complied with. 
Terminal Facilities. Thirty six docks, wharves, and 
terminals are available. The Chicago Regional Port District 
owns four wharves, two grain elevators, one dock, 
and one terminal. The United States Government owns 
one stone dock. The most important cargoes handled are 
iron ores and concentrates, coal, and lignite. 
Operations and results during period. Maintenance: 
A project map is being updated at a cost of 
$9,284. A credit for condition surveys was received in 
the amount of $15,166. Supervision and inspection of 
these activities were performed by hired labor at a cost 
of $1,222. 
Under the dike disposal program, engineering services 
were continued at a cost of $148,602. Construction 
of the Chicago Area Confined Disposal Facility was continued 
at a cost of $3,073,290. Supervision and inspection 
of these activities were performed at a cost of 
$123,390. 
Condition at end of fiscal year. The existing project 
is 79% complete. Work remaining to be accomplished 
consists of widening and straightening the Calumet 
River in the vicinity of 106th Street, and the inactive 
30-2

CHICAGO, IL, DISTRICT 
portion which consists of closing the gap between the 
breakwaters, and dredging minor shoals in the outer 
harbor. Total costs of existing project to September 30, 
1983 were $40,869,154, of which $21,722,594 was for 
new work ($18,685,991 regular funds and $3,036,603 
public works funds), $17,620,892 regular funds for 
maintenance, $836,667 non-Federal funds for maintenance, 
and $689,001 regular funds for rehabilitation. 
3. CHICAGO HARBOR, IL 
Location. Northeastern Illinois, on the southwest 
shore of Lake Michigan in Cook County, within the 
corporate limits of the City of Chicago. (See NOAA Nautical 
Charts Numbers 14926, 14927, and 14928). 
Previous projects. See page 1396 of Annual Report 
for 1962. 
Existing Project. Provides for (a) a stone filled timber 
crib shore arm extension breakwater 2,250 feet long; 
(b) a stone filled timber crib exterior breakwater 5,421 
feet long; (c) a rubble-mound and stone filled concrete 
caisson southerly extension to the exterior breakwater 
4,944 feet long, exclusive of 582 foot entrance gap inclosing 
an outer basin of about 970 acres; (d) a stone filled 
timber crib north pier 960 feet long; (e) a stone filled 
timber crib north inner breakwater 4,034 feet long with 
a 304 foot shore return, and a 754 foot gap; (f) a stone 
filled timber crib south inner breakwater 2,544 feet long 
inclosing an inner basin of approximately 224 acres; 
(g) a lake approach channel 29 feet deep and 800 feet 
wide; (h) a channel and maneuver area inside the exterior 
breakwater and exterior breakwater southerly extension 
28 feet deep with a maximum width of 1,300 
feet; (i) an inner basin 21 feet deep; (j) an entrance 
channel 21 feet deep. The project was authorized by the 
River and Harbor Acts of 11 July 1870, 14 June 1880, 3 
March 1899, 25 July 1912, 2 March 1919 and 23 October 
1962. See table 30-C. 
The Chicago Harbor Lock was constructed in 1938 by 
the Metropolitan Sanitary District of Greater Chicago. 
The deep draft lock is 600 feet long, 80 feet wide, and 23 
feet deep and uses a steel cellular design. Operation and 
maintenance responsibilities in the interests of navigation 
were transferred to the Federal Government by 
Public Law 98-63. 
Local Cooperation. Fully complied with. 
Terminal facilities. There are three docks, two for 
passenger excursion boats and one for cargo. The most 
important cargoes handled are sugar and non-metallic 
minerals. 
Operations and results during period. Maintenance: 
A project map is being updated at a cost of 
$10,901. At the north exterior breakwater, hazardous 
piles were removed by hired labor at a cost of $7,525. A 
credit for condition surveys was received in the amount 
of $27,454. A credit for stone placement in 1982 was 
received in the amount of $39,723. Engineering work for 
these activities were performed by hired labor at a cost 
of $208. Supervision and inspection of these activities 
were performed by hired labor at a cost of $785. 
Under the dike disposal program, engineering services 
were continued at a cost of $67,950. Construction 
of the Chicago Area Confined Disposal Facility at Calumet 
Harbor and River was continued at a cost of 
$1,027,263. Supervision and inspection of these activities 
were performed at a cost of $32,669. 
Condition at end of fiscal year. The existing project 
is complete. Total costs of existing project to September 
30, 1983 were $12,266,361, of which $4,342,822 
was for new work, $6,596,939 for maintenance and 
$1,326,600 for rehabilitation. 
4. CHICAGO RIVER, IL 
Location. Northeastern Illinois, in Cook County 
within the corporate limits of the city of Chicago. (See 
NOAA Nautical Chart Numbers 14926, 14927 and 
14928). 
Previous projects. See page 1394 of Annual Report 
for 1962. 
Existing Project. Provides for (a) a channel in the 
main branch of the Chicago River 21 feet deep from 
Rush Street to Wolf Point; (b) a channel in the north 
branch of the Chicago River 21 feet deep from Wolf 
Point to North Avenue; (c) a channel in the North 
Branch Canal 21 feet deep, (d) a turning basin 21 feet 
deep. All dredging to within 20 feet of existing docks. 
The project was authorized by the River and Harbor 
Acts of 3 March 1899, 13 June 1902 and 2 March 1907. 
See table 30-C. 
Local Cooperation. Fully complied with. 
Terminal Facilities. Six docks are available. The 
most important cargoes handled are sand, gravel and 
crushed rock. 
Operations and results during period. Maintenance: 
A project map is being updated at a cost of 
$9,786. Under the Lake Michigan Water Diversion 
Monitoring Program, engineering work was performed 
at a cost of $310,201. A credit for condition surveys was 
received in the amount of $7,734. Supervision and in- 
30-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
spection for these activities were performed by hired 
labor at a cost of $6,512. 
Under the dike disposal program, engineering services 
were continued at a cost of $76,026. Construction 
of the Chicago Area Confined Disposal Facility at Calumet 
Harbor and River was continued at a cost of 
$1,027,263. A sediment analysis of the North Branch of 
the Chicago River was initiated at a cost of $30,153. 
Supervision and inspection of these activities were performed 
at a cost of $33,864. 
Condition at end of fiscal year. The existing project 
is complete. Total costs of existing project to September 
30, 1983 were $6,536,405, of which $544,679 was for 
new work and $5,991,726 for maintenance. 
5. INDIANA HARBOR, IN 
Location. Northwestern Indiana, on the southwest 
shore of Lake Michigan in Lake County, 19 miles southeast 
of Chicago Harbor. (See NOAA Nautical Charts 
Numbers 14926 and 14929). 
Previous projects. For details see page 1943 of Annual 
Report for 1915, and page 1520 of Annual Report 
for 1938. 
Existing Project. Provides for (a) northerly rubblemound 
breakwater 1,120 feet long; (b) an easterly con.- 
crete capped concrete caisson breakwater 201 feet long 
with a rubble mound extension 2,324 feet long; (c) a lake 
approach channel 29 feet deep and 800 feet wide; (d) an 
anchorage and maneuver basin 28 feet deep; (e) a canal 
entrance channel 27 feet deep and 280 feet wide; (f) a 
main canal 22 feet deep; (g) a turning basin 22 feet deep; 
(h) the Forks Turning Basin 22 feet deep; (i) the Lake 
George Branch 22 feet deep; (j) the Calumet River 
Branch 22 feet deep. The project was authorized by the 
River and Harbor Acts of 4 March 1913, 2 March 1919, 
20 March 1922, 3 July 1930, 30 August 1935,26 August 
1937, and 14 July 1960. See table 30-C. 
Local Cooperation. Fully complied with. 
Terminal Facilities. Fifteen docks and wharves are 
available. Six docks for handling iron ore and limestone. 
Six docks for handling petroleum products. Three docks 
for handling gypsum, scrap metal and steel, and bulk 
products. 
Operations and results during period. Maintenance: 
A project map is being updated at a cost of 
$8,405. 
Under the dike disposal program, site selection studies 
and engineering and design were continued at a cost 
of $296,094. Supervision and inspection of this activity 
was performed by hired labor at a cost of $131. 
Condition at end of fiscal year. The existing project 
is complete. Total costs of existing project to September 
30, 1983 were $10,331,174, of which $8,700,633 was 
Regular Funds, $1,618,041 was Public Works Funds, 
and $12,500 was Contributed Funds. Of the total cost, 
$4,848,980 was for new work and $5,482,194 was for 
maintenance. 
6. MICHIGAN CITY HARBOR, IN 
Location. Northwestern Indiana, on the southeast 
shore of Lake Michigan in La Porte County, 38 miles 
southeast of Chicago Harbor. (See NOAA Nautical 
Charts Numbers 14905 and 14926). 
Previous projects. See page 1407 of Annual Report 
for 1962. 
Existing Project. Provides for (a) a stone filled timber 
crib detached breakwater 1,304 feet long; (b) a pile 
and steel sheeting west pier 835 feet long; (c) a stone 
filled timber crib, pile and steel sheeting east pier 2,276 
feet long; (d) a stone filled timber crib east breakwater 
1,000 feet long; (e) an entrance channel 18 feet deep and 
425 feet wide; (f) a turning basin 18 feet deep; (g) a 
channel in Trail Creek 18 feet deep; (h) a turning basin 
18 feet deep; (i) an outer basin 12 feet deep; (j) an outer 
basin 8 feet deep; (k) a channel in Trail Creek 6 feet deep 
and 50 feet wide. The project was authorized by the 
River and Harbor Acts of 3 March 1889, 3 March 1905, 
21 January 1927, 30 August 1935, and Section 107 of 
14 July 1960 approved on 30 September 1966. See table 
30-C. 
Local Cooperation. Fully complied with. 
Terminal Facilities. There are several marinas in 
the lower mile of Trail Creek. The commodity handled 
at this harbor is fresh fish. 
Operations and results during period. Maintenance: 
A credit for condition surveys was received in the 
amount of $2,179. A credit for dredging completed in 
1979 was received in the amount of $4,175. A credit for 
stone placement in 1982 was received in the amount of 
$1,219. 
Condition at end of fiscal year. The existing project 
is complete. Total costs of existing project to September 
30, 1983 were $7,526,239, of which $1,287,057 
was for new work ($1,256,257 Federal and $30,800 
30-4

CHICAGO, IL, DISTRICT 
non-Federal funds), $4,620,512 for maintenance and 
$1,618,670 for rehabilitation. 
7. WAUKEGAN HARBOR, IL 
Location. Northeastern Illinois, on the southwest 
shore of Lake Michigan in Lake County, 38 miles north 
of Chicago Harbor. (See NOAA Nautical Charts Numbers 
14904 and 14905). 
Previous projects. See page 1392 of Annual Report 
for 1962. 
Existing Project. Provides for (a) a northerly stone 
filled timber crib breakwater 588 feet long; (b) a stone 
filled reinforced concrete caisson shore connection 270 
feet long; (c) a stone filled double row steel sheeting 
shore connection 640 feet long; (d) a single row steel 
sheeting shore connection 398 feet long; (e) a stone filled 
timber crib north pier 998 feet long, (f) a single row steel 
sheet piling north pier 444 feet long; (g) a steel piling 
revetment 632 feet long; (h) a stone filled timber crib 
south pier 1,399 feet long; (i) a stone filled double row 
pile and sheeting south pier 1,712 feet long; (j) an entrance 
channel 22 feet deep and 390 feet wide; (k) a 
channel between the piers 18 feet deep and 200 feet 
wide; (1) an inner basin 18 feet deep; (m) an anchorage 
area in the southwest corner of the inner basin 8 feet 
deep. The project was authorized by the River and Harbor 
Acts of 13 June 1902, 3 July 1930, and 2 March 
1945. See table 30-C. 
Local Cooperation. Fully complied with. 
Terminal Facilities. Four docks are available. The 
commodities handled at this harbor are gypsum and 
building cement. 
Operations and results during period. Maintenance: 
A project map is being updated at a cost of 
$8,752. Engineering and design was performed for the 
north breakwater at a cost of $9,431. Engineering and 
design was performed for the north pier at a cost of 
$19,726. A credit for condition surveys was received in 
the amount of $8,768. A credit for a structural investigation 
was received in the amount of $806. Inspection and 
reports for these activities were performed by hired labor 
at a cost of $1,223. 
Under the dike disposal program, site selection studies 
and engineering and design were continued at a cost 
of $152,747. Supervision and inspection of t.is activity 
was performed by hired labor at a cost of $262. 
Condition at end of fiscal year. The existing project 
is complete. Total costs of existing project to September 
30, 1983 were $4,795,824, of which $604,793 was for 
new work and $4,191,031 for maintenance. 
8. RECONNAISSANCE AND 
CONDITION SURVEYS 
A project map is being updated for Michigan City 
Harbor, Indiana at a cost of $10,923. Condition surveys 
were performed by hired labor at a cost of $77,814 (see 
Table 30-G for projects and cost). A project survey was 
performed by real estate at a cost of $2,500. Supervision 
and inspection of these activities were performed by 
hired labor at a cost of $136,213. 
9. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Small Navigation Projects Not Specifically Authorized 
by Congress (Sec. 107 of the River and Harbor Act of 
1960, as amended, Public Law 645, 86th Congress). 
Project and Fiscal Year Costs 
Location to September 30, 1983 
SBH Burns Wtwy, IN $90,634 
Michigan City Harbor, IN SBH 6,854 
Investigation and Removal of Sunken Vessels and 
Other Obstructions to Navigation Under Authority of 
Sections 19 and 20 of the River and Harbor Act of 1899, 
the following work was undertaken: 
A contract for removal of hazardous piles at Burns 
Ditch, IN was completed in 1982 at a cost of $51,733. 
The preliminary survey cost was $2,030. Engineering 
and design was performed by hired labor at a cost of 
$23,204. Supervision and inspection of these activities 
were performed by hired labor at a cost of $7,512. 
A contract was awarded in 1983 for removal of a 
sunken vessel, ST. S. AMERICAN, which sank in Turning 
Basin No. 5 of the Calumet Harbor and River project. 
A preliminary survey was completed at a cost of 
$2,177. Engineering and design were performed by 
hired labor at a cost of $31,009. Supervision and inspection 
of these activities were performed by hired labor at 
a cost of $8,890. 
Alteration of Bridges 
10. OTHER AUTHORIZED BRIDGE 
ALTERATION 
See table 30-D. 
30-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Beach Erosion Control 
11. MT. BALDY INDIANA DUNES 
NATIONAL LAKESHORE, IN 
Location. On the south end of Lake Michigan shoreline, 
approximately two miles west of Michigan City, 
Indiana. 
Existing Project. The Corps of Engineers was funded 
under the Energy and Water Development Appropriation 
Act 1981, dated 1 October 1980, Public Law 96-367, 
to provide beach nourishment along approximately 
3,000 feet of shore at the toe of Mt. Baldy in the Indiana 
Dunes National Lakeshore. 
Local Cooperation. The work is within the National 
Park Service property and the National Park Service, 
acting through its Superintendent of the Indiana Dunes 
National Lakeshore, issued to the Corps of Engineers on 
28 April 1981 a right-of-way permit to do the work. 
Access to the project was made possible through the 
cooperation of the Northern Indiana Public Service 
Company. On 28 August 1973, the State of Indiana 
granted a 10-year license to the National Park Service 
for the installation and maintenance of beach nourishment 
material and stone revetment in this area, which 
was still valid for this project. 
Operations and results during period. New work: 
Administrative work in closing the contract was performed 
at a cost of $87.23. 
Condition at end of fiscal year. Project construction 
was completed in FY82. Total costs of existing project 
to September 30, 1983 were $1,500,000. 
12. INDIANA DUNES NATIONAL 
LAKESHORE BANK PROTECTION, 
BEVERLY SHORES, IN 
Location. Northwestern Indiana, on the southeast 
shore of Lake Michigan in Porter County, approximately 
35 miles southeast of Chicago Harbor. (See 
NOAA Nautical Charts Numbers 14905 and 14926). 
Existing Project. Provides for 13,000 feet of stone 
revetment and periodic repair of rip rap and placement 
of sand to maintain the full length of beach front at 
Beverly Shores, Indiana. The current project was authorized 
by Public Law 97-88 and Public Law 98-63. 
Local Cooperation. Fully complied with. 
Operations and results during period. New Work: 
A contract for repairs and maintenance of the stone 
revetment was completed at a cost of $542,519. Approximately 
12,700 tons of stone was placed. Engineering 
and design were performed at a cost of $9,880. Supervision 
and inspection of these activities were performed by 
hired labor at a cost of $19,087. 
Condition at end of fiscal year. Total costs of existing 
project to 30 September 1983 were $660,000 for new 
work. 
13. OTHER AUTHORIZED BEACH 
EROSION CONTROL PROJECTS 
See table 30-E. 
14. BEACH EROSION CONTROL 
UNDER SPECIAL 
AUTHORIZATION 
Beach erosion control activities pursuant to section 103 
of the River and Harbor Act of 1962, as amended. 
Project and Fiscal Year Costs 
Location to September 30, 1983 
Greenwood Beach, Evanston, IL $75,250 
Langdon Park, Wilmette, IL 55,485 
Flood Control 
15. CHICAGO RIVER, IL 
(NORTH BRANCH) 
Location. Northeastern Illinois, in Cook and Lake 
Counties. 
Existing Project. Provides for clearing the channel 
of the North Branch of the Chicago River, Illinois, of 
fallen trees, roots, and other debris and objects which 
contribute to the flooding, unsightliness, and pollution 
of the river. The project extends from Wolf Point in 
Chicago, Illinois, to its source just south of Rockland 
Road east of Libertyville, Illinois. The project was authorized 
by the River and Harbor Act of 31 December 
1970 (Section 116) and amended by the River and Harbor 
Act of 7 March 1974. 
Local Cooperation. The 1970 Act provided that local 
interests furnish without cost to the United States all 
lands, easements, rights-of-way, and disposal areas necessary 
for construction of the project; hold and save the 
United States free from damages due to construction; 
maintain and operate all works after completion without 
cost to the United States; and agree to bear all cost 
in excess of $200,000 for completing construction. As- 
30-6

CHICAGO, IL, DISTRICT 
surance of local cooperation for this act was approved on 
31 July 1972. The 1974 Act provided that the United 
States will maintain the channel free of trees, roots, 
debris and objects at a cost not to exceed $150,000 per 
year with non-Federal interests paying 25 per centum of 
the cost of maintenance. 
Operations and results during period. Maintenance: 
Federal funds in the amount of $750 were expended 
for the 1981 debris removal contract. Federal 
funds in the amount of $119,814 were expended for the 
1982 debris removal contract for snagging and clearing 
the north branch between Devon and Touhy Avenues in 
Chicago and Niles, the middle fork of the north branch 
from 1,000 feet downstream of Shermer Avenue to the 
Interstate 94 bridge in Northbrook, and the Skokie 
River branch from its junction with the middle fork of 
the North Branch to the Willow Road bridge in Northfield. 
Engineering and design work was performed in 
the amount of $6,064. Supervision and inspection for 
these activities were performed by hired labor at a cost 
of $7,279. The local sponsor, the Metropolitan Sanitary 
District of Greater Chicago, expended $63,367 for these 
activities. 
Condition at end of fiscal year. Total costs 
of existing project to 30 September 1983 were 
$1,361,143, of which $231,884 was for new work 
($191,884 regular funds and $40,000 contributed funds) 
and $1,129,259 for maintenance ($847,099 Federal 
funds and $282,160 contributed funds). 
16. LITTLE CALUMET RIVER, IL 
Location. Rises in western LaPorte County, Indiana, 
near Michigan City and flows generally westerly 
through Porter and Lake County, Indiana, into Cook 
County, Illinois, to its junction with the Calumet-Sag 
Channel in Calumet Park, Illinois. Approximately 12 
miles of the Little Calumet River lies within the State of 
Illinois. 
Existing project. Provides for clearing the channel of 
the Little Calumet River, Illinois, from its confluence 
with the Calumet-Sag Channel eastward to the Indiana 
State Line, of fallen trees, roots, silt, and other debris 
and objects which contribute to flooding, unsightliness 
and pollution of the river. Project was authorized by 
Water Resources Development Act of 1974, Section 66, 
approved 7 March 1974. 
Local cooperation. Fully complied with. 
Operations and results during period. New work: 
Planning and engineering studies were performed on 
the Phase II silt removal portion of the project with costs 
of $37,547. 
Condition at end of fiscal year. Total cost of existing 
project to September 30, 1983 was $582,965, all new 
work. 
17. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
See table 30-F. 
18. FLOOD CONTROL UNDER 
SPECIAL AUTHORIZATION 
Emergency flood control activities-repair, flood fighting 
and rescue work (Public Law 99, 84th Cong. and 
antecedent legislation). 
Project and Location Fiscal Year Costs 
Disaster Preparedness 
Emergency Operations 
to September 30, 1983 
$110,464 
54,303 
Emergency bank protection (Sec. 14 of the 1946 Flood 
Control Act Public Law 526, 79th Cong). 
Project and Location Fiscal Year Costs 
to September 30, 1983 
12th St. Beach Meigs Fld., Chgo., IL $ 4,900 
Illinois Beach State Park, Lake Co., IL 29,912 
Lincoln Park Gun Club, Chgo., IL 30,477 
Rosewood Beach, Highland Park, IL 39,650 
General Investigations 
19. SURVEYS 
Fiscal year costs were $1,897,579 itemized as follows: 
Navigation Studies $ 1,081 
Flood Damage Prevention Studies 471,439 
Shoreline Protection Studies 27,954 
Special Studies 1,238- 
Special Investigation 24,000 
Coordination Studies 3,015 
Supplemental Pre-authorization 1,371,328 
20. COLLECTION AND STUDY OF 
BASIC DATA 
Fiscal year costs of $90,301 were for: 
National Dam Safety Program 
Flood Plain Management Services 
$ 231 
90,070 
30-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
21. RESEARCH AND DEVELOPMENT 
Cost for hydrologic studies during the fiscal year was 
$5,207. 
22. NATIONAL EMERGENCY 
PREPAREDNESS 
Fiscal year costs of $138,889 were for: 
Training and Exercises 
Management 
Mobilization Planning 
30-8 
$ 19,500 
100,850 
18,499

TABLE 30-A 
CHICAGO, IL, DISTRICT 
COST AND FINANCIAL STATEMENT 
See 
Section Total to 
in Text Project Funding FY 80 FY 81 FY 82 FY 83 September 30, 1988 
1. Burns Waterway 
Harbor, IN 
(Federal Funds) 
(Contributed 
Funds) 
2. Calumet Harbor 
and River, IL 
and IN 
(Federal Funds) 
(Contributed 
Funds) 
3. Chicago Harbor 
IL 
(Federal Funds) 
4. Chicago River, 
IL 
5. Indiana Harbor, 
IN 
6. Michigan City 
Harbor, IN 
(Contributed 
Funds) 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
Rehab.: 
Approp. 
Cost 
Maint.: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
Rehab: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
Rehab.: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
1,010,000 455,000 325,000 -64,000 
1,001,531 463,466 300,624 -44,353 
540,000 320,000 1,519,000 4,431,000 
528,586 315,735 683,175 3,340,642 
258,000 260,000 793,000 1,499,000 
256,707 261,291 563,031 1,080,124 
145,000 290,000 545,000 1,994,000 
144,998 289,920 339,980 1,486,071 
257,000 30,000 
251,157 34,361 
118,000 83,000 
120,994 76,277 
80,000 510,000 
81,383 304,630 
15,000 -13,000 
17,299 -7,573 
13,584,000 
13,584,000 
3,714,793 
3,710,061 
15,900 
15,900 
22,578,5671 
22,578,5671 
19,562,7742 
17,620,9122 
689,0013 
689,0013 
836,667 
836,667 
4,788,8274 
4,788,8274 
7,245,786 
6,596,939 
1,326,600 
1,326,600 
1,500,5655 
1,500,5655 
6,704,7576 
5,991,7266 
4,897,1487 9 
4,897,1487 9 
5,687,6658 
5,482,1948 
1,543,64610 
1,543,64610 
4,620,512 
4,620,512 
1,618,670 
1,618,670 
30,800 
30,800 
30-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 30-A (Cont'd) COST AND FINANCIAL STATEMENT 
See 
Section Total to 
in Text Project Funding FY 80 FY 81 FY 82 FY 83 September 30, 1983 
7. Waukegan Harbor, New Work: 
IL Approp. 823,02611 
Cost 823,02611 
Maint.: 
Approp. 27,000 200,000 765,000 90,000 4,314,30912 
Cost 25,326 144,131 606,698 182,567 4,191,03112 
11. Mount Baldy, IN New Work: 
Dunes National Approp. - 1,500,000 - - 1,500,000 
Lakeshore, IN Cost - 227,305 1,272,608 87 1,500,000 
12. Indiana Dunes New Work: 
National Lakeshore Approp. 660,000 660,000 
Beverly Shores, IN Cost 88,514 571,486 660,000 
15. Chicago River, IL New Work: 
North Branch Approp. 191,884 
(Federal Funds) Cost 191,884 
Maint.: 
Approp. 150,000 150,000 150,000 150,000 997,000 
Cost 13,995 195,188 107,010 133,907 847,099 
(Contributed New Work: 
Funds) Contrib. 40,000 
Cost 40,000 
Maint.: 
Approp. 60,000 60,000 60,000 0 300,000 
Cost 9,721 50,842 47,344 63,367 282,160 
16. Little Calumet New Work: 
River, IL Approp. 50,000 100,000 125,000 - 583,000 
Cost 20,822 112,909 103,687 37,547 582,965 
1. Includes $855,973 for previous projects. 
2. Excludes contributed funds in settlement pursuant to 
decree [No. 54-C-1608] regarding removal of flue-dust and 
includes $45,230 for previous projects. 
3. In settlement pursuant to decree [No. 54-C-1608] 
regarding removal of flue-dust. 
4. Includes $446,005 for previous projects. 
5. Includes $955,886 for previous projects. 
6. Includes $109,463 for previous projects. 
7. Includes $60,668 for previous projects. 
8. Includes $2,509 for previous projects. 
9. Excludes $12,500 contributed funds. 
10. Includes $287,389 for previous projects. 
11. Includes $218,233 on previous projects. 
12. Includes $15,711 on previous projects. 
30-10

CHIGAGO, IL, DISTRICT 
TABLE 30-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
CALUMET HARBOR AND RIVER, IL AND IN 
(See Section 2 of Text) 
Mar. 3, 1899 
June 13, 1902 
Mar. 3, 1905 
June 25, 1910 
Sept. 22, 1922 
Aug. 30, 19351 2 
Aug. 30, 19351 2 
Mar. 2, 19453 
July 14, 1960 
Oct. 23, 1962 
Oct. 27, 1965 
July 11, 1870 
June 14, 1880 
Mar. 3, 1899 
July 25, 1912 
Mar. 2, 1919 
Mar. 3, 1931 
Mar. 2, 1945 
Oct. 23, 1962 
May 18, 1983 
Outer harbor protected by breakwaters. 
Five turning basins. 
Provided for shape and dimensions of turning basins. 
Consolidated the 2 projects for Calumet Harbor and Calumet 
River. 
Detached breakwater, dredging outer harbor to existing 
project depth and dimensions; deepen river-entrance 
channel and river to existing project depths; widen and 
straighten river channel; 5 turning basins to same depth 
as adjacent channel. 
Dredging areas A and B in south end of Lake Calumet and 
an entrance channel 300 feet wide to 21 feet deep. 
An approach channel to harbor 3,200 feet wide and 28 feet 
deep through shoals outside breakwater and closing 
existing gap between breakwaters. 
Depth of 29 feet in lake approach to 28 feet in outer harbor; 
and 27 feet in river entrance up to E.J.&E. Ry. Bridge. 
Deepen, widen, and straighten channel in Calumet River 
from E.J.&E. Ry. Bridge to and including turning basin 5, 
to a depth of 27 feet in earth and 28 feet in rock; deepen 
turning basins 1, 3 and 5 to 27 feet; enlarge turning 
basins 3 and 5; a channel into Lake Calumet to 27 feet 
deep for 3,000 feet and a width of 1,000 feet; and 
eliminate turning basins 2 and 4 from project. 
Modification of Act of Oct. 23, 1962. Protection for Elgin, 
Joliet and Eastern Railway Bridge over the Calumet 
River, to permit dredging to full width of the south draw 
to depth of 27 feet, and temporary protection for the center 
pier and south abutment of the New York, Chicago, and 
St. Louis Railroad Bridge [Nickel Plate] to permit 
dredging of full width of south bridge draw to depth of 27 
feet prior to its replacement. 
CHICAGO HARBOR, IL 
(See Section 3 of Text) 
Inner breakwaters and inner basin. 
Exterior Breakwater. 
Present project depth in basin, and entrance to Chicago 
River. 
Shore-arm and southerly extension of exterior breakwater. 
Modification of area to be dredged in inner basin. 
Shore-arm extension of exterior breakwater transferred to 
Lincoln Park Commissioners. 
Resumption of jurisdiction over shore-arm extension 
breakwater and over certain navigable waters in Lake 
Michigan which lie in northwestern part of outer harbor. 
Deepen a lake approach channel to 29 by 800 feet wide for 
6,600 feet; and deepen a channel and maneuver area 
inside harbor entrance to 28 by 1,300 feet wide. 
Provides for lock operations and maintenance 
responsibilities in the interests of navigation. 
Annual Report, 1896 pp. 2584 et 
seq., and H. Doc. 277, H. 54th 
Cong., 1st sess. 
H. Doc. 172, 58th Cong., 2d seas. 
H. Doc. 349, 60th Cong., 1st 
sess. 
H. Doc. 494, 72d Cong., 2d sess. 
H. Doc. 180, 73d Cong., 2d sess. 
H. Doc. 233, 76th Cong., 1st 
sess. 
H. Doc. 149, 86th Cong., 1st 
Sess.4 
H. Doc. 581, 87th Cong., 2d 
sess. 5 
H. Report No. 973, 89th Cong., 
1st sess. 
H. Ex. Doc. 114, 41st Cong., 2d 
sess., and Annual Report 
1879, pp. 1562-1567 
Annual Report 1870, pp. 1562- 
1567 
Annual Report 1897, pp. 
2790-2791 
H. Doc. 710, Cong., 2d sess. 
H. Doc. 1303, 64th Cong., 1st 
sess. 
Public Law 797, 71st Cong. 
Public Law 14, 79th Cong. 
H. Doc. 485, 87th Cong. 2d 
sess. 4 
Public Law 98-63 
30-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1988 
TABLE 30-B (Cont'd) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Mar. 3, 1899 
June 13, 1902 
Mar. 2, 1907 
Mar. 2, 1919 
July 24, 194613 
June 25, 1910 
Mar. 4, 1913 
Mar. 2, 1919 
Mar. 20, 1922 
Mar. 3, 1925 
Mar. 2, 1929 
July 3, 193010 
June 30, 1932 
Aug. 30, 193511 
Aug. 26, 1937 
July 14, 1960 
Oct. 27, 196512 
Mar. 3, 1889 
CHICAGO RIVER, IL (See Section 4 of Text) 
For project depth of 21 feet in lieu of that fixed by act of 
June 3, 1896. 
Turning basins. 
Interpreted by Chief of Engineers, April 11, 1908 as 
adopting new work of the then existing project for 21-foot 
depth. 
Eliminated all work except maintenance of main river. 
Dredging channel 9 feet deep to within 30 feet of existing 
bulkheads and river banks from North Ave. to Belmont 
Ave., thence 9 feet deep and 50 feet wide to Addison St. 
INDIANA HARBOR, IN (See Section 5 of Text) 
Maintenance of outer harbor. Maintenance of inner harbor 
channel when deeded free of cost to and accepted by the 
United States. 
Breakwaters. 
Lighthouse crib, present length and alignment easterly and 
northerly breakwaters. 
Reduce length of channel to be maintained in extension to 
Lake George. 
Authorized Secretary of War to modify project so far as 
relates to length and alignment of breakwaters and to sell 
Youngstown Sheet and Tube Co. about 1,180 linear feet of 
shoreward end of existing north breakwater. 
Accept 2.3 acres of land for construction of the Forks 
Turning Basin. 
Existing project channel width and depth in Lake George 
Branch and turning basin at the Forks. 
Authorized Secretary of War to sell Inland Steel Co. about 
1,903 linear feet of southerly end of existing east 
breakwater. 
Extended easterly breakwater, dredge entrance channel and 
outer harbor, deepen channel between bulkhead fills, 
widen main stem of canal and portion of Calumet River 
Branch to 141st St. 
Modified conditions of local cooperation required before 
enlargement of Indiana Harbor Canal is undertaken by 
United States. 
Increase authorized depths to 29 feet in outer harbor 
entrance channel; 28 feet in outer harbor, and 27 feet in 
canal entrance channel to first E.J.&E. Ry. Bridge. 
Deepen main canal from landward end of canal entrance 
channel to a point lakeward of Dickey Place Bridge over a 
modified channel width of 190 feet, except through bridge 
opemnings. 
MICHIGAN CITY HARBOR, IN (See Section 6 of Text) 
East breakwater and old east pier inclosing the outer basin. 
Extension of east pier. 
Extend east pier and construct detached breakwater. 
Specified in act. 
Specified in act. 
H. Doc. 95, 56th Cong., 1st sess. 
[Annual Report, 1900, p. 3863 
and Annual Report, 1909, 
p. 709]. 
H. Doc. 1294, 64th Cong., 1st 
ses. 
H. Doc. 767, 78th Cong., 2d 
ses. 6 
7 
H. Doc. 1113, 60th Cong., 2d 
sess. 
H. Doc. 690, 62d Cong. 2d sess. 
Rivers and Harbors Committee 
Doc. 6, 65th Cong., 2d sess. 
Public Law 176, 67th Cong. 
Rivers and Harbors Committee 
Doc. 21, 71st Cong., 2d sess. 
Public Law 219, 72d Cong. 
Rivers and Harbors Committee 
Doc. 29, 72d Cong., 1st sess. 
Rivers and Harbors Committee 
Doc. 13, 75th Cong., 1st sess. 
H. Doc. 195, 86th Cong., 1st 
sees. 
H. Doc. 227, 89th Cong., 1st 
ses. 8 
Recommendation of a Board of 
Engineers, Annual Report, 
1870, p. 123. 
Reports of Boards of Engineers, 
Annual Report, 1851, 
pp. 2187-2189; Annual Report 
1882, pp. 2264-2266. 
Annual Report, 1897, pp. 2903- 
2904. 
30-12

CHICAGO, IL, DISTRICT 
TABLE 30-B (Cont'd) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Mar. 3, 1905 
Jan. 21, 1927 
Aug. 30, 1935 
Sept. 30, 1966 
Sec. 107 
July 14, 1960 
June 14, 1880 
Aug. 3, 1882 
June 13, 1902 
July 3, 1930 
Mar. 2, 1945 
Dec. 17, 1970 
Sec. 201 
Oct. 27, 196513 
Oct. 1, 1980 
Dec. 4, 1981 
May 18, 1983 
Lower turning basin. 
Rebuild west pier as at present located. 
Present project dimensions of entrance channel. 
Existing project depth in channel, and in lower and middle 
turning basins, eliminated improvement of Trail Creek 
above middle turning basin and uncompleted portion of 
detached breakwater, abandonment of old east breakwater 
and old east pier inclosing outer basin. 
Restore and repair westerly 1,000 feet of east breakwater, 
dredging outer basin, and enlarging entrance to basin 
through east pier. 
Dredge river channel 50 feet wide and 6 feet deep from 
upper turning basin to E Street bridge. 
WAUKEGAN HARBOR, IL (See Section 7 of Text) 
Parallel piers and basins.9 
Modified location of harbor entrance. 
Detached breakwater, extend piers, increase width of harbor 
at inner end of north pier, and dredge channel and basin 
to depth of 20 feet. 
Extension of breakwater to shore, dredging near outer end of 
north pier, and enlarging inner basin. 
Dredge an entrance channel to existing project dimensions 
from outer end of north pier to project depth in lake, and 
dredge an anchorage area in southwest corner of inner 
basin to existing project depth. Abandonment of dredging 
triangular area in southwest corner of inner basin to 18 
feet deep. 
Provides for deepening the existing entrance channel in the 
outer harbor to 25 feet and extending it to that depth in 
Lake Michigan, at widths varying from 380 feet to 500 
feet; deepening the channel between piers to a depth of 23 
feet at a width of 180 feet, and deepening the inner basin 
to 23 feet and extending its limits approximately 275 feet 
northward. 
MOUNT BALDY, INDIANA DUNES NATIONAL 
LAKESHORE, IN (See Section 11 of Text) 
Provides for emergency beach nourishment. 
INDIANA DUNES NATIONAL LAKESHORE, IN, 
BEVERLY SHORES, IN 
Provides for emergency shore protection repairs to stone 
revetment initially constructed in 1973. 
Provides for operations and maintenance of the shore 
protection measures. 
Joint resolution of Congress 
approved May 13, 1908 
Public Law 23. 
H. Doc. 279, 69th Cong., 1st 
sess. 
Rivers and Harbors Committee 
Doc. 34, 74th Cong., 1st seas. 
Detailed Project Report June 
1965.8 
Annual Report, 1880, p. 1942. 
Annual Report, 1882, pp. 277, 
2162 
H. Doc. 343, 56th Cong., 1st 
sess. 
Rivers and Harbors Committee 
Dec. 27, 71st Cong., 2d sess. 
H. Doc. 116, 77th Cong., 1st 
seas. 
H. Dc. 368, 90th Cong., 2d 
sess.8 
Public Law 96-367. 
Public Law 97-88. 
Public Law 98-63. 
1. Included in Public Works Administration Program 
Sept. 6, 1943, and Dec. 16, 1933. 
2. Uncompleted portion was deauthorized in 1977 
[dredging in front of U.S. Steel Corp.] 
3. Uncompleted portion was deauthorized in 1977 
[breakwater closure. 
4. Contains latest map of harbor. Uncompleted portion 
is inactive. 
5. Contains latest map of river. 
6. Latest published map is in Annual Report for 1914, 
opposite p. 2928. 
7. Contains latest published map of North Branch above 
North Ave. 
8. Contains latest published map. 
9. Completed under previous project. 
10. Uncompleted portion was deauthorized in 1977 
[widen and deepen Lake George Branch.] 
11. Included in Public Works Administration Program 
Sept. 6, 1933, and July 25, 1934. Uncompleted portion was 
deauthorized in 1977 widen and deepen main canal and 
Calumet River Branch.I 
12. Project deauthorized in 1977. 
13. Project deauthorized in 1983. 
30-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 30-C EXISTING PROJECTS 
See 
Section Length Width Depth 
in Text Project Item (feet) (feet) (feet) 
1. Burns Waterway 
Harbor, IN 
2. Calumet Harbor and 
River, IL and IN 
3. Chicago Harbor, 
and Lock, IL 
4. Chicago River, IL 
5. Indiana Harbor, IN 
North Breakwater 
Outer West Bulkhead 
Approach Channel 
Outer Harbor 
East Harbor Arm 
West Harbor Arm 
Northerly Crib Breakwater 
Southerly Steel Breakwater 
North pier 
Approach channel 
Outer harbor 
River entrance 
Elgin, Joliet & Eastern Railway Bridge 
to turning basin No. 3 
Turning basin No. 3 to turning basin 
No. 5 
Approach into Lake Calumet 
Extension into Lake Calumet 
Turning basins 1, 3 and 5 
Shore arm extension 
Exterior breakwater 
Exterior breakwater southerly ext. 
North inner breakwater 
South inner breakwater 
North pier 
Approach channel 
Channel and maneuver area 
Lock 
Inner basin 
Entrance channel 
Main Branch of Chicago River 
North Branch of Chicago River 
North Branch Canal 
North Branch Turning Basin 
Northerly Breakwater 
Easterly Breakwater 
Approach Channel 
Outer Harbor 
Entrance Channel 
Main Canal 
Turning Basin 
Lake George Branch 
Calumet River Branch 
4,646 
3,476 
2,200 
3,700 
2,100 
3,800 
6,714 
5,007 
2,450 
9,700 
10,500 
3,000 
21,100 
8,000 
4,000 
3,000 
2,250 
5,421 
4,944 
4,034 
2,544 
960 
6,600 
2,200 
600 
1,270 
7,300 
3,800 
11,100 
5,500 
1,120 
2,525 
7,200 
4,200 
3,600 
7,400 
3,700 
2,500 
4 
Vari 
66 
3,2 
3,0
22 
and varial 
Varial
00 30 
ies 28 
20 27 
20 27 
- - 
00 29 
00 28 
90 27 
00 27 
ble earth 
28 
rock 
ble 27 
400 
1,000 
800 
1,300 
80 
740 
190-470 
190-390 
91-390 
56-210 
800 
Varies 
65-280 
61-210 
64-160 
160-260 
27 
27 
27 
29 
28 
23 
21 
21 
21 
21 
21 
21
- 
29 
28 
27 
22 
22 
22 
22 
30-14

TABLE 30-C (Cont'd) 
CHICAGO, IL, DISTRICT 
EXISTING PROJECTS 
See 
Section Length Width Depth 
in Text Project Item (feet) (feet) (feet) 
6. Michigan City Harbor, Detached breakwater 1,304 - - 
IN West pier 835 - - 
EasArpeiae ro f about 2,276 
East breakwater 1,00S0e ptember 30, 19-83 -to 
Entrance channel 1,900 150-425 18 
Main channel 2,400 120-150 18 
Outer basin 900 900 8-12 
Trail Creek 3,000 50-100 8 
Trail Creek 2,300 50 6 
7. Waukegan Harbor, North breakwater and Shore Conne1ct,8io9n6 - -Text) 
IL North pier and North Revetment 2,074 - - 
South pier 3,111 -C -t 
Entrance channel 3,250 390 22 
Channel to inner basin 1,700 200 18 
Inner basin 1,650 375-500 18 
Anchorage Area _1 _1 8 
1Area of about 6 acres. 
TABLE 30-D OTHER AUTHORIZED BRIDGE ALTERATION 
(See Section 10 of Text) 
For Last Cost to September 30, 1983 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Calumet River Bridges 1967 $1,625,068271 
1Transferred to Department of Transportation in accordance with Section 6[g] of the Act of October 15, 1966, P.L. 89-670. 
TABLE 30-E OTHER AUTHORIZED BEACH EROSION PROJECTS 
(See Section 13 of Text) 
For Last Cost to September 30, 1983 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Hollywood-Ardmore Beach, 
Chicago, IL 1982 $237,271 
Evanston, IL 1979 766,052 
Lake Michigan-Lake Bluff, IL 1976 244,889 
Lake Michigan-Lake Forest, ILl 1975 65,611 
xAuthorized by River and Harbor Act of 1954. 
30-15

TABLE 30-F 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
OTHER AUTHORIZED 
FLOOD CONTROL PROJECTS 
(See Section 17 of Text) 
For Last Cost to September 30, 1983 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
KANKAKEE RIVER, IL AND IN 
Levee between Shelby Bridge and Baum's 
Bridge in IN 1938 
LITTLE CALUMET RIVER, IL AND IN 
Little Calumet River and Tributaries, IL 
and IN' 1968 53,136 
1Classified inactive in November 1971. 
TABLE 30-G RECONNAISSANCE AND CONDITION SURVEYS 
(See Section 8 of Text) 
Date 
Reconnaissance 
or Condition 
Survey 
Project Conducted Cost 
Burns Waterway Harbor, IN June 1983 $-19,1861 
Calumet Harbor & River, 
IL and IN March, May, July 1983 47,537 
Chicago Harbor, IL March 1983 11,146 
Chicago River, IL March 1983 488 
Indiana Harbor,. IN June, Aug, Sept. 1983 24,758 
Michigan City Harbor, IN July 1983 11,093 
Waukegan Harbor, IL March 1983 1,978 
1Note: A credit of $19,186 occurred in 1983 as a result of condition surveys performed at Burns Waterway Harbor, IN during 
1982. 
30-16

DETROIT, MI DISTRICT* 
The district is composed of the upper and lower 
peninsulas of Michigan and portions of Indiana, 
Wisconsin and Minnesota, which border the lakes. It 
includes U. S. waters of Lakes Superior, Michigan, 
Huron, St. Clair and western Lake Erie. Unless 
otherwise indicated all depths stated in this report 
are referred to low water datum as follows: Lake 
Superior, 600 feet; Lake Michigan-Huron, 576.8 feet; 
Lake Erie, 568.6 feet; and Lake St. Clair, 571.7 feet. 
Elevations in feet are above mean water level at 
Father Point, Quebec (International Great Lakes 
Datum-1955). 
IMPROVEMENTS 
Navigation Page 
1. Arcadia Harbor, MI ...................... 31-2 
2. Ashland Harbor WI ....................... 31-2 
3. Au Sable Harbor, (Oscoda) MI ............. 31-3 
4. Big Bay Harbor, MI ....................... 31-3 
5. Black River,(U.P.) MI ..................... 31-3 
6. Channels in the Straits 
of Mackinac, MI...........................31-3 
7. Charlevoix Harbor, MI .................... 31-4 
8. Cheboygan Harbor, MI .................... 31-4 
9. Clinton River, MI..........................31-5 
10. Cross Village Harbor, MI..................31-5 
11. Detour Harbor, MI ........................ 31-6 
12. Detroit River, MI..........................31-6 
13. Duluth-Superior Harbor, MN and WI ...... 31-7 
14. Eagle Harbor, MI ......................... 31-7 
15. Fox River, W I.............................31-7 
16. Frankfort Harbor, MI ...................... 31-8 
17. Grand Haven Harbor and 
Grand River, MI .......................... 31-9 
18. Grand Marais Harbor, MN ............... 31-9 
19. Grand Traverse Bay Harbor, MI .......... 31-10 
20. Green Bay Harbor, WI................... 31-10 
21. Hammond Bay Harbor, MI .............. 31-11 
22. Harbor Beach Harbor, MI ............... 31-11 
23. Harrisville Harbor, MI .................. 31-11 
24. Holland Harbor, MI ..................... 31-11 
25. The Inland Route, MI.................... 31-12 
26. Kenosha Harbor, WI..................... 31-13 
27. Kewaunee Harbor, WI................... 31-13 
28. Keweenaw Waterway, MI................ 31-14 
29. Knife River Harbor, MN................. 31-14 
30. Lac La Belle Harbor, MI................. 31-15 
31. Lake St. Clair, MI Channels.............. 31-15 
32. Leland Harbor, MI ...................... 31-15 
33. Lexington Harbor, MI ................... 31-15 
34. Little Lake Harbor, MI .................. 31-16 
35. Ludington Harbor, MI...................31-16 
36. Manistee Harbor, MI .................... 31-17 
37. Manistique Harbor, MI.................. 31-17 
Navigation (cont.) Page 
38. Manitowoc Harbor, WI .................. 31-17 
39. Marquette Harbor, MI................... 31-18 
40. Menominee Harbor and River, 
MI and W I.............................. 31-18 
41. Milwaukee Harbor, WI .................. 31-19 
42. Monroe Harbor, MI...................... 31-20 
43. Muskegon Harbor, MI................... 31-20 
44. New Buffalo Harbor, MI................. 31-20 
45. Oconto Harbor, WI ...................... 31-21 
46. Ontonagon Harbor, MI .................. 31-21 
47. Pensaukee Harbor, WI................... 31-21 
48. Pentwater Harbor, MI................... 31-22 
49. Point Lookout Harbor, 
(Au Gres River) MI...................... 31-22 
50. Portage Lake Harbor, MI................ 31-22 
51. Port Sanilac Harbor, MI................. 31-23 
52. Port Washington Harbor, WI ............ 31-23 
53. Port Wing Harbor, WI................... 31-23 
54. Presque Isle Harbor, MI................. 31-24 
55. Racine Harbor, WI ....................... 31-24 
56. Rouge River, MI......................... 31-24 
57. Saginaw River, MI ...................... 31-25 
58. St. Clair River, MI ...................... 31-26 
59. St. Joseph Harbor, MI ................... 31-26 
60. St. Marys River, MI ..................... 31-27 
61. Saugatuck Harbor and Kalamazoo 
River, M I............................... 31-27 
62. Saxon Harbor, WI....................... 31-28 
63. Sheboygan Harbor, WI .................. 31-28 
64. South Haven Harbor, MI ................. 31-28 
65. Sturgeon Bay and Lake Michigan 
Ship Canal, WI..........................31-29 
66. Two Harbors, MN....................... 31-29 
67. White Lake Harbor, MI................... 31-30 
68. Reconnaissance and Condition 
Surveys................................. 31-30 
69. Other Authorized Navigation Projects ..... 31-30 
70. Navigation Work Under Special 
Authorization........................... 31-30 
31-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Beach Erosion Control Page 
71. Authorized Beach Erosion 
Control Projects......................... 31-30 
72. Emergency Shore Protection .............. 31-30 
73. Beach Erosion Work Under Special 
Authorization...........................31-30 
74. Mitigation of Shore Damages ............ 31-31 
Flood Control 
75. Red Run Drain-Lower Clinton 
River, M I ............................... 31-31 
76. Saginaw River, MI ...................... 31-32 
77. Sebewaing, Sebewaing River, MI.......... 31-33 
78. Inspection of Completed Flood 
Control Projects......................... 31-33 
79. Other Authorized Flood Control 
Projects ................................ 31-33 
80. Flood Control Under Special 
Authorization ........................... 31-33 
81. Surveillance of Northern Boundary 
W aters ................................. 31-34 
General Investigations Page 
82. Surveys................................. 31-36 
83. Advanced Engineering and Design ........ 31-36 
84. Collection and Study of Basic 
Data.................................... 31-36 
Tables 
Table 31-A Cost & Financial Statement ...... 31-37 
Table 31-B Authorizing Legislation .......... 31-53 
Table 31-C Features of Existing 
Project......................... 31-71 
Table 31-D St. Marys River, MI: 
Existing Project ................. 31-72 
Table 31-E Fox River, WI: Locks & Dams .... 31-73 
Table 31-F Reconnaissance & Condition 
Surveys ........................ 31-74 
Table 31-G Other Authorized 
Navigation Projects............. 31-75 
Table 31-H Other Authorized Flood 
Control Projects ................ 31-76 
Table 31-I Deauthorized Projects........... 31-77 
Navigation 
1. ARCADIA HARBOR, MI 
Location. On east shore of Lake Michigan, 193 
miles northeasterly from Chicago, IL, and 15 miles 
northerly from Manistee, MI. (See NOAA Nautical 
Chart No. 14907). 
Existing project. Provided for maintenance dredging 
of the existing harbor built by private interests for a 
period of five years. The five years covered by this 
project were the calendar years 1905 to 1909, inclusive. 
Funds were also appropriated and maintenance was 
performed in calendar years 1911,1912,1913 and 1915, 
inclusive. There is at present no approved project for 
the improvement of this harbor. (See Table 31-B for 
authorizing legislation.) 
Local cooperation. None required. 
Terminal facilities. Dock facilities are considered 
adequate for existing recreational traffic. 
Operations during fiscal year. Maintenance: 
Condition surveys, environmental studies, miscellaneous 
inspections and reports were performed by Government 
forces at a cost of $52,165. A contract was 
awarded and completed for maintenance dredging at a 
cost of $26,940. Approximately 7,920 cubic yards of 
shoal material was removed by hydraulic dredge. 
Repair to the South Pier was performed by hired labor 
at a cost of $56,549. Engineering and design for repair 
to breakwater was continued at a cost of $1,988. 
Engineering, design, surveys, supervision and administration 
cost $18,356. 
Existing project was completed in 1909. Varying 
depths of 5-12 feet exist in the channel at present. 
Future maintenance of the harbor will be based on 
providing a 9-foot depth. Piers and revetments are in 
good condition with some sections in need of major 
repair. Total cost at end of FY for existing project was 
$779,388. 
2. ASHLAND HARBOR, WI 
Location. At head of Chequamegon Bay, on south 
shore of Lake Superior, about 65 miles east of Duluth, 
MN. (See NOAA Nautical Chart 14974.) 
Existing project. A west channel 20 and 21 feet 
deep and an east basin 25 and 27 feet deep, both all 
protected by an 8,000-foot breakwater. For additional 
details see page 1008 of Annual Report for 1965. (See 
Table 31-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. City of Ashland owns 4,150 
feet of waterfront for future public needs. Wharves for 
handling coal, ore, limestone, logs, and pulpwood are 
served by railroads. Facilities are considered adequate 
for existing commerce. Handling of ore and logs has 
been discontinued for the present. 
Operations during fiscal year. Maintenance:Condition 
surveys, environmental studies and miscellaneous 
reports and services were performed by Government 
forces at a cost of $21,482. Repairs to breakwater 
and seawalls were performed by hired labor at a cost of 
$39,278. Engineering, supervision and administration 
cost $16,730. 
Work authorized prior to 1960 Act was completed in 
1950. Work authorized by 1960 Act was completed in 
31-2

DETROIT, MICHIGAN DISTRICT 
November 1962. Total cost of existing project to end of 
FY was $3,913,782, of which $1,695,645 was for new 
work and $2,218,137 for maintenance. 
3. AU SABLE HARBOR AT AU SABLE 
RIVER (OSCODA), MI 
Location. Au Sable River and Village of Oscoda, 
MI, are on west shore of Lake Huron, 8 miles north of Au 
Sable Point, northeast limit of Saginaw Bay. (See 
NOAA Nautical Chart 14863.) 
Previous project. For details see pages 336 and 
2453 of Annual Report for 1892. 
Existing project. Riprapping outer 200 feet of 
north pier at mouth of Au Sable River, dredging an 
entrance channel 12 feet deep and dredging between 
piers and upstream to State highway bridge 10 feet 
deep. (See Table 31-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Several small timber pile 
wharves used primarily by commercial fishermen and 
pleasure craft operators; also a private marina basin 
east of U.S. Highway 23 Bridge. Facilities are considered 
adequate for existing commerce. 
Operations during fiscal year. Maintenance: Condition 
surveys and miscellaneous inspections were 
performed by Government forces at a cost of $16,181. 
Engineering and design for maintenance dredging was 
performed at a cost of $14,111. 
Existing project was completed in 1962. Controlling 
depths are 10.0 feet in entrance channel, 8.0 feet 
between the jetties, and 6 feet in river to upstream 
limits of project. Total costs to end of FY for existing 
project were $2,660,203, of which $209,776 was for new 
work (including $16,400 contributed funds) and 
$2,450,427 for maintenance. 
4. BIG BAY HARBOR, MI 
Location. On south shore of Lake Superior 33 miles 
northwesterly from Marquette, MI, and 38 miles 
easterly from Portage entry to Keweenaw Waterway. 
(See NOAA Nautical Chart 14964.) 
Existing project. Provides for two converging 
piers extending from shore, an entrance channel 
between piers and rectangular harbor basin. Project 
depths are 12 feet in entrance channel and 10 feet in 
harbor basin. For details see page 1009 of Annual 
Report for 1965 and page 1261 of Annual Report for 
1962. (See Table 31-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Operations during fiscal year. New Work. Detailed 
project studies on the authorized section 111 
project were terminated at a cost of $2,975. Maintenance: 
Condition surveys, environmental studies, miscellaneous 
inspections and reports were performed by 
hired labor at a cost of $35,632. Repair to navigation 
structures was performed by hired labor at a cost of 
$38,752. 
Project was completed in June 1961 except for 
protection at inner end of east breakwater, completed in 
November 1961. A contract for repair of breakwater, 
damaged by storms, was completed in August 1969. 
Total cost to end of FY was $1,384,484, of which 
$390,432 was for new work and $994,052 for maintenance. 
5. BLACK RIVER HARBOR 
(UPPER PENINSULA), MI 
Location. At mouth of Black River on south shore of 
Lake Superior 39 miles westerly from Ontonagon, MI, 
and 47 miles easterly from Ashland, WI. (See NOAA 
Nautical Chart 14965.) 
Existing project. Two converging breakwaters, an 
entrance channel between breakwaters, an inner channel, 
and an irregular harbor basin. For additional 
details see page 1092 of Annual Report for 1966. Project 
depths are 12 feet in the approach channel and 8 feet in 
the river channel and basin. (See Table 31-B for 
authorizing legislation.) 
Local cooperation. Fully complied with. Local 
interests furnished easements on 0.85 acre of land. 
Terminal facilities. Wharves constructed on both 
sides of river. Wharf on east bank has frontage of 400 
feet; on west bank, a frontage of 750 feet. 
Operations during fiscal year. Maintenance: Condition 
survey and miscellaneous inspections were 
performed by hired labor at a cost of $6,975. Engineering 
and design for maintenance dredging was 
performed at a cost of $4,025. 
Project was completed in June 1958. A triangularshaped 
rock shoal 50 feet wide at easterly end extends 
along southerly side of channel. Total cost for existing 
project to end of FY was $875,773, of which $383,350 
was for new work and $492,423 for maintenance. 
6. CHANNELS IN THE STRAITS OF 
MACKINAC, MI 
Location. A Great Lakes connecting channel, joins 
Lakes Michigan and Huron at their upper ends and is 
about 7 miles northeasterly from Mackinaw City, MI. 
(See NOAA Nautical Chart 14881.) 
Existing project. Provides for a channel between 
Mackinac Island and Round Island, MI, 1,250 feet wide, 
30 feet deep, and 3,500 feet long; and for removal of Poe 
Reef Shoal to a depth of 30 feet over an area of about 
120,000 square yards to permit navigation through 
Straits of Mackinac by vessels drawing 25.5 feet at low 
water datum. (See Table 31-B for authorizing legislation.) 
31-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1988 
Local cooperation. None required. 
Terminal facilities. None. 
Operations during fiscal year. Maintenance: Condition 
surveys, environmental studies, miscellaneous 
inspections and reports were performed by Government 
forces at a cost of $30,907. The existing project is 
complete. Total costs to end of FY were $2,976,854, of 
which $2,832,629 was for new work and $144,225 for 
maintenance. 
7. CHARLEVOIX HARBOR, MI 
Location. On east shore of Lake Michigan, 276 
miles northeasterly from Chicago, IL, and 75 miles 
northerly from Frankfort, MI. (See NOAA Nautical 
Chart 14942.) 
Existing project. A channel 24 feet deep in Lake 
Michigan and a river channel 23 feet deep in the lower 
and upper channels connecting Lake Michigan with 
Lake Charlevoix via Round Lake. The channels are 
protected where needed by piers and revetments. For 
additional details see page 1476 of Annual Report for 
1962. (See Table 31-B for authorizing legislation.) 
Local cooperation. None required except the latest 
project modification is subject to the following: 
Provide without cost to the United States, all lands, 
easements, and rights-of-way required for construction 
and subsequent maintenance of the modified project 
upon the request of the Chief of Engineers, including 
suitable areas determined by the Chief of Engineers to 
be required in the general public interest for initial and 
subsequent disposal of excavated materials and any 
necessary retaining dikes, bulkheads, and embankments, 
therefor, or the cost of such retaining works; 
hold and save the United States free from damages due 
to the construction and maintenance of the modified 
project, except for damages due to the fault or negligence 
of the United States or its contractors; provide 
and maintain without cost to the United States depths 
in berthing areas and local access channels serving the 
terminals commensurate with the depths provided in 
the related project areas; accomplish, without cost to 
the United States, such alterations of submarine utility 
crossing as are required by the modified project; 
establish regulations prohibiting discharge of 
pollutants into the waters of the harbor by users thereof 
which regulations shall be in accordance with applicable 
laws or regulations of Federal, State and local 
authorities responsible for pollution prevention and 
control; if acquiring lands, easements and rights-ofway 
for construction of the project, local interests will 
comply with the applicable provisions of the Uniform 
Relocation Assistance and Real Property Acquisition 
Policies Act of 1970; Public Law 91-646, approved 
January 2, 1971; contribute all costs in excess of 
$1,000,000 should the total cost of construction of the 
general navigation facilities exceed that amount, in 
accordance with provisions of Section 107 of the 1960 
River and Harbor Act, as amended. The total first cost 
of construction is presently estimated at $652,000. 
Terminal facilities. Several small landing places 
in Round Lake at Charlevoix for handling fish and 
miscellaneous commodities, a wharf for petroleum 
products at west end of Lake Charlevoix, and coal 
wharves at Advance and Boyne City. Charlevoix, Boyne 
City, and East Jordan provide public docks for small 
craft. Facilities considered adequate for existing commerce. 
Operations during fiscal year. Maintenance: Condition 
surveys, operation of safety features, miscellaneous 
inspections and reports were performed at a 
cost of $45,188. Repair to North and South revetments 
and breakwaters was performed by Government forces 
at a cost of $119,300. An adjustment of $81,664 was 
made in contract completed last FY for major repair to 
North and South piers and revetments. Engineering 
and design for repair to Park Island Revetment was 
continued at a cost of $32,873. Engineering and design 
for other work items, supervision and administration 
cost $31,429. 
Existing project was completed in 1939 except for the 
latest modification. A controlling depth of 18 feet is 
available throughout the entire project, except for 
minor shoaling along the channel limits. Total costs to 
end of FY were $5,828,492, of which $180,623 was for 
new work, $4,518,473 for maintenance (Bank Stabilization 
$46,352), and $1,129,396 for rehabilitation. 
8. CHEBOYGAN HARBOR, MI 
Location. At mouth of Cheboygan River which 
empties into Western Lake Huron about 16 miles 
southeast of the Straits of Mackinac Bridge. (See 
NOAA Nautical Charts 14881 and 14886.) 
Previous project. For details see page 1956 of 
Annual Report for 1915, and page 1546 of Annual 
Report for 1938. 
Existing project. A channel 21 feet deep and 200 
feet wide from 21-foot contour in Lake Huron to outer 
end of west pier; thence, between lines parallel to and 25 
feet from the docks, 21 feet deep from this point to East 
First Street and thence 18.5 feet deep and 60 feet wide 
from this bridge to the lock in Cheboygan River; a 
turning basin 21 feet deep, 400 feet wide, and 420 to 770 
feet long on east side of existing project channel just 
below East First Street; and rubblemound breakwater 
about 775 feet long on the site of existing west pier at 
mouth of river. Improvement is 12,000 feet long, of 
which about 6,000 feet are in Straits of Mackinac. 
Local cooperation. Fully complied with. 
Terminal facilities. Several privately owned 
wharves used for receiving coal, stone and petroleum 
products. Public recreational boating facilities constructed 
by the State and local agencies are available. 
31-4

DETROIT, MICHIGAN DISTRICT 
These facilities satisfy existing commerce and vessel 
traffic. 
Operations during fiscal year. Maintenance: Condition 
surveys, environmental studies, miscellaneous 
inspections and reports were performed by hired labor 
at a cost of $17,593. An adjustment of $-11,306 was 
made in contract completed last FY for minor repairs to 
breakwater. Engineering, design, supervision and 
administration cost $6,321. Total costs to end of FY 
were $1,366,431, of which $504,236 was for new work 
and $862,195 for maintenance. 
9. CLINTON RIVER, MI 
Location. Has its source in Oakland County, MI, 
flows easterly about 60 miles and empties into Anchor 
Bay in northwestern part of Lake St. Clair. (See NOAA 
Nautical Chart 14850.) 
Previous project. For details see page 1958 of 
Annual Report for 1915, and page 1556 of Annual 
Report for 1938. 
Existing project. An entrance channel in Anchor 
Bay 8 feet deep, 300 feet wide at 8-foot depth contour in 
the bay, gradually decreasing to 50 feet wide at about 
1,000 feet upstream from mouth of Clinton River, a 
length of about 4,600 feet; a channel 8 feet deep and 50 
feet wide in the river about 38,700 feet long from 
entrance channel upstream to Mt. Clemens at Cass 
Avenue; closing old channel and making a cutoff at 
Shoemakers Bend; closing Catfish Channel; construction 
of revetments as needed in the river; and a harbor 
basin, 5 feet deep and 11 acres in area at entrance along 
bay channel, protected by breakwaters on north and 
south sides. (See Table 31-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. River is used exclusively by 
recreational craft. There are numerous public and 
private piers and wharves along the river below the 
City. They are considered adequate. 
Operations during fiscal year. Maintenance: Condition 
surveys, miscellaneous inspections and reports 
were performed by Government forces at a cost of 
$12,660. Engineering and design for a confined disposal 
area for polluted dredged material was continued at a 
cost of $33,412. 
Existing project was completed in 1966. Total costs to 
end of FY were $1,773,107, of which $549,798 (including 
$289,752 contributed funds) was for new work, and 
$1,223,309 for maintenance. 
10. CROSS VILLAGE HARBOR, MI 
Location. On northeast shore of Lake Michigan, 
about 26 miles northeast of Charlevoix, MI (See NOAA 
Nautical Chart 14902.) 
Existing project. Provides for two breakwaters 
having an aggregate length of about 2,300 feet with 
provision r recreational fishing on the main breakwater; 
an anchorage and maneuver area of about 8 
acres and 10 feet deep and a flared entrance channel 12 
feet deep decreasing in width to 100 feet through the 
breakwaters. Estimated (1982) Federal cost for new 
work is $2,766,000; the non-Federal cost is $1,744,000, 
which is a cash contribution. (See Table 31-B for 
authorizing legislation.) 
Local cooperation. Responsible local interests must 
furnish assurances that they will contribute in cash 38 
percent of the first cost of construction of the general 
navigation facilities and 50 percent of the first cost of 
facilities necessary to provide for recreational fishing 
on the main breakwater, such contributions presently 
estimated at $1,538,000 and $206,000, respectively, to 
be paid in a lump sum prior to initiation of construction, 
subject to final adjustment after actual costs have been 
determined; provide without cost to the United States 
all lands, easements and rights-of-way required for the 
construction and maintenance of the project and of aids 
to navigation upon the request of the Chief of Engineers, 
including suitable areas determined by the Chief 
of Engineers to be required in the general public 
interest for initial and subsequent disposal of spoil and 
necessary retaining dikes, bulkheads, and embankments 
therefor, or the costs of such retaining works; 
hold and save the United States free from damages due 
to the construction works and subsequent use, operation, 
and maintenance of the project; provide and maintain 
without cost to the United States necessary mooring 
facilities and utilities, including an adequate public 
landing with provision for the sale of motor fuel, 
lubricants, potable water, a parking lot with adequate 
sanitary facilities, and a launching ramp, open to all on 
equal terms, the dredging of berthing areas to be 
commensurate with the depth of the Federal channel 
improvements; establish a competent and properly 
constituted public body empowered to regulate the use, 
growth, and development of the harbor and recreationoriented 
facilities with the understanding that said 
facilities shall be open to all on equal terms: reserve 
spaces wthin the anchorage and mooring facilities 
adequate for the accommodation of transient craft; 
provide and maintain, without cost to the United States, 
for recreational fishing access facilities, parking areas, 
and adequate sanitary facilities; establish regulations 
prohibiting discharge of untreated sewage, garbage, 
and other pollutants in the waters of the harbor by users 
thereof, which regulations shall be in accordance with 
applicable laws or regulations of Federal, State, and 
local authorities responsible for pollution prevention 
and control; bear all costs of operation, maintenance, 
and replacement of the recreational fishing facilities, 
the amount involved currently being estimated at 
$1,500 on an average annual basis; and provided 
further that the improvement for navigation may be 
undertaken independently of the public recreational 
fishing facilities on the main breakwater whenever 
31-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
funds for that purpose are available and the 
required local cooperation has been furnished. 
Terminal facilities. No facilities are available 
except a small launching ramp for recreational craft. 
Complete boating facilities are planned by State and 
local agencies in connection with the harbor construction. 
Operations during fiscal year. New work: The 
Phase II General Design Memorandum initiated last 
FY was approved on May 13,1983. The Phase II GDM 
contains an environmental analysis section that addresses 
potential impacts of breakwater configuration changes 
from the Phase I GDM plan, and details the Phase II 
underwater reef configuration. FY 83 cultural resources 
work has resulted in the identification of eight 
separate sites and structures, six houses, and the entire 
community of Cross Village, as potentially eligible for 
inclusion in the National Register of Historic Places. 
Costs in FY 83 were $24,590. 
11. DETOUR HARBOR, MI 
Location. On the west side of DeTour Passage, 
about 2 miles upstream from Lake Huron. The passage 
forms the mouth of the St. Marys River which connects 
Lakes Huron and Superior. (See NOAA Nautical Chart 
14882.) 
Existing project. Provides for small boat harbor 
and harbor of refuge by dredging a 10-foot deep 
entrance channel and providing an 8-foot deep access 
channel protected by a 1,305-foot breakwater. The total 
estimated (October 1981) project cost is $2,650,000; the 
Federal cost is $1,400,000 and the non-Federal cost is 
$1,250,000 which is a cash contribution. 
Local cooperation. Fully complied with. 
Terminal facilities. Public docking, landing, parking 
and sanitary facilities will be provided by the State 
of Michigan. 
Operations during fiscal year. New work: An 
adjustment of $-31,490 was made in the contract 
awarded in FY 80 and completed last FY. Of the above, 
$30,626 was contributed funds. Maintenance: Condition 
surveys were performed at a cost of $280. The existing 
project is complete. Total cost to end of FY is $2,553,172, 
of which $280 was for maintenance and $2,552,892 for 
new work. 
12. DETROIT RIVER, MI 
Location. One of the Great Lakes connecting 
channels, 31 miles long and flows south from Lake St. 
Clair to Lake Erie. (See NOAA Nautical Chart 14848.) 
Previous project. For details see page 1958 of 
Annual Report for 1915, and page 1541 of Annual 
Report for 1938. 
Existing project. Improving Detroit River main 
channels to provide 25.5-foot draft navigation; improving 
certain auxiliary and side channels; and construction 
of various water level and crosscurrent control 
structures. Details are in accompanying Table 31-C. 
Project depths are referred to local low water datum 
planes which correspond to low water datums for Lakes 
St. Clair and Erie, 571.7 and 568.6 feet above mean 
water level at Father Point, Quebec (International 
Great Lakes Datum-1955.XSee Table 31-B for authorizing 
legislation.) 
Estimated 1978 Federal cost for new work, exclusive 
of amounts expended on previous projects, is $159,300,- 
000. 
Local cooperation. Fully complied with. No local 
cooperation is required for modifications authorized by 
Acts of July 1946 and March 1956. Tie Trenton 
Channel modification approved August 13, 1968 is 
considered inactive. 
Terminal facilities. Numerous commercial installations 
used for handling coal, iron ore, limestone, steel 
products, petroleum products, and other items such as 
overseas general cargo. Detail on actuak port and 
harbor facilities is in Port Series No. 45 (revised 1972) 
prepared and published as part 2 by Board of Engineers 
for Rivers and Harbors. Information on port and 
steamship services is prepared and published as part I 
by Port Development Staff, U.S. Department of Commerce. 
Facilities are considered adequate for existing 
commerce. 
Operations during fiscal year. Maintenance: Condition 
surveys, environmental studies, Hi-Fix surveys, 
support of Water Control Center, miscellaneous inspections 
and reports were performed at a cost of $1,373,737. 
Environmental studies for extended navigation season 
were continued at a cost of $294,965. Studies were 
continued for construction of a marsh under Section 150 
of the Water Resources Development Act of 1967 at a 
cost of $8,842. The U.S. Hopper Dredge HAINS 
performed maintenance dredging removing 35,863 
cubic yards, bin measure, of shoal material at a cost of 
$257,872. Operation of booster pump in connection with 
dredging cost $102,817. Maintenance of disposal area 
by hired labor cost $66,447. Location and removal of 
obstructions cost $1,198,673. Hired labor repair of 
compensating work cost $114,316. The contract awarded 
last FY for repair of Sugar Island Compensating 
Dike was completed at a cost of $946,039. The contract 
awarded last FY for maintenance dredging East Outer 
Channel, Lower Livingstone Channel and Pte. Mouillee 
Access and South Interior Channel was completed at a 
cost of $4,002,568. Approximately 642,838 cubic yards, 
bin measure, of shoal material was removed by hopper 
dredge. An adjustment of $-58,778 was made in 
Tcounrtnriancgt Bcaossitn foofr Pmte.a iMntoeunilalenec ec odmrpeldegteidn gl aosft FSYou. tAh 
contract was awarded in the amount of $1,298,675, for 
dredging East Outer Channel, Lower Livingstone and 
Mouillee Access Channel and Pte. Mouillee North 
31-6

DETROIT, MICHIGAN DISTRICT 
Interior Channel including North Turning Basin. No 
work was performed this FY. Engineering, design, 
surveys, supervision and administration cost $222,804. 
Under the dike disposal program approximately $3, 
610 was expended for review of claims. Latest modification 
of connecting channels project in the Detroit River 
is complete except for compensating works. 
All work in Trenton Channel is complete. Pertinent 
data concerning channels covered by project at end of 
FY are set forth in Table 31-C. Costs for existing project 
were $171,081,614, of which $74,780,103 was for new 
work ($72,969,197 regular funds and $1,530,688 Public 
Work Funds) and $96,301,511 for maintenance. 
13. DULUTH-SUPERIOR HARBOR, 
MN AND WI 
Location. At extreme western end of Lake Superior. 
Cities of Duluth, MN, and Superior, WI, are on 
north and south sides, respectively. (See NOAA Nautical 
Chart 14975.) 
Previous projects. See page 1246 of Annual Report 
for 1962. 
Existing project. Provides for rebuilding canal 
piers at Duluth entry, replacement or construction of 
piers and breakwater at Superior entry and dredging 
approaches and channels within harbor, St. Louis Bay, 
and St. Louis River. Channels vary in depth from 32 to 
28 feet in entrances, are 27 feet deep in iron-ore route 
channels, and are from 20 to 23 feet in inner channels. 
(See Table 31-B for authorizing legislation.) 
For details of authorized channel dimensions and 
dimensions of structures, see pages 1246 and 1247 of 
Annual Report for 1962 and page 1011 of Annual 
Report for 1965. Portion of project for deepening 
Twenty-first Avenue West channel is inactive. Estimated 
cost (1967) of this portion was $577,000. 
Local cooperation. Fully complied with for active 
portion of project. 
Terminal facilities. There are 113 docks or terminals 
including some 54 major ones; all but one are 
privately owned. Facilities for handling iron ore, coal, 
limestone, petroleum, steel and scrap iron, cement, 
general cargo, and grain are believed adequate for most 
existing commerce. 
Operations during fiscal year. Maintenance: Condition 
surveys, environmental studies, support of Water. 
Control Center, co-operative stream gaging, miscellaneous 
inspections and reports were performed by 
Government forces at a cost of $289,674. The reconnaissance 
report for major rehabilitation of Duluth 
Ship Canal was completed and a General Design 
Memorandum initiated at a cost of $30,131. Operation 
and maintenance of the museum was performed by 
Government forces at a cost of $240,327. Repairs to 
breakwaters and seawalls were performed at a cost of 
$270,379. Maintenance of service facilities and 
park pier was performed at a cost of $41,887. Maintenance 
of disposal area was performed at a cost of 
$81,102. Hired labor dredging initiated last FY by the 
GAILLARD and COLEMAN was completed by COLEMAN 
at a cost of $185,282. An adjustment of $30,511 
was made for payment of a claim for contract dredging 
completed in FY 81. Two contracts were awarded this 
FY for maintenance dredging. The first contract was 
awarded in the amount of $749,185. The contract is 
approximately 42 percent complete with 21,000 cubic 
yards removed at a cost of $314,716. The second 
contract, awarded in the amount of $357,800, is 46 
percent complete removing 19,700 cubic yards at a cost 
of $164,588. Engineering, design, surveys, supervision 
and administration cost $237,474. 
Work authorized prior to 1960 Act was completed in 
June 1956. Under the 1960 Act, work on the outer 
harbor, included in House Document 150, was completed 
in June 1965. Work on the inner harbor, included 
in House Document 196, started in May 1963, was 
completed in November 1968 except for the 21st 
Avenue West channel portion which is inactive. 
The United States owns 34.90 acres of land in fee in 
Minnesota and Wisconsin of which 2.15 acres are used 
for a vessel yard. Total cost of existing project was 
$44,784,301, of which $16,109,158 was for new work 
and $28,675,143 was for maintenance. 
14. EAGLE HARBOR, MI 
Location. On the south shore of Lake Superior on 
the North Face of Keweenaw Point, 31 miles northeasterly 
from the Upper Entrance to Keweenaw 
Waterway. (See NOAA Nautical Chart 14964.) 
Existing project. Provides for a short entrance 
channel, a guide pier marking the entrance on the west 
side, and a harbor basin. Project depths are 14 feet in 
the entrance channel and 12 feet in the harbor basin. 
For additional details see page 1182 of Annual Report 
for 1959. (See Table 31-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. An old L-shaped timber wharf 
is available but is in poor condition. A dock and 
launching ramp constructed by the State is located on 
the north side of the Harbor Basin. 
Operations during fiscal year. Maintenance: Condition 
surveys, miscellaneous inspections and reports 
were performed by Government forces at a cost of 
$13,353. The original project was completed in 1879. 
The modification for a small boat harbor was completed 
in 1959. Total cost to end of FY was $272,869, of which 
$205,164 was for new work and $67,705 for maintenance. 
15. FOX RIVER, WI 
Location. Rises in Columbia County, WI, and flows 
about 176 miles northerly into Green Bay. Wolf River, 
physically a main river but by designation a tributary 
31-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
of Fox River, rises in central part of Fort County, WI, 
and flows southerly. (See NOAA Nautical Chart 14916 
for Lake Winnebago and lower Fox River.) 
Previous projects. See page 1368 of Annual Report 
for 1962. 
Existing project. Deepening and widening channel 
of Fox River from DePere 7 miles above mouth to 
confluence of Wolf River, a total length of 59 miles, to 6 
feet, with 9.6 feet in rock cut below DePere lock and 7 
feet in other rock cuts on lower river below Menasha 
lock; construction and reconstruction of 19 locks and 9 
dams; a concrete retaining wall at Kaukauna; construction 
and maintenance of harbors having depths of 6 feet 
on Lake Winnebago; widening Neenah Channel to 100 
feet, with a 6-foot depth for about 1 mile; and dredging, 
snagging, and otherwise improving Wolf River 47 miles 
from its mouth to New London, depth to be 4 feet. 
Cost of completed portion of project is $513,424 for the 
lower river exclusive of previous projects. River and 
Harbor Act of 1925 portion of project is considered 
inactive and excluded from cost estimate. Estimated 
cost (1924) of this portion is $2,886,000. (See Table 31-B 
for authorizing legislation.) 
Local cooperation. None required. 
Terminal facilities. Wharf and landing facilities 
are, in general, adequate for existing needs. (See Table 
31-E on locks and dams, Fox River, WI.) 
Operations during fiscal year. Maintenance: Condition 
surveys, boundary monumentation, miscellaneous 
inspections and reports were performed by Government 
forces at a cost of $151,864. Plans for flood 
emergencies at Federal dams were prepared at a cost of 
$56,574. Water Control studies, monitoring and regulation 
of water levels were performed at a cost of 
$214,319. Rehabilitation materials for Little Chute 2nd 
Lock and Combined Locks were received at a cost of 
$29,004. Miter gates and valve systems at Little 
Kaukauna Lock were reconditioned at a cost of 
$119,726. Tainter gates and seals were reconditioned at 
Little Chute Dam at a cost of 64,181. Repairs to Federal 
canal banks at Little Kaukauna Dam, Appleton 4th 
Lock, Kaukauna 2nd Lock, and Little Chute Lock were 
performed at a cost of $111,124. Filling valve systems 
were overhauled at Kaukauna 3rd, 4th and 5th Lock at a 
cost of $10,010. The seventeen locks and two guard locks 
were operated and maintained at a cost of $507,218. The 
nine dams and ten overflow weirs were operated and 
maintained at a cost of $432,220. Engineering, design, 
supervision and administration cost $56,091. Existing 
project is complete except for the inactive portion. 
Nineteen original locks and nine original dams have 
been rebuilt. (See Table 31-E for year of completion of 
each.) Structures and dredging in pools have increased 
original depths generally about 2 feet. Work remaining 
to complete project consists of dredging in upper 
portion of Wolf River, and rock removal and deepening 
of Neenah Channel on lower Fox River, which are no 
longer considered necessary. Existing lock and dams 
are in generally fair to good condition. Costs for existing 
project to end of FY were $3,753,334 for new work and 
$32,939,523 for operation and maintenance; a total of 
$36,692,857. Funds in the amount of $3,706,187 were 
expended between July 5, 1884, and June 30, 1935, on 
operation and care of works of improvement under 
provisions of permanent indefinite appropriation for 
such purposes. 
16. FRANKFORT HARBOR, MI 
Location. On east shore of Lake Michigan, 204 
miles northeasterly from Chicago, IL, and 28 miles 
northerly from Manistee, MI. (See NOAA Nautical 
Chart 14907). 
Existing project. Provides for constructing an 
exterior basin in Lake Michigan formed by two 
breakwaters, 450 feet apart at the outer ends, diverging 
at an angle of about 90 degrees, the main arm and shore 
connection on north breakwater are 972 and 1,000 feet 
long, respectively, and the main arm and shore connection 
of south breakwater 1,188 and 1,400 feet long, 
respectively; for removing 801 feet of north and 1,172 
feet of south pier; dredging basin 20 feet deep and 800 
feet wide at entrance, decreasing toward new pier 
heads to 600 feet wide, dredging approach and entrance 
channel through outer basin to a depth of 24 feet from 
deep water in Lake Michigan to a point 500 feet 
landward of opening between breakwaters, over the 
entire width outside the breakwaters and to a maximum 
width of 500 feet inside the breakwaters; thence to 
23 feet deep through inner portion of outer basin to 
outer end of north pier, over widths decreasing from 
500 to 160 feet; and thence to 22 feet deep between the 
piers to the inner basin in Lake Betsie; dredging an 
18-foot deep interior basin in Lake Betsie from within 
50 feet of existing structures on the west and extending 
eastward about 1,550 feet to easterly boundary and 
from within 50 feet of existing structures on the north 
and extending southward 800 feet to the southerly 
boundary; dredging a recreational craft anchorage 
area 10 feet deep and 300 feet wide, extending 600 feet 
eastward of the east limit of the interior basin, with its 
north side in line with the north limit of the basin. 
Breakwaters and shore connections are built of concrete 
caissons and piling capped with concrete. Inner 
piers and revetments are built of stonefilled timber 
cribs and piling, all capped with concrete, except for 
476 feet of south revetment which consists of steel sheet 
piling. (See Table 31-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Two car ferry slips on south 
shore and several docks along north shore of Lake 
Betsie. The City and State provide a recreational 
docking facility on north side of Lake Betsie which is 
31-8

DETROIT, MICHIGAN DISTRICT 
open to all on equal terms. There is also a marine 
railway capable of handling small craft. Facilities are 
considered adequate for existing commerce. 
Operations during fiscal year. Maintenance: Condition 
surveys, operation of safety features, environmental 
studies, miscellaneous inspections and reports 
were performed by Government forces at a cost of 
$28,917. The contract awarded last FY for rehabilitation 
of N. Pier and S. Pier and Revetment Sections K, 
K-1, L-1, M-1, N, O and P was completed at a cost of 
$891,895. An adjustment of $-8,802 was made in 
contract dredging performed last FY. Maintenance of 
safety features was performed at a cost of $4,904. 
Engineering, design, surveys, supervision and administration 
cost $72,319. The contract for construction of 
confined disposal area was completed. Cost this FY was 
$47,578 for contract and $35,372 for engineering and 
design during construction and supervision and administration. 
Existing project was completed in 1939, with exception 
of the latest modification which was completed in 
1969. Navigation structures are in good condition and 
programmed for major repair on an as needed basis. 
For additional details on completion of existing project 
see page 1474 of Annual Report for 1962. Total costs for 
existing project to end of FY were $9,218,786, of which 
$1,955,159 (including $31,709 contributed funds) was 
for new work, $6,988,801 for maintenance, and 
$274,776 for rehabilitation. 
17. GRAND HAVEN HARBOR AND 
GRAND RIVER, MI 
Location. Harbor is on east shore of Lake Michigan, 
108 miles northeasterly from Chicago, IL, and 23 
miles northerly from Holland, MI. River rises in 
Jackson County, MI, and flows 260 miles westerly into 
Lake Michigan. (See NOAA Nautical Chart 14933, and 
Geological Survey Grand Rapids quadrangle.) 
Previous project. For details see page 1949 of 
Annual Report for 1915, and page 1481 of Annual 
Report for 1938. 
Existing project. An entrance channel protected 
by parallel piers and revetments at mouth of Grand 
River, a deep draft channel in river extending to Spring 
Lake, a turning basin, and a shallow draft channel in 
river extending 14.5 miles upstream to Bass River. 
Project depths are 23 feet in entrance channel, 21 feet in 
river to turning basin, 18 feet in turning basin and 
channel to Spring Lake, and 8 feet in upper Grand 
River channel. For additional details see page 1461 of 
Annual Report for 1962. Dredging on northerly side of 
inner channel is considered inactive. Estimated cost of 
this portion (1954) is $38,600. (See Table 31-B for 
authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Several wharves exist for 
handling coal, limestone, sand and gravel, petroleum 
products, fish and miscellaneous commodities. There is 
also a car ferry slip which is inactive. The State and 
local agencies provide recreational boating facilities 
which are open to all on equal terms. Facilities are 
considered adequate for existing commerce. 
Operations during fiscal year. Maintenance: Condition 
surveys, environmental studies, miscellaneous 
inspections and reports were performed by Government 
forces at a cost of $86,560. Repair to North and 
South Pier and North and South Revetment was 
performed by hired labor at a cost of $91,538. The U.S. 
Hopper Dredge HAINS performed maintenance dredging 
removing 60,580 cubic yards, bin measure, of shoal 
material at a cost of $148,442. Maintenance of disposal 
area cost $2,566. A contract was awarded for repair of 
North Revetment Sections C-1 and D, South Revetment 
Sections L, M, N, O and P, in the amount of $3,536,365. 
The contract is approximately 11 percent complete at a 
cost of $389,000. Engineering and design cost in 
connection with this contract was $257,943. Engineering 
and design of all other work, surveys, supervision 
and administration cost $48,125. A contract was 
awarded and completed for placing 21,000 cubic yards 
of sand in connection with Section 111. Cost for 
mitigation under Section 111 of P.L. 90-483 was 
$139,860. 
Existing project was substantially completed in 1949. 
For additional details on completion of existing project 
see page 1463 of Annual Report for 1962. Structures are 
generally in good condition; repairs are made on an as 
needed basis. Total costs of existing project to end of FY 
were $18,013,481, of which $1,458,469 was for new 
work, $15,741,399 for maintenance, and $813,613 for 
rehabilitation. 
18. GRAND MARAIS HARBOR, MN 
Location. On north shore of Lake Superior, 106 
miles northeasterly from Duluth, MN. (See NOAA 
Nautical Chart 14967.) 
Existing project. Provides breakwater piers to 
narrow the entrance; concrete seawalls across ledge at 
southeast corner of harbor; an anchorage area and a 
small-boat basin protected by a rubblemound breakwater. 
Project depths are 16 feet in anchorage area 
increasing to 20 feet near entrance and 8 feet in smallboat 
basin. For additional details see page 1014 of 
Annual Report for 1965. (See Table 31-B for authorizing 
legislation.){ 
Local cooperation. Fully complied with. 
Terminal facilities. Two inactive pulpwood 
wharves and several fish wharves, all privately owned. 
Facilities are considered adequate for existing commerce. 
Operations during fiscal year. Maintenance: Condition 
surveys, miscellaneous inspections and reports 
were performed at a cost of $19,174. Existing project is 
31-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
complete. Concrete seawall and both breakwaters are 
in good condition. Total costs of existing project to end of 
FY were $1,029,115. 
19. GRAND TRAVERSE BAY 
HARBOR, MI 
Location. At mouth of Traverse River on eastern 
shore of Keweenaw Peninsula about 20 miles northeasterly 
from Portage entry to Keweenaw Waterway. 
(See NOAA Nautical Chart 14964.) 
Existing projects: Provides two parallel piers, an 
entrance channel between piers and a harbor basin. 
Project depths are 12 feet between piers and 10 feet in 
basin. Project area extended 200 feet upstream in 1966. 
For additional details see page 1015 of Annual Report 
for 1965. (See Table 31-B for authorizing legislation.) 
Local cooperation. Fully complied with. Local 
interests furnished easements on 5.1 acres of land. 
Terminal facilities. Several privately owned fishing 
wharves. Facilities are considered adequate for 
existing commerce. 
Operations during fiscal year.. New Work: Plans 
and specifications were initiated on the authorized 
Section 111 project, at a cost of $4,848. Maintenance: 
Condition surveys, environmental studies, miscellaneous 
inspections and reports were performed by Government 
forces at a cost of $17,137. A contract in the 
amount of $158,725 was awarded for repair of South 
Revetment Section E. Approximately 2 percent of the 
work has been completed at a cost of $3,175. The 
maintenance dredging contract awarded last FY was 
completed. Approximately 4,072 cubic yards, place 
measule, of shoal material was removed. An adjustment 
of $-21,478 was made in contract dredging cost 
reported last FY. Engineering and design for Section E 
was completed at a cost of $38,719. Supervision and 
administration cost $14,485. 
Existing project was completed in 1950 except for 
extension of north pier completed in 1964. Steel cells 
and piers are in good condition. Timber and round 
wood-pile structures are deteriorated but still in 
serviceable condition. Total cost of existing project to 
end of FY was $1,568,080. 
20. GREEN BAY HARBOR, WI 
Location. At mouth of Fox River, at head of Green 
Bay, about 180 miles from Milwaukee, WI, via Sturgeon 
Bay Canal, and about 49 miles southwest of 
Menominee Harbor, MI, and WI. (See NOAA Nautical 
Chart 14918.) 
Previous projects. See page 1366 of Annual Report 
for 1962. 
Existing project. See Chicago District 1979 Annual 
Report, Table 30-C, p. 30-30. 
For more detailed description of project see page 
1216 of Annual Report for 1963. 
Cost of completed portion of project is $9,334,421, 
Federal, and non-Federal cost is $490,000 including 
$100,000 contributed funds. Local interests requested 
that the inactive portion of the 1962 River and Harbor 
Act, consisting of dredging the reach from 150 feet 
downstream of the C.&N.W. Railway Bridge to 1,700 
feet upstream of this bridge, be reactivated and the 
authorization modified to include deepening the adjacent 
turning basin and modifying the C.&N.W. 
Railway Bridge to provide increased horizontal clearance. 
(See Table 31-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. There are 16 wharves for 
handling coal, petroleum products, cement, limestone, 
general overseas cargo and miscelleneous commodities. 
Facilities are considered adequate for existing commerce. 
Operations during fiscal year. New Work: Engineering 
and design work on the reactivated portion of 
the 1962 modification was initiated at a cost of $78,574. 
Maintenance: Condition surveys, environmental study, 
support of Water Control Center, miscellaneous inspections 
and reports were performed by Government 
forces at a cost of $203,279. The U.S. Hopper Dredge 
MARKHAM performed maintenance dredging twice 
in project this FY. Approximately 273,606 cubic yards, 
bin measure, of shoal material was removed at a cost of 
$427,464. Additional handling of dredge material cost 
$36,123. Maintenance of disposal area was performed 
at a cost of $154,850. The contract awarded last FY for 
maintenance dredging was completed at a cost of 
$970,825. Approximately 177,831 cubic yards of shoal 
material was removed. Engineering, design, surveys, 
supervision and administration cost $111,585. Engineering 
and design for confined disposal area was 
continued at a cost of $101,122. 
Existing project is complete. The 1962 modification 
was started in November 1966 and completed in 
September 1973. Dredging turning basin above Chicago 
& Northwestern Railways Bridge was commenced 
in August 1938. The turning basin was enlarged under 
authority of Section 5 of the River and Harbor Act of 
March 4,1915, in order to provide sufficient area for the 
large ships that use it. The work was performed as part 
of a maintenance dredging contract in September and 
October 1973. East revetment at Grassy Island was 
entirely removed in July 1935. Dredging Fox River and 
entrance channel to Tail Point Light was completed in 
September 1967. The total costs of the existing project 
were $27,720,755, of which $18,005,884 were regular 
funds and $940,800 Public Works funds; $10,016,806 
for new work and $17,703,949 for maintenance. The 
new work costs do not include $100,000 contributed 
funds. 
31-10

DETROIT, MICHIGAN DISTRICT 
21. HAMMOND BAY HARBOR, MI 
Location. On northwest shore of Lake Huron, 35 
miles southeast of Straits of Mackinac. (See NOAA 
Nautical Chart 14881.) 
Existing project. Provides for a harbor of refuge, 
protected by breakwater structures, extending to 12- 
foot depth contour in the lake; for dredging a harbor 
basin 10 feet deep; and for dredging an entrance 
channel 12 feet deep. 
Local cooperation. Fully complied with. 
Terminal facilities. Public facilities being planned 
by State and local agencies. Plans and specifications are 
complete, but construction has not started. 
Operations during fiscal year. New Work: An 
adjustment of $10,243 was made in cost for beach 
nourishment performed last FY. Maintenance: Condition 
surveys, miscellaneous inspections and reports 
were performed at a cost of $1,467. The contract 
awarded last FY for stone placement and restoration of 
the east breakwater was completed at a cost of $39,125. 
Engineering, supervision and administration cost 
$10,599. The existing project was completed in 1965. 
Total costs of existing project to end of FY were 
$1,442,184, of which $1,089,122 was for new work and 
$353,062 for maintenance. 
22. HARBOR BEACH HARBOR, MI 
Location. On west shore of Lake Huron about 60 
miles north of Port Huron, MI. (See NOAA Nautical 
Chart 14862.) 
Existing project. Harbor of refuge protected by 
three breakwaters; a main entrance 23 feet deep; and an 
anchorage area 21 feet deep. For additional details see 
page 1485 of Annual Report for 1962. (See Table 31-B 
for authorizing legislation.) 
Local cooperation. None required. 
Terminal facilities. Coal and limestone are received 
at a private wharf. In addition, there is a public 
recreational craft pier, a Coast Guard pier, and several 
small installations engaged in docking and servicing 
light-draft commercial and recreational vessels. These 
facilities satisfy current commerce and traffic requirements. 
Operations during fiscal year. Maintenance: Condition 
surveys, miscellaneous inspections and reports 
were performed at a cost of $18,127. A contract was 
awarded in the amount of $42,500 for repair of concrete 
cap on the North Breakwater. The contract is approximately 
18 percent complete at a cost of $7,650. Engineering 
and design for repair of North Breakwater was 
completed at a cost of $41,578. A reconnaissance report 
for major rehabilitation of Main Breakwater was 
initiated at a cost of $3,689. Supervision and administration 
cost $2,747. 
Existing project was completed in 1928. For additional 
details on completion of existing project see page 
1485 of Annual Report for 1962. Total costs to end of FY 
were $6,715,183, of which $1,200,598 was for new work, 
$5,320,081 for maintenance, and $194,504 for rehabilitation. 
23. HARRISVILLE HARBOR, MI 
Location. On the west shore of Lake Huron, 20 
miles north of Oscoda and 30 miles south of Alpena. (See 
NOAA Nautical Chart 14864.) 
Existing project. A harbor of refuge protected by 
breakwater structures, and dredging an entrance 
channel 12 feet deep and a harbor basin 10 feet deep. 
(See Table 31-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Dockage facilities built by 
State and local agencies for recreational craft; considered 
adequate for existing commerce. 
Operations during fiscal year. New Work. Engineering 
and design for construction of small-boat 
harbor was completed at a cost of $17,632. A contract 
was awarded in the amount of $719,700 for construction 
of a small-boat harbor. The contract covers extensions 
to the north and south breakwaters and includes 
navigation light work for the U.S. Coast Guard. The 
Michigan Department of Natural Resources has provided 
contributed funds for the project, ($250,000.00). 
No work was performed this FY. Supervision and 
administration cost $3,794. Engineering and design for 
beach nourishment was completed at a cost of $29,041. 
A contract in the amount of $379,022 was awarded for 
construction of the authorized Section 111 beach 
nourishment project. The contract is approximately 26 
percent complete at a cost of $115,192. Supervision and 
administration cost $7,896. 
Maintenance: Condition surveys, environmental 
studies, miscellaneous inspection and reports were 
performed by Government forces at a cost of $10,089. A 
contract was awarded and completed for maintenance 
dredging at a cost of $98,225. Approximately 23,300 
cubic yards of shoal material was removed. Engineering, 
design, surveys, supervision and administration 
cost $23,410. The existing project was completed in 
1960. Controlling depths are 12 feet in the entrance 
channel and 10 feet in the harbor basin. Total costs of 
project to end of FY were $2,594,075, of which 
$1,854,251 was for new work (includes $3,794 contributed 
funds) and $739,824 for maintenance. 
24. HOLLAND HARBOR, MI 
Location. On east shore of Lake Michigan 95 miles 
northeasterly from Chicago, IL, and 23 miles southerly 
from Grand Haven, MI. (See NOAA Nautical chart 
14932.) 
31-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1988 
Previous project. For details see page 1948 of 
Annual Report for 1915 and page 1478 of Annual 
Report for 1938. 
Existing project. An outer breakwater protected 
approach channel in Lake Michigan, an entrance 
channel to Lake Macatawa protected by piers and 
revetments, a channel through Lake Macatawa into 
Black River, and a turning basin. Project depths are 28 
feet in outer portion of approach channel decreasing to 
21 feet at outer end of inner piers, 21 feet to upper end of 
project, and 18 feet in turning basin. For additional 
details see page 1458 of Annual Report for 1962. 
Widening bend of entrance channel into Lake Macatawa 
is in an active category as a result of a reclassification 
recommendation approved by the Office of the 
Chief of Engineers on August 20,1981. Estimated cost 
of this portion (1982) is $3,180,000 Federal and $90,000 
non-Federal. (See Table 31-B for authorizing legislation.) 
Local cooperation. Fully complied with for completed 
portions of project. Work authorized by Act of 
1954 is subject to condition that work on either or both 
proposed modifications may be undertaken by the 
United States provided local interests furnish all lands 
except 1.5 acres of Federal lands, easements, rights-ofway, 
and suitable spoil disposal areas for initial work 
and future maintenance; remove buildings and other 
structures, except existing revetments, from lands to be 
furnished; and hold the United States free from 
damages. 
Terminal facilities. Wharves are at inner end of 
Lake Macatawa, and used for handling coal, building 
materials, petroleum products, and miscellaneous 
commodities. Two shipbuilding yards are on south 
shore of the lake. Holland provides a public wharf for 
small craft. Facilities are considered adequate for 
existing commerce. 
Operations during fiscal year. Maintenance: Condition 
surveys, environmental studies, operation of 
safety features, miscellaneous inspections and reports 
were performed by Government forces at a cost of 
$81,851. An adjustment of $78,889 was made for repair 
to breakwater accomplished last FY. The breakwater 
was damaged by private vessels, several years ago. The 
breakwater was repaired by contract and the costs were 
billed to the companies involved. However, $78,889 was 
in dispute. The case went to court and this amount was 
disallowed; consequently, it was charged to the 
Government. Repairs to the North and South Revetment 
were performed by the crane barge MANITOWOC 
at a cost of $31,982. The U.S. Hopper Dredge 
HAINS performed maintenance dredging removing 
79,000 cubic yards, bin measure, of shoal material at a 
cost of $191,994. Maintenance of confined disposal area 
was performed by hired labor at a cost of $14,487. A 
contract was awarded in the amount of $3,290,888 for 
repair of North Breakwater Section B, North Pier 
Connection, Section Q, and South Breakwater Sections 
A and B. The work is approximately 54 percent 
complete at a cost of $1,73388,88337. A contract was 
awarded and completed for construction of drainage 
trenches at Riverview Dike Disposal Site at a cost of 
$88,114. Engineering, design, surveys, supervision and 
administration cost $154,578. Surveys, environmental 
studies, and miscellaneous inspections in connection 
with Section 111 mitigation of shore damage cost 
$36,665. 
Existing project, with exception of widening bend in 
revetted entrance channel authorized by Act of September 
8, 1954, was completed in 1957. For additional 
details on completion of existing project, see page 1460 
of Annual Report for 1962. Costs of existing project to 
end of FY were $1,392,841 for new work ($1,180,502 
regular funds, $176,620 for previous project and 
$35,705 contributed funds), $10,909,244 regular funds 
for maintenance, and $502,452 regular funds for 
rehabilitation, for a total of $12,804,537. 
THE INLAND ROUTE, MI 
Location. A series of interconnected lakes and 
streams stretching across northern tip of Lower Peninsula 
of Michigan, and extends from Conway near Lake 
Michigan to Cheboygan on Lake Huron; a distance of 35 
miles. Crooked and Indian Rivers are connecting 
channels in the waterway. (See NOAA Nautical Chart 
14886.) 
Existing project. Provides for a channel 30 feet 
wide and 5 feet deep, with necessary widening at bends, 
through Crooked and Indian Rivers, and Crooked, Burt, 
and Mullett Lakes, and from Conway (west end of 
Crooked Lake) to navigation lock at Cheboygan; in 
Pickerel Channel from Pickerel Lake to Crooked Lake. 
It also provides for suitable jetties at head of Indian 
River. The addition of a lock and dam was approved by 
the Chief of Engineers on September 2, 1964, to correct 
a design deficiency. (See Table 31-B for authorizing 
legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. None exist for commercial 
cargo-handling along the Crooked and Indian Rivers. 
Numerous small privately owned timber piers and 
wharves, some equipped with covered boat wells for 
serving and storing recreational craft, have been 
constructed. Landings maintained by hotel and resort 
operators are open to the public for transfer of passengers. 
Public docks are at Conway and Oden on 
Crooked Lake; the Village of Indian River, Topinabee, 
and Mullett Lake Village on Mullett Lake; and at 
Cheboygan. About 30 highways dead end at the water's 
edge, permitting public access for various marine 
activities. Dock facilities are considered adequate for 
existing traffic. 
31-12
25.

DETROIT, MICHIGAN DISTRICT 
Operations during fiscal year. Maintenance: The 
navigation lock was maintained and operated on a 2- 
shift basis from October 1, 1982 to November 15, 1982. 
The lock was operated on a reduced schedule for the 
1983 season. The lock was open on weekends only from 
April 30 through May 8,1983 on a 1-shift basis and daily 
from May 14 to September 30, 1983, on a 2-shift basis. 
The State of Michigan operated and maintained the 
lock at a cost of $81,505. (U.S. Government funds). 
Conditionsurveys, cooperativestreamgaging, miscellaneous 
inspections and reports were performed by hired labor 
at a cost of $54,510. A contract for maintenance 
dredging was awarded and completed this FY at a cost 
of $139,810. Approximately 6,152 cubic yards, place 
measure, of shoal material was removed by clamshell 
dredge. An adjustment of $-1,499 was made in contract 
completed last FY for maintenance dredging. Engineering, 
design, supervision and administration cost 
$74,692. An adjustment of $-424 was made in contract 
completed last FY for construction of confined disposal 
area. Supervision and administration of contract closeout 
cost $5,754. 
The existing project was completed in 1958. The lock 
and dam was completed in FY 1968. For additional 
details see page 1382 of Annual Report for 1960. Total 
costs at end of FY were $3,360,033, of which $770,222 
was for new work and $2,441,811 for maintenance with 
$148,000 contributed by local interests. 
26. KENOSHA HARBOR, WI 
Location. On west shore of Lake Michigan about 35 
miles south of Milwaukee and about 54 miles north of 
Chicago. (See NOAA Nautical Chart 14904.) 
Previous projects. See page 1390 of Annual Report 
for 1962. 
Existing project. For detailed description see page 
1237, Annual Report for 1963. Estimated (1982) Federal 
cost is $673,000 exclusive of amounts expended on 
previous projects and $43,000 non-Federal which 
includes $3,000 local contribution. (See Table 31-B for 
authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Three wharves used for miscellaneous 
foreign overseas commodities and autos, and 
also several fishing wharves. While these facilities are 
considered generally adequate for existing commerce, 
more efficient use of existing terminals and utilization 
of available frontage for development of additional 
terminals should be made. 
Operations during fiscal year. Maintenance: Condition 
surveys, environmental studies, miscellaneous 
inspections and reports were performed by Government 
forces at a cost of $13,302. Repair to navigation 
structures was performed by hired labor at a cost of 
$38,039. Minor repair to the dike disposal area was 
accomplished at a cost of $23,280. Engineering, supervision 
and administration cost $5,174. 
Existing project is complete except for dredging 25- 
foot strips adjacent to the north and south piers which 
will be completed after rehabilitation of the piers. The 
north and south piers were completed in 1900 and the 
breakwater in 1909. The north pier is in excellent 
condition. The south pier and breakwater are in 
generally good condition. The total costs of the existing 
project to end of FY were $8,399,317, of which 
$7,907,899 were regular funds and $27,658 Emergency 
Relief funds; $480,597 being for new work, $6,620,787 
for maintenance, and $1,270,275 for rehabilitation. The 
new work costs do not include $3,000 contributed funds. 
27. KEWAUNEE HARBOR, WI 
Location. On west shore of Lake Michigan, about 
105 miles north of Milwaukee, WI, and about 78 miles 
from Green Bay, via Sturgeon Bay Canal. Harbor is at 
mouth of Kewaunee River. (See NOAA Nautical Chart 
14903.) 
Previous projects. See page 1375 of Annual Report 
for 1962. 
Existing project. See Chicago District 1979 Annual 
Report, Table 30-C, p. 30-31. 
Costs of completed project are $603,021, Federal, and 
$9,000 non-Federal, exclusive of amount expended op 
previous projects. Uncompleted portion (estimate 
$200,000-July 1965) of 1935 River and Harbor Act is 
considered inactive, and excluded from present cost 
estimate. The portion authorized by the 1960 River and 
Harbor Act was deauthorized in 1977. (See Table 31-B 
for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Two car-ferry slips, a petroleum 
tank farm, a Corps of Engineers project office, 
and several fishing wharves. Facilities are considered 
adequate for existing commerce. 
Operations during fiscal year. Maintenance: Condition 
surveys, environmental studies, miscellaneous 
inspections and reports were performed by hired labor 
at a cost of $32,087. The U.S. Hopper Dredge HAINS 
performed maintenance dredging removing 83,122 
cubic yards, bin measure, of shoal material at a cost of 
$249,622. Repair to dike disposal area was performed at 
a cost of $82,168. An adjustment of $-11,058 was made 
in HAINS dredging cost performed last FY. A contract 
was awarded and completed for maintenance dredging. 
Approximately 88,137 cubic yards, place measure, was 
removed by hydraulic dredge at a cost of $218,070. 
Engineering, design, surveys, supervision and administration 
cost $36,130. An adjustment of $747 was made 
in cost for dike disposal program. 
Active portion of existing project is complete. The 
north pier was completed in 1897 and the remaining 
portion is in generally good condition. Rehabilitation of 
31-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
the south pier was completed in June 1967. Construction 
of north breakwater and shore connection, except 
for a gap of 150 feet about 830 feet from shoreward end, 
and removal of outer 706.5 linear feet of north pier was 
commenced in September 1935 and completed in June 
1937. Removed 500 linear feet of north pier in April/ 
May 1963 and widened and deepened the adjacent 
channel in 1965. Outer end of the north pier was struck 
and severely damaged by car ferry vessel in October 
1973 and a 24-foot section at outer end was subsequently 
removed, thus reducing the structure to a length of 626 
feet. Dredging entrance channel in interior basin to 
existing project depth was commenced in April and 
completed in October 1938. Kewaunee River is navigable 
to about 6.5 miles above mouth for craft drawing not 
more than 4 feet. Total cost of existing project to end of 
FY was $7,022,387, of which $752,333 was for new work 
($183,021 regular and $420,000 Emergency Relief 
funds) $5,652,754 regular funds for maintenance, and 
$617,300 regular funds for rehabilitation. 
28. KEWEENAW WATERWAY, MI 
Location. In Lake Superior across Keweenaw Peninsula 
in upper peninsula of Michigan. The west 
entrance is 169 miles east of Duluth, MN. (See NOAA 
Nautical Chart 14972.) 
Existing project. A navigable channel, minimum 
width 300 feet, 25 miles long, partially natural and 
partially artificial, across Keweenaw Peninsula via 
Portage Lake. For details see page 1121 of Annual 
Report for 1963. Completed cost for new work is 
$5,967,700. Portion of project providing for extension of 
lower entrance breakwater and necessary alteration or 
replacement of structures due to deepening channels is 
inactive and excluded from foregoing cost. Estimated 
cost (1957) of this portion was $3,315,000. (See Table 
31-B for authorizing legislation.) 
Local cooperation. None required. 
Terminal facilities. Six coal docks, a petroleum 
dock, and several general merchandise and miscellaneous 
wharves, all privately owned. Facilities are 
considered adequate for existing commerce. Also 
present is a government constructed recreational area 
with facilities to include a picnic area and small boat 
landing range. 
Operations during fiscal year. Maintenance: Condition 
surveys, operation of safety features, miscellaneous 
inspections and reports were performed by 
Government forces at a cost of $5,987. Boundary 
monumentation was performed by hired labor and 
contract at a cost of $21,137. A reconnaissance report 
for major rehabilitation of Section F upper entry 
revetment was completed at a cost of $13,070. Repairs to 
Section F and Lily Pond were performed by hired labor 
at a cost of $354,323. An adjustment of $-68,861 was 
made in rock stock pile. Engineering, design, supervision 
and administration cost $20,031. Engineering 
and design for confined disposal area continued at a cost 
of $78,172. 
Active portion of the project is complete. Breakwaters 
are in generally good condition except for a 
weakness occurring in about 300 feet of substructure of 
breakwater lower entrance, and major storm damage 
repairs needed for stone-covered portions of breakwater 
at upper entrance. Mooring pier at Lily Pond 
requires repairs to halt movement and permit dredging 
to project depth adjacent thereto. The flared revetment 
at the upper entry should be modified to restrict wave 
action from the stilling basin entrance. Total costs of 
existing project to end of FY were $16,144,660, of which 
$5,974,141 was for new work, and $10,170,519 for 
maintenance. 
29. KNIFE RIVER HARBOR, MN 
Location. Near mouth of Knife River on north 
shore of Lake Superior, 19 miles northeasterly from 
Duluth, MN, and 7 miles southwest of Two Harbors, 
MN. (See NOAA Nautical Chart 14966.) 
Existing project. Provides for an entrance channel 
with a system of overlapping breakwaters, using the 
existing breakwater and a new breakwater constructed 
of 731 feet of rock rubblemound. The entrance channel 
is 9 feet deep and an inner straight channel is 8 feet 
deep, 50 feet wide, and 600 feet long with a public 
marina and side channel at its inner end. For additional 
details see page 1110 of Annual Report for 1963. A 
modification to correct a design deficiency was authorized 
in 1974. (See Table 31-B for authorizing legislation.) 
Total estimated approved Federal cost (1982) is 
$1,901,700 and $21,700 non-Federal cost. 
Local cooperation. Local interests are to furnish 
easements on 15.08 acres of land. 
Terminal facilities. Local interests have installed 
pile-and-timber docks on both sides of straight channel. 
Lake County has completed construction by contract of 
a marina along the east wing of the inner harbor. 
Operations during fiscal year. Maintenance: Condition 
surveys, miscellaneous inspections and reports 
were performed by Government forces at a cost of 
$23,808. 
Project was completed in June 1958. Breakwater and 
spending beach are in good condition. The existing 
breakwater does not effectively prevent waves caused 
by northeasterly winds from entering the entrance 
channel. This results in unsatisfactory and unsafe 
harbor entrance conditions during storms. Mooring 
conditions in the main channel and Y-branches of the 
inner harbor are also adversely affected. Plans and 
specifications for the construction of a breakwater to 
correct a design deficiency to reduce wave damage and 
improve navigation conditions were completed and 
31-14

DETROIT, MICHIGAN DISTRICT 
approved by NCD in 1982. Total project costs to end of 
FY were $661,381, of which $412,944 was for new work 
and $248,437 for maintenance. 
30. LAC LA BELLE HARBOR, MI 
Location. On south shore of Lake Superior on 
eastern shore of Keweenaw Peninsula, 41 miles northeasterly 
from Portage entry to Keweenaw Waterway. 
Lac La Belle, Bete Grise Bay, and Mendota Ship Canal 
combine to form the harbor. (See NOAA Nautical 
Chart 14964.) 
Existing project. Provides for construction of two 
parallel piers at the entrance having lengths of 584 and 
682 feet for north and south piers, respectively; for an 
entrance channel between the piers 50 feet wide and 12 
feet deep, about 820 feet long with a flared approach; 
and for an inner canal 50 feet wide and 10 feet deep, 
about 730 feet long. For additional details see page 
1039, Annual Report for 1964. (See Table 31-B for 
authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Several small, privately owned 
wharves are available in the harbor for use of small 
craft engaged in fishing and recreational activities. A 
state owned dock for small craft is located at northwest 
corner of Lac La Belle Bay. 
Operations during fiscal year. Maintenance: Condition 
surveys, environmental studies, miscellaneous 
inspections and reports were performed by hired labor 
at a cost of $2,590. The contract awarded last FY for 
maintenance dredging was completed. Approximately 
2,750 cubic yards, place measure, of shoal material was 
removed at a cost of $8,450. Repair to structures was 
performed at a cost of $39,493. Supervision and 
administration cost $2,961. An adjustment of $-2,749 
was made in environmental cost for last FY. The 
existing project was completed in 1960. Controlling 
depths are about 11 feet in the approach channel and 10 
feet in the inner channel. Total costs of existing project 
to end of FY were $532,131, of which $269,270 was for 
new work and $262,861 for maintenance. 
31. LAKE ST. CLAIR, MI CHANNELS 
Location. Lake St. Clair, a section of Great Lakes 
connecting channels, is an expansive shallow basin 
having a vessel track length of about 15 miles from 
mouth of St. Clair River to head of Detroit River. (See 
NOAA Nautical Chart 14850.) 
Previous project. For details see page 2882, Annual 
Report for 1896; pages 1957-58, Annual Report for 
1915; and page 1539, Annual Report for 1938. 
Existing project. An improved channel through 
Lake St. Clair 800 feet wide, 27.5 feet deep, and about 
14.5 miles long; extending from mouth of Southeast 
Bend cutoff channel at lower end of St. Clair River to 
head of Detroit River Channel. (See Table 31-B for 
authorizing legislation.) 
Local cooperation. None required. 
Terminal facilities. None. 
Operations during fiscal year. Maintenance: Condition 
surveys, environmental studies, support of Water 
Control Center, miscellaneous inspections and reports 
were performed at a cost of $161,737. Environmental 
studies in connection with the extended navigation 
season cost $129,384. Maintenance of disposal area was 
performed at a cost of $32,840. Total costs for existing 
project at end of FY were $18,602,237, of which 
$7,675,357 was for new work ($6,010,582 regular funds 
and $1,008,595 public works funds) and $10,926,880 for 
maintenance. 
32. LELAND HARBOR, MI 
Location. A light-draft harbor on eastern shore of 
Lake Michigan at mouth of Carp River, about 40 miles 
north of Frankfort, MI, and 40 miles southwest of 
Charlevoix, MI. (See NOAA Nautical Chart 14912.) 
Existing project. Provides for a harbor of refuge 
consisting of a breakwater about 1,200 feet long, a 
protected anchorage and maneuver area about 3 acres 
in extent and 10 feet deep, a 12-foot deep flared 
approach channel decreasing in width to 90 feet, an 
existing south pier 440 feet long, a 35-foot long cellular 
extension to south pier, an entrance channel 6 feet deep 
and 40 feet wide extending to mouth of Carp River, and 
for elimination of existing north pier. (See Table 31-B 
for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Privately owned wharves on 
each side of river below the dam which is 400 feet above 
the river mouth. These wharves serve the local fishing 
interests and recreational craft. Public facilities are 
operated by the State and local agencies. All available 
dockage space is utilized. 
Operations during fiscal year. Maintenance: Condition 
surveys, environmental studies, miscellaneous 
inspections and reports were performed by Government 
forces at a cost of $18,387. An adjustment of -701 
cubic yards and $-699 was made in maintenance 
dredging contract completed last FY. A contract was 
awarded and completed for maintenance dredging. 
Approximately 12,686 cubic yards were removed at a 
cost of $72,077. Repair to North and South Pier was 
performed by hired labor at a cost of $66,447. Engineering, 
design, supervision and administration cost 
$20,875. The existing project was completed in 1932 
except for the 1962 authorization which was completed 
in 1967. The total costs to end of FY were $2,191,960, of 
which $1,027,089 was for new work, $1,094,193 for 
maintenance, and $70,678 for rehabilitation. 
33. LEXINGTON HARBOR, MI 
Location. On southwest shore of Lake Huron, 20 
31-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
miles north of Port Huron, MI. (See NOAA Nautical 
Chart 14862.) 
Existing project. Provides for two offshore breakwaters 
opening to the southeast and totaling about 2,400 
feet long with provisions for recreational fishing on the 
main breakwater; an anchorage and maneuver area of 
about 5 acres, 8 feet deep; and a flared approach 
channel 10 feet deep, decreasing to 160 feet in width 
through the breakwaters. Project also provides for 
recreational fishing facilities. Estimated (1979) Federal 
cost for new work is $1,647,306 excluding $1,088,888 
to be contributed by local interests. (See Table 31-B for 
authorizing legislation.) 
Local cooperation. Assurances of local cooperation 
were furnished by Michigan Department of Natural 
Resources to the Secretary of the Army. The cash 
contribution was $1,088,888. 
Terminal facilities. An existing public fishing pier 
of open pile construction is not adequate for existing 
and prospective commerce. Complete boating facilities 
are planned by State and local agencies in connection 
with the harbor construction. 
Operations during fiscal year. Maintenance: Condition 
surveys, environmental studies, miscellaneous 
inspections and reports were performed by Government 
forces at a cost of $16,867. Engineering and design 
for maintenance dredging cost $6,742. Supervision and 
administration cost $1,364. Maintenance of shore 
erosion mitigation under Section 111 initiated last FY 
was completed at a cost of $25,048. Engineering, 
design, surveys, monitoring, supervision and administration 
cost $19,527. The existing project was completed 
during FY 1977. Total costs of existing project to 
end of FY were $3,396,078, of which $3,107,192 
(includes $1,088,888 contributed funds) was for new 
work and $288,886 for maintenance. 
34. LITTLE LAKE HARBOR, MI 
Location. On south shore of Lake Superior 21 miles 
west of Whitefish Point and 30 miles east of Grand 
Marais, MI. (See NOAA Nautical Chart 14962.) 
Existing project. Provides for a small-craft harbor 
of refuge by dredging an entrance channel 12 feet deep 
from Lake Superior into Little Lake, suitably protected 
by breakwaters and revetments. (See Table 31-B for 
authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Only terminal facility at project 
site consists of a public dock built by State of 
Michigan for light-draft craft. 
Operations during fiscal year. Maintenance: Condition 
surveys, environmental studies, miscellaneous 
inspections and reports were performed by Government 
forces at a cost of $4,949. The design deficiency 
study was continued at a cost of $3,720. An adjustment 
of $-44,602 was made in cost for contract completed last 
FY for dredging. A contract was awarded and completed 
this FY for maintenance dredging. Approximately 
12,569 cubic yards, place measure, of shoal 
material was removed at a cost of $94,942. Claims are 
pending. Hired labor costs in connection with maintenance 
dredging were $14,384. Engineering, design, 
supervision and administration cost $33,482. 
This project is considered complete; however, because 
of shifting sand, the harbor entrance shoals 
rapidly with the result that full project depth is not 
usually available. An analysis for the Design Deficiency 
Report was submitted to North Central Division in 
March 1978 and approved. Total cost at end of FY is 
$2,689,152. 
35. LUDINGTON HARBOR, MI 
Location. On east shore of Lake Michigan, 156 
miles northeasterly from Chicago, IL, and 67 miles 
northerly from Grand Haven, MI. (See NOAA Nautical 
Chart 14937.) 
Previous project. For details see page 1951 of 
Annual Report for 1915, page 1491 of Annual Report for 
1938, and page 1307 of Annual Report for 1963. 
Existing project. Provides for an exterior basin in 
Lake Michigan protected by north and south breakwater, 
north breakwater is 1,800 feet long and south 
breakwater 1,700 feet long, 550 feet apart at outer ends, 
diverging at an angle of 90 degrees, with shore 
connections, 1,103 and 2,004 feet long, respectively; for 
dredging exterior basin to 18 feet deep with a maximum 
width of 1,500 feet; for a channel with a depth of 29 
feet from deep water in Lake Michigan decreasing to 27 
feet at the west end of the north pier, over a maximum 
width of 600 feet; thence a channel with a depth of 27 
feet, over a minimum width of 230 feet with necessary 
widening at Pere Marquette Lake; and for inner piers 
and revetments 1,649 feet long on north and sufficiently 
long on the south for turn at Pere Marquette Lake. The 
estimated (1977) Federal cost for new work is $8,250,000. 
Estimated total costs for local interests is $147,000. (See 
Table 31-B for authorizing legislation.) 
Local cooperation. Has been complied with. 
Terminal facilities. In addition to main terminal of 
Chesapeake & Ohio Railway Co., consisting of three car 
ferry slips, a wharf, and warehouses, there are several 
wharves which handle coal, limestone, and miscellaneous 
commodities. Facilities adequate for existing 
commerce. 
Operations during fiscal year. Maintenance: Condition 
surveys, environmental studies, operation of 
safety features, miscellaneous inspections and reports 
were performed by Government forces at a cost of 
$65,558. A study on wave monitoring was initiated at a 
cost of $36,308. The contract awarded last FY for 
31-16

DETROIT, MICHIGAN DISTRICT 
emergency repairs to south breakwater head was 
expanded due to damage caused by Lake Michigan 
storms. The contract was completed this FY at a cost of 
$438,682. Hired labor work in connection with contract 
cost $48,275. The U.S. Hopper Dredge HAINS performed 
maintenance dredging removing 24,623 cubic 
yards, bin measure, of shoal material at a cost of 
$89,083. Engineering, design, supervision and administration 
cost $53,860. Existing project was completed in 
1918. For additional details on completion of existing 
project see page 1469 of Annual Report for 1962. Total 
costs for existing project to end of FY were $15,979,840 
of which $8,582,202 was for new work, $7,089,725 for 
maintenance, and $857,918 for rehabilitation. 
36. MANISTEE HARBOR, MI 
Location. On east shore of Lake Michigan, 179 
miles northeasterly from Chicago, IL, and 26 miles 
northerly from Ludington, MI. (See NOAA Nautical 
Chart 14938.) 
Previous project. For details see page 1952 of 
Annual Report for 1915, and page 1493 of Annual 
Report for 1938. 
Existing project. An entrance channel in Lake 
Michigan protected by a breakwater, piers, and revetments;'
a channel in Manistee River to Manistee Lake; 
and Federal participation in cost of replacing Maple 
Street Bridge. Project depths are 25 feet in entrance 
channel and 23 feet in river channel. For additional 
details see page 1470 of Annual Report for 1962. (See 
Table 31-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Installations are on both sides 
of river and on Manistee Lake. Commerce handled 
includes coal, sand, salt, and general cargo. In addition, 
there is a Government wharf and a State and City 
owned recreational craft pier which is open to the 
public. These facilities satisfy current commerce requirements. 
Operations during fiscal year. Maintenance: Condition 
surveys, environmental studies, miscellaneous 
inspections and reports were performed by Government 
forces at a cost of $15,844. Repair to South Pier 
and North Revetment was performed by hired labor at 
a cost of $144,436. Engineering and design for repair of 
North Revetment Sections F, G & H was continued at a 
c$o6s,7t 4o9f. $28,875. Supervision and administration cost 
Existing project was completed in August 1967. For 
additional details on completion of existing project see 
page 1470 of Annual Report for 1962. Total costs for 
existing project from regular funds to end of FY were 
$7,903,119, of which $2,696,522 was for new work, 
$3,832,433 for maintenance, and $1,374,164 for rehabilitation. 
37. MANISTIQUE HARBOR, MI 
Location. On north shore of Lake Michigan, 135 
miles northeasterly from Green Bay Harbor, WI, and 
220 miles northerly from Milwaukee, WI. (See NOAA 
Nautical Chart 14908.) 
Previous project. For details see page 1933 of 
Annual Report for 1915, and page 1422 of Annual 
Report for 1938. 
Existing project. A breakwater protected entrance 
channel in Lake Michigan, a channel in Manistique 
River, and a pier at river mouth. Project depths are 19 
feet in outer portion of entrance channel, 18 feet in inner 
portion of entrance channel, and 18 feet in river 
channel. For additional details see page 1451 of Annual 
Report for 1962. (See Table 31-B for authorizing 
legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. A car ferry slip, two coal and 
building material wharves, two fishing wharves, and 
numerous lumberyard slips. Facilities are considered 
adequate for existing commerce. 
Operations during fiscal year. Maintenance: Condition 
surveys, miscellaneous inspections and reports 
were performed by hired labor at a cost of $53,919. 
Repair to Pier was performed by hired labor at a cost of 
$93,819.Total costs to end of FY were $3,467,549, of 
which $1,299,355 was for new work, $1,851,861 for 
maintenance and $316,333 for rehabilitation. 
38. MANITOWOC HARBOR, WI 
Location. On west shore of Lake Michigan about 79 
miles north of Milwaukee and about 106 miles from 
Green Bay via Sturgeon Bay Canal. (See NOAA 
Nautical Chart 14922.) 
Previous projects. See page 1379 of Annual Report 
for 1962. 
Existing project. The total estimated (Oct 1981) 
project cost is $3,080,000; the Federal cost is $1,085,000 
and the non-Federal cost is $1,995,000, which is a cash 
contribution. See Chicago District Annual Report for 
1979, Table 30-C. 
For detailed description see page 1228 of Annual 
Report for 1963. Estimated costs (1970) of new work for 
1968 modification are $81,000 Federal and $30,000 non- 
Federal which includes a cash contribution of $18,000. 
Work on the 1968 modification was postponed until 
1982. The portion authorized by the 1962 River and 
Harbor Act is inactive and estimated (1970) at $1,150,- 
000, Federal, and $105,000 non-Federal. (See Table 31- 
B for authorizing legislation.) 
Construction of a small boat harbor within the 
existing harbor was authorized by the Chief of Engi- 
31-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
neers, June 26, 1979, and 720-foot channel extension 
reaffirmed in July 1982, under authority of Section 107, 
1960 River and Harbor Act, as amended. 
Local cooperation. Fully complied with for complete 
modifications. For 1968 modification local interests 
must make an annual cash contribution equivalent 
to 50% of the annual costs associated with construction 
and maintenance of the channel extension until such 
time that a second user utilizes the channel extension. 
Such a contribution is presently estimated at $14,200; 
provide without cost to the United States all lands, 
easements, and rights-of-way required for construction 
and subsequent maintenance, including suitable areas 
determined by the Chief of Engineers to be required in 
the general public interest for initial and subsequent 
disposal of dredged materials, and the necessary 
retaining dikes, bulkheads, and embankments therefor 
or the costs of such retaining works; hold and save 
the United States free from damages due to the 
construction works and subsequent use, operation, and 
maintenance of the project, not including damages due 
to the fault or negligence of the United States or its 
contractors; provide and maintain without cost to the 
United States adequate berthing areas at the docks 
adjacent to the improvement; accomplish at no cost to 
the United States all relocations and alterations of 
utilities necessary for the project; assume full responsibility 
for all project first costs in excess of the Federal 
cost limitation of $2,000,000; and comply with the 
Uniform Relocation Assistance and Real Property 
Acquisition Policies Act of 1970. 
Terminal facilities. Three car-ferry slips, a grain 
elevator, one shipbuildingyard, and three other wharves 
used for handling coal, building materials, cement, and 
miscellaneous commodities. While these facilities are 
considered adequate for existing commerce, it is 
believed the City should provide a suitable wharf with 
warehouse and railway connection open to the general 
public. 
Operations during fiscal year. New Work: The 
contract for construction of a small boat harbor was 
completed at a cost of $950,645. Engineering, design, 
supervision and administration cost $77,145. Of the 
above cost, $799,140 was contributed funds. The contract 
awarded last FY for extension of channel was 
completed at a cost of $88,630. Approximately 13,569 
cubic yards of shoal material was removed. Engineering, 
supervision and administration cost $6,832. 
Maintenance: Condition surveys, environmental 
studies, miscellaneous inspections and reports were 
performed by Government forces at a cost of $48,690. 
Repair to structures was performed by Government 
forces at a cost of $6,078. Maintenance of disposal area 
was performed at a cost of $32,890. The U.S. Hopper 
HAINS performed maintenance dredging removing 
20,906 cubic yards, bin measure, of shoal material at a 
cost of $77,653. Engineering and design for repair of 
South Breakwater was completed at a cost of $107,868. 
A contract in the amount of $518,130 was awarded for 
this repair. No work was performed this FY. Supervision 
and administration of all work cost $24,758. 
Existing project is completed except for the 1962 and 
1968 modifications. The 1962 modification is inactive. 
Work on the 1968 modification was essentially completed 
in FY 83. The breakwater, completed in 1910, is 
in generally fair condition. Dredging a channel through 
outer basin to existing project depth and removal of a 
portion of old north stub pier at the river entrance were 
completed in December 1937. Dredging river channel 
was completed in July 1942. Cost of existing project was 
$3,958,988 for new work (includes $1,795,054 contributed 
funds) and $6,820,487 for maintenance, a total of 
$10,779,475. 
39. MARQUETTE HARBOR, MI 
Location. In Marquette Bay on south shore of Lake 
Superior, 160 miles west of Sault Ste. Marie, MI, and 
265 miles east from Duluth, MN. (See NOAA Nautical 
Chart 14970.) 
Existing project. Provides for a breakwater, and a 
harbor basin 26.5 feet deep, giving a protected area of 
350 acres. Project was modified in 1960 to provide a 
27-foot depth in harbor area. (See Table 31-B for 
authorizing legislation.) 
Local cooperation. None required for earlier authorizations. 
Fully complied with for the 1960 Act. 
Terminal facilities. One ore dock, unused at present; 
two coal docks; one petroleum dock; and three 
other unused docks. There are also several small fish 
wharves without railroad connections. Facilities are 
considered adequate for existing commerce. 
Operations during fiscal year. Condition surveys, 
miscellaneous inspections and reports were performed 
by Government forces at a cost of $987. Projects 
authorized by earlier Acts were completed in 1935. The 
1960 Act was completed in 1966. Rehabilitation of 
rubblemound portion of breakwater was completed in 
November 1965. Total cost of existing project to end of 
FY is $3,255,522. 
40. MENOMINEE HARBOR AND 
RIVER, MI AND WI 
Location. On west shore of Green Bay, about 49 
miles northeast of Green Bay Harbor, and about 155 
miles from Milwaukee via Sturgeon Bay Canal. (See 
NOAA Nautical Chart 14917.) 
Previous projects. See page 1361 of Annual Report 
for 1962. 
Existing project. See Chicago District Annual 
Report 1979, Table 30-C, page 30-26. 
For detailed description see page 1214, Annual 
Report for 1963. The portion authorized by 1960 River 
31-18

DETROIT, MICHIGAN DISTRICT 
and Harbor Act is inactive and estimated (1964) at 
$442,000, Federal, and $105,000 non-Federal. Costs of 
completed new work exclusive of inactive work and 
amount expended on previous projects are $221,053 
Federal and $50,762 non-Federal, which includes a 
cash contribution of $36,762. (See Table 31-B for 
authorizing legislation.) 
Local cooperation. Fully complied with for completed 
work. 
Terminal facilities. There are 9 wharves for handling 
coal, limestone, pulp and miscellaneous commodities. 
City of Marinette, WI, provided a public wharf. 
Facilities are considered fairly adequate for existing 
commerce, except that there is need for a public wharf 
owned by City of Menominee, with warehouse and 
railway connection. 
Operations during fiscal year. Maintenance: Condition 
surveys, environmental studies, miscellaneous 
inspections and reports were performed by Government 
forces at a cost of $7,410. An adjustment of $- 
10,551 was made in cost for maintenance dredging 
performed last FY. Engineering and design for repair 
of S. Pier, Section D was continued at a cost of $36,746. 
Engineering and design for confined disposal area for 
polluted dredge spoil was continued at a cost of $24,427. 
The project in effect prior to the modification of 
March 2, 1945 was completed in 1938. No additional 
work was necessary under the modification of March 2, 
1945 to provide a depth of 12 feet in the extension of the 
channel to the vicinity of the Marinette Yacht Club as 
project depth or more was available. The entrance piers 
were completed in 1884, were rehabilitated (1954-1964) 
and are in excellent condition. Dredging of the channel 
below the Marinette municipal wharf, together with 
enlarging the turning basin to existing project depth, 
was commenced in May 1938. Modification of the 
project authorized by the 1960 River and Harbor Act is 
inactive. Construction for the 1967 modifications was 
started August 17,1968 and completed in October 1968. 
The costs of the existing project were $537,148 for new 
work (includes $36,762 contributed funds), $1,952,544 
for maintenance and $1,351,852 for rehabilitation, a 
total of $3,841,544. 
41. MILWAUKEE HARBOR, WI 
Location. On west shore of Lake Michigan about85 
miles north of Chicago, IL, and about 83 miles west of 
Grand Haven, MI. (See NOAA Nautical Chart 14924.) 
Previous projects. See page 1385 of Annual Report 
for 1962. 
Existing project. See Chicago District Annual 
Report for 1979, Table 30-C, page 30-26. 
For detailed description see page 1232 of Annual 
Report for 1963. 
Completed new work costs are $6,937,804 Federal 
and $478,000 non-Federal, exclusive of amount expended 
on previous projects. The uncompleted portion 
authorized by the 1935 River and Harbor Act was 
placed in the inactive category in June 1973. Estimated 
costs are $119,000 (July 1972) Federal and $1,170,000 
(July 1972) non-Federal for this portion. Uncompleted 
portion 1945 River and Harbor Act was deauthorized in 
1977. (See Table 31-B for authorizing legislation.) 
Local cooperation. Complied with for Acts of 
March 2, 1945, October 23, 1962, and July 14, 1960, 
except inactive portion of 1945 Act. Act of August 30, 
1935, provided that original dredging of outer harbor 
area be done by City of Milwaukee and City of 
Milwaukee be reimbursed at actual cost but not to 
exceed 10 cents per cubic yard, place measurement, for 
original dredging done subsequent to authorization of 
work by Congress. Agreement covering dredging was 
executed by Secretary of Way, February 23,1934, after 
this work was originally authorized as part of public 
works program. City was reimbursed for 10 percent of 
dredging. 
Terminal facilities. Four car-ferry slips, and 57 
other wharves, private and municipal, used for handling 
coal, grain, building materials, cement, petroleum 
products, and miscellaneous commodities. As facilities 
in inner harbor were inadequate for existing commerce, 
Milwaukee Harbor Commission has constructed 
nine docks in the outer harbor for handling general 
cargo. 
Operations during fiscal year. Maintenance: Condition 
surveys, environmental studies, miscellaneous 
inspections and reports were performed by Government 
forces at a cost of $121,832. A reconnaissance 
report for major rehabilitation of Inner North Revetment 
and North Detached Breakwater was completed 
and a General Design Memorandum initiated at a cost 
of $6,856. Repairs to the South Breakwater were performed 
by hired labor at a cost of $77,457. Maintenance 
of disposal area was performed at a cost of $153,103. 
Engineering, design, surveys, supervision and administration 
cost $53,079. 
Existing project is complete except for inactive 
portions. The 1962 modification was completed in July 
1967. North breakwater and shore connection, 9,954 
feet long, was completed in August 1925. North pier 
was completed in 1905 and construction of south pier 
was completed in November 1910. Construction of 
south breakwater and shore connection was completed 
in October 1929. Before modification of August 30, 
1935, City of Milwaukee also dredged most of the area in 
the outer harbor south of inner entrance piers and 
lakeward of pierhead line to more than 21 feet below 
datum without cost to the United States. City of 
Milwaukee also dredged a portion of the area of the 
outer harbor north of inner entrance piers to provide an 
approach channel to the passenger and auto pier 
31-19

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1988 
opposite East Claybourn Street. Work on the 1945 
modification was completed in August 1957, except for 
inactive portion which consists of dredging the Milwaukee 
River from Buffalo Street to upper limit of the 
project at Humbolt Avenue. In recent years, some 
repairs were completed on the north shore breakwater; 
however, additional repairs are required. South breakwater 
and shore connections are in generally good 
condition. Costs of existing project were $8,231,024 for 
new work, $29,338,191 for maintenance, and $1,891,810 
for rehabilitation; a total of $39,461,025. 
42. MONROE HARBOR, MI 
Location. On lower reach of River Raisin, which 
empties into Lake Erie and is 36 miles south of Detroit, 
MI. (See NOAA Nautical Chart 14830.) 
Existing project. Provides for a channel in Lake 
Erie and River Raisin to City of Monroe, for a turning 
basin, and for riprapping protecting dikes at river 
mouth. Project depths are 21 feet to turning basin, 18 
feet in turning basin, and 9 feet to upstream end of 
project. For additional details see page 1490 of Annual 
Report for 1962. Project feature for riprapping protecting 
dikes is considered inactive. Estimated costs of 
this feature (1954) is $90,000. (See Table 31-B for 
authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Several privately owned docks 
and a municipal terminal. Port of Monroe Authority 
built a steel and concrete wharf on southeast side of 
turning basin for commercial use. Facilities are considered 
adequate for existing commerce. 
Operations during fiscal year. Maintenance: Condition 
surveys, environmental studies, miscellaneous 
inspections and reports were performed by Government 
forces at a cost of $49,925. The U.S. Hopper 
Dredge HAINS performed maintenance dredging 
removing 117,237 cubic yards, bin measure, of shoal 
material at a cost of $233,835. Operation of booster 
pump cost $78,806. Maintenance of disposal area cost 
$10,199. Engineering, surveys, supervision and administration 
cost $7,499. The contract for construction of 
confined disposal area is approximately 81 percent 
complete at a cost this FY of $18,424,940, which 
includes $77,130 contributed funds. Erosion control 
was performed by hired labor at a cost of $19,129. 
Engineering, design and value engineering cost 
$212,342. Supervision and administration cost $441,937. 
Total costs to end of FY were $40,948,539, of which 
$994,340 was for new work (including $300,000 contributed 
by the Port Commission of Monroe), and 
$39,954,199 for maintenance including $166,667 contributed 
funds. ($125,000 by Consolidated Paper Company 
and $41,667 by River Raisin Company.) 
43. MUSKEGON HARBOR, MI 
Location. On east shore of Lake Michigan, 114 
miles northeasterly from Chicago, IL, and 80 miles 
easterly from Milwaukee, WI (See NOAA Nautical 
Chart 14934.) 
Previous project. For details see page 1950 of 
Annual Report for 1915; page 1899, Annual Report for 
1924; and page 1484, Annual Report for 1938. 
Existing project. A breakwater protected outer 
basin in Lake Michigan and an entrance channel from 
Lake Michigan to Muskegon Lake protected by piers 
and revetments. Project depths vary from 29 feet in the 
lakeward portion of the outer basin to 27 feet in the 
channel between the inner piers to Muskegon Lake. For 
additional details see page 1808 of Annual Report for 
1968. (See Table 31-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Several privately owned 
wharves primarily for commercial use. Details on 
actual port and harbor facilities are in Port Series, No. 
48 (revised 1973) prepared and published as part 2 by 
Board of Engineers for Rivers and Harbors. Information 
on port terminal services and charges, and steamship 
services is prepared and published as part I by the 
Port Development Staff, U.S. Department of Commerce. 
Facilities are considered adequate for existing 
commerce. 
Operations during fiscal year. Rehabilitation: 
Plans and specifications were completed for major 
rehabilitation of South Breakwater at a cost of $68,755. 
A contract in the amount of $3,099,799 was awarded for 
this repair. No work was performed this FY. Supervision 
and administration cost $5,496. 
Maintenance: Condition surveys, environmental studies, 
miscellaneous inspections and reports were performed 
by Government forces at a cost of $50,111. 
Repairs to North Breakwater were performed by hired 
labor at a cost of $70,552. Engineering and design for 
major rehabilitation of South and North Breakwaters 
was continued at a cost of $86,687. The South Breakwater 
plans and specifications were completed under 
New Work. Supervision and administration cost 
$2,014. Condition surveys and monitoring for shore 
erosion maintenance of Section 111 was performed at a 
cost of $33,785. 
Existing project, including latest project modification, 
was completed in 1965. For additional details on 
completion of existing project see page 1465 of Annual 
Report for 1962. Total costs to end of FY were 
$11,892,993, of which $3,017,110 was for new work, 
$4,924,632 for maintenance, and $3,951,251 for rehabilitation. 
44. NEW BUFFALO HARBOR, MI 
Location. At mouth of galien River on southeast 
shore of Lake Michigan in Berrien County, about 45 
miles easterly from Chicago, IL. (See NOAA Nautical 
Chart 14905.) 
31-20

DETROIT, MICHIGAN DISTRICT 
Local cooperation. Fully complied with. 
Existing project. Provides for an entrance channel 
10 feet deep by 80 feet wide and 850 feet long, to mouth 
of Galien River; new north and south breakwaters 1,305 
and 740 feet long, respectively, and deepening inner 
channel to Galien River to 8 feet wide and 1,250 feet 
long. (See Table 31-B for authorizing legislation.) 
Terminal facilities. One village owned boat ramp 
and three privately operated marinas, and a private 
boat club facility. 
Operations during fiscal year. Maintenance: Condition 
surveys, miscellaneous inspections and reports 
were performed by Government forces at a cost of 
$31,679. Repairs to North and South Breakwater were 
performed by hired labor at a cost of $77,536. A contract 
was awarded and completed for maintenance dredging. 
Approximately 22,628 cubic yards, place measure, of 
shoal material was removed at a cost of $76,015. 
Engineering, design, surveys, supervision and administration 
cost $18,855. 
Existing project is complete. Total costs at end of FY 
were $3,314,984, of which $1,285,716 was for new work 
and $2,029,268 for maintenance. Contributed funds 
were in the amount of $1,186,467. 
45. OCONTO HARBOR, WI 
Location. On the west shore of Green Bay, about 31 
miles northeasterly from Green Bay Harbor, WI, and 
about 25 miles southwesterly from Menominee Harbor, 
MI and WI, at mouth of Oconto River. (See NOAA 
Nautical Chart 14910.) 
Previous project. For details see page 1187 of 
Annual Report for 1958. 
Existing project. See Chicago District Annual 
Report 1979, Table 30-C, page 30-27. For detailed 
description see page 1187, Annual Report for 1958. (See 
Table 31-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Two municipally owned 
wharves of 400 and 100 foot frontage, respectively, for 
miscellaneous freight, open to general public use. 
Facilities considered adequate for existing commerce. 
Operations during fiscal year. Maintenance: Project 
condition surveys were performed at a cost of 
$12,278. Existing project was completed in 1912. Piers 
were completed in 1885. Dredging channel and turning 
basin to existing project depth was commenced in July 
1911 and completed in May 1912. The north pier was 
rebuilt as a rubblemound by local interests in 1967. 
Total costs for existing project to end of FY were 
$130,754 for new work and $1,050,141 for maintenance, 
for a total of $1,180,895. 
46. ONTONAGON HARBOR, MI 
Location. On south shore of Lake Superior. It 
consists of improvement of mouth of Ontonagon River. 
(See NOAA Nautical Chart 14965.) 
Previous project. For details see page 1931 of 
Annual Report for 1915, and page 1406 of Annual 
Report for 1938. 
Existing project. Provides for approach channel 
16 feet deep, a channel between piers with 17 and 15- 
foot depths, an inner basin 12 feet deep, and maintenance 
of channels, basin, and entrance piers. Completed 
project cost$19,619. See page 1100 of Annual Report for 
1966 for details. A modification authorized by 1962 
River and Harbor Act provides for increasing depths of 
channels, construction of an inner basin and a sedimentation 
basin. This portion of project is inactive. (Estimated 
cost (1965) of this work is $6,040,000. (See Table 
31-B for authorizing legislation.) 
Local cooperation. None required for earlier authorization. 
See page 1020 of Annual Report for 1965 
for requirements of 1962 Act. 
Terminal facilities. There are no publicly owned 
wharves. There are three coal wharves, an oil receiving 
facility, and a few small fish wharves. Facilities are 
considered adequate for existing commerce. 
Operations during fiscal year. Maintenance: Condition 
surveys, environmental studies, miscellaneous 
inspections and reports were performed by hired labor 
at a cost of $17,746. A reconnaissance report for major 
rehabilitation of East Pier and Revetment Sections A 
and B was initiated at a cost of $19,038. An adjustment 
of 17,510 cubic yards and $-115,420 was made in 
contract completed last FY. A contract was awarded 
and completed this FY for maintenance dredging. 
Approximately 25,807 cubic yards of shoal material 
was removed by clamshell dredge at a cost of $183,359. 
Repair to breakwater was made by hired labor at a cost 
of $43,198. Engineering, design, supervision and administration 
cost $63,092. All work authorized under 
previous Acts was completed in 1938. Work authorized 
under the 1962 Act is in an inactive status. Total costs of 
existing project to end of FY were $5,873,957, of which 
$112,101 was for new work and $5,761,856 for maintenance. 
47. PENSAUKEE HARBOR, WI 
Location. On west shore of Green Bay, about 22 
miles northeasterly from Green Bay Harbor, and about 
33 miles southwesterly from Menominee Harbor, MI 
and WI. (See NOAA Nautical Chart 14910.) 
Previous projects. For details, see Annual Report 
for 1899, page 2734, and Annual Report for 1938, page 
1429. 
Existing project. An entrance channel 100 feet 
wide and 8 feet deep at low water datum from the depth 
in Green Bay about 4,300 feet to mouth of Pensaukee 
River. Fluctuations of water level are seasonal changes 
31-21

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
of about one-half foot above or below the annual mean 
stage, and extreme fluctuations of a temporary nature, 
due to wind and barometric pressure, of about 2 feet 
above or below mean lake level prevailing at the time. 
New work for completed project cost $24,851, exclusive 
of amounts expended under previous projects. (See 
Table 31-B for authorizing legislation.) 
Local cooperation. None required. 
Terminal facilities. Small private wharves along 
lower half mile of river, used by the local fishing 
interests. Ample space is available for additional 
fishing wharves when required. Facilities considered 
adequate for existing commerce. 
Operations during fiscal year. Maintenance: Condition 
surveys, miscellaneous inspections and reports 
were performed by Government forces at a cost of 
$5,247. This project was dropped from the diked 
disposal program this FY because classification of 
material was changed to suitable for unconfined open 
lake disposal. Engineering and design costs were $272. 
The existing project was completed in 1938. Total costs 
at the end of FY were $183,192, of which $34,035 was 
for new work and $149,157 for maintenance. 
48. PENTWATER HARBOR, MI 
Location. On east shore of Lake Michigan, 146 
miles northeasterly from Chicago, IL, and 14 miles 
southerly from Ludington, MI. (See NOAA Nautical 
Chart 14907.) 
Existing project. Provides for widening old entrance 
channel to 150 feet between parallel piers and 
revetments, channel to extend from Lake Michigan to 
Pentwater Lake, with a depth of 16 feet. Piers and 
revetments are built of stonefilled timber cribs and 
piling and capped with concrete. The 200-foot extension 
to south pier portion of project is considered inactive. 
Estimated cost (1954) of this portion is $65,100. (See 
Table 31-B for authorizing legislation.) 
Local cooperation. None required. 
Terminal facilities. Several small privately owned 
wharves on west end of Pentwater Lake. The City and 
Michigan Waterways Commission jointly constructed a 
dock on northwest side of Pentwater Lake for public 
use. Facilities are considered adequate for existing 
commerce. 
Operations during fiscal year. Maintenance: Condition 
surveys, environmental studies, miscellaneous 
inspections and reports were performed by Government 
forces at a cost of $11,552. A reconnaissance 
report for major rehabilitation of North and South 
Piers and Revetments was initiated at a cost of $8,545. 
Adjustments of -12,296 cubic yards and $-14,193 were 
made in maintenance contract dredging completed last 
FY. A contract was awarded and completed this FY for 
maintenance dredging. Approximately 21,300 cubic 
yards, place measure, of shoal material was removed by 
hydraulic dredge at a cost of $60,232. Maintenance of 
safety features cost $1,037. Engineering, design, surveys, 
supervision and administration cost $14,050. 
Existing project was completed in 1959 except for a 
200-foot extension to the south pier which is not 
considered necessary under present conditions. For 
additional details see page 1468 of Annual Report for 
1962. Total costs for existing project at end of FY were 
$2,735,724, of which $179,899 was for new work, and 
$2,555,825 for maintenance. 
49. POINTE LOOKOUT HARBOR 
(AU GRES RIVER), MI 
Location. At Au Gres River on westerly shore of 
Lake Huron at entrance to Saginaw Bay, about 17 miles 
northeast of mouth of Saginaw River. (See NOAA 
Nautical Chart 14863.) 
Existing project. Provides for construction of a 
small boat harbor having a 12-foot deep, 100-foot wide, 
2,800-foot long outer entrance channel; a 5,600-foot 
long, 100-foot wide inner entrance channel having a 
10-foot depth; an 8,270-foot long 6-foot deep river 
channel ending just downstream from U.S. 23 highway 
bridge and having a width of 60 feet; a 4,000-foot long 
north breakwater and a 3,800-foot long south breakwater. 
(See Table 31-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Small boat marina facilities 
are under construction by the State of Michigan. 
Operations during fiscal year. Maintenance: Condition 
surveys, environmental studies, miscellaneous 
inspections and reports were performed by Government 
forces at a cost of $23,624. A contract was awarded 
for maintenance dredging in the amount of $214,170, of 
which $7,260 is to be contributed by local interests. The 
contract is approximately 56 percent complete at a cost 
of $120,452. Engineering and design for repairs to the 
East and West Breakwaters was initiated at a cost of 
$60,389. Engineering and design for dredging cost 
$21,053. Surveys, supervision and administration cost 
$19,021. Existing project was completed in 1974. Total 
costs to end of FY were $3,271,836, of which $2,642,584 
was for new work and $629,252 for maintenance. 
50. PORTAGE LAKE HARBOR, MI 
Location. On east shore of Lake Michigan about 
186 miles northeasterly from Chicago, IL, and about 37 
miles northerly from Ludington, MI. (See NOAA 
Nautical Chart 14939.) 
Existing project. Provides for a harbor of refuge 
with an entrance channel from Lake Michigan to 
Portage Lake protected by piers and revetments. 
Project depth is 18 feet. For additional details see page 
1297 of Annual Report for 1958. Latest published map 
is in H. Doc. 588, 64th Congress, 1st session. (See Table 
31-B for authorizing legislation.) 
31-22

DETROIT, MICHIGAN DISTRICT 
Local cooperation. None required. 
Terminal facilities. There are landing places and 
marinas at inner end of Portage Lake. Facilities are 
considered adequate for existing commerce. 
Operations during fiscal year. Maintenance: Condition 
surveys, miscellaneous inspections and reports 
were performed by hired labor at a cost of $5,102. 
Existing project was substantially completed in 1912. 
For additional details on completion of existing project 
see page 1298 of Annual Report for 1958. The structures 
are generally in fair condition. Total cost of existing 
project to end of FY is $1,670,911. 
51. PORT SANILAC HARBOR, MI 
Location. On southwest shore of Lake Huron, 30 
miles north of Port Huron, MI. (See NOAA Nautical 
Chart 14862.) 
Existing project. Provides for a harbor of refuge 
protected by breakwater structures extending to 12- 
foot depth contour in lake; for dredging a harbor basin 
10 feet deep; for dredging an entrance channel 12 feet 
deep; a 70-foot extension of the south breakwater; a 
300-foot arm added to the north breakwater; and riprap 
placed at the lakeward side of the breakwater additions. 
(See Table 31-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. There is one privately owned 
dock used principally as a fishing terminal by owner 
and a municipally owned pier for recreational craft. 
Facilities are considered adequate for existing commerce. 
Operations during fiscal year. Maintenance: Condition 
surveys, environmental studies, miscellaneous 
inspections and reports were performed by Government 
forces at a cost of $6,476. Placement of sand for 
mitigation under Section 111 was completed this FY at 
a cost of $29,006. Surveys, supervision and administration 
cost $12,222. The project was completed in 1951 
except for latest modification which was completed in 
FY 76. The breakwaters are in good condition. Total 
costs of existing project to end of FY were $3,686,617 
(includes $2,120,593 contributed funds). 
52. PORT WASHINGTON HARBOR, 
WI 
Location. On the west shore of Lake Michigan, 
about 53 miles south of Manitowoc and about 29 miles 
north of Milwaukee, WI. (See NOAA Nautical Chart 
14904.) 
Previous project. For details, see page 1938 of 
Annual Report for 1915, page 1459 of Annual Report for 
1938, and page 30-14 of Chicago District Annual Report 
for 1975. 
Existing project. See Chicago District Annual 
Report for 1979, Table 30-C, page 30-27. 
Construction of a small boat harbor within the 
existing harbor was authorized by the Chief of Engineers, 
June 12, 1975, under authority of Section 107, 
1960 River and Harbor Act, as amended. 
Local cooperation. Fully complied with. 
Terminal facilities. There is one coal wharf, a 
petroleum tank farm and several fishing wharves. City 
provided a wharf which is open to public use. Facilities 
considered adequate for existing commerce. 
Operations during fiscal year. New Work: An 
adjustment of $806 was made in cost for construction of 
small-boat harbor. Maintenance: Condition surveys, 
environmental studies, miscellaneous inspections and 
reports were performed by Government forces at a cost 
of $12,147. The existing project was completed in 1936. 
The 1958 modification was deauthorized in 1977. Total 
costs to end of FY were $6,020,809, of which $3,769,622 
was for new work, and $2,251,187 for maintenance. 
53. PORT WING HARBOR, WI 
Location. On south shore of Lake Superior, 34 miles 
easterly from Duluth, MN. (See NOAA Nautical Chart 
14966.) 
Existing project. Provides for two parallel piers at 
entrance, 835 and 1,017 feet long, respectively, 200 feet 
apart; an entrance channel between piers 150 feet wide 
with 15-foot depth; an irregular-shaped turning basin 
15 feet deep at inner end of piers from which two inner 
channels with 8-foot depth extend. One of these is 60 feet 
wide extending southerly for 340 feet and one 70 feet 
wide extending easterly 1,170 feet. 
Portion of dredging of entrance channel to complete 
project width and depth is considered unnecessary to 
meet present navigation requirements. (See Table 31-B 
for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. There are four privately 
owned fishing wharves which are considered adequate 
for existing conditions. 
Operations during fiscal year. Maintenance: Condition 
surveys, miscellaneous inspections and reports 
were performed by hired labor at a cost of $8,999. 
Existing project is complete except channel between 
piers has been dredged to only a 100-foot width. 
Widening the channel an additional 50 feet was 
considered unnecessary to meet present navigation 
requirements. That work was classified inactive and 
deauthorized on August 5, 1977 under Section 12 of 
Public Law 93-251. Piers are in good condition. 
At end of FY controlling depth was 12 feet in lake 
approach, and 10 feet between piers and in northerly 
portion of turning basin, and 8 feet in easterly inner 
channel. Lands owned by the United States total 7.80 
acres. 
31-23

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
54. PRESQUE ISLE HARBOR, MI 
Location. On south shore of Lake Superior at 
Marquette, MI. It is an indentation about 1.5 miles long 
and one-half mile wide in shore behind Presque Isle 
Point. (See NOAA Nautical Chart 14970.) 
Existing project. A breakwater off Presque Isle 
Point and dredging harbor to depth of 28 feet at inner 
portion with 30 feet at entrance. For details see page 
1021 of 1965 Annual Report. (See Table 31-B for 
authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. One merchandise and petroleum 
receiving wharf and one ore dock. Facilities are 
considered adequate for existing commerce. 
Operations during fiscal year. New Work: Plans 
and specifications were initiated on the authorized 
Section 111 project, at a cost of $2,474. Maintenance: 
Condition surveys, miscellaneous inspections and reports 
were performed by hired labor at a cost of $8,908. 
Engineering and design for maintenance dredging was 
initiated at a cost of $24,220. Project has been dropped 
from dike disposal program because classification of 
material was changed to suitable for unconfined open 
lake disposal. Cost this FY was $697. 
Project authorized by earlier Acts was completed in 
1939. A contract for harbor deepening authorized by 
1960 Act was completed in April 1962 except for a 
section where rocks were encountered in southeast 
portion of harbor. Rock removal has been accomplished 
intermittently by hired labor and the project is completed. 
Breakwater is in good condition. A Section 111 
project was approved by Chief of Engineers in October 
1981 providing a rock groin, beach restoration and 
nourishment program at vicinity of Shiras Park and 
3,000 feet west of park. Total cost of existing project to 
end of FY is $1,873,500. 
55. RACINE HARBOR, WI 
Location. On west shore of Lake Michigan about 26 
miles south of Milwaukee, WI, and about 64 miles north 
of Chicago, IL, (See NOAA Nautical Chart 14925.) 
Previous project. See page 1389 of Annual Report 
for 1962. 
Existing project. See Chicago District Annual 
Report for 1979, Table 30-C, page 30-27. 
For detailed description see page 1235, Annual 
Report for 1963. New work for project as completed cost 
$777,775, exclusive of amounts expended on previous 
projects and exclusive of inner 300 linear feet of pile 
pier and 450 linear feet of rubblemound originally part 
of south breakwater but no longer considered necessary. 
(See Table 31-B for authorizing legislation.) 
Construction of a small boat harbor within the 
existing harbor was authorized by the Chief of Engineers, 
June 26, 1979, under authority of Section 107, 
1960 River and Harbor Act, as amended; however has 
not been constructed. 
Local cooperation. Fully complied with. 
Terminal facilities. Five wharves used for handling 
coal, limestone, petroleum products, and fish. City 
provided a public wharf. 
Operations during fiscal year. New Work: Coordination 
was completed at the completed Section 111 
project at a cost of $1. Maintenance: Condition surveys, 
miscellaneous inspections and reports were performed 
by hired labor at a cost of $16,636. A contract for 
dredging in connection with beach nourishment Section 
111 was awarded and completed at a cost of 
$16,123. Engineering, design, supervision and administration 
cost $10,575. 
Existing project substantially completed in 1946. 
Construction of north breakwater and shore connection 
was completed in November 1918. Removal of old north 
pier was completed in 1913. Construction of south 
breakwater and shore connection and removal of old 
south pier were commenced in June 1916 and completed 
in December 1924. Removal of outer shoals, 
widening and deepening channel through outer basin to 
existing project depth and width, and dredging river 
channel began in July and completed in November 
1946.Total costs of existing project to end of FY were 
$8,123,193, of which $1,332,315 was for new work and 
$6,790,878 for maintenance. 
56. ROUGE RIVER, MI 
Location. Rises in Oakland and Washtenaw Counties, 
MI, 30 miles long, flows southeasterly through 
Wayne County, and joins Detroit River at westerly limit 
of City of Detroit. (See NOAA Nautical Chart 14854.) 
Previous project. For details see page 1530 of 
Annual Report for 1932, and page 1558 of Annual 
Report for 1938. 
Existing project. Provides for: (a) Main channel 
from Detroit River through Short Cut Canal extending 
to upstream limit of the project, a distance of 3.5 miles. 
Project depths are 25 and 21 feet in navigation channel, 
21 feet in turning basin, and 13 feet in upper reach of 
project. (b) Old channel from Detroit River extending to 
junction of Old Channel with Short Cut Canal. Project 
depths are 25, 18, 17, and 21 feet. For additional details 
see page 1324 of Annual Report for 1963. In 1973, work 
authorized by the 1962 River and Harbor Act was 
reclassified from the active to inactive category. Estimated 
cost (1972) of this work is $880,000. Except for 
dredging 25-foot channel 1,150 feet upstream from 
mouth of Old Channel, work authorized in Act of 
August 30,1935, is considered inactive. Estimated cost 
(1958) of inactive portion is $255,000. Work authorized 
by Act of July 3, 1958 is considered inactive. Estimated 
cost (1960) of this work is $210,000. (See Table 31-B for 
authorizing legislation.) 
31-24

DETROIT, MICHIGAN DISTRICT 
Local cooperation. Act of October 23, 1962, requires 
local interests to provide lands and rights-of-way 
for construction upon request of the Chief of Engineers; 
hold the United States free from damages; provide 
terminal facilities to accommodate prospective commerce 
considered in report of District Engineer; 
dredge and maintain areas between the Federal 
improvement and terminal facilities to depths commensurate 
with improved Federal channel; make 
alterations in docks, bulkheads and other structures, 
and take such other measures as may be necessary to 
assure stability of banks adjacent to channel; and 
provide bridge protection. The assurances of local 
cooperation for the River and Harbor Act of 1962 were 
furnished by the Michigan State Waterways Commission 
and accepted on January 7,1965. Fulfillment of all 
items of local cooperation has not been accomplished. 
Terminal facilities. Numerous large commercial 
docks for handling various type cargo. Details on actual 
port and harbor facilities are contained in the Port 
Series No. 45 (revised 1972) prepared and published as 
part 2 by the Board of Engineers for Rivers and 
Harbors. Information on port administration and 
Federal services, port and terminal services and 
charges, and steamship services is prepared and 
published as part 1 by the Port Development Staff, U.S. 
Department of Commerce. Facilities are considered 
adequate for existing commerce. 
Operations during fiscal year. Maintenance: Condition 
surveys, environmental studies, miscellaneous 
inspections and reports were performed by Government 
forces at a cost of $50,506. The contract awarded 
last FY for maintenance dredging was completed at a 
cost of $325,318. Approximately 44,310 cubic yards of 
shoal material was removed by mechanical dredge. The 
U.S. Hopper Dredge HAINS performed maintenance 
dredging removing 30,000 cubic yards, bin measure, of 
shoal material at a cost of $209,170. Maintenance of 
disposal area was performed by hired labor at a cost of 
$70,026. Engineering, design, surveys, supervision and 
administration cost $20,033. An adjustment of $-1,210 
was made in cost under the diked disposal program. 
Work authorized before 1962 modification is complete 
or deauthorized. For additional details on completion 
of existing project see Annual Report for 1962. 
Total costs for existing project to end of FY were 
$28,511,721, of which $675,251 was for new work and 
$27,836,470 for maintenance. In addition, $29,563 was 
expended for new work from Emergency Relief Act 
Funds. 
57. SAGINAW RIVER, MI 
Location. Formed by union of Tittabawassee and 
Shiawassee Rivers, 22 miles long, and flows northerly 
into extreme inner end of Saginaw Bay, Lake Huron. 
Cities of Saginaw and Bay City are on the river. (See 
NOAA Nautical Chart 14867.) 
Previous project. For details, see page 1957 of 
Annual Report for 1915, and page 1550 of Annual 
Report for 1938. 
Existing project. Provides for an entrance channel 
27 feet deep and 350 feet wide from 27-foot contour in 
Saginaw Bay to river mouth; thence a channel 26 feet 
deep and 200 feet wide to New York Central Railroad 
Bridge at Bay City; thence 22 feet deep and 200 feet 
wide to C&O Railroad Bridge in Saginaw; thence 16.5 
feet deep and 200 feet wide to upstream limit at Green 
Point. Project also provides for five turning basins; one 
25 feet deep at Essexville, 600 feet wide with a 
maximum length of 1,850 feet; one 22 feet deep on east 
side of channel about 1 mile upstream from Cass 
Avenue in Bay City, 650 feet wide and 1,000 feet long; 
one 20 feet deep at Carrollton, 100 to 300 feet wide and 
900 feet long; one 20 feet deep just downstream from 
C&O Bridge in Saginaw, 650 feet wide and 1,000 feet 
long; and one 15 feet deep between Bristol Street Bridge 
and New York Central Railroad Bridge in Saginaw. 
(See Table 31-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Numerous large commercial 
docks for handling a great variety of cargo. Details on 
actual port and harbor facilities are in Port Series No. 
45 (revised 1972) prepared and published as part 2 by 
Board of Engineers for Rivers and Harbors. Information 
on port administration and Federal services, port 
and terminal services and charges, and steamship 
services is prepared and published as part 1 by Port 
Development Staff, U.S. Department of Commerce. 
Facilities are considered adequate for existing commerce. 
Operations during fiscal year. Maintenance: Condition 
surveys, environmental studies, Hi-Fix surveys, 
support of Water Control Center, miscellaneous inspections 
and reports were performed by Government 
forces at a cost of $313,585. The U.S. Hopper Dredges 
HAINS and MARKHAM performed maintenance 
dredging removing 85,913 and 823,819 cubic yards, bin 
mesure, of shoal material at a cost of $418,564 and 
$1,229,481, respectively. Maintenance of the disposal 
areas was performed at a cost of $45,925. The contract 
awarded last FY for maintenance dredging was 
completed. Adjustments of 8,835 cubic yards and $- 
54,963 were made in maintenance dredging contract. A 
contract in the amount of $2,749,000 was awarded late 
in FY for maintenance dredging. No work was accomplished 
this FY. Engineering, design, surveys, supervision 
and administration cost $77,724. Engineering 
and design for construction of diked disposal area for 
upper Saginaw was continued at a cost of $89,284. 
Existing project is complete except for a small part of 
the work authorized by the Act of October 23, 1962. 
Section D (Sixth Street Turning Basin) of the 1962 Act 
is complete except for the channel portion, which is 
pending modification. Total costs for existing project to 
31-25

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
the end of FY were $56,671,604, of which $14,662,299 
was for new work and $42,009,305 for maintenance. 
58. ST. CLAIR RIVER, MI 
Location. A 40 mile long section of Great Lakes 
connecting channels which flows southerly from Lake 
Huron and discharges into Lake St. Clair. (See NOAA 
Nautical Chart 14852.) 
Existing project. Provides for channels through 
St. Clair River, which, at low water datum, are suitable 
for vessels drawing 25.5 feet. Project also provides for 
improvement of North Channel outlet, 100 feet wide 
and 10 feet deep, for recreational craft. Project depths 
are referred to low water datums for Lakes Huron and 
St. Clair, 576.8 and 571.7 feet above mean water level at 
Father Point, Quebec; International Great Lakes Datum 
1955. (See Tables 31-B and 31-C for authorizing 
legislation and features of existing project.) Act of July 
24, 1946 provides for widening and deepening of 
southeast bend and improvement of outlet of north 
channel. Estimated cost (1971) is $600,000. 
Local cooperation. None required. 
Terminal facilities. This improvement serves 
through commerce, between upper and lower Great 
Lakes, and has not materially influenced terminal 
facilities along its route. A number of privately owned 
piers and wharves are at Port Huron, Marysville, St. 
Clair, and Marine City, MI, which handle coal, limestone, 
petroleum products, woodpulp, salt and general 
cargo. These installations satisfy present commerce 
requirements. 
Operations during fiscal year. Maintenance: Condition 
surveys, environmental studies, support of Water 
Control Center and miscellaneous inspections and 
reports were performed by Government forces at a cost 
of $227,363. Environmental studies in connection with 
the extended navigation season cost $415,508. The U.S. 
Hopper Dredges HAINS and MARKHAM performed 
maintenance dredging removing 78,200 and 28,773 
cubic yards, bin measure, at a cost of $497,670 and 
$64,520, respectively. Maintenance of disposal area at 
Gull Island cost $252,118. Operation of booster pump in 
connection with dredging cost $41,499. Location and 
removal of obstructions was performed at a cost of 
$267,859. Engineering, design, supervision and administration 
cost $26,461. 
Existing project is complete. Total cost of existing 
project to end of FY was $30,433,203, of which 
$19,213,246 was for new work and $11,219,957 for 
maintenance. 
59. ST. JOSEPH HARBOR, MI 
Location. On east shore of Lake Michigan, 60 miles 
easterly from Chicago, IL, and 24 miles southerly from 
South Haven, MI. (See NOAA Nautical Chart 14930.) 
Previous project. For details see page 1945 of 
Annual Report for 1915, and page 1470 of Annual 
Report for 1938. 
Existing project. Provides for protecting mouth of 
St. Joseph River by two piers, 250 to 325 feet apart at 
their inner and outer ends, respectively, having lengths 
of 2,758 feet on north side and 2,603 feet on south side; 
for a channel 21 feet deep from Lake Michigan to mouth 
of Benton Harbor Canal, a length of about 6,900 feet 
with widths of 265 feet at outer end of piers, 190 feet at 
inner end of piers and revetments, thence generally 215 
feet to lower end of turning basin, increasing to 250 feet 
above the turning basin to mouth of Paw Paw River, 
thence generally 110 feet in Paw Paw River to mouth of 
Benton Harbor canal; for dredging channel in Benton 
Harbor canal up to west line of Riverview Drive 
extended northerly, to 18 feet deep and 80 feet wide; and 
a turning basin 18 feet deep on north side of channel 
above mouth of Morrison Channel and a turning basin 
18 feet deep near mouth of Paw Paw River. Public Law 
88-88th Congress declared a portion of Benton Harbor 
Canal a non-navigable stream. (See Table 31-B for 
authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Several commercial wharves 
for handling coal, building materials, petroleum products, 
and miscellaneous commodities. A package 
freight terminal and a public docking facility is also 
available. Facilities considered adequate for existing 
commerce. 
Operations during fiscal year. Maintenance: Condition 
surveys, environmental studies, miscellaneous 
inspections and reports were performed by Government 
forces at a cost of $97,208. The U.S. Hopper 
Dredge HAINS performed maintenance dredging 
removing 140,040 cubic yards, bin measure, of shoal 
material at a cost of $218,469. Maintenance of disposal 
area, including trucking of material, cost $44,792. 
Engineering and design for repair of N. Pier (Sec. A), S. 
Pier (Sec. H) and North Revetment (Sec. E), cost 
$23,861. Engineering, design, surveys, supervision and 
administration cost $50,398. Maintenance of shore 
erosion mitigation under Section 111 of P.L. 98-483 was 
performed by U.S. Hopper Dredge HAINS and hired 
labor at a cost of $247,024. (Part of this cost was for 
purchase of sand and equipment rental)f Engineering, 
design, surveys, supervision and administration cost 
$76,922. Engineering and design for confined disposal 
area for polluted dredged material was continued at a 
cost of $19,428. 
Existing project was completed in 1956. The structures 
are in generally good condition. For additional 
details on completion of existing project see page 1454 
of Annual Report for 1962. Total costs of existing 
project to end of FY were $11,475,646, of which 
$1,301,372 was for new work, $9,212,058 for maintenance 
and $962,216 for rehabilitation. 
31-26

DETROIT, MICHIGAN DISTRICT 
60. ST. MARYS RIVER, MI 
Location. A Great Lakes connecting channel about 
63 miles long, flows southeasterly between State of 
Michigan and Province of Ontario, Canada, from 
eastern end of Lake Superior into northern end of Lake 
Huron. (See NOAA Nautical Charts 14882,14883, and 
14884.) At. Sault Ste. Marie, MI, about 14 miles 
downstream from Lake Superior, there are four parallel 
locks and a hydroelectric powerplant. 
Previous project. For details see page 1955, 
Annual Report for 1915; and page 1529, Annual Report 
for 1938. 
Existing project. Channels permitting 25.5-foot 
draft navigation in St. Marys River and Lake Superior 
and Lake Huron approaches thereto; constructing and 
operating four locks and two canals; constructing an 
electric plant of 14,000 kilowatt capacity (45,000 
kilowatt ultimate capacity) constructing anchorage 
areas in river above and below locks; and constructing 
various other works in conjunction with project. Subsequently, 
in 1932, the Unit 10 powerhouse was 
installed raising the capacity to 18,400 kilowatts 
(45,000 ultimate capacity). Original State locks were 
operated and maintained under permanent indefinite 
appropriation from June 9,1881, to November 2, 1886, 
after which they were destroyed by excavation for the 
Poe Lock in 1896. Weitzel Lock, destroyed in 1942 by 
excavation for MacArthur Lock, was operated and 
maintained under the same appropriation from September 
1,1881, to June 30,1935. Poe Lock was operated 
and maintained under the same appropriation from 
August 3, 1896, Davis Lock from October 21, 1914, and 
Sabin Lock from September 18,1919, to end of FY 1935. 
The 1,200 foot by 110 foot new Poe Lock was authorized 
in 1962 and put into operation in 1968. Details of 
existing project are set forth in Table 31-D. 
Project depths are referred to low water datum 
corresponding to sloping surface of river as follows: 
Above locks: When water surface of Lake Superior is at 
elevation 600 feet and at upstream side of locks is 577.8 
feet above mean water level at Father Point, Quebec 
(International Great Lakes Datum 1955). Estimated 
(1973) cost for new work is $164,630. (See Table 31-B for 
authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. This improvement serves 
through commerce between Lake Superior and lower 
lakes and has not materially influenced terminal 
facilities at localities along its route. Three piers at 
Sault Ste. Marie receive coal and petroleum products. 
Limestone is shipped from a pier at Drummond Island. 
Vessel refueling stations are at Lime Island and Village 
of Detour; they receive coal and petroleum products. 
Present terminals satisfy current traffic requirements. 
Operations during fiscal year. Operation, maintenance 
and care of locks: Two canals and four locks 
were operated as required. Necessary repairs and 
improvements were made thereto and to appurtenant 
structures and equipment. Canals were open to navigation 
274 days from October 1, 1982 thru September 30, 
1983. During that period, a total of 9,009 vessels, 
aggregating 71,157,912 short tons of freight and 
169,385 passengers passed through the MacArthur, 
Poe, Davis and Sabin Locks. Cost for operation, 
maintenance, and care of the locks for the FY was 
$4,469,848, including $96,151 for extended season 
operation and maintenance. Powerhouse and equipment: 
Two hydroelectric powerhouses were operated 
and maintained. Cost of hired labor during the FY was 
$476,035, less a deduction of $35,048 for interdepartmental 
electricity sold. Compensating Works Structure: 
A contract in the amount of $149,990 was awarded 
in September 1983 for the placement of cement grout 
filled fabric bags for the repair of scoured areas 
beneath gates 9 through 16 of the structure. Other 
operation and care items: Buildings and grounds were 
maintained, condition surveys, operation studies, miscellaneous 
inspections and reports were performed at a 
cost of $649,085. Environmental studies were made at a 
cost of $74,874. Security measures were performed at a 
cost of $451,841, including a contract for $445,462. 
Janitorial service of the Administration and Davis 
Buildings was done by contract at a cost of $31,550. A 
study on winter and extended navigation season, ice 
measurements, and weather monitoring was performed 
at a cost of $917,640. An ice boom was installed and 
removed and work on the ice stabilization islands was 
performed at a cost of $79,958. An engineering study on 
the compensating works was performed at a cost of 
$46,440. Channels and canals: St. Marys River channels 
and canal approaches were examined by sweeping. 
Removal of shoals in St. Marys River channels and 
canal approaches was accomplished by hired labor and 
U.S. Derrickboats NICOLET and HARVEY at a cost of 
$1,190,579, including engineering and design. Recreational 
facilities: Information center, comfort stations, 
park fountain, observation and overlook platforms were 
maintained at a cost of $89,983, including a janitorial 
contract for the information center at a cost of $14,810. 
A total of 533,389 visitors used the observation and 
overlook platforms and the information center during 
the FY. 
Project in effect prior to modification of March 21, 
1956 is complete and work authorized by 1956 modification 
to provide a safe draft of 25.5 feet for both 
upbound and downbound traffic is also complete. 
Public Works Acceleration Funds used for maintenance 
were $118,000. Total costs to end of FY were 
$160,657,070 for new work and $146,966,317 for maintenance, 
for a grand total of $307,623,387. 
61. SAUGATUCK HARBOR AND 
KALAMAZOO RIVER, MI 
Location. Harbor is on east shore of Lake Michi- 
31-27

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1988 
gan, 90 miles northeasterly from Chicago, IL, and 22 
miles northerly from South Haven, MI. (See NOAA 
Nautical Chart 14906.) 
Previous project. For details see page 1947 of 
Annual Report for 1915, and page 1475 of Annual 
Report for 1938. 
Existing project. Entrance channel protected by 
parallel piers at mouth of Kalamazoo River and a river 
channel to Village of Saugatuck, MI. Project depths: 16 
feet in entrance channel, 14 feet in river channel. 
Additional details on page 1456, 1962 Annual Report. 
(See Table 31-B for authorizing legislation.) 
Local cooperation. None required. 
Terminal facilities. At Village of Saugatuck, MI, 
there are several landing places for recreational craft 
and one for small commercial vessels. At Village of 
Douglas, MI, there is a landing pier. Facilities are 
considered adequate for present traffic. 
Operations during fiscal year. Maintenance: Condition 
surveys, environmental studies, miscellaneous 
inspections and reports were performed by Government 
forces at a cost of $40,540. Repair to North and 
South Pier was performed by hired labor at a cost of 
$119,031. An adjustment of $-9,363 was made in the 
contract for dredging performed last FY. Engineering, 
design, supervision and administration cost $1,531. 
Existing project was completed in 1903. Total costs to 
end of FY were $3,001,568, of which $364,527 was for 
new work and $2,637,041 for maintenance. 
62. SAXON HARBOR, WI 
Location.On south shore of Lake Superior in Wisconsin 
at mouth of Oronto Creek, 27 miles southeast of 
harbor at Bayfield, WI. and 21 miles westerly of harbor 
at Black River, MI; 99 miles east of Duluth-Superior 
Harbor and 60 miles west of Ontonagon Harbor, MI. 
(See NOAA Nautical Chart 14965.) 
Previous project: For details see page 1254 of 
Annual Report for 1962. 
Existing project. Provides for east and west breakwaters, 
an outer channel 10 feet deep, an inner basin 
and side channel 8 feet deep, and diversion of Oronto 
Creek to Parkers Creek by three short reaches of 
channel excavation and a levee. For detailed dimensions 
of features see page 1025 of Annual Report for 
1965. (See Table 31-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. One wharf 800 feet long on 
east side of present harbor basin constructed by local 
interests. 
Operations during fiscal year. New Work: Detailed 
project studies on the authorized Section 111 
project were continued at a cost of $44,008. Maintenance: 
Condition surveys were performed by Government 
forces at a cost of $7,767. Harbor improvements 
were completed in November 1965 except for minor 
work. The project was fully completed in March 1968. A 
reconnaissance report was completed in August 1971 
concerning erosion of the shoreline west of the harbor. A 
detailed project report is being prepared to develop an 
acceptable plan for mitigation measures. Total cost of 
existing project to end of FY is $914,772. 
63. SHEBOYGAN HARBOR, WI 
Location. On west shore of Lake Michigan about26 
miles south of Manitowoc and about 55 miles north of 
Milwaukee, WI. (See NOAA Nautical Chart 14922.) 
Previous project. See page 1381 of Annual Report 
for 1962. 
Existing project. See Chicago District Annual 
Report for 1979, Table 30-C, page 30-27. 
For detailed description see page 1230, Annual 
Report for 1963. New Work for project as completed 
cost $648,271, exclusive of amounts expended on 
previous projects. (See Table 31-B for authorizing 
legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Three wharves for handling 
coal, petroleum products and miscellaneous commodities. 
City provided a public wharf. Facilities considered 
adequate for existing commerce. 
Operations during fiscal year. Condition surveys, 
environmental studies, miscellaneous inspections and 
reports were performed by Government forces at a cost 
of $17,941. A contract was awarded in the amount of 
$787,369 for major repair of North Revetment Section 
O and South Pier Section I. No work was performed this 
FY. Engineering and design for the repair cost 
$137,946. Supervision and administration cost $11,412. 
Engineering and design for construction of confined 
disposal area was continued at a cost of $71,290. 
Existing project was completed in 1904. Construction 
of north breakwater was commenced in October 1913 
and completed in October 1915. Dredging turning 
basin was commenced in October 1928 and completed 
in September 1931. Dredging entrance channel to 
existing project depth was commenced in June and 
completed in July 1938. Work on 1954 modification was 
completed in December 1956. Piers and breakwaters 
are in generally good condition. Inner 260 feet of south 
pier replaced with a revetment by private interests 
under permit granted July 16,1931, by the Secretary of 
War. Piers, therefore, are maintained only for a length 
of about 2,490 feet. Sheboygan river is navigable about 
2.4 miles above its mouth for craft drawing not more 
than 2 feet. Costs of existing project are $3,502,014 for 
maintenance, $609,028 for rehabilitation and $1,136,088 
for new work; a total of $5,247,130. 
64. SOUTH HAVEN HARBOR, MI 
Location. On east shore of Lake Michigan, 77 miles 
31-28

DETROIT, MICHIGAN DISTRICT 
northeasterly from Chicago, IL, and 24 miles 
northerly from St. Joseph, MI. (See NOAA Nautical 
Chart 14906.) 
Previous project. For details see page 1947 of 
Annual Report for 1915, and page 1473 of Annual 
Report for 1938. 
Existing project. An entrance channel protected 
by parallel piers and revetments at mouth of Black 
River, a river channel and a turning basin. Project 
depths are 21 feet in entrance channel and 19 feet in 
river channel and turning basin. For additional details 
see page 1455 of Annual Report for 1962. (See Table 
31-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Several wharves for handling 
coal, building materials, woodpulp, fish, and miscellaneous 
commodities will have warehouses. Facilities 
satisfy current commerce requirements. 
Operations during fiscal year. Maintenance: Condition 
surveys, environmental studies, miscellaneous 
inspections and reports were performed by Government 
forces at a cost of $27,620. Repair to North and 
South Pier, North and South Revetment was performed 
by hired labor at a cost of $60,480. Engineering, design, 
supervision and administration cost $12,749. 
Existing project was completed in 1960. Project now 
being maintained to 14-foot and 12-foot depths, respectively, 
in lieu of the 21 feet and 19 feet authorized, which 
is adequate for current usage. For additional details on 
completion of existing project see page 1456 of Annual 
Report for 1962. Total costs for existing project to the 
end of FY were $6,216,579, of which $797,193 was for 
new work, $3,600,077 for maintenance, and $1,632,076 
for rehabilitation. 
65. STURGEON BAY AND LAKE 
MICHIGAN SHIP CANAL, WI 
Location. On west shore of Lake Michigan about52 
miles northeast of Green Bay and about 128 miles north 
of Milwaukee, WI. (See NOAA Nautical Chart 14919.) 
Previous projects. See page 1373 of Annual Report 
for 1962. 
Existing project. See Chicago District Annual 
Report for 1979, Table 31-C, page 30-27. For detailed 
description, see page 1223, Annual Report for 1963. 
(See Table 31-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. As the canal and connecting 
channel is a through waterway, only terminal facilities 
are in City of Sturgeon Bay, 4 miles from west end of 
revetted portion of canal. These facilities consist of two 
wharves for handling coal, petroleum products and 
miscellaneous commodities and four shipbuilding yards. 
City of Sturgeon Bay provided a public wharf about 5 
miles northwesterly from City of Sturgeon Bay. Two 
major shipyards are located in Sturgeon Bay where 
repair facilities are available including dry docks, 
marine railways and hoists. Facilities are considered 
adequate for existing commerce. 
Operations during fiscal year. Maintenance: Condition 
surveys, environmental studies, miscellaneous 
inspections and reports were performed by Government 
forces at a cost of $55,270. A reconnaissance 
report for major rehabilitation of South Revetment 
(Sec. N) was initiated at a cost of $415. Repair to South 
Revetment Canal was performed at a cost of $84,940. 
Boundary monumentation was performed at a cost of 
$11,284. Supervision and administration cost $3,964. 
Engineering and design for construction of diked 
disposal program was continued at a cost of $10,823. 
Total cost of existing project is $1,059,722 for new 
work, $6,708,785 for maintenance and $884,899 for 
rehabilitation; a total of $8,653,406. In addition, 
$235,940 was expended between April 25, 1893 and 
June 30, 1917 on operating and care of works of 
improvements under provision of permanent indefinite 
appropriations for such purposes. 
66. TWO HARBORS, MN 
Location. Harbor is on north shore of Lake Superior, 
27 miles northeasterly from Duluth, MN. (See 
NOAA Nautical Chart 14966.) 
Existing project. Narrowing natural entrance by 
construction of two breakwaters, 1,628 and 900 feet 
long, from eastern and western points of bay, respectively; 
and dredging a maneuvering area on north side 
of harbor to 28 and 30 feet deep. A walkway on east 
breakwater is provided for public recreational use. For 
details see page 1026 of Annual Report for 1965. 
Dredging to deepen areas along easterly and northerly 
edges of channel was completed in 1980. This portion of 
project was reclassified from the "inactive" to "active" 
category in 1973. (See Table 31-B for authorizing 
legislation.) 
Local cooperation. Fully complied with. A section 
221 local cooperation agreement was entered into with 
the City of Two Harbors on August 14, 1978. 
Terminal facilities. No publicly owned wharves. 
Three ore docks, tug wharf, an unused coal dock, and 
merchandise wharf are privately owned. Facilities 
considered adequate for existing commerce. 
Operations during fiscal year. Maintenance: Condition 
surveys, miscellaneous inspections and reports 
were performed by Government forces at a cost of 
$26,168. Breakwater repairs were performed by 
Government forces at a cost of $103,084. Engineering, 
design, supervision and administration cost $25,914. 
The existing project is complete. Total cost to end of FY 
was $4,125,710 for new work and $1,819,947 for 
maintenance; a total of $5,945,657. 
31-29

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
67. WHITE LAKE HARBOR, MI 
Location. On east shore of Lake Michigan 120 miles 
northeasterly from Chicago, IL, and 45 miles southerly 
from Ludington, MI. (See NOAA Nautical Chart 
14935.) 
Existing project. Parallel piers, revetments, and a 
channel 16 feet deep, 200 feet wide, 1,950 feet long, 
extending from Lake Michigan to White Lake. For 
additional details see page 1465 of Annual Report for 
1962. (See Table 31-B for authorizing legislation.) 
Local cooperation. None required. 
Terminal facilities. A privately owned chemical 
shipping dock on north side of lake about 3 miles from 
inner end of revetted entrance channel. Across lake, at 
Village of Whitehall, there are several installations 
serving light draft vessels. These terminals satisfy 
present recreational and commercial traffic requirements. 
Operations during fiscal year. New work: The 
contract awarded last FY for placing sand was completed 
at a cost of $36,001. Engineering, design, 
supervision and administration cost $3,730. Maintenance: 
Condition surveys, miscellaneous inspections 
and reports were performed by Government forces at a 
cost of $10,483. Repair to north and south pier and north 
revetment was performed by hired labor at a cost of 
$41,056. A reconnaissance report for major rehabilitation 
of north and south piers, north and south revetments, 
was initiated at a cost of $6,949. Supervision and 
administration cost $4,876. 
Existing project was completed in 1908. Stone was 
placed on the north and south revetments in FY 1972. 
The structures are in generally good condition. Project 
now being maintained to 14-foot depth authorized, 
which is adequate for current usage. Total cost to end of 
FY is $2,308,857, of which $455,885 was for new work 
and $1,852,972 for maintenance. 
68. RECONNAISSANCE AND 
CONDITION SURVEYS 
See Table 31-F. 
69. OTHER AUTHORIZED 
NAVIGATION PROJECTS 
See Table 31-G. 
70. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation activities pursuant to Section 107, 
Public Law 86-645 (pre-authorization.) Negative 
reconnaissance studies were completed and funds 
reimbursed for Fond du Lac ($7,500) and Oconto 
($6,900) Harbors, WI. Coordination with local sponsor 
on small-boat harbor continued at Ashland, WI ($27). 
Detailed project studies completed with final DPR 
submittal for Bayfield, WI ($9,912), and continued for 
Kenosha, WI ($90,467). 
Beach Erosion Control 
71. AUTHORIZED BEACH EROSION 
CONTROL PROJECTS 
Beach erosion control projects are authorized at 
Berrien County Shore (St. Joseph) MI, and the Shore of 
Manitowoc County, WI. For last full report see Annual 
Report for 1963 (Berrien County). Both projects are in 
the inactive category. 
72. EMERGENCY SHORE 
PROTECTION 
Authority for emergency streambank and shoreline 
protection of public works and non-profit 
public services. (Section 14 Flood Control Act of 
1946, as amended.) Negative reconnaissance reports 
were completed and funds reimbursed for Algoma, WI 
($7,500); Arnheim Road, Sturgeon River, MI ($8564); 
CYO Camp at Sanilac, MI ($1,500); East Cleveland 
Avenue (Site 1) at Manitowoc, WI ($7,500); Oak Creek, 
WI ($3,100); and Saxon, WI ($6,000). Positive reconnaissance 
reports were completed and funds reimbursed 
($7,500), and plans and specifications initiated 
($2,839), for Bayshore Drive, Door County, WI; and 
($8,000) and ($3,095), respectively, for Elkhart River, 
IN. Restudy report on previously completed project 
substantially complete for Charlevoix, MI ($18,13388). 
At Meridian Township, MI, an adjustment of $9,208 
in the contract awarded and completed last FY for 
Erosion Control Project - Section 14, was made this FY. 
Surveys and layouts for the O&M manual cost $3,532. 
Engineering, design, supervision and administration 
cost $816. At Siena Center, Racine, WI, surveys and 
layouts for the O&M manual on the contract completed 
last FY for Erosion Control Project - Section 14, cost 
$70. At the Zoological Gardens, Racine, WI, a contract 
for Emergency Bank Protection - Section 14, was 
awarded this FY in the amount of $194,900. Plans and 
specifications and construction advertisement and 
award completed this FY cost $35,928. At Thunder 
Bay, Alpena, MI, the contract awarded last FY, 
Protection for Home for the Elderly - Section 14 project, 
was completed at a cost of $121,786. Surveys and 
layouts for the O&M manual, engineering, design, 
supervision and administration cost $20,025. At Eagle 
Harbor, MI, plans, specifications, reconnaissance reports, 
surveys, layouts, construction advertisement and 
award were performed at a cost of $29,590, and a 
contract was awarded in the amount of $64,940. 
73. BEACH EROSION WORK UNDER 
SPECIAL AUTHORIZATION 
Beach erosion activities pursuant to Section 103 of 
the 1962 River and Harbor Act. During the fiscal 
year, detailed project studies were continued at Escana- 
31-30

DETROIT, MICHIGAN DISTRICT 
ba, MI ($84,512), and Ontonagon, MI ($91,417), and 
terminated at Two Harbors, MN ($4,074). Plans and 
specifications were initiated for Ashland, WI, on the 
authorized Section 103 beach erosion project, at a cost of 
$4,602. 
74. MITIGATION OF SHORE 
DAMAGES 
Mitigation of Shore Damages pursuant to Section 
111 of the River and Harbor Act of 1968. Negative 
reconnaissance studies were completed and funds 
reimbursed for Bolles Harbor, MI ($6,800); Monroe 
Harbor, MI ($7,000); Portage Lake Harbor, MI 
($3,900); and Whitefish Pointe Harbor, MI ($5,000). 
Detailed project studies were terminated at Big Bay 
Harbor, MI ($2,975), and continued at Saxon Harbor, 
WI ($44,008). Coordination was completed at constructed 
project at Racine, WI ($1), and at the authorized 
project at Grand Traverse Harbor, MI ($305). Monitoring 
was initiated at Grand Marais, MI ($4,015). 
Flood Control 
75. RED RUN DRAIN-LOWER CLINTON 
RIVER, MI 
Location. The Clinton River basin has an area of 760 
square miles and includes parts of Macomb, Oakland, 
St. Clair and Lapeer Counties in the Southeastern 
portion of the lower peninsula of Michigan. The project 
itself is located in the southeastern section of the basin. 
Existing project. Provides for abandonment of the 
upper 2 miles of the Red Run Drain in Oakland County 
and for enlarging and paving the Red Run Drain from 
Dequindre Road on the west downstream to the Main 
Branch, Clinton River, a distance of approximately 8% 
miles. Bottom widths of the channel would vary from 70 
to 240 feet. The Main Branch, Clinton River would be 
widened, deepened and straightened for a distance of 
about 4% miles. The channel width would vary from 180 
to 200 feet and adjacent lands would be maintained as a 
floodway with a width of 500 feet. The authorized plan 
provides for a rectangular concrete-lined channel 
below this point, varying in width from 180 to 210 feet, 
to the existing Clinton River Cut-Off Canal, a distance 
of about 2 miles. The Cut-Off Canal would consist of a 
rectangular channel with concrete bottom 210 feet wide 
and steel sheet pile walls in the upper 1% miles and a 
trapezoidal concrete-lined channel with a 170-foot 
bottom width and 75-foot wide benches placed on each 
bank over the lower mile of the Canal to Lake St. Clair. 
The authorized plan would provide protection for 
surrounding urban areas against rainfall and flood 
having a 1.0 percent chance of occurrence under 
anticipated urbanized basin conditions in the year 2000. 
The cost estimate for new work (Mar 1983) is $114,600,- 
000 excluding $24,100,000 to be contributed by local 
interests. Estimate of cost to local interests (Mar 1983) 
is $43,800,000. 
Local cooperation. Prior to construction, local interests 
must furnish assurances satisfactory to the 
Secretary of the Army that they will: Provide without 
cost to the United States all lands, easements, rights-ofway, 
utility relocations, and highway bridge alterations 
necessary for construction of the channel improvements; 
presently estimated at (Mar 1983) $8,800,000 for 
Red Run Drain and (Mar 1983) $10,900,000 for Lower 
Clinton River; hold and save the United States free from 
damages due to the construction works; maintain and 
operate all the works after completion in accordance 
with regulations prescribed by the Secretary of the 
Army; contribute in cash a sum presently estimated at 
(Mar 1983) $24,100,000, which, together with items 
applicable to Red Run Drain to be furnished in above, 
would constitute 50 percent of all flood control costs for 
Red Run Drain; prevent or restrict development in the 
project area by providing easements or by establishing 
and enforcing flood plain regulations where such 
development would result in the increase of damage 
able property in the flood plain or would necessitate 
modifications, or reduce the efficiency of, the project; 
prevent encroachment on the project channels and 
ponding areas which would decrease the effectiveness 
of the improvements, and, if ponding areas and capacities 
are impaired, promptly provide substitute capacities 
to restore the effectiveness of the project channels 
by establishing and enforcing water quality standards 
commensurate with Federal, State, and local standards; 
hold and save the United States free from damages due 
to the construction and operation of any pollution 
abatement structures constructed by local interests on 
Red Run Drain in Oakland County; to bring the non- 
Federal share of costs to at least 50 percent of the total 
costs of recreation development, which may consist of 
the actual cost of carrying out an agreed upon portion of 
the development, a cash contribution, or a combination 
of both; operate and maintain the recreation facilities 
for the life of the project; and provide access to all on 
equal terms. 
Operations during fiscal year. Work continued at 
a cost of $45,100, on completing detailed hydraulic, 
hydrologic and economic analyses in response to issues 
raised by Federal, State and local governments and the 
public, on the post-authorization studies. These analyses 
included a reanalysis of structural and non-structural 
alternatives and an investigation of several 
alternative plans to alleviate basement flooding in the 
Twelve Towns area of the project. The Final Reevaluation 
Report, dated January 1983, concluded that 
flood damage conditions and project benefits were 
substantially less than presented in the original survey 
report. No alternative plans were found to be economically 
feasible. Thus, preconstruction planning was 
terminated and the project was classified as "inactive" 
in March 1983. 
31-31

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
76. SAGINAW RIVER, MI 
Location. Saginaw River basin including its tributaries, 
Tittabawassee, Shiawassee, Flint and Cass 
Rivers, drains an area of 6,260 square miles in the east 
central part of Michigan and empties into Saginaw 
Bay, an arm of Lake Huron. Bay City, near mouth of 
river, and Saginaw, 22 miles upstream from mouth, are 
on Federally improved deep-draft Saginaw River 
navigation channel. (See Saginaw and Flint Geological 
quadrangles and NOAA Nautical Chart 14867.) 
Existing project. Provides for improvements in 
Saginaw River Basin for flood control and other 
purposes: (a) at Middle Branch and South Branch, Cass 
River, to provide for major drainage improvements by 
channel improvements on Middle and South Branches, 
including a short reach of East Branch, at an estimated 
U.S. cost (July 1961) for construction of $1,448,000 for 
Middle and South Branches; provided local interests 
contribute in cash 42 percent of first cost of major 
drainage project on Middle Branch, and 38 percent of 
first cost of major drainage project on South Branch, 
exclusive of cost of rights-of-way and other work 
required as local cooperation, and give assurances 
satisfactory to Secretary of the Army they will construct 
and maintain local drainage work required to 
fully and effectively utilize improvements to be provided 
under the Federal projects; (b) at Vassar on Cass 
River, to provide for flood protection of areas on north 
and south sides of river by channel improvement, levee 
construction, floodwalls, modification of Moore Drain, 
and related work at an estimated U.S. cost (Oct 1982) of 
$8,105,000 and non-Federal cost of $541,000 for construction; 
(c) at Frankenmuth on Cass River, to provide 
for flood protection of areas on north side of river by 
channel improvement, levee construction related work, 
at an estimated U.S. cost (Jul 1974) of $410,900 for 
construction; (d) at Flint on Flint River, to provide for 
flood protection of areas on both sides of main stem of 
Flint River and its tributaries, Swartz and Thread 
Creeks by channel improvement, bridge alterations, 
floodwall and levee construction, and related work, at 
an estimated U.S. cost (Oct 1982) of $18,069,100 and 
non-Federal cost of $2,579,000 for construction; provided 
local interests contribute in cash 1 percent of first 
cost of project, exclusive of costs of rights-of-ways (e) at 
Corunna on Shiawassee River, to provide for flood 
protection by channel improvement, levee construction, 
and related work at an estimated U.S. cost(July 1961) of 
$48,000 for construction; provided local interests modify 
spillway of mill dam at Corunna at their own 
expense, substantially in accordance with plan of 
District Engineer and subject to approval of Chief of 
Engineers, or in lieu thereof, contribute to the United 
States actual cost of modification to be performed by the 
United States; (f) at Owosso on Shiawassee River, to 
provide for flood protection by channel improvement at 
an estimated U.S. cost (July 1961) of $425,000 for 
construction; (g) at Midland on Tittabawassee River, to 
provide for flood protection through non-structural 
(permanent evacuation) measures at an estimated U.S. 
cost (Oct 1981) of $4,760,000 and non-Federal cost of 
$1,445,000 for implementation; however, project was 
reclassified to the "inactive" category on December 15, 
1982; (h) at Shiawassee Flats along lower reaches of the 
four principal tributaries of Saginaw River, to provide 
for flood protection, including fish and wildlife areas; 
by channel improvement, levees, lateral reservoirs with 
control structures and related work at an estimated 
U.S. cost (Oct 1982) of $22,115,000 Federal, and a non- 
Federal cost of $2,534,000 which includes a cash 
contribution of $1,163,000; provided local interests 
contribute in cash 5 percent of cost of rights-of-way for 
flood control and other work required as local cooperation, 
and furnish one-half of land required for fish and 
wildlife areas; provided that the Federal allocation for 
conservation does not exceed amount obtained by 
taking 28 percent of project cost for Shiawassee Flats 
unit and subtracting therefrom one-half cost of lands 
for conservation; and provided further that before 
starting works for flood control to Shiawassee Flats, 
Chief of Engineers and Director, Fish and Wildlife 
Service, prepare a plan mutually acceptable to Secretary 
of the Army and Secretary of the Interior for 
operation of fish and wildlife areas to required degree of 
controlled storage of flood-waters while preserving the 
maximum fish and wildlife benefits. Total estimated 
cost for new work, for active portion (1982) is $48,700,- 
000 Federal and $1,346,000 to be contributed by local 
interests. Total estimated cost (1982)to local interests is 
$5,660,000. 
Local cooperation. Responsible local interests must 
make cash contributions as called for above; furnish 
lands, and rights-of-way, including removal of buildings, 
for construction; hold the United States free from 
damage; maintain and operate all works after completions; 
establish and enforce regulations designed to 
prevent encroachments in improved channels; and bear 
expense of constructing highway relocations and highway 
bridges, alter bridge approaches and existing 
highway bridge approaches and existing highway 
bridges (except underpinning and bridge raising), and 
alter utilities. Required assurances for Flint River at 
Flint were furnished by City of Flint and accepted by 
the United States on November 23, 1962. Estimated 
required cash contribution for Flint ($56,000) was 
furnished February 20, 1963. An additional $117,000 
was furnished by the City to cover increased construction 
costs. Required assurances for Cass River at 
Frankenmuth were accepted on September 8,1964. All 
necessary lands, easements, and rights-of-way have 
been provided. The Midland City Council adopted a 
resolution on June 7, 1982 declaring its intent not to 
sponsor the Flood Control project on the Tittabawassee 
River at Midland. The Vassar City Council, in a letter 
dated January 26, 1982, indicated a willingness and 
31-32

DETROIT, MICHIGAN DISTRICT 
capability to provide the assurances of local cooperation 
f 'the Vassar Flood Control Project. Saginaw County, 
in a resolution dated August 11, 1982, indicated a 
willingness and capability to provide the assurances of 
local cooperation for the Shiawassee Flats Flood 
Control Project. 
Operations during fiscal year. New Work: Midland: 
As a result of the Midland City Council action, the 
Midland Flood Control project was reclassified to the 
"inactive" category on December 15, 1982, and an 
adjustment of $-2,256 was made in FY 88. 
Shiawassee: The Final Re-evaluation Report on the 
project was prepared during the fall of 1982 and was 
approved by North Central Division on March 11, 1983. 
Work on preparing a General Design Memorandum 
was initiated in FY 83. Total cost for Shiawassee for 
new work this FY is $1,338,463. 
Flint: Investigations of claims for contract completed in 
FY 80 cost $55,473 in FY 88. 
Vassar: The Final Re-evaluation Report was submitted 
to North Central Division and approved on March 31, 
1983. Work on preparing a General Design Memorandum 
was initiated. Total cost for new work for Vassar 
this FY is $131,498. 
The Frankenmuth and Flint portions of the project are 
complete. 
Total costs for this project in FY 88 were $1,523,178. 
77. SEBEWAING, SEBEWAING 
RIVER, MI 
Location. Sebewaing River drains an area of 105 
square miles in Huron and Tuscola Counties on the 
westerly side of Thumb area of Lower Peninsula of 
Michigan and discharges into Saginaw Bay, an arm of 
Lake Huron, 20 miles northeast from mouth of Saginaw 
River. Village of Sebewaing is near mouth of river. (See 
NOAA Nautical Chart 14863.) 
Existing project. Enlarging present channel of 
Sebewaing River through Village of Sebewaing, MI, to 
a capacity of 7,500 cubic feet per second from junction of 
Columbia and State drains to a point 4,500 feet 
lakeward from railroad bridge near mouth; altering 
railroad bridge and three highway bridges to permit 
free passage of ice; and removal of present dike on south 
side of channel lakeward from railroad bridge. Project 
is designed to provide protection for Village of Sebewaing 
from floods with a frequency of once in 15 years 
and with a magnitude greater than the maximum flood 
of record. (See Table 81-B for authorizing legislation.) 
Local cooperation. Complied with except for furnishing 
easements and rights-of-way for removal of 
remaining portion of dike on south side of channel 
lakeward from railroad bridge. 
Operations during fiscal year. Maintenance: Condition 
surveys, miscellaneous inspections and reports 
were performed by Government forces at a cost of 
$9,533. 
78. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
The listed projects were inspected during this period. 
Battle Creek, Kalamazoo River, MI; Kawkawlin, Kawkawlin 
River, MI; Sebewaing, Sebewaing River, MI; 
Flint, Flint River, MI; Frankenmuth, Cass River, MI; 
Mount Clemens Spillway and Cutoff Canal, Clinton 
River, MI; Red Run, Clinton River, MI; Estral Beach, 
Lake Erie, MI; Fort Wayne Mechanic St. Dike, St. 
Marys River, IN; Rouge River, MI;Burr Oak, Prairie 
River, MI. Fiscal year costs were $90,000. Total costs to 
end of FY were $800,669. 
79. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
See Table 81-H. 
80. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Emergency Flood Control Activities, Flood Fighting 
(Public Law 84-99 and P.L. 98-288 and Antecedent 
Legislation). 
1. a. On March 21, 1983, a snowstorm accompanied 
by high winds down Saginaw Bay, Lake Huron, caused 
near shore flooding and property damage in beach 
areas north of Bay City, Michigan. 
b. The high waters necessitated the precautionary 
evacuation of some 200 people by local authorities. 
Damages were experienced primarily by shoreline 
trailer courts in Bangor Township, Bay County. There 
were no Federal estimates of damages. 
c. During this period the District's Saginaw 
Project Office staff remained on alert duty and in 
communication with local officials. However, local 
county resources handled emergency event without 
Corps aid. 
2. a A prolonged spell of rainy spring weather was 
climaxed with heavy rainstorms and scattered tornadoes 
on May 2,1988, sending many streams in southern 
Michigan and northern Indiana into flash-flood conditions. 
The National Weather Service (NWS) reported 
most streams in these areas would crest 2-8 feet above 
flood stage. Several "Recon Teams" from the Detroit 
District were dispatched to monitor reported flood 
prone areas, e.g., the Raisin River, Saline River, lower 
Rouge River, Huron River, and Clinton River in 
southeastern Michigan; the La Porte Lakes, upper 
Kankakee River, Yellow River, and Maumee River in 
northern Indiana. 
b. Flooding in most of the basins remained 
confined to low flood plain areas with negligible 
31-33

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
damage. The one exception was the Pine Lake shoreline 
developments in La Porte, Indiana. The existing high 
lake water conditions were exacerbated by this rainfall. 
Some 200 homes suffered first floor flooding and 
damages estimated at $3,042,950 were experienced as a 
result of the 1982-83 high lake levels. 
c. During this flood event the Detroit District 
furnished 40,000 sandbags and 2 pumps for use by La 
Porte County authorities and 15,000 sandbags for 
protection purposes along the lower Huron River 
Wayne County, Michigan. A total of 6 man-days were 
contributed to work under P.L. 84-99 with staff costs 
$1,369 for FY 83. 
3. Rehabilitation Project (Code 300). A project study 
for rehabilitation of the St. Marys, St. Joseph and 
Maumee River levees at Fort Wayne, IN, damaged by 
the 1982 Spring floods, was completed at the request of 
the Mayor of Fort Wayne at a cost of $19,995. 
A construction contract for rehabilitation of the 
Pemberton Street Levee in Fort Wayne, IN, awarded 
last FY in the amount of $288,495, was completed at a 
cost this FY of $172,615. Hired labor work, supervision 
and administration cost $19,614. Of the above amounts, 
$65,728 was contributed funds. 
4. On March 11, 1983, District staff participated in the 
inspection of earthworks encompassing waste lagoons 
on an abandoned hazardous waste disposal site. Purpose 
of investigation was to determine dike integrity 
over the near-term until removal of materials could be 
accomplished. Expenditures were $292. 
Flood Control activities pursuant to Section 205 of 
the 1948 Flood Control Act. Detailed project studies 
were continued on Paw Paw Lake, MI, at a cost of 
$69,996. Negative reconnaissance studies were completed 
and funds reimbursed at Baugo Creek, IN 
($7,500), Genessee Township, MI ($6,750), Brown Deer, 
WI ($7,500), Greenfield, WI ($7,500) and Princeton, WI 
($7,500). 
Flood Control activities pursuant to Section 208 of 
the 1954 Flood Control Act. A negative reconnaissance 
study was completed and funds reimbursed at 
Outagamie, WI ($7,500). 
81. SURVEILLANCE OF NORTHERN 
BOUNDARY WATERS 
Field Operations. The following field operations 
which were complemented by office activities in 
support of basic mission, were conducted during the 
current period: In support of the development calibration 
of Detroit District mathematical models, soundings 
and discharge measurements were conducted on 
the St. Clair, Detroit, and St. Marys Rivers; velocity and 
direction measurements, both open water and underice, 
were collected on the St. Marys River; and an aerial 
drogue velocity study was completed on the St. Clair 
River. 
During the winter months, the District observes the 
presence of ice in the St. Marys, St. Clair, and Detroit 
Rivers as an ongoing mission. The District monitors key 
telemetric water level gages (telemark) in these rivers 
for continuous updating of the hydrograph for possible 
detection of ice jams and associated potential for 
flooding to provide advance warning to area residents 
and other governmental agencies (in support of respective 
Flood Alert Plan). 
International Activities. The following activities 
were conducted specifically for the International Joint 
Commission (IJC) Boards and Committees: 
Members of the Detroit District staff attended the 
spring and fall semi-annual appearances of the International 
Great Lakes Boards before the Commission in 
Washington, DC, and Ottawa, Ontario, respectively. 
a. International Lake Superior Board of Control. 
The Detroit District Engineer is the United 
States Regulation Representative for the Board of 
Control. In support of the U.S. Section of the Board, the 
District provided monthly Lake Superior outflow 
recommendations based upon a review of the hydrologic 
factors which influence the future regulation of 
Lake Superior. These recommendations were based on 
the use of probability forecasts of water supplies routed 
through the lakes, rendering outflows under Plan 1977, 
the currently approved operating rule. A new regulation 
was developed by the Regulation Representatives 
for the Board to record data related to the regulation of 
Lake Superior. The sheet has been in use since May 
1983. Accumulated flow deviations; made to effect 
repairs to the Edison Sault Electric Company power 
canal. for maintenance of the U.S. piers of the compensating 
works and for delays in the start-up of the 
new Great Lakes Power Limited (GLPL) plant; were 
eliminated by the end of April 1983. Watering-up of the 
GLPL power canal began in September 1982 and all 
units of the Francis H. Clergue Generating Station in 
Sault Ste. Marie, Ontario, were operational by the end 
of February 1983. With completion of tests and modifications 
to the units, GLPL is now capable of using 
water allocations up to its full capacity. Monthly water 
quality sampling for the commissioning stage of the 
GLPL redevelopment project were carried out during 
March, April and May 1983. Work continues on a report 
on water quality changes and trends that occurred 
throughout Stage II of the redevelopment project. This 
report is being expanded to include data obtained 
during all stages of GLPL redevelopment. Edison Sault 
Electric Company and GLPL filed a petition with the 
IJC requesting an amendment to the October 3, 1979 
Supplementary Orders of Approval. The Commission 
reviewed the matter and concluded that it is not 
appropriate to revise its existing Orders of Approval (as 
amended) as requested. In September, the IJC formed a 
Consultative (Liaison) Group to seek a solution to the 
dewatering problem in the St. Marys Rapids which 
would minimize present power losses. District person- 
31-34

DETROIT, MICHIGAN DISTRICT 
nel are on the Work Group, which is evaluating 
proposed remedial measures for the rapids, which 
would require less water than presently allocated. 
Based upon the International Ad-Hoc Advisory Committee's 
report on the upgrading of the compensating 
works, remedial work has been started on the Canadiarn 
side and continued on the U.S. portion of the structure. 
An inspection and maintenance manual for the compensating 
works was completed by the Regulation 
Representatives and provided to the Board, to the 
owners, and to the International Ad-Hoc Advisory 
Committee. 
b. International Niagara Board of Control and 
International Niagara Working Committee. A 
member of the Great Lakes Hydraulics and Hydrology 
staff is on the U.S. Section of the Working Committee. 
The District was involved in the engineering and 
development of a revised rating curve for the Ashland 
Avenue gage. In 1981, the International Niagara Board 
of Control selected a representative rating and requested 
that it be accepted and implemented by the 
International Niagara Committee. The Board directed 
the Working Committee to make further cableway flow 
measurements to verify the accuracy of the new rating 
curve. The results of subsequent FY 82 and 83 measurements 
substantiated the revised Ashland Avenue 
stage-discharge relationship. The Board decided to 
limit further discharge measurements to as-needed or 
approximately every three years. 
c. International St. Lawrence River Board of 
Control. When requested, the Detroit District supported 
the Buffalo District in its activities. 
d. International Great Lakes Diversions and 
Consumptive Uses Study Board. The Detroit District 
Engineer is Chairman of the U.S. Section of the 
Working Committee. Personnel from the District hold 
membership on the Diversions and Environmental 
Evaluation Subcommittees and on the Public Involvement 
Ad Hoc Group. The Board completed its study and 
filed a report on their findings with the IJC in 
September 1981. During FY 83, staff of the Detroit 
District were involved in public meetings held in 
Canada and the U.S. during June. At these meetings, 
the IJC was able to present to the public the Board's 
final report, and to assess the public's reactions prior to 
the Commission's considerations and conclusions. 
e. International Lake Erie Regulation Study 
Board. Chief, Great Lakes Hydraulics and Hydrology 
Branch, is Chairman of the U.S. Section of the 
Regulation Subcommittee. Staff members also provided 
input to the other subcommittees. The Board 
completed its report in July 1981 and submitted it to the 
IJC. Public hearings were held in November 1982. 
f. International Great Lakes Technical Information 
Network Board. The Chief of the Great Lakes 
Hydraulics and Hydrology Branch is Chairman of the 
U.S. Section of this Board. The Detroit District also 
provides the U.S. Secretary to the Board as well as 
membership on the Hydraulics and Hydrology Committees. 
The committees are drafting their findings, 
conclusions and recommendations and are expected to 
provide the board with their final reports by January 
1984. The Board's main report to the IJC is scheduled 
for completion in March 1984. 
Coordinating Committee on Great Lakes Basin 
Hydraulic and Hydrologic Data. The Great Lakes 
Hydraulics and Hydrology Branch of the District 
provided the U.S. Secretary to this committee, as well 
as membership on its subcommittees. Operations 
continued pertaining to the coordination of basic 
hydraulic and hydrologic data with Canada. The 
Branch was involved in the publication of a Coordinating 
Committee report that documents the procedures 
used to determine St. Clair River and Detroit River 
flows for the period 1900-1978. Another report being 
worked on in the Branch documents the discharge 
measurements made on the Great Lakes Connecting 
Channels and St. Lawrence River during the period 
1900-1978. Through the auspices of the Coordinating 
Committee, the Corps of Engineers provided funds to 
Canada, in the amount of $215,000, to aid in completion 
of precise leveling in the International Section of the St. 
Lawrence River. This survey, as well as similar surveys 
conducted in the U.S. by NOAA, is part of a program to 
update the International Great Lakes Datum (IGLD). 
The new IGLD will revolve around the epic year 1980. 
Field surveys were completed in 1983, with datum 
analyses to follow. 
NCD Master Plan for Water Control Data System. 
The District completed its input for presentation 
to OCE. The District's plan calls for an annual average 
charge of $376,000 for updating the Great Lakes gaging 
network for fiscal years 1983-1987. In addition, 
$250,000 has been requested in FY 85 for a dedicated 
in-house mini-computer for real-time water control 
activities. 
Hydraulics and Hydrology of the Great Lakes. 
Studies to improve the existing Great Lakes water level 
forecasting system, including investigations into the 
factors affecting the Great Lakes water balance relationship 
(i.e. runoff, precipitation over water, evaporation, 
ice retardation, etc.) and use of real-time hydrologic 
data were continued by Great Lakes Hydraulics 
and Hydrology Branch staff members. Several conceptual 
hydrologic models have been studied and are 
being calibrated for eventual use in future forecasts of 
lake levels and outflows. This effort is being coordinated 
through the Hydrology Committee of the International 
Great Lakes Technical Information Network 
Board. District personnel are participating in the 
second year of a five-year program to assess winter 
supplies on the Lake Superior basin through use of a 
gamma radiation snow survey. 
Levels of the Great Lakes. The Branch provided 
technical information and expertise regarding lake 
31-35

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1988 
levels and long range still water forecasts to many 
interested parties such as Congressmen, State and local 
officials, news media, navigation and power interests, 
and concerned property owners. Explanation of the 
water levels was supplied to the public in the form of 
direct answers to numerous inquiries, addresses to 
various civic groups, and interviews with news media. 
The publication of an international (U.S. and Canada) 
forecast of Great Lakes water levels, under the auspices 
of the Coordinating Committee on Basic Hydraulic and 
Hydrologic Data was continued during the period. In 
support of these forecasts and to assist in lake regulation, 
funds have been provided to the Department of 
Commerce for maintenance of eleven telemetric water 
level gages at selected sites throughout the Great Lakes 
to obtain more real-time data. 
Costs for FY 88 are $1,092,046. 
General Investigations 
82. SURVEYS 
Fiscal year costs were $928,404 for navigation studies 
and $344,808 for flood control studies. Restudy of the 
deferred project at Kalamazoo, MI,was completed at a 
cost of $40,101. 
Coordination studies with other agencies include 
Special Investigations $10,000; F.E.R.C. $3,000; Soil 
Conservation Service $2,000; Coordination with States 
(Section 22) $55,999; International Water Studies 
$22,000; Special Hydrologic Study $8,000, and Flood 
Plain Management Services $167,587. 
88. ADVANCED ENGINEERING AND 
DESIGN 
Continuing AE&D costs for Cross Village Harbor 
and Green Bay Harbor were $24,590 and $78,574, respectively. 
Termination Report for Red Run Drain was 
completed in FY 83 at a cost of $45,082 (For further 
details see Section 75 of text). Total costs in FY 83 for 
Advanced Engineering and Design Projects were 
$148,246. 
84. COLLECTION AND STUDY OF 
BASIC DATA 
Three Michigan Flood Insurance Studies were initiated 
in late FY 82. They were for Taylor City of Wayne 
County; Woodhaven City of Wayne County; and 
Corunna City of Shiawassee County. The studies were 
continued in FY 83 at a cost of $92,356 and will be 
completed in late FY 84. 
An investigation of levee works along the Kankakee-
Yellow Rivers, IN, was undertaken in FY 83 at a 
cost of $22,587, 
A special hydrologic study to develop a regional flood 
frequency study for the Saginaw River Basin was 
initiated in FY 80, and continued in FY 83, at a cost of 
$3,000. 
31-36

DETROIT, MICHIGAN DISTRICT 
TABLE 31-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
in Text Project Funding FY 80 FY 81 FY 82 FY 83 Sept. 30, 1983 
1. Arcadia Harbor, 
MI 
2. Ashland Harbor, 
WI 
3. AuSable Harbor, 
MI 
4. Big Bay Harbor, 
MI 
Section 111 
5. Black River 
Harbor, MI (U.P.) 
6. Chnls in the 
Straits of 
Mackinaw, MI 
7. Charlevoix 
Harbor, MI 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
53,000 66,000 56,800 153,800 
53,031 65,992 48,350 155,998 
37,000 448,000 193,000 88,000 
37,000 448,000 211,002 77,490 
31,318 
30,292 
10,000 3,000 15,000 
15,097 10,575 12,045 
39,000 58,000 -88,942 
41,649 11,231 9,863 
38,000 - - 
43,832 - - 
2,975 
75,092 
74,384 
11,000 
11,000 
60,000 
53,907 
67,000 891,200 1,329,000 
67,223 887,546 1,320,896 
314,000 
310,454 
31-37 
784,848 
779,388 
1,695,645 
1,695,645 
2,229,796 
2,218,137 
209,7761 
209,7761 
2,451,453 
2,450,427 
340,4332 
340,4322 
50,000 
49,999 
994,760 
994,052 
383,350 
383,350 
492,423 
492,423 
2,832,629 
2,832,629 
150,318 
144,225 
180,623 
180,623 
4,536,900 
4,518,473 
1,129,396 
1,129,396 
1
1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 31-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY80 FY 81 FY 82 FY 83 Sept. 80, 1983 
8. Cheboygan 
Harbor, MI 
9. Clinton River 
MI 
10. Cross Village, 
MI 
11. Detour Harbor, 
MI 
Contributed Funds 
12. Detroit River, 
MI 
13. Duluth-Superior 
Harbor, MN and WI 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
7,000 20,460 357,455 
7,000 21,460 358,180 
-16,534 31,827 26,881 
-16,566 31,879 26,898 
11,000 2,000 25,000 
11,443 2,884 20,444 
79,000 130,000 85,065 
77,994 130,942 60,476 
100,000 797,000 250,000 
69,065 824,952 214,981 
500,000 500,000 250,000 
- 916,961 312,101 
11,390,800 11,797,500 5,515,500 
11,381,618 11,799,911 4,798,059 
11,832,000 7,993,700 
11,815,315 8,004,553 
982,000 
964,292 
2,151,000 1,940,000 1,581,000 
2,161,465 1,930,938 1,584,912 
-99,000 -1,900 - 
127,584 -1,898 - 
31-38 
15,000 
12,608 
12,660 
12,660 
33,000 
33,412 
24,590 
-864 
-45,564 
-30,626 
280 
280 
8,675,000 
8,530,302 
3,610 
2,348,000 
1,886,071 
504,236 
504,236 
864,862 
862,195 
549,7988 
549,7985 
992,257 
992,257 
235,200 
231,052 
364,000 
364,000 
1,389,510 
1,353,456 
1,204,436 
1,199,436 
280 
280 
76,877,357' 
76,877,357' 
55,813,578 
54,932,999 
41,389,694 
41,368,512 
16,109,2586 
16,109,1585 
27,600,170 
27,118,894 
1,556,249 
1,556,249

DETROIT, MICHIGAN DISTRICT 
TABLE 31-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
in Text Project Funding FY 80 FY 81 FY 82 FY 83 Sept. 80, 1983 
14. Eagle Harbor, 
MI 
15. Fox River, WI 
16. Frankfort Harbor 
MI 
17. Grand Haven 
Harbor, MI 
Section 111 
Section 111 
Contributed Funds 
18. Grand Marais 
Harbor, MN 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
14,348 
13,353 
1,735,100 1,628,000 1,571,000 
1,751,963 1,555,877 1,582,634 
360,000 136,000 1,891,000 
367,146 138,797 415,288 
81,000 76,254 736,000 
80,855 64,778 699,539 
1,780,000 
1,752,331 
-476,000 
994,733 
35,000 
82,950 
91 - 
481,000 1,614,000 
474,240 1,595,885 
2,000 
2,000 
983,000 
1,007,378 
3,747,000 
1,024,174 
124,000 -60,000 15,000 145,000 
124,000 -60,000 15,000 139,860 
- - - 27,200 
31-39 
205,1646 
205,164' 
68,700 
67,705 
3,753,3347 
3,753,3347 
33,032,6738 
32,939,5238 
1,955,159' 
1,955,159' 
5,789,397 
5,784,324 
274,776 
274,776 
1,204,500 
1,204,477 
1,283,46910 
1,283,46910 
175,000 
175,000 
17,438,29311 
14,714,93911 
813,613 
813,613 
780,400 
780,400 
224,000 
218,860 
27,200 
450,972 
450,972 
i

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 31-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
in Text Project Funding FY 80 FY 81 FY 82 FY 83 Sept. 80, 1983 
19. Grand Traverse, 
MI 
Section 111 
20. Green Bay 
Harbor, WI 
21. Hammond Bay 
Harbor, MI 
Section 111 
22. Harbor Beach 
Harbor, MI 
23. Harrisville Harbor, 
MI 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
2,000 4,000 
2,420 4,000 
34,910 
19,174 
3,000 3,200 3,000 
4,988 8,354 2,717 
5,000 
5,153 
46,000 57,000 113,000 253,800 
46,448 24,135 135,611 52,038 
40,000 55,000 10,000 
28,043 72,097 1,909 
445,000 1,171,000 1,066,500 
435,348 1,181,114 656,535 
593,879 
578,143 
1,230,000 
1,230,000 
197,771 
197,771 
37,200 
37,048 
1,545,283 
1,333,267 
75,000 10,021,39512,1 s 
78,574 10,016,8061,18s 
1,605,000 
1,904,126 
30,000 -250,000 10,000 104,000 
19,094 -236,094 9,740 101,122 
- - 87,000 
- - 63,513 
- 4,148 200,000 
- 4,148 139,629 
1,683,000 40,000 634,000 
1,682,999 40,002 634,000 
5 - - 
40,000 49,000 - 
39,777 49,183 40 
-10,000 
10,243 
-9,180 
51,191 
130,000 
73,791 
340,000 
17,633 
12,249,21314 
12,138,28014 
5,668,807 
5,565,669 
1,015,366 
1,015,366 
77,000 
73,756 
353,062 
353,062 
1,200,598 
1,200,598 
5,133,190 
5,076,981 
194,504 
194,504 
243,100 
243,100 
1,991,638 
1,669,270 
31-40

TABLE 31-A (Continued) 
DETROIT, MICHIGAN DISTRICT 
COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
in Text Project Funding FY 80 FY 81 FY 82 FY 88 Sept. 80, 1988 
Contributed Funds 
Section 111 
24. Holland Harbor, 
MI 
Section 111 
Section 111 
25. Inland Route, 
MI 
26. Kenosha Harbor, 
WI 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
- - - 250,000 
- - - 8,794 
- 5,000 45,000 480,000 
- 8,818 25,246 152,128 
8,000 1,050 
8,445 1,054 
186,097 
181,724 
665,000 567,000 487,000 3,021,100 
657,625 561,194 448,559 2,320,232 
19,000 7,200 25,000 
19,000 6,325 25,875 
39,000 
36,665 
-12,000 
-10,311 
92,000 160,000 399,000 333,000 
94,385 159,213 367,917 349,018 
30,000 26,000 245,000 -44,000 
28,778 27,013 195,901 5,33880 
- - - 100,000 
- - - 90,467 
79,000 67,000 267,000 
78,999 61,995 265,840 
100,000 
79,795 
31-41 
250,000 
3,794 
480,000 
181,187 
744,197 
789,824 
771,84115,16s 
771,84115,16 
621,000 
621,000 
9,905,232 
9,202,672 
173,200 
170,865 
502,452 
502,452 
1,663,300 
1,663,300 
918,22217 
918,22217 
2,053,488 
2,037,510 
404,800 
404,300 
946,969s,1" 
937,4361,n 
2,290,377� 
2,264,005w 
1,270,275 
1,270,275 
4,378,600 
4,378,600

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 31-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
in Text Project Funding FY 80 FY 81 FY 82 FY 83 Sept. 30, 1983 
27. Kewaunee New Work 
Harbor, WI 
28. Keweenaw 
Waterway, MI 
29. Knife River 
Harbor, MN 
30. Lac La Belle 
Harbor, MI 
31. Lake St. Clair, 
MI, Channels 
32. Leland Harbot*, 
MI 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
- 8,000 359,000 625,400 
- 6,951 354,382 607,019 
70,000 1,769,000 
61,792 1,770,999 
781,000 
786,462 747 
7,000 
7,000 
132,000 511,000 393,000 410,000 
133,888 506,487 400,985 345,687 
20,000 60,000 
18,300 44,466 
7,000 
7,000 
17,233 
18,100 4,048 4,203 
18,100 4,048 4,203 
-2,653 
-2,207 
40,000 
29,475 
101,000 
78,172
1 
24,638 
23,808 
75,000 
50,745 
662,000 90,000 701,000 346,000 
660,187 74,942 697,332 323,961 
1,000 1,000 - - 
681 1,321 - - 
- - - - 
103,000 37,000 75,000 189,000 
100,270 39,783 70,671 177,087 
752,33321 
752,33321 
2,715,3412 
2,691,2932 
617,300 
617,300 
2,961,461 
2,961,461 
5,974,141 
5,974,141 
10,151,684@ 
10,085,3472 
108,000 
85,172 
412,945 
412,945 
249,267 
248,437 
269,270 
269,270 
297,641 
262,861 
7,675,35724 
7,675,357u 
5,850,08425 
5,807,08025 
5,119,800 
5,119,800 
1,027,0892 
1,027,089" 
1,110,445 
1,094,193 
31-42

DETROIT, MICHIGAN DISTRICT 
TABLE 31-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
in Text Project Funding FY 80 FY 81 FY 82 FY 83 Sept. 30, 1983 
33. Lexington 
Harbor, MI 
Contributed Funds 
Section 111 
Section 111 
34. Little Lake 
Harbor, MI 
35. Ludington Harbor, 
MI 
Section 111 
Section 111 
36. Manistee Harbor, 
MI 
37. Manistique 
Harbor, MI 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
70,678 
70,678 
389,000 -25,000 -7,000 
179,843 177,156 541 
10,680 4,860 35,000 
10,680 4,860 35,000 
- - 180,000 
- - 135,425 
25,000 
24,973 
44,575 
233,000 168,000 168,000 129,000 
236,285 168,122 168,012 106,875 
1,250,000 
2,450,689 
- 85,000 
40,214 89,058 
157,716 1,355 - - 
179,000 204,000 618,000 549,500 
101,069 279,859 432,231 726,766 
- - 15,000 - 
- - 15,000 - 
109,000 54,000 402,000 190,000 
111,724 58,280 393,114 195,904 
1,646,304 
1,646,304 
1,088,888 
1,088,888 
372,000 
372,000 
108.913 
108,886 
180,000 
180,000 
600,47827 
600,478V 
2,110,774 
2,088,674 
7,912,2022 
7,912,202" 
620,000 
620,000 
7,085,30029 
7,074,725w 
357,913 
357,913 
15,000 
15,000 
2,696,522 � 
2,696,5223 
3,835,4331 
3,832,4333s1 
1,374,164 
1,374,164 
1,299,355 2 
1,299,3555 
31-43

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1988 
TABLE 81-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
in Text Project Funding FY 80 FY 81 FY 82 FY 88 Sept. 80, 1988 
88. Manitowoc 
Harbor, WI 
Contributed Funds 
39. Marquette 
Harbor, MI 
40. Menominee 
Harbor & River 
MI & WI 
Contributed Funds 
41. Milwaukee 
Harbor, WI 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
5,790 99,000 176,279 169,000 
24,802 99,000 165,758 147,788 
180,000 97,000 745,000 250,000 
158,765 120,470 664,971 824,112 
104,000 316,000 468,000 753,000 
116,877 815,982 468,988 297,937 
- 200,000 1,423,000 
- - 995,914 
- 120,000 
- 119,105 
-14,000 24,850 57,367 
23,596 24,850 53,835 
76,000 51,700 40,000 
71,561 60,076 37,653 
56,000 1,446,000 1,243,000 
41,709 1,445,281 1,237,384 
381,800 
799,140 
477 
987 
33,000 
33,898 
46,000 
24,427 
410,000 
412,327 
1,888,644 
1,851,861 
316,333 
316,333 
2,180,864w 
2,163,934@ 
4,197,825 u 
3,738,7318 
3,081,756 
3,081,756 
2,004,800 
1,795,054 
1,282,893 
1,282,893 
1,507,257 
1,506,872 
465,757 
465,757 
533,4768 
533,4768 
1,512,454 
1,509,8208 
1,351,852 
1,351,852 
446,661 
442,724 
36,762 
36,762 
8,231,024@ 
8,231,024 
22,975,5748 
22,957,266 
31-44

DETROIT, MICHIGAN DISTRICT 
TABLE 31-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
in Text Project Funding FY 80 FY 81 FY 82 FY 83 Sept. 30, 1983 
42. Monroe Harbor, 
MI 
Contributed Funds 
43. Muskegon Harbor, 
MI 
Section 111 
Section 111 
44. New Buffalo 
Harbor, MI 
Contributed Funds 
Rehab. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
519,000 533,000 872,000 398,000 
520,700 522,194 864,138 380,264 
206,000 319,000 11,599,000 
193,652 326,309 11,508,018 
22,268,000 
19,021,218 
85,000 
77,130 
-5,000 - - - 
1,995 - - - 
379,000 170,000 409,000 207,000 
381,314 172,835 396,535 209,364 
288,000 -115,000 20,000 
288,000 -115,000 20,000 
-263,000 
-140,493 4,874 
222,000 1,200,000 
216,205 1,203,832 
40,000 
33,785 
3,800,000 
74,251 
10,650 204,870 
12,650 204,085 
63,000 96,500 5,000 
60,246 97,845 6,419 
1,891,810 
1,891,810 
6,380,925 
6,380,925 
987,340w 
987,340w 
8,486,770 
8,450,006w 
34,793,900 
31,427,063 
85,000 
77,130 
2,912,1104 
2,912,11040 
105,000 
105,000 
4,698,1154' 
4,687,84741 
243,000 
236,785 
7,677,000 
3,951,251 
1,285,716 
1,285,716 
1,186,467 
1,186,467 
1,848,553 
1,847,768 
181,500 
181,500 
31-45

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 31-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
in Text Project Funding FY 80 FY 81 FY 82 FY 83 Sept. 30, 1983 
45. Oconto Harbor, 
WI 
46. Ontonagon Harbor, 
MI 
47. Pensaukee 
Harbor, WI 
48. Pentwater Harbor, 
MI 
49. Point Lookout 
Harbor, MI 
Contributed Funds 
50. Portage Lake, 
MI 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
8,000 
8,542 
9,150 
12,278 
12,278 
163,000 687,000 556,000 215,000 
125,324 724,698 552,932 211,013 
15,000 6,000 
15,000 6,000 
- 6,710 
- 6,710 
- 10,000 
- 9,728 
67,000 92,000 131,000 
64,948 94,019 128,583 
5,247 
5,247 
272 
82,000 
81,223 
39,000 10,000 26,528 419,721 
38,699 8,197 28,633 244,539 
94,000 
86,228 
-7,400 
372 
12,000 
118,941 
131,308 
31-46 
194,001 -6,000 
194,812 -8,258 
4,185 
5,102 
130,75442 
130,75442 
1,050,14143 
1,050,14148 
396,90344 
396,903"44 
5,861,25345 
5,854,18245 
21,000 
21,000 
34,035 
34,035 
139,157 
139,157 
10,000 
10,000 
179,899 
179,899 
2,559,052 
2,555,825 
2,642,584 
2,642,584 
670,834 
495,652 
121,600 
121,600 
12,000 
256,129 
256,129 
1,416,156 
1,414,782 
I
I

DETROIT, MICHIGAN DISTRICT 
TABLE 31-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
in Text Project Funding FY 80 FY 81 FY 82 FY 83 Sept. 80,1988 
Port Sanilac 
Harbor, MI 
Contributed Funds 
Section 111 
Contributed Funds 
Section 111 
52. Port Washington 
Harbor, WI 
Contributed Funds 
53. Port Wing 
Harbor, WI 
Presque Isle 
Harbor, MI 
Section 111 
51. New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
1,128,000 -313,000 
1,086,721 56,529 
-21,000 
395,000 243,000 106,000 
301,639 336,358 103,856 
1,459,000 25,000 - 
1,375,913 248,087 - 
4,000 
4,000 
3,000 
8,213 4,210 
7,000 10,849 4, 
7,001 10,849 4, 
3,738 
6,476 
-12,975 - - 
-12,975 - - 
-3,082 - - 
12,975 - - 
-23,000 49,000 52,000 
-22,469 26,596 74,219 
12,625 - - 
36,000 95,000 177,000 
10,959 120,041 147,833 
9,000 
8,999 
- 5,000 
30 2,474 
999 34,830 
999 33,128 
31-47 
15,000 
41,228 
806 
10,000 
12,147 
909,963 
909,963 
487,018 
487,018 
336,000 
336,000 
1,540,890 
1,540,890 
115,000 
83,527 
9,158 
9,158 
323,000 
320,061 
2,582,204" 
2,582,2044 
2,245,06847 
2,245,068' 7 
10,621 
10,621 
54. 
1,624,000 
1,624,000 
63,393 
63,393 
590,029 
590,028 
1,190,492 
1,190,492 
31,000 
28,474 
565,710 
564,008

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1988 
TABLE 31-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
in Text Project Funding FY 80 FY 81 FY 82 FY 883 Sept. 30, 1988 
55. Racine Harbor, 
WI 
Section 111 
Section 111 
56. Rouge River, 
MI 
57. Saginaw River, 
MI 
(Federal Funds) 
(Contributed Funds) 
Rehab. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
- 5,500 11,000 
- 5,470 10,333 
65,000 -1,000 - 
66,042 5,020 - 
- 33,000 2,000 
- 33,000 1,999 
1,787 260,338 168,000 
1,880 260,312 168,026 
697
1 
16,636 
16,636 
35,000 
26,698 
707,000 593,000 568,000 394,000 
708,564 592,382 236,548 675,053 
3,960,000 3,033,200 
8,959,950 8,032,905 
420,000 
395,630 
1,767,000 2,371,000 2,305,000 
1,765,226 2,396,906 2,303,739 
480,000 2,770,000 
480,699 2,770,177 
570,000 
560,815 
-1,210 
-1,210 
2,333,400 
2,030,316 
90,000 
89,284 
31-48 
76,500 
76,500 
16,500 
16,500 
1,297,3154 
1,297,315 a 
35,000 
35,000 
2,815,426" 
2,815,426" 
1,253,645 
1,253,645 
3,948,754 
3,948,754 
35,000 
26,698 
675,25150 
675,251� 
13,399,78851 
13,348,73951 
14,513,823 
14,487,731 
14,917,1272 
14,917,127w 
13,600 
13,600 
23,810,280 
23,498,886 
18,520,400 
18,510,419

DETROIT, MICHIGAN DISTRICT 
TABLE 81-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
in Text Project Funding FY 80 FY 81 FY 82 FY 88 Sept. 80, 1988 
wv. hw i-is. baI VVL, 
MI 
59. St. Joseph 
Harbor, MI 
Section 111 
Section 111 
60. St. Marys 
River, MI 
61. Saugatuck 
Harbor, MI 
and Kalamazoo 
River, MI 
62. Saxon Harbor, 
WI 
Section 111 
� qCw nVV rfJ 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
482,000 892,900 895,000 1,781,000 
428,980 889,001 889,687 1,792,998 
-1,000 
-798 
212,000 866,000 272,000 448,000 
212,803 365,898 270,089 434,728 
61,000 80,400 42,000 
62,021 80,761 41,801 
58,000 
19,428 
375,000 -45,000 481,000 361,000 
877,111 -45,000 480,999 323,946 
- -30,000 
112 -24,718 
8,254,000 7,972,400 8,394,000 
8,265,172 7,881,832 8,868,270 
8,818,256 
8,829,035 
19,213,246k 
19,213,246M 
11,270,557 
11,219,957 
976,485M 
976,485" 
828,000 
828,000 
6,647,949 
6,631,817 
962,216 
962,216 
487,776 
448,997 
2,168,300 
2,131,244 
160,657,071" 
160,657,070" 
147,634,608 
146,953,217 
13,100 
13,100 
57,215 70,601 180,000 182,000 
57,215 70,411 173,866 151,739 
20,000 -14,200 
11,621 1,317 
10,000 54,000 
10,000 53,999 
- 45,000 
- 44,008 
7,767 
7,767 
364,527" 
364,527" 
2,673,62767 
2,637,04167 
426,507" 
426,4698 
141,800 
140,846 
347,457 
347,457 
31-49

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1988 
TABLE 31-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
in Text Project Fundi FY 80 FY 81 FY 82 FY 88 Sept. 30, 1988 
68. Sheboyan New Work 
64. South Haven 
Harbor, MI 
Section 111 
Section 111 
65. Sturgeon Bay, 
WI & Lake MI 
Ship Canal, WI 
66. Two Harbors, 
MN 
Harbor,WI 
46,700 875,000 54,000 843,000 
59,078 208,742 216,036 167,298 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint 
Approp. 
Cost 
- 47,000 
- 33,557 
66,000 
71,290 
-4,151 76,000 257,000 121,881 
4,153 75,976 252,484 100,849 
- 324,000 -15,000 - 
- 320,670 -11,670 - 
30,790 88,000 160,000 
43,168 72,993 161,681 
35,000 -7,100 7,000 
25,865 2,000 5,716 
0 
178,058 
93,000 
105,873 
28,000 
10,823 
- 85,000 
886 90,086 
4,000 7,000 86,000 155,000 
4,000 7,041 79,143 155,166 
1,136,0886 
1,136,088' 
8,552,392 0 
2,872,468 0 
609,028 
609,028 
637,792 
629,546 
452,42661 
452,4266 
532,000 
532,000 
3,258,5986 
3,233,0266 
1,632,076 
1,632,076 
42,381 
42.381 
324,000 
324,670 
1,059,722M 
1,059,722U 
6,444,615" 
6,444,162k 
283,119 
264,623 
884,899 
884,899 
4,125,710" 
4,125,710' 
1,826,639 
1,819,947 
31-50 
67,800 
67,224

DETROIT, MICHIGAN DISTRICT 
TABLE 31-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
in Text Project Funding FY 80 FY 81 FY 82 FY 83 Sept. 30, 1983 
67. White Lake New Work 
Harbor, MI Approp. - - - - 207,862 
Cost - - - 207,863 
Section 111 New Work 
Approp. 31,000 -3,000 100,000 45,000 255,000 
Cost 67,014 456 98,292 39,731 248,022 
Maint. 
Approp. 5,550 - 129,000 96,000 1,887,463 
Cost 5,551 - 127,145 63,364 1,852,972 
75. Red Run, Lower New Work 
Clinton River, Approp. 290,000 507,000 166,000 45,000 3,823,000 
MI Cost 484,208 510,556 165,980 45,082 3,823,000 
76. Saginaw River, New Work 
MI Approp. 710,000 530,000 686,000 1,855,000 23,714,959 
(Federal Funds) Cost 693,449 545,638 689,949 1,523,178 23,378,806 
New Work 
Approp. - - - - 173,000 
(Contributed Funds) Cost - - - - 172,997 
77. Sebewaing River, New Work 
MI Approp. - - - - 365,642k 
Cost - - - - 365,642k 
Maint. 
Approp. 6,000 - 26,000 32,000 376,144 
Cost 4,891 1,109 26,000 9,533 353,677 
81. Surveillance of New Work 
North Boundary Approp. - - - - 
Waters Cost - - - - 
Maint. 
Approp. 800,000 934,000 1,091,700 1,165,000 36,064,334@ 
Cost 754,228 951,549 1,104,894 1,092,046 35,964,435" 
'Includes $18,889 for previous projects. 2*Elnxcclluuddeess $$2556,,550000 Contributed Funds. for previous projects and $289,752 
Contributed Funds for existing projects. 
'Includes $2,097,254 for previous projects. 
SIncludes $1,547,195 for new work for previous projects. 
'Excludes $27,800 for previous projects. 
Includes $3,239,910 for previous projects. 
'Includes $89,309 for previous projects. 
'Includes $31,709 Contributed Funds. 
'�Includes 311,329 for previous projects. 
"Includes 13,437 for previous projects. 1 Includes 396,974 for previous projects. 
'nIncludes 109,463 for previous projects. 
"Includes 8,918 for previous projects. 
1Includes $176,620 for new work, $127,598 for maintenance. 
"Includes $35,705 Contributed Funds. 
'Includes $148,000 Contributed Funds for existing 
project..tIncludes $453,839 for previous projects. 
"Excludes $3,000 Contributed Funds. 
lncludes 21,818 for previous projects. 
'Includes 149,312 for previous projects. 
"Includes 8,364 for previous projects. 
"Includes 02,242 for previous projects. 
"Includes 56,000 for previous projects. 
nIncludes 235,346 for previous projects. 
"Includes 54,139 Contributed Funds. 
'7 lncludes 57,670 Contributed Funds. 
"Includes 91,416 for previous projects. 
"Includes 126,451 for previous projects. 
"Includes 54,999 for previous projects. 
nIncludes 150,910 for previous projects. 
Includes ,955 for previous projects. 
Includes 00,126 for previous projects. 
"Includes 54,288 for previous projects. 
"Includes 12,423 for previous projects. 
Includes 36,194 for previous projects. 
Includes 1,293,220 for previous projects. 
"Includes 59,305 for previous projects. 
"Includes Contributed Funds of $300,000 for new work 
and $166,667 for maintenance Contributed by: Port Commission 
of Monroe, $300,000; Consolidated Paper Co. $125,000 
and River Raisin Paper Co., $41,667. 
40 
Includes $613,408 for previous projects. 
'1Includes $446,183 for previous projects. 
alncludes $84,569 for previous projects. 
31-51

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 31-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
in Text Project Funding FY 80 FY 81 FY 82 FY 83 Sept. 30, 1983 
"lncludes $8,161 for previous projects. 
"Includes $284,802 for previous projects. 
alncludes $113,826 for previous projects. 
"Includes $188,495 for previous projects. 
'7lncludes $15,128 for previous projects. 
"Includes $427,240 for previous projects. 
"Includes $79,587 for previous projects. 
"Includes $50,084 for previous projects. 
'1lncludes $56,608 for previous projects. 
"Includes $962,556 for previous projects. 
"Includes $1,671,660 Public Works Funds and $49,419 
Emergency Relief Funds. 
"Includes $503,118 for previous projects. 
"Includes $2,904,807 for previous projects. 
"Includes $90,232 for previous projects. 
'7Includes $117,554 for previous projects. 
"Excludes $50,198 for Contributed Funds. 
"Includes $487,817 for previous projects. 
"Includes $87,131 for previous projects. 
"Includes $187,233 for previous projects. 
elncludes $131,239 for previous projects. 
"Includes $323,419 for previous projects. 
"Includes $219,730 for previous projects. 
"Includes $48,404 National Industrial Recovery Act for 
new work funds. 
"Includes $15,000 for previous projects. 
"Includes $3,973,897 for previous projects. 
31-52

TABLE 31-B 
DETROIT, MICHIGAN DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Mar. 3, 1905 
Aug. 5, 1886 
Aug. 11, 1888 
Mar. 3, 1899 
Jun. 6, 1900 
Aug. 8, 1917 
Jul. 3, 1930 
Aug. 30, 1935 
Mar. 2, 1945 
Jul. 14, 1960 
Mar. 2, 1945 
Mar. 2, 1945 
Mar. 2, 1945 
ARCADIA HARBOR, MI (See Section 1 of Text) 
Maintenance of existing 12-foot channel. 
ASHLAND HARBOR, WI (See Section 2 of Text) 
Breakwater 7,900 feet long and dredging to remove a shoal. 
Appropriation of $60,000 for 'Continuing improvement on 
enlarged project.' (On completion of Poe Lock in 1896, with 
available depth of 20 feet, dredging at Ashland Harbor was 
carried to a similar depth.) 
Detached breakwater extending 4,700 feet out from shore at 
a point 2,600 feet east of main breakwater (prolonged) and 
parallel thereto. 
Project modified by omitting detached breakwater and 
defining depth and extent of channel to be dredged. 
Widening part of present channel for entrance channel and 
for basin in eastern part of harbor. 
Deepening east basin to 25 feet and west channel, as far as 
8th Ave. West extended to 21 feet. 
Widening west channel to 750 feet at its westerly end. 
Deepening portions of East Basin and West Channel to 27 
and 21 feet, respectively. 
AU SABLE HARBOR AT AU SABLE RIVER (OSCODA), MI 
(See Section 3 of Text) 
Dredging channels 12 and 10 feet deep and riprapping 
North Pier. 
BIG BAY HARBOR, MI (See Section 4 of Text) 
Provides for converging piers 
extending from shore, an entrance 
channel between piers and a rectangular 
harbor basin. Project depths are 
12 feet in entrance channel and 
10 feet in harbor basin. 
BLACK RIVER HARBOR, MI (UPPER PENISULA) 
(See Section 5 of Text) 
Two converging breakwaters, an entrance 
channel between breakwaters, an inner 
channel, and an irregular harbor basin. Project 
depths 12 feet in approach channel and 8 feet 
in the river channel and basin. 
H. Doc. 194, 58th Cong., 2d Sess. 
H. Ex. Doc. 89, 48th Cong., 
2d Sess. Annual Reports, 
1886, p. 1674; and 1887, p. 
1966. 
H. Doc. 1698, 64th Cong., 2d 
sess. 
S. Doc. 133, 71st Cong., 2d 
sees. 
Rivers and Harbors Committee 
Doc. 46, 82d Cong., 
1st sess. 
H. Doc. 337, 77th Cong., 1st 
sess. 
H. Doc. 165, 86th Cong., 1st sess.' 
H. Doc. 446, 78th Cong., 2d 
Sess.' 
H. Doc. 446, 78th Cong., 2d 
Sess.' 
H. Doc. 446, 78th Cong., 2d 
Sess.' 
31-53

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1988 
TABLE 31-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Aug. 30, 1935 
Mar. 21, 1956 
Aug. 14, 1876 
Aug. 2, 1882 
Jun. 13, 1902 
Jun. 20, 1938 
Mar. 29, 1977 
Jun. 3, 1896 
Mar. 2, 1907 
Aug. 26, 1937 
May 17, 1950 
Oct. 21, 1964 
Aug. 5, 1886 
Jul. 19, 1963 
Nov. 7, 1966 
Jun. 3, 1969 
Jun. 13, 1902 
CHANNELS IN THE STRAITS OF MACKINAC, MI 
(See Section 6 of Text) 
Dredging channel between Round Island 
and Mackinac Island, 1,250 feet wide, 
27 feet deep and 3,250 feet long. 
Removal of Poe Reef Shoal to a depth of 
27 feet over an area of about 22,000 
square yards. 
Deepening channel between Round Island 
and Mackinac Island and removing Poe Reef 
Shoal to depths of 30 feet. 
CHARLEVOIX HARBOR, MI (See Section 7 of Text) 
Channel from Lake Michigan to Round Lake protected 
where needed by Piers and Revetments. 
Channel from Round Lake to Lake Charlevoix. 
Project depth increased to 15 feet. 
Project depth increased to 18 feet. 
Project depth increased to 24 and 23 
feet, and construction of revetment 
upstream of Highway Bridge. 
CHEBOYGAN HARBOR, MI (See Section 8 of Text) 
18% foot channel. 
8% foot channel. 
Turning Basin. 
21-foot channel to East 1st St., Enlarge 
Turning Basin, deepen to 21 feet. 
Breakwater. 
CLINTON RIVER, MI (See Section 9 of Text) 
Channel in River and Lake St. Clair, Pile Dike, 
Closing Channels and making Cutoff, and 
Revetments as needed. 
Widening Entrance Channel and Constructing 
Protected Harbor Basin 
CROSS VILLAGE HARBOR, MI (See Section 10 of Text) 
Breakwaters with entrance channel and maneuver area. 
DETOUR HARBOR, MI (See Section 11 of Text) 
Small boat harbor and harbor 
of refuge, 10-foot channel, 8-foot 
deep access channel protected by 1,000-foot 
breakwater. 
DETROIT RIVER, MI (See Section 12 of Text) 
Amherstburg Channel and Removal of Grosse Ile 
River and Harbor Committee 
Doc. 2, 72d Cong., 1st Sess. 
River and Harbor Committee 
Doc. 53, 74th Cong., 1st 
Sess. 
S. Doc. 71, 84th Cong., 1st 
Sess.' 
S. Ex. Doc. 16, 44th Cong., 
1st Sess., and Annual 
Report 1876, p. 523 
No Prior Survey of Estimates. 
No Prior Survey of Estimates. 
S. Doc. 163, 75th Cong., 3rd 
Sess.' 
Section 107, 1960 River and Harbor 
Act. 
Annual Report, 1895, p. 2823 
H. Doc. 357, 59th Cong., 1st Sess. 
H. Doc. 134, 75th Cong., 1st Sess. 
H. Doc. 269, 81st Cong., 1st Sess.' 
Section 107, 1960 River and 
Harbor Act. 
S. Doc. 199, 46th Cong., 2d Sess. 
Annual Report 1880, p. 2062 and 
H. Doc. 210, 44th Cong., 2d Sess. 
and Annual Report 1886, P. 219 
Section 107, 1960 River and 
Harbor Act. 
H. Doc. 490, 89th Cong., 2d Sess. 
Section 107, 1960 River and 
Harbor Act. 
H. Doc. 712, 56th Cong., 1st Sess. 
31-54

TABLE 31-B (Continued) 
DETROIT, MICHIGAN DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Mar. 3, 1905 
Jun. 25, 1910 
Mar. 4, 1913 
Mar. 2, 1907 
Jun. 25, 1910 
Mar. 2, 1910 
Jul. 3, 1930 
Aug. 30, 19358 
Aug. 26, 1937 
Mar. 2, 1945 
Jul. 24, 1946 
May 17, 19504 
Mar. 21, 1956 
Jul. 14, 1960 
Aug. 13, 1968 
Shoal. 
Fighting Island Channel. 
Livingstone Channel. 
Channel Depths of 26 and 25 Feet. 
Channel to Wyandotte 21 Feet Deep and 300 
Feet Wide Through Middle Ground Opposite 
Head of Fighting Island. 
Trenton Channel and Turning Basin (West of 
Grosse Ile). 
American Channel North of Belle Isle Between 
Windmill Point and Fairway Slip, Detroit. 
Deepen Westerly 300 Feet of Amherstburg Channel 
and Ballards Reef Channel Below Livingstone 
Channel to 27 Feet to Provide Depths Adequate 
for 24-Foot Draft Navigation When Governing 
Lakes are at Datum, with Necessary Widening 
at Approaches and Bends and Construction of 
Necessary Compensating Works. Detroit River. 
Extend Turning Basin in Trenton Channel 600 Feet. 
Dredge Through East Draw of Lower Grosse Ile 
Bridge, and Extend 300-Foot Width of Channel 
North of Lower Grosse Ile Bridge. 
Channel Depth of 28.5 Feet Throughout 
Downbound and Two-Way Channels, Except 
in Upper (27.7-Foot Depth) and Lower, 
(29-Foot Depth) Livingstone Channel, and 
in Upbound Channel; 27-Foot Depth in 
Ballards Reef Channel Below Junction with 
Livingstone Channel. 27.5-Foot Depth in 
Westerly 300-Foot Width of Limekiln 
Crossing and Amherstburg Reaches, and 28.5- 
Foot Depth in Westerly 300-Foot Width of 
Hackett Beach, with Necessary Compensation 
Works. Also 28.5-Foot Depth in Lake Erie 
from Detroit River to Pelee Passage Shoal. 
Inclusive. 
Trenton Channel; Deepen to 27 Feet, Where 
Necessary, Wyandotte Reach from Detroit 
River to Upper Grosse Ile Bridge, About 
5.5 Miles, Deepen to 28 Feet and Widen to 
300 Feet Below Upper Grosse Ile Bridge to 
and Including a Turning Basin 28 Feet 
Deep and 15 Across in Area Outside 
Project Limits. 
Trenton Channel: Deepen to 28 Feet and 
Widen to 300 Feet from the Upper Turning 
Basin at Trenton to Gibraltar, about 
and 40, 58th Cong., 3rd Sess. 
H. Doe. 17, 62d Cong., 1st Sess. 
H. Doc. 266, 59th Cong., 2nd 
Sess. 676, 61st Cong., 2d Sess, 
and 32, 65th Cong., 1st Sess. 
H. Doc. 253, 70th Cong., 1st Sess. 
Rivers and Harbors Committee 
Doc. 1, 72nd Cong., 1st Sess. 
H. Doc. 205, 75th Cong., 1st Sess. 
H. Doc. 734, 79th Cong., 2d Ses. 
H. Doc. 335, 80th Cong., 1st Sess. 
S. Doc. 30, 81st Cong., 1st Sees.' 
S. Doc. 71, 84th Cong., 1st Sess. 
H. Doe. 319, 86th Cong., 2d Sess.' 
H. Doe. 338, 90th Cong., 2d Sess. 
31-55

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 31-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
20,500 Feet Downstream: Construct a Turning 
Basin at Gibraltar at a Depth of 28 Feet. 
Width of 830 Feet, and Length of 1,500 
Feet: Build Compensating Works to Maintain 
Water Levels. 
Jun. 8, 1896 
Jun. 13, 1902 
Mar. 2, 1907 
May 28, 1908* 
Jul. 27, 1916 
Mar. 2, 1919 
Jan. 21, 1927 
Jul. 30, 1980k 
Aug. 30, 1930 s 
Jul. 16, 1952' 
Jul. 14, 1960' 
Oct. 4,1961 
Mar. 2, 1867 
Mar. 2, 1945 
Aug. 5, 1886 
DULUTH-SUPERIOR HARBOR, MN AND WI 
(See Section 13 of Text) 
Dredging. 
Rebuilding piers at Superior Entry. 
Enlarge plan for Superior Entry and additional dredging near 
draw span of Burlington Northern railway bridge. 
Dredging additional area for basin inside Duluth entrance to 
22-foot depth. 
Enlarging Superior Harbor Basin. 
Removal of shoal point at southerly end of East Gate Basin. 
Howards Bay Channel, 20 feet deep. 
Deepening and widening channels and basins. 
Deepen Superior Front Channel and a portion of East Gate 
Basin to 25 feet. 
Present project dimensions of channels and basin. 
Abandons northerly portion of 21st Avenue West Channel. 
EAGLE HARBOR, MI (See Section 14 of Text) 
Breakwater and dredging of entrance chaninel 
130 feet wide to depth of 14 feet. 
Project modified by reduction of channel width 
from 130 feet to 80 feet. 
Project modified by increasing width of 
breakwater from 20 feet to 30 feet and 
increasing the channel from 80 to 130 feet. 
Project modified by omitting breakwater and 
constructing guide piers. 
Inner harbor basin and breakwaters and removal 
of east guide pier. 
FOX RIVER, WI (See Section 15 of Text) 
Improvement of Fox River 
H. Ex. Doc. 59, 53d Cong., 
3d Seas. and Annual Report, 
1895, p. 2538. 
H. Doc. 82, 59th Cong., 2d 
Sess. 
H. Doc. 221, 60th Cong., 1st 
Seas. 
H. Doc. 651, 64th Cong., 1st 
Sess. 
H. Doc. 1018, 64th Cong., 1st Seas 
H. Doc. 145, 69th Cong., 1st 
Sees. and Rivers and Harbors 
Committee, Doc. 32, 
71st Cong., 2d Sees. 
H. Doc. 482, 72d Cong., 2d 
Sess. 
H. Doc. 374, 82d Cong., 2d 
Sees. 
H. Doc. 150, 86th Cong., 1st 
Sess. 
H. Doc. 196, 86th Cong., 1st 
Sess. 
Annual Report for 1868, 
p. 89. 
Annual Report for 1874, 
pp. 36, 185, and 136. 
Annual Report for 1877, 
p. 98. 
H. Doc. 446, 78th Cong., 2d 
Sess.' 
Annual Report, 1885, pp. 
2041-2045 [plan of a 
board approach Dec. 10, 
1884, as modified by 
31-56

DETROIT, MICHIGAN DISTRICT 
TABLE 31-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Sep. 19, 1890 
Jun. 3, 1896 
Jun. 3, 1896 
Jun. 13, 1902 
Mar. 2, 1907 
Mar. 3, 19258 
Jun. 26,1934' 
Jul. 3, 195810 
Jun. 23, 186611 
Mar. 3, 1925 
Aug. 26, 1937 
Oct. 27, 1965 
Jun. 23, 1866 
Jun. 14, 1880 
Sep. 19, 1890 
Jul. 13, 1892 
Jul. 3, 1930 
Aug. 26, 1937 
Mar. 2, 1945 
Dredging Fond du Lac Harbor on Lake Winnebago. 
Improvement of Wolf River 
Improvement of Stockbridge, of Calumet 
and Miller Bay, and of Brothertown 
Harbor, on Lake Winnebago. 
Increased depth in rock cuts on lower river, widen Neenah 
Channel, and a concrete retaining wall at Kaukauna. 
Operation and care of locks and dams provided for with funds 
from War Department appropriations for rivers and harbors. 
Sec. 108. That Federal project structure, appurtenances, and 
real property of Upper Fox River, WI, be disposed of to 
State of Wisconsin. 
FRANKFORT HARBOR, MI (See Section 16 of Text) 
A New Outlet 12 feet deep protected by 
Piers and Revetments. 
Exterior Breakwaters, Removal of Portions 
of Piers, Project Dimensions of Outer 
Basin. 
Dredge the Area in Lake Betsie 
Deepen Approach and Entrance Channels, 
Extend Inner Basin, and Dredge 
Recreational Anchorage Area. 
GRAND HAVEN HARBOR, MI (See Section 17 of Text) 
Piers and Revetments. 
Piers and Revetments. 
Piers and Revetments. 
Piers and Revetments. 
Present Project Dimensions of Harbor 
Channel to Grand Trunk Car Ferry Slip 
and River Channel, Eliminating all of 
that portion of Grand River above Bass 
River, Consolidation of Projects for 
Harbor and River. 
Channel to Spring Lake 
Present Project Dimensions of Harbor 
Channel from Car Ferry Slip to Grand 
Trunk Railway Bridge and Turning Basin 
Corps of Engineers, 
May 14, 1886]. 
H. Ex. Doc. 24, 51st Cong. 
1st Sess. Annual Report, 
1890, p. 2390. 
No prior survey or estimates. 
No prior survey or estimates. 
No prior survey or estimates. 
H. Doc. 294, 68th Cong., 1st 
Sess.' 
S. Bill 3910, 85th Cong., 
2d Sess. 
H. Doc. 482, 55th Cong., 2d Sess. 
H. Doc. 208, 68th Cong., 1st Seas. 
H. Doc. 511, 74th Cong., 2d Sess. 
S. Doc. 16, 89th Cong., 1st Sess.' 
S. Ex. Doc. 42, 35th Cong., 1st 
Sess. 
S. Ex. Doc. 42, 35th Cong., 1st 
Sess. 
S. Ex. Doe. 42, 35th Cong., 1st 
Sess. 
S. Ex. Doc. 42, 35th Cong., 1st 
Sess. 
S. Doe. 88, 71st Cong., 2d Sess. 
Rivers and Harbors Committee 
Doc. 1, 75th Cong., 3d Ses.x 
H. Doe. 661, 76th Cong., 3d Seas.' 
31-57

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 31-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Mar. 3, 1879 
Aug. 30, 1935 
May 17, 1950 
Mar. 2, 1945 
Jun. 23, 1866 
Jul. 13, 1892 
Jun. 26, 1910 
Aug. 8, 1917 
Mar. 3, 1925 
Aug. 30, 19352 
Aug. 26, 1937 
Mar. 2, 1945 
Oct. 23, 1962 
Mar. 2, 1945 
Mar. 3, 1871 
GRAND MARAIS HARBOR, MN (See Section 18 of Text) 
Breakwaters and dredging of anchorage area 
of 26 acres to 16 feet. 
Seawalls across ledge in southeast corner 
of harbor, enlarging anchorage basin and deepening 
of entrance. 
Small-boat basin with breakwater. 
GRAND TRAVERSE BAY HARBOR, MI 
(See Section 19 of Text) 
Two Parallel piers, and entrance 
channel between piers and a harbor 
basin. Project depths are 12 feet 
between piers and 10 feet in basin. 
Project area extended 200 feet upstream 
in 1966. 
GREEN BAY HARBOR WI (See Section 20 of Text) 
Outer Channel and revetment at Grassy Islands.12 
Inner channel. 2 
Turning basin at DePere. 
Maintenance of turning basin at DePere. 
Increasing depth of inner channel and turning basin to 18 feet. 
Deepen outer channel to 22 feet with widening and 
straightening inside of Tail Point Bend, widen channel in 
Fox River through city of Green Bay to 22 feet. 
Turning basin above Chicago & North Western Ry. Bridge. 
Turning basin at mouth of East River. 
Deepen and widen 9 miles of entrance channel to 26 by 500 
feet; 3.6 miles of entrance channel to 24 by 300 
feet; and 3.2 miles of existing Fox River to 24 feet 
deep. 
HAMMOND BAY HARBOR, MI 
(See Section 21 of Text) 
Harbor of Refuge, breakwaters 
10-foot depth in harbor basin 
12-foot depth in entrance channel. 
HARBOR BEACH, LAKE HURON, MI 
(See Section 22 of Text) 
Adopted Site and made provision for harbor. 
H. Ex. Doc. 75, 43d Cong., 
2d Sess. Annual Report, 
1875, p. 184. 
Rivers and Harbors Committee 
Doc. 22, 72d 
Cong., 1st Sess. 
H. Doc. 187, 81st 
Cong., 1st Sess.' 
H. Doc. 446, 78th Cong., 2d Sess. 
Annual Report, 1867, p. 70. 
Unpublished report 
approved Aug. 3, 1892. 
H. Doc. 222, 61st Cong., 
2d Sess. 
H. Doe. 1017, 64th Cong., 1st 
Sess. 
H. Doc. 294, 68th Cong., 
1st Sess. 
Rivers and Harbors 
Committee Doc. 40, 72d 
Cong., 2d Sees. 
Rivers and Harbors 
Committee Doc. 73, 74th 
Cong., 2d Sees. 
H. Doe. 95, 76th Cong., 
sleSt ess. 
H. Doc. 470, 87th Cong., 2d Sess.1 
H. Doc. 446, 
78th Cong., 
2d Sess. 
Annual Report 1873, p. 292 
31-58

TABLE 31-B (Continued) 
DETROIT, MICHIGAN DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorised Documents 
Jan. 21, 1927 
Mar. 2, 1945 
Aug. 30, 1852 
Mar. 2, 1867 
Mar. 8, 1899 
Mar. 3, 1905 
Jul. 8, 1980 
Aug. 30, 1985 
Sep. 3, 1954 
Sep. 8, 1954 
Sep. 2, 1964 
Mar. 3, 1899 
Mar. 2, 1907 
Aug. 30, 19852 
May 17, 1950 
Oct. 23, 1962 
Closing North Entrance and Dredging 
Main Entrance and Anchorage Area. 
Removal of Portion of Breakwater in 
interest of sanitation. 
HARRISVILLE HARBOR, MI (See Section 28 of Text) 
Harbor of Refuge, Breakwaters, 
12-foot depth entrance channel 
10-foot depth in harbor basin. 
HOLLAND HARBOR, MI (See Section 24 of Text) 
Artificial channel between Lakes 
Macatawa and Michigan.12 
Piers and Revetments. 1z 
Extending Inner Piers. 
Converging Breakwater. 
Channel to Holland and Turning Basin 
at Holland. 
Present Project Dimensions of Channels 
and Turning Basin. 
Widen Bend in Reveted Entrance Channel 
into Lake Macatawa, Dredge Channel in 
Black River, and Widen and Extend 
Turning Basin. 
THE INLAND ROUTE, MI (See Section 25 of Text) 
Channel 30 feet wide and 5 feet deep 
through Lakes and Rivers with suitable 
jetties. 
Lock and Dam. 
KENOSHA HARBOR, WI (See Section 26 of Text) 
Parallel piers and 600 feet of breakwater." 
Extending breakwater 200 feet. 
Present project dimensions of entrance channel and basin. 
Channel northwesterly from basin. 
Deepen lake approach channel to 27 feet and 800 feet wide; 
deepen approach channel to 26 feet, entrance channel and 
inner basin to 25 feet. 
H. Doe. 1700, 64th Cong., 2d Sess 
H. Doe. 446, 78th Cong., 
2dSess. 
8. Ex. Doe. 42, 35th Cong., 1st 
Ses. 
Annual Report 1866, p. 106. 
H. Doec. 272, 51st Cong., 2d Sees., 
and Annual Report 1887, p. 2950. 
Annual Report 1905, p. 2176. 
H. Doe. 588, 69th Cong., 2d Sess. 
Rivers and Harbors Committee 
Doe. 48, 74th Cong., 1st Sees. 
H. Doe. 282, 88rd Cong., 2d Seas. 
H. Doe. 142, 82nd Cong., 1st 
Seas.' 
Chief of Enginee's. 
H. Doe. 828, 54th Cong., 2d 
Seas. Annual Report, 1897, 
p. 2772, H. Doe. 164, 55th 
Cong., 3d Seas. Annual 
Report, 1899, p. 1817. 
H. Doe. 62, 59th Cong., 
2d Seas. and Rivers and 
Harbors Committee Doe. 
8, 59th Cong., 2d Sess. 
Rivers and Harbors 
Committee Doe. 19, 74th 
Cong., 1st Sees. 
H. Doe. 750, 80th Cong., 
2d Seas. 
H. Doe. 496, 87th Cong., 
2d Sess.l 
31-59

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 31-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Mar. 3, 1881 
Jun. 25, 1910 
Aug. 30, 19352, 14 
Jul. 14, 1960 
Sep. 19, 1890 
Jun. 25, 1910 
Mar. 2, 1919 
Aug. 30, 193615 
Mar. 2, 1945 
Sep. 3, 1954 
Mar. 7, 1974 
Mar. 2, 1945 
KEWAUNEE HARBOR, WI (See Section 27 of Text) 
Entrance piers. 
Turning basin. 
North breakwater, remove old north pier, widen and deepen 
entrance channel and turning basin to 20 feet and remove 
outer south shoal. 
Enlarge existing turning basin, extend existing project into 
north basin, and increase depth of north basin to 20 feet 
at a maximum width of 500 feet and eliminate removal of 
outer shoal. 
KEWEENAW WATERWAY, MI (See Section 28 of Text) 
Acquisition of waterway; for a 16-foot 
channel of 70-foot bottom width, renew canal 
revetments, reconstruct and extend piers at 
upper entrance to 30-foot depth of water, and at 
proper time for increase of channel 
depth to 20 feet with bottom width of 
not less than 120 feet (increase in 
width and depth of channel approved 
Mar. 15, 1898). 
Anchorage basin just within lower entrance 
about one-half mile long, 800 feet wide; 
a mooring pier on its westerly side 2,000 
feet in length, and for purchase of 
necessary land. 
Princess Point Cutoff channel. 
General deepening, widening and straightening 
of channels and basins to provide 25-foot 
depth with additional overdepth at entrances, 
extend lower entrance breakwater, and 
necessary alteration or replacement of 
structures due to deepening channels. 
KNIFE RIVER HARBOR, MN (See Section 29 of Text) 
Dredging. 
Breakwater and modified channels. 
Construction of measures to correct the design deficiencies 
which results in unsatisfactory entrance and mooring conditions. 
LAC LA BELLE HARBOR, MI (See Section 30 of Text) 
Two parallel piers at the entrance, 
584 and 682 feet; an entrance channel 
between the piers 50 feet wide and 
12 feet deep, 820 feet long with a flared 
approach and inner canal 50 feet wide and 
10 feet deep and 730 feet long. 
Annual Report, 1881, 
p. 2082. 
H. Doc. 324, 60th Cong., 
1st Sess. 
Rivers and Harbors 
Committee Doc. 43, 72d 
Cong., 1st Sess. 
S. Doc. 19, 86th Cong., 
1st Sess.' 
H. Ex. Doc. 105 49th Cong., 
2d Sess. and Annual Report 
1887, p. 1977. 
H. Doc. 325, 60th Cong., 1st 
Sess. 
H. Doc. 835, 63rd Cong., 2d Sess. 
H. Doc. 55, 73rd Cong., 1st Sess.1 
H. Doc. 686, 77th Cong., 2d 
Sess. and Annual Report for 
1949. 
H. Doc. 463, 83d Cong., 2d Sess.1 
H. Doc. 446, 78th Cong., 2d 
Sess. Annual Report, 
1961, p. 1039. 
31-60

DETROIT, MICHIGAN DISTRICT 
TABLE 31-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Aug. 5, 1886 
Jul. 13, 1892 
Jun. 13, 1902 
Mar. 2, 1919 
Jul. 3, 1930 
Aug. 30, 1983 
Mar. 21, 1956 
Aug. 30, 1935 
Oct. 23, 1962 
Oct. 27, 1965 
Mar. 2, 1945 
Mar. 2, 1867 
Mar. 3, 1899 
Mar. 2, 1907 
Dec. 31, 1970 
Mar. 2, 1867 
Sep. 19, 1890 
Jul. 25, 1912 
Jul. 3, 1920 
LAKE ST. CLAIR, MI, CHANNELS(See Section 31 of Text) 
Two Dikes. 
Deepening Canal and Dredging Channel 
at Grosse Point. 
Second Canal for Downbound Vessels. 
21-Foot Depth in Grosse Pointe Channel 
for About 5.25 miles. 
25-Foot Depth Through Canals and Channel 
Through Lake St. Clair. 
Removal of Center Dike and Widening 
Channel to 700 Feet. 
Deepening Channel to 27.5 Feet and 
Abandonment of Channel above Mouth of Southeast 
Bend Cutoff Channel. 
LELAND HARBOR, MI (See Section 82 of Text) 
Entrance Channel Protected by Piers. 
Outer Breakwater, Anchorage Area. 
Approach Channel and Removal of North Pier. 
LEXINGTON HARBOR, MI (See Section 33 of Text) 
Approach Channel and Maneuver Area 
Protected by Breakwaters.' 
LITTLE LAKE HARBOR, MI (See Section 34 of Text) 
12-Foot Deep Channel From Lake Superior into 
Little Lake Breakwaters and Revetments. 
LUDINGTON HARBOR, MI (See Section 35 of Text) 
Entrance Piers. 
Pier Extension Reconstruction and Repairs 
to Existing Structures and Present 
Project Dimensions of Channel. 
Breakwaters, Shore Connections, and 
Removal of Outer Ends of the Two Inner 
piers. 
Deepen Channels and Widen Opening 
Between Breakwaters. 
MANISTEE HARBOR, MI (See Section 36 of Text) 
Entrance Piers. 
Extending Channel 8,000 Feet to Connect with 
Manistee Lake, and Further Pier Extension. 
Depth of 20 Feet in Outer Harbor 570 Feet Wide 
to Outer End of South Pier 18 Feet Deep in River, 
South Breakwater with Shore Connection, and 
Extend North Pier if Required. 
23-Foot Depths in Entrance Channel and 
21-Foot Depths in River Channel. 
Annual Report 1885, p. 2150. 
H. Doe. 297, 51st Cong., 2d Sees. 
H. Doe. 284, 56th Cong., 2d Sess. 
H. Doe. 188, 65th Cong., 1st Ses. 
H. Doc. 258, 70th Cong., 1st Ses. 
Rivers and Harbors Committee 
Doc. 3, 72nd Cong., 1st Sess. 
S. Doe. 71, 84th Cong., 1st Sess.' 
Rivers and Harbors Committee 
Doe. 28, 74th Cong., 1st Sess. 
H. Doe. 413, 87th Cong., 2d Beses. 
H. Doe. 301, 88th Cong., 2d Sess.' 
H. Doe. 446, 78th Cong., 2d Sess.' 
Annual Report 1867, p. 114'6 
H. Doe. 278, 54th Cong., 2d Sess. 
and Annual Report 1897, p. 2951. 
H. Doe. 62, 59th Cong., 1st Sess., 
and Rivers and Harbors 
Committee Doe. 8, 59th Cong., 
2d Sess.' 
H. Doe. 342, 91st Cong., 2d Sess.' 
Annual Report 1867, p. 115. 
Annual Report 1891, p. 2678. 
H. Doe. 599, 62d Cong., 2d Sess. 
S. Doe. 131, 71st Cong., 2d Sess. 
31-61

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 31-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Mar. 2, 1945 
Jul. 14, 1960 
Mar. 3, 1905 
Mar. 2, 1907 
Mar. 2, 1907 
Aug. 30, 1935' 
Aug. 26, 1937 
Oct. 23, 1962 
Dec. 31, 1968 
(Sec. 107 of 
1960 R& H) 
Mar. 2, 1867 
Aug. 11, 1888 
Jun. 25, 1910 
Aug. 30, 1935' 
Jul. 11, 1960 
Mar. 3, 1871 
Remove Old South Revetment, Construct New 
South Pier and Revetment, and Widen River 
Entrance Channel. 
Present Project Dimensions of Channel Through 
Outer Basin and River and Federal 
Participation in Cost of Replacing Maple 
Street Bridge. 
MANISTIQUE HARBOR, MI (See Section 37 of Text) 
Breakwaters and Outer Harbor. 
Present Location of West Breakwater and 
Pier at River Mouth. 
MANITOWOC HARBOR, WI (See Section 38 of Text) 
Breakwaters. 
Present project dimensions of channel through outer basin, 
removal of old north stub pier, and approach channel 
to a proposed city terminal south of shore end of south 
breakwater. 
Channel in river. 
Deepen Lake approach to 25 feet by 800 feet wide, deepen 
outer harbor to 25 feet, river channel to 23 feet to 
8th St., and Upper River Channel to 22 feet to Soo Line R.R. 
Dredge River Channel to 12 feet from Soo Line R.R. 
720 feet upstream. 
MARQUETTE HARBOR, MI (See Section 39 of Text) 
Breakwaters, 2,000 feet long. 
Extending the breakwater 1,000 feet. 
Additional 1,500-foot extension to breakwater and 
and removing a shoal in northerly part of harbor. 
Deepening harbor to 25 feet. 
Deepening harbor to 27 feet 
MENOMINEE HARBOR AND RIVER, MI AND WI 
(See Section 40 of Text) 
Entrance piers. 
H. Doc. 380, 77th Cong., 1st Seas. 
H. Doc. 358, 86th Cong., 2d Ses. 
H. Doe. 429, 58th Cong., 2d Seas. 
Annual Report 1908, p. 648, and 
Unpublished Report of Mar. 13, 
1908. Approved by Secretary of 
War, Apr. 3, 1908. 
H. Doc. 62, 59th Cong., 1st 
Sess., as modified by Rivers 
and Harbors Committee 
Doc. 3, 59th Cong., 2d Sess. 
Rivers and Harbors 
Committee Doc. 39, 73d 
Cong., 2d Sess. 
Rivers and Harbors 
Committee Doc. 80, 74th 
Cong., 2d Sess. 
H. Doc. 479, 87th Cong., 
2d Sess. 
Jun 1967 Detailed Project 
Report; Apr 1982 
Supplement'. 
H. Ex. Doe. 56, 39th Cong., 
2d Sees. pts. 1 and 2, and 
Annual Report, 1866, pp. 8 and 
77. 
Annual Report, 1889, pp. 272 
and 2021. 
H. Doe. 573, 61st Cong., 
2d Sees. 
Rivers and Harbors Committee 
Doc. 20, 72d Cong., 1st Seas. 
H. Doc. 154, 86th Cong., 
1st Sess.' 
Annual Report, 1867, P. 132. 
31-62

TABLE 31-B (Continued) 
DETROIT, MICHIGAN DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Jun. 13, 1902 
Mar. 4, 19183 
Jul. 3, 1930 
Aug. 30, 1935 
Mar. 2, 1945 
Jul. 14, 1960 
Jun. 27, 1967 
See. 107 
Aug. 30, 1852 
Mar. 3, 1883 
Mar. 2, 1907 
Sep. 22, 1922 
Aug. 30, 1935 
Mar. 2, 194518 
Jul. 14, 1960 
Oct. 23, 1962 
Feb. 24, 1835 ' 
Jul. 3, 1930 
Jul. 14, 19322s1 
Jun. 13, 1902 
Consolidation of project for harbor and river, and a channel 
18 feet deep. 
Partial restoration of work above bridge which had been 
eliminated by act of May 3, 1905. 
20-foot depth in channel and 18-foot depth in turning basin. 
21-foot depth in channel and turning basin and enlarge 
turning basin. 
Extend channel 12 feet deep to vicinity of Marinette Yacht 
Club. 
Deepen existing approach channel to 26 feet, entrance and 
river channels to 24 feet and enlarge turning basin. 
Deepen 1,100 feet of river channel generally north of 
Marinette Corp. facilities to 19 feet. 
MILWAUKEE HARBOR, WI (See Section 41 of Text) 
North pier.'2 
Inner 7,600 feet of breakwater.'2 
South pier. Extending north breakwater 1,000 feet. 
Extend north breakwater; a south breakwater; present project 
dimensions of inner entrance channel. 
Dredging a portion of outer harbor to 21-foot depth. 
Dredging river channels to 21-foot depth. 
Deepen South Menominee and Burnham Canals to 21 feet. 
Deepen an approach channel to 30 feet by 800 feet wide and 
300 feet wide through breakwater; deepen entrance channel 
28 feet through piers, outer harbor to 28 feet south of 
entrance channel, and a channel to 27 feet in Milwaukee 
River to Buffalo St., and in Kinnickinnic River to Chicago 
& North Western Ry. bridges. 
MONROE HARBOR, MI (See Section 42 of Text) 
9-foot channel, Protecting Revetments 
and Piers. 
21-foot channel, dikes and Turning Basin.o 
Modified Conditions of Local Cooperation 
Imposed by Act of Jul. 3, 1930 
MUSKEGON HARBOR, MI (See Section 43 of Text) 
Piers and Revetments. 
H. Doe. 419, 56th Cong., 
1st Sess. 
H. Doe. 171, 70th Cong., 
1st Sess. 
Rivers and Harbors 
Committee Doe. 28, 73d 
Cong., 2d Sess. 
H. Doe. 228, 76th Cong., 
1st Sess. 
H. Doe. 112, 86th Cong., 
1st Sess. 
Detailed Project Report 
Dec. 1960.1 
S. Doe. 175, 25th Cong., 
2d Bess. 
Annual Report 1881, 
p.2122. 
Annual Report 1906, 
p. 1752. [No prior survey 
or estimate affecting 
breakwater extensions.] 
H. Doc. 804, 66th Cong., 
2d Sess. 
H. Doe. 289, 72d Cong., 
1st Sess. 
S. Doe. 29, 76th Cong., 
1st Sess. 
H. Doe. 285, 86th Cong., 
2d Sess. 
H. Doc. 134, 87th Cong., 
1st Sess.' 
Annual Report 1872, p. 237. 
Rivers and Harbors Comm Doe. 
22, 71st Cong., 1st Sess., 
Rivers and Harbor Comm. Doc. 
12, 72d Cong., 1st Sess. 45, 
75th Cong., 1st Sess.' 
H. Doe. 104, 56th Cong., 2d Sess. 
31-63

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1988 
TABLE 31-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Mar. 3, 1925 
Aug. 80, 1985 
Oct. 23, 1962 
Oct. 28, 1962 
Aug. 2, 1882 
Jun. 25, 1910 
Jun. 25, 1910 
Aug. 26, 1987 
Aug. 2, 1882 
1888 
Aug. 30, 1935 
Mar. 2, 1867 
Mar. 3, 1873 
Jul. 5, 1881 
Jul. 13, 1892 
Mar. 25, 1907 
Breakwaters. 
Repairing Revetments around Car Ferry Slip. 
Channel deepening and present project 
dimensions of channel. 
Piers and Revetments. 
NEW BUFFALO HARBOR, MI (See Section 44 of Text) 
Entrance channel 10 feet deep by 
80 to 180 feet wide and 850 feet 
long to mouth of Galien River, new 
no. and so. breakwaters 1,305 and 
740 feet, respectively, deepening inner 
channel to Galien River to 8 feet and 80 
feet wide and 1,250 feet long. 
OCONTO HARBOR, WI (See Section 45 of Text) 
Piers, except for inner 300 feet of south pier 
and 250 feet of north pier built by city.' 
Present project dimensions of channel and 
turning basin. 
ONTONAGON HARBOR, MI (See Section 46 of Text) 
Channel 17 feet deep and 150 
feet wide through bar and 15 feet 
deep and 100 feet wide between piers, 
and pier maintenance. 
Modified project widths and provide 
inner basin. 
PENSAUKEE HARBOR, WI (See Section 47 of Text) 
Construction of slab pier 2,500 
feet long on the north side of 
the channel and dredging a channel 
100 feet wide and 10 feet deep. 
Extending pier to 10-foot contour 
(2,700 feet) and dredging to 10 feet 
below datum. (Datum elevation 580.69 feet) 
Dredging entrance channel 100 feet 
wide and 8 feet deep. 
PENTWATER HARBOR, MI (See Section 48 of Text) 
Piers and Revetments, Dredging. 
Piers and Revetments, Dredging. 
Piers and Revetments, Dredging. 
Piers and Revetments, Dredging. 
Present Project Depth of Channel 
H. Doe. 494, 67th Cong., 4th Seas. 
Rivers and Harbor Comm. Doc. 
64, 75th Cong., 1st Seas. 
H. Doe. 474, 87th Cong., 2d Seas.1 
H. Doe. 474, 87th Cong., 2d 
Seas. 
Annual Report 1881, p. 2066. 
H. Doe. 538, 61st Cong., 
2d Sess. Plan C.1 
H. Doe. 602, 61st Cong., 2d 
Seas. 
S. Committee print, 74th 
Cong., 2d Seas. 
H. Doe. No. 153, 
42d Cong., 3d Ses. 
R&HAct 
Aug. 2, 1882 
Modified 
H. Doe. No. 478, 
74th Cong., 2d Sess. 
H. Ex. Doe. 70, 39th Cong., 2d 
Sess. 
H. Ex. Doc. 70, 39th Cong., 2d 
Sess. 
H. Ex. Doc. 70, 39th Cong., 2d 
Seas. 
H. Ex. Doe. 70, 39th Cong., 2d 
Sm. 
H. Doc. 181, 39th Cong., 2d Sess.' 
31-64

DETROIT, MICHIGAN DISTRICT 
TABLE 31-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Mar. 2, 1945 
Mar. 3, 1879 
Mar. 2, 1945 
Jul. 11, 1870 
Aug. 14, 1876 
Aug. 30, 1935" 
Jul. 3, 195824 
Jun. 13, 1902 
Jun. 30, 1948 
Aug. 5, 1977 
Jun. 3, 1896 
Jun. 13, 1902 
Aug. 30, 1935 
Jul. 14, 1960 
Mar. 2, 1907 
POINT LOOKOUT HARBOR (AU GRES RIVER), MI 
(See Section 49 of Text) 
Breakwater, Anchorage Area, Channel Dredging. 
PORTAGE LAKE HARBOR, MI (See Section 50 of Text) 
Entrance Channel 18 Feet Deep Protected by 
Piers and Revetments. 
PORT SANILAC HARBOR, MI (See Section 51 of Text) 
Entrance Channel 12 Feet Deep, Anchorage Basin, 
Breakwater. 
PORT WASHINGTON HARBOR, WI 
(See Section 52 of Text) 
North pier and south basin.12 
North basin. 
North breakwater, removal of 650 feet of north pier, outer 
turning basin, present project dimensions of channel 
and basin and extension of south breakwater. 
Extending and raising of north breakwater and placing 
rubble along sides; removing 456 feet of south breakwater 
and dredging in outer basin. 
PORT WING HARBOR, WI (See Section 53 of Text) 
Construction of parallel piers and dredging. 
Dredging inner channels and abandonment of certain 
revetments and channels. 
Deauthorization of 50 feet of entrance channel 
widening. 
PRESQUE ISLE HARBOR, MI (See Section 54 of Text) 
Breakwater, 1,000 feet long. 
Shore extension, 216 feet long. 
For dredging and rubblemound extension 
to breakwater 1,600 feet long. Changed 
designation of project. 
Deepening harbor from 26 and 28 feet to 28 and 30 feet, 
respectively. 
RACINE HARBOR, WI (See Section 55 of Text) 
Breakwaters. 
H. Doc. 446, 78th Cong., 2d Sess. 
Annual Report 1879, p. 1634" 
H. Doc. 446, 78th Cong., 2d Sess. 
H. Ex. Doc. 28, 41st 
Cong., 2d Sess., 
and Annual Report, 
1879, p. 119. 
Annual Report, 1876, 
pt. 2, p. 379. 
H. Doc. 168, 72d Cong., 
1st Sess. and Rivers and 
Harbors Committee Doc. 
41, 74th Cong., 1st Sess. 
H. Doc. 446, 83d Cong., 
2d Sess.' 
H. Doc. 114, 56th Cong., 1st 
Sess. 
H. Doc. 668, 80th Congr., 2d 
Sess. 
H. Doc. 318, 54th Cong., 1st 
Sess., Annual Report for 
1903, pp. 474, 1823. 
H. Doc. 473, 72d Cong., 2d 
Sess. 
H. Doc. 145, 86th Cong., 
1st Sess. 
H. Doc. 62, 59th Cong., 
1st Sess., and Annual 
Report 1909, p. 1973. 
31-65

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1988 
TABLE 31-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Aug. 26, 1937 
Mar. 2, 1945 
Aug. 8, 1917 
Aug. 30, 19352,,2 
Jul. 3, 19582 
Oct. 23, 19622 
Jun. 25, 1910 
Jul. 3, 1930 
Aug. 26, 1937 
Jun. 20, 1938 
Sep. 3, 1954 
Oct. 23, 1962 
Oct. 27, 1965 
Remove shoals lakeward of harbor entrance, enlarge 
19-foot channel through outer basin and 19-foot channel in 
river. 
Present project dimensions of channel through outer basin 
and in river. 
ROUGE RIVER, MI(See Section 66 of Text) 
21-foot channel via the Shortcut Canal. 
25-foot channel at mouth of Old Channel, 
1,425 feet long and adjacent to latter, 
and 21-foot channel extending from 
junction of Old Channel and Shortcut 
Canal into Old Channel to Detroit, Toledo 
& Ironton R.R. Bridge. 
Old Channel; 100 feet wide from Peerless 
Cement Corp. to Junction with Shortcut 
Canal widened to 150 feet at 2 bends. 
25-foot channel over modified limits 
from Detroit River to Jefferson Ave. 
(via Shortcut Canal). 
SAGINAW RIVER, MI (See Section 57 of Text) 
Channel 200 feet wide, with depth of 18.5 
Feet in Bay and 16.5 Feet in River. 
Project Depth of 18.5 Feet Extended Up River 
to Saginaw 
Turning Basin. 
Present Project Channel Dimensions 
from Bay to Sixth Street Bridge in 
Saginaw. 
New Channel in Bay, 350 Feet Wide and 
24 Feet Deep from 24-Foot Contour to 
River Mouth, Project Depth of 24 Feet 
in River Channel Up to Detroit & Mackinac 
Railway Bridge, Project Depth of 22 Feet 
in River Channel Up to Sixth Street Bridge, 
Turning Basins at Essexville and Carrollton, 
and Elimination of Present Channel in Bay. 
Deepen Bay Channel, Deepen River Channel to 
Detroit & Mackinac Bridge, Extend 22-Foot 
Project Above 6th St. Bridge, Deepen 
Essexville Turning Basin, and Construct 
2 New Turning Basin. s 
Deepen River Channel to 25 Feet, from Detroit & 
Mackinac Bridge to New York Central Railroad 
Bridge. 
Rivers and Harbors 
Committee Doe. 46, 75th 
Cong., 1st Seas. 
H. Doe. 816, 77th Cong., 
2d Seas., and H. Doc. 255, 
78th Cong., 1st Sess. 
H. Doe. 1068, 64th Cong., 
2nd Sess." 
H. Doe. 125, 85th Cong., 1st Seas. 
H. Doe. 509, 87th Cong., 2d Sess.' 
H. Doc. 740, 61st Cong., 2d Seas. 
Rivers and Harbors Committee 
Doe. 30, 71st Cong., 2d Seas. 
Rivers and Harbors Comm Doc. 
21, 75th Cong., 1st Sess. 
H. Doe. 576, 75th Cong., 3d Sess. 
H. Doe. 500, 88rd Cong,, 2d Sess. 
H. Doc. 554, 87th Cong., 2d Sess. 
H. Doe. 240, 89th Cong.,lst Sess.' 
31-66

DETROIT, MICHIGAN DISTRICT 
TABLE 31-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Jul. 13, 1892 
Jul. 8, 1930 
Mar. 2, 1945 
Jul. 24, 1946 
Mar. 21, 1956 
Mar. 3, 1875 
Jun. 14, 1880 
Mar. 3, 1899 
Aug. 30, 1935 
Jun. 2, 1937 
Mar. 2, 1945 
Jul. 3, 1958 
Jul. 11, 1870 
Aug. 5,1886 
Jul. 13, 1892 
Jun. 13, 1902 
Jun. 13, 1902 
Mar. 3, 1907 
ST. CLAIR RIVER, MI (See Section 58 of Text) 
20-Foot Channel in the River. 
Deepen Channel to 25 and 26 Feet, and 
Compensating Works. 
Widening Channel at Southeast Bend 
to 700 Feet 
Widen and Deepen Southeast Bend and 
Improve Outlet of North Channel, 
St. Clair River. 
Deepen and Further Improve Channels in 
St. Clair River Between Limits of 27.1 
to 30 Feet to Provide Safe Navigation by 
Vessels with Drafts of 25.5 Feet. A Cutoff 
Channel in Canada of Southeast Bend and 
Abandon Old Southeast Iend Channels. 
ST. JOSEPH HARBOR, MI (See Section 59 of Text) 
Interior Revetments. 
Benton Harbor Canal.3 
Present Project Dimensions of Piers 
and a Turning Basin. 
Present Project Dimensions of 
Paw Paw River. 
Abandon Easterly 1,000 Feet of Channel 
Above West Line of 9th St. 
Turning Basin Above Mouth of Morrison 
Channel and Eliminate Turning Basin 
Near Mouth of Paw Paw River. 
Maintenance of Turning Basin Near Mouth 
of Paw Paw River. 
ST. MARYS RIVER, MI (See Section 60 of Text) 
Weitzel Lock (Replaced in 1943 by Mac 
Arthur Lock), Widen and Deepen 
Existing State Channel.2 
Poe Lock.' 
Dredging Through Shoals Above Falls 
and Shoals Below Falls Between Lower 
End of Canal and Upper Entrance Channel 
into Lake Nicolet (Formerly Hay Lake). 
Enlarging the Old Channel. 
Lake Nicolet and Neebish Channels Work 
in that Section of River Below Locks. 
David Lock Second Canal, and Emergency Dam. 
H. Doc. 207, 51st Cong., 2d Sess. 
H. Doc. 253, 70th Cong., 1st Seass. 
H. Doc. 809, 77th Cong., 1st Seas. 
H. Doc. 885, 80th Cong., 1st Sees. 
8. Doc. 71, 84th Cong., 1st Sees. 
H. Ex. Doc. 160, 43rd Cong., 
2d Seas., and Annual Report 
1875, pt. 1, p. 162. 
Annual Report 1880, pp. 2030, 
2081 and 2049, 2055. 
H. Doc. 307, 55th Cong., 2d Seas., 
and Annual Report 1898, p. 2496. 
Rivers and Harbors Comm Doc. 
52, 74th Cong., 1st Seas. 
H. Doc. 129, 76th Cong., 1st Sess. 
S. Doc. 95, 84th Cong., 2d Ses.1 
Report by Maj. O. M. Poe, Corps 
of Engineers, Not Published. 
H. Ex. Doe. 72, 49th Cong., 2d 
Seas. 
H. Ex. Doc. 207, 51st Cong., 
2d Seass., and Annual Report 
1891, p. 2810 
H. Doc. 138, 56th Cong., 2d 
Seas., and 215, 58th Cong., 3d 
Seas. 
H. Doc. 128, 56th Cong., 2d 
Seas. 
H. Do. 338, 59th Cong., 2d 
Seas. (Plan 3) 
31-67

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 31-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Mar. 3, 1909 
Jul. 25, 1912 
Mar. 4, 1915 
Sep. 22, 1922 
Jan. 21, 1927 
Jul. 3, 1930 
Jun. 26, 1934' 
Aug. 30, 1935 
Mar. 7, 1942 
Jun. 15, 1943 
Mar. 2, 1945 
Jul. 24, 1946 
Mar. 21, 1956 
Jul. 9, 1956 
Jun. 3, 1896 
Lease of Waterpower at Falls. Lease 
Entered Into with Michigan Northern 
Power Co. Provided for Construction of 
Remedial and Compensating Works. 
Fourth Lock (Renamed 'Sabin' Lock in 1943). 
Deepen Tailrace of Power Plant. 
Widen Upper Approach to Canals Through 
Vidal Shoals, Extend Anchorage and 
Maneuver Area Below Locks. 
Remove Round Island, Middle Ground 
Extension of Northwest Canal Pier, and 
Widen Channels Middle Neebish Route. 
Deepen Channels Throughout Downbound Route. 
Operation and Care of Canal and Locks 
Provided from War Department 
Appropriations for Rivers and Harbors. 
Widen Brush Point Turn and Channel from 
Brush Point to Point Louise. 
Construct New (Mac Arthur) Lock on Site of 
Former Weitzel Lock, Deepen Approach Channels 
to 27 Feet, and Reconstruct Approach Piers. 
Name 'Mac Arthur' Lock and Changed Name 
of 'Fourth' Lock to 'Sabin' Lock. 
Remove Bridge Island and Construct New 
Hydroelectric Power Plant. 
Replace Poe Lock at St. Marys Falls Canal 
with a New Structure 800 Feet Long, 100 Feet 
Wide and 32 Feet Deep, with Necessary 
Construction of Nose and Center Piers, and 
Widen and Deepen Channel Across Point Iroquois 
Shoals and in Lake Nicolet to Provide Wider 
Anchorage and Maneuver Areas in St. Marys 
River. 
Deepen to Provide a Project Safe Draft of 25.5 
Feet Over Full Width to Downbound and 2-Way 
Channels (Including Anchorage Areas) and Over 
Westerly 300-Foot Width of Upbound Middle 
Neebish Channel, When Levels of Lake Superior 
and Huron are at Their Respective Low-Water 
Datum. 
Repeal Authorization of Bridge as a Part of 
Project, Authorize Alteration With Cost to 
be Apportioned by Sec. 6, Truman Hobbs Act, 
June 21, 1940. 
SAUGATUCK HARBOR AND KALAMAZOO RIVER, 
MI (See Section 61 of Text) 
Entrance Channel, Piers and Revetments. 
H. Doc. 65, 62d Cong., 1st Sess. 
District Engineer Report, 
Oct. 29, 1920. 
H. Doc. 270, 69th Cong., 1st Sess. 
H. Doc. 253, 70th Cong., 1st Sess. 
River and Harbor Comm Doc. 
53, 74th Cong., 1st Sems. 
H. Doc. 218, 77th Cong., 1st Sess. 
H. Doe. 679, 78th Cong., 2d Sess. 
and H. Doe. 339, 77th Cong., 
1st Ses. 
H. Doc. 335, 80th Cong., 1st Ses. 
S. Doc. 71, 84th Cong., 1st Sess. 
None 
H. Doc. 912, 54th Cong., 1st Sess. 
Annual Report 1896, Vol. 2. 
Pt. 5, p. 2739 
31-68

TABLE 31-B (Continued) 
DETROIT, MICHIGAN DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Mar. 2, 1907 
Jun. 25, 1910 
Jul. 3, 1958 
Mar. 2, 1907 
Jan. 21, 1927 
Aug. 30, 1935 
Sep. 3, 1954 
Aug. 11, 1888 
Mar. 3, 1905 
Aug. 30, 1935 
Mar. 3, 1873 
Jul. 13, 1892 
Aug. 5, 1886 
Aug. 5, 1886 
Aug. 30,1935 
Nov. 7, 1945 
Deepening Entrance to 16 feet. 
Deepening Channel in River to 14 feet. 
SAXON HARBOR, WI (See Section 62 of Text) 
Provides for east and west breakwaters, 
an outer channel 10 feet deep, an inner basin 
and side channel 8 feet deep, and 
diversion of Oronto Creek to Parkers 
Creek by three short reaches of 
channel excavation and a levee. 
SHEBOYGAN HARBOR, WI (See Section 63 of Text) 
North breakwater. 
Preserving south pier as part of project, providing turning 
basin, and elimination of proposed south breakwaters. 
Present project dimensions of channel. 
Widen and deepen outer harbor entrance channel to 450 feet, 
widen and deepen river channel from present project limit 
to north side of Jefferson Ave. 
SOUTH HAVEN HARBOR, MI (See Section 64 of Text) 
Channel from Inner End of Piers to 
Highway Bridge.'2 
Present Dimensions of Piers and for a 
Turning Basin. 
Present Project Dimensions of Channel 
and Turning Basin 
STURGEON BAY AND LAKE MICHIGAN 
SHIP CANAL, WI (See Section 65 of Text) 
Breakwaters. 2 
Acquisition Qf the canal. 
TWO HARBORS, MN (See Section 66 of Text) 
Breakwater and dredging. 
Construction of two breakwater piers. 
Shore connection to east breakwater and 
dredging maneuvering area. 
Construct new east breakwater and 
enlargement of maneuvering basin. 
Annual Report 1907, p. 6416 
H. Doc. 635, 61st Cong., 2d Sess. 
River and Harbor Act 
H. Doc. 169, 85th Cong., 
1st Sess.,' Annual Report 
for 1965, p. 1025. 
H. Doc. 62, 59th Cong., 
1st Seas. 
H. Doc. 475, 68th Cong., 
2d Sees. 
Rivers and Harbors 
Committee Doc. 47, 74th 
Cong., 1st Sess. 
H. Doc. 554, 82d Cong., 
2d Sess.l 
No Prior Survey or Estimate. 
H. Doc. 119, 58th Cong., 2d Sess. 
Rivers and Harbors Comm Doc. 
9, 73d Cong., 1st Sess.' and 
Unpublished review Report of 
Chief of Engineers, Dated Dec. 
21, 1934. 
H. Ex. Doc. 34, 42d Cong., 
2d Seas. Annual Report, 
1872, p. 171. 
H. Ex. Doc. 106, 49th Cong., 
2d Sess. 
H.Ex.Doc. 94, 48th Cong., 
2d Sees. 
Annual Report for 1887, p. 
1952. 
Rivers and Harbors 
Comm. Doc. 17, 
72d Cong., 1st Sess 
H.Doc.805, 78th 
Cong.,2d Sess. 
31-69

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 31-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Jul. 14, 1960 Deepen harbor project depths from 26 and H.Doc.146, 86th 
28 feet to 28 and 30 feet, Cong., 1st Sess1 
respectively. 
WHITE LAKE HARBOR, MI (See Section 67 of Text) 
Mar. 2, 1867 New Channel, with Piers and Revetments. Unpublished Survey Report 
of 1868. 
Mar. 3, 1878 New Channel, with Piers and Revetments. Unpublished Survey Report 
of 1868. 
Jul. 5, 1884 New Channel, with Piers and Revetments. Unpublished Survey Report 
of 1868. 
Jul. 13, 1892 New Channel, with Piers and Revetments. No Prior Survey or Estimate.3 
Mar. 2, 1907 Present Project Depth of Channel. 
RED RUN DRAIN-LOWER CLINTON RIVER, MI 
(See Section 75 of Text) 
Dec. 30, 1970 Flood control and major drainage improvements to H. Doc. 431, 91st Cong., 2d Seas. 
Red Run Drain and Lower Clinton River. 
SAGINAW RIVER, MI FLOOD CONTROL 
(See Section 76 of Text) 
Jul. 3, 1958 Flood Control Improvements to Saginaw River H. Doc. 346, 84th Cong., 2d Seas.1 
and its Tributaries Including Tittabawassee, 
Shiawassee, Flint, and Cass Rivers. 
SEBEWAING, SEBEWAING RIVER, MI 
(See Section 77 of Text) 
Aug. 18, 1941 Enlarging Present Channel of Sebewaing River, H. Doc. 286, 76th Cong.; 1st Sease 
Altering Railroad and Highway Bridges, 
Removal of Dike. 
Contains latest published map. 
'Including Emergency Relief Administration Work 
authorized May 28, 1935. 
'Included in Public Works Administration Program 
September 6, 1933. 
4This modification deauthorized August 5, 1977 under 
Section 12, Public Law 93-251. 
6Administrative Act, Section 4. 
'Public Law 568, 82d Congress. 
7Public Law 388, 87th Congress. 
'This portion inactive. 
'Permanent Appropriations Repeal Act. 
'oTransfer completed June 1962. 
"Amended 1868, 1879, 1892. 
"Completed under previous project. 
s"Included in Public Works Administration Program 
January 3, 1934. 
"Inactive portion; removal of 200 linear feet of north pier, 
widening inner 200 feet of channel through outer basin, and 
closing gap in north shore connection of breakwater. 
16Latest published map is in Annual Report 1914, p.2974. 
16Latest published map in Annual Report 1914, p. 2914. 
17Superceded by Act of October 23, 1962. 
18sUncompleted portion was deauthorized in 1977 (dredging 
Milwaukee River from Buffalo St. Bridge to North 
Humboldt Ave. Bridge). 
19Modified by Act of June 10, 1872. 
3 Riprapping of protecting dikes portion of project is 
inactive. 
21War Department Appropriations Act. 
"Latest published map is in House Document 588, 64th 
Cong., 1st Sess. 
"Work recommended in H. Doc. 588, 64th Cong., 1st Sess. 
"Deauthorized in 1977. 
"Contains latest published maps. See also map with 
Rivers and Harbors Committee Doc. 19, 72d Cong., 1st Seas. 
"Except for dredging 25-foot channel to 1,150 feet 
upstream of mouth in old channel, work authorized in this Act 
is considered inactive. 
'7This modification deauthorized August 5, 1977 under 
Section 12, Public Law 93-251. 
"Completed under previous projects. Public Law 130, 
75th Cong., 1st Seas. 
"Latest published map is in H. Doc. 2053, 64th Cong., 2d 
Seas. 
31-70

TABLE 31-C 
DETROIT, MICHIGAN DISTRICT 
FEATURES OF EXISTING PROJECT 
Project 
Datum Planes 
Length Miles Used by Above Mean 
of from Upbound Water Level 
Channel Mouth or Down- Project Project at Father 
of bound Width Depth Point, Quebec Year 
Name of Channel (Feet) River Vessels (Feet) (Feet) (Feet) Complete 
DETROIT RIVER, MI (SEE SECTION 12 OF TEXT) 
Channel North of Belle Isle1 22 
Channel at Head of Detroit River 
Miscellaneous Shoals and 
Obstructions, Belle Isle to 
Fighting Island Channel 
Fighting Island Channel 
Ballards Reef Channel North of 
Junction with Livingstone Channel 
Livingstone Channel Upper 
Livingstone Channel Lower: 
CS 260+00 to 368+87 
CS 368+87 to 492+00 
East Outer Channel 
Misc., Shoals and Obstructions, 
Detroit River to Pelee Passage 
Pelee Passage Shoal 
Amherstburg Channel: 
Upper Section, Ballards 
Reef Channel 
Middle Section 
Lower Section, Hackett Range 
West Outer Channel 
Trenton Channel: 
Wyandotte Reach 
Trenton Reach (Upper) 
Trenton Reach (Lower) 
Grosse Ile Shoal 
.30 
38,800 32 
44,500 25 
24,800 17 
12,200 12 
Both 
Both 
Both 
Both 
Both 
26,000 10 Down 
10,887 
12,313 
42,000 
5 Down 
Both 
Both 
200 
800 
800 
600 
450 
450,800 
800-1,200 
1,200 
- - Both 
- - Both 
6,500 
12,000 
24,000 
21,000 
31,500 
5,100 
600 
600 
10 
17 
14 
14 
Up 
Up 
Up 
Down 
Local 
Local 
Local 
Local 
21.0 571.3 
28.5 571.5-570.9 
28.5 570.9-570.3 
28.5 
28.5 
569.8 1962 
569.8 1963 
27.7 569.8-568.6 1964 
29.0 
29.0 
38.5 
- 28.5-29.58 
- 29.5 
600 
600 
6000 
800 
300 
300 
250-300 
27.5 
21.27.54 
21.28.56 
22.0 
27.0 
28.0 
28.0 
20.0 
568.6 
568.6 
568.6 
568.6 1962 
568.6 1964 
569.8-569.5 
569.5-568.9 
568.9-568.6 
568.6 
569.9-569.7 
569.7-569.6 
569.6-568.8 
569.8 
ST. CLAIR RIVER, MI (SEE SECTION 58 OF TEXT) 
Channel at Foot of Lake Huron 
Channel North of Blue Water Bridge 
Port Huron to Stag Island 
Widening at Upper and Lower 
Ends of Stage Island 
St. Clair to Russel Island 
Russel Island to Southeast Bend 
Southeast Bend CS 324+00 
to 250+00 
Cutoff Channel 
North Channel Outlet 
26,500 44 
4,100 39 
38,000 
37,600 
77,000 
20,600 
7,400 
30,300 
8,000 
39 
31 
24 
11
5 
Both 
Both 
Both 
Both 
Both 
Both 
Both 
Both 
Small Craft 
800 
800 
800 
900-1,000 
1,000 
700-1,000 
700 
700 
100 
30.0 576.8-576.5 1961 
30.0 576.4-576.1 1962 
30.0 
27.4 
27.3 
17.2 
576.4-576.1 
574.9-573.8 
573.8-572.4 
572.4-572.1 
27.1 573.1-572.0 
27.1 572.1-571.7 
10.0 571.7 
1961 
1962 
1962 
1962 
1962 
1962 
1962 
1This is a Side Channel. 1This is a Side Channel. 
'Extends from Deep Water Near Windmill Point to a Point Opposite Fairview Slip, about 3,000 Feet. 
3Project Depth 29.5 Feet over Rock Shoals and 28.5 Feet over other than Rock Shoals. 
'Project Depth 21 Feet in Easterly 300-Foot Width of Channel and 27.5 Feet in Westerly 300-Foot Width. 
bProject Depth 21 Feet in Easterly 300-Foot Width of Channel and 28.5 Feet in Westerly 300-Foot Width. 
*Project Complete Except for Work Authorized by River and Harbor Act of 1950. 
31-71 
1964 
1964 
1964 
1961 
1961 
1964 
1960 
1960 
1960 
1929 
19644 
1964 
1941 
1904

TABLE 31-D 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1988 
ST. MARYS RIVER, MI: EXISTING PROJECT 
(See Section 60 of Text) 
Lock Davis Sabin MacArthur New Poe 
Miles Above Mouth 47 47 47 47 
Clear Width of Chamber Feet 80 80 80 110 
Length Between Gate Quoins Feet 1,350 1,350 800 1,200 
Lifts Feet 21.7 21.7 21.7 21.7 
Depth Over Upper Breast Walls' Feet 24.8 24.3 31 32 
Depth Over Lower Breast Walls' Feet 23.1 23.1 31 32 
Foundation Rock Rock Rock Rock 
Type of Construction Concrete Concrete Concrete Concrete 
Estimated Cost $6,200,00s $3,275,000 $12,909,440 $39,000,000 
Actual Cost $2,200,000' $1,750,000' $12,718,806',7 $34,813,066 
Completed (Open to Commerce) Oct. 21, 1914 Sep. 18, 1919 Jul. 11, 1943 Jun. 26, 1969 
Emergency Dam for South Canal North Canal 
Miles Above Mouth 47 47 
Estimated Cost -* $300,000 
Type Steel Stoplogs Recessed Steel Stoplogs Recessed 
Into Lock Masonry Into Lock Masonry 
Cost Completed' $169,224e 
Year Completed 1948 1922 (Modified 1963) 
'At low water datum 599.5 above and 577.8 below. 
'Includes Cost of North Canal. 
'Includes cost of canal excavations to provide necessary approaches to lock, canal walls, piers, and emergency dam, 
$662,919. 
4Excludes cost of deepening and enlarging South Canal, $1,653,378. 
'Excludes cost of 'Excludes cost North Canal, p,572,611. of canal excavations to provide necessary approaches to lock, canal walls, piers, and emergency dam, 
$662,919. 
Excluding cost of lower guard gates which were never installed. 
'Including engineering office, and inspection. 
'Not separable from cost of locks. 
Note: Limiting draft to locks is determined by depth over breast walls. 
31-72

DETROIT, MICHIGAN DISTRICT 
FOX RIVER WI: LOCKS AND DAMS 
TABLE 31-E (See section 15 of Text) 
Depth At 
Normal Pool 
Miles Avail- Lower 
from Die- Clear able Breast Miter Character Kind 
Green Nearest tance Width Length Lift Wal Sill of of Type of 
Name of Lock and Dam Bay Town (miles) (feet) (feet) (feet) (feet) (feet) Foundation Dam Construction 
DePere locks 7.1 DePere - 36.0 146.0 8.9 10.3 12.0 Rock - Concrete 
DePere dams 7.2 DePere - - - - - - Rock Fixeds3 Concrete 
Little Kaukauna lock s 18.0 DePere 6 36.0 146.0 7.2 8.0 9.5 Clay - Concrete 
Little Kaukauna dams 18.1 DePere 6 - - - - - Clay and gravel Fixed" Piers and conc 
Rapide Croche locks 192 Wrightstown 2 36.0 146.0 8.8 8.8 9.3 Rock - Concrete 
Rapide Croche Dams 19.8 Wrightstown 2 - - - - - Rock Fixeds Concrete 
Kaukauna fifth locks 22.8 Kaukauna - 35.6 144.0 9.1 6.7 9.3 Rock - Composite 
Kaukauna fourth lock' 28.1 Kaukauna - 36.6 144.1 10.2 6.9 6.0 Rock - Stone masonry 
Kaukauna third locks 23.3 Kaukauna - 30.6 144.0 102 6.9 6.3 Rock - Stone masonry 
Kaukauna second locks 23.4 Kaukauna - 35.0 144.0 9.6 6.0 6.0 Rock - Stone masonry 
Kaukauna first lock' 23.6 Kaukauna - 35.1 144.4 11.0 6.9 6.0 Rock - Stone masonry 
Kaukauna Dam' 24.0 Kaukauna - - - - - - Rock Fixed" Concrete 
Kaukauna guard lock 24.0 Kaukauna - 40.0 - - 9.4 - Rock - Stone masonry 
Little Chute combined lock: 
Lower 24.4 Little Chute 1 35.4 146.5 10.9 6.0 8.6 Rock - Stone masonry 
Upper 25.4 Little Chute 1 36.3 144.1 10.6 7.6 6.0 Hardpan - Stone masonry 
Little Chute second lock' 26.4 Little Chute - 35.0 144.2 13.8 8.0 6.1 Rock - Stone masonry 
Little Chute first (guard) locks 26.5 Little Chute - 35.4 - - 6.6 - Rock - Stone masonry 
Little Chute Dam' 26.6 Little Chute - - - - - - Rock Fixed* Concrete 
Cedars lock' 27.3 Little Chute 1 35.0 144.0 9.8 6.8 7.3 Rock - Stone masonry 
Cedars Dams 27.4 Little Chute 1 - - - Rock Fixed* Concrete 
Appleton fourth lock' 30.7 Appleton 1 35.0 144.0 7.6 8.1 7.9 Rock - Stone masonry 
Appleton lower dam' 30.9 Appleton 1 - - - - - Rock Fixeds Concrete 
Appleton third lock' 31.3 Appleton - 35.0 144.0 8.7 6.0 8.6 Rock - Stone masonry 
Appleton second locks' 31.6 Appleton - 35.1 144.6 9.6 6.9 6.0 Clay - Stone masonry 
Appleton first locks 31.9 Appleton - 35.0 144.7 10.0 6.6 6.0 Rock - Stone masonry 
Appleton upper dam 32.2 Appleton - - - - - - Rock Fixed' Concrete 
Menasha locks' 37.0 Menasha - 35.4 144.0 8.5 7.2 8.0 Clay - Composite 
Menasha Dams 37.8 Menasha - - - - - - Hardpan Fixeds Concrete 
Year 
Com- Actual 
plete Cost 
1986 $229,308 
1929 209,536 
1938 362,427 
rete 1926 179,898 
1934 228,738 
1980 118,975 
1898 18,3106 
1879 37,586 
1879 89,948 
1908 24,313 
1883 88,704 
1931 123,763 
1891 12,630 
1879 102,304 
1879 - 
1881 48,555 
1904 7,8176 
1932 82,554 
1888 34,972 
1933 84,973 
1907 40,893 
1934 73,903 
1900 32,238 
1901 22,940 
1884 36,004 
1940 151,558 
1899 19,3266 
1937 84,686 
'Depth shown is on breast wall, which is controlling 
depth for upper pool. 
")riginal structure built prior to assumption of 
control by United States on Sep. 18, 1872. 
'Provided with sluices. 
'Flash boards used. 
'Partially rebuilt. 
31-73

TABLE 81-F 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1988 
RECONNAISSANCE & CONDITION SURVEYS 
Name of Project Date Survey Conducted 
Algoma Harbor, MI 
Alpena Harbor, MI 
Bayport Harbor, MI 
Beaver Bay, MN 
Belle River, MI 
Big Suamico River, WI 
Black River (PH), MI 
Caseville Harbor, MI 
Chippewa Harbor, MI 
Cornucopia Harbor, WI 
Grays Reef Passage, MI 
Les Cheneaux Island Channels, MI 
Mackinaw City Harbor, MI 
Petoska Harbor, MI 
Pine River, MI 
Port Austin Harbor, MI 
St. James Harbor, MI 
Sebewaing River, MI 
Tawas Bay Harbor, MI 
Traverse City Harbor, MI 
Two Rivers Harbor. WI 
Washington Island Harbor, WI 
July 1988 
October 1982 
June 1983 
June 1983 
May 1983 
February 1983 
April 1983 
July 1988 
July 1983 
June 1983 
August 1983 
August 1983 
September 1983 
September 1983 
May 1983 
August 1983 
August 1983 
April 1983 
November 1982 
September 1983 
May 1983 
May 1983 
31-74 
_ __ __ 
-- -- I

DETROIT, MICHIGAN DISTRICT 
TABLE 31-G OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost To September 30, 1983 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Algoma Harbor, MI 1981 205,0101 893,142 
Alpena Harbor, MI 1980 337,3942 409,425 
Bayport Harbor, MI 1975 93,597 39,189 
Bayfield Harbor, WI 1979 183,855 64,214 
Belle River, MI 1980 24,301 69,159 
Beaver Bay, MN 1982 293,000 1,150 
Big Suamico River, WI 1975 20,243 128,338 
Black River (P.H.), MI 1982 830,1658 495,696 
Black River (Alcona Co.), MI 1907- 
Bolles Harbor, MI 1982 426,4134 2,053,030 
Caseville Harbor, MI 1981 587,314 93,934 
Cedar River Harbor, MI 1982 215,000- 
Chippewa Harbor, Isle Royale, MI 1959 125,629 7,740 
Cornucopia Harbor, WI 1982 462,653 694,198 
Forestville, MI 1969 -- 
Grand Marais Harbor, MI 1980 1,055,871 1,671,210 
Grays Reef Passage, MI 1970 190,521 646,657 
La Pointe Harbor, WI 1981 130,874 64,744 
Les Cheneaux Islands Channels MI 1980 399,478 284,533 
Little Bay De Noc, Gladstone Harbor, MI 1966 332,832 54,86 
Lutsen Harbor, MN 1982 357,000 
Mackinac Island Harbor, MI 1969 229,0586 71,469 
Mackinaw City Harbor, MI 1969 136,2866 43,117 
Northport Harbor, MI -.- 
Petoskey Harbor, MI 1979 118,239 320,672 
Pine River, MI 1980 13,649 29,452 
Port Austin Harbor, MI 1980 1,128,334 1,175,312 
St James, Beaver Island, MI 1957 49,1717 44,948 
St Joseph River, MI 1975 54,555 19,185 
Sebewaing River, MI 1982 35,573 2,266,902 
Tawas Bay Harbor, MI 1978 1,954,821 14,195 
Traverse City Harbor, MI 1976 866,579 114,425 
Two Rivers Harbor, WI 1982 418,3778 6,393,560' 
Washington Island, WI 1950 62,838 45,104 
Whitefish Pointe, MI 1981 771,639 213,193 
lncludes $92,774 for previous projects. 
'Includes $18,889 for previous projects. 
1Includes $349,921 Contributed Funds. 
+Includes 55,000 Contributed Funds. 
Excludes Contributed Funds of $105,004. 
*Excludes Contributed Funds of $186,286. 7Excludes Contributed Funds of $7,500. 
'Includes $58,057 for rehabilitation funds and $212,857 for previous projects. 
'Includes $33,118 for previous projects. 
31-75

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 31-H OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost To September 80, 1983 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Grand River, Grandville, MIl 1966- 
Grand River, Lansing, MI 1971 7,300 - 
Kalamazoo River (Battle Creek) MIs 1975 4,471,2385 - 
Kalamazoo River (Kalamazoo) MI 1975 421,466 - 
IKawkawlin River, MIs 1971 1,204,559' 
Mount Clemens, Clinton River, MIS 1958 1,186,008- 
Upper River Rouge, MI6 1968 7,935 - 
River Rouge, MI 1981 81,960,882 - 
'Awaiting Appropriation of Funds. 
2Includes $108,335 Contributed Funds. 
aCompleted. 
'Includes $204,559 Contributed Funds. 
5Includes $202,996 Contributed Funds. 
*Planning indefinitely suspended due to lack of local cooperation. 
31-76

TABLE 81-I D 
Project 
Black River Harbor, MI 
(Aug 80, 1985 R&H Act) 
Detroit River, Trenton ChnL, MI 
(May 17, 1950 R&H Act) 
Grand Haven Harbor, MI 
(Mar 2,1945 R&H Act) 
Grand River at Grandville, MI 
(Oct 27, 1965 Flood Control Act) 
Kewaunee River, WI 
(1960 R&H Act) 
Lansing, (Grand River), MI 
(Jul 8, 1958 Flood Control Act) 
Pentwater Harbor, MI 
(Jul 18, 1892 R&H Act) 
Rogers City Harbor, MI 
(Jun 25, 1910 R&H Act) 
Rouge River, MI 
(Oct 28, 1962 R&H Act) 
Rouge River, MI 
(Jul 3, 1958 R&H Act) 
Rouge River, MI 
(Aug 80,1985 R&H Act) 
St. Clair River Compensating Works, MI 
(Jul 8, 1980 R&H Act) 
South Milwaukee Harbor, WI 
(1886 Flood Control Act) 
St. Marys River (MacArthur Lock 
Guard Gates), MI 
(Mar 7,1942 R&H Act) 
DETROIT, MICHIGAN DISTRICT 
EAUTHORIZED PROJECTS 
For Last 
Full Report 
See Annual Date 
Report For Deauthorized 
1976 Nov 1977 
1976 Aug 1977 
1976 Nov 1977 
1966 Nov 1977 
1976 Aug 1977 
1971 Jun 1981 
1976 Nov 1977 
1926 Aug 1977 
1976 Aug 1977 
1976 Aug 1977 
1976 Aug 1977 
1976 Aug 1977 
1906 Aug 1977 
1977 Oct 1978 
Contributed 
81-77 
I 
Federal 
Funds 
Expended 
0
0
0
0
0 
7,000 
0 
5,892 
22,000 
12,000 
0
0
0
0 
Contributed 
Funds 
Expended 
0
0
0
0
0
0
0
0
0
0
0
0
0
0

BUFFALO, N.Y., DISTRICT* 
The district comprises northern Ohio, northwestern River, with their tributary drainage basins from boun- 
Pennsylvania and western and northern New York, em- dary between the states of Ohio and Michigan to interbracing 
U.S. waters of Lake Erie exclusive of small por- national boundary line east of Frontier, New York. 
tion of western end, Lake Ontario, and St. Lawrence 
IMPROVEMENTS 
Navigation Page 
1. Ashtabula Harbor, Ohio ................... 32-2 29. Other authorized beach erosion 
2. Barcelona Harbor, N.Y ................... 32-2 control projects .......................... 32-12 
3. Black Rock Channel and 30. Beach erosion work under 
Tonawanda Harbor, N.Y ................. 32-2 special authorization.....................32-12 
4. Buffalo Harbor, N.Y.......................32-3 Flood Control 
5. Cape Vincent Harbor, N.Y.................32-3 31. Cayuga Creek, Cheektowaga, N.Y ........ 32-13 
6. Cattaraugus Harbor, N.Y..................32-4 32. Cuyahoga River Basin, Ohio ............. 32-13 
7. Cleveland Harbor, Ohio ................... 32-4 33. Dansville and vicinity 
8. Conneaut Harbor, Ohio ................... 32-5 Canaseraga Creek, N.Y...................32-13 
9. Dunkirk Harbor, N.Y......................32-5 34. Ellicott Creek, N.Y ...................... 32-13 
10. Erie Harbor, Pa. .......................... 32-5 35. Euclid Creek, Cleveland, Ohio.............32-14 
11. Fairport Harbor, Ohio...................... 32-6 36. Mt. Morris Lake, N.Y., 
12. Geneva-on-the Lake, Ohio.................32-6 Genesee River........................... 32-14 
13. Huron Harbor, Ohio ...................... 32-7 37. Point Place, Toledo, Ohio ................ 32-15 
14. Irondequoit Bay, N.Y......................32-7 38. Reno Beach - 
15. Lorain Harbor, Ohio ...................... 32-7 Howard Farms Area, Ohio ............... 32-15 
16. Ogdensburg Harbor, N.Y ................. 32-8 39. Scajaquada Creek, N.Y .................. 32-15 
17. Oswego Harbor, N.Y ..................... 32-9 40. Inspection of completed 
18. Port Clinton Harbor, Ohio ................ 32-9 flood control projects......................32-16 
19. Rochester Harbor, N.Y ................... 32-9 41. Other authorized flood 
20. Rocky River Harbor, Ohio.................32-9 control projects .......................... 32-16 
21. Sandusky Harbor, Ohio .................. 32-10 42. Flood Control work under 
22. Toledo Harbor, Ohio......................32-10 special authorization.....................32-16 
23. West Harbor, Ohio ........................ 32-10 Deauthorized Projects 
24. Reconnaissance and condition surveys .... 32-11 43. Deauthorized projects ..................... 32-16 
25. Other authorized navigation projects ...... 32-11 General Investigations 
26. Navigation work under 44. Surveys..................................32-16 
special authorization ..................... 32-11 45. Collection and study of basic data........32-16 
Beach Erosion Control 46. Advance Engineering & Design .......... 32-16 
27. Lakeview Park, Lorain, Ohio ............. 32-11 
28. Presque Isle Peninsula, Erie, Pa.......... 32-11
32-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Navigation 
1. ASHTABULA HARBOR, OHIO 
Location. On south shore of Lake Erie, at mouth of 
Ashtabula River, 59 miles easterly from Cleveland, 
Ohio. (See NOAA Nautical Chart 14836.) 
Previous Projects. For details see page 1963 of 
Annual Report for 1915, and page 1593 of Annual 
Report for 1938. 
Existing Project. For description see pages 1297- 
99 of Annual Report for 1966. Federal cost of 
completed project is $12,240,147. Non-Federal costs of 
$5,743,000, including contribution of $47,000, were for 
construction of access roads, docks, storage and 
handling facilities and dockside dredging. See Table 
32-B for authorizing legislation. 
Local cooperation. Fully complied with. Local 
interests contributed $47,000 for work authorized by 
1936 and 1970 acts. 
Terminal facilities. There are 16 piers and 
wharves. One facility is owned by city of Ashtabula 
and one is owned by Coast Guard. Ten facilities are 
along banks of Ashtabula River and six are on 
southside of outer harbor. Eleven terminals have 
railroad connections and six have mechanicalhandling 
facilities. Facilities are considered adequate 
for existing commerce. (See Port Series No. 42, revised 
1972, Corps of Engineers.) 
Operations and results during fiscal year. 
Major Rehabilitation: Contract operations, initiated 
in June 1981, for rehabilitation of approximately 3,692 
feet of the east breakwater and 3,888 feet of the west 
breakwater, were completed in August 1982. The 
rehabilitation consisted of placing over 205,000 tons 
of armor, underlayer, and bedding stone on the slopes 
and rebuilding the structures to their design height. 
Total construction cost was $5,770,717. Finalization 
of contract costs resulted in an expenditure of $55,760 
in FY83. Maintenance: Miscellaneous inspection 
services and condition surveys by Government plant 
and hired labor cost $27,401. Expenditure of $55,000 
was attributed to the permanent lay-up of the U.S. 
hopper dredge Hoffman. Removal of 80,000 cubic 
yards of shoaled material, by contract, cost $230,685. 
Adjustment of costs for contract to test particle size 
and specific gravity resulted in a credit of $1,000. 
Engineering efforts cost $30,518. Subsurface 
exploration at Diked Disposal facility, by contract, 
cost $62,413. Aerial photographs of diked disposal, by 
contract, cost $3,984. Environmental testing and an 
environmental report, by contract, cost $8,000 and 
$63,505, respectively. In-house engineering costs for 
administering contracts and accomplishing plans 
and specifications for new dike construction were 
$193,329. 
2. BARCELONA HARBOR, N.Y. 
Location. On south shore of Lake Erie about 17 
miles southwesterly of Dunkirk, N.Y. and 29 miles 
northwesterly of Erie, Pa. (See NOAA Nautical Chart 
14823.) 
Previous projects. Adopted by July 4, 1936, River 
and Harbor Act. Only information available is in 
index to report of Chief of Engineers under title 
"Portland Harbor, N.Y." 
Existing Project. For description of existing 
project see page 1506 of Annual Report for 1961. 
Actual costs for new work for completed project were 
$1,124,286. Non-Federal costs of $60,000 were incurred 
by local interests. Of this amount, $7,500 was a cash 
contribution and remainder was for providing 
necessary lands and construction of public wharf. 
Existing project was authorized by the 1945 River and 
Harbor Act (H. Doc. 446, 78th Cong., 2nd sess.). 
Local cooperation. Fully complied with. Local 
interests contributed $7,500. 
Terminal facilities. Facilities consist of private 
docks for recreational craft and privately owned 
servicing and storage handling facilities for 
recreational and other small craft. 
Operations and results during fiscal year. 
Maintenance: Condition surveys by Government 
plant and hired labor cost $71. In-house engineering 
effort cost $87,812 for model study and project 
deficiency study. 
3. BLACK ROCK CHANNEL AND 
TONAWANDA HARBOR, N.Y. 
Location. Improvement is essentially that of upper 
13.5 miles of Niagara River from its head at Lake Erie, 
Buffalo, N.Y., to and including Tonawanda Harbor, 
N.Y. It comprises improvements formerly designated 
by three titles: viz, Lake Erie entrance to Black Rock 
Harbor and Erie Basin, N.Y., Black Rock Harbor and 
Channel, N.Y., and Tonawanda Harbor and Niagara 
River, N.Y. (See NOAA Nautical Chart 14832.) 
Previous projects. For details see items 5 and 7, 
page 1970 of Annual Report for 1915, and page 1612 of 
Annual Report for 1938. 
Existing project. For description of existing 
project and Federally owned Black Rock ship lock, see 
page 1548 of Annual Report for 1962. Improvements of 
guide pier at Black Rock lock, as authorized by 1935 
act was deauthorized by Congress in August 1977. 
Cost for completed portion of new work is $10,457,093. 
Enlarging of existing 21-foot turning basin and 
deepening lower 1,500 feet of Tonawanda inner 
harbor from 16 to 21 feet, authorized by the 1954 act, 
was deauthorized by Congress in May 1981, and is 
excluded from foregoing cost. Estimated cost (1961) of 
this portion is $339,000. Non-Federal costs are 
estimated at $1,540,000 for costs incurred by New 
York State for construction of Erie Basin and 
protecting breakwater, and construction and 
extension of Bird Island pier, and by other local 
interests for relocation of utilities. See Table 32-B for 
authorizing legislation. 
32-2

BUFFALO, N.Y. DISTRICT 
Local cooperation. Fully complied with. 
Terminal facilities. Two facilities are along 
upstream end of channel. Below Black Rock lock and 
at Tonawanda Harbor there are 13 privately owned 
terminals. There are two State-owned barge canal 
terminals at Tonawanda, N.Y., and several marine 
service and supply docks for recreational and other 
small craft. The Corps owns a wharf adjacent to Black 
Rock Lock which is private. Ten terminals have 
railroad connections and six mechanical-handling 
facilities. Facilities considered adequate for existing 
commerce. (Port Series No. 41, revised 1971, Corps of 
Engineers.) 
Operations and results during fiscal year: 
Operation and care (Black Rock Lock): Lock was in 
operation 280 days and closed for underwater 
cleaning and repairs from January 1 through April 3, 
1983. Ordinary maintenance and repair of structures 
and grounds were accomplished throughout the year 
by Government plant and hired labor. Total costs of 
$820,815 were distributed as follows: Operation and 
care: operation of lock, ordinary maintenance and 
repair $297,776; security service maintenance of 
grounds $40,992; miscellaneous inspection and 
condition surveys, project supervision, real estate, 
and support of Water Control Center $203,524; 
maintenance (structure repairs) by U.S. derrickboat 
McCauley at Bird Island Pier, fenderings, and lock 
gates cost $180,581. Clearing and snagging in project 
channels by Government plant and hired labor cost 
$7,206. Contract for replacement of lock building 
windows and doors was finalized at a cost of $2,075. 
Expenditure of $25,000 was attributed to the 
permanent lay-up of U.S. hopper dredge Hoffman. 
Engineering in-house effort on installation of 
windows and doors at the lock, repairs to fenders on 
lockwall, and repairs to lock watering pumps cost 
$65,661. 
4. BUFFALO HARBOR, N.Y. 
Location. At eastern end of Lake Erie, at head of 
Niagara River, 176 miles easterly from Cleveland 
Ohio. (See NOAA Nautical Charts 14820 and 14833.) 
Previous projects. For details see page 1967 of 
Annual Report for 1915 and page 1606 of Annual 
Report for 1938. 
Existing Projects. For description see page 1368 
of Annual Report for 1963. In addition, on 15 
December 1980, OCE authorized the removal of bridge 
abutments of South Michigan Avenue Bridge. New 
work for completed project cost $18,837,601. 
Estimated non-Federal costs were $9,188,000 for 
deepening, widening, and improving Buffalo River 
and ship canal, constructing piers, retaining walls, 
and dikes and performing dockside dredging. See 
Table 32-B for authorizing legislation. 
Local cooperation. Fully complied with. 
Terminal facilities. There are 45 wharves and 
piers of which 4 piers, owned by Niagara Frontier Port 
Authority, and 9 privately owned and operated 
facilities are on outer harbor and along sides of 
Lackawanna and Union ship canal, 4 are along banks 
of Buffalo ship canal, and 26 along Buffalo River. 
Coast Guard facilities are at mouth of Buffalo River 
along left bank. City of Buffalo owns a slip on right 
bank of Buffalo River just north of Michigan Avenue 
Bridge for mooring city fireboat. Thirty-four 
terminals have railroad connections and 29 
mechanical-handling facilities. Facilities considered 
adequate for existing commerce. (See Port Series No. 
41, revised 1971, Corps of Engineers.) 
Operations and results during fiscal year. New 
Work: Removal of South Michigan Avenue bridge 
abutment, by contract, was initiated in March 1981; 
however, the contractor was unable to complete the 
work and was terminated for default on August 16, 
1982. Completion of work by U.S. derrickboat 
McCauley cost $36,299. Maintenance: Miscellaneous 
inspection services, conditions surveys by 
Government plant and hired labor, water control 
management, and real estate activities cost $138,887. 
Repairs to about 120 1.f. on the South and Old 
breakwaters by U.S. derrickboat McCauley cost 
$184,514. Completion of repairs to North Breakwater, 
by contract, cost $292,950. Expenditure of $80,000 was 
attributed to the permanent lay-up of the U.S. hopper 
dredge Hoffman. Removal of 8,040 cubic yards of 
shoaled material, by contract, cost $203,662. 
Snagging and clearing in project channels by 
Government plant and hired labor cost $64,002. 
Adjustment in costs of contract for particle size and 
specific gravity testing resulted in a credit of $300. 
Costs of Co-Operative Stream-Gaging program were 
$12,150. In-house engineering costs for updating EIS 
and preparation of plans and specifications for all 
harbor work were $57,535. 
5. CAPE VINCENT HARBOR, N.Y. 
Location. On south shore of St. Lawrence River 
about 2.5 miles from Lake Ontario and 49 miles 
northerly from Oswego Harbor, N.Y. (See NOAA 
Nautical Chart 14800.) 
Previous Projects. For details see page 1975 of 
Annual Report for 1915 and page 1634 of Annual 
Report for 1938. 
Existing Project. For description of existing 
project see page 1566 of Annual Report for 1962. 
Actual costs for completed portion of project were 
$275,082. Deepening remainder of 16-foot area of 
project as authorized by 1945 act, at estimated cost of 
$159,000 (1954) is classified deferred. See Table 32-B 
for authorizing legislation. 
Local cooperation. Fully complied with. 
Terminal facilities. Two privately owned 
terminals for fish and a United States fish hatchery 
are located along waterfront bordering project. A ferry 
to Wolfe Island, Ontario, uses wharf owned by village. 
32-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
A yacht club dock and several other privately owned 
servicing and storage docks are for recreational and 
other small craft. Facilities are considered adequate 
for existing commerce. 
Operations and results during fiscal year. 
Maintenance: Miscellaneous inspection services by 
hired labor cost $461. 
6. CATTARAUGUS HARBOR, N.Y. 
Location. At mouth of Cattaraugus Creek on south 
shore of Lake Erie about 12 miles northeasterly from 
Dunkirk Harbor, N.Y. and 24 miles southwesterly 
from Buffalo Harbor, N.Y. (See NOAA Nautical Chart 
14823.) 
Existing project. Provides for navigation, flood 
control and recreational breakwater fishing by 
constructing: (a) arrowhead breakwaters in Lake Erie 
at mouth of Cattaraugus Creek; (b) an entrance 
channel, 200 feet wide at lakeward end, 100 feet wide 
and eight feet deep from that depth in lake to a point 
1,575 feet upstream; (c) a channel 100 feet wide, six feet 
deep an additional 3,425 feet upstream; and (d) 
development of recreational facilities at mouth for 
breakwater fishing. Estimated Federal cost for new 
work is $4,500,000 (Oct. 1981). Estimated non-Federal 
cost for new work is $2,520,000 (Oct. 1981) including 
cash contribution of $2,500,000 and the remainder for 
lands and damages. Existing project was authorized 
by 1968 River and Harbor Act (H. Doc. 97, 90th Cong., 
1st sess.). 
Local cooperation. See page 32-5 of Annual 
Report for 1976 for details of requirements of local 
cooperation. Required cash contribution is presently 
estimated at $2,500,000. The State of New York 
executed local cooperation agreement in July 1981. 
Terminal facilities. Facilities consist of private 
docks for recreational craft and privately owned 
servicing and storage handling facilities for 
recreational and other small craft. 
Operations and results during fiscal year. New 
work: Construction was completed in January, 1983. 
FY83 expenditures were $954,186 in Federal funds for 
finalization of construction contract. Maintenance: 
Project condition surveys cost $2,560. 
7. CLEVELAND HARBOR, OHIO 
Location. On south shore of Lake Erie, at mouth of 
Cuyahoga River, 176 miles westerly from Buffalo, 
N.Y. (See NOAA Nautical Chart 14839.) 
Previous projects. For details see page 1962, 
Annual Report for 1915, and page 1585, Annual 
Report for 1938. 
Existing project. For description of existing 
project, as authorized thru the 1966 modification, see 
page 1269 of Annual Report for 1967. Further 
improvements were recommended by 1976 WRD Act 
which authorized preparation of Phase I design 
memorandum for proposed new work comprising of: 
(a) extension of lake approach and entrance channel 
at arrowhead entrance and deepening of those areas 
to 32 feet; (b) incremental removal, as required, of 500 
feet of existing west breakwater spur and 400 feet of 
existing east breakwater spur to facilitate turning 
movements; (c) construction of a 1,200-foot 
rubblemound breakwater extension at east end of east 
breakwater; (d) deepening of fan shaped approach 
channel and a 1,000-foot wide entrance channel 
extending 2,900 feet into east basin, to a depth of 32 
feet; (e) deepening of existing 500-foot wide east basin 
channel to 28 feet; (f) construction of a diked disposal 
area; and, (g) recreational facilities, for fishing on 
west breakwater, including pedestrian handrail, 
pedestrian bridge and public parking. Estimated total 
Federal cost of new work is $65,215,000 (Oct. 1981) of 
which $29,315,100 is for completed work and balance 
of $35,900,000 (Oct. 1981) is for new work proposed by 
1976 WRD Act. Estimated non-Federal cost is 
$10,263,000 (Oct. 1981) of which $9,203,000 is actual 
cost for completed work and balance of $1,060,000 is 
required cash contribution for work authorized by 
1976 WRD Act. Remaining work authorized by 1946 
River and Harbor Act consisting of widening and 
deepening right bank of Cuyahoga River at 
downstream end of Cut 4 is considered inactive and 
excluded from foregoing cost estimate. Estimated 
Federal cost (1966) of this portion is $85,600 and non- 
Federal cost (1966) is $5,000,000. Remaining work 
authorized by 1958 R&H Act consisting of planning 
and replacement of bridges number 19 (E.L.R.R.) and 
32 (B.&O.R.R.) and widening Cuyahoga and Old 
River channels and remaining work authorized by 
1960 R&H Act consisting of deepening remainder of 
Cuyahoga River from bridge number 1 to and 
including Old River to a depth of 27 feet has been 
classified as deferred and is also excluded from 
foregoing cost estimate. Estimated Federal cost (Oct. 
1976) of this portion is $18,033,300 and estimated non- 
Federal cost (Oct. 1976) is $21,251,000. See Table 32-B 
for authorizing legislation. 
Local cooperation. Fully complied with for 
completed portion of project. See page 32-5 of Annual 
Report for 1977 for details of requirements of local 
cooperation for work recommended by 1976 WRD Act. 
Assurances will be requested upon completion of 
Phase II General Design Memorandum. 
Terminal facilities. There are 72 piers and 
wharves. Eleven are owned by city of Cleveland, of 
which 7 are operated by the Cleveland-Cuyahoga 
County Port Authority. Fourteen are on outer harbor, 
11 on banks of Old River and remaining 47 along deepdraft 
section of Cuyahoga River. Forty-seven 
terminals have railroad connections and 39 
mechanical-handling facilities. The Corps owns a 
wharf at foot of East 9th Street. Facilities are 
considered adequate for existing commerce. (See Port 
Series No. 43, revised 1970, Corps of Engineers.) 
Operations and results during fiscal year. New 
work: Preparation of Phase I General Design 
32-4

BUFFALO, N.Y. DISTRICT 
Memorandum, as authorized by 1976 WRD Act, was 
continued under the General Investigation 
Appropriation at a cost of $221,631. Maintenance: 
Miscellaneous inspection services and condition 
surveys by Government plant and hired labor cost 
$376,507. Repairs to pumpout facility cost $10,046. 
Repairs to approximately 146 l.f. of the east 
breakwater by U.S. derrick boats Tonawanda and 
Ohio cost $717,140. Repairs to 327 l.f. of the east 
breakwater, by contract, cost $422,224. Removal of 
327,389 cubic yards of shoaled material from 
Cuyahoga River, by contract, cost $2,916,636. 
Dredging cost by U.S. Hopper dredge Markham were 
$10,987. Expenditure of $149,426 was attributed to the 
permanent lay-up of the U.S. hopper dredge Hoffman. 
Environmental sediment study, by contract, cost 
$1,331. Costs for Co-Operative Stream Gaging 
Program were $17,370. Odor control contract was 
finalized at a cost of $295. Snagging and clearing, by 
contract, cost $14,970 and by Government plant and 
hired labor cost $2,594. Adjustment in cost of contract 
for particle size and specific gravity testing resulted in 
a credit of $680. Net credit to the project as a result of 
insurance re-payment for damages to pierhead light 
foundation was $316,796. In-house engineering costs 
for preparation of plans and specifications on 
contract dredging, major repairs to east breakwater, 
environmental testing, and structure inspections were 
$154,732. Support of the Diked Disposal program cost 
$493. 
8. CONNEAUT HARBOR, OHIO 
Location. On south shore of Lake Erie, at mouth of 
Conneaut River, 73 miles easterly from Cleveland, 
Ohio. (See NOAA Nautical Chart 14824.) 
Previous projects. For details see page 1964, 
Annual Report of 1915. 
Existing project. For description see page 1274 of 
Annual Report for 1967. Actual cost for new work for 
completed portion of the project were $7,541,369. See 
page 1274, Annual Report 1967, for complete 
description of project modification authorized by 1966 
R&H Act. Estimated cost (1970) of this modification is 
$717,000. For completed work non-Federal costs were 
$200,000 for dockside dredging and removal of 
existing dolphins. Estimated non-Federal cost of 
$2,877,000 (1970) includes cash contribution of 
$717,000 and the remainder is for construction of 
service facilities for the 1966 project modification. See 
Table 32-B for authorizing legislation. 
Local cooperation. Fully complied with for 
completed portion of project. See page 32-6 of Annual 
Report for 1971 for reauirements of local cooperation 
for project modification as authorized by the River 
and Harbor Act of 1966. 
Terminal facilities. There are seven piers and 
wharves. Six are privately owned and operated and 
located in inner harbor. Remaining facility is city 
owned on the south side of outer harbor. Six terminals 
have railroad connections and four mechanicalhandling 
facilities. (See Port Series No. 42, revised 
1972, Corps of Engineers.) 
Operations and results during fiscal year. 
Maintenance: Miscellaneous inspection services and 
condition surveys were done by Government plant 
and hired labor at a cost of $19,834. Repairs to 140 1.f. 
of the west breakwater by U.S. derrickboat 
Tonawanda cost $393,933. Expenditure of $55,000 was 
attributed to the permanent lay-up of U.S. hopper 
dredge Hoffman. Removal of 79,000 cubic yards of 
shoaled material from the outer harbor and 64,000 
cubic yards of shoaled material from the Municipal 
Dock Access Channel, by contract, cost $596,213. Inhouse 
related engineering effort cost $10,732. 
9. DUNKIRK HARBOR, N.Y. 
Location. On south shore of Lake Erie, 37 miles 
southwesterly from Buffalo, N.Y. (See NOAA 
Nautical Chart 14823.) 
Previous projects. For details see page 1966 of 
Annual Report for 1915, and page 1604 of Annual 
Report for 1938. 
Existing project. For description of completed 
portion of existing project see page 32-8 of Annual 
Report for 1976. For description of small boat harbor 
project as authorized under Section 201 of Flood 
Control Act of 1965, see page 32-8 of Annual Report for 
1978. Actual costs for completed work are $3,010,024. 
Actual non-Federal costs are $1,961,000. See Table 32- 
B for authorizing legislation. 
Local cooperation. Fully complied with. 
Terminal facilities. Facilities consist of private 
docks for recreational craft and privately owned 
servicing and storage handling facilities for 
recreational and other small craft. 
Operations and results during fiscal year. 
Maintenance: Miscellaneous inspection services and 
condition surveys by Government plant and hired 
labor cost $3,335. Dredging, by contract, removed 
11,516 cubic yards of shoaled material at a cost of 
$202,294. In-house engineering costs for preparation 
of plans and specifications for dredging cost $10,521. 
10.ERIE HARBOR, PA. 
Location. On southerly side of bay formed by 
Presque Isle Peninsula, on south shore of Lake Erie, 78 
miles westerly from Buffalo, N.Y. (See NOAA 
Nautical Chart 14835.) 
Previous projects. For details see page 1965 of 
Annual report for 1915 and page 1600 of Annual 
Report for 1938. 
Existing project. For description see pages 1363- 
64 of Annual Report for 1963. Entire project 
modification authorized by 1945 River and Harbor 
Act, providing for deepening channel and basin, both 
23 feet deep, to Penn Central Company coal docks at 
westerly end of harbor, was deauthorized by Congress 
32-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
in August 1977. Actual costs for new work for 
completed portion of project were $2,860,906. 
Extension of north pier portion as authorized by 1899 
act was deauthorized in November 1981. Estimated 
cost (1955) of this portion is $1,071,000. A portion of 
work authorized by 1960 act, deepening strips 
adjacent to north and south piers, was deauthorized in 
August 1982. Estimated cost (July 1962) of this portion 
is $78,000. Non-Federal costs for completed work were 
$51,000 for providing ore dock and dredging slip 
adjacent thereto. See Table 32-B for authorizing 
legislation. 
Local cooperation. Fully complied with. 
Terminal facilities. Sixteen piers and wharves, of 
which 12 are privately owned and operated. Erie 
International Marine Terminal No. 1 owned by Port 
Commission, city of Erie, is along main waterfront on 
south side of Presque Isle Bay and Coast Guard 
facilities are on north side. Two off-shore oil docks are 
on Lake Erie. Eight terminals have railroad 
connections and six mechanical-handling facilities. 
Facilities are considered adequate for existing 
commerce. (See Port Series No. 42, revised 1972, Corps 
of Engineers.) 
Operations and results during fiscal year. 
Maintenance: Miscellaneous inspection services and 
condition surveys by Government plant and hired 
labor cost $15,743. Maintenance dredging by U.S. 
hopper dredge Markham cost $253,426 for removal of 
168,271 cubic yards of shoaled material from the 
entrance channel. Adjustment in cost of contract for 
sediment testing resulted in a credit of $1,304. 
Contract for repairs to north pier was awarded in 
September 1983. In-house engineering costs for design 
analysis and plans and specifications for 
rehabilitation of north pier were $64,928. 
11.FAIRPORT HARBOR, OHIO 
Location. On south shore of Lake Erie at mouth of 
Grand River, 33 miles easterly from Cleveland, Ohio. 
(See NOAA Nautical Chart 14837.) 
Previous projects. For details see page 1963 of 
Annual Report for 1915, and page 1590 of Annual 
Report for 1938. 
Existing project. For description of existing 
project as authorized thru the 1960 modification, see 
page 1526 of Annual Report for 1962; for description of 
small boat harbor as authorized by Sec. 201 of 1965 
Flood Control Act, see page 32-10 of Annual Report for 
1977. Estimated total Federal cost of new work is 
$4,931,000 (Oct. 1980) of which $2,591,000 is actual 
cost for completed portion of project and the balance of 
$2,340,000 is for proposed work authorized by Sec. 201 
of 1965 FC Act. Entire project modification authorized 
by 1960 River and Harbor Act, providing for 
deepening lake approach channel, 800-foot wide 
channel through outer harbor and channel in Grand 
River, and enlargement of turning basin, is classified 
inactive and is excluded from foregoing cost. 
Estimated cost of this modification is $3,170,000 
(1963). Estimated non-Federal cost is $4,991,000 of 
which $101,000 were for bulkheads and dockside 
dredging for completed portion of project and 
$2,560,000 which includes cash contribution of 
$2,330,000, is for work authorized by Sec. 201 of 1965 
FC Act. For the inactive 1960 project modification, 
estimated non-Federal cost of $3,821,000 (1963) is for 
lands, relocations, utility changes, dock dredging and 
dock and bulkhead modifications. See Table 32-B for 
authorizing legislation. 
Local cooperation. See page 32-11 of 1976 Annual 
Report regarding assurances of local cooperation for 
work authorized by R&H Acts of 1927 and 1960 and 
page 32-11 of 1977 Annual Report for requirements of 
local cooperation for work authorized by Sec. 201 of 
1965 Flood Control Act. 
Terminal facilities. Sixteen piers and wharves, 
all along banks of Grand River. One facility is owned 
by Coast Guard. Nine terminals have railroad 
connections and ten mechanical-handling facilities. 
Facilities considered adequate for existing commerce. 
(See Port Series No. 42, revised 1972, Corps of 
Engineers.) 
Operations and results during fiscal year. 
Maintenance: Miscellaneous inspection services and 
condition surveys by Government plant and hired 
labor cost $33,833. Expenditure of $50,000 was 
attributed to the permanent lay-up of the U.S. hopper 
dredge Hoffman. U.S. hopper dredge Markham 
removed 34,475 cubic yards of shoaled material from 
lake approach channel at a cost of $170,384. U.S. 
derrickboat Ohio repaired 100 1.f of the west 
breakwater at a cost of $277,422. Finalization of 1982 
dredging contract costs was $51,260. In-house 
engineering effort cost $12,154. 
12. GENEVA-ON-THE-LAKE, OHIO 
Location. On south shore of Lake Erie, about 17 
miles east of Fairport Harbor, Ohio and 12 miles west 
of Ashtabula Harbor, Ohio (See NOAA Nautical 
Chart 14826.) 
Existing project. Small boat harbor project 
provides for: (a) breakwaters in Lake Erie aggregating 
about 1,050 feet in length; (b) entrance channel about 
770 feet long, 100 feet in width, 8 feet deep; (c) inner 
channels, 100 feet wide totaling 1,680 feet in length 
and 6 feet deep; (d) a mooring area 0.9 acres in area 
with depths varying from 6 to 8 feet (e) development of 
recreational facilities, and (f) development of wetland 
mitigation features. Estimated Federal cost for new 
work is $4,710,000 (Oct. 1983). Non-Federal cost 
estimate of $5,070,000 (Oct. 1983) is cash contribution 
toward first cost of construction. Existing project was 
authorized under provision of Section 201 of Flood 
Control Act of 1965. (H.D. 402, 91st Cong. 2 sess.) 
Local cooperation. See page 32-11 of 1978 Annual 
Report for requirements of local cooperation for work 
authorized by Sec. 201 of 1965 Flood Control Act. By 
32-6

BUFFALO, N.Y. DISTRICT 
letters dated November 10, 1977, April 15, 1981, and 
September 10, 1982 the State of Ohio Department of 
Natural Resources, the responsible agency, has 
indicated its willingness and ability to furnish the 
assurances. Assurances of local cooperation will be 
requested upon approval of Design Memorandum, 
Phase II, and draft Local Cooperation Agreement. 
Terminal facilities. There are no commercial or 
recreational facilities at the harbor. 
Operations and results during fiscal year. New 
work: Phase II General Design Memorandum was 
approved December 20, 1982, and further comments 
and issues were addressed at a cost of $63,998. Total 
costs including Construction, General, funds are 
$860,489. 
13.HURON HARBOR, OHIO 
Location. On south shore of Lake Erie at mouth of 
Huron River, 47 miles westerly from Cleveland, Ohio. 
(See NOAA Nautical Chart 14843.) 
Previous project. For details, see page 1961 of 
Annual Report for 1915, and page 1576 of Annual 
Report for 1938. 
Existing project. For description see page 1347 of 
Annual Report for 1963 and page 32-12 of Annual 
Report for 1978. Cost of completed portion of existing 
project was $4,834,006. Construction of detached 
breakwater as authorized by 1962 R&H act is deferred. 
Estimated cost of construction of breakwater is 
$12,970,000 (July 1972). Non-Federal costs of $163,000 
were incurred by local interests in 1963 for dockside 
dredging of areas between Federal improvement and 
terminal facilities. See Table 32-B for authorizing 
legislation. 
Local cooperation. Fully complied with. 
Terminal facilities. Six privately owned wharves 
and docks, one along left bank of Huron River and 
remainder along right bank. Four terminals have 
railroad connections and four mechnical-handling 
facilities. Facilities are regarded as adequate for 
existing commerce. (See Port Series No. 42, revised 
1972, Corps of Engineers.) 
Operations and results during fiscal year. 
Maintenance; Miscellaneous inspection services and 
condition surveys by Government plant and hired 
labor cost $18,708. Maintenance dredging, by 
contract, cost $356,000 for removal of 78,000 cubic 
yards from lake approach, river entrance channel, 
and turning basin. Expenditure of $40,000 was 
attributed to the permanent lay-up of U.S. hopper 
dredge Hoffman. Adjustment in cost of contract for 
particle size and specific gravity analysis testing 
resulted in a credit of $924. In-house engineering effort 
cost $30,294. 
14.IRONDEQUOIT BAY, N.Y. 
Location. On south shore of Lake Ontario, 4 miles 
east of Rochester, N.Y. at mouth of Irondequoit Creek, 
Monroe County, N.Y. (See NOAA Nautical Charts 
14804 and 14815.) 
Existing project. Provides for: (a) entrance 
channel located at easterly end of bay, 9 feet deep and 
100 feet wide, extending from 9-foot depth in Lake 
Ontario to junction with inner bay channels a 
distance of about 1350 feet; (b) inner channel, 8 feet 
deep and 100 feet wide, from entrance channel to deep 
water in bay, a distance of about 3,035 feet; (c) access 
channel, 8 feet deep, 100 feet wide, and 500 feet in 
length from the inner bay channel to the site of a 
proposed State marina; (d) two stone rubblemound 
structures 1,350 feet and 750 feet in length at the 
natural entrance; and (e) recreational facilities of 0.63 
acre parking area, two comfort stations, and hand 
railings on the breakwater and jetty. Estimated 
Federal cost presented in the Phase II General Design 
Memorandum for new work is $3,490,000 (April 1982). 
Estimated non-Federal cost for new work is $9,840,000 
(April 1982) including cash contribution of $2,590,000 
(April 1982) and remainder for lands, damages and 
highway bridge relocation. Existing project was 
authorized by 1958 River and Harbor Act (H. Doc 332, 
84th Cong. 2nd sess.) 
Local cooperation. By letters dated June 13,1980, 
December 24, 1981, and June 19,1982, New York State 
Office of Parks, Recreation and Historic Preservation 
reaffirmed its intent to provide assurances of 
cooperation. The Local Cooperation Agreement was 
executed April 20, 1983. 
Terminal facilities. Facilities consist of private 
docks for recreational craft and privately owned 
servicing and storage handling facilities for 
recreational and other small craft. 
Operations and results during fiscal year. New 
work: Preconstruction planning for the project was 
continued at a cost of $65,534. The railroad bridge 
steel superstructure was removed, by contract, in 
September 1983; bridge abutments are scheduled for 
removal in FY84. 
15.LORAIN HARBOR, OHIO 
Location. On south shore of Lake Erie at mouth of 
Black River, 28 miles westerly from Cleveland, Ohio. 
(See NOAA Nautical Chart 14841.) 
Previous projects. For details, see page 1961 of 
Annual Report for 1915, and page 1580 of Annual 
Report for 1938. 
Existing project. For description see pages 1319- 
22 of Annual Report for 1966. Estimated Federal cost 
of new work is $26,246,000 (Oct. 1976). Deepening and 
widening remainder of Black River Channel at Cut 1 
and construction of bank stabilization as authorized 
by 1960 act and modified by 1965 act is classified 
deferred. The estimated cost of $5,317,000 for this 
work is included in the above estimate. A portion of 
work authorized by 1960 act, dredging of 15- to 25-foot 
wide strips adjacent to the U.S. East and West piers is 
32-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
also deferred and estimated cost of $60,200 (July 1966) 
is excluded from foregoing cost estimate. Total non- 
Federal cost estimate is $8,853,000 (Oct. 1976) 
including $3,000 contributed by local interests toward 
construction of west breakwater shorearm. For work 
authorized by 1960 act, including deferred portion, 
non-Federal costs are estimated to be $8,805,000 for 
lands, relocations of utilities, modifications of 
existing dock and bulkheads, construction of new 
bulkheads and dockside dredging. For work 
authorized by 1965 act, classified as deferred, local 
interests must make a cash contribution presently 
estimated at $45,000. See Table 32-B for authorizing 
legislation. 
Local cooperation. For completed work, local 
interests contributed $3,000. Work authorized by 1960 
act (and modified by 1965 act) is deferred. All other 
conditions fully complied with. 
Terminal facilities. There are 23 piers and 
wharves, of which three are on outer harbor and 
remainder are along banks of Black River. Two are 
owned by the city. Eight terminals have railroad 
connections and 15 mechanical-handling facilities. 
Facilities are considered adequate for existing 
commerce. (See Port Series No. 42, revised 1972, Corps 
of Engineers.) 
Operations and results during fiscal year. 
Maintenance: Miscellaneous inspection surveys and 
condition surveys by Government plant and hired 
labor cost $68,708. Repairs to the pumpout unit by 
Government plant and hired labor cost $467. Repairs 
to 171 1.f. of the east breakwater by the U.S. 
derrickboat Ohio cost $483,325. Expenditure of 
$50,000 was attributed to the permanent lay-up of U.S. 
hopper dredge Hoffman. Removal of 109,557 cubic 
yards of shoaled material from Black River Channel 
and upper turning basin, by contract, cost $738,932. 
Costs for Co-Operative Stream Gaging Program were 
$5,370. Adjustment in cost of contract for sediment 
sampling study resulted in a credit of $1,000. In-House 
engineering costs were $31,206. 
16.OGDENSBURG HARBOR, N.Y. 
Location. On south shore of St. Lawrence River, 62 
miles by water from Lake Ontario. (See NOAA 
Nautical Chart 14764.) 
Previous projects. For details see page 1975 of 
Annual Report for 1915, and page 1635 of Annual 
Report for 1938. 
Existing project. For description see page 1568 of 
Annual Report for 1962. Actual cost for new work for 
completed portion of project was $375,086. Removal of 
hard material shoals from lower basin portion of 
project as authorized by 1935 act, at an estimated cost 
of $183,000 (1954) is classified inactive. See Table 32-B 
for authorizing legislation. On April 20, 1983, the 
Chief of Engineers under authority provided by 
Section 107 of the 1960 River and Harbor Act, as 
amended, authorized an extension of Lower East 
Entrance Channel, 600 feet west of the existing pier to 
a depth of 27 feet below LWD. Dredged material is to 
be disposed of in dredged disposal area Site 5, owned 
by Ogdensburg Bridge and Port Authority and 
previously used for this purpose. Estimated costs for 
this work (Aug. 82) are $870,000 Federal and 
$4,280,000 non-Federal. 
Local cooperation. Fully complied with for prior 
projects. On September 1, 1983, the Ogdensburg 
Bridge and Port Authority signed the local 
cooperation agreement to (a) provide without cost to 
the United States, all lands, easements, and rights-ofway 
necessary for constructin and subsequent 
maintenance of the harbor channel improvement, and 
for aids to navigation upon the request of the Chief of 
Engineers, including suitable areas required for 
initial and subsequent disposal of dredged material 
and all necessary retaining dikes, bulkheads, and 
embankments, or the costs of such retaining works; (b) 
Hold and save the United States free from damages 
due to the construction and maintenance of the project 
except for damages due to the fault or negligence of the 
Government or its Contractors; (c) Provide and 
maintain without cost to the United States depths in 
the berthing areas and local access channels 
commensurate with depths provided in the related 
Federal project channel; (d) Retain legal ownership of 
the specifically approved disposal area (Site No. 5) for 
the disposal of dredged material from construction 
and maintenance of the project by the United States 
and the Ogdensburg Bridge and Port Authroity and 
maintain the area after use in accordance with 
applicable State and Federal environmental 
requiremnts, during the life of the project; (e) 
Accomplish without cost of the United States all 
utility and other relocations or alterations made 
necessary by the project, except aids to navigation; (f) 
Comply with the applicable provisions of the uniform 
Relocation Assistance and Real Property Acquisition 
Policies Act of 1970, Public Law 91-646, approved 2 
January 1971, in acquiring lands, easements and 
rights-of-way for construction and subsequent 
maintenance of the project, and inform affected 
persons of pertinent benefits, policies, and procedures 
in connection with said Act; (g) Provide without cost to 
the United States, terminal, transfer, and 
transshipment facilities related to operations of the 
Ogdensburg Bridge and Port Authority. Plans and 
schedules for construction of these facilities must be 
approved by the Chief of Engineers; and (h) Maintain 
the terminal facilities at the Ogdensburg Bridge and 
Port Authority Terminal to accomodate the existing 
and prospective commerce. 
Operations and results during fiscal year. New 
Work: Contract for construction of initial stage of 
Section 107 work was awarded September 1983. Costs 
to date for Section 107 work are $248,212. 
Maintenance: Project condition surveys cost $1,017. 
32-8

BUFFALO, N.Y. DISTRICT 
17.OSWEGO HARBOR, N.Y. 
Location. On south shore of Lake Ontario, at 
mouth of Oswego River, 59 miles easterly from 
Rochester, N.Y. (See NOAA Nautical Chart 14813.) 
Previous projects. For details see page 1973 of 
Annual Report for 1915, and page 1630 of Annual 
Report for 1938. 
Existing project. For description see pages 1383- 
84 of Annual Report for 1963. Completed portion of 
project cost $7,242,039 and non-Federal costs for 
completed work were $4,440,000 for lands, dockside 
dredging, construction of terminal, wharves, and 
cargo handling facilities. Deepening a 200-foot wide 
strip along harbor line east of mouth of Oswego River, 
remaining feature of work authorized by the 1930 act, 
is classified as inactive. Deepening to 22 feet a 150-foot 
wide strip along harbor line in west outer harbor, 
remaining feature of work authorized by 1940 act, was 
deauthorized in May 1981. Estimated Federal costs for 
this work are$246,000 (July 1957) and $2,419,000 (July 
1966) respectively, and estimated non-Federal costs 
are $500,000 (July 1966) for dockside dredging for 
work authorized by 1940 act. See Table 32-B for 
authorizing legislation. 
Local cooperation. Fully complied with. 
Terminal facilities. Seven piers and wharves in 
harbor and along river channel. In addition, Port of 
Oswego Authority owns two public terminals, one of 
which is west of river and includes a grain elevator 
and warehouse for miscellaneous freight. Other 
terminal is east of river and used for handling 
aluminum and general cargo. State of New York owns 
a river terminal used for mooring vessels. City of 
Oswego owns one dock and shore facilities for 
recreational craft. Facilities considered adequate for 
existing commerce. 
Operations and results during fiscal year. 
Maintenance: Miscellaneous inspection services and 
condition surveys by Government plant and hired 
labor cost $33,710. Repairs to about 400 1.f. of west 
arrowhead breakwater by U.S. derrick boat McCauley 
cost $510,452. Expenditure of $10,000 was attributed 
to the permanent lay-up of the U.S. hopper dredge 
Hoffman. Adjustment in cost of FY82 dredging 
contract resulted in a credit of $12,975. In-house 
engineering effort cost $17,255. 
18.PORT CLINTON HARBOR, OHIO 
Location. Comprises lower half-mile of Portage 
River. River empties into Lake Erie 72 miles westerly 
from Cleveland, Ohio. (See NOAA Nautical Chart 
14820.) 
Existing project. Provides for parallel jetties at 
river mouth and a channel in Lake Erie and Portage 
River with a project depth of 10 feet. For additional 
details see page 1899 of Annual Report for 1951. (See 
Table 32-B for authorizing legislation.) 
Local cooperation. None required. 
Terminal facilities. There is one public fish dock, 
one private sand dock, one private fuel, lumber and 
coal dock, and five additional private docks. A dock at 
foot of Madison Avenue is owned by village of Port 
Clinton and open to the public. A shipyard builds 
small boats. Terminal facilities are adequate for 
existing commerce. 
Operations and results during fiscal year. 
Miscellaneous inspection services and hired labor cost 
$3,815. Repairs to east and west jetties, by contract, 
cost $182,877. In-house engineering effort on repairs 
to the jetties, including a subsurface exploration 
contract, cost $49,820. 
19.ROCHESTER HARBOR, N.Y. 
Location. On south shore of Lake Ontario, at 
mouth of Genesee River, 59 miles westerly from 
Oswego, N.Y. (See NOAA Nautical Chart 14815.) 
Previous project. For details see page 1471 of 
Annual Report for 1915, and page 1623 of Annual 
Report for 1938. 
Existing project. For description see page 1556 of 
Annual Report for 1962. Actual cost for new work for 
completed project is $21,191,514. Non-Federal costs 
are estimated at $2,260,000, all for 1960 act, for lands, 
relocation of submarine cable crossing, relocations of 
small docks and boathouses, dockside dredging, 
structure modifications, and replacement of 
Baltimore & Ohio coal loader. See Table 32-B for 
authorizing legislation. 
Local cooperation. Complied with except 
provision for replacement of coal loading facility as 
required by River and Harbor Act of July 14, 1960. 
Terminal facilities. One terminal facility at 
mouth of Genesee River has been leased to the Great 
Lakes Division of Pittston Stevedoring Corp. 
Facilities also consist of private docks for recreational 
craft and privately owned servicing and storage 
handling facilities for recreational and other small 
craft. Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal year. 
Maintenance: Miscellaneous inspection services and 
condition surveys by Government plant and hired 
labor cost $9,787. Expenditure of $25,000 was 
attributed to the permanent lay-up of the U.S. hopper 
dredge Hoffman. Finalization of FY82 dredging 
contract cost $61,571. Repairs to the west breakwater, 
by contract, cost $904,283. In-house engineering effort 
associated with preparation of plans and 
specifications for repair of breakwater cost $105,591. 
20.ROCKY RIVER HARBOR, OHIO 
Location. At mouth of Rocky River which empties 
into Lake Erie 7 miles westerly from Cleveland, Ohio. 
32-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
(See NOAA Nautical Chart 14826.) 
Existing project. For description see page 1329 of 
Annual Report for 1966. Federal cost for completed 
project was $343,494 and non-Federal cost was a cash 
contribution of $249,346. See Table 32-B for 
authorizing legislation. 
Local cooperation. Fully complied with. Local 
interests contributed $249,346 for new work. 
Terminal facilities. Facilities consist of private 
docks for recreational craft and privately-owned 
servicing and storage handling facilities for 
recreational and other small craft. 
Operations and results during fiscal year. 
Maintenance: Miscellaneous inspection services and 
project condition surveys by Government plant and 
hired labor cost $1,547. 
21.SANDUSKY HARBOR, OHIO 
Location. On south shore of Lake Erie, in 
southeasterly portion of Sandusky Bay, 50 miles 
westerly from Cleveland, Ohio. (See NOAA Nautical 
Chart 14845.) 
Previous projects. For details see page 1960 of 
Annual Report for 1915, and page 1574 of Annual 
Report for 1938. 
Existing project. For description see pages 1511- 
12 of Annual Report for 1962. Actual costs for new 
work for completed project were $6,250,121, excluding 
$325,000 contributed by local interests. Non-Federal 
costs for completed project are estimated at $675,000 
including $325,000 cash contribution and the 
remaining $350,000 is for dockside dredging adjacent 
to deepened channels authorized by 1960 act. See 
Table 32-B for authorizing legislation. 
Local cooperation. Fully complied with. Local 
interests contributed $325,000 for new work. 
Terminal facilities. Fourteen piers and wharves, 
three at west end of harbor and remainder along dock 
channel. One is a base for State-owned fish research 
and patrol boats. One publicly owned and six 
privately owned are used for mooring fishing boats 
and recreational craft and for ferry service. Five 
terminals have railroad connections and five 
mechanical-handling facilities. Facilities are 
considered adequate for existing commerce. (See Port 
Series No. 42, revised 1972, Corps of Engineers.) 
Operations and results during fiscal year. 
Maintenance: Miscellaneous inspection services and 
condition surveys by Government plant and hired 
labor cost $25,875. Repairs to 825 1.f. of east jetty 
rubblemound construction by U.S. derrick boat 
Tonawanda cost $275,145. U.S. hopper dredge 
Markham removed 306,643 cubic yards of shoaled 
material from Dock, Bay, and Straight Channels, and 
12,683 cubic yards from Lower Bay Channel for cost of 
$572,063. Expenditure of $25,000 was attributed to the 
permanent lay-up of the U.S. hopper dredge Hoffman. 
Costs for Co-Operative Stream Gaging Program were 
$4,520. Adjustment in cost of contract for sediment 
sampling resulted in a credit of $1,000. In-house 
engineering effort cost $14,902. 
22.TOLEDO HARBOR, OHIO 
Location. Comprises lower 7 miles of Maumee 
River and channel through Maumee Bay to Lake Erie. 
Maumee River has its source in northern Indiana and 
empties into Lake Erie. Harbor is at westerly end of 
Lake Erie, 99 miles westerly from Cleveland, Ohio. 
(See NOAA Nautical Chart 14847.) 
Previous projects. For details see page 1959 of 
Annual Report for 1915, and page 1565 of Annual 
Report for 1938. 
Existing project. For description of existing 
project see pages 32-18 and -19 of Annual Report for 
1978. Cost of completed existing project was 
$15,567,147. See Table 32-B for authorizing 
legislation. 
Local cooperation. Fully complied with. 
Terminal facilities. Maumee River through city of 
Toledo has been developed extensively for deep-draft 
navigation. Detailed information on actual port and 
harbor facilities are in Port Series No. 44 (revised 
1972) prepared and published as Part 2, by Board of 
Engineers for Rivers and Harbors. Information on 
port administration and Federal services, port and 
terminal services and charges, and steamship 
services is prepared and published as Part I by the 
Port Development Staff, U.S. Department of 
Commerce. Facilities are considered adequate for 
existing commerce. 
Operations and results during fiscal year. 
Maintenance: Condition surveys, environmental 
studies, support of Water Control Center, and 
miscellaneous inspections and reports were 
performed by hired labor at a cost of $146,631. U.S. 
hopper dredge Markham performed maintenance 
dredging removing 691,551 cubic yards of shoaled 
material at a cost of $1,532,564. Expenditure of 
$120,000 was attributed to the permanent lay-up of the 
U.S. hopper dredge Hoffman. Removal of 132,800 
cubic yards of shoaled material from the Bay Channel 
and 283,052 cubic yards from the Maumee River 
Channel, by contract, cost $1,636,231. Repairs to 
Diked Disposal facility, by contract, cost $18,690. 
Adjustment in costs of contract for particle size and 
specific gravity analysis resulted in a credit of $1,000. 
Costs for Co-Operative Stream Gaging Program were 
$21,290. In-house engineering effort cost $65,721. 
23.WEST HARBOR, OHIO 
Location. On southwest shore of Lake Erie, 13 
miles northeast of Port Clinton, Ohio. (See NOAA 
Nautical Chart 14847.) 
Existing project. Existing project, as modified by 
Phase I General Design Memorandum, provides for 
two arrowhead breakwaters with an aggregate length 
32-10

BUFFALO, N.Y. DISTRICT 
of approximately 2,925 feet; entrance channel 10 feet 
deep and 100 feet wide to mouth of natural entrance 
and thence 80 feet wide to a depth of 8 feet; and access 
channel 3,980 feet in length, 80 feet wide and 8 feet 
deep from inner entrance to "Y" near center of harbor 
where channel divides northerly about 2,733 feet and 
southerly about 4,295 feet. Estimated Federal cost for 
new work is $3,150,000 (Oct. 1980). Estimated non- 
Federal cost is $4,330,000 (Oct. 1980), including cash 
contribution of $3,570,000. Existing project was 
authorized by 1965 River and Harbor Act (H. Doc. 245, 
88th Cong., 2nd sess.) 
Local cooperation. See page 32-20 of 1978 Annual 
Report for requirements of local cooperation. By letter 
dated January 31, 1978, State of Ohio stated its intent 
to furnish assurances of local cooperation, and 
executed LCA was received on March 9, 1981. 
Terminal facilities. Commerce at the harbor 
presently consists of recreational boating and 
affiliated activities. 
Operations and results during fiscal year. New 
Work: Construction, initiated on 1 June 1981, was 
completed in November 1982. FY83 expenditures for 
finalization of construction contract were $315,796 
Federal funds and $486,266 non-Federal funds. 
Maintenance: Project condition surveys were 
conducted at a cost of $3,898. 
24.RECONNAISSANCE AND 
CONDITION SURVEYS 
Project 
Niagara River, N.Y. begun 
Oak Orchard, N.Y. 
Sackets Harbor, N.Y. 
Great Sodus Bay Harbor, N.Y. 
Olcott Harbor, N.Y. 
Vermilion Harbor, Oh. 
Wilson Harbor, N.Y. 
Put-in-Bay, Ohio 
Little Sodus, N.Y. 
Date of 
Survey 
Aug. 1983 
Aug. 1983 
Oct. 1982 
Aug. 1983 
Aug. 1983 
Oct. 1982 
Aug. 1983 
Oct. 1982 
Aug. 1983 
FY 
Cost 
$ 6,003 
1,063 
36 
3,145 
1,326 
17,446 
2,002 
68 
1,167 
25. OTHER AUTHORIZED 
NAVIGATION PROJECTS 
See Table 32-C 
26.NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
See Table 32-D 
Beach Erosion Control 
27. LAKEVIEW PARK, LORAIN, OHIO 
Location. In the City of Lorain, Lorain County, 
Ohio, on south shore of Lake Erie between 1,500 and 
3,000 feet west of Lorain Harbor west breakwater. (See 
NOAA Nautical Chart 14841.) 
Existing project. For description of existing 
project see page 32-19 of Annual Report for 1977. The 
Federal cost of the completed project was $1,360,986 
and estimated non-Federal cost (Oct. 1976) was 
$50,000 for relocation. In addition, local interests 
contributed $583,280. Annual cost of 5-year program 
for beach replenishment and monitoring was 
approximately $75,000. Existing project authorized 
by 1954 River and Harbor Act (H. Doc. 224, 83rd Cong. 
1st sess.) 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. New 
work. Five year monitoring program which was 
initiated in 1978 was continued at a cost of $22,737. 
Cooperative beach nourishment was conducted in 
FY80 and FY81, during which time a total of 9,000 
cubic yards of sand was placed within the project 
limits. The Federal cost for nourishment has totalled 
approximately $73,000 and costs to local interests 
totalled approximately $30,000, annually. Beach 
profile surveys were conducted in April 1983 to 
document shoreline changes. The data which was 
collected during the 5-year moinitoring program was 
evaluated during FY83. 
28.PRESQUE ISLE PENINSULA, 
ERIE, PA. 
Location. At Erie, Pa., on south shoreof Lake Erie, 
78 miles southwest of Buffalo, N.Y. and 102 miles eastnortheast 
of Cleveland, Ohio. (See NOAA Nautical 
Charts 14824 and 14835.) 
Existing project. For description of completed 
portion of existing project see page 1393 of Annual 
Report for 1963. The Water Resources Development 
(WRD) Act of March 7, 1974, reinstated and extended 
authorization for beach erosion control project, as 
provided in 1960 R&H Act, for a period of five years 
from date of enactment of 1974 WRD Act, or if the 
review study of such project is not completed prior to 
end of such period, until such study is completed and a 
report thereon submitted to Congress. Work 
authorized by the 1974 WRD Act was completed in 
1979. The 1976 Water Resources Development Act 
provides for continued annual nourishment by 
stating: "At expiration of authorization provided in 
Section 57 of Water Resources Development Act of 
1974, the Secretary of the Army, acting through the 
Chief of Engineers, may provide periodic beach 
nourishment in accordance with cost sharing 
provisions of Section 103(a) (2) of Act of October 23, 
1962." The act also authorized preparation of a Phase 
I General Design Memorandum. The Final Phase I 
General Design Memorandum was completed in 
August 1981 and the recommended plan provides for 
construction of 58 offshore rubblemound breakwater 
segments, beach restoration by placement of sand fill, 
and annual beach replenishment for shore protection. 
32-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Estimated Federal cost (Oct. 1983) is $33,046,000 
which includes $5,646,000 for completed work 
authorized by the 1954 and 1960 R&H Acts and 1974 
WRD Act and $3,635,700 for completed work 
authorized by the 1976 WRD Act. Estimated non- 
Federal cost (Oct. 1983) is $17,763,000 which includes 
$3,983,000 for completed work authorized by 1954 and 
1960 R&H Acts and $1,550,642 for completed work 
authorized by the 1976 WRD Act. See Table 32-B for 
authorizing legislation. 
Local cooperation. Fully complied with for 
completed project as authorized by 1954 and 1960 
R&H Acts and 1974 WRD Act. An agreement between 
the United States of America and the Commonwealth 
of Pennsylvania, acting through the Department of 
Environmental Resources, was entered into on 
February 21, 1979 for the annual nourishment which 
was extended by the 1976 Water Resources 
Development Act. The plan recommended in the Final 
Phase I General Design Memorandum is contingent 
upon local sponsor, namely the Department of 
Environmental Resources of the Commonwealth of 
Pennsylvania, agreeing in writing to provide without 
cost to United States all lands, easements and rightsof-
way, including suitable borrow and disposal areas 
for excavated material as determined by the Chief of 
Engineers and necessary for implementation and for 
periodic nourishment of the project; provide a cash 
contribution based on the appropriate percentage of 
final construction cost, exclusive of lands, easements, 
and rights-of-way, the percentage to be in accordance 
with existing law based on shore ownership and use 
existing at time of construction, and the President's 
proposed cost-sharing policy, which contribution is 
presently estimated at $9,800,000 or 35 percent; pay 30 
percent of the cost for annual beach redistribution and 
replenishment work for the project; hold and save the 
United States free from damages due to construction 
works, except for damages due to fault or negligence of 
Government or its contractors; maintain and operate 
all the works, including breakwaters and periodic 
sand replenishment and redistribution as needed, 
after completion in accordance with regulations 
prescribed by the Secretary of the Army; and assure 
continued public ownership and continued public use, 
without cost to United States, of appropriate access 
and facilities including parking and sanitation, 
necessary for realization of public benefits upon 
which Federal participation is based, and administer 
and maintain beach for continued public use during 
life of project. Formal assurances of local cooperation 
will be requested and executed prior to initiation of 
construction of improvements. 
Operations and results during fiscal year. New 
work: Beach replenishment as authorized by the 1976 
WRD Act was continued at a total cost of $1,049,027 
(Federal and non-Federal). For its share of cost of 
improvement, Commonwealth of Pennsylvania 
contributed $368,175 for a cumulative total 
contribution of $4,438,172. The Final Phase I General 
Design Memorandum was submitted to the Secretary 
of the Army in October 1981 for his review and 
transmittal to Congress. A hydraulic model study of 
the plan recommended in the Phase I General Design 
Memo was completed. Maintenance: Project condition 
surveys were conducted at a cost of $1,366. 
29.OTHER AUTHORIZED BEACH 
EROSION CONTROL PROJECTS 
See Table 32-E. 
Beach Erosion Work 
under Special Authorization 
30. LAKESHORE PARK 
ASHTABULA, OHIO 
Location. Lakeshore Park is located in Ashtabula, 
Ashtabula County, Ohio, about 40 miles southwest of 
Erie, Pennsylvania, and about 50 miles northeast of 
Cleveland, Ohio. 
Existing project. The project, authorized by Chief 
of Engineers on April 26, 1982 under Section 103(a) of 
the River and Harbor Act of 1962, as amended, 
provides for the construction otf 3 offshore detached 
breakwaters, restoration of an 800-foot long 
recreational beach and an access road to the beach to 
facilitate the initial placement of the beachfill and 
subsequent periodic nourishment as necessary. The 
breakwaters, each 125 feet long with 200-foot gaps 
between them, are of rubblemound construction and 
located approximately 150 feet offshore of the restored 
beach. These breakwaters will protect 52,000 cubic 
yards of clean sandfill placed to restore the 800-foot 
long beach fronting the clay bluff. Total construction 
cost is estimated at $1.3 million, of which 70 percent is 
Federal cost and 30 percent required non-Federal or 
local cash contribution. 
Local cooperation. Among other requirements, 
local interests provide all lands, easements and 
rights-of-way and relocations required for 
construction, including periodic nourishment. The 
locals will carry out the periodic beach nourishment 
program for the 50-year life of the project with the only 
cost to the United States being the said 
reimbursement to the town of 70 percent of the town 
expenditure thereof, subject to availability of funds 
and the 1.0 million total Federal expenditure 
limitation under Section 103 authority, whichever 
occurs first. 
Operations and results during fiscal year. New 
work: The Final Detailed Project Report and plans 
and specifications were completed in May 1982. 
Construction started late in July 1982 and was 
completed in July 1983. Total FY83 expenditure was 
$199,957 Federal funds and $81,438 non-Federal 
funds. 
32-12

BUFFALO, N.Y. DISTRICT 
Flood Control 
31.CAYUGA CREEK, CHEEKTOWAGA, 
N.Y. 
Location. Project area of Cayuga Creek is located 
in vicinity of Union Road and William Street in town 
of Cheektowaga, N.Y. 
Existing project. Provides for (a) concrete tee on 
right bank beginning at Union Road bridge and 
extending about 700 feet upstream, two feet of 
freeboard above 100-year flood stage, (b) about 600 feet 
of earth levee and 250 feet of concrete wall, with 
freeboard of three feet for levee and two feet for wall 
and an additional amount added for velocity head, (c) 
riprap on left bank beginning at Union Road Bridge 
and extending 850 feet upstream; on right bank from 
700 feet to 850 feet above bridge, and 400 square yards 
in vicinity of junction of the floodwall along the creek 
and the transverse levee, (d) removal of earth to 
bedrock to place tee wall and excavation for bank 
erosion protection and channel work. Project 
authorized by Chief of Engineers pursuant to Section 
205, Flood Control Act of 1948, as amended. 
Local cooperation. See page 32-16 of FY81 
Annual Report for requirements of local cooperation. 
On September 3, 1980, the NYS Department of 
Environmental Conservation signed the formal 
cooperation agreement. 
Operations and results during fiscal year. 
Construction completed in November 1982. 
Finalization of contract resulted in a credit of $17,273. 
Total costs were $1,404,241. 
32.CUYAHOGA RIVER BASIN, OHIO 
Location. The project is located in northeastern 
Ohio, in Cuyahoga and Summit Counties, in the 
Cuyahoga River watershed. (See Geological Survey 
Map of Cleveland-South.) 
Existing project. Big Creek flood control 
improvement project, as developed in reformulation 
studies, Phase II General Design Memorandum, 
provides for: (a) relocation of approximately 4,950 
linear feet of Baltimore and Ohio railroad mainline 
and 1,290 linear feet of spurline, construction of 
embankment for new track and construction of two 
new railroad bridges, (b) floodway channel, 2,700 feet 
long from existing channel in Brookside Park to 
existing channel, upstream from West 25th Street 
Bridge, including spillway, staged channel and 
associated work, (c) diversion channel extending 
1,000 feet from existing channel, about 140 feet 
upstream from West 25th Street Bridge to existing 
channel approximately 300 feet from Protector 
Products, and, (d) modifications to existing channel. 
Estimated cost (Oct. 1982) for new work is Federal 
$23,000,000 and non-Federal $1,080,000 for lands, 
damages and relocations. Existing project was 
authorized by Section 108 of 1970 River and Harbor 
Act. 
Local cooperation. See page 32-17 of 1981 Annual 
Report for requirements of local cooperation. These 
items were adopted and agreed to by the Cleveland 
Metro Park System on January 20, 1982. 
Operations and results during fiscal year. New 
Work: Preconstruction planning was continued at a 
cost of $17,903. 
33.DANSVILLE AND VICINITY, 
CANASERAGA CREEK, N.Y. 
Location. In towns of North Dansville and West 
Sparta, Livingston County, New York (See Geological 
Survey Map Dansville, N.Y. 1942.) 
Existing project. Flood control improvements as 
proposed, Phase II General Design Memorandum, 
provide for: (a) two levees, 2 feet high and 215 feet long 
and 4 feet high and 290 feet long respectively, 
extending from each side of Sewage Plant Road to 
southbound ramps of the Genesee Expressway, (b) 
steel sheet pile and concrete floodwall, 405 feet in 
length, along right bank between Route 36 bridge and 
north bridge abutment of Genesee Expressway, (c) 
steel sheet pile floodwall, 285 feet in length and 
concrete bank stabilization to provide protection 
along rightbank between Route 36 bridge and 
Hartman Road, and (d) removal of Hartman Road 
bridge and construction of two gravity walls, 14 to 19 
feet in height, to provide protection and to replace the 
existing deteriorated bridge abutments. Federal cost 
for new work is $1,090,000 (October 1983). Non- 
Federal cost estimate of $33,000 (October 1983) is for 
lands. Existing project was authorized by Sec. 203 of 
1948 Flood Control Act (H.D. 206, 80th Cong., 1st 
Sess.). 
Local cooperation. See page 32-17 of 1981 Annual 
Report for requirements of local cooperation. Formal 
assurances of local cooperation will be requested prior 
to completion of final plans and specifications. 
Operations and results during fiscal year. New 
Work: Expenditure of $16,053 was attributed to issues 
addressed by Chief of Engineers. 
34.ELLICOTT CREEK, N.Y. 
Location. The proposed channel improvement is 
located on the downstream portion of Ellicott Creek in 
the towns of Amherst and Tonawanda, Erie County. 
(See Geological Survey maps of Tonawanda East and 
Buffalo Northeast, N.Y.) 
Existing project. For detailed description of the 
original project as authorized by Section 201 of the 
1970 Flood Control Act, see page 32-24 of Annual 
Report for 1973. The basic authorization, as modified 
by the Water Resources Development Act of 1974 
provides authority to undertake flood control 
measures to alleviate flooding that is compatible with 
authorized project and any alternatives currently 
under restudy pursuant to Flood Control Act of 1970. 
32-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
As a result of restudy of alternatives, the project 
provides for: (a) widening, straightening and 
deepening about 2.5 miles of existing creek channel 
including the existing by-pass channel in Ellicott 
Creek Park; (b) construction of a diversion channel 
about 5,850 feet long between Maple Road and 
Millersport Highway; (c) construction of a diversion 
channel about 1,950 feet long through Pfohl Park; (d) 
construction of a diversion channel about 9,150 feet 
long from Niagara Falls Boulevard upstream to about 
Pfohl Park; (e) construction of 2 highway bridges; (f) 
modification of culverts at Tonawanda Creek Road; 
(g) foundation protection of 1 highway bridge; (h) 
modification of utilities and drainage outlets; and (i) 
recreation facilities consisting of a bike and hike path 
about 5.4 miles long, with open space park areas. The 
estimated Federal cost of existing project is 
$13,600,000 (Oct. 1983). The estimated non-Federal 
cost is $9,000,000 (Oct. 1983) which includes a cash 
contribution of $470,000 (Oct. 1983). Completion of 
preconstruction planning and construction was 
authorized December 29, 1981, under Section 5, P.L. 
97-128. 
Local cooperation. For details of local 
cooperation see page 32-22 of Annual Report for 1976. 
On October 25, 1976, the New York State Department 
of Conservation furnished a letter of intent to 
cooperate toward construction of project. On June 22, 
1983, a formal Local Cooperation Agreement was 
requested from N.Y. State. 
Operations and results during fiscal year. New 
Work: Preconstruction planning was continued at a 
cost of $73,709. 
35.EUCLID CREEK, CLEVLAND, OH. 
Location. Euclid Creek has a drainage area of 
approximately 25 square miles and is located east of 
Cleveland in Cuyahoga County and a small portion in 
Lake County, Ohio. 
Existing project. Project was authorized for 
construction by Chief of Engineers pursuant to 
Section 205 of Flood Control Act of 1948 as amended 
on October 9, 1981. Project provides for a 100-foot wide 
channel downstream of Lake Shore Boulevard Bridge 
and a 30-foot wide diversion channel through the 
oxbow. The existing Lake Shore Boulevard Bridge 
will be replaced with a 90-foot wide clear span 
structure. Upstream from the bridge a grouted fabric 
slope-protected friction channel will be constructed. A 
low levee, approximately 4 feet in height, including 3 
feet of freeboard, will be constructed along the right 
channel bank approximately 800 feet upstream of 
Bridge and a tie-back levee would be constructed to 
contain the 100-year flood event. 
Local cooperation. On August 10,1983, the city of 
Cleveland and the Board of Cuyahoga 
Commissioners agreed to (a) provide, without cost to 
the United States, all lands, easements, rights-of-way, 
spoil disposal, and borrow areas necessary for the 
construction and subsequent maintenance of the 
project, as required; (b) hold and save the United 
States free from damages due to construction of the 
project except for damages resulting from negligence 
by the United States Government or its Contractors; 
(c) maintain and operate, without cost to the United 
States, the completed works in accordance with 
regulations prescribed by the Secretary of the Army; 
(d) provide, without cost to the United States, all 
alterations and relocations of existing improvements 
including bridges, highways, buildings, utilities, 
sewers, and other facilities, except as otherwise 
provided; (e) in acquiring lands, easements, rights-ofway, 
and spoil disposal areas necessary for the 
construction and subsequent maintenance of the 
project works, the project sponsor will comply with the 
applicable provisions of the "Uniform Relocation 
Assistance and Real Property Acquisition Policies 
Act of 1970", Public Law 91-646, approved 2 January 
1971; (f) prescribe and enforce regulations to prevent 
obstruction or encroachment upon the project works 
detrimental to the flood control purpose of the project; 
(g) consider the adoption of flood plain regulations as 
necessary to assure compatibility between future 
developments within the flood plain and the 
protection afforded by the proposed improvements; (h) 
consider the adoption of land use and zoning 
ordinances which would require onsite detention of 
increased peak discharge from any future major land 
developments in the watershed, particularly those 
developments predicted for the Highland Heights and 
Richmond Heights areas; (i) at least annually, 
publicize and notify all interested parties that the 
project will not provide protection against floods 
greater than the 100-year event, nor will the flood 
control project eliminate the relatively frequent 
basement flooding that occurs in the floodprone area 
due to an inadequate sewer system servicing the area; 
(j) consider replacement of the inadequate sewer 
system to reduce or eliminate basement flooding; or as 
an alternative action, floodproof the affected homes 
by installing one-way check valves in basement 
drains and sump pumps and providing emergency 
generators for use during power failure; (k) assume all 
construction costs in excess of the Federal limitation 
of $2,000,000 under Section 205. 
Operations and results during fiscal year. New 
Work: Contract for construction was awarded in 
September 1983. FY83 costs were $78,324 for 
finalization of plans and specifications to award 
contract. 
36.MT. MORRIS LAKE, N.Y, 
GENESEE RIVER 
Location. Dam is on Genesee River 66.9 miles 
above river mouth and about 32 miles southwesterly 
of Rochester, N.Y. Reservoir is in Livingston and 
Wyoming Counties, N.Y. (See Geological Survey maps 
of Nunda and Portage, N.Y.) 
Existing project. For description of existing 
32-14

BUFFALO, N.Y. DISTRICT 
project as authorized by 1944 Flood Control Act see 
page 1575 of Annual Report for 1962. New work for 
completed project cost $23,365,559. In addition, $5,000 
contributed funds expended for new work. 
Local cooperation. None required. Local interests 
contributed $5,000 for new work. 
Operations and results during fiscal year. 
Operation and maintenance: Operation and ordinary 
maintenance of dam, reservoir, and service facilities, 
condition and operation studies and miscellaneous 
reports were accomplished by hired labor for $355,297. 
Contracts for debris removal and installation of log 
boom to collect debris were finalized at a combined 
cost of $5,321. Access roadway paving, by contract, 
cost $37,684. Electrical repairs, by contract, cost 
$3,025. Contract for heating access roadway cost 
$13,090.Co-Operative Stream Gaging Program 
accomplished by U.S. Geological Survey and 
National Weather Service reporting and 
hydroclimatic networks cost $55,350. Operation of the 
Water Control Center cost $150,441. Engineering and 
design costs of $164,439 were incurred for the 
preparation of specifications for debris removal, log 
boom installation, annual facility inspection, 
electrical maintenance repairs, dam safety study and 
monitoring of seismic instruments. 
37.POINT PLACE, TOLEDO, OHIO 
Location. Point Place is located on a peninsula in 
northeast portion of city of Toledo, Ohio. Its shores are 
bounded on the east by Maumee Bay of Lake Erie and 
on the west by Ottawa River. The peninsula extends in 
a northeasterly direction immediately north of mouth 
of Maumee River. 
Existing project. Existing project, as 
recommended in Phase II General Design 
Memorandum, provides for: (a) combination of 
protective structures consisting of 4,400 feet of steel 
sheet pile wall and 13,700 feet of levee; (b) three new 
pumping stations and 3,800 feet of new storm sewer 
facilities; and, (c) facilities for fishing and related 
recreational activities. Estimated costs (Oct. 1982) are 
$8,900,000 Federal and $3,990,000 non-Federal 
including a cash contribution of $2,240,000. Existing 
project was authorized by 1972 Flood Control Act 
(H.D. 363, 92nd Cong., 2nd sess.) 
Local cooperation. For details of local 
cooperation see pages 32-24 and -25 of Annual Report 
for 1978. The Local Cooperation Agreement was 
executed by city of Toledo on January 27, 1982. 
Operations and results during fiscal year. New 
Work: Phase I for rehabilitation of 1800 1.f existing 
stone dike on Maumee Bay was completed in 
September 1982. Construction contract for Phase 1A 
for rehabilitation of 980 1.f. of existing stone dike was 
awarded in September 1982, and completed in May 
1983. Phase 2A for constructing 6,700 l1.f. of stone dike, 
a drainage interceptor system and pump station was 
awarded in June 1983 and is 12% complete. Total costs 
for FY83 were $1,348,602 Federal funds and $15,158 
for non-Federal funds. 
38.RENO BEACH- HOWARD FARMS 
AREA, OHIO 
Location. Area is located in Lucas County, on the 
south shore of Lake Erie about 15 miles east of Toledo, 
Ohio. 
Existing project. The project, as authorized, 
provides for construction of 8,200 feet of roadway 
seawall, consisting of an earth dike, faced on the 
lakeward side with a quarry-run stone fill; and a steel 
sheet pile floodwall connecting the easterly end of this 
seawall at Wards Canal to the existing inland dike 
paralleling the canal. Estimated Federal cost of new 
work consisting of reconstructing to a permanent 
project the "Operation Foresight" work which was 
completed in 1973, is $7,370,000 (Oct. 1983). Non- 
Federal cost estimate of $2,460,000 (Oct. 1983) is a 
cash contribution toward first cost of construction 
and all lands, easements, and rights-of-way. Project 
was authorized under Section'203 of the Flood Control 
Act of 1948. (H.D. 554, 80th Congress, 2nd Sess.). 
Local cooperation. See page 32-16 of 1982 Annual 
Report for full requirements of local cooperation. A 
Local Cooperation Agreement will be requested upon 
approval of the Phase II General Design 
Memorandum. 
Operations and results during fiscal year. 
Work on Phase I General Design Memorandum was 
continued at a cost of $96,852. Total costs including 
Construction, General, funds are $349,888. 
39.SCAJAQUADA CREEK, N.Y. 
Location. Scajaquada Creek is a small stream 
draining to the Black Rock Canal and thence to 
Niagara River at Buffalo, New York. It flows from 
east to west and its drainage area is all in Erie County. 
About 65 percent of the watershed is upstream from 
the city of Buffalo, mostly in the towns of 
Cheektowaga and Lancaster, and the village of 
Depew. (See Geological Survey Maps of Buffalo- 
Northeast, N.Y. and Lancaster, N.Y.) 
Existing project. For description of existing 
project see page 32-23 of Annual Report for 1977. 
Estimated costs (Oct. 1980) are $5,065,000 Federal and 
$4,060,000 non-Federal. Existing project was 
authorized by Section 201 of 1965 Flood Control Act. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Net 
credit to project after contributed funds were received 
was $6,831. 
32-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
40.INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Inspection of completed flood control works for 
compliance with Federal requirements were made 
during the period at a cost of $53,049. Total cost to 
Sept. 30, 1983 was $348,221. 
41.OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
See Table 32-F 
42.FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
See Table 32-G. 
42.DEAUTHORIZED PROJECTS 
See Table 32-H. 
43.SURVEYS 
During FY 1983, costs of $2,051,330 were incurred as 
shown below: 
Navigation Studies ..................... $1,131,577 
Flood Damage Prevention Studies ......... 656,642 
Shoreline Protection Studies .................. 914 
Special Studies ............................ 13,575 
Miscellaneous Investigations .............. 24,994 
Coordination Studies ........................ 1,996 
Phase I GDM Studies..................... 221,632 
44.COLLECTION AND STUDY OF 
BASIC DATA 
During the period, costs of $19,927 were incurred in 
connection with International Water Studies under 
the General Investigations appropriation and 
$113,517 incurred under the Operation and 
Maintenance appropriation for total costs of $133,444. 
Flood plain management services were performed 
during the year at a cost of $188,537. During the year, 
flood hazard evaluation studies were continued for the 
Seneca Nation of Indians, and Ellicott Creek, Alden, 
N.Y. Costs for general hydrologic studies were $2,794. 
46.ADVANCE ENGINEERING AND 
DESIGN 
Costs during the period were $160,850 for advance 
engineering and design projects. For details of 
individual projects, see sections 12 and 38 in text. 
32-16

TABLE 32-A 
BUFFALO, N.Y. DISTRICT 
COST AND FINANCIAL STATEMENT 
See 
Section 
in Total Cost to 
Text Project Funding FY 80 FY 81 FY 82 FY 83 Sept. 30, 1983 
1. Ashtabula Harbor, 
Ohio 
2. Barcelona 
Harbor, N.Y. 
3. Black Rock Channel 
and Tonawanda 
Harbor, N.Y. 
4. Buffalo Harbor, 
N.Y. 
5. Cape Vincent 
Harbor, N.Y. 
6. Cattaraugus Harbor, 
N.Y. 
(Contrib. Funds) 
7. Cleveland Harbor, 
Ohio 
8. Conneaut Harbor, 
Ohio 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
685,000 780,000 
744,154 780,753 
- 3,665,000 
- 3,663,962 
10,857 
20,432 
843,000 
803,060 
934,500 
938,245 
1,005,000 
75,088 
305,506 
292,147 
1,170,000 
990,594 
1,370,000 
1,356,667 
380,000 
1,287,156 
37,000 382,500 
45,082 208,323 
- 450,000 
84,854 
5,788,000 
6,054,122 
5,450,000 
7,397,311 
215,000 
185,800 
268 
3,643,182 
4,201,154 
1,380,000 
1,363,651 
474,400 
511,609 
112,000 
-34,614 
2,512,000 
2,357,273 
-3,239 
11,087 
1,408,000 
1,624,585 
3,042,000 
2,452,622 
55,000 
89,724 
- 12,805,3391 
- 12,805,3391 
770,000 8,564,666 
673,834 8,317,145 
-100,000 6,077,000 
55,760 6,076,995 
232,168 
105,051 
1,185,8532 
1,185,8532 
594,334 
467,217 
- 10,515,1203 
- 10,515,1203 
1,065,000 26,939,3484 
820,815 26,671,0824 
- 23,115,1878 
- 23,115,1878 
470,000 46,286,800 
1,033,360 46,246,8846 
- 295,457 
- 295,457 
- 275,082 
- 275,082 
- 1,562,206 
461 1,562,206 
3,050,000 951,560 
3,217,467 954,186 
- 192,500 
5,067,801 
4,777,586 
16,967 
630,000 
604,527 
5,001,060 
4,996,037 
2,516,500 
2,323,936 
- 31,653,2997 
- 31,653,2997 
6,169,500 128,882,3608 
4,477,275 126,867,2658 
- 10,294,903 
9,492 10,294,903 
- 
1,165,000 
1,074,711 
8,346,6419 
8,346,6419 
7,517,40210 
7,395,6491� 
651,850 
651,850 
32-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 32-A (Cont'd.) COST AND FINANCIAL STATEMENT 
See 
Section 
in Total Cost to 
Text Project Funding FY 80 FY 81 FY 82 FY 83 Sept. 30, 1983 
9. Dunkirk Harbor, 
N.Y. 
(Federal Funds) 
(Contrib. Funds) 
10. Erie Harbor, Pa. 
11. Fairport Harbor, 
Ohio 
12. Geneva-on-the 
Lake, Ohio 
13. Huron Harbor 
Ohio 
(Federal Funds) 
(Contrib. Funds) 
14. Irondequoit Bay, 
N.Y. 
15. Lorain Harbor, 
Ohio 
16. Ogdensburg Harbor, 
N.Y. 
17. Oswego Harbor, 
N.Y. 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
800,000 
1,236,918 
25,055 
31,473 
1,000,000 
1,499,407 
- 
135,000 
175,382 
- 
425,000 
448,004 
140,000 
149,800 
1,038 
433,000 
557,976 
- 
110,000 
111,633 
- 
-30 
439,000 
453,703 
8,010 
2,667 
32,000 
31,621 
-19,400 
-16,483 
20,000 
18,485 
450,593 
256,000 
253,772 
445,000 
407,162 
210,000 
235,727 
509,000 
546,850 
125,000 
137,817 
-27,000 
-22,990 
525,000 
519,884 
45,007 
34,913 
80,000 
70,010 
5,439 
8,633 
190,000 
187,272 
580,000 
604,849 
18,595 
660,000 
633,426
- 
125,000 
113,752 
59 
1,004,000 
1,005,970 
- 
6,424 
23,818 
620,000 
625,113 
- 3,010,02411 
- 3,010,0241" 
229,335 1,657,276 
216,150 1,644,091 
- 1,950,000 
- 1,950,00012 
- 3,597,87313 
- 3,597,87313 
2,588,000 14,436,81914 
332,770 12,172,26914 
- 1,154 
- 1,154 
- 2,959,611s15 
- 2,959,611s15 
675,500 11,317,703 
595,053 11,220,994 
662,000 
662,000 
- 5,103,79516 
- 5,103,79516 
447,000 12,714,403 
444,078 12,682,550 
- 247,030 
- 247,030 
- 63,079 
- 63,079 
135,800 
65,534 
1,000,800 
917,666 
- 20,739,5581 
- 20,739,55817 
1,397,000 19,785,429 
1,377,008 19,762,458 
788 
1,017 
646,46618 
646,46618s 
1,326,3831" 
1,326,38319 
- 8,430,01620 
- 8,430,01620 
559,000 5,847,81521 
558,442 5,842,00221 
- 307,590 
- 307,590 
32-18

BUFFALO, N.Y. DISTRICT 
TABLE 32-A (Cont'd.) COST AND FINANCIAL STATEMENT 
See 
Section 
in Total Cost to 
Text Project Funding FY 80 FY 81 FY 82 FY 83 Sept. 30, 1983 
18. Port Clinton, 
Ohio 
19. Rochester Harbor, 
N.Y. 
20. Rocky River, 
Ohio 
21. Sandusky Harbor, 
Ohio 
22. Toledo Harbor, 
Ohio 
23. West Harbor, 
Ohio 
(Contrib. Funds) 
27. Lakeview Park, 
Lorain, Ohio 
(Federal Funds) 
(Contrib. Funds) 
28. Presque Isle 
Peninsula, Erie, Pa. 
(Federal Funds) 
(Contrib. Funds) 
30. Lakeshore Park 
Ashtabula, Ohio 
(Federal Funds) 
(Contrib. Funds) 
31. Cayuga Creek 
Cheektowaga, N.Y. 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
5,227 
5,227 
1,070,000 
575,062 
25,000 
22,128 
521,700 
416,883 
1,554,000 
1,654,161 
37,000 
36,654 
365,000 
854,160 
840,000 
833,557 
1,040,300 
1,157,595 
2,388,000 
2,377,534 
100,000 800,000 
143,982 808,224 
- 800,000 
- 764,079 
70,000 
61,801 
750,000 
768,870 
321,429 
331,881 
50,000 
60,556
-_ 
44,000 
41,840 
80,000 
61,911 
850,000 
850,115 
364,286 
364,611 
260,000 
26,781 
595,000 
598,867 
4,208 
12,584 
525,000 
518,185 
4,315,000 
4,101,546 
71,950 
71,950 
850,054 
723,994 
120,005 
236,517 
- 2,439,30822 
- 2,439,30822 
1,721,000 12,921,81623 
1,106,232 12,301,41023 
6,298 
7,237 
919,0 
916,5 
3,482,5 
3,540,1 
343,494 
343,494 
1,573,313 
1,573,313 
- 6,727,27024 
- 6,727,27024 
)00 11,247,199 
506 11,232,485 
- 675,606 
- 675,606 
- 17,191,84225 
- 17,191,84225 
500 63,455,864 
127 61,734,316 
1,840,000 318,898 
1,838,914 319,694 
- 628,000 
- 486,266 
54,655 
61,797 
1,000,000 
994,477 
428,571 
429,914 
7,000 410,000 
51,605 404,205 
- 262,000 
- 150,337 
53,000 
30,116 
1,249,000 
1,233,558 
22,737 
740,000 
741,242 
368,175 
307,785 
195,000 
199,957 
81,438 
-55,000 
-17,273 
3,393,898 
3,391,613 
3,795,000 
3,653,253 
1,716,125 
1,709,017 
729,000 
729,000 
9,435,562 
9,431,268 
4,438,172 
4,377,780 
3,842 
3,842 
786,444 
785,904 
262,000 
231,775 
1,462,000 
1,404,241 
32-19

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 32-A (Cont'd.) COST AND FINANCIAL STATEMENT 
See 
Section 
in Total Cost to 
Text Project Funding FY 80 FY 81 FY 82 FY 83 Sept. 30, 1983 
32. Cuyahoga River New Work 
Basin, Ohio Approp. 87,000 100,000 50,000 10,000 1,117,000 
Cost 78,021 72,615 81,750 17,903 1,113,329 
33. Dansville and New Work 
Vicinity, Canaseraga Approp. 75,000 70,000 - 25,000 490,300 
Creek, N.Y. Cost 82,090 61,164 13,355 16,053 479,574 
34. Ellicott Creek, New Work 
N.Y. Approp. 72,000 150,000 150,000 61,000 1,880,000 
Cost 92,928 151,067 116,912 73,709 1,766,612 
35. Euclid Creek New Work 
Cleveland, Ohio Approp. 61,000 60,000 140,000 2,220,000 2,772,000 
Cost 63,464 50,696 100,497 78,324 579,235 
36. Mt. Morris New Work 
Lake, N.Y. Approp. - - - - 23,365,55927 
Genesee River Cost - - - - 23,365,55927 
Maint. 
Approp. 708,000 890,300 905,000 1,035,000 8,080,309 
Cost 734,473 864,402 919,439 784,649 7,807,682 
37. Point Place New Work 
Toledo, Ohio Approp. 239,000 250,000 800,000 2,300,000 3,499,000 
(Federal Funds) Cost 415,773 250,855 587,705 1,348,602 3,133,813 
(Contrib. Funds) New Work 
Approp. - - - 300,000 300,000 
Cost - - - 15,150 15,150 
38. Reno Beach-Howard New Work 
Farms, Ohio Approp. 70,000 80,000 - - 150,000 
Cost 69,938 74,574 5,488 - 150,000 
39. Scajaquada Cr., New Work 
N.Y. Approp. 1,715,000 680,000 40,345 -30,800 4,944,852 
Cost 1,843,529 623,276 92,343 -6,831 4,943,596 
1. Includes $565,192 for previous projects. Excludes 
$47,000 contributed funds. 
2. Includes $56,616 for previous projects. Excludes $7,500 
contributed funds. 
3. Includes $58,027 for previous projects. 
4. Includes $4,922 emergency relief authority 
administrative costs transferred from new work to 
maintenance upon conversion to programming and 
budgeting system July 1, 1953, by direction of Office, 
Chief of Engineers. Also includes appropriations and 
costs under appropriation titles 96x3123 Operation and 
Maintenance and 96x5125 Maintenance and Operation 
of Dams and Other Improvements of Navigable Waters. 
5. Includes $4,277,586 for previous projects. Excludes 
expenditures of $239,305 for work authorized by Section 
107. 
6. Includes $1,883,647 for previous projects. Excludes 
$446,805 contributed funds. 
7. Includes $1,564,154 for previous project and 
appropriations and costs of $16,596 for modification 
authorized for construction under authority of Sec. 107, 
1960 R&H Act. 
8. Includes appropriations and costs under appropriation 
titles 96x3123 Operation and Maintenance and 96x5125 
Maintenance and Operation of Dams and other 
improvements of Navigable Waters. Excludes $201,960 
contributed funds. 
9. Includes $805,272 for previous projects. 
10. Includes $39,784 for previous projects. 
11. Includes $811,250 for previous projects. Excludes 
$11,000 contributed funds. 
12. Includes $176,520 for previous projects. 
13. Includes $736,967 for previous projects. 
14. Includes $104,900 for previous projects. Excludes 
$154,500 contributed funds. 
15. Includes $368,940 for previous projects. 
16. Includes $269,789 for previous projects. 
17. Includes $292,203 for new work for previous projects. 
Excludes $3,000 contributed funds. Also excludes 
appropriation and cost of $29,570 under authority of 
Section 107, 1960 R&H Act. 
18. Includes $271,380 for previous projects. 
19. Includes $130,512 for previous projects. 
20. Includes $1,187,977 for previous projects. 
21. Includes $945,684 for previous projects. 
22. Includes $247,794 for previous projects. 
23. Includes $617,529 for previous projects and $478 
emergency relief authority administration costs 
transferred from new work to maintenance upon 
conversion to programming and budgeting system, 
July 1, 1953, by direction of Office, Chief of Engineers. 
24. Includes $477,149 for previous projects. Excludes 
$325,000 contributed funds. 
25. Includes $1,624,695 for previous projects. 
26. Includes $16,914 for previous projects. 
27. Excludes $5,000 contributed funds. 
32-20

BUFFALO, N.Y. DISTRICT 
TABLE 32-B (Cont'd.) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
June 3, 1896 
Mar. 3, 1905 
June 25, 1910 
Mar. 2, 1919 
Aug. 30, 1935 
Aug. 26, 1937 
Mar. 2, 1945 
Sept. 3, 1954 
July 14, 1960 
Oct. 27, 1965 
Aug. 11, 1888 
June 3, 1896 
June 13, 1902 
June 13, 1902 
Aug. 8, 1917 
Mar. 3. 1905 
July 27, 1916 
Mar. 2, 1919 
Mar. 2, 1945 
ASHTABULA HARBOR, OHIO (See Section 1 of Text) 
Construction of breakwater. 
Enlarge outer harbor by extending west breakwater and constructing 
new east breakwater; pierheads on lakeward ends 
of breakwaters; and remove part of old east breakwater. 
Extend west breakwater to shore; dredge outer harbor to a 
depth of 20 feet. 
Remove portion of east breakwater, extend breakwaters to 
present project dimensions, and dredging restrictions in 
portion of west basin. 
Dredge channel through outer harbor, channel of approach 
to Penn Central Co. slip, channel in Ashtabula River, 
to and in turning basin, all to present project dimensions; 
remove portion of old east inner breakwater; and 
maintenance to 24-foot depth of portion of 
outer harbor. 
Extend river channel to present project limit. 
Dredging approach channel and turning basin in east 
outerharbor to 25-foot depth. 
A depth of 29 feet in soft and 30 feet in hard material in entrance 
channel to just inside outer ends of breakwaters; 
thence 28 feet in soft and 29 feet in hard material in 
a channel to inner breakwater: thence 27 feet in soft and 
28 feet in hard material in a channel extending to Penn 
Central Co. slip and extending 2000 feet up Ashtabula 
River; 22 feet in hard material in turning area; and 28 
feet in soft and 29 feet in hard material in areas adjacent 
to 250-foot section of inner breakwater when that section 
is removed as now authorized. 
Dredging approach channel and turning basin in east 
outer harbor to 28 feet in soft material and 29 feet 
in hard material. 
BLACK ROCK CHANNEL AND TONAWANDA 
HARBOR, N.Y. (See Section 3 of Text) 
Dredging channel through Horseshoe Reef at outlet of 
Lake Erie and Tonawanda Inner Harbor. to 16 feet. 
Deepening Tonawanda Creek to 16 feet. 
Dredging channel from Buffalo outer harbor to foot 
of Maryland St., Buffalo, to 21 feet. 
Dredging channel from foot of Maryland St.. Buffalo, 
to natural deepwater pool upstream from Tonawanda 
Harbor to 21 feet; construction of ship lock and bridge; 
and repair of Bird Island pier and towpath wall. 
Dredging channel along Tonawanda Island, with turning 
basin at its downstream end at the foot of the Island, 
to 21 feet. 
Dredging triangular area at junction with Buffalo north 
entrance channel. 
Annual Report, 1895, p. 
2132. 
H. Doc. 654, 61st Cong., 2d 
sess. 
H. Doc. 997, 64th Cong., 1st 
sess. 
H. Doc. 43, 73d Cong., 1st 
sess. 
Rivers and Harbors Committee 
Doc. 78, 74th Cong., 2d 
sess. 
H. Doc. 321. 77th Cong., 1st 
sess. 
H. Doc. 486. 83d Cong., 2d 
sess. 
H. Doc. 148. 86th Cong., 
Ist sess. 
H. Doc. 269. 89th Cong.. 
1st sess.' 
H. Ex. Doc. 83. 50th Cong.. 
1st sess.. Annual Report, 
1888, p. 2066, and Annual 
Report. 1897. pp. 3116- 
3120. 
H. Doc. 143, 56 Cong., I1st 
sess., and Annual Report, 
1900, p. 4152. 
H. Doc. 125, 56th Cong., 2d 
sess., and Annual Report, 
1901, p. 3343. 
H. Doc. 428, 58th Cong., 
2d sess. 
H. Doc. 658. 63rd Cong.. 
2d sess. 
H. Doc. 1004. 65th Cong.. 2d 
sess. and H. Doc. 92, 79th 
Cong.. 1st sess. 
32-21

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 32-B (Cont'd.) 
Acts 
Sept. 22, 1922 
Mar. 3, 1925 
June 26, 1934' 
Aug. 30, 1935' 
Mar. 2, 1945 
Sept. 3, 1954 
May 20, 1826 
June 23, 1866 
June 23, 1874 
June 3. 1896 
Mar. 3, 1899 
Mar. 3, 1909 
June 6, 1900 
June 13, 1902 
Mar. 2, 1907 
Mar. 2, 1907'1� 
June 25, 1910 
July 25, 1912 
Mar. 2, 1919 
Jan. 21, 1927 
July 3, 1930 
Aug. 30, 1935" 
Aug. 30. 1935 
AUTHORIZING LEGISLATION 
Work Authorized 
Widening channel at foot of Maryland St., Buffalo. 
Widening canal south of International Bridge and removal 
of westerly end of Rattlesnake Island shoal. 
Operation and care of improvements provided for with funds 
from War Department appropriations for rivers and 
harbors. 
Removal of rock shoals in Lake Erie entrance to canal, 
and in canal south of Ferry Street Bridge, to 22 feet; enlargement 
of North Tonawanda turning basin; extension of 
Bird Island pier; improvement of guide pier at the 
lock; and elimination of upper 150 feet of Tonawanda 
Creek channel from the project.' 
Widening Lake Erie entrance to canal. 
Deepen lower 1,500 feet of Tonawanda inner harbor and 
enlarge turning basin. 
BUFFALO HARBOR, N.Y. (See Section 4 of Text) 
Construction of south pier (extended in 1868)' 
Construction of old breakwater.' 
Extension of old breakwater.' 
Stony Point and south breakwater.' 
North breakwater.'9 
Deepening entrance channel to inner harbor and removing 
rock shoal therein. 
Dredging at entrance to canals at South Buffalo in 
outer harbor.' 
South entrance breakwater.' 
Extension of Federal project to Commercial St. and 
removal of Watson elevator site.' 
Deepening areas A, B, and D in outer harbor to 21 
feet, and area C in north entrance to 23 feet. 
Deepening areas F and G in outer harbor to 21 feet. 
Removal of shoal between entrance channel to Buffalo 
River and Erie Basin to 21 feet. 
Deepening areas H, I, and K in outer harbor to 21 feet. 
Extension of south entrance and south breakwaters, 
deepening outer harbor to present project dimensions, 
and removal of shoals on approach to south entrance. 
Maintenance of channels in Buffalo River and Buffalo 
Bshuifpfa claon. al to 21 feet, in cooperation with city of 
Documents 
H. Doc. 981, 66th Cong., 
3d sess. 
H. Doc. 289, 68th Cong., 
1st sess. 
H. Doc. 28, 73d Cong., 
1st sess. 
H. Doc. 92, 79th Cong., 
1st sess. 
4 
H. Doc. 423, 83rd Cong., 
2d sess. 4"8 
Annual Report, 1868, pp. 
222 and 232. 
Annual Report, 1868, pp. 
232-236. 
Annual Report, 1876, pt. 2, 
pp. 569 and 573. 
Annual Report, 1895, 
p. 3153. 
H. Doc. 72, 55th Cong., 1st. 
sess., and Annual Report, 
1897, p. 3245. 
Specified in acts. 
Specified in act. 
H. Doc. 240, 59th Cong., 
1st sess. 
H. Doc. 298, Rivers and 
Harbors Committee Doc. 
2, 61st Cong., 2d sess. 
H. Doc. 550, 62d Cong., 
2d sess. 
H. Doc. 1139, 64th Cong., 
1st sess. 
H. Doc. 481, 68th Cong., 
2d sess. 
Rivers and Harbors Committee 
Doc. 1, 71st Cong., 
1st sess. 
H. Doc. 46, 73d Cong., 
1st sess. 
Rivers and Harbors Committee 
Doc. 54, 74th Cong., 
1st sess. 
32-22

BUFFALO, N.Y. DISTRICT 
TABLE 32-B (Cont'd.) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Mar. 2, 1945" 
July 14, 1960 
Oct. 23, 1962 
Dec. 15, 1980 
Mar. 3, 1899 
Mar. 2. 1945 
Mar. 3, 1875 
Aug. 5, 1886 
Aug. 11, 1888 
June 3, 1896 
Mar. 3, 1899 
June 13, 1902 
June 13, 1902 
Mar. 2, 1907 
June 25, 1910 
July 27, 1916 
Aug. 8, 1917 
Aug. 29, 1937 
Aug. 30, 193512 
Deepening North and Buffalo River entrance channels, 
and deepening and maintaining Buffalo River and 
Buffalo ship canal to present project dimensions. 
Deepening approach to south entrance channel to 30 feet; 
deepen to 30 feet in outer area and 29 feet in inner area of 
south entrance channel; and deepen to 28 feet southerly 
part of outer harbor. 
Deepening portion of outer harbor to 27 feet over a width of 
500 feet for 2,500 feet northward from 28-foot project area, 
widening within 1,700 feet to limits within 150 feet of 
breakwater axis and 75 feet from harbor line and 
continuing within these limits for 7,000 feet. Elimination 
of 25-foot wide strip between presently authorized and 
proposed easterly dredging limits. Elimination of easterly 
50-foot wide undredged strip in existing 23-foot depth 
project area, extending northerly from 27-foot depth area 
to Buffalo River entrance channel. Previously authorized 
but uncompleted portions of work authorized by 1935 
act, combined with this act as a single improvement. 
Removal of abandoned abutments of South Michigan 
Avenue bridge. 
CAPE VINCENT HARBOR, N.Y. (See Section 5 of Text) 
Breakwater 1,000 feet long, and shore arm not to 
exceed 150 feet. 
Deepening to project dimensions; elimination from 
project of uncompleted portion of breakwater. 
CLEVELAND HARBOR, OHIO (See Section 7 of Text) 
West breakwater 
Part of east breakwater.' 
Extension of east breakwater.' 
Reconstruction of piers.9 
Dredging channel between piers and outer harbor to depth 
of 19 feet; dredging to depth of 23 feet in any portion 
of harbor in discretion of Secretary of War. 
Arrowhead breakwater and extension of east breakwater. 
Removal of deflecting arm of old east breakwater and 
closure of gap between old and new east breakwaters. 
Pierhead at easterly end of east breakwater. 
Maintenance and improvement of channels in Cuyahoga 
and Old Rivers to a depth of 21 feet to a point 2,000 feet 
upstream from Clark Ave. viaduct and 18-foot 
turning basin. 
Deepening outer harbor and channel between piers to present 
project dimensions, construction of 400-foot spur breakwater 
at gap in shore arm of west breakwater; removal of 
easterly 150 feet of west main breakwater; elimination 
from project of a 298-foot southerly extension of west 
pier; and abandonment of inner 932 feet of shore arm 
of west breakwater. 
H. Doc. 352, 78th Cong., 
1st sess. 
H. Doc. 151, 86th Cong., 
1st sess. 
H. Doc., 451, 87th Cong., 
2d sess. 
Section 107, 1960 River 
and Harbor Act. 
Annual Report, 1897, 
pp. 3286-3288. 
H. Doc. 363, 76th Cong., 
1st sess.' 
Annual Report, 1876, p. 558. 
H. Ex. Doc. 116, 48th Cong., 
2d sess., and Annual 
Report, 1886, p. 1865. 
H. Ex. Doc. 189, 50th Cong., 
1st sess., and Annual 
Report, 1888, p. 2005. 
H. Doc. 326, 54th Cong., 1st. 
sess., and Annual Report, 
1896, p. 2949. 
H. Doc. 156, 55th Cong., 
3d sess., and Annual 
Report, 1899, pp. 3075 and 
3078. 
H. Doc. 118, 56th Cong., 
2d sess. 
No printed report. 
H. Doc. 891, 63d Cong., 
2d sess. 
H. Doc. 707, 63d Cong., 
2d sess., and Rivers and 
Harbors Committee Doc. 
84, 74th Cong., 2d sess. 
H. Doc. 477, 72d Cong., 
2d sess. 
32-23

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 32-B (Cont'd.) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Aug. 30, 1935" 
Mar. 2, 1945" 
July 24, 1946 
July 3, 1958 
July 14, 1960 
Oct. 23, 1962 
Dec. 6, 1966 
Oct. 22, 1976 
(Sec. 175) 
Maintenance dredging in Cuyahoga and Old Rivers for 
1 year as an emergency measure. 
Maintenance of extension of Cuyahoga River channel. 
Extension, maintenance, and improvement to a depth of 
21 feet of Cuyahoga River channel to present project 
limit.,t,16 
Improvement of Cuyahoga and Old Rivers to a depth of 23 
feet and replacement or pier construction of 7 
railroad bridges.2 
Deepening channel 25 feet through east basin of outer 
harbor; replacement of Erie- Lackawanna Railroad bridge 
over Cuyahoga River at mile 4.1 and widening of 
channel at that point, with elimination of 
reconstruction of east pier of bridge as previously 
authorized; and replacement of Baltimore & 
Ohio Railroad Bridge over Old River near its 
mouth and Willow Avenue Highway Bridge about 800 
feet above mouth and widening channel at four 
locations along lower 2,000 feet of river.' 
Depth of 29 feet in lake approach to main entrance; 
28 feet in entrance channel to lakeward ends of piers at 
mouth of Cuyahoga River; 27 feet in river to a point just 
above its junction with Old River, and in Old River to 
upstream limit of present 23-foot project; 28 feet in west 
basin within existing project limits as modified to eliminate 
a triangular area at west end and to extend limits to a 
line parallel to and 75 feet from harbor line; and 28 
feet in westerly 800 feet of east basin."5 
An area in east basin 27 feet deep extending about 3,800 
feet easterly of 28-foot area with project limits 380 feet 
from east breakwater and on landward side generally by a 
line 75 feet lakeward of and parallel to harbor line. A 
dock channel to Nicholson Cleveland Terminal Co. pier, 
at easterly end of east basin, from 25-foot contour to a 
limit 75 feet north of pierhead line, 400 feet wide at 
shoreward end and flared toward the lake. 
Deepening upper end of Old River channel from 21 to 
27 feet. 
Preparation of Phase I design memorandum for 
improvements consisting of removal of portions of 
entrance breakwater; construction of breakwater extension 
at east entrance; deepening approach and entrance 
channels; construction of diked disposal area; 
and, installation of recreational fishing facilities on 
west breakwater. 
CONNEAUT HARBOR, OHIO (See Section 8 of Text) 
Extension of east breakwater, construction of new west 
breakwater; removal of portion of old west breakwater; 
and dredging of outer harbor to 19 feet. 
Realinement of west breakwater; removal of remainder of 
old west breakwater, and deepening outer harbor to 
20 feet. 
Removal by Bessemer & Lake Erie R.R. Co. of inner 
635 feet of west pier. 
H. Doc. 653, 61st Cong., 
2d sess. 
H. Doc. 983, 64th Cong., 
1st sess. 
32-24 
Rivers and Harbors 
Committee Doc. 39, 74th 
Cong., 1st sess. 
Specified in act. 
H. Doc. 95, 79th Cong., 1st. 
sess. 
H. Doc. 629, 79th Cong., 
2d sess. 
H. Doc. 107, 85th Cong., 
1st sess. 
H. Doc. 152, 86th Cong., 
1st sess. 
H. Doc. 527, 87th Cong., 
2d sess.' 
Sec. 107, 1960 River and 
Harbor Act. 
June 25, 1910 
Aug. 8, 1917

BUFFALO, N.Y. DISTRICT 
TABLE 32-B (Cont'd.) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Aug. 30, 1935" 
Oct. 23, 1962 
Nov. 7, 19668 
Mar. 2, 1827 
Mar. 2. 1867 
June 3, 1896 
June 25, 1910 
June 30. 1948 
Dec. 15, 1970 
(House Public 
Works Comm.) 
June 22, 1971 
(Senate Public 
Works Comm.) 
Sec. 201 of F.C. 
Act of 1965 
May 26, 1824 
Mar. 3, 1899 
June 15, 1910 
Nov. 28, 192220 
Removal of a portion of west breakwater; extension of 
breakwaters to present project dimensions; construction 
of pierheads on outer ends of breakwaters; deepening 
outer harbor to present project dimensions; removal of 
portions of river pier, and elimination from project of a 
255-foot shoreward extension of west breakwater. 
Deepening easterly part of outer harbor to 28 feet in 
soft material and 29 feet in hard material; deepening 
remaining triangular area of outer harbor to 22 feet in 
soft material and 23 feet in hard material; deepening inner 
harbor for 2.450 feet upstream of outer end of west pier 
to 27 feet in soft material and 28 feet in hard material; 
removal of east pier; extension of east breakwater to 
shore; and an access channel 8 feet deep in outer harbor 
to city dock. Previously authorized but uncompleted 
portion of work authorized by 1917 and 1935 acts combined 
with this act for accomplishment as a single improvement. 
Recreational small-boat harbor provided by: a stone dike 
about 2,200 feet long; access channels 6 feet deep., 
2,800 feet long and 100 feet wide; closing of 100-foot gap 
in existing west breakwater; and personnel guard rail 
on west breakwater. 
DUNKIRK HARBOR, N.Y. (See Section 9 of Text) 
Construction of west pier.9 '8 
Breakwater and excavation of entrance channel to 13 feet. 9 
Deepening of entrance channel and harbor basin to a 
depth suitable for vessels of 16-foot draft. 
Removal of rock reef bordering the inner entrance channel. 
Deepening outer entrance channel to present project 
depths; removal of rock shoal on the west side of the 
entrance channel to a depth of 17 feet, and changed limits 
of the inner entrance channel and basin to present 
project dimensions. 
Construction of small boat harbor. 
ERIE HARBOR, PA. (See Section 10 of Text) 
Breakwaters and piers; dredging entrance channel; and 
brushwood protection of beach of Presque Isle 
Peninsula.9 
Deepening channel and harbor basin to 18 feet; repair 
and extension of piers; and plant growth and emergency 
protection work on peninsula. 
Deepening channel and part of harbor to 20 feet. 
Reconveyed Presque Isle Peninsula to the State of 
Pennsylvania for park purposes. 
H. Doc. 48, 73d Cong., 1st 
sess. 
H. Doc. 415, 87th Cong., 
2d sess. 
H. Doc. 484, 89th Cong., 
2d sess.' 
S. Ex. Doc. 42. 35th Cong., 
1st sess., and Annual 
Report, 1866, pt. IV. 
p. 155 
Annual Report. 1871. p. 214. 
H. Doc. 63, 54th Cong., 
1st. sess. 
H. Doc. 720, 61st Cong., 
2d sess.' 
H. Doc. 632, 80th Cong., 
2d sess. 
H. Doc. 91-423. 91st Cong., 
2d sess. 
Annual Report. 1915. p. 
1965. 
H. Doc. 70. 55th Cong.. 
1st sess. and Annual 
Report, 1896. p.3237.1' 
Rivers and Harbors 
Committee Doc. 26, 61st 
Cong., 2d sess. 
32-25

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 32-B (Cont'd.) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Aug. 30, 1935 
Mar. 2, 1945 
Sept. 3, 1954 
July 14, 1960 
Oct. 23, 1962 
Mar. 3, 182521 
June 3, 1896 
Mar. 3, 1905 
Mar. 2, 1919 
Jan. 21, 1927 
July 3, 1930 
Aug. 30, 193522 
Aug. 26. 1937 
July 24, 1946 
July 14, 1960'� 
Deepening, widening, and straightening entrance channel, 
dredging channel at easterly end of harbor basin, 
deepening a portion of harbor basin, all to present 
project dimensions; elimination of north breakwater 
from project; and limitation of south breakwater to a 
length of 1,200 feet. 
Protection of the peninsula south of the waterworks 
settling basin. 
Widen 25-foot deep approach channel to ore dock. 
Depth of 29 feet in the entrance channel to a point 
opposite the inner end of the north pier; thence 28 
feet in soft and 29 feet in hard material in the 
remainder of the entrance channel, within the general 
limits of the 25-foot basin and inner channel opposite 
the ore dock except as modified to eliminate from the 
project a triangular area along the easterly side; and a 
depth of 28 feet over a 300-foot westward extension of the 
25-foot basin. 2' 
Depth of 27 feet in soft material and 28 feet in hard 
material in approach area to Duquesne Marine Terminal. 
Previously authorized but uncompleted portion of work 
authorized by 1935 act is combined with this act as a 
single improvement. 
FAIRPORT HARBOR, OHIO (See Section 11 of Text) 
Construction of piers. 
Breakwaters and dredging outer harbor to a depth of 
18 feet. 
1,400-foot extension of east breakwater, present project 
dimension of east pier; and deepening of harbor to 19 feet. 
4,000-foot extension of east breakwater at limit of cost 
to the United States of $715,000. 
Deepening of outer harbor and entrance channel to present 
project dimensions; extending the west breakwater to 
present project dimensions with pierhead at its outer 
end; removal of west pier; and construction of bulkhead 
on west side of river channel. 
Dredging of 21- and 24-foot river channels and turning 
basin in Grand River to present project dimensions. 
Dredging of 8-foot river channel. 
Depth of 29 feet in the approach channel from the lake; 
a depth of 28 feet over a width of 800 feet in the 
outer harbor: a depth of 27 feet in soft and 28 feet 
in hard material in Grand River, over a width of 200 
feet to the upstream limit of the turning basin, with 
suitable widening at the bends, thence over widths 
reducing from 200 to 100 feet to the upstream limit 
of the existing Federal project, except in the 8-foot 
channel; enlargement of the turning basin, including 
deepening of the entire basin to 21 feet; and minor 
modification of the existing project limits in the outer 
harbor. 
H. Doc. 52, 73d Cong., 
1st sess. 
Specified in act. 
H. Doc. 345, 83d Cong., 
2d sess. 
H. Doc. 199, 86th Cong., 
1st sess.' 
H. Doc. 340, 87th Cong., 
2d sess.' 
Annual Report, 1889, pp. 
2147-2153 
H. Doc. 347, 54th Cong., 1st 
sess. and Annual Reports, 
1896, p. 2956; 1903, p. 
2084; 1905, p. 2349. 
H. Doc. 206, 63d Cong., 
1st sess. 
H. Doc. 592, 69th Cong., 2d 
sess., Rivers and Harbors 
Committee Doc. 13, 70th 
Cong., 1st sess. 
H. Doc 472. 72d Cong., 
2d sess. 
Rivers and Harbors 
Committee Doc. 79, 74th 
Cong., 2d sess.4 
H. Doc. 706, 79th Cong., 
2d sess.4 
H. Doc. 347, 86th Cong., 
2d sess.4 
32-26

BUFFALO, N.Y. DISTRICT 
TABLE 32-B (Cont'd.) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
May 10, 1977 
(House Public 
Works Comm.) 
Oct. 1, 1976 
(Senate Public 
Works Comm.) 
Sec. 201 of F.C. 
Act of 1965 
Construction of small boat harbor. H. Doc. 627. 94th Cong., 
2d sess. 
HURON HARBOR, OHIO (See Section 14 of Text) 
Extension of west pier; construction of east breakwater:; 
removal of part of old east pier; deepening of channel 
to 19 feet; and dredging of sheltered area. 
Widening river to 200 feet; removal of remainder of old 
east pier; construction of new spur pier; enlargement 
of sheltered area; and closure of breach at shore end 
of west pier. 
Extension of west pier with pierhead at its outer end; 
removal of outer end of east breakwater and 
constructing pierhead on new outer end; widening and 
deepening channel to present project dimensions; 
enlargement of turning basin at head of channel; 
shore protection west of west pier; and elimination 
from project construction of spur pier and dredging 
sheltered area outside channe[llmits. 
Depths of 29 feet in approach channel, 28 feet in 
entrance channel, 27 feet in river channel, 21 feet 
in turning basin, a detached breakwater, 1,575 feet 
long 2.000 feet lakeward of outer end of existing 
west pier: and, abandonment of lakeward end of 
existing approach channel.' 
H. Doc. 122, 58th Cong., 
2d sess. 
H. Doc. 5, 63d Cong., 
1st sess. 
H. Doc. 478, 72d Cong., 
2d sess. 
H. Dpc. 165, 87th Cong., 
1st seas.' 
32-27 
Mar. 2, 1905 
Mar. 2, 1919 
Aug. 30, 1935" 
Oct. 23. 1962

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 32-B (Cont'd.) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Mar. 3, 1899 
Mar. 2, 1907 
June 25, 1910 
Aug. 8, 1917 
Aug. 8, 1917 
July 3, 1930 
Aug. 30. 1935 
Aug. 30, 1935 
Aug. 30, 1935 
23 
Mar. 2, 1945 
July 14, 1960 
Oct. 27, 1965 
June 25, 1910 
Mar. 2, 1919 
Aug. 30, 1935" 
Apr. 20, 1983 
LORAIN HARBOR. OHIO (See Section 15 of Text) 
Breakwaters and extensions of piers to present dimensions. 
Extend 18-foot channel from inner end of piers to Erie 
Avenue Bridge. 
Extend breakwaters and dredge to depth of 19 feet in outer 
harbor. 
Extend breakwaters to present project dimensions. 
Deepen outer harbor and river channel to Erie Avenue 
Bridge to 20 feet. 
Extend 20-foot channel to American Shipbuilding Co. 
drydock 2. 
Widen 2 bends in river and enlarge turning basin opposite 
National Tube Co. dock.' 2 
Approach channel to municipal pier. 
Deepen outer harbor and river channel to American 
Shipbuilding Co. drydock 2 to present project 
dimensions and extension of river channel to upper 
end of National Tube Co. dock with turning basin 
opposite that dock. Maintenance dredging in Black River 
from American Shipbuilding Co. drydock 2 upper end of 
National Tube Co. dock was authorized Apr. 7, 1934, by 
Public Works Administration. 
Enlarging turning basin opposite National Tube Co. dock 
to present project dimensions. 
Turning basin in bend of Black River immediately 
upstream from Baltimore & Ohio RR coal dock. 
Replace Norfolk and Western Railway swing bridge with a 
vertical lift bridge; construct two detached arrowhead 
breakwaters lakeward of existing breakwaters; construct 
extension of east breakwater to shore; remove 300 feet 
of lakeward end of west breakwater; remove outer 1,100 
feet of east pier; deepen lake approach to 29 feet, 
800-foot wide outer harbor channel to 28 feet, 
southwesterly portion of outer harbor to 25 feet and 
river channel to 27 feet; widen river channel at bends; 
and construct a new turning basin 21 feet deep near 
upstream limit of existing project.3 2 
Construct bank of stabilization works at cut numbered 1 
along left bank of river channel above Erie Avenue 
Bridge.* 
OGDENSBURG HARBOR, N.Y. (See Section 16 of Text) 
Deepening the several channels to 19 feet. 
Widening upper entrance channel to 400 feet, and city 
front to 350 feet. 
Enlarging and deepening lower basin to 21 feet, and 
removal of elevator wharf. 
Extend Lower East Entrance Channel, 600 feet west of 
existing pier to a depth of 27 feet below LWD. Dredged 
material to be disposed of in dredged disposal area site 5, 
owned by Ogdensburg Bridge and Port Authority. 
H. Doc. 131, 55th Cong., 
2d sess. and Annual 
Report 1898, p. 
2718. 
H. Doc. 560, 60th Cong., 
1st sess. 
H. Doc. 644, 61st Cong., 
2d sess. 
H. Doc. 980, 64th Cong., 
1st sess. 
H. Doc. 985, 64th Cong., 
1st sess. 
H. Doc. 587, 69th Cong., 
2d sess. 
H. Doc. 469, 72d Cong., 
2d sess. 
Senate Committee print, 73d 
Cong., 2d sess. 
Rivers and Harbors Committee 
Doc. 51, 74th Cong., 
1st sess. 
Specified in act. 
H. Doc. 161, 77th Cong. 
1st sess. 
H. Doc. 166, 86th Cong., 
1st sess." 
PL 89-298. 
H. Doc. 920, 60th Cong., 
1st sess. 
H. Doc. 663, 64th Cong., 
1st sess. 
H. Doc. 266, 72d Cong., 
1st sess. 4 , 24 
Section 107, 1960 
River and Harbor Act 
32-28

BUFFALO, N.Y. DISTRICT 
TABLE 32-B (Cont'd.) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
July 11, 1870 
Mar. 2, 1907 
July 3, 1930 
Aug. 30, 1935 
Oct. 17. 1940 
June 30, 1948 
Sept. 3, 1954 
Oct. 23, 1962 
June 10, 1872 
Mar. 2, 1829 
Aug. 2. 1882 
June 25, 1910 
Aug. 30, 19356 
Mar. 2, 1945 
July 14, 1960 
OSWEGO HARBOR (See Section 17 of Text) 
Construction of outer west breakwater.9 ' 
Repair of outer west breakwater under Plan (A).9 
Construction of arrowhead breakwaters; deepening outer 
harbor between arrowhead breakwaters, west outer 
harbor east of Erie-Lackawanna coal dock, and Oswego 
River north of Seneca St., to 21 feet; and deepening 
west outer harbor, west of Erie-Lackawanna coal dock, 
to 16 feet. 2' 
Widening channel to harbor lines in Oswego River north 
of Seneca St. 
Closing gap in west breakwater: deepening west outer 
harbor, west of east line of Erie-Lackawanna coal 
dock, to project depth.33 
Construction of east outer breakwater; removal of inner 
end of east arrowhead breakwater; and dredging 
channel and basin in east outer harbor.27 
Construction of detached breakwater at harbor entrance 
and removal of shoals in approach to harbor entrance 
to 25 feet deep. 
Depth of 27 feet in lake approach channel: 25 feet deep 
in outer harbor channel 800 feet wide from entrance 
gap to a turning basin 25 feet deep about 750 by 
1,100 feet, at mouth of Oswego River; depth of 24 
feet in earth and 25 feet in hard material in river 
channel from turning basin to upstream end of Port 
of Oswego Authority's east side terminal, a distance 
of about 1,600 feet; relocation of Federal project 
limits in Oswego River upstream of 24-foot channel 
to Federal project limit at north line of West Seneca 
St., on lines parallel to 50 feet channel ward of 
established harbor lines: elimination of maintenance 
of inner west breakwater; and, elimination of modification 
authorized by River and Harbor Act of 1948. 
PORT CLINTON HARBOR, OHIO (See Section 18 of Text) 
Parallel stone and pile jetties at mouth of river, east jetty 
2.200 feet long and west jetty 1,980 feet long extending to 
10-foot contour in lake. Channel 10 feet deep and 100 feet 
wide for outer 4,200-foot length and 200 feet wide for inner 
800-foot length to Highway Bridge. 
ROCHESTER HARBOR, N.Y. (See Section 19 of Text) 
Construction of piers.' 
Extension of piers to 15 foot contour in the lake. 
Concrete superstructure on piers.' 
Deepening channel to 20 feet. 
Dredging of the entrance channel and turning basin, and 
the elimination of the inner ends of the east and west 
piers, all to present project dimensions. 
Maintenance of the existing channel upstream of the 
Penn Central Co. bridge. 
Depth of 24 feet in the channel from the lake to the west 
pier: a depth of 23 feet between the piers and in the 
ower river to the Penn Central Co. bridge, including 
the existing turning basin; a depth of 21 feet from the 
bridge to the upstream project hmit, with suitable 
widening at the bends; and, an upstream turning basin 
21 feet deep and 650 feet wide adjacent to the improved 
channel, with two mooring dolphins. 
Annual Report. 1870, pp. 54, 
220. and 221. 
H. Doc. 55, 58th Cong., 
2d sess. 
Rivers and Harbors Committee 
Doc. 24, 71st Cong., 
2d sess. 
Rivers and Harbors Committee 
Doc. 7, 74th Cong., 
1st sess. 
H. Doc. 96, 76th Cong., 
1st sess. 
H. Doc. 722, 80th Cong., 
2d sess. 
H. Doc. 487, 81st Cong., 
2d sess. 
H. Doc. 471, 87th Cong.. 
2d sess. 
Annual Report, 1875, p. 295 
Annual Report. 1874, p. 247. 
Annual Report. 1881, p. 
2437. 
Annual Report, 1905, p. 
2383. 
H. Doc. 342, 61st Cong., 
2d sess. 
H. Doc. 484, 72d Cong., 
2d sess. 
H. Doc. 139, 76th Cong., 
1st sess. 
H. Doc. 409. 86th Cong., 
2d sess.' 
32-29

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 32-B (Cont'd.) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
June 10, 1872 
Aug. 26, 1937 
Oct. 27, 1965 
Mar. 3, 1899 
June 13, 1902 
Mar. 2, 1919 
Jan. 21, 1927 
Aug. 30, 193526 
Mar. 2, 1945 
July 14, 1960 
Mar. 3, 1899 
June 25, 1910 
ROCKY RIVER HARBOR, OHIO (See Section 20 of Text) 
East pier and dredging of channel. 
Extension of east pier and deepening channel to present 
project dimensions. 
Realign and extend channel and construct an anchorage 
basin. 
SANDUSKY HARBOR, OHIO (See Section 21 of Text) 
Construction of channel protection works. 
Widening of straight and dock channels and deepening to 
19 feet. 
Extension of east jetty to total length of 6,000 feet, 
with pierhead on outer end; deepening of the outer, 
straight, and easterly portion of dock channels to 
21 feet, and westerly portion of dock channel to 
20 feet. 
Deepening of dock channel to 22 feet. 
Enlargement of turning basin and construction 
of rock dike. 
Maintenance of bay channel to 22 feet; and elimination 
from project of portion of turning basin and rock dike. 
Extending Moseley channel and deepening that channel and 
the outer end of Straight channel to 26 feet, from deep 
water in the lake to the vicinity of Cedar Point dock; 
widening the bend at the junction of the Moseley and 
Straight channels and deepening to 26 feet; deepening 
the Straight Channel to 25 feet from the vicinity of 
Cedar Point dock to junction with Bay channel: 
deepening the Bay channel from junction with the 
Straight channel to the outer end of the Pennsylvania 
coal dock No. 3 to 25 feet, thence from outer end of 
the coal dock to the turning basin to 24 feet in soft 
material and 25 feet in hard, with no Federal 
dredging within 50 feet of the dock; and enlarging 
the turning basin, including removal of approximately 
300 feet of the rock dike, and deepening to 24 feet 
in soft material and 25 feet in hard. 
TOLEDO HARBOR, OHIO (See Section 22 of Text) 
A Channel 400 Feet Wide and 21 Feet Deep 
from 25-Foot Contour in Maumee Bay to 
Fassett Street Bridge, 200 Feet Wide and 
19 Feet Deep Above that Point and a 500-Foot 
Turning Basin at Upper End. A stone Revetted 
Earth Dike in Maumee Bay Channel. 
Act 1899 Modified to Insure a Navigable 
Channel to 21 Feet from Fassett Street Bridge to 
Lake. 
Annual Report, 1871, p. 211. 
H. Doc. 70, 75th Cong., 
1st sess. 
H. Doc. 352, 88th Cong., 
2d sess.4 
H. Doc. 362, 55th Cong., 
2d sess., and Annual Report, 
1898, p. 2708. 
H. Doc. 120, 56th Cong., 
2d sess. 
H. Doc. 982, 64th Cong., 
1st sess. 
H. Doc. 584, 69th Cong., 
2d sess. 
Rivers and Harbors Committee 
Doc. 2, 73d Cong., 
1st sess. 
H. Doc. 328, 76th Cong., 
1st sess. 
H. Doc. 144, 86th Cong., 
1st sess.' 
H. Doc. 198, 55th Cong., 
2d Sess. and Annual Report 
1898, p. 2693. 
H. Doc. 865, 60th Cong., 
1st sess. 
32-30

TABLE 32-B (Cont'd.) 
Acts 
Aug. 30, 1935 
May 17. 1950 
Sept. 3, 1954 
July 3. 1958 
July 14, 1960 
Sept. 3, 1954 
July 14, 1960 
Mar. 7, 1974 
Oct. 22, 1976 
(Sec. 101) 
BUFFALO, N.Y. DISTRICT 
AUTHORIZING LEGISLATION 
Work Authorized 
Channel 25 Feet Deep and 500 Feet Wide from 25.- 
Foot Contour to Mouth of Maumee River 1300 Feet 
Wide on Each Side of Center Dike in Bay Channel). 
Thence 400 Feet Wide to Fassett Street Bridge., 200 
Feet Wide Above That Point and a Turning Basin at 
Upper End 18 Feet Deep. 
Widening at Bend of Mouth of River Opposite Chesapeake 
and Ohio Railway Dock. 
Removal of Center Dike in Maumee Bay Channel. 
Enlarge Widening at Bend Opposite Chesapeake and Ohio 
CDoo.c k and Turning Basin Opposite American Shipbuilding Dock. 
Deepen Bay Channel Including Widenings to 28 Feet., 
Deepen River Channels to New York Central Railroad 
Bridge to 27 Feet and Construct New Turning Basin 
Below Anthony Wayne Bridge.3' 
PRESQUE ISLE PENINSULA, ERIE, PA. (See Section 28 
of Text) 
Construction of groin system. seawall. bulkhead, 
placement of beach material at waterworks reservation 
and along remainder of peninsula: removal of portions 
of existing structures. 
Periodic nourishment of shore for a 10-year period. 
Periodic nourishment of shore for a 5-year period. 
Preparation of Phase I design memorandum for improvements 
consisting of construction of five sections 
of spaced off-shore breakwaters and replenishment of 
beach area with sandfill. 
Documents 
Rivers and Harbors Committee 
Doc. 21, 72d Cong., 
1st sess. 
H. Doc. 189. 81st Cong.. 
1st sess. 
H. Doc. 620, 81st Cong.. 
2d sess. 
H. Doc. 436. 84th Cong., 
2d sess. 
H. Doc. 153. 86th Cong., 
1st sess.' 
H. Doc. 231. 83d Cong., 
I1st sess. 
H. Doc. 397, 86th Cong., 
2d sess. 
H. Doc. 796, 93d Cong., 
2d sess. 
32-31 
w 
- -

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 32-B (Cont'd.) AUTHORIZING LEGISLATION 
1. Authorized by Public Works Administration, Sept. 
6, 1933. 
2. Widening Cuyahoga River at downstream and of Cut 
4 classified inactive. 
3. Replacement of bridges 19 and 32, widening 
Cuyahoga and Old River Channels, classified deferred. 
4. Contains latest published map. 
5. Permanent Appropriations Repeal Act. 
6. Authorized May 28, 1935 by Emergency Relief Administration 
Act of 1935. 
7. Improvement of guide pier at Black Rock lock was 
deauthorized by Congress in August 1977. 
8. Classified deferred. 
9. Completed under previous projects. 
10. Also Sundry Civil Act of Mar. 3, 1905. 
11. Authorized in part by Public Works Administration, 
Sept. 6, 1933. 
12. Authorized by Public Works Administration Sept. 6, 
1933.
13. Previously authorized by Public Works Administration.
14. First Deficiency Appropriation Act approved April 
1, 1944. 
15. Authorized by Defense Plant Corp., May 19, 1942. 
16. Deepening left half of channel extension was 
eliminated from project by 1962 R&H Act. 
17. Permit of Secretary of War, Aug. 5, 1927. 
18. Modified 1828 and 1852. 
19. Extension of north pier portion of this modification 
was deauthorized Nov. 81. 
20. Public 366. 
21. Modified 1830, 1881, and 1890. New work completed 
under previous projects. 
22. Partly included in Public Works Administration program, 
Nov. 15, 1933. 
23. First supplemental National Defense Appropriation 
Act, 1944, approved Dec. 23, 1943. 
24. Removal of remaining hard-material shoals in lower 
basin is classified inactive. 
25. Deepening remainder of Cuyahoga River from bridge 
1 to and including Old River, classified deferred. 
26. Deepening a 200-foot strip along harbor line east of 
mouth of Oswego River is classified inactive. 
27. Modification eliminated by River and Harbor Act of 
Oct. 26, 1962. 
28. Included in Public Works Administration program, 
Nov. 15, 1933. 
29. Deepening strips adjacent to north and south piers 
was deauthorized Aug. 82. 
30. Modification classified inactive. 
31. Construction of breakwater classified deferred. 
32. Deepening and widening remainder of Black River 
channel at Cut I classified deferred. 
33. Deepening to 22 feet a 150-foot wide strip in west' 
outer harbor deauthorized in May 1981. 
34. The 27-foot project extended 2,800 feet and turning 
basin relocated under authority of Chief of Engineers. 
TABLE 32-C OTHER AUTHORIZED NAVIGATION PROJECTS 
(See Section 25 of Text) 
For Last Cost to September 30, 1983 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Aquatic Plant Control 1974 $ 1,137 - 
Big (Cunningham) Creek, Ohio1 _2 19,7633 - 
Black River Harbor, N.Y.4 -2 42,401 - 
Cattaraugus Creek, N.Y.5 -2 57,410 - 
Elk Creek Harbor, Pa.6 1978 101,500 - 
Grasse River (Massena), N.Y.4, 1891 9,0003 - 
Great Sodus Harbor, N.Y. 1982 1,324,503 2,352,127 
Hamlin Beach Harbor, N.Y.6 1973 72,052 - 
Kelleys Island, Ohio 197415 129,874 - 
Little River at 
Cayuga Island, N.Y.9 1969 46,8043 42,355 
Little Sodus Bay Harbor, N.Y. 1982 1,044,216 3,031,051 
Maumee River, above Toledo, Ohio17 1873's 12,000 
NMioargraisrtao wn Harbor, N.Y.u 1949 6,221 9,65612 Remedial Works, N.Y. 9,10 1966 6,069,395 510,819 
Oak Orchard Harbor, N.Y. 1982 1,586,996 79,660 
Olcott Harbor, N.Y. 1982 154,687 461,908 
Ottawa River Harbor, Michigan 
and Ohio14 197715 99,000 - 
Port Bay, N.Y.. 
Port Ontario Harbor, N.Y. 1982 810,000 - 
Pultneyville Harbor, N.Y.13 1934 68,219 20,087 
Put in Bay, Ohio 195115 51,609 12,600 
Sackets Harbor, N.Y. 1982 25,010 23,639 
Sandusky River, Ohio4 1894 58,0003 557 
Vermilion Harbor, Ohio 1982 1,295,893 1,373,167 
Wilson Harbor, N.Y. 1982 535,246 219,671 
32-32

BUFFALO, N.Y. DISTRICT 
TABLE 32-C (Continued) OTHER AUTHORIZED NAVIGATION PROJECTS 
1. No commerce reported. 
2. Only information available is in index to reports of 
Chief of Engineers. 
3. Amount includes maintenance; not separable. 
4. Abandonment recommended in H. Doc. 467, 69th 
Cong., 1st Sess. 
5. Abandonment recommended in Ex. Doc. 16, 35th 
Cong., 1st Sess. 
6. Project classified deferred. 
7. Channel improved by local interests. 
8. Includes local interests' contribution of $25.742. 
9. Completed. 
10. Costs of operation and maintenance of this project 
will be settled directly by concerned power agencies. No further 
appropriations will be made to this project. 
11. Includes local interests contribution of $27,563. 
12. Includes local interests contribution of $5,000. 
13. Abandonment recommended in H. Doc. 375, 64th 
Cong., 1st Sess. 
14. Project classified inactive. 
15. Annual Report for Detroit District. 
16. Construction of compensating works as authorized 
by 1930 R&H Act was deauthorized by Congress in August 
1977.
17. Project deauthorized by Congress in Nov. 1977. 
TABLE 32-D NAVIGATION WORK UNDER SPECIAL AUTHORIZATION 
(See Section 26 of Text) 
Navigation Activities Pursuant to Section 107, Public Law 86645 
(Preauthorization) 
Study Identification Fiscal Year Cost 
Barcelona H arbor, N .Y .................................................... ............................... $ 97 
Cooley Canal, Lucas Cty., OH ............................................................................... 82,542 
Edgewater M arina, Cleveland, OH .......................................................................... 115,483 
NFTA-Sm Boat Hbr, Buffalo, N.Y.................................... .... ........................... 12,452 
Ogdensburg Harbor, N.Y............................................................. . ..... .... .............. 54,403 
South Michigan Ave. Bridge, Buffalo, N.Y....................... .... ............................ 36,299 
Mitigation of Shore Damages Attributable to Navigation Projects 
(Section 111, Public Law 90483) 
Study Identification Fiscal Year Cost 
Cleveland H arbor, O H ...................................................................................... $33,878 
Conneaut H arbor, O H ........................................................................................ 24,211 
H uron H arbor, O H ........................................................... .. ............................ 44,293 
Lorain, OH ............................................................. .. .. ............... .............. 601 
Vermilion Harbor, OH........................................... ......... .................. 1,339 
32-33

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 32-E OTHER AUTHORIZED BEACH EROSION CONTROL PROJECTS 
(See Section 29 of Text) 
For Last 
Full Report 
Project See Annual Operation and Report For Construction Maintenance 
Cleveland and Lakewood, Ohio: 
Edgewater Park' - - - 
White City Park' - - - 
Fair Haven Beach State Park, 
Lake Ontario, N.Y.' 
Fort Niagara State Park, N.Y.' - - - 
Hamlin Beach State Park, N.Y.' 1976 $1,769,600 
Selkirk Shore State Park, 
Lake Ontario, N.Y.' 1963 58,978 $2,946 
1. Project authorized by River and Harbor Act of 4. Federal participation was limited to one-third of first 
2. Project authorized by River and Harbor Act of July 3, Act. Federal participation was changed from one-third to 70 
1958 is classified as deferred. percent of remaining work under Public Law 87-874. Uncom- 
3. Project authorized under provisions of Section 201, pleted portion of project is classified as deferred. 
1965 Flood Control Act is classified inactive. 5. Project completed. 
TABLE 32-F OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(See Section 41 of Text) 
For Last Cost to September 30, 1983 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
A u b u r n , N .Y . O w a s c o O u t le t ' 1 9 6 2 $ 3 7 1 ,9 8 5' - 
Batavia and vicinity, Tonawanda Creek, N.Y.' 1957 335,385 - 
Caledonia, Genesee River, N.Y. 1950 - - 
Camp Perry, Ohio' 1967's 275,000's - 
Chittenango Creek and tributaries, N.Y. " 1948 12,464 - 
Eastlake, Ohio, Chagrin River' 1976 506,344 - 
Fremont, Ohio, Sandusky River' 1976 8,589,824" - 
Hammondsport, Oswego River Basin, N.Y. 1951 18,691' - 
Ithaca, N.Y., Cayuga Inlet' 1978 3,929,330' - 
Lackawanna, N.Y., Smokes Creek' 1971 3,542,068' - 
Lancaster, Cayuga Creek, N.Y.' 1954 797,300 - 
Marsh Creek, Geneva, N.Y.' - 226,429 - 
Montour Falls, Oswego River Basin, N.Y.' 1954 1,681,785 - 
Onondaga Creek, Nedrow, N.Y.',* 1964 330,231 - 
Ottawa, Ohio 1967's - - 
Owasco Inlet and Outlet, Montville and Dry 
Creek, State Ditch and Crane Brook, N.Y.' 1950 281,559 - 
Red Creek, N.Y.' 1975 361,241 - 
Reno Beach-Howard Farms, 
Lucas County, Ohio 1953's 4,467 - 
Syracuse, Oswego River Basin, N.Y.' 1954 3,349,248 - 
Warsaw, N.Y., Oatka Creek',* 1969 558,317"- 
Wellsville, N.Y., Genesee River' 1978 3,145,303" - 
32-34

TABLE 32-F (Continued) 
BUFFALO, N.Y. DISTRICT 
OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
1. Completed. 
2. Project classified deferred. 
3. Local interests required to contribute $25,000. 
4. Project not considered economically justified and is 
inactive. 
5. Inactive portion of work for State ditch has been 
done by local interests and work on Crane Brook has been 
deferred at the request of local interests. 
6. Project authorized by Chief of Engineers. 
7. Excludes costs of $188,732 under Public Law 84-99, 
Flood Control and Coastal Emergencies Appropriation, incurred 
for project rehabilitation as a result of damages due to 
storm Agnes, June 1972. 
8. Excludes costs of $6,766 under Public Law 84-99, 
Flood Control and Coastal Emergencies Appropriation, incurred 
for project rehabilitation as a result of damages due to 
storm Agnes, June 1972. 
9. Includes local interests contribution of $50,000. 
10. Excludes costs of $26,807 under Public Law 84-99, 
TABLE 32-G FLOOD CONTROL WORK Ur 
Flood Control and Coastal Emergencies Appropriation, incurred 
for project rehabilitation as a result of damages due to 
storm Agnes, June 1972. 
11. Includes local interests contribution of $6,944. Excludes 
costs of $383,786 under Public Law 84-99, Flood Control 
and Coastal Emergencies Appropriation, for emergency 
restoration of levees damaged during 1973. 
12. Includes local interests contribution of $125,000. 
13. Annual Report for Detroit District. 
14. Includes local interests contribution of $99,000. Excludes 
costs of $104,005 under Public Law 84-99, Flood Control 
and Coastal Emergencies Appropriation, incurred for 
project rehabilitation as a result of damages due to storm 
Agnes, June 1972. 
15. Includes local interests contribution of $50,000. Excludes 
costs of $374,042 under Public Law 84-99, Flood Control 
and Coastal Emergencies Appropriation, incurred for 
project rehabilitation as a result of damages due to storms. 
JDER SPECIAL AUTHORIZATION 
(See Section 42 of Text) 
Flood control activities pursuant to Sec. 205, 
Public Law 858, 80th Congress as amended (preauthorization) 
Study Identification Fiscal Year Cost 
V irgil Creek, Dryden, N .Y .................................................................................... $ 7,500 
Butternut Creek, Dew itt, N .Y ................................................................................. 12,500 
Cattaraugus Indian Reservation, N.Y .............................. .......................... 2,500 
Cazenovia Creek, Buffalo, N .Y. .............................................. .. ........... . ............. 80,715 
Chagrin River, W illoughby Hills, OH .................................. ...................................... 19,208 
Conesus Lake, Livonia, N .Y .................................................................................. 25,462 
Euclid Creek, O H ............................................................. ............ ................... 78,324 
Glen Brook Flume, Hammondsport, N.Y....................................... . ............................ 94,805 
Lim estone Creek, Fayetteville, N .Y...................................... ...................................... 97,500 
M aumee River, Grand Rapids, OH ................................. .................. .......................... 7,500 
M aum ee River, Defiance, OH ........................................................ ....... ................... 8,670 
O neida Creek, Oneida N .Y .................................................................................... 50,339 
Silver-W alnut Creeks, Silver Creek, N.Y ............................................................. ............. 22 
St. Regis River, Hogansburg, N.Y................................................................ .............. 456 
W. Br. Limestone Creek, Manlius, N.Y............................. ................................... 92,983 
Flood Control and Coastal Emergencies (Public Law 99, 
84th Cong., as amended by Sec. 206 of Flood Control Act of 1962) 
Project Federal Cost 
Disaster preparedness ..................................................................................... $139,918 
Em ergency operations ......................................................................................... 2,849 
TO TA L ............................................................................................... $142,767 
Snagging and clearing of navigable streams and tributaries in interest 
of flood control. (Sec. 208, 1954 Flood Control Act, PL. 780, 83rd Cong. 
Project and location .Fiscal Year Cost 
Eighteen-Mile Creek, Hamburg, N.Y.................................. ...................................... $7,936 
32-35

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 32-G (Continued) FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION 
(See Section 42 of Text) 
Emergency bank protection (Sec. 14 of 1946 Flood Control Act, 
Public Law 526, 79th Cong.) 
Study Identification Fiscal Year Cost 
Study Identification Fiscal Year Cost 
Blanchard River, Ottawa, OH ............................................................................. $104,130 
Genesee River, Am ity, N .Y ................................................................................... 20,803 
Genesee River, Lattice Rd. Bridge, N.Y.........................................................................7,492 
Grand River, Painesville, OH .............................................. .............. ..... ................ 7,500 
State Route 163, Marblehead, OH........................................................................... 102,600 
Lk Ontario State Pkwy, Kendall, N.Y............ ......................... .. ............ ............. 18,050 
Little Elk Creek, Girard, PA .................................................... ........ ...... ............... 67,790 
St. Joseph H S, Euclid, O H ................................... ...... .... ... ........... ................. 67,498 
W endt Beach Pk, Evans, N .Y ..... .................................... ...................................... 24,222 
TABLE 32-H DEAUTHORIZED PROJECTS 
(See Section 43 of Text) 
Authorization Date 
Project Type Act Deauthorized 
Black Rock Channel and 
Tonawanda Harbor, NY Navigation 1935 R&H Act' Aug. 1977 
Black Rock Channel and 
Tonawanda Harbor, NY Navigation 1954 R&H Act May 1981 
Crane Creek State Park, OH Beach Erosion 1962 R&H Act Nov. 1979 
Erie Harbor, PA Navigation 1945 R&H Act Aug. 1977 
Erie Harbor, PA Navigation 1899 R&H Act Nov. 1981 
Erie Harbor, PA Navigation 1960 R&H Act Aug. 1982 
Grandview Bay Harbor, NY Navigation 1945 R&H Act Aug. 1977 
Great Sodus Bay Harbor, NY Navigation 1962 R&H Act Aug. 1977 
Ithaca, NY -Cascadilla Creek Flood Control 1941 FC Act Aug. 1977 
Ithaca, NY- Fall Creek Flood Control 1941 FC Act Aug. 1977 
Maumee River 
above Toledo, Ohio Navigation 1872 Act Nov. 1977 
Niagara River 
Compensating Works, NY Navigation 1930 R&H Act Aug. 1977 
Oswego Harbor, NY Navigation 1940 R&H Act 2 May 1981 
Sackets Harbor, NY Navigation 1945 R&H Act May 1981 
Sheffield Lake Community Park. Ohio Beach Erosion 1962 R&H Act Aug. 1977 
Watkins Glen, NY Flood Control 1941 FC Act Aug. 1977 
1. Extension of guide pier only, other improvements completed. 
2. Deepening of west outer harbor: other improvements completed. 
32-36

LOS ANGELES, CA, DISTRICT* 
This district (total area. about 226,000 square miles) 
comprises those drainage basins tributary to the Pacific 
Ocean that are in California between the Mexican 
boundary and Cape San Martin (about 265 miles north 
of entrance to Los Angeles Harbor): lower Colorado 
River drainage basin (below Lee Ferry, AZ). which is in 
southeastern California, southeastern Nevada. southwestern 
Utah, western New Mexico. and all of Arizona,. 
except the northeastern corner: that part of the Great 
Basin that is in southern Nevada and southeastern 
California: and the United States parts of those small 
drainage basins in southern Arizona and southwestern 
New Mexico west of the Continental Divide that drain 
southward into Mexico. 
IMPROVEMENTS 
Navigation Page 
1. Channel Islands Harbor, CA ........... 33-2 
2. Los Angeles and Long Beach 
Harbors, CA ......................... 33-2 
3. Oceanside Harbor, CA ............... 33-3 
4. Port Hueneme, CA ................... 33-3 
5. San Diego River and Mission 
Bay, CA ........................... 33-4 
6. Santa Barbara Harbor, CA ........... 33-4 
7. Ventura Marina (Ventura 
Harbor), CA .......................... 33-4 
8. Reconnaissance and condition 
surveys .............................. 33-5 
Beach Erosion Control 
9. Imperial Beach, San Diego 
County, CA .......................... 33-5 
10. San Gabriel River to Newport 
Bay (Surfside-Sunset and 
Newport Beach). Orange 
County, CA .......................... 33-5 
Flood Control 
11. Alamo Lake, Bill Williams 
River, AZ ........................... 33-5 
12. Allenville, AZ ....................... 33-5 
13. Cucamonga Creek. Santa Ana 
River Basin. CA ..................... 33-5 
14. Gila River Basin. AZ: ................ 33-6 
14A. Indian Bend Wash, AZ ............... 33-6 
14B. Painted Rock Dam (Gila 
River). AZ ........................... 33-6 
14C. Phoenix. AZ. and vicinity 
(including New River) ............... 33-6 
14D. Whitlow Ranch Dam. Queen 
Creek. AZ ........................... 33-7 
15. Los Angeles County drainage 
area. CA ............................ 33-7 
16. Mojave River Dam. Mojave 
River Basin. CA ..................... 33-8x 
Flood Control (Cont'd) Page 
17. Pine and Mathews Canyons Dams. 
Colorado River Basin, NV ............. 33-8 
18. San .Jacinto River levee and 
Bautista Creek channel, Santa 
Ana River Basin, CA ................. 33-8 
19. Santa Ana River Basin (and 
O()range County), CA ................. 33-8 
20. Santa Maria Valley levees, 
Santa Maria River Basin, CA .......... 33-9 
21. Santa Paula Creek channel and 
d(lebris basins (including Mud Creek), 
Santa Clara River Basin, CA ........... 3 3 -9 
22. Sespe Creek at Fillmore, 
Ventura County, CA ................. 33-9 
23. Sweetwater River, Sweetwater 
River Basin, CA ...................... 33-9 
24. Inspection of completed flooxxl 
control projects ....................... 33-9 
25. Scheduling flood control reservoir 
ol)erations ........................... 33- 111 
26. Flood control work under 
special authorization ................. 33- 10 
General Investigations 
27. Surveys ............................. :33-l0 
28. Collection and study of basic 
(lata ................................. 33-10 
29. Research and (levelopment ............ 33-10 
30. ('ontinuation of planning 
and engineering ...................... ::-10o 
30A. I lol brook levee, Little Colorado 
River. Colorado River Basin, AZ ....... 33-10 
30B. Santa Ana River main stemincluding 
Santiago (Creek an(l Oak 
Street I)rain, Santa Ana River 
Hasin. ('A ............................ , -lo 
3::-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
General Investigations (Cont'd) Page 
31. Advance engineering and 
design ............................... 33-11 
San Luis Rey River, San Luis 
River Basin, CA ..................... 33-11 
Tables 
Table 33-A 
Table 33-B 
Table 33-C 
Table 33-D 
Table 33-E 
Cost and financial 
statement ................... 33-12 
Authorizing 
legislation .................. 33-16 
Other authorized 
navigation projects ........... 33-21 
Other authorized 
beach erosion 
control projects .............. 33-22 
Other authorized flood 
control projects .............. 33-23 
Tables (Cont'd) Page 
Table 33-F Not applicable 
Table 33-G Deauthorized projects ........ 33-24 
Table 33-H Reconnaissance and 
condition surveys ............ 33-25 
Table 33-I Los Angeles County 
drainage area, CA: Latest 
approved estimated first 
costs for all units of 
improvement under 
existing project ............. 33-25 
Table 33-J Santa Ana River Basin 
(and Orange County), CA: 
Lasted approved estimated 
Federal first cost for all 
units ........................ 33-27 
Table 33-K Flood control work under 
special authorization ......... 33-27 
Navigation 
1. CHANNEL ISLANDS HARBOR, CA 
Location. On coast of southern California about a 
mile northwest of existing harbor of Port Hueneme, 65 
miles northwest of Los Angeles Harbor, and 345 miles 
south of San Francisco. (See Coast and Geodetic Survey 
Charts 5007 and 5202.) 
Existing project. For details, see page 33-2 of Annual 
Report for 1981. 
Local cooperation. Fully complied with. 
Terminal facilities. One thousand and eight hundred 
boat slips in 6 marinas, with restroom and shower 
facilities; dry storage area for 300 boats with 3-ton and 
1-ton hoist facilities: 2 marine construction and repair 
yards with 5-ton travel lift and 35-ton hoist to 70-ton 
boatway haulout capacities; a fuel dock facility; a sportfishing 
complex: 6 restaurants: 2 coffee shops; 800 
waterfront apartments-many with adjoining slips;: 
300 motel units: 4 yacht club buildings; 3 public 
convenience d(locks: a 40-slip guest boat complex: a 
harbor administration building/harbor patrol office 
and dlock complex: a marine emporium complex, housing 
a chandlery store, a sail loft. a delicatessen, a fishing 
tackle shop, yacht sales, an underwater repair service, 
and an adjacent (lock complex: a 7-lane free access 
public launch ramp. with paved pay parking for cars 
and trailers; a xboaters' convenience center; a commercial 
fishing pier and hoist: 2 large public parks: a fire 
station: and a U.S. Coast Guard station. Waterwayconnected(
l and north of the harbor is Mandalay Bay, a 
private keys-type waterfront homes development with 
an area for about 500 homes and connected dockage for 
boats. Transition from harxbor to Mandalay Bay is 
restricted(l by a 4-lane high-rise bridge with a clearance 
height of 29 feet at high tide. 
Operations during fiscal year. Completed contract 
payment for maintenance dredging of sand trap and 
entrance channel at a cost of $73,661 regular funds and 
$13,254 Navy funds. Awarded contract for maintenance 
dredging in September 1983. 
2. LOS ANGELES AND LONG BEACH 
HARBORS, CA 
Location. On coast of southern California in San 
Pedro Bay about 25 miles south of City of Los Angeles, 
about 96 miles northwest of San Diego Harbor, and 
about 410 miles southeast of San Francisco Harbor. 
(See Coast and Geodetic Survey Chart 5147.) 
Previous projects. For details, see page 1977 of 
Annual Report for 1915 and page 1646 of Annual 
Report for 1938. 
Existing project. A stone breakwater 11,152 feet 
long (San Pedro breakwater) extending eastward from 
Point Fermin; a stone-and-earth detached breakwater 
18,500 feet long (middle breakwater); a stone-and-earth 
detached breakwater 13,350 feet long (Long Beach 
breakwater); maintenance of original Long Beach breakwater 
south of outer end of pier A (now an integral part 
of pier A as extended); an entrance channel 1,000 feet 
wide and 40 feet deep to outer Los Angeles Harbor, with 
a turning basin 3,500 feet long and 1,500 feet wide of 
same depth opposite end of pier 1, and enlargement of 
entrance to inner harbor by dredging to a depth of 35 
feet a triangular area at junction of inner harbor with 
this turning basin; irregular anchorage areas (areas A 
and B) 40 feet deep adjacent to 40-foot-depth entrance 
channel: an inner harbor channel (Los Angeles channel) 
35 feet deep and 1,000 feet wide, with a turning basin at 
its north extremity 35 feet deep; a channel (East Basin 
channel) 35 feet deep and 650 feet wide extending from 
turning basin to slip 5: a channel (Cerritos channel) 35 
feet deep and 400 feet wide from slip 5 to a turning basin 
33-2

LOS ANGELES, CA, DISTRICT 
in Long Beach inner harbor; a turning basin 35 feet 
deep in Long Beach inner harbor; an entrance channel 
to Long Beach inner harbor 35 feet deep and 300 to 500 
feet wide; a settling basin at mouth of Los Angeles River 
diversion channel, dredged material to be deposited on 
the beaches eastward therefrom to Belmont pier; a siltdiversion 
channel (Los Angeles River) for protection of 
Los Angeles and Long Beach Harbors; and maintenance 
of entire project, except silt-diversion channel. Dredging 
to a depth of 35 feet in East Basin was authorized as a 
modification of existing project in 1954. Dredging to a 
depth of 35 feet in West Basin was authorized as a 
further modification of existing project in 1960. As 
authorized in 1976, existing project was further modified 
to provide for depths of 45 feet in all inner harbor 
channels and basins of Los Angeles Harbor and in the 
Los Angeles entrance channel, and to provide maintenance 
for the new dimensions. Plane of reference is 
mean lower low water. Range between mean lower low 
water and mean higher high water is 5.5 feet. Extreme 
range is about 10 feet. Latest approved estimated (1981) 
first cost for project as modified is $65,316,000, comprising 
$30,545,000 Federal (including $45,000 for 
Coast Guard costs) and $34,771,000 non-Federal. 
Local cooperation. All items of local cooperation 
required under the terms of the previous authorizing 
acts have been fully complied with. See page 33-3 of 
Annual Report for 1981 for requirements under the 
terms of the 1976 Water Resources Development Act. 
Terminal facilities. In Los Angeles Harbor, 81,602 
feet of wharves, of which 74,595 feet are owned by the 
city and 7.007 feet are owned by private interests. In 
Long Beach Harbor, 58,705 feet of wharves, of which 
48,865 feet are owned by the city and 9,840 feet are 
owned by private interests. Federal Government owns 
18,587 feet of wharves and bulkheads. 
Operations during fiscal year. Completed channel 
and basin dredging (1976 modification of existing 
project) in April 1983 at a cost of $5,532,635 regular 
funds: $156,142 required contributed funds; and 
$4,478,502 other contributed funds. 
3. OCEANSIDE HARBOR, CA 
Location. On coast of southern California at Oceanside. 
about 30 miles north of City of San Diego. (See 
Coast and Geodetic Survey Chart 5101.) 
Existing project. For details, see page 33-4 of Annual 
Report for 1981. 
Local cooperation. Fully complied with for maintenance 
to date. 
Terminal facilities. Berthing for 828 boats (718 
slips. 76 side-ties. 28 visitors slips, and 6 dry storage 
spaces at Oceanside Marine Center): a fuel dock: a boat 
hoist: a launching ramp. which can accommodate 4 
launchings at the same time: parking for 1.684 cars: 
temporary parking for about 144 boat trailers: a boatrepair 
facility: a pump-out facility: a Coast Guard 
cutter; restaurants; retail stores; yacht brokers; a boatel/- 
motel; condominiums; and a sport-fishing facility. 
Operations during fiscal year. Completed contract 
payment for maintenance dredging at a cost of $7,500 
other contributed funds. In addition, a reconnaissance 
and condition survey was conducted at a cost of $25,782. 
4. PORT HUENEME, CA 
Location. On coast of southern California about 65 
miles northwest of Los Angeles and Long Beach Harbors, 
about 1 mile southeast of Channel Islands Harbor, 
immediately west of the City of Port Hueneme, 4 miles 
southwest of the City of Oxnard, and 10 miles southeast 
of the City of Ventura. 
Existing project. Plan provides for adoption and 
maintenance of existing harbor for deep-draft vessels at 
Port Hueneme, constructed by local interests and subsequently 
acquired by the U.S. Navy, consisting of a 
west jetty about 800 feet long; an east jetty about 1,000 
feet long; an approach channel about 800 feet long, 600 
feet wide, and 40 feet deep; an entrance channel about 
1,550 feet long, 330 feet wide, and 36 feet deep; a central 
basin 1,080 feet long, 1,025 feet wide, and 32 feet deep; 
and a channel (channel A) 1,850 feet long, 150 feet wide, 
and 32 feet deep. It further provides that the central 
basin be deepened to 35 feet and that channel A be 
improved by lengthening it to 2,830 feet, widening it to 
275 feet, and deepening it to 35 feet. Plane of reference 
is mean lower low water. Range between mean lower 
low water and mean higher high water is 5.4 feet. 
Extreme range is about 10 feet. Approved estimated 
(1983) first cost for project is $4,520,000 ($3,380,000 
Federal and $1,140,000 non-Federal). 
Local cooperation. Requirements are described in 
full on page 33-3 of Annual Report for 1976. 
Terminal facilities. Oxnard Harbor District owns 
and operates terminal facilities known as the Port of 
Hueneme. A 1,800-foot-long commercial deep-water' 
concrete wharf (wharf No. 1) provides berthing space 
for vessels of 35-foot draft at mean lower low water. One 
concrete utility wharf provides 380 feet of berthing 
space along the entrance channel for vessels of 14-foot 
draft at mean lower low water; and two wood utility 
wharves provide 250 feet of berthing space for vessels of 
18-foot draft at mean lower low water. Ancillary facilities 
include extensive paved and unpaved open storage 
areas: two clear span transit sheds, providing 80,000 
square feet of covered storage area. with ample rail and 
truck loading capability: and an administration building. 
Operations during fiscal year. Awarded contract 
for maintenance dredging in September 1983. In addition. 
a reconnaissance and condition survey was conducted 
at a cost of $20.569. 
33-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
5. SAN DIEGO RIVER AND MISSION 
BAY, CA 
Location. The San Diego River has its source on the 
tableland in the Cuyamaca Mountains near Santa 
Ysabel, CA, and flows southwestward 52 miles to the 
Pacific Ocean at the City of San Diego. Mission Bay 
Harbor is adjacent to the outlet of the San Diego River, 
77 miles southeast of Los Angeles and Long Beach 
Harbors and 8 miles north of San Diego Harbor. 
Existing project. A leveed flood channel 800 feet 
wide, with a capacity of 115,000 cubic feet per second, 
from 0.4 mile above Morena Boulevard, 3.3 miles 
directly to the ocean; an altered railroad bridge over the 
leveed river flood channel; an entrance channel about 
5,200 feet long, 670 feet wide, and 20 to 25 feet deep into 
Mission Bay; in the bay, a main channel and turning 
basin about 2,700 feet long, 1,000 feet wide, and 20 feet 
deep, and two anchorage basins, one about 3,200 feet 
long, 600 feet wide, and 15 feet deep, and the other about 
1,600 feet long, ranging from 800 to 1,800 feet wide, and 
20 feet deep; three jetties at the entrance; and stone 
revetment for the banks of the entrance and main 
channels and turning basin. Plane of reference is mean 
lower low water. Range between mean lower low water 
and mean higher high water is 4.4 feet. Extreme range 
is about 10 feet. Approved estimated (1983) first cost is 
$39,100,000 (includes allowance for estimated inflation 
through construction period), comprising $21,600,000 
Federal and $17,500,000 non-Federal. This project 
modified the flood control project: "San Diego River 
Basin, California"(See H. Doc. 635, 77th Cong., 2d sess.) 
Local cooperation. Fully complied with. 
Terminal facilities. None, with the exception of 
mooring facilities for recreational craft and commercial 
sport-fishing boats only. 
Operations during fiscal year. Continued preparation 
of supplemental project plan, which is about 95 
percent complete. Continued preparation of environmental 
assessment, which is about 95 percent complete. 
6. SANTA BARBARA HARBOR, CA 
Location. On coast of southern California 90 miles 
northwest of Los Angeles Harbor and 320 miles southeast 
of San Francisco Harbor. (See Coast and Geodetic 
Survey Chart 5261.) 
Existing project. Maintenance dredging of depths 
existing in 1934 in harbor formed by breakwater 
constructed by local interests. See page 1014 of Annual 
Report for 1969 for detailed description of 1962 authorized 
modification. Further modification was authorized 
in December 1970 (Public Law 91-611) to provide for 
dredging and maintenance of existing project by the 
United States. Also, see Annual Report for 1971 for 
detailed description of previous authorized maintenance. 
Plane of reference is mean lower low water. Range 
between mean lower low water and mean higher high 
water is 5.4 feet. Extreme range is about 10 feet. Latest 
approved estimated (1969) first cost for project as 
modified is $6,810,000, comprising $3,480,000 Federal 
(including $40,000 for Coast Guard costs) and $3,330,00() 
non-Federal (including cash contribution of $3,320,000). 
Prior to adoption by Congress, work was authorized by 
Public Works Administration. 
Local cooperation. See page 1015 of Annual Report 
for 1969 for items of local cooperation under 1962 
authorized modification of existing project. 
Terminal facilities. A wharf 2,000 feet long; a pier 
325 feet long in harbor for tie-up mooring for Coast 
Guard cutter; a landing float; an open mooring and slip) 
anchorage for small craft; and a launching ramp for 
small craft. 
Operations during fiscal year. Completed contract 
payment for maintenance dredging at a cost of $505,001 
regular funds. Awarded contract for maintenance (ldred(lging 
in September 1983. In addition, a reconnaissance 
and condition survey was conducted at a cost of $543. 
7. VENTURA MARINA (VENTURA 
HARBOR), CA 
Location. On coast of southern California about 65 
miles northwest of the City of Los Angeles, about 70 
miles northwest of Los Angeles and Long Beach Harxbors, 
and about 6 miles northwest of Channel Islands Harbor. 
Existing project. For details, see page 33-5 of Annual 
Report for 1981. 
Local cooperation. Fully complied with. 
Terminal facilities. Two fuel docks; guest berthing 
docks; 3 boat-repair facilities, 1 with a 60-ton travel ift; 1 
full service with a 150-ton marine elevator, and 1 (do-ityourself 
boatyard with a 20-ton travelift; Fisherman's 
Pier, with 350-ton jib cranes for off-loading commercial 
fishing vessels; flake ice manufacturing and d(listribution 
system; 3 wholesale fish buying stations; a retail fish 
market and seafood restaurant; offshore oil industry 
crew transportation; 1,800 boat slips; a dry storage area 
for 155 boats; a 3-lane deluxe launch ramp; 2 yacht 
clubs; a restaurant and cocktail lounge; a carpenter 
shop; 2 sport-fishing facilities; sightseeing cruises; 3 
yacht sales; marine communications; 3 marine chandleries; 
3 public restroom buildings; a harbor administration 
building/harbor master's office; paved jetties with handrails 
for sport fishing; and headquarters and visitor 
center for Channel Islands National Park. Under construction 
are a Fisherman's Quay recreational complex, 
with 4 restaurants and 26 marine related ancilliary 
businesses; Marine Center, with 18 outlets for goods and 
services; and Marine Arts and Science Center, with 
fisheries training facilities. Completed in this complex 
are a convenience grocery store: a marine bookstore; an 
accountant office; secretarial services; sport fishing 
and harbor tours. Construction has begun on a 230- 
room resort hotel, which is expected to be completedl in 
the fall of 1984. Plans are under way for constructing a 
saltwater aquarium. 
33-4

LA)S AN(EI.ES. tA. I)ISTRICT 
Operations during fiscal year. Completed maintenance 
dredging of entrance channel and sand trap in 
July 1983 at a cost of $2.16ti6.258. 
8. RECONNAISSANCE AND 
CONDITION SURVEYS 
See table 33-H. 
Beach Erosion Control 
9. IMPERIAL BEACH, SAN DIEGO 
COUNTY, CA 
Location. On coast of southern California at Imperial 
Beach in San Diego County. 
Existing project. Plan as modified by Chief of 
Engineers in August 1979 provides for a submerged 
offshore breakwater about 5.000 feet long. extending 
southward from northern groin: extension of northern 
groin about 100 feet to connect with breakwater: and a 
groin about 600 feet long from shoreline to southern end 
of breakwater. Approved estimated (1983) first cost for 
project as modified is $5.880.000 (includes allowance 
for estimated inflation through construction period). 
comprising $3.340.000 Federal and $2.540.000 non- 
Federal. Map of modified plan is in "Design Memorandum 
No.4. General Design Memorandum. Imperial 
Beach Erosion Control Project. San Diego County. 
California." prepared by Los Angeles District in 
September 1978. 
Local cooperation. Requirements are dtescribed in 
full on page 33-6 of Annual Report for 1981. 
Operations during fiscal year. Continued preparation 
of plans and specifications. which are about 9() 
percent complete. 
10. SAN GABRIEL RIVER TO 
NEWPORT BAY 
(SURFSIDE-SUNSET AND 
NEWPORT BEACH), ORANGE 
COUNTY, CA 
Location. Along the coast of southern California for 
about 17 miles from Anaheim Bay Harbor downcoast to 
Newport Bay Harbor. 
Existing project. Original authorized project provided 
for a single detached offshore rubblemound 
breakwater, located along the minus 24-foot contour 
just upcoast from the Newport Beach fishing pier. and 
the deposition of about 3.000.000 cubic yards of suitable 
beach-building material along the shoreline in the 
vicinity of Surfside-Sunset Beach to provide a protective 
beach. Existing project was modified in September 
1963 by Chief of Engineers, as follows: (a) Consider 
south limit of project to be west jetty at entrance to 
Newport Harbor: (b) construct offshore breakwater, for 
entrapping sand in littoral movement, near mouth of 
the Santa Ana River. Periodically transport this entrapped 
sand to Surfside area to replenish that beach: 
and (c)c onst'ruct a groin as an extension o f sout h jetty of 
the Santa Ana River to compartmentalize beach from 
this area to Newport pier. Construct additional stcruetures 
and fills in this area at such time and in such 
locations. as required. to retain existing beach. Applr'toved 
estimated (1983) first cost for modified project is 
848.200.00t0 t includes allowance for estimated inflat ion 
through construction period ). comprising $32.200.(00t 
Federal and $16.6().000() non-Federal. 
Local cooperation. Requirements are described in 
full on page 33-8 of Annual Report for 1979. 
Operations during fiscal year. Completed preparation 
of project plan for stage 8 construct ion. which 
would consist of placement of beach fill on Surfside- 
Sunset Beach. Awarded contract. 
Flood Control 
11. ALAMO LAKE, BILL WILLIAMS 
RIVER, AZ 
Location. About 70 miles southeast of Kingman. AZ. 
in a narrow gorge at river mile 39 on Bill Williams 
River. AZ. a tributary of Colorado River. 
Existing project. For details. see page 33-7 of Annual 
Report for 1981. 
local cooperation. Fully complied with. 
Operations during fiscal year. Maintained dam in 
good operating condition and administered real estate. 
12. ALLENVILLE,AZ 
Location. On Gila River 1.5 miles south of Buckeye 
and 35 miles west of Phoenix. Maricopa County. AZ. 
Existing project. A 60-acre tract near intersect ion of 
Interstate 10 and Palo Verde Road. about 8 miles 
northwest of Buckeye. AZ. with streets, utilities, community 
center, park. and houses. Latest approved 
estimated (1980) first cost for project is $3.723.00 
($2.866.000 Federal and $857.(X,00) non-Federal). 
Local cooperation. Requirements are descril)ed lin 
full on page 33-7 of Annual Report for 1981. 
Operations during fiscal year. Completed contract 
payment for construction of buildings, grounds, and 
utilities at a cost of $6,297 regular funds. 
13. CUCAMONGA CREEK, SANTA 
ANA RIVER BASIN, CA 
Location. In and near the Cities of Upland. Rancho 
Cucamonga, and Ontario, and the communities of Alta 
Loma and San Antonio Heights, San Bernardino and 
Riverside Counties, CA. 
Existing project. Plan as modified provides for a 
debris basin on Cucamonga Creek and a concrete 
channel along Cucamonga Creek from the debris 1basin 
to Prado Dam; an improved San Antonio hleights 
diversion system that would include 6 debris basins andl 
33-5

REPORT OF THE CHIEF OOFF ENGINEERS U.S. ARMY 1983 
a concrete diversion channel to divert West Cucamonga 
Creek headwaters into Cucamonga Creek: a collection 
levee and a debris basin downstream from Demens, 
Thorpe, and Angalls Canyons and a concrete outlet 
channel from the debris basin to Cucamonga Creek; a 
debris basin in I)eer Canyon and a channel along Deer 
Creek from the debris basin to Cucamonga Creek: the 
Hillside debris basin in a canyon just west of Deer 
Canyon with an outlet channel to Deer Creek channel; 
improvement of an existing levee system along the west 
bank of Day Creek to assure that flows from Day 
Canyon do not enter Deer Creek channel; turnouts to 
mitigate ground water basin recharge losses; landscaping 
appropriate for esthetic treatment; and recreational 
facilities in the project area. Subdrainage would be 
provided along specific reaches of the channels. Approved 
estimated (1983) first cost for modified project is 
$118,456,000 (includes allowance for estimated inflation 
through construction period), comprising $94,500,000 
Federal and $23,956,000 non-Federal. Map of modified 
plan is in "Design Memorandum No. 2, General Design 
for Flood Control and Recreation, Cucamonga Creek, 
Santa Ana River Basin, San Bernardino and Riverside 
Counties, California," prepared by Los Angeles District 
in June 1973. 
Local cooperation. Requirements are described in 
full on page 33-7 of Annual Report for 1981. 
Operations during fiscal year. Completed construction 
of ninth contract, Deer and Hillside debris basins, 
north half of Deer Creek channel, Hillside channel, and 
Deer-Day separation levee, in June 1983. Initiated and 
completed construction of tenth contract, erosion control 
of San Antonio Heights, in May 1983. Completed 
preparation of plans and specifications for eleventh 
contract, erosion control of Cucamonga and Demens 
Creeks channels(part 1); awarded contract; and initiated 
construction, which is about 83 percent complete. Initiated 
and completed preparation of plans and specifications 
for twelfth contract, erosion control of Deer Creek 
and Hillside channels; awarded contract; and initiated 
construction, which is about 15 percent complete. Administered 
rights-of-way acquisition continued by local 
interests. Costs for construction of channels were 
$2,733,538 regular funds and $191,897 other contributed 
funds; cost for relocations was $252,312 regular funds; 
and cost for construction of levees was $230,042 regular 
funds. 
14. GILA RIVER BASIN, AZ 
14A. INDIAN BEND WASH, AZ 
Location. On Indian Bend Wash in Scottsdale and 
Tempe, AZ. 
Existing project. Plan as modified provides for a 
greenbelt floodway with an unlined inlet channel, 
including an unlined interceptor channel, a siphon to 
carry Arizona Canal irrigation waters under Indian 
Bend Wash, and a wasteway structure to discharge 
floodwaters from the canal into the inlet channel: an 
unlined outlet channel to discharge floodwaters into the 
Salt River: a collector and side channels system to 
relieve ponding west of the Arizona Canal; beautification; 
and recreational facilities. Design flood of 30.000 
cubic feet per second would be controlled by improvements. 
Latest approved estimated (1982) first cost for 
modified project is $45,130,000 ($34.400.000 Federal 
and $10,730,000 non-Federal). Map of modified plan is 
in "Design Memorandum No. 1, General Design Memorandum 
Phase II, Project Design for Indian Bend 
Wash, Arizona," prepared by Los Angeles District in 
May 1975. 
Local cooperation. Requirements are described in 
full on page 33-8 of Annual Report for 1981. 
Operations during fiscal year. Completed construction 
of eighth contract, reaches 1, 2, and 3 of side 
channels system, in August 1983. Initiated and completed 
construction of ninth contract, bike stop, and 
greenbelt trail system, in May 1983. Completed preparation 
of plans and specifications for tenth contract, reach 
4 of side channels system; awarded contract; and 
initiated construction, which is about 50 percent complete. 
Initiated and completed preparation of plans and 
specifications for eleventh contract, esthetic treatment 
of inlet channel; and awarded contract. Continued 
preparation of operation and maintenance manual, 
which is about 62 percent complete. Costs for construction 
of channels were $3,464,739 regular funds and 
$376,620 other contributed funds; and costs for construction 
of recreational facilities were $609,070 regular 
funds and $37,118 required contributed funds. Administered 
rights-of-way acquisition continued by local 
interests. 
14B. PAINTED ROCK DAM (GILA 
RIVER), AZ 
Location. On Gila River (mile 126) about 20 miles 
downstream from Gila Bend, AZ, in Gila River Basin, 
which is a part of Colorado River Basin. 
Existing project. For details, see page 33-9 of Annual 
Report for 1981. 
Local cooperation. Requirements are described in 
full on page 33-9 of Annual Report for 1981. 
Operations during fiscal year. Maintained dam in 
good operating condition and administered real estate. 
14C. PHOENIX, AZ, AND VICINITY 
(INCLUDING NEW RIVER) 
Location. On Cave Creek, Skunk Creek, Dreamy 
Draw, New River, and Agua Fria River in and adjacent 
to metropolitan Phoenix, AZ. 
Existing project. Plan as modified by Division Engineer, 
South Pacific Division, in July 1977, provides for 
four dams and detention basins, one each on Dreamy 
Draw, Cave Creek, Skunk Creek, and New River; 
Arizona Canal diversion channel; channel improvements 
33-6

LOS ANGELES, CA, I)ISTRICT 
on Cave Creek, Skunk Creek, and New River; flowage 
easements with some floodproofing along Skunk Creek 
and New and Agua Fria Rivers; flood plain management 
along Dreamy Draw, Cave Creek, Skunk Creek, and 
New River; and recreational facilities. Approved estimated 
(1983) first cost for modified project is 
$747,290,000 (full funding estimate and includes allowance 
for estimated inflation through construction period), 
comprising $545,200,000 Federal and $202,090,000 
non-Federal. Map of modified plan is in "Design Memorandum 
No.3, General Design Memorandum-Phase I, 
Plan Formulation for New River and Phoenix City 
Streams, Arizona," prepared by Los Angeles District in 
March 1976. 
Local cooperation. Requirements are decribed in 
full on page 33-9 of Annual Report for 1981. 
Operations during fiscal year. Completed contract 
payment for construction of Adobe Dam at a cost of 
$303,610 regular funds and $7,147 required contributed 
funds; and for bridge alterations at a cost of $68,330 
regular funds. Continued construction of Skunk Creek 
channels and levees, which is about 95 percent complete. 
Costs for construction of channels were $990,843 regular 
funds and $63,441 required contributed funds. Cost for 
construction of levees was $1,274,542 regular funds. 
Continued preparation of part 4 of project plan, phase 
II, Skunk Creek and New and Agua Fria Rivers, which 
is about 15 percent complete. Continued preparation of 
part 5 of project plan, phase II, Arizona Canal diversion 
channel, which is about 40 percent complete. Completed 
preparation of part 3 of project plan, phase II, New 
River Dam; initiated and completed preparation of 
plans and specifications; and awarded contract. Continued 
preparation of master plan for Adobe Dam, 
which is about 95 percent complete. Administered 
rights-of-way acquisition continued by local interests. 
14D. WHITLOW RANCH DAM, QUEEN 
CREEK, AZ 
Location. On Queen Creek, AZ, a tributary of Gila 
River, about 10 miles west of Superior, AZ. 
Existing project. For details, see page 33-10 of 
Annual Report for 1981. 
Local cooperation. Fully complied with. 
Operations during fiscal year. Maintained dam in 
good operating condition; continued acquisition of rightsof-
way; and administered real estate. 
15. LOS ANGELES COUNTY 
DRAINAGE AREA, CA 
Location. Along Los Angeles and San Gabriel Rivers, 
Rio Hondo, and Ballona Creek, and tributaries thereof 
in Los Angeles County, CA. 
Previous project. For details, see pages 1768 to 1772 
of Annual Report for 1941; page 1602 of Annual Report 
for 1942; and page 1535 of Annual Report for 1943. 
Existing project. Plan provides for flood control 
improvements in four stream basins in Los Angeles 
County, CA, as follows: Los Angeles River Basin, San 
Gabriel River Basin, Rio Hondo Basin, and Ballona 
Creek Basin. Provides for protection of about 325,()00 
acres in densely populated Los Angeles County, including 
areas in Los Angeles, Pasadena, Glendale, Burbank, 
and other cities. Plan provides for construction of 5 
flood control dams (Hansen, Lopez, Santa Fe, Sepulveda, 
and Whittier Narrows); debris basins at mouths of 22 
canyons; channel improvements along 101.3 miles of 
Los Angeles River, San Gabriel River, Rio Hondo, and 
Ballona Creek; and channel improvements along 193.69 
miles of tributary channels. All units of improvement 
are physically completed in those four stream basins, 
except the one listed below, and are described in Annual 
Report for 1962. 
Unit of improvement not physically completed in Rio 
Hondo Basin is Sierra Madre Wash. Plan provides for 
the construction of about 0.8 mile of concrete channel on 
Sierra Madre Wash extending from inlet to existing 
Santa Anita Wash channel. (See table 33-I for latest 
approved estimated (1976) first costs for all units of 
improvement under existing project.) 
Local cooperation. Requirements are described in 
full on page 33-11 of Annual Report for 1981. 
Operations during fiscal year. Operations for units 
in Los Angeles River Basin: (a) Compton Creek: Maintained 
channel in good operating condition from Alameda 
Street to Hooper Avenue storm drain. (b) Haines 
Canyon: Maintained debris basin and channel upstream 
from Plainview Avenue in good operating condition and 
administered real estate. (c) Hansen Dam: Maintained 
dam in good operating condition and administered real 
estate. (d) Lopez Dam: Maintained dam in good operating 
condition and administered real estate. (e) Los Angeles 
River channel, Lankershim Boulevard to Stewart and 
Gray Road: Administered real estate. (f) Los Angeles 
River channel, Santa Ana Branch, Pacific Electric 
railway bridge to Pacific Ocean: Initiated and completed 
preparation of plans and specifications for phase 2A 
construction of recreational facilities. Maintained dam 
in good operating condition and administered real 
estate. 
Operations for units in San Gabriel River Basin: (a) 
Santa Fe Dam: Maintained dam in good operating 
condition and administered real estate. Completed 
contract payment for construction of segments I and 2, 
phase 4, recreational facilities, at a cost of $17,431 
regular funds. (b) San Gabriel River channel, San 
Gabriel Canyon to Santa Fe Dam, Approach channel to 
Santa Fe Dam (remedial work): Maintained channel in 
good operating condition. (c) Whittier Narrows Dam: 
Completed preparation of plans and specifications for 
fourteenth contract for recreational facilities, riparian 
stream development. Maintained dam in good operating 
condition and administered real estate. 
Operations for units in Rio Hondo Basin: (a) Alhambra 
Wash: Maintained channel upstream from Valley Boule- 
33-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
vard in good operating condition. (b) Rio Hondo channel, 
Whittier Narrows Dam to Los Angeles River (lower): 
Initiated and completed preparation of plans and specifications 
for phase 2A construction of recreational 
facilities. 
Operations for unit in Ballona Creek Basin: Ballona 
Creek channel and jetties: Maintained channel downstream 
from Washington Boulevard to La Salle Avenue 
and downstream from Los Angeles city boundary to 
ocean; jetties; and Pacific Avenue bridge in good operating 
condition. Completed construction of second contract 
for recreational facilities in September 1983 at a cost of 
$121,045 regular funds and $223,168 required contributed 
funds. 
16. MOJAVE RIVER DAM, MOJAVE 
RIVER BASIN, CA 
Location. On Mojave River at the Forks site, just 
downstream from mouth of Deep Creek and about 14 
miles upstream from Victorville, in Mojave River 
Basin, CA. 
Existing project. A flood control dam and reservoir. 
Dam is a rolled-earthfill structure with a maximum 
height of 200 feet above streambed, a crest length of 
2,200 feet, and a detached spillway with a crest length of 
200 feet. Reservoir has a total capacity at spillway crest 
of 89.670 acre-feet (1965), including 11,000 acre-feet for 
sediment. Reservoir regulates runoff from a tributary 
area of 215 square miles, reducing flow of design flood 
from 94,000 cubic feet per second to a maximum 
outflow of about 23,500 cubic feet per second. Latest 
approved estimated (1981) first cost for modified project 
is $18,190,000 ($17,900,000 Federal and $290,000 non- 
Federal). Modification of project was authorized by the 
Chief of Engineers on November 27, 1964. 
Local cooperation. Requirements are described in 
full on page 33-13 of Annual Report for 1981. 
Operations during fiscal year. Maintained dam in 
good operating condition and administered real estate. 
17. PINE AND MATHEWS CANYONS 
DAMS, COLORADO RIVER BASIN, 
NV 
Location. In Lincoln County, NV. about 100 miles 
north of Hoover Dam and about 17 and 20 miles, 
respectively, east of Caliente, NV. 
Existing project. For details, see page 33-13 of 
Annual Report for 1981. 
Local cooperation. Fully complied with. 
Operations during fiscal year. Maintained dams in 
good operating condition and administered real estate. 
18. SAN JACINTO RIVER LEVEE AND 
BAUTISTA CREEK CHANNEL, 
SANTA ANA RIVER BASIN, CA 
Location. In Riverside County, CA, near San Jacinto, 
Hemet, and Valle Vista, CA. 
Existing project. A 3.9-mile-long levee on the left 
side of the San Jacinto River and about 3 miles of 
concrete-lined channel on Bautista Creek upstream 
from California State Highway 74. Latest approved 
estimated (1982) first cost is $15,630,000 ($13,600,000 
Federal and $2,030,000 non-Federal). 
Local cooperation. Fully complied with. 
Operations during fiscal year. Completed preparation 
of plans and specifications for construction of 48 
rock groins to correct project deficiency on San Jacinto 
River; awarded contract; and initiated construction, 
which is about 43 percent complete, at a cost of $661,447 
regular funds. Completed preparation of supplement to 
Design Memorandum No. 3 to correct project deficiency 
on Bautista Creek; and initiated preparation of plans 
and specifications, which are about 50 percent complete, 
for construction of a 1-mile-long concrete-lined channel 
on Bautista Creek. 
19. SANTA ANA RIVER BASIN (AND 
ORANGE COUNTY), CA 
Location. On Santa Ana River and tributaries and on 
other streams in Orange, Riverside, and San Bernardino 
Counties, CA. 
General plan of improvement. For details, see page 
33-14 of Annual Report for 1981. 
Existing project. For details on active units, see 
Annual Report for 1968. For other pertinent information, 
see table 33-E, "Other Authorized Flood Control Projects," 
and table 33-G, "Deauthorized Projects." (See 
table 33-J for latest approved estimated Federal first 
cost for all units.) 
Local cooperation. Fully complied with. 
Operations during fiscal year. Operations for units 
in existing project: (a) Brea Dam: Maintained dam in 
good operating condition and administered real estate. 
(b) Carbon Canyon Dam and channel: Maintained 
project in good operating condition; administered real 
estate; and continued acquisition of rights-of-way. (c) 
Fullerton Dam: Maintained dam in good operating 
condition and administered real estate. (d) Prado Dam: 
Maintained dam in good operating condition and administered 
real estate. Completed contract payment for 
construction of third contract for recreational facilities 
caot nat rciobsut toefd $f1u,6n0d9s . r(ee)g uSlaanr fAunntdosn iaon dD a$m1,:6 09 required Maintained 
dam in good operating condition and administered real 
estate. (f) San Antonio and Chino Creeks channel: 
Maintained project in good operating condition and 
administered real estate. 
33-8

LOS ANGELES, CA, DISTRICT 
20. SANTA MARIA VALLEY LEVEES, 
SANTA MARIA RIVER BASIN, CA 
Location. Along Santa Maria River and Bradley 
Canyon in Santa Barbara and San Luis Obisix Counties, 
CA, about 60 miles northwest of City of Santa Barbara. 
Improvements along Santa Maria River extend about 
21.9 miles from Fugler Point (at junction of Cuyama 
and Sisquoc Rivers) to Pacific Ocean. Improvements 
along Bradley Canyon extend from Canyon mouth to 
Santa Maria River. 
Existing project. Levee and channel improvements 
along Santa Maria River and along Bradley Canyon. 
Principal features include: about 17 miles of revetted 
levee along left bank of Santa Maria River from Fugler 
Point to State Highway 1 bridge at Guadalupe; about 5 
miles of revetted levee along right bank of Santa Maria 
River from about 1.3 miles downstream from U.S. 
Highway 101 to about 1.5 miles upstream from Southern 
Pacific railroad bridge; about 1.8 miles of channel and 
revetted levee from mouth of Bradley Canyon to Santa 
Maria River; about 21.9 miles of cleared channel along 
Santa Maria River from Fugler Point to Pacific Ocean; 
and raised Southern Pacific railroad bridge. Latest 
approved estimated (1980) first cost is $13,710,000 
(includes allowance for estimated inflation through 
construction period), comprising $12,600,000 Federal 
and $1,110,00)0 non-Federal. 
Local cooperation. Fully complied with. 
Operations during fiscal year. Completed contract 
payment for construction to correct project deficiencies 
at a cost of $61,019 regular funds. 
21. SANTA PAULA CREEK CHANNEL 
AND DEBRIS BASINS (INCLUDING 
MUD CREEK), SANTA CLARA 
RIVER BASIN, CA 
Location. Along lower Santa Paula Creek, a tributary 
of Santa Clara River, Ventura County, CA. 
Existing project. Plan as modified provides for a 
debris basin on Santa Paula Creek; a concrete channel 
along Santa Paula Creek from Santa Paula Creek 
debris basin to Santa Clara River; a debris basin on 
Mud Creek, a tributary of Santa Paula Creek; and a 
concrete channel along Mud Creek from Mud Creek 
debris basin to confluence with Santa Paula Creek. 
Approved estimated (1983) first cost for modified project 
is $37,980,000 (includes allowance for estimated inflation 
through construction period), comprising 
$.35,000,000 Federal and $2,980,000 non-Federal. Authorized 
project 4, approvedw as modified by Design Memorandum No. April 1973, which contains a map of 
modified project plan. 
Local cooperation. Requirements are described in 
full on page 33-15 of Annual Report for 1981. 
Operations during fiscal year. Continued preparation 
of supplement to Design Memorandum No. 4, 
which is about 85 percent complete. Continued preparation 
of environmental assessment. which is about 85 
percent complete 
22. SESPE CREEK AT FILLMORE, 
VENTURA COUNTY, CA 
LocIation. In and near the City of Fillmore. Ventura 
County, CA. 
Existing project. A 2-mile long rock-revetted single 
levee on the east bank of Sespe Creek; 25 rock groins 
that divert flows away from levee toe; floodgates in 
levee at Southern Pacific Railroad crossing; a new east 
span for Old Telegraph Road bridge; reinforced spans 
of railroad bridge; and 2 floodproofed homes on west 
bank. Latest approved estimated (1980) first cost for 
project is $6,600,000 ($4,000,000 Federal and $2,600,000 
non-Federal). 
Local cooperation. Requirements are described in 
full on page 33-15 of Annual Report for 1981. 
Operations during fiscal year. Completed construetion 
in May 1983. Costs for construction were $1,808,159 
regular funds and $482,397 required contributed funds; 
and cost for relocations was $24,737 regular funds. 
Initiated preparation of operation and maintenance 
manual, which is about 40 percent complete. 
23. SWEETWATER RIVER, 
SWEETWATER RIVER BASIN, CA 
Location. Lower Sweetwater River Valley, along 
Sweetwater River from Bonita Mesa Road to San Diego 
Bay, San Diego County, CA. 
Existing project. Plan provides for about 3.4 miles of 
improved trapezoidal channel along Sweetwater River 
from Bonita Mesa Road to San Diego Bay as part of a 
combined flood control and highway project. Approved 
estimated (1983) first cost for project is $35,100,000 
(includes allowance for estimated inflation through 
construction period), comprising $17,400,000 Federal 
and $17,700,000 non-Federal. 
Local cooperation. Requirements are described in 
full on page 33-16 of Annual Report for 1981. 
Operations during fiscal year. Continued preparation 
of project plan, which is about 99 percent complete. 
Continued preparation of final environmental statement, 
which is about 99 percent complete. 
24. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Los Angeles County drainage area, CA, channels 
were inspected in May, June, July, and August 1983. 
Inspection costs for fiscal year from regular funds for 
maintenance were $252,480. 
33-9

REPORT OF THE CHIEF OFF ENGINEERS. U.S. ARMY 1983 
25. SCHEDULING FLOOD CONTROL 
RESERVOIR OPERATIONS 
In accordance with section 7. Flood Control Act of 
1944. studies of reservoir operations for flood control 
were conducted: and preparation of regulations for the 
use of storage allocated for flood control was continued 
for the following Bureau of Reclamation projects: Hoover 
Dam and Twitchell Dam. Costs for fiscal year from 
regular funds for maintenance were $34.914. 
26. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control activities pursuant to section 205,. 
Public Law 80-858, as amended (preauthorization) 
See table 33-K on flood control work under special 
authorization. 
Emergency bank protection (sec. 14 of 1946 Flood 
Control Act, Public Law 526, 79th Cong.) 
Federal cost for fiscal year was $107 for Pismo Beach. 
CA, seawall. 
Emergency flood control activities - repair, flood 
fighting, and rescue work (Public Law 99, 84th 
Cong., and antecedent legislation) 
Federal cost for fiscal year was $169.181. of which 
$127,103 were for advance preparation: $17.889 were 
for flood emergency operations: and $24.189 were for 
rehabilitation. 
Flood insurance activities (sections 1301-1377, 
1968 Housing and Urban Development Act, Public 
Law 90-448, as amended) 
In coordination with flood control activities, flood 
insurance studies were continued in accordance with 
Inter-Agency Agreements at fiscal year cost of $22.427 
under Housing and Urban Development reimbursable 
order. 
General Investigations 
27. SURVEYS 
Fiscal year cost was $3,290,212 regular funds, of 
which $553,059 were for navigation studies: $6,608 
were for beach erosion control studies: $1,795.557 were 
for flood control studies: $587,947 were for surveys; 
$47,320 were for special studies involving coordination 
with other agencies: $192,987 were for review of authorized 
projects; and $106,734 were for special investigations. 
28. COLLECTION AND STUDY OF 
BASIC DATA 
Fiscal year costs were $95,480 for technical services, 
including -$128 for Salt and Gila Rivers, Maricopa 
County, AZ; and $93 for Ventura River, Ventura 
County, CA; $48,305 for flood plain management; and 
$195 for inspection of dams. 
29. RESEARCH AND DEVELOPMENT 
Fiscal year cost was $7.572 for hydrologic studies. 
30. CONTINUATION OF PLANNING 
AND ENGINEERING 
30A. HOLBROOK LEVEE, LITTLE 
COLORADO RIVER, COLORAI)DO 
RIVER BASIN, AZ 
Holbrook levee is on Little Colorado River at Hlo lbrook. 
Navajo County. AZ. in northeastern Arizona. about 200 
miles northeast of Phoenix. Project was authorized by 
Flood Control Act of 1970. Public Law 91-611. dated 
December 31. 1970. 
Plan of improvement provides for raising existing 
north bank levee and adding a new south bank levee, a 
low flow channel, recreational facilities, and mit igat ion 
features. Existing levee (north) would be raised to a 
height ranging from 23 feet high upstream from Apache 
Railroad bridge to about 12 feet high downstream from 
bridge, and would be about 18.000 feet long. South side 
levee would be about 5,000 feet long and would have a 
maximum height of 23 feet. 
Continued preparation of project plan during fiscal 
year. Estimated preconstruction planning cost is 
$853.000. Total costs during fiscal year were $195.710. 
30B. SANTA ANA RIVER MAIN STEM 
-INCLUDING SANTIAGO CREEK 
AND OAK STREET DRAIN, SANTA 
ANA RIVER BASIN, CA 
Santa Ana River main stem-including Santiago 
Creek and Oak Street Drain, Santa Ana River Basin. 
CA. is on Santa Ana River and tributaries and on other 
streams in Orange. Riverside. and San Bernardino 
Counties. CA. Project was authorized by Water Resources 
Development Act of 1976. Public Law 94-587. dated 
October 22, 1976. 
Plan of improvement provides for construction of 
Mentone Dam near community of Mentone, San e rnardinoCounty; 
managementofflood plain between Mentone 
Dam and Prado Reservoir: improvement of Oak Street 
Drain in Corona, Riverside County; enlargement of 
existing Prado Dam and reservoir, Riverside and San 
Bernardino Counties: improvement of lower Santa A na 
River channel from Prado Dam to Pacific Ocean: and 
improvement of lower reach of Santiago Creek channel 
in Orange County; recreational development along 
project length; purchase of 8 acres of salt marsh for 
mitigation of project effects: purchase of 84 acres of 
tidal lands at mouth of Santa Ana River for preservation 
of endangered least tern habitat: landscaping: andl 
recreational features. 
Initiated preparation of project plan, phase II. (luring 
fiscal year. Estimated preconstruction planning cost is 
33-10

LOS ANGELES, CA, DISTRICT 
$20,300,000. Total costs during fiscal year were 
$2,400,692. 
31. ADVANCE ENGINEERING AND 
DESIGN 
SAN LUIS REY RIVER, SAN 
LUIS REY RIVER BASIN, CA 
San Luis Rey River, San Luis Rey River Basin, CA, is 
in the lower San Luis Rey River Valley, along San Luis 
Rey River from Murray Road (river mile 7.2) to Pacific 
Ocean, San Diego County, CA. Project was authorized 
by Flood Control Act of 1965, Public Law 89-298, dated 
October 27, 1965. Final date of approval by House and 
Senate Public Works Committees resolution was DIecember 
17, 1970. 
Plan of improvement provides for about 5.7 miles of 
earth-bottom trapezoidal channel along San Iluis Rey 
River from Murray Road to about 1 mile upstream from 
U.S. Highway No. 101; about 1.5 miles of channel 
grading, which would generally be limited to removal 
of spoil banks, from about I mile upstream from U.S. 
Highway No. 101 to ocean; and about 800 feet of stonerevetted 
leveeon the left (south) bank from the Atchesonm. 
Topeka and Santa Fe railroad to ocean. Plan also 
provides for beautification features. 
Continued preparation of project plan, phase II, 
during fiscal year. Estimated preconstruction planning 
cost is $1,944,000. Total costs during fiscal year were 
$241,061. 
33-41

TABLE 33-A 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 80 FY 81 FY 82 FY 83 Sep. 30, 1988 
1. Channel Islands New Work: 
Harbor, CA Approp. 
2. Los Angeles and 
Long Beach 
Harbors, CA 
(Regular Funds) 
Required Contrib. 
unds) 
Other Contrib. 
unds) 
3. Oceanside Harbor., 
CA (Regular 
Funds) 
(Other Contrib. 
Funds) 
4. Port Hueneme. CA 
(Regular Funds) 
Other Contrib. 
Funds) 
5. San Diego River 
and Mission Bay, 
CA 
6. Santa Barbara 
Harbor. CA 
7. Ventura Marina 
(Ventura Harbor). 
CA 
Cot 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Contrib. 
Cost 
Maint.: 
Contrib. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
Maint.: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
- - - - $5,123,345' 
- - - - 5,123,345' 
$1,755,800 $135,000 $2,212,577 $2,441,000 17,879,5062 
1,749,607 120,000 2,226,683 109,904 15,539,5732 
1,897,000 9,525,000 12,968,000 5,323,000 65,119,719' 
613,231 9,208,416 13,626,683 5,721,814 64,550,3318 
1,032,592 80,322 980,000 2,768,600 8,142,0594 
984,783 131,664 972,371 358,760 5,724,5904 
- 599,000 390,000 214,180 1,203,180 
- 365,188 548,526 175,655 1,089,369 
2,500,000 18,688,000 11,294,000 4,220,130 38,374,705b 
125,353 15,661,607 14,893,514 4,777,401 37,130,4506 
- - - - 87,120' 
- - - - 87,1206 
- 1,063,000 692,825 5,081,782 10,035,6727 
- 998,795 649.198 642.862 5,487,4187 
- - - - 491.2866 
- - - - 491,2866 
- 1.200,000 - - 1,200,000 
- 1.160,000 20,000 7.500 1.187.500 
41.000 - 240,000 - 1,681.400 
6.634 24.970 260,105 6.504 1.279,161 
2.000 - 22,931 1,510.569 1,550,7251 
2,000 - 22,931 81,256 121,4121 
- - - - 58,088 
-- - - 57.609 
270,000 250.000 285,000 - 11.870,09910 
228.165 222.763 269,031 122.034 11,835,334"' 
7.308 7,701 - 3,627.000 4.874,473" 
7,540 7,701 - 289.324 1.536.797" 
-- - - 172.00012 
- - - - 172.00012 
670.000 819.088 855.169 945.543 7.919,1191; 
669.003 820,922 855.755 555.992 7.529.436 ' 
- - - - 1.711.539' 
- - - - 1.711.539 1 
448.800 1.119.489 1.047.100 2.488.000 11.640.437 ' 
423.228 1.124.735 1.046,894 2.329.024 11.458.268 ' 
33-12

LOS AN(ELES, CA, I)ISTRICT 
TABLE 33-A (Cont'd) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 80 FY 81 FY 82 FY 83 Sep. 30, 1983 
9. Imperial Beach, 
CA (Regular 
Funds) 
(Required Contrib. 
Funds 
10. San Gabriel River 
to Newport Bay 
(Surfside-Sunset 
and Newport Beach), 
Orange County, CA 
(Regular Funds) 
(Required Contrib. 
Funds) 
(Other Contrib. 
Funds) 
11. Alamo Lake, 
Bill Williams 
River, AZ 
12. Allenville, AZ 
(Regular Funds) 
(Required Contrib. 
Funds) 
13. Cucamonga Creek, 
Santa Ana River 
Basin, CA 
(Regular Funds) 
(Required Contrib. 
Funds) 
(Other Contrib. 
Funds) 
14A. Gila River Basin, 
AZ, Indian 
Bend Wash 
(Regular Funds) 
(Required Contrib. 
Funds) 
(Other Contrib. 
Funds) 
14B. Gila River Basin, 
AZ, Painted 
Rock Dam (Gila 
River) 
14C. Gila River Basin, 
AZ, Phoenix, 
AZ, and vicinity 
(including New River) 
(Regular Funds) 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
-28,000 - 849.757' 
38.174 74.623 798.871"s 
- - 25,601 
- - 25.584 
- 255,000 6.469.100 
33,321 153,690 6,357.184 
- 246,900 
- 58,135 
69,550 -31,826 
- 103,738 
- 51 
212,000 272.000 
208,931 266,153 
179,857 2,780,0(X) 
195,298 2,335,961 
- 200,000 
- 159,196 
10,360,000 23,754,000 
10.568,282 23,239,439 
424,000 48 
411,266 37 
- -51 
390,474 
28,769 
17,256,000 
15,700,133 
758,083 
1,645,662 
2,515,000 
1,869,796 
3,956 
4,05 
3,266,010 
2,987,250 
2,577,000 
- 16,934,060 
- 16,934,060' 
7,000 3,388,799 
2.021 3,242,167 
0,000 2,949,857 
8,322 2,942,961 
- 200,000 
- 187,965 
0,000 91.546,900 
7,329 89.167,620 
-270,893 
400,965 
6,000,000 
5,006,159 
85,512 
72.264 
9,422,858 
9,250,347 
30,596,480 
28,712,969 
10 - 
90,107 4,229 
- 2,577,000 
3,574.144 
1,747,264 
1,133,000 
1,199,929 
1,264,509 
1,596,452 
3,243,000 
3,198,191 
43,064 - 46,190 - 384,754 
27,985 - 4,089 37,118 304,720 
-29,428 - 359,000 668,979 3.303,361 
134,015 20.275 8,345 386,307 2,580,185 
- - - 19,980,564"' 
- 208 - - 19,980,564'" 
1,827,000 325,500 592,000 594,000 6,310,148 
1,803,377 309,586 629,289 551,293 6,262,683 
5,023,000 11,400,000 6,198,000 4,680,000 49,895,297 
5,064,307 11,008,053 5,399,656 5,621,403 49,060,073 
33-13

REPORT OF THE CHIIEF OF ENG;INEERS. '.S. ARMY 1983 
TABLE 33-A (Cont'd) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 80 FY 81 FY 82 FY 83 Sep. 30. 1983 
(Required Contrib. 
Funds) 
(Other Contrib. 
Funds) 
14D. Gila River Basin. 
AZ. Whitlow 
Ranch Dam. 
Queen Creek 
15. Los Angeles County 
drainage area., 
CA (Regular Funds) 
Required Contrib. 
Funds) 
(Other Contrib. 
Funds) 
16. Mojave River Dam. 
Mojave River 
Basin, CA 
(Regular Funds) 
(Other Contrib. 
Funds) 
17. Pine and Mathews 
Canyons Dams., 
Colorado River 
Basin. NV 
18. San Jacinto River 
levee and Bautista 
Creek channel, 
Santa Ana River 
Basin. CA 
19. Santa Ana River 
Basin (and Orange 
County), CA 
(Regular Funds) 
(Required Contrib. 
Funds) 
20. Santa Maria Valley 
levees. Santa Maria 
River Basin. CA 
21. Santa Paula Creek 
channel and debris 
basins (including 
Mud Creek), Santa 
Clara River Basin. CA 
New Work: 
Contrib. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
359.(0k) 
178.751 
296.000 
-906 - ) 
52.00() 
48.685 
3.568.000 
4.528.809 
3.837.700 
3,808,269 
2.747,3(K)00 
2.755.063 
8.544 
207.00MM4) 
235.(i4 
51.($M) 
48.620 
- 
46.($$) 
-2.114 
2.172.5(K) 
1.965.343 
-84.0()0 
149.595 
150,0() 
ItW,269 
49,(0)0 
17,016 
202.521 
240.960 
33.000 
36.566 
2.697.000 
1.990.086 
3.234.600 
2.773.217 
616.467 
760.513 
9.927 
241.0(X) 
240.158 
28.000 
30.760 
92.000 
154.058 
1.606.000 
1.744.626 
45.000 
118.891 
1.6(00.000 
1.475.037 
250.000 
213.732 
127.0 0 
47.262 
38.7(00 
77.223 
47.000 
42.645 
815.000 
1.337,870 
3,044,000 
2.719,160 
127.500 
527.013 
244 
773.(X) 
754.707 
44.000) 
39.883 
239,000 
212,270 
-1,367 
1,291,700 
1,224,904 
44.056 
2,405,000 
2,466,494 
310,000 
313,444 
34
8 
148. 
96 
36 
9.10 
5.72 
28 
37 
65 
24
64 
2.63 
1.(X) 
t.i(,0 1.214.21.1 
1.743 753.t7r7 
- 459.700t 
- 396.562 
- 1.86t;7.ii3" ' 
- 1.867.sK;3. 
5.(KX) 623.113:; 
4.911 558.0;9 
7.700 377.05t.t685 ' 
7.925 375.953.821 " 
7.tXx) 44.832.020 ' 
3.627 40.58t..thk' 
6.818 13.933.3.11 
8.256 13.70 1.580 ' 
- 36.6.14.85 
- 36.639.888 
- 17.838.198 
- 17.838.198 
3.(Kk) 2.411.548 
4.816 1.983.942 
- 286.3() 
- 284.501 
- 1.401\248 
- 1.401.48 
3.0(K) 616.35;ti 
3.070 592.34 9 
;88..99)033 4.248. 1lI44. 7 ;' 
819.3(K) 47.970,9382 > 
83,204 47.204.818 " : 
2.266,0(K) 18.854.810 : 
1,686,767 18.114.954 " :i 
- 3.140.15 ;:* 
21,149 3..22: 
- 10.080.134:" 
75,776 10.048.70.5" 
- 4,591.1NNFM', 
30,477 4,55.455:.!" 
33-14

LOS ANGELES, CA, I)ISTRICT 
TABLE 33-A (Cont'd) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 80 FY 81 FY 82 FY 83 Sep. 30, 1983 
22. Sespe Creek at New Work: 
Fillmore, Ventura Approp. 25,000 40,(100 2.630,00() 1,080.00(0 4,00.)000 
County, CA Cost 24,229 46,769 1.784,599 1,930,193 3,996.313 
(Regular Funds) 
(Required Contrib. New Work: 
Funds) Contrib. - - 185,542 297,983 483,525 
Cost - - - 482,442 482,442 
23. Sweetwater River, New Work: 
Sweetwater River Approp. 100,000 15,100 50,000 145,000 1,624,503 
Basin, CA Cost 40,948 72,395 53,603 136,413 1,615,914 
33-15 
1. Excludes $1,361,668 Navy funds; Coast Guard costs; 
and $210,748 other contributed funds. 
2. Includes $7,178 for reconnaissance and condition surveys. 
Excludes $3,634,550 for maintenance accomplished 
with Navy funds. 
3. Includes $2,187,047 for new work for previous project:; 
$1,593,667 public works funds; a credit of $33,050 for transfer 
of land at Reservation Point; and $996,792 emergency relief 
funds. Excludes Federal funds spent by the Navy for new 
work on middle breakwater, and Coast Guard costs. 
4. Includes $139,347 for maintenance forprevious project 
and $121,523 for reconnaissance and condition survey costs 
since FY 1958. 
5. Includes $1,672,575 for new work betterments desired 
by local interests prior to 1976 modification. 
6. Includes $87,120 for maintenance betterments desired 
by local interests prior to 1976 modification. 
7. Includes $67,937 for reconnaissance and condition 
surveys. Excludes $3,945,517 for maintenance accomplished 
with Navy funds. 
8. For jetty and groin extensions desired by local interests. 
9. Includes $60,725 for reconnaissance and condition 
surveys. 
10. Includes $2,610,000 regular funds and excludes 
$2.910,()000 required contributed funds, both for new work on 
fklxxl control project, "San Diego River Basin, Calif." 
11. Includes $81,941 for reconnaissance and condition 
surveys. 
12. Excludes Coast Guard costs. 
13. Includes $29,198 public works funds; $11,000 working 
funds for work performed in addition to existing project; an 
$19,741 for reconnaissance and condition surveys. Excludes 
$462,986 other contributed funds spent by the Corps for 
maintenance-dredging bettermentsdesired by local interests. 
14. Excludes $1,708,836 required contributed funds and 
Coast Guard costs. 
15. Includes $53,899 for reconnaissance and condition 
surveys. 
16. Excludes $66,124 other contributed funds and Coast 
Guard costs. 
17. Includes $57,000) Code 710 funds since FY 1975. 
18. Includes 357,469 Code 710 funds since FY 1962. 
19. Includes 3,758 Code 710 funds since FY 1962. 
20. Includes $11,008,935 emergency relief funds for new 
work. Excludes $16,726,888 emergency relief funds spent by 
Corps in connection with emergency relief (previous) project 
and $107,939 for minor rehabilitation. 
21. Includes $23,787,700 Code 710 funds since FY 1974 
($1,226,100 for Sepulveda Dam; $6,290,000 for Whittier 
Narrows Dam; $22,000 for LACDA prototype; $535,000 for 
Hansen Dam: $10,437,100() for Santa Fe Dam; $215,000 for 
Tujunga Wash channel: $8,500 for Lopez Dam; $3,571,000 for 
LosI Angeles River and Rio Hondo channels; and $1.483,000 
for Ballona Creek channel). 
22. Includes $22,690,835 Code 710 funds since FY 1974 
($1,222,833 for Sepulveda Dam; $6,289,218 for Whittier 
Narrows Dam; $22,000 for LACDA prototype: $534,206 for 
Hansen Dam; $9,426,202 for Santa Fe Dam; $215,000 for 
Tujunga Wash channel: $8,500 for Lopez Dam; $3,511,875 for 
Los Angeles River and Rio Hondo channels; and $1,461,001 
for Ballona Creek channel). 
23. Includes $13,933,341 Code 710 funds since FY 1974 
($992,650 for Sepulveda Dam; $6,797,556 for Whittier Narrows 
Dam; $199,541 for Tujunga Wash channel: $460,500 for 
Hansen Dam; $2,824,056 for Los Angeles River and Rio 
Hondo channels: $1,467,538 for Santa Fe Dam: and $1,191,500 
for Ballona Creek channel). 
24. Includes $13,701,580 Code 710 funds since FY 1974 
($992,545 for Sepulveda Dam: $6,590,581 for Whittier Narrows 
Dam; $199,083 for Tujunga Wash channel: $457,623 for 
Hansen Dam; $2,824,054 for Los Angeles River and Rio 
Hondochannels; $1,467,538 for Santa Fe Dam; and $1,170,156 
for Ballona Creek channel). 
25. Non-Federal funds spent by the Federal Government 
to September 30, 1983, for replacements required as part of 
local cooperation and betterments desired by local interests. 
Excludes $4,238,000 other contributed funds spent by the 
Corps in connection with emergency relief(previous) project. 
26. Excludes $327,723 other contributed funds. 
27. Comprises funds for Brea, Fullerton, Prado, and San 
Antonio Dams, Carbon Canyon Dam and channel, Lytle and 
Cajon Creeks channel improvements, and San Antonio and 
Chino Creeks channel (active units). 
28. Includes $5,000 working funds for San Antonio Dam: 
$67,361 for San Juan Dam (inactive unit) (also reported under 
"Other Authorized Flood Control Projects"); and $85,310 
undistributed funds. Excludes other contributed funds spent 
by the Corps, as follows: $124,105 for water conservation 
betterments desired by local interests at Prado Dam; $8,500 
for betterments desired by local interests at San Antonio 
Dam; $234,709 for betterments desired by local interests on 
San Antonio and Chino Creeks channel; and $601,762 for 
required items of local cooperation on Lytle and Cajon Creeks 
channel improvements. Excludes $290,000 spent direct by 
local interests on San Antonio and Chino Creeks channel for 
local cooperation items not required. 
29. Includes $5,897,031 Code 710 funds since FY 1974 
($1,058,731 for Carbon Canyon Dam and channel; $1,264,300 
or Fullerton Dam; and $3,574,000 for Prado Dam). 
30. Includes $5,130,911 Code 710 funds since FY 1974 
($1,058,731 for Carbon Canyon Dam and channel: $1,264,300 
or Fullerton Dam; and $2,807,880 for Prado Dam). 
31. Excludes maintenance for Lytle and Cajon Creeks 
channel improvements, which are operated and maintained 
by local interests. 
32. Includes $3,140,156 Code 710 funds since FY 1974 
($1,424,926 for Carbon Canyon Dam and channel; $1,289,230 
for Fullerton Dam: and $426,000 for Prado Dam).

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 33-A (Cont'd) COST AND FINANCIAL STATEMENT 
33. Includes $3,099,622 Code 710 funds since FY 1975 35. Excludes $49,458 other contributed funds and non- 
($1,407.964 for Carbon Canyon Dam and channel: $1,267,523 Federal costs of $295,000 for local cooperation items not 
for Fullerton Dam; and $424,135 for Prado Dam). required. 
34. Excludes $106,364 other contributed funds. 
TABLE 33-B AUTHORIZING LEGISLATION 
See Date of 
Section in Authorizing 
Text Act Project and Work Authorized Documents 
1. Sep. 3, 1954 
2. June 3, 1896 
June 25, 1910 
July 25, 1912 
Aug. 8. 1917 
Sep. 22. 1922 
Mar. 3. 1925 
July 3. 1930 
Do. 
Aug. 30. 1935 
Oct. 17. 1940 
CHANNEL ISLANDS HARBOR, CA 
Harbor for light-draft vessels and shore protection works. H. Doc. 362, 83d Cong., 
2d sess. 
LOS ANGELES AND LONG BEACH HARBORS, CA 
A breakwater 8.500 feet long, east of Point Fermin. S. Doc. 18, 55th Cong., 
1st sess. 
Extend said breakwater to shore, making a total length H. Doc. 969, 60th Cong., 
of 11,152 feet from Point Fermin. 1st sess. 
Dredge Los Angeles outer harbor west of entrance Rivers and Harbors 
channel. Committee Doc. 8, 
62d Cong., 2d sess. 
For silt-diversion works. Rivers and Harbors 
Committee Doc. 9, 
64th Cong., 2d sess. 
Triangular area approach to Los Angeles inner harbor H. Doc. 1013, 66th Cong., 
entrance channel. 3d sess. 
Dredge Los Angeles Harbor main channel and entrance H. Doc. 349, 68th 
35 feet deep and 1,000 feet wide: dredge inner harbor Cong., 1st sess. 
turning basin 35 feet deep: and reclamation of Reservation 
Point. 
A detached breakwater 12,500 feet long in prolongation Rivers and Harbors 
of existing breakwater (authorized by act of 1896). Committee Doc. 33, 
71st Cong., 2d sess. 
Widen fairway on east side of entrance to Los Angeles S. Doc. 130, 71st Cong., 
inner harbor; dredge a channel 35 feet deep and 650 2d sess. 
feet wide in East Basin from turning basin to U.S. 
station 406: dredge 35 feet deep and 400 feet wide 
in Cerritos channel from U.S. station 406 to Long 
Beach turning basin; a turning basin 35 feet deep 
at Long Beach: entrance channel to Long Beach Harbor 
35 feet deep and 500 feet wide: and maintenance 
of the Long Beach breakwater south of outer end pier 
A. This act provides that in no case shall dredging 
be done within 50 feet of established pierhead lines 
of existing piers and wharves. 
Dredge 1,000-foot-wide entrance channel to Los Angeles S. Committee print, 
outer harbor to 40-foot depth and a turning basin 3,500 74th Cong.. 1st sess. 
feet long and 1,500 feet wide to same depth: and enlarge 
entrance to inner harbor by dredging to 35-foot depth a 
triangular area at its junction with turning basin. 
Dredge to a depth of 40 feet areas A and B adjacent to H. Doc. 843. 76th Cong.. 
40-foot-depth entrance channel: construct and maintain a 3d sess. 
rubblemound breakwater of composite type 21.000 feet 
long in eastward direction from northeast end of existing 
detached breakwater: dredge about 4 million cubic yards 
initially for a settling basin at mouth of Los Angeles 
River diversion channel, and deposit material on beaches 
eastward therefrom to Belmont pier: maintenance dredging 
of areas A and B. and at mouth of Los Angeles River 
diversion channel: all subject to such modifications as 
in discretion of the Chief of Engineers may be advisable 
to meet requirements of the Navy. 
33-16

L)S ANGELES, CA, I)ISTRICT 
TABLE 33-B (Cont'd) AUTHORIZING LEGISLATION 
See Date of 
Section in Authorizing 
Text Act Project and Work Authorized Documents 
Sep. 3, 1954 
July 14, 1960 
Oct. 22, 1976 
3. Oct. 27, 1965 
4. Aug. 13, 1968 
5. July 24, 1946 
6. Aug. 30, 1935 
Mar. 2. 1945 
Oct. 23. 1962 
Dec. 31. 1970 
7. Aug. 13, 1968 
Dredge to a depth of 35 feet in East Basin as a modification 
of existing project. This act provides that the Secretary 
of the Army is authorized to reimburse local interests 
for work they have done upon this project prior to 
July 1, 1953, at actual cost to local interests so 
far as same shall be approved by Chief of Engineers and 
found to have been done in accordance with the project 
hereby adopted and that such reimbursement shall be 
subject to appropriations applicable thereto or funds 
available therefor and shall not take precedence over 
other pending projects of higher priority for harbor 
improvements; and that such payments shall not exceed 
$500,000. 
Dredge to a depth of 35 feet in West Basin as a 
modification of existing project. 
Dredge Los Angeles Harbor entrance channel 45 feet 
deep, 1,000 feet wide, and about 5,500 feet long; Los 
Angeles channel 45 feet deep, 750 feet wide, and about 
12,500 feet long; inner harbor turning basin 45 feet 
deep, 1,350 feet wide, and about 1,650 feet long; East 
Basin channel 45 feet deep, 400 feet wide, and about 6,000 
feet long; West Basin 45 feet deep, from 350 to 1,350 feet 
wide, and about 3,800 feet long; and East Basin 45 feet 
deep, from 400 to 950 feet wide, and about 2,000 feet 
long. This act provides that no dredging shall be done 
within 125 feet of established pierhead lines, wharves, 
or other structures 
OCEANSIDE HARBOR, CA 
Maintenance of general navigation features of Del Mar 
Boat Basin and of Oceanside Harbor. 
PORT HUENEME, CA 
Adoption and maintenance of existing harbor for 
deep-draft vessels: dredge central basin to 35 feet 
deep; and widen, dredge to 35 feet deep, and extend 
southernmost interior channel. 
SAN DIEGO RIVER AND MISSION BAY, CA 
Modification of existing flood control project for San Diego 
River, CA, to include a multiple-purpose project for 
flood control on San Diego River and small-boat navigation 
on Mission Bay. 
SANTA BARBARA HARBOR, CA 
Maintenance dredging present depths into harbor formed 
by breakwater constructed by local interests. 
Permits maintenance by means of a fixed sand-intercepting 
plant to be provided and operated by and at expense of 
local interests. United States to contribute to operating 
expense an amount not to exceed $30,000 annually, 
whenever funds are allotted therefor; funds thus contributed 
to be reduced by actual cost of harbor maintenance if 
and when intercepting plant has been installed. 
Modification of existing project. 
Dredging and maintenance by United States. 
VENTURA MARINA (VENTURA HARBOR), CA 
Adoption and maintenance of existing general navigation 
features of harbor, excluding interior basins; construction 
of an offshore breakwater: dredging a sand trap in lee of 
breakwater: repairing existing north and middle jetties: 
and construction of recreational fishing facilities on 
jetty crests. 
33-17 
H. Doc. 161, 83d Cong., 
1st sess. 
H. Doc. 401, 86th Cong., 
2d sess. 
H. Doc 94-594, 94th 
Cong., 2d sess.' 
H. Doc. 76, 89th Cong., 
1st sess. 
H. Doc. 362, 90th Cong., 
2d sess. 
H. Doc. 760, 79th Cong., 
2d sess.' 
S. Committee Print. 73d 
Cong., 2d sess. 
H. Doc. 348, 77th Cong.. 
1st sess. 
H. Doc. 518. 87th Cong.. 
2d seas.' 
None 
H. Doc. 356. 9oth Cong.. 
2d sess.

REPORT OF THE C'HlIEF OF EM;NGINEERS. t'.S. ARMY 1983 
TABLE 33-B (Cont'd) AUTHORIZING LEGISLATION 
I)ate of 
Authorizing 
Act Project and Work Authorized I)ocunents 
9. July 3. 1958 
10. Oct. 23. 1962 
11. Dec. 22. 1944 
12. July 15. 1980? 
13. Aug. 13. 1968 
14A. Oct. 27, 1965 
Mar. 7. 1974 
14B. May 17. 1950 
14C. Oct. 27, 1965 
14D. July 24. 1946 
15. June 22, 1936 
May 15. 1937 
June 28. 1938 
Aug. 18, 1941 
IMPERIAL BEACH. ('A 
Federal participation by contribution of Federal funds 
toward cost of five groins. 
SAN GABRIEL RIVER TO NEWPORT BAY 
SURFSIDE-SUNSET AND NEWPORT BEACH). 
RANGE COUNTY. CA 
Modification of authorized project at Anaheim Bay 
Harbor. CA. to provide for an offshore breakwater at 
Newport Beach and a protective and feeder beach in 
the vicinity of Surfside-Sunset Beach. Federal participation 
by contribution of Federal funds toward 
first costs and costs of periodic nourishment and 
maintenance. 
ALAMO LAKE, BILL WILLIAMS RIVER, AZ 
Multiple-purpose dam and reservoir. 
ALLENVILLE, AZ 
Relocate community, streets, utilities, community center, 
and park: and replace houses. 
CUCAMONGA ('REEK. SANTA ANA RIVER 
BASIN, CA 
Debris-collection facilities. with a system of channels. and 
a diversion system. 
INDIAN BEND WASH, GILA RIVER BASIN, AZ 
Channel. levees, a siphon system. and transition works. 
Cost of siphon system borne by United States. 
PAINTED ROCK DI)AM (GILA RIVER), GILA 
RIVER BASIN, AZ 
Dam and flood control basin. 
PHOENIX, AZ., ANDI) VICINITY (INCLUDING NEW 
RIVER), GILA RIVER BASIN 
Detention basins, diversion channels, and channel 
improvements. 
WHITLOW RANCH DAM, QUEEN CREEK, GILA 
RIVER BASIN, AZ 
Dam and flood control basin. 
LOS ANGELES COUNTY DI)RAINAGE AREA, CA 
Reservoirs and flood channels for flood control and related 
purposes at an estimated construction cost not to exceed 
70 million. 
Added flood channels on Ballona Creek and tributaries to 
project. 
Provision of lands, easements, and rights-of-way and 
relocations by Federal Government instead of by local 
interests. (Resultant additional cost to the United 
States. $12,541,000.) 
Project extended to include additional flood control 
reservoirs, flood control channels, and debris basins for 
flood control and related purposes. Also authorized to be 
appropriated $25 million for further accomplishment of 
plan. 
H . I)w. 3:99. 8.lth 'Cong.. 
2d sess. 
H. Doc. 602. 87th Cong.. 
2d sess. 
H. Doc. 625. 78th Cong.. 
2d sess. 
None 
H. Doc. 323. 90th ('ong.. 
2d sess. 
H. Doc. 303. 88th Collng.. 
2d sess. 
None 
H. Doc. 331. 81st ('ong.. 
1st sess. 
H. Doc. 216. 89th ('ong.. 
1st sess. 
H. Doc. 220. 80th C('ong.. 
1st sess. 
None 
None 
None 
H. Doc. 838. 76th ('ong.. 
3d sess. 
33-18 
See 
Section in 
Text

LOS ANGELES, CA, ISTRICT 
TABLE 33-B (Cont'd) AUTHORIZING LEGISLATION 
See I)ate of 
Section in Authorizing 
Text Act Project and Work Authorized Documents 
I)ec. 22. 1944 Authorized to be appropriated an additional $25 million None 
for prosecution of comprehensive plan approved in Flood 
Control Act of Aug 18. 1941. 
Authorized to be appropriated an additional $25 million 
for further prosecution of comprehensive plan. 
Rio Hondo channel improvement. Whittier Narrows 
Reservoir to Los Angeles River (in lieu of enlarging 
channel and bridges on San Gabriel River downstream 
from reservoir). Also authorized to be appropriated 
an additional $40 million for further prosecution of 
comprehensive plan. 
Authorized to be appropriated an additional $12.500,000 
for further prosecution of comprehensive plan. 
Authorized to be appropriated an additional $44 million 
for further prosecution of comprehensive plan. 
Authorized to be appropriated an additional $32 million 
for further prosecution of comprehensive plan. 
Authorized to be appropriated an additional $3,700.000 
for further prosecution of comprehensive plan. 
Authorized to be appropriated an additional $30 million 
for further prosecution of comprehensive plan. 
In addition to all previous authorizations, completion of 
improvements under the comprehensive plan for flood 
control in the Ls Angeles River Basin at a presently 
estimated cost of $31 million for completion. 
MOJAVE RIVER I)AM. MOJAVE RIVER BASIN, CA 
Dam and reservoir. and an earthfill dike. 
17. May 17. 1954) 
1s. May 17. 1950) 
19. .June 22. 1936 
.June 28. 1938 
Aug. 18. 1941 
PINE AND MATHEWS CANYONS DI)AMS. 
COLORADO RIVER BASIN. NV 
Dams and flood control basins. H. Doc. 530. 81st Cong.. 
2d sess. 
SAN JACINTO RIVER LEVEE AND BAUTISTA 
CREEK CHANNEL, SANTA ANA RIVER BASIN, CA 
Levees along Mill Creek in zone 1: a system including H. Doc. 135. 81st Cong.. 
levees and channel improvements generally along Devil, 1st sess. 
East Twin. and Warm Creeks in zone 5: levees along Santa 
Ana River near Riverside in zone 7: and levees along 
Bautista Creek and San Jacinto River in zone 9. at an 
estimated construction cost not to exceed $17.577.000. 
SANTA ANA RIVER BASIN (AND ORANGE 
COUNTY), CA 
Reservoirs and flood channels for flood control and None 
related purposes for protection of metropolitan area of 
Orange County, at an estimated construction cost not to 
exceed $13 million. 
San Antonio and Chino Creeks channel portion of H. Doc. 688. 75th Cong.. 
improvement. Authorized to be appropriated $6.500.000 3d sess. 
for initiation and partial accomplishment of plans for 
those creeks. Rescinded provisions of Flood Control Act 
of 1936. providing that local interests pay for 
relocations, lands. easements. and rights-of-way. 
(Estimated resultant addlitional cost to United States. $3.50O0.000J. 
Authorized to be appropriated an additional $2.;4).00) for None 
prosecution of projects approved in above flood control acts. 
33-19 
None 
None 
None 
None 
None 
None 
None 
None 
H. Doc. 164. 86th Cong.. 
1st sess. 
.July 24. 1946 
May 17. 1954) 
Sep.. 1954 
.July 3. 1958 
.July 14. 1960 
Oct. 23. 1962 
l)ec. 30. 1963 
June 18, 1965 
16. .July 14. 196()

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 33-B (Cont'd) AUTHORIZING LEGISLATION 
See I)ate of 
Section in Authorizing 
Text Act Project and Work Authorized Documents 
Dec. 22, 1944 Authorized to be appropriated an additional $10 million H. Doc. 534, 78th Cong., 
for prosecution of projects adopted in above-mentioned 2d sess.' 
flood control acts, including projects on Lytle and Cajon 
Creeks for local flood protection at San Bernardino and 
Colton, CA. 
.July 3, 1958 Authorized to be appropriated an additional $8 million None 
for prosecution of projects approved in abovementioned 
flood control acts. 
SANTA MARIA VALLEY LEVEES, SANTA MARIA 
RIVER BASIN, CA 
20. Sep. 3, 1954 Levee and channel improvements. H. Doc. 400, 83d Cong., 
2d sess. 
SANTA PAULA CREEK CHANNEL AND DEBRIS 
BASINS (INCLUDING MUD CREEK), SANTA 
CLARA RIVER BASIN, CA 
21. June 30, 1948 Channel improvement. H. Doc 443, 80th Cong., 
1st sess. 
SESPE CREEK AT FILLMORE, VENTURA 
COUNTY, CA 
22. Aug. 11, 19802 Levee, rock groins, floodgates, bridge span. and None 
floodproofed homes. 
SWEETWATER RIVER, SWEETWATER RIVER 
BASIN, CA 
23. Aug. 13, 1968 Channel improvement, as part of a combined flood H. Doc. 148, 90th Cong., 
control and highway project. 1st sess. 
1. (ontains latest published map. 
2. I)ate approved by Chief of Engineers under provisions 
of section 205, Public Law 80-858, as amended. 
33-20

LOS ANGELES, CA, DISTRICT 
TABLE 33-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to Sep. 30, 1983 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Dana Point Harbor, CA Completed 1972 $4.737.550' $74.769~ 
Marina del Rey. Los Angeles 
County, CA Completed 1981 4.238.752 1.323.037' 
Morro Bay Harbor, CA Completed 1980 2.612.093 5.016,370 
Newport Bay Harbor. CA Inactive 1982 796.897 579.15 
Port San Luis. CA Completed & 1977 1.137.759 . 292.369' 
Active (mod) 
Redondo Beach Harbor 
(King Harbor), CA Completed 1982 4.766.898" 1.026,.094' 
San Diego Harbor. CA Completed 1980 28.092.199 1.543.55014 
1. Excludes $4,777,000 required contributed funds and 
Coast Guard costs. 
2. Includes $40,396 for reconnaissance and condition 
surveys. Includes $34,373 expended in FY 1983. 
3. Excludes $4.238,752 required contributed funds: 
$1,843,146 other contributed funds: and Coast Guard costs. 
4. Includes $76,282 for reconnaissance and condition 
surveys. Excludes $114,000 required contributed funds. 
5. Navy funds. Excludes $2.128,411 for rehabilitation. 
6. Includes $263,024 for reconnaissance and condition 
surveys since F Y 1958 and $307,945 Navy funds. Excludes 
$124,578 other contributed funds. Includes $58,794 expended 
in FY 1983. 
7. Public Works Administration funds. Excludes $796,897 
required contributed funds and $1,100 preauthorization costs. 
8. Includes $95,479 for reconnaissance and condition 
survey costs since FY 1958. Excludes 7,000 other contributed 
funds. Includes $2,000 expended in FY 1983. 
9. Includes $568,417 for new work prior to modification 
by 1965 River and Harbor Act. Excludes Coast Guard costs. 
10. Includes $54,715 for maintenance for project prior to 
modification by 1965 River and Harbor Act and $18,958 for 
reconnaissance and condition surveys. Includes $218,696 
expended in FY 1983. 
11. Excludes Coast Guard costs. 
12. Includes $20,517 for reconnaissance and condition 
survey costs since FY 1958. Includes $61,699 expended in FY 
1983. 
13. Includes $154,704 for new work for previous projects: 
$86.352 public works funds: and $1.226.793 emergency relief 
funds. Excludes $254.795 Navy funds for dredging entrance 
channel in FY 1961 to depth of -42 feet mean lower low water 
or 2 feet below project depth): $715,215 required contributed 
funds: $1,900,063 other contributed funds, including $4,441 
for betterments desired by local interests prior to modification 
by 1968 River and Harbor Act: and Coast Guard costs. 
Includes $423 expended in FY 1983. 
14. Includes $59,904 for maintenance for previous projects 
and $146,289 for reconnaissance and condition surveys since 
FY 1958. In addition, includes $144 for retroactive pay 
increase, as reported in 1958 Annual Report. page 1430. 
Includes $9,724 expended in FY 1983. 
33-21

TABLE 33-D 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
OTHER AUTHORIZED BEACH EROSION 
CONTROL PROJECTS 
For Last Cost to Sep. 30, 1983 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Anaheim Bay Harbor, 
Orange County, CA' Completed 1967 $89,119- 
Bird Rock area, La Jolla, 
San Diego County, CA2 Completed 1967 25,881: - 
Coast of California, Point Mugu 
to San Pedro breakwater, CA Completed 1972 1,253,594a - 
Doheny Beach State Park (Doheny 
State Beach), CA Completed 1968 578,717 - 
Las Tunas Beach, San Diego 
County, CA Active 1976 107,484 
Ocean Beach, San Diego 
County, CA Completed 1960 7,912- 
Oceanside, San Diego County, CA Completed 1982 4,350,5477 
San Diego (Sunset Cliffs), CA Active 1979 365,000 
Ventura-Pierpont area, CA Completed (part) 1969 715,819" 
& Deferred (part) 
1. The project authorized by the Act of Congress of 
October 23, 1962, H. Doc. 602, 87th Cong., 2d sess., in lieu of 
part of the original Anaheim Bay Harbor project is covered 
under San Gabriel River to Newport Bay (Surfside-Sunset 
and Newport Beach), Orange County, CA. 
2. Authorized by Chief of Engineers under authority of 
section 103, Public Law 87-874. 
3. Excludes $75,614 required contributed funds. 
4. Excludes $1.238.418 required contributed funds. 
5. Excludes $431,260 required contributed funds. 
6. Plant in service. 
7. Excludes $604,817 other contributed funds. Includes 
$13,515 expended in FY 1983. 
8. Excludes $180,438 required contributed funds. 
9. Excludes $117,406 other contributed funds for beachnourishment 
betterments and $618,949 required contributed 
funds. 
33-22

LOS ANGELES, CA. I)ISTRICT 
TABLE 33-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to Sep. 30. 1988 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
City Creek levee. San Bernardino 
County. CA' 
Gila River Basin, AZ: 
Camelsback Dam (Gila River) 
Gila and Salt Rivers levee and 
channel improvements 
Lower Gila River levee and channel 
improvements (Gila River and 
tributaries downstream from 
Painted Rock Dam) 
Middle Gila River channel 
improvements, upper end of 
Safford Valley to Buttes damsite 
(Camelsback damsite to 
Salt River) 
Pinal Creek channel improvements 
(Globe) 
Santa Rosa Wash (Tat 
Momolikot Dam and 
Lake St. Clair) 
Tucson diversion channel 
Goleta, CA, and vicinity 
Holbrook levee, Little Colorado 
River, Colorado River Basin, AZ 
Lytle and Warm Creeks, Santa Ana 
River Basin, CA 
Needles, San Bernardino County, 
CA' 
Oro Grande Wash channel improvements, 
Mojave River Basin. CA' 
Quail Wash levee, Joshua Tree, San 
Bernardino County, CA' 
Ridgecrest, Kern County, CA' 
Rose Creek channel improvements, 
San Diego, CA' 
San Diego River (Mission Valley), 
San Diego River Basin, CA 
San Luis Rey River, San 
Luis Rey River Basin, CA 
Santa Ana River Basin, CA: 
Devil, East Twin, and Warm 
Creeks channel improvements 
and Lytle Creek levee 
Mill Creek levees 
Riverside levees 
Santa Ana River Basin (and Orange 
County), CA: 
Aliso Creek Dam 
San Juan Dam 
Trabuco Dam 
Santa Clara River levee improvement, 
Santa Clara River 
Basin, CA 
Tijuana River Basin, CA 
University Wash and Spring Brook. 
Riverside, CA 
Ventura River Basin, CA: 
Stewart Canyon debris basin and 
channel 
Ventura River levee 
Completed 
Deferred 
Active(part) 
& Deferred (part) 
Inactive 
Active 
Deferred 
Completed 
Completed 
Active 
Completed 
Completed 
Completed 
Completed 
Completed 
Terminated 
Completed 
Inactive 
Active 
Completed 
Completed 
Completed 
Inactive 
Inactive 
Inactive 
Completed 
Completed 
Inactive 
Completed 
Completed 
$4OO,000 
1963 
1966 
1975 
1970 
1968 
1982 
1982 
1982 
1950 
1981 
1973 
1970 
1973 
1972 
1978 
1982 
1962 
1961 
1959 
1950 
1961 
1979 
1975 
1964 
1950 
73.201: 
2.413.051 
402.867 
121.509' 
10.218.640 
6.103.0794 
499.946 
335.000 
35.022.278k 
1.000.000 
1.000,000; 
212.745 
195.194 
982.432" 
1,708.437 
1.364.000 
7.753.937' 
617.890'" 
2,104,478 
67.361 
2.126,672 
1,703.031" 
213.313 
989,908"2 
1.349,638 1 
33-23

REPORT OF THE CHIEF OOFF ENGINEERS U.S. ARMY 1983 
TABLE 33-E (Cont'd) 
OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to Sep. 30, 1983 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Whitewater River Basin. CA: 
Banning levee-San Gorgonio 
River. Riverside County' Completed 1966 97,868 - 
Chino Canyon improvements. 
Palm Springs' Completed 1973 819,878" - 
Tahchevah Creek detention basin 
and channel improvements Completed 1967 1,420.552'- 
Tahquitz Creek Inactive 1974 1,063,600 - 
Winslow (tributaries of Little 
Colorado River), Little Colorado 
River Basin. AZ Completed (part) 1973 1,831,300- 
& Deferred (part) 
1. Authorized by Chief of Engineers under authority of 8. Excludes $251,000 required contributed funds and 
section 205, Public Law 80-858, as amended. $154,733 other contributed funds. 
2. Excludes $371.058 other contributed funds. 9. Excludes $200,000 required contributed funds and 
3. Advance planning only. $1.641.668 other contributed funds. 
4. Excludes $394,364 other contributed funds. Includes 10. Excludes $35.830 other contributed funds. 
$33 8.454 Code 710 funds since FY 1977. 11. International Boundary and Water Commission funds. 
;. Excludes $5,457,642other contributed funds. Includes 12. Excludes $179,148 other contributed funds. 
-$21,026 expended in FY 1983. 13. Includes $6,000 Code 710 funds since FY 1977. Excludes 
6. Excludes $619,912 required contributed funds and $17,006 other contributed funds. 
$91,176. 0E oxtchluedr ecso ntributed funds. 14. Excludes $8,718 required contributed funds and $53,470 $514.806 required contributed funds and other contributed funds. 
$176,295 other contributed funds. 15. Excludes $74,718 required contributed funds. 
TABLE 33-G DEAUTHORIZED PROJECTS 
For Last 
Full Report Date Federal Contributed 
See Annual and Funds Funds 
Project Report For Authority Expended Expended 
Iodges )am. San Dieguito 
River Basin. CA 1958 1978 - - 
Sec. 12, Public 
Law 93-251 
Las Vegas Wash tributaries, 
Colorado River Basin, NV 1964 1977 $295,191 - 
Sec. 12, Public 
Law 93-251 
Villa Park I)am, Santa Ana 
River Basin (and Orange 
County). CA 1978 
Sec. 12, Public 
Law 93-251 
33-24

LOS ANGELES, CA, DISTRICT 
TABLE 33-H RECONNAISSANCE AND CONDITION SURVEYS 
(See Section 8 of Text) 
Project 
Date 
Marina del Rey, Los Angeles County, CA August 1983 
Morro Bay Harbor, CA May 1983 
Newport Bay Harbor, CA October 1982 
Port San Luis, CA May 1983 
San Diego Harbor, CA September 1983 
TABLE 33-I LOS ANGELES COUNTY DRAINAGE AREA CA: 
LATEST APPROVED ESTIMATED FIRST COSTS FOR ALL UNITS 
OF IMPROVEMENT UNDER EXISTING PROJECT 
(See Section 15 of Text)
Latest Approved Estimated Cost 1976' 
Project Units Federal Local2 Total 
UNITS IN $70 MILLION PROJECT 
Los Angeles River Basin: 
Compton Creek. Los Angeles River to Hooper Ave. storm drain $2,510,5 ) - $2.510,50N) 
Haines Canyon 524,00(X) - 524,M) 
Hansen Dam 11,343,0(X) - 11,343,0(0 
Los Angeles River channel: 
Lankershim Blvd. to Steward and Gray Rd. 40,807.300) - 40.807,34) 
Los Angeles River channel. Long Beach Blvd. 34.200 - 34.20) 
Sepulveda Dam 6.657,00(() - 6.657.(0) 
Sycamore Wash 24.0(4K) - 24.,1) 
Verdugo Wash. Concord St. to upper Canada bridge 1,087,00) - 1.087,.1) 
San Gabriel River Basin: 
San Gabriel River channel: 
San Gabriel Canyon to Santa Fe Dam 810,8X) - 810,80) 
Approach channel to Santa Fe Dam (remedial work) 951.9(00) - 951,.94) 
Santa Fe Dam to Walnut Creek 32,30X) - 32,3M) 
Santa Fe Dam 12,647,000 - 12,647,00) 
Rio Hondo Basin: 
Alhambra Wash 1,109,000 - 1,109,000 
Ballona Creek Basin: 
Ballona Creek channel and jetties Subtotal 1,280,000) - 1,280,0() 79,818,04) - 79.818.(x) 
UNITS OUTSIDE $70 MILLION PROJECT 
Los Angeles River Basin: 
Blanchard Canyon 682,0(X) $476,(M) 1,158,(#) Blue Gum Canyon 533,000 233,000 766,040 
Burbank-Eastern system 7,149,000 1,850,00)) 8,999,040) 
Burbank-Western system (lower) 1,279,000 268,00) 1,547,4X) Burbank-Western system (upper) 4,930,004) 2,959000 7,889,0() 
Caballero Creek 1.484.200 493,MM) 1.977,2(K) 
Compton Creek: 
Los Angeles River to Hooper Ave. storm drain 149,() - 149,() 
Hooper Ave. storm drain to Main St. 1.052.00) 457.(M) 1.509.KM) Dead Horse Canyon and Royal Blvd. channel 664.() 316.4K) 980,00) 
Lopez Canyon diversion 743.54) 665.KM) 1.408.-&#K Lopez Dam 729.00) - 729.MM) 
Los Angeles River channel: 
Owensmouth Ave. to Lankershim Blvd. 8.135.8) 4.247.KM) 12.382.8M) 
Lankershim Blvd. to Stewart and G(;ray Rd. 9.202.100 - 9.202.14; 
Steward and G(;ra Rd. to Santa Ana Branch. Pacific 
Electric railway bridge 5.860.900 81.04M 5.941 .!0 
33-25

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
LOS ANGELES COUNTY DRAINAGE AREA CA: 
LATEST APPROVED ESTIMATED FIRST COSTS FOR ALL UNITS 
OF IMPROVEMENT UNDER EXISTING PROJECT 
TABLE 33-I (Cont'd) (See Section 15 of Text)
iLatest Approved Estimated Cost 1976' 
Project Units Federal LocalP Total 
Santa Ana Branch. Pacific Electric railway bridge to 
PI'acific Ocean 
'Patima Wash channel 
Tujunga Wash channel 
'erdlugo Wash. upper Canada bridge to debris basin 
Wilson Canyon and Mansfield St. channel 
Winery ('anyon 
San (alhriel River Basin: 
('Coyote ('reek (including North Fork) 
Emerald Wash andl Live Oak Wash 
Marshall ('reek 
San (;abriel River channel: 
Santa Fe DI)am to Whittier Narrows Dam 
Whittier Narrows DI)am to Pacific Ocean 
Thompson ('reek and San .Jose Wash (including San .Jose ('reek) 
Walnut ('reek inlet channel 
Walnut ('reek system 
Whittier Narrows Darn 
Rio IlIondo Basin: 
A read ia W%'ash system 
Eaton Wash 
Rio londlo channel: 
Peck Rd. to Rosemead Blvd. (upper) 
Whittier Narrows D)amn to Los Angeles River (lower) 
Rubio ('anyon (liversion 
Santa Anita Wash 
Sawpit Wash 
Sierra Madre Villa channel 
Sierra Madre Wash 
Iallona ('reek Basin: 
lall ona ('reek channel 
lene lijet ('anyon system 
('ent inela ('reek 
Sawtelle-Westwxood system (including Sepulveda channel) 
Subtotal 
(;ranl total for comprehensive plan 
32.612.,(M) 
3.178.10() 
7.322.90() 
635.0(x) 
3.917.500) 
413.0(M) 
18.802.3(M) 
1.658.6M) 
2.577.9(x0 
5.748.80) 
20.887.2(M) 
21.274.600) 
2.879.(MM) 
17.232.6M) 
32.254.000) 
5.236.800M) 
4.225.10) 
4.412.(hM) 
8.165.0)0 
1.066.40(M) 
3.045.700) 
2.348.6M) 
781.40) 
1.732.0 ) 
746.681() 
15.284.9(M) 
4.083.800 
9.620.7M) 
274.736.0(M) 
354.554.000 
9.173.000 
1.306.000 
2.557.000 
363.000 
857.000 
265.00()0 
8.426.00() 
1.182.0()00 
968.00() 
1.797.0(M) 
3.108.000) 
6.095,() 
1.091.(00) 
8.715.00() 
38.000 
1.893.0)0 
1.194.(M) 
550.(M) 
2.565.(00) 
254.000() 
434.00() 
745.004) 
366.000 
248.() 
3.785.(M) 
4.788.(H) 
1.492.0() 
76.30).000 
41.785.000 
4.484,100 
9.879.900 
998,000 
4.774,500 
678,000 
27.228.300 
2.840,600 
3.545.900 
7.545.800 
23.995.200 
27.369.600 
3.970.000 
25.947.600 
32.292.000 
7.129.800 
5.419.100 
4.962.000 
10.730.()0 
1.320.400 
3.479.700 
3.093.600 
1.147.400 
1.980.00 
746.600 
19.069.900 
8.871.8(M) 
11.112.700 
351.036.000 
76.300.000 430.854.000 
I. Excludes estimated cost for Code 710 funds and 
estimatedt cost for minor rehabilitation. 
2. Approved by ls Angeles County Flood Control District 
as of September :10. 1976. except for Walnut Creek system 
channel estimate, which was increased by $42.000 to permit 
rounding of overall non-Federal estimate to three significant 
figures.

LOS ANGELES, CA, DISTRICT 
TABLE 33-J SANTA ANA RIVER BASIN 
(AND ORANGE COUNTY), CA: 
LATEST APPROVED ESTIMATED FEDERAL FIRST COST 
FOR ALL UNITS 
(See Section 19 of Text) 
Estimated Cost 
Project Total Latest Revision Date 
ACTIVE UNIT' 
Completed: 
Brea Dam $1,189,0682: 
Fullerton Dam 411,076 
Lytle and Cajon Creeks channel improvements 7,612,000 : 
Prado Dam 9,473,2732: 
San Antonio and Chino Creeks channel 10,924,170 
San Antonio Dam 7,001.1764 : 
Completed Except for Minor Completion Items: 
Carbon Canyon Dam and channel 5,150,0002 1961 
INACTIVE UNITS* 
Aliso Creek Dam 340.000 1954 
San Juan Dam 5,960,000 1954 
Trabuco Dam 2,190,000 1954 
DEAUTHORIZED UNITE 
Villa Park Dam 2,270,000 1954 
1. For details, see section 19 of text. 4. Includes $5,000 working funds. 
2. Not including estimated cost of Code 710 funds. 5. For additional information, see "Other Authorized 
3. Plant in service. Flood Control Projects." 
FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION 
Flood Control Activities Pursuant to Section 205, Public Law 80-858, 
As Amended (Preauthorization) 
TABLE 33-K (See Section 26 of Text) 
Project FIscal Year Costs 
Los Coches Creek, San Diego County, CA $154,571 
Newhall Creek, Newhall, CA 187,057 
South Fork of the Santa Clara River, Santa 
Clarita Valley, CA 14,970 
Telegraph Canyon Creek, Chula Vista, CA 87,250 
West Magnesia Canyon channel, Rancho Mirage, CA 16.223 
33-27

SAN FRANCISCO, CA, DISTRICT* 
This district comprises the Klamath River Basin in 
southern Oregon and portions of northern and western 
California consisting of drainage basins tributary to the 
Pacific Ocean from the Oregon-California State line on 
the north to Cape San Martin, CA, on the south, except 
for basins tributary to the San Francisco Bay system 
which lie east of the Benicia-Martinez Bridge. 
IMPROVEMENTS 
Navigation Page 
1. Crescent City Harbor, CA ............... 34-1 
2. San Francisco Bay to Stockton, CA 
(John F. Baldwin and Stockton 
Ship Channels).......................... 34-2 
3. San Francisco Bay and 
Delta Model, CA ........................ 34-2 
4. Reconnaissance and Condition Surveys .... 34-3 
5. Navigation Work under Special 
Authorization........................... 34-3 
Flood Control 
6. Russian River Basin, CA ................ 34-3 
7. Inspection of Completed Flood 
Control Projects......................... 34-4 
8. Flood Control Work under Special 
Authorization........................... 34-4 
General Investigations 
9. Surveys ................................ 34-4 
General Investigations (Cont'd) Page 
10. Collection and Study of Basic Data ........ 34-4 
11. Continuation of Planning 
and Engineering .......................... 34-4 
12. Advance Engineering and Design........ 34-4 
Tables 
Table 34-A 
Table 34-B 
Table 34-C 
Table 34-D 
Table 34-E 
Table 34-F 
Table 34-G 
Cost and Financial 
Statement .................... 34-6 
Authorizing 
Legislation.................... 34-9 
Other Authorized 
Navigation Projects ........... 34-10 
Other Authorized 
Beach Erosion 
Control Projects ............... 34-10 
Not Applicable 
Not Applicable 
Deauthorized Projects ......... 34-11 
Navigation 
1. CRESCENT CITY HARBOR, CA 
Location. Harbor is 17 miles south of Oregon State 
line, 125 miles south of Coos Bay, OR, 70 miles north of 
Humboldt Bay, CA, and midway between San Francisco 
Bay and mouth of Columbia River. (See Coast and 
Geodetic Survey Chart 5895.) 
Existing project. A rubblemound outer breakwater 
extending about 3,700 feet on a bearing of S.27 degrees 
E.; from Battery Point, thence about 1,000 feet on a 
bearing of S. 80 degrees E.; for maintenance dredging 
of an outer harbor basin 1,800 feet long and 1,400 feet 
wide to 20 foot depth at mean lower low water, except in 
rock; a rubblemound sand barrier from Whaler Island 
to easterly shore and maintenance dredging at seaward 
end of sand barrier; an inner breakwater extending 
northwesterly about 1,200 feet from Whaler Island, 
thence westerly 400 feet to form a protected fish-boat 
harbor; for removal of pinnacle rock in fish-boat harbor 
to 20-foot depth; and a T-shaped inner harbor basin 20 
feet deep, 1,500 feet long extending along north side of 
Citizen's Dock for 325 feet, with a stem 1,000 feet long. 
Deepening of the harbor adjacent to Citizen's Dock was 
found to be not economically feasible, and this portion 
was reclassified to the "inactive" category. Approved 
estimated cost for new work (1983) is $4,565,000, of 
which $4,411,000 is Federal cost (includes $11,000 
Coast Guard costs) and $154,000 is non-Federal cost 
(includes $54,000 cash contribution). 
Local cooperation. Fully complied with for completed 
modifications and acts of 1927, 1937, 1945, and 1965 
portion for construction of 400-foot extension of the 
inner breakwater. The Board of Harbor Commissioners, 
by its Resolution No. 77-10, dated September 6, 1977, 
reaffirmed its intention to meet the requirements of 
local cooperation. A notification was received by letter 
from the President of the Board, dated February 10, 
34-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
1978, stating that the area serving the Citizen's Dock 
should not be included at this time. By Board of Harbor 
Commissioners letter dated February 10, 1978, local 
interests reaffirmed support for dredging in the vicinity 
of the oil dock. Rights-of-way are publicly owned and 
available for public use. Resolution No. 81-1 of March 17, 
1981 gives assurance that the Harbor District will 
provide a cash contribution of $54,000 in lieu of providing 
land disposal sites. An agreement in conformance with 
the requirements of Section 221, Flood Control Act of 
1970, Public Law 91-611, was obtained from the local 
sponsor in April 1982. 
Terminal facilities. Three piers, one of which is publicly 
owned and from which boats are fueled; one oil terminal; 
and a private mooring for barges discharging petroleum 
products to pipelines on inner breakwater. Facilities 
are considered adequate for existing commerce. 
Operations during fiscal year. New Work: A contract 
to dredge the channel at the oil dock to a depth of 
20 feet was continued during the months of August- 
September 1983. Total bid price including additive 
reach is $789,000. The channel has now been spudded 
and dredged to the authorized -20 feet MLLW (mean 
lower low water) depth. Maintenance: Dredging by 
contract removed 76,000 cubic yards of rock and sediment. 
Historical summary. Project is completed including 
deepening and enlarging the inner harbor basin adjacent 
to Petroleum Dock to a depth of 20 feet and deepening of 
the harbor adjacent to Citizen's Dock which was found 
to be not economically justified and reclassified to the 
"inactive" category in 1978. The 3,000-foot outer breakwater 
was completed in 1930, sand barrier in 1939, 
inner breakwater in 1946, removal of pinnacle rock in 
1951, and outer breakwater extension in 1957. Major 
rehabilitation of outer breakwater was completed in 
1964 and again in 1980. The 400-foot extension of inner 
breakwater was completed in 1973. 
2. SAN FRANCISCO BAY TO 
STOCKTON, CA (JOHN F. 
BALDWIN AND STOCKTON 
SHIP CHANNELS) 
Location. On navigation channels extending from 
entrance to San Francisco Bay to vicinity of Concord 
through San Francisco, Marin, Contra Costa, and 
Solano Counties. (See Coast and Geodetic Charts 5527 
and 5532-5534 for respective areas.) 
Existing project. Project provides for modification 
of existing San Francisco Harbor, Richmond Harbor, 
San Pablo Bay and Mare Island Strait, Suisun Bay 
Channel to vicinity of Concord and Navigation projects 
to provide depths of 55 feet for San Francisco Bar 
Channel (completed), 45 feet (currently 35 feet) for 
main internal bay channels upstream to vicinity of 
Concord; enlargement and deepening to 45 feet (currently 
35 feet) of maneuvering areas adjacent to major 
petroleum refinery terminals along channel route; 
widening Suisun Bay Channel. San Francisco Harbor 
Main Channel was completed February 1974. Approved 
cost estimate (1983) of Federal cost (Corps), see Sacramento 
District Annual Report. Existing project was 
adopted by 1965 River and Harbor Act (H. Doc. 208, 
89th Cong., 1st sess., contains latest published map). 
Local cooperation. See Sacramento District Annual 
Report. The local sponsor, Contra Costa County, supports 
the project. 
Terminal facilities. See Port Series No. 30, revised 
1983, No. 31, revised 1982, and No. 32, revised 1975, 
titled respectively: "The Ports of San Francisco, Redwood 
City, and Humboldt Bay, Calif."; "The Ports of Oakland, 
Alameda, Richmond, and Ports on Carquinez Strait, 
Calif."; and "The Ports of Sacramento, Stockton, Pittsburg, 
and Antioch, Calif." Facilities are considered 
adequate for existing commerce and will be adequate 
for future commerce upon completion of new terminal 
facilities. 
Operations during fiscal year. New work: Continued 
planning activities. 
3. SAN FRANCISCO BAY AND 
DELTA MODEL, CA 
Location. The model, including a regional visitor 
center, is located in Sausalito, CA, adjacent to San 
Francisco Bay about two miles north of the Golden Gate 
Bridge. 
Existing project. The San Francisco Bay/Delta 
Model, which covers 17 miles of the Pacific Ocean 
beyond Golden Gate, all of San Francisco Bay proper, 
San Pablo Bay, Suisun Bay, and all of the Sacramento- 
San Joaquin Delta east of Suisun Bay to the cities of 
Sacramento on the northeast and Stockton and Tracy on 
the south, was constructed in a rehabilitated warehouse 
at Sausalito, CA, as a part of the San Francisco Bay and 
Tributaries, California, Study authorized by the River 
and Harbor Act of May 17, 1950 (PL 81-516, Section 
110). The model was authorized as an operation and 
maintenance project in the Water Resources Development 
Act of 1974 (PL 93-251, Section 8). The model 
successfully reproduces to the proper scale the rise and 
fall of the tide, flow and currents of water, salinity 
intrusion, and trends in disposition of sediments. It is a 
useful tool to examine forces existing in the bay and 
estuarine system and to predict results of proposed 
changes. 
Local cooperation. None required. 
Operations during fiscal year. Maintenance: Operation 
and maintenance of the model continued. The data 
collection system was computerized in February 1983. 
Extensive tests were run to verify model repeatability. 
Tests were also conducted for FEMA to evaluate 
salinity changes associated with delta levee failures. 
Historical summary. Original model construction 
was initiated 1956 and completed 1957. The addition of 
the Sacramento-San Joaquin Delta to the original 
model was initiated 1966 and completed 1969. The 
34-2

SAN FRANCISCO, CALIFORNIA, DISTRICT 
central exhibits were completed in December 1981. 
Continued testing of proposals affecting the environmental 
quality of the region including, but not limited 
to: salinity intrusion, dispersion of pollutants, water 
quality, improvements for navigation, dredging, bay 
fill, physical structures, other shoreline changes. Total 
cost of regional visitor exhibits and model as of September 
30, 1983, was $9,145,319, of which $4,094,142 was 
for the regional visitor center, $744,888 for exhibits, 
and $4,306,289 for maintenance. 
4. RECONNAISSANCE AND 
CONDITION SURVEYS 
Reconnaissance and condition surveys of channels to 
be dredged in years other than FY 83 were conducted 
on two projects, Bodega Bay, CA, and San Leandro 
Marina, CA. 
5. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation activities pursuant to section 107, Public 
Law 86-645 (preauthorization). 
Fiscal year costs for preauthorization studies were 
$68,567, of which $5,619 was for Pillar Point Marina, 
San Mateo County, CA, and $62,948 for South Beach 
Small Boat Harbor, San Francisco, San Francisco 
County, CA. 
Flood Control 
6. RUSSIAN RIVER BASIN, CA 
Location. Russian River rises in Coast Range in 
northwestern California, flows southerly for 87 miles, 
and then turns westerly to flow for 23 miles to Pacific 
Ocean at Jenner, 60 miles northwest of San Francisco, 
CA. (For general location see Geological Survey map 
for California.) 
Existing project. Active authorized project provides 
for construction of a dam on East Fork of Russian River 
at Coyote Valley to a height of 160 feet; a dam on Dry 
Creek at Warm Springs to a height of 319 feet; and 
channel stabilization works on Russian River between 
mouth and mile 98, on lower reaches of several tributaries, 
and on Dry Creek downstream from dam. Coyote 
Valley Dam (Lake Mendocino), completed in 1959, is 
operated and maintained by the United States. (See 
tables 34-H and 34-I for latest approved estimated 
costs.) 
Local cooperation. Fully complied with for Coyote 
Valley Dam and channel improvements accomplished 
to date. For the Dry Creek portion, local interests are 
required by the authorizing act to comply with the 
usual a., b., c. requirements for channel improvements 
and, in addition, prevent any encroachment in the 
channel of Dry Creek which would interfere with 
proper functioning of the channel improvement works; 
adjust all claims concerning water rights arising from 
the construction and operation of the improvements, 
including acquisition of water rights needed for preservation 
of fish and wildlife resources affected by the 
project; and reimburse the United States in accordance 
with the Water Supply Act of 1958, as amended, for that 
part of the construction cost, (27.8% of total construction 
cost, currently estimated at $93,220,000) and the annual 
operation, maintenance and replacement costs allocated 
to municipal and industrial water supply, tentatively 
estimated at $308,000. The estimated annual cost to 
local interests for maintenance of channel improvement 
works is $70,000. Sonoma County Water Agency (formerly 
Sonoma County Flood Control and Water Conservation 
District) provided assurances of willingness and 
ability to meet requirements by Resolutions No. DR 
00793-1, September 25,1961, No. DR 4770-1, December 
17, 1962, and No. DR 45759, August 5, 1974, for Dry 
Creek (Warm Springs) Lake and Channel. By letter 
dated March 7, 1967, Sonoma County Flood Control and 
Water Conservation District further indicated their 
interest in optimization of the Dry Creek (Warm Springs) 
damsite to provide additional water supply storage. 
Reimbursement to the United States for Dry Creek 
(Warm Springs) Lake and Channel costs allocated to 
212,000 acre-feet of water supply storage is specified in 
a water supply contract with the local sponsor approved 
in October 1982. 
Operations during fiscal year. New work: Planning 
is underway for the relocation of Hot Springs Road, the 
boat launching ramp, which will be inundated by the 
reservoir, inclusion of incidental hydropower facilities 
within the control structure, determining effects of the 
reservoir upon the riparian habitat and the possible 
impacts of mitigation downstream from the damsite, 
implementing the vegetation management program, 
planning for minimum Federal recreation facilities, 
and initiating upgrade of Rockpile Road. Contract for 
construction of the Warm Springs Dam and appurtenances 
awarded May 1978, is 98 percent complete. 
Maintenance: Operation and maintenance continued on 
Dry Creek (Warm Springs) Lake and Channel and 
Coyote Valley Dam and in April 1982 responsibility was 
transferred to the Sacramento District. 
Historical summary. Entire project, exclusive of 
recreation facilities at completed project (Lake Mendocino), 
is about 85 percent complete. Coyote Valley Dam, 
initiated November 1958, was completed April 1959 
(cost $17,550,000, of which $11,952,000 was Federal; 
and $5,598,000 contributed). Work, including removal 
of slides resulting from storms in 1958, was completed 
April 1959. Bank stabilization work on Russian River 
near Geyserville was completed in 1957 and channel 
improvements in remaining reaches on Russian River 
and East Fork of Russian River were completed in 1974 
(cost $2,483,900). Warm Springs construction completions 
include fish hatchery in December 1980, reservoir 
clearing in July 1981, project overlook in May 1981, 
downstream stabilization sills in October 1981, and 
dam closure in October 1982. Work remaining includes 
monitoring of initial reservoir filling of Dry Creek 
34-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
(Warm Springs) Lake and Channel and additional 
channel improvements on Dry Creek. Responsibility for 
construction was transferred to Sacramento District in 
August 1983. 
7. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Section 3, Flood Control Act of June 22, 1936, as 
amended and supplemented, included requirement that 
local interests maintain and operate completed flood 
control works in accordance with regulations prescribed 
by the Secretary of War. Inspections made throughout 
the year to determine effectiveness of operation and 
maintenance by local interests of completed local protection 
projects and works constructed under emergency 
and special authorities of Sections 205 and 208 of the 
1948 Flood Control Act, Section 14 of the 1946 Flood 
Control Act, and Public Law 99, 84th Congress. Fiscal 
year cost was $85,475. Total cost to September 30, 1983 
was $629,155. Projects inspected included Alameda 
Creek, March 1983; Butte Creek, July 1983; Canyon 
Creek, July 1983; Coffee Creek, July 1983; Corte 
Madera Creek, April 1983; Coyote Creek, April 1983; 
East Weaver Creek, July 1983; Eel River at Sandy 
Prairie, August 1983; Klamath River, July 1983; Mad 
River at Blue Lake, August 1983; Mark West Creek, 
September 1983; Meiss Lake, July 1983; Pajaro River, 
April 1983; Pinole Creek, April 1983; Redwood Creek, 
August 1983; Rheem Creek, April 1983; Rodeo Creek, 
April 1983; Russian River, May and June 1983; San 
Leandro Creek, March 1983; San Lorenzo Creek, March 
1983; San Lorenzo River, April 1983; Santa Rosa Creek, 
September 1983; Schell's Slough, September 1983; 
Smith River, July 1983; and Van Duzen River, August 
1983. 
8. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood Control activities pursuant to Section 205, 
Public Law 858, 80th Congress, as amended (preauthorization). 
Fiscal year costs for preauthorization studies were 
$15,616, of which $1,626 was for City of Yountville, 
Napa County, CA; $6,510 for Mad River, Blue Lake 
County, CA; and $7,480 for Petaluma River, Petaluma, 
CA. 
Emergency flood control activities-repair, flood 
fighting and rescue work (Public Law 99, 84th 
Congress, and antecedent legislation). 
Fiscal year costs of $1,248,307 were incurred for 
emergency flood control activities, of which $268,636 
was for disaster preparedness; $113,801 for emergency 
operations; and $865,870 for rehabilitation. 
Emergency bank protection (Section 14, 1946 
Flood Control Act, Public Law 526, 79th Congress). 
Fiscal year costs were $59,124 for emergency bank 
protection of which $18,890 was for Boronda Road 
Bridge, Carmel River, CA; $18,235 for San Francisquito 
Creek, Site 74, CA; and $21,999 for Schulte Road 
Bridge, Carmel River, CA. 
General Investigations 
9. SURVEYS 
Fiscal year costs for surveys were $1,037,042, of 
which $167,828 was for navigation; $808,322 for flood 
damage prevention; $57,908 for inventory of dams; and 
$2,984 for coordination with other agencies. 
10. COLLECTION AND STUDY OF 
BASIC DATA 
Fiscal year total costs of $27,660 were incurred, of 
which $25,642 was for flood plain management service 
program and $2,018 was for hydrologic studies. 
11. CONTINUATION OF PLANNING 
AND ENGINEERING 
Fiscal year total costs were $379,152 of which $253,873 
was for Fisherman's Wharf, CA and $125,279 was for 
Oakland Outer Harbor (Deepening), CA. 
12. ADVANCE ENGINEERING AND 
DESIGN 
BODEGA BAY, CA 
Bodega Bay is a triangular lagoon on the California 
coast, 85 miles south of Noyo River and 58 miles north of 
San Francisco. In March 1965, the Committee on Public 
Works authorized a modification to the existing project 
and the General Design Memorandum was approved by 
the Office of Chief of Engineers on June 30, 1982. The 
plan of improvement consists of a 19-acre marina 
located at Spud Point on the west side of the harbor and 
protected by a 1,268 foot long baffled concrete pile 
breakwater and an access channel 1,992 feet long, 100 
feet wide and 12 feet deep. Federal construction would 
consist of the access channel and the breakwater. The 
marina would be constructed by local interests and 
would accommodate 238 commercial fishing and recreational 
boats. Advance engineering and design for the 
channel and breakwater is complete. Plans and specifications 
are 95 percent complete. Estimated preconstruction 
planning cost is $585,000. Total costs during the 
fiscal year were $99,249 with General Investigation 
funds. 
NOYO RIVER AND HARBOR, CA 
Noyo River rises in the Coast Range, flows westerly, 
and empties into Noyo Harbor. Noyo Harbor is a cove on 
the California Coast about 87 miles south of Humboldt 
Bay and 135 miles northwest of San Francisco. The 
1962 Rivers and Harbors Act modified by the 1976 
Water Resources Development Act authorized up to 
two breakwaters as necessary to provide protection. 
The 1976 WRDA authorized construction of additional 
channel improvements. Recommended plans of im- 
34-4

SAN FRANCISCO, CALIFORNIA, DISTRICT 
provement for the breakwater and channel improvement 
were previously considered as a single project. Due to 
significant differences in the time required for planning 
and construction, each part is now reported separately. 
The plans of improvement for Noyo River and Harbor 
(Breakwater), CA, provide for a single breakwater 
immediately west of entrance channel in Noyo Harbor 
or for two breakwaters inside of Noyo Cove. Estimated 
preconstruction planning cost is $1,300,000. Total costs 
during the fiscal year were $30,632 with General 
Investigation funds. Planning is about 40 percent cornmplete. 
A physical model has been constructed to test 
alternative plans in FY 1984. 
The plan of improvement for Noyo River and Harbor 
(Channel Extension), CA, provides for a 100-foot wide 
extension channel, 6 feet deep, for a distance of about 
3,000 feet upstream from the end of the Federal project 
existing river channel to the Dolphin Isle Marina. 
Estimated preconstruction planning cost is $450,000. 
Total costs during the fiscal year were $150,500 with 
General Investigation funds. Planning is about 80 
percent complete. 
34-5

TABLE 34-A 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
COST AND FINANCIAL STATEMENT 
See 
Section 
in Text Project 
Bodega Bay, CA 
1. Crescent City 
Harbor, CA 
Humboldt Harbor 
and Bay, CA 
Moss Landing 
Harbor, CA 
Napa River, CA 
Noyo River and 
Harbor, CA 
Oakland Harbor, CA 
Petaluma River, CA 
Redwood City 
Harbor, CA 
Funding 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Minor rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Total Cost to 
FY 80 FY 81 FY 82 FY 83 Sep 30, 1983 
106,000 25,000 
108,674 33,471 
260,000 153,000 
259,627 158,414 
120,000 
113,944 
2,095,000 
2,095,700 
87,223 
202,312 
710,600 
679,111 
5,000 
4,731 
100,000 
138,763 
264,000 
255,228 
129,000 
28,721 
1,070,000 
549,307 
2,117,000 
1,677,366 
1,636,000 2,123,000 
1,653,268 2,098,890 
341,000 
74,622 
- 
256,000 
520,680 
79,500 885,000 100,000 
69,655 293,412 527,787 
240,000 145,000 204,000 
270,930 124,347 123,148 
240,000 246,000 279,000 
239,292 239,864 264,329 
1,206,000 469,000 1,191,000 
1,205,305 439,711 1,185,187 
- 
508,000 
392,086 
358,000 
467,773 
- 
1,560,000 
76,490 
- 1,226,7651 2 
99,249 1,222,0511 3 
- 794,3944 
- 794,3944 
- 397,7795 
- 397,7795 
802,000 9,498,9726 
419,303 8,590,7616 
2,875,300 12,053,9747 
645,408 9,375,6297 
- 525,0008 
- 525,0008 
- 9,847,2999 47 
- 9,847,2999 47 
8,562,200 42,115,8721o 47 
2,683,029 36,192,21510 47 
- 338,21511 47 
- 338,21511 47 
59,000 3,320,63112 47 
47,971 3,307,63612 47 
- 1,021,27413 47 
- 1,021,27413 47 
72,000 1,775,80913 14 47 
240,156 1,770,24713 14 47 
79,000 1,246,48215 16 
181,133 1,235,48515 17 
826,900 4,720,65418 19 
314,635 4,186,69518 19 
- 222,81020 47 
- 222,81020 47 
- 9,646,98421 47 
- 9,646,98421 47 
1,796,000 25,022,273 47 
1,771,880 24,962,252 a7 
- 297,146 47 
- 297,146 47 
670,000 6,930,15924 47 
912,547 5,683,006 47 
- 1,672,72225 47 
- 1,672,72225 47 
34-6

SAN FRANCISCO, CALIFORNIA, DISTRICT 
TABLE 34-A (Cont'd) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 80 FY 81 FY 82 FY 83 Sep 30, 1983 
Richmond Harbor, CA 
2. San Francisco Bay 
to Stockton, CA 
John F. Baldwin and 
tockton Ship 
Channels) 
3. San Francisco Bay 
and Delta Model, CA 
San Francisco 
Harbor, CA 
San Francisco 
Harbor and Bay CA 
(Removal of Drift) 
San Leandro 
Marina, CA 
San Pablo Bay 
and Mare Island 
Strait, CA 
Santa Cruz 
Harbor, CA 
(Federal Funds) 
(Contrib. Funds) 
Suisun Bay Channel, 
CA 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint 
Approp. 
Cost 
Minor rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
20,000 1,199,000 90,000 44,000 4,834,3252 47 
19,717 1,042,130 227,129 61,044 4,831,3452 47 
- - - - 2,886,6952 2 
- - - - 2,886,695 2 
542,000 605,000 2,011,000 1,650,000 12,850,1162 
542,463 601,144 1,987,571 493,783 11,664,8172 
- - - - 164,689 
- - - - 164,689 
410,000 665,000 600,000 432,000 7,342,200 
404,541 434,944 555,315 467,014 7,042,084 
1,685,000 736,000 513,000 1,782,000 9,482,700 
1,965,818 618,490 584,347 1,530,770 9,145,319 
- - - - 2,689,3562 o 
- - - - 2,689,35628 0 
751,000 
750,834 
47,700 2,119,500 1,401,000 18,410,54531 
41,709 1,928,330 1,409,397 18,217,60531 
- 47 
- 47 
1,260,000 1,324,000 1,167,000 1,073,000 
1,257,633 1,257,564 1,101,096 1,075,404 
- - 18,000 - 
- - 17,955 45 
17,885,182' 7 
17,736,8754? 
644,3512 
644,351" 
- - - - 1,369,37228 33 
- - - - 1,369,372 3 
1,015,000 1,132,300 2,923,000 1,465,000 24,951,433k 
1,012,515 1,034,491 2,415,274 1,841,748 24,720,046* 
- - - - 1,852,340 
- - - - 1,852,340 
- - - - 160,000@ 
- - - - 160,000 
530,000 675,000 595,000 742,000 6,987,159 
529,983 503,639 679,855 566,161 6,724,747 
- 36 
- 36 
320,000 297,000 253,000 594,000 2,243,338k 7 
318,963 297,632 61,595 782,935 2,240,428 37 
34-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 34-A (Cont'd) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 80 FY 81 FY 82 FY 83 Sep 30, 1983 
Suisun Channel, CA New Work 
Approp. - - - - 217,6773 
Cost - - - - 217,67738 
Maint. 
Approp. - 51,000 561,000 -32,000 1,335,95739 
Cost - 50,806 434,762 94,431 1,335,95739 
6. Russian River Basin, New Work 
CA Approp. - - - - 14,435,86940 41 
Coyote Valley Dam Cost - - - - 14,435,86940 41 
Lake Mendocino) and Maint. 
Channel Improvements MAaipnpt.rop. 1,744,000 1,829,000 1,246,000 1,518,000 16,845,61642 43 
Cost 1,334,220 2,056,798 1,305,758 1,196,832 16,359,38442 44 
Dry Creek (Warm New Work 
Springs) Lake and Approp. 43,930,000 34,400,000 37,900,000 23,548,000 267,334,64548 49 
Channel Improvements Cost 39,841,016 38,001,042 34,273,493 22,397,207 261,549,69648 50 
CA 
Maint. 
Approp. - 581,000 797,000 1,330,000 2,708,00042 45 
Cost - 552,149 753,145 1,141,392 2,446,68642 46 
1. Includes $641,800 for jetties, bulkheads, main Bodega 
Bay Channel and turning basin completed in 1943. 
2. Includes $585,000 for Preconstruction Planning 
($456,000 Construction, General funds and $129,000 General 
Investigation funds). 
3. Includes $580,249 Preconstruction Planning costs 
($455,563 Construction, General costs and $124,686 General 
Investigation costs). 
4. Includes $83,744 for reconnaissance and condition 
surveys, FY 1956-1983. 
5. Excludes contributed funds of $2,000. 
6. Excludes contributed funds of $271,116 and $2,138 
surplus material from Corps military activities. 
7. Excludes contributed funds of $44,340. Includes $61,031 
for reconnaissance and condition surveys, FY 1956-1983. 
8. Excludes $2,000 contributed funds in lieu of royaltyfree 
rock. 
9. Includes $2,261,371 for previous project. Excludes 
$95,000 contributed funds for existing project. 
10. Includes $98,206 for previous project and $1,641 for 
reconnaissance and condition surveys, FY 1956-1983. 
11. Excludes $5,337 previous project costs. 
12. Excludes $8,539 surplus material from Corps' military 
activities. Includes $43,112 for reconnaissance and condition 
surveys, FY 1956-1983. 
13. Excludes previous project costs. Excludes $154,500 
contributed funds. 
14. Includes $203,684 for reconnaissance and condition 
surveys, FY 1956-1983. 
15. Includes $11,985 for previous project. Excludes $7,180 
contributed funds for previous project. 
16. Includes $948,000 for Preconstruction Planning 
($589,000 for Breakwater of which $500,000 allocated under 
onstruction, General and $89,000 under General Investigations); 
($359,000 for Channel Extension of which $165,000 
allocated under Construction, General and $194,000 under 
General Investigations.) 
17. Includes $937,002 Preconstruction cost ($578,602 for 
Breakwater of which $500,000 was under Construction, 
General and $78,602 under General Investigations); ($358,400 
for Channel Extension of which $165,000 under Construction, 
General and $193,400 under General Investigations.) 
18. Includes $32,097 for previous project and $15,436 for 
reconnaissance and condition surveys, FY 1956-1983. Excludes 
contributed funds of $820 for previous project. 
19. Excludes contributed funds of $4,000 in lieu of providing 
dike disposal areas on existing project. 
20. Excludes contributed funds of $1,700. 
21. Includes $2,899,232 for previous projects. Excludes 
$397,266 contributed funds on existing project. 
22. Includes $684,028 for previous projects and $501 for 
reconnaissance and condition surveys, FY 1956-1983. 
23. Includes $212,083 for previous project. Excludes contributed 
funds of $15,559 for previous project. 
24. Includes $314,692 for previous project and $75,909 for 
reconnaissance and condition surveys, FY 1956-1983. 
25. Includes previous project costs $31,443. Excludes 
$119,572 contributed funds for existing project. 
26. Includes $67,759 for reconnaissance and condition 
surveys, FY 1956-1983. 
27. Excludes contributed funds of $524,778. Includes 
$105,000 Public Works Administration funds. 
28. Excludes modification authorized October 27, 1965, 
under project "San Francisco Bay to Stockton, CA (John F. 
Baldwin and Stockton Ship Channels)." 
29. Excludes $34,800 contributed funds. Includes $3,138 
for reconnaissance and condition surveys, FY 1956-1983. 
30. Includes $1,030,399 for previous projects. Excludes 
$134,591 contributed funds for existing project. 
31. Includes $475,321 for previous projects and $20,319 
for reconnaissance and condition surveys, FY 1956-1983. 
32. Authorized by FC Actof 1965 (Sec. 201); Maintenance 
R&H Act of 1970 (Sec. 103). Includes $24,351 for reconnaissance 
and condition surveys FY 1979-1983. See FY 1977 
Annual Report for last full report. 
33. Includes $1,086,703 for previous projects. 
34. Includes $1,359,380 for previous projects and $904 for 
reconnaissance and condition surveys, FY 1956-1983. 
34-8

SAN FRANCISCO, CALIFORNIA, DISTRICT 
TABLE 34A (Cont'd) COST AND FINANCIAL STATEMENT 
35. Excludes $810,046 contributed funds. 
36. See Sacramento District FY 1974 Annual Report for 
details. 
37. Project maintenance responsibility to Point Edith was 
transferred to San Francisco DistrictJanuary 1,1974. Excludes 
Sacramento District's portion. Includes $8,588 for reconnaissance 
and project condition surveys, FY 1976-1983. 
38. Project maintenance assigned to San Francisco District 
from Sacramento District January 1, 1974. See Sacramento 
District 1972 Annual Report for full report. 
39. Includes $28,448 for reconnaissance and condition 
surveys FY 1978-1983. 
40. Excludes $5,598,000 contributed funds and $400,000 
for recreation facilities at completed projects funded under 
Public Work Acceleration Program. 
TABLE 34-B AUTHORIZING 
41. Excludes $1,628,411 for recreation facilities at completed 
projects funded under Code 711. 
42. Responsibility for maintenance transferred to Sacramento 
District in April 1982. 
43. Excludes $215,400 recreation user fee funds. Includes 
$2,298,484 Sacramento District funds. 
44. Excludes $315,392 recreation user fee costs. Includes 
$1,812,252 Sacramento District costs. 
45. Includes $1,743,886 Sacramento District funds. 
46. Includes $1,482,572 Sacramento District costs. 
47. See FY 1981 Annual Report for last full report. 
48. Responsibility for construction transferred to Sacramento 
District in August 1983. 
49. Includes $13,912,852 Sacramento District funds. 
50. Includes $8,127,903 Sacramento District costs. 
LEGISLATION 
See Date 
Section in Authorizing 
Text Act Project and Work Authorized Documents 
1.CRESCENT CITY HARBOR, CA 
July 18, 1918 Breakwater H. Doc. 434, 64th Cong., 
1st sess. 
Sep. 22, 1922 Conditions of local cooperation modified. Rivers and Harbors 
Committee Doc. 4, 67th 
Cong., 2nd sess. 
Jan. 21, 1927 Extend breakwater to 3,000 feet long. H. Doc. 595, 69th Cong., 
2nd sess. 
Aug. 30, 1935 Dredge harbor basin, 1,800 feet long, 1,400 feet Rivers and Harbors 
wide, and 20 feet deep. Committee Doc. 40, 
74th Cong., 1st sess. 
Aug. 26, 1937 Sand barrier and maintenance dredging in vicinity of S. Commerce Committee 
seaward end thereof. print, 75th Cong., 
1st sess. 
Mar. 2, 1945 Extend breakwater to Round Rock (modified by H. Doc 688, 76th Cong., 
Chief of Engineers). 3rd sess. 
Mar. 2, 1945 Inner breakwater and removal of rock in inner harbor. Report on file in Office, 
Chief of Engineers. 
Oct. 27, 1965 Extend inner breakwater 400 feet and dredge T-shaped H. Doc. 264, 89th Cong.1 
basin 20 feet deep. 
6. RUSSIAN RIVER BASIN, CA 
May 17, 1950 Coyote Valley Dam (Lake Mendocino): Channel H. Doc. 585, 81st Cong., 
improvements on lower 98 miles of Russian River and 2nd sess. 
lower reaches of tributaries. 
Feb. 10, 1956 Increased appropriation authorization for initial stage of Public Law 404, 84th 
project development. Cong., 2nd sess. 
Oct. 23, 1962 Dry Creek (Warm Springs) Lake; Channel Improvements on H. Doc. 547, 87th Cong., 
Dry Creek below dam. 2nd sess. 
Mar. 7, 1974 Dry Creek (Warm Springs) Lake and channel; compensate Sec. 95, 1974 WRDA 
for fish losses on the Russian River which may be 
attributed to the operation of the Coyote Dam 
component of the project through measures such as 
possible expansion of the capacity of the fish 
hatchery at the Warm Springs Dam component of the 
project. 
1. Contains latest published map. 
34-9

TABLE 34-C 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to Sep 30, 1983 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Berkeley Harbor, CA' Completed 1966 155,5502 - 
Berkeley Marina, CA' Completed 1979 505,2014 - 
Halfmoon Bay Harbor, CA Completed 1979 6,697,396E - 
Lower San Francisco Bay, CA Inactive 1935 - - 
Monterey Harbor, CA Inactive 1971 1,108,182 83,0096 
San Francisco Marina (Gas House Cove), 
CA' Completed 1974 180,4727 - 
San Francisco Harbor (Islais Creek), CA' Completed 1976 848,2278 - 
San Leandro Marina (Breakwater), CA' Completed 1976 210,3909 - 
San Rafael Creek, CA Active/ 1981 32,3591t0 1,981,902" 
no FY 83 
expenditure 
1. Authorized by Chief of Engineers (Sec. 107, Public 7. Includes preauthorization costs $26,855 and excludes 
Law 86-645). contributed funds $153,618. 
2. Excludes $155,551 contributed funds. 8. Includes $94,550 preauthorization costs. 
3. Excludes $100,000 contributed funds and $105,000 9. Includes $72,000 preauthorization costs and excludes 
contributed in lieu of royalty-free rock. contributed funds $138,189. 
4. Excludes $378,989 contributed funds. 10. Excludes $41,094 contributed funds. 
5. Includes $207,800 Public Works Administration funds 11. Includes $81,455 for reconnaissance and condition 
and breakwater modifications (1960 Act) placed inactive surveys FY 1956-1983. 
1974.
6. Includes $5,170 for reconnaissance and condition surveys 
for FY 1956-1983. 
TABLE 34-D OTHER AUTHORIZED BEACH EROSION 
CONTROL PROJECTS 
For Last Cost to Sep 30, 1983 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Humboldt Bay, CA Inactive 1958 2,000 - 
Santa Cruz County, CA Inactive 1966 245,639 - 
34-10

TABLE 34-G 
SAN FRANCISCO, CALIFORNIA, DISTRICT 
DEAUTHORIZED PROJECTS 
For Last 
Full Report Federal Contributed 
See Annual Date Funds Funds 
Project Report For Deauthorized Expended Expended 
Knights Valley Lake, R.R. 
Basin, CA 1974 Aug. 5, 1977 - - 
Oakland Harbor, CA 
(Deepen Tidal Canal) 1981 Nov. 6, 1977 - - 
Oakland Harbor, CA (Fruitvale 
Avenue Bridge) 1981 Nov. 6, 1977 - - 
San Lorenzo Creek, CA 
(Upper Portion) 1962 Nov. 6, 1977 - - 
San Pablo Bay and Mare 
Island Strait, CA 
(Approaches to Vallejo 
and South Vallejo) 1982 Nov. 6, 1977 - - 
TABLE 34-H RUSSIAN RIVER BASIN, CA: ESTIMATED 
COST FOR NEW WORK 
(See Section 6 of Text) 
Estimated Cost 
Project Feature Federal Non-Federal Total 
Coyote Valley Dam (Lake Mendocino); 
Channel Improvements Below Dam 
on Lower 98 Miles of Russian River $ 14,436,000 $ 5,598,000 $ 20,034,0001 
Dry Creek (Warm Springs) Lake; Channel 
Improvements Below Dam 244,900,000 93,220,0002 338,120,000 
Total $259,336,000 $98,818,000 $358,154,000 
1. Exclusive of $1,628,000 for recreation facilities at 
completed projects. 
2. Reimbursement by local interests to Federal Government 
for costs allocated to water supply storage to be paid 
over a period not to exceed 50 years after use of storage is 
initiated and exclusive of lands and damages. 
34-11

TABLE 34-I 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
RUSSIAN RIVER BASIN, CA: PROJECT 
FEATURES AND ESTIMATED COSTS 
(See Section 6 of Text) 
Height of Reservoir 
Nearest City Distance Dam and Capacity Estimated 
Name (California) Above Mouth Type (Acre-Ft) Cost 
Coyote Valley Dam (Lake Ukiah Mile 0.8-East Fork 160 Feet-Earthfill 122,500 $ 17,550,0001 
Mendocino) of Russian River 
Channel Improvement (East Fork Ukiah Mile 0 to 0.8 East - - 2,484,000 
Fork 
Below Coyote Valley Dam and Guerneville Mile 0 to 98, Russian - - 
Lower 98 Miles of Russian River) River 
Dry Creek (Warm Springs) Lake Healdsburg Mile 14.4 Dry Creek 319 Feet-Earthfill 381,000 334,600,000 
Channel Improvement (Dry Creek) Healdsburg Mile 1 to 14.4 Dry - - 3,520,000 
Below Dry Creek (Warm Springs Creek 
Dam) 
1. Exclusive of $1,628,000 for recreation facilities at 
completed projects. 
34-12

SACRAMENTO, CA, DISTRICT* 
This district comprises basins of Suisun Bay and San 
Joaquin and Sacramento Rivers in California; Goose 
Lake in Oregon; basins of the Great Salt Lake and 
Sevier Lake in Utah; an intervening portion of Great 
Basin in northern Nevada, northern California, and 
southeastern Idaho; and the upper Colorado River 
basin, which is in southwestern Wyoming, eastern 
Utah, northeastern Arizona, northwestern New Mexico, 
and western Colorado, west of the Continental Divide. 
IMPROVEMENTS 
Navigation 
1. Sacramento River, CA .................. 
2. San Francisco Bay to Stockton, CA 
(John F. Baldwin and Stockton 
Ship Channels).......................... 
3. San Joaquin River, CA .................. 
Page 
35-1 
35-2 
35-3 
Flood Control 
4. Buchanan Dam-H.V. Eastman Lake, 
Chowchilla River, CA ................... 35-4 
5. Calaveras River and Littlejohn 
Creek and tributaries, including 
New Hogan Lake and Farmington 
Dam, CA ............................... 35-4 
6. Corte Madera Creek, CA ................ 35-5 
7. Hidden Dam-Hensley Lake, Fresno 
River, CA .............................. 35-6 
8. Isabella Lake, Kern River, CA ........... 35-6 
9. Kaweah and Tule Rivers, including 
Terminus Dam and Success Lake, CA ..... 35-7 
10. Martis Creek Lake, Martis Creek, 
NV and CA ............................. 35-9 
11. Merced County Stream Group, CA ........ 35-9 
12. Pine Flat Lake and Kings River, 
CA ..................................... 35-9 
13. Sacramento River and tributaries, 
CA from Collinsville to Shasta Dam ....... 35-11 
Flood Control (Cont'd) Page 
14. Walnut Creek, CA ....................... 35-12 
15. Inspection of Completed Flood 
Control Projects.........................35-13 
16. Flood Control Work under Special 
Authorization............................35-14 
17. Scheduling Flood Control Reservoir 
Operations.............................. 35-14 
Multiple-Purpose Projects Including Power 
18. New MelonesLake, CA..................35-14 
General Investigations 
19. Surveys ................................. 35-15 
20. Collection and Study of Basic Data ........ 35-16 
21. Research and Development ............... 35-16 
22. Advance Engineering and Design......... 35-16 
Tables 
Table 35-A 
Table 35-B 
Table 35-C 
Table 35-D 
Table 35-E 
Table 35-F 
Table 35-G 
Cost and Financial 
Statement ..................... 35-18 
Authorizing 
Legislation .................... 35-21 
Other Authorized 
Navigation Projects ............ 35-23 
Not Applicable 
Other Authorized Flood 
Control Projects ................ 35-24 
Not Applicable 
Deauthorized Projects .......... 35-26 
Navigation 
1. SACRAMENTO RIVER, CA 
Location. Rises in Trinity Mountains in north-central 
California, flows generally southerly about 374 miles 
and empties into Suisun Bay, an arm of San Francisco 
Bay, at Collinsville, CA. (See Geological Survey topographic 
map of Sacramento Valley, CA.) 
Previous projects. For details see page 1985 of 
Annual Report for 1915 and page 1708 of Annual 
Report for 1938. 
Existing project. For description of Sacramento 
Deep Water Ship Channel, see Annual Report for 1969. 
Total first cost for completed portion was $43,932,558 
($39,560,558 Federal (Corps), $300,000 (Coast Guard), 
and $4,072,000 non-Federal for lands and damages, 
35-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
including relocations) and excludes local interests cost 
$10,741,000 (June 1963) for 30-foot deep water ship 
channel and 13-foot deep connecting canal basic terminal 
facilities required under terms of project authorization. 
Project also provides for a shallow-draft channel 
10 feet deep at mean lower low water 150 to 200 feet 
bottom width, from Suisun Bay to Sacramento, CA, 60 
miles; a depth of 6 feet at low water between Sacramento 
and Colusa, 85 miles; a depth of 5 feet at low water 
between Colusa and Chico Landing, 50 miles; and such 
depths as practicable between Chico Landing and Red 
Bluff, 53 miles, a total distance of 248 miles. Estimated 
Federal cost (July 1973) of new work for shallow-draft 
river channel is $1,360,000 (includes $1,163,000 for 
deferred portion between Colusa and Chico Landing). 
(See table 35-H on tidal and flood conditions prevailing.) 
Local cooperation. Fully complied with for deep 
water ship channel project. None required on shallowdraft 
feature. 
Terminal facilities. Piers, wharves, and docks at 
Port of Sacramento for shallow-draft navigation are 
open-pile structures with timber decks, some of which 
are designed to meet extreme high waters of flood 
stages. All main wharves at Sacramento have rail 
connections. Three of above facilities are owned by city 
of Sacramento and remainder by private interests; all 
are privately operated. For full description see "Port 
and Terminal Facilities at the Ports of Sacramento, 
Stockton, Pittsburg and Antioch, Calif., 1975." Deep 
water terminal facilities comprise wharves and piers, 
administration and storage buildings, and belt railroad 
facilities. Majority of these facilities are owned and 
operated by Sacramento-Yolo Port District; remainder 
are privately owned and operated. Facilities are considered 
adequate for existing commerce. 
Operations and results during fiscal year. New 
work, Deep Water Ship Channel: None. Maintenance: 
Shallow Draft Channel: Minor maintenance and operation 
activities continued in Sacramento River, Sacramento 
upstream to Colusa. Deep Water Ship Channel: 
Maintenance and operation activities continued. Fiscal 
year costs for major maintenance items consisted of: 
Maintenance dredging on Sacramento River, mile 12.9 
to mile 13.1 and mile 26.9 to mile 35.5 by suction dredge 
initiated by contract, $200,000; and stone protection on 
levees continued by contract, $358,230. 
Historical summary. Construction of 7-foot shallowdraft 
channel below Sacramento was initiated in September 
1899 and completed in 1904. Modified 10-foot 
shallow-draft channel up to Sacramento was initiated 
in FY 1928 and completed in 1931. Shallow-draft 
channel above Sacramento was begun in April 1946 but 
new work was discontinued when about 48 percent 
complete. In February 1974, remaining work for shallowdraft 
portion of project, provision of a 5-foot depth 
between Colusa and Chico Landing (50 miles), was 
reclassified as "deferred." Channel is navigable all 
year; however, there is no regular navigation above 
Colusa, 145 miles above river mouth. Construction of 
30-foot deep water ship channel was initiated in July 
1949; improvement dredging by continuing contracts 
resulted in provision of an operational facility for 
oceangoing vessels during June 1963. Bascule bridge 
was completed in April 1960, barge lock in August 
1961, barge canal in November 1961, and entire deep 
water ship channel in June 1970. 
2. SAN FRANCISCO BAY TO 
STOCKTON, CA (JOHN F. 
BALDWIN AND STOCKTON 
SHIP CHANNELS) 
Location. On navigation channels extending from 
entrance to San Francisco Bay to Port of Stockton 
through San Francisco, Marin, Contra Costa, Solano, 
Sacramento, and San Joaquin Counties. (See Coast and 
Geodetic Charts 5527 and 5532-5534 for respective 
areas.) 
Existing project. Project provides for modification 
of existing San Francisco Harbor, Richmond Harbor, 
San Pablo Bay and Mare Island Strait, Suisun Bay 
Channel, and San Joaquin River navigation projects to 
provide depths of 55 feet for San Francisco Bar Channel, 
45 feet for main internal bay channels upstream to 
vicinity of Avon, and 35 feet from Avon to Stockton; 
enlargement and deepening to 45 feet of maneuvering 
areas adjacent to major petroleum refinery terminals 
along channel route; widening Suisun Bay Channel; 
reclaiming shoreline marshes and inundated or lowlying 
areas by spoil deposit for public recreation and for 
industrial use; providing basic recreation facilities on 
some of the reclaimed areas for public use; and placing 
additional rock revetment on waterside of levees bordering 
channels. 
Approved project estimate (October 1983) is 
$256,400,000, (includes an allowance for estimated 
inflation through the construction period) comprising 
Federal cost (Corps) of $203,000,000, including basic 
recreation facilities ($5,500,000); Federal cost (Coast 
Guard) for navigation aids $1,300,000; and non-Federal 
cost of $52,100,000 for lands and damages, relocations, 
berthing areas, and spoil retention dikes, including the 
cash contribution ($250,000) that local interests must 
make for land enhancement at time of construction. 
Local interests must also pay, contribute in kind, or 
repay with interest one-half of separable cost of project 
allocated to recreation ($2,600,000). Existing project 
was adopted by 1965 River and Harbor Act (H. Doc. 
208, 89th Cong., 1st sess., contains latest published 
map). 
Local cooperation. Local interests, through a public 
body legally authorized and financially capable, must 
give assurances they will furnish lands, easements, and 
rights-of-way for construction and future maintenance 
of the project and for aids to navigation, including spoildisposal 
areas designated by the Chief of Engineers; 
provide necessary spoil retention dikes, bulkheads, and 
35-2

SACRAMENTO, CALIFORNIA DISTRICT 
embankments except as applicable to spoil-disposal 
areas designated as public recreation areas; make 
utility modifications and relocations required for construction, 
including new bridges or bridge alterations 
(except for railroad bridges), and absorb any increased 
annual maintenance and operation costs resulting therefrom; 
provide and maintain all necessary berthing 
areas, at a depth commensurate with project depth, at 
all terminals and wharves to be served by the deepened 
channels; and in recognition of the local land enhancement 
benefits to result from landfill during dredging, 
contribute to the United States 4 cents per cubic yard of 
all spoil material placed during initial construction for 
modification of Suisun Bay Channel project on areas not 
developed for public use. Local interests must also give 
satisfactory assurances, before starting construction of 
the affected units, that they will maintain and operate 
the Federally provided recreation areas and facilities, 
continue to maintain to adequate standards the levees 
altered, set back or provided revetment protection, and 
hold the U.S. Government free from damages due to 
deposition of spoil and construction of new levees or 
reconstruction of existing levees. Local interests, represented 
by Board of Supervisors of Contra Costa County 
and Stockton Port District, must, at time of construction, 
contribute $250,000 in cash for land enhancement; pay, 
contribute in kind, or repay with interest one-half of 
separable cost of project allocated to recreation 
($2,600,000); and maintain and operate basic recreation 
facilities after construction and install additional basic 
facilities required as demands on area expand. No work 
shall be undertaken on a modification of Suisun Bay 
Channel project unit to deepen the channel to more than 
35 feet between Avon and a proposed refinery or 
manufacturing plant, until local interests furnish formal 
assurances and definite plans for such installation 
within the Avon-Chipps Island reach of channel. Also, 
no work shall be undertaken on modification of San 
Joaquin River navigation project unit, regarding access 
channels in vicinity of Antioch, until local interests 
furnish formal assurances and definite plans for Port of 
Antioch. Formal assurances for deepening and otherwise 
improving the Stockton Deep Water Ship Channel from 
Pittsburg to Stockton were furnished by Stockton Port 
District April 9, 1970. The Stockton Port District, in 
August 1980, formally provided their intent to sponsor 
the Avon to Pittsburg reach (Suisun Bay Channel) and 
recreation development on Roberts Island. The Port of 
Stockton, by letter of October 20, 1981, stated that they 
would furnish the necessary assurances for fish and 
wildlife mitigation and enhancement, and on April 13, 
1982, provided formal updated assurances for the Avon 
to Stockton portion. No sec. 221 agreements are required 
for this project. 
Terminal facilities. See Port Series No. 30, revised 
1983, and 31, revised 1982, titled respectively: "The 
Ports of San Francisco, Redwood City, and Humboldt 
Bay, Calif." and "The Ports of Oakland, Alameda, 
Richmond, and Ports on Carquinez Strait, Calif."; and 
Port Series No. 32, revised 1975, "The Ports of Sacramento, 
Stockton, Pittsburg and Antioch, Calif." Facilities 
are considered adequate for existing commerce and 
will be adequate for future commerce upon completion 
of new terminal facilities. 
Operations and results during fiscal year. New 
work: Sacramento District: Engineering continued. 
Channel improvement-dredging mile 41.0-mile 30.9 
John F. Baldwin and Stockton Ship Channel was 
continued at fiscal year contract cost of $2,966,655. San 
Francisco District: Continued planning activities including 
model studies. 
Historical summary. Construction of project was 
initiated in June 1971 and is about 4 percent complete. 
3. SAN JOAQUIN RIVER, CA 
Location. Rises in east central California and flows 
westerly and northwesterly about 340 miles to its 
confluence with Sacramento River at head of Suisun 
Bay, 48 miles northeast of San Francisco. Deep water 
channel in San Joaquin River extends 41 miles from its 
mouth in Suisun Bay at Pittsburg to city of Stockton. 
Waterborne access to city provided by Stockton Channel, 
an artificial cut extending from river about 2 miles into 
city. (See Coast and Geodetic Survey Sheet 5527.) 
Existing project. For description of completed 
improvement, modifications, and authorizing acts, see 
Annual Report for 1967. (See table 35-I for total cost of 
new work for project completed in May 1960.) 
Projects units (1950 modification) reclassifed and 
excluded from project cost are set forth in table 35-J. 
Modification of existing project is included as one 
unit of San Francisco Bay to Stockton, CA, (John F. 
Baldwin and Stockton Ship Channels) project, authorized 
by 1965 River and Harbor Act (H. Doc. 209, 89th 
Cong., 1st sess.); this modification is reported in detail 
under Sacramento District, Improvement No. 2. 
Local cooperation. Fully complied with for completed 
portion of project; for details of required cash contributions 
on completed, inactive and deferred portions of 
project, see Existing project paragraph, Annual Report 
for 1967. 
Terminal facilities. For description of harbor facilities 
at Port of Stockton, CA, see Port Series 32, "The 
Ports of Sacramento, Stockton, Pittsburg and Antioch, 
Calif.," revised 1975. Downstream from Stockton, traffic 
is accommodated by bank landings and sheds except at 
Antioch and near Pittsburg, where there are wharves 
for shallow- and deep-draft vessels. Terminal transfer 
facilities at public ocean terminal of Port of Stockton 
are adequate for present and immediate future. 
Operations and results during fiscal year. Maintenance: 
Condition studies and miscellaneous inspections 
and reports were accomplished by hired labor. Stone 
protection maintenance on Stockton Deep Water Ship 
Channel was completed at fiscal year contract cost of 
35-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
$429,625. (Repair or restoration of wavewash protection 
is required by legislation authorized by Improvement 
No. 2.) 
Historical summary. Active portion of existing project 
was completed in May 1960. Construction of project 
was initiated in December 1877. 
Flood Control 
4. BUCHANAN DAM-H. V. EASTMAN 
LAKE, CHOWCHILLA RIVER, 
CA 
Location. On Chowchilla River about 36 miles above 
its mouth and about 16 miles northeast of city of 
Chowchilla, CA. (See Geological Survey quadrangles 
for area.) 
Existing project. Provides for construction of a 205- 
foot high rockfill dam to create a reservoir with gross 
storage capacity of 150,000 acre-feet for flood control, 
irrigation, recreation, and fish and wildlife. In conjunction 
with dam, project plan provides for about 12 miles 
of downstream levee and channel construction on Ash 
Slough to accommodate a project design flow of 5,000 
cubic feet per second within slough and 7 miles of levee 
and channel improvement on Berenda Slough. Operation 
and maintenance of dam and reservoir is the responsibility 
of the Federal Government. Total first cost for 
existing project is $28,919,597, of which $27,369,597 is 
Federal cost, including $4,580,000 for basic recreation 
facilities, and $1,550,000 non-Federal costs for lands 
and damages, including relocations for downstream 
levee and channel improvements. Local interests have 
contracted with the Bureau of Reclamation for irrigation 
service. For future non-Federal reimbursement, 
see Local cooperation paragraph. 
Local interests have also, over a period of years, 
expended about $500,000 for construction of low levees 
and clearing downstream channels to provide some 
local flood protection in project area. This work is 
inadequate during major floods. Existing project was 
adopted by 1962 Flood Control Act (S. Doc. 98, 87th 
Cong., 2d sess., contains latest published map). Lake 
formed by Buchanan Dam on Chowchilla River was 
designated "H. V. Eastman Lake" by Public Law 
93-217. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. New 
work: Minor engineering. (Construction of Buchanan 
and Hidden dam and appurtenances combined under 
one contract.) Maintenance: Maintenance and operation 
activities were continued. Paving of recreation roads 
and parking areas at Wildcat recreation area was 
initiated and completed at fiscal year contract cost of 
$23,972. Paving of roads and parking areas at Chowchilla 
recreation area was initiated at fiscal year contract cost 
of $45,000. Runoff of Chowchilla River above Buchanan 
Dam was above normal for the year. Maximum storage 
of 145,300 acre-feet occurred June 10, 1983. Maximum 
bihourly inflow to reservoir was 13,800 cubic feet per 
second on March 1, 1983. Maximum release of 5,000 
cubic feet per second on March 1, 1983, was below 
maximum permissible flood release. During the year, 
283,400 acre-feet of water was released for flood control 
and a total of 42,300 acre-feet of water was released for 
irrigation and other purposes. Project prevented an 
estimated $3,400,000 in damages from the December 
1982-April 1983 rainfloods. 
Historical summary. Construction began in July 
1971 and was completed in May 1979. Project was 
completed in September 1983, except for installation of 
piezometers (now deferred indefinitely). Dam closure 
was in March 1975; dam was completed in January 
1976. Reservoir clearing and boundary marking were 
completed May 1975. Bifurcation structure was completed 
in February 1976. Channel improvement, Ash 
and Berenda Sloughs, was completed in March 1976. 
Recreation areas: Phase I was completed in January 
1976; Phase II was completed in February 1978. Residences, 
administration building, and visitors center 
contract was completed in May 1978. Landscaping was 
completed in May 1979 and erosion control was completed 
in April 1979. A resources interpretive display 
and road relocation were completed in FY 1982. Dam 
safety assurance studies were initiated in FY 1981. 
5. CALAVERAS RIVER AND 
LITTLEJOHN CREEK AND 
TRIBUTARIES, INCLUDING 
NEW HOGAN LAKE AND 
FARMINGTON DAM, CA 
Location. Streams comprising Calaveras River and 
Littlejohn Creek groups rise in Sierra Nevada and its 
foothills, flow easterly across flatlands of San Joaquin 
Valley and empty into San Joaquin River directly, or 
through various sloughs, in vicinity of Stockton, CA. 
Littlejohn Creek is in Calaveras, Stanislaus, and San 
Joaquin Counties. The three principal stream systems 
of the group are, from south to north, Lone Tree Creek, 
Littlejohn Creek, and Duck Creek. Calaveras River 
group is in Calaveras and San Joaquin Counties. The 
two principal streams of the groups are, from south to 
north, Calaveras River and Bear Creek. (See Geological 
Survey Valley Springs quadrangle for New Hogan 
reservoir area and Trigo and Bachelor Valley quadrangles 
for Farmington reservoir area.) 
Existing project. For description of completed 
improvements consisting of Farmington Dam, New 
Hogan Lake, and Bear Creek levee and channel improvement, 
and authorizing act, see Annual Report for 1967. 
(a) Farmington: Total first cost (July 1955) for project 
was $3,995,684, of which $3,676,384 was Federal and 
$319,300 non-Federal for lands and damages including 
relocations. (b) New Hogan: Federal cost for project is 
$15,906,150, including $543,514 for basic recreation 
facilities. For future non-Federal reimbursement, see 
35-4

SACRAMENTO, CALIFORNIA DISTRICT 
Local cooperation paragraph. Federal cost for recreation 
facilities funded from Code 710 appropriations is 
$897,742. (c) Bear Creek: Project cost is $6,485,734, of 
which $3,242,867 is Federal, including reimbursement 
($488,096) to local interests of one-half of excess local 
interest cost of lands, rights-of-way, and relocations 
over estimated Federal construction cost in accordance 
with section 3, Public Law 738, 74th Congress. Non- 
Federal cost included in above amount is $3,242,867 for 
relocations and lands and damages, exclusive of above 
Federal reimbursement. 
Local cooperation. Fully complied with. New Hogan: 
Local interests must pay portion of first cost and annual 
operation and maintenance costs allocated to conservation 
functions of project. These costs are estimated at 
36.2 percent of first cost and 38 percent of annual costs. 
In addition, local interests contributed land, the (July 
1964) market value of which was $556,000. For years 
1961 through 1970, an interim contract between the 
Bureau of Reclamation and local water users provided 
for storage and payment of irrigation water; local 
interests paid $2,207,101 through December 31,1982. A 
long-term contract between that agency and local water 
users was executed August 25, 1970. A concessionaire 
at New Hogan Marina provided public use facilities in 
accordance with lease agreement with the Secretary of 
the Army at an estimated cost to date of $234,000. 
Operations and results during fiscal year. New 
work: New Hogan Lake, regular funds: None. Code 710 
funds: None. Bear Creek, San Joaquin County: None. 
Maintenance: Bear Creek-Levee and channel improvement 
prevented $1,500,000 in damages from the December 
1982-April 1983 rainfloods. Farmington Dam- 
Maintenance and operation activities continued; structures 
were maintained in serviceable condition. During 
the rainflood season, maximum flow of Duck Creek 
diversion was 2,600 cubic feet per second January 22, 
1983. Maximum uncontrolled flow of Littlejohn Creek 
at Farmington was 2,800 cubic feet per second January 
22, 1983. Maximum storage in reservoir was 31,700 
acre-feet on January 29, 1983, and maximum bihourly 
inflow to reservoir was 16,500 cubic feet per second on 
January 22, 1983. Project prevented an estimated 
$6,000,000 in damages from the December 1982-April 
1983 rainfloods. New Hogan Lake-Maintenance and 
operation activities continued. A cultural resources 
survey was initiated at fiscal year contract cost of 
$20,766. Structures were maintained in serviceable 
condition. Runoff of Calaveras River above New Hogan 
was above normal for the year. Maximum storage of 
262,300 acre-feet occurred June 5, 1983. Maximum 
bihourly inflow to reservoir was 19,500 cubic feet per 
second on March 13, 1983. Maximum release of 8,000 
cubic feet per second on March 2, 1983, was below 
maximum permissible flood release. During the year, 
485,000 acre-feet of water was released for flood control 
and 69,400 acre-feet was released for irrigation and 
other purposes. Project prevented an estimated 
$7,000,000 in damages from the December 1982-April 
1983 rainfloods. 
Historical summary. Farmington Dam: Construction 
of Farmington project was initiated in July 1949 and 
completed for beneficial flood control operation in 1952. 
Duck Creek channel improvement was completed in 
November 1951; and channel improvement on south 
Littlejohn Creek was completed in May 1955. There are 
no recreation facilities or public-use areas. All work 
completed. Dam safety assurance studies were initiated 
in FY 1982. New Hogan Lake: Construction was initiated 
May 1960, main dam closure November 1963, project 
completed for operational use in June 1964, and all 
work completed October 1973. Recreation facilities 
have been provided from Code 710 appropriations. 
Seepage measurement weir constructed in June 1980. 
Dam safety assurance studies were initiated in FY 
1980. Bear Creek, San Joaquin County: Construction 
began in June 1963 and was completed in June 1967. 
Final cash contribution was made to local interests 
December 23, 1970. 
6. CORTE MADERA CREEK, CA. 
Location. Creek and tributaries drain an area of 28 
square miles in Marin County, CA., and discharge into 
west side of San Francisco Bay at a point about 9 miles 
north of Golden Gate. (See Geological Survey quadrangle 
San Rafael.) 
Existing project. Provides for about 11 miles of 
channel improvements, including realignment, enlargement, 
levees, riprapping, rectangular concrete sections, 
interior drainage facilities, bridge relocations, and 
debris removal on Corte Madera Creek and lower 
reaches of its tributaries, and a continuous channel 
rights-of-way to deep water in San Francisco Bay 
reserved to assure channel outlet in the event of future 
tideland reclamation. Approved estimated cost for new 
work (October 1983) is $16,010,000, of which $10,000,000 
is Federal cost and $6,010,000 is non-Federal cost 
(includes $160,000 to be contributed by local interests.) 
(See table 34-B for authorizing legislation.) 
Local cooperation. Local interests must provide 
lands and rights-of-way, including suitable areas for 
disposal of waste material, modify or relocate all bridges 
and utilities necessary for construction and maintenance; 
hold and save the United States free from damages due 
to the construction works; maintain and operate the 
project after completion in accordance with the regulations 
prescribed by the Secretary of the Army, and 
prevent encroachment on flood channels that would 
result in decreasing the effectiveness of project for flood 
control; adjust all claims regarding water rights that 
might be affected by the project; and contribute in cash 
1.5 percent of Federal construction cost of Ross Valley 
unit and tidal areas, an estimated $160,000. Marin 
County Flood Control and Water Conservation District 
previously furnished resolution of local assurances 
dated March 29,1966, March 28,1967, August 15,1967, 
and July 8,1969, and Marin County Board of Supervisors 
35-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
reaffirmed by letter dated September 28, 1978. The 
Ross Town Council approved the alternative plan on 
May 25,1978. The project was authorized by the State of 
California by 1965 Statute, Chapter 1388. The Board of 
Supervisors of Marin County Flood Control and Water 
Conservation District furnished assurances of willingness 
and ability to meet requirements for portion of 
project below Sir Francis Drake Boulevard. Acquisition 
of rights-of-way and dredge material disposal areas, 
relocations and construction for remaining work is 
being held in abeyance as a result of a request from 
Congress for a review of alternatives other than completing 
the project as an open concrete channel. 
Operations and results during fiscal year. New 
work: At Congressional request, Sacramento District 
completed an analysis to determine if it was economically 
justified to redredge the earthen channel of the Corte 
Madera flood control project without completing the 
unimproved channel reach downstream of the Sir 
Francis Drake Boulevard Bridge (Unit 4). Analysis 
indicated that redredging was not economically justified 
without completing Unit 4. 
Historical summary. Project is about 75 percent 
complete considering the portion being held in abeyance 
upstream of Sir Frances Drake Boulevard. Work remaining: 
Design and construction of the remaining 
3,000 feet of channel downstream of Sir Francis Drake 
Boulevard and Ross Creek. In lieu of the authorized 
concrete channel, an alternative plan consisting of wing 
walls and individual house floodproofing is being recommended 
in the Significant Post-Authorization Change 
Report. That portion of the project upstream of Sir 
Francis Drake Boulevard is indefinite due to lack of 
local support. 
7. HIDDEN DAM-HENSLEY LAKE, 
FRESNO RIVER, CA 
Location. On Fresno River about 50 miles above its 
mouth and about 15 miles northeast of Madera, CA (See 
Geological Survey quadrangles for area.) 
Existing project. Provides for construction of a 163- 
foot high earthfill dam to create a reservoir with gross 
storage capacity of 90,000 acre-feet for flood control, 
irrigation, recreation and other purposes. In conjunction 
with the dam, the project provides for about 13 miles of 
downstream levee and channel improvements on Fresno 
River immediately upstream of Chowchilla Canal crossing 
to accommodate project design flow of 5,000 cubic 
feet per second. Operation and maintenance of dam and 
reservoir is the responsibility of the Federal Government. 
Total first cost for existing project is $31,785,426, 
of which $30,555,426 is Federal cost, including 
$3,564,168 for basic recreation facilities, and estimated 
$1,230,000 non-Federal cost for lands and damages 
including relocations for downstream levee and channel 
improvements. Local interests have contracted with the 
Bureau of Reclamation for irrigation service. For 
future non-Federal reimbursement, see Local cooperation 
paragraph. Local interests have also, over a period 
of years, expended about $300,000 for construction of 
low levees and clearing downstream channels to provide 
some local flood protection in the project area. This 
work is inadequate during major floods. Existing project 
was adopted by 1962 Flood Control Act (S. Doc. 37, 87th 
Cong., 1st sess., contains latest published map). Lake 
created by Hidden Reservoir project on Fresno River 
was designated "Hensley Lake" by Public Law 93-603. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. New 
work. None. Maintenance: Maintenance and operation 
activities were continued. Runoff of Fresno River above 
Hidden Dam was above normal for the year. Maximum 
storage of 89,500 acre-feet occurred May 16, 1983. 
Maximum bihourly inflow to reservoir was 11,700 
cubic feet per second on January 27, 1983. Maximum 
release of 4,000 cubic feet per second on March 1, 1983, 
was below maximum permissible flood release. During 
the year, 266,400 acre-feet of water was released for 
flood control and about 65,700 acre-feet of water was 
released for irrigation and other purposes. Project 
prevented an estimated $2,900,000 in damages from the 
December 1982-April 1983 rainfloods. 
Historical summary. Construction began in July 
1971 and was completed in January 1979. Dam closure 
was in March 1975; dam was completed November 
1975. Instrumentation was completed in January 1976. 
Downstream channel improvement, Fresno River, was 
completed April 1976. Recreation areas: Phase I was 
completed in March 1976; Phase II was completed in 
June 1978. Residences, administration building, grounds, 
and utilities contract was completed in February 1978. 
Landscaping was completed in December 1978 and 
erosion control was completed in January 1979. Project 
was completed in September 1980. Final land audit was 
approved February 5, 1980. Dam safety assurance 
studies were initiated in FY 1980. Piezometer installation 
was completed in September 1982. 
8. ISABELLA LAKE, KERN RIVER, 
CA 
Location. About 35 miles northeast of city of Bakersfield, 
CA, near confluence of north and south forks of 
Kern River; auxiliary dam is about one-half mile east of 
main dam. (See Geological Survey quadrangles of 
area.) 
Existing project. For description of completed 
improvement and authorizing act, see Annual Report 
for 1967. Federal cost for new work is $22,027,452. For 
future non-Federal reimbursement see Local cooperation 
and Licenses paragraphs. Federal cost funded 
from Code 710 appropriations is $2,199,085. Operation 
and maintenance of dam and reservoir is Federal 
responsibility. 
Local cooperation. California officially adopted project 
by chapter 1514 of statutes of 1945, State of 
35-6

SACRAMENTO, CALIFORNIA DISTRICT 
California. Local interests, represented by North Kern, 
Buena Vista, and Tulare Lake Basin Water Storage 
Districts and La Hacienda Water District, were required 
to reimburse the Federal Government the portion of 
first cost and annual operation and maintenance costs 
allocated to irrigation functions of project. These costs 
based on a cost allocation study completed in December 
1955, are $4,573,000 of first cost and 21.7 percent of 
annual operation and maintenance cost. For the years 
1956 through 1964, an interim contract between the 
Bureau of Reclamation and local water users provided 
for storage and payment of irrigation water. Under 
provisions of this interim contract, local interests paid 
$1,936,229 through December 31, 1964. A long-term 
contract between the Bureau and local water users was 
executed October 23, 1964. Balance due on allocated 
first cost of $4,573,000 was paid by the water users on 
March 31, 1965. Kern County assumed administration 
of recreation and development and maintenance of 
public use areas at project in accordance with a 25-year 
license February 15, 1955. The agreement with Kern 
County provided for joint operation and development by 
the Corps and Kern County including permits granted 
to concessionaires by the county to provide certain 
services. As of September 30, 1971, Kern County relinquished 
all administration of recreation and development 
and maintenance of public use areas at the 
project. A State law permitting the Department of 
Boating and Waterways (known as the Department of 
Navigation and Ocean Development prior to January 
1979) to participate in inland water development with 
Federal agencies was signed by the Governor on 
August 11, 1972. All concessionaires will operate under 
permits granted by the Corps. Total cost to date of 
present recreation facilities developed by the county 
and the marina concessionaires is about $880,000; 
$235,000 of this was a grant from the California 
Wildlife Conservation Board and about $449,000 is 
investment by marina concessionaires. 
Licenses. In accordance with Federal Power Commission 
Docket No. E-6578, issued April 1, 1963, payment 
of $377,426 was made to the Federal Government by 
Pacific Gas and Electric Co. ($108,352) and Southern 
California Edison Co. ($269,074) for headwater benefits 
to downstream existing plants from Isabella Dam to 
cover benefits from April 15, 1954, to December 31, 
1962. Subsequent to 1962, the power companies have in 
the aggregate made annual payments of $44,650 for 
headwater benefits. That amount is to be paid each year 
until changes in operation, development, or costs indicate 
some modification to be advisable. Federal Power 
Commission Docket No. E-6578 is being modified to 
increase cumulative use charges for subsequent years. 
Cumulative use charges collected by the Federal Power 
Commission (known as the Federal Energy Regulatory 
Commission since January 9, 1978) and returned to the 
U. S. Treasury through period ending September 30, 
1983, amounted to $1,315,076. 
Operations and results during fiscal year. New 
work, regular funds: None. Code 710 funds: None. 
Maintenance: Maintenance and operation continued. A 
cultural resources survey was initiated at fiscal year 
contract cost of $57,059. Installation of solar retrofit 
water heating at recreation facilities was initiated and 
completed at contract cost of $72,497. Dam safety 
assurance studies at Isabella Dam were continued by 
contract and hired labor at a fiscal year cost of $509,738. 
Structures were maintained in good condition. Runoff 
of Kern River above Isabella Lake was above normal for 
the year. Maximum storage of 630,800 acre-feet occurred 
July 6,1983. Maximum bihourly inflow to the reservoir 
was 9,100 cubic feet per second on December 22, 1982, 
and maximum outflow of 7,200 cubic feet per second 
occurred June 29, 1983. During the year, 2,051,000 
acre-feet was released for flood control, and 190,800 
acre-feet was released for irrigation. Project prevented 
an estimated $30,400,000 in damages from the December 
1982-April 1983 rainfloods and the May-June 1983 
snowmelt runoff. 
Historical summary. Construction began in March 
1948 and was completed in June 1968. Main dam, Borel 
Canal outlet works and appurtenances, and auxiliary 
dam were completed in April 1953. Storage impoundment 
began December 1952. Piezometer was installed 
in August 1982. Project is operating to provide flood 
protection and irrigation benefits for which it was 
designed. Recreation facilities were provided by Code 
710 funds. Dam safety assurance studies were initiated 
in FY 1979. 
9. KAWEAH AND TULE RIVERS, 
INCLUDING TERMINUS DAM 
AND SUCCESS LAKE, CA 
Location. Terminus Dam is on Kaweah River about 
20 miles east of Visalia, CA. Success Lake is on Tule 
River about 5 miles east of Porterville, CA. (See Geological 
Survey quadrangles of area.) 
Existing project. Terminus Dam: For description of 
completed improvement and authorizingact, see Annual 
Report for 1975. Federal costof new work is $19,302,957, 
including $242,605 for basic recreation facilities and 
excluding spreading works constructed by local interests 
at an estimated (July 1957) cost of about $750,000. 
Spreading works portion of project has been deauthorized. 
The 90-day Congressional project review period, 
required by sec. 12, Public Law 93-251, as amended, 
ended August 5, 1977, and resulted in deauthorization 
of that portion of project. Federal cost of recreation 
facilities funded from Code 710 appropriations is 
$700,004. Success Lake: For description of completion 
improvement and authorizing act, see Annual Report 
for 1975. Federal cost of new work for Success Lake is 
$14,247,221, including $253,697 for basic recreation 
facilities. Federal cost of recreation facilities funded 
from Code 710 appropriations is $747,048. For future 
non-Federal reimbursements, see Local cooperation 
35-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
paragraph. Operation and maintenance of reservoirs is 
Federal responsibility. 
Local cooperation. California officially adopted projects 
by chapter 1514 of statutes of 1945, State of 
California. Local interests for Terminus Dam are represented 
by Kaweah Delta Water Conservation District. 
Local interests for Success Lake are considered to be 
represented by the Vandalia, Porterville, and Lower 
Tule River Irrigation Districts, the Tulare Lake Basin 
Water Storage District, and Pioneer Water Co., which 
represent over 90 percent of irrigated land and waterright 
holders along Tule River below damsite. Local 
interests must reimburse the Federal Government the 
portion of first cost and annual operation and maintenance 
costs allocated to irrigation functions of projects. 
These costs are estimated at 14.1 percent of first and 
annual costs for Terminus and 9.5 percent of first and 
annual costs for Success. Local interests for Terminus 
stated they will continue to operate and maintain 
spreading works and downstream channel systems to 
provide required capacity for disposal of floodwaters. 
Local interests for Success stated they will continue to 
maintain downstream channel systems to provide 
required capacity for disposal of floodwaters. Repayment 
contracts between the Bureau of Reclamation and 
local water users for irrigation supply from Terminus 
and Success reservoirs were executed January 11, 1965, 
and April 30, 1965, respectively. Reservoirs are being 
operated for irrigation storage as well as flood control 
and incidental recreation use. Tulare County acquired 
water for recreation pools at the projects. Local interests 
paid the following total amounts for irrigation services 
from the reservoirs through December 31, 1982: 
Terminus, $1,421,705 and Success, $650,901. Tulare 
County was granted a 25-year license for planning, 
devel pment, and management of public recreation 
areas at Success, July 10,1960, and at Terminus, June 5, 
1961. asic public-use facilities constructed by Corps at 
the Success reservoir were transferred tojurisdiction of 
Tulare County on January 18, 1962; facilities at 
Terminus were transferred June 20, 1962. In March 
1967, an amendment to the license agreements was 
approved by the Assistant Secretary of the Army. 
Under these amended licenses, Tulare County retained 
administration of only specified land areas and operation 
and maintenance of recreation facilities in these 
areas. In addition, they continued their program of 
water safety, boat inspection, and law enforcement at 
both reservoirs. The Corps took over the administration 
of the remainder of the project land areas and the 
operation and maintenance of recreation facilities in 
these areas. Calif. Department of Fish and Game 
expended funds to improve fishery resources of the 
Terminus reservoir. As of April 1, 1972, Tulare County 
relinquished all planning, development, and management 
of public recreation areas at Terminus Dam. 
Tulare County by expenditure of county funds and by a 
lease to a marina concessionaire has aided in the 
development of recreation facilities at an estimated cost 
of $145,000. Calif. Department of Fish and Game 
expended funds in conjunction with Tulare Sportsman's 
Council, developing a habitat for upland game birds at 
Success Lake. As of April 1, 1972, Tulare County 
relinquished all planning, development, and management 
of public recreation areas at Success Lake, except 
for the Bartlett Park recreation area. Tulare County 
has aided in development of recreation facilities. Total 
cost to date of present recreation facilities developed by 
the county ($360,000) and the marina concessionaires 
($368,000) is about $728,000. 
Operations and results during fiscal year. New 
work: Terminus Dam, regular funds: None. Code 710 
funds: None. 
Success Lake, regular funds, None. Code 710 funds: 
None. 
Maintenance: Terminus Dam: Maintenance and operation 
continued. A cultural resources survey was initiated 
at fiscal year contract cost of $35,394. Dam safety 
assurance studies at Terminus Dam were continued at 
fiscal year cost of $3,519. Structures were maintained 
in serviceable condition. Runoff of Kaweah River above 
Terminus Dam was above normal for the year. Maximum 
storage of 146,100 acre-feet occurred on June 26, 
1983. Maximum bihourly inflow to the reservoir on 
December 22, 1982, was about 17,000 cubic feet per 
second. Maximum outflow of 4,500 cubic feet per second 
occurred June 26,1983. Water released for flood control 
amounted to 1,070,000 acre-feet and irrigation and 
spreading releases totaled 327,800 acre-feet. Project 
prevented an estimated $26,700,000 in damages from 
the December 1982-April 1983 rainfloods and the May- 
June 1983 snowmelt runoff. Success Lake: Maintenance 
and operation continued. Paving of recreation roads 
and parking areas at Tule recreation area, Success 
Lake, was initiated at fiscal year contract cost of 
$200,000. A cultural resources survey was initiated at 
fiscal year contract costof $30,167. Dam safety assurance 
studies were continued at Success Dam at fiscal year 
costof $6,664. Structures were maintained in serviceable 
condition. Runoff of Tule River above the reservoir was 
above normal during the year. Maximum bihourly 
inflow to the reservoir was 12,000 cubic feet per second 
on January 22, 1983, and maximum outflow of 1,500 
cubic feet per second occurred on May 31, 1983. Maximum 
storage of 82,200 acre-feet occurred on June 18, 
1983. Water released for flood control amounted to 
486,000 acre-feet and irrigation and spreading releases 
amounted to 125,500 acre-feet. Project prevented an 
estimated $11,300,000 in damages from the December 
1982-April 1983 rainfloods and the May-June 1983 
snowmelt runoff. 
Historical summary. Terminus Dam: Construction 
of project began in July 1957 and was completed in June 
1968 except for final settlement for one tract of land 
upon decision of pending court case. Construction of 
main dam and appurtenances, initiated in February 
1959, was completed in June 1962. Dam has been 
operating since November 1961 to provide flood protection 
for which it was designed; conservation impound- 
35-8

SACRAMENTO, CALIFORNIA DISTRICT 
ment was commenced May 1962. Appurtenances are in 
good condition. Recreation facilities were provided by 
Code 710 funds. Dam safety assurance studies were 
initiated in FY 1979. Success Lake: Construction of 
project began in November 1956, was completed in 
June 1968, and final audit of historical land record was 
approved December 17, 1979. Construction of main 
dam and appurtenances, initiated in October 1958, was 
completed in May 1961. Dam has been operating since 
October 1960 to provide flood protection for which it 
was designed; conservation impoundment was commenced 
March 1962. Recreation facilities were provided 
by Code 710 funds. Dam safety assurance studies were 
initiated in FY 1979. 
10. MARTIS CREEK LAKE, MARTIS 
CREEK, NV AND CA 
Location. Reservoir is on Martis Creek a tributary of 
Truckee River, near Truckee, CA; intermittent channel 
improvements are on Truckee River in Reno, NV. (See 
Geological Survey quadrangles for areas.) 
Existing project. For description of completed 
improvement and authorizing act, see Annual Report 
for 1975. Federal cost for project was $8,503,789 including 
$289,506 for basic recreation facilities. Federal cost 
of recreation facilities funded from Code 710 appropriations 
was $1,200. Construction of recreation facilities 
under Code 710 was determined to be infeasible. Operation 
and maintenance of reservoir is Federal responsibility. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. New 
work: None. Maintenance: Maintenance and operation 
of project, including recreation facilities, was continued. 
Structures were maintained in serviceable condition. 
Runoff above Martis Creek Dam was above normal for 
the year. Maximum storage of 1,099 acre-feet occurred 
on May 28,1983. Maximum daily inflow to the reservoir 
on May 28, 1983, was about 380 cubic feet per second 
and maximum outflow of 360 cubic feet per second 
occurred May 29, 1983. 
Historical summary. Project construction began in 
August 1967; dam closure was in October 1971; dam 
was completed in August 1972; basic recreation facilities 
were completed in December 1972; and project was 
completed in June 1974. Recreation facilities under 
Code 710 funding were considered infeasible. Dam 
safety assurance studies were initiated in FY 1981. 
11. MERCED COUNTY STREAM 
GROUP, CA 
Location. Reservoirs and channel improvements are 
on Bear, Burns, Mariposa, and Owens Creeks, in foothills 
of Sierra Nevada about 15 to 20 miles east of city of 
Merced, CA. (See Geological Survey Haystack Mountain 
quadrangle for Burns and Indian Gulch quadrangle for 
Bear, Owens, and Mariposa areas.) 
Existing project. For description of completed 
improvements and authorizing act, see Annual Report 
for 1962. Improvements consist of reservoirs at Mariposa, 
Owens, Burns and Bear Creeks and diversions 
from Black Rascal Creek to Bear Creek and from 
Owens Creek to Mariposa Creek. Total first cost for 
project was $3,899,259, of which $2,751,259 was Federal 
and $1,148,000 non-Federal for lands including relocations 
and channel improvement. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Maintenance: 
Ordinary maintenance and operation of the four 
completed reservoirs continued. Structures were maintained 
in a serviceable condition. Runoff from drainage 
areas above Merced County stream group reservoirs 
was above normal for the year. (See table 35-K for 
maximum inflow storage and outflow for projects.) 
Outflows were less than channel capacity rates in the 
project streams. Project prevented an estimated 
$10,200,000 in damages from the December 1982-April 
1983 rainfloods. 
Historical summary. Construction was initiated 
March 1948, with construction of Mariposa project, 
which was completed in November 1948. Construction 
of Owens project, initiated in March, was completed in 
October 1949; Burns project, initiated in July 1949, was 
completed in January 1950; and Bear project initiated 
in April, was completed in December 1954. Black 
Rascal and Owens Creek diversion channels and streamgaging 
stations were completed in April 1956. Local 
interests completed channel enlargement and restoration 
of channel capacities of Miles, Burns, Owens, and 
Mariposa Creeks in 1956 at their expense. Improvement 
of Bear Creek and Black Rascal Slough, below their 
confluence, was deferred pending possible improvements 
downstream, outside limits of project. 
12. PINE FLAT LAKE AND KINGS 
RIVER, CA 
Location. Reservoir is on Kings River, about 25 miles 
east of Fresno, CA, and channel improvements are on 
Kings River downstream from Lemoore weir, about 25 
miles south of Fresno. (See Geological Survey quadrangles 
of area.) 
Existing project. Improvement is a unit in comprehensive 
plan for flood control and other related purposes 
for Sacramento-San Joaquin Basins. Project consists of 
a 429-foot high concrete gravity dam, including a gated 
overflow section with a maximum discharge capacity of 
391,000 cubic feet per second, creating a reservoir with 
gross storage capacity of 1 million acre-feet, for flood 
control, irrigation, and related purposes. Outlet provisions 
for future power development are included in 
dam, but Federal construction of power-generating 
facilities is not authorized. Improvement also includes 
levee and channel work on Kings River and its distributaries 
on valley floor about 25 miles south of Fresno. 
35-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Channel improvement work will enlarge channel capacities 
and regulate flows in lower branches of the Kings 
River. There are nine public-use and recreation areas: 
One maintained by the Corpp, four by the Forest 
Service, three jointly by the Corps and concession, and 
one by Fresno County. Also, five boat access-only areas 
are maintained by the Corps on the south side of the 
reservoir. Project cost is $42,072,330, of which 
$41,502,330 is Federal (including $13,700 for basic 
recreation facilities) and $570,000 non-Federal for 
rights-of-way for downstream channel improvements. 
For future non-Federal reimbursement, see Local 
cooperation paragraph. Federal cost of recreation 
facilities for Pine Flat Lake, funded from Code 710 
appropriations is $1,595,100 exclusive of recreation 
facilities previously provided at a cost of $13,700. In 
addition, Federal cost of recreation facilities for Pine 
Flat Lake, funded from Public Works Acceleration 
Executive Act of 1962 appropriations, was $239,235 
(July 1963). Operation and maintenance of dam and 
reservoir is Federal responsibility. Existing project 
was adopted by 1944 Flood Control Act (H. Doc. 630, 
76th Cong., 3d sess., contains latest published map). 
Local cooperation. Local interests must reimburse 
the Federal Government for first costs allocated to 
irrigation functions of reservoir portion of project in 
accordance with reclamation law. Under provision of 
War Department Civil Appropriations Act of 1947, the 
Secretary of War, with concurrence of the Secretary of 
the Interior, determined allocation of cost to irrigation 
should be set at an amount not to exceed $14,250,000. In 
addition, local interests must pay 37.4 percent of annual 
maintenance, operation, and replacement costs of dam 
and reservoir allocated to irrigation function. Repayment 
contracts between the Bureau of Reclamation and 
the local water users for the irrigation use of the 
reservoir were executed December 23,1963. The Bureau 
is administering the contracts in accordance with 
reclamation law as amended by the Reclamation Reform 
Act of October 12,1982. That act generally exempts the 
limitations under the early reclamation laws as being 
applicable to projects constructed by the Corps with two 
exceptions; however, all existing contracts to share 
construction and maintenance costs remain in effect. 
Prior to execution of the final contracts, the Bureau 
provided conservation water to local interests under an 
interim contract. Irrigation interests paid $14,216,886 
for irrigation services through December 31, 1982. 
With respect to the downstream channel improvements, 
sec. 3, Flood Control Act of June 22,1936, applies. King 
River Conservation District represents local interests; 
assurances were accepted November 20, 1959. Local 
interests have furnished all requirements for construction 
rights-of-way for construction of channel improvements 
required to date. Three concessionaires-one 
each at Lakeridge Marina (Deer Creek), Lakeview 
Marina (Lombardo's Fishing Village), and Trimmer 
Marina provided public-use facilities in accordance 
with lease agreements with the Secretary of the Army. 
Estimated cost to date of facilities installed by these 
concessionaires is $1,694,000. Fresno County developed 
public-use facilities on an 85-acre tract immediately 
downstream from dam for picnicking, camping, swimming, 
and playground activities, at an estimated cost to 
date of $476,000 under provisions of a license agreement. 
The U.S. Forest Service developed and operates a 
picnic area at the upper end of reservoir. Cost of site 
development is about $37,500. 
Licenses. License No. 1988, effective April 1, 1955, 
was issued by Federal Power Commission to Pacific 
Gas and Electric Co. for hydroelectric power development 
of North Fork Kings River by the company 
upstream from the Pine Flat reservoir. Under interim 
Contract No. DA-04-167-eng-1182 with the Department 
of the Army, Pacific Gas and Electric Co. paid for 
storage of power water in the Pine Flat reservoir 
May 15,1954, through March 31,1955. Current Contract 
No. DA-04-167-eng-1328 with the Department of the 
Army provides for storage of power water at the rate of 
0.1375 per acre-foot; the contract covers April 1, 1955, 
through March 31, 2005. By an agreement of January 
1972, supplementing the December 1954 contract, Pacific 
Gas and Electric Co. transferred ownership of 
most of its Kings River system water to the Kings River 
Water Association. Accordingly, no further significant 
storage service to Pacific Gas and Electric Co. by the 
reservoir at Pine Flat is anticipated. Total payment 
under these contracts through June 30, 1972, (last year 
of payment), amounts to $2,478,798; these funds are 
paid to Sacramento District and deposited for return to 
the Treasury. 
Operations and results during fiscal year. New 
work, regular funds: None. Code 710 funds: None. 
Maintenance: Maintenance and operation activities 
continued. Improvement of access road to Deer Creek 
Group area near Island Park recreation area was 
initiated at fiscal year contract cost of $200,000. A 
cultural resources survey was initiated at fiscal year 
contract cost of $50,869. Structures were maintained in 
serviceable condition. Runoff of Kings River above Pine 
Flat Dam was above normal for the year. Maximum 
storage of 992,300 acre-feet occurred on August 10, 
1983. Maximum bihourly inflow to the reservoir was 
50,000 cubic feet per second on December 22, 1982, and 
maximum outflow of 13,600 cubic feet per second 
occurred on July 6, 1983. During the year, 3,502,000 
acre-feet of water was released for flood control and 
657,000 acre-feet of water was released for irrigation 
and spreading. Project prevented an estimated 
$79,800,000 in damages from the December 1982-April 
1983 rainfloods and May-June 1983 snowmelt runoff. 
Historical summary. Construction began in April 
1947 and project, including channel improvement, was 
completed in September 1977. Main dam was initiated 
in January 1950, completed in June 1954, and has been 
operating since February 1954 to provide flood protection 
for which it was designed. Total of 35.2 miles of new 
and reconstructed levees and 13.2 miles of channel 
clearing have been transferred to the Kings River 
35-10

SACRAMENTO, CALIFORNIA DISTRICT 
Conservation District for maintenance. Recreation facilities 
for various recreation areas under Code 710 appropriation 
are complete. Completed preliminary design 
and cost estimates for Pine Flat fish barrier were 
reviewed by the State, but the State was unable to 
provide necessary assurances of local cooperation. Dam 
safety assurance studies were initiated in FY 1982. 
13. SACRAMENTO RIVER AND 
TRIBUTARIES, CA, FROM 
COLLINSVILLE TO SHASTA DAM 
Location. Rises in Trinity Mountains in north-central 
California, flows generally southerly about 374 miles 
and empties into Suisun Bay, an arm of San Francisco 
Bay at Collinsville, CA. Works covered by this improvement 
are on Sacramento River and tributaries from 
Collinsville to Shasta Dam, about mile 312. Drainage 
area above Rio Vista is 26,500 square miles (See 
Geological Survey quadrangles of area for Sacramento 
River and Upper Butte Basin; Flournoy and Fruto 
quadrangles for Black Butte Lake; and Tuscan Buttes, 
Tehama, Redding, and Hooker quadrangles for Table 
Mountain Lake.) 
Existing project. Improvement of Sacramento River 
and tributaries, from Collinsville to Shasta Dam was 
authorized as a unit of a comprehensive plan for flood 
control and other related purposes in Sacramento River 
Basin. (a) Sacramento River and major and minor 
tributaries, for flood control purposes: Enlargement of 
existing levees on Sacramento River between vicinity of 
Moulton weir and Ord Bend; construction of new levees 
from present levee terminus to vicinity of Chico Landing; 
construction of a weir near Chico Landing, extension of 
Moulton weir, and construction of a bypass through 
Upper Butte Basin; construction of new levees in Lower 
Butte Basin; enlargement of existing levees in Sutter, 
Tisdale, Sacramento, and Yolo Bypasses; and levee 
construction and/or channel enlargement on following 
minor tributaries of Sacramento River: Antelope Creek; 
Chico and Mud Creeks and Sandy Gulch; Butte and 
Little Chico Creeks; Cherokee Canal; Elder Creek; Deer 
Creek (Tehama County); Thomes Creek; and Willow 
Creek. Improvement provides for about 155 miles of 
channel improvement and about 294 miles of levees 
with an average height of 12 feet and a freeboard of 3 
feet. Improvement also provides for revetment as required 
for protection of bypass levee slopes against 
erosion. Total first cost for project is $18,300,000 (October 
1983), of which $11,900,000 is Federal, and $6,400,000 
non-Federal for lands and damages, including relocations. 
(See table 35-L on project units classified and 
excluded from cost estimate.) (b) Sacramento River, 
Chico Landing to Red Bluff, CA: An extension of the 
existing Sacramento River Flood Control project which 
provides for construction of bank protection works and 
minor channel improvements as required on Sacramento 
River between Chico Landing and Red Bluff for flood 
control purposes. Estimated first cost (October 1982) 
for project work in Tehama, Butte, and Glenn Counties 
is $16,700,000, of which $14,700,000 is Federal cost and 
$2,000,000 non-Federal cost for lands and damages 
including relocations. (c) Sacramento River, CA, Bank 
Protection Project: Includes initial phase covering 
405,000 lineal feet of bank protection and a second 
phase covering 430,000 lineal feet of bank protection 
under a long range program of bank protection, erosion 
control works, and setback levees at critical locations 
within limits of authorized or existing levees included 
in the Sacramento River Flood Control project to 
protect integrity of levee system for flood control 
purposes. Total estimated (October 1983) first cost for 
project is $150,000,000, of which $100,000,000 is Federal 
(including $2,760,000 for recreation facilities) and 
$50,000,000 non-Federal comprising $27,000,000 for 
lands and damages including relocations and $23,000,000 
required cash contribution toward first cost. Construction 
in (a), (b), and (c) above supplements program of 
levee improvements as accomplished pursuant to 1917 
Flood Control Act, as amended by subsequent acts, ding 
inclul941 Flood Control Act, and which are reported by 
California Debris Commission under Sacramento 
River, CA, flood control. (d) Authorization also 
provided for Black Butte Lake. For description of 
completed project see Annual Report for 1975. Federal 
first cost for project is $14,508,820, including $475,507 
for basic recreation facilities. For future non-Federal 
reimbursement, see Local cooperation paragraph. 
Federal cost for recreation facilities funded from Code 
710 appropriations is $1,000,162. A concessionaire at 
Black Butte Marina provided public use facilities in 
accordance with lease agreement with the Secretary of 
the Army at an estimated cost to date of $87,000. (e) 
Authorization also provided for construction of Table 
Mountain (Iron Canyon) project, an earthfill dam on 
Sacramento River about 3 miles north of Red Bluff, CA. 
This project unit was deauthorized August 5, 1977. For 
details, see Annual Report for 1978. 
Local cooperation. (a) Sacramento River and major 
and minor tributaries: Sec. 3, Flood Control Act of June 
22, 1936, applies. Fully complied with for all work 
completed or under contract, and local interests indicated 
they will be able to fulfill requirements for 
remaining work as scheduled. Levee construction (107 
miles) total requirement for the "active" project has 
been completed, transferred to, and accepted by the 
State. (b) Sacramento River, Chico Landing to Red 
Bluff: Sec. 3, Flood Control Act of June 22, 1936, 
applies; local interests must also assume responsibility 
for flood plain zoning. Fully complied with for portions 
completed in Tehama, Butte, and Glenn Counties; 
completed work, bank protection at 29 sites, was transferred 
to and accepted by the State. (c) Sacramento 
River Bank Protection Project: Sec. 3, Flood Control 
Act of June 22, 1936, applies. Local interests must also 
contribute an amount in cash that, when added to costs 
of lands, easements, rights-of-way and utility modifications, 
equals one-third of cost of each unit of remedial 
work; this contribution is estimated (October 1983) at 
$23,000,000. Local interests fully complied with require- 
35-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
ments for all work completed or under contract, and 
indicated they will be able to fulfill requirements for 
remaining work as scheduled. In addition, for reaches 
where local interests request bank stabilization in lieu 
of more feasible levee setbacks, local interests will 
contribute costs over and above costs of setbacks, and 
provide local contribution indicated above. Completed 
units transferred to and accepted by the State. (d) Black 
Butte Lake: None required for construction. Local 
interests must pay the portion of first cost and annual 
operation and maintenance costs allocated to the conservation 
functions of the project; these costs are estimated 
at 39.9 percent of first cost and 40.2 percent of annual 
costs. From March 2, 1960, to October 22,1970, contract 
between the Bureau of Reclamation and the State of 
California provided for repayment of irrigation storage 
costs; Bureau administered contract in accordance with 
reclamation law. Local interests paid a total of $77,205 
for irrigation services during this period. Public Law 
502, 91st Cong., 2d sess., October 23,1970, provided that 
Black Butte project be financially integrated with the 
Central Valley project, coordinated operationally with 
other Central Valley project storage units by the Bureau 
under the Secretary of the Interior, and that dam and 
reservoir at Black Butte be physically operated and 
maintained by the Corps in a manner compatible with 
recreational use of the reservoir. 
Operations and results during fiscal year. New 
work: (a) Sacramento River and major and minor 
tributaries-Engineering and design activities continued. 
Following inspection of bypass levees after 
1982-1983 winter floodflows, a rock procurement contract 
in the amount of $211,540 for remedial work to be 
performed by the State of California was awarded in 
September 1983. Project prevented an estimated 
$1,200,000 in damages from the December 1982-April 
1983 rainfloods. (b) Sacramento River Bank Protection 
Project-Engineering and design activities continued. 
Project prevented an estimated $300,000 in damages 
from the December 1982-April 1983 rainfloods. (See 
table 35-M for construction accomplished and contract 
costs.) (c) Sacramento River, Chico Landing to Red 
Bluff-Bank protection, one site, mile 215, (Unit 5), 
Sacramento River, Tehama County, completed in 
November 1982 at fiscal year contract cost of $548,541. 
Plans and specifications for bank protection, two sites, 
mile 209.5 and mile 217.5 (Unit 6), Sacramento River, 
Tehama County were completed; contract was awarded 
August 10,1983 and construction was initiated at fiscal 
year cost of $237,118. Project prevented an estimated 
$40,000 in damages from the December 1982-April 
1983 rainfloods, (d) Black Butte Lake, regular funds: 
None. Code 710 funds: None. Maintenance: Maintenance 
and operation activities continued. Paving of recreation 
roads and parking areas at Eagle Pass recreation area, 
Black Butte Lake, was initiated at fiscal year contract 
cost of $75,000. Piezometer installation and slope protection 
at Black Butte Dam were completed at fiscal year 
contract costs of $24,781 and $339,788, respectively. A 
cultural resources survey was initiated at fiscal year 
contract cost of $56,999. Dam safety assurance studies 
were continued at fiscal year cost of $213,901. Structures 
were maintained in serviceable condition. Runoff above 
Black Butte Dam was above normal for the year. 
Maximum storage of 156,300 acre-feet occurred 
March 4, 1983. Maximum bihourly inflow to Black 
Butte reservoir was 54,400 cubic feet per second on 
February 28, 1983, and maximum outflow of 15,000 
cubic feet per second occurred on February 28, 1983. 
Releases of water for irrigation totaled 1,107,000 acrefeet 
and flood control releases totaled 286,900 acre-feet. 
For the first time during the history of the Black Butte 
20-year operation, spillway flow occurred on March 3, 
1983, and spilled for three days. Project prevented an 
estimated $9,100,000 in damages from the December 
1982-April 1983 rainfloods. (e) Table Mountain (Iron 
Canyon) Lake: None. 
Historical summary. (a) Sacramento River and 
major and minor tributaries (active portions): Construction 
was initiated in May 1949 on Deer Creek and Butte 
Creek units; Cherokee Canal, Elder Creek, Chico and 
Mud Creeks, and Sandy Gulch units have been completed. 
Active portion of this improvement is about 93 
percent complete. Work remaining is bypass levee 
revetment as required. (b) Sacramento River Bank 
Protection Project: Construction of first unit was initiated 
in June 1963; initial phase of project was completed 
in November 1974. Phase II is underway, and overall 
project is about 45 percent complete. (c) Sacramento 
River, Chico Landing to Red Bluff: Active portion of 
project, bank protection in Tehama County, was initiated 
in June 1963 and completed in March 1964. Project was 
reopened in June 1968 to place additional necessary 
bank protection. Work at 29 sites was completed in 
Tehama, Butte, and Glenn Counties as of September 
1979 and transferred to State for maintenance. Bank 
protection on Sacramento River, Tehama County-one 
site, mile 215, (Unit 5), was completed November 1982, 
and two sites, mile 209.5 and mile 217.5, (Unit 6), were 
initiated. (d) Black Butte Lake: Construction began in 
March 1960 and project is complete. Final land acquisition 
was completed in December 1966. Construction 
of main dam was initiated in June 1960 and 
completed in December 1963. Dam has been operating 
since November 1962 to provide the flood protection for 
which it was designed. Final cost allocation approved 
May 3,1977. Dam safety assurance studies were initiated 
in FY 1980. Piezometer installation and slope for 
protection at the dam were completed in FY 1983. (e) 
Table Mountain (Iron Canyon) Lake: Project unit deauthorized 
as of August 5, 1977. 
14. WALNUT CREEK, CA 
Location. Project is on Walnut Creek and lower 
reaches of its principal tributaries, Pacheco, Grayson, 
San Ramon, Las Trampas, Galindo, and Pine Creeks in 
Contra Costa County, CA. Improvement will extend 
from Suisun Bay to head of project about 1 mile above 
35-12

SACRAMENTO, CALIFORNIA DISTRICT 
southern limits of city of Walnut Creek. City of Walnut 
Creek is about 10 miles south of Suisun Bay. (See 
Geological Survey quadrangles for area.) 
Existing project. Comprises extension of existing 
levees, construction of new levees and concrete channels, 
channel rectification and enlargement, and utilization 
of improvements constructed or planned by local interests. 
Plan provides for about 21.8 miles of channel 
improvement, two reinforced-concrete drop structures, 
two stilling basins, and 13.8 miles of levees. Cost 
estimate (1983) is $103,240,000 (includes an allowance 
for estimated inflation through the construction period), 
of which $74,300,000 is Federal cost and $28,940,000 is 
non-Federal cost (includes $23,000,000 for lands and 
damages and relocations except railroad facilities, and 
$5,940,000 required cash contribution for land enhancement 
benefits provided by the project). Local interests 
have expended about $3 million for flood control in the 
project area during the period 1955-1965, including the 
concrete conduits constructed through the city of Walnut 
Creek at an estimated cost of $1,000,000 considered a 
preproject condition to be incorporated in the Corps 
project. The cost thereof is not included in above costs of 
local cooperation. Improvement adopted by 1960 Flood 
Control Act (H. Doc. 76, 86th Cong., 1st sess., contains 
latest published map). 
Local cooperation. Section 3, Flood Control Act of 
June 22,1936, applies, except that relocation of railroad 
facilities is a Federal responsibility. In addition, local 
interests must make a cash contribution to the United 
States, in amount of 7.4 percent of cost of construction 
for land enhancement benefits provided by project. 
Cash contribution is estimated (October 1983) at 
$5,940,000. Local interests are represented by Contra 
Costa County Flood Control and Water Conservation 
District; formal assurances, including evidence of financial 
and legal ability to fulfill requirement for the cash 
contribution, were accepted by the Sacramento District 
Engineer on November 15, 1963. The Flood Control 
District furnished all rights-of-way required to date 
and indicated that it will furnish all requirements as 
needed for future construction. The Flood Control 
District will arrange for highway bridge modifications 
and utility relocations before start of work by the Corps 
contractor. Payment of required contributed funds will 
be made in installments in amounts equal to 7.4 percent 
of the estimated construction expenditure for each 
fiscal year. To date, $2,956,000 has been furnished. 
Operations and results during fiscal year. New 
work: Engineering and design for the uncompleted 
portions of Walnut and San Ramon Creeks and upper 
Pine Creek are continuing. Construction contract for 
channel improvement on lower Pine Creek (Clayton 
Road to BART) and Galindo Creek (Detroit Avenue to 
San Miguel Road) was completed at a fiscal year cost of 
$484,218. Contract for upper Pine Creek channel improvement, 
Phase 3, was initiated at fiscal year cost of 
$3,387,122. Project prevented an estimated $2,500,000 
in damages from the December 1982-April 1983 rainfloods. 
Historical summary. Construction was initiated 
June 1964; project is about 77 percent complete. Total of 
13.1 miles of channel improvement, 9.2 miles of levee 
construction, part of channel improvement landscaping, 
and Drop Structures No. 1 and 2 have been transferred 
to local interests for operation and maintenance. Planning 
and design continued on remaining reaches. Work 
remaining consists of channel improvement on Walnut 
Creek (SPRR bridge to Broadway Avenue) and San 
Ramon bypass (Ignacio Valley Road to Rudgear Road 
along SPRR alignment) and Upper Pine Creek. 
Construction responsibility was transferred from 
San Francisco District on April 1, 1982. 
15. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Approved regulations for operation and maintenance 
of flood control works, part 208, title 33, Code of Federal 
Regulations, provide for inspection of completed projects 
transferred to local interests for operation and maintenance 
to determine status of project and insure compliance 
with regulations. During fiscal year, inspections 
were made of: Completed units of Sacramento River 
and major and minor tributaries; completed units of 
Sacramento River flood control project, Kings River 
Channel Improvement (Pine Flat Lake project), and 
Walnut Creek project; American River levees; Chester, 
North Fork Feather River; levee and channel improvements 
on Chowchilla River (Buchanan project) and 
Fresno River (Hidden project); Duck Creek diversion, 
Green Valley Creek, Littlejohn Creek, Mormon Slough, 
Bear Creek, and North Fork, Pit River at Alturas, all in 
California; Truckee River, CA and NV; completed units 
of lower San Joaquin River and tributaries, CA; Big 
Dry Creek Dam and diversion, CA; Reese River, Battle 
Mountain, NV; Sevier River, Redmond and vicinity, 
Jordan River, Big Wash near Milford, and Kays Creek, 
all in Utah; various emergency flood control works 
under authority of sec. 208, Flood Control Act of 
June 30, 1948, and September 3, 1954; Public Law 99, 
June 28,1955, and antecedent legislation; and sec. 14 of 
Flood Control Act of July 24,1946. Maintenance inspections 
conducted indicate that existing agreements and 
regulations are being complied with on completed flood 
control works. Continuing effort is required to improve 
maintenance practices and active steps are being taken 
by responsible State and local agencies to achieve 
desired results. Local agencies were advised, as necessary, 
of measures required to maintain these projects in 
accordance with standards prescribed by regulations. 
Total cost of inspection for fiscal year of $1,073,283 
included continuation of dam safety assurance program 
for Folsom Lake, CA ($951,889). 
35-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
16. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control activities pursuant to sec. 205, Public 
Law 858, 80th Congress, as amended (Preauthorization). 
Costs for preauthorization studies for fiscal year were 
$149,923 for Berryessa Creek, CA, (project responsibility 
transferred to Sacramento District April 1, 1982). 
Emergency flood control activities-repair, flood 
fighting, and rescue work (Public Law 99, 84th 
Cong., and antecedent legislation). 
Federal cost for fiscal year was $5,854,005, of which 
$120,555 was for disaster preparedness, $2,485,508 for 
flood emergency operations, $317,155 for repair and 
restoration, and $2,930,787 for advance measures. 
Emergency bank protection (sec. 14, 1946 Flood 
Control Act, Public Law 526, 79th Cong.). 
Federal cost for fiscal year was $24,653. Bank protection 
was continued, Mormon Slough, Jack Tone Road, 
CA ($11,094), and on Sutter Creek near lone, CA 
(reconstruction of revetment displaced by high flows) 
($13,559). 
Snagging and clearing navigable streams and 
tributaries in interest of flood control (see. 208,1954 
Flood Control Act, Public Law 780, 83d Cong.). 
No snagging and clearing activities this fiscal year. 
Flood insurance activities (see. 1301-1877, 1968 
Housing and Urban Development Act, Public Law 
90-448 as amended). 
In coordination with flood control activities, two flood 
insurance studies were initiated in accordance with 
Inter-Agency Agreements EMW-E-1153 and EMW-E- 
0941 at a fiscal year cost of $43,529 under Federal 
Emergency Management Agency reimbursable order. 
17. SCHEDULING FLOOD CONTROL 
RESERVOIR OPERATIONS 
In accordance with sec. 7, Flood Control Act of 1944, 
summaries of monthly operations at Big Dry Creek, 
Boca, Camanche, Del Valle, Folsom, Friant (Millerton 
Lake), Indian Valley, Los Banos Detention, New Bullards 
Bar, New Don Pedro, New Exchequer (Lake McClure), 
New Melones, Oroville, Prosser, Shasta, and Stampede, 
CA; East Canyon, Echo, Lost Creek, Pineview, Starvation, 
and Wanship, UT; Blue Mesa, Lemon, Peonia, and 
Vallecito, CO; and Navajo, NM reservoirs were prepared. 
A revision to the Truckee River Basin reservoir 
control manual (which includes Boca, Stampede, and 
Prosser Reservoirs) and a revision to the Los Banos 
Detention Reservoir water control manual were initiated 
in FY 1983. Corps personnel provided advice as requested 
during flood control operations at all sec. 7 
reservoirs. Fiscal year cost was $307,706. Total cost to 
September 30, 1983, $2,117,994. 
Multiple-Purpose Projects including Power 
18. NEW MELONES LAKE, CA 
Location. On Stanislaus River about three-quarters 
mile downstream from existing Melones Dam and 
about 35 miles northeast of city of Modesto. (See 
Geological Survey quadrangles of the area.) 
Existing project. Provides for construction of (a) an 
earth and rockfill dam about 625 feet high to create a 
reservoir with gross storage capacity of about 2,400,000 
acre-feet for flood control, irrigation, power, general 
recreation, fish and wildlife, and other purposes, and (b) 
a powerplant below the dam with an installed capacity 
of 300,000 kilowatts. Upon completion of construction of 
dam and powerplant by the Corps, the project became 
an integral part of Central Valley project and is being 
operated and maintained by the Secretary of the Interior 
pursuant to Federal reclamation laws, except that the 
flood control operation of the project shall be in accordance 
with rules and regulations prescribed by the 
Secretary of the Army. Maintenance of Stanislaus 
River channel from Goodwin Dam to San Joaquin River 
to a capacity of at least 8,000 cubic feet per second will 
also be Corps responsibility. Approved estimated (October 
1983) Federal cost is $378,000,000 (includes an 
allowance for estimated inflation through the construction 
period). For future non-Federal reimbursement, 
see Local cooperation paragraph. In addition, local 
interests expended $300,000 for levees along lower 
reaches of Stanislaus River. Existing project was adopted 
by 1962 Flood Control Act (H. Doc. 453, 87th Cong., 
2d sess., contains latest published map). This act modified 
original authorization adopted by 1944 Flood 
Control Act. (H. Flood Control Committee Doc. 2, 78th 
Cong., 2d sess., contains latest published map.) The 
1944 Flood Control act established $8 million monetary 
limitation for partial accomplishment of project. Further 
monetary authorizations of $2.5 million, $5 million, 
$13 million, $2 million, $17 million, $18 million, $44 
million, $83 million, $46 million, $6 million, and $61 
million were provided for this project by Public Laws 
235 and 780, 83d Cong., and 85-500, 90-17, 90-483, 
91-282, 92-222, 93-251, 94-397, 95-104, and 95-189, 
making a total monetary authorization of $305,500,000 
available for the basin plan comprising Lower San 
Joaquin River and tributaries, including Tuolumne and 
Stanislaus Rivers, CA. Since FY 1979, appropriations 
have not been subject to the river basin monetary 
limitation and legislation is before Congress to eliminate 
the monetary limitation ceiling. 
Local cooperation. Based on approved preliminary 
cost allocation studies (July 1965) local interests will be 
required to pay 35.2 percent of first cost and 12.7 
percent of annual operation and maintenance costs 
allocated to irrigation. In addition, 31.1 percent of first 
cost and 62.5 percent of annual cost would be allocated 
to power. Local interests must also maintain existing 
private levees along Stanislaus River from Goodwin 
Dam to San Joaquin River and prevent encroachment 
35-14

SACRAMENTO, CALIFORNIA DISTRICT 
on channel and floodway between levees to preserve 
safe carrying capacity throughout the reach of at least 
8,000 cubic feet per second. Recovery of costs allocated 
to irrigation and power will be the responsibility of the 
Bureau of Reclamation. Reimbursement of costs will be 
in accordance with Bureau policies and procedures for 
the Central Valley project. State of California officially 
adopted project by chapter 918 of statutes of 1963, and 
by chapter 1438 of those statutes authorized State 
Reclamation Board to furnish required assurances. The 
Board, by letter dated December 13, 1963, stated it 
would furnish required assurances when formally 
requested to do. Assurances were requested by letter of 
December 30, 1977. On October 2, 1979, the Board 
reaffirmed its intent to furnish the required assurances. 
Operations and results during fiscal year. New 
work: Engineering activities continued including continuation 
of plans and specifications for the Lower 
Stanislaus recreation areas, minimal recreation facilities 
only. Fiscal year costs for major items of work 
included: Continuation of land acquisition activities, 
$364,474; continuation of operations access road, 
$1,194,251; continuation of Glory Hole Phase I recreation 
area contract $1,749,118; and completion of Tuttletown 
Phase I recreation area contract, $113,682. Maintenance: 
Maintenance and operation activities continued on 
Lower Stanislaus River. Project prevented an estimated 
$12,700,000 in damages from the December 1982-April 
1983 rainfloods. 
Historical summary. Construction was initiated in 
August 1966. Main dam contract which was awarded in 
March 1974 has been completed; dam dedication ceremonies 
were held July 14, 1979. Cultural resources 
preservation contract, water intake facilities contract, 
flood control and irrigation tailrace modification contract, 
reservoir area clearing contract, Tuttletown Phase 
I recreation area contract, and Oakdale recreation 
contract have been completed. Glory Hole recreation 
area contract and operations access road contract have 
been initiated. Overall project is nearing completion 
except for Lower Stanislaus River recreation facilities. 
Remaining recreation facilities were unscheduled pending 
development of cost sharing agreements with local 
interests. A Memorandum of Understanding between 
the Department of the Interior and the Department of 
the Army transferring the New Melones dam and 
reservoir from the Corps of Engineers to the Bureau of 
Reclamation was executed on November 20, 1979. 
Agreement provides that the Corps complete land 
acquisition actions and retain budgeting, design, and 
construction responsibility for reservoir clearing and 
recreation development; completion of cultural resources 
mitigation in project area was vested in the Department 
of the Interior. The California State Water Resources 
Control Board's Decision 1422 of April 1973 established 
conditions which impacted on the planned filling and 
operation of the project by the Department of the 
Interior. As a result, the Departmentof Interior brought 
suit against the State of California claiming State 
limitations on project operation were contrary to Congressional 
intent and authority. The case was heard 
before the U.S. District Court in Fresno, CA, and in 
early March 1981, a Federal judge ruled that the 
Federal Government could fill the New Melones reservoir 
for purpose of generating electrical power, but not 
for agricultural or other purposes. Both the Government 
and the California State Resources Control Board 
appealed this decision to the 9th Circuit Court of 
Appeals in San Francisco, CA. 
On December 20, 1982, the Court upheld all 25 
requirements placed on the Federal Government by the 
State Water Resources Control Board. The decision 
reversed the lower court's decision to permit filling of 
the reservoir for generating electrical power. The 
Bureau of Reclamation subsequently filed for a permit 
from the State Water Resources Control Board to fill 
the reservoir. Permit was approved. The Bureau had 
originally started generating power on a limited basis 
on July 1, 1979; however, after the filling of the 
reservoir in spring of 1983, full power generating 
benefits are being attained. Project is about 93 percent 
complete. 
General Investigations 
19. Surveys 
See table 35-N. 
MORRISON CREEK STREAM 
GROUP, CA (PHASE I, FEASIBILITY 
STUDY) 
Phase I studies (estimated cost $3,000,000) were 
authorized by sec. 101(a), Water Resources Development 
Act, of 1976, in accordance with Report of Chief of 
Engineers, March 2, 1976. Proposed plan of improvement 
would be located on streams in Morrison Creek 
Stream Group Basin in the central part of Sacramento 
County and would provide for construction of a dam 
with an 11,000 acre-foot reservoir at the Vineyard site 
on Elder and Laguna Creeks, diversion of Morrison 
Creek flows into this reservoir, construction of 26 miles 
of levee and 66 miles of channel work along streams in 
the basin, and purchase of lands and related construction 
for a 7,800-acre flood retardation basin in the Beach- 
Stone Lakes area. Phase I studies were continued at a 
fiscal year cost of $583,786. 
CONTINUATION OF PLANNING 
AND ENGINEERING 
CACHE CREEK BASIN, CA 
Project is located on eastern slope of the Coast Range. 
Clear Lake unit is about 110 miles north of San 
Francisco and Settling unit is about 15 miles northwest 
of Sacramento. 
Plan of improvement consists of two project units: 
Upper basin at Clear Lake-widening and/or deepening 
35-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
3.3 miles of existing 5 mile long Clear Lake outlet 
channel to a capacity of 8,000 cubic feet per second, 
constructing a 1.1 mile long bypass channel around the 
highly developed area adjacent to existing channel, and 
nonstructural measures; and lower basin at the mouth 
of Cache Creek-enlarging existing perimeter levees of 
Cache Creek Settling Basin an average of 12 feet to 
provide 50 years of sediment storage capacity and 
enlarging existing project levees from settling basin 
mouth upstream to County Road 102, reconstructing 
and enlarging existing Cobble weir, degrading the 
existing training levees and rebuilding them adjacent 
to the western perimeter levee to allow utilization of 
entire basin for sediment deposition, purchasing in fee 
3,600 acres of existing settling basin and establishing a 
wildlife refuge and nonstructural measures. 
Preconstruction planning estimate is $2,000,000. Continuation 
of planning and engineering (including a 
sedimentation study) was initiated at a fiscal year cost 
of $67,392. 
REDBANK AND FANCHER CREEKS, CA 
Project is located northeast of Fresno-Clovis metropolitan 
area in Fresno County, CA. 
Plan of improvement includes flood control detention 
basins on Redbank Creek, Pup Creek, and Alluvial 
Drain; construction of a flood control reservoir on 
Fancher Creek; and enlargement of Big Dry Creek 
project to provide increased flood protection and recreation 
opportunities. 
Estimated preconstruction planning cost is $3,800,000. 
General Design Memorandum studies including 
environmental, hydrology, real estate, cultural resources, 
and foundation exploration (including fault 
evaluation) studies and surveys were continued at a 
fiscal year cost of $520,441. 
SACRAMENTO RIVER DEEP WATER 
SHIP CHANNEL, CA 
Plan of improvement consists primarily of deepening 
to 35 feet the Suisun Bay and Sacramento River Deep 
Water Ship Channels from New York Slough to Port of 
Sacramento, and the Avon to New York Slough reach to 
35 feet which wil be accomplished under the San 
Francisco Bay to Stockton (John F. Baldwin and Stockton 
Ship Channels) project. 
Selected plan also provides for a water quality monitoring 
program, authority to construct a submerged 
sill, 45 acres of land for establishment of wetland 
habitat, and 156 acres of land for upland habitat to 
mitigate for losses of such habitat. 
Preconstruction planning estimate is $3,500,000. Continuation 
of planning and engineering (including explorations 
and water quality studies, and a Bay-Delta Model 
repeatibility test) was continued at a fiscal year cost of 
$599,416. 
20. COLLECTION AND STUDY OF 
BASIC DATA 
Technical assistance was performed for other Federal 
agencies as well as non-Federal agencies in connection 
with Flood Plain Management Services Program at 
fiscal year cost of $367,205. No Flood Plain Information 
Studies were prepared after FY 1980. 
Fiscal year costs for hydrologic studies were $8,000. 
21. RESEARCH AND DEVELOPMENT 
The Hydrologic Engineering Center was designated 
as a separate Field Operating Agency as of January 1, 
1979, in accordance with OCE permanent orders 1-1, 
January 10,1979, but Sacramento District is continuing 
to provide advisory and administrative support services 
to HEC as specified in local support agreement 
DACWO5-79-A-0038 of March 1979. Fiscal year costs 
were $1,083,130, of which $176,200 was for planning 
methodologies, $673,530 was for analytical techniques, 
$175,600 for Water Conservation and Supply, and 
$57,800 for earth resources satellites, all at the Hydrologic 
Engineering Center. 
22. ADVANCE ENGINEERING AND 
DESIGN 
COTTONWOOD CREEK, CA 
Project will be located on main stem and the North, 
South, and Middle Forks of Cottonwood Creek on 
eastern slope of the Coast Range and southern slope of 
Trinity Range between cities of Redding and Red Bluff, 
CA, and was authorized by the 1970 Flood Control Act 
(Document not yet printed). 
Plan of improvement provides for two multiplepurpose 
reservoirs, one at Dutch Gulch (capacity 900,000 
acre-feet) and one at Tehama (capacity 700,000 acrefeet), 
and includes base facilities for future installation 
of hydropower generating equipment. 
General Design Memorandum and Environmental 
Impact Statement were completed. Estimated preconstruction 
planning estimate is $20,900,000. 
PAJARO RIVER BASIN, CA 
Pajaro River and tributaries drain an area of 1,300 
square miles in the Coast Range and empty into Monterey 
Bay about 75 miles south of San Francisco. Pajaro 
Valley sub-basin in Santa Cruz and Monterey Counties 
includes 112 square miles in lower 13 miles of Pajaro 
River. 
Plan of improvement consists of construction of a 
variable setback levee beginning approximately 1,000 
feet upstream of Miller Avenue and ending 2,000 feet 
below Thomas Road Bridge on north side of Uvas 
Creek. 
Phase I General Design Memorandum and Environmental 
Impact Statement was completed by San Fran- 
35-16

SACRAMENTO, CALIFORNIA DISTRICT 
cisco District in FY 1982. A Post Authorization Change 
was approved by the Office of Chief of Engineers on 
August 4, 1982. Responsibility for remaining portions 
of advance engineering and design, plans and specifications 
and construction was transferred to the Sacramento 
District in April 1982. Preparation of Phase II General 
Design Memorandum was initiated (including surveys) 
at a fiscal year cost of $95,129. Estimated preconstruction 
planning cost is $450,000. 
MERCED COUNTY STREAMS, CA 
Project will be located on streams draining from 
Mariposa County foothills of Sierra Nevada into Merced 
County in vicinity of city of Merced, CA. Project is 
modification of Merced County Stream Group, CA, 
Improvement No.11, authorized by 1944 Flood Control 
Act and completed FY 1957. Project providing for 
construction of three new reservoirs-Castle, Haystack 
Mountain, and Marguerite on Canal, Black Rascal, and 
Deadman-Dutchman Creeks, respectively, and enlargement 
of four existing reservoirs-Burns, Bear, Owens, 
and Mariposa, was authorized by 1970 Flood Control 
Act (Document not yet printed). 
Current plan of improvement would defer enlargement 
of existing Burns reservoir, Mariposa reservoir, construction 
of Marguerite Dam, and the irrigation function 
associated with the latter two facilities, enlargement of 
existing Owens reservoir and about 32 miles of levee 
and channel improvement on Owens, Mariposa, and 
Deadman-Dutchman Creeks. 
Phase I General Design Memorandum was approved 
February 1982 and Phase II General Design Memorandum 
was approved June 1982. Channel Improvement 
Design Memorandum was initiated. Estimated preconstruction 
planning cost is $6,350,000. 
35-17

TABLE 35-A 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 80 FY 81 FY 82 FY 83 Sep 30, 1983 
1. Sacramento River, 
CA 
2. San Francisco Bay 
to Stockton, CA 
John F. Baldwin and 
tockton Ship 
Channels) 
3. San Joaquin River, 
CA 
4. Buchanan Dam-H.V. 
Eastman Lake, 
Chowchilla River, CA 
(Federal Funds) 
Contributed Funds, 
ther) 
5. Calaveras River and 
Littlejohn Creek and 
Tributaries including 
New Hogan Lake and 
Farmington Dam, CA 
(Federal Funds) 
Contributed Funds, 
Other) 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
6. Corte Madera Creek, CA New Work 
(Federal Funds) Approp. 
Cost 
Required Contributed New Work 
Funds) Cost 
7. Hidden Dam-Hensley New Work 
Lake, Fresno Approp. 
River, CA Cost 
(Federal Funds) Maint. 
Approp. 
Cost 
Contributed Funds, New Work 
Other) Contrib. 
Cost 
8. Isabella Lake, Kern New Work 
River, CA Approp. 
(Federal Funds) Cost 
Maint. 
Approp. 
Cost 
Contributed Funds, New Work 
Other) Contrib. 
Cost 
- 40,331,1921 
- 40,331,1921 
1,682,200 2,597,300 2,927,000 
290,722 3,480,162 3,057,288 
585,000 850,000 1,574,000 
609,722 647,007 1,437,564 
415,000 -79,000 
397,979 -61,787 
- 60,000 
31,149 41,050 
570,000 647,000 
550,952 598,841 
51,515 
969,000 
936,875 
3,540 
13,402 
42,078 
769,000 
704,757 
1,514,000 
618,949 
6,700,000 
3,890,097 
34,424,8312 
33,147,6628 
17,683,0004 
14,446,217s 
5,833,1176 
5,833,1176 
20,000 943,000 10,452,4767 
18,645 892,679 10,400,6907 
- 27,369,597 
33 27,369,597 
830,000 
766,878 
4,250,500 
4,048,015 
111,1878 
111,1878 
- 23,723,1449 
- 23,723,14410 
841,000 921,000 945,000 
765,773 915,116 923,280 
- - 10,000 
- - 2,248 
- - 35,000 
- - 34,868 
9,381,16911 
9,235,62712 
1,304,25113 14 15 
1,296,49913 14 16 
7,034,72517 
7,034,59318 
106,09519 20 
97,40021 
- 30,555,426 
- 30,555,426 
632,000 1,499,000 1,216,000 510,000 5,242,500 
591,310 946,240 1,456,926 742,736 5,110,697 
- - - - 165,1122 
- - - - 165,1122 
-10,000 
5,762 
1,153,000 
1,087,662 
- - - 24,450,53723 25 
- - - 24,450,53724 25 
1,550,000 1,461,640 2,227,400 15,790,99826 
1,596,512 1,244,401 1,924,520 15,248,687 7 
438,00028 
438,00028 
35-18

SACRAMENTO, CALIFORNIA DISTRICT 
TABLE 35-A (Cont'd) COST AND FINANCIAL STATEMENT 
See 
Section 
in Text Project 
9. Kaweah and Tule 
Rivers including 
Terminus Dam and 
Success Lake, CA 
Contributed Funds, 
Other) 
10. Martis Creek Lake, 
Martis Creek, NV, 
and CA 
11. Merced County Stream 
Group, CA 
12. Pine Flat Lake and 
Kings River, CA 
(Federal Funds) 
Contributed Funds, 
Other) 
13. Sacramento River and 
Tributaries, CA 
from Collinsville to 
Shasta Dam 
(Federal Funds) 
Required Contributed 
Funds) 
Contributed Funds, 
ther) 
14. Walnut Creek, CA 
(Federal Funds) 
Required Contributed 
Funds) 
Contributed Funds, 
Other) 
18. Lower San Joaquin 
River and 
Tributaries, CA 
including fuolumne 
MdoSta kC 
Mel1ne ake,eCA 
Funding 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Total Cost to 
FY 80 FY 81 FY 82 FY 83 Sep 30, 1988 
1, 
1, 
1, 
1, 
1, 
1, 
1, 
1, 
11, 
10, 
- - - - 34,997,230 
- - - - 34,997,230 
,729,000 1,575,000 1,616,000 1,850,000 15,904,525a 
,718,138 1,532,424 1,534,147 1,660,695 15,537,731 s' 
- - - - 42,420 
- - - - 42,420 
- - - - 8,504,989" 
- - - - 8,504,989" 
160,000 210,000 192,000 243,000 2,135,350 
152,515 217,492 192,004 165,188 2,046,292 
- - - - 2,751,2598 
- - - - 2,751,259"84 
117,700 81,000 89,000 120,000 1,182,506 
125,290 69,548 66,942 100,652 1,127,295 
250,000 - - - 43,356,265" x8 
271,440 - - - 48,856,265w 87 88 
,686,000 1,232,000 1,337,000 1,498,000 13,827,285" 
,657,512 1,187,602 1,383,372 1,381,523 13,645,768 
- - - - 110,00041 
- - - - 110,00041 
,841,000 3,215,000 3,726,000 2,150,000 80,133,508 42 43 
516,498 3,564,715 2,759,156 1,925,392 78,783,242 42 44 
938,000 826,000 1,589,000 1,154,000 9,637,334@ 
921,588 787,350 1,159,591 1,554,463 9,508,964# 
350,000 463,000 950,000 752,000 14,737,538 
341,003 775,433 1,011,197 97,482 14,011,732 
- - - 10,000 2,452,36247 
- - - 4,428 2,446,7904 4 
,000,000 5,045,000 5,965,000 4,050,000 36,241,429"� 
,115,815 4,454,990 4,971,022 4,119,569 34,638,96751 
- - 482,688 928,624 3,064,0826 
123,572 22,194 393,269 800,233 2,842,346" 
31,700 42,000 232,200 781,026 2,243,071" 
73,375 29,080 177,082 877,114 2,238,3118 
,461,692 9,000,000 12,700,000 6,849,000 331,037,996" 
,716,483 9,828,850 12,207,662 5,825,274 329,075,357x7 
191,000 311,000 388,000 410,000 1,512,000 
189,147 311,609 361,647 368,700 1,433,505 
35-19 
.

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 35-A (Cont'd) COST AND FINANCIAL STATEMENT 
1. Includes the following amounts for new work: Regular 
funds: Previous project, $185,198; existing project, $585,436 
for shallow-draft and $39,560,558 for deep-draft. 
2. Includes the following funds for maintenance: Regular 
funds: Previous project, $553,720; existing project, $15,287,907 
for shallow-draft and $18,513,204 for deep-draft; and deferred 
maintenance funds, $70,000 for shallow-draft. 
3. Includes the following costs for maintenance: Regular 
funds: Previous project, $553,720; existing project, $15,217,250 
for shallow-draft and $17,306,692 for deep-draft; and deferred 
maintenance funds, $70,000 for shallow-draft. 
4. Includes $10,340,800 funds for Sacramento District 
and $7,342,200 for San Francisco District. 
5. Includes $7,404,133 costs for Sacramento District and 
$7,042,084 for San Francisco District. 
6. Includes $1,158,348 public work funds, of which $207,198 
was for work done along 30-foot channel in Suisun Bay 
Channel; excludes $19,000 expended for engineering for 
inactive portion of 1950 modification. In addition, $1,342,500 
was expended from required contributed funds. 
7. In addition, $1,250 was expended from required contributed 
funds. 
8. Contributed funds, other, from State of California for 
design and construction of downstream channel improvements 
on Ash and Berenda Sloughs below Buchanan Dam. 
9. Includes Code 710 funds for recreation facilities at 
New Hogan Lake: $140,000 for FY 1979: Total to date 
$897,742. 
10. Includes Code 710 costs for recreation facilities at New 
Hogan Lake: $124,111 and $51,515 for fiscal years 1979 and 
1980, respectively. Total to date $897,742. 
11. Includes $99,000 special recreation use fees at New 
Hogan Lake. 
12. Includes $99,000 special recreation use costs at New 
Hogan Lake. 
13. For miscellaneous construction under local cooperation 
requirements, primarily Bear Creek, San Joaquin County; 
includes $108,056 as related to Duck and Littlejohn Creeks 
channel improvements as part of Farmington Dam project 
unit. 
14. Includes $393,195 contributed funds, other, from California 
Department of Boating and Waterways for design and 
construction of boat launching and related facilities, and 
$30,000 for design and construction of a boarding float at 
North Shore recreation area at New Hogan Lake. 
15. Includes $10,000 contributed funds, other, from 
Calaveras County Water District for New Hogan hydropower 
studies. 
16. Includes $2,247 contributed funds, other, costs for 
New Hogan hydropower studies. 
17. Includes $6,999,725 San Francisco District construction 
funds. 
18. Includes $6,999,725 San Francisco District construction 
costs. 
19. $8,695 contributed funds transferred to Sacramento 
District in FY 1983. 
20. Includes $97,400 San Francisco District required 
contributed funds. 
21. Includes $97,400 San Francisco District required 
contributed costs. 
22. Contributed funds, other, from State of California for 
miscellaneous design and construction at Hidden Dam. 
23. Includes total Code 710 funds for recreation facilities 
at Isabella Lake: -$200,000 and -$10,000 for fiscal years 1979 
and 1980, respectively. Total to date $2,199,085. 
24. Includes total Code 710 costs for recreation facilities at 
Isabella Lake: $477,593 and $5,762 for fiscal years 1979 and 
1980, respectively. Total to date $2,199,085. 
25. Includes $224,000 Code 713 funds and costs for 
improvement at Tillie Creek and Live Oak campgrounds. 
26. Includes $201,640 special recreation use fees at Isabella 
Lake. 
27. Includes $201,640 special recreation use costs at 
Isabella Lake. 
28. Funds from California Department of Boating and 
Waterways for design and construction of boat launching and 
related facilities at Old Isabella Road and Isabella Peninsula. 
29. Includes Code 710 funds and costs for recreation 
facilities: Success Lake: Total to date $747,048. Terminus 
Dam: Total to date $700,004. 
30. Includes $165,000 special recreation use fees at Success 
Lake. 
31. Includes $165,000 special recreation use costs at Success 
Lake. 
32. Funds from State of California Department of Boating 
and Waterways and costs for acquisition of a boarding float at 
Success Lake, $30,000 and at Terminus Dam, $12,420. 
33. Includes $1,200, initiation of plans and specifications 
for Code 710 recreation facilities, for FY 1978. Construction of 
recreation facilities at Martis Creek Lake under Code 710 was 
determined to be infeasible. 
34. In addition, $66,532 expended for new work from 
contributed funds, other, for miscellaneous construction under 
local cooperation requirements as related to acquisition of 
rights-of-way and utility alterations for project. 
35. Includes Code 710 funds for recreation facilities at 
Pine Flat Lake: $110,000 and $250,000 for fiscal years 1979 
and 1980, respectively. Total to date $1,595,100. 
36. Includes Code 710 costs for recreation facilities at Pine 
Flat Lake: $753,825 and $271,440 for fiscal years 1979 and 
1980, respectively. Total to date $1,595,100. 
37. Includes Public Works Acceleration, Executive (PL 
87-658) (Transfer to Corps of Engineers, Civil) 1963 funds for 
recreation facilities: Total appropriations $239,235 and total 
costs $239,235. 
38. Includes $19,600 Code 713 funds and costs for Pine 
Flat fish barrier. 
39. Includes $158,300 special recreation use fees at Pine 
Flat Lake. 
40. Includes $158,300 special recreation use costs at Pine 
Flat Lake. 
41. Miscellaneous construction and engineering and design 
services (non-project) accomplished at expense of State of 
California under local cooperation requirements in connection 
with acquisition of rights-of-way and utility alterations at 
Pine Flat Lake. 
42. Excludes $614,608 for Table Mountain (Iron Canyon) 
project, deauthorized August 5, 1977, and $531,000 for Sacramento 
River and Major and Minor Tributaries portions which 
are considered inactive and deferred. 
43. Includes Code 710 funds for recreation facilities at 
Black Butte Lake: $60,000 and $110,000 for fiscal years 1979 
and 1980, respectively. Total to date $1,000,162. 
44. Includes Code 710 costs for recreation facilities at 
Black Butte Lake: $51,857, $212,747, and $2,868 for fiscal 
years 1979,1980, and 1981, respectively. Total to date $1,000,162. 
45. Includes $104,100 special recreation use fees at Black 
Butte Lake. 
46. Includes $104,100 special recreation use costs at Black 
Butte Lake. 
47. Miscellaneous construction and engineering and design 
services (non-project) accomplished at expense of State of 
California under local cooperation requirements in connection 
with acquisition of rights-of-way and utility alterations (primarily 
for Sacramento Rivet and major and minor tributaries 
project). Includes State Highway Commission payment, 
789,008, for use of excess excavation from Chico and Mud 
reeks and Sandy Gulch (Sacramento River and Major and 
Minor Tributaries) for freeway embankment through city of 
Chico. 
35-20

SACRAMENTO, CALIFORNIA DISTRICT 
TABLE 35-A (Cont'd) COST AND FINANCIAL STATEMENT 
48. Includes $7,984, contributed funds, other, from State 
of California for required modification of existing private 
facilities, Sacramento River, Chico Landing to Red Bluff; 
$15,977 contributed funds, other, from State of California 
Department of Boating and Waterways for replacing a 
boarding float at Orland Buttes boat launching ramp at Black 
Butte Lake; and $10,000 contributed funds, other, from the 
city of Santa Clara for hydropower studies at Black Butte 
Lake. 
49. Includes $4,428 contributed funds, other, costs for 
Black Butte hydropower studies. 
50. Includes 8,849,825 San Francisco construction funds. 
51. Includes 9,049,609 San Francisco construction funds. 
52. Includes $450,268 San Francisco required construction 
funds. 
TABLE 35-A COST AND FINAN 
ADVANCE ENGINE 
53. Includes $525,846 San Francisco required construction 
funds. 
54. Includes $400,348 San Francisco contributed funds, 
other. 
55. Includes $400,348 San Francisco contributed funds, 
other, costs. 
56. Excludes funds applicable to other units of this basin 
authorization (Lower San Joaquin River and tributaries and 
Tuolumne River Basin, Calif.) (See table 35-E). 
57. Includes $110,000 utilized for preparation of 1957 
Economic Feasibility Report and of Revised Feasibility 
Report (FY 1960,1961, and 1962) applicable to 1962 reauthorization 
of project. 
CIAL STATEMENT 
ERING AND DESIGN 
See 
Section Total Cost to 
in Text Project Funding FY 80 FY 81 FY 82 FY 83 Sep 30, 1983 
Cottonwood Creek, New Work 
CA Approp. 1,250,000 1,650,000 3,150,000 3,375,000 11,875,0001 
Cost 1,111,715 1,773,318 3,088,134 2,667,898 11,235,5322 
Pajaro River New Work 
Basin, CA Approp. 135,000 - - 190,000 2,139,9688 
Cost 62,627 67,159 17,228 95,129 2,045,0974 
Merced County New Work 
Streams, CA Approp. 655,000 1,350,000 1,344,000 500,000 6,350,000b 
Cost 777,725 1,368,594 1,317,691 522,953 6,343,7596 
1. Includes $6,175,000 General Investigation funds. 4. Includes $1,949,968 San Francisco construction costs. 
2. Includes $5,536,531 General Investigation costs. 5. Includes 1,034,000 General Investigation funds. 
3. Includes $1,949,968 San Francisco construction funds. 6. Includes $1,034,000 General Investigation costs. 
TABLE 35-B AUTHORIZING LEGISLATION 
See Date 
Section in Authorizing 
Text Act Project and Work Authorized Documents 
Mar. 3, 1899 
July 25, 1912 
Jan. 21, 1927 
Aug. 30, 1935 
Aug. 30, 1935 
SACRAMENTO RIVER, CA 
A depth of 7 feet below Sacramento 
For work above Sacramento. 
The 10-foot channel up to Sacramento. 
A depth of 6 feet between Sacramento and Colusa and 5 feet 
between Colusa and Chico Landing, at a cost of $390,000 
provided flow of rivers is increased to minimum flow of 
5,000 cubic feet per second after Shasta Reservoir is built. 
Authority for a special direct participation of Federal 
Government of $12 million in cost of Shasta Reservoir. 
H. Doc. 186, 55th Cong., 
2d sess., and 48, 55th 
Cong., 3d sess. (Annual 
Report 1898, p. 2844 
and 1899, p. 3171). 
H. Doc. 76, 62d Cong., 
1st sess' 
H. Doc. 123, 69th Cong., 
1st sess. 
Rivers and Harbors 
Committee Doc. 35, 
73d Cong., 2d sess. 
Rivers and Harbors 
Committee Doc. 35, 
73d Cong., 2d sess. 
35-21 
1.

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 35-B (Cont'd) AUTHORIZING LEGISLATION 
See Date 
Section in Authorizing 
Text Act Project and Work Authorized Documents 
Aug. 26, 1937 
July 24, 1946 
Transfer of authority for expenditure of above $12 million 
from Secretary of War to Secretary of the Interior. 
Modified existing navigation project for Sacramento River, S. Doc. 142, 79th Cong., 
CA, to provide for construction of a ship channel 30 2d sess. 
feet deep and 200 to 300 feet wide from deep water in 
Suisun Bay to Washington Lake, including such works as 
may be necessary to compensate for or alleviate any 
detrimental salinity conditions resulting from ship channel; 
a triangular basin of equal depth, 2,400 by 2,000 by 3,400 
feet at Washington Lake; and connecting channel 13 feet 
deep and 120 feet wide, with lock and drawbridge, thence to 
Sacramento River. 
Oct. 23, 1962 
Nov. 7, 1966 
Dec. 22, 1944 
May 17, 1950 
July 3, 1958 
July 3, 1958 
July 14, 1960 
May 12, 1967 
Mar. 7, 1974 
June 19, 1975 
CORTE MADERA CREEK, CA 
Levees and channel improvements, lower 11 miles of Corte 
Madera Creek and tributaries, as modified by Chief of 
Engineers. 
Local cooperation requirements modified to provide 1.5 
percent cash contribution toward cost of Ross Valley unit. 
SACRAMENTO RIVER AND TRIBUTARIES, CA, 
FROM COLLINSVILLE TO SHASTA DAM 
Modify Sacramento River Flood Control Project to provide 
for extensions in levees and other structures along 
Sacramento River and major and minor tributaries; 
construct Black Butte Dam and Reservoir; construct lowlevel 
Table Mountain Dam and Reservoir with power 
facilities; and provision of monetary authorization of $15 
million for initiation of modification. 
Improvement for protection of Upper Butte Basin (included 
full monetary authorization). 
Extend existing Sacramento River Flood Control Project to 
Keswick Dam for purposes of zoning area below dam and 
modification of project by construction of bank protection 
and incidental channel improvements between Chico 
aLuatnhdoirnigz aatinodn )R. ed Bluff (included full monetary 
Additional authorization of $17 million for comprehensive 
plan approved in act of December 22, 1944. 
Further modification of Sacramento River Flood Control 
Project by construction of initial 10-year phase of 
bank erosion control works and setback levees on 
Sacramento River and authorization of $14,240,000 for 
prosecution of modification. 
Additional authorization of $7 million for bank protection 
approved in act of July 14, 1960. 
Initiation of construction of second phase of bank erosion 
control works and setback levees on Sacramento River as 
approved in act of July 14, 1960, and additional 
authorization of $16 million for such purpose.s 
Deauthorization of Table Mountain Dam and Reservoir4 
H. Doc. 545, 87th Cong., 
2d sess. 
Sec. 204, 1966 Flood 
Control Act. 
H. Doc. 649, 78th Cong., 
2d sess.2 
H. Doc. 367, 81st Cong., 
1st sess. 2 
H. Doc. 272, 84th Cong., 
2d sess.2 
S. Doc. 103, 80th Cong., 
2d sess.2 
PL 90-17 
PL 93-251 
H. Doc. 94-192, 94th 
Cong., 1st sess. 
1. Contains latest published ma of section above Sacramento. 
For map of section below Sacramento, see H. Doc. 
1123, 60th Cong. 2d sess. and S. Doc. 142, 79th Cong., 2d sess. 
2. Contains latest published map. 
3. Total monetary authorization available, exclusive of 
preauthorization studies from general investigations appropriations, 
amounts to $72,740,000. 
4. The 90-day Congressional project review period, required 
by sec. 12, PL 93-251, as amended by sec. 157, PL 
94-587, ended August 5,1977, and resulted in deauthorization 
of project unit. 
35-22 
6. 
13.

SACRAMENTO, CALIFORNIA DISTRICT 
TABLE 35-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to Sep 30, 1988 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Feather River, CA 1951 - 5,7521 2 
Middle River and Connecting 
Channels, CA Completed 1974 8,8548 98,4944 
Mokelumne River, CA Completed 1974 8,500 189,152 
Navajo Reservoir, NM Completed - 2,182 6 - 
Old River, CA Completed 1970 28,185 681,128 
Stockton and Mormon Channels, CA Completed 1970 258,1518 218,854 
Suisun Bay Channel, CA Completed 1974 200,928' 10 11 8,816,62212 18 
Suisun Channel, CA Completed 1978 217,677 788,48918 14 
Suisun Point Channel, CA Completed 1965 191,7286 15 
1. Maintenance project, channels adequate for commerce. 
2. Includes $10 for maintenance for previous project. 
Excludes $6,160 for previous project and $3,840 for existing 
project for maintenance expended from contributed funds. 
3. Includes $1,600 for previous project. 
4. Includes $790 for previous project. 
5. Authorized by Chief of Engineers under authority of 
sec. 107, Public Law 86-645, as amended. 
6. All costs transferred from Los Angeles District in FY 
1968. 
7. Estimated cost to local interests was $3,600 for lands, 
damages, and public landings. 
8. Upon completion of Mormon Slough, Calaveras River, 
CA in February 1970, local interests accepted maintenance 
responsibility for Mormon Slough as well as for Stockton and 
Mormon Channels, CA, and Federal maintenance was discontinued. 
No Federal maintenance costs have been incurred 
since FY 1969. 
9. Includes $58,901 for previous projects. 
10. Excludes $59,551 expended from required contributed 
funds for previous project. 
11. Excludes work accomplished under existing project at 
a cost of $207,198 from Public Works Administration funds 
allotted to San Joaquin River, CA. 
12. Includes $59,817 for previous projects. Excludes $5,449 
expended from required contributed funds for previous 
pro1je3c. t.Maintenance responsibility transferred to San Francisco 
District, January 1, 1974. 
14. Includes reconnaissance and condition surveys of $5,496 
and $483 for fiscal years 1963 and 1964, respectively. 
15. Estimated cost (July 1964) to local interests was 
$12,000 for lands, damages, and spoil retention dikes. 
35-23

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 35-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to Sep 30, 1983 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Alameda Creek, CA 
Alhambra Creek, CA 
American River, CA 
Aquatic Plant Control, CA 
Bear River, CA 
Big Dry Creek Dam and diversion, CA 
Big Wash, Milford, Beaver County, UT 
Burch Creek, Weber County, UT 
Chester, CA 
Coyote Creek, CA 
Duck Creek, San Joaquin County, CA 
East Weaver Creek, CA 
Eel River, CA 
Fairfield Vicinity Streams, CA 
Folsom Lake, American River, CA 
Gleason Creek, NV 
Green Valley Creek, Solano 
County, CA 
Humboldt River and Tributaries, NV 
Kays Creek, UT 
Kern River-California Aqueduct 
Intertie, CA 
Klamath River, CA 
Lake Camanche, CA 
Lake Oroville, CA 
Lakeport Lake, CA 
Lower San Joaquin River and 
Tributaries, including Tuolumne 
and Stanislaus Rivers, CA 
Mad River Basin, CA 
Marysville Lake, CA 
Merced River, CA 
Middle Creek, CA 
Mormon Slough, CA 
Napa River Basin, CA 
New Bullards Bar, CA 
North Fork, Pit River at Alturas, CA 
Pinole Creek, CA 
Redwood Creek, Humboldt County, CA 
Reese River, Battle Mountain, NV 
Rheem Creek, CA 
Rodeo Creek, CA 
Salinas River, CA 
Salt Lake City, Jordan River, UT 
San Leandro Creek, CA 
San Lorenzo Creek, CA 
San Lorenzo River, CA 
Sevier River near Redmond, UT 
Sonoma Creek, CA 
Truckee River and tributaries, 
CA and NV 
Completed 
Inactive 
Completed 
Completed 
Inactive 
Completed 
Completed 
Active/minor FY 82 
expenditure 
Completed 
Completed 
Completed 
Inactive 
Active/no FY 83 
expenditure 
Completed 
Deferred 
Completed 
Inactive 
Completed 
Completed 
Completed 
Completed 
Completed 
Deferred 
Completed 
Inactive 
Active/no FY 83 
expenditure 
Completed 
Completed 
Completed 
Inactive 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Inactive 
Completed 
Completed 
Completed 
Completed 
Completed 
Inactive 
Active/no FY 83 
expenditure 
1978 
1981 
1959 
1967 
1980 
1955 
1961 
1964 
1981 
1968 
1967 
1965 
1971 
1977 
1967 
1977 
1963 
1982 
1973 
1977 
1972 
1976 
1981 
1976 
1976 
1973 
1980 
1976 
1967 
1976 
1979 
1972 
1974 
1968 
1970 
1969 
1962 
1966 
1952 
1961 
1973 
1962 
1966 
1952 
1973 
1968 
26,995,350 
300,0001 3 
2,125,8184 
1,000 
_5 
1,369,9316 
217,879? 8 
26,0497 
3,570,0009 
705,6221 7 
664,8257 1o 
220,63617 11 
1,272,8161 12 
687,00018 
63,014,81014 
215,82615 
136,0267 16 
1,532,93217 
407,9897 s18 
1,503,0737 19 
4,838,0001 
10,252,950W 
70,425,47021 
2,353,003n 
27,835,2632 
4,243,7501 24 
_25 
10,918,7962 
2,643,499 7 
2,965,402w 
2,639,9551 
12,890,62529 
904,2787 3o 31 
885,7501 7 
4,620,0701 32 
133,3397 33 
400,0001 7 34 
974,1001 7 
94,2131 35 
1,227,5706 
1,000,0001 37 
5,130,8211 38 
4,314,4061 39 
919,0004o 
781,5001 41 
1,038,960 
35-24 
54,7781 2

SACRAMENTO, CALIFORNIA DISTRICT 
TABLE 35-E (Cont'd) 
OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to Sep 30, 1983 
Full Report 
Project Status See Annual Operation and Report For Construction Maintenance 
Wildcat and San Pablo Creeks, CA Active/no FY 83 1979 1,110,0001 
expenditure 
1. Project responsibility transferred from San Francisco 
District to Sacramento District April 1, 1982. 
2. Scheduling of reservoir operations costs. 
3. Project classified as "inactive" January 19, 1982. 
4. Excludes $54,919 other contributed funds for miscellaneous 
construction for local interests pursuant to requirements 
of local cooperation. Total costs for all requirements of 
local cooperation were $951,000 (1959) for lands and relocations. 
5. Due to infeasibility, Bear River Phase I stud was 
suspended and project classified as "inactive" on November 6, 
1981.
6. Excludes $44,008 other contributed funds for construction 
in connection with bridge construction pursuant to 
requirements of local cooperation. Total cost to local interests 
for all requirements of local cooperation was $370,000 (1959) 
for lands and relocations. 
7. Authorized by Chief of Engineers under authority of 
sec. 205, Public Law 80-858, as amended. 
8. Excludes $22,000 for preauthorization studies. 
9. Excludes $69,262 other contributed funds from State 
of California for two low water crossings and appurtenances 
at Chester. Minor FY 1983 engineering costs of $3,436. 
10. Excludes $50,000 for preauthorization studies. Estimated 
costs to local interests were $665,000 for lands and 
damages including relocations. 
11. Includes $174,938 Public Works Acceleration Program 
Funds. 
12. Excludes $194,821 contributed funds and placed inactive 
1973. 
13. Due to lack of local support, Fairfield project was 
reclassified as "deferred" on September 15, 1977, but reclassified 
as "active" June 23, 1982, after receipt of local support. 
14. Transferred to Bureau of Reclamation in May 1956 for 
operation and maintenance by that agency in conjunction 
with other units of Central Valley project. 
15. Due to lack of local support, Gleason Creek project was 
reclassified as "deferred" on November 3, 1977. Fiscal year 
1978 carryover funds of $27,984 were revoked. 
16. Excludes $20,000 for preauthorization'studies. 
17. Vista and Devils Gate reservoirs and channel improvements 
were classified "inactive" on January 12, 1982, and 
Hylton reservoir was classified "inactive" on March 21, 1983, 
due to lack of economic feasibility. 
18. Includes $30,000 for preauthorization studies. Estimated 
costs (FY 1973) to local minterests for all requirements of 
local cooperation were $150,117 for lands and damages 
including relocations. 
19. Includes $73,000 for preauthorization studies. Non- 
Federal (Kern County Water Agency) cost for road relocation 
was $18,260 (required contributed funds). Project prevented 
$34,000,000 in damages from May-June 1983 snowmelt runoff. 
20. Constructed by East Bay Municipal Utility District. 
Final Federal contribution of $51,202 made July 18, 1978 
(total $10,111,684). Non-Federal costs $24,876,842. 
21. Constructed by State of California. Final Federal 
contribution of $64,186 was made on February 9, 1981 (total 
$69,994,015) for flood control reservation. 
22. Preconstruction planning complete. Necessary reaffirmation 
of local cooperation assurances by Lake County 
Flood Control and Water Conservation District not received. 
Project was reclassified as "deferred" on September 15,1977. 
Includes $298,500 costs for advance acquisition of land, 
Public Law 91-439. 
23. Cherry Valley and New Don Pedro Reservoirs constructed 
by local interests. Federal contributions of $9,000,000 
and $5,464,000, respectively, for flood control reservation. 
Final Federal contribution of $308,898 was made on January 
18, 1972, for New Don Pedro. Excludes $3,004,946, 
contributed funds, other, for miscellaneous engineering and 
construction (non-project) at local interests expense under 
local cooperation requirements for acquisition of rights-ofway 
for levee and channel improvements on Lower San 
Joaquin River and tributaries. 
24. Placed inactive 1974. Excludes $225,000 applicable to 
Public Works Acceleration Program and $162,761 previous 
project Blue Lake levee. 
25. Planning and any future development is uncertain 
awaiting State of California's position on support of Marysville 
project. 
26. Constructed by Merced Irrigation District. Final 
Federal contribution of $839 was made December 2, 1975 
(total $10,818,638) for flood control reservation. 
27. Estimated costs (FY 1967) to local interests for all 
requirements of local cooperation were $1,340,000 for lands 
and damages including relocations. 
28. Non-Federal cost $2,965,402 (FY 1976) for lands and 
relocations. Federal contribution of $599,336 made to State 
Reclamation Board. 
29. Constructed by Yuba County Water Agency. Final 
Federal contribution of $33,470 was made in FY 1972 (total 
$12,759,127) for flood control reservation. 
30. Includes $41,800 for preauthorization studies. 
31. Excludes $146,000 other contributed funds for miscellaneous 
construction and engineering and design services 
under local cooperation requirements in connection with 
acquisition of rights-of-way, relocation, and utility alterations. 
32. Includes $107,000 costs for remedial work to drainage 
system completed in FY 1977. 
33. Includes $19,000 for preauthorization studies. 
34. Excludes $52,549 contributed funds. 
35. Cost includes engineering and design prior to June 30, 
1952 and costs of $4,288 FY 1962 and 1963 to determine if 
project classification to an active category was justified. 
36. Estimated costs to local interests for all requirements 
of local cooperation were $463,000 (July 1962) for lands and 
damages including relocations. 
37. Excludes $285,329 contributed funds. 
38. Excludes $200,000 estimated value of work performed 
in lieu of cash contribution. 
39. Excludes 421,182 contributed funds. 
40. Excludes $48,000 required contributed funds toward 
first cost. Costs to local interests for all requirements of local 
cooperation, including required contributions, were $118,000 
(1951). 
41. Placed inactive 1974. 
35-25

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 35-G DEAUTHORIZED PROJECTS 
For Last 
Full Report Federal Contributed 
See Annual Date Funds Funds 
Project Report For Deauthorized Expended Expended 
Little Valley Wash, Magna, UT 1951 1977 - - 
Spanish Fork River, UT 1955 1977 20,000 - 
Weber River and Tributaries, UT 1974 1972 75,120 - 
TABLE 85-H SACRAMENTO RIVER, CA: 
TIDAL AND FLOOD CONDITIONS PREVAILING 
(See Section 1 of Text) 
Miles from Range in Feet 
Mouth of Mean Extreme Ordinary Extreme 
Place River Tidall Tidal2 Flood s Flood4 
Collinsville 0 4.3 7 8 10 
Sacramento 59 2.02 3 20 28 
Verona (Mouth of Feather River) 80 - Trace 22 30 
Colusa 144 - - 26 32 
Chico Landing 193 - - 20 25 
Red Bluff 248 - - 24 30 
1. Mean lower low water to mean higher high water. 3. Mean lower low water to flood stage. 
2. Tide at low water season only. 4. Extreme low water to indicated flood condition. 
TABLE 35-I SAN JOAQUIN RIVER, CA: 
TOTAL COST OF NEW WORK FOR PROJECT1 
(See Section 3 of Text) 
Federal Non-FederalP 
Corps of Coast Required Lands and 
Engineers Guard Cash Damages (includ- Total 
Modification (Construction) (Construction) Contribution ing Relocations) Total Project 
Prior to 1950 Modification $4,009,938 $80,000 $1,307,500 $1,042,000 $2,349,500 $6,439,438 
1950 Modification 1,823,179 - 35,000 135,000 170,000 1,993,179 
Total $5,833,117 $80,000 $1,342,500 $1,177,000 $2,519,500 $8,432,617 
1. Completed in May 1960. 
2. Excludes $5 865,000 (Feb. 1954) local interests costs 
for Stockton Deep Water Channel terminal facilities required 
under terms of project authorization. 
35-26

SACRAMENTO, CALIFORNIA DISTRICT 
TABLE 35-J SAN JOAQUIN RIVER, CA: 
PROJECT UNITS (1950 MODIFICATION) RECLASSIFIED AND EXCLUDED 
FROM PROJECT COST 
(See Section 3 of Text)
Non-Federal 
Federal Required Lands and 
Corps of Cash Damages (includ- Total 
Unit Engineers Contribution ing Relocations) Total Project 
Settling Basin above head of Burns 
Cutoff1 $1,073,000 $ 30,000 $ 200,000 $ 230,000 $1,303,000 
Burns Cutoff improvement; new 
turning basin; dredging Mormon 
Channel2 7,882,0008 431,000 1,455,000 1,886,000 9,768,000 
Upper Stockton Channel enlargement* 535,000 34,000 15,000 49,000 584,000 
1. July 1959 price index. Deauthorized August 5, 1977. 4. Deleted by 1965 River and Harbor Act authorization 
2. Deferred; July 1960 price index. of San Francisco Bay to Stockton Channel, Sacramento 
3. For lands and construction. District, Improvement No. 2. 
TABLE 35-K MERCED COUNTY STREAM GROUP, CA, 
MAXIMUM INFLOW, STORAGE, AND OUTFLOW FOR PROJECTS 
(See Section 11 of Text) 
Maximum 
Inflow Maximum Maximum 
(c.f.s.) Storage Outflow 
Stream (bihourly) (acre-feet) (c.f.s.) 
Burns 4,800 1,400 1,600 
Bear 5,100 2,400 1,500 
Owens 2,500 1,600 160 
Mariposa 10,300 8,100 970 
TABLE 35-L SACRAMENTO RIVER AND TRIBUTARIES, CA, 
COLLINSVILLE TO SHASTA DAM: 
PROJECT UNITS RECLASSIFIED AND EXCLUDED FROM COST ESTIMATE 
(See Section 13 of Text) 
Current Estimated Cost 
Unit Classification Federal Non-FederalP Total 
1944 Modification: 
Antelope Creek2 Inactive $1,400,000 $ 340,000 $1,740,000 
Lower Butte Basina Deferred 7,286,000 2,285,000 9,571,000 
Thomes Creek s Deferred 1,140,000 140,000 1,280,000 
Willow Creek2 Inactive 1,290,000 120,000 1,410,000 
Bypass Levees Deferred 7,100,000 940,000 8,040,000 
Bypass Levees Inactive 3,010,000 - 3,010,000 
1950 Modification: 
Upper Butte Basin s Deferred 3,530,000 1,787,000 5,317,000 
1. For lands and damages, including relocations. 
2. July 1960 price level. 
3. Excludes work applicable to extension of Moulton 
weir (July 1954 price level. 
4. July 1961 price level. 
35-27

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 35-M SACRAMENTO RIVER AND TRIBUTARIES, CA, 
FROM COLLINSVILLE TO SHASTA DAM: 
CONSTRUCTION ACCOMPLISHED AND CONTRACT COSTS 
(See Section 13 of Text) 
Required 
Contract Federal Contributed Total 
Contract 35 completion (Bank protection, 
Sacramento River, miles 110.0-184.0) $152,078 $21,421 $173,499 
Contract 36 completion (Bank protection, 
selected sites, Sacramento River, 
downstream from Freeport) 543,727 15,953 5f9,680 
TABLE 35-N SURVEYS 
(See Section 19 of Text) 
Fiscal year costs were as follows: 
Navigation studies $ 0 
Flood damage prevention studies 1,600,307 
Little Dell, UT project reevaluation study 12,430 
Coordination with Soil Conservation Service 2,000 
Coordination with Bureau of Reclamation pertaining 
to projects under reclamation program (including 
PL 984) 11,000 
Special investigations 95,000 
Review of FERC licenses 28,000 
Planning assistance to states 39,000 
$1,787,737 
35-28

PACIFIC OCEAN DIVISION* 
This division comprises the State of Hawaii. The division 
also performs such actions pertaining to preservation 
and protection of navigable waters on and about 
the island of Guam and American Samoa as provided for 
under River and Harbor Act of 1899, and the Commonwealth 
of the Northern Mariana Islands as provided for 
under Public Law 94-241 (H.J. Res 549) (March 24, 
1976). 
IMPROVEMENTS 
Navigation 
1. Barbers Point Harbor, Oahu, Hawaii ...... 
2. Honolulu Harbor, Oahu, Hawaii ........... 
3. Kahului Harbor, Maui, Hawaii ............ 
4. Kaulana Bay Boat Harbor, Hawaii, Hawaii 
5. Nawiliwili Harbor, Kauai, Hawaii ......... 
6. Port Allen Harbor, Kauai, Hawaii ........ 
7. Rota Harbor, Northern Marianas .......... 
8. Tau Small Boat Harbor, American Samoa.. 
9. Navigation Work Under Special 
Authorization ........................... 
Page 
36-1 
36-2 
36-2 
36-2 
36-3 
36-3 
36-3 
36-4 
36-4 
Beach Erosion Control 
10. Asquiroga Bay, Territory of Guam ......... 36-4 
11. Matafao Shoreline, American Samoa ...... 36-4 
12. Pago Pago Airport, American Samoa ...... 36-5 
13. Beach Erosion Work Under Special 
Authorization ........................... 36-5 
14. Inspection of Completed Beach 
Erosion Projects ......................... 36-5 
Flood Control 
15. Asan Village, Territory of Guam ......... . 
16. Iao Stream, Maui, Hawaii ................ 
17. Kahoma Stream, Maui, Hawaii............ 
18. Kaneohe-Kailua Area, Oahu, Hawaii ...... 
36-5 
36-6 
36-6 
36-7 
Flood Control (Cont.) 
19. Paauau Stream, Hawaii, Hawaii .......... 36- 7 
20. Waimea River, Kauai, Hawaii ............ 36- 8 
21. Flood Control Work Under 
Special Authorization ................... 36- 8 
22. Inspection of Completed Flood 
Control Projects ........................ 36- 9 
General Investigations 
23. Surveys ................................ 36- 9 
24. Collection and Study of Basic Data ........ 36- 9 
Tables 
Table 36-A Cost and Financial Statement ..... 36-10 
Table 36-B Authorizing Legislation ........... 36-12 
Table 36-C Other Authorized Navigation 
Projects ......................... 36-14 
Table 36 -D Other Authorized Beach Erosion 
Control Projects ................. 36-15 
Table 36 -E Other Authorized Flood 
Control Projects ................. 36-15 
Table 36-F Not Applicable 
Table 36 -G Deauthorized Projects ............ 36-16 
Table 36-H Reconnaissance and Condition 
Surveys ......................... 36-16 
Navigation 
1. BARBERS POINT HARBOR, 
OAHU, HAWAII 
Location. On the west coast of Oahu, about 25 miles 
from metropolitan Honolulu. (See Coast and Geodetic 
Survey Charts 4110 and 4133.) 
Existing project. Deep-draft harbor provides for an 
entrance channel 4,280 feet long, 450 feet wide and 38 
to 42 feet deep; an inshore harbor basin of about 92 
acres and 38 feet deep; and 4,700 feet long wave absorber. 
Light -draft harbor provides for a main access channel 
1,200 feet long, 80-140 feet wide, and 12 feet deep; 
and wave absorber 300 feet long. Plane of reference is 
mean lower low water datum. The mean tidal range between 
mean lower low water and mean higher high 
water level is 1.8 feet; extreme range under normal condition 
is 2.3 feet. Approved project cost estimate (October 
1982) is $66,600,000 of which $58,300,000 (includes 
$400,000 in Coast Guard cost) is federal cost and 
$8,300,000 is non -federal cost including lands and 
right -of -way and cash contribution of $2,500,000. (See 
Table 36-B for Authorizing Legislation.) 
Local cooperation. Local interest must provide 
36-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
lands and right -of -way for construction and future 
maintenance, provide and maintain mooring facilities 
and utilities open to all on equal terms; provide such 
utility and drainage relocations or alterations as 
necessary; hold the United States free from damages; 
and provide a cash contribution estimated to be 
$,500,000 for the deep -draft harbor. 
Terminal facilities. Existing privately owned barge 
harbor consists of a concrete marginal wharf, 250 feet 
long along south side of the barge basin. An offshore 
tanker facility is connected to the oil refinery by 
pipelines. 
Operations during fiscal year. New Work: A construction 
contract was awarded in March 1982 for 
$48,182,000 and is scheduled for completion in May 
1985. A motion for a Tbmporary Restraining Order to 
stop the construction was dismissed in November 1982. 
A second motion for a Temporary Restraining Order to 
halt blasting operations was dismissed in February 
1983 and onshore blasting was resumed in February 
1983 and offshore blasting was resumed in June 1983. 
An Environmental Assessment for offshore blasting 
and a Finding of No Significant Impact was completed 
in September 1983. Progress of construction work is 53 
percent. Remaining work includes dredging of basin 
and entrance channel, construction of wave absorbers 
and ground beautification. A separate construction contract 
for a Regional Visitor Center at Fort DeRussy was 
completed in January 1983 for $708,481 which included 
$24,118 in military funds for repair of the roof. Exhibit 
production ($185,637) was finalized in May 1983 and 
the center was dedicated by the Chief of Engineers and 
opened to the public in June 1983. Maintenance: 
Routine operation cost for the Regional Visitor Center 
was $16,366 for the first year. 
2. HONOLULU HARBOR, 
OAHU, HAWAII 
Location. On the southern coast of the island of 
Oahu in the city of Honolulu. (See Coast and Geodetic 
Survey Chart 4109.) 
Existing project. Completed portion of project comprises 
three channels 35-40 feet deep, two harbor basin 
35 feet deep, and a double -leaf -bascule bridge. Last full 
report on this is on page 1828 and 1829 of Annual Report 
for 1962. Modifications provide deepening seaward 
3,600 feet of Fort Armstrong entrance channel to 45 
feet, deepening main harbor basin and Kapalama Channel 
to 40 feet; widening Kapalama Channel by 60 feet 
along Sand Island side for 3,100 feet; and relocating 
project line to provide a 100 -foot offset from pierheads 
in Kapalama Channel and at piers 9, 10, and 11, and an 
offset of 50 to 75 feet elsewhere in the harbor. The mean 
tidal range between mean lower low water and mean 
higher high water is 1.9 feet. The usual extreme range 
is 2.3 feet. Tbtal project cost for modifications is 
$7,820,842 of which $7,615,143 is federal cost and 
p205,699 is non -federal cost. (See Table 36-B for 
Authorizing Legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. There are 34 piers and 2 
marginal wharves, which include 3 piers and 1 
marginal wharf owned by the federal government; 13 
piers and 1 marginal wharf owned by the State of 
Hawaii; and 18 piers State owned. All non -federal piers 
are open to all on equal basis, although certain ones are 
reserved for passenger terminals, for container ships or 
for handling specific bulk commodities such as 
petroleum products, pineapple, sugar, animal feeds, and 
cement. 
Operations during fiscal year. A law suit against 
the government filed in September 1981 for damages to 
a marine railway is pending. 
3. KAHULUI HARBOR, 
MAUI, HAWAII 
Location. On the northern coast of the island of Maui 
at the town of Kahului. (See Coast and Geodetic Survey 
Chart 4124.) 
Existing project. Rubblemound breakwaters on east 
and west sides of harbor, approximately 2,766 and 2,315 
feet long, respectively, and an entrance 600 feet wide 
between breakwaters and harbor basin, 2,050 feet wide, 
2,400 feet long, and 35 feet deep. Range of tide between 
mean lower low water and mean higher high water is 
S2.2 feet and extreme tidal range under normal conditions 
is 4.5 feet. Estimated total project cost for the 
major rehabilitation is $2,924,000 in federal cost. (See 
Table 36-B for Authorizing Legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Two wharves owned and operated 
by State of Hawaii which are open to shipping on 
equal terms. Pipelines for fuel oil, distillate, kerosene, 
gasoline, molasses, and water are available. There is 
also a bulk -sugar plant of 30,000 -ton storage capacity 
with a conveyor loading system capable of conveying at 
a rate of about 750 tons per hour. Facilities are considered 
adequate for existing commerce. 
Operations during fiscal year. New Work: A construction 
contract for rehabilitation of breakwater was 
awarded in July 1982 for p2,437,500 and scheduled for 
completion in March 1984. Progress of construction 
work is 86 percent. Remaining work includes placement 
of 9-ton tribars and construction of concrete ribs on the 
east breakwater. 
4. KAULANA BAY BOAT HARBOR, 
HAWAII, HAWAII 
Location. On the southern tip of the island of Hawaii 
in the Ka'u Judicial District about 80 road miles southwest 
of the city of Hilo. (See NOAA Chart 19320.) 
Existing project. Project provides for an entrance 
channel 135 feet long, 60-80 feet side tapered and 8.5 
feet deep; a turning basin 200 feet long, 100 feet wide 
and 6.5 feet deep; and a rubblemound main breakwater 
155 feet long, with a +11.5 feet crest elevation at the 
36-2

PACIFIC OCEAN DIVISION 
head and a +8.0 feet crest elevation at the trunk; a new 
single -lane launch ramp; and appurtenant aids to 
navigation. Range of tide between mean lower low 
water and mean higher high water is 2.5 feet. Estimated 
total project cost is $621,000 (includes $20,000 
in Coast Guard cost) in federal cost. Project authority is 
Section 107 of the 1960 River and Harbor Act, as 
amended. Project was approved for construction in 
April 1982. 
Local cooperation. Requirements are described in 
full on page 36-3 of Fiscal Year 1982 Annual Report. 
Terminal facilities. There is an existing boat 
launching ramp owned by the State of Hawaii and open 
to all on equal basis. 
Operations during fiscal year. New Work: Plans 
and specifications were completed and favorable bids 
were received in September 1983. A contract was not 
awarded due to commencement in October 1983 of a 
civil action to enjoin the award of construction contract. 
5. NAWILIWILI HARBOR, 
KAUAI, HAWAII 
Location. On the southwest coast of the island of 
Kauai and about 100 nautical miles, northwest of 
Honolulu. (See NOAA Chart 19383.) 
Existing project. Rubblemound breakwater 2,150 
feet long; an entrance channel 2,400 feet long, 600 feet 
wide and 40 feet deep; a harbor basin 1,950 feet long, 
1,540 feet wide and 35 feet deep; and a revetted fill on 
the west side of the harbor. The tidal range between 
mean lower low water and mean higher high water is 
1.8 feet. Estimated total project cost for the major 
rehabilitation is $5,070,000. (See Table 36-B for 
Authorizing Legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. The State of Hawaii owns a reinforced 
concrete wharf with two sheds. Bulk-storage 
facilities and pipeline are available for petroleum products, 
liquid fertilizer and molasses. There is also a bulk 
sugar plant of 28,000 -ton storage capacity with a conveyor 
system capable of loading at a rate of about 750 
tons per hour. 
Operations during fiscal year. Maintenance: Preparation 
of a General Design Memorandum for major 
rehabilitation of the breakwater was initiated in September 
1982 and is scheduled for completion in January 
1984. Maintenance dredging was completed in March 
1983 by U.S. hopper dredge Yaquina and 184,000 cubic 
yards removed at a total cost of $1,352,226 which 
included $34,917 for bioassay testing of dredged 
materials. $45,025 was utilized for preparation of plans 
and specifications for storm damage repairs to breakwater 
caused by Hurricane Iwa in November 1982. 
Repair work was deferred as the structure is not in 
immediate danger of failure and the work will be incorporated 
in the major rehabilitation General Design 
Memorandum. 
6. PORT ALLEN HARBOR, 
KAUAI, HAWAII 
Location. On the southern coast of the island of 
Kauai in Hanapepe Bay, about 110 nautical miles northwest 
of Honolulu. (See NOAA Chart 19382.) 
Existing project. The project provides for a rubblemound 
breakwater 1,200 feet long on the east side of the 
bay; a harbor basin 1,200 feet wide, 1,500 feet long and 
35 feet deep; and an entrance channel 500 feet wide, 
and 35 feet deep. The range of tide between mean lower 
low water and mean higher high water is 1.7 feet, and 
the extreme tidal range under ordinary conditions is 2.7 
feet. Ibtal estimated cost for storm damage repairs to 
breakwater is p261,300 (includes $3,300 in Coast Guard 
cost) in federal cost. (See Table 36-B for Authorizing 
Legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. There is one pier and a storage 
shed owned and operated by the State of Hawaii. Bulk 
storage facilities and pipelines are available for 
petroleum products, liquid fertilizer and molasses. The 
facilities are open to all on equal terms and are considered 
adequate for existing commerce. 
Operations during fiscal year. Maintenance: 
Bioassay testing of dredged materials was completed in 
December 1982 for $16,423. The District Engineer in 
April 1983 deleted maintenance dredging which was 
scheduled in FY 83. A construction contract for repair 
work on storm damages to breakwater caused by Hurricane 
Iwa in November 1982 was awarded in September 
1983 for $177,600 (base) and scheduled for completion 
in January 1984. There was no physical construction 
progress during the fiscal year. 
7. ROTA HARBOR, 
NORTHERN MARIANAS 
Location. On the island of Rota within the Commonwealth 
of the Northern Mariana Islands which is 
located in the Western Pacific, approximately 3,820 
miles west of Hawaii and approximately 40 miles north 
of Guam. (See U.S. Defense Mapping Agency 
Hydrographic Map No. 81063.) 
Existing project. The project provides for an 
entrance channel 800 feet long, 300 feet wide, 20 feet 
deep; a turning basin 400 feet long, 200 -400 feet wide, 
16.5 feet deep; a revetted mole of armor stones 500 feet 
long, 10 feet high; a basin extension 250 feet long, 150 
feet wide, 16.5 feet deep; and appurtenant aids to 
navigation. Range of tide between mean lower low 
water and mean higher high water is 2.4 feet. Estimated 
total project cost is $3,170,500 of which 
$,057,000 (includes $87,000 in Coast Guard cost) is 
federal cost and $1,083,500 is non -federal cost for cash 
contribution. Project authority is Section 107 of the 
1960 River and Harbor Act, as amended. Project was 
approved for construction in October 1980. 
Local cooperation. Fully complied with. 
Terminal facilities. There is an existing 144 foot 
36-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
long concrete dock at the West Harbor. Presently, cargo 
is lightened from offshore of West Harbor by a U.S. 
Government surplus LCM which is able to navigate the 
narrow and shallow entrance at high tide and off -load 
at the existing concrete dock. 
Operations during fiscal year. New Work: A construction 
contract was awarded in September 1982 for 
$2,482,982 and scheduled for completion in April 1984. 
Progress of construction work is 72 percent. Remaining 
work includes completion of dredging of the turning 
basin and construction of revetted mole. 
8. TAU SMALL BOAT HARBOR, 
AMERICAN SAMOA 
Location. On the island of Tau, American Samoa, 
about 2,300 miles southwest of Hawaii, 1,236 miles 
northwest of Tahiti, and 80 miles southeast of Western 
Samoa. (See Coast and Geodetic Survey Chart 4190.) 
Existing project. Project provides for an entrance 
channel 520 feet long, 130 feet wide, 16 feet deep; a 
turning basin 85,000 square feet, 14 feet deep; a rubblemound 
breakwater 290 feet long, 13 feet high; revetments 
with a total length of 975 feet; and a rubblemound 
groin 200 feet long. Plane of reference is mean 
sea level. The range of tide between mean lower low 
water and mean higher high water is 2.5 feet. Estimated 
total project cost is $2,058,800 of which 
$2,004,800 (includes $4,800 in Coast Guard cost) is 
federal cost and $54,000 is non -federal cost for cash 
contribution. Project authority is Section 107 of the 
1960 River and Harbor Act, as amended. Project was 
approved for construction in January 1975. 
Local cooperation. Fully complied with. 
Operations during fiscal year. New Work : Contractor 
claim filed in May 1981 for different site conditions 
was settled for $422,000 which included $1,730 in nonfederal 
funds. Plans for corrective measures for post - 
construction navigation difficulties were deferred to FY 
1984. 
9. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation activities pursuant to Section 107, Public 
Law 86 -645. 
Preauthorization studies were initiated on 
Honouliwai Small Boat Harbor, Molokai, $7,352; 
Kahana Bay, Oahu, $46,941, and Saipan Deep Draft 
Harbor, Northern Marianas, $59,096; continued on 
Laupahoehoe Harbor, Hawaii, $60,422, and Merizo Harbor, 
Guam, $85,551; and completed on Agat Harbor, 
Guam, $1,443. 
Beach Erosion Control 
10. ASQUIROGA BAY, 
TERRITORY OF GUAM 
Location. On the southeastern shore of the island of 
Guam, about 3,318 miles west of Honolulu, Hawaii. 
(See NOAA Chart 81048.) 
Existing project. Project provides for a 275 feet rock 
revetment with a crest elevation of +14.0 feet MLLW 
with a slope of 1V on 1.5H. Estimated total project cost 
is $320,000 of which $250,000 is federal cost and $70,000 
is non -federal cost. Project authority is Section 14 of 
the 1946 Flood Control Act, as amended. Project was 
approved for construction in August 1980. 
Local cooperation. 
(a) Provide without cost to the United States all 
necessary lands, easements, rights -of -way, or other 
real estate interests required for construction of the 
project; 
(b) Hold and save the United States free from 
damages which may result from construction, operation 
and subsequent maintenance of the project, except 
damages due to the fault or negligence of the United 
States or its contractors; 
(c) Assure continued conditions of public ownership 
and use of the shore upon which the amount of Federal 
participation is based during the economic life of the 
project; 
(d) Assure maintenance and repair during the economic 
life of the project as required to serve the 
intended purposes; 
(e) Provide and maintain necessary access roads, 
open and available to all on equal terms; 
(f) Comply with the provisions of the Uniform 
Relocation Assistance and Real Property Acquisition 
Policies Act of 1970 (Public Law 91-646); 
(g) Comply with Title VI of the Civil Rights Act of 
1964 (PL 88-352); and 
(h) Assume full responsibility for all project costs in 
excess of the Federal cost limitation of $250,000. 
Operations during fiscal year. New Work: Plans 
and specifications are 95 percent complete. Construction 
was deferred in August 1983 due to inability of the 
Government of Guam to provide the required cash contribution. 
11. MATAFAO SHORELINE, 
AMERICAN SAMOA 
Location. On the south shore of the island of Thtuila, 
American Samoa, about 2,300 nautical miles southwest 
of Hawaii. (See NOAA Chart 83484.) 
Existing project. Project provides for a 430 feet long 
rock revetment with a crest elevation of +9. 5 feet MSL 
with a slope of 1V on 1.5H. Estimated total project cost 
is $225,000 in federal cost. Project authority is Section 
14 of the 1946 Flood Control Act, as amended. Project 
was approved for construction in February 1980. 
Local cooperation. 
(a) Provide without cost to the United States all 
necessary lands, easements, rights -of -way, and reloca- 
36-4

PACIFIC OCEAN DIVISION 
tions required for construction of the project; 
(b) Hold and save the United States free from claims 
for damages which may result from construction, and 
subsequent maintenance of the project, except damages 
due to the fault or negligence of the United States or its 
contractors; 
(c) Assure continued conditions of public ownership 
and use of the shore upon which the amount of Federal 
participation is based during the economic life of the 
project; 
(d) Assure maintenance, repair and operation during 
the economic life of the project as required to serve the 
intended purposes; 
(e) Provide and maintain necessary access roads, 
parking areas, and other public use facilities, open and 
available to all on equal terms; 
(f) Comply with the provisions of the Uniform 
Relocation Assistance and Real Property Acquisition 
Policies Act of 1970 (Public Law 91-646); 
(g) Comply with Title VI of the Civil Rights Act of 
1964 (PL 88-352); and 
(h) Assume full responsibility for all project costs in 
excess of the federal cost limitation of $250,000. 
Operations during fiscal year. New Work: A construction 
contract for Matafao shoreline and Pago Pago 
Airport was awarded in July 1983 for $284,320 of which 
$166,720 is for Matafao. The contract completion is 
scheduled in February 1984 for both projects. There was 
no physical construction progress during the fiscal year. 
12. PAGO PAGO AIRPORT, 
AMERICAN SAMOA 
Location. On the south shore of the island of Thtuila, 
American Samoa, about 2,300 nautical miles southwest 
of Hawaii. (See NOAA Chart 83484.) 
Existing project. Project provides for a 1,580 feet 
long rock revetment with a crest elevation of +8.0 feet 
MSL with a slope of 1V on 1.5H. Estimated total project 
cost is $175,000 in federal cost. Project authority is Section 
14 of the 1946 Flood Control Act, as amended. Project 
was approved for construction in February 1981. 
Local cooperation. 
(a) Provide without cost to the United States all 
lands, easements, rights -of -way, and utility relocations 
and alterations required for the project construction; 
(b) Hold and save the United States free from 
damages due to the construction works and maintenance 
of the project when not due to the fault or negligence 
of the United States or its contractors; 
(c) Assure continued public ownership and use of the 
shore upon which the amount of Federal participation is 
based during the economic life of the project; 
(d) Maintain and operate the project after completion 
without cost to the United States as may be 
required to serve the intended purpose; 
(e) Assume full responsibility for all project costs in 
excess of the Federal cost limitation of p250,000 which 
are presently (January 1983) estimated to be $72,500. 
(f) Fulfill those requirements of local cooperation as 
may be required by the Uniform Relocation Assistance 
and Real Property Acquisition Policies Act of 1970 
(Public Law 91-646, 9 1st Congress, 2nd Session). 
(g) Comply with Section 601 of Title VI of the Civil 
Rights Act of 1964 (Public Law 88-352) that no person 
shall be excluded from participation in, denied the 
benefits of or subjected to discrimination in connection 
with the project on the grounds of race, creed, or 
national origin. 
Operations during fiscal year. New Work: A construction 
contract for Pago Pago Airport and Matafao 
Shoreline was awarded in July 1983 for p284,320 of 
which $117,600 is for Pago Pago Airport. The contract 
completion is scheduled in February 1984 for both projects. 
There was no physical construction progress during 
the fiscal year. 
13. BEACH EROSION WORK 
UNDER SPECIAL AUTHORIZATION 
Emergency streambank and shoreline protection 
activities pursuant to Section 14, Public Law 79-526. 
Preauthorization study was completed on Merizo 
Area, Guam, $3,500. 
Beach erosion control activities pursuant to Section 
103, Public Law 87-874. 
Preauthorization studies were initiated on Lepua 
Area, American Samoa $52,655, and Makaha Beach, 
Oahu, $12,286; and completed on Beach Road, Saipan, 
Northern Marianas, $10,000; Lauli'i to Tla, American 
Samoa, $5,000; Paseo De Susana, Guam, $71,198, and 
Sand Island, Oahu, $58,644. 
14. INSPECTION OF COMPLETED 
BEACH EROSION PROJECTS 
Inspection and survey were conducted on Kaaawa 
Beach, Oahu, and Sand Island, Oahu, in December 1982; 
and Waikiki Beach, Oahu, in January 1983 for a total 
cost of $870. 
Flood Control 
15. ASAN VILLAGE, 
TERRITORY OF GUAM 
Location. On the west central coastal area of the 
island of Guam and about 2.5 miles east of Agana, the 
capital of Guam. The island of Guam is approximately 
3,318 miles west of Honolulu, Hawaii, and 1,300 miles 
south of 'Ibkyo, Japan. (See NOAA Chart 81048.) 
Existing project. Project provides for 400 feet of 
unlined channel, 592 feet of grass -lined channel, 1,054 
36-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
feet of riprapped channel, and modification of Marine 
Drive culvert. The interior drainage work by the Guam 
Housing and Urban Renewal Authority consists of a 
1,960 -foot swale with an ocean outlet. Estimated total 
project cost is $1,905,500 of which $1,275,500 is federal 
cost and $630,000 in cash contribution is non -federal 
cost. Project authority is Section 205 of the Flood Control 
Act of 1948, as amended. Project was authorized for 
construction in May 1983. Construction funds allotted 
under the Jobs Bill Program. 
Local cooperation. 
(a) Provide, without cost to the United States, all 
real estate interests (including but not limited to lands, 
easements, and rights -of -way) necessary for the construction 
and subsequent maintenance of the project; 
(b) Hold and save the United States free from 
damages due to the construction, operation and maintenance 
of the project except where such damages are due 
to the fault or negligence of the United States or its contractors; 
(c) Maintain and operate the project, or integral 
parts thereof, in accordance with regulations prescribed 
by the Secretary of the Army; 
(d) Accomplish without cost to the United States all 
alterations and relocations of buildings, streets, storm 
drains, utilities, highway bridges, culverts and other 
structures made necessary by the construction; 
(e) Provide assurances that encroachment on 
improved channels or on required flowage easements 
will not be permitted; 
(f) Assume all costs, exclusive of lands, easements, 
rights -of -way, and relocation of buildings, streets, 
utilities, bridges and other structures, in excess of the 
$4,000,000 federal limitation for channel improvements 
and related works. 
(g) The local cash contribution shall be paid in a 
lump -sum prior to initiation of construction and is subject 
to final adjustment after actual costs have been 
determined, such amounts to be deposited upon receipt 
by the Corps in U.S. freasury; 
(h) Provide, as determined in the Detailed Project 
Report, improvements to Calacag River sized to a design 
discharge consistent with the improvements for Asan 
River; 
(i) Provide, as determined in the Detailed Project Report, 
a swale in the location of the existing swale sized 
to a design discharge consistent with the level of protection 
provided in improvements for the Asan and 
Calacag Rivers; 
(j) Prescribe and enforce floodplain management 
regulations for the improved waterway and surrounding 
floodplain; 
(k) At least annually inform affected interests 
regarding the limitations of the protection afforded by 
the project. 
(1) Fulfill the requirements of non -federal cooperation 
as may be required by the Uniform Relocation 
Assistance and Real Property Policies Act of 1970 
(Public Law 91-646); and 
(m) Comply with Title VI of the Civil Rights Act of 
1964 (Public Law 88-352). 
Operations during fiscal year. New Work: Plans 
and specifications initiated in April 1983 and completed 
in September 1983. A construction contract was 
awarded in September 1983 for $1,349,500 (Federal: 
$780,400, Non -Federal: $569,100) and scheduled for 
completion in April 1985. There was no physical construction 
progress during the fiscal year. 
16. IAO STREAM, 
MAUI, HAWAII 
Location. Iao Stream on the island of Maui drains a 
portion of the slopes of the West Maui mountains, and 
its lower course runs into the sea just to the east of the 
town of Wailuku, Maui. (See Coast and Geodetic Survey 
Chart 4124.) 
Existing project. Project provides for a debris basin 
2.5 miles upstream of stream mouth; channel improvement 
from the debris basin to about 1,100 feet 
downstream of Market Street bridge; diversion levees 
and flood plain management from the channel improvements 
for about 1,400 feet downstream of Waiehu 
bridge. The standard project design discharge is 26,500 
cubic feet per second at the stream mouth. 'btal project 
cost is $11,140,000 of which $10,540,000 is federal cost 
(allocation received $11,753,000) and $600,000 is non - 
federal cost for lands and relocations. Project was completed 
in May 1981 but corrective measures required in 
January 1982. Construction for remedial work was 
authorized in January 1983. Construction funds allotted 
under the Jobs Bill Program. (See Table 36-B for 
Authorizing Legislation.) 
Local cooperation. Fully complied with. 
Operations during fiscal year. New Work : Two contractor 
appeals filed in July 1980 for flood damages and 
August 1980 for defective specifications were dismissed 
without prejudice by the Engineer Board of Contract 
Appeals in June 1983. There are no other claims pending. 
Construction contract for corrective measures for 
levee protection was awarded in June 1983 for $455,923 
and scheduled for completion in January 1984. Funds 
under the Jobs Bill Program authorized $470,000. 
Progress of construction work is 40 percent which 
included completion of left bank lining and work on 
right bank lining. 
17. KAHOMA STREAM, 
MAUI, HAWAII 
Location. Kahoma Stream drainage basin is located 
in Lahaina, Maui. Lahaina is on the west coast of Maui 
about 4 miles from Kaanapali. The drainage basin of 
Kahoma Stream totals 5.3 square miles. (See NOAA 
Chart 19348.) 
Existing project. The project provides for a debris 
basin with 120 feet maximum based width and a 
36-6

PACIFIC OCEAN DIVISION 
capacity of 55,000 cubic yards; a concrete trapezoid 
channel 5,415 feet long; three concrete bridges with a 
clear span of 60 feet; and a revetted outlet extending 70 
feet seaward of the river mouth. Approved project cost 
estimate (October 1983) is $22,900,000 of which 
$14,900,000 is federal cost and $8,000,000 is non -federal 
cost for lands, damages, relocations and cash contributions 
($2,100,000). (See Table 36 -B for Authorizing 
Legislation.) 
Local cooperation. Local interests are required to 
provide without cost to the United States all lands, 
easements, and right -of -way; all relocation of building 
and utilities, highway and street bridges and driveways, 
railroad track and bridge, and other related facilities 
which may be required for construction of the project; 
hold and save the United States free from damages due 
to the construction works; maintain and operate all the 
work after completion; and prohibit encroachment on 
improved channels and debris basin. Local interests 
have agreed to voluntarily pay a minimum of 35 percent 
of the costs allocated to flood control, but not less than 
that required by the project authorization. 
Operations during fiscal year. New Work: Plans 
and specifications are 99 percent complete. Work on 
Section 221 Agreement and related agreements continuing. 
This project was included under the FY 83 
budget amendment of May 25, 1982 and then under the 
FY 84 budget for initial construction funds. 
18. KANEOHE-KAILUA AREA, 
OAHU, HAWAII 
Location. Kamooalii-Kaneohe Stream drainage 
basin is on the east coast of the island of Oahu. The 
drainage basin is bounded on west and south by the 
Koolau Mountain range, on the east by the remnants of 
Kaneohe volcanic cone and on the north by Kaneohe 
Bay. (See Coast and Geodetic Survey Chart 4134 and 
U.S. Geological Survey quadrangles Kaneohe, Hawaii 
and Honolulu, Hawaii.) 
Existing project. Project provides for a dam and 
reservoir about 3.2 miles above the mouth of Kaneohe 
Stream on the tributary Kamooalii Stream. Project consists 
of an earth-fill dam 80 feet high, with a crest 
length of about 2,300 feet, and about 1,274 feet of channel 
improvements, a concrete side channel and chute 
spillway and reservoir with storage of 2,500 acre -feet, 
of which 500 acre -feet for sediment reserve and recreation 
use and 2,000 acre -feet for flood control. 'Ttal project 
cost is $24,993,100 of which $18,993,100 is federal 
cost (allocation received $24,661,400) and $6,000,000 is 
non -federal cost for recreation facilities, lands and 
damages, and relocations. Non -federal reimbursement 
of construction cost is $5,668,300 at 5.116 percent with a 
repayment life of 35 yers and an annual payment of 
$359,220. Project was completed in May 1981. (See 
Table 36-B for Authorizing Legislation.) 
Local cooperation. Fully complied with. 
Operations during fiscal year. New Work : Contractor 
claims are pending for defective specifications filed 
in October 1979 and suspension of work on spillway 
filed in December 1980. Contractor claim on landscaping 
and wildlife pond was settled in May 1983 for $9,200 
which included $675 in non -federal funds. 
19. PAAUAU STREAM, 
HAWAII, HAWAII 
Location. In the Ka'u District on the island of 
Hawaii, approximately 45 miles southwest of Hilo. (See 
NOAA Chart 19320.) 
Existing project. Project provides for a 295 feet 
levee and three CRM walls of 550 feet, 272 feet and 670 
feet. Estimated total project cost is $1,910,000 in federal 
funds. Project authority is Section 205 of the Flood Control 
Act of 1948, as amended. Project was authorized for 
construction in August 1983. 
Local cooperation. 
(a) Provide, without cost to the United States, all 
lands, easements, and rights -of -way and other real 
estate interests including suitable borrow and spoil disposal 
areas determined by the Chief of Engineers to be 
necessary and required for construction and subsequent 
maintenance of the project; and 
(b) Hold and save the United States free from 
damages due to the construction, operation, and maintenance 
of the project except where such damages are 
due to the fault or negligence of the United States or its 
contractors; and 
(c) Maintain and operate the project, in its entirety 
after completion, in accordance with regulations 
prescribed by the Secretary of the Army; and 
(d) Accomplish, without cost to the United States, all 
alterations and relocations of utilities, buildings, 
streets, storm drains, highway bridges, and other structures 
made necessary for project purposes; and 
(e) Establish regulations prohibiting the discharge of 
pollutants into the waters of the channel by users 
thereof, which regulations shall be in accordance with 
applicable laws or regulations of federal and local 
authorities responsible for pollution prevention and 
control; and 
(f) Establish and enforce floodplain management 
regulations and policies to prevent obstruction or 
encroachment on the floodplain waterway designated 
for the project; and 
(g) Maintain eligibility under the National Flood 
Insurance Program; and 
(h) Comply with all provisions of the Uniform Relocation 
Assistance and Real Property Acquisition Policies 
Act of 1970 (PL 88- 352), as amended, codified at 42 USC 
4601, et seq.; and 
(i) Comply with Title VI of the Civil Rights Act of 
1964 (PL 88-352), as amended, codified at 42 USC 1971, 
et seq.; and 
(j) Provide guidance and leadership in preventing 
36-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
unwise future development of the floodplain by 
encouraging prudent use of the watershed and flood - 
plain lands through proper identification of lands subject 
to flooding and by floodproofing, land use regulation, 
or other floodplain management techniques to 
reduce future flood losses. 
(k) Agree to bear all costs in excess of the current 
monetary limitation contained in Section 205 of the 
Flood Control Act of 1948, as amended. 
Operations during fiscal year. New Work: Plans 
and specifications were completed in September 1983 
and bids received in September 1983. A construction 
contract was awarded in September 1983 for $1,473,900 
(base schedule) and scheduled for completion in September 
1984. There was no physical construction 
progress during the fiscal year. 
20. WAIMEA RIVER, 
KAUAI, HAWAII 
Location. On the west-central portion of the island of 
Kauai which is about 103 statute miles northwest of 
Honolulu. (See NOAA Chart 19381.) 
Existing project. Project provides for 3,175 feet of 
CRM floodwall on existing levee, 4,650 feet of rock toe 
protection, 500 feet of road raise, 1,325 feet of levee 
extension, 250 feet of concrete wall, new floodgates and 
a flood warning system. Estimated total project cost is 
$3,078,000 of which $3,058,000 is federal cost and 
p20,000 is non -federal cost share of flood warning 
system. Project authority is Section 205 of the Flood 
Control Act of 1948, as amended. Project was authorized 
for construction in May 1983. Construction funds allotted 
under the Jobs Bill Program. 
Local cooperation. 
(a) Provide without cost to the United States all 
lands, easements, and rights -of -way necessary for the 
construction and subsequent maintenance of the project; 
(b) Hold and save the United States free from 
damages due to the construction and maintenance of 
the project, excluding damages due to the fault or negligence 
of the United States or its contractors; 
(c) Maintain and operate all the work including flood 
warning systems on Kauai after completion in accordance 
with regulations prescribed by the Secretary of 
the Army; 
(d) Provide without cost to the United States all 
relocations or alterations of buildings, utilities, highway 
bridges, sewers, and other structures and improvements; 
(e) Prescribe and enforce regulations to prevent 
obstruction on the channels, the interior ponding area 
up to elevation 5 feet MSL, and the lands opposite the 
levee on the eastern overbank between the river and 
elevation 20 feet MSL, which would reduce their flood 
carrying capacity or hinder maintenance and operations; 
(f) At least annually inform affected interests 
regarding the limitations of the protection afforded by 
the project; 
(g) Provide contributions for the flood warning 
system equal to 20 percent of the first cost allocated to 
these measures; 
(h) Assume all costs (in addition to those already 
assumed under g, above) in excess of the $4,000,000 
federal limitation for the channel improvements and 
related work; 
(i) Fulfill the requirements of non -federal cooperation 
as may be required by the Uniform Relocation 
Assistance and Real Property Policies Act of 1970 
(Public Law 91-646); and 
(j) Comply with Title VI of the Civil Rights Act of 
1964 (Public Law 88- 352.) 
Operations during fiscal year. New Work: Plans 
and specifications were completed in September 1983 
and bids received in September 1983. A construction 
contract was awarded in September 1983 for p2,454,400 
and scheduled for completion in June 1985. There was 
no physical construction progress during the fiscal year. 
21. FLOOD CONTROL WORK 
UNDER SPECIAL AUTHORIZATION 
Flood control activities pursuant to Section 205, Public 
Law 80-858. 
Preauthorization studies were initiated on Honaunau 
Area, Hawaii, 0,670; continued on Garapan Area, 
Northern Marianas, $76,914; completed on Inoaole 
Stream, Oahu, $7,471, and Lake Susupe, Northern 
Marianas, $22,737; and terminated on South Makaha 
Stream, Oahu, $101,158. 
Emergency flood control activities pursuant to Public 
Law 84-99. 
On November 23,1982, Hurricane Iwa caused major 
damages to the islands of Kauai, Oahu, and Niihau. 
Coastal flooding resulting from the storm surge and 
high wave action was concentrated on the west and 
south shores of the islands of Kauai and Oahu. All flood 
reconnaissance activities in connection with Hurricane 
Iwa were completed in June 1983 at a cost of $13,169. A 
post -flood report on Hurricane Iwa was completed in 
September 1983 for $25,000 under the Revolving Fund 
to be reimbursed with appropriated funds. A construction 
contract for repair work at Sand Island Park, Oahu, 
was awarded in June 1983 for $16,400 and completed in 
August 1983. 'Ibtal cost for Sand Island is estimated to 
be $60,000. A construction contract for repair work at 
Kekaha Beach, Kauai, was awarded in May 1983 for 
$299,600 and completed in October 1983. 'btal cost for 
Kekaha Beach is estimated to be $400,000. 
Federal cost during fiscal year was $584,145 of which 
$193,925 was for disaster preparedness, $13,169 for 
emergency operations, and $377,051 for rehabilitation 
work for Sand Island, $41,441; Kekaha Beach, 270,440; 
and Pearl City Drainage, $65,170. 
36-8

PACIFIC OCEAN DIVISION 
22. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Inspection was conducted on Hanapepe River, Kauai; 
Wailoa Stream, Hawaii; lao Stream, Maui; and 
Kaneohe -Kailua Area, Oahu, in November 1982; 
Kuliouou Stream, Oahu; and Kawainui Swamp, Oahu, 
in December 1982 for a total cost of $3,650. 
General Investigations 
23. SURVEYS 
Fiscal year costs were $1,327,651 of which $622,609 
was for navigation studies, $504,144 for flood damage 
prevention studies, $44,229 for miscellaneous activities, 
and $156,669 for coordination with other agencies. 
24. COLLECTION AND STUDY 
OF BASIC DATA 
Flood plain management services. Flood Plain 
Management Services Program comes under Section 
206 of the 1960 Flood Control Act, PL 86-645, as 
amended. Through technical services and planning guidance, 
the program provides information on floods and 
flood related information to improve planning for the 
careful use of the nation's flood plains, thereby reducing 
the potential for losses to life and property from floods 
and wave actions. Federal and non -federal agencies and 
the private sector are assisted with flood hazard evaluation 
and planning information for flood and coastal 
hazard areas. This assistance is in the form of local flood 
plain regulations, National Flood Insurance requirements, 
and Executive Order 11988 requirements for 
federal agencies. Such assistance may include flood 
information and timing, flood-water velocity, extent of 
flooding, duration of flooding, flood frequency and 
regulatory floodway limits. 
Services accomplished during fiscal year. 
Requests and responses for technical services and planning 
assistance totalled 300. Of this total, 39 were from 
other federal agencies, 126 from non -federal agencies, 
and 135 from individuals, realtors, corporations, lending 
institutions, engineers, architects and others. Of the 
300 requests, assistance resulted in 870 site specific 
responses. Costs for providing Flood Plain Management 
services during fiscal year were $163,819. 
Hydrologic Studies. For the on-going storm study 
series, a storm which struck Oahu in March 1951 was 
investigated. The meteorological storm conditions and 
rainfall data were researched and compiled during fiscal 
year at cost of $4,996. 
'Ibtal costs for collection and study of basic data during 
fiscal year were $168,815. 
36-9

TABLE 36 -A 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
COST AND FINANCIAL STATEMENT 
See 
Section Total Cost To 
in Text Project Funding FY 80 FY 81 FY 82 FY 83 Sept. 30, 1983 
1. Barbers Point 
Harbor, Oahu, 
Hawaii 
(Federal Funds) 
(Contributed 
Funds) 
2. Honolulu Harbor, 
Oahu, Hawaii 
(Federal Funds) 
(Contributed 
Funds) 
3. Kahului Harbor, 
Maui, Hawaii 
(Federal Funds) 
(Contributed 
Funds) 
4. Kaulana Bay, 
Boat Harbor, 
Hawaii, Hawaii 
(Federal Funds) 
5. Nawiliwili Harbor, 
Kauai, Hawaii 
(Federal Funds) 
(Contributed 
Funds) 
6. Port Allen 
Harbor, Kauai, 
Hawaii 
(Federal Funds) 
(Contributed 
Funds) 
7. Rota Harbor, 
Northern Marianas 
( Federal Funds) 
(Contributed 
Funds) 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint : 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Aprop. 
Cst 
Major Rehab : 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint : 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
New Work: 
Contrib. 
Cost 
$ 238,500 $ 500,000 
309,049 422,970 
$10,192,000 
5,954,543 
$17,690,000 
21,659,777 
594,095 875,801 
220,615 943,309 
1,273,521 2,480,000 1,195,000 
2,379,441 3,142,126 1,338,290 
- 171,199 
- 158,489 
- 107,000 
76,859 119,572 
21,000 79,000 
20,082 78,441 
34,500 
39,805 
-14,300 
6,701 
2,988 
569 - 
364,000 2,050,000 
208,034 2,150,766 
20,000 481,000 
8,096 38,336 
111,500 1,489,400 
67,552 1,474,014 
45,000 
28,573 
258,000 
60,535 
2,500 70,000 350,000 1,490,500 
4,009 63,308 6,356 1,821,053 
- - - 697,000 
- - - 119,716 
$29,572,178 
29,144,676 
1,469,896 
1,163,924 
16,079,095 
16,042,845 
2,038,271 
2,038,271 
205,699 
201,282 
2,388,693 
2,388,693 
6,738,020 
6,738,020 
2,414,000 
2,358,800 
30,200 
30,200 
601,000 
144,955 
2,127,724 
2,127,724 
5,750,220 
5,690,886 
233,261 
233,261 
752,645 
752,645 
892,933 
679,041 
200,000 
200,000 
2,000,000 
1, 980,204 
697,000 
119,716 
36-10

PACIFIC OCEAN DIVISION 
TABLE 36 -A (Cont.) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost To 
in Text Project Funding FY 80 FY 81 FY 82 FY 83 Sept. 30, 1983 
8. Tau Small Boat 
Harbor, American 
Samoa 
(Federal Funds) 
(Contributed 
Funds) 
10. Asquiroga Bay, 
Territory of Guam 
(Federal Funds) 
11. Matafao Shoreline, 
American Samoa 
(Federal Funds) 
12. Pago Pago Airport, 
American Samoa 
(Federal Funds) 
15. Asan Village, 
Guam 
(Federal Funds) 
(Contributed 
Funds) 
16. Iao Stream, 
Maui, Hawaii 
(Federal Funds) 
17. Kahoma Stream, 
Maui, Hawaii 
(Federal Funds) 
18. Kaneohe- Kailua 
Area, Oahu, 
Hawaii 
(Federal Funds) 
(Contributed 
Funds) 
19. Paauau Stream, 
Hawaii, Hawaii 
(Federal Funds) 
20. Waimea River, 
Kauai, Hawaii 
(Federal Funds) 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Ap-prop. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Aprop. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
72,376 121,917 
57 1,840 
9,000 20,000 
9,000 15,574 
21,000 
21,199 
27,500 423,803 
18,181 433,219 
-4,400 
26 
-5,051 
-97 
9,000 
9,000 
48,000 25,000 
53,225 25,586 
..- -.. 
310,000 903,000 
3,695,735 1,271,121 
225,000 239,000 
213,603 233,317 
260,000 705,000 
2,876,368 987,547 
5,381 
5,381 
225,051 
6,478 
241,000 
19,643 
14,500 908,400 
14,257 115,838 
- 630,000 
1,961,569 
1,961,569 
52,450 
52,296 
29,981 
29,981 
250,000 
31,427 
250,000 
28,643 
1,155,900 
363,041 
630,000 
- 546,000 12,299,000 
52,394 242,662 11,953,761 
25,000 
42,915 
8,000 
29,744 
20,000 
19,854 
739,000 
738,659 
23,500 24, 661,400 
25,359 24,652,732 
675 
75,000 
73,300 
30,000 12,000 
30,000 11, 579 
85,000 
84,686 
150,000 
134,347 
1,000 2,564,000 
1,421 109,505 
675 
310,000 
292,333 
2,712,000 
257,505 
36-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 36 -B AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Oct. 27, 1965 
Mar. 3, 1905 
Aug. 8, 1917 
Jul. 3, 1930 
Aug. 30, 19351 
Jul. 24, 1946 
Sep. 3, 1954 
Oct. 27, 1965 
Jun. 25, 1910 
Jul. 27, 1916 
Jan. 21, 1927 
Jul. 14, 1960 
Mar. 2, 1919 
Sep. 3, 1954 
Dec. 31, 1970 
BARBERS POINT HARBOR, OAHU, HAWAII 
An entrance channel 42 feet deep, 450 feet wide, and 
3,100 feet long; an inshore basin of about 46 acres, 
28 feet deep, a breakwater on the north side of the 
entrance channel, if model study shows it to be necessary; 
spending beaches with wave absorbers within the 
harbor totaling 1,320 feet in length; and a main access 
channel 12 feet deep, 80 feet wide, and 1,200 feet long 
to a small -boat harbor on the west side of the deep - 
draft harbor to be developed by local interests. 
HONOLULU HARBOR, OAHU, HAWAII 
Deepening to 35 feet the inner harbor with a general 
width of 1,200 feet and casing the curve between the 
entrance channel and the inner harbor. 
For the channel 1,000 feet long. 
Channel connecting Honolulu Harbor and 
Kapalama Basin. 
Enlarging entrance channel to present project dimensions, 
widening of the harbor basin by 320 feet and 
the maintenance of the improved 400 -foot wide portion 
of the reserved channel. 
A depth of 35 feet over the full width of 600 feet 
throughout the reserved channel; a turning basin in 
Kapalama Basin 35 feet deep by 1,000 feet wide and 
3,000 feet long; and a slip of like depth 1,000 feet 
long on the easterly side of Pier 39. 
The second entrance channel; and installation of a 
moveable -type bridge across the 2nd entrance channel. 
(Modified by the Chief of Engineers.) 
Reopening Fort Armstrong entrance channel to 45 feet, 
Main Harbor Basin and Kapalama Channel to 40 feet, 
and relocating existing project lines. 
KAHULUI HARBOR, MAUI, HAWAII 
Extending east breakwater and dredging the basin. 
For the west breakwater. 
Extend both breakwaters and enlarge dredged basin. 
Enlarge harbor basin, 600 feet wide, 2,500 feet long, 
35 feet deep. 
NAWILIWILI HARBOR, KAUAI, HAWAII 
An entrance channel 35 feet deep; a harbor basin 
1,100 feet wide, 35 feet deep, and about 1,950 feet 
long; and a rubble -mound breakwater. 
Deepening entrance channel to 40 feet; enlarging 
harbor basin; and constructing a revetted -fill area. 
(Modified by the Chief of Engineers.) 
Modification of General Navigation features. 
H. Doc. 93, 89th Cong., 
1st sess. 
Annual Report, 1905, 
p. 2565. 
H. Doc. 392, 64th Cong., 
1st sess. 
H. Doc. 753, 69th Cong., 
2nd sess. 
H. Doc. 54, 73rd Cong., 
1st sess. 
H. Doc. 705, 79th Cong., 
2nd sess. 
H. Doc. 717, 81st Cong., 
2nd sess. (Contains 
latest published map.) 
H. Doc. 93, 89th Cong., 
1st sess. 
H. Doc. 593, 61st Cong., 
2nd sess. 
H. Doc. 1330, 62nd Cong., 
3rd sess. 
H. Doc. 235, 69th Cong., 
1st sess. 
H. Doc. 109, 86th Cong., 
1st sess. (Contains 
latest map.) 
H. Doc. 609, 62nd Cong., 
2nd sess., as modified 
by the Chief of Engi - 
neers. 
H. Doc. 453, 83rd Cong., 
2nd sess. (Contains 
latest published maps.) 
River and Harbor Act. 
36-12

PACIFIC OCEAN DIVISION 
TABLE 36 -B (Cont.) AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
6 PORT ALLEN HARBOR, KAUAI, HAWAII 
Aug. 30, 19351 Construction of a breakwater 1,200 feet long; H. Doc. 30, 73rd Cong., 
dredging of a harbor basin about 1,000 feet wide, 1st sess. 
1,500 feet long, and 35 feet deep; and an entrance 
channel 500 feet wide and 35 feet deep. 
Mar. 2, 1945 Additional dredging of an area at the northerly side H. Doc. 180, 77th Cong., 
of the existing project 200 feet wide, 1,200 feet 1st sess. (Contains 
long, and 35 feet deep. latest published map.) 
16 IAO STREAM, MAUI, HAWAII 
Aug. 13, 1968 Channel enlargement, levees, a debris basin and H. Doc. 151, 90th Cong., 
related works. 1st sess. 
17 KAHOMA STREAM, MAUI, HAWAII 
Oct. 22, 1976 A debris basin 100 feet wide and 700 feet long with a H. Doc. 94-488, 94th Cong., 
capacity of 22,000 cubic yards; a rock sill, a diver - 2nd sess. 
sion levee which is 80 feet long to direct flows into 
the concrete channel; a concrete trapezoidal channel 
about 5,280 feet long; three concrete bridges with 
clear span of 50 feet; and revetted outlet extending 
70 feet seaward of the stream mouth. 
18 KANEOHE-KAILUA AREA, OAHU, HAWAII 
Dec. 31, 1970 Provide a dam and reservoir about 3.2 miles above the H. Doc. 92-141, 92nd Cong., 
mouth of Kaneohe Stream on the tributary Kamooalii 1st sess. 
Stream. Project consists of an earthfill dam 80 feet 
high, with a crest length of about 2,300 feet and about 
1,000 feet of channel improvements at the entrance of 
Kaneohe Stream to Kaneohe Bay; and reservoir with 
storage of 2,500 acre -feet of which 500 acre -feet 
would be for sediment reserve and recreation use and 
2,000 acre -feet for flood control. 
'Included in the Public Works Administration program, Sep. 6, 1933. 
36-13

TABLE 36-C 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
OTHER AUTHORIZED NAVIGATION PROJECTS 
Project 
Agana Small Boat Harbor, 'Tbrritory of Guam 
Ala Wai Small Boat Harbor, Oahu, Hawaii 
Auasi Harbor, American Samoa 
Aunuu Harbor, American Samoa 
Haleiwa Small Boat Harbor, Oahu, Hawaii 
Heeia -Kea Small Boat Harbor, Oahu, Hawaii 
Hilo Harbor, Hawaii, Hawaii 
Honokohau Small Boat Harbor, Hawaii, Hawaii 
Kahului Beach Road, Maui, Hawaii 
Kailua Small Boat Harbor, Oahu, Hawaii 
Kalaupapa Harbor, Molokai, Hawaii 
Kaunakakai Harbor, Molokai, Hawaii 
Kawaihae Harbor, Hawaii, Hawaii 
Keehi Lagoon, Oahu, Hawaii 
Kikiaola Small Boat Harbor, Kauai, Hawaii 
Lahaina Small Boat Harbor, Maui, Hawaii 
Maalaea Small Boat Harbor, Maui, Hawaii 
Manele Small Boat Harbor, Lanai, Hawaii 
Maunalua Bay Small Boat Harbor, Oahu, Hawaii 
Nawiliwili Small Boat Harbor, Kauai, Hawaii 
Ofu Small Boat Harbor, American Samoa 
Pohoiki Bay, Hawaii, Hawaii 
Reeds Small Boat Harbor, Oahu, Hawaii 
Saipan Small Boat Harbor, Northern Marianas 
Waianae Small Boat Harbor, Oahu, Hawaii 
Wake Island Harbor, Wake Island 
Wells Harbor, Territory of Guam 
_ 
Status 
Completed 
Deferred 
Completed 
Completed 
Completed 
Deferred 
Completed 
Completed 
Completed 
Deferred 
Completed 
Deferred 
Active 
Completed 
Active 
Inactive 
Active 
Completed 
Deferred 
Completed 
Completed 
Completed 
Deferred 
Active 
Completed 
Inactive 
Completed 
For Last 
Full Report 
See Annual 
Report for: 
1978 
1976 
1982 
1982 
1978 
1972 
1982 
1971 
1976 
1967 
1968 
1966 
1981 
1956 
1981 
1977 
1981 
1967 
1972 
1976 
1976 
1979 
1967 
1982 
1979 
1950 
1950 
'Authorized by the Chief of Engineers and completed in 
October 1977. In addition, Contributed Funds of $282,747 for 
Construction. 
'Authorized by the Chief of Engineers and completed in 
February 1982. In addition, Contributed Funds of $86,563 for 
Construction. 
'Authorized by the Chief of Engineers and completed in 
February 1982 In addition, Contributed Funds of $231,437 for 
Construction. 
4Authorized by the Chief of Engineers and completed in 
November 1975. In addition, Contributed Funds of $410,077 
for Construction and $84,388 for Operation and Maintenance. 
6Completed in March 1970. In addition, Contributed 
Funds of $30,568 for Construction. 
6Authorized by the Chief of Engineers and completed in 
April 1976 
7Authorized by the Chief of Engineers and completed in 
September 1967. 
8In addition, Contributed Funds of $62,102 for Construction. 
'Abandonment authorized by R&H Act of 1965 (HD 98, 
89th Congress, 1st Session). 
"Authorized by the Chief of Engineers and completed in 
December 1965. In addition, Contributed Funds of $370,845 
for Construction. 
"Authorized by the Chief of Engineers and completed in 
November 1974. In addition, Contributed Funds of $405,471 
for Construction. 
"Authorized by the Chief of Engineers and completed in 
August 1965. In addition, Contributed Funds of $61,953 for 
Construction. 
';Authorized by the Chief of Engineers and completed in 
April 1979. 
'4In addition, Contributed Funds of $1,791,068 for Construction. 
'6Completed in 1941 and Maintenance transferred to 
Department of Navy. 
36 14 
Cost to September 30, 1983 
Operation and 
Construction Maintenance 
$ 937,7981 $ 11,196 
40,117 - 
1,033,0152 - 
1,783,129; - 
527,0474 208,902 
1,481 - 
5,423,440 3,667,533 
781,0366 63,693 
751,8676 - 
157,9977 3,127 
138,188 292,441 
5,983,5018 61,800 
3,348,000k 41,857 
193,000 - 
186,937 - 
195,000 - 
372,00010 255,256 
30,378 - 
584,51311 30,707 
980,01812 668,354 
432,52313- 
194,000 - 
1,940,011'14 17,767 
- 14,493 
2,448,0561 2,111

PACIFIC OCEAN DIVISION 
TABLE 36 -D OTHER AUTHORIZED BEACH EROSION CONTROL PROJECTS 
For Last Cost to September 30, 1983 
Full Report 
See Annual Operation and 
Project Status Report for: Construction Maintenance 
Afono Area and Aoa Area, American Samoa Completed 1978 $254,0151 - 
Haleiwa Beach, Oahu, Hawaii Completed 1967 240,1482 - 
Hanapepe Bay, Kauai, Hawaii Deferred 1965 - - 
Kaaawa Beach, Oahu, Hawaii Completed 1976 176,488; - 
Kapaa Tobwn, Kauai, Hawaii Completed 1977 158,9164 - 
Kekaha Beach, Maui, Hawaii Completed 1981 999,9966 - 
Kihei Beach, Maui, Hawaii Completed 1972 154,3136 - 
Kualoa Regional Park, Oahu, Hawaii Terminated 1982 355,4727 - 
Pago Pago to Nuuuli, American Samoa Active 1978 394,187" - 
Poloa Area, American Samoa Completed 1978 136,040" - 
Sand Island, Oahu, Hawaii Completed 1981 301,879"o - 
Vatia Area, American Samoa Completed 1978 154,309" - 
Waikiki Beach, Oahu, Hawaii Active 1979 729,08712 85,043 
Waimea Beach, Kauai, Hawaii Deferred 13 
'Authorized by the Chief of Engineers and completed in In addition, $177,300 in Contributed Funds. 
October 1977. In addition, $209,549 in Contributed Funds. "Authorized by the Chief of Engineers and Phase I com- 
2Completed in April 1965. In addition $160,098 in Con- pleted in September 1978. In addition, $312,480 in Contributed 
Funds. tributed Funds. 
'Authorized by the Chief of Engineers and completed in .Authorized by the Chief of Engineers and completed in 
August 1975. In addition, $97,075 in Contributed Funds. October 1977. In addition, $101,547 in Contributed Funds. 
4Authorized by the Chief of Engineers and completed in "'Authorized by the Chief of Engineers and completed in 
September 1976. In addition, $60,000 in Contributed Funds. April 1981. In addition, $401,000 in Contributed Funds. 
"Authorized by the Chief of Engineers and completed in "Authorized by the Chief of Engineers and completed in 
December 1980. In addition, $1,672,524 in Contributed Funds. October 1977. In addition, $132,075 in Contributed Funds. 
"Authorized by the Chief of Engineers and completed in '2In addition $82,000 in Advanced Funds and $17,640 in 
June 1971. In addition, $154,313 in Contributed Funds. Contributed Funds. 
7Authorized by the Chief of Engineers and terminated in '3No previous full report; project authorized by R&H Act 
April 1980 as a Circuit Court ruled sand mining to be illegal. of 1958. 
TABLE 36 .E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to September 30, 1983 
Full Report 
See Annual Operation and 
Project Status Report for: Construction Maintenance 
Hanapepe River, Kauai, Hawaii Completed 1967 $ 784,8671 - 
Kaunakakai Stream, Molokai, Hawaii Completed 1950 73,7482 - 
Kawainui Swamp, Oahu, Hawaii Completed 1967 1,265,567 - 
Kuliouou Stream, Oahu, Hawaii Completed 1971 1,000,0004 - 
Namo River, Territory of Guam Completed 1982 2,416,3146 - 
Wailoa Stream and Tributaries, Hawaii, Hawaii Completed 1966 1,044, 8886 - 
'Completed in November 1966. In addition, $11,953 in 
Contributed Funds. 
2Authorized by the Chief of Engineers and completed in 
December 1950. 
'Completed in August 1966. 
4Authorized by the Chief of Engineers and completed in 
February 1970. In addition, $540,335 in Contributed Funds. 
5Authorized by the Chief of Engineers and completed in 
April 1982 
6Completed in August 1965. 
36-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 36 -G DEAUTHORIZED PROJECTS 
For Last 
Full Report Date Federal Contributed 
See Annual and Funds Funds 
Project Report for: Authority Expended Expended 
Hana Small Boat Harbor, 1967 November 1977 $ - - 
Maui, Hawaii HD #94-413 
Hanalei Small Boat Harbor, 1967 November 1981 - - 
Kauai, Hawaii HD #97 -59 
Kaimu Black Sand Beach, 1975 July 1981 86,235 - 
Hawaii, Hawaii Director of 
Civil Works 
Kapaakea Homestead Flood Control, 1979 July 1981 221,500 - 
Molokai, Hawaii Director of 
Civil Works 
Kewalo Harbor, Oahu, Hawaii 1976 September 1975 98,800 - 
Director of 
Civil Works 
Talofofo Bay Shore Protection, - August 1981 80,764 - 
Guam Director of 
Civil Works 
TABLE 36-H RECONNAISSANCE AND CONDITION SURVEYS 
Date Fiscal Year 
Project Survey Conducted Cost 
Agana Small Boat Harbor, Guam August 1983 $ 7,831 
Auasi Small Boat Harbor, American Samoa July 1983 4,822 
Aunuu Small Boat Harbor, American Samoa July 1983 4,822 
Haleiwa Small Boat Harbor, Oahu, Hawaii August 1983 14,738 
Hilo Harbor, Hawaii, Hawaii September 1983 11,686 
Honokohau Small Boat Harbor, Hawaii, Hawaii September 1983 9,494 
Honolulu Harbor, Oahu, Hawaii August 1983 30,256 
Kahului Harbor, Maui, Hawaii August 1983 18,625 
Kaunakakai Harbor, Molokai, Hawaii September 1983 9,389 
Kawaihae Harbor, Hawaii, Hawaii September 1983 11,542 
Manele Small Boat Harbor, Lanai, Hawaii September 1983 8,303 
Nawiliwili Harbor, Kauai, Hawaii February 1983 15,313 
Nawiliwili Small Boat Harbor, Kauai, Hawaii February 1983 4,184 
Ofu Small Boat Harbor, American Samoa July 1983 4,822 
Port Allen Harbor, Kauai, Hawaii February 1983 16,290 
Tau Small Boat Harbor, American Samoa July 1983 4,823 
Waianae Small Boat Harbor, Oahu, Hawaii August 1983 13,974 
36-16

PORTLAND, OR, DISTRICT* 
The territorial limits of the Portland District include the 
Pacific coastal drainage area of the State of Oregon, the 
portions of the States of Oregon and Washington which 
lie within the Columbia River watershed downstream of 
the Umatilla Bridge below McNary Dam, and south 
central Oregon west of the Malheur River and the Steens 
Mountains, but not including that part which drains into 
the Klamath Lake and River. 
IMPROVEMENTS 
Navigation 
1. Bandon Small Boat Basin, Coquille, OR ... 
2. Charleston Channel, Coos Bay, OR ...... 
3. Chetco River, OR ....................... 
4. Columbia and Lower Willamette Rivers 
below Vancouver, WA, and 
Portland, OR ........................... 
5. Columbia River at Baker Bay, WA ........ 
6. Columbia River between Chinook, WA, 
and Head of Sand Island ................. 
7. Columbia River at the Mouth, 
OR and W A ............................ 
8. Columbia River between Vancouver, WA 
and The Dalles, OR..................... 
9. Coos Bay, OR ........................... 
10. Coos and Millicoma Rivers, OR ........... 
11. Coquille River, OR ...................... 
12. DI)epoe Bay, OR ......................... 
13. Lake River, WA ........................ 
14. Navigation Work Under Special 
Authorization .......................... 
15. Nehalem Bay, OR ....................... 
16. Port Orford, OR ........................ 
17. Project Condition Surveys ............... 
18. Rogue River Harbor at Gold Beach, OR.... 
19. Siuslaw River, OR ....................... 
20. Skamokawa Creek, WA ................. 
21. Skipanon Channel, OR.................. 
22. South Channel, Government Island, OR... 
23. Tillamook Bay and Bar, OR ............. 
24. Umpqua River, OR ..................... 
25. Willamette River above Portland and 
Yamhill River, OR ...................... 
26. Willamette River at Willamette Falls, 
OR ..................................... 
27. Winchester Bay, Umpqua River, OR ...... 
28. Yaquina Bay and Harbor, OR ........... 
29. Yaquina River, OR ..................... 
Flood Control 
30. Applegate Lake, Rogue River Basin, OR.. . 
31. Beaver Drainage District, Columbia 
County, OR ............................ 
Page Page 
37-2 32. Blue River Lake, OR ..................... 37-13 
37-2 33. Cottage Grove Lake, OR ................ 37-13 
37-2 34. Dorena Lake, OR ........................ 37-13 
35. Elk Creek Lake, Rogue River Basin, OR ... 37-14 
36. Fall Creek Lake, OR ..................... 37-14 
37-3 37. Fern Ridge Lake, OR..................... 37-14 
37-4 38. Flood Control Work Under Special 
Authorization ........................... 37-15 
37-4 39. Inspection of Completed Flood Control 
Projects................................. 37-16 
37-4 40. Inspection of Non-Federal Levees ......... 37-16 
41. Lower Columbia River Basin, 
37-5 OR and WA ............................. 37-16 
37-5 42. Lower Columbia River Basin Bank 
37-6 Protection, OR and WA ................. 37-17 
37-6 43. Mt. St. Helens & Vicinity, WA ............ 37-17 
37-7 44. Scappoose Drainage DI)istrict, OR......... 37-17 
37-7 45. Scheduling Flood Control Reservoir 
Operations .............................. 37-18 
37-7 46. Trask River, Tillamook County, OR ....... 37-18 
37-7 47. Tualatin, OR ............................ 37-18 
37-7 48. Wahkiakum County Consolidated Diking 
37-7 District No. 1, WA ....................... 37-18 
37-8 49. Willamette River Basin, OR ............. 37-18 
37-8 50. Willamette River Basin Bank Protection, 
37-9 OR ..................................... 37-19 
37.9 Multiple-Purpose Projects 
37-9 Including Power 
37-9 51. Bonneville Lock and Dam - Lake 
37-10 Bonneville, OR and WA................. 37-19 
52. Cougar Lake, OR ....................... 37-20 
37-10 53. Detroit Lake, OR ........................ 37-21 
54. Green Peter-Foster Lakes, OR............. 37-21 
37-11 55. Hills Creek Lake, OR ................... 37-22 
37-11 56. John Day Lock and Dam - Lake Umatilla, 
37-11 OR and WA ............................. 37-22 
37-12 57. Lookout Point Lake, OR................. 37-23 
58. Lost Creek Lake, Rogue River Basin, 
37-12OR ..................................... 37-23 
59. The Dalles Lock and Dam - Lake Cello, 
37-13 WA and OR ............................ 37-24 
37-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
General Investigations Page 
60. Surveys ............................... 37-24 
61. Collection and Study of Basic Data ...... 37-24 
62. Continuation of Planning and 
Engineering ........................... 37-25 
63. Advance Engineering and Design ....... 37-25 
Tables 
Table 37-A 
Table 37-B 
Table 37-C 
Table 37-E 
Table 37-F 
Table 37-G 
Cost & Financial Statement ... 37-26 
Authorizing Legislation ....... 37-33 
Other Authorized Navigation 
Projects ...................... 37-43 
Other Authorized Flood Control 
Projects ...................... 37-44 
Other Authorized Multiple 
Purpose Projects............. 
Including Power .............. 37-48 
Deauthorized Projects ........ 37-48 
Page 
Table 37-H Columbia and Lower Willamette 
River Below Vancouver, WA and 
Portland, OR ................. 37-49 
Table 37-I Navigation Activities Pursuant 
to Section 107, Public Law 
86-645........................ 37-50 
Table 37-J Willamette River at Willamette 
Falls, OR, Principal Features of 
Existing Canal and Locks ..... 37-50 
Table 37-K Flood Control Reservoir 
Operations .................... 37-51 
Table 37-L Lower Columbia River Basin, 
OR and WA Levees and 
Improvements to Existing 
Works........................ 37-52 
Table 37-M Willamette River Basin 
Comprehensive Plan .......... 37-53 
Table 37-N Principal Data Concerning 
Navigation Lock, Spillway Dam 
and Powerplant .............. 37-54 
Navigation 
1. BANDON SMALL BOAT BASIN, COQUILLE 
RIVER, OR 
Location. Coquille River rises in Coast Range, flows 
generally westerly for about 100 miles, and empties into 
the Pacific Ocean at Bandon, OR, 225 miles south of 
mouth of Columbia River and 420 miles north of San 
Francisco Bay. (See NOAA charts 18580 and 18186.) 
Existing project. Provides for a protective rubblemound 
NOAA breakwater and an entrance and access 
channel, 13 feet deep, for a small boat basin at Bandon. 
Mean lower low water is plane of reference. Tidal range 
between mean lower low water and mean higher high 
water at mouth is 7 feet and extreme about 10 feet. 
Local cooperation. Fully complied with. 
Terminal Facilities. At Bandon, there is a privately 
owned mill dock used exclusively for shipping lumber on 
coastwise vessels, a public owned wharf, and a smallboat 
basin open to all on equal terms. 
Operations during fiscal year. New work: Project 
was completed. 
2. CHARLESTON CHANNEL, COOS BAY, OR 
Location. Charleston Channel is located in south 
slough tributary of Coos Bay. The Charleston Channel 
follows the south slough from its confluence with the 
main channel of Coos Bay south to the Cape Arago 
highway bridge. 
Existing project. Plan of improvement provides for a 
150 foot wide channel 6,800 feet long with depths 
between 16 to 17 feet mean lower low water. Also provides 
for a 180 foot by 900 foot turning basin and 100 by 
400 foot access channel, both - 16 feet mean lower low 
water. 
Localcooperation. Port of Coos Bay, project sponsor. 
Operations during fiscal year. New work: Contractor 
completed rock probing to determine quantity of rock 
to be removed in channel. DI)redging will be completed in 
FY 1984. 
3. CHETCO RIVER, OR 
Location. Rises in Siskiyou Mountains of Coast 
Range at an elevation of 4,000 feet, flows for about 51 
miles in a circuitous route, and empties into Pacific 
Ocean at Brookings, OR, 300 miles south of entrance to 
Columbia River and 345 miles north of San Francisco 
Bay. (See National Oceanic and Atmospheric Administration 
Charts 18600 and 18203.) 
Existing project. Provides for two jetties at the 
mouth of the river. Modification in 1965 authorized an 
entrance channel 120 feet wide by 14 feet deep; a barge 
turning basin about 250 feet wide, 650 feet long, and 14 
feet deep; and a small boat access channel 100 feet wide 
by 12 feet deep. Also authorized was a 450-foot extension 
of north jetty with an increase in elevation of existing 
portion and a protective dike about 1,800 feet long with a 
top elevation of 18 feet. Mean lower low water is plane of 
reference. Tidal range between lower low water and 
mean higher high water is 6.9 feet and extreme is about 
12 feet. Construction of jetties was completed December 
1957. Removal of rock pinnacles and an abandoned 
bridge structure was accomplished in June 1959. Under 
authorized modification of October 1965, two contracts 
were completed. Construction of entrance channel and 
extension of north jetty was initiated in July 1968 and 
completed in July 1969. Construction of a protective dike, 
turning basin and small boat access channel was started 
in September 1969 and completed in March 1970. (For 
plan of improvement authorized by Public Law 97-88, 
Dec. 4, 1981, see Section 63.) 
37-2

PORTLAND, OREGON DISTRICT 
Local cooperation. Fully complied with. 
Terminal facilities. The Port Commission of Brookings 
has developed two large boat basins, one for commercial 
fishing boats and the other for small private 
boats, and a public boat launching ramp. There are four 
fish receiving docks and a sea-going barge dock for 
lumber loading and storage. There is also a privately 
owned marina and a Coast Guard Station. 
Operations during fiscal year. Maintenance: A 
total of 59,715 cubic yards of material was removed by the 
U.S. hopper dredge Yaquina. The sand-bypasser Sandwick 
displaced shoal areas to provide longer periods of 
channel depths for navigation traffic within the authorized 
project. 
4. COLUMBIA AND LOWER WILLAMETTE 
RIVERS BELOW VANCOUVER, WA, AND 
PORTLAND, OR 
Location. The Columbia River rises in British Columbia, 
through which it flows for 425 miles. It enters the 
United States in northeastern Washington, and empties 
into the Pacific Ocean 645 miles north of San Francisco 
Bay and 160 miles south of Strait of Juan DeFuca. Total 
length of river is 1,210 miles. (See NOAA Charts 18520, 
18521, 18522,18523,18524, 18526, & 18531; also Geological 
Survey Map of Washington). Willamette River rises in 
in CascadeRangein southwestern Oregon, flowsnortherly, 
and empties into Columbia River about 100 miles from 
the sea. Its length from source of Middle Fork is about 294 
miles. Project embraces 103.5 miles of Columbia River 
below Vancouver, WA, and 14.6 miles of Willamette 
River below Portland, OR. (See NOAA Chart 18526 and 
Geological Survey Map, State of Oregon.) 
Existing project. Provides for a channel 35 feet deep 
and 500 feet wide from River Mile 106.5 to 105.5, the 
distance between existing highway and railroad bridges; 
a channel 40 feet deep and 600 feet wide from Vancouver, 
WA, River Mile 105.5 to mouth of Columbia River, River 
Mile 3; a turning basin at Vancouver, WA, 40 feet deep, 
800 feet wide, and about 5,000 feet long; a turning basin at 
Longview, WA, 40 feet deep, average width of 1,200 feet, 
and about 6,000 feet long; and a channel 40 feet deep in 
the Willamette River with varying widths of 600 to 1,900 
feet from mouth (River Mile 0) to Broadway Bridge (River 
Mile 11.6) which encompasses Portland Harbor area, subject 
to provisions that channel from mouth of Willamette 
River to turning basin at Vancouver, WA, be limited to 
500 feet in width until need for additional width is demonstrated 
by developed traffic. Existing project also provides 
for auxiliary channels 10 feet deep and 300 feet wide 
near Cathlamet, WA; 30 feet deep and 300 feet wide in St. 
wHiedleen cso (nOnreecgtionng) Cuphpaenrn eenl;d a onfd S 3t0. Hfeeelte dnes epC hanandn 5e0l0 w feiteht 
main ship channel of Columbia; 24 feet deep and 200 feet 
wide along frontage of town of Rainier, OR, extended at 
its upper and lower ends to deep water in Columbia River, 
8 feet deep and 150 feet wide from this depth in Columbia 
River through old mouth of Cowlitz River to a point about 
3,000 feet upstream from present terminus of harbor line; 
a channel from Longview Port dock downstream along 
pierhead line and past Weyerhaeuser Timber Co. plant at 
Longview to a connection with main ship channel below 
Mount Coffin, the downstream 2,400 feet of this channel 
to be 30 feet deep and 300 feet wide and remainder to be 28 
feet deep and 250 feet wide; construction of a small-boat 
mooring basin at Astoria, OR, to include a sheet-pile, 
sand-filled breakwater about 2,400 feet long with a 30- 
foot roadway along its full length, and steel pile shore 
wings totaling about 1,460 feet long and for stone-andpile 
dikes and revetments. Plane of reference in estuary 
from mouth to Harrington Point is mean lower low 
water; thence to Portland and Vancouver, low water. 
Tidal range between mean lower low water and mean 
higher high water at mouth of Columbia is about 8 feet, 
and at Portland and Vancouver about 3 feet at low stages 
of rivers. Extreme tidal ranges are about 13 and 3 feet, 
respectively. Annual freshets have little effect on stage of 
tide at mouth of Columbia; at Portland and Vancouver 
they average about 12 feet, while highest known reached 
a stage of 33 feet above low water at Portland. 
Work on the 40-foot channel in Columbia River from 
Portland, OR, and Vancouver, WA, to the sea was completed 
in 1976 except for observation of channel to determine 
if additional control structures or dredging will be 
required. Auxiliary channel in vicinity of Longview was 
completed in 1949, and improvement of mouth of Cowlitz 
River and small boat mooring basin at Astoria were 
completed in 1950. Project depths are maintained all year 
except for the period immediately following the annual 
freshet in May-June when shoaling occurs at several 
locations. Timing of vessel movement with tidal fluctuations 
permit maximum draft conditions. In Columbia 
and Willamette Rivers between mouth and Broadway 
Bridge at Portland a depth of 40 feet at low tide and 42 
feet at high tide is practicable all year. In Columbia River 
between mouth of Willamette River and Vancouver, WA, 
depths of 40 and 42 feet at low and high tide, respectively, 
are practicable all year. (For details relating to previous 
project, see pages 1995 and 1998 of Annual Report for 
1915 and page 1746 of Annual Report for 1938.) 
Local cooperation. Fully complied with. Requirements 
are described in full on page 37-3 of FY 1981 
Annual Report. 
Terminal facilities. At Portland, OR, there are six 
Port of Portland terminals consisting of 43 berths with 
total capacity of 8,800,000 tons equipped to handle general 
cargo, bulk cargo, lumber, automobiles, lift on-lift off 
and roll on-roll off containers, and breakbulk vessels. 
The Port of Portland owns and operates a major ship 
repair yard, which includes the West Coast's largest, and 
the world's third largest, floating dry dock. The Port of 
Portland also has a 450,000-cubic-foot cold storage warehouse. 
Also available in the harbor area are privately 
foopre rraetceediv fiancgi,l itsiteosr iwnigt ha tnodta ol uctalopaadciitnyg opf e1t6r,o2l0e0u,m00, 0 wtooonds 
chips, grain, logs, sand and gravel, cement and steel 
products. 
At Astoria, OR, there is a terminal with facilities for 
receiving and handling all types of general cargo. 
At Vancouver, WA, there are municipal facilities capable 
of berthing five ships simultaneously. Each berth is 
completely outfitted with mechanical and lift facilities 
37-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
for receiving and handling all types of cargo. The port 
has a low dock to handle roll on-roll off and side-port 
discharging vessels. The grain terminal has a storage 
capacity of 4,500,000 bushels. 
Port of Longview has a public terminal on Columbia 
River and a privately owned grain elevator with a capacity 
of 6,900,000 bushels. This port also has a heavy lift 
facility, with a capacity of about 600 tons. 
Port of Kalama has two berthing areas, one port 
owned and one private, with a capacity of 6,000,000 tons. 
At other locations on Columbia River between Portland 
and Columbia River entrance there are sufficient 
private facilities to accommodate river vessels and fishing 
craft. These facilities, with planned extensions, are 
considered adequate for existing commerce. (For details 
see Port Series Nos. 33 and 34, Corps of Engineers, published 
in 1974 and 1975 respectively.) 
Operations during fiscal year. Maintenance: Regular 
maintenance continued through the year. A total of 
2,533,621 cubic yards of material was removed by the 
U.S. hopper dredges Biddle, Essayons, and Yaquina, 
and contract hopper and pipeline dredges removed 
87,833 cubic yards. The pipeline dredge Oregon removed 
3,724,168 cubic yards. Eruption of Mount St. Helens on 
May 18,1980 and the ensuing "mud flow" deposited more 
than 50,000,000 cubic yards of material in the Columbia 
River near Longview. Immediate start of dredging operations 
permitted deep draft vessel traffic to resume operations 
on May 23,1980, with full draft passage available 
by July 30, 1980. Dredging activities are continuing. 
Emergency dredging, to September 30, 1983, including 
both pipeline and hopper dredges, equalled 39,558,126 
cubic yards of material. 
5. COLUMBIA RIVER AT BAKER BAY, WA 
Location. Baker Bay is a shallow body of water about 
15 square miles in extent on the north side of Columbia 
River near its mouth. Bay is separated from river by 
Sand Island, a low-lying sand bar only a few feet above 
high tide level. (See NOAA Chart 18521.) 
Existing project. A mooring basin 10 and 12 feet 
deep, about 20 acres in extent with protecting breakwaters; 
and a west channel 10 feet deep connecting basin 
with deep water in Columbia River, with a width of 150 
feet, increased to 200 feet for 2,000 feet at southerly end; a 
channel east of Sand Island to Port of Ilwaco, a distance 
of about 5 miles. Mean lower low water is plane ence. Tidal of refer- range between mean lower low water and 
mean higher high water is about 8 feet, and extreme 
about 13 feet. 
Channel extending through easterly passage of Sand 
Island was completed in 1934. This portion of authorized 
project is not passable and is not maintained at the 
present time. Dredging west channel to 8 feet was 
accomplished September 1948. Deepening west channel 
to 10 feet, and boat basin and breakwater construction at 
Ilwaco, WA, finished December 1957, completed the 
project. 
Local cooperation. Fully complied with. 
Terminal facilities. Wharves, floats, ramps, and 
berths, for fishing craft, barges and tow-boats. Smallboat 
basin and protecting breakwater provides moorings 
for numerous fishing and recreational craft all year. 
Facilities are considered adequate for existing commerce. 
Operations during fiscal year. Maintenance: A 
total of 24,835 cubic yards of material was removed by 
the contract hopper dredge Westport. 
6. COLUMBIA RIVER BETWEEN CHINOOK, 
WA, AND HEAD OF SAND ISLAND 
Location. At easterly end of Baker Bay, lying on 
north side of Columbia River near mouth. (See Coast and 
Geodetic Survey Chart 6151.) 
Existing project. Channel 10 feet deep and 150 feet 
wide, extending from head of Sand Island to Chinook: a 
turning and mooring basin at upper end of channel, 10 
feet deep, 660 feet long, and ranging from 275 to 500 feet 
wide; reconstruction of easterly 393 feet of existing 
breakwater; and extension of existing breakwater easterly 
and thence northerly to connect with shore in vicinity 
of Portland Street, Chinook, WA. Tidal range between 
mean lower low water and mean higher high water is 
about 8 feet and extreme about 13 feet. 
Project as originally authorized was completed in 
1940. The 10-foot channel depth modification was accomplished 
September 1958. Rehabilitation of existing breakwater 
was completed September 1962. 
Local cooperation. Fully complied with. 
Terminal facilities. Chinook Packing Company 
owns a wharf for receiving fresh fish, and one additional 
fish buying company is located at Chinook. A portion of 
wharf is also used as a public landing. At upper end of 
channel there is a turning and mooring basin with facilities 
for mooring 350 fishing and recreational craft. Adequate 
terminal and mooring facilities include a public 
launching ramp, hoist with 10-ton capacity and suitable 
supply facilities. 
Operations during fiscal year. Maintenance: Contract 
pipeline and hopper dredges removed 332,179 cubic 
yards of material. 
7. COLUMBIA RIVER AT THE MOUTH, 
OR, AND WA 
Location. The Columbia River entrance is 645 miles 
north of San Francisco Bay. Project is about 120 miles 
downstream of Portland, OR, and Vancouver, WA. For 
description of Columbia River see Improvement No. 3. 
Existing project. Provides for a channel across bar 
48 feet deep (mean lower low water), one-half mile wide to 
be secured by two rubblemound jetties, spur jetty "B" on 
the north shore and by dredging. The north jetty is about 
2.5 miles long and the jetty about 6.6 miles long. The 
unconstructed spur jetty "B" would be about 1 mile long. 
Tidal range on bar between mean lower low water and 
mean higher high water is about 8 feet, and extreme 
about 13 feet. 
The originally authorized project depth of 40 feet was 
completed in 1918; south jetty completed in 1914 and 
37-4

PORTLAND, OREGON DISTRICT 
north jetty in 1917. A spur jetty (jetty "A") was completed 
in 1939 (repaired in 1961) for the purpose of channel 
stabilization. Spur jetty "B" currently is classified "inactive." 
Dredging of the 48-foot bar channel started April 
1956, was completed in September 1957. South jetty 
rehabilitation started June 1962, was completed September 
1964. North jetty rehabilitation started January 
1965, was completed April 1965. Project dimensions were 
available at end of fiscal year. (For details relating to 
previous projects, see page 1999, Annual Report for 1915 
and page 1740 of Annual Report for 1938.) 
Local cooperation. Fully complied with. Local interests 
contributed $500,000 toward construction of the 
north jetty which was completed in 1917. 
Operations during fiscal year. Maintenance: The 
U.S. hopper dredge Essayons removed 969,880 cubic 
yards of material and the contract dredge Manhattan 
Island removed 1,003,873 cubic yards. 
Rehabilitation: Contractual work completed. 
New work, Code 710: Construction was completed on 
the access road, parking and boundary fencing at Ft. 
Stevens State Park under State of Oregon cost-sharing 
agreement. 
8. COLUMBIA RIVER BETWEEN VANCOUVER, 
WA, AND THE DALLES, OR 
Location. On Columbia River, between Interstate 
Bridge at Vancouver, WA, 106.5 miles above mouth and 
The Dalles, OR, mile 191, a distance of 84.5 miles. For 
description of Columbia River, see Improvement No. 3, 
"Columbia and Lower Willamette Rivers Below Vancouver, 
WA, and Portland, OR." 
Existing project. Channel 27 feet deep at low water 
and 300 feet wide between Vancouver, WA, and The 
DI)alles, OR, 84.5 miles; a channel 10 feet deep at low water 
and 300 feet wide at upstream entrance to Oregon 
Slough, OR, a suitable turning basin adjacent to site of 
port development in vicinity of Camas and Washougal, 
WA, a boat basin at Hood River, OR, 500 by 1,300 feet 
and 10 feet deep at normal Bonneville pool level, with a 
connecting channel of same depth to deepwater, and a 
protecting breakwater on easterly side; a barge channel 
to waterfront at Bingen, WA, 10 feet deep at normal 
Bonneville pool level, 200 feet wide and about 1 mile long, 
and an access channel 7 feet deep at normal Bonneville 
pool level, 100 feet wide and about 1,000 feet long, to a 
natural mooring basin for small boats near east end of 
channel; and construction of The Dalles small boat 
basin, to provide a breakwater and shear boom protected 
basin about 400 by 800 feet in size with depth of 8 feet 
below a pool elevation of 72.5 feet at mean sea level. Tidal 
range between mean lower low water and mean higher 
high water at Vancouver is about 3 feet and at Bonneville 
about 0.2 foot at low stages of the river. Extreme 
tidal ranges are about 4 feet and 0.4 foot, respectively. 
Existing project is complete. Construction of The 
Dalles small boat basin, was completed in 1949. Channel 
dredging at upper end of Oregon Slough was accomplished 
in 1957. Project depth of 27 feet between Bonneville 
and The Dalles, OR, was achieved April 1959. The 
27-foot channel depth between Vancouver, WA, and 
Bonneville, OR, was completed May 1960. Improvement 
of lower entrance of Bonneville Dam lock was completed 
in May 1961. At the present time, the channel is maintained 
to a depth of 16 feet, which is adequate for using 
traffic. Construction of a boat basin at Hood River, OR, 
and of Camas-Washougal, WA, turning basin was accomplished 
February 1962. Construction of a barge channel 
in Columbia River near Bingen, WA, was completed 
September 1963. 
Local cooperation. Fully complied with. 
Terminal facilities. At Vancouver, WA, upstream of 
Interstate Highway bridge at River Mile 108.1 on site of 
former shipyard are numerous idle ship-building facilities 
equipped with railway and river moorage facilities. 
Also in this area are a paper-storage warehouse with 
barge slip, two boat building businesses (one temporary), 
and a storage dock with gantry crane. Sites are available 
for development to suit lessee. 
At Camas, WA, about 13.5 miles upstream from Vancouver, 
there is a private wharf used for transfer of 
papermill supplies and paper to and from barges, and 
facilities for discharging bulk oils from barges. 
At Port of The Dalles (mile 44 above Bonneville) there 
is a municipal wharf 125 by 1,100 feet for use by tugs and 
barges. There are two 1-story timber and corrugated iron 
warehouses, each 94 by 461 feet, on this wharf. A private 
elevator with a capacity of 40,000 bushels and a public 
elevator of 1,113,800-bushel capacity for handling bulk 
grain to tugs and barges are also at The I)alles. Public 
elevator has rail, truck, and water connections. There is a 
port owned rail connection about three-fourths mile 
below municipal wharf where certain types of cargo may 
be handled between railroad cars and tugs or barges. 
At numerous locations over entire waterway are log 
rollways for transfer of logs to water from trucks and 
public and private boat basins. Facilities are considered 
adequate for present commerce. 
Operations during fiscal year. Maintenance: The 
U.S. hopper dredge Yaquina removed 166,650 cubic 
yards of material. 
9. COOS BAY, OR 
Location. On Oregon coast 200 miles south of mouth 
of Columbia River and 445 miles north of San Francisco 
Bay. It is about 13 miles long and 1 mile wide, with an 
area at high tide of about 15 square miles. (See NOAA 
Charts 18580 and 18587.) 
Existing project. Two rubblemound, high-tide jetties 
at entrance; a channel across the outer bar 45 feet deep 
and 700 feet wide, reducing gradually to 35 feet deep and 
300 feet wide near River Mile 1 and continuing to about 
river mile 9; thence a channel 35 feet deep and generally 
400 feet wide to river mile 15; an anchorage area 35 feet 
deep, 800 feet wide, and 1,000 feet long at Empire (River 
Mile 5.5); turning basins at North Bend (River Mile 12.5) 
and Coalbank (River Mile 14.7) 35 feet deep, 650 feet wide 
and 1,000 feet long; a channel 22 feet deep and 150 feet 
wide from Smith's Mill (River Mile 15) to Millington 
(River Mile 17); a small boat basin, about 500 by 900 feet 
37-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
at Charleston, with a connecting channel, 10 feet deep 
and 150 feet wide, to deep water in Coos Bay, and construction 
of a protecting breakwater and bulkhead. 
Plane of reference is mean lower low water. Tidal range 
between lower low water and mean higher high water is 
7 feet and extreme is about 11 feet at both the entrance 
and at Coos Bay. 
South jetty was completed in 1928, north jetty in 1929, 
and 24-foot channel in 1937. The south jetty was restored 
in 1941 and 1942 by construction of a concrete cap for full 
length of the jetty. Excavation of channel to 30 feet deep 
and generally 300 feet wide from entrance to Isthmus 
Slough was completed in 1951. Dredging outer bar channel 
to a depth of 40 feet, decreasing to 30 feet at Guano 
Rock was completed in 1952. Construction of the Charleston 
Channel and small-boat basin was completed in 
September 1956. Rehabilitation of south jetty was started 
in June 1962 and completed DI)ecember 1963. Repair of 
north jetty was completed in August 1970. Construction 
of the deeper and wider channel to mile 15 was completed 
in 1979. (For details relating to previous projects, see 
page 1987 of Annual Report for 1915 and page 1728 of 
Annual Report for 1938.) 
Local cooperation. Fully complied with. Requirements 
are described in full on page 37-5 of FY 1981 
Annual Report. 
Terminal facilities. At North Bend there is a municipal 
dock 649 feet long fronting on channel, about 2,380 
feet of privately owned mill docks, and three oil-receiving 
terminals in vicinity. 
At Coos Bay there is a privately owned dock with a 
frontage of 1,345 feet, open to the public on equal terms; 
several small landings for fishing and harbor craft; and 
three lumber docks with 1,300, 576, and 500-foot frontages, 
respectively. 
At Eastside, on Isthmus Slough, there is a 200-foot 
dock. 
At Empire there is a privately owned lumber dock with 
frontage of 510 feet, and an oil terminal, also privately 
owned, for receipt of petroleum products by barge. 
At Charleston there are four wharves, one public and 
three private, with usable areas of 1,200, 750, 7,000, and 
12,000 square feet, respectively, for receipt of fresh fish 
and shellfish and a large seafood receiving and processing 
plant. There is also a municipally owned small-boat 
basin, open to all on equal terms, capable of mooring 250 
fishing and recreation craft. Servicing facilities for small 
craft are available at all facilities, and public launching 
ramps have been constructed in Charleston area by private 
interests. A privately owned floating moorage on 
Joe Ney Slough has facilities for mooring about 50 fishing 
vessels. 
At Jordan Cove area there is a dock, 248 feet long, for 
wood chip ships. 
These facilities are considered adequate for existing 
commerce. (For details see Port Series No. 33, Corps of 
Engineers, published in 1975.) 
Operations during fiscal year. Maintenance: U.S. 
hopper dredge Yaquina removed 299,253 cubic yards; 
contract hopper dredge Manhattan Island removed 
440,817 cubic yards; and the contract hopper dredge 
Westport, removed 960,744 cubic yards of material. 
10. COOS AND MILLICOMA RIVERS, OR 
Location. South Fork and Millicoma Rivers rise in 
Coast Range in southern Oregon, flow generally westerly 
and join to make Coos River, 5.3 miles above mouth 
of Coos River in Coos Bay. (See NOAA Chart 18587, 
Allegany and Daniels Creek Quadrangle.) 
Existing project. Originally authorized project: a 
channel depth of 3 feet, generally, from mouth of Coos 
River and 1 foot near head of navigation. Project as 
modified: two channels 5 feet deep and 50 feet wide from 
mouth of Coos River to Allegany on Millicoma River, 
river mile 13.8 and to Delwood on South Fork, river mile 
14, and thence a channel 3 feet deep and 50 feet wide to 
river mile 14.7 on South Fork, including stabilization 
works on Coos River. Mean lower low water is plane of 
reference. Tidal range between mean lower low water 
and mean higher high water at the mouth of Coos River 
is 7 feet and extreme about 11 feet. Tidal range at head of 
navigation in both forks is about 1 foot. Freshet stages 
usually reach a height of from 10 to 15 feet at Allegany, 
head of navigation on Millicoma River. 
Originally authorized project providing for a channel 
from mouth of Coos River to head of navigation in both 
forks, to provide a depth of 3 feet generally and 1 foot 
near head of navigation, was completed in 1899. In 
March 1966 construction of project as modified by 1948 
River and Harbor Act was completed. 
Local cooperation. Fully complied with. 
Terminal facilities. Several small privately owned 
docks and landing places on the river are used by towboats 
and pleasure craft. There are no publicly owned 
docks. Present facilities are considered adequate for 
existing commerce. 
Operations during fiscal year. Maintenance: Contract 
dredging removed 29,127 cubic yards of material. 
11. COQUILLE RIVER, OR 
Location. Rises in Coast Range, flows generally westerly 
for about 100 miles, and empties into Pacific Ocean 
at Bandon, OR, 225 miles south of mouth of Columbia 
River and 420 miles north of San Francisco Bay. (See 
NOAA Charts 18580 and 18186.) 
Existing project. Two rubblemound high-tide jetties 
at river mouth, south jetty 2,700 feet long and the north, 
3,450 feet long; and a channel 13 feet deep at mean lower 
low water and of suitable width from the sea to a point 1 
mile above old Coquille River Lighthouse, and snagging 
to State highway bridge at city of Coquille. Mean lower 
low water is plane of reference. Tidal range between 
mean lower low water and mean higher high water at 
mouth is 7 feet and extreme about 10 feet. 
Jetties were completed in 1908 and entrance channel 
in 1933. North jetty was reconstructed in 1942 and a 
750-foot extension to easterly end was constructed in 
1951. South jetty was repaired in 1954 and north jetty in 
1956. Coquille Lighthouse rehabilitation was completed 
37-6

PORTLAND, OREGON DISTRICT 
June 21, 1976. (For details relating to previous projects, 
see page 1986 of Annual Report for 1915 and page 1727 of 
Annual Report for 1938.) 
Local cooperation. None required. However, restoration 
of lighthouse using Code 710, Recreation Facilities 
at Completed Projects, funding required 50 percent cost 
sharing with non-Federal sponsor (Oregon State Parks). 
Terminal facilities. At Bandon: A privately owned 
mill dock used exclusively for shipping lumber on coastwise 
vessels, a publicly owned wharf, and a small-boat 
basin open to all on equal terms. 
Operations during fiscal year. Maintenance: U.S. 
hopper dredge Yaquina removed 30,025 cubic yards of 
material from entrance channel. 
12. DEPOE BAY, OR 
Location. Harbor on Oregon coast 100 miles south of 
mouth of Columbia River. (See Coast and Geodetic Survey 
Chart 5902.) 
Existing project. Two breakwaters north of entrance; 
an entrance channel 8 feet deep and 50 feet wide; and 
inner basin 750 feet long, 390 feet wide and 8 feet deep 
with retaining wall along easterly side; and a stone 
spending beach. Mean lower low water is plane of reference. 
Tidal range between lower low water and higher 
high water is 8 feet and extreme is about 12 feet. Project 
as originally authorized was completed in 1939 and project 
modification, enlarging the basin and deepening to 8 
feet, was accomplished in June 1952 and August 1966. 
Local cooperation. Fully complied with. 
Terminal facilities. Facilities, in inner basin, consist 
of landings and floats to accommodate operators of 
excursion and commercial fishing boats. Facilities considered 
adequate for existing commerce. 
Operations during fiscal year. Maintenance: Condition 
surveys, miscellaneous inspections and reports 
were performed. 
13. LAKE RIVER, WA 
Location. Is outlet of Vancouver Lake in Washington, 
flows northerly 11 miles and empties into Columbia 
River about 88 miles above mouth. (See Coast and Geodetic 
Survey Chart 6154.) 
Existing project. A channel 6 feet deep and 100 feet 
wide to Ridgefield (3 miles). 
Local cooperation. None required. 
Terminal facilities. A public marina at Ridgefield 
2.5 miles above river mouth with facilities for moorage of 
200 fishing and recreation craft. Also plywood plant 
which has facilities for receipt of logs by water. From 
Ridgefield to river mouth are several booms for storage of 
logs. Facilities are considered adequate for existing 
commerce. 
Operations during fiscal year. Maintenance: Periodic 
hydrosurveys were conducted. 
14. NAVIGATION WORK UNDER SPECIAL 
AUTHORIZATION 
Navigation activities pursuant to Section 107, 
Public Law 86-645 (preauthorization). 
See Table 37-I. 
Aquatic plant control (Section 302, Public Law 
89-298): Total costs for fiscal year were $10,436. 
Streambank erosion control evaluation and demonstration 
(Section 32, Public Law 93-251): Total 
costs for fiscal year were $1,803. 
15. NEHALEM BAY, OR 
Location. On Oregon coast, 40 miles from Columbia 
River mouth and 10 miles north of the entrance to Tillamook 
Bay. 
Existing project. Provides for a jetty about 3,850 feet 
long on the north side of entrance and a jetty 4,950 feet 
long on the south side. Mean lower low water is plane of 
reference. Tidal range between mean lower low water 
and mean higher high water is 8 feet, extreme is about 15 
feet. Project as originally authorized was completed in 
1918. 
Local cooperation. Fully complied with for existing 
project. Local cooperation has been acquired for the 
major rehabilitation. 
Terminal facilities. Facilities for pleasure craft only: 
I)art's Marina, Brighton Moorage, Jetty Fishery, Port of 
Nehalem and city of Nehalem DI)ock. All areas have 
approximately 50-60 slips. However, due to shoaling, all 
are semi-usable. 
Operations during fiscal year. Major rehabilitation 
of both north and south jetties continued and is 
essentially complete. 
16. PORT ORFORD, OR 
Location. On Oregon coast 250 miles south of Columbia 
River entrance and 390 miles north of San Francisco 
Bay. (NOAA Chart 18203 and Geological Survey Quadrangle, 
Port Orford, OR.) 
Existing project. Improvement of harbor by 550-foot 
extension of existing locally constructed breakwater and 
dredging of a turning basin, 340 feet long, 100 feet wide 
and 16 feet deep. Breakwater was completed October 
1968. Turning basin was completed September 1971. 
Local cooperation. Fully complied with. 
Terminal facilities. A dock which is a timber piling 
structure about 210 by 70 feet, equipped with hydraulic 
crane for lifting boats from the water to dock for repairs 
and/or storage and removing fish catches from boats. 
About 500 fishing and private boats use this dock each 
year. 
Operations during fiscal year. Maintenance: The 
sand-bypasser Sandwick displaced shoal areas to provide 
longer periods of channel depths for navigation 
traffic within the authorized project. 
17. PROJECT CONDITION SURVEYS 
Surveys were conducted during FY 1983 at Depoe Bay, 
OR, Nehalem Bay, OR, and at Youngs Bay, OR at cost of 
$16,058. The cumulative cost through FY 1983 is 
$404,736. 
37-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
18. ROGUE RIVER HARBOR AT GOLD BEACH, 
OR 
Location. Rises in Cascade Range in southwestern 
Oregon, flows westerly through Coast Range, and empties 
into Pacific Ocean 264 miles south of mouth of 
Columbia River and 381 miles north of San Francisco 
Bay. (See NOAA Chart 18202.) 
Existing project. Two jetties at entrance, and a 
channel 13 feet deep and 300 feet wide from ocean to a 
point immediately below State highway bridge, about 1 
mile, including widening channel at a point about 0.25 
mile below bridge to form a turning basin 13 feet deep, 
500 feet wide, and 650 feet long. At request of local interests, 
turning basin was located in south portion of estuary 
downstream from a point 0.25 mile below bridge. 
This change was effected to permit adequate terminal 
facilities to be constructed adjacent to turning basin. 
Mean lower low water is plane of reference. Range of tide 
between mean lower low water and mean higher high 
water is 7 feet, and extreme about 14 feet. 
Project as authorized has been completed. Construction 
of two jetties at entrance was completed September 
1960. Dredging river channel by contract and entrance 
bar by government plant was completed October 1961. 
North jetty rehabilitation along channel side was completed 
October 1966. Breakwater construction and dredging, 
under contract awarded in September 1964, was 17 
percent accomplished when flood of December 1964 destroyed 
all completed works. Contract was terminated as 
further construction at that location was considered 
unfeasible. Bank protection work at Wedderburn location 
was completed in October 1972. A breakwater, constructed 
by Port of Gold Beach, was completed during 
1973. 
Local cooperation. Fully complied with. 
Terminal facilities. There are various landings for 
fishing and recreational craft. At Wedderburn, across 
river from Gold Beach, is a facility to accommodate 
excursion passengers and small freight items destined 
for various private landings between Wedderburn and 
Agness, OR. Facilities considered adequate for existing 
commerce. 
Operations during fiscal year. Maintenance: The 
sand-bypasser Sandwick displaced shoal areas to provide 
longer periods of channel depths for navigation 
traffic within the authorized project. The U.S. hopper 
dredge Yaquina removed 142,260 cubic yards of material. 
Contract dredging was accomplished to clear the boat 
basin entrance channel. A total of 10,000 cubic yards of 
material was removed by three contract pipeline dredges. 
19. SIUSLAW RIVER, OR 
Location. Rises in coast range, flows about 110 miles 
westerly and empties into Pacific Ocean about 160 miles 
south of entrance of Columbia River and 485 miles north 
of San Francisco Bay, CA. (See NOAA Charts 18583 and 
18580.) 
Existing project. Provides for 2 high-tide, rubblemound 
jetties 750 feet apart at the outer end, the north 
jetty 8,390 feet long (600 feet unconstructed) and the 
south jetty 4,200 feet long; an entrance channel 18 feet 
deep and 300 feet wide from deep water in ocean to a 
point 1,500 feet inside the outer end of existing north 
jetty; thence a channel 16 feet deep, 200 feet wide with 
additional widening at bends, and about 5 miles long, to 
a turning basin, 16 feet deep, 400 feet wide, and 600 feet 
long, opposite Suislaw dock at Florence; a channel 12 feet 
deep, 150 feet wide from Florence to River mile 16.5; and 
at River Mile 15.5, a turning basin 12 feet deep, 300 feet 
wide and 500 feet long. Mean lower low water is plane of 
reference. Tidal range between mean lower low water 
and mean higher high water at mouth of river is 7 feet 
and extreme about 11 feet. During low stages of river, 
tidal effect extends to Mapleton, 20.5 miles above mouth. 
(For details relating to previous project see page 1988 of 
Annual Report for 1915.) 
A modification to the existing project was authorized 
by Public Law 96-367, October 1, 1980 and is currently 
under construction. Plan of improvement provides for 
extending the north and south jetties by 1,900 and 2,300 
feet respectively. The jetty extensions will terminate at 
approximately the minus 25-foot contour. Spur jetties are 
being constructed on each jetty extension to prevent 
longshore currents from transporting material around 
the heads of the jetties. Each spur jetty will be about 400 
feet long and originate approximately 900 feet shoreward 
of the jetty head. The north jetty spur should be 
oriented 45 degrees to the north of the existing jetty 
alignment and the south jetty spur 5 degrees to the south 
of the jetty alignment. Estimated cost of new work is 
$30,620,000; $30,400,000 Corps of Engineers, $182,000 
non-Federal, and $38,000 U.S. Coast Guard. 
Local cooperation. Fully complied with. 
Terminal facilities. The principal terminal facility 
on the river is at DI)avidson Lumber Dock at Mapleton 
which accommodates ocean-going barges with packaged 
lumber. 
Port dock at Florence, 150 feet wide and 350 feet long, is 
about 5.3 miles above river entrance and accommodates 
a fish-receiving station at east end of wharf which maintains 
a 2-ton capacity winch and supplies gasoline, oil 
and ice to fishermen. Other facilities at Florence consist 
of various floatways which provide docking facilities for 
fishing vessels and other small craft and a floating dock 
with accommodations for 75 commercial fishing vessels. 
The Port has recently acquired a marine travel lift to 
accommodate vessels 70 feet in length or 60 tons in 
weight. Adjacent to commercial basin is mooring basin 
with accommodations for 200 sport boats of all sizes. 
Across the river and below highway bridge at Glaneda 
are floatways used by small craft. A modern dock for 
loading ocean-going barges with packaged lumber is 
maintained at Mapleton by U.S. Plywood Champion 
Lumber Company. 
There are also a number of private landings and log 
booms between Cushman and Mapleton to accommodate 
river traffic. These facilities are considered adequate 
for existing traffic. 
Operations during fiscal year. New work: Contract 
for the modification, the extension of the north and south 
jetties, was awarded in July 1983. 
37-8

PORTLAND, OREGON DISTRICT 
Maintenance: U.S. hopper dredge Yaquina removed 
213,325 cubic yards of material. 
20. SKAMOKAWA CREEK, WA 
Location. Rises in Wahkiakum County, in southwestern 
part of the State of Washington, flows southwesterly 
and southerly about 10 miles, and empties into 
Columbia River about 34 miles above mouth. (See NOAA 
Chart 18523.) 
Existing project. Provides for a channel 6.5 feet deep 
at low water and 75 feet wide, between Steamboat and 
Brooks Sloughs, about 1,600 feet long. Tidal range 
between mean lower low water and mean higher high 
water is about 7 feet and maximum variation of water 
level due to tides or freshets is about 12 feet. DI)uring 
ordinary freshets a stage of 12 feet is reached in creek at 
Skamokawa, WA. Project as authorized was completed 
in 1920. 
Local cooperation. None required. 
Terminal facilities. There are several privately owned 
docks on Skamokawa Creek, Steamboat Slough, and 
Brooks Slough for use of towboats and pleasure craft. 
Operations during fiscal year. Maintenance: Condition 
surveys, miscellaneous inspections and reports. 
21. SKIPANON CHANNEL, OR 
Location. In tidal waterway extending south 2.7 
miles from deep water in Columbia River. Channel 
enters Columbia about 10 miles above mouth and 4 miles 
below Astoria, OR. (See NOAA Chart 18523.) 
Existing project. Channel 30 feet deep and generally 
200 feet wide extending from deep water in Columbia 
River to railroad bridge at Warrenton, OR, distance of 1.8 
miles, turning basin of same depth, mooring basin 12 feet 
deep at mean lower low water at Warrenton, OR, and 
channel 6 feet deep, generally 40 feet wide, with increased 
widths at log dumps and terminals, for 4,500 feet via 
cutoff channel above railroad bridge. Mean lower low 
water is plane of reference. Tidal range between mean 
lower low water and mean higher high water is about 8 
feet, extreme is about 13 feet. 
Project as authorized is complete. Dredging river 
channel and turning basin was completed in 1939. Construction 
of small-boat mooring basin at Warrenton, OR, 
was completed October 1957, and fill stabilization work 
was accomplished in August 1958. 
Local cooperation. Fully complied with. 
Terminal facilities. City of Warrenton owns wharf 
with a 300-foot frontage open to public on equal terms. 
One privately owned cannery wharf with a 300-foot frontage 
is used for unloading fish and handling fish nets. 
One privately owned boatyard has floats and moorage 
facilities for use of a maximum of 80 small boats. In 
channel above railroad bridge, facilities consist of log 
rollways used for sorting logs which are no longer operated. 
Small-boat basin has facilities for numerous fishing 
and recreation craft. These facilities, except during 
the fishing season, are considered adequate for existing 
commerce. 
Operations during fiscal year. Maintenance: Contract 
dredge removed 62,500 cubic yards of material. 
22. SOUTH CHANNEL, GOVERNMENT 
ISLAND, OR 
Location. South Channel is a side channel of the 
Columbia River about 7 miles long. It connects the main 
shipping channel of the Columbia River just downstream 
of Lemon Island with the main shipping channel 
just upstream of Maguire Island. The downstream end of 
the channel is just north of the Portland International 
Airport. 
Existing project. Provides for a small boat recreational 
channel 100' wide to a depth of 6' (Columbia River 
datum) between river mile 111.8 and 118.4. 
Local cooperation. Port of Portland, project sponsor. 
Operations during fiscal year. New work: Contract 
was awarded in September 1983 with work scheduled to 
be completed in early FY 1984. 
23. TILLAMOOK BAY AND BAR, OR 
Location. Bay is on Oregon coast about 50 miles 
south of mouth of Columbia River. (See NOAA Charts 
18520 and 18558.) 
Existing project. Provides for a jetty about 5,700 feet 
long on north side of entrance and a jetty 8,000 feet long 
on south side; a channel through bar 18 feet deep and of 
such width as can be practically and economically 
obtained; for a channel 200 feet wide and 18 feet deep 
from deep water in bay to Miami Cove; and for initial 
dredging to 12 feet deep of a small-boat basin and 
approach thereto at Garibaldi, OR. Project also provides 
for improvement of Bayocean Peninsula, OR, by construction 
of sand and rockfill dike 1.4 miles long, on 
alinement extending between Pitcher Point and town of 
Bayocean. Mean lower low water is plane of reference. 
Tidal range between mean lower low water and mean 
higher high water is 8 feet, extreme is about 14 feet. 
Hobsonville Channel portion of project is inactive. 
Except for construction of Hobsonville Channel portion, 
classified inactive, channels were completed in 
1927, north jetty in 1933, improvement of Bayocean 
Peninsula in 1956, and small-boat basin in 1958. Rehabilitation 
of north jetty was accomplished September 
1965. Construction of south jetty was initiated April 1969 
and was completed in September 1979. (For details relating 
to previous projects, see page 1989 of Annual Report 
for 1915 and page 1474 of Annual Report for 1936.) 
Local cooperation. Fully complied with. Requirements 
are described in full on page 37-9 of FY 1981 
Annual Report. 
Terminal facilities. At Garibaldi: A facility owned 
by the Port of Bay City, for shipping lumber and receiving 
logs, a public landing suitable for mooring fishing 
vessels, towboats, and other craft. Small-boat basin has 
adequate facilities for mooring fishing and recreational 
craft. A privately owned boat ramp and moorage is 
available for recreational craft. 
37-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
At Bay City: A privately owned wharf used exclusively 
for receipt of fresh fish and shellfish. Facilities considered 
adequate for existing commerce. 
Operations during fiscal year. Maintenance: Contract 
pipeline dredge removed 8,255 cubic yards of material 
to clear a 1,000-foot channel at Old Mill Marina. 
24. UMPQUA RIVER, OR 
Location. Rises in Cascade Range, flows westerly 
about 120 miles, and empties into Pacific Ocean 180 
miles south of Columbia River and 465 miles north of 
San Francisco Bay. (See NOAA Charts 18580 and 18584.) 
Existing project. A jetty on north side of entrance 
about 8,000 feet long, a south jetty 4,200 feet long extending 
to a point 1,800 feet south of outer end of north jetty; 
dredging to provide a usable entrance channel 26 feet 
deep, and a river channel 22 feet deep and 200 feet wide, 
from mouth to Reedsport, a distance of about 12 miles 
with a turning basin at Reedsport 1,000 feet long, 600 feet 
wide, and 22 feet deep; a channel 12 feet deep and 100 feet 
wide from deep water in the river to vicinity of docks in 
Winchester Bay with a mooring and turning basin 12 
feet deep, 175 feet wide, and 300 feet long at inner end; 
and a channel 22 feet deep and 200 feet wide from main 
river channel near River Mile 8 to Gardiner, OR, and a 
turning basin of same depth, 500 feet wide, and 800 feet 
long, opposite Gardiner. Project was modified in 1954 to 
provide a channel in Scholfield River, but this portion of 
the project is currently inactive. Mean lower low water is 
plane of reference. Tidal range between mean lower low 
water and mean higher high water at river mouth is 7 
feet, and extreme range is about 11 feet. 
Project is complete. North jetty was completed in 1940. 
Extension to original south jetty was completed in 1938. 
Dredging a 22-foot channel from mouth of river to 
Reedsport was completed in 1941. Gardiner Channel and 
turning basin was completed in 1949 and Winchester 
Bay Channel and mooring basin in 1956. The 12-foot 
channel in Scholfield River is currently classified inactive. 
Rehabilitation of south jetty was completed August 
1963. Extension of training jetty was completed October 
9,1980. (For details relating to previous projects see page 
2967 of Annual Report for 1898 and page 1732 of Annual 
Report for 1938.) 
Local cooperation. Complied with for all work except 
Scholfield River channel modification. 
Terminal facilities. At Gardiner there is about 650 
feet of wharf frontage. Also, there is an oil unloading 
facility owned by International Paper Co. for exclusive 
use of tanker barges. Port of Umpqua owns one wharf 
with 456 feet of water frontage, of which 228 feet is usable 
for vessels and another with about 75 feet of water frontage 
which has not been used generally for commercial 
shipping. 
On Bolon Island across the river from Reedsport a 
wharf was constructed which has about 5 acres of open 
storage for lumber and available to all on equal terms. 
At Winchester Bay, 2 miles from river entrance there is 
a major sports and commercial fishing harbor. Facilities 
are considered adequate for existing commerce. 
Operations during fiscal year. Maintenance: U.S. 
hopper dredge Yaquina removed 216,705 cubic yards of 
material. 
25. WILLAMETE RIVER ABOVE PORTLAND 
AND YAMHILL RIVER, OR 
Location. Yamhill River rises in Coast Range, flows 
easterly, and empties into Willamette River about 42 
miles above Portland. Its length from source of South 
Fork is about 52 miles. (See NOAA Chart 18526 and 
Geological Survey map, State of Oregon.) For description 
of Willamette River see Improvement No. 3 
Existing project. Provides for improvement of Willamette 
River between Portland (River Mile 14) and 
Oregon City (River Mile 26) by a channel 8 feet deep at 
low water, 200 feet wide below Cedar Island and 150 feet 
wide thence to Oregon City; such channel improvement 
and contraction works as may be necessary to secure 
with streamflow regulation, controlling depths of 6 feet at 
low water and of no prescribed width, from Oregon City 
to mouth of Santiam River (River Mile 108.5), 5 feet from 
that point to Albany (River Mile 120) 2.5 to 3.5 feet deep 
from Albany to Corvallis (River Mile 132), and for necessary 
snagging between Corvallis and Eugene (River Mile 
185). Local interests dredge and maintain a 20-foot channel 
to the dock at Lake Oswego for receipt of limerock. 
Project also provides for a channel in Yamhill River 4 
feet deep at low water and 60 feet wide from its mouth to 
McMinnville (18 miles) secured by means of a lock and 
dam near Lafayette and by removal of obstructions. Section 
of Willamette River in vicinity of Willamette Falls at 
Oregon City is covered by Improvement No. 26. For Willamette 
River below falls at Oregon City ordinary fluctuation 
of stage of water is 15 feet and extreme fluctuation 
due to flood conditions 35 to 50 feet. Above Oregon City 
ordinary fluctuation is 12 to 20 feet and extreme is 20 to 27 
feet. For Yamhill River ordinary fluctuation is 35 feet and 
extreme 48 feet. Tidal changes vary from about 2.5 feet at 
mouth of Willamette to zero, 26 miles above mouth. 
Project is about 18 percent complete. The 8-foot channel 
between Portland and Oregon City and 2.5- to 3.5-foot 
channel between Oregon City and Albany were completed 
in 1939. The 2.5- to 3.5-foot channel between 
Albany and Corvallis was completed in 1945. Remaining 
work required to complete project consists of construction 
of such contraction works and channel improvements as 
may be necessary, with streamflow regulation, to secure 
controlling depths of 6 feet at low water from Oregon City 
to mouth of Santiam River, and 5 feet from that point to 
Albany. This remaining portion has been placed in the 
deferred category. Due to lack of use by commercial traffic 
for which facilities were provided, operation of Yamhill 
lock was discontinued February 7,1954, and the lock 
and adjacent property reported surplus and turned over 
to Yamhill County January 16,1959. There is no maintenance 
of the channel above Newberg, so it is only usable 
during higher river stages. (For details relating to previous 
projects see page 1997 of Annual Report for 1915 
and page 1754 of Annual Report for 1938.) 
Local cooperation. None required. 
37-10

PORTLAND, OREGON DISTRICT 
Terminal facilities. Between Ross Island Bridge 
at Portland and Willamette Falls at Oregon City: Privately 
owned mill docks, sand and gravel wharves, a 
cement loading facility, a small shipyard, and oilreceiving 
stations. Above the falls there are privately 
owned landings including a facility at Pulp Siding (3 
miles above the falls) with rail and water connections 
for shipment of clay and receipt of papermill products 
by barge. 
At Wilsonville and Newberg there are sand and 
gravel facilities. 
At numerous locations as far as Corvallis (River 
Mile 132) there are log rollways which are currently 
inactive. 
At Lake Oswego there is a dock for the receipt of 
limerock used in the manufacture of cement. Facilities 
considered adequate for existing commerce. 
Operations during fiscal year. Maintenance: 
Condition surveys, coordination with Port authorities 
and resource monitoring continued. 
26. WILLAMETTE RIVER AT WILLAMETTE 
FALLS, OR 
Location. Locks and dam covered by this project 
are at Willamette Falls, a rocky reef in Willamette 
River at Oregon City, OR, about 26 miles above mouth 
of river. 
Existing project. Provides for construction of a 
new single-lift main lock and a guard lock each with 
clear dimensions of 56 by 400 feet and a minimum 
depth over sills of 9.5 feet, to replace existing facilities 
which were provided for by purchase, rehabilitation, 
and deepening to 6 feet at low water of existing canal 
and locks and separation of canal from waterpower 
intake by construction of a concrete division wall. 
Construction of a new lock is currently an inactive 
project. The existing locks are on the National Register 
for historic sites, making their replacement unlikely. 
Total length of existing canals and locks is 
about 3,500 feet. Principal features of existing canal 
and locks at Willamette Falls are set forth in Table 
37-J. Ordinary fluctuation of stage of water above 
locks is 12 feet and extreme, due to flood conditions, 20 
feet. Below locks, ordinary fluctuation is 15 feet and 
extreme 50 feet. 
Canal and locks originally constructed by private 
interests in 1873 were purchased by the United States 
in April 1915 for $375,000. Final report on purchase 
and rehabilitation of canal and locks is in Annual 
Report for 1923, when project was reported 98 percent 
complete. Replacement of gates Nos. 6 and 7 was completed 
August 1967 under minor rehabilitation funds. 
Existing locks and grounds are in fair condition and 
in continuous operation except when flooded out by 
high water or undergoing repair. Facilities are obsolete 
and inadequate for existing traffic. No construction 
work has been done on lock and guard lock, which 
was authorized to replace existing facilities by Flood 
Control Act of 1939, and River and Harbor Act of 1945. 
This portion of the project has been reclassified 
"deferred." 
Local cooperation. Fully complied with. 
Terminal facilities. Crown Zellerbach Corp. has a 
timber wharf about 850 feet long, extending to and 
supported by concrete division wall built in lock canal 
by United States. This wharf is used for receiving mill 
supplies and shipping paper and paper products. 
Operations during fiscal year. Maintenance: Replacement 
of guide booms throughout the locks. 
27. WINCHESTER BAY, UMPQUA RIVER, OR 
Location. Bay is on the Oregon coast about 180 
miles south of the Columbia River, 465 miles north of 
San Francisco Bay (See NOAA charts, 18580 and 
18584). 
Existing Project. A channel 16 feet and 100 feet 
wide from deep water in the river to vicinity of docks in 
Winchester Bay with a turning basin 16 feet deep, 175 
feet wide and 300 feet long; thence a channel 100 feet 
wide and 16 feet deep for approximately 500 feet, 
thence 75 feet wide and 12 feet deep for approximately 
950 feet; a channel 100 feet wide and 16 feet deep 
extending from deep water in the river approximately 
4,100 feet in length to a turning basin 160 feet wide, 16 
feet deep and 200 feet long at the southerly end of the 
west basin. 
Local cooperation. Fully complied with. 
Operations during fiscal year. New work: Initial 
construction contract awarded September 1982 and 
was completed. Contract for rock removal was awarded 
in late FY 1983 and is currently underway. The contractor 
removed 202,367 cubic yards of material and 
1,044 cubic yards of rock during FY 1983. 
28. YAQUINA BAY AND HARBOR, OR 
Location. Bay is on Oregon coast, 113 miles south 
of mouth of Columbia River. (See NOAA Charts 18580 
and 18581.) 
Existing project. Two high tide rubblemound jetties 
at entrance, north jetty 7,000 feet, and south jetty 
8,600 feet long; a spur jetty on channel side of south 
jetty 4,700 feet from its sea end, 800 feet long; five 
groins channelward from south jetty; channel 40 feet 
deep for a general width of 400 feet across bar and at 
outer end of entrance channel; a channel 30 feet deep 
and 300 feet wide to a turning basin of same depth, 900 
to 1,200 feet wide and 1,400 feet long, and a channel 18 
feet deep and 200 feet wide from 30-foot channel at 
about mile 2.4, thence upstream to abandoned railroad 
terminus at Yaquina, a distance of about 4.5 
miles. Project also provides for two small boat mooring 
basins at Newport, OR. Mean lower low water is 
plane of reference. Tidal range between mean lower 
low water and mean higher high water is 8 feet and 
extreme is about 12 feet. 
Project as originally authorized was completed in 
May 1952. Restoration ofjetties was completed in 1934 
37-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
and extension of north jetty 1,000 feet seaward was 
completed in 1940. Construction of mooring basin at 
Newport and dredging of channel and turning basin 
to project dimensions were completed during fiscal 
year 1949. Restoration of north jetty was again accomplished 
in 1956. Under modification of July 3, 1958, 
extension of north jetty was completed in September 
1966, dredging of 40-foot bar channel and 30-foot river 
channel was completed in October 1968, and extension 
of south jetty was completed in June 1972. (For 
details relating to previous projects see Annual Report 
for 1893, part 4, page 3314, and Annual Report for 
1938, page 1736.) 
Local cooperation. Fully complied with. 
Terminal facilities. At McLean Point, on north 
side of bay, about 2 miles from entrance, Yaquina 
Terminals has two berths capable of serving oceangoing 
vessels, one 435 feet long, the second 520 feet 
long. At the time the second berth was dredged, a 
retaining wall and fill of 6 acres were constructed 
adjacent to deep water. The company now has 40 acres 
of filled land adjacent to deep water, and of this total, 7 
acres were constructed in 1956-57. This facility has 
necessary carriers and lift trucks for handling lumber 
cargoes, warehouse for covered cargo storage, and is 
open to all on equal terms. No deep draft commerce 
presently use these facilities. 
Port of Newport has a public wharf within 300 feet 
of frontage for servicing fishing boats. In addition, 
Port of Newport maintains 510 berths for mooring 
commercial and sport fishing vessels. There are several 
seafood companies on the bay which have their 
own facilities for handling fresh fish and crab. Supplies 
and petroleum products are readily available for 
small vessels. On south side of bay about 1.2 miles 
above entrance, Port of Newport has constructed 
South Beach Marina which can handle approximately 
600 small pleasure craft and shallow draft 
fishing boats. Public facilities include public automobile 
and boat trailer parking, boat launching ramp, 
fuel dock, fishing pier, and picnic area. A dry boat 
moorage for 120 boats, is nearing completion. A swing 
hoist with 3-ton capacity is currently available and 
one with 60-ton capacity is planned. 
About 1.5 miles above entrance, Oregon Aqua Foods, 
subsidiary of Weyerhaeuser Company, maintains a 
commercial fish farm facility. 
About 2.0 miles above entrance, Oregon State University, 
in conjunction with the Marine Science Center on 
52 acres, maintains a 220-foot pier for docking large 
and small research vessels and a 100-foot float for 
docking small boats. Docking facilities are restricted 
to research vessels and State of Oregon small boats. 
Operations during fiscal year. Maintenance: 
U.S. hopper dredge Yaquina removed 103,325 cubic 
yards of material, and contract hopper dredge Westport 
removed 349,994 cubic yards. 
29. YAQUINA RIVER, OR 
Location. Rises in Coast Range, flows about 50 
miles in a westerly direction, and empties into 
Yaquina Bay, on Oregon Coast. (See U.S. Coast and 
Geodetic Survey Charts Nos. 5802 and 6058.) 
Existing project. Provides for two controlling 
half-tide dikes of piling, brush, and stone, each about 
1,100 feet long (constructed by local interests), and for 
a channel 10 feet deep and generally 150 feet wide on 
Yaquina River and 200 feet wide in Depoe Creek, 
extending from town of Yaquina to Toledo, about 9 
miles. 
Mean lower low water is plane of reference. Tidal 
range between lower low water and mean higher high 
water is 8 feet and extreme about 12 feet. Freshet 
heights are about 12 feet at mouth of Depoe Creek. 
Channel work authorized March 1913 was completed 
in 1914. 
Local cooperation. Fully complied with. 
Terminal facilities. Near town of Yaquina at river 
mouth, which is also head of Yaquina Bay, there is a 
moorage for small vessels and a small-craft shipyard. 
Both port and city of Toledo have public-terminal 
facilities for accommodation of local craft. There are 
also privately owned facilities for loading lumber 
barges, receipt of bunker fuel oil, and log rollways for 
receipt of logs. These facilities are considered adequate 
for existing commerce. 
Operations during fiscal year. Maintenance: 
Yaquina River at Depoe Slough was dredged by a 
contract dredge and 45,521 cubic yards of material 
removed. 
Flood Control 
30. APPLEGATE LAKE, ROGUE RIVER 
BASIN, OR 
Location. In Jackson County, OR, on Upper Applegate 
River, a tributary of Rogue River, at River Mile 
46, about 23 airline miles southwest of Medford, OR. 
Existing project. A gravel-fill embankment dam, 
242 feet high from streambed to crest with an overall 
length of 1,300 feet. A gate-controlled concrete chutetype 
spillway on the left abutment, and a regulating 
outlet conduit, and intake tower with multilevel intakes 
on the left side of valley floor. Lake, 5 miles long, 
provides 75,000 acre-feet of usable storage for flood 
control and water conservation utilization. Project 
controls runoff from a drainage area of 223 square 
miles. In addition to flood control, reservoir is operated 
to provide irrigation, fish and wildlife enhancement, 
water quality control, and recreation benefits. 
Project is complete and operating. 
Local cooperation. Authorizing act requires that 
State of Oregon insure maintenance of stream flow 
released for fishery. In addition, costs allocated to 
irrigation would have to be repaid in a manner and to 
an extent consistent with reclamation laws and policies. 
Oregon Department of Fish and Wildlife made 
filing May 31, 1962 with State Engineer for water 
rights for use of stored water and natural flows for fish 
habitat improvement in amounts and at times specified 
in project authorization. The U.S. Bureau of Reclamation 
has made a feasibility study of Applegate 
37-12

PORTLAND, OREGON DISTRICT 
Irrigation Division. The results of the study indicate 
that at present there does not appear to be a feasible 
Federal irrigation project for the Applegate River valley. 
Local interests have furnished all local cooperation 
specified by the 1970 Flood Control Act. The assurances 
were approved by the Secretary of the Army on 
May 8, 1975. 
Operations during fiscal year. New work: 
Miscellaneous contracts for earth work completion 
and roadway repair were completed. A floating trash 
barrier was also finished. 
Maintenance: Normal operation and maintenance 
was performed. Freshets regulated by Applegate Lake 
on Applegate River and Rogue River are shown in 
Table 37-K. 
31. BEAVER DRAINAGE DISTRICT, 
COLUMBIA COUNTY, OR 
Location. In Columbia County, OR, north of town 
of Clatskanie and extends along Columbia River and 
Bradbury Slough between River Miles 49.7 and 55.4. 
Existing project. The project originally provides 
for construction of 10.4 miles of existing levee; construction 
of 0.9 mile of new levee; construction of 2.5 
miles stone revetment, one pumping plant and 1.1 
miles of diversion canal. The Flood Control Act of 
May 17, 1950 authorized additional improvements 
which included raising and strengthening the existing 
levee and installing toe drains where required; 
removing two antiquated pumping stations from the 
levee section; constructing a new pumping station 
with increased capacity; removing the existing Tank 
Creek tide box structure; and replacing the Tank 
Creek tide box with a fresh water intake. 
Local cooperation. Requirements are described in 
full on page 37-12 of FY 1981 Annual Report. 
Operations during fiscal year. New work: Operation 
and Maintenance manuals were prepared and 
essentially completed during the fiscal year. 
32. BLUE RIVER LAKE, OR 
Location. On Blue River, a major tributary of 
McKenzie River, 1.8 miles above confluence of the two 
streams at the confluence of Quartz Creek and Blue 
River and about 42 miles easterly of Eugene, OR. 
Existing project. A gravel-fill embankment dam 
1,329 feet long at crest including spillway and 319 feet 
above the lowest point of the general foundation. A 
concrete gravity chute-type spillway with two gates is 
located on left abutment. Outlet works are in left 
abutment. On left shore of reservoir an earth-andgravel 
fill embankment, about 1,535 feet long and 70 
feet high, closes a low saddle between Blue River and 
McKenzie River. Project controls runoff from drainage 
area of 88 square miles. Reservoir provides 85,000 
acre-feet of usable flood control storage and is operated 
as a unit of coordinated reservoir system to protect 
Willamette River Valley and increase low waterflows 
for navigation and other purposes. Recreation 
facilities are provided by the U.S. Forest Service under 
a Memorandum of Agreement. Project is complete. 
Construction of dam and appurtenant works was 
initiated in May 1963 and operation for flood control 
was effective in October 1968. Settlement of claims 
was completed in May 1974. Eugene Water and Electric 
Board made an application in April 1982 for permit 
to install two small hydropower units at Blue River 
Lake project. They also made an application in 1982 
for permit to build a dam with two hydropower units, 
called Sunnyside Dam, between Foster and Green 
Peter project. 
Local cooperation. None required. 
Operations during fiscal year. Maintenance: 
Normal operation and maintenance work performed. 
Freshets regulated by Blue River Lake project on Blue 
River, a major tributary of McKenzie River, are shown 
in Table 37-K. 
33. COTTAGE GROVE LAKE, OR 
Location. On Coast Fork of Willamette River, 29 
miles from mouth. Coast Fork rises in Douglas County, 
OR, on western slope of Cascade Range and northern 
slope of Calapooia Range, flows north for 49 miles, 
and unites with Middle Fork to form main Willamette 
River. 
Existing project. An earthfill dam, 1,750 feet long 
at crest, 114 feet high from lowest point of the general 
foundation, a concrete gravity free overflow spillway 
264 feet long near the right abutment, and a concrete 
gravity non-overflow section 96 feet long forming the 
right abutment. Total length of dam is 2,110 feet. 
Outlet works, consisting of three gate-controlled conduits, 
pass through spillway section. Reservoir provides 
30,060 acre-feet of usable flood control storage 
and controls runoff of drainage area of 104 square 
miles. Project is operated as a unit of coordinated 
reservoir system to protect Willamette River Valley 
and increase low waterflow for navigation and for 
other purposes. Recreational development consists of 
day use and overnight facilities at four sites operated 
by the Corps of Engineers. Construction of project 
initiated August 1940 was completed April 1952. Dam 
and reservoir have been in continuous operation since 
September 1942. 
Local cooperation. None required. No cost-sharing 
sponsor for recreation facilities has expressed an 
interest in this project. 
Operations during fiscal year. Maintenance: 
Normal operation and maintenance work performed. 
Freshets regulated by Cottage Grove Lake on Coast 
Fork Willamette River are shown in Table 37-K. 
34. DORENA LAKE, OR 
Location. On Row River, OR, 7 miles from mouth. 
Row River rises in Lane County on western slope of 
Cascade Range, flows northwest for 19 miles, and 
enters Coast Fork of Willamette River 19.5 miles 
above mouth. 
37-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Existing project. An earthfill embankment dam, 
3,352 feet long at crest and 145 feet high from lowest 
point of the general foundation. Concrete gravity freeoverflow 
spillway, 200 feet long, forms right abutment. 
Outlet works on five slide-gate-controlled conduits 
pass through spillway section. Reservoir provides 
70,500 acre-feet of usable flood control storage and 
controls runoff of 265 square miles, practically entire 
drainage area tributary to Row River. Project is operated 
as a unit of coordinated reservoir system to protect 
Willamette River Valley and increase low waterflows 
for navigation and other purposes. Construction of 
project initiated June 1941 was completed October 
1952 except for construction of additional recreation 
facilities to be funded from Recreation Facilities at 
Completed Projects. Recreation facilities construction 
will be accomplished in accordance with the costsharing 
contract with Lane County, OR. Dam and 
reservoir have been in continuous operation since 
November 1949. 
Local cooperation. Future recreational development 
is contingent upon a cost-sharing agreement 
with a non-Federal sponsor. Lane County Parks is 
participating in a multiple project cost-sharing (50 
percent) contract, for many of the existing parks at 
four projects, including Dorena Lake. 
Operations during fiscal year. New work, code 
710: Construction of restroom facilities have been 
completed at Schwarz Park. 
Maintenance: Normal operation and maintenance 
work performed. Freshets regulated by Dorena Lake 
project on Row and Coast Fork Willamette Rivers are 
shown in Table 37-K. 
35. ELK CREEK LAKE, ROGUE RIVER 
BASIN, OR 
Location. In Jackson County, OR at River Mile 1.7 
on Elk Creek, a tributary of Rogue River, about 26.5 
miles northerly from Medford, OR. 
Existing project. Design work continues to provide 
for a 249-foot high roller compacted concrete 
gravity dam, 2,600 feet long at the crest, with a gate 
controlled concrete chute spillway, regulating outlet 
conduits, power penstock and multiple use intake 
tower attached to the upstream face of the dam. 
Reservoir 6.2 miles long will provide 95,000 acre-feet of 
usable storage for flood control and water conservation 
utilization. Project will control runoff from a 
drainage area of 135 square miles. Reservoir will be 
operated to provide future municipal and industrial 
water supply, irrigation, fish and wildlife enhancement, 
water quality control, and recreation benefits. 
Construction of the project was initiated in February 
1971. Work completed to date includes construction 
of a bypass road to route traffic away from the 
damsite and stockpiling of gravels to be used in the 
main dam and relocated roads. All private lands for 
the project have been acquired. Final environmental 
statement was filed with Council of Environmental 
Quality June 15, 1972 and Supplement No. 1 
addressing water quality and social/demographic 
information was filed with EPA on December 24,1980. 
The Oregon Water Policy Review Board voted October 
3,1975 not to support the Elk Creek project. On April 4, 
1981 the Board reversed its previous position and 
voted to support Elk Creek project. Estimated Federal 
cost of project is $124,000,000 (1983). 
Local cooperation. Authorizing act requires that 
State of Oregon take action prior to construction to 
insure maintenance in stream of flow to be released for 
fishery. In addition, costs allocated to irrigation would 
have to be repaid in a manner and to an extent consistent 
with the U.S. Bureau of Reclamation laws and 
policies. On February 24, 1966 State of Oregon Water 
Resources Board filed for withdrawal rights of 25 cfs 
to maintain minimum flow for fish. 
Operations during fiscal year. New work: Administration 
of project land continued. 
36. FALL CREEK LAKE, OR 
Location. On Fall Creek, a tributary of Middle 
Fork Willamette River, about 7 miles above confluence 
of the streams and about 19 miles southeasterly of 
Eugene, OR. 
Existing project. An earth-and-gravel fill embankment 
about 5,100 feet long at crest and 193 feet high 
from lowest point of the general foundation. A gated 
concrete gravity spillway is in left abutment. Outlet is 
in right abutment. Reservoir provides 115,000 acrefeet 
of usable flood control storage and is operated as a 
unit of coordinated reservoir system to protect Willamette 
River Valley and increase low waterflows for 
navigation and other purposes. 
Construction of project began May 1962 and was 
essentially complete November 1965. Reservoir storage 
for flood control was effective October 1965. Sky 
Camp Lodge was completed October 1978. Future 
recreation facilities will be provided in accordance 
with the cost-sharing contracts with Lane County and 
Bethel School District, federally funded from Recreation 
Facilities at Completed Projects. 
Local cooperation. Additional recreational development 
is contingent upon a cost-sharing agreement 
with a non-Federal sponsor. Lane County Parks is 
participating in a multiple project cost-sharing (50 
percent) contract for many of the existing parks at 
four projects, including Fall Creek Lake. Also, Bethel 
School District is cost-sharing 50 percent for Sky 
Camp. 
Operations during fiscal year. Maintenance: 
Normal operation and maintenance work performed. 
Freshets regulated by Fall Creek Lake project on Fall 
Creek, a tributary of Middle Fork, Willamette River, 
are shown in Table 37-K. 
37. FERN RIDGE LAKE, OR 
Location. On Long Tom River, 23.6 miles from the 
mouth. Long Tom River rises in Lane County, OR, on 
eastern slope of Coast Range, flows north for 50 miles, 
and enters Willamette River 147 miles above its mouth. 
37-14

PORTLAND, OREGON, DISTRICT 
Existing project. A main dam, 6,624 feet long at 
crest and 49 feet high from lowest point of the general 
foundation and two auxiliary dikes, 915 and 3,929 feet 
long, along northeasterly boundary of lake. Main dam 
consists of an earthfill embankment dam 6,330 feet 
long, a concrete gravity spillway near left abutment 
with a non-overflow structure 46 feet long, containing 
outlet works, and an overflow structure, 248 feet long, 
controlled by six automatic gates. Project includes 
rectification of channel of Long Tom River downstream 
of dam. Reservoir provides 110,000 acre-feet of 
usable flood control storage and controls runoff of 
tributary drainage area of 275 square miles. Reservoir 
protects Long Tom River Valley and is operated as a 
unit of coordinated reservoir system to protect Willamette 
River Valley generally and to increase low 
water-flows for navigation and other purposes. Dam 
was originally constructed in 1941 to height of 47 feet. 
Provision of additional storage for flood control was 
obtained in 1965 by raising embankments 2 feet to 49 
feet above lowest point of the general foundation. 
Construction of project initiated April 1940 was 
completed August 1951, except for provision of additional 
storage for flood control authorized in 1962 and 
completed April 1965, and construction of additional 
recreation facilities to be funded from Recreation 
Facilities at Completed Projects. Dam and reservoir 
have been in continuous operation since December 
1941. Development of recreation facilities in accordance 
with the cost-sharing contract with Lane County 
continues. 
Local cooperation. Additional recreational development 
is contingent upon a cost-sharing agreement 
with a non-Federal sponsor. Lane County Parks is 
participating in a multiple project cost-sharing (50 
percent) contract for many of the existing parks at 
four projects, including Fern Ridge Lake. 
Operations during fiscal year. New work, code 
710: Construction of additional recreation facilities 
have been completed. 
Maintenance: Normal operation and maintenance 
work performed. Freshets regulated by Fern Ridge 
Lake project on Long Tom River are shown in Table 
37-K. 
38. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control activities pursuant to Section 
205, Public Law 858, 80th Cong., as amended 
(preauthorization). 
Fiscal year costs for preauthorization studies were: 
Alder Creek Lane, Molalla, OR, $40; Clatsop County 
Diking Districts Nos. 2 and 5, OR, $5,822; Malheur 
Lake, Harney County, OR, $7,406; North Santiam 
River, Idanha, OR, $94; and Svensen Island, Columbia 
River, OR, $3,027. 
Emergency bank protection (Section 14 of 1946 
Flood Control Act, Public Law 526, 79th Cong.). 
Fiscal year costs for preauthorization studies were: 
State Highway 101 and 401, Columbia River, WA, 
$6,302; McKenzie River, Rainbow, OR, $6,478; Salmon 
Creek, Clark County, WA, $37,780; and Umatilla 
River, Thorn Hollow, OR, $38,302. 
Emergency flood control activities-repair, 
flood fighting and rescue work (Public Law 99, 
84th Cong., and antecedent legislation). 
Federal costs for fiscal year were $223,114 for disaster 
preparedness, $1,146,071 for emergency operations, 
$75,423 for rehabilitation and $14,439,529 for advance 
measures. 
Cowlitz-Toutle Operations. The May 18, 1980 
eruption of Mt. St. Helens dramatically altered the 
hydraulic and hydrologic regimes of the Cowlitz and 
Toutle river valleys. Volcanic debris substantially 
reduced the river's hydraulic capacity to the point 
where major flooding could be expected with even 
normal runoff. 
A major recovery program for the Cowlitz and 
Toutle rivers funded under advance measures was 
initiated a short time after the eruption and was 
essentially completed during FY 1982. 
Total payments and funding commitments for the 
Cowlitz-Toutle recovery program, from initiation 
through FY 1983, with some contract modifications 
remaining to be negotiated, totalled $251,814,800. The 
authorized navigation channel on the Cowlitz between 
river mile 0 and 4.2 remains unusable due to continued 
sedimentation. 
Dredging to remove approximately three million 
cubic yards of material from the sediment stabilization 
basin (LT-1) in the lower Toutle River began in 
January 1983 and continued into April 1983. This 
work was done to improve the level of flood protection 
at Castle Rock. The total cost for this dredging was 
$3,361,386. 
In early October 1982, preliminary results of the 
Corps' sediment study indicated that flood protection 
for leveed areas along the lower Cowlitz River was less 
than previously estimated. In order to provide adequate 
flood protection, ten miles of levee were raised 
during November and December, on the average of 2.5 
feet, at Lexington, Castle Rock, Kelso and Longview. 
The cost of these temporary emergency flood protection 
measures totaled $2,650,000. 
Spirit Lake, WA. Portland District was directed on 
August 24, 1982 to respond to the Presidential Declaration 
of a State of Emergency for the Spirit Lake 
area. This declaration was precipitated by the release 
of a US Forest Service Spirit Lake Interagency Task 
Force report assessing the flood hazard posed by that 
body of water, which has been without a natural outlet 
since the May 18, 1980 eruption of Mt. St. Helens. The 
report concluded that Spirit Lake would fill to an 
extremely dangerous level by as early as Spring 1983 
and also mentioned concern over the structural stability 
of the debris plug holding back the lake due to the 
development of an extensive system of deep erosion 
gullies on its surface, some as deep as 40 feet. 
To contain the threat of a possible devastating flood 
caused by a failure of the Spirit Lake debris plug, and 
37-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
in response to a tasking from the Federal Emergency 
Management Agency (FEMA), the Portland District 
initiated a program aimed at meeting two objectives: 
(a) Undertake interim measures to assure that the lake 
is not allowed to continue rising unchecked so that the 
threat of a possible flood during 1983 is averted, and, 
(b) Perform field investigations and preliminary design 
work necessary to make a recommendation to 
FEMA for a permanent solution to the threat of flooding 
from Spirit Lake. 
By the end of FY 1982, plans for an interim solution 
to the Spirit Lake problem were well underway. Two 
contracts had been awarded; one for $3,119,914 to construct 
a 3,400-foot-long 60-inch diameter pipeline and 
outlet structure on the debris plug, a second for 
$3,751,419 to install and operate a barge-mounted 
pumping plant capable of pumping a sustained flow of 
180 cubic feet per second through the pipeline until 
July 1983. The pumps and engines were overhauled, 
the pump barge inlet was dredged, and a containment 
berm built to prevent further sediment infill into the 
inlet area during August and September 1983. Pumping 
was resumed on September 22, 1983. A supplemental 
agreement was negotiated with the original 
contractor to continue pumping throughout the 83/84 
winter until the end of July 1984. The cost for the pump 
and engine overhaul work and pumping through July 
1984 is estimated to cost about $3,400,000. 
In May 1982, President Reagan directed the Corps 
to prepare a comprehensive plan for long-term flood 
control and navigation maintenance. This 18-month 
study, due for completion in November 1983, will 
include various alternative permanent solutions to 
the threat of flooding from Spirit Lake. 
39. INSPECTION OF COMPLETED FLOOD 
CONTROL PROJECTS 
Funds appropriated for inspection of completed 
local flood protection works are used to determine 
maintenance condition of completed works and to 
ascertain whether those works are being properly 
maintained by local interests. A total of 61 leveed 
areas and 267 bank protection works were inspected at 
various locations along both banks of Lower Columbia 
River below Bonneville Dam, along Oregon Coast, 
in eastern Oregon, in southern Oregon and in Willamette 
River Basin. Of this total, 19 leveed areas in 
Oregon and 14 leveed areas in Washington along 
Lower Columbia River were inspected February 1983 
through September 1983. A representative of sponsoring 
districts accompanied the Portland District representatives 
performing the levee inspections. Aerial 
inspection of revetments in Willamette River Basin 
was supplemented by an onsite inspection at locations 
requiring maintenance. Deficiencies in maintenance 
and need for repairs were discussed with sponsoring 
districts' representatives and a report was made to 
each sponsor with recommendations for improving 
maintenance. The program to improve maintenance 
of completed Federal projects initiated by House 
Appropriations Committee on Civil Functions was 
continued. Periodic contact was maintained with uncooperative 
areas reported in FY 1982 to ascertain any 
change in attitude and to provide technical assistance, 
if requested. Of the 81 sponsors for some 125 
local flood protection projects inspected in Portland 
District, 18 were reported deficient in maintenance. 
Fiscal year costs were $52,841 and total costs to September 
30, 1983 were $920,040. 
40. INSPECTION OF NON-FEDERAL LEVEES 
Annual inspections are made of levees, flood control 
structures, and communities that have received previous 
assistance under the various features of Public 
Law 84-99 (flood fights, levee rehabilitation, advance 
measures). Inspections involve determining physical 
condition of levees and other structures, riprap displacement 
and vegetation control. Inspections also 
serve a valuable disaster preparedness function in 
terms of explaining to local interests their preparedness 
responsibilities and criteria for qualifying for 
future emergency assistance under PL 84-99. Local 
sponsors are advised of results of inspections. Approximately 
60 locations throughout the Portland District 
were inspected under this feature during FY 1983, at a 
cost of $54,385. 
41. LOWER COLUMBIA RIVER BASIN, 
OR AND WA 
Location. On Columbia River and minor tributaries, 
channels, and sloughs, between Sandy River, OR, 
about 15 miles east of Vancouver, WA, and mouth of 
Columbia River. 
Existing project. Plan for bank protection work, 
improvements to existing projects, and construction 
of flood control works in Lower Columbia River Basin 
provides for new construction and supplementing and 
extending projects constructed in Lower Columbia 
River Basin under authority of 1936 Flood Control 
Act: (a) Lower Columbia River Bank Protection, OR 
and WA provides for bank protection works at 96 locations 
on Columbia River and tributaries between 
Sandy River and mouth of Columbia River, totaling 
about 224,000 linear feet. Estimated total Federal cost 
is $24,800,000 (full funding) and non-Federal cost is 
$269,000; (b) See Table 37-L on Levees and Improvements 
to Existing Works; (c) Lower Columbia River 
Basin levees at new locations, Oregon and Washington, 
provides for construction of flood control works 
at: Washougal area, Clark County, WA, about 5.5 
miles of levee and appurtenant works at a Federal cost 
of $1,803,488, and non-Federal cost at $98,000; and 
Vancouver Lake area in vicinity of Vancouver, WA, 
about 18 miles of levee and appurtenant works at an 
estimated Federal cost (1980) of $19,500,000 and non- 
Federal cost at $900,000. This portion, Vancouver 
Lake, WA, has been reclassified "deferred." Total 
estimated Federal costs (1980) for both areas of work 
are $21,303,488 and non-Federal costs $998,000. 
Approved (1982) Federal cost for all work under project, 
Lower Columbia River Basin, OR, and WA, is 
$66,650,717. 
37-16

PORTLAND, OREGON DISTRICT 
Construction of improvement to existing project in 
Sandy Drainage District, OR, was completed by local 
interests at no construction cost to the Government. 
Improvements of levees have been accomplished by 
contract at the following locations: Multnomah County 
Drainage District, No. 1, OR, June 1962; Sauvie Island 
Drainage District, OR, October 1962; Woodson Drainage 
District, OR, December 1963; Rainier Drainage 
District, OR, June 1964; Cowlitz County Diking 
Improvement District, No. 15, WA, December 1965; 
Cowlitz County Diking Improvement Districts, Nos. 2 
and 13, WA, June 1965; Midland Drainage District, 
OR, April 1967; Cowlitz County Consolidated Diking 
Improvement District, No. 2, WA, June 1974; Beaver 
Drainage District, OR, June 1978; Wahkiakum County 
Consolidated Diking District #1, WA, October 1979; 
and Scappoose Drainage District, OR, September 
1980. Washougal Area, WA, (new location) levee construction 
has been completed. Under authorization for 
Lower Columbia River Basin bank protection works, 
construction has been completed at numerous locations. 
(See Section 42 for additional information). 
Local cooperation. Flood Control act of 1950 provides 
local interests furnish lands and rights-of-way; 
make necessary highway, highway bridge, and utility 
alterations; hold the United States free from damages; 
and maintain and operate completed works. Total 
non-Federal costs for all work are $4,367,000. For 
details of status or requirements of local cooperation 
see individual project reports. 
Operations during fiscal year. See individual 
projects. 
42. LOWER COLUMBIA RIVER BASIN BANK 
PROTECTION, OR AND WA 
Location. On Columbia River and tributaries 
between Sandy River, OR, and mouth of Columbia 
River. 
Existing project. Provides for construction of 
224,000 linear feet of bank protection works at 96 locations 
along Lower Columbia River below River Mile 
125 and along principal tributaries in this reach, to 
protect existing improvements such as levees and 
developed industrial lands from further erosion. 
Existing project is a unit of general comprehensive 
plan for flood control, navigation, and other purposes 
in Columbia River Basin. Construction of project 
began in July 1961 and is 71 percent complete. A total 
of 158,828 linear feet of bank protection work at 71 
locations has been completed. Estimated Federal cost 
is $24,800,000 (full funding). 
Local cooperation. Flood Control Act of 1950 provides 
local interests furnish lands and rights-of-way; 
make necessary highway, highway bridge, and utility 
alterations; hold the United States free from damages; 
and maintain and operate works after completion. 
Estimated costs for all requirements of local cooperation 
are $269,000. 
Operations during fiscal year. New work: White, 
122nd Avenue Extension, Fraser, Hudson, Armstrong 
and Cashdollar locations that will provide 6,023, 857, 
1750, 2010, 1720, and 471 linear feet of protection, 
respectively. White, 122nd Avenue Extension, and 
Cashdollar are scheduled for completion by December 
1983. Fraser, Hudson, and Armstrong are scheduled 
for completion by March 1984. 
43. MOUNT ST. HELENS & VICINITY, WA 
Location. On the Cowlitz River in the vicinity of 
Castle Rock, on the Toutle River about 2 miles above 
the mouth, and at Spirit Lake, at the base of Mt. St. 
Helens near the headwaters of the North Fork Toutle 
River. 
Existing project: 
Cowlitz-Toutle operations. The May 18, 1980 
eruption of Mt. St. Helens dramatically altered the 
hydraulic and hydrologic regimes of the Cowlitz and 
Toutle river valleys. Mudflows triggered by the eruption 
carried large volumes of sediment from the debris 
avalanche into these river valleys, reducing the hydraulic 
capacity to the point where major flooding could be 
expected with even normal runoff. Storm runoff and 
surface drainage continue to deliver sediment from 
the debris avalanche into the rivers. Funds allocated 
under Public Law 84-99 have previously been used for 
major recovery work on the Cowlitz and Toutle rivers. 
Spirit Lake, WA. An interim solution to the threat 
of a possible flood due to filling of the lake behind the 
debris plug was begun in late FY 1982. A contract to 
pump water from the lake, funded under Public Law 
84-99, was completed on July 31, 1983. A supplemental 
contract was subsequently negotiated to continue 
pumping for an additional year. 
Local cooperation. None required. 
Operations during fiscal year. New work: Dredging 
and levee rehabilitation were performed on the 
Cowlitz and Toutle Rivers at a cost of $6,301,733. 
Repair and replacement work performed on the pumps 
and engines and fuel purchased at cost of $1,255,634 
as part of supplemental contract to continue pumping 
Spirit Lake. 
44. SCAPPOOSE DRAINAGE DISTRICT, OR 
Location. In Columbia County, OR, along left 
bank of Multnomah Channel opposite Columbia River 
Miles 90.3 to 97.0. 
Existing project. The project as originally authorized 
by the Flood Control Act of June 22, 1936, provided 
for reconstruction of the existing levee system. 
Additional improvements provide for raising and 
strengthening 52,000 feet of levee, construction of toe 
drains, and additional pumping capacity. Project as 
originally authorized was completed in 1941. Design 
memorandum approved by higher authority in September 
1971. Final Environmental Impact Statement 
filed with CEQ April 24, 1972. Supplement to EIS was 
filed with CEQ July 29, 1974. Additional improvements 
were completed in September 1980. 
Local cooperation. Fully complied with. Requirements 
are described in full on page 37-14 of FY 1981 
Annual Report. 
37-17

REPORT OF THE CHIEF OF ENGINEERS. U.S. ARMY 1983 
Operations during fiscal year. Completed contract 
was finalized. 
45. SCHEDULING FLOOD CONTROL 
RESERVOIR OPERATIONS 
Corps of Engineers monitored flood control operations 
at four Bureau of Reclamation projects (Prineville, 
Ochoco, Emigrant, and Scoggins) and (Mossyrock) a 
municipal power project operated by Tacoma City 
Light. The Bureau of Reclamation projects were partially 
constructed with flood control funds, thereby 
subjecting project operation to monitoring by the 
Corps of Engineers under Section 7, Flood Control Act 
of 1944. Monitoring of Mossyrock flood control operation 
is assigned to the Corps by the Federal Energy 
Regulatory Commission as the Mossyrock license 
calls for specific flood control regulation. Under licensing 
agreement, the Tacoma City Light utility is required 
to provide 360,000 acre-feet of flood storage by 
December of each year. The Bureau of Reclamation 
sponsored projects were operated satisfactorily during 
FY 1983 for flood control. At Mossyrock, two winter 
high water periods occurred in December 1982 and 
January 1983. The spring snowmelt runoff was near 
normal. During the December high water period, 
reservoir regulation stored approximately 62,000 acrefeet 
at Mossyrock. Peak discharges at Castle Rock 
were observed to be 65,200 cubic feet per second, 
slightly below the regulation goal of 70,000 cubic feet 
per second. Unregulated flow would have been near 
78,000 cubic feet per second. All reservoirs filled to 
normal full pool levels during the refill season. Preparation 
of Reservoir Regulation Manuals for Scoggins 
and Mossyrock Projects is scheduled. Total cost of 
monitoring the five projects during FY 1983 was 
$6,021. 
46. TRASK RIVER, TILLAMOOK COUNTY, 
OR 
Location. On south branch of Trask River about 1 
mile west-southwest of Tillamook, Tillamook County, 
Oregon. 
Existing project. There is no existing project at 
the site. Work was authorized under the special continuing 
authority contained in Section 14 of the 1946 
Flood Control Act. This authority allows construction 
of emergency bank protection to prevent flood damages 
to public works. Riprap erosion protection along 
630 linear feet of bankline was constructed to protect 
Tone Road, a county roadway that provides the only 
vehicle access to seven dairy farms. 
Local cooperation. The project sponsor, Tillamook 
County, provided construction easements and 
rights-of-way and made necessary utility relocations. 
The county also agreed to hold the United States free 
from damages and maintain and operate the completed 
bank protection works. 
Operations during fiscal year. New work: Contract 
was awarded in June 1983 and work was completed 
September 8, 1983. 
47. TUALATIN, OR 
Location. Tualatin River channel between river 
mile 7.6 and 8.8 above the confluence with the Willamette 
River. Project is located in the city of Tualatin. 
Existing project. Provides channel improvements 
to reduce potential flood damage in the river basin. 
Major flood damage is concentrated in the city of Tualatin. 
Reduction of potential flood damage results 
from removal of channel constrictions in the project 
area by increasing channel capacity. The city's core 
area lies in a high water secondary channel which 
floods when the river surface rises above 120 feet 
NGVD (National Geodetic Vertical Datum). The project 
will improve channel capacity and exceeding 120 
feet NGVD would then average once in 13 years 
through the project area. 
Channel capacity is increased through excavation 
of approximately 75,000 cubic yards of river deposits 
and channel bottom rock. An average 100-foot channel 
bottom width excavation extends through the project. 
Nominal excavation depth varied between 4 feet 
and 8 feet. 
Local cooperation. Section 205 of Flood Control 
Act of 1948 fully complied with. 
Operations during fiscal year. New work: Contract 
awarded June 1983 and work was completed 
September 1983. 
48. WAHKIAKUM COUNTY CONSOLIDATED 
DIKING DISTRICT NO.1, WA 
Location. District occupies both Puget and Little 
Islands in Columbia River between River Miles 38.4 
and 45.0. These islands are in Wahkiakum County, 
WA, near town of Cathlamet. 
Existing project. Provides for raising and strengthening 
existing levees, removing several abandoned 
tide boxes, constructing a new tide box, extending an 
existing tide box and adding a gate well structure, 
constructing a new pumping station and relocating 
umping three existing pstations; raising the discharge 
lines of all pumping stations; and filling borrow 
ditches along the landward levee toe. Construction of 
new tide box was completed January 1976. Replacement 
of three pump stations and one tide box and 
addition of one pumphouse is complete. Final EIS 
filed September 18, 1972. 
Local cooperation. Flood Control Act of 1950 provides 
local interests furnish lands and rights-of-way; 
make necessary highway, highway bridge, and utility 
alterations; hold the United States free from damages; 
and maintain and operate completed works. 
Operations during fiscal year. New work: Contractual 
claim settled. 
49. WILLAMETTE RIVER BASIN, OR 
Location. Willamette River, formed by Coast and 
Middle Forks which join a few miles above Eugene, 
OR, flows north 189 miles, and enters Columbia River 
101.5 miles above its mouth. Basin has an area of 
37-18

PORTLAND, OREGON DISTRICT 
11,200 square miles and lies between Cascade Range 
on the east and Coast Range on the west. Major tributaries 
of Willamette River rise in Cascade Mountains 
and consist of Coast and Middle Forks and McKenzie, 
Calapooia, Santiam, Molalla, and Clackamas Rivers. 
Important tributaries that head in the Coast Range 
are Luckiamute, Yamhill, and Tualatin Rivers. Minor 
tributaries, all of which enter main stream from the 
west, are Marys River, Rickreall Creek, and Long Tom 
River. 
Existing project. Flood Control Act of 1938 
approved general comprehensive plan for flood control, 
navigation, and other purposes in Willamette 
River Basin and authorized $11,300,000 for initiation 
and partial accomplishment of plan recommended for 
initial development: the reservoirs and related works 
to be selected by Chief of Engineers. Subsequent Flood 
Control Acts, 1941 through 1974, authorized additional 
flood control and other works and increased 
monetary authority. 
Following projects were completed as authorized 
and in continuous operation: Fern Ridge Lake, August 
1951; Cottage Grove Lake, March 1952; Dorena Lake, 
October 1952; Detroit Lake, December 1960; Lookout 
Point Lake, June 1961. Hills Creek Lake, June 1963; 
Cougar Lake, March 1964; Fall Creek Lake, November 
1965; Green Peter-Foster Lakes, June-December 1967 
respectively; and Blue River Lake, October 1968. Under 
the authorization for construction of recreation facilities 
at completed projects, work has been accomplished 
at Fern Ridge, Cottage Grove, Dorena, Lookout 
Point, and Fall Creek Lakes. Details of operation, 
construction, and financial status of projects are in 
individual reports. During low-water season, July- 
September, supplemental water releases are made 
from Willamette River Basin Reservoirs for conservation 
purposes. Interests which benefit from increased 
downstream flows include irrigation, navigation, 
power, pollution abatement, and recreation. Although 
optimum regulation cannot be provided for every conservation 
interest, water released from reservoirs during 
the low-water season for a particular purpose will 
usually provide benefits to other conservation uses as 
well. Basic policy is to provide most beneficial overall 
uses as well. Basic policy is to provide most beneficial 
overall regulation, consistent with established wateruse 
priorities. (See Table 37-M on Willamette River 
Basin comprehensive plan.) 
Local cooperation. Section 2, Flood Control Act of 
June 28, 1938 applies. Local cooperation for other projects 
is in individual reports for those projects. 
Operations during fiscal year. See individual 
reports. 
50. WILLAMETTE RIVER BASIN BANK 
PROTECTION, OR 
Location. On Willamette River and tributaries, 
between Cascade Range and Coast Range, from a 
point south of Eugene to Portland, OR. 
Existing project. Provides for clearing, sloping, 
and revetting riverbanks; construction of pile and 
timber bulkheads and drift barriers; minor channel 
improvements; and maintenance of existing works for 
control of floods and prevention of erosion at various 
locations along Willamette River and its tributaries. 
The current scope of the project is a total of 510,000 
linear feet of bank protection at 236 locations. Estimated 
Federal cost is $31,000,000 (full funding). 
Construction of project began in 1938 and is 95 percent 
complete. A total of 483,870 linear feet of bank 
protection work at 228 locations consisting of revetment 
of riverbanks, pile and timber bulkheads, drift 
barriers, and channel improvements, have been completed 
on Willamette River and tributaries. 
Local cooperation. Section 3, Flood Control Act of 
1936 applies. Estimated costs for all requirements of 
local cooperation under terms of project authorization 
were $368,000 (1983). 
Operations during fiscal year. New work: A 
total of 4,468 linear feet of riprap revetment bank protection 
has been constructed at three locations. 
Maintenance: Annual inspection of revetments was 
made by helicopter in July 1983. 
Multiple-Purpose Projects 
Including Power 
51. BONNEVILLE LOCK AND DAM-LAKE 
BONNEVILLE, OR AND WA 
Location. Project is on Columbia River, 40 miles 
east of Portland, OR, about 146 miles above mouth of 
river. For description of Columbia River see Section 4. 
Existing project. A dam, powerplant, and lock for 
power and navigation. Spillway dam extends across 
main channel from Washington shore to Bradford 
Island, which divides the river at this point. Overflow 
crest at 24 feet above mean sea level is surmounted by 
18 vertical-lift steel gates and 10 remote control main 
dam hoists placed between piers which extend to elevation 
99 feet where a service roadway permits operation 
of two 350-ton gantry cranes for regulating gates. 
Powerhouse No. 1 extending across Bradford Slough 
to the Oregon shore has an installation of 10 units, 
consisting of two units of 43,200 kilowatts and eight 
units of 54,000 kilowatts each, totaling 518,400 kilowatts. 
Ordinary and extreme fluctuations of river at 
lower lock gate are about 21 and 47 feet respectively. 
Project includes fish ladders and locks to serve both 
main channel and Bradford Slough channel. Navigation 
lock and powerhouse are founded on andesite, 
and main dam rests upon solidified sedimentary rock 
of volcanic origin. The pool created by dam provides a 
navigable channel 15 feet deep between Bonneville 
and The Dalles Dams, a distance of 47 river miles. 
Principal data concerning navigation lock spillway 
dam, and powerplant are set forth in Table 37-N. 
Dam, navigation lock, 10-unit power generating installation, 
fishways, and attendant buildings and grounds 
cost $83,239,395, of which $6,072,480 is for navigation 
37-19

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
facilities 39,350,824 for power facilities and 
$37,816,091 for joint facilities, consisting of dam, 
fishways, buildings and grounds, and headwall section 
of power units 1 to 6, cost of which $2,106,000 is 
allocated to dam and lake facilities. 
In response to flow regulations and peakings from 
upstream plants operating under conditions of Canadian 
storage and Pacific Northwest-Southwest Intertie, 
two modifications were undertaken at the 
Bonneville project. The modification for peaking project 
was undertaken to minimize adverse environmental 
effects under rapidly changing flow conditions 
from upstream dams. The project was completed in 
1978 at a cost of $27,195,000. The second modification 
provides installation by building a second powerhouse 
located for increased power on the Washington 
shore adjacent to the end of the existing spillway. The 
new powerhouse contains eight units of 66,500 kilowatts 
each and two fish turbine generator units of 
13,100 kilowatts each for a combined capacity of 
558,200 kilowatts, bringing the entire Bonneville capacity 
to 1,076.6 megawatts. Additional fish facilities 
consist of the powerhouse collection system, second 
fish ladder on the Washington shore, transportation 
channel connecting existing Washington shore fish 
ladder with new exit control section, and fingerling 
bypass facilities which include fish screens in both the 
powerhouses. To provide for the anticipated increased 
visitor use, onsite visitor facilities are included. Under 
authority of the Bonneville Project Act (August 20, 
1937), a letter from Bonneville Power Administration 
to North Pacific Division dated January 21, 1965, 
requested construction of a second powerhouse. 
Construction of project started October 1933, was 
completed February 1953. Modification of powerhouse 
control equipment started March 1957, was completed 
September 1958. First two power units were placed in 
operation during fiscal year 1938. Powerhouse with 
complete installation of 10 units, was in operation 
December 1943. 
Construction of modification for peaking work 
commenced in September 1970 and was completed in 
September 1978. 
Construction of second powerhouse is near completion. 
Final environmental impact statement was filed 
with Council on Environmental Quality in April 1972. 
In response to increasing visitation which now exceeds 
800,000 a year at the dam site itself and 1,500,000 
project-wide, a visitor center with windows into the 
fish ladders, a 60-seat theatre, exhibits and displays 
was completed in 1975. Contracts for relocation of the 
highway, railroad and town of North Bonneville as 
well as excavation of the powerhouse are 99 percent 
complete. Construction of the main powerhouse and 
supply contracts for associated powerhouse equipment 
are 99 percent complete and Units 11 through 18 
were on-line by October, 1982. The visitor facility for 
the new powerhouse (which does not require costsharing) 
is an integral part of that structure. Estimated 
cost for construction of second powerhouse is 
$624,000,000 (full funding). 
Construction of future recreational facilities is contingent 
upon a cost-sharing contract with a nonFederal 
sponsor. Skamania County, WA has indicated an 
interest in cost-sharing at Home Valley upstream 
from Bonneville Lock and Dam; however, a costsharing 
contract has not been consummated. 
Through September 1983 power generation totaled 
173.6 billion kilowatt-hours. Of the gross income from 
sale of this power by Bonneville Power Administration, 
$157,854,450 was reimbursed to the U.S. Treasury 
to recover Corps of Engineers project investment 
and operating costs. 
Local cooperation. None required, except for non- 
Federal cost-sharing for development of Recreation 
Facilities at Completed Projects. 
Operations during fiscal year. New work: Negotiations 
were started for innovative financing of the 
Bonneville Power Units. Contracts were awarded to 
restore areas disturbed by powerhouse construction 
and are continuing. Contractual work also continued 
on the juvenile fish by-pass system. 
Maintenance: Normal operation and maintenance 
was performed during period. During the fiscal year 
6,026,452,000 kilowatt-hours of electrical power energy 
were generated, of which 5,989,820,000 kilowatt-hours 
were delivered to Bonneville Power Administration, 
the marketing agency. Traffic through the navigation 
lock consisting of rafted logs, petroleum products, 
grains, and miscellaneous cargo amounted to 8,369,680 
tons during calendar year 1982. 
52. COUGAR LAKE, OR 
Location. At mile 4.4 on South Fork McKenzie 
River which joins McKenzie River about 56.5 miles 
above its confluence with Willamette River. Project is 
about 42 miles east of Eugene, OR. 
Existing project. A rockfill dam with an impervious 
earth core, about 1,738 feet long at crest and 445 
feet high above the streambed. Reservoir is 6 miles 
long with storage capacity at full pool of 219,000 acrefeet 
and controls runoff of tributary drainage area of 
210 square miles. Spillway is on right abutment and 
outlet and power tunnels in left abutment. Outlet 
tunnel is provided with a chute and stilling basin. 
Powerplant consists of two 12,500 kilowatt units with 
minimum provisions for installing a third unit of 
35,000 kilowatts for future peaking capacity. Improvement 
functions as a unit in coordinated system of 
reservoirs for multiple-purpose development of water 
resources in Willamette River Basin. Recreation facilities 
are provided by the U.S. Forest Service. Also 
authorized (but unconstructed) is a reregulating dam, 
Strube Lake, below Cougar Lake which would permit 
Cougar to operate as a peaking powerplant. The 
Strube dam would contain two units totalling 4,600 
kilowatts. 
Construction of project initiated June 1956 is complete, 
excluding Strube Lake and Cougar Additional 
Unit for which planning is essentially complete. Also, 
plans and specifications for the first construction 
37-20

PORTLAND, OREGON DISTRICT 
contract (relocations) have been completed. Generating 
units 1 and 2 were placed in commercial operation 
March 23 and February 4, 1964, respectively. Physical 
in-service date for flood control was November 29, 
1963. Through September 1983 power generation totaled 
2.6 billion kilowatt hours. Of the gross income from 
sale of this power by Bonneville Power Administration, 
$12,558,550 was reimbursed to the U.S. Treasury 
to recover Corps of Engineers project investment and 
operating costs. Estimated Federal cost of Strube 
Lake and Cougar Additional Unit is $108,000,000 (full 
funding). 
Local cooperation. None required. 
Operations during fiscal year. New work: Negotiations 
were initiated for the innovative financing of 
Strube Lake and Cougar Additional Unit. 
Maintenance: Ordinary operation and maintenance 
continued. During fiscal year, 168,325,000 kilowatthours 
of electrical energy were generated at project, of 
which 167,544,000 kilowatt-hours were delivered to 
Bonneville Power Administration, the marketing 
agency. Freshets regulated by Cougar Lake on South 
Fork McKenzie River are shown on Table 37-K. 
53. DETROIT LAKE, OR 
Location. On North Santiam River with dam 50 
miles from mouth 45 miles southeast of Salem, OR, 
North Santiam River flows north and west for 85 
miles, and unites with South Santiam River to form 
Santiam River, which 10 miles downstream enters 
Willamette River 108 miles above its mouth. 
Existing project. One main dam and a reregulating 
dam, both with power-generating facilities. Detroit 
Dam is a concrete gravity structure about 1,522 feet 
long and 454 feet high from lowest point of the general 
foundation to roadway deck. Spillway is a gatecontrolled 
overflow section, and outlet works are gatecontrolled 
conduits through dam. Powerhouse with 
two units having a capacity of 50,000 kilowatts each is 
in right abutment immediately below dam. Reservoir 
has a storage capacity at full pool of 454,900 acre-feet 
and runoff of tributary drainage area of 438 square 
miles. It is being operated as a unit in coordinated 
reservoir system to protect Willamette Valley from 
floods, to increase low water flows in interest of navigation 
and irrigation, to generate power, and for other 
purposes. Reregulating dam 3 miles downstream at 
Big Cliff site is concrete gravity type, about 191 feet 
high from lowest point of the general foundation to 
roadway deck. Power installation consists of one unit 
with a capacity of 18,000 kilowatts. Reservoir has a 
storage capacity of 5,930 acre-feet at full pool. Project 
is a unit of comprehensive plan for flood control and 
other purposes in Willamette Basin. Recreation facilities 
are provided by the U.S. Forest Service, Oregon 
State Park System and the town of Detroit. 
Construction of project was begun in May 1947 
completed December 1960. The two powerhouse generating 
units were placed in commercial operation 
June and October 1953. At Big Cliff powerhouse, 
single generating unit was placed on-line June 1954. 
Use of Big Cliff Dam for reregulating fluctuating flow 
from Detroit units was effected October 1953. Through 
September 1983 power generation totaled 14.5 billion 
kilowatt-hours. Of the gross income from sale of this 
power by Bonneville Power Administration, 
$16,217,300 was reimbursed to the U.S. Treasury to 
recover Corps of Engineers project investment and 
operating costs. 
Local cooperation. None required. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance continued. During 
fiscal year 605,035,000 kilowatt-hours of electrical 
energy were generated at project of which 601,914,000 
kilowatt-hours were delivered to Bonneville Power 
Administration, the marketing agency. Freshets regulated 
by the Detroit Lake project on North Santiam 
River are shown in Table 37-K. 
54. GREEN PETER-FOSTER LAKES, OR 
Location. At approximate mile 5.5 on Middle Santiam 
River which joins South Santiam River about 
56.8 miles above its confluence with Willamette River. 
Dam is about 30 miles southeast of Albany in Linn 
County, OR. 
Existing project. One main dam and a reregulating 
dam, both with power-generating facilities. Green 
Peter Dam is a concrete gravity structure, 1,400 feet 
long and 385 feet high above the lowest point of the 
general foundation with a gate-controlled spillway. 
Outlet works consist of two conduits through spillway, 
discharging into a stilling basin. Powerplant, on 
right bank adjacent to spillway stilling basin, consists 
of two units with an installed capacity of 80,000 
kilowatts. Reservoir provides storage capacity at full 
pool of 430,000 acre-feet, extending 6.5 miles up Quartzville 
Creek and some 7.5 miles up Middle Santiam 
River above creek junction, forming a Y-shaped pool. 
Reservoir controls runoff of tributary drainage area of 
277 square miles. 
Foster Dam, 7 miles downstream from Green Peter 
Dam is located on South Santiam River about 38 miles 
above its confluence with Santiam River and 1.5 miles 
below its confluence with Middle Santiam River. Foster 
Dam consists of an earth, gravel, androck-filledembankment, 
146 feet high from lowest point of the general 
foundation and a concrete gravity gate-controlled 
spillway and stilling basin for a total length of 4,800 
feet. Power installation consists of two units with a 
capacity of 20,000 kilowatts. Foster Lake has a storage 
capacity, at full pool, of 61,000 acre-feet. Project 
functions as a unit in coordinated system of reservoirs 
for multiple-purpose development of water resources 
in Willamette River Basin. 
All construction on Green Peter-Foster Lakes project 
initiated June 1961 is completed. Green Peter Lake 
was placed in operation for useful flood control June 
1967 as a unit of coordinated reservoir system for protection 
of the Willamette River Basin. First powergeneration 
unit was placed on the line June 9, 1967 
37-21

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
and second, June 28, 1967. Use of Foster Lake for 
reregulating fluctuating flows from Green Peter units 
was effective December 1967. First power generation 
unit was placed on-line August 22, 1968 and second, 
September 6, 1968. Through September 1983 power 
generation totaled 5.5 billion kilowatt-hours. Of the 
gross income from sale of this power by Bonneville 
Power Administration, $28,622,250 was reimbursed to 
the U.S. Treasury to recover Corps of Engineers project 
investment and operating costs. 
Local cooperation. None required. 
Operations during fiscal year. Maintenance: Normal 
operation and maintenance continued. During 
the fiscal year 409,946,000 kilowatt-hours of electrical 
energy were generated at project of which 407,023,000 
kilowatt-hours were delivered to Bonneville Power 
Administration, the marketing agency. Freshets regulated 
by Green Peter Lake project on Middle Santiam 
River are shown in Table 37-K. 
55. HILLS CREEK LAKE, OR 
Location. On the Middle Fork, Willamette River, 
47.8 miles from mouth and 26.5 miles upstream from 
Lookout Point Dam. Middle Fork, Willamette River 
rises on west slope of Cascade Range and flows 
northwesterly to its junction with Coast Fork, Willamette 
River. Dam is about 45 miles southeast from 
Eugene, OR. 
Existing project. An earth-and-gravel-fill dam 
about 2,150 feet long at the crest and 338 feet above 
lowest point of the general foundation. A gate-controlled 
concrete gravity chute-type spillway is in right 
abutment. Diversion tunnel, outlet tunnel and power 
tunnel are in same abutment. Powerhouse with two 
15,000 kilowatt units is located next to spillway. Hills 
Creek Lake is about 8.5 miles long and provides storage 
capacity at full pool of 356,000 acre-feet. Project 
controls runoff of drainage area of 389 square miles 
and is an integral unit of comprehensive plan for 
development of water resources of Willamette River 
Basin. Hills Creek Lake and Lookout Point Lake are 
operated as a unit for control of floods and generation 
of power on Middle Fork Willamette River. These projects, 
in conjunction with Dexter reregulating dam and 
Fall Creek Lake flood control system, will effectively 
control floods on Middle Fork and provide maximum 
efficient generation of hydroelectric power. Recreation 
facilities are provided by the U.S. Forest Service. 
Construction of project, initiated May 1956, was 
completed June 1963. The project was placed in service 
for useful flood control in November 1961. On 
May 2, 1962, the two power units were placed on-line. 
Through September 1983 power generation totaled 3.3 
billion kilowatt-hours. Of the gross income from sale 
of this power by Bonneville Power Administration, 
$13,293,700 was reimbursed to the U.S. Treasury to 
recover Corps of Engineers project investment and 
operating costs. 
Local cooperation. None required. 
Operations during fiscal year. Ordinary operation 
and maintenance continued. During fiscal year 
206,442,000 kilowatt-hours of electrical power were 
generated, of which 205,867,000 kilowatt-hours were 
delivered to Bonneville Power Administration, the 
marketing agency. Freshets regulated by Hills Creek 
Lake on Middle Fork Willamette River are shown in 
Table 37-K. 
56. JOHN DAY LOCK AND DAM-LAKE 
UMATILLA, OR AND WA 
Location. On Columbia River about 3 miles downstream 
from mouth of John Day River and about 215 
miles above mouth of Columbia River. 
Existing project. A dam, powerplant, navigation 
lock, fish ladders, and appurtenant facilities with a 
slack-water lake about 75 miles long extending to 
McNary Lock and Dam. Included is relocation of railroads, 
highways, utilities, and communities affected 
by the impoundment. The project as originally authorized 
would have provided 2,000,000 acre-feet of flood 
control storage. As modified, the project provides 
500,000 acre-feet of flood control storage between elevations 
257 and 268. The structure is 5,900 feet in 
length and stands about 161 feet above streambed. 
Powerhouse has space for 20 generating units of 
135,000 kilowatts each; 16 units have been installed 
for a present capacity of 2,160,000 kilowatts. Principal 
project data are set forth in Table 37-N. 
A detailed description of project as authorized and 
modified is on pages 1992 and 1993 of Annual Report 
for 1962 under the Walla Walla District. 
Construction began July 1958 and the project was 
opened to navigation April 1968. The main dam contract 
is complete. Lock rehabilitation work begun in 
FY 1980 is essentially complete. Entire project is estimated 
to be 99 percent complete. Through September 
1983 Power Generation totaled 158.9 billion kilowatthours. 
Of the gross income from sale of this power by 
Bonneville Power Administration, $173,875,400 was 
reimbursed to the U.S. Treasury to recover Corps of 
Engineers project investment and operating costs. 
Estimated Federal cost of new work is $512,333,000 
(full funding), consisting of $512,000,000 Corps of 
Engineers and $333,000 for Coast Guard navigation 
aids. 
Local cooperation. None required. 
Operations during fiscal year. New work: Design 
work continued for the fish by-pass including plans 
and specifications for scheduled contracts. 
Rehabilitation: Navigation lock work was 
completed. 
Maintenance: Work has begun to refurbish turbinegenerator 
units and auxiliary equipment. Normal 
operation and maintenance continued. During fiscal 
year 10,915,702 kilowatt-hours of electrical power 
were generated by the 16 generating units of which 
10,898,009 kilowatt-hours were delivered to Bonneville 
Power Administration, the marketing agency. 
37-22

PORTLAND, OREGON DISTRI 
Traffic through the navigation lock, consisting of 
petroleum products, grains, and miscellaneous cargo, 
amounted to 7,181,719 tons during calendar year 1982. 
57. LOOKOUT POINT LAKE, OR 
Location. On Middle Fork, Willamette River at 
Meridian site, 21.3 miles from mouth. Middle Fork, 
Willamette River, rises in Lane County on western 
slope of Cascade Range and flows northwesterly to its 
junction with Coast Fork, which is head of main stem 
Willamette River. Dam is about 22 miles southeast 
from Eugene, OR. 
Existing project. A main dam at Meridian site 
and a reregulating dam 3 miles downstream at Dexter 
site. Both dams are earth-and-gravel-fills with concrete 
spillways and have power generating facilities. 
Main dam is 258 feet high from lowest point of the 
general foundation to deck and is 3,381 feet long at 
crest forming a reservoir 14.2 miles long providing 
storage of 456,000 acre-feet at full-pool level. Reservoir 
controls runoff of tributary drainage area of 991 
square miles. Spillway, 274 feet long, is a gate-- 
controlled overflow type, forming right abutment. 
Outlet works consisting of slide-gate-controlled conduits 
pass through spill-way section. Powerhouse has 
three main generating units with a capacity of 120,000 
kilowatts. Reregulating dam has a maximum height 
of 107 feet above lowest point of the general foundation 
and is 2,765 feet long at crest, forming a full pool 
of 27,500 acre-feet extending upstream to main dam 
and providing pondage to regulate Lookout Point 
powerhouse water releases to a uniform discharge. 
Spillway consists of a gate-controlled overflow section 
509 feet long forming right abutment. 
Flow regulation is accomplished by use of spillway 
gates and releases through powerhouse, which contains 
one 15,000-kilowatt unit. Lookout Point and 
Dexter Lakes are operated as a single unit of a coordinated 
system of reservoirs to protect Willamette River 
Valley against floods, to provide needed hydroelectric 
power, and to increase low water flows for navigation, 
irrigation, and other purposes. Existing project authorized 
as a unit of comprehensive plan for flood control 
and other purposes in Willamette River Basin. 
Construction of project initiated May 1947 was 
completed June 1961, except for construction of additional 
recreation facilities to be funded from Recreation 
Facilities at Completed Projects. Future recreation 
facilities will be provided in accordance with the costsharing 
contract with Lane County. At Lookout Point 
powerhouse, generating units 1, 2 and 3 were placed in 
commercial operation December 1954, February 1955, 
and April 1955, respectively. At Dexter powerhouse 
the single unit was placed on-line May 1955. Use of 
Dexter Lake for reregulating fluctuating flows from 
Lookout Point units was effected in December 1954. 
Through September 1983 power generation totaled 
11.7 billion kilowatt-hours. Of the gross income from 
sale of this power by Bonneville Power Administration, 
$48,261,600 was reimbursed to the U.S. Treasury 
to recover Corps of Engineers project investment and 
operating costs. 
Local cooperation. Lane County Parks is participating 
in a multiple project cost-sharing (50 percent) 
contract for many of the existing parks at four projects, 
including Lookout Point-Dexter. 
Operations during fiscal year. Maintenance: 
Normal operation and maintenance continued. During 
fiscal year 518,895,000 kilowatt-hours of electrical 
power energy were generated at project of which 
517,382,000 kilowatt-hours were delivered to Bonneville 
Power Administration, the marketing agency. 
Freshets regulated by Lookout Point Lake project on 
Middle Fork Willamette River are shown in Table 
37-K. 
58. LOST CREEK LAKE, ROGUE RIVER 
BASIN, OR 
Location. On upper Rogue River at mile 153.6 
about 30 miles northeasterly from Medford, OR. 
Existing project. A rock and gravel-fill embankment 
dam about 327 feet high from streambed to crest, 
with an overall length of 3,750 feet with an impervious 
earth core and a gate-controlled concrete spillway. 
Powerhouse is on right abutment and houses two 
Francis-type turbines with installed capacity of 24,500 
kilowatts each. Regulating outlet facility with provisions 
for temperature regulation for releases in interest 
of fishery enhancement is also on right bank. 
Reservoir 10 miles long provides 315,000 acre-feet of 
usable storage. Project provides control of runoff of 
drainage area of 674 square miles. In addition to 
hydroelectric power generation, project provides flood 
control, irrigation, future municipal and industrial 
(M&I) water supply, fish and wildlife enhancement, 
water quality control and recreation benefits. 
Construction of project initiated July 1967 is 
complete. Generating units 1 and 2 were placed in 
commercial operation July 6 and July 13,1977, respectively. 
Physical in-service date for flood control was 
February 18, 1977. Final environmental statement 
was filed with Council on Environmental Quality in 
June 1972. Through September 1983 power generation 
totaled 1.8 billion kilowatt-hours. Of the gross income 
from sale of this power by Bonneville Power Administration, 
$7,453,350 was reimbursed to the U.S. 
Treasury to recover Corps of Engineers project investment 
and operating costs. 
Local cooperation. Authorizing act required that 
local agencies furnish assurances prior to construction 
that demands will be made for future use of water 
supply storage within a period that will permit repayment 
of costs, including interest, allocated to water 
supply within life of the project; that State of Oregon 
take action, prior to construction to insure maintenance 
in stream of flows to be released for fishery; in 
addition, costs allocated to irrigation would have to be 
repaid in manner and to an extent consistent with 
reclamation laws and policies; and costs allocated to 
power will be repaid on a system basis by revenue 
37-23

REPORT OF THE CHIEF OF ENGINEERS. U.S. ARMY 1983 
from sales of power in Pacific Northwest Federal system 
by Bonneville Power Administration. A survey in 
September, 1980 of M&I water supply needs showed 
nine communities with water supply needs. A contract 
for M&I supply has been completed with one of the 
communities. Assurances for municipal and industrial 
water supply were obtained from six communities 
in Rogue River Valley. On February 26, 1966 
Oregon State Department of Fish and Wildlife agreed 
to operate Rogue River hatchery for mitigation and 
enhancement of fish. The hatchery became operational 
in 1972. 
Operations during fiscal year. New work: The 
roadway was repaired and a contract was awarded for 
replacement of exterior panels on the powerhouse and 
service building. 
Maintenance: During fiscal year 371,483,000 
kilowatt-hours of electrical power energy were generated 
at project of which 369,199,000 kilowatthours 
were delivered to Bonneville Power Administration, 
the marketing agency. Freshets regulated by Lost 
Creek Lake on Rogue River are shown in Table 37-K. 
59. THE DALLES LOCK AND DAMLAKE 
CELILO, WA AND OR 
Location. On Columbia River at head of pool 
behind Bonneville DI)am, about 192 miles above mouth 
of river and 88 miles east of Portland, OR. 
Existing project. A dam, powerplant, navigation 
lock, and appurtenant facilities. Improvement provides 
for navigation and hydroelectric power generation. 
Dam is designed for a normal pool at elevation 
160 feet at mean sea level. Normal pool forms a reservoir 
extending upstream about 23 miles providing 
slackwater to John Day Dam site. The Dalles Dam is 
8,700 feet long and consists of a rock, gravel, and sand 
river closure section from Oregon shore connecting to 
a nonoverflow section which in turn joins powerhouse, 
then concrete nonoverflow sections connecting 
spillway with powerhouse and spillway with navigation 
lock at right abutment on Washington shore. 
Fish-passing facilities including two ladders and a 
fish lock are provided. Powerhouse was constructed 
for 14 units initially and substructure for eight additional 
units, an ultimate total of 22 units. Initial 
installation, excluding two 13,500 kilowatt fishwater 
units, is 1,092,000 kilowatts. With eight units installed 
for a capacity of 687,800 kilowatts, the 22 unit total is 
1,808,800 kilowatts. Structures are founded on 
Columbia River basalt. Principal data concerning 
lock, spillway, and powerhouse are set forth in Table 
37-N. 
Major construction of project initiated February 
1952 was completed October 1960 when unit No. 14 
was placed in commercial operation. Initial contract 
for additional units 15-22 was awarded in September 
1967. Additional 8-unit phase was completed when 
unit 22 was placed in commercial operation in 
November 1973. Construction of future recreational 
facilities is contingent upon a cost-sharing contract 
with a non-Federal sponsor. Studies for adding power 
generation facilities to the North Shore Fish Ladder 
Auxiliary Water Supply System were initiated in 
October 1979 and completed in December 1980. These 
facilities would provide baseload generation (3.5 megawatts) 
and would not impact the present operation of 
the North Fish Ladder. Seufert Visitor Center was 
completed in September 1980. Through September 
1983 power generation totaled 177.6 billion kilowatthours. 
Of the gross income from sale of this power by 
Bonneville Power Administration, $212,059,050 was 
reimbursed to the U.S. Treasury to recover Corps of 
Engineers project investment and operating costs. 
Local cooperation. None required except for non- 
Federal cost-sharing for development of Recreation 
Facilities at Completed Projects. 
Operations during fiscal year. Maintenance: 
Ordinary operation and maintenance continued. 
During fiscal year 8,821,254,000 kilowatt-hours of 
electrical power energy were generated at project of 
which 8,802,304,000 kilowatt-hours were delivered to 
Bonneville Power Administration, the marketing agency. 
Traffic through the navigation lock, consisting of 
petroleum products, grains and miscellaneous cargo 
amounted to 7,326,219 tons during calendar year 1982. 
General Investigations 
60. SURVEYS 
Fiscal year costs were $5,018,558 of which $858,080 
was for navigation studies, $1,126,838 for flood damage 
prevention studies, $169,512 for comprehensive 
studies, $2,615,647 for review of authorized projects, 
$203,027 for miscellaneous activities, and $45,454 for 
coordination with other agencies. 
61. COLLECTION AND STUDY OF 
BASIC DATA 
International water studies. The Columbia 
River Treaty between Canada and the United States 
of America relating to cooperative Development of the 
Water Resources of the Columbia River Basin was 
signed at Washington, D.C., on January 17,1961, and 
the exchange of ratifications took place on September 
16, 1964. 
Implementation of the Treaty by the United States 
and Canada entities under the guidance of the Permanent 
Engineering Board has continued. The two 
permanent committees established by the entities, the 
Operating Committee and the Hydrometeorological 
Committee, continue to function. 
Costs for support of both committee activities were 
$13,374 for the fiscal year. 
Flood plain management services. Flood Plain 
Management Services Program comes under Section 
206 of the 1960 Flood Control Act, PL 86-645, as 
amended. Through technical services and planning 
guidance, the program encourages comprehensive 
flood plain management planning at all levels to 
reduce the potential for losses to life and property from 
floods. Federal and non-Federal agencies and the 
37-24

PORTLAND, OREGON DISTRICT 
private sector are assisted with planning and development 
information for flood hazard areas. This 
assistance is in the form of local flood plain regulations, 
Federal Insurance Program requirements, and 
Executive Order 11988 guidelines. Such assistance 
may include factual flood information (available or 
determined) and interpretation on flood frequencies, 
extent of flooding, flood-water velocity, duration of 
flooding and floodway limits. 
Services accomplished during fiscal year. Technical 
services and planning guidance responses furnished 
totaled 620. Of this total, 75 were from other Federal 
agencies; 160 from non-Federal agencies; and 385 
from individuals, realtors, corporations, lending institutions, 
engineers, architects, and others. Cost for 
providing these services during FY 1983 totaled 
$176,521. 
Hydrologic studies. Environmental and ecological 
aspects are being considered on all hydrologic studies. 
Improvements in procedures to determine reservoir 
temperatures, nitrogen supersaturation, dissolved 
oxygen, suspended sediment, turbidity, design floods, 
flood forecasting and flood regulation are a continuing 
program. Costs for hydrologic studies during the 
fiscal year were $2,984. 
Total costs for collection and study of basic data for 
fiscal year 1983 were $192,880. 
62. CONTINUATION OF PLANNING AND 
ENGINEERING, BONNEVILLE 
NAVIGATION LOCK, OR AND WA 
The proposed project would provide for a new lock 
just south of the existing lock on the Oregon shore and 
will have dimensions of 86 feet wide, 675 feet long and 
at least 15.0 feet deep over the sill. 
Work on the General Design Memorandum and a 
feature Memo (Relocation) was initiated in FY 1982 
and was continued in FY 1983, and they are 68 percent 
and 90 percent complete, respectively. Other feature 
memorandums that were initiated in FY 1983, (and 
percentage completed) are Site Selection (100%), BPA 
Substation and Project Power Requirements (20%), 
Real Estate for Relocation (15%), Geology, Foundation 
and Excavation(60%), and Concrete Materials (20%). Total 
costs to September 30, 1983 are $5,352,734. Estimated 
Federal project cost is $182,019,000 (October 1983); 
Corps of Engineers, $182,000,000 and U.S. Coast 
Guard, $19,000. 
63. ADVANCE ENGINEERING AND DESIGN 
Chetco River, OR. The modification to the existing 
project was authorized by Public Law 97-88, 
December 4, 1981. Plan of improvement would deepen 
the existing navigation channel and turning basin by 
two feet to a depth of 16 feet MLLW and extend the 
existing jetty system 750 feet for the north and 1,250 
feet for the south jetty. (For details relating to previous 
project, see Section 3.) 
Work on the General Design Memorandum was 
initiated in FY 1982 and is 98 percent complete. Total 
costs were $27,464. Estimated project cost (full funding), 
is $8,302,000; Corps of Engineers $8,200,000; U.S. 
Coast Guard, $2,000; Non-Federal, $100,000. 
Total cost of Advance Engineering and Design for 
FY 1983 was $47,529: Chetco River, OR, $27,464; 
Johnson Creek, OR, $952; Siuslaw River and Bar, OR, 
$19,113. 
37-25

TABLE 37-A 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
In Text Project Funding FY 80 FY 81 FY 82 FY 83 Sep. 30, 1983 
1. Bandon Small Boat New Work 
Basin, Coquille, OR 
2. Charleston Channel, 
Coos Bay, OR 
3. Chetco River, OR 
4. Columbia and Lower 
Willamette Rivers 
Below Vancouver, 
WA and Portland, 
OR (Federal Funds) 
(Contributed Funds) 
5. Columbia River at 
Baker Bay, WA 
6. Columbia River 
Between Chinook, 
WA, and Head of 
Sand Island 
7. Columbia River at 
The Mouth, OR 
and WA 
8. Columbia River 
Between Vancouver, 
WA and The Dalles, 
OR 
9. Coos Bay, OR 
(Federal Funds) 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
54,000 
67,189 
10,300 
10,300 
15,000 438,691 601,000 
15,101 111,798 925,771 
40,000 
35,704 
63,000 1,156,000 
67,032 48,538 
218,000 438,000 515,000 535,500 
220,562 414,518 536,070 537,204 
1,177,314 
1,175,175 
1,269,300 
161,574 
2,043,7131 
2,043,7131 
3,439,674 
3,438,220 
- - - - 28,349,3042 
- - - - 28,349,3042 
49,893,300 10,007,000 9,027,100 15,812,000 188,659,126 
25,420,498 28,326,565 14,286,451 17,042,261 188,634,820 
- - - - 665,954 
- - - - 665,954 
- - - - 941,252 
- - - - 941,252 
179,000 
129,258 
80,000 
114,461 
92,000 150,400 
107,273 137,965 
317,000 158,000 847,000 
317,040 148,446 229,649 
18,000 250,000 100,000 
17,000 198,546 -35,955 
53,150 
663,437 
187,772 
3,008,000 5,326,000 4,075,000 2,131,100 
2,976,030 4,768,601 4,583,876 2,191,396 
- 3,105,000 
- 3,089,332 
177,000 
191,730 
2,273,774 
2,260,136 
220,2835 
220,2835 
2,694,691 
2,677,402 
17,557,7616 
17,557,1246 
62,388,2597 
62,348,2797 
7,322,878 
7,321,940 
- 5,989,5098 
- 5,989,5098 
342,500 622,000 206,000 
352,115 615,974 216,968 
189,000 
187,748 
-53,608 
1,801 
9,986,5489 
9,984,8829 
29,750,09210 
29,750,09210 
37-26

TABLE 37-A 
(Continued) 
PORTLAND, OREGON DISTRICT 
COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
In Text Project Funding FY 80 FY 81 FY 82 FY 83 Sep. 30, 1983 
(Contributed Funds) 
10. Coos and Millicoma 
Rivers, OR 
11. Coquille River, OR 
12. Depoe Bay, OR 
13. Lake River, WA 
15. Nehalem Bay, OR 
16. Port Orford, OR 
18. Rogue River Harbor 
at Gold Beach, OR 
Maint. 
Approp. 
Cost 
Major 
Rehab. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint 
Approp. 
Cost 
Major 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
3,355,000 2,737,200 4,566,000 2,263,000 
3,304,736 2,701,903 3,632,308 3,269,372 
171,800 
125,524 
67,000 130,000 136,400 
109,343 132,768 122,851 
53,000 292,000 383,000 167,600 
52,855 230,454 438,165 172,074 
26,000 165,000 
26,471 140,925 
23,000 
22,916 
-6,000 
18,224 
2,000 
2,464 
3,000 
419 2,700 
160,000 2,232,000 9,020,000 550,000 
156,584 2,201,795 8,648,997 922,899 
70,000 
70,649 
60,500 179,000 191,000 
56,486 175,849 198,364 
685,700 399,000 755,000 1,044,500 
599,711 552,841 718,623 796,151 
37-27 
48,169,74811 
48,147,82811 
2,335,966 
2,335,966 
486,680 
486,680 
350,23812 
350,23812 
1,364,399 
1,349,575 
693,36613 
693,36613 
4,093,54414 
4,090,64414 
367,364 
367,364 
582,764 
582,551 
2,700 
2,700 
74,036 
73,736 
302,00615 
302,00615 
44,760 
44,760 
11,962,000 
11,930,275 
758,6921e 
758,6921e 
1,442,728 
1,442,622 
4,156,25217 
4,156,25217 
6,587,02018 
6,294,98518

TABLE 37-A 
(Continued) 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
In Text Project Funding FY 80 FY 81 FY 82 FY 83 Sep. 30, 1983 
19. Siuslaw River, OR 
20. Skamokawa Creek, 
WA 
21. Skipanon Channel, 
WA 
22. South Channel, 
Government Island, 
OR 
23. Tillamook Bay and 
Bar, OR 
24. Umpqua River, OR 
25. Willamette River 
Above Portland and 
Yamhill River, OR 
Major 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
- 210,000 115,042 4,999,813 
- 196,104 107,638 287,947 
385,000 943,000 1,088,000 504,000 
384,838 909,802 1,122,756 503,243 
35,000 
35,799 
15,000 
3,713 
-10,000 
59 
-1,500 
66,000 487,000 177,000 534,100 
67,244 304,010 357,467 214,238 
43,500 
28,763 
102,000 
27,643 
-5,399 
8,868 
66,500 230,000 
69,269 229,073 
10,150,000 
10,157,855 
15,000 
-170,736 
67,000 
60,312 
-100,000 
18,076 
68,800 
74,903 
-50,000 
13,654 
964,000 650,000 1,201,000 413,000 
956,832 602,890 1,167,055 503,589 
83,000 
107,520 
47,000 
54,802 
10,000 
11,359 
15,500 
16,897 
37-28 
635,783 
635,783 
5,324,855's 
591,68919 
8,541,64320 
8,537,26320 
879,285 
879,285 
2,400 
2,400 
293,299 
292,917 
280,854 
280,854 
2,126,507 
1,803,810 
145,500 
56,406 
22,434,82723 
22,434,82721 
2,619,2832 
2,617,5002 
2,839,799 
2,839,799 
17,718,87723 
17,708,86523 
19,020,305 
19,018,265 
2,500,677 
2,500,677 
862,91824 
862,91824 
17,653,55625 
17,653,51325

PORTLAND, OREGON DISTRICT 
TABLE 37-A 
(Continued) 
COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
In Text Project Funding FY 80 FY 81 FY 82 FY 83 Sep. 30, 1983 
26. Willamette River at New Work 
Willamette Falls, 
OR 
27. Winchester Bay, 
Umpqua River, OR 
28. - Yaquina Bay and 
Harbor, OR 
29. Yaquina River, OR 
30. Applegate Lake, 
Rogue River Basin, 
OR 
31. Beaver Drainage 
District, OR 
32. Blue River Lake, OR 
33. Cottage Grove Lake, 
OR 
34. Dorena Lake, OR 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Minor 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
520,00526 
520,00526 
1,150,000 526,000 625,000 720,000 
1,172,411 515,060 631,011 537,797 
65,000 
37,678 
60,000 
80,685 
533,000 920,000 
78,148 795,066 
287,000 420,000 737,000 1,085,100 
291,721 408,591 741,918 1,089,700 
12,433,82327 
12,244,04627 
234,794 
234,794 
1,608,598 
1,019,581 
19,242,04628 
19,242,04628 
15,558,60729 
15,556,29429 
12,005 
12,005 
28,800 
28,800 
21,500 
107,720 
23,000 159,000 
19,547 16,413 
26,500 
172,755 
Approp. 33,130,000 5,784,480 3,600,000 291,000 
Cost 33,078,782 5,866,394 2,658,965 971,353 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
80,500 410,700 623,500 
75,849 405,951 474,474 
50,000 
584 
-8,000 
45,632 9,066 
82,300 107,000 142,700 221,600 
82,210 100,028 115,732 246,991 
25,000 255,000 
24,904 254,267 
9,025 
9,874 
416,000 509,000 531,480 537,698 
407,342 507,201 472,734 607,162 
17,000 
16,150 
33,000 
32,323 
450,000 
96,831 354,286 
778,24530 
777,90230 
91,572,089 
91,274,607 
1,114,700 
956,274 
3,131,94431 
3,128,69731 
32,038,22532 
32,038,22532 
1,369,991 
1,360,791 
4,013,12333 
4,013,12333 
5,974,67834 
5,969,93634 
14,567,06235 
14,566,65235 
37-29

TABLE 37-A 
(Continued) 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
COST AND FINANCIAL STATEMENT 
See 
Section 
In Text Project 
35. Elk Creek Lake, 
Rogue River Basin, 
OR 
36. Fall Creek Lake, OR 
37. Fern Ridge Lake, OR 
42. Lower Columbia 
River Basin Bank 
Protection, OR & WA 
43. Mt. St. Helens and 
Vicinity, WA 
44. Scappoose Drainage 
District, OR 
46. Trask River 
Tillamook County, 
OR 
47. Tualatin, OR 
48. Wahkiakum County 
Consolidated Diking 
District No. 1, WA 
50. Willamette River 
Basin Bank Protection, 
OR 
51. Bonneville Lock and 
Dam-Lake Bonneville, 
OR and WA 
52. Cougar Lake, OR 
Funding 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Total Cost to 
FY 80 FY 81 FY 82 FY 83 Sep. 30, 1983 
202,000 
202,962 
24,450 
87,739 
14 
4,084 
491,000 
478,862 
4,786 
3,140 
669,000 
479,303 
1,035,000 
979,961 
1,659 
23,471 
250,000 
194,681 
172,550 
179,958 
75,000 
84,498 
148,336,000 
148,464,079 
5,103,000 
5,293,379 
-59,251 
106,449 
526,000 
424,205 
251,000 
247,184 
8,550 
23,072 
916 
261,000 
297,580 
10,000 
12,817 
519,000 
705,536 
810,000 
721,022 
- 
50,000 
8,759 
15,000 
8,842 
- 
36,201 
1,935,000 
1,931,497 
93,000 
87,657 
84,232,000 
84,275,102 
5,560,000 
5,207,930 
12,353 
508,000 
591,598 
260,500 
225,543 
1,495,000 
1,460,877 
14 
308,000 
261,448 
307,200 
342,935 
1,350,000 
1,389,366 
241,000 
296,904 
171,983 16,958 
510,700 905,000 
423,165 961,183 
550,000 1,700,000 
690,173 1,710,021 
- 15,730,000 
- 7,557,368 
- -1,000 
26,867 15,304 
2,073 120,000 
5,266 106,136 
35,000 1,200,000 
31,341 1,200,860 
300,000 -1,000 
317,775 5,889 
1,150,000 1,050,000 
1,054,893 1,086,098 
50,000 160,000 
43,024 165,055 
25,417,000 21,456,000 
25,151,114 21,390,863 
6,440,800 7,350,600 
5,652,065 8,369,863 
-12 15,000 
86 8,233 
555,700 682,000 
523,511 716,706 
3,344,174 
3,340,519 
11,863,079 
11,837,610 
22,118,26436 
22,118,26436 
3,286,365 
3,284,936 
8,526,93537 
8,526,85937 
7,638,93338 
6,642,20038 
14,124,745 
14,113,229 
15,730,000 
7,557,368 
3,991,55839 
3,972,62539 
137,073 
120,244 
1,235,000 
1,232,201 
5,289,833 
5,286,028 
22,597,31640 
22,534,12240 
3,210,944 
3,203,578 
708,740,60441 
708,313,34141 
98,443,20742 
98,150,70842 
58,636,39343 
58,629,62643 
6,798,816 
6,781,519 
37-30

PORTLAND, OREGON DISTRICT 
TABLE 37-A 
(Continued) 
COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
In Text Project Funding FY 80 FY 81 FY 82 FY 83 Sep. 30, 1983 
53. Detroit Lake, OR 
54. Green Peter-Foster 
Lakes, OR 
55. Hills Creek Lake, 
OR 
56. John Day Lock and 
Dam-Lake Umatilla, 
OR and WA 
57. Lookout Point 
Lake, OR 
58. Lost Creek Lake, 
Rogue River 
Basin, OR 
59. The Dalles Lock and 
Dam-Lake Celilo, 
WA and OR 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Minor 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
942,500 1,190,000 1,206,600 1,232,000 
971,951 1,183,361 1,142,679 1,312,198 
1,185,000 1,547,500 1,310,800 1,423,000 
1,187,043 1,501,227 1,236,338 1,550,143 
354,500 360,000 510,600 693,900 
355,031 320,090 447,630 4,726,170 
62,729,698 
62,729,698 
19,204,767 
19,201,538 
363,086 
363,086 
84,005,78844 
84,005,7884 
14,860,984 
14,852,492 
45,700,619 
45,700,619 
5,525,267 
441,000 1,009,000 2,143,000 1,298,000 484,144,24645 
272,902 1,252,292 1,737,709 1,597,688 484,023,77845 
7,740,000 6,199,500 7,795,000 9,496,100 
5,664,016 7,573,634 7,056,756 10,637,483 
2,255,000 4,300,000 645,000 
2,207,522 4,339,347 502,806 
10,000 
9,968 
-45,000 
53,108 
32 - 
1,798,000 1,746,000 1,911,900 2,092,100 
1,769,206 1,695,300 1,697,620 2,356,652 
655,000 
980,866 
-8,550 
-218,984 
- 250,000 
85,018 537,648 
1,443,500 1,908,000 1,620,000 20,092,300 
1,409,880 1,722,303 1,761,302 2,157,181 
1,976,000 -85,480 
1,636,272 254,888 301 
63,870,28546 
63,348,57346 
7,155,000 
7,102,783 
88,238,39547 
88,238,39547 
27,253,550 
27,206,974 
136,113,450 
135,877,411 
9,738,800 
9,720,877 
- 301,064,28848 
- 301,064,28848 
4,484,000 5,317,000 4,196,000 5,120,000 
4,374,992 4,877,000 4,151,104 5,763,701 
60,386,54849 
60,306,50249 
1. Excludes $17,742 contributed funds for new work. 
2. Includes $1,529,413 for previous project. 
3. Includes $150,955 allotted from deferred maintenance 
funds, Code 700, $62,296 for public works accelerated program 
repair, and $1,214,865 for previous project. Excludes 
$24,320 expended from contributed funds prior to 1964. 
4. Excludes $31,636 contributed by city of Astoria and 
Bumble Bee Sea Foods, Astoria, Oregon (not part of regular 
project.) Includes $223,026 expended from contributed funds 
prior to 1964 and $428,137 contributed by Port of Portland 
and $14,792 by Port of Vancouver. 
5. Includes $84,930 rehabilitation funds. 
37-31 
1

TABLE 37-A 
(Continued) 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
COST AND FINANCIAL STATEMENT 
6. Includes $1,986,253 for previous project and $608,111 
allotted and $607,474 expended under Code 710, recreation 
facilities at completed project. Excludes $500,000 contributed 
funds. 
7. Includes $2,186,000 for previous project and $1,188,625 
under deferred maintenance, Code 700. 
8. Includes funds under Code 721 (small authorized projects) 
$30,393 Entrance to Oregon Slough; $161,897 Camas- 
Washougal Turning Basin; $227,908 Hood River Small Boat 
Basin; $157,470 Bingen, Wash., Barge Channel; and $140,619 
The Dalles Small Boat Basin. 
9. Includes $2,033,408 under Code 700 (Deferred Maintenance). 
10. Includes $802,096 for previous project. Excludes contributed 
funds. 
11. Includes $178,801 for previous project and $1,444,640 
under Code 700, Deferred Maintenance. Excludes $8,387 
contributed funds. 
12. Excludes $80,000 (other funds) contributed for new 
work by Port of Coos Bay to cover additional cost of disposing 
of dredge spoils in Coos Bay, OR; includes $8,000 for 
previous project. 
13. Includes $340,726 for previous project. Excludes 
$72,891 contributed funds. Includes $36,000 under Code 711. 
14. Includes $41,467 for previous project and $78,500 
under Code 700, Deferred Maintenance. 
15. Excludes $304,826 contributed funds. 
16. Excludes $9,900 contributed funds. 
17. Excludes $13,779 (other funds) contributed for additional 
landfill and extension of drainage lines. 
18. Includes $20,750, Wedderburn Study Funds. 
19. Includes $151,701 for previous project. Excludes 
$322,532 expended from contributed funds. 
20. Includes $10,611 for previous project and $188,000 
under Code 700, Deferred Maintenance. 
21. Includes $77,209 for previous project and $57,767 
under Code 720 (Small Authorized Projects) Garibaldi Boat 
Basin. Excludes $592,622 contributed funds and $300,000 
channel dredging by local interest. Includes $324,855 allotted 
and $322,855 expended for AE&D. 
22. Includes $71,498 for previous project. Excludes $6,450 
expended from contributed funds. 
23. Includes $39,242 for previous project and $58,824 
under Code 720 (Small Authorized Projects) Winchester Bay 
and Schofield River, OR. Excludes $267,500 contributed 
funds. 
24. Includes $247,748 for previous project. Excludes 
$484,900 Emergency Relief Administration flood control 
funds for bank protection. 
25. Includes $51,500 deferred maintenance funds Code 
700, and $35,935 for Public Works Acceleration program 
repair. In addition $7,500 for maintenance from contributed 
funds and $246,637 on operating and care of improvements 
under provisions of permanent indefinite appropriation. 
26. Excludes $300,000 contributed funds. 
27. Includes $452,110 on operation and care from permanent 
indefinite appropriation and $150,000 under maintenance 
and operation of dams and other improvements of 
navigable waters. 
28. Includes $707,313 for previous project and $170,000 
appropriated from public works acceleration program for 
north jetty rehabilitation. 
29. Includes $6,026 for previous project. 
30. Excludes $3,000 contributed funds. 
31. Includes $274,578 for previous project. 
32. Includes $96,000 pro rata share of site selection costs 
in lieu of Quartz Creek Lake. 
33. Includes $1,639,828 allotted and expended under 
Code 711, recreation facilites at completed project. 
34. Includes $147,878 special recreation use fees. 
35. Includes $1,037,590 allotted and $1,037,180 expended 
under Code 711, recreation facilities at completed project. 
36. Includes $259,650, Code 711, recreation facilities at 
completed project. Includes $766,614 allotted and expended 
under Code 713. 
37. Includes $464,029 allotted; $463,953 expended, Code 
711, $2,421,978 Code 712, and $1,008,666 under Code 713, 
recreation facilities at completed projects and $136,482 
allotted under 721 (small authorized project) reservoir modification. 
Excludes $2,100 (other funds contributed). 
38. Includes $9,750 allotted under Code 700, deferred 
maintenance. 
39. Includes $424,310 for previous project. 
40. Excludes $93,733 contributed funds. 
41. Includes $12,200,000 Public Works Administration 
funds, $20,240,700 National Recovery Act funds, $27,195,400 
modification for peaking funds, $436,457 code 711, recreation 
facilities at completed project funds and $597,863,352 
allotted and $597,441,592 expended second powerhouse 
funds; $6,000 allotted and $497 expended, Power Units 
funds. 
42. Includes $540,000 deferred maintenance funds, Code 
700 and $1,620,448 maintenance and operation of dams and 
other improvements of navigable waters. 
43. Includes $96,000 pro rata share of site selection in 
lieu of Quartz Creek Lake. Includes $1,789,988 allotted and 
$1,783,221 expended, for Strube Lake and Cougar Additional 
Unit. 
44. Includes $113,000 pro rata share of site selection 
costs in lieu of Sweet Home Lake. 
45. Includes $25,984 allotted amd $25,934 expended 
under Code 713, recreation facilities at completed projects. 
46. Includes $1,361,900 for O&M and fish evaluation of 
Spring Creek Hatchery (funds revoked and paid to USFWS 
at OCE level, but a cost to project); includes $413,800 special 
recreation use fees. Includes $861,738 allotted under maintenance 
and operation of dams and other improvements of 
navigable waters. 
47. Includes $457,611 allotted and expended under Code 
713, recreation facilities at completed project. 
48. Includes $985,318 Code 712, $138,682 Code 711, 
$16,747 Code 713, recreation facilities at completed project, 
and $52,997,220 allotted and expended additional units 15- 
22 funds. 
49. Includes $569,363 under maintenance and operation 
of dams and other improvements of navigable waters. 
37-32

TABLE 37-B 
PORTLAND, OREGON DISTRICT 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
1. BANDON SMALL BOAT BASIN. 
July 14, 1960 
July 14, 1960 
3. 
Mar. 2, 1945 
Oct. 27, 1965 
Dec. 4, 1981 
4. 
Feb. 27, 1911 
July 25, 1912 
July 27, 1916 
Aug. 8, 1917 
Sep. 22, 1922 
Mar. 4, 19232 
Mar. 3, 1925 
Mar. 3, 1927 
July 3, 1930 
Sep. 6, 19333 
Aug. 30, 1935 
COQUILLE, OR 
A breakwater 413 feet in length, an entrance 
channel 100 feet wide, 250 feet long and 13 feet 
deep, an access channel 50 feet wide, 500 feet long, 
and 13 feet deep. 
CHARSLESTON CHANNEL, COOS BAY, OR 
A channel 150 feet wide, 6,800 feet long with depths 
between 16 to 17 feet. 
CHETCO RIVER, OR 
To provide for the stabilization of the channel, 
by constructing jetties and dredging. 
Modification of channel entrance and channel 
improvements. 
Deepen channel 2 feet to 16 feet, extend the existing 
jetty system 750 feet for the North, and 1,250 feet 
for the South jetty. 
COLUMBIA AND LOWER WILLAMETTE 
RIVERS BELOW VANCOUVER, WA AND 
PORTLAND, OR 
2 pipeline dredges and accessories. 
Increasing main channel to 30 feet. 
Consolidating improvement below Portland, OR, and 
between Vancouver, WA, and mouth of Willamette. 
For the Cathlamet channel. 
Construct an additional dredge (dredge was not 
built) and accessories for better maintenance, and 
construct contraction works. 
Channel from deep water in Willamette Slough to 
deep water in Columbia River. 
Depth of 25 feet and width of 300 feet from mouth of 
Willamette River to Vancouver, WA. 
Closing east channel at Swan Island in Willamette 
River on condition that main channel to be opened 
to project dimensions on west side of island by Port 
of Portland. 
For a 35-foot channel 500 feet wide from Portland to 
the sea. 
A channel 28 feet deep and 300 feet wide from mouth 
of Willamette River to Vancouver, with 2 turning 
basin, each generally 28 feet deep by 800 feet wide 
by 2,000 feet long. 
A channel in Columbia River from mouth of Willamette 
to interstate highway bridge at Vancouver, 
WA, 30 feet deep and 300 feet wide, with 2 turning 
basins at Vancouver. 
Section 107, P.L. 86-645, 
Approved by Chief of 
Engineers Nov. 18,1981 
Section 107, P.L. 86-645 
Authorized by Chief of 
Engineers April 8, 1983 
H. Doc. 817, 77th Cong., 
2d Sess. 
S. Doc. 21, 89th Cong., 
1st Sess. 
S. Doc. 10, 96th Cong., 
1st Sess. 
H. Doc. 1278, 61st Cong., 
3d Sess.1 
H. Doc. 1278, 61st Cong., 
3d Sess.' 
No Prior Report. 
H. Doc. 120, 63d Cong., 
1st Sess.' 
H. Doc. 1009, 66th Cong., 
3d Sess. 
H. Doc. 156, 67th Cong., 
2d Sess. 
H. Doc. 126, 68th Cong., 
1st Sess. 
Rivers and Harbors 
Committee Doc. 10, 
69th Cong., 2d Sess. 
H. Doc. 195, 70th Cong., 
1st Sess. and Rivers 
and Harbors Committee 
Doc. 8, 71st Cong., 
1st Sess.' 
H. Doc. 249, 72d Cong., 
2d Sess.' 
Rivers and Harbors 
Committee Doc. 1, 
74th Cong., 1st Sess. 
37-33

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 37-B 
(Continued) 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Aug. 30, 1935 
Aug. 30, 1935 
Aug. 26, 1937 
Aug. 26, 1937 
Mar. 2, 1945 
Mar. 2, 1945 
July 24, 1946 
Oct. 23, 1962 
Oct. 23, 1962 
Dec. 11, 1933 
Aug. 30, 1935 
Mar. 2, 1945 
May 17, 1950 
6. 
June 20, 1938 
Sep. 3, 1954 
7. 
Mar. 3, 1905 
Sep. 3, 1954 
Dec. 22, 1944 
as amended 
July 30, 1983 
Maintenance of not to exceed 35-foot depth at low 
water in Portland Harbor and Willamette River between 
its mouth and Broadway Bridge at Portland. 
Auxiliary channels, 30 feet deep, 300 feet and 500 
feet at St. Helens. 
Extension of lower turning basin at Vancouver, WA, 
1,000 feet downstream. 
An auxiliary channel 24 feet deep and 200 feet wide 
along waterfront at Rainier, OR. 
Improvement of old mouth of Cowlitz River. 
An auxiliary channel in vicinity of Longview, WA. 
A small-boat mooring basin at Astoria, OR. 
A channel 35 feet deep and 500 feet wide from mouth 
of Willamette River to interstate highway bridge at 
Vancouver, WA, with 2 turning basins of same 
depth. 
A channel 40 feet deep and 600 feet wide from Vancouver, 
WA, to mouth of Columbia River; a turning 
basin at Vancouver, WA, a turning basin at Longview, 
WA, and a channel 40 feet deep in Willamette 
River from mouth to Broadway Bridge which 
encompasses Portland Harbor area. 
COLUMBIA RIVER AT BAKER BAY, WA 
Main channel. 
Main channel. 
West channel 8 feet deep. 
West channel 10 feet deep and mooring basin with 
protecting breakwaters. 
COLUMBIA RIVER BETWEEN CHINOOK, WA 
AND HEAD OF SAND ISLAND 
Channel 8 feet deep. 
Channel 10 feet deep and mooring basin. 
COLUMBIA RIVER AT THE MOUTH, 
OR AND WA 
Extend South Jetty and construct North Jetty and 
dredging. 
Bar channel of 48-foot depth and spur jetty on north 
shore.9 
Construction, operation, and maintenance of recreation 
facilities. 
Deepening the northermost 2000 feet of the channel 
cross section to 55 feet. 
Rivers and Harbors 
Committee Doc. 6 
73d Cong., 1st Sess. 1 
H. Doc. 235, 72d Cong., 
1st Sess.' 
Rivers and Harbors 
Committee D)oc. 81, 
74th Cong., 2d Sess.' 
H. D)oc. 203, 75th Cong., 
1st Sess.' 
H. Doc. 341, 77th Cong., 
1st Sess.' 
H. Doc. 630, 77th Cong., 
2d Sess.' 
H. Doc. 692, 79th Cong., 
2d Sess.' 
H. Doc. 203, 87th Cong., 
1st Sess. 
H. )oc. 452, 87th Cong., 
2d Sess.' 
Public Works 
Administration 
H. Doc. 44, 73d Cong., 
1st Sess. 
H. Doc. 443, 76th Cong., 
1st Sess. 
S. Doc. 95, 81st Cong., 
1st Sess. 
Rivers and Harbors 
Committee Doc. 50, 
75th Cong., 2d Sess. 
S. Doc. 8, 83d Cong., 
1st Sess. 
H. Doc. 94, 56th Cong., 
1st Sess. 
H. Doc. 249, 83d Cong., 
2d Sess.' 
Sec. 4, Flood Control 
Act of 1944 
P.L. 98-63 
37-34 
5.

TABLE 37-B 
(Continued) 
PORTLAND, OREGON DISTRICT 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Aug. 26, 1937 
Mar. 2, 1945 
July 24, 1946 
July 24, 1946 
July 24, 1946 
July 24, 1946 
June 25, 1910 
Mar. 2, 1919 
Sep. 22, 1922 
Jan. 21, 1927 
July 3, 1930 
Aug. 30, 1935 
July 24, 1946 
June 30, 1948 
Dec. 31, 1970 
June 3, 1896 
June 30, 1948 
June 25, 1910 
Mar. 2, 1919 
7. COLUMBIA RIVER, BETWEEN 
VANCOUVER, WA, AND THE DALLES, OR 
Construct a channel 27 feet deep by 300 feet from 
Vancouver, WA, to Bonneville, OR. 
Construct Camas-Washougal turning basin. 
Construct a channel 27 feet deep by 300 feet wide 
from Bonneville, OR, to The Dalles, OR. 
Construct a boat basin at Hood River, OR, 10 feet 
deep, 500 feet wide, by 1,300 feet long. 
Construct a barge channel at Bingen, WA, 10 feet 
deep, 200 feet wide, by 1 mile long, and an access 
channel 7 feet deep, 100 feet wide, by 1,000 feet long 
to natural mooring basin. 
Construct The D1)alles Harbor 8 feet deep, 400 feet 
wide by 800 feet long. 
COOS BAY, OR 
Dredging the Ocean Bar Channel. 
A channel 22 feet deep to Smith's Mill. 
Restore North Jetty 9,600 feet long, construct a 
South Jetty about 3,900 feet long, extend 22-foot 
bay channel from Smith's Mill to Millington. 
Extend jetties to such lengths as may be practicable 
within estimate of total cost of jetties, $3,250,000 as 
given in H. Doc. 150, 67th Cong. 
A channel 24 feet deep and 300 feet wide, through 
Pigeon Point Reef, following a location along 
westerly side of bay. 
For 24-foot channel from Pigeon Point Reef to 
Smith's Mill and a turning basin above Marshfield. 
Increased dimensions of channel across bar and to 
Isthmus Slough and turning basin opposite Coalbank 
Slough and at city of North Bend; anchorage 
basins at mile 3.5 and near mile 7. 
A mooring basin and connecting channel at 
Charleston. 
Increase dimensions to provide for bar channel 45 
feet deep, inner channel 35 feet deep to mile 15, 
and deepening and widening existing turning 
basins and anchorage area. 
COOS AND MILLICOMA RIVERS, OR 
Dredging channel from mouth to head of navigation. 
For a 5 ft. depth from mouth to head of navigation 
on the Millicoma River and South Fork. Except on 
South Fork above M. 14 where 3 ft. will suffice. 
COQUILLE RIVER, OR 
Dredging shoals between mouth and Riverton, and 
removing obstruction between mouth of North Fork 
and Brandon 
For a 13-foot channel from ocean to Bandon 
37-35 
H. Committee Doc. 94, 
74th Cong., 2d Sess. 1 
H. Doc. 218, 76th Cong., 
1st Sess. 
H. Doc. 704, 79th Cong., 
2d Sess. 
H. Doc. 704, 79th Cong., 
2d Sess. 
H. Doc. 704, 79th Cong., 
2d Sess. 
S. Doc. 89, 79th Cong., 
1st Sess.' 
H. Doc. 958, 60th Cong., 
1st Sess. 
H. Doc. 325, 65th Cong., 
1st Sess. 
H. Doc. 150, 67th Cong., 
2d Sess. 
H. Doc. 320, 69th Cong., 
1st Sess. 
H. Doc. 110, 70th Cong., 
1st Sess.' 
S. Committee Print, 
73d Cong., 2d Sess.' 
S. Doc. 253, 79th Cong., 
2d Sess. 
H. Doc. 646, 80th Cong., 
2nd Sess. 
H. Doc. 151, 91st Cong., 
2d Sess. 
H. Doc. 237, 53rd Cong., 
3d Sess. 
S. Doc. 124, 80th Cong., 
2d Sess. 
H. Dco. 673, 61st Cong., 
2d Sess. 
H.Doc. 207, 65th Cong., 
1st Sess. 
9. 
10. 
11.

TABLE 37-B 
(Cnntinued) 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
July 3, 1930 
Aug. 30, 1935 
Mar. 2, 1945 
Dec. 22, 1944 
as amended 
Aug, 26, 1937 
Mar. 2, 1945 
July 3, 1930 
July 25, 1912 
Oct. 27, 1965 
Dec. 31, 1970 
Sep. 3, 1954 
June 25, 1910 
Mar. 3, 1925 
July 3, 1958 
Oct. 22, 1976 
Oct. 1, 1980 
Mar. 2, 1919 
July 3, 1930 
Deepen channel to 16 feet between sea and eastern 
end of North Jetty. 
Present project depth between sea and eastern end of 
North Jetty. 
For 13-foot depth from sea to a point 1 mile above 
Coquille River Lighthouse and snagging to State 
Highway Bridge. 
Construction, operation, and maintenance of 
recreation facilities. 
DEPOE BAY, OR 
Construction of inner basin 375 feet long, 125 feet 
wide and 5 feet deep, with entrance channel of same 
depth and 50 feet wide. 
Construction of inner basin 750 feet long, 390 feet 
wide and 8 feet deep, with entrance channel at same 
depth and 30 feet wide. 
LAKE RIVER, WA 
Construction of channel 6 feet deep and 110 feet wide 
from mouth to Ridgefield. 
H. Doc. 186, 70th Cong., 
1st Sess. 1 
S. Committee Print, 
74th Cong., 1st Sess. 
H. Doc. 672, 76th Cong., 
2d Sess.1 
Sec. 4, Flood Control 
Act of 1944 
H. Doc. 202, 75th Cong., 
1st Sess. 
H. Doc. 350, 77th Cong., 
1st Sess. 
H. Doc. 2, 69th 
Cong., 1st Sess. 
NEHALEM BAY, OR 
Two rubber-stone jetties. H. Doc. 623, 62d Cong., 
2d Sess. 
PORT ORFORD, OR 
Extension of existing breakwater by 550 feet. 
Dredging of turning basin 340 feet long, 100 feet 
wide, 16 feet deep. 
ROGUE RIVER HARBOR AT GOLD 
BEACH, OR 
Two jetties at entrance and improvement of channel. 
SIUSLAW RIVER, OR 
Extends North Jetty 3,700 feet from old work constructed 
under previous project and provides for 
4,200 foot South Jetty. 
12-foot deep channel. 
18-foot bar channel and 16-foot river channel and a 
600-foot extension of North Jetty. (600-foot 
extension classified deferred.) 
Phase I advance engineering and design for north 
and south jetty extensions. 
Extending north and south jetties about 2,000 and 
2,500 feet, respectively. 
SKAMOKAWA CREEK, WA 
Channel 6.5 feet deep and 75 feet wide, a low water 
between Steamboat and Brooks Slough. 
SKIPANON CHANNEL, OR 
Channel from deep water in Columbia River to railroad 
bridge. 
S. Doc. 62, 88th Cong., 
2d Sess. 
H. Doc. 151, 91st Cong., 
2d Sess. 
S. Doc. 83, 83d Cong., 
2d Sess. 
H. D)oc. 648, 61st Cong., 
2d Sess. 
S. Committee Print, 
Serial, 68th Cong., 
1st Sess. 
H. D)oc. 204, 85th Cong., 
91st Sess.1 
Final Report of Chief 
of Engineers 
P.L. 96-367, 
H. Doc. 63rd Cong., 
1st Sess. 
H. Doc. 278, 70th Cong., 
1st Sess. x 
37-36 
12. 
13. 
15. 
16. 
18. 
19. 
20. 
21.

TABLE 37-B 
(Continued) 
PORTLAND, OREGON DISTRICT 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Aug. 26, 1937 
June 30, 1948 
July 14, 1960 
July 26, 1912 
Mar. 4, 1913 
Mar. 2, 1919 
Mar. 3, 1925 
Mar. 2, 1945 
June 30, 1948 
Sep. 3, 1954 
Oct. 27, 1965 
Sep. 22, 1922 
Jan. 21, 1927 
July 3, 1930 
Aug. 30, 1935 
June 20, 1938 
Mar. 2, 1945 
Mar. 2, 1945 
June 30, 1948 
Sep. 3, 1954 
25. 
June 3, 1896 
22. 
Channel extending upstream from railroad bridge a 
distance of 4,500 feet. 
Mooring basin 12 feet deep at Warrenton. 
SOUTH CHANNEL, GOVERNMENT ISLAND 
OR 
A small boat recreational channel 6 feet deep 
and 100 feet wide between River Mile 111.8 and 
118.4 
TILLAMOOK BAY AND BAR, OR 
Construct North Jetty 5,700 feet long and dredging 
channel 16 feet deep, 200 feet wide, to Bay City. 
Abandon that portion of project above Bay City. 
Abandon Bay City Channel and present project 
dimension of channels and turning basins with 
regulating works as needed.4 
Repair damage and check erosion on Bayocean 
Peninsula caused by storm Jan. 1939. 
Dredging small-boat basin and approach at 
Garibaldi, OR, to depth of 12 feet. 
Closure of breach in Bayocean Peninsula. 
Construct South Jetty, 8,000 feet long. 
UMPQUA RIVER, OR 
North Jetty, 7,500 feet long. 
Present project dimensions of North Jetty and 
dredging ocean bar. 
A short south jetty. 
A full length south jetty and maintenance dredging 
to a 26-foot depth. 
Channel 22 feet deep and 200 feet wide from mouth 
to Reedsport. 
Channel 22 feet deep and 200 feet wide from river 
channel to Gardiner, and turning basin 22 feet 
deep, 500 feet wide and 800 feet long. 
Channel 10 feet deep and 100 feet wide from river 
channel to dock in Winchester Bay with mooring 
and turning basin 10 feet deep, 175 feet wide, and 
300 feet long at inner end. 
Channel 12 feet deep and 100 feet wide from river 
channel to dock in Winchester Bay with mooring 
and turning basin 12 feet deep, 175 feet wide, and 
300 feet long at inner end. 
Channel 12 feet deep, Scholfield River.5 
WILLAMETTE RIVER ABOVE PORTLAND 
AND YAMHILL RIVER, OR 
Improvement of Willamette River above Oregon 
City. 
37-37 
H. Doc. 201, 75th Cong., 
1st Sess.' 
S. Doc. 95, 81st Cong., 
1st Sess. 
Section 107, P.L. 86-645 
Authorized by Chief of 
Engineers July 25, 1983 
H. Doc. 349, 62d Cong., 
2d Sess. 
H. Doc. 760, 65th Cong., 
2d Sess. 
H. Doc. 562, 68th Cong., 
2d Sess. 
S. Doc. 35, 79th Cong., 
1st Sess. 
H. Doc. 650, 80th Cong., 
1st Sess. 
S. Doc. 128, 83d Cong., 
2d Sess.1 
S. Doc. 43, 89th Cong., 
1st Sess.1 
H. Doc. 913, 65th Cong., 
2d Sess. 
H. Doc. 320, 69th Cong., 
1st Sess. 
H. Doc. 317, 70th Cong., 
1st Sess.' 
Rivers and Harbors 
Committee Doc. 9, 
72d Cong., e1sSte ss.' 
S. Doc. 158, 75th Cong., 
3rd Sess.' 
S. Doc. 86, 76th Cong., 
slet Sess.' 
S. Doc. 191, 77th Cong., 
2d Sess.' 
S. Doc. 154, 80th Cong., 
2d Sess. 
S. Doc. 133, 81st Cong., 
2d Sess.' 
H. Doc. 260, 54th Cong., 
1st Sess. (Annual 
Report, 1896, p. 3300) 
23. 
24.

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 37-B 
(Continued) 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
June 3, 1896 
July 25, 1912 
June 26, 19346 
June 28, 1938 
26. 
June 25, 1910 
Aug. 8, 1917 
June 26, 19346 
Mar. 2, 1945 
July 14, 1960 
27. 
28. 
Mar. 2, 1919 
Aug. 26, 1937 
Mar. 2, 1945 
July 24, 1946 
July 3, 1958 
July 14, 1960 
Improvement of Yamhill River by lock and dam 
construction. 
Project modified in 1904 by abandoning 20-mile 
stretch of river between Harrisburg and Eugene as 
unworthy of improvement. 
A 6-foot channel in Willamette River below Oregon 
City. 
Operating and care of lock and dam at Yamhill River 
and provided for with funds from War Department 
appropriations for rivers and harbors. 
Streamflow regulation with controlling depths of 
6 feet to mouth of Santiam River and 5 feet to 
Albany with enlargement of locks at Oregon City.8 
Operation of Yamhill Lock was discountined 
Feb 7, 1954, and the lock and adjacent property 
turned over to Yamhill County Jan 16, 1959. 
WILLAMET'E RIVER AT WILLAMETTE 
FALLS, OR 
For purchase and rehabilitation of system and 
construction of concrete division wall. 
Deepening of locks. 
Operation and care of canal and locks provided 
for with funds from War Department appropriations 
for Rivers and Harbors. 
Construction of New Willamette Falls Locks.8 
WINCHESTER BAY, UMPQUA RIVER, OR 
Channel 16 feet deep, 100 feet wide, changing to 75 
feet wide by 12 feet deep in Winchester Bay; channel 
100 feet wide, 16 feet deep, 4,100 feet long to turning 
basin 160 feet wide, 16 feet deep and 200 feet long in 
west basin. 
YAQUINA BAY AND HARBOR, OR 
Restoration and extension of jetties constructed under 
previous projects, rock removal at entrance, and 
dredging in bay up to railroad terminus at Yaquina. 
Extension of north jetty seaward 1,000 feet. 
26-foot channel of suitable width across entrance bar, 
so far as rock bottom will allow, a 20-foot channel 
300 feet wide along south side of bay to and including 
a turning basin 22 feet deep, 1,000 feet wide and 1,200 
feet long. 
Construct a small-boat mooring basin at Newport, OR. 
40-foot bar channel and 30-foot river channel 
extension of jetties at entrance. 
A small boat basin, south shore. 
Annual Report, 1895, 
p. 3602 
Annual Report, 1904, 
p. 3529 
H. 1)oc. 438, 62d Cong., 
2d Sess. 
H. D)oc. 554, 75th Congr., 
3d Sess. 
H. Doc. 202, 56th Cong., 
1st Sess. and Annual 
Report, 1900, p. 4374 
H. D)oc. 1060, 62d Cong., 
3rd Sess.' 
H. Doc. 544, 75th Cong.; 
3rd Sess. 
Sec. 107, P.L 86-645 
Approved by Chief of 
Engineers July 6, 1982. 
H. Doc. 109, 65th Cong., 
1st Sess. 
S. Committee Print, 
75th Cong., 1st Sess. 
S. Doc. 119, 77th Cong., 
1st Sess.' 
S. Doc. 246, 79th Cong., 
2d Sess. 
S. D)oc. 8, 85th Cong., 
1st Sess. 
Section 107, P.L. 86-645 
Approved Chief of 
Engineers, Mar. 4, 
1977 
37-38

TABLE 37-B 
(Continued) 
PORTLAND, OREGON DISTRICT 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
29. YAQUINA RIVER. OR 
Mar. 4, 1913 
30. 
Oct. 23, 1962 
Mar. 7, 1974 
31. 
32. 
33. 
34. 
35. 
June 22, 1936 
May 17, 1950 
Mar. 16, 1938 
Dec. 22, 1944 
as amended 
Mar. 16, 1938 
Dec. 22, 1944 
as amended 
Oct. 23, 1962 
Oct. 7, 1970 
May 17, 1950 
Dec. 22, 1944 
as amended 
Mar. 16, 1938 
Oct. 23, 1962 
Dec. 22, 1944 
as amended 
May 17, 1950 
36. 
37. 
41. 
Construction of channel 10 feet deep and generally 150 
feet wide on Yaquina River and 200 feet wide in 
Depoe Creek. 
APPLEGATE LAKE, ROGUE RIVER 
BASIN, OR 
Authorizes a rockfill embankment dam. 
Authorizes construction of project but no operation for 
irrigation until local interests agree to repay cost 
allocated. 
BEAVER DRAINAGE DISTRICT, COLUMBIA 
BASIN, OR 
Improvements to existing levee and additional levee 
and revetment construction. 
BLUE RIVER LAKE, OR 
Authorizes gravel-filled embankment dam. 
COTTAGE GROVE LAKE, OR 
Earthfill dam. 
Construction, operation, and maintenance of recreation 
facilities. 
DORENA LAKE, OR 
Earthfill dam. 
Construction, operation, and maintenance of recreation 
facilities. 
ELK CREEK LAKE, ROGUE RIVER BASIN, OR 
Rock and gravel embankment dam. 
Authorizes construction but not operation for irrigation 
until local interests agree to repay cost allocated. 
FALL CREEK LAKE, OR 
Earth and gravel fill embankment dam. 
Construction, operation, and maintenance of recreation 
facilities. 
FERN RIDGE LAKE, OR 
Earthfill embankment dam. 
Raise height of dam to obtain additional storage. 
Construction, operation, and maintenance of recreation 
facilities. 
LOWER COLUMBIA RIVER BASIN, OR 
AND WA 
Bank protection work, improvements to existing 
projects, and construction of flood control works in 
Lower Columbia River Basin. 
Doc. 579, 62d Cong., 
2d Sess. 
H. Doc. 566, 87th Cong., 
2d Sess. 
P.L. 93-251, 
Act of 1974. 
F.C. Act 1936 
H. Doc. 531, 81st Cong., 
2d Sess. 
H. Doc. 544, 7th Cong., 
3d Sess. 
Sec. 4, Flood Control Act 
of 1944 
H. Doc. 544, 75th Cong., 
3rd Sess. 
Sec. 4, Flood Control 
Act of 1944 
H. Doc. 566, 87th Cong., 
2d Sess. 
P.L 91-439 
H. Doc. 531, 81st Cong., 
2d Sess. 
Sec. 4, Flood Control 
Act of 1944 
H. Doc. 544, 75th Cong., 
3rd Sess. 
H. Doc. 403, 87th Cong., 
2d Sess. 
Sec. 4, Flood Control 
Act of 1944 
H. Doc. 531, 81st Cong., 
2d Sess. 
37-39

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 37-B 
(Continued) 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
May 17, 1950 
July 30, 1983 
LOWER COLUMBIA RIVER BASIN BANK 
PROTECTION, OR AND WA 
Provides bank protection on Columbia River below 
river mile 125 and along principal tributaries. 
MT. ST. HELENS AND VICINITY, WA 
Implement and maintain flood control measures 
on the Cowlitz and Toutle Rivers by dredging 
or other means determined by the Secretary to 
be necessary to assure flood protection for developed 
areas in the vicinity of such rivers against a onehundred-
year flood on the lower Cowlitz River and to 
reduce sedimentation flow and the chance of blockage 
on the Columbia River. 
H. Doc. 531, 81st Cong., 
2d Sess. 
P.L. 98-63 
June 22, 1936 
May 17, 1950 
July 24, 1946 
June 30, 1948 
48. 
May 17, 1950 
49. 
Mar. 16, 1938 
May 17, 1950 
June 22, 1936 
Mar. 16, 1938 
May 17, 1950 
SCAPPOOSE DRAINAGE DISTRICT, OR 
Construction of levee system. 
Raising and strengthening of levee. 
TRASK RIVER, TILLAMOOK COUNTY, OR 
Construction of riprap bank protection. 
TUALATIN, OR 
Deepening an approximately one mile long 
reach of the Tualatin River. 
WAHKIAKUM COUNTY CONSOLIDATED 
DIKING DISTRICT NO. 1, WA 
Raising and strengthening all levees encircling islands. 
Construct drainage canal, tide box and pumping 
plant. 
WiILAMETTrE RIVER BASIN, OR 
Comprehensive plan for flood control, navigation and 
other purposes in Willamette River Basin. 
General improvements. 
WILLAMETTE RIVER BASIN BANK 
PROTECTION, OR 
Bank protection works, with channel clearing. 
Provide additional protection against flooding. 
Addition of 77 locations to scope of projects. 
BONNEVILLE LOCK AND DAM-BONNEVILLE 
LAKE, OR AND WA 
Existing project was originally authorized Sep. 
30, 1933, by Federal Emergency Administration 
of Public Works. 
Existing project authorized by Congress. 
Completion, maintenance, and operation of 
Bonneville Project under direction of Secretary of War 
and supervision of Chief of Engineers, subject to 
F.C. Act 1936 
H. D)oc. 531, 81st Cong., 
2d Sess. 
Section 14, P.L. 79-526 
Authorized by Chief of 
Engineers April 9, 1981 
Section 205, P.L. 80-858 
Authorized by Chief of 
Enginers April 19, 1983 
H. Doc. 531, 81st Cong., 
2d. Sess. 
H. Doc. 544, 75th Cong., 
3d Sess. 
H. Doc. 531, 81st Cong., 
2d Sess. 
F.C. Act 1936 
H. Doc. 544, 75th Cong., 
3d Sess. 
H. Doc. 531, 81st Cong., 
2d Sess. 
S. Committee Print, 73d 
Cong., 2d Sess., (Report 
of Chief of Engineers 
Dated Aug. 21, 1933) 
37-40 
42. 
43. 
44. 
46. 
47. 
.50r 
51. 
Aug. 30, 1935 
Aug. 20, 1937

TABLE 37-B 
(Continued) 
PORTLAND, OREGON DISTRICT 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Mar. 7, 1974 
D)ec. 22, 1944 
as amended 
May 17, 1950 
Sep. 3, 1954 
Oct. 23, 1962 
Mar. 16, 1938 
June 30, 1948 
May 17, 1950 
Sep. 3, 1954 
May 26, 1960 
May 17, 1950 
May 17, 1950 
Mar. 24, 1965 
Dec. 22, 1944 
as amended 
Mar. 16, 1938 
May 17, 1950 
Dec. 22, 1944 
as amended 
Sep. 21, 1962 
Oct. 15, 1966 
59. 
May 17, 1950 
52. 
certain provisions therein relating to powers and 
duties of Bonneville Power 
Administrator. 
Authorizes relocation of town of North Bonneville 
to new town site. 
Construction, operation, and maintenance of 
recreation facilities. 
COUGAR LAKE, OR 
Rockfill dam. 
Addition of Power. 
Strube Lake reregulating dam. 
DETROIT LAKE, OR 
Authorizes concrete gravity structure. 
Addition of power and regulating Big Cliff dam 
with power. 
GREEN PETER-FOSTER LAKES, OR 
Authorized Green-Peter Dam in lieu of originally 
authorized Sweet Home Lake (1938). 
Addition of power at Green-Peter and White Bridge 
Reregulating Dam. 
Changes location of reregulating dam from White 
Bridge location to Foster. 
HILLS CREEK LAKE, OR 
Earth and gravel fill dam. 
JOHN DAY LOCK AND DAM-LAKE 
UMATILLA, OR AND WA 
Multiple-purpose dam, flood control, navigation and 
power. 
John Day waterfowl management area. 
Construction, operation, and maintenance of 
recreation facilities. 
LOOKOUT POINT LAKE, OR 
Earth-and-gravel filled dam. 
Addition of power and authorization of Dexter Lake 
as reregulating dam. 
Construction, operation, and maintenance of 
recreation facilities. 
LOST CREEK LAKE, ROGUE RIVER 
BASIN, OR 
Rock and gravel fill embankment dam, including 
power. 
Authorizes construction of project but not operation 
for irrigation until local interest agree to repay cost 
allocated. 
THE DALLES LOCK AND DAMLAKE 
CELILO, WA AND OR 
Multiple-purpose dam, flood control, navigation and 
power. 
H. Doc. 531, 81st Cong., 
2d Sess. 
37-41 
P.L. 93-251 
Sec. 4, Flood Control 
Act of 1944 
H. DI)oc. 531, 81st Cong., 
2d Sess. 
P.L. 83-780 
P.L. 87-874 
H. Doc. 544, 75th Cong., 
3d Sess. 
P.L. 858, 80th Cong., 
92d Sess. 
H. Doc. 531, 81st Cong., 
2d Sess. 
P.L. 83-780 
F.C. Act 1954 
S. Doc. 104, 86th Cong., 
2d Sess. 
H. Dl)oc. 531, 81st Cong., 
2d Sess. 
H. Doc. 531, 81st Cong., 
2d Sess. 
S. Doc. 28, 89th Cong., 
1st Sess. 
Sec. 4, Flood Control 
Act of 1944 
H. Doc. 544, 75th Cong., 
3d Sess. 
H. Doc. 531, 81st Cong., 
2d Sess. 
Sec. 4, Flood Control 
Act of 1944 
H. Doc. 566, 87th Cong., 
2d Sess. 
P.L. 89-689 
53. 
54. 
55. 
56. 
57. 
58.

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 37-B 
(Continued) 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Dec. 22, 1944 Construction, operation, and maintenance of Sec. 4, Flood Control 
as amended recreation facilities. Act of 1944 
'Contains latest published maps. 
2Public Resolution 105, 67th Cong. 
3Public Works Administration. 
4Includes following work, classified inactive. A channel 
to Hobsonville 200 feet wide and 16 feet deep, with a turning 
basin 500 feet wide at Hobsonville, and regulating works as 
needed. 
5Inactive. 
6Permanent Appropriations Repeal Act. 
7Flood Control Act. 
8Classified deferred. 
9Spur Jetty "B" classified inactive. 
37-42

PORTLAND, OREGON DISTRICT 
TABLE 37-C OTHER AUTHORIZED NAVIGATION PROJECTS 
Project 
Alsea River, OR 
Astoria Turning Basin, OR2 
Bridges, Columbia River, 
Cascade Locks and Hood River, 
OR (Alteration) 
Cathlamet, WA2 
Clatskanie River, OR' 
Cowlitz River, WA 
Cushman-Mapleton Channels 
(Siuslaw River), OR2 
Deep River, WA3 
Depoe Bay, OR2 
Elochoman Slough, WA' 
Grays River, WA3 
Hammond Small Boat Basin, 
OR 2 
Interstate Bridge, Columbia 
River, Portland, OR to 
Vancouver, WA (Alteration) 
Interstate Highway Bridge 
(Barge Channel), OR2 
Lewis River, WA 
Long Tom River, OR 
Mooring for Battleship 
Oregon, OR 
Multnomah Channel, OR' 
Nestucca River, OR 
Oregon Slough (North Portland 
Harbor), OR3 
Salmon River, OR3 
Smith River, OR 
South Slough (Charleston), OR2 
The Cascades Canal, 
Columbia River, OR 1'0� 
The Dalles-Celilo Canal, OR 
and WA 11 
Umatilla Harbor, OR" 
Westport Slough, OR3 
Yaquina Bay and Harbor 
Small Boat Basin, OR2 
Yaquina River, OR 2 
Youngs and Klaskanine 
River, OR 
Youngs Bay and Youngs 
River, OR3 
Status 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Abandoned 
Abandoned 
Abandoned 
Completed 
Completed 
Completed 
Completed 
Completed 
Consti 
8 
Cost to Sep. 30, 1983 
Operation 
and 
ruction Maintenance' 
2,000 - 
70,139 - 
For Last 
Full Report 
See Annual 
Report For 
1977 
1944 
1971 
1969 
1980 
1975 
1963 
1971 
1971 
1941 
1977 
1961 
1963 
1981 
1982 
1963 
1949 
1974 
1970 
1939 
1957 
1952 
1966 
2,000 
9,348 
- 
206,2958 
1,484,54615 
7,080 
54,905 
33,358 
14,757 
1,081,806 
171,467 
19,2404 
277,4367 
329,423 
15,384 
145,588" 
18,641 ' 
2,500 
519,0906 
1,154,162'" 
15,281 
58,13217 
4,000 
25,000 
437,669''� 
6,000 
16,881 
2,145 
143,120 
26,821 
3,903,780 
4,716,205 
16,276 
891,69514 
195,3131'2 
78.582 
'Includes Project Condition Surveys. 
2Authorized by Chief of Engineers (Sec. 107). 
3Channel adequate for present commerce. 
4Includes $15,537 for previous project. 
5Includes $23,489 for previous project. 
6Excludes $75,000 contributed funds. 
7Includes $239,529 for Sec. 107 project. 
"Excludes $42,000 expended from contributed funds. 
9Excludes $19,555 contributed funds and $67,031 (other 
funds) contributed for additional dredging by Port of 
Cathlamet. 
10 Project abandoned due to flooding by Bonneville Dam 
pool. 
"Project abandoned due to flooding by The Dalles Dam 
pool.
12 Excludes $50,565 contributed funds. 
"Project transferred to Portland District from Walla 
Walla District FY 1974 and abandoned due to flooding by 
the John Day Dam pool. 
"4Excludes $969,342 contributed funds. 
"'Includes $48,184 for previous project. 
'6Non-Federal funds, $1,204,100. 
"'Includes $22,252 for previous project. 
'SIncludes $8,098 for previous project. 
' Includes $419,557 for Sec. 107 project. 
37-43 
- 
687,35318 
6,147 
109,410 
501 
235,877 
559,858 
2,833,888 
118833,7,20720 
1979 
1971 
1979 
a - i

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 37-E OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
For Last Cost to Sep. 30,1983 
Full Report Operation 
See Annual and 
Project Status Report For Construction Maintenance 
COLUMBIA RIVER BASIN 
Blind Slough Diking District, 
Clatsop County, OR Completed 1939 163,397- 
Consolidated Diking and 
Improvement District 1, Cowlitz 
County, WA Completed 1941 163,291- 
Deep River Area, Wahkiakum 
County, WA Completed 1942 69,724- 
Deer Island Area, Columbia 
County, OR Completed 1943 574,123- 
Diking District 2, Clatsop 
County, OR Completed 1940 43,150- 
Diking District 5, Clatsop 
County, OR Completed 1940 25,609- 
Diking and Improvement 
District 5, Cowlitz County, WA Completed 1940 161,381- 
Diking District 1 and 3 (Puget 
Island) and Little Island, 
Wahkiakum County, WA Completed 1941 258,795- 
Diking Improvement District 
1, Pacific County, WA Completed 1941 26,810- 
Diking and Improvement 
District 4, Wahkiakum 
County, WA Completed 1951 169,542- 
Drainage District 1, Clatsop 
County, OR Completed 1939 240,939- 
John Day River Area, Clatsop 
County, OR Completed 1942 33,080- 
Karlson Island, Clatsop 
County, OR Completed 1941 25,773- 
Knappa area, Clatsop County, 
OR Completed 1942 18,789- 
Lewis and Clark River Area, 
Clatsop County, OR Completed 1942 158,419- 
Lower Cowlitz River Area, 
Clatsop County, OR Completed 1962 181,652- 
Magruder Drainage District, 
Columbia County, OR Completed 1940 61,186- 
Marshland Drainage District, 
Columbia County, OR Completed 1940 39,475 - 
Midland Drainage District, 
Columbia County, OR Completed 1939 77,7743 - 
Multnomah Drainage District 
1, OR Completed 1951 593,0344 
Peninsula Drainage District 1, 
Multnomah County, OR Completed 1942 211,160 
Peninsula Drainage District 2, 
Multnomah County, OR Completed 1942 241,148 - 
Port of Kalama, WA Completed - 99,844 - 
Rainier Drainage District, 
Columbia County, OR Completed 1942 47,662 
Sauvie Island Areas A and B, 
Multnomah County, OR Completed 1951 1,623,505 
Skamokawa Creek Area, 
Wahkiakum County, WA Completed 1946 178,885- 
37-44

PORTLAND, OREGON DISTRICT 
TABLE 37-E OTHER AUTHORIZED FLOOD 
(Continued) CONTROL PROJECTS 
For Last Cost to Sep. 30, 1983 
Full Report Operation 
See Annual and 
Project Status Report For Construction Maintenance 
Tenasillahe Island, Clatsop 
County, OR Completed 1939 133,778 - 
Upper Grays River Area, WA Completed 1947 61,263 - 
Walluski River, Clatsop 
County, OR Completed 1942 66,932- 
Warrenton Diking District 1, 
Clatsop County, OR Completed 1940 69,503- 
Warrenton Diking District 2, 
Clatsop County, OR Completed 1940 117,143- 
Warrenton Diking District 3, 
Clatsop County, OR Completed 1940 74,596- 
Webb District Improvement 
Co., Columbia County, OR Completed 1940 84,592- 
Westland District Improvement 
Co., Columbia County, 
OR Completed 1940 205,531- 
Westport District, Columbia 
and Clatsop Counties, OR Completed 1943 40,658- 
Woodson Drainage District, 
Columbia County, OR Completed 1940 22,797- 
Youngs River Dikes, Clatsop 
County, OR Completed 1942 248,802 - 
Total Columbia River Basin - 6,613,742 - 
LEWIS RIVER BASIN 
Diking and Improvement 
District 11, Cowlitz County, 
WA Completed 1943 172,521 - 
COWLITZ RIVER BASIN 
Cowlitz County Drainage 
Improvement District 1, WA Completed 1939 42,978- 
Diking Improvement District 
2, Cowlitz County, WA Completed 1940 121,165- 
Diking Improvement District 
13, Cowlitz County, WA Completed 1939 28,592 - 
Total Cowlitz River Basin 192,735 - 
LOWER COLUMBIA 
RIVER BASIN 
Columbia Drainage District 1, 
OR Inactive- - - 
Cowlitz County Consolidated 
Diking Improvement District 
No. 2, WA Completed 1977 1,661,367 
Cowlitz County Diking 
Improvement District 2, WA Completed 1967 363,000 - 
Cowlitz County Diking 
Improvement District 13, WA Completed 1967 65,345 - 
Cowlitz County Diking 
Improvement District 15, WA Completed 1967 304,794 
Cowlitz River, Hopkins Creek, 
WA Completed 236,860 
Deer Island Drainage District, 
OR Inactive - - - 
Hayden Island, OR Inactive 1950 - - 
37-45

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 37-E 
(Continued) 
OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
For Last Cost to Sep. 30, 1983 
Full Report Operation 
See Annual and 
Project Status Report For Construction Maintenance 
Midland Drainage District, OR Completed 1971 304,511- 
Multnomah County Drainage 
District 1, OR 
Peninsula Drainage District 2, 
OR 
Rainier Drainage District, OR 
Sandy Drainage District, OR 
Sauvie Island Drainage 
District, OR 
Vancouver Lake Area, WA 
Wahkiakum Co. Diking 
District 4, WA 
Washougal Area Levees, 
Clark County, WA 
Woodson Drainage District, OR 
Total Lower Columbia River 
Basin 
WILLAMETTE RIVER 
BASIN 
Amazon Creek, OR 
Cascadia Lake, OR 
Gate Creek Lake, OR 
Holley Lake, OR 
Sandy River and Sleepy 
Hollow, OR 1 
Shelton Ditch, OR 
Willamette River Basin 
Channel Clearing and 
Snagging 
Total Willamette River Basin 
ALL OTHER FLOOD 
CONTROL 
Arlington, Alkali Canyon, OR7 
Bear Creek, Medford, OR1 
Beaver Creek Near Tillamook, 
OR2 
Castle Rock, Cowlitz River, WA 
Catching Inlet Drainage 
District, Coos River, OR2 
Chewaucan River, Paisley, OR' 
Clackamas River at Dixon 
Farm Location, OR2 
Days Creek Lake, OR 
(Phase I) 
Depoe Bay, Lincoln County, 
OR' ' 
McKenzie River Near Walterville, 
OR2 
Miami River, OR1 
Mill Four Drainage District, 
Yaquina River, OR 
Molalla River at Milk Creek 
Location, OR2 
Completed 
Active 
Completed 
Completed 
Completed 
Deferred 
Inactive 
Completed 
Completed 
Completed 
Deferred 
Deferred 
Deferred 
Completed 
Inactive 
Inactive 
Abandoned 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Deferred 
Completed 
Completed 
Completed 
Completed 
Completed 
1964 
1961 
1967 
1954 
1966 
1981 
1971 
1973 
1964 
1960 
1976 
1972 
1963 
1967 
1,491,425 
35,265 
593,945 
154,0126 
674,086 
839,391 
48,619 
1,803,488 
162,500 
8,738,608 
1,214,3006 
1,066,114 
840,001 
241,992 
276,692 
39,624 
3,678,723 
23,439 
23,050 
106,198 
104,921 
182,655 
42,761 
70,8458 
1,307,177 
1950 
1967 
1957 
1959 
1952 
1982 
1967 
1948 
1955 
22,963 
148,358 
15,321 
118,433 
55,007 
37-46 
l

PORTLAND, OREGON DISTRICT 
TABLE 37-E 
(Continued) 
OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
For Last Cost to Sep. 30, 1983 
Full Report Operation 
See Annual and 
Project Status Report For Construction Maintenance 
Molalla River at Ressel 
Location, OR2 Completed 1952 55,189- 
Nestucca River, Condor 
Road, OR' Completed- 11,690- 
Nestucca River, Vicinity 
Pacific City, OR' Completed -16,000- 
Pendleton Levees, Umatilla 
River, OR'0 1960 
(a)Riverside Area Units Deferred 9,100- 
(b)State Hospital and City 
Areas (Zone 1) Completed 1959 267,748- 
(c)State Hospital and City 
Areas (Zone 2)2 Completed 1960 161,540- 
Pendleton, Umatilla River, 
OR' � Completed 1939 143,263- 
Reedsport Levees, Umpqua 
River, OR2 Completed 1971 968,7169 - 
Rogue River, OR' Completed - 86,230 - 
Salmon Creek at Oakridge, 
OR 2 Completed 1960 288,447- 
Siuslaw River, Lane County, 
OR ' Completed -215,939- 
Stillwell Drainage District, 
Tillamook Bay, OR 2 Completed 1961 176,351 - 
Sumner Parker Airport, OR' Completed - 92,500 - 
Umpqua River and 
Tributaries, OR Completed 1952 428,881 - 
Umpqua River, Stanfield, OR' Completed - 33,835 - 
Vicinity of Nehalem, Nehalem 
River, OR Completed 1952 45,677- 
Wilson River, Vicinity 
Highway 101, OR' Completed -30,000- 
Total All Other Flood Control 5,252,234 
'Authorized by Chief of Engineers (Sec. 14). 
2Authorized by Chief of Engineers (Sec. 205). 
'Includes $26,241, Emergency Relief Act funds. 
4In addition $25,000 contributed funds expended for 
new work. 
Previous completed project, $138,956; $15,056 engineering 
costs project constructed by local interests. 
I61n addition, $154,751 contributed funds expended for 
new work, $88,784 "Required" and $65,967 "Other". 
7Project transferred from Walla Walla District FY 1974 
and abandoned due to flooding by the John Day Dam pool. 
Includes $3,328 FY 1960 preauthorization costs, Sec. 205, 
P.L. 80-858. See FY 1960 Annual Report, page 1887. 
8In addition $2,520 contributed funds expended for new 
work. 
9Excludes $230,070 contributed funds for new work and 
$31,284 Government furnished sheet steel pile. 
' �Reported by Walla Walla District prior to 1974. 
37-47

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 37-F OTHER AUTHORIZED MULTIPLE PURPOSE 
PROJECTS, INCLUDING POWER 
For Last Cost to Sep. 30, 1983 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Restoration of Indian Fishing Grounds, 
Bonneville, OR Completed 1969 185,000 
TABLE 37-G DEAUTHORIZED PROJECTS 
For Last Contri- 
Full Report Date Federal buted 
See Annual Deauth- Funds Funds 
Project Report For orized Expended Expended 
Area East of Albany, OR - 1977 -- 
Bachelor Island, WA - 1977 -- 
Bear Creek, Long Tom River, OR 1966 1971 4,559- 
Calapooya River, OR 1959 1965 11,595- 
Clatskanie River Area, 
Columbia County, OR 1960 1965 268 - 
Clatskanie Drainage Dist. 1, OR 1964 1978 18,543 - 
Clatsop County Drainage 
District 1, OR 1960 1974 4,472- 
Clatsop County Diking 
District 3, OR 1938 1961 258- 
Clatsop County, Diking 
District 4, OR -1978 - - 
Clatsop County Diking 
District 6, OR 1961 1978 8,824 - 
Columbia Slough, OR 1953 1978 - - 
Coquille River, OR 1948 1953 908 - 
Cowlitz County Consolidated Diking 
Improvement District 1, OR - 1977 - - 
Cowlitz River at Randle, WA 1962 1977 11,095 - 
Coyote and Spencer Creek, 
Long Tom River, OR 1960 1970 6,819 - 
East Muddy and Lake Creek, OR 1959 1970 6,465 - 
Ferguson Creek, 
Long Tom River, OR - 1978 -- 
Flat Creek, Long Tom River, OR - 1977 - - 
Floodwall and Levees at 
Portland, OR - 1977 - - 
John Drainage District, OR 1961 1979 23,754 - 
John Day River, OR 1974 1974 210,220 - 
Kalama River (South Area) 
Levee, Cowlitz County, WA 1969 1978 55,594 - 
Lake River Delta Area, WA - 1977 - - 
Lewis River Area, WA - 1978 - - 
Magruder Drainage District, OR 1940 1974 774 - 
Mud and Basket Slough 
Rickreall Creek, OR 1977 
Peninsula Drainage 
District 1, OR 1942 1977 43,292 - 
Pilot Rock, Birch Creek, OR 1963 1968 4,558 - 
37-48

TABLE 37-G 
(Continued) 
PORTLAND, OREGON DISTRICT 
DEAUTHORIZED PROJECTS 
For Last Contri- 
Full Report Date Federal buted 
See Annual Deauth- Funds Funds 
Project Report For orized Expended Expended 
Prescott Area, Columbia 
County, OR 1941 1978 125- 
Prineville Area, Crooked River 
and Ochoco Creek, OR 1962 1977 11,318 - 
Pudding River, OR 1950 1979 5,000 - 
Skamokawa (Steamboat Slough), WA 1939 1979 - - 
Soap Creek, WA - 1977 - - 
Turner Prairie, Mill Creek, OR - 1978 - - 
Umatilla River (Echo), OR 1960 1964 24,145 - 
Waldo Lake Tunnel, OR - 1958 - - 
West Muddy Creek and 
Mary's River, OR 1962 1970 4,056 - 
Westport Slough, OR 
(Modification for 32-foot channel) 1966 "1977 - - 
Wiley Creek Lake, OR - 1960 112,000 - 
Willamette Falls Fishladder, OR - 1961 - - 
TABLE 37-H COLUMBIA AND LOWER WILLAMETTE RIVER 
BELOW VANCOUVER WA, AND PORTLAND, OR 
TOTAL COST OF EXISTING PROJECT TO SEP. 30, 1983 
(See Section 4 of Text) 
Funds New Work Maintenance Total 
Regular 28,349,304 188,634,820 216,984,124 
Public Works 446,296 14,515 460,811 
Emergency Relief Administration 138,449 98,668 237,117 
Total U.S. 28,934,049 188,748,003 217,682,052 
Contributed Prior to 1964 223,026 24,320 247,346 
Contributed (1975) 35 to 40-foot Channel 442,928 - 442,928 
Total Contributed 665,954 24,320 690,274 
Total All Funds 29,600,003 188,772,323 218,372,326 
37-49

TABLE 37-I 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Navigation Activities Pursuant to Section 107, 
Public Law 86-645 (Preauthorization) 
Study Identification Fiscal Year Costs (1983) 
Columbia River, Ilwaco, WA 26,614 
Port of Camas, Washougal, WA 1,825 
Siuslaw R&B Small Boat Basin, OR 190 
Skamokawa Creek, WA 5,000 
Welcome Slough, Pudget Island, WA 6,200 
Wind River, WA 7,587 
TOTAL $ 47,416 
TABLE 37-J WILLAMETTE RIVER AT 
WILLAMETTE FALLS, OR 
PRINCIPAL FEATURES OF EXISTING CANAL AND LOCKS 
(See Section 26 of Text) 
Usable Lock Dimensions Series of 4 locks, each 175 feet by 37 feet 1 
Lift of Each Lock Lock 1 (Lower), 22.5 feet; Lock 2, 8.7 feet; 
Lock 3, 10.9 feet & Lock 4 (Upper), 8.1 feet 2 
Depth on Miter Sills at Lower Water Lower Lock, 8.4 feet; Upper Lock, 6 feet 
Character of Foundation Rock 
Kind of Dam Fixed3 
Type of Construction Concrete 
Year of Completion 1873; Purchased by United States Apr. 26, 1915 
Cost Unknown; purchase price, $375,000 
1A guard lock 210 by 40 feet, which is used only at higher 
stages of water, is at upper end of canal basin. 
2A concrete division wall, 1,227 feet long, extending 
from Lock 4 to Guard Lock, separates upper basin of canal 
from head race, which formerly led directly from basin and 
supplied water for powerplants operated by Crown Zellerbach 
Corp., and Portland Ry., Light & Power Co., which is 
now being operated by Portland General Electric Co. 
3The dam is owned by private parties. 
37-50

PORTLAND, OREGON DISTRICT 
37-K FLOOD CONTROL RESERVOIR OPERATIONS 
See 
Section Date of Peak Inflow Storage Used 
in Text Project Peak Inflow cu. ft./sec. acre/feet 
30. Applegate Lake, OR December 16, 1982 7,900 10,230 
31. Blue River Lake, OR 
33. Cottage Grove Lake, OR 
52. Cougar Lake, OR 
53 Detroit Lake, OR 
34. Dorena Lake, OR 
36. Fall Creek Lake, OR 
37. Fern Ridge Lake, OR 
54. Foster Lake, OR 
54. Green Peter Lake, OR 
55. Hills Creek Lake, OR 
January 26, 1983 
February 18, 1983 
March 30, 1983 
December 4, 1982 
December 16, 1982 
January 7, 1983 
February 17, 1983 
March 30, 1983 
December 4, 1982 
December 17, 1982 
February 18, 1983 
March 30, 1983 
December 4, 1982 
December 17, 1982 
January 7, 1982 
February 18, 1983 
March 30, 1983 
December 4, 1982 
December 16, 1982 
January 7, 1983 
February 18, 1983 
March 30, 1983 
December 4, 1982 
December 16, 1982 
January 4, 1983 
February 8, 1983 
March 30, 1983 
December 6, 1982 
D)ecember 17, 1982 
January 7, 1983 
February 18, 1983 
March 30, 1983 
December 4, 1982 
December 17, 1982 
January 4, 1983 
February 18, 1983 
March 30, 1983 
DI)ecember 3, 1982 
Jan'iary 7, 1983 
February 18, 1983 
December 4, 1982 
December 16, 1982 
January 7, 1983 
February 18, 1983 
March 30, 1983 
December 4, 1982 
December 17, 1982 
January 7, 1983 
February 17, 1983 
March 30, 1983 
37-51 
6,600 
11,100 
6,970 
6,060 
4,660 
5,720 
5,360 
4,500 
1,600 
3,200 
5,440 
3,650 
6,800 
3,460 
5,190 
6,490 
6,100 
16,900 
13,600 
20,700 
15,900 
14,460 
5,070 
7,990 
3,890 
12,800 
7,900 
4,200 
3,160 
4,250 
7,660 
5,630 
3,210 
8,330 
2,730 
8,660 
5,950 
9,740 
11,900 
10,600 
17,700 
10,600 
20,100 
14,400 
15,430 
7,310 
7,730 
4,490 
13,700 
13,250 
6,990 
13,390 
10,820 
20,610 
10,810 
20,310 
15,710 
7,830 
1,710 
6,110 
12,270 
3,700 
26,050 
7,260 
23,560 
18,790 
13,630 
64,670 
45,040 
112,140 
50,690 
39,550 
6,620 
19,060 
6,360 
31,940 
14,250 
20,190 
17,170 
16,060 
18,960 
9,660 
2,680 
30,430 
3,730 
27,730 
13,320 
1,330 
2,310 
3,620 
64,820 
19,970 
117,440 
41,500 
32,600 
32,220 
14,490 
21,310 
38,930 
24,590

37-K 
(Continued) 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
FLOOD CONTROL RESERVOIR OPERATIONS 
See 
Section Date of Peak Inflow Storage Used 
in Text Project Peak Inflow cu. ft./sec. acre/feet 
57. Lookout Point Lake, OR December 6, 1982 13,100 44,460 
December 17, 1982 13,000 39,600 
January 7, 1983 11,300 33,050 
February 18, 1983 17,700 71,810 
March 30, 1983 10,990 29,310 
58. Lost Creek Lake, OR December 16, 1982 8,090 22,280 
February 18, 1983 10,000 22,270 
March 30, 1983 10,840 20,770 
TABLE 37-L LOWER COLUMBIA RIVER BASIN, OR AND WA 
LEVEES AND IMPROVEMENTS TO EXISTING WORKS 
(See Section 41 of Text) 
Estimated Cost 
of Work 
Location Approved 1983 
Beaver Drainage District, OR $ 2,854,119 
Cowlitz County Diking Improvement District 2, WA 363,000 
Cowlitz County Diking Improvement District 13, WA 65,345 
Cowlitz County Diking Improvement District 15, WA 304,794 
Cowlitz County Consolidated Diking Improvement District 2, WA 1,661,367 
Midland Drainage District, OR 304,511 
Multnomah County Drainage District 1, OR 1,491,425 
Peninsula Drainage District No. 2, OR 3,200,000 
Rainier Drainage District, OR 593,945 
Sandy Drainage District, OR 15,0561 
Sauvie Island Drainage District, OR 674,086 
Scappoose Drainage District, OR 3,567,248 
Wahkiakum County Consolidated Diking District 1, WA 5,289,833 
Woodson Drainage District, OR 162,500 
Total Estimated Cost, Federal Funds $ 20,547,229 
Estimated Non-Federal Cost $ 3,100,000 
Locations deauthorized or reclassified inactive and excluded from above cost estimate: 
Bachelor Island, WA (Deauthorized - 1977) 
Clatskanie Drainage District, OR (Deauthorized - 1978) 
Clatskanie River Area, OR (Deauthorized - 1965) 
Clatsop County Drainage District 1, OR (Deauthorized - 1974) 
Clatsop County Diking District 4, OR (Deauthorized - 1978) 
Clatsop County Diking District 6, OR (Deauthorized - 1978) 
Columbia Drainage District 1, OR (Inactive) 
Cowlitz County Consolidated Diking Improvement District 1, WA (Deauthorized - 1977) 
Deer Island Drainage District, OR (Inactive) 
Hayden Island, OR (Inactive) 
John Drainage District, OR (Deauthorized - 1979) 
Kalama River Levee, WA (Deauthorized - 1978) 
Lake River Delta Area, WA (Deauthorized - 1977) 
Lewis River Area, WA (Deauthorized - 1977) 
Magruder Drainage District, OR (Deauthorized - 1974) 
Peninsula Drainage District 1, OR (Deauthorized - 1977) 
Wahkiakum County Diking District 4, WA (Inactive) 
'Cost is for Engineering only. Project was constructed 
by local interests. 
37-52

TABLE 37-M 
PORTLAND, OREGON DISTRICT 
WILLAMETTE RIVER BASIN 
COMPREHENSIVE PLAN 
(See Section 49 of Text) 
Estimated 
Federal 
Project Authorizing Act Cost (1983) 
Blue River Lake, McKenzie Basin 1 3 
Cascadia Lake, South Santiam River4 s 
Channel Clearing and Snagging on Willamette 
River and Major Tributaries6 
Channel Improvements for Flood Control 
Major Drainage on 16 Streams 
Tributary to Willamette River 1 
Cottage Grove Lake, Coast Fork' 
Cougar Lake, South Fork McKenzie' 3 
Detroit Lake, Including Big Cliff Lake, 
North Santiam River' 
Dorena Lake, Row River' 
Fall Creek Lake, Middle Fork' 
Fern Ridge Lake, Long Tom River' 
Gate Creek Lake, McKenzie Basin3 s 
Green Peter-Foster Lakes, Middle Santiam' 4 
Hills Creek Lake, Middle Fork1' 
Holley Lake, Calapooya River5 
Johnson Creek, Vicinity of Portland, OR 
Lookout Point Lake, Including Dexter Lake, 
Middle Fork' 
Strube Lake & Cougar Additional Unit, 
(South Fork McKenzie)(Modification to 
Cougar Lake) 
Waldo Lake Tunnel and Reregulating Works 
North Fork, Middle Fork, Willamette River 
Willamette River Bank Protection' 
May 17, 1950, H. Doc. 531, 
81st Cong. 
Oct. 23, 1962, H. Doc. 403, 
87th Cong., 2nd Sess. 
May 17, 1950, H. Doc., 531, 
81st Cong., 2d Sess. 
May 17, 1950, H. Doc. 531, 
81st Cong., 2d Sess. 
June 28, 1938, H. Doc. 544, 
75th Cong., 3rd Sess. 
May 17, 1950, H. Doc. 531, 
81st Cong., 2d Sess. and 
Sep. 3, 1954, S. Doc. 131, 
83rd Cong., 2d Sess. 
June 28, 1938, H. Doc. 544, 
75th Cong., 3rd Sess. and 
June 30, 1948, Public Law 
858. 
June 28, 1938, H. Doc. 544, 
75th Cong., 3rd Sess. 
May 17, 1950, H. Doc. 531, 
81st Cong., 2d Sess. 
June 28, 1938, H. Doc. 544, 
75th Cong., 3rd Sess. 
Oct. 23, 1962, H. Doc. 403, 
87th Cong., 2d Sess. 
May 17, 1950, H. Doc. 531, 
81st Cong., 2d Sess. and 
Sep. 3, 1954, S. Doc. 131, 
83rd Cong., 2d Sess. and 
July 14, 1960, S. Doc. 104, 
86th Cong., 2d Seas. 
May 17, 1950, H. Doc. 531, 
81st Cong., 2d Sess. 
May 17, 1950, H. Doc. 531, 
81st Cong., 2d Sess. 
May 17, 1950, H. Doc. 531, 
81st Cong., 2d Sess. 
June 28, 1938, H. Doc. 544, 
75th Cong., 3d Seas. and 
May 17, 1950, H. Doc. 531, 
81st Cong., 2d Sess. 
Oct. 23, 1962, H. Doc. 403, 
87th Cong., 2d Sess. 
May 17, 1950, H. Doc. 5318 
81st Cong., 2d Sess. 
June 22, 1936, Special Report 
Division Engr., June 28, 
1938, H. Doc. 544, 75th 
Cong., 3d Sess., and May 17, 
1950, H. Doc. 531, 81st 
Cong., 2d Sess. 
$ 32,038,2252 
104,000,000 
(1975) 
3,005,000 
(1960) 
1,214,3002 
4,013,1232 9 
56,750,4052 1'4 
62,729,6982 
14,566,6522 9 
22,118,2642 9 
8,526,8592 9 
127,000,000 
(1980) 
84,005,7882 
45,700,6192 
13,300,000 
(1960) 
5,450,000 
(1983) 
88,238,3952 9 
108,000,000 
(1983) 
31,000,000 
(1983) 
37-53

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
1See individual reports for details of the project. 
2Actual cost. 
3For construction in lieu of originally authorized Quartz 
Creek Lake. 
4For construction in lieu of originally authorized Sweet 
Home Lake. 
5Project classified deferred. 
6Project classified inactive. 
TABLE 37-N PRINCIPAL DATA CON 
7Does not include Reclassified Locations. 
8Authorization rescinded August 28, 1958, Public Law 
85-820. 
9Includes cost of Recreation Facilities at Completed 
Projects (710). 
'�Does not include $96,000 pro rata share of site selection 
costs in lieu of Quartz Creek Lake and Strube Lake and 
Cougar additional unit. 
[CERNING NAVIGATION 
LOCK, SPILLWAY DAM, AND POWERPLANT 
Project 
Bonneville Lock and Dam, 
OR and WA-Lake 
Bonneville 
(See Section 51 of Text) 
NAVIGATION LOCK 
Dimensions: 
Clear Width of Chamber 
Greatest Length Available for Full Width 
Lift (Vertical): 
At Extreme Low Water and Normal Pool Level 
At Normal River Stage 
At Extreme High Water 
Depth Over Miter Sills at Adopted Low Water 
Character of Foundation 
Opened to Navigation 
SPILLWAY DAM 
Type of Construction 
Completed 
Capacity 
Elevation of Gate Sills on Crest of Spillway 
Height Above Lowest Foundation 
Length of Dam Proper 
Length of Dam Overall 
Width at Base 
Gate Openings 
Crest Overflow (Above Mean Sea Level) 
Pool Elevation(Normal)(Above Mean Sea Level) 
POWERPLANT 
Length 
Length (Second Powerhouse) 
Width 
Width (Second Powerhouse) 
Height (Roof to Bedrock) 
Height (Roof to Bedrock) (Second Powerhouse) 
Generator (Station Unit) 
Generators 
Generators (Second Powerhouse) 
Fishwater Supply Units (Second Powerhouse) 
Total Rated Capacity 
Speed 
76 Feet 
500 Feet 
66 Feet 
59 Feet 
About 30 Feet 
24.2 Feet 
Andesite 
January 1938 
Concrete Gravity 
1938 
1,600,000 Cubic Feet 
Per Second 
23.3 Feet 
About 170 Feet 
1,090 Feet 
1,230 Feet 
200 Feet 
18 
24 Feet 
72 Feet 
1,027 Feet 
953 
190 Feet 
235 
190 Feet 
200 feet 
1-4,000 kw 
2 @ 43,200 kw each 
8@ 54,000 kw each 
8 @ 66,500 kw each 
2 @ 13,100 kw each 
1,076,600 kw 
75 Revolutions per 
Minute 
37-54 
TABLE 37-M 
(Continued) 
WILLAMETTE RIVER BASIN 
COMPREHENSIVE PLAN 
(See Section 49 of Text) 
I

PORTLAND, OREGON DISTRICT 
TABLE 37-N PRINCIPAL DATA CONCERNING NAVIGATION 
(Continued) LOCK, SPILLWAY DAM, AND POWERPLANT 
Project 
NAVIGATION 
John Day Lock and Dam, 
OR and WA-Lake 
Umatilla (See Section 56 
of Text) 
The Dalles Lock and Dam 
WA and OR-Lake Celilo 
(See Section 59 of Text) 
Clear Width 
Clear Length 
Lift: 
Minimum 
Average 
Maximum 
Minimum Water Depth Over Sills 
Opened to Navigation 
SPILLWAY DAM 
Type of Construction 
Completed 
Maximum Capacity 
Crest Elevation 
Control Gates: 
Type 
Size, Width by Height 
Number 
POWERPLANT 
Length 
Width 
Generating Units: 
Number Installed 
Space for Additional 
Rating, Each 
Total Installed Capacity 
Total Potential Capacity 
Maximum Structural Height 
First Power-On-Line 
IMPOUNDMENT 
Elevations: 
Normal Operating Range 
Maximum 
Flood Control Storage 
Lake Length 
Lake Water Surface Area at 
Elevation 268 
Navigation Channel, Depth by Width 
Length of Shoreline 
NAVIGATION LOCK 
Type 
Lift Normal 
Net Clear Length 
Net Clear Width 
Normal Depth Over Upper Sill 
Minimum Depth Over Lower Sill 
Opened to Navigation 
SPILLWAY DAM 
Type 
Elevation of Crest 
Top of Crest Gates 
Number of Gates 
86 Feet 
669 Feet 
97 Feet 
105 Feet 
113 Feet 
15 Feet 
April 1968 
Concrete Gravity 
March 1968 
2,250,000 cfs 
210 
Tainter 
50 Ft. by 58.5 Ft. 
20 
1,975 Feet 
243 Feet 
16 
4
135,000 kw 
2,160,000 kw 
2,700,000 kw 
235 Feet 
July 1968 
268-257 
276 
500,000 Ac.-Ft. 
76.4 Miles 
55,000 Acres 
15 Ft. by 250 Ft. 
200 Miles 
Single Lift 
87.5 Feet 
675 Feet 
86 Feet 
20 Feet 
15 Feet 
March 17, 1957 
Controlled 
121 Ft. msl 
162 Ft. mal 
23 
37-55

TABLE 37-N 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
PRINCIPAL DATA CONCERNING NAVIGATION 
LOCK, SPILLWAY DAM, AND POWERPLANT 
Project 
50 by 43 Feet 
120 Feet 
2,290,000 cfs 
Size of Gates 
Height (Foundation to Crest) 
Design Flood 
POWERPLANT 
Powerhouse Dimensions 
Generators Main Units 
Generators Main Units 
240 by 2,150 Feet 
14 @ 78,000 kw each 
Additional 8 @ 
86,000 kw each 
2 @ 13,500 kw each 
1,807,000 kw 
2 @ 3,000 kw each 
Fishwater Supply Units 
Total Rated Capacity 
Station Service Units
37-56

SEATTLE, WA, DISTRICT* 
This District comprises Washington State except southern 
and southeastern portions, northern Idaho, and 
northwestern Montana embraced in drainage basins 
tributary to Pacific Ocean south of international boundary 
to Cape Disappointment, and to Columbia River 
above Yakima River, inclusively. 
IMPROVEMENTS 
Navigation 
1. Anacortes Harbor, WA................... 
2. Bellingham Harbor, WA ................ 
3. East Bay Marina, Olympia Harbor, WA.. . 
4. Ediz Hook, WA .......................... 
5. Everett Harbor and Snohomish 
River, WA ............................... 
6. Floating Breakwater Prototype 
Test Program, West Point, Seattle, WA .... 
7. Friday Harbor Marina, WA .............. 
8. Grays Harbor and Chehalis 
River, W A .............................. 
9. Lake Crockett, WA....................... 
10. Lake Washington Ship Canal, WA....... 
11. Navigation Work under Special 
Authorization .......................... 
12. Project Condition Surveys ................ 
13. Puget Sound and its 
Tributary Waters, WA.................... 
14. QuillayuteRiver, WA ................... 
15. Seattle Harbor, WA ................. ..... 
16. Swinomish Channel, WA................. 
17. Tacoma Harbor, WA ..................... 
18. Willapa River and Harbor and 
Naselle River, WA ....................... 
Flood Control 
19. Clark Fork River, Missoula, MT........... 
20. Hoh River, near Forks, WA ............... 
21. Howard A. Hanson Dam, WA ............ 
22. Inspection of Completed Flood 
Control Projects ........................ 
23. Inspection of Non-Federal Levees ......... 
24. Mud Mountain Dam, WA ................ 
25. Placer Creek, ID ........................ 
26. Scheduling Flood Control 
Reservoir Operations ..................... 
27. Stillaguamish River, WA................ 
Page 
38-2 
38-2 
38-2 
32QQ 
Page 
28. Tacoma, Puyallup River, WA ............ 38-9 
29. Wynoochee Lake, WA................... 38-10 
30. Yakima River, Yakima, WA ............. 38-10 
'-" Multiple-Purpose Projects, Including Power 
383 31. Albeni Falls Dam, ID ..................... 
32. Chief Joseph Dam - Rufus Woods 
38-3 Lake, W A .............................. 
38-3 33. Libby DI)am - Lake Koocanusa, MT ........ 
38-4 
38-4 
38-4 
38-5 
38-5 
38-5 
38-6 
38-6 
38-6 
38-7 
38-7 
38-8 
38-8 
38-8 
38-8 
38-8 
38-8 
38-9 
38-9 
38-9 
General Investigations 
34. Surveys ................................ 
35. Collection and Study of 
Basic Data ............................. 
36. Continuation of Planning 
and Engineering........................ 
Tables 
Table 38-A 
Table 38-B 
Table 38-C 
Table 38-E 
Table 38-F 
Table 38-G 
Table 38-H 
Table 38-I 
Table 38-J 
Table 38-K 
Cost & Financial Statement..... 
Authorizing Legislation ....... 
Other Authorized Navigation 
Projects ...................... 
Other Authorized Flood Control 
Projects ...................... 
Other Authorized Multiple 
Purpose Projects, Including 
Power ........................ 
Deauthorized Projects .......... 
Lake Washington Ship Canal, 
WA, Principal Features of Double 
Lock and Dam ................. 
Project Condition Surveys ...... 
Flood Control Activities 
Pursuant to Section 205, Public 
Law 858, 80th Congress ....... 
Emergency Flood Control 
Activities - Public Law 99, 84th 
Congress ..................... 
38-10 
38-10 
38-11 
38-12 
38-12 
38-12 
38-13 
38-18 
38-24 
38-25 
38-29 
38-30 
38-30 
38-31 
38-31 
38-32 
38-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Navigation 
1. ANACORTES HARBOR, WA 
Location. On northern point of Fidalgo Island in 
Puget Sound, 17 miles south of Bellingham, WA, and 64 
miles north of Seattle. The main harbor is on Guemes 
Channel. (See NOAA Survey Chart 18427.) 
Existing project. Channel in Capsante Waterway, 12 
feet deep and 150 to 250 feet wide, between east side of Q 
Avenue and deep water in Fidalgo Bay, a distance of 
2,850 feet; and mooring basin 12 feet deep, 570 feet wide, 
and 960 feet long adjacent to north side of Capsante 
Waterway, protected by two pile breakwaters, each 470 
feet long, east and southeast of basin. Plane of reference 
is mean lower low water. Range between mean lower low 
water and mean higher high water is 8.2 feet. Extreme 
range is about 15.5 feet. Project was completed in July 
1957, excluding the inactive portion and inner portion of 
boat basin. (For further details, see Annual Report for 
1958.) 
Local cooperation. Fully complied with. 
Terminal facilities. There are 24 piers and wharves 
in the Port of Anacortes; 15 on Guemes Channel, 3 on 
Capsante Waterway, and 7 on Fidalgo Bay. Three 
wharves on Guemes Channel are open for public use; of 
these, one is publicly owned and operated and used for 
handling general cargo in foreign and domestic trade. In 
addition, two wharves are used for ferries plying to the 
San Juan Islands and to Vancouver Island, British 
Columbia. Both are publicly owned and operated. Two of 
the wharves on Capsante Waterway and basin are publicly 
owned and operated and used for receiving petroleum 
products, and as a moorage for fishing and pleasure 
craft. All other wharves are used for general industrial 
purposes. In addition, there are two oil-refinery wharves 
located to the south of Capsante Waterway that are 
privately owned and operated and used for handling 
petroleum products in foreign and domestic trade. These 
facilities are considered adequate for existing commerce. 
(See Port Series No. 37 - Ports of Everett, Bellingham, 
Port Angeles, and Anacortes, WA, revised 1976). 
Operations during fiscal year. Maintenance, hired 
labor: Conducted channel condition surveys. 
2. BELLINGHAM HARBOR, WA 
Location. Part of Bellingham Bay, an arm of Puget 
Sound, at Bellingham, in northwestern Washington. (See 
NOAA Survey Chart 18424.) 
Existing project. Channel 30 feet deep in Whatcom 
Creek Waterway from deep water to head of harbor, 363.2 
feet wide to 750 feet from inner end, thence 18 feet deep for 
inner 750 feet; Squalicum Creek Waterway, including 
dredging an entrance channel 200 feet wide and 26 feet 
deep from deep water in the bay to main pierhead line, 
and maintenance of southerly half and westerly end of 
Squalicum Creek basin to 26 feet deep, provided that no 
dredging can be done within 75 feet of wharves, piers, or 
similar structures; and small-boat basin adjacent to 
Squalicum Creek Waterway by construction and maintenance 
of two sections of rubblemound breakwater with 
combined length of 5,400 feet, including maintenance of 
minimum depths of 12 feet in entrance to basin. Plane of 
reference is mean lower low water. Range between mean 
lower low water and mean higher high water is 8.6 feet. 
Extreme range is about 16 feet. Project was completed in 
February 1961. (For further details, see Annual Report for 
1961. For details relating to previous projects, see page 
2006 of Annual Report for 1915 and page 1888 of Annual 
Report for 1938.) 
Local cooperation. Fully complied with. In complying 
with terms of local cooperation, the Port of Bellingham 
expended $2,157,473 for bulkheads, groins, 
dredging, mooring and terminal facilities and utilities, 
and land development. 
Terminal facilities. Of the forty wharves and piers in 
Bellingham Harbor, 9 are on Whatcom Creek Waterway; 
3 on Squalicum Creek Waterway; 3 on I&J Street Waterway; 
and 9 on Bellingham Bay. Two wharves on Whatcom 
Creek Waterway serve general cargo terminals. One 
is publicly owned and operated and is suitable for use by 
ocean-going vessels; the other one is privately owned and 
operated. Also, there is one publicly owned terminal and 
small-boat harbor with 11 wharves handling private 
craft and fishing boats. (See Port Series No. 37- Ports of 
Everett, Bellingham, Port Angeles, and Anacortes, WA, 
revised 1976.) 
Operations during fiscal year. Maintenance, hired 
labor: Conducted channel condition surveys. 
3. EAST BAY MARINA, OLYMPIA HARBOR, WA 
Location. The city of Olympia, capital of the State of 
Washington, is located at the extreme southern end of 
Puget Sound. East Bay is just north of Olympia. (See 
NOAA Survey Charts 18445 and 18456.) 
Existing project. Construction of 700 feet of concrete 
floating breakwater and dredging of the entrance and 
access channels and a turning basin for a new 800-boat 
marina. 
Local cooperation. Fully complied with. Requirements 
are described in full on page 38-3 of FY 1981 
Annual Report. 
Operations during fiscal year. New work, contract: 
Construction of the floating breakwater was completed 
in May 1983. The marina is currently in operation and 
project is physically complete. 
4. EDIZ HOOK, WA 
Location. Ediz Hook and the city of Port Angeles are 
on the Strait of Juan de Fuca in Clallam County, WA, 
about 100 miles northwest of Seattle. (See NOAA Survey 
Chart 18468.) 
Existing project. Provides for about 13,300 lineal feet 
of rock revetment and 3,100 lineal feet of rock blanketing, 
together with initial beach replenishment and annual 
nourishment. Project was completed in October 1978. 
(For further details, see Annual Report for 1979.) 
Local cooperation. Fully complied with. 
Operations during fiscal year. Maintenance, hired 
labor: Condition surveys of revetment and immediate 
offshore area accomplished. 
38-2

SEATTLE, WASHINGTON DISTRICT 
5. EVERETT HARBOR AND SNOHOMISH 
RIVER, WA 
Location. On Port Gardner Bay, at northern end of 
Possession Sound, an arm of Puget Sound at Everett, in 
northwestern Washington; and Snohomish River for 6.3 
miles above mouth. (See NOAA Survey Chart 18443.) 
Existing project. Training dike extending from a 
point opposite 23d Street northward 12,550 feet to outlet 
of Snohomish River, with spur dike extending 400 feet to 
pierhead line from north end of main dike; spur dike 
extending 1,410 feet westward from Preston Point; removal 
of a section of training dike north of Snohomish 
River outlet; channel 150 to 425 feet wide and 15 feet deep 
from deep water in Port Gardner Bay to 14th Street dock; 
thence a settling basin 700 feet wide, 1,200 feet long, and 
20 feet deep, thence a channel 150 feet wide and 8 feet 
deep up river to head of Steamboat Slough, a total distance 
of about 6.3 miles; settling basin within upper 
channel reach about 1 mile long with a capacity of 1 
million cubic yards and maintaining East Waterway to 
30 feet deep. The 1968 modification included raising the 
southerly 4,100 feet of existing training dike, extending 
the training dike 1,500 feet farther south, and constructing 
a breakwater along the south and west sides of the 
existing small-boat basin. Plane of reference is mean 
lower low water. Range between mean lower low water 
and mean higher high water is 11.1 feet. Extreme tidal 
range is about 19 feet. The boat basin breakwater has 
been deleted at the request of the local sponsor, and the 
remainder of the 1968 modification has been deferred 
indefinitely. Project was completed in April 1963, excluding 
the deleted and deferred portions. (For further details, 
see page 1683 of Annual Report for 1963. For details 
relating to previous projects, see page 704 of Annual 
Report for 1905, page 2005 of Annual Report for 1915, and 
page 1883 of Annual Report for 1938.) 
Local cooperation. Fully complied with. Requirements 
are described in full on page 38-3 of FY 1981 
Annual Report. 
Terminal facilities. There are 42 piers and wharves 
in the Port of Everett, 17 in Port Gardner and 25 on the 
Snohomish River. These include: 19 publicly owned terminals 
with 4 berths handling ocean-going vessels and 1 
publicly owned terminal and small-boat basin handling 
fishing and pleasure craft. The rest are at Bayside and 
the Snohomish River. 
Operations during fiscal year. Maintenance, hired 
labor: Channel condition surveys were conducted throughout 
the year. 
Maintenance, contract: Lower Snohomish River 
channel maintenance dredging contract was 
awarded in August 1983 to dredge 200,000 cubic yards at 
a cost of $365,650. Completion is scheduled for December 
1983 and is 22 percent complete. 
6. FLOATING BREAKWATER PROTOTYPE 
TEST PROGRAM, WEST POINT, 
SEATTLE, WA 
Location. West Point is a point of land located about 
6.8 miles northwest of Elliott Bay in Puget Sound within 
the boundaries of the city of Seattle, WA. The area is well 
suited for the project in that it often experiences waves 
that equal and exceed design waves contemplated at 
most proposed project sites. The site is situated within 
quick and easy access for purposes of maintenance and 
monitoring. (See NOAA Survey Chart 18440.) 
Existing project. Provides for the construction, 
placement, monitoring, and removal of two types of floating 
breakwater at a site with a high occurrence of wave 
attack. The prototype structures built and monitored are 
a concrete box design, 16 feet wide and 150 feet long, with 
a depth of 5 feet and a 3.5-foot draft, and a pipe-tire mat 
design, 45 feet wide and 100 feet long. Information from 
the test program will be used on other Corps of Engineers 
projects throughout the nation to design and build more 
economical and efficient wave protection structures. Test 
program information will also be available to other public 
entities and to the private sector. Construction was 
begun in March 1982. Estimated total cost is $1,800,000, 
Federal funds. 
Local cooperation. None required. 
Operations during fiscal year. New work, contract: 
Field data were collected during numerous winter storms. 
The anchor system and connection system on the concrete 
breakwater were modified and tested. Tests on the 
pipe-tire breakwater were successfully completed in 
August 1983 when it was removed from the test site for 
surplus action. The concrete breakwater will continue to 
be monitored by the University of Washington through 
January 1983, when it will be turned over to the contractor 
who is constructing the Friday Harbor Marina in the 
San Juan Islands, about 60 nautical miles north of Seattle. 
Data analysis is being carried out with the assistance 
of the Coastal Engineering Research Center (CERC), 
and a final report on the test program is scheduled for 
completion in September 1984. 
7. FRIDAY HARBOR MARINA, WA 
Location. Friday Harbor is located on the eastern 
shore of San Juan Island on the inland waters of northwestern 
Washington, about 28 nautical miles east of Victoria, 
British Columbia, and 60 nautical miles north of 
Seattle, WA. San Juan Island is one of over 170 islands in 
the San Juan Archipelago. Friday Harbor is the San 
Juan County seat and a United States Customs Port of 
Entry. (See NOAA Survey Chart 18425.) 
Existing project. Construction of a 1,600-foot breakwater 
seaward of the existing breakwater to protect the 
existing port facilities and to allow the port to provide 294 
additional permanent moorage spaces and 44 additional 
transient spaces. The moorage area would be protected 
by the new concrete floating breakwater. Estimated total 
cost of project is $3,160,000, of which $1,800,000 is Federal 
funds and $1,360,000 is non-Federal funds. 
Local cooperation. Fully complied with. Requirements 
are described in full on page 38-4 of FY 1981 
Annual Report. 
Operations during fiscal year. New work, hired 
labor: Plans and specifications were completed. 
38-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
New work, contract: Breakwater construction contract 
was awarded in June 1983 with completion scheduled for 
June 1984. Breakwater fabrication is underway. 
8. GRAYS HARBOR AND CHEHALIS 
RIVER, WA 
Location. Harbor lies at mouth of Chehalis River, in 
southwestern part of Washington, 45 miles north of 
entrance to Columbia River. Inner portion comprises two 
main channels, the south and the north, connecting harbor 
proper with Chehalis River at Aberdeen. Chehalis 
River rises in southwestern part of Washington about 40 
miles east of Pacific Ocean, flows generally northwesterly 
and empties into eastern part of Grays Harbor. (See 
NOAA Survey Chart 18502.) 
Existing project. Provides for an entrance channel 
across the bar 600 feet wide and 30 feet deep, to be secured 
by a south jetty 13,734 feet long and a north jetty 17,200 
feet long, both at an elevation of 16 feet, and by dredging; 
maintenance of channel 30 feet deep and 350 feet wide 
from deep water in Grays Harbor 14 miles to Cow Point; 
thence 30 feet deep and 200 feet wide, suitably widened at 
bends, to a point 13,700 feet upstream from Union Pacific 
Railroad bridge at Aberdeen, a distance of 4.125 miles; a 
turning basin 30 feet deep, 550 feet wide, and 1,000 feet 
long at upstream end of 30-foot channel near Cosmopolis; 
a channel 14 feet deep and 100 feet wide in South Bay to 
Bay City; three breakwaters at, and maintenance of 
entrance channel to Westhaven Cove; and protection of 
Point Chehalis for an exposed length of about 7,500 feet. 
Plane of reference is mean lower low water. Tidal range 
between mean lower low water and mean higher high 
water is 8.9 feet at Point Chehalis, 10.1 feet at Aberdeen, 
and 8.1 feet at Montesano. Extreme range is 17.5 feet at 
Point Chehalis, 17.8 feet at Aberdeen, and 23.8 feet at 
Montesano (river flood of 1935). Project was completed in 
March 1965 excluding deferred and inactive portions. 
Rehabilitation of 4,000 feet of the south jetty was completed 
in October 1966. (For further details, see Annual 
Report for 1967. For details relating to previous projects, 
see pages 2002-03 of Annual Report for 1915 and page 
1863 of Annual Report for 1938.) 
Local cooperation. Fully complied with. 
Terminal facilities. In Aberdeen, there are 2 terminals 
with 7 berths owned by the Port of Grays Harbor 
handling ocean-going vessels and 10 usable privately 
owned piers and wharves; and 1 each at Markham and 
Cosmopolis, 7 at Hoquiam, 5 private wharves and 1 
Coast Guard station at Westhaven Cove. Of the 22 privately 
owned, 1 is used for the receipt of sand and gravel, 
3 for fish, and 7 for lumber or logs. In addition, there are 8 
log dumps or receiving areas in Grays Harbor. 
Operations during fiscal year. Maintenance, hired 
labor: Channel condition surveys were conducted throughout 
the year. 
Maintenance, contract: Dredging at Cow Point turn 
was completed in November 1982 at a cost of $469,972 
with 154,161 cubic yards of material removed. 
Code 710 Funds. Funds were used to complete construction 
of the handicap access due to a revised estimate 
of that work. 
9. LAKE CROCKETT, WA 
Location. The harbor is on the west side of Whidbey 
Island, about 35 nautical miles north of Seattle, WA. The 
lake lies parallel to Admiralty Bay and is separated from 
it by a narrow strip of gravel beach. (See NOAA Survey 
Chart 18441.) 
Existing project. Provides for a basin in Lake Crockett 
with an area of about 6 acres and 18 feet deep at mean 
lower low water, connected with Admiralty Bay by a 
channel of the same depth and 150 feet wide, protected by 
a breakwater. The diurnal tidal range in Admiralty Bay 
is 8.4 feet and the extreme range is about 16.5 feet. Project 
was completed in January 1948. (For further details, see 
Annual Report for 1948.) Recreational facilities at project 
under cost-sharing agreement with Washington State 
Parks and Recreation Commission include the following 
construction and improvements: Construct a 35-unit 
camping loop and restroom, new boat ramp handling 
facility, breakwater, a restroom in the day-use area and 
porto-potti dumps for boats; and expand day-use facility 
and add riprap at the construction site. 
Local cooperation. None required. 
Terminal facilities. One publicly owned and privately 
operated passenger and automobile ferry landing 
within the dredged basin is open for public use, and is 
adequate for existing commercial traffic. The basin contains 
two publicly owned boat ramps open for public use. 
The ramps are adequate for recreational craft. 
Operations during fiscal year. Maintenance, hired 
labor: Channel condition surveys conducted. 
Code 710 Funds. Funds provided additional riprap at 
the construction site. 
10. LAKE WASHINGTON SHIP CANAL, WA 
Location. Entirely within city of Seattle and extends 
from Puget Sound through Shilshole Bay, Salmon Bay, 
Lake Union, Portage Bay, and Union Bay to deep water 
in Lake Washington. (See NOAA Survey Chart 18447.) 
Existing project. Provides for a double lock and fixed 
dam with gated spillway and necessary accessory works, 
including fishladder, at the Narrows at entrance to Salmon 
Bay, about 1.25 miles from deep water in Puget 
Sound; for a channel 34 feet deep and 300 feet wide from 
Puget Sound to Burlington Northern Railway bridge, 
about 5,500 feet, with a passing basin 34 feet deep and log 
basin 8 feet deep at turn below railway bridge; then 34 
Union and Washington; and for a channel 30 feet deep 
with a width of 100 feet from locks to Lake Union, 200 feet 
thence to Portage Cut, 100 feet through Portage Cut, and 
thence 200 feet wide through Union Bay to Lake 
Washington. Section included in project is about 10 miles 
long. Plane of reference is mean lower low water. 
Extreme tidal range is 19.3 feet. Range between mean 
lower low water and mean higher high water is 11.3 feet, 
and between mean lower low water and extreme low 
water is 4.6 feet. Ordinary fluctuation in upper pool is 
about 22 inches; extreme fluctuation has been 3.6 feet. 
38-4

SEATTLE, WASHINGTON DISTRICT 
Principal features of double lock and dam (structures are 
at Seattle, WA) are set forth in Table 38-H. Project was 
completed in 1934. (For further details, see Annual Report 
for 1935. For details relating to previous projects, see page 
2003 of Annual Report for 1915, and page 1880 of Annual 
Report for 1938.) Estimated Federal cost of major rehabilitation 
is $6,800,000. 
Local cooperation. Fully complied with. 
Terminal facilities. There are 104 wharves and piers 
on Lake Washington Ship Canal and adjacent inland 
waters, including Salmon Bay, Lake Union, Portage 
Bay, and Lake Washington. Of these, 18 are publicly 
owned, 3 of which are privately operated. The other 
wharves include 61 used for building, outfitting, or repair 
of vessels, 6 for handling petroleum products, 38 for various 
industrial purposes, and 7 for mooring and servicing 
pleasure craft. Facilities are considered adequate for 
existing commerce. (See Port Series No. 36--The Port of 
Seattle, Washington - Revised 1975.) 
Operations during fiscal year. Maintenance, hired 
labor: Locks were operated and maintained all year, 
passing 20,000 commercial and 65,000 pleasure vessels, 
and 2,000,000 tons of commerce. Fishladder passed 
500,000 fish and there were more than 800,000 project 
visitors. 
Major Rehabilitation. New work: Contract for 
rehabilitation of three piers is physically complete. Contract, 
in the amount of $3,291,200, for construction of a 
new Emergency Closure System and rehabilitation of 
the downstream guard gate was awarded in January 
1983 and is scheduled for completion in May 1985. Contract, 
in the amount of $614,266, for reconstruction of 
retaining structure in Montlake Cut was awarded in 
June 1983 and is scheduled for completion in January 
1984. 
11. NAVIGATION WORK UNDER SPECIAL 
AUTHORIZATION 
Navigation activities pursuant to Section 107, Public 
Law 86-645 (preauthorization). 
Fiscal year costs for preauthorization studies were: 
Gooseberry Point Small Boat Harbor, Hale Passage, WA, 
$113,999; Sandy Point Harbor, Whatcom County, WA, 
$194,960; Seacrest Small Boat Harbor, WA, $1 (Detailed 
project report terminated). 
Aquatic plant control (Section 302, Public Law 89- 
298): The program consists of control measures for 
selected water bodies currently infested with Eurasian 
watermilfoil and measures to prevent its spread into 
uninfested waters. Operations under the cost-share program 
included mechanical harvesting of 200 acres and 
maintaining 5 acres of fiberglass bottom screens at Lake 
Washington and Lake Sammamish, WA; treating with 
2,4-D/invert 100 acres at Okanogan River, WA, and 15 
acres in the Columbia River; and treating with 2,4- 
D/invert (8 acres) and 2,4-D/polymer (8 acres) at Pend 
Oreille River, WA. The Fiscal Year 1983 work also 
included the completion of research reports by the 
Waterways Experiment Station, and aerial photography 
and interpretation of Columbia River reservoirs. Total 
costs for fiscal year were $296,179. 
Streambank erosion control evaluation and demonstration 
(Section 32, Public Law 93-251). Total costs for 
fiscal year were -$4,420. 
Shoreline erosion control demonstration (Section 54, 
Public Law 93-251). Total costs for fiscal year were $5. 
12. PROJECT CONDITION SURVEYS 
Preliminary and detailed surveys to determine navigation 
conditions at boat basins, small navigation 
projects, channels, and tributaries of major rivers not 
within major project boundaries. Soundings and visual 
inspections in subject areas are conducted in order to 
evaluate shoaling conditions. Channel centerline 
markers are inspected for visibility and proper operation 
in applicable areas frequented by boating traffic consisting 
mostly of recreationalists. In addition, all subject 
areas are inspected to insure that they are clean of snags 
and obstructions. Total costs for fiscal year were $86,010. 
13. PUGET SOUND AND ITS TRIBUTARY 
WATERS, WA 
Location. Puget Sound is in western part of 
Washington. Cities of Seattle, Tacoma, Olympia, Everett, 
Bellingham, and many small towns are on its bays 
and inlets. (See NOAA Survey Charts 18400, 18441 and 
18448.) 
Existing project. Maintenance of Puget Sound and 
its tributary waters by snagging and dredging; and removal, 
in cooperation with city of Seattle, of floating 
debris from Seattle Harbor area. Work consists of collecting 
floating and partially floating logs and larger-sized 
debris from Puget Sound and Federally authorized 
channels. (For details relating to previous projects, see 
page 2003 of Annual Report for 1915 and page 1869 of 
Annual Report for 1938.) 
Local cooperation. None required. City of Seattle is 
cooperating in a program for control of floating debris in 
Seattle Harbor. 
Terminal facilities. Terminal facilities at numerous 
localities on Puget Sound and its tributary waters are, in 
general, considered adequate for existing commerce. 
Operations during fiscal year. Maintenance, hired 
labor: In June 1983, the U.S. debris boat W.T. Preston 
was transferred to the city of Anacortes where she is the 
focal point of its maritime museum. The debris vessel 
Puget operated continuously throughout Puget Sound 
and its tributary waters. The patrol boat Walton removed 
floating debris in the greater Seattle vicinity. Together 
they removed approximately 2,500 tons of floating debris 
and hazards to navigation. Debris was disposed of 
locally or loaded aboard barges and disposed of by contract. 
Snagging operations were accomplished at Blaine 
Harbor, Bellingham Harbor, Swinomish Channel, Skagit 
River, Everett Harbor, Lake Washington Ship Canal, 
Lake Washington, Tacoma Harbor, Olympia Harbor, 
Duwamish River, and Elliott Bay. 
Maintenance, contract: 2,296 tons of harbor debris 
were disposed of at a cost of $40,088. Current contractor is 
recycling approximately 90 percent of the debris and 
placing the remainder in a landfill. 
38-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
14. QUILLAYUTE RIVER, WA 
Location. River is formed by junction of Soleduck and 
Bogachiel Rivers, in northwestern Washington, and 
flows westerly 5 miles to Pacific Ocean at La Push, about 
30 miles south of Cape Flattery. (See NOAA Survey 
Chart 18480.) 
Existing project. Provides for: (a) Jetty 15 feet high 
on easterly side of river mouth, and a dike on westerly 
side, with a view of stabilizing entrance; (b) channel 10 
feet deep and 100 feet wide extending 2,000 feet upstream 
from deep water; (c) basin 10 feet deep, 300 to 425 feet 
wide, and 2,400 feet long upstream of channel; and (d) 
maintenance of an ocean spit. Plane of reference is mean 
lower low water. Range between mean lower low water 
and mean higher high water at La Push is 8.3 feet. 
Extreme range is about 15 feet. The spit was nourished in 
conjunction with channel dredging contracts completed 
in 1973 and in 1977. The spit was rehabilitated with 
quarry rock in 1974, in 1979-80, and in 1982. In addition, a 
500-foot breakwater section paralleling the channel and 
extending the spit was constructed. Project was completed 
in February 1960; however, the channel upstream 
of the boat basin has been classified as inactive. (For 
further details, see Annual Report for 1963.) 
Local cooperation. Complied with except that the 
requirement to provide a public landing open to all on 
equal terms in the boat basin was not complied with 
between May and July 1981, due to the closure of the 
Quileute Indian Reservation to the landing of salmon by 
sport and charter fishermen. 
Terminal facilities. There are 6 privately-owned 
docks at La Push, near the mouth of the Quillayute River. 
In addition, there is a protected boat basin owned by the 
Quileute Tribe Port Authority which is used by fishing 
boats, pleasure craft, and the Coast Guard, which has a 
separate pier. 
Operations during fiscal year. Maintenance, hired 
labor: Condition surveys and studies were made of the 
river channel throughout the year. Minor entrance 
channel dredging was performed in March 1983 by the 
U.S. agitation dredge Sandwick at a cost of $39,100. 
Maintenance, contract: Dredging of the boat basin was 
completed in November 1982, with 51,551 cubic yards of 
material being removed at a cost of $132,245. Repair of 
the upper spit and construction of a breakwater on the 
lower spit were completed in December 1982, with placement 
of 52,510 tons of armor rock and 41,778 tons of 
quarry rock fill at a cost of $1,915,316. 
15. SEATTLE HARBOR, WA 
Location. Harbor at Seattle, WA, includes all waterways 
within city limits. Chief anchorage basin is Elliott 
Bay, an arm of Puget Sound. (See NOAA Survey Chart 
18450.) 
Existing project. Maintenance of East and West 
Waterways, 34 feet deep and 750 feet wide for 6,500 and 
5,200 feet, respectively, from pierhead line in Elliott Bay; 
maintenance of East Waterway between upper end of 
750-foot section and Spokane Street, 34 feet deep, 700 feet 
long, and 400 feet wide, and a turning basin, including 
head of East Waterway at junction of waterways south of 
Chicago, Milwaukee, St. Paul & Pacific Railroad Bridge, 
to 30 feet deep, after these sections of waterway are 
dredged by local interests to full project dimensions; and 
dredging Duwamish Waterway 200 feet wide and 30 feet 
deep between West Waterway and First Avenue South, 
150 by 20 feet between First and Eighth Avenues South, 
thence 150 feet by 15 feet to a point about 1.4 miles above 
14th Avenue South Bridge, with turning basin 600 by 350 
feet and 20 feet deep just south of First Avenue South 
Bridge, and turning basin 500 by 250 feet and 15 feet 
deep, and settling basin of about 100,000 cubic yards 
capacity at upper end of waterway, a distance of 5.12 
miles. Total length of waterways included in project is 
about 7.5 miles. Plane of reference is mean lower low 
water. Range between mean lower low water and mean 
higher high water is 11.3 feet. Extreme tidal range is 19.3 
feet. Project was completed in 1931, excluding the settling 
basin at upstream end which is classified inactive and 
East Waterway above the 750-foot section. (For further 
details, see Annual Report for 1932.) 
Local cooperation. Complied with, except for inactive 
portion of project. 
Terminal facilities. There are 102 wharves and piers 
on Seattle Harbor, exclusive of those given in report for 
Lake Washington Ship Canal. These facilities are considered 
adequate for existing commerce and are described 
in Port Series No. 36 -The Port of Seattle, WA, revised 
1975. 
Operations during fiscal year. Maintenance, hired 
labor: Condition surveys made of channels. 
Maintenance, contract: 126,223 cubic yards of material 
removed from Duwamish Waterway at upper end above 
First Avenue South Bridge during February and March 
1983 at a cost of $311,801. 
16. SWINOMISH CHANNEL, WA 
Location. An inland passage, 11 miles long, between 
Saratoga Passage and Padilla Bay, in northwestern part 
of Washington, about 60 miles north of Seattle. (See 
NOAA Survey Charts 18400, 18427 and 18421.) 
Existing project. A channel 100 feet wide and 12 feet 
deep for 11 miles from deep water in Saratoga Passage to 
deep water in Padilla Bay, by dredging and dike construction 
where necessary; and removal of protecting 
rocky points of McGlinn and Fidalgo Islands obstructing 
navigation at "Hole-in-the-Wall." Plane of reference is 
mean lower low water. Range between mean lower low 
water and mean higher high water is 11.5 feet at south 
end of channel, 8.4 feet at north end, and 10 feet at La 
Conner. Extreme tidal range is about 19.5 feet at south 
end of channel and about 16 feet at north end. Project was 
completed in March 1965. (For further details, see Annual 
Report for 1965.) 
Local cooperation. Fully complied with. 
Terminal facilities. There are 18 wharves, docks, 
and piers on Swinomish Channel, all but 3 of which are 
privately owned. Of these, 1 is used for handling general 
38-6

SEATTLE, WASHINGTON DISTRICT 
cargo, 5 are used exclusively for moorage, unloading, and 
servicing of fishing vessels; 2 are used for handling petroleum 
products; 3 facilities are used for log dumps; and 2 
for handling non-metallic minerals. Three publicly 
owned facilities for launching, mooring, and servicing 
small craft are within the city limits of La Conner. 
Operations during fiscal year. Maintenance, hired 
labor: Condition surveys were made of various reaches of 
the channel. 
17. TACOMA HARBOR, WA 
Location. Harbor includes Commencement Bay and 
tributary waterways at Tacoma, in northwestern 
Washington (See NOAA Survey Chart 18453.) 
Existing project. Provides for: (a) Channel in City 
Waterway 500 feet wide and 29 feet deep from deep water 
in Commencement Bay to 11th Street Bridge, 500 feet 
wide and 22 feet deep to 14th Street Bridge, and varying 
from 500 to 250 feet wide and 19 feet deep from 14th Street 
Bridge to end of this waterway, a total length of 8,500 feet; 
(b) channel in Hylebos Waterway 30 feet deep, 3.1 miles 
long, and 200 feet wide except where width is increased to 
250 feet at the bend below East 11th Street, to 300 feet at 
Lincoln Avenue bend, and to 510 feet and 770 feet, respectively, 
at the channel widening above Lincoln Avenue 
and the turning basin at the head of the waterway; (c) 
construction of two training walls, each about 700 feet 
long at mouth of Puyallup River; and (d) channel in Blair 
Waterway 2.6 miles long, including a portion seaward of 
East 11th Street, 650 feet wide and 30 feet deep over 
southerly 350 feet, and 35 feet deep over northerly 300 
feet; and remaining portion, 35 feet deep and 150 feet wide 
at East 11th Street, 600 feet wide between East 11th 
Street and Lincoln Avenue, and 300 feet wide between 
Lincoln Avenue and a 1,200-foot wide turning basin at 
head of waterway. Plane of reference is mean lower low 
water. Range between mean lower low water and mean 
higher high water is 11.8 feet. Extreme tidal range is 
about 20 feet. Project was completed in December 1966. 
(For further details, see Annual Report for 1967. For 
details relating to previous projects, see pages 1372 to 
1376 of Annual Report for 1934 and page 1875 of Annual 
Report for 1938 for Puyallup Waterway, and page 1702 of 
Annual Report of 1944 and page 1502 of Annual Report 
for 1954 for Blair (formerly Wapato and Port Industrial) 
Waterway.) 
Local cooperation. Fully complied with. 
Terminal facilities. There are 99 privately owned 
piers and wharves, 12 of which handle general cargo, 14 
handle petroleum products, 1 is a copper-handling dock, 5 
handle wood chips or hogged fuel, 5 handle industrial 
chemicals and salt, 4 receive sand and gravel, and there 
is 1 ferry dock. The remainder of the privately owned 
facilities is used for various activities normal to a port of 
this size. In addition, the Port of Tacoma owns 27 
wharves or terminals, including 1 industrial yard, and an 
industrial area. The Port of Tacoma is presently in an 
expansion program. 
Operations during fiscal year. Maintenance, hired 
labor: Condition surveys were conducted during the year. 
18. WILLAPA RIVER AND HARBOR AND 
NASELLE RIVER, WA 
Location. Willapa Harbor consists of lower reaches of 
Willapa River and Bay, an inlet of Pacific Ocean about 30 
miles north of mouth of Columbia River in Washington. 
Willapa River rises about 30 miles east of harbor, flows 
generally westerly, and empties into the bay. Naselle 
River enters the bay near its southerly end. (See NOAA 
Survey Chart 18504.) 
Existing project. Provides for: (a) channel over bar at 
mouth of Willapa Bay, 26 feet deep and at least 500 feet 
wide; (b) channel 24 feet deep and 200 feet wide from deep 
water in Willapa Bay to foot of Ferry Street at South 
Bend, thence 300 feet wide to westerly end of narrows, 
thence 250 feet wide to forks of river at Raymond, including 
a cutoff channel 3,100 feet long at narrows and a 
closing dike at Mailboat Slough; (c) channel 24 feet deep 
and 150 feet wide up south fork to deep basin above Cram 
lumber mill, and up north fork to 12th Street, with a 
turning basin 250 feet wide, 350 feet long, and 24 feet deep 
at latter point; (d) channel 10 feet deep and 40 feet wide 
from deep water in Palix River to Bay Center dock, with 
widening at shoreward end to provide a small mooring 
basin; (e) mooring basin 15 feet deep, 340 feet wide, and 
540 feet long adjacent to port wharf at Tokeland; (f) 
entrance channel at Nahcotta 10 feet deep and 200 feet 
wide, and mooring basin 10 feet deep, 500 feet wide, and 
1,150 feet long, protected by a rubblemound breakwater 
about 1,500 feet long; and (g) removal ofsnags, piles, and 
other obstructions in navigable channel of Naselle River 
between Naselle and mouth. Project includes about 26 
miles of channel from entrance through Willapa River 
forks, 2,800 feet of Palix River-Bay Center channel, and 9 
miles of Naselle River upstream of U.S. Highway 101 
Bridge. Plane of reference is mean lower low water. Tidal 
range between mean lower low water and mean higher 
high water is 8.9 feet at Toke Point, 9.9 feet at Raymond, 
8.9 feet at Bay Center, and 10.8 feet near Naselle. 
Extreme range is 18 feet at Toke Point, 19.3 feet at Raymond, 
16 feet at Bay Center, and 18 feet near Naselle. 
Project was completed in November 1958. (For further 
details, see Annual Report for 1959. For details relating to 
previous projects, see page 968 of Annual Report for 1910, 
page 2001 of Annual Report for 1915, and page 1861 of 
Annual Report for 1938.) 
Local cooperation. Complied with except that local 
sponsor is financially unable to dredge Tokeland Boat 
Basin moorage area which has resulted in the deferral 
of maintenance dredging of the boat basin access 
channel. 
Terminal facilities. There are 24 wharves on Willapa 
River and Harbor, including 5 in Willapa Bay, 4 in Bay 
Center, 12 in Raymond and South Bend, and 1 in Tokeland. 
Two of the wharves at Raymond and South Bend 
are suitable for use by ocean-going vessels; one of these is 
publicly owned and operated as a general cargo terminal, 
and one is located at a sawmill. The other wharves, 
including 3 that are publicly owned and operated, are 
used by shallow-draft vessels. These facilities are considered 
adequate for existing commerce. 
38-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Operations during fiscal year. Maintenance, hired 
labor: Condition surveys were made of various segments 
of the project. 
Flood Control 
19. CLARK FORK RIVER, MISSOULA, MT 
Location. On Clark Fork at Missoula, in southwestern 
Montana, 190 miles above its mouth in Pend Oreille 
Lake, Idaho. (See Geological Survey quadrangles Missoula 
and Bonner, MT). 
Existing project. Construction of flood protective 
works to prevent flood damage at two locations within 
city limits of Missoula, consisting of a levee and floodgate 
structure at area 5, levee and floodwall at area 3, and 
levee extension at area 3. Area 5 levee was completed in 
January 1964, and stoplog structure in April 1965. Area 3 
levee, floodwall, and levee extension were completed in 
June 1966. (For further details, see Annual Report for 
1966.) 
Local cooperation. Fully complied with. 
Operations during fiscal year. Code 710 Funds: A 
letter report was completed by the city of Missoula. 
20. HOH RIVER NEAR FORKS, WA 
Location. The project is located on the right bank of 
the Hoh River, adjacent to Jefferson County Road 216,4 
miles upstream from U.S. Highway 101 bridge over the 
Hoh River and about 14 miles southeast from Forks, 
Washington, in Spruce Mountain Quadrangle NW 1/4 of 
sec. 30, T. 25 N., R. 11 W. 
Existing project. Riprap bank protection consisting 
of a 36-inch-thick blanket of riprap placed on a slope of 
1V to 2H and fitted with an 11-foot-wide, 5-foot-thick 
weighted riprap toe to protect County Road 216 from 
further erosion. Work was accomplished in two segments 
- one segment consisting of 1,200 lineal feet of riprap and 
the other, approximately mile downstream, consisting 
of 600 lineal feet. Local participation costs estimated to 
be $1,000 for legal requirements. Construction began 
April 11, 1983. 
Local cooperation. Section 3, Flood Control Act of 
June 22, 1936, applies. 
Operations during fiscal year. New work: Work, 
including plans and specifications and construction by 
equipment rental, was completed on May 18, 1983, at a 
cost of $362,000 Federal funds ($173,000, Corps of Engineers 
and $189,000, Federal Highway Administration). 
21. HOWARD A. HANSON DAM, WA 
Location. Green River, in northwestern Washington, 
flows westerly for 40 miles to Auburn, thence northerly 
32 miles to its mouth in Elliott Bay at Seattle. Dam is at 
river mile 64, 6 miles southeast of Kanaskat, and 1 mile 
downstream from mouth of North Fork. (See Geological 
Survey topographic sheet, "Cedar Lake quadrangle, 
Wash.") 
Existing project. Rockfill dam about 235 feet high, 
with gated spillway having a concrete weir at elevation 
1176 feet above mean sea level and top of gates at 
elevation 1206, creating a reservoir with capacity of 
106,000 acre-feet. Dam along crest is about 675 feet long. 
Improvement is designed to control flooding in Green 
River Valley to alleviate agricultural and urban flood 
damage, and make possible further expansion of Seattle 
industrial area. It also supplements Tacoma water supply 
which was included as a betterment. Project was completed 
in June 1963. (For further details, see Annual 
Report for 1963.) 
Local cooperation. Fully complied with. 
Operations during fiscal year. Maintenance, hired 
labor: Operation continued all year. Routine maintenance 
was accomplished on roads, gages, debris booms, 
turbidimeter, ditches, powerline, and other project features. 
The outlet works stilling basin was inspected and 
repaired. Work continued on water quality surveys, 
water storage studies, and channel capacity study. 
Maintenance, contract: Settlement of the fill for the 
relocated Burlington Northern Railway between stations 
10989 and 10991 was under continued surveillance. 
The deferred construction period has been extended to 
cover this area to observe effect of remedial work. 
(Improvements to the drainage system have apparently 
stabilized the railroad fill.) 
22. INSPECTION OF COMPLETED FLOOD 
CONTROL PROJECTS 
Inspections are made of Federally constructed local 
flood protection projects which are maintained by local 
interests and agencies responsible for their operation 
and maintenance are advised of any needed repairs. 
During the fiscal year, inspections were made on American 
Lake, Shelton Creek, Dungeness River, Okanogan 
River at Omak and Oroville, Skykomish-Wallace, Tacoma- 
Puyallup, Stillaguamish, and Yakima Rivers - all in the 
State of Washington; Coeur d'Alene, Lightning Creek, 
and St. Maries projects in Idaho; and Clark Fork River at 
Missoula, Montana. Fiscal year costs were $66,265. Costs 
to date have been $450,177. 
23. INSPECTION OF NON-FEDERAL LEVEES 
Inspections are made of levees that have been rehabilitated 
under Public Law 84-99. Inspections involve determining 
condition of levees, riprap displacement and 
vegetative control. Local sponsors are advised of results 
and recommendations. Inspections made this fiscal year 
were at Ocosta, French Creek near Darrington, Hansville, 
Camano and Whidbey Islands, the entire 
Snohomish River Basin, and the Methow, Okanogan, 
and Spokane Rivers - all in the State of Washington; 
Coeur d'Alene River in Idaho; and Flathead and Kootenai 
Rivers in Montana. Fiscal year costs were $39,977. 
Total costs to date have been $39,977. 
24. MUD MOUNTAIN DAM, WA 
Location. On White River, principal tributary of 
Puyallup River, near Mud Mountain, 28 miles above its 
confluence with Puyallup River, and 38 miles above 
mouth of Puyallup River. Dam is 6 miles southeast of 
Enumclaw, in northwestern Washington, and 38 miles 
38-8

SEATTLE, WASHINGTON DISTRICT 
east of Tacoma. (See Geological Survey topographic 
sheet "Cedar Lake quadrangle, Washington.") 
Existing project. Rockfill dam, 700 feet long at crest 
elevation, rises 425 feet above bedrock. Reservoir has 
storage capacity of about 106,000 acre-feet. Outlet works 
are in right abutment and permit controlled discharge of 
17,700 cubic feet per second through two concrete-lined 
tunnels with uncontrolled discharge over spillway having 
maximum capacity of 139,000 cubic feet per second. 
Improvement affords flood protection to White and 
Puyallup River Valleys and protects Tacoma industrial 
district in conjunction with Puyallup River project at 
Tacoma against floods about 50 percent greater than 
maximum discharge of record. Project was completed in 
June 1953, except for recreational facilities. (For further 
details, see Annual Report for 1953.) To date the Corps 
has constructed two vistas, a picnic area, and playground 
adjacent to the project office, a reservoir access 
point for hunters and fishermen, and a 1,760-foot trail 
leading to the lower vista area. 
Local cooperation. None required. 
Operations during fiscal year. Maintenance, hired 
labor: Project features were operated all year. Maintenance 
was accomplished on dam facilities, 9-foot regulating 
outlet tunnel, intake structure, gages, debris booms, 
power lines, roads, ditches, and fish facilities. Approximately 
1,000 fish are transported annually from the fish 
collection facility. 
Maintenance, contract: Contracts for 9-foot tunnel 
intake repair were awarded and completed in the amount 
of $138,559. A contract in the amount of $117,162 for two 
propulsion units was awarded in September 1983. 
25. PLACER CREEK, ID 
Location. Placer Creek rises in the St. Joe Mountains 
of northern Idaho, flows northerly about 7.8 miles, and 
discharges into the South Fork of Coeur d'Alene River at 
the city of Wallace. 
Existing project. Provides for flood control by construction 
of a 3,700-foot-long concrete channel to confine 
Placer Creek flows through Wallace. A debris basin capable 
of storing 17,000 cubic yards of debris is located 
upstream from the channel to prevent plugging of the 
channel. 
Local cooperation. Fully complied with. Requirements 
are described in full on page 38-10 of FY 1981 
Annual Report. 
Operations during fiscal year. New work, contract: 
Contract for construction of the debris basin and concrete 
channel is physically complete. Remaining work 
includes joint caulking and landscaping. 
26. SCHEDULING FLOOD CONTROL 
RESERVOIR OPERATIONS 
Flood control storage space was available in Hungry 
Horse Reservoir, MT, Flathead Lake, MT (controlled by 
Kerr Dam), Grand Coulee Project, WA, Upper Baker and 
Ross Reservoirs, WA. Guidance forecasts were made 
during the flood control season, as required. A public 
meeting was held on regulations of Upper Baker and 
Ross Dams for flood control. A study was performed to 
develop a Skagit River hydromet system. No lost valley 
storage replacement was requested at Rocky Reach, Priest 
Rapids, and Wells Dams. Daily and/or hourly data 
were collected and tabulated as required to check compliance 
with operating criteria. Coordination necessary 
in preparation or revision of reservoir regulation 
manuals was carried on during the year with agencies 
responsible for the operation of these projects. Fiscal year 
costs were $124,802. 
27. STILLAGUAMISH RIVER, WA 
Location. Formed by confluence of its north and 
south forks at Arlington, in northwestern Washington, 
Stillaguamish River flows westerly 22 miles to Puget 
Sound, entering Port Susan through Hat Slough and 
South Pass, and Skagit Bay through West Pass. (See 
NOAA Survey Chart 18441, and Geological Survey 
quadrangles Stanwood, Marysville, and Stillaguamish, 
WA.) 
Existing project. Works to reduce bank erosion and 
channel changes on Stillaguamish River 15 miles between 
Arlington and head of Hat Slough, and on Cook Slough, 
3 miles long, as follows: Revetment at 26 places on river 
and Cook Slough; concrete weir 275 feet long between 
steel-sheet-pile piers at head of Cook Slough to limit flow 
through slough; and two cutoff channels, each about 900 
feet long, to eliminate sharp bends in Cook Slough. Tidal 
influence extends about 3 miles into improved section. 
Flood stages of 16 feet above low water at Cook Slough 
weir have been observed. Project was completed in July 
1939. (For further details, see Annual Report for 1940.) 
Local cooperation. None required. 
Operations during fiscal year. Maintenance: Removed 
brush and trees on 3,000 linear feet of 2 segments; 
repaired 2 segments with gravel and riprap. Placed 
riprap adjacent to upstream face of Cook Slough weir to 
prevent further damage. 
28. TACOMA, PUYALLUP RIVER, WA 
Location. Puyallup River has its source in glaciers on 
western slopes of Mount Rainier, WA, flows northwesterly 
50 miles, and empties into Commencement Bay, an 
arm of Puget Sound, at Tacoma. Work covered by this 
project is on Puyallup River, within city limits of Tacoma. 
(See NOAA Survey Chart 18453.) 
Existing project. A channel with a capacity of 50,000 
cubic feet per second between East 11th Street Bridge and 
lower end of inter-county improvement, a distance of 
about 2.2 miles, by straightening channel, building 
levees, revetting channel and levees, and making necessary 
bridge changes. The 11th Street Bridge at lower end 
of project is 0.75 mile above mouth of Puyallup River. 
Diurnal tidal range at mouth of river is 11.8 feet and 
extreme range is 20 feet. Improvement was planned in 
conjunction with Mud Mountain Dam and affords protection 
against floods about 50 percent greater than maximum 
discharge of record. Project was completed in May 
1950. (For further details, see Annual Report for 1950.) 
Local cooperation. None required. 
38-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Operations during fiscal year. Maintenance, hired 
labor: Repaired damaged levee embankment. Other 
funds expended to prepare environmental assessment for 
the Corps maintenance program. Puyallup Indian 
Nation has a court injunction against removal of brush 
and trees on the Puyallup River system. 
29. WYNOOCHEE LAKE, WA 
Location. On Wynoochee River, a tributary of Chehalis 
River, about 28 miles north of Montesano, Grays Harbor 
County, WA. (See Geological Survey quadrangles, 
Grisdale, Wynoochee Valley, and Montesano, WA.) 
Existing project. Provides for a concrete and earthfill 
dam, 177 feet high, and reservoir of 70,000 acre-feet of 
total storage for water supply, flood control, irrigation, 
and fish and wildlife. Upstream fish facilities were operational 
in the fall of 1970. The project was completed and 
became operational in December 1972. Installation of 
power-generating facilities was not authorized, pending 
a reexamination report by the Chief of Engineers. In 
February 1966, the Federal Power Commission asserted 
that power production as part of the Wynoochee project 
was not feasible at that time. (For further details, see 
Annual Report for 1972.) 
Local cooperation. Fully complied with. Requirements 
are described in full on page 38-12 of FY 1981 
Annual Report. 
Operations during fiscal year. Maintenance, hired 
labor: Project facilities were operated all year. Maintenance 
was accomplished on dam and fish facilities, 
roads, ditches, culverts, and visitors' facilities. A tank 
truck hauled 1,720 fish past the dam. 
30. YAKIMA RIVER, YAKIMA, WA 
Location. The project is located on the left bank of the 
Yakima River at RM 115.0, 1.5 miles downstream from 
the confluence with the Naches River in Yakima East 
Quadrangle, SE '4Ao f sec. 7, T. 13 N., R. 19 E., Willamette 
Meridian. 
Existing project. A 500-lineal-foot riprap bank protection 
project consisting of riprap blanket, 30 inches 
thick on a 1V to 2H slope and a 12-foot-wide, 4-foot-thick 
weighted riprap toe. Clean gravel and quarry spalls 
would be used to reconstruct the required embankment 
slope. Proposed work is considered the most effective and 
least costly method of protecting the Moxee Hubbard 
irrigation ditch from further erosion. Local participation 
costs are estimated to be $1,000 for legal requirements. 
Construction began April 25, 1983. 
Local cooperation. Section 3, Flood Control Act of 
June 22, 1936, applies. 
Operations during fiscal year. New work: Proposed 
work, including letter report, plans and specifications, 
and construction by equipment rental, was 
completed on May 11, 1983, at a cost of $118,000, Federal 
funds. 
Multiple-Purpose Projects, Including 
Power 
31. ALBENI FALLS DAM, ID 
Location. Dam is on Pend Oreille River about 25 miles 
west of Sandpoint, in northern Idaho, and 50 miles northeast 
of Spokane, WA. Dam is 838 and 90 miles 
upstream from mouths of Columbia and Pend Oreille 
Rivers, respectively. (See Geological Survey topographic 
sheets, Sandpoint, ID, and Newport, WA.) 
Existing project. Provides flood control, hydroelectric 
power, and related water uses on Pend Oreille River as 
a part of the multiple-purpose plan for development of 
Columbia River Basin, including recreation development. 
At the dam, channel was formerly divided by an 
island and a low waterfall of about 7 feet. Dam is a gated, 
gravity-structure spillway in left channel and a powerhouse 
having an installation of 42,600 kilowatts in right 
channel, creating a reservoir with a usable storage capacity 
of 1,153,000 acre-feet. Project was completed in June 
1957. (For further details, see Annual Report for 1957.) 
Recreational facilities for public use have been provided 
at Albeni Cove, Priest River, Riley Creek, Johnson Creek, 
Trestle Creek, Strongs Island, and Springy Point. 
(Strongs Island was closed in FY 1982 to reduce O&M 
costs.) (Refer to Albeni Falls Master Plan dated June 
1981 for further planned development.) 
Local cooperation. None required. 
Operations during fiscal year. Maintenance, hired 
labor: Reservoir was operated through its annual cycle of 
storage and release. Routine structural, mechanical, and 
electrical maintenance was performed on spillway, dam, 
powerhouse, and equipment. 
Maintenance, contract: A $158,475 debris facility rehabilitation 
contract, awarded in July 1983, was completed. A 
$118,344 station service circuit breaker contract was 
awarded in September 1983, with completion scheduled 
for March 1985. 
32. CHIEF JOSEPH DAM, RUFUS WOODS 
LAKE, WA 
Location. On Columbia River in north central Washington, 
at river mile 545, just upstream from mouth of 
Foster Creek, 1.5 miles upstream from Town of Bridgeport. 
(Geological Survey topographic sheet Okanogan, 
WA, shows general locality.) 
Existing project. A concrete gravity structure which 
consists of a 19-gate spillway and a 27-unit powerhouse. 
The powerhouse has sixteen 64,000 kilowatt and eleven 
95,000 kilowatt generators with nameplate capacity of 
2,069,000 kilowatts. Pool raising to elevation 956 was 
completed in 1981 which increased the powerplant capability 
to 2,450,000 kilowatts. Project providing initial 16 
power units was completed in FY 1961. (For further 
details, see Annual Report for 1962.) Generator units 17 
through 27 are producing power; however, additional 
work will be required to bring turbine efficiency up to 
design standards. Construction of structural modifications 
to dam and powerhouse, installation of additional 
units, uprating and plant modernization of units 1-16, 
38-10

SEATTLE, WASHINGTON DISTRICT 
and other miscellaneous project work is approximately 
82 percent complete. Estimated cost of current construction 
project is $387,000,000 (full funding). 
Local cooperation. None required. 
Operations during fiscal year. New work, hired 
labor: Completed power lines to site 15; continued real 
estate acquisition and stability analysis; and completed 
rewrite of design memorandum for project security. 
Plans and specifications were completed for turbine cavitation, 
battery chargers, main unit excitation system, 
generator stator rewind, installation and fire protection, 
transformers, governor system, station service system, 
protective relays, and powerhouse shops - all part of 
uprating Units 1 - 16; and wildlife mitigation: powersouth 
side/power-north side, and planting. 
New work, contract: Contracts were awarded for turbine 
cavitation, battery chargers, main unit excitation 
system, generator stator rewind, installation and fire 
protection, transformers, governor system, station service 
system, protective relays, and 15 Kv circuit breakers. 
Contracts continuing through the fiscal year included 
cultural resources relocation, spillway gate deficiencies, 
pier crack grouting, roads/paving/utilities, Bridgeport 
State Park restroom and comfort station, administration 
building renovation, wildlife mitigation: plant propagation, 
mule deer study, mitigation evaluation, and planting. 
Contracts completed during the fiscal year included 
14.4 Kv switchgear, in the amount $2,327,960 and land 
restoration, in the amount of $1,054,320. 
Maintenance, hired labor: Project was operated all 
year, and routine maintenance work was performed. 
Maintenance, contract: Contracts for structural repairs 
were awarded and completed in the amount of $500,000. 
33. LIBBY DAM-LAKE KOOCANUSA, MT 
Location. On Kootenai River in Lincoln County, MT, 
about 17 miles upstream from Libby, and 219 miles 
upstream from confluence of Kootenai with Columbia 
River. (See Geological Survey topographic sheet, Thompson 
Lakes, MT.) 
Existing project. Provides storage for local flood control 
protection in Montana and Idaho, and main stem 
flood control in Lower Columbia River, hydroelectric 
power generation at-site and at downstream plants 
through storage release. Project will be operated as a unit 
of comprehensive system for improvement of Columbia 
River Basin for flood control, navigation, hydroelectric 
power, and other purposes. 
Local cooperation. Fully complied with. 
Libby Dam-Lake Koocanusa Project. Dam is a 
straight concrete gravity overflow type, 420 feet high, 
3,055 feet long, with normal full pool at elevation 2459 
feet above mean sea level. Powerhouse has an initial 
installed capacity of 420,000 kilowatts from four hydroelectric 
generating units with provision for four additional 
units, one of which is currently under construction. 
Lake Koocanusa is 90 miles long, backing water 42 miles 
into Canada and has a usable storage capacity of 
4,965,000 acre-feet at 50 percent drawdown. Construction 
of dam was in accordance with treaty between United 
States and Canada relating to international cooperation 
in water-resource development of the Columbia River 
Basin. Project features include: Relocation of 52 miles of 
Montana State Highway; 60 miles of Burlington Northern 
Railroad, including a seven- mile tunnel; 50 miles of 
Forest Development roads, including a 2,400-foot long 
steel truss bridge; construction of a selective withdrawal 
structure to control temperature and oxygen conditions 
of water released past the dam; school facilities for education 
of dependents of construction personnel; participation 
in airport facilities at Kelley Flats, MT; use of 
$4,000,000 project funds for fish production measures; 
acquisition and conveyance to the State of Montana not 
more than 12,000 acres of land, at cost not to exceed 
$2,000,000, for the prevention of wildlife grazing losses 
caused by the project; relocating Deep Creek Bridge, 
Boundary County, ID; compensating drainage districts 
and owners of leveed and unleveed tracts in Kootenai 
Flats, Boundary County, ID, for modification of pumping 
facilities, crops and other damages caused by duration of 
higher flows during drawdown operation of Libby Dam; 
constructing central sewage collection and treatment 
facilities as part of the relocation of municipal facilities of 
Rexford, MT; and 7 campground recreation facilities. 
Recreation development beyond the initial 7 sites will be 
by the U.S. Forest Service. Construction is essentially 
complete, with flood contingency measures in the powerhouse 
the only remaining item of work. 
Operations during fiscal year. New work, hired 
labor: Investigative work of downstream effects, development 
of a master plan, and continued supervision and 
administration of cultural resources contracts were carried 
out. Meetings with Canada for water quality protection 
and hydrology and reservoir operations were held. 
Monolith crack grouting and spillway repairs were completed 
by hired labor. 
New work, contract: A contract was awarded for flood 
contingency plan, scheduled for completion in January 
1984. Contracts completed during the fiscal year included 
powerhouse circuit breaker barriers, downstream restoration 
(Phase II), rock slide detection system, and sluice 
vent modification. 
Maintenance, hired labor: Reservoir was operated 
through its annual cycle of storage and release. Routine 
structural, mechanical, and electrical maintenance was 
performed on spillway, dam powerhouse, and equipment. 
Maintenance, contract: Contracts, in the amount of 
$154,500, were awarded for left abutment installation. 
Libby Additional Units Project. Provides for 
installation of 4 additional units at the Libby Dam 
Powerhouse. Estimated Federal cost is $52,800,000 (full 
funding). 
Operations during fiscal year. New work, contract: 
Fabrication of generators for units 5 through 8 was completed; 
however, only the unit 5 generator is being 
installed. Manufacture of auxiliary electrical equipment 
continued. Installation of the electrical equipment is 
limited to unit 5. Parts for units 6 through 8 will be stored 
at the site. 
38-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Libby Reregulating Dam Project. Provides for 
construction of a reregulating dam about 10 miles downstream 
of Libby Dam and associated relocation of about 
9 miles of Burlington Northern Railroad, 7.5 miles of St. 
Regis log haul road, 0.5 miles of Forest Development 
Road, and 7.5 miles of Montana State Highway. Estimated 
Federal cost is $285,000,000 (October 1982). Funds 
were provided for a construction start in 1977; however, 
courts have found that Congress did not authorize construction 
of the reregulating dam. 
Operations during fiscal year. Construction work 
continues to be halted due to a court injunction. 
Libby Reregulating Dam - Power Units Project. 
Provides for installation of three hydroelectric generating 
units at the reregulating dam with 78,900 kilowatt 
installed capacity. A General DI)esign Memorandum 1, 
Phase II, Preliminary Design Report was approved by 
the Office, Chief of Engineers on March 3, 1981. Cost to 
install the three units is estimated at $74,000,000 (October 
1982). 
General Investigations 
34. SURVEYS 
Fiscal year costs were $240,234 for navigation studies, 
$195,728 for flood control studies, $423,546 for comprehensive 
basin studies, $1,667 for review of authorized 
projects, $71,775 for miscellaneous activities, and $58,835 
for coordination studies with other agencies, a total of 
$991,785. 
35. COLLECTION AND STUDY OF BASIC DATA 
The work programmed for collection and study of basic 
data covers international water studies, flood plain management 
services, and hydrologic studies. Work on international 
water studies included checking Kootenay Lake 
storage computations to determine compliance of West 
Kootenay Power & Light Co. with orders of International 
Joint Commission, and coordination with International 
Kootenay Lake, Osoyoos Lake, and Skagit River Boards 
of Control in enforcement of International Joint Commission 
orders. Technical assistance was provided other 
Federal and non-Federal agencies in flood hazard evaluation 
and related services as requested. Fiscal year costs 
were $2,814 for inspection of dams, $2,999 for international 
water studies, $110,376 for flood plain management 
services, and $5,373 for hydrologic studies, a total of 
$121,562. 
36. CONTINUATION OF PLANNING AND 
ENGINEERING 
Blair and Sitcum Waterways, Tacoma Harbor, WA 
Tacoma Harbor, Pierce County, is located in southern 
Puget Sound in the northwest corner of Washington 
about 30 miles south of Seattle in Washington's 6th Congressional 
District. 
The proposed plan of improvement provides for (a) 
modification of the existing Federal project for Blair 
Waterway to provide for the construction and maintenance 
of a 45-foot and a 41-foot channel including 
replacement of the East 11th Street Bridge and (b) Federal 
maintenance of the locally constructed Sitcum 
Waterway to depths of 40 and 35 feet. 
Continuation of planning and engineering studies 
were initiated in May 1982 which included environmental 
studies necessary for a Section 404 evaluation report 
and a bridge design report conducted by the Washington 
State Department of Transportation. Bioassay testing, 
evaluation for Section 404 evaluation report, and the 
bridge design report have been completed. 
Estimated preconstruction planning cost is $980,000. 
Costs during the fiscal year were $22,192 for a total of 
$513,809, including $300,000 appropriated and expended 
under Section 101(c). 
38-12

SEATTLE, WASHINGTON DISTRICT 
TABLE 38-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
In Text Project Funding FY 80 FY 81 FY 82 FY 83 Sept. 30, 1983 
1. Anacortes Harbor, 
WA (Federal Funds) 
(Contrib. Funds) 
2. Bellingham Harbor, 
WA (Federal Funds) 
(Contrib. Funds) 
3. East Bay Marina, 
Olympia Harbor, WA 
(Federal Funds) 
(Contrib. Funds) 
4. Ediz Hook, WA 
(Federal Funds) 
(Contrib. Funds) 
5. Everett Harbor and 
Snohomish River, 
WA (Federal Funds) 
(Contrib. Funds) 
Ei. Floating Breakwater 
Prototype Test 
Program, WA 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Maint. 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Maint. 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Maint. 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Maint. 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
19,875 140,000 
19,875 104,113 
382,300 
384,579 1,953 
25,000 
60,608 
49,000 
50,687 
279 
3,025 
3,270 
10,000 175,000 905,000 341,000 
14,562 162,464 917,529 318,254 
- - 1,614,000 276.000 
- - 1,044,205 723,671 
8,977 - - - 
25,000 
25,000 
900,000 
1,071,683 
24,000 
22,588 
4,605 
5,700 
34,000 
31,394 
1,655 
3,284 
15,000 
8,925 
855 
2,165 
54,000 522,000 363,617 
52,654 523,497 363,615 
441,000 
441,000 
251,000 793,000 402,000 
250,121 792,047 403,779 
38-13 
222,345 
222,345 
612,761 
612,7611 
59,523 
59,523 
5,000 
5,000 
1,566,840 
1,566,8402 
1,094,100 
1,094,098'1 
31,581 
31,581 
9,103 
9,103 
1,729,976 
1,707,149 
1,890,000 
1,767,876 
5,876,880 
5,876,880 
136,104 
126,011' 
396,000 
396,000 
8,210 
5,449 
1,775,744 
1,775,7446 
5,829,269 
5,829,2671 7 
5,618 
5,618 
457,000 
457,000 
1,446,000 
1,445,947

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 38-A 
(Continued) 
COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
In Text Project Funding FY 80 FY 81 FY 82 FY 83 Sep. 30, 1983 
7. Friday Harbor 
Marina, WA 
(Federal Funds) 
(Contrib.Funds) 
8. Grays Harbor and 
Chehalis River, WA 
(Federal Funds) 
(Contrib. Funds) 
9. Lake Crockett, WA 
10. Lake Washington 
Ship Canal, WA 
13. Puget Sound and its 
Tributary Waters, 
WA 
14. Quillayute River, 
WA 
(Federal Funds) 
(Contrib. Funds) 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Minor 
Rehab. 
Approp. 
Cost 
Major 
Rehab. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Maint. 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
110,000 
114,810 
2,000 
1,249 
55,000 115,000 1,115,000 
52,700 110,148 1,042,099 
60,000 
60,259 
37,545 
38,026 
60,000 
35,000 
35,010 
2,660,000 3,972,800 3,193,000 3,289,000 
2,661,536 3,946,277 3,224,499 3,289,402 
22,000 
26,657 
41,858 138,000 
37,852 140,955 
59,000 
58,502 472 
1,032 
-7,545 
-7,519 
54,000 
52,273 
19 
3,499,600 2,938,000 2,837,000 2,851,000 
3,183,942 3,429,332 2,814,197 2,856,510 
- - 1,100,000 2,275,000 
- - 1,099,779 2,275,220 
1,168,500 1,160,800 927,000 600,000 
1,162,637 1,168,840 928,715 601,269 
150,000 370,000 3,074,000 -310,000 
151,429 369,427 2,262,394 501,062 
38-14 
1,538,037 
1,457,9698 
60,000 
5,165,396 
55,,116655,,339965'9 
65,710,464 
65,707,192 o 
120,592 
120,592 
4,606,145 
4,606,145 
35,834 
35,834 
47,889 
47,889 
406,240 
404,513" 
574,465 
574,465' 
4,803,952 
4,803,952'z 
50,774,230 
50,744,199'' 
3,375,000 
3,374,999 
43,337 
43,337 
14,662,302 
14,662,30214 
521,850 
521,8505 
8,128,760 
8,127,258 
20,000 
' 20,000

SEATTLE, WASHINGTON DISTRICT 
TABLE 38-A 
(Continued) 
COST AND FINANCIAL STATEMENT 
See 
Section 
In Text Project 
15. Seattle Harbor, WA 
(Federal Funds) 
(Contrib. Funds) 
16. Swinomish Channel, 
WA 
17. Tacoma Harbor, WA 
(Federal Funds) 
(Contrib. Funds) 
18. Willapa River and 
Harbor and Naselle 
River, WA 
(Federal Funds) 
(Contrib. Funds) 
19. Clark Fork River, 
Missoula, MT 
(Federal Funds) 
(Contrib. Funds) 
20. Hoh River, near 
Forks, WA 
21. Howard A. Hanson 
Dam, WA 
(Federal Funds) 
(Contrib. Funds) 
24. Mud Mountain 
Dam, WA 
Funding 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Total Cost to 
FY 80 FY 81 FY 82 FY 83 Sep. 30, 1983 
- - - - 170,335 
- - - - 170,335 
325,000 378,000 312,000 428,358 
327,356 377,121 312,240 428,995 
70,000 276,500 114,000 
72,376 265,245 124,922 
78,633 
78,583 
80,000 
88,788 
-1,311 
40,000 
40,072 
77,000 113,000 
73,863 116,137 
7,000 
6,999 
70,000 
65,360 
20,000 
21,289 
60,000 
59,914 
1,000 
1,000 
5,572,074 
5,572,0721 
69,333 
69,333 
808,332 
808,33216 
5,147,243 
5,142,270 
2,435,500 
2,435,500'7 
1,446,335 
1,446,335118 s 
559,581 
559,58119 
1,579,269 
1,579,26920 
12,578,978 
12,578,89221 
78,372 
78,37222 
385,012 
385,0112:z 
13,500 
13,500 
173,000 
173,000 
369,000 588,000 530,000 528,000 
400,360 588,848 531,095 527,245 
837,500 1,162,000 828,000 1,136,162 
861,114 1,163,507 830,027 1,110,512 
173,000 
173,00024 
37,048,061 
37,048,061 
7,623,251 
7,622,213 
2,000,000 
2,000,000 
13,295,848 
13,295,84825 
12,854,534 
12,817,186 
38-15

TABLE 39-A 
(Continued) 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
In Text Project 
25. Placer Creek, ID 
27. Stillaguamish 
River, WA 
28. Tacoma, Puyallup 
River, WA 
29. Wynoochee Lake, 
WA 
30. Yakima River, 
Yakima, WA 
31. Albeni Falls Dam, 
IDI) 
32. Chief Joseph Dam- 
Rufus Woods Lake, 
WA 
33. Libby Dam, Lake 
Koocanusa, MT 
(Federal Funds) 
(Contrib. Funds) 
Funding 
Minor 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
FY 80 FY 81 FY 82 FY 83 Sep. 30, 1983 
375,000 750,000 3,225,000 845,000 
384,471 732,345 3,235,803 722,954 
85,000 
72,008 
9,600 
12,731 
32,000 141,000 150,000 
37,257 148,672 142,972 
4,000 
730 
32,000 
29,593 
3,270 
:39,000 
41,406 
40,000 
39,947 
1 - 
974,881 1,013,000 891,000 908,000 
877,626 1,158,860 873,785 934,637 
- - 7,500 118,000 
- - 7,500 118,000 
16 - - - 
1,351,000 1,408,000 1,377,320 1,923,231 
1,372,010 1,391,276 1,364,305 1,843,759 
16,597,000 20,858,000 8,170,000 11,900,000 
15,835,523 21,556,256 8,091,788 12,088,050 
3,743,200 4,551,800 4,381,000 5,198,000 
3,669,785 4,648,742 4,379,283 5,194,095 
14,123,000 8,913,000 10,090,000 6,250,000 
13,154,883 9,959,243 9,943,442 6,365,210 
2,005,000 2,180,000 1,997,000 2,590,900 
2,033,236 2,168,699 1,990,590 2,583,965 
285,908 
285,908 
5,475,000 
5,345,800 
220,594 
220,594 
1,209,845 
1,201,584 
3,947,853 
3,947,853" 
366,597 
366,543 
23,494,445 
23,494,4457 
7,835,069 
7,832,902 
125,500 
125,500 
31,878,297 
31,878,2972 
20,948,807 
20,825,5309 
462,878,235 
462,713,1881 
54,323,935 
54,284,765 
297,630 
297,630 
540,351,1403' 
540,293,09212 
16,069,979 
16,030,828 
1,458,252 
1,458,252 
38-16

SEATTLE, WASHINGTON DISTRICT 
See 
Section Total Cost to 
In Text Project Funding FY 80 
lIncludes applicable portion of Reconnaissance and 
Condition Surveys appropriations and costs. 
2Includes $56,582 appropriated and expended for previous 
projects. Excludes $13,000 Coast Guard funds expended. 
3Includes $1,092 appropriated and expended for previous 
project. 
4Excludes $2,157,473 expended by Port of Bellingham in 
fulfilling requirements of local cooperation. 
Includes $330,517 appropriated and expended for preauthorization 
cost. 
6Includes $418,209 appropriated and expended for previous 
projects. Excludes $43,000 Coast Guard funds expended. 
Includes $5,869 appropriated and expended for previous 
projects. 
8Includes $43,037 for previous project and $235,341 
preauthorization cost, appropriated and expended. 
9Includes $134,545 appropriated and $134,544 expended 
for recreation facilities at completed project (Code 710), and 
$113,134 appropriated and expended for previous projects. 
Excludes $162,000 Navy funds and $6,000 Coast Guard 
funds, expended. 
1 l�Includes $37,415 appropriated and expended for previous 
projects. 
"1 Includes $146,000 appropriated and $144,273 expended 
for recreation facilities at completed project (Code 710). 
12Includes $779,655 for recreation facilities at completed 
project (Code 710), and $485,002 for previous projects, appropriated 
and expended. 
3Includes $1,631,195 appropriated and expended between 
1916 and 1936 on operation and care of works of 
improvement, under provisions of the permanent indefinite 
appropriation for such purposes. 
'4Includes $67,496 appropriated and expended for previous 
project. 
' Excludes Navy funds expended on dredging river 
channel in 1944 and Coast Guard funds expended for channel 
dredging in 1948 and 1949. 
FY 81 FY 82 FY 83 Sep. 30, 1983 
16Excludes $1,000 Coast Guard funds expended. 
17Includes $159,584 appropriated and expended for previous 
projects. 
l 8Includes $5,347 appropriated and expended for previous 
projects. 
19Includes $62,697 value in work contributed and expended 
by Port of Tacoma. 
20Includes $228,084 appropriated and expended for previous 
projects. Excludes $40,000 Coast Guard funds ex 
pended. 
21Includes $309,177 appropriated and expended for previous 
projects. 
22Includes $6,597 appropriated and expended for previous 
project. 
2 3Includes $8,000 appropriated and $7,999 expended for 
recreation facilities at completed project (Code 710). 
2 4Excludes $189,000 Federal Highway Administration 
funds expended. 
25Includes $87,785 appropriated and expended for recreation 
facilities at completed project (Code 710). 
26Includes $5,035 appropriated and expended for recreation 
facilities at completed project (Code 710). 
27 lIncludes $102,200 appropriated and expended for recreation 
facilities at completed project (Code 710). 
28lIncludes $136,736 Public Works Acceleration Act Funds 
and $971,947 for recreation facilities at completed project 
(Code 710), appropriated and expended. 
29Includes $152,776 Special Recreation Use Fees, appropriated 
and expended. 
30lncludes $58,000 Public Works Acceleration Act Funds 
and $147,983 for recreation facilities at completed project 
(Code 710), appropriated and expended. 
31lIncludes $39,756,634 for additional units, $16,276,363 
for reregulating dam, and $475,000 for power planning. 
32Includes $39,714,545 for additional units, $16,276,363 
for reregulating dam, and $475,000 for power planning. 
38-17 
TABLE 38-A 
(Continued) 
COST AND FINANCIAL STATEMENT

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 38-B AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Mar. 2, 1919 
Sep. 3, 1954 
June 25, 1910 
July 3, 1930 
Aug. 26, 1937 
Sep. 3, 1954 
July 3, 1958 
July 14, 1960 
as amended 
Mar. 7, 1974 
June 25, 1910 
July 3, 1930 
June 20, 1938 
Sep. 3, 1954 
July 14, 1960 
Aug. 13, 1968 
6. 
July 14, 1960 
as amended 
1. 
9. 
ANACORTES HARBOR, WA 
Channel in Capsante Waterway. 
Mooring basin. 
BELLINGHAM HARBOR, WA 
Whatcom Creek Waterway 26- and 18-foot channels. 
Entrance channel in Squalicum Creek Waterway. 
Maintenance of southerly half and westerly end of 
Squalicum Creek Basin. 
Small-boat basin adjacent to Squalicum Creek 
Waterway. 
Whatcom Creek Waterway, 30-foot channel. 
EAST BAY MARINA, OLYMPIA 
HARBOR, WA 
Construction of 700 feet of concrete floating 
breakwater and dredging of the entrance and access 
channels and turning basin. 
EDIZ HOOK, WA 
Construction of 10,000 lineal feet of rock revetment, 
together with initial beach replenishment and 
annual nourishment. 
Emergency interim measures necessary to prevent 
breaching of Ediz Hook prior to construction of 
authorized project. 
EVERETT HARBOR AND SNOHOMISH 
RIVER, WA 
Training dike 10,500 feet long extending across bar 
at outlet of old river channel. 
Raise 6,000 feet of training dike, extend spur dike, 
widen gap in dike as required, maintain East 
Waterway and channel to gap. 
Abandon project for Snohomish River and provide 
settling basin near 14th Street. 
Spur dike at Preston Point, remove training dike 
north of river outlet, enlarge channel to 14th Street, 
and deepen settling basin. 
Widen channel from settling basin to gap; extend 
channel to head of Steamboat Slough; and a settling 
basin within upper channel reach. 
Raise and extend existing training dike; and construct 
breakwater on westerly and southerly sides of 
14th Street small-boat basin.4 
FLOATING BREAKWATER PROTOTYPE 
TEST PROGRAM, WEST POINT, SEATTLE, 
WA 
Construction, placement, monitoring, and removal of 
two types of floating breakwater, a concrete box 
design and a pipe-tire mat design. 
Sec. 107, P.L. 86-645 
Authorized by Chief of 
Engineers, Feb. 5, 1981 
38-18 
H. Doc. 1117, 64th Cong., 
1st Sess. 
S. Doc. 102, 83d Cong., 
2d Sess. 
H. Doc. 1161, 60th Cong. 
2d Sess. 
H. Doc. 187, 70th Cong., 
1st Sess. 
Rivers and Harbors 
Committee Doc. 70, 74th 
Cong., 1st Sess.' 
H. Doc. 558, 82d Cong., 
2d Sess. 2 
S. Doc. 46, 85th Cong., 
1st Sess. 
Sec. 107, P.L. 86-645 
Authorized by Chief of 
Engineers, May 13, 1981 
H. Doc. 93-101, 93d Cong., 
1st Sess., P.L. 93-251 
H. Doc. 1108, 60th Cong., 
2d Sess. 
H. Doc. 377, 71st Cong., 
2d Sess. 
H. Doc. 546, 75th Cong., 
3d Sess. 
H. Doc. 569, 81st Cong., 
2d Sess. 
H. Doc. 348, 86th Cong., 
2d Sess. 
H. Doc. 357, 90th Cong., 
2d Sess. 5 
3. 
4.

SEATTLE, WASHINGTON 
TABLE 38-B 
(Continued) 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
1. 
8. 
July 14, 1960 
as amended 
June 3, 1896 
Mar. 2, 1907 
Mar. 2, 1907 
June 25, 1910 
June 25, 1910 
Aug. 8, 1917 
Jan. 21, 1927 
July 3, 1930 
Aug. 30, 1935 
Aug. 30, 1935 
Dec. 22, 1944 
as amended 
Mar. 2, 1945 
June 30, 1948 
Sep. 3, 1954 
Sep. 3, 1954 
Mar. 2, 1945 
Dec. 22, 1944 
as amended 
FRIDAY HARBOR MARINA, WA 
Construction of 1600 feet of concrete floating 
breakwater. 
GRAYS HARBOR AND CHEHALIS 
RIVER, WA 
South jetty. 
A north jetty 9,000 feet long. 
The 18-foot channel. 
Extend north jetty 7,000 feet; length of south jetty 
fixed at 13,734 feet. 
A 6-foot channel above Cosmopolis. 
Dredging in bar channel. 
Dredging in bar channel. 
16-foot channel from Cosmopolis to Montesano.6 
Reconstruct north and south jetties to an elevation of 
16 feet above mean lower low water. 
Maintain 26-foot channel below Aberdeen (as authorized 
by Public Works Administration Dec. 11, 1933) 
and combining projects for Grays Harbor and bar 
entrance and Grays Harbor, inner portion, and 
Chehalis River under a modified project for Grays 
Harbor and Chehalis River. 
Construction, operation, and maintenance of 
recreation facilities. 
Maintain 30-foot depth in channel from deep water in 
Grays Harbor to Port of Grays Harbor Commission 
terminal, which was deepened from 26 to 30 feet 
with Navy funds. 
14-foot channel to Bay City; breakwater at 
Westhaven; protection of Point Chehalis; and 
maintenance of Westhaven entrance channel.7 
Dredging and maintenance of a 30-foot channel and 
turning basin from Aberdeen to Cosmopolis. 
Additional breakwater, 1,400 feet long, at Westhaven 
Cove. 
LAKE CROCKETT, WA 
Small-boat basin. 
Construction, operation, and maintenance of 
recreation facilities.
38-19 
Sec. 107, P.L. 86-645 
Authorized by Chief of 
Engineers, July 9, 1981 
Annual Report, 1895, 
pp. 3517-3533 
Rivers and Harbors 
Committee Doc. 2, 59th 
Cong., 2d Sess. 
H. Doc. 507, 59th Cong., 
1st Sess. 
Rivers and Harbors 
Committee Doc. 29, 
61st Cong., 2d Sess. 
H. I)oc. 1125, 60th Cong., 
2d Sess. 
H. Doc. 1729, 64th Cong., 
2d Sess. 
H. Doc. 582, 69th Cong., 
2d Sess. 
H. Doc. 315, 70th Cong., 
1st Sess. 
Rivers and Harbors 
Committee Doc. 2, 74th 
Cong., 1st Sess. 
H. Doc. 53, 73d Cong., 1st 
Sess.; Rivers and 
Harbors Committee 
DI)oc. 2, 74th Cong., 
1st Sess. 
Sec. 4, Flood Control Act 
of 1944 
Report in Office, Chief of 
Engineers 
H. DI)oc. 635, 80th Cong., 
2d Sess. 
H. Doc. 412, 83d Cong., 
2d Sess. 
H. Doc. 30, 84th Cong., 
1st Sess. . 
H. Doc. 303, 77th Cong., 
1st Sess. 5 
Sec. 4, Flood Control Act 
of 1944 
9.

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 38-B 
(Continued) 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
June 25, 1910 
Mar. 4, 1913 
Aug. 8, 1917 
Sep. 22, 1922 
June26,1934' 
Aug. 30,19359 
DI)ec. 22, 1944 
as amended 
July 13, 1892 
July 3, 1930 
Mar. 2, 1945 
Sep. 3, 1954 
Mar. 2, 1919 
Mar. 3, 1925 
July 3, 1930 
Aug. 30, 1935 
July 13, 1892 
10. LAKE WASHINGTON SHIP CANAL, WA 
For a double lock and fixed dam with gated spillway 
and necessary accessory works at entrance to 
Salmon Bay; dredging a channel from locks to deep 
water in Puget Sound, and excavation by local 
interests of a channel from locks into Lake 
Washington. 
Dredging below locks and revetting canal basis. 
Increased dimensions of channel between Puget 
Sound and locks and a 600-foot extension of lower 
guide pier. 
Operating and care of locks and dam provided for 
with funds from War DI)epartment appropriations for 
Rivers and Harbors. 
Enlarge channel between locks and Lake 
Washington. 
Construction, operation, and maintenance of 
recreation facilities. 
PUGET SOUND AND ITS TRIBUTARY 
WATERS, WA 
Maintenance of the rivers tributary to Puget Sound 
by snagging and dredging; and removal of floating 
debris from Seattle Harbor. 
QUILLAYUTE RIVER, WA 
Jetty (5 feet high) on easterly side of mouth, and a 
dike with groins, on westerly side, to stabilize 
entrance." 
Maintenance dredging to provide a channel 6 feet 
deep and of suitable width from ocean to within 
river mouth. 
Raising jetty to 15 feet; channel 10 by 100 feet, 2,000 
feet long; moorage basin.' 2 
SEATTLE HARBOR, WA 
Maintenance of East and West Waterways 750 feet 
wide and 34 feet deep, and of Duwamish Waterway 
20 feet deep and 150 feet wide as far south as Eighth 
Avenue South Bridge. 
Enlargement of Duwamish Waterway.' ' 
Maintenance of East Waterway between 750-foot 
section and Spokane Street, and turning basin at 
junction of East and Duwamish Waterways. 
SWINOMISH CHANNEL, WA 
Channel 4 feet deep and 100 feet wide, and dike 
construction. 
38-20 
H. Doc. 953, 60th Cong., 
1st Sess. 
H. D)oc. 800, 64th Cong., 
1st Sess. 
H. I)oc. 324, 67th Cong., 
2d Sess. 
H. I)oc. 140, 72d Cong., 
1st Sess. 
Sec. 4, Flood Control Act 
of 1944 
Annual Report for 1893, 
page 3425" 
H. I)oc. 125, 71st Cong., 
1st Sess. 
H. I)oc. 218, 78th Cong., 
1st Sess. 
H. Doc. 579, 81st Cong., 
2d Sess.- 
S. Doc. 313, 65th Cong., 
3d Sess. 
H. Doc. 108, 68th Cong., 
1st Sess. and H. Doc. 
126, 71st Cong.,2d Sess. 
H. Doc. 211, 72d Cong., 
1st Sess. 
H. I)oc. 31, 52d Cong., 
1st Sess., and Annual 
Report, 1892, p. 2752 
13. 
14. 
15. 
16.

TABLE 38-B 
(Continued) 
SEATTLE, WASHINGTON DISTRICT 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Aug. 30, 1935 
Oct. 23, 1962 
June 13, 1902 
July 3, 1930 
Aug. 26, 1937 
Aug. 30, 1935 
Sep. 3, 1954 
Oct. 23, 1962 
18. 
July 27, 1916 
Aug. 30, 19359 
Aug.30,193514 
Mar. 2, 1945 
Sep. 3, 1954 
19. 
May 17, 1950 
20. 
July 24, 1946 
21. 
May 17, 1950 
Aug. 6, 1958 
June 22, 1936 
Dec. 22, 1944 
as amended 
17. 
Enlargement of channel to present project 
dimensions. 
Removal of navigation hazards at "Hole-in-the-Wall". 
TACOMA HARBOR, WA 
City Waterway. 
Hylebos Waterway. 
Training walls at mouth of Puyallup River (previously 
authorized by Public Works Administration Sep. 
6, 1933). 
Blair Waterway extension. 
Blair and Hylebos Waterways extension. 
WILLAPA RIVER AND HARBOR AND 
NASELLE RIVER, WA 
Channel 24 feet deep, 200 feet wide, in Willapa River, 
and 150 feet wide in the forks. 
Maintenance of channel over bar to a depth of 26 feet 
and minimum width of 500 feet. 
For cutoff channel at Narrows. 
Channel from deep water in Palix River to Bay 
Center dock. 
Widen Willapa River channel to 360 and 250 feet 
between South Bend and the forks; Tokeland and 
Nahcotta basins; and Naselle River clearance. 
CLARK FORK RIVER, MISSOULA, MT 
Construction of levee and floodgate structure at 
area 5, levee and floodwall at area 3, and levee 
extension at area 3. 
HOH RIVER, NEAR FORKS, WA 
Construction of riprap bank 
protection. 
HOWARD A. HANSON DAM, WA 
Eagle Gorge flood control dam on Green River. 
Redesignation of project as Howard A. Hanson Dam. 
MUD MOUNTAIN DAM, WA 
Flood control dam on White River. 
Construction, operation, and maintenance of 
recreation facilities.
38-21 
S. Committee Print, 73d 
Cong., 1st Sess. 
H. Doc. 499, 87th Cong., 
2d Sess.5 
H. Doc. 76, 56th Cong., 
2d Sess. 
Rivers and Harbors 
Committee Docs. 25, 
71st Cong., 2d Sess., 
and 91, 74th Cong., 
2d Sess. 
Rivers and Harbors 
Committee Doc. 55, 
72d Cong., 2d Sess. 
H. Doc. 171, 84th Cong., 
2d Sess. 
S. Doc. 101, 87th Cong., 
2d Sess.5 
H. Doc. 706, 63d Cong., 
2d Sess. 
Rivers and Harbors 
Committee Doc. 41, 
72d Cong., 1st Sess. 
Rivers and Harbors 
Committee DI)oc. 37, 
73d Cong., 2d Sess. 
H. Doc. 481, 76th Cong., 
2d Sess. 
H. Doc. 425, 83d Cong., 
2d Sess. 
H. Doc. 531, 
81st Cong., 2d Sess. 
Sec. 14, P.L. 79-526 
Authorized by Chief of 
Engineers, Dec. 2, 1981 
H. Doc. 271, 81st Cong., 
1st Sess.5 
P.L. 85-592 
S. Comm. Print, 
Puyallup River, WA, 
74th Cong., 2d Sess. 
Sec. 4, Flood Control Act 
of 1944 
24.

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 38-B AUTHORIZING LEGISLATION 
(Continued) 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
25. PLACER CREEK. ID 
Dec. 15, 1970 
June 22, 1936 
June 28, 1938 
June 22, 1936 
Dec. 22, 1944 
as amended 
Oct. 23, 1962 
D)ec. 22, 1944 
as amended 
Mar. 7, 1974 
Mar. 7, 1974 
July 24, 1946 
May 17, 1950 
Dec. 22, 1944 
as amended 
July 24, 1946 
June 30, 1948 
July 9, 1952 
Dec. 22, 1944 
as amended 
Oct. 22, 1976 
as amended 
on May 4, 1977 
May 17, 1950 
27. 
Construction of 3,700 feet concrete channel to confine 
Placer Creek flows through Wallace, Idaho. 
STILLAGUAMISH RIVER, WA 
Improvement of flood channel by clearing and bank 
revetment at 26 places; concrete weir at head of 
Cook Slough; and 2 cutoff channels in Cook Slough. 
Maintenance of improvements. 
TACOMA, PUYALLUP RIVER, WA 
Channel improvement to protect people and industrial 
section of city of Tacoma. 
Construction, operation, and maintenance of 
recreation facilities. 
WYNOOCHEE LAKE, WA 
Dam and reservoir for water supply, flood control, 
irrigation, fish and wildlife, and recreation. 
Construction, operation, and maintenance of 
recreation facilities. 
Transfer to State of Washington as a part of project 
costs $696,000 for construction of fish hatchery 
facilities. 
Amend contract between city of Aberdeen and 
United States for use of storage space, permitting 
deferral of the major portion of the first 10-year 
payments. 
YAKIMA RIVER, YAKIMA, WA 
Construction of riprap bank protection. 
ALBENI FALLS DAM, ID 
Multi-purpose dam with powerhouse. 
Construction, operation, and maintenance of 
recreation facilities. 
CHIEF JOSEPH DAM - RUFUS WOODS 
LAKE, WA 
Multi-purpose dam and powerhouse on Columbia 
River at Foster Creek. 
Redesignation of the project as Chief Joseph Dam. 
Designation of reservoir as Rufus Woods Lake. 
Construction, operation, and maintenance of 
recreation facilities. 
School facilities for education of dependents of 
construction personnel. 
LIBBY DAM - LAKE KOOCANUSA, MT 
Multi-purpose dam and powerhouse, and 
reregulating facilities.
38-22 
H. Doc. 357, 91st Cong., 
2d Sess.5 
H. Doc. 657, 71st Cong., 
3d Sess.- 
P.L. 75-761 
S. Comm. Print, 
Puyallup River, Wash, 
74th Cong., 2d Sess. 
Sec. 4, Flood Control Act 
of 1944 
H. I)oc. 601, 87th Cong., 
2d Sess. 
Sec. 4, Flood Control Act 
of 1944 
P.L. 93-251 
P.LI. 93-251 
Sec. 14, P.LI. 79-526 
Authorized by Chief of 
Engineers, I)ec. 2, 1981 
S. l)oc. 9, 81st Cong., 
Ist Sess.' 
Sec. 4, Flood Control Act 
of 1944 
H. D)oc. 693, 79th Cong., 
2d Sess. 
P.L. 858, 80th Cong,. 
2d Sess. 
P.L. 469, 82d Cong., 
2d Sess. 
Sec. 4, Flood Control Act 
of 1944 
P.L. 94-587 
P.L. 95-26 
H. Doc. 531, 81st Cong., 
2d Sess. 
28. 
29. 
30. 
31. 
32. 
33.

TABLE 38-B 
(Continued) 
SEATITLE, WASHINGTON DISTRICT 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Nov. 7, 1966 
Jan. 2, 1968 
Aug. 13, 1968 
June 19, 1970 
Dec. 31, 1970 
Dec. 31, 1970 
Mar. 7, 1974 
Mar. 7, 1974 
Mar. 7, 1974 
Mar. 7, 1974 
Mar. 7, 1974 
School facilities for education of dependents of 
construction personnel, Libby project. 
Airport facility at Kelley Flats, MT. 
Design standards for relocation of Montana State 
Highway 37 to be those adopted by State of 
Montana pursuant to provisions of Highway Safety 
Act of 1966. 
Participation with State of Montana in construction, 
operation and maintenance of fish hatchery 
facilities. 
Designation of lake formed by the waters impounded 
by Libby Dam as Lake Koocanusa. 
Design and construction of sewage collection and 
sewage treatment facility as part of relocation of 
municipal facilities of Rexford, MT; and 
compensation for railroad employees suffering longterm 
economic injury through reduction of income 
as result of the relocation of rail transportation 
facilities due to the construction of Libby Dam. 
Phase I design memorandum stage for installation 
of power generating facilities at Libby Reregulating 
Dam. 
Construction of fish production measures to 
compensate for fish losses attributed to the project, 
and for acquisition of necessary real estate, 
construction of access roads and utilities (Amends 
P.L. 91-282 by increasing limitation from $750,000 
to $4,000,000). 
Acquisition of land not to exceed $2,000,000 for 
prevention of wildlife grazing losses caused by the 
project. 
Reimbursement (not to exceed $350,000) to Boundary 
County, ID for reconstruction of I)eep Creek 
Bridge made necessary by duration of high flows 
during drawdown operations at Libby I)am. 
Compensation, not to exceed $1,500,000, to Drainage 
Districts and owners of leveed and unleveed lands, 
in Kootenai Flats, Boundary County, ID, for 
damages caused by duration of higher flows during 
drawdown operations at Libby Dam. 
P.L. 89-789 
P.L. 90-2391 
P.L. 90-483'" 
P.L. 91-282' 
P.L. 91-625 
P.I. 91-611 
S. l)oc. 93-29, 93d Cong., 
1st Sess., P.L. 93-251 
P.LI. 93-251 
P.LI. 93-251 
P.L. 93-251 
P.I. 93-251 
'Contains latest published map of Squalicum Creek 
Waterway. 
2Contains latest published map of small-boat basin. 
3Contains latest published map of Whatcom Creek 
Waterway. 
4D)eferred. 
5Contains latest published map. 
"Inactive. 
7A portion deferred. 
*Permanent Appropriations Repeal Act. 
9Included in Public Works Administration Program. 
'�Annual Report for 1913 contains latest published map 
(page 3127). 
"A portion inactive. 
''Maintenance of these items, as well as sandspit north 
of James Island, is included in this modification. 
':Includes settling basin of 100,000 cubic yards capacity 
which has been classified as inactive. 
"Included in Emergency Relief Program, May 28,1935. 
''Supplemental Appropriations Act of 1968, Section 
502. 
'"Flood Control Act of 1968, Section 212. 
'7River Basin Monetary Authorization and Miscellaneous 
Civil Works Amendments Act of 1970, Section 7. 
38-23

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 38-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to Sep. 30, 1983 
Full Report Operation 
See Annual and 
Project Status Report For Construction Maintenance' 
Anacortes Navigation 
Channel, WA' 5 Completed 1977 825,2632 - 
Bellingham Harbor, WA (I&J 
Street Waterway) 15 Completed 1966 125,634 6,570 
Bellingham, Squalicum Small 
Boat Harbor, WA15 Completed 1981 1,703,235' - 
Blaine Harbor, WA Completed 1958 346,650 32,642 
Columbia River, Wenatchee 
to Kettle Falls, WA Completed 1923 274,3904 7,693 
Edmonds Harbor, WA 17 Completed 1966 - 16,889 
Flathead River, MT Completed 1901 9,811 - 
Hammersley Inlet, WA Completed 1950 9,000 30,707 
Hoquiam River, WA Completed 1950 51,294 13,221 
Kenmore Navigation 
Channel, WA' 5 Completed 1982 946,0001 - 
Kingston Harbor, WA Completed 1967 262,5707 25,942" 
Kootenai River, ID and MT Completed 1933 9,255 5,643 
Mats Mats Bay, WA15 Completed 1970 137,6798 28,736 
Neah Bay, WA Completed 1982 2,057,266 1,834,466 
Okanogan and Pend Oreille 
Rivers, WA Abandoned 1913 63,880 7,634 
Olympia Harbor, WA Deferred 1975 442,7829 651,630" 
Polson Bay, Flathead Lake, 
MT Completed 1918 4,491 259 
Port Angeles Harbor, WA Completed 1960 470,873 53,268 
Port Gamble Harbor, WA Completed 1953 11,911" 51,410 
Port Orchard Bay, WA Completed 1928 42,804 12,731 
Port Townsend, WA Completed 1974 480,899 'z 57,441 
Shilshole Bay, Seattle, WA Completed 1962 2,575,091 61,294 
Skagit River, WA Completed 1950 102,330'' 60,265 
Stillaguamish River, WA Inactive 1946 4,234'14 - 
Waterway Connecting Port 
Townsend and Oak Bay, WA Completed 1975 73,322 248,712 
Westhaven Cove Small Boat 
Basin, WA' 5 Completed 1981 2,000,00016' - 
1Includes applicable portion of reconnaissance and condition 
survey costs. 
2Excludes $457,200 contributed funds expended. 
3lncludes $132,349 preauthorization cost and excludes 
$1,626,000 contributed funds expended. 
4Includes $8,005 expended for previous project. 
5lncludes $148,765 preauthorization cost. 
6Includes $5,000 for mitigation shore damages study 
expended. 
'Excludes $117,585 contributed funds expended. 
8Excludes $28,288 contributed funds expended. 
9Includes $183,257 for previous projects, and $2,803 
expended for restudy Fiscal Years 1971-1973. 
"'Includes $14,418 expended for previous project. 
"Excludes $21,260 contributed funds expended. 
' Excludes $85,223 contributed funds expended. 
1:Includes $2,500 expended for previous project. 
14Foreconomic study only. 
' Autlhorized by Chief of Engineers under authority of 
Section 107, Public Law 86-645. 
'6Includes $178,371 preauthorization cost and excludes 
$1,251,000 contributed funds expended. 
"'Constructed by local interests. 
38-24

SEATTLE, WASHINGTON DISTRICT 
OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
Project 
American Lake, Vicinity of Fort 
Lewis, WA1 
Bear Creek, Flathead County 
Bridge, near Essex, MT2 
Blackfoot River, Matt Little Road, 
MT2 
Bogachiel River, Highway 101, 
near Forks, WA 2 
Bogachiel River, Undie Road, 
Forks WA2 
Cedar River, Renton, WA2 
Chehalis River, City of Chehalis, 
Raw Water Pumphouse, WA2 
Chehalis River, Independence 
Road Thurston County, WA2 
Chehalis River, Montesano, WA2 
Clallam Bay, Sekiu, WA 2 
Clallam River, Highway 112, 
WA2 
Clark Fork River, Drummond, 
MT2 
Clark Fork River, Missoula, MT2 
Clark Fork River, Superior, MT 2 
Clark Fork River, Vicinity of 
Plains, MT2 
Clearwater River, Jefferson 
County Road, WA2 
Clearwater, River, Queets River 
Bridge, WA2 
Coeur d'Alene, Spokane River, ID 
Coeur d'Alene River, Springston, 
ID2 
Columbia River Basin, Local 
Protection Projects, ID, MT, and 
WA: 
Entiat River, WA 
Lightning Creek, Clark Fork, ID 
Methow River, WA 
Okanogan River, WA 
Yakima River at Ellensburg, WA 
Deschutes River, Gleason Road 
Bridge, near Tumwater, WA 2 
Deschutes River, Rich Road 
Bridge, near East Olympia, WA 2 
For Last Cost to Sep 30, 1983 
Full Report Operation 
See Annual and 
Status Report for Construction Maintenance 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Inactive 
Completed 
Inactive 
Inactive 
Inactive 
Completed 
Completed 
1957 
1971 
1964 
1981 
1981 
1949 
1966 
1965 
1977 
1977 
1981 
1978 
1978 
1971 
1950 
1968 
1950 
1941 
1950 
1958 
1959 
1958 
1958 
1980 
1965 
1967 
59,5826 
1,424 
17,836 
156,000 
57,000 
32,264 
35,454 
47,916 
140,080 
48,698 
43,500 
18,660 
31,548 
28,356 
27,947 
50,0006 
49,165 
152,872 
25,452 
42,726 
1,1007 
30,0008 
26,292 
22,956 
38-25 
TABLE 38-E

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 38-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(Continued) 
Project 
Dungeness River, Area #5, WA2 
Dungeness River, Area #8, WA2 
Dungeness River, Clallam County, 
WA' 
Dungeness River, Sequim, WA2 
Dungeness River, Taylor Cut-off 
Road, WA2 
Elwha River, Clallam County, WA2 
Entiat River, Chelan County, WA2 
Flathead River, MT2 
Flathead River, Bradley Channel 
Area, MT2 
Flathead River, near Kalispell, MT2 
Flathead River, near 
Kalispell, MT 
Flathead River, Old Steel Bridge, 
near Kalispell, MT2 
FosterCreekRoad,DouglasCounty, 
WA2 
Green River between Kent and 
Auburn, WA and Allentown, WA2 
Green River, State Highway 181, 
WA2 
Henderson Bay, Purdy, WA2 
Hoh River, County Road 16, WA 2 
Hoh River, U.S. Highway 101, WA2 
Hoh River Road, Jefferson County, 
WA (HO 1360)2 
Hoh River Road, Jefferson County, 
WA (HO 1361)2 
Hoh River Road, Jefferson County, 
WA (HO 1362)2 
Hoko River, Sekiu, WA2 
Hood Canal, Hoodsport, WA2 
Hoquiam River, WA2 
Kootenai River, Bonners Ferry, ID2 
Kootenai River, Kootenai Flats 
Area, District #1, ID2 
La Conner, Swinomish Channel, 
WA2 
Methow River, WA (MET 1-74)2 
Methow River, WA (MET 2-74)2 
Methow River, WA (MET 3-74)2 
Methow River, Barclay Canal, 
WA2 
Methow River, Twisp, WA 2 
Status 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Deferred 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
22,082" 
11,916 
41,622 
21,083 
59,812 
52,600 
42,325 
14,885 
40,525 
15,700 
11,200 
13,450 
19,810 
31,783 
38-26 
For Last 
Full Report 
See Annual 
Report for 
1950 
1950 
1964 
1981 
1961 
1951 
1978 
1972 
1955 
1948 
1981 
1964 
1962 
1972 
1976 
1977 
1980 
1980 
Cost to Sep 30, 1983 
Operation 
and 
Construction Maintenance 
2,155 - 
2,895 - 
52,0409 - 
99,000 - 
14,093' 0 
17,303- 
38,000- 
20,940- 
26,265- 
33,347- 
300,000' - 
13,438- 
50,000- 
24,605- 
27,001- 
37,359- 
143,000- 
194,000- 
1956 
1961 
1964 
1977 
1977 
1977 
1950 
1965 
1979 
1974 
1974 
1974 
1976 
1949

SEATTLE, WASHINGTON DISTRICT 
OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
Project 
Methow River, Twisp-Carlton 
Highway, Vicinity of Twisp, WA2 
Methow River, Vicinity of 
Pateros, WA2 
Mineral Creek, Lewis County, 
WA2 
Moclips River, Moclips, WA2 
Naches River, Naches, WA2 
Newaukum River, Lewis County, 
Hamilton,WA2 
Nisqually River, near Elbe, WA2 
Nisqually River, Thurston 
County, WA2 
Nisqually River, Vicinity of Elbe, 
WA2 
Nooksack River, Guide Bridge 
Location, WA 2 
Nooksack River, above Highway 
1Z Bridge, WA2 
North Fork Skykomish River, 
WA 2 
Okanogan River, WA2 
Okanogan River, Omak, WA' 
Okanogan River, Oroville, 
WA 
Pilchuck River, WA2 
Pilchuck River, Everett, WA2 
Pilchuck River, State Highway, 
92, Granite Falls, WA2 
Powell County High School, Deer 
Lodge, MT2 
Pysht River, Sekiu, WA2 
Queets River, Jefferson County 
Sewage Lagoon, WA2 
Quillayute River, Quileute Tribal 
Float and Bridge, WA2 
Quinalt River, Grays Harbor, 
WA2 
Quinalt River Road, Jefferson 
County, WA 2 
Rock Creek, Granite County, MT2 
Rock Creek, Missoula County, 
MT2 
Rock Creek Road, MT2 
Rye Creek, MT2 
St. Maries, St. Joe River, ID 
Sammamish River, WA 
For Last Cost to Sep 30, 1983 
Full Report Operation 
See Annual and 
Status Report for Construction Maintenance 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
1951 
1951 
1972 
1977 
1982 
1972 
1948 
1960 
1952 
1950 
1960 
1981 
1974 
1981 
1982 
1971 
1980 
1971 
1964 
1977 
1981 
1972 
1981 
1961 
1974 
1973 
1980 
1973 
1942 
1967 
33,200 
11,726 
11,836 
17,608 
59,000 
24,792 
37,636 
26,790 
19,445 
6,075 
10,807 
222,500 
10,100 
2,230,000'2 
1,779,500';' 
10,713 
54,000 
30,973 
11,291 
86,160 
125,000 
39,300 
208,000 
15,928" 
49,657 
31,565 
50,000 
22,819 
357,698 
2,582,5361s 
38-27 
TABLE 38-E 
(Continued)

TABLE 38-E 
(Continued) 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
Project 
Sauk River, WA 2 
Sewage Treatment Plant, 
Missoula, MT2 
Shelton Creek, WA' 
Skagit River, WA. 
(Avon Bypass) 
Skagit River, WA. (Levee and 
Channel Improvements) 
Skagit River, Cape Horn Road, 
WA 2 
Skagit River, Deadman's Slough, 
WA 2 
Skagit River, Pressentin Creek, 
WA 2 
Skagit River, South Skagit 
Highway, WA2 
Skagit River, South Skagit 
Highway, WA (Job 66-1)2 
Skagit River, South Skagit 
Highway, WA (Job 67-1)2 
Snohomish River, Lowell- 
Snohomish River Road, WA2 
Snohomish River, Snohomish, 
WA2 
Snoqualmie River, West 
Snoqulamie, WA2 
Soleduck River Bridge, WA2 
Soleduck River, near Mora Road 
Bridge, WA2 
Spokane, Spokane River, WA 
Startup, Skykomish and Wallace 
Rivers, WA' 
Stillaguamish River, South Fork, 
Mountain Loop Highway, near 
Robe, WA2 
Stillwater River, MT2 
Stillwater and Whitefish Rivers, 
MT2 
Strong Creek, Hope, ID2 
Tahola, WA2 
Upper Puyallup River, WA3 
Wenatchee Canyons 1 and 2, WA 4 
West Fork Foster Creek, WA2 
Willapa River at Raymond, WA 
Wynoochee River, County Road 
141, WA2 
. ... 
For Last 
Full Report 
See Annual 
Report for 
1974 
1965 
1979 
1968 
1982 
1966 
1980 
1980 
1963 
1966 
Status 
Completed 
Completed 
Completed 
Deferred 
Inactive 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Inactive 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Active 
Completed 
Deferred 
Completed 
Cost to Sep 30, 1983 
Operation 
and 
Construction Maintenance 
20,860- 
50,00016 
872,0211 7 
54,4687 
1,934,79218's 
46,489- 
93,000- 
137,000- 
40,753- 
17,719- 
50,000'9 
44,227 
60,90021 
15,565 
16,43621 
11,433 
2,9447 
271,713 
50,00022 
17,457 
34,513 
8,442 
223,893 
71,49523 
544,331 
19,513 
508,13024 
111,072 
38-28
1967 
1969 
1970 
1977 
1961 
1963 
1939 
1970 
1964 
1973 
1977 
1970 
1979 
1938 
1977 
1958 
1982 
1976

SEATTLE, WASHINGTON DISTRICT 
TABLE 38-E 
(Continued) 
OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to Sep 30, 1983 
Full Report Operation 
See Annual and 
Project Status Report for Construction Maintenance 
Wynooche River, near 
Montesano, WA2 Completed 1969 50,00025 
Wynoochee River, near 
Montesano, WA (WR-1-72)2 Completed 1972 50,000 - 
Yakima, Yakima River, WA Completed 1948 381,961 - 
Yakima River, Cle Elum, WA2 Completed 1949 8,047 - 
Yakima River, below mouth of 
Teanaway River, near Cle 
Elum, WA2 Completed 1947 48,272- 
Yakima River, West Richland, 
WA2 Completed 1977 36,768- 
'Authorized by Chief of Engineers under authority of '"Includes $125,000 preauthorization cost. 
Section 205, Public Law 858, 80th Congress, as amended. ':Includes $160,700 for preauthorization cost. 
2Authorized by Chief of Engineers under authority of "Excludes $4,843 contributed funds expended. 
Section 14, Public Law 526, 79th Congress, as amended. '-Excludes $696,923 contributed funds expended. 
'Authorized by Works Progress Administration Project Includes $117,420 preconstruction planning. 
No. OP 65-93-917. 'Excludes $5,340 contributed funds expended. 
4Authorized by Secretary of Army under authority of 'Includes $100,221 preauthorization cost. 
Section 201, Public Law 298, 89th Congress, H. Doc. 91-370. 'Includes $1,806,792 for preconstruction planning cost. 
5Excludes $10,000 contributed funds expended. '"Excludes $24,488 contributed funds expended. 
6Excludes $24,728 contributed funds expended. 2 Excludes $14,307 contributed funds expended. 
7Preconstruction planning only. 2 'Excludes $1,960 contributed funds expended. 
8Excludes $14,300 for restudy. 22 Excludes $46,182 contributed funds expended. 
9Excludes Public Works Acceleration Act funds of ':Emergency Relief Funds, Works Progress Admini- 
$340,066. stration. Excludes $13,704 contributed funds expended. 
'Excludes $3,314 contributed funds expended. 'Includes $32,630 for preconstruction planning cost. 
"Excludes $21,807 contributed funds expended. 25Excludes $21,311 contributed funds expended. 
TABLE 38-F OTHER AUTHORIZED MULTIPLE PURPOSE 
PROJECTS, INCLUDING POWER 
For Last Cost to Sep. 30, 1983 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Priest Rapids Dam, Columbia River, WA 1954 350,000' 
'For partnership planning. Excludes funds expended 
for acquisition of lands under partnership arrangement for 
Priest Rapids and Wanapum Dams, in accordance with 
Public Law 544, 83d Congress. Project constructed by Grant 
County Public Utility District. 
38-29

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 38-G DEAUTHORIZED PROJECTS 
For Last Contri- 
Full Report Date Federal buted 
See Annual Deauth- Funds Funds 
Project Report For orized Expended Expended 
Columbia River Basin, Local 
Protection Projects, ID, MT, 
and WA: 
Crab and Wilson Creeks, WA 1958 1964 $ 9,1001 
St. Regis River, MT 1958 1978 4,4002 
Wenatchee River, WA 1958 1978 2,000;- 
Hammersley Inlet, WA 1950 1978 -- 
(Uncompleted Portion) 
Port Angeles Harbor, WA 1960 1977 - - 
(Uncompleted Portion)* 
Port Gamble Harbor, WA 1953 1977 - - 
(Uncompleted Portion) 
Skagit River, WA 1950 1978 - - 
(Uncompleted Portion) 
'Includes $100 for preauthorization studies and $9,000 2Includes $3,000 for preauthorization studies and $1,400 
for preconstruction planning. for preconstruction planning. 
'Preauthorization studies only. 
TABLE 38-H LAKE WASHINGTON SHIP CANAL, WA 
PRINCIPAL FEATURES OF DOUBLE LOCK AND DAM 
(See Section 10) 
Section Large Lock Small Lock 
Miles above mouth 1% 11 
Clear width of chamber Feet 80 28 
Maximum available length Feet 760 123 
Lift Feet 26 26 
Depth on upper miter sill' Feet 36 16 
Depth on intermediate miter sill2 Feet 29 - 
Depth on lower miter sill2 Feet 29 16 
Character of foundation Clay Clay 
Kind of dam Fixed dam with Fixed dam with 
gated spillway. gated spillway. 
Type of construction Concrete Concrete 
Year completed 1916 1916 
Cost 3 3 
'Low water in upper pool. 
-'Mean lower low water in Puget Sound. 
3Cost of double lock and dam was $2,224,712 and the 
emergency gates, completed in 1923, $174,693. 
38-30

SEATTLE, WASHINGTON DISTRICT 
PROJECT CONDITION SURVEYS 
Name of Project Date Survey Conducted 
Washington: 
Anacortes Harbor 
Anacortes Navigation Channel 
Bellingham Harbor 
Blaine Harbor 
Edmonds Harbor 
Hoquiam River 
Kingston Harbor 
Lake Crockett 
Olympia Harbor 
Port Gamble Harbor 
Shilshole Bay, Seattle 
Tacoma Harbor 
Waterway Connecting Port 
Townsend and Oak Bay 
January 1983 
October 1982 
October 1982 
October 1982 
October 1982 
February 1983 
October 1982 
May 1983 
December 1982 
October 1982 
November 1982 - June 1983 
August 1983 
October 1982 
TABLE 38-J Flood Control Activities Pursuant to Section 205, 
Public Law 858, 80th Congress, as amended 
(Preauthorization) 
Study Identification Fiscal Year Costs (1983) 
Bowman Hilton Mobile Home Park, WA $ 70,561 
Cottonwood Creek, Deer Lodge, MT 77,757 
Dosewallips River, Brinnon, WA 239,961 
Elwha Klallam Reservation, Elwha River, WA 148,210 
Snohomish River, WA1 7,500 
Sultan, WA 115,150 
TOTAL $ 659,139 
1Unfavorable reconnaissance report. 
38-31 
TABLE 38-I

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 38-K Emergency Flood Control Activities 
Repair, Flood Fighting, and Rescue Work 
(Public Law 99, 84th Cong., and antecedent legislation) 
Project and Location Fiscal Year Costs (1983) 
Advance preparation $ 204,745 
Flood emergency operations 33,479 
Repair and restoration: 
Kittitas County, WA' 2,687 
Kootenai County, ID -2,999 
Mutch Creek, at St. Maries, ID 236,577 
Yakima County, WA 2 -4,614 
TOTAL $ 469,875 
'Investigation only. 
2Excludes $2,673 contributed funds expended. 
38-32

WALLA WALLA, WA, DISTRICT* 
This District consists of all Columbia River drainage 
and tributaries thereto between the head of the McNary 
pool (River Mile 345.4) and the Umatilla Bridge below 
McNary Dam, except the Yakima River Basin above 
the Van Giesen Street Bridge near Richland, WA. 
IMPROVEMENTS 
Flood Control 
1. Columbia River Basin, Local 
Flood Protection Projects ................ 
2. Cottonwood Creek Community Church, 
Culdesac, ID ........................... 
3. Flood Control Work Under 
Special Authorization .................. 
4. Inspection of Completed Flood 
Control Projects........................ 
5. Inspection of Non-Federal Levees ........ 
6. Lucky Peak Lake, ID................... 
7. Mill Creek Lake, WA ................... 
8. Ririe Lake, ID .......................... 
9. Scheduling Flood Control 
Reservoir Operations .................... 
10. Sewage Lagoons, Vale, OR ............. 
11. Willow Creek Lake, Heppner, OR ....... 
12. Zintel Canyon Dam, WA ............... 
Page 20. McNary Lock and Dam-Lake Wallula- Page 
OR and WA ............................ 39-8 
39-2 21. Snake River Downstream from Johnson 
Bar Landing, OR, WA and ID ........... 39-9 
39-2 
39-2 
39-2 
39-2 
39-2 
39-3 
39-3 
39-4 
39-4 
39-4 
39-4 
Multiple-Purpose Projects, Including Power 
13. Dworshak Dam and Reservoir, ID ....... 3 
14. Ice Harbor Lock and Dam-Lake 
Sacajawea-WA ....................... 3 
15. Lewiston-Clarkston Bridge, 
ID and WA ............................ 3 
16. Little Goose Lock and Dam- 
Lake Bryan-WA ...................... 3 
17. Lower Granite Lock and Dam, WA ....... 3 
18. Lower Monumental Lock and 
Dam-Lake Herbert G. West-WA ....... 3 
19. Lower Snake River Fish & Wildlife 
Compensation Plan, WA, OR, ID ........ 3
9-5 
9-5 
9-6 
9-6 
9-7 
9-7 
9-8 
General Investigations 
22. .Surveys................................ 39-9 
23. Collection and Study of Basic Data ...... 39-10 
24. Continuation of Planning 
and Engineering ....................... 39-10 
Tables 
Table 39-A Cost & Financial Statement ... 39-11 
Table 39-B Authorizing Legislation ,....... 39-14 
Table 39-C Other Authorized Navigation 
Projects ...................... 39-17 
Table 39-E Other Authorized Flood Control 
Projects ...................... 39-17 
Table 39-G Deauthorized Projects ......... 39-19 
Table 39-H Columbia River Basin, Local 
Flood Control Projects ......... 39-20 
Table 39-I Inspection of Completed 
Flood Control Projects......... 39-21 
Table 39-J Principal Data Concerning 
Navigation Lock, Spillway 
Dam, Powerplant and 
Impoundment ................. 39-22 
Table 39-K Snake River Downstream from 
Johnson Bar Landing, OR, WA 
and ID ....................... 39-26 
39-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Flood Control 
1. COLUMBIA RIVER BASIN, LOCAL FLOOD 
PROTECTION PROJECTS 
Location. Improvements included in this project 
are along Columbia River and its tributaries. 
Existing project. Flood Control Act of 1950 approved 
a general comprehensive plan for Columbia 
River Basin for flood control and other purposes based 
on plans in H. Doc. 531, 81st Cong., 2d Sess. and 
authorized $75 million to be appropriated for partial 
accomplishment of certain projects. Of that authorization, 
an amount not to exceed $15 million was allotted 
for construction of local flood protection works 
throughout Columbia River Basin, subject to conditions 
that all work undertaken pursuant to authorization 
should be economically justified prior to construction, 
and local cooperation specified in 1936 Flood 
Control Act, as amended, should be required. (See 
Tables 39-B and 39-H for projects in Walla Walla 
District.) 
Local cooperation. Section 3, Flood Control Act of 
June 22, 1936, applies. 
Operations during fiscal year. No projects were 
recommended for deauthorization during the fiscal 
year. 
2. COTTONWOOD CREEK COMMUNITY 
CHURCH, CULDESAC, ID 
Location. On Cottonwood Creek, Nez Perce County, 
ID. The project is located one mile upstream of the 
mouth of Cottonwood Creek at river mile 19 on the 
Clearwater River, near Myrtle, ID. 
Existing project. A levee was built for flood protection 
by locals in prior years. 
Local cooperation. Local entities have provided 
rights of way and other sponsorship requirements. 
Operations during fiscal year. New work: Under 
Section 14 of Public Law 79-526 bank protection was 
provided. Heavy spring runoff had damaged the levees 
and caused extensive erosion. Quarry tailings overlaid 
by placed stone riprap were placed along 300 feet 
of eroding streambank adjacent to the Cottonwood 
Creek Community Church property. 
3. FLOOD CONTROL WORK UNDER SPECIAL 
AUTHORIZATION 
Flood control activities pursuant to Section 
205, Public Law 858, 80th Congress, as amended. 
Fiscal year costs for preauthorization studies were 
$13,500 for Orofino, ID, and $32,195 for Salmon River, 
Lemhi County, ID. 
Emergency flood control activities-repair, 
flood fighting, and rescue work (Public Law 99, 
84th Congress, and antecedent legislation). 
Federal costs for fiscal year were $61,757 for disaster 
preparedness, $450,235 for emergency operations, 
$269,915 for rehabilitation, and $14,170 for advance 
measures. 
Snagging and clearing of navigable streams 
and tributaries in interest of flood control (Section 
208, 1954 Flood Control Act, Public Law 
780, 83d Congress). 
Fiscal year costs of $2,100 were incurred at Boise 
River, Ada County, ID; $5,500 at Lapwai Creek, Nez 
Perce County, ID; $5,100 at Lostine and Wallowa 
River, Enterprise, OR; $1,800 at Tucannon and Touchet 
River, WA; and $10,390 at Touchet River, Walla Walla 
County, WA. 
4. INSPECTION OF COMPLETED FLOOD 
CONTROL PROJECTS 
Federal law requires local interests to maintain and 
operate completed local protection projects in accordance 
with regulations prescribed by Secretary of 
Army. Inspections were made to determine extent of 
compliance and to advise local interests as necessary 
of measures required to correct deficiencies. See Table 
39-I for inspections made during fiscal year. 
Fiscal year costs were $95,025. Total costs to September 
30, 1983 have been $718,176. 
5. INSPECTION OF NON-FEDERAL LEVEES 
Inspections are pursuant to Public Law 84-99 which 
directs the Corps to establish through inspection whether 
non-federal flood control works will continue to provide 
the intended degree of flood protection and to 
determine if the maintenance program is adequate. 
FY 1983 costs for this program were $30,001. 
6. LUCKY PEAK LAKE, ID 
Location. On Boise River in southwestern Idaho 
about 10 miles southeast of city of Boise. 
Existing project. A rolled-earthfill dam about 250 
feet high above streambed and 1,700 feet long at crest, 
with a lake providing a total storage at upper operating 
lake level of 306,000 acre-feet. (For further details 
see page 2000 of Annual Report for 1962.) 
Construction of existing project was initiated 
November 1949 and completed June 1961. A feasible 
method of achieving better flood control through diversion 
into New York Canal, through Lake Lowell, 
and into the Snake River has been developed but 
rejected by local interests due to the infrequent use of 
this diversion method. Since 1961, $88,129,000 in 
potential flood damages have been prevented by the 
project. Final Environmental Impact Statement on 
the initial project was filed with the Council on Environmental 
Quality on November 29, 1976. A revised 
draft Environmental Impact Statement for the modification 
work was filed with the Council on Environmental 
Quality on September 18, 1978. 
During the detailed investigation of outlet capacity 
and the potential for adding hydropower to the existing 
project, a need for an auxiliary outlet became 
apparent. Construction of an auxiliary outlet was 
authorized in the Water Resource Development Act of 
1976 but to date it has not been funded. In FY 1978, an 
39-2

WALLA WALLA, WASHINGTON DISTRICT 
"Interim Feasibility Report on Modification of Lucky 
Peak Dam and Lake" (power facilities) was submitted 
to the Board of Engineers for Rivers and Harbors and 
approved. States, agencies, and the Chief of Engineers 
have commented on the report to the Secretary 
of the Army. The report was forwarded to the Office of 
Management and Budget in February 1982. No further 
action has been taken. 
A license to construct and operate power facilities at 
the project was issued by the Federal Energy Regulatory 
Commission (Project #2832) to the Boise Project 
Board of Control on June 10, 1980 and modified on 
October 9, 1980. The license required that construction 
begin within two years and be completed within four 
years of the issuing date of the license. A two year 
extension of the license was granted on June 10, 1982 
by FERC. 
Local cooperation. None required. 
Operations during fiscal year. Maintenance: 
Normal operation for flood control, recreation, and 
irrigation continued. A report was initiated on the 
project's outlet works deterioration problems. The 
report is scheduled for completion and review in early 
FY 1984. 
7. MILL CREEK LAKE, WA 
Location. In and upstream from Walla Walla, WA, 
on Mill Creek, a tributary of Walla Walla River. 
Existing project. Off-stream earthfill storage dam 
about 145 feet high and 3,200 feet long at the crest, two 
concrete-lined outlet channels, an earthfill diversion 
dam, and division structures. 
Authorizing legislation to provide a channel through 
the city of Walla Walla was added to the project in 
1941. Federal cost of original project was $2,162,155. 
Adding recreation facilities has thus far increased 
project costs by $68,446 to $2,230,601. Not included in 
that cost is $80,000 contributed by local interests 
toward construction of the channel through Walla 
Walla. (For further details see page 2005 of Annual 
Report for 1962.) 
Construction of dam and appurtenant works was 
completed in 1942. Paving of channel through city of 
Walla Walla was completed in 1948. Park and recreation 
facilities were opened to the public July 1, 1964. 
Since 1942, $4,121,000 in potential flood damages 
have been prevented by the combined storage and 
channel operation. 
Final Environmental Impact Statement was filed 
with the Council on Environmental Quality on December 
12, 1975. 
The rehabilitation of the existing project is designed 
to correct the seepage and internal erosion which have 
occurred during each subsequent filling of the reservoir 
requiring limited flood control use of the project. 
Project cost estimate for the rehabilitation is 
$16,900,000 (full funding). 
Local cooperation. Fully complied with. For 
details see page 2006 of Annual Report for 1962. 
Operations during fiscal year. Major rehabilitation. 
New work: Contract for concrete cutoff wall at 
the dam is complete. Remedial action has also been 
started on deteriorated segments of the project channels. 
This work will enable the channels to handle 
short duration standard project floods. Additional 
slope treatment work was completed in FY 1983. 
Maintenance: Routine maintenance by Government 
forces continued, which included regulation of water 
control structures and care of recreation area. 
8. RIRIE LAKE, ID 
Location. On Willow Creek, a tributary of Snake 
River, in Bonneville County, ID. The channel improvement 
extends from junction of Sand and Willow 
Creeks to a point on Snake River about 4 miles 
upstream from city of Idaho Falls, ID. (See Geological 
Survey quadrangle map, Ucon, ID.) Dam is about 5 
miles below confluence of Willow Creek and Meadow 
Creek and about 15 miles northeast of city of Idaho 
Falls, ID. (See Geological Survey quadrangle map, 
Poplar, ID.) 
Existing Project. A rockfill dam about 840 feet 
long at the crest and about 184 feet high above 
streambed and downstream channel construction. 
Spillway has a concrete-lined channel in right abutment. 
Outlet works utilize a reinforced concrete conduit 
leading from an intake tower upstream to a stilling 
basin downstream at the toe of left abutment. 
Lake has gross storage capacity of 100,000 acre-feet; 
90,000 acre-feet of active space for flood control, irrigation, 
and recreation and 10,000 acre-feet of space for 
sediment storage and conservation. Floodway channel 
is about 8.0 miles long with a capacity of 900 cubic 
feet per second. Authorization specified that the project 
shall be constructed by the Corps of Engineers 
and operated and maintained by the Bureau of Reclamation. 
Construction began June 1967 and was completed 
in September 1980. All necessary real estate has been 
acquired. Entire project is complete. A Project Transfer 
Agreement with the Bureau of Reclamation was signed 
on October 14, 1976 for transfer of the project for flood 
control and recreation use only until the irrigation 
water rights and space allocation issues are resolved. 
The final Environmental Impact Statement was filed 
with the Council on Environmental Quality February 
13, 1973. 
Local Cooperation. Complete except for irrigation 
contracts. 
Operations during fiscal year. New work: In FY 
1982 a contractor's claim was disapproved by the 
courts and liquidated damage monies were subsequently 
released with $38,267 used for preliminary 
seismic stability analysis. This testing was completed 
in FY 1983. Since 1975, $270,000 in potential flood 
damages have been prevented by the project. 
39-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
9. SCHEDULING FLOOD CONTROL 
RESERVOIR OPERATIONS 
Functional regulation of non-Corps projects was 
accomplished under several authorities. Regulations 
of Palisades, Little Wood, and Anderson Ranch 
Reservoir in Idaho, and Bully Creek, Warm Springs, 
Agency Valley, and Mason Reservoirs in Oregon, was 
accomplished as authorized under Section 7, Flood 
Control Act of 1944, and coordinated with the Bureau 
of Reclamation. 
Flood control operations at Jackson Lake, Arrowrock 
Reservoir, and Lake Lowell were in accordance 
with formal agreements with the Bureau of Reclamation. 
Regulation of American Falls, Owyhee, Magic, 
Mackay, Cascade, and Deadwood Reservoirs, Idaho, 
for flood control was accomplished under informal 
agreements. Brownlee, Oxbow, and Hells Canyon 
Reservoirs provided flood control regulation in accordance 
with provisions of the Federal Power Commission 
license to Idaho Power Company. 
Fiscal year costs were $139,000. 
10. SEWAGE LAGOONS, VALE, OR 
Location. On the Malheur River, Malheur County, 
OR. The project is located on the west half of Section 
21 and east half of Section 20, T18S, R45E, Boise 
Meridian. 
Existing project. Channel rectification, levees and 
bank protection were provided to the city of Vale 
under Public Law 516 in 1960. The city has maintained 
the project and periodically placed concrete 
and asphalt rubble on the streambank for protection. 
Local cooperation. The city has sponsored the 
project and complied with sponsorship requirements. 
Operations during fiscal year. New work: Under 
Section 14 of Public Law 79-526 the unstable vertical 
bank between the city's sewage lagoons and the river 
was stabilized by placing stone riprap with bedding 
material on 800 feet of riverbank. The bank had been 
severely eroded by heavy spring runoff. Further erosion 
could have resulted in breaching of the lagoons 
and contamination of the Malheur River with the contents 
of the lagoons. 
11. WILLOW CREEK LAKE, HEPPNER, OR 
Location. On Willow Creek just upstream from 
Heppner and just downstream from junction of Balm 
Fork and Willow Creek in Section 35, Township 2 
South, Range 26 East, Willamette Meridian. 
Existing project. Project provides flood protection 
to the city of Heppner and downstream area by controlling 
runoff from a drainage area of 96 square 
miles. The dam is a roller compacted concrete structure 
160 feet high at crest elevation 2130. Ancillary 
features include a center uncontrolled spillway with a 
maximum flood capacity of 93,300 cfs, an outlet works 
with a capacity of 500 cfs, a minor flow works and 
diversion works. Gross storage capacity of the project 
is 13,250 acre-feet, consisting of 7,750 acre-feet for 
exclusive flood control, 1,750 acre-feet for joint flood 
control and irrigation, 1,750 acre-feet exclusive irrigation, 
and 2,000 acre-feet dead storage for fish, wildlife, 
recreation, sediment accumulation, and aesthetics. 
Limited recreation facilities are being provided. 
The final Environmental Impact Statement was 
filed with the Environmental Protection Agency on 
December 20, 1979. The provisions of the Clean Water 
Act were met by a Section 404(b)(1) Evaluation and a 
public notice issued January 12, 1980, and a Section 
401 certification from the State of Oregon on February 
15, 1980. Land acquisition is about 99 percent complete. 
Contracts have been completed for relocation of 
the city water main, and construction of the water 
tank, road, and main dam. Estimated Federal Cost 
(full funding) is $34,760,000. 
Local cooperation. None required. 
Operations during fiscal year. New Work: Main 
dam construction was completed in March 1983 and 
the pool raised to elevation 2018 in subsequent months 
to test for structural seepage. Evidence of seepage 
necessitated a grouting program designed to seal the 
leaks with completion scheduled in FY 1984. The project 
was credited with preventing $24,000 in flood 
damages in FY 1983. 
12. ZINTEL CANYON DAM, WA 
Location. In Zintel Canyon, 2.1 miles southwest of 
Kennewick, WA, in Section 16, Township 8, North, 
Range 29 East, Willamette Meridian. 
Existing project. The proposed project consists of 
a roller compacted concrete dam 102 feet high with 
uncontrolled spillway and a fixed maximum release 
outlet works that would create a detention reservoir of 
2,500 acre-feet of capacity. The storage comprises 
2,100 acre-feet for flood control and 400 acre-feet for 
sediment. In addition, the project also includes a 
channel with a capacity of 400 cfs. The plan of 
improvement would provide protection against heavy 
rainfall, snowmelt, and thunderstorm floods to the 
city of Kennewick, WA. 
Project adopted by resolution of House Committee 
on Public Works December 15, 1970 and by resolution 
of Senate Committee on Public Works December 17, 
1970 under authority of Section 201 of Flood Control 
Act of 1965 (P.L. 298, 89th Cong.). The final Environmental 
Impact Statement was filed with the Council 
on Environmental Quality January 8,1975. Estimated 
Federal cost (October 1983) is $8,550,000 and non- 
Federal cost $1,250,000. 
Local cooperation. The city of Kennewick, WA 
has provided a new letter of intent dated February 17, 
1982 to sponsor the project. 
Operations during fiscal year. Study update was 
completed and indicated project feasibility. 
39-4

WALLA WALLA, WASHINGTON DISTRICT 
Multiple-Purpose Projects, 
Including Power 
13. DWORSHAK DAM AND RESERVOIR, ID 
Location. Dam is on North Fork Clearwater River 
1.9 miles above its junction with Clearwater River, 
near Orofino, ID, and about 35 miles east of Lewiston, 
ID. 
Existing project. A straight concrete gravity dam 
about 717 feet in maximum structural height above 
foundation and 3,300 feet long at crest elevation 1613. 
The reservoir has a gross storage capacity of 3,453,000 
acre-feet, of which 2,000,000 acre-feet are effective for 
both local and regional flood control, and for at-site 
and downstream power generation. In addition, the 
reservoir, extending 53 miles into a rugged and relatively 
inaccessible timberland, provides important 
transportation savings in connection with movements 
of marketable logs. The project also provides substantial 
recreation benefits. Powerhouse includes two 
90,000 and one 220,000 kilowatt generating units, with 
provisions for three additional 220,000 kilowatt units 
for an ultimate installed capacity of 1,060,000 kilowatts. 
Principal project data are set forth in Table 
39-J. 
Fish passage at Dworshak Dam is not feasible due 
to the height of the dam and a hatchery has been built 
below the dam to assure continuance of anadromous 
fish runs. The reservoir area has been habitat for elk, 
deer, and other wildlife. Project plans include acquisition 
of land outside reservoir limits to mitigate losses 
of big game winter browse areas inundated by reservoir. 
Construction of the project started April 1963 and is 
complete except for recreation facilities and fish and 
wildlife development. It became operational for flood 
control June 1972 and has prevented about $728,000 in 
potential flood damages downstream since then. All 
project lands have been acquired except those required 
to replace the loss of wildlife browse areas from inundation 
by reservoir. Relocations are estimated to be 
100 percent complete; dam, 100 percent; fish and wildlife 
facilities, 96 percent; powerplant, 100 percent; 
reservoir clearing, 100 percent; and recreation facilities, 
90 percent. A reconnaissance report justifying the 
feasibility and cost benefits for the addition of a 
220,000-kilowatt fourth generating unit was completed 
in FY 1978. Environmental and economic studies on 
additional generating units have been curtailed due to 
public opposition. Units 4, 5, and 6 are now classified 
"inactive." 
Power generating Unit No. 1, 90,000-kilowatt capacity, 
was put in service March 1, 1973; Unit No. 2, also 
90,000-kilowatt capacity, began producing April 6, 
1973; Unit No. 3, 220,000-kilowatt capacity, went on 
the line April 20, 1973. Power generation through September 
1983 has been 19.51 billion kilowatt hours. 
Eighty mini-recreation sites have been established 
along the reservoir shoreline. Each site includes at 
least a picnic table, U.S. Forest Service-type fireplace, 
and chemical toilet. Some of the sites have several 
picnic tables. 
Dent Acres and Freeman Creek recreation sites are 
open to the public. Facilities consist of a boat launching 
ramp, boat docks, car-trailer parking, comfort stations, 
and fully developed overnight camping at each 
site. 
Estimated total cost for new work is $330,740,000 
consisting of $328,000,000 (full funding) for construction 
and $2,740,000 for value of public-domain lands. 
Local cooperation. None required. 
Operations during fiscal year. New work: Wildlife 
habitat browse development continues on project 
lands to provide winter browse for elk and deer. A 
contract to pass dam drainage water around the ice 
sluice was completed in FY 1983. 
Maintenance: Normal operation and maintenance 
continued. Hatchery operations were impaired by an 
infection of IHN virus which caused a 25 percent 
decrease in steelhead smolt releases from 1982 levels. 
In Spring 1983, 2,144,947 steelhead smolts weighing 
318,000 pounds were released. A return of 7,662 adults 
in Spring 1983 was expected to produce the hatchery's 
capacity of 2,900,000 smolts for 1984 release; however, 
virtually all were killed by the viral infection. After 
the infection was brought under control, 1,900,000 
smolts were acquired from another hatchery for rearing 
and release in 1984. In addition to steelhead, the 
hatchery released 550,048 rainbow trout weighing 
51,561 pounds into the reservoir in 1983. A total of 1.89 
billion kilowatt hours of electric energy was delivered 
to Bonneville Power Administration, the marketing 
agency. 
14. ICE HARBOR LOCK AND DAM-LAKE 
SACAJAWEA, WA 
Location. On Snake River, 9.7 miles above river 
mouth at head of Lake Wallula and 12 miles east of 
Pasco, WA. 
Existing project. The project includes a dam, 
powerplant, navigation lock, fish ladders, appurtenant 
facilities, and relocation of railroads. Project 
provides for navigation, hydroelectric power generation, 
recreation, and incidental irrigation. Reservoir 
has normal operating range between elevations 440 
and 437 mean sea level, and extends upstream about 
31.9 miles, providing slack water to Lower Monumental 
Lock and Dam. Structure is about 2,790 feet long 
and about 130 feet high above streambed. Beginning 
at south end, project consists of a concrete nonoverflow 
section, concrete powerhouse, spillway dam, navigation 
lock, and an earth and rockfill embankment at 
north abutment. Fish passing facilities, including two 
ladders, are provided. Powerplant now has three 90,000- 
kilowatt units and three 111,000-kilowatt units in 
operation. Spillway dam is 610 feet long, and overflow 
crest at Elevation 391 mean sea level is surmounted by 
10 radial gates, 50 feet wide by 51 feet high, which 
provide the capacity to pass a design flood of 850,000 
cubic feet per second. Deck is at Elevation 453 mean 
39-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
sea level and provides a service road and track for a 
gantry crane. Navigation lock is single-lift type with 
clear plan dimensions of 86 by 675 feet and 15-foot 
minimum depth over the sills. A navigation channel 
250 feet wide and 14 feet deep is provided from the 
mouth of the Snake River to the dam. Principal project 
data are set forth in Table 39-J. 
Construction started December 1955 and the project 
was placed in useful operation January 1962. The project 
is complete. 
An Environmental Impact Statement concerning 
power units 4 through 6 was filed with the Council on 
Environmental Quality August 1971. 
Power generation through September 1983 has been 
49.86 billion kilowatt hours. 
Local cooperation. None required. 
Operations during fiscal year. Maintenance: 
Normal operation and maintenance continued. Contracts 
were awarded for protective relaying, replacement 
of three circuit breakers, mooring dolphins, seal 
coating of project roads, relocation of Charbonneau 
Park sanitary facilities, and purchasing navigation 
lock gate cable sets. 3.41 billion kilowatt hours of 
electric energy were delivered to Bonneville Power 
Administration, the marketing agency. A total of 
3,771,458 tons of cargo passed through the navigation 
lock during calendar year 1982. 
15. LEWISTON-CLARKSTON BRIDGE, 
ID AND WA 
Location. On the Snake River, River Mile 141.3,1.7 
miles upstream of the existing interstate bridge connecting 
the towns of Lewiston, ID and Clarkston, WA. 
Existing project. The project consists of a new 
fixed high-level four lane highway bridge and approaches 
on U.S. Highway 12 across the Snake River 
constructed at a cost "not to exceed $21,000,000." In 
December 1981 Congress authorized an additional 
expenditure of $2,200,000 for construction of Lewiston's 
North Ramp which had been an unfunded additive 
item. An approach roadway from the bridge to 
16th Avenue in Clarkston, WA was authorized in July 
1983 at an additional expenditure of $800,000. 
Final Environmental Impact Statement Supplement 
filed with the Council on Environmental Quality on 
July 16, 1979. 
Local cooperation. Non-Federal interests have 
provided, without cost to the United States all lands, 
easements, and rights-of-way necessary for the construction 
of the bridge and its approaches, and after 
construction have agreed to own, operate toll free, and 
maintain the bridge and approach facilities. The non- 
Federal costs for land and relocation are $755,193. 
Operations during fiscal year. New work: Construction 
of the main bridge structure and Lewiston 
ramp is complete. Design work was begun on 1600-foot 
roadway from the bridge to 16th Avenue in Clarkston, 
WA. 
16. LITTLE GOOSE LOCK AND DAM-LAKE 
BRYAN, WA 
Location. Dam is 70.3 miles above mouth of Snake 
River at head of Lower Monumental Lake, about 40 
airline miles northerly of Walla Walla, WA, and 50 
miles westerly of Lewiston, ID. 
Existing project. The project includes a dam, 
powerplant, navigation lock, fish ladder, and appurtenant 
facilities. Improvements provide navigation, 
hydroelectric power generation, recreation, and incidental 
irrigation. The reservoir has a normal operating 
range between Elevations 638 and 633 mean sea 
level. Lake Bryan extends upstream about 37.2 miles 
and provides slack water to Lower Granite Lock and 
Dam. Dam structure is 2,670 feet long and about 160 
feet high above streambed and consists of a powerhouse, 
spillway dam, navigation lock, and necessary 
nonoverflow sections. Fish passage facilities include 
one ladder with entrances on both shores with a fish 
channel through the spillway which connects to the 
powerhouse fish collection system and south shore 
ladder. Powerhouse now has six 135,000-kilowatt generating 
units for a capacity of 810,000 kilowatts. Spillway 
dam can pass a design flood of 850,000 cubic feet 
per second. Navigation lock is single-lift type with 
clear plan dimensions of 86 by 675 feet and a minimum 
depth of 15 feet over the sills. Relocations along 
the lake include 32 miles of Camas Prairie Railroad, 
5.8 miles of county roads, 2.2 miles of state highways, 
and Central Ferry bridge. Principal project data are 
set forth in Table 39-J. 
A final Environmental Impact Statement was filed 
with the Council on Environmental Quality on January 
8, 1975. 
Power generation through September 1983 has been 
36.37 billion kilowatt hours. 
Local cooperation. None required. 
Operations during fiscal year. Maintenance: 
Normal operation and maintenance continued. A 
total of 3.20 billion kilowatt hours of electric energy 
was delivered to Bonneville Power Administration, 
the marketing agency. Contracts were awarded for repairs 
on the navigation lock discharge culvert bulkhead 
and guide, cathodic protection, floor repair and modifications 
to the armor plate. Contracts were also 
awarded for spillway gate position indicators, purchase 
of a 55-ton crane, additional traveling fish 
screens, a voltage regulator (excitation system), cleaning 
of draft tube drains, seal coating and overlay of a 
project road, spillway gate repair, modifications to the 
Boyer Park docks and turbine oil sump modifications. 
Major difficulties have been encountered in recent 
years with a high fingerling mortality rate. As this is a 
major collection facility, the difficulties are affecting 
the entire fish trapping and transport program. A 
total of 3,118,728 tons of cargo passed through the 
navigation lock during calendar year 1982. 
39-6

WALLA WALLA, WASHINGTON DISTRICT 
17. LOWER GRANITE LOCK AND DAM, WA 
Location. At River Mile 107.5 on Snake River at 
head of Lake Bryan and about 33 miles downstream 
from Lewiston, ID. 
Existing project. The facility includes a dam, 
powerplant, navigation lock, fish ladder, and appurtenant 
facilities, and requires about 8 miles of backwater 
levees along Snake and Clearwater Rivers at 
Lewiston, ID. Benefits afforded by project include 
slack-water navigation, power generation, recreation, 
and incidental irrigation. Water surface at the dam 
varies between Elevations 738 and 724 to maintain a 
normal operating range between Elevations 738 and 
733 in the Lewiston, ID-Clarkston, WA area. Dam 
structure is about 3,200 feet long and about 146 feet 
high above streambed. Powerhouse now has six 135,000- 
kilowatt units. Spillway has a capacity for a design 
flood of 850,000 cubic feet per second. Navigation lock 
is a single-lift type (105 feet maximum) with clear plan 
dimensions of 86 by 675 feet and a minimum depth of 
15 feet over the sills. Principal project data are set 
forth in Table 39-J. 
Construction started July 1965 and is complete. 
Acquisition of lands is also complete. Lake was filled 
February 15, 1975 and the first power generating unit 
went on the line April 15, 1975. Approximately 
$3,254,000 in potential flood damage has been prevented 
since the levees became functional. An Environmental 
Impact Statement was filed with the Council 
on Environmental Quality November 1971. A revised 
statement to include the additional units was filed 
with the Council on Environmental Quality on July 
23, 1975. Installation of three additional 135,000- 
kilowatt generating units was completed in May 1978. 
Power generation through September 1983 has been 
23.85 billion kilowatt hours. 
Local cooperation. None required. 
Operations during fiscal year. New work: Fingerling 
facility modifications and wildlife habitat development 
contracts were completed as scheduled in FY 
1983. A contract was awarded in FY 1983 for a trash 
shearboom at the powerhouse forebay. 
Maintenance: Normal operation and maintenance 
continued. Contracts were awarded for emergency 
repair of the upstream navigation lock gate, navigation 
lock cathodic protection and armor plate modification 
as well as fish barge moorage facilities, 
additional traveling fishscreens, fingerling facility 
fencing, turbine guide bearing repair spillway gate 
position indicators, and cleaning of the draft tube 
drains. An additional floating bulkhead, 55-ton crane 
and a hydraulic crane were also purchased. 
As the first collection point on the Snake River, 
Lower Granite is a primary component in the District's 
fish trapping and transport program. This program 
was begun because construction of eight dams 
on the Columbia and Snake Rivers has had a significant 
impact on the life cycle and migration patterns of 
anadromous fish such as salmon and steelhead trout. 
Since the early 1960's, efforts to mitigate the adverse 
impacts have included extensive studies, structural 
modifications of the dams, installation of turbine 
screening systems, and implementation of a system 
for trapping and transporting juvenile fish. 
The Walla Walla District operates the fish trapping 
and transportation program for the Columbia-Snake 
system. Three primary collection points have been 
established at Lower Granite, Little Goose and 
McNary dams, with fish sorting and handling facilities. 
Fingerlings collected at these facilities are taken 
by specially designed barges and trucks to an area 
below Bonneville Dam and released to make the rest of 
their journey to the sea. An average of seven million 
fingerlings have been transported in each of the last 
four years. In 1982 and 1983 state and federal fishery 
agencies, as well as the tribes, requested increased 
spills at each dam as a back-up means of insuring 
continuance of the fish runs. This philosophy of 
spreading-the-risk is likely to continue for the foreseeable 
future and will necessitate both increased spillage 
for fish passage and a viable trapping and 
transport program. Advances in fish research and 
technology will no doubt require modifications to the 
facilities currently in use. 
A total of 3.20 billion kilowatt hours of electric 
energy were delivered to Bonneville Power Administration, 
the marketing agency. A total of 1,889,026 
tons of cargo passed through the navigation lock during 
calendar year 1982. 
18. LOWER MONUMENTAL LOCK AND 
DAM-LAKE HERBERT G. WEST, WA 
Location. On Snake River at head of Lake Sacajawea, 
about 45 miles northeast of Pasco, WA, and 41.6 
miles above river mouth. 
Existing project. The facility includes a dam, 
powerplant, fish ladders, navigation lock, appurtenant 
facilities, and relocated railroads and highways. 
The project functions include navigation, hydroelectric 
power generation, recreation and irrigation. Reservoir 
has normal operating range between Elevations 
540 and 537. The lake extends about 28.7 miles upstream 
to Little Goose Lock and Dam. The dam is 
concrete gravity type with earthfill and rockfill abutments. 
It is 3,800 feet long including abutments, spillway, 
navigation lock, and powerhouse, and is about 
135 feet high above streambed. There are two fish 
ladders, one at each end of the dam. Powerhouse has 
six 135,000-kilowatt units for a total capacity of 810,000 
kilowatts. Spillway is 508 feet long, and overflow crest 
at Elevation 483 feet above mean sea level is surmounted 
by 8 radial gates, each 50 feet wide and 61 
feet high. Deck is at Elevation 553 feet and provides a 
service road and track for a gantry crane. Navigation 
lock is single-lift type, with lock chamber 86 by 675 feet 
and minimum depth of 15 feet over the sills. Principal 
project data are set forth in Table 39-J. 
Construction began June 1961, and the project was 
opened to navigation April 1969. The project is complete. 
39-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
A final Environmental Impact Statement was filed 
with the Council on Environmental Quality on May 
21, 1976. 
Power generation through September 1983 has been 
37.61 billion kilowatt hours. 
Local cooperation. None required. 
Operations during fiscal year. Maintenance: 
Normal operation and maintenance continued. Contracts 
were awarded for a 50-ton crane, repairs to the 
navigation lock interior wall coating and lift gate 
cable sets as well as repairs to the spillway gate position 
indicators and spillway gates. A transformer 
safety fence was installed, navigation lock monolith 
concrete repairs and modifications to the navigation 
lock armor plating were made. A total of 2.90 billion 
kilowatt hours of electric energy was delivered to 
Bonneville Power Administration, the marketing 
agency. Cargoes totaling 3,260,570 tons passed 
through the navigation lock during calendar year 
1982. 
19. LOWER SNAKE RIVER FISH & WILDLIFE 
COMPENSATION PLAN, WA, OR, ID 
Location. At various locations within the Columbia 
Snake River drainage in the States of Idaho, 
Oregon and Washington. 
Existing project. The project will consist of a series 
of fish hatcheries and wildlife development areas 
at sites to be selected. The project will compensate for 
loss of wildlife habitat and anadromous and resident 
fishery inundated as a result of construction of four 
multiple purpose dams and reservoirs on the Lower 
Snake River (Ice Harbor, Lower Monumental, Little 
Goose, Lower Granite). 
In 1980 the first release from the McCall, ID summer 
chinook hatchery was made, and the adult trapping 
facility which provides the fish egg supply for the 
McCall Hatchery became operational. 
The real estate design memorandum, and feature 
design memorandums on the McCall Hatchery, Hagerman 
Hatchery, Lookingglass Hatchery, Lyons 
Ferry Hatchery, Dworshak Hatchery Expansion, 
Irrigon Hatchery, Buhl (Crystal Springs) Hatchery, 
Sawtooth River Satellite Facility, the off-project wildlife 
Hatchery, East Fork Salmon lands, and the site 
selection report have all been approved. A final 
Environmental Impact Statement was filed with 
Council on Environmental Quality on November 2, 
1977. The compensation plan is 36 percent complete. 
Estimated Federal cost of the project is $181,000,000 
(full funding). 
Local cooperation. None required. 
Operations during fiscal year. New work: 
McCall Hatchery, Lookingglass Hatchery, Lyons 
Ferry Phase I Hatchery, and spring chinook rearing 
facilities at Dworshak National Fish Hatchery are in 
operation. The latter three facilities made their first 
releases in FY 1983. Construction contracts were 
awarded for the Sawtooth Hatchery, ID, Irrigon 
Hatchery, OR, water wells, and the second and final 
stage of the Lyons Ferry, WA, Hatchery. The design 
for the Irrigon Hatchery and its companion facility, 
the Wallowa Hatchery, is 95 percent complete. The 
design for Buhl, formerly called Crystal Springs, is 10 
percent complete. The final hatchery site has been 
selected at Ahsahka, Idaho, for the Clearwater River 
basin. This hatchery will rear both spring chinook 
and steelhead. Studies are continuing to identify 
satellite sites for this hatchery. Contacts with landdowners 
for participation in off-project wildlife programs 
in Washington are continuing. Several appraisals 
have been made but are not presently approved. 
Acquiring the various lands for wildlife compensation 
has been a problem. In March 1983 a report was prepared 
for Congress on the progress in implementing 
the plan. This report is currently being reviewed. The 
report recommends continuation of the willing-seller, 
willingbuyer acquisition but requests authority to 
acquire any combination of upland game, chukar habitat, 
or fisherman access in fee and/or by easement. 
20. McNARY LOCK AND DAMLAKE 
WALLULA, OR AND WA 
Location. On Columbia River 292 miles above 
mouth, near Umatilla, Oregon, and 3 miles above 
mouth of Umatilla River. 
Existing project. Includes a concrete dam 7,300 
feet long overall and 183 feet high above streambed, 
powerplant with 14 power generating units, navigation 
lock, fishways, levees and pumping plants, incidental 
irrigation, and modification and relocation of 
railroad bridges over the Columbia and Snake Rivers 
in order to eliminate hazards to navigation. Principal 
project data are set forth in Table 39-J. 
Construction started May 1947 and is complete. Project 
placed on permanent operating basis and lake 
raised to Elevation 340 in November 1953. Except for 
maintenance interruptions, all 14 power units have 
been in commercial operation since February 1957. 
A final Environmental Impact Statement was filed 
with Council on Environmental Quality in June 1976. 
Power generation through September 1983 has been 
176.75 billion kilowatt hours. 
Local cooperation. None required. 
Operations during fiscal year. New work: A navigation 
study was completed which evaluated 
hazardous conditions for downbound river traffic in 
the navigation channel below the Ice Harbor powerhouse. 
The study determined that widening the channel 
by 100 feet riverward for a distance of 2,500 feet 
below Ice Harbor Lock would significantly reduce the 
hazardous conditions in that reach of the channel. 
The report is complete and under agency review. The 
feasibility of installing two tube turbine generators, 
with a combined capacity of 6.5 megawatts, in the 
water supply conduits for the North Shore Fishway 
Attraction Water System was established by a study 
completed in FY 1983. It has been determined that 
Congressional authorization is required for this 
39-8

WALLA WALLA, WASHINGTON DISTRICT 
project. Two public power entities have applied for a 
Federal Energy Regulatory Commission permit to 
proceed with the project. 
Code 710: Federal recreation cost sharing funds of 
$200,000 were expended for completion of Chinawa 
Bike Trail and remedial work on the Columbia Park 
swimming lagoon. 
Maintenance: Normal operation and maintenance 
of project continued. Contracts were awarded for 
Strawberry Island erosion protection, cathodic protection 
and painting of the navigation lock stoplogs 
and a levee annunciation system. Additional work 
accomplished during the year includes: modification 
to fish barge #3, replacement of the Drott hydraulic 
crane, acquisition of additional traveling fish screens, 
a prefab restroom, emergency generator building and 
modifications to Hood Park ramp and parking. A 
report justifying the need for major powerhouse rehabilitation 
at McNary was not-approved. A revised 
report outlining a repair and modernization program 
was approved and funded as a high priority program. 
Contractual work continued on heat pumps, drainage 
pump, protection relays, transfer oil heat exchanger, 
battery chargers, oil pumps and 3-D cams, generator 
thrust bearing, radio system, telephone system, governor 
air compressors, bridge crane alignment, transformer 
cooling, fire protection, turbine shaft sleeves, 
modifications to the intake gates, surge arrestors and 
elevator controls. Approximately 6.67 billion kilowatt 
hours of electric energy were delivered to Bonneville 
Power Administration, the marketing agency. A total 
of 6,778,658 tons of commodities passed through the 
navigation lock during calendar year 1982. 
21. SNAKE RIVER DOWNSTREAM 
FROM JOHNSON BAR LANDING, 
OR, WA, AND ID 
Location. On Snake River downstream from Johnson 
Bar Landing, River Mile 230. Snake River, which 
is largest tributary of Columbia River, rises in Yellowstone 
National Park in western part of Wyoming, 
flows generally westerly for about 1,000 miles, and 
empties into Columbia River near Pasco, WA, 324 
miles from Pacific Ocean. 
Existing project. The River and Harbor Act of 
1945 authorized construction of dams as necessary 
and open channel improvements for purposes of providing 
slack-water navigation and irrigation between 
mouth of Snake River and Lewiston, ID. That authorization 
modified previous authorizations only for that 
portion of improvement below Lewiston, ID. Acts of 
June 13, 1902, and August 30, 1935, as they pertain to 
open river improvement from Lewiston, ID, to Johnson 
Bar Landing, remain part of existing project. 
Improvements included in existing project are Ice 
Harbor Lock and Dam-Lake Sacajawea; Little Goose 
Lock and Dam-Lake Bryan; Lower Granite Lock and 
Dam; Lower Monumental Lock and Dam-Lake Herbert 
G. West; and open-river improvement, Lewiston 
to Johnson Bar Landing. Each of the four locks and 
dams is described in an individual report, and cost 
and financial data for the entire project are shown on 
Tables 39-A and 39-K. 
Ice Harbor, Lower Monumental, Little Goose and 
Lower Granite are in full operation. (See individual 
reports for details.) (For further details see Annual 
Reports, page 2246 for 1903; page 1986 for 1906; page 
1991 for 1915; and page 1981 for 1962.) 
Local cooperation. None required. 
Terminal facilities. On Snake River from the 
mouth to Johnson Bar Landing there are 18 privately 
owned barge terminals in use for shipping grain, petroleum 
products, fertilizers, cement, and other general 
cargo. There are also 5 marinas and 28 small-boat 
launching ramps, all open to public use. The facilities 
serve slack-water navigation to Snake River Mile 140, 
the site of Lewiston, ID. That slack-water reaches the 
Lewiston, ID-Clarkston, WA area since the lake behind 
Lower Granite Dam was filled in February 1975. 
Operations during fiscal year. See individual 
reports for Ice Harbor, Lower Monumental, Little 
Goose, and Lower Granite locks and dams. On Snake 
River from Lewiston, ID, to Johnson Bar Landing, 
reconnaissance and condition surveys were conducted 
and navigation aids were maintained. 
General Investigations 
22. SURVEYS 
The Upper Snake River and Tributaries is the principal 
ongoing survey. The area covered by the study 
extends from the headwaters of the Snake River in 
Wyoming down to and including the Weiser River in 
Idaho. The potential for supplemental water storage, 
power generation, and streamflow augmentation to 
enhance fisheries, continues to be the primary focus. 
A survey study of the Mill Creek Basin was resumed 
in FY 1983. Mill Creek originates in the Blue Mountains 
in northern Oregon and southern Washington, 
and is tributary to the Walla Walla River. Water 
resource problems and needs being investigated include 
municipal and industrial water supply, power 
generation, fish enhancement, flood control, and irrigation. 
The Columbia River and Tributaries is a survey 
study directed by the North Pacific Division in which 
the Walla Walla District is participating. The feasibility 
of utilizing an outlet at McNary Lock and Dam to 
furnish water downstream on the Oregon shore for 
municipal, industrial, irrigation, and fish enhancement 
use is the primary investigation for Walla Walla 
District under this study. Also, identification of additional 
potential water storage sites for the Columbia 
River System was continued. 
Total cost of surveys during fiscal year was $868,300. 
That sum was expended for: flood control studies, 
$729,350; special studies including Soil Conservation 
Service, Bureau of Reclamation, River Basin and 
Regional Planning Commissions, Cooperation with 
States, $73,950; and Special Investigations and FERC 
Licensing Activities, $65,000. 
39-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
23. COLLECTION AND STUDY OF BASIC DATA 
During the fiscal year flood hazard data for a 
number of locations in the District were collected and 
analyzed. Flood information was provided to several 
Federal agencies, to the States of Idaho, Oregon, and 
Washington, to various cities and counties in those 
states, and to some private organizations. 
Total cost of collection and study of basic data during 
fiscal year was $115,000 which was expended for 
flood plain management services, $45,000; and technical 
services, $70,000. 
24. CONTINUATION OF PLANNING AND 
ENGINEERING 
McNary Lock and Dam (Second Powerhouse) 
OR and WA 
McNary Second Powerhouse is a proposed addition 
on the south shore of McNary Lock and Dam on the 
Columbia River near Umatilla, OR. The project will 
increase the present 1127 megawatt generating capacity 
by an additional 742 megawatts. Provisions are 
included for compensation of negative impacts on fish 
and wildlife. The project is estimated to cost 
$616,000,000 at October 1, 1983 price levels. Annual 
power benefits are estimated to be $109,347,000. 
The General Design Memorandum Phase I was prepared 
under the Water Resource Development Act of 
1976, Public Law 94-587, and submitted to the Secretary 
of the Army on July 1, 1981. 
Studies were initiated in FY 1982 and continued 
through FY 1983 on the General Design Memorandum 
Phase II and the Powerhouse Preliminary Design Report. 
FY 1983 expenditures were $1,573,272. 
39-10

TABLE 39-A 
WALLA WALLA, WASHINGTON DISTRICT 
COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
In Text Project Funding FY 80 FY 81 FY 82 FY 83 Sep. 30, 1983 
2. Cottonwood New Work 
Community Church, 
Culdesac, ID 
6. Lucky Peak Lake, 
ID 
7. Mill Creek Lake, 
WA 
8. Ririe Lake, ID 
10. Sewage Lagoons, 
Vale, OR 
11. Willow Creek Lake, 
OR 
12. Zintel Canyon Dam, 
WA 
13. Dworshak Dam and 
Reservior, ID 
14. Ice Harbor Lock 
and Dam, WA 
15. Lewiston-Clarkston 
Bridge, ID 
16. Little Goose Lock 
and Dam, WA 
Approp 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
23,400 
23,140 
35,000 
15,797 19,242 
495,700 641,500 658,700 698,800 
451,111 653,207 647,109 740,442 
196,900 220,140 220,400 299,044 
196,946 215,360 223,960 298,254 
473,830 6,382,000 2,770,000 1,596,734 
465,524 6,313,198 2,846,712 1,594,699 
-39,000 
138,623 -38,267 
67,000 
8,100 
1,778,275 5,283,000 19,730,000 4,993,540 
1,423,064 5,543,180 19,820,937 4,977,858 
15,000 
15,000 
25,000 
19,250 
23,400 
23,140 
19,580,681' 
19,580,681' 
7,053,204 
7,047,295 
2,230,6012 
2,230,6012 
5,282.193 
5,278,526 
11,222,564 
11,220,133 
39,677,448 
13 39,677,448 
67,000 
8,100 
32,849,114 
32,828,899 
425,153 
5,750 425,153 
7,618,000 4,616,000 3,755,000 1,630,00 322,409,196' 
7,204,811 4,729,546 4,061,316 1,634,122 322,408,260; 
3,629,100 3,911,700 4,798,496 3,750,922 
3,584,353 3,879,789 4,079,228 4,515,463 
2,126,000 972,000 
2,047,262 951,132 
30,000 
131,082 
-2,299 
-3,290 
3,117,100 2,953,000 3,549,684 4,800,141 
2,677,636 3,216,745 3,665,786 4,869,452 
6,535,000 9,050,000 
6,521,804 8,632,959 
4,535,000 692,664 
4,979,230 693,216 
2,569,600 2,095,850 505,000 
2,348,876 1,779,273 1,044,258 
33,132,987 
33,094,003 
166,991,647 
166,990,647" 
37,200,5747 
37,176,7877 
22,237,664 
22,237,537 
220,298,527 
11 220,298,5269 
2,318,800 2,477,360 2,896,600 4,904,122 
2,142,940 2,528,912 2,913,390 4,868,523 
25,735,19522 
25,598,50922 
39-11

TABLE 39-A 
(Continued) 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
In Text Project Funding FY 80 FY 81 FY 82 FY 83 Sep. 30, 1983 
17. Lower Granite Lock New Work 
and Dam, WA Approp. 3,905,395 3,724,000 2,885,000 2,052,181 367,310,8261o 
Cost 3,491,903 4,063,602 2,956,258 2,047,995 367,298,908" 
Maint. 
Approp. 2,811,100 3,350,000 4,684,500 5,896,535 25,238,89712 
Cost 2,612,169 3,372,373 4,788,472 5,776,641 25,026,69112 
18. Lower Monumental New Work 
Lock and Dam, Approp. 1,367,300 261,150 - - 236,358,211' 
WA Cost 1,363,277 221,243 49,298 -906 236,357,297'14 
Maint. 
Approp. 3,398,000 2,173,000 2,372,100 3,677,483 23,226,273'15 
Cost 3,230,045 2,143,387 2,540,071 3,691,797 23,184,689's 
19. Lower Snake Fish & New Work 
Wildlife Compensa- Approp. 4,538,600 14,811,000 18,660,000 19,656,180 65,705,780 
tion, ID, OR & WA Cost 3,663,819 15,030,546 19,253,981 19,706,580 65,694,906 
20. McNary Lock & New Work 
Dam-Lake Wallula Approp. 7,665,000 8,126,000 1,137,000 439,000 322,293,486 ' 
OR & WA Cost 7,534,824 6,531,897 2,822,859 479,320 322,292,483' 7 
Maint. 
Approp. 6,386,600 6,229,200 8,944,380 10,317,455 89,448,5111' 
Cost 5,258,598 7,009,520 8,582,087 11,024,478 89,400,6801s 
21. Snake River Down- New Work 
stream from John- Approp. 9,968,295 7,053,000 3,420,000 2,049,882 991,393,974's 
son Bar Landing, Cost 9,251,318 7,015,246 4,180,896 2,043,810 991,380,14019 
OR, WA & ID Maint. 
Approp. 11,663,000 10,943,360 13,533,584 19,311,281 111,721,54220 
Cost 10,677,118 11,274,502 13,933,979 19,254,422 111,307,2322' 
'Includes $499,431 appropriated and expended for Code 
710, Recreation Facilities at Completed Projects. 
-Excludes $80,000 contributed funds, but includes 
$68,446 appropriated and expended for Code 710, Recreation 
Facilities at Completed Projects. 
'Includes $2,046,100 regular project construction funds 
appropriated for and expended by Department of Interior in 
Fiscal Years 1969 through 1972 for hatchery operations. 
Includes $655,000 appropriated and expended for additional 
unit.
4Includes $11,887,800 regular project operation and 
maintenance funds expended by Department of Interior 
starting FY 1972 for hatchery operations. FY 72-78 funds of 
$6,097,000 were charged to the project as a cost, but not as an 
expenditure for accounting purposes. Includes $49,996 allotted 
and expended under Special Recreation Use Fees. 
5Includes $714,150 appropriated for Code 710, Recreation 
Facilities at Completed Projects. Excludes $82,500 contributed 
for artificial spawning channel. Includes 
$36,699,017 appropriated for additional units 4 through 6. 
"Includes $713,150 expended for Code 710, Recreation 
Facilities at Completed Projects. Includes $36,699,017 
expended for additional units 4 through 6. 
7Includes $61,507 allotted and expended under Special 
Recreation Use Fees; $569,363 appropriated and expended 
under Maintenance and Operation of Dams and Other 
Improvements of Navigable Waters. 
"Includes $59,885,311 appropriated for additional units 
4 through 6. 
9Includes $59,885,310 expended for additional units 4 
through 6. 
1�Includes $46,211,511 appropriated for additional units 
4 through 6. 
'Includes $46,211,510 expended for additional units 4 
through 6. Excludes $405,819 contributed funds on lock and 
dam project. 
'2Includes $266,463 appropriated and expended under 
Maintenance and Operation of Dams and Other Improvements 
of Navigable Waters. 
' Includes $51,645,850 appropriated for additional units 
4 through 6. 
'4Includes $51,644,936 expended for additional units 4 
through 6. 
'6Includes $300,676 appropriated and expended under 
Maintenance and Operation of Dams and Other Improvements 
of Navigable Waters. 
39-12

TABLE 39-A 
(Continued) 
WALLA WALLA, WASHINGTON DISTRICT 
COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
In Text Project Funding FY 80 FY 81 FY 82 FY 83 Sep. 30, 1983 
'6lncludes $1,773,986 appropriated for Code 710, 
Recreation Facilities at Completed Projects. 
'?7Includes $1,772,984 expended for Code 710, Recreation 
Facilities at Completed Projects. 
1SIncludes $105,258 allotted and expended under Special 
Recreation Use Fees and $964,160 allotted and expended 
under Maintenance and Operation of Dams and Other 
Improvements of Navigable Waters. 
19Includes $400,150 for new work on previous projects 
(Pasco to Lewiston), and $34,613 for new work appropriation 
used for maintenance prior to 1953. Excludes $167,500 contributed 
funds for new work consisting of $82,500 for 
previous projects (Pasco to Riparia), plus $82,500 for new 
work on existing artificial spawning channel. 
"Includes $186,570 appropriated for maintenance on 
previous projects (Pasco to Lewiston) and $324,953 open 
river Pasco to Lewiston and Lewiston to Johnson Bar 
Landing. 
O'Includes $186,570 expended for maintenance on previous 
projects (Pasco to Lewiston) and $324,905 open river 
Pasco to Lewiston and Lewiston to Johnson Bar Landing. 
'Includes $549,363 appropriated and expended under 
Maintenance and Operation of Dams and Other Improvements 
of Navigable Waters. 
39-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 39-B AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
1. 
May 17, 1950 
2. 
July 24, 1946 
6. 
July 24, 1946 
Oct. 22, 1976 
Dec. 22, 1944 
as amended 
June 28, 1938 
Aug. 18, 1941 
COLUMBIA RIVER BASIN, LOCAL FLOOD 
PROTECTION PROJECTS 
Blackfoot Area, Snake River, ID. Levee left bank. 
Blackfoot River, ID. Levees, channel improvement, 
and rectification works. 
Boise Valley, Boise River, ID, Channel improvement 
and enlargement, levees, and revetments in Ada 
County. Canyon County unit was deauthorized 
April 18, 1967. 
Grande Ronde Valley, OR. Levees and channel 
clearing, straightening, and realignment; would 
complement stream regulation by upstream storage 
projects. 
Heise-Roberts Extension, Snake River, ID. Channel 
clearing and rectification, levees, and bank 
protection. 
Kendrick, Potlatch River, ID. Revetted levee. 
Malheur River, OR. Channel rectification, levees, and 
bank protection at Vale. Willow Creek unit was 
deauthorized October 14, 1969. 
Palouse River, WA. Flood protection for urban and 
rural areas at Garfield and near Malden. 
Payette Valley, ID. Channel rectification, levees, and 
bank protection along 38 miles of Payette River 
below Black Canyon Dam. Payette Valley was 
deauthorized 3 October 1978. 
Portneuf River and Marsh Creek, ID. Concrete-lined 
channel through Pocatello. Inkom-Marsh Creek unit 
was deauthorized October 14, 1969. 
Shelley Area, Snake River, ID. Bank protection. 
Weiser River, Weiser Area, ID. Intermittent channel 
realignment and improvement, levees, and bank 
protection, lower river area. 
COTTONWOOD COMMUNITY CHURCH, 
CULDESAC, ID 
Construction of riprap bank protection. 
LUCKY PEAK LAKE, ID 
Dam for flood control, irrigation, and recreation. 
Second outlet for streamflow maintenance. 
Construction, operation, and maintenance of 
recreation facilities. 
MILL CREEK LAKE, WALLA WALLA, WA 
Off-stream storage project upstream from Walla 
Walla. 
Channel improvement through Walla Walla; 
concrete lined channel. 
H. Doc. 531, 81st 
Cong., 2nd Sess. 
Sec. 14, P.L. 79-526 
Authorized by Chief 
of Engineers, March 
14, 1983 
P.L. 526-79, Chief of 
Engineers Report 
dated May 13, 1946 
P.L. 94-587 
Sec. 4, Flood Control 
Act of 1944 
H. Doc. 578, 75th 
Cong., 3d Sess. 
H. Doc. 719, 76th 
Cong., 1st Sess. 
39-14 
7.

TABLE 39-B 
(Continued) 
WALLA WALLA, WASHINGTON DISTRICT 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Oct. 23, 1962 
July 24, 1946 
Oct. 27, 1965 
Oct. 27, 1965 
13 
July 3, 1958 
Oct. 23, 1962 
Aug. 15, 1963 
14. 
Mar. 2, 1945 
Dec. 22, 1944 
as amended 
Oct. 22, 1976 
Dec. 29, 1981 
July 30, 1983 
Mar. 2, 1945 
Dec. 31, 1970 
Mar. 2, 1945 
Mar. 2, 1945 
May 25, 1978 
Oct. 22, 1976 
8. 
10. 
11. 
12. 
RIRIE LAKE, ID 
Storage project for flood control, irrigation, recreation, 
and sports fishery. 
SEWAGE LAGOONS, VALE, OR 
Construction of riprap bank protection. 
WILLOW CREEK LAKE, OR 
Storage project for flood control, recreation, and fish 
and wildlife. 
ZINTEL CANYON DAM, KENNEWICK, WA 
Dam and storage space for temporary detention 
of flood flows plus channel improvement downstream. 
(BRUCES EDDY) DWORSHAK DAM AND 
RESERVOIR, ID 
Preparation of detailed plans. 
Bruces Eddy dam and reservoir for flood control, 
navigation, power, recreation, and area redevelopment. 
Redesignation of project as Dworshak Dam and 
Reservoir. 
ICE HARBOR LOCK AND DAM - 
LAKE SACAJAWEA, WA 
Unit 1 of 4, Lower Snake River project, Lock and dam for 
navigation, power, recreation, and irrigation. 
Construction, operation, and maintenance of 
recreation facilities. 
LEWISTON-CLARKSTON BRIDGE, ID AND WA 
Four lane highway bridge and approaches. 
Increase of authorized amount to $23,200,000. 
Approach roadway from bridge to Sixteenth Avenue 
in Clarkston, WA. Increase of authorized amount to 
$24,000,000. 
LITTLE GOOSE LOCK AND DAMLAKE 
BRYAN, WA 
Unit 3 of 4, Lower Snake River project. Lock and Dam 
for navigation, power, and recreation, and irrigation. 
Designation of reservoir as Lake Bryan. 
LOWER GRANITE LOCK AND DAM, WA 
Unit 4 of 4, Lower Snake River project. Lock and dam 
for navigation, power, recreation, irrigation. 
LOWER MONUMENTAL LOCK AND DAMLAKE 
HERBERT G. WEST, WA 
Unit 2 of 4, Lower Snake River project. Lock and dam 
for navigation, power, recreation, and irrigation. 
Designation of reservoir as Lake Herbert G. West. 
LOWER SNAKE RIVER FISH & WILDLIFE 
COMPENSATION PLAN, WA, OR AND ID 
Fish hatcheries and replacement of wildlife habitat. P.L. 94-587 
39-15 
H. Doc. 562, 87th 
Cong., 2d Sess. 
Sec. 14, P.L. 79-526 
Authorized by Chief of 
Engineers, Aug. 3, 1983 
H. Doc. 233, 89th Cong., 
1st Sess. 
H. D)oc. 416, 89th 
Congr., 2d Sess. 
S. I)oc. 51, 84th Cong., 
1st Sess. 
H. DI)oc. 403, 87th Cong., 
2d Sess. 
P.L. 88-96 
H. Doc. 704, 75th Cong., 
3d Sess. 
Sec. 4, Flood Control 
Act of 1944 
P.L. 94-587 
P.L. 97-140 
P.L. 98-63 
H. Doc. 704, 75th Cong., 
3d Sess. 
P.L. 91-638 
H. Doc. 704, 75th Cong., 
3d Sess. 
H. Doc. 704, 75th Cong., 
3d Sess. 
P.L. 95-285 
15. 
16. 
17. 
18. 
19.

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 39-B 
(Continued) 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
20. 
Mar. 2, 1945 
Dec. 22, 1944 
as amended 
21. 
June 13, 1902 
June 25, 1910 
Aug. 30, 1935 
Mar. 2, 1945 
McNARY LOCK AND DAM-LAKE WALLULA, 
OR AND WA 
Lock and dam for navigation, power, recreation, and 
irrigation. 
Construction, operation, and maintenance of recreation 
facilities. 
SNAKE RIVER MOUTH TO JOHNSON BAR, OR, 
WA AND ID 
Open-river navigation. 
Riparia to Pittsburg Landing. 
Mouth to Riparia. 
Pittsburg Landing to Johnson Bar. 
Supersedes previous legislation mouth to Lewiston, ID, 
only. See Ice Harbor, Lower Monumental, Little 
Goose, and Lower Granite Locks and Dams. 
H. Doc. 704,75th Cong., 
3d Sess. 
Sec. 4, Flood Control 
Act of 1944 
H. Doc. 127, 56th Cong., 
2d Sess. 
H. Doc. 411, 55th Cong., 
2d Sess. 
Rivers and Harbors 
Committee Doc. 25, 
72d Cong., 1st Sess. 
H. Doc. 704, 75th Cong., 
2d Sess. 
39-16

WALLA WALLA, WASHINGTON DISTRICT 
TABLE 39-C OTHER AUTHORIZED 
NAVIGATION PROJECTS 
For Last Cost to Sep. 30, 1983 
Full Report Operation 
See Annual and 
Project Status Report For Construction Maintenance 
Columbia River and Tribu- Completed 1968 1,851,195 - 
taries above Celilo Falls to 
Kennewick, WA' 
'Obviated by The Dalles, John Day, and McNary 
Projects. 
TABLE 39-E OTHER AUTHORIZED 
FLOOD CONTROL PROJECTS 
For Last Cost to Sep. 30, 1983 
Full Report Operation 
See Annual and 
Project Status Report For Construction Maintenance 
Asotin Creek, Asotin, ID' Completed 1951 12,019 
Bear Creek, Kendrick, ID' Completed 1970 133,518 - 
Blackfoot Area, Snake River, 
Columbia River Basin, ID Completed 1958 42,796- 
Blackfoot Reservoir, ID Inactive 1980 267,626 - 
Blackfoot River, Columbia 
River Basin, ID Completed 1965 391,143- 
Boise Valley, Ada County 
Unit, Columbia River Basin, 
ID Deferred 1967 46,084 - 
Catherine Creek Lake, OR Deferred 1978 1,552,000 - 
Colfax, Palouse River, WA Completed 1966 5,557,240 - 
Connell, WA' Completed 1967 60,000 - 
Cottonwood Creek Dam, 
Boise, ID Active 1973 183,100 - 
Dayton, Touchet River, WA Completed 1966 380,617 - 
Dry Creek, WA' Completed 1961 384,426-- 
Esquatzel Coulee, Connell, 
WA' Completed 1967 232,792 - 
Esquatzel Coulee, Mesa, WA' Completed 1969 2,665- 
Gooding Area, ID' Completed 1954 59,167 - 
Grande Ronde Lake, OR Deferred 1966 - - 
Grande Ronde Valley, 
Columbia River Basin, OR Deferred 1958 102,458 - 
Graves Creek, ID' Completed 1953 75,469 - 
Heise-Roberts Area, Snake 
River, ID Completed 1955 1,575,838 
Heise-Roberts Extension, 
Columbia River Basin, ID 1968 
(a) Henrys Fork Unit Deferred 27,800 - 
(b) Snake River Unit Completed 3,375,158 - 
�Jackson Hole, Snake River, 
WY Completed 1978 2,388,270 
39-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 39-E OTHER AUTHORIZED 
FLOOD CONTROL PROJECTS 
For Last Cost to Sep. 30, 1983 
Full Report Operation 
See Annual and 
Project Status Report For Construction Maintenance 
Kendrick, Potlatch River, 
Columbia River Basin, ID Completed 1960 59,942- 
Lapwai Creek, Culdesac, ID' Completed 1972 176,833 - 
Lava Hot Springs, Portneuf 
River, ID' Completed 1973 113,296- 
Lower Dry Creek, Lowden, 
WA' Completed 1972 17,592- 
Lower Walla Walla River, 
Columbia River Basin, WA Inactive 1953 4,000 - 
Lyman Creek, ID' Completed 1971 230,315 - 
Malheur Improvement District, 
Snake River, OR Completed 1957 55,894- 
Malheur River, Vale Unit, 
Columbia River Basin, OR Completed 1961 325,581 
Milton-Freewater, Walla 
Walla River, OR' Completed 1968 1,786,753- 
Mission and Lapwai Creeks, 
ID' Completed 1965 54,538- 
Mud Lake, Columbia River 
Basin, ID Inactive 1957 5,996- 
Orofino Creek & Clearwater 
River, Orofino, ID Inactive 1949 23,050 - 
Palouse River, Columbia 
River Basin, WA Deferred - - - 
Pataha Creek, Pomeroy, WA2 Completed 1977 110,815 - 
Payette River, Emmett 
Sewage Lagoon, ID2 Completed 1967 39,172- 
Portneuf River & Marsh 
Creek Pocatello Unit, 
Columbia River Basin, ID Completed 1969 6,456,032 - 
Pullman, Palouse, WA Deferred 1964 99,540 - 
Riverside Area, Pasco, WA' Completed 1972 28,839- 
Shelley Area, Snake River, 
Columbia River Basin, ID Completed 1958 32,335- 
Shobe Canyon, Heppner, OR' Completed 1970 5,000- 
Snake River, Blackfoot, ID' Completed 1980 131,700 - 
Snake River, Heise Bridge 
Location, ID2 Completed 1952 8,501- 
Snake River, Stevens, 
Blackfoot, ID' Completed 1968 32,425- 
South Fork Clearwater River, 
Columbia River Basin, ID Inactive 1973 3,899- 
South Fork Clearwater River, 
Kooskia-Stites, ID' Completed 1973 61,055- 
Teton River, Columbia River 
Besin, ID Inactive 1955 10,387 - 
Tomanovich-Salmon City, ID' Completed 1955 128,635 - 
Touchet River, Waitsburg, 
WA' Completed 1973 72,140 - 
Tucannon River, Wooten, WA' Completed 1971 73,932 
Umatilla River, OR' Completed 1961 161,540 - 
Wallowa River, Weaver 
Bridge OR2 Completed 1960 16,118 
39-18

TABLE 39-E 
(Continued) 
WALLA WALLA, WASHINGTON DISTRICT 
OTHER AUTHORIZED 
FLOOD CONTROL PROJECTS 
For Last Cost to Sep. 30, 1983 
Full Report Operation 
See Annual and 
Project Status Report For Construction Maintenance 
Weiser River, Columbia River 
Basin, ID Deferred 1960 37,757 
Whitebird Creek, Columbia 
River Basin, ID Inactive 1956 1,896 - 
Willow Creek, ID' Completed 1963 976 - 
Yakima River, West Richland, 
WA' 4 Completed 1964 238,890 
'Authorized by Chief of Engineers pursuant to Section 'Exclusive of $6,300 contributed funds. 
205, PL 80-858. 'Includes $9,000 contributed funds. 
2Authorized by Chief of Engineers pursuant to Section 
14, PL 79-526. 
TABLE 39-G DEAUTHORIZED PROJECTS 
For Last Contri- 
Full Report Date Federal buted 
See Annual Deauth- Funds Funds 
Project Report For orized Expended Expended 
Asotin Dam, Snake R., ID & WA 1964 1975 -- 
Boise Valley, Canyon County 
Unit, ID -1967 10,600 - 
Camas Creek, ID -1965 9,080 - 
Little Wood River, ID -1965 21,334 - 
Malheur River, Willow Creek 
Unit, ID -1969 13,000 - 
Mill Creek, WA -1977 3,537 - 
Payette Valley, ID -1978 23,178 - 
Portneuf River, Inkom-Marsh 
Creek, ID - 1969 -- 
Stuart Gulch Dam, Boise, ID 1974 1979 234,100- 
Touchet River,WA - 1977 11,198- 
Weiser River, Cambridge- 
Midvale, ID - - 75,000- 
39-19

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1.983 
TABLE 39-H COLUMBIA RIVER BASIN, LOCAL 
FLOOD PROTECTION PROJECTS 
(See Section 1 of Text) 
Estimated Cost to Sep. 30, 1983 
Federal 
Project Status Cost 
Blackfoot Area, Snake River, ID Completed - 42,796 
Blackfoot River, ID Completed - 391,143 
Boise Valley, ID 
Ada County Unit Deferred 1,060,000 46,084 
Canyon County Unit Deauthorized - 10,600 
Camas Creek, ID Deauthorized - 9,080 
Grande Ronde Valley, OR Deferred 8,639,000 102,458 
Heise-Roberts Extension, ID 
Henrys Fork Unit Deferred 165,000 27,800 
Snake River Unit Completed - 3,375,158 
Kendrick, Potlatch River, ID Completed - 59,942 
Little Wood River, ID Deauthorized - 21,334 
Lower Walla Walla River, WA Inactive 372,000 4,000 
Malheur River, OR 
Vale Unit Completed - 325,581 
Willow Creek Unit Deauthorized - 13,000 
Mill Creek, WA Deauthorized - 3,537 
Mud Lake, ID Inactive 1,187,000 5,996 
Palouse River, WA Deferred 914,000 - 
Payette Valley, ID Deauthorized - 23,178 
Portneuf River and Marsh Creek, ID 
Pocatello Unit Completed - 6,456,032' 
Shelley Area, Snake River, ID Completed - 32,335 
South Fork Clearwater River, ID Inactive - 3,899 
Teton River, ID Inactive - 10,387 
Touchet River, WA Deauthorized - 11,198 
Weiser River, ID Deferred 1,565,000 37,757 
Weiser River, ID 
Cambridge-Midvale Deauthorized - 75,000 
Whitebird Creek, ID Inactive - 1,896 
Total 11,090,191 
'Exclusive of $36,800 contributed funds. 
39-20

TABLE 39-I 
WALLA WALLA, WASHINGTON DISTRICT 
INSPECTION OF COMPLETED FLOOD 
CONTROL PROJECTS 
(See Section 4 of Text) 
Bear Creek, Kendrick, ID 
Blackfoot, Blackfoot River, ID 
Camp Wooteen, Tucannon River, WA 
Colfax, Palouse River, WA 
Culdesac, Lapwai Creek, ID 
Dayton, Touchet River, WA 
Esquatzel, Coulee, WA 
Gooding Area, Little Wood River, ID 
Heise-Roberts Area, Snake River, ID 
Heise-Roberts Extension, Snake River, ID 
Jackson Hole, Snake River, WY 
Kendrick, Potlatch River, ID 
Lower Dry Creek, Lowden WA 
Lyman, Lyman Creek, ID 
Malheur Improvement District, Snake River, OR 
Milton-Freewater, Walla Walla River, OR 
Mission Creek, ID 
Pocatello, Portneuf River, ID 
Shelley Area, Snake River, ID 
Tomanovich-Salmon City, Salmon River, ID 
Vale, Malheur River, OR 
Walla Walla, Mill Creek, WA 
West Richland, Yakima River, WA 
February 1983 
October 1982 
March 1983 
June 1983 
November 1982 
February 1983 
March 1983 
March 1983 
August 1983 
August 1983 
August 1983 
February 1983 
February 1983 
August 1983 
July 1983 
February 1983 
February 1983 
March 1983 
August 1983 
March 1983 
March 1983 
October 1982 
December 1982 
39-21 
__ 
_ I

TABLE 39-J 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
PRINCIPAL DATA CONCERNING 
NAVIGATION LOCK, SPILLWAY DAM, 
POWERPLANT, AND IMPOUNDMENT 
Project 
Dworshak Dam and 
Reservoir, ID 
(See Section 13 of Text) 
Ice Harbor Lock and Dam, 
WA (See Section 14 of 
Text) 
SPILLWAY DAM 
Type of Construction 
Completed 
Maximum Capacity 
Crest Elevation 
Control Gates: 
Type 
Size, Width by Height 
Number 
POWERPLANT 
Length 
Generating Units: 
Number Installed 
Space for Additional 
Rating, Each 
Total Capacity Installed 
Total Potential Capacity 
Maximum Structural Height 
First Power-On-Line 
IMPOUNDMENT 
Elevations: 
Normal Operating Range 
Maximum 
Flood Control Storage 
Lake Length 
Lake Water Surface Area at Elevation 1600 
Length of Shoreline 
NAVIGATION LOCK 
Clear Width 
Clear Length 
Lift: 
Minimum 
Average 
Maximum 
Minimum Water Depth Over Sills 
Opened to Navigation 
SPILLWAY DAM 
Type of Construction 
Completed 
Maximum Capacity 
Crest Elevation 
Control Gates: 
Type 
Size, Width by Height 
Number 
POWERPLANT 
Length 
Generating Units: 
Number Installed 
Rating, Each 
Concrete Gravity 
September 1974 
150,500 Cubic Feet 
Per Second 
1613 Feet 
Tainter 
50 Ft. by 55 Ft. 
2
428 Feet 
33 
2 @ 90,000 kw; 
4 @ 220,000 kw 
400,000 kw 
1,060,000 kw 
150 Feet 
March 1973 
1600-1445 Feet 
1605 Feet 
2,000,000 Ac.-Ft. 
53 Miles 
17,090 Acres 
175 Miles 
86 Feet 
675 Feet 
97 Feet 
100 Feet 
103 Feet 
15 Feet 
May 1962 
Concrete Gravity 
January 1962 
850,000 cfs 
391 Feet 
Tainter 
50 Ft. by 51 Ft. 
10 
671 Feet 
6
3 @ 90,000 kw; 
3 @ 111,000 kw 
39-22

TABLE 39-J 
(Continued) 
WALLA WALLA, WASHINGTON DISTRICT 
PRINCIPAL DATA CONCERNING 
NAVIGATION LOCK, SPILLWAY DAM, 
POWERPLANT, AND IMPOUNDMENT 
Project 
Little Goose Lock and Dam, 
WA (See Section 16 of 
Text) 
Lower Granite Lock 
and Dam, WA (See 
Section 17 of Text) 
Total Installed Capacity 
Maximum Structural Height 
First Power-On-Line 
IMPOUNDMENT 
Elevations: 
Normal Operating Range 
Maximum 
Lake Length 
Lake Water Surface Area at Elevation 440 
Navigation Channel, Depth by Width 
Length of Shoreline 
NAVIGATION LOCK 
Clear Width 
Clear Length 
Lift: 
Minimum 
Average 
Maximum 
Minimum Water Depth Over Sills 
Opened to Navigation 
SPILLWAY DAM 
Type of Construction 
Completed 
Maximum Capacity 
Crest Elevation 
Control Gates: 
Type 
Size, Width by Height 
Number 
POWERPLANT 
Length 
Width 
Generating Units: 
Number Installed 
Rating, Each 
Total Installed Capacity 
Maximum Structural Height 
First Power-On-Line 
IMPOUNDMENT 
Elevations: 
Normal Operating Range 
Maximum 
Lake Length 
Lake Water Surface Area at Elevation 638 
Navigation Channel, Depth by Width 
Length of Shoreline 
NAVIGATION LOCK 
Clear Width 
Clear Length 
Lift: 
Minimum 
Average 
Maximum 
Minimum Water Depth Over Sills 
603,000 kw 
226 Feet 
December 1961 
440-437 Feet 
446 Feet 
31.9 Miles 
9,200 Acres 
14 Ft. by 250 Ft. 
80 Miles 
86 Feet 
675 Feet 
93 Feet 
98 Feet 
101 Feet 
15 Feet 
May 1970 
Concrete Gravity 
January 1970 
850,000 cfs 
581 Feet 
Tainter 
50 Ft. by 60 Ft. 
8
656 Feet 
243 Feet 
6
135,000 kw 
810,000 
244 Feet 
March 1970 
638-633 Feet 
646.5 Feet 
37.2 Miles 
10,025 Acres 
14 Ft. by 250 Ft. 
92 Miles 
86 Feet 
675 Feet 
95 Feet 
100 Feet 
105 Feet 
15 
39-23

TABLE 39-J 
(Continued) 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
PRINCIPAL DATA CONCERNING 
NAVIGATION LOCK, SPILLWAY DAM, 
POWERPLANT, AND IMPOUNDMENT 
Project 
Lower Monumental 
Lock and Dam, WA 
(See Section 18 of Text) 
SPILLWAY DAM 
Type of Construction 
Completed 
Maximum Capacity 
Crest Elevation 
Control Gates: 
Type: 
Size, Width by Height 
Number 
POWERPLANT 
Length 
Width 
Generating Units: 
Number Installed 
Rating, Each 
Total Capacity Installed 
Maximum Structural Height 
First Power-On-Line 
IMPOUNDMENT 
Elevations: 
Normal Operating Range 
Maximum 
Lake Length 
Lake Water Surface area at Elevation 738 
Navigation Channel, Depth by Width 
Length of Shoreline 
NAVIGATION LOCK 
Clear Width 
Clear Length 
Lift: 
Minimum 
Average 
Maximum 
Minimum Water Depth Over Sills 
Opened to Navigation 
SPILLWAY DAM 
Type of Construction 
Completed 
Maximum Capacity 
Crest Elevation 
Control Gates: 
Type 
Size, Width by Height 
Number 
POWERPLANT 
Length 
Width 
Generating Units: 
Number Installed 
Rating, Each 
Total Installed Capacity 
Maximum Structural Height 
First Power-On-Line 
Concrete Gravity 
February 1975 
850,000 cfs 
581 Feet 
581 
Tainter 
50 Ft. by 60.5 Ft. 
8
656 Feet 
243 Feet 
6
135,000 kw 
810,000 kw 
246 Feet 
April 1975 
738-733 Feet 
746.5 Feet 
38 Miles 
8,900 Acres 
14 Ft. by 250 Ft. 
91 Miles 
86 Feet 
675 Feet 
97 Feet 
98 Feet 
103 Feet 
15 Feet 
April 1969 
Concrete Gravity 
March 1969 
850,000 cfs 
483 Feet 
Tainter 
50 Ft. by 61 Ft. 
8
656 Feet 
243 Feet 
6
135,000 kw 
810,000 kw 
242 Feet 
May 1969 
39-24

TABLE 39-J 
(Continued) 
WALLA WALLA, WASHINGTON DISTRICT 
PRINCIPAL DATA CONCERNING 
NAVIGATION LOCK, SPILLWAY DAM, 
POWERPLANT, AND IMPOUNDMENT 
Project 
McNary Lock and 
Dam, OR and WA 
(See Section 20 of Text) 
IMPOUNDMENT 
Elevations: 
Normal Operating Range 
Maximum 
Lake Length 
Lake Water Surface Area at Elevation 540 
Navigation Channel, Depth by Width 
Length of Shoreline 
NAVIGATION LOCK 
Clear Width 
Clear Length 
Lift: 
Minimum 
Average 
Maximum 
Minimum Water Depth Over Sills 
Opened to Navigation 
SPILLWAY DAM 
Type of Construction 
Completed 
Maximum Capacity 
Crest Elevation 
Control Gates: 
Type 
Size, Width by Height 
Number 
POWERPLANT 
Length 
Generating Units: 
Number Installed 
Rating, Each 
Total Installed Capacity 
Maximum Structural Height 
First Power-On-Line 
IMPOUNDMENT 
Elevations: 
Normal Operating Range 
Maximum 
Lake Length 
Lake Water Surface Area at Elevation 340 
Navigation Channel, Depth by Width 
Length of Shoreline 
540-537 Feet 
548 Feet 
28.7 Miles 
6,590 Acres 
14 Ft. by 250 Ft. 
78 Miles 
86 Feet 
675 Feet 
67 Feet 
75 Feet 
83 Feet 
15 Feet 
November 1953 
Concrete Gravity 
October 1953 
2,200,000 cfs 
291 Feet 
Vertical Lift 
50 Ft. by 51 Ft. 
22 
1,348 Feet 
14 
70,000 kw 
980,000 kw 
193 Feet 
November 1953 
340-335 Feet 
356.5 Feet 
64 Miles 
38,800 Acres 
14 Ft. by 250 Ft. 
242 Miles 
39-25

TABLE 39-K 
REPORT OF THE CHIEF, OF ENGINEERS, U.S. ARMY 1983 
SNAKE RIVER DOWNSTREAM FROM 
JOHNSON BAR LANDING 
OR, WA, AND ID 
(See Section 21 of Text) 
Estimated 
Cost (Corps New Work Maintenance Percent 
of Engineers to Sep. 301983 to Sep. 30, 1983 Cornm- Constr. 
Project Funds Only) Approp. Cost Approp. Cost pleted Started 
Ice Harbor Lock & Dam 
Initial Project 129,578,480 129,578,480 129,578,480 37,200,574 37,176,787 100 FY 57 
Code 710 Recreation 
Facilities 1,645,000 714,150 713,150 - - 43 FY 57 
Power Units 4-6 36,699,017 36,699,017 36,699,017 - - 100 FY 71 
Totals 167,922,497 166,991,647 166,990,647 37,200,574 37,176,787 99 
Little Goose Lock & Dam 
Initial Project 160,413,215 160,413,215 160,413,215 25,735,195 25,598,509 100 FY 63 
Power Units 4-6 59,885,312 59,885,312 59,885,311 - - 100 FY 74 
Totals 220,298,527 220,298,527 220,298,526 25,735,195 25,598,509 100 
Lower Granite 
Lock & Dam 
Initial Project 321,399,315 321,099,315 321,087,398 25,238,897 25,026,691 99 FY 65 
Power Units 4-6 46,211,511 46,211,511 46,211,510 - - 10() FY 74 
Totals 367,610,826 367,310,826 628,8,908897 25,026,691 99 
Lower Monumental 
Lock & Dam 
Initial Project 184,712,361 184,712,361 184,712,361 23,226,273 23,184,689 100 FY 61 
Power Units 4-6 51 645,850 51,645,850 51,644,936 -- 100 FY 75 
Totals 3 21 236,358,211 236,357,297 23,226,273 23,184,689 100 
Open River Lewiston to 
Johnson Bar Landing 34,613 34,613' 34,613' 320,603 320,5552 
Open River Pasco to 
Lewiston - - 4,350 4,350 
Totals Existing 
Project 992,224,674 990,993,824 990,979,991 111,725,892 111,311,581 99 
Previous Projects 
Pasco to Lewiston 400,150 400,150 400,150 186,570 186,570 
Totals Authorized 
Project 992,624,824 991,393,974 991,380,141 111,912,462 111,498,151 
'New work appropriations used for maintenance prior 
to 1953. 
"Includes $48,009 FY 1983 project condition survey cost. 
39-26

ALASKA DISTRICT* 
This District consists of the State of Alaska.
IMPROVEMENTS 
Navigation 
Anchorage Harbor, AK.................. 
Bar Point Harbor, AK ................... 
Bethel Small Boat Harbor, AK ........... 
Cordova Small Boat Harbor, AK ......... 
Craig Small Boat Harbor, AK ............ 
Dillingham Harbor, AK................. 
Dry Pass, AK .......................... 
Homer Harbor, AK ...................... 
Hoonah Harbor, AK ..................... 
Kake Harbor, AK ........................ 
Metlakatla Harbor, AK .............. ... 
Ninilchik Harbor, AK .................... 
Nome Harbor, AK ....................... 
Port Lions Small Boat Harbor, AK ...... . 
Stikine River, AK ........................ 
Flood Control 
Chena River Lakes, AK.................. 
Flood Control Work Under 
Special Authorization .................... 
Page 18. Inspection of Completed Flood 
Control Projects ........................ 
40-1 19. Inspection of Non-Federal Levees ......... 
40-2 
40-2 Multiple-Purpose Projects, 
40-2 Including Power 
40-2 20. Snettisham, AK ........................ 
40-3 
40-3 
40-3 
40-3 
40-4 
40-4 
40-4 
40-5 
40-5 
40-5 
General Investigations 
21. Surveys................................. 
22. Collection and Study of Basic Data ....... 
23. Advance Engineering and Design ........ 
Tables 
Table 40-A 
Table 40-B 
Table 40-C 
Table 40-E 
Table 40-G 
40-6 Table 40-H 
40-6 Table 40-I 
Page 
40-6 
40-6 
Page 
40-6 
40-7 
40-7 
40-7 
Cost & Financial Statement .... 40-8 
Authorizing Legislation ........ 40-10 
Other Authorized Navigation 
Projects ...................... 40-12 
Other Authorized Flood Control 
Projects ....................... 40-13 
Deauthorized Projects......... 40-13 
Navigation Work Under Special 
Authorization ................ 40-14 
Project Condition Surveys ...... 40-15 
Navigation 
1. ANCHORAGE HARBOR, AK 
Location. Anchorage is in southcentral Alaska on 
the southeast shore of Knik Arm, north of 'Turnagain 
Arm near its junction with Cook Inlet. (See NOAA 
Charts 16660 and 16664.) 
Existing project. Provides for dredging along a 
3,000-foot baseline adjacent to the Port of Anchorage 
dock to a depth of 35 feet below mean lower low water. 
Tidal range between mean lower low water and mean 
higher high water is 29.0 feet and the extreme range is 
42.0 feet. 
Local cooperation. Fully complied with. 
Terminal facilities. The Port of Anchorage facility 
consists of a POL terminal at the southern end and three 
general cargo terminals northward. The northernmost 
terminal, completed during 1976 and 1977 was outside 
the Federal project limits. Extension of limits from 2,070 
feet northward to 3,000 feet was authorized by Public 
Law 94-587, and funded in FY 1978. 
Operations during fiscal year. Regular funds, 
maintenance: The maintenance dredging contract was 
awarded in June 1983 and 379,000 cubic yards of material 
were removed by the contractor. Excessive shoaling 
continued throughout the year which forced the contractor 
to concentrate his efforts along the dock. 
Maintenance dredging was accomplished across the 
entire project during 1983 with the area adjacent to the 
dock face dredged to the authorized depth of -35 feet 
mean lower low water. Controlling depth at the close of 
the contract was -34 feet MLLW along the face of the 
dock with the remaining areas varying between -30 and 
-40 MLLW. 
40-1 
1. 
2. 
3. 
4. 
5. 
6. 
7. 
8. 
9. 
10. 
11. 
12. 
13. 
14. 
15. 
16. 
17.

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
2. BAR POINT HARBOR, AK 
Location. On coast of Revillagigedo Island, on northeasterly 
side on Tongass Narrows. Ketchikan is approximately 
220 nautical miles southeast of Juneau, AK. 
(See Coast and Geodetic Survey Charts 8075, 8094, and 
8095.) 
Existing project. As originally authorized and constructed, 
Bar Point Basin consisted of a 780,000 square 
foot basin at depths of 10 and 15 feet below mean lower 
low water, protected by three rock breakwaters. An 
additional 25 acres protected by a 960-foot long floating 
breakwater has been added and the State of Alaska is in 
the process of adding additional floats to this area. Tidal 
range between mean lower low water and mean higher 
high water is 15.3 feet, with an extreme range of 26 feet. 
Local cooperation. Fully complied with. 
Terminal facilities. Publicly owned facilities are 
four small-boat floats, including two in project basins, 
and two ferry docks. Privately owned facilities include 
two general cargo docks open to public use, one of which 
serves as a passenger terminal; three oil wharves, which 
include facilities for fueling small boats; and approximately 
25 industrial wharves, piers, and floats. Additional 
facilities are available at Saxman and Ward Cove 
in the immediate area. One wharf is used exclusively for 
Government vessels. 
Operations during fiscal year. Regular funds, 
maintenance: Bids were solicited in September 1983 to 
retorque connecting rods and bolts on the floating 
breakwater. 
3. BETHEL SMALL BOAT HARBOR, AK 
Location. The city of Bethel is 65 miles upriver on the 
north bank of the Kuskokwim River, which flows 
through southwestern Alaska. Bethel is about 400 miles 
west of Anchorage. (See Coast and Geodetic Survey 
Chart 9302 and USGS Map Bethel D8.) 
Existing project. Project (Section 107) includes provision 
of a 12-acre small boat harbor and 1,270 foot 
entrance channel by deepening, widening, and straightening 
a portion of the Lousetown Slough which is 0.3 
miles east of Bethel. Range between mean lower low 
water and mean higher high water is 4.0 feet and 
extreme tidal range is 10.0 feet, during low summer 
water flow in Kuskokwim River. Water level also 
depends on river state; tidal effects decrease with higher 
river flows, disappearing only at the 20-year-frequency 
flood stage. 
Local cooperation. Fully complied with. 
Terminal facilities. Bethel serves as a regional 
transportation center for approximately 50 villages. A 
medium-draft port facility was built along the city's 
riverfront in 1975. Goods, including gas, oil, food, clothing, 
and construction material are all brought into 
Bethel for redistribution to outlying villages. Generally, 
river shipments of bulk goods are transported by 
medium-draft barges. Personal supplies are often moved 
in individually owned riverboats which also are used for 
fishing activities. The riverboat fleet in Bethel is estimated 
to number between 1,000 and 1,100 boats, of 
which 400 are transient boats from other villages along 
the Kuskokwim River. There are also eight river barges 
varying in size to as large as 30 by 100 feet. The barges 
are powered by five locally-based tug boats with lengths 
ranging from 25 to 40 feet. No protected berthing areas 
exist at Bethel for any water craft. The riverboats are 
beached on the sandbars and banks for temporary storage. 
Brown's Slough is particularly popular as a berthing 
area, resulting in overcrowding and congestion. 
Operations during fiscal year. Regular funds, new 
work: The contract awarded in September 1982 was 
completed in August 1983. 
4. CORDOVA SMALL BOAT HARBOR, AK 
Location. Cordova is on Orca Inlet, a strait near the 
eastern entrance of Prince William Sound, about 150 air 
miles south-southeast of Anchorage, Alaska. (See Coast 
and Geodetic Survey Charts 8520, 8525, and 8551.) 
Existing project. The Office of the Chief of Engineers 
approved construction of a harbor expansion from 
8.26 acres to 20 acres by removal of the existing 1400-foot 
breakwater and construction of a new 2000-foot long 
breakwater. The entrance channel is dredged to -16 feet 
mean lower low water and the turning basin is dredged 
from -10 to -12 mean lower low water. Tidal range 
between mean lower low water and mean higher high 
water is 12.4 feet with an extreme range of 21.7 feet. The 
dredged material is disposed of in two diked upper tidal 
areas which will be used as staging facilities. * 
Local cooperation. Fully complied with. 
Terminal Facilities. Two municipal docks accommodate 
general cargo and passengers, including automobile 
ferry traffic. One privately owned wharf, reduced 
by fire, provides oil handling and bunkering facilities. 
Three privately owned wharves are used for industrial 
purposes. A small boat float system for public use is in 
original basin. State ferry dock in basin has been superseded 
by municipal dock and is inactive. Facilities are 
considered adequate for present commerce. 
Operations during fiscal year. Regular funds, new 
work: Contract was awarded May 15, 1981 for construction 
of breakwater, diked disposal areas and dredging of 
existing and new harbor areas. All harbor structures 
were completed July 1983. Floats in new area are being 
installed by city of Cordova. 
5. CRAIG SMALL BOAT HARBOR, AK 
Location. Craig is located on Craig Island, adjacent 
to Prince of Wales Island in southeastern Alaska, about 
200 Survmeyi les south of Juneau. (See Coast and Geodetic Charts 8152 and 8155.) 
Existing project. The Office of the Chief of Engineers 
approved construction for navigation improvements 
at South Cove Harbor at Craig, AK on February 
19,1980. Improvements consisted of construction of two 
short rubblemound breakwaters, a 70-foot-long north 
breakwater and a 200-foot-long south breakwater. Tidal 
range between mean lower low water and mean higher 
high water is 10 feet, with an extreme range of 18 feet. 
Local cooperation. Fully complied with. 
40-2

ALASKA DISTRICT 
Terminal facilities. Publicly owned facilities are 
one general cargo wharf and three small boat floats, 
including one in project basin. Privately owned facilities 
are two oil piers and several industrial wharves. One 
float is used by Government boats. 
Operations during fiscal year. Regular funds, new 
work: Fiscally completed. Contract to extend the north 
breakwater 40 feet was awarded October 16, 1981 and 
completed January 13, 1982 ahead of schedule. 
6. DILLINGHAM HARBOR, AK 
Location. At head of Nushagak Bay, an arm of Bristol 
Bay, on right bank of Nushagak River just below its 
confluence with Wood River; about 470 miles northeasterly 
of Dutch Harbor and 300 miles southwest of 
Anchorage, AK. (See Coast and Geodetic Survey Chart 
9052.) 
Existing project. A small-boat basin 230,000 square 
feet in area with a depth of 2 feet above mean lower low 
water along Scandinavian Creek; with entrance channel 
1,100 feet long and 40 feet wide in Scandinavian 
Creek; and a sheet pile sill across the basin outlet with a 
top elevation of 7 feet above mean lower low water. 
During design stage the project was revised to include a 
rock sill with adjacent scour-protection blankets and the 
embankment was relocated to include a berm between 
the basin and the embankment. Tidal range between 
mean lower low water and mean higher high water is 
19.8 feet. Extreme range is 30.0 feet. 
Local cooperation. Fully complied with. 
Terminal facilities. Three docks at the city of Dillingham, 
all privately owned, and a publicly owned 
small-boat float in the project basin. Two docks are used 
for salmon-cannery operations; the third is an oil handling 
and bunkering terminal. Small boat approach and 
floats were installed in small-boat basin in summer of 
1963, and were demolished by winter ice movement. 
New floats were installed in June 1982, and removed 
before fall freezeup. They will be replaced each spring. 
Cargo and passengers from ocean vessels are lightered 
from the anchorage just below Snag Point, and are 
unloaded at the docks or in the small-boat basin. Facilities 
are considered adequate for existing commerce. 
Operations during fiscal year. Regular funds, 
maintenance: Government plant and hired labor performed 
maintenance dredging from June through September 
1983.77,700 cubic yards ofmaterial were dredged 
this fiscal year. 
7. DRY PASS, AK 
Location. Dry Pass is a 2-V2-mile section of a natural 
waterway between Kosciusko and Prince of Wales 
Islands, in southeastern Alaska. It forms a portion of 
the extensive network of sheltered waterways between 
Ketchikan and Juneau and is used by fishing vessels 
and log rafts. (See U.S. Coast and Geodetic Survey 
Charts Nos. 8172 and 8152.) 
Existing project. The original project provided for 
dredging of a channel 60 feet wide and 6 feet deep at 
mean lower low water through five shoals between El1 
Capitan Passage and Shakan Strait. This project was 
modified in 1954 to provide a channel 70 feet wide and 12 
feet deep at mean lower low water through 7 shoals. The 
tidal range between mean lower low water and mean 
higher high water is 11.7 feet and the extreme range is 
about 19 feet. 
Local cooperation. None required. 
Terminal facilities. The improvement forms a part 
of an existing trade route. There are no terminal facilities 
within the limits of the improvement. 
Operations during fiscal year. Regular funds, 
maintenance: The scope of the project was reanalyzed 
and a new cost estimate prepared. No construction 
funds were provided. 
8. HOMER HARBOR, AK 
Location. In Kachemak Bay, on Kenai Peninsula, 
152 miles by water southwest of Anchorage. Harbor site 
is land based near the extremity of Homer Spit which 
varies to one-quarter mile in width and extends 4.5 miles 
southeasterly from the mainland. (See Coast and Geodetic 
Survey Charts 8554 and 8531.) 
Existing project. Provides for sheltered small-boat 
harbor, relocated and based within Homer Spit about 10 
acres in area, with a 2.75-acre berthing area 14 feet deep 
and a 7.25-acre anchorage area 15 feet deep, below mean 
lower low water; a north entrance channel; protected by 
a main rock breakwater 1,018 feet long and secondary 
rock breakwater 238 feet long. Tidal range between 
mean lower low and mean higher high water is 18.1 feet, 
with an extreme range of 30.4 feet. (For details relating 
to previous projects, see page 1593 of Annual Report for 
1964.) 
Local cooperation. Fully complied with. 
Terminal facilities. One publicly owned and operated 
wharf capable of handling oceangoing vessels 
serves for passengers and general cargo. Small-boat 
facilities in basin area include publicly owned mooring 
floats, a publicly owned wharf, and an industrial wharf. 
A separate basin with unloading facilities for barges 
and small boats is being constructed by private interests. 
A detailed project report has been prepared recommending 
doubling the size of the harbor. The city of 
Homer has tripled the size of its fish dock located at the 
southern end of the harbor. 
Operations during fiscal year. Regular funds, 
maintenance: During FY 1983, 11,500 cubic yards were 
removed by the Government-owned pipeline dredge 
Warren George. The material was disposed of in a low 
depression located on the southern tip of the spit. 
9. HOONAH HARBOR, AK 
Location. Hoonah is located on the eastern shore of 
Port Frederick, a deep tidal fjord on the northeastern 
shore of Chichagof Island in southeastern Alaska. The 
city is 70 miles west of Juneau. (See National Geodetic 
Survey Charts 8202 and 8302.) 
Existing project. Consists of an authorized smallboat 
basin 16 acres in extent, and an entrance channel 
40-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
and turning basin; with the entrance channel 100 feet 
wide and 400 feet long (widening to 150 feet for 600 feet 
along the western edge of the basin) all to a depth of 18.5 
feet below mean lower low water, three rubblemound 
breakwaters 140,800 and 1,459 feet long; and one rubblemound 
diversion dike 1,165 feet long. Tidal range 
between mean lower low water and mean higher high 
water is 14.8 feet. Extreme tidal range is 25 feet. Total 
project cost of the basin is $4,255,000 Corps of Engineers 
funds. 
Local cooperation. Fully complied with. 
Terminal facilities. Publicly owned facilities are 
two general cargo docks, a ferry dock and a small-boat 
float attached to one of the cargo docks. Privately owned 
facilities are one oil dock and one industrial-oil dock. 
Facilities are not sufficient or suitable for moorage of 
more than a small portion of the resident and transient 
commercial fishing vessels operating Hoonah. The constructed 
harbor will provide the necessary moorage. 
Operations during fiscal year. Regular funds, new 
work: Fiscally completed after claim settlement. 
10. KAKE HARBOR, AK 
Location. Kake Harbor is located in the city of Kake, 
on the northwest corner of Kupreanof Island in southeastern 
Alaska, 39 air miles west of Petersburg, AK, and 
850 water miles northwesterly of Seattle, WA. (See Coast 
and Geodetic Chart 8201.) 
Existing project. The authorized project consists of 
a 1,580-foot-long west breakwater and a 900-foot long 
south breakwater, enclosing a 7-acre berthing area. Poor 
foundation conditions found during preconstruction investigations 
have forced modification of the project to 
include a 1,760-foot-long west breakwater and a 1,750- 
foot-long south breakwater. Estimated project cost is 
$11,434,000 (October 1983), including $11,400,000 Corps 
of Engineers funds, $20,000 Coast Guard funds, and 
$14,000 non-Federal cost. Tidal range between mean 
lower low water and mean higher water is 14.0 feet with 
an extreme range of 22 feet. 
Local cooperation. Fully complied with. 
Terminal facilities. At Kake, a publicly owned 
wharf with seaplane float equipped airplanes and shallowdraft 
vessels is located within area of proposed basin. At 
cannery 1 mile from city, there are two privately owned 
deep-draft piers: one for cargo, open to all local boat 
owners, the second for fuel, including a float for fueling 
small boats. At Portage Cove, there is one publiclyowned 
small-boat float. Facilities are not considered 
adequate for present commerce due to the following 
deficiencies in small-boat facilities: the complete lack of 
protection in the directions of the most severe storms; 
shallow water at Portage Cove float and its approaches; 
ice formation on the cove during the winter months 
causes major boat damage and limits the use of the 
mooring float; and traAsportation problems between 
city and present small-boat float at Portage Cove. 
Operations during fiscal year. A biological study 
was initiated to investigate the aquatic habitats and 
organisms of the project area through the use of a joint 
United States Fish and Wildlife Service - Corps of Engineers 
dive effort. The data being gathered will be used to 
understand temporal changes in these natural systems, 
pre- and post-project conditions, as well as provide 
background information for a recolonization study of 
man-made rubble structures in Alaska. The initial 
phase of the study is to be completed after a final field 
investigation during the spring of 1984. A temporary 
automatic meteorburst wind monitoring station was 
established at Kake in June 1983 to gather wind velocity 
and directional data more closely associated with the 
location of the project for comparison with data used in 
complying with the plans and specifications. 
11. METLAKATLA HARBOR, AK 
Location. Metlakatla is located in the southern portion 
of Port Chester, a small bay on the northwest coast 
of Annette Island in southeastern Alaska, 18 miles 
south of Ketchikan. (See Coast and Geodetic Charts 
8074, 8075, and 8102.) 
Existing project. Consists of two small-boat basins. 
Existing basin is 2.18 acres in extent with a depth of 10 
feet below mean lower low water, protected by a rubblemound 
breakwater 900 feet long. New basin consists of 
two rubblemound breakw,aters, 1,255 and 1,150 feet 
long, and an entrance channel and maneuvering area, 
1,100 feet long, 100 feet wide, dredged to a depth of 15 feet 
below mean lower low water and a basin area of 6.25 
acres dredged to a depth of 15 feet below mean lower low 
water. Tidal range between mean lower low water and 
mean higher high water is 14.7 feet, with an extreme 
range of 24 feet. Total project cost of basin is $5,101,470 
Corps of Engineers funds. 
Local cooperation. Fully complied with. 
Terminal facilities. Publicly owned facilities are 
one general-cargo dock, one barge ramp, and a smallboat 
float system in existing basin. Privately owned 
facilities are one oil pier and one industrial wharf. Facilities 
are not adequate for mooring the commercial fishing 
vessels operating from Metlakatla. Existing protected 
harbor area is fully utilized. 
Operations during fiscal year. Regular funds, new 
work: Construction is essentially complete with some 
underwater removal of isolated rocks to be completed by 
January 1984. 
12. NINILCHIK HARBOR, AK 
Location. At mouth of Ninilchik River in Cook Inlet, 
at the community of Ninilchik, AK, about 40 miles 
upcoast from Homer and 112 miles southwest of 
Anchorage. (See Coast and Geodetic Survey Chart 
8554.) 
Existing project. A small-boat basin 320 feet long 
by 150 feet wide dredged to elevation of 2 feet above 
mean lower low water, with an approach channel 400 
feet long and 50 feet wide dredged to an elevation of 9 
feet above mean lower low water; protected by a pile 
jetty 410 feet long. Project was modified in design stage 
to delete pile jetty and revise harbor dimensions to 400 
feet long by 125 feet wide, and was completed in 
November 1961. Modification, including river channel 
40-4

ALASKA DISTRICT 
diversion, two armor rock jetties, and beach protection, 
was accomplished in 1967 and 1969. Range between 
mean lower low water and mean higher high water is 
19.1 feet, with an extreme range of 33.5 feet. 
Local cooperation. Fully complied with. 
Terminal facilities. Facilities, limited to shallowdraft 
vessels and accessible from Cook Inlet only at 
half-tide or higher, are a cannery dock along Ninilchik 
River available for offloading fish, and small-boat floats 
in project basin, provided by State of Alaska. Other 
supplies are landed on beach or brought by road from 
deep-draft ports in the vicinity. Facilities are extremely 
inadequate for the number of boats presently using harbor. 
Expansion of facilities would require construction 
of additional protected harbor area. 
Operations during fiscal year. Regular funds, 
maintenance: Maintenance dredging of the harbor and 
entrance channel was accomplished with 7,100 cubic 
yards removed in 1983. A survey of the basin during 
June 1983 indicated project depth was available 
throughout the Federal limits. 
13. NOME HARBOR, AK 
Location. At mouth of Snake River at the city of 
Nome, AK, on northerly shore of Norton Sound, an arm 
of Bering Sea. It is a shallow open roadstead, 581 nautical 
miles north of Dutch Harbor and 545 air miles 
northwest of Anchorage. (See Coast and Geodetic Survey 
Charts 9302 and 9380.) 
Existing project. Provides for two jetties, the easterly 
951 and the westerly not exceeding 676 feet long, at 
mouth of Snake River; a channel 8 feet at mean lower 
low water, 75 feet wide, from Norton Sound through 
Snake River to mouths of Bourbon and Dry Creeks, in 
city of Nome, ending in a turning basin of the same 
depth, 250 feet wide and 600 feet long; revetting banks of 
rivers; and protecting all existing water-front improvements 
on easterly beach by means of rock-mound seawall 
3,350 feet long extending easterly from east jetty. 
Project has been completed except extension of jetties 
beyond present 400 and 240 feet, which is classified 
inactive. Range between mean lower low water and 
mean higher high water is 1.6 feet and extreme tidal 
range is 7.5 feet, but water levels are influenced more by 
wind than tide. Levels of 5 feet below mean lower low 
water have been observed during offshore winds, and a 
level of 14 feet above mean lower low water has been 
observed during a southerly storm. 
Local cooperation. Fully complied with. 
Terminal facilities. Cargoes and passengers from 
ocean vessels are lightered to and from shore a distance 
of about 2 miles. Traffic enters dredged channel and is 
handled over revetment, where lighterage company has 
transfer facilities which are open to the public. Facilities 
considered inadequate for existing commerce. The State 
of Alaska is conducting a study of the feasibility of 
constructing a causeway with unloading facilities and 
docking berths for deep draft vessels. If constructed, the 
proposal calls for modifying the existing harbor into a 
small boat basin requiring shallower draft. 
Operations during fiscal year. Regular funds, 
maintenance: Maintenance dredging by contract was 
accomplished throughout the ice-free season. 14,300 
cubic yards were removed in FY 1983. Damage to the 
East Jetty during spring 1982 caused a separation of the 
last 40 feet. Removal of the damaged section and capping 
of the remaining jetty was not accomplished pending 
further study. An underwater inspection was 
accomplished in September 1983 and a reconnaissance 
report on rehabilitating the project will be prepared in 
FY 1984. 
14. PORT LIONS SMALL BOAT HARBOR, AK 
Location. Port Lions is located on the north end of 
Kodiak Island, approximately 19 air miles west of the 
city of Kodiak. (See Coast and Geodetic Survey Chart 
8534.) 
Existing project. The Office of the Chief of Engineers 
approved construction for a small boat harbor at 
Port Lions on April 9, 1979. Construction consisted of a 
600-foot-long breakwater, a 170-foot-long stub breakwater 
inclosing a 12-acre harbor. Tidal range between 
mean lower low water and mean higher high water is 9.6 
feet with an extreme range of 18 feet. 
A severe storm in November 1981 badly damaged the 
project. The repair work includes replacing material of 
the existing main breakwater, extending the main 
breakwater 125 feet, changing the seaward breakwater 
slope to a 2.OH:1.OV adding a layer of armor rock and 
raising the design crest elevation from +18.5 mean lower 
low water to +22.0 mean lower low water. Minor dredging 
in the entrance channel to -15.0 mean lower low 
water is also included. 
Local cooperation. Fully complied with. 
Terminal facilities. A municipal timber pile dock at 
Port Wakefield serves as both a shallow-draft and deepdraft 
facility for Port Lions. 
Operations during fiscal year. Regular funds, 
maintenance. The contract for the repair work was 
awarded on October 12, 1982 and re-construction of 
breakwater was complete as of September 30, 1983. 
15. STIKINE RIVER, AK 
Location. Rises in northwestern Canada and flows 
southwesterly through Canada for about 200 miles, then 
about 30 miles westerly across Panhandle of Alaska to 
Sumner Strait. Mouth of river is on coast of mainland 
about 3 miles north of Wrangell. (See Coast and Geodetic 
Survey Chart 8201.) 
Existing project. Snagging Stikine River from its 
mouth for about 30 miles to Canadian border. The Canadian 
Government maintains that portion of the river 
between Alaskan border and Telegraph Creek, British 
Columbia, a distance of 130 miles. The head of navigation 
is at Telegraph Creek, B.C., about 160 miles above 
the mouth. No data is available concerning stages of 
high and low water in river. At mouth, tidal range 
between mean lower low water and mean higher high 
water is 13.9 feet, and maximum range is about 
40-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
25 feet. Tidal effects have been reported at a distance of 
20 miles from the mouth. 
Local cooperation. None required. 
Terminal facilities. None along Alaskan portion of 
river. Vessels operating on Stikine River are dependent 
on terminal facilities at Wrangell Harbor. Facilities 
include a city operated pier for general cargo and passengers; 
two publicly operated small-boat mooring floats; 
two privately operated small-boat fueling floats; a State 
of Alaska Ferry Pier, and three industrial wharves. 
Operations during fiscal year. Regular funds, 
maintenance: Memorandum of Understanding between 
Corps and Forest Service signed August 1972 provided 
for Forest Service personnel to do project clearing. However, 
due to environmental restraints, no work was 
accomplished until 1977 after completion of an environmental 
assessment. The work has been accomplished 
annually by the U.S. Forest Service since 1977. 
Flood Control 
16. CHENA RIVER LAKES, AK 
Location. In the vicinity of Fairbanks, AK, and 
encompassing the Tanana River, Chena River, Little 
Chena River, and their tributaries. (See USGS map 
Fairbanks, Cl, D1, D2, and Big Delta D6.) 
Local cooperation. Fully complied with. 
Existing project. Moose Creek Dam has been constructed 
17 miles east of Fairbanks with control works 
on Chena River. The dam itself extends from a bluff one 
mile north of the Chena River and south past the control 
works for approximately six miles to the Tanana River. 
The dam connects with a completed 22-mile levee system 
along the north boundary of the Tanana River to a 
point south and west of Fairbanks. Estimated Federal 
cost is $262,000,000, (full funding), and estimated non- 
Federal cost is $12,447,000. 
Operations during fiscal year. Regular funds, new 
work: Contracts were awarded for installing safety catwalks 
on the control works fish ladder and modifications 
were made to the control works for the storage of 
emergency gates. Interior Drainage Channel "A" was 
completed and work on the Recreation Area was initiated 
with the contract 60 percent complete at the end of the 
fiscal year. Work on clearing brush from the floodway 
and seepage control channels plus repairs to an earthen 
dam slough block were completed. The access road from 
trhelei emf waienll sh aiglohnwga tyh teo d tahme cnoonrttrho l works was paved and of the Chena River were 
installed by in-house forces. The Tanana River Levee 
system is complete except for anticipated repair work 
due to settling and construction of protective groins. 
17. FLOOD CONTROL WORK UNDER SPECIAL 
AUTHORIZATION 
Flood Control Activities, Section 205, Public 
Law 80-858. 
Fiscal year preauthorization study costs for Skagway 
River, AK, were $7,500. 
Emergency Bank Protection, Section 14 of 1946 
Flood Control Act, Public Law 79-526. 
Fiscal year preauthorization study costs for Yukon 
River, Galena, AK, were $7,500. 
Emergency flood control activities - repair, 
flood fighting, and rescue work (Public Law 99, 
84th Congress, and antecedent legislation). 
Federal costs for the fiscal year were $89,914 for disaster 
preparedness, $18,636 for emergency operations, and 
$350 for advance measures. 
18. INSPECTION OF COMPLETED FLOOD 
CONTROL PROJECTS 
Inspections were made of flood control works at 
Lowell Creek on January 20,1983, Gold Creek, Skagway 
River and Salmon River during October 25-28, 1982. 
Repairs at each project were recommended to the local 
authority. Total costs for the fiscal year: $11,918. 
19. INSPECTION OF NON-FEDERAL LEVEES 
Inspections were made of levees rehabilitated under 
Public Law 84-99 and local sponsors advised of results 
and recommendations. Fiscal year costs were $784. 
Multiple-Purpose rojects, 
Including Power 
20. SNETTISHAM, AK 
Location. At mouth of Speel River, between Crater 
Lake to the west and Long Lake to the north, 28 nautical 
miles southeast of Juneau, AK. (See Coast Geodetic 
Survey Chart 8227.) 
Existing project. Snettisham is a multi-stage power 
project. The initial stage which was completed in 1977 
tapped Long Lake and included an underground powerhouse 
with two 26.9 megawatt units and two transmission 
lines to Juneau, AK. The project was turned 
over to the Alaska Power Administration for operation 
and maintenance. The second stage, (under design), 
would provide a tap to Crater Lake and add a third unit. 
The final stage will provide a dam on Long Lake to 
increase storage and the energy capability of Long 
Lake. The Long Lake Dam is in a "Deferred" status. The 
existing Long Lake (elevation 815 feet) water is transported 
through an approximately horizontal tunnel 
8,400 feet long and a 1,400-foot penstock dropping at a 46 
degree angle to the undergound powerhouse at tidewater 
to drive two turbines with a combined generating 
cisa psuacpiptyli eodf 5t3o, 7J0u5n keialouw bayt ts1.3 P8 okwielorv forlotm o vtweroh geeande rtartaonrssmission 
lines and a submarine cable traversing Taku 
Inlet. Crater Lake phase of construction provides for 
tapping Crater Lake (elevation 1,022 feet) to drive a 
third turbine to be installed in the existing underground 
powerhouse to provide an additional generating capacity 
of 31,050 kilowatts. Estimated cost of initial stage 
construction is $150,000,000 (October 1983). 
Local cooperation. None required. 
Operations during fiscal year. Regular funds, new 
work: Engineering and Design on the Crater Lake 
40-6

ALASKA DISTRICT 
Phase included approximately 90 percent completion of 
the feature design memorandum for power tunnel, penstock, 
lake tap, gate structure and surge tank; 100 percent 
completion of plans and specifications for the 
access road and construction camp facilities and 95 percent 
completion of plans and specifications for turbine, 
generator, powerhouse completion and electrical contracts. 
Investigations included an evaluation of alternative 
power tunnel and surge tank schemes and an extensive 
study using side scan sonar and sub-bottom profiling 
to determine the amount of overburden and bedrock 
conditions in the lake tap area. 
General Investigations 
21. SURVEYS 
Fiscal year costs of $1,577,240 for surveys include 
$235,645 for navigation studies, $1,173,595 for flood control 
studies, $41,000 for coordination studies and $127,000 
for miscellaneous activities. 
22. COLLECTION AND STUDY 
OF BASIC DATA 
Technical assistance, information, flood plain management 
guidance and other flood plain management 
services have been provided to military and nonmilitary 
Federal agencies, local communities, State agencies, 
Architectural/Engineering firms, lending institutions 
and private individuals at a fiscal year cost of $156,779. 
Other activities included initiation of Type 19 Flood 
Insurance Studies for the Municipality of Anchorage 
and the Matanuska-Susitna Borough. 
Fiscal year costs for Hydrologic Studies were $11,250. 
23. ADVANCE ENGINEERING AND DESIGN 
Bradley Lake, AK. Bradley Lake, AK is located at 
the head of Kachemak Bay near the southwestern end of 
Kenai Peninsula about 110 air miles south of Anchorage 
and 25 miles northeast of Homer. The project was authorized 
under the Flood Control Act of October 23, 1962. 
The proposed project included construction of a concrete 
gravity dam 850 feet in length and 130 feet in 
height, a 17,310-foot long power tunnel, a 23.5-foot 
diameter surge tank, a 2,711-foot long x 11-foot diameter 
steel penstock, an above ground powerhouse with three 
Francis-type turbine units (135,000 KW capacity), and 
an 18-mile wood pole transmission line (115 KV). 
The project was deauthorized by Public Law 97-377, 
Section 149, December 21, 1982 because completion of 
design and full construction has been assumed by the 
State of Alaska. 
Fiscal year costs were $189,484 of General Investigations 
Funds and $114,662 of Construction, General 
Funds for a combined total of $304,146. Total cost to 
September 30, 1983 is $6,701,000. 
40-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 40-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
In Text Project Funding FY 80 FY 81 FY 82 FY 83 Sep. 30, 19836 
1. Anchorage Harbor. New Work 
2. Bar Point Harbor, 
AK 
(Contrib. Funds) 
3. Bethel Small Boat 
Harbor, AK 
(Contrib. Funds) 
4. Cordova Small Boat 
Harbor, AK 
(Contrib. Funds) 
5. Craig Small Boat 
Harbor, AK 
6. Dillingham Harbor, 
AK 
(Contrib. Funds) 
7. Dry Pass, AK 
8. Homer Harbor, AK 
AK 533,235 
533,235 
1,196,700 1,935,000 2,374,900 964,000 
1,387,648 1,923,216 2,001,021 1,225,405 
343,792 
806,461 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
2,871 
499 
695 
26,785 
163 
22,000 
23,345 
14,500 690,000 307,000 
25,855 73,665 915,017 
2,000,000 -1,284,600 
101,000 1,410,000 299,975 
94,041 1,166,754 550,205 
- 4,647,200 
- 2,403,878 
43,700 590,000 
28,633 468,136 
-633 
- 113,000 
1,954,080 301,525 
-37,000 
99,416 515 
841,000 331,000 384,500 266,000 
335,076 808,750 352,356 295,862 
1,700 - - - 
1,700 - - - 
25,000 
14,468 8,461 
247,000 267,000 296,400 294,000 
268,821 249,473 288,570 316,897 
12,549,447 
12,417,997 
2,000,000 
2,000,000 
22,000 
272,7794 
272,7794 
1,520,272 
1,511,954 
715,4004 
715,4004 
2,000,000 
1,998,973 
4,760,200 
4,659,483 
656,240 
656,240 
548,790 
548,790 
4,216,821 
4,181,189 
1,700 
1,700 
943,351 
943,351 
25,000 
22,929 
1,512,349 
1,512,349 
2,278,711 
2,276,207 
67,974 
67,974 
40-8 
240,495 
208,000 
201,645

ALASKA DISTRICT 
TABLE 40-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
In Text Project Funding FY 80 FY 81 FY 82 FY 83 Sep. 30, 1983 
9. Hoonah Harbor, 
AK 
(Contrib. Funds) 
10. Kake Harbor, AK 
11. Metlakatla Harbor, 
AK 
(Contrib. Funds) 
12. Ninilchik Harbor, 
AK 
13. Nome Harbor, AK 
(Contrib. Funds) 
14. Port Lions Small 
Boat Harbor, AK 
(Contrib. Funds) 
15. Stikine River, AK 
16. Chena River Lakes, 
AK 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Maint. 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
2,243,000 
2,244,096 
113,525 
255,000 
253,210 
400,000 
279,627 
38,190 
80,000 
79,588 
3,160,000 860,000 
3,116,770 184,628 
- -100,000 
21,612 18 
- 120,000 
2,685 91,298 
621,898 
-25,000 
28,597 
4,255,000 
4,255,000 
973,8754 
973,8754 
760,700 
731,997 
5,076,470 
5,032,170 
50,520 
50,520 
- - 200,000 - 
328,483 329,656 200,007 - 
208,000 216,000 270,700 237,000 
206,635 216,881 260,871 244,916 
506,000 488,000 753,700 291,000 
472,901 475,218 432,511 532,403 
2,500 
2,500 
2,500 
70,000 1,700,000 
19,823 1,697,929 
2,500 
5,000 
-7,000 
44,738 
2,500 
80,000 1,600,000 
32,008 1,555,354 
14,000 
8,249 
44,000 
41,537 
5,000 
7,451 
1,110,000 
22,000 
17,544 
- 
904,018 
4,000 
10,000 
828,0004 
828,0004 
428,720 
428,720 
2,664,476 
2,662,037 
1,348,240 
1,348,240 
6,120,907 
5,994,709 
125 
125 
152,500 
150,000 
1,825,311 
1,824,801 
1,680,000 
1,587,362 
1,061,1374 
945,5554 
151,364 
149,572 
8,770,000 14,758,806 15,100,000 13,900,000 184,758,4652 
8,752,012 14,726,776 14,794,879 13,522,702 183,909,8972 
- 350,000 459,700 538,000 
- 176,685 571,821 536,356 
1,349,324 
1,286,486' 
40-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 40-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
In Text Project Funding FY 80 FY 81 FY 82 FY 83 Sep. 30, 1983 
Maint. 
Contrib. - - - 2,031,700 2,031,700 
Cost - - - 1,616,440 1,616,440 
20. Snettisham, AK New Work 
Approp. -18,200 - 2,000,000 570,000 83,952,856 
Cost -19,239 4,872 1,347,018 1,157,838 83,887,443 
'Includes $2,672 of code 710 Rec. Funds. 4Includes only actual funds received and costs incurred. 
2Includes $310,000 for previous project (Fairbanks). 5Cumulative maintenance totals no longer include Proj- 
3Includes $1,624 for previous project (Fairbanks). ect Condition survey appropriations and costs. 
TABLE 40-B AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
1. ANCHORAGE HARBOR. AK 
July 3, 1958 
Oct. 22, 1976 
July 14, 1960 
July 14, 1960 
July 14, 1960 
July 14, 1960 
Aug. 30, 1935 
Sep. 3, 1954 
Deep water harbor, adjacent to docks, dredge to 35 
feet below mean lower low water, protected 
by two jetties.' 
Extension of project limits. 
BAR POINT HARBOR, AK 
Construct two breakwaters 963 feet, and 120 feet. 
BETHEL SMALL BOAT HARBOR, AK 
Construct 7,700-foot-long small boat harbor 
and entrance channel by deepening, widening, and 
straightening the upper 6,800 feet of Brown's Slough. 
CORDOVA SMALL BOAT HARBOR, AK 
Construction of 2,000-foot breakwater. 
CRAIG SMALL BOAT HARBOR, AK 
Construction of 2 short rubblemound breakwaters. 
DILLINGHAM HARBOR, AK 
Basin 230,000 square feet in area with depth of 2 feet 
above mean lower low water along Scandinavian 
Creek, with entrance channel 1,100 feet long and 40 
feet wide. 
DRY PASS, AK 
Dredge channel 60 feet wide, 6 feet deep through 5 
shoals. 
Provide additional dredging for channel 70 feet wide 
and 12 feet deep through 7 shoals. 
H. Doc. 34, 85th Cong., 
1st Sess. 2 
P.L. 94-587 
Section 107, P.L. 86-645 
Authorized by Chief 
of Engineers, June 
29, 1978 
Section 107, P.L. 86-645 
Authorized by Chief 
of Engineers, June 29, 
1978 
Section 107. P.L. 86-645 
Authorized by Chief 
of Engineers, April 
23, 1981 
Section 107, P.L. 86-645 
Authorized by Chief 
of Engineers, Feb. 19, 
1980 
H. Doc. 390, 84th Cong., 
2d Sess.2 
H. Doc. 470, 70th Cong., 
2d Sess.2 
H. Doc. 414, 83d Cong., 
2d Sess. 2 
40-10 
2. 
3. 
4. 
5. 
6. 
July 3, 1958 
7.

ALASKA DISTRICT 
TABLE 40-B (Continued) AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
8. 
July 3, 1958 
Aug. 19, 1964 
Oct. 27, 1965 
Aug. 13, 1968 
Mar. 2, 1945 
Oct. 27, 1965 
July 3, 1958 
Aug. 8, 1917 
Aug. 30, 1935 
June 16, 1948 
July 14, 1960 
Aug. 30, 1935 
HOMER HARBOR, AK 
Basin 2.7 acres in area with depth of 12 feet below mean 
lower low water, and rock breakwater 1,260 feet long. 
Relocation and rehabilitation of project destroyed by 
March 27, 1964 earthquake, by construction of basin 
10 acres in area with 12-foot depth over 2.75 acres 
and 15-foot depth over 7.25 acres protected by rock 
breakwaters, 1,018 feet and 238 feet long. 
HOONAH HARBOR, AK 
Entrance channel, a rubblemound breakwater and 
diversion dike and two rubblemound breakwaters 
inclosing a 15.1 acre harbor area. 
KAKE HARBOR, AK 
Basin 7-acre berthing area, 15 feet deep, inclosed by a 
1,580-foot west rock breakwater and a 900-foot south 
rock breakwater. 
METLAKATLA HARBOR, AK 
Dredging small boat basin 2.18 acres in extent to a 
depth of 10 feet below plane of mean lower low; 
water; construction of rubblemound breakwater 900 
feet long. 
Improvement consists of entrance channel and two 
rubblemound breakwaters inclosing a 7.0 acre 
basin. 
NINILCHIK HARBOR, AK 
Basin 320 feet long by 150 feet wide with depth of 2 feet 
above mean lower low water, approach channel 400 
feet long and 50 feet wide with depth of 9 feet above 
mean lower low water, protected by 410-foot jetty. 
NOME HARBOR, AK 
Two jetties, easterly 335 feet and westerly 460 feet long 
revetment, channel and basin 200 feet wide and 250 
feet long. 
Extension of the jetties and enlarging basin to 250 
feet wide and 600 feet long.3 
Sea wall. 
PORT LIONS SMALL BOAT HARBOR, AK 
Construction of a 600-foot breakwater and a 170-foot 
stub breakwater inclosing a 12-acre harbor. 
STIKINE RIVER, AK 
Snagging from mouth to Canadian border. 
H. Doc. 34, 85th Cong., 
1st Sess.2 
P.L. 88-451 
Section 201, P.L 89-298 
H. Doc. 92-900, 92d 
Cong., 2d Sess. 2 
Authorized Oct. 12, 
1972 
S. Doc. 70, 90th Cong., 
2d Sess. 
2 
H. Doc. 138, 76th Cong., 
91st Sess. 
Section 201, .L. 89-298 
S. Doc. 92-64, 92d Cong. 
2d Sess. 2 Authorized 
Oct. 12, 1972 
H. Doc. 34, 85th Cong., 
1st Sess. 2 
H. Doc. 1932, 64th Cong 
2d Sess, 2 
H. Doc. 404, 71st Cong., 
2d Sess., and Rivers 
and Harbors, 
Committee Doc. 38, 
73d Cong., 2d Sess. 2 
Report of Chief of 
Engineers dated 
March 8, 1948. 
Section 107, P.L. 86-645 
Authorized by Chief 
of Engineers, 
April 9, 1979 
H. Doc. 210. 72d Cong., 
1st Sess. 2 
40-11 
9. 
10. 
11. 
12. 
13. 
14. 
15.

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 40-B (Continued) AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
16. CHENA RIVER LAKES, AK 
Aug. 13, 1968 Dam and reservoir on the main Chena River, a dam S. Doc. 89, 90th Cong., 
and detention reservoir on the Little Chena River, and 2d Sess.2 
a levee along the north side of the Tanana River. 
20. ' SNETTISHAM, AK 
Oct. 23, 1962 Multi-purpose dam, with powerhouse and transmission H. Doc. 40, 87th Cong., 
facilities. 1st Sess.2 
'Purchase of dredge and deepwater jetties deauthorized 2Contains latest published map. 
November 6, 1977 under Section 12, Public Law 93-251. 3Extension of jetties classified "inactive". 
TABLE 40-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to Sep. 30, 1983 
Full Report Operation 
See Annual and 
Project Status Report For Construction Maintenance' 
Apoon Mouth of Yukon 
River, AK1 Completed 1920 $ 128,896 $ 2,154 
Cook Inlet Shoals, AK Completed 1977 1,220,000 6,875 
Cordova Harbor, AK Completed 1978 843,534 488,156 
Craig Harbor, AK Completed 1974 377,260 72,500 
Douglas Harbor, AK Completed 1963 282,019 - 
Egegik River, AK Completed 1972 4,441 3,107 
Elfin Cove, AK Completed 1959 154,191 - 
Gastineau Channel, AK Completed 1964 789,461 102,701 
Haines Harbor, AK2 Completed 1977 1,000,0003 - 
Humboldt Harbor, AK Completed 1977 3,679,6834 
Iliuliuk Harbor, AK Completed 1941 66,037 - 
Juneau Harbor, AK Completed 1974 1,381,150 260,991 
Kasilof Harbor, AK2 Completed 1975 109,848 - 
Ketchikan Harbor, AK Completed 1979 1,602,417 307,092 
King Cove Harbor, AK Completed 1974 2,264,948 - 
Kodiak Harbor, AK Completed 1973 1.891,2125 37,946 
Myers Chuck Harbor, AK Inactive 1970 9,700 - 
Naknek River, AK Completed 1961 20,789- 
Neva and Olga Straits, AK Completed 1960 155,009- 
Old Harbor, Kodiak Island, AK 2 Completed 1972 370,415 132,946 
Pelican Harbor, AK Completed 1964 369,683 18,973 
Petersburg Harbor, AK Completed 1972 252,932 26,800 
Port Alexander, AK Completed 1949 17,000- 
Rocky Pass, AK Completed 1960 337,668- 
St. Michael Canel, AK Completed 1916 377,062 1,360 
Seldovia Harbor, AK Completed 1974 1,051,8836 5,518 
Sergius Whitestone, AK Completed 1973 1,798,010 1,934 
Seward Harbor, AK Completed 1973 712,3697 219,789 
Sitka Harbor, AK Completed 1973 1,611,009 15,490 
Skagway Harbor, AK Completed 1972 133,180 32,665 
Valdez Harbor, AK Completed 1968 649,7408 221,498 
Wrangell Harbor, AK Completed 1969 537,020 331,352 
Wrangell Narrows, AK Completed 1979 3,562,343 309,260 
1Abandonment recommended in H. Doc. 467, 69th Cong., 
1st Sess. 
2Authorized by Chief of Engineers (Sec. 107). 
: In addition $925,500 of State funds. 
4In addition $857,000 of State funds. 
5Includes $594,163 for rehabilitation. 
6Includes $400,000 for rehabilitation. 
'Includes $90,026 for rehabilitation and $2,528 Code 710, 
Recreation Facilities at Completed projects. 
8Includes $73,000 for rehabilitation and $2,713 Code 710, 
Recreation Facilities at Completed projects. 
40-12r.

ALASKA DISTRICT 
TABLE 40-E OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
For Last Cost to Sep. 30, 1983 
Full Report Operation 
See Annual and 
Project Status Report For Construction Maintenance 
Fairbanks, Tanana River & 
Chena Slough, AK Completed 1943 557,000 2,657 
Gold Creek, AK Completed 1975 876,006 4,301 
Klutina River, Copper Center, 
AK' Completed 1973 260,681 - 
Lowell Creek, AK Completed 1945 416,3822 30,771 
Salmon River, AK Completed 1963 37,7704 5 - 6 
Skagway River, AK Deferred' 1966 26,385 1,253 
Talkeetna River, AK Completed 1981 516,694 - 
'Authorized by Chief of Engineers (Sec. 205). 6In addition, $138,957 expended for emergency flood 
2In addition, $25,000 expended from contributed funds. activities (1963), and $27,400 expended from contributed 
3In addition, $12,000 expended from contributed funds. funds. 
4In addition, $7,000 expended from contributed funds. 7 Project eligible for deauthorization. 
5Includes $34,197 of PWA funds. 
TABLE 40-G DEAUTHORIZED PROJECTS 
For Last Contri- 
Full Report Date Federal buted 
See Annual Deauth- Funds Funds 
Project Report For orized Expended Expended 
Anchorage Harbor, AK 1967 1977 - - 
(Uncompleted Portion) 
Ketchikan Harbor, AK 1979 1979 - - 
(West Breakwater) 
Port Alexander, AK 1949 1977 - - 
(Inner Harbor) 
Tolovana River, AK 1931 1977 -- - 
(Snagging) 
40-13

Study Identifscation 
Buckland, AK 
Chignik, AK 
Dillingham Small Boat Harbor, AK 
Homer Harbor, AK 
Hydaburg, AK 
Juneau Harbor, AK 
Little Diomede, AK 
Mekoryuk, AK 
Ninilchik Harbor, AK 
Sand Point, AK 
Saxman, AK 
Seward Harbor, AK 
Tatitlek Harbor, AK 
Whittier, AK 
Total 
Fiscal Year Costs 
$ 7,500 
55,246 
48,052 
78,817 
30,000 
41,879 
7,500 
26,257 
55,852 
66,028 
93,963 
119,841 
12,700 
73,843 
$717,478 
40-14 
TABLE 40-H 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
NAVIGATION WORK 
UNDER SPECIAL AUTHORIZATION 
Navigation Activities Pursuant to Section 107, Public Law 86-645 
(Preauthorization)

ALASKA DISTRICT 
TABLE 38-I PROJECT CONDITION SURVEYS 
Name of Project Date Survey Conducted 
Alaska: 
Apoon Mouth of the Yukon 
Craig Harbor 
Douglas Harbor 
Egegik River 
Elfin Cove 
Gastineau Channel 
Haines Harbor 
Hoonah Harbor 
Humboldt Harbor 
Iliuliu Harbor 
Juneau Harbors 
Ketchikan Harbor 
King Cove 
Kodiak Harbor 
Naknek River 
Old Harbor 
Pelican Harbor 
Petersburg Harbor 
Port Alexander 
Rocky Pass in Keku Strait 
St. Michael Canal 
Seldovia Harbor 
Sergius and Whitestone Narrows 
Seward Harbor 
Sitka Harbor 
Skagway Harbor 
Valdez Harbor 
Wrangell Harbor 
Wrangell Narrows 
October 1982 
February 1983 
October 1982 
November 1982 
November 1982 
November 1982 
April 1983 
March 1983 
June 1983 
June 1983 
April 1983 
January 1983 
June 1983 
July 1983 
July 1983 
August 1983 
December 1982 
December 1982 
December 1982 
December 1982 
September 1983 
August 1983 
September 1983 
August 1983 
September 1983 
March 1983 
August 1983 
February 1983 
February 1983 
40-15 

BOARD OF ENGINEERS FOR RIVERS AND HARBORS 
The Board of Engineers for Rivers and Harbors is a 
continuing body created by Section 3 of the 1902 River 
and Harbor Act. The Board is selected by the Chief of 
Engineers and is comprised of seven senior engineer officers. 
The Deputy Chief of Engineers normally serves as 
Chairman. Five members are Division Engineers with 
membership rotated among divisions having civil works 
missions. The seventh member, assigned full time to the 
Board as Resident Member, also directs the staff in carrying 
out the responsibilities of the Board. The Board 
meets quarterly or on call of the Chairman. 
The Board has several statutory duties. It conducts 
independent reviews of Corps survey reports covering 
water resources projects and reports its conclusions and 
recommendations to the Chief of Engineers. The Chief of 
Engineers then forwards the reports with his conclusions 
and recommendations to the Assistant Secretary 
of the Army (Civil Works) for transmission to the Congress. 
The Board also conducts independent reviews of 
special reports ordered by the Congress. It also considers 
and approves general plans for major modification and 
reconstruction of any lock, canal, canalized river or 
other work for the use or benefit of navigation. 
In addition to its statutory duties, the Chief of Engineers 
has assigned further duties to the Board. It reviews 
Corps policies and procedures as directed, additional 
special reports for the Secretary of the Army and the 
Chief of Engineers, reports of other Federal agencies 
pertaining to water resource development as directed, 
and conducts a ten-month program of in-service training 
for approximately fifteen Corps planners annuallygenerally 
at GS 12 and 13 levels-in all aspects of Federal 
water resources development. The training program 
helps meet Corps need for increased numbers of qualified 
people in the planning field. The Board also has 
administrative responsibility for processing proposed 
reports of the Chief of Engineers, along with Final Environmental 
Impact Statements, to states and Federal 
agencies for their 90-day review. 
In addition to other duties, the Resident Member of 
the Board has served as second alternate for the Secretary 
of the Army on the Foreign Trade Zones Board. The 
Secretary of the Army has also appointed the Resident 
Member to serve as his representative on the Committee 
of Alternates of the Foreign Trade Zones Board and 
authorized him to act directly on the Secretary's behalf 
on all nondiscretionary matters involving foreign trade 
zones. This appointment relieves the Assistant Secretary 
of the Army for Civil Works of routine duties in this 
regard; however, discretionary matters concerning the 
Foreign Trade Zones Board remain under previous delegations 
of authority. 
The Resident Member of the Board also serves as exofficio 
secretary of the U. S. Section, Permanent International 
Association of Navigation Congresses (PIANC), 
a quasi-official organization. 
The membership of the Board on September 30, 1983 
was as follows: 
Major General Richard M. Wells, Chairman, Deputy 
Chief of Engineers, Pulaski Building, Washington, 
DC 
Major General William E. Read, Division Engineer, 
U. S. Army Engineer Division, Lower Mississippi 
Valley, Vicksburg, MS 
Brigadier General Richard S. Kemrn, Division Engineer, 
U. S. Army Engineer Division, Ohio River, 
Cincinnati, OH 
Brigadier General Mark J. Sisinyak, Division Engineer, 
U. S. Army Engineer Division, Missouri 
River, Omaha, NE 
Brigadier General James W. van Loben Sels, Division 
Engineer, U. S. Army Engineer Division, 
North Pacific, Portland, OR 
Brigadier General Thomas A. Sands, Division Engineer, 
U. S. Army Engineer Division, North Atlantic, 
New York, NY 
Colonel Frederick W. Mueller, Jr., Resident Member, 
Board of Engineers for Rivers and Harbors, 
Ft. Belvoir, VA 
Official Board Actions. In compliance with resolutions 
of the Congress and instructions from the Chief of 
Engineers, the Board completed 61 official report reviews 
during Fiscal Year 1983. 
The favorable reports category includes favorably recommended 
projects for Federal construction as well as 
projects for solving water resources problems for major 
metropolitan areas, even though they may not include 
recommendations for construction by any agency of the 
Federal Government. The urban studies listed below fall 
into this latter category. 
Reports Recommending Favorably for Federal Construction: 
The Board recommended 32 projects estimated 
to cost a total of $1,491,629,700, of which $1,316,540,200 
is the first cost to the United States, as follows: 
Trinity River Project, Fish and Wildlife Plan, TX 
Scammon Bay, Small Hydropower Project, AK 
Miami River, Fairfield, OH 
Dresden Island Lock and Dam, Illinois Waterway, IL 
Upper Little Arkansas River Watershed, KS 
Brandon Road Lock and Dam, Illinois Waterway, IL 
Hampton Roads and Vicinity, VA 
Bethel Bank Stabilization, AK 
Galveston Bay Area, Texas City Channel, TX 
Grays Harbor, WA 
Arkansas River Hydropower, Locks and Dam Nos. 13 
and 9 and Toad Suck Ferry Lock and Dam, AR 
Dade County, North of Haulover Beach Park, FL 
Alenaio Stream, HI 
St. Paul Island Harbor, AK 
Indiana Shoreline Erosion, IN 
South Quincy Drainage and Levee District, IL 
St. Louis Harbor, MO and IL 
Duluth-Superior Harbor, MN and WI 
Lower Rio Grande Basin, TX 
Wrightsville Beach, NC 
Wynoochee Lake, Wynoochee River, WA 
East, West and Duwamish Waterways, Seattle Harbor, 
WA 
Fort Gibson Lake, Powerhouse Extension, OK 
Monroe County, FL 
Park River at Grafton, NC 
Sims Bayou, TX 
Starved Rock Lock and Dam, IL 
Threemile Creek, Mobile, AL 
Wailua River Hydropower, HI 
41-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1988 
Hilo Harbor, HI 
Lock and Dam 26 (Replacement), IL 
Willoughby Spit and Vicinity, Norfolk, VA 
During this fiscal year, four reports were recalled by 
reporting officers without Board action: Summersville 
Lake Modification Study, Gauley River, West Virginia; 
Rudee Inlet, Virginia; Cape Girardeau.Jackson Metro 
Area, Missouri; and Columbia Rived at the Mouth, 
Oregon and Washington. 
Reports Recommending Unfavorably for Federal Construction: 
During Fiscal Year 1983, the Board concurred 
in unfavorable recommendations of the reporting officers 
for Federal construction on 22 projects: 
Plattin Creek Basin, MO 
Baldwin Hills, CA 
Smith Island, MD and VA 
New Hogan Fishery, CA 
Metropolitan Christina River Basin, DE and PA 
Alameda County Shoreline, CA 
Housatonic River Basin, MA and CT 
Southeastern New Hampshire 
Kern River, CA 
LaMoine River Basin, IL 
Mill Creek at Moab, UT 
Withlacoochee River Region, FL 
Walikill River Basin, NY and NJ 
Adequate Mooring Facilities, Mississippi River, MS 
Iowa-Cedar River Basin, IA 
Mississippi River Headwaters Lakes, MN 
Degognia-Fountain Bluff and Grand Tower Drainage 
and Levee District, IL 
Delaware Estuary Salinity Intrusion Study, DE, NJ 
and PA 
Ballona Creek and Tributaries, CA 
Nemaha and Little Nemaha Rivers and Tributaries, 
NE and KS 
Carolina Beach Inlet, NC 
Crescent City Harbor (Shoaling), CA 
One flood control project in this category-Novato Creek, 
Marin County, California-was recalled by reporting 
officers without Board action. 
General Design Memoranda: The Board reviewed and 
submitted favorable recommendations on 2 general 
design memoranda during the reporting period: Wyoming 
Valley, Pennsylvania and Clarion River Basin, 
Pennsylvania. 
Urban Studies: In response to Congressional resolutions, 
the Board submitted its findings on 5 urban studies: 
Salinas-Monterey Bay Area Urban Study, CA 
Tulsa Urban Study and Fry Creeks, OK 
Lake Erie Wastewater Management Study, OH 
Great River Resource Management Study, GREAT 
III, Saverton, MO to Cairo, IL 
Phoenix Urban Study, AZ 
During Fiscal Year 1983 the Board held four meetings: 
December 14-15, 1983; March 2-3, 1983; June 27-28, 
1983; and September 28-29, 1983. 
Since 1902, the Board has acted on 8,644 survey reports, 
recommending favorably on 3,857 and unfavorably 
on 4,787. 
41-2

MISSISSIPPI RIVER COMMISSION* 
The Mississippi River Commission (MRC) was created 
by an act of Congress on Jun. 28, 1879. The Flood 
Control Act of May 15, 1928, authorized the Flood 
Control, Mississippi River and Tributaries (MR&T) 
Project. The Commission consists of three officers of 
the Corps of Engineers, one from the former Coast and 
Geodetic Survey (presently the National Oceanic and 
Atmospheric Administration), and three civilians, two 
of whom must be civil engineers. All members are 
appointed by the President with the advice and consent 
of the Senate. 
During the fiscal year the Commissioners were: MG 
William E. Read, U.S. Army, President, appointed 
Dec. 1, 1981; Mr. Roy T. Sessums, civil engineer; Mr. 
Sam E. Angel; Mr. R. D. James, civil engineer, 
appointed Dec. 1, 1981; MG Hugh G. Robinson, U.S. 
Army, appointed Dec. 1, 1981; BG Richard S. Kernm, 
U.S. Army, appointed Dec. 1, 1981; and RA Herbert R. 
Lippold, NOAA, appointed March 23,1982; COL Joseph 
Yore, U.S. Army served as Secretary of the Commission. 
The MRC is charged, under direction of the Secretary 
of the Army and supervision of the Chief of Engineers, 
with prosecution of improvements for flood control of 
the Mississippi River and of its tributaries and outlets 
in its alluvial valley, so far as they are affected by 
Mississippi River backwater, between Head of Passes, 
LA (mile 0), and Cape Girardeau, MO (1,006 miles 
AHP-Lower Mississippi mileage terminates at mile 
954 AHP), and with prosecution of improvements in 
the interest of navigation between Cairo, IL (954 miles 
AHP), and Baton Rouge, LA (234 miles AHP); and for 
stabilization of the lower 7 miles of the right bank of 
the Ohio River, to former mouth of Cache River. It also 
is charged with prosecution of certain flood control 
works on the Mississippi River and tributaries, as far 
as they are affected by backwater, between Cape 
Girardeau, MO, and Rock Island, IL (1,437 miles AHP), 
and with prosecution of improvements on designated 
tributaries and outlets below Cape Girardeau for flood 
control, navigation, major drainage, and related water 
uses. Authorized operations of the Commission below 
Cape Girardeau are conducted by District Engineers 
of New Orleans, Vicksburg, and Memphis Districts 
within the areas described below, in accordance with 
approved directives and programs and congressional 
appropriations therefor. 
New Orleans District: Mississippi River project 
levees and river channel stabilization as required from 
Head of Passes, mile 0 to 320 AHP, construction of four 
salinity-control structures for fish and wildlife enhancement 
in lower Mississippi River Delta region; 
Bonnet Carre and Morganza Floodways; maintenance 
and improvements of Mississippi River navigation 
channel from Baton Rouge, LA (mile 234 AHP), to mile 
320; Baton Rouge Harbor (Devils Swamp); navigation 
improvement of Atchafalaya and Old Rivers from 
Mississippi River to Morgan City; control of Old and 
Atchafalaya Rivers; Atchafalaya Basin Floodways; 
flood control and drainage improvements in Bayou 
Cocodrie and tributaries, in Bayou des Glaises, and in 
Upper Pointe Coupee Loop area; flood protection in 
eastern Rapides and south-central Avoyelles Parishes, 
LA; and freshwater distribution from Atchafalaya 
River to Teche-Vermilion Basins. 
Vicksburg District: Mississippi River project levees 
and river channel stabilization as required from upper 
limits of New Orleans District (mile 320 AHP) in 
vicinity of Black Hawk, LA, to Coahoma-Bolivar 
County line, MS (mile 620 AHP) on left bank, and to 
vicinity of mouth of White River, AR (mile 599 AHP), 
on right bank including south bank Arkansas River 
levee to vicinity of Pine Bluff, AR, and north bank 
levee to vicinity of Tucker on left bank of Plum Bayou, 
AR; bank stabilization in lower 36.1 miles of Arkansas 
River; maintenance and improvement of Mississippi 
River navigation channel between miles 320 and 599 
AHP; Vicksburg and Greenville Harbors; specific fish 
and wildlife facilities in Tensas, Yazoo, and Big Sunflower 
Basins; a streambank erosion control project in 
the Yazoo Basin; flood control and drainage improvements 
in Red River backwater area including leveed 
portion east and west of Black River and south of Red 
River; Jonesville, LA, Boeuf and Tensas Rivers and 
Bayou Macon Basins and tributaries, AR and LA, and 
Bayou Lafourche, LA; Yazoo River Basin, MS, including 
backwater area; Big and Little Sunflower 
Rivers, Deer Creek, and Steele Bayou, MS; and Grand 
Prairie Region and Bayou Meto Basin, AR, including 
provision for agricultural water supply. 
Memphis District: Mississippi River project levees 
and river channel stabilization as required, from upper 
limits of Vicksburg District to north bank of Little 
River diversion channel, MO (1,003 miles AHP), a few 
miles below Cape Girardeau, MO, on right bank, and to 
Cache River diversion channel (967 miles AHP) above 
Cairo, IL, on left bank, including levees and revetment 
on right bank of Ohio River, in Mounds-Mound City 
area, IL; except operations above Cairo, IL, do not 
* Authorizing legislation (Tables 42-D and 42-E) is listed at the end of this chapter. All other tables are referenced in text and also appear 
at the end of this chapter. 
42-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
include channel stabilization on the Mississippi River. 
Maintenance and improvement of Mississippi River 
navigation channel between mile 599 and 954 AHP and 
of Memphis Harbor, TN; specific fish and wildlife 
facilities in St. Francis Basin; levees in White River 
backwater area up to vicinity of Augusta, AR, and a 
pumping plant near mouth of White River; levees and 
pumping plants at De Valls Bluff and Des Arc, AR; 
channel improvements in Cache River Basin, AR; 
channel improvements in Big Creek and tributaries, 
AR; improvement works in St. Francis River Basin, 
MO and AR, including backwater area improvements 
in Belle Fountain Ditch and Drainage District No. 17, 
AR; Little River diversion channel, MO, and L'Anguille 
River, AR; Wolf River Basin, TN; Obion and Forked 
Deer River Basins, TN; Reelfoot Lake area, including 
channel improvement for Bayou du Chien and Lake 
No. 9, TN and KY; West Kentucky tributaries, KY; 
Mud Lake pumping station, TN; and pumping plants 
and outlet structures in the Cairo-Mounds-Mounds 
City area, IL. 
Field operations of the Commission restricted to 
levee construction under Sec. 6, 1928 Flood Control Act 
(local interests contributing one-third of costs and 
furnishing rights-of-way) are conducted within the 
following limits by two districts reporting directly to 
the Commission on matters within their jurisdiction- 
St. Louis District: Mississippi River (Sec. 6) levees 
from upper limits of Memphis District to Clemens 
Station, MO (1,254 miles AHP), on right bank, and 
Hamburg Bay, IL (1,215 miles AHP), on left bank, and 
Illinois River from its mouth to mile 120 at Havana, IL. 
Rock Island District: Mississippi River (Sec. 6) levees 
from upper limits of St. Louis District to Rock Island, 
IL (1,437 miles AHP). For work accomplished see 
Table 42-N, page 42-50, Annual Report for 1975. 
MISSISSIPPI RIVER AND 
ALLUVIAL VALLEY BELOW 
CAPE GIRARDEAU, MO. 
Location and description. The Mississippi River 
rises in Lake Itasca, MN, and flows generally southerly 
for 2,340 miles through the central portion of United 
States to empty into the Gulf of Mexico 115 miles below 
New Orleans. It is improved for barge navigation for 
1,832 miles to Minneapolis, MN. The Mississippi River 
and its major tributaries, the Missouri, Ohio, St. 
Francis, White, Arkansas, Yazoo, and Red-Old Rivers, 
drain 1,245,000 square miles in all or part of 31 states 
between the Rocky and Appalachian Mountains and 
part of two Canadian provinces. Below Cape Girardeau, 
MO, 53 miles above Ohio River, river bottomlands 
widen abruptly into an alluvial valley of 35,460 square 
miles which was originally subjected to flood overflow. 
A major part of the alluvial valley has been protected 
from floods by levees which confine floodflows within a 
floodplain having an average width of 5 miles. (See 
map of alluvial valley of Mississippi River, scale 
1:500,000.) Observations made by Mississippi River 
Commission to Sep. 30, 1982, show approximate alltime 
maximum and minimum discharges between 
levees as follows: Cairo to White River, 2,000,000 and 
70,000 cubic feet per second; thence to Red River, 
2,150,000 and 90,000 cubic feet per second; thence to 
the Gulf of Mexico, 1,500,000 and 50,000 cubic feet per 
second in Mississippi River and 660,000 and 11,000 
cubic feet per second in Atchafalaya River. As the 1927 
floodflow was not confined between levees, maximum 
discharges recorded do not include entire flow of the 
1927 flood, maximum of record below White River. 
High water and flood stages usually occur in late 
winter or early spring, but great floods such as that of 
1937 occurred as early as January. Low water stages 
/ generally prevail from August to December. Extreme 
all-time ranges in stages recorded at representative 
gages (rounded to nearest foot) are 60 feet at Cairo, 49 
feet at Memphis, 57 feet at Red River Landing, and 21 
feet at New Orleans (Carrollton). The river is nontidal 
above Red River Landing where tidal amplitude rarely 
exceeds 0.1 foot during extreme low water. 
Previous projects. For details see page 1944, 
Annual Report for 1932. 
Existing project. The Mississippi River and Tributaries 
Project in the alluvial valley between Head of 
Passes, LA, and Cape Girardeau, MO, provides protection 
from floods by means of levees, floodwalls, 
floodways, reservoirs (in Yazoo and St. Francis Basins), 
bank stabilization, and channel improvements in and 
along the river and its tributaries and outlets insofar as 
affected by backwater of Mississippi River, including 
levee work on the main stem between Cape Girardeau 
and Rock Island. When completed, 23,621 square miles 
will be protected from the Mississippi River project 
flood. The project also provides for a 12- by 300-foot 
navigation channel between Baton Rouge, LA, and 
Cairo, IL; for salinity-control structures; and for 
channel realinement and improvement including bank 
stabilization and dikes to reduce flood heights, control 
natural tendency of river to lengthen by meandering, 
and protect levees from being destroyed by caving 
banks. Locations of major main stem Mississippi River 
improvements are shown in Table 42-A and those for 
off-main stem tributaries are shown in Table 42-B. 
Pertinent data on dams and lakes are shown in Table 
42-C. Authorizing and incorporating legislation are 
shown in Tables 42-D and 42-E. Summary of presently 
estimated Federal cost of authorized improvements is 
shown in Table 42-F. Construction of the existing 
project began in 1928 and has continued throughout 
ensuing years. Based on the estimated cost of 
$10,050,642,000 (Cost projected through the construction 
period), and actual expenditures through Sep.30, 
1983, of $3,457,110,595, the entire project is about 74.8 
percent complete. 
Recommended modifications. None. 
Local cooperation. The Flood Control Act of 1928, 
as amended, applies. Such requirements have, in 
general, been complied with by local interests. 
Terminal facilities. See volume 1 of two-volume 
Port Series No. 21, 1979, "Ports on the Gulf Coast of the 
42-2

MISSISSIPPI RIVER COMMISSION 
United States," for Baton Rouge and Lake Charles, LA; 
Port Series No. 20, 1981, for New Orleans, LA; also 
folio of Flood Control and Navigation Maps of Mississippi 
River Cairo, IL, to the Gulf of Mexico (50th 
edition), 1982. 
Project cost. Total allotted for flood control, including 
maintenance charges through Aug. 18, 1941, 
chargeable under authorizations to Sep. 30, 1983, was 
$3,556,357,836. (See Table 42-S.) (See also Tables 42-R, 
42-T, and 42-U for additional financial statements.) 
Operations and results during fiscal year. Commission 
activities: 
The 318th session was held on September 27-October 
1, 1982, on board the U.S. MV Mississippi en route on 
the Mississippi River from Cairo, IL, to Morgan City, 
LA. Bank protection works, levees and channel conditions 
were observed en route, as well as an inspection 
of the Lake Chicot project in Arkansas and an on-site 
inspection of the Teche Vermilion Pumping Plant in 
Louisiana. Approximately, 165 persons attended public 
meetings held at Cairo, IL; Memphis, TN; Vicksburg, 
MS; and Morgan City, LA. About 27 of the representatives 
presented various problems pertaining to flood 
control and navigation. This session adjourned at 
Morgan City, LA, at 11:25 a.m., October 1, 1982. 
The 319th session was held December 16, 1982. The 
Commission met at its headquarters in Vicksburg, MS, 
to consider two project reports Helena, AR, and 
Vicinity Feasibility Report of the Memphis District, 
and the Yazoo Backwater Area Fish and Wildlife 
Mitigation Report of the Vicksburg District. This 
session adjourned at 11:50 a.m., December 16, 1982. 
The 320th session was held April 25, 1983. The 
Commission met at its headquarters in Vicksburg, MS, 
to consider the Memphis District project report: West 
Memphis, Arkansas and Vicinity Feasibility Report 
and Environmental Assessment. This session adjourned 
at 2:20 p.m. on April 25, 1983. 
Records of Proceedings of all sessions of the Mississippi 
River Commission are on file in the office of the 
President. 
Alluvial Valley Mapping 
General. Contoured quadrangles and general maps 
of the alluvial valley are available for departmental use 
and public distribution under prescribed regulations. 
Preparation, revision, and publication of quadrangle 
maps (scale 1:62,500) continued. Road-map-type information 
brochures of principal portions of the overall 
project were published along with pamphlets on the 
subject of flood control and navigation. Maps and 
supplemental data sheets for active works were updated 
and published as required. 
The 1982 (50th) edition of the folio of flood control 
and navigation maps (scale 1:62,500) covering the 
Mississippi River from Cairo, IL, to the Gulf of Mexico 
was revised and printed. 
Approximately 6932 flight-line miles of infra-red 
color; 8961 flight-line miles of black-and-white aerial 
photography (various scales); and about 89.2 hours of 
oblique photography were flown along the Mississippi 
River and tributaries in the New Orleans, Vicksburg, 
and Memphis Districts. 
Work accomplished in the Districts: New Orleans 
Revisions of Donaldsonville, Mount Airy, Chef Menteur, 
and Spanish Fort, LA, 1:62,500-scale quadrangles are 
in progress. 
Memphis District-Series conversion of U. S. Geological 
Survey 1:24,000-scale to 1:62,500-scale quadrangles 
of Hayti, MO-AR; Malden, MO, and Pascola, 
MO, are complete and Edmondson, AR, Horseshoe 
Lake, AR, Weiner, AR, and Tilton, AR, are in progress. 
Revision of Rolls, Paducah, Poplar Bluff, Dyersburg, 
Memphis, and Blytheville, scale 1:25,000 are 
complete and have been printed. 
Vicksburg District-Series conversion of U.S. Geological 
Survey 1:24,000-scale quadrangles with addition 
of flood damage features of Raymond, Terry, Seven 
Pines, Lexington, Greenwood, Hernando, Mileston, 
and Senatobia, Mississippi are in progress. 
Floods 
Streamflow observations during the fiscal year 
follow: 
Memphis District-Mississippi River crest stage of 
54.2 feet at Cairo gage on May 8-9, 1983, and maximum 
discharge of 1,486,000 cubic feet per second, occurred 
on May 9, 1983, at Hickman, KY and crest stage of 
39.2 feet at Memphis on May 15, 1983, with maximum 
discharge of 1,645,000 cubic feet per second on May 15, 
1983. 
Vicksburg District-Flooding was rampant throughout 
the Vicksburg District during FY 83. No river 
basin was spared as new maximum at record stages 
were set at 17 locations throughout the district during 
FY 83. Peak stages and discharges on the Mississippi 
River Vicksburg District's reach were as follows: 
Arkansas City-43.6 feet on May 25-26, 1983, and 
maximum discharge of 1,738,000 cubic feet per second; 
Vicksburg-49.3 feet on May 27-29, 1983, maximum 
discharge of 1,787,000 cubic feet per second; and 
Natchez 55.7 feet on May 29-31, 1983, and maximum 
discharge of 1,804,000 cubic feet per second. The 1983 
Mississippi River flood ranked number 5 in magnitude 
from 1927 to date. Also it was of long duration with the 
Vicksburg Stage remaining above its bankful stage of 
43.0 feet from April 28 to June 16, 1983. 
New Orleans District-On the Mississippi River, the 
Red River Landing gage recorded a maximum stage of 
60.48 feet NGVD on May 31, 1983, and the New 
Orleans gage recorded a maximum stage of 17.42 feet 
NGVD on May 22, 1983. On the Atchafalaya River, the 
Simmesport gage recorded a maximum stage of 43.57 
feet NGVD on May 31, 1983 
42-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Studies and Investivations 
General investigations. Surveys and reports, authorized 
by laws and by Senate and House Public Works 
Committee resolutions, were made as required. Collection 
and study of basic data continued. Actions taken 
on various requests for modifications of the existing 
project, Mississippi River and Tributaries, authorized 
by the Flood Control Act of May 15, 1928, as amended 
(see Table 42-D), follow: 
St. Johns Bayou and New Madrid Floodway, MO, 
Phase I GDM - The MRC Report dated January 29, 
1982 contained recommendations for a total of 143.7 
miles of channel improvements and construction of a 
1,000-cfs and a 1,500-cfs pumping station. Environmental 
features included purchase of 2,500 acres in 
mitigation lands, development of a greentree reservoir, 
and construction of a fish pool weir. The total estimated 
cost of this recommended improvement is $106,100,000 
(Oct 83). 
Nonconnah Creek, TN and MS, Phase I GDM- The 
MRC Report dated January 28, 1982 contained recommendations 
for 18.2 miles of channel improvement on 
Nonconnah Creek and recreation features consisting of 
picnic tables, sanitation facilities, hike/bike trails, and 
a nature area. The total estimated cost of this recommended 
improvement is $25,300,000 (Oct 83). 
Horn Lake Creek and Tributaries, including Cow 
Pen Creek, TN and MS, Phase I GDM - The MRC 
Report dated January 28, 1982 recommended 10.67 
miles of various channel improvements in the area of 
Horn Lake & Cow Pen Creeks, and 4.57 miles of 
hike/bike trails. The total estimated cost of this improvement 
is $3,240,000 (Oct 83). 
Louisiana State Penitentiary Levee, Mississippi River 
- The Assistant Secretary of the Army (Civil Works) 
report dated August 3, 1983, found that Federal financial 
participation in reconstruction of a state levee 
protecting a state prison is not an appropriate Federal 
responsibility. However, the Corps may provide technical 
assistance to the state, if requested. 
Atchafalaya Basin Floodway System, LA, Interim 
Feasibility Report/Phase I GDM/FEIS which recommended 
a comprehensive flood control plan with provisions 
for management and preservation of the environmental 
resources of the Atchafalaya Basin was 
submitted to President, MRC, in January 1982. The 
MRC acted on the report in April 1982 and submitted 
recommendations to the Chief of Engineers in June 
1982. After completion of required state, agency, and 
public reviews of the report and final EIS, the Chief, 
by letter report to President, MRC, on February 28, 
1983, approved for implementation all features of the 
report falling Within his discretionary authority, primarily 
the flood cOntrol features, except for the Avoca 
Island levee extension. By separate letter of the same 
date, the Chief recommended to the Assistant Secretary 
of the Army for .Civil Works the submission of the 
remaining features of the plan for Congressional 
authorizationpP arily the new features for real estate 
acquisition, enitronmental protection, and recreation 
development. The total estimated cost of plan features 
approved by the Chief of Engineers is $816,980,000 
(October 1982) and the total estimated cost of those 
features under review by the ASA is $250,240,000 
(October 1982). Additional survey studies and advanced 
studies of the Terrebonne marshes will be completed in 
FY 87 culminating in the management measures for 
the Atchafalaya Delta and flooding solutions in areas 
outside the floodway, to the east and west, including 
solutions to the backwater flooding influence of the 
Lower Atchafalaya River to the east of the Avoca 
Island levee. 
Engineering studies. A research program was 
continued for development of materials and more 
effective and economical design of regulation features 
for placing and stabilizing the Mississippi River in a 
suitable alinement. 
Potamology investigations of river behavior continue 
to be made. Investigations into the major cause-andeffect 
relationships attributable to major changes in 
stage-discharge relationships on the Mississippi River 
as a result of both natural and man-made modifications 
are continuing. 
Mississippi River and Tributaries-Levees 
Operations and results during fiscal year. This 
feature consists of construction of new, and enlargement 
of existing, levees to approved grade and section; 
construction and restoration of levee berms; and construction, 
repair, and maintenance of roads on levees. 
Work accomplished is summarized in Table 42-N and 
further broken down as follows: 
New Orleans District-Enlarged 14.7 miles of levees 
in the Main Stem System. 
Vicksburg District-Constructed 1.3 miles of berms, 
and enlarged 4.5 miles of levees, in the Main Stem 
System. See Table 42-L. 
Memphis District-No construction this fiscal year. 
See Table 42-M. 
Condition as of Sep. 30. (See Tables 42-K, 42-L, 
42- M, and 42-N.) There are 1,608.3 miles of levees 
authorized for the Mississippi River below Cape Girardeau, 
of which 1,601.5 are in place with 1,159.4 built to 
approved grade and section. The Main Stem Levee 
System consists of 2,202.1 miles, of which 2,195.3 are in 
place with 1,551.5 miles completed to approved grade 
and section. Included in this system are additional 
levees and structures along the south bank of Arkansas 
River (85.4 miles); along the south bank of Red River 
(59.2 miles, with 59.2 completed); and 449.2 miles in 
the Atchafalaya RiverBasin, with 449.2 in place with 
257.5 completed to grade and section (see Table 42-N). 
Of the authorized 707.0 miles of berms, 480.3 are 
complete. Graveled or hard-surfaced roads have been 
constructed on 1,789.0 miles of these levees. 
There are an additional 1,604.2 miles of authorized 
levees off the main stem, of which 1,109.2 are in place 
with 812.6 to approved grade and section. Berms have 
been completed on 9.8 miles and 805.7 miles of graveled 
42-4

MISSISSIPPI RIVER COMMISSION 
or hard-surfaced roads have been constructed on the 
levees. 
For last summary of levee work accomplished under 
Sec. 6, 1928 Flood Control Act, see Table 42-N, pages 
42-50, Annual Report for 1975. 
Mississippi River and Tributaries- 
Channel Improvements 
Operations and results during fiscal year. Dredging: 
Mississippi River Main Stem-(See Table 42-G). 
Work included dredging 31,018,400 cubic yards for 
maintenance of channel and harbor improvements. 
Minimum channel depth of 9 feet was maintained. 
Dredging was done with the following plant: New 
Orleans District, channel maintenance dredging was 
performed by the dredges Jadwin and Lenel Bean. 
Vicksburg District, one Government-owned dustpan 
dredge, one leased dustpan dredge and two leased 
cutterhead dredges. The Vicksburg District channel 
maintenance dredging was performed by the dredges 
Burgess and Lenel Bean. The harbors were maintained 
with two leased contract cutterhead dredges Butcher 
and Lewis James. Memphis District, one Governmentowned 
dustpan dredge, one leased cutterhead dredge, 
and one contract dustpan dredge. 
Sole source negotiations with Bean Dredging Corporation 
began in April 1983 for lease of the contractor's 
dustpan dredge Lenel Bean. The contract was awarded 
in July 1983. 
In addition to the contract dustpan, channel maintenance 
dredging was performed by the dredge 
Burgess. Seven district harbors including McKellar 
Lake Harbor were maintained with the leased contract 
cutterhead dredge Natchez. 
Bank revetment and dikes: (See Table 42-H, 42-I, 
and 42-J.) Construction of 12.24 miles of new bank 
revetment and 106,016 squares of concrete mattress, 
for maintenance, along the Mississippi River was completed 
by Government plant and hired labor. Also, 6.86 
miles of new dikes were constructed and 23,795 squares 
were placed for maintenance. 
In addition, work on tributaries consisted of placement 
of 0 miles of new dikes and 0 squares for 
maintenance. 
Other work performed in the interest of navigation, 
supplementing maintenance dredging on Mississippi 
River between Cairo, IL, and Baton Rouge, LA, included 
removal of snags, wrecks, and obstructions; 
issuance of bulletins by the Vicksburg District providing 
information on available high-water velocities 
at selected locations; maintaining bulletin boards 
showing daily gage readings at regular MRC gages; 
and contract pilot service furnishing navigation interests 
with latest information and advice on channel 
conditions and obtaining their views as to needs of 
navigation interests. Cost of this work is given in Table 
42-R. 
Condition as of Sep. 30. In carrying out authorized 
channel improvement program between Baton Rouge 
and Cairo, 16 cutoffs were developed between 1933 and 
1942. These, combined with chute channel development 
and alinement improvements, decreased channel length 
between these cities by about 170 miles. However, 
current velocities increased the attack on the banks 
and the river began to regain its length. As a result, the 
net shortening between 1933 and 1962 was 114 miles of 
the theoretical 170-mile cutoff. 
There are now in place 814.62 miles of operative 
bank revetment and 196.14 miles of dikes on the lower 
Mississippi River. This amount of channel stabilization 
should prevent the river from regaining much more of 
its length due to meandering. A navigation channel 
9-by 300-feet is being accomplished by revetment and 
dikes and maintained by dredging as required during 
the low-water season. Due to growing effectiveness of 
channel improvement program, average maintenance 
dredging requirements are steadily being reduced, 
and an increase in navigable depth is being obtained. 
Approximately 99.8 miles of foreshore protection have 
been constructed along the lower Mississippi River. 
There are 62.74 miles of revetment and 5.20 miles of 
dikes on tributary channels as listed in Tables 42-H, 
42-I, and 42-J.
New Orleans District 
ATCHAFALAYA BASIN, LA 
Operations and results during fiscal year. New 
work by hired labor: Real estate activities and planning 
for construction were continued. 
New work by contract: Construction of floodside and 
landside berms and levee enlargement continued intermittently 
on the east and west protection levees, 
although there was considerable delay during the year 
due to exceptionally high water flooding the borrow 
pits. An additional 11.2 miles of levee enlargement and 
floodside and landside berms are under construction on 
the west protection levee involving placement of 
275,124 cubic yards during this period and 12.7 miles 
of levee enlargement and floodside and landside berms 
on the east protection levee with placement of 660,190 
cubic yards. A contract for Pointe Coupee pumping 
station, Upper Pointe Coupee Loop area, initiated Mar. 
23, 1981, was completed Jul. 29, 1983. Contract for the 
new Tiger Island floodwall, initiated Jan. 18, 1982, is 
93 percent complete. Contract for the new Morgan City 
floodwall, south of Brashear Avenue, was awarded 
Feb. 24, 1983, initiated May 3, 1983, and is 10 percent 
complete. Contract for the new Morgan City floodwall, 
north of Brashear Avenue, was awarded Sep. 8, 1983. 
A contract for the Berwick floodwall was awarded 
May 2, 1983, initiated Jun. 16, 1983, and is 11 percent 
complete. 
Maintenance by hired labor: Operation and maintenance 
of Bayou Boeuf, Berwick, and Bayou Sorrell 
Locks, Morganza Control Structure, and numerous 
drainage structures as required, condition and operation 
studies, and water control management. 
42-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Maintenance by contract: Contract for resurfacing 
and expanding roadways and parking areas at Bayou 
Boeuf Lock, initiated Sep. 22, 1982, was completed Oct. 
29, 1982. Contract for Avoca Island levee emergency 
erosion repair was awarded May 12, 1983, initiated 
May 17, and completed May 23, 1983. A contract for 
construction of new dolphins, Bayou Boeuf Lock, was 
awarded Jul. 7, 1983, initiated Jul. 15, 1983, and is 48 
percent complete. 
Maintenance dredging was performed, resulting in 
the removal of 1,121,000 cubic yards by one leased 
cutterhead dredge from Berwick Bay harbor between 
Jul. 25 and Sep. 15, 1983. 
Condition as of Sep. 30. Construction was initiated 
Aug. 7, 1929, with commencement of the west protection 
levee from Bordelonville to Hamburg, LA. The 
project is 67 percent complete, based on the current 
estimated Federal cost of $1,555,000,000 and non- 
Federal cost of $11,000,000. Of the 449.2 miles of levees 
and floodwalls authorized for the Atchafalaya system, 
257.5 miles are built to grade. See Table 42-K for status 
of levees. 
Major items remaining to be completed include 
completion of levees to grade and section, channel 
improvement by dredging to reduce flow line, and 
bank stabilization. The channel has been enlarged to 
60,000 square feet from mile 54.5 to 96.2, and 40,000 
square feet from mile 96.2 to 112.3. Enlargement to 
100,000 square feet from mile 54.5 to 112.3 remains to 
be done. Drainage improvements in Upper Pointe 
Coupee Loop area have not been initiated. Approximately 
36.7 miles of bank stabilization have been 
placed as shown in Table 42-H. 
BATON ROUGE HARBOR 
(DEVILS SWAMP), LA 
Operations and results during fiscal year. Maintenance 
by contract: Dredging for the removal of shoal 
from the entrance channel was performed, resulting in 
the removal of 132,670 cubic yards between Aug. 23 
and Aug. 29, 1983. 
Condition as of Sep. 30. Construction of the first 2.5 
miles of the proposed 5.0 miles of channel was initiated 
in January 1958 and completed in July 1959, with 
7,458,086 cubic yards excavated. 
The project is 16 percent complete, based on the 
current estimated Federal cost of $699,200 and cash 
contributions of $650,000. Completion of the remaining 
2.5 miles is dependent on economic justification by 
developments on the initial channel. 
BAYOU COCODRIE AND TRIBUTARIES, LA 
Operations and results during fiscal year. Maintenance 
by hired labor consisted of water control 
management. 
Condition as of Sep. 30. Construction was initiated 
in June 1946 and is 57 percent complete, based on the 
current estimated Federal cost of $25,000,000 and 
non-Federal cost of $316,000. See page 2031, Annual 
Report for 1961, for description of completed work. 
Work required to complete the project consists of 
enlargement of 13.5 miles of upper Bayou Boeuf, 
channel improvement of 25.3 miles of Bayou Cocodrie, 
enlargement of Bayou Courtableau from Washington, 
LA, to the west protection levee, and additional 
culverts through the west protection levee at 100 
percent Federal cost in lieu of the previously authorized 
diversion channel from Washington to the Bayou 
Courtableau drainage structure. 
BONNET CARRE SPILLWAY, LA 
Operations and results during fiscal year. Maintenance 
by hired labor: Condition and operation 
studies, water control management, and ordinary 
maintenance of the control structure and spillway 
continued. 
Condition as of Sep. 30. Construction of the spillway 
was initiated in Fiscal Year 1929. The control structure 
was completed in 1931, levees were completed in 1932, 
and utility crossings were completed in 1936. The cost 
of the completed work is $14,212,200. 
It was necessary to operate the structure to reduce 
flood stages in 1937, 1945, 1950, 1973, 1975, 1979, and 
1983. 
OLD RIVER, LA 
Operations and results during fiscal year. New 
work by hired labor consisted of engineering studies. 
New work by contract: Old River Control Auxiliary 
Structure, Phase I construction, initiated Jul. 9, 1981, 
was completed Oct. 16, 1982. Contract for Phase II construction 
initiated Nov. 6, 1982, and is 22 percent 
complete. Contract for radar and TV surveillance 
system at the control structure, initiated Apr. 21, 1981, 
was completed Dec. 15, 1982. 
Maintenance by hired labor consisted of operation 
and maintenance of the lock and control structures as 
required, condition and operation studies, water control 
management, maintenance of cleared areas, levee 
shaping, operation of a picket boat at the inflow 
channel to the low-sill control structure during high 
river stages, and engineering studies. 
Maintenance by contract: During the period Sep. 15 
to Oct. 7, 1983, 272,603 cubic yards of shoal were 
dredged from the lock forebay. Contract for the overbank 
outlet riprap repairs was awarded Sep. 22, 1983. 
Condition as of Sep. 30. Construction began September 
1955 and is 77 percent complete based on the 
current estimated Federal cost of $315,000,000. Principal 
items completed are as follows: Low-sill structure, 
June 1959; overbank structure, October 1959; levees 
and levee enlargements, October 1963; inflow and 
outflow channels, February 1961; navigation lock 
completed December 1962 and opened to navigation 
42-6

MISSISSIPPI RIVER COMMISSION 
March 1963, at which time Old River was closed to 
navigation with a rock and earthfill dam; highway 
approaches and bridge over the lock completed March 
1965. Approximately 4.7 miles of bank protection have 
been constructed at the inflow and outflow channels. 
(See Table 42-H for details of bank protection.) 
Principal items remaining to complete the project 
consist of constructing additional bank protection 
works, providing additional scour protection in the 
inflow and outflow channels, and completion of the 
Auxiliary Structure. 
TECHE VERMILION BASINS, LA 
(WATER SUPPLY) 
Operations and results during fiscal year. New 
work by hired labor consisted of engineering studies. 
New work by contract: A contract for construction of 
a pumping station, initiated May 27, 1980, was 
completed Dec. 7, 1982. A contract for the Bayou 
Courtableau borrow pit control structure, initiated 
Aug. 18, 1928, was completed Apr. 26, 1983. 
Condition as of Sep. 30. The project is 99 percent 
complete based on the current estimated Federal cost 
of $34,857,000 and non-Federal cost of $848,000. 
Construction was authorized by the Flood Control Act 
of May 15, 1928, as modified by the Flood Control Act 
of 1966 (Public Law 89-789 approved Nov. 7, 1966) of 
the following: a low leveed excavated channel on the 
west bank of the Atchafalaya River north of Krotz 
Springs; an inverted siphon under Darbonne Bay; a 
grated control structure in the WABPL; a gated 
culvert in the berm between Bayou Courtableau and 
the WABPL borrow pit to the south; a slotted weir in 
Bayou Fusilier near Arnaudville; and a navigable 
sector control structure in the Loreauville Canal. 
Improvements are to provide additional surface water 
in Bayou Teche, Vermilion River, and the WABPL 
borrow pit to satisfy the present and future needs for 
municipal, industrial, and irrigation water supply and 
to prevent pollution of these streams. 
Vicksburg District 
TENSAS BASIN, ARK AND LA 
Operations and results during fiscal year. 
(a) Boeuf and Tensas Rivers, and Bayou Macon, 
AR and LA. Planning and design were continued on 
project features. Contracts for the pumps and motors, 
Phase I recreational facilities, Connerly Bayou Dam, 
and Ditch Bayou Dam, slurry trench, and storage 
building are complete on the Lake Chicot Pumping 
Plant Project. The contract for the Lake Chicot Pumping 
Plant is underway. 
Work was completed on relocation of the Illinois 
Central Gulf Railroad bridge located in Reach 3, Big 
and Colewa Creeks. 
(b) Red River backwater area. Planning and 
design continued on project features. The channel 
improvement contract for Wild Cow Bayou and additional 
channel work contract for the Tensas-Cocodrie 
Pumping Plant has been completed. The gravity 
structure contract is complete, and the pumping plant 
contract was initiated in FY 83. Design and rightof-
way acquisition are continuing for the remainder of 
the Tensas-Cocodrie levee enlargement. An 8a Contract 
has been negotiated for constructing the Six Mile 
Bayou project. The contract awarded September 23, 
1983, for $968,875, is for 1.5 miles connecting channel 
and a drainage structure (2-60" pipes). A contract for 
Sicily Island item la was awarded June 9, 1983, at a 
contract price of $1,258,804 and funded with Jobs Bills 
appropriations. Item la includes 1.0 mile levee and a 
water control structure (2-60" pipes). The plans and 
specifications for item lB are complete and preparation 
of the Haha Bayou Pumping Plant design in documents 
has been initiated. Work on the Below Red River Phase 
II GDM is underway. 
Condition as of Sep. 30. 
(a) Boeuf and Tensas Rivers, and Bayou Macon, 
AR and LA. Channel improvement has been accomplished 
on 744.6 miles of project streams, providing 
major drainage outlets for the tributary areas. Additional 
57.2 miles of channel previously enlarged has 
been further enlarged and 61.6 miles of the Tensas 
River have been cleared and snagged. A Reevaluation 
report for the Tensas River Project, above mile 61.6, 
and the Mill Bayou-Bayou Vidal project has been 
completed and is awaiting approval. 
(b) Red River backwater area. Levees in Tensas- 
Cocodrie area are complete except for levee raising 
necessary to conform to the Refined 1973 MR&T 
Project Flood Flowline on the Mississippi River of 
which 17.8 miles have been completed. The work 
comprised 93.1 miles of new levee, excluding 2.1 miles 
of high ground where no levees are required, and 86.9 
miles of gravel road on levees. Construction of 68.6 
miles of levee, Larto Lake to Jonesville levee system, 
has been completed. A levee grade reevaluation study 
is underway for all levee systems in the Red River 
Backwater area. Pending the outcome of this study, 
enlargement of the Tensas-Cocodrie levee system has 
been suspended. 
LOWER ARKANSAS BASIN, AR 
Condition as of Sep. 30. Arkansas River levees. A 
total of 56.2 miles of the 61.5 miles of north bank levees 
and all of the 85.4 miles of south bank levees have been 
completed to approved grade and section. These levees 
above mile 36.1 are protected by bank-protection 
works constructed as a feature of project for Arkansas 
River and tributaries, AR and OK. For present status 
of this work, see report of Little Rock District. Below 
mile 36.1, needed bank protection is constructed with 
project maintenance funds. 
42-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
YAZOO BASIN, MS 
Operations and results during fiscal year. 
(a) Yazoo City and Belzoni protection works. 
Hired labor forces continued operation and maintenance 
of levees, drainage facilities, and pumping plant. 
(b) Greenwood protection works. Hired labor 
forces continued operation and maintenance of pumping 
plant, levees, and drainage facilities. A review of 
the protection provided to Greenwood and vicinity was 
submitted in Supplement C to Greenwood Protection 
Work (GDM #1) and approved subject to comments in 
March 1983. Detailed studies are underway for various 
proposals recommended in the Sup. C report. Four 
bank stabilization projects are in various stages of 
planning and construction. These projects, Sites 1, 2, 3 
and Claiborne Ave. are planned under the "not less 
than $250,000" authority in the Appropriations bill. 
The Site 1 contract was awarded July 20, 1982, and 
completed November 10, 1982, at a contract price of 
$388,085. Site 2 contract was awarded September 12, 
1983, with a contract price of $582,850, and utilizing 
Jobs Bill appropriations. Planning is continuing on 
Claiborne Ave. and Site 3. 
(c) Main stem. Planning is under way to provide 
drainage structure and levee closure at Bee Lake. 
Construction is complete on the Wasp Lake drainage 
structure and levee closure. 
Channel maintenance. Random clearing and snagunflower 
River. A Phase II GDM for additional work 
in the Steele Bayou Basin was approved Dec. 20, 1978. 
Construction on a 11.4 mile item of channel improvement 
began in April 1982. 
(d) Big Sunflower River, etc. A contract was 
awarded on Item 55A, Steele Bayou Channel Improvement, 
Mile 51.6 to 63.0, on 15 March 1982, and is 
scheduled for completion in FY 84. Plans and specifications 
are being prepared for the next item which is 
scheduled for award in October 85. 
(e) Tributaries. Construction: (1) Levees. Construction 
of a dike north of Big Sand Creek. The work is 
associated with plans to upgrade a portion of south Big 
Sand Creek levee. Plans and specifications are complete 
for this item of work, and also for levee work associated 
with the last item of work on Ascalmore-Tippo Project. 
Plans and specifications are being prepared for the 
completion of Panola-Quitman Levee Item C(R). 
(2) Channels. Removal of a portion of the plug on 
Alligator-Catfish Bayou channel at the site of bridge 
relocations was accomplished. The Alligator-Catfish 
channel enlargement project is now complete except 
for removal of the remaining portion of the plug. 
Controls in Alligator-Catfish channel may be necessary 
prior to removal of the plug. A study is underway to 
evaluate these needs. Plans and specifications are 
complete on remaining channel work on the Ascalmore-
Tippo Project. 
(3) Bank Stabilization. Construction contract of 
Tillatoba Creek Phase I was awarded in July 1983. 
Plans and specifications are being prepared for Phase 
II Tillatoba Creek. 
The planning of the Pelucia Creek Levee Project, 
printed as Supplement B to the Greenwood Protection 
Works (GDM #1), is complete and plans and specifications 
are being prepared for Item 1 contruction. 
Maintenance of channels of Yalobusha, Little Tallahatchie, 
and Yocona Rivers; Cassidy, David, Burrell, 
and Bobo Bayous; and Ascalmore Creek, by random 
clearing and snagging and herbicide willow control, 
continued. 
(f) Enid Lake. (See Table 42-C.) Construction of 
public use facilities is substantially complete. Maintenance 
of these facilities continued. The dam and 
appurtenant structures were maintained and operated. 
Rehabilitation of boat channels and snagging and 
clearing of tributary streams in the lake area continued. 
Maximum pool elevation in the lake was 270.34 feet 
above NGVD on May 23, 1983, when storage in the 
flood control pool was 727,600 acre-feet. Peak 24 hr. 
inflow was 47,350 cubic feet per second on December 
26, 1982. On Sep. 30, 1983, pool elevation was 253.85 
feet above NGVD and storage in the flood control pool 
was 336,700 acre-feet. 
(g) Grenada Lake. (See Table 42-C.) Construction 
and maintenance of public use facilities continued. The 
dam and appurtenant structures were operated and 
maintained. Maintenance snagging and clearing of 
tributary streams in the lake area continued. Maximum 
pool elevation in the lake was 236.30 feet above NGVD 
on May 22, 1983, when storage in the flood control pool 
was 1,710,700 acre-feet. Peak 24 hour inflow was 
137,100 cubic feet per second on Dec. 26, 1982. On Sep. 
30, 1983, the pool elevation was 214.10 feet above 
NGVD and storage in the flood control pool was 
517,700 acre-feet. 
Construction of a levee to provide protection to the 
community of Coffeeville from high Grenada Lake 
stages was begun in FY 82. In addition to the levee, 
other features of Coffeeville project include: three 
drainage structures through the levee; portable pumps; 
area rehabilitation; and raising of a town street. Construction 
of the levee and two of the drainage structures 
was completed in FY 82. The remaining feature of the 
Coffeeville project will be completed in early FY 84. 
(h) Sardis Lake. (See Table 42-C.) Construction and 
maintenance of public use facilities continued. The 
dam and appurtenant structures were maintained and 
operated. Clearing of tributary streams in the lake 
area continued. Maximum pool elevation in the lake 
was 283.89 feet above NGVD on May 24, 1983, when 
storage in the flood control pool was 1,718,000 acre-feet. 
Peak 24 hour inflow was 72,100 cubic feet per second 
on Dec. 26, 1982. On Sep. 30, 1983, the pool elevation 
was 260.06 feet above NGVD and storage in the flood 
control pool was 614,500 acre-feet. An 8-mile reach of 
the Little Tallahatchie River from Sardis Dam to 
Highway 51 was clogged with sediment restricting 
releases from the lake. This reach has been dredged to 
restore the design capacity of the river. Six disposal 
42-8

MISSISSIPPI RIVER COMMISSION 
sites were selected, located in upland hill areas to 
reduce the adverse impact on prime agricultural lands 
along the river and still be in compliance with environmental 
laws and regulations. Dredging was completed 
in August 1982. 
(i) Arkabutla Lake. (See Table 42-C.) Construction 
of public use facilities is substantially complete. Maintenance 
of these facilities continued. The dam and 
appurtenant structures were maintained and operated. 
Clearing of tributary streams in the lake area was 
continued. Maximum pool elevation in the lake was 
238.06 feet above NGVD on Jan. 2, 1983, and storage in 
flood control pool was 517,900 arce-feet. Peak 24 hour 
inflow was 42,300 cubic feet per second on Dec. 26, 
1982. On Sep. 30, 1983, the pool elevation was 218.82 
feet above NGVD, and storage in the flood control pool 
was 108,100 acre-feet. 
(j) Yazoo Basin backwater. The Yazoo Area backwater 
levees are complete, including the backwater 
levee from the Mississippi River levee to the west levee 
of the lower Auxiliary Channel, the Little Sunflower 
River drainage structure, and the connecting channel 
from the Steele Bayou drainage structure to the Big 
Sunflower River. A Phase I GDM was completed in FY 
82 which addresses rural flooding from ponded runoff 
inside the backwater levee. 
The Satartia area backwater levee is complete. Plans 
and specifications are being prepared for the drainage 
structure and Item 1 of the Rocky Bayou Levee System. 
Completed backwater levees will require raising to 
provide the degree of protection intended based on the 
project design flow line developed for the Mississippi 
River following the 1973 flood. 
Four Greentree Reservoirs are now complete. Two of 
the three remaining reservoirs will be constructed 
when funds are appropriated. One reservoir has been 
indefinitely delayed because of right-of-way problems. 
Project funds will not be available until FY 85. The 
supply contract for the pumps and motors for the four 
completed reservoirs is scheduled for award in FY 86. 
The project is 42 percent complete. 
(k) Upper Yazoo projects. The first five items of 
work, approximately 40 miles of channel improvement, 
beginning at Yazoo City, MS, and extending upstream 
to just south of Belzoni, MS, have been completed. 
The next item of work, Item 2-C, consisting of 
approximately 7.7 miles of channel improvement is 
under construction. Planning is continuing on the 
remainder of Items 2 and 3. 
(1) Streambank erosion control. Construction of 
the following projects has been completed: Tillatoba 
and Hunter Creeks, Items 1 and 2; Hunter Creek 1A; 
South Fork Tillatoba Creek, Items 5A and 5B; North 
Fork Tillatoba Creek, Items A and 3A; Batupam 
Boque, Items 4A, 4A-1, and 4A-2; Perry Creek, Items 
6A and 6B; Johnson Creek, Items 9A, 9B, and 
vegetative treatment, Item 12; Goodwin Creek, Items 
8A, 8B, and 8C; and Hotopha Creek, Item 7. 
All construction under this feature is complete, and a 
final report was submitted to the Secretary of the 
Army Jan. 5, 1982. All work constructed has been 
turned over to the local sponsors for operation and 
maintenance except for the instrumented system on 
Goodwin Creek where the structures were retained for 
possible future studies. 
Condition as of Sep. 30. The first feature of Yazoo 
Basin project was started in 1936, and the total project 
is about 35 percent complete. A total of 47.9 miles of 
backwater levee has been completed to the interim 
grade. The ongoing Yazoo Basin Comprehensive Study 
will address other water resources problems and needs 
in the area to include urban and rural flood damage 
prevention, hydropower, and water supply. 
LOWER RED RIVER-SOUTH BANK 
RED RIVER LEVEES, LA 
Operations and results during fiscal year. New 
work by hired labor consisted of engineering studies. 
Maintenance by hired labor consisted of water 
control management, and economic studies. 
Condition as of Sep. 30. Construction was initiated 
in Fiscal Year 1929 and is 50 percent complete, based 
on the current estimated cost of $37,100,000. Of the 
59.2 miles of levees authorized, 59.2 miles are complete. 
(See Table 42-L for status of levees and Table 42-I for 
status of revetments. 
Memphis District 
ST. FRANCIS BASIN, AR AND MO 
Operations and results during fiscal year. 
(a) Little River Drainage. Channel improvement 
on Castor River, Item 1-Parcel 2 completed Jul. 15, 
1983. Channel improvement on Ditch 19, Item 2-Parcel 
2 completed Apr. 20, 1983. County bridge, Ditch 24, 
Mile 5.4 completed Jul. 1, 1983. County bridge, Castor 
River, Item 1, Mile 7.85 completed Oct. 25, 1982. P&S 
alterations railroads facilities, Castor River, Item 1 
awarded Jul. 26, 1982-98 percent complete. Railroad 
bridge, Ditch 19, Item 2 awarded Jan. 17, 1983, 2 
percent complete. Channel enlargement, Ditch 24, 
awarded Jun. 17, 1983, 2 percent complete. County 
bridge, Mile 27.75 Ditch 19, Item 2 awarded Jun. 17, 
1983. Levee work, Item R-48.5, AC Nash, 77 percent 
complete. Levee work, Item R-24.5 A.C. 50 percent 
complete. Scour repair at Bridge Mile 1.65 Dudley 
Ditch-Lick Creek completed May 10, 1983. Gravel 
below Kennett-Senath awarded Jul. 20, 1983. Nash 
Relief Well Ditches awarded Jul. 29, 1983. Caruthersville 
Berm Item R-846 awarded Sep. 23, 1983, 2 
percent complete. Levee protection, Allenville, MO 
awarded Aug. 30, 1983. Levee roadway resurfacing 
Commerce, MO-Scott, awarded Sep. 20, 1983. 
(b) Upper St. Francis River. Channel enlargement, 
Ditch 27-Item 2 awarded Apr. 18, 1983-52 percent 
42-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
complete. Alteration of 6-inch gas line, Ditch 27 
awarded Feb. 9, 1983-85 percent complete. Channel 
enlargement, Ditch No. 71, 21A and 25 awarded Jul. 
30, 1982-completed Jul. 30, 1983. Channel excavation, 
Buffalo Creek-Item 2 completed Dec. 10, 1982. Alteration 
of three sewer lines, Ditch 27 awarded Mar. 16, 
1982-74 percent complete. Alteration of US Hwy 63 
and placement of riprap protection awarded Sep. 1, 
1982-15 percent complete. Alteration of State Hwy 77 
and 119, Upper Buffalo Creek was awarded Aug. 29, 
1983. Channel Cleanout Ditch 9-Lake City awarded 
Jul. 13, 1983-98 percent complete. Gravel contract at 
Rivervale to Mark Tree awarded Jul. 15, 1983- 
completed Sep. 22, 1983. Levee roadway resurfacing at 
Princedale in Cross County-completed Sep. 30, 1982. 
Alteration contract for gas lines crossing Ditch 27 at 
Miles 12.90, 13.34 and 14.41 awarded Feb. 9, 1983. 
Alteration of 2-inch gas line, Ditch 25 completed Sep. 
20, 1983. Alteration contract of waterline, Ditch 
25-completed Sep. 20, 1983. Big Slough Ditch, Cleanout, 
Item 1 awarded Sep. 26, 1983. 
(c) Lower St. Francis River. Alteration of four 
county bridges, Big Creek, Item 2-Phase II, awarded 
Feb. 26, 1979-34 percent complete. Relocation of 
county road and abandonment of one county road, 
Blackfish Bayou awarded FY 78. Levee work Item 
R-703, Porter Lake awarded May 20, 1983-52 percent 
complete. Outlet channel clean-out-shoal removal at 
Huxtable Pumping Plant awarded Aug. 16, 1983. 
Levee roadway resurfacing, Frenchman Bayou- 
Whitewall awarded Sep. 13, 1983. Levee roadway 
resurfacing, Whitewall-St. Francis awarded Sep. 15, 
1983. Levee roadway resurfacing, Williamson Light- 
Point Pleasant awarded Sep. 16, 1983. Levee roadway 
resurfacing, Helena-Williamson Light awarded Sep. 
16, 1983. Slide repairs at Poker Point-West Memphis 
awarded Sep. 29, 1983. Stateline Outlet, Arkansas 
Game and Fish Commission, Bridge Mile 4.98 awarded 
Jun. 23, 1983. Engine replacement at Huxtable Pumping 
Plant awarded Aug. 5, 1983. 
Condition as of Sep. 30. 
(a) Little River Drainage. Project was initiated 
during 1938 and is 72 percent complete. 
(b) Upper and Lower St. Francis River and 
Tributaries. Project was initiated during 1937 and is 
77 percent complete. 
(c) Wappapello Lake, MO. Generator replacement 
complete. 
WHITE RIVER BACKWATER LEVEES 
Operations and results during fiscal year. 
(a) Metallizing three pump impellers and three 
exhaust and intake systems. 
(b) Landside Berm Repairs, Item R-641. 
(c) Levee work, slide repairs. 
Condition as of Sep. 30. 
(a) Graham Burke Pumping Plant, awarded Sep. 17, 
1982, and is 77 percent complete. 
(b) Oldtown awarded Mar. 28, 1983, and completed 
Jul. 14, 1983. 
(c) Phillips and Desha Counties awarded Jun. 10, 
1983,79 percent complete. 
LOWER WHITE RIVER 
Operations and results during fiscal year. 
(a) Augusta to Clarendon Levee. There were no 
contracts awarded or completed during the fiscal year. 
(b) Clarendon Levee. There were no contracts 
awarded or completed. 
Condition as of Sep. 30. 
(a) Augusta to Clarendon Levee. Project was 
initiated during 1946 and is 39 percent complete. 
(b) Clarendon Levee. Project was initiated during 
1972 and is 36 percent complete. 
CACHE BASIN, AR 
Operations and results during fiscal year. No 
contracts awarded or completed during the fiscal year. 
Condition as of Sep. 30. Project was initiated 
during 1971 and is 4 percent complete. 
REELFOOT LAKE-LAKE NO.9, TN AND KY 
Operations and results during fiscal year. No 
contracts awarded or completed during the fiscal year. 
Condition as of Sep. 30. Project was initiated 
during 1974 and is 89 percent complete. 
WEST TENNESSEE TRIBUTARIES, TN 
Operations and results during fiscal year. 
(a) Obion River, TN. Obion River alteration Illinois 
Central Railroad bridge across South and Middle 
Forks. Obion River, Alteration of Hwy 22 Bridge and 
channel was completed Sep. 13, 1983. Obion River, 
Channel Improvement- 33 percent complete. 
(b) Forked Deer River, TN. Forked Deer River, 
Alteration of Illinois Central Gulf Railroad bridges 
across North and South Forks. 
(c) Bradford Creek Improvement started. 
Condition as of Sep. 30. 
(a) Project is 94 percent complete. 
(b) Project is 33 percent complete. 
(c) Contract awarded Sep. 21, 1983. 
WEST KENTUCKY TRIBUTARIES, KY 
Operations and results during fiscal year. Reimbursable 
contract for alterations of Illinois Central 
Gulf Railroad bridge across Obion Creek, Item No. 3, is 
under way. Phase I planning is complete, but con- 
42-10

MISSISSIPPI RIVER COMMISSION 
struction has not started. However, the Interstate UPPER YAZOO LEVEE, MS 
Commerce Commission has authorized the abandonment 
of this bridge. Operations and results during fiscal year. A 
men ofthssbrdge.contract for Slide Repairs-Walls, MS was awarded 
Condition as of Sep. 30. Project was initiated Sep. 26, 1983. 
during 1978 and is 4 percent complete. 
42-11

TABLE 42-A 
Mileage 
Above Head 
of Passes 
0-957' 
10-81 
11-25 
38 
45 
59 
75 
44-91 
81-96 
91-104 
96-279 
101-234 
127-129 
235 
279-287 
287-303 
303-314 
306-572 
437 
437-721 
490 
537 
646 
605-666 
672-993 
722-725 
721-734 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
MISSISSIPPI RIVER IMPROVEMENTS 
Locality 
Head of Passes, LA-Cairo, IL 
The Jump-New Orleans, LA 
Baptiste Collette-Bayou Ostrica, 
LA 
Homeplace, LA 
Bohemia, LA 
Myrtle Grove, LA 
Scarsdale, LA 
Bohemia, LA-New Orleans, LA 
New Orleans, LA 
New Orleans, LA 
New Orleans-Morganza, LA 
New Orleans-Baton Rouge, LA 
Bonnet Carrd Floodway, LA 
Baton Rouge Harbor 
Morganza Floodway, LA 
Morganza-Old River, LA 
Old River, LA control 
Old River-Cypress Creek, AR 
Vicksburg Harbor, MS 
Vicksburg-Lake View, MS 
Wilson Point, LA 
Greenville Harbor, MS 
Long Lake, Helena, AR 
Henrico-Helena, AR 
St. Francis River-Commerce, 
MO3 
Industrial levee (Ensley Bottoms) 
Memphis Harbor, TN 
Improvement 
Dredging, revetment, and 
contraction work 
Main line levee, right bank 
Main line setback, left bank 
Salinity control structure, right 
bank 
Salinity control structure, left bank 
Salinity control structure, right 
bank 
Salinity control structure, left bank 
Main line levee and floodwall, left 
bank 
Main line levee, right bank 
Main line levee and floodwall, left 
bank 
Main line levee, right bank 
Main line levee and floodwall, left 
bank 
Regulating spillway, left bank 
Devils Swamp barge channel 
Regulating spillway, right bank 
Main line levee, right bank 
Levee closure and enlargement, 
low and high water spillway 
structures, navigation lock, and 
approach channels, right bank 
Main line levee, right bank 
Harbor extension and industrial 
fill 
Main line levee, left bank 
Pumping Plant and drainage 
structure, right bank 
Harbor improvements and port 
area 
Culvert and floodgate, right bank 
Main line levee and floodwall, right 
bank 
Main line levee, right bank 
Levee and pumping station 
Closure of Tennessee Chute, 
industrial fill, levee, harbor 
channels, etc. 
42-12 
Authorized by Public Law 
89-298 (HD 308/74/1). 
Included in MS Delta 
Region, LA feature. 
Authorized by Public Law 
89-298 (HD 308/74/1). 
Included in MS Delta 
Region, LA feature. 
Authorized by Public Law 
89-298 (HD 308/74/1). 
Included in MS Delta 
Region, LA feature. 
Authorized by Public Law 
89-298 (HD 308/74/1). 
Included in MS Delta 
Region, LA feature. 
Authorized by Public Law 
81-516. 
Authorized by Public Law 
81-516. 
Modified by Public Law 
87-874. 
Extends up south bank of 
Old River to Barbre 
Landing. 
Authorized by Public Law 
83-780. 
Joins Arkansas River, south 
bank levee. 
Authorized by Public Law 
70-391. Modified by Public 
Laws 79-526 and 83-780. 
Unpublished Vicksburg 
District's MRC report 
approved Apr. 14, 1966.2 
Authorized by Public Law 
85-500. 
Authorized by Public Law 
79-526.2 
Authorized by Public Law 
79-526. 
Remarks

MISSISSIPPI RIVER COMMISSION 
TABLE 42-A MISSISSIPPI RIVER IMPROVEMENTS 
(Continued) 
Mileage 
Above Head 
of Passes 
803-873 T 
857 N 
Main 
exte 
Riv 
Pum 
chat 
890 St. Johns Bayou, MO Drai 
clos 
890 New Madrid Floodway, MO Drai 
clos 
890-954 New Madrid-Birds Point, MO Floo 
902-922 Slough Bend, Hickman, KY Main 
922 Hickman, KY Floo 
946 Peafield, MO Drai 
9571 Cairo, Cairo drainage district Floo 
9571 Cairo, Cairo drainage district, Floo 
Mounds, Mound City, and plar 
vicinity 
Thebes-Rock Island, IL Leve 
Cape Girardeau, MO to Rock Leve 
Island, IL 
1. Cairo, IL, is on Ohio River about 3 miles above its 
mouth (Mississippi River mile 954 AHP). 
2. Also see Table 42-D, "Authorizing Legislation." 
Locality 
Ciptonville-Obion River 
rear Mud Lake, TN 
Improvement 
line levee, left bank, levee 
nsion, and diversion Obion 
er 
ping station and adjacent 
nnel improvements 
nage floodgate and levee 
ure 
nage floodgate and levee 
ure 
dway, right bank 
line levee, left bank 
dwall, left bank 
nage floodgate 
dwalls and levees 
dwalls, levees, and pumping 
nt 
es, both banks 
es 
3. Commerce, MO, is on Upper Mississippi River, 39 
miles above mouth of Ohio River. 
42-13 
Remarks 
Modified by Acts of Jul. 24, 
1946 and Dec. 23, 1971. 
Authorized Dec. 15 and 17, 
1970 under Sec. 201 of Oct. 
27, 1965 FC Act. 
Modified by Jul. 24, 1946 
Act. 
Modified by Sep. 3, 1954 
Act. 
Authorized by Sep. 3, 1954 
Act. 
Intermittent (Sec. 6). 
Intermittent (Sec. 6).

TABLE 42-B 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
MISSISSIPPI RIVER TRIBUTARY AND 
OUTLET IMPROVEMENTS 
Mileage 
Below Head 
of Atchafalaya 
River Locality Improvement Remarks 
0-54 
27-54 
54-117 
20-27 
25-117 
27 
0-27 
31-57 
80 
53-117 
117 
117-129 
117-129 
105 
105-120 
115 
116 
5 
5-105 
29 
29 
40 
40 
40 
Floodway 
Floodway 
Floodway 
ATCHAFALAYA BASIN, LA' 
Atchafalaya Basin. Morganza 
and West Atchafalaya 
Floodways 
West Atchafalaya Floodway 
between Red River and 
Alabama Bayou 
Morganza Floodway between 
Mississippi River and Alabama 
Bayou 
Atchafalaya Basin Floodway 
between Alabama Bayou and 
Morgan City 
East protection levee (Morganza 
and Atchafalaya Flood ways) 
Lacour-Red Cross 
Morganza-Morgan City 
Bayou Latenache 
Upper Pointe Coupee Loop area 
Bayou Fordoche-Ramah 
Bayou Sorrell 
Bayou Sorrel Lock-Morgan City 
Morgan City 
Below Morgan City 
Below Morgan City 
Atchafalaya Basin Floodway 
lower protection levee 
Calumet 
Below Morgan City 
Berwick' 
Patterson 
West protection levee (Atchafalaya 
Basin and West Atchafalaya 
Floodways) 
Simmesport-Hamburg 
Mansura to Wax Lake Outlet 
Coulee des Grues 
West Atchafalaya Floodway 
Morganza Floodway 
Bayou Darbonne 
West Atchafalaya Floodway 
Morganza Floodway 
Including lower Morganza 
Floodway guide levee. 
Through upper Morganza 
guide levee and enlargement 
of outlet channel. 
Enlargement of Bayou 
Latenache. Approved Jun. 
4, 1970. See Table 42-D. 
Levee landside borrow pit. 
Alternate route Gulf 
Intracoastal Waterway 
Port Allen to Morgan City. 
Gulf Intracoastal Waterway 
utilizes levee west side 
borrow pit channel. 
Gulf Intracoastal 
Waterway. 
Bypass route for Gulf 
Intracoastal Waterway. 
East of lower river. 
Bayou Teche-Wax Lake 
Outlet. 
Inclosed area between Wax 
Lake Outlet and Berwick. 
Lower Atchafalaya River. 
Adjustment to provide fresh 
water. 
West Atchafalaya 
Floodway. 
Through West Atchafalaya 
protection levee. 
42-14 
Levee, upper Morganza guide 
Levee and Morgan City floodwall 
Drainage structure, Pointe Coupee, 
and channel enlargement 
Additional drainage facilities 
Drainage channel 
Lock 
Alternate navigation channel, Gulf 
Intracoastal Waterway 
Lock in Bayou Boeuf' 
Channel relocation 
Levee, floodwall 
Floodgate, east 
Levees, floodwall, drainage 
structures, and pumping plants 
Lock 
Water system 
Levee fuse plug 
Protection levee 
Levee enlargement and floodgate 
extension 
Railway 
Railway 
Gated drainage structures 
Highway 
Highway

MISSISSIPPI RIVER COMMISSION 
TABLE 42-B 
(Continued) 
MISSISSIPPI RIVER TRIBUTARY AND 
OUTLET IMPROVEMENTS 
Mileage 
Below Head 
of Atchafalaya 
River Locality Improvement Remarks 
41 Bayou Courtableau 
41 
41 
94 
94 
105 
105 
0-54 
5-6 
5-66 
28-30 
40-41 
54-117 
94-106 
Mileage 
Above 
Mouth 
0-8 
50-133 
96 
133 
0-17 
17-40 
40-51 
51-60 
17-42 
87-107 
40 
60 
West Atchafalaya Floodway 
Morganza Floodway 
Charenton 
Jaws-Lake Fausse Pointe 
Calumet 
Wax Lake Outlet 
Atchafalaya River 
Barbre Landing-Alabama Bayou 
Simmesport 
Simmesport-Bayou Garofier 
Melville 
Krotz Springs 
Below Alabama Bayou 
Mississippi River-Morgan City 
TECHE-VERMILION BASINS, 
LA 
Atchafalaya River to Teche- 
Vermilion Basins 
Courtableau Basin, LA, and 
outlets 
Charenton Canal 
West Atchafalaya protection levee 
borrow pit channel 
Bayou Courtableau spillway 
Bayou des Glaises 
BAYOU COCODRIE AND 
TRIBUTARIES 
Bayou Courtableau 
Bayou Cocodrie 
Bayous Cocodrie-Bouef diversion 
Bayou Boeuf 
Bayous Boeuf-Rapides diversion 
Upper Cocodrie 
Bayou Boeuf 
Bayou Lamourie to Kincaid 
Structures 
Lecompte Control Structure 
Bayou Rapides Control Structure 
Gated drainage control structures 
and channels 
Railway 
Railway 
Floodgate and approach channels 
Outlet, Charenton drainage canal 
and protection levee. 
Floodgate, west 
Drainage canal-railway and 
highway bridges 
East bank, levee 
Levee, ring, and drainage structure 
West bank, levee 
Levee, ring 
Levee, ring 
Channel enlargement 
12- by 125-foot navigation channel 
Pumping station above Krotz 
Springs, conveyance channels, 
and appurtenant works 
Drainage channel 
Drainage channel 
Drainage control structure 
Diversion channel 
Enlargement and additional 
culverts 
Enlargement and realinement 
New channel 
New channel 
New channel 
Enlargement, clearing, and 
snagging 
Enlargement, realinement, 
clearing and snagging 
Fixed elevation weir 
Gated drainage structure 
42-15 
Borrow pit channel to 
Grand Lake through West 
Atchafalaya protection 
levee. 
Restoration of drainage 
west of West Atchafalaya 
Basin protection levee. 
Bayou Teche and Wax Lake 
Outlet. 
To lower flood heights. 
Increase channel capacities 
to decrease flood heights. 
Through Grand and Six 
Mile Lakes. 
Freshwater distribution 
from Atchafalaya River to 
Teche-Vermilion Basins. 
Outlet to gulf. 
Intercepting drainage 
channel. 
Washington to west 
protection levee.

TABLE 42-B 
(Continued) 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
MISSISSIPPI RIVER TRIBUTARY AND 
OUTLET IMPROVEMENTS 
Mileage 
Below Head 
of Atchafalaya 
River Locality Improvement Remarks 
Bayou Lamourie Control 
Structure 
Various 
LAKE PONTCHARTRAIN, LA 
Lake Pontchartrain, Jefferson 
Parish, LA 
AMITE RIVER, LA 
Amite River, LA 
LOWER RED RIVER, SOUTH 
BANK, RED RIVER LEVEES, 
LA 
Moncla-Hotwells 
Red River-Moncla to Lake Long 
EASTERN RAPIDES AND 
SOUTH-CENTRAL 
AVOYELLES PARISHES, LA 
Eastern Rapides and southcentral 
Avoyelles Parishes, LA 
TENSAS BASIN, AR AND LA 
Red River backwater area 
Tensas-Cocodrie area 
Larto Lake-Jonesville 
Sicily Island area 
Below Red River area 
Black River, LA 
Six Mile Bayou area 
Jonesville, LA 
Ouachita River 
Boeuf and Tensas Rivers and 
Bayou Macon, AR, and LA 
Boeuf River, AR, and LA 
Below Bayou La Fourche 
Bayou LaFourche 
Boeuf River, AR, and LA above 
Bayou LaFourche 
Canal 19 
Canal 19 extension 
Big and Colewa Creeks 
Gated drainage structure 
Railway, highway, and local road 
bridges, and pipeline crossing 
Flood protection (2, 3) 
Bank protection 
Levee, south bank 
Levees 
Flood protection and drainage 
improvement 
Levees, drainage channels, 
structures, and pumping plant 
Levees, drainage channels, and 
structures 
Levees, drainage channels, and 
structures 
Levees, drainage channels, and 
structures 
Drainage structure and 
appurtenant channel works 
Levees, floodwall, pumping plant, 
and interior drainage 
Levees, drainage channels, and 
structures 
Clearing 
Channel improvement and 
realinement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvements 
Authorized by Public Law 
81-516. Eliminated by 
Public Law 89-298. 
Intermittent (Sec. 6). 
Authorized by Public Law 
91-611. 
(4) 
(4) 
(4) 
(4) 
Unpublished VXD-MRC 
Letter Report dated May 
31, 1977. MR&T 
authority.2 
Portion of levee built under 
Sec. 6. Incorporated in 
MR&T by Public Law 
81-516.2 
Monroe to Sandy Bayou and 
Bawcomville (Sec. 6). 
(5) 
(5) 
Authorized by Public Laws 
78-534 and 79-526.2 3 
(5) 
(6) 
Authorized by Public Law 
78-534. 3 
42-16 
87 
82-145 
3-56 
3-56 
5 
56 
0-32 
0-56 
151-235 
210-286 
286-296 
0-75

MISSISSIPPI RIVER COMMISSION 
TABLE 42-B 
(Continued) 
MISSISSIPPI RIVER TRIBUTARY AND 
OUTLET IMPROVEMENTS 
Mileage 
Below Head 
of Atchafalaya 
River Locality Improvement Remarks 
0-8 
0-7 
0-33 
0-10 
0-9 
0-14 
0-170 
0-34 
0-35 
Lake Chicot 
0-6 
0-160 
0-16 
0-0.2 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
To divert flows from Lake Chicot 
(6) 
(6) 
(5) 
(6) 
(6) 
(6) 
See Table 42-E
(5) 
(5) 
Authorized by Public Law 
90-483. 
Tributaries of Boeuf River- 
Canal 19 
Fleschmans Bayou 
Caney Bayou 
Big Bayou 
Canal 18 
Kirsch Lake Canal 
Black Pond Slough 
Bayou Macon, AR, and LA 
Bayou Macon 
Canal 43 
Canal 81 
Pumping plant and drainage 
structure 
Tributary of Bayou Macon 
Rush Bayou 
Tensas River, AR and LA 
Tensas River 
Tributary of Tensas River 
Mill and Vidal Bayous 
Grant's Canal, LA 
Grant's Canal at Lake Providence 
LOWER ARKANSAS RIVER, 
AR 
Yancopin-Pine Bluff 
Fletcher Bend, AR to Pine Bluff 
North Little Rock to Gillett (below 
Plum Bayou) 
GRAND PRAIRIE-BAYOU 
METO, AR 
Grand Prairie Region and Bayou 
Meto Basin, AR 
YAZOO BASIN, MS 
Yazoo Backwater area 
Yazoo River System below 
Arkabutla Lake 
Yazoo River between Yazoo City 
and Prichard 
Yazoo River between Yazoo City 
and Askew 
Will M. Whittington Auxiliary 
Channel 
Yazoo City protection 
Rocky Bayou area 
Belzoni protection 
Greenwood protection 
Arkabutla Lake 
Channel improvement 
Channel improvement 
Filling canal 
Levee, south bank 
Revetment 
Levee, north bank 
Water supply and drainage 
improvements 
Levees and pumping plants 
Channel improvement 
Levees, right bank 
Levees, left bank 
(6) 
Authorized by Public Law 
78-534.3 
Authorized by Public Law 
89-298. 
Authorized by Public Law 
81-516. 
(5) 
Authorized by Public Law 
81-516. 
Including Tallahatchie and 
Coldwater Rivers. 
Intermittent. 
Intermittent. 
Floodway channel 
Levee, drainage structure, and 
pumping plant 
Channel clearing and enlargement 
Levee and floodwall 
Levees, channel improvement, 
drainage structures, and pumping 
plants 
Flood detention and conservation 
Improvement of 7.8 miles 
was approved Apr. 29, 
1970. 
See Table 42-C. 
42-17 
Clearing 
23-98 
35-98 
48-102 
0-75 
0-381 
75-366 
75-345 
45-109 
75 
127 
185 
381

TABLE 42-B 
(Continued) 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
MISSISSIPPI RIVER TRIBUTARY AND 
OUTLET IMPROVEMENTS 
Mileage 
Below Head 
of Atchafalaya 
River 
0-64 
64 
0-24 
0-26 
26 
0-13 
13 
0-88 
137-260 
75-381 
0-8.3 
0-23 
0-42 
275-290 
0-204 
0-8 
0-28 
0-81 
0-43 
0-4 
0-27 
153-160 
0-68 
13-55 
0-68 
99 
Locality 
Yalobusha River below Grenada 
Lake 
Grenada Lake 
Tallahatchie River-Little 
Tallahatchie River 
Little Tallahatchie River below 
Sardis Lake 
Sardis Lake 
Yocona River below Enid Lake 
Enid Lake 
Cassidy Bayou below Old 
Coldwater River 
Upper Yazoo Projects 
Area between main stem and hills 
including Bobo Bayou 
McKinney Bayou 
Alligator-Catfish Bayous 
Bear Creek 
Whiteoak Bayou 
Tallahatchie River, MS 
Big Sunflower River, etc. 
Big Sunflower River 
Hull Brake-Mill Creek Canal 
Hushpuckena River 
Quiver River 
Gin and Muddy Bayous, MS 
Bogue Phalia 
Ditchlow Bayou 
Little Sunflower River 
Deer Creek 
Steele Bayou 
Muddy Bayou 
LOWER WHITE RIVER AND 
BASIN, AR 
Laconia Circle-Old Town Lake 
Big Creek and tributaries 
Clarendon levee 
Improvement 
Channel improvement 
Flood detention and conservation 
Levees, Panola-Quitman Floodway 
Channel improvement 
Flood detention and conservation 
Channel improvement 
Flood detention and conservation 
Channel improvement 
Floodway channel 
Levees and channel improvement 
Channel improvement and 
enlargement of pumping plant 
Channel improvement 
Channel improvement 
Channel improvement 
Two road crossings of Panola- 
Quitman Floodway, MS and for 
protection of Sheley Bridge 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Water-control structure 
42-18 
Remarks 
See Table 42-C. 
See Table 42-C. 
See Table 42-C. 
Including Moores Bayou, 
Cutoff Bayou, Whiting 
Lake and outlet. 
Authorized by Public Law 
79-526. 
Authorized by Public Law 
79-526. 
Authorized by Public Law 
89-298. As modified in 
GDM in 1967. 
Authorized by Public Law 
89-298. 
Authorized by Public Law 
89-298. 
Authorized by Public Law 
90-147. 
Authorized by Public Law 
78-534. 3 
Authorized by Public Law 
87-874. 
Authorized by Public Law 
78-534. 3 
Authorized by Public Law 
78-534. 3 
Authorized by Public Law 
78-534. 3 
Authorized by Public Law 
78-534.3 
Authorized by Public Law 
78-534.3 Modified in 
December 1970. See Table 
42-D. 
Approved Mar. 3, 1970. See 
Table 42-D. 
Mile 605-645 Mississippi 
River. 
(6) 
Authorized by Public Law 
89-298. 
Authorized by Public Law 
89-298. 
Levee, backwater including outlet 
Pumping plant 
Channel improvement and 
structures 
Levee and outlet structures

MISSISSIPPI RIVER COMMISSION 
TABLE 42-B 
(Continued) 
MISSISSIPPI RIVER TRIBUTARY AND 
OUTLET IMPROVEMENTS 
Mileage 
Below Head 
of Atchafalaya 
River Locality Improvement Remarks 
Augusta to Clarendon 
De Valls Bluff 
143 
0-196 
0-90 
260 
0-225 
225 
0-105 
86 
0-36 
0-29 
0-17 
0-12 
0-108 
0-25 
0-20 
0-15 
108-192 
122 
(6) 
(5) 
Des Arc, AR 
CACHE BASIN, AR 
Cache River, AR 
Bayou DeView, AR 
ST. FRANCIS RIVER AND 
BASIN, AR, AND MO 
Inter-River Drainage District in 
Missouri 
Mouth of St. Francis River- 
Wappapello Dam 
Wappapello Lake 
Little River Basin 
Marked Tree, AR 
Tyronza River 
Big Slough Ditch 
Mayo Ditch 
Cross County Ditch 
Belle Fountain Ditch 
Drainage District No. 17 
L'ANGUILLE RIVER, AR 
L'Anguille River and tributaries, 
Brushy and First Creeks 
WEST TENNESSEE 
TRIBUTARIES 
Wolf River and tributaries, TN 
Obion River and tributaries, 
North, South, Middle, and 
Rutherford Forks 
Forked Deer River and 
tributaries, North, Middle, and 
South Forks 
Mud Lake Pumping Station, TN 
Harris Fork Creek, TN and KY 
Porter Gap, TN 
REELFOOT LAKE-LAKE NO. 
9, TN AND KY 
Running Reelfoot Bayou, TN 
Bayou du Chien and Lake No. 9, 
KY and TN 
42-19 
Levees, outlet structures 
Levee, outlet structure, and 
pumping station 
Levee, outlet structure, and 
pumping station 
Channel improvement and 
structures 
Channel improvement and 
structures 
Channel improvement and two 
outlet structures 
Floodway, levees, drainage 
channels, and structures 
Flood detention and conservation 
Floodway, levees, drainage 
channels,'and structures 
Marked Tree Siphon 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement and 
pumping station 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Pumping plant 
Flood control improvements 
Construction to main-stem 
standards, levee and appurtanent 
structures for flood control 
Channel improvement 
Channel improvements and 
pumping station 
Authorized by Public Law 
81-516. 
Authorized by Public Law 
81-516. 
Authorized by Public Law 
81-516. 
Authorized Dec. 16, 1975. 
See Table 42-D. 
See Table 42-C. 
Authorized by Public Law 
90-483. 
Authorized by Public Law 
90-483. 
Authorized by Public Law 
80-858. 
(6) 
Authorized by 1948 Flood 
Control Act. 
Authorized by 1948 Flood 
Control Act. 
Authorized by Resolutions 
Dec. 15 and 17, 1970.2 
Authorized by Water 
Resources Act of Oct. 22, 
1976.2 Section 102, 1976.2 
Section 183, 1976.2 
Authorized by Public Law 
83-780. 
Authorized in December 
1970, See Table 42-D.

TABLE 42-B 
(Continued) 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
MISSISSIPPI RIVER TRIBUTARY AND 
OUTLET IMPROVEMENTS 
Mileage 
Below Head 
of Atchafalaya 
River Locality Improvement Remarks 
WEST KENTUCKY 
TRIBUTARIES, KY 
0-47 Obion Creek, KY Channel improvement Authorized by Public Law 
89-298. 
LITTLE RIVER DIVERSION 
CHANNEL, MO 
Delta to Ancell, MO Levees Mile 49 above Cairo. 
MISSOURI RIVER, MO 
0-28 Mouth to St. Charles, MO Levees Intermittent (Sec. 6). 
ILLINOIS RIVER, IL 
0-120 Mouth to Havana, IL Levees Intermittent (Sec. 6). 
OHIO RIVER, IL AND KY 
Cairo to Mound City and Mounds, Floodwall, levee, revetment, and 
IL pumping plant 
1. General data concerning Bayou Boeuf, Bayou Sorrel, 
and Berwick locks where Atchafalaya Basin protection levees 
cross Gulf Intracoastal Waterway, alternate route to Plaquemine, 
LA and lower Atchafalaya River (extension of Bayou 
Teche Waterway), respectively, are in report of New Orleans 
district. 
2. Also see Table 42-D, "Authorizing Legislation." 
3. Public Law 81-516 modified requirements of local 
cooperation. 
4. Authorized by Public Law 77-228. Modified by Public 
Law 89-298. 
5. Authorized or incorporated in MR&T by Public Law 
79-526.$ See Table 42-D. 
6. Authorized by Public Law 85-500. 
42-20

MISSISSIPPI RIVER COMMISSION 
TABLE 42-C MISSISSIPPI RIVER TRIBUTARY 
DAMS AND LAKES 
Grenada Enid Sardis Arkabutla Wappapello 
Name1 Lake Lake Lake Lake Lake 
River Yalobusha Yocona Little Tallahatchie Coldwater St. Francis 
Nearest town to damsite Grenada Enid Sardis Arkabutla Wappapello 
Drainage area, square miles 1,320 560 1,545 1,000 1,310 
Conservation pool: 
Area, thousand acres 10 6 11 5 4 
Volume, thousand acre-feet 86 58 108 31 31 
Elevation, feet, NGVD 193 230 236.0 209.3 354.7 
Flood control pool: 
Area, thousand acres 65 28 58.5 33 23 
Volume, thousand acre-feet 1,252 602 1,462 494 582 
Runoff, inches 17.8 20.2 17.7 9.3 8.4 
Outlet gates: 
Number 3 2 4 3 3 
Size, feet 7.5 by 14 8 by 16f 6 by 12 8.5 by 19 10 by 20 
Capacity, thousand cubic 
feet per second 10.7 9.4 10.0 10.0 18.0 
Spillway: 
Type, uncontrolled Chute Chute Chute Chute Gravity 
Length, feet 200 200 400 300 740 
Elevation, crest, feet, NGVD 231 268 281.4 238.3 394.7 
Discharge capacity, thousand 
cubic feet per second 52 50 132 89 229 
Surcharge pool: 
Area, thousand acres 106 41 90 63 32 
Volume, thousand acre-feet 1,385 554 1,447 858 521 
Runoff, inches 19.7 18.5 17.6 16.1 7.5 
Elevation, feet, NGVD 247.5 284.0 301.0 256.3 413.7 
Dam: 
Type, earthfill Rolled Rolled Hydraulic Rolled Rolled 
Length, thousand feet 13.9 8.4 15.3 11.5 2.7 
Elevation, crest, feet, NGVD 256.0 293.0 311.4 264.3 419.7 
1. Grenada, Enid, Sardis and Arkabutla Lakes are in 
Yazoo River Basin, MS; Wappapello Lake is in St. Francis 
River Basin, MO. 
42-21

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 42-D AUTHORIZING LEGISLATION 
Act or 
Authorization Work Authorized Document 
May 15, 1928 
Jun. 19, 1930 
Feb. 15, 1933 
Apr. 23, 1934 
Aug. 30, 1935 
Jun. 15, 1936 
Flood protection in alluvial valley of Mississippi River, revetment 
and contraction works and dredging to provide least channel 
depth of 9 feet and width of 300 feet below Cairo. 
Provided for allotment of the balance of emergency rescue funds 
to reimburse levee districts and others for expenditures in floodcontrol 
works during the 1927 and subsequent floods. 
Provided for ownership of lands in Bonnet Carr& Spillway and 
Floodway with proviso for granting rights-of-way, easements, 
and permits, in said lands 
Authorized payment for purchase of, or to reimburse states and 
local levee districts for the cost of, levee rights-of-way for flood 
control work in the Mississippi Valley, and for other purposes. 
Improvement of Wolf and Nonconnah Rivers, TN (Nonconnah 
Creek is correct title) 
Improvement of Wolf River (Memphis Harbor), TN 
Modification of the 1928 Act to provide for: 
Construction of a backwater levee at mouth of White River, AR 
Construction of Eudora floodway in lieu of Boeuf floodway; flood 
control, Yazoo River; construction of Morganza floodway; and 
an outlet to the Gulf of Mexico west of Berwick, LA, including a 
6-year program for the improvement and regularization of the 
Mississippi River between Arkansas and Red Rivers, and 
Atchafalaya River; and construction of roads on levees and 
drainage adjustments incident to floodway levees. 
Provided for construction of floodwalls, levees, and revetments 
along Wolf River and Nonconnah Creek for protection of 
Memphis, TN 
Modify the Yazoo River project to substitute a combined 
reservoir floodway and levee plan. 
Construction of Mounds to Mound City levee and control works 
along Cache River, IL 
Modification of previous act pertaining to floodways and outlets 
and lands therein; including program for the improvement and 
regularization of the Mississippi River, between Cairo and 
oAfr kansas River, extension of levee road system; strengthening levees. 
Enlarge main line levees to offset abandonment of floodways 
between Arkansas and Red Rivers, flood control works in 
backwater areas of Yazoo and Red Rivers, and in Bayous 
Rapides, Boeuf, and Cocodrie, LA 
Navigation channel 12 feet deep and 300 feet wide between Baton 
Rouge and Cairo; flood protection of Yazoo River Backwater 
Area in vicinity of Satartia, MS 
Continue prosecution of channel improvement and stabilization 
program, $200 million. 
Flood control on the Big Sunflower, Little Sunflower, 
Hushpuckena, and Quiver Rivers and their tributaries, and on 
Hull Brake-Mill Creek Canal, Bogue Phalia, Ditchlow Bayou, 
Deer Creek, and Steele Bayou, MS 1 
Improve Boeuf and Tensas Rivers and Bayou Macon, AR1 
Improve Bayou Lafourche, LA 
Improve Yazoo River tributaries. 
North bank, Arkansas River levees (below Plum Bayou). 1 
Unpublished report on 
record in OCE. 
H. Comm. on Flood Control, 
Doc. 1, 75th Cong., 1st sess. 
H. Comm. on Flood Control, 
Doc. 1, 75th Cong., 1st sess. 
H. Doc. 359, 77th Cong., 1st 
sess. 
H. Doc. 509, 78th Cong., 2d 
sess. 
Public Law 534, 78th Cong., 
2d sess. 
H. Doc. 516, 78th Cong., 2d 
sess. 
S. Doc. 151, 78th Cong., 2d 
sess. 
S. Doc. 191, 79th Cong., 2d 
sess. 
H. Doc. 516, 78th Cong., 2d 
sess. 
H. Doc. 308, 74th Cong., 1st 
sess. 
42-22 
H. Doc. 90, 70th Cong., 1st 
sess. 
Public 395, 71st Cong., 2d 
sess. 
Public 351, 72d Cong. 
Public 171, 73d Cong. 
R&H Comm. Doc. 26, 72d 
Cong., 1st sess. 
R&H Comm. Doc. 45, 74th 
Cong., 1st sess. 
Unpublished report dated 
Apr. 2, 1925. 
H. Comm. on Flood Control, 
Doc. 1, 74th Cong., 1st sess. 
Aug. 28, 1937 
Jun. 28, 1938 
Aug. 18, 1941 
Dec. 22, 1944 
Jul. 24, 1946

TABLE 42-D 
(Continued) 
MISSISSIPPI RIVER COMMISSION 
AUTHORIZING LEGISLATION 
Act or 
Authorization Work Authorized 
Levees on White River (Augusta to Clarendon).' 
Bayou des Glaises diversion channel, LA x ' 
Modify local cooperation requirements in St. Francis and Yazoo 
Basins. 
Tiptonville-Obion levee and drainage improvements.' 
Improvement of St. Johns Bayou, MO 
Big Sunflower River, etc.' 
Tennessee Chute (Memphis Harbor), TN 
Continue prosecution of project for flood control and channel 
improvement, $100 million. 
Improve Mississippi River below Cape Girardeau, MO with 
respect to West Tennessee tributaries. 
Improve L'Anguille River, AR 
Baton Rouge Harbor (Devils Swamp), LAx ' 
Flood protection at Des Arc, AR 
Improve St. Francis River and Basin, AR and MO 
Improve Cache River and Bayou DeView, AR and MO 
Improve Grand Prairie Region and Bayou Meto Basin, AR 
Flood protection, Lake Pontchartrain, Jefferson Parish, LA' 
Filling Grant's Canal, Lake Providence, LA 
Additional protection to Red River Backwater Area. 
Extend Federal jurisdiction to cover levees in Orleans Parish, LA 
Bank protection, Amite River, LA 
Continue prosecution of project for flood control and channel 
improvement, $200 million. 
Jonesville, LA levee, retaining wall, and drainage structure.' 
Modify requirements for local cooperation in White River 
Backwater Area, AR 
Navigation improvement of Atchafalaya from Mississippi River 
to Morgan City, LA 
Modify project for Vicksburg-Yazoo Area (Harbor), MS 
Improve New Madrid Floodway, MO, including Peafield 
drainage floodgate. 
Control of Old and Atchafalaya Rivers and a lock for navigation. 
Improve Reelfoot Lake area, KY and TN 
Improve Greenville Harbor, MS 
42-23 
.__.._. 
Jun. 30, 1948 
May 17, 1950 
Oct. 30, 1951 
Sep. 3, 1954 
Jul. 3, 1958 
Document 
H. Doc. 98, 76th Cong., 1st 
sess. 
H. Doc. 602, 79th Cong., 2d 
sess. 
Public Law 526, 79th Cong., 
2d sess. 
H. Doc. 757, 79th Cong., 2d 
sess. 
H. Doc. 138, 80th Cong., 1st 
sess. 
H. Doc. 516, 78th Cong., 2d 
sess. 
S. Doc. 51, 80th Cong., 1st 
sess. 
Public Law 526, 79th Cong., 
2d sess. 
H. Doc. 627, 80th Cong., 2d 
sess. 
H. Doc. 651, 80th Cong., 2d 
sess. 
H. Doc. 321, 80th Cong., 1st 
sess. 
H. Doc. 485, 81st Cong., 2d 
sess. 
H. Doc. 132, 81st Cong., 1st 
sess. 
S. Doc. 88, 81st Cong., 1st 
sess. 
H. Doc. 255, 81st Cong., 1st 
sess. 
S. Doc. 139, 81st Cong., 2d 
sess. 
Public Law 516, 81st Cong., 
2d sess. 
Public Law 516, 81st Cong., 
2d sess. 
Public Law 516, 81st Cong., 
2d sess. 
Public Law 516, 81st Cong., 
2d sess. 
Public Law 516, 81st Cong., 
2d sess. 
S. Doc. 117, 81st Cong., 1st 
sess. 
Public Law 237, 82d Cong., 
1st sess. 
S. Doc. 53, 82d Cong., 1st 
sess. 
H. Doc. 85, 83d Cong., 1st 
sess. 
H. Doc. 183, 83d Cong., 1st 
sess. 
H. Doc. 478, 83d Cong., 2d 
sess. 
S. Doc. 160, 83d Cong., 2d 
sess. 
S. Doc. 15, 86th Cong., 1st 
sess.

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 42-D 
(Continued) 
AUTHORIZING LEGISLATION 
Act or 
Authorization Work Authorized Document 
Jul. 14, 1960 
Oct. 23, 1962 
Jun. 18, 1965 
Oct. 27, 1965 
Extensions to project for Boeuf and Tensas Rivers and Bayou 
Macon in Arkansas. 
White River backwater area pumping plant. 
Wolf River and tributaries for flood protection in Tennessee. 
Continue prosecution of project for channel improvement-$50 
million. 
Modification-Baton Rouge Harbor (Devils Swamp), LA 
Construct improvements in Gin and Muddy Bayous, Yazoo River 
Basin, MS 
Replace 2 bridges with adequate floodway over Boeuf River and 
Big Bayou in Boeuf Basin, AR 
Continue prosecution of project for flood control and channel 
improvement, $53 million. 
Modify and expand levees and channel improvement features of 
main stem project. 
Modify flood control improvements in following tributary areas 
and basins: Cairo-Mounds-Mounds City, St. Francis, Lower 
White, Boeuf-Tensas-Macon, Red River backwater, Yazoo 
headwater, Grand Prairie, and Bayou Meto. 
Acquire any modified easements required in New Madrid 
Floodway as provided by Sec. 4 of May 15, 1928 act. 
Operate and maintain pumping plant in Red River backwater 
area (Tensas-Cocodrie Pumping Plant). 
Provide improvements in West Kentucky tributaries. 
Provide fish and wildlife facilities in St. Francis and Big 
Sunflower Basins; Yazoo Headwater and Backwater Areas; and 
Mississippi Delta region. 
Deauthorize Amite River, LA project. 
Modify St. Francis River, MO and AR, project within District 
No. 7, Poinsett County, AR 
Provide pumping plant and drainage structure at Wilson Point, 
LA 
Construction of improvements to supplement freshwater supply 
in Teche-Vermilion Basins in Louisiana. 
Bank revetment for protection of existing industrial facilities 
along Mississippi River below Baton Rouge, LA 
Modification of West Tennessee tributaries feature to provide 
relocation of gas transmission lines at Federal expense. 
Continue emergency work, $87,135,000 which includes $100,000 
for road crossing of Panola-Quitman Floodway, MS, and $80,000 
for protection of Sheley Bridge, Tallahatchie River, MS 
Improvements in Boeuf and Tensas Rivers and Bayou Macon 
Basin to divert flows that would otherwise enter Lake Chicot, 
AR 
Improvements in the Belle Fountain ditch and tributaries, MO, 
and Drainage District No. 17, AR 
Provide pumping plants and other drainage facilities in Cairo, 
IL, and vicinity. 
Modification of Yazoo Headwater Project to include cleanout 
along David Bayou, MS 
Modify Yazoo Backwater feature to include a control structure in 
Muddy Bayou, MS 
42-24 
H. Doc. 108, 85th Cong., 1st 
sess. 
S. Doc. 26, 85th Cong., 1st 
sess. 
H. Doc. 76, 85th Cong., 1st 
sess. 
Public Law 86-645. 
Public Law 87-874. 
Public Law 87-874. 
Public Law 87-874. 
Public Law 89-42. 
H. Doc. 308, 88th Cong., 2d 
sess. 
H. Doc. 308, 88th Cong., 2d 
sess. 
H. Doc. 308, 88th Cong., 2d 
sess. 
H. Doc. 308, 88th Cong., 2d 
sess. 
H. Doc. 308, 88th Cong., 2d 
sess. 
H. Doc. 308, 88th Cong., 2d 
sess. 
H. Doc. 308, 88th Cong., 2d 
sess. 
S. Doc. 57, 89th Cong., 1st 
sess. 
Unpublished Vicksburg 
District's MRC report 
Approved-Apr. 14, 1966. 
H. Doc. 524, 89th Cong., 2d 
sess. 
Public Law 89-789. 
Public Law 89-789. 
Public Law 90-147. 
H. Doc. 168, 90th Cong., 1st 
sess. 
H. Doc. 339, 90th Cong., 2d 
sess. 
Public Law 90-483. 
Unpublished MRC report 
dated May 8, 1968. 
Unpublished MRC report 
dated Feb. 2, 1970. 
Apr. 14, 19662 
Nov. 7, 1966 
Nov. 20, 1967 
Aug. 13, 1968 
Sep. 10, 1968$ 
Mar. 3, 19708

TABLE 42-D 
(Continued) 
MISSISSIPPI RIVER COMMISSION 
AUTHORIZING LEGISLATION 
Act or 
Authorization Work Authorized Document 
Apr. 29, 19703 
Jun. 4, 19703 
Dec. 31, 1970 
Senate and 
House Public 
Works 
Resolutions 
adopted Dec. 17 
and 15, 1970, 
respectively.4 
River Basin 
Monetary Act 
of Dec. 23, 1971 
Jan. 19, 19732 
TITLE I Water 
Resources 
Development 
Act of 1974. 
Modification of Yazoo Headwater Project to include drainage 
structure and channel improvement on Rocky Bayou, MS 
Provide for enlargement of Bayou Latenache from Pointe Coupee 
drainage structure to Alabama Bayou, LA 
Modify and expand project to include flood protection within the 
area of eastern Rapides and south-central Avoyelles Parishes, 
LA, that are drained by Bayou des Glaises diversion channel and 
Lake Long, and their tributaries. 
Modify the project for West Kentucky tributaries (Obion Creek), 
KY, to provide for all relocations, at Federal expense, of all 
transmission lines required by the project. 
Report on Western Tennessee Tributaries, TN and KY, 
authorized: 
a. Modification of Reelfoot Lake feature to provide channel 
improvements on Bayou du Chien and Lake No. 9 in KY and 
TN 
b. Modification of Mississippi levee feature to include a 
pumping station near Mud Lake floodgate and adjacent 
channel improvements. 
Modification of Big Sunflower Basin feature to provide 
additional improvements in Steele Bayou Basin, MS 
Continue prosecution of project for the comprehensive 
development of the basin, $97 million. 
Modification of Tiptonville-Obion River levee feature to relieve 
local interests of all responsibility except that of providing 
maintenance. 
Modification of the Mississippi levee feature to provide additional 
drainage facilities in Long Lake area, vicinity of Helena, AR 
Projects recommended by four completed reports were 
authorized for accomplishment of Phase I design memorandum 
of advance engineering and design on: 
a. Greenville Harbor, Greenville, MS 
b. East bank of Mississippi River, Warren to Wilkinson 
Counties, MS (Natchez area). 
c. East bank of Mississippi River, Warren to Wilkinson 
Counties, MS (Vicksburg-Yazoo area). 
d. Bushley Bayou Area of Red River Backwater Area, LA 
Modification of West Tennessee tributaries feature (Obion and 
Forked Deer Rivers), TN, to acquire lands for fish and wildlife, 
recreation, and environmental purposes. 
Modification of the Yazoo Basin, MS, feature to provide for a 
streambank erosion control demonstration project for the delta 
and hill areas of basin. 
Modification of project to provide that the Secretary of the Army, 
acting through the Chief of Engineers, can substitute authorized 
mitigation lands, not yet acquired and no longer suitable, for 
like acreage in the same or adjacent subbasins of the project 
area. This section provides the authority to substitute authorized 
mitigation lands in: 
a. Tensas Basin, LA and AR, feature (Red River backwater). 
b. St. Francis Basin, AR and MO, feature. 
Modification of Bayou Cocodrie and tributaries, LA, feature, to 
provide for: enlargement of Bayou Courtableau from 
Washington to west protection levee; right-of-way and spoil 
disposal areas at Federal expense; and necessary additional 
culverts through west protection levee. 
Unpublished MRC report 
dated Mar. 6, 1970. 
Unpublished MRC report 
dated Sep. 22, 1969. 
S. Doc. 91-113, 2d sess. 
Public Law 91-611. 
H. Doc. 91-414, 2d sess. 
S. Doc. 91-74, 2d sess. 
Sec. 1, Public Law 92-222. 
Sec. 7, Public Law 92-222. 
Unpublished Memphis 
District's MRC report 
dated Oct. 4, 1972. 
Sec. 1, Public aw 93-251. 
Mar. 7, 1974. 
S. Doc. 93-38, 1st sess. 
H. Doc. 93-148, 1st sess. 
H. Doc. 93-148, 1st sess. 
H. Doc. 93-157, 1st sess. 
Sec. 3, Public Law 93-251. 
Sec. 32, Public Law 93-251. 
Sec. 42, Public Law 93-251. 
Sec. 87, Public Law 93-251. 
42-25

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 42-D 
(Continued) 
AUTHORIZING LEGISLATION 
Act or 
Authorization Work Authorized Document 
TITLE II River 
Basin 
Monetary 
Authorization 
Act of 1974 
River Basin 
Monetary Act 
of Oct. 2, 1975 
Dec. 16, 19752 
TITLE II Public 
Works for 
Water and 
Power 
Development 
and Energy 
Research 
Appropriation 
Act 1976. 
TITLE II Public 
Works for 
Water and 
Power 
Development 
and Energy 
Research 
Appropriation 
Act, 1977. 
Water Resources 
Development 
Act of 1976. 
TITLE II Public 
Works for 
Water and 
Power 
Development 
and Energy 
Research 
Appropriation 
Act, 1978. 
Modification of Cache River Basin, AR, feature to provide for: 
acquisition by fee easements of lands for fish and wildlife 
management, recreation, and environmental purposes. 
Continue prosecution of project for the comprehensive 
development of the basin, $211 million. 
Continue prosecution of project for the comprehensive 
development of the basin, $158,000,000. 
Modification of St. Francis Basin, AR and MO, feature to provide 
relief from ponding of interior runoff in the Inter-River 
Drainage District of Missouri. 
Continue prosecution of project for comprehensive development 
during period Jul. 1- Sep. 30, 1976, $60,300,000. 
Continue prosecution of project for flood control, rescue work, 
repair, restoration, and control of bank erosion, $231,497,000. 
Sec. 101(a) authorized accomplishment of Phase I - Advanced 
Engineering and Design Memoranda - On: 
a. St. Johns Bayou and New Madrid Floodway, MO, project: 
Report of OCE - Sep. 26, 1975. 
b. Nonconnah Creek, TN and MS, project: Report of OCE - Jun. 
23, 1976, and as an independent part of the project: 
Improvements for flood control and allied purposes on Horn 
Lake Creek and tributaries, including Cowpen Creek, TN 
and MS. 
Modification of West Tennessee Tributaries feature (Obion and 
Forked Deer Rivers), TN, to: 
a. (Sec. 102)- Provide project for flood control for Harris Fork 
Creek, TN and KY: (H.D. 94-221) except that highway bridge 
relocations and alterations shall be at Federal expense. 
b. (Sec. 183)- Provide for construction of a levee and 
appurtenant works from mouth of Obion diversion channel to 
vicinity Highway 88 and thence to vicinity of Porter Gap, TN 
Continue prosecution of project for flood control, rescue work, 
repair, restoration, and control of bank erosion, $258,081,000. 
Sec. 99, Public Law 93-251. 
Sec. 201, Public Law 93-251. 
Mar. 7, 1974. 
Sec. 1, Public Law 94-101. 
Unpublished Memphis 
District's MRC report 
dated Nov. 11, 1975. 
Public Law 94-180, Dec. 26, 
1975. 
Public Law 94-355, Jul. 12, 
1976. 
Public Law 94-587, Oct. 22, 
1976. 
Public Law 95-96 Aug. 7, 
1977. 
42-26

TABLE 42-D 
(Continued) 
MISSISSIPPI RIVER COMMISSION 
AUTHORIZING LEGISLATION 
Actor 
Authorization Work Authorized Document 
Dec. 9, 1977, 5th Modification of the Tensas Basin Project, Red River Backwater Unpublished Vicksburg 
Ind. on VXD Area, to include a drainage structure and appurtenant channel District report dated May 
May 31, 1977, works in the Six Mile Bayou area of Concordia Parish, LA 31, 1977, on Cynthia and 
Letter Report.2 Six Mile Bayous, LA 
Jun. 28, 1980 The establishment of the Tensas River National Wildlife Refuge Public Law 96-285, Jun. 28, 
for the preservation and development of environmental 1980. 
resources and in lieu of mitigation acquisitions which otherwise 
would be required for certain water resources projects, within 
designated limits, in the basins of the Tensas, Boeuf, and Red 
Rivers in the State of Louisiana. 
Energy and For expenses necessary for prosecuting work of flood control Public Law 96-367, Oct. 1, 
Water projects, rescue work, repair, restoration or maintenance of 1980. 
Development flood control projects threatened or destroyed by flood, 
Appropriation $232,519,000: Provided, That not less than $250,000 be available 
Act, 1981 or control of bank erosion of streams in the Yazoo Basin, 
including the foothill area. Provided further, That funds for the 
Tensas Basin Red River Backwater Area, be used for flood 
control, etc. for Sicily Island and Below Red River including 
pumping stations. 
1. Incorporated into Mississippi River and tributaries 3. Date minor modification was approved under disproject 
as shown in Table 42-E. cretionary authority of Chief of Engineers contained in May 
2. Date minor modification for blocked drainage was 15, 1928, Flood Control Act, as amended. 
approved under delegated authority of the President, Missis- 4. Projects approved under the provisions of Sec. 201 of 
sippi River Commission, and in accordance with Sec. 10(p) of Flood Control Act of Oct. 27, 1965. 
the 1946 Flood Control Act (Public Law 79-526). 
TABLE 42-E INCORPORATING AND AUTHORIZING LEGISLATION 
For Last 
Public Full Report 
Act of Law Authorizing See Annual 
Incorporation No. Act Description Report for 
Jul. 24, 1946 79-526 Jun. 22, 1936 Tiptonville-Obion levee and drainage 1941, p. 943 
improvements, TN 
Jul. 24, 1946 79-526 Jun. 22, 1936 Bayou des Glaises diversion ditch, LA 1946, p. 1029 
Jul. 24, 1946 79-256 Jun. 22, 1936 From North Little Rock, AR, to Gillett, AR, on 1946, p. 1053 
north bank of Arkansas River (portion below 
Plum Bayou). 
Jul. 24, 1946 79-256 Aug. 18, 1941 White River levees, Augusta to Clarendon and De 1946, p. 1083 
Valls Bluff, AR 
Jul. 24, 1946 79-526 Dec. 22, 1944 Boeuf and Tensas Rivers and Bayou Macon, LA 1945, p. 982 
Jul. 24, 1946 79-526 Dec. 22, 1944 Big Sunflower River, etc. 1946, p. 1061 
Jun. 30, 1948 80-858 Jul. 24, 1946 Devils Swamp barge channel at Baton Rouge, LA 1948, p.1059 
(Baton Rouge Harbor) 
May 17, 1950 81-516 Jun. 22, 1936 Jonesville, LA 1953, p.773 
May 17, 1950 81-516 Jul. 24, 1946 Lake Pontchartrain-Jefferson Parish, LA 1953, p. 737 
42-27

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 42-F SUMMARY OF PRESENTLY ESTIMATED 
FEDERAL FIRST COST OF AUTHORIZED IMPROVEMENTS 
Project Title 
Estimated Cost1 
Fiscal Year 1983 
Completed features2 
Mississippi River levees 
Mud Lake Pumping Station, TN 
Sec. 6 levees, 1928 Flood Control Act 
Channel improvement 
Atchafalaya Basin, LA 
Bayou Cocodrie and tributaries, LA 
Old River, LA 
Lower Red River- South Bank Red River levees, LA 
Eastern Rapides and South-Central Avoyelles Parishes, LA 
Mississippi Delta Region, LA 
Teche-Vermilion Basins, LA 
Tensas Basin, AR and LA 
Lower Arkansas River, AR 
Grand Prairie-Bayou Meto, AR 
Yazoo Basin, MS 
Lower White River, AR 
Cache Basin, AR 
St. Francis Basin, AR and MO 
L'Anguille Basin, AR 
West Tennessee Tributaries, TN 
Harris Fork Creek, TN & KY 
Reelfoot Lake-Lake No. 9, TN & KY 
Reelfoot Lake, TN & KY (Completed) 
Reelfoot Lake-Lake No. 9, TN & KY 
West Kentucky Tributaries, KY 
Tensas River National Wildlife Refuge 
TOTAL 
$ 165,432,000 
1,516,000,000 
4,170,000 
4,000,000 
3,055,000,000 
1,752,000,000 
25,000,000 
320,000,000 
42,000,000 
57,900,000 
33,200,000 
35,700,000 
495,000,000 
34,700,000 
130,900,000 
1,625,000,000 
52,000,000 
146,000,000 
351,000,000 
24,900,000 
89,400,000 
18,000,000 
(10,840,000) 
440,000 
10,400,000 
22,500,000 
40,000,000 
$10,050,642,000 
1. Inflation projected through the construction period. 
2. Includes Bonnet Carr, Morganza, and New Madrid 
Floodways; Memphis, Greenville, and Vicksburg Harbors; 
Lake Pontchartrain; Wolf River; completed roads on main 
stem levees; channel construction works; Atchafalaya River 
and Basin; Wax Lake Outlet; Charenton Canal; Bayou des 
Glaises diversion channel, Boeuf Basin levees; Grant's Canal; 
De Valls Bluff, Jonesville, and Des Arc protection works; 
Baton Rouge Harbor; and miscellaneous features. 
42-28

TABLE 42-G 
MISSISSIPPI RIVER COMMISSION 
MISSISSIPPI RIVER MAIN STEM 
CHANNEL IMPROVEMENTS 
Operations in 1,000 Cubic Yards 
Location Fiscal Year 1983 
Mileage 
Above Head Channel 
District of Passes Construction Maintenance Total 
New Orleans 
Baton Rouge Harbor 
(Devils Swamp) 235 - 132.7 132.7 
Main stem channel 234-320 - 357.3 357.3 
Vicksburg 
Main stem channel 320-600- 2,831.0 2,831.0 
Vicksburg Harbor 437 - 0 0 
Greenville Harbor 537 - 273.0 273.0 
Memphis 
Main stem channel 600-954 846.3 11,672.7 11,672.7 
Memphis Harbor 726 - 466.4 466.4 
TOTAL 846.3 15,733.1 15,733.1 
42-29

TABLE 42-H BANK REVETMENTS AND DIKES: NEW ORLEANS DISTRICT 
(FISCAL YEAR 1983) 
Operations This FY 
Construction Nonop- Operaerative 
tive 
Above New Work Reinforcement Since Thru 
Head Bank Exten- Prior This 
Location of R sion Lap Mainte- FY FY 
Passes or (Linear (Linear (Linear nance (Linear (Linear 
(Miles) L Feet) Feet) (Squares)1 Feet) (Squares) (Squares) Feet) Feet) 
MISSISSIPPI RIVER 
Standard revetment: 
Lower Childress- 
Fort Jackson, LA ............ 22 
Buras, LA .................... 25 
Tropical Bend, LA ............ 30 
Port Sulphur, LA ............ 39 
Point Michel, LA ............. 44 
Bohemia, LA ................. 46 
Diamond, LA ................. 49 
Gravolet, LA ................. 51 
Junior, LA ................... 54 
Harlem, LA .................. 56 
Myrtle Grove, LA ............ 59 
Monsecour, LA .............. 61 
Alliance, LA ................ 62 
Belair, LA ................... 65 
Jesuit Bend, LA ............. 68 
Linwood, LA ................. 71 
Oak Point, LA ............... 72 
Scarsdale, LA ............... 75 
English Turn, LA ............ 78 
Poydras, LA .................. 82 
Cutoff, LA ................... 88 
Third district reach, LA ....... 93 
Algiers Point, LA ............ 95 
Gouldsboro Bend, LA ......... 96 
Gretna Bend, LA ............. 97 
Greenville Bend, LA .......... 100 
Carrollton Bend, LA .......... 104 
Avondale Bend, LA .......... 109 
Kenner, LA .................. 114 
Luling, LA.................. 119 
Good Hope,'LA ............... 126 
Waterford, LA ............... 128 
Montz, LA ................... 132 
Lucy, LA .................... 136 
Reserve, LA ................. 138 
Willow Bend, LA ............ 141 
Angelina, LA ................ 145 
Vacherie, LA ................. 148 
Belmont, LA ................. 152 
Rich Bend, LA ............... 157 
Romeville, LA ................ 161 
R
RRRRL
RL
RL
RL
RL
RL
RL
RL
RL
RRRRLRLRLRLRLRLRL
RL 
4,320 
2,600 
5,315 
5,635 
6,840 
5,495 
1,380 
250 26,737 
160 11,770 
90 26,685 
55 22,866 
120 24,883 
130 25,642 
135 5,796 
4,175 
4,169 
10,133 
10,194 
17,283 
25,012 
27,238 
17,842 
12,380 
8,750 
17,435 
17,570 
13,975 
15,925 
10,020 
9,750 
21,295 
22,860 
9,125 
7,040 
11,575 
13,750 
44,814 
21,256 
21,101 
7,728 
4,960 
9,662 
22,045 
15,015 
22,371 
22,219 
28,908 
14,980 
12,295 
17,502 
17,826 
20,947 
7,618 
19,000 
13,295 
24,785 
19,144 
15,334 
2,430 
4,599 
r

St. Alice, LA ................. 165 
Burnside, LA ................ 170 
Aben, LA ................... 172 
St. Elmo, LA ................. 174 
Smoke Bend, LA ............ 177 
Marchand, LA ............... 180 
Philadelphia Point, LA ........ 183 
New River Bend, LA ......... 185 
White Castle, LA ............ 193 
St. Gabriel, LA ............... 201 
Plaquemine Bend, LA ........ 209 
Manchac, LA ................ 215 
Missouri Bend, LA ........... 222 
Arlington, LA ................ 227 
Port Allen, LA ............... 231 
Allendale, LA ................ 238 
Springfield Bend, LA ......... 244 
Arboth, LA .................. 250 
Grand Bay, LA .............. 258 
Bayou Sara, LA ............. 265 
Red Store, LA ................ 269 
Arrow Bend, LA .............. 272 
Boies Point, LA ............... 275 
Morganza, LA ................ 279 
Iowa Point, LA ............. 282 
Brunette Point, LA .......... 285 
Greenwood Bend, LA ......... 289 
Hog Point, LA ................ 296 
Carr Point, LA ............... 304 
Above Old River, LA ......... 305 
Fort Adams, MS .............. 308 
Point Breeze, LA ............ 313 
Coochie, LA ................. 317 
Palmetto, MS ................ 322 
Subtotal 
New Orleans District, 
Mississippi River ...... 
Dikes: 
None 
OLD RIVER CONTROL 
Standard revetment: 
Inflow channel ............. 315 
Inflow channel ............... 315 
Outflow channel .............. 315 
RL
RLRLRL
RL
RLRLR
RL 
R
RLRL
RRLRLRRRL
RRL 
L
RR 
4,680 
10,790 
3,485 
110 24,878 
430 55,124 
6,742 
2,799 
13,071 
6,633 
6,689 
27,052 
16,050 
10,113 
10,240 
17,075 
7,845 
5,379 
24,394 
33,335 
25,161 
35,475 
30,972 
16,193 
12,244 
11,320 
17,940 
25,690 
13,190 
7,090 
4,780 
11,315 - 
13,600 
16,094 
20,513 r 
11,375 
8,038 
14,987 - 
8,673 E 
8,600 
4,800 ! 
17,219 n 
11,165 C 
17,150 
3Q64 
8,897 
50,540 1,480 233,278 - - 61,440 - 1,237,755 
(9.57 Miles) (234.42 Miles) 
- - - - - - - 2,415 
- - - - - - - 4,365 
- - - - - - - 17,754 
0
zin 
Total standard revetment, 
Old River ............... 24,534 
(4.65 Miles)

TABLE 42-H 
(Continued) 
BANK REVETMENTS AND DIKES: NEW ORLEANS DISTRICT 
(FISCAL YEAR 1983) 
Operations This FY N 
Construction Neroantoivpe- Otpaevera- 
Above New Work Reinforcement Since Thru 
Head Bank Exten- Prior This 
Location of R sion Lap Mainte- FY FY 
Passes or (Linear (Linear (Linear nance (Linear (Linear 
(Miles) L Feet) Feet) (Squares)' Feet) (Squares)' (Squares) Feet) Feet) 
ATCHAFALAYA RIVER 
Standard revetment: 
Mile One, LA ................ 
Coville, Bayou, LA ........... 
Legonier, LA ................ 
Simmesport, LA ............. 
Kuhlman Bayou, LA ......... 
Odenburg, LA ............... 
Cason, LA ................... 
McCrea, LA ................. 
Woodside, LA ............... 
Provosty, LA ................. 
Crooked Bayou, LA ........... 
Mercier, LA ................. 
Barberton, LA .............. 
Evans Point, LA ............. 
Goudeau, LA ................ 
Morris Bayou, LA ........... 
Goodwood, LA ............... 
Red Cross, LA ............... 
Melville, LA ................. 
Cross Bayou, LA ............. 
Melville South, LA ........... 
Toles, LA ................... 
Petite Prairie, LA ........... 
Holloway Lake, LA .......... 
Bayou Sherman, LA ......... 
Krotz Springs, LA ........... 
Sherburne, LA .............. 
Bayou Big Graw, LA ......... 
Morgan City ................. 
Total standard revetment ... 
Below Confluence 
of Red and 
Atchafalaya 
Rivers 
1
34679 
12 
13 
14 
17 
18 
22 
23 
24 
26 
27 
28 
29 
30 
31 
33 
35 
36 
37 
38 
40 
43 
46 
115 
L
RLRLRRL 
RL 
RL 
RL 
RL 
RLRLRL 
RLL 
RRRL 
- - - - - - - 4,150 
- - - - - - - 6,550 
- - - - - - - 8,940 
- - - - - - - 10,636 
- - - - - - - 5,565 
- - - - - - - 5,375 
- - - - - - - 10,798 
- - - - - - 5,027 
- - - - - - - 13,002 
- - - - - - - 7,768 
- - - - - - - 9,600 
- - - - - - - 10,478 
- - - - - - 3,592 
...... 4,961 
- - - - - - - 3,938 
- - - - - - - 3,800 
- - - - - - - 8,505 
- - - - - - - 8,065 
- - - - - - - 4,870 
- - - - - - - 3,815 
- - - - - - - 4,070 
- - - - - - - 6,355 
- - - - - - - 8,381 
- - - - - - - 7,085 
- - - - - - - 5,200 
- - - - - - - 4,625 
- - - - - - - 7,035 
- - - - - - - 8,394 
- - - - - - - 3,410 
- - - - - - - 193,990 
(36.74 Miles) 
Dikes: 
None 
0
0
0
z
li' 
O
y
0
y
n
x
O
z
z
>
d 
ca 
00

LOWER RED RIVER 
Standard revetment: 
Long Lake, LA .............. 
Naples, LA .................. 
Turnbull Island, LA ......... 
Total standard revetment 
Below Confluence 
of Old River 
Outflow Channel 
and Red River 
10
79 
RRL 
- - - - - - - 6,652 
- - - - - - - 6,190 
- - - - - - - 6,815 
- - - - - - - 19,657 
(3.72 Miles) 
Dikes: 
None 
1. Gross squares articulated concrete mattress (100 square feet).

TABLE 42-I BANK REVETMENTS AND DIKES: VICKSBURG DISTRICT 
(FISCAL YEAR 1983) 
Operations This FY 
Construction eNroantiovpe- Otpiveera- 
Above New Work Reinforcement Since Thru 
Head Bank Exten- Prior This 
Location of R sion Lap Mainte- FY FY 
Passes or (Linear (Linear (Linear nance (Linear (Linear 
(Miles) L Feet) Feet) (Squares)1 Feet) (Squares)' (Squares) Feet) Feet) 
MISSISSIPPI RIVER 
Standard revetment: 
Bougere Bend, LA ........... 
Dead Mans Bend, MS ......... 
Railroad Landing, MS ....... 
St. Catherine Bend, LA ...... 
Morville, LA ................ 
Natchez Island, MS .......... 
Carthage, MS ............... 
Natchez Front, MS ........... 
Gibson, LA ................... 
Ashland, LA-MS ............ 
Kempe Bend, LA ............ 
Browns Field, LA ........... 
Goldbottom, MA ............. 
Hardscrabble, LA ........... 
Grand Gulf, MS ............. 
Point Pleasant, MS-LA ....... 
Togo Island, LA.............. 
Lake Karnac, LA-MS ......... 
Diamond Point, LA-MS ....... 
Reid-Bedford, LA ........... 
Racetrack, MS ............... 
Barge Line Terminal, MS ..... 
Vicksburg Harbor, MS ...... 
Delta Point, LA ............... 
King's Point-Opposite 
Delta Point, LA-MS ........ 
False Point, LA .............. 
Marshall-Brown's Point, 
LA-MS ................... 
Milliken Bend, LA ............ 
Belle Island, LA-MS ......... 
Goodrich, LA ................ 
Fitler-Cottonwood, MS ....... 
Hagaman, LA ............... 
Ben Lomond, MS ............ 
Baleshed Towhead-Stack 
Island, LA-MS ............ 
Lake Providence, LA ........ 
Mayersville, MS ............. 
Sarah Island-Opossum Point, 
LA-MS ................... 
329 
335 
346 
350 
356 
357 
361 
364 
371 
374 
383 
389 
392 
398 
403 
413 
415 
419 
423 
429 
433 
437 
437 
437 
439 
443 
446 
453 
460 
467 
474 
481 
486 
488 
489 
497 
RLL 
RRRLL 
RL 
RRL 
RL 
RRLRRLLL 
R
L
R
L
RL 
RLRL 
RRL 
7,215 
3,920 
22,579 
9,064 
20,805 0 
10,380 y 
7,215 
21,470 0 
11,815 
2,180 
14,585 tj 
6,510 
22,735 
18,657 
26,655 
9,280 
30,250 
22,530 
49,076 Z 
32,345 
5,670 
19,260 m 
12,125 
18,392 
13,935 
3,040 
7,350 
7,650 
19,330 
12,860 4 
19,580 
44,650 
24,160 
37,220 
28,427 
37,756 
10,235 
52,1242 
11,600 
34,992 
503 R 16,970

Carolina, MS ................. 
Cracraft, AR ................ 
Worthington, MS-AR ........ 
Walnut Point Kentucky 
Bend, MS .................. 
American Cutoff, MS-AR ..... 
Sunnyside-Lakeport, AR ...... 
Vancluse, AR ............... 
Island 84, AR, MS ........... 
Warfield Point, MS .......... 
Leland-LaGrange, AR-MS .... 
Spanish Moss, AR ........... 
Tarpley Island, MS .......... 
Miller Bend, MS ............. 
Island 82, AR ................ 
Ashbrook Island, MS ......... 
Arkansas City-Yellow 
Bend, AR ................. 
Huntington Point, MS ....... 
Pair O'Dice, AR .............. 
Eutaw-Mounds, MS ......... 
Cypress Bend, AR ............ 
Catfish Point, MS............. 
Ozark, AR-MS .............. 
Prentiss, AR-MS ............ 
Rosedale Bend, AR ........... 
Riverton, MS ................ 
Klondike, AR ................ 
Victoria Bend-Terrene, MS ... 
Big Island, AR .............. 
Smith Point, MS ............. 
Dennis, MS ................. 
Cessions, MS ................ 
Total revetment, 
Vicksburg District, 
Mississippi River ........ 
Dikes: 
Jackson Point, MS ........... 
Opposite Warnicott Ldg, MS 
Natchez Island, LA-MS ...... 
Waterproof Bar, LA ......... 
Spithead Towhead, MS ...... 
Browns Field, LA ........... 
Cottage Bend, LA-MS ........ 
Bondurant Towhead, LA ...... 
Coffee Point, LA .............. 
Yucatan, MS ................ 
Togo Island, LA ............. 
Below Racetrack, MS ......... 
Racetrack Towhead, MS ...... 
Marshall Cutoff, LA ......... 
Forest Home Towhead, LA .... 
Willow Cutoff, LA ........... 
Point Lookout, LA ........... 
Ajax Bar, MS ............... 
507 
511 
514 
519 
526 
530 
534 
535 
537 
538 
539 
542 
544 
546 
549 
553 
556 
561 
563 
568 
573 
578 
582 
585 
586 
588 
593 
598 
601 
611 
615 
L
RR 
LL
RRLLL
RRL
RR 
RLRLRL
RLLL
RL
RLLL 
11,080 
22,210 
8,350 
- - - - - - 45,653 
- - - - - - - 2,980 
- - - - - - - 33,685 
- - - - - - - 4,300 
- - - - - - - 13,475 
- - - - - - - 4,320 
- - - - - - - 14,150 
- - - - - - - 4,580 
- - - - - - - 2,000 
- - - - - - - 29,360 
- - - - - - - 3,080 
- - - - - - - 3,455 
- - - - - - - 40,560 
- - - - - - - 10,045 
- - - - - - - 9,095 
- - - - - - - 40,188 
- - - - - - - 26,585 
- - - - - - - 20,075 
- - - - - - - 22,015 
- - - - - - - 20,315 
- - - - - - - 4,820 
- - - - - - - 12,500 
- - - - - - - 23,400 
- - - - - - - 29,245 
- - - - - - - 16,515 
- - - - - - - 18,185 
- - - - - - - 21,265 
- - - - - - - 10,910 
11,135 
(2.10 Miles) 
0 31,643 0 0 1,272,210 
(241.0 Miles) 
(3) 
330 
352 
358 
379 
386 
388 
389 
394 
405 
410 
416 
430 
431 
448 
449 
462 
478 
482 
LL
RRL
RL
RRRLL
RRL
RRL 
5,341 
- 1,000 
2,350 
4,306 
3,341 
7,695 
11,372 
3,6614 
4,8354 
14,049 
4,421 
3,260 
9,010 
8,226 
10,299 
1,752 
5,1664 
4,609 
4,275 
2,751 
24,339 
1,845 
2,260 
2,570

TABLE 42-I 
(Continued) 
BANK REVETMENTS AND DIKES: VICKSBURG DISTRICT 
(FISCAL YEAR 1983) 
Operations This FY 
Construction eNroantiovpe- Otpiveera- 
Above New Work Reinforcement Since Thru 
Head Bank Exten- Prior This 
Location of R sion Lap Mainte- FY FY 
Passes or (Linear (Linear (Linear nance (Linear (Linear 
(Miles) L Feet) Feet) (Squares)' Feet) (Squares) (Squares)' Feet) Feet) 
MISSISSIPPI RIVER 
continued 
Dikes: 
Ben Lomond, MS ............ 
Balshed Ldg., MS ............ 
Wilson Point, LA ............ 
Corregidor, MS .............. 
Carolina, AR ................ 
Cracraft Lower, AR ......... 
Cracraft, AR ................ 
Leota, MS ................... 
Island, 86, AR ............... 
Seven Oaks, AR ............. 
Walnut Point, MS ........... 
Refuge, MS ................. 
Island 84, AR ................ 
Leland Bar, AR-MS ......... 
Leland Neck, AR-MS ........ 
Tarpley Cutoff, MS-AR ...... 
Island 82-Miller Bend, 
AR-MS ................... 
Ashbrook-Miller Bend, 
AR-MS ................... 
Ashbrook Cutoff, MS ........ 
Chicot Ldg., AR ............. 
Catfish Point, MS ............ 
Below Prentiss, MS .......... 
Malone Field, AR ............ 
Terrene, MS ................. 
White River Landing, AR ..... 
Montgomery Towhead, AR .... 
Victoria Bend, AR ........... 
Smith Point, MS ............. 
Island 70, MS ............... 
Total dikes, 
Vicksburg District, 
Mississippi River ........ 
488 
493 
500 
505 
509 
510 
513 
514 
520 
523 
525 
528 
532 
538 
540 
540 
544 
547 
549 
564 
571 
580 
585 
590 
591 
592 
596 
600 
608 
LL 
RLL 
RRL 
RRLLL 
RL 
R 
R&L 
L&R 
L
RL 
RRL 
RRRLL 
5,220 
2,230 
0 
24,667 y 
8,238 
3,592 4 
6,730 , 
2,897 x 
9,614 M 
3,809 r 
7,571 x 
6,592 m 
5,754 Tj 
4,725 0 
5,278 
4,580 M 
14,428 Z 
4,315 
10,320 Z 
13,646 
13,029 
8,728 
17,451 & 
5,290 
7,813 
7,549 
7,921 
2,201 c 
6,071 
5,0334 
7,617 
14,949 
690 
16,141 2,535 
(3.06 Miles) 
369,805 
(70.04 Miles)

ARKANSAS RIVERS 
Standard Revetment: 
Menard Bend, AR ........... 
Como, AR ................... 
Morgan Bend, AR ........... 
Yancopin, AR ............... 
Total standard revetment, 
Arkansas River .......... 
Dikes 
Hopedale Cutoff, AR ......... 
Morgan Bend, AR ........... 
Fletcher Bend, AR ........... 
Total dikes, Arkansas River ... 
LOWER RED RIVER 
Standard revetment: 
Long Lake, LA .............. 
Naples, LA .................. 
Turnbill Island, LA .......... 
Total standard revetment 
Dikes: 
None 
RED RIVER6 
Standard revetment:7 
Dupre, LA .................. 
Bringol, LA ................. 
Egg Bend,LA ................ 
Cologne Bend, LA ........... 
Roxana, LA ................. 
Ryland, LA ................. 
Whittington, LA ............. 
Smith, LA ................... 
Latanier, LA ................ 
Hudson, LA .................. 
Robert, LA .................. 
Alexandria Front, LA ....... 
Callahan, LA ................ 
Cotton, LA .................. 
Rapides, LA ................. 
Boyce, LA ................... 
Total standard revetment, 
Red River ................... 
Below Confluence 
of Old and 
Mississippi 
Rivers 
10
79 
69 
73 
75 
77 
83 
88 
89 
91 
93 
99 
102 
105 
110 
116 
119 
125 
RRL 
RRRRRRRR
RRRRRRRR 
- - - - - - - 6,652 
- - - - - - - 6,190 
- - - - - - - 6,815 
- - - - - - - 19,657 
(3.72 Miles) 
- - - - - - - 2,690 
- - - - - - - 4,000 
- - - - - - - 2,400 
- - - - - - - 650 
- - - - - - - 3,325 
- - - - - - - 3,925 
- - - - - - - 2,900 
- - - - - - - 2,700 
- - - - - - - 2,460 
- - - - - - - 1,458 
- - - - - - - 5,500 
- - - - - - - 5,280 
- - - - - - - 4,000 
- - - - - - - 14,700 
- - - - - - - 1,030 
- - - - - - - 4,548 
- - - - - - - 61,566 
(11.66 Miles) 
Miles 
Above 
Mouth 
LRLR 
31 
34 
36 
24 
30 
36 
39 
RL 
R 
11,770 
11,720 
5,250 
2,800 
31,540 
(5.97 Miles) 
1,848 
3,658 
2,187 
7,693 
(1.46 Miles) 
Ct 
C12 
C, 
C
07 z

TABLE 42-I 
(Continued) 
BANK REVETMENTS AND DIKES: VICKSBURG DISTRICT 
(FISCAL YEAR 1983) 
Operations This FY 
Construction .erative Nonop- Otpievrea- 
Above New Work Reinforcement Since Thru 
Head Bank Exten- Prior This 
Location of R sion Lap Mainte- FY FY 
(PMasilseess) oLr (LFieneeta) r (LFieneeta) r (Linear nance (Linear (Linear (Squares)' Feet) (Squares)1 (Squares) Feet) Feet) 
RED RIVER' 
continued 
Dikes?: 
Choctaw Bayou Bend, LA ..... 71 R - - - - - - - 2,000 
Bringol(Egg Bend), LA ....... 73 R - - - - - 2,477 
EggBend,LA ................ 75 R - - - - - - - 900 
Cologne Bend, LA ............ 77 R - - - - - - - 1,850 
Echo, LA .................... 78 R - - - - - - - 1,900 
Richardson, LA .............. 79 R - - - - - - - 2,700 
Alexandria, LA ............. 105 R - - - - - - (Rock groin) 270 
Bertrand, LA ................ 122 R - - - - - - - 7,630 
Total dikes, Red River ......- - - - - - - 19,727 
(3.74 Miles) 
1. Gross squares articulated concrete mattress (100 
square feet). 
2. Contains 7,814 linear feet of trenchfill revetment 
(stone). 
3. Linear feet of dike on which repairs were made. 
4. Changed to correct previous errors. 
5. See report on Arkansas River and tributaries, AR and 
OK, under Little Rock District. 
6. Mileages based on 1967 hydrographic survey. 
7. Includes all types of dikes and retards.

TABLE 42-J BANK REVETMENTS AND DIKES: MEMPHIS DISTRICT 
(FISCAL YEAR 1983) 
Operations This FY 
Construction Non Ue- 
Above New Work Reinforcement Sine T 
Head Bank Exten- Prior This 
Location Paosfs es oRr (Lsiinonea r Lap Mainte- FY FY (Linear (Linear nance (Linear (inear 
(Miles) L Feet) Feet) (Squares)' Feet) (Squares)' (Squares) Feet) Feet) 
MISSISSIPPI RIVER 
Standard revetment: 
Big Island, AR ............... 598 R - - - - - - - 3,905 
Scrubgrass Bend, AR ......... 600 R - - - - - - 7,315 
Henrico, AR ................. 606 R - - - - - - - 25,040 
Cessions Towhead, AR ........ 615 L - - - - - - - 10,615 
Knowlton, AR ................ 620 R - - - - - 3,412 - 16,900 
Island 67, MS .............. 621 L - - - - - - - 7,625 
Island 68 Bar, AR ........... 622 R - - - - - - - 6,445 
Ludlow, AR ................. 626 R - - - - - - - 10,390 
Rescue Landing, AR-MS ...... 629 L - - - - - - - 27,020 
Fair Landing, AR ............ 632 R 1,800 143 4,154 - - 6,747 - 25,690 
Burke Landing, MS .......... 637 L - - - - - - - 19,070 
Island 62, AR ................ 638 R - - - - - - - 9,030 
Island 63, MS ................ 639 L - - - - - - - 11,454 
Island 63 Bar, MS ........... 639 L - - - - - - - 3,795 
Oldtown Bend, AR ........... 644 R - - - - - 5,853 - 25,995 
Horseshoe, MS ............. 647 L - - - - - - - 16,385 
Westover, AR ................ 650 R - - - - - - - 12,730 
Delta-Friars Point, MS ....... 655 L - - - - - - - 30,090 
Helena, AR................. 660 R - - - - - - - 36,460 
Trotters Landing, MS ......... 665 L - - - - - - - 32,905 
Flower Lake, MS ............ 667 L - - - - - 2,443 - 16,385 
St. Francis, AR ............. 672 R - - - - - - - 24,663 
Harbert Point, MS ........... 675 L - - - - - - - 9,065 
Walnut Bend, AR ............. 680 R - - - - - - - 27,220 
Mhoon Bend, MS ............ 685 L - - - - - - - 35,828 
Peters, AR .................. 692 R - - - - - 2,188 - 23,675 
Commerce, MS ............. 695 L - - - - - - - 11,615 
Porter Lake, AR .............. 700 R - - - - - - - 34,155 
Pickett, MS-AR ............. 703 R - - - - - - - 12,575 
Norfolk-Star, MS ............ 709 L - - - - - 3,326 - 35,582 
Cow Island Bend, AR ......... 714 R - - - - - - - 22,274 
Cow Island Bend (Upper), 
TN ....................... 716 R - - - - - 6,853 
Coahoma, TN ................ 717 L - - - - - - -9,270 
Ensley, TN .................. 723 L - - - - - - 36,566 
Dismal Point, AR ............. 724 R - - - - - - 7,200 
Bauxippi-Wyanoke, AR ....... 730 R 1,230 - - - - - 24,530 
Presidents Island, TN ......... 733 L - - - - - - 12,755 
Hopefield Point, AR, TN ...... 736 R - - - - - - - 5,390 
Loosahatchie-Memphis, TN ... 737 L - - - - - - 31,293 
Loosahatchie Bar, TN ......... 740 R - - - - - - 2,070 
St. Clair, AR ................. 742 R - - - - - - 2,930 
Island 40, TN-AR ............. 744 R .n 2,312 - 30,750 
1U, 
r, 
1 i 
0

TABLE 42-J BANK REVETMENTS AND DIKES: MEMPHIS DISTRICT 
(Continued) (FISCAL YEAR 1983) 
OpeCroantisotnrus cTthioisn FY Nonop- Opera- 
Construcerative tive 
Above New Work Reinforcement Since Thru 
Head Bank Exten- Prior This 
Location of R sion Lap Mainte- FY FY 
Passes or (Linear (Linear (Linear nance (Linear (Linear 
(Miles) L Feet) Feet) (Squares)1 Feet) (Squares)' (Squares) Feet) Feet) 
MISSISSIPPI RIVER 
continued 
Standard Revetment: 
Brandywine, AR-TN ......... 750 R - - - . - - -18,010 
Shelby Forest, TN ........... 753 L - - - - - - 9,550 
Dean Island, AR .............. 756 R - - - - - - 7,555 
Cedar Point-Densford, TN .... 759 L - - - - - - 20,190 
Chute of Island 35, TN ........ 764 R - - - - - - 29,190 
Lookout Bar, TN ............ 772 R - - - - - 2,990 
Lookout, TN ................. 774 R - - - - - - 5,005 
Sunrise Towhead, TN ......... 776 R - - - - - 2,226 - 14,615 
Lower Bullerton, AR ......... 782 R ....... 28,350 
Kate Aubrey Towhead- 
Island 30, TN ............... 786 R - - - - - 2,667 - 28,658 
Oseeola, AR ................ 786 R ....... 1,3503 
Osceola, AR ................. 786 R - - - - - - 5,823 
Ashport-Keyes Point, TN ...... 791 L - - - - - - 44,232 
Kate Aubrey, TN ............ 793 R - - - - - - 2,500 
Island 26, TN ................ 798 R - - - - - - 15,690 
Bend of Island 25, TN ......... 803 L - - - - - 22,730 
Barfield, AR ................. 808 R - - - - - 44,040 
Obion-Tamm, TN ............. 819 L - - - - - - 49,831 
Huffman-Hickman, AR-TN ... 826 R - - - - - - 26,984 
Heloise, TN ................. 831 L - - - - - - 12,935 
Island 18, MO ................ 836 R - - - - - - 22,170 
Linwood Bend, TN ........... 841 L - - - - - - 14,850 
Blaker Towhead, TN ......... 845 L - - - - - 5,952 - 17,087 
Bells Point, MO .............. 845 R - - - - - 5,420 
Gayoso-Caruthersville, MO .... 848 R - - - - - 25,600 
Island 15, TN ................ 851 L - - - - - - 3,630 
Hathaway Landing, TN ....... 852 L - - - - - - 1,000 
Robinson Bayou, MO.......... 852 R - - - - - - 22,630 
Fritz Landing, TN ............ 857 L - - - - - 3,325 - 15,670 
Lee Towhead, MO ..... 859 L ....... 8,470 
Bend of Island 14, TN ......... 859 L - - - - - 12,050 
Above Lee Towhead, TN ...... 861 L - - - - - 4,943 
Little Cypress, MO ........... 864 R - - - - - 32,240 
Merriwether-Cherokee, TN ... 869 L - - - - - - 41,058 
Linda, MO ................... 876 R - - - - - - 11,950 
Below Toney's Towhead, TN ... 879 L - - - - - - 20,895 
New Madrid Bend, MO ....... 886 R - - - - - - 30,348 
Kentucky Point, KY .......... 887 L - - - - - - 7,960 
New Madrid Bar, KY ......... 888 R - - - - - - 15,375 
New Madrid, MO ............. 889 R -. 5,559

La Forge, MO ................ 
Slough Landing Neck, 
TN-KY .................... 
Winchester Towhead, MO ..... 
Island 9, KY-TN ............. 
Milton Bell, MO ............. 
Chute of Island 8, KY ........ 
Bend of Island 8, MO ......... 
Island 8, KY ................. 
Hickman-Reelfoot, KY ....... 
Beckwith Bend, MO ......... 
Williams, KY ............... 
Wolf Island, KY ............. 
Columbus, KY ............... 
Belmont, MO ................ 
Island 3 and 4, KY ........... 
Campbell, KY ............... 
Pritchard, MO ............... 
Mayfield Creek, KY .......... 
Wickliffe, KY ................ 
Cache-Cairo, IL (Ohio River) .. 
Total revetment, 
Memphis District 
Mississippi River ........ 
Dikes: 
Henrico, AR ................. 
Below Knowlton, AR ......... 
Island 67, MS ............... 
Below Ludlow, AR ........... 
Sunflower, AR .............. 
Island 64, AR ................ 
Island 62, AR ................ 
Island 63 Bar, MS ........... 
Island 63, MS ............... 
Kangaroo Point, AR ......... 
Friars Point, MS ............ 
Montezuma Bar, MS ......... 
Montezuma Towhead, AR ..... 
Prairie Point, AR ............. 
St. Francis Towhead, MS ..... 
Below Walnut Bend, AR ...... 
Bordeaux Point, MS ......... 
Commerce, MS .............. 
Basket Bar, AR .............. 
Buck Island, MS ............. 
Porter Lake, AR ............. 
Pickett, MS ................. 
Seyppel, AR ................. 
CatIsland, AR .............. 
Coahoma, TN ............... 
Armstrong, AR-TN .......... 
Dismal Point, AR ............ 
Hopefield Point, AR ......... 
892 
899 
900 
905 
908 
913 
914 
914 
919 
924 
927 
934 
937 
938 
940 
943 
948 
949 
953 
958 
R
L
RL
RL
RRL
RL
RL
RRL
RLL 
R 
- - - - - 2,003 - 
3,030 143 4,154 0 42,454 
(5) 
603 
616 
621 
624 
627 
630 
638 
639 
640 
649 
652 
657 
656 
668 
671 
676 
681 
694 
696 
700 
701 
704 
706 
710 
718 
720 
724 
736 
RRLRLRRLLRLL
RRL
RLL
RL
RL 
R
RL
RRR 
20,680 
32,940 
5,540 
33,5854 
14,375 
12,620 
9,800 
13,175 
41,909 
14,588 
10,015 
19,205 
3,825 
5,785 
19,970 
6,865 
15,045 
5,935 
8,455 
26,152 
0 1,791,100 
(339.2 Miles) 
(6) 
4,700 
235 
6,310 
10,233 
4,320 
5,040 
5,520 
7,330 
23,180 
2,600 
5,640 
5,730 
6,870 
12,430 
3,450 
10,101 
3,380 
6,420 
4,920 
5,700 
5,060 
4,890 
7,930 
7,180 
11,640 
15,590 
4,640 
18,690 
22,170 
1,330 
M', 
C', 
J2, 
1-I 
0z

TABLE 42-J BANK REVETMENTS AND DIKES: MEMPHIS DISTRICT 
(Continued) (FISCAL YEAR 1983) 
Operations This FY 
Construction Nne ra- 
Above New Work Reinforcement Since Thru 
Head Bank Exten- Prior This 
Location Paosfs es oRr (Lsiinonea r (LLinaepa r Mainte- FY FY (Linear nance (Linear (Linear 
(Miles) L Feet) Feet) (Squares)1 Feet) (Squares) (Squares) Feet) Feet) 
MISSISSIPPI RIVER 
continued 
Dikes: 
Robinson Crusoe, TN ......... 738 R - - - - - 40 - 21939 
Loosahatchie Bar, TN ......... 739 R - - - - - 3,950 
Above Loosahatchie, TN ...... 742 L - - - - - - 8,990 
Redman Point, AR ............ 743 R - - - - - 850 - 7,750 
Randolph Point, TN .......... 747 L - - - - - - 16,740 
Poker Point, AR .............. 748 R - - - - - - 8,050 
Corona Bar, TN-AR .......... 755 R - - - - - - 8,430 
Densford, TN ................ 757 L - - - - - 2,000 - 7,780 
Cedar Point, TN ............ 759 L .. - - 2,890 
Below Richardson Landing, 
TN ....................... 767 L - - - - - - 5,950 
Lookout, TN-AR .............. 771 R - - - - - - 5,538 
Plum Point, TN ............. 784 L 2,050 - - - - - - 7,910 
Kate Aubrey, TN ............ 791 R - - - - - - 11,270 
Keyes Point, TN .............. 791 L 5,610 - - - - - - 19,755 
Ashport-Goldust, TN-AR ...... 795 R - - - - - - 17,330 
Forked Deer, TN ............. 798 L - - - - - 8,550 
Island 25, AR ................ 804 R - - 80-5,450 - -800 
Nebraska Point, TN .......... 808 L ..... 3,000 - 12,149 
Below Tamm Bend, TN ....... 813 L ....... 8,300 
Wrights Point, AR ........... 820 R - - - - - - 30,505 
Island 21, Chute, TN .......... 824 L - - - - - - 3,170 
Head of Island 21, TN ......... 828 L - - - - - 1,180 - 5,460 
Island 20, MO-TN ........... 831 R ....... 18,139 
Island 18, TN ................ 837 L - - - - - - 5,395 
Tennemo, TN ................ 842 L - - - - - - 2,505 
Caruthersville-Linwood 
Bend, MO .................. 844 R - - - - - 1,000 - 25,877 
Sandy Hook, TN .............. 850 R - - - - - - - 2,350 
Island 15, TN ............... 851 L - - - - - 125 - 7,016 
Robinson Bayou, MO ......... 853 R ..... 1,200 - 9,890 
Hathaway, TN ............. 854 L ....... 15,620 
Island 15 Neck, TN ........... 854 L ..... 8,900 - 21,100 
Above Lee Towhead, TN ...... 859 L ....... 1,300 
Below Cherokee, TN ......... 866 L - - - - - 6,230 
Stewart Towhead, MO ........ 871 R - - - - - - 18,290 
Ruddles Point, MO ........... 874 R - - - - - - 8,130 
Kentucky Point, KY .......... 887 L - - - - - - - 11,550 
Morrison Towhead, MO ....... 890 R - - - - - - 1,070 
0
0O
y
x
0
0
i z
tC

Below Island 9, TN ........... 
Donaldson Point, MO ......... 
Island 9, KY ................. 
Campbell, KY ............... 
Pritchard, MO............... 
Island 1, KY .................. 
Total dikes, 
Memphis District, 
Mississippi River ......... 
1. Gross squares-articulated concrete mattress (100 
square feet). 
2. Lumber mattress revetment 
3. Rock groins. 
4. Stone mipni le dike. 
5. Linear feet of dike on which repairs were made. 
6. Linear feet of triangular frame retards and pile dikes. 
901 12,582 
905 
906 
942 
944 
948 
L
RLL 
RL 
20,242 
(3.8 Miles) 
12,582 
8,320 
7,010* 
2,610 
9,390 
15,260 
23,795 665,784 
(126.1 Miles) 
r
C2 
0
CD, 
CD) 
z

TABLE 42-K PROJECT LEVEES: NEW ORLEANS DISTRICT 
(FISCAL YEAR 1983) 
Levees and Floodwalls Berms (Miles) Surfaced Roads on Levees 
(Miles) (Miles) 
Built to Approved Total 
Location Total Grade and Section In In Com- 
In Total System Com- Sstem pete 
Authorized Place Thru When Built plete en Built 
for This This This Com- This This Com- This This 
System FY FY FY pleted1 FY FY pleted FY FY 
MISSISSIPPI RIVER 
Fifth Louisiana Levee District .......... 
Levees ............................. 
Floodwalls .......................... 
Old River structures and levees ....... 
Atchafalaya Basin Levee District ....... 
Levees ............................. 
Floodwalls .......................... 
Morganza structure and levee ....... 
Morganza forebay levee ............. 
Port Allen lock ..................... 
Lafourche Basin Levee District ........ 
Levees ............................. 
Plaquemines West Levee District ....... 
Levees ............................. 
Floodwalls ......................... 
Buras Levee District ................... 
Levees ............................. 
Floodwalls ......................... 
Empire lock ........................ 
Baton Rouge front levees ............... 
Pontchartrain Levee District ........... 
Levees ............................. 
Floodwalls ......................... 
Bonnet Carre guide levees ............ 
Bonnet Carr6 forebay levee ........... 
Bonnet Carre structure .............. 
East Jefferson Levee District ........... 
Levees ............................. 
Floodwalls ......................... 
West Jefferson Levee District ........... 
Levees ............................. 
Floodwalls ......................... 
Harvey Canal Lock ................. 
Orleans Levee District ................. 
Left descending, east bank 
Levees ............................. 
Floodwalls ......................... 
IHNC lock ......................... 
(16.8) 
15.5 
1.3 
(126.3) 
118.7 
0.8 
6.7 
0.1 
(61.7) 
61.7 
(37.9) 
37.9 
(34.1) 
34.0 
0.1 
(2.1) 
(124.9) 
110.8 
11.3 
1.3 
1.5 
(11.6) 
11.6 
(20.0) 
19.8 
0.1 
0.1 
(27.2) 
4.6 
8.6 
0.1 
(16.8) 
15.5 
1.3 
(126.3) 
118.7 
0.8 
6.7 
0.1 
(61.7) 
61.7 
(37.9) 
37.9 
(34.1) 
34.0 
0.1 
(2.1) 
(124.9) 
110.8 
11.3 
1.3 
1.5 
(11.6) 
11.6 
(20.0) 
19.8 
0.1 
0.1 
(27.2) 
4.6 
8.6 
0.1 
(2.3) 
2.3 
(9.3) 
9.3 
(-) 
(3.0) 
3.0 
(-) 
(-) 
(-) 
(-) 
(-) 
(0.1) 
(9.6) 
8.3 
1.3 
(85.4) 
77.8 
0.8 
6.7 
0.1 
(24.1) 
24.1 
(25.8) 
25.8 
(19.7) 
19.7 
(0.9) 
(81.9) 
67.8 
11.3 
1.3 
1.5 
(8.8) 
8.8 
(4.5) 
4.3 
0.1 
0.1 
(16.5) 
(-) 
(5.3) 
5.3 
(0.1) 
0.1 
(-) 
(-) 
(-) 
(4.7) 
4.7 
(-) 
(-) 
(-) 
(-) 
(-) 
(-) 
(-) 
(-) 
(-) 
(-) 
(-) 
(-) 
(-) 
(-) (15.5) 
- 15.5 
(1.0) (118.7) 
1.0 118.7 
(0.1) (61.7) 
0.1 61.7 
(-) (37.9) 
- 37.9 
(-) (34.0) 
- 34.0 
(-) (2.1) 
(-) (110.8) 
- 110.8 
(-) (11.6) 
- 11.6 
(-) (19.9) 
- 19.8 
- 0.1 
(-) (18.4) 
2.3 
2.3 
0.1 
4.6 
(-) 
(-) 
(-) 
(-) 
(-) 
(-) 
(-) 
(-) 
(-) 
(-) 
(15.5) 
15.5 
(118.7) 
118.7 
(61.7) 
61.7 
(37.9) 
37.9 
(34.0) 
34.0 
(2.1) 
(110.8) 
110.8 
(11.6) 
11.6 
(19.9) 
19.8 
0.1 
(18.4) 
4.6

Right descending, west bank 
Levees ............................. 
Floodwalls ......................... 
Algiers Canal lock ................... 
Lake Borgne Basin Levee District ....... 
Levees ............................. 
Floodwalls ......................... 
Grand Prairie Levee District ........... 
Levees ............................. 
Floodwalls ......................... 
Total Mississippi River .......... 
ATCHAFALAYA BASIN FLOODWAY 
Atchafalaya River and 
Bayou des Glaises ..................... 
East bank Atchafalaya River ........ 
Bayou des Glaises ................... 
West bank Atchafalaya River ........ 
Simmesport Ring ................... 
Melville Ring ....................... 
Krotz Springs Ring ................. 
Mansura Hills to Hamburg .......... 
West protection levee, Hamburg to Berwick 
drainage canal via Calumet ....... 
Levees west of Berwick, Berwick drainage 
canal to Charenton drainage canal ..... 
Morganza upper guide levee ........... 
East protection levee, Morganza to Cutoff 
Bayou, including 19.5 miles of Morganza 
lower guide levee ..................... 
Total Atchafalaya Basin and 
Floodway .................... 
Total-Main Stem System ...... 
LAKE PONTCHARTRAIN, LA 
Lake Pontchartrain, LA ................ 
Item A levees ....................... 
Item B levees ....................... 
Item C levees ....................... 
Total .......................... 
13.8 
0.1 
(11.6) 
11.6 
(37.4) 
37.4 
511.6 
(148.4) 
52.5 
7.9 
60.1 
1.6 
4.1 
1.7 
20.5 
13.8 
0.1 
(11.6) 
11.6 
(37.4) 
37.4 
511.6 
(148.4) 
52.5 
7.9 
60.1 
1.6 
4.1 
1.7 
20.5 
(128.7) (128.7) 
(56.5) 
(8.9) 
(56.5) 
(8.9) 
0.1 
(-) 
(-) 
14.7 
11.7 
0.1 
(10.8) 
10.8 
(19.0) 
19.0 
307.02 
(-) (143.9) 
- 52.5 
- 7.9 
- 55.6 
- 1.6 
- 4.1 
- 1.7 
- 20.5 
(-) (66.3) 
(-) 
(-) 
(9.6) 
(8.9) 
(-) 
(-) 
10.1 
(-) 
(-) 
(-) 
(-) 
(-) 
(-) 
(-) 
(-) 
(-) 
(-) 
1.1 
(-) 
(-) 
(-) 
13.8 
(11.6) 
11.6 
(37.4) 
37.4 
479.6 
(148.4) 
52.5 
7.9 
60.1 
1.6 
4.1 
1.7 
20.5 
(56.5) 
(8.9) 
(-) 
(-) 
13.8 
(11.6) 
11.6 
(37.4) 
37.4 
479.6 
(-) (43.9) 
- 20.2 
- 12.0 
- 11.7 
(-) (66.3) 
(-) 
(-) 
(-) 
(8.9) C
C
z 
(106.7) (106.7) (-) (28.8) (-) (-) (-) (105.0) (-) (28.8) 
449.2 449.2 - 257.5 - - - 446.5 - 147.9 
960.8 960.8 14.7 564.5 10.1 - 1.1 926.1 - 627.5 
(17.4) (17.4) (-) (17.4) (-) (-) (-) (17.4) (-) (17.4) 
5.0 5.0 - 5.0 - - - 5.0 - 5.0 
10.1 10.1 - 10.1 - - - 10.1 - 10.1 
2.3 2.3 - 2.3 - - - 2.3 - 2.3 
17.4 17.4 - 17.4 - - - 17.4 - 17.4 
1. Figures indicate landside seepage berms only. 
2. Completed 14.7 miles in FY 83 minus 28.3 miles of 
previously constructed levees that have settled below design 
grade. 
3. Reflects results of flowline reanalysis. 
II 
(-) (-) (-) (127.7)

TABLE 42-L PROJECT LEVEES: VICKSBURG DISTRICT 
(FISCAL YEAR 1983) 
Levees and Floodwalls Berms (Miles)' Surfaced Roads on Levees 
(Miles) (Miles) 
Built to Approved Total 
Location Total Grade and Setion In In Com- 
In Total System Comrn- Systemp 
Authorized Place Thru When Built lete en Built ru 
for This This This Com- This Ihis Com- This This 
System FY FY FY2 pleted8 FY4 FY pleted FY FY 
MISSISSIPPI RIVER 
East bank in Mississippi ................ 178.35 178.3 - 109.1 158.9 - 108.1 168.4 - 168.4 
Greenville Harbor dikes ................ 7.8 7.8 - 7.8 - - - 
West bank in Arkansas ................ 75.6 75.6 - 42.9 51.1 - 46.4 75.4 - 75.4 
West bank in Louisiana 
(above Red River) ..................... 198.7 198.7 4.5 67.1 88.7 1.3 67.3 197.8 - 197.8 
Total Mississippi River ............. 460.4 460.4 4.5 226.9 298.7 1.3 221.8 442.5 - 442.5 
YAZOO RIVER BASIN 
Headwater ........................... 620.76 305.1 (-) 130.1 - - -620.7 (-) 281.5 
Backwater ........................... 96.6 44.6 - 0.0 - - - 96.6 - 39.0 
Total Yazoo River Basin ............ 717.3 349.7 (-) 130.1 - - -717.3 (-) 320.5 
ARKANSAS RIVER, ARKANSAS 
North bank ........................... 61.5' 56.2 - 56.2 8.3 - 8.3 47.4 - 47.4 
South bank ........................... 85.4 85.4 - 85.4 24.7 - 24.7 84.1 - 81.1 
Total Arkansas River .............. 146.9 141.6 - 141.6 33.0 - 33.0 131.5 - 128.5 
RED RIVER BACKWATER LEVEES 
Total Red River backwater ......... 263.6 156.5 - 81.38 - - - 249.0 - 141.9 
LOWER RED RIVER-SOUTH BANK 
RED RIVER 
Lower Red River-South Bank 
Red River levees ..................... (59.2) (59.2) (-) (49.2) (-) (-) (-) (59.2) (-) (42.8) 
Hotwells to Moncla, LA, levees ........ 59.2 59.2 - 49.2 - - - 59.2 - 42.8 
Floodwalls ....................... - - - - 
Total Lower Red River ............. 59.2 59.2 - 49.2 9.2 - 42.8 
1. This tabulation does not include riverside berms 
which are considered an integral part of the levee section. 
Riverside berms will be constructed along with levee enlargements 
or seepage berm contracts. 
2. Levee that has adequate freeboard based on the 
refined 1973 MR&T project flood flow line for the Mississippi 
River. Levees with more than 2 feet of freeboard are 
considered adequate. 
3. Subject to change as planning progresses. Does not 
include existing berms which need restudy. 
4. Based on refined 1973 MR&T project flood flow line. 
5. Includes 1.4 miles of concrete floodwall and 0.3 mile of 
levee on Vicksburg city front. 
6. Includes 33.1 miles of local protection works; 61.3 
miles along Whittington Auxiliary Channel; 210 miles in 
Upper Yazoo Projects; 156.1 miles along main stem; and 
160.2 miles on tributaries. 
7. Includes 5.3 miles for Gillett new levee. 
8. Revised to reflect 1973 project design flow line. 
9. Reflects results of flowline reanalysis. 
t j 
O
0
0
y
n
x
t i 
t0j 
1
N
NW~ 
w,

TABLE 42-M PROJECT LEVEES: MEMPHIS DISTRICT 
(FISCAL YEAR 1983) 
Levees and Floodwalls Berms (Miles)1 Surfaced Roads on Levees 
(Miles) (Miles) 
Built to Approved Total 
Location Total Grade andSetion In In Com- 
In Total System Com- System 
Authorized Place Thru When Built plete When Built 
for This This This Com- This Ths Com- This This 
System FY FY FY pleted' FY FY pleted FY FY 
MISSISSIPPI RIVER 
Mounds, IL ........................... 
Mound City, IL ........................ 
Cairo Drainage District ............... 
City of Cairo ........................... 
Little River Drainage District .......... 
Levee District No. 2, 
Scott County, MO ..................... 
Levee District No. 3, 
Mississippi County, MO ............... 
St. Johns Leveee and 
Drainage District .................... 
St. Francis Levee District of MO ........ 
City of Hickman, KY .................. 
Fulton County Levee District of 
Fulton County, KY .................... 
Reelfoot Levee District of Lake and 
Obion Counties, TN................... 
Madrid Bend Levee District ........... 
Lake Count Levee and 
Drainage District .................... 
Der County Levee and 
rainage District No. 1 ............... 
Tipton-Obion levee extension .......... 
St. Francis Levee District of AR ....... 
Helena Improvement District No.1 ..... 
Cotton Belt Levee District No. 1 ........ 
Laconia Drainage and Levee District 
Phillips County, AR .................. 
Laconia Levee District No. 1 of 
Desha County, AR ................... 
Laconia Circle Special Drainage 
District of Desha County, AR .......... 
Yazoo-Mississippi Delta Levee 
District ............................. 
New Madrid, MO, St. Johns 
Levee and Drainage District .......... 
3.9 
2.7 
13.82 
6.2 
19.3 
3.9 
2.7 
13.8 
6.2 
19.3 
13.8 13.8 
26.0 26.0 
58.73 
55.7 
1.4 
58.7 
55.7 
1.4 
16.7 16.7 
4.5 
9.6 
4.5 
9.6 
15.9 15.9 
21.3. 
6.5 
156.7 
5.3 
23.9 
21.3 
156.7 
5.3 
23.9 
3.9 
2.7 
13.8 
6.2 
19.3 
13.8 
26.0 
58.2 
55.7 
1.4 
0.3 
2.7 
7.8 
2.9 
8.0 
0.9 
2.4 
4.2 - 
3.6 
1.1 
8.5 
4.0 
19.3 
13.8 
4.9 3.2 26.0 
42.7 
10.6 10.4 
10.6 
0.3 
16.74 16.3 
4.54 
9.64 
15.9 
21.3 
153.24 
5.3 
23.9 
20.5 20.5 
18.1 
6.6 
18.1 
6.6 
20.5 
0.6 
7.3 
13.0 
94.6 
2.4 
13.4 
8.4 
18.14 12.1 
6.64 
93.6 93.6 93.6 
46.6 
55.1 
0.5 
16.3 
4.5 
9.6 
4.5 15.9 
79.9 
2.4 
13.4 
21.3 
6.5 
156.7 
4.7 
23.9 
8.4 20.5 
10.6 
85.7 85.7 
16.5 
93.6 
0.3 
3.6 
1.1 
8.5 
3.5 
19.3 
13.8 
26.0 
46.1 
55.1 
16.3 
M
1 
-
0
Hin 
-"1 
0P 
x 
4.3 
9.6 
15.9 
21.3 
156.7 
4.2 
23.9 
20.5 
16.5 
93.6 
0.3 0.3

TABLE 42-M 
(Continued) 
PROJECT LEVEES: MEMPHIS DISTRICT 
(FISCAL YEAR 1983) 
Levees and Floodwalls Berms (Miles)' Surfaced Roads on Levees 
(Miles)_ (Miles) 
Built to Approved Total 
Location Total Grade and Section In In Com- 
In Total System Comrn- System ete 
Authorized Place Thru When Built plete When Built ru 
for This This This Com- This This Com- This This 
System FY FY FY pleted' FY FY pleted FY FY 
MISSISSIPPI RIVER-continued 
Birds Point-New Madrid 
setback levee ......................... 35.3 35.3 - 35.3 35.3 - - 35.3 - 35.3 
Total Mississippi River ............. 636.3 629.5 - 625.5 373.5 - 232.7 604.1 - 595.1 
ST. FRANCIS RIVER 
East bank ............................ 159.5 156.2 - 156.2 - - - 156.7 - 81.7 
West bank ............................ 148.7 146.7 - 146.7 - - - 144.3 - 38.8 
Total St. Francis River ............. 308.2 302.9 - 302.9 - - - 301.0 - 120.5 
LITTLE RIVER 
East bank (left) ....................... 40.7 40.7 - 40.7 40.7 - 13.1 
West bank ............................ 35.1 35.1 - 35.1 - - - 35.1 - 23.7 
Elk Chute ............................. 39.9 39.9 - 39.9 - - - 39.7 - 17.3 
West Basin and middle valley ........... 14.4 14.4 - 14.4 - - - 13.4 - 13.4 
Total Little River ................. 130.1 130.1 - 130.1 - - - 128.9 - 67.5 
LOWER WHITE RIVER 
White River backwater levee ........... . 40.2 40.2 - 40.2 - - - 38.8 - 38.8 
Augusta to Clarendon ................. 49.2 39.5 - 39.5 - - - 49.2 - 36.2 
Clarendon levee ........................ 6.2 6.2 - 4.4 - - - 
Total Lower White River ........... 95.6 85.9 - 84.1 - - - 88.0 - 75.0 
MEMPHIS HARBOR 
Memphis Harbor ..................... 10.5 10.5 - 10.5 7.0 - 1.5 10.5 - 10.5 
1. Subject to change as planning progresses. 
2. Includes 5.1 miles of Cache River levee. This levee was 
enlarged to 1928 grades with Federal funds, but since that 
time has been classified as a secondary levee. 
3. Includes 12.1 miles of Farrenburg levee. This levee 
was enlarged to 1928 grades with Federal funds, but since 
that time has been classified as a secondary levee. 
4. Shown complete. Authority MSRC-ED-TL (MD 19 
Mar. 80)1st Ind. 21 Apr. 80. 
0
0
O
n 
0
z
O.sj 
0d

TABLE 42-N 
RECAPITULATION 
PROJECT LEVEE TABLES 42-K, -L, AND -M 
(FISCAL YEAR 1983) 
Levees and Floodwalls Berms (Miles) Surfaced Roads on Levees 
(Miles)_ (Miles) 
Built to Approved Total 
Location Total Grade and Section In In Com- 
In Total System Comrn- System ete 
Authorized Place Thru When Built lete When Built ru 
for This This This Com- This hns Com- This This 
System FY FY FY pleted FY FY pleted FY FY 
MISSISSIPPI RIVERMAIN 
STEM 
New Orleans District, Table 42-K ....... 511.6 511.6 14.7 307.0 10.1 (-) 1.1 479.6 - 479.6 
Vicksburg District, Table 42-L ......... 460.4 460.4 4.5 226.9 298.7 1.3 221.8 442.5 - 442.5 
Memphis District, Table 42-M .......... 636.3 629.5 - 625.5 373.5 - 232.7 604.1 - 595.1 
Subtotal-Main Stem ................ 1,608.3 1,601.5 19.2 1,159.4 682.3 1.3 455.6 1,526.2 - 1,517.2 
TRIBUTARIES OFF MAIN STEM) 
INCLUDED IN MR&T SYSTEM 
Atchafalaya Basin 
Floodway-NOD .................... 449.2 449.2 - 257.5 - - - 446.5 - 147.9 
Lower Red River- 
South Bank-VXD ................... 59.2 59.2 - 49.2 - - - 59.2 (-) 42.8 
Arkansas River-South Bank-VXD ..... 85.4 85.4 - 85.4 24.7 - 24.7 84.1 - 81.1 
Subtotal-Tribs. in MR&T System .... 593.8 593.8 - 392.1 24.7 - 24.7 589.8 - 271.8 
Total in MR&T System ............. 2,202.1 2,195.3 19.2 1,551.5 707.0 1.3 480.3 2,116.0 - 1,789.0 
OTHER TRIBUTARIES IN 
MR&T PROJECT 
Lake Pontchartrain, LA,-NOD ........ 17.4 17.4 - 17.4 - - - 17.4 - 17.4 
Yazoo River Basin-VXD .............. 717.3 349.7 (-) 130.1 - - - 717.3 (-) 320.5 
Arkansas River-North Bank-VXD ..... 61.5 56.2 - 56.2 8.3 - 8.3 47.4 - 47.4 
Red River Backwater-VXD ........... 263.6 156.5 - 81.3 - - - 249.0 - 141.9 
St. Francis River-MD ................ 308.2 302.9 - 302.9 - - - 301.0 - 120.5 
Little River-MD ..................... 130.1 130.1 - 130.1 - - - 128.9 - 67.5 
Lower White River-MD ............... 95.6 85.9 - 84.1 - - - 88.0 - 75.0 
Memphis Harbor-MD ................. 10.5 10.5 - 10.5 7.0 - 1.5 10.5 - 10.5 
Subtotal-Other Tribs. in 
MR&T Project .................... 1,604.2 1,109.2 (-) 812.6 15.3 - 9.8 1,559.5 (-) 805.7 
Grand Total in Project ............ 3,806.3 3,304.5 19.2 2,364.1 722.3 1.3 490.1 3,675.5 - 2,594.7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 42-0 CHANNEL IMPROVEMENTS: NEW ORLEANS DISTRICT 
(FISCAL YEAR 1983) 
In Total 
System Complete 
Year When Built Thru 
Location Initi- Comrn- This This Percent 
ated pleted FY FY Complete 
(Miles) 
Bayou des Glaise diversion channel ................. 1938 6.0 - 6.0 100 
Bayous Rapides, Boeuf, and Cocodrie ............... 1946 92.6 - 63.4 75 
Charenton drainage and navigation canal ........... 1939 6.3 - 6.3 100 
Wax Lake Outlet ................................. 1938 15.7 - 15.7 100 
Atchafalaya Basin Floodway ...................... 1933 244.2 - 186.4 49 
Morganza Floodway ............................... 1941 3.3 - 3.3 100 
Old River outflow channel ......................... 1956 8.3 - 7.4 89 
Old River inflow channel.......................... 1960 2.3 - 0.4 17 
Old River lock approach channels ................. 1961 2.2 - 2.2 100 
Baton Rouge Harbor (Devils Swamp) ............... 1958 2.5 - 2.5 100 
Eastern Rapides-S.C. Avoyelles .................... - 83.5 - - 
Teche-Vermillion Water Supply.................... - 6.3 - 6.3 100 
42-50

MISSISSIPPI RIVER COMMISSION 
TABLE 42-P CHANNEL IMPROVEMENTS: VICKSBURG DISTRICT 
(FISCAL YEAR 1983) 
In Total 
System Complete 
Year When Built Thru 
Location Initi- Comrn- This This Percent 
ated pleted FY FY Complete 
(Miles) 
BIG SUNFLOWER RIVER, ETC., MS 
Big Sunflower River .............................. 1947 199.1 - 199.1 100 
Quiver River ..................................... 1947 69.6 - 69.6 100 
Deer Creek ...................................... 1947 7.0 - 7.0 100 
Steele Bayou ..................................... 1947 54.9 - 54.9 100 
Steele Bayou 1 ..... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1965 71.2 - 51.6 50 
Main Canal ...................................... 1959 21.1 - 21.1 100 
Main Canal2 .... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . - 22.2 - -- 
Black Bayou ..................................... - 36.5 - - 
Big Sunflower River tributaries ................... 1957 227.2 - 227.2 100 
Quiver River tributaries .......................... 1960 35.4 - 35.4 100 
YAZOO BACKWATER 
Yazoo Backwater ................................ 1960 39.9 - 39.9 100 
YAZOO BASIN HEADWATER, MS 
Upper Yazoo Project ............................. 1976 179.0 - 40.3 22 
Coldwater River ................................. 1941 54.6 - 54.6 100 
Arkabutla Canal ................................. 1948 0.4 - 0.4 100 
Tallahatchie Canal ............................... 1940 74.8 - 73.5 85 
Little Tallahatchie River and 
Panola-Quitman Floodway ...................... 1939 48.0 - 48.0 100 
Greenwood protection works ...................... 1971 2.9 - 2.9 100 
Yacona River .................................... 1952 1.8 - 1.8 100 
Bobo Bayou ...................................... 1944 16.1 - 16.1 100 
Cassidy Bayou ................................... 1934 69.0 - 69.0 100 
Cassidy Bayou s ..... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . - 26.0 - - 
Bear Creek Diversion ............................. - 4.8 - - - 
Lake Cormorant ................................. - 20.9 - - 
Hurricane Bayou ................................. - 2.5 - - 
Opossum Bayou .................................. - 20.8 - - 
Abaica Creek .................................... - 7.7 - - 
Chicopa Creek .................................... - 7.0 - - 
Bear Creek ...................................... - 23.3 - - 
Rocky Bayou ..................................... - 7.8 - - 
Whiteoak Bayou .................................. - 55.9 - - 
Miscellaneous diteches ............................ - 12.3 - - 
Yalobusha River ................................. 1939 46.0 - 46.0 100 
Yazoo River ...................................... 1940 160.2 - 160.2 100 
Whittington Auxiliary Chanel ..................... 1956 30.8 - 30.8 100 
Tchula Lake ..................................... 1964 26.4 - 26.4 100 
David-Burrell Bayou ............................. 1957 40.4 - 40.4 100 
McKinney Bayou ................................. 1960 3.5 - 3.5 100 
Hillside Floodway ................................ 1964 11.0 - 11.0 100 
Yazoo City protection works ....................... 1953 1.6 - 1.6 100 
Ascalmore-Tippo Bayous ......................... 1975 29.8 - 15.1 50 
Alligator-Catfish Bayou .......................... 1973 8.3 - 8.2 99 
Pelucia Creek .................................... 1975 6.4 - 2.9 25 
BOEUF & TENSAS RIVERS, ETC., 
LA AND AR 
Bayou Lafourche .................................. 1949 45.3 - 45.3 100 
Bayou Lafourche4 .... . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1972 43.0 - 4.4 10 
Big & Colewa Creeks ............................. .. 1947 81.4 - 81.4 100 
42-51

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 42-P CHANNEL IMPROVEMENTS: VICKSBURG DISTRICT 
(Continued) (FISCAL YEAR 1983) 
In Total 
System Complete 
Year When Built Thru 
Location Initi- Comrn- This This Percent 
ated pleted FY FY Complete 
(Miles) 
BOEUF & TENSAS RIVERS, ETC., 
LA AND AR-continued 
Big & Colewa Creeks............................. 1965 86.8 - 51.5 60 
Tensas River ..................................... 1947 96.5 - 06.5 100 
Tensas River 6 ..... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1968 160.0 - 61.0 38 
Boeuf River, AR and LA .......................... 1953 103.9 - 103.9 100 
Fleschmans Bayou, AR ........................... 1963 6.6 - 6.6 100 
Caney Bayou, AR ................................. 1964 7.4 - 7.4 100 
Canal 18, AR ..................................... 1963 10.3 - 10.3 100 
Big Bayou, AR ................................... 1952 33.3 - 33.3 100 
Black Pond Slough, AR ........................... 1962 14.3 - 14.3 100 
Bayou Macon, AR and LA 1959 150.8 - 150.8 100 
Rush Bayou, AR .................................. 1964 6.7 - 6.7 100 
Canal 19, AR ..................................... 1957 50.2 - 50.2 100 
Canal 43, AR ..................................... 1956 34.5 - 34.5 100 
Canal 81, AR ..................................... 1957 32.7 - 32.7 100 
Mill Bayou-Bayou Vidal .......................... - 15.0 - - 
Kirsch Lake Canal ............................... - 9.3 - - 
Canal 19 Extension ............................... 1964 9.4 - 9.4 100 
Lake Chicot Pumping Plant ....................... - 2.5 - - 
RED RIVER BACKWATER, LA 
Tensas-Cocodrie Pumping Plant ................... 1976 6.9 - 6.0 85 
Six Mile Bayou, LA ............................... - 1.5 - - 
GRAND PRAIRIE, AR ........................... - 338.1 - - 
BAYOU METO, AR ............................... - 164.9 - - 
1. Includes further work on 54.9 miles and adds 16.3 
miles of channel to the project. 
2. Includes further work on 21.1 miles and adds 1.1 
miles of channel to the project. 
3. Includes further work on 26.0 miles. 
4. Includes further work on 38.6 miles and adds 4.4 
miles of channel to the project. 
5. Includes further work on 75.3 miles and 
miles of channel to the project. 
6. Includes further work on 96.5 miles and 
additional miles of channel to the project. 
42-52 
adds 11.5 
adds 63.5

MISSISSIPPI RIVER COMMISSION 
TABLE 42-Q CHANNEL IMPROVEMENTS: MEMPHIS DISTRICT 
(FISCAL YEAR 1983) 
In Total 
System Complete 
Year When Built Thru 
Location Initi- Corn- This This Percent 
ated pleted FY FY Complete 
(Miles) 
BIRDS POINT-NEW MADRID 
FLOODWAY 
Birds Point-New Madrid Intercepting Ditch 
Enlargement, Samos and Vicinity, MO ........... 1952 9.6 - 9.5 100 
ST. FRANCIS BASIN 
Little River Drainage, MO ....................... 1963 291.3 16.6 233.6 80 
St. Francis River, MO and AR ..................... 1953 602.7 10.1 363.9 60 
West Memphis Drainage, AR ..................... 1951 19.8 - 19.8 100 
Big Slough and Mayo Ditch, AR .................... 1960 28.0 - 28.0 100 
Tyronza River, AR ............................... 1939 12.7 - 12.7 100 
L'Anguille River, AR ............................. (1) 112.0 - - 
LOWER WHITE RIVER 
BASIN, AR 
Cache River Basin, AR ........................... 1972 231.5 - 7.2 3 
Big Creek and tributaries, AR ...................... (1) 103.8 - - 
WEST KENTUCKY TRIBUTARIES 
Obion Creek, KY ................................. (1) 41.7 - - 
WEST TENNESSEE TRIBUTARIES 
MS River, Western TN tributaries 
(Backwater Areas)(1946 Act) .................... 1952 34.3 - 34.3 100 
Obion River Diversion Channel, 
TN (1946 Act) .................................. (1) 9.3 - - 
Reelfoot Lake-Lake No. 9, KY 
and TN ........................................ 1974 15.8 - 3.0 19 
Running Reelfoot Bayou, TN ...................... 1955 19.7 - 19.7 100 
MS River Below Cape Girardeau; West 
TN tributaries. (1948 Act) ....................... 1961 225.0 - 84.8 38' 
Wolf River and tributaries, TN ..................... 1960 25.5 - 25.5 100 
1. Not started. 
42-53

TABLE 42-R 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
COSTS DURING FISCAL YEAR 1983 
Item Construction Maintenance Other 
FEDERAL FUNDS 
Flood control, Mississippi River and tributaries: 
St. Louis District: 
General investigations 
Advance engineering and design 
St. Francis Basin-Wappapello Lake 
Subtotal 
Memphis District: 
General investigations 
Advance engineering and design 
Mississippi River levees 
St. Francis Basin 
Lower White River 
Cache Basin, Ark. 
Channel improvement 
West Tennessee tributaries 
West Kentucky tributaries 
Inspection of completed works 
Mapping 
Recreation facilities-completed projects 
Reelfoot Lake No. 9, TN-KY 
Mud Lake, TN 
Subtotal 
Vicksburg District: 
General investigations 
Advance engineering and design 
Mississippi River levees 
Lower Arkansas River 
Tensas Basin 
Yazoo Basin 
Channel improvement 
Mapping 
Inspection of completed works 
Streambank erosion control 
Tensas National Wildlife Refuge, LA 
Lower Red River-South Bank Red River Levee 
Subtotal 
New Orleans District: 
General investigations 
Advance engineering and design 
Mississippi River levees 
Lower Red River 
Old River 
Bayou Cocodrie and tributaries 
Atchafalaya Basin 
Channel improvement 
Bonnet Carr 
Teche-Vermilion Basin water supply 
Inspection of completed works 
Mapping 
Major Rehabilitation Old River 
Subtotal 
Total Federal Funds 
$ 
611 
3,384,235 
6,953,760 
15,360 
19,838,355 
3,345,044 
6,796 
-- 
35,403 
9,032 
p 2,252,989 -- 
2,252,989 
2,252,989 
2,353,783 
4,733,835 
1,112,700 
23,439,894 
�-- 
85,767 
104,993 
-- 
$ 
1,702,330 
--= 
--_ 
33,588,646 31,830,972 1,702,330 
-- -- 2,210,347 
24,133 -- -- 
3,581,480 365,173 -- 
-- 113,921 -- 
18,794,173 1,512,276 -- 
21,583,860 16,065,520 -- 
20,417,588 11,272,589 -- 
-- 168,321 -- 
-- 59,105 -- 
(15,991) -- -- 
65,538 -- -- 
17,991 14,217 -- 
64,468,508 29,571,122 2,210,347 
-- -- 670,537 
71,583 -- -- 
12,462,063 3,698,280 -- 
2,568 788 -- 
34,047,117 6,192,267 -- 
93,034 67,659 -- 
20,039,136 5,194,145 -- 
38,361,287 10,976,835 -- 
-- 707,730 -- 
1,077,659 -- -- 
-- 136,875 -- 
-- 102,925 -- 
-- (18,385) -- 
106,154,447 27,059,119 670,537 
204,211,601 90,714,202 4,583,214 
42-54

TABLE 42-R 
(Continued) 
MISSISSIPPI RIVER COMMISSION 
COSTS DURING FISCAL YEAR 1983 
Item Construction Maintenance Other 
CONTRIBUTED FUNDS 
Memphis District: 
Lake Neark AR, Recreation Facility 296,065 -- -- 
New Orleans District: 
Old River -- 51,592 -- 
Mississippi River Levees -- -- -- 
Teche-Vermilion Basin -- -- -- 
Total Contributed Funds 296,065 51,592 -- 
Grand Total, Federal 
and Contributed Funds 204,507,666 90,765,794 4,583,214 
42-55

TABLE 42-S 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
STATEMENTS OF ALLOTMENTS AND ACCRUED 
EXPENDITURES FOR FLOOD CONTROL, 
MISSISSIPPI RIVER AND TRIBUTARIES, 
FROM MAY 15,1928, THROUGH SEP. 30,1983 
Unexpended 
Accrued Balance 
District or Installation and Class of Work Allotments Expenditures Sep. 30,1983 
ALLOTMENTS AND ACCRUED EXPENDITURES 
CHARGEABLE AGAINST FLOOD CONTROL 
ACT LIMITATIONS: 
COMPLETED WORKS: 
Waterways Experiment Station 
Office, Chief of Engineers 
Rock Island District: 
S. G. & O. prior to Aug. 18, 1941 
St. Louis District: 
S. G. & O. prior to Aug. 18, 1941 
Subtotal 
Memphis District: 
Des Arc, Ark. 
Contraction works 
DeValls Bluff, Ark. 
Mapping 
Memphis Harbor 
New Madrid Floodway 
Wolf River and tributaries 
Roads on levees (Mississippi River levees) 
S. G. & O. prior to Aug. 18, 1941 
Subtotal 
Vicksburg District: 
Boeuf Basin levees 
Channel realignment, Arkansas River 
Contraction works 
Eudora Floodway 
Vicksburg Harbor 
Greenville Harbor 
Grants Canal (Mississippi River levees) 
Mapping 
Jonesville, LA 
Roads on levees 
S. G. & O. prior to Aug. 18,1941 
Subtotal 
New Orleans District: 
Baton Rouge Harbor, LA 
Atchafalaya River and Basin, LA 
Bonnet Carre Spillway, LA 
Contraction works 
Mapping 
Roads on levees 
S. G. & O. prior to Aug. 18, 1941 
Wax Lake Outlet and Charenton Canal 
Morganza Floodway and structure 
Lake Pontchartrain 
Atchafalaya Basin, rights-of-way and flowage, 
Bayou des Glaises setback 
Subtotal 
All other completed items: 
Surveys under Sec. 10, Flood Control Act of 1928 
Impounded savings 
Plant transferred to revolving fund 
OCE (portion of allotment transferred to 
revolving fund, Washington Dist.) 
Subtotal 
Total completed works 
$ 874,000 
19,158 
14,010 
$ 874,000 
19,158 
14,010 
169,352 169,352 -- 
1,076,520 1,076,520 -- 
178,925 178,925 -- 
8,692,791 8,692,791 -- 
231,215 231,215 -- 
1,450,337 1,450,337 -- 
18,736,432 18,736,432 -- 
6,521,543 6,521,543 -- 
1,723,620 1,723,620 -- 
12,426 12,426 -- 
1,998,766 1,998,766 -- 
39,546,055 39,546,055 -- 
2,764,605 2,764,605 -- 
125,074 125,074 -- 
1,972,183 1,972,183 -- 
826,235 826,235 -- 
4,664,515 4,664,515 -- 
2,864,516 2,864,516 -- 
7,070 7,070 -- 
1,531,021 1,531,021 -- 
172,950 172,950 -- 
105,660 105,660 -- 
2,350,201 2,350,201 -- 
17,384,030 17,384,030 -- 
699,185 699,185 -- 
3,375,492 3,375,492 -- 
14,212,198 14,212,198 -- 
1,258,916 1,258,916 -- 
1,112,967 1,112,967 -- 
540,838 540,838 -- 
2,701,566 2,701,566 -- 
10,098,817 10,098,817 -- 
35,992,117 35,992,117 -- 
5,513,110 5,513,110 -- 
387,917 387,917 -- 
75,893,123 75,893,123 -- 
4,995,215 4,995,215 -- 
1,593,097 1,593,097 -- 
24,924,578 24,924,578 -- 
19,882 19,882 -- 
31,532,772 31,532,772 -- 
165,432,500 165,432,500 -- 
42-56

MISSISSIPPI RIVER COMMISSION 
TABLE 42-S 
(Continued) 
STATEMENTS OF ALLOTMENTS AND ACCRUED 
EXPENDITURES FOR FLOOD CONTROL, 
MISSISSIPPI RIVER AND TRIBUTARIES, 
FROM MAY 15, 1928, THROUGH SEP. 30, 1983 
Unexpended 
Accrued Balance 
District or Installation and Class of Work Allotments Expenditures Sep. 30,1983 
UNCOMPLETED WORKS: 
Rock Island District: 
Levees under Sec. 6, Flood Control Act of 1928 
St. Louis District: 
Levees under Sec. 6, Flood Control Act of 1928 
Subtotal 
Memphis District: 
Mississippi River levees 
Mississippi River levees 
New Madrid 
Channel improvement: 
Revetments 
Dredging 
Dikes 
Reelfoot Lake 
Reelfoot Lake, Lake No. 9, TN-KY 
St. Francis Basin: 
Wappapello Lake 
St. Francis River and tributaries 
Big Slough and Mayo ditch 
Little River drainage 
Lower White River: 
Clarendon Levee 
Augusta to Clarendon, AR 
White River backwater levee, AR 
Levees under Sec. 6, Flood Control Act of 1928 
West Tennessee tributaries 
Cache Basin, AR 
West Kentucky tributaries 
Mud Lake Pumping Station, TN 
Subtotal 
Vicksburg Distict: 
Mississippi River levees (excludes Grants Canal, 
$7,070, shown under completed works) 
Lower Arkansas River: 
North Bank 
South Bank 
Tensas Basin: 
Lake Chicot pumping plant 
Boeuf and Tensas Rivers, etc. 
Red River Backwater: 
Red River backwater levee, LA 
Tensas, Cocodrie pumping plant 
Lower Red River South Bank Red River Levees 
Tensas National Wildlife Refuge, LA 
Channel improvement: 
Revetments 
Dredging 
Dikes 
Levees under Sec. 6, Flood Control Act of 1928 
Yazoo Basin: 
Sardis Lake 
Enid Lake 
Arkabutla Lake 
Grenada Lake 
Greenwood 
Belzoni 
Yazoo City 
579,462 
1,897,980 
2,477,442 
147,251,354 
98,000 
310,284,307 
57,367,400 
98,990,000 
439,434 
7,865,000 
9,019,908 
174,253,382 
965,429 
44,462,892 
496,715 
1,779,846 
10,624,501 
108,651 
28,040,900 
7,910,000 
990,000 
157,000 
901,104,719 
179,238,990 
7,049,414 
15,676,286 
72,272,800 
39,965,200 
48,506,646 
39,969,300 
438,400 
9,900,000 
318,666,065 
23,549,260 
70,206,040 
958,175 
26,672,600 
21,307,400 
16,040,700 
45,240,900 
9,480,000 
316,656 
2,205,611 
579,462 
1,897,980 
2,477,442 
144,877,579 
98,000 
306,984,679 
57,189,565 
95,769,273 
439,434 
7,827,023 
9,019,908 
173,841,523 
965,429 
43,349,781 
496,715 
1,779,846 
10,624,501 
108,651 
27,085,620 
7,887,319 
973,144 
58,603 
889,376,593 
177,519,993 
7,049,414 
15,676,286 
70,382,633 
39,791,060 
46,995,125 
27,350,486 
17,727 
4,831,530 
304,787,869 
23,549,260 
69,043,336 
958,175 
26,459,069 
21,287,587 
16,015,596 
44,813,185 
8,325,510 
316,656 
2,205,611 
42-57 
2,373,775 
-- 
3,299,629 
177,835 
3,220,727 
37,977 
411,859 
1,113,111 
955,280 
22,681 
16,856 
98,397 
11,728,126 
1,718,997 
1,890,167 
174,140 
1,511,521 
12,618,814 
420,673 
5,068,470 
13,878,197 
1,162,704 
213,532 
19,813 
25,104 
427,715 
1,154,490 
--

TABLE 42-S 
(Continued) 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
STATEMENTS OF ALLOTMENTS AND ACCRUED 
EXPENDITURES FOR FLOOD CONTROL, 
MISSISSIPPI RIVER AND TRIBUTARIES, 
FROM MAY 15, 1928, THROUGH SEP. 30, 1983 
Unexpended 
Accrued Balance 
District or Installation and Class of Work Allotments Expenditures Sep. 30,1983 
Yazoo Basin: (Continued) 
Will M. Whittington auxiliary channel 
Big Sunflower, etc. 
Main Stem 
Upper Yazoo Projects 
Yazoo Basin-Tributaries 
Tributaries (Except Ascal-Tippo-Opossum Bayous) 
Tributaries-Bank Stabilization 
Ascalmore-Tippo-Opossum Bayous 
Yazoo Basin Backwater 
Yazoo Backwater (Except Muddy Bayou) 
Muddy Bayou 
Steambank Erosion Control, Eval. and Demo. 
Subtotal 
New Orleans District: 
Teche-Vermilion Basin Water Supply 
Bayou Cocodrie and Tributaries 
Channel improvement: 
Dredging 
Revetments 
Lower Red River (South Bank Levees) 
Levees Under Sec. 6, Flood Control Act of 1928 
Mississippi River Levees 
Atachafalaya Basin: 
Atachafalaya Basin Floodway 
Atachafalaya River Navigation 
Old River 
Subtotal 
TOTAL UNCOMPLETED WORKS 
ADVANCE ENGINEERING AND DESIGN 
(CONSTRUCTION) 
Memphis District: 
L'Anguille River Basin, AR 
Reelfoot Lake, Lake No. 9 
Cache River 
Big Creek and Tributaries, Lower White River 
Clarendon Levee, Lower White River 
West Kentucky Tributaries 
Mud Lake Pumping Station, TN 
Harris Fork Creek, KY & TN 
Subtotal 
Vicksburg District: 
Yazoo Basin, Big Sunflower River, Steele Bayou 
Tensas - National Wildlife Refuge, LA 
Subtotal 
New Orleans District: 
Mississippi Delta Region 
Teche Vermilion Basin-Water Supply 
East Rapides & S. Central Avoyelles Parishes 
Subtotal 
TOTAL ADVANCE ENGINEERING 
AND DESIGN 
TOTAL COMPLETED WORKS, UNCOMPLETED 
WORKS AND ADVANCE ENGINEERING 
AND DESIGN 
10,950,966 
32,010,300 
26,583,000 
39,727,006 
55,531,310 
612,484 
17,293,200 
51,209,200 
5,145,200 
14,793,000 
10,950,966 
29,084,931 
26,384,417 
35,062,418 
52,334,558 
612,484 
13,731,533 
51,051,294 
5,145,200 
14,747,512 
2,925,369 
198,583 
4,664,588 
3,196,752 
3,561,667 
157,906 
45,488 
1,201,516,109 1,146,481,419 55,034,690 
33,749,000 33,425,320 323,680 
4,289,008 4,250,374 38,634 
35,945,266 35,945,266 -- 
423,056,117 408,149,360 14,906,757 
18,056,600 18,056,600 -- 
200,680 200,680 -- 
171,596,000 170,077,199 1,518,801 
446,314,537 433,863,502 12,451,035 
303,463 303,463 -- 
137,716,000 135,028,126 2,687,874 
1,271,226,671 1,239,299,890 31,926,781 
3,376,324,941 3,277,635,344 98,689,597 
150,000 150,000 -- 
30,000 30,000 -- 
420,000 420,000 -- 
365,000 364,339 -- 
65,000 65,000 -- 
175,000 175,000 -- 
350,000 350,000 -- 
540,000 540,000 -- 
2,095,000 2,095,000 -- 
29,700 29,700 -- 
200,000 200,000 -- 
229,700 229,700 -- 
69,753 69,753 -- 
1,109,000 1,109,000 -- 
965,247 965,247 -- 
2,144,000 2,144,000 -- 
4,468,700 4,468,700 -- 
3,546,226,141 3,447,536,544 98,689,597 
42-58

MISSISSIPPI RIVER COMMISSION 
TABLE 42-S 
(Continued) 
STATEMENTS OF ALLOTMENTS AND ACCRUED 
EXPENDITURES FOR FLOOD CONTROL, 
MISSISSIPPI RIVER AND TRIBUTARIES, 
FROM MAY 15, 1928, THROUGH SEP. 30,1983 
Unexpended 
Accrued Balance 
District or Installation and Class of Work Allotments Expenditures Sep. 30,1983 
RECREATION FACILITIES-COMPLETED 
PROJECTS 
Eight-Year Program Funds 
St. Louis District: 
Wappapello Lake, MO 2,255,300 1,697,656 557,644 
Wappapello Lake, MO, Rockwood Landing 203,286 203,286 -- 
Subtotal 2,458,586 1,900,942 557,644 
Vicksburg District: 
Sardis Lake 1,584,339 1,584,339 -- 
Enid Lake 2,268,209 2,268,209 -- 
Arkabutla Lake 2,189,280 2,189,280 -- 
Grenada Lake 1,631,281 1,631,281 -- 
Subtotal 7,673,109 7,673,109 -- 
Total Eight-Year Program Funds 10,131,695 9,574,051 557,644 
Total chargeable against Flood Control 
Act Limitations excluding flood 
control emergencies 3,556,357,836 3,457,110,595 99,247,241 
Total maintenance since Aug. 18, 1941 1,290,048,855 1,264,696,107 25,352,748 
Total rehabilitation 31,113,000 31,113,000 -- 
Total flood control emergencies 14,900,300 14,900,300 -- 
Total general investigations 42,217,881 41,051,643 1,166,238 
Total flood control, MR&T appropriations 4,934,637,872 4,808,871,645 125,766,227 
Appropriations in addition to flood control, MR&T 
Other appropriations itemized in footnote (1), 
pp.2068-69, Annual Report for 1953 32,068,909 32,068,909 -- 
Grand total appropriated to Sep. 30, 1983 4,966,706,781 4,840,940,554 125,766,227 
Note: Preauthorization study costs chargeable to the MR&T authorization have been transferred to completed work.Costs 
not chargeable have been exluded from this report. 
TABLE 42-T STATEMENTS OF EXPENDITURES FOR LEVEES 
BY STATE AND LOCAL ORGANIZATIONS 
THROUGH DEC. 31,1983 
Engineer 
District Expenditures 
Rock Island 
St. Louis 
Memphis 
Vicksburg 
New Orleans 
Total 
$ 11,159,551 
67,700,481 
218,941,099 
113,576,836 
476,652,173 
$888,030,140 
42-59

TABLE 42-U 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
COST AND FINANCIAL STATEMENT1 
Total 
Project Funding FY 80 FY 81 FY 82 FY 83 Sep. 30,1983 
Mississippi River General investigations: 
and tributaries Alloted 3,090,000 3,720,000 5,315,000 4,271,000 42,217,8812 
(Regular Funds)1 Cost 3,185,080 4,101,537 4,158,386 4,583,214 41,051,644 
Construction (includes 
advance engineering 
and design): 
Alloted 134,796,000 140,644,000 179,793,000 289,370,000 3,505,837,422 
Cost 161,368,655 162,592,395 176,047,889 204,211,601 3,407,091,647 
Maintenance 
Alloted 67,837,000 79,794,000 78,290,000 109,548,000 1,340,427,406 
Cost 71,662,120 77,674,822 79,934,108 90,732,587 1,315,074,654 
Rehabilitations 
Alloted 4,500,000 8,150,000 600,000 137,000 31,113,000 
Cost 5,424,874 13,151,406 339,193 18,385 31,113,000 
Flood control emergencies 
(Maintenance): 
Alloted -- -- -- -- 14,885,922 
Cost -- -- -- -- 14,885,922 
(Contributed Funds) New Work: 
Contributed 193,871 53,201 40,736 393,600 9,199,166 
Cost 198,812 1,876 81,201 296,065 9,085,933 
Maintenance 
Contributed 427,594 54,930 169,852 125,424 1,756,840\ 
Cost 316,015 145,254 145,008 51,592 1,626,511 
1. Appropriations were as follows: 
Appropriations chargeable against Flood Control Act authorizations: 
Flood Control, MR&T except for emergencies (excludes Maintenance 
allotments Aug. 18, 1941, through Sep. 30, 1983): 
Net total allotted for works under Mississippi River Commission: 
Eight-Year Program Funds, Construction General: 
Surveys under Sec. 10, Flood Control Act of 1928 (not under MRC): 
Transferred to revolving fund: 
Impounded savings: 
Flood control emergencies: 
Net total alloted: 
Impounded savings: 
Additional funds not chargeable against Flood Control Act authorizations: 
Appropriations for Flood Control,MR&T, except for flood control emergencies: 
General investigations: 
Maintenance allotments Aug. 18, 1941, through Sep. 30, 1983 
Appropriations in addition to appropriations for Flood Control, MR&T 
(itemized in footnote (1), pp. 2068-69, Annual Report for 1953): 
Budgetary and OCE Reserves: 
Grand total: 
Reconciliation of appropriations and allotments: 
Total allotted to Sep. 30, 1983 
Transferred to revolving fund: 
Surveys under Sec. 10, Flood Control Act of 1928 (not under MRC): 
Impounded savings withdraiwn by Chief of Engineers: 
Budgetary and OCE Reserves: 
Total Appropriations to Sep. 30, 1983: 
Appropriations for past four reporting periods were as follows: 
FY 80: $210,223,000; FY 81: $232,308,000; FY 82: $262,798,000; 
and FY 83: $403,052,000. 
2. Totals for General Investigations include four projects transferred from 
Construction totals per DAEN-CWB-W, Aug. 4, 78, teletype. 
$3,545,806,370 
10,131,695 
4,995,215 
24,944,460 
1,593,097 
14,885,922 
14,378 
42,217,881 
1,290,048,885 
$3,587,470,837 
14,900,300 
1,332,266,736 
32,068,909 
4,966,706,782 
4,935,159,632 
24,944,460 
4,995,215 
1,607,475 
4,966,706,782 
42-60

NATURAL DISASTER PREPAREDNESS, 
RESPONSE AND RECOVERY ACTIVITIES 
Authority. Public Law 84-99, as amended, (Flood 
Control and Coastal Emergencies) provides authority for 
the Chief of Engineers to undertake disaster preparedness 
activities, flood fighting and rescue work, rehabilitation 
of flood control works damaged or destroyed by flood, 
protection or repair of Federally authorized shore protective 
works threatened or damaged by coastal storm, 
provision of emergency drinking water, and drought 
assistance. 
Activities. During FY 1983, disaster preparedness 
activities included the review and update of existing 
emergency response plans; development of required new 
plans; training of response personnel exercises to test 
plans, personnel and training; procurement and maintenance 
of critical supplies and equipment not readily 
available during initial response phase; maintenance 
and required upgrade of emergency operations centers; 
coordination with Federal, State and local response 
agencies and other public entities; and, overall management 
of the preparedness program. 
The Corps responded to widespread emergencies beginning 
with Hurricane Iwa which hit the Hawaiian 
Islands in November 1982. Subsequent responses were 
to the coastal storms which hit California beginning in 
December 1982; record flooding in Arkansas and Missouri 
in early December; near record flooding in Louisiana 
in late December; widespread major flooding in the 
Sacramento River, San Joaquin River and Tulare Lake 
basins in California; record lake levels on Utah Lake, 
Utah; major mudslides across the west; major flooding 
on the lower Mississippi River and its tributaries in April 
through June; record flooding on streams in southern 
Louisiana and Mississippi in April and major snowmelt 
flooding in Idaho, at Salt Lake City, Utah and along the 
Colorado River. Responses to smaller flood problems in 
other areas across the country also occurred. 
Recovery activities were also widespread. In the Mount 
St. Helens area, an interim pumping facility was placed 
in operation at Spirit Lake to alleviate the threat of catastrophic 
flooding; emergency temporary raises of the 
levees protecting the urban areas along the lower Cowlitz 
River were completed; and, a monitoring program 
continued throughout the year. Throughout California, 
major rehabilitation of damaged flood control projects 
(levees and channels) was undertaken. Major levee rehabilitation 
efforts were also undertaken along the 
lower Missouri River and its tributaries, along the Illinois 
River, along the middle Mississippi River, and along 
the Snake River in Idaho. Much of the work on rehabilitation 
projects continued past the end of the fiscal year. 
. For the status of the PL 84-99 Emergency Fund see 
Table 43. 
TABLE 43 
Status of the PL 84-99 Emergency Fund 
Unallocated Balance as of 30 Sep 82 
FY 1983 Appropriation 
FY 1983 Supplemental Appropriation 
Revocations, FY 1983 
Total Funds Available 
Allocations 
Disaster Preparedness 
Emergency Operations 
Rehabilitations 
Advance Measures 
Unallocated Balance as of 30 Sep 83 
$29,733,577 
29,877,000 
25,000,000 
7,049,129 
$91,659,706 
$ 7,316,900 
12,133,698 
19,355,173 
9,749,229 
$43,104,706 
43-1

CALIFORNIA DEBRIS COMMISSION 
This Commission, consisting of three Corps officers 
appointed by the President with the consent of the 
Senate, created by act of March 1, 1893 (27 Stat. L., p. 
507), was organized in San Francisco, CA, on June 8, 
1893, and has jurisdiction and duties extending over 
drainage area of Sacramento and San Joaquin Rivers, 
comprising great central valley of California and extending 
from crest of the Sierra Nevada on the east to that of 
the Coast Range on the west, and from Mount Shasta 
and Pit River Basin on the northto Tehachapi Mountains 
on the south. These rivers empty into head of Suisun 
Bay ultimately discharging into Pacific Ocean through 
connecting bays and straits and the Golden Gate. Duties 
of the Commission comprise regulation of hydraulic 
mining in drainage area of Sacramento and San Joaquin 
Rivers, CA, so that debris will not be carried into 
navigable waters or otherwise cause damage; jurisdiction 
over construction and control of water storage 
facilities for domestic, irrigation, and power development 
purposes; and direction of improvements for 
control of floods on Sacramento River. 
IMPROVEMENTS 
Navigation Page 
1. Regulation of hydraulic mining and 
preparation of plans ..................... 44-1 
2. Sacramento River and tributaries, CA 
(debris control) ........................... 44-2 
3. Treatment of Yuba River debris 
situation-restraining barriers, CA ........ 44-2 
Flood Control Page 
4. Sacramento River, CA .................... 44-3 
Tables 
Table 44-A Cost and Financial 
Table 44-B 
Statement ..................... 44-5 
Authorizing 
Legislation .................... 44-6 
Navigation 
1. REGULATION OF HYDRAULIC 
MINING AND PREPARATION 
OF PLANS 
Location. Operations largely limited to territory 
between Mount Lassen on the north and Yosemite 
Valley on the south, on western watershed of Sierra 
Nevada. (See Geological Survey sheets for the area, 25 
in number.) 
Existing project. Provides for regulating hydraulic 
mining operations, planning improvement of conditions 
upon Sacramento and San Joaquin Rivers and their 
tributaries affected by such operations, and preparation 
of plans to enable hydraulic mining to be resumed in 
their drainage areas. In addition, the Secretary of the 
Army is authorized to enter into contracts to supply 
storage for water and use of outlet facilities from 
debris-storage reservoirs for domestic and irrigation 
purposes and power development upon such conditions 
of delivery, use, and payment as he may approve. 
Applications of prospective miners are fully investigated 
by California Debris Commission and permits to operate 
are issued to those who provide satisfactory debrisrestraining 
basins by construction of suitable dams 
where necessary or agree to make payment for storage 
in Government-constructed debris-restraining reservoirs 
constructed under act of June 19,1934, as set forth 
below. For location and description of Governmentconstructed, 
debris-restraining reservoirs for general 
hydraulic mining, see Improvement 2. 
Local cooperation. Mineowners must bear all expenses 
incurred in complying with orders of the Commission 
for regulation of mining and restraint of debris. 
Operations and results during fiscal year. Minor 
administrative duties were accomplished. Administrative 
work overlaps that of improvements 2, 3, and 4, 
hereunder, and that of Sacramento District. 
Historical summary. The Commission received 1,292 
applications for hydraulic mining licenses; 1 mine is 
licensed, but does not use storage behind Government 
debris dams. Work remaining is, in general, continuation 
of above or similar operations. 
44-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
2. SACRAMENTO RIVER AND 
TRIBUTARIES, CA (DEBRIS 
CONTROL) 
Location. Project reservoirs are to be constructed in 
watersheds of Yuba, Bear, and American Rivers, CA 
(See Geological Survey sheets for basin areas, seven in 
number.) 
Existing project. For description of completed North 
Fork and Harry L. Englebright projects and authorizing 
act, see Annual Report for 1975. Initial recreation 
facilities were provided in FY 1959. Recreation areas at 
Harry L. Englebright Dam are maintained by the 
Corps. Recreation areas at North Fork Dam are no 
longer maintained and operated by Auburn Recreation 
Park and Parkway District, but have been turned over 
to the Bureau of Reclamation (known as the Water and 
Power Resources Service between November 6, 1979, 
and May 18, 1981) on a permit basis. Total Federal cost 
of new work for construction of these reservoirs was 
$4,646,872, including $40,000 and $25,000, respectively, 
for basic recreation facilities at Englebright Dam and 
North Fork Dam. Reservoir project sites on Middle 
Fork of American River and on Bear River have been 
deauthorized and excluded from foregoing cost. The 
90-day Congressional project review period, required 
by sec. 12, Public Law 93-251, as amended, ended 
August 5, 1977, and resulted in deauthorization of that 
portion of the project. Estimated cost of that portion is 
$1,820,000 (1935). 
Local cooperation. Fully complied with. Improvements 
made to facilities at North Fork Dam by Auburn 
Recreation Park and Parkway District under a lease 
agreement with the Secretary of the Army and Auburn 
Boat Clubs (concessionaire) at an estimated cost of 
$46,000 since September 1953. On March 1,1979, lands 
and waters at North Fork Dam were turned over to the 
Bureau of Reclamation on a 5-year renewable basis. 
Bureau will operate and maintain such use until Auburn 
project is completed, then a fee transfer will be made. 
Actual operation and maintenance of the recreation 
resourcei being done by State of California by contract 
with the Bureau. 
Licenses. Under provisions of Contract No. W-1105- 
eng-2998 with Pacific Gas and Electric Co., payment is 
to be made to the Federal Government of $18,000 per 
year for the first 30 years (December 29, 1942 through 
December 28, 1972) and $48,000 per year between 
December 29, 1972, and December 28, 1992, in return 
for use of head at Englebright Dam and generation of 
hydroelectric power. Total payment through September 
30, 1983, amounts to $1,038,393; these funds 
are paid to California Debris Commission and deposited 
for return to the Treasury. License No. 2246, effective 
April 9, 1970 (date New Narrows powerplant put in 
operation) was issued by Federal Power Commission 
(known as the Federal Energy Regulatory Commission 
since January 9, 1978) to Yuba County Water Agency 
for hydroelectric power development of Yuba River by 
the company upstream from Englebright Dam. Under 
provisions of Contract No. DA-04-167-CIVENG-66-95 
with Yuba County Water Agency, payment is to be 
made to the Federal Government of $100,000 per year 
for no more than 50 years. First payment (partial) of 
$73,151 was made April 1,1971; total payment through 
September 30, 1983, amounts to $1,273,151. These 
funds are paid to Sacramento District and deposited for 
return to the Treasury. 
Operations and results during fiscal year. New 
work: Maintenance: Maintenance and operation activities 
continued at North Fork Dam at a cost of $432; and 
at Harry L. Englebright Dam at a cost of $556,795, 
including recreation facilities. Dam safety assurance 
studies were continued at Englebright Dam at a fiscal 
year cost of $109,864. 
Historical summary. Construction of dams was 
initiated in 1937; North Fork project was completed 
and in use at end of FY 1939, and Harry L. Englebright 
project was completed in January 1941. The two debriscontrol 
structures are in good condition. Public use of 
these reservoir recreation areas greatly overtaxes present 
capacities. Dam safety assurance studies were 
initiated at Englebright Dam in FY 1981. 
3. TREATMENT OF YUBA RIVER 
DEBRIS SITUATIONRESTRAINING 
BARRIERS, CA 
Location. Works are on Yuba River between Marysville 
and where the river emerges from the foothills, 
near Hammonton, some 10 miles easterly from Marysville, 
or about 9 miles below the Narrows. (See Geological 
Survey Topographic map of Sacramento Valley, CA) 
Existing project. For description of completed project 
and authorizing act, see Annual Report for 1975. 
Total cost of new work was $723,259, of which $361,482 
was U.S. funds and $361,777 required contributed 
funds by State of California. (For details of project in its 
original form, see Annual Report, 1917, p. 1810.) In 
February 1963, center section of dam failed and major 
rehabilitation of structure was completed in December 
1964. Total cost for required rehabilitation was 
$1,660,000, of which $880,000 was Federal cost and 
$830,000 required contribution by State of California 
toward rehabilitation cost. During the December 24, 
1964, floodflows on the Yuba River, the rehabilitated 
Daguerre Point Dam sustained considerable damage. 
(See 1965 Annual Report, p. 1647 "Operations and 
results during fiscal year.") The reconstructed portion 
of the dam completed earlier in December 1964 was 
undamaged by the flood. Permanent repair of Daguerre 
Point Dam abutment and fish facilities was completed 
in October 1965 at a cost of $447,808 with Federal and 
required State contributed funds on a matching basis. 
Local cooperation. Fully complied with for new 
work and major rehabilitation work. Total first cost to 
local interests for new work was $361,777 (required 
44-2

CALIFORNIA DEBRIS COMMISSION 
contribution by State of California). In addition, training 
walls were built on each bank below Daguerre Point for 
11,250 feet and just above Daguerre Point, on the south 
bank, for 11,000 linear feet by two gold-dredging 
companies in connection with their dredging operations. 
To build these training walls would have cost the 
United States $450,000 (1902 estimate). Flood channels 
were also built by gold-dredging companies within 
confines of project works. Cost to the United States of 
equally effective works to restrain debris movement 
would have been more than $776,000 (1926 estimate). 
Total costs to local interests for initial and permanent 
major rehabilitation works were $830,000 from foregoing 
cost estimate. Estimated cost (July 1962) of these 
project units is $2,560,000 and $520,000, respectively, a 
total of $3,080,000 plus U.S. costs, for construction. and 
$223,904, respectively, (required contribution by State 
of California). State of California must contribute 
annually an amount equal to the Federal allotment for 
maintenance. 
Operations and results during fiscal year. Maintenance: 
Operations included condition and operation 
studies by hired labor; and bank protection, Yuba 
River, various locations upstream from Marysville 
completed by contract, $10,849. 
Historical summary. Construction of project works 
was initiated in November 1902. Construction of 
Daguerre Point Dam was completed in May 1906; 
diversion of river over dam was completed in 1910; 
training walls and dikes were completed in 1935. About 
149 million cubic yards of debris are held in lower 7 
miles of Yuba River between Marysville and downstream 
end of training walls. About 20 million cubic 
yards are confined in river channel by Daguerre Point 
Dam. Additional millions of yards of loose material are 
in mine tailing fields adjacent to project training walls 
in upper 7-mile reach of project. Initial rehabilitation of 
Daguerre Point Dam begun in July 1963 was completed 
in December 1964. Contract for permanent rehabilitation 
of structure was initiated in July and completed in 
October 1965. 
Flood Control 
4. SACRAMENTO RIVER, CA 
Location. Works covered by this improvement are on 
Sacramento River and tributaries in north-central 
California from Collinsville to Ordbend, a distance of 
184 miles. 
Previous project. For details see page 1815 of 
Annual Report for 1917, page 1995 of Annual Report for 
1938, and page 2262 of Annual Report for 1907. 
Existing project. Sacramento River flood control 
project is a comprehensive plan of flood control for 
Sacramento River and lower reaches of its principal 
tributaries. Improvement extends along Sacramento 
River from Ordbend in Glenn County, CA, 184 miles 
downstream to its mouth at Collinsville at upper end of 
Suisun Bay, and comprises a system of levees, overflow 
weirs, drainage pumping plants, and flood bypass 
channels or floodways designed to carry surplus floodwaters 
without inundation of valley lands. About 980 
miles of levee construction, with an average height of 15 
feet, and 98 miles of bank protection are involved in 
project. For further details, see Annual Report for 1962, 
page 2115. 
Estimated (October 1983) cost for existing project 
(exclusive of supplemental levee improvements), including 
new work and maintenance, is $170,875,000 of 
which $75,875,000 is Federal cost and $95 million non- 
Federal ($90,050,562 for lands and damages and relocations 
and $4,949,438 required contributed funds for 
levee construction, bank protection works, and levee 
setbacks). Of this amount, $4,939,752 was for new work 
and $9,686 for maintenance. In addition to project 
requirements, local interests constructed several pumping 
plants for drainage of agricultural and urban land 
protected by project levees. Some channel clearing 
work was accomplished by State of California and other 
local interests to supplement project levee construction. 
Dredging below Cache Slough and reconstruction of 
Cache Creek settling basin weir are considered deferred 
and excluded from foregoing cost estimate. Estimated 
cost (July 1962) of these project units is $2,560,000 and 
$520,000, respectively, a total of $3,080,000 plus U.S. 
costs, for construction. Operation and maintenance of 
completed project will be responsibility of local interests; 
as units of project are completed, they are transferred to 
agencies of State of California for operation and maintenance. 
Existing project was adopted by 1917 Flood 
Control Act (H. Doc 81, 62d Cong., 1st sess., as modified 
by Rivers and Harbors Committee Doc. 5, 63d Cong.,1st 
sess.), 1928 Flood Control Act (S. Doc. 23, 69th Cong., 
1st sess.), River and Harbor Act of 1937 (S. Committee 
print 75th Cong., 1st sess.), and 1941 Flood Control Act 
(H. Doc. 205, 77th Cong., 1st sess.). 
Local cooperation. Local interests have fully complied 
with requirements for all work completed or 
under contract, and indicated they will be able to fulfill 
requirements for remaining work as scheduled. Local 
interest costs from required contributed funds for 
project work total $4,929,438 for levee construction, 
bank protection works, and levee setbacks, of which 
$4,939,752 was for new work and $9,686 for maintenance. 
Operations and results during fiscal year. Regular 
funds: Engineering continued. Project prevented an 
estimated $300,000,000 in damages from the December 
1982-April 1983 rainfloods. 
Historical summary. Construction of existing project 
began in FY 1918 and is about 99 percent complete. 
Channel improvement to date has produced a channel 
with a capacity of 579,000 cubic feet per second in 
Sacramento River below Cache Slough. In addition, 
discharges up to 21,000 cubic feet per second can be 
diverted from Sacramento River through Georgiana 
Slough. Completed major project items include about 
977 miles of levees; five weirs with a combined discharge 
capacity of 602,000 cubic feet per second; two cutoff 
44-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1988 
channels; two sets of outfall gates; channel improvement 
and clearing in Sacramento River, Butte Creek, Putah 
Creek, and Sutter and Tisdale Bypasses; construction of 
two main bypasses or floodways and secondary bypasses 
at Tisdale and Sacramento weirs and at Wadsworth 
Canal; construction of Knights Landing ridge cut and of 
Cache Creek settling basin; installation of gaging stations; 
and enlargement of Sacramento River below 
Cache Slough. Cutoffs at Collins Eddy and between 
Wild Irishman and Kinneys Bends were made in 1918 
and 1919, respectively. Sacramento weir was completed 
in 1917, Fremont weir in 1924, Tisdale and Moulton 
weirs in 1932, and Colusa weir in 1988. Outfall gates at 
Knights Landing were constructed in 1930 and at 
mouth of Butte Slough in 1936. Pumping plants on 
Sutter Bypass were completed in 1944. Work items 
with reference to clearing, snagging, rectification of 
channels, and bank protection on Sacramento River 
and tributaries in Tehama County and from Red Bluff 
southerly, provided for by 1941 Flood Control Act were 
accomplished in fiscal years 1947,1948,1949, and 1951. 
Work remaining comprises completion of levee stage 
construction, Yolo Bypass and Cache Slough. (See table 
44-C for total cost of existing project to September 80, 
1983.) 
44-4

CALIFORNIA DEBRIS COMMISSION 
TABLE 44-A COST AND FINANCIAL STATEMENT 
See 
iSection Total Cost to 
FY 80 FY 81 FY 82 FY 83 Sep 30, 1983 
821,325 
821,325 
- - 50,000 
- - 50,000 
377,990 479,000 633,000 71 
324,835 511,710 635,354 60 
- - - 
-. -. - 
in Text Project 
1. Regulation of 
Hydraulic Mining 
and Preparation of 
Plans 
2. Sacramento River and 
Tributaries, CA 
(Debris Control) 
(Contributed Funds, 
her) 
3. Treatment of Yuba 
River Debris 
ituation Restraining 
rriers,C A 
(Federal Funds) 
Required Contributed 
unds) 
Ctohnetrr)ibute d Funds, 
4. Saramento River, 
(Federal Funds) 
(Contributed Funds) 
Funding 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Costp 
Maint. 
APprop. 
New Work 
Contrib. 
Cost 
New Work 
AppCrop. 
Cost 
Maint. 
CAopsptrop. 
Rehab. 
Approp. 
Cost 
p " 
New Work 
tCooantt rib. 
Maint. 
ontrib. 
Cost 
Rehab. 
Contrib. 
lost 
New Work 
Contrib. 
ost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Maint. 
contrib. 
ost 
807 
10,000 
68,911 
28,000 
344 1 
- 2 
2,851 1 
3,255 
S 5,093,9991 2 
S 5,093,9991 a 
13,000 5,211,043b 
)5,227 5,071,166 
- 12,4206 
- 12,4206 
- 361,482 
- 361,482 
- 1,597,6567 
16,564 1,586,370' 
- 1,053,904 
- 1,053,904 
- 361 777 
- 361,777 
0,000 1,605,223 
19,026 1,584,706 
- 1,053,904 
- 1,053,904 
- 34,0008 
- 34,0008 
- 67,626,3359 
2,257 67,626,335' 
- 1,979,104 
- 1,979,104 
- 10,724,08510 
- 10,724,08510 
- 9,68611 
- 9,6861 
1. Exclusive of $644,503 appropriation and cost on inactive 
portion of project. 
2. Includes $447,127 for recreational facilities at North 
Fork ($32,473) and Harry L. Englebright ($414,654), Code 
710 appropriations. 
3. Includes $447,127 for recreational facilities at North 
Fork ($32,473) and Harry L. Englebright ($414,654), Code 
710 costs. 
4. Includes $4,226,962 from regular funds and $984,082 
from Hydraulic Mining in California funds. 
5. Includes $4,087,085 from regular costs and $984,082 
from Hydraulic Mining in California costs. 
6. Funds from State of California Department of Navigation 
and Ocean Development for acquisition of a boarding 
float at Englebright Dam. 
7. Includes deferred maintenance funds in amount of 
$207,500. 
8. Miscellaneous engineering and construction accomplished 
at expense of local interests in connection with 
rehabilitation of Daguerre Point Dam necessitated by December 
1964 floodflows. 
9. Includes appropriation and cost of $680,000 for new 
work for previous project and $1,486,469 public works funds 
for new work for existing project. 
10. Includes $680,000 required contribution for previous 
project; $4,939,752 required contributed funds for existing 
project; and $310,801 voluntary contribution for bank proteetion 
for existing project. 
11. Includes $9,686 required contributed funds for existing 
project. 
44-5 
10 6,000 
10 5,806 
-8 
65,000 
20,491

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
TABLE 44-B AUTHORIZING LEGISLATION 
See Date 
Section in Authorizing 
Text Act Project and Work Authorized Documents 
1. 
Mar. 1, 1893 
Feb. 27, 1907 
June 19, 1934 
June 25, 1938 
4. 
Dec. 22, 1944 
and May 17, 1950 
July 3, 1958 
July 14, 1960 
REGULATION OF HYDRAULIC MINING AND 
PREPARATION OF PLANS 
Created California Debris Commission and authorized: (a) Ex. Doc. 267, 51st Cong., 
Hydraulic mining under its regulation in drainage areas of 2d sess., Ex. Doc. 98, 
Sacramento and San Joaquin Rivers, if possible without 47th Cong., 1st sess.1 
injury to navigability of these river systems or to lands 
adjacent thereto; and (b) preparation of plans by 
Commission for improvement of navigability of these river 
systems, and flood and debris-control therein. 
Authorized California Debris Commission to permit (Amendment of see. 13, 
hydraulic mining without construction of impounding Act of Mar. 1, 1893.)1 
works, provided there is no injury to navigability of above 
river systems or lands adjacent thereto. 
Amended act of Mar. 1, 1893, which provides for construction 
of debris dams or other restraining works by California 
Debris Commission and collection of a 3-percent tax on 
gross proceeds of each mine using such facilities, 
so as to eliminate this tax and substitute an annual tax 
per cubic yard mined, obtained by dividing total capital cost 
of each dam, reservoir, and rights-of-way, by total capacity 
roef vroecsaetrivooni ro ff or restraint of debris; and authorized Commission orders permitting such mining, 
for failure to pay this annual tax within 30 days after its due 
date; and also authorized receipt of money advances, from 
mineowners to aid such construction, to be refunded later 
from annual payments of yardage taxes on material mined. 
Added at end of sec. 23 of above act, a provision that the 
Secretary of the Army is authorized to enter into contracts 
to supply storage for water and use of outlet facilities 
from debris-storage reservoirs for domestic and irrigation 
purposes and power development, upon such conditions of 
delivery, use, and payment as he may approve, these 
payments are to be deposited to credit of such reservoir 
project, reducing its capital cost to be repaid by tax 
on mining operations. 
SACRAMENTO RIVER, CA 
Additional levee construction and reconstruction, including H. Does. 649, 78th Cong., 
levee protection of Upper Butte Basin, and multipurpose 2d sess., and 367, 81st 
reservoirs.2 Cong., 1st sess. 
Bank protection and incidental channel improvements, H. Doc. 272, 84th Cong., 
Sacramento River from Chico Landing to Red Bluff, and 2d sess. 
local interests flood plain zoning above Chico Landing.2 
Bank protection works at critical locations, Sacramento S. Doc. 103, 86th Cong., 
River.2 2d sess. 
44-6 
1. For latest published map, see Annual Report for 1913, 2. This supplemental work is reported in detail under 
p. 3170, and Rivers and Harbors Committee Document 50, Sacramento District, Improvement No. 13. 
74th Cong., 1st sess.

CALIFORNIA DEBRIS COMMISSION 
TABLE 44-C SACRAMENTO RIVER, CA: TOTAL COST OF 
EXISTING PROJECT TO SEPTEMBER 30, 1983 
(See Section 4 of Text) 
Funds New Work Maintenance Total 
Regular $65,459,866 $1,979,104 $67,438,9701 
Public Works 1,486,469 - 1,486,469 
Total U.S. $66,946,335 $1,979,104 $68,925,439 
Contributed Project Work 4,939,752 9,686 4,949,438 
Contributed, Other 5,104,333 - 5,104,333 
Total All Funds $76,990,420 $1,988,790 $78,979,210 
1. Includes $429,671 representing book value of plant 
purchased with previous project funds and transferred to 
existing project without reimbursement. 
44-7

U.S. ARMY ENGINEER WATERWAYS 
EXPERIMENT STATION 
Organization and functions. The Waterways Experiment 
Station (WE S) is a field operating agency of the Chief of 
Engineers operating under the staff supervision of the Director, 
Research and Development. COL Tilford C. Creel, Corps 
of Engineers, is Commander and Director. Mr. Frederick 
Brown is Technical Director. 
WE S, the Corps of Engineers largest laboratory complex 
for research, testing, and development, consists of five technical 
laboratories: Hydraulics, Geotechnical, Structures, 
Environmental, and Coastal Engineering Research Center.1 
The Hydraulics Laboratory, the largest laboratory of its kind 
in the world, uses a wide range of working models and 
computer-based numerical models for research and analysis 
of dams, levees, rivers, and harbor projects, soil and streambank 
erosion, thermal pollution, etc. The Geotechnical Laboratory 
conducts research in soil mechanics, structural foundation 
design, embankment design and slope stability, 
seepage analysis, military pavements, engineering geology, 
rock mechanics, expedient surfacing, earthquake engineering, 
and mobility and trafficability. The Structures Laboratory 
uses theoretical, analytical, experimental, and modeling 
approaches to research the effects of nuclear and 
nonnuclear explosions, the response of structures to natural 
and explosive disturbances, and various construction 
materials with emphasis on concrete, especially the testing, 
repair, and preservation of existing concrete structures. The 
Environmental Laboratory researches the problems caused 
by man's activities with respect to the environment. Research 
programs include Dredged Material, Aquatic Plant Control, 
Environmental and Water Quality Operational Studies, 
Environmental Impact, Wetlands, and the Recreation 
Research Program. These and other programs of the Environmental 
Laboratory range through waste management, 
environmental regulations, and military aspects of terrain 
and camouflage. The Coastal Engineering Research Center 
conceives, plans, and conducts research and data collection in 
coastal/ocean engineering and nearshore oceanography to: 
provide a better understanding of waves, winds, water levels, 
tides, and currents; provide scientific and engineering data 
and design criteria; and determine the effects of the coastal 
activities of the Corps of Engineers which are important to 
environmental considerations in the coastal zone. 
WES Laboratories are engaged in research and engineering 
investigations in support of the civil and military missions 
of the Chief of Engineers. On a reimbursable basis, WES 
performs basic and applied research, develops state of the art 
methods and techniques, tests materials and equipment, and 
provides consulting services. Subject to the approval of the 
Chief of Engineers, studies and investigations may be undertaken 
for agencies outside the Department of the Army. 
WES maintains an extensive scientific and engineering 
reference library to serve the specialized needs of the Corps of 
Engineers and issues publications of general interest; operates 
DOD Information Analysis Centers in the fields of 
Pavements and Soils Trafficability, Concrete Technology, 
Hydraulic Engineering, Soils Mechanics, and Coastal Engineering; 
and maintains the Corps of Engineers Engineering 
Computer Programs Library. 
During Fiscal Year 1983, 276 WES numbered reports of 
individual studies conducted at or for WES, 12 contract 
translations, and 15 unnumbered publications (conference 
reports, special study reports, etc.) for WES and other offices 
were printed and distributed to Corps offices and interested 
outside agencies. 
Operations and results during the period. Work accomplished 
at WES is, in general, initially financed by the Corps 
of Engineers Revolving Fund, with direct reimbursement 
from agencies requesting research investigations and related 
services. The Station's total program during Fiscal Year 1983 
was $91,085,614 which included $25,551,000 performed by 
contract. Of the total program $47,580,986 was charged to 
civil, $43,108,731 to military, and $395,897 to non- 
Governmental activities. The plant replacement and improvement 
program was $3,338,307 for this period. 
1The Coastal Engineering Research Center was relocated to 
the Waterways Experiment Station effective 1 July 1983 by 
Permanent Order 5-1 dated 21 March 1983. 
45-1

PERMANENT INTERNATIONAL ASSOCIATION OF NAVIGATION CONGRESSES 
(PIANC) 
The Permanent International Association of Navigation 
Congresses (PIANC) is an international organization 
with headquarters in Brussels, Belgium. It is a clearinghouse 
where the views and experiences of engineers and 
port operators of the nations of the world are exchanged 
on problems relating to ocean and inland navigation 
improvements. Its objective is broadly stated "to promote 
the progress of inland and maritime navigation." 
The Association developed during the period 1885-1902 
from an international interest in perpetuating a series 
of Congresses for the exchange of technical information 
on problems related to inland and ocean navigation. The 
Permanent International Commission was formed during 
the 8th International Congress at Paris in 1900 and 
led to the formation of PIANC during the 9th International 
Congress at Dusseldorf, Germany in 1902. The 
United States became a member nation by authority of 
an Act of Congress approved June 28, 1902, which provided 
for annual appropriations toward the maintenance 
of the Association. 
In 1902, the United States appropriated $3,000 annually 
for support and maintenance of the Permanent 
International Commission of Congresses of Navigation 
and for payment of the actual expenses of properly accredited 
national delegates of the United States to meetings 
of the Congresses and Commissions. An increase in 
the appropriation to $5,000 annually was authorized by 
the 1948 River and Harbor Act and an appropriation of 
$22,000 annually by the 1965 River and Harbor Act. 
The current appropriation of $45,000 was authorized by 
the 1974 Water Resources Development Act. Of this 
amount, an annual subvention of about $6,900 is paid by 
the U. S. Section to the International Association in 
Brussels, Belgium. 
The objective of the Association-to promote the progress 
of inland and maritime navigation-is met by holding 
International Congresses and publishing technical 
bulletins and other documents. The Congresses are held 
in various member countries, usually at four-year intervals. 
The Association is supported principally by member 
governments, but membership also extends to corporations 
and to individuals. Member governments are 
represented at the Congresses and at meetings of the 
Permanent International Commission by delegates, the 
number of official delegates to be determined by the 
amount of the annual subsidy paid by the government, 
but not to exceed ten in number. Corporate members 
may send one official representative to the Congresses. 
Currently, the Permanent International Commission 
has 39 countries represented. Individual membership is 
of two classes-Annual and Life-depending on the 
method of payment of dues. There are 1,207 annual 
international members, 676 life members, and 597 corporate 
members, for a total of 2,480 members. Membership 
of the U. S. Section on September 30, 1983 totaled 
595, consisting of 117 life members, 391 individual 
members, and 87 corporate members. 
The affairs of the Association are managed by the Permanent 
International Commission composed of delegates 
from the supporting governments. The National 
Commission constitutes the governing body of the U. S. 
Section and the U. S. Members of the Permanent International 
Commission. The Director of Civil Works, Office 
of the Chief of Engineers, U. S. Army, and the Resident 
Member, Board of Engineers for Rivers and Harbors are 
the ex-officio Chairman and Secretary, respectively, of 
the National Commission. The Secretary handles all 
administrative matters of the U. S. Section. 
During Fiscal Year 1983, National Commissioners 
were: Major General John F. Wall, USA, ex-officio Chairman; 
Colonel F. W. Mueller, Jr., CE, ex-officio Secretary; 
Rear Admiral Richard A. Bauman, USCG; Mr. Harry N. 
Cook; Mr. James M. Goldston; Colonel Herbert T. Haar, 
Jr., USA (Ret); Mr. Vernon J. Ljungren; Mr. William R. 
Murden; and Mr. George H. Kimmons. 
Lieutenant General John W. Morris, USA (Ret) is an 
honorary Vice President of PIANC, having served two 
terms as a Vice President. Major General Charles G. 
Holle, USA (Ret), Secretary-General, XXth International 
Navigation Congress, 1961, is ex-officio member of the 
Permanent International Commission. Honorary American 
members of the Permanent International Commission 
include Brigadier General Herbert D. Vogel, USA 
(Ret); Colonel Alvin D. Wilder, USA (Ret); and Colonel 
Carl H. Bronn, USA (Ret). 
The annual meeting of the Permanent International 
Commission (PIC) was held in Wiesbaden, Germany on 
June 7, 1983, and was attended by all National Commissioners. 
Lieutenant General John W. Morris, USA (Ret) 
and Major General Charles G. Holle, USA (Ret) also 
attended the PIC meeting. 
American representatives attended meetings of the 
International Study Commissions, two Permanent Technical 
Committees (PTCs) and Work Groups of PTCs. 
U. S. representation on these groups during this fiscal 
year was as follows: 
International Commission for Study of Locks, Ship 
Lifts, and River Weirs-Mr. John Davis 
Permanent Committee for Developing Countires- 
Brigadier General Herbert D. Vogel, USA (Ret) 
Permanent Technical Committee I-Mr. J. W. Hershey 
Work Group 1, Identification of Methods for Economic 
Study of Inland Waterways-Mr. Howard E. Olson 
Work Group 2, Disposal of Dredged Materials- 
Mr. Alf H. Sorensen 
Permanent Technical Committee II-Mr. Eugene H. 
Harlow 
Work Group 1, Shipping and Handling of Dangerous 
Cargo-Captain William R. Riedel, USCG (Ret) 
Work Group 2, Stability of Rubble Mound Breakwaters-
Mr. Eugene H. Harlow 
Work Group 3, Bank Protection, Probabilistic Approach 
of Design, and the Effect of Propeller Wash (Jet) 
on Bank Protections-Mr. Alan Crowhurst 
Work Group 3a, Minimum Underkeel Clearances- 
Mr. Ronald C. Uhlin 
Work Group 3b, Navigation in Muddy Waters- 
Dr. John B. Herbich 
Work Group 4, Winter Ice Navigation-Professor 
C. Allen Wortley 
Work Group 5, Ocean Dredge Disposal-Colonel 
Herbert R. Haar, Jr., USA (Ret) 
Work Group 6, Classification of Soils to be Dredged- 
Mr. J. W. Bean 
46-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Joint Subcommittee for Advice on Sport and Pleasure 
Navigation-Mr. John M. Nichol 
The first time meeting by a U. S. Section regional 
group was held on March 30-April 1,1983, in Vicksburg, 
Mississippi by the Central Region. Over 155 participants 
were registered. 
On September 13-14, 1983, the Western Region met in 
Seattle, Washington concurrent with the annual convention 
of the American Association of Port Authorities. 
During 1983, the U. S. Section also held concurrent 
meetings and the PIANC exhibit was displayed by Executive 
Secretary Lyle C. McLaren at meetings with 
National Waterways Conference, Inc., Western Dredging 
Association, Water Resources Congress, American Society 
of Civil Engineers, and the International Inland 
Waterways Conference and Trade Show. 
46-2

INVESTIGATIONS OF PROJECTS UNDER THE FEDERAL POWER ACT 
The Federal Water Power Act of June 10, 1920, created 
the Federal Power Commission (in 1977 renamed to 
Federal Energy Regulatory Commission, FERC) composed 
of the Secretaries of War, Interior, and Agriculture, 
with authority to grant permits and licenses for hydroelectric 
development in all waters over which Congress 
has jurisdiction. The act further required that work of 
the commission be performed by and through the Departments 
of War, Interior and Agriculture and their engineering, 
technical, and other personnel except as may be 
otherwise provided by law. By an act of June 23, 1930, 
entitled "An Act to Reorganize the Federal Power Commission," 
Secs. 1 and 2 of the Federal Water Power Act 
of 1920 were amended. A commission was provided for, 
to be composed of five commissioners to be appointed by 
the President, by and with the advice and consent of the 
Senate. The necessity of performing work through the 
Departments of War, Interior and Agriculture was removed 
and the commission was authorized to appoint 
such officers and employees as necessary in executing 
its function. By Title II, Public Utility Act of 1935, the 
original Federal Water Power Act was made Part I of 
the Federal Power Act, and Parts II and III were added 
to that act. On October 1, 1977, pursuant to the provisions 
of the Department of Energy Organization Act 
(DOE Act), Public Law 59-91 Stat. 565 (August 4, 1977) 
and Executive Order No. 12009, 42 Fed. Reg. 46267 
(September 15, 1977), the Federal Power Commission 
ceased to exist and its functions and regulatory responsibilities 
were transferred to the Secretary of Energy and 
the Federal Energy Regulatory Commission (FERC) 
which, as an independent commission within the Department 
of Energy was activated on October 1, 1977. 
Section 4(e) of the Federal Power Act provides that no 
water power license affecting navigable capacity of any 
navigable waters of the United States shall be issued 
until plans of the dam or other structures affecting navigation 
have been approved by the Chief of Engineers 
and the Secretary of the Army. By an action, notice of 
which was published in the Federal Register Volume 40, 
Number 74, dated April 16, 1975, the Secretary of the 
Army delegated to the Chief of Engineers his authority 
under Sec. 4(e) of the Federal Power Act. The Chief of 
Engineers on September 5, 1980, delegated to the Corps 
division engineers the authority for Section 4(e) approval 
of plans for non-Federal hydropower development affecting 
navigation. 
The following work of an engineering nature was accomplished 
by the Corps division and district offices 
under the direction of the Chief of Engineers during the 
fiscal year: 1,106 applications from non-Federal entities 
for planning, design, construction and operation of hydropower 
projects were reviewed and appropriate recommendations 
in the interest of flood control, navigation, 
and structural safety, relative to Corps projects, were 
furnished to the FERC. Of the total 1,106 applications, 
164 applications were for hydropower development at 
Corps projects. Recommendations were furnished to the 
Commission concerning the impact of hydroelectric 
power development on the existing and proposed Federal 
Water resources projects. Recommendations also were 
provided to the Commission on the environmental impacts 
of constructing power plant(s) at either proposed or 
existing projects. 
To date, there are 26 constructed non-Federal power 
plants at Corps projects. Non-Federal entities had 5 
power plants under active construction at Corps projects 
during the fiscal year, and had 11 licensed power plants 
in final design stages. The Corps bills FERC licensees 
for the costs incurred by the Corps in approving final 
design, plans and construction of power plants at Corps 
projects. In FY 1983, the total cost reimbursement to the 
Corps for this service was $246,875. Review of license 
applications is funded by the Corps as line item in the 
General Investigation Account. In FY 1983, Civil Works 
budget contained $399,500 dollars for this prelicensing 
activity. 
47-1

REGULATORY, SUNKEN VESSEL REMOVAL 
& NATIONAL EMERGENCY PREPAREDNESS ACTIVITIES 
1. Regulatory Activities 
Authorities. The following authorities charge the 
Corps of Engineers with the regulation of various waterrelated 
construction activities: Sections 9 and 10 of the 
River and Harbor Act of 1899 (structures in an alteration 
of waterways, e.g. boat docks); Section 103 of the 
Marine Protection and Sanctuaries Act of 1972 (ocean 
dumping); and Section 404 of the Clean Water Act (discharge 
of dredged and fill material). 
Work Completed. During FY 1982, the Corps received 
approximately 14,500 applications for permits 
and issued 8,650 permits and 3,200 letters of permission. 
In addition about 10,000 activities were authorized 
by regional or statewide permits which did not require 
individual applications from the public. Many thousands 
of other minor activities were authorized by the Corps' 
nationwide permits. The Corps discovered or was notified 
of a total of 3,200 alleged violations to be investigated. 
In FY 1983 the Corps continued its efforts toward regulatory 
reform based on a May 7, 1982, directive from 
the President's Task Force on Regulatory Relief. Proposed 
regulations were announced to the public for comment 
on May 12, 1983. By the end of FY 1983, actions to 
streamline the Corps' procedures had reduced average 
permit application processing time to 73 days compared 
with 119 days at the end of FY 1982. 
TABLE 48-A 
GENERAL REGULATORY FUNCTIONS 
Obligations 
Unobligated Balance-30 Sep 82...... 
Allotments ....................... 
Total Funds Available .............. 
Obligations ....................... 
Unobligated Balance-30 Sep 83 ...... 
Expenditures 
Unexpended Balance-30 Sep 82 ...... 
Allotments ...................... 
Total Funds Available .............. 
Expenditures ..................... 
Unexpended Balance-30 Sep 83 ...... 
$ 1,505,107 
+48,178,786 
49,683,893 
47,538,291 
$ 2,145,602 
4,604,504 
+48,178,786 
52,783,290 
-47,313,133 
$ 5,470,157 
2. Investigation and Removal of Sunken Vessels 
Under the authority of Sections 19 and 20 of the River 
and Harbor Act of 1899, the Corps of Engineers investigated 
sunken vessels in navigable waters and removed 
those obstructing navigation. For obligations expenditures, 
see Table 48-B.
TABLE 48-B 
REMOVAL OF SUNKEN VESSELS 
Obligations 
Unobligated Balance-30 Sep 82 ...... $ 276,480 
Allotments ....................... 
Total Funds Available ............... 
Obligations ........................ 
Unobligated Balance-30 Sep 83....... 
Expenditures 
Unexpended Balance-30 Sep 82 ...... 
Allotments ....................... 
Total Funds Available .............. . 
Expenditures....................... 
Unexpended Balance-30 Sep 83 ....... 
+5,745,262 
6,021,742 
-5,777,622 
$ 244,120 
$ 277,469 
+5,745,262 
6,022.731 
-5,026,169 
$ 996,562 
3. National Emergency Preparedness Activities 
Authority. Executive Order 11490, as amended, 
assigns responsibilities to executive departments and 
agencies to undertake national emergency planning and 
preparedness to develop an effective national capability 
to meet essential civilian and defense needs during major 
domestic emergencies and national security emergencies. 
Status: The Corps of Engineers Readiness Posture has 
improved through the preparedness activities undertaken 
to maintain a national engineering and construction 
capability for an effective response to any national 
emergency. Planning and preparedness initiatives were 
in these major program areas: (1) to define the Corps' 
national support requirements; (2) to prepare national 
emergency preparedness plans; (3) to develop an engineering 
organization structure which supports mission 
accomplishment; (4) to maintain an adequate level of 
national emergency operational readiness for rapid 
response to requirements; (5) to develop program controls 
which guide plan formulation and periodically test 
plans to ensure feasibility, applicability and effectiveness. 
For Fiscal Year obligations and expenditures see 
Table 48-C. 
TABLE 48-C 
NATIONAL EMERGENCY PREPAREDNESS 
Obligations 
Unobligated Balance-30 Sep 82....... 
Allotments ........................ 
Total Funds Available ............... 
Obligations ........................ 
Unobligated Balance-30 Sep 83 ....... 
Expenditures 
Unexpended Balance-30 Sep 82 ....... 
Allotments ........................ 
Total Funds Available .............. . 
Expenditures ...................... 
Unexpended Balance-30 Sep 83 ....... 
$ 847,016 
+4,872,329 
5,719,345 
-5,630,695 
88,650 
1,970,011 
+4,872,329 
6,842,340 
-5,055,898 
$1,786,442 
48-1

INTERNATIONAL BOUNDARY WATERS BOARDS 
In order to carry out United States obligations under 
international agreements, the Office of the Chief of 
Engineers and several Corps Divisions and Districts 
with jurisdiction over areas bordering Canada have representation 
on numerous international boards and committees. 
The majority of these boards were established 
by the International Joint Commission (IJC) as empowered 
in accordance with the provisions of the Boundary 
Waters Treaty of 1909 between the United States and 
Great Britain (for Canada). IJC boards fall into two 
broad categories: boards of control, which are more or 
less permanent and supervise compliance over an IJC 
order; and engineering or technical boards, which are 
usually dissolved after completing and reporting on an 
investigation assignment. In addition to boards created 
by the Commission, other international boards and committees 
are created by treaties or other informal arrangement 
in matters concerned with the water resources of 
joint interest, and the members report directly to the 
Governments or establishing agency. International 
boundary waters boards and committees having Corps 
of Engineer memberships during the fiscal year are 
listed in Table 49-1. For an explanation of the constitution 
of the various boards and committees, see the FY 77 
and FY 80 annual reports. 
TABLE 49-1 
IJC BOARDS OF CONTROL HAVING CE MEMBERS 
BOARD NAME 
1. 
2. 
3. 
4. 
5. 
Int. Lakes Superior 
Int. St. Croix River 
Int. Lake of the Woods 
Int. Lake Champlain 
Int. Kootenay Lake 
6. Int. Rainy Lake 
7. Int. Osoyoos Lake 
8. Int. Niagara 
9. Int. St. Lawrence River 
10. Int. Skagit River 
YEAR 
ESTABLISHED 
1914 
1915 
1925 
1937 
1938 
1941 
1943 
1953 
1953 
1967 
UNITED STATES REPRESENTATION 
*Div. Engr., NCD 
*Div. Engr., NED 
*Dist. Engr., St. Paul 
*Dist. Engr., New York 
*1. Dist. Engr. Seattle 
2. Dept. of Interior, USGS, Boise, ID 
*Dist. Engr., St. Paul 
1. Dist. Engr., Seattle 
*2. Dept. of Interior, USGS, Tacoma, WA 
3. Washington Dept. of Ecology, Olympia 
*1. Div. Engr., NCD 
2. Dept. of Energy, FERC, Washington, D.C. 
*1. Div. Engr., NCD 
2. St. Lawrence Seaway Development Corporation, 
Massena, NY 
3. St. Lawrence-Eastern Ontario Commission, 
Waterton, NY 
4. NY State Power Authority, Massena, NY 
*Dist. Engr., Seattle 
*Signifies U. S. Section Chairman 
IJC ENGINEERING OR STUDY BOARDS HAVING CE MEMBERS 
BOARD NAME 
11. Int. Souris-Red Rivers 
Engineering 
12. Int. Champlain-Richelieu 
13. Int. Lake Erie Regulation 
Study 
14. Int. Great Lakes Diversions 
and Consumptive 
Uses Study 
YEAR 
ESTABLISHED 
1948 
1975 
1977 
1977 
UNITED STATES REPRESENTATION 
1. Dist. Engr., St. Paul 
*2. Dept. of Interior, WPRS, Washington, D.C. 
3. Dept. of Interior, USGS, Washington, D.C. 
*1. New York Depart. Envir. Conser. 
2. Dist. Engr., New York 
3. Vermont Agency Envir. Conser. 
4. New England River Basins Commission, Staff 
Associate 
5. Dept. of Interior, F&WS, Boston, MA 
*1. Div. Engr., NCD 
2. Ohio Environmental Protection Agency 
3. New York Dept. Envir. Conser. 
4. Dept. of Interior, F&WS, Boston, MA 
*1. Div. Engr., NCD 
2. Michigan Dept. Nat. Res. 
3. Illinois Dept. of Trans. 
49-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
15. Int. Great lakes Technical 
Information Network 
Board 
1979 
4. Pennsylvania Dept. of Envir. Res. 
5. Dept. of Energy, FERC, New York, NY 
*1. NCEED-L, Detroit, MI 
2. Great Lakes Environmental Research Lab., 
NOAA, Ann Arbor, MI 
3. USGS, Reston, VA 
OTHER INTERNATIONAL BOARDS OR GROUPS HAVING CE MEMBERS 
BOARD NAME 
16. Int. Lake Memphremagog 
17. Coordinating Committee 
on Great Lakes Basic 
Hydraulic and Hydrologic 
Data 
18. Int. Niagara Committee 
19. Columbia River Treaty 
Entities 
20. Columbia River Treaty 
Permanent Engineering 
*Signifies U. S. Section Chairman. 
YEAR 
ESTABLISHED 
1920 
1953 
1955 
1964 
1964 
UNITED STATES REPRESENTATION 
*Dist. Engr., New York 
*1. Eng. Div., North Central Div. 
2. Dept. of Commerce, NOAA, Rockville, MD 
*Div. Engr., NCD 
1. Div. Engr., NPD 
*2. Bonneville Power Admin., Portland, OR 
*1. OCE, DAEN-CWE, Washington, D.C. 
2. Dept. of Energy, Washington, D.C. 
49-2

U.S. ARMY CONSTRUCTION ENGINEERING RESEARCH LABORATORY 
Organization and functions. The U.S. Army Construction 
Engineering Research Laboratory (CERL) 
is a field operating agency of the Chief of Engineers 
operating under the supervision of the Chief, Research 
and Development Office. CERL, which is 
located in Champaign, IL, was officially dedicated on 
July 25, 1969, and is one of the Corps' four major 
laboratories. The laboratory is closely affiliated with 
the University of Illinois, sharing laboratory, library, 
computer, and personnel resources with the University. 
Colonel Paul J. Theuer, Corps of Engineers, is 
Commander and Director. 
CERL research programs are oriented toward the 
support of the total Army, the Army in garrison, the 
military installation, the Department of Defense, and 
to the nation as a whole. The laboratory, which has 
base support, combat support, and civil works missions, 
is engaged in a construction research program 
designed to improve planning, design, construction, 
operation, and maintenance of a variety of Army facilities. 
The ultimate goal of the overall research effort is 
to create products that will save the Army resources. 
Research findings are transmitted directly to the field, 
as well as to private industry and the academic community. 
Within the Corps, research supports both military 
and civil works projects in the general areas of 
environmental quality, energy, materials, engineering 
management, and military engineering. 
In the area of environmental quality, CERL has 
developed a broad-based program designed to maintain 
military readiness standards, while still conforming to 
environmental quality regulations. These programs 
have included development of methods to predict 
noise impacts, water and air pollution control techniques, 
adaptations of currently used technologies to 
more stringent fluid and solid waste control, and computerized 
methods to cut the time and costs involved 
in environmental impact assessment. 
Energy research is oriented toward helping the 
Army meet its energy conservation goals. These projects 
include development of computer simulation 
technology for selection of more fuel-efficient energy 
systems and design methods and exploration of alternative 
fuel sources like solar energy and biomass. 
CERL's materials program is designed to lower the 
Army's costs for construction, modification, operation, 
and maintenance of its facilities. These projects 
include investigations on protective coatings, polymer 
technology, seismic criteria, quality monitoring 
systems, and materials syntheses and selection 
programs. 
CERL supports the Army decision-maker through 
its engineering management programs that are designed 
to increase facility efficiency and productivity. The 
development of automated data processing systems 
for management information, cost estimating, profit 
determination, architecture and design, corrosion 
mitigation, pavement management, housing contract 
maintenance, and habitability information have helped 
reduce costs throughout the military. 
CERL's military engineering program provides 
direct support to the battlefield engineer and to the 
maintenance of military readiness. This research has 
developed training aids, field-protective structures to 
increase combat survivability, and methods to enhance 
the effectiveness of operations during combat situations. 
In mobilization, CERL research has led to the 
development of planning systems to evaluate installation 
troop housing and other requirements, and to the 
development of low-cost, troop constructible foam 
shelters for use as emergency housing during the critical 
early stages of mobilization. 
During Fiscal Year 1983, CERL produced 158 publications, 
of which 62 were technical reports, 34 were 
Army-level publications, and 62 were publications 
presented in the public domain. In addition, CERL 
personnel presented 49 papers at scientific meetings. 
CERL personnel prepared and presented 31 training 
programs in areas such as corrosion, energy conservation, 
pavement management, environment and 
microcomputers. Three patents were issued to CERL 
personnel. 
Operations and results during the period. Work performed 
during Fiscal Year 1983 was funded both 
directly and through reimbursable programs. CERL's 
total program was $23.8 million, of which $13.9 
million was direct RDT&E funding and $3.0 million 
was reimbursable funding from the Office of the Chief 
of Engineers and Corps Divisions and Districts. Other 
Federal agencies, such as the Air Force, Navy, Department 
of Energy, and Environmental Protection Agency 
accounted for $6.9 million. 
50-1

U.S. ARMY ENGINEER TOPOGRAPHIC LABORATORIES 
Organization and functions. The U.S. Army Engineer 
Topographic Laboratories (ETL) began during World War 
I as a temporary Engineer Detachment, formed to test 
aerial photography for topographic mapping. Since that 
time, ETL has grown into a sophisticated, modern research 
and development laboratory, applying the latest advances 
in optics, electronics, computer data processing, space 
sciences, and related technologies to military and civil 
problems in mapping, surveying, land navigation, and 
geodesy. ETL is now a field operating agency of the Corps 
of Engineers and is commanded by Colonel Edward K. 
Wintz. 
The Engineer Topographic Laboratories is the only 
defense research and development laboratory that addresses 
the full range of development from basic research to a final 
product in the topographic sciences. Support is provided to 
both the Military and Civil Works elements of the Corps 
and to the Army Materiel Development and Readiness 
Command and the Defense Mapping Agency. To provide 
this support, ETL is organized into five operational elements, 
three of which are developmental laboratories. The 
Geographic Sciences Laboratory performs research and 
development associated with the extraction and presentation 
of geographic data for the Army in the field. The Topographic 
Development Laboratory supports technological development 
in surveying and mapmaking. The Computer Sciences Laboratory 
develops advanced computer techniques and systems for 
processing, analyzing, and displaying topographic data derived 
from digital photography. The Research Institute performs 
most of the Laboratories' basic and applied research, and the 
Terrain Analysis Center prepares terrain studies needed by 
field Army elements, as directed by the Assistant Chief of 
Staff of the Army for Intelligence. During Fiscal Year 1983 
copies of 33 Engineer Topographic Laboratories numbered 
reports of individual studies conducted at or for the Engineer 
Topographic Laboratories were distributed to Corps' offices 
and interested outside agencies. 
In recent years, the emphasis of ETL's research and 
development program has shifted from conventional mapmaking 
and surveying equipment and related techniques to new topographic 
data systems, which are required to support the coming 
generation of complex weapons systems and military geographic 
information systems required by field commanders for improved 
command, control, communications, and intelligence. 
The new systems frequently use data acquired by remote 
sensing, and much of the work done at ETL involves this 
technology. Several projects are investigating the types of data 
derived from sensors and means for exploiting those data. 
Central to this work are studies regarding the possibilities of 
automating image interpretation. Research in pattern recognition 
theory, hybrid optical digital devices, and artificial 
intelligence methodologies offers long-range promise toward 
this objective. Meanwhile, the extension of manual photo 
analysis to create knowledge-based/expert software indicates 
near-term improvements to interactive computer-assisted 
photo interpretation. The knowledge gained in these areas 
will be applicable not only to the mapping and terrain analysis 
missions of ETL, but also to the Army thrust of teleoperated 
and autonomous robotic vehicles. Other work is to investigate 
the digital processing of remotely sensed data and to define 
remote sensing inputs required for Army terrain graphics and 
terrain data bases. In addition, a Remote Sensing Consultant 
conducts short courses on remote sensing for Corps of Engineers 
and other government personnel. 
Operations and results during FY 83. The Engineer 
Topographic Laboratories' total program for FY 83 was 
$50,325,200. This included work done for other agencies as 
well as for the Corps of Engineers. Of this total program, 
$34,097 supported work performed by contract. Reimbursable 
work in FY 83 included $168,400 charged to civil works 
funds. 
51-1

U.S. ARMY COLD REGIONS RESEARCH 
AND ENGINEERING LABORATORY 
Background. The U.S. Army Cold Regions Research 
and Engineering Laboratory (USA 
CRREL), located in Hanover, New Hampshire, 
was created in January, 1961. It merged the 
Snow, Ice and Permafrost Research Establishment, 
created in 1949, and the Arctic Construction 
and Frost Effects Laboratory, created in 
1953, both of which were outgrowths of the Army's 
World War II experience in Alaska, Iceland 
and Greenland. 
The Laboratory's mission is to conduct and coordinate 
research and technology Applicable to 
the Army's needs in those geographic areas of the 
world where cold presents a problem. 
The total authorized strength of USACRREL is 
278 (263 civilian and 15 military), with a budget 
for FY83 of over $19 million. USACRREL has five 
main buildings in Hanover which total 240,000 
square feet on 24 acres of land. The buildings include 
the main laboratory, the ice engineering 
facility, the logistics and supply building, the 
plant and equipment building, and the equipment 
storage building. 
Construction of a new Frost Effects Research 
Facility was begun during FY82 and will be completed 
in FY84. This 27,000-square-foot laboratory 
will allow accelerated full-size testing of 
pavement, utility and foundation systems during 
freeze-thaw cycles. USACRREL also maintains an 
Alaska Projects Office in Fairbanks with six 
buildings totaling 30,000 square feet. The Alaska 
Projects Office manages the laboratory's unique 
permafrost tunnel, a 360-ft shaft drilled into 
frozen soil, serving as the site for numerous field 
studies on permafrost. 
USACRREL's basic and applied research covers 
a broad spectrum of cold regions studies. Basic 
research includes work in the physical, 
mechanical, and chemical properties of snow and 
other forms of frozen precipitation, freshwater 
ice, sea ice, and frozen ground. Basic research 
supports applied research in winter battlefield operations 
and materiel, construction, transportation, 
and other problems encountered in arctic, 
subarctic, and temperate cold regions. Major cold 
regions research topics include ice engineering, 
river-ice management, cold regions hydrology, remote 
sensing, environmental impact and preservation, 
design, operation and maintenance of military 
facilities, road and airfield construction, 
mobility, control of snow and ice, wastewater 
management, battlefield obscuration, and combat 
engineering. 
As the only Federal laboratory dedicated to 
cold regions research, USACRREL has a national 
reputation and maintains close ties with Federal 
and state agencies where it provides consulting 
services on a reimbursable basis. As the center of 
cold regions scientific and engineering expertise 
for the Corps of Engineers, USACRREL supports 
Corps districts and divisions by publishing field 
engineering reports, conducting demonstrations, 
sponsoring technical seminars for field engineers, 
and making field visits to consult on engineering 
problems. 
Operations and Results During FY83. During 
FY83, USACRREL published and distributed over 
66 scientific and engineering reports (CRREL 
Reports, Special Reports, Technical Notes, Internal 
Reports, etc), contributed to 15 U.S. Army 
publications and presented 17 technical seminars 
and meetings. 
CRREL personnel consulted with Divisions and 
Districts on a broad range of topics and problems 
concerning Ice Engineering and Remote Sensing 
and in particular the SPOT Simulation evaluation. 
Also Prototype sensor packages have been interfaced 
and installed within the St. Paul, Detroit, 
and Pittsburgh Corps districts using near-real 
time collection systems. A total of 360 One-Stop 
Consulting Services were performed in FY83. 
The CRREL River Ice Management Program 
began in FY83. Included in the RIM start was the 
initiation of the development of an ice forecasting 
model along with the initial planning for the 
remote ice monitoring system. 
CRREL participated in the U.S. Army Exercise 
BRIMFROST, observing various aspects of the exercise. 
They provided technical advice and documented 
problems in areas such as Ice Bridges, 
Living and Work Shelters and Water Purification. 
The SNOW-ONE-B field experiment to relate 
electro-optical weapon system performance to 
winter conditions, was attended by CRREL personnel 
at Camp Grayling, MI during the period 
29 Nov-18 Dec 82. The primary objective was met 
with limited success due to the unusually warm 
weather. However, some useful rain and fog data 
were acquired, and logistical preparations for 
SNOW-TWO were accomplished with a successful 
smoke subtest and boundary layer turbulent wind 
measurement program. 
52-1

U. S. ARMY CORPS OF ENGINEERS WATER RESOURCES SUPPORT CENTER 
The Water Resources Support Center (WRSC), under 
the staff supervision of the Director of Civil Works, 
Headquarters, U. S. Army Corps of Engineers, is commanded 
by Colonel George R. Kleb. The Center is located 
at the Humphreys Engineer Center, Ft. Belvoir, Virginia. 
Its divisions are the Institute for Water Resources, 
Dredging Division, Data Collection and Management 
Division, Publications and Training Division, and Office 
of Budget and Management Support. Elements managed 
by the Center in other locations include the Hydrologic 
Engineering Center at Davis, California; the Marine 
Design Branch of the Dredging Division at Philadelphia, 
Pennsylvania; and the Waterborne Commerce Statistics 
Center of the Data Collection and Management 
Division at New Orleans, Louisiana. The accomplishments 
of WRSC during 1983 are given by division. 
DATA COLLECTION 
AND MANAGEMENT DIVISION 
Remote Sensing 
FY 1983 was an active year for change and new direction 
regarding the Corps of Engineers Remote Sensing 
Program. The Remote Sensing Research Program's 
technical monitorship was expanded beyond WRSC to 
include the Engineering and Construction Directorate 
and the Civil Works Directorate's Planning Division 
and Hydraulics and Hydrology Division. This expansion 
made the program more sensitive to the remote sensing 
requirements and objectives of the Corps mission. 
The successful integration of remote sensing technology 
into the standard procedures of the field operating 
agencies was evidenced by the 50 poster sessions presented 
at the fourth Corps of Engineers Remote Sensing 
Symposium, held November 7-9, 1983, in Reston, Virginia. 
Also, the Remote Sensing Demonstration Program, 
a mechanism for technology transfer, expanded 
beyond North Central Division to include the South 
Pacific and the Southwest Divisions. 
With the administration's increased activities to commercialize 
land civil satellites and the French emergence 
into the land satellite remote sensing technology with 
SPOT, to be launched in 1985, WRSC has been required to 
increase its interagency and international coordination. 
WRSC is the Corps representative to the Department of 
Commerce Civil Land Satellite Source Evaluation Board. 
Data Collection and Management mastered a demonstration 
videodisc containing typical Corps products to 
demonstrate the state-of-the-art capabilities of videodisc 
in support of the Corps mission. The disc was delivered 
to WRSC in August 1983 and was demonstrated to various 
organizations during the following 60-day period. As 
a result of the demonstrations, three applications are 
being developed: litigation support, archiving of Panama 
Canal engineering drawings, and networking or videodisc 
work stations for transfer of information related to 
emergency operations. 
The FY 83 demonstration videodisc and the follow-on 
projects provide a mechanism for evaluating videodisc 
technology coupled with microcomputers to assess capabilities 
and limitations in comparison with existing 
methods of archiving and retrieving information and to 
assist users in selecting the most effective combination 
of videodisc, microcomputer, and data management 
design for their specific needs. 
The Corps' use of the GOES (Geostationary Operational 
Environmental Satellite) data collection system is 
increasing significantly. The number of data collection 
platforms installed or authorized through FY 1983 totals 
1074. Water control management procedures are 
becoming increasingly automated with the addition of 
several minicomputers dedicated to water control, and 
more are planned for the next two to three years. The 
cooperative stream gaging program with the U.S. Geological 
Survey, automated in 1982, was released to the 
field for testing in 1983 and will be operational for the 
1984 program. 
Emergency Communications 
After nearly four years of planning, analysis and coordination 
on establishing a Corps-wide emergency communication 
system, divisions and districts will be 
receiving performance specifications to implement a 
high frequency single sideband system. 
This network will make each district office able to 
communicate anywhere within its district boundaries 
with a 90 percent probability of success during an emergency 
or disaster when normal communications are disrupted. 
In coming months, the system will provide field 
personnel the capability to communicate within the disaster 
area, via handie-talkies, to mobile units, the district 
office the Federal Emergency Management Agency, 
state governments, military and police units, and the 
civil population. 
Datakit Virtual Circuit Switch 
The concept of managing operation of data communications 
equipment and data terminal equipment through 
the use of interconnected digital virtual circuit switches 
was developed by the South Atlantic Division (SAD) as a 
result of that division's growing communication requirements. 
A study of current and emerging technologies in 
the data communications area indicated that the Western 
Electric Datakit switch might provide the required access 
to both local area networks and wide area networks 
required for efficient access to a variety of computers 
both government and private. 
To test fully the wide area capabilities of the Datakit 
switch, South Atlantic Division asked WRSC to participate 
in the test. Switches were installed at both locations, 
Ft. Belvoir, VA, and Atlanta, GA, and were connected 
by the dedicated telephone lines. 
Datakit supports communication between computers 
and terminals in digital form using RS-232C serial transmission 
techniques. Other transmission capabilities are 
planned, but only RS-232C asynchronous transmission 
capabilities are employed at the WRSC node. Since the 
switch supports digital transmission, modems are not 
required for each terminal. The only modems required 
for the WRSC installation are those supporting dial-in/ 
dial-out and dedicated data lines. Since modems are 
shared by all system users, fewer are required for efficient 
system operation. 
53-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
All terminals served by the local Datakit are wired 
directly to the switch through an internal network. All 
data communications equipment and data terminal 
equipment connected to a single point within each node 
results in a star topology. The Datakit functions as a 
single point of control to handle differences in terminal 
characteristics such as parity, baud rate, and byte configuration. 
Transmission rates up to 19,200 bits per second 
are supported by the switch. Datakit handles node 
to node transmission through trunk boards which make 
efficient use of dedicated telephone lines. The wide area 
capabilities offer the possibility of building a sophisticated 
network with the flexibility to grow and change 
without major renovation. 
Waterborne Commerce Statistics Center 
The Waterborne Commerce Statistics Center (WCSC) 
reached significant milestones toward its primary goal 
of a more timely and accurate reporting program. In the 
past year, WCSC contracted the task of analyzing data 
collection procedures in an effort to correct specific deficiencies. 
The study, completed in February 1984, recommended 
an improved reporting form; explicit, detailed 
reporting instructions; a method of cross-checking the 
performance monitoring system and WCSC data; and 
the development of standard data productions for vessel 
operating company use. All have a phased implementation 
plan. A contractor was selected to develop a data 
base management system and a query system targeted 
for completion by the summer of 1984. In addition, a 
public domain data base is to be available during the 
second quarter of 1985. 
Although modified data collection procedures and 
processing techniques made the 1982 data available less 
than a year after the 1981 data, input from the district 
offices was still a significant problem. The Director of 
Civil Works tentatively approached recommendation for 
WCSC to assume total responsibility for collection of the 
data directly from the operators in a phased implementation 
plan over the next two years. Comments have 
been solicited from the field, and, if given final approval, 
the present system of collecting the data would be replaced, 
at sizable manpower savings. 
Port Facilities Branch 
The Port Facilities Branch collects and publishes data 
on the physical characteristics of the coastal, Great 
Lakes, and inland waterway ports of the United States. 
Fifty-three port series reports are published at intervals 
of approximately eight to nine years, covering approximately 
120 port areas. 
During FY 1983, eight reports covering 21 port areas 
were published and offered for sale: 
No. 10-Baltimore, MD 
No. 16-Miami, Palm Beach, and Port Everglades, FL 
No. 25-Corpus Christi, TX 
No. 30-San Francisco, Redwood City, and Humboldt 
Bay, CA 
No. 31-Oakland-Alameda, Richmond, and Ports on 
Carquinez Strait, CA 
No. 61-Huntington, WV, and Ports on Ohio River 
Miles 40-317 and Kanawha River, WV 
No. 70-St. Louis, MO, and Ports on the Upper Mississippi 
River, Miles 0-300 AOR. 
No. 71-Memphis, TN; Helena, AR; and Ports on Lower 
Mississippi River, Miles 620-954 AHP. 
DREDGING DIVISION 
National Dredging Program 
For maintenance and improvement dredging of rivers, 
channels, and harbors, the Corps spent an estimated 
$443 million to move 287 million cubic yards of material. 
This was a reduction of about $2 million from FY 1982 
but an increase of 15 million cubic yards or 5.5 percent. 
Private industry, however, continued to increase its 
share of dredging yardage from 78 percent in FY 1982 to 
83 percent in FY 1983. The 238 million cubic yards 
dredged by industry were 12 percent more than last 
year. Private industry increased its share of dollars for 
dredging from 83 to 85 percent in FY 1983, and the dollar 
amount increased from $369 million in FY 82 to 
$379 million in FY 1983. The Corps decreased its own 
dredging from 60 million to 49 million cubic yards and 
its dollar amount from $76 million to $64 million. 
Retirement of Dredges 
Consistent with the direction of Public Law 95-269 to 
increase private industry's share of dredging, the Corps 
continued to retire its dredges. In FY 1983, eight dredges 
were retired-three medium class hopper dredges: Biddle, 
Comber, and Markham; three small class hopper dredges: 
Hains, Hoffman, and Pacific; and two dustpan dredges: 
Mitchell and Ockerson. The Markham, Hains, and Ockerson 
are being maintained in a standby status until the 
industry has actually demonstrated a capability to 
perform all work that these dredges had previously 
performed. 
Corps of Engineers Reserve Fleet (CERF) 
The Corps continued the implementation of CERF 
during FY 1983 by issuing the required regulations and 
selecting New Orleans District as the contracting office 
for the basic ordering agreement. The New Orleans District 
is currently proceeding with procurement actions, 
and CERF will be fully implemented in FY 1984. 
Support For Other Agencies 
Technical support and training was provided to the 
Air Force for the design and procurement of the cutterhead 
dredge to be operated in the Azores. The application 
of dredging technology was provided the Agency for 
International Development at Roseires Dam on the Blue 
Nile in Sudan, the Environmental Protection Agency to 
develop suitable dumping sites within acceptable environmental 
tolerances, and the Department of Interior 
for the nourishment of beaches at Sandy Hook, NJ. 
International Activities 
Under existing government to government agreements, 
annual meetings were held with counterparts from The 
Netherlands and Japan regarding dredging technology 
53-2

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
and dredged material disposal issues. The ninth U. S.- 
Japan memorandum of understanding meeting of dredging 
experts was hosted by the Corps of Engineers in 
Jacksonville, FL, in October 1983. The third annual 
U. S.-Netherlands meeting was hosted by the Ministry 
of Public Works, North Sea Directorate, in June 1983 in 
The Netherlands. The Water Resources Support Center 
represents the Corps of Engineers in both of these 
agreements. 
HYDROLOGIC ENGINEERING CENTER 
The Hydrologic Engineering Center (HEC) was productive 
in several areas in FY 1983. Significant advances 
were made in increasing the capability of new computer 
models as well as extending the utility of basic rainfallrunoff 
and reservoir operation models. The water control 
software programs have been expanded and improved, 
the family of automated flood damage computation programs 
have been consolidated and are experiencing 
increased usage, and the Data Storage System is enjoying 
widespread use both in HEC and in district studies. 
The recently developed program for dredged disposal 
material management was improved and was extensively 
used in a project application. The storm runoff 
forecasting version of the basic rainfall-runoff model and 
the reservoir operation program were both enhanced to 
improve their capability to perform in a real-time operation 
mode. 
HEC has formulated computer program development 
guidelines that are designed to improve the ability to 
develop modular, easy-to-read, maintainable computer 
codes. The guidelines received an initial trial on the reservoir 
operations program. The program was substantially 
modified to most portions of the guidelines, and 
the result appears to be a very positive improvement in 
the computer code. 
The Center provided technical assistance to 28 Corps 
field offices; the Waterways Experiment Station; Headquarters, 
U. S. Army Corps of Engineers; and the Bureau 
of Reclamation during FY 1983. About one-third of the 
efforts were devoted to direct assistance to Corps field 
offices in the performance of these studies. HEC assisted 
four or more offices in each of the areas of real-time water 
control and data management, river hydraulics, and reservoir 
system analysis. Two offices were assisted in each 
of the areas of rainfall-runoff analysis, economic analysis, 
project formulation, and hydrodynamics. 
Twelve formal training courses involving 18 weeks of 
training were conducted at HEC for 336 Corps professionals. 
In addition, five weeks of special training, specifically 
requested by Corps field offices, were conducted 
for 161 Corps and other employees. Twenty-seven foreign 
visitors were hosted, mostly one-day visits except 
one UNESCO fellow who worked for six months. 
HEC will continue to emphasize the high-priority 
technical areas identified by HQ, USACE, and the field 
offices during FY 1984. Strong interest seems to continue 
in real-time water control activities, analytical 
techniques for planning (such as the geographic information 
system work), and water supply, both surface and 
groundwater. Also recent successes with two-dimensional 
hydrodynamic math models will encourage their application 
to complex river mechanics problems. 
INSTITUTE FOR WATER RESOURCES 
Organization and Functions 
The Institute for Water Resources (IWR), established 
in 1969, consists of three units: the Research Division, 
the Policy Studies Division, and the Navigation Division. 
IWR's mission is to perform research in planning 
methods, conduct policy studies, manage data systems 
for planning and operations, maintain a center of expertise 
on water transportation, manage national and special 
studies, train Corps personnel in water resources 
planning, and provide technical assistance on water 
resource related problems and studies confronting HQ, 
USACE, division and district offices, other government 
agencies, and foreign nations. 
Research 
The Research Division work in FY 1983 included development 
of water demand forecasting model for use in 
water supply and conservation studies, development of a 
deep draft navigation evaluation manual, and preparation 
of guidelines for evaluating nonstructural flood mitigation 
plans. Work continues in the areas of economic 
and demographic forecasting, economic effects of lock 
congestion, and flood damage assessment techniques. 
Work was initiated to determine the defense uses of civil 
works projects. 
The Institute's training program provides a means for 
transferring technical information and statef-the-art 
techniques to various Corps users. Courses inConflict 
Management and Economic Analysis for Wateresources 
Planning were initiated during the year. During FY 1983 
approximately 400 persons attended 10 sessions of eight 
training courses. 
Policy Studies 
The Policy Studies Division provides analysis and 
decision support on critical policy issues for the use of 
the Director of Civil Works through investigations in 
policy development, program management and evaluation 
methods and procedures, and new missions and 
strategic planning. Fiscal Year 1983 work included 
studies of permit enforcement, wetlands mitigation 
banking, project deauthorization review process, federal 
engineering activities, water conservation and supply 
mission, public port financing, and non-Federal financing 
techniques. Other studies included assessment of 
the Federal interest in various water programs and the 
responsiveness of civil works missions to local needs. 
Among studies involving evaluation of programs and 
methods were projects on the provision of planning information 
to non-Federal interests, the evaluation of 
unquantifiable amenities, and the update of data base 
on existing and potential hydropower projects. The 
53-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
state-of-the-art in planning for the implementing nonstructural 
flood control measures was the subject of an 
important seminar held in November. 
The Policy Studies Division has also assisted HQ, 
USACE, in several special studies: Emergency Water 
Planning and Chief of Engineers' Blue Ribbon Panels on 
Construction Quality and Engineering Capability and 
Planners' Training Needs. 
Navigation Division 
The Navigation Division was formed in 1983 by combining 
the Navigation Analysis Center and the National 
Waterways Study staff. The Navigation Division supports 
Corps planners by development and maintenance 
of transportation planning data bases on waterway 
carriers, other transportation modes, and commodity 
movements; development of analytical capabilities; and 
dissemination of technical information and advice with 
regard to use of navigation data and analytical techniques. 
The division also conducts policy studies and 
performs reimbursable and research studies for HQ, 
USACE, and field offices. 
One of the important data bases is the lock Performance 
Monitoring System (PMS), which contains information 
of Corps lock operations on the inland waterways. 
This data base enables Corps personnel to study lock 
operation and performance; to determine methods, benefits, 
and costs of improving the waterway system; to 
monitor traffic and commodities moving on the inland 
waterways; and the monitor conditions that could affect 
traffic flow. 
Vessel operating costs (ocean and inland), waterway 
and two characteristics, and the commodity and other 
economic projections are maintained to support various 
navigation systems studies. The Navigation Division 
has developed computer models to estimate economic 
development which would occur due to water resource 
and navigation projects, and supports the navigation 
user charge data base, which is used to estimate impacts 
of various cost recovery policies and strategies. 
53-4

APPENDIX A 
FLOOD CONTROL RESERVOIRS OPERABLE SEPTEMBER 30, 1983 
Permanent 
Pool 
Cal. Year Total (Acreage Characteristics of Dam 
Community Placed in Storage or No Project Height Length 
Name River Basin Stream in Vicinity Usetal Op. (Acre.Ft.) Pool (NPP) Functions Type (Feet) (Feet) 
Alaska 
Chena River Lakes Yukon-Kuskokwim 
Arizona 
Adobe 
Alamo 
Cave Buttes 
Painted Rock 
Dreamy Draw 
Tat Momolikot 
Whitlow Ranch 
Arkansas 
Blue Mountain 
DeQueen 
Dierks 
Gillham 
Millwood 
Nimrod 
California 
Gila 
Colorado 
Gila 
Gila 
Gila 
Gila 
Gila 
Arkansas 
Red 
Red 
Red 
Red 
Arkansas 
Black Butte Sacramento 
Brea Santa Ana 
Buchanan Dam- 
H.V. Eastman Lake San Joaquin 
Carbon Canyon Santa Ana 
Coyote Valley Russian 
Dry Creek 
(Warm Springs) 
Lake and Channel Russian 
Farmington San Joaquin 
Fullerton Santa Ana 
Hansen Los Angeles 
Harry L. Englebright Sacramento 
Hidden Dam- 
Hensley Lake San Joaquin 
Isabella San Joaquin 
Lopez Los Angeles 
Martis Creek Sacramento 
Merced County Stream Group: 
Bear San Joaquin 
Burns San Joaquin 
Mariposa San Joaquin 
Owens San Joaquin 
Mojave River Mojave 
New Hogan San Joaquin 
North Fork Sacramento 
Pine Flat San Joaquin 
Prado Santa Ana 
San Antonio Santa Ana 
Santa Fe San Gabriel 
Sepulveda Los Angeles 
Success San Joaquin 
Terminus San Joaquin 
Whittier Narrows San Gabriel 
Colorado 
Bear Creek 
Chatfield 
Cherry Creek 
John Martin 
Trinidad 
Connecticut 
Black Rock 
Colebrook River 
Hancock Brook 
Hop Brook 
Mansfield Hollow 
Northfield Brook 
Thomaston 
West Thompson 
Idaho 
Lucky Peak 
Missouri 
Missouri 
Missouri 
Arkansas 
Arkansas 
Housatonic 
Connecticut 
Housatonic 
Housatonic 
Thames 
Thames 
Housatonic 
Thames 
Columbia 
Chena River Fairbanks 
Skunk Creek Phoenix 
Bill Williams River Wenden 
Cave Creek Phoenix 
Gila River Gila Bend 
Dreamy Draw Phoenix 
Santa Rosa Wash Casa Grande 
Queen Creek Superior 
Petit Jean River Paris 
Rolling Fork River DeQueen 
Saline River Dierks 
Cossatot River Gillham 
Little River Ashdown 
Fourche La Fave River Plainview 
Stony Creek Orland 
Brea Creek Fullerton 
Chowchilla River Chowchilla 
Carbon Canyon Creek Brea 
East Fork Russian Ukiah 
River 
Dry Creek Healdsburg 
Littlejohn Creek Farmington 
East Fullerton Creek Fullerton 
Big Tujunga Wash Los Angeles 
Yuba River Maryaville 
Fresno River Madera 
Kern River Bakersfield 
Pacoima Wash San Fernando 
Martis Creek Reno 
Bear Creek Merced 
Burns Creek Merced 
Mariposa Creek Merced 
Owens Creek Merced 
Mojave Victorville 
Calaveras Valley Springs 
American River Auburn 
Kings River Piedra 
Santa Ana River Corona 
San Antonio Creek Upland 
San Gabriel River Duarte 
Los Angeles River Van Nuys 
Tule River Porterville 
Kaweah River Visalia 
San Gabriel River and El Monte 
Rio Hondo 
Bear Creek Denver 
South Platte River Denver 
Cherry Creek Denver 
Arkansas River Lamar 
Purgatoire River Trinidad 
Branch Brook Thomaston 
West Branch, Riverton 
Farmington River 
Hancock Brook Plymouth 
Hop Brook Middlebury 
Natchaug River Willimantic 
Northfield Brook Thomaston 
Naugatuck River Thomaston 
Quinebaug Thompson 
Boise River Boise 
1981 2,000 NPP FR Earth 
1982 18,350 NPP FR Earth 
1968 1,046,310 560 FRWX Earth 
1979 46,600 NPP FRX Earth 
1959 2,491,700 NPP FRWX Earth 
1973 320 NPP FRX Earth 
1974 198,550 NPP FWX Earth 
1960 35,590 NPP FX Earth 
50 40,200 
109 2,275 
283 975 
109 2,275 
181 4,780 
50 448 
75.5 12,500 
149 837 
1947 257,900 2,910 FRWX Earth 115 2,800 
1977 136,100 1,680 FSQRW Earth 160 2,360 
1975 96,800 1,360 FSRAW Earth & Rock 153 2,500 
1975 221,800 1,370 FSQW Earth & Rock 160 1,750 
1966 1,854,930 29,200 FWS Earth 88 17,554 
1942 336,010 3,550 FSWX Concrete 97 1,012 
1963 160,000 770 FIRX Earth 156 2,970 
1942 4,010 NPP FRX Earth 87 1,765 
1975 150,00 470 FIRW Earth & Rock 205.5 1,800 
1961 6,610 NPP FRX Earth 99 2,610 
1959 122,500 1,700 FRX Earth 160 3,500 
1983 381,000 500 FRSW Earth 319 3,000 
1952 52,000 NPP F Earth 60 7,800 
1941 760 NPP FRX Earth 46 575 
1940 26,690 120 FRWX Earth 97 10,475 
1941 69,000 400 DR Concrete 280 1,142 
1975 90,000 5,000 FIRW Earth 163 5,730 
1953 570,000 1,850 FIRW Earth 185 4,952 
1954 440 NPP FX Earth 50 1,300 
1971 20,400 71 FSR Earth 113 2,670 
1954 7,700 NPP F Earth 92 1,830 
1950 7,000 NPP F Earth 55 4,075 
1948 15,000 NPP F Earth 88 1,330 
1949 3,600 NPP F Earth 75 790 
1971 89,670 NPP FRWX Earth 200 2,200 
1963 325,000 715 FIRX Earth & Rock 210 1,960 
1939 14,700 280 DR Concrete 155 620 
1954 1,000,000 NPP FIRX Concrete 429 1,820 
1941 196,240 NPP FRX Earth 106 2,280 
1956 7,700 NPP FX Earth 160 3,850 
1948 32,100 NPP FRX Earth 92 23,800 
1941 17,430 NPP FRX Earth 57 15,444 
1960 85,000 400 FIRX Earth 142 3,490 
1961 150,00 345 FIRX Earth 250 2,375 
1957 35,150 NPP FRWX Earth 56 16,960 
1978 30,810 109 FRX Earth 180 5,300 
1974 231,429 1,412 FRX Earth 148 12,500 
1950 93,920 852 FRX Earth 141 14,300 
1948 615,500 NPP FIR Concrete & 106 13,274 
Earth 
1977 123,500 280 FIRX Earth 200 6,610 
1970 
1969 
1960 
1968 
1952 
1965 
1960 
1965 
8,700 20 FR Earth 
97,700 760 FRSX Earth 
4,030 40 FRW Earth 
6,970 21 FR Earth 
52,000 450 FRW Earth 
2,430 8 FRW Earth 
42,000 NPP F Earth 
26,800 200 FRW Earth 
1956 306,000 2,850 FIR Earth 
154 933 
223 1,300 
57 630 
97 520 
68 12,420 
118 810 
142 2,000 
70 2,550 
250 1,700 
A-1

APPENDIX A (Continued) 
FLOOD CONTROL RESERVOIRS OPERABLE SEPTEMBER 30, 1983 
Permanent 
Pool 
Cal. Year Total (Acreage) Characteristics of Dam 
Community Placed in Storage or No Project Height Length 
Name River Basin Stream in Vicinity Usefl Op. (Acre-Ft) Pool (NPP) Functions Type (Feet) (Feet) 
Illinois 
Carlyle 
Farmdale 
Fondulac 
Shelbyville 
Rend Lake 
' Indiana 
Brookville 
Cagles Mill 
Cecil M. Harden 
Huntington 
Mississinewa 
Monroe 
Patoka 
Salamonie 
Iowa 
Coralville 
Rathbun 
Red Rock 
Saylorville 
Kansas 
Clinton 
Council Grove 
El Dorado 
Elk City 
Fall River 
Hillsdale 
John Redmond 
Kanopolis 
Marion 
Melvern 
Milford 
Pearson Skubitz Big Hill 
Perry 
Pomona 
Toronto 
Tuttle Creek 
Wilson 
Kentucky 
Barren River 
Buckhorn 
Carr Fork 
Cave Run 
Dewey 
Fishtrap 
Grayson 
Green River 
Martins Fork 
Paintsville 
Nolin 
Rough River 
Taylorsville 
Louslalana 
Bayou Bodcau 
Caddo Lake 
Wallace Lake 
Maryland 
Bloomington Lake 
Massachusetts 
Barre Falls 
Birch Hill 
Buffumville 
Connant Brook 
East Brimfield 
Hodges Village 
Knightville 
Littleville 
Upper Mississippi 
Upper Mississippi 
Upper Missiasippi 
Upper Mississippi 
Upper Mississippi 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Upper Mississippi 
Missouri 
Upper Mississippi 
Upper Mississippi 
Missouri 
Arkansas 
Arkansas 
Arkansas 
Arkansas 
Missouri 
Arkansas 
Missouri 
Arkansas 
Missouri 
Missouri 
Arkansas 
Missouri 
Missouri 
Arkansas 
Missouri 
Missouri 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Cumberland 
Ohio 
Ohio 
Ohio 
Ohio 
Red 
Red 
Red 
Potomac 
Connecticut 
Connecticut 
Thames 
Connecticut 
Connecticut 
Connecticut 
Connecticut 
Connecticut 
Kaskaskia River 
Farm Creek 
Fondulac Creek 
Kaskaskia River 
Big Muddy River 
East Fork of 
Whitewater River 
Mill Creek 
Raccoon Creek 
Wabash River 
Mississinewa 
Salt Creek 
Patoka River 
Salamonie 
Iowa River 
Chariton River 
Des Moines River 
Des Moines River 
Wakarusa River 
Grand (Neosho) 
Walnut River 
Elk River 
Fall River 
Big Bull Creek 
Grand (Neosho) 
Smoky Hill River 
Cottonwood River 
Marias Des Cygnes 
Republican River 
Big Hill Creek 
Delaware River 
110 Mile Creek 
Verdigris River 
Big Blue River 
Saline River 
Barren River 
Middle Fork of 
Kentucky River 
Carr Fork 
Licking River 
Johns Creek 
Levisa Fork, 
Big Sandy River 
Little Sandy 
Green River 
Martins Fork 
Paint Creek 
Nolin River 
Rough River 
Salt River 
Rayou Bodcau 
Cypress Bayou 
Cypress Bayou 
North Branch 
Potomac River 
Ware River 
Millers River 
Little River 
Conant Brook 
Quinebaug River 
French River 
Westfield River 
Middle Branch, 
Westfield River 
Carlyle 
East Peoria 
East Peoria 
Shelbyville 
Benton 
Brookville 
Terre Haute 
Rockville 
Huntington 
Peru 
Harrodsburg 
Ellsworth 
Wabash 
Iowa City 
Centerville 
Des Moines 
Des Moines 
Lawrence 
Council Grove 
El Dorado 
Independence 
Fall River 
Kansas City 
Burlington 
Salina 
Marion 
Melvern 
Junction City 
Cherryvale 
Perry 
Pomona 
Toronto 
Manhattan 
Wilson 
Glasgow 
Buckhorn 
Hazard 
Farmers 
Paintaille 
Pikeville 
Grayson 
Campbellsville 
Harlan 
Paintsville 
Kyrock 
Leitchfleld 
Tayloreville 
Shreveport 
Shreveport 
Shreveport 
Barnum 
Barre 
So. Royalaton 
Charlton 
Monson 
Fiskdale 
Oxford 
Huntington 
Chester 
1967 
1951 
1951 
1970 
1970 
1974 
1952 
1960 
1969 
1967 
1964 
1978 
1966 
1958 
1969 
1969 
1975 
1977 
1964 
1981 
1966 
1949 
1981 
1963 
1948 
1968 
1972 
1965 
1981 
1969 
1963 
1960 
1962 
1964 
1964 
1960 
1976 
1974 
1949 
1968 
1967 
1969 
1978 
1983 
1963 
1958 
1983 
983,000 26,000 FSNRWA Earth 
15,500 NPP F Earth 
3,780 NPP F Earth 
684,000 11,100 FSNRW Earth 
294,000 18,900 FQRSW Earth 
67 6,570 
80 1,275 
67 1,000 
108 3,000 
54 10,600 
359,600 2,250 FRSW Earth & Rock 182 3,000 
228,120 1,400 FRX Earth 150 950 
132,800 1,100 FRX Earth 117 1,790 
153,100 500 FRW Earth 91 ,332 
368,400 1,100 FRW Earth 137 8,100 
441,000 3,280 FARS Earth 93 1,400 
301,600 2,010 FRSQW Earth & Rock 84 1,550 
263,600 976 FRW Earth 133 6,100 
492,000 1,820 FARW Earth 
552,000 11,000 FNRWXQ Earth 
1,830,000 8,950 FARWQ Earth 
602,000 74,000 FARWQ Earth 
100 1,400 
86 10,600 
110 5,676 
125 6,750 
397,200 7,00 FSWAXR Earth 114 9,250 
112,265 3,235 FSQR Earth 96 6,500 
236,200 8,000 FSQR Earth 99 20,930 
284,300 4,450 FSQ Earth 107 4,840 
256,400 2,350 FSX Earth 94 6,015 
160,00 4,580 FSQR Earth 75 11,600 
630,250 9,280 FSQR Earth 86.5 21,790 
450,000 3,815 FRWX Earth 131 15,360 
143,850 6,200 FRQS Earth 67 8,375 
363,000 6,930 FRQWX Earth 98 9,700 
1,160,000 15,600 FRSXWQ Earth & Rock 126 6,300 
40,600 1,240 FSR Earth 83 3,870 
770,000 12,200 FRSXW Earth & Rock 95 7,750 
230,000 4,000 FRSWXQ Earth & Rock 85 7,750 
200,800 2,660 FX Earth 90 4,712 
2,346,000 15,800 FRWXQAN Earth & Rock 157 7,500 
776,000 9,000 FIRWXNA Earth 160 5,600 
815,200 4,340 FARS Earth 146 3,970 
168,000 550 FR Earth 162 1,020 
47,700 530 FQRW Earth & Rock 130 720 
614,100 6,790 FQRW Earth & Rock 148 2,740 
93,000 1,100 FARW Earth 118 918 
164,360 569 FARW Rock 195 1,100 
118,990 1,050 FORW Earth & Rock 120 1,460 
723,200 5,070 FRSQW Earth & Rock 142 2,350 
21,000 578 FQ Concrete 97 574 
73,500 261 FQRW Earth & Rock 160 1,600 
609,400 2,890 FAR Earth & Rock 174 990 
334,400 2,180 FRX Earth & Rock 124 1,530 
291,670 1,625 FQRW Earth & Rock 164 1,280 
1949 357,300 NPP FRW 
1971 175,000 32,700 NFRS 
1946 88,300 2,300 FR 
1981 130,900 
1958 
1941 
1958 
1966 
1960 
1959 
1941 
1965 
Earth 
Concrete & 
Earth 
Earth 
76 12,850 
3,600 
48 4,934 
952 FQRS Earth & Rock 296 2,130 
24,00 NPP FRW Earth & Rock 62 885 
49,900 NPP FRW Earth & Rock 56 1,400 
12,700 200 FRW Earth & Rock 66 3,255 
3,740 NPP F Earth & Rock 85 1,050 
30,000 360 FRW Earth & Rock 55 520H 
12,800 NPP FRW Earth & Rock 55 2,140 
49,000 NPP FRW Earth & Rock 160 1,200 
32,400 275 FRWS Earth & Rock 164 1,360 
A-2

APPENDIX A (Continued) 
FLOOD CONTROL RESERVOIRS OPERABLE SEPTEMBER 30, 1983 
Permanent 
Pool 
Cal. Year Total (AcreageP Characteristics of Dam 
Community Placed in Storage or No Project Height Length 
Name River Basin Stream in Vicinity Useful Op. (Acre-Ft.) Pool (NPP) Functions Type (Feet) (Feet) 
Massachusetts (Continued) 
Tully River Fryville 
West River Uxbridge 
Quinebaug River Sturbridge 
1949 23,000 300 FRW Earth & Rock 62 1,570 
1960 12,350 NPP FRW Earth & Rock 51 2,400 
1961 11,100 23 FRW Earth & Rock 78 560 
Big Stone Lake- 
Whetstone River Upper Mi 
Lac Qui Parle Chippewa 
River Upper Mi 
Lac Qui Parle Upper Mi 
Marsh Lake Upper Mi 
Orwell Red Rive 
Red Lake Red Rivei 
Mississippi 
Arkabutla Lake Lower Mi 
Enid Lake Lower Mi 
Grenada Lake Lower Mi 
Okatibbee Pascagou 
Sardis Lake Lower Mi 
Missouri 
Clearwater White 
Long Branch Grande C 
Pomme de Terre Missouri 
Smithville Missouri 
Wappapello Lower Mi 
Nebraska 
Harlan County Missouri 
Papillion Creek and Tributaries: 
Glenn Cunningham 
(Site 11) Missouri 
Standing Bear Lake 
(Site 16) Missouri 
Salt Creek & Tributaries: 
Olive Creek (Site 2) Missouri 
Blue Stem (Site 4) Missouri 
Wagon Train (Site 8) Missouri 
Stagecoach (Site 9) Missouri 
Yankee Hill (Site 10) Missouri 
Conestoga (Site 12) Missouri 
Twin Lake (Site 13) Missouri 
Pawnee (Site 14) Missouri 
Holmes Park Lake 
(Site 17) Missouri 
Branched Oak (Site 18) Missouri 
ississippi Minnesota River 
ississippi Chippewa River 
ississippi Minnesota River 
ississippi Minnesota River 
r of the North Otter Tail River 
r of the North Red Lake River 
ississippi 
ississippi 
ississippi 
la 
ississippi 
hariton 
issiuippi 
New Hampshire 
Blackwater Merrimack 
Edward MacDowell Merrimack 
Franklin Falls Merrimack 
Hopkinton-Everett Merrimack 
Merrimack 
Otter Brook Connecticut 
Surry Mountain Connecticut 
Nevada 
Mathews Canyon 
Pine Canyon 
New Mexico 
Abiquiu 
Cochiti 
Conchas 
Galisteo 
Jemes Canyon 
Two Rivers: 
Diamond "A" Dam 
Rocky Dam 
Santa Rosa Dam & 
Reservoir 
Colorado 
Colorado 
Rio Grande 
Rio Grande 
Arkansas 
Rio Grande 
Rio Grande 
Rio Grande 
Rio Grande 
Pecos 
Ortonville 
Montevideo 
Montevideo 
Montevideo 
Fergus Falls 
Red River 
Coldwater River Arkabutla 
Yocona River Enid 
Yalobusha River Grenada 
Okatibbee Creek Meridian 
Little Tallahatchie River Sardis 
Black River Piedmont 
Little Chariton Macon 
Pomme de Terre River Hermitage 
Little Platte River Smithville 
St. Francis River Wappapello 
Republican River Republican City 
Knight Creek Omaha 
Trib. of Big Papillion Omaha 
Creek 
S. Trib. Olive Br. Creek Kramer 
N. Trib. Olive Br. Creek Sprague 
N. Trib. Hickman Creek Holland 
S. Trib. Hickman Creek Hickman 
Cardwell Creek Denton 
Holmes Creek Denton 
Middle Creek Pleasantdale 
N. Middle Creek Emerald 
Antelope Creek Lincoln 
Oak Creek Raymond 
Blackwater River 
Nubanusit Brook 
Pemigewasset River 
Contoocook River 
Piscataquog River 
Otter Brook 
Ashuelot River 
Webster 
West Perterborough 
Franklin 
West Hopkinton 
East Weare 
Keene 
Keene 
Mathews Canyon Caliente 
Pine Canyon Caliente 
Rio Chama 
Rio Grande 
Canadian River 
Galisteo Creek 
Jemez River 
Rio Hondo 
Rocky Arroyo 
Pecos 
Abiquiu 
Pena Blanca 
Tucumcari 
Albuquerque 
Bernalillo 
Roswell 
Santa Rosa 
1973 
1950 
1950 
1950 
1953 
1951 
45,000 
(1) 
122,800 
35,000 
14,100 
2,680,000 
1943 525,300 
1951 660,000 
1954 1,337,400 
1969 142,400 
1940 1,570,000 
1948 413,700 
1980 65.]] 
1961 650,000 
1982 246,500 
1941 613,200 
5,470 
10,260 
9,280 
6,640 
7,560 
10,640 
8,080 
29,520 
6,510 
97,560 
46,000 
12,800 
154,000 
71,500 
87,500 
18,300 
32,500 
12,700 FRW 
NPP FRWX 
6,500 FRWX 
5,100 FRWX 
210 FARS 
279,000 FARSX 
5,100 FRSW 
6,100 FRSW 
9,800 FRSW 
1,280 FQSR 
10,700 FRSW 
1,630 FRWX 
2,430 FRSQW 
7,820 FRWX 
7,190 FSQRW 
4,100 FR 
1952 850,000 13,600 FIRWX 
1975 
1973 
1964 
1963 
1963 
1964 
1966 
1964 
1966 
1965 
1963 
1968 
1941 
1950 
1943 
1962 
1962 
1958 
1941 
174 FR 
315 FR 
303 FR 
196 FR 
208 FR 
230 FR 
255 FR 
729 FR 
100 FR 
1,780 FR 
NPP FRW 
NPP FRW 
NPP FRW 
200 FRW 
120 FRW 
85 FRW 
265 FRW 
Earth 
Earth & Rock 
Earth & Rock 
Earth & Rock 
Earth & Rock 
Earth & Rock 
Earth & Rock 
Earth & Rock 
Earth & Rock 
Earth 
Earth & Rock 
Earth & Rock 
Earth 
Earth & Rock 
Earth 
Earth & Rock 
25 13,700 
23.5 17,975 
21 41,000 
19.5 11,800 
47 1,355 
15.5 36,500 
95 
99 
102 
67 
117 
154 
71 
155 
95 
109 
11,500 
8,400 
13,900 
6,543 
15,300 
4,225 
3,800 
4,630 
4,200 
2,700 
Earth & Rock 107 11,827 
67 
70 
45 
57 
52 
48 
52 
63 
58 
65 
55 
70 
75 
67 
140 
76 
115 
133 
86 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
1967 6,270 NPP FX Earth 
1957 7,750 NPP FX Earth 
1963 
1975 
1939 
1970 
1963 
1963 
1,212,000 
596,300 
529,000 
89,000 
106,100 
168,000 
NPP FX 
1,161 FRWX 
3,000 FIl 
NPP FX 
286 FX 
NPP F 
Earth 
Earth 
Concrete & 
Earth 
Earth 
Earth 
Earth 
1979 447,000 NPP FIX Earth 
1,940 
1,460 
3,020 
2,760 
1,650 
2,250 
3,100 
3,000 
2,075 
5,000 
7,700 
5,200 
1,150 
1,030 
1,740 
790 
2,000 
1,288 
1,670 
71 800 
92 884 
325 
251 
200 
158 
135 
96 
118 
212 
1,540 
28,300 
19,400 
2,820 
70 
4,885 
2,940 
1,950 
A-3 
Tully 
West Hill 
Westville 
Minnesota 
Connecticut 
Blackstone 
Thames 
17,910 392 FQRX Earth 
5,220 137 FRX Earth

APPENDIX A (Continued) 
FLOOD CONTROL RESERVOIRS OPERABLE SEPTEMBER 30, 1983 
Permanent 
Pool 
Cal. Year Total (Acreage ) Characteristics of Dam 
Community Placed in Storage or No Project Height Length 
Name River Basin Stream in Vicinity Useful Op. (Acre-Ft.) Pool (NPP) Functions Type (Feet) (Feet) 
New York 
Almond Susquehanna 
Arkport Susquehanna 
East Sidney Susquehanna 
Mount Morris Genesee 
Whitney Point Susquehanna 
North Carolina 
B. Everett Jordan Cape Fear 
Falls Neuse 
W. Kerr Scott Yadkin-Pee Dee 
North Dakota 
Baldhill 
Bowman-Haley 
Homme 
Pipestem 
Ohio 
Canacadea Creek Hornell 
Canisteo Creek Hornell 
Ouleout Creek Sidney 
Genesee River Mount Morris 
Otelic River Binghamton 
New Hone 
Neuse 
Yadkin 
Durham 
Raleigh 
Wilkeeboro 
Red River of the North Sheyenne River Valley City 
Missouri North Fork, Grand River Haley 
Red River of the North South Branch of Park Park River 
River 
James River Pipestem Creek Jamestown 
Alum Creek Ohio 
Berlin Ohio 
Caesar Creek Ohio 
Clarence J. Brown Ohio 
Deer Creek Ohio 
Delaware Ohio 
Dillon Ohio 
Michael J. Kirwan Ohio 
Mosquito Creek Ohio 
Muskingum River Reservoirs: 
Atwood Ohio 
Beach City Ohio 
Bolivar Ohio 
Charles Mill Ohio 
Clendening Ohio 
Dover Ohio 
Leesville Ohio 
Mohawk Ohio 
Mohicanville Ohio 
Piedmont Ohio 
Pleasant Hill Ohio 
Senecaville Ohio 
Tappan Ohio 
Wills Creek Ohio 
North Branch, 
Kokosing River Lake Ohio 
Paint Creek Ohio 
Tom Jenkins Ohio 
West Fork Mill Creek Ohio 
William H. Harsha Ohio 
Oklahoma 
Birch Arkansas 
Canton Arkansas 
Copan Arkansas 
Fort Supply Arkansas 
Great Salt Plains Arkansas 
Heyburn Arkansas 
Hugo Red 
Hulah Arkansas 
Kaw Arkansas 
Oologah Arkansas 
Optima Arkansas 
Pine Creek Red 
Sardis Red 
Waurika Red 
Wister Arkansas 
Oregon 
Alum Creek Africa 
Mahoning River Deerfield 
Caesar Creek Wilmington 
Buck Creek Springfield 
Deer Creek New Holland 
Olentangy River Delaware 
Licking River Zanesville 
West Branch, Newton Falls 
Mahoning River 
Mosquito Creek Cortland 
Indian Fork New Cumberland 
Sugar Creek Beach City 
Sandy Creek Bolivar 
Black Fork Muffin 
Brushy Fork Tippecanoe 
Tuscarawas River Dover 
McGuire Creek Leesville 
Walhonding River Nellie 
Lake Fork Mohicanville 
Stillwater Creek Piedmont 
Clear Fork Perrysville 
Seneca Fork Senecaville 
Little Stillwater Creek Tappan 
Wills Creek Conesville 
North Branch of 
Kokosing River Fredericktown 
Paint Creek New Petersburg 
East Branch, Gloucester 
Sunday Creek 
Mill Creek Mount Healthy 
Little Miami River Williamsburg 
Birch Creek Barnedall 
North Canadian River Canton 
Little Caney River Copan 
Wolf Creek Fort Supply 
Salt Fork, Cherokee 
Arkansas River 
Polecat Creek Sapulpa 
Kiamichi River Hugo 
Caney River Caney 
Arkansas River Ponca City 
Verdigris River Oologah 
North Canadian River Hardesty 
Little River Wright City 
Jackfork Creek Clayton 
Beaver Creek Waurika 
Poteau River Wister 
1949 14,800 124 FRW Earth 90 1,260 
1939 7,900 NPP F Earth 113 1,200 
195 33,500 210 FRW Concrete & 130 2,010 
Earth 
1952 337,000 170 FR Concrete 210 1,028 
1942 86,440 1,200 FRW Earth 95 4,900 
1982 778,000 14,300 FQRSWX Earth 
1983 397,000 12,490 FQRSWX Earth 
1963 153,000 1,470 FARSX Earth 
1950 70,000 325 FARS Earth 
1967 92,980 1,750 FSRWX Earth 
1951 3,650 51 FARS Earth 
1974 146,880 885 FRWX Earth 
112 1,330 
92 1,915 
148 1,740 
61 1,650 
79 5,730 
67 865 
108 4,000 
1975 134,800 348 FRSW Concrete & 93 10,000 
Earth 
1943 91,200 240 FARSWQ Concrete & 96 5,750 
Earth 
1978 242,200 13,300 FRSQW Earth & Rock 165 2,750 
1974 63,700 1,010 FQRW Earth & Rock 72 62,620 
1968 102,500 727 FRW Earth 93 3,880 
1951 132,000 950 FARWX Earth 92 18,600 
1961 273,000 1,325 FRWX Earth 118 1,400 
1966 78,700 580 FAQRSW Earth 83 9,900 
1944 104,100 700 FARSWQ Earth 47 5,650 
1937 49,700 1,540 FRX Earth 65 3,700 
1937 71,700 420 FRX Earth 64 5,600 
1938 149,600 NPP FR Earth 87 6,300 
1936 88,000 1,350 FRX Earth 48 1,390 
1937 54,000 1,800 FRX Earth 64 950 
1938 203,000 350 FRX Concrete 83 824 
1937 37,400 1,000 FRX Earth 74 1,694 
1937 285,000 NPP FR Earth 111 2,330 
1936 102,000 NPP FR Earth 46 1,220 
1937 65,000 2,270 FRX Earth 56 1,750 
1938 87,700 850 FRX Earth 113 775 
1937 88,500 3,550 FRSX Earth 45 2,350 
1936 61,600 2,350 FRX Earth 52 1,550 
1937 196,000 900 FRX Earth 87 1,950 
1973 14,900 98 FRW Earth 71 1,400 
1972 145,000 710 FRSQW Earth & Rock 118 700 
1951 26,900 394 FRSWX Concrete 84 944 
1952 11,380 200 FRX Earth 100 1,100 
1978 284,500 18,760 FRSQW Earth 200 1,450 
1977 58,200 1,137 FSQRW Earth 
1948 377,100 7,910 FSI Earth 
1983 227,700 4,850 FSQRW Earth 
1942 100,700 1,820 FSX Earth 
1941 271,400 8,690 FRWX Earth 
1950 55,030 920 FRWXS Earth 
1974 966,700 13,250 FSQRW Earth 
1951 289,000 3,570 FSAX Earth 
1976 1,348,000 17,040 FFSQRW Earth 
1963 1,519,000 29,460 FSN Earth 
1978 229,500 5,340 FSRW Earth 
1969 465,780 3,750 FSQW Earth 
1983 429,600 14,360 FSRW Earth 
1977 343,500 10,100 FSQWR Earth 
1949 427,900 5,360 FSAX Earth 
97 3,193 
73 15,140 
70 7,730 
85 12,225 
68 6,010 
89 2,920 
101 10,200 
94 5,200 
125 9,466 
137 4,000 
120 15,200 
124 7,712 
81 14,138 
106 16,600 
99 5,700 
Applegate River 
Blue River 
Coast Fork, 
Willamette River 
Medford 
Blue River 
Cottage Grove 
1981 82,000 988 AFIQRSW Gravel Em- 242 1,300 
bankment 
1968 85,000 975 FINR Earth 319 1,329 
1942 30,060 1,155 FINR Concrete & 114 2,110 
Earth 
A-4 
Applegate 
Blue River 
Cottage Grove 
Rogue River 
Columba 
Columbia

APPENDIX A (Continued) 
FLOOD CONTROL RESERVOIRS OPERABLE SEPTEMBER 30, 1983 
Permanent 
Pool 
Cal. Year Total (Aereae Characterlstlies of Dam 
Community Placed in Storage or No Project Height Length 
Name River Basin Stream in Vicintty Useful Op. (Acre-Ft.) Pool (NPP) Functions Type (Feet) (Feet) 
Oregon (Continued) 
Dorena 
Fall Creek 
Fern Ridge 
Willow Creek 
Columbia 
Columbia 
Columbia 
Columbia 
Pennsylvania 
Alvin R. Bush Susquehanna 
Aylesworth Creek Susquehanna 
Beltzville Delaware 
Blue Marsh Delaware 
Conemaugh Ohio 
Cowanesque Susquehanna 
Crooked Creek Ohio 
Curweneville Susquehanna River 
East Branch, 
Clarion River Ohio 
Foster Joseph Sayers Susquehanna 
Francis E. Walter 
(Bear Creek) Delaware 
Gen. Edgar Jadwin Delaware 
Indian Rock Susquehanna 
Kinzua Ohio 
Loyalhanna Ohio 
Mahoning Creek Ohio 
Prompton Delaware 
Raystown Suaquehanna 
Shenango Ohio 
Stillwater Susquehanna 
Tioga-Hammond Lakes Susquehanna 
Tionesta Ohio 
Union City Ohio 
Woodcock Creek Ohio 
Youghiogheny River Ohio 
South Dakota 
Cold Brook Missouri 
Cottonwood Springs Missouri 
Lake Traverse: 
Reservation Control 
Dam Red River 
White Rock Red River 
Texas 
Addicks San Jacinto 
Bardwell Trinity 
Barker San Jacinto 
Belton Brazos 
Benbrook Trinity 
Canyon Guadalupe 
Ferrells Bridge Dam- 
Lake O' the Pines Red 
Granger Dam and Lake Brazos 
Grapevine Trinity 
Herds Creek Colorado 
Lake Kemp Red 
Lavon Trinity 
Lewieville Trinity 
Navarro Mills Trinity 
North San Gabriel Dam, 
Lake Georgetown Brasoe 
O. C. Fisher Colorado 
Pat Mayse Red 
Proctor Brazos 
Somerville Brazos 
Stillhouse Hollow Brazose 
Waco Brazose 
Wright Patman Red 
Row River 
Middle Fork, 
Willamette River 
Long Tom River 
Willow Creek 
Cottage Grove 
Eugene 
Eugene 
Heppner 
Kettle Creek Renovo 
Aylesworth Creek East Jermyn 
Pohopoco Lehighton 
Tulephocken Reading 
Conemaugh River Salteburg 
Cowanesque River Lawrenceville 
Crooked Creek Ford City 
West Branch, Clearfield 
Susquehanna River 
East Branch, 
Clarion River Wilcox 
Bald Eagle Creek Blanchard 
Lehigh River Wilkes-Barre 
Dyberry Creek Honesdale 
Codorus Creek York 
Allegheny River Warren 
Loyalhanna Creek Salteburg 
Mahoning Creek New Bethlehem 
Lackawaxen River Honesdale 
Raystown Branch, Huntingdon 
Juniata River 
Shenanago River Sharpsville 
Lackawanna River Forest City 
Tioga River Tioga 
Crooked Creek Tioga 
Tionesta Creek Tionesta 
French Creek Union City 
French Creek Meadville 
Youghiogheny River Confluence 
Cold Brook Hot Springs 
Cottonwood Springs Hot Springs 
Creek 
r of the North Bois de Sioux River Wheaton 
r of the North Bois de Sioux River Wheaton 
South Mayde Creek Addicks 
Waxahachie Creek Ennis 
Buffalo Bayou Barker 
Leon River Belton 
Clear Fork, Trinity River Fort Worth 
Guadalupe New Braunfels 
Cypress Creek Jefferson 
San Gabriel River Granger 
Denton Creek Grapevine 
Hords Creek Coleman 
Wichita River Wichita Falls 
East Fork, Trinity River Fort Worth 
Elm Fork, Trinity River Lewisville 
Richland Creek Corsicana 
North Fork, Georgetown 
San Gabriel River 
North Concho River San Angelo 
Sanders Creek Paris 
Leon River Comanche 
Yegua Creek Somerville 
Lampasas River Belton 
Bosque River Waco 
Sulphur River Texarkana 
1949 
1965 
1941 
1983 
1962 
1970 
1971 
1979 
1952 
1980 
1940 
1965 
1952 
1969 
1961 
1969 
1942 
1965 
1942 
1941 
1960 
1978 
1966 
1960 
1979 
1979 
1940 
1970 
1973 
1943 
70,500 8,885 FINR Concrete & 145 3,352 
Earth 
115,000 1,865 FINR Rockflll & 193 5,100 
Concrete 
110,000 10,305 FINE Rockflll & 49 6,624 
Concrete 
183,250 96 FRN Roller 160 1,780 
Compacted 
Concrete 
75,000 160 FEW Earth & Rock 165 1,850 
1,760 NPP F Earth & Rock 90 1,270 
68,250 947 FQRSW Earth & Rock 170 4,200 
500,000 22,900 FAQRS Earth 98 1,775 
274,000 300 F Concrete & 137 1,265 
Earth 
89,000 410 FR Earth & Rock 151 3,100 
93,900 350 FRW Earth 143 1,480 
124,200 790 FR Earth 131 2,850 
84,300 90 FARQ Earth 184 1,725 
99,000 1,730 FRW Earth 100 6,835 
110,000 90 FNRW Rockflll 263 3,500 
24,500 NPP F Earth 109 1,255 
28,000 NPP FRW Earth 83 1,000 
1,180,000 1,900 PFAQR Concrete & 177 1,877 
Earth 
95,300 210 FRW Concrete & 144 960 
Earth 
74,200 170 FEW Concrete 162 926 
52,000 290 FNRW Earth 140 1,230 
762,000 8,300 FRW Earth & Rock 225 1,700 
191,400 1,910 FAQRW Concrete 68 720 
12,000 85 FS Earth 77 1,700 
62,000 470 FR Earth & Rock 140 2,738 
63,000 680 FR Earth & Rock 122 6,000 
133,400 480 FRW Earth 154 1,050 
47,640 NPP F Earth 88 1,420 
20,000 118 FQRA Earth 90 4,650 
254,000 450 FARWQ Earth 184 1,610 
1953 7,200 36 FRWX Earth 
1970 8,385 41 FRWX Earth 
1941 164,500 10,925 FRX Earth 
1941 85,000 6,500 FRX Earth 
1948 
1965 
1945 
1954 
1952 
1964 
1959 
1980 
1952 
1948 
1972 
1953 
1954 
1962 
1980 
1952 
1967 
1963 
1967 
1968 
1965 
1957 
127 925 
123 1,190 
14 9,100 
16 14,400 
204,500 NPP FX Earth 49 61,166 
140,000 8,570 FRSX Earth 82 15,400 
207,000 NPP FX Earth 37 72,844 
1,097,600 12,800 FIRSX Earth 192 5,524 
258,600 3,770 FNRXA Earth 180 9,130 
740,900 8,240 FRSX Earth 224 6,830 
842,100 18,700 FRS Earth 97 10,600 
244,200 4,400 FRSWX Earth 115 16,20 
425,00 7,280 FNRSXA Earth 137 12,850 
25,310 510 FARSX Earth 91 6,800 
502,900 15,590 FX Earth & Rock 115 8,890 
748,200 21,400 FRSX Earth 81 19,483 
989,700 23,280 FRSX Earth 125 32,888 
212,200 5,070 FRSX Earth 82 7,570 
130,800 1,310 FRSWX Rock 164 6,700 
396,400 5,440 FRSX Earth 128 40,885 
189,100 5,993 FRSX Earth 96 7,060 
374,200 4,610 FRSX Earth 86 13,480 
507,500 11,460 FRSX Earth 80 26,175 
630,400 6,430 FRSX Earth 200 15,624 
726,400 7,270 FRSX Concrete & 140 24,618 
Earth 
2,654,300 20,300 FRSX Earth 100 18,500 
A-5

APPENDIX A (Continued) 
FLOOD CONTROL RESERVOIRS OPERABLE SEPTEMBER 30, 1983 
Permanent 
Pool 
Cal. Year Total (Acreage) Characteristics of Dam 
Community Placed in Storage or No Project Height Length 
Name River Basin Stream in Vicinity Useful Op. (Acre-Ft.) Pool (NPP) Functions Type (Feet) (Feet) 
Vermont 
Ball Mountain Connecticut West River Jamaica 1961 54,600 75 FRW Concrete & 265 915 
Earth 
North Hartland Connecticut Ottauguechee River North Hartland 1960 71,420 220 FRW Concrete & 185 1,520 
Earth 
North Springfield Connecticut Black River Springfield 1960 51,067 290 FRW Concrete & 120 2,940 
Earth 
Townshend Connecticut West River Townshend 1961 33,700 100 FRW Concrete & 133 1,700 
Earth 
Union Village Connecticut Ompompanoosuc River Union Village 1950 38,000 NPP FRW Concrete & 
Earth 170 1,100 
John W. Flannagan Ohio Pound River Haysi 1963 145,700 310 FAQR Concrete & 250 960 
Gathright Dam &E 
Lake Moomaw James Jackson Alleghany 1979 123,739 2,532 FQR Earth & Rock 257 1,172 
North Fork of 
Pound River Ohio North Fork, Pound River Pound 1966 11,293 106 FR Rock 122 600 
Washington 
Howard A. Hanson Green Green River Kanaskat 1961 106,000 1,600 FAs Rock 235 675 
Mill Creek Columbia Mill Creek Walla Walla 1942 8,300 225 FR Earth 145 3,200 
Mud Mountain Puyallup White River Enumclaw 1953 106,000 NPP FR Rock 425 700 
Wynoochee Chehalis Wynoochee River Montesano 1972 70,000 1,150 FSARI Concrete & 177 1,700 
Earth 
West Virginia 
Beech Fork Ohio Beech Fork Lavalette 1977 37,540 450 FRW Earth 86 1,080 
Bluestone Ohio New River Hinton 1952 631,000 1,800 FRWX Concrete 180 2,048 
Burnsville Ohio Little Kanawha Burnsville 1977 65,400 550 FQRW Earth & rock 89 1,400 
East Lynn Ohio Twelve Pole Creek East Lynn 1970 82,500 823 FQRW Earth & Rock 122 650 
R. D. Bailey Ohio Guynabdot River Justice 1979 203,700 440 FQRW Earth & Rock 310 1,397 
Summersville Lake Ohio Gauley River Summersville 1965 413,800 407 FANR Rock 390 2,280 
Sutton Ohio Elk River Sutton 1960 265,300 270 FARWX Concrete 220 1,178 
Tygart River Ohio Tygart River Grafton 1938 287,700 620 FNAR Concrete 230 1,921 
Wisconsin 
Eau Galle Chippewa Eau Galle Spring Valley 1969 43,600 150 FR Earth 122 1,600 
FLOOD CONTROL RESERVOIRS CONSTRUCTED OR CONTRIBUTED TO 
BY CORPS OF ENGINEERS BUT OPERATED BY OTHERS 
SEPTEMBER 30, 1983 
Permanent 
Pool 
Cal. Year Total (Acreage) Characteristics of Dam 
Community Placed in Storage or No Project Height Length 
Name River Basin Stream in Vicinity Useful Op. (Acre-Ft.) Pool (NPP) Functions Type (Feet) (Feet) 
Arizona 
California 
Big Dry Creek San Joaquin 
Camanche' San Joaquin 
Cherry Valley* Tuolumne 
Del Valle Alameda 
Eaton Wash Rio Hondo 
New Bullards Bar' Sacramento 
New Don Pedro' San Joaquin 
New Exchequer' San Joaquin 
Oroville' Sacramento 
Tahchevah Creek Whitewater 
Colorado 
Pinon Canyon 
Connecticut 
Colorado 
East Branch Housatonic 
Hall Meadow Brook Housatonic 
Mad River Connecticut 
Sucker Brook Connecticut 
Big Dry Creek Fresno 
Mokelumne River Clements 
Cherry Creek Sonora 
Arroyo Del Valle Livermore 
Eaton Wash Pasadena 
Yuba River Marysville 
Tuolumne River Modesto 
Merced River Merced 
Feather River Oroville 
Tahchevah Creek Palm Springs 
Pinon Canyon Arroyo Trinidad 
East Branch, Torrington 
Naugatuck River 
Hall Meadow Brook Torrington 
Mad River Winchester 
Sucker Brook Winchester 
1948 16,250 NPP F Earth 40 20,038 
1963 431,500 NPP FRS Earth & Rock 171 2,450 
1956 268,000 475 FS Earth & Rock 315 2,500 
1968 77,000 200 FRS Earth 223 880 
1937 960 NPP F Earth 82 1,795 
1968 960,000 1,910 FIRPW Concrete 645 2,323 
1970 2,030,000 3,520 FISP Earth & Rock 565 1,920 
1966 1,026,000 1,900 FIR Rock 480 1,200 
1964 3,539,000 5,838 FIRSW Earth 770 6,850 
1965 960 NPP F Earth 42 3,610 
1964 4,350 NPP FRW Earth 
1964 4,350 NPP FR 
1962 8,620 NPP F 
1963 9,700 10 FR 
1970 1,480 NPP F 
92 700 
Earth 92 100 
Earth & Rock 73 1,200 
Earth 178 940 
Earth 68 1,160 
A-6

FLOOD CONTROL RESERVOIRS CONSTRUCTED OR CONTRIBUTED TO 
BY CORPS OF ENGINEERS BUT OPERATED BY OTHERS 
SEPTEMBER 30, 1983 
Permanent 
Pool 
Cal. Year Total (Acreage)' Characteristics of Dam 
Community Placed in Storage or No Project Name Height Length River Basin Stream in Vicinity Useful Op. (Acre-Ft.) Pool (NPP) Functions Type (Feet) (Feet) 
Idaho 
Ririe Upper Snake Willow Creek Idaho Falls 1979 100,500 364 FIR Earth 184 840 
Maryland 
Savage River Potomac Savage Western Port 1952 20,000 360 FRS Earth 184 1,050 
Missouri 
Bear Creek Upper Mississippi Bear Creek Hannibal 1962 8,700 NPP F Earth 65 1,450 
New York 
Onondaga Oswego Onondaga Creek Syracuse 1949 18,200 NPP F Earth 67 1,782 
Oklahoma 
Lugert-Altus' Red North Fork, Red Altus 1948 152,429 6,260 FISR Concrete 98 1,112 
Markham Ferry' Arkansas Grand (Neosho) River Locust Grove 1964 444,500 10,900' FRP Concrete & 90 4,494 
Earth 
Pensacola' Arkansas Grand (Neosho) River Disney 1941 2,197,000 46,500' FRP Concrete 147 6,565 
Utah 
Big Wash Beaver Big Wash Milford 1961 1,200 NPP F Earth 34 2,814 
Vermont 
East Barre Winooski Jail Branch East Barre 1938 23,550 NPP F Earth & Rock 65 1,460 
Fill 
Waterbury Winooski Waterbury Waterbury 1938 82,100 900 FRH Earth & Rock 158 1,800 
Fill 
Wrightsville Winooski North Branch, Wrightsville 1938 36,000 90 FR Earth & Rock 115 1,525 
Winooski River Fill 
NOMENCLATURE FOR PROJECT FUNCTIONS: 
A -Low Flow Augmentation 
D -Debris Control 
F -Flood Control 
I -Irrigation 
N -Navigation 
P -Power 
Q -Water Quality Control 
R -Public Recretion (Annual Attendance exceeding 5,000) 
S -Water Supply 
W-Fish and Wildlife (Federal or State) 
X -Water Conservation and Sedimentation 
'Acres of water surface at top of permanent pool. 
*Federal Government contributed for flood control storage. 
'Cherry Valley Reservoir: Planned and constructed by local interests as initial phase; provided flood control on interim basis. Second and final phase, New Don Pedro Reservoir: Federal Government 
contributed for flood protection, construction and operation by City and County of San Francisco, and Turlock and Modesto Irrigation Districts. 
'Construction by Bureau of Reclamation Participation by Department of the Army to finance flood control portion. 
'Construction by Grand River Dam Authority Participation by Department of the Army to finance flood control portion. 
'Top of power pool. 
A-7

APPENDIX B 
FLOOD CONTROL PROJECTS UNDER CONSTRUCTION DURING FISCAL YEAR 1983 
Fiscal Year 
Fiscal Placed in Completed or 
Year Useful Scheduled for 
Project Started Operation Completion Nature of Project 
Alamosa, CO (Sec 14)...................................... 
Allegheny River, Oil City, PA (Sec 205)....................... 
Allegheny River, Tionesta, PA (Sec 14) ....................... 
Alpena, MI (Sec 14) ....................................... 
Alum Creek Lake, OH .................................... 
Applegate, OR ........................................... 
Aquilla Lake, TX ......................................... 
Arcadia Lake,OK ........................................ 
Arkansas-Red Basins, Chloride Control (Area VIII), OK, 
TX, and KS (Stage I).................................... 
Asan Village (Guam) (Sec 205) .............................. 
B. Everett Jordan Dam and Lake, NC ........................ 
Bagaduce River, Castine, ME (Sec 14) ........................ 
Beech Fork Lake, WV .................................... 
Bettendorf,IA .......................................... 
Big South Fork National River & Recreation Area, KY and TN.... 
Big Stone Lake & Whetstone River, MN and SD ................ 
Blanchard River, Ottawa, OH (Sec 14) ........................ 
Bloomington Lake, MD and WV ............................. 
Brookville Lake, IN ...................................... 
Brush Bayou, LA ........................................ 
Buffalo Bayou and Tributaries, TX .......................... 
Burketts Cr, Armory, MS (Sec 205)........................... 
Burlington, IA .......................................... 
Burnsville Lake, WV ..................................... 
Caesar Creek Lake, OH.................................... 
CandyLake,OK ......................................... 
Carolina Beach & Vicinity, NC .............................. 
Cave Run Lake, KY ....................................... 
Cayuga Creek, Cheektowaga, NY (Sec 205) ..................... 
Central and Southern, FL................................. 
Charles River (Natural Valley Storage), MA ................... 
Chatfield Lake, CO ...................................... 
Chena River Lakes, AK .................................... 
Chillicothe, OH ......................................... 
Cibolo Creek, TX (Sec 205) ................................. 
Clinton Lake, KS ........................................ 
Columbus, NE (Sec 205) ................................... 
Cooper Lake and Channels, TX ............................. 
Copan Lake,OK ......................................... 
Corte Madera Creek, CA ................................. . 
Cottonwood Creek Community Church, Culdesac, ID (Sec 14) ..... 
Cowanesque Lake, PA .................................... 
Cow CastleCr,SC ....................................... 
Cucamonga Creek, CA ................................... 
Dade County, FL ........................................ 
Dayton, KY ............................................ 
Deep Cr, Edgecombe, NC (See 205) ........................... 
Dry Creek (Warm Springs) Lake & Channel, CA................ 
Duck Creek Channel Improvement, TX ....................... 
Eagle Cr, SC ............................................ 
East Beyer River, Vail, IA (Sec 14) ........................... 
East Brewton, AL (Sec 205) .............................. 
East Lynn Lake, WV ..................................... 
East M oline,IL .......................................... 
East Rockaway Inlet to Rockaway Inlet & Jamaica Bay, 
NY ,PartI ............................................ 
East St. Louis and Vicinity, IL .............................. 
El Dorado Lake, KS.............................. ........ 
E1Paso,TX ............................................. 
El Tuque Beach, PR (Sec 103) ............................... 
Elizabeth, NJ ............................................ 
Elk Creek Lane, OR....................................... 
Emerson, GA (Sec 14) .................................... 
Euclid Creek, OH (Sec 205) ................................. 
Evansdale, IA ........................................... 
1983 
1982 
1983 
1982 1983 
1970 1975 
1974 1981 
1977 1983 
1980 
1976 
1983 
1967 
1988 
1970 
1982 
1979 
1971 
1983 
1971 
1966 
1977 
1956 
1982 
1982 
1972 
1971 
1976 
1965 
1965 
1981 
1950 
1977 
1967 
1973 
1971 
1982 
1972 
1982 
1958 
1973 
1966 
1983 
1973 
1983 
1976 
1975 
1978 
1982 
1967 
1973 
1983 
1983 
1982 
1965 
1980 
1975 
1972 
1974 
1971 
1982 
1972 
1972 
1983 
1983 
1981 
1982 
1978 
1975 
1983 
1981 
1974 
1983 
1978 
1982 
1983 
1976 
1981 
1983 
1983 
1980 
1982 
1983 
1970 
1977 
1981 
1973 
1983 
1984 
1984 
1984 
1983 
1984 
1983 
1983 
1987 
19841 
1985 
1988 
1984 
1986 
1987 
1987 
1985 
1983 
1984 
1984 
1980 
Indefinite 
1984 
1984 
1984 
1984 
Indefinite 
1983 
1986 
1983 
1993 
1983 
1986 
1994 
1984 
1983 
1984 
1985 
Indefinite 
1983 
Indefinite 
1983 
1983 
1984 
1985 
1982 
1984 
1983 
1987 
Indefinite 
1985 
1984 
1983 
1982 
1984 
1988 
Indefinite 
1985 
Indefinite 
1984 
1986 
Indefinite 
1984 
1985 
1983 
Streambank protection 
Local protection 
Local protection 
Local protection 
Reservoir 
Reservoir 
Reservoir 
Reservoir 
Reservoir 
Local protection 
Reservoir 
Local protection 
Reservoir 
Local protection 
Reservoir 
Local protection 
Local protection 
Reservoir 
Reservoir 
Local protection 
Local protection 
Local protection 
Local protection 
Reservoir 
Reservoir 
Reservoir 
Shore protection 
Reservoir 
Local protection 
Local protection 
Non-structural reservoir storage 
Reservoir 
Reservoirs and levee 
Local protection 
Local protection 
Reservoir 
Local protection 
Reservoir, channel improvement 
and levees 
Reservoir 
Local protection 
Local protection 
Reservoir 
Local protection 
Local protection 
Shore protection 
Local protection 
Local protection 
Reservoir 
Local protection 
Local protection 
Local protection 
Local protection, FP evacuation 
Reservoir 
Local protection 
Beach nourishment 
Local protection 
Reservoir 
Local protection 
Shore protection 
Local protection 
Reservoir 
Local protection 
Local protection 
Local protection 
B-1

APPENDIX B (Continued) 
FLOOD CONTROL PROJECTS UNDER CONSTRUCTION DURING FISCAL YEAR 198 
Fiscal Year 
Fiscal Placed in Completed or 
Year Useful Scheduled for 
Project Started Operation Completion Nature of Project 
Evansville, IN ................. .......................... 
Falls Lake, NC...................................... 
Fire Island Inlet to Montauk Point, NY ....................... 
(Rem ainder) ................ . .......................... 
Fountain Creek, CO (Sec 14) ............................. 
Fountain Creek, 1-15, CO (Sec 14) ............................ 
Fountain Creek, Security, CO (Sec 14) ........................ 
Fourmile Creek, CO (Sec 14) ............................. 
Fourmile Run, VA................................... 
Four Rivers Basin, FL ..................................... 
Fulton, IL................................... ............ 
Genesee Rivers, Amity, NY (Sec 14) .......................... 
Grand Prairie, TX (Sec 14) ............................. 
Great Falls, MT...................................... 
Greenville, TX ................. .......................... 
Gypsum, KS (Sec 205) ............... ...................... 
Highland Bayou, TX ................ ...................... 
Hillsdale Lake, KS .................................. 
Hoh River, Near Forks, WA (Sec 14) .......................... 
Housatonic River, Pittsfield, MA (Sec 205)..................... 
Indian Bend Wash, AZ ................................. 
Indian Creek, Emerson, IA (Sec 205)......................... 
Island Ave., Quincy, MA (Sec 14) .......................... 
Islesboro Harbor, Islesboro, ME (Sec 14)....................... 
Joe Pool Lake, TX (formerly Lakeview Lake)................... 
Joyce Creek, Camden Co, NC (Sec 205) ....................... 
Kansas City, KS (1962 Mod.) ............................. 
Kaskaskia Island Drainage & Levee Dist, IL................... 
Keshequa Creek, NY (Sec 14) ............................... 
King Arroyo, CO (Sec 14).................... .... .......... 
Lake Ontario State Pkwy, Kendall, NY (Sec 14) ................ 
Lake Pontchartrain, LA ............................... 
Larose to Golden Meadow, LA .............................. 
Las Animas, Hwy 101, CO (Sec 14) ........................... 
Lavon Lake Modification and East Fork Channel 
Improvement, TX ................ ....................... 
(mod.) 
Leith Creek, SC (Sec 205) .................................. 
Levee Unit 5, Wabash River, IN ............................. 
Levisa & Tug Forks of the Big Sandy River & Cumberland 
River, KY, W V & VA ................ .................... 
Lewisville Dam, TX ................ ....................... 
Little Blue River Channel, MO ........................... 
Little Blue River Lakes, MO............................ 
Little Elk Creek, Girard, PA (Sec 14) ......................... 
Long Branch Lake, MO ........................ ............ 
Lorraine Rd, Biloxi River Lorraine, MS (Sec 107)............... 
Lower Columbia River Bank Protection, OR and WA ............ 
Mankato and N. Mankato, MN .............................. 
Martins Fork Lake, KY............................... 
Matafao Shoreline, American Somoa (Sec 14) ................. . 
McGee Creek Drainage and Levee Dist., IL .................... 
Mentor Beach Park, OH (Sec 14) ............................. 
Mentor on the Lake, OH (Sec 14)............................. 
Meridian Township, MI (Sec 14) ............................. 
Milan, IL .......................................... 
Miss R. Ag Area 8, Elsberry, MO ............................ 
Mt. St. Helens & Vicinity .................................. 
Missouri River Levee System, IA, NE, KS, and MO ............. 
Mt. St. Helens & Vicinity, WA............................ 
Muscatine (Mad Creek), IA .............. ................. 
Muskingham River Lakes, OH ........................... 
Muskingum River Lakes, OH (Dam Safety Assurance) ........... 
Namo River, Guam (Sec 205)............... ............ 
New London, CT ...................................... 
New Orleans to Venice, LA .............. .............. 
Newark, OH ............... . .......................... 
1939 
1973 
1963 
1963 
1983 
1983 
1983 
1983 
1974 
1966 
1978 
1981 
1983 
1982 
1973 
1978 
1974 
1975 
1983 
1982 
1976 
1983 
1982 
1983 
1975 
1982 
1971 
1980 
1981 
1983 
1983 
1967 
1972 
1983 
1970 
1981 
1964 
1981 
1979 
1975 
1978 
1983 
1973 
1983 
1962 
1971 
1973 
1983 
1979 
1981 
1981 
1982 
1980 
1979 
1983 
1948 
1983 
1981 
1976 
1982 
1978 
1978 
1969 
1976 
1983 
1982 
1979 
1980 
1981 
1983 
1976 
1982 
1969 
1983 
1980 
1983 
1978 
1983 
1982 
1988 
1988 
Indefinite 
Indefinite 
1984 
1984 
1984 
1984 
1984 
1986 
1983 
1982 
1984 
1984 
1983 
1982 
1987 
1983 
1983 
1984 
1984 
1984 
1983 
1984 
1988 
1984 
Indefinite 
1987 
1982 
1984 
1983 
Indefinite 
1992 
1984 
1984 
1982 
1984 
Indefinite 
1983 
1986 
1986 
1983 
Indefinite 
1984 
1989 
1990 
1982 
1984 
1985 
1982 
1982 
1983 
1986 
1982 
1984 
Indefinite 
1984 
1983 
1993 
Indefinite 
1980 
1984 
Indefinite 
Indefinite 
Local protection 
Reservoir 
Local protection 
Local protection 
Streambank protection 
Streambank protection 
Streambank protection 
Streambank protection 
Local protection 
Local protection 
Local protection 
Local protection 
Local protection 
Local protection 
Local protection 
Local protection 
Local protection 
Reservoir 
Local protection 
Local protection 
Local protection 
Local protection 
Local protection 
Local protection 
Reservoir 
Local protection 
Local protection 
Local protection 
Local protection 
Streambank protection 
Local protection 
Local protection 
Local protection 
Streambank protection 
Reservoir and channel 
improvement 
Local protection 
Local protection 
Local protection 
Major rehabilitation 
Local protection 
Reservoir 
Local protection 
Reservoir 
Streambank protection 
Local protection 
Local protection 
Reservoir 
Emergency protection 
Local protection 
Local protection 
Local protection 
Local protection 
Local protection 
Local protection 
Local protection 
Local protection 
Local protection 
Local protection 
Major rehabilitation 
Modernization of Dams 
Local protection 
Local protection 
Local protection 
Local protection 
B-2

APPENDIX B (Continued) 
FLOOD CONTROL PROJECTS UNDER CONSTRUCTION DURING FISCAL YEAR 1983 
Fiscal Year 
Fiscal Placed in Completed or 
Year Useful Scheduled for 
Project Started Operation Completion Nature of Project 
Ohio River, Chester, WV (Sec 14) ............................ 
Osborne Cr, Prentiss, CO, MS (Sec 14)....................... 
Paauau Stream, Hawaii, Hawaii (Sec 205)..................... 
Pago Pago Int Airport, American Somoa (Sec 14) ............... 
Paintsville Lake, KY ...................................... 
Papillion Creek and Tributaries Lake, NE ................... . 
Patoka Lake, IN .......................................... 
Pawtuxet River, Warwick, RI (Sec 205) ....................... 
Pearson-Skubitz Big Hill Lake, KS .......................... 
PerryCounty L & D Nos.1,2,3,MO ........................ 
Phoeniz, AZ, and Vicinity (including New River) ............... 
Placer Creek, ID ........................................ 
Plum Creek, Penn Hills, PA (Sec 14) ......................... 
Point Place, OH ......................................... 
Port Arthur and Vicinity, TX ............................... 
Portugues and Bucana Rivers, PR ........................... 
Prairie Du Chien, W I...................................... 
Presque Isle Peninsula, PA ................................ 
Punta Salinas, PR (Sec 103)............................... 
Purgatoire River, Hwy 12 (Sec 14) ........................... 
R. D. Bailey Lake, W V ..................................... 
Rapidan River, Orange, VA (Sec 14) .......................... 
Raritan Bay and Sandy Hook Bay, NJ, Matawan and 
Union Beach Sections .................................... 
Ray Roberts Lake, TX .................................... 
Raynolds Ave, CO ....................................... 
RedOak,IA (Sec205) ..................................... 
Red River below Denison Dam, TX ........................... 
Roberta Clemente Park, Pittsburgh, PA (Sec 14) ................ 
Rockford, IL (Kent Creek).................................. 
Root Creek, Bolivar, NY (Sec).............................. 
Sacramento River Bank Protection, CA ....................... 
Sacramento River, Chico Landing to Red Bluff, CA ............. 
Sacramento River Flood Control, CA ................ ......... 
Sacramento River, Major and Minor Tributaries, CA ............ 
Saginaw River, MI....................................... 
San Antonio Channel Improvement, TX ...................... 
San Gabriel River, TX .................................... 
San Jacinto River Levee & Bautista Creek Channel ............. 
Santa Rosa Dam and Reservoir, NM ......................... 
Sardis Lake,OK ......................................... 
Saylorville Lake, IA ..................................... 
Saxtons River, Rockingham, VT (Sec 14) ...................... 
Scajaquada Creek, NY ................................... 
Sebasticook River, Harland, ME (Sec 205) ..................... 
Sespe Creek at Fillmore, CA (Sec 205) ........................ 
Sewage Lagoons, Vale, OR (Sec 14)........................... 
Siena Center, Racine, WI (Sec 14)........................... 
Skiatook Lake,OK ....................................... 
Shoshone River, Byron, WY (Sec 14). .......................... 
Smith Creek, CO (Sec 14) .................................. 
Smithville Lake, MO ...................................... 
Seuthwestern Jefferson County, KY ......................... 
Squantz Pond, New Fairfield, CT (Sec 14) ..................... 
St. Joseph HS, Cleveland, OH (Sec 14) ......................... 
St. Louis, M O ........................................... 
State Route 163, Marblehead, OH (See 14) ..................... 
Stonewall Jackson Lake, WV .............................. 
SunCr,MS(Sec208) ..................................... 
Taylors Bayou, TX ........................................ 
Taylorsville Lake, KY ..................................... 
Texas City and Vicinity, TX (1958 authorization) ............... 
Three Rivers, TX ........................................ 
Tioga-Hammond Lakes, PA............................ 
Tombigbee River Tributaries, AL and MS ..................... 
Trask River, Tillamook County, OR .......................... 
Trim Cane Cr, MS (Sec 205) ................................ 
1983 
1983 
1983 
1983 
1973 
1972 
1972 
1982 
1974 
1977 
1973 
1981 
1983 
1982 
1966 
1975 
1979 
1975 
1981 
1982 
1967 
1983 
1965 
1975 
1983 
1982 
1948 
1983 
1979 
1963 
1963 
1918 
1949 
1965 
1957 
1973 
1960 
1974 
1976 
1965 
1983 
1978 
1982 
1982 
1983 
1981 
1974 
1983 
1982 
1974 
1974 
1982 
1983 
1959 
1983 
1977 
1983 
1982 
1974 
1962 
1979 
1972 
1965 
1983 
1983 
1983 
1983 
1974 
1978 
1981 
1981 
1982 
1983 
1983 
1979 
19801 
1979 
1983 
1977 
1983 
1983 
1982 
1983 
1982 
1983 
1983 
1983 
1973 
1983 
1983 
1983 
1978 
1983 
1984 
1984 
1984 
1984 
1986 
1987 
1985 
1985 
1983 
1983 
1991 
1984 
1984 
1985 
1984 
1990 
1984 
1986 
1982 
1983 
1984 
1984 
Indefinite 
1989 
1983 
1983 
1985 
1984 
1986 
1991 
1986 
1989 
1986 
1992 
1990 
1983' 
1984 
1983 
1984 
1985 
1984 
1982 
1984 
1983 
1983 
1982 
1985 
1984 
1983 
1984 
1987 
1983 
1983 
1980 
1983 
1988 
1984 
1990 
1986 
1984 
1983 
Indefinite 
Indefinite 
1983 
1984 
Local protection 
Streambank protection 
Local protection 
Emergency protection 
Reservoir 
Reservoirs 
Reservoir 
Local protection 
Reservoir 
Local protection 
Local protection 
Local protection 
Local protection 
Local protection 
Local protection 
Local protection 
Non-structural local protection 
Beach replenishment 
Shore protection 
Streambank protection 
Reservoir 
Streambank Erosion 
Local protection 
Reservoir 
Streambank protection 
Local protection 
Local protection 
Local protection 
Local protection 
Local protection 
Local protection 
Local protection 
Local protection 
Local protection 
Local protection 
Reservoir 
Local protection 
Reservoir 
Reservoir 
Reservoir 
Local protection 
Local protection 
Local protection 
Local protection 
Local protection 
Local protection 
Reservoir 
Local protection 
Streambank protection 
Reservoir 
Local protection 
Local protection 
Local protection 
Local protection 
Local protection 
Reservoir 
Local protection 
Local protection 
Reservoir 
Local protection 
Local protection 
Reservoir 
Local protection 
Local protection 
B-3

APPENDIX B (Continued) 
FLOOD CONTROL PROJECTS UNDER CONSTRUCTION DURING FISCAL YEAR 1983 
Fiscal Year 
Fiscal Placed in Completed or 
Year Usetul Scheduled for 
Project Started Operation Completion Nature of Project 
Trinidad Lake, CO (Dam Safety Assurance).................. . 
Truchas Creek, Ft. Summer, NM (Sec 14).................... . 
Tualation, OR (Sec 205).................................... 
Vince and Little Vince Bayous, TX ........................... 
Waimea River, Kauai, Hawaii (Sec 205)....................... 
Walnut Creek, CA ....................................... 
W aterloo, IA ............................................. 
Wendt Beach, Evans, NY (Sec 14) ............................ 
West Br Westfield River, Huntington, MA (Sec 14) .............. 
West Springfield, WA (Sec 205).............................. 
Wheeler Creek, TX ...................................... 
Wild Rice River S. Branch Felton Ditch, MN ................... 
Willamette River Basin Bank Protection, OR ................. . 
William H. Harsha Lake,OH ............................... 
W illow Creek, OR ....................................... 
Wilson Branch, Cheraw, SC (Sec 205)......................... 
W inona, M N ............................................ 
W olf Cr., MS(Sec 14)...................................... 
Wood River Drainage and Levee District, IL ................... 
Yakima River, Yakima, WA (Sec 14) ......................... 
Yatesville Lake, KY ..................................... 
Yonkers, NY ........................................... 
Zacate Creek, TX (Sec 205) ................................. 
1982 
1983 
1983 
1968 
1983 
1964 
1973 
1982 
1983 
1983 
1983 
1981 
1938 
1970 
1974 
1982 
1979 
1983 
1953 
1983 
1964 
1975 
1981 
1983 
1978 
1983 
1962 
1984 
1984 
1983 
1987 
1985 
1987 
1986 
1982 
1983 
1984 
1984 
1984 
1988 
1984 
1984 
1984 
1985 
1984 
1986 
1983 
Not scheduled 
1984 
1983 
Reservoir, spillway modification 
Streambank protection 
Local protection 
Local protection 
Local protection 
Local protection 
Local protection 
Local protection 
Local protection 
Local protection 
Local protection 
Local protection 
Local protection 
Reservoir 
Reservoir 
Local protection, FP evacuation 
Local protection 
Local protection 
Local protection 
Local protection 
Reservoir 
Local protection 
Local protection 
'Granger Dam & Lake Georgetown-complete FY 83. 
'South Fork-Construction deferred indefinitely, work on GDM only. 
'Completion of Stage I (Truscott facilities) only. Stage II (Ross facilities) indefinite. 
B-4

APPENDIX C 
NAVIGATION LOCKS ANDDAMS OPERABLE SEPTEMBER 80,1988 
Lokeb Dems Authorlbed Channel 
LAftet 
Miee Width Avaihale Namelm 
Above Community of Lenagth ftor Poel Dp aas Length Year Lengw Depth Width 
Project Mouath In Vi ority Chamber iaM Width Level Upper Lower Type' (fUt) Opened (mies) (feet) (feet) 
Alabama.Coosa Rivers, AL 
Claiborne Lock and Dam 81.8' Claiborne, AL 
Millers Ferry Lock and 
Dam 142.8' Camden. AL 
Jones Bluff Lock and Dam 245.4' Benton, AL 
Allegheny River, PA and NY 
Lock and Dam No. 2 6.7 Aspinwall, PA 
Lock and Dam No. 8 14.5 Cheswick, PA 
Lock and Dam No. 4 24.2 Natrona, PA 
Lock and Dam No. 5 30.4 Freeport, PA 
Lock and Dam No. 6 86. Clinton, PA 
Lock and Dam No. 7 45.7 Kittanning, PA 
Lock and Dam No. 8 52.8 Templeton, PA 
Lock and Dam No. 9 62.2 Rimer, PA 
Apalachicola, Chattaboochee, 
and Flint Rivers, GA, AL 
and FL 
Jim Woodruff Lock and 
Dam 107.6' Chattahoochee 
George W. Andrews Lock 
and Dam 154.3' Columbia, GA 
Walter F. George Lock and 
Dam 182.8' Fort Gaines, G 
84 
84 
84 
600 80 16 
600 45 186 
600 45 186 
56 860 11 
56 360 18 
6 860 10 
56 860 12 
56 860 12 
56 360 18 
56 6800 18 
6 860 22 
82 450 88 
82 450 25 
82 450 88 
,FL 
A 
11 
12
9 
10 
11 
11 
14 
11 
14 
19 
18 
18 Movable 
18 Movable 
13 Movable 
3,160' 
9,900' 
14,982' 
1973 60.6 9 900 
1989 105.1 9 900 
1974 88.0 9 200 
12 Fixed 1,398 1984" 7.8 9 200 
11 Fixed 1,486 1984" 9.7 9 200 
10 Fixed 876 1927 86.2 9 200 
11 Fixed 780 1927 5.9 9 200 
11 Fixed 1,140 1928 9.4 9 200 
10 Fixed 916 1980 6.9 9 900 
10 Fixed 984 1981 9.8 9 200 
11 Fixed 950 1988 9.8 9 200 
14 Movable 
13 Movable 
13 Movable 
5,924 1967 
890 19886 
13,371 19638 
46.7 86 
28.5 6 
85.0 6 
100 
100 
100 
Atlantic Intracoastal 
Waterway 
Albemarle and Chesapeake 
Canal Route: 
Great Bridge Lock 
Dismal Swamp Canal 
Route: 
Deep Creek Lock 
South Mills Lock 
Bayou Teche, LA 
Berwick Lock 
Keystone Lock 
Black Rock Channel and 
Tonawanda Harbor, NY 
Black Rock Lock 
Black Warrior, Warrior, and 
Tombigbee Rivers, AL 
Coffeeville (Jackson) Lock 
and Dam 
Demopolis Lock and Dam 
Warrior Lock and Dam 
Win. Bacon Oliver Lock 
and Dam 
Holt Lock and Dam 
John Hollis Bankhead Lock 
and Dam (new lock) 
Canaveral Harbor, FL 
Canaveral Lock 
Cape Fear River, NC 
Lock and Dam No. 1 
Lock and Dam No. 2 
William O. Huske Lock 
and Dam 
Central and Southern Florida 
561 Lock 
8.65 Lock 
S46A Lock 
5458 
8450 Lock 
8.645LDo ck 
S45E Look 
8808B 
8310 
11.5' Great Bridge, VA 75 600 3 16' 16' None 
10.6" Deep Creek, VA 52 800 12 
38.2' South Mills, NC 52 800 12 
1.5' Berwick, LA 
72.5' New Iberia, LA 
0.0 Buffalo, NY 
116.6" Coffeeville, AL 
218.2" Demopols, AL 
261.1" Eutaw, AL 
888.1" Tuscaloosa, AL 
347.0" Holt, AL 
365.1" Adger, AL 
2.7 Cocoa, FL 
167.0 Kings Bluff, NC 
99.0 Browns Landing, NC 
128.0 Tolars Landing, NC 
0.0 St. Cloud, FL 
56.0 Frostproof, FL 
46.0 Avon Park, FL 
288.0 Sbring, FL 
25.0 Sobring, FL 
16.0 Okeechobee, FL 
12.0 Okeechobee, FL 
88.7 Port Mayaca, FL 
0.0 Clewaton, FL 
Columbia River, OR and WA 
Bonneville Lock and Dam 146.0 Bonneville, OR 
The Dalles Lock and Dam 190.0 The Dalles, OR 
John Day Lock and Dam 215.0 Ruias, OR 
McNary Lock and Dam 292.0 Umatilla, OR 
CrossFlorida Barge Canal 
Inglis Lock, Dam and 
Spillway 168.6" Inglis, FL 
Eureka Lock and Dam 20.0 
Henry H. Buckman Lock 904 Palatka, FL 
12' 12' None 
12' 12' None 
46 807 7' 9' 9' None 
86 162 9 9 8 Fixed 
68 625 5 21.6 21.6 None 
110 600 3388 13 
110 600 40 13 
110 800 22 13 
95 460 28 12 
110 600 64 19 
110 600 68 13 
13 Movable 
13 Fixed 
13 Movable 
12 Fixed 
13 Movable 
13 Fixed 
90 600 3 14 14 None 
40 
40 
40 
200 
200 
300 
80 90 
80 90 
80 90 
80 90 
80 90 
80 80 
80 90 
56 400 
50 60 
11
9
9
2
86 
86 
68
786 
6 
14
5 
9 
12
9
86 
66 
86 
86 
86 
86 
14 
183 
78 500 8 32 
86 675 88 15 
88 875 110 15 
86 685 75 15 
84 
84 
84 
800 28 18 
000 20 14 
600 S0 14 
19883 
1940 
1941 
1960 
175 1913 
9 90 
9 50 
9 50 
8 80 
34.5 8 80 
1914 7.1 21 
1,185 
1,485 
1,882 
700 
1,138 
1,170 
1965 
1962 
1962 
1940 
1969 
1975 
96.6 
47.9 
77.0 
8.9 
18.1 
42.7 
999 
90 
9 
1965 12 
900 
200 
200 
200 
200 
200 
200 
125 
9 Fixed 275 1915 32.0 8 100 
12 Fixed 229 1917 24.0 8 100 
9 Fixed 220 1985 0.0 8 100 
8 None 
8 None 
6 None 
8 None 
8 None 
6 None 
8 None 
14 Movable 
13 Movable 
24 Movable 
15 Movable 
15 Movable 
20 Movable 
15 Movable 
Movable 
15 None 
1963 
1984 
1967 
1985 
1965 
1984 
1964 
1977 
1980 
2,680 1988 
8,7685 1967 
5,900 1988 
7,365 1953 
28.0 
10.0 
14.0 
7.0 
9.0 
4.0 
5.0 
.5 
47.5 27 
25.0 14 
76.0 14 
64.0 14 
5,100 1968 11.0 
3,830 1971 
1972 21.2 
12 
12 
12 
90 
80 
80 
80 
80 
30 
80 
100 
50 
300 
250 
250 
250 
150 
150 
150 
C-1 
A
1,

APPENDIX C (Continued) 
NAVIGATION LOCKS AND DAMS OPERABLE SEPTEMBER 30, 1983 
Locks Dams Authorized Channel 
Lift at 
Miles Width Available Normal 
Above Community of Length for Pool Depth on Sills Length Year Length Depth Width 
Project Mouth In Vicinity Chamber Full Width Level Upper Lower Type' (feet) Opened (miles) (feet) (feet) 
Cumberland River, KY and 
TN 
Barkley Dam 30.6 Kuttawa, KY 
Cheatham Lock and Dam 148.7 Ashland City, TN 
Old Hickory Lock and Dam 216.2 Old Hickory, TN 
Cordell Hull Dam and Res. 313.5 Carthage, TN 
Fox River, WI 
DePere Lock 
DePere Dam 
Little Kaukauna Lock 
Little Kaukauna Dam 
Rapide Croche Lock 
Rapide Croche Dam 
Kaukauna Fifth Lock 
Kaukauna Fourth Lock 
Kaukauna Third Lock 
Kaukauna Second Lock 
Kaukauna First Lock 
Kaukauna Dam 
Kaukauna Guard Lock 
Little Chute combined Lock 
Lower 
Upper 
Little Chute Second Lock 
Little Chute First (Guard) 
Lock 
Little Chute Dam 
Cedars Lock 
Cedars Dam 
Appleton Fourth Lock 
Appleton Lower Dam 
Appleton Third Lock 
Appleton Second Lock 
Appleton First Lock 
Appleton Upper Dam 
Menasha Lock 
Menasha Dam 
Freshwater Bayou, LA 
Freshwater Bayou Lock 
Green and Barren Rivers, 
KY 
Green River: 
Lock and Dam No. 1 
Lock and Dam No. 2 
Gulf Intracoastal Waterway 
Inner Harbor Navigation: 
Channel Lock 
Harvey Lock 
Algiers Lock 
Bayou Boeuf Lock 
Bayou Sorrel Lock 
Port Allen Lock 
Vermilion Lock 
Calcasieu Lock 
Brazos River Floodgates 
Colorado River 
East Lock 
West Lock 
Hudson River, NY 
Troy Lock and Dam 
Illinois Waterway, IL 
LaGrange Lock and Dam 
Peoria Lock and Dam 
Starved Rock Lock and 
Dam 
Marseilles Lock 
Marseilles Dam 
Dresden Island Lock and 
Dam 
Brandon Road Lock and 
Dam 
Lockport Lock 
Thomas J. O'Brien Lock 
and Dam 
Inland Route, MI 
Crooked River Lock and 
Weir 
7.1 DePere, WI 
7.2 DePere, WI 
13.0 DePere, WI 
13.1 DePere, WI 
19.2 Wrightstown, WI 
19.3 Wrightstown, WI 
22.8 Kaukauna, WI 
23.1 Kaukauna, WI 
23.3 Kaukauna, WI 
23.4 Kaukauna, WI 
23.6 Kaukauna, WI 
24.0 Kaukauna, WI 
24.0 Kaukauna, WI 
25.4 Little Chute, WI 
25.4 Little Chute, WI 
26A4 Little Chute, WI 
26.5 Little Chute, WI 
26.6 Little Chute, WI 
27.3 Little Chute, WI 
27.4 Little Chute, WI 
30.7 Appleton, WI 
30.9 Appleton, WI 
31.3 Appleton, WI 
31.6 Appleton, WI 
31.9 Appleton, WI 
32.2 Appleton, WI 
37.8 Menasha, WI 
37.8 Menasha, WI 
19.0' Intracoastal City, LA 
9.1 Spottaville, KY 
63.1 Calhoun, KY 
92.6" New Orleans, LA 
98.3" Harvey, LA 
88.0" Algiers, LA 
93.3 Morgan City, LA 
131.0" Plaquemine, LA 
228.5" Port Allen, LA 
162.7" Abbeville, LA 
238.5" Lake Charles, LA 
404.1" Freeport, TX 
444.8 Matagorda, TX 
444.8 Matagorda, TX 
153.8 Troy, NY 
80.2 Beardstown, IL 
157.7 Peoria, IL 
231.0 Utica, IL 
244.6 Marseilles, IL 
247.0 Marseilles, IL 
271.5 Morris, IL 
286.0 Joliet, IL 
291.1 Lockport, IL 
326.5 Chicago, IL 
30.0 Alanson, MI 
110 
110 
84 
84 
36 
36 
36 
36 
37 
31 
35 
35 
40 
35 
36 
35 
35 
35 
35 
35 
35 
34 
34 
800 
800 
400 
400 
146 
146 
146 
144 
144 
144 
144 
144 
147 
144 
144 
144 
144 
144 
145 
145 
144 
84 600 
57 11 
26 14 
60 14 
59 14 
9 10 
7 8 
8 9 
9 7 
10 7 
10 7 
10 6 
11 7 
13 Movable 
12 Movable 
10 Movable 
13 Movable 
12 
10 
10
96666 
9 
11 
11 
14
7 
10
8
9 
10 
10
8 
Movable 
Movable 
Movable 
Movable 
Movable 
Movable 
Movable 
Movable 
Movable 
16 16 None 
84 600 12 12 11 Fixed 
84 600 14 15 12 Fixed 
75 
75 
75 
75 
56 
84 
56 
75 
75 
75 
75 
640 9' 31' 
425 10' 12' 
797 10' 13' 
1,158 6' 13' 
800 10' 14' 
1,198 45 13' 
1,200 3' 11' 
1,205 6' 13' 
15' 
1,200 5' 15' 
1,200 5' 15' 
9,959 1964 118.1 9 
801 1959 67.5 9 
3,605 1957 97.3 9 
1,138 1973 71.9 9 
1936 
986 1929 
1938 
588 1926 
1934 
461 1930 
1898 
1879 
1879 
1903 
1883 
603 1931 
1891 
1879 
1879 
1881 
1904 
562 1932 
1888 
654 1933 
1907 
549 1934 
1900 
1901 
1884 
691 1940 
1899 
401 1937 
401 1968 
5.9 
6.2 
3.6 
0.3 
0.2 
0.1 
0.2 
0.4 
1.4 
1.0 
0.7 
3.4 
0.6 
0.3 
0.3 
5.1 
28.3 
150 
150 
150 
150 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
12 125 
482 1956 54.0 9 200 
519 1956 45.4 9 200 
31' None 
12' None 
13' None 
13' None 
14' None 
14' None 
11' None 
13' None 
15' None 
15' None 
15' None 
44 493 17 16 13 Fixed 
110 
110 
110 
110 
110 
110 
110 
110 
600 
600 
600 
600 
600 
600 
600 
1,000 
10 
11 
19 
24 
22 
34 
40
2 
16 
16 
17 
19 
17 
18 
12 
14 
13 Movable 
12 Movable 
14 Movable 
14 
Movable 
12 Movable 
14 Movable 
15 None 
14 Movable 
17.8 66 1 6.9 7.9 SSP Weir 
1923 
1935 
1956 
1956 
1952 
1961 
1934 
1950 
1943 
1954 
1954 
12 
12 
16 
16 
12 
12 
16 
16 
12 
12 
12 
150 
125 
150 
150 
125 
125 
200 
200 
125 
125 
125 
1,495 1917 2.2 14 200 
1,066 1939 
536 1939 
1,280 1933 
1933 
819 1933 
1,616 1933 
2,373 1933 
1933 
257 1970 
77.5 9 
73.3 9 
13.6 9 
26.9 9 
24.6 
14.5 9 
5.1 99 
6.9 9 
300 
300 
300 
300 
300 
300 
300 
300 
83 1967 4.0 5 30 
C-2

APPENDIX C (Continued) 
NAVIGATION LOCKS AND DAMS OPERABLE SEPTEMBER 30, 1983 
Locks Dams Authorized Channel 
Lift at 
Miles Width Available Normal 
Above Community of Length for Pool Depth on Sills Length Year Length Depth Width 
Project Mouth In Vicinity Chamber Full Width Level Upper Lower Type' (feet) Opened (miles) (feet) (feet) 
Kanawha River, WV 
Winfield Lock and Dam 
Marmet Lock and Dam 
London Lock and Dam 
Kaskaskia River, IL 
Kaskaskia Lock and Dam 
Kentucky River, KY 
Lock and Dam No. 1 
Lock and Dam No. 2 
Lock and Dam No. 3 
Lock and Dam No. 4 
Lock and Dam No. 5 
Lock and Dam No. 6 
Lock and Dam No. 7 
Lock and Dam No. 8 
Lock and Dam No. 9 
Lock and Dam No. 10 
Lock and Dam No. 11 
Lock and Dam No. 12 
Lock and Dam No. 13 
Lock and Dam No. 14 
Lake Washington Ship Canal 
Hiram M. Chittenden Lock 
Large Lock 
Small Lock 
McClellan-Kerr Arkansas 
River Navigation System, 
AR and OK 
Norrell Lock and Dam 
Lock No. 2 
Dam No. 2 
Lock and Dam No. 3 
Lock and Dam No. 4 
Lock and Dam No. 5 
David D. Terry Lock and 
Dam 
Murray Lock and Dam 
Toad Suck Ferry Lock and 
Dam 
Lock and Dam No. 9 
Dardanelle Lock and Dam 
Ozark-Jeta Taylor Lock 
and Dam 
Lock and Dam No. 13 
W. D. Mayo Lock and Dam 
Robert S. Kerr Lock and 
Dam and Reservoir 
Webbers Falls Lock and 
Dam 
Chouteau Lock and Dam 
Newt Graham Lock and 
Dam 
31.1 Winfield, WV 
67.8 Marmet, WV 
82.8 London, WV 
.8 Ellis Grove, IL 
4.0 Carrolton, KY 
31.0 Lockport, KY 
42.0 Gest, KY 
65.0 Frankfort, KY 
82.2 Tyrone, KY 
96.2 High Bridge, KY 
117.0 High Bridge, KY 
139.9 Camp Nelson, KY 
157.5 Valley View, KY 
176.4 Ford, KY 
201.0 Irvine, KY 
220.9 Ravenna, KY 
239.9 Willow, KY 
249.0 Heidelberg, KY 
1.3 Seattle, WA 
1.3 Seattle, WA 
10.3 Arkansas Post, AR 
13.3 Arkansas Post, AR 
40.5 Arkansas Post, AR 
50.2 Grady, AR 
66.0 Pine Bluff, AR 
86.3 Redfield, AR 
108.1 Little Rock, AR 
125.4 Little Rock, AR 
155.9 Conway, AR 
176.9 Morrilton, AR 
205.5 Russellville, AR 
256.8 Ozark, AR 
292.8 Fort Smith, AR 
319.6 Fort Smith, AR 
336.2 Sallisaw, OK 
366.6 Webbers Falls, OK 
401.5 Muskogee, OK 
421.6 Inola, OK 
56 
56 
56 
360 
360 
360 
28 
24 
24 
84 600 32 
38 
38 
38 
38 
38 
52 
52 
52 
52 
52 
52 
52 
52 
52 
145 
145 
145 
145 
145 
147 
147 
146 
148 
148 
148 
148 
148 
148 
8 
14 
13 
13 
15 
14 
15 
19 
17 
17 
18 
17 
18 
17 
18 
18 
18 
12 Movable 
12 Movable 
12 Movable 
834 
707 
707 
18 11 Movable 
88 
9
6 
10
9
9 
11 
11
9 
10 
10 
10
9 
15 Fixed 
6 Fixed 
7 Fixed 
6 Fixed 
6 Fixed 
6 Fixed 
7 Fixed 
6 Fixed 
7 Fixed 
6 Fixed 
6 Fixed 
6 Fixed 
6 Fixed 
6 Fixed 
1937 36.7 9 
1934 15.0 9 
1934 7.8 9 
300 
300 
300 
130 1973 35.0 9 225 
424 
400 
465 
543 
556 
413 
350 
257 
362 
472 
208 
240 
248 
248 
80 760 26 16 29 Movable 
28 123 26 16 16 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
600 
600 
600 
600 
600 
600 
600 
600 
600 
600 
600 
600 
600 
600 
600 
600 
600 
30 
20 
20 
14 
17 
18 
18 
16 
19 
54 
34 
20 
20 
48 
30 
21 
21 
16 
18 
18 
18 
18 
18 
18 
18 
18 
18 
18 
18 
14 
18 
19 
15 
15 
15 Fixed 
14 
Movable 
14 Movable 
14 Movable 
14 Movable 
14 Movable 
14 Movable 
14 Movable 
14 Movable 
14 Movable 
15 Movable 
14 Movable 
15 Movable 
14 Movable 
16 Movable 
14 Movable 
14 Movable 
1839 
1939 
1844 
1844 
1844 
1891 
1897 
1900 
1907 
1907 
1906 
1910 
1915 
1917 
27.0 
11.0 
23.0 
17.2 
14.0 
20.8 
22.9 
17.6 
18.9 
24.6 
19.9 
19.0 
9.1 
9.6 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
235 1916 17.0 34 150 
4,677 
42,073 
6,110 
5,745 
7,455 
8,890 
3,930 
1,580 
1,505 
1,815 
2,480 
4,725 
7,400 
7,230 
4,370 
11,490 
1,630 
1967 
1967 
1968 
1968 
1968 
1968 
1968 
1969 
1969 
1969 
1969 
1969 
1969 
1970 
1970 
1970 
1970 
1970 
3.0 
36.9 
15.8 
20.3 
21.8 
17.3 
30.5 
21.0 
28.6 
51.3 
36.0 
26.8 
16.6 
30.4 
34.8 
20.2 
23.7 
Mississippi River 
Between Ohio and Missouri 
Rivers 
Lock and Dam No. 27 185.1" Granite City, IL 
Mississippi River Between 
Missouri River and 
Minneapolis, MN 
Lock and Dam No. 26 202.91 Alton, IL 
Lock and Dam No. 25 241.4" Cap Au Gris, MO 
Lock and Dam No. 24 273.4" Clarksville, MO 
Lock and Dam No. 22 301.2" Saverton, MO 
Lock and Dam No. 21 324.9 Quincy, IL 
Lock and Dam No. 20 343.2" Canton, MO 
Lock and Dam No. 19 364.2" Keokuk, IA 
Lock and Dam No. 18 410.5" Burlington, IA 
Lock and Dam No. 17 437.1" New Boston, IL 
Lock and Dam No. 16 457.2" Muscatine, IA 
Lock and Dam No. 15 482.9" Rock Island, IL 
Lock and Dam No. 14 493.1" LeClaire, IA 
493.3" LeClaire, IA 
Lock and Dam No. 13 522.5" ClintonI,A 
Lock and Dam No. 12 556.7" Bellevue, IA 
Lock and Dam No. 11 583.0" Dubuque, IA 
Lock and Dam No. 10 615.1" Guttenberg, IA 
Lock and Dam No. 9 647.9" LynxvilleI,A 
Lock and Dam No. 8 679.2" Genoa, WI 
Lock and Dam No. 7 702.5" Dresbach, MN 
110 1,200 21 16 15 Fixed 
110 
110 
110 
110 
110 
110 
110 
110 
100 
110 
110 
110 
80 
110 
110 
110 
110 
110 
110 
110 
110 
600 
360 
600 
600 
600 
600 
600 
1,200 
600 
600 
600 
600 
360 
320 
600 
600 
600 
600 
600 
600 
600 
600 
24 
24 
15 
15 
10 
10 
10 
38 
10
8
9 
16 
16 
11 
11 
11 
9 
11 
8
9 
11
8 
19 
16 
19 
19 
18 
17 
15 
15 
17 
16 
17 
27 
27 
18 
21 
19 
17 
19 
15 
16 
22 
18 
10 Movable 
10 
12 Movable 
12 Movable 
14 Movable 
12 Movable 
12 Movable 
13 Fixed 
14 Movable 
13 Movable 
12 Movable 
11 Movable 
11 
11 
14 Movable 
13 Movable 
13 Movable 
13 Movable 
12 Movable 
13 Movable 
14 Movable 
12 Movable 
250 
250 
250 
250 
250 
250 
250 
250 
250 
250 
250 
250 
250 
250 
250 
150 
150 
3,240 1953 178 9 200 
1,725 
1,296 
4,280 
1,024 
1,066 
2,144 
4,434 
1,350 
921 
1,099 
1,203 
1,343 
1,066 
849 
1,278 
763 
811 
897 
940 
1938 
1939 
1940 
1938 
1938 
1936 
1913 
1937 
1939 
1937 
1934 
1922 
1939 
1939 
1938 
1937 
1936 
1938 
1937 
1937 
38.5 
32.0 
27.8 
23.7 
18.3 
21.0 
46.3 
26.6 
20.1 
25.7 
10.4 
29.2 
34.2 
26.3 
32.1 
32.8 
31.3 
23.3 
11.8 
200 
200 
200 
NS 
NS 
NS 
NS 
NS 
NS 
NS 
NS 
NS 
NS 
NS 
NS 
NS 
NS 
NS 
NS 
C-3

APPENDIX C (Continued) 
NAVIGATION LOCKS AND DAMS OPERABLE SEPTEMBER 30, 1983 
Locks Dams Authorized Channel 
Lift at 
Miles Width Available Normal Depth on is 
Above Community of Length for Pool Dpth on Sills Length Year Length Depth Width 
Project Mouth In Vicinity Chamber Full Width Level Upper Lower Type' (feet) Opened (miles) (feet) (feet) 
Mississippi River (Continued) 
Between Missouri River 
and Minneapolis, MN 
Lock and Dam No. 6 714.3" Treampealeau, WI 
Lock and Dam No. SA 728.5" Winona, MN 
Lock and Dam No. 5 738.1" Minneiska, MN 
Lock and Dam No. 4 752.8" Alma, WI 
Lock and Dam No. 3 796.9" Red Wing, MN 
Lock and Dam No. 2 815.2" Hastings, MN 
Lock and Dam No. 1 847.6" Minneapolis-St. Paul, MN 
St. Anthony Falls 
Lower Lock and Dam 853.3" Minneapolis, MN 
Upper Lock and Dam 853.9" Minneapolis, MN 
Monongahela River, PA 
and WV 
Locks and Dam No. 2 11.2 Braddock, PA 
Locks and Dam No. 3 23.8 Elizabeth, PA 
Locks and Dam No. 4 41.5 Monessen, PA 
Maxwell Locks and Dam 61.2 Maxwell, PA 
Locks and Dam No. 7 85.0 Greensboro, PA 
Locks and Dam No. 8 90.8 Point Marion, PA 
Morgantown Lock and 
Dam 102.0 Morgantown, WV 
Hidebrand Lock and Dam 108.0 Morgantown, WV 
Opekiska Lock and Dam 115.4 Morgantown, WV 
Ohio River 
Locks and Dam No. 53 18.4 Mound City, IL 
Locks and Dam No. 52 42.1 Brookport, IL 
8mithland Locks and Dam 35.3 Smithland, KY 
Uniontown Locks and Dam 135.0 Uniontown, KY 
Newburgh Locks and Dam 204.9 Newburg, IN 
Cannelton Locks and Dam 260.3 Cannelton, IN 
McAlpine Locks and Dam 374.2 Louisville, KY 
Markland Locks and Dam 449.5 Markland, IN 
Capt. Anthony Meldahl 
Locks and Dam 544.8 Chile, OH 
Greenup Locks and Dam 640.0 Greenup, KY 
Gallipolis Locks and Dam 701.8 Hogsett, WV 
Racine Locks and Dam 743.5 Letart Falls, OH 
Belleville Locks and Dam 777.1 Reedsville, OH 
Willow Island Locks and 
Dam 819.3 Waverly, WV 
Hannibal Locks and Dam 854.6 New Martinsville, WV 
Pike Island Locks and 
Dam 896.7 Warwood, WV 
New Cumberland Locks 
and Dam 926.6 Stratton, OH 
Montgomery Island Locks 
and Dam 949.3 Industry, PA 
Dashilds Locks and Dam 967.7 Glenwillard, PA 
Emsworth Locks and Dam 974.8 Emsworth, PA 
Okeechobee Waterway, FL 
St. Lucie Lock and Dam 15.1 Stuart, FL 
Moore Haven Lock 78.0 Moore Haven, FL 
Ortona Lock and Dam 93.6 LaBelle, FL 
W. P. Franklin Lock and 
Control Structure 121.4 Fort Myers, FL 
110 
110 
110 
110 
110 
110 
56 
56 
56 
66 
600 6 
600 5 
600 9 
600 7 
600 8 
600 12 
500 12 
400 38 
400 38 
400 25 
400 49 
56 360 
110 720 
56 860 
56 720 
56 360 
56 720 
84 720 
84 720 
56 38060 
56 360 
4 600 
84 600 
84 600 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
56 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
56 
110 
56 
110 
56 
600 
1,200 
600 
1,200 
1,200 
1,200 
1,200 
600 
1,200 
600 
1,200 
600 
1,200 
600 
360 
1,200 
600 
1,200 
600 
1,200 
600 
600 
860 
1,200 
600 
1,200 
600 
1,200 
600 
1,200 
600 
1,200 
600 
1,200 
600 
600 
360 
600 
360 
600 
360 
50 250 
50 250 
50 250 
56 400 
9988 
17 
17 
20 
20 
15 
19 
17 
21 
22 
12 
12 
12 
12 
22 
22 
22 
22 
16 
16 
25 
25 
37 
37 
37 
35 
35 
30 
30 
30 
30 
23 
23 
22 
22 
22 
22 
20 
20 
21 
21 
21 
21 
21 
21 
18 
18 
10 
10 
18 
18 
13
2 
11 
3 
17 
18 
18 
17 
17 
22 
16 
13 
13 
14 
16 
16 
16 
12 
12 
20 
20 
21 
21 
11 
15 
18 
14 
18 
15 
15 
15 
15 
34 
34 
34 
34 
32 
32 
38 
38 
49 
19 
19 
50 
50 
45 
45 
45 
45 
18 
18 
37 
37 
37 
37 
35 
35 
38 
38 
17 
17 
17 
17 
16 
16 
13 
13 
17 
16 
14 
10 
12 
13 
13 Movable 
13 Movable 
12 Movable 
13 Movable 
14 Movable 
13 Movable 
15
8 Fixed 
10 
10 Movable 
14 Fixed 
16 Fixed 
16 
12 Fixed 
12 
11 Movable 
11 
15 Movable 
15 
10 Fixed 
10 Movable 
15 Movable 
15 Movable 
14 Movable 
10 Movable 
10 Temporary Lock 
11 Movable 
11 Temporary Lock 
12 Movable 
12 
12 Movable 
12 
16 Movable 
16 
13 Movable 
13 
12 Movable 
11 
11 
15 Movable 
15 
15 Movable 
15 
15 Movable 
15 
15 Movable 
15 
15 Movable 
15 
15 Movable 
15 
15 Movable 
15 
17 Movable 
17 
18 Movable 
18 
15 Movable 
15 
15 Movable 
15 
18 Fixed 
18 
13 Movable 
13 
12 Movable 
11 None 
11 Movable 
- Movable 
893 1936 14.2 9 NS 
682 1936 9.6 9 NS 
1,619 1935 14.7 9 NS 
1,367 1935 44.1 9 NS 
365 1938 18.3 9 NS 
822 1930 32.4 9 NS 
1948 
574 1932 5.7 9 NS 
1917 
188 1959 0.5 9 100 
3,584 1963 3.8 9 100 
748 1951 12.6 9 300 
1953" 
670 1907 17.7 9 300 
1907" 
535 1932 19.7 9 300 
1932" 
460 1964 23.8 9 300 
1964 
610 1925" 5.8 9 300 
560 1925" 11.2 9 300 
410 1950 6.0 9 300 
530 1959 7.4 9 300 
366 1964 7.0 9 300 
3,978 1929 23.7 9 300 
1980 
3,073 1928 35.8 9 300 
1969 
3,560 1980 99.7 9 300 
3,516 1975 69.9 9 300 
2,272 1975 55.4 9 300 
1,965 1972 116.3 9 400 
8,627 1961 75.3 9 300 
1921 
1930 
1,395 1963 95.3 9 300 
1963 9 300 
1,756 1962 95.2 9 300 
1962 
1,287 1962 61.8 9 300 
1,132 1937 41.7 9 300 
1,202 1970 33.6 9 300 
1,206 1969 36.4 9 300 
1,128 1973 35.3 9 1,000 
1,098 1972 36.0 9 300 
1,306 1965 29.9 9 300 
1,315 1961 22.7 9 300 
1,379 1936 18.4 9 300 
1,585 1929 7.1 9 300 
1,717 1921 6.2 9 300 
170 1941 15.1 8 80 
1953 15.6 8 90 
104 1937 15.6 8 90 
1,150 1965 7.9 8 90 
C-4

APPENDIX C (Continued) 
NAVIGATION LOCKS AND DAMS OPERABLE SEPTEMBER 30, 1983 
Locks Dams Authorised Channel 
Lift at 
Miles Width Available Normal 
Above Community of Length for Pool Depth on 8ills Length Year Length Depth Width 
Project Mouth In Vicinity Chamber Full Width Level Upper Lower Type' (feet) Opened (miles) (feet) (feet) 
Old River, LA 
Old River Lock 
Ouachita and Black Rivers, 
AK & LA 
Jonesville Lock and Dam 
(Black River) 
Columbia Lock and Dam 
(Ouachita River) 
Lock and Dam No. 6 
(Ouachita River) 
Lock and Dam No. 8 
(Ouachita River) 
Pearl River, MS AND LA 
Lock 1 
Lock 2 
Lock 3 
Sacramento River, CA 
Barge Canal Lock 
Snake River, WA 
Ice Harbor Lock and Dam 
Lower Monumental Lock 
and Dam 
Little Goose Lock and Dam 
Lower Granite Lock and 
Dam 
St. Marys River, MI 
South Canal: 
MacArthur Lock 
Poe Lock 
North Canal: 
Davis Lock 
Sabin Lock 
Savannah River, GA 
New Savannah Bluff Lock 
and Dam 
Tennessee River, TN, AL, 
MS, and KY" 
Kentucky Lock and Dam 
Pickwick Landing Lock 
and Dam 
304.0 Simmesport, LA 
25.0 Joneaville, LA 
117.2 Columbia, LA 
223.4 Felsenthal, AR 
282.8 Calion, AR 
228.7" Pearl River, LA 
40.8" Bush, LA 
14.0" Sun, LA 
42.8 West Sacramento, CA 
9.7 Pasco, WA 
41.6 Kahlotus, WA 
70.3 Starbuck, WA 
107.5 Pomeroy, WA 
47.0 Sault Ste. Marie, MI 
47.0 Sault Ste. Marie, MI 
47.0 Sault Ste. Marie, MI 
47.0 Sault Ste. Marie, MI 
187.2 Augusta, GA 
22.4 Gibertsville, KY 
206.7 Hamburg, TN 
Waterway Connecting 
Tombigbee and Tennessee 
Rivers, Alabama 
and Mississippi Rivers 
Gainesville Lock and Dam 49.1 Gainesville 
Aliceville Lock and Dam 89.8 Aliceville 
Columbus Lock and Dam 117.6 Columbus 
Wilson Lock and Dam 
Main Lock 259.4 Florence, AL 
Auxillary Lock 259.4 Florence, AL 
General Joe Wheeler Lock 
and Dam 
Main Lock 274.9 Florence, AL 
Auxillary Lock 274.9 Florence, AL 
Guntersville Lock and Dam 
Main Lock 349.0 Guntersville, AL 
Auxillary Lock 349.0 Guntersville, AL 
Nickajack Lock and Dam 424.7 Chattanooga, TN 
Chickamauga Lock and 
Dam 471.0 Chattanooga, TN 
Watts Bar Lock and Dam 529.9 Breedenton, TN 
Fort Loudon Lock and 
Dam 602.3 Lenoir City, TN 
Melton Hill Lock and Dam 
(Clinch River) 23.1 Kingston, TN 
Tennessee-Tombigbee 
Waterway, AL and MS 
Beginning of Project 217.0" 
Gainesville Lock and 
Dam 266.1"
0 
Gainesville, AL 
Aliceville Lock and Dam 306.8" Aliceville, AL 
,,lumbus Lock and Dam 334.7" Columbus, MS 
75 1,200 35 11 11 None 
84 
84 
55 
55 
65 
65 
65 
600 
600 
268 
268 
310 
310 
310 
30 
18 
10 
14 
17 
15 
11 
18 
18 
14 
17 
10 
10 
10 
450 
400 
314 
306 
14 Movable 
13 Fixed 
7 Movable 
7 Movable 
10 None 
10 None 
10 None 
86 600 4 13 13 None 
86 
86 
86 
86 
80 
110 
80 
80 
675 
675 
675 
675 
800 
1,200 
1,350 
1,350 
100 
98 
98 
100 
15 
15 
15 
15 
22 31 
22 32 
22 24 
22 24 
56 360 15 
110 
110 
110 
110 
110 
110 
60 
600 
600 
600 
600 
600 
600 
292 
56 
55 
36 
27 
27 
94 
94 
110 600 48 
60 400 48 
110 600 39 
60 360 39 
119 600 39 
60 360 49 
60 360 58 
60 360 72 
75 400 54 
110 
110 
110 
600 
600 
600 
36 
27 
27 
15 Movable 
15 Movable 
15 Movable 
15 Movable 
31 None 
32 None 
23 None 
23 None 
14 12 Movable 
11 
10 
15 
15 
15 
13 
11 
13 
15 
13 
13 
13 
10 
12 
12 
13 
15 
15 
15 
13 Tainter 
13 Bulkhead 
15 Movable 
15 Movable 
15 Movable 
13 Bulkhead 
11 Bulkhead 
13 Bulkhead 
13 Bulkhead 
13 Tainter 
12 Tainter 
11 Tainter 
14 Tainter 
12 Tainter 
12 Tainter 
13 Tainter 
15 Comb. Fixed 
&Movable 
15 Comb. Fixed 
& Movable 
15 Movable 
2,790 
3,800 
2,670 
3,200 
1963 
1972 
1972 
1923 
1926 
12 125 
92.2 
106.2 
59.4 
55.2 
9
9
9" 
9" 
1951 11.1 7 
1951 3.2 7 
1951 13.2 7 
1961 1.5 13 120 
1962 
1969 
1970 
1975 
31.9 
28.7 
37.2 
32.0 
1943 
1968 - 
1914 
1919 
360 1936 16.2 
14 
14 
14 
14 
27
9 90 
7,976 1944 184.3 9 
7.385 1937 52.7 9 
15,460 
14,790 
10,040 
3,728 
3,728 
5,738 
5,738 
3,837 
3,837 
3,763 
5,$54 
2,646 
3,687 
1,072 
1978 
1979 
1981 
1959 
1927 
1963 
1962 
1965 
1939 
1967 
1940 
1942 
1943 
1963 
49.1 
40.7 
27.8 
15.5 
15.5 
74.1 
74.1 
75.7 
75.7 
46.3 
58.9 
72.4 
49.8 
38.2 
15,460 1978 49.1 
14,790 1979 40.7 
10,040 1981 27.9 
C-5 
100 
100 
100 
100 
80 
80 
80 
250 
250 
250 
250 
300 
300 
300 
300 
300 
300 
300 
300 
300 
300 
300 
300 
300 
300 
300 
300" 
300 
300 
300

APPENDIX C (Continued) 
NAVIGATION LOCKS AND DAMS OPERABLE SEPTEMBER 30, 1983 
Locks Dams Authorized Channel 
Lift at 
Miles Width Available Normal 
Above Community of Length for Pool Depth on Sills Length Year Length Depth Width 
Project Mouth In Vicinity Chamber Full Width Level Upper Lower Type' (feet) Opened (miles) (feet) (feet) 
Willamette River at 
Willamette Falls, OR 
Lock No. 1 26.0 Oregon City, OR 40 210 20 6 8 None 1872 6 150 
Lock No. 2 26.0 Oregon City, OR 40 210 10 6 8 None 1872 
Lock No. 3 26.0 Oregon City, OR 40 210 10 6 8 None 1872 
Lock No. 4 26.0 Oregon City, OR 40 210 10 6 8 None 1872 4 
Guard Lock 26.4 Oregon City, OR 40 210 10 6 8 None 1872 23.6 6 NS 
'Fixed: crest without gates or other facility to control streamflow. Movable: includes any type of crest gates, tainter gates, wickets, or others to control streamflow. 
'Above mouth of Mobile River. 
*Includes length of earth dikes. 
' om mouth of Apalachicola River. 
'Above Norfolk, VA. 
'With reference to mean low water, or low mean Gulf as case may be. 
'From Gulf Intracoastal Waterway. 
'Average high and low water conditions, lift varying widely, depending on tides and river stages. 
"From foot of Government Street, Mobile, AL. 
"From mouth of St. Johns River. 
"Above Head of Passes. 
"From New Orleans, LA. 
"Salt water barrier in down position. Will clear 15-foot vessels in normal position. 
"Above the Ohio River. 
"Channel completed to depth of 6.5 feet. 
"From mouth of West Pearl River. 
"Tennessee River locks operated by the Corps, dams operated by the Tennessee Valley Authority. 
"300foot width from lock to mouth of Cinch River and 175foot width upstream from lock to Clinton, TN. 
"Dates shown represent replacement structures. 
"Dates shown represent reconstruction for locks and dams Nos. 2.8 inclusive. 
"Dam was rebuilt in 1959. 
"Old 110' x 358' lock replaced in 1957. 
C-6

APPENDIX D 
NAVIGATION PROJECTS UNDER CONSTRUCTION DURING FISCAL YEAR 1983 
Fiscal Year 
Fiscal Placed in Completed or 
Year Useful Scheduled for 
Project Started Operation Completion Nature of Project 
AIWW-Replacement ofFederay Hwy Bridges in NC ........... . 
Aquatic Plant Control ..................................... 
Ashtabula Harbor, OH ................................... 
Barbers Point Harbor, Oahu, Hawaii ......................... 
Bandon SBB, Coquille, OR (Sec 107).......................... 
Buffalo Harbor, NY (Sec 107) ............................... 
Buttermilk Bay, Bourne, MA (Sec 107)....................... 
Calumet Harbor & River, IL and IN .......................... 
Calumet-Sag. Mod., IL Waterway, IL and IN, Part 1............. 
Cannelton Locks and Dam, Ohio River, IN and KY .............. 
Carolina Beach Inlet, NC (Sec 107).......................... 
Cattaraugus Harbor, NY ................................. 
Cedar Point, McIntosh Co, GA (Sec 107)....................... 
Channel to Newport News, VA (1965 Mod.) .................... 
Charleston Channel, Coos Bay, OR (Sec 107) ................... 
Cooper River, Charleston Harbor, SC ......................... 
Cordova Harbor, AK (Sec 107) ............................. 
Corea Harbor, Gouldsboro, ME (Sec 107) ...................... 
Jeremy Creek, McClellanville, SC (Sec 107) ................... 
Corpus Christi Ship Channel, TX........................... 
Crescent City Harbor, CA ............................... . 
Delaware River, PA, NJ, and DE, Philadelphia to Sea 
(Anchorage)............................................ 
Detour Harbor, MI ......................................... 
East Bay Marina, Olympia, WA (Sec 107) ..................... 
Eastpoint Breakwater, FL (Sec 107) .......................... 
Emsworth Locks and Dams, Ohio River, PA ................... 
Dresden Island Lock and Dam Illinois Waterway, IL ............ 
Floating Breakwater Prototype Test Program, West Point, 
Seattle, WA (Sec 107) ................................. 
Friday Harbor Marina, WA (Sec 107) ......................... 
Inland Waterway, Delaware River to Chesapeake Bay, DE 
and M D, Part II........................................ 
Kahului Harbor, Maui, Hawaii ............................. 
Kaskaskia River, IL ...................................... 
Krebbs Lake, MS (Sec 107) .............................. 
Little River Inlet, NC & SC .............................. 
Lockwoods Folly Inlet, NC (Sec 107)......................... 
Lock and Dam 26 Replace IL-MO .......................... / 
Locks and Dam 52, IL and KY ........................... ,. 
Locks and Dam 53, IL and KY ............................. . 
Los Angeles-Long Beach Harbors, CA ........ .................. 
Manitowoc Harbor, WI ................................... . 
McClellan-Kerr Arkansas River Navigation System ............ 
Metlakatla Harbor, AK .................................... 
Mississippi River between Ohio and Missouri Rivers ............ 
Mississippi River between Missouri River and Minneapolis, MN .... 
Mississippi River, Gulf Outlet, LA ........................... 
Missouri River, Sioux City, IA to mouth ...................... 
Mobile Harbor (Theodore Channel) .......................... 
Montgomery Locks & Dams, Ohio River, PA ................... 
Morgan Creek, Beaufort, NC ............................... 
1974 
1959 
1981 
1982 
1982 
1981 
1983 
1964 
1955 
1962 
1982 
1981 
1981 
1967 
1983 
1977 
1981 
1982 
1982 
1972 
1970 
1964 
1980 
1981 
1983 
1980 
1980 
1982, 
1981 
1962 
1982 
$966 
1983 
1981 
1982 
1980 
1979 
1979 
1980 
1981 
1963 
1979 
1910 
1979 
1958 
1912 
1979 
1983 
1983 
19811 Indefinite Replacement of existing bridges 
Indefinite Control and eradication of 
aquatic plants 
1983 Rehabilitation of breakwater 
1985 Dredging and breakwater 
1983 Breakwater and channel 
1982 Removal bridge abutment 
1984 Dredging 
1966 Indefinite Dredging and channel, widening 
and deepening 
196 Indefinite Channel improvements and 
relocation 
1966 1984 Replacement of existing locks 
and dams 43-45 inclusive 
S1983 Dredging 
1983 Breakwaters and berm 
1982 1982 Dredging 
1968 Indefinite Deep draft channel widening 
and deepening, deferred 
anchorage construction 
1984 Dredging 
1984 Rediversion of river and powerhouse 
construction 
1983 I 1983 Breakwater 
1983 1983 Dredging 
1982 1982 Dredging 
/ 1988 Dredging 
/ 1984 Dredging and breakwater 
/ Indefinite Dredging 
1982 1982 Dredging and breakwater 
1983 Dredging and breakwater 
1983 Dredging and breakwater 
1985 Major rehabilitation of locks and 
dams 
1983 Major rehabilitation of locks and 
dams 
1984 
1984 
Test Floating Breakwaters 
Breakwater 
Indefinite Dredging and bridge construction 
1984 Rehabilitation of breakwater 
1974 1986 Lock, dam and channel 
1983 1984 Dredging 
1984 Dredging and jetties 
1984 Dredging 
1990 Replace existing structure 
1984 Major rehabilitation of locks and 
dam 
1985 Major rehabilitation of locks and 
dam 
1983 1983 Dredging 
1984 Dredging and breakwater 
1968 1985 Locks and dams 
1981 1984 Breakwater and dredging 
1992 Regulating works 
1983 Rehabilitation of Lock and Dam 
No. 1 
1984 Dredging and jetties 
1980 Indefinite Navigation and bank stabilization 
complete-wildlife mitigation 
awaiting authorization 
1981 1982 Dredging 
1987 Major rehabilitation of locks and 
dams 
1984 Dredging 
D-1

APPENDIX D (Continued) 
NAVIGATION PROJECTS UNDER CONSTRUCTION DURING FISCAL YEAR 1983 
Fiscal Year 
Fiscal Placed in Completed or 
Year Useful Scheduled for 
Project Started Operation Completion Nature of Project 
Murrels Inlet, SC..................................... . 
Multnomah Channel, OR (Sec 107)......................... . 
New York Harbor, NY and NJ .............................. 
Newburgh Locks & Dam, Ohio River, IN and KY ............... 
Norfolk Harbor Channel, VA (1965 Mod.) ..................... 
Ogdensburg Harbor, NY (Sec 107) ........................... 
Ouachita and Black River, AR and LA ........................ 
Rysco Shipyard Channel, FL................................ 
Patchogue River, Westbrook, CT (Sec 107)..................... 
Port Everglades Harbor, FL ................................ 
Red River Emergency Bank Protection ....................... 
Red River WW, Mississippi River to Shreveport, LA ............. 
Rota Harbor, Northern Marianas (Sec 107) .................... 
Saco River, Camp Ellis Harbor, ME (Sec 107) .................. 
San Diego River and Mission Bay, CA ........................ 
San Francisco Bay to Stockton, CA (John F. Baldwin and 
Stockton Ship Channels) ................................. 
Smith Island, MO (Sec 107)................................. 
Smithland Locks and Dam, IL, IN, and KY .................... 
South Channel, Government Island, OR (Sec 107) ............... 
St. George Creek, MD (Sec 107)............................. 
St. Lucie Inlet, FL ........................................ 
Starved Rock Lock and Dam Illinois Waterway, IL .............. 
Tampa Harbor, FL (Main Channel) .......................... 
Tau Harbor, American Samoa (Sec 107) ....................... 
Tennessee-Tombigbee Waterway, AL and MS .................. 
Tilghman Island Harbor, MD (Sec 107) ....................... 
Uniontown Locks and Dam, Ohio River, IN and KY ............. 
Waianae Small Boat Harbor, Oahu, HI ....................... 
W allisville Lake, TX ...................................... 
West Harbor, OH ........................................ 
Winchester Bay, Umpqua River, OR (Sec 107).................. 
1977 
1981 
1976 
1965 
1966 
1983 
1964 
1981 
1983 
1979 
1973 
1974 
1982 
1982 
1948 
1971 
1982 
1971 
1983 
1983 
1979 
1980 
1976 
1977 
1973 
1982 
1965 
1977 
1967 
1981 
1982 
1981 
Incremental 
1969 
1967 
1981 
1983 
1982 
1980 
1983 
1983 
1982 
1970 
1983 Jetties and dredging 
1982 Dredging 
1993 Collection and removal of drift 
1983 Replacement of existing locks 
and dams 46 and 47 
Indefinite Deep draft channel, deepening 
and deferred anchorage const. 
1984 Dredging and diked disposal 
1983 Replacement of existing lock 
and dams 6 and 8 
1982 Dredging 
1984 Dredging 
1984 Dredging 
1985 Bank protection 
Indefinite Channel improvement and 
realignment 
1984 Dredging and breakwater 
1983 Dredging & icebreaker structures 
Indefinite Dredging and breakwater 
1992 Deep draft channel, widening, 
deepening and dredging 
1983 
1987 Replacement of existing locks 
and dams 50 and 51 
1984 Dredging 
1984 Dredging 
1984 Dredging, jetties & breakwaters 
1983 Major rehabilitation of lock and 
dam 
1986 Dredging 
1981 Dredging and breakwater 
1985 Dredging and locks and dams 
1983 Breakwater 
1983 Replacement of locks and dams 
48 and 49 
1979 Dredging and breakwater 
Indefinite Multipurpose lake (navigation, 
salinity control, water supply, 
fish & wildlife, & recreation) 
1983 Breakwaters 15-17 
1984 Channel improvement 
'Walter Jones Bridge completed; Coinjale Bridge under contract; the three remaining bridges have most been funded. 
D-2

APPENDIX E 
MULTIPLE-PURPOSE PROJECTS INCLUDING POWER IN OPERATION 
SEPTEMBER 30, 1983 
Flood Control 
and/or 
Total Nay. Feature 
Storage Place Initial Eziting Scheduled Ultimate 
Community Capability in UseMl Power Installatlo Installation Installation Proect eig Lea~th 
Project River in Vicinity (acre4eet Operation CY n FY (KW) (KW) (KW) Functlions Type (iFeeO (PeeO 
Albeni Falls, ID Pend Oreille Newport, WA 1,153,000 
Allatoona Lake, 
GA Etowah Cartersville, GA 670,000 
Barkley Dam & 
Lake Barkley, 
KY & TN Cumbrland Grand Rivers, KY 2,082,000 
Beaver lake, AR White Eureka Springs, 1,952,000 
AR 
Big Bend Dam 
Lake Sharpe), 
SD Missouri Chamberlain, SD 1,883,000 
Blakely Mountain 
Dam-Lake 
Ouachita, AR Ouachita Hot Springs, AR 2,768,000 
Bonneville L&D 
Lake Bonneville, 
OR & WA Columbia Bonneville, OR 537,000 
Broken Bow Lake, 
OK Columbia Broken Bow, OK 1,368,230 
Buford Dam, 
Lanier, GA Chattahoochee Buford, GA 2,554,000 
Bull Shoals Lake, Mountain Home, 
AR & MO White AR 5,408,000 
Carters Dam, GA Coosawattee Carters, GA 472,756 
Center Hill Lake, 
TN Caney Fork Lancaster, TN 2,092,000 
Cheatham L&D, 
TN Cumberland Ashland City, TN 104,000 
Chief Joseph Dam 
(Rufus Woods 
Lake), WA Columbia Bridgeport, WA 593,100 
Clark Hill Lake, 
GA & SC Savannah Augusta, GA 2,900,000 
Cordell Hull 
L&D, TN Cumberland Carthage, TN 310,900 
Cougar Lake, OR S. Fork, McKenzie Blue River, OR 219,000 
Dale Hollow 
Lake, TN & KY Obey Celina, TN 1,708,000 
Dardanelle L&D, 
AR Arkansas Dardanelle, AR 486,200 
DeGray Lake, AR Caddo Arkadelphia, AR 831,900 
Denison Dam 
(Lake Texoma), 
TX & OK Red Denison, TX 5,312,300 
Detroit Lake, OR, 
including Big 
Cliff Lake, OR North Santiam Mill City, OR 461,000 
Dworshak Dam N. Fork, 
& Reservoir, ID Cleanwater Orofino, ID 3,453,000 
Eufaula Lake, OK Canadian Eufaula, OK 3,798,000 
Fort Gibson 
Lake, OK Grand (Neosho) Ft. Gibson, OK 1,284,400 
Fort Peck Lake, 
MT Missouri Glasgow, MT 18,909,000 
Fort Randal Dam 
(Lake Francis 
Case), SD Missouri Lake Andes, SD 5,574,000 
Garrison Dam 
(Lake Sakaka. 
wea), ND Missouri Riverdale, ND 24,187,000 
Gavins Point Dam 
(Lewis & Clark 
Lake), SD & NE Missouri Yanktown, SD 504,000 
Green Peter Lake, 
OR, including 
Foster Lake, OR Middle Santiam Sweet Home, OR 491,000 
Greers Ferry 
Lake, AR Little Red Heber Springs 2,844,000 
Harry S. Truman 
Dam & Res. Osage Warsaw, MO 5,202,000 
Hartwell Lake, 
GA & SC Savannah Hartwell, GA 2,842,700 
Hills Creek Lake, Middle Fork 
OR Willamette Oakridge, OR 356,000 
Ice Harbor L&D 
(Lake Sacajawea), 
WA Snake Pasco, WA 417,000 
Jim Woodruff 
Dam (Lake 
Seminole), FL, 
GA & AL Appalachicola Chattahoochee, FL 367,300 
John Day L&D 
(Lake Umatilla), 
OR & WA Columbia Rufus, OR 2,500,000 
1952 1965 42,600 
1950 1960 74,000 
42,600 NFPR C 90 1,056 
74,000 FPRW C 190 1,250 
1964 1966 180,000 130,000 NPFR CE 17 9,969 
1963 1965 112,000 112,000 FPSR CE 228 2,575 
1964 1965 468,000 468,000 FPRIW E 95 10,570 
1953 1956 75,000 75,000 FPRWN E 235 1,100 
1938 1988 1,076,600 1,076,600 NPR C 122 2,6900 
1968 1970 100,000 100,000 FPWSR E 225 2,750 
1956 1967 86,000 86,000 NFPW E 192 5,400 
1952 1953 340,000 340,000 FPR C 258 2,256 
1975 1975 500,000 500,000 FPRW ER 450 1,9650 
1948 1951 135,000 1385,000 FPR CE 250 2,160 
1952 1958 36,000 36,000 NPR C 75 801 
1955 1956 2,069,000 204,160' 2,273,160 PIR C 220 4,300 
1952 1953 280,000 280,000 NFPRS CE 200 5,680 
1973 1974 100,000 100,000 NPR CE 98 1,806 
1963 1964 25,000 64,600 NFPRI ER 448 1,788 
1943 1949 84,000 54,000 FPR C 200 1,717 
1969 1965 124,000 124,000 NPR C 68 2,688 
1959 1972 68,000 40,000 108,000 FNPRSA E 243 8,400 
1944 
1953 
1972 
1964 
1960 
1938 
1945 70,000 175,000 FPSRN E 168 17,200 
1954 
1973 
1964 
1953 
1944 
118,000 
400,000 
90,000 
45,000 
185,250 
118,000 NFPRI C 382 1,528 
1,060,000 PNFR C 717 3,800 
90,000 FNPSR E 114 3,200 
67,500 FPR CE 110 2,090 
186,250 NFPRIW E 251 21,026 
1953 1954 820,000 820,000 NFPRIW E 166 10,700 
1964 1986 480,000 430,000 NFPRIW E 210 11,800 
1956 1957 100,000 100,000 NFPRIW E 74 8,700 
1967 1967 100,000 100,000 PFNIR C 840 1,880 
1962 1984 96,000 96,000 FPR8 C 248 1,704 
1982 1982' 160,000 160,000 FPRW CE 96 5,000 
1961 1962 264,000 330,000 NFPRS CE 204 17,862 
1961 1962 30,000 30,000 NFPRI GE 804 2,150 
1962 1962 608,000 603,000 NPRI CE 180 2,790 
1957 1957 80,000 30,000 NPRW CE 67 6,150 
1968 1968 11996699 22,,116800,,000000 22,,770000,0,0000 NNPPRRFFII CCEE 116611 5,,990000 
E-1

APPENDIX E (Continued) 
MULTIPLE-PURPOSE PROJECTS INCLUDING POWER IN OPERATION 
SEPTEMBER 30, 1983 
Flood Control 
and/or 
Total Nay. Feature 
Storage Place Initial Existing Scheduled Ultimate 
Community Capability in Useful Power Installation Installation Installation Project Height Length 
Project River in Vicinity (acre-feet)' Operation CY in FY (KW) (KW) (KW) Functions Type' (Feet) (Feet) 
John H. Kerr 
Dam & Res., 
NC & VA Roanoke Boydton, VA 2,750,300 
Jones Bluff L&D, 
AL Alabama Benton, AL 234,200 
J. Percy Priest 
Dam & Res., TN Stones Nashville, TN 652,000 
Keystone Lake, 
OK Arkansas Tulsa, OK 1,737,600 
Laurel River 
Lake, KY Laurel London, KY 435,600 
Libby Dam, Lake 
Koocanusa, MT Kootenai Libby, MT '* 5,869,000 
Little Goose L&D 
(Lake Bryan), 
WA Snake Starbuck, WA 565,000 
Lookout Point 
Lake, including Middle Fork, 
Dexter Lake, OR Willamette Lowell, OR 483,000 
Lost Creek Lake, 
OR Rogue Trail, OR 465,000 
Lower Granite 
L&D, WA Snake Pomercy, WA 484,000 
Lower Monumental 
L&D, 
WA Snake Kahlotus, WA 376,000 
McNary L&DLake 
Wallula, 
OR & WA Columbia Umatilla, OR 1,550,000 
Millers Ferry 
L&D, AL Alabama Camden, AL 331,800 
Narrows Dam- 
Lake Greeson, 
AR Little Missouri Murfreesboro, AR 407,900 
New Melones 
Lake, CA' Stanislaus Oakdale, CA 2,400,000 
Norfolk Lake, AR 
& MO North Fork Norfolk, AR 1,983,000 
Oahe Dam (Lake 
Oahe), SD & ND Missouri Pierre, SD 23,337,000 
Old Hickory Hendersonville, 
L&D, TN Cumberland TN 545,000 
Ozark-Jeta Taylor 
L&D, AR Arkansas Ozark, AR 148,400 
Philpott Lake, VA Roanoke Bassett, VA 318,500 
Robert S. Kerr 
L&D and Res., 
OK Arkansas Sallisaw, OK 525,700 
Sam Rayburn 
Dam & Res., TX Angelina Jasper, TX 3,997,600 
St. Mary's River, Sault Ste. Marie, 
MI Great Lakes MI - 
Snettisham, AK' Speel Juneau, AK 352,400 
Stockton Lake, 
MO Sac Stockton, MO 1,674,000 
Table Rock Lake, 
AR & MO White Branson, MO 3,462,000 
Tenkiller Lake, 
OK Illinois Gore, OK 1,230,800 
The Dalles L&D 
(Lake Celilo), 
WA & OR Columbia The Dalles, OR 53,000 
Walter F. George 
L&D, GA & FL Chattahoochee Fort Gaines, GA 934,000 
Webbers Falls Webbers Falls, 
L&D, OK Arkansas OK 170,100 
West Point Lake, 
AL & GA Chattahoochee West Point, GA 604,500 
Whitney Lake, TX Brazos Whitney, TX 1,999,500 
Wolf Creek Dam 
(Lake Cumberland), 
KY Cumberland Jamestown, KY 6,089,000 
1952 
1972 
1967 
1964 
1973 
1972 
1970 
1954 
1977 
1975 
1953 
1975 
1970 
1968 
1978 
1975 
204,000 204,000 FPRW CE 144 22,285 
68,000 68,000 NPRW CE 101 14,962 
28,000 28,000 FPRW CE 147 2,716 
70,000 70,000 FNPWSR E 121 4,600 
61,000 61,000 FPRW R 282 1,420 
420,000 105,000 840,000 FPR C 420 3,055 
1970 810,000 
1955 
1977 
1975 
1969 1969 
1953 
1969 
1950 
1978 
1943 
1959 
1954 
1969 
1951 
1970 
1965 
1855 
1969 
1958 
1952 
1957 
1963 
1970 
1975 
1953 
1950 
1954 
1970 
1950 
1979 
1944 
1962 
1957 
1973 
1954 
1971 
1966 
1952 
1973 
1973 
1959 
1953 
1957 
1963 
1973 
1975 
1954 
135,000 
49,000 
810,000 
810,000 
810,000 NPRI CE 160 2,670 
135,000 NFPRI CE 243 3,381 
49,000 DFPISWR CE 345 3,600 
810,000 NPRIF CE 146 3,200 
810,000 NPRI CE 135 3,800 
980,000 645,000' 1,625,000 NPRI CE 183 7,300 
75,000 75,000 NPRW CE 90 11,380 
25,500 
300,000 
80,550 
595,000 
100,000 
100,000 
14,000 
25,500 FPRW C 183.5 941 
300,000 FIPRW ER 625 1,560 
163,000 FPRS C 216 2,624 
595,000 NFPRIW E 245 9,300 
100,000 NPR CE 98 3,605 
100,000 NPR C 58 2,480 
14,000 FPR C 220 892 
110,000 110,000 NPR E 75 7,230 
52,000 52,000 FPWR CE 120 19,430 
Control 
18,400 18,400 NP Gate 
46,700 27,000' 73,700 P C' 18 338 
45,200 45,200 FPRW CE 128 5,100 
200,000 200,000 FPR CE 252 6,423 
34,000 34,000 FPR E 197 3,000 
1,806,800 
130,000 
60,000 
73,375 
30,000 
1952 270,000 
1,806,800 NPR CR 300 8,875 
130,000 NPRW CE 114 13,585 
60,000 NPR E 84 4,370 
108,375 FPRW CE 97 7,250 
30,000 FPR CE 159 17,695 
270,000 FPR CE 258 5,736 
'Total of all storage functions, including inactive and dead storage to normal full pool level. 
'G: gravel; R: rock; C: concrete; E: earth 
'Chief Joseph Additional Units & Operating Units 1-16 
'All units are synchronized-to-line and two units have passed the pumpback test. However, due to damaging effects to fish, no further pumping will be done for their testing or operation until a 
solution to the problem is found. 
'McNary Second Powerhouse Units 
'Being operated for the Department of Interior by the Bureau of Reclamation 
'Being operated by the Alaska Power Administration 
E-2

APPENDIX E (Continued) 
MULTIPLE-PURPOSE PROJECTS INCLUDING POWER IN OPERATION 
SEPTEMBER 30, 1983 
'Crater Lake Unit 
'Weir for Long Lake 
"Unit 5 only; 315,000 KW not scheduled 
Nomenclature for Project Functions 
D -Debris Control 
F -Flood Control 
I -Irrigation 
N -Navigation 
P -Power 
R -Public Recreation (Annual Attendance exceeding 5,000) 
S -Water Supply 
W-Fish and Wildlife (Federal or State) 
E-3

APPENDIX F 
MULTIPURPOSE PROJECTS INCLUDING POWER UNDER CONSTRUCTION 
SEPTEMBER 30, 1983 
Fiscal Scheduled Scheduled Nameplate Capacity 
Year for for Scheduled Ultimate 
Project Started Operation Completion Functions Installation Installation 
Bonneville Second Power House, OR 
and WA.............................. 1974 1981 1986 PR 558,200 558,200 
Clarence Cannon Dam, Salt River, MO ...... 1966 1985 1985 FSRPW 58,000 58,000 
Harry S. Truman Dam and Reservoir, 
Osage River, MO....................... 1965 1982' 1987' FRPW 160,000 160,000 
Libby Additional Units 5-8, MT ............ 1977 1984 Indefinite' P 420,000 105,000' 
Richard B. Russell Dam and Lake, 
Savannah River, GA and SC ............. .1975 1984 1990 FRP 600,000 600,000 
Cooper River, Charleston Harbor, SC ........ 1977 1984 1984 NWD 84,000 84,000 
'All units ther pumpairneg s ynchronized-to-line and two units have passed the pumpback test. However, due to damaging effects to fish, no fur- will be done for either testing or operation until a solution to the problem is found. 
'Units 6-8 indefinite by Congressional direction. 
KEY 
D -Redevelopment 
F -Flood Control 
I -Irrigation 
N -Navigation 
P -Power 
R -Recreation 
S -Water Supply 
W-Fish and Wildlife 
F-i

FLOOD DAMAGES PREVENTED BY CORPS PROJECTS BY DISTRICTS 
(IN THOUSANDS OF DOLLARS) 
District During FY 1983 
Memphis 
New Orleans 
St. Louis 
Vicksburg 
Kansas City 
Omaha 
New England 
Baltimore 
New York 
Norfolk 
Philadelphia 
Buffalo 
Chicago 
Detroit 
Rock Island 
St. Paul 
Alaska 
Portland 
Seattle 
Walla Walla 
Huntington 
Louisville 
Nashville 
Pittsburgh 
Pacific Ocean 
Charleston 
Jacksonville 
Mobile 
Savannah 
Wilmington 
Los Angeles 
Sacramento 
San Francisco 
Albuquerque 
Fort Worth 
Galveston 
Little Rock 
Tulsa 
TOTAL 
705,629 
16,985,567 
145,278 
2,724,171 
342,413 
92,883 
5,428 
12,002 
5,214
0 
12,952 
3,813
0 
1,646 
99,800 
9,216 
4,885 
496,436 
4,362 
46,712 
98,350 
86,847 
7,044 
15,122 
624 
163 
16,387 
5,766 
2,601 
24,467 
479,136 
612,248 
12,500 
29,965 
17,537
0 
61,702 
51,930 
23,220,796 
Cumulative through FY 1983 
5,679,230 
58,486,674* 
1,218,199 
24,534,7181 
4,590,216 
1,658,969 
936,873 
2,328,934 
102,114 
5,682 
38,204 
401,963
0= 
38,434$ 
730,044' 
286,454' 
31,418 
6,005,282 
234,090 
138,178 
3,166,191 
1,111,835 
439,590 
2,786,913 
11,511 
3,467* 
515,834 
107,447* 
18,582 
159,142* 
6,832,089 
2,814,2736 
112,594' 
251,949* 
1,517,1138 
364,363 
361,459* 
933,492' 
128,953,520 
*Revised figures. 
1Pearl Riber Basin transferred to LMVD in FY 1982, Cumulation flood damages through FY 1981 of $114,208 transferred 
to the Vicksburg District, however, Pearl River Basin remains within the Gulf and South Atlantic Region. 
'Adjustment in boundaries between Chicago and Rock Island District ($45,444) transferred from Chicago to Rock 
Island. 
'Includes 1 project ($651) transferred from St. Paul District to Detroit District due to adjustment in boundaries (Ball 
Park Creek Division at Bayfield, Wisconsin. 
'Information for Illinois River Basin not completely available. 
5Revised figures. Also excludes 1 project ($651) transferred from St. Paul District to Detroit District (Ball Park Creek 
Division at Bayfield, Wisconsin. 
'Includes 2 projects transferred from San Francisco District (Walnut Creek and Coyote Valley Dam). 
7Excludes 2 projects transferred from San Francisco District (Walnut Creek and Coyote Valley Dam. 
'Includes 2 projects previously in New Orleans District (Ferrell Bridge Dam, Lake O' the Pines and Wright Patman 
Dam and Lake). 
'Includes 4 projects transferred from Tulsa District (Dierks, DeQueen, Gilham and Millwood Reservoir, Little River 
Basin, Arkansas). 
G-1

FLOOD DAMAGES PREVENTED BY CORPS PROJECTS BY REGION 
(IN THOUSANDS OF DOLLARS) 
During FY 1983 Cumulative through FY 1983 
New England 
Mid-Atlantic 
Gulf and South Atlantic 
Ohio 
Tennessee 
Great Lakes 
Upper Mississippi 
Souris-Red-Rainy 
Missouri 
Arkansas-Red-White 
Lower Mississippi 
Rio Grande 
Texas and Gulf 
Colorado 
Great Basin 
California 
Columbia-North Pacific 
Alaska 
Hawaii 
TOTAL 
9,496 
25,703 
49,384 
207,363
0 
5,856 
251,594 
2,700 
435,296 
161,010 
20,386,036* 
29,918 
17,537 
13,000 
15,015 
1,075,869 
547,510 
4,885 
624 
23,220,796 
958,220 
2,437,550 
918,680* 
7,495,043 
9,486 
459,976 
2,035,956 
188,432 
6,249,185* 
2,345,357* 
87,616,215* 
178,509* 
1,881,476 
325,331 
26,540 
9,407,085 
6,377,550 
31,418 
11,511 
128,953,520 
*Revised figures. 
G-2 
District

INDEX 
The following abbreviations are used in the index: 
LMK 
LMM 
LMN 
LMS 
MR+T 
MRK 
MRO 
NAB 
NAN 
NAO 
NAP 
NCB 
NCC 
NCD 
NCE 
NCR 
NCS 
NED 
NPA 
NPP 
NPS 
VICKSBURG, MISS., DISTRICT 
MEMPHIS, TENN., DISTRICT 
NEW ORLEANS, LA., DISTRICT 
ST.LOUIS, MO., DISTRICT 
MISSISSIPPI, RIVER AND TRIBUTARIES 
KANSAS CITY, OM., DISTRICT 
OMAHA, NEBR., DISTRICT 
BALTIMORE, MD., DISTRICT 
NEW YORK, N.Y., DISTRICT 
NORFOLK, VA., DISTRICT 
PHILADELPHIA, PA., DISTRICT 
BUFFALO, N.Y., DISTRICT 
CHICAGO, ILL., DISTRICT 
MISSISSIPPI RIVER BETWEEN MISSOURI 
DETROIT, MICH., DISTRICT 
ROCK ISLAND, ILL., DISTRICT 
ST. PAUL, MINN., DISTRICT 
NEW ENGLAND DIVISION 
ALASKA DISTRICT 
PORTLAND, OREG., DISTRICT 
SEATTLE, WASH., DISTRICT 
A 
Aberdeen, Ohio (ORH) 25-20 
Aberdeen Creek, Va. (NAO) 5-24, 5-26 
Abilene, Kans. (MRK) 20-19, 20-23 
Abiquiu Dam, N. Mex. (SWA) 17-4, 17-10, 17-12 
Absecon Creek, N.J. (NAP) 3-24 
Absecon Inlet, N.J. (NAP) 3-2, 3-17, 3-21 
Accotink Creek, Va. (NAB) 4-36 
Ackerman Creek, Ill. (NCR) 28-3, 28-10, 28-13 
Adams, Mass. (NAN) 2-33 
Adams Creek, S.C. (SAN) 7-6, 7-15 
Adams Levee, Ind. (ORL) 24-23, 24-27 
Addison, N.Y. (NAB) 4-15, 4-27 
Adena, Ohio (Short Creek) (ORP) 26-24 
Adkin Branch, N.C. (SAW) 6-29 
Afono Area and Aoa Area, American Samoa (POD) 
36-15 
Agana Small Boat Harbor, Guam (POD) 36-14, 36-16 
AIWW-Mooring Basins, N.C. (SAW) 6-29 
Ala Wai Small Boat Harbor, Hawaii (POD) 36-14 
Alabama River at Montgomery, Ala. (SAM) 10-39 
Alameda Creek, Calif. (SPK) 35-24 
Alamo Lake, Ariz. (SPL) 33-5, 33-13, 33-18 
Alamogordo Diversion Channel, Tularosa (Closed) 
Basin, N. Mex. (SWA) 17-12 
Albemarle and Chespeake Canal (Great Bridge, Va.) 
(NAO) 5-24 
Albeni Ralls Dam, Idaho (NAS) 38-10, 38-16, 38-22 
NPW 
ORD 
ORH 
ORL 
ORN 
ORP 
POD 
SAJ 
SAM 
SAN 
SAS 
SAW 
SPK 
SPL 
SPN 
SWA 
SWF 
SWG 
SWL 
SWT 
WALLA WALLA, WASH., DISTRICT 
OHIO RIVER DIVISION 
HUNTINGTON, W. VA., DISTRICT 
LOUISVILLE, KY., DISTRICT 
NASHVILLE, TENN., DISTRICT 
PITTSBURGH, PA., DISTRICT 
PACIFIC OCEAN DIVISION 
JACKSONVILLE, FLA., DISTRICT 
MOBILE, ALA., DISTRICT 
CHARLESTON. S.C., DISTRICT 
SAVANNAH, GA., DISTRICT 
WILMINGTON, N.C., DISTRICT 
SACRAMENTO, CALIF., DISTRICT 
LOS ANGELES, CALIF., DISTRICT 
SAN FRANCISCO, CALIF., DISTRICT 
ALBURQUERQUE, N. MEX., DISTRICT 
FORT WORTH, TEX., DISTRICT 
GALVESTON, TEX., DISTRICT 
LITTLE ROCK, ARK., DISTRICT 
TULSA, OKLA., DISTRICT 
Alburquerque Diversion Channels, N. Mex. (SWA) 
17-1, 17-9 
Alford, Mass. (NED) 1-29, 1-55, 1-62 
Algoma Harbor, Wis (NCE) 31-74, 31-75 
Alhambra Creek, Calif. (SPK) 35-24 
Aliso Creek Dam, Calif. (SPL) 33-27 
Allatoona Lake, Ga. (SAM) 10-17, 10-26, 10-35 
Allegany, N.Y. Unit I (Allegheny River) (ORP) 26-24 
Allegany, N.Y. Unit II (Five Mile Creek Area) (ORP) 
26-23, 26-27 
Allegneny River, Pa. (ORP) 26-2, 26-14, 26-18, 26-22, 
26-27 
Allegheny River, Pa., Locks and Dams (ORP) 26-24 
Allegheny River, Oil City, Pa. (ORP) 26-3, 26-14 
Allentown, Pa. (NAP) 3-26 
Allenville, Ariz. (SPL) 33-5, 33-13, 33-18 
Alley Bay, Beals, Maine (NED) 1-55 
Alloway Creek, N.J. (NAP) 3-24 
Alluvial Valley Mapping (MR+T) 42-3 
Alma Harbor, Wis. (NCD) 29-8 
Almond Lake, N.Y. (NAB) 4-15, 4-27 
Almond Village, N.Y. (NAB) 4-39 
Aloha-Rigolette Area, Grant and Rapides Pairshes, La 
(LMN) (LMK) 11-36, 12-25 
Alpena Harbor, Mich. (NCE) 31-74, 31-75 
Alpine Dam, Rockford, Ill. (NCR) 28-18 
Alpine, Tex. (SWA) 17-12 
Alsea River, Oreg. (NPP) 37-43 
Altamaha, Oconee, and Ocmulgee Rivers, Ga. (SAS) 
8-1, 8-11, 8-12 
Alteration of Berwick Bay Bridge (LMN) 11-34 
I-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Alternative for Sugar Hill Reservoir (NED) 1-57 
Alton, Ind. (ORL) 24-23, 24-26 
Altus Reservoir, Okla. (SWT) 19-13 
Alum Creek Lake, Ohio (ORH) 25-2, 25-11, 25-15 
Alvin R. Bush Dam, Pa. (MAB) 4-20, 4-29 
Amazon Creek, Oreg. (NPP) 37-46 
American Lake, Vicinity of Fort Lewis, Wash. (NPS) 
38-8, 38-25 
American River, Calif. (SPK) 35-24 
Ames Lake, Iowa (NCR) 28-17 
Amesbury, Mass. (NED) 1-29, 1-55, 1-63 
Amite River, La. (MR+T) 42-16 
Amite River and Bayou Manchac, La. (LMN) 11-34 
Amite River and Tributaries, La. (LMN) 11-36 
Amsterdam, Ohio (ORP) 26-23, 26-29 
Anacortes Harbor, Wash. (NPS) 38-2, 38-13, 38-18, 
38-31 
Anacortes Navigation Channel, Wash. (NPS) 38-24, 
38-31 
Anacostia River and Flates (NAB) 4-36 
Anacostia River and Tributaries, Md. (NAB) 4-38, 4-40 
Anacostia River and Tributaries, Flood Protection and 
Navigation Improvements, D.C. and Md. (NAB) 4-38 
Anacostia River Basin, Md. (NAB) 4-41 
Anaheim Bay Harbor, Orange County, Calif. (SPL) 
33-22 
Anahuac Channel, Tex. (SWG) 15-8 
Anchorage Harbor, Alaska (NPA) 40-1, 40-8, 40-10, 
40-13 
Anclote River, Fla. (SAJ) 9-49, 9-50 
Andalusia Harabor, Ill. (NCP) 29-9 
Anderson, Ind. (ORL) 24-22 
Anderson Park, Newport News, Va. (NAO) 5-26 
Andover Lake, Conn. (NED) 1-57 
Andrews, George W., Lock and Dam, Ala. and Ga. 
(SAM) 10-19, 10-27, 10-36 
Andrews River, Mass. (NED) 1-50 
Angler-Use Sites, Meramec Basin, Mo. (LMS) 14-41 
Annapolis Harbor, Md. (LMS) 4-36 
Ansonia, Conn. (NED) 1-29, 1-55, 1-62 
Anthony Shoals Dam and Lake, Ga. (SAS) 8-17 
Apalachee Bay, Fla. to New Orleans, La. (SAM) 10-31 
Apalachicola Bay, Fla. (SAM) 10-2, 10-23, 10-28 
Apalachicola Bay to St. Marks River, Fla. (SAM) 10-31 
Apalachicola, Chattahoochee and Flint Rivers, Ala. 
Ga. and Fla. (SAM) 10-18, 10-26, 10-36, 10-42 
Apoon Mouth of Yukon River, Alaska (NAP) 40-12 
Appanoose Township, Hancock County, Ill. (NCR) 
28-3, 28-10, 28-13 
Appleton First Lock, Wisc. (NCE) 31-73 
Appleton Fourth Lock, Wis. (NCE) 31-73 
Appleton Lower Dam, Wis. (NCE) 31-73 
Appleton Second Locks, Wis. (NCE) 31-73 
Appleton Third Locks, Wis. (NCE) 31-73 
Applegate Lake, Oreg. (NPP) 37-12, 37-29, 37-39, 37-51 
Appomattox River, Va. (NAO) 5-24 
Apponaug Cove, R.I. (NED) 1-50 
Appoquinimink River, Del. (NAP) 3-24, 3-27 
Aquashicola Reservoir, Pa. (NAP) 3-26 
Aquatic Plant Control 
Buffalo, N.Y., District (NCB) 32-32 
Charleston, S.C., District (SAN) 7-2, 7-9, 7-11, 7-15 
Galveston, Tex., District (SWG) 15-2, 15-13, 15-16, 
15-27 
Jacksonville, Fla., District (SAJ) 9-2, 9-14, 9-29, 9-31, 
9-35, 9-50 
Mobile, Ala., District (SAM) 10-3, 10-23, 10-28 
New England Division (NED) 1-3, 1-32, 1-41 
New Orleans, La., District (LMN) 11-2, 11-21, 11-26 
New York, N.Y., District (NAN) 2-2, 2-20, 2-24 
Philadelphia, Pa., District (NAP) 3-24 
Portland, Oreg., District (NPP) 37-7 
Sacramento, Calif., District (SPK) 35-24 
Savannah, Ga., District (SAS) 8-2, 8-11, 8-13, 8-16 
Seattle, Wash., District (NPS) 27-18 
Southwestern Division (SWG) 15-2, 15-13, 15-16, 
15-27 
St. Paul, Minn., District (NCSZ) 27-18 
Wilmington, NC., District (SAW) 6-2, 6-19, 6-26 
Aquia Creek, Va. (NAB) 4-36 
Aquilla Lake, Tex. (SWF) 16-2, 16-16, 6-20 
Aquia Creek, Va. (NAB) 4-36 
Aquilla Lake, Tex. (SWF) 16-2, 16-16, 6-20 
Ararat River, Surry County, N.C. (SAW) 6-10, 6-20 
Arbuckle Reservoir, Okla. (SWT) 19-13 
Arcadia Harbor, Mich. (NCE) 31-2, 31-37, 31-53 
Arcadia Lake, Okla. (SWT) 19-4, 19-18, 19-22 
Arch Creek, Fla. (SAJ) 9-57 
Archers Creek, s.c. (SAN) 7-15 
Ardsley, N.Y. (NAN) 2-11, 2-22, 2-27 
Area East of Albany, Oreg. (NPP) 37-48 
Arecibo Harbor, P.R. (SAJ) 9-2, 9-29, 9-35, 9-49 
Argyle, Minn., Middle River (NCS) 27-29 
Arabutla Lake, Miss. (MR+T) 42-21, 42-57 
Arkansas-Red River Basins Chloride Control, Okla. 
and Tex. (SWT) 19-4, 19-5, 19-17, 19-18, 19-22, 19-24, 
19-25, 19-26 
Arkansas River Basin, Ark. Okla. (Kans. (SWL) 
(SWT) 18-2, 18-10, 18-13, 18-18, 18-21, 19-2, 19-25 
Arkansas River, Great Bend, Kans. to Tulsa, Okla. 
(SWT) 19-17 
Arkansas River Plan, Okla. (SWT) 19-25 
Arkansas River Project Levees (MR +T) 42-46, 42-49 
Arkansas River Standard Revetments and Dikes 
(MR+T) 42-37 
Arkport Dam, N.Y. (NAB) 4-15, 4-27 
Arlington Lake, Mo. (MRK) 20-20 
Armuchee Creek, Ga. (SAM) 10-39 
Arroyo Colorado, Tex. (SWG) 15-9, 15-14, 15-25 
Asan Village, Territory of Guam (POD) 36-5, 36-11 
Ashland, Ky. (ORH) 25-19, 25-21 
Ashland Harbor, Wis. (NCE) 31-2, 31-37, 31-53 
Ashland River, S.C. (SAN) 7-6, 7-15 
Ashtabula Harbor, Ohio (NCB) 32-2, 32-17, 32-21 
Asotin Creek, Idaho (NPW) 39-17 
Asotin Dam, Idaho and Wash. (NPW) 39-19 
Asquiroga Bay, Territory of Guam (POD) 36-11 
Astoria Turning Basin, Oreg. (NPP) 37-43 
Atchafalaya River and Bayous Chene, Boeuf, and 
Black, La. (LMN) 11-2, 11-21, 11-26 
Atchalafaya River Basin, La. (MR+T) 42-5, 42-14, 
42-28, 42-56, 42-58 
I-2

INDEX 
Atchafalaya River, Morgan City to Gulf of Mexico, La. 
(LMN) 11-34 
Atchafalaya River, Standard Revetments (MR+T) 
42-32 
Atchison, Kans. (MRK) 20-19 
Athalia, Ohio (ORH) 25-20 
Athens, Ohio (ORH)25-19, 25-21 
Atlantic Beach Channels, N.J. (NP) 6-26, 6-30 
Atlantic City, N.J. (NAP)3-26 
Atlantic Coast of N.J. Sandy Hook to Barnegat Inlets 
(NAN) 2-32 
Atlantic Gulf Ship Canal, Fla. (SAJ) 9-50 
Atlantic Intracoastal Waterway between Norfolk, Va. 
and St. Johns River, Fla. (NAO) (SAW) (SAN) (SAS) 
(SAJ) 5-2, 5-15, 5-19, 5-24, 5-26, 6-2, 6-19, 6-23, 7-2, 
7-9, 7-11, 8-2, 8-11, 8-13, 9-2, 9-29, 9-35, 9-49 
Au Sable, Mich. (NCE) 31-3, 31-37, 31-53 
Auasi Harbor, American Samoa (POD) 36-14, 36-16 
Aubrey Lake, Tex. (SWF) 16-10, 16-17, 16-21 
Auburn, N.Y., Owasco Outlet (NCB) 32-34 
Augusta, Ga. (SAS) 8-16 
Augusta, Ky. (ORH) 25-19 
Augusta Levee, Kans. (SWT) 19-24 
Aunuu Harbor, American Samoa (POD) 36-14, 36-16 
Aurora, Ind. (ORL) 24-23, 24-27 
Avoca, N.Y. (NAB) 4-15, 4-27 
Avon Harbor, N.C. (SAW) 6-26 
Aylesworth Creek Lake, Pa. (NAB) 4-14, 4-27 
B 
B. Everett Jordan Dam and Lake, N.C. (Formerly New 
Hope Lake, N.C.) (SAW) 6-11, 6-21 
Bachelor Island, Wash. (NPP) 37-48, 37-52 
Back Creek, Md. (NAB) 4-36, 4-40 
Bad River, Bank Protection, Fort Pierre, S. Dak. 
(MRO) 21-20 
Bagaduce River, Maine (NED) 1-26, 1-39, 1-49, 1-57 
Bailey, R.D., Lake, W. Va. (ORH) 25-8, 25-14, 25-17 
Bainbridge, N.Y. (NAB) 4-38, 4-41 
Baker Brook, Mass. (NED) 1-57 
Bakers Haulover Inlet, Fla. (SAJ) 9-49, 9-50 
Ball Mountain Lake, Vt. (NED) 1-16, 1-36, 1-60 
Baltimore Harbor, Md. Collection and Removal of 
Drift (NAB) 4-4, 4-24, 4-31 
Baltimore Harbor, Md. Prevention of Obstruction and 
Injurious Deposits (NAB) 4-9, 4-25, 4-33 
Baltimore Harbor and Channels, Md. and Va. (NAB) 
4-3, 4-24, 4-30 
Baltimore Harbor and Channels (Norfolk District) 
(NAO) 5-2, 5-15, 5-19, 5-26 
Bandon Small Boat Basin, Oreg. (NPP) 37-2, 37-26, 
37-33 
Bank Revetments and Dikes (MR+T) 42-30, 42-34, 
42-39 
Bank Stabilization & Channel Rectification, Ark. 
(SWL) 18-2, 18-10, 18-20 
Bank Stabilization and Channel Rectification, 
Arkansas River, Ark. and Okla. (SWT) 19-3, 19-18, 
19-25 
Bank Stabilization, Red River Below Dennison (SWT) 
19-24, 19-26 
Banner Special Drainage and Levee Districts (NCR) 
28-16, 28-18 
Banning Levee-San Gorgonio River, Calif. (SPL) 33-24 
Bar Harbor, Maine (NED) 1-50 
Bar Point Harbor, Alaska (NPA) 40-2, 40-8, 40-10 
Barataria Bay Waterway, La. (LMN) 11-3, 11-21, 11-26 
Barbers Point Harbor, Hawaii (POD) 36-2, 36-10, 36-12 
Barbourville, Ky. (ORN) 23-13, 23-19 
Barcelona Harbor, N.Y. (NCB) 32-2, 32-17 
Bardwell Lake, Tex. (SWF) 16-3, 16-16- 16-20 
Barkley Dam and Lake Barkley, Ky. and Tenn. (ORN) 
23-14 
Barnard, Kans. (MRK) 20-19 
Barnegat Inlet, N.J. (NAP) 3-2, 3-17, 3-21 
Barnett Creek, Ky. (ORL) 24-25 
Barre Falls Dam, Mass. (NED) 1-16, 1-36, 1-60 
Barren River Lake, Ky. (ORL) 24-5, 24-15, 24-28 
Bartley, Nebr. (MRK) 20-19, 20-23 
Bass Harbor, Maine (NED) 1-50 
Bass Harbor Bar, Maine (NED) 1-50 
Bassett Creek, Minn. (NCS) 27-3, 27-19 
Bastrop Bayou, Tex. (SWG) 15-27 
Batavia and Vicinity, N.Y. (NCB) 32-34 
Bath, N.Y. (NAB) 4-38, 4-41 
Baton Rouge Harbor, La. (LMN) 11-34 
Baton Rouge Harobr (Devil's Swamp), La. (MR+T) 
42-6, 42-50 
Battle Creek, Bank Protection, Battle Creek, Nebr. 
(MRO) 21-21 
Baudette Harbor, Minn. (NCS) 27-32 
Bay City Harbor, Wis. (NCD) 29-8 
Bay Ridge and Red Hook Channels, N.Y. (NAN) 2-2, 
2-20, 2-24, 2-30 
Bay River, N.C. (SAW) 6-26 
Bayard, W. Va. (NAB) 4-38, 4-41 
Bayfield Harbor, Wis. (NCE) 31-75 
Bayou Bartholomew and Tributaries, Ark. and La. 
(LMK) 12-6, 12-14, 12-17, 12-21, 12-22 
Bayou Bodcau and Tributaries, Ark. and La. (LMn) 
(LMK) 11-23, 12-6, 12-14, 12-17 
Bayou Bodcau, Red Chute, and Loggy Bayou, La. 
(LMN) (LMK) 11-36, 12-25 
Bayou Bodcau, Reservoir, La. (LMN) (LMK) 11-23, 
12-7, 12-14, 12-17, 12-22 
Bayou Bonfouca, La. (LMN) 11-34 
Bayou Choupique, La. (LMN) 11-36 
Bayou Cocodrie and Tributaries, La. (MR+T) 42-6, 
42-15, 42-28, 42-54, 42-58 
Bayou Coden, Ala. (SAM) 10-3, 10-23, 10-28 
Bayou Dorcheat, Loggy Bayou and Lake Bisteneau, 
La. (LMN) 11-34 
Bayou Dupre, La. (LMN) 11-34 
Bayou Galere, Miss. (SAM) 10-39 
Bayou Grosse Tete, La. (LMN) 11-34 
Bayou La Batre, Ala. (SAM) 10-3, 10-23, 10-28 
TBayou La Loutre, St. Malo, and Yscolskey, La. (LMN) 
11-34 
I-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Bayou Lacombe, La. (LMN) 11-34 
Bayou Lafourche and Lafourche-Jump Waterway, La. 
(LMN) 11-3. 11-21, 11-26 
Bayou Meto, Ark. (MR+T) 42-52 
Bayou Nicholas, Coushatta, La. (LMN) 11-36 
Bayou Pierre, La. (LMN) (LMK) 11-23, 11-36, 12-7, 
12-14, 12-17, 12-25 
Bayou Plaquemine Brule, La. (LMN) 11-34 
Bayou Queue de Tortue, La. (LMN) 11-34 
Bayou Rapides, La. (LMN) 11-36 
Bayou Segnette Waterway, La. (LMN) 11-34 
Bayou Teche, La. (LMN) 11-5, 11-21, 11-26, 11-31 
Bayou Teche and Vermilion River, La. (LMN) 11-4, 
11-21, 11-26 
Bayou Terrebonne, La. (LMN) 11-34 
Bayou Vermilion, La. (LMN) 11-34 
Bayous D'Arbonne and Corney, La. (LMK) 12-21 
Bayous Des Glaise Diversion Channel, La. (MR+T) 
42-50 
Bayous Rapides, Boeuf, and Cocodrie (MR+T) 42-50 
Bayport, Fla. (SAJ) 9-50 
Bayport Harbor, Mich. (NCE) 31-74, 31-75 
Baytown, Tex. (SWG) 15-27 
Beals Harbor, Maine (NED) 1-50 
Beals Island, Maine (NED) 1-29 
Bear Creek, Mont. (NPS) 38-25 
Bear Creek, Oreg, (NPP) 37-46, 37-48 
Bear Creek Dam (City of Hannibal, Mo.) (NCR) 28-16, 
28-18 
Bear Creek, Hannibal, Mo. (NCR) 28-18 
Bear Creek, Kendrick, Idaho (NPW) 39-17, 39-21 
Bear Creek, La Quinta, Calif. (SPL) 33-31 
Bear Creek Lake, Colo. (MRO) 21-2, 21-10, 21-12 
Bear River, Calif. (SPK) 35-23 
Beards Brook Reservoir, N.H. (NED) 1-57 
Beatrice, Nebr. (MKR) 20-20 
Beaufort Harbor, N.C. (SAW) 6-4, 6-19, 6-24 
Beaver and Mahoning Rivers, Pa. and Ohio (ORP) 
26-22 
Beaver Bay Harbor, Minn. (NCE) 31-74, 31-75 
Beaver Brook Lake, N.H. (NED) 1-57 
Beaver Creek, Montezuma, Ga. (SAM) 10-39 
Beaver Creek near Tillamook, Oreg. (NPP) 37-46 
Beaver Drainage District, Oreg. (NPP) 37-13, 37-29, 
37-39, 37-52 
Beaver Lake, Ark. (SWL) 18-7, 18-11, 18-23 
Bedford, Iowa (MRK) 20-19 
Beech Fork Lake, W. Va. (ORH) 25-2, 25-11, 25-15 
Belfast Harbor, Maine (NED) 1-50 
Belhaven Harbor, N.C. (SAW) 6-26, 6-30 
Bell Foley Lake, White River Basin, Ark. (SWL) 18-16, 
18-23 
Bellaire, Ohio (ORP) 26-24 
Bellamy River, N.H. (NED) 1-50 
Belle Fourche, S. Dak. (MRO) 21-16, 21-20 
Belle River Harbor, Mich. (NCE) 31-74, 31-75 
Belleville Locks and Dam, Ohio (ORD) 22-1, 22-8 
Bellevue, Ky. (ORL) 24-23, 24-26 
Bellingham Harbor, Wash. (NPS) 38-2, 38-13, 38-18, 
38-31 
Bellingham Harbor, Wash. (I and J Street Waterway) 
(NPS) 38-24 
Bellingham, Squalicum Small Boat Harbor, Wash. 
(NPS) 38-24 
Belpre, Ohio (ORH) 25-20 
Belton Lake, Tex. (SWF) 16-3, 16-16, 16-20 
Belton Lake Modification, Tex. (SWF) 16-14 
Beltzville Lake, Pa. (NAP) 3-11, 3-19 
Benbrook Lake, Tex. (SWF) 16-3, 16-16, 16-20 
Bennett-McDonald-Smithland D.D., Little Sioux River 
Iowa, (MRO) 21-21 
Bennington, Vt. (NAN) 2-33 
Bennington Reservoir, N.H. (NED) 1-57 
Benwood, W. Va. (ORP) 26-23, 26-27 
Berkeley Harbor, Calif. (SPN) 34-10 
Berkeley Marina, Calif. (SPN) 34-10 
Berlin Lake, Ohio (ORP) 26-5, 26-14, 26-19 
Brewick Bay Bridge Alteration (LMN) 11-34 
Bethel Small Boat Harbor, Alaska (NPA) 40-2, 40-8, 
40-10 
Bethelehem, Pa. (NAP) 3-26 
Bettendorf, Iowa (NCR) 28-3, 28-10, 28-13 
Betterton Harbor, Md. (NAB) 4-36 
Beverly Harbor, Mass. (NED) 1-50 
Big and Little Sallisaw Creeks Navigation Project, 
Okla. (SWT) 19-2, 19-18, 19-22 
Big Bay Harbor, Mich. (NCE) 31-3, 31-37, 31-53 
Big Bend, W. Va. (ORH) 25-20 
Big Bend Dam-Lake Sharpe, S. Dak. (MRO) 21-7, 
21-11, 21-15 
Big Black River, Miss. (LMK) 12-21, 12-25 
Big Blue Lake, Ind. (ORL) 24-23, 24-29 
Big Blue River, Nebr. (MRK) 20-9, 20-19 
Big Choctaw Bayou, La. (LMK) 12-25 
Big Creek and L'Anguille River, Ark. (LMM) 13-10 
Big Creek Canal, Millington, Tenn. (LMM) 13-10 
Big (Cunningham) Creek, Ohio (NCB) 32-32 
Big Darby, Ohio (ORH) 25-20 
Big Dry Creek Dam and Diversion, Calif. (SPK) 35-24 
Big Fossil Creek, Tex. (SWF) 16-23 
Big Fossil Creek Floodway, Tex. (SWF) 16-23 
Big Hole River, Pennington Bridge, near Twin 
Bridges, Mont. (MRO) 21-20 
Big Horn River, Two Leggin Bridge, near Hardin, 
Mont. (MRO) 21-20 
Big Lake Drainage and Levee Dsitrict, Ill. (NCR) 
28-16, 28-18 
Big Pigeon and Little Pigeon Bayous, La. (LMN) 11-34 
Big Pine Lake, Ind. (ORL) 24-22 
Big Pine Lake, Tex, (SWT) 19-6, 19-18, 19-22 
Big Run, Pa. (ORP) 26-23, 26-29 
Big Sandy Lake, Tex. (SWF) 16-3, 16-16, 16-20 
Big Sandy River, W. Va. and Ky., including Levisa 
and Tug Forks (ORH) 25-18 
Big Sioux River at Sioux City, Iowa and S. Dak. 
(MRO) 21-16 
Big Sioux River, Fink Bridge, near Flandreau, S. Dak. 
(MRO) 21-20 
Big Sioux River, Schofield Bridge, near Flandreau, S. 
Dak. (MRO) 21-20 
Big Slough & Mayo Ditch, Ark. (MR+T) 42-57 
Big South Fork National River and Recreation Area, 
14

INDEX 
Ky. and Tenn. (ORN) 23-4, 23-9 
Big Spring, Tex. (SWF) 16-23 
Big Stone Lake and Whetstone River, Minn. and S. 
Dak. (NCS) 27-4, 27-19 
Big Stranger Creek, Kans. (MRK) 20-19 
Big Suamico Harbor, Wis. (NCE) 31-74 
Big Suamico River, Wis. (NCE) 31-75 
Big Sunflower River, Miss. (LMK) (MR+T) 12-21, 
42-51 
Big Swan Drainage and Levee District, Ill. (LMS) 
14-14 
Big Timber Creek, N.J. (NAP) 3-24 
Big Walnut Lake, Ind. (ORL) 42-22, 24-29 
Big Wash, Milford, Utah (SPK) 35-24 
Billings, Montana (MRO) 21-17 
Biloxi Harbor, Miss. (SAM) 10-4, 10-23, 10-29 
Binghamton, N.Y. (NAB) 4-15, 4-27 
Birch, W. Va. (ORH) 25-19 
Birch Hill Dam. Mass. (NED) 1-16, 1-36, 1-60 
Birch Lake, Okla. (SWT) 19-6, 19-18 
Bird Rock Area, La Jolla, Calif. (SPL) 33-22 
Birds Point-New Madrid Floodway, Mo. (MR +T) 42-53 
Biscayne Bay, Fla., Hurricane Protection (SAJ) 9-57 
Black Bayou-Pine Island Area, La. (LMN) 11-36 
Black Bayou Reservoir, La. (LMN) (LMK) 11-36, 12-25 
Black Creek, Gadshen, Ala. (SAM) 10-39 
Black Fork at Hendricks, W. Va. (ORP) 26-23 
Black River, Ark. & Mo. (SWL) 18-15 
Black River, Mich. (NCE) 31-74, 31-75 
Black River, N.C. (SAW) 6-11, 6-20, 6-26 
Black River, Wis. (NCS) 27-32, 27-25, 27-28 
Black River Harbor, Mich. (NCE) 31-3, 31-37, 31-53, 
31-74, 31-75, 31-77 
Black River Harbor, N.Y. (NCB) 32-32 
Black River Lake, Wis. (NCS) 27-25 
Black River, Poplar Bluff, Mo., To Knobel, Ark. (SWL) 
18-16 
Black River (Port Huron), Mich. (NCE) 31-74, 31-75 
Black Rock Channel and Tonawanda Harbor, N.Y. 
(NCB) 32-2, 32-17, 32-21, 32-36 
Black Rock Harbor, Conn. (NED) 1-3, 1-32, 1-41 
Black Rock Lake, Conn. (NED) 1-21, 1-37, 1-61 
Black Walnut Point, Md. (NAB) 4-12, 4-26, 4-34, 4-36 
Black Warrior and Tombigbee Rivers, Ala. (SAM) 
104, 10-23, 10-29, 10-37 
Blackbird Creek near Macy, Nebr. (MRO) 21-16, 21-21 
Blackfoot Area, Snake River, Idaho (NPW) 39-17, 
39-20 
Blackfoot Reservoir, Idaho (NPW) 39-17 
Blackfoot River, Idaho (NPW) 39-17, 39-20,39-21 
Blackfoot River, Mont. (NPS) 38-25 
Blackhawk Creek, Davenport, Iowa (NCR) 28-18 
Blackstone, Mass. (NED) 1-29 
Blackstone River Basin, Mass. and R.I. (NED) 1-14, 
1-30, 1-59 
Blackwater Dam, N.H. (NED) 1-24, 1-38, 1-63 
Blackwater River, Fla. (SAM) 10-37, 10-38 
Blackwater River, Va. (NAO) 5-24 
Blaine, Maine (NED) 1-29 
Blaine Harbor, Wash. (NPS) 38-24, 38-31 
Blair and Sitcom Waterways, Tacoma Harabor, Wash. 
(NPS) 3 "2 
Blakely Mountain Dam-Lake Quachita, Ark. (LKM) 
12-7, 12-14, 12-22 
Blind Slough Diking District, Oreg. (NPP) 3744 
Bloomington Lake, Md. and W. Va. (NAB) 4-12, 4-26, 
4-34 
Blue Marsh Lake, Pa. (NAP) 3-12, 3-19 
Blue Mountain Lake, Ark. (SWL) 18-5, 18-11, 18-21 
Blue River Basin (Kansas City District) (MRK) 20-2, 
20-15 
Blue River Channel, Kansas City, Mo. (MRK) 20-2, 
20-11, 20-15 
Blue River Lake, Oreg. (NPP) 37-13, 37-29, 37-39, 
37-51, 37-53 
Bluestone Lake, W. Va. (ORH) 52-3, 25-11, 25-15 
Bluff Creek, Miss (SAM) 10-38 
Board of Engineers for Rivers and Harbors (BERH) 
41-1 
Bodega Bay, Calif. (SPN) 43-3, 34-4, 34-6 
Bodie Island, N.C. (SAW) 6-29 
Boeuf and Tensas Rivers and Bayou Macon, Ark. and 
La. (MR �T) 42-51 
Boeuf River, La. (LMN) 12-21 
Bogachiel River, Wash. (NPS) 38-25 
Boggy Creek, Tex. (SWF) 16-4, 16-16, 16-20 
Boise Valley, Idaho (NPW) 39-17, 39-19, 39-20 
Bolles Harbor, Mich. (NCE) 31-31, 31-75 
Bon Secour River, Ala. (SAM) 10-5, 10-23, 10-30, 10-38 
Bonnet Carre Spillway, La. (MR+T) 42-6, 42-56, 42-58 
Bonneville Lock and Dam-Lock Bonneville, Oreg. and 
Wash. (NP 37-19, 37-25, 37-30, 37-40, 37-54 
Bonpas Creek, Ill. (ORL) 24-23, 24-27, 24-32 
Bonum Creek, Va. (NAB) 4-36 
Boone County, Ky. (ORL) 24-21, 24-31 
Booneville Lake, Ky. (ORL) 24-22, 24-28 
Boothbay Harbor, Maine (NED) 1-50 
Boston Harbor, Mass. (NED) 1-3, 1-32, 1-41, 1-64 
Boswell Lake, Okla. (SWT) 19-24, 19-26 
Boulder Creek, Boulder, Colo. (MRO) 21-16 
Bound Brook, Scituate, Mass. (NED) 1-55 
Bowman, Leland, Lock, La. (formerly Vermilion Lock) 
(LMN) 11-10, 11-22, 11-28 
Bowman-Haley Lake, N. Dak. (MRO) 21-2, 21-10, 
21-12 
Brackenridge, Tarentum and Natrona, Pal (ORP) 
62-23, 26-27 
Bradford, Pa. (ORP) 26-23, 26-29 
Bradford, Tenns. (LMM) 13-3, 13-6, 13-8 
Bradley Lake, Alaska (NPA) 40-7 
Bramwell, W. Va. (ORH) 25-21 
Brandenburg, Ky. (ORL) 24-31 
Brandon Road Lock and Dam, Ill. (NCC) 28-22, 28-23 
Branford Harbor, Conn. (NED) 1-50 
Branson Cove, Va. (NAB) 4-36, 4-41 
Brant Rock Beach, Marshfield, Mass. (NED) 1-57 
Braymer Lake, Mo. (MRK) 20-19 
Brazos Island Harbor, Tex. (SWG) 15-2, 15-13, 15-16, 
15-28, 15-29, 15-34 
Brazos River, Tex., Velasco to Old Washington (SWG) 
15-27 
Breton Bay, Md. (NAB) 4-36 
I-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Brevard County, Fla. (SAJ) 9-19, 9-32, 9-43 
Brevoort Levee, Ill. (ORL) 42-22, 42-30 
Bridge Alterations Authorized 
Chicago, ill., District (NCC) 30-15 
Nashville, Tenn., District (ORN) 23-4 
New England Division (NED) 1-13 
Bridgeport Harbor, Conn. (NED) 1-4, 1-32, 1-42, 1-57 
Bridges, Columbia River, Oreg. (NPP) 37-43 
Bridgewater, Va. (NAB) 4-38, 4-41 
Brilliant, Ohio (ORP) 26-24 
Bristol Harbor, R.I. (NEDt)) 14, 1-32, 1-42 
Broad Creek, Md. (NAB) 4-36 
Broad Creek, N.C. (SAW) 6-28 
Broad Creek, Va. (NAO) 5-3, 5-15' 5-19, 5-26 
Broadkill River, Del. (NAP) 3-24 
Broadwater Creek, Md. (NAB) 4-39 
Broadway Lake, S.C. (SAS( 8-7, 8-11, 8-15 
Brockway, Pa. (ORP) 26-24 
Brockway Lake, Vt. (NED) 1-57 
Broken Bow, Nebr. (MRO) 21-21 
Broken Bow Lake, Okla. (SWT) 19-14, 19-21, 19-26 
Bromley, Ky. (ORL) 24-23, 24-26 
Bronx River, N.Y. (NAN) 2-36 
Brookfield Lake, Mo. (MRK) 20-19 
Brooklyn, W. Va. (ORH) 25-20 
Brookport, Ill. (ORL) 42-21, 24-25, 24-30 
Brookville, Pa. (ORP) 26-23, 26-29 
Brookville Lake, Ind. (ORL) 24-5, 24-15, 24-28 
Broward County, Fla., Beach Erosion Control and 
Hillsboro Inlet, Fla., Navigation Project (SAJ) 9-19, 
9-32, 9-43, 9-49 
Brown, Clarence J., Dam and Reservoir, Ohio (ORL) 
42-8, 24-16 
Browns Creek, N.Y. (NAN) 2-35 
Brownstown, Ind. (ORL) 24-31 
Brownwood Channel Improvement, Tex. (SWF) 16-23 
Brunswick County Beaches, N.C. (Cape Fear to North 
Carolina-South Carolina State Line) (SAW) 6-28 
Brunswick Harbor, Ga. (SAS) 8-3, 8-11, 8-13 
Brush Bayou, La. (LMN) 11-23 
Buchanan Dam-H.V. Eastman Lake, Calif. (SPK) 35-4, 
35-18 
Buck Creek, N.C. and S.C. (SAN) 7-8, 7-16 
Buckhannon, W. Va. (ORP) 26-23, 26-24, 26-29 
Buckhannon River, W. Va. (ORP) 26-22 
Buckhorn Lake, Ky. (ORL) 42-6, 24-15- 24-28 
Bucks Harbor, Machiasport, Maine (NED) 1-50 
Bucksport Harbor, Maine (NED) 1-50 
Buena Vista, Ohio (ORH) 25-20 
Buena Vista, Va. (NAO) 5-26 
Buffalo, Wyo. (MRO) 21-16 
Buffalo Bayou and Tributaries, Tex. (SWG) 15-9, 
15-14, 15-25 
Buffalo Creek, Meadow Grove, Nebr. (MRO) 21-16, 
21-21 
Buffalo Creek, Scranton, N. Dak. (MRO) 21-16, 21-20 
Buffalo Harbor, N.Y. (NCB) 32-3, 32-17, 32-22 
Buffalo River, Miss. (LMK) 12-25 
Buffumville Lake, Mass. (NED) 1-28, 1-39, 1-64 
Buford Dam, Ga. (SAM) 10-19 
Bull Run, Pal (NAB) 4-13, 4-26, 4-34 
Bull Shoals Lake, Ark. (SWL) 18-7, 18-11, 18-23 
Bullocks Point Cove, R.I. (NED) 1-50 
Bunker Harbor, Maine (NED) 1-50 
Brubank-Eastern System, Calif. (SPL) 33-25 
Burbank-Western System (Lower) Calif. (SPL) 33-25 
Burbank-Western System (Upper) Calif. (SPL) 33-25 
Burch Creek, Weber County, Utah (SPK) 35-24 
Burgettstown, Pa. (ORP) 26-23 
Burgettstown-Slovan, Pa. (ORP) 26-29 
Burial Hill Beach, Westport, Conn. (NED) 1-54 
Burketts Creek, Amory, Miss. (SAM) 10-13, 10-25, 
10-35 
Burlington, Iowa (NCR) 28-4, 28-10, 28-13 
Burlington, Ohio (ORH) 25-19 
Burlington Dam, N. Dak. (NCS) 27-4, 27-19 
Burlington Harbor, Vt. (NAN) 2-31 
Burns Waterway Harbor, Ind. (NCD) 30-2, 30-9, 30-14, 
30-16 
Burnsville Lake, W. Va. (ORH) 25-3, 25-11, 25-15 
Bush, Alvin R., Dam, Pa. (NAB) 4-20, 4-29 
Butler, Pa. (ORP) 26-23, 26-29 
Buttermilk Channel, N.Y. (NAN) 2-31 
Byram River at Pemberwick, Conn. (NAN) 2-33 
C 
Cache Basin, Ark. (MR+T) 42-10, 42-19, 42-28, 42-53 
Cache Creek Basin, Calif. (SPK) 35-15 
Cache La Poudre River, Ft. Collins, Colo. (MRO) 
21-21 
Cache River Diversion, Ill. (LMS) 14-14 
Caddo Lake, La. (LMN) (LMK) 11-23, 12-8, 12-14, 
12-17 
Cadet Bayou, Miss. (SAM) 10-6, 10-23, 10-30 
Cadle Creek, Md. (NAB) 4-39 
Caesar Creek Lake, Ohio (ORL) 24-6, 24-16, 24-28 
Cagles Mill Lake, Ind. (ORL) 24-6, 24-16, 24-28 
Cahaba River, Ala. (SAM) 10-38 
Cairo, W. Va. (ORH) 25-21 
Calabash Creek, N.C. (SAN) 7-17 
Calapooya River, Oreg. (NPP) 37-48 
Calaveras River and Little John Creek and 
Tributaries, including New Hogan Lake and 
Farmington Dam, Calif. (SPK) 35-4, 35-18 
Calcasieu River and Pass, La. (LMN) 11-6, 11-21, 
11-26 
Calcasieu River at Coon Island, La. (LMN) 11-34 
Calcasieu River at Devil's Elbow, La. (LMN) 11-34 
Calcasieu River Salt Water Barrier, La. (LMN) 11-34 
Caledonia, N.Y. (NCB) 32-34 
Calf Pasture Beach Park, Conn. (NED) 1-54 
Calico Creek, N.C. (SAW) 6-30 
California (Cincinnati) Ohio (ORL) 24-23, 24-27 
California Debris Commission (CDC) 44-1 
Calion, Ark. (LMK) 12-22 
Calumet Harbor and River, Ill. and Indiana (NCC) 
30-2, 30-9, 30-11, 30-14, 30-16 
Calumet River Bridges, Ill. (NCC) 30-15 
I-6

INDEX 
Camas Creek, Idaho (NPW) 39-19, 39-20 
Cambridge Harbor, Md. (NAB) 4-36 
Cambridgeport Lake, Vt. (NED) 1-57 
Camden Harbor, Maine (NED) 1-50 
Camelsback Dam, Ariz. (SPL) 33-32 
Camp Ground Lake, Ky. (ORL) 24-7, 24-16 
Camp Perry, Ohio (NCB) 32-34 
Camp Wooten, Wash. (NPW) 39-21 
Campbells Island, Ill. (NCR) 28-18 
Campti-Clarence Area in Natchitoches Parish, La. 
(LMN) (LMK) 11-36, 12-25 
Canapitist Channel, Mass. (NED) 1-50 
Canaveral Harbor, Fla. (SAJ) 9-3, 9-29, 9-35, 9-46 
Candy Lake, Okla. (SWT) 19-6, 19-18, 19-22 
Cane River, La. (LMN) 11-34 
Caney Fork River, Tenn. (ORN) 23-13 
Canisteo, N.Y. (NAB) 4-16, 4-27 
Cannelton, Ind. (ORL) 24-21, 24-25, 24-30 
Cannelton Locks and Dam, Ind. (ORL) 22-3, 22-9 
Cannon, Clarence, Dam and Reservoir, Mo. (LMS) 
14-7, 14-10, 14-12 
Canton, Mass. (NED) 1-55 
Canton, Mo. (NCR) 28-16, 28-18 
Canton Lake, Okla. (SWL) (SWT) 18-21, 19-6, 19-18, 
19-25 
Canton (Nimishillen), Ohio (ORH) 25-21 
Canyon Lake, Tex. (SWF) 16-4, 16-16, 16-20 
Cape Charles City Harbor, Va. (NAO) 5-3, 5-15, 5-19 
Cape Cod Canal, Mass. (NED) 1-4, 1-32, 1-42 
Cape Fear River, N.C., above Wilmington (SAW) 6-4, 
6-19 
Cape Fear River Basin, N.C. (SAW) 6-11, 6-31 
Cape Florida State Park, Fla. (SAJ) 9-51 
Cape Girardeau, Mo., No. 2 (LMS) 14-14 
Cape Girardeau, Mo., Reaches Nos. 1, 3, 4 (LMS) 14-14 
Cape Henry Channel, Va. (NAO) 5-2, 5-19 
Cape Lookout, N.C. (SAW) 6-29 
Cape May City, N.J. (NAP) 3-26 
Cape May Inlet to Lower Township, N.J. (NAP) 3-12, 
3-19 
Cape Porpoise Harbor, Maine (NED) 1-50 
Cape Vincent Harbor, N.Y. (NCB) 32-3, 32-17, 32-23 
Captain Anthony Meldahl Locks and Dam, Ky. (ORD) 
22-1, 22-8 
Carden's Bottom Drainage District No. 2, Arkansas 
River, Ark. (SWL) 18-16 
Carl L. Estes Dam and Lake, Tex. (SWF) 16-23 
Carlyle Lake, Ill. (LMS) 14-14 
Carolina Beach and Vicinity, N.C. (SAW) 6-12, 6-21 
Carr Fork Lake, Ky. (ORL) 24-7, 24-16, 24-28 
Carrabelle Bar and Harbor, Fla. (SAM) 10-38 
Carrabelle Harbor, Fla. (SAM) 10-37 
Carroll County Levee and Drainage District, Ill. 
(NCR) 28-18 
Carrollton, Ky. (ORL) 24-23, 24-26 
Carters Creek, Va. (NAO) 5-24 
Carters Lake, Ga. (SAM) 10-16, 10-26 
Carthage Levee, Mo. (SWT) 19-27 
Caruthersville Harbor, Mo. (LMM) 13-1, 13-6, 13-8 
Carvers Harbor, Vinalhaven, Maine (NED) 1-50 
Cascadia Lake, Oreg. (NPP) 37-46, 37-53 
Caseville Harbor, Mich. (NCE) 31-74, 31-75 
Caseyville, Ky. (ORL) 24-22, 24-25 
Cashie River, N.C. (SAW) 6-26 
Cassville Harbor, Wis. (NCD) 29-8 
Castle Rock, Wash. (NPP) 37-46 
Castlewood Lake, Colo. (MRO) 21-16 
Catching Inlet Drainage District, Oreg. (NPP) 37-46 
Cathance River, Maine (NED) 1-50 
Catherine Creek Lake, Oreg. (NPWZ) 39-17 
Cathlamet, Wash. (NPP) 37-43 
Catlettsburg, Ky. (ORH) 25-19, 25-21 
Cattaraugus Creek, N.Y. (NCB) 32-32 
Cattaraugus Harbor, N.Y. (NCB) 32-4, 32-17 
Cave Run Lake, Ky. (ORL) 24-7, 24-16, 24-28 
Cave-In-Rock, Ill. (ORL) 24-23, 24-26 
Cayuga Creek, Cheektowaga, N.Y. (NCB), 32-13, 32-19 
Cecil M. Harden Lake, Ind. (ORL) 24-8, 24-16, 24-28 
Cedar Bayou, Tex. (SWG) 15-9, 15-27 
Cedar Canyon Dam, S. Dak. (MRO) 21-16, 21-20 
Cedary Creek, Del. (NAP) 3-16, 3-24 
Cedar Keys Harbor, Fla. (SAJ) 9-49, 9-50 
Cedar Point, Ga. (SAS) 8-16 
Cedar Point Lake, Kans. (SWT) 19-24 
Cedar River, Wash. (NPS) 38-25 
Cedar River Harbor, Mich. (NCE) 31-75 
Cedar Lock and Dam, Wis. (NCE) 31-73 
Celina Dam, Ky. (ORN) 23-14 
Center Hill Lake, Ohio River Basin, Tenn. (ORN) 23-6, 
23-9, 23-18 
Central and Southern Florida (SAJ) 9-24, 9-33, 9-44, 
9-51, 9-52, 9-53, 9-54 
Central City Lake, Iowa (NCR) 28-18 
Ceredo-Kenova, W. Va. (ORH) 25-19, 25-21 
Chambersburg, Ohio (ORH) 25-20 
Channel between North and South Hero Island, Lake 
Champlain, Vt. (NAN) 2-31 
Channel Clearing and Snagging on Willamette River 
and Major Tributaries, (NPP) 37-53 
Channel Connecting Plain Dealing Creek and Oak 
Creek, Md. (NAB) 4-39 
Channel Connecting Thoroughfare Bay with Cedar 
Bay, N.C. (SAW) 6-26 
Channel Connecting York River, Va. with Back Creek 
to Slaights Wharf (NAO) 5-24 
Channel from Back Sound to Lookout Bight, N.C. 
(SAW) 6-5, 6-19 
Channel from Naples to Big Marco Pass, Fla. (SAJ) 
9-3, 9-29, 9-35, 9-49 
Channel from Pamlico Sound to Rodanthe, N.C. (SAW) 
6-26 
Channel from Phoebus, Va. to Deep Water in 
Hampton Roads (NAO) 5-24 
Channel Improvements for Flood Control and Major 
Drainage on 16 Streams Tributary to Willamette 
River (NPP) 37-53 
Channel Islands Harbor, Calif. (SPL) 33-2, 33-12, 33-16 
Channel to Liberty, Tex. (SWG) 15-8 
Channel to Newport News, Va. (NAO) 5-24 
Channel to Port Bolivar, Tex. (SWG) 15-2, 15-13, 
15-16, 15-28, 15-34 
Channels, Strait of Mackinac, Mich. (NCE) 31-3, 31-37, 
I-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
31-54 
Chaplin River, Perryville, Ky. (ORL) 24-21 
Chappaqua, N.Y. (NAN) 2-36 
Charenton Drainage and Navigation Canal (MR�T) 
42-50 
Chariton River, Mo. (1944 Act) (MRK) 20-19 
Chariton-Little Chariton Basin Mo. (1965 Act) (MRK) 
20-19 
Charles River (Natural Valley Storage Areas), Mass. 
(NED) 1-15, 1-36, 1-47 
Charles River Dam, Mass. (NED) 1-27, 1-55 
Charleston Channel, Oreg. (NPP) 37-2, 37-26, 37-33 
Charleston Harbor, S.C. (SAN) 7-2, 7-9, 7-11, 7-17 
Charlestown, N.H. (NED) 1-29, 1-55, 1-61 
Charlevoix Harbor, Mich. (NCE) 31-4, 31-37, 31-54 
Charlotte Harbor, Fla. (SAJ) 9-4, 9-29, 9-35, 9-49 
Chartiers Creek, Pa. (ORP) 26-3, 26-14, 26-29 
Chaska, Minn. (NCS) 27-5, 27-19 
Chatfield Lake, Colo. (MRO) 21-2, 21-10, 21-12 
Chatham (Stage) Harbor, Mass. (NED) 1-5, 1-32, 1-43 
Chattanooga, Tenn. and Rossville, Ga. (ORN) 23-13 
Chattooga Dam and Lakes, Ga. and S.C. (SAS) 8-17 
Cheat River, W. Va. (ORP) 26-22 
Cheatham Lock and Dam, Tenn. (ORN) 23-14 
Cheboyan Harbor, Mich. (NCE) 31-4, 31-38, 31-54 
Cheesequake Creek, N.J. (NAN) 2-35 
Chefuncte River and Bogue Falia, La. (LMN) 11-34 
Chehalis River, Wash. (NPS) 38-25 
Chelsea Street Highway Bridge, Mass. (NED) 1-13 
Chena River Lakes, Alaska (NPA) 40-6, 40-9, 40-12 
Cheney Reservoir, Kans. (SWT) 19-13 
Cherry and Red Fork Creeks Channel Improvement, 
Okla, (SWT) 19-24, 19-27 
Cherry Creek Lake, Colo. (MRO) 21-3, 21-10, 21-12 
Cherryfield, Maine (NED) 1-29, 1-55 
Chesapeake, Ohio (ORH) 25-19 
Chesconessex Creek, Va. (NAO) 5-24 
Cheshire, Ohio (ORH) 25-20 
Chester, Calif. (SPK) 35-24 
Chester River, Md. (NAB) 4-4, 4-24, 4-31 
Chester River, Pa. (NAP) 3-24 
Chester River at Chester, Pa. (NAP) 3-15 
Chetco River, Oreg. (NPP) 37-2, 37-25, 37-26, 37-33 
Chewaucan River, Oreg. (NPP) 37-46 
Chicago Harbor, Ill. (NCC) 30-3, 30-9, 30-11, 30-14, 
30-16 
Chicago River, Ill. (NCC) 30-3, 30-9, 30-12, 30-14, 
30-16 
Chicago River, ill (North Branch) (NCC) 30-6, 30-10 
Chickamauga Lock and Dam, Tenn. (ORN) 23-17 
Chicopee, Mass. (NED) 1-29, 1-55, 1-57, 1-61 
Chicopee Falls, Mass. (NED) 1-55, 1-51 
Chief Joseph Dam-Rufus Woods Lake, Wash. (NPS) 
38-10, 38-16, 38-22 
Chillicothe, Ohio (ORH) 25-3, 25-11, 25-15 
Chilo, Ohio (ORH) 25-20 
Chincoteague Bay, Va. (NAO) 5-4, 5-15 
Chincoteague Harbor of Refuge, Va. (NAO) 5-24 
Chincoteague Inlet, Va. (NAO) 5-5, 5-15, 5-20 
Chino Canyon Improvements, Palm Springs, Calif. 
(SPL) 33-24 
Chippewa Harbor, Mich. (NCE) 31-74 
Chippewa Harbor, Isle Royale, Mich. (NCE) 31-75 
Chittenango Creek and Tributaries, N.Y. (NCB) 32-34 
Choctaw Bayou and Tributaries, La. (LMN) 11-36 
Choctawhatchee Bay to Pensacola Bay, Fla. (SAM) 
10-31 
Choctawhatchee River, Fla. and Ala. (SAM) 10-38 
Choptank River, Md. (NAB) 4-36 
Chouteau Lock and Dam, Okla. (SWL) (SWT) 18-19, 
19-25 
Chouteau, Nameoki, and Venice Drainage and Levee 
District, Ill. (LMS) 14-14 
Chowan River, N.C. (NAO) 5-24 
Chowan River, N.C. (SAW) 6-26 
Christiansted Harbor, V.I. (SAJ) 9-50 
Cibolo Creek, Tex. (SWA) 17-2, 17-9, 17-11 
Cincinnati, Ohio (ORL) 24-21, 24-23, 24-25, 24-26, 
24-30 
Cincinnatus, N.Y. (NAB) 4-41 
City Creek Levee, Calif. (SPL) 33-23 
City of Aurora, Colo. (MRO) 21-16 
Clackamas River at Dixon Farm Location, Oreg. 
(NPP) 37-46 
Claiborne County Port, Miss. (LMK) 12-2, 12-13, 12-16 
Claiborne Harbor, Md. (NAB) 4-36, 4-40 
Claiborne Lock and Dam, Ala. (SAM) 10-16, 10-26 
Clallam Bay, Wash. (NPS) 38-25 
Clallam River, Wash. (M(NPS) 38-25 
Clanton, Ala. (SAM) 10-39 
Claremont Lake, N.H. (NED) 1-57 
Clarence Cannon Dam and Reservoir, Mo. (LMS) 14-7, 
14-10, 14-12 
Clarence J. Brown Dam and Reservoir, Ohio (ORL) 
24-8, 24-16 
Clarendon to Laconia Circle, Ark. (LMM) 13-10 
Clarington, Ohio (ORP) 26-24 
Clark Fork River, Mont. (NPS) 38-8, 38-15, 38-21, 
38-25 
Clark Point Beach, New Bedford, Mass. (NED) 1-54 
Clarks Hill Lake, Ga. and S.C. (SAS) 8-8, 8-11, 8-15, 
8-17 
Clarkson, Nebr. (MRO) 21-16, 21-21 
Clarksville, Ark. (SWL) 18-16 
Clatskanie Drainage District 1, Oreg. (NPP) 3748, 
37-52 
Clatskanie River, Oreg. (NPP) 37-43 
Clatskanie River Area, Oreg. (NPP) 37-48, 37-52 
Clatsop County Diking District 3, Oreg. (NPP) 37-48 
Clatsop County Diking District 4, Oreg. (NPP) 37-48, 
37-52 
Clatsop County Diking District 6, Oreg. (NPP) 37-48, 
37-52 
Clatsop County Diking District 1, Oreg. (NPP) 37-48, 
37-52 
Clear Creek, Tex. (SWG) 15-12 
Clear Creek and Clear Lake, Tex. (SWG) 15-27 
Clear Creek Drainage and Levee District, Ill. (LMS) 
14-14 
Clear Creek, Franklin, Ohio (ORL) 24-21 
Clearwater Lake, Mo. (SWL) 18-5, 18-11, 18-23 
Clearwater Pass, Fla. (SAJ) 9-4, 9-29, 9-35, 9-49, 9-50 
I-8

INDEX 
Clearwater River, Minn. (NCS) 27-28 
Clearwater River, Wash. (NPS) 38-25 
Cleveland and Lakewood, Ohio (NCB) 32-34 
Cleveland Harbor, Ohio (NCB) 32-4, 32-17, 32-23 
Cleves, Ohio (ORL) 24-23, 24-26 
Cliff Walk, Newport, R.I. (NED) 1-13, 1-35, 1-47 
Clifton, W. Va. (ORH) 25-20 
Clifty Creek Lake, Ind. (ORL) 24-23 
Clinch River, Tenn., and Va. (ORN) 23-13 
Clinton, Ind. (ORL) 24-23, 24-26 
Clinton, Iowa (NCR) 28-16, 28-18 
Clinton Harbor, Conn. (NED) 1-5, 1-32, 1-43 
Clinton Harbor, Iowa (NCD) 29-8 
Clinton Lake, Kans. (MRK) 20-3, 20-11, 20-15 
Clinton River, Mich. (NCE) 31-5, 31-38, 31-54 
Cloverport, Ky. (ORL) 24-22, 24-25, 24-31 
Clyde, R.I. (NED) 1-57 
Clyde Park, Mont. (MRO) 21-20 
Coal Creek and Tributaries (Lake City), Tenn. (ORN) 
23-13 
Coal Creek Drainage and Levee District, Ill. (NCR) 
28-16, 28-18 
Coal Grove, Ohio (ORH) 25-19 
Coal River, W. Va. (NAB) 25-19 
Coan River, Va. (NAB) 4-39 
Coast of California, Point Mugu to San Pedro 
Breakwater, Calif. (SPL) 33-22 
Coastal Engineering Research Center (CERC) 45-1 
Coaster Island Harbor, R.I. (NED) 1-50 
Cobscook Bay, Maine (NED) 1-50 
Cocheco River, N.H. (NED) 1-50, 1-55 
Cochiti Lake, N. Mex. (SWA) 17-4, 17-10, 17-12 
Cochrane, Wis. (NCS) 27-28 
Cockrells Creek, Va. (NAO) 5-25 
Coeur D'Alene, Idaho (NPS) 38-8, 38-25 
Cohansey River, N.J. (NAP) 3-3, 3-16, 3-17, 3-21 
Cohasset Harbor, Mass. (NED) 1-50 
Coschester, Vt. (NAN) 2-37 
Cold Regions Research Engineering Laboratory 
(CRREL) 52-1 
Cold Spring Inlet, N.J. (NAP) 3-3, 3-17, 3-21 
Colebrook River Lake, Conn. (NED) 1-16, 1-36, 1-60 
Colfax, Wash. (NPW) 39-17, 39-21 
Colfax, Grant Parish, La. (LMN) (LMK) 11-36, 12-25 
Colliers, W. Va. (ORP) 26-29 
Colonial Beach, Va. (NAB) 4-12, 4-26, 4-34 
Colorado River, Matagorda, Tex. (SWG) 15-27 
Colorado Springs, Colo. (Templeton Gap Floodway) 
(SWA) 17-12 
Colombia, La. (LMK) 12-22 
Columbia and Lower Willamette Rivers below 
Vancouver, Wash., and Portland, Oreg. (NPP) 37-3, 
37-26, 37-33, 37-49 
Columbia Drainage and Levee District No. 3, Ill. 
(LMS) 14-14 
Columbia Drainage District 1, Oreg. (NPP) 37-45, 
37-52 
Columbia River and Tributaries above Celilo Falls to 
Kennewick, Wash. (NPW) 39-17 
Columbia River at Baker Bay, Wash. (NPP) 37-4, 
37-26, 37-34 
Columbia River at the Mouth, Oreg. and Wash. (NPP) 
37-4, 37-26, 37-33 
Columbia River Basin, Local Flood Protection Projects 
(NPW) 39-2, 39-14, 39-20 
Columbia River Basin, Local Flood Protection Projects 
Idaho, Mont., and Wash. (NPS) 38-25, 38-30 
Columbia River between Chinook, Wash., and Head of 
Sand Island (NPP) 37-4, 37-26, 37-34 
Columbia River between Vancouver, Wash., and The 
Dalles, Oreg. (NPP) 37-5, 37-26, 37-35 
Columbia River Treaty Permanent Engineering Board 
49-2 
Columbia River, Wenatchee to Kettle Falls, Wash. 
(NPS) 38-24 
Columbia Slough, Oreg. (NPP) 3748 
Columbus, Nebr. (MRO) 21-21 
Columbus, Ohio (ORH) 25-20 
Comps Beach, Westport, Conn. 1-54 
Computer Sciences Laboratory 51-1 
Conant Brook Dam, Mass (NED) 1-17, 1-36, 1-60 
Conchas Lake, N. Mex. (SWA) 17-2, 17-9 
Concordia, Ky. (ORL) 24-22, 24-25 
Conemaugh River Lake, Pa. (ORP) 26-6, 26-15, 26-19 
Conetoe Creek, N.C. (SAW) 6-28 
Coney Island Creek, N.Y. (NAN) 2-35 
Coney Island Inlet, N.Y. (NAN) 2-31 
Congaree River, Cayce, S.C. (SAN) 7-15 
Conklin-Kirkwood, N.Y. (NAB) 4-38, 441 
Conneaut Harbor, Ohio (NCB) 32-5, 32-17, 32-24 
Connecticut River (above Hartford), Conn. (NED) 1-50 
Connecticut River Basin, Vt., N.H., Mass., and Conn. 
(NED) 1-15, 1-29, 1-60 
Connecticut River below Hartford, Conn. (NED) 1-5, 
1-33, 1-43, 1-57 
Connecticut River, North Stratford, N.H. (NED) 1-55 
Connecticut River, W. Stewardstown, N.H. (NED) 1-55 
Connell, Wash. (NPW) 39-17 
Concho Creek, N.C. (SAW) 6-29 
Construction Engineering Research Laboratory 
(CERL) 50-1 
Construction of Locks and Dams, Ohio River (ORD) 
22-1, 22-5, 22-6 
Contentnea Creek, N.C. (SAW) 6-26, 6-28, 6-29 
Conway County Drainage & Levee District No. 1, 
Arkansas River, Ark. (SWL) 18-16 
Conway County Levee District No. 6, Arkansas River, 
Ark. (SWL) 18-16 
Conway County Levee District Nos. 1, 2, & 8, Arkansas 
River, Ark. (SWL) 18-16 
Cook Inlet Shoals, Alaska (NPA) 40-12 
Cooper Lake and Channels, Tex. (LMN) 11-36 
Cooper Lake and Channels, Tex. (SWF) 16-5, 16-16, 
16-20 
Cooper River, Charleston Harbor, S.C. (SAN) 7-3, 7-9, 
7-12 
Cooper River, N.J. (NAP) 3-24 
Cooper River Seismic Modification, S.C. (SAN) 7-4, 7-9, 
7-12 
Cooper's Ditch, Va. (NAO) 5-14 
Coordinating Committee on Great Lakes Basic 
Hydraulic and Hydrologic Data Board 49-2 
I-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Coos and Millicoma Rivers, Oreg. (NPP) 37-6, 37-27, 
37-35 
Coos Bay, Oreg. (MPP) 37-5, 37-26, 37-35 
Coosa River Navigation, Ala. (SAM) 10-17, 10-26 
Copan Lake, Okla. (SWT) 19-7, 19-18, 19-22 
Copes Corner Lake, New York (NAB) 4-39 
Coquille River, Oreg. (NPP) 37-6, 37-27, 37-35, 37-48 
Coralville Lake, Iowa (NCR) 28-4, 28-10, 28-14 
Corapolis, Pa. (ORP) 26-24 
Corbin, Ky. (ORN) 23-19 
Corbin (Lynn Camp Creek), Ky. (ORN) 23-13 
Cordell Hull Lock and Dam, Tenn. (ORN) 23-14 
Cordova Harbor, Alaska (NPA) 40-12 
Cordova Small Boat Harbor, Alaska (NPA) 40-2, 40-8, 
40-10 
Core Creek, N.C. (SAW) 6-28 
Corea Harbor, Maine (NED) 1-6, 1-33, 1-43 
Corining, N.Y. (NAB) 4-16, 4-28 
Cornucopia Harbor, Wis. (NCE) 31-74, 31-75 
Corpus Christi, Tex., Channel to Navy Seaplane Base, 
Encinal Peninsula (SWG) 15-27 
Corpus Christi Beach, Tex. (Restoration Project) 
(SWG) 15-9, 15-14, 15-25 
Corpus Christi Ship Channel, Tex. (SWG) 15-2, 15-13, 
15-16, 15-28, 15-29, 15-34 
Corsica River, Md. (NAB) 4-36, 4-40 
Corte Madera Creek, Calif. (SPK) (SPN) 34-5, 35-18, 
35-22 
Cortland, N.Y. (NAB) 4-38, 4-41 
Cottage Grove Lake, Oreg. (NPP) 37-13, 37-29, 37-39, 
37-51, 37-53 
Cottonwood Creek, Calif. (SPK) 35-16, 35-21 
Cottonwood Creek Community Church, Idaho (NPW) 
39-2, 39-11, 39-14 
Cottonwood Creek Dam, Bosie, Idaho (NPW) 39-17 
Cottonwood Slough Pumping Plant, Ill. (LMN) 13-10 
Cotuit Harbor, Mass. (NED) 1-50, 1-57 
Cougar Lake, Oreg. (NPP) 37-20, 37-30, 37-41, 37-51, 
37-53 
Council Bluffs, Iowa (MRO) 21-16, 21-21 
Council Gove Lake, Kans. (SWT) 19-7, 19-18 
Courtenay Channel, Fla. (SAJ) 9-50 
Cove Island, Stamford, Conn. (NED) 1-54 
Covington, Ky. (ORL) 24-21, 24-25, 24-30 
Cow Castle Creek, S.C. (SAN) 7-7, 7-10, 7-14 
Cow Creek Channel Improvement, Kans. (SWT) 19-24 
Cowanesque Lake, Pa. (NAB) 4-19, 4-28 
Cowlitz County Consolidated Diking Improvement 
District 1, Wash. (NPP) 37-44, 37-48, 37-52 
Cowlitz County Diking Improvement Districts 2, 13, 
and 15, Wash. (NPP) 37-45, 37-52 
Cowlitz County Drainage Improvement District 1, 
Wash. (NPP) 37-45 
Cowlitz River, Wash. (NPP) 37-15, 37-43, 37-45 
Cowlitz River at Randle, Wash. (NPP) 3748 
Cowlitz River Basin, Wash. (NPP) 37-15 
Cowpen Swamp, S.C. (SAN) 7-8, 7-16 
Coyote and Spencer Creeks, Oreg. (NPP) 37-48 
Coyote Creek, Calif. (SPK) 35-24 
Coyote Valley Dam (Lake Medocino) and Channel 
Improvements, Calif. (SPN) 34-8, 34-11, 34-12 
Crabtree Swamp, S.C (SAN) 7-8, 7-16 
Craig Harbor, Alaska (NPA) 40-12 
Craig Small Boat Harbor, Alaska (NPA) 40-2, 40-8, 
40-10 
Cramerton, S. Fork, S.C. (SAN) 7-15 
Crane Creek Drainage and Levee District (NCR) 
28-16, 28-18 
Crane Creek State Park, Ohio (NCB) 32-36 
Cranes Creek, Va. (NAO) 5-25 
Crawford County Levee District, Arkansas River, Ark. 
(SWL) 18-16 
Creede, Willow Creek, Colo. (Floodway) (SWA) 17-12 
Crescent City Harbor, Calif. (SPN) 34-1, 34-6, 34-9 
Criehaven Harbor, Maine (NED) 1-50 
Crisfield Harbor, Md. (NAB) 4-36 
Crooked Creek Lake, Pa., (ORP) 26-6, 26-15, 26-19 
Crooked Creek Lake & Levee, Ark. (SWL) 18-16 
Cross Creek, Rossville, Kan. (MRK) 20-9 
Cross-Florida Barge Canal (SAJ) 9-5, 9-29, 9-35, 9-47 
Cross Rip Sholas Nantucket Sound, Mass. (NED) 1-50 
Cross Village Harbor, Mich. (NCE) 31-5, 31-38, 31-54 
Crutcho Creek Channel Improvement, Okla. (SWT) 
19-24 
Crystal River, Fla. (SAJ) 9-50 
Cucamonga Creek, Calif. (SPL) 33-5, 33-13, 33-18 
Cuckold Creek, Md. (NAB) 4-39 
Cuivre River, Mo. (LMS) 14-13 
Culesac, Idaho 39-21 
Cumberland, Ky. (ORN) 23-9, 23-18 
Cumberland, Md., and Ridgeley, W. Va. (NAB) 4-13, 
4-26, 4-34, 4-41 
Cumberland River, Tenn. and Ky. (ORN) 23-2, 23-9, 
23-11, 23-15 
Cummings Park, Stamford, Conn. (NED) 1-54 
Cuninghill Cove, Md. (NAB) 4-39 
Current River, Ark. & Mo. (SWL) 18-15 
Curry Creek Dan and Lake, Ga. (SAS) 8-16 
Curwensville Lake, Pa. (NAB) 4-20, 4-29 
Cushman-Mapleton Channels, Oreg. (NPP) 37-43 
Cuttyhunk Harbor, Mass. (NED) 1-50 
Cuyahoga River Basin, Ohio (NCB) 32-13, 32-20 
Cypress Bayou and Waterway between Jefferson, Tex., 
and Shreveport, La. (LMN) (LMK) 11-34, 12-21 
Cypress Creek, Ky. (ORL) 24-31 
Cypress Creek, Md. (NAB) 4-36 
D 
Dade County, Fla. (SAJ) 9-20, 9-32, 9-43 
Dale Hollow Lake, Ohio River Basin, Tenn. and Ky. 
(ORN) 23-7, 23-9, 23-18 
Dallas Floodway, Tex. (SWF) 16-14, 16-20 
Dam "A" Lake, Tex. (SWF) 16-14, 16-20 
Dam Safety Program, New York District (NAN) 2-19 
Damariscotta River, Maine (NED) 1-50 
Dana Point Harbor, Calif. (SPL) 33-21 
Dansbury, Conn. (NED) 1-26, 1-55, 1-62 
1-10

INDEX 
Dancing Swan Channel, Va. (NAO) 5-27 
Dansville and Vicinity, N.Y. (NCB) 32-13, 32-20 
Dardanelle Lock & Dam, ARK. (SWL) 18-7, 18-12, 
18-19 
Darien Harbor, Ga. (SAS) 8-16 
Dashields Locks and Dam, Pa. (ORD) 22-1, 22-7 
Data Collection and Management Division, 53-1 
Dauphin Island Bay, Ala. (SAM) 10-6, 10-24, 10-30 
Davenport, Iowa (NCR) 28-4, 28-10, 28-14 
Davenport Center Lake, N.Y. (NAB) 4-39 
Davenport Harbor, Iowa (Lindsey Park) (NCD) 29-8 
David D. Terry Lock & Dam, Ark. (SW:) 18-2, 18-18 
Davids Creek Lake, Iowa (MRO) 21-16 
Davis, N.C. (SAW) 6-29 
Davis Creek, Va. (NAO) 5-25 
Day, John, Lock and Dam-Lake Umatilla, Oreg. and 
Wash. (NPP) 37-22, 37-31 
Dayton, Ky. (ORL) 24-3, 24-15, 24-25, 24-30 
Dayton, Wash. (NPW) 39-17, 39-21 
Dayton, Wyo. (MRO) 21-17 
De Kalb, Ill. (NCR) 28-18 
Decorah, Iowa (NCS) 27-28 
Deep Creek, N.C. (SAW) 6-12, 6-21 
Deep Creek, Va. (NAO) 5-25 
Deep Creek, Newport News, Va. (NAO) 5-24 
Deep Fork Channel Improvement, Okla. (SWT) 19-27 
Deep River Area, Wash. (NPP) 37-44 
Deer Creek Lake, Ohio (ORH) 25-3, 25-11, 25-15 
Deer Creek Prairie Levee, Ind. (ORL) 24-23, 24-26 
Deer Island Area, Oreg. (NPP) 37-44 
Deer Island Drainage District, Oreg. (NPP) 37-45, 
37-72 
Deer Island Thoroughfare, Maine (NED) 1-50 
Degonia and Fountain Bluff Levee and Drainage 
District, Ill. (LMS) 14-14 
Degray Lake, Ark. (LMK) 12-8, 12-14, 12-22 
Dekalb, Ill. (NCR) 28-18 
Delaware River, N.Y., N.J., and Pa., at or near Mouth 
of Neversink River (NAP) 3-27 
Delaware River, Pa., N.J. and Del., Philadelphia to 
the Sea (NAP) 3-4, 3-17, 3-22 
Delaware River at Camden, N.J. (NAP) 3-24 
Delaware River at East Branch, N.Y. (NAP) 3-14 
Delaware River at Pennsville, N.J. (NAP) 3-24 
Delaware River between Philadelphia, Pa., and 
Trenton, N.J. (NAP) 3-3, 3-17, 3-21 
Delphi, Ind. (ORL) 24-21, 24-25, 24-30 
Denison Dam-Lake Texoma, Tex. and Okla. (SWT) 
19-14, 19-21 
Dennis Creek, N.J. (NAP) 3-24 
Depere Lock and Dam, Wis. (NCE) 31-73 
Depoe Bay, Oreg. (NPP) 37-7, 37-27, 37-36, 37-43, 
37-46 
Depue, Ill. (NCR) 28-4, 28-10, 28-14 
Dequeen Lake, Ark. (SWL) 18-5, 18-11, 18-22 
Derby, Conn. (NED) 1-29, 1-55, 1-62 
Derby, Ind. (ORL) 24-23, 24-26 
Des Moines, Iowa (NCR) 28-16, 28-18 
Des Moines and Mississippi Levee District No. 1, Mo. 
(NCR) 28-16, 28-18 
Deschutes River, Wash. (NPS) 3825 
Detour Harbor, Mich. (NCE) 31-6, 31-38, 31-54 
Detroit Lake, Oreg. (NPP) 37-21, 37-31, 37-41, 37-51, 
37-53 
Detroit River, Mich. (NCE) 31-6, 31-38, 31-54, 31-71, 
31-77 
Devils Lake, N. Dak. (NCS) 27-5, 27-19 
Devil's Swamp, La. (MR�T) 42-6, 42-27 
Dewey Lake, Ky. (ORH) 25-4, 25-12, 25-15 
Dickey-Lincoln School Lakes, Maine (NED) 1-26, 1-39, 
1-49, 1-57 
Dickinson Bayou, Tex. (SWG) 15-27 
Dicks Creek, Amanda Station, Ohio (ORL) 24-21 
Dierks Lake, Little River Basin, Ark. (SWL) 18-5, 
18-11, 18-22 
Diking and Improvement District 4, Wahkiakum 
County, Wash. (NPP) 37-44 
Diking and Improvement District 5, Cowlitz County, 
Wash. (NPP) 37-44 
Diking and Improvement District 11, Cowlitz County, 
Wash. (NPP) 37-45 
Diking Districts 1 and 3 (Puget Island) and Little 
Island, Wash. (NPP) 37-44 
Diking Districts 2, 3, and 5, Clatsop County, Oreg. 
(NPP) 37-44 
Diking Improvement District 1, Pacific County, Wash. 
(NPP) 37-45 
Diking Improvement District 2 and 13, Cowlitz County 
(NPP) 37-45 
Dillingham Harbor, Alaska (NPA) 40-3, 40-8, 40-10 
Dillion Lake, Ohio (ORH) 52-4, 25-12, 25-15 
Dillionvale, Ohio (Short Creek) (ORP) 26-24 
Dismal Swamp Canal (Deep Creek), Va. (NAO) 5-24 
Dismal Swamp Canal, (South Mills, N.C.) (NAO) 5-24 
Dively Drainage & Levee District, Ill. (LMS) 14-14 
Dodge City, Kans. (SWA) 17-12 
Dodge City, Kans. (SWT) 19-27 
Dog and Fowl Rivers, Ala. (SAM) 10-6, 10-24, 10-30 
Doheny Beach State Park (Doheny State Beach), Calif. 
(SPL) 33-22 
Dorchester Bay and Neponset River, Mass. (NED) 1-50 
Dorena Lake, Oreg. (NPP) 37-13, 37-29, 37-39, 37-51, 
37-53 
Double Bayou, Tex. (SWG) 15-3, 15-9, 15-13, 15-18 
Double Creek, N.J. (NAP) 3-24 
Douglas Harbor, Alaska (NPA) 40-12 
Douglass Lake, Kans. (SWT) 19-24 
Dover, Ky. (ORH) 25-19 
Downeyville Lake, Ind. (ORL) 24-22, 24-29 
Drainage District 1, Clatsop County, Oreg. (NPP) 
37-44 
Dresden Island Lock and Dam, Ill. (NCC) 28-22 
Drinkwater Sewer, Mo. (LMM) 13-4, 13-6, 13-8 
Drum Inlet, N.C. (SAW) 6-26 
Drury Drainage District, Ill. (NCR) 28-16, 28-18 
Dry Creek, Wash. (NPW) 39-17 
Dry Creek, Hawarden, Iowa (MRO) 21-16, 21-21 
Dry Creek, Wash. (NPW) 39-17 
Dry Creek, Hawarden, Iowa (MRO) 21-16, 21-21 
Dry Creek, (Warm Springs) Lake and Channel 
Improvements, Calif. (SPN) 34-8, 34-11, 34-12 
Dry Fork and East Fork Lakes, Mo. (MRK) 20-19 
I-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Dry Pass, Alaska (NPA) 40-3, 40-8, 40-10 
Dry Run, Iowa (NCS) 27-24 
Dubois, Pa. (ORP) 26-23, 26-29 
Dubuque, Iowa (NCR) 28-16, 28-18 
Dubuque Harbor, Iowa (NCD) 29-8 
Duck Creek, Calif. (SPK) 35-24 
Duck Creek Channel Improvement, Tex. (SWF) 16-5, 
16-16, 16-20 
Duck Island Harbor, Conn. (NED) 1-50 
Duck Point Cove, Md. (NAB) 4-36 
Duck River, Tenn. (ORN) 23-13 
Duluth-Superior Harbor, Minn. and Wis. (NCE) 31-7, 
31-38, 31-56 
Dungeness River, Wash. (NPS) 38-8, 38-26 
Dunkirk Harbor, N.Y. (NCB) 32-5, 32-18, 32-25 
Dunn Branch, Woodbine, Camden County, Ga. (SAS) 
8-7, 8-16 
Duval County, Fla. (SAJ) 9-21, 9-32, 9-43 
Duxbury Harbor, Mass. (NED) 1-50 
Dworshak Dam and Reservoir, Idaho (NPW) 39-5, 
39-11, 39-15, 39-22 
Dyersburg, Tenn. (LMM) 13-10 
Dyersburg, Tenn. (Southwest) (LMM) 13-10 
Dymers Creek, Va. (NAO) 5.25 
E 
Eagle Bay and Fort Yates Highway Bridges, N. Dak. 
(MRO) 21-16 
Eagle Creek, S.C. (SAN) 7-7, 7-10, 7-14 
Eagle Creek Lake, Ky. (ORL) 24-22 
Eagle Creek Reservoir, Ohio (ORP) 26-23 
Eagle Harbor, Mich. (NCE) 31-7, 31-39, 31-56 
Eagle Barre Dam, Vt. (NAN) 2-33 
East Bay (Hanna Reef), Tex. (SWG) 15-27 
East Bay Marina, Olympia Harbor, Wash. (NPS)38-2, 
38-13, 38-18 
East Boothbay Harbor, Maine (NED) 1-50 
East Boyer River at Vail, Iowa (MRO) 21-3, 21-10, 
21-13 
East Branch, Clarion River Lake, Pa. (ORP) 26-6, 
26-15, 26-19 
East Branch Dam, Conn. (NED) 1-55, 1-61 
East Brimfield Lake, Mass. (NED) 1-28, 1-39, 1-64 
East Canada Creek, N.Y. (NAN) 2-36 
East Cape Girardeau and Clear Creek Drainage 
District, Ill. (LMS) 14-14 
East Chester Creek, N.Y. (NAN) 2-30, 2-31 
East Fork, Tex. (SWF)16-23 
East Hartford, Conn. (NED) 1-29, 1-55, 1-61 
East Liverpool Drainage and Levee District (NCR) 
28-16, 28-18 
East Lynn Lake, W. Va. (ORH) 25-4, 25-12, 25-15 
East Moline, Ill. (NCR) 28-4, 28-10, 28-14 
East Muddy and Lake Creek, Oregl (NPP) 37-48 
East Nishnabotna River, Near Griswold, Iowa (MRO) 
21-21 
East Nishnabotna River, Page Co. Bridge, Near Essex, 
Iowa (MRO) 21-21 
East Nishnabotna River, Red Oak, Iowa (MRO) 21-3, 
21-10, 21-21 
East Pass Channel from Gulf of Mexico into 
Choctawhatchee Bay, Fla. (SAM) 10-7, 10-24, 10-30 
East Peoria Drainage and Levee District (NCR) 28-16, 
28-18 
East Peoria Sanitary District, Ill. (NCR) 28-18 
East Point, La. (LMN) (LMK) 11-36, 12-25 
East Poplar Bluff & Poplar Bluff, Mo. (SWL) 18-16 
East Rainelle, W. Va. (ORH) 25-19, 25-21 
East River, N.Y. (NAN) 2-30, 2-31 
East Rockaway (DEBS) Inlet, N.Y. (NAN) 2-35 
East Rockaway Inlet, N.Y. (NAN) 2-2, 2-20, 2-24, 2-30 
East Rockaway Inlet to Rockaway Inlet and Jamaica 
Bay, N.Y. (Part I) (NAN) 2-11, 2-22, 2-27 
East Rockaway Inlet to Rockaway Inlet and Jamaica 
Bay, N.Y. (Part II) (NA 2-33 
East Sidney Lake, N.Y. (NAB) 4-17, 4-28 
East St. Louis and Vicinity, Ill. (LMS) 14-3, 14-9, 14-11 
East Weaver Creek, Calif. (SPK) 35-24 
Eastern Branch, Va. (NAO) 5-21 
Eastern Rapidis and South-Central Avoyelles 
Parishes, La. (MR+T) 42-16, 42-28, 42-50, 42-58 
Eastlake, Ohio (NCB) 32-34 
Eastman, H.V., Lake, Calif. (SPK) 35-4, 35-18 
Eastport Harbor, Maine (NED) 1-50 
Eau Gallie Harbor, Wis. (NCS) 27-5, 27-19 
Eau Gallie Harbor, Fla. (SAJ) 9-49, 9-50 
Echo Bay Harbor, N.Y. (NAN) 2-31 
Edenton Harbor, N.C. (SAW) 6-26 
Edgartown Harbor, Mass. (NED) 1-50 
Edisto River, S.C. (SAN) 7-8, 7-15, 7-16 
Edisto River, North Fork, S.C. (SAN) 7-16 
Edisto River, Vicinity Canadays Landing, S.C. (SAN) 
7-16 
Ediz Hook, Wash. (NPS) 38-2, 38-13, 38-18 
Edmonds Harbor, Wash. (NPS) 38-24, 38-31 
Edward Macdowell Lake, N.H. (NED) 1-24, 1-38, 1-63 
Eel River, Calif. (SPK) 35-24 
Egegik River, Alaska (NPA) 40-12 
Eighteen Mile Island, Ky. (ORL) 24-31 
El Dorado, Kans., W. Br., Walnut River, Channel 
Improvement (SWT) 19-24 
El Dorado Lake, Kans. (SWT) 19-7, 19-18, 19-23 
El Paso, Tex. (SWA) 17-2, 17-9, 17-11 
El Tuque Beach, P.R. (SAJ) 9-21, 9-32, 9-43 
Eldred, Ill. (LMS) 14-14 
Eldred, Pa. (ORP) 26-29 
Eldred and Spankey Drainage and Levee District, Ill. 
(LMS) 14-3, 14-9, 14-11 
Elfin Cove, Alaska (NPA) 40-12 
Elizabeth, N.J. (NAN) 2-12, 2-22, 2-27 
Elizabeth River, N.J. (NAN) 2-35, 2-36 
Elizabethtown, ill. (ORL) 24-23, 24-26 
Elk and Little Elk Rivers, Md. (NAB) 4-36 
Elk City Lake, Kans. (SWL) SWT) 18-21, 19-7, 19-19, 
19-25 
Elk Creek, Clyde, Kans. (MRK) 20-19 
Elk Creek Harbor, Pa. (NOB) 32-32 
1-12

INDEX 
Elk Creek Lake, Oreg. (NPP) 37-14, 37-30, 37-39 
Elk River, Ala. and Tenn. (ORN) 23-13 
Elk River, Minn. (NCS) 27-24, 27-28 
Elk River, W. Va. (ORH) 25-18 
Elkhorn River, Q Street Bridge, near Gretna, Nebr. 
(MRO) 21-21 
Elkhorn River, Ray Bridge, near Norfolk, Nebr. 
(MRO) 21-21 
Elkins, W. Va. (ORP) 26-4, 26-14, 26-19, 26-27 
Elkland, Pa. (NAB) 4-38 
Elkport, Iowa (NCR) 28-16, 28-18 
Ellerbe Creek, Durham County, N.C. (SAW) 6-28 
Ellicott Creek, N.Y. (NOB) 32-13, 32-20 
Ellis Swamp, Gates County, N.C. (SAW) 6-28 
Elm Fork Floodway, Tex. (SWF) 16-6, 16-16, 16-20 
Elmira, N.Y. (NAB) 4-17, 4-28 
Elochoman Slough, Wash. (NPP) 37-43 
Elwha River, Wash. (NPS) 38-26 
Emergency Bank Protection Activities 
Alaska District (NPA) 40-6 
Albuquerque, N. Mex., District (SWA) 17-8 
Buffalo, N.Y., District (NCB) 32-36 
Chicago, Ill., District (NCC) 30-7 
Detroit, Mich., District (NCE) 31-30 
Huntington, W. Va. District (ORH) 25-10 
Kansas City, Mo., District (MRK) 20-9 
Little Rock, Ark., District (SWL) 18-7 
Los Angeles, Calif., District (SWL) 33-10 
Louisville, Ky., District (ORL) 24-14, 24-32 
Memphis, Tenn., District (LMM) 13-5 
Nashville, Tenn., District (ORN) 23-19 
New England Division (NED) 1-30 
New York, N.Y., District (NAN) 2-37 
Omaha, Nebr., District (MRO) 21-7 
Pacific Ocean Division (POD) 36-5' 
Pittsburgh, Pa., District (ORP) 26-30 
Portland, Oreg., District (NPP) 37-15 
Rock Island, Ill., District (NCR) 28-20 
Sacramento, Calif., District (SPK) 35-14 
San Francisco, Calif., District (SPN) 34-4 
St. Louis, Mo., District (LMS) 14-14 
St. Paul, Minn., District (NCS) 27-29 
Tulsa, Okla., District (SWT) 19-14 
Vicksburg, Miss., District (LMK) 12-12 
Emergency Flood Control Activities 
Alaska District (NPA) 40-6 
Alburquerque, N. Mex., District (SWA) 17-8 
Baltimore, Md., District (NAB) 4-21 
Buffalo, N.Y., District (NCB) 32-37 
Charleston, S.C., District (SAN) 7-8 
Chicago, Ill., District (NCC) 30-7 
Detroit, Mich., District (NCE) 31-33 
Fort Worth, Tex., District (SWF) 16-14 
Galveston, Tex., District (SWG) 15-11 
Huntington, W. Va., District (ORH) 25-10 
Jacksonville, Fla., District (SAJ) 9-28 
Kansas City, Mo., District (MRK) 20-9 
Little Rock, Ark., District (SWL) 18-7 
Los Angeles, Calif., District (SPL) 33-10 
Louisville, Ky., District (ORL) 24-14 
Memphis, Tenn., District (LMM) 13-5 
New England Division (NED) 1-30 
New Orleans, La., District (LMN) 11-20 
Norfolk, Va., District (NAO) 5-14 
Omaha, Nebr., District (MRO) 21-7 
Philadelphia, Pa., District (NAP) 3-13 
Portland, Oreg., District (NPP) 37-15 
Rock Island, Ill., District (NCR) 28-20 
Sacramento, Calif., District (SPK). 35-14 
San Francisco, Calif., District (SPN) 34-4 
Savannah, Ga., District (SAS) 8-7 
Seattle, Wash., District (NPS) 38-32 
St. Louis, Mo., District (LMS) 14-7 
St. Paul, Minn., District (NCS) 27-29 
Tulsa, Okla., District (SWT) 19-14 
Vicksburg, Miss., District (LMK) 12-12 
Walla Walla, Wash., District (NPW) 39-2 
Wilmington, N.C., District (SAW) 6-16 
Emergency Streambank and Shoreline Protection, 
Jacksonville, Fla., District (SAJ) 9-28 
Emergency Streambank and Shoreline Protection, 
New York, N.Y., District (NAN) 2-37 
Empire-Stratton, Ohio (ORP) 26-23, 26-27 
Emsworth Locks and Dam, Pa. (ORD) 22-1, 22-7 
Enderlin, N. Dak. (NCS) 27-6, 27-19, 27-28 
Endicott-Johnson City and Vestal, N.Y. (NAB) 4-38, 
4-41 
Engineer Topographic Laboratories (ETL) 51-1 
England Pond Levee, Ill. (ORL) 24-21, 24-25, 24-30 
English, Ind. (ORL) 24-21, 24-31 
English Coulee, Grand Forks, N. Dak. (NCS) 27-29 
Enid Diversion Canal and Levee, Okla. (SWT) 19-27 
Enid Lake, Miss. (MR�T) 42-21, 42-57 
Enid Levee Floodway, Okla. (SWT) 19-24 
Entiat River, Wash. (NPS) 38-26 
Erie Harbor, Pa. (NCB) 32-5, 32-18, 32-25, 32-36 
Escambia and Conecuh Rivers, Fla. and Ala. (SAM) 
10-38 
Escambia Bay, Fla. (SAM) 10-37 
Esopus Creek, N.Y. (NAN) 2-36, 2-37 
Esquatzel Coulee, Wash. (NPW) 39-17, 39-21 
Essex River, Mass. (NED) 1-50 
Estes, Carl L. Dam and Lake, Tex. (SWF) 16-23 
Euclid Creek, Cleveland, Ohio (NCB) 32-14, 32-30 
Eufaula Lake, Okla. (SWL) (SWT) 18-21, 19-14, 19-21, 
19-25 
Evansdale, Iowa (NCR) 28-5, 28-10, 28-14 
Evnaston, Ill. (NCC) 30-15 
Everett Harbor and Snohomish River, Wash. (NPS) 
38-3, 38-13, 38-18 
Everglad Harbor, Fla. (SAJ) 9-50 
Exeter River, N.H. (NED) 1-50 
Existing levees and extensions from Bastrop, La. to 
mouth of Boeuf River (LMK) 12-22 
Experimental Chloride Control Project, Red River 
Basin, Estelline and Gutherie, Tex. (SWT) 19-24 
1-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Falls Lake, N.C. (SAW) 6-14, 6-21 
Falmouth Harbor, Mass. (NED) 1-50 
Falmouth Lake, Ky. (ORL) 24-22, 24-28 
Fancy Bluff Creek, Ga. (SAS) 8-16 
Far Creek, N.C. (SAW) 6-26 
Fargo, N. Dak. (NCS) 27-28 
Farm Creek, Ill. (NCR) 28-5, 28-10, 28-14 
Farmers Drainage and Levee District (NCR) 28-16, 
28-18 
Farmers Levee and Drainage District (NCR) 28-17 
Farmington, N.H. (NED) 1-29 
Faulkner County Levee District No. 1, Arkansas 
River, Ark. (SWL) 18-16 
Feather River, Calif. (SPK) 35-23 
Federal Energy Regulatory Commission 47-1 
Federal Energy Regulatory Commission Licenses at 
Locks and Dams, Ohio River (ORD) 22-6 
Ferguson Creek, Oreg. (NPP) 37-48 
Fern Ridge Lake, Oreg. (NPP) 37-14, 37-30, 37-39, 
37-51, 37-53 
Fernandina Harbor, Fla. (SAJ) 9-5, 9-29, 9-35 
Ferrells Bridge Dam-Lake O' The Pines, Tex, (LMN) 
11-36 
Ferrells Bridge Dam-Lake O' The Pines, Tex. SWF) 
16-6, 16-16, 16-20 
Filberts Creek, N.C. (SAW) 6-28 
Fire Island Inlet to Jones Inlet, N.Y. (NAN) 2-3, 2-20, 
2-24, 2-30, 2-32 
Fire Island Inlet to Montauk Point, N.Y. (NAN) 2-13, 
2-22, 2-28 
Fisher, O.C., Dam and Lake, Tex. (SWF) 16-10, 16-17, 
16-21 
Fishing Bay, Md. (NAB) 4-36, 4-40 
Fishing Creek, Md. (NAB) 4-4, 4-24, 4-31 
Fishing Creek, N.C. (SAW) 6-26 
Fishing Creek, Pine Grove, W. Va. (ORH) 25-21 
Fishtrap Lake, Ky. (ORH) 25-5, 25-12, 25-16 
Fitchburg, Mass. (NED) 1-29, 1-55 
Fivemile River Harbor, Conn. (NED) 1-50, 1-57 
Flannagan, John W., Dam and Reservoir, Va. (ORH) 
25-5, 25-12, 25-16 
Falt Creek, Oreg. (NPP) 37-48 
Flat Rock Creek Channel Improvement, Tulsa, Okla. 
(SWT) 19-24, 19-27 
Flathead River, Mont. (NPS) 38-24, 38-26 
Fletcher and Sunshine Gardens Levee, Ind. (ORL) 
24-23, 24-26 
Floating Breakwater Protype Test Program, Seattle, 
Wash. (NPS) 38-3 
Flood Control and Coastal Emergency Activities 
Huntington, W. Va., District (ORH) 25-10 
Pittsburgh, Pa., District (ORP) 26-13 
Flood Control Activities 
Los Angeles, Calif., District (SPL) 33-10 
Sacramento, Calif., District (SPK) 35-14 
Tulsa, Okla., District (SWT) 19-13 
Floodwall and Levees at Portland, Oreg. (NPP) 37-48 
Florence Levee, Kans. (SWT) 19-24, 19-27 
Floyd River, Sioux City, Iowa (MRO) 21-16, 21-21 
Flushing Bay and Creek, N.Y. (NAN) 2-3, 2-20, 2-24, 
2-30 
Fly Creek, Ala. (SAM) 10-37, 10-38 
Follansbee, W. Va. (ORP) 26-24 
Folly Brook, Wethersfield, Conn. (NED) 1-55, 1-61 
Folly River, S.C. (SAN) 7-4, 7-9, 7-12 
Folsom Lake, Calif. (SPK) 35-24 
Fore River, Braintree and Weymouth, Mass. (NED) 
1-7, 1-33, 1-43 
Forest Heights, Md. (NAB) 4-38, 4-41 
Forestville, Mich. (NCE) 31-75 
Forked Deer River, Tenn., including South Fork 
(LMN) 13-10 
Forsyth, Mont. (MRO) 21-16, 21-20 
Fort Chartres and Ivy Landing Drainage District No. 
5 and Stringtown Drainage and Levee District No. 4, 
Ill. (LMS) 14-14 
Fort Cobb Reservoir, Okla. (SWT) 19-13 
Fort Fisher and Vicinity, N.C. (SAW) 6-10, 6-20 
Fort Gibson Lake, Okla. (SWL) (SWT) 18-21, 19-15, 
19-21, 19-25 
Fort Kent, Maine (NED) 1-29, 1-55 
Fort Leavenworth, Kans., Bridge Removal (MRK) 
20-18 
Fort Loudon Lock and Dam, Tenn. (ORN) 23-17 
Fort Macon State Park, N.C. (SAW) 6-27 
Fort Madison, Iowa (NCR) 28-5, 28-11, 28-14 
Fort Madison Harbor, Iowa (NCD) 29-9 
Fort Myers Beach, Fla. (SAJ) 9-5, 9-2, -3 9-49 
Fort Niagara State Park, N.Y. (NCB)JB244' 
Fort Peck Lake, Mont. (MRO) 21-7, 21-11, 21-'15 
Fort Pierce, Fla. (SAJ) 9-6, 9-30, 9-36, 9-49 
Fort Randall Dam-Lake Francis Case, S. Dak. (MRO) 
21-8, 21-11, 21-15 
Fort Scott Lake, Kans. (MRK) 20-19, 20-23 
Fort Smith, Arkansas River, Ark. (SWL) 18-16 
Fort Supply Lake, Okla. (SWT) 19-8, 19-19 
Fort Worth Floodway (Clear Fork), Tex. (SWF) 16-23 
Fort Worth Floodway (West Fork), Tex. (SWF) 16-23 
Foss Reservoir, Okla. (SWT) 19-13 
Foster Creek Road, Wash. (NPS) 38-26 
Foster Joseph Sayers Dam, Pa. (NAB) 4-20, 4-29 
Foster Lake, Oreg. (NPP) 37-51 
Four Pole Creek, W. Va. (ORH) 25-21 
Four River Basins, Fla. (SAJ) 9-26, 9-33, 9-45, 9-56 
Fourche Creek, Little Rock, Ark. (SWL) 18-16 
Fourmile Run, Va. (NAB) 4-13, 4-27, 4-34 
Fox Point Barrier, R.I. (NED) 1-55 
Fox River, Wis. (NCE) 31-7, 31-39, 31-56, 31-73 
1-14

INDEX 
Fox River Locks and Dams, Wis. (NCE) 31-73 
Francis E. Walter Dam, Pa. (NAP) (NAB) 3-13, 3-19 
Frankfort, Kans. (MRK) 20-19 
Frankfort, Ky. (ORL) 24-22, 24-30 
Frankfort Harbor, Mich. (NCE) 31-8, 31-39, 31-57 
Franklin Falls Dam, N.H. (NED) 1-24, 1-38, 1-63 
Franklin, W.P., Lock and Dam, Fla. (SAJ) 9-52 
Frazer-Wolf Point, Mont. (MRO) 21-16 
Frazeysburg, Ohio (ORH) 25-20 
Freeport, Ill. (NCR) 28-17 
Freeport, Pa. (ORP) 26-24 
Freeport and Vicinity, Tex. Hurricane-Flood Protection 
(SWG) 15-10, 15-14, 15-25 
Freeport Harbor, Tex. (SWG) 15-3, 15-13, 15-18, 15-29, 
15-34 
Fremont, Ohio (NCB) 32-34 
French Broad and Little Pigeon Rivers, Tenn. (ORN) 
23-13 
Frenchboro Harbor, Maine (NED) 1-50 
Freshwater Bayou, La. (LMN) 11-7, 11-21, 11-27 
Friday Harbor Marina, Wash. (NPS) 38-3, 38-14, 38-19 
Friendly, W. Va. (ORH) 25-20 
Friendsville, Md. (ORP) 26-23, 26-29 
From North Little Rock to Gillett, Ark. (Above Plum 
Bayou) (SWL) 18-16 
Fullerton, Ky. (ORH) 25-19 
Fulmer Creek, Mohawk, N.Y. (NAN) 2-36 
Fulton, Ill. (NCR) 28-5, 28-11, 28-14 
G 
Galax, Va. (ORH) 25-19, 25-21 
Galena, Ill. (NCR) 28-16, 28-18 
Galisteo Dam, N. Mex. (SWA) 17-5, 17-10, 17-12 
Gallepolis Locks and Dam, W. Va. (ORD) 22-1, 22-8 
Gallipolis, Ohio (ORH) 25-20 
Galveston Harbor and Channel, Tex. (SWG) 15-4, 
15-13, 15-19, 15-28, 15-29 
Gapway Swamp, N.C. and S.C. (SAN) (SAW) 6-28 
Gardner, Mass. (NED) 1-27, 1-55, 1-61 
Gardners Creek, N.C. (SAW) 6-28 
Garland City, Ark. (LMN) (LMK) 11-36, 12-25 
Garnett Lake, Kans. (MRK) 20-19, 20-23 
Garrison Dam-Lake Sakakawea, N. Dak. (MRO) 21-8, 
21-11, 21-15 
Gasconade River, Mo. (MRK) 20-18 
Gastineau Channel, Alaska (NPA) 40-12 
Gate Creek Lake, Oreg. (NPP) 37-46, 37-53 
Gathright Dam and Lake Moomaw, Va. (NAO) 5-12, 
5-18, 5-23 
Gauley River, W. Va. (ORH) 25-18 
Gavins Point Dam-Lewis and Clark Lake, Nebr. and 
S. Dak. (MRO) 21-15, 21-16 
Gaysville Lake, Vt. (NED) 1-57 
Genegantslet Lake, N.Y. (NAB) 4-39 
General Edgar Jadwin Dam and Reservoir, Pa. (NAP) 
3-14, 3-20 
General Joe Wheeler Dam (ORN) 23-17 
Geneva-On-The-Lake, Ohio (NCB) 32-6, 32-18 
Genoa Sewer Facility,N.C. (SAW) 6-13, 6-21 
Geographic Sciences Laboratory 51-1 
George, Walter R., Lock and Dam, Ala. and Ga. (SAM) 
10-20, 10-27, 10-36 
George W. Andrews Lock and Dam, Ala. and Ga. 
(SAM) 10-19, 10-27, 10-36 
Georges River, Maine (NED) 1-50 
Georgetown Harbor, S.C. (SAN) 7-4, 7-9, 7-12, 7-17 
Gering Valley, Nebr. (MRO) 21-16, 21-21 
Gila and Salt Rivers Levee and Channel Improvements, 
Ariz. (SPL) 33-23 
Gila River Basin, Ariz. (SPL) 33-6, 33-13, 33-14, 33-23 
Giles Creek, Elkhorn, Nebr. (MRO) 21-17 
Gill Township Levee, Ind. (ORL) 24-21, 24-30 
Gillham Lake, Ark. (SWL) 18-6, 18-11, 18-22 
Gill's Creek, Lancaster, S.C. (SAN) 7-17 
Girty's Run, Millvale, Pa. (OEP) 26-4, 26-14 
Glasgow, Mont. (MRO) 21-16, 21-20 
Gleason Creek, Nev. (SPK) 35-24 
Glen Cove Creek, N.Y. (NAN) 2-31 
Glen Cove Harbor, N.Y. (NAN) 2-35 
Gloucester Harbor and Annisquam River, Mass. (NED) 
1-7, 1-33, 1-44 
Goat Island, Ga. and S.C. (SAS) 8-17 
Golconda, Ill. (ORL) 24-21, 24-25, 24-30 
Gold Creek, Alaska (NPA) 40-13 
Goldsboro, Neuse River, N.C. (SAW) 6-13, 6-21 
Goleta, Calif., and Vicinity (SPL) 33-23 
Gooding Area, Idaho (NPW) 39-17, 39-21 
Goose Creek, Md. (NAB) 4-36 
Goose Creek, S.C. (SAN) 7-15 
Goose Hill Channel, Va. (NAO) 5-27 
Gordons Creek, Hattiesburg, Miss. (SAM) 10-13, 10-25, 
10-35 
Gordons Landing, Lake Champlain, Vt. (NAN) 2-31 
Goshen Creek, N.J. (NAP) 3-24 
Governor's Run, Md. (NAB) 4-39 
Gowanus Creek Channel, N.Y. (NAN) 2-31 
Grafton, N. Dak. (NCS) 27-6 
Grafton Small Boat Harbor, Ill. (LMS) 14-13 
Grahn, Ky. (ORH) 25-21 
Grand Bayou Pass, La. (LMN) 11-34 
Grand Calumet River Lock, Ind. (NCC) 28-22 
Grand Forks, N. Dak. (NCS) 27-28 
Grand Haven Harbor and Grand River, Mich. (NCE) 
31-9, 31-39, 31-57, 31-77 
Grand Isle and Vicinity, La. (LMN) 11-15, 11-24, 11-29 
Grand Lagoon, Panama City, Fla. (SAM) 10-37 
Grand Lake, Okla. (SWT) 19-15 
Grand Marais Harbor, Mich. (NCE) 31-9, 31-39, 31-58, 
31-75 
Grand Marais Harbor, Minn. (NCE) 31-75 
Grand Prairie, Tex., Sanitary Landfill (SWF) 16-6, 
16-16, 16-20 
Grand Prairie-Bayou Meto, Ark., (MR+T) 42-17, 42-52 
Grand River, Grandville, Mich. (NCE) 31-76, 31-77 
Grand River, Lansing, Mich. (NCE) 31-76 
Grand Tower Drainage and Levee District, Ill. (LMS) 
14-14 
I-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Grand Traverse Bay Harbor, Mich. (NCE) 31-10, 
31-40, 31-58 
Grande Ronde Lake, Oreg. (NPW) 39-17 
Grande Ronde Valley, Oreg. (NPW) 39-17, 39-20 
Grandview, Ind. (ORL) 24-23, 24-26 
Grandview Bay Harbor, N.Y. (NCB) 32-36 
Grant Parish, Below Colfax, La. (LMN) (LMK) 11-36, 
12-25 
Grant's Canal Lake Providence, La. (MR+T) 42-56 
Granville, Pa. (ORP) 26-23, 26-29 
Grapevine Lake, Tex. (SWF)16-7, 16-17, 16-20 
Grasse River (Massena), N.Y. (NCB) 32-32 
Grassy Creek, Ind. (ORL) 24-21, 24-31 
Graves Creek, Idaho (NPW) 39-17 
Grays Harbor and Chehalis River, Wash. (NPS) 38-4, 
38-14, 38-19 
Grays Landing Lock and Dam, Pa. (ORP) 26-26 
Grays Reef Passage, Mich. (NCE) 31-74, 31-75 
Grays River, Wash. (NPP) 37-43 
Grayson Lake, Ky. (ORH) 25-5, 25-12, 25-16 
Great Chazy River, N.Y. (NAN) 2-31 
Great Coharie Creek, N.C. (SAW) 6-32 
Great Falls, Mont. (MRO) 21-4, 21-10, 21-13 
Great Kills Harbor, N.Y. (NAN) 2-31 
Great Lakes to Hudson River Waterway, N.Y. (NAN) 
2-30, 2-31 
Great Pee Dee River, S.C. (SAN) 7-15 
Great Salt Plains Lake, Okla. (SWT) 19-8, 19-19 
Great Salt Pond, R.I. (NED) 1-7, 1-33, 1-44 
Great Sodus Bay Harbor, N.Y. (NCB) 32-11, 32-32, 
32-38 
Great South Bay, N.Y. (NAN) 2-31 
Green and Barren Rivers, Ky. (ORL) 24-2, 24-15, 
24-19, 24-24, 24-28 
Green Bay Harbor, Wis. (NCE) 31-10, 31-40, 31-58 
Green Bay Levee and Drainage District No. 2, Iowa 
(NCR) 28-18 
Green Harbor, Mass. (NED) 1-8, 1-33, 1-44 
Green Island Levee and Drainage District, Iowa (NCR) 
28-18 
Green Peter-Foster Lakes, Oreg. (NPP) 37-21, 37-31, 
37-42, 37-51, 37-53 
Green River, Wash. (NPS) 38-26 
Green River Lake, Ky. (ORL) 24-8, 24-16, 24-28 
Green Valley Creek, Calif. (SPK) 35-24 
Greene, N.Y. (NAB) 4-38, 4-41 
Greenfield Bayou Levee, Ind.(ORL) 24-22, 24-25 
Greenport Harbor, N.Y. (NAN) 2-31 
Greenup, Ky. (ORH) 25-19 
Greenup Locks and Dam, Ky. (ORD) 22-1, 22-8 
Greenvale Creek, Va. (NAO) 5-25 
Greenville, Tex. (SWF) 16-7, 16-17, 16-21 
Greenville Floodway, Tex. 16-23 
Greenville Harbor, Miss. (MR+T) 42-29, 42-54 
Greenwich Bay, R.I. (NED) 1-50 
Greenwich Harbor, Conn. (NED) 1-50 
Greenwich Point Beach, Conn. (NED) 1-57 
Greenwood Beach, Evanston, Ill. (NCC) 30-6 
Greers Ferry Lake, Ark. (SWL) 18-8, 18-12, 18-23 
Gregory Drainage District, Mb. (NCR) 28-16, 28-19 
Grenada Lake, Miss. (MR+T) 42-21, 42-57 
Greybull, Wyo. (MRO) 21-16, 21-20 
Griffinthsville-Yawkey, W. Va. (ORH) 25-21 
Grove Lake, Kans. (MRK) 20-19 
Guadalupe River (Remove Log Jams), Tex. (SWG) 
15-27 
Guayanes Harbor, P.R. (SAJ) 9-50 
Guilford Harbor, Conn. (NED) 1-8, 1-33, 144 
Guilford Point Beach (Jacobs Beach), Guilford, Conn. 
(NED) 1-54 
Gulf Beach, Milford, Conn. (NED) 1-54 
Gulf Intrcoastal Waterway between Apalachee Bay, 
Fla., and Mexican Border (Mobile District) (SAM) 
10-7, 10-24, 10-31 
Gulf Intacoastal Waterway between Apalachee Bay, 
Fla., and Mexican Border (New Orleans Dist.) (LMN) 
11-7, 11-22, 11-27, 11-32 
Gulf Intracoastal Waterway between Apalachee Bay 
Fla., and Mexican Border (SWG) 15-5, 15-13, 
15-20, 15-28, 15-32, 15-33, 15-34 
Gulf Intracoastal Waterway St. Marks to Tampa Bay, 
Fla. (SAJ) 9-50 
Gulfport Harbor, Miss. (SAM) 10-8, 10-24, 10-31 
Gull Lake Reservoir, Minn. (NCS) 27-26 
Guntersville Lock and Dam, Ala. (ORN) 23-17 
Guttenberg, Iowa (NCS) 27-24, 27-28 
Guyandotte River, W. Va. (ORH) 25-18 
Gypsum, Kans. (MRK) 20-3, 20-11, 20-15 
H 
H.V. Eastman Lake, Calif. (SPK) 35-4, 35-18 
Hackleman Corners Lake, Mo. (MRK) 20-20 
Haines Harbor, Alaska (NPA) 40-12 
Haleiwa Beach, Hawaii (POD) 36-15 
Haleiwa Small Boat Harbor, Hawaii (POD) 36-14, 
36-16 
Halfmoon Bay Harbor, Calif. (SPN) 34-10 
Hall Meadow Brook, Conn. (NED) 1-29 
Hall Meadow Brook Dam, Conn. (NED) 1-55, 1-61 
Halsite Area, Huntington, N.Y. (NAN) 2-36 
Hamburg L-575, Iowa (MRO) 21-21 
Hamlin Beach Harbor, N.Y. (NCB) 32-32 
Hamlin Beach State Park, N.Y. (NCB) 32-34 
Hammersley Inlet, Wash. (NPS) 38-24, 38-30 
Hammonassett Beach, Madison, Conn. (NED) 1-54 
Hammond Bay Harbor, Mich. (NCE) 31-11, 31-40, 
31-58 
Hammond Small Boat Basin, Oreg. (NPP) 37-43 
Hammondsport, N.Y. (NCB) 32-34 
Hampton Beach, Hampton, N.H. (NED) 1-50 
Hampton Creek, Va. (NAO) 5-25 
Hampton Harbor, N.H. (NED) 1-50 
Hampton Institute, Va. (NAO) 5-26 
Hampton Roads and Harbors of Norfolk and Newport 
News, Va.-Collection and Removal of Drift (NAO) 
5-5, 5-16, 5-20 
Hampton Roads harbor, Supervision of (NAO) 5-9, 5-17 
1-16 
''

INDEX 
Hana Small Boat Harbor, Hawaii (POD) 36-16 
Hanapepe Bay, Hawaii (POD) 36-15 
Hanapepe River, Hawaii (POD) 36-9, 36-15 
Hancock Brook Lake, Conn. (NED) 1-21, 1-37, 1-62 
Hanging Rock, Ohio (ORH) 25-20 
Hannibal, Mo. (NCR) 28-5, 28-11, 28-14 
Hannibal Harbor, Mo. (NCD) 29-9 
Hannibal Locks and Dam, W. Va. (ORD) 22-1, 22-7 
Hanson, Howard A., Dam, Wash. (NAS) 38-8, 38-15, 
38-21 
Harbor Beach Harbor, Mich. (NCE) 31-11, 31-40, 31-58 
Harbor of Refuge, Block Island, R.I. (NED) 1-8, 1-34, 
1-44 
Harbor of Refuge, Delaware Bay, Del. (NAP) 3-24 
Harbor of Refuge, N.C. (SAW) 6-29 
Harbor of Refuge and Pt. Judith Pond, R.I. (NED) 1-8 
1-34, 1-45 
Harden, Cecila M., Lake, Ind. (ORL) 24-8, 24-16, 24-28 
Harkers Island Harbor, N.C. (SAW) 6-30 
Harlan County Lake, Nebr. (MRK) 20-3, 20-11, 20-14, 
20-23 
Harlem River, N.Y. (NAN) 2-30, 2-31 
Harpers Ferry, W. Va. (NAB) 4-39 
Harpswell, Maine (NED) 1-29 
Harraseeket River, Maine (NED) 1-50 
Harriet Island Harbor, St. Paul, Minn. (NCD) 29-8 
Harris Fork Creek, Tenn. and Ky. (MR+T) 42-58 
Harrisburg, Ill. (ORL) 24-21, 24-25, 24-30 
Harrison County, Miss. (SAM) 10-39 
Harrisonville Levee and Drainage District, Ill. (LMS) 
14-14 
Harrisville Harbor, Mich. (NCE) 31-11, 31-40, 31-59 
Harrodsburg, Ky. (ORL) 24-31 
Harry S. Truman Dam and Reservoir, Mo. (MRK) 
20-9, 20-13, 20-18, 20-23 
Harsha, William H., Lake, Ohio (ORL) 24-13, 24-18, 
24-28 
Hartford, Conn. (NED) 1-29, 1-55, 1-61 
Hartford, Vt. (NED) 1-55, 1-61 
Hartford, W. Va. (ORH) 25-20 
Hartwell Drainage and Levee District, Ill. (LMS) 14-3, 
14-9, 14-11 
Hartwell Lake, Ga. and S.C. (SAS) 8-8, 8-12, 8-15, 
8-17 
Harvey Canal, Bayou Barataria Levee, La. (LMN) 
11-36 
Hastings, Minn. (NCD) 27-28 
Hastings Harbor, Minn. (NCD) 29-8 
Haverhill, Mass. (NED) 1-29 
Havre, Mont. (MRO) 21-16, 21-20 
Havre, Scott Coulee-Bull Hook Dam, Mont. (MRO) 
21-20 
Hawarden, Iowa (MRO) 21-21 
Hawesville, Ky. (ORL) 24-21, 24-25, 24-30, 24-31 
Hay Creek, Birdsboro, Pa. (NAP) 3-14, 3-20 
Hay (West Harbor), Fisher's Island, N.Y. (NED) 1-50 
Hayden Island, Oreg. (NPP) 37-45, 37-52 
Hays, Kans. (MRK) 20-20 
Haysi, Va. (ORH) 25-19 
Hayward Creek, Mass. (NED) 1-29 
Hayward Creek, Quincy-Braintree, Mass. (NED) 1-55 
Heeia-Kea Small Boat Harbor, Hawaii (POD) 36-14 
Heise-Roberts Area, Idaho (NPW) 39-17, 39-21 
Heise-Roberts Extension, Idaho (NPW) 339-17, 39-20, 
39-21 
Helena Harbor, Ark. (LMN) 13-2, 13-6, 13-8 
Hellens Creek, Md. (NAB) 4-39 
Helms Lake, Ill. (ORL) 24-23, 24-29 
Hempstead County Levee District No. 1, Ark. (LMN) 
(LMK) 11-36, 12-25 
Hempstead Harbor, N.Y. (NAN) 2-31 
Henderson, W. Va. (ORH) 25-20 
Henderson Bay, Wash. (NPS) 38-26 
Henderson County Drainage Districts Nos. 1, 2 and 3, 
Ill. (NCR) 28-16, 28-19 
Henderson River, Ill. (NCR) 28-18 
Hendrick's Harbor, Maine (NED) 1-50 
Hennepin Drainage and Levee District, Ill. (NCR) 
28-16, 28-19 
Henry, Robert F., Lock and Dam, Ala. (SAM) 10-16, 
10-26 
Henry T. Rainey Dam, Ill. (NCD) 29-7 
Hergot Drainage and Levee District (NCR) 28-19 
Herkimer, N.Y. (NAN) 2-33 
Herreid, Spring Creek, S. Dak. (MRO) 21-16, 21-20 
Herring Bay & Rockhold Creek, Md. (NAB) 4-36 
Heyburn Lake, Okla. (SWT) 19-8, 19-19 
Hickman Harbor, Ky. (LMM) 13-2, 13-6, 13-8 
Hidden Dam-Hensley Lake, Fresno River, Calif. (SPK) 
35-6, 35-18 
Higginsport, Ohio (ORH) 25-20 
Highland Bayou, Tex. (SWG) 15-10, 15-15, 15-25 
Highway 12, Colo. (SWA) 17-3, 17-9, 17-11 
Hildebrand Lock and Dam. W. Va. (ORP) 26-26 
Hills Creek Lake, Oreg. (NPP) 37-22, 37-31, 37-41, 
37-51, 37-53 
Hillsborough Bay, Fla. (SAJ) 9-57 
Hillsborough River, Fla. (SAJ) 9-42 
Hillsdale Lake, Kans. (MRK) 20-3, 20-11, 20-15, 20-23 
Hillview Drainage and Levee District, Ill. (LMS) 14-4, 
14-9, 14-11 
Hilo Harbor, Hawaii (POD) 36-14, 36-16 
Hingham Harbor, Mass. (NED) 1-50 
Hitchins, Ky. (ORH) 25-21 
Hiwassee River, Tenn. (ORN) 23-13 
Hockingport, Ohio (ORH) 25-20 
Hodges Dam, Calif. (SPL) 33-24 
Hodges Village Dam, Mass. (NED) 1-28, 1-39, 1-64 
Hoh River, Wash. (NPS) 38-8, 38-15, 38-21, 38-26 
Hoko River, Wash. (NPS) 38-26 
Holbrook Levee, Ariz. (SPL) 33-10, 33-23 
Holland Harbor, Mich. (NCE) 31-11, 31-41, 31-59 
Holley Lake, Oreg. (NPP) 37-46, 37-53 
Holly, Colo. (SWA) 17-3, 17-9, 17-11 
Hollywood-Ardmore Beach along Lake Michigan, Ill. 
(NCC) 30-15 
Holmes Bay, Whiting, Maine (NED) 1-55 
Holmes Creek, Fla. (SAM) 10-38 
Holston River, Tenn. (ORN) 23-13 
Holyoke, Mass. (NED) 1-27, 1-55, 1-61 
Homer Harbor, Alaska (NPA) 40-3, 40-8, 40-11 
Hominy Swamp, N.C. (SAW) 6-29 
1-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Homme Lake and Dam, N. Dak. (NCS) 27-7, 27-20 
Homochitto River, Miss. (LMK) 12-21, 12-25 
Homosassa River, Fla. (SAJ) 9-50 
Honey Creek Levee, Ind. (ORL) 24-23, 24-26 
Honey Hill Lake, N.H. (NED) 1-57 
Honga River and Tar Bay, Md. (NAB) 4-5, 4-24, 4-31 
Honokohau Small Boat Harbor, Hawaii (POD) 36-14, 
36-16 
Honolulu Harbor, Hawaii (POD) 36-2, 36-10, 36-12, 
36-16 
Hood Canal, Wash. (NPS) 38-26 
Hoonah Harbor, Alaska (NPA) 40-3, 40-9, 40-11 
Hooper, Nebr. (MRO) 21-16, 21-21 
Hoosic Falls, Hoosic River Basin, N.Y. (NAN) 2-33 
Hop Brook Lake, Conn. (NED) 1-21, 1-38, 1-62 
Hopkinton-Everett Lakes, N.H. (NED) 1-24, 1-38, 1-63 
Hoquiam River, Wash. (NPS) 38-24, 38-26, 38-31 
Hords Creek Lake, Tex. (SWF) 16-7, 16-17, 16-21 
Horn Harbor, Va. (NAO) 5-25 
Hornell, N.Y. (NAB) 4-17, 4-28 
Horseshoe Cove, Fla. (SAJ) 9-50 
Hoskins Creek, Va. (NAO) 5-25 
Hot Springs, S. Dak. (MRO) 21-20 
Houlka Creek, Miss. (SAM) 10-39 
Houma Navigation Canal, La. (LMN) 11-10, 11-22, 
11-28 
Housatonic River, Conn. (NED) 1-9, 1-34, 1-45, 1-50 
Housatonic River Basin, Conn. (NED) 1-20, 1-30, 1-61 
Housatonic River, Pittsfield, Mass. (NED) 1-21, 1-38, 
1-61 
Housatonic River, Salisbury, Conn. (NED) 1-55, 1-57 
Housatonic River, Sheffield, Mass. (NED) 1-55 
Houston Ship Channel, Tex. (SWG) 15-6, 15-14, 15-22, 
15-28, 15-30, 15-34 
Howard A. Hanson Dam, Wash. (NAS) 38-8, 38-15, 
38-21 
Howards Mill Lake, N.C. (SAW) 6-28 - 
Hudson River, Fla. (SAJ) 9-50 
Hudson River, N.Y. (NAN) 2-3, 2-20, 2-24, 2-29, 2-30, 
2-35, 2-37 
Hudson River Channel, N.Y. (NAN) 2-30, 2-31 
Hugo Lake, Okla. (SWT) 19-8, 19-19, 19-26 
Hulah Lake, Okla. (SWT) 19-9, 19-19 
Humboldt Bay, Calif. (SPN) 34-10 
Humboldt Harbor, Alaska (NPA) 40-12 
Humboldt Harbor and Bay, Calif. (SPN) 34-6 
Humboldt River and Tributaries, Nev. (SPK) 35-24 
Hunt Drainage District and Lima Lake Drainage 
District, Ill. (NCR) 28-16, 28-19 
Hunting Island Beach, S.C. (SAN) 7-7, 7-10, 7-14 
Huntingdon, Tenn. (LMM) 134, 13-6, 13-8 
Huntington, Mass, (NED) 1-55, 1-61 
Huntington, W. Va. (ORH) 25-19, 25-21 
Huntington Harbor, N.Y. (NAN) 2-35 
Huntington Lake, Ind. (ORL) 24-9, 24-16 
Huron Harbor, Ohio (NCB) 32-7, 32-18, 32-27 
Hurrican Barrier Operations, New England Division 
(NED) 1-30 
Hutchinson Levee and Channel, Kans. (SWT) 19-24, 
19-27 
Hyannis Harbor, Mass. (NED) 1-51 
Hyde County Dike, N.C. (SAW) 6-29 
Hydraulics and Hydrology of the Great Lakes 31-35 
Hydrologic Engineering Center 53-3 
I 
Iao Stream, Hawaii (POD) 36-6, 36-9, 36-11, 36-13 
Ice Harbor at Marcus Hook, Pa. (NAP) 3-24 
Ice Harbor at New Castle, Del. (NAP) 3-24 
Ice Harbor Lock and Dam-Lake Sacajawea, Wash. 
(NPW) 39-5, 39-11, 39-15, 39-22, 39-26 
Ida Grove, Iowa (MRO) 21-16, 21-21 
Iliuliuk Harbor, Alaska (NPA) 40-12 
Illinois and Mississippi Canal, Ill. (NCR) 28-2, 28-10 
Illinois River, Ill. (MR+T) 42-20 
Illinois Waterway, Ill: and Ind. (NCR) 28-2, 28-10, 
28-12, 28-18, 28-21, 28-22, 28-23, 28-24 
Imperial Beach, Calif. (SPL) 33-5, 33-13, 33-18 
Indian Bend Wash, Ariz. (SPL) 33-6, 33-13, 33-18 
Indian Creek Area, Ill. (LMS) 14-14 
Indian Creek, Corydon, Ind. (ORL) 24-21, 24-31 
Indian Creek Lake, Emerson, Iowa (MRO) 21-4, 21-10, 
21-13, 21-17 
Indian Grave Drainage District, Ill. (NCR) 28-16, 
28-19 
Indian Hills, Ohio (ORL) 24-31 
Indian Island, Maine (NED) 1-29 
Indian Lake, Kans. (MRK) 20-19 
Indian River Inlet and Bay, Del. (NAP) 3-5, 3-18, 3-22 
Indiana Dunes National Lakeshore Emergency Stone 
Repairs, Beverly Shores, Ind. (NCC) 30-6, 30-10, 
30-13 
Indiana Harbor, Ind. (NCC) 30-4, 30-9, 30-12, 30-14, 
30-16 
Indianapolis, Ind. (Fall Creek Section) (ORL) 24-21 
Indianola, Nebr. (MRK) 20-19, 20-23 
Industry, Pa. (ORP) 26-24 
Inez, Ky. (ORH) 25-21 
Inland Route, Mich. (NCE) 31-12, 31-41, 31-59 
Inland Waterway from Chicoteague Bay, Va., to 
Delaware Bay, Del. (NAP) 3-24 
Inland Waterway from Delaware River to Chesapeake 
Bay, Del. and Md. (NAP) 3-6, 3-18, 3-22 
Inland Waterway from Franklin to Mermentau River, 
.La. (LMN) 11-34 
Inland Waterway from the Mississippi River to Bayou 
Teche, La. (LMN) 11-34 
Inland Waterway, Rehoboth Bay to Delaware Bay, 
Del. (NAP) 3-5, 3-18, 3-22 
Institute for Water Resources 53-3 
Intercounty D.D., Little Sioux River, Iowa (MRO) 
21-21 
International Boundary Waters Boards, 49-1 
International Champlain-Richelieu Board 49-1 
International Great Lakes Diversions and Consumptive 
Uses Study Board 31-33, 49-1 
International Joint Commission Board of Control (IJC) 
49-1 
1-18

INDEX 
International Kootenay Lake Board of Control 49-1 
International Lake Champlain Board of Control 49-1 
International Lake Erie Regulatory Study Board 
31-35, 49-2 
International Lake Memphremagog Board 49-2 
International Lake of the Woods Control Board 49-1 
International Lake Superior Board of Control 31-34, 
49-1 
International Niagara Board of Control 31-35, 49-1 
International Niagara Committee 49-2 
International Niagara Working Committee 31-35 
International Osoyoos Lake Board of Control 49-1 
International Rainy Lake Board of Control 49-1 
International Skagit River Board of Control 49-1 
International Souris-Red Rivers Engineering Board, 
49-1 
International St. Croix River Board of Control 49-1 
International St. Lawrence River Board of Control 
31-35, 49-1 
Interstate Bridge, Portland, Oreg. (NPP) 37-43 
Interstate Highway Bridge (Barge Channel), Oreg. 
(NPP) 37-43 
Intracoastal Waterway, Calooshatchee River to 
Anclote 
River, Fla. (SAJ) 9-6, 9-30, 9-36 
Intracoastal Waterway, Jacksonville to Miami, Fla. 
(SAJ) 9-7, 9-30, 9-36, 9-49 
Intracoastal Waterway, Miami to Key West, Fla. (SAJ) 
9-49, 9-50 
Intracoastal Waterway, Mississippi River to Bayou 
Teche, La. (LMN) 11-34 
Iola Levee, Kans. (SWT) 19-24, 19-27 
Iowa River-Flint Creek Levee District No. 16, Iowa 
(NCR) 28-16, 28-19 
Ipswich River, Mass. (NED) 1-51 
Irondequoit Bay, N.Y. (NCB) 32-7, 32-18 
Ironton, Ohio (ORH) 25-19, 25-21 
Irving Township, Jackson Co., Wis. (NCS) 27-7, 27-20 
Irvington Harbor, N.Y. (NAN) 2-35 
Isabella Lake, Kern River, Calif. (SPK) 35-6, 35-18 
Island Avenue, Quincy, Mass. (NED) 1-22, 1-38, 1-48 
Island Creek, Md. (NAB) 4-36, 4-40 
Island Creek, St. Georges Island, Md. (NAB) 4-36 
Island End River, Chelsea, Mass. (NED) 1-9, 1-34, 1-45 
Island Levee, Ind. (ORL) 24-22, 24-25 
Isle Au Haut Thoroughfare, Maine (NED) 1-51 
Isle of Shoals Harbor, Maine and N.H. (NED) 1-51 
Islesboro (The Narrows), Maine (NED) 1-22, 1-38, 148 
Israel R., Lancaster, N.H. (NED) 1-61 
Ithaca, N.Y., Cascadilla Creek (NCB) 32-36 
Ithaca, N.Y., Cayuga Inlet (NCB) 32-34 
Ithaca, N.Y., Fall Creek (NCB) 32-36 
J 
J. Perry Priest Dam and Reservoir, Ohio River Basin, 
Tenn. (ORN) 23-7, 23-9, 23-18 
Jackson, Ky. (ORL) 24-21, 24-25, 24-31 
Jackson and East Jackson, Miss. (SAM) 10-39 
Jackson Creek, Va. (NAO) 5-25 
Jackson Hole, Wyo. (NPW) 39-17, 39-21 
Jacksonburg, Fishing Creek, W. Va. (ORH) 25-21 
Jacksonville Harbor, Fla. (SAJ) 9-8, 9-30, 9-37 
Jadwin, General Edgar, Dam and Reservoir, Pa. 
(NAP) 3-14, 3-20 
Jamaica Bay, N.Y. (NAN) 2-30, 2-31 
James River, Va. (NAO) 5-5, 5-16, 5-20, 5-27 
Jamestown Reservoir, N. Dak. (MRO) 21-16 
Janesville and Indian Ford Dams, Wis. (NCR) 28-18 
Jarvis Creek, Va. (NAO) 5-25 
Jefferson River, Bank Protection, near Waterloo, 
Mont. (MRO) 21-20 
Jefferson River, Willow Creek Bridge, near Three 
Forks, Mont. (MRO) 21-20 
Jeffersonville-Clarksville, Ind. (ORL) 24-21, 24-25, 
24-30 
Jemez Canyon Dam, N. Mex. (SWA) 17-5, 17-10, 17-12 
Jenkins, Tom, Dam, Ohio (ORH) 25-14, 25-17 
Jenkins, Tom, Reservoir, Ohio (ORH) 25-9 
Jenks Levee, Okla. (SWT) 19-24, 19-27 
Jennings Beach, Fairfield, Conn. (NED) 1-54 
Jeremy Creek, S.C. (SAN) 7-4, 7-9, 7-12, 7-17 
Jim Woodruff Lock and Dam, Ga. and Fla. (SAM) 
10-20, 10-27, 10-36 
JOBS ACT CONTRACTS AWARDED 
Alburquerque, New Mex., District (SWA) 17-13 
Fort Worth, Tex., District (SWF) 16-25 
Galveston, Tex., (SWG) 15-35 
Little Rock, Ark., District (SWL) 18-25 
Tulsa, Okla., District (SWT) 19-28 
Joe Creek Channel Improvement, Okla. (SWT) 19-27 
Joe Pool Lake (Lakeville Lake), Tex. (SWF) 16-7, 
16-17, 16-21 
John Day Lock and Dam-Lake Umatilla, Oreg. and 
Wash. (NPP) 37-22, 37-31, 37-41, 37-55 
John Day River, Oreg. (NPP) 37-44, 3748 
John Drainage District, Oreg. (NPP) 37-48, 37-52 
John H. Kerr Dam and Reservoir, Va. and N.C. (SAW) 
6-16, 6-21 
John Martin Reservoir, Colo. (SWA) 17-3, 17-9 
John Redmond Dam and Reservoir, Kans. (SWT) 19-9, 
19-19 
John W. Flannagan Dam and Reservoir, Va. (ORH) 
25-5, 25-12, 25-16 
Johns Pass, Fla. (SAJ) 9-8, 9-30, 9-37, 9-49 
Johnson Bay, Lubec, Maine (NED) 1-23, 1-38, 1-48, 
1-55 
Johnson Bayou, La. (SWG) 15-27 
Johnson Creek, Vicinity of Portland, Oreg. (NPP) 
37-53 
Johnsonburg, Pa. (ORP) 26-23, 26-27, 26-29 
Johnstown, Pa. (ORP) 26-5, 26-14, 26-19, 26-27 
Jones Inlet, N.Y. (NAN) 2-4, 2-20, 2-25, 2-30 
Jonesport Harbor, Maine (NED) 1-51 
Jordan, B. Everett, Dam and Lake, N.C. (SAW) 6-11, 
6-21 
Josias River, Maine (NED) 1-51 
Joyce Creek, Camden County, N.C. (SAW) 6-13, 6-21 
1-19

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Julian, Nebr. (MRO) 21-21 
Junea Harbor, Alaska (NPA) 40-12 
K 
Kaaw Beach, Hawaii (POD) 36-15 
Kaaterskill Creek, N.Y. (NAN) 2-36 
Kahoma Stream, Hawaii (POD) 36-6, 36-9, 36-11, 
36-13 
Kahului Beach Road, Hawaii (POD) 36-14 
Kahului Harbor, Hawaii (POD) 36-2, 36-9, 36-10, 
36-12, 36-16 
Kailua Small Boat Harbor, Hawaii (POD) 36-14 
Kaimu Black Sand Beach, Hawaii (POD) 36-16 
Kake Harbor, Alaska (NPA) 40-4, 40-9, 40-11 
Kalama River (South Area) Levee, Wash. (NPP) 37-48, 
37-52 
Kalamazoo River (Battle Creek), Mich. (NCE) 31-76 
Kalamazoo River (Kalamazoo), Mich. (NCE) 31-76 
Kalaupapa Harbor, Hawaii (POD) 36-14 
Kanawha River, W. Va. (ORH) 25-2, 25-11, 25-15 
Kaneohe-Kailua Area, Hawaii (POD) 36-7, 36-11, 
36-13 
Kanakee River, Ill. and Ind. (NCC) 30-16 
Kanopolis Lake, Kans. (MRK) 20-4, 20-12, 20-15, 20-23 
Kansas City, Kans. (1962 Mod.) (MRK) 20-4, 20-12, 
20-15 
Kansas Citys on Mo. and Kansas Rivers, Mo. and 
Kans. (MRK) 20-19 
Kansas River and Minor Tributaries (MRK) 20-24 
Kansas River Navigation, Kans. (MRK) 20-18, 20-19 
Kapaa Town, Hawaii (POD) 36-15 
Kapaakea Homestead Flood Control, Hawaii (POD) 
36-16 
Karlson Island, Alaska (NPA) 40-12 
Kaskaskia Island Drainage and Levee District, Ill. 
(LMS) 14-4, 14-9, 14-11, 14-14 
Kaskaskia River, Ill. (LMS) 14-2, 14-9, 14-11 
Kaukauna Dam, Wis. (NCE) 31-73 
Kaukauna Fifth Lock, Wis. (NCE) 31-73 
Kaukauna First Lock, Wis. (NCE) 31-73 
Kaukauna Fourth Lock, Wis. (NCE) 31-73 
Kaukauna Guard Lock, Wis. (NCE) 31-73 
Kaukauna Second Lock, Wis. (NCE) 31-73 
Kaukauna Third Lock, Wis. (NCE) 31-73 
Kaulana Bay Boat Harbor, Hawaii, (POD) 36-2, 36-10 
Kaunakakai Harbor, Hawaii (POD) 36-14, 36-16 
Kaunakakai Stream, Hawaii (POD) 36-15 
Kaw Lake, Okla. (SWT) 19-9, 19-19 
Kawaihae Harbor, Hawaii (POD) 36-14, 36-16 
Kawainui Swamp, Hawaii (POD) 36-9, 36-15 
Kaweah and Tule Rivers, including Terminus Dam 
and Success Lake, Calif. (SPK) 35-7, 35-19 
Kawkawlin River, Mich. (NCE) 31-76 
Kayaderroseras Creek, Ballston Spa, N.Y. (NAN) 2-36 
Kays Creek, Utah (SPK) 35-24 
Keach Drainage and Levee District, Ill. (LMS) 14-14 
Keehi Lagoon, Hawaii (POD) 36-14 
Keene, N.H. (NED) 1-26, 1-55, 1-61 
Kehoe Lake, Ky. (ORH) 25-19 
Keithsburg Drainage District, ll. (NCR) 28-18 
Kekaha Beach, Hawaii (POD) 36-15 
Kelleys Island, Ohio (NCB) 32-32 
Kendrick, Idaho (NPW) 39-18, 39-20, 39-21 
Kenmore Navigation Channel, Wash. (NPS) 38-24 
Kennebec River, Maine (NED) 1-51 
Kennebunk River, Maine (NED) 1-9, 1-34, 1-45 
Kenosha Harbor, Wis. (NCE) 31-13, 31-41,.31-59 
Kentucky Lock and Dam, Ky. (ORN) 23-17 
Kentucky River, Ky. (ORL) 24-2, 24-15, 24-24 
Keokuk Harbor, Iowa (NCD) 29-9 
Kern River-California Aqueduct Intertie, Calif. (SPK) 
35-24 
Kerr, John H., Dam and Reservoir, Va. and N.C. 
(SAW) 6-16, 6-21 
Kerr, Robert S., Lock and Dam, Okla. (SWL) (SWT) 
18-19, 19-16, 19-21, 19-25 
Kerr, Robert S., Marine Terminal, Sallisaw, Okla. 
(SWT) 19-25 
Kerton Valley Drainage and Levee District, Ill. (NCC) 
28-19 
Ketchikan Harbor, Alaska (NPA) 40-12, 40-13 
Kawalo Harbor, Hawaii (POD) 36-16 
Kewaunee Harbor, Wis. (NCE) 31-13, 31-42, 31-60 
Kewaunee River, Wis. (NCE) 31-77 
Keweenaw Waterway, Mich. (NCE) 31-14, 3142, 31-60 
Key West, Fla. (SAJ) 9-51 
Key West Harbor, Fla. (SAJ) 9-49, 9-50 
Keyport Harbor, N.H. (NAN) 2-30, 2-31 
Keystone Lake, Okla. (SWL) (SWT) 18-21, 19-15, 
19-21, 19-25 
Kihei Beach, Hawaii (POD) 36-15 
Kikiaola Small Boat Harbor, Hawaii (POD) 36-14 
King Cove Harbor, Alaska (NPA) 40-12 
Kings Creek, Va. (NAO) 5-25 
Kingston-Edwardsville, Pa. (NAB) 4-38, 4-41 
Kingston Harbor, Wash. (NPS) 38-24, 38-31 
Kingston Harbor (North Plysmouth), Mass. (NED) 1-51 
Kingstree Branch, S.C. (SAN) 7-8, 7-16 
Kinzua Dam and Allegheny Reservoir, Pa. and N.Y. 
(ORP) 26-7, 26-15, 26-20 
Kirwan, Michael J., Dam and Reservoir, Ohio (NCR) 
26-8, 26-15, 26-20 
Kishawaukee River at De Kalb, Ill. (NCR) 28-16 
Kissimmee River, Fla. (SAJ) 9-49, 9-50 
Kittanning, Pa. (ORP) 26-29 
Kittanning, Pa. Part I (ORP) 26-23, 26-27 
Kittanning, Pa. Part II (ORP) 26-24 
Kitzmiller, Md. (NAB) 4-38, 4-41 
Klamath River, Calif. (SPK) (SPN) 35-24 
Klutina River, Copper Center, Alaska (NPA) 40-13 
Knappa Area, Oreg. (NPP) 37-44 
Knapps Narrows, Md. (NAB) 4-36, 4-40 
Knife River Harbor, Minn. (NCE) 31-14, 31-42, 31-60 
Knights Valley Lake, Calif. (SPN) 34-11 
Knightville Dam, Mass. (NED) 1-17, 1-36, 1-60 
Knobb's Creek, N.C. (SAW) 6-26 
Kodiak Harbor, Alaska (NPA) 40-12 
1-20

INDEX 
Kootenai River, Idaho and Mont. (NPS) 38-24, 38-26 
Kualoa Regional Park, Hawaii (POD) 36-15 
Kuliouou Stream, Hawaii (POD) 36-9, 36-15 
L 
L'Anguille Basin, Ark. (MR+T) 42-28 
L'Anguille River, Ark. (MR+T) 42-19 
La Conner, Wash. (NPS) 38-26 
La Crosse, Wis. (NCS) 27-8 
La Farge Lake and Channel Improvement, Wis. (NCS) 
27-8, 27-20 
La Grange Bayou, Fla. (SAM) 10-37, 10-38 
La Grange Lock and Dam, Ill. (NCC) 28-21, 28-22 
La Pointe Harbor, Wis. (NCE) 31-75 
La Trappe, Md. (NAB) 4-36 
Lac La Belle Harbor, Mich. (NCE) 31-15, 31-42, 31-60 
Lac Qui Parle Lake, Minnesota River, Minn. (NCS) 
27-7, 27-20 
Lacey Drainage and Levee District, Ill. (NCC) 28-19 
Lacey, Langellier, West Mantanzas and Kerton Valley 
and Drainage and Levee District, Ill. (NCR) 28-16 
Lackawanna, N.Y. (NCB) 32-34 
Lackawanna River Basin, Pa. (NAB) 4-14, 4-35 
Lafayette Lake, Ind. (ORL) 24-22 
Lafayette River, Va. (NAO) 5-25 
Lago De Cerrillos, P.R. (SAJ) 9-45 
Lago De Portugues, P.R. (SAJ) 9-45 
Lagoon Pond, Martha's Vineyard, Mass. (NED) 1-51 
Lahaina Small Boat Harbor, Hawaii (POD) 36-14 
Lake Ashtabula and Baldhill Dam, Sheyenne River, 
N. Dak. (NCS) 27-8, 27-20 
Lake Borgue and Chef Menteur-Bulkheads and Jetties 
(LMN) 11-34 
Lake Brownwood Modification, Tex. (SWF) 16-8, 16-17, 
16-21 
Lake Bryan, Wash. (NPW) 39-6 
Lake Camanche, Calif. (SPK) 35-24 
Lake Celilo, Wash. and Oreg. (NPP) 37-24, 37-31, 
31-41, 31-55 
Lake Champlain Narrows, N.Y. (NAN) 2-6, 2-21, 2-25, 
2-30 
Lake Charles Deep Water Channel, La. (LMN) 11-34 
Lake Chautauqua and Chadakoin River, N.Y. (ORP) 
26-24, 26-27 
Lake City, Tenn. (ORN) 23-19 
Lake City Harbor, Minn. (NCD) 29-8 
Lake Crescent and Dunnus Creek, Fla. (SAJ) 9-49, 
9-50 
Lake Crockett, Wash. (NPS) 38-4, 38-14, 38-19, 38-31 
Lake Darling, N. Dak. (NCS) 27-9, 27-20 
Lake Douglas, Ga. (SAM) 10-39 
Lake Erie-Ohio Canal, Ohio and Pa. (ORP) 26-24 
Lake Fork Lake, Sabine River, Tex. (SWF) 16-23 
Lake Francis Case, S. Dak. (MRO) 21-8, 21-11 
Lake Greeson, Ark. (LMK) 12-8, 12-14, 12-22 
Lake Herbert G. West, Wash. (NPW) 39-7 
Lake Hudson, Okla. (SWT) 19-15 
Lake Kemp, Tex. (SWT) 19-9, 19-19 
Lake Meredith, Okla. (SWT) 19-13 
Lake Michigan-Lake Bluff, Ill. (NCC) 30-15 
Lake Michigan-Lake Forest, Ill. (NCC) 30-15 
Lake Montauk Harbor, N.Y. (NAN) 2-30, 2-31 
Lake Ocklawaha, Fla. (SAJ) 9-5 
Lake Ogleton, Md. (NAB) 4-40 
Lake Oroville, Calif. (SPK) 35-24 
Lake Ouachita (Blakely Mountain Dam), Ark. (LMK) 
12-7, 12-14, 12-22 
Lake Pontchartrain, La. (MR�T) 42-16, 42-56 
Lake Pontchartrain, La. Project Levees (MR+T) 42-45 
Lake Pontchartrain and Vicinity, La., (Hurricane Protection) 
(LMN) 11-16, 11-24, 11-29 
Lake Providence Harbor, La. (LMK) 12-2, 12-13, 12-16 
Lake River, Wash. (NPP) 37-7, 37-27 
Lake River Delta Area, Wash. (NPP) 37-48, 37-52 
Lake Rousseau, Fla. (SAJ) 9-5 
Lake Sacajawea, Wash. (NPW) 39-5 
Lake Sakakawea, N. Dak, (MRO) 21-8, 21-11 
Lake Sharpe, S. Dak. (MRO) 21-7, 21-11 
Lake Shelbyville, Ill. (LMS) 14-14 
Lake Sidney Lanier, Ga. (SAM) 10-27, 10-36 
Lake St. Clair, Mich., Channels (NCE) 31-15, 31-42, 
31-61 
Lake Texoma, Tex. and Okla. (SWT) 19-14, 19-21 
Lake Thunderbird, Okla. (SWT) 19-13 
Lake Traverse, Minn. and S. Dak. (NCS) 27-23 
Lake Traverse and Boise De Sioux River, S. DAk. and 
Minn. (NCS) 27-10, 27-20 
Lake Umatilla, Oreg. and Wash. (NPP) 37-22, 37-31, 
31-41, 31-55 
Lake Wallula, Wash. (NPW) 39-8, 39-10 
Lake Washington Ship CAnal, Wash. (NPS) 38-4, 
38-14, 38-20, 38-30 
Lake Wichita, Tex. (SWT) 19-17 
Lakeport Lake, Calif. (SPK) 35-24 
Lakeshore Park, Ashtabula, Ohio (NCB) 31-12, 31-19 
Lakeview Lake, Tex. (SWF) 16-7, 16-17, 16-21 
Lakeview Park, Lorain, Ohio (NCB) 32-11, 32-19 
Lamoille River, Vt. (NAN) 2-33, 2-35 
Lamprey River, N.H. (NED) 1-51 
Lancaster, Mass. (NED) 1-29 
Lancaster, N.H. (NED) 1-55 
Lancaster, N.Y. (NCB) 32-34 
Langdon Park, Wilmette, Ill. (NCC) 30-6 
Langellier Drainage and Levee District, Ill. (NCC) 
28-19 
Langston Creek, S.C. (SAN) 7-15 
Lansing (Grand River), Mich. (NCE) 31-77 
Lansing Harbor, Iowa (NCD) 29-8 
Lapwai Creek, Culdesac, Idaho (NPW) 39-18 
Larchmont Harbor, N.Y. (NAN) 2-31 
Largo Sound Channel. Fla. (SAJ) 9-50 
Larned, Kans. (SWA) (SWT) 17-3, 17-10, 17-11, 19-27 
Larose to Golden Meadow, La. (Hurricane Protection) 
(LMN) 11-17, 11-24, 11-30 
Las Animas, Colo. (SWA) 17-12 
Las Cruces, N. Mex. (SWA) 17-12 
1-21

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Las Tunas Beach, Calif. (SPL) 33-22 
Las Vegas Wash Tributaries, Nev. (SPL) 33-24 
Latrobe, Pa. (ORP) 26-23, 26-27, 26-29 
Latta Brook Road, N.Y. (NAB) 4-14, 4-27, 4-35 
Laurel River Lake, Ohio River Basin, Ky. (ORN) 23-7, 
23-9, 23-18 
Lava Hot Springs, Idaho (NPW) 39-18 
Lavaca-Navidad River, Tex. (SWG) 15-11, 15-27 
Lavon Lake, Tex. (SWF) 16-8, 16-17, 16-21 
Lavon Lake Modification and East Fork Channel Improvement, 
Tex. (SWF) 16-8, 16-17, 16-21 
Lawrence, Kans. (MRK) 20-4, 20-12, 20-15, 20-23 
Lawrenceburg, Ind. (ORL) 24-21, 24-25, 24-30 
Lead Bayou, Miss. (LMK) 12-8, 12-14, 12-17 
Leading Creek, W. Va. (ORH) 25-19 
Leaf and Chickasawhay River, Miss. (SAM) 10-38 
Leavenworth, Ind. (ORL) 24-23, 24-26 
Lebanon Junction, Ky. (ORL) 24-21, 24-30 
Le Claire Lock (Canal), Iowa (NCD) 29-6 
Lee, Mass. (NED) 1-27, 1-55 
Lee County, Fla. (SAJ) 9-51 
Leech Lake Reservoir, Minn. (NCS) 27-26 
Leesville, Va., Roanoke River, Sec. 32, Demo. Project 
(SAW) 6-14, 6-21 
Leetonia, Ohio (ORP) 26-23 
Leetsdale, Pa. (ORP) 26-23, 26-27 
Lehigh River at Allentown, Pa. (NAP) 3-14 
Lehigh River at Bethlehem, Pa. (NAP) 3-14, 3-27 
Leipsic River, Del. (NAP) 3-24 
Leith Creek, S.C. (SAN) 7-16 
Leland Bowman Lock, La. (formerly Vermilion Lock) 
(LMN) 11-10, 11-22, 11-28 
Leland Harbor, Mich. (NCE) 31-15, 31-42, 31-61 
Lemon Creek, N.Y. (NAN) 2-31 
Les Cheneaux Islands, Channels, Mich. (NCE) 31-74, 
31-75 
Letart, W. Va. (ORH) 25-20 
Levee Districts between Carlyle and New Athens, Ill. 
(LMS) 14-14 
Levee Districts between Cowden and Vandalia, Ill. 
(LMS) 14-14 
Levee Unit No. 1, Ill1. (ORL) 24-22 
Levee Unit No. 5, Ind. (ORL) 24-3, 24-15, 24-30 
Levee Unit No. 8, Ind. (ORL) 24-21, 24-30 
Levee (LMK) (LMS) (MR+T) (ORL) 424, 42-9, 42-23, 
42-28, 42-44, 42-46, 42-47, 42-49, 42-54, 42-55, 42-57, 
14-14, 24-23, 24-26 
Levisa and Tug Forks of the Big Sandy River and 
Cumberland River, W. Va., Va., and Ky. (ORH) 25-5, 
25-12, 25-26 
Lewes, Del. (NAP) 3-11 
Lewis and Clark Lake, Nebr. and S. Dak. (MRO) 21-8, 
21-12, 21-19 
Lewis and Clark River Area, Oreg. (NPP) 37-44 
Lewis River, Wash. (NPP) 37-43 
Lewis River Area, Wash. (NPP) 37-48, 37-52 
Lewisport, Ky. (ORL) 24-22, 24-25 
Lewiston-Clarkston Bridge, Idaho and Wash. (NPW) 
39-6, 39-11, 39-15 
Lewisville Dam, Tex. (SWF) 16-9, 16-17, 16-21 
Lexington Harbor, Mich. (NCE) 31-15, 31-43, 31-61 
Libby Dam-Lake Koocanusa, Mont. (NAS) 38-11, 
38-16, 38-22 
Liberty Local Protection Project, Tex. (SWG) 15-27 
Liberty State Park Levee and Seawall, N.J. (NAN) 
(NAP) 2-15, 2-22, 2-28 
Lick Run, Roanoke, Va. (SAW) 6-28 
Lickling River, Ky. (ORL) 24-20 
Lido Key, Fla. (SAJ) 9-51 
Lighthouse Point Park, Conn. (NED) 1-54 
Lincoln, N.H. (NED) 1-29 
Lincoln, Nebr. (MRO) 21-21 
Lincoln Lake, Ind. (ORL) 24-23 
Linton, N. Dak. (MRO) 21-16 
Lisle, N.Y. (NAB) 4-18, 4-28 
Little Bay, Tex. (SWG) 15-27 
Little Bay De Noc, Gladstone Harbor, Mich. (NCE) 
31-75 
Little Blue River Channel Improvement, Mo. (MRK) 
20-5, 20-12, 20-16 
Little Blue River Lakes, Mo. (MRK) 20-5, 20-12, 20-16 
Little Caillou Bayou, La. (LMN) 11-34 
Little Calumet River, Ill. (NCC) 30-7, 30-10, 30-16 
Little Chute Combined Lock, Wis. (NCE) 31-73 
Little Chute Dam, Wis. (NCE) 31-73 
Little Chute First (Guard) Lock, Wis. (NCE) 31-73 
Little Chute Second Lock, Wis. (NCE) 31-73 
Little Cove Creek, Glencoe, Ala. (SAM) 10-39 
Little Creek, Kent Island, Md. (NAB) 4-36, 4-40 
Little Creek, Va. (NAO) 5-11 
Little Cypress Bayou Levee, Tex. (SWG) 5-11 
Little Egg Harbor, N.J. (NAP) 3-24 
Little Goose Lock and Dam-Lake Bryan, Wash. (NPW) 
39-6, 39-11, 39-15, 39-23, 39-26 
Little Harbor, N.H. (NED) 1-51 
Little Harbor, Woods Hole, Mass. (NED) 1-51 
Little Kanawha River, W. Va. (ORH) 25-18 
Little Lake Harbor, Mich. (NCE) 31-16, 31-43, 31-61 
Little Machipongo River, Va. (NAO) 5-25, 5-27 
Little Manatee River, Fla. (SAJ) 9-50 
Little Missouri River, Ark. (LMK) 12-21, 12-22 
Little Neck Bay, N.Y. (NAN) 2-31 
Little Nemaha River, Nebr. (MRO) 21-16 
Little Papillion, Nebr. (MRO) 21-16, 21-21 
Little Pee Dee and Pee Dee Rivers, N.C. and S.C. 
(SAN) 7-17 
Little River, Del. (NAP) 3-24 
Little River, La. (LMK) 12-21 
Little River at Cayuga Island, N.Y. (NCB) 32-32 
Little River Basin (Little Rock District) (SWL) 18-4, 
18-10, 18-22 
Little River (Creek), Va. (NAO) 5-53 
Little River Diversion Channel, Mo. (MR +T) 42-20 
Little River Inlet, N.C. and S.C. (SAN) 7-5, 7-9, 7-13 
Little River Project Levees (MR +T) 42-48 
Little River Levee, Ark. (East End Fourche Bayou) 
(SWL)18-14, 18-16 
Little Rockfish Cree, Hope Mills, N.C. (SAW) 6-28 
Little Sioux River and Tributaries, Iowa (MRO) 21-4, 
21-10, 21-13 
Little Sodus Bay Harbor, N.Y. (NCB) 32-11, 32-32 
Little Sugar Creek, Charlotte, N.C. (SAW) 6-28 
1-22

INDEX 
Little Tallahatchie River, Miss. (LMK) 12-21 
Little Tennessee River, Tenn. (ORN) 23-13 
Little Valley Wash, Magna, Utah (SPK) 35-26 
Little Wicomico River, Va. (NAB) 4-5, 4-24, 4-31 
Little Wood River, Idaho (NPW) 39-19, 39-20 
Littleville Lake, Mass. (NED) 1-17, 1-36, 1-60 
Liverpool Drainage and Levee District, Ill. (NCR) 
28-16, 28-19 
Lock and Dam No. 1, Minn. (NCD) 29-6, 29-10 
Lock and Dam No. 2, Allegheny River, Pa. (ORP) 26-25 
Lock and Dam No. 2, Ark. (SWL) 18-2, 18-18 
Lock and Dam No. 2, Minn. (NCD) 29-6 
Lock and Dam No. 2, Monogahela River, Pa. (ORP) 
26-26 
Lock and Dam No. 3, Allegheny River, Pa. (ORP) 26-25 
Lock and Dam No. 3, Ark. (SWL) 18-3, 18-18 
Lock and Dam No. 3, Minn. (NCD) 29-6 
Lock and Dam No. 3, Monongahela River, Pa. (ORP) 
26-26 
Lock and Dam No. 4, Allegheny River, Pa. (ORP) 26-25 
Lock and Dam No. 4, Ark. (SWL) 18-3, 18-18 
Lock and Dam No. 4, Monongahela River, Pa. (ORP) 
26-26 
Lock and Dam No. 4, Wis. (NCD) 29-6 
Lock and Dam No. 5, Allegheny River, Pa. (ORP) 26-25 
Lock and Dam No. 5, Ark. (SWL) 18-3, 18-18 
Lock and Dam No. 5, Minn. (NCD) 29-6 
Lock and Dam No. 5A, Minn. (NCD) 29-6 
Lock and Dam No. 6, Allegheny River, Pa. (ORP) 26-25 
Lock and Dam No. 6, Wis. (NCD) 29-6 
Lock and Dam No. 7, Allegheny River, Pa. (ORP) 26-25 
Lock and Dam No. 7, Minn. (NCD) 29-6 
Lock and Dam No. 7, Monongahela River, Pa. (ORP) 
26-26 
Lock and Dam No. 8, Allegheny River, Pa. (ORP) 26-25 
Lock and Dam No. 8, Monongahela River, Pa. (ORP) 
26-26 
Lock and Dam No. 8, Wis. (NCD) 29-6 
Lock and Dam No. 9, Allegheny River, Pa. (ORP) 26-25 
Lock and Dam No. 9, Ark. (SWL) 18-3, 18-18 
Lock and Dam No. 9, Wis. (NCD) 29-6 
Lock and Dam No. 10, Iowa (NCD) 29-6 
Lock and Dam No. 11, Ark. (SWL) 18-19 
Lock and Dam No. 11, Iowa (NCD) 29-6 
Lock and Dam No. 12, Iowa (NCD) 29-6 
Lock and Dam No. 13, Ark. (SWL) 18-3, 18-18 
Lock and Dam No. 13, Iowa (NCD) 29-6 
Lock and Dam No. 14, Iowa (NCD) 29-6 
Lock and Dam No. 15, Ill. (NCD) 29-7 
Lock and Dam No. 16, Iowa (NCD) 29-7 
Lock and Dam No. 17, Ill. (NCD) 29-7 
Lock and Dam No. 18, Iowa (NCD) 29-7 
Lock and Dam No. 19, Iowa (NCD) 29-7 
Lock and Dam No. 20, Mo. (NCD) 29-7 
Lock and Dam No. 21, Ill. (NCD) 29-7 
Lock and Dam No. 22, Mo. (NCD) 29-7 
Lock and Dam No. 24, Mo. (NCD) 29-7 
Lock and Dam No. 25, Mo. (NCD) 29-7 
Lock and Dam No. 26, Ill. (NCD) 29-7 
Lock and Dam No. 52, Ill. (NCD) 22-9 
Lock and Dam No. 53, Ill. (ORD) 22-10 
Lock and Dam No. 54, Ill. (ORD) 22-10 
Lock S-53, Fla. (SAJ) 9-52 
Lock S-55, Fla. (SAJ) 9-52 
Lock S-57, Fla. (SAJ) 9-52 
Lock S-58, Fla. (SAJ) 9-52 
Lock S-59, Fla. (SAJ) 9-52 
Lock S-60, Fla. (SAJ) 9-52 
Lock S-61, Fla. (SAJ) 9-52 
Lock S-62, Fla. (SAJ) 9-52 
Lock S-63, Fla. (SAJ) 9-52 
Lock S-63A, Fla. (SAJ) 9-52 
Lock S-65, Fla. (SAJ) 9-52 
Lock S-65A, Fla. (SAJ) 9-52 
Lock S-65B, Fla. (SAJ) 9-52 
Lock S-65C, Fla. (SAJ) 9-52 
Lock S-65D, Fla. (SAJ) 9-52 
Lock S-65E, Fla. (SAJ) 9-52 
Lock S-96, Fla. (SAJ) 9-52 
Lock S-96A, Fla. (SAJ) 9-52 
Lock S-157, Fla. (SAJ) 9-52 
Lock S-158, Fla. (SAJ) 9-52 
Lock S-193, Fla. (SAJ) 9-52 
Lock S-308B, Fla. (SAJ) 9-52 
Lock S-310, Fla. (SAJ) 9-52 
Lock Haven, Pa. (NAB) 4-38 
Locklies Creek, Va. (NAO) 5-25 
Lockport Lock and Dam, Ill. (NCC) 28-22, 28-23 
Locks in Pearl River Project, La. (LMK) 12-20 
Lockwoods Folly River, N.C. (SAW) 6-5, 6-19 
Logan, Ohio (ORH) 25-19 
Logan Creek, Bank Protection, near Bancroft, Nebr. 
(MRO) 21-21 
Lone Rock, Ark. (SWL) 18-17 
Long Beach Island, N.J. (NAP) 3-26 
Long Branch Lake, Mo. (MRK) 20-5, 20-12, 20-16 
Long Island Intracoastal Waterway, N.Y. (NAN) 2-5, 
2-20, 2-25, 2-30 
Long Island Sound, N.Y. (NAN) 2-35 
Long Lake Area, Helena, Ark. (LMM) 13-4, 13-6, 13-8 
Long Tom River, Oreg. (NPP) 37-43 
Longboat Pass, Fla. (SAJ) 9-9, 9-30, 9-37, 9-49 
Lookout Point Lake, Oreg. (NPP) 37-23, 37-31, 37-41, 
37-52, 37-53 
Lopez Canyon Diversion, Los Angeles River Basin, 
Calif. (SPL) 33-25 
Lopez Dam, Los Angeles River Basin, Calif. (SPL) 33-25 
Lorain Harbor, Ohio (NCB) 32-7, 32-18, 32-28 
Los Angeles and Long Beach Harbors, Calif. (SPL) 
33-2, 33-12, 33-16 
Los Angeles County Drainage Area, Calif. (SPL) 33-7, 
33-9, 33-14, 33-18, 33-25 
Lso Coches Creek, Calif. (SPL) 33-27 
Lost Creek, Columbus, Nebr. (MRO) 21-4, 21-10, 21-13 
Lost Creek Drainage and Levee District, ill. (NCR) 
28-16, 28-19 
Lost Creek Lake, Oreg. (NPP) 37-23, 37-31, 3741, 37-52 
Lost River, Minn. (NCS) 27-24, 27-28 
Louisville, Ky. (ORL) 24-21, 24-25, 24-28 
Louisville Lake, Ill. (ORL) 24-9, 24-16, 24-29 
Loup River, Columbus, Nebr. (MRO) 21-16 
Lowell, Mass. (NED) 1-29, 1-55 
1-23

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Lowell, N.H. (NED) 1-63 
Lowell Creek, Alaska (NPA) 40-6, 40-13 
Lower Arkansas River, Ark. (MR+T) 42-17, 42-28, 
42-54, 42-57 
Lower Arkansas River Basin, Ark. (MR+T) 42-7 
Lower Big Sioux River, Iowa and S. Dak. (MRO) 21-16 
Lower Branch Rush River, N. Dak. (NCS) 27-24, 27-28 
Lower Columbia River Basin, Oreg. and Wash. (NPP) 
37-16, 37-39, 37-52 
Lower Columbia River Basin Bank Protection, Oreg. 
and Wash. (NPP) 37-17, 37-30, 37-40 
Lower Cowlitz River, Wash. (NPP) 37-44 
Lower Dry Creek, Lowden, Wash. (NPW) 39-18, 39-21 
Lower Gila River Levee and Channel Improvements 
(Gila River and Tributaries) Downstream from 
Painted Rock Dam, Ariz. (SPL) 33-23 
Lower Grand River, Mo. (MRK) 20-19 
Lower Granite Lock and Dam, Wash. (NPW) 39-7, 
39-12, 29-15, 39-23, 39-26 
Lower Guyandotte River Basin, W. Va. (ORH) 25-19 
Lower Heart River, N. Dak. (MRO) 21-16 
Lower Machodoc Creek, Va. (NAB) 4-36, 4-41 
Lower Monumental Lock and Dam, Wash. (NPW) 39-7, 
39-12, 39-15, 39-24, 39-26 
Lower Red River-South Bank, Red River Levees, La. 
(MR+T) 42-9, 42-16, 42-28, 42-46, 42-49, 42-58 
Lower Red River Standard Revetments (MR+T) 42-33, 
42-37 
Lower San Francisco Bay, Calif. (SPN) 34-10 
Lower San Joaquin River and Tributaries, including 
Tuolumne and Stanislaus Rivers, Calif. (SPK) 35-19, 
35-24 
Lower Snake River, Wash., Oreg., Idaho, Fish and 
Wildlife Compensation (NPW) 39-8, 39-12, 39-15 
Lower Thorofare, Deal Island, Md. (NAB) 4-36 
Lower Walla Walla River, Wash. (NPW) 39-18, 39-20 
Lower White River and Basin, Ark. (MR+T) 42-10, 
42-18, 42-53 
Lower White River Levees (MR+T) 42-10, 42-48, 
42-53 
Lower Woonsocket, R.I. (NED) 1-55, 1-59 
Lowes Wharf, Md. (NAB) 4-5, 4-24, 4-31 
Loyalhanna Lake, Pa. (ORP) 26-7, 26-15, 26-20 
Loyalsock, Pa. (NAB) 4-41 
Lubec, Maine (NED) 1-29 
Lubec Channel, Maine (NED) 1-51 
Lucky Peak Lake, Idaho (NPW) 39-2, 39-11, 39-14 
Ludington Harbor, Mich. (NCE) 31-16, 31-43, 31-61 
Ludlow, Ky. (ORL) 24-23, 24-26 
Ludlow Lake, Vt. (NED) 1-57 
Lukfata Lake, Okla. and Ark. (SWT) 19-9, 19-19, 19-26 
Lumber River, N.C. and S.C. (SAN) 7-17 
Lutsen Harbor, Minn. (NCE) 31-75 
Lyford Levee, Ind. (ORL) 24-21, 24-30 
Lyman, Idaho (NPW) 39-21 
Lyman Creek, Idaho (NPW) 39-18, 39-21 
Lynches River and Creek, S.C. (SAN) 7-15 
Lynn Harbor, Mass. (NED) 1-51 
Lynn-Nahant Beack, Mass. (NED) 1-54 
Lynnhsven Inlet, Va. (NAO) 5-6, 5-16, 5-21, 5-27 
Lytle and Warm Creeks, Calif. (SPL) 33-23 
M 
Maalaea Small Boat Harbor, Hawaii (POD) 36-14 
Macdowell, Edward, Lake, N.H. (NED) 1-24, 1-38, 1-63 
Manchias River, Maine (NED) 1-51 
Mackay Creek, N.C. (SAW) 6-26, 6-29 
Mackinac Island Harbor, Mich. (NCE) 31-75 
Mackinaw City Harbor, Mich. (NCE) 31-74, 31-75 
Macon, Ga. (SAS) 8-16 
Macy, Nebr. (MRO) 21-21 
Mad Creek, Muscatine, Iowa (NCR) 28-19 
Mad River, Conn. (NED) 1-29, 1-60 
Mad River Basin, Calif. (SPK) 35-24 
Mad River Lake, Conn. (NED) 1-55 
Madison, Ind. (ORL) 24-23, 24-26, 24-31 
Madison, Nebr. (MRO) 21-16, 21-21 
Madison Bay, Md. (NAB) 4-36, 4-40 
Madison Parish Port, La. (LMK) 12-2, 12-13, 12-16 
Magruder Drainage District, Oreg. (NPP) 37-44, 37-48, 
37-52 
Mahoning Creek Lake, Pa. (ORP) 26-8, 26-15, 26-20 
Maiden Creek Reservoir, Pa. (NAP) 3-26 
Maintenance and Repair Fleet and Marine Terminals, 
Ark. (SWL) 18-3, 18-20 
Maintenance and Repair Fleet and Marine Terminals, 
Okla. (SWT) 19-3, 19-18, 19-22 
Malden River, Mass. (NED) 1-51 
Malheur Improvement District, Oreg. (NPW) 39-18, 
39-21 
Malheur River, Idaho (NPW) 39-19 
Malheur River, Oreg. (NPW) 39-18, 39-20 
Mamaroneck Harbor, N.Y. (NAN) 2-31 
Manasquan River, N.J. (NAP) 3-7, 3-18, 3-23 
Manatee County, Fla. (SAJ) 9-22, 9-33, 9-44 
Manatee River, Fla. (SAJ) 9-49, 9-50 
Manchester, Ohio (ORH) 25-20 
Manchester Harbor, Mass. (NED) 1-57 
Mandan, N. Dak. (MRO) 21-16, 21-20 
Manele Small Boat Harbor, Hawaii (POD) 36-14, 36-16 
Manhasset Bay, N.Y. (NAN) 2-31 
Manhattan, Kans. (MRK) 20-19, 20-23 
Maniece Bayou, Ark. (LMN) (LMK) 11-36, 12-26 
Manistee Harbor, Mich. (NCE) 31-17, 31-43, 31-61 
Manistique Harbor, Mich (NCE) 31-17, 31-43, 31-62 
Manitowoc Harbor, Wis. (NCE) 31-17, 31-44, 31-62 
Mankato and North Mankato, Minn. (NCS) 27-10, 
27-20, 27-28 
Mann's Harbor, N.C. (SAW) 6-29 
Manokin River, Md. (NAB) 4-36, 4-40 
Mansfield Hollow Lake, Conn. (NED) 1-28, 1-40, 1-64 
Manteo (Shallowbag) Bay, N.C. (SAW) 6-5, 6-19 
Mantua Creek, N.J. (NAP) 3-24 
Maple River, N. Dak. (NCS) 27-25 
Mapleshade, Ohio (ORH) 25-20 
Marblehead Harbor, Mass. (NED) 1-57 
Marengo, Iowa (NCR) 28-16, 28-19 
Marietta, Ohio (ORH) 25-20 
Marina Del Rey, Calif. (SPL) 33-21, 33-25 
Marion, Ind. (ORL) 24-22, 24-29 
Marion, Kans. (SWT) 19-10, 19-20, 19-23 
1-24

INDEX 
Marion County Drainage District, Mo. (NCR) 28-16, 
28-19 
Marion Diversion Channel and Levee, Kans. (SWT) 
19-27 
Marion Lake, Kans. (SWT) 19-10, 19-20 
Markham Feery Lake, Okla. (SWL) 18-21 
Markham Ferry Reservoir, Okla. (SWT) 19-15, 19-25 
Markland Locks and Dam, Ind. (ORD) 22-3, 22-9 
Marmarth, N. Dak. (MRO) 21-16, 21-20 
Marquette Harbor, Mich. (NCE) 31-18, 31-44, 31-62 
Marseilles Lock and Dam, Ill. (NCC) 28-22 
Marsh Creek, Geneva, N.Y. (NCB) 32-34 
Marsh River, Minn. (NCS) 27-28 
Marshall, Minn. (NCS) 27-24, 27-28 
Marshalltown, Iowa (NCR) 28-16, 28-19 
Marshland Drainage District, Oreg. (NPP) 37-44 
Martin, John, Reservoir, Colo. (SWA) 17-3, 17-9 
Martin, Ky. (ORH) 25-6, 25-12, 25-16 
Martins Ferry, Ohio (ORP) 26-23, 26-27 
Martins Fork Lake, Ky. (ORN) 23-5, 23-9, 23-18 
Martis Creek Lake, Martis Cree, Nev. and Calif. 
(SPK) 35-9, 35-19 
Marysville, Kans. (MRK) 20-20 
Marysville Lake, Calif. (SPK) 35-24 
Mason, W. Va. (ORH) 25-20 
Mason and Menard Drainage District, Ill. (NCR) 
28-16, 28-19 
Mason J. Niblack Levee, Ind. (ORL) 24-4, 24-15, 24-21, 
24-25, 34-30 
Massillon, Ohio (ORH) 25-6, 25-12, 25-16 
Matafao Shoreline, American Samoa (POD) 36-4, 36-11 
Matagorda Ship Channel, Tex. (SWG) 15-6, 15-14, 
15-22, 15-30, 15-34 
Matawan Creek, N.J. (NAN) 2-30, 2-31 
Matinicus Harbor, Maine (NED) 1-51 
Mats Mats Bay, Wash. (NPS) 38-24 
Mattapoisett Harbor, Mass. (NED) 1-57 
Mattituck Beach, South Kingston, R.I. (NED) 1-54 
Mauckport, Ind. (ORL) 24-23, 24-26 
Maumee River, above Toledo, Ohio (NCB) 32-32, 32-36 
Maunalua Bay Small Boat Harbor, Hawaii (POD) 36-14 
Maurice River, N.J. (NAP) 3-24, 3-27 
Maxwell Locks and Dam. Pa. (ORP) 26-26 
Mayaguez Harbor, P.R. (SAJ) 9-9, 9-30, 9-37 
Mayo, W.D., Lock and Dam, Okla. (SWL) (SWT) 18-19, 
19-25 
Mayse, Pat, Lake, Tex. (SWT) 19-10, 19-20 
Maysville, Ky. (ORH) 25-19, 25-21 
McAlpine Locks and Dam (ORD) 22-3, 22-9 
McCook Lake, S. Dak. (MRO) 21-17 
McGee Creek Drainage and Levee District, Ill. (LMS) 
14-5, 14-9, 14-12 
McGinnis Levee, Ind. (ORL) 24-23, 24-26 
McKees Rocks, Pa. (ORP) 26-24 
McKenzie River near Walterville, Oreg. (NPP) 37-46 
McKinney Bayou, Ark, and Tex. (LMN) 11-17, 11-24, 
11-30 
McKinney Bayou, Finn Bayou Segment, Ark. (LMN) 
(LMK) 11-36, 12-25 
McLean Bottom Levee District No. 3, Arkansas River 
Ark. (SWL) 18-16 
McNary Lock and Dam-Lake Wallula-Oreg. and Wash. 
(NPW) 39-8, 39-10, 39-12, 39-16, 39-25 
Meadow Grove, Nebr. (MRO) 21-21 
Medomak River, Maine (NED) 1-51 
Meherrin River, N.C. (NAO) 5-25 
Melbourne Harbor, Fla. (SAJ) 9-49, 9-50 
Meldahl, Captain Anthony, Locks and Dam, Ky. 
(ORD) 22-1, 22-8 
Melton Hill Lock and Dam, Tenn. (ORN) 23-17 
Melvern Lake, Kans. (MRK) 20-6, 20-12, 20-16, 20-23 
Melvern Lake and Pomona Lake (Road Improvement), 
Kans. (MRK) 20-23 
Memphis Harbor, Tenn. (MR+T) 42-29 
Memphis, Wolf River, and Nonconnah Creek, Tenn. 
(LMM) 13-10 
mensha Lock and Dam (NCE) 31-73 
Menemsha Creek, Martha's Vineyard, Mass. (NED)1-51 
Menominee Harbor and River, Mich. and Wis. (NCE) 
31-18, 3144, 31-62 
Meramec Park Lake, Mo. (LMS) 14-4, 14-11, 14-13 
Merced County Stream Group, Calif. (SPK) 35-9, 
35-19, 35-27 
Merced County Streams, Calif. (SPK) 35-17, 35-21 
Merced River, Calif. (SPK) 35-24 
Mercer Lake, Mo. (MRK) 20-19 
Meredosia, Ill., and Meredosia, Willow Creek, and 
Coon Run Drainage and Levee Districts, Ill. (LMS) 
14-5, 14-9, 14-12 
Meredosia Lake and Willow Creek Drainage and 
Levee District, Ill. (LMS) 14-5, 14-9, 14-12, 14-14 
Meredosia Levee and Drainage District, Ill. (NCR) 
28-16, 28-19 
Mermentau River, La. (LMN) 11-10, 11-22, 11-28 
Mermentau River, Bayou Nezique, and Bay Des 
Cannes, La. (LMN) 11-34 
Merom, Ind. (ORL) 24-31 
Merriam, Kans. (MRK) 20-20 
Merriconeag Sound, Harpswell, Maine (NED) 1-55 
Merrimack River, Mass. (NED) 1-51 
Merrimack River Basin, N.H and Mass. (NED) 1-24, 
1-29, 1-63 
Metamora Lake, Ind. (ORL) 24-23, 24-28 
Methow River, Wash. (NAS) 38-26, 38-27 
Metlakatla Harbor, Alaska (NPA) 40-4, 40-9, 40-11 
Metopolis, Ill. (ORL) 24-22, 24-25 
Miami Harbor, Fla. (SAJ) 9-9, 9-30, 9-38, 9-49 
Miami River, Oreg. (NPP) 37-46 
Mianus River, Conn. (NED) 1-51 
Michael J. Kirwan Dam and Reservoir, Ohio (ORP) 
26-8, 26-15, 26-20 
Michigan City Harbor, Ind. (NCC) 30-4, 30-9, 30-12, 
30-15, 30-16 
Middle Beach, Conn. (NED) 1-54 
Middle Creek, Calif. (SPK) 35-24 
Middle Gila River Channel Improvements, Upper End 
of Safford Valley to Buttes Damsite (Camelsback 
Damsite to Salt River), Ariz. (SPL) 33-23 
Middle River and Connecting Channels, Calif. (SPK) 
35-23 
Middle River and Dark Head Creek, Md. (NAB) 4-36, 
4-40 
1-25

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Middleport, Ohio (ORH) 25-20 
Middlesboro, Ky. (ORN) 23-5, 23-9 
Middlesboro, Ky. (Diversion Canal) (ORN) 23-19 
Middlesboro, Ky. (Yellow Creek) (ORN) 23-13, 23-18, 
23-19 
Middleton Shoals, Ga. and S.C. (SAS) 8-17 
Midland Drainage District, Oreg. (NPP) 37-44, 37-46, 
37-52 
Milan, ll. (NCR) 28-6, 28-11, 28-14 
Miles City, Mont. (MRO) 21-17 
Milford Harbor, Conn. (NED) 1-51 
Milford Haven, Va. (NAO) 5-25 
Mill Creek, Tex. (SWG) 15-27 
Mill Creek, Md. (NAB) 4-40 
Mill Creek, N.C. (SAW) 6-29 
Mill Creek, Ohio (ORL) (ORH) 24-4, 24-15, 24-20 
Mill Creek, Tex. (SWG) 15-27 
Mill Creek, Va. (NAO) 5-25 
Mill Creek, Wash. (NPW) 39-19, 39-20 
Mill Creek and South Slough at Milan, Ill. (NCR) 28-3, 
28-10, 28-13 
Mill Creek Lake, Wash. (NPW) 39-3, 39-11, 39-14 
Mill Four Drainage District, Oreg. (NPP) 37-46 
Mill Lake, Mo. (MRK) 20-19 
Miller, Ohio (ORH) 25-19 
Miller Pond Drainage District, Ill. (LMS) 14-14 
Millers Ferry Lock and Dam, Ala. (SAM) 10-17, 10-26 
Millersburg, Ohio (ORH) 25-20 
Millican Lake, Tex. (SWF) 16-9, 16-17, 16-21 
Millwood, W. Va. (ORH) 25-20 
Millwood Lake, Little River Basin, Ark, (SWL) 18-6, 
18-11, 18-22 
Milton, Ky. (ORL) 24-23, 24-26 
Milton, Pa. (NAB) 4-41 
Milton-Freewater, Oreg. (NPW) 39-18, 39-21 
Milton Harbor, N.Y. (NAN) 2-30, 2-31 
Milwaukee Harbor, Wis. (NCE) 31-19, 31-44, 31-63 
Mineral Creek, Wash. (NPS) 38-27 
Mines Creek, Wis. (NCS) 27-28 
Mingo Creek, S.C. (SAN) 7-15 
Mingo Junction, Ohio (ORP) 26-24 
Mining City Lake, Ky. (ORL) 24-22, 24-28 
Minneota, Minn. (NCS) 27-24, 27-28 
Minnesota River, Minn. (NCS) 27-2, 27-19, 27-22 
Minot, N. Dak. (NCS) 27-10, 27-20, 27-22 
Mispillion River, Del. (NAP) 3-16, 3-24 
Misquamicut Beach, Westerly, R.I. (NED) 1-54 
Mission and Lapwai Creeks, Idaho (NPW) 39-18 
Mission Creek, Idaho (NPW) 39-21 
Mississinewa Lake, Ind. (ORL) 24-10, 24-17 
Mississippi and Leech Rivers, Minn. (NCS) 27-23 
Mississippi Delta Region, La. (MR+T) 42-28 
Mississippi River Agricultural Area No. 8, Mo. (LMS) 
14-6, 14-9, 14-12 
Mississippi River Agricultural Area No. 10, Mo. (LMS) 
14-15 
Mississippi River Agricultural Area No. 12, Mo. (LMS) 
14-15 
Mississippi River Alluvial Valley Mapping (MR+T) 
42-3 
Mississippi River, Alton to Gale, Ill., Underseepage 
Measures (LMS) 14-15 
Mississippi River and Alluvial Valley below Cape 
Girardeau, Mo. (MR+T) 42-2 
Mississippi River and Tributaries (MR+T) 42-1 to 
42-60 
Mississippi River and Tributaries-Channel 
Improvements (MR+T) 42-5 
Mississippi and Leech Rivers, Minn. (NCS) 27-23 
Mississippi Delta Region, La. (MR+T) 42-28 
Mississippi River Agricultural Area No. 8, Mo. (LMS) 
14-6, 14-9, 14-12 
Mississippi River Agricultural Area No. 10, Mo. (LMS) 
14-15 
Mississippi River Agricultural Area No. 12, Mo. (LMS) 
14-15 
Mississippi River Alluvial Valley Mapping (MR+T) 
42-3 
Mississippi River, Alton to Gale, Ill., Underseepage 
Measures (LMS) 14-15 
Mississippi River and Alluvial Valley below Cape 
Girardeau, Mo. (MR+T) 42-2 
Mississippi River and Tributaries (MR+T) 42-1 to 
42-60 
Mississippi River and Tributaries-Channel 
Improvements (MR+T) 42-5 
Mississippi River and Tributaries-Levees (MR +T)42-4 
Mississippi River at Alton, Ill. (LMS) 14-13 
Mississippi River at St. Louis, Mo. (LMS) 14-15 
Mississippi River Bank Revetments and Dikes 
(MR+T) 42-30, 42-34, 42-39 
Mississippi River, Baton Rouge to Gulf of Mexico, La. 
(LMN) 11-11, 11-22, 11-28 
Mississippi River between Brainerd and Grand Rapids, 
Minn. (NCS) 27-23 
Mississippi River between Missouri River and Minneapolis, 
Minn. (NCD) (NCS) 27-2, 29-1, 29-5, 29-11 
Mississippi River between Ohio and Missouri 
Rivers, Mo. and Ill. (LMS) 14-2, 14-9, 14-11 
Mississippi River Channel Improvements (MR+T) 
42-50, 42-51, 42-52 
Mississippi River Commission (MR+T) 42-1 
Mississippi River Delta at and below New Orleans, 
La. (New Orleans to Venice, La., Hurricane Protection) 
(LMN) 11-18, 11-24, 11-30 
Mississippi River Delta Region, La. (MR+T) 42-58 
Mississippi River-Gulf Outlet, La. (LMN) 11-13, 11-22, 
11-29 
Mississippi River-Gulf Outlet, Michoud Canal, La. 
(LMN) 11-34 
Mississippi River Headwater Reservoirs, Minn. (NCS) 
27-2, 27-19, 27-22 
Mississippi River Improvements (MR+T) 42-12 
Mississippi River Levees (MR+T) 42-28, 42-44, 4246, 
42-47 
Mississippi River Main Stem Channel Improvements 
(MR+T) 42-29 
Mississippi River near Aitkin, Minn. (NCS) 27-24 
Mississippi River Outlets, Venice, La. (LMN) 11-13, 
11-22, 11-29 
Mississippi River Tributary and Outlet Improvements 
(MR+T) 42-14 
1-26

INDEX 
Mississippi River Tributary Dams and Lakes (MR+T) 
42-21 
Mississquoi River at Richford, Vt. (NP 2-33, 2-36 
Missouri National Recreational River, Nebr. and S. 
Dak. (MRO) 21-5, 21-10, 21-13 
Missouri River, Mo. (MR+T) 42-20 
Missouri River at New Haven, Mo. (MRK) 20-19 
Missouri River, Aten, Nebr. (MRO) 21-17 
Missouri River, Bank Protection, Greenwood, S.Dak. 
(MRO) 21-20 
Missouri River, Bank Stabilization, Fort Benton, 
Mont. (MRO) 21-20 
Missouri River, Garrison Dam to Lake Oahe, N. Dak. 
(MRO) 21-5, 21-10, 21-13 
Missouri River, Kenslers, Bend, Nebr. to Sioux City, 
Iowa (MRO) 21-5, 21-11, 21-13 
Missouri River Levee System, Iowa, Nebr., Kans., and 
Mo. (Rulo, Nebr. to Mouth) (MRK) 20-6, 20-12, 
20-16, 20-22, 20-23 
Missouri River Levee System, Iowa, Nebr., Kans., and 
Mo. (Sioux City, Iowa, to Rulo, Nebr.) (MRO) 21-5, 
21-11, 21-13, 21-18, 21-22 
Missouri River Main Stem (MRK) 20-24 
Missouri River, Marina, Sioux City, Iowa (MRO) 21-21 
Missouri River, Niobrara, Nebr. (MRO) 21-17 
Missouri River, Sioux City, Iowa, to Fort Benton, 
Mont. (MRO) 21-16 
Missouri River, Sioux City, Iowa, to Mouth (Rulo, 
Nebr., to Mouth) (MRK) 20-2, 20-11, 20-14, 20-20 
Missouri River, Sioux City, Iowa, to Mouth, Terminal 
Facilities (MRK) 20-21 
Missouri River, Sioux City, Iowa, to Rulo, Nebr. 
(MRO) 21-2, 21-12, 21-18 
Missouri River, Sioux City, Iowa, to Rulo, Nebr. 
Terminal Facilities (MRO) 21-19 
Mobile Bay, Ala. to New Orleans, La. (SAM) 10-31 
Mobile Harbor, Ala. (SAM) 10-8, 10-24, 10-32 
Mocassin Swamp, N.C. (SAW) 6-29 
Moccasin Springs, Mo. (LMS) 14-13 
Moclips River, Wash. (NPS) 38-27 
Mojave River Dam, Calif. (SPL) 33-8, 33-14, 33-19 
Mokelumne River, Calif. (SPK) 35-23 
Molalla River at Milk Creek location, Oreg. (NPP) 
37-46 
Molalla River at Ressel location, Oreg. (NPP) 37-47 
Moline, Ill. (NCR) 28-6, 28-11, 28-14 
Moline Harbor, Ill. (NCD) 29-8 
Monongahela River, Pa. and W. Va. Locks and Dams 
(ORP) 26-2, 26-14, 26-18, 26-26, 26-27 
Monoosnoc Brook, Mass. (NED) 1-55, 1-63 
Monoosnoc Lake, Mass. (NED) 1-55, 1-63 
Monroe, La., floodwall extension (LMK) 12-22 
Monroe Bay and Creek, Va. (NAB) 4-36 
Monroe County, Iowa, Highway Bridges (NCR) 28-6, 
28-11, 28-14 
Monroe Floodwall, La. (LMK) 12-8, 12-14, 12-18 
Monroe Harbor, Mich. (NCE) 31-20, 31-45, 31-63 
Monroe Lake, Ind. (ORL) 24-10, 24-17, 24-28 
Montcalm, W. Va. (ORH) 25-21 
Monterey Harbor, Calif. (SPN) 34-10 
Montgomery Locks and Dam, Pa. (ORD) 22-2, 22-7 
Montour Falls, N.Y. (NCB) 32-34 
Moore Haven Lock, Fla. (SAJ) 9-52 
Moorefield, W. Va. (NAB) 4-40 
Moores Ferry, Va. (ORH) 25-19 
Moorhead, Minn. (NCS) 27-25 
Mooring for Battleship Oregon, Oreg. (NPP) 37-43 
Moosabec Bar, Maine (NED) 1-51 
Morehead, Ky. (ORL) 24-31 
Morehead City Harbor, N.C. (SAW) 6-6, 6-19 
Morgan City and Vicinity, La. (LMN) 11-18, 11-24, 
11-30 
Morgantown Lock and Dam, W. Va. (ORP) 26-26 
Morganza Floodway, La. (MR+T) 42-50 
Moriches Inlet, N.Y. (NAN) 2-5, 2-21, 2-25 
Mormon Slough, Calif. (SPK) 35-24 
Morrison, Colo. (MRO) 21-17 
Morrison Creek Stream Group, Calif. (SPK) 35-15 
Morristown Harbor, N.Y. (NCB) 32-32 
Morro Bay Harbor, Calif. (SPL) 33-21, 33-25 
Moscow, Ohio (ORL) 24-23, 24-26 
Mosquito Creek Lake, Ohio River Basin, Ohio (ORP) 
26-9, 26-15, 26-20 
Moss Bluff Lock, Fla. (SAJ) 9-56 
Moss Landing Harbor, Calif. (SPN) 34-6 
Mott, N. Dak. (MRO) 21-17 
Mound City Locks and Dam, Ill. (ORD) 22-1, 22-10 
Mounds and Mound City, Ill. (LMM) 13-10 
Moundsville, W. Va. (ORP) 26-23, 26-27 
Mount Clemens, Clinton River, Mich. (NCE) 31-76 
Mount St. Helens and Vicinity, Wash. (NPP) 37-17, 
37-30, 37-40 
Mountain Brook Dam, N.H. (NED) 1-57 
Mountain Park (Tom Steed Lake), Okla. (SWT) 19-13 
Mouth of Yazoo River, Miss. (LMK) 12-21 
Moyock Creek, N.C. (SAW) 6-29 
Mt. Baldy, Indiana Dunes National Lakeshore, Ind. 
(NBC) 30-6, 30-10, 30-13 
Mt. Carmel, Ill. (ORL) 24-21, 24-30 
Mt. Holly, N.J. (NAP) 3-26 
Mt. Morris Lake, N.Y. (MCB) 32-14, 32-20 
Mud and Basket Slough, Rickreall Creek, Oreg. (NPP) 
37-48 
Mud Creek, Broken Bow, Nebr. (MRO) 21-17, 21-21 
Mud Creek Channel Improvement, Okla. (SWT) 19-24 
Mud Lake, Idaho (NPW) 39-18, 39-20 
Mud Lake Pumping Station, Tenn. (MR+T) 42-28 
Mud Mountain Dam, Wash. (NAS) 38-8, 38-15, 38-21 
Mud River, W. Va. (ORH) 25-20 
Muddy Creek Dam, Pa. (ORP) 26-23 
Muddy Hook and Tyler Coves, Md. (NAB) 4-5, 4-24, 
4-31 
Mulberry Creek, Va. (NAO) 5-25 
Mullet Key, Fla. (SAJ) 9-51 
Multnomah Channel, Oreg. (NPP) 37-43 
Multnomah Drainage District 1, Oreg. (NPP) 3744, 
37-46, 37-52 
Muncie, Ind. (ORL) 24-21, 24-30 
Munday Floodway, Tex. (SWF) 16-23 
Murder and Burnt Corn Creeks, Brewton, Ala. (SAM) 
10-39 
Murder Creek, East Brewton, Ala. (SAM) 10-13, 10-26, 
1-27

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
10-35 
Murderkill River, Del. (NAP) 3-8, 3-16, 3-18 
Murfreesboro Dam and Lake (LMK) 12-25 
Murray Lock & Dam, Ark. (SWL) 18-3, 18-18 
Murrells Inlet, S.C. (SAN) 7-5, 7-10, 7-13 
Muscatatuck River, Crothersville, Ind. (ORL) 24-31 
Muscatine, Iowa (NCR) 28-6, 28-11, 28-15 
Muscatine, Iowa (Mad Creek) (NCR) 28-16 
Muscatine Harbor, Iowa (NCD) 29-9 
Muscatine Island L. and D.D., Louisa D.D. No. 13, 
Iowa (NCR) 28-16, 28-19 
Muskegon Harbor, Mich. (NCE) 31-20, 3145, 31-63 
Muskingum River, Ohio (ORH) 25-18 
Muskingum River Lakes, Ohio (ORH) 25-6, 25-13, 
25-16 
Mustinka River, Minn. (NCS) 27-27, 27-28 
Myers Chuck Harbor, Alaska (NPA) 40-12 
Myrtle Beach, S.C. (SAN) 7-17 
Mystic, Conn. (NED) 1-57 
Mystic River, Conn. (NED) 1-51 
Mystic River, Mass. (NED) 1-10, 1-34, 1-45 
N 
Naches River, Naches, Wash. (NPS) 38-27 
Nagel Drainage District, Iowa (MRO) 21-21 
Nahunta Swamp, N.C. (SAW) 6-29 
Naknek River, Alaska (NPA) 40-12 
Namo River, Territory of Guam (POD) 36-15 
Nan Cove, Md. (NAB) 4-36, 4-40 
Nandua Creek, Va. (NAO) 5-25 
Nannyhagen Brook, N.Y. (NAN) 2-36 
Nansemond River, Va. (NAO) 5-25 
Nantasket Beach, Mass. (NED) 1-54 
Nanticoke River, Md. (NAB) 4-6, 4-24, 4-32 
Nanticoke River at Bivalve, Md. (NAB) 4-6, 4-24, 4-32 
Nanticoke River (including Northwest Fork), Del. and 
Md. (NAB) 4-36 
Nantucket (Harbor of Refuge), Mass. (NED) 1-51 
Napa River, Calif. (SPN) 34-6 
Napa River Basin, Calif. (SPK) 35-24 
Napatree Beach, R.I. (NED) 1-57 
Narragansett Pier, R.I. (NED) 1-57 
Narraguagus River, Maine (NED) 1-51 
Narrows Dam-Lake Greeson, Ark, (LMK) 12-8, 12-14, 
12-22 
Narrows of Lake Champlain, N.Y. and Vt. (NAN) 2-6, 
2-21, 2-25, 2-30 
Nashua, N.H. (NED) 1-29, 1-55, 1-63 
Natchez Port Area, Miss. (LMK) 12-25 
Natchitoches Parish, La. (LMN) (LMK) 11-36, 12-25 
National Waterways Study (MRO) 21-9 
National Disaster Preparedness, Response and 
Recovery Activities, 43-1 
Navajo Reservoir, N. Mex. (SPK) 35-23 
Navarro Mills Lake, Tex. (SWF) 16-9, 16-17, 16-21 
Navasota Lake, Tex. (SWF) 16-23 
Navigation Aids (U.S. Coast Guard), Ark, (SWL) 18-10 
Navigation Locks and Dams, Ark. (SWL) 18-10 
Navigation Work under Special Authorization 
(Calcasieu Pass Channel in Old River Bend at 
Cameron, La.) (LMN) 11-34 
Nawiliwili Harbor, Hawaii (POD) 36-3, 36-10, 36-12, 
36-16 
Nawiliwili Small Boat Harbor, Hawaii (POD) 36-14, 
36-16 
Neabsco Creek, Md. (NAB) 4-36 
Neah Bay, Wash. (NPS) 38-24 
Near Dardanelle, Arkansas River, Ark. SWL) 18-16 
Near Springfield on Sangamon River, Ill. (NCR) 28-16 
Neavitt Harbor, Md. (NAB) 4-36, 440 
Neches River and Tributaries, Salt Water Barrier at 
Beaumont, Tex. (SWG)15-13 
Needles, Calif. (SPL) 33-23 
Nehalem, Oreg. (NPP) 37-37 
Nehalem Bay, Oreg. (NPP) 37-7, 37-27, 37-36 
Neodesha Lake, Kans. (SWL) (SWT) 18-21, 19-24, 19-25 
Neon-Fleming, Ky. (ORL) 24-21, 24-31 
Neptune City, N.J. (NAN) 2-35 
Neshanminy State Park Harbor (NAP) 3-24 
Nestucca River, Oreg. (NPP) 3743, 3747 
Neuse River, N.C. (SAW) 6-26, 6-29 
Neva and Olga Straits, Alaska (NPS) 40-12 
Nevile Island, Pa. (ORP) 26-23, 26-27 
New Albany, Ind. (ORL) 24-21, 24-25, 24-30 
New Amsterdam, Ind. (ORL) 24-23, 24-26 
New Bedford and Fairhaven Harbors, Mass. (NED) 1-51 
New Bedford, Fairhaven, and Acushnet, Mass. (NED) 
1-25, 1-39, 149 
New Boston harbor, Ill. (NCD) 29-9 
New Buffalo Harbor, Mich. (NCE) 31-20, 3145, 31-64 
New Bullards Bar, Calif. (SPK) 35-24 
New Cumberland, W. Va. (ORP) 26-24 
New Cumberland Locks and Dam, Stratton, Ohio 
(ORD) 22-1, 22-7 
New Harbor, Maine (NED) 1-51 
New Harmony, Ind. (ORL) 24-23, 24-26, 24-31 
New Harmony Bridge, Ill. and Ind. (ORL) 24-22, 24-25 
New Haven Breakwater, Conn. (NED) 1-51 
New Haven Harbor, Conn. (NED) 1-10, 1-34, 146 
New Hope Lake (B. Everett Jordan Dam and Lake), 
N.C. (SAW) 6-11, 6-21 
New Jersey Intracoastal Waterway (NAP) 3-8, 3-18 
New Kensington and Parnassus, Pa. (ORP) 26-23, 26-27 
New Lock and Dam 26, Ill. (NCD) 29-7 
New London, Conn. (NED) 1-25, 1-29, 1-39, 1-49 
New London Harbor, Conn. (NED) 1-51 
New Madrid Harbor, Mo. (LMM) 13-2, 13-6, 13-8 
New Martinsville, W. Va. (ORH) 25-20 
New Matamoras, Ohio (ORH) 25-20 
New Melones Lake, Calif. (SPK) 35-14 
New Orleans to Venice, La. Hurricane Protection 
(LMN) 11-18, 11-24, 11-30 
New Pass, Sarasota, Fla. (SAJ) 9-10, 9-30, 9-38, 9-49 
New Richmond, Ohio (ORL) 24-23, 24-26 
New River, Fla. (SAJ) 9-49, 9-50 
New River, N.C. (SAW) 6-28 
New River, Onslow County, N.C. (SAW) 6-28 
New River, Va. and W. Va. (ORH) 25-18 
New Rochelle Harbor, N.Y. (NAN) 2-31 
1-28

INDEX 
New York and New Jersey Channels, (NAN) 2-7, 2-21, 
2-26, 2-29, 2-30, 2-35 
New York Harbor-Collection and Removal of Drift 
(NAN) 2-8, 2-21, 2-26 
New York Harbor-Entrance Channels and Anchorage 
Areas (NAN) 2-8, 2-21, 2-26 
New York Harbor, Supervisor of (NAN) 2-10, 2-22, 
2-29, 2-30 
Newark, Ohio (ORH) 25-7, 25-13, 25-16, 25-21 
Newark Bay, Hackensack and Passaic Rivers, N.J. 
(NAN) 2-6, 2-21, 2-25, 2-30, 2-35 
Newaukum River, Wash. (NPS) 38-27 
Newbegun Creek, N.C. (SAW) 6-26 
Newburgh, Ind. (ORL) 24-21, 24-31 
Newburgh Locks and Dam, Ind. (ORD) 22-3, 22-9 
Newburyport Harbor, Nass. (NED) 1-10, 1-34, 1-46 
Newhall Creek, Calif. (SPL) 33-27 
Newmarket Creek, Va. (NAO) 5-26 
Newport, Ark, (SWL) 18-16 
Newport, Ky. (ORL) 24-21, 24-25, 24-30 
Newport, Ohio (ORH) 25-20 
Newport Bay Harbor, Calif. (SPL) 33-21, 33-25 
Newport Harbor, R.I. (NED) 1-51 
Newport News Channel, Va. (NAO) 5-26 
Newport News Creek, Va. (NAO) 5-25 
Newry-Old Pickens Dam and Lake, S.C. (SAS) 8-17 
Newt Graham Lock and Dam, Okla. (SWL) (SWT) 
18-19, 19-25 
Newton Creek, N.Y. (NAN) 2-30, 2-31 
Niagara Remedial Works, N.Y. (NCB) 32-32 
Niagara River, N.Y. (NCB) 32-31, 32-36 
Niantic Bay and Harbor, Conn. (NED) 1-51 
Niblack, Mason J., Levee, Ind. (ORL) 24-4, 24-15, 
24-21, 24-25, 24-30 
Nicholasville, (Townfork) Vicinity, Ky. (ORL) 24-31 
Nichols, N.Y. (NAB) 4-38, 4-41 
Nickajack Lock and Dam, Tenn. (ORN) 23-17 
Nimrod Lake, Ark. (SWL) 18-6, 18-21 
Ninlchik Harbor, Alaska (NPA) 40-4, 40-9, 40-11 
Nishnabotna River at Hamburg, Iowa (MRO) 21-17, 
21-21 
Nisqually River, Wash. (NPS) 38-27 
Nixon Creek, Tenn. (LMM) 13-10 
Nolin Lake, Ky. (ORL) 24-10, 24-17, 24-28 
Nome Harbor, Alaska (NPA) 40-5, 40-9, 40-11 
Nomini Bay and Creek, Va. (NAB) 4-36 
Nonconnah Blvd., Noncannah Creek, Tenn. (LMM) 
134, 13-6, 13-8 
Nookagee Lake, Mass. (NED) 1-55, 1-63 
Nooksack River, Wash. (NPS) 38-27 
Norfolk, Nebr. (MRO) 21-17, 21-21 
Norfolk Floodwall, Va. (NAO) 5-26 
Norfolk Harbor, Va. (NAO) 5-7, 5-16, 5-21, 5-27 
Norfork Lake, Ark. (SWL) 18-8, 18-12, 18-23 
Normal, Ky. (ORH) 25-19 
Norman Reservoir (Lake Thunderbird), Okla. (SWT) 
19-13 
Norrell Lock ( Dam (No. 1) & Entrance Channel, Ark. 
(SWL) 18-3, 18-18 
North Adams, Mass. (NAN) 2-33 
North Alexander Drainage and Levee District, Ill. 
(LMS) 14-15 
North Andover and Lawrence, Mass. (NED) 1-57 
North Branch of Kokosing River Lake, Ohio (ORH) 
25-7, 25-13, 25-16 
North Canaan, Conn. (NED) 1-29, 1-55, 1-62 
North Ellenville, N.Y. (NAN) 2-33 
North Fork of Pound River Lake, Va. (ROH) 25-7, 
25-13, 25-16 
North Fork, Pit River at Altruas, Calif. (SPK) 35-24 
North Fork Skykomish River, Wash. (NPS) 38-27 
North Hampton Beach, North Hampton, N.H. (NED) 
1-54 
North Hartland Lake, Vt. (NED) 1-17, 1-36, 1-60 
North Little Rock, Arkansas River, Ark. (SWL) 18-16 
North Middleton, Ky. (ORL) 24-31 
North Nashua River, Fitchburg, Mass. (NED) 1-55 
North Nashua River, Lancaster, Mass. (NED) 1-55, 
1-63 
North Platte River, Bank Stabilization, Minatare, 
Nebr. (MRO) 21-21 
North River Dike, N.C. (SAW) 6-29 
North Scituate, Mass. (NED) 1-54 
North Second St., Memphis, Tenn. (Wolf River Bridge) 
(LMM) 13-4, 13-7, 13-8 
North Shore of Long Island, Suffolk County, N.Y. 
(NAN) 2-32 
North Springfield Lake, Vt. (NED) 1-17, 1-36, 1-60 
North Stratford, N.H. (NED) 1-61 
North Wildwood, N.J. (NAP) 3-26 
Northhampton, Mass. (NED) 1-29, 1-55, 1-61 
Northeast (Cape Fear) River, N.C. (SAW) 6-26, 6-28 
Northeast Harbor, Maine (NED) 1-51 
Northeast River, Md. (NAB) 4-7, 4-25, 4-32 
Northfield Brook Lake, Conn. (NED) 1-21, 1-38, 1-61 
Northport Harbor, N.Y. (NAN) 2-31 
Northport Harbor, Wis. (NCE) 31-75 
Norwalk, Conn. (NED) 1-29, 1-55 
Norwalk Harbor, Conn. (NED) 1-11, 1-34, 1-46 
Norwalk-Wilton, Conn. (NED) 1-57 
Norwich, Conn. (NED) 1-55, 1-64 
Norwich, N.Y. (NAB) 4-38, 4-41 
Northport Harbor, N.Y. (NAN) 2-31 
Northport Harbor, Wis. (NCE) 31-75 
Norwalk, Conn. (NED) 1-29, 1-55 
Norwalk Harbor, Conn. (NED) 1-11, 1-34, 1-46 
Norwalk-Wilton, Conn. (NED) 1-57 
Norwich, Conn. (NED) 1-55, 1-64 
Norwich, N.Y. (NAB) 4-38, 4-41 
Nottoway River, Va. (NAO) 5-25 
Noxubee River, Miss. (SAM) 10-38 
Noyo River and Harbor, Calif. (SPN) 34-4, 34-6 
Nutwood Drainage and Levee District, Ill. (LMS) 14-6, 
14-10, 14-12 
O 
O.C. Fisher Dam and Lake, Tex. (SWF) 16-10, 16-17, 
16-21 
Oahe Dam-Lake Oahe, Missouri River Basin S. Dak. 
1-29

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
and N. Dak. (MRO) 21-8, 21-12 
Oak Bluffs Town Beach, Mass. (NED) 1-54 
Oak Orchard Harbor, N.Y. (NCB) 32-11, 32-32 
Oakdale, Pa. (ORP) 26-23 
Oakford Special Drainage District (NCR) 28-16, 28-19 
Oakland Beach, Warwick, R.I. (NED) 1-35, 1-54 
Oakland Harbor, Calif. (SPN) 34-6, 34-11 
Obey River, Tenn. (ORN) 23-13 
Obion River, Tenn. (LMM) 13-10 
O'Brien, T.J., Lock and Dam, Ill. (NCC) 28-22, 28-23 
Occohannock Creek, Va. (NAO) 5-25 
Occoquan Creek, Va. (NAB) 4-36 
Ocean Beach, Calif. (SPL) 33-22 
Ocean City, N.J. (NAP) 3-26 
Ocean City Harbor and Inlet and Sinepuxent Bay, Md. 
(NAB) 4-7, 4-25, 4-32 
Oceana, W. Va. (ORH) 25-19 
Oceanside, Calif. (SPL) 33-22 
Oceanside Harbor, Calif. (SPL) 33-3, 33-12, 33-17 
Ocholockonee (Ochlockney) River, Ga. and Fla. (SAM) 
10-38 
Octono Harbor, Wis. (NCE) 31-21, 31-46, 31-64 
Ocracoke Inlet, N.C. (SAW) 6-7, 6-20 
Ocracoke Island, N.C. (SAW) 6-28 
Ofu Small Boat Harbor, American Samoa (POD) 36-14, 
36-16 
Ogdensburg Harbor, N.Y. (NCB) 32-8, 32-18, 32-28 
Ohio River, Ill. and Ky. (MR�T) 42-20 
Ohio River Basin (Huntington District) (ORH) 25-7, 
25-13 
Ohio River Basin (Louisville Dist.) (ORL) 24-11, 24-17, 
24-19, 24-25 
Ohio River Basin (Nashville District) (ORN) 23-6, 
23-12, 23-18 
Ohio River Basin (Pittsburgh District) (ORP) 26-9, 
26-15, 26-20, 26-27 
Ohio River, Locks and Dams (ORD) 22-1, 22-5, 22-7 
Ohio River, Open Channel Work (ORD) 22-3, 22-5, 
22-6 
Oil City, Pa. (ORP) 26-23 
Okabena Creek at Worthington, Minn. (NCR) 28-16 
Okanogan and Pend Oreille River (NPS) 38-24 
Okanogan River, Wash. (NPS) 38-27 
Okanogan River, Omak, Wash. (NPS) 38-8, 38-27 
Okanogan River, Oroville, Wash. (NPS) 38-27 
Okatibbee Lake, Miss. (SAM) 10-12, 10-25, 10-34 
Okeechobee Waterway, Fla. (SAJ) 9-11, 9-31, 9-38, 
9-48 
Oklahoma City Floodway, Okla. (SWT) 19-24, 19-27 
Oklawaha River, Fla. (SAJ) 9-11, 9-31, 9-39 
Olcott Harbor, N.Y. (NCB) 32-11, 32-32 
Old Field Swamp, N.C. (SAW) 6-28 
Old Harbor, Kodiak Island, Alaska (NPA) 40-12 
Old Hickory Lock and Dam, Tenn. (ORN) 23-14 
Old River, Calif. (SPK) 35-23 
Old River, La. (MR +T) 42-6, 42-28, 42-50 
Old River, Standard Revetments (MR�T) 42-31 
Old Town, Maine (NED) 1-55 
Old Town Creek, Miss. (SAM) 10-38 
Oldmans Creek, N.J. (NAP) 3-24, 3-27 
Olean, N.Y. (ORP) 26-23, 26-27 
Olive Hill, Ky. (ORH) 25-21 
Olympia Harbor, Wash. (NPS) 38-24, 38-31 
Omaha, Nebr. (MRO) 21-17, 21-21 
Onaga Lake, Kans. (MRK) 20-19 
Onancock River, Va. (NAO) 5-25 
Onondaga Creek, Nedrow, N.Y. (NCB) 32-34 
Ontonagon Harbor, Mich. (NCE) 31-21, 31-46, 31-64 
Oologah Lake, Okla. (SWL) (SWT) 18-21, 19-10, 19-20, 
19-25 
Oostanaula and Coosawatee River, Ga. (SAM) 10-38 
Opekiska Lock and Dam, W. Va. (ORP) 26-26 
Open Channel Work, Ohio River (ORD) 22-3, 22-5, 
22-6 
Open River Lewiston to Johnson Bar Landing (NPW) 
39-26 
Open River Pasco to Lewiston (NPW) 39-26 
Optima Lake, Okla. (SWT) 19-10, 19-20 
Orange River, Fla. (SAJ) 9-50 
Oregon Slough (North Portland Harbor), Oreg. (NPP) 
37-43 
Orleans, Ind. (ORL) 24-23 
Oro Grande Wash Channel Improvements, Calif. (SPL) 
33-23 
Orofino Creek and Clearwater River, Idaho (NPW) 
37-43 
Orowoc Creek, N.Y. (NAN) 2-31 
Orwell Reservoir (Ottertail River) (NCS) 27-27 
Osage River, Kans. and Mo. (MRK) 20-24 
Osage River, Mo., Lock and Dam (MRK) 20-18 
Osawatomie, Kans. (MRK) 20-19, 20-23 
Osceola Harbor, Ark. (LMM) 13-2, 13-6, 13-8 
Oswego, N.Y. (NAB) 4-41 
Oswego Harbor, N.Y. (NCB) 32-9, 32-18, 32-28, 32-36 
Ottawa, Kans. (MRK) 20-19, 20-23 
Ottawa River Harbor, Mich. and Ohio (NCB) 32-32 
Otter Brook Lake, N.H. (NED) 1-17, 1-37, 1-60 
Otter Creek, Vt. (NAN) 2-31 
Otter Creek Park, Ky. (ORL) 24-31 
Otter Tail River, Minn. (NCS) 27-27, 27-28 
Ottumwa, Iowa (NCR) 28-17 
Ouachita and Black River, Ark. and La. (Felsenthal 
Canal) (LMK) 12-21 
Ouachita and Black Rivers below Camden, Ark. 
(LMK) 12-2, 12-13, 12-16, 12-19 
Ouachita River and Tributaries, Ark. and La. (LMK) 
12-9, 12-18, 12-22 
Ouachita River Levees, La. (LMK) 12-9, 12-15, 12-22 
Overton-Red River Waterway, La. (LMN) (LMK) 11-22 
12-3, 12-13, 12-16 
Owasco Inlet and Outlet, Montville and Dry Creek, 
State Ditch and Crane Brook, N.Y. (NCB) 32-34 
Owensboro, Ky. (ORL) 24-22, 24-25 
Owl's Head Harbor, Maine (NED) 1-51 
Oxford, Md. (NAB) 4-38 
Oxford, N.Y. (NAB) 4-18, 4-28 
Oyster Channel, Va. (NAO) 5-8, 5-16, 5-22, 5-27 
Oyster Creek, Tex. (SWG) 15-27 
Ozan Creek, Ark. (LMK) 12-22 
Ozark-Jeta Taylor Lock & Dam, Ark. (SWL) 18-8, 
18-12, 18-19 
Ozona, Fla. (SAJ) 9-50 
1-30

INDEX 
P 
Paauau Stream, Hawaii (POD) 36-7, 36-11 
Paducah, Ky. (ORL) 24-21, 24-25, 24-30 
Pagan River, Va. (NAO) 5-25 
Pago Pagon Airport, American Samoa (POD) 36-5, 
36-11 
Pago Pago to Nuuuli, American Samoa (POD) 36-15 
Paint Creek at Chillicothe, Ohio (ORH) 25-21 
Paint Creek at Washington Court House, Ohio (ORH) 
25-21 
Paint Creek Lake, Ohio (ORH) 25-8, 25-13, 25-17 
Paint Rock River, Ala. (ORN) 23-13, 23-19 
Painted Post, N.Y. (NAB) 4-38, 441 
Painted Rock Dam, Ariz. (SPL) 33-6, 33-13, 33-18 
Paintsville Lake, Ky. (ORH) 25-8, 25-13, 25-17 
Pajaro River, Calif. (SPN) 34-21 
Pajaro River Basin, Calif. (SPN) 34-16 
Palm Beach, Fla. (SAJ) 9-50 
Palm Beach County, Fla. , from Lake Worth Inlet to 
South Lake Worth Inlet (SAJ) 9-51 
Palm Beach County, Fla., from Martin County Line of 
Lake Worth Inlet and from South Lake Worth Inlet 
to Broward County Line (SAJ) 9-23, 9-33, 9-44 
Palm Beach Harbor, Fla. (SAJ) 9-12, 9-31, 9-39 
Palouse River, Wash. (NPW) 39-18, 39-20 
Pamlico and Tar River, N.C. (SAW) 6-26 
Pamunkey River, Va. (NAO) 5-25 
Panacea Harbor, Fla. (SAM) 10-37, 10-38 
Panama City Harbor, Fla. (SAM) 10-9, 10-24, 10-32 
Pantego Creek and Cucklers Creek, N.C. (SAW) 6-28 
Panther Creek, Curdsville, Ky. (ORL) 24-21, 24-31 
Panther Cree, W. Va. (ORH) 25-19 
Papillion Creek and Tributaries Lakes, Nebr. (MRO) 
21-5, 21-11, 21-13 
Parish Creek, Md. (NAB) 4-36, 4-40 
Park River, N.D. (NCS) 27-28 
Park River, Hartford, Conn. (NED) 1-18, 1-37, 1-48, 
1-61 
Parker Creek, Va. (NAO) 5-25 
Parkersburg, W. Va. (ORH) 25pl9, 25-21 
Parrotts Creek, Va. (NAO) 5-25 
Pascagoula Harbor, Miss. (SAM) 10-9, 10-25, 10-33 
Pascagoula River, Miss. (SAM) 10-38 
Pasquotank River, N.C. (SAW) 6-28 
Pass Christian, Miss. (SAM) 10-37 
Pass Christian Harbor, Miss. (SAM) 10-38 
Pass Manchac, La. (LMN) 11-34 
Pass-a-Grille Pass, Fla. (SAJ) 9-49, 9-50 
Passaic River Basin, N.J. and N.Y., Phase I (NAN) 
2-15, 2-22, 2-28 
Passamaquoddy Tidal Power Project, Maine (NED) 1-56 
Pat Mayse Lake, Tex. (SWT) 19-10, 19-20 
Pataha Creek, Wash. (NPW) 39-18 
Patchogue River, Conn. (NED) 1-11, 1-35, 1-46 
Patman, Wright, Dam and Lake, Tex. (LMN) (SWF) 
11-37, 16-13, 16-18, 16-22 
Patoka Lake, Ind. (ORL) 24-11, 24-17, 24-28 
Patoka River at Jasper, Ind. (ORL) 24-31 
Patriot, Ind. (ORL) 24-23, 24-26 
Patroon Creek, Albany, N.Y. (NAN) 2-36 
Pattonsburg Lake, Mo. (MRK) 20-19 
Patuxent River, Md. (NAB) 4-36 
Pawacatuck River, R.I. and Conn. (NED) 1-51, 1-57 
Pawtucket, R.I. (NED) 1-57 
Pawtuxet Cove, R.I. (NED) 1-51 
Pawtuxet River, Warwick, R.I. (NED) 1-14, 1-35, 1-47 
Pax, W. Va. (ORH) 25-21 
Payette River, Idaho (NPW) 39-18 
Payette Valley, Idaho (NPW) 39-19, 39-20 
Peacock Creek, Liberty County, Ga. (SAS) 8-7, 8-16 
Pearl River, Miss. and La. (LMK) 12-3, 12-13, 12-16 
Pearson-Skubitz Big Hill Lake, Kans. (SWT) 19-11, 
19-20, 19-23 
Pebble Creek, Scribner, Nebr. (MRO) 21-22 
Pecan Bayou Lake, Pecan Bayou, Tex. (SWF) 16-23 
Pecatonica River at Darlington, Wis. (NCR) 28-18 
Peconic River, N.Y. (NAN) 2-31 
Pecos, Tex. (SWA) 17-12 
Peekskill Harbor, N.Y. (NAN) 2-31 
Pekin-LaMarsh Drainage and Levee District, Ill. 
(NCR) 28-17, 28-19 
Pelican Harbor, Alaska (NPA) 40-12 
Pembina, N. Dak. (NCS) 27-28 
Pembina River, N. Dak. (NCS) 27-11 
Pembina River Lake, N. Dak. (NCS) 27-24 
Pembroke Creek, N.C. (SAW) 6-26 
Pendleton, Oreg. (NPP) 37-47 
Pendleton Levees, Oreg. (NPP) 37-47 
Penisula Drainage District 1, Oreg. (NPP) 37-44, 
37-48, 37-52 
Penisula Drainage District 2, Oreg. (NPP) 37-44, 
37-46, 37-52 
Penny Slough, Ill. (NCR) 28-17, 28-19 
Penny Slough Drainage and Levee District, Ill. (NCR) 
28-7 
Penobscot River, Maine (NED) 1-51 
Pensacola Bay, Fla. to Mobile Bay, Ala. (SAM) 10-31 
Pensacola Harbor, Fla. (SAM) 10-10, 10-25, 10-33 
Pensacola Lake, Okla. (SWL) (SWT) 18-21, 19-21, 
19-25 
Pensacola Reservoir, Okla. (SWT) 19-15 
Pensaukee Harbor, Wis. (NCE) 31-21, 31-46, 31-64 
Pentwater Harbor, Mich. (NCE) 31-22, 31-36, 31-64, 
31-77 
Peoria, Ill. (NCC) 28-17 
Peoria Lock and Dam, Ill. (NCC) 18-21, 18-22 
Pepin Harbor, Wis. (NCD) 29-8 
Pepper Creek, Del. (NAP) 3-24 
Pepperell Cove, Maine (NED) 1-51 
Perdido Pass Channel, Ala. (SAM) 10-10, 10-25, 10-34 
Permanent International Association of Navigation 
Congress (PIANC) 46-1 
Perquimans River, N.C. (SAW) 6-26, 6-28 
Perry County Drainage and Levee Districts No.s 1, 2, 
and 3, Mo. (LMS) 14-6, 14-10, 14-12 
Perry Lake, Kans. (MRK) 20-6, 20-13, 20-16, 20-23 
Perry Lake Area (Road Improvements) Kans. (MRK) 
20-19 
Perth Amboy, N.J. (NAN) 2-32 
Petaluma River, Calif. (SPN) 34-6 
1-31

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Petersburg Harbor, Alaska (NPA) 40-12 
Petit Anse, Tigre, and Carlin Bayous, La. (LMN) 11-34 
Petit Jean River, Ark. (SWL) 18-16 
Petoskey Harbor, Mich. (NCE) 31-74, 31-75 
Peyton Creek, Tex. (SWG) 15-27 
Phillippi Creek Basin, Fla. (SAJ) 9-57 
Phillips Lake, Mass. (NED) 1-55, 1-63 
Philpott Lake, Va. (SAW) 6-17, 6-22 
Phoenix, Ariz., and Vicinity (including New River) 
(SPL) 33-6, 33-13, 33-18 
Pick-Sloan Missouri Basin Program (Kansas City Dist) 
(MRK) 20-6, 20-13, 20-16, 20-23 
Pick-Sloan Missouri Basin Program (Omaha Dist) 
(MRO) 21-6, 21-14, 21-19 
Pickwick Landing Lock and Dam, Tenn. (ORN) 23-17 
Pierce, Nebr. (MRO) 21-17, 21-21 
Pig Island Gut, Maine (NED) 1-51 
Pike Island Locks and Dam, W. Va. (ORD) 22-1, 22-7 
Pilchuck River, Wash. (NPS) 38-27 
Pilot Rock, Oreg. (NPP) 38-27 
Pinal Creek Channel Improvements (Globe), Ariz., 
(SPL) 33-23 
Pine and Mathews Canyons Dams, Nev. (SPL) 33-8, 
33-14, 33-19 
Pine Bluff, Ark. (LMK) 12-22 
Pine Brook, N.J. (NAN) 2-36 
Pine Creek, Angle Inlet, Minn. (NCS) 27-23 
Pine Creek Lake, Okla. (SWT) 19-11, 19-20, 19-26 
Pine Flat Lake and Kings River, Calif. (SPK) 35-9, 
35-19 
Pine Ford Lake, Mos. (LMS) 14-5, 14-9 
Pine Mountain Lake, Ark. (SWL) 18-6, 18-11 
Pine River, Mich. (NCE) 31-74, 31-75 
Pine River Reservoir, Minn. (NCS) 27-26 
Pinellas County, Fla. (SAJ) 9-23, 9-33, 9-44 
Pineville, Ky. (ORN) 23-13, 23-19 
Pineville, La. (LMN) (LMK) 11-36, 12-25 
Pinole Creek, Calif. (SPK) 35-24 
Pinon Canyon Dam, Trinidad, Colo. (SWA) 17-12 
Pioneer Lake, Kans. (MRK) 20-20 
Pipestem Lake, N. Dak. (MRO) 21-6, 21-11, 21-14 
Pithlachascotee River, Fla. (SAJ) 9-50 
Pittsburgh, Pa. (Golden Triangle) (ORP) 26-24 
Pittsburgh, Pa. (North Side) (ORP) 26-24 
Pittsburgh, Pa. (The Strip) (ORP) 26-24 
Pittsburgh Harbor, Pa. (ORP) 26-22 
Pittsfield, Mass. (NED) 1-62 
Placer Creek, Idaho (NPS) 38-9, 38-16, 38-22 
Plainview Local Flood Protection Project (SWF) 16-23 
Platte River, Mo., Channel Improvement (MRK) 20-19 
Platte River and Lost Creek, Schuyler, Nebr. (MRO) 
21-17 
Platte River and Tributaries, Nebr. (MRO) 21-17 
Platte River, Bank Protection, Louisville, Nebr. (MRO) 
21-21 
Platte River, M.U.D. Protection, Cedar Island, Nebr. 
(MRO) 21-21 
Platte River near Schuyler, Nebr. (MRO) 21-17, 21-21 
Plattsburgh Harbor, N.Y. (NAN) 2-31 
Pleasant Bay, Mass. (NED) 1-51 
Pleasant River, Maine (NED) 1-51 
Pleasanton Floodway, Tex. (SWF) 16-23 
Plum Creek, Ky. (ORL) 24-31 
Plum Creek, Minn. (NCS) 27-29 
Plum Creek, Bank Stabilization, Aurora, Colo. (MRO) 
21-21 
Plum Island, Mass. (NED) 1-54 
Plymouth, Pa. (NAB) 4-38, 4-41 
Plymouth Harbor, Mass. (NED) 1-51 
Poca, W. Va. (ORH) 25-20 
Pocatello, Idaho (NPW) 39-21 
Pocomoke River, Md. (NAB) 4-7, 4-25, 4-32 
Pokoiki Bay, Hawaii (POD) 36-14 
Point Judith, R.I. (NED) 1-57 
Point Lookout Harbor (Au Gres River), Mich. (NCE) 
31-22, 31-46, 31-65 
Point Place, Toledo, Ohio (NCB) 32-15, 32-20 
Point Pleasant, W. Va. (ORL) 25-19, 25-21 
Pokegama Reservoir, Minn. (NCS) 27-26 
Polecat Creek Channel Improvements, Okla. (SWT) 
19-27 
Pollock Rip Shoals, Nantucket Sound, Mass. (NED) 
1-51 
Poloa Area, American Samoa (POD) 36-15 
Polson Bay, Flathead Lake, Mont. (NPS) 38-24 
Pomeroy, Ohio (ORL) 25-20 
Pomme De Terre Lake, Mos. (MRK) 20-7, 20-13, 20-17, 
20-23 
Pomona Lake, Kans. (MRK) 20-7, 20-13, 20-17, 20-23 
Ponce, P.R. (SAJ 9-45 
Ponce De Leon Inlet, Fla. (SAJ) 9-12, 9-31, 9-39, 9-49 
Pome Harbor, P.R. (SAJ) 9-12, 9-31, 9-39 
Pontiac Diversion, R.I. (NED) 1-57 
Pool, Joe, Lake (Lakeview Lake), Tex. (SWF) 16-7, 
16-17, 16-21 
Port Alexander, Alaska (NPA) 40-12, 40-13 
Port Allen Harbor, Hawaii (POD) 36-3, 36-10, 36-13, 
36-16 
Port Angeles Harbor, Wash. (NPS) 38-24, 38-30 
Port Arthur and Vicinity, Tex. Hurricane-Flood Protection 
(SWG) 15-10, 15-11, 15-15, 15-25 
Port Austin Harbor, Mich. (NCE) 31-74, 31-75 
Port Bay, N.Y. (NCB) 32-32 
Port Clinton Harbor, Ohio (NCB) 32-9, 32-19, 32-29 
Port Dickenson, N.Y. (NAB) 4-41 
Port Everglades Harbor, Fla. (SAJ) 9-13, 9-31, 9-40, 
9-49 
Port 5 Facility, Bridgeport, Conn. (NED) 1-23, 1-38, 
1-48 
Port Gamble Harbor, Wash. (NPS) 38-24, 38-30, 38-31 
Port Henry Harbor, N.Y. (NAN) 2-31 
Port Hueneme, Calif. (SPL) 33-3, 33-12, 33-17 
Port Jefferson Harbor, N.Y. (NAN) 2-30, 2-31 
Port Lions Small Boat Harbor, Alaska (NPA) 40-5, 
40-9, 40-11 
Port of Kalma, Wash. (NPP) 37-44 
Port Mahon, Del. (NAP) 3-11 
Port Ontario Harbor, N.Y. (NCB) 32-32 
Port Orchard Bay, Wash. (NP 38-24 
Port Orford, Oreg. (NPP) 37-7, 37-27, 37-36 
Port Royal Harbor, S.C. (SAN) 7-15 
Port San Luis, Calif. (SPL) 33-21, 33-25 
1-32

INDEX 
Port Sanilac Harbor, Mich. (NCE) 31-23, 31-47, 31-65 
Port St. Joe Harbor, Fla. (SAM) 10-11, 10-25, 10-34 
Port Townsend, Wash. (NPS) 38-24 
Port Washington Harbor, Wis. (NCE) 31-23, 31-47, 
31-65 
Port Wing Harbor, Wis. (NCE) 31-23, 31-47, 31-65 
Portage, Pa. (ORP) 26-23 
Portage Lake Harbor, Mich. (NCE) 31-22, 3146, 31-65 
Portchester Harbor, N.Y. (NAN) 2-30, 2-35 
Porter Bayou, Miss. (LMK) 12-9, 12-15, 12-18 
Portland, Ind. (ORL) 24-21, 24-31 
Portland, Ohio (ORH) 25-20 
Portland Harbor, Maine (NED) 1-51 
Portneuf River and Marsh Creek, Idaho (NPW) 39-18 
39-19, 39-20 
Portsmouth Harbor, Va. Channel to Nansemond Ordnance 
Depot (NAO) 5-25 
Portmouth Harbor and Piscataqua River, Maine and 
N.H. (NED) 1-12, 1-35, 1-46 
Portsmouth-New Boston, Ohio (ORH) 25-19, 25-21 
Portugues and Bucana Rivers, P.R. (SAJ) 9-27, 9-33, 
9-45 
Portville, N.Y. (ORP) 26-23, 26-27 
Posten Bayou, Ark. and La. (LMN) (LMK) 11-36, 12-25 
Poteau River Navigation, Ark. and Okla. (SWT) 19-4, 
19-18, 19-23 
Poteet Floodway, Tex. (SWF) 16-23 
Potomac and Anacostia Rivers, D.C., Collection and 
Removal of Drift (NAB) 4-8, 4-25, 4-33 
Potomac Estuary Pilot Water Treatment Plant, D.C., 
(NAB) 4-21, 4-29, 4-35 
Potomac River and Tributaries at and below 
Washington, D.C., Elimination of Waterchestnut 
(NAB) 4-37 
Potomac River at Alexandria, Va. (NAB) 4-37 
Potomac River at Lower Cedar Point, Md. (NAB) 4-37 
Potomac River at Mount Vernon, Va. (NAB) 4-8, 4-25, 
4-32 
Potomac River below Washington, D.C. (NAB) 4-8, 
4-25, 4-32 
Potomac River North Side of Washington Channel, 
D.C. (NAB) 4-37 
Potowomut River, R.I. (NED) 1-51 
Pottstown and Vininity, Pa. (NAP) 3-15, 3-20 
Powell County High School, Mont. (NPS) 38-27 
Powhatan Point, Ohio (ORP) 26-23, 26-27 
Prairie and Silver Creek, Grand Island, Nebr. (MRO) 
21-22 
Prarie Du Chien, Wis. (NCS) 27-11, 27-20 
Prarie Du Chien Harbor, Wis. (NCD) 29-8 
Prarie du Pont Levee and Sanitary District, Ill. (LMS) 
14-15 
Prarie du Rocher and Vicinity, Ill. (LMS) 14-15 
Prattville, Ala. (SAM) 10-39 
Pre-Authorization Studies for Beach Erosion Control 
Activities 
Chicago, Ill., District (NCC) 30-6 
Detroit, Mich., (NCE) 31-30 
Jacksonville, Fla., District (SAJ) 9-24 
New England Division (NED) 1-58 
New York, N.Y., District (NAN) 2-32 
Pacific Ocean Division (POD) 36-5 
Philadelphia, Pa., District (NAP) 3-11 
Pre-Authorization Studies for Flood Control Activities 
Alaska District (NPA) 40-6 
Albuquerque, N. Mex., District (SWA) 17-8 
Baltimore, Md., District (NAB) 4-21 
Buffalo, N.Y., District (NCB) 32-35 
Charleston, S.C., District (SAN) 7-15 
Detroit, Mich., District (NCE) 31-33 
Fort Worth, Tex., District (SWF) 16-14, 16-24 
Galveston, Tex., District (SWG) 15-11 
Huntington, W. Va., District (ORH ) 25-10 
Jacksonville, Fla., District (SAJ) 9-57 
Little Rock, Ark., District (SWL) 18-7, 18-24 
Los Angeles, Calif., District (SPL) 33-27 
Louisville, Ky., District (ORL) 24-14, 24-32 
Memphis, Tenn., District (LMM) 13-5 
Mobile, Ala., District (SAM) 10-40 
Nashville, Tenn., District (ORN) 23-6, 23-19 
New England Division (NED) 1-59 
New Orleans, La., District (LMN) 11-20 
New York, N.Y., District (NAN) 2-19 
Omaha, Nebr., District (NRO) 21-22 
Pacific Ocean Division (POD) 36-8 
Philadelphia, Pa., District (NAP) 3-13 
Pittsburgh, Pa., District (ORP) 26-30 
Portland, Oreg., District (NPP) 37-15 
Rock Island, Ill., District (NCR) 28-20 
Sacramento, Calif., District (SPK) 35-14 
San Francisco, Calif., District (SPN) 34-4 
Savannah, Ga., District (SAS) 8-7 
Seattle, Wash., District (NPS) 38-31 
St. Louis, Mo., District (LMS) 14-7 
St. Paul, Minn., District (NCS) 27-29 
Tulsa, Okla., District (SWT) 19-27 
Vicksburg, Miss., District (LMK) 12-12 
Walla Walla, Wash., District (NPW) 39-2 
Wilmington, N.C., District (SAW) 6-32 
Pre-Authorization Studies for Navigation Activities 
Alaska District (NPA) 40-14 
Baltimore, Md., District (NAB) 4-11 
Buffalo, N.Y., District (NCB) 32-33 
Charleston, S.C., District (SAN) 7-17 
Chicago, Ill., District (NCC) 30-5 
Detroit, Mich., District (NCE) 31-30 
Galveston, Tex., District (SWG) 15-9 
Jacksonville, Fla., District (SAJ) 9-19 
Memphis, Tenn., District (LMM) 13-3 
Mobile, Ala., District (SAM) 10-38 
Nashville, Tenn., District (ORN) 23-4 
New England Division (NED) 1-58 
New Orleans, La., District (LMN) 11-15, 11-34 
Norfolk, Va., District (NAO) 5.11 
Pacific Ocean Division (POD) 364 
Philadelphia, Pa., District (NAP) 3-8 
Portland, Oreg., District (NPP) 37-50 
Rock Island, Ill., District (NCR) 28-3 
San Francisco, Calif., District (SPN) 34-3 
Savannah, Ga., District (SAS) 8.6 
Seattle, Wash., District (NPS) 38-5 
St. Louis, Mo., District (LMS) 14-7 
I-33

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
St. Paul, Minn., District (NCS) 27-27 
Tulsa, Okla., District (SWT) 19-4 
Vicksburg, Miss., District (LMK) 12-6 
Wilmington, N.C., District (SAW) 6-30 
Prescott Area, Oreg. (NPP) 37-49 
Presque Isle Harbor, Mich. (NCE) 31-24, 31-47, 31-65 
Presque Isle Peninsula, Erie, Pa. (NCB) 32-11, 32-19, 
32-31 
Prestile Stream, Blaine, Maine (NED) 1-55 
Preston Drainage and Levee District, Ill. (LMS) 14-15 
Prestonburg, Ky. (ORH) 25-21 
Prestonville, Ky. (ORL) 24-23, 24-26 
Priest, J. Percy, Dam and Reservoir, Tenn. (ORN) 
23-7, 23-9, 23-18 
Priest Rapids Dam, Wash. (NPS) 38-29 
Princeton, W. Va. (ORH) 25-19, 25-21 
Prineville Area, Oreg. (NPP) 37-49 
Proctor, Vt. (NAN) 2-35 
Proctor, W. Va. (ORP) 26-23, 26-27 
Proctor Lake, Tex. (SWF) 16-10, 16-17, 16-21 
Proctorville, Ohio (ORH) 25-19 
Prompton Lake, Pa. (NAP) 3-15, 3-20 
Prospect Beach, West Haven, Conn. (NED) 1-54 
Providence River and Harbor, R.I. (NED) 1-57 
Provincetown Beach (Herring Cove), Mass. (NED) 1-57 
Provincetown Harbor, Mass. (NED) 1-51, 1-57 
Pudding River, Oreg. (NPP) 37-49 
Pueblo Arkansas River, Colo. (Floodway Levee Extension) 
(SWA) 17-12 
Puget Sound and Its Tributary Waters, Wash. (NPS) 
38-5, 38-14, 38-20 
Pullman, Palouse, Wash. (NPW) 39-18 
Pultneyville Harbor, N.Y. (NCB) 32-32 
Pugo Creek, N.C. (SAW) 6-28 
Pungo River, N.C. (SAW) 6-28 
Punta Salina, P.R. (SAJ) 9-23, 9-33, 9-44 
Punxsutawney, Pa. (ORP) 26-5, 26-14, 26-19, 26-27 
Punxsutawney, Pa. (Allegheny River Basin) (ORP) 
26-27 
Put In Bay, Ohio (NCB) 32-11, 32-32 
Pysht River, Wash. (NPS) 38-27 
Q 
Quail Wash Levee, Joshuea Tree, Calif. (SPL) 33-23 
Queens Creek, Va. (NAO) 5-25 
Queenstown Harbor, Md. (NAB) 4-36, 4-40 
Queets River, Wash. (NPS) 38-27 
Quillayute River, Wash. (NPS)38-6, 38-14, 38-20, 38-27 
Quinault River, Wash. (NPS) 38-27 
Quinby Creek, Va. (NAO) 5-9, 5-16, 5-22 
Quincy, Ill., Harbor Access Channel (NCR) 28-15 
Quincy Harbor, Ill. (NCD) 29-9 
Quincy Shore Beach, Quincy, Mass. (NED) 1-54 
R 
R.D. Bailey Lake, W. Va. (ORH) 25-8, 25-14, 25-17 
Raccoon Creek, N.J. (NAP) 3-24 
Raccoon Levee, Ind. (ORL) 24-23, 24-26 
Racine, Ohio (ORH) 25-20 
Racine Harbor, Wis. (NCE) 31-24, 31-48, 31-65 
Racine Locks and Dam, Ohio (ORD) 22-1, 22-8 
Rahway, N.J. (NAN) 2-33 
Rahway South Branch, N.J. (NAN) 2-33 
Rahway River, N.J. (NAN) 2-35 
Rainey, Henry T., Dam, Ill. (NCD) 29-7 
Rainier Drainage District, Oreg. (NPP) 37-44, 37-46, 
37-52 
Ramapo River, Monroe, N.Y. (NAN) 2-36 
Rancocas Creek at Mt. Holly, N.J. (NAP) 3-15 
Racnocas River, N.J. (NAP) 3-27 
Randleman Lake, N.C. (SAW) 6-12, 6-21 
Rapid City, Cedar Canyon Dam, S. Dak. (MRO) 21-20 
Rapid Creek, Rapid City, S. Dak. (MRO) 21-20 
Rapidan River, Va. (NAO) 5-13, 5-18, 5-23 
Rapide Croche Lock and Dam, Wis. (NCE) 31-73 
Rappahannock River, Va. (NAO) 5-9, 5-17, 5-22 
Rappahannock River at Bowlers Wharf, Va. (NAO) 
5-25 
Rappanhannock Shoal Channel, Va. (NAO) 5-3, 5-19 
Raritan Bay and Sandy Hook Bya,m N.J. (NAN) 2-33 
Raritan River, N.J. (NAN) 2-30, 2-35 
Raritan River to Arthur Kill Cutoff Channel, N.J. 
(NAN) 2-31 
Rathbun Lake, Iowa (MRK) 20-7, 20-13, 20-17 
Rathbun Lake Fish Hatchery (MRK) 20-19 
Ravenswood, W. Va. (ORH) 25-19 
Ray Roberts Lake, Tex. (SWF) 16-10, 16-17, 16-21 
Rayburn, Sam, Dam and Reservoir, Tex. (SWF) 16-14, 
16-17, 16-21 
Raystown Lake, Pa. (NAB) 4-14, 4-27, 4-35 
Red Bank and Fancher Creeks, Calif. (SPK) 35-16 
Red Brook Harbor, Bourne, Mass. (NED) 1-51 
Red Creek, N.Y. (NCB) 32-34 
Red Lake and Red Lake River, Minn. (NCS) 27-23 
Red Lake River, Minn. (NCS) 27-11, 27-12, 27-20, 27-28 
Red Lake River, Minn. including Clearwater River, 
Minn. (NCS) 27-12, 27-21 
Red River, Tenn. (ORN) 23-13 
Red River at East Grand Forks, Minn. (NCS) 27-27 
Red River at Fargo, N. Dak. (NCS) 27-27 
Red River at Grand Forks, N. Dak. (NCS) 27-27 
Red River Backwater Levees (MR�T) 42-46, 42-52 
Red River below Denison Dam including Little River 
Basin, Okla. and Ark. (SWL) 18-14 
Red River below Denison Dam, Levees and Bank Stabilization 
(Vicksburg Dist.) (LMK) 12-10, 12-15, 
12-18 
Red River below Denison Dam (New Orleans Dist.) 
(LMN) 11-24 
Red River below Denison Dam (Tulsa District) (SWT) 
19-11, 19-23, 19-26 
Red River below Denison Dam (Vicksburg District) 
(LMK) 12-10, 12-23, 12-24 
1-34

INDEX 
Red River below Fulton, Ark. (LMN) (LMK) 11-38, 
12-21 
Red River Emergency Bank Protection (LMN) (LMK) 
11-22, 12-4, 12-13, 12-16 
Red River from Fulton, Ark., to Mouth of Washita 
River (SWT) 19-4 
Red River in Vicinity of Shreveport, La. (LMN) (LMK) 
11-36, 12-25 
Red River Lake, Ky. (ORL) 24-22 
Red River of the North, Minn. and N. Dak, (NCS) 
27-23 
Red River of the North, Argusville, N. Dak. (NCS) 
27-29 
Red River of the North at Oslo, Minn. (NCS) 27-14, 
27-21 
Red River of the North at Pembina, N. Dak. (NCS) 
27-24 
Red River of the North Drainage Basin, Minn., S. 
Dak. and N. Dak. (NCS) 27-13, 27-21, 27-27 
Red River of the North, Halstad, Minn. (NCS) 27-13, 
27-21 
Red River Parish, La. (LMN) (LMK) 11-36, 12-25 
Red River Plan, Okla. and Tex. (SWT) 19-24 
Red River Standard Revetments (MR+T) 42-37 
Red River Waterway, La., Ark., Okla., and Tex. (LMN) 
(LMK) 11-38, 12-21 
Red River Waterway, La., Ark., Okla., and Tex., Index 
Ark. to Denison Dam (Tulsa District) (SWT) 19-3, 
19-18 
Red River Waterway-Mississippi River to Shreveport, 
La. (LMN) (LMK) 11-22, 12-5, 12-13, 12-17 
Red River Waterway, Shreveport, La., to Daingerfield, 
Tex. ((LMN) (LMK) 11-38, 12-21 
Red River Waterway-Shreveport, La., to Index, Ark. 
(LA) (LMK) 11-24, 12-10, 12-15, 12-18 
Red Rock Dam and Lake Red Rock, Iowa (NCR) 28-6, 
28-11, 28-15 
Red Run Drain-Lower Clinton River, Mich. (NCE) 
31-31, 31-51, 31-70 
Red Wing Harbor, Minn. (NCD) 29-8 
Redbank and Fanches Creeks, Calif. (SPK) 35-16 
Redbank Creek Lake, Pa. (ORP) 26-24 
Reddies River Lake, N.C. (SAN) 7-16 
Redmond, John, Dam and Reservoir, Kans. (SWT) 
19-9, 19-19 
Redondo Beach Harbor (King Harbor), Calif. (SPL) 
33-21 
Redwater River and Hay Creek, S.D. (MRO) 21-17 
Redwood City Harbor, Calif. (SPN) 34-6 
Redwood Creek, Humboldt County, Calif. (SPK) 35-24 
Redwood River below Marshall, Minn. (NCS) 27-24, 
27-28 
Reeds Bay Small Boat Harbor, Hawaii (POD) 36-14 
Reedsport Levees, Oreg. (NPP) 37-47 
Reedy River, S.C. (SAN) 7-16 
Reelfoot Lake-Lake No. 9, Tenn. and Ky. (MR+T) 
42-10, 42-19, 42-28 
Reese River, Battle Mountain, Nev. (SPK) 35-24 
Reevesville, Ill. (ORL) 24-21, 24-25, 24-30 
Regulation of Hydraulic Mining and Preparation of 
Plans (CDC) 44-1, 44-5, 44-6 
Regulatory and Sunken Vessel Removal and National 
Emergency Preparedness Activities 48-1 
Rehoboth Beach to Indian River Inlet, Del. (NAP) 3-26 
Removal of Aquatic Growth, La. (LMN) 11-14, 11-23, 
11-29 
Removal of Aquatic Growth from Navigable Waters in 
the State of Florida (SAJ) 9-14, 9-31, 9-40, 9-49 
Removal of Sunken Vessels 48-1 
Removing Snags and Wrecks from Mississippi River 
below Mouth of Missouri River and from Old and 
Atchafalaya Rivers (LMK) (LMM) 12-21, 13-10 
Removing Water Hyacinths, Mobile District (SAM) 
10-11, 10-25, 10-34 
Rend Lake, Ill. (LMS) 14-6, 14-10, 14-12 
Reno Beach-Howard Farms Area, Ohio (NCB) 32-15, 
32-20, 32-34 
Republican River, Nebr. and Kans. (MRK) 20-24 
Research Institute, 51-1 
Reservoir at Headwaters, of Mississippi River, Minn. 
(NCS) 27-2, 27-19, 27-22, 27-26 
Restoration of Indian Fishing Grounds, Bonneville, 
Oreg. (NPP) 37-48 
Revere Beach, Mass. (NED) 1-54 
Reynoldsville, Pa. (ORP) 26-23 
Rheem Creek, Calif. (SPK) 35-24 
Rhodes Point of Tylerton, Md. (NAB) 4-9, 4-25, 4-33 
Rice Creek, Fla. (SAJ) 9-50 
Richard B. Russell Dam and Lake, Ga. and S.C. 
(Formerly Trotters Shoals Lake) (SAS) 8-9, 8-12, 8-15 
Richland Creek, Ill. (LMS) 14-15 
Richland Lake, Mo. (MRK) 20-20 
Richmond Filtration Plant, Va. (NAO) 5-26 
Richmond Harbor, Maine (NED) 1-51 
Richmond's Island Harbor, Maine (NED) 1-51 
Richwood and Fenwick, W. Va. (ORH) 25-21 
Ridgecrest, Calif. (SPL) 33-23 
Ridgway, Pa. (Allegheny River Basin) (ORP) 26-27 
Ridgway, Pa. (Elk Creek) (ORP) 26-23 
Ridgway and Vicinity, Pa. (On Clarion River) (ORP) 
26-23 
Right and Left Forks of Beaver Creek, Ky. (OHR) 
25-21 
Rio Grande Basin, N. Mex. (SWA) 17-4, 17-10, 17-11, 
12-12 
Rio Grande Floodway, N. Mex. (SWA) 17-5, 17-10, 
17-11, 17-12 
Ripley, Ohio (ORH) 25-20 
Ripley, W. Va. (ORH) 25-21 
Ririe Lake, Idaho (NPW) 39-3, 39-11, 39-15 
Rising Sun, Ind. (ORL) 24-23, 24-26 
River Rouge, Mich. (NCE) 31-76 
Riverdale, Mass. (NED) 1-56, 1-61 
Riverland Levee District, Mo. (LMS) 14-15 
Riverside Area, Pasco, Wash. (NPW) 39-18 
Riverview, W. Va. (ORH) 25-20 
Roanoak Lake, Tex. (SWF) 16-23 
Roanoke River, N.C. (SAW) 6-7, 6-20 
Roanoke River Basin, Va. and N.C., John H. Kerr 
Dam and Reservoir (SAW) 6-16, 6-31 
Roanoke River Basin, Va. and N.C., Philpott Lake, 
Va. (SAW) 6-31 
1-35

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Roaring River, N.C. (SAN) 7-16 
Robert F. Henry Lock and Dam, Ala. (SAM) 10-16, 
10-26 
Robert S. Kerr Lock and Dam, Okla. (SWL) (SWT) 
18-19, 19-16, 19-21, 19-25 
Robert S. Kerr Marine Terminal, Sallisaw, Okla. 
(SWT) 19-25 
Roberts, Ray, Lake, Tex. (SWF) 16-10, 16-17, 16-21 
Rochester and McCleary's Bluff Levee, Ill. (ORL) 
24-21, 24-25, 29-30 
Rochester, Minn. (NCS) 27-14, 27-21 
Rochester, Pa. (ORP) 26-23, 26-27 
Rochester Harbor, N.Y. (NCB) 32-9, 32-19, 32-29 
Rochester Lake, Iowa (NCR) 28-18 
Rock Creek, Mont. (NPS) 38-27 
Rock Hall Harbor, Md. (NAB) 4-37 
Rock Island District (NCD) 29-5 
Rock Island Harbor, Ill. (NCD) 29-8 
Rock River Agricultural Levees, Ill. (NCR) 28-7, 28-11, 
28-15 
Rockfish Creek, N.C. (SAW) 6-29 
Rockford, Ill. (NCR) 28-7, 28-11, 28-15 
Rockland Harbor, Maine (NED) 1-52 
Rockland Lake, Tex. (SWF) 16-14, 16-21 
Rockport, Ind. (ORL) 24-23, 24-26, 24-31 
Rockport Harbor, Maine (NED) 1-52 
Rockport Harbor, Mass. (NED) 1-52 
Rocky Ford Drainage and Levee District, Ill. (NCR) 
28-17 
Rocky Fork, Ohio (ORH) 25-20 
Rocky Pass, Alaska (NPA) 40-12 
Rocky River Harbor, Ohio (NCB) 32-9, 32-19, 32-30 
Rodeo Creek, Calif. (SPK) 35-24 
Rodgers City Harbor, Mich. (NCE) 31-77 
Rogue River, Oreg. (NPP) 37-47 
Rogue River Harbor at Gold Beach, Oreg. (NPP) 37-8, 
37-27, 37-36 
Roland Drainage District, Arkansas River, Ark. (SWL) 
18-16 
Rollinson Channel, N.C. (SAW) 6-7, 6-20, 6-29 
Rome, Ga. (SAM) 10-39 
Rome, Ind. (ORL) 24-23, 24-26 
Rome, N.Y. (NAN) 2-35 
Rondout Harbor, N.Y. (NAN) 2-30, 2-31 
Root Creek, Bolivar, N.Y. (ORP) 26-5, 26-14 
Rose Creek Channel Improvements, San Diego, Calif. 
(SPL) 33-23 
Roseau River, Minn. (NCS) 27-14, 27-21 
Rosedale Harbor, Miss. (LMK) 12-5, 12-13, 12-17 
Rosendale, N.Y. (NAN) 2-33 
Roseville, Ohio (ORH) 25-8, 25-14, 25-17, 25-21 
Roseclare, Ill. (ORL) 24-21, 24-30 
Rossview Reservoir, Ohio River Basin, Tenn. and Ky. 
(ORN) 23-13, 23-18 
Rota Harbor, Northern Marianas (POD) 36-3, 36-10 
Rouge River, Mich. (NCE) 31-24, 3148, 31-66, 31-77 
Rough River, Ky. (ORL) 24-20, 24-25 
Rough River Lake and Channel Improvements, Ky. 
(ORL) 24-11, 24-17, 24-28 
Rouses Point, Lake Champlain, N.Y. (NAN) 2-31 
Rouseville, Pa. (ORP) 26-23 
Rowlesburg Lake, W. Va. (ORP) 26-23 
Royal River, Maine (NED) 1-52 
Ruby River, Wheatly Bridge, near Twin Bridges, 
Mont. (MRO) 21-20 
Ruffy Brook, Minn. (NCS) 27-25 
Rufus Woods Lake, Wash. (NPS) 38-10, 38-16, 38-22 
Rush River, N. Dak. (NCS) 27-27, 27-28 
Rushford, Minn. (NCS) 27-24, 27-28 
Russell, Ky. (ORH) 25-19, 25-21 
Russell and Allison Levee, Ill. (ORL) 24-21, 24-25 
Russell, Richard B., Dam and Lake, Ga. and S.C. 
(SAS) 8-9, 8-12, 8-15 
Russian River Basin, Calif. (SPN) 34-3, 34-8, 34-9, 
34-11, 34-12 
Rutland, Otter Creek, Vt. (NAN) 2-33 
Rutledge Hollow Creek Channel Improvement, Poteet, 
Tex. (SWF) 16-23 
Rye Creek, Mont. (NPS) 38-27 
Rye Harbor, N.H. (NED) 1-52 
S 
Sabine-Neches Waterway, Tex. (SWG) 15-7, 15-14, 
15-22, 15-28, 15-30, 15-34 
Sabine River and Tributaries, Tex. (Echo to Morgan 
Bluff) (SWG) 15-27 
Sabula, Iowa (NCR) 28-17, 28-19 
Sackets Harbor, N.Y. (NCB) 32-11, 32-32, 32-36 
Saco, Mont. (MRO) 21-17, 21-20 
Saco River, Maine (NED) 1-12, 1-35, 1-47, 1-57 
Sacramento River, Calif. (CDC) 44-3, 44-5, 44-6, 44-7 
Sacramento River, Calif. (SPK) 35-1, 35-18, 35-21, 35-26 
Sacramento River and Tributaries, Calif. (CDC) 44-2, 
44-5 
Sacramento River and Tributaries, Calif., from Collinsville, 
to Shasta Dam (SPK) 35-11, 35-19, 35-22, 
35-27, 35-28 
Sacramento River Deep Water Ship Channel, Calif. 
(SPK) 35-16 
Sacred Heart Hospital, Yankton, S. Dak. (MRO) 21-17, 
21-20 
Sag Harbor, N.Y. (NAN) 2-31 
Saginaw River, Mich. (NCE) 31-25, 31-32, 31-48, 
31-66, 31-51, 31-70 
Saint John River Basin, Maine (NED) 1-25 
Saipan Small Boat Harbor, Northern Marianas (POD) 
36-14 
Sakonnet Harbor, R.I. (NED) 1-12, 1-35, 1-47, 1-57 
Sakonnet River, R.I. (NED) 1-52 
Salamanca, N.Y. (ORP) 26-23 
Salamonie Lake, Ind. (ORL) 24-12, 24-17 
Salem Church Lake, Va. (NAO) 5-26 
Salem Harbor, Mass. (NED) 1-52 
Salem River, N.J. (NAP) 3-9, 3-19 
Salina, Kans. (MRK) 20-19, 20-23 
Salinas River, Calif. (SPK) 35-24 
Saline Point, La. (LMN) (LMK) 11-36, 12-25 
1-36

INDEX 
Saline River, Ark. (LMK) 12-21 
Saline River and Tributaries, Ill. (ORL) 24-21, 24-31 
Salisbury, Conn. (NED) 1-29, 1-62 
Salkahatchie River, S.C. (SAN) 7-15 
Salmon Creek at Oakridge, Oreg. (NPP) 37-47 
Salmon River, Alaska (NPA) 40-6, 40-13 
Salmon River, Oreg. (NPP) 37-43 
Salmon River, Colchester, Conn. (NED) 1-18, 1-37, 
1-48, 1-61 
Salt Creek, Ohio (ORH) 25-19 
Salt Creek and Tributaries, Nebr. (MRO) 21-6, 21-11, 
21-14 
Salt Creek, Barnard, Kans. (MRK) 20-19 
Salt Lake City, Jordan River, Utah (SPK) 35-24 
Saluda River, S.C. (SAN) 7-16 
Salyersville, Ky. (ORL) 24-22 
Sam Rayburn Dam and Reservoir, Tex. (SWF) 16-14, 
16-17, 16-21 
Sammamish River, Wash. (NAS) 38-27 
San Antonio Channel Improvement, Tex. (SWF) 16-10, 
16-18, 16-21 
San Antonio Floodway, Tex. (SWF) 16-23 
San Diego Creek, Alice, Tex. (SWG) 15-27 
San Diego River and Mission Bay, Calif. (SPL) 33-4, 
33-12, 33-17 
San Diego River (Mission Valley), Calif. (SPL) 33-23 
San Diego (Sunset Cliffs), Calif. (SPL) 33-22 
San Francisco Bay and Delta Model, Calif. (SPN) 34-2, 
34-7 
San Francisco Bay to Stockton, Calif. (John F. Baldwin 
and Stockton Ship Channels) (SPK) (SPN) 34-2, 34-7, 
35-2, 35-18 
San Francisco Harbor, Calif. (SPN) 34-7, 34-10 
San Francisco Harbor and Bay (Removal of Drift), 
Calif. (SPN) 34-7 
San Francisco Marina (Gas House Cove), Calif. (SPN) 
34-10 
San Gabriel River, Tex. (SWF) 16-11, 16-18, 16-21 
San Gabriel River to Newport Bay (Surfside-Sunset and 
Newport Beach), Calif. (SPL) 33-8, 33-14, 33-19 
San Jacinto River Levee and Bautista Creek Channel, 
Calif. (SPL) 33-8, 33-14, 33-19 
San Joanquin River, Calif. (SPK) 35-3, 35-18, 35-26, 
35-27 
San Juan, P.R. (SAJ) 9-51 
San Juan Dam, Calif. (SPL) 33-27 
San Juan Harbor, P.R. (SAJ) 9-16, 9-32, 9-41, 9-49 
San Leandro Creek, Calif. (SPK) 35-24 
San Leandro Marina, Calif. (SPN) 34-3, 34-7 
San Leandro Marina (Breakwater), Calif. (SPN) 34-10 
San Lorenzo Creek, Calif. (SPK) (SPN) 34-11, 35-24 
San Lorenzo River, Calif. (SPK) 35-24 
San Luis Rey River, CAlif. (SPL) 33-11, 33-23 
San Pablo Bay and Mare Island Strait, Calif. (SPN) 
34-7, 34-11 
San Rafael Creek, Calif. (SPN) 34-10 
Sand Creek Channel Improvement, Kans. (SWT) 
19-24, 19-27 
Sand Hill Cove Beach, R.I. (NED) 1-54 
Sand Hill River, Minn. (NCS) 27-27, 27-28 
Sand Island, Hawaii (POD) 36-15 
Sand Lake, Okla. (SWT) 19-24 
Sandburg Creek, Spring Glen, N.Y. (NAN) 2-33, 2-37 
Sandusky Harbor, Ohio (NCB) 32-10, 32-19, 32-30 
Sandusky River, Ohio (NCB) 32-32 
Sandy Bay, Cape Ann, Mass. (NED) 1-57 
Sandy Bay (Harbor of Refuge), Cape Ann, Mass. (NED) 
1-52 
Sandy Drainage District, Oreg. (NPP) 37-46, 37-52 
Sandy Hook Bay, N.J. (NAN) 2-31 
Sandy Hook Bay at Leonardo, N.J. (NAN) 2-31 
Sandy Lake Reservoir, Minn. (NCS) 27-26 
Sandy River and Sleepy Lake, Oreg. (NPP) 37-46 
Sanford Reservoir (Lake Meredith), Okla. (SWT) 19-13 
Sangamon River (Mouth), Ill. (NCR) 28-17 
Sanitary District of Beardstown, Ill. (NCR) 28-19 
Santa Ana River Basin, Calif. (SPL) 33-8, 33-14, 33-19 
Santa Ana River Basin (and Orange County), Calif. 
(SPL) 33-8, 33-14, 33-19, 33-23, 33-27 
Santa Ana River Basin, Calif.: Devil, East Twin, and 
Warm Creeks Channel Improvements (SPL) 33-23 
Santa Ana River Main Stem, CAlif. (SPL) 33-10 
Santa Barbara Harbor, Calif. (SPL) 33-4, 33-12, 33-17 
Santa Clara River Levee Improvement, Calif. (SPL) 
33-23 
Santa Cruz County, Calif. (SPN) 34-10 
Santa Cruz Harbor, Calif. (SPN) 34-7 
Santa Fe River and Arroyo Mascaras, N. Mex. (SWA) 
17-6, 17-10, 17-11 
Santa Maria Valley Levees, Calif. (SPL) 33-9, 33-14, 
33-20 
Santa Paula Creek Channel and Debris Basins (including 
Mud Creek), Calif. (SPL) 33-9, 33-14, 33-20 
Santa Rosa Dam and Lake, N. Mex. (SWA) 17-6, 17-10 
Santa Rosa Wash (at Momolikot Dam and Lake St. 
Clair), Ariz. (SPL) 33-23 
Santee River, N.C. and S.C. (SAN) 7-15 
Sapelo Harbor, Ga. (SAS) 8-16 
Sardis, Ohio (ORH) 25-20 
Sardis Lake, Miss. (MR+T) 42-21, 42-57 
Sardis Lake, Okla. (SWT) 19-11, 19-20 
Sasanoa River, Maine (NED) 1-52 
Sasco Hill Beach, Fairfield, Conn. (NED) 1-54 
Satilla River, Ga. (SAS) 8-16 
Saugatuck Harbor and Kalamazoo River, Mich. (NCE) 
31-27, 31-49, 31-68 
Saugerties Harbor, N.Y. (NAN) 2-30, 2-31 
Sauk River, Wash. (NPS) 38-28 
Sauquoit Creek, Whitesboro, N.Y. (NAN) 2-36 
Sauvie Island Drainage District, Oreg. (NPP) 37-44, 
37-46, 37-52 
Savage River Dam, Md. (NAB) 4-38, 4-41 
Savanna Harbor, Ill. (NCD) 29-8 
Savannah Harbor, Ga. (SAS) 8-4, 8-11, 8-14 
Savannah River above Augusta, Ga. (SAS) 8-16 
Savannah River at Augusta, Ga. (SAS) 8-16 
Savannah River Basin, Ga. (SAS) 8-8, 8-17 
Savannah River below Augusta, Ga. (SAS) 8-5, 8-11, 
8-15 
Saw Mill River at Elmsford and Greenburgh, N.Y. 
(NAN) 2-16, 2-22, 2-28 
Sawmill Branch, S.C. (SAN) 7-8, 7-16 
1-37

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Saxon Harbor, Wis. (NCE) 31-28, 31-49, 31-69 
Saxonville, Mass. (NED) 1-29, 1-56, 1-63 
Saxtons River, Rockingham, Vt. (NED) 1-18, 1-37, 1-48 
Sayers, Foster Joseph, Dam, Pa. (NAB) 4-20, 4-29 
Saylorville Lake, Iowa (NCR) 28-7, 28-11, 28-15 
Scajaquada Creek, N.Y. (NCB) 32-15, 32-20 
Scappoose Drainage District, Oreg. (NPP) 37-17, 37-30, 
37-40, 37-52 
Scarboro River, Maine (NED) 1-52 
Schuyler, Nebr. (MRO) 21-21 
Schuylkill River, Pa. (NAP) 3-10, 3-19, 3-23, 3-24 
Schuylkill River above Fairmount Dam, Pa. (NAP) 
3-24 
Scioto River at Portsmouth, Ohio (ORH) 25-18 
Sciotoville, Ohio (ORH) 25-18 
Scituate, Mass. (NED) 1-29 
Scituate Harbor, Mass. (NED) 1-52 
Scoharie Creek, Middleburgh, N.Y. (NAN) 2-36 
Scott, W. Kerr, Dam and Reservoir, N.C. (SAW) 6-15, 
6-21 
Scott County Drainage and Levee District, Ill. (LMS) 
14-15 
Scotts Creek, Va. (NAO) 5-22 
Scranton, Pa. (NAB) 4-38, 4-41 
Scranton, Buffalo, N. Dak. (MRO) 21-20 
Scuppernong River, N.C. (SAW) 6-15, 6-21, 6-26 
Seahorn Drainage and Levee District, Ill. (NCR) 28-17, 
28-19 
Searsport Harbor, Maine (NED) 1-52 
Seaside Park, Conn. (NED) 1-54 
Seattle Harbor, Wash. (NPS) 38-6, 38-15, 38-20 
Sebasticook River, Hartland, Maine (NED) 1-26, 1-39, 
1-49 
Sebewaing, Mich. (NCE) 31-33, 31-51, 31-70 
Seekonk River, R.I. (NED) 1-52 
Seldovia Harbor, Alaska (NPA) 40-12 
Selkirk Shore State Park, N.Y. (NCB) 32-34 
Sergius Whitestone, Alaska (NPA) 40-12 
Sespe Creek at Fillmore, Calif. (SPL) 33-9, 33-15, 33-20 
Sesuit Harbor, Mass. (NED) 1-12, 1-35, 1-47 
Sevier River near Redmond, Utah (SPK) 35-24 
Sewage Lagoons, Vale, Oreg. (NPW) 39-4, 39-11, 39-15 
Sewage Treatment Plant, Missoula, Mont. (NPS) 38-28 
Seward, Nebr. (MRK) 20-19 
Seward Harbor, Alaska (NPA) 40-12 
Shad Landing State Park, Md. (NAB) 4-37, 4-40 
Shallotte River, N.C. (SAW) 6-7, 6-20 
Shark River, N.J. (NAN) 2-9, 2-21$, 2-27, 2-30 
Shawneetown, Ill. (ORL) 24-22, 24-25, 24-30 
Sheboygan Harbor, Wis. (NCE) 31-28, 31-50, 31-69 
Sheepshead Bay, N.Y. (NAN) 2-31, 2-35 
Sheffield, Mass. (NED) 1-29, 1-62 
Sheffield Lake Community Park, Ohio (NCB) 32-36 
Shelburne, N.H. (NED) 1-29, 1-56 
Sheldon Brook, Tarrytown, N.Y. (NAN) 2-36 
Shell Creek, Nebr. (MRO) 21-18 
Shelley Area, Idaho (NPW) 39-18, 39-20, 39-21 
Shelton Creek, Wash. (NAS) 38-28 
Shelton Ditch, Oreg. (NPP) 37-46 
Shenago River Lake, Pa. and Ohio (ORP) 26-9, 26-15, 
26-21 
Shepard Road, St. Paul, Minn. (NCS) 27-15, 27-21 
Sherburne, N.Y. (NAB) 441 
Sheridan, Wyo. (MRO) 21-17, 21-20 
Sherwood Island State Park, Conn. (NED) 1-13, 1-35, 
1-47 
Sheyenne River, N. Dak. (NCS) 27-15, 27-21, 27-25, 
27-28 
Shidler Lake, Okla. (SWT) 19-21, 19-20, 19-23 
Shields River, near Clyde Park, Mont. (MRO) 21-17, 
21-20 
Shilshole Bay, Seattle, Wash. (NPS) 38-24, 38-31 
Shinnecock Inlet, N.Y. (NAN) 2-31 
Shipyard River, S.C. (SAN) 7-6, 7-10, 7-13 
Shoal Harbor and Compton Creek, N.J. (NAN) 2-9, 
2-22, 2-27, 2-30 
Shoals, Ind. (ORL) 24-23 
Shobe Canyon, Oreg. (NPW) 39-18 
Shooters Island, N.Y. and N.J. (NAN) 2-10, 2-22, 2-27 
Shoreline Erosion Control Demonstration, Philadelphia, 
Pa. (NAP) 3-11 
Shoreline Erosion Control Work Under Special 
Authorization 
Detroit, Mich., District (NCE) 31-30 
Jacksonville, Fla., District (SAJ) 9-24 
Mobile, Ala., District (SMA) 10-12 
Philadelphia, Pa., District (NAP) 3-11 
Pittsburgh, Pa., District (ORP) 26-30 
Seattle, Wash., District (NPS) 38-5 
Short Beach, Conn. (NED) 1-54 
Shoshone River, Bank Protection, Lovell, Wyo. (MRO) 
21-20 
Shoshone River, Byron, Wyo. (MRO) 21-6, 21-11, 21-14 
Shoshone River, Lovell, Wyo. (MRO) 21-17, 21-20 
Shot Pouch Creek, S.C. (SAN) 7-8, 7-16 
Shrewsbury River, N.J. (NAN) 2-30, 2-31 
Shufflebarger Levee, Ind. (ORL) 24-23, 24-26 
Sid Simpson Project, Ill. (NCR) 28-17 
Silver Beach to Cedar Branch, Conn. (NED) 1-54 
Silver Lake Harbor, N.C. (SAW) 6-8, 6-20, 6-24 
Simmon Bay, N.C. (SAW) 6-28 
Simpson Creek, S.C. (SAN) 7-8, 7-16 
Sioux City, Iowa (MRO) 21-21 
Sioux Falls, S. Dak. (MRO) 21-17, 21-20 
Sistersville, Ohio (ORH) 25-20 
Sitka Harbor, Alaska (NPA) 40-12 
Siuslaw River, Oreg. (NPP) 37-8, 37-28, 37-36, 37-47 
Six Runs Creek, N.C. (SAW) 6-29 
Sixes Bridge Lake, Md. and Pa. (N) 4-40 
Skaggs Ferry, Black River, Ark. (SWL) 18-16 
Skagit River, Wash. (NPS) 38-24, 38-28, 38-30 
Skagit River, Wash. (Avon By-Pass) (NPS) 38-28 
Skagit River, Wash. (Levee and Channel Improvements) 
(NPS) 38-28 
Skagway Harbor, Alaska (NPA) 40-12 
Skagway River, Alaska (NPA) 40-6, 40-13 
Skamokawa Creek, Wash. (NPP) 37-9, 37-28, 37-36, 
37-49 
Skamokawa Creek Area, Wash. (NPP) 3744 
Skiatook Lake, Okla. (SWT) 19-12, 19-20, 19-23 
Skipanon Channel, Oreg. (NPP) 37-9, 37-28, 37-36 
Slauughter Creek, Md. (NAB) 4-37 
1-38

INDEX 
Slovan, Pa. (ORP) 26-23 
Small Boat Harbor Opposite Chester, Ill. (LMS) 14-13 
Small Boat Harbor Opposite Hamburg, Ill. (LMS) 14-13 
Small Navigation Project at Sioux City, Iowa (MRO) 
21-16 
Smelt Brook, Mass. (NED) 1-29, 1-56 
Smith Creek, Colo. (SWA) 17-7, 17-10, 17-11 
Smith Creek, Md. (NAB) 4-37 
Smith River, Oreg. (NPP) 37-43 
Smithfield, W. Va. (ORH) 25-21 
Smithland, Ky. (ORL) 24-22, 24-25 
Smithland Locks and Dam, Ky. (ORD) 22-3, 22-9 
Smiths Creek, Pamlico County, N.C. (SAW) 6-26 
Smiths Creek (Wilmington), N.C. (SAW) 6-26 
Smiths Ferry, Pa. (ORP) 26-24 
Smithville Channel, Little Platte River, Mo. (MRK) 
20-19 
Smithville Lake, Mo. (MRK) 20-8, 20-13, 20-17 
Smoky Hill, Saline, and Solomon Rivers (MRK) 20-24 
Smyrna River, Del. (NAP) 3-24, 3-27 
Snagging and Clearing Activities 
Buffalo, N.Y., District (NCB) 32-35 
Charleston, S.C., District (SAN) 7-7 
Louisville, Ky., District (ORL) 24-14, 24-32 
Mobile, Ala., District (SAM) 10-15 
Rock Island, Ill., District (NCR) 28-20 
Sacramento, Calif., District (SPK) 35-14 
St. Paul, Minn., District (NCS) 27-29 
Vicksburg, Miss., District (LMK) 12-12 
Walla Walla, Wash., District (NPW) 39-2 
Snake River, Idaho (NPW) 39-18 
Snake River, below Warren, Minn. (NCS) 27-29 
Snake River Downstream from Johnson Bar Landing, 
Oreg., Wash., and Idaho (NPW) 39-9, 39-12, 39-16, 
39-26 
Snettisham, Alaska (NPA) 40-6, 40-10, 40-12 
Snohomish River, Wash. (NPS) 38-28 
Snoqualmie River, Wash. (NPS) 38-28 
Sny Basin, Ill. (NCR) 28-17, 28-19 
Sny Island Levee Drainage District, Ill. (NCR) 28-17, 
28-19 
Soap Creek, Wash. (NPP) 37-49 
Socastee Creek, S.C. (SAN) 7-15 
Socorro Diversion Channel, Tributaries of Rio Grande, 
N. Mex. (SWA) 17-12 
Soleduck River Bridge, Wash. (NPS) 38-28 
Somerville Lake, Tex. (SWF) 16-11, 16-18, 16-22 
Sonoma Creek, Calif. (SPK) 35-24 
South Amsterdam, Mohawk River, N.Y. (NAN) 2-33 
South Bank Arkansas River, (Head Fourche Island to 
Pennington Bayou), Ark. (SWL) 18-16 
South Bank Arkansas River, Little Rock to Pine Bluff, 
Ark. Tucker Lakes (SWL) 18-16 
South Bank White River, Petersburg, Ind. (ORL) 24-31 
South Beardstown and Valley Drainage and Levee 
District, Ill. (NCR) 28-17 
South Beardstown Drainage and Levee District, Ill. 
(NCR) 28-17, 28-19 
South Beloit, Ill. (NCR) 28-17 
South Bristol Harbor, Maine (NED) 1-52 
South Channel, Government Island, Oreg. (NPP) 37-9, 
37-28, 37-37 
South Coventry Lake, Conn. (NED) 1-57 
South Creek, N.C. (SAW) 6-28 
South Deer Creek Levee, Okla. (SWT) 19-27 
South Ellenville, N.Y. (NAN) 2-17, 2-22, 2-28 
South Fabius River, Mo. (NCR) 28-8, 28-11, 28-15 
South Fork, Clearwater River, Idaho (NPW) 39-18, 
39-20 
South Fork of Cumberland River, Ky. (ORN) 23-13 
South Haven Harbor, Mich. (NCE) 31-28, 31-50, 31-69 
South Milwaukee Harbor, Wis. (NCE) 31-77 
South Orange, N.J. (NAN) 2-33 
South Platte River, Bank Protection, Denver, Colo. 
(MRO) 21-6, 21-14 
South Platte River Basin, Colo. (MRO) 21-6, 21-14 
South Platte River Levees and Channel Improvements, 
Chatfield Lake to Ft. Morgan, Colo. 
(MRO) 21-17 
South Plymouth Lake, N.Y. (NAB) 4-40 
South Point, Ohio (ORH) 25-19 
South Portsmouth, Ky. (ORH) 25-19 
South Quincy Drainage and Levee District, Ill. (NCR) 
28-17, 28-19 
South River, N.C. (SAW) 6-26 
South River Drainage District, Mo. (NCR) 28-17, 28-19 
South Slough (Charleston), Oreg. (NPP) 37-43 
South St. Paul, Minn. (NCS) 27-28 
South Tunbridge Lake, Vt. (NED) 1-57 
South Williamson, Ky. (ORH) 25-21 
South Williamsport, Pa. (NAB) 4-41 
Southern Branch, Va. (NAO) 5-21 
Southern New York Flood Control Projects (NAB) 
4-14, 4-35 
Southport Beach, Conn. (NED) 1-54 
Southport Harbor, Conn. (NED) 1-52 
Southwest Harbor, Maine (NEO) 1-52 
Southwestern Jefferson County, Ky. (ORL) 24-5, 24-15 
Sowashee Creek, Meridian, Miss. (SAM) 10-39 
Spanish Fork River, Utah (SPK) 35-26 
Spewrell Bluff Lake, Ga. (SAM) 10-20, 10-27, 10-36 
Spirit Lake, Wash. (NAS) 38-28 
Spokane, Wash. (NAS) 38-28 
Spring City, Tenn. (ORN) 23-19 
Spring Creek Channel Improvement, Springdale, Ark. 
(SWT) 19-24 
Spring Lake Drainage and Levee District, Ill. (NCR) 
28-17, 28-19 
Springdale, Mass. (NED) 1-56, 1-61 
Springdale, Levee, Ark. (SWT) 19-27 
Springer, William L., Lake, Ill. (NCR) 28-17 
Springfield, Mass. (NED) 1-29, 1-61 
Squantz Pond, New Fairfield, Conn. (NED) 1-22, 1-38, 
1-48, 1-62 
Squaw Chute at Quincy, Ill. (NCR) 28-15 
St. Albans Harbor, Lake Champlain, Vt. (NAN) 2-31 
St. Anthony Falls, Lower Lock and Dam, Minn. (NCD) 
29-6, 29-10 
St. Anthony Falls, Upper Lock, Minn. (NCD) 29-6 
St. Augustine Harbor, Fla. (SAJ) 9-14, 9-31, 940, 9-49 
St. Catherines Sound, Md. (NAB) 4-37 
St. Clair River, Mich. (NCE) 31-26, 31-49, 31-67, 31-71, 
1-39

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
31-77 
St. Croix River, Maine (NED) 1-52 
St. Croix River, Minn. and Wis. (NCS) 27-2, 27-19, 
27-22 
St. Francis and L'Anguille Rivers and Blackfish 
Bayou, Ark. (LMM) 13-10 
St. Francis Basin, Ark. and Mo. (MR+T) 42-9, 42-28 
St. Francis River and Basin, Ark. and Mo. (MR�T) 
42-19, 42-53 
St. Francis River Levees (MR+T) 42-48 
St. George Creek, Md. (NAB) 4-9, 4-25, 4-33, 4-37 
St. James, Beaver Island, Mich. (NCE) 31-75 
St. James Harbor, Mich. (NCE) 31-74 
St. Jeromes Creek, Md. (NAB) 4-37 
St. Johns River, Fla. (SAJ) 9-37 
St. Johns River, Fla., Jacksonville to Lake Harney 
(SAJ) 9-15, 9-31, 940, 9-49 
St. Johns River, Fla., Jacksonville to the Ocean (SAJ) 
9-37 
St. Johns River, Fla., Opposite the City of Jacksonville 
(SAJ) 9-37 
St. Jones River, Del. (NAP) 3-24, 3-25 
St. Joseph Harbor, Mich. (NCE) 31-26, 31-49, 31-67 
St. Joseph River, Mich. (NCE) 31-75 
St. Louis County Drainage and Levee District No. 1, 
Mo. (LMS) 14-15 
St. Louis District (NCD) 29-5 
St. Lucie Inlet, Fla. (SAM) 10-37, 10-38 
St. Maries, Idaho (NAS) 38-27 
St. Marks River, Fla. (SAM) 10-37, 10-38 
St. Marys, Pa. (ORP) 26-24 
St. Marys, W. Va. (ORH) 25-20 
St. Marys River, Ga. and Fla., and North River, Ga. 
(SAS) 8-16 
St. Marys River, Mich. (NCE) 31-27, 31-49, 31-67, 
31-72, 31-77 
St. Michael Canal, Alaska (NPA) 40-12 
St. Michael Harbor, Md. (NAB) 4-37, 440 
St. Patricks Creek, Md, (NAB) 4-10, 4-25, 4-33 
St. Paul and South St. Paul, Minn. (NCS) 27-24, 27-28 
St. Paul District (NCD) 29-5 
St. Paul Harbor, Minn. (NCD) 29-8 
St. Peters Creek, Md. (NAB) 4-37, 440 
St. Petersburg Harbor, Fla. (SAJ) 9-16, 9-32, 9-41 
St. Thomas Harbor, V.I. (SAJ) 9-50 
Ste. Genevieve County Drainage and Levee District 
No. 1, Mo. (LMS) 14-15 
Stamford, Conn. (NED) 1-27, 1-29, 1-39, 149 
Starlings Creek, Va. (NAO) 5-25, 5-27 
Startup, Wash. (NAS) 38-28 
Starved Rock Lock and Dam, Ill. (NCC) 28-21, 28-22 
State Road and Ebner Coulees, Wis. (NCS) 27-16, 27-21 
Staten Island, N.Y. (NAN) 2-17, 2-22, 2-28 
Staten Island Rapid Transit Railway Co. Bridge Across 
Arthur Kill, N.Y. 2-31 
Station Road, Irvington, N.Y. (NAN) 2-37 
Steinhatchee River, Fla. (SAJ) 9-50 
Stewart Canyon Debris Basin and Channel, Calif. 
(SPL) 33-23 
Stikine River, Alaska (NPA) 40-5, 40-9, 40-11 
Stillaguamish River, Wash. (NPS) 38-9, 38-16, 38-22, 
38-24, 38-28 
Stillhouse Hollow Dam, Tex. (SWF) 16-12, 16-18, 16-22 
Stillwater Lake, Pa. (NAB) 4-18, 4-28, 4-35 
Stillwater River, Mont. (NPS) 38-28 
Stillwell Drainage District, Oreg. (NPP) 37-47 
Stockton and Mormon Channels, Calif. (SPK) 35-23 
Stockton Harbor, Maine (NE) 1-52 
Stockton Lake, Mo. (MRK) 20-9, 20-14, 20-18, 20-23 
Stone Harbor, N.J. (NAP) 3-26 
Stonehouse Creek, Kans. (MRK) 20-19 
Stonewall Jackson Lake, W. Va. (ORP) 26-9, 26-16, 
26-21 
Stonington Harbor, Conn. (NED) 1-52 
Stonington Harbor, Maine (NED) 1-27, 1-39, 1-49, 1-57 
Stony Brook, Wilton, N.H. (NED) 1-56 
Stony Creek, Branford, Conn. (NED) 1-52 
Stratford, Conn. (NED) 1-57 
Streambank Erosion Control Evaluation and Demonstration 
Project 
Huntington, W. Va., District (ORH) 25-10 
Louisville, Ky., District (ORL) 24-14 
New England Division (NED) 1-30 
Omaha, Nebr., District (MRO) 21-9, 21-12, 21-15 
Pittsburgh, Pa., District (ORP) 26-30 
Portland, Oreg., District (NPP) 37-7 
Rock Island, Ill., District (NCR) 28-8 
Seattle, Wash., District (NPS) 38-5 
Strington, Ft. Chartres and Ivy Landing, Ill. (LMS) 
14-15 
Strong Creek, Idaho (NPS) 38-28 
Strube Lake & Cougar Additional Unit, (South Fork 
McKenzie) (Modification to Cougar Lake) Oreg. 37-53 
Stuart Gulch Dam, Boise, Idaho (NPW) 39-19 
Stumpy Point Bay, N.C. (SAW) 6-26 
Sturgeon Bay and Lake Michigan Ship Canal, Wis. 
(NCE) 31-29, 31-50, 31-69 
Sturgis, Ky. (ORL) 24-21, 24-25, 24-30 
Subdistrict No.1 of Drainage Union No. 1 and Bay 
Island Drainage and Levee District No. 1, Ill. (NCR) 
28-17, 28-19 
Sucker Brook, Conn. (NED) 1-26, 1-56, 1-60 
Sugar Creek Basin, N.C. and S.C. (SAN) 7-17 
Sugar Creek Levee, Ind. (ORL) 24-23, 24-26 
Sugar Hill Reservoir, N.H. (NED) 1-57 
Suisun Bay Channel, Calif. (SPK) (SPN) 34-7, 35-23 
Suisun Channel, Calif. (SPK) (SPN) 34-8, 35-23 
Suisun Point Channel, Calif. (SPK) 35-23 
Sullivan Falls Harbor, Maine (NED) 1-52 
Sulphur River, Ark. and Tex. (LMN) 11-34 
Sulphur River Levees, Tex. (SWF) 16-23 
Summersville Lake, W. Va. (ORH) 25-9, 25-14, 25-17 
Sumner Parker Airport, Oreg. (NPP) 3747 
Sumpawanus (Babylon Creek) Inlet, N.Y. (NAN) 2-31 
Sun Creek, Miss. (SAM) 10-14, 10-26, 10-35 
Sunbury, Pa. (NAB) 4-38, 4-41 
Sunken Vessel Removal 48-1 
Supervision of the Harbor of Hampton Roads (Prevention 
of Obstructive and Injurious Deposits) (NAO) 
5-9, 5-17 
Supervisor of New York Harbor (NAN) 2-10, 2-22, 2-29 
Surry Mountain Lake, N.H. (NED) 1-19, 1-37, 1-60 
1-40

INDEX 
Surveillance of Northern Boundary Waters (NCE) 
31-34, 31-51 
Susquehanna River above and below Havre De Grace, 
Md. (NAB) 4-37 
Susquehanna River at Williamsport, Pa. (NAB) 4-37 
Susquehanna River Flood Control Projects, N.Y. and 
Pa. (NAB) 4-19, 4-35 
Sutton Lake, W. Va. (ORH) 25-9, 25-14, 25-17 
Suwannee River, Fla. (SAJ) 9-50 
Swanton Harbor, Vt. (NAN) 2-35 
Sweetwater Creek, N.C. (SAW) 6-29 
Sweetwater River, Calif. (SPL) 33-9, 33-15, 33-20 
Swift Creek, N.C. (SAW) 6-26 
Swiftcreek, Pitt and Craven Counties, N.C. (SAW) 6-28 
Swinomish Channel, Wash. (NPS) 38-6, 38-15, 38-20 
Swoyersville, and Forty Fort, Pa. (NAB) 4-38, 4-41 
Sykesville, Pa. (ORP) 26-23 
Syracuse, N.Y. (NCB) 32-34 
Syracuse, Ohio (ORH) 25-20
T 
T.J. O'Brien Lock and Dam, Ill. (NCC) 28-22, 28-23 
Table Rock Lake, Mo. (SWL) 18-8, 18-12, 18-23 
Tacoma, Wash. (NPS) 38-9, 38-16, 38-22 
Tacoma Harbor, Wash. (NPS) 38-7, 38-15, 38-21, 38-31 
Tahchevah Creek Detention Basin and Channel Improvements, 
Calif. (SPL) 33-24 
Tahola, Wash. (NPS) 38-28 
Tahquitz Creek, Calif. (SPL) 33-24 
Talkeetna River, Alaska (NPA) 40-13 
Tallahala Creek Lake, Miss. (SAM) 10-13, 10-25, 10-35 
Tallahatchie and Coldwater Rivers, Miss. (LMK) 12-21 
Tallapoosa River, Ala. (SAM) 10-38 
Tallow Hill, Ga. (SAS) 8-17 
Talofofo Bay Shore Protection, Guam (POD) 36-16 
Tamaqua, Pa. (NAP) 3-16, 3-20 
Tampa and Hillsborough Bays, Fla. (SAJ) 9-42 
Tampa Bay, Fla. (SAJ) 9-41 
Tampa Harbor, Fla. (SAJ) 9-17, 9-32, 9-42 
Tangeman, Nebr. (MRO) 21-21 
Tangier Channel, Va. (NAO) 5-10, 5-17, 5-23 
Tangipahoa River, La. (LMN) 11-15, 11-23, 11-29 
Tar River, N.C. (SAW) 6-28 
Tar River and Tributaries, N.C. (SAW) 6-28 
Tar River, Princeville, N.C. (SAW) 6-28 
Tarentum, Pa. (ORP) 26-23 
Tarrrytown Harbor, N.Y. (NAN) 2-31 
Taskinas Creek, Va. (NAO) 5-25 
Tau Small Boat Harbor, American Samoa (POD) 36-4, 
36-11, 36-16 
Taunton River, Mass. (NED) 1-52 
Tawas Bay Harbor, Mich. (NCE) 31-74, 31-75 
Taylors Bayou, Tex. (SWG) 15-11, 15-15, 15-26 
Taylorsville, Ky. (ORL) 24-21, 24-25, 24-30 
Teche-Vermilion Basins, La. (Water Supply) (MR+T) 
42-7, 42-15, 42-28, 42-50 
Telegraph Canyon Creek, Calif. (SPL) 31-27 
Tell City, Ind. (ORL) 24-21, 24-25, 24-30 
Tenants Harbor, Maine (NED) 1-52 
Tenasillahe Island, Oreg. (NPP) 37-45 
Tenkiller Ferry Lake, Okla. (SWL) (SWT) 18-21, 19-16, 
19-21, 19-25 
Tenmile Creek at Marianna, Pa. (ORP) 26-23 
Tennessee River, Tenn., Ala., and Ky. (ORN) 23-3, 
23-9, 23-11, 23-17, 23-18 
Tennessee-Tombigbee Waterway, Ala. and Miss. 
(ORN) 23-4, 23-9, 23-12 
Tensas Basin, Ark. and La. (MR+T) 42-7, 42-16, 
42-28 
Tensas River and Bayou Macon, La. (LMK) 12-21 
Tensas River National Wildlife Refuge (MR+T) 42-28 
Terrain Analysis Center 51-1 
Terre Haute (Conover Levee), Ind. (ORL) 24-21, 24-30 
Terre Noire Creek, Ark. (LMK) 12-22 
Terry, David D., Lock and Dam, Ark. (SWL) 18-2, 
18-18 
Teton River, Idaho (NPW) 39-18, 39-20 
Texas City and Vicinity, Tex., Hurricane-Flood Protection 
(SWG) 15-11, 15-15, 15-26 
Texas City Channel, Tex. (SWG) 15-7, 15-14, 15-24, 
15-28 
Thames River, Conn. (NED) 1-52 
Thames River Basin, Conn., R.I., and Mass. (NED) 
1-27, 1-29, 1-64 
The Cascades Canal, Oreg. (NPP) 37-43 
The Dalles-Celilo Canal, Oreg. and Wash. (NPP) 37-43 
The Dalles Lock and Dam-Lake Celilo, Wash. and 
Oreg. (NPP) 37-24, 37-31, 37-41, 37-55 
The Island Lake, Vt. (NED) 1-57 
The Sny Basin, Ill. (NCR) 28-19 
Thimble Shoal Channel, Va. (NAO) 5-11, 5-17, 5-23, 
5-27 
Thomaston Dam, Conn. (NED) 1-22, 1-38, 1-61 
Thoroughfare Swamp, N.C. (SAW) 6-29 
Three Forks, Mont. (MRO) 21-20 
Three Islands Reservoir, Tenn. (ORN) 23-14 
Three Rivers, Mass. (NED) 1-29, 1-56, 1-61 
Three Rivers, Tex. (SWF) 16-12, 16-18, 16-22 
Thumpertown Beach, Eastham, Mass. (NED) 1-57 
Tickfaw, Natalbany, Ponchatoula, and Blood Rivers, 
La. (LMN) 11-34 
Ticonderoga River, N.Y. (NAN) 2-35 
Tijuana River Basin, Calif. (SPL) 33-23 
Tilgham Island Harbor, Md. (NAB) 4-10, 4-26, 4-33, 
4-41 
Tillamook Bay and Bar, Oreg. (NPP) 37-9, 37-28, 37-37 
Tioga-Hammond Lakes, Pa. (NAB) 4-19, 4-29 
Tionesta Lake, Pal. (ORP) 26-10, 26-16, 26-21 
Toad Suck Ferry Lock & Dam, Ark. (SWL) 18-4, 18-18 
Tocks Island Lake, Pa., and N.Y. (NAP) 3-27 
Tocks Island (Relocation of U.S. Route 209 Only) Pa. 
(NAP) 3-27 
Todd Swamp, NS.C. (SAN) 7-8, 7-16 
Toledo Harbor, Ohio (NCB) 32-10, 32-19, 32-30 
Tolovana River, Alaska (NPA) 40-13 
Tolu, Ky. (ORL) 24-22, 24-25 
1-41

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Tom Jenkins Dam, Ohio (ORH) 25-14, 25-17 
Tom Jenkins Reservoir, Ohio (ORH) 25-9 
Tomahawk Lake, Kans. (MRK) 20-19 
Tomanovich-Salmon City, Idaho (NPW) 39-18, 39-21 
Tombigbee River, Miss. and Ala. (SAM) 10-39 
Tombigbee River Tributaries, Miss. and Ala. (SAM) 
10-14, 10-26, 10-35 
Toms River, N.J. (NAP) 3-24, 3-27 
Tongue River Lake, N. Dak. (NCS) 27-24 
Topeka, Kans. (MRK) 20-19, 20-23 
Topographic Laboratory 51-1 
Topsoil Beach, N.C. (SAW) 6-29 
Toronto Lake, Kans. (SWL) (SWT) 18-21, 19-12, 19-20, 
19-25 
Torrington, Conn. (NED) 1-29, 1-56, 1-62 
Totuskey Creek, Va. (NAO) 5-25 
Trinity River Project, Tex. (SWF) 16-2, 16-16, 16-22 
Triplett Creek, Morehead, Ky. (ORL) 24-21 
Ti-Pond Levee, Ill. (ORL) 24-23, 24-26 
Trotters Shoals Lake (SAS) 8-9, 8-12, 8-15 
Troublesome Creek, Hindman, Ky. (ORL) 24-31 
Troy, Ind. (ORL) 24-23, 24-26, 24-31 
Truckee River and Tributaries, Calif. and Nev. (SPK) 
35-24 
Truman, Harry S., Dam and Reservoir, Mo. (MRK) 
20-9, 20-13, 20-18, 20-23 
Trumbull Lake, Conn. (NED) 1-23, 1-38, 1-49 
Trussville, Ala. (SAM) 10-39 
Truth of Consequences (Hot Springs) Unit, N. Mex. 
(SWA) 17-6, 17-11, 17-12 
Tualatin, Oreg. (NPP) 37-18, 37-30, 37-40 
Tucannon River, Camp Wooten, Wash. (NPW) 39-18 
Tuckahoe River, Md. (NAB) 4-37 
Tuckerton Creek, N.J. (NAP) 3-24 
Tucson Diversion Channel, Ariz. (SPL) 33-23 
Tug and Levisa Forks of the Big Sandy River and 
Cumberland River, W. Va., Va., and Ky. (ORN) 23-6, 
23-9 
Tully Lake, Mass. (NED) 1-19, 1-37, 1-60 
Tulsa and West Tulsa Levee, Okla. (SWT) 19-24, 19-27 
Turkey Creek, S.C. (SAN) 7-8, 7-16 
Turner Prairie, Mill Creek, Oreg. (NPP) 37-49 
Turtle Creek, Pa. (ORP)26-23 
Turtle Creek Channel Improvement, Yukon, Okla. 
(SWT) 19-24 
Tuskahoma Lake, Okla. (SWT) 19-24, 19-26 
Tuttle Creek Lake, Kans. (MRK) 20-8, 20-13, 29-18, 
20-23 
Tuttle Creek Lake (Road Improvement), Kans. (MRK) 
20-23 
Twelvemile Bayou, La. (LMN) (LMK) 11-36, 12-25 
Twin Valley Lake, Wild Rice River, Minn. (NCS) 27-24 
Twitch Cove and Big Thorofare, Md. (NAB) 4-37 
Two Harbors, Minn. (NCE) 31-29, 31-50, 31-69 
Two Rivers Dam, N. Mex. (SWA) 17-7, 17-10 
Two Rivers Harbor, Wis. (NCE) 311-74, 31-75 
Tyaskin Creek, Md. (NAB) 4-37, 4-41 
Tybee Island, Ga. (SAS) 8-6, 8-11, 8-15 
Tygart Lake, W. Va. (ORP) 26-3, 26-14, 2619 
Tylers Beach, Va. (NAO) 5-25 
Tyrone, Pa. (NAB) 4-38, 4-41 
U 
Umatilla Harbor, Oreg. (NPP) 37-43 
Umatilla River (ECHO), Oreg. (NPP) (NPW) 37-49, 
37-18 
Umpqua River, Oreg. (NPP) 37-10, 37-28, 37-37, 37-47 
Umpqua River and Tributaries, Oreg. (NPP) 37-47 
Unadilla, N.Y. (NAB) 4-38, 4-41 
Unio City Dam, Pa. (ORP) 26-11, 26-16, 26-21 
Union Lake, Mo. (LMS) 14-15 
Union River, Maine (NED) 1-52 
Union Township Drainage District, Mo. (NCR) 28-17, 
28-19 
Union Village Dam, Vt. (NED) 1-19, 1-37, 1-60 
Uniontown, Ky. (ORL) 24-21, 24-25, 24-30 
Uniontown, Pa. (ORP) 26-24 
Uniontown Locks and Dam, Ky. (ORL) 22-3, 22-9 
University Wash and Spring Brook, Riverside, Calif. 
(SPL) 33-23 
Upper Chipola River, Fla., from Mariana to its mouth 
(SAM) 10-38 
Upper Grand River, Mo. (MRK) 20-19 
Upper Grays River Area, Wash. (NPP) 37-45 
Upper Iowa River, Iowa (NCS) 27-24, 27-28 
Upper Machodoc Creek, Va. (NAB) 4-37, 4-41 
Upper Marlboro, Md. (NAB) 4-38, 4-41 
Upper Puyallup River, Wash. (NAS) 38-28 
Upper River Road, Jefferson Co., Ky. (ORL) 24-31 
Upper River Rouge, Mich. (NCE) 31-76 
Upper Thorofare, Deal Island, Md. (NAB) 4-37 
Upper White Oak Bayou and Tributaries, Tex. (SWG) 
15-13 
Upper White River, Ark. (SWL) 18-15 
Upper Yazoo Levee, Miss. (MR+T) 42-11 
Urban Areas at Alton, Ill. (LMS) 14-15 
Urbanna Creek, Va. (NAO) 5-25 
U.S. Highway 51, Tenn. (LMM) 13-4, 13-7, 13-8 
Utica, Ind. (ORL) 24-23, 24-27 
Utica, Ohio (ORH) 25-19, 25-21 
V 
Valdez Harbor, Alaska (NPA) 40-12 
Vale, Oreg. (NPW) 39-21 
Valley City Drainage and Levee District, Ill. (LMS) 
14-15 
Valley Drainage and Levee District, Ill. (NCR) 28-19 
Van Buren, Arkansas River, Ark. (SWL) 18-16 
Van Meter, Iowa (NCR) 28-17, 28-19 
Vanceburg, Ky. (ORH) 25-19 
Vancouver Lake Area, Wash. (NPP) 37-46 
Vatia Area, American Samoa (POD) 36-15 
Vaughn, Mont. (MRO) 21-17, 21-20 
Velva, N. Dak. (NCS) 27-24, 27-28 
Ventnor, Margate and Longport, N.J. (NAP) 3-26 
Ventura Marina (Venture Harbor), Calif. (SPL) 33-4, 
33-12, 33-17 
142

INDEX 
Ventura-Pierpont Area, Calif. (SPL) 33-22 
Ventura River Basin, Calif. (SPL) 33-23 
Vermilion Harbor, Ohio (NCB) 32-11 
Vermilion Lock, La. (Replacement of Lock) (LMN) 
11-10, 11-22, 11-28 
Vermillion River, S.D. (MRO) 21-18 
Vermillion River, Hastings, Minn. (NCS) 27-24 
Verona Lake, Va. (NAB) 4-38 
Veteran's Memorial Levee, Hastings, Minn. (NCS) 
27-16, 27-21 
Vevay, Ind. (ORL) 24-23, 24-26 
Vicinity of Nehalam, Oreg. (NPP) 37-47 
Vicksburg Harbor, Miss. (MR+T) 42-29 
Victory Lake, Vt. (NED) 1-57 
Villa Park Dam, Calif. (SPL) 33-24, 33-27 
Village Creek, S.C. (SAN) 7-6, 7-10, 7-14 
Village Creek, Jackson & Lawrence Counties, Ark. 
(SWL) 18-16, 18-23 
Village Creek, White River, and Mayberry Levee 
District, Ark. (SWL) 18-14, 18-16 
Village of New Athens, Ill. (LMS) 14-15 
Vince and Little Vince Bayous, Tex. (SWG) 15-11, 
15-15, 15-26 
Vincennes, Ind. (ORL) 24-21, 24-25, 24-30 
Vineyard Haven, Mass. (NED) 1-52 
Vinton Waterway, La. (LMN) 11-34 
Virginia Beach, Va. (NAO) 5-12, 5-17, 5-23 
Virginia Beach Streams Canal Number 2, Va. (NAO) 
5-13, 5-18, 5-23 
Virginia Key and Key Biscayne, Fla. (SAJ) 9-51 
W 
W.D. Mayo Lock and Dam, Okla. (SWL) (SWT) 18-19, 
19-25 
W. Kerr Scott Dam and Reservoir, N.C. (SAW) 6-15, 
6-21 
W.P. Franklin Lock and Dam, Fla. (SAJ) 9-52 
Wabash Railroad Bridges, Illinois River, Meredosia, 
and Valley City, Ill. (LMS) 14-13 
Wabash River Basin, Ind., Ill., and Ohio (ORL) 24-13, 
24-20, 24-29 
Wabash Harbor, Minn. (NCD) 29-8 
Waccamaw River, N.C. and S.C. (SAN) 7-17 
Waccamaw River and Seven Creeks, N.C. and S.C. 
(SAN) (SAW) 6-28, 7-15 
Waco Lake, Tex. (SWF) 16-12, 16-18, 16-22 
Wahkiakum County Consolidated Diking District No. 
1, Wash. (NPP) 37-18, 37-30, 37-40, 37-52 
Wahkiakum County Diking District 4, Wash. (NPP) 
37-46, 37-52 
Waianae Small Boat Harbor, Hawaii (POD) 36-14, 
36-16 
Waikiki Beach, Hawaii (POD) 36-15 
Wailoa Stream and Tributaries, Hawaii (POD) 36-9, 
36-15 
Waimea Beach, Hawaii (POD) 36-15 
Waimea River, Hawaii (POD) 36-8, 36-11 
Wake Island Harbor, Wake Island (POD) 36-14 
Waldo Lake Tunnel and Reregulating Works, Oreg. 
(NPP) 37-49, 37-53 
Walla Walla, Wash. (NPW) 36-21 
Wallabout Channel, N.Y. (NAN) 2-31 
Wallace, W. Va. (ORP) 26-23 
Wallace Channel, Pamlico Sound, N.C. (SAW) 6-26 
Wallace Lake, La. (LMN) (LMK) 11-24, 12-11, 12-15, 
12-18, 12-22 
Wallis Sands State Beach, N.H. (NED) 1-54 
Wallisville Lake, Tex. (SWG) 15-8 
Wallowa River, Oreg. (NPW) 39-18 
Walluski River, Oreg. (NPP) 37-45 
Walnut Bayou Channel Improvement, Ark. (SWT) 
19-27 
Walnut Creek, Calif. (SPK) 35-12, 35-19 
Walter, Francis E., Dam, Pa. (NAP) 3-13, 3-19 
Walter F. George Lock and Dam, Ala. and Ga. (SAM) 
10-20, 10-27, 10-36 
Walters Slough, N.C. (SAW) 6-30 
Wappapello Lake, Mo. (MR�T) 42-21, 42-57 
Wappinger Creek, N.Y. (NAN) 2-31 
Wappinger Creek at Pleasant Valley, N.Y. (NAN) 2-33 
Ware, Mass. (NED) 1-27, 1-56, 1-61 
Wareham Harbor, Mass. (NED) 1-52 
Wareham-Marion, Mass. (NED) 1-57 
Warren River, R.I. (NED) 1-52 
Warrenton Diking Districts 1, 2, and 3, Oreg. (NPP) 
37-45 
Warroad Harbor and River, Minn. (NCS) 27-3, 27-19, 
27-22, 27-25 
Warroad River and Bull Dog Creek, Minn. (NCS) 27-24 
Warsaw, N.Y. (NCB) 32-34 
Warsaw Harbor, Ill. (NCD) 29-9 
Warwick Cove, R.I. (NED) 1-52 
Warwick River, Md. (NAB) 4-10, 4-26, 4-33 
Warwood, W. Va. (ORP) 26-23, 26-27 
Washington, D.C. and Vicinity (NAB) 4-38, 4-41 
Washington, Pa. (ORP) 26-23 
Washington Aqueduct (NAB) 4-22 
Washington Canal and South River, N.J. (NAN) 2-31 
Washington Harbor, D.C. (NAB) 4-10, 4-26, 4-33 
Washington, D.C. and Vicinity (NAB) 4-38, 4-41 
Washington, Pa. (ORP) 26-23 
Washington Aqueduct (NAB) 4-22 
Washington Canal and South River, N.J. (NAN) 2-31 
Washington Harbor, D.C. (NAB) 4-10, 4-26, 4-33 
Washington Island, Wis. (NCE) 31-74, 31-75 
Washougal Area Levees, Wash. (NPP) 37-46 
Wassagusset Beach, Weymouth, Mass. (NED) 1-54 
Water Resources Support Center (WRSC) 53-1 
Water Valley, Ark. and Mo. (SWL) 18-17 
Waterbury, Vt. (NAN) 2-35 
Waterbury Reservoir, Vt. (NAN) 2-33 
Waterbury-Watertown, Conn. (NED) 1-26, 1-56, 1-62 
Wateree River, S.C. (SAN) 7-15 
Waterford, N.Y. (NAN) 2-35 
Waterloo, Iowa (NCR) 28-8, 28-11, 28-15 
Waterloo, Nebr. (MRO) 21-17, 21-21 
Waterway Connecting Pamlico Sound and Beaufort 
I-43

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Harbor, S.C. (SAW) 6-8, 6-20, 6-24, 6-29 
Waterway Connecting Port Townsend and Oak Bay, 
Wash. (NPS) 38-24, 38-31 
Waterway Connecting Swanquarter Bay with Deep 
Bay, N.C. (SAW) 6-8, 6-20 
Waterway Connecting Tombigbee and Tennessee 
Rivers, Ala. and Miss. (SAM) 10-11, 10-25, 10-34 
Waterway from Empire, La., to Gulf of Mexico (LMN) 
11-35 
Waterway from Indian River Inlet to Rehobeth Bay, 
Del. (NAP) 3-24 
Waterway from Intracoastal Waterway to Bayou 
Dulac, La. (Bayous Grand Caillou and LeCarpe, La.) 
(LMN) 11-15, 11-23, 11-29 
Waterway from Little Choptank River to Choptank 
River, Md. (NAB) 4-40 
Waterway from White Lake to Pecan Island, Island, 
La. (LMN) 11-35 
Waterway-Norfolk, Va. to Sounds of N.C. (SAW) 6-26 
Waterway on the Coast of Virginia (NAO) 5-11, 5-17, 
5-23, 5-27 
Waterway Experiment Station (WES) 45-1 
Watkins Glen, N.Y. (NCB) 32-36 
Watts Bar Lock and Dam, Tenn. (ORN) 23-17 
Waukegan Harbor, Ill. (NCC) 30-5, 30-10, 30-15, 30-16 
Waurika Lake, Okla. (SWT) 19-12, 19-20, 19-23 
Waverly, W. Va. (ORH) 25-20 
Wax Lake Outlet, La. (MR+T) 42-50 
Waycake Creek, N.J. (NAN) 2-31 
Webb District Improvement Co., Oreg. (NPP) 37-45 
Webbers Falls Lock and Dam, Okla. (SWL) (SWT) 
18-19, 19-16, 19-21, 19-25 
Weber River and Tributaries, Utah (SPK) 35-26 
Weiser River, Weiser Area, Idaho (NPW) 39-19 39-20 
Weldon Fork River, Mo. (MRK) 20-9 
Wellfleet Harbor, Mass. (NED) 1-52 
Wells Harbor, Maine (NED) 1-52 
Wells Harbor, Territory of Guam (POD) 36-14 
Wellsburg, W. Va. (ORP) 26-24 
Wellsville, N.Y. (NCB) 32-34 
Wellsville, Ohio, Sec. I (ORP) 26-23, 26-27 
Wellsville, Ohio, Sec. II (ORP) 26-23, 26-27 
Wenatchee Canyons 1 and 2, Wash. (NPS) 38-28 
West, Herbert G., Lake, Wash. (NPW) 39-7 
West Agurs, La. (LMN) 11-25 
West Atchalayfaya Floodway, La. (MR�T) 42-14 
West Branch Chisholm Creek Channel Improvement, 
Kans. (SWT) 19-24 
West Branch of Susquehanna River, Pa. (NAB) 4-20, 
4-35 
West Branch, Westfield River, Huntington, Mass. 
(NED) 1-20, 1-37, 1-48 
West Bridgewater, Pa. (ORP) 26-24 
West Brookfield Reservoir, Mass. (NED) 1-58 
West Canaan Lake, N.H. (NED) 1-58 
West Fork, W. Va. (ORH) 25-19 
West Fork, Foster Creek, Wash. (NPS) 38-28 
West Fork of Mill Creek Lake, Ohio (ORL) 24-13, 
24-18, 24-28 
West Glendive, Mont. (MRO) 21-20 
West Harbor, Ohio (NCB) 32-10, 32-19 
West Hickman Area, Hickman, Ky. (LMM) 13-5, 13-7, 
13-9 
West Hill Dam, Mass. (NED) 1-15, 1-35 
West Kentucky Tributaries, Ky. (MR+T) 42-10, 42-20, 
42-28, 42-53 
West Magnesia Canyon Channel, Calif. (SPL) 31-27 
West Matanzas Drainage and Levee District, Ill. 
(NCR) 28-19 
West Muddy Creek and Marys River, Oreg. (NPP) 37-49 
West Nishnabotna River, Mills Co. Bridge, near 
Hastings, Iowa (MRO) 21-21 
West Nishnabotna River, Mills Co. Bridge, near 
Malvern, Iowa (MRO) 21-21 
West Nishnabotna River, near Hancock, Iowa (MRO) 
21-21 
West of Morrilton, Arkansas River, Ark. (SWL) 18-16 
West Oneonta Lake, N.Y. (NAB) 4-40 
West Point, Ga. (SAM) 10-39 
West Point, Ky. (ORL) 24-22, 24-25 
West Point, Nebr. (MRO) 21-17, 21-21 
West Point Lake, Ga. and Ala. (SAM) (SAS) 8-10, 
10-21, 10-27, 10-36 
West Richland, Wash. (NPW) 39-21 
West Springfield, Mass. (NED) 1-20, 1-37, 1-48, 1-56, 
1-61 
West Stewartstown, N.H. (NED) 1-29 
West Tennessee Tributaries, Tenn. (MR+T) 42-10, 
42-19, 42-28, 42-53 
West Terre Haute, Ind. (ORL) 24-21, 24-25, 24-30 
West Thompson Lake, Conn. (NED) 1-28, 1-40, 1-64 
West Union, W. Va. (ORH) 25-21 
West Warren, Mass. (NED) 1-29, 1-56, 1-61 
Westchester Creek, N.Y. (NAN) 2-35 
Westcott Cofe, Conn. (NED) 1-52 
Westerly, R.I. (NED) 1-56 
Western Branch, Va. (NAO) 5-22 
Westfield, Mass. (NED) 1-58 
Westhaven Cove Small Boat Basin (Westport Marina), 
Wash. (NPS) 38-24 
Westland District Improvement Co., Oreg. (NPP) 37-45 
Weston, Vt. (NED) 1-29, 1-56, 1-61 
Weston Mills. Olean, N.Y. (ORP) 26-23 
Weston Mills. Portsville, N.Y. (ORP) 26-23 
Westport, Conn. (NED) 1-58 
Westport, Ky. (ORL) 24-23, 24-26 
Westport District, Oreg. (NPP) 37-45 
Westport Harbor and Saugatuck River, Conn. (NED) 
1-52, 1-58 
Westport River, Mass. (NED) 1-52 
Westport Slough, Oreg. (NPP) 37-43, 37-49 
Westville Lake, Mass. (NED) 1-29, 1-40, 1-64 
Wethersfield, Conn. (NED) 1-29 
Weymouth Back River, Mass. (NED) 1-52 
Weymouth-Fore & Town Rivers, Boston Hbr., Mass. 
(ORN) 23-17 
Wheeler, General Joe, Lock and Dam, Ala. (ORN) 23-17 
Wheeler Creek, Gainsville, Tex. (SWF) 16-12, 16-18, 
16-22 
Wheeling, W. Va. (ORP) 26-23, 26-27 
Wheeling, W. Va. (North Wheeling) (ORP) 26-23, 26-28 
Wheeling, W. Va. (Wheeling Island) (ORP) 26-23, 
1-44

INDEX 
26-28 
White Lake Harbor, Mich. (NCE) 31-30, 31-51, 31-70 
White Oak Creek, Ohio (ORH) 25-20 
White Oak Dike, Bladen and Pender Counties, N.C. 
(SAW) 6p2 8 
White Oak River, N.C. (SAW) 6-30 
White River, Ark. (above Peach Orchard Bluff) (SWL) 
18-15 
White River, Ark. (below Newport) (LMM) 13-3, 13-6, 
13-8 
White River, Ind. (ORL) 24-20 
White River Backwater Levees (MR�T) 42-10 
White River Basin (Little Rock District) (SWL) 18-4, 
18-10, 18-14, 18-23 
White River Fish Hatchery, Ark. (SWL) 18-23 
Whitebird Creek, Idaho (NPW) 38-19, 39-20 
Whitefish Point Harbor, Mich. (NCE) 31-75 
Whitesburg, Ky. (ORL) 24-31 
Whitewater River Basin, Calif. (SPL) 33-24 
Whiting, Maine (NED) 1-29 
Whitings Creek, Va. (NAO) 5-25 
Whtilow Ranch Dam, Ariz. (SPL) 33p7, 33-14, 33-18 
Whitmanville Lake, Mass. (NED) 1-56, 1-63 
Whitney Lake, Tex. (SWF) 16-14, 16-18, 16-22 
Whitney Point Lake, N.Y. (NAB) 4-18, 4-28 
Whitney Point Village, N.Y. (NAB) 4-18, 4-28 
Wichita and Valley Center Channel Improvement, 
Kans. (SWT) 19-24 
Wickford Harbor, R.I. (NED) 1-52 
Wicomico River, Md. (NAB) 4-11, 4-26, 4-34 
Wiedmer Chemical Drainage and Levee District, Mo. 
(LMS) 14-15 
Wilcox, Pa. (ORP) 26-24 
Wild Rice and Marsh River, Minn. (NCS) 27-27 
Wild Rice River, Minn. (NCS) 27-17, 27-21, 27-28 
Wild Rice River, South Branch and Felton Ditch, 
Minn. 27-17, 27-21, 27-28 
Wildcat and San Pablo Creeks, Calif. (SPK) 35-24 
Wilders, Ky. (ORL) 24-25 
Wiley Creek Lake, Oreg. (NPP) 37-49 
Wilkes-Barre, Pa. (NAB) 4-38 
Willamette Falls Fishladder, Oreg. (NPP) 37-49 
Willamette River above Portland and Yamhill River, 
Oreg. (NPP) 37-10, 37-28, 37-37 
Willamette River at Willamette Falls, Oreg. (NPP) 
37-11, 37-29, 37-38, 37-50 
Willamette River Basin, Oreg. (NPP) 37-18, 3740, 
37-54 
Willamette River Basin, Oreg.-Bank Protection (NPP) 
37-19, 37-30, 37-40, 37-53 
Willamette River Basin Channel Clearing and Snag 
ging (NPP) 37-46 
Willapa River and Harbor and Naselle River, Wash. 
(NPS) 38-7, 38-15, 38-21 
Willard Beach, South Portland, Me. (NED) 1-14, 1-35, 
1-47 
William H. Harsh Lake, Ohio (ORL) 24-13, 24-18, 
24-28 
William L. Springer Lake, Ill. (NCR) 28-17 
Williamson, W. Va. (ORH) 25-19, 25-21 
Williamsport, Pa. (NAB) 4-38, 4-41 
Williamstown, W. Va. (ORH) 25-20 
Williamsville Reservoir, Vt. (NED) 1-58 
Willoughby Channel. Va. (NAO) 5-25 
Willow Creek, Idaho (NPW) 39-19 
Willow Creek Lake, Heppner, Oreg. (NPW) 39-4, 
39-11, 39-15 
Willow Island Locks and Dam, W. Va. (ORD) 22-1, 
22-7 
Wilmington Harbor, Del. (NAP) 3-10, 3-19, 3-23 
Wilmington Harbor, N.C. (SAW) 6-9, 6-20 
Wilmore, Pa. (ORP) 26-23 
Wilson Branch, Cheraw, S.C. (SAN) 7-7, 7-10, 7-14 
Wilson Harbor, N.Y. (NCB) 32-11, 32-32 
Wilson Lake, Kans. (MRK) 20-8, 20-13, 20-18, 20-23 
Wilson Lock and Dam, Ala. (ORN) 23-17 
Wilson Point Harbor, Conn. (NED) 1-52 
Wilson River, Oreg. (NPD) 37-47 
Wilton, N.H. (NED) 1-29 
Winchester Bay, Oreg. (NPP) 37-11, 37-29, 37-38 
Winfield Levee, Kans. (SWT) 19-24 
Winfield Levee Modification, Kans. (SWT) 19-24 
Winnibigoshish Reservoir, Minn. (NCS) 27-26 
Winnipesaukee Lake, N.H. (NED) 1-52 
Winona, Minn. (NCS) 27-17, 27-21, 27-28 
Winooski River, Vt. (NAN) 2-33 
Winslow (Tributaries of Little Colorado River), Ariz. 
(SPL) 33-24 
Winsted, Conn. (NED) 1-29, 1-56, 1-61 
Winter Harbor, Maine (NED) 1-52 
Winter Harbor, Va. (NAO) 5-25 
Winthrop Beach, Mass. (NED) 1-54 
Winthrop Harbor, Va. (NAO) 1-52 
Wisconsin River, Wis. (NCS) 27-23 
Wishart Point Channel, Va. (NAO) 5-25 
Wister Lake, Okla. (SWL) (SWT) 18-21, 19-13, 19-21, 
19-25 
Withlacoochee River, Fla. (SAJ) 9-50 
Wolf and Jordan Rivers, Miss. (SAM) 10-37, 10-38 
Wolf-Coffee Lake, Kans. (MRK) 20-19 
Wolf Creek Dam-Lake Cumberland, Ohio River Basin, 
Ky. (ORN) 23-8, 23-10 
Wolf River (Memphis Harbor), Tenn. (LMM) 13-3, 
13-6, 13-8 
Wood Island Harbor, Maine (NED) 1-52 
Wood River Drainage and Levee District, Ill. (LMS) 
14-7, 14-10, 14-12 
Woodbridge Creek, N.J. (NAN) 2-31 
Woodbury Creek, N.J. (NAP) 3-24 
Woodcock Creek Lake, Pa. (ORP) 26-11, 26-16, 26-21 
Woodland St. Bridge, Tenn. (ORN) 23-4 
Woodlands, W. Va. (ORP) 26-23, 26-28 
Woodmont Shore, Milford, Conn. (NED) 1-54 
Woodruff, Jim, Lock and Dam, Ga. and Fla. (SAM) 
10-20, 10-27, 10-36 
Woods Hole Channel, Mass. (NED) 1-52 
Woodson Drainage District, Oreg. (NPP) 37-45, 37-46, 
37-52 
Woonsocket, R.I. (NED) 1-26, 1-56, 1-59 
Worcester, Mass. (NED) 1-27, 1-56, 1-59 
Wrangell Harbor, Alaska (NPA) 40-12 
Wrangell Narrows, Alaska (NPA) 40-12 
I-45

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1983 
Wright Patman Dam and Lake, Tex. (LMN) (SWF) 
11-37, 16-13, 16-18, 16-22 
Wright's Creek, N.C. (SAW) 6-26, 6-30 
Wrightsville Beach, N.C. (SAW) 6-15, 6-21 
Wrightsville Dam, Vt. (NAN) 2-33 
Wynoochee Lake, Wash. (NPS) 38-10, 38-16, 38-22 
Wynoochee River, Wash. (NPS) 38-28, 38-29 
Wyoming Valley, Pa. (NAB) 4-20, 4-29, 4-35 
Y 
Yadkin River Basin, N.C. & S.C. (SAW) 6-15, 6-31 
Yakima, Wash. (NPS) 38-29 
Yakima River, Cle Elum, Wash. (NPS) 38-29 
Yakima River, West Richlamd, Wash. (NPS) (NPW) 
38-29, 39-19 
Yakima River, Yakima, Wash. (NPS) 38-10, 38-16, 
38-22, 38-29 
Yalobusha River, Miss. (LMR) 12-21 
Yaquina Bay and Harbor, Oreg. (NPP) 37-11, 37-29, 
37-38 
Yaquina Bay and Harbor Small Boat Basin, Oreg. 
(NPP) 37-43 
Yaquina River, Oreg. (NPP) 37-12, 37-29, 37-39, 37-43 
Yatesville Lake Ky. (ORH) 25-9, 25-14, 25-17 
Yazoo River, Miss. (LMK) 12-5, 12-14, 12-17 
Yazoo River Backwater Area (MR+T) 42-51 
Yazoo River Basin, Miss. (MR+T) 42-8, 42-17, 42-28, 
42-46 
Yazoo River Basin Project Levees (MR+T) 42-46 
Yellow Jacket Creek, Hogansville, Ga. (SAM) 10-39 
Yellowstone River, Bank Protection, Billings, Mont. 
(MRO) 21-20 
Yellowstone River, Greycliff Bridge, Mont. (MRO) 
21-20 
Yellowstone River, near Miles City, Mont., Water Intake 
and Sewage Lagoon (MRO) 21-20 
Yellowstone River, Reedpoint Bridge, Mont. (MRO) 
21-20 
Yellowstone River, Springdale Bridge, Mont. (MRO) 
21-20 
Yellowstone River, Vogue Bridge, near Big Timber, 
Mont. (MRO) 21-20 
Yellowstone River, W. Glendive, Mont. (MRO) 21-17, 
21-20 
Yellowstone River, Water Plant, Livingston, Mont. 
(MRO) 21-20 
Yellowstone River, Yellowstone Co. Bridge, near 
Billings, Mont. (MRO) 21-20 
Yonkers, N.Y. (NAN) 2-18, 2-23, 2-28, 2-36 
York, Pa. (NAB) 4-21, 4-29, 4-35 
York Harbor, Maine (NED) 1-52 
York River, Va. (NAO) 5-25, 5-27 
York Spit Channel, Va. (NAO) 5-3, 5-19 
Youghiogheny River, Pa. and Md. (ORP) 26-22 
Youghiogheny River Lake, Pa. and Md. (ORP) 26-12, 
26-16, 26-21 
Youngs and Klaskanine River, Oreg. (NPP) 37-43 
Youngs Bay and Youngs River, Oreg. (NPP) 37-43 
Youngs River Dikes, Oreg. (NPP) 37-45 
Youngstown, Ohio (ORP) 26-23 
Z 
Zacate Creek Channel Improvement, Tex. (SWF) 
16-13, 16-18, 16-22 
Zanesville, Ohio (ORH) 25-20 
Zintel Canyon Dam, Wash. (NPW) 39-4, 39-11, 39-15 
Zippel Bay, Minn. (NCS) 27-27 
Zippel Bay Harbor, Minn. (NCS) 27-23 
Zumbro River, Minn. (NCS) 27-24, 27-28 
,U.8. GOVERNMENT PRINTING OFFICE: 19 84 445 9 57. 1 86 88 
- - - - -I- - - - I 
v
30: 
aa
z
N
to 
V
W 
v
vC 
ri' 
0
0 
I-46

DIVISIONS AND DISTRICTS FOR CIVIL WORKS ACTIVITIES 
NORTH PACIFIC 
NORTH CENTRAL 
C
'~ ' d at"
r- - 
'<i mm 
SOUTH PA( 
SOUTHWESTERN / NEW ORLEANS 
The Alaska District Headquarters, GALVESTON LOWER 
Anchorage, Alaska, is included in MISSISSIPPI 
the North Pacific Division. MISSISSIPPI 
VALLEY 
The State of Hawaii and Islands in 
the Pacific are included in Pacific 
Ocean Division, with Headquarters 
at Honolulu, Hawaii 
Puerto Rico and the 
Virgin Islands are included 
in Jacksonville District, South 
Atlantic Division. 
- DISTRICT BOUNDARIES 
SDIVISION HEADQUARTERS 
DISTRICT HEADQUARTERS SDIVISION AND DISTRICT HEADQUARTERS 
d '-' 
mm N 
E-.0 
'ri 
mm
f r 
{Q a
3B 
0
i1 
'O

3 136~4 000160U1 4-

